2. AIMS & OBJECTIVES
• Identify the various stages in
Project Cycle Management (PCM)
• Outline where and how participatory
approaches can be applied to PCM
• List some of the major problems in
Project Cycle Management
3. WHAT IS PROJECT CYCLE
MANAGEMENT (PCM)?
• Projects are the primary means through
which development plans and policies are
translated into programmes of action.
• Due to the methodological advances that
were made in the 1960’s and 1970’s PCM
obtained standard form to facilitate
project management.
5. Programming
Purpose To establish an overall strategy in relation
to local, national and international context
To Agree on broad framework on long term
objectives and sector priorities for co-
operation in the country/region or sector
Stakeholder
involvement
High level political decision makers and the
co-operating institution/ agency
Steps General analysis of the current situation
and future prospects
Analysis of national priorities
Review of previous collaboration
Complementary action with other actors
Strategic choices in collaboration with
other stakeholders
Product Strategy paper
6. Identification
Purpose Identification and selection of relevant
areas of intervention and project ideas for
further studies
Stakeholder
involvement
Senior officials of the co-operating
institution and from line ministries of the
partner countries, consultants
Steps Collect and evaluate information on areas
of intervention
Review/include lessons learned from
previous experiences
Product Brief project descriptions that will be
further developed and TOR for formulation
7. Formulation
Purpose A well defined and formulated project
according to the criteria of relevance,
feasibility and sustainability
Stakeholder
involvement
Project formulation mission involving all
stakeholders
Steps Conduct a feasibility study
Involve the different stakeholders
Define implementation arrangements
Elaborate solutions and achieve agreement
on the project approach with all stakeholders
Product A sound project document (meeting the
quality criteria) that is the basis for a
financing proposal
8. Financing
Purpose Financing agreement and commitment for
project resources
Stakeholder
involvement
Internal and relevant committee
Steps Preparation of the financing proposal
Examination of the proposal
Financing decision
Product Signed financing agreement
9. Implementation
Purpose Implementing the project towards its
objectives
Stakeholder
involvement
Project implementation team, counterpart
institution, beneficiaries and eventually
external monitoring
Steps Tendering and contract award
Detailed work plan
Executing activities
Adapting project activities
Ongoing monitoring and mid-term evaluation
Documents E.g. project monitoring reports, annual
reports
10. Evaluation
Purpose Accountability and formulation of lessons
learned
Conclusions for programming and future
action
Stakeholder
involvement
External neutral party and all relevant
stakeholders
Steps Terms of reference for the evaluation
(questions to be asked)
Organise evaluation exercise with
appropriate methods
Analyse relevance, efficiency,
effectiveness, impact, and sustainability
Draw lessons from experiences
Provide recommendations
Product
12. Application of Participatory
Techniques to the Project Cycle
• At the Identification stage, by involving
people in identifying problems through use
objective trees, SWOT analysis, priority
setting, situation analysis, needs
assessments, feasibility studies, etc.
13. Application of Participatory
Techniques to the Project Cycle
• At the Implementation stage, through
examination of a particular problem and
being involved in decision making and on
going monitoring of the projects
• At the Monitoring and Evaluation stages,
by enabling participants to implement
procedures to examine their own activities
and judge the impact of the project.
14. Problems in PCM
• The Nature of Development Problems
– the complexity and challenges of development problems
are such that they cannot be characterised as ‘well
structured’ development problems, as project planning
methodologies would assume.
– problems and solutions cannot be thought through in
advance but it is necessary for these to evolve as the
project progresses.
15. Problems in PCM…
• Poor Data
– Many project planning methodologies are dependent on
large amounts of reliable data that is often not available.
– In these case planners have often made assumptions,
which have often been over optimistic about items such
as costs involved, potential for increasing yield, potential
for changing behaviour or adapting new technologies, etc.
16. Problems in PCM…
• Uncertainty
– Many project environments are characterised by
uncertainty and instability. However, there is a
tendency not to make allowances in the projects
for the impact of such factors such as a drought,
changes in domestic or world prices, civil unrest.
17. Problems in PCM…
• Separation of Project Planning and Management
– A disconnection between those who design projects
and implement them enables participants to avoid
taking responsibility for project outcomes.
• “The project design was fine but it was implemented badly” or
“It was so badly designed there was little that could be done
with it”.
18. Problems in PCM…
• Lack of Beneficiary Participation
– The failure to involve beneficiaries in all stages
of project design, management and monitoring
has often undermined ownership and alienated
people from projects.
19. Problems in PCM…
• Projects and Politics
– Planning methodologies often ignore political factors.
They tend to ignore the fact that projects are designed,
selected and implemented by people working in social
contexts.
– By ignoring such a reality it reduces the opportunity for
the intended beneficiaries (usually the powerless/
marginalized) to gain influence over the project process.
20. Problems in PCM…
• the little attention paid to critical role of
the ‘Human Factor’ in project cycle
management. In essence successful
application of PCM and its associated
methodologies, tools and techniques are
dependent on the vision, values and capacity
of the people and institutions that apply
them.