This document outlines regulations for forecasting, scheduling, and deviation settlement related to solar and wind power generation sources in Gujarat, India. Key points:
- The regulations apply to all wind and solar generators over 1 MW connected to the state grid and selling power within or outside the state.
- Generators/qualified coordinating agencies must provide day-ahead and week-ahead forecasts and are allowed to revise schedules intraday. Forecasts and schedules are submitted to the state load dispatch center.
- Deviations from schedules will result in commercial impacts that are borne by the generators. Qualified coordinating agencies can represent generators and be responsible for deviation charges.
- The regulations establish definitions, objectives, roles