Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13 Harmal RMS-2 Construction & 16" DSS Pipeline to KGP Phase 1 & Phase 2 - FinalHarmal FD-10-Oct13 Harmal RMS-2 Construction & 16" D... 776 09-Dec-12 28-Jan-15 0
Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1 625 09-Dec-12 30-Aug-14 36
Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1 625 09-Dec-12 30-Aug-14 36
Harmal FD-10-Oct13.3.1.11.1.1.2 AFC PackageHarmal FD-10-Oct13.3.1.11.1.1.2 AFC Package 286 09-Dec-12 25-Sep-13 140
D100 Electrical 200 05-Jan-13 10-Sep-13 28
D100A Electrical-OHL 238 05-Jan-13 31-Aug-13 165
D110 Control and automation 215 01-Jan-13 25-Sep-13 28
D120 Pipeline 237 06-Jan-13 31-Aug-13 71
D70 Civil 145 27-Jan-13 27-Jul-13 53
D80 Mechanical and Piping 142 24-Dec-12 18-Jun-13 28
D90 Process 225 09-Dec-12 14-Sep-13 0
Harmal FD-10-Oct13.3.1.11.1 Bulk MTOHarmal FD-10-Oct13.3.1.11.1 Bulk MTO 172 30-Jan-13 21-Jul-13 50
A3110 Mechanical and Piping 170 30-Jan-13 19-Jul-13 37
A3120 Civil and Structural 165 01-Feb-13 16-Jul-13 50
A3130 Electrical 165 06-Feb-13 21-Jul-13 50
A3140 Control and Automation 162 06-Feb-13 18-Jul-13 50
Harmal FD-10-Oct13.3.1.11.2 Project Management and Support DocumentsHarmal FD-10-Oct13.3.1.11.2 Project Management and Support Documents 625 09-Dec-12 30-Aug-14 36
A3150 Project Management 600 09-Dec-12 05-Aug-14 41
A3160 Project Support & As Built Completion 339 25-Sep-13 30-Aug-14 36
A3270 SAP Management 319 25-Sep-13 10-Aug-14 36
A3280 CCMS 319 25-Sep-13 10-Aug-14 36
Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1 487 13-Jan-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 ConstructionHarmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 Construction 487 13-Jan-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1.2 MechanicalHarmal FD-10-Oct13.3.1.2.1.2 Mechanical 474 13-Jan-13 02-May-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS PipesHarmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS Pipes 367 13-Jan-13 15-Jan-14 47
357 PR Issue 1 13-Jan-13 14-Jan-13 47
358 Enquiry Floating 7 14-Jan-13 21-Jan-13 47
359 Receive quotes from Vendors 7 22-Jan-13 29-Jan-13 47
360 Technical Bid Evaluation 14 30-Jan-13 13-Feb-13 47
361 Vendor Data and complete commercial 10 14-Feb-13 24-Feb-13 47
362 Issue of PO 2 25-Feb-13 27-Feb-13 47
363 Manufacturing of Pipes & Coating 286 28-Feb-13 11-Dec-13 47
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
364 Inspection, Rlease & Shipment 150 29-Jul-13 26-Dec-13 47
365 Pipe Receipt at Site 125 12-Sep-13 15-Jan-14 47
Harmal FD-10-Oct13.3.1.2.1.2.1.2.3 FlangesHarmal FD-10-Oct13.3.1.2.1.2.1.2.3 Flanges 283 30-Mar-13 07-Jan-14 67
375 PR Issue 2 30-Mar-13 01-Apr-13 67
376 Enquiry Floating 7 02-Apr-13 09-Apr-13 67
377 Receive quotes from Vendors 21 09-Apr-13 30-Apr-13 67
378 Technical Bid Evaluation 15 30-Apr-13 15-May-13 67
379 Vendor Data and complete commercial 5 15-May-13 20-May-13 67
380 Issue of PO 7 21-May-13 28-May-13 67
381 Manufacturing process at Vendor Yard 145 28-May-13 20-Oct-13 67
382 Shipping Delivery 34 20-Oct-13 23-Nov-13 67
383 Flange Receipt at site 45 23-Nov-13 07-Jan-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ SpoolsHarmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ Spools 322 31-Mar-13 16-Feb-14 76
402 PR Issue 2 31-Mar-13 02-Apr-13 76
403 Enquiry Floating 11 03-Apr-13 14-Apr-13 76
404 Receive quotes from Vendors 14 15-Apr-13 29-Apr-13 76
405 Technical Bid Evaluation 30 30-Apr-13 30-May-13 76
406 Vendor Data and complete commercial 10 31-May-13 10-Jun-13 76
407 Issue of PO 6 11-Jun-13 17-Jun-13 76
408 Manufacturing of Items 185 18-Jun-13 20-Dec-13 76
409 Shipping Delivery 40 21-Dec-13 30-Jan-14 76
410 IJ Spool Receipt at Site 10 06-Feb-14 16-Feb-14 76
Harmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred TeeHarmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred Tee 316 01-Apr-13 11-Feb-14 138
411 PR Issue 2 01-Apr-13 03-Apr-13 138
412 Enquiry Floating 7 03-Apr-13 10-Apr-13 138
413 Receive quotes from Vendors 14 10-Apr-13 24-Apr-13 138
414 Technical Bid Evaluation 30 24-Apr-13 24-May-13 138
415 Vendor Data and complete commercial 14 24-May-13 07-Jun-13 138
416 Issue of PO 2 07-Jun-13 09-Jun-13 138
417 Manufacturing of Items 190 09-Jun-13 16-Dec-13 138
418 Shipping Delivery 20 16-Dec-13 05-Jan-14 138
419 Barred TEE Receipt at Site 30 12-Jan-14 11-Feb-14 138
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeveHarmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeve 210 15-Apr-13 11-Nov-13 85
420 PR Issue 2 15-Apr-13 17-Apr-13 85
421 Enquiry Floating 11 17-Apr-13 28-Apr-13 85
422 Receive quotes from Vendors 14 28-Apr-13 12-May-13 85
423 TBE & Vendor Finilize 30 12-May-13 11-Jun-13 85
424 Issue of PO 2 11-Jun-13 13-Jun-13 85
425 Manufacturing of Items 100 13-Jun-13 21-Sep-13 85
426 Inspection & Release 4 21-Sep-13 25-Sep-13 85
427 Material Delivery 20 25-Sep-13 15-Oct-13 85
428 Shrink Sleeve Receipt at Site 20 22-Oct-13 11-Nov-13 85
Harmal FD-10-Oct13.3.1.2.1.2.2 Vent StackHarmal FD-10-Oct13.3.1.2.1.2.2 Vent Stack 383 14-Apr-13 02-May-14 67
A1360 PR Issue 6 14-Apr-13 20-Apr-13 67
A1370 Enquiry Floating 14 20-Apr-13 04-May-13 67
A1380 Receive quotes from Vendors 145 04-May-13 26-Sep-13 67
A1390 TBE & Vendor Finilize 140 19-May-13 06-Oct-13 67
A1400 Issue of PO 2 06-Oct-13 08-Oct-13 67
A1410 Manufacturing of Items 120 08-Oct-13 05-Feb-14 67
A1420 FAT, Final Inspection & Release 30 05-Feb-14 07-Mar-14 67
A1430 Material Delivery 20 07-Mar-14 27-Mar-14 67
A1431 Vent Stack Receipt at Site 26 06-Apr-14 02-May-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.2.1 Bulk Materials 298 30-Apr-13 22-Feb-14 37
1529 PR Issue 30 30-Apr-13 30-May-13 37
1539 Enquiry Floating 90 30-May-13 28-Aug-13 37
1549 Receive quotes from Vendors 100 04-Jun-13 12-Sep-13 37
1569 Vendor Data and complete commercial 75 09-Jul-13 22-Sep-13 37
1579 Issue of PO 30 23-Sep-13 23-Oct-13 37
1589 Manufacturing of Materials 110 13-Oct-13 31-Jan-14 37
1599 Shipping Delivery 110 02-Nov-13 20-Feb-14 37
1609 Fittings Receipt at site( 106 08-Nov-13 22-Feb-14 37
Harmal FD-10-Oct13.3.1.2.1.2.4 Internal ClampsHarmal FD-10-Oct13.3.1.2.1.2.4 Internal Clamps 151 27-Apr-13 25-Sep-13 79
A2330 PR Issue 6 27-Apr-13 03-May-13 79
A2340 Enquiry Floating 14 03-May-13 17-May-13 79
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2350 Recieve quotes from Vendors 21 17-May-13 07-Jun-13 79
A2360 Vendor Data and complete commercial 7 07-Jun-13 14-Jun-13 79
A2370 Issue of PO 2 15-Jun-13 17-Jun-13 79
A2380 Maufacturing of mateirals 70 18-Jun-13 27-Aug-13 79
A2390 Shipping Delivery 10 28-Aug-13 17-Sep-13 79
A2400 Reciept at site 7 18-Sep-13 25-Sep-13 79
Harmal FD-10-Oct13.3.1.2.1.3 ElectricalHarmal FD-10-Oct13.3.1.2.1.3 Electrical 361 08-May-13 04-May-14 63
Harmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSBHarmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSB 224 26-Jun-13 05-Feb-14 136
A1200 PR Issue 2 26-Jun-13 28-Jun-13 136
A1210 Enquiry Floating 14 28-Jun-13 12-Jul-13 136
A1220 Receive quotes from Vendor 7 12-Jul-13 19-Jul-13 136
A1230 TBE & Vendor Finilze 62 19-Jul-13 19-Sep-13 136
A1240 Issue of PO 2 19-Sep-13 21-Sep-13 136
A1250 Manufacturing of Material 90 21-Sep-13 20-Dec-13 136
A1260 Inspection & Release 20 20-Dec-13 09-Jan-14 136
A1270 Material Delivery 20 16-Jan-14 05-Feb-14 136
Harmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical TransformerHarmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical Transformer 345 08-May-13 18-Apr-14 61
448 PR Issue 2 08-May-13 10-May-13 61
449 Enquiry Floating 14 10-May-13 24-May-13 61
450 Receive quotes from Vendors 120 20-May-13 17-Sep-13 61
451 Technical Bid Evaluation & Vendor Finalize 120 30-May-13 27-Sep-13 61
452 Vendor Data and complete commercial 12 27-Sep-13 09-Oct-13 61
453 Issue of PO 9 09-Oct-13 18-Oct-13 61
454 Manufacturing of Items 125 18-Oct-13 20-Feb-14 61
455 FAT, Final Inspection & Release 30 20-Feb-14 22-Mar-14 61
456 Delivery at Site 20 29-Mar-14 18-Apr-14 61
Harmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DB 259 25-Jun-13 11-Mar-14 117
458 PR Issue 6 25-Jun-13 01-Jul-13 117
459 Enquiry Floating 21 01-Jul-13 22-Jul-13 117
460 Receive quotes from Vendors 15 22-Jul-13 06-Aug-13 117
461 Vendor Finilize 55 06-Aug-13 30-Sep-13 117
462 Issue of PO 10 30-Sep-13 10-Oct-13 117
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
463 Manufacturing of Items 100 10-Oct-13 18-Jan-14 117
464 FAT, Final Inspection & Release 15 18-Jan-14 02-Feb-14 117
465 Material Delivery 30 09-Feb-14 11-Mar-14 117
Harmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materialsHarmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materials 213 25-Jun-13 24-Jan-14 137
477 PR Issue 6 25-Jun-13 01-Jul-13 137
478 Enquiry Floating 6 01-Jul-13 07-Jul-13 137
479 Receive quotes from Vendors 12 07-Jul-13 19-Jul-13 137
480 Vendor Finilize 15 19-Jul-13 03-Aug-13 137
481 Issue of PO 4 03-Aug-13 07-Aug-13 137
482 Manufacturing of Items 140 07-Aug-13 25-Dec-13 137
483 Material Delivery 20 04-Jan-14 24-Jan-14 137
Harmal FD-10-Oct13.3.1.2.1.3.2 Containerized SubstationHarmal FD-10-Oct13.3.1.2.1.3.2 Containerized Substation 313 25-Jun-13 04-May-14 50
A1520 PR Issue 2 25-Jun-13 27-Jun-13 50
A1530 Enquiry Floating 7 27-Jun-13 04-Jul-13 50
A1540 Receive quotes from Vendors 90 04-Jul-13 02-Oct-13 50
A1550 Technical Bid Evaluation 15 02-Oct-13 17-Oct-13 50
A1560 Vendor Data and complete commercial 10 17-Oct-13 27-Oct-13 50
A1570 Issue of PO 6 27-Oct-13 02-Nov-13 50
A1580 Manufacturing of Items 150 02-Nov-13 01-Apr-14 50
A1590 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 50
A1600 Material Delivery 15 19-Apr-14 04-May-14 50
Harmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DB 296 25-Jun-13 17-Apr-14 75
467 PR Issue 7 25-Jun-13 02-Jul-13 75
468 Enquiry Floating 21 02-Jul-13 23-Jul-13 75
469 Receive quotes from Vendors 60 23-Jul-13 21-Sep-13 75
470 Technical Bid Evaluation 15 21-Sep-13 06-Oct-13 75
471 Vendor Data and complete commercial 15 06-Oct-13 21-Oct-13 75
472 Issue of PO 6 21-Oct-13 27-Oct-13 75
473 Manufacturing of Items 130 27-Oct-13 06-Mar-14 75
474 FAT, Final Inspection & Release 15 06-Mar-14 21-Mar-14 75
475 Material Delivery 20 28-Mar-14 17-Apr-14 75
Harmal FD-10-Oct13.3.1.2.1.3.3 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.3.3 Bulk Materials 193 24-Aug-13 05-Mar-14 112
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
1709 PR Issue 6 24-Aug-13 30-Aug-13 112
1719 Enquiry Floating 6 30-Aug-13 05-Sep-13 112
1729 Receive quotes from Vendors 25 05-Sep-13 30-Sep-13 112
1739 Vendor Finilize 30 30-Sep-13 30-Oct-13 112
1749 Issue of PO 6 30-Oct-13 05-Nov-13 112
1759 Manufacturing of Items 90 05-Nov-13 03-Feb-14 112
1769 Material Delivery 20 13-Feb-14 05-Mar-14 112
Harmal FD-10-Oct13.3.1.2.1.4 InstrumentationHarmal FD-10-Oct13.3.1.2.1.4 Instrumentation 396 14-Apr-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS systemHarmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS system 329 16-Jun-13 11-May-14 51
438 PR Issue 2 16-Jun-13 18-Jun-13 51
439 Enquiry Floating 7 18-Jun-13 25-Jun-13 51
440 Receive quotes from Vendors 130 25-Jun-13 02-Nov-13 51
441 Technical Bid Evaluation 10 02-Nov-13 12-Nov-13 51
442 Vendor Data and complete commercial 10 12-Nov-13 22-Nov-13 51
443 Issue of PO 10 22-Nov-13 02-Dec-13 51
444 Manufacturing of Items 120 02-Dec-13 01-Apr-14 51
445 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 51
446 Material Delivery 20 21-Apr-14 11-May-14 51
Harmal FD-10-Oct13.3.1.2.1.4.4 GaugeHarmal FD-10-Oct13.3.1.2.1.4.4 Gauge 369 14-Apr-13 18-Apr-14 81
889 PR Issue 2 14-Apr-13 16-Apr-13 81
899 Enquiry Floating 14 17-Apr-13 01-May-13 81
909 Receive quotes from Vendors 160 02-May-13 09-Oct-13 81
919 Technical Bid Evaluation 20 11-Oct-13 31-Oct-13 81
929 Vendor Data and complete commercial 20 01-Nov-13 21-Nov-13 81
939 Issue of PO 2 22-Nov-13 24-Nov-13 81
949 Manufacturing of Items 120 04-Dec-13 03-Apr-14 81
959 Material Delivery 10 08-Apr-14 18-Apr-14 81
Harmal FD-10-Oct13.3.1.2.1.4.7 TransmittersHarmal FD-10-Oct13.3.1.2.1.4.7 Transmitters 315 21-May-13 01-Apr-14 98
1129 PR Issue 30 21-May-13 20-Jun-13 98
1139 Enquiry Floating 140 20-Jun-13 07-Nov-13 98
1149 Receive quotes from Vendors 140 30-Jun-13 17-Nov-13 98
1159 Technical Bid Evaluation 140 10-Jul-13 27-Nov-13 98
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
1169 Vendor Data and complete commercial 140 20-Jul-13 07-Dec-13 98
1179 Issue of PO 6 09-Aug-13 08-Oct-13 98
1189 Manufacturing of Items 150 08-Oct-13 07-Mar-14 98
1199 Material Delivery 20 12-Mar-14 01-Apr-14 98
Harmal FD-10-Oct13.3.1.2.1.4.10 F&G SystemsHarmal FD-10-Oct13.3.1.2.1.4.10 F&G Systems 321 05-May-13 22-Mar-14 108
1289 PR Issue 2 05-May-13 07-May-13 108
1299 Enquiry Floating 7 07-May-13 14-May-13 108
1309 Receive quotes from Vendors 150 22-May-13 19-Oct-13 108
1319 Technical Bid Evaluation 146 06-Jun-13 30-Oct-13 108
1329 Vendor Data and complete commercial 25 10-Oct-13 04-Nov-13 108
1339 Issue of PO 3 04-Nov-13 07-Nov-13 108
1349 Manufacturing of Items 110 07-Nov-13 25-Feb-14 108
1359 Material Delivery 20 02-Mar-14 22-Mar-14 108
Harmal FD-10-Oct13.3.1.2.1.4.13 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.4.13 Bulk Materials 360 20-May-13 15-May-14 66
1619 PR Issue 2 28-May-13 30-May-13 66
1629 Enquiry Floating 140 30-May-13 17-Oct-13 66
1639 Receive quotes from Vendors 160 20-May-13 27-Oct-13 66
1659 Vendor Data and complete commercial 15 22-Oct-13 06-Nov-13 66
1669 Issue of PO 140 16-Nov-13 05-Apr-14 66
1679 Manufacturing of Items 150 26-Nov-13 25-Apr-14 66
1699 Material Delivery 20 25-Apr-14 15-May-14 66
Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1 605 09-Dec-12 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km)Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km) 349 26-Aug-13 10-Aug-14 44
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil Works 349 26-Aug-13 10-Aug-14 44
PL C1000 Route Survey and Peg Marking 30 26-Aug-13 25-Sep-13 35
PL C1010 Right of Way Preparation 30 31-Aug-13 30-Sep-13 35
PL C1020 Excavation of Trench 80 24-Nov-13 12-Feb-14 44
PL C1030 Prepadding of sand for Pipeline 70 27-Nov-13 05-Feb-14 44
PL C1040 Post Padding after Laying of Pipeline 45 17-Apr-14 01-Jun-14 44
PL C1050 Back filling of Trench 80 18-Mar-14 06-Jun-14 44
PL C1060 Construction of Windrow 31 08-Jul-14 08-Aug-14 44
PL C1070 Final Grading for the ROW & Marker plate 30 11-Jul-14 10-Aug-14 44
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical Works 287 24-Sep-13 08-Jul-14 44
PL M1000 Stringing of Pipes 120 24-Sep-13 22-Jan-14 47
PL M1020 Straight Welding 180 20-Oct-13 18-Apr-14 47
PL M1030 NDT and repair if any 170 04-Nov-13 23-Apr-14 47
PL M1040 Sleeve Installation 150 29-Nov-13 28-Apr-14 47
PL M1050 Lowering of Pipes 150 09-Dec-13 08-May-14 44
PL M1060 Tie-in Welding 150 16-Dec-13 15-May-14 44
PL M1070 Barred Tee Welding 4 26-Apr-14 30-Apr-14 64
PL M1080 IJ Spool Installation 8 27-Apr-14 05-May-14 56
PL M1090 NDT and Repair if any 80 01-Mar-14 20-May-14 44
PL M1100 Sleeve Installation 75 13-Mar-14 27-May-14 44
PL M1110 Line Completion and Clearence 5 03-Jun-14 08-Jun-14 44
PL M1120 Hydrotesting 30 08-Jun-14 08-Jul-14 44
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC Works 103 09-Apr-14 21-Jul-14 54
PL FOC1000 HDPE Duct Laying 60 09-Apr-14 08-Jun-14 67
PL FOC1010 Post Padding & Backfilling 50 22-Apr-14 11-Jun-14 80
PL FOC1020 FO Cable Blowing 7 08-Jul-14 15-Jul-14 54
PL FOC1030 FO Jointing & Splicing 5 16-Jul-14 21-Jul-14 54
Harmal FD-10-Oct13.3.4.2 Cathodic Protection WorksHarmal FD-10-Oct13.3.4.2 Cathodic Protection Works 597 09-Dec-12 02-Aug-14 44
Harmal FD-10-Oct13.3.4.2.1 Design WorksHarmal FD-10-Oct13.3.4.2.1 Design Works 45 09-Dec-12 27-Jan-13 192
PL CP1000 Design Preparation, Submission & Approval 45 09-Dec-12 27-Jan-13 192
Harmal FD-10-Oct13.3.4.2.4 ProcurementHarmal FD-10-Oct13.3.4.2.4 Procurement 365 29-Jan-13 29-Jan-14 192
A2280 CP Transformer Manufacturing 250 29-Jan-13 06-Oct-13 192
A2290 FAT & Documentation and Release 100 07-Oct-13 21-Dec-13 192
A2300 CP Transformer Receipt 31 29-Dec-13 29-Jan-14 192
Harmal FD-10-Oct13.3.4.2.2 Temporary CP InstallationHarmal FD-10-Oct13.3.4.2.2 Temporary CP Installation 75 09-Mar-14 23-May-14 58
PL CP1010 Temp.CP Installation for Pipeline 75 09-Mar-14 23-May-14 58
Harmal FD-10-Oct13.3.4.2.3 Permanent CP InstallationHarmal FD-10-Oct13.3.4.2.3 Permanent CP Installation 57 06-Jun-14 02-Aug-14 44
PL CP1020 Ground Bed Installation 15 06-Jun-14 21-Jun-14 44
PL CP1030 Anode JB Installation 3 19-Jun-14 22-Jun-14 46
PL CP1040 NDB Installation 2 22-Jun-14 24-Jun-14 46
PL CP1080 CP Tranformer Installation 1 26-Jun-14 27-Jun-14 44
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
PL CP1100 Trenching, Cable laying, Backfilling 7 26-Jun-14 03-Jul-14 44
PL CP1110 CP Cable Termination 5 03-Jul-14 08-Jul-14 44
PL CP1120 DCVG Survey 10 11-Jun-14 21-Jun-14 60
PL CP1140 Pre-Commissioning activity 10 08-Jul-14 18-Jul-14 44
PL CP1150 Final Commissioning 15 18-Jul-14 02-Aug-14 44
PL CP1160 CP System CIPS Survey 10 18-Jul-14 28-Jul-14 49
Harmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction workHarmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction work 339 05-Sep-13 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil Works 339 05-Sep-13 10-Aug-14 45
RMS C101 Plot Survey and set out 50 05-Sep-13 25-Oct-13 35
RMS C102 Land Filling and Access Road Preparation 45 09-Nov-13 24-Dec-13 35
RMS C103 Precasting for Foundation 45 25-Oct-13 09-Dec-13 50
RMS C104 Fencing and Gate Instalaltion 25 19-Nov-13 14-Dec-13 35
RMS C105 Marking and Excavation of the Foundation 20 24-Nov-13 14-Dec-13 36
RMS C106 PCC for Foundation 20 01-Dec-13 21-Dec-13 36
RMS C107 Foundation Installation 30 08-Dec-13 07-Jan-14 36
RMS C108 Foundation Backfilling & Compacting 35 12-May-14 16-Jun-14 36
RMS C109 Cable Trench Excavation 15 16-Jun-14 01-Jul-14 39
RMS C110 Cable Trench Backfilling 10 12-Jul-14 22-Jul-14 45
RMS C111 Grouting, Final Grading & House Keeping 19 22-Jul-14 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical Works 211 22-Nov-13 21-Jun-14 67
RMS M101 Prefabrication of Spools 105 22-Nov-13 07-Mar-14 37
RMS M102 NDT and Repair if any 90 22-Dec-13 22-Mar-14 52
RMS M103 Structure Support Fabrication & Coating 105 22-Nov-13 07-Mar-14 37
RMS M104 Suppot Erection 80 07-Jan-14 28-Mar-14 36
RMS M105 Piping Erection, Welding & Tie In 75 14-Jan-14 30-Mar-14 36
RMS M106 NDT and Repair if any 20 20-Mar-14 09-Apr-14 36
RMS M107 Box Up 25 01-Apr-14 26-Apr-14 36
RMS M108 Hydrotesting 35 05-Apr-14 10-May-14 36
RMS M109 Vent Stack Installation 50 02-May-14 21-Jun-14 67
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument Works 66 11-May-14 16-Jul-14 36
RMS I101 Panel Installation 10 14-Jun-14 24-Jun-14 36
RMS I102 Cable laying 25 17-Jun-14 12-Jul-14 39
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
RMS I103 Field Instrument Installation 15 11-May-14 26-May-14 58
RMS I104 Junction Box & Support Installation 20 13-May-14 02-Jun-14 58
RMS I105 Glanding, Tremination & Tubing 22 24-Jun-14 16-Jul-14 36
RMS I106 Actuated Valve Installation 20 17-May-14 06-Jun-14 62
RMS I107 Name Plate Installation 5 24-May-14 29-May-14 62
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical Works 92 25-Apr-14 26-Jul-14 39
RMS E101 Transformer installation (3 nos) 15 25-Apr-14 10-May-14 61
RMS E102 Instrument Air Compressor 5 10-May-14 15-May-14 61
RMS E103 Cable Laying 15 17-Jun-14 02-Jul-14 39
RMS E104 Glanding & Termination 7 04-Jul-14 11-Jul-14 39
RMS E105 Fence Earthing 15 25-Apr-14 10-May-14 66
RMS E106 Equipment Earthing 35 25-May-14 29-Jun-14 51
RMS E107 Panel Energization 15 11-Jul-14 26-Jul-14 39
Harmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil worksHarmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil wo... 227 17-Nov-13 02-Jul-14 50
SS C1001 Earth Work for Containerized Building Foundation 25 17-Nov-13 12-Dec-13 83
SS C1002 Laying of Polythene sheet 3 13-Dec-13 16-Dec-13 83
SS C1003 PCC for the foundation 2 13-Dec-13 15-Dec-13 83
SS C1004 Reinforce work for Foundation 7 15-Dec-13 22-Dec-13 83
SS C1005 Shuttering for Foundation 4 23-Dec-13 27-Dec-13 83
SS C1006 Concreting work for Foundation 3 28-Dec-13 31-Dec-13 83
SS C1007 Deshuttering for Foundation 4 01-Jan-14 05-Jan-14 83
SS C1008 Reinforcement work for Coloumn 4 07-Jan-14 11-Jan-14 83
SS C1009 Shuttering of column 6 12-Jan-14 18-Jan-14 83
SS C1010 Column Concreting 7 18-Jan-14 25-Jan-14 83
SS C1011 Deshuttering for Column 4 26-Jan-14 30-Jan-14 83
SS C1012 Shuttering work for floor beam 20 31-Jan-14 20-Feb-14 83
SS C1013 Reinforcement work for floor beam 20 05-Feb-14 25-Feb-14 83
SS C1014 Concreting for floor beam 3 26-Feb-14 01-Mar-14 83
SS C1015 Deshuttering of floor beam 7 08-Mar-14 15-Mar-14 83
SS C1016 Applying Protective coating 7 16-Mar-14 23-Mar-14 83
SS C1017 Backfilling the foundation 9 23-Mar-14 01-Apr-14 83
SS C1018 Containerized Substation Installation 8 04-May-14 12-May-14 50
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation WorksHarmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation Works 52 11-May-14 02-Jul-14 50
SS I1000 Installation of Panels 4 11-May-14 15-May-14 51
SS I1010 Installation of Battery Bank 10 15-May-14 25-May-14 52
SS I1020 Installation of DC-DB 7 25-May-14 01-Jun-14 52
SS I1030 Installation of Lighting DB 7 12-May-14 19-May-14 50
SS I1040 Installation of 415 v Switch Board 15 12-May-14 27-May-14 50
SS I1050 Installation of emergency Lighting DB 7 27-May-14 03-Jun-14 50
SS I1060 Installation of HVAC system 29 03-Jun-14 02-Jul-14 50
Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2)Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2) 190 25-Oct-13 03-May-14 110
OHL 1000 Survey & ROW grading 50 25-Oct-13 14-Dec-13 110
OHL 1020 Pole hole drilling 50 14-Dec-13 02-Feb-14 110
OHL 1030 Pole distribution 50 22-Dec-13 10-Feb-14 110
OHL 1040 Dressing 35 15-Feb-14 22-Mar-14 110
OHL 1050 Errectioning 25 20-Feb-14 17-Mar-14 110
OHL 1060 Conductor Stringing 20 24-Feb-14 16-Mar-14 110
OHL 1070 Jumpering 15 16-Mar-14 31-Mar-14 110
OHL 1080 Installation of Field Isolator 14 31-Mar-14 14-Apr-14 110
OHL 1090 Installation of Auto recloser 14 02-Apr-14 16-Apr-14 110
OHL 1100 33 KV Spur Lines from OHL to RMS 14 17-Apr-14 01-May-14 110
OHL 1110 33 KV Underground cabling and Termination 10 23-Apr-14 03-May-14 110
Harmal FD-10-Oct13.3.4.6 Shut Down ActivitiesHarmal FD-10-Oct13.3.4.6 Shut Down Activities 183 25-Sep-13 27-Mar-14 153
Harmal FD-10-Oct13.3.4.6.1.3.3.1 Civil WorksHarmal FD-10-Oct13.3.4.6.1.3.3.1 Civil Works 183 25-Sep-13 27-Mar-14 152
SD C10 Plot Survey and set out 15 25-Sep-13 10-Oct-13 270
SD C20 Precasting for Foundation 15 25-Sep-13 10-Oct-13 287
SD C30 Marking and Excavation of the Foundation 20 11-Oct-13 31-Oct-13 270
SD C40 PCC for Foundation 15 20-Oct-13 04-Nov-13 270
SD C50 Foundation Installation 10 27-Oct-13 06-Nov-13 270
SD C60 Foundation Backfilling & Compacting 15 09-Nov-13 24-Nov-13 270
SD C70 Cable Trench Excavation 20 22-Jan-14 11-Feb-14 156
SD C80 Cable Trench Backfilling 10 08-Mar-14 18-Mar-14 156
SD C90 Grouting, Final Grading & House Keeping 5 22-Mar-14 27-Mar-14 152
Harmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical Works 99 28-Nov-13 07-Mar-14 152
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
SD M10 Prefabrication of Spools 55 28-Nov-13 22-Jan-14 152
SD M20 NDT and Repair if any 10 17-Jan-14 27-Jan-14 159
SD M30 Structure Support Fabrication & Coating 30 08-Dec-13 07-Jan-14 152
SD M40 Suppot Erection 30 12-Jan-14 11-Feb-14 152
SD M50 Piping Erection, Welding 15 03-Feb-14 18-Feb-14 152
SD M60 NDT and Repair if any 20 05-Feb-14 25-Feb-14 152
SD M70 Hydrotesting 10 25-Feb-14 07-Mar-14 152
Harmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical Works 25 11-Feb-14 08-Mar-14 156
SD E10 Cable Laying 15 11-Feb-14 26-Feb-14 156
SD E20 Glanding & Termination 10 26-Feb-14 08-Mar-14 156
Harmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument WorksHarmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument Works 41 14-Feb-14 27-Mar-14 153
SD I10 Cable laying 15 14-Feb-14 01-Mar-14 163
SD I20 Field Instrument Installation 10 25-Feb-14 07-Mar-14 152
SD I30 Junction Box & Support Installation 10 27-Feb-14 09-Mar-14 152
SD I40 Glanding, Tremination & Tubing 15 12-Mar-14 27-Mar-14 152
SD I50 ESD Valve Installation 7 01-Mar-14 08-Mar-14 171
SD I60 Name Plate Installation 5 04-Mar-14 09-Mar-14 171
Harmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at KautherHarmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at Kauther 11 17-Mar-14 28-Mar-14 171
Harmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDOHarmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDO 11 17-Mar-14 28-Mar-14 171
SD 1000 Final Shut Down Date from PDO 11 17-Mar-14 28-Mar-14 171
Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1 124 18-Apr-14 20-Aug-14 36
A3170 Punch List Clearance 30 21-Jul-14 20-Aug-14 36
A3180 CP-Testing and Commmision 7 26-Jul-14 02-Aug-14 44
A3190 HVAC system 15 02-Jul-14 17-Jul-14 50
A3200 FOC ODTR Testing 2 21-Jul-14 23-Jul-14 54
A3210 RMS-2 Loop checking works 25 16-Jul-14 10-Aug-14 36
A3220 RMS-2 Electrical Testing 12 26-Jul-14 07-Aug-14 39
A3230 RMS-2 Panel Enegization 10 22-Jul-14 01-Aug-14 45
A3240 Transformer Energization 10 11-Jul-14 21-Jul-14 46
A3250 OHL Relay Setting and Testing 20 18-Apr-14 08-May-14 110
A3260 Pre-Commisioning Completion 10 10-Aug-14 20-Aug-14 36
Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2 686 09-Dec-12 30-Oct-14 90
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test Installation 682 09-Dec-12 26-Oct-14 23
Harmal FD-10-Oct13.1.1.1.1.1.2 AFC PackageHarmal FD-10-Oct13.1.1.1.1.1.2 AFC Package 210 09-Dec-12 29-Oct-13 55
D0010 Process 320 09-Dec-12 29-Oct-13 0
D0020 Civil 287 14-Jan-13 28-Oct-13 56
D0030 Mechanical and Piping 310 22-Dec-12 29-Oct-13 0
D0040 Electrical 297 31-Dec-12 24-Oct-13 0
D0050 Control and automation 300 29-Dec-12 25-Oct-13 0
Harmal FD-10-Oct13.1.1.1.1 Bulk MTOHarmal FD-10-Oct13.1.1.1.1 Bulk MTO 254 18-Jan-13 29-Sep-13 85
A3620 Civil & Structural 205 19-Feb-13 12-Sep-13 45
A3630 Electrical 235 20-Jan-13 12-Sep-13 45
A3640 Mechanical and Piping 249 23-Jan-13 29-Sep-13 85
A3650 Control and Automation 240 18-Jan-13 15-Sep-13 44
Harmal FD-10-Oct13.1.1.1.2 Project Management and Supporting DocumentsHarmal FD-10-Oct13.1.1.1.2 Project Management and Supporting Documents 642 22-Jan-13 26-Oct-14 23
A3660 Project Management 580 22-Jan-13 25-Aug-14 85
A3670 As Built Packages 35 21-Sep-14 26-Oct-14 4
A3790 SAP 45 22-Aug-14 06-Oct-14 0
A3800 CCMS 45 22-Aug-14 06-Oct-14 0
Harmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test Installation 533 03-Mar-13 18-Aug-14 31
Harmal FD-10-Oct13.1.1.21.5 Test Seperator Installation MaterialsHarmal FD-10-Oct13.1.1.21.5 Test Seperator Installation Materials 533 03-Mar-13 18-Aug-14 31
Harmal FD-10-Oct13.1.1.21.5.1.2.4 ESD ValveHarmal FD-10-Oct13.1.1.21.5.1.2.4 ESD Valve 494 24-Mar-13 31-Jul-14 49
1939 PR Issue 2 24-Mar-13 26-Mar-13 31
1949 Enquiry Floating 14 27-Mar-13 10-Apr-13 49
1959 Receive quotes from Vendors 180 10-Apr-13 07-Oct-13 49
1969 Technical Bid Evaluation 30 07-Oct-13 06-Nov-13 49
1979 Vendor Data and complete commercial 15 06-Nov-13 21-Nov-13 49
1989 Issue of PO 5 21-Nov-13 26-Nov-13 49
1999 Manufacturing of Items 200 27-Nov-13 15-Jun-14 49
2009 Shipping Delivery 30 16-Jun-14 16-Jul-14 49
3189 ESD Valve Receipt at site 10 21-Jul-14 31-Jul-14 49
Harmal FD-10-Oct13.1.1.21.5.1.2.5 Relief ValveHarmal FD-10-Oct13.1.1.21.5.1.2.5 Relief Valve 493 27-Mar-13 02-Aug-14 23
2019 PR Issue 2 27-Mar-13 29-Mar-13 23
2029 Enquiry Floating 14 29-Mar-13 12-Apr-13 23
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
2039 Receive quotes from Vendors 200 13-Apr-13 19-Oct-13 23
2049 Technical Bid Evaluation 16 20-Oct-13 04-Nov-13 23
2059 Vendor Data and complete commercial 16 05-Nov-13 20-Nov-13 23
2069 Issue of PO 7 21-Nov-13 28-Nov-13 23
2079 Manufacturing of Items 200 28-Nov-13 16-Jun-14 23
2089 Shipping Delivery 30 16-Jun-14 16-Jul-14 23
3199 Relief Valve Receipt at Site 10 23-Jul-14 02-Aug-14 23
Harmal FD-10-Oct13.1.1.21.5.1.2.9 Control ValvesHarmal FD-10-Oct13.1.1.21.5.1.2.9 Control Valves 465 16-Mar-13 24-Jun-14 62
2339 PR Issue 2 16-Mar-13 18-Mar-13 62
2349 Enquiry Floating 14 18-Mar-13 01-Apr-13 62
2359 Receive quotes from Vendors 190 01-Apr-13 08-Oct-13 62
2369 Technical Bid Evaluation 16 08-Oct-13 24-Oct-13 62
2379 Vendor Data and complete commercial 12 17-Oct-13 29-Oct-13 62
2389 Issue of PO 7 29-Oct-13 05-Nov-13 62
2399 Manufacturing of Items 184 05-Nov-13 08-May-14 62
2409 Shipping Delivery 30 08-May-14 07-Jun-14 62
3209 Control Valve Receipt at Site 10 14-Jun-14 24-Jun-14 62
Harmal FD-10-Oct13.1.1.21.5.1 Test SeparatorHarmal FD-10-Oct13.1.1.21.5.1 Test Separator 517 03-Mar-13 02-Aug-14 0
A2490 PR Issue 2 03-Mar-13 05-Mar-13 0
A2500 Enquiry Floating 14 05-Mar-13 19-Mar-13 0
A2510 Receive Quotes from Vendor 21 19-Mar-13 09-Apr-13 0
A2520 TBE & Vendor Finilize 195 09-Apr-13 21-Oct-13 0
A2530 Issue of PO 4 21-Oct-13 25-Oct-13 0
A2540 Manufacturing of Items 236 29-Oct-13 22-Jun-14 0
A2550 Inspection & Release 20 22-Jun-14 12-Jul-14 0
A2560 Material Delivery 12 13-Jul-14 25-Jul-14 0
A2820 Test Separator Receipt at Site 7 26-Jul-14 02-Aug-14 0
Harmal FD-10-Oct13.1.1.21.5.2 Piping Materials & FittingsHarmal FD-10-Oct13.1.1.21.5.2 Piping Materials & Fittings 403 26-Mar-13 03-May-14 73
A2850 PR Issue 2 26-Mar-13 28-Mar-13 73
A2860 Enquiry Floating 48 28-Mar-13 15-May-13 73
A2870 Receive Quotes from Vendor 140 15-May-13 02-Oct-13 73
A2880 TBE & Vendor Finilize 88 30-Jul-13 26-Oct-13 73
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2890 Issue of PO 28 26-Oct-13 23-Nov-13 73
A2900 Manufacturing of Items 136 23-Nov-13 08-Apr-14 73
A2910 Inspection & Release 112 23-Dec-13 14-Apr-14 73
A2920 Material Delivery 112 28-Dec-13 19-Apr-14 73
A2930 Material Receipt at Site 112 11-Jan-14 03-May-14 73
Harmal FD-10-Oct13.1.1.21.5.3 Bulk MaterialsHarmal FD-10-Oct13.1.1.21.5.3 Bulk Materials 413 26-Mar-13 13-May-14 56
A2940 PR Issue 2 26-Mar-13 28-Mar-13 56
A2950 Enquiry Floating 7 29-Mar-13 05-Apr-13 56
A2960 Receive Quotes from Vendor 128 06-Apr-13 12-Aug-13 56
A2970 Vendor Finilize 128 30-Apr-13 05-Sep-13 56
A2980 Issue of PO 48 05-Sep-13 23-Oct-13 56
A2990 Manufacturing of Items 200 12-Sep-13 31-Mar-14 56
A3000 Inspection & Release 200 10-Oct-13 28-Apr-14 56
A3010 Material Receipt at Site 150 14-Dec-13 13-May-14 56
Harmal FD-10-Oct13.1.1.21.5.4 Instrument Air CompressorHarmal FD-10-Oct13.1.1.21.5.4 Instrument Air Compressor 429 28-Mar-13 31-May-14 85
A3020 PR Issue 6 28-Mar-13 03-Apr-13 85
A3030 Enquiry Floating 152 03-Apr-13 02-Sep-13 85
A3040 Receive quotes from Vendors 144 23-Apr-13 14-Sep-13 85
A3050 TBE & Vendor Finilize 136 13-May-13 26-Sep-13 85
A3060 Issue of PO 7 26-Sep-13 03-Oct-13 85
A3070 Manufacturing of Items 160 03-Oct-13 12-Mar-14 85
A3080 Inspection & Release 20 12-Mar-14 01-Apr-14 85
A3090 Material Delivery 20 01-Apr-14 21-Apr-14 85
A3100 Air Compressor Receipt at Site 30 01-May-14 31-May-14 85
Harmal FD-10-Oct13.1.1.21.5.5 Flow MeterHarmal FD-10-Oct13.1.1.21.5.5 Flow Meter 445 24-Mar-13 12-Jun-14 98
A3680 PR Issue 6 24-Mar-13 30-Mar-13 31
A3690 Enquiry Floating 152 30-Mar-13 29-Aug-13 31
A3700 Receive quotes from Vendors 136 23-Apr-13 06-Sep-13 31
A3710 TBE & Vendor Finilize 12 06-Sep-13 18-Sep-13 31
A3720 Issue of PO 7 18-Sep-13 25-Sep-13 31
A3730 Manufacturing of Items 180 25-Sep-13 24-Mar-14 98
A3740 Inspection & Release 20 24-Mar-14 13-Apr-14 98
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A3750 Material Delivery 20 13-Apr-14 03-May-14 98
A3760 Material Receipt at Site 30 13-May-14 12-Jun-14 98
Harmal FD-10-Oct13.1.1.21.5.6 F & G SystemHarmal FD-10-Oct13.1.1.21.5.6 F & G System 334 18-Sep-13 18-Aug-14 31
A3810 PR Issue 25 18-Sep-13 13-Oct-13 31
A3820 Enquiry Floating 60 13-Oct-13 12-Dec-13 31
A3830 Receive quotes from Vendors 60 21-Oct-13 20-Dec-13 31
A3840 TBE & Vendor Finilize 12 20-Dec-13 01-Jan-14 31
A3850 Issue of PO 7 01-Jan-14 08-Jan-14 31
A3860 Manufacturing of Items 150 08-Jan-14 07-Jun-14 31
A3870 Inspection & Release 20 07-Jun-14 27-Jun-14 31
A3880 Material Delivery 20 27-Jun-14 17-Jul-14 31
A3890 Material Receipt at Site 22 27-Jul-14 18-Aug-14 31
Harmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test Installation 197 29-Mar-14 12-Oct-14 107
Harmal FD-10-Oct13.1.2.2 Well Test Seperator InstallationHarmal FD-10-Oct13.1.2.2 Well Test Seperator Installation 197 29-Mar-14 12-Oct-14 107
Harmal FD-10-Oct13.1.2.2.1 Civil WorksHarmal FD-10-Oct13.1.2.2.1 Civil Works 197 29-Mar-14 12-Oct-14 107
WTS C18 Excavation for Foundations 30 29-Apr-14 29-May-14 35
WTS C28 PCC for Foundation 45 01-May-14 15-Jun-14 35
WTS C38 Foundation Installation 45 08-May-14 22-Jun-14 35
WTS C48 Foundation Backfilling & Compaction 30 15-Aug-14 14-Sep-14 136
WTS C58 Excavation for Cable Trench 7 29-May-14 05-Jun-14 96
WTS C68 Cable trench backfilling 7 14-Sep-14 21-Sep-14 2
WTS C78 Grouting, Final Grading and Housekeeping 22 21-Sep-14 12-Oct-14 2
WTS C8 Plot Survey and set out 30 29-Mar-14 28-Apr-14 35
Harmal FD-10-Oct13.1.2.2.2 Mechanical WorksHarmal FD-10-Oct13.1.2.2.2 Mechanical Works 172 11-Apr-14 30-Sep-14 0
WTS M19 Prefabrication of Piping spools 40 11-Apr-14 21-May-14 56
WTS M29 NDT 36 25-Apr-14 31-May-14 56
WTS M39 Spool Hydrotest 32 09-May-14 10-Jun-14 56
WTS M49 Structural support Fabrication & Coating 32 11-Apr-14 13-May-14 82
WTS M59 Structual Support installation 24 22-Jun-14 16-Jul-14 35
WTS M69 Piping Erection 35 05-Aug-14 09-Sep-14 0
WTS M79 Final Hydrotest 7 09-Sep-14 16-Sep-14 0
WTS M89 Valve installation / Nitrogen Purging 14 16-Sep-14 30-Sep-14 0
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
WTS M9 Test Separator errection and alignment 3 02-Aug-14 05-Aug-14 0
Harmal FD-10-Oct13.1.2.2.3 Electrical WorksHarmal FD-10-Oct13.1.2.2.3 Electrical Works 27 09-Sep-14 06-Oct-14 0
WTS E13 Cable Glanding & Termination 12 15-Sep-14 27-Sep-14 0
WTS E23 Earthing works for Equipment & Instruments 9 27-Sep-14 06-Oct-14 0
WTS E3 Cable laying 5 09-Sep-14 14-Sep-14 0
Harmal FD-10-Oct13.1.2.2.4 Instrumentation worksHarmal FD-10-Oct13.1.2.2.4 Instrumentation works 65 02-Aug-14 06-Oct-14 0
WTS I14 ESD Valve /Flow meter /F & G system Installation 12 18-Sep-14 30-Sep-14 0
WTS I24 Instrument cable laying & Termination 12 21-Sep-14 03-Oct-14 0
WTS I34 Instrument Tubing works 19 17-Sep-14 06-Oct-14 0
WTS I4 Instruments Calibration 24 02-Aug-14 26-Aug-14 23
Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2 175 08-May-14 30-Oct-14 0
Pre 072 Substation Readiness 15 08-May-14 23-May-14 115
Pre 092 WTS Precommissioning activities 24 06-Oct-14 30-Oct-14 0
Pre 102 Ex- Inspection works 10 10-Oct-14 20-Oct-14 0
Pre 112 Pie - Configuration by PDO 14 06-Oct-14 20-Oct-14 0
Pre 122 Loop Checking 10 20-Oct-14 30-Oct-14 0
Harmal FD-10-Oct13.Comm Support Commissioning SupportHarmal FD-10-Oct13.Comm Support Commissioning Support 161 20-Aug-14 28-Jan-15 0
A3770 Commissioning Support Assistance for Testing Facilities 90 30-Oct-14 28-Jan-15 0
A3780 Commisioning Support Assistance for Production Facilities 90 20-Aug-14 18-Nov-14 36
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 

More Related Content

PDF
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
PDF
NNP Shutdown 2014 Plans - Scurve and npt graph
PDF
01. P269 - Project Implementation Programme - Rev 00
PDF
Contract 2 - Project Progress Status. Oct-13
PDF
Adaptadores hidraulicos bsp
PPTX
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
NNP Shutdown 2014 Plans - Scurve and npt graph
01. P269 - Project Implementation Programme - Rev 00
Contract 2 - Project Progress Status. Oct-13
Adaptadores hidraulicos bsp
Projects Department Weekly Report - SVC AlJouf-2, Dynamic and Static Rea... d...

What's hot (9)

PDF
Standard detailed drawings
PDF
Monthly Progress Report No.13 - September 2011
PPTX
Update Data of APR2014 in SPICEPARK
PDF
Cetpro san pedro
PPTX
Slide3 phasing ofp_rdelgrpswork
PPTX
Rice Co-Op Presentation
PDF
Equivalent grades of steel
PDF
1) Photo report Hook up Pipe spool#6
DOC
PIPING DESIGNER
Standard detailed drawings
Monthly Progress Report No.13 - September 2011
Update Data of APR2014 in SPICEPARK
Cetpro san pedro
Slide3 phasing ofp_rdelgrpswork
Rice Co-Op Presentation
Equivalent grades of steel
1) Photo report Hook up Pipe spool#6
PIPING DESIGNER
Ad

Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2

  • 1. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13 Harmal RMS-2 Construction & 16" DSS Pipeline to KGP Phase 1 & Phase 2 - FinalHarmal FD-10-Oct13 Harmal RMS-2 Construction & 16" D... 776 09-Dec-12 28-Jan-15 0 Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1 625 09-Dec-12 30-Aug-14 36 Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1 625 09-Dec-12 30-Aug-14 36 Harmal FD-10-Oct13.3.1.11.1.1.2 AFC PackageHarmal FD-10-Oct13.3.1.11.1.1.2 AFC Package 286 09-Dec-12 25-Sep-13 140 D100 Electrical 200 05-Jan-13 10-Sep-13 28 D100A Electrical-OHL 238 05-Jan-13 31-Aug-13 165 D110 Control and automation 215 01-Jan-13 25-Sep-13 28 D120 Pipeline 237 06-Jan-13 31-Aug-13 71 D70 Civil 145 27-Jan-13 27-Jul-13 53 D80 Mechanical and Piping 142 24-Dec-12 18-Jun-13 28 D90 Process 225 09-Dec-12 14-Sep-13 0 Harmal FD-10-Oct13.3.1.11.1 Bulk MTOHarmal FD-10-Oct13.3.1.11.1 Bulk MTO 172 30-Jan-13 21-Jul-13 50 A3110 Mechanical and Piping 170 30-Jan-13 19-Jul-13 37 A3120 Civil and Structural 165 01-Feb-13 16-Jul-13 50 A3130 Electrical 165 06-Feb-13 21-Jul-13 50 A3140 Control and Automation 162 06-Feb-13 18-Jul-13 50 Harmal FD-10-Oct13.3.1.11.2 Project Management and Support DocumentsHarmal FD-10-Oct13.3.1.11.2 Project Management and Support Documents 625 09-Dec-12 30-Aug-14 36 A3150 Project Management 600 09-Dec-12 05-Aug-14 41 A3160 Project Support & As Built Completion 339 25-Sep-13 30-Aug-14 36 A3270 SAP Management 319 25-Sep-13 10-Aug-14 36 A3280 CCMS 319 25-Sep-13 10-Aug-14 36 Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1 487 13-Jan-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 ConstructionHarmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 Construction 487 13-Jan-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1.2 MechanicalHarmal FD-10-Oct13.3.1.2.1.2 Mechanical 474 13-Jan-13 02-May-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS PipesHarmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS Pipes 367 13-Jan-13 15-Jan-14 47 357 PR Issue 1 13-Jan-13 14-Jan-13 47 358 Enquiry Floating 7 14-Jan-13 21-Jan-13 47 359 Receive quotes from Vendors 7 22-Jan-13 29-Jan-13 47 360 Technical Bid Evaluation 14 30-Jan-13 13-Feb-13 47 361 Vendor Data and complete commercial 10 14-Feb-13 24-Feb-13 47 362 Issue of PO 2 25-Feb-13 27-Feb-13 47 363 Manufacturing of Pipes & Coating 286 28-Feb-13 11-Dec-13 47 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 2. Activity ID Activity Name Original Duration Start Finish Total Float 364 Inspection, Rlease & Shipment 150 29-Jul-13 26-Dec-13 47 365 Pipe Receipt at Site 125 12-Sep-13 15-Jan-14 47 Harmal FD-10-Oct13.3.1.2.1.2.1.2.3 FlangesHarmal FD-10-Oct13.3.1.2.1.2.1.2.3 Flanges 283 30-Mar-13 07-Jan-14 67 375 PR Issue 2 30-Mar-13 01-Apr-13 67 376 Enquiry Floating 7 02-Apr-13 09-Apr-13 67 377 Receive quotes from Vendors 21 09-Apr-13 30-Apr-13 67 378 Technical Bid Evaluation 15 30-Apr-13 15-May-13 67 379 Vendor Data and complete commercial 5 15-May-13 20-May-13 67 380 Issue of PO 7 21-May-13 28-May-13 67 381 Manufacturing process at Vendor Yard 145 28-May-13 20-Oct-13 67 382 Shipping Delivery 34 20-Oct-13 23-Nov-13 67 383 Flange Receipt at site 45 23-Nov-13 07-Jan-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ SpoolsHarmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ Spools 322 31-Mar-13 16-Feb-14 76 402 PR Issue 2 31-Mar-13 02-Apr-13 76 403 Enquiry Floating 11 03-Apr-13 14-Apr-13 76 404 Receive quotes from Vendors 14 15-Apr-13 29-Apr-13 76 405 Technical Bid Evaluation 30 30-Apr-13 30-May-13 76 406 Vendor Data and complete commercial 10 31-May-13 10-Jun-13 76 407 Issue of PO 6 11-Jun-13 17-Jun-13 76 408 Manufacturing of Items 185 18-Jun-13 20-Dec-13 76 409 Shipping Delivery 40 21-Dec-13 30-Jan-14 76 410 IJ Spool Receipt at Site 10 06-Feb-14 16-Feb-14 76 Harmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred TeeHarmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred Tee 316 01-Apr-13 11-Feb-14 138 411 PR Issue 2 01-Apr-13 03-Apr-13 138 412 Enquiry Floating 7 03-Apr-13 10-Apr-13 138 413 Receive quotes from Vendors 14 10-Apr-13 24-Apr-13 138 414 Technical Bid Evaluation 30 24-Apr-13 24-May-13 138 415 Vendor Data and complete commercial 14 24-May-13 07-Jun-13 138 416 Issue of PO 2 07-Jun-13 09-Jun-13 138 417 Manufacturing of Items 190 09-Jun-13 16-Dec-13 138 418 Shipping Delivery 20 16-Dec-13 05-Jan-14 138 419 Barred TEE Receipt at Site 30 12-Jan-14 11-Feb-14 138 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 3. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeveHarmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeve 210 15-Apr-13 11-Nov-13 85 420 PR Issue 2 15-Apr-13 17-Apr-13 85 421 Enquiry Floating 11 17-Apr-13 28-Apr-13 85 422 Receive quotes from Vendors 14 28-Apr-13 12-May-13 85 423 TBE & Vendor Finilize 30 12-May-13 11-Jun-13 85 424 Issue of PO 2 11-Jun-13 13-Jun-13 85 425 Manufacturing of Items 100 13-Jun-13 21-Sep-13 85 426 Inspection & Release 4 21-Sep-13 25-Sep-13 85 427 Material Delivery 20 25-Sep-13 15-Oct-13 85 428 Shrink Sleeve Receipt at Site 20 22-Oct-13 11-Nov-13 85 Harmal FD-10-Oct13.3.1.2.1.2.2 Vent StackHarmal FD-10-Oct13.3.1.2.1.2.2 Vent Stack 383 14-Apr-13 02-May-14 67 A1360 PR Issue 6 14-Apr-13 20-Apr-13 67 A1370 Enquiry Floating 14 20-Apr-13 04-May-13 67 A1380 Receive quotes from Vendors 145 04-May-13 26-Sep-13 67 A1390 TBE & Vendor Finilize 140 19-May-13 06-Oct-13 67 A1400 Issue of PO 2 06-Oct-13 08-Oct-13 67 A1410 Manufacturing of Items 120 08-Oct-13 05-Feb-14 67 A1420 FAT, Final Inspection & Release 30 05-Feb-14 07-Mar-14 67 A1430 Material Delivery 20 07-Mar-14 27-Mar-14 67 A1431 Vent Stack Receipt at Site 26 06-Apr-14 02-May-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.2.1 Bulk Materials 298 30-Apr-13 22-Feb-14 37 1529 PR Issue 30 30-Apr-13 30-May-13 37 1539 Enquiry Floating 90 30-May-13 28-Aug-13 37 1549 Receive quotes from Vendors 100 04-Jun-13 12-Sep-13 37 1569 Vendor Data and complete commercial 75 09-Jul-13 22-Sep-13 37 1579 Issue of PO 30 23-Sep-13 23-Oct-13 37 1589 Manufacturing of Materials 110 13-Oct-13 31-Jan-14 37 1599 Shipping Delivery 110 02-Nov-13 20-Feb-14 37 1609 Fittings Receipt at site( 106 08-Nov-13 22-Feb-14 37 Harmal FD-10-Oct13.3.1.2.1.2.4 Internal ClampsHarmal FD-10-Oct13.3.1.2.1.2.4 Internal Clamps 151 27-Apr-13 25-Sep-13 79 A2330 PR Issue 6 27-Apr-13 03-May-13 79 A2340 Enquiry Floating 14 03-May-13 17-May-13 79 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 4. Activity ID Activity Name Original Duration Start Finish Total Float A2350 Recieve quotes from Vendors 21 17-May-13 07-Jun-13 79 A2360 Vendor Data and complete commercial 7 07-Jun-13 14-Jun-13 79 A2370 Issue of PO 2 15-Jun-13 17-Jun-13 79 A2380 Maufacturing of mateirals 70 18-Jun-13 27-Aug-13 79 A2390 Shipping Delivery 10 28-Aug-13 17-Sep-13 79 A2400 Reciept at site 7 18-Sep-13 25-Sep-13 79 Harmal FD-10-Oct13.3.1.2.1.3 ElectricalHarmal FD-10-Oct13.3.1.2.1.3 Electrical 361 08-May-13 04-May-14 63 Harmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSBHarmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSB 224 26-Jun-13 05-Feb-14 136 A1200 PR Issue 2 26-Jun-13 28-Jun-13 136 A1210 Enquiry Floating 14 28-Jun-13 12-Jul-13 136 A1220 Receive quotes from Vendor 7 12-Jul-13 19-Jul-13 136 A1230 TBE & Vendor Finilze 62 19-Jul-13 19-Sep-13 136 A1240 Issue of PO 2 19-Sep-13 21-Sep-13 136 A1250 Manufacturing of Material 90 21-Sep-13 20-Dec-13 136 A1260 Inspection & Release 20 20-Dec-13 09-Jan-14 136 A1270 Material Delivery 20 16-Jan-14 05-Feb-14 136 Harmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical TransformerHarmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical Transformer 345 08-May-13 18-Apr-14 61 448 PR Issue 2 08-May-13 10-May-13 61 449 Enquiry Floating 14 10-May-13 24-May-13 61 450 Receive quotes from Vendors 120 20-May-13 17-Sep-13 61 451 Technical Bid Evaluation & Vendor Finalize 120 30-May-13 27-Sep-13 61 452 Vendor Data and complete commercial 12 27-Sep-13 09-Oct-13 61 453 Issue of PO 9 09-Oct-13 18-Oct-13 61 454 Manufacturing of Items 125 18-Oct-13 20-Feb-14 61 455 FAT, Final Inspection & Release 30 20-Feb-14 22-Mar-14 61 456 Delivery at Site 20 29-Mar-14 18-Apr-14 61 Harmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DB 259 25-Jun-13 11-Mar-14 117 458 PR Issue 6 25-Jun-13 01-Jul-13 117 459 Enquiry Floating 21 01-Jul-13 22-Jul-13 117 460 Receive quotes from Vendors 15 22-Jul-13 06-Aug-13 117 461 Vendor Finilize 55 06-Aug-13 30-Sep-13 117 462 Issue of PO 10 30-Sep-13 10-Oct-13 117 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 5. Activity ID Activity Name Original Duration Start Finish Total Float 463 Manufacturing of Items 100 10-Oct-13 18-Jan-14 117 464 FAT, Final Inspection & Release 15 18-Jan-14 02-Feb-14 117 465 Material Delivery 30 09-Feb-14 11-Mar-14 117 Harmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materialsHarmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materials 213 25-Jun-13 24-Jan-14 137 477 PR Issue 6 25-Jun-13 01-Jul-13 137 478 Enquiry Floating 6 01-Jul-13 07-Jul-13 137 479 Receive quotes from Vendors 12 07-Jul-13 19-Jul-13 137 480 Vendor Finilize 15 19-Jul-13 03-Aug-13 137 481 Issue of PO 4 03-Aug-13 07-Aug-13 137 482 Manufacturing of Items 140 07-Aug-13 25-Dec-13 137 483 Material Delivery 20 04-Jan-14 24-Jan-14 137 Harmal FD-10-Oct13.3.1.2.1.3.2 Containerized SubstationHarmal FD-10-Oct13.3.1.2.1.3.2 Containerized Substation 313 25-Jun-13 04-May-14 50 A1520 PR Issue 2 25-Jun-13 27-Jun-13 50 A1530 Enquiry Floating 7 27-Jun-13 04-Jul-13 50 A1540 Receive quotes from Vendors 90 04-Jul-13 02-Oct-13 50 A1550 Technical Bid Evaluation 15 02-Oct-13 17-Oct-13 50 A1560 Vendor Data and complete commercial 10 17-Oct-13 27-Oct-13 50 A1570 Issue of PO 6 27-Oct-13 02-Nov-13 50 A1580 Manufacturing of Items 150 02-Nov-13 01-Apr-14 50 A1590 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 50 A1600 Material Delivery 15 19-Apr-14 04-May-14 50 Harmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DB 296 25-Jun-13 17-Apr-14 75 467 PR Issue 7 25-Jun-13 02-Jul-13 75 468 Enquiry Floating 21 02-Jul-13 23-Jul-13 75 469 Receive quotes from Vendors 60 23-Jul-13 21-Sep-13 75 470 Technical Bid Evaluation 15 21-Sep-13 06-Oct-13 75 471 Vendor Data and complete commercial 15 06-Oct-13 21-Oct-13 75 472 Issue of PO 6 21-Oct-13 27-Oct-13 75 473 Manufacturing of Items 130 27-Oct-13 06-Mar-14 75 474 FAT, Final Inspection & Release 15 06-Mar-14 21-Mar-14 75 475 Material Delivery 20 28-Mar-14 17-Apr-14 75 Harmal FD-10-Oct13.3.1.2.1.3.3 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.3.3 Bulk Materials 193 24-Aug-13 05-Mar-14 112 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 6. Activity ID Activity Name Original Duration Start Finish Total Float 1709 PR Issue 6 24-Aug-13 30-Aug-13 112 1719 Enquiry Floating 6 30-Aug-13 05-Sep-13 112 1729 Receive quotes from Vendors 25 05-Sep-13 30-Sep-13 112 1739 Vendor Finilize 30 30-Sep-13 30-Oct-13 112 1749 Issue of PO 6 30-Oct-13 05-Nov-13 112 1759 Manufacturing of Items 90 05-Nov-13 03-Feb-14 112 1769 Material Delivery 20 13-Feb-14 05-Mar-14 112 Harmal FD-10-Oct13.3.1.2.1.4 InstrumentationHarmal FD-10-Oct13.3.1.2.1.4 Instrumentation 396 14-Apr-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS systemHarmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS system 329 16-Jun-13 11-May-14 51 438 PR Issue 2 16-Jun-13 18-Jun-13 51 439 Enquiry Floating 7 18-Jun-13 25-Jun-13 51 440 Receive quotes from Vendors 130 25-Jun-13 02-Nov-13 51 441 Technical Bid Evaluation 10 02-Nov-13 12-Nov-13 51 442 Vendor Data and complete commercial 10 12-Nov-13 22-Nov-13 51 443 Issue of PO 10 22-Nov-13 02-Dec-13 51 444 Manufacturing of Items 120 02-Dec-13 01-Apr-14 51 445 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 51 446 Material Delivery 20 21-Apr-14 11-May-14 51 Harmal FD-10-Oct13.3.1.2.1.4.4 GaugeHarmal FD-10-Oct13.3.1.2.1.4.4 Gauge 369 14-Apr-13 18-Apr-14 81 889 PR Issue 2 14-Apr-13 16-Apr-13 81 899 Enquiry Floating 14 17-Apr-13 01-May-13 81 909 Receive quotes from Vendors 160 02-May-13 09-Oct-13 81 919 Technical Bid Evaluation 20 11-Oct-13 31-Oct-13 81 929 Vendor Data and complete commercial 20 01-Nov-13 21-Nov-13 81 939 Issue of PO 2 22-Nov-13 24-Nov-13 81 949 Manufacturing of Items 120 04-Dec-13 03-Apr-14 81 959 Material Delivery 10 08-Apr-14 18-Apr-14 81 Harmal FD-10-Oct13.3.1.2.1.4.7 TransmittersHarmal FD-10-Oct13.3.1.2.1.4.7 Transmitters 315 21-May-13 01-Apr-14 98 1129 PR Issue 30 21-May-13 20-Jun-13 98 1139 Enquiry Floating 140 20-Jun-13 07-Nov-13 98 1149 Receive quotes from Vendors 140 30-Jun-13 17-Nov-13 98 1159 Technical Bid Evaluation 140 10-Jul-13 27-Nov-13 98 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 7. Activity ID Activity Name Original Duration Start Finish Total Float 1169 Vendor Data and complete commercial 140 20-Jul-13 07-Dec-13 98 1179 Issue of PO 6 09-Aug-13 08-Oct-13 98 1189 Manufacturing of Items 150 08-Oct-13 07-Mar-14 98 1199 Material Delivery 20 12-Mar-14 01-Apr-14 98 Harmal FD-10-Oct13.3.1.2.1.4.10 F&G SystemsHarmal FD-10-Oct13.3.1.2.1.4.10 F&G Systems 321 05-May-13 22-Mar-14 108 1289 PR Issue 2 05-May-13 07-May-13 108 1299 Enquiry Floating 7 07-May-13 14-May-13 108 1309 Receive quotes from Vendors 150 22-May-13 19-Oct-13 108 1319 Technical Bid Evaluation 146 06-Jun-13 30-Oct-13 108 1329 Vendor Data and complete commercial 25 10-Oct-13 04-Nov-13 108 1339 Issue of PO 3 04-Nov-13 07-Nov-13 108 1349 Manufacturing of Items 110 07-Nov-13 25-Feb-14 108 1359 Material Delivery 20 02-Mar-14 22-Mar-14 108 Harmal FD-10-Oct13.3.1.2.1.4.13 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.4.13 Bulk Materials 360 20-May-13 15-May-14 66 1619 PR Issue 2 28-May-13 30-May-13 66 1629 Enquiry Floating 140 30-May-13 17-Oct-13 66 1639 Receive quotes from Vendors 160 20-May-13 27-Oct-13 66 1659 Vendor Data and complete commercial 15 22-Oct-13 06-Nov-13 66 1669 Issue of PO 140 16-Nov-13 05-Apr-14 66 1679 Manufacturing of Items 150 26-Nov-13 25-Apr-14 66 1699 Material Delivery 20 25-Apr-14 15-May-14 66 Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1 605 09-Dec-12 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km)Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km) 349 26-Aug-13 10-Aug-14 44 Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil Works 349 26-Aug-13 10-Aug-14 44 PL C1000 Route Survey and Peg Marking 30 26-Aug-13 25-Sep-13 35 PL C1010 Right of Way Preparation 30 31-Aug-13 30-Sep-13 35 PL C1020 Excavation of Trench 80 24-Nov-13 12-Feb-14 44 PL C1030 Prepadding of sand for Pipeline 70 27-Nov-13 05-Feb-14 44 PL C1040 Post Padding after Laying of Pipeline 45 17-Apr-14 01-Jun-14 44 PL C1050 Back filling of Trench 80 18-Mar-14 06-Jun-14 44 PL C1060 Construction of Windrow 31 08-Jul-14 08-Aug-14 44 PL C1070 Final Grading for the ROW & Marker plate 30 11-Jul-14 10-Aug-14 44 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 8. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical Works 287 24-Sep-13 08-Jul-14 44 PL M1000 Stringing of Pipes 120 24-Sep-13 22-Jan-14 47 PL M1020 Straight Welding 180 20-Oct-13 18-Apr-14 47 PL M1030 NDT and repair if any 170 04-Nov-13 23-Apr-14 47 PL M1040 Sleeve Installation 150 29-Nov-13 28-Apr-14 47 PL M1050 Lowering of Pipes 150 09-Dec-13 08-May-14 44 PL M1060 Tie-in Welding 150 16-Dec-13 15-May-14 44 PL M1070 Barred Tee Welding 4 26-Apr-14 30-Apr-14 64 PL M1080 IJ Spool Installation 8 27-Apr-14 05-May-14 56 PL M1090 NDT and Repair if any 80 01-Mar-14 20-May-14 44 PL M1100 Sleeve Installation 75 13-Mar-14 27-May-14 44 PL M1110 Line Completion and Clearence 5 03-Jun-14 08-Jun-14 44 PL M1120 Hydrotesting 30 08-Jun-14 08-Jul-14 44 Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC Works 103 09-Apr-14 21-Jul-14 54 PL FOC1000 HDPE Duct Laying 60 09-Apr-14 08-Jun-14 67 PL FOC1010 Post Padding & Backfilling 50 22-Apr-14 11-Jun-14 80 PL FOC1020 FO Cable Blowing 7 08-Jul-14 15-Jul-14 54 PL FOC1030 FO Jointing & Splicing 5 16-Jul-14 21-Jul-14 54 Harmal FD-10-Oct13.3.4.2 Cathodic Protection WorksHarmal FD-10-Oct13.3.4.2 Cathodic Protection Works 597 09-Dec-12 02-Aug-14 44 Harmal FD-10-Oct13.3.4.2.1 Design WorksHarmal FD-10-Oct13.3.4.2.1 Design Works 45 09-Dec-12 27-Jan-13 192 PL CP1000 Design Preparation, Submission & Approval 45 09-Dec-12 27-Jan-13 192 Harmal FD-10-Oct13.3.4.2.4 ProcurementHarmal FD-10-Oct13.3.4.2.4 Procurement 365 29-Jan-13 29-Jan-14 192 A2280 CP Transformer Manufacturing 250 29-Jan-13 06-Oct-13 192 A2290 FAT & Documentation and Release 100 07-Oct-13 21-Dec-13 192 A2300 CP Transformer Receipt 31 29-Dec-13 29-Jan-14 192 Harmal FD-10-Oct13.3.4.2.2 Temporary CP InstallationHarmal FD-10-Oct13.3.4.2.2 Temporary CP Installation 75 09-Mar-14 23-May-14 58 PL CP1010 Temp.CP Installation for Pipeline 75 09-Mar-14 23-May-14 58 Harmal FD-10-Oct13.3.4.2.3 Permanent CP InstallationHarmal FD-10-Oct13.3.4.2.3 Permanent CP Installation 57 06-Jun-14 02-Aug-14 44 PL CP1020 Ground Bed Installation 15 06-Jun-14 21-Jun-14 44 PL CP1030 Anode JB Installation 3 19-Jun-14 22-Jun-14 46 PL CP1040 NDB Installation 2 22-Jun-14 24-Jun-14 46 PL CP1080 CP Tranformer Installation 1 26-Jun-14 27-Jun-14 44 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 9. Activity ID Activity Name Original Duration Start Finish Total Float PL CP1100 Trenching, Cable laying, Backfilling 7 26-Jun-14 03-Jul-14 44 PL CP1110 CP Cable Termination 5 03-Jul-14 08-Jul-14 44 PL CP1120 DCVG Survey 10 11-Jun-14 21-Jun-14 60 PL CP1140 Pre-Commissioning activity 10 08-Jul-14 18-Jul-14 44 PL CP1150 Final Commissioning 15 18-Jul-14 02-Aug-14 44 PL CP1160 CP System CIPS Survey 10 18-Jul-14 28-Jul-14 49 Harmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction workHarmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction work 339 05-Sep-13 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil Works 339 05-Sep-13 10-Aug-14 45 RMS C101 Plot Survey and set out 50 05-Sep-13 25-Oct-13 35 RMS C102 Land Filling and Access Road Preparation 45 09-Nov-13 24-Dec-13 35 RMS C103 Precasting for Foundation 45 25-Oct-13 09-Dec-13 50 RMS C104 Fencing and Gate Instalaltion 25 19-Nov-13 14-Dec-13 35 RMS C105 Marking and Excavation of the Foundation 20 24-Nov-13 14-Dec-13 36 RMS C106 PCC for Foundation 20 01-Dec-13 21-Dec-13 36 RMS C107 Foundation Installation 30 08-Dec-13 07-Jan-14 36 RMS C108 Foundation Backfilling & Compacting 35 12-May-14 16-Jun-14 36 RMS C109 Cable Trench Excavation 15 16-Jun-14 01-Jul-14 39 RMS C110 Cable Trench Backfilling 10 12-Jul-14 22-Jul-14 45 RMS C111 Grouting, Final Grading & House Keeping 19 22-Jul-14 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical Works 211 22-Nov-13 21-Jun-14 67 RMS M101 Prefabrication of Spools 105 22-Nov-13 07-Mar-14 37 RMS M102 NDT and Repair if any 90 22-Dec-13 22-Mar-14 52 RMS M103 Structure Support Fabrication & Coating 105 22-Nov-13 07-Mar-14 37 RMS M104 Suppot Erection 80 07-Jan-14 28-Mar-14 36 RMS M105 Piping Erection, Welding & Tie In 75 14-Jan-14 30-Mar-14 36 RMS M106 NDT and Repair if any 20 20-Mar-14 09-Apr-14 36 RMS M107 Box Up 25 01-Apr-14 26-Apr-14 36 RMS M108 Hydrotesting 35 05-Apr-14 10-May-14 36 RMS M109 Vent Stack Installation 50 02-May-14 21-Jun-14 67 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument Works 66 11-May-14 16-Jul-14 36 RMS I101 Panel Installation 10 14-Jun-14 24-Jun-14 36 RMS I102 Cable laying 25 17-Jun-14 12-Jul-14 39 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 10. Activity ID Activity Name Original Duration Start Finish Total Float RMS I103 Field Instrument Installation 15 11-May-14 26-May-14 58 RMS I104 Junction Box & Support Installation 20 13-May-14 02-Jun-14 58 RMS I105 Glanding, Tremination & Tubing 22 24-Jun-14 16-Jul-14 36 RMS I106 Actuated Valve Installation 20 17-May-14 06-Jun-14 62 RMS I107 Name Plate Installation 5 24-May-14 29-May-14 62 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical Works 92 25-Apr-14 26-Jul-14 39 RMS E101 Transformer installation (3 nos) 15 25-Apr-14 10-May-14 61 RMS E102 Instrument Air Compressor 5 10-May-14 15-May-14 61 RMS E103 Cable Laying 15 17-Jun-14 02-Jul-14 39 RMS E104 Glanding & Termination 7 04-Jul-14 11-Jul-14 39 RMS E105 Fence Earthing 15 25-Apr-14 10-May-14 66 RMS E106 Equipment Earthing 35 25-May-14 29-Jun-14 51 RMS E107 Panel Energization 15 11-Jul-14 26-Jul-14 39 Harmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil worksHarmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil wo... 227 17-Nov-13 02-Jul-14 50 SS C1001 Earth Work for Containerized Building Foundation 25 17-Nov-13 12-Dec-13 83 SS C1002 Laying of Polythene sheet 3 13-Dec-13 16-Dec-13 83 SS C1003 PCC for the foundation 2 13-Dec-13 15-Dec-13 83 SS C1004 Reinforce work for Foundation 7 15-Dec-13 22-Dec-13 83 SS C1005 Shuttering for Foundation 4 23-Dec-13 27-Dec-13 83 SS C1006 Concreting work for Foundation 3 28-Dec-13 31-Dec-13 83 SS C1007 Deshuttering for Foundation 4 01-Jan-14 05-Jan-14 83 SS C1008 Reinforcement work for Coloumn 4 07-Jan-14 11-Jan-14 83 SS C1009 Shuttering of column 6 12-Jan-14 18-Jan-14 83 SS C1010 Column Concreting 7 18-Jan-14 25-Jan-14 83 SS C1011 Deshuttering for Column 4 26-Jan-14 30-Jan-14 83 SS C1012 Shuttering work for floor beam 20 31-Jan-14 20-Feb-14 83 SS C1013 Reinforcement work for floor beam 20 05-Feb-14 25-Feb-14 83 SS C1014 Concreting for floor beam 3 26-Feb-14 01-Mar-14 83 SS C1015 Deshuttering of floor beam 7 08-Mar-14 15-Mar-14 83 SS C1016 Applying Protective coating 7 16-Mar-14 23-Mar-14 83 SS C1017 Backfilling the foundation 9 23-Mar-14 01-Apr-14 83 SS C1018 Containerized Substation Installation 8 04-May-14 12-May-14 50 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 11. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation WorksHarmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation Works 52 11-May-14 02-Jul-14 50 SS I1000 Installation of Panels 4 11-May-14 15-May-14 51 SS I1010 Installation of Battery Bank 10 15-May-14 25-May-14 52 SS I1020 Installation of DC-DB 7 25-May-14 01-Jun-14 52 SS I1030 Installation of Lighting DB 7 12-May-14 19-May-14 50 SS I1040 Installation of 415 v Switch Board 15 12-May-14 27-May-14 50 SS I1050 Installation of emergency Lighting DB 7 27-May-14 03-Jun-14 50 SS I1060 Installation of HVAC system 29 03-Jun-14 02-Jul-14 50 Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2)Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2) 190 25-Oct-13 03-May-14 110 OHL 1000 Survey & ROW grading 50 25-Oct-13 14-Dec-13 110 OHL 1020 Pole hole drilling 50 14-Dec-13 02-Feb-14 110 OHL 1030 Pole distribution 50 22-Dec-13 10-Feb-14 110 OHL 1040 Dressing 35 15-Feb-14 22-Mar-14 110 OHL 1050 Errectioning 25 20-Feb-14 17-Mar-14 110 OHL 1060 Conductor Stringing 20 24-Feb-14 16-Mar-14 110 OHL 1070 Jumpering 15 16-Mar-14 31-Mar-14 110 OHL 1080 Installation of Field Isolator 14 31-Mar-14 14-Apr-14 110 OHL 1090 Installation of Auto recloser 14 02-Apr-14 16-Apr-14 110 OHL 1100 33 KV Spur Lines from OHL to RMS 14 17-Apr-14 01-May-14 110 OHL 1110 33 KV Underground cabling and Termination 10 23-Apr-14 03-May-14 110 Harmal FD-10-Oct13.3.4.6 Shut Down ActivitiesHarmal FD-10-Oct13.3.4.6 Shut Down Activities 183 25-Sep-13 27-Mar-14 153 Harmal FD-10-Oct13.3.4.6.1.3.3.1 Civil WorksHarmal FD-10-Oct13.3.4.6.1.3.3.1 Civil Works 183 25-Sep-13 27-Mar-14 152 SD C10 Plot Survey and set out 15 25-Sep-13 10-Oct-13 270 SD C20 Precasting for Foundation 15 25-Sep-13 10-Oct-13 287 SD C30 Marking and Excavation of the Foundation 20 11-Oct-13 31-Oct-13 270 SD C40 PCC for Foundation 15 20-Oct-13 04-Nov-13 270 SD C50 Foundation Installation 10 27-Oct-13 06-Nov-13 270 SD C60 Foundation Backfilling & Compacting 15 09-Nov-13 24-Nov-13 270 SD C70 Cable Trench Excavation 20 22-Jan-14 11-Feb-14 156 SD C80 Cable Trench Backfilling 10 08-Mar-14 18-Mar-14 156 SD C90 Grouting, Final Grading & House Keeping 5 22-Mar-14 27-Mar-14 152 Harmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical Works 99 28-Nov-13 07-Mar-14 152 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 12. Activity ID Activity Name Original Duration Start Finish Total Float SD M10 Prefabrication of Spools 55 28-Nov-13 22-Jan-14 152 SD M20 NDT and Repair if any 10 17-Jan-14 27-Jan-14 159 SD M30 Structure Support Fabrication & Coating 30 08-Dec-13 07-Jan-14 152 SD M40 Suppot Erection 30 12-Jan-14 11-Feb-14 152 SD M50 Piping Erection, Welding 15 03-Feb-14 18-Feb-14 152 SD M60 NDT and Repair if any 20 05-Feb-14 25-Feb-14 152 SD M70 Hydrotesting 10 25-Feb-14 07-Mar-14 152 Harmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical Works 25 11-Feb-14 08-Mar-14 156 SD E10 Cable Laying 15 11-Feb-14 26-Feb-14 156 SD E20 Glanding & Termination 10 26-Feb-14 08-Mar-14 156 Harmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument WorksHarmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument Works 41 14-Feb-14 27-Mar-14 153 SD I10 Cable laying 15 14-Feb-14 01-Mar-14 163 SD I20 Field Instrument Installation 10 25-Feb-14 07-Mar-14 152 SD I30 Junction Box & Support Installation 10 27-Feb-14 09-Mar-14 152 SD I40 Glanding, Tremination & Tubing 15 12-Mar-14 27-Mar-14 152 SD I50 ESD Valve Installation 7 01-Mar-14 08-Mar-14 171 SD I60 Name Plate Installation 5 04-Mar-14 09-Mar-14 171 Harmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at KautherHarmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at Kauther 11 17-Mar-14 28-Mar-14 171 Harmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDOHarmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDO 11 17-Mar-14 28-Mar-14 171 SD 1000 Final Shut Down Date from PDO 11 17-Mar-14 28-Mar-14 171 Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1 124 18-Apr-14 20-Aug-14 36 A3170 Punch List Clearance 30 21-Jul-14 20-Aug-14 36 A3180 CP-Testing and Commmision 7 26-Jul-14 02-Aug-14 44 A3190 HVAC system 15 02-Jul-14 17-Jul-14 50 A3200 FOC ODTR Testing 2 21-Jul-14 23-Jul-14 54 A3210 RMS-2 Loop checking works 25 16-Jul-14 10-Aug-14 36 A3220 RMS-2 Electrical Testing 12 26-Jul-14 07-Aug-14 39 A3230 RMS-2 Panel Enegization 10 22-Jul-14 01-Aug-14 45 A3240 Transformer Energization 10 11-Jul-14 21-Jul-14 46 A3250 OHL Relay Setting and Testing 20 18-Apr-14 08-May-14 110 A3260 Pre-Commisioning Completion 10 10-Aug-14 20-Aug-14 36 Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2 686 09-Dec-12 30-Oct-14 90 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 13. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test Installation 682 09-Dec-12 26-Oct-14 23 Harmal FD-10-Oct13.1.1.1.1.1.2 AFC PackageHarmal FD-10-Oct13.1.1.1.1.1.2 AFC Package 210 09-Dec-12 29-Oct-13 55 D0010 Process 320 09-Dec-12 29-Oct-13 0 D0020 Civil 287 14-Jan-13 28-Oct-13 56 D0030 Mechanical and Piping 310 22-Dec-12 29-Oct-13 0 D0040 Electrical 297 31-Dec-12 24-Oct-13 0 D0050 Control and automation 300 29-Dec-12 25-Oct-13 0 Harmal FD-10-Oct13.1.1.1.1 Bulk MTOHarmal FD-10-Oct13.1.1.1.1 Bulk MTO 254 18-Jan-13 29-Sep-13 85 A3620 Civil & Structural 205 19-Feb-13 12-Sep-13 45 A3630 Electrical 235 20-Jan-13 12-Sep-13 45 A3640 Mechanical and Piping 249 23-Jan-13 29-Sep-13 85 A3650 Control and Automation 240 18-Jan-13 15-Sep-13 44 Harmal FD-10-Oct13.1.1.1.2 Project Management and Supporting DocumentsHarmal FD-10-Oct13.1.1.1.2 Project Management and Supporting Documents 642 22-Jan-13 26-Oct-14 23 A3660 Project Management 580 22-Jan-13 25-Aug-14 85 A3670 As Built Packages 35 21-Sep-14 26-Oct-14 4 A3790 SAP 45 22-Aug-14 06-Oct-14 0 A3800 CCMS 45 22-Aug-14 06-Oct-14 0 Harmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test Installation 533 03-Mar-13 18-Aug-14 31 Harmal FD-10-Oct13.1.1.21.5 Test Seperator Installation MaterialsHarmal FD-10-Oct13.1.1.21.5 Test Seperator Installation Materials 533 03-Mar-13 18-Aug-14 31 Harmal FD-10-Oct13.1.1.21.5.1.2.4 ESD ValveHarmal FD-10-Oct13.1.1.21.5.1.2.4 ESD Valve 494 24-Mar-13 31-Jul-14 49 1939 PR Issue 2 24-Mar-13 26-Mar-13 31 1949 Enquiry Floating 14 27-Mar-13 10-Apr-13 49 1959 Receive quotes from Vendors 180 10-Apr-13 07-Oct-13 49 1969 Technical Bid Evaluation 30 07-Oct-13 06-Nov-13 49 1979 Vendor Data and complete commercial 15 06-Nov-13 21-Nov-13 49 1989 Issue of PO 5 21-Nov-13 26-Nov-13 49 1999 Manufacturing of Items 200 27-Nov-13 15-Jun-14 49 2009 Shipping Delivery 30 16-Jun-14 16-Jul-14 49 3189 ESD Valve Receipt at site 10 21-Jul-14 31-Jul-14 49 Harmal FD-10-Oct13.1.1.21.5.1.2.5 Relief ValveHarmal FD-10-Oct13.1.1.21.5.1.2.5 Relief Valve 493 27-Mar-13 02-Aug-14 23 2019 PR Issue 2 27-Mar-13 29-Mar-13 23 2029 Enquiry Floating 14 29-Mar-13 12-Apr-13 23 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 14. Activity ID Activity Name Original Duration Start Finish Total Float 2039 Receive quotes from Vendors 200 13-Apr-13 19-Oct-13 23 2049 Technical Bid Evaluation 16 20-Oct-13 04-Nov-13 23 2059 Vendor Data and complete commercial 16 05-Nov-13 20-Nov-13 23 2069 Issue of PO 7 21-Nov-13 28-Nov-13 23 2079 Manufacturing of Items 200 28-Nov-13 16-Jun-14 23 2089 Shipping Delivery 30 16-Jun-14 16-Jul-14 23 3199 Relief Valve Receipt at Site 10 23-Jul-14 02-Aug-14 23 Harmal FD-10-Oct13.1.1.21.5.1.2.9 Control ValvesHarmal FD-10-Oct13.1.1.21.5.1.2.9 Control Valves 465 16-Mar-13 24-Jun-14 62 2339 PR Issue 2 16-Mar-13 18-Mar-13 62 2349 Enquiry Floating 14 18-Mar-13 01-Apr-13 62 2359 Receive quotes from Vendors 190 01-Apr-13 08-Oct-13 62 2369 Technical Bid Evaluation 16 08-Oct-13 24-Oct-13 62 2379 Vendor Data and complete commercial 12 17-Oct-13 29-Oct-13 62 2389 Issue of PO 7 29-Oct-13 05-Nov-13 62 2399 Manufacturing of Items 184 05-Nov-13 08-May-14 62 2409 Shipping Delivery 30 08-May-14 07-Jun-14 62 3209 Control Valve Receipt at Site 10 14-Jun-14 24-Jun-14 62 Harmal FD-10-Oct13.1.1.21.5.1 Test SeparatorHarmal FD-10-Oct13.1.1.21.5.1 Test Separator 517 03-Mar-13 02-Aug-14 0 A2490 PR Issue 2 03-Mar-13 05-Mar-13 0 A2500 Enquiry Floating 14 05-Mar-13 19-Mar-13 0 A2510 Receive Quotes from Vendor 21 19-Mar-13 09-Apr-13 0 A2520 TBE & Vendor Finilize 195 09-Apr-13 21-Oct-13 0 A2530 Issue of PO 4 21-Oct-13 25-Oct-13 0 A2540 Manufacturing of Items 236 29-Oct-13 22-Jun-14 0 A2550 Inspection & Release 20 22-Jun-14 12-Jul-14 0 A2560 Material Delivery 12 13-Jul-14 25-Jul-14 0 A2820 Test Separator Receipt at Site 7 26-Jul-14 02-Aug-14 0 Harmal FD-10-Oct13.1.1.21.5.2 Piping Materials & FittingsHarmal FD-10-Oct13.1.1.21.5.2 Piping Materials & Fittings 403 26-Mar-13 03-May-14 73 A2850 PR Issue 2 26-Mar-13 28-Mar-13 73 A2860 Enquiry Floating 48 28-Mar-13 15-May-13 73 A2870 Receive Quotes from Vendor 140 15-May-13 02-Oct-13 73 A2880 TBE & Vendor Finilize 88 30-Jul-13 26-Oct-13 73 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 15. Activity ID Activity Name Original Duration Start Finish Total Float A2890 Issue of PO 28 26-Oct-13 23-Nov-13 73 A2900 Manufacturing of Items 136 23-Nov-13 08-Apr-14 73 A2910 Inspection & Release 112 23-Dec-13 14-Apr-14 73 A2920 Material Delivery 112 28-Dec-13 19-Apr-14 73 A2930 Material Receipt at Site 112 11-Jan-14 03-May-14 73 Harmal FD-10-Oct13.1.1.21.5.3 Bulk MaterialsHarmal FD-10-Oct13.1.1.21.5.3 Bulk Materials 413 26-Mar-13 13-May-14 56 A2940 PR Issue 2 26-Mar-13 28-Mar-13 56 A2950 Enquiry Floating 7 29-Mar-13 05-Apr-13 56 A2960 Receive Quotes from Vendor 128 06-Apr-13 12-Aug-13 56 A2970 Vendor Finilize 128 30-Apr-13 05-Sep-13 56 A2980 Issue of PO 48 05-Sep-13 23-Oct-13 56 A2990 Manufacturing of Items 200 12-Sep-13 31-Mar-14 56 A3000 Inspection & Release 200 10-Oct-13 28-Apr-14 56 A3010 Material Receipt at Site 150 14-Dec-13 13-May-14 56 Harmal FD-10-Oct13.1.1.21.5.4 Instrument Air CompressorHarmal FD-10-Oct13.1.1.21.5.4 Instrument Air Compressor 429 28-Mar-13 31-May-14 85 A3020 PR Issue 6 28-Mar-13 03-Apr-13 85 A3030 Enquiry Floating 152 03-Apr-13 02-Sep-13 85 A3040 Receive quotes from Vendors 144 23-Apr-13 14-Sep-13 85 A3050 TBE & Vendor Finilize 136 13-May-13 26-Sep-13 85 A3060 Issue of PO 7 26-Sep-13 03-Oct-13 85 A3070 Manufacturing of Items 160 03-Oct-13 12-Mar-14 85 A3080 Inspection & Release 20 12-Mar-14 01-Apr-14 85 A3090 Material Delivery 20 01-Apr-14 21-Apr-14 85 A3100 Air Compressor Receipt at Site 30 01-May-14 31-May-14 85 Harmal FD-10-Oct13.1.1.21.5.5 Flow MeterHarmal FD-10-Oct13.1.1.21.5.5 Flow Meter 445 24-Mar-13 12-Jun-14 98 A3680 PR Issue 6 24-Mar-13 30-Mar-13 31 A3690 Enquiry Floating 152 30-Mar-13 29-Aug-13 31 A3700 Receive quotes from Vendors 136 23-Apr-13 06-Sep-13 31 A3710 TBE & Vendor Finilize 12 06-Sep-13 18-Sep-13 31 A3720 Issue of PO 7 18-Sep-13 25-Sep-13 31 A3730 Manufacturing of Items 180 25-Sep-13 24-Mar-14 98 A3740 Inspection & Release 20 24-Mar-14 13-Apr-14 98 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 16. Activity ID Activity Name Original Duration Start Finish Total Float A3750 Material Delivery 20 13-Apr-14 03-May-14 98 A3760 Material Receipt at Site 30 13-May-14 12-Jun-14 98 Harmal FD-10-Oct13.1.1.21.5.6 F & G SystemHarmal FD-10-Oct13.1.1.21.5.6 F & G System 334 18-Sep-13 18-Aug-14 31 A3810 PR Issue 25 18-Sep-13 13-Oct-13 31 A3820 Enquiry Floating 60 13-Oct-13 12-Dec-13 31 A3830 Receive quotes from Vendors 60 21-Oct-13 20-Dec-13 31 A3840 TBE & Vendor Finilize 12 20-Dec-13 01-Jan-14 31 A3850 Issue of PO 7 01-Jan-14 08-Jan-14 31 A3860 Manufacturing of Items 150 08-Jan-14 07-Jun-14 31 A3870 Inspection & Release 20 07-Jun-14 27-Jun-14 31 A3880 Material Delivery 20 27-Jun-14 17-Jul-14 31 A3890 Material Receipt at Site 22 27-Jul-14 18-Aug-14 31 Harmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test Installation 197 29-Mar-14 12-Oct-14 107 Harmal FD-10-Oct13.1.2.2 Well Test Seperator InstallationHarmal FD-10-Oct13.1.2.2 Well Test Seperator Installation 197 29-Mar-14 12-Oct-14 107 Harmal FD-10-Oct13.1.2.2.1 Civil WorksHarmal FD-10-Oct13.1.2.2.1 Civil Works 197 29-Mar-14 12-Oct-14 107 WTS C18 Excavation for Foundations 30 29-Apr-14 29-May-14 35 WTS C28 PCC for Foundation 45 01-May-14 15-Jun-14 35 WTS C38 Foundation Installation 45 08-May-14 22-Jun-14 35 WTS C48 Foundation Backfilling & Compaction 30 15-Aug-14 14-Sep-14 136 WTS C58 Excavation for Cable Trench 7 29-May-14 05-Jun-14 96 WTS C68 Cable trench backfilling 7 14-Sep-14 21-Sep-14 2 WTS C78 Grouting, Final Grading and Housekeeping 22 21-Sep-14 12-Oct-14 2 WTS C8 Plot Survey and set out 30 29-Mar-14 28-Apr-14 35 Harmal FD-10-Oct13.1.2.2.2 Mechanical WorksHarmal FD-10-Oct13.1.2.2.2 Mechanical Works 172 11-Apr-14 30-Sep-14 0 WTS M19 Prefabrication of Piping spools 40 11-Apr-14 21-May-14 56 WTS M29 NDT 36 25-Apr-14 31-May-14 56 WTS M39 Spool Hydrotest 32 09-May-14 10-Jun-14 56 WTS M49 Structural support Fabrication & Coating 32 11-Apr-14 13-May-14 82 WTS M59 Structual Support installation 24 22-Jun-14 16-Jul-14 35 WTS M69 Piping Erection 35 05-Aug-14 09-Sep-14 0 WTS M79 Final Hydrotest 7 09-Sep-14 16-Sep-14 0 WTS M89 Valve installation / Nitrogen Purging 14 16-Sep-14 30-Sep-14 0 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 17. Activity ID Activity Name Original Duration Start Finish Total Float WTS M9 Test Separator errection and alignment 3 02-Aug-14 05-Aug-14 0 Harmal FD-10-Oct13.1.2.2.3 Electrical WorksHarmal FD-10-Oct13.1.2.2.3 Electrical Works 27 09-Sep-14 06-Oct-14 0 WTS E13 Cable Glanding & Termination 12 15-Sep-14 27-Sep-14 0 WTS E23 Earthing works for Equipment & Instruments 9 27-Sep-14 06-Oct-14 0 WTS E3 Cable laying 5 09-Sep-14 14-Sep-14 0 Harmal FD-10-Oct13.1.2.2.4 Instrumentation worksHarmal FD-10-Oct13.1.2.2.4 Instrumentation works 65 02-Aug-14 06-Oct-14 0 WTS I14 ESD Valve /Flow meter /F & G system Installation 12 18-Sep-14 30-Sep-14 0 WTS I24 Instrument cable laying & Termination 12 21-Sep-14 03-Oct-14 0 WTS I34 Instrument Tubing works 19 17-Sep-14 06-Oct-14 0 WTS I4 Instruments Calibration 24 02-Aug-14 26-Aug-14 23 Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2 175 08-May-14 30-Oct-14 0 Pre 072 Substation Readiness 15 08-May-14 23-May-14 115 Pre 092 WTS Precommissioning activities 24 06-Oct-14 30-Oct-14 0 Pre 102 Ex- Inspection works 10 10-Oct-14 20-Oct-14 0 Pre 112 Pie - Configuration by PDO 14 06-Oct-14 20-Oct-14 0 Pre 122 Loop Checking 10 20-Oct-14 30-Oct-14 0 Harmal FD-10-Oct13.Comm Support Commissioning SupportHarmal FD-10-Oct13.Comm Support Commissioning Support 161 20-Aug-14 28-Jan-15 0 A3770 Commissioning Support Assistance for Testing Facilities 90 30-Oct-14 28-Jan-15 0 A3780 Commisioning Support Assistance for Production Facilities 90 20-Aug-14 18-Nov-14 36 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone