Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Al MuraqqAl Muraqqabat Mixed Use Development 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0
GeneralGeneral 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0
ContractualContractual Milestones 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0
A1000 Project Commencement Date 0 02-Jan-12 31-Dec-11 0
A1030 Completion Date of Phase 1 0 04-Jul-13 04-Jul-13 0
A1050 Overall Duration of Phase 1 550 02-Jan-12 04-Jul-13 01-Apr-12 02-Oct-13 90
A1010 Completion Date of Phase 2 0 02-Oct-13 02-Oct-13 0
A1020 Overall Duration of Phase 2 640 02-Jan-12 02-Oct-13 02-Jan-12 02-Oct-13 0
Control MileControl Milestones 367 24-Apr-12 08-Jul-13 15-Dec-12 02-Oct-13 74
Civil WorksCivil Works Completion Milestones 158 08-May-12 14-Nov-12 02-Oct-13 02-Oct-13 270
A9066 Completion of Raft Slab (Block A,B,C) 0 08-May-12 02-Oct-13 428
A9067 Completion of Ground Floor Slab (Block A,B,C) 0 23-Jun-12 02-Oct-13 390
A9068 Completion of the Skeleton for Block A 0 17-Sep-12 02-Oct-13 318
A9089 Completion of the Skeleton for Block C 0 30-Oct-12 02-Oct-13 283
A9069 Completion of the Skeleton for Block B 0 14-Nov-12 02-Oct-13 270
ArchitecturaArchitectural Works Milestones 81 24-Apr-12 29-Jul-12 15-Dec-12 16-Dec-12 114
A9182 Start of Block Works @ Basements 0 24-Apr-12 16-Dec-12 195
A9183 Start of Block Works @ 1st Floor 0 29-Jul-12 15-Dec-12 113
Fit Out andFit Out and FF&E Milestones 78 06-Apr-13 08-Jul-13 16-Apr-13 02-Oct-13 74
Fit Out MilestFit Out Milestones 15 06-Apr-13 23-Apr-13 16-Apr-13 28-Apr-13 4
A9360 Completion of Fit Out for Block C 0 06-Apr-13 16-Apr-13 9
A9340 Completion of Fit Out for Block A 0 17-Apr-13 25-Apr-13 7
A9350 Completion of Fit Out for Block B 0 23-Apr-13 28-Apr-13 4
FF & E MilestFF & E Milestones 2 06-Jul-13 08-Jul-13 02-Oct-13 02-Oct-13 74
A9370 Commencement of FF&E @ Block A 0 06-Jul-13 02-Oct-13 76
A1232 Commencement of FF&E @ Block B 0 06-Jul-13 02-Oct-13 76
A1222 Commencement of FF&E @ Block C 0 08-Jul-13 02-Oct-13 74
MEP WorksMEP Works Milestones 67 26-Jan-13 14-Apr-13 05-Mar-13 24-Apr-13 9
A9226 Completion of LPG System 0 26-Jan-13 10-Apr-13 64
A9256 Completion of MEP Works ( Related to Temporary Power) 0 21-Feb-13 05-Mar-13 10
A9196 Completion of Elevators 0 14-Mar-13 23-Mar-13 7
A9216 Completion of Garbage & Linen Chute 0 14-Apr-13 24-Apr-13 9
Facade WorFacade Works Milestones 69 02-Apr-13 23-Jun-13 04-Jul-13 04-Jul-13 10
A9236 Completion of Facade Cleaning System 0 02-Apr-13 04-Jul-13 79
A9206 Completion of Facade Glazing 0 22-Jun-13 04-Jul-13 11
A9246 Completion of Facade Lighting System 0 23-Jun-13 04-Jul-13 10
Authorities AAuthorities Approvals 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10
SwimmimngSwimmimng Pool 86 08-Jul-12 17-Oct-12 17-Jul-12 01-Nov-12 11
A1435 EHS Approval for Pouring Pools Slab - Block B 10 08-Jul-12 18-Jul-12 17-Jul-12 28-Jul-12 8
A1436 EHS Approval for Pouring Pools Slab - Block A 10 27-Aug-12 06-Sep-12 10-Sep-12 20-Sep-12 12
A1438 EHS Approval for Pouring Pools Slab - Block C 10 07-Oct-12 17-Oct-12 20-Oct-12 01-Nov-12 11
Temporary PTemporary Power Connection 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10
A1348 Receipt of Design NOC for Electrical Drawings 0 30-Jan-12 17-Mar-12 39
A1358 Confirmation of RMU & Transformers Rooms Layout 0 30-Jan-12 17-Jul-12 143
A1368 Submission & Approval of Electrical Drawings 25 02-Jun-12 01-Jul-12 18-Jul-12 15-Aug-12 39
A1408 Application for Fee Estimation 11 21-Jul-12 01-Aug-12 13-Oct-12 24-Oct-12 70
A1418 Fee Payment by Client to DEWA 12 02-Aug-12 15-Aug-12 28-Oct-12 10-Nov-12 70
A1378 Substation Inspection Invitation to DEWA 6 01-Oct-12 07-Oct-12 09-Mar-13 14-Mar-13 130
A1388 Civil Work Inspection by DEWA 6 08-Oct-12 14-Oct-12 16-Mar-13 21-Mar-13 130
A1398 Approval & Handover Substations to DEWA 0 14-Oct-12 21-Mar-13 130
A1428 Delivery- Installation - Termination of Transformers - RMU 0 27-Dec-12 21-Mar-13 70
A1458 Invitation to DEWA for MEP Work Inspection 2 23-Feb-13 24-Feb-13 06-Mar-13 07-Mar-13 10
A1468 1st MEP Inspection & Comments by DEWA 2 25-Feb-13 26-Feb-13 09-Mar-13 10-Mar-13 10
A1478 Attend DEWA Comments 10 27-Feb-13 10-Mar-13 11-Mar-13 21-Mar-13 10
A1488 Final MEP Inspection & Approval By DEWA 1 11-Mar-13 11-Mar-13 23-Mar-13 23-Mar-13 10
A1518 Release DEWA Temporary Power for T & C 0 11-Mar-13 23-Mar-13 10
Utilities ConUtilities Connection 118 16-Feb-13 04-Jul-13 26-Mar-13 04-Jul-13 0
Gas ConnecGas Connection 0 28-Feb-13 28-Feb-13 26-Mar-13 26-Mar-13 22
A2970 Gas Supply Connection 0 28-Feb-13 26-Mar-13 22
Water SuppWater Supply Connection 0 07-Mar-13 07-Mar-13 01-May-13 01-May-13 47
A2950 Water Supply Connection 0 07-Mar-13 01-May-13 47
Sewage ConSewage Connection 0 16-Feb-13 16-Feb-13 16-Apr-13 16-Apr-13 51
A2960 Sewage Connection 0 16-Feb-13 16-Apr-13 51
PermenanetPermenanet Power Connection 0 04-Jul-13 04-Jul-13 04-Jul-13 04-Jul-13 0
A1528 Release of Permanent Power By DEWA 0 04-Jul-13 04-Jul-13 0
Client SubmClient Submissions 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43
Awarding ofAwarding of Provisional Sum Packages 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43
A1456 Awarding of Kitchen Equipments Package to ASGC 0 15-Apr-12 30-Apr-12 13
A1466 Awarding of Laundry Equipments Package to ASGC 0 15-Apr-12 29-Apr-12 12
A1476 Awarding of Facade Lighting Package to ASGC 0 21-Apr-12 14-May-12 20
A1489 Awarding of Cooking StationPackage to ASGC 0 30-Apr-12 14-Aug-12 90
A1486 Awarding of Gymnasium Equipments Package to ASGC 0 30-Dec-12 20-Feb-13 43
Technical DTechnical Data for Prime Cost Items 134 23-May-12 31-Oct-12 23-Sep-12 02-Feb-13 76
A1257 Submit the Techincal Data for Porcalin Tiles 7 23-May-12 30-May-12 23-Sep-12 30-Sep-12 102
A1247 Submit the Techincal Data for Ironmongery 7 24-Jul-12 31-Jul-12 10-Jan-13 17-Jan-13 139
A1277 Submit the Techincal Data for Wooden Parquet 7 24-Jul-12 31-Jul-12 19-Dec-12 26-Dec-12 121
A1267 Submit the Techincal Data for Carpet 7 23-Sep-12 30-Sep-12 15-Dec-12 22-Dec-12 67
A1287 Submit the Techincal Data for Kitchen Appliances 7 22-Oct-12 31-Oct-12 26-Jan-13 02-Feb-13 76
MobilizationMobilization 121 02-Jan-12 22-May-12 22-Jan-12 06-Jun-12 13
Project SiteProject Site 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17
A8950 Installation of Site Gate 5 02-Jan-12 07-Jan-12 02-Feb-12 08-Feb-12 27
A5490 Installation of Project Signboard 6 02-Jan-12 08-Jan-12 01-Feb-12 08-Feb-12 26
A5460 Installation of Generator 7 02-Jan-12 09-Jan-12 23-Jan-12 30-Jan-12 18
A5410 Installation of Fence 8 02-Jan-12 10-Jan-12 30-Jan-12 08-Feb-12 24
A5480 Installation of Store Yard 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22
A8920 Installation of Workshop 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22
A5470 Installation of Septic Tank & Water Tank 7 10-Jan-12 17-Jan-12 31-Jan-12 08-Feb-12 18
A5450 Installation of Site Offices 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17
Tower CraneTower Cranes 85 14-Feb-12 22-May-12 05-Mar-12 06-Jun-12 13
A5420 Installation of Tower Crane 1 12 14-Feb-12 27-Feb-12 05-Mar-12 18-Mar-12 17
A5467 Installation of Tower Crane 4 12 22-Feb-12 06-Mar-12 28-Apr-12 10-May-12 56
A5430 Installation of Tower Crane 2 12 28-Apr-12 10-May-12 24-May-12 06-Jun-12 23
A5440 Installation of Tower Crane 3 12 09-May-12 22-May-12 24-May-12 06-Jun-12 13
EngineerinEngineering 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19
Shop DrawinShop Drawings 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Project Commencement Date
Completion Date of Phase 1
Overall Duration of Phase 1
Completion Date
Overall Duration
Completion of Raft Slab (Block A,B,C)
Completion of Ground Floor Slab (Block A,B,C)
Completion of the Skeleton for Block A
Completion of the Skeleton for Block C
Completion of the Skeleton for Block B
Start of Block Works @ Basements
Start of Block Works @ 1st Floor
Completion of Fit Out for Block C
Completion of Fit Out for Block A
Completion of Fit Out for Block B
Commencement of FF&E @ Block
Commencement of FF&E @ Block
Commencement of FF&E @ Block
Completion of LPG System
Completion of MEP Works ( Related to Temporary Power)
Completion of Elevators
Completion of Garbage & Linen Chute
Completion of Facade Cleaning System
Completion of Facade Glazing
Completion of Facade Lighting Syste
EHS Approval for Pouring Pools Slab - Block B
EHS Approval for Pouring Pools Slab - Block A
EHS Approval for Pouring Pools Slab - Block C
Receipt of Design NOC for Electrical Drawings
Confirmation of RMU & Transformers Rooms Layout
Submission & Approval of Electrical Drawings
Application for Fee Estimation
Fee Payment by Client to DEWA
Substation Inspection Invitation to DEWA
Civil Work Inspection by DEWA
Approval & Handover Substations to DEWA
Delivery- Installation - Termination of Transformers - RMU
Invitation to DEWA for MEP Work Inspection
1st MEP Inspection & Comments by DEWA
Attend DEWA Comments
Final MEP Inspection & Approval By DEWA
Release DEWA Temporary Power for T & C
Gas Supply Connection
Water Supply Connection
Sewage Connection
Release of Permanent Power By D
Awarding of Kitchen Equipments Package to ASGC
Awarding of Laundry Equipments Package to ASGC
Awarding of Facade Lighting Package to ASGC
Awarding of Cooking StationPackage to ASGC
Awarding of Gymnasium Equipments Package to ASGC
Submit the Techincal Data for Porcalin Tiles
Submit the Techincal Data for Ironmongery
Submit the Techincal Data for Wooden Parquet
Submit the Techincal Data for Carpet
Submit the Techincal Data for Kitchen Appliances
Installation of Site Gate
Installation of Project Signboard
Installation of Generator
Installation of Fence
Installation of Store Yard
Installation of Workshop
Installation of Septic Tank & Water Tank
Installation of Site Offices
Installation of Tower Crane 1
Installation of Tower Crane 4
Installation of Tower Crane 2
Installation of Tower Crane 3
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 1 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
CivilCivil 296 02-Jan-12 20-Dec-12 02-Jan-12 23-May-13 130
GeneralGeneral 35 02-Jan-12 12-Feb-12 02-Jan-12 04-Mar-12 18
SubmissionSubmission 19 02-Jan-12 23-Jan-12 02-Jan-12 13-Feb-12 17
A46740 Submission of Excavation Level 1 02-Jan-12 02-Jan-12 02-Jan-12 02-Jan-12 0
A46770 Submission of Raft Construction Joint Layout 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0
A46750 Submission of Water Proofing Details 7 02-Jan-12 09-Jan-12 02-Jan-12 09-Jan-12 0
A46760 Submission of Tower Crane Layout 7 10-Jan-12 17-Jan-12 06-Feb-12 13-Feb-12 22
A46780 Submission of Retaining Wall Joint Layout 7 16-Jan-12 23-Jan-12 18-Jan-12 25-Jan-12 2
ApprovalApproval 29 03-Jan-12 12-Feb-12 03-Jan-12 04-Mar-12 15
A117180 Approval of Excavation Level 1 03-Jan-12 03-Jan-12 03-Jan-12 03-Jan-12 0
A117190 Approval of Water Proofing Details 7 10-Jan-12 18-Jan-12 10-Jan-12 18-Jan-12 0
A117210 Approval of Raft Construction Joint Layout 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0
A117200 Approval of Tower Crane Layout 14 18-Jan-12 06-Feb-12 14-Feb-12 04-Mar-12 19
A117220 Approval of Retaining Wall Joint Layout 14 24-Jan-12 12-Feb-12 26-Jan-12 14-Feb-12 2
Hotel ApartemHotel Apartements (Block A) 219 02-Jan-12 17-Sep-12 02-Jan-12 23-May-13 207
Deep FoundDeep Foundation 20 02-Jan-12 24-Jan-12 02-Jan-12 24-Jan-12 0
SubmissionSubmission 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0
A46720 Submission of Structural Dwgs. for Raft 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0
ApprovalApproval 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0
A46730 Approval of Structural Dwgs. for Raft 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0
1st Baseme1st Basement Floor Slab 60 11-Jan-12 21-Mar-12 15-Jan-12 06-Sep-12 142
SubmissionSubmission 44 11-Jan-12 03-Mar-12 15-Jan-12 15-Aug-12 141
A101070 Submission of Structural Dwgs. for Ret. Walls -Columns 7 11-Jan-12 18-Jan-12 15-Jan-12 22-Jan-12 3
A101080 Submission of Structural Dwgs. for Core Walls 7 16-Jan-12 23-Jan-12 21-Jan-12 28-Jan-12 4
A101060 Submission of Structural Dwgs. for Slab 7 19-Jan-12 26-Jan-12 23-Jan-12 30-Jan-12 3
A101090 Submission of Structural Dwgs. for Ramp 7 19-Jan-12 26-Jan-12 29-Jan-12 06-Feb-12 8
A101140 Submission of Structural Dwgs. for Staircase 7 25-Feb-12 03-Mar-12 08-Aug-12 15-Aug-12 141
ApprovalApproval 45 19-Jan-12 21-Mar-12 26-Jan-12 06-Sep-12 118
A101110 Approval of Structural Dwgs. for Ret. Walls -Columns 14 19-Jan-12 07-Feb-12 26-Jan-12 14-Feb-12 5
A101120 Approval of Structural Dwgs. for Core Walls 14 24-Jan-12 12-Feb-12 29-Jan-12 15-Feb-12 3
A101100 Approval of Structural Dwgs. for Slab 14 29-Jan-12 15-Feb-12 31-Jan-12 19-Feb-12 2
A101130 Approval of Structural Dwgs. for Ramp 14 29-Jan-12 15-Feb-12 07-Feb-12 26-Feb-12 7
A101150 Approval of Structural Dwgs. for Staircase 14 04-Mar-12 21-Mar-12 16-Aug-12 06-Sep-12 118
Ground FloGround Floor Slab 66 31-Jan-12 17-Apr-12 06-Feb-12 11-Sep-12 123
SubmissionSubmission 49 31-Jan-12 28-Mar-12 06-Feb-12 22-Aug-12 123
A101170 Submission of Structural Dwgs. for Ret. Walls -Columns 7 31-Jan-12 08-Feb-12 06-Feb-12 13-Feb-12 4
A101180 Submission of Structural Dwgs. for Core Walls 7 31-Jan-12 08-Feb-12 15-Feb-12 22-Feb-12 12
A102200 Submission of Structural Dwgs. for Ramp 7 07-Feb-12 14-Feb-12 26-Feb-12 04-Mar-12 16
A101160 Submission of Structural Dwgs. for Slab 7 15-Feb-12 22-Feb-12 20-Feb-12 27-Feb-12 4
A101240 Submission of Structural Dwgs. for Staircase 7 21-Mar-12 28-Mar-12 13-Aug-12 22-Aug-12 123
ApprovalApproval 49 09-Feb-12 17-Apr-12 22-Feb-12 11-Sep-12 102
A101210 Approval of Structural Dwgs. for Ret. Walls -Columns 14 09-Feb-12 28-Feb-12 22-Feb-12 12-Mar-12 9
A101220 Approval of Structural Dwgs. for Core Walls 14 09-Feb-12 28-Feb-12 23-Feb-12 13-Mar-12 10
A102210 Approval of Structural Dwgs. for Ramp 14 15-Feb-12 05-Mar-12 05-Mar-12 22-Mar-12 13
A101200 Approval of Structural Dwgs. for Slab 14 23-Feb-12 13-Mar-12 28-Feb-12 18-Mar-12 3
A101250 Approval of Structural Dwgs. for Staircase 14 29-Mar-12 17-Apr-12 23-Aug-12 11-Sep-12 102
1st Floor Sl1st Floor Slab 61 04-Mar-12 13-May-12 11-Mar-12 13-Sep-12 103
SubmissionSubmission 44 04-Mar-12 23-Apr-12 11-Mar-12 26-Aug-12 104
A101270 Submission of Structural Dwgs. for Columns 7 04-Mar-12 11-Mar-12 11-Mar-12 18-Mar-12 6
A101280 Submission of Structural Dwgs. for Core Walls 7 04-Mar-12 11-Mar-12 11-Mar-12 18-Mar-12 6
A101260 Submission of Structural Dwgs. for Slab 7 12-Mar-12 19-Mar-12 19-Mar-12 26-Mar-12 6
A101340 Submission of Structural Dwgs. for Staircase 7 16-Apr-12 23-Apr-12 16-Aug-12 26-Aug-12 104
ApprovalApproval 45 12-Mar-12 13-May-12 21-Mar-12 13-Sep-12 86
A101310 Approval of Structural Dwgs. for Columns 14 12-Mar-12 29-Mar-12 21-Mar-12 09-Apr-12 7
A101320 Approval of Structural Dwgs. for Core Walls 14 12-Mar-12 29-Mar-12 21-Mar-12 09-Apr-12 7
A101300 Approval of Structural Dwgs. for Slab 14 20-Mar-12 08-Apr-12 27-Mar-12 15-Apr-12 5
A101350 Approval of Structural Dwgs. for Staircase 14 24-Apr-12 13-May-12 27-Aug-12 13-Sep-12 86
2nd Floor S2nd Floor Slab 60 24-Mar-12 31-May-12 02-Apr-12 25-Sep-12 97
SubmissionSubmission 44 24-Mar-12 13-May-12 02-Apr-12 05-Sep-12 96
A102230 Submission of Structural Dwgs. for Columns 7 24-Mar-12 31-Mar-12 02-Apr-12 09-Apr-12 8
A102240 Submission of Structural Dwgs. for Core Walls 7 24-Mar-12 31-Mar-12 08-Apr-12 15-Apr-12 13
A102220 Submission of Structural Dwgs. for Slab 7 01-Apr-12 08-Apr-12 16-Apr-12 23-Apr-12 13
A102280 Submission of Structural Dwgs. for Staircase 7 06-May-12 13-May-12 29-Aug-12 05-Sep-12 96
ApprovalApproval 45 01-Apr-12 31-May-12 18-Apr-12 25-Sep-12 80
A102260 Approval of Structural Dwgs. for Columns 14 01-Apr-12 18-Apr-12 18-Apr-12 07-May-12 13
A102270 Approval of Structural Dwgs. for Core Walls 14 01-Apr-12 18-Apr-12 18-Apr-12 07-May-12 13
A102250 Approval of Structural Dwgs. for Slab 14 09-Apr-12 26-Apr-12 24-Apr-12 13-May-12 11
A102290 Approval of Structural Dwgs. for Staircase 14 14-May-12 31-May-12 06-Sep-12 25-Sep-12 80
3rd & 4th Fl3rd & 4th Floor Slab 61 18-Apr-12 28-Jun-12 28-Apr-12 02-Oct-12 80
SubmissionSubmission 44 18-Apr-12 07-Jun-12 28-Apr-12 12-Sep-12 80
A101370 Submission of Structural Dwgs. for Columns 7 18-Apr-12 25-Apr-12 28-Apr-12 05-May-12 8
A101380 Submission of Structural Dwgs. for Core Walls 7 18-Apr-12 25-Apr-12 05-May-12 12-May-12 14
A101360 Submission of Structural Dwgs. for Slab 7 26-Apr-12 03-May-12 13-May-12 20-May-12 14
A101440 Submission of Structural Dwgs. for Staircase 7 31-May-12 07-Jun-12 05-Sep-12 12-Sep-12 80
ApprovalApproval 45 26-Apr-12 28-Jun-12 16-May-12 02-Oct-12 66
A101410 Approval of Structural Dwgs. for Columns 14 26-Apr-12 15-May-12 16-May-12 04-Jun-12 14
A101420 Approval of Structural Dwgs. for Core Walls 14 26-Apr-12 15-May-12 16-May-12 04-Jun-12 14
A101400 Approval of Structural Dwgs. for Slab 14 06-May-12 23-May-12 21-May-12 07-Jun-12 11
A101450 Approval of Structural Dwgs. for Staircase 14 10-Jun-12 28-Jun-12 13-Sep-12 02-Oct-12 66
5th & 6th Fl5th & 6th Floor Slab 60 31-May-12 09-Aug-12 10-Jun-12 16-Oct-12 56
SubmissionSubmission 44 31-May-12 22-Jul-12 10-Jun-12 26-Sep-12 55
A102390 Submission of Structural Dwgs. for Columns 7 31-May-12 07-Jun-12 10-Jun-12 18-Jun-12 8
A102400 Submission of Structural Dwgs. for Core Walls 7 31-May-12 07-Jun-12 10-Jun-12 18-Jun-12 8
A102380 Submission of Structural Dwgs. for Slab 7 09-Jun-12 16-Jun-12 19-Jun-12 26-Jun-12 8
A102440 Submission of Structural Dwgs. for Staircase 7 15-Jul-12 22-Jul-12 19-Sep-12 26-Sep-12 55
ApprovalApproval 44 10-Jun-12 09-Aug-12 25-Jun-12 16-Oct-12 46
A102420 Approval of Structural Dwgs. for Columns 14 10-Jun-12 28-Jun-12 25-Jun-12 12-Jul-12 10
A102430 Approval of Structural Dwgs. for Core Walls 14 10-Jun-12 28-Jun-12 25-Jun-12 12-Jul-12 10
A102410 Approval of Structural Dwgs. for Slab 14 18-Jun-12 05-Jul-12 27-Jun-12 16-Jul-12 7
A102450 Approval of Structural Dwgs. for Staircase 14 23-Jul-12 09-Aug-12 27-Sep-12 16-Oct-12 46
7th Floor Sl7th Floor Slab 51 27-Jun-12 27-Aug-12 12-Jul-12 04-Nov-12 57
SubmissionSubmission 34 27-Jun-12 05-Aug-12 12-Jul-12 14-Oct-12 58
A102470 Submission of Structural Dwgs. for Columns 7 27-Jun-12 04-Jul-12 12-Jul-12 19-Jul-12 13
A102480 Submission of Structural Dwgs. for Core Walls 7 27-Jun-12 04-Jul-12 14-Jul-12 21-Jul-12 14
A102460 Submission of Structural Dwgs. for Slab 7 05-Jul-12 12-Jul-12 22-Jul-12 29-Jul-12 14
A102520 Submission of Structural Dwgs. for Staircase 7 29-Jul-12 05-Aug-12 07-Oct-12 14-Oct-12 58
ApprovalApproval 36 05-Jul-12 27-Aug-12 24-Jul-12 04-Nov-12 48
A102500 Approval of Structural Dwgs. for Columns 14 05-Jul-12 24-Jul-12 24-Jul-12 12-Aug-12 13
A102510 Approval of Structural Dwgs. for Core Walls 14 05-Jul-12 24-Jul-12 24-Jul-12 12-Aug-12 13
A102490 Approval of Structural Dwgs. for Slab 14 15-Jul-12 01-Aug-12 30-Jul-12 16-Aug-12 11
A102530 Approval of Structural Dwgs. for Staircase 14 06-Aug-12 27-Aug-12 15-Oct-12 04-Nov-12 48
Roof FloorRoof Floor Slab 45 14-Jul-12 05-Sep-12 29-Jul-12 23-May-13 217
SubmissionSubmission 28 14-Jul-12 14-Aug-12 29-Jul-12 05-May-13 218
A101470 Submission of Structural Dwgs. for Columns 7 14-Jul-12 21-Jul-12 29-Jul-12 05-Aug-12 13
A101480 Submission of Structural Dwgs. for Core Walls 7 14-Jul-12 21-Jul-12 30-Jul-12 06-Aug-12 14
A101460 Submission of Structural Dwgs. for Slab 7 22-Jul-12 29-Jul-12 07-Aug-12 14-Aug-12 14
A101540 Submission of Structural Dwgs. for Staircase 7 22-Jul-12 29-Jul-12 10-Nov-12 18-Nov-12 91
A117120 Submission of Structural Dwgs. for Chillers Foundations 14 22-Jul-12 06-Aug-12 04-Oct-12 20-Oct-12 62
A117020 Submission of Structural Dwgs. for Parapets 14 30-Jul-12 14-Aug-12 20-Apr-13 05-May-13 218
ApprovalApproval 32 22-Jul-12 05-Sep-12 08-Aug-12 23-May-13 181
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Excavation Level
Submission of Raft Construction Joint Layout
Submission of Water Proofing Details
Submission of Tower Crane Layout
Submission of Retaining Wall Joint Layout
Approval of Excavation Level
Approval of Water Proofing Details
Approval of Raft Construction Joint Layout
Approval of Tower Crane Layout
Approval of Retaining Wall Joint Layout
Submission of Structural Dwgs. for Raft
Approval of Structural Dwgs. for Raft
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Ramp
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Ramp
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Ramp
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Ramp
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Chillers Foundations
Submission of Structural Dwgs. for Parapets
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 2 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A101510 Approval of Structural Dwgs. for Columns 14 22-Jul-12 08-Aug-12 12-Aug-12 02-Sep-12 15
A101520 Approval of Structural Dwgs. for Core Walls 14 22-Jul-12 08-Aug-12 08-Aug-12 29-Aug-12 13
A101500 Approval of Structural Dwgs. for Slab 14 30-Jul-12 16-Aug-12 15-Aug-12 05-Sep-12 12
A101550 Approval of Structural Dwgs. for Staircase 14 30-Jul-12 16-Aug-12 19-Nov-12 09-Dec-12 76
A117130 Approval of Structural Dwgs. for Chillers Foundations 14 07-Aug-12 28-Aug-12 21-Oct-12 08-Nov-12 51
A117010 Approval of Structural Dwgs. for Parapets 14 15-Aug-12 05-Sep-12 06-May-13 23-May-13 181
Upper RoofUpper Roof Floor Slab 40 31-Jul-12 17-Sep-12 15-Aug-12 13-Feb-13 122
SubmissionSubmission 23 31-Jul-12 28-Aug-12 15-Aug-12 26-Jan-13 123
A101570 Submission of Structural Dwgs. for Columns 7 31-Jul-12 07-Aug-12 15-Aug-12 25-Aug-12 13
A101560 Submission of Structural Dwgs. for Slab 7 08-Aug-12 15-Aug-12 26-Aug-12 02-Sep-12 13
A101640 Submission of Structural Dwgs. for Staircase 7 21-Aug-12 28-Aug-12 17-Jan-13 26-Jan-13 123
ApprovalApproval 27 08-Aug-12 17-Sep-12 28-Aug-12 13-Feb-13 102
A101610 Approval of Structural Dwgs. for Columns 14 08-Aug-12 29-Aug-12 28-Aug-12 16-Sep-12 12
A101600 Approval of Structural Dwgs. for Slab 14 16-Aug-12 06-Sep-12 03-Sep-12 20-Sep-12 10
A101650 Approval of Structural Dwgs. for Staircase 14 29-Aug-12 17-Sep-12 27-Jan-13 13-Feb-13 102
Hotel (BlockHotel (Block B) 270 01-Feb-12 20-Dec-12 15-Feb-12 23-May-13 130
Deep FoundDeep Foundation 24 01-Feb-12 29-Feb-12 15-Feb-12 12-Apr-12 37
SubmissionSubmission 7 01-Feb-12 09-Feb-12 15-Feb-12 22-Feb-12 11
A102540 Submission of Structural Dwgs. for Raft 7 01-Feb-12 09-Feb-12 15-Feb-12 22-Feb-12 11
ApprovalApproval 14 12-Feb-12 29-Feb-12 26-Mar-12 12-Apr-12 31
A102550 Approval of Structural Dwgs. for Raft 14 12-Feb-12 29-Feb-12 26-Mar-12 12-Apr-12 31
1st Baseme1st Basement Floor Slab 67 22-Feb-12 09-May-12 06-Mar-12 17-Jan-13 209
SubmissionSubmission 51 22-Feb-12 21-Apr-12 06-Mar-12 29-Dec-12 209
A102570 Submission of Structural Dwgs. for Ret. Walls -Columns 7 22-Feb-12 29-Feb-12 06-Mar-12 13-Mar-12 11
A102580 Submission of Structural Dwgs. for Core Walls 7 22-Feb-12 29-Feb-12 07-Apr-12 14-Apr-12 38
A104100 Submission of Structural Dwgs. for Water Tank 7 25-Feb-12 03-Mar-12 09-Apr-12 16-Apr-12 38
A102590 Submission of Structural Dwgs. for Ramp 7 01-Mar-12 08-Mar-12 07-Apr-12 14-Apr-12 31
A102560 Submission of Structural Dwgs. for Slab 7 10-Mar-12 17-Mar-12 15-Apr-12 22-Apr-12 31
A102640 Submission of Structural Dwgs. for Staircase 7 14-Apr-12 21-Apr-12 22-Dec-12 29-Dec-12 209
ApprovalApproval 50 01-Mar-12 09-May-12 16-Apr-12 17-Jan-13 174
A102610 Approval of Structural Dwgs. for Ret. Walls -Columns 14 01-Mar-12 20-Mar-12 16-Apr-12 03-May-12 32
A102620 Approval of Structural Dwgs. for Core Walls 14 01-Mar-12 20-Mar-12 18-Apr-12 07-May-12 34
A104110 Approval of Structural Dwgs. for Water Tank 14 04-Mar-12 21-Mar-12 17-Apr-12 06-May-12 32
A102630 Approval of Structural Dwgs. for Ramp 14 11-Mar-12 28-Mar-12 01-May-12 20-May-12 37
A102600 Approval of Structural Dwgs. for Slab 14 18-Mar-12 04-Apr-12 23-Apr-12 10-May-12 26
A102650 Approval of Structural Dwgs. for Staircase 14 22-Apr-12 09-May-12 30-Dec-12 17-Jan-13 174
Ground FloGround Floor Slab 66 17-Apr-12 03-Jul-12 30-Apr-12 23-Jan-13 168
SubmissionSubmission 49 17-Apr-12 12-Jun-12 30-Apr-12 05-Jan-13 169
A102670 Submission of Structural Dwgs. for Ret. Walls -Columns 7 17-Apr-12 24-Apr-12 30-Apr-12 07-May-12 11
A102680 Submission of Structural Dwgs. for Core Walls 7 17-Apr-12 24-Apr-12 03-May-12 10-May-12 14
A103060 Submission of Structural Dwgs. for Ramp 7 17-Apr-12 24-Apr-12 20-May-12 27-May-12 28
A102660 Submission of Structural Dwgs. for Slab 7 25-Apr-12 02-May-12 12-May-12 19-May-12 14
A102720 Submission of Structural Dwgs. for Staircase 7 05-Jun-12 12-Jun-12 27-Dec-12 05-Jan-13 169
ApprovalApproval 49 25-Apr-12 03-Jul-12 14-May-12 23-Jan-13 140
A102700 Approval of Structural Dwgs. for Ret. Walls -Columns 14 25-Apr-12 14-May-12 14-May-12 31-May-12 13
A102710 Approval of Structural Dwgs. for Core Walls 14 25-Apr-12 14-May-12 15-May-12 03-Jun-12 14
A103070 Approval of Structural Dwgs. for Ramp 14 25-Apr-12 14-May-12 28-May-12 14-Jun-12 23
A102690 Approval of Structural Dwgs. for Slab 14 03-May-12 22-May-12 20-May-12 06-Jun-12 11
A102730 Approval of Structural Dwgs. for Staircase 14 13-Jun-12 03-Jul-12 06-Jan-13 23-Jan-13 140
1st Floor Sl1st Floor Slab 70 13-May-12 02-Aug-12 26-May-12 18-Feb-13 163
SubmissionSubmission 54 13-May-12 15-Jul-12 26-May-12 29-Jan-13 162
A102750 Submission of Structural Dwgs. for Columns 7 13-May-12 20-May-12 26-May-12 02-Jun-12 11
A102760 Submission of Structural Dwgs. for Core Walls 7 13-May-12 20-May-12 31-May-12 07-Jun-12 16
A102740 Submission of Structural Dwgs. for Slab 7 21-May-12 28-May-12 09-Jun-12 16-Jun-12 16
A102800 Submission of Structural Dwgs. for Staircase 7 08-Jul-12 15-Jul-12 21-Jan-13 29-Jan-13 162
ApprovalApproval 53 21-May-12 02-Aug-12 11-Jun-12 18-Feb-13 135
A102780 Approval of Structural Dwgs. for Columns 14 21-May-12 07-Jun-12 11-Jun-12 01-Jul-12 15
A102790 Approval of Structural Dwgs. for Core Walls 14 21-May-12 07-Jun-12 11-Jun-12 01-Jul-12 15
A102770 Approval of Structural Dwgs. for Slab 14 29-May-12 18-Jun-12 18-Jun-12 05-Jul-12 13
A102810 Approval of Structural Dwgs. for Staircase 14 16-Jul-12 02-Aug-12 30-Jan-13 18-Feb-13 135
2nd Floor S2nd Floor Slab 81 07-Jun-12 12-Sep-12 21-Jun-12 18-Feb-13 130
SubmissionSubmission 64 07-Jun-12 23-Aug-12 21-Jun-12 29-Jan-13 130
A103090 Submission of Structural Dwgs. for Columns 7 07-Jun-12 14-Jun-12 21-Jun-12 28-Jun-12 11
A103100 Submission of Structural Dwgs. for Core Walls 7 07-Jun-12 14-Jun-12 23-Jun-12 30-Jun-12 12
A103080 Submission of Structural Dwgs. for Slab 7 16-Jun-12 24-Jun-12 01-Jul-12 08-Jul-12 12
A103140 Submission of Structural Dwgs. for Staircase 7 14-Aug-12 23-Aug-12 21-Jan-13 29-Jan-13 130
ApprovalApproval 61 18-Jun-12 12-Sep-12 04-Jul-12 18-Feb-13 108
A103120 Approval of Structural Dwgs. for Columns 14 18-Jun-12 05-Jul-12 04-Jul-12 23-Jul-12 12
A103130 Approval of Structural Dwgs. for Core Walls 14 18-Jun-12 05-Jul-12 04-Jul-12 23-Jul-12 12
A103110 Approval of Structural Dwgs. for Slab 14 25-Jun-12 12-Jul-12 09-Jul-12 26-Jul-12 10
A103150 Approval of Structural Dwgs. for Staircase 14 26-Aug-12 12-Sep-12 30-Jan-13 18-Feb-13 108
3rd & 4th Fl3rd & 4th Floor Slab 81 04-Jul-12 08-Oct-12 17-Jul-12 27-Jan-13 89
SubmissionSubmission 64 04-Jul-12 18-Sep-12 17-Jul-12 06-Jan-13 89
A102830 Submission of Structural Dwgs. for Columns 7 04-Jul-12 11-Jul-12 17-Jul-12 24-Jul-12 11
A102840 Submission of Structural Dwgs. for Core Walls 7 04-Jul-12 11-Jul-12 17-Jul-12 24-Jul-12 11
A102820 Submission of Structural Dwgs. for Slab 7 12-Jul-12 19-Jul-12 25-Jul-12 01-Aug-12 11
A102880 Submission of Structural Dwgs. for Staircase 7 11-Sep-12 18-Sep-12 29-Dec-12 06-Jan-13 89
ApprovalApproval 61 12-Jul-12 08-Oct-12 30-Jul-12 27-Jan-13 74
A102860 Approval of Structural Dwgs. for Columns 14 12-Jul-12 31-Jul-12 30-Jul-12 16-Aug-12 12
A102870 Approval of Structural Dwgs. for Core Walls 14 12-Jul-12 31-Jul-12 30-Jul-12 16-Aug-12 12
A102850 Approval of Structural Dwgs. for Slab 14 22-Jul-12 08-Aug-12 02-Aug-12 23-Aug-12 9
A102890 Approval of Structural Dwgs. for Staircase 14 19-Sep-12 08-Oct-12 07-Jan-13 27-Jan-13 74
5th & 6th Fl5th & 6th Floor Slab 80 30-Jul-12 04-Nov-12 12-Aug-12 22-Jan-13 65
SubmissionSubmission 64 30-Jul-12 14-Oct-12 12-Aug-12 02-Jan-13 64
A103170 Submission of Structural Dwgs. for Columns 7 30-Jul-12 06-Aug-12 12-Aug-12 21-Aug-12 11
A103180 Submission of Structural Dwgs. for Core Walls 7 30-Jul-12 06-Aug-12 14-Aug-12 23-Aug-12 13
A103160 Submission of Structural Dwgs. for Slab 7 07-Aug-12 14-Aug-12 25-Aug-12 01-Sep-12 13
A103220 Submission of Structural Dwgs. for Staircase 7 07-Oct-12 14-Oct-12 25-Dec-12 02-Jan-13 64
ApprovalApproval 61 07-Aug-12 04-Nov-12 28-Aug-12 22-Jan-13 54
A103200 Approval of Structural Dwgs. for Columns 14 07-Aug-12 28-Aug-12 28-Aug-12 16-Sep-12 13
A103210 Approval of Structural Dwgs. for Core Walls 14 07-Aug-12 28-Aug-12 28-Aug-12 16-Sep-12 13
A103190 Approval of Structural Dwgs. for Slab 14 15-Aug-12 05-Sep-12 02-Sep-12 19-Sep-12 10
A103230 Approval of Structural Dwgs. for Staircase 14 15-Oct-12 04-Nov-12 03-Jan-13 22-Jan-13 54
7th Floor Sl7th Floor Slab 86 27-Aug-12 09-Dec-12 09-Sep-12 22-Jan-13 37
SubmissionSubmission 69 27-Aug-12 18-Nov-12 09-Sep-12 02-Jan-13 37
A103250 Submission of Structural Dwgs. for Columns 7 27-Aug-12 03-Sep-12 09-Sep-12 16-Sep-12 11
A103260 Submission of Structural Dwgs. for Core Walls 7 27-Aug-12 03-Sep-12 15-Sep-12 22-Sep-12 16
A103240 Submission of Structural Dwgs. for Slab 7 04-Sep-12 11-Sep-12 23-Sep-12 30-Sep-12 16
A103300 Submission of Structural Dwgs. for Staircase 7 10-Nov-12 18-Nov-12 25-Dec-12 02-Jan-13 37
ApprovalApproval 66 04-Sep-12 09-Dec-12 24-Sep-12 22-Jan-13 31
A103280 Approval of Structural Dwgs. for Columns 14 04-Sep-12 23-Sep-12 26-Sep-12 15-Oct-12 16
A103290 Approval of Structural Dwgs. for Core Walls 14 04-Sep-12 23-Sep-12 24-Sep-12 11-Oct-12 14
A103270 Approval of Structural Dwgs. for Slab 14 12-Sep-12 01-Oct-12 01-Oct-12 18-Oct-12 13
A103310 Approval of Structural Dwgs. for Staircase 14 19-Nov-12 09-Dec-12 03-Jan-13 22-Jan-13 31
Roof FloorRoof Floor Slab 79 16-Sep-12 20-Dec-12 29-Sep-12 23-May-13 130
SubmissionSubmission 71 16-Sep-12 11-Dec-12 29-Sep-12 14-May-13 130
A102910 Submission of Structural Dwgs. for Columns 7 16-Sep-12 23-Sep-12 29-Sep-12 06-Oct-12 11
A102900 Submission of Structural Dwgs. for Slab 7 24-Sep-12 01-Oct-12 07-Oct-12 14-Oct-12 11
A102960 Submission of Structural Dwgs. for Staircase 7 24-Sep-12 01-Oct-12 25-Dec-12 02-Jan-13 75
A117150 Submission of Structural Dwgs. for Chillers Foundations 14 30-Sep-12 15-Oct-12 13-Oct-12 30-Oct-12 11
A117030 Submission of Structural Dwgs. for Parapets 7 04-Dec-12 11-Dec-12 07-May-13 14-May-13 130
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Chillers Foundations
Approval of Structural Dwgs. for Parapets
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Raft
Approval of Structural Dwgs. for Raft
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Water Tank
Submission of Structural Dwgs. for Ramp
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Water Tank
Approval of Structural Dwgs. for Ramp
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Ramp
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Ramp
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Chillers Foundations
Submission of Structural Dwgs. for Parapets
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 3 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
ApprovalApproval 61 24-Sep-12 20-Dec-12 14-Oct-12 23-May-13 108
A102940 Approval of Structural Dwgs. for Columns 14 24-Sep-12 11-Oct-12 14-Oct-12 01-Nov-12 14
A102930 Approval of Structural Dwgs. for Slab 14 02-Oct-12 21-Oct-12 16-Oct-12 05-Nov-12 10
A102970 Approval of Structural Dwgs. for Staircase 14 02-Oct-12 21-Oct-12 03-Jan-13 22-Jan-13 63
A117140 Approval of Structural Dwgs. for Chillers Foundations 14 16-Oct-12 05-Nov-12 31-Oct-12 20-Nov-12 10
A117040 Approval of Structural Dwgs. for Parapets 7 12-Dec-12 20-Dec-12 15-May-13 23-May-13 108
Upper RoofUpper Roof Floor Slab 30 30-Sep-12 05-Nov-12 13-Oct-12 20-Nov-12 12
SubmissionSubmission 14 30-Sep-12 15-Oct-12 13-Oct-12 30-Oct-12 11
A102990 Submission of Structural Dwgs. for Columns 7 30-Sep-12 07-Oct-12 13-Oct-12 20-Oct-12 11
A102980 Submission of Structural Dwgs. for Slab 7 08-Oct-12 15-Oct-12 21-Oct-12 30-Oct-12 11
ApprovalApproval 20 08-Oct-12 05-Nov-12 28-Oct-12 20-Nov-12 10
A103020 Approval of Structural Dwgs. for Columns 14 08-Oct-12 28-Oct-12 28-Oct-12 14-Nov-12 13
A103010 Approval of Structural Dwgs. for Slab 14 16-Oct-12 05-Nov-12 31-Oct-12 20-Nov-12 10
Residentail (BResidentail (Block C) 260 02-Jan-12 06-Nov-12 14-Jan-12 23-May-13 166
Deep FoundDeep Foundation 24 02-Jan-12 29-Jan-12 14-Jan-12 08-Feb-12 8
SubmissionSubmission 7 02-Jan-12 09-Jan-12 14-Jan-12 21-Jan-12 10
A103320 Submission of Structural Dwgs. for Raft 7 02-Jan-12 09-Jan-12 14-Jan-12 21-Jan-12 10
ApprovalApproval 14 10-Jan-12 29-Jan-12 22-Jan-12 08-Feb-12 8
A103330 Approval of Structural Dwgs. for Raft 14 10-Jan-12 29-Jan-12 22-Jan-12 08-Feb-12 8
1st Baseme1st Basement Floor Slab 60 19-Jan-12 29-Mar-12 13-Feb-12 17-Jan-13 244
SubmissionSubmission 44 19-Jan-12 11-Mar-12 13-Feb-12 29-Dec-12 244
A103350 Submission of Structural Dwgs. for Ret. Walls -Columns 7 19-Jan-12 26-Jan-12 13-Feb-12 20-Feb-12 20
A103360 Submission of Structural Dwgs. for Core Walls 7 19-Jan-12 26-Jan-12 22-Feb-12 29-Feb-12 28
A103370 Submission of Structural Dwgs. for Water Tank 7 19-Jan-12 26-Jan-12 22-Feb-12 29-Feb-12 28
A103340 Submission of Structural Dwgs. for Slab 7 28-Jan-12 05-Feb-12 05-Mar-12 12-Mar-12 31
A103420 Submission of Structural Dwgs. for Staircase 7 04-Mar-12 11-Mar-12 22-Dec-12 29-Dec-12 244
ApprovalApproval 45 29-Jan-12 29-Mar-12 01-Mar-12 17-Jan-13 203
A103390 Approval of Structural Dwgs. for Ret. Walls -Columns 14 29-Jan-12 15-Feb-12 04-Mar-12 21-Mar-12 25
A103400 Approval of Structural Dwgs. for Core Walls 14 29-Jan-12 15-Feb-12 01-Mar-12 20-Mar-12 24
A103410 Approval of Structural Dwgs. for Water Tank 14 29-Jan-12 15-Feb-12 01-Mar-12 20-Mar-12 24
A103380 Approval of Structural Dwgs. for Slab 14 06-Feb-12 23-Feb-12 13-Mar-12 01-Apr-12 26
A103430 Approval of Structural Dwgs. for Staircase 14 12-Mar-12 29-Mar-12 30-Dec-12 17-Jan-13 203
Ground FloGround Floor Slab 51 10-Mar-12 07-May-12 02-Apr-12 17-Jan-13 211
SubmissionSubmission 34 10-Mar-12 17-Apr-12 02-Apr-12 29-Dec-12 212
A103450 Submission of Structural Dwgs. for Ret. Walls -Columns 7 10-Mar-12 17-Mar-12 02-Apr-12 09-Apr-12 20
A103460 Submission of Structural Dwgs. for Core Walls 7 10-Mar-12 17-Mar-12 07-Apr-12 14-Apr-12 24
A103440 Submission of Structural Dwgs. for Slab 7 18-Mar-12 25-Mar-12 15-Apr-12 22-Apr-12 24
A103500 Submission of Structural Dwgs. for Staircase 7 10-Apr-12 17-Apr-12 22-Dec-12 29-Dec-12 212
ApprovalApproval 37 18-Mar-12 07-May-12 17-Apr-12 17-Jan-13 176
A103480 Approval of Structural Dwgs. for Ret. Walls -Columns 14 18-Mar-12 04-Apr-12 17-Apr-12 06-May-12 22
A103490 Approval of Structural Dwgs. for Core Walls 14 18-Mar-12 04-Apr-12 18-Apr-12 07-May-12 23
A103470 Approval of Structural Dwgs. for Slab 14 26-Mar-12 12-Apr-12 23-Apr-12 10-May-12 20
A103510 Approval of Structural Dwgs. for Staircase 14 18-Apr-12 07-May-12 30-Dec-12 17-Jan-13 176
1st Floor Sl1st Floor Slab 61 10-Apr-12 20-Jun-12 03-May-12 18-Feb-13 200
SubmissionSubmission 44 10-Apr-12 30-May-12 03-May-12 29-Jan-13 200
A103530 Submission of Structural Dwgs. for Columns 7 10-Apr-12 17-Apr-12 03-May-12 10-May-12 20
A103540 Submission of Structural Dwgs. for Core Walls 7 10-Apr-12 17-Apr-12 05-May-12 12-May-12 21
A103520 Submission of Structural Dwgs. for Slab 7 18-Apr-12 25-Apr-12 13-May-12 20-May-12 21
A103580 Submission of Structural Dwgs. for Staircase 7 23-May-12 30-May-12 21-Jan-13 29-Jan-13 200
ApprovalApproval 45 18-Apr-12 20-Jun-12 16-May-12 18-Feb-13 166
A103560 Approval of Structural Dwgs. for Columns 14 18-Apr-12 07-May-12 16-May-12 04-Jun-12 20
A103570 Approval of Structural Dwgs. for Core Walls 14 18-Apr-12 07-May-12 16-May-12 04-Jun-12 20
A103550 Approval of Structural Dwgs. for Slab 14 26-Apr-12 15-May-12 21-May-12 07-Jun-12 17
A103590 Approval of Structural Dwgs. for Staircase 14 31-May-12 20-Jun-12 30-Jan-13 18-Feb-13 166
2nd Floor S2nd Floor Slab 65 03-May-12 18-Jul-12 27-May-12 07-Feb-13 167
SubmissionSubmission 49 03-May-12 30-Jun-12 27-May-12 19-Jan-13 167
A103870 Submission of Structural Dwgs. for Columns 7 03-May-12 10-May-12 27-May-12 03-Jun-12 20
A103880 Submission of Structural Dwgs. for Core Walls 7 03-May-12 10-May-12 28-May-12 04-Jun-12 21
A103860 Submission of Structural Dwgs. for Slab 7 12-May-12 19-May-12 05-Jun-12 12-Jun-12 21
A103920 Submission of Structural Dwgs. for Staircase 7 23-Jun-12 30-Jun-12 12-Jan-13 19-Jan-13 167
ApprovalApproval 48 13-May-12 18-Jul-12 10-Jun-12 07-Feb-13 139
A103900 Approval of Structural Dwgs. for Columns 14 13-May-12 30-May-12 10-Jun-12 28-Jun-12 20
A103910 Approval of Structural Dwgs. for Core Walls 14 13-May-12 30-May-12 10-Jun-12 28-Jun-12 20
A103890 Approval of Structural Dwgs. for Slab 14 20-May-12 06-Jun-12 13-Jun-12 03-Jul-12 18
A103930 Approval of Structural Dwgs. for Staircase 14 01-Jul-12 18-Jul-12 20-Jan-13 07-Feb-13 139
3rd & 4th Fl3rd & 4th Floor Slab 76 29-May-12 28-Aug-12 23-Jun-12 05-Feb-13 132
SubmissionSubmission 59 29-May-12 06-Aug-12 23-Jun-12 15-Jan-13 132
A103610 Submission of Structural Dwgs. for Columns 7 29-May-12 05-Jun-12 23-Jun-12 30-Jun-12 20
A103620 Submission of Structural Dwgs. for Core Walls 7 29-May-12 05-Jun-12 23-Jun-12 30-Jun-12 20
A103600 Submission of Structural Dwgs. for Slab 7 06-Jun-12 13-Jun-12 01-Jul-12 08-Jul-12 20
A103660 Submission of Structural Dwgs. for Staircase 7 30-Jul-12 06-Aug-12 08-Jan-13 15-Jan-13 132
ApprovalApproval 57 06-Jun-12 28-Aug-12 03-Jul-12 05-Feb-13 110
A103640 Approval of Structural Dwgs. for Columns 14 06-Jun-12 26-Jun-12 03-Jul-12 22-Jul-12 18
A103650 Approval of Structural Dwgs. for Core Walls 14 06-Jun-12 26-Jun-12 03-Jul-12 22-Jul-12 18
A103630 Approval of Structural Dwgs. for Slab 14 14-Jun-12 04-Jul-12 09-Jul-12 26-Jul-12 16
A103670 Approval of Structural Dwgs. for Staircase 14 07-Aug-12 28-Aug-12 16-Jan-13 05-Feb-13 110
5th & 6th Fl5th & 6th Floor Slab 66 25-Jun-12 11-Sep-12 21-Jul-12 04-Feb-13 119
SubmissionSubmission 49 25-Jun-12 22-Aug-12 21-Jul-12 14-Jan-13 119
A103950 Submission of Structural Dwgs. for Columns 7 25-Jun-12 02-Jul-12 21-Jul-12 28-Jul-12 22
A103960 Submission of Structural Dwgs. for Core Walls 7 25-Jun-12 02-Jul-12 21-Jul-12 28-Jul-12 22
A103940 Submission of Structural Dwgs. for Slab 7 03-Jul-12 10-Jul-12 29-Jul-12 05-Aug-12 22
A104000 Submission of Structural Dwgs. for Staircase 7 13-Aug-12 22-Aug-12 07-Jan-13 14-Jan-13 119
ApprovalApproval 49 03-Jul-12 11-Sep-12 02-Aug-12 04-Feb-13 99
A103980 Approval of Structural Dwgs. for Columns 14 03-Jul-12 22-Jul-12 02-Aug-12 23-Aug-12 22
A103990 Approval of Structural Dwgs. for Core Walls 14 03-Jul-12 22-Jul-12 02-Aug-12 23-Aug-12 22
A103970 Approval of Structural Dwgs. for Slab 14 11-Jul-12 30-Jul-12 06-Aug-12 27-Aug-12 18
A104010 Approval of Structural Dwgs. for Staircase 14 23-Aug-12 11-Sep-12 15-Jan-13 04-Feb-13 99
7th Floor Sl7th Floor Slab 61 26-Jul-12 07-Oct-12 23-Aug-12 30-Jan-13 93
SubmissionSubmission 44 26-Jul-12 17-Sep-12 23-Aug-12 09-Jan-13 93
A104030 Submission of Structural Dwgs. for Columns 7 26-Jul-12 02-Aug-12 23-Aug-12 30-Aug-12 22
A104040 Submission of Structural Dwgs. for Core Walls 7 26-Jul-12 02-Aug-12 23-Aug-12 30-Aug-12 22
A104020 Submission of Structural Dwgs. for Slab 7 04-Aug-12 11-Aug-12 01-Sep-12 08-Sep-12 22
A104080 Submission of Structural Dwgs. for Staircase 7 10-Sep-12 17-Sep-12 02-Jan-13 09-Jan-13 93
ApprovalApproval 44 05-Aug-12 07-Oct-12 03-Sep-12 30-Jan-13 78
A104060 Approval of Structural Dwgs. for Columns 14 05-Aug-12 26-Aug-12 03-Sep-12 20-Sep-12 19
A104070 Approval of Structural Dwgs. for Core Walls 14 05-Aug-12 26-Aug-12 03-Sep-12 20-Sep-12 19
A104050 Approval of Structural Dwgs. for Slab 14 12-Aug-12 02-Sep-12 09-Sep-12 26-Sep-12 18
A104090 Approval of Structural Dwgs. for Staircase 14 18-Sep-12 07-Oct-12 10-Jan-13 30-Jan-13 78
Roof FloorRoof Floor Slab 72 11-Aug-12 06-Nov-12 09-Sep-12 23-May-13 166
SubmissionSubmission 56 11-Aug-12 16-Oct-12 09-Sep-12 05-May-13 166
A103690 Submission of Structural Dwgs. for Columns 7 11-Aug-12 18-Aug-12 09-Sep-12 16-Sep-12 23
A103700 Submission of Structural Dwgs. for Core Walls 7 11-Aug-12 18-Aug-12 09-Sep-12 16-Sep-12 23
A103680 Submission of Structural Dwgs. for Slab 7 21-Aug-12 28-Aug-12 17-Sep-12 24-Sep-12 23
A117170 Submission of Structural Dwgs. for Chillers Foundations 14 21-Aug-12 05-Sep-12 06-Oct-12 21-Oct-12 39
A103740 Submission of Structural Dwgs. for Staircase 7 01-Oct-12 08-Oct-12 08-Jan-13 15-Jan-13 80
A117070 Submission of Structural Dwgs. for Parapets 7 09-Oct-12 16-Oct-12 28-Apr-13 05-May-13 166
ApprovalApproval 55 21-Aug-12 06-Nov-12 18-Sep-12 23-May-13 138
A103720 Approval of Structural Dwgs. for Columns 14 21-Aug-12 09-Sep-12 20-Sep-12 09-Oct-12 22
A103730 Approval of Structural Dwgs. for Core Walls 14 21-Aug-12 09-Sep-12 18-Sep-12 07-Oct-12 20
A103710 Approval of Structural Dwgs. for Slab 14 29-Aug-12 17-Sep-12 25-Sep-12 14-Oct-12 19
A117160 Approval of Structural Dwgs. for Chillers Foundations 14 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Chillers Foundations
Approval of Structural Dwgs. for Parapets
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Raft
Approval of Structural Dwgs. for Raft
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Water Tank
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Water Tank
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Ret. Walls -Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Ret. Walls -Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Chillers Foundations
Submission of Structural Dwgs. for Staircase
Submission of Structural Dwgs. for Parapets
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Chillers Foundations
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 4 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A103750 Approval of Structural Dwgs. for Staircase 14 09-Oct-12 29-Oct-12 16-Jan-13 05-Feb-13 67
A117080 Approval of Structural Dwgs. for Parapets 14 17-Oct-12 06-Nov-12 06-May-13 23-May-13 138
Upper RoofUpper Roof Floor Slab 60 21-Aug-12 31-Oct-12 27-Sep-12 18-Feb-13 90
SubmissionSubmission 44 21-Aug-12 10-Oct-12 27-Sep-12 29-Jan-13 89
A103770 Submission of Structural Dwgs. for Columns 7 21-Aug-12 28-Aug-12 27-Sep-12 04-Oct-12 32
A103760 Submission of Structural Dwgs. for Slab 7 29-Aug-12 05-Sep-12 06-Oct-12 13-Oct-12 32
A103820 Submission of Structural Dwgs. for Staircase 7 03-Oct-12 10-Oct-12 21-Jan-13 29-Jan-13 89
ApprovalApproval 45 29-Aug-12 31-Oct-12 08-Oct-12 18-Feb-13 74
A103800 Approval of Structural Dwgs. for Columns 14 29-Aug-12 17-Sep-12 08-Oct-12 28-Oct-12 28
A103790 Approval of Structural Dwgs. for Slab 14 06-Sep-12 25-Sep-12 14-Oct-12 01-Nov-12 26
A103830 Approval of Structural Dwgs. for Staircase 14 11-Oct-12 31-Oct-12 30-Jan-13 18-Feb-13 74
ArchitecturalArchitectural 403 13-Mar-12 07-Jul-13 24-Mar-12 29-Jul-13 19
Hotel ApartemHotel Apartements (Block A) 383 13-Mar-12 13-Jun-13 24-Mar-12 29-Jul-13 39
2nd Baseme2nd Basement Floor 223 13-Mar-12 05-Dec-12 24-Mar-12 17-Apr-13 112
SubmissionSubmission 206 13-Mar-12 13-Nov-12 24-Mar-12 30-Mar-13 113
A119010 Submission of Block Work Setting Out Plan for 2nd Basement 8 13-Mar-12 21-Mar-12 24-Mar-12 01-Apr-12 9
A119130 Submission of Staircase Layout & Details 8 26-Apr-12 05-May-12 30-Aug-12 08-Sep-12 105
A119060 Submission of Doors Details 8 08-May-12 16-May-12 05-Feb-13 13-Feb-13 225
A119040 Submission of Flooring 8 20-May-12 28-May-12 07-Feb-13 16-Feb-13 217
A119050 Submission of Reflected Ceiling Layout 8 31-May-12 09-Jun-12 26-Dec-12 05-Jan-13 172
A119140 Submission of Handrail Layout & Details 8 18-Jul-12 26-Jul-12 24-Sep-12 02-Oct-12 56
A119100 Submission of Sinage Layout and Details 8 11-Aug-12 21-Aug-12 21-Mar-13 30-Mar-13 183
A119080 Submission of Parking Layout 8 05-Nov-12 13-Nov-12 12-Feb-13 20-Feb-13 81
A119090 Submission of Traffic Sign Layout 8 05-Nov-12 13-Nov-12 12-Feb-13 20-Feb-13 81
ApprovalApproval 179 22-Mar-12 05-Dec-12 09-Sep-12 17-Apr-13 93
A119290 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Mar-12 10-Apr-12 12-Sep-12 01-Oct-12 121
A119270 Approval of Staircase Layout & Details 14 06-May-12 23-May-12 09-Sep-12 26-Sep-12 87
A119340 Approval of Doors Details 14 17-May-12 05-Jun-12 14-Feb-13 05-Mar-13 187
A119320 Approval of Flooring 14 29-May-12 18-Jun-12 17-Feb-13 06-Mar-13 180
A119330 Approval of Reflected Ceiling Layout 14 10-Jun-12 28-Jun-12 06-Jan-13 23-Jan-13 143
A119280 Approval of Handrail Layout & Details 14 29-Jul-12 15-Aug-12 03-Oct-12 22-Oct-12 46
A119400 Approval of Sinage Layout and Details 14 22-Aug-12 10-Sep-12 31-Mar-13 17-Apr-13 152
A119360 Approval of Parking Layout 14 14-Nov-12 05-Dec-12 21-Feb-13 12-Mar-13 67
A119370 Approval of Traffic Sign Layout 14 14-Nov-12 05-Dec-12 21-Feb-13 12-Mar-13 67
1st Baseme1st Basement Floor 222 22-Mar-12 13-Dec-12 02-Apr-12 23-Apr-13 110
SubmissionSubmission 206 22-Mar-12 24-Nov-12 02-Apr-12 03-Apr-13 109
A119410 Submission of Block Work Setting Out Plan for 1st Basement 8 22-Mar-12 31-Mar-12 02-Apr-12 10-Apr-12 9
A119520 Submission of Staircase Layout & Details 8 06-May-12 14-May-12 02-Sep-12 10-Sep-12 99
A119460 Submission of Doors Details 8 17-May-12 26-May-12 23-Jan-13 02-Feb-13 207
A119440 Submission of Flooring 8 04-Jun-12 12-Jun-12 13-Jan-13 21-Jan-13 183
A119450 Submission of Reflected Ceiling Layout 8 10-Jun-12 19-Jun-12 17-Oct-12 28-Oct-12 108
A119530 Submission of Handrail Layout & Details 8 28-Jul-12 05-Aug-12 08-Oct-12 16-Oct-12 60
A119540 Submission of Sinage Layout and Details 8 22-Aug-12 30-Aug-12 26-Mar-13 03-Apr-13 179
A119480 Submission of Parking Layout 8 14-Nov-12 24-Nov-12 12-Feb-13 20-Feb-13 73
A119490 Submission of Traffic Sign Layout 8 14-Nov-12 24-Nov-12 12-Feb-13 20-Feb-13 73
ApprovalApproval 179 01-Apr-12 13-Dec-12 15-Jul-12 23-Apr-13 91
A119550 Approval of Block Work Setting Out Plan for 1st Basement 14 01-Apr-12 18-Apr-12 15-Jul-12 01-Aug-12 74
A119600 Approval of Staircase Layout & Details 14 15-May-12 03-Jun-12 11-Sep-12 30-Sep-12 82
A119620 Approval of Doors Details 14 27-May-12 13-Jun-12 03-Feb-13 20-Feb-13 172
A119580 Approval of Flooring 14 13-Jun-12 03-Jul-12 22-Jan-13 11-Feb-13 152
A119590 Approval of Reflected Ceiling Layout 14 20-Jun-12 09-Jul-12 29-Oct-12 18-Nov-12 90
A119610 Approval of Handrail Layout & Details 14 06-Aug-12 27-Aug-12 17-Oct-12 06-Nov-12 50
A119680 Approval of Sinage Layout and Details 14 02-Sep-12 19-Sep-12 04-Apr-13 23-Apr-13 149
A119640 Approval of Parking Layout 14 25-Nov-12 13-Dec-12 21-Feb-13 12-Mar-13 61
A119650 Approval of Traffic Sign Layout 14 25-Nov-12 13-Dec-12 21-Feb-13 12-Mar-13 61
Ground FloGround Floor 333 24-Apr-12 27-May-13 05-May-12 29-Jul-13 53
SubmissionSubmission 316 24-Apr-12 07-May-13 05-May-12 09-Jul-13 53
A118450 Submission of Block Work Setting Out Plan for Ground 8 24-Apr-12 02-May-12 05-May-12 13-May-12 9
A119150 Submission of Staircase Layout & Details 8 07-Jun-12 16-Jun-12 06-Sep-12 15-Sep-12 75
A118370 Submission of Reflected Ceiling Layout 8 20-Jun-12 28-Jun-12 22-Dec-12 30-Dec-12 152
A118380 Submission of Flooring Layout 8 20-Jun-12 28-Jun-12 16-Dec-12 24-Dec-12 147
A118420 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 25-Jul-12 02-Aug-12 21-Jan-13 30-Jan-13 147
A119160 Submission of Handrail Layout & Details 8 01-Sep-12 09-Sep-12 20-Oct-12 30-Oct-12 42
A118400 Submission of Doors Details 8 06-Oct-12 14-Oct-12 28-Jan-13 05-Feb-13 92
A118410 Submission of Sinage Layout and Details 8 17-Oct-12 28-Oct-12 26-Mar-13 03-Apr-13 131
A118440 Submission of Furniture Layout and Details 8 29-Apr-13 07-May-13 01-Jul-13 09-Jul-13 53
ApprovalApproval 270 03-May-12 27-May-13 16-Sep-12 29-Jul-13 44
A118480 Approval of Block Work Setting Out Plan for Ground 14 03-May-12 22-May-12 07-Nov-12 27-Nov-12 130
A119250 Approval of Staircase Layout & Details 14 18-Jun-12 05-Jul-12 16-Sep-12 03-Oct-12 62
A118490 Approval of Reflected Ceiling Layout 14 01-Jul-12 18-Jul-12 31-Dec-12 20-Jan-13 126
A118500 Approval of Flooring Layout 14 01-Jul-12 18-Jul-12 25-Dec-12 14-Jan-13 122
A118510 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 05-Aug-12 26-Aug-12 31-Jan-13 19-Feb-13 122
A119260 Approval of Handrail Layout & Details 14 10-Sep-12 27-Sep-12 31-Oct-12 20-Nov-12 36
A118530 Approval of Doors Details 14 15-Oct-12 04-Nov-12 06-Feb-13 25-Feb-13 77
A118550 Approval of Sinage Layout and Details 14 29-Oct-12 18-Nov-12 04-Apr-13 23-Apr-13 109
A118540 Approval of Furniture Layout and Details 14 08-May-13 27-May-13 10-Jul-13 29-Jul-13 44
Typical FlooTypical Floors 333 03-May-12 05-Jun-13 14-May-12 29-Jul-13 45
GeneralGeneral 109 03-May-12 10-Sep-12 14-May-12 23-Dec-12 85
SubmissiSubmission 92 03-May-12 21-Aug-12 14-May-12 03-Dec-12 85
A117470 Submission of Block Work Setting Out Plan for 1st Floor 8 03-May-12 12-May-12 14-May-12 22-May-12 9
A117230 Submission of Block Work Setting Out Plan for 2nd Floor 8 30-May-12 07-Jun-12 10-Jun-12 19-Jun-12 9
A117240 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 27-Jun-12 05-Jul-12 08-Jul-12 16-Jul-12 9
A117250 Submission of Block Work Setting Out Plan for 7th Floor 8 11-Aug-12 21-Aug-12 24-Nov-12 03-Dec-12 85
ApprovalApproval 84 13-May-12 10-Sep-12 09-Jul-12 23-Dec-12 71
A117480 Approval of Block Work Setting Out Plan for 1st Floor 14 13-May-12 30-May-12 09-Jul-12 26-Jul-12 40
A117490 Approval of Block Work Setting Out Plan for 2nd Floor 14 10-Jun-12 28-Jun-12 12-Jul-12 31-Jul-12 23
A117500 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7
A117510 Approval of Block Work Setting Out Plan for 7th Floor 14 22-Aug-12 10-Sep-12 04-Dec-12 23-Dec-12 71
Corridor / GCorridor / General 184 30-Jun-12 07-Feb-13 16-Sep-12 15-Apr-13 57
SubmissiSubmission 168 30-Jun-12 19-Jan-13 16-Sep-12 26-Mar-13 56
A119170 Submission of Staircase Layout & Details 8 30-Jun-12 08-Jul-12 16-Sep-12 24-Sep-12 65
A117430 Submission of Reflected Ceiling Layout 8 11-Jul-12 19-Jul-12 26-Nov-12 05-Dec-12 113
A119180 Submission of Handrail Layout & Details 8 15-Aug-12 26-Aug-12 17-Oct-12 28-Oct-12 52
A117450 Submission of Flooring Layout 8 10-Sep-12 18-Sep-12 22-Dec-12 30-Dec-12 84
A117400 Submission of Doors Details 8 03-Oct-12 11-Oct-12 10-Jan-13 19-Jan-13 80
A117420 Submission of Sinage Layout and Details 8 10-Nov-12 19-Nov-12 18-Mar-13 26-Mar-13 106
A117410 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 05-Mar-13 13-Mar-13 45
ApprovalApproval 147 09-Jul-12 07-Feb-13 25-Sep-12 15-Apr-13 47
A119230 Approval of Staircase Layout & Details 14 09-Jul-12 26-Jul-12 25-Sep-12 14-Oct-12 54
A117520 Approval of Reflected Ceiling Layout 14 22-Jul-12 08-Aug-12 06-Dec-12 25-Dec-12 94
A119240 Approval of Handrail Layout & Details 14 27-Aug-12 13-Sep-12 29-Oct-12 18-Nov-12 44
A117530 Approval of Flooring Layout 14 19-Sep-12 08-Oct-12 31-Dec-12 20-Jan-13 70
A117550 Approval of Doors Details 14 14-Oct-12 01-Nov-12 20-Jan-13 07-Feb-13 66
A117580 Approval of Sinage Layout and Details 14 20-Nov-12 10-Dec-12 27-Mar-13 15-Apr-13 88
A117570 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 14-Mar-13 02-Apr-13 38
Studio ApaStudio Apartements 285 30-Jun-12 05-Jun-13 18-Sep-12 29-Jul-13 45
SubmissiSubmission 268 30-Jun-12 16-May-13 18-Sep-12 09-Jul-13 45
A117340 Submission of Wet Area Ceramic & Pocalin Layout 8 30-Jun-12 08-Jul-12 01-Oct-12 09-Oct-12 78
A117300 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 18-Sep-12 26-Sep-12 47
A117280 Submission of Waredrobe Details 8 03-Oct-12 11-Oct-12 04-Nov-12 12-Nov-12 25
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Parapets
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Slab
Submission of Structural Dwgs. for Staircase
Approval of Structural Dwgs. for Columns
Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Staircase
Submission of Block Work Setting Out Plan for 2nd Basement
Submission of Staircase Layout & Details
Submission of Doors Details
Submission of Flooring
Submission of Reflected Ceiling Layout
Submission of Handrail Layout & Details
Submission of Sinage Layout and Details
Submission of Parking Layout
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 2nd Basement
Approval of Staircase Layout & Details
Approval of Doors Details
Approval of Flooring
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for 1st Basement
Submission of Staircase Layout & Details
Submission of Doors Details
Submission of Flooring
Submission of Reflected Ceiling Layout
Submission of Handrail Layout & Details
Submission of Sinage Layout and Details
Submission of Parking Layout
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 1st Basement
Approval of Staircase Layout & Details
Approval of Doors Details
Approval of Flooring
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for Ground
Submission of Staircase Layout & Details
Submission of Reflected Ceiling Layout
Submission of Flooring Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Handrail Layout & Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Furniture Layout and Details
Approval of Block Work Setting Out Plan for Ground
Approval of Staircase Layout & Details
Approval of Reflected Ceiling Layout
Approval of Flooring Layout
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Handrail Layout & Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Furniture Layout and Details
Submission of Block Work Setting Out Plan for 1st Floor
Submission of Block Work Setting Out Plan for 2nd Floor
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Block Work Setting Out Plan for 7th Floor
Approval of Block Work Setting Out Plan for 1st Floor
Approval of Block Work Setting Out Plan for 2nd Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Approval of Block Work Setting Out Plan for 7th Floor
Submission of Staircase Layout & Details
Submission of Reflected Ceiling Layout
Submission of Handrail Layout & Details
Submission of Flooring Layout
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Carpet Flooring Details
Approval of Staircase Layout & Details
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Flooring Layout
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Carpet Flooring Details
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Waredrobe Details
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 5 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A117320 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 23-Dec-12 31-Dec-12 55
A117260 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 09-Feb-13 17-Feb-13 74
A117270 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 09-Feb-13 17-Feb-13 74
A117370 Submission of Sinage Layout and Details 8 10-Nov-12 19-Nov-12 21-Mar-13 30-Mar-13 109
A117290 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 09-Feb-13 17-Feb-13 64
A117310 Submission of Doors Details 8 22-Nov-12 01-Dec-12 19-Jan-13 28-Jan-13 47
A117330 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 24-Mar-13 01-Apr-13 61
A117380 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45
ApprovalApproval 231 09-Jul-12 05-Jun-13 27-Sep-12 29-Jul-13 37
A117600 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Jul-12 26-Jul-12 10-Oct-12 30-Oct-12 65
A117620 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 27-Sep-12 16-Oct-12 39
A117650 Approval of Wardrobe Details 14 14-Oct-12 01-Nov-12 13-Nov-12 04-Dec-12 21
A117660 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 02-Jan-13 21-Jan-13 46
A117630 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 18-Feb-13 07-Mar-13 61
A117640 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 18-Feb-13 07-Mar-13 61
A117710 Approval of Sinage Layout and Details 14 20-Nov-12 10-Dec-12 31-Mar-13 17-Apr-13 90
A117690 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 18-Feb-13 07-Mar-13 53
A117670 Approval of Doors Details 14 03-Dec-12 20-Dec-12 29-Jan-13 17-Feb-13 39
A117700 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 02-Apr-13 21-Apr-13 51
A117720 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37
One Bed ROne Bed Room Apartements 285 30-Jun-12 05-Jun-13 09-Sep-12 29-Jul-13 45
SubmissiSubmission 268 30-Jun-12 16-May-13 09-Sep-12 09-Jul-13 45
A117730 Submission of Wet Area Ceramic & Pocalin Layout 8 30-Jun-12 08-Jul-12 13-Jan-13 21-Jan-13 162
A117750 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 09-Sep-12 17-Sep-12 39
A117780 Submission of Wardrobe Details 8 03-Oct-12 11-Oct-12 04-Nov-12 12-Nov-12 25
A117790 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 27-Dec-12 06-Jan-13 59
A117760 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 11-Feb-13 19-Feb-13 76
A117770 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 14-Feb-13 23-Feb-13 79
A117820 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 14-Feb-13 23-Feb-13 69
A117800 Submission of Doors Details 8 22-Nov-12 01-Dec-12 21-Jan-13 30-Jan-13 49
A117840 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 21-Mar-13 30-Mar-13 89
A117830 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 19-Mar-13 27-Mar-13 57
A117850 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45
ApprovalApproval 231 09-Jul-12 05-Jun-13 18-Sep-12 29-Jul-13 37
A117860 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Jul-12 26-Jul-12 22-Jan-13 11-Feb-13 135
A117880 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 18-Sep-12 07-Oct-12 32
A117910 Approval of Wardrobe Details 14 14-Oct-12 01-Nov-12 13-Nov-12 04-Dec-12 21
A117920 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 07-Jan-13 27-Jan-13 49
A117890 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 20-Feb-13 11-Mar-13 63
A117900 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 24-Feb-13 13-Mar-13 65
A117950 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 24-Feb-13 13-Mar-13 57
A117930 Approval of Doors Details 14 03-Dec-12 20-Dec-12 31-Jan-13 19-Feb-13 41
A117970 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 31-Mar-13 17-Apr-13 73
A117960 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 28-Mar-13 16-Apr-13 48
A117980 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37
Two Bed RTwo Bed Room Apartements 275 11-Jul-12 05-Jun-13 16-Aug-12 29-Jul-13 45
SubmissiSubmission 258 11-Jul-12 16-May-13 16-Aug-12 09-Jul-13 45
A117990 Submission of Wet Area Ceramic & Pocalin Layout 8 11-Jul-12 19-Jul-12 14-Jan-13 22-Jan-13 153
A118010 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 16-Aug-12 27-Aug-12 21
A118040 Submission of Wardrobe Details 8 29-Aug-12 06-Sep-12 21-Oct-12 31-Oct-12 45
A118050 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 03-Jan-13 12-Jan-13 64
A118020 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 03-Feb-13 11-Feb-13 69
A118030 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 03-Feb-13 11-Feb-13 69
A118080 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 03-Feb-13 11-Feb-13 59
A118060 Submission of Doors Details 8 22-Nov-12 01-Dec-12 23-Jan-13 02-Feb-13 51
A118100 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 21-Mar-13 30-Mar-13 89
A118090 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 16-Mar-13 24-Mar-13 54
A118110 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45
ApprovalApproval 222 22-Jul-12 05-Jun-13 28-Aug-12 29-Jul-13 37
A118120 Approval of Wet Area Ceramic & Pocalin Layout 14 22-Jul-12 08-Aug-12 23-Jan-13 12-Feb-13 127
A118140 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 28-Aug-12 16-Sep-12 17
A118170 Approval of Wardrobe Details 14 09-Sep-12 26-Sep-12 01-Nov-12 21-Nov-12 38
A118180 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 13-Jan-13 31-Jan-13 53
A118150 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 12-Feb-13 03-Mar-13 57
A118160 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 12-Feb-13 03-Mar-13 57
A118210 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 12-Feb-13 03-Mar-13 49
A118190 Approval of Doors Details 14 03-Dec-12 20-Dec-12 03-Feb-13 20-Feb-13 42
A118230 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 31-Mar-13 17-Apr-13 73
A118220 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 25-Mar-13 11-Apr-13 45
A118240 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37
Roof - UppeRoof - Upper Roof Floor 271 23-Jul-12 13-Jun-13 09-Sep-12 29-Jul-13 39
GeneralGeneral 124 23-Jul-12 20-Dec-12 09-Sep-12 04-Apr-13 88
SubmissiSubmission 108 23-Jul-12 01-Dec-12 09-Sep-12 17-Mar-13 88
A118640 Submission of Block Work Setting Out Plan for Roof & upper ... 8 23-Jul-12 31-Jul-12 09-Sep-12 17-Sep-12 39
A118570 Submission of Roof's Water Proofing System 8 01-Aug-12 09-Aug-12 30-Dec-12 08-Jan-13 123
A118580 Submission of Pool Deck Layout 8 07-Aug-12 15-Aug-12 18-Feb-13 26-Feb-13 159
A118620 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 20-Nov-12 28-Nov-12 09-Mar-13 17-Mar-13 90
A118630 Submission of Flooring Layout 8 20-Nov-12 28-Nov-12 23-Feb-13 03-Mar-13 78
A119190 Submission of Staircase Layout & Details 8 20-Nov-12 28-Nov-12 04-Feb-13 12-Feb-13 62
A119200 Submission of Handrail Layout & Details 8 20-Nov-12 28-Nov-12 09-Feb-13 17-Feb-13 66
A118590 Submission of Doors Details 8 22-Nov-12 01-Dec-12 07-Mar-13 16-Mar-13 87
ApprovalApproval 97 01-Aug-12 20-Dec-12 14-Oct-12 04-Apr-13 73
A118700 Approval of Block Work Setting Out Plan for Roof & Upper Roof 14 01-Aug-12 22-Aug-12 14-Oct-12 01-Nov-12 50
A118710 Approval of Roof's Water Proofing System 14 12-Aug-12 02-Sep-12 09-Jan-13 29-Jan-13 102
A118690 Approval of Pool Deck Layout 14 16-Aug-12 06-Sep-12 27-Feb-13 18-Mar-13 132
A118720 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 29-Nov-12 19-Dec-12 18-Mar-13 04-Apr-13 74
A118730 Approval of Flooring Layout 14 29-Nov-12 19-Dec-12 04-Mar-13 21-Mar-13 64
A119210 Approval of Staircase Layout & Details 14 29-Nov-12 19-Dec-12 13-Feb-13 04-Mar-13 51
A119220 Approval of Handrail Layout & Details 14 29-Nov-12 19-Dec-12 18-Feb-13 07-Mar-13 54
A118740 Approval of Doors Details 14 03-Dec-12 20-Dec-12 17-Mar-13 03-Apr-13 72
GymnasiumGymnasium 243 27-Aug-12 13-Jun-13 19-Nov-12 29-Jul-13 39
SubmissiSubmission 226 27-Aug-12 23-May-13 19-Nov-12 09-Jul-13 39
A118650 Submission of Reflected Ceiling Layout 8 27-Aug-12 04-Sep-12 19-Nov-12 27-Nov-12 69
A118680 Submission of Vinyl Floor Detals 8 03-Dec-12 11-Dec-12 19-Jan-13 28-Jan-13 39
A118660 Submission of Furniture Layout and Detals 8 15-May-13 23-May-13 01-Jul-13 09-Jul-13 39
ApprovalApproval 196 05-Sep-12 13-Jun-13 28-Nov-12 29-Jul-13 32
A118770 Approval of Reflected Ceiling Layout 14 05-Sep-12 24-Sep-12 28-Nov-12 18-Dec-12 58
A118780 Approval of Vinyl Floor Detals 14 12-Dec-12 31-Dec-12 20-Mar-13 08-Apr-13 68
A118790 Approval of Furniture Layout and Detals 14 26-May-13 13-Jun-13 10-Jul-13 29-Jul-13 32
Hotel (BlockHotel (Block B) 377 05-Apr-12 30-Jun-13 23-Apr-12 29-Jul-13 25
2nd Baseme2nd Basement Floor 222 05-Apr-12 27-Dec-12 23-Apr-12 25-Apr-13 100
SubmissionSubmission 206 05-Apr-12 09-Dec-12 23-Apr-12 07-Apr-13 100
A123210 Submission of Block Work Setting Out Plan for 2nd Basement 8 05-Apr-12 14-Apr-12 23-Apr-12 01-May-12 15
A123250 Submission of Doors Details 8 20-May-12 28-May-12 12-Feb-13 20-Feb-13 221
A123240 Submission of Flooring 8 31-May-12 09-Jun-12 09-Feb-13 17-Feb-13 208
A123330 Submission of Staircase Layout & Details 8 25-Jun-12 03-Jul-12 08-Jan-13 16-Jan-13 162
A123340 Submission of Handrail Layout & Details 8 25-Jun-12 03-Jul-12 12-Jan-13 20-Jan-13 165
A123300 Submission of Sinage Layout and Details 8 05-Sep-12 13-Sep-12 30-Mar-13 07-Apr-13 170
A123280 Submission of Parking Layout 8 29-Nov-12 09-Dec-12 16-Feb-13 24-Feb-13 64
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Kitchen Cabinet Details
Submission of Sinage Layout and Details
Submission of Mirror Details
Submission of Doors Details
Submission of Carpet Flooring Details
Submission of Furniture Layout and Detals
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Kitchen Cabinet Details
Approval of Sinage Layout and Details
Approval of Mirror Details
Approval of Doors Details
Approval of Carpet Flooring Details
Approval of Furniture Layout and Detals
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Kitchen Cabinet Details
Submission of Mirror Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Carpet Flooring Details
Submission of Furniture Layout and Detals
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Kitchen Cabinet Details
Approval of Mirror Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Carpet Flooring Details
Approval of Furniture Layout and Detals
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Kitchen Cabinet Details
Submission of Mirror Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Carpet Flooring Details
Submission of Furniture Layout and Detals
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Kitchen Cabinet Details
Approval of Mirror Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Carpet Flooring Details
Approval of Furniture Layout and Detals
Submission of Block Work Setting Out Plan for Roof & upper Roof
Submission of Roof's Water Proofing System
Submission of Pool Deck Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Flooring Layout
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Doors Details
Approval of Block Work Setting Out Plan for Roof & Upper Roof
Approval of Roof's Water Proofing System
Approval of Pool Deck Layout
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Flooring Layout
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Doors Details
Submission of Reflected Ceiling Layout
Submission of Vinyl Floor Detals
Submission of Furniture Layout and Detals
Approval of Reflected Ceiling Layout
Approval of Vinyl Floor Detals
Approval of Furniture Layout and Detals
Submission of Block Work Setting Out Plan for 2nd Basement
Submission of Doors Details
Submission of Flooring
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Sinage Layout and Details
Submission of Parking Layout
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 6 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A123290 Submission of Traffic Sign Layout 8 29-Nov-12 09-Dec-12 16-Feb-13 24-Feb-13 64
ApprovalApproval 179 15-Apr-12 27-Dec-12 14-Nov-12 25-Apr-13 83
A123490 Approval of Block Work Setting Out Plan for 2nd Basement 14 15-Apr-12 02-May-12 14-Nov-12 05-Dec-12 149
A123530 Approval of Doors Details 14 29-May-12 18-Jun-12 21-Feb-13 12-Mar-13 184
A123520 Approval of Flooring 14 10-Jun-12 28-Jun-12 18-Feb-13 07-Mar-13 173
A123470 Approval of Staircase Layout & Details 14 04-Jul-12 23-Jul-12 17-Jan-13 06-Feb-13 135
A123480 Approval of Handrail Layout & Details 14 04-Jul-12 23-Jul-12 21-Jan-13 10-Feb-13 137
A123580 Approval of Sinage Layout and Details 14 16-Sep-12 03-Oct-12 08-Apr-13 25-Apr-13 141
A123560 Approval of Parking Layout 14 10-Dec-12 27-Dec-12 25-Feb-13 14-Mar-13 53
A123570 Approval of Traffic Sign Layout 14 10-Dec-12 27-Dec-12 25-Feb-13 14-Mar-13 53
1st Baseme1st Basement Floor 193 20-May-12 08-Jan-13 06-Jun-12 18-Apr-13 85
SubmissionSubmission 176 20-May-12 18-Dec-12 06-Jun-12 31-Mar-13 86
A123610 Submission of Block Work Setting Out Plan for 1st Basement 8 20-May-12 28-May-12 06-Jun-12 14-Jun-12 15
A123650 Submission of Doors Details 8 23-Jun-12 01-Jul-12 18-Feb-13 26-Feb-13 198
A123660 Submission of Reflected Ceiling Layout 8 04-Jul-12 12-Jul-12 29-Dec-12 07-Jan-13 146
A123730 Submission of Staircase Layout & Details 8 04-Jul-12 12-Jul-12 16-Jan-13 26-Jan-13 161
A123640 Submission of Flooring 8 16-Jul-12 24-Jul-12 31-Jan-13 09-Feb-13 163
A123740 Submission of Handrail Layout & Details 8 16-Jul-12 24-Jul-12 19-Jan-13 28-Jan-13 153
A123700 Submission of Sinage Layout and Details 8 03-Sep-12 11-Sep-12 23-Mar-13 31-Mar-13 166
A123680 Submission of Parking Layout 8 10-Dec-12 18-Dec-12 23-Feb-13 03-Mar-13 62
A123690 Submission of Traffic Sign Layout 8 10-Dec-12 18-Dec-12 23-Feb-13 03-Mar-13 62
ApprovalApproval 154 29-May-12 08-Jan-13 16-Sep-12 18-Apr-13 71
A123770 Approval of Block Work Setting Out Plan for 1st Basement 14 29-May-12 18-Jun-12 16-Sep-12 03-Oct-12 75
A123810 Approval of Doors Details 14 02-Jul-12 19-Jul-12 27-Feb-13 18-Mar-13 165
A123750 Approval of Staircase Layout & Details 14 15-Jul-12 01-Aug-12 27-Jan-13 13-Feb-13 133
A123820 Approval of Reflected Ceiling Layout 14 15-Jul-12 01-Aug-12 08-Jan-13 28-Jan-13 121
A123760 Approval of Handrail Layout & Details 14 25-Jul-12 13-Aug-12 29-Jan-13 17-Feb-13 127
A123800 Approval of Flooring 14 25-Jul-12 13-Aug-12 10-Feb-13 27-Feb-13 135
A123860 Approval of Sinage Layout and Details 14 12-Sep-12 01-Oct-12 01-Apr-13 18-Apr-13 138
A123840 Approval of Parking Layout 14 19-Dec-12 08-Jan-13 04-Mar-13 21-Mar-13 51
A123850 Approval of Traffic Sign Layout 14 19-Dec-12 08-Jan-13 04-Mar-13 21-Mar-13 51
Ground FloGround Floor 293 04-Jul-12 20-Jun-13 22-Jul-12 29-Jul-13 33
Public ArePublic Areas 283 04-Jul-12 09-Jun-13 22-Jul-12 29-Jul-13 43
SubmissiSubmission 266 04-Jul-12 19-May-13 22-Jul-12 09-Jul-13 43
A122880 Submission of Block Work Setting Out Plan for Ground 8 04-Jul-12 12-Jul-12 22-Jul-12 30-Jul-12 15
A122840 Submission of Reflected Ceiling Layout 8 06-Aug-12 14-Aug-12 20-Dec-12 29-Dec-12 111
A122850 Submission of Flooring Layout 8 06-Aug-12 14-Aug-12 02-Feb-13 10-Feb-13 146
A122860 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 06-Aug-12 14-Aug-12 26-Dec-12 05-Jan-13 116
A123350 Submission of Staircase Layout & Details 8 18-Aug-12 28-Aug-12 09-Feb-13 17-Feb-13 142
A123360 Submission of Handrail Layout & Details 8 18-Aug-12 28-Aug-12 12-Feb-13 20-Feb-13 145
A122820 Submission of Doors Details 8 24-Sep-12 02-Oct-12 09-Mar-13 17-Mar-13 136
A122830 Submission of Sinage Layout and Details 8 24-Sep-12 02-Oct-12 23-Mar-13 31-Mar-13 148
A122890 Submission of Crapet Flooring Details 8 06-Feb-13 14-Feb-13 19-Mar-13 27-Mar-13 35
A122870 Submission of Furniture Layout and Detals 8 11-May-13 19-May-13 01-Jul-13 09-Jul-13 43
ApprovalApproval 228 15-Jul-12 09-Jun-13 27-Aug-12 29-Jul-13 36
A122960 Approval of Block Work Setting Out Plan for Ground 14 15-Jul-12 01-Aug-12 27-Aug-12 13-Sep-12 29
A122920 Approval of Reflected Ceiling Layout 14 15-Aug-12 05-Sep-12 30-Dec-12 17-Jan-13 92
A122930 Approval of Flooring Layout 14 15-Aug-12 05-Sep-12 11-Feb-13 28-Feb-13 121
A122940 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 15-Aug-12 05-Sep-12 06-Jan-13 23-Jan-13 96
A123450 Approval of Staircase Layout & Details 14 29-Aug-12 17-Sep-12 18-Feb-13 07-Mar-13 118
A123460 Approval of Handrail Layout & Details 14 29-Aug-12 17-Sep-12 21-Feb-13 12-Mar-13 121
A122900 Approval of Doors Details 14 03-Oct-12 22-Oct-12 18-Mar-13 04-Apr-13 113
A122910 Approval of Sinage Layout and Details 14 03-Oct-12 22-Oct-12 01-Apr-13 18-Apr-13 123
A123950 Approval of Carpet Flooring Details 14 17-Feb-13 06-Mar-13 28-Mar-13 16-Apr-13 29
A122950 Approval of Furniture Layout and Detals 14 20-May-13 09-Jun-13 10-Jul-13 29-Jul-13 36
RestaurantRestaurant 266 02-Aug-12 18-Jun-13 18-Dec-12 29-Jul-13 35
SubmissiSubmission 249 02-Aug-12 28-May-13 18-Dec-12 09-Jul-13 35
A123980 Submission of Reflected Ceiling Layout 8 02-Aug-12 11-Aug-12 18-Dec-12 26-Dec-12 112
A123990 Submission of Flooring Layout 8 02-Aug-12 11-Aug-12 05-Feb-13 13-Feb-13 152
A123960 Submission of Sinage Layout and Details 8 27-Dec-12 06-Jan-13 30-Mar-13 07-Apr-13 77
A123970 Submission of Furniture Layout and Details 8 20-May-13 28-May-13 01-Jul-13 09-Jul-13 35
ApprovalApproval 215 12-Aug-12 18-Jun-13 27-Dec-12 29-Jul-13 29
A124020 Approval of Reflected Ceiling Layout 14 12-Aug-12 02-Sep-12 27-Dec-12 16-Jan-13 94
A124030 Approval of Flooring Layout 14 12-Aug-12 02-Sep-12 14-Feb-13 05-Mar-13 127
A124000 Approval of Sinage Layout and Details 14 07-Jan-13 27-Jan-13 08-Apr-13 25-Apr-13 64
A124010 Approval of Furniture Layout and Detals 14 29-May-13 18-Jun-13 10-Jul-13 29-Jul-13 29
BussinessBussiness Center & Retail 275 14-Jul-12 09-Jun-13 28-Nov-12 29-Jul-13 43
SubmissiSubmission 258 14-Jul-12 19-May-13 28-Nov-12 09-Jul-13 43
A124040 Submission of Reflected Ceiling Layout 8 14-Jul-12 22-Jul-12 28-Nov-12 08-Dec-12 113
A124050 Submission of Flooring Layout 8 18-Aug-12 28-Aug-12 19-Jan-13 28-Jan-13 125
A124070 Submission of Sinage Layout and Details 8 18-Feb-13 26-Feb-13 21-Mar-13 30-Mar-13 27
A124060 Submission of Furniture Layout and Details 8 11-May-13 19-May-13 01-Jul-13 09-Jul-13 43
ApprovalApproval 222 23-Jul-12 09-Jun-13 09-Dec-12 29-Jul-13 36
A124080 Approval of Reflected Ceiling Layout 14 23-Jul-12 09-Aug-12 09-Dec-12 26-Dec-12 94
A124090 Approval of Flooring Layout 14 29-Aug-12 17-Sep-12 29-Jan-13 17-Feb-13 104
A124110 Approval of Sinage Layout and Details 14 27-Feb-13 18-Mar-13 31-Mar-13 17-Apr-13 22
A124100 Approval of Furniture Layout and Detals 14 20-May-13 09-Jun-13 10-Jul-13 29-Jul-13 36
EnteranceEnterance Lobby & Lounge 285 14-Jul-12 20-Jun-13 23-Dec-12 29-Jul-13 33
SubmissiSubmission 268 14-Jul-12 30-May-13 23-Dec-12 09-Jul-13 33
A124120 Submission of Reflected Ceiling Layout 8 14-Jul-12 22-Jul-12 23-Dec-12 31-Dec-12 133
A124130 Submission of Flooring Layout 8 18-Aug-12 28-Aug-12 21-Feb-13 02-Mar-13 153
A124150 Submission of Sinage Layout and Details 8 18-Feb-13 26-Feb-13 30-Mar-13 07-Apr-13 34
A124140 Submission of Furniture Layout and Details 8 22-May-13 30-May-13 01-Jul-13 09-Jul-13 33
ApprovalApproval 231 23-Jul-12 20-Jun-13 02-Jan-13 29-Jul-13 27
A124160 Approval of Reflected Ceiling Layout 14 23-Jul-12 09-Aug-12 02-Jan-13 21-Jan-13 111
A124170 Approval of Flooring Layout 14 29-Aug-12 17-Sep-12 03-Mar-13 20-Mar-13 127
A124190 Approval of Sinage Layout and Details 14 27-Feb-13 18-Mar-13 08-Apr-13 25-Apr-13 28
A124180 Approval of Furniture Layout and Detals 14 02-Jun-13 20-Jun-13 10-Jul-13 29-Jul-13 27
Typical FlooTypical Floors 293 14-Jul-12 30-Jun-13 31-Jul-12 29-Jul-13 25
GeneralGeneral 74 14-Jul-12 09-Oct-12 31-Jul-12 11-Feb-13 101
SubmissiSubmission 57 14-Jul-12 19-Sep-12 31-Jul-12 29-Dec-12 82
A122030 Submission of Block Work Setting Out Plan for 1st Floor 8 14-Jul-12 22-Jul-12 31-Jul-12 08-Aug-12 15
A121790 Submission of Block Work Setting Out Plan for 2nd Floor 8 23-Jul-12 31-Jul-12 31-Oct-12 08-Nov-12 82
A121800 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 01-Aug-12 09-Aug-12 10-Nov-12 19-Nov-12 82
A121810 Submission of Block Work Setting Out Plan for 7th Floor 8 11-Sep-12 19-Sep-12 20-Dec-12 29-Dec-12 82
ApprovalApproval 55 23-Jul-12 09-Oct-12 17-Sep-12 11-Feb-13 84
A122070 Approval of Block Work Setting Out Plan for 1st Floor 14 23-Jul-12 09-Aug-12 17-Sep-12 04-Oct-12 38
A122040 Approval of Block Work Setting Out Plan for 2nd Floor 14 01-Aug-12 22-Aug-12 22-Jan-13 11-Feb-13 118
A122050 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 12-Aug-12 02-Sep-12 30-Dec-12 17-Jan-13 95
A122060 Approval of Block Work Setting Out Plan for 7th Floor 14 20-Sep-12 09-Oct-12 30-Dec-12 17-Jan-13 68
Corridor / PCorridor / Public Areas 285 23-Jul-12 30-Jun-13 13-Oct-12 29-Jul-13 25
SubmissiSubmission 268 23-Jul-12 10-Jun-13 13-Oct-12 09-Jul-13 25
A121990 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 06-Jan-13 14-Jan-13 136
A122310 Submission of Landscaping's Water Proofing Details 8 23-Jul-12 31-Jul-12 13-Oct-12 21-Oct-12 68
A121960 Submission of Doors Details 8 23-Aug-12 01-Sep-12 03-Mar-13 11-Mar-13 158
A122290 Submission of Landscaping Layout & Details 8 23-Aug-12 01-Sep-12 01-Dec-12 10-Dec-12 82
A123370 Submission of Staircase Layout & Details 8 29-Aug-12 06-Sep-12 13-Jan-13 21-Jan-13 112
A123380 Submission of Handrail Layout & Details 8 29-Aug-12 06-Sep-12 17-Jan-13 27-Jan-13 116
A122010 Submission of Flooring Layout 8 04-Sep-12 12-Sep-12 19-Feb-13 27-Feb-13 138
A123890 Submission of Pool Deck Layout 8 10-Sep-12 18-Sep-12 14-Feb-13 23-Feb-13 129
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 2nd Basement
Approval of Doors Details
Approval of Flooring
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for 1st Basement
Submission of Doors Details
Submission of Reflected Ceiling Layout
Submission of Staircase Layout & Details
Submission of Flooring
Submission of Handrail Layout & Details
Submission of Sinage Layout and Details
Submission of Parking Layout
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 1st Basement
Approval of Doors Details
Approval of Staircase Layout & Details
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Flooring
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for Ground
Submission of Reflected Ceiling Layout
Submission of Flooring Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Crapet Flooring Details
Submission of Furniture Layout and Detals
Approval of Block Work Setting Out Plan for Ground
Approval of Reflected Ceiling Layout
Approval of Flooring Layout
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Carpet Flooring Details
Approval of Furniture Layout and Detals
Submission of Reflected Ceiling Layout
Submission of Flooring Layout
Submission of Sinage Layout and Details
Submission of Furniture Layout and Details
Approval of Reflected Ceiling Layout
Approval of Flooring Layout
Approval of Sinage Layout and Details
Approval of Furniture Layout and Deta
Submission of Reflected Ceiling Layout
Submission of Flooring Layout
Submission of Sinage Layout and Details
Submission of Furniture Layout and Details
Approval of Reflected Ceiling Layout
Approval of Flooring Layout
Approval of Sinage Layout and Details
Approval of Furniture Layout and Detals
Submission of Reflected Ceiling Layout
Submission of Flooring Layout
Submission of Sinage Layout and Details
Submission of Furniture Layout and Detail
Approval of Reflected Ceiling Layout
Approval of Flooring Layout
Approval of Sinage Layout and Details
Approval of Furniture Layout and Deta
Submission of Block Work Setting Out Plan for 1st Floor
Submission of Block Work Setting Out Plan for 2nd Floor
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Block Work Setting Out Plan for 7th Floor
Approval of Block Work Setting Out Plan for 1st Floor
Approval of Block Work Setting Out Plan for 2nd Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Approval of Block Work Setting Out Plan for 7th Floor
Submission of Reflected Ceiling Layout
Submission of Landscaping's Water Proofing Details
Submission of Doors Details
Submission of Landscaping Layout & Details
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Flooring Layout
Submission of Pool Deck Layout
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 7 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A121980 Submission of Sinage Layout and Details 8 15-Oct-12 23-Oct-12 25-Mar-13 02-Apr-13 132
A122300 Submission of Irrigation Layout & Details 8 15-Oct-12 23-Oct-12 19-Jan-13 28-Jan-13 77
A122320 Submission of Sky Light Details 8 22-Nov-12 01-Dec-12 24-Feb-13 04-Mar-13 77
A121970 Submission of Carpet Flooring Details 8 16-Feb-13 24-Feb-13 05-Mar-13 13-Mar-13 15
A122000 Submission of Furniture Layout and Details 8 01-Jun-13 10-Jun-13 01-Jul-13 09-Jul-13 25
ApprovalApproval 230 01-Aug-12 30-Jun-13 22-Oct-12 29-Jul-13 21
A122120 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 15-Jan-13 04-Feb-13 113
A123930 Approval of Landscaping's Water Proofing Details 14 01-Aug-12 22-Aug-12 22-Oct-12 11-Nov-12 56
A122090 Approval of Doors Details 14 02-Sep-12 19-Sep-12 12-Mar-13 31-Mar-13 132
A123910 Approval of Landscaping Layout & Details 14 02-Sep-12 19-Sep-12 11-Dec-12 30-Dec-12 69
A123430 Approval of Staircase Layout & Details 14 09-Sep-12 26-Sep-12 22-Jan-13 11-Feb-13 93
A123440 Approval of Handrail Layout & Details 14 09-Sep-12 26-Sep-12 28-Jan-13 14-Feb-13 96
A123900 Approval of Pool Deck Layout 8 19-Sep-12 30-Sep-12 24-Feb-13 05-Mar-13 107
A122140 Approval of Flooring Layout 14 13-Sep-12 02-Oct-12 28-Feb-13 19-Mar-13 115
A122110 Approval of Sinage Layout and Details 14 24-Oct-12 13-Nov-12 03-Apr-13 22-Apr-13 110
A123920 Approval of Irrigation Layout & Details 14 24-Oct-12 13-Nov-12 29-Jan-13 17-Feb-13 64
A123940 Approval of Sky Light Details 14 03-Dec-12 20-Dec-12 05-Mar-13 24-Mar-13 64
A122100 Approval of Carpet Flooring Details 14 25-Feb-13 14-Mar-13 14-Mar-13 02-Apr-13 13
A122130 Approval of Furniture Layout and Detals 14 11-Jun-13 30-Jun-13 10-Jul-13 29-Jul-13 21
Hotel RoomHotel Rooms 255 29-Aug-12 30-Jun-13 20-Nov-12 29-Jul-13 25
SubmissiSubmission 238 29-Aug-12 10-Jun-13 20-Nov-12 09-Jul-13 25
A121860 Submission of Reflected Ceiling Layout 8 29-Aug-12 06-Sep-12 20-Nov-12 28-Nov-12 68
A121900 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 29-Aug-12 06-Sep-12 03-Dec-12 11-Dec-12 78
A121840 Submission of Wardrobe Details 8 15-Oct-12 23-Oct-12 24-Dec-12 02-Jan-13 56
A121880 Submission of Floors Layout and Details 8 29-Oct-12 06-Nov-12 10-Feb-13 18-Feb-13 85
A121850 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 11-Feb-13 19-Feb-13 66
A121870 Submission of Doors Details 8 22-Nov-12 01-Dec-12 03-Feb-13 11-Feb-13 59
A121820 Submission of Vanity Counter Details 8 17-Dec-12 25-Dec-12 12-Feb-13 20-Feb-13 47
A121890 Submission of Carpet Flooring Details 8 16-Feb-13 24-Feb-13 17-Mar-13 25-Mar-13 25
A121930 Submission of Sinage Layout and Details 8 16-Feb-13 24-Feb-13 23-Mar-13 31-Mar-13 30
A121940 Submission of Furniture Layout and Detals 8 01-Jun-13 10-Jun-13 01-Jul-13 09-Jul-13 25
ApprovalApproval 205 09-Sep-12 30-Jun-13 29-Nov-12 29-Jul-13 21
A122200 Approval of Reflected Ceiling Layout 14 09-Sep-12 26-Sep-12 29-Nov-12 19-Dec-12 57
A122240 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Sep-12 26-Sep-12 12-Dec-12 31-Dec-12 65
A122180 Approval of Wardrobe Details 14 24-Oct-12 13-Nov-12 03-Jan-13 22-Jan-13 47
A122220 Approval of Floors Layout and Details 14 07-Nov-12 27-Nov-12 19-Feb-13 10-Mar-13 70
A122190 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 20-Feb-13 11-Mar-13 55
A122210 Approval of Doors Details 14 03-Dec-12 20-Dec-12 12-Feb-13 03-Mar-13 49
A122160 Approval of Vanity Counter Details 14 26-Dec-12 15-Jan-13 21-Feb-13 12-Mar-13 39
A122230 Approval of Carpet Flooring Details 14 25-Feb-13 14-Mar-13 26-Mar-13 14-Apr-13 21
A122270 Approval of Sinage Layout and Details 14 25-Feb-13 14-Mar-13 01-Apr-13 18-Apr-13 25
A122280 Approval of Furniture Layout and Detals 14 11-Jun-13 30-Jun-13 10-Jul-13 29-Jul-13 21
Roof - UppeRoof - Upper Roof Floor 32 29-Aug-12 04-Oct-12 29-Nov-12 21-Apr-13 164
GeneralGeneral 32 29-Aug-12 04-Oct-12 29-Nov-12 21-Apr-13 164
SubmissiSubmission 16 29-Aug-12 16-Sep-12 29-Nov-12 01-Apr-13 163
A123070 Submission of Block Work Setting Out Plan for Roof&Upper ... 8 29-Aug-12 06-Sep-12 29-Nov-12 09-Dec-12 76
A122970 Submission of Roof's Water Proofing System 8 08-Sep-12 16-Sep-12 07-Feb-13 16-Feb-13 125
A123000 Submission of Doors Details 8 08-Sep-12 16-Sep-12 24-Mar-13 01-Apr-13 163
A123030 Submission of Flooring Layout 8 08-Sep-12 16-Sep-12 06-Jan-13 14-Jan-13 98
ApprovalApproval 20 09-Sep-12 04-Oct-12 10-Dec-12 21-Apr-13 136
A123160 Approval of Block Work Setting Out Plan for for Roof&Upper ... 14 09-Sep-12 26-Sep-12 10-Dec-12 27-Dec-12 63
A123090 Approval of Roof's Water Proofing System 14 17-Sep-12 04-Oct-12 17-Feb-13 06-Mar-13 104
A123120 Approval of Doors Details 14 17-Sep-12 04-Oct-12 02-Apr-13 21-Apr-13 136
A123150 Approval of Flooring Layout 14 17-Sep-12 04-Oct-12 15-Jan-13 04-Feb-13 82
Residentail (BResidentail (Block C) 383 05-Apr-12 07-Jul-13 26-Apr-12 29-Jul-13 19
2nd Baseme2nd Basement Floor 222 05-Apr-12 27-Dec-12 26-Apr-12 08-Apr-13 85
SubmissionSubmission 206 05-Apr-12 09-Dec-12 26-Apr-12 19-Mar-13 84
A121110 Submission of Block Work Setting Out Plan for 2nd Basement 8 05-Apr-12 14-Apr-12 26-Apr-12 05-May-12 18
A121230 Submission of Staircase Layout & Details 8 20-May-12 28-May-12 26-Dec-12 05-Jan-13 182
A121150 Submission of Doors Details 8 31-May-12 09-Jun-12 20-Jan-13 29-Jan-13 192
A121240 Submission of Handrail Layout & Details 8 31-May-12 09-Jun-12 30-Dec-12 08-Jan-13 175
A121140 Submission of Flooring 8 12-Jun-12 21-Jun-12 17-Jan-13 27-Jan-13 180
A121160 Submission of Reflected Ceiling Layout 8 12-Jun-12 21-Jun-12 14-Nov-12 24-Nov-12 128
A121200 Submission of Sinage Layout and Details 8 05-Sep-12 13-Sep-12 11-Mar-13 19-Mar-13 154
A121180 Submission of Parking Layout 8 29-Nov-12 09-Dec-12 03-Feb-13 11-Feb-13 53
A121190 Submission of Traffic Sign Layout 8 29-Nov-12 09-Dec-12 03-Feb-13 11-Feb-13 53
ApprovalApproval 179 15-Apr-12 27-Dec-12 20-Sep-12 08-Apr-13 70
A121390 Approval of Block Work Setting Out Plan for 2nd Basement 14 15-Apr-12 02-May-12 20-Sep-12 09-Oct-12 111
A121370 Approval of Staircase Layout & Details 14 29-May-12 18-Jun-12 06-Jan-13 23-Jan-13 151
A121380 Approval of Handrail Layout & Details 14 10-Jun-12 28-Jun-12 09-Jan-13 29-Jan-13 146
A121430 Approval of Doors Details 14 10-Jun-12 28-Jun-12 30-Jan-13 18-Feb-13 160
A121420 Approval of Flooring 14 24-Jun-12 11-Jul-12 28-Jan-13 14-Feb-13 149
A121440 Approval of Reflected Ceiling Layout 14 24-Jun-12 11-Jul-12 25-Nov-12 13-Dec-12 106
A121480 Approval of Sinage Layout and Details 14 16-Sep-12 03-Oct-12 20-Mar-13 08-Apr-13 128
A121460 Approval of Parking Layout 14 10-Dec-12 27-Dec-12 12-Feb-13 03-Mar-13 44
A121470 Approval of Traffic Sign Layout 14 10-Dec-12 27-Dec-12 12-Feb-13 03-Mar-13 44
1st Baseme1st Basement Floor 203 20-May-12 20-Jan-13 10-Jun-12 14-Apr-13 71
SubmissionSubmission 186 20-May-12 30-Dec-12 10-Jun-12 25-Mar-13 71
A121510 Submission of Block Work Setting Out Plan for 1st Basement 8 20-May-12 28-May-12 10-Jun-12 19-Jun-12 18
A121560 Submission of Reflected Ceiling Layout 8 23-Jun-12 01-Jul-12 25-Nov-12 04-Dec-12 128
A121630 Submission of Staircase Layout & Details 8 23-Jun-12 01-Jul-12 26-Dec-12 05-Jan-13 154
A121640 Submission of Handrail Layout & Details 8 23-Jun-12 01-Jul-12 30-Dec-12 08-Jan-13 157
A121540 Submission of Flooring 8 04-Jul-12 12-Jul-12 21-Jan-13 30-Jan-13 165
A121550 Submission of Doors Details 8 16-Jul-12 24-Jul-12 28-Jan-13 05-Feb-13 160
A121600 Submission of Sinage Layout and Details 8 15-Sep-12 23-Sep-12 17-Mar-13 25-Mar-13 151
A121580 Submission of Parking Layout 8 22-Dec-12 30-Dec-12 03-Feb-13 11-Feb-13 35
A121590 Submission of Traffic Sign Layout 8 22-Dec-12 30-Dec-12 03-Feb-13 11-Feb-13 35
ApprovalApproval 162 29-May-12 20-Jan-13 21-Oct-12 14-Apr-13 59
A121670 Approval of Block Work Setting Out Plan for 1st Basement 14 29-May-12 18-Jun-12 21-Oct-12 08-Nov-12 100
A121650 Approval of Staircase Layout & Details 14 02-Jul-12 19-Jul-12 06-Jan-13 23-Jan-13 128
A121660 Approval of Handrail Layout & Details 14 02-Jul-12 19-Jul-12 09-Jan-13 29-Jan-13 131
A121720 Approval of Reflected Ceiling Layout 14 02-Jul-12 19-Jul-12 05-Dec-12 24-Dec-12 107
A121700 Approval of Flooring 14 15-Jul-12 01-Aug-12 31-Jan-13 19-Feb-13 137
A121710 Approval of Doors Details 14 25-Jul-12 13-Aug-12 06-Feb-13 25-Feb-13 133
A121760 Approval of Sinage Layout and Details 14 24-Sep-12 11-Oct-12 26-Mar-13 14-Apr-13 126
A121740 Approval of Parking Layout 14 31-Dec-12 20-Jan-13 12-Feb-13 03-Mar-13 29
A121750 Approval of Traffic Sign Layout 14 31-Dec-12 20-Jan-13 12-Feb-13 03-Mar-13 29
Ground FloGround Floor 133 23-Jun-12 29-Nov-12 14-Jul-12 11-Apr-13 111
SubmissionSubmission 116 23-Jun-12 08-Nov-12 14-Jul-12 24-Mar-13 112
A120780 Submission of Block Work Setting Out Plan for Ground 8 23-Jun-12 01-Jul-12 14-Jul-12 22-Jul-12 18
A121250 Submission of Staircase Layout & Details 8 02-Jul-12 10-Jul-12 28-Jan-13 05-Feb-13 172
A120750 Submission of Flooring Layout 8 08-Jul-12 16-Jul-12 18-Dec-12 26-Dec-12 134
A120740 Submission of Reflected Ceiling Layout 8 19-Jul-12 28-Jul-12 23-Dec-12 31-Dec-12 128
A121260 Submission of Handrail Layout & Details 8 19-Jul-12 28-Jul-12 02-Feb-13 10-Feb-13 161
A120760 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 06-Aug-12 14-Aug-12 29-Jan-13 06-Feb-13 143
A120720 Submission of Doors Details 8 01-Sep-12 09-Sep-12 02-Feb-13 10-Feb-13 126
A120730 Submission of Sinage Layout and Details 8 31-Oct-12 08-Nov-12 16-Mar-13 24-Mar-13 112
ApprovalApproval 105 02-Jul-12 29-Nov-12 11-Nov-12 11-Apr-13 92
A120860 Approval of Block Work Setting Out Plan for Ground 14 02-Jul-12 19-Jul-12 11-Nov-12 29-Nov-12 91
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Sinage Layout and Details
Submission of Irrigation Layout & Details
Submission of Sky Light Details
Submission of Carpet Flooring Details
Submission of Furniture Layout and Det
Approval of Reflected Ceiling Layout
Approval of Landscaping's Water Proofing Details
Approval of Doors Details
Approval of Landscaping Layout & Details
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Pool Deck Layout
Approval of Flooring Layout
Approval of Sinage Layout and Details
Approval of Irrigation Layout & Details
Approval of Sky Light Details
Approval of Carpet Flooring Details
Approval of Furniture Layout and De
Submission of Reflected Ceiling Layout
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Mirror Details
Submission of Doors Details
Submission of Vanity Counter Details
Submission of Carpet Flooring Details
Submission of Sinage Layout and Details
Submission of Furniture Layout and Det
Approval of Reflected Ceiling Layout
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Mirror Details
Approval of Doors Details
Approval of Vanity Counter Details
Approval of Carpet Flooring Details
Approval of Sinage Layout and Details
Approval of Furniture Layout and De
Submission of Block Work Setting Out Plan for Roof&Upper Roof
Submission of Roof's Water Proofing System
Submission of Doors Details
Submission of Flooring Layout
Approval of Block Work Setting Out Plan for for Roof&Upper Roof
Approval of Roof's Water Proofing System
Approval of Doors Details
Approval of Flooring Layout
Submission of Block Work Setting Out Plan for 2nd Basement
Submission of Staircase Layout & Details
Submission of Doors Details
Submission of Handrail Layout & Details
Submission of Flooring
Submission of Reflected Ceiling Layout
Submission of Sinage Layout and Details
Submission of Parking Layout
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 2nd Basement
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Doors Details
Approval of Flooring
Approval of Reflected Ceiling Layout
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for 1st Basement
Submission of Reflected Ceiling Layout
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Flooring
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Parking Layout
Submission of Traffic Sign Layout
Approval of Block Work Setting Out Plan for 1st Basement
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Reflected Ceiling Layout
Approval of Flooring
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Parking Layout
Approval of Traffic Sign Layout
Submission of Block Work Setting Out Plan for Ground
Submission of Staircase Layout & Details
Submission of Flooring Layout
Submission of Reflected Ceiling Layout
Submission of Handrail Layout & Details
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Doors Details
Submission of Sinage Layout and Details
Approval of Block Work Setting Out Plan for Ground
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 8 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A121350 Approval of Staircase Layout & Details 14 11-Jul-12 30-Jul-12 06-Feb-13 25-Feb-13 143
A120830 Approval of Flooring Layout 14 17-Jul-12 05-Aug-12 27-Dec-12 16-Jan-13 112
A120820 Approval of Reflected Ceiling Layout 14 29-Jul-12 15-Aug-12 02-Jan-13 21-Jan-13 107
A121360 Approval of Handrail Layout & Details 14 29-Jul-12 15-Aug-12 11-Feb-13 28-Feb-13 134
A120840 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 15-Aug-12 05-Sep-12 07-Feb-13 26-Feb-13 119
A120800 Approval of Doors Details 14 10-Sep-12 27-Sep-12 11-Feb-13 28-Feb-13 105
A120810 Approval of Sinage Layout and Details 14 11-Nov-12 29-Nov-12 25-Mar-13 11-Apr-13 92
Typical FlooTypical Floors 163 02-Jul-12 15-Jan-13 23-Jul-12 14-Apr-13 75
GeneralGeneral 79 02-Jul-12 03-Oct-12 23-Jul-12 27-Nov-12 44
SubmissiSubmission 62 02-Jul-12 13-Sep-12 23-Jul-12 06-Nov-12 44
A119930 Submission of Block Work Setting Out Plan for 1st Floor 8 02-Jul-12 10-Jul-12 23-Jul-12 31-Jul-12 18
A119690 Submission of Block Work Setting Out Plan for 2nd Floor 8 11-Jul-12 19-Jul-12 12-Aug-12 22-Aug-12 27
A119700 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 21-Jul-12 29-Jul-12 30-Aug-12 08-Sep-12 33
A119710 Submission of Block Work Setting Out Plan for 7th Floor 8 05-Sep-12 13-Sep-12 29-Oct-12 06-Nov-12 44
ApprovalApproval 59 11-Jul-12 03-Oct-12 07-Aug-12 27-Nov-12 37
A119970 Approval of Block Work Setting Out Plan for 1st Floor 14 11-Jul-12 30-Jul-12 07-Aug-12 28-Aug-12 19
A119940 Approval of Block Work Setting Out Plan for 2nd Floor 14 22-Jul-12 08-Aug-12 23-Aug-12 11-Sep-12 22
A119950 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 30-Jul-12 16-Aug-12 09-Sep-12 26-Sep-12 27
A119960 Approval of Block Work Setting Out Plan for 7th Floor 14 16-Sep-12 03-Oct-12 07-Nov-12 27-Nov-12 37
Corridor / GCorridor / General 105 04-Aug-12 10-Dec-12 08-Dec-12 11-Apr-13 103
SubmissiSubmission 88 04-Aug-12 19-Nov-12 08-Dec-12 24-Mar-13 104
A121270 Submission of Staircase Layout & Details 8 04-Aug-12 12-Aug-12 08-Jan-13 16-Jan-13 128
A121280 Submission of Handrail Layout & Details 8 04-Aug-12 12-Aug-12 12-Jan-13 20-Jan-13 131
A119890 Submission of Reflected Ceiling Layout 8 16-Sep-12 24-Sep-12 08-Dec-12 16-Dec-12 67
A119860 Submission of Doors Details 8 29-Oct-12 06-Nov-12 21-Jan-13 30-Jan-13 69
A119880 Submission of Sinage Layout and Details 8 29-Oct-12 06-Nov-12 16-Mar-13 24-Mar-13 114
A119910 Submission of Flooring Layout 8 10-Nov-12 19-Nov-12 17-Jan-13 27-Jan-13 56
ApprovalApproval 81 13-Aug-12 10-Dec-12 17-Dec-12 11-Apr-13 86
A121330 Approval of Staircase Layout & Details 14 13-Aug-12 03-Sep-12 17-Jan-13 06-Feb-13 107
A121340 Approval of Handrail Layout & Details 14 13-Aug-12 03-Sep-12 21-Jan-13 10-Feb-13 109
A120020 Approval of Reflected Ceiling Layout 14 25-Sep-12 14-Oct-12 17-Dec-12 06-Jan-13 56
A119990 Approval of Doors Details 14 07-Nov-12 27-Nov-12 31-Jan-13 19-Feb-13 57
A120010 Approval of Sinage Layout and Details 14 07-Nov-12 27-Nov-12 25-Mar-13 11-Apr-13 94
A120040 Approval of Flooring Layout 14 20-Nov-12 10-Dec-12 28-Jan-13 14-Feb-13 46
One Bed ROne Bed Room Apartements 105 10-Sep-12 15-Jan-13 14-Nov-12 14-Apr-13 75
SubmissiSubmission 88 10-Sep-12 25-Dec-12 14-Nov-12 25-Mar-13 75
A119800 Submission of Wet Area Ceramic & Pocalin Layout 8 10-Sep-12 18-Sep-12 19-Jan-13 28-Jan-13 107
A119760 Submission of Reflected Ceiling Layout 8 22-Sep-12 30-Sep-12 14-Nov-12 24-Nov-12 44
A119740 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 13-Dec-12 22-Dec-12 37
A119780 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 08-Jan-13 16-Jan-13 48
A119720 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 04-Feb-13 12-Feb-13 50
A119750 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 04-Feb-13 12-Feb-13 50
A119770 Submission of Doors Details 8 05-Dec-12 13-Dec-12 26-Jan-13 03-Feb-13 42
A119830 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 17-Mar-13 25-Mar-13 85
A119730 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 03-Feb-13 11-Feb-13 39
ApprovalApproval 81 19-Sep-12 15-Jan-13 25-Nov-12 14-Apr-13 62
A120140 Approval of Wet Area Ceramic & Pocalin Layout 14 19-Sep-12 08-Oct-12 29-Jan-13 17-Feb-13 89
A120100 Approval of Reflected Ceiling Layout 14 01-Oct-12 18-Oct-12 25-Nov-12 13-Dec-12 37
A120080 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 23-Dec-12 10-Jan-13 30
A120120 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 17-Jan-13 06-Feb-13 40
A120060 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 13-Feb-13 04-Mar-13 41
A120090 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 13-Feb-13 04-Mar-13 41
A120110 Approval of Doors Details 14 16-Dec-12 03-Jan-13 04-Feb-13 21-Feb-13 34
A120170 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 26-Mar-13 14-Apr-13 70
A120070 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 12-Feb-13 03-Mar-13 32
Two Bed RTwo Bed Room Apartements 125 15-Aug-12 15-Jan-13 20-Oct-12 08-Apr-13 70
SubmissiSubmission 108 15-Aug-12 25-Dec-12 20-Oct-12 19-Mar-13 70
A120270 Submission of Wet Area Ceramic & Pocalin Layout 8 15-Aug-12 26-Aug-12 23-Jan-13 02-Feb-13 131
A120230 Submission of Reflected Ceiling Layout 8 22-Sep-12 30-Sep-12 20-Oct-12 30-Oct-12 24
A120210 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 29-Nov-12 09-Dec-12 26
A120250 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 26-Dec-12 05-Jan-13 38
A120190 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 11-Feb-13 19-Feb-13 56
A120220 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54
A120240 Submission of Doors Details 8 05-Dec-12 13-Dec-12 27-Jan-13 04-Feb-13 43
A120300 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 11-Mar-13 19-Mar-13 80
A120200 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 07-Feb-13 16-Feb-13 43
ApprovalApproval 98 27-Aug-12 15-Jan-13 31-Oct-12 08-Apr-13 58
A120400 Approval of Wet Area Ceramic & Pocalin Layout 14 27-Aug-12 13-Sep-12 03-Feb-13 20-Feb-13 109
A120360 Approval of Reflected Ceiling Layout 14 01-Oct-12 18-Oct-12 31-Oct-12 20-Nov-12 21
A120340 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 10-Dec-12 27-Dec-12 21
A120380 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 06-Jan-13 23-Jan-13 31
A120320 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 20-Feb-13 11-Mar-13 46
A120350 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44
A120370 Approval of Doors Details 14 16-Dec-12 03-Jan-13 05-Feb-13 24-Feb-13 35
A120430 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 20-Mar-13 08-Apr-13 66
A120330 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 17-Feb-13 06-Mar-13 35
Three BedThree Bed Room Apartements 125 15-Aug-12 15-Jan-13 02-Oct-12 08-Apr-13 70
SubmissiSubmission 108 15-Aug-12 25-Dec-12 02-Oct-12 19-Mar-13 70
A120530 Submission of Wet Area Ceramic & Pocalin Layout 8 15-Aug-12 26-Aug-12 17-Jan-13 27-Jan-13 126
A120490 Submission of Reflected Ceiling Layout 8 29-Aug-12 06-Sep-12 02-Oct-12 10-Oct-12 29
A120470 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 20-Nov-12 28-Nov-12 18
A120510 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 15-Dec-12 23-Dec-12 28
A120450 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54
A120480 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54
A120500 Submission of Doors Details 8 05-Dec-12 13-Dec-12 21-Jan-13 30-Jan-13 39
A120560 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 11-Mar-13 19-Mar-13 80
A120460 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 28-Jan-13 05-Feb-13 34
ApprovalApproval 98 27-Aug-12 15-Jan-13 11-Oct-12 08-Apr-13 58
A120660 Approval of Wet Area Ceramic & Pocalin Layout for 14 27-Aug-12 13-Sep-12 28-Jan-13 14-Feb-13 105
A120620 Approval of Reflected Ceiling Layout 14 09-Sep-12 26-Sep-12 11-Oct-12 31-Oct-12 24
A120600 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 29-Nov-12 19-Dec-12 15
A120640 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 24-Dec-12 13-Jan-13 23
A120580 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44
A120610 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44
A120630 Approval of Doors Details 14 16-Dec-12 03-Jan-13 31-Jan-13 19-Feb-13 32
A120690 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 20-Mar-13 08-Apr-13 66
A120590 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 06-Feb-13 25-Feb-13 28
Roof - UppeRoof - Upper Roof Floor 241 22-Sep-12 07-Jul-13 14-Oct-12 29-Jul-13 19
GeneralGeneral 83 22-Sep-12 31-Dec-12 14-Oct-12 27-Mar-13 72
SubmissiSubmission 66 22-Sep-12 11-Dec-12 14-Oct-12 09-Mar-13 73
A120970 Submission of Block Work Setting Out Plan for Roof & upper ... 8 22-Sep-12 30-Sep-12 14-Oct-12 22-Oct-12 19
A120870 Submission of Roof's Water Proofing System 8 01-Oct-12 09-Oct-12 06-Jan-13 14-Jan-13 78
A120880 Submission of Pool Deck Layout 8 07-Oct-12 15-Oct-12 09-Feb-13 17-Feb-13 101
A120900 Submission of Doors Details 8 07-Nov-12 17-Nov-12 23-Feb-13 03-Mar-13 88
A121290 Submission of Staircase Layout & Details 8 07-Nov-12 17-Nov-12 28-Jan-13 05-Feb-13 66
A120920 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 03-Dec-12 11-Dec-12 25-Feb-13 05-Mar-13 70
A120930 Submission of Flooring Layout 8 03-Dec-12 11-Dec-12 28-Feb-13 09-Mar-13 73
A121300 Submission of Handrail Layout & Details 8 03-Dec-12 11-Dec-12 02-Feb-13 10-Feb-13 50
ApprovalApproval 63 01-Oct-12 31-Dec-12 25-Nov-12 27-Mar-13 60
A121060 Approval of Block Work Setting Out Plan for Ground 14 01-Oct-12 18-Oct-12 25-Nov-12 13-Dec-12 37
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Staircase Layout & Details
Approval of Flooring Layout
Approval of Reflected Ceiling Layout
Approval of Handrail Layout & Details
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Doors Details
Approval of Sinage Layout and Details
Submission of Block Work Setting Out Plan for 1st Floor
Submission of Block Work Setting Out Plan for 2nd Floor
Submission of Block Work Setting Out Plan for 3rd to 6th Floor
Submission of Block Work Setting Out Plan for 7th Floor
Approval of Block Work Setting Out Plan for 1st Floor
Approval of Block Work Setting Out Plan for 2nd Floor
Approval of Block Work Setting Out Plan for 3rd to 6th Floor
Approval of Block Work Setting Out Plan for 7th Floor
Submission of Staircase Layout & Details
Submission of Handrail Layout & Details
Submission of Reflected Ceiling Layout
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Flooring Layout
Approval of Staircase Layout & Details
Approval of Handrail Layout & Details
Approval of Reflected Ceiling Layout
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Flooring Layout
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Mirror Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Kitchen Cabinet Details
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Mirror Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Kitchen Cabinet Details
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Mirror Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Kitchen Cabinet Details
Approval of Wet Area Ceramic & Pocalin Layout
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Mirror Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Kitchen Cabinet Details
Submission of Wet Area Ceramic & Pocalin Layout
Submission of Reflected Ceiling Layout
Submission of Wardrobe Details
Submission of Floors Layout and Details
Submission of Vanity Counter Details
Submission of Mirror Details
Submission of Doors Details
Submission of Sinage Layout and Details
Submission of Kitchen Cabinet Details
Approval of Wet Area Ceramic & Pocalin Layout for
Approval of Reflected Ceiling Layout
Approval of Wardrobe Details
Approval of Floors Layout and Details
Approval of Vanity Counter Details
Approval of Mirror Details
Approval of Doors Details
Approval of Sinage Layout and Details
Approval of Kitchen Cabinet Details
Submission of Block Work Setting Out Plan for Roof & upper Roof
Submission of Roof's Water Proofing System
Submission of Pool Deck Layout
Submission of Doors Details
Submission of Staircase Layout & Details
Submission of Wet Area Ceramic & Pocalin Layout for Toilets
Submission of Flooring Layout
Submission of Handrail Layout & Details
Approval of Block Work Setting Out Plan for Ground
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 9 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A120990 Approval of Roof's Water Proofing System 14 10-Oct-12 30-Oct-12 15-Jan-13 04-Feb-13 65
A121000 Approval of Pool Deck Layout 14 16-Oct-12 05-Nov-12 18-Feb-13 07-Mar-13 84
A121020 Approval of Doors Details 14 18-Nov-12 06-Dec-12 04-Mar-13 21-Mar-13 73
A121310 Approval of Staircase Layout & Details 14 18-Nov-12 06-Dec-12 06-Feb-13 25-Feb-13 55
A121040 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 12-Dec-12 31-Dec-12 06-Mar-13 25-Mar-13 58
A121050 Approval of Flooring Layout 14 12-Dec-12 31-Dec-12 10-Mar-13 27-Mar-13 60
A121320 Approval of Handrail Layout & Details 14 12-Dec-12 31-Dec-12 11-Feb-13 28-Feb-13 41
GymnasiumGymnasium 213 24-Oct-12 07-Jul-13 27-Dec-12 29-Jul-13 19
SubmissiSubmission 196 24-Oct-12 17-Jun-13 27-Dec-12 09-Jul-13 19
A120950 Submission of Reflected Ceiling Layout 8 24-Oct-12 04-Nov-12 27-Dec-12 06-Jan-13 51
A120980 Submission of Vinyl Floor Detals 8 08-Jan-13 16-Jan-13 31-Jan-13 09-Feb-13 19
A120960 Submission of Furniture Layout and Details 8 09-Jun-13 17-Jun-13 01-Jul-13 09-Jul-13 19
ApprovalApproval 170 05-Nov-12 07-Jul-13 07-Jan-13 29-Jul-13 16
A121080 Approval of Reflected Ceiling Layout 14 05-Nov-12 25-Nov-12 07-Jan-13 27-Jan-13 42
A121100 Approval of Vinyl Floor Detals 14 17-Jan-13 06-Feb-13 10-Mar-13 27-Mar-13 35
A121090 Approval of Furniture Layout and Detals 14 18-Jun-13 07-Jul-13 10-Jul-13 29-Jul-13 16
Speciality WSpeciality Works 235 05-May-12 12-Feb-13 07-Jun-12 05-Jun-13 97
Swimming PoSwimming Pool 78 03-Jul-12 03-Oct-12 26-Dec-12 20-Feb-13 114
SubmissionSubmission 62 03-Jul-12 15-Sep-12 26-Dec-12 02-Feb-13 114
A53720 Submission of Swimming Pool Layout & Details for Block A 12 03-Jul-12 16-Jul-12 13-Jan-13 27-Jan-13 159
A53730 Submission of Swimming Pool 's Water Prrofing for Block A 12 03-Jul-12 16-Jul-12 19-Jan-13 02-Feb-13 164
A118850 Submission of Swimming Pool Layout & Details for Block B 12 03-Jul-12 16-Jul-12 26-Dec-12 09-Jan-13 145
A118860 Submission of Swimming Pool 's Water Prrofing for Block B 12 03-Jul-12 16-Jul-12 02-Jan-13 15-Jan-13 150
A118870 Submission of Swimming Pool Layout & Details for Block C 12 02-Sep-12 15-Sep-12 03-Jan-13 16-Jan-13 101
A118880 Submission of Swimming Pool 's Water Prrofing for Block C 12 02-Sep-12 15-Sep-12 08-Jan-13 21-Jan-13 105
ApprovalApproval 55 17-Jul-12 03-Oct-12 10-Jan-13 20-Feb-13 95
A118900 Approval of Swimming Pool Layout & Details for Block A 14 17-Jul-12 05-Aug-12 28-Jan-13 14-Feb-13 132
A118910 Approval of Swimming Pool 's Water Prrofing for Block A 14 17-Jul-12 05-Aug-12 03-Feb-13 20-Feb-13 136
A118920 Approval of Swimming Pool Layout & Details for Block B 14 17-Jul-12 05-Aug-12 10-Jan-13 30-Jan-13 121
A118930 Approval of Swimming Pool 's Water Proofing for Block B 14 17-Jul-12 05-Aug-12 16-Jan-13 05-Feb-13 125
A118940 Approval of Swimming Pool Layout & Details for Block C 14 16-Sep-12 03-Oct-12 17-Jan-13 06-Feb-13 85
A118950 Approval of Swimming Pool 's Water Proofing for Block C 14 16-Sep-12 03-Oct-12 22-Jan-13 11-Feb-13 88
External FacaExternal Facade 165 26-Jul-12 12-Feb-13 16-Oct-12 15-May-13 79
Hotel ApartHotel Apartements (Block A) 135 26-Jul-12 07-Jan-13 16-Oct-12 27-Mar-13 67
SubmissionSubmission 118 26-Jul-12 17-Dec-12 16-Oct-12 09-Mar-13 68
A118250 Submission of External Elevation - North 10 26-Jul-12 06-Aug-12 16-Oct-12 29-Oct-12 68
A118260 Submission of External Elevation - South 10 26-Jul-12 06-Aug-12 14-Jan-13 26-Jan-13 140
A118290 Submission of Aluminum Curtain Wall Layout & Details 10 26-Jul-12 06-Aug-12 16-Oct-12 29-Oct-12 68
A118270 Submission of External Elevation - East 10 07-Aug-12 18-Aug-12 27-Jan-13 06-Feb-13 140
A118280 Submission of External Elevation - West 10 07-Aug-12 18-Aug-12 27-Jan-13 06-Feb-13 140
A118300 Submission of GRC Layout & Details 8 09-Dec-12 17-Dec-12 28-Feb-13 09-Mar-13 68
ApprovalApproval 104 07-Aug-12 07-Jan-13 07-Feb-13 27-Mar-13 56
A118310 Approval of External Elevation - North 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125
A118320 Approval of External Elevation - South 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125
A118350 Approval of Aluminum Curtain Wall Layout & Details 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125
A118330 Approval of External Elevation - East 14 21-Aug-12 09-Sep-12 07-Feb-13 26-Feb-13 117
A118340 Approval of External Elevation - West 14 21-Aug-12 09-Sep-12 07-Feb-13 26-Feb-13 117
A118360 Approval of GRC Layout & Details 14 18-Dec-12 07-Jan-13 10-Mar-13 27-Mar-13 56
Hotel (BlocHotel (Block B) 135 02-Sep-12 12-Feb-13 09-Dec-12 15-May-13 79
SubmissionSubmission 118 02-Sep-12 22-Jan-13 09-Dec-12 27-Apr-13 80
A124230 Submission of External Elevation - North 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80
A124240 Submission of External Elevation - South 10 02-Sep-12 12-Sep-12 14-Jan-13 26-Jan-13 110
A124270 Submission of Aluminum Curtain Wall Layout & Details 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80
A124250 Submission of External Elevation - East 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110
A124260 Submission of External Elevation - West 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110
A124280 Submission of GRC Layout & Details 8 14-Jan-13 22-Jan-13 18-Apr-13 27-Apr-13 80
ApprovalApproval 104 13-Sep-12 12-Feb-13 07-Feb-13 15-May-13 66
A124290 Approval of External Elevation - North 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124300 Approval of External Elevation - South 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124330 Approval of Aluminum Curtain Wall Layout & Details 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124310 Approval of External Elevation - East 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92
A124320 Approval of External Elevation - West 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92
A124340 Approval of GRC Layout & Details 14 23-Jan-13 12-Feb-13 28-Apr-13 15-May-13 66
ResidentailResidentail (Block C) 135 02-Sep-12 12-Feb-13 09-Dec-12 15-May-13 79
SubmissionSubmission 118 02-Sep-12 22-Jan-13 09-Dec-12 27-Apr-13 80
A124350 Submission of External Elevation - North 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80
A124360 Submission of External Elevation - South 10 02-Sep-12 12-Sep-12 14-Jan-13 26-Jan-13 110
A124390 Submission of Aluminum Curtain Wall Layout & Details 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80
A124370 Submission of External Elevation - East 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110
A124380 Submission of External Elevation - West 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110
A124400 Submission of GRC Layout & Details 8 14-Jan-13 22-Jan-13 18-Apr-13 27-Apr-13 80
ApprovalApproval 104 13-Sep-12 12-Feb-13 07-Feb-13 15-May-13 66
A124410 Approval of External Elevation - North 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124420 Approval of External Elevation - South 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124450 Approval of Aluminum Curtain Wall Layout & Details 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100
A124430 Approval of External Elevation - East 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92
A124440 Approval of External Elevation - West 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92
A124460 Approval of GRC Layout & Details 14 23-Jan-13 12-Feb-13 28-Apr-13 15-May-13 66
Facade CleanFacade Cleaning 32 26-Nov-12 03-Jan-13 01-May-13 05-Jun-13 130
SubmissionSubmission 15 26-Nov-12 13-Dec-12 01-May-13 18-May-13 131
A118560 Submission of Glass Cleaning Machine 15 26-Nov-12 13-Dec-12 01-May-13 18-May-13 131
ApprovalApproval 14 16-Dec-12 03-Jan-13 19-May-13 05-Jun-13 108
A118960 Approval of Glass Cleaning Machine 14 16-Dec-12 03-Jan-13 19-May-13 05-Jun-13 108
Garbage ChuGarbage Chute 141 05-May-12 18-Oct-12 07-Jun-12 28-Nov-12 32
SubmissionSubmission 125 05-May-12 30-Sep-12 07-Jun-12 05-Nov-12 29
A118810 Submission of Garbage Chute Layout & Details for Block A 15 05-May-12 21-May-12 07-Jun-12 25-Jun-12 29
A118820 Submission of Garbage Chute Layout & Details for Block B 15 09-Jul-12 25-Jul-12 12-Aug-12 30-Aug-12 29
A118830 Submission of Garbage Chute Layout & Details for Block C 15 13-Sep-12 30-Sep-12 17-Oct-12 05-Nov-12 29
ApprovalApproval 105 22-May-12 18-Oct-12 24-Oct-12 28-Nov-12 27
A118970 Approval of Garbage Chute Layout & Details for Block A 14 22-May-12 10-Jun-12 24-Oct-12 13-Nov-12 108
A118980 Approval of Garbage Chute Layout & Details for Block B 14 26-Jul-12 14-Aug-12 08-Nov-12 28-Nov-12 72
A118990 Approval of Garbage Chute Layout & Details for Block C 14 01-Oct-12 18-Oct-12 06-Nov-12 26-Nov-12 25
Linen ChuteLinen Chute 32 03-Jul-12 08-Aug-12 20-Oct-12 28-Nov-12 91
SubmissionSubmission 15 03-Jul-12 19-Jul-12 20-Oct-12 07-Nov-12 91
A118840 Submission of Linen Chute Layout & Details for Block B 15 03-Jul-12 19-Jul-12 20-Oct-12 07-Nov-12 91
ApprovalApproval 14 22-Jul-12 08-Aug-12 08-Nov-12 28-Nov-12 76
A119000 Approval of Linen Chute Layout & Details for Block B 14 22-Jul-12 08-Aug-12 08-Nov-12 28-Nov-12 76
ProvisionalProvisional Sum 249 10-May-12 06-Mar-13 24-May-12 25-Apr-13 43
Kitchen EquiKitchen Equipments 36 10-May-12 21-Jun-12 26-May-12 08-Jul-12 14
SubmissionSubmission 20 10-May-12 02-Jun-12 26-May-12 18-Jun-12 13
A9983 Submission of Kitchen Equipments Drawings 20 10-May-12 02-Jun-12 26-May-12 18-Jun-12 13
ApprovalApproval 14 03-Jun-12 21-Jun-12 19-Jun-12 08-Jul-12 11
A9984 Approval of Kitchen Equipments Drawings 14 03-Jun-12 21-Jun-12 19-Jun-12 08-Jul-12 11
Lundary EquLundary Equipments 36 10-May-12 21-Jun-12 24-May-12 05-Jul-12 12
SubmissionSubmission 20 10-May-12 02-Jun-12 24-May-12 16-Jun-12 12
A9986 Submission of Laundary Equipments Drawings 20 10-May-12 02-Jun-12 24-May-12 16-Jun-12 12
ApprovalApproval 14 03-Jun-12 21-Jun-12 18-Jun-12 05-Jul-12 10
A9987 Approval of Laundary Equipments Drawings 14 03-Jun-12 21-Jun-12 18-Jun-12 05-Jul-12 10
Facade LightFacade Lighting 37 16-May-12 28-Jun-12 09-Jun-12 22-Jul-12 20
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Approval of Roof's Water Proofing System
Approval of Pool Deck Layout
Approval of Doors Details
Approval of Staircase Layout & Details
Approval of Wet Area Ceramic & Pocalin Layout for Toilets
Approval of Flooring Layout
Approval of Handrail Layout & Details
Submission of Reflected Ceiling Layout
Submission of Vinyl Floor Detals
Submission of Furniture Layout and De
Approval of Reflected Ceiling Layout
Approval of VinylFloor Detals
Approval of Furniture Layout and D
Submission of Swimming Pool Layout & Details for Block A
Submission of Swimming Pool 's Water Prrofing for Block A
Submission of Swimming Pool Layout & Details for Block B
Submission of Swimming Pool 's Water Prrofing for Block B
Submission of Swimming Pool Layout & Details for Block C
Submission of Swimming Pool 's Water Prrofing for Block C
Approval of Swimming Pool Layout & Details for Block A
Approval of Swimming Pool 's Water Prrofing for Block A
Approval of Swimming Pool Layout & Details for Block B
Approval of Swimming Pool 's Water Proofing for Block B
Approval of Swimming Pool Layout & Details for Block C
Approval of Swimming Pool 's Water Proofing for Block C
Submission of External Elevation - North
Submission of External Elevation - South
Submission of Aluminum Curtain Wall Layout & Details
Submission of External Elevation - East
Submission of External Elevation - West
Submission of GRC Layout & Details
Approval of External Elevation - North
Approval of External Elevation - South
Approval of Aluminum Curtain Wall Layout & Details
Approval of External Elevation - East
Approval of External Elevation - West
Approval of GRC Layout & Details
Submission of External Elevation - North
Submission of External Elevation - South
Submission of Aluminum Curtain Wall Layout & Details
Submission of External Elevation - East
Submission of External Elevation - West
Submission of GRC Layout & Details
Approval of External Elevation - North
Approval of External Elevation - South
Approval of Aluminum Curtain Wall Layout & Details
Approval of External Elevation - East
Approval of External Elevation - West
Approval of GRC Layout & Details
Submission of External Elevation - North
Submission of External Elevation - South
Submission of Aluminum Curtain Wall Layout & Details
Submission of External Elevation - East
Submission of External Elevation - West
Submission of GRC Layout & Details
Approval of External Elevation - North
Approval of External Elevation - South
Approval of Aluminum Curtain Wall Layout & Details
Approval of External Elevation - East
Approval of External Elevation - West
Approval of GRC Layout & Details
Submission of Glass Cleaning Machine
Approval of Glass Cleaning Machine
Submission of Garbage Chute Layout & Details for Block A
Submission of Garbage Chute Layout & Details for Block B
Submission of Garbage Chute Layout & Details for Block C
Approval of Garbage Chute Layout & Details for Block A
Approval of Garbage Chute Layout & Details for Block B
Approval of Garbage Chute Layout & Details for Block C
Submission of Linen Chute Layout & Details for Block B
Approval of Linen Chute Layout & Details for Block B
Submission of Kitchen Equipments Drawings
Approval of Kitchen Equipments Drawings
Submission of Laundary Equipments Drawings
Approval of Laundary Equipments Drawings
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 10 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
SubmissionSubmission 20 16-May-12 07-Jun-12 09-Jun-12 02-Jul-12 20
A9988 Submission of Facade Lighitng Drawings 20 16-May-12 07-Jun-12 09-Jun-12 02-Jul-12 20
ApprovalApproval 14 10-Jun-12 28-Jun-12 03-Jul-12 22-Jul-12 16
A9991 Approval of Facade Lighitng Drawings 14 10-Jun-12 28-Jun-12 03-Jul-12 22-Jul-12 16
Cooking StatCooking Station 37 26-May-12 08-Jul-12 11-Sep-12 23-Oct-12 90
SubmissionSubmission 20 26-May-12 18-Jun-12 11-Sep-12 03-Oct-12 90
A124680 Submission of Cooking Station Drawings 20 26-May-12 18-Jun-12 11-Sep-12 03-Oct-12 90
ApprovalApproval 14 19-Jun-12 08-Jul-12 04-Oct-12 23-Oct-12 75
A124690 Approval of Cooking Station Drawings 14 19-Jun-12 08-Jul-12 04-Oct-12 23-Oct-12 75
Gymnasium EGymnasium Equipments 34 27-Jan-13 06-Mar-13 18-Mar-13 25-Apr-13 43
SubmissionSubmission 20 27-Jan-13 18-Feb-13 18-Mar-13 09-Apr-13 43
A9977 Submission of Gymnasium Drawings 20 27-Jan-13 18-Feb-13 18-Mar-13 09-Apr-13 43
ApprovalApproval 14 19-Feb-13 06-Mar-13 10-Apr-13 25-Apr-13 43
A9944 Approval of Gymnasium Drawings 14 19-Feb-13 06-Mar-13 10-Apr-13 25-Apr-13 43
Method 0f SMethod 0f Statements 333 04-Jan-12 06-Feb-13 09-Jan-12 05-Jun-13 102
CivilCivil 98 04-Jan-12 28-Apr-12 09-Jan-12 09-Sep-12 112
A46480 Sub & App- MOS for Raft Slab Construction 14 04-Jan-12 19-Jan-12 09-Jan-12 24-Jan-12 4
A46520 Sub & App- MOS for Columns Construction 30 04-Jan-12 08-Feb-12 10-Jan-12 14-Feb-12 5
A46530 Sub & App- MOS for Retaining Walls Construction 30 04-Jan-12 08-Feb-12 10-Jan-12 14-Feb-12 5
A46560 Sub & App- MOS for Core Walls Constrcution 30 05-Jan-12 09-Feb-12 11-Jan-12 15-Feb-12 5
A46510 Sub & App- MOS for Slabs Construction 30 07-Jan-12 11-Feb-12 15-Jan-12 19-Feb-12 7
A46540 Sub & App- MOS for Ramp Construction 30 08-Jan-12 12-Feb-12 22-Jan-12 26-Feb-12 12
A46500 Sub & App- MOS for Backfilling 30 13-Mar-12 16-Apr-12 04-Aug-12 09-Sep-12 122
A46550 Sub & App- MOS for Staircase Construction 30 25-Mar-12 28-Apr-12 02-Aug-12 08-Sep-12 111
ArchitecturalArchitectural 135 07-Feb-12 14-Jul-12 23-Aug-12 05-Mar-13 193
A46570 Sub & App- MOS for Blocks Works 30 07-Feb-12 12-Mar-12 28-Aug-12 01-Oct-12 171
A46580 Sub & App- MOS for Plaster Works 30 07-Feb-12 12-Mar-12 10-Sep-12 14-Oct-12 182
A46600 Sub & App- MOS for Panintng 30 13-Mar-12 16-Apr-12 11-Oct-12 18-Nov-12 179
A46610 Sub & App- MOS for Wall&Floor Tiles 30 25-Mar-12 28-Apr-12 23-Aug-12 26-Sep-12 127
A46620 Sub & App- MOS for Suspended Ceiling System 30 11-Apr-12 15-May-12 20-Dec-12 26-Jan-13 210
A46650 Sub & App- MOS for Doors 30 17-Apr-12 21-May-12 30-Jan-13 05-Mar-13 238
A46630 Sub & App- MOS for Water Proofing for Wet Areas 30 19-Apr-12 23-May-12 25-Dec-12 30-Jan-13 207
A46590 Sub & App- MOS for GRP Lining 30 09-Jun-12 14-Jul-12 03-Oct-12 08-Nov-12 97
MEPMEP 130 01-Feb-12 03-Jul-12 26-Nov-12 25-Feb-13 195
HVACHVAC 60 12-Apr-12 21-Jun-12 06-Dec-12 21-Jan-13 176
A113860 Sub & App- MOS for Piping Works 30 12-Apr-12 16-May-12 06-Dec-12 10-Jan-13 197
A113840 Sub & App- MOS for Duct Works 30 24-Apr-12 28-May-12 11-Dec-12 15-Jan-13 191
A113850 Sub & App- MOS for Fan Coil Instllation 30 17-May-12 21-Jun-12 17-Dec-12 21-Jan-13 176
ElectricalElectrical 30 17-May-12 21-Jun-12 05-Dec-12 09-Jan-13 166
A113870 Sub & App- MOS for MDBs,SMDBs,DBs Installation 30 17-May-12 21-Jun-12 05-Dec-12 09-Jan-13 166
PlumbingPlumbing 130 01-Feb-12 03-Jul-12 19-Dec-12 25-Feb-13 195
A113880 Sub & App- MOS for Pipings 30 01-Feb-12 07-Mar-12 19-Dec-12 23-Jan-13 268
A113890 Sub & App- MOS for Sanitarywares 30 29-May-12 03-Jul-12 21-Jan-13 25-Feb-13 195
Fire FightingFire Fighting 60 12-Apr-12 21-Jun-12 26-Nov-12 31-Jan-13 184
A113910 Sub & App- MOS for Pipings 30 12-Apr-12 16-May-12 26-Nov-12 31-Dec-12 189
A113920 Sub & App- MOS for Testing 30 12-Apr-12 16-May-12 12-Dec-12 16-Jan-13 202
A113930 Sub & App- MOS for Fire Alarm Devices Fixing 30 17-May-12 21-Jun-12 26-Dec-12 31-Jan-13 184
Speciality WSpeciality Works 160 26-Jul-12 06-Feb-13 08-Oct-12 05-Jun-13 102
SwimmimngSwimmimng Pool 49 07-Aug-12 04-Oct-12 31-Dec-12 16-Mar-13 133
A113810 Sub & App- MOS for Water Proofing 30 07-Aug-12 12-Sep-12 31-Dec-12 05-Feb-13 119
A113820 Sub & App- MOS for Tiling 30 01-Sep-12 04-Oct-12 10-Feb-13 16-Mar-13 133
Facade CleanFacade Cleaning System 30 02-Jan-13 06-Feb-13 02-May-13 05-Jun-13 102
A124200 Sub & App- MOS for Facade Cleaning 30 02-Jan-13 06-Feb-13 02-May-13 05-Jun-13 102
Linen ChuteLinen Chute System 50 26-Jul-12 24-Sep-12 08-Oct-12 20-Dec-12 71
A113790 Sub & App- MOS for Piping Installation 30 26-Jul-12 01-Sep-12 08-Oct-12 13-Nov-12 61
A113800 Sub & App- MOS for Equipment Installation 30 21-Aug-12 24-Sep-12 14-Nov-12 20-Dec-12 71
Garbage ChuGarbage Chutes System 50 07-Aug-12 06-Oct-12 22-Oct-12 05-Jan-13 73
A53930 Sub & App- MOS for Piping Installation 30 07-Aug-12 12-Sep-12 22-Oct-12 28-Nov-12 63
A104200 Sub & App- MOS for Equipment Installation 30 02-Sep-12 06-Oct-12 29-Nov-12 05-Jan-13 73
ProcuremeProcurement 441 02-Jan-12 11-Jun-13 09-Jan-12 29-Jul-13 41
Submittion &Submittion & Approval of Prequalification 325 02-Jan-12 26-Jan-13 09-Jan-12 17-Mar-13 43
Domestic SuDomestic Sub Contractors 165 02-Jan-12 14-Jul-12 09-Jan-12 03-Nov-12 92
A8500 Sub & App- Water Proofing Works Subcontractor 2 02-Jan-12 03-Jan-12 09-Jan-12 10-Jan-12 6
A8600 Sub & App- LPG System Subcontractor 21 02-Jan-12 25-Jan-12 20-Jun-12 14-Jul-12 144
A8460 Sub & App- MEP Subcontractor 21 08-Jan-12 31-Jan-12 05-Mar-12 28-Mar-12 48
A8540 Sub & App- Susbended Ceilings Subcontractor 35 02-Jan-12 12-Feb-12 04-Mar-12 12-Apr-12 52
A8480 Sub & App- Garbage Chute System Subcontractor 35 07-Feb-12 18-Mar-12 12-Mar-12 21-Apr-12 29
A8470 Sub & App- Elevators Subcontractor 35 19-Feb-12 29-Mar-12 21-Mar-12 30-Apr-12 27
A8560 Sub & App- GRP Lining Subcontractor 35 13-Mar-12 22-Apr-12 23-Jun-12 01-Aug-12 86
A8444 Sub & App- Linen Chute System Subcontractor 35 13-Mar-12 22-Apr-12 02-Apr-12 12-May-12 17
A8490 Sub & App- Swimming PoolWorks Subcontractor 35 17-Apr-12 27-May-12 26-Apr-12 05-Jun-12 8
A8530 Sub & App- Wood & Joinery Subcontractor 35 17-Apr-12 27-May-12 29-May-12 09-Jul-12 36
A8590 Sub & App- Landscaping Subcontractor 35 17-Apr-12 27-May-12 31-May-12 11-Jul-12 38
A8520 Sub & App- Aluminum&Glazing Works Subcontractor 35 10-May-12 20-Jun-12 30-Jul-12 10-Sep-12 68
A8510 Sub & App- Facade Cleanining Subcontractor 35 22-May-12 02-Jul-12 22-Sep-12 03-Nov-12 102
A8580 Sub & App- Traffic Deck Coating Subcontractor 35 03-Jun-12 14-Jul-12 22-Aug-12 01-Oct-12 66
A8999 Sub & App- Irrigation Works Subcontractor 35 03-Jun-12 14-Jul-12 27-Aug-12 06-Oct-12 70
Nominated SNominated Sub Contractors 236 16-Apr-12 26-Jan-13 30-Apr-12 17-Mar-13 43
Kitchen EquiKitchen Equipments 21 16-Apr-12 09-May-12 01-May-12 24-May-12 13
A8610 Sub & App- Kitchen Equipments Subcontractor 21 16-Apr-12 09-May-12 01-May-12 24-May-12 13
Lundary EquLundary Equipments 21 16-Apr-12 09-May-12 30-Apr-12 23-May-12 12
A114230 Sub & App- Laundary Equipments Subcontractor 21 16-Apr-12 09-May-12 30-Apr-12 23-May-12 12
Facade LightFacade Lighting 21 22-Apr-12 15-May-12 15-May-12 07-Jun-12 20
A8533 Sub & App- Facade Lighting Subcontractor 21 22-Apr-12 15-May-12 15-May-12 07-Jun-12 20
Cooking StatCooking Station 21 01-May-12 24-May-12 15-Aug-12 10-Sep-12 90
A124700 Sub & App- Cooking Station Subcontractor 21 01-May-12 24-May-12 15-Aug-12 10-Sep-12 90
Gymnasium EGymnasium Equipments 21 31-Dec-12 26-Jan-13 21-Feb-13 17-Mar-13 43
A1142 Sub & App- Gym Equipments Subcontractor 21 31-Dec-12 26-Jan-13 21-Feb-13 17-Mar-13 43
Submittion &Submittion & Approval of Material Submittal 344 04-Jan-12 19-Feb-13 11-Jan-12 25-Apr-13 56
CivilCivil 198 04-Jan-12 26-Aug-12 11-Jan-12 13-Nov-12 66
A7630 Sub & App- Water Proofing for Substructure 2 04-Jan-12 05-Jan-12 11-Jan-12 12-Jan-12 6
A7610 Sub & App- Concerete - 1st Pour 5 08-Jan-12 12-Jan-12 11-Jan-12 16-Jan-12 3
A7620 Sub & App- Steel Reinforcement - 1st Patch 5 08-Jan-12 12-Jan-12 11-Jan-12 16-Jan-12 3
A8190 Sub & App- Water Proofing for Wet Areas 21 04-Mar-12 27-Mar-12 01-Aug-12 27-Aug-12 128
A113940 Sub & App- Water Proofing for Roof 21 02-Apr-12 25-Apr-12 24-Jun-12 17-Jul-12 70
A7640 Sub & App- GRP Lining 21 23-Apr-12 16-May-12 02-Aug-12 28-Aug-12 86
A8210 Sub & App- Traffic Coating 35 15-Jul-12 26-Aug-12 02-Oct-12 13-Nov-12 66
ArchitecturalArchitectural 266 19-Jan-12 03-Dec-12 14-Apr-12 10-Mar-13 81
Wet WorksWet Works 36 19-Jan-12 01-Mar-12 28-May-12 17-Jul-12 117
A7310 Sub & App- Blocks 21 19-Jan-12 13-Feb-12 28-May-12 21-Jun-12 110
A7240 Sub & App- Paint Materials 21 31-Jan-12 25-Feb-12 20-Jun-12 14-Jul-12 119
A7300 Sub & App- Plaster Materials 21 07-Feb-12 01-Mar-12 24-Jun-12 17-Jul-12 117
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Submission of Facade Lighitng Drawings
Approval of Facade Lighitng Drawings
Submission of Cooking Station Drawings
Approval of Cooking Station Drawings
Submission of Gymnasium Drawings
Approval of Gymnasium Drawings
Sub & App- MOS for Raft Slab Construction
Sub & App- MOS for Columns Construction
Sub & App- MOS for Retaining Walls Construction
Sub & App- MOS for Core Walls Constrcution
Sub & App- MOS for Slabs Construction
Sub & App- MOS for Ramp Construction
Sub & App- MOS for Backfilling
Sub & App- MOS for Staircase Construction
Sub & App- MOS for Blocks Works
Sub & App- MOS for Plaster Works
Sub & App- MOS for Panintng
Sub & App- MOS for Wall&Floor Tiles
Sub & App- MOS for Suspended Ceiling System
Sub & App- MOS for Doors
Sub & App- MOS for Water Proofing for Wet Areas
Sub & App- MOS for GRP Lining
Sub & App- MOS for Piping Works
Sub & App- MOS for Duct Works
Sub & App- MOS for Fan Coil Instllation
Sub & App- MOS for MDBs,SMDBs,DBs Installation
Sub & App- MOS for Pipings
Sub & App- MOS for Sanitarywares
Sub & App- MOS for Pipings
Sub & App- MOS for Testing
Sub & App- MOS for Fire Alarm Devices Fixing
Sub & App- MOS for Water Proofing
Sub & App- MOS for Tiling
Sub & App- MOS for Facade Cleaning
Sub & App- MOS for Piping Installation
Sub & App- MOS for Equipment Installation
Sub & App- MOS for Piping Installation
Sub & App- MOS for Equipment Installation
Sub & App- Water Proofing Works Subcontractor
Sub & App- LPG System Subcontractor
Sub & App- MEP Subcontractor
Sub & App- Susbended Ceilings Subcontractor
Sub & App- Garbage Chute System Subcontractor
Sub & App- Elevators Subcontractor
Sub & App- GRP Lining Subcontractor
Sub & App- Linen Chute System Subcontractor
Sub & App- Swimming Pool Works Subcontractor
Sub & App- Wood & Joinery Subcontractor
Sub & App- Landscaping Subcontractor
Sub & App- Aluminum&Glazing Works Subcontractor
Sub & App- Facade Cleanining Subcontractor
Sub & App- Traffic Deck Coating Subcontractor
Sub & App- Irrigation Works Subcontractor
Sub & App- Kitchen Equipments Subcontractor
Sub & App- Laundary Equipments Subcontractor
Sub & App- Facade Lighting Subcontractor
Sub & App- Cooking Station Subcontractor
Sub & App- Gym Equipments Subcontractor
Sub & App- Water Proofing for Substructure
Sub & App- Concerete - 1st Pour
Sub & App- Steel Reinforcement - 1st Patch
Sub & App- Water Proofing for Wet Areas
Sub & App- Water Proofing for Roof
Sub & App- GRP Lining
Sub & App- Traffic Coating
Sub & App- Blocks
Sub & App- Paint Materials
Sub & App- Plaster Materials
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 11 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
CeilingCeiling 21 13-Feb-12 07-Mar-12 14-Apr-12 07-May-12 52
A7260 Sub & App- Ceiling Suspension System 21 13-Feb-12 07-Mar-12 14-Apr-12 07-May-12 52
Walls & FlooWalls & Floors 211 13-Mar-12 20-Nov-12 31-May-12 20-Dec-12 25
A7230 Sub & App- Porcelain Tiles 21 13-Mar-12 05-Apr-12 31-May-12 25-Jun-12 68
A7490 Sub & App- Ceramic Tiles 21 13-Mar-12 05-Apr-12 31-Jul-12 26-Aug-12 119
A7270 Sub & App- Granite Tiles 21 25-Mar-12 17-Apr-12 16-Oct-12 11-Nov-12 173
A8370 Sub & App- MDF Cladding 21 25-Mar-12 17-Apr-12 16-Aug-12 11-Sep-12 123
A114010 Sub & App- Natural Stone 21 25-Mar-12 17-Apr-12 26-Sep-12 20-Oct-12 156
A113970 Sub & App- Carpet Tiles 21 05-Apr-12 29-Apr-12 06-Oct-12 31-Oct-12 154
A114040 Sub & App- Veneer Cladding 21 05-Apr-12 29-Apr-12 18-Aug-12 12-Sep-12 114
A7480 Sub & App- Terrazo Tiles 21 29-Apr-12 22-May-12 22-Sep-12 15-Oct-12 122
A7500 Sub & App- Marble Tiles 21 29-Apr-12 22-May-12 06-Nov-12 01-Dec-12 159
A7660 Sub & App- Vinyel Sheet 21 29-Apr-12 22-May-12 14-Oct-12 08-Nov-12 141
A114030 Sub & App- Raised Floor Tiles 21 29-Apr-12 22-May-12 04-Nov-12 28-Nov-12 157
A114050 Sub & App- Wenge cCladding 21 29-Apr-12 22-May-12 13-Sep-12 07-Oct-12 115
A113990 Sub & App- Honed Limestone 21 22-May-12 14-Jun-12 04-Oct-12 30-Oct-12 113
A114000 Sub & App- Mosiac Tiles 21 22-May-12 14-Jun-12 07-Aug-12 02-Sep-12 65
A7520 Sub & App- Wooden Floor 21 28-May-12 21-Jun-12 08-Sep-12 01-Oct-12 85
A114020 Sub & App- Polished Moche Tiles 21 03-Jun-12 27-Jun-12 04-Oct-12 30-Oct-12 103
A7670 Sub & App- Precast Conc. Interlocking Paving 21 09-Jul-12 01-Aug-12 09-Oct-12 04-Nov-12 77
A7680 Sub & App- Precast Conc. Kerbs 21 09-Jul-12 01-Aug-12 30-Sep-12 23-Oct-12 69
A113950 Sub & App- Heavy Duty Tiles 21 01-Aug-12 27-Aug-12 26-Nov-12 20-Dec-12 95
A8360 Sub & App- Vinyl Wall Covering 21 08-Sep-12 01-Oct-12 13-Nov-12 09-Dec-12 55
A7510 Sub & App- Carpet 21 24-Oct-12 20-Nov-12 31-Oct-12 25-Nov-12 4
Doors & WinDoors & Windows 146 25-Jan-12 15-Jul-12 22-Aug-12 17-Nov-12 102
A7430 Sub & App- Aluminum Louver Doors 21 25-Jan-12 19-Feb-12 06-Oct-12 31-Oct-12 214
A7450 Sub & App- Fire Rated Doors 21 25-Jan-12 19-Feb-12 08-Oct-12 03-Nov-12 216
A7350 Sub & App- Galzed Aluminum Doors 21 25-Mar-12 17-Apr-12 10-Oct-12 05-Nov-12 168
A114060 Sub & App- Ironmongery 21 17-Apr-12 10-May-12 11-Sep-12 04-Oct-12 123
A7340 Sub & App- Wooden Doors 21 28-May-12 21-Jun-12 22-Aug-12 15-Sep-12 71
A7470 Sub & App- Curtain Wall&Glazing 21 21-Jun-12 15-Jul-12 21-Oct-12 17-Nov-12 102
MetalMetal 41 05-Apr-12 22-May-12 30-Apr-12 14-Nov-12 146
A7420 Sub & App- Balustrades and Handrails 21 05-Apr-12 29-Apr-12 30-Apr-12 23-May-12 21
A7280 Sub & App- Sinages 21 29-Apr-12 22-May-12 20-Oct-12 14-Nov-12 146
FurnitureFurniture 31 24-Oct-12 03-Dec-12 16-Dec-12 10-Mar-13 81
A8330 Sub & App- Furniture 21 24-Oct-12 20-Nov-12 16-Dec-12 09-Jan-13 41
A7390 Sub & App- Reception Counter 21 07-Nov-12 03-Dec-12 14-Feb-13 10-Mar-13 81
Soft LandscpSoft Landscping 41 28-May-12 15-Jul-12 12-Jul-12 30-Oct-12 88
A114080 Sub & App- Soft Landscping Items 21 28-May-12 21-Jun-12 12-Jul-12 05-Aug-12 38
A8390 Sub & App- Landscaping Light 21 21-Jun-12 15-Jul-12 04-Oct-12 30-Oct-12 88
OthersOthers 151 17-Apr-12 13-Oct-12 10-Jul-12 03-Jan-13 66
A7250 Sub & App- Toliets Accessories 21 17-Apr-12 10-May-12 03-Oct-12 29-Oct-12 142
A7290 Sub & App- Mirrors & Glasses 21 29-Apr-12 22-May-12 06-Oct-12 31-Oct-12 134
A124220 Sub & App- Sky Light 21 29-Apr-12 22-May-12 24-Jul-12 16-Aug-12 73
A7370 Sub & App- Waredrobes 21 28-May-12 21-Jun-12 10-Jul-12 02-Aug-12 36
A7360 Sub & App- Kitchen Cabinets 30 28-May-12 02-Jul-12 02-Oct-12 07-Nov-12 106
A7380 Sub & App- Vanity Counters 21 21-Jun-12 15-Jul-12 07-Oct-12 01-Nov-12 90
A115280 Sub & App- GRC 21 27-Aug-12 19-Sep-12 14-Nov-12 10-Dec-12 66
A114090 Sub & App- Hump 21 19-Sep-12 13-Oct-12 10-Dec-12 03-Jan-13 66
MechanicalMechanical 166 01-Feb-12 14-Aug-12 29-Mar-12 07-Feb-13 144
HVACHVAC 146 01-Feb-12 22-Jul-12 29-Mar-12 22-Oct-12 77
A8290 Sub & App- Chiller 21 01-Feb-12 26-Feb-12 29-Mar-12 22-Apr-12 48
A8060 Sub & App- HAVC Ducts 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62
A8100 Sub & App- Chilled Water Pipes-Fittings-Valves 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62
A8120 Sub & App- Condensate Pipes-Fittings-Valves 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62
A8070 Sub & App- FCUs 21 20-Feb-12 14-Mar-12 22-May-12 14-Jun-12 79
A8160 Sub & App- Air Oulets 21 20-Feb-12 14-Mar-12 29-Sep-12 22-Oct-12 187
A8080 Sub & App- AHU 21 26-Feb-12 20-Mar-12 17-Jul-12 09-Aug-12 121
A8090 Sub & App- FAHU 21 26-Feb-12 20-Mar-12 21-Jul-12 13-Aug-12 124
A8140 Sub & App- Chilled Pipes Insulation 21 01-Apr-12 24-Apr-12 07-Jul-12 30-Jul-12 82
A8130 Sub & App- Ducts Insulation 21 24-Apr-12 17-May-12 24-Jul-12 16-Aug-12 77
A8150 Sub & App- Condensate Pipes Insulation 21 24-Apr-12 17-May-12 24-Jul-12 16-Aug-12 77
A8300 Sub & App- Primary Chilled Water Pump 35 10-Jun-12 21-Jul-12 25-Aug-12 03-Oct-12 62
A8270 Sub & App- Heat Exchanger (HEX) 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61
A8280 Sub & App- Pumps for HEX 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61
A8310 Sub & App- Secpndry Chilled Water Pump 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61
PlumbingPlumbing 141 01-Feb-12 16-Jul-12 11-Jun-12 15-Dec-12 124
A7900 Sub & App- Floor Drains 21 01-Feb-12 26-Feb-12 20-Nov-12 15-Dec-12 244
A104240 Sub & App- Water Boiler Tank 21 08-Feb-12 03-Mar-12 26-Sep-12 20-Oct-12 195
A7930 Sub & App- PPR Pipes -Fittings-Valves (Water) 21 13-Feb-12 07-Mar-12 13-Jun-12 08-Jul-12 104
A7910 Sub & App- Sump Pump 21 14-Feb-12 08-Mar-12 22-Oct-12 18-Nov-12 212
A104260 Sub & App- Water Boiler 21 26-Feb-12 20-Mar-12 18-Sep-12 11-Oct-12 173
A104270 Sub & App- Water Boiler Pump 21 03-Mar-12 26-Mar-12 11-Nov-12 06-Dec-12 212
A7940 Sub & App- Transfer Pump 21 08-Mar-12 01-Apr-12 03-Oct-12 29-Oct-12 176
A7960 Sub & App- Steam Pipes for Boilers 21 08-Mar-12 01-Apr-12 13-Oct-12 07-Nov-12 184
A7890 Sub & App- uPVC Pipes-Fittings-Valves(Drainge) 21 20-Mar-12 12-Apr-12 11-Jun-12 05-Jul-12 71
A104250 Sub & App- Sanitarywares 21 06-May-12 29-May-12 13-Oct-12 07-Nov-12 134
A104340 Sub & App- GRP Water Tank 21 17-May-12 10-Jun-12 22-Sep-12 15-Oct-12 106
A115100 Sub & App- Booster Pump 21 23-Jun-12 16-Jul-12 03-Oct-12 29-Oct-12 86
Fire FighitngFire Fighitng 61 01-Feb-12 12-Apr-12 15-Apr-12 07-Nov-12 174
A7970 Sub & App- Fire Pipes-Fittings-Valves 21 01-Feb-12 26-Feb-12 15-Apr-12 08-May-12 62
A7990 Sub & App- Sprinklers 21 01-Feb-12 26-Feb-12 27-Aug-12 19-Sep-12 174
A8010 Sub & App- Landing Valves 21 01-Feb-12 26-Feb-12 18-Sep-12 11-Oct-12 193
A7780 Sub & App- Fire Alram Devices 30 01-Feb-12 07-Mar-12 18-Jul-12 23-Aug-12 142
A7980 Sub & App- Fire Pump 21 14-Feb-12 08-Mar-12 29-Jul-12 23-Aug-12 141
A8040 Sub & App- Foam Spary System for Generators 21 08-Mar-12 01-Apr-12 13-Oct-12 07-Nov-12 184
A8000 Sub & App- Fire Extinguishers & Banket 21 20-Mar-12 12-Apr-12 06-Sep-12 30-Sep-12 143
A8020 Sub & App- Fire Hose Cabinets 21 20-Mar-12 12-Apr-12 18-Sep-12 11-Oct-12 153
LPG SystemLPG System 116 01-Apr-12 14-Aug-12 18-Dec-12 07-Feb-13 144
A8430 Sub & App- LPG Pipes-Fittings-Valves 21 01-Apr-12 24-Apr-12 18-Dec-12 12-Jan-13 217
A8440 Sub & App- LPG Tanks( 2000 Gallons) 21 22-Jul-12 14-Aug-12 14-Jan-13 07-Feb-13 144
Coveying SysCoveying System 21 31-Mar-12 23-Apr-12 01-May-12 05-Jul-12 62
A7550 Sub & App- Passenger Lifts 21 31-Mar-12 23-Apr-12 11-Jun-12 05-Jul-12 62
A114290 Sub & App- Brakets,Guide Rails and Others 21 31-Mar-12 23-Apr-12 01-May-12 24-May-12 27
ElectricalElectrical 65 01-Feb-12 17-Apr-12 26-Apr-12 13-Nov-12 175
Cable Trays -Cable Trays - Cables 35 08-Feb-12 19-Mar-12 02-Jun-12 15-Aug-12 127
A7760 Sub & App- Cable Trays 30 08-Feb-12 13-Mar-12 07-Jun-12 12-Jul-12 103
A7700 Sub & App- Bus Bars 35 08-Feb-12 19-Mar-12 07-Jul-12 15-Aug-12 127
A7740 Sub & App- LV Cable 35 08-Feb-12 19-Mar-12 18-Jun-12 28-Jul-12 111
A7770 Sub & App- Trunking 35 08-Feb-12 19-Mar-12 02-Jun-12 12-Jul-12 98
Low CurrentLow Current Systems 65 01-Feb-12 17-Apr-12 26-Apr-12 22-Sep-12 132
A7820 Sub & App- CCTV System 35 01-Feb-12 13-Mar-12 01-May-12 10-Jun-12 76
A7830 Sub & App- Access Control System 35 01-Feb-12 13-Mar-12 26-Apr-12 05-Jun-12 72
A7840 Sub & App- Central Battery System 35 01-Feb-12 13-Mar-12 01-Aug-12 12-Sep-12 154
A7870 Sub & App- BMS 35 01-Feb-12 13-Mar-12 09-Jul-12 18-Aug-12 134
A8400 Sub & App- MATV/ Interactive TV System 35 01-Feb-12 13-Mar-12 30-Jul-12 10-Sep-12 152
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Sub & App- Ceiling Suspension System
Sub & App- Porcelain Tiles
Sub & App- Ceramic Tiles
Sub & App- Granite Tiles
Sub & App- MDF Cladding
Sub & App- Natural Stone
Sub & App- Carpet Tiles
Sub & App- Veneer Cladding
Sub & App- Terrazo Tiles
Sub & App- Marble Tiles
Sub & App- VinyelSheet
Sub & App- Raised Floor Tiles
Sub & App- Wenge cCladding
Sub & App- Honed Limestone
Sub & App- Mosiac Tiles
Sub & App- Wooden Floor
Sub & App- Polished Moche Tiles
Sub & App- Precast Conc. Interlocking Paving
Sub & App- Precast Conc. Kerbs
Sub & App- Heavy Duty Tiles
Sub & App- Vinyl Wall Covering
Sub & App- Carpet
Sub & App- Aluminum Louver Doors
Sub & App- Fire Rated Doors
Sub & App- Galzed Aluminum Doors
Sub & App- Ironmongery
Sub & App- Wooden Doors
Sub & App- Curtain Wall&Glazing
Sub & App- Balustrades and Handrails
Sub & App- Sinages
Sub & App- Furniture
Sub & App- Reception Counter
Sub & App- Soft Landscping Items
Sub & App- Landscaping Light
Sub & App- Toliets Accessories
Sub & App- Mirrors & Glasses
Sub & App- Sky Light
Sub & App- Waredrobes
Sub & App- Kitchen Cabinets
Sub & App- Vanity Counters
Sub & App- GRC
Sub & App- Hump
Sub & App- Chiller
Sub & App- HAVC Ducts
Sub & App- Chilled Water Pipes-Fittings-Valves
Sub & App- Condensate Pipes-Fittings-Valves
Sub & App- FCUs
Sub & App- Air Oulets
Sub & App- AHU
Sub & App- FAHU
Sub & App- Chilled Pipes Insulation
Sub & App- Ducts Insulation
Sub & App- Condensate Pipes Insulation
Sub & App- Primary Chilled Water Pump
Sub & App- Heat Exchanger (HEX)
Sub & App- Pumps for HEX
Sub & App- Secpndry Chilled Water Pump
Sub & App- Floor Drains
Sub & App- Water Boiler Tank
Sub & App- PPR Pipes -Fittings-Valves (Water)
Sub & App- Sump Pump
Sub & App- Water Boiler
Sub & App- Water Boiler Pump
Sub & App- Transfer Pump
Sub & App- Steam Pipes for Boilers
Sub & App- uPVC Pipes-Fittings-Valves(Drainge)
Sub & App- Sanitarywares
Sub & App- GRP Water Tank
Sub & App- Booster Pump
Sub & App- Fire Pipes-Fittings-Valves
Sub & App- Sprinklers
Sub & App- Landing Valves
Sub & App- Fire Alram Devices
Sub & App- Fire Pump
Sub & App- Foam Spary System for Generators
Sub & App- Fire Extinguishers & Banket
Sub & App- Fire Hose Cabinets
Sub & App- LPG Pipes-Fittings-Valves
Sub & App- LPG Tanks( 2000 Gallons)
Sub & App- Passenger Lifts
Sub & App- Brakets,Guide Rails and Others
Sub & App- Cable Trays
Sub & App- Bus Bars
Sub & App- LV Cable
Sub & App- Trunking
Sub & App- CCTV System
Sub & App- Access Control System
Sub & App- Central Battery System
Sub & App- BMS
Sub & App- MATV/ Interactive TV System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 12 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A8240 Sub & App- GSM System 35 08-Mar-12 17-Apr-12 11-Aug-12 22-Sep-12 132
Electrical EquElectrical Equipments 61 01-Feb-12 12-Apr-12 23-May-12 13-Nov-12 179
A7710 Sub & App- MDBs 35 01-Feb-12 13-Mar-12 17-Jul-12 28-Aug-12 141
A7720 Sub & App- SMDBs 35 01-Feb-12 13-Mar-12 08-Aug-12 19-Sep-12 160
A7730 Sub & App- DBs 35 01-Feb-12 13-Mar-12 23-May-12 03-Jul-12 95
A7800 Sub & App- Generators 35 01-Feb-12 13-Mar-12 04-Jul-12 13-Aug-12 130
A7860 Sub & App- UPS 35 01-Feb-12 13-Mar-12 11-Jul-12 22-Aug-12 136
A8670 Sub & App- Telephone System 35 01-Feb-12 13-Mar-12 18-Jun-12 28-Jul-12 116
A8260 Sub & App- ElectricalHeaters 21 20-Mar-12 12-Apr-12 18-Oct-12 13-Nov-12 179
OthersOthers 35 01-Feb-12 13-Mar-12 05-Aug-12 16-Sep-12 157
A7880 Sub & App- Light Fixtures 35 01-Feb-12 13-Mar-12 05-Aug-12 16-Sep-12 157
Speciality WSpeciality Works 111 19-Mar-12 26-Jul-12 06-May-12 28-Jan-13 151
Swimming PoSwimming Pool 21 28-May-12 21-Jun-12 05-Jul-12 08-Nov-12 116
A7560 Sub & App- Pool Finishes 21 28-May-12 21-Jun-12 29-Sep-12 22-Oct-12 103
A7570 Sub & App- Pool Equipments 21 28-May-12 21-Jun-12 05-Jul-12 29-Jul-12 32
A8180 Sub & App- Water Proofing for Swimming Pool 21 28-May-12 21-Jun-12 04-Oct-12 30-Oct-12 108
A104220 Sub & App- Pool Electrical Items 21 28-May-12 21-Jun-12 14-Oct-12 08-Nov-12 116
Garbage ChuGarbage Chute System 40 19-Mar-12 03-May-12 06-May-12 30-Jul-12 74
A7580 Sub & App- Pipes & Fittings 21 19-Mar-12 11-Apr-12 21-Jun-12 15-Jul-12 80
A104180 Sub & App- Equipments 28 19-Mar-12 19-Apr-12 28-Jun-12 30-Jul-12 86
A104190 Sub & App- Garbage Chutes 40 19-Mar-12 03-May-12 06-May-12 21-Jun-12 41
Linen ChuteLinen Chute System 40 23-Apr-12 07-Jun-12 13-May-12 05-Jul-12 23
A114140 Sub & App- Pipes & Fittings 21 23-Apr-12 16-May-12 13-May-12 05-Jun-12 17
A114120 Sub & App- Equipments 28 23-Apr-12 24-May-12 26-May-12 27-Jun-12 28
A114130 Sub & App- Linen Chutes 40 23-Apr-12 07-Jun-12 20-May-12 05-Jul-12 23
Facade CleanFacade Cleaning System 21 03-Jul-12 26-Jul-12 03-Jan-13 28-Jan-13 151
A7600 Sub & App- Cleaning System 21 03-Jul-12 26-Jul-12 03-Jan-13 28-Jan-13 151
ProvisionalProvisional Sum 236 10-May-12 19-Feb-13 11-Jun-12 25-Apr-13 56
Kitchen EquiKitchen Equipments 21 10-May-12 03-Jun-12 13-Jun-12 08-Jul-12 29
A8650 Sub & App- Kitchen Equipments 21 10-May-12 03-Jun-12 13-Jun-12 08-Jul-12 29
Laundary EqLaundary Equipments 21 10-May-12 03-Jun-12 11-Jun-12 05-Jul-12 27
A114220 Sub & App- Laundary Equipments 21 10-May-12 03-Jun-12 11-Jun-12 05-Jul-12 27
Facade LightFacade Lighting 21 16-May-12 09-Jun-12 28-Jun-12 22-Jul-12 36
A115260 Sub & App- Facade Lighting 21 16-May-12 09-Jun-12 28-Jun-12 22-Jul-12 36
Cooking StatCooking Station 21 26-May-12 19-Jun-12 30-Sep-12 23-Oct-12 106
A124710 Sub & App- Cooking Station 21 26-May-12 19-Jun-12 30-Sep-12 23-Oct-12 106
Gymnasium EGymnasium Equipments 21 27-Jan-13 19-Feb-13 02-Apr-13 25-Apr-13 56
A114270 Sub & App- Gym Equipments 21 27-Jan-13 19-Feb-13 02-Apr-13 25-Apr-13 56
ProcuremenProcurement and Delivery 437 07-Jan-12 11-Jun-13 14-Jan-12 29-Jul-13 41
CivilCivil 286 07-Jan-12 13-Dec-12 14-Jan-12 03-Mar-13 66
A6390 Order&Delivery- Water Proofing for Substructure 5 07-Jan-12 11-Jan-12 14-Jan-12 18-Jan-12 6
A6370 Order&Delivery- Conceret - 1st Pour 7 14-Jan-12 21-Jan-12 17-Jan-12 24-Jan-12 3
A6380 Order&Delivery- Steel Reinforcement - 1st Patch 7 14-Jan-12 21-Jan-12 17-Jan-12 24-Jan-12 3
A6930 Order&Delivery- Water Proofing for Wet Areas 90 28-Mar-12 11-Jul-12 28-Aug-12 15-Dec-12 128
A6400 Order&Delivery- GRP Lining 60 17-May-12 26-Jul-12 29-Aug-12 08-Nov-12 86
A9170 Order&Delivery- Reinforced Plastic 60 17-May-12 26-Jul-12 15-Sep-12 26-Nov-12 100
A46460 Order&Delivery- Water Proofing for Roof 100 26-Apr-12 23-Aug-12 18-Jul-12 17-Nov-12 70
A6950 Order&Delivery- Traffic Coating 90 27-Aug-12 13-Dec-12 14-Nov-12 03-Mar-13 66
ArchitecturalArchitectural 405 14-Feb-12 11-Jun-13 24-May-12 29-Jul-13 41
Wet WorksWet Works 70 14-Feb-12 05-May-12 23-Jun-12 24-Sep-12 119
A5580 Order&Delivery- Blocks 30 14-Feb-12 19-Mar-12 23-Jun-12 26-Jul-12 110
A5570 Order&Delivery- Plaster Materials 30 03-Mar-12 05-Apr-12 18-Jul-12 23-Aug-12 117
A5510 Order&Delivery- Paint Materials 60 26-Feb-12 05-May-12 15-Jul-12 24-Sep-12 119
CeilingCeiling 140 01-Mar-12 12-Aug-12 31-May-12 27-Jan-13 136
A9130 Order&Delivery- Metal Celing System 90 01-Mar-12 13-Jun-12 31-Jul-12 18-Nov-12 129
A5720 Order&Delivery- Fibre Celing System 90 25-Mar-12 08-Jul-12 08-Oct-12 27-Jan-13 166
A5530 Order&Delivery- Gybsum Ceiling System 90 01-Apr-12 15-Jul-12 31-May-12 16-Sep-12 52
A9270 Order&Delivery- Aluminum Ceiling Tiles 90 17-Apr-12 31-Jul-12 03-Oct-12 21-Jan-13 142
A9330 Order&Delivery- MDF Ceiling System 90 29-Apr-12 12-Aug-12 29-Sep-12 16-Jan-13 128
Walls & FlooWalls & Floors 290 07-Apr-12 20-Mar-13 26-Jun-12 13-Apr-13 20
A5500 Order&Delivery- Porcelain Tiles 105 07-Apr-12 07-Aug-12 26-Jun-12 30-Oct-12 68
A5760 Order&Delivery- Ceramic Tiles 105 07-Apr-12 07-Aug-12 27-Aug-12 31-Dec-12 119
A5840 Order&Delivery- Natural Stone 95 18-Apr-12 07-Aug-12 21-Oct-12 14-Feb-13 156
A7120 Order&Delivery- MDF Cladding 100 18-Apr-12 13-Aug-12 12-Sep-12 12-Jan-13 123
A5540 Order&Delivery- Granite Tiles 105 18-Apr-12 21-Aug-12 12-Nov-12 18-Mar-13 173
A9140 Order&Delivery- Carpet Tiles 95 30-Apr-12 21-Aug-12 01-Nov-12 24-Feb-13 154
A5750 Order&Delivery- Terrazo Tiles 90 23-May-12 08-Sep-12 16-Oct-12 04-Feb-13 122
A9240 Order&Delivery- Raised Floor Tiles 90 23-May-12 08-Sep-12 29-Nov-12 17-Mar-13 157
A9250 Order&Delivery- Veneer Cladding 110 30-Apr-12 08-Sep-12 13-Sep-12 26-Jan-13 114
A6110 Order&Delivery- VinyelSheet 95 23-May-12 13-Sep-12 10-Nov-12 04-Mar-13 141
A9320 Order&Delivery- Wenge Cladding 95 23-May-12 13-Sep-12 08-Oct-12 02-Feb-13 115
A5770 Order&Delivery- Marble Tiles 105 23-May-12 25-Sep-12 03-Dec-12 06-Apr-13 159
A9290 Order&Delivery- Honed Limestone Tiles 90 16-Jun-12 01-Oct-12 31-Oct-12 17-Feb-13 113
A5790 Order&Delivery- Wooden Floor 95 23-Jun-12 13-Oct-12 02-Oct-12 27-Jan-13 85
A9300 Order&Delivery- Polished Moche Tiles 90 28-Jun-12 13-Oct-12 31-Oct-12 17-Feb-13 103
A9120 Order&Delivery- Mosiac Tiles 105 16-Jun-12 18-Oct-12 03-Sep-12 08-Jan-13 65
A9310 Order&Delivery- Water Jet Limestone Tiles 90 01-Aug-12 19-Nov-12 31-Oct-12 17-Feb-13 74
A6320 Order&Delivery- Precast Conc. Interlocking Paving 90 02-Aug-12 20-Nov-12 05-Nov-12 21-Feb-13 77
A6420 Order&Delivery- Precast Conc. Kerbs 90 02-Aug-12 20-Nov-12 24-Oct-12 12-Feb-13 69
A9260 Order&Delivery- Heavy Duty Tiles 95 28-Aug-12 20-Dec-12 22-Dec-12 13-Apr-13 95
A7110 Order&Delivery- Vinyl Wall Covering 100 02-Oct-12 02-Feb-13 10-Dec-12 07-Apr-13 55
A5780 Order&Delivery- Carpet 100 21-Nov-12 20-Mar-13 26-Nov-12 25-Mar-13 4
Doors & WinDoors & Windows 225 20-Feb-12 13-Nov-12 16-Sep-12 23-Feb-13 83
A5700 Order&Delivery- Aluminum Louver Doors 90 20-Feb-12 03-Jun-12 01-Nov-12 18-Feb-13 214
A5710 Order&Delivery- Fire Rated Doors 90 20-Feb-12 03-Jun-12 04-Nov-12 20-Feb-13 216
A5620 Order&Delivery- Galzed Aluminum Doors 90 18-Apr-12 01-Aug-12 06-Nov-12 23-Feb-13 168
A6220 Order&Delivery- Ironmongery 105 12-May-12 13-Sep-12 06-Oct-12 11-Feb-13 123
A5610 Order&Delivery- Wooden Doors 120 23-Jun-12 13-Nov-12 16-Sep-12 09-Feb-13 71
MetalMetal 140 30-Apr-12 13-Oct-12 24-May-12 08-Apr-13 146
A5690 Order&Delivery- Balustrades and Handrails 120 30-Apr-12 19-Sep-12 24-May-12 14-Oct-12 21
A5550 Order&Delivery- Sinages 120 23-May-12 13-Oct-12 17-Nov-12 08-Apr-13 146
FurnitureFurniture 170 21-Nov-12 11-Jun-13 10-Jan-13 29-Jul-13 41
A5660 Order&Delivery- Reception Counter 120 04-Dec-12 24-Apr-13 11-Mar-13 29-Jul-13 81
A7010 Order&Delivery- Furniture 170 21-Nov-12 11-Jun-13 10-Jan-13 29-Jul-13 41
Soft LandscpSoft Landscping 130 23-Jun-12 26-Nov-12 06-Aug-12 12-Mar-13 88
A5590 Order&Delivery- Soft Landscping Items 100 23-Jun-12 18-Oct-12 06-Aug-12 06-Dec-12 38
A7140 Order&Delivery- Landscaping Light 110 16-Jul-12 26-Nov-12 31-Oct-12 12-Mar-13 88
OthersOthers 210 12-May-12 20-Jan-13 04-Aug-12 08-Apr-13 66
A5520 Order&Delivery- Toliets Accessories 100 12-May-12 08-Sep-12 30-Oct-12 27-Feb-13 142
A5730 Order&Delivery- Sky Light 90 23-May-12 08-Sep-12 18-Aug-12 06-Dec-12 73
A5560 Order&Delivery- Mirrors & Glasses 100 23-May-12 19-Sep-12 01-Nov-12 02-Mar-13 134
A5640 Order&Delivery- Waredrobes 90 23-Jun-12 07-Oct-12 04-Aug-12 21-Nov-12 36
A5630 Order&Delivery- Kitchen Cabinets 90 03-Jul-12 17-Oct-12 08-Nov-12 25-Feb-13 106
A51060 Order&Delivery- Irrigation System 90 15-Jul-12 31-Oct-12 07-Oct-12 26-Jan-13 70
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Sub & App- GSM System
Sub & App- MDBs
Sub & App- SMDBs
Sub & App- DBs
Sub & App- Generators
Sub & App- UPS
Sub & App- Telephone System
Sub & App- ElectricalHeaters
Sub & App- Light Fixtures
Sub & App- Pool Finishes
Sub & App- Pool Equipments
Sub & App- Water Proofing for Swimming Pool
Sub & App- Pool Electrical Items
Sub & App- Pipes & Fittings
Sub & App- Equipments
Sub & App- Garbage Chutes
Sub & App- Pipes & Fittings
Sub & App- Equipments
Sub & App- Linen Chutes
Sub & App- Cleaning System
Sub & App- Kitchen Equipments
Sub & App- Laundary Equipments
Sub & App- Facade Lighting
Sub & App- Cooking Station
Sub & App- Gym Equipments
Order&Delivery- Water Proofing for Substructure
Order&Delivery- Conceret - 1st Pour
Order&Delivery- Steel Reinforcement - 1st Patch
Order&Delivery- Water Proofing for Wet Areas
Order&Delivery- GRP Lining
Order&Delivery- Reinforced Plastic
Order&Delivery- Water Proofing for Roof
Order&Delivery- Traffic Coating
Order&Delivery- Blocks
Order&Delivery- Plaster Materials
Order&Delivery- Paint Materials
Order&Delivery- Metal Celing System
Order&Delivery- Fibre Celing System
Order&Delivery- Gybsum Ceiling System
Order&Delivery- Aluminum Ceiling Tiles
Order&Delivery- MDF Ceiling System
Order&Delivery- Porcelain Tiles
Order&Delivery- Ceramic Tiles
Order&Delivery- Natural Stone
Order&Delivery- MDF Cladding
Order&Delivery- Granite Tiles
Order&Delivery- Carpet Tiles
Order&Delivery- Terrazo Tiles
Order&Delivery- Raised Floor Tiles
Order&Delivery- Veneer Cladding
Order&Delivery- Vinyel Sheet
Order&Delivery- Wenge Cladding
Order&Delivery- Marble Tiles
Order&Delivery- Honed Limestone Tiles
Order&Delivery- Wooden Floor
Order&Delivery- Polished Moche Tiles
Order&Delivery- Mosiac Tiles
Order&Delivery- Water Jet Limestone Tiles
Order&Delivery- Precast Conc. Interlocking Paving
Order&Delivery- Precast Conc. Kerbs
Order&Delivery- Heavy Duty Tiles
Order&Delivery- Vinyl Wall Covering
Order&Delivery- Carpet
Order&Delivery- Aluminum Louver Doors
Order&Delivery- Fire Rated Doors
Order&Delivery- Galzed Aluminum Doors
Order&Delivery- Ironmongery
Order&Delivery- Wooden Doors
Order&Delivery- Balustrades and Handrails
Order&Delivery- Sinages
Order&Delivery- Reception Counter
Order&Delivery- Furniture
Order&Delivery- Soft Landscping Items
Order&Delivery- Landscaping Light
Order&Delivery- Toliets Accessories
Order&Delivery- Sky Light
Order&Delivery- Mirrors & Glasses
Order&Delivery- Waredrobes
Order&Delivery- Kitchen Cabinets
Order&Delivery- Irrigation System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 13 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A5650 Order&Delivery- Vanity Counters 100 16-Jul-12 13-Nov-12 03-Nov-12 03-Mar-13 90
A50690 Order&Delivery- Hump 80 14-Oct-12 20-Jan-13 05-Jan-13 08-Apr-13 66
MechanicalMechanical 239 27-Feb-12 09-Dec-12 23-Apr-12 24-Mar-13 88
HVACHVAC 215 27-Feb-12 08-Nov-12 23-Apr-12 29-Jan-13 66
A6900 Order&Delivery- Air Oulets 60 15-Mar-12 23-May-12 23-Oct-12 06-Jan-13 187
A6880 Order&Delivery- Chilled Pipes Insulation 30 25-Apr-12 29-May-12 31-Jul-12 05-Sep-12 82
A6870 Order&Delivery- Ducts Insulation 15 19-May-12 04-Jun-12 18-Aug-12 05-Sep-12 77
A6890 Order&Delivery- Condensate Pipes Insulation 15 19-May-12 04-Jun-12 18-Aug-12 05-Sep-12 77
A6810 Order&Delivery- FCUs 75 15-Mar-12 10-Jun-12 16-Jun-12 13-Sep-12 79
A6800 Order&Delivery- HAVC Ducts 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62
A6840 Order&Delivery- Chilled Water Pipes-Fittings-Valves 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62
A6860 Order&Delivery- Condensate Pipes-Fittings-Valves 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62
A6830 Order&Delivery- FAHU 100 25-Apr-12 22-Aug-12 20-Sep-12 20-Jan-13 124
A6820 Order&Delivery- AHU 110 25-Apr-12 03-Sep-12 17-Sep-12 29-Jan-13 121
A7050 Order&Delivery- Chiller 180 27-Feb-12 26-Sep-12 23-Apr-12 25-Nov-12 48
A7060 Order&Delivery- Primary Chilled Water Pump 90 22-Jul-12 07-Nov-12 04-Oct-12 22-Jan-13 62
A7030 Order&Delivery- Heat Exchanger (HEX) 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61
A7040 Order&Delivery- Pumps for HEX 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61
A7070 Order&Delivery- Secpndry Chilled Water Pump 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61
PlumbingPlumbing 210 27-Feb-12 03-Nov-12 07-Jul-12 25-Feb-13 94
A6640 Order&Delivery- Floor Drains 30 27-Feb-12 01-Apr-12 16-Dec-12 20-Jan-13 244
A6670 Order&Delivery-PPR Pipes -Fittings-Valves (Water) 30 08-Mar-12 11-Apr-12 09-Jul-12 12-Aug-12 104
A6630 Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge) 30 14-Apr-12 17-May-12 07-Jul-12 09-Aug-12 71
A6650 Order&Delivery- Sump Pump 60 10-Mar-12 17-May-12 19-Nov-12 30-Jan-13 212
A7020 Order&Delivery- ElectricalHeaters 30 14-Apr-12 17-May-12 14-Nov-12 20-Dec-12 179
A9200 Order&Delivery- Water Boiler Pump 60 27-Mar-12 04-Jun-12 08-Dec-12 17-Feb-13 212
A9190 Order&Delivery- Water Boiler Tank 90 04-Mar-12 16-Jun-12 21-Oct-12 09-Feb-13 195
A9180 Order&Delivery- Water Boiler 90 21-Mar-12 04-Jul-12 13-Oct-12 31-Jan-13 173
A9210 Order&Delivery- Steam Pipes for Boilers 90 02-Apr-12 16-Jul-12 08-Nov-12 25-Feb-13 184
A9220 Order&Delivery- Transfer Pump 90 02-Apr-12 16-Jul-12 30-Oct-12 16-Feb-13 176
A8790 Order&Delivery- Sanitarywares 90 30-May-12 15-Sep-12 08-Nov-12 25-Feb-13 134
A9400 Order&Delivery- GRP Water Tank 100 11-Jun-12 08-Oct-12 16-Oct-12 16-Feb-13 106
A115090 Order&Delivery- Booster Pump 90 17-Jul-12 03-Nov-12 30-Oct-12 16-Feb-13 86
Fire FighitngFire Fighitng 140 27-Feb-12 08-Aug-12 09-May-12 31-Jan-13 143
A6710 Order&Delivery- Fire Pipes-Fittings-Valves 90 27-Feb-12 10-Jun-12 09-May-12 25-Aug-12 62
A6730 Order&Delivery- Sprinklers 90 27-Feb-12 10-Jun-12 20-Sep-12 08-Jan-13 174
A6750 Order&Delivery- Landing Valves 90 27-Feb-12 10-Jun-12 13-Oct-12 31-Jan-13 193
A6780 Order&Delivery- Foam Spary System for Generators 60 02-Apr-12 10-Jun-12 08-Nov-12 20-Jan-13 184
A9000 Order&Delivery- Fire Alarm Devices 90 08-Mar-12 21-Jun-12 25-Aug-12 11-Dec-12 142
A6740 Order&Delivery- Fire Extinguishers & Banket 90 14-Apr-12 28-Jul-12 01-Oct-12 19-Jan-13 143
A6760 Order&Delivery- Fire Hose Cabinets 90 14-Apr-12 28-Jul-12 13-Oct-12 31-Jan-13 153
A9230 Order&Delivery- Fire Fighting Pump 130 10-Mar-12 08-Aug-12 25-Aug-12 29-Jan-13 141
LPG SystemLPG System 125 25-Apr-12 20-Sep-12 13-Jan-13 24-Mar-13 152
A7180 Order&Delivery- LPG Pipes-Fittings-Valves 60 25-Apr-12 04-Jul-12 13-Jan-13 24-Mar-13 217
A7190 Order&Delivery- LPG Tanks( 2000 Gallons) 30 15-Aug-12 20-Sep-12 09-Feb-13 14-Mar-13 144
Coveying SysCoveying System 190 24-Apr-12 09-Dec-12 26-May-12 21-Feb-13 62
A1143 Order&Delivery- Brakets,Guide Rails and Others 100 24-Apr-12 21-Aug-12 26-May-12 22-Sep-12 27
A5820 Order&Delivery- Passenger Lifts 120 16-Jul-12 09-Dec-12 29-Sep-12 21-Feb-13 62
ElectricalElectrical 212 14-Mar-12 22-Nov-12 04-Jul-12 17-Feb-13 71
Cable Trays -Cable Trays - Cables 193 14-Mar-12 30-Oct-12 14-Jul-12 17-Dec-12 39
A6500 Order&Delivery- Cable Trays 45 14-Mar-12 05-May-12 14-Jul-12 05-Sep-12 103
A6480 Order&Delivery- LV Cable 45 20-Mar-12 10-May-12 29-Jul-12 20-Sep-12 111
A6510 Order&Delivery- Trunking 45 20-Mar-12 10-May-12 14-Jul-12 05-Sep-12 98
A6440 Order&Delivery- Bus Bars 100 02-Jul-12 30-Oct-12 16-Aug-12 17-Dec-12 39
Low CurrentLow Current Systems 140 14-Mar-12 27-Aug-12 23-Jul-12 06-Feb-13 134
A7150 Order&Delivery- MATV/ Interactive TV System 60 14-Mar-12 22-May-12 11-Sep-12 22-Nov-12 152
A6610 Order&Delivery- BMS 70 26-Mar-12 14-Jun-12 02-Sep-12 25-Nov-12 134
A6580 Order&Delivery- Central Battery System 90 18-Apr-12 01-Aug-12 18-Oct-12 06-Feb-13 154
A6990 Order&Delivery- GSM System 90 18-Apr-12 01-Aug-12 23-Sep-12 10-Jan-13 132
A6560 Order&Delivery- CCTV System 90 24-Apr-12 07-Aug-12 23-Jul-12 08-Nov-12 76
A6570 Order&Delivery- Access Control System 90 12-May-12 27-Aug-12 05-Aug-12 22-Nov-12 72
Electrical EquElectrical Equipments 212 14-Mar-12 22-Nov-12 04-Jul-12 17-Feb-13 71
A6470 Order&Delivery- DBs 100 14-Mar-12 09-Jul-12 04-Jul-12 01-Nov-12 95
A6450 Order&Delivery- MDBs 110 14-Mar-12 21-Jul-12 29-Aug-12 09-Jan-13 141
A6460 Order&Delivery- SMDBs 110 14-Mar-12 21-Jul-12 20-Sep-12 02-Feb-13 160
A6540 Order&Delivery- Generators 120 26-Mar-12 13-Aug-12 28-Aug-12 20-Jan-13 130
A6600 Order&Delivery- UPS 60 04-Jun-12 13-Aug-12 17-Nov-12 28-Jan-13 136
A1334 Order&Delivery- Telephone System 60 04-Jun-12 13-Aug-12 21-Oct-12 03-Jan-13 116
A6430 Order&Delivery- Transformers 80 16-Aug-12 22-Nov-12 12-Nov-12 17-Feb-13 71
A2345 Order&Delivery- RMU Unit 80 16-Aug-12 22-Nov-12 11-Nov-12 16-Feb-13 70
OthersOthers 70 14-Mar-12 03-Jun-12 17-Sep-12 11-Dec-12 157
A6620 Order&Delivery- Light Fixtures 70 14-Mar-12 03-Jun-12 17-Sep-12 11-Dec-12 157
Speciality WSpeciality Works 237 12-Apr-12 22-Jan-13 23-Jun-12 05-Jun-13 114
Swimming PoSwimming Pool 120 23-Jun-12 13-Nov-12 30-Jul-12 23-Mar-13 107
A5830 Order&Delivery- Finishes Items 80 23-Jun-12 25-Sep-12 23-Oct-12 30-Jan-13 103
A6920 Order&Delivery- Water Proofing for Swimming Pool 80 23-Jun-12 25-Sep-12 31-Oct-12 05-Feb-13 108
A9150 Order&Delivery- ElectricalItems 80 23-Jun-12 25-Sep-12 10-Nov-12 14-Feb-13 116
A9280 Order&Delivery- Sand Stone Pavers 80 23-Jun-12 25-Sep-12 18-Dec-12 23-Mar-13 147
A9160 Order&Delivery- Pocalin for Pool Deck 100 23-Jun-12 18-Oct-12 21-Nov-12 20-Mar-13 125
A44340 Order&Delivery- Swimming Pool Equipments 120 23-Jun-12 13-Nov-12 30-Jul-12 23-Dec-12 32
External FacaExternal Facade 145 16-Jul-12 08-Jan-13 18-Nov-12 28-Mar-13 67
A5740 Order&Delivery- Curtain Wall&Glazing 110 16-Jul-12 26-Nov-12 18-Nov-12 28-Mar-13 102
A5678 Order&Delivery- GRC 90 20-Sep-12 08-Jan-13 11-Dec-12 27-Mar-13 66
Facade CleanFacade Cleaning 110 28-Jul-12 09-Dec-12 29-Jan-13 05-Jun-13 151
A5870 Order&Delivery- Facade Cleaning System 110 28-Jul-12 09-Dec-12 29-Jan-13 05-Jun-13 151
Garbage ChuGarbage Chute 169 12-Apr-12 31-Oct-12 23-Jun-12 30-Jan-13 74
A5850 Order&Delivery- Pipes & Fittings 100 12-Apr-12 07-Aug-12 16-Jul-12 13-Nov-12 80
A9380 Order&Delivery- Equipments 150 21-Apr-12 15-Oct-12 31-Jul-12 30-Jan-13 86
A9390 Order&Delivery- Garbage Chutes 150 05-May-12 31-Oct-12 23-Jun-12 20-Dec-12 41
Linen ChuteLinen Chute 188 09-Jun-12 22-Jan-13 07-Jul-12 25-Feb-13 28
A114180 Order&Delivery- Pipes & Fittings 100 10-Jul-12 07-Nov-12 30-Jul-12 28-Nov-12 17
A114200 Order&Delivery- Linen Chutes 150 09-Jun-12 08-Dec-12 07-Jul-12 05-Jan-13 23
A114190 Order&Delivery- Equipments 150 24-Jul-12 22-Jan-13 28-Aug-12 25-Feb-13 28
ProvisionalProvisional Sum 293 23-Jun-12 09-Jun-13 07-Jul-12 29-Jul-13 43
Kitchen EquiKitchen Equipments 108 23-Jun-12 30-Oct-12 09-Jul-12 17-Nov-12 14
A8640 Order&Delivery- Kitchen Equipments 108 23-Jun-12 30-Oct-12 09-Jul-12 17-Nov-12 14
Lundary EquLundary Equipments 108 23-Jun-12 30-Oct-12 07-Jul-12 13-Nov-12 12
A114210 Order&Delivery- Laundary Equipments 108 23-Jun-12 30-Oct-12 07-Jul-12 13-Nov-12 12
Facade LightFacade Lighting 90 30-Jun-12 14-Oct-12 23-Jul-12 08-Nov-12 20
A115270 Order&Delivery- Facade Lighting 90 30-Jun-12 14-Oct-12 23-Jul-12 08-Nov-12 20
Cooking StatCooking Station 120 09-Jul-12 01-Dec-12 24-Oct-12 19-Mar-13 90
A124670 Order&Delivery- Cooking Station 120 09-Jul-12 01-Dec-12 24-Oct-12 19-Mar-13 90
Gymnasium EGymnasium Equipments 80 07-Mar-13 09-Jun-13 27-Apr-13 29-Jul-13 43
A45220 Order&Delivery- Gym Equipments 80 07-Mar-13 09-Jun-13 27-Apr-13 29-Jul-13 43
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Order&Delivery- Vanity Counters
Order&Delivery- Hump
Order&Delivery- Air Oulets
Order&Delivery- Chilled Pipes Insulation
Order&Delivery- Ducts Insulation
Order&Delivery- Condensate Pipes Insulation
Order&Delivery- FCUs
Order&Delivery- HAVC Ducts
Order&Delivery- Chilled Water Pipes-Fittings-Valves
Order&Delivery- Condensate Pipes-Fittings-Valves
Order&Delivery- FAHU
Order&Delivery- AHU
Order&Delivery- Chiller
Order&Delivery- Primary Chilled Water Pump
Order&Delivery- Heat Exchanger (HEX)
Order&Delivery- Pumps for HEX
Order&Delivery- Secpndry Chilled Water Pump
Order&Delivery- Floor Drains
Order&Delivery-PPR Pipes -Fittings-Valves (Water)
Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge)
Order&Delivery- Sump Pump
Order&Delivery- ElectricalHeaters
Order&Delivery- Water Boiler Pump
Order&Delivery- Water Boiler Tank
Order&Delivery- Water Boiler
Order&Delivery- Steam Pipes for Boilers
Order&Delivery- Transfer Pump
Order&Delivery- Sanitarywares
Order&Delivery- GRP Water Tank
Order&Delivery- Booster Pump
Order&Delivery- Fire Pipes-Fittings-Valves
Order&Delivery- Sprinklers
Order&Delivery- Landing Valves
Order&Delivery- Foam Spary System for Generators
Order&Delivery- Fire Alarm Devices
Order&Delivery- Fire Extinguishers & Banket
Order&Delivery- Fire Hose Cabinets
Order&Delivery- Fire Fighting Pump
Order&Delivery- LPG Pipes-Fittings-Valves
Order&Delivery- LPG Tanks( 2000 Gallons)
Order&Delivery- Brakets,Guide Rails and Others
Order&Delivery- Passenger Lifts
Order&Delivery- Cable Trays
Order&Delivery- LV Cable
Order&Delivery- Trunking
Order&Delivery- Bus Bars
Order&Delivery- MATV/ Interactive TV System
Order&Delivery- BMS
Order&Delivery- Central Battery System
Order&Delivery- GSM System
Order&Delivery- CCTV System
Order&Delivery- Access Control System
Order&Delivery- DBs
Order&Delivery- MDBs
Order&Delivery- SMDBs
Order&Delivery- Generators
Order&Delivery- UPS
Order&Delivery- Telephone System
Order&Delivery- Transformers
Order&Delivery- RMU Unit
Order&Delivery- Light Fixtures
Order&Delivery- Finishes Items
Order&Delivery- Water Proofing for Swimming Pool
Order&Delivery- Electrical Items
Order&Delivery- Sand Stone Pavers
Order&Delivery- Pocalin for Pool Deck
Order&Delivery- Swimming Pool Equipments
Order&Delivery- Curtain Wall&Glazing
Order&Delivery- GRC
Order&Delivery- Facade Cleaning System
Order&Delivery- Pipes & Fittings
Order&Delivery- Equipments
Order&Delivery- Garbage Chutes
Order&Delivery- Pipes & Fittings
Order&Delivery- Linen Chutes
Order&Delivery- Equipments
Order&Delivery- Kitchen Equipments
Order&Delivery- Laundary Equipments
Order&Delivery- Facade Lighting
Order&Delivery- Cooking Station
Order&Delivery- Gym Equipments
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 14 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
ConstructiConstruction 516 04-Jan-12 10-Sep-13 04-Jan-12 02-Oct-13 19
Civil PackagCivil Package 304 04-Jan-12 02-Jan-13 04-Jan-12 05-Jun-13 131
Hotel AparteHotel Apartements (Block A) 249 04-Jan-12 24-Oct-12 04-Jan-12 05-Jun-13 186
Foundation LFoundation Level 34 04-Jan-12 13-Feb-12 04-Jan-12 13-Feb-12 0
Earth WorksEarth Works 12 04-Jan-12 17-Jan-12 04-Jan-12 17-Jan-12 0
A1370 Excavation and Compaction 7 04-Jan-12 11-Jan-12 04-Jan-12 11-Jan-12 0
A1400 Base Coarse and Compaction 8 09-Jan-12 17-Jan-12 09-Jan-12 17-Jan-12 0
Deep FoundDeep Foundation 25 15-Jan-12 13-Feb-12 15-Jan-12 13-Feb-12 0
A1060 Laying Polythene Sheet & Blinding 7 15-Jan-12 22-Jan-12 15-Jan-12 22-Jan-12 0
A1080 Water Proofing & Screed 8 19-Jan-12 28-Jan-12 19-Jan-12 28-Jan-12 0
A1160 MEP Works inside Raft Slab 7 29-Jan-12 06-Feb-12 06-Feb-12 13-Feb-12 6
A1100 Raft Slab 1000 mm RC Works 16 25-Jan-12 13-Feb-12 25-Jan-12 13-Feb-12 0
1st Basemen1st Basement Floor Slab 80 14-Feb-12 16-May-12 15-Feb-12 15-Sep-12 101
Walls and CWalls and Columns 15 14-Feb-12 01-Mar-12 15-Feb-12 04-Mar-12 2
A1110 Core Wall RC Works 6 16-Feb-12 22-Feb-12 16-Feb-12 22-Feb-12 0
A1130 Ramp Wall RC Works 6 19-Feb-12 25-Feb-12 27-Feb-12 04-Mar-12 7
A1140 Columns RC Works 10 14-Feb-12 25-Feb-12 15-Feb-12 26-Feb-12 1
A1120 Retaining Wall 250 mm RC Works 15 14-Feb-12 01-Mar-12 15-Feb-12 03-Mar-12 1
SlabSlab 73 20-Feb-12 14-May-12 20-Feb-12 15-Sep-12 103
A1200 Ramp Slab RC Works 7 26-Feb-12 04-Mar-12 05-Mar-12 12-Mar-12 7
A1150 MEP Works inside Slab 7 03-Mar-12 10-Mar-12 05-Mar-12 12-Mar-12 2
A1170 1st Basement Floor Slab RC Works 19 20-Feb-12 12-Mar-12 20-Feb-12 12-Mar-12 0
A1180 Curing for Slab 3 13-Mar-12 15-Mar-12 06-Aug-12 08-Aug-12 124
A1190 Strike Formwork 3 10-Apr-12 12-Apr-12 09-Aug-12 12-Aug-12 103
A1210 Pouring of Light Weight Concrete 2 14-Apr-12 15-Apr-12 13-Aug-12 14-Aug-12 103
A1320 Water Proofing Membrane for Ret. Walls 10 16-Apr-12 26-Apr-12 15-Aug-12 28-Aug-12 103
A1330 Gunited Concrete 50 mm for Ret. Walls 10 28-Apr-12 08-May-12 29-Aug-12 09-Sep-12 103
A1360 Backfilling 5 09-May-12 14-May-12 10-Sep-12 15-Sep-12 103
StairsStairs 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101
Stairs 1Stairs 1 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101
A1380 Stairs RC Works (2nd Basement to 1st Basement) 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101
Ground FloorGround Floor Slab 81 13-Mar-12 14-Jun-12 13-Mar-12 18-Sep-12 79
Walls and CWalls and Columns 15 13-Mar-12 29-Mar-12 13-Mar-12 01-Apr-12 2
A1220 Core Wall RC Works 6 14-Mar-12 20-Mar-12 14-Mar-12 20-Mar-12 0
A1240 Ramp Wall RC Works 7 17-Mar-12 24-Mar-12 25-Mar-12 01-Apr-12 7
A1250 Columns RC Works 10 13-Mar-12 24-Mar-12 13-Mar-12 24-Mar-12 0
A1230 Retaining Wall 250 mm RC Works 15 13-Mar-12 29-Mar-12 13-Mar-12 29-Mar-12 0
SlabSlab 72 19-Mar-12 10-Jun-12 19-Mar-12 18-Sep-12 83
A1300 Ramp Slab RC Works 7 25-Mar-12 01-Apr-12 02-Apr-12 09-Apr-12 7
A1260 MEP Works inside Slab 6 31-Mar-12 05-Apr-12 03-Apr-12 09-Apr-12 3
A1270 Ground Floor Slab RC Works 19 19-Mar-12 09-Apr-12 19-Mar-12 09-Apr-12 0
A1280 Curing for Slab 3 10-Apr-12 12-Apr-12 26-Jul-12 29-Jul-12 91
A1290 Strike Formwork 3 07-May-12 09-May-12 30-Jul-12 01-Aug-12 71
A1310 Pouring of Light Weight Concrete 2 10-May-12 12-May-12 16-Aug-12 18-Aug-12 83
A1340 Water Proofing Membrane for Ret. Walls 10 13-May-12 23-May-12 21-Aug-12 01-Sep-12 83
A1350 Gunited Concrete 50 mm for Ret. Walls 10 24-May-12 04-Jun-12 02-Sep-12 12-Sep-12 83
A1520 Backfilling 5 05-Jun-12 10-Jun-12 13-Sep-12 18-Sep-12 83
StairsStairs 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79
Stair 1Stair 1 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79
A1530 Stairs RC Works (1st Basement to Ground) 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79
1st Floor Slab1st Floor Slab 78 10-Apr-12 10-Jul-12 10-Apr-12 29-Sep-12 67
Walls and CWalls and Columns 9 10-Apr-12 19-Apr-12 10-Apr-12 19-Apr-12 0
A1390 Core Wall RC Works 6 10-Apr-12 16-Apr-12 10-Apr-12 16-Apr-12 0
A1420 Columns RC Works 9 10-Apr-12 19-Apr-12 10-Apr-12 19-Apr-12 0
SlabSlab 46 16-Apr-12 07-Jun-12 16-Apr-12 11-Sep-12 79
A1430 MEP Works inside Slab 5 21-Apr-12 25-Apr-12 02-May-12 07-May-12 10
A1440 1st Floor Slab RC Works 19 16-Apr-12 07-May-12 16-Apr-12 07-May-12 0
A1450 Curing for Slab 3 08-May-12 10-May-12 05-Sep-12 08-Sep-12 100
A1460 Strike Formwork 3 05-Jun-12 07-Jun-12 09-Sep-12 11-Sep-12 79
StairsStairs 6 04-Jul-12 10-Jul-12 16-Sep-12 29-Sep-12 67
Stair 1Stair 1 6 04-Jul-12 10-Jul-12 16-Sep-12 22-Sep-12 61
A1540 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 16-Sep-12 22-Sep-12 61
Stair 2Stair 2 6 04-Jul-12 10-Jul-12 19-Sep-12 25-Sep-12 64
A1550 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 19-Sep-12 25-Sep-12 64
Stair 3Stair 3 6 04-Jul-12 10-Jul-12 23-Sep-12 29-Sep-12 67
A111130 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 23-Sep-12 29-Sep-12 67
2nd Floor Sl2nd Floor Slab 70 08-May-12 29-Jul-12 08-May-12 06-Oct-12 57
Walls and CWalls and Columns 9 08-May-12 17-May-12 08-May-12 17-May-12 0
A1560 Core Wall RC Works 6 08-May-12 14-May-12 08-May-12 14-May-12 0
A1570 Columns RC Works 9 08-May-12 17-May-12 08-May-12 17-May-12 0
SlabSlab 43 14-May-12 03-Jul-12 14-May-12 26-Jul-12 20
A1580 MEP Works inside Slab 5 19-May-12 23-May-12 30-May-12 04-Jun-12 10
A1590 2nd Floor Slab RC Works 19 14-May-12 04-Jun-12 14-May-12 04-Jun-12 0
A1600 Curing for Slab 3 05-Jun-12 07-Jun-12 21-Jul-12 23-Jul-12 38
A1610 Strike Formwork 3 01-Jul-12 03-Jul-12 24-Jul-12 26-Jul-12 20
StairsStairs 6 23-Jul-12 29-Jul-12 26-Sep-12 06-Oct-12 57
Stair 1Stair 1 6 23-Jul-12 29-Jul-12 26-Sep-12 02-Oct-12 54
A1630 Stairs RC Works (1st to 2nd) 6 23-Jul-12 29-Jul-12 26-Sep-12 02-Oct-12 54
Stair 2Stair 2 6 23-Jul-12 29-Jul-12 30-Sep-12 06-Oct-12 57
A1640 Stairs RC Works (1st to 2nd) 6 23-Jul-12 29-Jul-12 30-Sep-12 06-Oct-12 57
3rd Floor Slab3rd Floor Slab 58 05-Jun-12 12-Aug-12 05-Jun-12 13-Oct-12 51
Walls and CWalls and Columns 9 05-Jun-12 14-Jun-12 05-Jun-12 14-Jun-12 0
A1650 Core Wall RC Works 6 05-Jun-12 11-Jun-12 05-Jun-12 11-Jun-12 0
A1660 Columns RC Works 9 05-Jun-12 14-Jun-12 05-Jun-12 14-Jun-12 0
SlabSlab 36 10-Jun-12 22-Jul-12 10-Jun-12 31-Jul-12 8
A1670 MEP Works inside Slab 5 14-Jun-12 20-Jun-12 14-Jun-12 20-Jun-12 0
A1680 3rd Floor Slab RC Works 9 10-Jun-12 20-Jun-12 10-Jun-12 20-Jun-12 0
A1690 Curing for Slab 3 21-Jun-12 24-Jun-12 25-Jul-12 28-Jul-12 29
A1700 Strike Formwork 3 19-Jul-12 22-Jul-12 29-Jul-12 31-Jul-12 8
StairsStairs 6 06-Aug-12 12-Aug-12 03-Oct-12 13-Oct-12 51
Stair 1Stair 1 6 06-Aug-12 12-Aug-12 03-Oct-12 09-Oct-12 48
A1710 Stairs RC Works (2nd to 3rd) 6 06-Aug-12 12-Aug-12 03-Oct-12 09-Oct-12 48
Stair 2Stair 2 6 06-Aug-12 12-Aug-12 07-Oct-12 13-Oct-12 51
A1720 Stairs RC Works (2nd to 3rd) 6 06-Aug-12 12-Aug-12 07-Oct-12 13-Oct-12 51
4th Floor Slab4th Floor Slab 57 21-Jun-12 28-Aug-12 21-Jun-12 20-Oct-12 45
Walls and CWalls and Columns 9 21-Jun-12 01-Jul-12 21-Jun-12 01-Jul-12 0
A1730 Core Wall RC Works 6 21-Jun-12 27-Jun-12 21-Jun-12 27-Jun-12 0
A1740 Columns RC Works 9 21-Jun-12 01-Jul-12 21-Jun-12 01-Jul-12 0
SlabSlab 35 26-Jun-12 05-Aug-12 26-Jun-12 05-Aug-12 0
A1750 MEP Works inside Slab 5 30-Jun-12 04-Jul-12 30-Jun-12 04-Jul-12 0
A1760 4th Slab RC Works 8 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0
A1770 Curing for Slab 3 05-Jul-12 08-Jul-12 30-Jul-12 01-Aug-12 21
A1780 Strike Formwork 3 02-Aug-12 05-Aug-12 02-Aug-12 05-Aug-12 0
StairsStairs 6 22-Aug-12 28-Aug-12 10-Oct-12 20-Oct-12 45
Stair 1Stair 1 6 22-Aug-12 28-Aug-12 10-Oct-12 16-Oct-12 42
A1790 Stairs RC Works (3rd to 4th) 6 22-Aug-12 28-Aug-12 10-Oct-12 16-Oct-12 42
Stair 2Stair 2 6 22-Aug-12 28-Aug-12 14-Oct-12 20-Oct-12 45
A1800 Stairs RC Works (3rd to 4th) 6 22-Aug-12 28-Aug-12 14-Oct-12 20-Oct-12 45
5th Floor Slab5th Floor Slab 57 05-Jul-12 11-Sep-12 14-Jul-12 29-Oct-12 39
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Excavation and Compaction
Base Coarse and Compaction
Laying Polythene Sheet & Blinding
Water Proofing & Screed
MEP Works inside Raft Slab
Raft Slab 1000 mm RC Works
Core Wall RC Works
Ramp Wall RC Works
Columns RC Works
Retaining Wall 250 mm RC Works
Ramp Slab RC Works
MEP Works inside Slab
1st Basement Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (2nd Basement to 1st Basement)
Core Wall RC Works
Ramp Wall RC Works
Columns RC Works
Retaining Wall 250 mm RC Works
Ramp Slab RC Works
MEP Works inside Slab
Ground Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (1st Basement to Ground)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
1st Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
2nd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (1st to 2nd)
Stairs RC Works (1st to 2nd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
3rd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (2nd to 3rd)
Stairs RC Works (2nd to 3rd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
4th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (3rd to 4th)
Stairs RC Works (3rd to 4th)
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 15 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Walls and CWalls and Columns 9 05-Jul-12 15-Jul-12 14-Jul-12 23-Jul-12 7
A1810 Core Wall RC Works 6 05-Jul-12 11-Jul-12 14-Jul-12 19-Jul-12 7
A1820 Columns RC Works 9 05-Jul-12 15-Jul-12 14-Jul-12 23-Jul-12 7
SlabSlab 36 09-Jul-12 21-Aug-12 17-Jul-12 06-Sep-12 14
A1830 MEP Works inside Slab 5 14-Jul-12 18-Jul-12 23-Jul-12 28-Jul-12 8
A1840 5th Slab RC Works 10 09-Jul-12 19-Jul-12 17-Jul-12 28-Jul-12 7
A1850 Curing for Slab 3 21-Jul-12 23-Jul-12 01-Sep-12 03-Sep-12 34
A1860 Strike Formwork 3 16-Aug-12 21-Aug-12 04-Sep-12 06-Sep-12 14
StairsStairs 6 05-Sep-12 11-Sep-12 17-Oct-12 29-Oct-12 39
Stair 1Stair 1 6 05-Sep-12 11-Sep-12 17-Oct-12 23-Oct-12 36
A1870 Stairs RC Works (4th to 5th) 6 05-Sep-12 11-Sep-12 17-Oct-12 23-Oct-12 36
Stair 2Stair 2 6 05-Sep-12 11-Sep-12 21-Oct-12 29-Oct-12 39
A1880 Stairs RC Works (4th to 5th) 6 05-Sep-12 11-Sep-12 21-Oct-12 29-Oct-12 39
6th Floor Slab6th Floor Slab 57 21-Jul-12 26-Sep-12 29-Jul-12 06-Nov-12 33
Walls and CWalls and Columns 9 21-Jul-12 30-Jul-12 29-Jul-12 07-Aug-12 7
A1890 Core Wall RC Works 6 21-Jul-12 26-Jul-12 29-Jul-12 04-Aug-12 7
A1900 Columns RC Works 9 21-Jul-12 30-Jul-12 29-Jul-12 07-Aug-12 7
SlabSlab 34 25-Jul-12 04-Sep-12 02-Aug-12 20-Sep-12 14
A1910 MEP Works inside Slab 5 29-Jul-12 02-Aug-12 07-Aug-12 12-Aug-12 8
A1920 6th Slab RC Works (L + 9.20) 9 25-Jul-12 04-Aug-12 02-Aug-12 12-Aug-12 7
A1930 Curing for Slab 3 05-Aug-12 07-Aug-12 15-Sep-12 17-Sep-12 33
A1940 Strike Formwork 3 02-Sep-12 04-Sep-12 18-Sep-12 20-Sep-12 14
StairsStairs 6 20-Sep-12 26-Sep-12 24-Oct-12 06-Nov-12 33
Stair 1Stair 1 6 20-Sep-12 26-Sep-12 24-Oct-12 01-Nov-12 29
A1950 Stairs RC Works (5th to 6th) 6 20-Sep-12 26-Sep-12 24-Oct-12 01-Nov-12 29
Stair 2Stair 2 6 20-Sep-12 26-Sep-12 31-Oct-12 06-Nov-12 33
A1960 Stairs RC Works (5th to 6th) 6 20-Sep-12 26-Sep-12 31-Oct-12 06-Nov-12 33
7th Floor Slab7th Floor Slab 56 05-Aug-12 10-Oct-12 13-Aug-12 28-Nov-12 39
Walls and CWalls and Columns 9 05-Aug-12 14-Aug-12 13-Aug-12 25-Aug-12 7
A1970 Core Wall RC Works 6 05-Aug-12 11-Aug-12 13-Aug-12 21-Aug-12 7
A1980 Columns RC Works 9 05-Aug-12 14-Aug-12 13-Aug-12 25-Aug-12 7
SlabSlab 34 09-Aug-12 19-Sep-12 18-Aug-12 27-Sep-12 7
A1990 MEP Works inside Slab 5 13-Aug-12 18-Aug-12 25-Aug-12 29-Aug-12 8
A2000 7th Slab RC Works 9 09-Aug-12 21-Aug-12 18-Aug-12 29-Aug-12 7
A2010 Curing for Slab 3 22-Aug-12 25-Aug-12 22-Sep-12 24-Sep-12 26
A2020 Strike Formwork 3 17-Sep-12 19-Sep-12 25-Sep-12 27-Sep-12 7
StairsStairs 6 04-Oct-12 10-Oct-12 05-Nov-12 28-Nov-12 39
Stair 1Stair 1 6 04-Oct-12 10-Oct-12 05-Nov-12 11-Nov-12 25
A2030 Stairs RC Works (6th to 7th) 6 04-Oct-12 10-Oct-12 05-Nov-12 11-Nov-12 25
Stair 2Stair 2 6 04-Oct-12 10-Oct-12 22-Nov-12 28-Nov-12 39
A2040 Stairs RC Works (6th to 7th) 6 04-Oct-12 10-Oct-12 22-Nov-12 28-Nov-12 39
Roof Floor SlRoof Floor Slab 55 22-Aug-12 24-Oct-12 30-Aug-12 05-Jun-13 186
Walls and CWalls and Columns 8 22-Aug-12 30-Aug-12 30-Aug-12 11-Sep-12 10
A2050 Core Wall RC Works 5 22-Aug-12 27-Aug-12 30-Aug-12 04-Sep-12 7
A2060 Columns RC Works 8 22-Aug-12 30-Aug-12 03-Sep-12 11-Sep-12 10
SlabSlab 34 26-Aug-12 03-Oct-12 06-Sep-12 10-Nov-12 30
A2070 MEP Works inside Slab 4 29-Aug-12 02-Sep-12 11-Sep-12 15-Sep-12 11
A2080 Roof Floor Slab RC Works 8 26-Aug-12 03-Sep-12 06-Sep-12 15-Sep-12 10
A2090 Curing for Slab 3 04-Sep-12 06-Sep-12 07-Nov-12 10-Nov-12 53
A2100 Strike Formwork 3 01-Oct-12 03-Oct-12 13-Oct-12 15-Oct-12 10
ParapetsParapets 10 08-Sep-12 18-Sep-12 26-May-13 05-Jun-13 217
A104120 Parapets RC Works 10 08-Sep-12 18-Sep-12 26-May-13 05-Jun-13 217
Chillers FouChillers Foundation 5 08-Sep-12 12-Sep-12 11-Nov-12 17-Nov-12 53
A117090 Chillers Foundations RC Works 5 08-Sep-12 12-Sep-12 11-Nov-12 17-Nov-12 53
StairsStairs 6 18-Oct-12 24-Oct-12 10-Dec-12 02-Jan-13 55
Stair 1Stair 1 6 18-Oct-12 24-Oct-12 10-Dec-12 16-Dec-12 41
A2110 Stairs RC Works (7th to Roof) 6 18-Oct-12 24-Oct-12 10-Dec-12 16-Dec-12 41
Stair 2Stair 2 6 18-Oct-12 24-Oct-12 26-Dec-12 02-Jan-13 55
A2120 Stairs RC Works (7th to Roof) 6 18-Oct-12 24-Oct-12 26-Dec-12 02-Jan-13 55
Upper Roof LUpper Roof Level 44 04-Sep-12 24-Oct-12 17-Sep-12 20-Feb-13 96
ColumnsColumns 9 04-Sep-12 13-Sep-12 17-Sep-12 26-Sep-12 11
A2140 Columns RC Works 9 04-Sep-12 13-Sep-12 17-Sep-12 26-Sep-12 11
SlabsSlabs 34 09-Sep-12 17-Oct-12 22-Sep-12 29-Jan-13 83
A2150 MEP Works inside Slab 4 12-Sep-12 16-Sep-12 26-Sep-12 30-Sep-12 12
A2160 Upper Roof Level Slab RC Works 8 09-Sep-12 17-Sep-12 22-Sep-12 30-Sep-12 11
A2170 Curing for Slab 3 18-Sep-12 20-Sep-12 27-Jan-13 29-Jan-13 106
A2180 Strike Formwork 3 15-Oct-12 17-Oct-12 30-Oct-12 01-Nov-12 11
StairsStairs 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96
Stair 2Stair 2 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96
A2200 Stairs RC Works (Roof to Upper Roof) 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96
Hotel (BlockHotel (Block B) 241 19-Mar-12 02-Jan-13 27-Mar-12 05-Jun-13 131
Foundation LFoundation Level 44 19-Mar-12 08-May-12 27-Mar-12 20-May-12 10
Earth WorksEarth Works 13 19-Mar-12 02-Apr-12 27-Mar-12 24-Apr-12 19
Part 1 (B1)Part 1 (B1) 13 19-Mar-12 02-Apr-12 27-Mar-12 10-Apr-12 7
A12320 Excavation and Compaction 8 19-Mar-12 27-Mar-12 27-Mar-12 04-Apr-12 7
A12330 Base Coarse and Compaction 8 25-Mar-12 02-Apr-12 02-Apr-12 10-Apr-12 7
Part 2 (B2)Part 2 (B2) 13 19-Mar-12 02-Apr-12 10-Apr-12 24-Apr-12 19
A12730 Excavation and Compaction 8 19-Mar-12 27-Mar-12 10-Apr-12 18-Apr-12 19
A12740 Base Coarse and Compaction 8 25-Mar-12 02-Apr-12 16-Apr-12 24-Apr-12 19
Deep FoundDeep Foundation 35 29-Mar-12 08-May-12 07-Apr-12 20-May-12 10
Part 1 (B1)Part 1 (B1) 25 29-Mar-12 26-Apr-12 07-Apr-12 05-May-12 7
A11520 Laying Polythene Sheet & Blinding 5 29-Mar-12 03-Apr-12 07-Apr-12 11-Apr-12 7
A11530 Water Proofing & Screed 7 02-Apr-12 09-Apr-12 10-Apr-12 17-Apr-12 7
A11580 MEP Works inside Raft Slab 7 10-Apr-12 17-Apr-12 28-Apr-12 05-May-12 15
A11540 Raft Slab 1000 mm RC Works (Part 1) 18 07-Apr-12 26-Apr-12 15-Apr-12 05-May-12 7
Part 2 (B2)Part 2 (B2) 35 29-Mar-12 08-May-12 21-Apr-12 20-May-12 10
A12750 Laying Polythene Sheet & Blinding 4 29-Mar-12 02-Apr-12 21-Apr-12 24-Apr-12 19
A12760 Water Proofing & Screed 6 02-Apr-12 08-Apr-12 24-Apr-12 30-Apr-12 19
A12770 MEP Works inside Raft Slab 10 18-Apr-12 29-Apr-12 09-May-12 20-May-12 18
A12780 Raft Slab 1000 mm RC Works (Part 2) 18 18-Apr-12 08-May-12 30-Apr-12 20-May-12 10
1st Basemen1st Basement Floor Slab 79 28-Apr-12 29-Jul-12 06-May-12 26-Jan-13 147
Walls and CWalls and Columns 20 28-Apr-12 20-May-12 06-May-12 05-Jun-12 14
Part 1 (B1)Part 1 (B1) 10 28-Apr-12 08-May-12 06-May-12 16-May-12 7
A11570 Columns RC Works 6 28-Apr-12 03-May-12 07-May-12 13-May-12 8
A12340 Tank Wall RC Works 6 29-Apr-12 05-May-12 07-May-12 13-May-12 7
A11550 Core Wall RC Works 8 30-Apr-12 08-May-12 08-May-12 16-May-12 7
A11560 Retaining Wall 250 mm RC Works (Part 1) 10 28-Apr-12 08-May-12 06-May-12 16-May-12 7
Part 2 (B2)Part 2 (B2) 10 09-May-12 20-May-12 21-May-12 05-Jun-12 14
A12610 Ramp Wall RC Works 5 09-May-12 14-May-12 21-May-12 26-May-12 10
A12790 Columns RC Works 6 09-May-12 15-May-12 21-May-12 27-May-12 10
A12800 Tank Wall RC Works 6 10-May-12 16-May-12 28-May-12 03-Jun-12 15
A12810 Core Wall RC Works 6 12-May-12 17-May-12 28-May-12 03-Jun-12 14
A12820 Retaining Wall 250 mm RC Works (Part 2) 8 12-May-12 20-May-12 28-May-12 05-Jun-12 14
SlabSlab 63 03-May-12 16-Jul-12 12-May-12 26-Jan-13 158
A11590 MEP Works inside Slab 5 12-May-12 16-May-12 28-May-12 02-Jun-12 14
A12200 Ramp Slab RC Works 6 15-May-12 21-May-12 27-May-12 02-Jun-12 10
A11600 1st Basement Floor Slab RC Works 19 03-May-12 24-May-12 12-May-12 02-Jun-12 7
A11610 Curing for Slab 3 26-May-12 28-May-12 28-Nov-12 01-Dec-12 154
A11620 Strike Formwork 3 21-Jun-12 24-Jun-12 03-Dec-12 05-Dec-12 135
A11630 Pouring of Light Weight Concrete 2 25-Jun-12 26-Jun-12 03-Jan-13 05-Jan-13 158
A11720 Water Proofing Membrane for Ret. Walls 7 27-Jun-12 04-Jul-12 06-Jan-13 13-Jan-13 158
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
5th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (4th to 5th)
Stairs RC Works (4th to 5th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
6th Slab RC Works (L + 9.20)
Curing for Slab
Strike Formwork
Stairs RC Works (5th to 6th)
Stairs RC Works (5th to 6th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
7th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (6th to 7th)
Stairs RC Works (6th to 7th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
Roof Floor Slab RC Works
Curing for Slab
Strike Formwork
Parapets RC Works
Chillers Foundations RC Works
Stairs RC Works (7th to Roof)
Stairs RC Works (7th to Roof)
Columns RC Works
MEP Works inside Slab
Upper Roof Level Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (Roof to Upper Roof)
Excavation and Compaction
Base Coarse and Compaction
Excavation and Compaction
Base Coarse and Compaction
Laying Polythene Sheet & Blinding
Water Proofing & Screed
MEP Works inside Raft Slab
Raft Slab 1000 mm RC Works (Part 1)
Laying Polythene Sheet & Blinding
Water Proofing & Screed
MEP Works inside Raft Slab
Raft Slab 1000 mm RC Works (Part 2)
Columns RC Works
Tank WallRC Works
Core Wall RC Works
Retaining Wall 250 mm RC Works (Part 1)
Ramp Wall RC Works
Columns RC Works
Tank WallRC Works
Core Wall RC Works
Retaining Wall 250 mm RC Works (Part 2)
MEP Works inside Slab
Ramp Slab RC Works
1st Basement Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 16 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A11730 Gunited Concrete 50 mm for Ret. Walls 7 05-Jul-12 12-Jul-12 14-Jan-13 21-Jan-13 158
A11820 Backfilling 3 14-Jul-12 16-Jul-12 22-Jan-13 26-Jan-13 158
StairsStairs 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
Stairs 1Stairs 1 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
A12350 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
Stairs 2Stairs 2 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
A12360 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
Stairs 3Stairs 3 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
A12370 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147
Ground FloorGround Floor Slab 76 26-May-12 25-Aug-12 03-Jun-12 02-Feb-13 132
Walls and CWalls and Columns 21 26-May-12 19-Jun-12 03-Jun-12 27-Jun-12 7
A117050 Ramp Wall RC Works 6 26-May-12 31-May-12 16-Jun-12 23-Jun-12 18
A11660 Columns RC Works 11 26-May-12 06-Jun-12 03-Jun-12 14-Jun-12 7
A11640 Core Wall RC Works 15 27-May-12 12-Jun-12 04-Jun-12 21-Jun-12 7
A11650 Retaining Wall 250 mm RC Works 21 26-May-12 19-Jun-12 03-Jun-12 27-Jun-12 7
SlabSlab 64 30-May-12 13-Aug-12 07-Jun-12 02-Feb-13 140
A117060 Ramp Slab RC Works 7 02-Jun-12 09-Jun-12 24-Jun-12 01-Jul-12 18
A11670 MEP Works inside Slab 10 02-Jun-12 12-Jun-12 20-Jun-12 01-Jul-12 15
A11680 Ground Floor Slab RC Works 20 30-May-12 23-Jun-12 07-Jun-12 01-Jul-12 7
A11690 Curing for Slab 3 24-Jun-12 26-Jun-12 27-Sep-12 30-Sep-12 80
A11700 Strike Formwork 3 19-Jul-12 22-Jul-12 01-Oct-12 03-Oct-12 61
A11710 Pouring of Light Weight Concrete 2 23-Jul-12 24-Jul-12 10-Jan-13 12-Jan-13 140
A11740 Water Proofing Membrane for Ret. Walls 7 25-Jul-12 01-Aug-12 13-Jan-13 20-Jan-13 140
A11750 Gunited Concrete 50 mm for Ret. Walls 7 02-Aug-12 09-Aug-12 21-Jan-13 29-Jan-13 140
A11830 Backfilling 3 11-Aug-12 13-Aug-12 30-Jan-13 02-Feb-13 140
StairsStairs 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
Stairs 1Stairs 1 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
A12380 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
Stairs 2Stairs 2 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
A12390 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
Stairs 3Stairs 3 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
A12400 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132
1st Floor Slab1st Floor Slab 72 24-Jun-12 17-Sep-12 02-Jul-12 25-Feb-13 132
Walls and CWalls and Columns 9 24-Jun-12 03-Jul-12 02-Jul-12 11-Jul-12 7
A11760 Core Wall RC Works 6 24-Jun-12 30-Jun-12 02-Jul-12 08-Jul-12 7
A11770 Columns RC Works 9 24-Jun-12 03-Jul-12 02-Jul-12 11-Jul-12 7
SlabSlab 42 28-Jun-12 15-Aug-12 07-Jul-12 23-Oct-12 57
A11780 MEP Works inside Slab 5 04-Jul-12 09-Jul-12 18-Jul-12 23-Jul-12 12
A11790 1st Floor Slab RC Works 15 28-Jun-12 15-Jul-12 07-Jul-12 23-Jul-12 7
A11800 Curing for Slab 3 16-Jul-12 18-Jul-12 17-Oct-12 20-Oct-12 78
A11810 Strike Formwork 3 13-Aug-12 15-Aug-12 21-Oct-12 23-Oct-12 57
StairsStairs 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
Stairs 1Stairs 1 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
A12410 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
Stairs 2Stairs 2 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
A12420 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
Stairs 3Stairs 3 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
A12430 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
Stairs 4Stairs 4 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
A109130 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132
2nd Floor Sl2nd Floor Slab 66 16-Jul-12 02-Oct-12 24-Jul-12 25-Feb-13 119
Walls and CWalls and Columns 9 16-Jul-12 25-Jul-12 24-Jul-12 02-Aug-12 7
A11840 Core Wall RC Works 6 16-Jul-12 22-Jul-12 24-Jul-12 30-Jul-12 7
A11850 Columns RC Works 9 16-Jul-12 25-Jul-12 24-Jul-12 02-Aug-12 7
SlabSlab 43 21-Jul-12 10-Sep-12 29-Jul-12 04-Oct-12 21
A11860 MEP Works inside Slab 5 26-Jul-12 31-Jul-12 13-Aug-12 18-Aug-12 15
A11870 2nd Floor Slab RC Works 18 21-Jul-12 09-Aug-12 29-Jul-12 18-Aug-12 7
A11880 Curing for Slab 3 11-Aug-12 13-Aug-12 29-Sep-12 01-Oct-12 40
A11890 Strike Formwork 3 08-Sep-12 10-Sep-12 02-Oct-12 04-Oct-12 21
StairsStairs 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
Stairs 1Stairs 1 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
A12440 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
Stairs 2Stairs 2 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
A12450 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
Stairs 3Stairs 3 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
A12460 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119
3rd Floor Slab3rd Floor Slab 55 11-Aug-12 15-Oct-12 21-Aug-12 25-Feb-13 108
Walls and CWalls and Columns 6 11-Aug-12 16-Aug-12 21-Aug-12 27-Aug-12 7
A11900 Core Wall RC Works 3 11-Aug-12 13-Aug-12 21-Aug-12 23-Aug-12 7
A11910 Columns RC Works 6 11-Aug-12 16-Aug-12 21-Aug-12 27-Aug-12 7
SlabSlab 35 14-Aug-12 25-Sep-12 25-Aug-12 20-Oct-12 21
A11920 MEP Works inside Slab 3 18-Aug-12 22-Aug-12 30-Aug-12 02-Sep-12 9
A11930 3rd Floor Slab RC Works 8 14-Aug-12 25-Aug-12 25-Aug-12 02-Sep-12 7
A11940 Curing for Slab 3 26-Aug-12 28-Aug-12 14-Oct-12 16-Oct-12 42
A11950 Strike Formwork 3 23-Sep-12 25-Sep-12 17-Oct-12 20-Oct-12 21
StairsStairs 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
Stairs 1Stairs 1 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
A12470 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
Stairs 2Stairs 2 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
A12480 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
Stairs 3Stairs 3 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
A12490 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108
4th Floor Slab4th Floor Slab 54 26-Aug-12 29-Oct-12 03-Sep-12 03-Feb-13 79
Walls and CWalls and Columns 6 26-Aug-12 01-Sep-12 03-Sep-12 09-Sep-12 7
A11960 Core Wall RC Works 3 26-Aug-12 28-Aug-12 03-Sep-12 05-Sep-12 7
A11970 Columns RC Works 6 26-Aug-12 01-Sep-12 03-Sep-12 09-Sep-12 7
SlabSlab 35 29-Aug-12 08-Oct-12 06-Sep-12 20-Oct-12 10
A11980 MEP Works inside Slab 5 02-Sep-12 06-Sep-12 11-Sep-12 16-Sep-12 8
A11990 4th Slab RC Works 9 29-Aug-12 08-Sep-12 06-Sep-12 16-Sep-12 7
A12000 Curing for Slab 3 09-Sep-12 11-Sep-12 14-Oct-12 16-Oct-12 30
A12010 Strike Formwork 3 06-Oct-12 08-Oct-12 17-Oct-12 20-Oct-12 10
StairsStairs 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
Stairs 1Stairs 1 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
A12500 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
Stairs 2Stairs 2 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
A12510 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
Stairs 3Stairs 3 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
A12520 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79
5th Floor Slab5th Floor Slab 53 09-Sep-12 11-Nov-12 17-Sep-12 03-Feb-13 68
Walls and CWalls and Columns 6 09-Sep-12 15-Sep-12 17-Sep-12 23-Sep-12 7
A12020 Core Wall RC Works 3 09-Sep-12 11-Sep-12 17-Sep-12 19-Sep-12 7
A12030 Columns RC Works 6 09-Sep-12 15-Sep-12 17-Sep-12 23-Sep-12 7
SlabSlab 33 12-Sep-12 20-Oct-12 20-Sep-12 10-Nov-12 16
A12040 MEP Works inside Slab 3 16-Sep-12 18-Sep-12 26-Sep-12 29-Sep-12 9
A12050 5th Slab RC Works 8 12-Sep-12 20-Sep-12 20-Sep-12 29-Sep-12 7
A12060 Curing for Slab 3 22-Sep-12 24-Sep-12 04-Nov-12 06-Nov-12 35
A12070 Strike Formwork 3 17-Oct-12 20-Oct-12 07-Nov-12 10-Nov-12 16
StairsStairs 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
Stairs 1Stairs 1 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
A12530 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
Stairs 2Stairs 2 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (2nd Basement to 1st Basement)
Stairs RC Works (2nd Basement to 1st Basement)
Stairs RC Works (2nd Basement to 1st Basement)
Ramp Wall RC Works
Columns RC Works
Core Wall RC Works
Retaining Wall 250 mm RC Works
Ramp Slab RC Works
MEP Works inside Slab
Ground Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (1st Basement toGround)
Stairs RC Works (1st Basement toGround)
Stairs RC Works (1st Basement toGround)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
1st Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
2nd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (1st to 2nd)
Stairs RC Works (1st to 2nd)
Stairs RC Works (1st to 2nd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
3rd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (2nd to 3rd)
Stairs RC Works (2nd to 3rd)
Stairs RC Works (2nd to 3rd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
4th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (3rd to 4th)
Stairs RC Works (3rd to 4th)
Stairs RC Works (3rd to 4th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
5th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (4th to 5th)
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 17 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A12540 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
Stairs 3Stairs 3 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
A12550 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68
6th Floor Slab6th Floor Slab 53 22-Sep-12 25-Nov-12 30-Sep-12 30-Jan-13 54
Walls and CWalls and Columns 6 22-Sep-12 27-Sep-12 30-Sep-12 06-Oct-12 7
A12080 Core Wall RC Works 3 22-Sep-12 24-Sep-12 30-Sep-12 02-Oct-12 7
A12090 Columns RC Works 6 22-Sep-12 27-Sep-12 30-Sep-12 06-Oct-12 7
SlabSlab 32 26-Sep-12 04-Nov-12 04-Oct-12 17-Nov-12 10
A12100 MEP Works inside Slab 3 29-Sep-12 01-Oct-12 10-Oct-12 13-Oct-12 10
A12110 6th Slab RC Works 8 26-Sep-12 04-Oct-12 04-Oct-12 13-Oct-12 7
A12120 Curing for Slab 3 06-Oct-12 08-Oct-12 10-Nov-12 12-Nov-12 28
A12130 Strike Formwork 3 01-Nov-12 04-Nov-12 13-Nov-12 17-Nov-12 10
StairsStairs 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
Stairs 1Stairs 1 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
A12560 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
Stairs 2Stairs 2 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
A12570 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
Stairs 3Stairs 3 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
A12580 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54
7th Floor Slab7th Floor Slab 58 06-Oct-12 16-Dec-12 14-Oct-12 30-Jan-13 37
Walls and CWalls and Columns 6 06-Oct-12 11-Oct-12 14-Oct-12 22-Oct-12 9
A12140 Core Wall RC Works 3 06-Oct-12 08-Oct-12 14-Oct-12 16-Oct-12 7
A12150 Columns RC Works 6 06-Oct-12 11-Oct-12 16-Oct-12 22-Oct-12 9
SlabSlab 31 10-Oct-12 18-Nov-12 21-Oct-12 28-Nov-12 9
A12160 MEP Works inside Slab 3 13-Oct-12 15-Oct-12 29-Oct-12 31-Oct-12 12
A12170 7th Slab RC Works 8 10-Oct-12 18-Oct-12 21-Oct-12 31-Oct-12 9
A12180 Curing for Slab 3 20-Oct-12 22-Oct-12 22-Nov-12 25-Nov-12 26
A12190 Strike Formwork 3 14-Nov-12 18-Nov-12 26-Nov-12 28-Nov-12 9
StairsStairs 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
Stairs 1Stairs 1 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
A12590 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
Stairs 2Stairs 2 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
A12600 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
Stairs 3Stairs 3 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
A109150 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37
Roof Floor SlRoof Floor Slab 60 20-Oct-12 02-Jan-13 03-Nov-12 05-Jun-13 131
ColumnsColumns 6 20-Oct-12 28-Oct-12 03-Nov-12 08-Nov-12 10
A12210 Columns RC Works 6 20-Oct-12 28-Oct-12 03-Nov-12 08-Nov-12 10
SlabSlab 32 23-Oct-12 03-Dec-12 06-Nov-12 15-Dec-12 10
A12220 MEP Works inside Slab 3 29-Oct-12 31-Oct-12 12-Nov-12 14-Nov-12 12
A12230 Roof Floor Slab RC Works 8 23-Oct-12 03-Nov-12 06-Nov-12 14-Nov-12 10
A12240 Curing for Slab 3 04-Nov-12 06-Nov-12 18-Nov-12 20-Nov-12 11
A12250 Strike Formwork 3 29-Nov-12 03-Dec-12 12-Dec-12 15-Dec-12 10
ParapetsParapets 10 22-Dec-12 02-Jan-13 26-May-13 05-Jun-13 131
A104150 Parapets RC Works 10 22-Dec-12 02-Jan-13 26-May-13 05-Jun-13 131
Chillers FouChillers Foundation 5 07-Nov-12 12-Nov-12 21-Nov-12 26-Nov-12 11
A117100 Chillers Foundations RC Works 5 07-Nov-12 12-Nov-12 21-Nov-12 26-Nov-12 11
StairsStairs 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32
Stairs 1Stairs 1 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32
A109160 Stairs RC Works (7th to Roof) 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32
Stairs 2Stairs 2 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32
A109170 Stairs RC Works (7th to Roof) 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32
Upper Roof LUpper Roof Level 34 04-Nov-12 15-Dec-12 18-Nov-12 27-Dec-12 11
ColumnsColumns 6 04-Nov-12 10-Nov-12 18-Nov-12 24-Nov-12 11
A12270 Columns RC Works 6 04-Nov-12 10-Nov-12 18-Nov-12 24-Nov-12 11
SlabsSlabs 31 07-Nov-12 15-Dec-12 21-Nov-12 27-Dec-12 11
A12280 MEP Works inside Slab 3 11-Nov-12 13-Nov-12 26-Nov-12 28-Nov-12 12
A12290 Upper Roof Level Slab RC Works 7 07-Nov-12 14-Nov-12 21-Nov-12 28-Nov-12 11
A12300 Curing for Slab 3 17-Nov-12 19-Nov-12 22-Dec-12 24-Dec-12 29
A12310 Strike Formwork 3 12-Dec-12 15-Dec-12 25-Dec-12 27-Dec-12 11
ResidentialResidential (Block C) 275 15-Jan-12 09-Dec-12 23-Jan-12 05-Jun-13 151
Foundation LFoundation Level 51 15-Jan-12 14-Mar-12 23-Jan-12 22-Mar-12 7
Earth WorksEarth Works 11 15-Jan-12 26-Jan-12 23-Jan-12 22-Feb-12 22
Part 1 (C1)Part 1 (C1) 11 15-Jan-12 26-Jan-12 23-Jan-12 05-Feb-12 7
A12660 Excavation and Compaction 8 15-Jan-12 23-Jan-12 23-Jan-12 31-Jan-12 7
A12670 Base Coarse and Compaction 8 18-Jan-12 26-Jan-12 26-Jan-12 05-Feb-12 7
Part 2 (C2)Part 2 (C2) 7 15-Jan-12 22-Jan-12 15-Feb-12 22-Feb-12 26
A11200 Excavation and Compaction 5 15-Jan-12 19-Jan-12 15-Feb-12 20-Feb-12 26
A11210 Base Coarse and Compaction 5 17-Jan-12 22-Jan-12 18-Feb-12 22-Feb-12 26
Deep FoundDeep Foundation 44 23-Jan-12 14-Mar-12 31-Jan-12 22-Mar-12 7
Part 1 (C1)Part 1 (C1) 44 23-Jan-12 14-Mar-12 31-Jan-12 22-Mar-12 7
A12620 Laying Polythene Sheet & Blinding 5 23-Jan-12 28-Jan-12 31-Jan-12 06-Feb-12 7
A12630 Water Proofing & Screed 8 26-Jan-12 05-Feb-12 05-Feb-12 13-Feb-12 7
A12640 MEP Works inside Raft Slab 7 06-Feb-12 13-Feb-12 22-Feb-12 29-Feb-12 14
A12650 Raft Slab 1000 mm RC Works (Part 1) 18 31-Jan-12 21-Feb-12 09-Feb-12 29-Feb-12 7
A12680 Ramp Cutting 19 22-Feb-12 14-Mar-12 01-Mar-12 22-Mar-12 7
Part 2 (C2)Part 2 (C2) 43 23-Jan-12 13-Mar-12 23-Feb-12 21-Mar-12 7
A10170 Laying Polythene Sheet & Blinding 3 23-Jan-12 25-Jan-12 23-Feb-12 26-Feb-12 26
A10180 Water Proofing & Screed 5 26-Jan-12 31-Jan-12 27-Feb-12 03-Mar-12 26
A10240 MEP Works inside Raft Slab 4 14-Feb-12 18-Feb-12 18-Mar-12 21-Mar-12 28
A10190 Raft Slab 1000 mm RC Works (Part 2) 18 22-Feb-12 13-Mar-12 01-Mar-12 21-Mar-12 7
1st Basemen1st Basement Floor Slab 116 22-Feb-12 07-Jul-12 21-Mar-12 26-Jan-13 166
Walls and CWalls and Columns 27 22-Feb-12 24-Mar-12 21-Mar-12 25-Apr-12 28
Part 1 (C1)Part 1 (C1) 12 22-Feb-12 06-Mar-12 21-Mar-12 10-Apr-12 30
A10230 Columns RC Works 8 22-Feb-12 01-Mar-12 28-Mar-12 05-Apr-12 30
A11220 Tank Wall RC Works 10 23-Feb-12 05-Mar-12 21-Mar-12 01-Apr-12 23
A10200 Core Wall RC Works 10 25-Feb-12 06-Mar-12 21-Mar-12 01-Apr-12 22
A10210 Retaining Wall 250 mm RC Works 12 22-Feb-12 06-Mar-12 28-Mar-12 10-Apr-12 30
Part 2 (C2)Part 2 (C2) 9 14-Mar-12 24-Mar-12 22-Mar-12 25-Apr-12 28
A12690 Columns RC Works 4 14-Mar-12 18-Mar-12 22-Apr-12 25-Apr-12 33
A12710 Core Wall RC Works 6 17-Mar-12 22-Mar-12 19-Apr-12 25-Apr-12 29
A12720 Retaining Wall 250 mm RC Works 9 14-Mar-12 24-Mar-12 22-Mar-12 01-Apr-12 7
SlabSlab 78 25-Mar-12 24-Jun-12 02-Apr-12 26-Jan-13 177
A10250 MEP Works inside Slab 8 25-Mar-12 02-Apr-12 28-Apr-12 06-May-12 29
A10260 1st Basement Floor Slab RC Works 30 25-Mar-12 28-Apr-12 02-Apr-12 06-May-12 7
A10270 Curing for Slab 3 29-Apr-12 01-May-12 03-Oct-12 06-Oct-12 132
A10280 Strike Formwork 3 29-May-12 31-May-12 07-Oct-12 09-Oct-12 109
A10300 Pouring of Light Weight Concrete 2 02-Jun-12 03-Jun-12 03-Jan-13 05-Jan-13 177
A10410 Water Proofing Membrane for Ret. Walls 7 04-Jun-12 11-Jun-12 06-Jan-13 13-Jan-13 177
A10420 Gunited Concrete 50 mm for Ret. Walls 7 12-Jun-12 20-Jun-12 14-Jan-13 21-Jan-13 177
A10520 Backfilling 3 21-Jun-12 24-Jun-12 22-Jan-13 26-Jan-13 177
StairsStairs 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
Stairs 1Stairs 1 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
A11230 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
Stairs 2Stairs 2 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
A11240 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
Stairs 3Stairs 3 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
A11250 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166
Ground FloorGround Floor Slab 77 29-Apr-12 28-Jul-12 07-May-12 26-Jan-13 148
Walls and CWalls and Columns 21 29-Apr-12 22-May-12 07-May-12 30-May-12 7
A10340 Columns RC Works 11 29-Apr-12 10-May-12 07-May-12 19-May-12 7
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Stairs RC Works (4th to 5th)
Stairs RC Works (4th to 5th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
6th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (5th to 6th)
Stairs RC Works (5th to 6th)
Stairs RC Works (5th to 6th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
7th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (6th to 7th)
Stairs RC Works (6th to 7th)
Stairs RC Works (6th to 7th)
Columns RC Works
MEP Works inside Slab
Roof Floor Slab RC Works
Curing for Slab
Strike Formwork
Parapets RC Works
Chillers Foundations RC Works
Stairs RC Works (7th to Roof)
Stairs RC Works (7th to Roof)
Columns RC Works
MEP Works inside Slab
Upper Roof LevelSlab RC Works
Curing for Slab
Strike Formwork
Excavation and Compaction
Base Coarse and Compaction
Excavation and Compaction
Base Coarse and Compaction
Laying Polythene Sheet & Blinding
Water Proofing & Screed
MEP Works inside Raft Slab
Raft Slab 1000 mm RC Works (Part 1)
Ramp Cutting
Laying Polythene Sheet & Blinding
Water Proofing & Screed
MEP Works inside Raft Slab
Raft Slab 1000 mm RC Works (Part 2)
Columns RC Works
Tank WallRC Works
Core Wall RC Works
Retaining Wall 250 mm RC Works
Columns RC Works
Core Wall RC Works
Retaining Wall 250 mm RC Works
MEP Works inside Slab
1st Basement Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (2nd Basement to 1st Basement)
Stairs RC Works (2nd Basement to 1st Basement)
Stairs RC Works (2nd Basement to 1st Basement)
Columns RC Works
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 18 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A10310 Core Wall RC Works 15 30-Apr-12 16-May-12 08-May-12 24-May-12 7
A10320 Retaining Wall 250 mm RC Works 21 29-Apr-12 22-May-12 07-May-12 30-May-12 7
SlabSlab 68 03-May-12 22-Jul-12 12-May-12 26-Jan-13 153
A10350 MEP Works inside Slab 8 13-May-12 21-May-12 27-May-12 04-Jun-12 12
A10360 Ground Floor Slab RC Works 21 03-May-12 27-May-12 12-May-12 04-Jun-12 7
A10370 Curing for Slab 3 28-May-12 30-May-12 03-Nov-12 05-Nov-12 131
A10380 Strike Formwork 3 27-Jun-12 30-Jun-12 06-Nov-12 08-Nov-12 109
A10400 Pouring of Light Weight Concrete 2 01-Jul-12 02-Jul-12 03-Jan-13 05-Jan-13 153
A10430 Water Proofing Membrane for Ret. Walls 7 03-Jul-12 10-Jul-12 06-Jan-13 13-Jan-13 153
A10440 Gunited Concrete 50 mm for Ret. Walls 7 11-Jul-12 18-Jul-12 14-Jan-13 21-Jan-13 153
A10530 Backfilling 3 19-Jul-12 22-Jul-12 22-Jan-13 26-Jan-13 153
StairsStairs 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
Stairs 1Stairs 1 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
A11260 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
Stairs 2Stairs 2 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
A11270 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
Stairs 3Stairs 3 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
A11280 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148
1st Floor Slab1st Floor Slab 73 28-May-12 23-Aug-12 05-Jun-12 25-Feb-13 153
Walls and CWalls and Columns 9 28-May-12 06-Jun-12 05-Jun-12 14-Jun-12 7
A10460 Core Wall RC Works 6 28-May-12 03-Jun-12 05-Jun-12 11-Jun-12 7
A10470 Columns RC Works 9 28-May-12 06-Jun-12 05-Jun-12 14-Jun-12 7
SlabSlab 42 02-Jun-12 21-Jul-12 10-Jun-12 01-Dec-12 109
A10480 MEP Works inside Slab 5 07-Jun-12 12-Jun-12 24-Jun-12 28-Jun-12 13
A10490 1st Floor Slab RC Works 16 02-Jun-12 20-Jun-12 10-Jun-12 28-Jun-12 7
A10500 Curing for Slab 3 21-Jun-12 24-Jun-12 25-Nov-12 27-Nov-12 129
A10510 Strike Formwork 3 18-Jul-12 21-Jul-12 28-Nov-12 01-Dec-12 109
StairsStairs 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
Stairs 1Stairs 1 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
A11290 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
Stairs 2Stairs 2 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
A11300 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
Stairs 3Stairs 3 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
A11310 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
Stairs 4Stairs 4 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
A109210 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153
2nd Floor Sl2nd Floor Slab 64 21-Jun-12 05-Sep-12 30-Jun-12 14-Feb-13 133
Walls and CWalls and Columns 9 21-Jun-12 01-Jul-12 30-Jun-12 09-Jul-12 7
A10570 Core Wall RC Works 6 21-Jun-12 27-Jun-12 30-Jun-12 05-Jul-12 7
A10580 Columns RC Works 9 21-Jun-12 01-Jul-12 30-Jun-12 09-Jul-12 7
SlabSlab 43 26-Jun-12 14-Aug-12 04-Jul-12 28-Aug-12 10
A10590 MEP Works inside Slab 5 02-Jul-12 07-Jul-12 17-Jul-12 22-Jul-12 13
A10600 2nd Floor Slab RC Works 16 26-Jun-12 14-Jul-12 04-Jul-12 22-Jul-12 7
A10610 Curing for Slab 3 15-Jul-12 17-Jul-12 22-Aug-12 25-Aug-12 31
A10620 Strike Formwork 3 12-Aug-12 14-Aug-12 26-Aug-12 28-Aug-12 10
StairsStairs 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
Stairs 1Stairs 1 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
A11320 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
Stairs 2Stairs 2 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
A11330 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
Stairs 3Stairs 3 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
A11340 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133
3rd Floor Slab3rd Floor Slab 56 15-Jul-12 19-Sep-12 23-Jul-12 14-Feb-13 121
Walls and CWalls and Columns 9 15-Jul-12 24-Jul-12 23-Jul-12 01-Aug-12 7
A10650 Core Wall RC Works 6 15-Jul-12 21-Jul-12 23-Jul-12 29-Jul-12 7
A10660 Columns RC Works 9 15-Jul-12 24-Jul-12 23-Jul-12 01-Aug-12 7
SlabSlab 34 19-Jul-12 29-Aug-12 28-Jul-12 11-Sep-12 11
A10670 MEP Works inside Slab 5 22-Jul-12 26-Jul-12 01-Aug-12 06-Aug-12 9
A10680 3rd Floor Slab RC Works 9 19-Jul-12 29-Jul-12 28-Jul-12 06-Aug-12 7
A10690 Curing for Slab 3 30-Jul-12 01-Aug-12 05-Sep-12 08-Sep-12 30
A10700 Strike Formwork 3 27-Aug-12 29-Aug-12 09-Sep-12 11-Sep-12 11
StairsStairs 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
Stairs 1Stairs 1 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
A11350 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
Stairs 2Stairs 2 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
A11360 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
Stairs 3Stairs 3 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
A11370 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121
4th Floor Slab4th Floor Slab 57 30-Jul-12 06-Oct-12 07-Aug-12 12-Feb-13 105
Walls and CWalls and Columns 9 30-Jul-12 08-Aug-12 07-Aug-12 16-Aug-12 7
A10730 Core Wall RC Works 6 30-Jul-12 05-Aug-12 07-Aug-12 13-Aug-12 7
A10740 Columns RC Works 9 30-Jul-12 08-Aug-12 07-Aug-12 16-Aug-12 7
SlabSlab 33 04-Aug-12 12-Sep-12 12-Aug-12 26-Sep-12 12
A10750 MEP Works inside Slab 5 08-Aug-12 13-Aug-12 16-Aug-12 23-Aug-12 7
A10760 4th Slab RC Works 9 04-Aug-12 13-Aug-12 12-Aug-12 23-Aug-12 7
A10770 Curing for Slab 3 14-Aug-12 16-Aug-12 20-Sep-12 23-Sep-12 30
A10780 Strike Formwork 3 10-Sep-12 12-Sep-12 24-Sep-12 26-Sep-12 12
StairsStairs 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
Stairs 1Stairs 1 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
A11380 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
Stairs 2Stairs 2 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
A11390 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
Stairs 3Stairs 3 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
A11400 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105
5th Floor Slab5th Floor Slab 56 14-Aug-12 20-Oct-12 25-Aug-12 11-Feb-13 92
Walls and CWalls and Columns 9 14-Aug-12 26-Aug-12 25-Aug-12 03-Sep-12 7
A10810 Core Wall RC Works 6 14-Aug-12 22-Aug-12 25-Aug-12 30-Aug-12 7
A10820 Columns RC Works 9 14-Aug-12 26-Aug-12 25-Aug-12 03-Sep-12 7
SlabSlab 35 18-Aug-12 29-Sep-12 28-Aug-12 13-Oct-12 12
A10830 MEP Works inside Slab 5 23-Aug-12 28-Aug-12 02-Sep-12 06-Sep-12 8
A10840 5th Slab RC Works 9 18-Aug-12 29-Aug-12 28-Aug-12 06-Sep-12 7
A10850 Curing for Slab 3 30-Aug-12 02-Sep-12 07-Oct-12 09-Oct-12 32
A10860 Strike Formwork 3 26-Sep-12 29-Sep-12 10-Oct-12 13-Oct-12 12
StairsStairs 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
Stairs 1Stairs 1 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
A11410 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
Stairs 2Stairs 2 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
A11420 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
Stairs 3Stairs 3 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
A11430 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92
6th Floor Slab6th Floor Slab 57 30-Aug-12 06-Nov-12 08-Sep-12 13-Feb-13 81
Walls and CWalls and Columns 9 30-Aug-12 09-Sep-12 08-Sep-12 17-Sep-12 7
A10890 Core Wall RC Works 6 30-Aug-12 05-Sep-12 08-Sep-12 13-Sep-12 7
A10900 Columns RC Works 9 30-Aug-12 09-Sep-12 08-Sep-12 17-Sep-12 7
SlabSlab 34 04-Sep-12 13-Oct-12 12-Sep-12 28-Oct-12 11
A10910 MEP Works inside Slab 5 09-Sep-12 13-Sep-12 17-Sep-12 22-Sep-12 7
A10920 6th Slab RC Works 9 04-Sep-12 13-Sep-12 12-Sep-12 22-Sep-12 7
A10930 Curing for Slab 3 15-Sep-12 17-Sep-12 20-Oct-12 22-Oct-12 30
A10940 Strike Formwork 3 10-Oct-12 13-Oct-12 23-Oct-12 28-Oct-12 11
StairsStairs 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
Stairs 1Stairs 1 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Core Wall RC Works
Retaining Wall 250 mm RC Works
MEP Works inside Slab
Ground Floor Slab RC Works
Curing for Slab
Strike Formwork
Pouring of Light Weight Concrete
Water Proofing Membrane for Ret. Walls
Gunited Concrete 50 mm for Ret. Walls
Backfilling
Stairs RC Works (1st Basement toGround)
Stairs RC Works (1st Basement toGround)
Stairs RC Works (1st Basement toGround)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
1st Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Stairs RC Works (Ground to 1st floor)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
2nd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (1st to 2nd)
Stairs RC Works (1st to 2nd)
Stairs RC Works (1st to 2nd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
3rd Floor Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (2nd to 3rd)
Stairs RC Works (2nd to 3rd)
Stairs RC Works (2nd to 3rd)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
4th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (3rd to 4th)
Stairs RC Works (3rd to 4th)
Stairs RC Works (3rd to 4th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
5th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (4th to 5th)
Stairs RC Works (4th to 5th)
Stairs RC Works (4th to 5th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
6th Slab RC Works
Curing for Slab
Strike Formwork
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 19 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A11440 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
Stairs 2Stairs 2 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
A11450 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
Stairs 3Stairs 3 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
A11460 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81
7th Floor Slab7th Floor Slab 57 15-Sep-12 22-Nov-12 23-Sep-12 06-Feb-13 62
Walls and CWalls and Columns 9 15-Sep-12 24-Sep-12 23-Sep-12 02-Oct-12 7
A10970 Core Wall RC Works 6 15-Sep-12 20-Sep-12 23-Sep-12 29-Sep-12 7
A10980 Columns RC Works 9 15-Sep-12 24-Sep-12 23-Sep-12 02-Oct-12 7
SlabSlab 34 19-Sep-12 30-Oct-12 27-Sep-12 10-Nov-12 9
A10990 MEP Works inside Slab 5 24-Sep-12 29-Sep-12 02-Oct-12 07-Oct-12 7
A11000 7th Slab RC Works 9 19-Sep-12 29-Sep-12 27-Sep-12 07-Oct-12 7
A11010 Curing for Slab 3 30-Sep-12 02-Oct-12 04-Nov-12 06-Nov-12 28
A11020 Strike Formwork 3 28-Oct-12 30-Oct-12 07-Nov-12 10-Nov-12 9
StairsStairs 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
Stairs 1Stairs 1 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
A11470 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
Stairs 2Stairs 2 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
A11480 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
Stairs 3Stairs 3 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
A11490 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62
Roof Floor SlRoof Floor Slab 57 30-Sep-12 09-Dec-12 08-Oct-12 05-Jun-13 151
Walls and CWalls and Columns 9 30-Sep-12 09-Oct-12 08-Oct-12 20-Oct-12 9
A11050 Core Wall RC Works 6 30-Sep-12 06-Oct-12 08-Oct-12 14-Oct-12 7
A11060 Columns RC Works 9 30-Sep-12 09-Oct-12 10-Oct-12 20-Oct-12 9
SlabSlab 34 04-Oct-12 14-Nov-12 15-Oct-12 26-Nov-12 9
A11070 MEP Works inside Slab 5 09-Oct-12 14-Oct-12 20-Oct-12 24-Oct-12 9
A11080 Roof Floor Slab RC Works 9 04-Oct-12 14-Oct-12 15-Oct-12 24-Oct-12 9
A11090 Curing for Slab 3 15-Oct-12 17-Oct-12 08-Nov-12 11-Nov-12 19
A11100 Strike Formwork 3 12-Nov-12 14-Nov-12 24-Nov-12 26-Nov-12 9
ParapetsParapets 10 07-Nov-12 19-Nov-12 26-May-13 05-Jun-13 167
A104160 Parapets RC Works 10 07-Nov-12 19-Nov-12 26-May-13 05-Jun-13 167
Chillers FouChillers Foundation 5 18-Oct-12 23-Oct-12 12-Nov-12 18-Nov-12 19
A117110 Chillers Foundations RC Works 5 18-Oct-12 23-Oct-12 12-Nov-12 18-Nov-12 19
StairsStairs 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
Stairs 1Stairs 1 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
A109230 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
Stairs 2Stairs 2 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
A109240 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
Stairs 3Stairs 3 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
A111200 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
Stairs 4Stairs 4 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
A113370 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54
Upper Roof LUpper Roof Level 44 15-Oct-12 09-Dec-12 29-Oct-12 25-Feb-13 65
ColumnsColumns 9 15-Oct-12 24-Oct-12 29-Oct-12 07-Nov-12 10
A11140 Columns RC Works 9 15-Oct-12 24-Oct-12 29-Oct-12 07-Nov-12 10
SlabsSlabs 34 20-Oct-12 01-Dec-12 03-Nov-12 04-Feb-13 53
A11150 MEP Works inside Slab 4 24-Oct-12 30-Oct-12 07-Nov-12 11-Nov-12 10
A11160 Upper Roof Level Slab RC Works 8 20-Oct-12 30-Oct-12 03-Nov-12 11-Nov-12 10
A11170 Curing for Slab 3 31-Oct-12 03-Nov-12 02-Feb-13 04-Feb-13 76
A11180 Strike Formwork 3 28-Nov-12 01-Dec-12 11-Dec-12 13-Dec-12 10
StairsStairs 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65
Stairs 4Stairs 4 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65
A109260 Stairs RC Works (Roof to Upper Roof) 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65
ArchitecturaArchitectural & MEP Package 431 14-Apr-12 10-Sep-13 28-Jul-12 02-Oct-13 19
Hotel AparteHotel Apartements (Block A) 429 14-Apr-12 08-Sep-13 28-Jul-12 02-Oct-13 21
2nd Basemen2nd Basement Floor 258 14-Apr-12 18-Feb-13 27-Sep-12 25-Apr-13 57
Public AreaPublic Area 258 14-Apr-12 18-Feb-13 27-Sep-12 25-Apr-13 57
Parking ArParking Area 247 26-Apr-12 18-Feb-13 15-Oct-12 25-Apr-13 57
FinishingFinishing Works 247 26-Apr-12 18-Feb-13 15-Oct-12 25-Apr-13 57
Wet WorWet Works 193 26-Apr-12 15-Dec-12 15-Oct-12 21-Feb-13 57
A47830 Plaster Works 5 26-Apr-12 01-May-12 15-Oct-12 20-Oct-12 144
A47850 1st Coat Paint 12 01-Dec-12 15-Dec-12 09-Feb-13 21-Feb-13 57
Traffic DTraffic Deck Coating 42 16-Dec-12 04-Feb-13 23-Feb-13 25-Apr-13 69
A47630 Installation of Kerbs 8 16-Dec-12 24-Dec-12 23-Feb-13 03-Mar-13 57
A47620 Installation of Interlocking Tiles 8 25-Dec-12 03-Jan-13 04-Mar-13 12-Mar-13 57
A47550 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 13-Mar-13 21-Mar-13 57
A47560 Application of 1st Coat 7 10-Jan-13 17-Jan-13 19-Mar-13 26-Mar-13 57
A47600 Application of Final Coat 7 19-Jan-13 27-Jan-13 27-Mar-13 03-Apr-13 57
A47580 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 04-Apr-13 11-Apr-13 57
A47610 Installation of Speed Hump 7 28-Jan-13 04-Feb-13 18-Apr-13 25-Apr-13 69
Final StaFinal Stage Finishes 12 05-Feb-13 18-Feb-13 13-Apr-13 25-Apr-13 57
A47860 Final Coat Paint 5 05-Feb-13 10-Feb-13 13-Apr-13 17-Apr-13 57
A47930 Installation of Sinages 7 11-Feb-13 18-Feb-13 18-Apr-13 25-Apr-13 57
MEP WorkMEP Works 234 26-Apr-12 03-Feb-13 02-Jan-13 24-Apr-13 69
HVACHVAC 10 04-Jul-12 15-Jul-12 28-Jan-13 07-Feb-13 170
A47970 Chilled Water Pipe Installation & Insulation 7 04-Jul-12 11-Jul-12 28-Jan-13 04-Feb-13 170
A47980 Condensate Pipe Installation 7 04-Jul-12 11-Jul-12 28-Jan-13 04-Feb-13 170
A47990 Installation of Induction Fan 3 12-Jul-12 15-Jul-12 05-Feb-13 07-Feb-13 170
ElectricalElectrical 173 06-May-12 29-Nov-12 03-Jan-13 07-Feb-13 57
A48000 Installation of Cable Trays 10 06-May-12 16-May-12 03-Jan-13 14-Jan-13 200
A47940 Installation of Bus Bars 15 31-Oct-12 18-Nov-12 09-Jan-13 27-Jan-13 57
A48010 Cable Pulling 10 06-Nov-12 18-Nov-12 15-Jan-13 27-Jan-13 57
A47920 Installation of Lighting Fittings 10 19-Nov-12 29-Nov-12 28-Jan-13 07-Feb-13 57
PlumbingPlumbing 12 26-Apr-12 09-May-12 26-Jan-13 07-Feb-13 226
A48060 H/L Hot&Cold Water Pipe Installation 7 26-Apr-12 03-May-12 26-Jan-13 02-Feb-13 226
A48070 Water Pipes Testing 5 05-May-12 09-May-12 03-Feb-13 07-Feb-13 226
A48080 Floor Drain Fixing 4 06-May-12 09-May-12 04-Feb-13 07-Feb-13 226
Fire FighFire Fighting 195 11-Jun-12 03-Feb-13 02-Jan-13 24-Apr-13 69
A48040 Fire Fighting Pipe 8 11-Jun-12 20-Jun-12 02-Jan-13 10-Jan-13 168
A48030 Hydro Static Test for Pipes 5 21-Jun-12 26-Jun-12 17-Jan-13 22-Jan-13 173
A48020 Sprinkler Fixing 7 27-Jun-12 04-Jul-12 23-Jan-13 31-Jan-13 173
A47950 Fire Alarm Devices 6 05-Jul-12 11-Jul-12 02-Feb-13 07-Feb-13 173
A47960 Installation of Fire Hose Cabinet & Landing Valve 6 28-Jan-13 03-Feb-13 18-Apr-13 24-Apr-13 69
RampRamp 117 20-Sep-12 10-Feb-13 15-Oct-12 25-Apr-13 64
FinishingFinishing Works 117 20-Sep-12 10-Feb-13 15-Oct-12 25-Apr-13 64
A8730 Install Handrail 7 20-Sep-12 27-Sep-12 15-Oct-12 22-Oct-12 21
A8720 1st Coat Paint 10 04-Dec-12 15-Dec-12 11-Mar-13 21-Mar-13 81
A1136 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 23-Mar-13 31-Mar-13 65
A1138 Application of 1st Coat 5 14-Jan-13 19-Jan-13 01-Apr-13 06-Apr-13 65
A1134 Application of Final Coat 5 21-Jan-13 27-Jan-13 07-Apr-13 11-Apr-13 64
A1132 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 13-Apr-13 20-Apr-13 64
A8760 Final Coat Paint 5 05-Feb-13 10-Feb-13 21-Apr-13 25-Apr-13 64
Lift LobbyLift Lobby 203 14-Apr-12 13-Dec-12 02-Oct-12 25-Apr-13 112
FinishingFinishing Works 203 14-Apr-12 13-Dec-12 02-Oct-12 25-Apr-13 112
Wet WorWet Works 90 14-Apr-12 28-Jul-12 02-Oct-12 07-Feb-13 159
A48140 Block Works 4 14-Apr-12 17-Apr-12 02-Oct-12 06-Oct-12 144
A48090 Plaster Works 7 17-May-12 24-May-12 14-Jan-13 21-Jan-13 199
A48110 Installation of Suspended Ceiling Grid 5 16-Jul-12 21-Jul-12 27-Jan-13 31-Jan-13 159
A48100 1st Coat Paint 6 22-Jul-12 28-Jul-12 02-Feb-13 07-Feb-13 159
Fisrt StaFisrt Stage Finishes 23 29-Jul-12 26-Aug-12 19-Feb-13 28-Feb-13 154
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Stairs RC Works (5th to 6th)
Stairs RC Works (5th to 6th)
Stairs RC Works (5th to 6th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
7th Slab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (6th to 7th)
Stairs RC Works (6th to 7th)
Stairs RC Works (6th to 7th)
Core Wall RC Works
Columns RC Works
MEP Works inside Slab
Roof Floor Slab RC Works
Curing for Slab
Strike Formwork
Parapets RC Works
Chillers Foundations RC Works
Stairs RC Works (7th to Roof)
Stairs RC Works (7th to Roof)
Stairs RC Works (7th to Roof)
Stairs RC Works (7th to Roof)
Columns RC Works
MEP Works inside Slab
Upper Roof LevelSlab RC Works
Curing for Slab
Strike Formwork
Stairs RC Works (Roof to Upper Roof)
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Installation of Induction Fan
Installation of Cable Trays
Installation of Bus Bars
Cable Pulling
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Floor Drain Fixing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Hose Cabinet & Landing Valve
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 20 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A48120 Suspended Ceiling Tiles 5 29-Jul-12 02-Aug-12 19-Feb-13 24-Feb-13 168
A48380 MDF for Lift Lobby Wall 7 14-Aug-12 23-Aug-12 19-Feb-13 26-Feb-13 154
A48360 Screed Works 2 25-Aug-12 26-Aug-12 27-Feb-13 28-Feb-13 154
Second SSecond Stage Finishes 8 27-Aug-12 04-Sep-12 02-Mar-13 10-Mar-13 154
A48370 Wall Tiles Work 5 27-Aug-12 01-Sep-12 02-Mar-13 06-Mar-13 154
A48400 Floor Tiles Work 3 02-Sep-12 04-Sep-12 07-Mar-13 10-Mar-13 154
Final StaFinal Stage Finishes 82 05-Sep-12 13-Dec-12 11-Mar-13 25-Apr-13 112
A48130 Installation of Doors 2 05-Sep-12 06-Sep-12 11-Mar-13 12-Mar-13 154
A48150 Doors Ironmongery 2 15-Sep-12 16-Sep-12 17-Apr-13 18-Apr-13 178
A48410 Final Coat Paint 3 09-Dec-12 11-Dec-12 06-Apr-13 08-Apr-13 99
A48350 Installation of Sinages 2 12-Dec-12 13-Dec-12 24-Apr-13 25-Apr-13 112
MEP WorkMEP Works 194 18-Apr-12 08-Dec-12 26-Nov-12 04-Apr-13 99
HVACHVAC 37 24-Jun-12 05-Aug-12 16-Jan-13 05-Mar-13 174
A48160 Duct Installation & Insulation 5 24-Jun-12 28-Jun-12 16-Jan-13 21-Jan-13 170
A48180 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 16-Jan-13 21-Jan-13 170
A48170 Chilled Water Pipe Installation & Insulation 5 28-Jun-12 03-Jul-12 16-Jan-13 21-Jan-13 166
A48190 FCU Installation 3 04-Jul-12 07-Jul-12 22-Jan-13 26-Jan-13 166
A48200 Air-Outlet Installation 2 04-Aug-12 05-Aug-12 04-Mar-13 05-Mar-13 174
ElectricalElectrical 194 18-Apr-12 08-Dec-12 26-Nov-12 05-Mar-13 73
A48210 Install Conduits in Wall 3 18-Apr-12 21-Apr-12 26-Nov-12 28-Nov-12 184
A48220 Install Cable Trays & Trunking 3 06-May-12 08-May-12 16-Jan-13 19-Jan-13 211
A48260 Cable Laying for Low Current System 5 12-May-12 16-May-12 27-Jan-13 31-Jan-13 214
A48270 Cable Laying for Power 5 12-May-12 16-May-12 27-Jan-13 31-Jan-13 214
A48230 Wiring for Lighting & Power 3 26-May-12 28-May-12 22-Jan-13 26-Jan-13 199
A48240 Wiring for Low Current System 3 26-May-12 28-May-12 22-Jan-13 26-Jan-13 199
A48290 Installation of Lighting Fittings 6 01-Dec-12 08-Dec-12 27-Feb-13 05-Mar-13 73
Fire FighFire Fighting 44 21-Jun-12 11-Aug-12 12-Jan-13 04-Apr-13 195
A48340 Fire Fighting Pipe 7 21-Jun-12 28-Jun-12 12-Jan-13 19-Jan-13 168
A48330 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 20-Jan-13 26-Jan-13 168
A48390 Fire Alarm Devices 5 04-Aug-12 08-Aug-12 31-Mar-13 04-Apr-13 197
A48320 Sprinkler Fixing 7 04-Aug-12 11-Aug-12 26-Feb-13 05-Mar-13 169
GSM RoomGSM Rooms 202 18-Apr-12 17-Dec-12 07-Oct-12 25-Apr-13 109
FinishingFinishing Works 202 18-Apr-12 17-Dec-12 07-Oct-12 25-Apr-13 109
Wet WorWet Works 42 18-Apr-12 05-Jun-12 07-Oct-12 03-Mar-13 223
A47420 Block Works 5 18-Apr-12 23-Apr-12 07-Oct-12 11-Oct-12 144
A47380 Installation of Doors& Windows Sub-frame 2 02-May-12 03-May-12 02-Mar-13 03-Mar-13 251
A47370 Plaster Works 8 02-May-12 10-May-12 06-Dec-12 15-Dec-12 180
A47390 1st Coat Paint 7 29-May-12 05-Jun-12 03-Jan-13 10-Jan-13 180
Fisrt StaFisrt Stage Finishes 85 19-Jun-12 27-Sep-12 09-Mar-13 21-Apr-13 170
A47410 Installation of Doors 2 19-Jun-12 20-Jun-12 09-Mar-13 10-Mar-13 217
A47430 Doors Ironmongery 2 17-Sep-12 18-Sep-12 20-Apr-13 21-Apr-13 178
A47480 Epoxy Paint Works 2 26-Sep-12 27-Sep-12 11-Mar-13 12-Mar-13 136
Second SSecond Stage Finishes 3 12-Dec-12 15-Dec-12 09-Apr-13 11-Apr-13 99
A47400 Final Coat Paint 3 12-Dec-12 15-Dec-12 09-Apr-13 11-Apr-13 99
Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109
A47470 Installation of Sinages 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109
MEP WorkMEP Works 130 24-Apr-12 25-Sep-12 29-Nov-12 10-Mar-13 136
HVACHVAC 21 24-Jun-12 17-Jul-12 12-Jan-13 03-Mar-13 188
A47510 Chilled Water Pipe Installation & Insulation 4 24-Jun-12 27-Jun-12 12-Jan-13 15-Jan-13 166
A47520 Condensate Pipe Installation 4 30-Jun-12 03-Jul-12 22-Jan-13 27-Jan-13 170
A47530 FCU Installation 4 08-Jul-12 11-Jul-12 21-Feb-13 25-Feb-13 188
A47540 Air-Outlet Installation 5 12-Jul-12 17-Jul-12 26-Feb-13 03-Mar-13 188
ElectricalElectrical 130 24-Apr-12 25-Sep-12 29-Nov-12 05-Mar-13 132
A47440 Install Conduits in Wall 5 24-Apr-12 29-Apr-12 29-Nov-12 05-Dec-12 182
A47450 Wiring for Lighting & Power 5 12-May-12 16-May-12 27-Dec-12 02-Jan-13 190
A47460 Installation of Lighting Fittings 5 06-Jun-12 11-Jun-12 16-Jan-13 21-Jan-13 184
A47500 Installation of GSM System 45 02-Aug-12 25-Sep-12 12-Jan-13 05-Mar-13 132
Fire FighFire Fighting 5 12-Jul-12 17-Jul-12 05-Mar-13 10-Mar-13 194
A47490 Fire Alarm Devices 5 12-Jul-12 17-Jul-12 05-Mar-13 10-Mar-13 194
MechanicaMechanical Rooms 147 24-Apr-12 15-Oct-12 13-Oct-12 25-Apr-13 159
FinishingFinishing Works 147 24-Apr-12 15-Oct-12 13-Oct-12 25-Apr-13 159
Wet WorWet Works 30 24-Apr-12 28-May-12 13-Oct-12 05-Mar-13 232
A47230 Block Works 2 24-Apr-12 25-Apr-12 13-Oct-12 14-Oct-12 144
A47190 Installation of Doors& Windows Sub-frame 2 12-May-12 13-May-12 04-Mar-13 05-Mar-13 245
A47180 Plaster Works 5 12-May-12 16-May-12 16-Dec-12 20-Dec-12 180
A47200 1st Coat Paint 6 22-May-12 28-May-12 26-Dec-12 02-Jan-13 180
Fisrt StaFisrt Stage Finishes 81 16-Jun-12 20-Sep-12 06-Mar-13 23-Apr-13 178
A47220 Installation of Doors 2 16-Jun-12 18-Jun-12 06-Mar-13 07-Mar-13 217
A47290 Epoxy Paint Works 2 21-Jun-12 23-Jun-12 09-Mar-13 10-Mar-13 215
A47240 Doors Ironmongery 2 19-Sep-12 20-Sep-12 22-Apr-13 23-Apr-13 178
Second SSecond Stage Finishes 2 24-Jun-12 25-Jun-12 03-Apr-13 04-Apr-13 235
A47210 Final Coat Paint 2 24-Jun-12 25-Jun-12 03-Apr-13 04-Apr-13 235
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
A47280 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
MEP WorkMEP Works 44 30-Apr-12 20-Jun-12 11-Dec-12 05-Mar-13 213
HVACHVAC 15 29-May-12 14-Jun-12 05-Jan-13 21-Jan-13 181
A47320 Shaft Works 15 29-May-12 14-Jun-12 05-Jan-13 21-Jan-13 181
ElectricalElectrical 44 30-Apr-12 20-Jun-12 11-Dec-12 27-Jan-13 181
A47250 Install Conduits in Wall 4 30-Apr-12 03-May-12 11-Dec-12 15-Dec-12 186
A47260 Wiring for Lighting & Power 4 17-May-12 21-May-12 22-Dec-12 25-Dec-12 180
A47270 Installation of Lighting Fittings 4 16-Jun-12 20-Jun-12 22-Jan-13 27-Jan-13 181
PlumbingPlumbing 3 29-May-12 31-May-12 03-Mar-13 05-Mar-13 229
A47360 Floor Drain Fixing 3 29-May-12 31-May-12 03-Mar-13 05-Mar-13 229
StaircaseStaircase 144 29-May-12 19-Nov-12 27-Sep-12 25-Apr-13 132
Stair 1Stair 1 144 29-May-12 19-Nov-12 27-Sep-12 25-Apr-13 132
A107930 Floor Screed 3 29-May-12 31-May-12 27-Sep-12 30-Sep-12 101
A107940 Install Handrails 4 29-Sep-12 02-Oct-12 23-Oct-12 29-Oct-12 21
A107950 Ceiling 1st Coat Paint 7 03-Oct-12 10-Oct-12 19-Nov-12 26-Nov-12 37
A107960 Wall 1st Coat Paint 7 11-Oct-12 18-Oct-12 27-Nov-12 05-Dec-12 37
A107970 Install Granite/Terrazo 12 20-Oct-12 04-Nov-12 20-Dec-12 03-Jan-13 49
A107980 Final Coat Paint 12 05-Nov-12 19-Nov-12 13-Apr-13 25-Apr-13 132
1st Basemen1st Basement Floor 235 10-May-12 18-Feb-13 02-Aug-12 25-Apr-13 57
Public AreaPublic Area 235 10-May-12 18-Feb-13 02-Aug-12 25-Apr-13 57
Parking ArParking Area 200 14-Jun-12 12-Feb-13 30-Oct-12 25-Apr-13 62
FinishingFinishing Works 158 04-Aug-12 12-Feb-13 30-Oct-12 25-Apr-13 62
Wet WorWet Works 109 04-Aug-12 15-Dec-12 30-Oct-12 21-Feb-13 57
A50110 Plaster Works 5 04-Aug-12 08-Aug-12 30-Oct-12 04-Nov-12 71
A50120 1st Coat Paint 12 01-Dec-12 15-Dec-12 09-Feb-13 21-Feb-13 57
Traffic DTraffic Deck Coating 49 16-Dec-12 12-Feb-13 23-Feb-13 25-Apr-13 62
A115650 Installation of Kerbs 8 16-Dec-12 24-Dec-12 23-Feb-13 03-Mar-13 57
A115660 Installation of Interlocking Tiles 8 25-Dec-12 03-Jan-13 04-Mar-13 12-Mar-13 57
A50050 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 13-Mar-13 21-Mar-13 57
A50060 Application of 1st Coat 7 10-Jan-13 17-Jan-13 19-Mar-13 26-Mar-13 57
A50100 Application of Final Coat 7 19-Jan-13 27-Jan-13 27-Mar-13 03-Apr-13 57
A50080 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 04-Apr-13 11-Apr-13 57
A115670 Installation of Speed Hump 7 05-Feb-13 12-Feb-13 18-Apr-13 25-Apr-13 62
Final StaFinal Stage Finishes 7 05-Feb-13 12-Feb-13 13-Apr-13 25-Apr-13 62
A50130 Final Coat Paint 5 05-Feb-13 10-Feb-13 13-Apr-13 17-Apr-13 57
A50150 Installation of Sinages 2 11-Feb-13 12-Feb-13 24-Apr-13 25-Apr-13 62
MEP WorkMEP Works 139 14-Jun-12 29-Nov-12 03-Jan-13 07-Feb-13 57
HVACHVAC 28 24-Jun-12 25-Jul-12 28-Jan-13 07-Feb-13 161
A50170 Chilled Water Pipe Installation & Insulation 7 24-Jun-12 01-Jul-12 28-Jan-13 04-Feb-13 179
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Condensate Pipe Installation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of GSM System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Shaft Works
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Floor Drain Fixing
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 21 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A50180 Condensate Pipe Installation 7 15-Jul-12 22-Jul-12 28-Jan-13 04-Feb-13 161
A50250 Installation of Induction Fans 3 23-Jul-12 25-Jul-12 05-Feb-13 07-Feb-13 161
ElectricalElectrical 139 14-Jun-12 29-Nov-12 03-Jan-13 07-Feb-13 57
A115680 Installation of Cable Trays 10 14-Jun-12 26-Jun-12 03-Jan-13 14-Jan-13 166
A115690 Installation of Bus Bars 15 31-Oct-12 18-Nov-12 09-Jan-13 27-Jan-13 57
A115700 Cable Pulling 10 06-Nov-12 18-Nov-12 15-Jan-13 27-Jan-13 57
A50140 Installation of Lighting Fittings 10 19-Nov-12 29-Nov-12 28-Jan-13 07-Feb-13 57
PlumbingPlumbing 10 14-Jun-12 26-Jun-12 28-Jan-13 07-Feb-13 186
A50220 H/L Hot&Cold Water Pipe Installation 7 14-Jun-12 23-Jun-12 28-Jan-13 04-Feb-13 186
A50240 Floor Drain Fixing 7 14-Jun-12 23-Jun-12 31-Jan-13 07-Feb-13 189
A50260 H/L Drainage Pipes Installation 7 14-Jun-12 23-Jun-12 28-Jan-13 04-Feb-13 186
A50230 Water Pipes Testing 3 24-Jun-12 26-Jun-12 05-Feb-13 07-Feb-13 186
A50270 Drainage&Water Pipes Testing 3 24-Jun-12 26-Jun-12 05-Feb-13 07-Feb-13 186
Fire FighFire Fighting 61 20-Jun-12 01-Sep-12 08-Jan-13 07-Feb-13 131
A50210 Fire Fighting Pipe 8 20-Jun-12 28-Jun-12 08-Jan-13 16-Jan-13 166
A50200 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 17-Jan-13 22-Jan-13 166
A50190 Sprinkler Fixing 7 05-Jul-12 12-Jul-12 23-Jan-13 31-Jan-13 166
A115200 Installation of Fire Hose Cabinet & Landing Valve 6 29-Jul-12 04-Aug-12 02-Feb-13 07-Feb-13 153
A50160 Fire Alarm Devices 6 26-Aug-12 01-Sep-12 02-Feb-13 07-Feb-13 131
RampRamp 113 03-Oct-12 18-Feb-13 30-Oct-12 25-Apr-13 57
FinishingFinishing Works 113 03-Oct-12 18-Feb-13 30-Oct-12 25-Apr-13 57
A113690 Install Handrail 7 03-Oct-12 10-Oct-12 30-Oct-12 06-Nov-12 21
A113700 1st Coat Paint 10 16-Dec-12 26-Dec-12 09-Mar-13 19-Mar-13 69
A113710 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 20-Mar-13 28-Mar-13 63
A113720 Application of 1st Coat 5 14-Jan-13 19-Jan-13 30-Mar-13 03-Apr-13 63
A113740 Application of Final Coat 5 21-Jan-13 27-Jan-13 04-Apr-13 09-Apr-13 62
A113760 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 10-Apr-13 17-Apr-13 62
A113770 Final Coat Paint 7 11-Feb-13 18-Feb-13 18-Apr-13 25-Apr-13 57
Genset RoGenset Room 170 28-May-12 19-Dec-12 25-Aug-12 25-Apr-13 107
FinishingFinishing Works 170 28-May-12 19-Dec-12 25-Aug-12 25-Apr-13 107
Wet WorWet Works 70 28-May-12 18-Aug-12 25-Aug-12 10-Mar-13 167
A49500 Block Works 4 28-May-12 31-May-12 25-Aug-12 28-Aug-12 73
A49460 Installation of Doors& Windows Sub-frame 1 25-Jul-12 25-Jul-12 10-Mar-13 10-Mar-13 187
A49450 Plaster Works 8 25-Jul-12 02-Aug-12 18-Oct-12 29-Oct-12 71
A49470 1st Coat Paint 9 08-Aug-12 18-Aug-12 08-Jan-13 17-Jan-13 124
Fisrt StaFisrt Stage Finishes 68 25-Sep-12 17-Dec-12 26-Feb-13 23-Apr-13 107
A49560 Epoxy Paint Works 2 25-Sep-12 26-Sep-12 26-Feb-13 27-Feb-13 126
A49490 Installation of Doors 2 15-Dec-12 16-Dec-12 11-Mar-13 12-Mar-13 72
A49510 Doors Ironmongery 2 16-Dec-12 17-Dec-12 22-Apr-13 23-Apr-13 107
Second SSecond Stage Finishes 4 27-Sep-12 01-Oct-12 02-Apr-13 06-Apr-13 154
A49480 Final Coat Paint 4 27-Sep-12 01-Oct-12 02-Apr-13 06-Apr-13 154
Final StaFinal Stage Finishes 2 18-Dec-12 19-Dec-12 24-Apr-13 25-Apr-13 107
A49550 Installation of Sinages 2 18-Dec-12 19-Dec-12 24-Apr-13 25-Apr-13 107
MEP WorkMEP Works 94 04-Jun-12 24-Sep-12 29-Aug-12 06-Apr-13 160
HVACHVAC 40 02-Jul-12 16-Aug-12 20-Jan-13 25-Feb-13 157
A49580 Duct Installation & Insulation 7 02-Jul-12 09-Jul-12 20-Jan-13 28-Jan-13 166
A49620 Air-Outlet Installation 7 09-Aug-12 16-Aug-12 18-Feb-13 25-Feb-13 157
ElectricalElectrical 94 04-Jun-12 24-Sep-12 29-Aug-12 25-Feb-13 126
A49520 Install Conduits in Wall 4 04-Jun-12 07-Jun-12 29-Aug-12 02-Sep-12 71
A49530 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 03-Jan-13 07-Jan-13 124
A49540 Installation of Lighting Fittings 7 21-Aug-12 28-Aug-12 19-Jan-13 27-Jan-13 124
A49590 Installation of Generator 30 21-Aug-12 24-Sep-12 21-Jan-13 25-Feb-13 126
Fire FighFire Fighting 14 02-Sep-12 17-Sep-12 18-Feb-13 06-Apr-13 166
A49570 Fire Alarm Devices 7 02-Sep-12 09-Sep-12 18-Feb-13 25-Feb-13 139
A49630 Installation of Fire Extingusher&Blanket 7 10-Sep-12 17-Sep-12 30-Mar-13 06-Apr-13 166
BMS RoomBMS Room 164 02-Jun-12 17-Dec-12 30-Aug-12 25-Apr-13 109
FinishingFinishing Works 164 02-Jun-12 17-Dec-12 30-Aug-12 25-Apr-13 109
Wet WorWet Works 45 02-Jun-12 24-Jul-12 30-Aug-12 06-Mar-13 185
A49690 Block Works 2 02-Jun-12 03-Jun-12 30-Aug-12 01-Sep-12 74
A49650 Installation of Doors& Windows Sub-frame 1 19-Jul-12 19-Jul-12 06-Mar-13 06-Mar-13 189
A49640 Plaster Works 5 19-Jul-12 24-Jul-12 13-Oct-12 17-Oct-12 71
Fisrt StaFisrt Stage Finishes 95 25-Jul-12 18-Nov-12 19-Nov-12 06-Mar-13 90
A49860 Installation of Suspended Ceiling Grid 2 25-Jul-12 26-Jul-12 19-Nov-12 20-Nov-12 95
A49660 1st Coat Paint 4 02-Aug-12 06-Aug-12 21-Nov-12 25-Nov-12 90
A49870 Suspended Ceiling Tiles 2 07-Aug-12 08-Aug-12 14-Jan-13 15-Jan-13 130
A49910 Screed Works 2 13-Nov-12 14-Nov-12 03-Mar-13 04-Mar-13 90
A49890 Floor Tiles Work 2 17-Nov-12 18-Nov-12 05-Mar-13 06-Mar-13 90
Second SSecond Stage Finishes 22 19-Nov-12 15-Dec-12 07-Mar-13 21-Apr-13 107
A49670 Final Coat Paint 2 19-Nov-12 20-Nov-12 07-Apr-13 08-Apr-13 116
A49680 Installation of Doors 3 11-Dec-12 13-Dec-12 07-Mar-13 10-Mar-13 72
A49700 Doors Ironmongery 4 11-Dec-12 15-Dec-12 17-Apr-13 21-Apr-13 107
Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109
A49740 Installation of Sinages 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109
MEP WorkMEP Works 130 09-Jun-12 12-Nov-12 03-Sep-12 08-Apr-13 122
HVACHVAC 50 24-Jun-12 22-Aug-12 11-Nov-12 05-Mar-13 161
A49780 Chilled Water Pipe Installation & Insulation 3 24-Jun-12 26-Jun-12 11-Nov-12 13-Nov-12 116
A49790 Condensate Pipe Installation 3 30-Jun-12 02-Jul-12 11-Nov-12 13-Nov-12 111
A49800 FCU Installation 3 03-Jul-12 05-Jul-12 14-Nov-12 18-Nov-12 111
A49810 Air-Outlet Installation 3 18-Aug-12 22-Aug-12 03-Mar-13 05-Mar-13 161
ElectricalElectrical 130 09-Jun-12 12-Nov-12 03-Sep-12 02-Mar-13 90
A49710 Install Conduits in Wall 2 09-Jun-12 10-Jun-12 03-Sep-12 04-Sep-12 71
A49720 Wiring for Lighting & Power 2 25-Jul-12 26-Jul-12 19-Nov-12 20-Nov-12 95
A49730 Installation of Lighting Fittings 2 13-Aug-12 14-Aug-12 16-Jan-13 17-Jan-13 127
A49760 Installation of BMS System 80 07-Aug-12 12-Nov-12 26-Nov-12 02-Mar-13 90
Fire FighFire Fighting 12 18-Aug-12 02-Sep-12 27-Jan-13 08-Apr-13 181
A49750 Fire Alarm Devices 5 18-Aug-12 25-Aug-12 27-Jan-13 31-Jan-13 131
A49820 Installation of Fire Extinguisher&Blanket 7 26-Aug-12 02-Sep-12 01-Apr-13 08-Apr-13 181
CBS RoomCBS Room 158 04-Jun-12 12-Dec-12 02-Sep-12 25-Apr-13 113
FinishingFinishing Works 158 04-Jun-12 12-Dec-12 02-Sep-12 25-Apr-13 113
Wet WorWet Works 42 04-Jun-12 23-Jul-12 02-Sep-12 04-Mar-13 184
A48470 Block Works 3 04-Jun-12 06-Jun-12 02-Sep-12 04-Sep-12 74
A48420 Plaster Works 6 04-Jul-12 10-Jul-12 27-Sep-12 03-Oct-12 71
A48430 Installation of Doors& Windows Sub-frame 2 14-Jul-12 15-Jul-12 03-Mar-13 04-Mar-13 191
A48440 1st Coat Paint 6 17-Jul-12 23-Jul-12 05-Nov-12 11-Nov-12 91
Fisrt StaFisrt Stage Finishes 79 05-Sep-12 10-Dec-12 24-Feb-13 16-Apr-13 107
A48530 Epoxy Paint Works 2 05-Sep-12 06-Sep-12 24-Feb-13 25-Feb-13 141
A48460 Installation of Doors 2 09-Dec-12 10-Dec-12 05-Mar-13 06-Mar-13 72
A48480 Doors Ironmongery 2 09-Dec-12 10-Dec-12 15-Apr-13 16-Apr-13 107
Second SSecond Stage Finishes 2 09-Sep-12 10-Sep-12 31-Mar-13 01-Apr-13 168
A48450 Final Coat Paint 2 09-Sep-12 10-Sep-12 31-Mar-13 01-Apr-13 168
Final StaFinal Stage Finishes 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113
A48520 Installation of Sinages 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113
MEP WorkMEP Works 58 11-Jun-12 18-Aug-12 05-Sep-12 23-Feb-13 154
HVACHVAC 33 24-Jun-12 31-Jul-12 15-Jan-13 09-Feb-13 157
A48550 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 22-Jan-13 28-Jan-13 175
A48560 Condensate Pipe Installation 5 03-Jul-12 08-Jul-12 15-Jan-13 20-Jan-13 161
A48570 FCU Installation 3 09-Jul-12 11-Jul-12 29-Jan-13 31-Jan-13 167
A48580 Air-Outlet Installation 7 24-Jul-12 31-Jul-12 02-Feb-13 09-Feb-13 157
ElectricalElectrical 58 11-Jun-12 18-Aug-12 05-Sep-12 23-Feb-13 154
A48490 Install Conduits in Wall 5 11-Jun-12 16-Jun-12 05-Sep-12 10-Sep-12 71
A48500 Wiring for Lighting & Power 5 11-Jul-12 16-Jul-12 30-Oct-12 04-Nov-12 91
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Condensate Pipe Installation
Installation of Induction Fans
Installation of Cable Trays
Installation of Bus Bars
Cable Pulling
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Floor Drain Fixing
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Hose Cabinet & Landing Valve
Fire Alarm Devices
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Generator
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Final Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of BMS System
Fire Alarm Devices
Installation of Fire Extinguisher&Blanket
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 22 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A48510 Installation of Lighting Fittings 5 24-Jul-12 29-Jul-12 30-Dec-12 05-Jan-13 130
A48730 Installation of Centeral Battery System 14 02-Aug-12 18-Aug-12 07-Feb-13 23-Feb-13 154
Fire FighFire Fighting 5 12-Aug-12 16-Aug-12 20-Jan-13 26-Jan-13 131
A48540 Fire Alarm Devices 5 12-Aug-12 16-Aug-12 20-Jan-13 26-Jan-13 131
ELV RoomELV Room 154 07-Jun-12 11-Dec-12 06-Sep-12 25-Apr-13 114
FinishingFinishing Works 154 07-Jun-12 11-Dec-12 06-Sep-12 25-Apr-13 114
Wet WorWet Works 47 07-Jun-12 01-Aug-12 06-Sep-12 02-Mar-13 174
A49310 Block Works 4 07-Jun-12 11-Jun-12 06-Sep-12 10-Sep-12 75
A49270 Installation of Doors& Windows Sub-frame 2 11-Jul-12 12-Jul-12 28-Feb-13 02-Mar-13 191
A49260 Plaster Works 7 11-Jul-12 18-Jul-12 04-Oct-12 11-Oct-12 71
A49280 1st Coat Paint 7 25-Jul-12 01-Aug-12 12-Nov-12 20-Nov-12 90
Fisrt StaFisrt Stage Finishes 4 04-Dec-12 08-Dec-12 28-Feb-13 14-Apr-13 107
A49370 Epoxy Paint Works 2 04-Dec-12 05-Dec-12 28-Feb-13 02-Mar-13 72
A49300 Installation of Doors 2 06-Dec-12 08-Dec-12 03-Mar-13 04-Mar-13 72
A49320 Doors Ironmongery 2 06-Dec-12 08-Dec-12 13-Apr-13 14-Apr-13 107
Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 09-Apr-13 11-Apr-13 104
A49290 Final Coat Paint 3 06-Dec-12 09-Dec-12 09-Apr-13 11-Apr-13 104
Final StaFinal Stage Finishes 2 10-Dec-12 11-Dec-12 24-Apr-13 25-Apr-13 114
A49360 Installation of Sinages 2 10-Dec-12 11-Dec-12 24-Apr-13 25-Apr-13 114
MEP WorkMEP Works 139 18-Jun-12 03-Dec-12 11-Sep-12 11-Apr-13 109
HVACHVAC 40 24-Jun-12 08-Aug-12 21-Jan-13 17-Feb-13 157
A49400 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 30-Jan-13 04-Feb-13 181
A49410 Condensate Pipe Installation 5 09-Jul-12 14-Jul-12 21-Jan-13 27-Jan-13 161
A49390 Duct Installation & Insulation 6 10-Jul-12 16-Jul-12 29-Jan-13 04-Feb-13 166
A49420 FCU Installation 4 17-Jul-12 21-Jul-12 05-Feb-13 09-Feb-13 166
A49430 Air-Outlet Installation 7 01-Aug-12 08-Aug-12 10-Feb-13 17-Feb-13 157
ElectricalElectrical 139 18-Jun-12 03-Dec-12 11-Sep-12 27-Feb-13 72
A49330 Install Conduits in Wall 5 18-Jun-12 23-Jun-12 11-Sep-12 16-Sep-12 71
A49340 Wiring for Lighting & Power 5 19-Jul-12 24-Jul-12 06-Nov-12 11-Nov-12 90
A49350 Installation of Lighting Fittings 5 02-Aug-12 07-Aug-12 06-Jan-13 10-Jan-13 127
A114310 Installation of MATC,TV System 80 02-Aug-12 07-Nov-12 24-Nov-12 27-Feb-13 92
A49600 Installation of Access ControlSystem 80 28-Aug-12 03-Dec-12 24-Nov-12 27-Feb-13 72
Fire FighFire Fighting 15 02-Aug-12 21-Aug-12 10-Jan-13 11-Apr-13 194
A49380 Fire Alarm Devices 8 02-Aug-12 11-Aug-12 10-Jan-13 19-Jan-13 131
A49440 Installation of Fire Extinguisher&Blanket 7 12-Aug-12 21-Aug-12 04-Apr-13 11-Apr-13 194
MechanicaMechanical Rooms 105 12-Jun-12 15-Oct-12 15-Sep-12 25-Apr-13 159
FinishingFinishing Works 105 12-Jun-12 15-Oct-12 15-Sep-12 25-Apr-13 159
Wet WorWet Works 28 12-Jun-12 15-Jul-12 15-Sep-12 27-Feb-13 187
A49970 Block Works 2 12-Jun-12 13-Jun-12 15-Sep-12 16-Sep-12 78
A49930 Installation of Doors& Windows Sub-frame 2 28-Jun-12 30-Jun-12 26-Feb-13 27-Feb-13 200
A49920 Plaster Works 5 28-Jun-12 03-Jul-12 22-Sep-12 26-Sep-12 71
A49940 1st Coat Paint 6 09-Jul-12 15-Jul-12 29-Oct-12 04-Nov-12 92
Fisrt StaFisrt Stage Finishes 30 13-Aug-12 18-Sep-12 19-Feb-13 11-Apr-13 170
A50030 Epoxy Paint Works 2 13-Aug-12 14-Aug-12 19-Feb-13 20-Feb-13 155
A49960 Installation of Doors 2 08-Sep-12 09-Sep-12 28-Feb-13 02-Mar-13 143
A49980 Doors Ironmongery 2 17-Sep-12 18-Sep-12 10-Apr-13 11-Apr-13 170
Second SSecond Stage Finishes 2 15-Aug-12 16-Aug-12 25-Mar-13 26-Mar-13 182
A49950 Final Coat Paint 2 15-Aug-12 16-Aug-12 25-Mar-13 26-Mar-13 182
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
A50020 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
MEP WorkMEP Works 43 24-Jun-12 12-Aug-12 17-Sep-12 15-Jan-13 127
HVACHVAC 15 16-Jul-12 01-Aug-12 24-Dec-12 10-Jan-13 132
A50040 Shaft Works 15 16-Jul-12 01-Aug-12 24-Dec-12 10-Jan-13 132
ElectricalElectrical 43 24-Jun-12 12-Aug-12 17-Sep-12 15-Jan-13 127
A49990 Install Conduits in Wall 4 24-Jun-12 27-Jun-12 17-Sep-12 20-Sep-12 71
A50000 Wiring for Lighting & Power 4 04-Jul-12 08-Jul-12 22-Oct-12 28-Oct-12 92
A50010 Installation of Lighting Fittings 4 08-Aug-12 12-Aug-12 12-Jan-13 15-Jan-13 127
LV Room (LV Room (Block A) 122 23-May-12 15-Oct-12 16-Aug-12 25-Apr-13 159
FinishingFinishing Works 122 23-May-12 15-Oct-12 16-Aug-12 25-Apr-13 159
Wet WorWet Works 34 23-May-12 02-Jul-12 16-Aug-12 25-Feb-13 196
A48640 Block Works 4 23-May-12 27-May-12 16-Aug-12 22-Aug-12 72
A48600 Installation of Doors& Windows Sub-frame 2 06-Jun-12 07-Jun-12 24-Feb-13 25-Feb-13 216
A48590 Plaster Works 6 06-Jun-12 12-Jun-12 15-Sep-12 20-Sep-12 83
A48610 1st Coat Paint 5 27-Jun-12 02-Jul-12 21-Oct-12 28-Oct-12 97
Fisrt StaFisrt Stage Finishes 12 03-Sep-12 16-Sep-12 21-Feb-13 09-Apr-13 170
A48700 Epoxy Paint Works 2 03-Sep-12 04-Sep-12 21-Feb-13 23-Feb-13 141
A48630 Installation of Doors 2 05-Sep-12 06-Sep-12 26-Feb-13 27-Feb-13 143
A48650 Doors Ironmongery 2 15-Sep-12 16-Sep-12 08-Apr-13 09-Apr-13 170
Second SSecond Stage Finishes 3 05-Sep-12 08-Sep-12 27-Mar-13 30-Mar-13 168
A48620 Final Coat Paint 3 05-Sep-12 08-Sep-12 27-Mar-13 30-Mar-13 168
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
A48690 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
MEP WorkMEP Works 84 24-May-12 02-Sep-12 23-Aug-12 20-Feb-13 141
HVACHVAC 5 24-May-12 29-May-12 07-Jan-13 12-Jan-13 187
A48750 Air-Outlet Installation 5 24-May-12 29-May-12 07-Jan-13 12-Jan-13 187
ElectricalElectrical 80 29-May-12 02-Sep-12 23-Aug-12 20-Feb-13 141
A48660 Install Conduits in Wall 5 29-May-12 03-Jun-12 23-Aug-12 28-Aug-12 71
A48670 Wiring for Lighting & Power 5 13-Jun-12 19-Jun-12 15-Oct-12 20-Oct-12 103
A48680 Installation of Lighting Fittings 5 03-Jul-12 08-Jul-12 24-Dec-12 29-Dec-12 143
A114360 Laying of LV Cables 15 03-Jul-12 19-Jul-12 22-Jan-13 09-Feb-13 167
A114370 Test of LV Cables 5 21-Jul-12 25-Jul-12 10-Feb-13 14-Feb-13 167
A48720 Installation of MDBs 30 22-Jul-12 27-Aug-12 10-Jan-13 14-Feb-13 141
A114380 Termination of LV Cables 5 28-Aug-12 02-Sep-12 16-Feb-13 20-Feb-13 141
Fire FighFire Fighting 10 14-Jul-12 24-Jul-12 29-Dec-12 09-Jan-13 138
A48710 Fire Alarm Devices 10 14-Jul-12 24-Jul-12 29-Dec-12 09-Jan-13 138
Sub-StatioSub-Station 1 186 16-May-12 26-Dec-12 08-Aug-12 25-Apr-13 101
FinishingFinishing Works 128 16-May-12 15-Oct-12 08-Aug-12 25-Apr-13 159
Wet WorWet Works 35 16-May-12 26-Jun-12 08-Aug-12 23-Feb-13 199
A48810 Block Works 6 16-May-12 22-May-12 08-Aug-12 14-Aug-12 71
A48770 Installation of Doors& Windows Sub-frame 2 31-May-12 02-Jun-12 21-Feb-13 23-Feb-13 219
A48760 Plaster Works 5 31-May-12 05-Jun-12 09-Sep-12 13-Sep-12 83
A48780 1st Coat Paint 9 16-Jun-12 26-Jun-12 10-Oct-12 20-Oct-12 97
Fisrt StaFisrt Stage Finishes 5 24-Jul-12 29-Jul-12 16-Feb-13 07-Apr-13 208
A48870 Epoxy Paint Works 3 24-Jul-12 26-Jul-12 16-Feb-13 18-Feb-13 169
A48800 Installation of Doors 2 28-Jul-12 29-Jul-12 24-Feb-13 25-Feb-13 173
A48820 Doors Ironmongery 2 28-Jul-12 29-Jul-12 06-Apr-13 07-Apr-13 208
Second SSecond Stage Finishes 4 31-Jul-12 04-Aug-12 04-Mar-13 07-Mar-13 177
A48790 Final Coat Paint 4 31-Jul-12 04-Aug-12 04-Mar-13 07-Mar-13 177
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
A48860 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
MEP WorkMEP Works 180 23-May-12 26-Dec-12 15-Aug-12 21-Mar-13 71
HVACHVAC 12 10-Jul-12 23-Jul-12 17-Jan-13 31-Jan-13 157
A48890 Air-Outlet Installation 12 10-Jul-12 23-Jul-12 17-Jan-13 31-Jan-13 157
ElectricalElectrical 180 23-May-12 26-Dec-12 15-Aug-12 21-Mar-13 71
Light &Light & Power 34 23-May-12 02-Jul-12 15-Aug-12 23-Dec-12 143
A48830 Install Conduits in Wall 5 23-May-12 28-May-12 15-Aug-12 22-Aug-12 71
A48840 Wiring for Lighting & Power 5 06-Jun-12 11-Jun-12 04-Oct-12 09-Oct-12 100
A48850 Installation of Lighting Fittings 5 27-Jun-12 02-Jul-12 18-Dec-12 23-Dec-12 143
TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71
A48910 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71
A48900 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87
A48920 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Lighting Fittings
Installation of Centeral Battery System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of MATC,TV System
Installation of Access ControlSystem
Fire Alarm Devices
Installation of Fire Extinguisher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Shaft Works
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Laying of LV Cables
Test of LV Cables
Installation of MDBs
Termination of LV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Install Cable Tray & Trunking
Installation of Transformer
Install of LV Cables
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 23 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A48930 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
A48940 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A48970 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A48960 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
A48980 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
Fire FighFire Fighting 14 27-Jun-12 12-Jul-12 12-Dec-12 27-Dec-12 138
A48880 Fire Alarm Devices 14 27-Jun-12 12-Jul-12 12-Dec-12 27-Dec-12 138
House keeHouse keeping Room 133 10-May-12 15-Oct-12 02-Aug-12 25-Apr-13 159
FinishingFinishing Works 133 10-May-12 15-Oct-12 02-Aug-12 25-Apr-13 159
Wet WorWet Works 31 10-May-12 14-Jun-12 02-Aug-12 20-Feb-13 206
A49040 Block Works 5 10-May-12 15-May-12 02-Aug-12 07-Aug-12 71
A49000 Installation of Doors& Windows Sub-frame 2 21-May-12 22-May-12 19-Feb-13 20-Feb-13 226
A48990 Plaster Works 9 21-May-12 30-May-12 29-Aug-12 08-Sep-12 83
A49010 1st Coat Paint 9 05-Jun-12 14-Jun-12 30-Sep-12 09-Oct-12 97
Fisrt StaFisrt Stage Finishes 57 10-Jul-12 16-Sep-12 12-Feb-13 12-Mar-13 146
A49100 Epoxy Paint Works 3 10-Jul-12 12-Jul-12 12-Feb-13 14-Feb-13 178
A49030 Installation of Doors 2 14-Jul-12 15-Jul-12 21-Feb-13 23-Feb-13 183
A49050 Doors Ironmongery 2 15-Sep-12 16-Sep-12 11-Mar-13 12-Mar-13 146
Second SSecond Stage Finishes 4 26-Jul-12 30-Jul-12 27-Feb-13 03-Mar-13 177
A49020 Final Coat Paint 4 26-Jul-12 30-Jul-12 27-Feb-13 03-Mar-13 177
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
A49090 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159
MEP WorkMEP Works 64 16-May-12 30-Jul-12 11-Aug-12 03-Mar-13 177
HVACHVAC 14 24-Jun-12 09-Jul-12 05-Nov-12 16-Jan-13 157
A49140 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 03-Jan-13 08-Jan-13 159
A49150 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 05-Nov-12 10-Nov-12 111
A49130 Duct Installation & Insulation 7 24-Jun-12 01-Jul-12 31-Dec-12 08-Jan-13 157
A49160 FCU Installation 3 02-Jul-12 04-Jul-12 09-Jan-13 12-Jan-13 157
A49170 Air-Outlet Installation 4 05-Jul-12 09-Jul-12 13-Jan-13 16-Jan-13 157
ElectricalElectrical 31 16-May-12 21-Jun-12 11-Aug-12 11-Feb-13 193
A49060 Install Conduits in Wall 4 16-May-12 20-May-12 11-Aug-12 14-Aug-12 73
A49070 Wiring for Lighting & Power 4 31-May-12 04-Jun-12 25-Sep-12 29-Sep-12 97
A49080 Installation of Lighting Fittings 5 16-Jun-12 21-Jun-12 06-Feb-13 11-Feb-13 193
PlumbingPlumbing 3 16-Jun-12 19-Jun-12 09-Feb-13 11-Feb-13 195
A49250 Floor Drain Fixning 3 16-Jun-12 19-Jun-12 09-Feb-13 11-Feb-13 195
Fire FighFire Fighting 42 11-Jun-12 30-Jul-12 30-Dec-12 03-Mar-13 177
A49210 Fire Fighting Pipe 7 11-Jun-12 19-Jun-12 30-Dec-12 07-Jan-13 166
A49200 Hydro Static Test for Pipes 3 20-Jun-12 23-Jun-12 23-Jan-13 27-Jan-13 179
A49190 Sprinkler Fixing 6 24-Jun-12 30-Jun-12 28-Jan-13 03-Feb-13 179
A49110 Fire Alarm Devices 7 01-Jul-12 08-Jul-12 04-Feb-13 11-Feb-13 179
A49180 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 02-Mar-13 03-Mar-13 177
StaircaseStaircase 133 28-Jun-12 06-Dec-12 01-Oct-12 25-Apr-13 118
Stair 1Stair 1 133 28-Jun-12 06-Dec-12 01-Oct-12 25-Apr-13 118
A107990 Floor Screed 3 28-Jun-12 01-Jul-12 01-Oct-12 03-Oct-12 79
A108000 Install Handrails 4 11-Oct-12 15-Oct-12 07-Nov-12 11-Nov-12 21
A108010 Ceiling 1st Coat Paint 7 20-Oct-12 29-Oct-12 06-Dec-12 13-Dec-12 37
A108020 Wall 1st Coat Paint 7 30-Oct-12 06-Nov-12 15-Dec-12 22-Dec-12 37
A108030 Install Granite/Terrazo 12 07-Nov-12 21-Nov-12 05-Jan-13 17-Jan-13 47
A108040 Final Coat Paint 12 22-Nov-12 06-Dec-12 13-Apr-13 25-Apr-13 118
Ground FloorGround Floor 381 09-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21
Public AreaPublic Area 381 09-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21
RampRamp 103 16-Oct-12 19-Feb-13 12-Nov-12 22-Apr-13 53
A115710 Install Handrail 7 16-Oct-12 23-Oct-12 12-Nov-12 20-Nov-12 21
A115720 1st Coat Paint 10 24-Oct-12 06-Nov-12 05-Mar-13 16-Mar-13 107
A115730 Surface Preparation (including Grinding & Repairing) 8 13-Jan-13 21-Jan-13 17-Mar-13 25-Mar-13 53
A115740 Application of 1st Coat 5 22-Jan-13 28-Jan-13 26-Mar-13 31-Mar-13 53
A115750 Application of Final Coat 5 29-Jan-13 03-Feb-13 01-Apr-13 06-Apr-13 53
A115760 Road Marking & Arrows 7 04-Feb-13 11-Feb-13 07-Apr-13 14-Apr-13 53
A115770 Final Coat Paint 7 12-Feb-13 19-Feb-13 15-Apr-13 22-Apr-13 53
Retail 1Retail 1 118 14-Jul-12 04-Dec-12 03-Jan-13 25-Apr-13 120
FinishingFinishing Works 118 14-Jul-12 04-Dec-12 03-Jan-13 25-Apr-13 120
Wet WorWet Works 12 14-Jul-12 26-Jul-12 03-Jan-13 23-Feb-13 173
A53150 Block Works 10 14-Jul-12 24-Jul-12 03-Jan-13 14-Jan-13 142
A53010 Installation of Doors& Windows Sub-frame 2 25-Jul-12 26-Jul-12 21-Feb-13 23-Feb-13 173
Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 14-Mar-13 25-Apr-13 120
A53090 Installation of Windows&Doors 2 03-Dec-12 04-Dec-12 14-Mar-13 16-Mar-13 85
A53160 Doors Ironmongery 2 03-Dec-12 04-Dec-12 24-Apr-13 25-Apr-13 120
MEP WorkMEP Works 23 25-Jul-12 22-Aug-12 15-Jan-13 05-Mar-13 161
HVACHVAC 23 25-Jul-12 22-Aug-12 19-Jan-13 05-Feb-13 137
A53200 Condensate Pipe Installation 10 25-Jul-12 05-Aug-12 19-Jan-13 30-Jan-13 145
A53190 Chilled Water Pipe Installation & Insulation 10 04-Aug-12 14-Aug-12 19-Jan-13 30-Jan-13 137
A53210 FCU Installation 5 15-Aug-12 22-Aug-12 31-Jan-13 05-Feb-13 137
ElectricalElectrical 10 25-Jul-12 05-Aug-12 23-Feb-13 05-Mar-13 174
A53230 Install Conduits in Wall 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174
A53250 Wiring for Lighting & Power 3 02-Aug-12 05-Aug-12 03-Mar-13 05-Mar-13 174
PlumbingPlumbing 10 25-Jul-12 05-Aug-12 23-Feb-13 05-Mar-13 174
A53330 Drainge Pipes in Wall 7 25-Jul-12 01-Aug-12 26-Feb-13 05-Mar-13 177
A53340 H/L Drainage Pipes Installation 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174
A53350 H/L Hot&Cold Water Pipe Installation 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174
A53400 Water Pipes in Wall 7 25-Jul-12 01-Aug-12 26-Feb-13 05-Mar-13 177
A53360 Drainage&Water Pipes Testing 3 02-Aug-12 05-Aug-12 03-Mar-13 05-Mar-13 174
Fire FighFire Fighting 20 25-Jul-12 16-Aug-12 15-Jan-13 05-Mar-13 164
A53440 Fire Fighting Pipe 7 25-Jul-12 01-Aug-12 15-Jan-13 22-Jan-13 142
A53430 Hydro Static Test for Pipes 4 02-Aug-12 06-Aug-12 23-Jan-13 28-Jan-13 142
A53420 Sprinkler Fixing 3 07-Aug-12 09-Aug-12 29-Jan-13 31-Jan-13 142
A53520 Fire Alarm Devices 5 11-Aug-12 15-Aug-12 02-Feb-13 06-Feb-13 142
A115210 Installation of Fire Hose Cabinet & Landing Valve 6 11-Aug-12 16-Aug-12 27-Feb-13 05-Mar-13 164
Retail 2Retail 2 127 01-Jul-12 01-Dec-12 20-Dec-12 23-Apr-13 120
FinishingFinishing Works 127 01-Jul-12 01-Dec-12 20-Dec-12 23-Apr-13 120
Wet WorWet Works 13 01-Jul-12 15-Jul-12 20-Dec-12 20-Feb-13 181
A53550 Block Works 11 01-Jul-12 12-Jul-12 20-Dec-12 02-Jan-13 142
A53530 Installation of Doors& Windows Sub-frame 2 14-Jul-12 15-Jul-12 19-Feb-13 20-Feb-13 181
Final StaFinal Stage Finishes 2 29-Nov-12 01-Dec-12 12-Mar-13 23-Apr-13 120
A53540 Installation of Windows&Doors 2 29-Nov-12 01-Dec-12 12-Mar-13 13-Mar-13 85
A53560 Doors Ironmongery 2 29-Nov-12 01-Dec-12 22-Apr-13 23-Apr-13 120
MEP WorkMEP Works 25 14-Jul-12 11-Aug-12 07-Jan-13 05-Mar-13 169
HVACHVAC 23 14-Jul-12 08-Aug-12 07-Jan-13 30-Jan-13 142
A53580 Condensate Pipe Installation 10 14-Jul-12 24-Jul-12 07-Jan-13 17-Jan-13 145
A53570 Chilled Water Pipe Installation & Insulation 10 23-Jul-12 02-Aug-12 07-Jan-13 17-Jan-13 137
A53590 FCU Installation 5 04-Aug-12 08-Aug-12 26-Jan-13 30-Jan-13 142
ElectricalElectrical 10 14-Jul-12 24-Jul-12 14-Feb-13 05-Mar-13 184
A53600 Install Conduits in Wall 7 14-Jul-12 21-Jul-12 14-Feb-13 21-Feb-13 177
A53610 Wiring for Lighting & Power 3 22-Jul-12 24-Jul-12 03-Mar-13 05-Mar-13 184
PlumbingPlumbing 10 14-Jul-12 24-Jul-12 23-Feb-13 05-Mar-13 184
A53620 Drainge Pipes in Wall 7 14-Jul-12 21-Jul-12 26-Feb-13 05-Mar-13 187
A53630 H/L Drainage Pipes Installation 7 14-Jul-12 21-Jul-12 23-Feb-13 02-Mar-13 184
A53640 H/L Hot&Cold Water Pipe Installation 7 14-Jul-12 21-Jul-12 23-Feb-13 02-Mar-13 184
A53660 Water Pipes in Wall 7 14-Jul-12 21-Jul-12 26-Feb-13 05-Mar-13 187
A53650 Drainage&Water Pipes Testing 3 22-Jul-12 24-Jul-12 03-Mar-13 05-Mar-13 184
Fire FighFire Fighting 25 14-Jul-12 11-Aug-12 07-Jan-13 05-Mar-13 169
A53700 Fire Fighting Pipe 7 14-Jul-12 21-Jul-12 07-Jan-13 14-Jan-13 145
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install of MV Cables
Test of LV Cables
Test of MV Cables
Termination of LV Cables
Termination of MV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Installation of Windows&Doors
Doors Ironmongery
Condensate Pipe Installation
Chilled Water Pipe Installation & Insulation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Hose Cabinet & Landing Valve
Block Works
Installation of Doors& Windows Sub-frame
Installation of Windows&Doors
Doors Ironmongery
Condensate Pipe Installation
Chilled Water Pipe Installation & Insulation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Fire Fighting Pipe
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 24 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A53690 Hydro Static Test for Pipes 4 22-Jul-12 25-Jul-12 17-Jan-13 21-Jan-13 147
A53680 Sprinkler Fixing 3 26-Jul-12 29-Jul-12 22-Jan-13 26-Jan-13 147
A53710 Fire Alarm Devices 5 30-Jul-12 04-Aug-12 27-Jan-13 31-Jan-13 147
A115220 Installation of Fire Hose Cabinet & Landing Valve 6 05-Aug-12 11-Aug-12 27-Feb-13 05-Mar-13 169
EnteranceEnterance & Lift Lobby 368 25-Jun-12 08-Sep-13 15-Dec-12 02-Oct-13 21
FinishingFinishing Works 368 25-Jun-12 08-Sep-13 15-Dec-12 02-Oct-13 21
Wet WorWet Works 62 25-Jun-12 06-Sep-12 15-Dec-12 16-Feb-13 133
A50750 Block Works 5 25-Jun-12 30-Jun-12 15-Dec-12 19-Dec-12 142
A50700 Plaster Works 4 12-Jul-12 16-Jul-12 13-Jan-13 16-Jan-13 151
A50720 Installation of Suspended Ceiling Grid 5 29-Jul-12 02-Aug-12 21-Jan-13 27-Jan-13 144
A50710 1st Coat Paint 6 01-Sep-12 06-Sep-12 10-Feb-13 16-Feb-13 133
Fisrt StaFisrt Stage Finishes 9 08-Sep-12 17-Sep-12 17-Feb-13 26-Feb-13 133
A50730 Suspended Ceiling Tiles 5 08-Sep-12 12-Sep-12 17-Feb-13 21-Feb-13 133
A50970 MDF for Lift Lobby Wall 7 08-Sep-12 15-Sep-12 17-Feb-13 24-Feb-13 133
A50950 Screed Works 2 16-Sep-12 17-Sep-12 25-Feb-13 26-Feb-13 133
Second SSecond Stage Finishes 9 18-Sep-12 27-Sep-12 27-Feb-13 09-Mar-13 133
A50960 Wall Tiles Work 5 18-Sep-12 23-Sep-12 27-Feb-13 04-Mar-13 133
A50990 Floor Tiles Work 4 24-Sep-12 27-Sep-12 05-Mar-13 09-Mar-13 133
Final StaFinal Stage Finishes 240 27-Nov-12 08-Sep-13 10-Mar-13 02-Oct-13 21
A50740 Installation of Doors 2 27-Nov-12 28-Nov-12 10-Mar-13 11-Mar-13 85
A50760 Doors Ironmongery 2 27-Nov-12 28-Nov-12 20-Apr-13 21-Apr-13 120
A51010 Installation of Mirrors 5 27-Nov-12 03-Dec-12 06-Apr-13 10-Apr-13 108
A51000 Final Coat Paint 3 04-Dec-12 06-Dec-12 11-Apr-13 14-Apr-13 108
A50940 Installation of Sinages 2 08-Dec-12 09-Dec-12 24-Apr-13 25-Apr-13 116
A53770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 71 01-Jul-12 23-Sep-12 29-Dec-12 05-Mar-13 134
HVACHVAC 67 03-Jul-12 20-Sep-12 29-Dec-12 05-Mar-13 136
A50790 Condensate Pipe Installation 7 03-Jul-12 10-Jul-12 29-Dec-12 06-Jan-13 147
A50770 Duct Installation & Insulation 7 10-Jul-12 17-Jul-12 07-Jan-13 14-Jan-13 148
A50780 Chilled Water Pipe Installation & Insulation 7 15-Jul-12 22-Jul-12 29-Dec-12 06-Jan-13 137
A50800 FCU Installation 5 23-Jul-12 28-Jul-12 15-Jan-13 20-Jan-13 144
A50810 Air-Outlet Installation 7 13-Sep-12 20-Sep-12 26-Feb-13 05-Mar-13 136
ElectricalElectrical 68 01-Jul-12 19-Sep-12 09-Jan-13 05-Mar-13 137
A50820 Install Conduits in Wall 3 01-Jul-12 03-Jul-12 09-Jan-13 12-Jan-13 158
A50830 Install Cable Trays & Trunking 3 01-Jul-12 03-Jul-12 12-Jan-13 14-Jan-13 160
A50870 Cable Laying for Low Current System 5 04-Jul-12 09-Jul-12 21-Jan-13 27-Jan-13 165
A50880 Cable Laying for Power 5 04-Jul-12 09-Jul-12 21-Jan-13 27-Jan-13 165
A50840 Wiring for Lighting & Power 3 17-Jul-12 19-Jul-12 17-Jan-13 20-Jan-13 151
A50850 Wiring for Low Current System 3 17-Jul-12 19-Jul-12 17-Jan-13 20-Jan-13 151
A50900 Installation of Lighting Fittings 6 13-Sep-12 19-Sep-12 27-Feb-13 05-Mar-13 137
Fire FighFire Fighting 71 01-Jul-12 23-Sep-12 29-Dec-12 05-Mar-13 134
A50930 Fire Fighting Pipe 7 01-Jul-12 08-Jul-12 29-Dec-12 06-Jan-13 149
A50920 Hydro Static Test for Pipes 7 09-Jul-12 16-Jul-12 13-Jan-13 20-Jan-13 154
A50910 Sprinkler Fixing 5 13-Sep-12 18-Sep-12 26-Feb-13 03-Mar-13 136
A50980 Fire Alarm Devices 7 13-Sep-12 20-Sep-12 24-Feb-13 03-Mar-13 134
A51020 Installation of Fire Hose Cabinet & Landing Valve 2 22-Sep-12 23-Sep-12 04-Mar-13 05-Mar-13 134
Electrical -Electrical -Telephone Room 133 21-Jun-12 28-Nov-12 11-Dec-12 25-Apr-13 124
FinishingFinishing Works 133 21-Jun-12 28-Nov-12 11-Dec-12 25-Apr-13 124
Wet WorWet Works 25 21-Jun-12 19-Jul-12 11-Dec-12 18-Feb-13 175
A51610 Block Works 3 21-Jun-12 24-Jun-12 11-Dec-12 13-Dec-12 142
A51570 Installation of Doors& Windows Sub-frame 2 08-Jul-12 09-Jul-12 17-Feb-13 18-Feb-13 184
A51560 Plaster Works 4 08-Jul-12 11-Jul-12 06-Jan-13 09-Jan-13 149
A51580 1st Coat Paint 4 16-Jul-12 19-Jul-12 14-Jan-13 17-Jan-13 149
Fisrt StaFisrt Stage Finishes 70 03-Sep-12 26-Nov-12 05-Mar-13 18-Apr-13 120
A51670 Epoxy Paint Works 2 03-Sep-12 04-Sep-12 05-Mar-13 06-Mar-13 151
A51600 Installation of Doors 2 25-Nov-12 26-Nov-12 07-Mar-13 09-Mar-13 85
A51620 Doors Ironmongery 2 25-Nov-12 26-Nov-12 17-Apr-13 18-Apr-13 120
Second SSecond Stage Finishes 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167
A51590 Final Coat Paint 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167
Final StaFinal Stage Finishes 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124
A51660 Installation of Sinages 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124
MEP WorkMEP Works 58 25-Jun-12 02-Sep-12 02-Jan-13 08-Apr-13 181
HVACHVAC 7 25-Jul-12 01-Aug-12 04-Feb-13 11-Feb-13 158
A51700 Air-Outlet Installation 7 25-Jul-12 01-Aug-12 04-Feb-13 11-Feb-13 158
ElectricalElectrical 58 25-Jun-12 02-Sep-12 02-Jan-13 04-Mar-13 151
A51630 Install Conduits in Wall 3 25-Jun-12 27-Jun-12 02-Jan-13 05-Jan-13 157
A51640 Wiring for Lighting & Power 3 12-Jul-12 15-Jul-12 10-Jan-13 13-Jan-13 149
A51650 Installation of Lighting Fittings 4 21-Jul-12 24-Jul-12 28-Feb-13 04-Mar-13 183
A51690 Installation of SMDBs 7 22-Jul-12 29-Jul-12 25-Feb-13 04-Mar-13 179
A51740 Installation of Telephone System 15 14-Aug-12 02-Sep-12 16-Feb-13 04-Mar-13 151
Fire FighFire Fighting 9 21-Jul-12 30-Jul-12 19-Jan-13 08-Apr-13 208
A51680 Fire Alarm Devices 6 21-Jul-12 26-Jul-12 19-Jan-13 26-Jan-13 149
A51710 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 07-Apr-13 08-Apr-13 208
Main GarbMain Garbage Room 213 09-Jun-12 21-Feb-13 28-Nov-12 24-Apr-13 53
FinishingFinishing Works 213 09-Jun-12 21-Feb-13 28-Nov-12 24-Apr-13 53
Wet WorWet Works 64 09-Jun-12 25-Aug-12 28-Nov-12 11-Feb-13 140
A51180 Block Works 2 09-Jun-12 10-Jun-12 28-Nov-12 29-Nov-12 142
A51040 Installation of Doors& Windows Sub-frame 1 14-Jun-12 14-Jun-12 11-Feb-13 11-Feb-13 198
A51030 Plaster Works 3 14-Jun-12 18-Jun-12 16-Dec-12 18-Dec-12 151
A51510 Wall Tiles Work 8 14-Aug-12 25-Aug-12 21-Jan-13 30-Jan-13 130
Fisrt StaFisrt Stage Finishes 10 26-Aug-12 05-Sep-12 31-Jan-13 11-Feb-13 130
A51500 Screed Works 2 26-Aug-12 27-Aug-12 31-Jan-13 02-Feb-13 130
A51050 1st Coat Paint 3 28-Aug-12 30-Aug-12 03-Feb-13 05-Feb-13 130
A51520 Floor Tiles Work 2 04-Sep-12 05-Sep-12 10-Feb-13 11-Feb-13 130
Second SSecond Stage Finishes 2 22-Nov-12 24-Nov-12 05-Mar-13 16-Apr-13 120
A51120 Installation of Doors 2 22-Nov-12 24-Nov-12 05-Mar-13 06-Mar-13 85
A51190 Doors Ironmongery 2 22-Nov-12 24-Nov-12 15-Apr-13 16-Apr-13 120
Final StaFinal Stage Finishes 105 16-Oct-12 21-Feb-13 12-Feb-13 24-Apr-13 53
A51150 Installation of Equipments 60 16-Oct-12 29-Dec-12 12-Feb-13 22-Apr-13 96
A51080 Final Coat Paint 2 20-Feb-13 21-Feb-13 23-Apr-13 24-Apr-13 53
MEP WorkMEP Works 211 11-Jun-12 21-Feb-13 08-Dec-12 24-Apr-13 53
HVACHVAC 60 24-Jun-12 03-Sep-12 08-Dec-12 09-Feb-13 130
A51220 Chilled Water Pipe Installation & Insulation 4 24-Jun-12 27-Jun-12 08-Dec-12 11-Dec-12 137
A51230 Condensate Pipe Installation 4 24-Jun-12 27-Jun-12 19-Dec-12 23-Dec-12 147
A51240 FCU Installation 3 01-Sep-12 03-Sep-12 06-Feb-13 09-Feb-13 130
ElectricalElectrical 70 11-Jun-12 03-Sep-12 12-Dec-12 05-Mar-13 151
A51260 Install Conduits in Wall 3 11-Jun-12 13-Jun-12 12-Dec-12 15-Dec-12 151
A51280 Wiring for Lighting & Power 3 19-Jun-12 21-Jun-12 30-Jan-13 02-Feb-13 185
A51340 Installation of Lighting Fittings 3 01-Sep-12 03-Sep-12 03-Mar-13 05-Mar-13 151
PlumbingPlumbing 7 11-Jun-12 19-Jun-12 12-Dec-12 02-Feb-13 187
A51430 Water Pipes in Wall 3 11-Jun-12 13-Jun-12 12-Dec-12 15-Dec-12 151
A51370 H/L Drainage Pipes Installation 4 11-Jun-12 14-Jun-12 26-Jan-13 29-Jan-13 187
A51380 H/L Hot&Cold Water Pipe Installation 4 11-Jun-12 14-Jun-12 26-Jan-13 29-Jan-13 187
A51390 Drainage&Water Pipes Testing 3 16-Jun-12 19-Jun-12 30-Jan-13 02-Feb-13 187
Fire FighFire Fighting 211 11-Jun-12 21-Feb-13 19-Dec-12 24-Apr-13 53
A51470 Fire Fighting Pipe 5 11-Jun-12 16-Jun-12 19-Dec-12 24-Dec-12 157
A51460 Hydro Static Test for Pipes 5 18-Jun-12 23-Jun-12 11-Feb-13 16-Feb-13 196
A51450 Sprinkler Fixing 5 01-Sep-12 05-Sep-12 17-Feb-13 21-Feb-13 139
A51550 Fire Alarm Devices 5 05-Sep-12 10-Sep-12 18-Feb-13 23-Feb-13 136
A51440 Installation of Fire Extingusher&Blanket 2 20-Feb-13 21-Feb-13 23-Apr-13 24-Apr-13 53
ToiletsToilets 141 11-Jun-12 28-Nov-12 01-Dec-12 25-Apr-13 124
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Hose Cabinet & Landing Valve
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Installation of Mirrors
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Hose Cabinet & Landing Valve
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of SMDBs
Installation of Telephone System
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
Screed Works
1st Coat Paint
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Installation of Equipments
Final Coat Paint
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 25 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
FinishingFinishing Works 141 11-Jun-12 28-Nov-12 01-Dec-12 25-Apr-13 124
Wet WorWet Works 54 11-Jun-12 13-Aug-12 01-Dec-12 13-Feb-13 150
A51870 Block Works 4 11-Jun-12 14-Jun-12 01-Dec-12 05-Dec-12 142
A51730 Installation of Doors& Windows Sub-frame 2 21-Jun-12 23-Jun-12 12-Feb-13 13-Feb-13 194
A51720 Plaster Works 7 21-Jun-12 28-Jun-12 19-Dec-12 26-Dec-12 149
A52200 Wall Tiles Work 5 08-Aug-12 13-Aug-12 15-Jan-13 20-Jan-13 130
Fisrt StaFisrt Stage Finishes 22 14-Aug-12 10-Sep-12 29-Jan-13 24-Feb-13 137
A52190 Screed Works 2 14-Aug-12 15-Aug-12 29-Jan-13 30-Jan-13 136
A51790 Water Proofing for Wet Area 2 16-Aug-12 18-Aug-12 31-Jan-13 02-Feb-13 136
A52230 Installation of Suspended Ceiling Grid 4 21-Aug-12 25-Aug-12 03-Feb-13 06-Feb-13 136
A52220 Suspended Ceiling Tiles 5 26-Aug-12 30-Aug-12 07-Feb-13 12-Feb-13 136
A52210 Floor & Wall Tiles Work 4 06-Sep-12 10-Sep-12 20-Feb-13 24-Feb-13 137
Second SSecond Stage Finishes 4 20-Nov-12 24-Nov-12 03-Mar-13 14-Apr-13 118
A51810 Installation of Doors 2 20-Nov-12 21-Nov-12 03-Mar-13 04-Mar-13 85
A51880 Doors Ironmongery 2 20-Nov-12 21-Nov-12 13-Apr-13 14-Apr-13 120
A51820 Installation of Mirrors 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113
A51860 Installation of Vanity Counter 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113
A52170 Installation of Toliets Accessories 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113
Final StaFinal Stage Finishes 4 25-Nov-12 28-Nov-12 09-Apr-13 25-Apr-13 124
A51770 Final Coat Paint 2 25-Nov-12 26-Nov-12 09-Apr-13 10-Apr-13 113
A52180 Installation of Sinages 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124
MEP WorkMEP Works 79 16-Jun-12 18-Sep-12 12-Dec-12 10-Apr-13 169
HVACHVAC 64 24-Jun-12 08-Sep-12 12-Dec-12 25-Feb-13 140
A51900 Duct Installation & Insulation 4 24-Jun-12 27-Jun-12 20-Dec-12 24-Dec-12 148
A51910 Chilled Water Pipe Installation & Insulation 4 28-Jun-12 02-Jul-12 12-Dec-12 16-Dec-12 137
A51920 Condensate Pipe Installation 4 28-Jun-12 02-Jul-12 24-Dec-12 27-Dec-12 147
A51930 FCU Installation 2 03-Jul-12 04-Jul-12 13-Jan-13 14-Jan-13 159
A51940 Air-Outlet Installation 7 01-Sep-12 08-Sep-12 18-Feb-13 25-Feb-13 140
ElectricalElectrical 68 16-Jun-12 05-Sep-12 15-Dec-12 05-Mar-13 149
A51950 Install Conduits in Wall 4 16-Jun-12 20-Jun-12 15-Dec-12 18-Dec-12 149
A51970 Wiring for Lighting & Power 4 30-Jun-12 03-Jul-12 29-Jan-13 02-Feb-13 175
A52030 Installation of Lighting Fittings 5 01-Sep-12 05-Sep-12 28-Feb-13 05-Mar-13 149
PlumbingPlumbing 79 16-Jun-12 18-Sep-12 16-Dec-12 08-Apr-13 167
A52050 Drainge Pipes in Wall 3 16-Jun-12 19-Jun-12 16-Dec-12 18-Dec-12 150
A52120 Water Pipes in Wall 3 16-Jun-12 19-Jun-12 16-Dec-12 18-Dec-12 150
A52060 H/L Drainage Pipes Installation 4 16-Jun-12 20-Jun-12 26-Jan-13 29-Jan-13 183
A52070 H/L Hot&Cold Water Pipe Installation 4 16-Jun-12 20-Jun-12 26-Jan-13 29-Jan-13 183
A52090 ElectricalWater Heater Installation 2 21-Jun-12 23-Jun-12 31-Jan-13 02-Feb-13 184
A52080 Drainage&Water Pipes Testing 3 21-Jun-12 24-Jun-12 30-Jan-13 02-Feb-13 183
A52100 Floor Drain Fixning 2 16-Aug-12 18-Aug-12 19-Feb-13 20-Feb-13 152
A52110 Installation of Sanitaryware 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167
Fire FighFire Fighting 72 18-Jun-12 11-Sep-12 25-Dec-12 10-Apr-13 175
A52160 Fire Fighting Pipe 3 18-Jun-12 20-Jun-12 25-Dec-12 27-Dec-12 157
A52150 Hydro Static Test for Pipes 3 21-Jun-12 24-Jun-12 30-Jan-13 02-Feb-13 183
A52240 Fire Alarm Devices 4 01-Sep-12 04-Sep-12 13-Feb-13 17-Feb-13 136
A52140 Sprinkler Fixing 3 06-Sep-12 09-Sep-12 23-Feb-13 25-Feb-13 139
A52130 Installation of Fire Extingusher&Blanket 2 10-Sep-12 11-Sep-12 09-Apr-13 10-Apr-13 175
OfficeOffice 375 16-Jun-12 08-Sep-13 06-Dec-12 02-Oct-13 21
FinishingFinishing Works 375 16-Jun-12 08-Sep-13 06-Dec-12 02-Oct-13 21
Wet WorWet Works 46 16-Jun-12 08-Aug-12 06-Dec-12 16-Feb-13 156
A52400 Block Works 2 16-Jun-12 18-Jun-12 06-Dec-12 08-Dec-12 142
A52260 Installation of Doors& Windows Sub-frame 2 30-Jun-12 01-Jul-12 14-Feb-13 16-Feb-13 189
A52250 Plaster Works 3 30-Jun-12 02-Jul-12 27-Dec-12 30-Dec-12 149
A52280 Installation of Suspended Ceiling Grid 2 04-Aug-12 05-Aug-12 28-Jan-13 29-Jan-13 144
A52270 1st Coat Paint 3 06-Aug-12 08-Aug-12 30-Jan-13 02-Feb-13 144
Fisrt StaFisrt Stage Finishes 28 09-Aug-12 12-Sep-12 05-Feb-13 26-Feb-13 137
A52290 Suspended Ceiling Tiles 2 09-Aug-12 11-Aug-12 05-Feb-13 06-Feb-13 146
A52720 Screed Works 2 12-Aug-12 13-Aug-12 23-Feb-13 24-Feb-13 159
A52310 Floor Tiles Work 2 11-Sep-12 12-Sep-12 25-Feb-13 26-Feb-13 137
Second SSecond Stage Finishes 55 13-Sep-12 19-Nov-12 28-Feb-13 11-Apr-13 120
A52300 Final Coat Paint 2 13-Sep-12 15-Sep-12 03-Apr-13 04-Apr-13 167
A52340 Installation of Windows&Doors 2 18-Nov-12 19-Nov-12 28-Feb-13 02-Mar-13 85
A52410 Doors Ironmongery 2 18-Nov-12 19-Nov-12 10-Apr-13 11-Apr-13 120
Final StaFinal Stage Finishes 247 19-Nov-12 08-Sep-13 24-Apr-13 02-Oct-13 21
A52710 Installation of Sinages 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131
A52420 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 55 19-Jun-12 23-Aug-12 17-Dec-12 04-Apr-13 186
HVACHVAC 47 24-Jun-12 16-Aug-12 17-Dec-12 17-Feb-13 150
A52450 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 14-Jan-13 19-Jan-13 168
A52430 Duct Installation & Insulation 5 28-Jun-12 03-Jul-12 25-Dec-12 30-Dec-12 148
A52440 Chilled Water Pipe Installation & Insulation 5 03-Jul-12 08-Jul-12 17-Dec-12 22-Dec-12 137
A52460 FCU Installation 6 09-Jul-12 15-Jul-12 20-Jan-13 27-Jan-13 160
A52470 Air-Outlet Installation 5 12-Aug-12 16-Aug-12 12-Feb-13 17-Feb-13 150
ElectricalElectrical 53 19-Jun-12 21-Aug-12 24-Dec-12 05-Mar-13 162
A52480 Install Conduits in Wall 3 19-Jun-12 21-Jun-12 24-Dec-12 26-Dec-12 155
A52490 Install Cable Trays & Trunking 4 19-Jun-12 23-Jun-12 24-Dec-12 27-Dec-12 155
A52530 Cable Laying for Low Current System 4 24-Jun-12 27-Jun-12 26-Jan-13 29-Jan-13 177
A52540 Cable Laying for Power 4 24-Jun-12 27-Jun-12 26-Jan-13 29-Jan-13 177
A52500 Wiring for Lighting & Power 3 03-Jul-12 05-Jul-12 23-Jan-13 27-Jan-13 168
A52510 Wiring for Low Current System 3 03-Jul-12 05-Jul-12 23-Jan-13 27-Jan-13 168
A52560 Installation of Lighting Fittings 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162
Fire FighFire Fighting 55 19-Jun-12 23-Aug-12 16-Jan-13 04-Apr-13 186
A52690 Fire Fighting Pipe 5 19-Jun-12 24-Jun-12 16-Jan-13 21-Jan-13 174
A52680 Hydro Static Test for Pipes 4 25-Jun-12 28-Jun-12 22-Jan-13 27-Jan-13 174
A52670 Sprinkler Fixing 6 12-Aug-12 18-Aug-12 27-Feb-13 05-Mar-13 163
A52660 Installation of Fire Extingusher&Blanket 2 21-Aug-12 22-Aug-12 03-Apr-13 04-Apr-13 187
A52770 Fire Alarm Devices 5 16-Aug-12 23-Aug-12 07-Feb-13 12-Feb-13 142
Luggae StoLuggae Storage 128 19-Jun-12 20-Nov-12 09-Dec-12 25-Apr-13 131
FinishingFinishing Works 128 19-Jun-12 20-Nov-12 09-Dec-12 25-Apr-13 131
Wet WorWet Works 35 19-Jun-12 29-Jul-12 09-Dec-12 25-Feb-13 173
A52830 Block Works 2 19-Jun-12 20-Jun-12 09-Dec-12 10-Dec-12 142
A52780 Plaster Works 4 03-Jul-12 07-Jul-12 31-Dec-12 05-Jan-13 149
A52800 1st Coat Paint 4 10-Jul-12 14-Jul-12 09-Jan-13 13-Jan-13 150
A52790 Installation of Doors& Windows Sub-frame 2 28-Jul-12 29-Jul-12 24-Feb-13 25-Feb-13 173
Fisrt StaFisrt Stage Finishes 94 25-Jul-12 17-Nov-12 24-Feb-13 09-Apr-13 120
A52890 Epoxy Paint Works 2 25-Jul-12 26-Jul-12 24-Feb-13 25-Feb-13 175
A52820 Installation of Doors 2 14-Nov-12 17-Nov-12 26-Feb-13 27-Feb-13 85
A52840 Doors Ironmongery 2 14-Nov-12 17-Nov-12 08-Apr-13 09-Apr-13 120
Second SSecond Stage Finishes 3 28-Jul-12 30-Jul-12 31-Mar-13 02-Apr-13 203
A52810 Final Coat Paint 3 28-Jul-12 30-Jul-12 31-Mar-13 02-Apr-13 203
Final StaFinal Stage Finishes 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131
A52880 Installation of Sinages 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131
MEP WorkMEP Works 34 21-Jun-12 30-Jul-12 23-Dec-12 02-Apr-13 203
HVACHVAC 27 24-Jun-12 24-Jul-12 23-Dec-12 03-Feb-13 158
A52930 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 17-Jan-13 22-Jan-13 171
A52910 Duct Installation & Insulation 5 04-Jul-12 09-Jul-12 31-Dec-12 06-Jan-13 148
A52920 Chilled Water Pipe Installation & Insulation 5 09-Jul-12 14-Jul-12 23-Dec-12 27-Dec-12 137
A52940 FCU Installation 3 15-Jul-12 17-Jul-12 23-Jan-13 27-Jan-13 158
A52950 Air-Outlet Installation 6 18-Jul-12 24-Jul-12 28-Jan-13 03-Feb-13 158
ElectricalElectrical 23 21-Jun-12 17-Jul-12 27-Dec-12 23-Feb-13 181
A52850 Install Conduits in Wall 3 21-Jun-12 24-Jun-12 27-Dec-12 30-Dec-12 156
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Floor & Wall Tiles Work
Installation of Doors
Doors Ironmongery
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
ElectricalWater Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Final Coat Paint
Installation of Windows&Doors
Doors Ironmongery
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
1st Coat Paint
Installation of Doors& Windows Sub-frame
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 26 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A52860 Wiring for Lighting & Power 2 08-Jul-12 09-Jul-12 07-Jan-13 08-Jan-13 150
A52870 Installation of Lighting Fittings 3 15-Jul-12 17-Jul-12 20-Feb-13 23-Feb-13 181
Fire FighFire Fighting 34 21-Jun-12 30-Jul-12 29-Dec-12 02-Apr-13 203
A52990 Fire Fighting Pipe 5 21-Jun-12 26-Jun-12 29-Dec-12 03-Jan-13 157
A52980 Hydro Static Test for Pipes 4 27-Jun-12 01-Jul-12 05-Jan-13 08-Jan-13 157
A52970 Sprinkler Fixing 4 02-Jul-12 05-Jul-12 09-Jan-13 13-Jan-13 157
A52900 Fire Alarm Devices 4 07-Jul-12 10-Jul-12 14-Jan-13 17-Jan-13 157
A52960 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 01-Apr-13 02-Apr-13 203
StaircaseStaircase 154 23-Jul-12 27-Jan-13 04-Oct-12 25-Apr-13 76
Stair 1Stair 1 126 23-Jul-12 23-Dec-12 04-Oct-12 25-Apr-13 104
A108050 Floor Screed 3 23-Jul-12 25-Jul-12 04-Oct-12 07-Oct-12 61
A108060 Install Handrails 4 24-Oct-12 30-Oct-12 21-Nov-12 25-Nov-12 21
A108070 Ceiling 1st Coat Paint 7 07-Nov-12 14-Nov-12 23-Dec-12 30-Dec-12 37
A108080 Wall 1st Coat Paint 7 17-Nov-12 24-Nov-12 31-Dec-12 08-Jan-13 37
A108090 Install Granite/Terrazo 12 25-Nov-12 09-Dec-12 19-Jan-13 02-Feb-13 45
A108100 Final Coat Paint 12 10-Dec-12 23-Dec-12 13-Apr-13 25-Apr-13 104
Stair 2Stair 2 137 26-Jul-12 09-Jan-13 08-Oct-12 25-Apr-13 90
A108110 Floor Screed 3 26-Jul-12 29-Jul-12 08-Oct-12 10-Oct-12 61
A108120 Install Handrails 4 31-Oct-12 04-Nov-12 26-Nov-12 29-Nov-12 21
A108130 Ceiling 1st Coat Paint 7 25-Nov-12 03-Dec-12 09-Jan-13 16-Jan-13 37
A108140 Wall 1st Coat Paint 7 04-Dec-12 11-Dec-12 17-Jan-13 26-Jan-13 37
A108150 Install Granite/Terrazo 12 12-Dec-12 25-Dec-12 03-Feb-13 16-Feb-13 43
A108160 Final Coat Paint 12 26-Dec-12 09-Jan-13 13-Apr-13 25-Apr-13 90
Stair 3Stair 3 148 30-Jul-12 27-Jan-13 11-Oct-12 25-Apr-13 76
A111140 Floor Screed 3 30-Jul-12 01-Aug-12 11-Oct-12 14-Oct-12 61
A111180 Install Handrails 4 05-Nov-12 08-Nov-12 01-Dec-12 05-Dec-12 21
A111150 Ceiling 1st Coat Paint 7 12-Dec-12 19-Dec-12 27-Jan-13 03-Feb-13 37
A111160 Wall 1st Coat Paint 7 20-Dec-12 27-Dec-12 04-Feb-13 11-Feb-13 37
A111170 Install Granite/Terrazo 12 29-Dec-12 12-Jan-13 17-Feb-13 02-Mar-13 41
A111190 Final Coat Paint 12 13-Jan-13 27-Jan-13 13-Apr-13 25-Apr-13 76
1st Floor1st Floor 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21
Public AreaPublic Area 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20
Garbage RGarbage Room 170 01-Aug-12 24-Feb-13 02-Sep-12 25-Apr-13 52
FinishingFinishing Works 170 01-Aug-12 24-Feb-13 02-Sep-12 25-Apr-13 52
Wet WorWet Works 149 01-Aug-12 30-Jan-13 02-Sep-12 22-Apr-13 70
A14500 Block Works 3 01-Aug-12 04-Aug-12 02-Sep-12 04-Sep-12 25
A14440 Plaster Works 3 16-Aug-12 21-Aug-12 27-Jan-13 29-Jan-13 132
A14450 Installation of Doors& Windows Sub-frame 1 01-Sep-12 01-Sep-12 22-Apr-13 22-Apr-13 194
A14480 Wall Tiles Work 4 19-Jan-13 22-Jan-13 17-Feb-13 20-Feb-13 24
A14460 1st Coat Paint 2 29-Jan-13 30-Jan-13 21-Feb-13 23-Feb-13 20
Fisrt StaFisrt Stage Finishes 15 31-Jan-13 17-Feb-13 24-Feb-13 24-Apr-13 57
A14790 Screed Works 2 31-Jan-13 02-Feb-13 24-Feb-13 25-Feb-13 20
A14810 Floor Tiles Work 2 04-Feb-13 05-Feb-13 27-Feb-13 28-Feb-13 20
A14510 Doors Ironmongery 1 16-Feb-13 16-Feb-13 24-Apr-13 24-Apr-13 58
A14490 Installation of Doors 2 16-Feb-13 17-Feb-13 23-Apr-13 24-Apr-13 57
Second SSecond Stage Finishes 2 21-Feb-13 23-Feb-13 09-Apr-13 10-Apr-13 40
A14470 Final Coat Paint 2 21-Feb-13 23-Feb-13 09-Apr-13 10-Apr-13 40
Final StaFinal Stage Finishes 1 24-Feb-13 24-Feb-13 25-Apr-13 25-Apr-13 52
A14780 Installation of Sinages 1 24-Feb-13 24-Feb-13 25-Apr-13 25-Apr-13 52
MEP WorkMEP Works 153 05-Aug-12 07-Feb-13 10-Sep-12 01-Apr-13 45
ElectricalElectrical 153 05-Aug-12 07-Feb-13 23-Jan-13 05-Mar-13 22
A14570 Install Conduits in Wall 2 05-Aug-12 06-Aug-12 23-Jan-13 26-Jan-13 140
A14590 Wiring for Lighting & Power 2 22-Aug-12 23-Aug-12 14-Feb-13 16-Feb-13 145
A14640 Installation of Lighting Fittings 2 06-Feb-13 07-Feb-13 04-Mar-13 05-Mar-13 22
PlumbingPlumbing 149 05-Aug-12 03-Feb-13 21-Jan-13 26-Feb-13 20
A14660 Drainge Pipes in Wall 2 05-Aug-12 06-Aug-12 21-Jan-13 22-Jan-13 138
A14730 Water Pipes in Wall 2 05-Aug-12 06-Aug-12 21-Jan-13 22-Jan-13 138
A14690 Drainage&Water Pipes Testing 2 14-Aug-12 15-Aug-12 23-Jan-13 26-Jan-13 132
A14710 Floor Drain Fixning 1 03-Feb-13 03-Feb-13 26-Feb-13 26-Feb-13 20
Fire FighFire Fighting 152 06-Aug-12 07-Feb-13 10-Sep-12 01-Apr-13 45
A14770 Fire Fighting Pipe 2 06-Aug-12 07-Aug-12 10-Sep-12 11-Sep-12 28
A14760 Hydro Static Test for Pipes 2 14-Aug-12 15-Aug-12 27-Feb-13 28-Feb-13 161
A14750 Sprinkler Fixing 2 06-Feb-13 07-Feb-13 02-Mar-13 03-Mar-13 20
A14800 Fire Alarm Devices 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45
Corridor &Corridor & Lift Lobby 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20
FinishingFinishing Works 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20
Wet WorWet Works 142 29-Jul-12 17-Jan-13 29-Aug-12 11-Feb-13 20
A9810 Block Works 3 29-Jul-12 31-Jul-12 29-Aug-12 01-Sep-12 25
A9660 Plaster Works 6 04-Aug-12 09-Aug-12 15-Dec-12 20-Dec-12 108
A9690 Installation of Suspended Ceiling Grid 6 17-Sep-12 23-Sep-12 26-Dec-12 02-Jan-13 82
A9700 Suspended Ceiling Tiles 6 10-Jan-13 16-Jan-13 04-Feb-13 10-Feb-13 20
A10150 MDF for Lift Lobby Wall 7 10-Jan-13 17-Jan-13 04-Feb-13 11-Feb-13 20
Fisrt StaFisrt Stage Finishes 8 19-Jan-13 28-Jan-13 12-Feb-13 20-Feb-13 20
A10140 Screed Works 3 19-Jan-13 21-Jan-13 12-Feb-13 14-Feb-13 20
A9680 1st Coat Paint 5 22-Jan-13 28-Jan-13 16-Feb-13 20-Feb-13 20
Second SSecond Stage Finishes 2 13-Feb-13 14-Feb-13 11-Apr-13 25-Apr-13 60
A9750 Installation of Doors 2 13-Feb-13 14-Feb-13 11-Apr-13 13-Apr-13 49
A9820 Doors Ironmongery 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60
Final StaFinal Stage Finishes 11 21-Mar-13 02-Apr-13 14-Apr-13 25-Apr-13 20
A9780 Installation of Carpets 4 21-Mar-13 25-Mar-13 14-Apr-13 17-Apr-13 20
A9720 Fixing of Wall Covering 5 26-Mar-13 31-Mar-13 18-Apr-13 23-Apr-13 20
A10130 Installation of Sinages 2 01-Apr-13 02-Apr-13 24-Apr-13 25-Apr-13 20
MEP WorkMEP Works 147 01-Aug-12 28-Jan-13 05-Sep-12 05-Mar-13 31
HVACHVAC 141 01-Aug-12 20-Jan-13 17-Dec-12 20-Feb-13 26
A9860 Condensate Pipe Installation 5 01-Aug-12 06-Aug-12 17-Dec-12 22-Dec-12 112
A9840 Duct Installation & Insulation 5 12-Aug-12 16-Aug-12 17-Dec-12 22-Dec-12 103
A9850 Chilled Water Pipe Installation & Insulation 5 12-Aug-12 16-Aug-12 17-Dec-12 22-Dec-12 103
A9870 FCU Installation 3 18-Aug-12 22-Aug-12 23-Dec-12 25-Dec-12 103
A9880 Air-Outlet Installation 3 17-Jan-13 20-Jan-13 18-Feb-13 20-Feb-13 26
ElectricalElectrical 143 01-Aug-12 22-Jan-13 12-Dec-12 05-Mar-13 35
A9890 Install Conduits in Wall 2 01-Aug-12 02-Aug-12 12-Dec-12 13-Dec-12 108
A9900 Install Cable Trays & Trunking 2 01-Aug-12 02-Aug-12 17-Dec-12 18-Dec-12 112
A9940 Cable Laying for Low Current System 2 04-Aug-12 05-Aug-12 31-Dec-12 02-Jan-13 122
A9950 Cable Laying for Power 4 04-Aug-12 07-Aug-12 29-Dec-12 02-Jan-13 120
A9910 Wiring for Lighting & Power 3 11-Aug-12 13-Aug-12 23-Dec-12 25-Dec-12 109
A9920 Wiring for Low Current System 4 11-Aug-12 14-Aug-12 22-Dec-12 25-Dec-12 108
A9930 DB installation,Dressing & Termination 6 24-Sep-12 30-Sep-12 04-Feb-13 10-Feb-13 108
A9990 Installation of Sockets 3 17-Jan-13 20-Jan-13 03-Mar-13 05-Mar-13 37
A9970 Installation of Lighting Fittings 5 17-Jan-13 22-Jan-13 28-Feb-13 05-Mar-13 35
PlumbingPlumbing 5 04-Aug-12 08-Aug-12 20-Dec-12 25-Dec-12 113
A10020 H/L Hot&Cold Water Pipe Installation 5 04-Aug-12 08-Aug-12 20-Dec-12 25-Dec-12 113
Fire FighFire Fighting 147 01-Aug-12 28-Jan-13 05-Sep-12 20-Feb-13 20
A10110 Fire Fighting Pipe 4 01-Aug-12 05-Aug-12 05-Sep-12 09-Sep-12 28
A10100 Hydro Static Test for Pipes 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107
A10090 Sprinkler Fixing 5 17-Jan-13 22-Jan-13 11-Feb-13 16-Feb-13 20
A13900 Fire Alarm Devices 4 21-Jan-13 26-Jan-13 14-Feb-13 18-Feb-13 20
A10080 Installation of Fire Extingusher&Blanket 4 23-Jan-13 28-Jan-13 17-Feb-13 20-Feb-13 20
A115230 Installation of Fire Hose Cabinet & Landing Valve 6 21-Jan-13 28-Jan-13 14-Feb-13 20-Feb-13 20
Electrical /Electrical /Telephone/ELV Rooms 170 05-Aug-12 27-Feb-13 05-Sep-12 25-Apr-13 49
FinishingFinishing Works 170 05-Aug-12 27-Feb-13 05-Sep-12 25-Apr-13 49
Wet WorWet Works 22 05-Aug-12 01-Sep-12 05-Sep-12 08-Apr-13 182
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Installation of Fire Hose Cabinet & Landing Valve
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 27 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A14880 Block Works 3 05-Aug-12 07-Aug-12 05-Sep-12 08-Sep-12 25
A14820 Plaster Works 3 22-Aug-12 25-Aug-12 30-Jan-13 02-Feb-13 132
A14830 Installation of Doors& Windows Sub-frame 1 30-Aug-12 30-Aug-12 08-Apr-13 08-Apr-13 183
A14840 1st Coat Paint 3 29-Aug-12 01-Sep-12 06-Feb-13 09-Feb-13 132
Fisrt StaFisrt Stage Finishes 2 11-Feb-13 12-Feb-13 09-Apr-13 23-Apr-13 60
A14870 Installation of Doors 2 11-Feb-13 12-Feb-13 09-Apr-13 10-Apr-13 49
A14890 Doors Ironmongery 2 11-Feb-13 12-Feb-13 22-Apr-13 23-Apr-13 60
A15010 Epoxy Paint Works 2 11-Feb-13 12-Feb-13 09-Apr-13 10-Apr-13 49
Second SSecond Stage Finishes 2 24-Feb-13 25-Feb-13 11-Apr-13 13-Apr-13 40
A14850 Final Coat Paint 2 24-Feb-13 25-Feb-13 11-Apr-13 13-Apr-13 40
Final StaFinal Stage Finishes 2 26-Feb-13 27-Feb-13 24-Apr-13 25-Apr-13 49
A15000 Installation of Sinages 2 26-Feb-13 27-Feb-13 24-Apr-13 25-Apr-13 49
MEP WorkMEP Works 152 08-Aug-12 10-Feb-13 27-Jan-13 03-Apr-13 45
HVACHVAC 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33
A15050 Air-Outlet Installation 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33
ElectricalElectrical 40 08-Aug-12 25-Sep-12 27-Jan-13 05-Mar-13 132
A14900 Install Conduits in Wall 3 08-Aug-12 11-Aug-12 27-Jan-13 29-Jan-13 139
A14910 Wiring for Lighting & Power 3 26-Aug-12 28-Aug-12 03-Feb-13 05-Feb-13 132
A14930 Installation of SMDBs 7 02-Sep-12 09-Sep-12 24-Feb-13 03-Mar-13 144
A14920 Installation of Lighting Fittings 2 10-Sep-12 11-Sep-12 04-Mar-13 05-Mar-13 144
A114400 Installation of Access ControlSystem 20 02-Sep-12 24-Sep-12 11-Feb-13 05-Mar-13 133
A114390 Installation of MATC,TV System 20 02-Sep-12 24-Sep-12 11-Feb-13 05-Mar-13 133
A14940 Installation of Telephone System 21 02-Sep-12 25-Sep-12 10-Feb-13 05-Mar-13 132
Fire FighFire Fighting 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45
A15020 Fire Alarm Devices 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45
Room ServRoom Service 162 08-Aug-12 21-Feb-13 09-Sep-12 25-Apr-13 54
FinishingFinishing Works 162 08-Aug-12 21-Feb-13 09-Sep-12 25-Apr-13 54
Wet WorWet Works 22 08-Aug-12 04-Sep-12 09-Sep-12 06-Apr-13 177
A15120 Block Works 3 08-Aug-12 11-Aug-12 09-Sep-12 11-Sep-12 25
A15060 Plaster Works 3 26-Aug-12 28-Aug-12 16-Feb-13 18-Feb-13 143
A15070 Installation of Doors& Windows Sub-frame 1 29-Aug-12 29-Aug-12 06-Apr-13 06-Apr-13 182
A15080 1st Coat Paint 3 02-Sep-12 04-Sep-12 21-Feb-13 24-Feb-13 142
Fisrt StaFisrt Stage Finishes 130 05-Sep-12 10-Feb-13 25-Feb-13 24-Apr-13 63
A15250 Screed Works 2 05-Sep-12 06-Sep-12 25-Feb-13 26-Feb-13 142
A15270 Floor Tiles Work 3 05-Feb-13 07-Feb-13 28-Feb-13 03-Mar-13 20
A15110 Installation of Doors 2 09-Feb-13 10-Feb-13 07-Apr-13 08-Apr-13 49
A15130 Doors Ironmongery 2 09-Feb-13 10-Feb-13 23-Apr-13 24-Apr-13 63
Second SSecond Stage Finishes 2 19-Feb-13 20-Feb-13 07-Apr-13 08-Apr-13 40
A15090 Final Coat Paint 2 19-Feb-13 20-Feb-13 07-Apr-13 08-Apr-13 40
Final StaFinal Stage Finishes 1 21-Feb-13 21-Feb-13 25-Apr-13 25-Apr-13 54
A15240 Installation of Sinages 1 21-Feb-13 21-Feb-13 25-Apr-13 25-Apr-13 54
MEP WorkMEP Works 151 12-Aug-12 12-Feb-13 12-Sep-12 06-Apr-13 45
HVACHVAC 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33
A15280 Air-Outlet Installation 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33
ElectricalElectrical 149 12-Aug-12 10-Feb-13 13-Feb-13 05-Mar-13 20
A15140 Install Conduits in Wall 2 12-Aug-12 13-Aug-12 13-Feb-13 14-Feb-13 151
A15150 Wiring for Lighting & Power 2 29-Aug-12 30-Aug-12 19-Feb-13 20-Feb-13 143
A15160 Installation of Lighting Fittings 2 09-Feb-13 10-Feb-13 04-Mar-13 05-Mar-13 20
PlumbingPlumbing 144 12-Aug-12 04-Feb-13 22-Dec-12 27-Feb-13 20
A15170 Drainge Pipes in Wall 2 12-Aug-12 13-Aug-12 22-Dec-12 23-Dec-12 107
A15200 Water Pipes in Wall 2 12-Aug-12 13-Aug-12 22-Dec-12 23-Dec-12 107
A15180 Drainage&Water Pipes Testing 2 14-Aug-12 15-Aug-12 24-Dec-12 25-Dec-12 107
A15190 Floor Drain Fixning 1 04-Feb-13 04-Feb-13 27-Feb-13 27-Feb-13 20
Fire FighFire Fighting 151 12-Aug-12 12-Feb-13 12-Sep-12 06-Apr-13 45
A15230 Fire Fighting Pipe 2 12-Aug-12 13-Aug-12 12-Sep-12 13-Sep-12 25
A15220 Hydro Static Test for Pipes 2 14-Aug-12 15-Aug-12 15-Sep-12 16-Sep-12 25
A15210 Sprinkler Fixing 2 09-Feb-13 10-Feb-13 04-Mar-13 05-Mar-13 20
A15260 Fire Alarm Devices 2 11-Feb-13 12-Feb-13 04-Apr-13 06-Apr-13 45
StaircaseStaircase 166 11-Aug-12 28-Feb-13 15-Oct-12 13-Apr-13 37
Stair 1Stair 1 152 11-Aug-12 12-Feb-13 15-Oct-12 30-Mar-13 39
A108170 Floor Screed 3 11-Aug-12 13-Aug-12 15-Oct-12 17-Oct-12 54
A108180 Install Handrails 4 10-Nov-12 13-Nov-12 06-Dec-12 10-Dec-12 21
A108190 Ceiling 1st Coat Paint 7 29-Dec-12 06-Jan-13 12-Feb-13 19-Feb-13 37
A108200 Wall 1st Coat Paint 7 07-Jan-13 14-Jan-13 20-Feb-13 27-Feb-13 37
A108210 Install Granite/Terrazo 12 15-Jan-13 29-Jan-13 03-Mar-13 16-Mar-13 39
A108220 Final Coat Paint 12 30-Jan-13 12-Feb-13 17-Mar-13 30-Mar-13 39
Stair 2Stair 2 163 14-Aug-12 28-Feb-13 18-Oct-12 13-Apr-13 37
A108230 Floor Screed 3 14-Aug-12 16-Aug-12 18-Oct-12 21-Oct-12 54
A108240 Install Handrails 4 14-Nov-12 19-Nov-12 11-Dec-12 15-Dec-12 21
A108250 Ceiling 1st Coat Paint 7 15-Jan-13 22-Jan-13 28-Feb-13 07-Mar-13 37
A108260 Wall 1st Coat Paint 7 23-Jan-13 31-Jan-13 09-Mar-13 16-Mar-13 37
A108270 Install Granite/Terrazo 12 02-Feb-13 14-Feb-13 17-Mar-13 30-Mar-13 37
A108280 Final Coat Paint 12 16-Feb-13 28-Feb-13 31-Mar-13 13-Apr-13 37
ApartementsApartements 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21
Studio FlatsStudio Flats 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21
FinishingFinishing Works 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21
Wet WoWet Works 62 25-Jul-12 07-Oct-12 26-Aug-12 24-Mar-13 138
A6040 Block Works 3 25-Jul-12 28-Jul-12 26-Aug-12 28-Aug-12 25
A5880 Plaster Works 7 01-Aug-12 08-Aug-12 08-Oct-12 15-Oct-12 56
A8780 Wall Tiles Work (Wet Area) 8 09-Aug-12 18-Aug-12 31-Oct-12 08-Nov-12 67
A5890 Installation of Doors& Windows Sub-frame 3 26-Aug-12 28-Aug-12 21-Mar-13 24-Mar-13 172
A5910 Installation of Suspended Ceiling Grid (Dry Area) 6 10-Sep-12 16-Sep-12 17-Oct-12 23-Oct-12 32
A5900 1st Coat Paint 6 01-Oct-12 07-Oct-12 24-Oct-12 01-Nov-12 20
Fisrt StaFisrt Stage Finishes 79 13-Oct-12 17-Jan-13 07-Nov-12 27-Feb-13 34
A5920 Suspended Ceiling Tiles (DryArea) 2 13-Oct-12 14-Oct-12 07-Nov-12 08-Nov-12 20
A5960 Installation of Wardrobes 2 12-Nov-12 13-Nov-12 22-Dec-12 23-Dec-12 32
A8770 Screed Works 5 29-Nov-12 05-Dec-12 24-Dec-12 29-Dec-12 20
A5950 Water Proofing for Wet Area 3 06-Dec-12 09-Dec-12 30-Dec-12 02-Jan-13 20
A5940 Floor & Wall Tiles Work (Dry Area) 4 06-Dec-12 10-Dec-12 22-Jan-13 27-Jan-13 39
A9110 Installation of Suspended Ceiling Grid (Wet Area) 3 10-Dec-12 12-Dec-12 03-Jan-13 06-Jan-13 20
A8990 Suspended Ceiling Tiles (Wet Area) 2 08-Jan-13 09-Jan-13 02-Feb-13 03-Feb-13 20
A8970 Floor Tiles Work (Wet Area) 2 16-Jan-13 17-Jan-13 26-Feb-13 27-Feb-13 34
SecondSecond Stage Finishes 11 20-Jan-13 02-Feb-13 25-Mar-13 25-Apr-13 71
A5970 Installation of Windows&Doors 2 20-Jan-13 21-Jan-13 25-Mar-13 26-Mar-13 54
A6050 Doors Ironmongery 2 20-Jan-13 21-Jan-13 24-Apr-13 25-Apr-13 80
A6020 Installation of Balustrades& Handrails 2 22-Jan-13 23-Jan-13 28-Mar-13 30-Mar-13 55
A5990 Installation of Mirrors 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51
A6000 Installation of Kitchen Cabinets 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51
A6030 Installation of Vanity Counter 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51
A6960 Installation of Toliets Accessories 2 31-Jan-13 02-Feb-13 28-Mar-13 30-Mar-13 48
Final StFinal Stage Finishes 177 12-Feb-13 08-Sep-13 31-Mar-13 02-Oct-13 21
A5930 Final Coat Paint 6 12-Feb-13 18-Feb-13 31-Mar-13 06-Apr-13 40
A6010 Installation of Carpets 4 31-Mar-13 03-Apr-13 22-Apr-13 25-Apr-13 19
A6970 Installation of Sinages 7 27-Mar-13 03-Apr-13 18-Apr-13 25-Apr-13 19
A6060 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 148 29-Jul-12 26-Jan-13 02-Sep-12 06-Apr-13 60
HVACHVAC 139 29-Jul-12 14-Jan-13 07-Oct-12 17-Feb-13 28
A6090 Condensate Pipe Installation 7 29-Jul-12 05-Aug-12 07-Oct-12 14-Oct-12 58
A6070 Duct Installation & Insulation 7 04-Aug-12 11-Aug-12 07-Oct-12 14-Oct-12 53
A6080 Chilled Water Pipe Installation & Insulation 7 04-Aug-12 11-Aug-12 07-Oct-12 14-Oct-12 53
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Doors& Windows Sub-frame
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 28 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A6100 FCU Installation 2 12-Aug-12 13-Aug-12 15-Oct-12 16-Oct-12 53
A6120 Air-Outlet Installation 3 12-Jan-13 14-Jan-13 14-Feb-13 17-Feb-13 28
ElectricElectrical 139 29-Jul-12 14-Jan-13 04-Oct-12 05-Mar-13 42
A6130 Install Conduits in Wall 3 29-Jul-12 31-Jul-12 04-Oct-12 07-Oct-12 56
A6140 Install Cable Trays & Trunking 4 29-Jul-12 01-Aug-12 09-Oct-12 13-Oct-12 60
A6180 Cable Laying for Low Current System 3 02-Aug-12 05-Aug-12 21-Oct-12 23-Oct-12 66
A6190 Cable Laying for Power 3 02-Aug-12 05-Aug-12 21-Oct-12 23-Oct-12 66
A6150 Wiring for Lighting & Power 3 07-Aug-12 09-Aug-12 14-Oct-12 16-Oct-12 56
A6160 Wiring for Low Current System 3 07-Aug-12 09-Aug-12 14-Oct-12 16-Oct-12 56
A6170 DB installation,Dressing & Termination 6 08-Oct-12 14-Oct-12 03-Nov-12 08-Nov-12 20
A6230 Installation of Sockets 3 10-Jan-13 13-Jan-13 03-Mar-13 05-Mar-13 43
A6210 Installation of Lighting Fittings 4 10-Jan-13 14-Jan-13 02-Mar-13 05-Mar-13 42
PlumbinPlumbing 148 29-Jul-12 26-Jan-13 04-Oct-12 30-Mar-13 54
A6240 Drainge Pipes in Wall 4 29-Jul-12 01-Aug-12 04-Oct-12 08-Oct-12 56
A6310 Water Pipes in Wall 4 29-Jul-12 01-Aug-12 04-Oct-12 08-Oct-12 56
A6250 H/L Drainage Pipes Installation 4 30-Jul-12 02-Aug-12 24-Dec-12 27-Dec-12 120
A6260 H/L Hot&Cold Water Pipe Installation 4 30-Jul-12 02-Aug-12 16-Dec-12 19-Dec-12 113
A6270 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 29-Dec-12 02-Jan-13 113
A6280 ElectricalWater Heater Installation 2 23-Aug-12 25-Aug-12 31-Dec-12 02-Jan-13 107
A6290 Floor Drain Fixning 2 03-Dec-12 04-Dec-12 23-Feb-13 24-Feb-13 68
A6300 Installation of Sanitaryware 3 22-Jan-13 26-Jan-13 27-Mar-13 30-Mar-13 54
Fire FigFire Fighting 141 29-Jul-12 16-Jan-13 02-Sep-12 06-Apr-13 67
A6360 Fire Fighting Pipe 3 29-Jul-12 31-Jul-12 02-Sep-12 04-Sep-12 28
A6350 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 14-Oct-12 16-Oct-12 51
A12830 Fire Alarm Devices 3 10-Jan-13 13-Jan-13 04-Feb-13 06-Feb-13 20
A6340 Sprinkler Fixing 3 12-Jan-13 14-Jan-13 07-Feb-13 10-Feb-13 22
A6330 Installation of Fire Extingusher&Blanket 2 15-Jan-13 16-Jan-13 04-Apr-13 06-Apr-13 67
One BedroOne Bedroom Flats 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 (1 BR) 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21
FinishingFinishing Works 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21
Wet WoWet Works 62 18-Jul-12 30-Sep-12 16-Aug-12 12-Mar-13 134
A22080 Block Works 6 18-Jul-12 24-Jul-12 16-Aug-12 25-Aug-12 25
A21940 Installation of Doors& Windows Sub-frame 4 21-Aug-12 25-Aug-12 09-Mar-13 12-Mar-13 165
A21930 Plaster Works 9 21-Aug-12 30-Aug-12 24-Sep-12 03-Oct-12 29
A22410 Wall Tiles Work (Wet Area) 6 01-Sep-12 06-Sep-12 10-Nov-12 17-Nov-12 58
A21960 Installation of Suspended Ceiling Grid (Dry Area) 5 04-Sep-12 09-Sep-12 08-Oct-12 13-Oct-12 29
A21950 1st Coat Paint 9 20-Sep-12 30-Sep-12 14-Oct-12 23-Oct-12 20
Fisrt StaFisrt Stage Finishes 75 15-Oct-12 15-Jan-13 10-Nov-12 25-Feb-13 34
A21970 Suspended Ceiling Tiles (DryArea) 3 15-Oct-12 17-Oct-12 10-Nov-12 12-Nov-12 20
A22010 Installation of Wardrobes 5 06-Nov-12 11-Nov-12 05-Dec-12 10-Dec-12 23
A22400 Screed Works 11 17-Nov-12 28-Nov-12 11-Dec-12 23-Dec-12 20
A22000 Water Proofing for Wet Area 4 29-Nov-12 04-Dec-12 25-Dec-12 29-Dec-12 21
A21990 Floor & Wall Tiles Work (Dry Area) 4 11-Dec-12 15-Dec-12 28-Jan-13 31-Jan-13 39
A22440 Installation of Suspended Ceiling Grid (Wet Area) 5 13-Dec-12 18-Dec-12 07-Jan-13 12-Jan-13 20
A22430 Suspended Ceiling Tiles (Wet Area) 5 02-Jan-13 07-Jan-13 27-Jan-13 31-Jan-13 20
A22420 Floor Tiles Work (Wet Area) 7 08-Jan-13 15-Jan-13 18-Feb-13 25-Feb-13 34
SecondSecond Stage Finishes 12 16-Jan-13 30-Jan-13 13-Mar-13 21-Mar-13 43
A22020 Installation of Windows&Doors 3 16-Jan-13 19-Jan-13 13-Mar-13 16-Mar-13 47
A22090 Doors Ironmongery 3 16-Jan-13 19-Jan-13 19-Mar-13 21-Mar-13 52
A22060 Installation of Balustrades& Handrails 2 20-Jan-13 21-Jan-13 20-Mar-13 21-Mar-13 50
A22030 Installation of Mirrors 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46
A22040 Installation of Kitchen Cabinets 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46
A22070 Installation of Vanity Counter 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46
A22380 Installation of Toliets Accessories 5 26-Jan-13 30-Jan-13 17-Mar-13 21-Mar-13 43
Final StFinal Stage Finishes 184 04-Feb-13 08-Sep-13 23-Mar-13 02-Oct-13 21
A21980 Final Coat Paint 7 04-Feb-13 11-Feb-13 23-Mar-13 30-Mar-13 40
A22050 Installation of Carpets 4 26-Mar-13 30-Mar-13 17-Apr-13 21-Apr-13 19
A22390 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23
A22100 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 149 25-Jul-12 22-Jan-13 29-Aug-12 30-Mar-13 56
HVACHVAC 139 25-Jul-12 10-Jan-13 27-Sep-12 13-Feb-13 28
A22130 Condensate Pipe Installation 7 25-Jul-12 01-Aug-12 27-Sep-12 04-Oct-12 53
A22110 Duct Installation & Insulation 7 26-Jul-12 02-Aug-12 27-Sep-12 04-Oct-12 52
A22120 Chilled Water Pipe Installation & Insulation 7 26-Jul-12 02-Aug-12 27-Sep-12 04-Oct-12 52
A22140 FCU Installation 2 04-Aug-12 05-Aug-12 06-Oct-12 07-Oct-12 52
A22150 Air-Outlet Installation 3 08-Jan-13 10-Jan-13 11-Feb-13 13-Feb-13 28
ElectricElectrical 140 25-Jul-12 12-Jan-13 20-Sep-12 05-Mar-13 44
A22160 Install Conduits in Wall 3 25-Jul-12 28-Jul-12 20-Sep-12 23-Sep-12 47
A22170 Install Cable Trays & Trunking 4 25-Jul-12 29-Jul-12 27-Sep-12 01-Oct-12 53
A22210 Cable Laying for Low Current System 3 30-Jul-12 01-Aug-12 10-Oct-12 13-Oct-12 60
A22220 Cable Laying for Power 3 30-Jul-12 01-Aug-12 10-Oct-12 13-Oct-12 60
A22180 Wiring for Lighting & Power 3 01-Sep-12 03-Sep-12 04-Oct-12 07-Oct-12 29
A22190 Wiring for Low Current System 3 01-Sep-12 03-Sep-12 04-Oct-12 07-Oct-12 29
A22200 DB installation,Dressing & Termination 6 01-Oct-12 07-Oct-12 06-Nov-12 12-Nov-12 29
A22250 Installation of Sockets 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45
A22240 Installation of Lighting Fittings 4 08-Jan-13 12-Jan-13 02-Mar-13 05-Mar-13 44
PlumbinPlumbing 149 25-Jul-12 22-Jan-13 15-Sep-12 21-Mar-13 49
A22270 H/L Drainage Pipes Installation 4 25-Jul-12 29-Jul-12 19-Dec-12 23-Dec-12 120
A22280 H/L Hot&Cold Water Pipe Installation 4 25-Jul-12 29-Jul-12 11-Dec-12 15-Dec-12 113
A22260 Drainge Pipes in Wall 8 25-Jul-12 02-Aug-12 15-Sep-12 23-Sep-12 42
A22330 Water Pipes in Wall 8 25-Jul-12 02-Aug-12 15-Sep-12 23-Sep-12 42
A22290 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 26-Dec-12 30-Dec-12 111
A22300 ElectricalWater Heater Installation 4 16-Aug-12 22-Aug-12 26-Dec-12 30-Dec-12 107
A22310 Floor Drain Fixning 2 19-Nov-12 20-Nov-12 20-Feb-13 21-Feb-13 77
A22320 Installation of Sanitaryware 3 20-Jan-13 22-Jan-13 19-Mar-13 21-Mar-13 49
Fire FigFire Fighting 144 25-Jul-12 16-Jan-13 29-Aug-12 30-Mar-13 61
A22370 Fire Fighting Pipe 3 25-Jul-12 28-Jul-12 29-Aug-12 01-Sep-12 28
A22360 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 04-Oct-12 07-Oct-12 43
A22350 Sprinkler Fixing 3 08-Jan-13 10-Jan-13 04-Feb-13 06-Feb-13 22
A22340 Installation of Fire Extingusher&Blanket 2 12-Jan-13 13-Jan-13 28-Mar-13 30-Mar-13 64
A22450 Fire Alarm Devices 3 14-Jan-13 16-Jan-13 07-Feb-13 10-Feb-13 20
Two BedroTwo Bedroom Flats 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 (2 BR) 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21
FinishingFinishing Works 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21
Wet WoWet Works 65 04-Jul-12 19-Sep-12 28-Jul-12 23-Feb-13 128
A24730 Block Works 12 04-Jul-12 17-Jul-12 28-Jul-12 09-Aug-12 20
A24590 Installation of Doors& Windows Sub-frame 6 30-Jul-12 05-Aug-12 17-Feb-13 23-Feb-13 165
A24580 Plaster Works 17 30-Jul-12 18-Aug-12 25-Aug-12 12-Sep-12 20
A24610 Installation of Suspended Ceiling Grid (Dry Area) 7 25-Aug-12 01-Sep-12 17-Sep-12 24-Sep-12 20
A24600 1st Coat Paint 16 02-Sep-12 19-Sep-12 25-Sep-12 13-Oct-12 20
A25060 Wall Tiles Work (Wet Area) 11 08-Sep-12 19-Sep-12 18-Nov-12 29-Nov-12 58
Fisrt StaFisrt Stage Finishes 64 18-Oct-12 06-Jan-13 13-Nov-12 17-Feb-13 35
A24620 Suspended Ceiling Tiles (DryArea) 7 18-Oct-12 28-Oct-12 13-Nov-12 21-Nov-12 20
A24660 Installation of Wardrobes 7 29-Oct-12 05-Nov-12 22-Nov-12 29-Nov-12 20
A25050 Screed Works 8 06-Nov-12 14-Nov-12 01-Dec-12 10-Dec-12 20
A24650 Water Proofing for Wet Area 8 17-Nov-12 25-Nov-12 16-Dec-12 24-Dec-12 24
A25090 Installation of Suspended Ceiling Grid (Wet Area) 6 19-Dec-12 25-Dec-12 13-Jan-13 19-Jan-13 20
A24640 Floor & Wall Tiles Work (Dry Area) 10 16-Dec-12 26-Dec-12 02-Feb-13 12-Feb-13 39
A25080 Suspended Ceiling Tiles (Wet Area) 5 26-Dec-12 31-Dec-12 20-Jan-13 26-Jan-13 20
A25070 Floor Tiles Work (Wet Area) 4 02-Jan-13 06-Jan-13 13-Feb-13 17-Feb-13 35
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Wall Tiles Work (Wet Area)
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 29 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
SecondSecond Stage Finishes 15 07-Jan-13 23-Jan-13 24-Feb-13 12-Mar-13 40
A24670 Installation of Windows&Doors 5 07-Jan-13 12-Jan-13 24-Feb-13 28-Feb-13 40
A24740 Doors Ironmongery 5 07-Jan-13 12-Jan-13 07-Mar-13 12-Mar-13 50
A24710 Installation of Balustrades& Handrails 5 13-Jan-13 17-Jan-13 07-Mar-13 12-Mar-13 45
A24680 Installation of Mirrors 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42
A24690 Installation of Kitchen Cabinets 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42
A24720 Installation of Vanity Counter 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42
A25030 Installation of Toliets Accessories 10 13-Jan-13 23-Jan-13 02-Mar-13 12-Mar-13 40
Final StFinal Stage Finishes 192 26-Jan-13 08-Sep-13 13-Mar-13 02-Oct-13 21
A24630 Final Coat Paint 8 26-Jan-13 03-Feb-13 13-Mar-13 21-Mar-13 40
A24700 Installation of Carpets 4 21-Mar-13 25-Mar-13 13-Apr-13 16-Apr-13 19
A25040 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A24750 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 153 18-Jul-12 20-Jan-13 11-Aug-12 21-Mar-13 51
HVACHVAC 140 18-Jul-12 05-Jan-13 06-Sep-12 10-Feb-13 30
A24760 Duct Installation & Insulation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41
A24770 Chilled Water Pipe Installation & Insulation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41
A24780 Condensate Pipe Installation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41
A24790 FCU Installation 2 26-Jul-12 28-Jul-12 15-Sep-12 16-Sep-12 41
A24800 Air-Outlet Installation 3 02-Jan-13 05-Jan-13 07-Feb-13 10-Feb-13 30
ElectricElectrical 141 18-Jul-12 06-Jan-13 21-Aug-12 05-Mar-13 49
A24810 Install Conduits in Wall 3 18-Jul-12 21-Jul-12 21-Aug-12 23-Aug-12 27
A24820 Install Cable Trays & Trunking 4 18-Jul-12 22-Jul-12 06-Sep-12 10-Sep-12 41
A24860 Cable Laying for Low Current System 3 23-Jul-12 25-Jul-12 22-Sep-12 24-Sep-12 50
A24870 Cable Laying for Power 3 23-Jul-12 25-Jul-12 22-Sep-12 24-Sep-12 50
A24830 Wiring for Lighting & Power 3 21-Aug-12 23-Aug-12 13-Sep-12 16-Sep-12 20
A24840 Wiring for Low Current System 3 21-Aug-12 23-Aug-12 13-Sep-12 16-Sep-12 20
A24850 DB installation,Dressing & Termination 6 20-Sep-12 26-Sep-12 14-Nov-12 21-Nov-12 45
A24900 Installation of Sockets 3 02-Jan-13 05-Jan-13 03-Mar-13 05-Mar-13 50
A24890 Installation of Lighting Fittings 4 02-Jan-13 06-Jan-13 02-Mar-13 05-Mar-13 49
PlumbinPlumbing 149 18-Jul-12 15-Jan-13 11-Aug-12 12-Mar-13 47
A24920 H/L Drainage Pipes Installation 4 18-Jul-12 22-Jul-12 15-Dec-12 18-Dec-12 122
A24930 H/L Hot&Cold Water Pipe Installation 4 18-Jul-12 22-Jul-12 06-Dec-12 10-Dec-12 115
A24980 Water Pipes in Wall 8 18-Jul-12 26-Jul-12 13-Aug-12 23-Aug-12 22
A24910 Drainge Pipes in Wall 10 18-Jul-12 29-Jul-12 11-Aug-12 23-Aug-12 20
A24940 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107
A24950 ElectricalWater Heater Installation 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107
A24960 Floor Drain Fixning 2 08-Nov-12 10-Nov-12 12-Feb-13 13-Feb-13 78
A24970 Installation of Sanitaryware 3 13-Jan-13 15-Jan-13 10-Mar-13 12-Mar-13 47
Fire FigFire Fighting 153 18-Jul-12 20-Jan-13 26-Aug-12 21-Mar-13 51
A25020 Fire Fighting Pipe 3 18-Jul-12 21-Jul-12 26-Aug-12 28-Aug-12 31
A25010 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 13-Sep-12 16-Sep-12 25
A25000 Sprinkler Fixing 3 02-Jan-13 05-Jan-13 31-Jan-13 03-Feb-13 24
A24990 Installation of Fire Extingusher&Blanket 2 06-Jan-13 07-Jan-13 20-Mar-13 21-Mar-13 62
A25100 Fire Alarm Devices 3 17-Jan-13 20-Jan-13 11-Feb-13 13-Feb-13 20
2nd Floor2nd Floor 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21
Public AreaPublic Area 196 25-Aug-12 16-Apr-13 22-Oct-12 25-Apr-13 8
Garbage RGarbage Room 125 03-Sep-12 02-Feb-13 17-Dec-12 25-Apr-13 71
FinishingFinishing Works 125 03-Sep-12 02-Feb-13 17-Dec-12 25-Apr-13 71
Wet WorWet Works 115 03-Sep-12 20-Jan-13 17-Dec-12 07-Feb-13 15
A15690 Block Works 3 03-Sep-12 05-Sep-12 17-Dec-12 19-Dec-12 86
A15640 Installation of Doors& Windows Sub-frame 1 10-Oct-12 10-Oct-12 07-Feb-13 07-Feb-13 97
A15630 Plaster Works 3 10-Oct-12 13-Oct-12 21-Jan-13 23-Jan-13 83
A15670 Wall Tiles Work 4 16-Oct-12 20-Oct-12 28-Jan-13 31-Jan-13 83
A15650 1st Coat Paint 2 19-Jan-13 20-Jan-13 02-Feb-13 03-Feb-13 11
Fisrt StaFisrt Stage Finishes 7 21-Jan-13 29-Jan-13 09-Feb-13 24-Apr-13 73
A15820 Screed Works 2 21-Jan-13 22-Jan-13 09-Feb-13 10-Feb-13 15
A15840 Floor Tiles Work 2 26-Jan-13 27-Jan-13 02-Mar-13 03-Mar-13 30
A15700 Doors Ironmongery 1 28-Jan-13 28-Jan-13 24-Apr-13 24-Apr-13 74
A15680 Installation of Doors 2 28-Jan-13 29-Jan-13 23-Apr-13 24-Apr-13 73
Second SSecond Stage Finishes 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52
A15660 Final Coat Paint 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52
Final StaFinal Stage Finishes 1 02-Feb-13 02-Feb-13 25-Apr-13 25-Apr-13 71
A15810 Installation of Sinages 1 02-Feb-13 02-Feb-13 25-Apr-13 25-Apr-13 71
MEP WorkMEP Works 119 06-Sep-12 29-Jan-13 20-Dec-12 31-Mar-13 52
ElectricalElectrical 119 06-Sep-12 29-Jan-13 19-Jan-13 05-Mar-13 30
A15710 Install Conduits in Wall 2 06-Sep-12 08-Sep-12 19-Jan-13 20-Jan-13 110
A15720 Wiring for Lighting & Power 2 14-Oct-12 15-Oct-12 26-Jan-13 27-Jan-13 83
A15730 Installation of Lighting Fittings 2 28-Jan-13 29-Jan-13 04-Mar-13 05-Mar-13 30
PlumbingPlumbing 115 06-Sep-12 23-Jan-13 16-Jan-13 28-Feb-13 30
A15740 Drainge Pipes in Wall 2 06-Sep-12 08-Sep-12 16-Jan-13 17-Jan-13 108
A15770 Water Pipes in Wall 2 06-Sep-12 08-Sep-12 16-Jan-13 17-Jan-13 108
A15750 Drainage&Water Pipes Testing 2 09-Sep-12 10-Sep-12 19-Jan-13 20-Jan-13 108
A15760 Floor Drain Fixning 1 23-Jan-13 23-Jan-13 28-Feb-13 28-Feb-13 30
Fire FighFire Fighting 119 06-Sep-12 29-Jan-13 20-Dec-12 31-Mar-13 52
A15800 Fire Fighting Pipe 2 06-Sep-12 08-Sep-12 20-Dec-12 22-Dec-12 86
A15790 Hydro Static Test for Pipes 2 09-Sep-12 10-Sep-12 02-Mar-13 03-Mar-13 143
A15780 Sprinkler Fixing 2 28-Jan-13 29-Jan-13 04-Mar-13 05-Mar-13 30
A15830 Fire Alarm Devices 2 28-Jan-13 29-Jan-13 30-Mar-13 31-Mar-13 52
Corridor &Corridor & Lift Lobby 196 25-Aug-12 16-Apr-13 08-Dec-12 25-Apr-13 8
FinishingFinishing Works 196 25-Aug-12 16-Apr-13 08-Dec-12 25-Apr-13 8
Wet WorWet Works 57 25-Aug-12 31-Oct-12 08-Dec-12 21-Jan-13 67
A15350 Block Works 8 25-Aug-12 02-Sep-12 08-Dec-12 16-Dec-12 86
A15290 Plaster Works 7 02-Oct-12 09-Oct-12 19-Dec-12 26-Dec-12 63
A15310 Installation of Suspended Ceiling Grid 6 15-Oct-12 21-Oct-12 02-Jan-13 08-Jan-13 63
A15320 Suspended Ceiling Tiles 6 22-Oct-12 30-Oct-12 09-Jan-13 15-Jan-13 63
A15610 MDF for Lift Lobby Wall 7 22-Oct-12 31-Oct-12 14-Jan-13 21-Jan-13 67
Fisrt StaFisrt Stage Finishes 8 09-Jan-13 17-Jan-13 22-Jan-13 31-Jan-13 11
A15590 Screed Works 3 09-Jan-13 12-Jan-13 22-Jan-13 26-Jan-13 11
A15300 1st Coat Paint 5 13-Jan-13 17-Jan-13 27-Jan-13 31-Jan-13 11
Second SSecond Stage Finishes 2 19-Jan-13 20-Jan-13 13-Feb-13 25-Apr-13 81
A15330 Installation of Doors 2 19-Jan-13 20-Jan-13 13-Feb-13 14-Feb-13 21
A15360 Doors Ironmongery 2 19-Jan-13 20-Jan-13 24-Apr-13 25-Apr-13 81
Final StaFinal Stage Finishes 20 25-Mar-13 16-Apr-13 03-Apr-13 25-Apr-13 8
A15340 Installation of Carpets 4 25-Mar-13 28-Mar-13 03-Apr-13 07-Apr-13 8
A15600 Fixing of Wall Covering 7 30-Mar-13 06-Apr-13 08-Apr-13 15-Apr-13 8
A15580 Installation of Sinages 9 07-Apr-13 16-Apr-13 16-Apr-13 25-Apr-13 8
MEP WorkMEP Works 56 03-Sep-12 08-Nov-12 17-Dec-12 05-Mar-13 96
HVACHVAC 51 03-Sep-12 03-Nov-12 23-Dec-12 26-Jan-13 68
A15370 Duct Installation & Insulation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91
A15380 Chilled Water Pipe Installation & Insulation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91
A15390 Condensate Pipe Installation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91
A15400 FCU Installation 3 09-Sep-12 11-Sep-12 29-Dec-12 31-Dec-12 91
A15410 Air-Outlet Installation 3 31-Oct-12 03-Nov-12 22-Jan-13 26-Jan-13 68
ElectricalElectrical 53 03-Sep-12 05-Nov-12 17-Dec-12 05-Mar-13 99
A15420 Install Conduits in Wall 2 03-Sep-12 04-Sep-12 17-Dec-12 18-Dec-12 86
A15430 Install Cable Trays & Trunking 2 03-Sep-12 04-Sep-12 23-Dec-12 24-Dec-12 91
A15470 Cable Laying for Low Current System 2 05-Sep-12 06-Sep-12 07-Jan-13 08-Jan-13 101
A15480 Cable Laying for Power 3 05-Sep-12 08-Sep-12 06-Jan-13 08-Jan-13 100
A15440 Wiring for Lighting & Power 3 10-Oct-12 13-Oct-12 29-Dec-12 31-Dec-12 64
A15450 Wiring for Low Current System 4 10-Oct-12 14-Oct-12 27-Dec-12 31-Dec-12 63
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 30 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A15460 DB installation,Dressing & Termination 6 22-Oct-12 30-Oct-12 09-Jan-13 15-Jan-13 63
A15500 Installation of Lighting Fittings 3 31-Oct-12 03-Nov-12 03-Mar-13 05-Mar-13 101
A15510 Installation of Sockets 5 31-Oct-12 05-Nov-12 28-Feb-13 05-Mar-13 99
PlumbingPlumbing 5 03-Sep-12 08-Sep-12 26-Dec-12 31-Dec-12 94
A15520 H/L Hot&Cold Water Pipe Installation 5 03-Sep-12 08-Sep-12 26-Dec-12 31-Dec-12 94
Fire FighFire Fighting 51 09-Sep-12 08-Nov-12 23-Dec-12 26-Jan-13 63
A15570 Fire Fighting Pipe 4 09-Sep-12 12-Sep-12 23-Dec-12 26-Dec-12 86
A15560 Hydro Static Test for Pipes 4 13-Sep-12 17-Sep-12 27-Dec-12 31-Dec-12 86
A15550 Sprinkler Fixing 4 31-Oct-12 04-Nov-12 16-Jan-13 20-Jan-13 63
A15620 Fire Alarm Devices 5 31-Oct-12 05-Nov-12 20-Jan-13 26-Jan-13 66
A15540 Installation of Fire Extingusher&Blanket 4 05-Nov-12 08-Nov-12 21-Jan-13 26-Jan-13 63
Electrical /Electrical /Telephone/ELV Rooms 142 06-Sep-12 25-Feb-13 20-Jan-13 25-Apr-13 51
FinishingFinishing Works 142 06-Sep-12 25-Feb-13 20-Jan-13 25-Apr-13 51
Wet WorWet Works 115 06-Sep-12 23-Jan-13 20-Jan-13 09-Feb-13 13
A15900 Block Works 3 06-Sep-12 09-Sep-12 20-Jan-13 22-Jan-13 111
A15860 Installation of Doors& Windows Sub-frame 1 11-Oct-12 11-Oct-12 09-Feb-13 09-Feb-13 97
A15850 Plaster Works 4 10-Oct-12 14-Oct-12 27-Jan-13 30-Jan-13 87
A15870 1st Coat Paint 3 21-Jan-13 23-Jan-13 04-Feb-13 06-Feb-13 11
Fisrt StaFisrt Stage Finishes 26 21-Jan-13 20-Feb-13 16-Feb-13 23-Apr-13 53
A15890 Installation of Doors 2 21-Jan-13 22-Jan-13 16-Feb-13 17-Feb-13 21
A15910 Doors Ironmongery 2 21-Jan-13 22-Jan-13 22-Apr-13 23-Apr-13 77
A15960 Epoxy Paint Works 2 19-Feb-13 20-Feb-13 30-Mar-13 31-Mar-13 33
Second SSecond Stage Finishes 2 21-Feb-13 23-Feb-13 01-Apr-13 02-Apr-13 33
A15880 Final Coat Paint 2 21-Feb-13 23-Feb-13 01-Apr-13 02-Apr-13 33
Final StaFinal Stage Finishes 2 24-Feb-13 25-Feb-13 24-Apr-13 25-Apr-13 51
A15950 Installation of Sinages 2 24-Feb-13 25-Feb-13 24-Apr-13 25-Apr-13 51
MEP WorkMEP Works 133 10-Sep-12 18-Feb-13 23-Jan-13 28-Mar-13 33
HVACHVAC 2 26-Jan-13 27-Jan-13 04-Mar-13 05-Mar-13 32
A15990 Air-Outlet Installation 2 26-Jan-13 27-Jan-13 04-Mar-13 05-Mar-13 32
ElectricalElectrical 133 10-Sep-12 18-Feb-13 23-Jan-13 05-Mar-13 13
A15920 Install Conduits in Wall 2 10-Sep-12 11-Sep-12 23-Jan-13 26-Jan-13 111
A15930 Wiring for Lighting & Power 2 15-Oct-12 16-Oct-12 02-Feb-13 03-Feb-13 88
A15980 Installation of SMDBs 7 26-Jan-13 02-Feb-13 24-Feb-13 03-Mar-13 25
A15940 Installation of Lighting Fittings 2 03-Feb-13 04-Feb-13 04-Mar-13 05-Mar-13 25
A114430 Installation of Access ControlSystem 20 26-Jan-13 17-Feb-13 11-Feb-13 05-Mar-13 14
A114410 Installation of MATC,TV System 20 26-Jan-13 17-Feb-13 11-Feb-13 05-Mar-13 14
A114420 Installation of Telephone System 21 26-Jan-13 18-Feb-13 10-Feb-13 05-Mar-13 13
Fire FighFire Fighting 5 05-Feb-13 10-Feb-13 24-Mar-13 28-Mar-13 40
A15970 Fire Alarm Devices 5 05-Feb-13 10-Feb-13 24-Mar-13 28-Mar-13 40
Room ServRoom Service 130 10-Sep-12 14-Feb-13 23-Jan-13 25-Apr-13 60
FinishingFinishing Works 130 10-Sep-12 14-Feb-13 23-Jan-13 25-Apr-13 60
Wet WorWet Works 115 10-Sep-12 28-Jan-13 23-Jan-13 11-Feb-13 12
A16050 Block Works 2 10-Sep-12 11-Sep-12 23-Jan-13 26-Jan-13 111
A16010 Installation of Doors& Windows Sub-frame 2 15-Oct-12 16-Oct-12 10-Feb-13 11-Feb-13 95
A16000 Plaster Works 4 15-Oct-12 18-Oct-12 31-Jan-13 04-Feb-13 87
A16020 1st Coat Paint 3 26-Jan-13 28-Jan-13 07-Feb-13 10-Feb-13 11
Fisrt StaFisrt Stage Finishes 8 29-Jan-13 06-Feb-13 11-Feb-13 23-Apr-13 65
A16180 Screed Works 2 29-Jan-13 30-Jan-13 11-Feb-13 12-Feb-13 11
A16200 Floor Tiles Work 3 02-Feb-13 04-Feb-13 14-Feb-13 17-Feb-13 11
A16040 Installation of Doors 2 05-Feb-13 06-Feb-13 18-Feb-13 19-Feb-13 11
A16060 Doors Ironmongery 2 05-Feb-13 06-Feb-13 22-Apr-13 23-Apr-13 65
Second SSecond Stage Finishes 5 07-Feb-13 12-Feb-13 28-Mar-13 02-Apr-13 42
A16030 Final Coat Paint 5 07-Feb-13 12-Feb-13 28-Mar-13 02-Apr-13 42
Final StaFinal Stage Finishes 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60
A16170 Installation of Sinages 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60
MEP WorkMEP Works 121 12-Sep-12 06-Feb-13 27-Jan-13 27-Mar-13 42
HVACHVAC 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23
A16210 Air-Outlet Installation 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23
ElectricalElectrical 121 12-Sep-12 06-Feb-13 29-Jan-13 05-Mar-13 23
A16070 Install Conduits in Wall 2 12-Sep-12 13-Sep-12 29-Jan-13 30-Jan-13 113
A16080 Wiring for Lighting & Power 2 20-Oct-12 21-Oct-12 05-Feb-13 06-Feb-13 87
A16090 Installation of Lighting Fittings 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23
PlumbingPlumbing 116 12-Sep-12 31-Jan-13 27-Jan-13 13-Feb-13 11
A16100 Drainge Pipes in Wall 2 12-Sep-12 13-Sep-12 27-Jan-13 28-Jan-13 111
A16130 Water Pipes in Wall 2 12-Sep-12 13-Sep-12 27-Jan-13 28-Jan-13 111
A16110 Drainage&Water Pipes Testing 2 15-Sep-12 16-Sep-12 29-Jan-13 30-Jan-13 111
A16120 Floor Drain Fixning 1 31-Jan-13 31-Jan-13 13-Feb-13 13-Feb-13 11
Fire FighFire Fighting 120 13-Sep-12 06-Feb-13 27-Feb-13 27-Mar-13 42
A16160 Fire Fighting Pipe 2 13-Sep-12 15-Sep-12 27-Feb-13 28-Feb-13 137
A16150 Hydro Static Test for Pipes 2 16-Sep-12 17-Sep-12 02-Mar-13 03-Mar-13 137
A16140 Sprinkler Fixing 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23
A16190 Fire Alarm Devices 2 05-Feb-13 06-Feb-13 26-Mar-13 27-Mar-13 42
StaircaseStaircase 126 27-Aug-12 27-Jan-13 22-Oct-12 02-Apr-13 56
Stair 1Stair 1 112 27-Aug-12 09-Jan-13 22-Oct-12 19-Mar-13 58
A108290 Floor Screed 3 27-Aug-12 29-Aug-12 22-Oct-12 24-Oct-12 48
A108300 Install Handrails 4 20-Nov-12 24-Nov-12 16-Dec-12 19-Dec-12 21
A108310 Ceiling 1st Coat Paint 7 25-Nov-12 03-Dec-12 12-Jan-13 19-Jan-13 39
A108320 Wall 1st Coat Paint 7 04-Dec-12 11-Dec-12 20-Jan-13 28-Jan-13 39
A108330 Install Granite/Terrazo 12 12-Dec-12 25-Dec-12 20-Feb-13 05-Mar-13 58
A108340 Final Coat Paint 12 26-Dec-12 09-Jan-13 06-Mar-13 19-Mar-13 58
Stair 2Stair 2 123 30-Aug-12 27-Jan-13 28-Oct-12 02-Apr-13 56
A108350 Floor Screed 3 30-Aug-12 02-Sep-12 28-Oct-12 30-Oct-12 48
A108360 Install Handrails 4 25-Nov-12 28-Nov-12 20-Dec-12 24-Dec-12 21
A108380 Wall 1st Coat Paint 7 12-Dec-12 19-Dec-12 29-Jan-13 05-Feb-13 39
A108370 Ceiling 1st Coat Paint 7 20-Dec-12 27-Dec-12 06-Feb-13 13-Feb-13 39
A108390 Install Granite/Terrazo 12 29-Dec-12 12-Jan-13 06-Mar-13 19-Mar-13 56
A108400 Final Coat Paint 12 13-Jan-13 27-Jan-13 20-Mar-13 02-Apr-13 56
ApartementsApartements 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21
Studio FlatsStudio Flats 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21
Wet WoWet Works 65 16-Aug-12 04-Nov-12 14-Oct-12 13-Feb-13 83
A34800 Block Works 5 16-Aug-12 23-Aug-12 14-Oct-12 18-Oct-12 48
A34650 Plaster Works 7 24-Sep-12 01-Oct-12 24-Oct-12 03-Nov-12 26
A34680 Installation of Suspended Ceiling Grid (Dry Area) 2 06-Oct-12 07-Oct-12 07-Nov-12 08-Nov-12 26
A35130 Wall Tiles Work (Wet Area) 8 02-Oct-12 10-Oct-12 21-Nov-12 29-Nov-12 40
A34660 Installation of Doors& Windows Sub-frame 2 17-Oct-12 18-Oct-12 12-Feb-13 13-Feb-13 95
A34670 1st Coat Paint 4 31-Oct-12 04-Nov-12 10-Nov-12 13-Nov-12 8
Fisrt StaFisrt Stage Finishes 67 10-Nov-12 30-Jan-13 20-Nov-12 04-Mar-13 28
A34690 Suspended Ceiling Tiles (DryArea) 2 10-Nov-12 11-Nov-12 20-Nov-12 21-Nov-12 8
A34730 Installation of Wardrobes 3 17-Dec-12 19-Dec-12 09-Jan-13 12-Jan-13 19
A35120 Screed Works 5 03-Jan-13 08-Jan-13 13-Jan-13 17-Jan-13 8
A34720 Water Proofing for Wet Area 3 09-Jan-13 12-Jan-13 19-Jan-13 21-Jan-13 8
A34710 Floor & Wall Tiles Work (Dry Area) 4 09-Jan-13 13-Jan-13 28-Feb-13 04-Mar-13 42
A35160 Installation of Suspended Ceiling Grid (Wet Area) 3 13-Jan-13 15-Jan-13 22-Jan-13 26-Jan-13 8
A35150 Suspended Ceiling Tiles (Wet Area) 2 27-Jan-13 28-Jan-13 10-Feb-13 11-Feb-13 12
A35140 Floor Tiles Work (Wet Area) 2 29-Jan-13 30-Jan-13 12-Feb-13 13-Feb-13 12
SecondSecond Stage Finishes 33 07-Feb-13 17-Mar-13 20-Feb-13 26-Mar-13 8
A34740 Installation of Windows&Doors 2 07-Feb-13 09-Feb-13 20-Feb-13 21-Feb-13 11
A34810 Doors Ironmongery 2 07-Feb-13 09-Feb-13 25-Mar-13 26-Mar-13 39
A34750 Installation of Mirrors 2 10-Feb-13 11-Feb-13 25-Mar-13 26-Mar-13 37
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Wall 1st Coat Paint
Ceiling 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
Installation of Doors& Windows Sub-frame
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 31 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A34780 Installation of Balustrades& Handrails 2 10-Feb-13 11-Feb-13 25-Mar-13 26-Mar-13 37
A34790 Installation of Vanity Counter 2 11-Mar-13 12-Mar-13 25-Mar-13 26-Mar-13 12
A34760 Installation of Kitchen Cabinets 3 12-Mar-13 14-Mar-13 24-Mar-13 26-Mar-13 10
A35100 Installation of Toliets Accessories 2 16-Mar-13 17-Mar-13 25-Mar-13 26-Mar-13 8
Final StFinal Stage Finishes 148 18-Mar-13 08-Sep-13 27-Mar-13 02-Oct-13 21
A34700 Final Coat Paint 6 18-Mar-13 24-Mar-13 27-Mar-13 02-Apr-13 8
A34770 Installation of Carpets 4 25-Mar-13 28-Mar-13 22-Apr-13 25-Apr-13 24
A35110 Installation of Sinages 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24
A34820 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 142 25-Aug-12 12-Feb-13 20-Oct-12 02-Apr-13 42
HVACHVAC 132 25-Aug-12 31-Jan-13 28-Oct-12 05-Mar-13 28
A34830 Duct Installation & Insulation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53
A34840 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53
A34850 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53
A34860 FCU Installation 2 02-Sep-12 03-Sep-12 05-Nov-12 06-Nov-12 53
A34870 Air-Outlet Installation 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
ElectricElectrical 133 25-Aug-12 02-Feb-13 21-Oct-12 05-Mar-13 27
A34880 Install Conduits in Wall 3 25-Aug-12 27-Aug-12 21-Oct-12 23-Oct-12 49
A34890 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 28-Oct-12 31-Oct-12 53
A34930 Cable Laying for Low Current System 3 29-Aug-12 01-Sep-12 06-Nov-12 08-Nov-12 57
A34940 Cable Laying for Power 3 29-Aug-12 01-Sep-12 06-Nov-12 08-Nov-12 57
A34900 Wiring for Lighting & Power 3 02-Oct-12 04-Oct-12 04-Nov-12 06-Nov-12 26
A34910 Wiring for Low Current System 3 02-Oct-12 04-Oct-12 04-Nov-12 06-Nov-12 26
A34920 DB installation,Dressing & Termination 6 05-Nov-12 11-Nov-12 14-Nov-12 21-Nov-12 8
A34970 Installation of Sockets 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
A34960 Installation of Lighting Fittings 4 29-Jan-13 02-Feb-13 02-Mar-13 05-Mar-13 27
PlumbinPlumbing 142 25-Aug-12 12-Feb-13 20-Oct-12 26-Mar-13 36
A34980 Drainge Pipes in Wall 4 25-Aug-12 28-Aug-12 20-Oct-12 23-Oct-12 48
A34990 H/L Drainage Pipes Installation 4 25-Aug-12 28-Aug-12 13-Jan-13 16-Jan-13 116
A35000 H/L Hot&Cold Water Pipe Installation 4 25-Aug-12 28-Aug-12 13-Jan-13 16-Jan-13 116
A35050 Water Pipes in Wall 4 25-Aug-12 28-Aug-12 20-Oct-12 23-Oct-12 48
A35010 Drainage&Water Pipes Testing 4 29-Aug-12 02-Sep-12 17-Jan-13 21-Jan-13 116
A35020 ElectricalWater Heater Installation 4 29-Aug-12 02-Sep-12 17-Jan-13 21-Jan-13 116
A35030 Floor Drain Fixning 2 06-Jan-13 07-Jan-13 09-Feb-13 10-Feb-13 28
A35040 Installation of Sanitaryware 3 10-Feb-13 12-Feb-13 24-Mar-13 26-Mar-13 36
Fire FigFire Fighting 134 25-Aug-12 03-Feb-13 31-Oct-12 02-Apr-13 50
A35090 Fire Fighting Pipe 3 25-Aug-12 27-Aug-12 31-Oct-12 03-Nov-12 56
A35080 Hydro Static Test for Pipes 3 28-Aug-12 30-Aug-12 04-Nov-12 06-Nov-12 56
A35070 Sprinkler Fixing 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
A35170 Fire Alarm Devices 3 29-Jan-13 31-Jan-13 24-Mar-13 26-Mar-13 46
A35060 Installation of Fire Extingusher&Blanket 2 02-Feb-13 03-Feb-13 01-Apr-13 02-Apr-13 50
One BedroOne Bedroom Flats 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21
FinishingFinishing Works 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21
Wet WoWet Works 67 09-Aug-12 30-Oct-12 29-Sep-12 17-Feb-13 90
A35330 Block Works 6 09-Aug-12 15-Aug-12 29-Sep-12 04-Oct-12 41
A35180 Plaster Works 7 16-Sep-12 23-Sep-12 15-Oct-12 22-Oct-12 25
A35210 Installation of Suspended Ceiling Grid (Dry Area) 3 30-Sep-12 02-Oct-12 29-Oct-12 31-Oct-12 23
A35660 Wall Tiles Work (Wet Area) 4 11-Oct-12 15-Oct-12 01-Dec-12 05-Dec-12 40
A35190 Installation of Doors& Windows Sub-frame 3 20-Oct-12 22-Oct-12 14-Feb-13 17-Feb-13 95
A35200 1st Coat Paint 7 21-Oct-12 30-Oct-12 01-Nov-12 08-Nov-12 8
Fisrt StaFisrt Stage Finishes 70 12-Nov-12 05-Feb-13 22-Nov-12 09-Mar-13 27
A35220 Suspended Ceiling Tiles (DryArea) 4 12-Nov-12 17-Nov-12 22-Nov-12 26-Nov-12 8
A35260 Installation of Wardrobes 4 12-Dec-12 16-Dec-12 27-Dec-12 31-Dec-12 13
A35650 Screed Works 9 23-Dec-12 02-Jan-13 02-Jan-13 12-Jan-13 8
A35250 Water Proofing for Wet Area 3 03-Jan-13 06-Jan-13 22-Jan-13 26-Jan-13 16
A35240 Floor & Wall Tiles Work (Dry Area) 4 14-Jan-13 17-Jan-13 05-Mar-13 09-Mar-13 42
A35690 Installation of Suspended Ceiling Grid (Wet Area) 4 16-Jan-13 20-Jan-13 27-Jan-13 30-Jan-13 8
A35680 Suspended Ceiling Tiles (Wet Area) 4 21-Jan-13 26-Jan-13 05-Feb-13 09-Feb-13 12
A35670 Floor Tiles Work (Wet Area) 5 31-Jan-13 05-Feb-13 14-Feb-13 19-Feb-13 12
SecondSecond Stage Finishes 29 10-Feb-13 14-Mar-13 23-Feb-13 27-Mar-13 11
A35270 Installation of Windows&Doors 3 10-Feb-13 12-Feb-13 23-Feb-13 25-Feb-13 11
A35340 Doors Ironmongery 3 10-Feb-13 12-Feb-13 25-Mar-13 27-Mar-13 37
A35310 Installation of Balustrades& Handrails 2 13-Feb-13 14-Feb-13 26-Mar-13 27-Mar-13 35
A35280 Installation of Mirrors 3 13-Feb-13 16-Feb-13 25-Mar-13 27-Mar-13 34
A35320 Installation of Vanity Counter 3 07-Mar-13 10-Mar-13 21-Mar-13 24-Mar-13 12
A35290 Installation of Kitchen Cabinets 3 09-Mar-13 11-Mar-13 20-Mar-13 23-Mar-13 10
A35630 Installation of Toliets Accessories 4 11-Mar-13 14-Mar-13 20-Mar-13 24-Mar-13 8
Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21
A35230 Final Coat Paint 5 16-Mar-13 20-Mar-13 28-Mar-13 02-Apr-13 11
A35300 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A35640 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A35350 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 150 16-Aug-12 16-Feb-13 06-Oct-12 02-Apr-13 39
HVACHVAC 135 16-Aug-12 29-Jan-13 16-Oct-12 05-Mar-13 30
A35360 Duct Installation & Insulation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50
A35370 Chilled Water Pipe Installation & Insulation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50
A35380 Condensate Pipe Installation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50
A35390 FCU Installation 2 27-Aug-12 28-Aug-12 24-Oct-12 28-Oct-12 50
A35400 Air-Outlet Installation 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30
ElectricElectrical 136 16-Aug-12 30-Jan-13 11-Oct-12 05-Mar-13 29
A35410 Install Conduits in Wall 3 16-Aug-12 21-Aug-12 11-Oct-12 14-Oct-12 46
A35420 Install Cable Trays & Trunking 4 16-Aug-12 22-Aug-12 16-Oct-12 20-Oct-12 50
A35460 Cable Laying for Low Current System 3 23-Aug-12 26-Aug-12 29-Oct-12 31-Oct-12 55
A35470 Cable Laying for Power 3 23-Aug-12 26-Aug-12 29-Oct-12 31-Oct-12 55
A35430 Wiring for Lighting & Power 3 24-Sep-12 26-Sep-12 23-Oct-12 28-Oct-12 25
A35440 Wiring for Low Current System 3 24-Sep-12 26-Sep-12 23-Oct-12 28-Oct-12 25
A35450 DB installation,Dressing & Termination 6 31-Oct-12 06-Nov-12 20-Nov-12 26-Nov-12 16
A35500 Installation of Sockets 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30
A35490 Installation of Lighting Fittings 4 27-Jan-13 30-Jan-13 02-Mar-13 05-Mar-13 29
PlumbinPlumbing 150 16-Aug-12 16-Feb-13 06-Oct-12 27-Mar-13 34
A35520 H/L Drainage Pipes Installation 4 16-Aug-12 22-Aug-12 08-Jan-13 12-Jan-13 117
A35530 H/L Hot&Cold Water Pipe Installation 4 16-Aug-12 22-Aug-12 08-Jan-13 12-Jan-13 117
A35510 Drainge Pipes in Wall 8 16-Aug-12 27-Aug-12 06-Oct-12 14-Oct-12 41
A35540 Drainage&Water Pipes Testing 4 23-Aug-12 27-Aug-12 13-Jan-13 16-Jan-13 117
A35550 ElectricalWater Heater Installation 4 23-Aug-12 27-Aug-12 13-Jan-13 16-Jan-13 117
A35580 Water Pipes in Wall 8 16-Aug-12 27-Aug-12 06-Oct-12 14-Oct-12 41
A35560 Floor Drain Fixning 2 25-Dec-12 26-Dec-12 14-Feb-13 16-Feb-13 42
A35570 Installation of Sanitaryware 3 13-Feb-13 16-Feb-13 25-Mar-13 27-Mar-13 34
Fire FigFire Fighting 137 16-Aug-12 31-Jan-13 20-Oct-12 02-Apr-13 52
A35620 Fire Fighting Pipe 3 16-Aug-12 21-Aug-12 20-Oct-12 22-Oct-12 53
A35610 Hydro Static Test for Pipes 3 22-Aug-12 25-Aug-12 23-Oct-12 28-Oct-12 53
A35600 Sprinkler Fixing 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30
A35700 Fire Alarm Devices 3 27-Jan-13 29-Jan-13 25-Mar-13 27-Mar-13 49
A35590 Installation of Fire Extingusher&Blanket 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52
Two BedroTwo Bedroom Flats 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21
FinishingFinishing Works 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21
Wet WoWet Works 84 23-Jul-12 01-Nov-12 01-Aug-12 25-Feb-13 95
A35860 Block Works 15 23-Jul-12 08-Aug-12 01-Aug-12 18-Aug-12 8
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
Installation of Doors& Windows Sub-frame
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 32 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A35710 Plaster Works 20 23-Aug-12 15-Sep-12 02-Sep-12 24-Sep-12 8
A35740 Installation of Suspended Ceiling Grid (Dry Area) 9 19-Sep-12 29-Sep-12 29-Sep-12 08-Oct-12 8
A35730 1st Coat Paint 18 30-Sep-12 20-Oct-12 09-Oct-12 31-Oct-12 8
A35720 Installation of Doors& Windows Sub-frame 7 23-Oct-12 01-Nov-12 18-Feb-13 25-Feb-13 95
A36190 Wall Tiles Work (Wet Area) 13 16-Oct-12 01-Nov-12 06-Dec-12 20-Dec-12 40
Fisrt StaFisrt Stage Finishes 75 18-Nov-12 16-Feb-13 27-Nov-12 23-Mar-13 30
A35750 Suspended Ceiling Tiles (DryArea) 12 18-Nov-12 01-Dec-12 27-Nov-12 11-Dec-12 8
A35790 Installation of Wardrobes 8 03-Dec-12 11-Dec-12 12-Dec-12 20-Dec-12 8
A36180 Screed Works 9 12-Dec-12 22-Dec-12 22-Dec-12 31-Dec-12 8
A35780 Water Proofing for Wet Area 9 23-Dec-12 02-Jan-13 20-Jan-13 30-Jan-13 23
A36220 Installation of Suspended Ceiling Grid (Wet Area) 7 21-Jan-13 29-Jan-13 31-Jan-13 07-Feb-13 8
A35770 Floor & Wall Tiles Work (Dry Area) 12 19-Jan-13 02-Feb-13 10-Mar-13 23-Mar-13 42
A36210 Suspended Ceiling Tiles (Wet Area) 10 30-Jan-13 10-Feb-13 09-Feb-13 19-Feb-13 8
A36200 Floor Tiles Work (Wet Area) 5 11-Feb-13 16-Feb-13 20-Feb-13 25-Feb-13 8
SecondSecond Stage Finishes 19 17-Feb-13 10-Mar-13 26-Feb-13 23-Mar-13 11
A35800 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 26-Feb-13 05-Mar-13 8
A35870 Doors Ironmongery 5 20-Feb-13 25-Feb-13 18-Mar-13 23-Mar-13 22
A35840 Installation of Balustrades& Handrails 5 25-Feb-13 02-Mar-13 18-Mar-13 23-Mar-13 18
A35810 Installation of Mirrors 9 25-Feb-13 06-Mar-13 13-Mar-13 23-Mar-13 14
A35850 Installation of Vanity Counter 9 25-Feb-13 06-Mar-13 11-Mar-13 20-Mar-13 12
A35820 Installation of Kitchen Cabinets 10 25-Feb-13 07-Mar-13 09-Mar-13 19-Mar-13 10
A36160 Installation of Toliets Accessories 12 25-Feb-13 10-Mar-13 06-Mar-13 19-Mar-13 8
Final StFinal Stage Finishes 154 11-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21
A35760 Final Coat Paint 9 11-Mar-13 20-Mar-13 24-Mar-13 02-Apr-13 11
A35830 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A36170 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A35880 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 166 09-Aug-12 27-Feb-13 21-Aug-12 02-Apr-13 29
HVACHVAC 154 09-Aug-12 13-Feb-13 18-Sep-12 05-Mar-13 17
A35890 Duct Installation & Insulation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32
A35900 Chilled Water Pipe Installation & Insulation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32
A35910 Condensate Pipe Installation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32
A35920 FCU Installation 2 18-Aug-12 21-Aug-12 26-Sep-12 27-Sep-12 32
A35930 Air-Outlet Installation 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17
ElectricElectrical 155 09-Aug-12 14-Feb-13 29-Aug-12 05-Mar-13 16
A35940 Install Conduits in Wall 3 09-Aug-12 12-Aug-12 29-Aug-12 01-Sep-12 15
A35950 Install Cable Trays & Trunking 4 09-Aug-12 13-Aug-12 18-Sep-12 22-Sep-12 32
A35990 Cable Laying for Low Current System 3 14-Aug-12 16-Aug-12 06-Oct-12 08-Oct-12 43
A36000 Cable Laying for Power 3 14-Aug-12 16-Aug-12 06-Oct-12 08-Oct-12 43
A35960 Wiring for Lighting & Power 3 16-Sep-12 18-Sep-12 25-Sep-12 27-Sep-12 8
A35970 Wiring for Low Current System 3 16-Sep-12 18-Sep-12 25-Sep-12 27-Sep-12 8
A35980 DB installation,Dressing & Termination 6 21-Oct-12 29-Oct-12 05-Dec-12 11-Dec-12 35
A36030 Installation of Sockets 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17
A36020 Installation of Lighting Fittings 4 11-Feb-13 14-Feb-13 02-Mar-13 05-Mar-13 16
PlumbinPlumbing 166 09-Aug-12 27-Feb-13 21-Aug-12 23-Mar-13 20
A36050 H/L Drainage Pipes Installation 4 09-Aug-12 13-Aug-12 21-Jan-13 26-Jan-13 134
A36060 H/L Hot&Cold Water Pipe Installation 4 09-Aug-12 13-Aug-12 21-Jan-13 26-Jan-13 134
A36070 Drainage&Water Pipes Testing 4 14-Aug-12 18-Aug-12 27-Jan-13 30-Jan-13 134
A36110 Water Pipes in Wall 8 09-Aug-12 18-Aug-12 23-Aug-12 01-Sep-12 10
A36040 Drainge Pipes in Wall 10 09-Aug-12 22-Aug-12 21-Aug-12 01-Sep-12 8
A36080 ElectricalWater Heater Installation 4 03-Sep-12 06-Sep-12 27-Jan-13 30-Jan-13 119
A36090 Floor Drain Fixning 2 15-Dec-12 16-Dec-12 20-Feb-13 21-Feb-13 56
A36100 Installation of Sanitaryware 3 25-Feb-13 27-Feb-13 20-Mar-13 23-Mar-13 20
Fire FigFire Fighting 156 09-Aug-12 16-Feb-13 22-Sep-12 02-Apr-13 39
A36150 Fire Fighting Pipe 3 09-Aug-12 12-Aug-12 22-Sep-12 24-Sep-12 35
A36140 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 25-Sep-12 27-Sep-12 35
A36130 Sprinkler Fixing 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17
A36230 Fire Alarm Devices 3 11-Feb-13 13-Feb-13 20-Mar-13 23-Mar-13 32
A36120 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 01-Apr-13 02-Apr-13 39
3rd Floor3rd Floor 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21
Public AreaPublic Area 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8
Garbage RGarbage Room 166 16-Sep-12 03-Apr-13 24-Oct-12 25-Apr-13 19
FinishingFinishing Works 166 16-Sep-12 03-Apr-13 24-Oct-12 25-Apr-13 19
Wet WorWet Works 62 16-Sep-12 29-Nov-12 24-Oct-12 09-Feb-13 58
A16620 Block Works 3 16-Sep-12 18-Sep-12 24-Oct-12 29-Oct-12 33
A16570 Installation of Doors& Windows Sub-frame 1 22-Oct-12 22-Oct-12 09-Feb-13 09-Feb-13 88
A16560 Plaster Works 3 22-Oct-12 24-Oct-12 20-Jan-13 22-Jan-13 72
A16600 Wall Tiles Work 4 30-Oct-12 03-Nov-12 27-Jan-13 30-Jan-13 72
A16580 1st Coat Paint 2 28-Nov-12 29-Nov-12 31-Jan-13 02-Feb-13 52
Fisrt StaFisrt Stage Finishes 7 01-Dec-12 09-Dec-12 04-Feb-13 24-Apr-13 115
A16750 Screed Works 2 01-Dec-12 03-Dec-12 04-Feb-13 05-Feb-13 53
A16770 Floor Tiles Work 2 05-Dec-12 06-Dec-12 07-Feb-13 09-Feb-13 53
A16630 Doors Ironmongery 1 08-Dec-12 08-Dec-12 24-Apr-13 24-Apr-13 116
A16610 Installation of Doors 2 08-Dec-12 09-Dec-12 10-Feb-13 11-Feb-13 53
Second SSecond Stage Finishes 2 01-Apr-13 02-Apr-13 10-Apr-13 11-Apr-13 8
A16590 Final Coat Paint 2 01-Apr-13 02-Apr-13 10-Apr-13 11-Apr-13 8
Final StaFinal Stage Finishes 1 03-Apr-13 03-Apr-13 25-Apr-13 25-Apr-13 19
A16740 Installation of Sinages 1 03-Apr-13 03-Apr-13 25-Apr-13 25-Apr-13 19
MEP WorkMEP Works 66 19-Sep-12 09-Dec-12 30-Oct-12 25-Mar-13 89
ElectricalElectrical 66 19-Sep-12 09-Dec-12 17-Jan-13 28-Feb-13 68
A16640 Install Conduits in Wall 2 19-Sep-12 20-Sep-12 17-Jan-13 19-Jan-13 98
A16650 Wiring for Lighting & Power 2 28-Oct-12 29-Oct-12 23-Jan-13 26-Jan-13 72
A16660 Installation of Lighting Fittings 2 08-Dec-12 09-Dec-12 27-Feb-13 28-Feb-13 68
PlumbingPlumbing 62 19-Sep-12 04-Dec-12 15-Jan-13 06-Feb-13 53
A16670 Drainge Pipes in Wall 2 19-Sep-12 20-Sep-12 15-Jan-13 16-Jan-13 96
A16700 Water Pipes in Wall 2 19-Sep-12 20-Sep-12 15-Jan-13 16-Jan-13 96
A16680 Drainage&Water Pipes Testing 2 22-Sep-12 23-Sep-12 17-Jan-13 19-Jan-13 96
A16690 Floor Drain Fixning 1 04-Dec-12 04-Dec-12 06-Feb-13 06-Feb-13 53
Fire FighFire Fighting 65 20-Sep-12 09-Dec-12 30-Oct-12 25-Mar-13 89
A16730 Fire Fighting Pipe 2 20-Sep-12 22-Sep-12 30-Oct-12 31-Oct-12 32
A16720 Hydro Static Test for Pipes 2 23-Sep-12 24-Sep-12 17-Feb-13 18-Feb-13 120
A16710 Sprinkler Fixing 2 08-Dec-12 09-Dec-12 19-Feb-13 20-Feb-13 61
A16760 Fire Alarm Devices 2 08-Dec-12 09-Dec-12 24-Mar-13 25-Mar-13 89
Corridor &Corridor & Lift Lobby 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8
FinishingFinishing Works 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8
Wet WorWet Works 56 06-Sep-12 12-Nov-12 14-Oct-12 20-Jan-13 56
A16280 Block Works 8 06-Sep-12 15-Sep-12 14-Oct-12 22-Oct-12 32
A16220 Plaster Works 7 14-Oct-12 21-Oct-12 18-Dec-12 25-Dec-12 52
A16240 Installation of Suspended Ceiling Grid 6 29-Oct-12 04-Nov-12 31-Dec-12 07-Jan-13 52
A16250 Suspended Ceiling Tiles 6 05-Nov-12 11-Nov-12 08-Jan-13 14-Jan-13 52
A16540 MDF for Lift Lobby Wall 7 05-Nov-12 12-Nov-12 13-Jan-13 20-Jan-13 56
Fisrt StaFisrt Stage Finishes 12 13-Nov-12 27-Nov-12 21-Jan-13 30-Jan-13 52
A16520 Screed Works 3 13-Nov-12 17-Nov-12 21-Jan-13 23-Jan-13 56
A16230 1st Coat Paint 5 22-Nov-12 27-Nov-12 26-Jan-13 30-Jan-13 52
Second SSecond Stage Finishes 11 28-Nov-12 11-Dec-12 12-Feb-13 13-Feb-13 53
A16260 Installation of Doors 2 28-Nov-12 29-Nov-12 12-Feb-13 13-Feb-13 62
A16290 Doors Ironmongery 2 10-Dec-12 11-Dec-12 12-Feb-13 13-Feb-13 53
Final StaFinal Stage Finishes 9 07-Apr-13 16-Apr-13 16-Apr-13 25-Apr-13 8
A16270 Installation of Carpets 2 07-Apr-13 08-Apr-13 16-Apr-13 17-Apr-13 8
A16530 Fixing of Wall Covering 5 09-Apr-13 14-Apr-13 18-Apr-13 23-Apr-13 8
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Water Pipes in Wall
Drainge Pipes in Wall
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 33 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A16510 Installation of Sinages 2 15-Apr-13 16-Apr-13 24-Apr-13 25-Apr-13 8
MEP WorkMEP Works 55 16-Sep-12 21-Nov-12 23-Oct-12 05-Mar-13 86
HVACHVAC 50 16-Sep-12 14-Nov-12 22-Dec-12 23-Jan-13 57
A16300 Duct Installation & Insulation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79
A16310 Chilled Water Pipe Installation & Insulation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79
A16320 Condensate Pipe Installation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79
A16330 FCU Installation 3 22-Sep-12 24-Sep-12 27-Dec-12 30-Dec-12 79
A16340 Air-Outlet Installation 3 12-Nov-12 14-Nov-12 21-Jan-13 23-Jan-13 57
ElectricalElectrical 52 16-Sep-12 18-Nov-12 16-Dec-12 05-Mar-13 89
A16350 Install Conduits in Wall 2 16-Sep-12 17-Sep-12 16-Dec-12 17-Dec-12 74
A16360 Install Cable Trays & Trunking 2 16-Sep-12 17-Sep-12 22-Dec-12 23-Dec-12 79
A16400 Cable Laying for Low Current System 2 18-Sep-12 19-Sep-12 06-Jan-13 07-Jan-13 89
A16410 Cable Laying for Power 3 18-Sep-12 20-Sep-12 05-Jan-13 07-Jan-13 88
A16370 Wiring for Lighting & Power 3 22-Oct-12 24-Oct-12 27-Dec-12 30-Dec-12 53
A16380 Wiring for Low Current System 4 22-Oct-12 28-Oct-12 26-Dec-12 30-Dec-12 52
A16390 DB installation,Dressing & Termination 6 05-Nov-12 11-Nov-12 08-Jan-13 14-Jan-13 52
A16430 Installation of Lighting Fittings 3 12-Nov-12 14-Nov-12 24-Feb-13 26-Feb-13 85
A16440 Installation of Sockets 5 12-Nov-12 18-Nov-12 28-Feb-13 05-Mar-13 89
PlumbingPlumbing 5 16-Sep-12 20-Sep-12 25-Dec-12 30-Dec-12 82
A16450 H/L Hot&Cold Water Pipe Installation 5 16-Sep-12 20-Sep-12 25-Dec-12 30-Dec-12 82
Fire FighFire Fighting 55 16-Sep-12 21-Nov-12 23-Oct-12 23-Jan-13 52
A16500 Fire Fighting Pipe 4 16-Sep-12 19-Sep-12 23-Oct-12 29-Oct-12 32
A16490 Hydro Static Test for Pipes 4 20-Sep-12 24-Sep-12 26-Dec-12 30-Dec-12 79
A16480 Sprinkler Fixing 4 12-Nov-12 17-Nov-12 15-Jan-13 19-Jan-13 52
A16550 Fire Alarm Devices 5 12-Nov-12 18-Nov-12 19-Jan-13 23-Jan-13 55
A16470 Installation of Fire Extingusher&Blanket 4 18-Nov-12 21-Nov-12 20-Jan-13 23-Jan-13 52
Electrical /Electrical /Telephone/ELV Rooms 167 19-Sep-12 08-Apr-13 19-Jan-13 25-Apr-13 15
FinishingFinishing Works 167 19-Sep-12 08-Apr-13 19-Jan-13 25-Apr-13 15
Wet WorWet Works 62 19-Sep-12 04-Dec-12 19-Jan-13 13-Feb-13 59
A16830 Block Works 3 19-Sep-12 22-Sep-12 19-Jan-13 21-Jan-13 99
A16790 Installation of Doors& Windows Sub-frame 1 28-Oct-12 28-Oct-12 13-Feb-13 13-Feb-13 89
A16780 Plaster Works 4 28-Oct-12 31-Oct-12 26-Jan-13 29-Jan-13 73
A16800 1st Coat Paint 3 01-Dec-12 04-Dec-12 03-Feb-13 05-Feb-13 52
Fisrt StaFisrt Stage Finishes 39 14-Nov-12 31-Dec-12 14-Feb-13 13-Apr-13 86
A16820 Installation of Doors 2 14-Nov-12 17-Nov-12 14-Feb-13 16-Feb-13 75
A16840 Doors Ironmongery 2 12-Dec-12 13-Dec-12 14-Feb-13 16-Feb-13 53
A16890 Epoxy Paint Works 2 30-Dec-12 31-Dec-12 11-Apr-13 13-Apr-13 86
Second SSecond Stage Finishes 2 04-Apr-13 06-Apr-13 14-Apr-13 15-Apr-13 8
A16810 Final Coat Paint 2 04-Apr-13 06-Apr-13 14-Apr-13 15-Apr-13 8
Final StaFinal Stage Finishes 2 07-Apr-13 08-Apr-13 24-Apr-13 25-Apr-13 15
A16880 Installation of Sinages 2 07-Apr-13 08-Apr-13 24-Apr-13 25-Apr-13 15
MEP WorkMEP Works 80 23-Sep-12 29-Dec-12 22-Jan-13 27-Mar-13 74
HVACHVAC 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74
A16920 Air-Outlet Installation 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74
ElectricalElectrical 80 23-Sep-12 29-Dec-12 22-Jan-13 05-Mar-13 55
A16850 Install Conduits in Wall 2 23-Sep-12 24-Sep-12 22-Jan-13 23-Jan-13 99
A16860 Wiring for Lighting & Power 2 01-Nov-12 03-Nov-12 31-Jan-13 02-Feb-13 74
A16910 Installation of SMDBs 7 05-Dec-12 12-Dec-12 21-Feb-13 28-Feb-13 65
A16870 Installation of Lighting Fittings 2 13-Dec-12 15-Dec-12 02-Mar-13 03-Mar-13 65
A114460 Installation of Access ControlSystem 20 05-Dec-12 27-Dec-12 11-Feb-13 05-Mar-13 56
A114440 Installation of MATC,TV System 20 05-Dec-12 27-Dec-12 11-Feb-13 05-Mar-13 56
A114450 Installation of Telephone System 21 05-Dec-12 29-Dec-12 10-Feb-13 05-Mar-13 55
Fire FighFire Fighting 2 16-Dec-12 17-Dec-12 26-Mar-13 27-Mar-13 84
A16900 Fire Alarm Devices 2 16-Dec-12 17-Dec-12 26-Mar-13 27-Mar-13 84
Room ServRoom Service 161 23-Sep-12 04-Apr-13 22-Jan-13 25-Apr-13 18
FinishingFinishing Works 161 23-Sep-12 04-Apr-13 22-Jan-13 25-Apr-13 18
Wet WorWet Works 62 23-Sep-12 08-Dec-12 22-Jan-13 16-Feb-13 58
A16980 Block Works 2 23-Sep-12 24-Sep-12 22-Jan-13 23-Jan-13 99
A16940 Installation of Doors& Windows Sub-frame 1 01-Nov-12 01-Nov-12 16-Feb-13 16-Feb-13 87
A16930 Plaster Works 4 01-Nov-12 05-Nov-12 30-Jan-13 03-Feb-13 73
A16950 1st Coat Paint 3 05-Dec-12 08-Dec-12 06-Feb-13 09-Feb-13 52
Fisrt StaFisrt Stage Finishes 7 09-Dec-12 16-Dec-12 10-Feb-13 24-Apr-13 109
A17110 Screed Works 2 09-Dec-12 10-Dec-12 10-Feb-13 11-Feb-13 52
A17130 Floor Tiles Work 3 12-Dec-12 15-Dec-12 13-Feb-13 16-Feb-13 52
A16970 Installation of Doors 1 16-Dec-12 16-Dec-12 17-Feb-13 17-Feb-13 52
A16990 Doors Ironmongery 1 16-Dec-12 16-Dec-12 24-Apr-13 24-Apr-13 109
Second SSecond Stage Finishes 1 03-Apr-13 03-Apr-13 13-Apr-13 13-Apr-13 8
A16960 Final Coat Paint 1 03-Apr-13 03-Apr-13 13-Apr-13 13-Apr-13 8
Final StaFinal Stage Finishes 1 04-Apr-13 04-Apr-13 25-Apr-13 25-Apr-13 18
A17100 Installation of Sinages 1 04-Apr-13 04-Apr-13 25-Apr-13 25-Apr-13 18
MEP WorkMEP Works 70 25-Sep-12 19-Dec-12 26-Jan-13 30-Mar-13 84
HVACHVAC 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65
A17140 Air-Outlet Installation 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65
ElectricalElectrical 68 25-Sep-12 17-Dec-12 28-Jan-13 05-Mar-13 65
A17000 Install Conduits in Wall 2 25-Sep-12 26-Sep-12 28-Jan-13 29-Jan-13 101
A17010 Wiring for Lighting & Power 2 06-Nov-12 07-Nov-12 04-Feb-13 05-Feb-13 73
A17020 Installation of Lighting Fittings 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65
PlumbingPlumbing 63 25-Sep-12 11-Dec-12 26-Jan-13 12-Feb-13 52
A17030 Drainge Pipes in Wall 2 25-Sep-12 26-Sep-12 26-Jan-13 27-Jan-13 99
A17060 Water Pipes in Wall 2 25-Sep-12 26-Sep-12 26-Jan-13 27-Jan-13 99
A17040 Drainage&Water Pipes Testing 2 27-Sep-12 29-Sep-12 28-Jan-13 29-Jan-13 99
A17050 Floor Drain Fixning 1 11-Dec-12 11-Dec-12 12-Feb-13 12-Feb-13 52
Fire FighFire Fighting 69 26-Sep-12 19-Dec-12 17-Feb-13 30-Mar-13 84
A17090 Fire Fighting Pipe 2 26-Sep-12 27-Sep-12 17-Feb-13 18-Feb-13 117
A17080 Hydro Static Test for Pipes 2 29-Sep-12 30-Sep-12 19-Feb-13 20-Feb-13 117
A17070 Sprinkler Fixing 2 16-Dec-12 17-Dec-12 21-Feb-13 23-Feb-13 56
A17120 Fire Alarm Devices 2 18-Dec-12 19-Dec-12 28-Mar-13 30-Mar-13 84
StaircaseStaircase 142 10-Sep-12 28-Feb-13 31-Oct-12 15-Apr-13 39
Stair 1Stair 1 128 10-Sep-12 12-Feb-13 31-Oct-12 15-Apr-13 53
A108410 Floor Screed 3 10-Sep-12 12-Sep-12 31-Oct-12 03-Nov-12 42
A108420 Install Handrails 4 29-Nov-12 04-Dec-12 25-Dec-12 29-Dec-12 21
A108430 Ceiling 1st Coat Paint 7 29-Dec-12 06-Jan-13 14-Feb-13 21-Feb-13 39
A108440 Wall 1st Coat Paint 7 07-Jan-13 14-Jan-13 23-Feb-13 02-Mar-13 39
A108450 Install Granite/Terrazo 12 15-Jan-13 29-Jan-13 05-Mar-13 18-Mar-13 41
A108460 Final Coat Paint 12 30-Jan-13 12-Feb-13 02-Apr-13 15-Apr-13 53
Stair 2Stair 2 139 13-Sep-12 28-Feb-13 04-Nov-12 15-Apr-13 39
A108470 Floor Screed 3 13-Sep-12 16-Sep-12 04-Nov-12 06-Nov-12 42
A108480 Install Handrails 4 05-Dec-12 09-Dec-12 30-Dec-12 03-Jan-13 21
A108490 Ceiling 1st Coat Paint 7 15-Jan-13 22-Jan-13 03-Mar-13 10-Mar-13 39
A108500 Wall 1st Coat Paint 7 23-Jan-13 31-Jan-13 11-Mar-13 18-Mar-13 39
A108510 Install Granite/Terrazo 12 02-Feb-13 14-Feb-13 19-Mar-13 01-Apr-13 39
A108520 Final Coat Paint 12 16-Feb-13 28-Feb-13 02-Apr-13 15-Apr-13 39
ApartementsApartements 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21
Studio FlatsStudio Flats 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21
FinishingFinishing Works 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21
Wet WoWet Works 62 01-Sep-12 13-Nov-12 08-Oct-12 17-Feb-13 78
A36390 Block Works 5 01-Sep-12 05-Sep-12 08-Oct-12 13-Oct-12 32
A36250 Installation of Doors& Windows Sub-frame 1 06-Oct-12 06-Oct-12 17-Feb-13 17-Feb-13 109
A36240 Plaster Works 7 06-Oct-12 13-Oct-12 28-Oct-12 04-Nov-12 17
A36270 Installation of Suspended Ceiling Grid (Dry Area) 2 17-Oct-12 18-Oct-12 08-Nov-12 10-Nov-12 17
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 34 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A36720 Wall Tiles Work (Wet Area) 8 14-Oct-12 22-Oct-12 21-Nov-12 29-Nov-12 30
A36260 1st Coat Paint 3 11-Nov-12 13-Nov-12 11-Nov-12 13-Nov-12 0
Fisrt StaFisrt Stage Finishes 73 14-Nov-12 11-Feb-13 14-Nov-12 17-Mar-13 29
A36280 Suspended Ceiling Tiles (DryArea) 6 14-Nov-12 21-Nov-12 14-Nov-12 21-Nov-12 0
A36320 Installation of Wardrobes 2 22-Nov-12 24-Nov-12 05-Dec-12 06-Dec-12 10
A36710 Screed Works 5 25-Nov-12 29-Nov-12 19-Dec-12 24-Dec-12 20
A36310 Water Proofing for Wet Area 3 01-Dec-12 04-Dec-12 25-Dec-12 27-Dec-12 20
A36300 Floor & Wall Tiles Work (Dry Area) 4 01-Dec-12 05-Dec-12 13-Mar-13 17-Mar-13 85
A36750 Installation of Suspended Ceiling Grid (Wet Area) 3 05-Dec-12 08-Dec-12 26-Jan-13 28-Jan-13 42
A36740 Suspended Ceiling Tiles (Wet Area) 2 07-Feb-13 09-Feb-13 07-Feb-13 09-Feb-13 0
A36730 Floor Tiles Work (Wet Area) 2 10-Feb-13 11-Feb-13 10-Feb-13 11-Feb-13 0
SecondSecond Stage Finishes 35 12-Feb-13 24-Mar-13 18-Feb-13 02-Apr-13 8
A36330 Installation of Windows&Doors 2 12-Feb-13 13-Feb-13 18-Feb-13 19-Feb-13 5
A36400 Doors Ironmongery 2 12-Feb-13 13-Feb-13 01-Apr-13 02-Apr-13 41
A36340 Installation of Mirrors 2 14-Feb-13 16-Feb-13 20-Mar-13 21-Mar-13 29
A36370 Installation of Balustrades& Handrails 2 14-Feb-13 16-Feb-13 01-Apr-13 02-Apr-13 39
A36380 Installation of Vanity Counter 2 18-Mar-13 19-Mar-13 01-Apr-13 02-Apr-13 12
A36350 Installation of Kitchen Cabinets 2 19-Mar-13 20-Mar-13 01-Apr-13 02-Apr-13 11
A36690 Installation of Toliets Accessories 2 23-Mar-13 24-Mar-13 01-Apr-13 02-Apr-13 8
Final StFinal Stage Finishes 142 25-Mar-13 08-Sep-13 03-Apr-13 02-Oct-13 21
A36290 Final Coat Paint 6 25-Mar-13 31-Mar-13 03-Apr-13 09-Apr-13 8
A36360 Installation of Carpets 4 01-Apr-13 04-Apr-13 22-Apr-13 25-Apr-13 18
A36700 Installation of Sinages 7 28-Mar-13 04-Apr-13 18-Apr-13 25-Apr-13 18
A36410 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 135 06-Sep-12 17-Feb-13 21-Oct-12 09-Apr-13 44
HVACHVAC 131 06-Sep-12 12-Feb-13 29-Oct-12 05-Mar-13 18
A36420 Duct Installation & Insulation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43
A36430 Chilled Water Pipe Installation & Insulation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43
A36440 Condensate Pipe Installation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43
A36450 FCU Installation 2 15-Sep-12 16-Sep-12 06-Nov-12 07-Nov-12 43
A36460 Air-Outlet Installation 3 10-Feb-13 12-Feb-13 03-Mar-13 05-Mar-13 18
ElectricElectrical 134 06-Sep-12 16-Feb-13 22-Oct-12 05-Mar-13 15
A36470 Install Conduits in Wall 3 06-Sep-12 09-Sep-12 22-Oct-12 24-Oct-12 39
A36480 Install Cable Trays & Trunking 4 06-Sep-12 10-Sep-12 29-Oct-12 01-Nov-12 43
A36520 Cable Laying for Low Current System 3 11-Sep-12 13-Sep-12 07-Nov-12 10-Nov-12 47
A36530 Cable Laying for Power 3 11-Sep-12 13-Sep-12 07-Nov-12 10-Nov-12 47
A36490 Wiring for Lighting & Power 3 14-Oct-12 16-Oct-12 05-Nov-12 07-Nov-12 17
A36500 Wiring for Low Current System 3 14-Oct-12 16-Oct-12 05-Nov-12 07-Nov-12 17
A36510 DB installation,Dressing & Termination 6 14-Nov-12 21-Nov-12 14-Nov-12 21-Nov-12 0
A36560 Installation of Sockets 3 10-Feb-13 12-Feb-13 03-Mar-13 05-Mar-13 18
A36550 Installation of Lighting Fittings 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15
PlumbinPlumbing 135 06-Sep-12 17-Feb-13 21-Oct-12 02-Apr-13 38
A36580 H/L Drainage Pipes Installation 4 06-Sep-12 10-Sep-12 15-Jan-13 19-Jan-13 107
A36590 H/L Hot&Cold Water Pipe Installation 4 06-Sep-12 10-Sep-12 15-Jan-13 19-Jan-13 107
A36640 Water Pipes in Wall 4 06-Sep-12 10-Sep-12 21-Oct-12 24-Oct-12 38
A36600 Drainage&Water Pipes Testing 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107
A36610 ElectricalWater Heater Installation 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107
A36570 Drainge Pipes in Wall 4 13-Sep-12 17-Sep-12 21-Oct-12 24-Oct-12 32
A36620 Floor Drain Fixning 2 27-Nov-12 28-Nov-12 06-Feb-13 07-Feb-13 58
A36630 Installation of Sanitaryware 3 14-Feb-13 17-Feb-13 31-Mar-13 02-Apr-13 38
Fire FigFire Fighting 120 23-Sep-12 16-Feb-13 01-Nov-12 09-Apr-13 45
A36680 Fire Fighting Pipe 3 23-Sep-12 25-Sep-12 01-Nov-12 04-Nov-12 32
A36670 Hydro Static Test for Pipes 3 26-Sep-12 29-Sep-12 05-Nov-12 07-Nov-12 32
A36660 Sprinkler Fixing 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17
A36760 Fire Alarm Devices 3 11-Feb-13 13-Feb-13 31-Mar-13 02-Apr-13 41
A36650 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 08-Apr-13 09-Apr-13 45
One BedroOne Bedroom Flats 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21
FinishingFinishing Works 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21
Wet WoWet Works 64 26-Aug-12 10-Nov-12 15-Sep-12 19-Feb-13 83
A36920 Block Works 5 26-Aug-12 30-Aug-12 15-Sep-12 19-Sep-12 17
A36780 Installation of Doors& Windows Sub-frame 1 27-Sep-12 27-Sep-12 19-Feb-13 19-Feb-13 118
A36770 Plaster Works 7 27-Sep-12 04-Oct-12 17-Oct-12 24-Oct-12 17
A36800 Installation of Suspended Ceiling Grid (Dry Area) 3 11-Oct-12 14-Oct-12 31-Oct-12 03-Nov-12 15
A37250 Wall Tiles Work (Wet Area) 4 23-Oct-12 29-Oct-12 01-Dec-12 05-Dec-12 30
A36790 1st Coat Paint 6 04-Nov-12 10-Nov-12 04-Nov-12 10-Nov-12 0
Fisrt StaFisrt Stage Finishes 72 22-Nov-12 17-Feb-13 22-Nov-12 21-Mar-13 28
A36810 Suspended Ceiling Tiles (DryArea) 4 22-Nov-12 26-Nov-12 22-Nov-12 26-Nov-12 0
A36850 Installation of Wardrobes 4 27-Nov-12 01-Dec-12 08-Dec-12 11-Dec-12 8
A37240 Screed Works 9 03-Dec-12 12-Dec-12 18-Dec-12 27-Dec-12 13
A36840 Water Proofing for Wet Area 3 13-Dec-12 16-Dec-12 29-Dec-12 31-Dec-12 13
A36830 Floor & Wall Tiles Work (Dry Area) 4 13-Dec-12 17-Dec-12 18-Mar-13 21-Mar-13 79
A37280 Installation of Suspended Ceiling Grid (Wet Area) 4 17-Dec-12 20-Dec-12 29-Jan-13 02-Feb-13 35
A37270 Suspended Ceiling Tiles (Wet Area) 4 03-Feb-13 06-Feb-13 03-Feb-13 06-Feb-13 0
A37260 Floor Tiles Work (Wet Area) 5 12-Feb-13 17-Feb-13 12-Feb-13 17-Feb-13 0
SecondSecond Stage Finishes 28 18-Feb-13 21-Mar-13 20-Feb-13 09-Apr-13 16
A36860 Installation of Windows&Doors 3 18-Feb-13 20-Feb-13 20-Feb-13 23-Feb-13 2
A36930 Doors Ironmongery 3 18-Feb-13 20-Feb-13 07-Apr-13 09-Apr-13 41
A36900 Installation of Balustrades& Handrails 2 21-Feb-13 23-Feb-13 08-Apr-13 09-Apr-13 39
A36870 Installation of Mirrors 3 21-Feb-13 24-Feb-13 23-Mar-13 25-Mar-13 25
A36910 Installation of Vanity Counter 3 14-Mar-13 17-Mar-13 28-Mar-13 31-Mar-13 12
A36880 Installation of Kitchen Cabinets 3 16-Mar-13 18-Mar-13 28-Mar-13 31-Mar-13 11
A37220 Installation of Toliets Accessories 4 18-Mar-13 21-Mar-13 27-Mar-13 31-Mar-13 8
Final StFinal Stage Finishes 144 23-Mar-13 08-Sep-13 10-Apr-13 02-Oct-13 21
A36820 Final Coat Paint 5 23-Mar-13 27-Mar-13 10-Apr-13 15-Apr-13 16
A36890 Installation of Carpets 4 28-Mar-13 01-Apr-13 22-Apr-13 25-Apr-13 21
A37230 Installation of Sinages 7 25-Mar-13 01-Apr-13 18-Apr-13 25-Apr-13 21
A36940 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 146 01-Sep-12 24-Feb-13 20-Sep-12 15-Apr-13 43
HVACHVAC 134 01-Sep-12 10-Feb-13 18-Oct-12 05-Mar-13 20
A36950 Duct Installation & Insulation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41
A36960 Chilled Water Pipe Installation & Insulation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41
A36970 Condensate Pipe Installation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41
A36980 FCU Installation 2 09-Sep-12 10-Sep-12 29-Oct-12 30-Oct-12 41
A36990 Air-Outlet Installation 3 07-Feb-13 10-Feb-13 03-Mar-13 05-Mar-13 20
ElectricElectrical 135 01-Sep-12 11-Feb-13 14-Oct-12 05-Mar-13 19
A37000 Install Conduits in Wall 3 01-Sep-12 03-Sep-12 14-Oct-12 16-Oct-12 37
A37010 Install Cable Trays & Trunking 4 01-Sep-12 04-Sep-12 18-Oct-12 22-Oct-12 41
A37050 Cable Laying for Low Current System 3 05-Sep-12 08-Sep-12 31-Oct-12 03-Nov-12 46
A37060 Cable Laying for Power 3 05-Sep-12 08-Sep-12 31-Oct-12 03-Nov-12 46
A37020 Wiring for Lighting & Power 3 06-Oct-12 08-Oct-12 28-Oct-12 30-Oct-12 17
A37030 Wiring for Low Current System 3 06-Oct-12 08-Oct-12 28-Oct-12 30-Oct-12 17
A37040 DB installation,Dressing & Termination 6 11-Nov-12 18-Nov-12 20-Nov-12 26-Nov-12 7
A37090 Installation of Sockets 3 07-Feb-13 10-Feb-13 03-Mar-13 05-Mar-13 20
A37080 Installation of Lighting Fittings 4 07-Feb-13 11-Feb-13 25-Feb-13 28-Feb-13 15
PlumbinPlumbing 146 01-Sep-12 24-Feb-13 08-Oct-12 09-Apr-13 38
A37110 H/L Drainage Pipes Installation 4 01-Sep-12 04-Sep-12 10-Jan-13 14-Jan-13 108
A37120 H/L Hot&Cold Water Pipe Installation 4 01-Sep-12 04-Sep-12 19-Jan-13 22-Jan-13 115
A37130 Drainage&Water Pipes Testing 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115
A37140 ElectricalWater Heater Installation 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Drainge Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 35 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A37170 Water Pipes in Wall 8 01-Sep-12 09-Sep-12 08-Oct-12 16-Oct-12 32
A37100 Drainge Pipes in Wall 8 04-Sep-12 12-Sep-12 08-Oct-12 16-Oct-12 29
A37150 Floor Drain Fixning 3 05-Dec-12 08-Dec-12 11-Feb-13 13-Feb-13 56
A37160 Installation of Sanitaryware 3 21-Feb-13 24-Feb-13 07-Apr-13 09-Apr-13 38
Fire FigFire Fighting 136 01-Sep-12 12-Feb-13 20-Sep-12 15-Apr-13 53
A37210 Fire Fighting Pipe 3 01-Sep-12 03-Sep-12 20-Sep-12 23-Sep-12 17
A37200 Hydro Static Test for Pipes 3 04-Sep-12 06-Sep-12 28-Oct-12 30-Oct-12 44
A37190 Sprinkler Fixing 3 07-Feb-13 10-Feb-13 27-Feb-13 02-Mar-13 17
A37290 Fire Alarm Devices 3 07-Feb-13 10-Feb-13 27-Mar-13 30-Mar-13 41
A37180 Installation of Fire Extingusher&Blanket 2 11-Feb-13 12-Feb-13 14-Apr-13 15-Apr-13 53
Two BedroTwo Bedroom Flats 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21
FinishingFinishing Works 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21
Wet WoWet Works 82 06-Aug-12 13-Nov-12 06-Aug-12 23-Feb-13 83
A37450 Block Works 15 06-Aug-12 25-Aug-12 06-Aug-12 25-Aug-12 0
A37310 Installation of Doors& Windows Sub-frame 7 04-Sep-12 11-Sep-12 16-Feb-13 23-Feb-13 135
A37300 Plaster Works 20 04-Sep-12 26-Sep-12 04-Sep-12 26-Sep-12 0
A37330 Installation of Suspended Ceiling Grid (Dry Area) 9 01-Oct-12 10-Oct-12 01-Oct-12 10-Oct-12 0
A37320 1st Coat Paint 18 11-Oct-12 03-Nov-12 11-Oct-12 03-Nov-12 0
A37780 Wall Tiles Work (Wet Area) 13 30-Oct-12 13-Nov-12 06-Dec-12 20-Dec-12 30
Fisrt StaFisrt Stage Finishes 73 27-Nov-12 23-Feb-13 27-Nov-12 04-Apr-13 35
A37340 Suspended Ceiling Tiles (DryArea) 12 27-Nov-12 11-Dec-12 27-Nov-12 11-Dec-12 0
A37380 Installation of Wardrobes 8 12-Dec-12 20-Dec-12 12-Dec-12 20-Dec-12 0
A37770 Screed Works 9 22-Dec-12 31-Dec-12 22-Dec-12 31-Dec-12 0
A37370 Water Proofing for Wet Area 9 02-Jan-13 12-Jan-13 02-Jan-13 12-Jan-13 0
A37360 Floor & Wall Tiles Work (Dry Area) 12 02-Jan-13 15-Jan-13 23-Mar-13 04-Apr-13 67
A37810 Installation of Suspended Ceiling Grid (Wet Area) 7 13-Jan-13 20-Jan-13 13-Jan-13 20-Jan-13 0
A37800 Suspended Ceiling Tiles (Wet Area) 10 21-Jan-13 02-Feb-13 21-Jan-13 02-Feb-13 0
A37790 Floor Tiles Work (Wet Area) 5 18-Feb-13 23-Feb-13 18-Feb-13 23-Feb-13 0
SecondSecond Stage Finishes 19 24-Feb-13 17-Mar-13 24-Feb-13 04-Apr-13 16
A37390 Installation of Windows&Doors 7 24-Feb-13 03-Mar-13 24-Feb-13 03-Mar-13 0
A37460 Doors Ironmongery 6 27-Feb-13 05-Mar-13 30-Mar-13 04-Apr-13 26
A37430 Installation of Balustrades& Handrails 5 04-Mar-13 09-Mar-13 31-Mar-13 04-Apr-13 23
A37400 Installation of Mirrors 9 04-Mar-13 13-Mar-13 26-Mar-13 04-Apr-13 19
A37440 Installation of Vanity Counter 9 04-Mar-13 13-Mar-13 18-Mar-13 27-Mar-13 12
A37410 Installation of Kitchen Cabinets 10 04-Mar-13 14-Mar-13 17-Mar-13 27-Mar-13 11
A37750 Installation of Toliets Accessories 12 04-Mar-13 17-Mar-13 13-Mar-13 26-Mar-13 8
Final StFinal Stage Finishes 148 18-Mar-13 08-Sep-13 06-Apr-13 02-Oct-13 21
A37350 Final Coat Paint 9 18-Mar-13 27-Mar-13 06-Apr-13 15-Apr-13 16
A37420 Installation of Carpets 4 28-Mar-13 01-Apr-13 22-Apr-13 25-Apr-13 21
A37760 Installation of Sinages 7 25-Mar-13 01-Apr-13 18-Apr-13 25-Apr-13 21
A37470 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 160 26-Aug-12 06-Mar-13 26-Aug-12 15-Apr-13 34
HVACHVAC 135 26-Aug-12 05-Feb-13 20-Sep-12 05-Mar-13 24
A37480 Duct Installation & Insulation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22
A37490 Chilled Water Pipe Installation & Insulation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22
A37500 Condensate Pipe Installation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22
A37510 FCU Installation 2 03-Sep-12 04-Sep-12 29-Sep-12 30-Sep-12 22
A37520 Air-Outlet Installation 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24
ElectricElectrical 136 26-Aug-12 06-Feb-13 01-Sep-12 05-Mar-13 23
A37530 Install Conduits in Wall 3 26-Aug-12 28-Aug-12 01-Sep-12 03-Sep-12 5
A37540 Install Cable Trays & Trunking 4 26-Aug-12 29-Aug-12 20-Sep-12 24-Sep-12 22
A37580 Cable Laying for Low Current System 3 30-Aug-12 02-Sep-12 08-Oct-12 10-Oct-12 33
A37590 Cable Laying for Power 3 30-Aug-12 02-Sep-12 08-Oct-12 10-Oct-12 33
A37550 Wiring for Lighting & Power 3 27-Sep-12 30-Sep-12 27-Sep-12 30-Sep-12 0
A37560 Wiring for Low Current System 3 27-Sep-12 30-Sep-12 27-Sep-12 30-Sep-12 0
A37570 DB installation,Dressing & Termination 6 04-Nov-12 10-Nov-12 05-Dec-12 11-Dec-12 25
A37620 Installation of Sockets 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24
A37610 Installation of Lighting Fittings 4 03-Feb-13 06-Feb-13 20-Feb-13 24-Feb-13 15
PlumbinPlumbing 160 26-Aug-12 06-Mar-13 26-Aug-12 06-Mar-13 0
A37640 H/L Drainage Pipes Installation 4 26-Aug-12 29-Aug-12 03-Jan-13 07-Jan-13 107
A37650 H/L Hot&Cold Water Pipe Installation 4 26-Aug-12 29-Aug-12 03-Jan-13 07-Jan-13 107
A37630 Drainge Pipes in Wall 8 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0
A37660 Drainage&Water Pipes Testing 4 30-Aug-12 03-Sep-12 08-Jan-13 12-Jan-13 107
A37670 ElectricalWater Heater Installation 4 30-Aug-12 03-Sep-12 08-Jan-13 12-Jan-13 107
A37700 Water Pipes in Wall 8 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0
A37680 Floor Drain Fixning 3 24-Dec-12 26-Dec-12 17-Feb-13 19-Feb-13 45
A37690 Installation of Sanitaryware 3 04-Mar-13 06-Mar-13 04-Mar-13 06-Mar-13 0
Fire FigFire Fighting 129 04-Sep-12 07-Feb-13 24-Sep-12 15-Apr-13 57
A37740 Fire Fighting Pipe 3 04-Sep-12 06-Sep-12 24-Sep-12 26-Sep-12 17
A37730 Hydro Static Test for Pipes 3 08-Sep-12 10-Sep-12 27-Sep-12 30-Sep-12 17
A37720 Sprinkler Fixing 3 03-Feb-13 05-Feb-13 24-Feb-13 26-Feb-13 18
A37820 Fire Alarm Devices 3 03-Feb-13 05-Feb-13 24-Mar-13 26-Mar-13 42
A37710 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 14-Apr-13 15-Apr-13 57
4th Floor4th Floor 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21
Public AreaPublic Area 167 19-Sep-12 08-Apr-13 07-Nov-12 25-Apr-13 15
Garbage RGarbage Room 129 29-Sep-12 04-Mar-13 15-Jan-13 25-Apr-13 45
FinishingFinishing Works 129 29-Sep-12 04-Mar-13 15-Jan-13 25-Apr-13 45
Wet WorWet Works 43 29-Sep-12 20-Nov-12 15-Jan-13 22-Apr-13 128
A17550 Block Works 3 29-Sep-12 01-Oct-12 15-Jan-13 17-Jan-13 88
A17500 Installation of Doors& Windows Sub-frame 1 07-Nov-12 07-Nov-12 22-Apr-13 22-Apr-13 138
A17490 Plaster Works 3 07-Nov-12 10-Nov-12 23-Jan-13 27-Jan-13 63
A17530 Wall Tiles Work 4 13-Nov-12 18-Nov-12 30-Jan-13 03-Feb-13 63
A17510 1st Coat Paint 2 19-Nov-12 20-Nov-12 04-Feb-13 05-Feb-13 63
Fisrt StaFisrt Stage Finishes 85 21-Nov-12 03-Mar-13 23-Feb-13 24-Apr-13 45
A17680 Screed Works 2 21-Nov-12 22-Nov-12 23-Feb-13 24-Feb-13 77
A17700 Floor Tiles Work 2 25-Nov-12 26-Nov-12 26-Feb-13 27-Feb-13 77
A17560 Doors Ironmongery 1 02-Mar-13 02-Mar-13 24-Apr-13 24-Apr-13 46
A17540 Installation of Doors 2 02-Mar-13 03-Mar-13 23-Apr-13 24-Apr-13 45
Second SSecond Stage Finishes 2 29-Nov-12 01-Dec-12 07-Apr-13 08-Apr-13 107
A17520 Final Coat Paint 2 29-Nov-12 01-Dec-12 07-Apr-13 08-Apr-13 107
Final StaFinal Stage Finishes 1 04-Mar-13 04-Mar-13 25-Apr-13 25-Apr-13 45
A17670 Installation of Sinages 1 04-Mar-13 04-Mar-13 25-Apr-13 25-Apr-13 45
MEP WorkMEP Works 47 02-Oct-12 28-Nov-12 19-Jan-13 06-Apr-13 107
ElectricalElectrical 47 02-Oct-12 28-Nov-12 21-Jan-13 05-Mar-13 80
A17570 Install Conduits in Wall 2 02-Oct-12 03-Oct-12 21-Jan-13 22-Jan-13 90
A17580 Wiring for Lighting & Power 2 11-Nov-12 12-Nov-12 28-Jan-13 29-Jan-13 63
A17590 Installation of Lighting Fittings 2 27-Nov-12 28-Nov-12 04-Mar-13 05-Mar-13 80
PlumbingPlumbing 43 02-Oct-12 24-Nov-12 19-Jan-13 25-Feb-13 77
A17600 Drainge Pipes in Wall 2 02-Oct-12 03-Oct-12 19-Jan-13 20-Jan-13 88
A17630 Water Pipes in Wall 2 02-Oct-12 03-Oct-12 19-Jan-13 20-Jan-13 88
A17610 Drainage&Water Pipes Testing 2 04-Oct-12 06-Oct-12 21-Jan-13 22-Jan-13 88
A17620 Floor Drain Fixning 1 24-Nov-12 24-Nov-12 25-Feb-13 25-Feb-13 77
Fire FighFire Fighting 46 03-Oct-12 28-Nov-12 25-Feb-13 06-Apr-13 107
A17660 Fire Fighting Pipe 2 03-Oct-12 04-Oct-12 25-Feb-13 26-Feb-13 118
A17650 Hydro Static Test for Pipes 2 06-Oct-12 07-Oct-12 02-Mar-13 03-Mar-13 120
A17640 Sprinkler Fixing 2 27-Nov-12 28-Nov-12 04-Mar-13 05-Mar-13 80
A17690 Fire Alarm Devices 2 27-Nov-12 28-Nov-12 04-Apr-13 06-Apr-13 107
Corridor &Corridor & Lift Lobby 167 19-Sep-12 08-Apr-13 15-Dec-12 25-Apr-13 15
FinishingFinishing Works 167 19-Sep-12 08-Apr-13 15-Dec-12 25-Apr-13 15
Wet WorWet Works 120 19-Sep-12 12-Feb-13 15-Dec-12 02-Apr-13 42
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Water Pipes in Wall
Drainge Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Wall Tiles Work (Wet Area)
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 36 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A17210 Block Works 8 19-Sep-12 27-Sep-12 15-Dec-12 23-Dec-12 70
A17150 Plaster Works 7 30-Oct-12 06-Nov-12 26-Dec-12 03-Jan-13 47
A17170 Installation of Suspended Ceiling Grid 6 12-Nov-12 19-Nov-12 09-Jan-13 15-Jan-13 47
A17180 Suspended Ceiling Tiles 6 05-Feb-13 11-Feb-13 21-Feb-13 27-Feb-13 14
A17470 MDF for Lift Lobby Wall 7 05-Feb-13 12-Feb-13 26-Mar-13 02-Apr-13 42
Fisrt StaFisrt Stage Finishes 12 13-Feb-13 26-Feb-13 03-Apr-13 11-Apr-13 38
A17450 Screed Works 3 13-Feb-13 16-Feb-13 03-Apr-13 06-Apr-13 42
A17160 1st Coat Paint 5 21-Feb-13 26-Feb-13 07-Apr-13 11-Apr-13 38
Second SSecond Stage Finishes 2 27-Feb-13 28-Feb-13 20-Apr-13 25-Apr-13 48
A17190 Installation of Doors 2 27-Feb-13 28-Feb-13 20-Apr-13 21-Apr-13 44
A17220 Doors Ironmongery 2 27-Feb-13 28-Feb-13 24-Apr-13 25-Apr-13 48
Final StaFinal Stage Finishes 12 26-Mar-13 08-Apr-13 13-Apr-13 25-Apr-13 15
A17200 Installation of Carpets 4 26-Mar-13 30-Mar-13 13-Apr-13 16-Apr-13 15
A17460 Fixing of Wall Covering 5 31-Mar-13 04-Apr-13 17-Apr-13 22-Apr-13 15
A17440 Installation of Sinages 3 06-Apr-13 08-Apr-13 23-Apr-13 25-Apr-13 15
MEP WorkMEP Works 119 29-Sep-12 20-Feb-13 24-Dec-12 06-Apr-13 38
HVACHVAC 114 29-Sep-12 14-Feb-13 30-Dec-12 05-Mar-13 16
A17240 Chilled Water Pipe Installation & Insulation 5 29-Sep-12 03-Oct-12 30-Dec-12 05-Jan-13 75
A17250 Condensate Pipe Installation 5 29-Sep-12 03-Oct-12 30-Dec-12 05-Jan-13 75
A17230 Duct Installation & Insulation 5 03-Oct-12 08-Oct-12 30-Dec-12 05-Jan-13 71
A17260 FCU Installation 3 09-Oct-12 11-Oct-12 06-Jan-13 08-Jan-13 71
A17270 Air-Outlet Installation 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
ElectricalElectrical 116 29-Sep-12 17-Feb-13 24-Dec-12 05-Mar-13 14
A17280 Install Conduits in Wall 2 29-Sep-12 30-Sep-12 24-Dec-12 25-Dec-12 70
A17290 Install Cable Trays & Trunking 2 29-Sep-12 30-Sep-12 30-Dec-12 31-Dec-12 75
A17330 Cable Laying for Low Current System 2 01-Oct-12 02-Oct-12 14-Jan-13 15-Jan-13 85
A17340 Cable Laying for Power 3 01-Oct-12 03-Oct-12 13-Jan-13 15-Jan-13 84
A17300 Wiring for Lighting & Power 3 07-Nov-12 10-Nov-12 06-Jan-13 08-Jan-13 48
A17310 Wiring for Low Current System 4 07-Nov-12 11-Nov-12 05-Jan-13 08-Jan-13 47
A17320 DB installation,Dressing & Termination 6 20-Nov-12 26-Nov-12 21-Feb-13 27-Feb-13 77
A17360 Installation of Lighting Fittings 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
A17370 Installation of Sockets 5 12-Feb-13 17-Feb-13 28-Feb-13 05-Mar-13 14
PlumbingPlumbing 5 29-Sep-12 03-Oct-12 03-Jan-13 08-Jan-13 78
A17380 H/L Hot&Cold Water Pipe Installation 5 29-Sep-12 03-Oct-12 03-Jan-13 08-Jan-13 78
Fire FighFire Fighting 119 29-Sep-12 20-Feb-13 30-Dec-12 06-Apr-13 38
A17430 Fire Fighting Pipe 4 29-Sep-12 02-Oct-12 30-Dec-12 03-Jan-13 75
A17420 Hydro Static Test for Pipes 4 03-Oct-12 07-Oct-12 05-Jan-13 08-Jan-13 75
A17410 Sprinkler Fixing 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15
A17480 Fire Alarm Devices 5 12-Feb-13 17-Feb-13 01-Apr-13 06-Apr-13 41
A17400 Installation of Fire Extingusher&Blanket 4 17-Feb-13 20-Feb-13 02-Apr-13 06-Apr-13 38
Electrical /Electrical /Telephone/ELV Rooms 127 02-Oct-12 05-Mar-13 23-Jan-13 25-Apr-13 44
FinishingFinishing Works 127 02-Oct-12 05-Mar-13 23-Jan-13 25-Apr-13 44
Wet WorWet Works 43 02-Oct-12 24-Nov-12 23-Jan-13 21-Apr-13 124
A17760 Block Works 3 02-Oct-12 04-Oct-12 23-Jan-13 27-Jan-13 92
A17720 Installation of Doors& Windows Sub-frame 1 11-Nov-12 11-Nov-12 21-Apr-13 21-Apr-13 134
A17710 Plaster Works 4 11-Nov-12 14-Nov-12 30-Jan-13 03-Feb-13 65
A17730 1st Coat Paint 3 21-Nov-12 24-Nov-12 06-Feb-13 09-Feb-13 63
Fisrt StaFisrt Stage Finishes 61 20-Dec-12 03-Mar-13 08-Apr-13 23-Apr-13 44
A17820 Epoxy Paint Works 2 20-Dec-12 22-Dec-12 08-Apr-13 09-Apr-13 91
A17750 Installation of Doors 2 02-Mar-13 03-Mar-13 22-Apr-13 23-Apr-13 44
A17770 Doors Ironmongery 2 02-Mar-13 03-Mar-13 22-Apr-13 23-Apr-13 44
Second SSecond Stage Finishes 2 23-Dec-12 24-Dec-12 10-Apr-13 11-Apr-13 91
A17740 Final Coat Paint 2 23-Dec-12 24-Dec-12 10-Apr-13 11-Apr-13 91
Final StaFinal Stage Finishes 2 04-Mar-13 05-Mar-13 24-Apr-13 25-Apr-13 44
A17810 Installation of Sinages 2 04-Mar-13 05-Mar-13 24-Apr-13 25-Apr-13 44
MEP WorkMEP Works 61 06-Oct-12 19-Dec-12 28-Jan-13 07-Apr-13 91
HVACHVAC 2 25-Nov-12 26-Nov-12 04-Mar-13 05-Mar-13 82
A17850 Air-Outlet Installation 2 25-Nov-12 26-Nov-12 04-Mar-13 05-Mar-13 82
ElectricalElectrical 61 06-Oct-12 19-Dec-12 28-Jan-13 05-Mar-13 63
A17780 Install Conduits in Wall 2 06-Oct-12 07-Oct-12 28-Jan-13 29-Jan-13 92
A17790 Wiring for Lighting & Power 2 17-Nov-12 18-Nov-12 04-Feb-13 05-Feb-13 65
A17840 Installation of SMDBs 7 25-Nov-12 03-Dec-12 24-Feb-13 03-Mar-13 75
A17800 Installation of Lighting Fittings 2 04-Dec-12 05-Dec-12 04-Mar-13 05-Mar-13 75
A114490 Installation of Access ControlSystem 20 25-Nov-12 18-Dec-12 11-Feb-13 05-Mar-13 64
A114470 Installation of MATC,TV System 20 25-Nov-12 18-Dec-12 11-Feb-13 05-Mar-13 64
A114480 Installation of Telephone System 21 25-Nov-12 19-Dec-12 10-Feb-13 05-Mar-13 63
Fire FighFire Fighting 2 06-Dec-12 08-Dec-12 06-Apr-13 07-Apr-13 101
A17830 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 06-Apr-13 07-Apr-13 101
Room ServRoom Service 112 06-Oct-12 19-Feb-13 07-Feb-13 25-Apr-13 56
FinishingFinishing Works 112 06-Oct-12 19-Feb-13 07-Feb-13 25-Apr-13 56
Wet WorWet Works 43 06-Oct-12 27-Nov-12 07-Feb-13 17-Apr-13 118
A17910 Block Works 2 06-Oct-12 07-Oct-12 07-Feb-13 09-Feb-13 101
A17870 Installation of Doors& Windows Sub-frame 1 17-Nov-12 17-Nov-12 17-Apr-13 17-Apr-13 127
A17860 Plaster Works 4 17-Nov-12 20-Nov-12 14-Feb-13 18-Feb-13 74
A17880 1st Coat Paint 3 25-Nov-12 27-Nov-12 21-Feb-13 24-Feb-13 73
Fisrt StaFisrt Stage Finishes 68 28-Nov-12 18-Feb-13 25-Feb-13 24-Apr-13 56
A18040 Screed Works 2 28-Nov-12 29-Nov-12 25-Feb-13 26-Feb-13 73
A18060 Floor Tiles Work 3 03-Dec-12 05-Dec-12 28-Feb-13 03-Mar-13 73
A17900 Installation of Doors 1 18-Feb-13 18-Feb-13 18-Apr-13 18-Apr-13 51
A17920 Doors Ironmongery 1 18-Feb-13 18-Feb-13 24-Apr-13 24-Apr-13 56
Second SSecond Stage Finishes 1 09-Dec-12 09-Dec-12 09-Apr-13 09-Apr-13 102
A17890 Final Coat Paint 1 09-Dec-12 09-Dec-12 09-Apr-13 09-Apr-13 102
Final StaFinal Stage Finishes 1 19-Feb-13 19-Feb-13 25-Apr-13 25-Apr-13 56
A18030 Installation of Sinages 1 19-Feb-13 19-Feb-13 25-Apr-13 25-Apr-13 56
MEP WorkMEP Works 49 08-Oct-12 08-Dec-12 10-Feb-13 08-Apr-13 102
HVACHVAC 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
A18070 Air-Outlet Installation 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
ElectricalElectrical 49 08-Oct-12 08-Dec-12 12-Feb-13 05-Mar-13 73
A17930 Install Conduits in Wall 2 08-Oct-12 09-Oct-12 12-Feb-13 13-Feb-13 103
A17940 Wiring for Lighting & Power 2 21-Nov-12 22-Nov-12 19-Feb-13 20-Feb-13 74
A17950 Installation of Lighting Fittings 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
PlumbingPlumbing 44 08-Oct-12 01-Dec-12 10-Feb-13 27-Feb-13 73
A17960 Drainge Pipes in Wall 2 08-Oct-12 09-Oct-12 10-Feb-13 11-Feb-13 101
A17990 Water Pipes in Wall 2 08-Oct-12 09-Oct-12 10-Feb-13 11-Feb-13 101
A17970 Drainage&Water Pipes Testing 2 10-Oct-12 11-Oct-12 12-Feb-13 13-Feb-13 101
A17980 Floor Drain Fixning 1 01-Dec-12 01-Dec-12 27-Feb-13 27-Feb-13 73
Fire FighFire Fighting 49 08-Oct-12 08-Dec-12 27-Feb-13 08-Apr-13 102
A18020 Fire Fighting Pipe 2 08-Oct-12 09-Oct-12 27-Feb-13 28-Feb-13 116
A18010 Hydro Static Test for Pipes 2 10-Oct-12 11-Oct-12 02-Mar-13 03-Mar-13 116
A18000 Sprinkler Fixing 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
A18050 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 07-Apr-13 08-Apr-13 102
StaircaseStaircase 118 24-Sep-12 14-Feb-13 07-Nov-12 11-Apr-13 48
Stair 1Stair 1 104 24-Sep-12 29-Jan-13 07-Nov-12 11-Apr-13 62
A108530 Floor Screed 3 24-Sep-12 26-Sep-12 07-Nov-12 10-Nov-12 36
A108540 Install Handrails 4 10-Dec-12 13-Dec-12 05-Jan-13 08-Jan-13 21
A108550 Ceiling 1st Coat Paint 7 15-Dec-12 22-Dec-12 09-Jan-13 16-Jan-13 21
A108560 Wall 1st Coat Paint 7 23-Dec-12 30-Dec-12 17-Jan-13 26-Jan-13 21
A108570 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 03-Feb-13 16-Feb-13 27
A108580 Final Coat Paint 12 15-Jan-13 29-Jan-13 30-Mar-13 11-Apr-13 62
Stair 2Stair 2 115 27-Sep-12 14-Feb-13 11-Nov-12 11-Apr-13 48
A108590 Floor Screed 3 27-Sep-12 30-Sep-12 11-Nov-12 13-Nov-12 36
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access ControlSystem
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 37 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A108600 Install Handrails 4 15-Dec-12 18-Dec-12 21-Jan-13 26-Jan-13 31
A108610 Ceiling 1st Coat Paint 7 31-Dec-12 08-Jan-13 27-Jan-13 03-Feb-13 21
A108620 Wall 1st Coat Paint 7 09-Jan-13 16-Jan-13 04-Feb-13 11-Feb-13 21
A108630 Install Granite/Terrazo 12 17-Jan-13 31-Jan-13 17-Feb-13 02-Mar-13 25
A108640 Final Coat Paint 12 02-Feb-13 14-Feb-13 30-Mar-13 11-Apr-13 48
ApartementsApartements 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21
Studio FlatsStudio Flats 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21
FinishingFinishing Works 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21
Wet WoWet Works 62 15-Sep-12 28-Nov-12 28-Nov-12 11-Mar-13 85
A37980 Block Works 4 15-Sep-12 18-Sep-12 28-Nov-12 03-Dec-12 61
A37840 Installation of Doors& Windows Sub-frame 1 20-Oct-12 20-Oct-12 11-Mar-13 11-Mar-13 116
A37830 Plaster Works 7 20-Oct-12 29-Oct-12 09-Dec-12 16-Dec-12 39
A37860 Installation of Suspended Ceiling Grid (Dry Area) 3 03-Nov-12 05-Nov-12 20-Dec-12 23-Dec-12 39
A38310 Wall Tiles Work (Wet Area) 8 03-Nov-12 11-Nov-12 27-Dec-12 06-Jan-13 45
A37850 1st Coat Paint 3 26-Nov-12 28-Nov-12 24-Dec-12 26-Dec-12 23
Fisrt StaFisrt Stage Finishes 54 09-Dec-12 11-Feb-13 27-Dec-12 13-Mar-13 26
A37870 Suspended Ceiling Tiles (DryArea) 6 09-Dec-12 15-Dec-12 27-Dec-12 03-Jan-13 16
A37910 Installation of Wardrobes 2 18-Dec-12 19-Dec-12 05-Jan-13 06-Jan-13 14
A38300 Screed Works 5 20-Dec-12 25-Dec-12 07-Jan-13 12-Jan-13 14
A37900 Water Proofing for Wet Area 3 26-Dec-12 29-Dec-12 13-Jan-13 15-Jan-13 14
A37890 Floor & Wall Tiles Work (Dry Area) 4 26-Dec-12 30-Dec-12 10-Mar-13 13-Mar-13 61
A38340 Installation of Suspended Ceiling Grid (Wet Area) 3 30-Dec-12 02-Jan-13 16-Jan-13 19-Jan-13 14
A38330 Suspended Ceiling Tiles (Wet Area) 2 03-Feb-13 04-Feb-13 19-Feb-13 20-Feb-13 14
A38320 Floor Tiles Work (Wet Area) 2 10-Feb-13 11-Feb-13 10-Mar-13 11-Mar-13 24
SecondSecond Stage Finishes 15 16-Feb-13 04-Mar-13 12-Mar-13 25-Mar-13 18
A37920 Installation of Windows&Doors 2 16-Feb-13 17-Feb-13 12-Mar-13 13-Mar-13 21
A37990 Doors Ironmongery 2 16-Feb-13 17-Feb-13 24-Mar-13 25-Mar-13 31
A37940 Installation of Kitchen Cabinets 2 18-Feb-13 19-Feb-13 14-Mar-13 16-Mar-13 21
A37960 Installation of Balustrades& Handrails 2 18-Feb-13 19-Feb-13 24-Mar-13 25-Mar-13 29
A37970 Installation of Vanity Counter 2 18-Feb-13 19-Feb-13 14-Mar-13 16-Mar-13 21
A37930 Installation of Mirrors 2 26-Feb-13 27-Feb-13 24-Mar-13 25-Mar-13 22
A38280 Installation of Toliets Accessories 2 03-Mar-13 04-Mar-13 24-Mar-13 25-Mar-13 18
Final StFinal Stage Finishes 156 09-Mar-13 08-Sep-13 26-Mar-13 02-Oct-13 21
A37880 Final Coat Paint 6 09-Mar-13 14-Mar-13 26-Mar-13 01-Apr-13 15
A37950 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A38290 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A38000 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 127 19-Sep-12 20-Feb-13 04-Dec-12 01-Apr-13 34
HVACHVAC 116 19-Sep-12 07-Feb-13 10-Dec-12 05-Mar-13 22
A38020 Chilled Water Pipe Installation & Insulation 7 19-Sep-12 26-Sep-12 10-Dec-12 17-Dec-12 66
A38030 Condensate Pipe Installation 7 19-Sep-12 26-Sep-12 10-Dec-12 17-Dec-12 66
A38010 Duct Installation & Insulation 7 25-Sep-12 02-Oct-12 10-Dec-12 17-Dec-12 61
A38040 FCU Installation 2 03-Oct-12 04-Oct-12 18-Dec-12 19-Dec-12 61
A38050 Air-Outlet Installation 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22
ElectricElectrical 117 19-Sep-12 09-Feb-13 05-Dec-12 05-Mar-13 21
A38060 Install Conduits in Wall 3 19-Sep-12 22-Sep-12 05-Dec-12 08-Dec-12 62
A38070 Install Cable Trays & Trunking 4 19-Sep-12 23-Sep-12 10-Dec-12 13-Dec-12 66
A38110 Cable Laying for Low Current System 3 24-Sep-12 26-Sep-12 20-Dec-12 23-Dec-12 71
A38120 Cable Laying for Power 3 24-Sep-12 26-Sep-12 20-Dec-12 23-Dec-12 71
A38080 Wiring for Lighting & Power 3 30-Oct-12 01-Nov-12 17-Dec-12 19-Dec-12 39
A38090 Wiring for Low Current System 3 30-Oct-12 01-Nov-12 17-Dec-12 19-Dec-12 39
A38100 DB installation,Dressing & Termination 6 29-Nov-12 06-Dec-12 27-Dec-12 03-Jan-13 23
A38150 Installation of Sockets 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22
A38140 Installation of Lighting Fittings 4 05-Feb-13 09-Feb-13 02-Mar-13 05-Mar-13 21
PlumbinPlumbing 127 19-Sep-12 20-Feb-13 04-Dec-12 25-Mar-13 28
A38170 H/L Drainage Pipes Installation 4 19-Sep-12 23-Sep-12 07-Jan-13 10-Jan-13 89
A38180 H/L Hot&Cold Water Pipe Installation 4 19-Sep-12 23-Sep-12 07-Jan-13 10-Jan-13 89
A38230 Water Pipes in Wall 4 19-Sep-12 23-Sep-12 04-Dec-12 08-Dec-12 61
A38190 Drainage&Water Pipes Testing 4 24-Sep-12 27-Sep-12 12-Jan-13 15-Jan-13 89
A38200 ElectricalWater Heater Installation 4 24-Sep-12 27-Sep-12 12-Jan-13 15-Jan-13 89
A38160 Drainge Pipes in Wall 4 27-Sep-12 01-Oct-12 04-Dec-12 08-Dec-12 54
A38210 Floor Drain Fixning 3 23-Dec-12 25-Dec-12 03-Mar-13 05-Mar-13 58
A38220 Installation of Sanitaryware 3 18-Feb-13 20-Feb-13 23-Mar-13 25-Mar-13 28
Fire FigFire Fighting 118 19-Sep-12 10-Feb-13 13-Dec-12 01-Apr-13 43
A38270 Fire Fighting Pipe 3 19-Sep-12 22-Sep-12 13-Dec-12 16-Dec-12 69
A38260 Hydro Static Test for Pipes 3 23-Sep-12 25-Sep-12 17-Dec-12 19-Dec-12 69
A38250 Sprinkler Fixing 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22
A38350 Fire Alarm Devices 3 05-Feb-13 07-Feb-13 23-Mar-13 25-Mar-13 39
A38240 Installation of Fire Extingusher&Blanket 2 09-Feb-13 10-Feb-13 31-Mar-13 01-Apr-13 43
One BedroOne Bedroom Flats 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21
FinishingFinishing Works 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21
Wet WoWet Works 64 09-Sep-12 25-Nov-12 10-Nov-12 07-Mar-13 85
A38510 Block Works 5 09-Sep-12 13-Sep-12 10-Nov-12 14-Nov-12 51
A38370 Installation of Doors& Windows Sub-frame 1 11-Oct-12 11-Oct-12 07-Mar-13 07-Mar-13 120
A38360 Plaster Works 7 11-Oct-12 18-Oct-12 26-Nov-12 04-Dec-12 36
A38390 Installation of Suspended Ceiling Grid (Dry Area) 4 28-Oct-12 31-Oct-12 09-Dec-12 12-Dec-12 34
A38840 Wall Tiles Work (Wet Area) 4 29-Oct-12 01-Nov-12 23-Dec-12 26-Dec-12 45
A38380 1st Coat Paint 6 19-Nov-12 25-Nov-12 13-Dec-12 19-Dec-12 20
Fisrt StaFisrt Stage Finishes 56 04-Dec-12 09-Feb-13 23-Dec-12 18-Mar-13 32
A38400 Suspended Ceiling Tiles (DryArea) 4 04-Dec-12 08-Dec-12 23-Dec-12 26-Dec-12 16
A38440 Installation of Wardrobes 4 13-Dec-12 17-Dec-12 30-Dec-12 03-Jan-13 14
A38830 Screed Works 9 18-Dec-12 27-Dec-12 06-Jan-13 15-Jan-13 15
A38430 Water Proofing for Wet Area 3 29-Dec-12 31-Dec-12 16-Jan-13 19-Jan-13 15
A38420 Floor & Wall Tiles Work (Dry Area) 4 31-Dec-12 05-Jan-13 14-Mar-13 18-Mar-13 61
A38870 Installation of Suspended Ceiling Grid (Wet Area) 4 03-Jan-13 07-Jan-13 20-Jan-13 23-Jan-13 14
A38860 Suspended Ceiling Tiles (Wet Area) 4 29-Jan-13 02-Feb-13 14-Feb-13 18-Feb-13 14
A38850 Floor Tiles Work (Wet Area) 5 04-Feb-13 09-Feb-13 03-Mar-13 07-Mar-13 23
SecondSecond Stage Finishes 16 12-Feb-13 02-Mar-13 09-Mar-13 19-Mar-13 15
A38450 Installation of Windows&Doors 3 12-Feb-13 14-Feb-13 09-Mar-13 11-Mar-13 21
A38520 Doors Ironmongery 3 12-Feb-13 14-Feb-13 17-Mar-13 19-Mar-13 28
A38490 Installation of Balustrades& Handrails 2 16-Feb-13 17-Feb-13 18-Mar-13 19-Mar-13 26
A38470 Installation of Kitchen Cabinets 3 20-Feb-13 23-Feb-13 17-Mar-13 19-Mar-13 21
A38500 Installation of Vanity Counter 3 20-Feb-13 23-Feb-13 17-Mar-13 19-Mar-13 21
A38460 Installation of Mirrors 3 23-Feb-13 25-Feb-13 17-Mar-13 19-Mar-13 19
A38810 Installation of Toliets Accessories 4 26-Feb-13 02-Mar-13 16-Mar-13 19-Mar-13 15
Final StFinal Stage Finishes 161 03-Mar-13 08-Sep-13 20-Mar-13 02-Oct-13 21
A38410 Final Coat Paint 5 03-Mar-13 07-Mar-13 20-Mar-13 25-Mar-13 15
A38480 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A38820 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A38530 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 129 15-Sep-12 18-Feb-13 17-Nov-12 25-Mar-13 30
HVACHVAC 118 15-Sep-12 05-Feb-13 27-Nov-12 05-Mar-13 24
A38550 Chilled Water Pipe Installation & Insulation 7 15-Sep-12 22-Sep-12 27-Nov-12 05-Dec-12 60
A38560 Condensate Pipe Installation 7 15-Sep-12 22-Sep-12 27-Nov-12 05-Dec-12 60
A38540 Duct Installation & Insulation 7 17-Sep-12 24-Sep-12 27-Nov-12 05-Dec-12 58
A38570 FCU Installation 2 25-Sep-12 26-Sep-12 06-Dec-12 08-Dec-12 58
A38580 Air-Outlet Installation 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24
ElectricElectrical 119 15-Sep-12 06-Feb-13 22-Nov-12 05-Mar-13 23
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Kitchen Cabinets
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Mirrors
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Drainge Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Mirrors
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 38 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A38590 Install Conduits in Wall 3 15-Sep-12 17-Sep-12 22-Nov-12 25-Nov-12 56
A38600 Install Cable Trays & Trunking 4 15-Sep-12 18-Sep-12 27-Nov-12 01-Dec-12 60
A38640 Cable Laying for Low Current System 3 19-Sep-12 22-Sep-12 10-Dec-12 12-Dec-12 66
A38650 Cable Laying for Power 3 19-Sep-12 22-Sep-12 10-Dec-12 12-Dec-12 66
A38610 Wiring for Lighting & Power 3 20-Oct-12 22-Oct-12 05-Dec-12 08-Dec-12 36
A38620 Wiring for Low Current System 3 20-Oct-12 22-Oct-12 05-Dec-12 08-Dec-12 36
A38630 DB installation,Dressing & Termination 6 26-Nov-12 03-Dec-12 20-Dec-12 26-Dec-12 20
A38680 Installation of Sockets 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24
A38670 Installation of Lighting Fittings 4 03-Feb-13 06-Feb-13 02-Mar-13 05-Mar-13 23
PlumbinPlumbing 129 15-Sep-12 18-Feb-13 17-Nov-12 19-Mar-13 25
A38700 H/L Drainage Pipes Installation 4 15-Sep-12 18-Sep-12 02-Jan-13 06-Jan-13 89
A38710 H/L Hot&Cold Water Pipe Installation 4 15-Sep-12 18-Sep-12 10-Jan-13 14-Jan-13 96
A38720 Drainage&Water Pipes Testing 4 19-Sep-12 23-Sep-12 15-Jan-13 19-Jan-13 96
A38730 ElectricalWater Heater Installation 4 19-Sep-12 23-Sep-12 15-Jan-13 19-Jan-13 96
A38760 Water Pipes in Wall 8 15-Sep-12 23-Sep-12 17-Nov-12 25-Nov-12 51
A38690 Drainge Pipes in Wall 8 18-Sep-12 26-Sep-12 17-Nov-12 25-Nov-12 48
A38740 Floor Drain Fixning 3 20-Dec-12 23-Dec-12 02-Mar-13 04-Mar-13 59
A38750 Installation of Sanitaryware 3 16-Feb-13 18-Feb-13 17-Mar-13 19-Mar-13 25
Fire FigFire Fighting 120 15-Sep-12 07-Feb-13 01-Dec-12 25-Mar-13 39
A38800 Fire Fighting Pipe 3 15-Sep-12 17-Sep-12 01-Dec-12 04-Dec-12 63
A38790 Hydro Static Test for Pipes 3 18-Sep-12 20-Sep-12 05-Dec-12 08-Dec-12 63
A38780 Sprinkler Fixing 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24
A38880 Fire Alarm Devices 3 03-Feb-13 05-Feb-13 17-Mar-13 19-Mar-13 36
A38770 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 24-Mar-13 25-Mar-13 39
Two BedroTwo Bedroom Flats 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21
FinishingFinishing Works 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21
Wet WoWet Works 73 22-Aug-12 18-Nov-12 08-Sep-12 20-Feb-13 78
A39040 Block Works 15 22-Aug-12 08-Sep-12 08-Sep-12 24-Sep-12 14
A38900 Installation of Doors& Windows Sub-frame 7 18-Sep-12 25-Sep-12 13-Feb-13 20-Feb-13 121
A38890 Plaster Works 20 18-Sep-12 10-Oct-12 04-Oct-12 29-Oct-12 14
A38920 Installation of Suspended Ceiling Grid (Dry Area) 9 15-Oct-12 24-Oct-12 03-Nov-12 12-Nov-12 14
A39370 Wall Tiles Work (Wet Area) 13 11-Oct-12 28-Oct-12 08-Dec-12 22-Dec-12 45
A38910 1st Coat Paint 18 28-Oct-12 18-Nov-12 13-Nov-12 05-Dec-12 14
Fisrt StaFisrt Stage Finishes 63 19-Nov-12 03-Feb-13 06-Dec-12 01-Apr-13 49
A38930 Suspended Ceiling Tiles (DryArea) 12 19-Nov-12 03-Dec-12 06-Dec-12 19-Dec-12 14
A38970 Installation of Wardrobes 8 04-Dec-12 12-Dec-12 20-Dec-12 29-Dec-12 14
A39360 Screed Works 9 13-Dec-12 23-Dec-12 03-Jan-13 13-Jan-13 17
A38960 Water Proofing for Wet Area 9 24-Dec-12 03-Jan-13 14-Jan-13 23-Jan-13 17
A39400 Installation of Suspended Ceiling Grid (Wet Area) 7 08-Jan-13 15-Jan-13 26-Jan-13 02-Feb-13 14
A38950 Floor & Wall Tiles Work (Dry Area) 12 06-Jan-13 19-Jan-13 19-Mar-13 01-Apr-13 61
A39390 Suspended Ceiling Tiles (Wet Area) 10 16-Jan-13 28-Jan-13 03-Feb-13 13-Feb-13 14
A39380 Floor Tiles Work (Wet Area) 5 29-Jan-13 03-Feb-13 16-Feb-13 20-Feb-13 15
SecondSecond Stage Finishes 27 04-Feb-13 06-Mar-13 21-Feb-13 01-Apr-13 22
A38980 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 21-Feb-13 28-Feb-13 15
A39050 Doors Ironmongery 6 07-Feb-13 13-Feb-13 26-Mar-13 01-Apr-13 40
A39020 Installation of Balustrades& Handrails 5 12-Feb-13 17-Feb-13 27-Mar-13 01-Apr-13 37
A38990 Installation of Mirrors 9 12-Feb-13 21-Feb-13 06-Mar-13 16-Mar-13 19
A39340 Installation of Toliets Accessories 12 12-Feb-13 25-Feb-13 02-Mar-13 14-Mar-13 15
A39030 Installation of Vanity Counter 9 24-Feb-13 05-Mar-13 23-Mar-13 01-Apr-13 23
A39000 Installation of Kitchen Cabinets 10 24-Feb-13 06-Mar-13 21-Mar-13 01-Apr-13 22
Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 02-Apr-13 02-Oct-13 21
A38940 Final Coat Paint 9 16-Mar-13 25-Mar-13 02-Apr-13 11-Apr-13 15
A39010 Installation of Carpets 4 26-Mar-13 30-Mar-13 22-Apr-13 25-Apr-13 23
A39350 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23
A39060 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 131 09-Sep-12 14-Feb-13 25-Sep-12 11-Apr-13 48
HVACHVAC 119 09-Sep-12 31-Jan-13 21-Oct-12 05-Mar-13 28
A39070 Duct Installation & Insulation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36
A39080 Chilled Water Pipe Installation & Insulation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36
A39090 Condensate Pipe Installation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36
A39100 FCU Installation 2 17-Sep-12 18-Sep-12 31-Oct-12 01-Nov-12 36
A39110 Air-Outlet Installation 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
ElectricElectrical 120 09-Sep-12 02-Feb-13 01-Oct-12 05-Mar-13 27
A39120 Install Conduits in Wall 3 09-Sep-12 11-Sep-12 01-Oct-12 03-Oct-12 19
A39130 Install Cable Trays & Trunking 4 09-Sep-12 12-Sep-12 21-Oct-12 24-Oct-12 36
A39170 Cable Laying for Low Current System 3 13-Sep-12 16-Sep-12 10-Nov-12 12-Nov-12 47
A39180 Cable Laying for Power 3 13-Sep-12 16-Sep-12 10-Nov-12 12-Nov-12 47
A39140 Wiring for Lighting & Power 3 11-Oct-12 14-Oct-12 30-Oct-12 01-Nov-12 14
A39150 Wiring for Low Current System 3 11-Oct-12 14-Oct-12 30-Oct-12 01-Nov-12 14
A39160 DB installation,Dressing & Termination 6 19-Nov-12 25-Nov-12 13-Dec-12 19-Dec-12 20
A39210 Installation of Sockets 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
A39200 Installation of Lighting Fittings 4 29-Jan-13 02-Feb-13 02-Mar-13 05-Mar-13 27
PlumbinPlumbing 131 09-Sep-12 14-Feb-13 25-Sep-12 01-Apr-13 39
A39230 H/L Drainage Pipes Installation 4 09-Sep-12 12-Sep-12 27-Dec-12 31-Dec-12 90
A39240 H/L Hot&Cold Water Pipe Installation 4 09-Sep-12 12-Sep-12 15-Jan-13 19-Jan-13 105
A39220 Drainge Pipes in Wall 8 09-Sep-12 17-Sep-12 25-Sep-12 03-Oct-12 14
A39250 Drainage&Water Pipes Testing 4 13-Sep-12 17-Sep-12 20-Jan-13 23-Jan-13 105
A39260 ElectricalWater Heater Installation 4 13-Sep-12 17-Sep-12 20-Jan-13 23-Jan-13 105
A39290 Water Pipes in Wall 8 09-Sep-12 17-Sep-12 25-Sep-12 03-Oct-12 14
A39270 Floor Drain Fixning 3 16-Dec-12 18-Dec-12 14-Feb-13 17-Feb-13 50
A39280 Installation of Sanitaryware 3 12-Feb-13 14-Feb-13 30-Mar-13 01-Apr-13 39
Fire FigFire Fighting 121 09-Sep-12 03-Feb-13 24-Oct-12 11-Apr-13 58
A39330 Fire Fighting Pipe 3 09-Sep-12 11-Sep-12 24-Oct-12 29-Oct-12 39
A39320 Hydro Static Test for Pipes 3 12-Sep-12 15-Sep-12 30-Oct-12 01-Nov-12 39
A39310 Sprinkler Fixing 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28
A39410 Fire Alarm Devices 3 29-Jan-13 31-Jan-13 30-Mar-13 01-Apr-13 51
A39300 Installation of Fire Extingusher&Blanket 2 02-Feb-13 03-Feb-13 10-Apr-13 11-Apr-13 58
5th Floor5th Floor 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21
Public AreaPublic Area 153 03-Oct-12 06-Apr-13 14-Nov-12 25-Apr-13 17
Garbage RGarbage Room 73 13-Oct-12 10-Jan-13 15-Jan-13 25-Apr-13 89
FinishingFinishing Works 73 13-Oct-12 10-Jan-13 15-Jan-13 25-Apr-13 89
Wet WorWet Works 63 13-Oct-12 29-Dec-12 15-Jan-13 28-Feb-13 51
A18480 Block Works 3 13-Oct-12 15-Oct-12 15-Jan-13 17-Jan-13 76
A18430 Installation of Doors& Windows Sub-frame 1 22-Nov-12 22-Nov-12 28-Feb-13 28-Feb-13 81
A18420 Plaster Works 3 22-Nov-12 25-Nov-12 23-Jan-13 27-Jan-13 51
A18460 Wall Tiles Work 4 28-Nov-12 03-Dec-12 30-Jan-13 03-Feb-13 51
A18440 1st Coat Paint 2 27-Dec-12 29-Dec-12 04-Feb-13 05-Feb-13 31
Fisrt StaFisrt Stage Finishes 7 30-Dec-12 07-Jan-13 24-Feb-13 24-Apr-13 91
A18610 Screed Works 2 30-Dec-12 31-Dec-12 24-Feb-13 25-Feb-13 46
A18630 Floor Tiles Work 2 03-Jan-13 05-Jan-13 27-Feb-13 28-Feb-13 46
A18490 Doors Ironmongery 1 06-Jan-13 06-Jan-13 24-Apr-13 24-Apr-13 92
A18470 Installation of Doors 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46
Second SSecond Stage Finishes 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46
A18450 Final Coat Paint 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46
Final StaFinal Stage Finishes 1 10-Jan-13 10-Jan-13 25-Apr-13 25-Apr-13 89
A18600 Installation of Sinages 1 10-Jan-13 10-Jan-13 25-Apr-13 25-Apr-13 89
MEP WorkMEP Works 67 16-Oct-12 07-Jan-13 19-Jan-13 03-Mar-13 46
ElectricalElectrical 67 16-Oct-12 07-Jan-13 21-Jan-13 03-Mar-13 46
A18500 Install Conduits in Wall 2 16-Oct-12 17-Oct-12 21-Jan-13 22-Jan-13 78
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Water Pipes in Wall
Drainge Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Kitchen Cabinets
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 39 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A18510 Wiring for Lighting & Power 2 26-Nov-12 27-Nov-12 28-Jan-13 29-Jan-13 51
A18520 Installation of Lighting Fittings 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46
PlumbingPlumbing 63 16-Oct-12 02-Jan-13 19-Jan-13 26-Feb-13 46
A18530 Drainge Pipes in Wall 2 16-Oct-12 17-Oct-12 19-Jan-13 20-Jan-13 76
A18560 Water Pipes in Wall 2 16-Oct-12 17-Oct-12 19-Jan-13 20-Jan-13 76
A18540 Drainage&Water Pipes Testing 2 18-Oct-12 20-Oct-12 21-Jan-13 22-Jan-13 76
A18550 Floor Drain Fixning 1 02-Jan-13 02-Jan-13 26-Feb-13 26-Feb-13 46
Fire FighFire Fighting 66 17-Oct-12 07-Jan-13 25-Feb-13 03-Mar-13 46
A18590 Fire Fighting Pipe 2 17-Oct-12 18-Oct-12 25-Feb-13 26-Feb-13 106
A18580 Hydro Static Test for Pipes 2 20-Oct-12 21-Oct-12 27-Feb-13 28-Feb-13 106
A18570 Sprinkler Fixing 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46
A18620 Fire Alarm Devices 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46
Corridor &Corridor & Lift Lobby 153 03-Oct-12 06-Apr-13 10-Dec-12 25-Apr-13 17
FinishingFinishing Works 153 03-Oct-12 06-Apr-13 10-Dec-12 25-Apr-13 17
Wet WorWet Works 57 03-Oct-12 12-Dec-12 10-Dec-12 23-Jan-13 35
A18140 Block Works 8 03-Oct-12 11-Oct-12 10-Dec-12 18-Dec-12 54
A18080 Plaster Works 7 13-Nov-12 21-Nov-12 22-Dec-12 29-Dec-12 31
A18100 Installation of Suspended Ceiling Grid 6 27-Nov-12 04-Dec-12 05-Jan-13 10-Jan-13 31
A18110 Suspended Ceiling Tiles 6 05-Dec-12 11-Dec-12 12-Jan-13 17-Jan-13 31
A18400 MDF for Lift Lobby Wall 7 05-Dec-12 12-Dec-12 16-Jan-13 23-Jan-13 35
Fisrt StaFisrt Stage Finishes 12 13-Dec-12 26-Dec-12 26-Jan-13 03-Feb-13 31
A18380 Screed Works 3 13-Dec-12 16-Dec-12 26-Jan-13 28-Jan-13 35
A18090 1st Coat Paint 5 22-Dec-12 26-Dec-12 29-Jan-13 03-Feb-13 31
Second SSecond Stage Finishes 2 08-Jan-13 09-Jan-13 04-Mar-13 25-Apr-13 90
A18120 Installation of Doors 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46
A18150 Doors Ironmongery 2 08-Jan-13 09-Jan-13 24-Apr-13 25-Apr-13 90
Final StaFinal Stage Finishes 11 25-Mar-13 06-Apr-13 14-Apr-13 25-Apr-13 17
A18130 Installation of Carpets 4 25-Mar-13 28-Mar-13 14-Apr-13 17-Apr-13 17
A18390 Fixing of Wall Covering 5 30-Mar-13 03-Apr-13 18-Apr-13 23-Apr-13 17
A18370 Installation of Sinages 2 04-Apr-13 06-Apr-13 24-Apr-13 25-Apr-13 17
MEP WorkMEP Works 56 13-Oct-12 20-Dec-12 19-Dec-12 05-Mar-13 62
HVACHVAC 51 13-Oct-12 15-Dec-12 25-Dec-12 28-Jan-13 36
A18160 Duct Installation & Insulation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59
A18170 Chilled Water Pipe Installation & Insulation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59
A18180 Condensate Pipe Installation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59
A18190 FCU Installation 3 18-Oct-12 21-Oct-12 31-Dec-12 03-Jan-13 59
A18200 Air-Outlet Installation 3 12-Dec-12 15-Dec-12 26-Jan-13 28-Jan-13 36
ElectricalElectrical 52 13-Oct-12 16-Dec-12 19-Dec-12 05-Mar-13 66
A18210 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 19-Dec-12 20-Dec-12 54
A18220 Install Cable Trays & Trunking 2 13-Oct-12 14-Oct-12 25-Dec-12 26-Dec-12 59
A18260 Cable Laying for Low Current System 2 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 69
A18270 Cable Laying for Power 3 15-Oct-12 17-Oct-12 08-Jan-13 10-Jan-13 68
A18230 Wiring for Lighting & Power 3 22-Nov-12 25-Nov-12 31-Dec-12 03-Jan-13 32
A18240 Wiring for Low Current System 4 22-Nov-12 26-Nov-12 30-Dec-12 03-Jan-13 31
A18250 DB installation,Dressing & Termination 6 05-Dec-12 11-Dec-12 12-Jan-13 17-Jan-13 31
A18290 Installation of Lighting Fittings 3 12-Dec-12 15-Dec-12 03-Mar-13 05-Mar-13 67
A18300 Installation of Sockets 4 12-Dec-12 16-Dec-12 02-Mar-13 05-Mar-13 66
PlumbingPlumbing 5 13-Oct-12 17-Oct-12 29-Dec-12 03-Jan-13 62
A18310 H/L Hot&Cold Water Pipe Installation 5 13-Oct-12 17-Oct-12 29-Dec-12 03-Jan-13 62
Fire FighFire Fighting 56 13-Oct-12 20-Dec-12 25-Dec-12 28-Jan-13 31
A18360 Fire Fighting Pipe 4 13-Oct-12 16-Oct-12 25-Dec-12 29-Dec-12 59
A18350 Hydro Static Test for Pipes 4 17-Oct-12 21-Oct-12 30-Dec-12 03-Jan-13 59
A18340 Sprinkler Fixing 4 12-Dec-12 16-Dec-12 19-Jan-13 22-Jan-13 31
A18410 Fire Alarm Devices 5 12-Dec-12 17-Dec-12 22-Jan-13 28-Jan-13 34
A18330 Installation of Fire Extingusher&Blanket 4 17-Dec-12 20-Dec-12 23-Jan-13 28-Jan-13 31
Electrical /Electrical /Telephone/ELV Rooms 90 16-Oct-12 04-Feb-13 23-Jan-13 25-Apr-13 69
FinishingFinishing Works 90 16-Oct-12 04-Feb-13 23-Jan-13 25-Apr-13 69
Wet WorWet Works 63 16-Oct-12 02-Jan-13 23-Jan-13 05-Mar-13 52
A18690 Block Works 3 16-Oct-12 18-Oct-12 23-Jan-13 27-Jan-13 80
A18650 Installation of Doors& Windows Sub-frame 1 26-Nov-12 26-Nov-12 05-Mar-13 05-Mar-13 82
A18640 Plaster Works 4 26-Nov-12 29-Nov-12 30-Jan-13 03-Feb-13 53
A18660 1st Coat Paint 3 30-Dec-12 02-Jan-13 06-Feb-13 09-Feb-13 31
Fisrt StaFisrt Stage Finishes 17 10-Jan-13 30-Jan-13 06-Mar-13 23-Apr-13 71
A18680 Installation of Doors 2 10-Jan-13 12-Jan-13 06-Mar-13 07-Mar-13 46
A18700 Doors Ironmongery 2 10-Jan-13 12-Jan-13 22-Apr-13 23-Apr-13 86
A18750 Epoxy Paint Works 2 29-Jan-13 30-Jan-13 09-Apr-13 10-Apr-13 60
Second SSecond Stage Finishes 2 31-Jan-13 02-Feb-13 11-Apr-13 13-Apr-13 60
A18670 Final Coat Paint 2 31-Jan-13 02-Feb-13 11-Apr-13 13-Apr-13 60
Final StaFinal Stage Finishes 2 03-Feb-13 04-Feb-13 24-Apr-13 25-Apr-13 69
A18740 Installation of Sinages 2 03-Feb-13 04-Feb-13 24-Apr-13 25-Apr-13 69
MEP WorkMEP Works 81 20-Oct-12 28-Jan-13 28-Jan-13 08-Apr-13 60
HVACHVAC 2 03-Jan-13 05-Jan-13 04-Mar-13 05-Mar-13 50
A18780 Air-Outlet Installation 2 03-Jan-13 05-Jan-13 04-Mar-13 05-Mar-13 50
ElectricalElectrical 81 20-Oct-12 28-Jan-13 28-Jan-13 05-Mar-13 31
A18710 Install Conduits in Wall 2 20-Oct-12 21-Oct-12 28-Jan-13 29-Jan-13 80
A18720 Wiring for Lighting & Power 2 01-Dec-12 03-Dec-12 04-Feb-13 05-Feb-13 53
A18770 Installation of SMDBs 7 03-Jan-13 10-Jan-13 24-Feb-13 03-Mar-13 43
A18730 Installation of Lighting Fittings 2 12-Jan-13 13-Jan-13 04-Mar-13 05-Mar-13 43
A114520 Installation of Access ControlSystem 20 03-Jan-13 27-Jan-13 11-Feb-13 05-Mar-13 32
A114500 Installation of MATC,TV System 20 03-Jan-13 27-Jan-13 11-Feb-13 05-Mar-13 32
A114510 Installation of Telephone System 21 03-Jan-13 28-Jan-13 10-Feb-13 05-Mar-13 31
Fire FighFire Fighting 2 14-Jan-13 15-Jan-13 07-Apr-13 08-Apr-13 70
A18760 Fire Alarm Devices 2 14-Jan-13 15-Jan-13 07-Apr-13 08-Apr-13 70
Room ServRoom Service 73 20-Oct-12 17-Jan-13 07-Feb-13 25-Apr-13 83
FinishingFinishing Works 73 20-Oct-12 17-Jan-13 07-Feb-13 25-Apr-13 83
Wet WorWet Works 63 20-Oct-12 06-Jan-13 07-Feb-13 07-Mar-13 51
A18840 Block Works 2 20-Oct-12 21-Oct-12 07-Feb-13 09-Feb-13 89
A18800 Installation of Doors& Windows Sub-frame 1 01-Dec-12 01-Dec-12 07-Mar-13 07-Mar-13 80
A18790 Plaster Works 4 01-Dec-12 05-Dec-12 14-Feb-13 18-Feb-13 62
A18810 1st Coat Paint 3 03-Jan-13 06-Jan-13 21-Feb-13 24-Feb-13 41
Fisrt StaFisrt Stage Finishes 7 07-Jan-13 14-Jan-13 25-Feb-13 24-Apr-13 85
A18970 Screed Works 2 07-Jan-13 08-Jan-13 25-Feb-13 26-Feb-13 41
A18990 Floor Tiles Work 3 10-Jan-13 13-Jan-13 28-Feb-13 03-Mar-13 41
A18830 Installation of Doors 1 14-Jan-13 14-Jan-13 09-Mar-13 09-Mar-13 45
A18850 Doors Ironmongery 1 14-Jan-13 14-Jan-13 24-Apr-13 24-Apr-13 85
Second SSecond Stage Finishes 1 16-Jan-13 16-Jan-13 13-Apr-13 13-Apr-13 73
A18820 Final Coat Paint 1 16-Jan-13 16-Jan-13 13-Apr-13 13-Apr-13 73
Final StaFinal Stage Finishes 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83
A18960 Installation of Sinages 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83
MEP WorkMEP Works 69 22-Oct-12 15-Jan-13 10-Feb-13 11-Apr-13 73
HVACHVAC 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41
A19000 Air-Outlet Installation 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41
ElectricalElectrical 69 22-Oct-12 15-Jan-13 12-Feb-13 05-Mar-13 41
A18860 Install Conduits in Wall 2 22-Oct-12 23-Oct-12 12-Feb-13 13-Feb-13 91
A18870 Wiring for Lighting & Power 2 06-Dec-12 08-Dec-12 19-Feb-13 20-Feb-13 62
A18880 Installation of Lighting Fittings 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41
PlumbingPlumbing 64 22-Oct-12 09-Jan-13 10-Feb-13 27-Feb-13 41
A18890 Drainge Pipes in Wall 2 22-Oct-12 23-Oct-12 10-Feb-13 11-Feb-13 89
A18920 Water Pipes in Wall 2 22-Oct-12 23-Oct-12 10-Feb-13 11-Feb-13 89
A18900 Drainage&Water Pipes Testing 2 24-Oct-12 28-Oct-12 12-Feb-13 13-Feb-13 89
A18910 Floor Drain Fixning 1 09-Jan-13 09-Jan-13 27-Feb-13 27-Feb-13 41
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 40 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Fire FighFire Fighting 69 22-Oct-12 15-Jan-13 27-Feb-13 11-Apr-13 73
A18950 Fire Fighting Pipe 2 22-Oct-12 23-Oct-12 27-Feb-13 28-Feb-13 104
A18940 Hydro Static Test for Pipes 2 24-Oct-12 28-Oct-12 02-Mar-13 03-Mar-13 104
A18930 Sprinkler Fixing 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41
A18980 Fire Alarm Devices 2 14-Jan-13 15-Jan-13 10-Apr-13 11-Apr-13 73
StaircaseStaircase 133 09-Oct-12 19-Mar-13 14-Nov-12 13-Apr-13 21
Stair 1Stair 1 119 09-Oct-12 03-Mar-13 14-Nov-12 13-Apr-13 35
A108650 Floor Screed 3 09-Oct-12 11-Oct-12 14-Nov-12 18-Nov-12 29
A108660 Install Handrails 4 13-Oct-12 16-Oct-12 19-Nov-12 22-Nov-12 29
A108670 Ceiling 1st Coat Paint 7 17-Jan-13 26-Jan-13 12-Feb-13 19-Feb-13 21
A108680 Wall 1st Coat Paint 7 27-Jan-13 03-Feb-13 20-Feb-13 27-Feb-13 21
A108690 Install Granite/Terrazo 12 04-Feb-13 17-Feb-13 03-Mar-13 16-Mar-13 23
A108700 Final Coat Paint 12 18-Feb-13 03-Mar-13 31-Mar-13 13-Apr-13 35
Stair 2Stair 2 130 13-Oct-12 19-Mar-13 20-Nov-12 13-Apr-13 21
A108710 Floor Screed 3 13-Oct-12 15-Oct-12 20-Nov-12 22-Nov-12 30
A108720 Install Handrails 4 17-Oct-12 21-Oct-12 24-Nov-12 27-Nov-12 29
A108730 Ceiling 1st Coat Paint 7 04-Feb-13 11-Feb-13 28-Feb-13 07-Mar-13 21
A108740 Wall 1st Coat Paint 7 12-Feb-13 19-Feb-13 09-Mar-13 16-Mar-13 21
A108750 Install Granite/Terrazo 12 20-Feb-13 05-Mar-13 17-Mar-13 30-Mar-13 21
A108760 Final Coat Paint 12 06-Mar-13 19-Mar-13 31-Mar-13 13-Apr-13 21
ApartementsApartements 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21
Studio FlatsStudio Flats 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21
FinishingFinishing Works 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21
Wet WoWet Works 61 29-Sep-12 12-Dec-12 27-Nov-12 09-Mar-13 72
A39570 Block Works 4 29-Sep-12 02-Oct-12 27-Nov-12 01-Dec-12 48
A39430 Installation of Doors& Windows Sub-frame 1 05-Nov-12 05-Nov-12 09-Mar-13 09-Mar-13 102
A39420 Plaster Works 7 05-Nov-12 12-Nov-12 08-Dec-12 15-Dec-12 26
A39900 Wall Tiles Work (Wet Area) 8 13-Nov-12 22-Nov-12 06-Jan-13 14-Jan-13 43
A39450 Installation of Suspended Ceiling Grid (Dry Area) 6 18-Nov-12 24-Nov-12 19-Dec-12 25-Dec-12 26
A39440 1st Coat Paint 3 10-Dec-12 12-Dec-12 26-Dec-12 29-Dec-12 14
Fisrt StaFisrt Stage Finishes 23 13-Dec-12 09-Jan-13 30-Dec-12 16-Mar-13 55
A39460 Suspended Ceiling Tiles (DryArea) 6 13-Dec-12 19-Dec-12 30-Dec-12 06-Jan-13 14
A39500 Installation of Wardrobes 2 20-Dec-12 22-Dec-12 16-Jan-13 17-Jan-13 22
A39890 Screed Works 5 23-Dec-12 27-Dec-12 26-Jan-13 30-Jan-13 27
A39490 Water Proofing for Wet Area 3 29-Dec-12 31-Dec-12 31-Jan-13 03-Feb-13 27
A39480 Floor & Wall Tiles Work (Dry Area) 4 29-Dec-12 02-Jan-13 12-Mar-13 16-Mar-13 61
A39930 Installation of Suspended Ceiling Grid (Wet Area) 3 02-Jan-13 05-Jan-13 06-Feb-13 09-Feb-13 29
A39920 Suspended Ceiling Tiles (Wet Area) 2 06-Jan-13 07-Jan-13 12-Feb-13 13-Feb-13 31
A39910 Floor Tiles Work (Wet Area) 2 08-Jan-13 09-Jan-13 26-Feb-13 27-Feb-13 41
SecondSecond Stage Finishes 4 15-Jan-13 19-Jan-13 10-Mar-13 06-Apr-13 65
A39510 Installation of Windows&Doors 2 15-Jan-13 16-Jan-13 10-Mar-13 11-Mar-13 45
A39580 Doors Ironmongery 2 15-Jan-13 16-Jan-13 04-Apr-13 06-Apr-13 67
A39520 Installation of Mirrors 2 17-Jan-13 19-Jan-13 18-Mar-13 19-Mar-13 50
A39530 Installation of Kitchen Cabinets 2 17-Jan-13 19-Jan-13 17-Mar-13 18-Mar-13 49
A39550 Installation of Balustrades& Handrails 2 17-Jan-13 19-Jan-13 04-Apr-13 06-Apr-13 65
A39560 Installation of Vanity Counter 2 17-Jan-13 19-Jan-13 19-Mar-13 20-Mar-13 51
A39870 Installation of Toliets Accessories 2 17-Jan-13 19-Jan-13 13-Mar-13 14-Mar-13 46
Final StFinal Stage Finishes 195 21-Jan-13 08-Sep-13 07-Apr-13 02-Oct-13 21
A39470 Final Coat Paint 6 21-Jan-13 28-Jan-13 07-Apr-13 13-Apr-13 64
A39540 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A39880 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A39590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 89 03-Oct-12 20-Jan-13 03-Dec-12 13-Apr-13 70
HVACHVAC 81 03-Oct-12 10-Jan-13 09-Dec-12 05-Mar-13 45
A39600 Duct Installation & Insulation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53
A39610 Chilled Water Pipe Installation & Insulation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53
A39620 Condensate Pipe Installation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53
A39630 FCU Installation 2 11-Oct-12 13-Oct-12 17-Dec-12 18-Dec-12 53
A39640 Air-Outlet Installation 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45
ElectricElectrical 82 03-Oct-12 12-Jan-13 04-Dec-12 05-Mar-13 44
A39650 Install Conduits in Wall 3 03-Oct-12 06-Oct-12 04-Dec-12 06-Dec-12 49
A39660 Install Cable Trays & Trunking 4 03-Oct-12 07-Oct-12 09-Dec-12 12-Dec-12 53
A39700 Cable Laying for Low Current System 3 08-Oct-12 10-Oct-12 23-Dec-12 25-Dec-12 61
A39710 Cable Laying for Power 3 08-Oct-12 10-Oct-12 23-Dec-12 25-Dec-12 61
A39670 Wiring for Lighting & Power 3 13-Nov-12 17-Nov-12 16-Dec-12 18-Dec-12 26
A39680 Wiring for Low Current System 3 13-Nov-12 17-Nov-12 16-Dec-12 18-Dec-12 26
A39690 DB installation,Dressing & Termination 6 13-Dec-12 19-Dec-12 30-Dec-12 06-Jan-13 14
A39740 Installation of Sockets 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45
A39730 Installation of Lighting Fittings 4 08-Jan-13 12-Jan-13 02-Mar-13 05-Mar-13 44
PlumbinPlumbing 89 03-Oct-12 20-Jan-13 03-Dec-12 06-Apr-13 64
A39750 Drainge Pipes in Wall 4 03-Oct-12 07-Oct-12 03-Dec-12 06-Dec-12 48
A39760 H/L Drainage Pipes Installation 4 03-Oct-12 07-Oct-12 28-Jan-13 31-Jan-13 94
A39770 H/L Hot&Cold Water Pipe Installation 4 03-Oct-12 07-Oct-12 28-Jan-13 31-Jan-13 94
A39820 Water Pipes in Wall 4 03-Oct-12 07-Oct-12 03-Dec-12 06-Dec-12 48
A39780 Drainage&Water Pipes Testing 4 08-Oct-12 11-Oct-12 02-Feb-13 05-Feb-13 94
A39790 ElectricalWater Heater Installation 4 08-Oct-12 11-Oct-12 02-Feb-13 05-Feb-13 94
A39800 Floor Drain Fixning 3 25-Dec-12 27-Dec-12 21-Feb-13 24-Feb-13 48
A39810 Installation of Sanitaryware 3 17-Jan-13 20-Jan-13 03-Apr-13 06-Apr-13 64
Fire FigFire Fighting 83 03-Oct-12 13-Jan-13 12-Dec-12 13-Apr-13 76
A39860 Fire Fighting Pipe 3 03-Oct-12 06-Oct-12 12-Dec-12 15-Dec-12 56
A39850 Hydro Static Test for Pipes 3 07-Oct-12 09-Oct-12 16-Dec-12 18-Dec-12 56
A39840 Sprinkler Fixing 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45
A39940 Fire Alarm Devices 3 08-Jan-13 10-Jan-13 03-Apr-13 06-Apr-13 72
A39830 Installation of Fire Extingusher&Blanket 2 12-Jan-13 13-Jan-13 11-Apr-13 13-Apr-13 76
One BedroOne Bedroom Flats 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21
FinishingFinishing Works 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21
Wet WoWet Works 63 23-Sep-12 09-Dec-12 12-Nov-12 11-Mar-13 77
A40100 Block Works 5 23-Sep-12 27-Sep-12 12-Nov-12 18-Nov-12 41
A39960 Installation of Doors& Windows Sub-frame 1 28-Oct-12 28-Oct-12 11-Mar-13 11-Mar-13 111
A39950 Plaster Works 7 28-Oct-12 04-Nov-12 28-Nov-12 06-Dec-12 26
A39980 Installation of Suspended Ceiling Grid (Dry Area) 4 10-Nov-12 13-Nov-12 15-Dec-12 18-Dec-12 28
A40430 Wall Tiles Work (Wet Area) 4 24-Nov-12 27-Nov-12 15-Jan-13 19-Jan-13 43
A39970 1st Coat Paint 6 03-Dec-12 09-Dec-12 19-Dec-12 25-Dec-12 14
Fisrt StaFisrt Stage Finishes 34 20-Dec-12 30-Jan-13 07-Jan-13 19-Mar-13 41
A39990 Suspended Ceiling Tiles (DryArea) 4 20-Dec-12 24-Dec-12 07-Jan-13 10-Jan-13 14
A40030 Installation of Wardrobes 4 25-Dec-12 29-Dec-12 19-Jan-13 22-Jan-13 20
A40420 Screed Works 9 30-Dec-12 09-Jan-13 23-Jan-13 03-Feb-13 20
A40010 Floor & Wall Tiles Work (Dry Area) 3 10-Jan-13 13-Jan-13 17-Mar-13 19-Mar-13 55
A40020 Water Proofing for Wet Area 4 10-Jan-13 14-Jan-13 04-Feb-13 07-Feb-13 20
A40460 Installation of Suspended Ceiling Grid (Wet Area) 4 15-Jan-13 19-Jan-13 10-Feb-13 13-Feb-13 21
A40450 Suspended Ceiling Tiles (Wet Area) 4 20-Jan-13 23-Jan-13 14-Feb-13 18-Feb-13 21
A40440 Floor Tiles Work (Wet Area) 5 26-Jan-13 30-Jan-13 28-Feb-13 05-Mar-13 29
SecondSecond Stage Finishes 7 31-Jan-13 07-Feb-13 12-Mar-13 07-Apr-13 50
A40040 Installation of Windows&Doors 3 31-Jan-13 03-Feb-13 12-Mar-13 14-Mar-13 34
A40110 Doors Ironmongery 3 31-Jan-13 03-Feb-13 04-Apr-13 07-Apr-13 54
A40090 Installation of Vanity Counter 2 04-Feb-13 05-Feb-13 21-Mar-13 23-Mar-13 39
A40050 Installation of Mirrors 3 04-Feb-13 06-Feb-13 20-Mar-13 23-Mar-13 38
A40060 Installation of Kitchen Cabinets 3 04-Feb-13 06-Feb-13 19-Mar-13 21-Mar-13 37
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Floor & Wall Tiles Work (Dry Area)
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Vanity Counter
Installation of Mirrors
Installation of Kitchen Cabinets
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 41 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A40080 Installation of Balustrades& Handrails 3 04-Feb-13 06-Feb-13 04-Apr-13 07-Apr-13 51
A40400 Installation of Toliets Accessories 4 04-Feb-13 07-Feb-13 16-Mar-13 19-Mar-13 34
Final StFinal Stage Finishes 180 09-Feb-13 08-Sep-13 08-Apr-13 02-Oct-13 21
A40000 Final Coat Paint 5 09-Feb-13 13-Feb-13 08-Apr-13 13-Apr-13 50
A40070 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A40410 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A40120 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 107 29-Sep-12 06-Feb-13 19-Nov-12 13-Apr-13 56
HVACHVAC 99 29-Sep-12 28-Jan-13 04-Dec-12 05-Mar-13 31
A40130 Duct Installation & Insulation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53
A40140 Chilled Water Pipe Installation & Insulation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53
A40150 Condensate Pipe Installation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53
A40160 FCU Installation 2 07-Oct-12 08-Oct-12 12-Dec-12 13-Dec-12 53
A40170 Air-Outlet Installation 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31
ElectricElectrical 100 29-Sep-12 29-Jan-13 25-Nov-12 05-Mar-13 30
A40180 Install Conduits in Wall 3 29-Sep-12 01-Oct-12 25-Nov-12 27-Nov-12 46
A40190 Install Cable Trays & Trunking 4 29-Sep-12 02-Oct-12 29-Nov-12 04-Dec-12 50
A40230 Cable Laying for Low Current System 3 03-Oct-12 06-Oct-12 16-Dec-12 18-Dec-12 59
A40240 Cable Laying for Power 3 03-Oct-12 06-Oct-12 16-Dec-12 18-Dec-12 59
A40200 Wiring for Lighting & Power 3 05-Nov-12 07-Nov-12 11-Dec-12 13-Dec-12 29
A40210 Wiring for Low Current System 3 05-Nov-12 07-Nov-12 11-Dec-12 13-Dec-12 29
A40220 DB installation,Dressing & Termination 6 10-Dec-12 16-Dec-12 05-Jan-13 10-Jan-13 21
A40270 Installation of Sockets 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31
A40260 Installation of Lighting Fittings 4 26-Jan-13 29-Jan-13 02-Mar-13 05-Mar-13 30
PlumbinPlumbing 107 29-Sep-12 06-Feb-13 19-Nov-12 07-Apr-13 51
A40290 H/L Drainage Pipes Installation 4 29-Sep-12 02-Oct-12 22-Jan-13 27-Jan-13 94
A40300 H/L Hot&Cold Water Pipe Installation 4 29-Sep-12 02-Oct-12 31-Jan-13 04-Feb-13 101
A40280 Drainge Pipes in Wall 8 29-Sep-12 07-Oct-12 19-Nov-12 27-Nov-12 41
A40310 Drainage&Water Pipes Testing 4 03-Oct-12 07-Oct-12 05-Feb-13 09-Feb-13 101
A40320 ElectricalWater Heater Installation 4 03-Oct-12 07-Oct-12 05-Feb-13 09-Feb-13 101
A40350 Water Pipes in Wall 8 29-Sep-12 07-Oct-12 19-Nov-12 27-Nov-12 41
A40330 Floor Drain Fixning 3 02-Jan-13 05-Jan-13 27-Feb-13 02-Mar-13 47
A40340 Installation of Sanitaryware 3 04-Feb-13 06-Feb-13 04-Apr-13 07-Apr-13 51
Fire FigFire Fighting 101 29-Sep-12 30-Jan-13 08-Dec-12 13-Apr-13 62
A40390 Fire Fighting Pipe 3 29-Sep-12 01-Oct-12 08-Dec-12 10-Dec-12 56
A40380 Hydro Static Test for Pipes 3 02-Oct-12 04-Oct-12 11-Dec-12 13-Dec-12 56
A40370 Sprinkler Fixing 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31
A40470 Fire Alarm Devices 3 26-Jan-13 28-Jan-13 04-Apr-13 07-Apr-13 59
A40360 Installation of Fire Extingusher&Blanket 2 29-Jan-13 30-Jan-13 11-Apr-13 13-Apr-13 62
Two BedroTwo Bedroom Flats 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21
FinishingFinishing Works 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21
Wet WoWet Works 82 05-Sep-12 13-Dec-12 22-Sep-12 11-Mar-13 73
A40630 Block Works 15 05-Sep-12 22-Sep-12 22-Sep-12 08-Oct-12 14
A40490 Installation of Doors& Windows Sub-frame 7 02-Oct-12 09-Oct-12 04-Mar-13 11-Mar-13 125
A40480 Plaster Works 20 02-Oct-12 24-Oct-12 18-Oct-12 12-Nov-12 14
A40510 Installation of Suspended Ceiling Grid (Dry Area) 8 31-Oct-12 08-Nov-12 18-Nov-12 26-Nov-12 14
A40500 1st Coat Paint 18 10-Nov-12 01-Dec-12 27-Nov-12 18-Dec-12 14
A40960 Wall Tiles Work (Wet Area) 13 28-Nov-12 13-Dec-12 20-Jan-13 04-Feb-13 43
Fisrt StaFisrt Stage Finishes 47 25-Dec-12 19-Feb-13 12-Jan-13 02-Apr-13 36
A40520 Suspended Ceiling Tiles (DryArea) 12 25-Dec-12 08-Jan-13 12-Jan-13 26-Jan-13 14
A40560 Installation of Wardrobes 8 09-Jan-13 17-Jan-13 27-Jan-13 04-Feb-13 14
A40950 Screed Works 9 19-Jan-13 29-Jan-13 05-Feb-13 14-Feb-13 14
A40550 Water Proofing for Wet Area 9 22-Jan-13 02-Feb-13 09-Feb-13 18-Feb-13 14
A40990 Installation of Suspended Ceiling Grid (Wet Area) 7 29-Jan-13 05-Feb-13 14-Feb-13 21-Feb-13 14
A40540 Floor & Wall Tiles Work (Dry Area) 12 30-Jan-13 12-Feb-13 20-Mar-13 02-Apr-13 42
A40980 Suspended Ceiling Tiles (Wet Area) 10 03-Feb-13 13-Feb-13 19-Feb-13 02-Mar-13 14
A40970 Floor Tiles Work (Wet Area) 5 14-Feb-13 19-Feb-13 06-Mar-13 11-Mar-13 17
SecondSecond Stage Finishes 19 20-Feb-13 13-Mar-13 12-Mar-13 02-Apr-13 17
A40640 Doors Ironmongery 6 20-Feb-13 26-Feb-13 27-Mar-13 02-Apr-13 30
A40570 Installation of Windows&Doors 7 20-Feb-13 27-Feb-13 12-Mar-13 19-Mar-13 17
A40610 Installation of Balustrades& Handrails 5 28-Feb-13 05-Mar-13 28-Mar-13 02-Apr-13 24
A40580 Installation of Mirrors 9 28-Feb-13 10-Mar-13 24-Mar-13 02-Apr-13 20
A40620 Installation of Vanity Counter 9 28-Feb-13 10-Mar-13 24-Mar-13 02-Apr-13 20
A40590 Installation of Kitchen Cabinets 10 28-Feb-13 11-Mar-13 23-Mar-13 02-Apr-13 19
A40930 Installation of Toliets Accessories 12 28-Feb-13 13-Mar-13 20-Mar-13 02-Apr-13 17
Final StFinal Stage Finishes 151 14-Mar-13 08-Sep-13 03-Apr-13 02-Oct-13 21
A40530 Final Coat Paint 9 14-Mar-13 24-Mar-13 03-Apr-13 13-Apr-13 17
A40600 Installation of Carpets 4 25-Mar-13 28-Mar-13 22-Apr-13 25-Apr-13 24
A40940 Installation of Sinages 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24
A40650 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 133 23-Sep-12 03-Mar-13 09-Oct-12 13-Apr-13 35
HVACHVAC 116 23-Sep-12 11-Feb-13 06-Nov-12 05-Mar-13 19
A40660 Duct Installation & Insulation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36
A40670 Chilled Water Pipe Installation & Insulation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36
A40680 Condensate Pipe Installation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36
A40690 FCU Installation 2 01-Oct-12 02-Oct-12 14-Nov-12 17-Nov-12 36
A40700 Air-Outlet Installation 3 09-Feb-13 11-Feb-13 03-Mar-13 05-Mar-13 19
ElectricElectrical 117 23-Sep-12 12-Feb-13 15-Oct-12 05-Mar-13 18
A40710 Install Conduits in Wall 3 23-Sep-12 25-Sep-12 15-Oct-12 17-Oct-12 19
A40720 Install Cable Trays & Trunking 4 23-Sep-12 26-Sep-12 06-Nov-12 10-Nov-12 36
A40760 Cable Laying for Low Current System 3 27-Sep-12 30-Sep-12 24-Nov-12 26-Nov-12 46
A40770 Cable Laying for Power 3 27-Sep-12 30-Sep-12 24-Nov-12 26-Nov-12 46
A40730 Wiring for Lighting & Power 3 28-Oct-12 30-Oct-12 13-Nov-12 17-Nov-12 14
A40740 Wiring for Low Current System 3 28-Oct-12 30-Oct-12 13-Nov-12 17-Nov-12 14
A40750 DB installation,Dressing & Termination 6 03-Dec-12 09-Dec-12 19-Jan-13 26-Jan-13 39
A40800 Installation of Sockets 3 09-Feb-13 11-Feb-13 03-Mar-13 05-Mar-13 19
A40790 Installation of Lighting Fittings 4 09-Feb-13 12-Feb-13 02-Mar-13 05-Mar-13 18
PlumbinPlumbing 133 23-Sep-12 03-Mar-13 09-Oct-12 02-Apr-13 26
A40820 H/L Drainage Pipes Installation 4 23-Sep-12 26-Sep-12 17-Jan-13 21-Jan-13 95
A40830 H/L Hot&Cold Water Pipe Installation 4 23-Sep-12 26-Sep-12 05-Feb-13 09-Feb-13 110
A40810 Drainge Pipes in Wall 8 23-Sep-12 01-Oct-12 09-Oct-12 17-Oct-12 14
A40840 Drainage&Water Pipes Testing 4 27-Sep-12 01-Oct-12 10-Feb-13 13-Feb-13 110
A40850 ElectricalWater Heater Installation 4 27-Sep-12 01-Oct-12 10-Feb-13 13-Feb-13 110
A40880 Water Pipes in Wall 8 23-Sep-12 01-Oct-12 09-Oct-12 17-Oct-12 14
A40860 Floor Drain Fixning 3 21-Jan-13 23-Jan-13 03-Mar-13 05-Mar-13 34
A40870 Installation of Sanitaryware 3 28-Feb-13 03-Mar-13 31-Mar-13 02-Apr-13 26
Fire FigFire Fighting 123 23-Sep-12 19-Feb-13 10-Nov-12 13-Apr-13 45
A40920 Fire Fighting Pipe 3 23-Sep-12 25-Sep-12 10-Nov-12 12-Nov-12 39
A40910 Hydro Static Test for Pipes 3 26-Sep-12 29-Sep-12 13-Nov-12 17-Nov-12 39
A40900 Sprinkler Fixing 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14
A41000 Fire Alarm Devices 3 14-Feb-13 17-Feb-13 31-Mar-13 02-Apr-13 38
A40890 Installation of Fire Extingusher&Blanket 2 18-Feb-13 19-Feb-13 11-Apr-13 13-Apr-13 45
6th Floor6th Floor 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21
Public AreaPublic Area 150 18-Oct-12 17-Apr-13 25-Nov-12 25-Apr-13 7
Garbage RGarbage Room 66 30-Oct-12 17-Jan-13 15-Jan-13 25-Apr-13 83
FinishingFinishing Works 66 30-Oct-12 17-Jan-13 15-Jan-13 25-Apr-13 83
Wet WorWet Works 56 30-Oct-12 06-Jan-13 15-Jan-13 14-Feb-13 33
A19410 Block Works 3 30-Oct-12 01-Nov-12 15-Jan-13 17-Jan-13 63
A19360 Installation of Doors& Windows Sub-frame 1 20-Nov-12 20-Nov-12 14-Feb-13 14-Feb-13 71
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Wall Tiles Work (Wet Area)
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Doors Ironmongery
Installation of Windows&Doors
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 42 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A19350 Plaster Works 3 20-Nov-12 22-Nov-12 23-Jan-13 27-Jan-13 53
A19390 Wall Tiles Work 4 26-Nov-12 29-Nov-12 30-Jan-13 03-Feb-13 53
A19370 1st Coat Paint 2 05-Jan-13 06-Jan-13 04-Feb-13 05-Feb-13 25
Fisrt StaFisrt Stage Finishes 7 07-Jan-13 14-Jan-13 10-Feb-13 24-Apr-13 85
A19540 Screed Works 2 07-Jan-13 08-Jan-13 10-Feb-13 11-Feb-13 28
A19560 Floor Tiles Work 2 10-Jan-13 12-Jan-13 13-Feb-13 14-Feb-13 28
A19420 Doors Ironmongery 1 13-Jan-13 13-Jan-13 24-Apr-13 24-Apr-13 86
A19400 Installation of Doors 2 13-Jan-13 14-Jan-13 16-Feb-13 17-Feb-13 28
Second SSecond Stage Finishes 2 15-Jan-13 16-Jan-13 01-Apr-13 02-Apr-13 64
A19380 Final Coat Paint 2 15-Jan-13 16-Jan-13 01-Apr-13 02-Apr-13 64
Final StaFinal Stage Finishes 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83
A19530 Installation of Sinages 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83
MEP WorkMEP Works 60 03-Nov-12 14-Jan-13 19-Jan-13 31-Mar-13 64
ElectricalElectrical 60 03-Nov-12 14-Jan-13 21-Jan-13 05-Mar-13 42
A19430 Install Conduits in Wall 2 03-Nov-12 04-Nov-12 21-Jan-13 22-Jan-13 65
A19440 Wiring for Lighting & Power 2 24-Nov-12 25-Nov-12 28-Jan-13 29-Jan-13 53
A19450 Installation of Lighting Fittings 2 13-Jan-13 14-Jan-13 04-Mar-13 05-Mar-13 42
PlumbingPlumbing 56 03-Nov-12 09-Jan-13 19-Jan-13 12-Feb-13 28
A19460 Drainge Pipes in Wall 2 03-Nov-12 04-Nov-12 19-Jan-13 20-Jan-13 63
A19490 Water Pipes in Wall 2 03-Nov-12 04-Nov-12 19-Jan-13 20-Jan-13 63
A19470 Drainage&Water Pipes Testing 2 05-Nov-12 06-Nov-12 21-Jan-13 22-Jan-13 63
A19480 Floor Drain Fixning 1 09-Jan-13 09-Jan-13 12-Feb-13 12-Feb-13 28
Fire FighFire Fighting 59 04-Nov-12 14-Jan-13 25-Feb-13 31-Mar-13 64
A19520 Fire Fighting Pipe 2 04-Nov-12 05-Nov-12 25-Feb-13 26-Feb-13 93
A19510 Hydro Static Test for Pipes 2 06-Nov-12 07-Nov-12 02-Mar-13 03-Mar-13 95
A19500 Sprinkler Fixing 2 13-Jan-13 14-Jan-13 04-Mar-13 05-Mar-13 42
A19550 Fire Alarm Devices 2 13-Jan-13 14-Jan-13 30-Mar-13 31-Mar-13 64
Corridor &Corridor & Lift Lobby 150 18-Oct-12 17-Apr-13 10-Dec-12 25-Apr-13 7
FinishingFinishing Works 150 18-Oct-12 17-Apr-13 10-Dec-12 25-Apr-13 7
Wet WorWet Works 50 18-Oct-12 19-Dec-12 10-Dec-12 23-Jan-13 29
A19070 Block Works 8 18-Oct-12 29-Oct-12 10-Dec-12 18-Dec-12 41
A19010 Plaster Works 7 11-Nov-12 19-Nov-12 22-Dec-12 29-Dec-12 33
A19030 Installation of Suspended Ceiling Grid 6 05-Dec-12 11-Dec-12 05-Jan-13 10-Jan-13 25
A19040 Suspended Ceiling Tiles 6 12-Dec-12 18-Dec-12 12-Jan-13 17-Jan-13 25
A19330 MDF for Lift Lobby Wall 7 12-Dec-12 19-Dec-12 16-Jan-13 23-Jan-13 29
Fisrt StaFisrt Stage Finishes 12 20-Dec-12 03-Jan-13 26-Jan-13 03-Feb-13 25
A19310 Screed Works 3 20-Dec-12 23-Dec-12 26-Jan-13 28-Jan-13 29
A19020 1st Coat Paint 5 29-Dec-12 03-Jan-13 29-Jan-13 03-Feb-13 25
Second SSecond Stage Finishes 2 15-Jan-13 16-Jan-13 18-Feb-13 25-Apr-13 84
A19050 Installation of Doors 2 15-Jan-13 16-Jan-13 18-Feb-13 19-Feb-13 28
A19080 Doors Ironmongery 2 15-Jan-13 16-Jan-13 24-Apr-13 25-Apr-13 84
Final StaFinal Stage Finishes 20 26-Mar-13 17-Apr-13 03-Apr-13 25-Apr-13 7
A19060 Installation of Carpets 4 26-Mar-13 30-Mar-13 03-Apr-13 07-Apr-13 7
A19320 Fixing of Wall Covering 7 31-Mar-13 07-Apr-13 08-Apr-13 15-Apr-13 7
A19300 Installation of Sinages 9 08-Apr-13 17-Apr-13 16-Apr-13 25-Apr-13 7
MEP WorkMEP Works 49 30-Oct-12 27-Dec-12 19-Dec-12 05-Mar-13 56
HVACHVAC 44 30-Oct-12 22-Dec-12 25-Dec-12 28-Jan-13 30
A19090 Duct Installation & Insulation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46
A19100 Chilled Water Pipe Installation & Insulation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46
A19110 Condensate Pipe Installation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46
A19120 FCU Installation 3 05-Nov-12 07-Nov-12 31-Dec-12 03-Jan-13 46
A19130 Air-Outlet Installation 3 19-Dec-12 22-Dec-12 26-Jan-13 28-Jan-13 30
ElectricalElectrical 45 30-Oct-12 23-Dec-12 19-Dec-12 05-Mar-13 60
A19140 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 19-Dec-12 20-Dec-12 41
A19150 Install Cable Trays & Trunking 2 30-Oct-12 31-Oct-12 25-Dec-12 26-Dec-12 46
A19190 Cable Laying for Low Current System 2 01-Nov-12 03-Nov-12 09-Jan-13 10-Jan-13 56
A19200 Cable Laying for Power 3 01-Nov-12 04-Nov-12 08-Jan-13 10-Jan-13 55
A19160 Wiring for Lighting & Power 3 20-Nov-12 22-Nov-12 31-Dec-12 03-Jan-13 34
A19170 Wiring for Low Current System 4 20-Nov-12 24-Nov-12 30-Dec-12 03-Jan-13 33
A19180 DB installation,Dressing & Termination 6 12-Dec-12 18-Dec-12 12-Jan-13 17-Jan-13 25
A19220 Installation of Lighting Fittings 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61
A19230 Installation of Sockets 4 19-Dec-12 23-Dec-12 02-Mar-13 05-Mar-13 60
PlumbingPlumbing 5 30-Oct-12 04-Nov-12 29-Dec-12 03-Jan-13 49
A19240 H/L Hot&Cold Water Pipe Installation 5 30-Oct-12 04-Nov-12 29-Dec-12 03-Jan-13 49
Fire FighFire Fighting 49 30-Oct-12 27-Dec-12 25-Dec-12 28-Jan-13 25
A19290 Fire Fighting Pipe 4 30-Oct-12 03-Nov-12 25-Dec-12 29-Dec-12 46
A19280 Hydro Static Test for Pipes 4 04-Nov-12 07-Nov-12 30-Dec-12 03-Jan-13 46
A19270 Sprinkler Fixing 4 19-Dec-12 23-Dec-12 19-Jan-13 22-Jan-13 25
A19340 Fire Alarm Devices 5 19-Dec-12 24-Dec-12 22-Jan-13 28-Jan-13 28
A19260 Installation of Fire Extingusher&Blanket 4 24-Dec-12 27-Dec-12 23-Jan-13 28-Jan-13 25
Electrical /Electrical /Telephone/ELV Rooms 83 03-Nov-12 11-Feb-13 23-Jan-13 25-Apr-13 63
FinishingFinishing Works 83 03-Nov-12 11-Feb-13 23-Jan-13 25-Apr-13 63
Wet WorWet Works 56 03-Nov-12 09-Jan-13 23-Jan-13 19-Feb-13 34
A19620 Block Works 3 03-Nov-12 05-Nov-12 23-Jan-13 27-Jan-13 67
A19580 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 19-Feb-13 19-Feb-13 72
A19570 Plaster Works 4 24-Nov-12 27-Nov-12 30-Jan-13 03-Feb-13 55
A19590 1st Coat Paint 3 07-Jan-13 09-Jan-13 06-Feb-13 09-Feb-13 25
Fisrt StaFisrt Stage Finishes 17 17-Jan-13 06-Feb-13 20-Feb-13 23-Apr-13 65
A19610 Installation of Doors 2 17-Jan-13 19-Jan-13 20-Feb-13 21-Feb-13 28
A19630 Doors Ironmongery 2 17-Jan-13 19-Jan-13 22-Apr-13 23-Apr-13 80
A19680 Epoxy Paint Works 2 05-Feb-13 06-Feb-13 30-Mar-13 31-Mar-13 45
Second SSecond Stage Finishes 2 07-Feb-13 09-Feb-13 01-Apr-13 02-Apr-13 45
A19600 Final Coat Paint 2 07-Feb-13 09-Feb-13 01-Apr-13 02-Apr-13 45
Final StaFinal Stage Finishes 2 10-Feb-13 11-Feb-13 24-Apr-13 25-Apr-13 63
A19670 Installation of Sinages 2 10-Feb-13 11-Feb-13 24-Apr-13 25-Apr-13 63
MEP WorkMEP Works 74 06-Nov-12 04-Feb-13 28-Jan-13 28-Mar-13 45
HVACHVAC 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
A19710 Air-Outlet Installation 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
ElectricalElectrical 74 06-Nov-12 04-Feb-13 28-Jan-13 05-Mar-13 25
A19640 Install Conduits in Wall 2 06-Nov-12 07-Nov-12 28-Jan-13 29-Jan-13 67
A19650 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 04-Feb-13 05-Feb-13 55
A19700 Installation of SMDBs 7 10-Jan-13 17-Jan-13 24-Feb-13 03-Mar-13 37
A19660 Installation of Lighting Fittings 2 19-Jan-13 20-Jan-13 04-Mar-13 05-Mar-13 37
A114550 Installation of Access ControlSystem 20 10-Jan-13 03-Feb-13 11-Feb-13 05-Mar-13 26
A114530 Installation of MATC,TV System 20 10-Jan-13 03-Feb-13 11-Feb-13 05-Mar-13 26
A114540 Installation of Telephone System 21 10-Jan-13 04-Feb-13 10-Feb-13 05-Mar-13 25
Fire FighFire Fighting 2 21-Jan-13 22-Jan-13 27-Mar-13 28-Mar-13 55
A19690 Fire Alarm Devices 2 21-Jan-13 22-Jan-13 27-Mar-13 28-Mar-13 55
Room ServRoom Service 66 06-Nov-12 26-Jan-13 29-Jan-13 25-Apr-13 77
FinishingFinishing Works 66 06-Nov-12 26-Jan-13 29-Jan-13 25-Apr-13 77
Wet WorWet Works 56 06-Nov-12 13-Jan-13 29-Jan-13 21-Feb-13 33
A19770 Block Works 2 06-Nov-12 07-Nov-12 29-Jan-13 30-Jan-13 68
A19730 Installation of Doors& Windows Sub-frame 1 28-Nov-12 28-Nov-12 21-Feb-13 21-Feb-13 70
A19720 Plaster Works 4 28-Nov-12 03-Dec-12 05-Feb-13 09-Feb-13 56
A19740 1st Coat Paint 3 10-Jan-13 13-Jan-13 12-Feb-13 14-Feb-13 27
Fisrt StaFisrt Stage Finishes 7 14-Jan-13 21-Jan-13 16-Feb-13 24-Apr-13 79
A19900 Screed Works 2 14-Jan-13 15-Jan-13 16-Feb-13 17-Feb-13 27
A19920 Floor Tiles Work 3 17-Jan-13 20-Jan-13 19-Feb-13 21-Feb-13 27
A19760 Installation of Doors 1 21-Jan-13 21-Jan-13 23-Feb-13 23-Feb-13 27
A19780 Doors Ironmongery 1 21-Jan-13 21-Jan-13 24-Apr-13 24-Apr-13 79
Second SSecond Stage Finishes 1 23-Jan-13 23-Jan-13 02-Apr-13 02-Apr-13 58
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access ControlSystem
Installation of MATC,TV System
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 43 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A19750 Final Coat Paint 1 23-Jan-13 23-Jan-13 02-Apr-13 02-Apr-13 58
Final StaFinal Stage Finishes 1 26-Jan-13 26-Jan-13 25-Apr-13 25-Apr-13 77
A19890 Installation of Sinages 1 26-Jan-13 26-Jan-13 25-Apr-13 25-Apr-13 77
MEP WorkMEP Works 62 08-Nov-12 22-Jan-13 31-Jan-13 01-Apr-13 58
HVACHVAC 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35
A19930 Air-Outlet Installation 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35
ElectricalElectrical 62 08-Nov-12 22-Jan-13 03-Feb-13 05-Mar-13 35
A19790 Install Conduits in Wall 2 08-Nov-12 10-Nov-12 03-Feb-13 04-Feb-13 70
A19800 Wiring for Lighting & Power 2 04-Dec-12 05-Dec-12 10-Feb-13 11-Feb-13 56
A19810 Installation of Lighting Fittings 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35
PlumbingPlumbing 57 08-Nov-12 16-Jan-13 31-Jan-13 18-Feb-13 27
A19820 Drainge Pipes in Wall 2 08-Nov-12 10-Nov-12 31-Jan-13 02-Feb-13 68
A19850 Water Pipes in Wall 2 08-Nov-12 10-Nov-12 31-Jan-13 02-Feb-13 68
A19830 Drainage&Water Pipes Testing 2 11-Nov-12 12-Nov-12 03-Feb-13 04-Feb-13 68
A19840 Floor Drain Fixning 1 16-Jan-13 16-Jan-13 18-Feb-13 18-Feb-13 27
Fire FighFire Fighting 62 08-Nov-12 22-Jan-13 27-Feb-13 01-Apr-13 58
A19880 Fire Fighting Pipe 2 08-Nov-12 10-Nov-12 27-Feb-13 28-Feb-13 91
A19870 Hydro Static Test for Pipes 2 11-Nov-12 12-Nov-12 02-Mar-13 03-Mar-13 91
A19860 Sprinkler Fixing 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35
A19910 Fire Alarm Devices 2 21-Jan-13 22-Jan-13 31-Mar-13 01-Apr-13 58
StaircaseStaircase 59 23-Oct-12 05-Jan-13 25-Nov-12 02-Apr-13 74
Stair 1Stair 1 45 23-Oct-12 18-Dec-12 25-Nov-12 02-Apr-13 88
A108770 Floor Screed 3 23-Oct-12 28-Oct-12 25-Nov-12 27-Nov-12 25
A108780 Install Handrails 4 29-Oct-12 01-Nov-12 28-Nov-12 03-Dec-12 25
A108790 Ceiling 1st Coat Paint 7 03-Nov-12 10-Nov-12 04-Dec-12 11-Dec-12 25
A108800 Wall 1st Coat Paint 7 11-Nov-12 19-Nov-12 12-Dec-12 19-Dec-12 25
A108810 Install Granite/Terrazo 12 20-Nov-12 04-Dec-12 29-Dec-12 12-Jan-13 32
A108820 Final Coat Paint 12 05-Dec-12 18-Dec-12 20-Mar-13 02-Apr-13 88
Stair 2Stair 2 56 29-Oct-12 05-Jan-13 12-Dec-12 02-Apr-13 74
A108830 Floor Screed 3 29-Oct-12 31-Oct-12 12-Dec-12 15-Dec-12 36
A108840 Install Handrails 4 03-Nov-12 06-Nov-12 16-Dec-12 19-Dec-12 35
A108850 Ceiling 1st Coat Paint 7 20-Nov-12 27-Nov-12 20-Dec-12 27-Dec-12 25
A108860 Wall 1st Coat Paint 7 28-Nov-12 06-Dec-12 29-Dec-12 06-Jan-13 25
A108870 Install Granite/Terrazo 12 08-Dec-12 20-Dec-12 13-Jan-13 27-Jan-13 30
A108880 Final Coat Paint 12 22-Dec-12 05-Jan-13 20-Mar-13 02-Apr-13 74
ApartementsApartements 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21
Studio FlatsStudio Flats 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21
FinishingFinishing Works 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21
Wet WoWet Works 44 14-Oct-12 08-Dec-12 13-Nov-12 23-Feb-13 64
A41160 Block Works 4 14-Oct-12 17-Oct-12 13-Nov-12 18-Nov-12 24
A41020 Installation of Doors& Windows Sub-frame 1 03-Nov-12 03-Nov-12 23-Feb-13 23-Feb-13 92
A41010 Plaster Works 7 03-Nov-12 10-Nov-12 24-Nov-12 01-Dec-12 17
A41040 Installation of Suspended Ceiling Grid (Dry Area) 6 27-Nov-12 04-Dec-12 06-Dec-12 12-Dec-12 7
A41490 Wall Tiles Work (Wet Area) 8 25-Nov-12 04-Dec-12 16-Jan-13 26-Jan-13 43
A41030 1st Coat Paint 3 05-Dec-12 08-Dec-12 13-Dec-12 16-Dec-12 7
Fisrt StaFisrt Stage Finishes 23 09-Dec-12 05-Jan-13 17-Dec-12 05-Mar-13 50
A41050 Suspended Ceiling Tiles (DryArea) 6 09-Dec-12 15-Dec-12 17-Dec-12 23-Dec-12 7
A41090 Installation of Wardrobes 2 16-Dec-12 17-Dec-12 06-Jan-13 07-Jan-13 17
A41480 Screed Works 5 18-Dec-12 23-Dec-12 27-Jan-13 31-Jan-13 32
A41080 Water Proofing for Wet Area 3 24-Dec-12 26-Dec-12 02-Feb-13 04-Feb-13 32
A41070 Floor & Wall Tiles Work (Dry Area) 4 24-Dec-12 27-Dec-12 02-Mar-13 05-Mar-13 56
A41520 Installation of Suspended Ceiling Grid (Wet Area) 3 27-Dec-12 30-Dec-12 05-Feb-13 07-Feb-13 32
A41510 Suspended Ceiling Tiles (Wet Area) 2 31-Dec-12 02-Jan-13 11-Feb-13 12-Feb-13 34
A41500 Floor Tiles Work (Wet Area) 2 03-Jan-13 05-Jan-13 16-Feb-13 17-Feb-13 36
SecondSecond Stage Finishes 4 22-Jan-13 27-Jan-13 24-Feb-13 26-Mar-13 50
A41100 Installation of Windows&Doors 2 22-Jan-13 23-Jan-13 24-Feb-13 25-Feb-13 27
A41170 Doors Ironmongery 2 22-Jan-13 23-Jan-13 25-Mar-13 26-Mar-13 52
A41110 Installation of Mirrors 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50
A41120 Installation of Kitchen Cabinets 2 26-Jan-13 27-Jan-13 12-Mar-13 13-Mar-13 39
A41140 Installation of Balustrades& Handrails 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50
A41150 Installation of Vanity Counter 2 26-Jan-13 27-Jan-13 23-Mar-13 24-Mar-13 48
A41460 Installation of Toliets Accessories 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50
Final StFinal Stage Finishes 189 29-Jan-13 08-Sep-13 27-Mar-13 02-Oct-13 21
A41060 Final Coat Paint 6 29-Jan-13 04-Feb-13 27-Mar-13 02-Apr-13 49
A41130 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A41470 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A41180 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 82 18-Oct-12 28-Jan-13 19-Nov-12 02-Apr-13 55
HVACHVAC 64 18-Oct-12 06-Jan-13 25-Nov-12 05-Mar-13 49
A41190 Duct Installation & Insulation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29
A41200 Chilled Water Pipe Installation & Insulation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29
A41210 Condensate Pipe Installation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29
A41220 FCU Installation 2 29-Oct-12 30-Oct-12 04-Dec-12 05-Dec-12 29
A41230 Air-Outlet Installation 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49
ElectricElectrical 65 18-Oct-12 07-Jan-13 20-Nov-12 05-Mar-13 48
A41240 Install Conduits in Wall 3 18-Oct-12 21-Oct-12 20-Nov-12 22-Nov-12 25
A41250 Install Cable Trays & Trunking 4 18-Oct-12 22-Oct-12 25-Nov-12 28-Nov-12 29
A41290 Cable Laying for Low Current System 3 23-Oct-12 28-Oct-12 10-Dec-12 12-Dec-12 37
A41300 Cable Laying for Power 3 23-Oct-12 28-Oct-12 10-Dec-12 12-Dec-12 37
A41260 Wiring for Lighting & Power 3 11-Nov-12 13-Nov-12 03-Dec-12 05-Dec-12 17
A41270 Wiring for Low Current System 3 11-Nov-12 13-Nov-12 03-Dec-12 05-Dec-12 17
A41280 DB installation,Dressing & Termination 6 09-Dec-12 15-Dec-12 17-Dec-12 23-Dec-12 7
A41330 Installation of Sockets 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49
A41320 Installation of Lighting Fittings 4 03-Jan-13 07-Jan-13 02-Mar-13 05-Mar-13 48
PlumbinPlumbing 82 18-Oct-12 28-Jan-13 19-Nov-12 26-Mar-13 49
A41340 Drainge Pipes in Wall 4 18-Oct-12 22-Oct-12 19-Nov-12 22-Nov-12 24
A41350 H/L Drainage Pipes Installation 4 18-Oct-12 22-Oct-12 27-Jan-13 30-Jan-13 80
A41360 H/L Hot&Cold Water Pipe Installation 4 18-Oct-12 22-Oct-12 27-Jan-13 30-Jan-13 80
A41410 Water Pipes in Wall 4 18-Oct-12 22-Oct-12 19-Nov-12 22-Nov-12 24
A41370 Drainage&Water Pipes Testing 4 23-Oct-12 29-Oct-12 31-Jan-13 04-Feb-13 80
A41380 ElectricalWater Heater Installation 4 23-Oct-12 29-Oct-12 31-Jan-13 04-Feb-13 80
A41390 Floor Drain Fixning 3 20-Dec-12 23-Dec-12 11-Feb-13 13-Feb-13 43
A41400 Installation of Sanitaryware 3 26-Jan-13 28-Jan-13 24-Mar-13 26-Mar-13 49
Fire FigFire Fighting 66 18-Oct-12 08-Jan-13 28-Nov-12 02-Apr-13 71
A41450 Fire Fighting Pipe 3 18-Oct-12 21-Oct-12 28-Nov-12 01-Dec-12 32
A41440 Hydro Static Test for Pipes 3 22-Oct-12 24-Oct-12 03-Dec-12 05-Dec-12 32
A41430 Sprinkler Fixing 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49
A41530 Fire Alarm Devices 3 03-Jan-13 06-Jan-13 24-Mar-13 26-Mar-13 67
A41420 Installation of Fire Extingusher&Blanket 2 07-Jan-13 08-Jan-13 01-Apr-13 02-Apr-13 71
One BedroOne Bedroom Flats 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21
FinishingFinishing Works 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21
Wet WoWet Works 46 08-Oct-12 04-Dec-12 30-Oct-12 25-Feb-13 69
A41690 Block Works 5 08-Oct-12 13-Oct-12 30-Oct-12 04-Nov-12 17
A41550 Installation of Doors& Windows Sub-frame 1 23-Oct-12 23-Oct-12 25-Feb-13 25-Feb-13 101
A41540 Plaster Works 7 23-Oct-12 01-Nov-12 14-Nov-12 22-Nov-12 17
A42020 Wall Tiles Work (Wet Area) 4 03-Nov-12 06-Nov-12 26-Dec-12 30-Dec-12 44
A41570 Installation of Suspended Ceiling Grid (Dry Area) 4 22-Nov-12 26-Nov-12 01-Dec-12 05-Dec-12 7
A41560 1st Coat Paint 6 27-Nov-12 04-Dec-12 06-Dec-12 12-Dec-12 7
Fisrt StaFisrt Stage Finishes 34 16-Dec-12 26-Jan-13 24-Dec-12 09-Mar-13 36
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 44 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A41580 Suspended Ceiling Tiles (DryArea) 4 16-Dec-12 19-Dec-12 24-Dec-12 27-Dec-12 7
A41620 Installation of Wardrobes 4 20-Dec-12 24-Dec-12 08-Jan-13 12-Jan-13 15
A42010 Screed Works 9 25-Dec-12 05-Jan-13 23-Jan-13 03-Feb-13 24
A41600 Floor & Wall Tiles Work (Dry Area) 3 06-Jan-13 08-Jan-13 06-Mar-13 09-Mar-13 50
A41610 Water Proofing for Wet Area 4 06-Jan-13 09-Jan-13 04-Feb-13 07-Feb-13 24
A42050 Installation of Suspended Ceiling Grid (Wet Area) 4 10-Jan-13 14-Jan-13 09-Feb-13 12-Feb-13 24
A42040 Suspended Ceiling Tiles (Wet Area) 4 15-Jan-13 19-Jan-13 13-Feb-13 17-Feb-13 24
A42030 Floor Tiles Work (Wet Area) 5 20-Jan-13 26-Jan-13 18-Feb-13 23-Feb-13 24
SecondSecond Stage Finishes 7 27-Jan-13 03-Feb-13 26-Feb-13 27-Mar-13 45
A41630 Installation of Windows&Doors 3 27-Jan-13 29-Jan-13 26-Feb-13 28-Feb-13 26
A41700 Doors Ironmongery 3 27-Jan-13 29-Jan-13 25-Mar-13 27-Mar-13 49
A41670 Installation of Balustrades& Handrails 2 30-Jan-13 31-Jan-13 26-Mar-13 27-Mar-13 47
A41640 Installation of Mirrors 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46
A41650 Installation of Kitchen Cabinets 3 30-Jan-13 02-Feb-13 14-Mar-13 17-Mar-13 37
A41680 Installation of Vanity Counter 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46
A41990 Installation of Toliets Accessories 4 30-Jan-13 03-Feb-13 24-Mar-13 27-Mar-13 45
Final StFinal Stage Finishes 184 04-Feb-13 08-Sep-13 28-Mar-13 02-Oct-13 21
A41590 Final Coat Paint 5 04-Feb-13 09-Feb-13 28-Mar-13 02-Apr-13 45
A41660 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A42000 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A41710 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 90 14-Oct-12 02-Feb-13 05-Nov-12 02-Apr-13 51
HVACHVAC 82 14-Oct-12 22-Jan-13 20-Nov-12 05-Mar-13 35
A41720 Duct Installation & Insulation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29
A41730 Chilled Water Pipe Installation & Insulation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29
A41740 Condensate Pipe Installation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29
A41750 FCU Installation 2 22-Oct-12 23-Oct-12 28-Nov-12 29-Nov-12 29
A41760 Air-Outlet Installation 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35
ElectricElectrical 83 14-Oct-12 23-Jan-13 11-Nov-12 05-Mar-13 34
A41770 Install Conduits in Wall 3 14-Oct-12 16-Oct-12 11-Nov-12 13-Nov-12 22
A41780 Install Cable Trays & Trunking 4 14-Oct-12 17-Oct-12 17-Nov-12 20-Nov-12 26
A41820 Cable Laying for Low Current System 3 18-Oct-12 21-Oct-12 03-Dec-12 05-Dec-12 35
A41830 Cable Laying for Power 3 18-Oct-12 21-Oct-12 03-Dec-12 05-Dec-12 35
A41790 Wiring for Lighting & Power 3 03-Nov-12 05-Nov-12 27-Nov-12 29-Nov-12 20
A41800 Wiring for Low Current System 3 03-Nov-12 05-Nov-12 27-Nov-12 29-Nov-12 20
A41810 DB installation,Dressing & Termination 6 05-Dec-12 11-Dec-12 22-Dec-12 27-Dec-12 14
A41860 Installation of Sockets 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35
A41850 Installation of Lighting Fittings 4 20-Jan-13 23-Jan-13 02-Mar-13 05-Mar-13 34
PlumbinPlumbing 90 14-Oct-12 02-Feb-13 05-Nov-12 27-Mar-13 46
A41880 H/L Drainage Pipes Installation 4 14-Oct-12 17-Oct-12 30-Jan-13 03-Feb-13 87
A41890 H/L Hot&Cold Water Pipe Installation 4 14-Oct-12 17-Oct-12 30-Jan-13 03-Feb-13 87
A41870 Drainge Pipes in Wall 8 14-Oct-12 22-Oct-12 05-Nov-12 13-Nov-12 17
A41900 Drainage&Water Pipes Testing 4 18-Oct-12 22-Oct-12 04-Feb-13 07-Feb-13 87
A41910 ElectricalWater Heater Installation 4 18-Oct-12 22-Oct-12 04-Feb-13 07-Feb-13 87
A41940 Water Pipes in Wall 8 14-Oct-12 22-Oct-12 05-Nov-12 13-Nov-12 17
A41920 Floor Drain Fixning 3 27-Dec-12 30-Dec-12 17-Feb-13 19-Feb-13 42
A41930 Installation of Sanitaryware 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46
Fire FigFire Fighting 84 14-Oct-12 26-Jan-13 24-Nov-12 02-Apr-13 57
A41980 Fire Fighting Pipe 3 14-Oct-12 16-Oct-12 24-Nov-12 26-Nov-12 32
A41970 Hydro Static Test for Pipes 3 17-Oct-12 20-Oct-12 27-Nov-12 29-Nov-12 32
A41960 Sprinkler Fixing 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35
A42060 Fire Alarm Devices 3 20-Jan-13 22-Jan-13 25-Mar-13 27-Mar-13 54
A41950 Installation of Fire Extingusher&Blanket 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57
Two BedroTwo Bedroom Flats 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21
FinishingFinishing Works 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21
Wet WoWet Works 69 20-Sep-12 13-Dec-12 29-Sep-12 28-Feb-13 64
A42220 Block Works 15 20-Sep-12 07-Oct-12 29-Sep-12 15-Oct-12 7
A42080 Installation of Doors& Windows Sub-frame 7 14-Oct-12 21-Oct-12 21-Feb-13 28-Feb-13 106
A42070 Plaster Works 20 14-Oct-12 07-Nov-12 22-Oct-12 17-Nov-12 7
A42100 Installation of Suspended Ceiling Grid (Dry Area) 8 12-Nov-12 21-Nov-12 21-Nov-12 29-Nov-12 7
A42550 Wall Tiles Work (Wet Area) 13 08-Nov-12 24-Nov-12 31-Dec-12 15-Jan-13 43
A42090 1st Coat Paint 18 22-Nov-12 13-Dec-12 08-Dec-12 27-Dec-12 12
Fisrt StaFisrt Stage Finishes 52 20-Dec-12 20-Feb-13 29-Dec-12 23-Mar-13 26
A42110 Suspended Ceiling Tiles (DryArea) 12 20-Dec-12 03-Jan-13 29-Dec-12 12-Jan-13 7
A42150 Installation of Wardrobes 8 05-Jan-13 13-Jan-13 13-Jan-13 21-Jan-13 7
A42540 Screed Works 9 14-Jan-13 23-Jan-13 22-Jan-13 02-Feb-13 7
A42140 Water Proofing for Wet Area 9 26-Jan-13 04-Feb-13 03-Feb-13 12-Feb-13 7
A42130 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 10-Mar-13 23-Mar-13 37
A42580 Installation of Suspended Ceiling Grid (Wet Area) 7 05-Feb-13 12-Feb-13 13-Feb-13 20-Feb-13 7
A42560 Floor Tiles Work (Wet Area) 5 16-Feb-13 20-Feb-13 24-Feb-13 28-Feb-13 7
A42570 Suspended Ceiling Tiles (Wet Area) 10 10-Feb-13 20-Feb-13 18-Feb-13 28-Feb-13 7
SecondSecond Stage Finishes 19 21-Feb-13 14-Mar-13 02-Mar-13 23-Mar-13 7
A42160 Installation of Windows&Doors 7 21-Feb-13 28-Feb-13 02-Mar-13 09-Mar-13 7
A42230 Doors Ironmongery 6 26-Feb-13 04-Mar-13 17-Mar-13 23-Mar-13 16
A42180 Installation of Kitchen Cabinets 5 02-Mar-13 06-Mar-13 18-Mar-13 23-Mar-13 14
A42210 Installation of Vanity Counter 7 02-Mar-13 09-Mar-13 16-Mar-13 23-Mar-13 12
A42170 Installation of Mirrors 9 02-Mar-13 11-Mar-13 13-Mar-13 23-Mar-13 10
A42200 Installation of Balustrades& Handrails 9 02-Mar-13 11-Mar-13 13-Mar-13 23-Mar-13 10
A42520 Installation of Toliets Accessories 12 02-Mar-13 14-Mar-13 10-Mar-13 23-Mar-13 7
Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21
A42120 Final Coat Paint 9 16-Mar-13 25-Mar-13 24-Mar-13 02-Apr-13 7
A42190 Installation of Carpets 4 26-Mar-13 30-Mar-13 22-Apr-13 25-Apr-13 23
A42530 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23
A42240 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 121 08-Oct-12 04-Mar-13 16-Oct-12 02-Apr-13 25
HVACHVAC 109 08-Oct-12 18-Feb-13 10-Nov-12 05-Mar-13 13
A42250 Duct Installation & Insulation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26
A42260 Chilled Water Pipe Installation & Insulation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26
A42270 Condensate Pipe Installation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26
A42280 FCU Installation 2 16-Oct-12 17-Oct-12 19-Nov-12 20-Nov-12 26
A42290 Air-Outlet Installation 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13
ElectricElectrical 110 08-Oct-12 19-Feb-13 18-Oct-12 05-Mar-13 12
A42300 Install Conduits in Wall 3 08-Oct-12 10-Oct-12 18-Oct-12 21-Oct-12 9
A42310 Install Cable Trays & Trunking 4 08-Oct-12 11-Oct-12 10-Nov-12 13-Nov-12 26
A42350 Cable Laying for Low Current System 3 13-Oct-12 15-Oct-12 27-Nov-12 29-Nov-12 36
A42360 Cable Laying for Power 3 13-Oct-12 15-Oct-12 27-Nov-12 29-Nov-12 36
A42320 Wiring for Lighting & Power 3 08-Nov-12 11-Nov-12 18-Nov-12 20-Nov-12 7
A42330 Wiring for Low Current System 3 08-Nov-12 11-Nov-12 18-Nov-12 20-Nov-12 7
A42340 DB installation,Dressing & Termination 6 15-Dec-12 20-Dec-12 06-Jan-13 12-Jan-13 18
A42390 Installation of Sockets 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13
A42380 Installation of Lighting Fittings 4 16-Feb-13 19-Feb-13 02-Mar-13 05-Mar-13 12
PlumbinPlumbing 121 08-Oct-12 04-Mar-13 16-Oct-12 23-Mar-13 16
A42410 H/L Drainage Pipes Installation 4 08-Oct-12 11-Oct-12 04-Feb-13 07-Feb-13 96
A42420 H/L Hot&Cold Water Pipe Installation 4 08-Oct-12 11-Oct-12 04-Feb-13 07-Feb-13 96
A42470 Water Pipes in Wall 4 08-Oct-12 11-Oct-12 17-Oct-12 21-Oct-12 8
A42400 Drainge Pipes in Wall 5 08-Oct-12 13-Oct-12 16-Oct-12 21-Oct-12 7
A42430 Drainage&Water Pipes Testing 4 13-Oct-12 16-Oct-12 09-Feb-13 12-Feb-13 96
A42440 ElectricalWater Heater Installation 4 13-Oct-12 16-Oct-12 09-Feb-13 12-Feb-13 96
A42450 Floor Drain Fixning 3 16-Jan-13 19-Jan-13 23-Feb-13 25-Feb-13 31
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Floor & Wall Tiles Work (Dry Area)
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Water Pipes in Wall
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Floor Tiles Work (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Mirrors
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainge Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 45 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A42460 Installation of Sanitaryware 3 02-Mar-13 04-Mar-13 20-Mar-13 23-Mar-13 16
Fire FigFire Fighting 114 08-Oct-12 24-Feb-13 13-Nov-12 02-Apr-13 32
A42510 Fire Fighting Pipe 3 08-Oct-12 10-Oct-12 13-Nov-12 17-Nov-12 29
A42500 Hydro Static Test for Pipes 3 11-Oct-12 14-Oct-12 18-Nov-12 20-Nov-12 29
A42490 Sprinkler Fixing 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13
A42480 Installation of Fire Extingusher&Blanket 2 19-Feb-13 20-Feb-13 01-Apr-13 02-Apr-13 35
A42590 Fire Alarm Devices 3 21-Feb-13 24-Feb-13 20-Mar-13 23-Mar-13 23
7th Floor7th Floor 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21
Public AreaPublic Area 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10
Garbage RGarbage Room 60 24-Oct-12 07-Jan-13 14-Jan-13 25-Apr-13 92
FinishingFinishing Works 60 24-Oct-12 07-Jan-13 14-Jan-13 25-Apr-13 92
Wet WorWet Works 50 24-Oct-12 25-Dec-12 14-Jan-13 14-Feb-13 42
A20340 Block Works 3 24-Oct-12 29-Oct-12 14-Jan-13 16-Jan-13 65
A20290 Installation of Doors& Windows Sub-frame 1 14-Nov-12 14-Nov-12 14-Feb-13 14-Feb-13 75
A20280 Plaster Works 3 14-Nov-12 18-Nov-12 22-Jan-13 26-Jan-13 56
A20320 Wall Tiles Work 4 21-Nov-12 25-Nov-12 29-Jan-13 02-Feb-13 56
A20300 1st Coat Paint 2 24-Dec-12 25-Dec-12 03-Feb-13 04-Feb-13 33
Fisrt StaFisrt Stage Finishes 7 26-Dec-12 03-Jan-13 10-Feb-13 24-Apr-13 94
A20470 Screed Works 2 26-Dec-12 27-Dec-12 10-Feb-13 11-Feb-13 37
A20490 Floor Tiles Work 2 30-Dec-12 31-Dec-12 13-Feb-13 14-Feb-13 37
A20350 Doors Ironmongery 1 02-Jan-13 02-Jan-13 24-Apr-13 24-Apr-13 95
A20330 Installation of Doors 2 02-Jan-13 03-Jan-13 16-Feb-13 17-Feb-13 37
Second SSecond Stage Finishes 2 05-Jan-13 06-Jan-13 01-Apr-13 02-Apr-13 73
A20310 Final Coat Paint 2 05-Jan-13 06-Jan-13 01-Apr-13 02-Apr-13 73
Final StaFinal Stage Finishes 1 07-Jan-13 07-Jan-13 25-Apr-13 25-Apr-13 92
A20460 Installation of Sinages 1 07-Jan-13 07-Jan-13 25-Apr-13 25-Apr-13 92
MEP WorkMEP Works 54 30-Oct-12 03-Jan-13 17-Jan-13 31-Mar-13 73
ElectricalElectrical 54 30-Oct-12 03-Jan-13 20-Jan-13 05-Mar-13 51
A20360 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 20-Jan-13 21-Jan-13 67
A20370 Wiring for Lighting & Power 2 19-Nov-12 20-Nov-12 27-Jan-13 28-Jan-13 56
A20380 Installation of Lighting Fittings 2 02-Jan-13 03-Jan-13 04-Mar-13 05-Mar-13 51
PlumbingPlumbing 50 30-Oct-12 29-Dec-12 17-Jan-13 12-Feb-13 37
A20390 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 17-Jan-13 19-Jan-13 65
A20420 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 17-Jan-13 19-Jan-13 65
A20400 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 20-Jan-13 21-Jan-13 65
A20410 Floor Drain Fixning 1 29-Dec-12 29-Dec-12 12-Feb-13 12-Feb-13 37
Fire FighFire Fighting 54 30-Oct-12 03-Jan-13 27-Feb-13 31-Mar-13 73
A20450 Fire Fighting Pipe 2 30-Oct-12 31-Oct-12 27-Feb-13 28-Feb-13 99
A20440 Hydro Static Test for Pipes 2 01-Nov-12 03-Nov-12 02-Mar-13 03-Mar-13 99
A20430 Sprinkler Fixing 2 02-Jan-13 03-Jan-13 04-Mar-13 05-Mar-13 51
A20480 Fire Alarm Devices 2 02-Jan-13 03-Jan-13 30-Mar-13 31-Mar-13 73
Corridor &Corridor & Lift Lobby 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10
FinishingFinishing Works 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10
Wet WorWet Works 51 15-Oct-12 17-Dec-12 24-Dec-12 07-Feb-13 43
A20000 Block Works 8 15-Oct-12 23-Oct-12 24-Dec-12 02-Jan-13 56
A19940 Plaster Works 7 06-Nov-12 13-Nov-12 06-Jan-13 13-Jan-13 49
A19960 Installation of Suspended Ceiling Grid 6 03-Dec-12 09-Dec-12 19-Jan-13 26-Jan-13 39
A19970 Suspended Ceiling Tiles 6 10-Dec-12 16-Dec-12 27-Jan-13 02-Feb-13 39
A20260 MDF for Lift Lobby Wall 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43
Fisrt StaFisrt Stage Finishes 18 18-Dec-12 08-Jan-13 09-Feb-13 17-Feb-13 33
A20240 Screed Works 3 18-Dec-12 20-Dec-12 09-Feb-13 11-Feb-13 43
A19950 1st Coat Paint 5 03-Jan-13 08-Jan-13 12-Feb-13 17-Feb-13 33
Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 18-Feb-13 25-Apr-13 89
A19980 Installation of Doors 2 09-Jan-13 10-Jan-13 18-Feb-13 19-Feb-13 33
A20010 Doors Ironmongery 2 09-Jan-13 10-Jan-13 24-Apr-13 25-Apr-13 89
Final StaFinal Stage Finishes 20 23-Mar-13 14-Apr-13 03-Apr-13 25-Apr-13 10
A19990 Installation of Carpets 4 23-Mar-13 26-Mar-13 03-Apr-13 07-Apr-13 10
A20250 Fixing of Wall Covering 7 27-Mar-13 03-Apr-13 08-Apr-13 15-Apr-13 10
A20230 Installation of Sinages 9 04-Apr-13 14-Apr-13 16-Apr-13 25-Apr-13 10
MEP WorkMEP Works 50 24-Oct-12 25-Dec-12 03-Jan-13 05-Mar-13 58
HVACHVAC 45 24-Oct-12 19-Dec-12 09-Jan-13 11-Feb-13 44
A20020 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61
A20030 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61
A20040 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61
A20050 FCU Installation 3 01-Nov-12 04-Nov-12 15-Jan-13 17-Jan-13 61
A20060 Air-Outlet Installation 3 17-Dec-12 19-Dec-12 09-Feb-13 11-Feb-13 44
ElectricalElectrical 46 24-Oct-12 20-Dec-12 03-Jan-13 05-Mar-13 62
A20070 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 03-Jan-13 05-Jan-13 56
A20080 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 09-Jan-13 10-Jan-13 61
A20120 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 23-Jan-13 26-Jan-13 71
A20130 Cable Laying for Power 3 29-Oct-12 31-Oct-12 22-Jan-13 26-Jan-13 70
A20090 Wiring for Lighting & Power 3 14-Nov-12 18-Nov-12 15-Jan-13 17-Jan-13 50
A20100 Wiring for Low Current System 4 14-Nov-12 19-Nov-12 14-Jan-13 17-Jan-13 49
A20110 DB installation,Dressing & Termination 6 10-Dec-12 16-Dec-12 27-Jan-13 02-Feb-13 39
A20150 Installation of Lighting Fittings 3 17-Dec-12 19-Dec-12 03-Mar-13 05-Mar-13 63
A20160 Installation of Sockets 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62
PlumbingPlumbing 5 24-Oct-12 31-Oct-12 13-Jan-13 17-Jan-13 64
A20170 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 13-Jan-13 17-Jan-13 64
Fire FighFire Fighting 50 24-Oct-12 25-Dec-12 09-Jan-13 11-Feb-13 39
A20220 Fire Fighting Pipe 4 24-Oct-12 30-Oct-12 09-Jan-13 13-Jan-13 61
A20210 Hydro Static Test for Pipes 4 31-Oct-12 04-Nov-12 14-Jan-13 17-Jan-13 61
A20200 Sprinkler Fixing 4 17-Dec-12 20-Dec-12 03-Feb-13 06-Feb-13 39
A20270 Fire Alarm Devices 5 17-Dec-12 22-Dec-12 06-Feb-13 11-Feb-13 42
A20190 Installation of Fire Extingusher&Blanket 4 22-Dec-12 25-Dec-12 07-Feb-13 11-Feb-13 39
Electrical /Electrical /Telephone/ELV Rooms 77 30-Oct-12 31-Jan-13 21-Jan-13 25-Apr-13 72
FinishingFinishing Works 77 30-Oct-12 31-Jan-13 21-Jan-13 25-Apr-13 72
Wet WorWet Works 50 30-Oct-12 29-Dec-12 21-Jan-13 19-Feb-13 43
A20550 Block Works 3 30-Oct-12 01-Nov-12 21-Jan-13 23-Jan-13 68
A20510 Installation of Doors& Windows Sub-frame 1 19-Nov-12 19-Nov-12 19-Feb-13 19-Feb-13 76
A20500 Plaster Works 4 19-Nov-12 22-Nov-12 28-Jan-13 31-Jan-13 57
A20520 1st Coat Paint 3 26-Dec-12 29-Dec-12 05-Feb-13 07-Feb-13 33
Fisrt StaFisrt Stage Finishes 13 12-Jan-13 27-Jan-13 20-Feb-13 23-Apr-13 74
A20540 Installation of Doors 2 12-Jan-13 13-Jan-13 20-Feb-13 21-Feb-13 33
A20560 Doors Ironmongery 2 12-Jan-13 13-Jan-13 22-Apr-13 23-Apr-13 85
A20610 Epoxy Paint Works 2 26-Jan-13 27-Jan-13 30-Mar-13 31-Mar-13 54
Second SSecond Stage Finishes 2 28-Jan-13 29-Jan-13 01-Apr-13 02-Apr-13 54
A20530 Final Coat Paint 2 28-Jan-13 29-Jan-13 01-Apr-13 02-Apr-13 54
Final StaFinal Stage Finishes 2 30-Jan-13 31-Jan-13 24-Apr-13 25-Apr-13 72
A20600 Installation of Sinages 2 30-Jan-13 31-Jan-13 24-Apr-13 25-Apr-13 72
MEP WorkMEP Works 68 03-Nov-12 23-Jan-13 26-Jan-13 28-Mar-13 54
HVACHVAC 2 30-Dec-12 31-Dec-12 04-Mar-13 05-Mar-13 53
A20640 Air-Outlet Installation 2 30-Dec-12 31-Dec-12 04-Mar-13 05-Mar-13 53
ElectricalElectrical 68 03-Nov-12 23-Jan-13 26-Jan-13 05-Mar-13 34
A20570 Install Conduits in Wall 2 03-Nov-12 04-Nov-12 26-Jan-13 27-Jan-13 68
A20580 Wiring for Lighting & Power 2 24-Nov-12 25-Nov-12 03-Feb-13 04-Feb-13 58
A20630 Installation of SMDBs 7 30-Dec-12 07-Jan-13 24-Feb-13 03-Mar-13 46
A20590 Installation of Lighting Fittings 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46
A114580 Installation of Access ControlSystem 20 30-Dec-12 22-Jan-13 11-Feb-13 05-Mar-13 35
A114560 Installation of MATC,TV System 20 30-Dec-12 22-Jan-13 11-Feb-13 05-Mar-13 35
A114570 Installation of Telephone System 21 30-Dec-12 23-Jan-13 10-Feb-13 05-Mar-13 34
Fire FighFire Fighting 2 10-Jan-13 12-Jan-13 27-Mar-13 28-Mar-13 64
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Installation of Telephone System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 46 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A20620 Fire Alarm Devices 2 10-Jan-13 12-Jan-13 27-Mar-13 28-Mar-13 64
Room ServRoom Service 61 03-Nov-12 15-Jan-13 26-Jan-13 25-Apr-13 85
FinishingFinishing Works 61 03-Nov-12 15-Jan-13 26-Jan-13 25-Apr-13 85
Wet WorWet Works 50 03-Nov-12 02-Jan-13 26-Jan-13 21-Feb-13 42
A20700 Block Works 2 03-Nov-12 04-Nov-12 26-Jan-13 27-Jan-13 68
A20660 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 21-Feb-13 21-Feb-13 74
A20650 Plaster Works 4 24-Nov-12 27-Nov-12 02-Feb-13 05-Feb-13 57
A20670 1st Coat Paint 3 30-Dec-12 02-Jan-13 09-Feb-13 11-Feb-13 33
Fisrt StaFisrt Stage Finishes 10 03-Jan-13 14-Jan-13 16-Feb-13 24-Apr-13 85
A20830 Screed Works 2 03-Jan-13 05-Jan-13 16-Feb-13 17-Feb-13 36
A20850 Floor Tiles Work 3 07-Jan-13 09-Jan-13 19-Feb-13 21-Feb-13 36
A20690 Installation of Doors 1 14-Jan-13 14-Jan-13 23-Feb-13 23-Feb-13 33
A20710 Doors Ironmongery 1 14-Jan-13 14-Jan-13 24-Apr-13 24-Apr-13 85
Second SSecond Stage Finishes 1 13-Jan-13 13-Jan-13 02-Apr-13 02-Apr-13 67
A20680 Final Coat Paint 1 13-Jan-13 13-Jan-13 02-Apr-13 02-Apr-13 67
Final StaFinal Stage Finishes 1 15-Jan-13 15-Jan-13 25-Apr-13 25-Apr-13 85
A20820 Installation of Sinages 1 15-Jan-13 15-Jan-13 25-Apr-13 25-Apr-13 85
MEP WorkMEP Works 56 05-Nov-12 12-Jan-13 28-Jan-13 01-Apr-13 67
HVACHVAC 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
A20860 Air-Outlet Installation 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
ElectricalElectrical 56 05-Nov-12 12-Jan-13 30-Jan-13 05-Mar-13 44
A20720 Install Conduits in Wall 2 05-Nov-12 06-Nov-12 30-Jan-13 31-Jan-13 70
A20730 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 06-Feb-13 07-Feb-13 57
A20740 Installation of Lighting Fittings 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
PlumbingPlumbing 51 05-Nov-12 06-Jan-13 28-Jan-13 18-Feb-13 36
A20750 Drainge Pipes in Wall 2 05-Nov-12 06-Nov-12 28-Jan-13 29-Jan-13 68
A20780 Water Pipes in Wall 2 05-Nov-12 06-Nov-12 28-Jan-13 29-Jan-13 68
A20760 Drainage&Water Pipes Testing 2 07-Nov-12 08-Nov-12 30-Jan-13 31-Jan-13 68
A20770 Floor Drain Fixning 1 06-Jan-13 06-Jan-13 18-Feb-13 18-Feb-13 36
Fire FighFire Fighting 56 05-Nov-12 12-Jan-13 27-Feb-13 01-Apr-13 67
A20810 Fire Fighting Pipe 2 05-Nov-12 06-Nov-12 27-Feb-13 28-Feb-13 94
A20800 Hydro Static Test for Pipes 2 07-Nov-12 08-Nov-12 02-Mar-13 03-Mar-13 94
A20790 Sprinkler Fixing 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44
A20840 Fire Alarm Devices 2 10-Jan-13 12-Jan-13 31-Mar-13 01-Apr-13 67
StaircaseStaircase 71 08-Nov-12 03-Feb-13 29-Dec-12 02-Apr-13 50
Stair 1Stair 1 57 08-Nov-12 16-Jan-13 29-Dec-12 02-Apr-13 64
A108890 Floor Screed 3 08-Nov-12 11-Nov-12 29-Dec-12 31-Dec-12 41
A108900 Install Handrails 4 12-Nov-12 17-Nov-12 02-Jan-13 06-Jan-13 41
A108910 Ceiling 1st Coat Paint 7 08-Dec-12 15-Dec-12 07-Jan-13 14-Jan-13 25
A108920 Wall 1st Coat Paint 7 16-Dec-12 23-Dec-12 15-Jan-13 22-Jan-13 25
A108930 Install Granite/Terrazo 11 24-Dec-12 06-Jan-13 28-Jan-13 09-Feb-13 28
A108940 Final Coat Paint 9 07-Jan-13 16-Jan-13 24-Mar-13 02-Apr-13 64
Stair 2Stair 2 68 12-Nov-12 03-Feb-13 15-Jan-13 04-Mar-13 25
A108950 Floor Screed 3 12-Nov-12 14-Nov-12 15-Jan-13 17-Jan-13 52
A108960 Install Handrails 4 18-Nov-12 21-Nov-12 19-Jan-13 22-Jan-13 51
A108970 Ceiling 1st Coat Paint 7 24-Dec-12 31-Dec-12 23-Jan-13 31-Jan-13 25
A108980 Wall 1st Coat Paint 7 02-Jan-13 09-Jan-13 02-Feb-13 09-Feb-13 25
A108990 Install Granite/Terrazo 11 10-Jan-13 22-Jan-13 10-Feb-13 21-Feb-13 25
A109000 Final Coat Paint 9 23-Jan-13 03-Feb-13 23-Feb-13 04-Mar-13 25
ApartementsApartements 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21
Studio FlatsStudio Flats 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (Studio) 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
FinishingFinishing Works 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Wet WoWet Works 38 04-Oct-12 20-Nov-12 21-Oct-12 23-Feb-13 78
A42750 Block Works 4 04-Oct-12 08-Oct-12 21-Oct-12 24-Oct-12 14
A42610 Installation of Doors& Windows Sub-frame 1 29-Oct-12 29-Oct-12 23-Feb-13 23-Feb-13 96
A42600 Plaster Works 7 29-Oct-12 05-Nov-12 14-Nov-12 22-Nov-12 14
A43080 Wall Tiles Work (Wet Area) 8 06-Nov-12 14-Nov-12 30-Dec-12 08-Jan-13 44
A42630 Installation of Suspended Ceiling Grid (Dry Area) 6 10-Nov-12 17-Nov-12 27-Nov-12 04-Dec-12 14
A42620 1st Coat Paint 3 18-Nov-12 20-Nov-12 11-Dec-12 13-Dec-12 19
Fisrt StaFisrt Stage Finishes 25 21-Nov-12 20-Dec-12 10-Jan-13 05-Mar-13 62
A42640 Suspended Ceiling Tiles (DryArea) 6 21-Nov-12 27-Nov-12 10-Jan-13 16-Jan-13 41
A42680 Installation of Wardrobes 2 28-Nov-12 29-Nov-12 17-Jan-13 19-Jan-13 41
A43070 Screed Works 5 01-Dec-12 06-Dec-12 27-Jan-13 31-Jan-13 46
A42670 Water Proofing for Wet Area 3 08-Dec-12 10-Dec-12 02-Feb-13 04-Feb-13 46
A42660 Floor & Wall Tiles Work (Dry Area) 4 08-Dec-12 11-Dec-12 02-Mar-13 05-Mar-13 70
A43110 Installation of Suspended Ceiling Grid (Wet Area) 3 11-Dec-12 13-Dec-12 05-Feb-13 07-Feb-13 46
A43100 Suspended Ceiling Tiles (Wet Area) 2 17-Dec-12 18-Dec-12 11-Feb-13 12-Feb-13 46
A43090 Floor Tiles Work (Wet Area) 2 19-Dec-12 20-Dec-12 16-Feb-13 17-Feb-13 48
SecondSecond Stage Finishes 4 15-Jan-13 19-Jan-13 24-Feb-13 10-Mar-13 42
A42690 Installation of Windows&Doors 2 15-Jan-13 16-Jan-13 24-Feb-13 25-Feb-13 33
A42760 Doors Ironmongery 2 15-Jan-13 16-Jan-13 09-Mar-13 10-Mar-13 44
A42700 Installation of Mirrors 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42
A42710 Installation of Kitchen Cabinets 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42
A42730 Installation of Balustrades& Handrails 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42
A42740 Installation of Vanity Counter 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42
A43050 Installation of Toliets Accessories 2 17-Jan-13 19-Jan-13 03-Mar-13 04-Mar-13 37
Final StFinal Stage Finishes 195 21-Jan-13 08-Sep-13 11-Mar-13 02-Oct-13 21
A42650 Final Coat Paint 6 21-Jan-13 28-Jan-13 11-Mar-13 17-Mar-13 41
A42720 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A43060 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A42770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 84 09-Oct-12 20-Jan-13 10-Nov-12 17-Mar-13 47
HVACHVAC 60 09-Oct-12 22-Dec-12 17-Nov-12 05-Mar-13 61
A42780 Duct Installation & Insulation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30
A42790 Chilled Water Pipe Installation & Insulation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30
A42800 Condensate Pipe Installation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30
A42810 FCU Installation 2 17-Oct-12 18-Oct-12 25-Nov-12 26-Nov-12 30
A42820 Air-Outlet Installation 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61
ElectricElectrical 61 09-Oct-12 23-Dec-12 11-Nov-12 05-Mar-13 60
A42830 Install Conduits in Wall 3 09-Oct-12 11-Oct-12 11-Nov-12 13-Nov-12 26
A42840 Install Cable Trays & Trunking 4 09-Oct-12 13-Oct-12 17-Nov-12 20-Nov-12 30
A42880 Cable Laying for Low Current System 3 14-Oct-12 16-Oct-12 01-Dec-12 04-Dec-12 38
A42890 Cable Laying for Power 3 14-Oct-12 16-Oct-12 01-Dec-12 04-Dec-12 38
A42850 Wiring for Lighting & Power 3 06-Nov-12 08-Nov-12 24-Nov-12 26-Nov-12 14
A42860 Wiring for Low Current System 3 06-Nov-12 08-Nov-12 24-Nov-12 26-Nov-12 14
A42870 DB installation,Dressing & Termination 6 21-Nov-12 27-Nov-12 10-Jan-13 16-Jan-13 41
A42920 Installation of Sockets 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61
A42910 Installation of Lighting Fittings 4 19-Dec-12 23-Dec-12 02-Mar-13 05-Mar-13 60
PlumbinPlumbing 84 09-Oct-12 20-Jan-13 10-Nov-12 10-Mar-13 41
A42930 Drainge Pipes in Wall 4 09-Oct-12 13-Oct-12 10-Nov-12 13-Nov-12 25
A42940 H/L Drainage Pipes Installation 4 09-Oct-12 13-Oct-12 27-Jan-13 30-Jan-13 88
A42950 H/L Hot&Cold Water Pipe Installation 4 09-Oct-12 13-Oct-12 27-Jan-13 30-Jan-13 88
A43000 Water Pipes in Wall 4 09-Oct-12 13-Oct-12 10-Nov-12 13-Nov-12 25
A42960 Drainage&Water Pipes Testing 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88
A42970 ElectricalWater Heater Installation 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88
A42980 Floor Drain Fixning 3 04-Dec-12 06-Dec-12 11-Feb-13 13-Feb-13 57
A42990 Installation of Sanitaryware 3 17-Jan-13 20-Jan-13 07-Mar-13 10-Mar-13 41
Fire FigFire Fighting 62 09-Oct-12 24-Dec-12 20-Nov-12 17-Mar-13 69
A43040 Fire Fighting Pipe 3 09-Oct-12 11-Oct-12 20-Nov-12 22-Nov-12 33
A43030 Hydro Static Test for Pipes 3 13-Oct-12 15-Oct-12 24-Nov-12 26-Nov-12 33
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 47 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A43020 Sprinkler Fixing 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61
A43120 Fire Alarm Devices 3 19-Dec-12 22-Dec-12 07-Mar-13 10-Mar-13 65
A43010 Installation of Fire Extingusher&Blanket 2 23-Dec-12 24-Dec-12 16-Mar-13 17-Mar-13 69
One BedroOne Bedroom Flats 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 (1 BR) 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21
FinishingFinishing Works 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21
Wet WoWet Works 34 09-Oct-12 20-Nov-12 28-Oct-12 25-Feb-13 80
A43280 Block Works 5 09-Oct-12 14-Oct-12 28-Oct-12 01-Nov-12 14
A43140 Installation of Doors& Windows Sub-frame 1 18-Oct-12 18-Oct-12 25-Feb-13 25-Feb-13 105
A43130 Plaster Works 7 18-Oct-12 28-Oct-12 06-Nov-12 13-Nov-12 14
A43160 Installation of Suspended Ceiling Grid (Dry Area) 4 01-Nov-12 05-Nov-12 22-Nov-12 26-Nov-12 17
A43150 1st Coat Paint 6 06-Nov-12 12-Nov-12 04-Dec-12 10-Dec-12 22
A43610 Wall Tiles Work (Wet Area) 4 17-Nov-12 20-Nov-12 09-Jan-13 13-Jan-13 44
Fisrt StaFisrt Stage Finishes 36 17-Nov-12 29-Dec-12 06-Jan-13 09-Mar-13 58
A43170 Suspended Ceiling Tiles (DryArea) 4 17-Nov-12 20-Nov-12 06-Jan-13 09-Jan-13 41
A43210 Installation of Wardrobes 4 21-Nov-12 25-Nov-12 13-Jan-13 16-Jan-13 43
A43600 Screed Works 9 26-Nov-12 06-Dec-12 23-Jan-13 03-Feb-13 48
A43200 Water Proofing for Wet Area 4 08-Dec-12 11-Dec-12 04-Feb-13 07-Feb-13 48
A43190 Floor & Wall Tiles Work (Dry Area) 3 12-Dec-12 15-Dec-12 06-Mar-13 09-Mar-13 70
A43640 Installation of Suspended Ceiling Grid (Wet Area) 4 15-Dec-12 18-Dec-12 09-Feb-13 12-Feb-13 46
A43630 Suspended Ceiling Tiles (Wet Area) 4 19-Dec-12 23-Dec-12 13-Feb-13 17-Feb-13 46
A43620 Floor Tiles Work (Wet Area) 5 24-Dec-12 29-Dec-12 18-Feb-13 23-Feb-13 46
SecondSecond Stage Finishes 7 17-Jan-13 26-Jan-13 26-Feb-13 17-Mar-13 43
A43220 Installation of Windows&Doors 3 17-Jan-13 20-Jan-13 26-Feb-13 28-Feb-13 33
A43290 Doors Ironmongery 3 17-Jan-13 20-Jan-13 14-Mar-13 17-Mar-13 47
A43260 Installation of Balustrades& Handrails 2 21-Jan-13 22-Jan-13 16-Mar-13 17-Mar-13 45
A43230 Installation of Mirrors 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44
A43240 Installation of Kitchen Cabinets 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44
A43270 Installation of Vanity Counter 3 21-Jan-13 23-Jan-13 12-Mar-13 14-Mar-13 42
A43580 Installation of Toliets Accessories 4 21-Jan-13 26-Jan-13 05-Mar-13 09-Mar-13 36
Final StFinal Stage Finishes 189 29-Jan-13 08-Sep-13 18-Mar-13 02-Oct-13 21
A43180 Final Coat Paint 5 29-Jan-13 03-Feb-13 18-Mar-13 23-Mar-13 41
A43250 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27
A43590 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27
A43300 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 82 15-Oct-12 23-Jan-13 03-Nov-12 23-Mar-13 49
HVACHVAC 59 15-Oct-12 26-Dec-12 11-Nov-12 05-Mar-13 57
A43310 Duct Installation & Insulation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21
A43320 Chilled Water Pipe Installation & Insulation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21
A43330 Condensate Pipe Installation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21
A43340 FCU Installation 2 23-Oct-12 24-Oct-12 20-Nov-12 21-Nov-12 21
A43350 Air-Outlet Installation 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57
ElectricElectrical 60 15-Oct-12 27-Dec-12 03-Nov-12 05-Mar-13 56
A43360 Install Conduits in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14
A43370 Install Cable Trays & Trunking 4 15-Oct-12 18-Oct-12 07-Nov-12 11-Nov-12 18
A43410 Cable Laying for Low Current System 3 20-Oct-12 22-Oct-12 24-Nov-12 26-Nov-12 27
A43420 Cable Laying for Power 3 20-Oct-12 22-Oct-12 24-Nov-12 26-Nov-12 27
A43380 Wiring for Lighting & Power 3 29-Oct-12 31-Oct-12 19-Nov-12 21-Nov-12 17
A43390 Wiring for Low Current System 3 29-Oct-12 31-Oct-12 19-Nov-12 21-Nov-12 17
A43400 DB installation,Dressing & Termination 6 13-Nov-12 20-Nov-12 03-Jan-13 09-Jan-13 41
A43450 Installation of Sockets 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57
A43440 Installation of Lighting Fittings 4 24-Dec-12 27-Dec-12 02-Mar-13 05-Mar-13 56
PlumbinPlumbing 82 15-Oct-12 23-Jan-13 03-Nov-12 17-Mar-13 44
A43460 Drainge Pipes in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14
A43530 Water Pipes in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14
A43470 H/L Drainage Pipes Installation 4 15-Oct-12 18-Oct-12 30-Jan-13 03-Feb-13 86
A43480 H/L Hot&Cold Water Pipe Installation 4 15-Oct-12 18-Oct-12 30-Jan-13 03-Feb-13 86
A43490 Drainage&Water Pipes Testing 4 20-Oct-12 23-Oct-12 04-Feb-13 07-Feb-13 86
A43500 ElectricalWater Heater Installation 4 20-Oct-12 23-Oct-12 04-Feb-13 07-Feb-13 86
A43510 Floor Drain Fixning 3 28-Nov-12 01-Dec-12 17-Feb-13 19-Feb-13 66
A43520 Installation of Sanitaryware 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44
Fire FigFire Fighting 61 15-Oct-12 29-Dec-12 14-Nov-12 23-Mar-13 70
A43570 Fire Fighting Pipe 3 15-Oct-12 17-Oct-12 14-Nov-12 18-Nov-12 24
A43560 Hydro Static Test for Pipes 3 18-Oct-12 21-Oct-12 19-Nov-12 21-Nov-12 24
A43550 Sprinkler Fixing 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57
A43650 Fire Alarm Devices 3 24-Dec-12 26-Dec-12 14-Mar-13 17-Mar-13 67
A43540 Installation of Fire Extingusher&Blanket 2 27-Dec-12 29-Dec-12 21-Mar-13 23-Mar-13 70
Two BedroTwo Bedroom Flats 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21
ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21
FinishingFinishing Works 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21
Wet WoWet Works 65 04-Oct-12 23-Dec-12 16-Oct-12 28-Feb-13 56
A43810 Block Works 15 04-Oct-12 21-Oct-12 16-Oct-12 04-Nov-12 10
A43670 Installation of Doors& Windows Sub-frame 7 28-Oct-12 04-Nov-12 21-Feb-13 28-Feb-13 96
A43660 Plaster Works 18 28-Oct-12 18-Nov-12 08-Nov-12 29-Nov-12 10
A43690 Installation of Suspended Ceiling Grid (Dry Area) 8 22-Nov-12 01-Dec-12 05-Dec-12 13-Dec-12 10
A44140 Wall Tiles Work (Wet Area) 13 21-Nov-12 06-Dec-12 14-Jan-13 29-Jan-13 44
A43680 1st Coat Paint 18 03-Dec-12 23-Dec-12 15-Dec-12 05-Jan-13 10
Fisrt StaFisrt Stage Finishes 46 24-Dec-12 17-Feb-13 06-Jan-13 23-Mar-13 29
A43700 Suspended Ceiling Tiles (DryArea) 12 24-Dec-12 07-Jan-13 06-Jan-13 19-Jan-13 10
A43740 Installation of Wardrobes 8 08-Jan-13 16-Jan-13 20-Jan-13 29-Jan-13 10
A44130 Screed Works 9 17-Jan-13 28-Jan-13 30-Jan-13 09-Feb-13 10
A43730 Water Proofing for Wet Area 9 22-Jan-13 02-Feb-13 04-Feb-13 13-Feb-13 10
A44170 Installation of Suspended Ceiling Grid (Wet Area) 7 28-Jan-13 04-Feb-13 09-Feb-13 16-Feb-13 10
A43720 Floor & Wall Tiles Work (Dry Area) 12 29-Jan-13 11-Feb-13 10-Mar-13 23-Mar-13 34
A44160 Suspended Ceiling Tiles (Wet Area) 10 31-Jan-13 11-Feb-13 12-Feb-13 23-Feb-13 10
A44150 Floor Tiles Work (Wet Area) 5 12-Feb-13 17-Feb-13 24-Feb-13 28-Feb-13 10
SecondSecond Stage Finishes 19 18-Feb-13 11-Mar-13 02-Mar-13 23-Mar-13 10
A43750 Installation of Windows&Doors 7 18-Feb-13 25-Feb-13 02-Mar-13 09-Mar-13 10
A43820 Doors Ironmongery 6 21-Feb-13 27-Feb-13 17-Mar-13 23-Mar-13 20
A43770 Installation of Kitchen Cabinets 5 26-Feb-13 03-Mar-13 18-Mar-13 23-Mar-13 17
A43800 Installation of Vanity Counter 7 26-Feb-13 05-Mar-13 16-Mar-13 23-Mar-13 15
A43760 Installation of Mirrors 9 26-Feb-13 07-Mar-13 13-Mar-13 23-Mar-13 13
A43790 Installation of Balustrades& Handrails 9 26-Feb-13 07-Mar-13 13-Mar-13 23-Mar-13 13
A44110 Installation of Toliets Accessories 12 26-Feb-13 11-Mar-13 10-Mar-13 23-Mar-13 10
Final StFinal Stage Finishes 153 12-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21
A43710 Final Coat Paint 9 12-Mar-13 21-Mar-13 24-Mar-13 02-Apr-13 10
A43780 Installation of Carpets 4 23-Mar-13 26-Mar-13 22-Apr-13 25-Apr-13 26
A44120 Installation of Sinages 7 19-Mar-13 26-Mar-13 18-Apr-13 25-Apr-13 26
A43830 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 116 10-Oct-12 28-Feb-13 05-Nov-12 02-Apr-13 28
HVACHVAC 94 22-Oct-12 14-Feb-13 24-Nov-12 05-Mar-13 16
A43840 Duct Installation & Insulation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25
A43850 Chilled Water Pipe Installation & Insulation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25
A43860 Condensate Pipe Installation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25
A43870 FCU Installation 2 01-Nov-12 03-Nov-12 03-Dec-12 04-Dec-12 25
A43880 Air-Outlet Installation 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
ElectricElectrical 95 22-Oct-12 16-Feb-13 05-Nov-12 05-Mar-13 15
A43890 Install Conduits in Wall 3 22-Oct-12 24-Oct-12 05-Nov-12 07-Nov-12 10
A43900 Install Cable Trays & Trunking 4 22-Oct-12 28-Oct-12 24-Nov-12 27-Nov-12 25
A43940 Cable Laying for Low Current System 3 29-Oct-12 31-Oct-12 11-Dec-12 13-Dec-12 35
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Wall Tiles Work (Wet Area)
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Mirrors
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 48 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A43950 Cable Laying for Power 3 29-Oct-12 31-Oct-12 11-Dec-12 13-Dec-12 35
A43910 Wiring for Lighting & Power 3 19-Nov-12 21-Nov-12 01-Dec-12 04-Dec-12 10
A43920 Wiring for Low Current System 3 19-Nov-12 21-Nov-12 01-Dec-12 04-Dec-12 10
A43930 DB installation,Dressing & Termination 6 24-Dec-12 30-Dec-12 13-Jan-13 19-Jan-13 16
A43980 Installation of Sockets 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
A43970 Installation of Lighting Fittings 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15
PlumbinPlumbing 116 10-Oct-12 28-Feb-13 05-Nov-12 23-Mar-13 19
A44060 Water Pipes in Wall 3 10-Oct-12 13-Oct-12 05-Nov-12 07-Nov-12 20
A43990 Drainge Pipes in Wall 3 22-Oct-12 24-Oct-12 05-Nov-12 07-Nov-12 10
A44000 H/L Drainage Pipes Installation 4 22-Oct-12 28-Oct-12 30-Jan-13 03-Feb-13 80
A44010 H/L Hot&Cold Water Pipe Installation 4 22-Oct-12 28-Oct-12 30-Jan-13 03-Feb-13 80
A44020 Drainage&Water Pipes Testing 4 29-Oct-12 01-Nov-12 04-Feb-13 07-Feb-13 80
A44030 ElectricalWater Heater Installation 4 29-Oct-12 01-Nov-12 04-Feb-13 07-Feb-13 80
A44040 Floor Drain Fixning 3 20-Jan-13 22-Jan-13 23-Feb-13 25-Feb-13 28
A44050 Installation of Sanitaryware 3 26-Feb-13 28-Feb-13 20-Mar-13 23-Mar-13 19
Fire FigFire Fighting 96 22-Oct-12 17-Feb-13 27-Nov-12 02-Apr-13 38
A44100 Fire Fighting Pipe 3 22-Oct-12 24-Oct-12 27-Nov-12 29-Nov-12 28
A44090 Hydro Static Test for Pipes 3 28-Oct-12 30-Oct-12 01-Dec-12 04-Dec-12 28
A44080 Sprinkler Fixing 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
A44180 Fire Alarm Devices 3 12-Feb-13 14-Feb-13 20-Mar-13 23-Mar-13 31
A44070 Installation of Fire Extingusher&Blanket 2 16-Feb-13 17-Feb-13 01-Apr-13 02-Apr-13 38
Roof LevelRoof Level 301 13-Sep-12 08-Sep-13 03-Nov-12 02-Oct-13 21
Public AreaPublic Area 301 13-Sep-12 08-Sep-13 03-Nov-12 02-Oct-13 21
SwimmimgSwimmimg Pool Room 115 18-Oct-12 07-Mar-13 03-Nov-12 25-Apr-13 42
FinishingFinishing Works 115 18-Oct-12 07-Mar-13 03-Nov-12 25-Apr-13 42
Wet WorWet Works 76 18-Oct-12 20-Jan-13 03-Nov-12 21-Apr-13 77
A44240 Block Works 4 18-Oct-12 22-Oct-12 03-Nov-12 06-Nov-12 11
A44190 Plaster Works 6 24-Dec-12 30-Dec-12 07-Jan-13 13-Jan-13 11
A44200 Installation of Doors& Windows Sub-frame 1 19-Jan-13 19-Jan-13 21-Apr-13 21-Apr-13 78
A44210 1st Coat Paint 11 08-Jan-13 20-Jan-13 21-Jan-13 03-Feb-13 11
Fisrt StaFisrt Stage Finishes 14 13-Feb-13 28-Feb-13 14-Apr-13 23-Apr-13 46
A44230 Installation of Doors 2 13-Feb-13 14-Feb-13 22-Apr-13 23-Apr-13 58
A44250 Doors Ironmongery 2 13-Feb-13 14-Feb-13 22-Apr-13 23-Apr-13 58
A44300 Epoxy Paint Works 5 24-Feb-13 28-Feb-13 14-Apr-13 18-Apr-13 42
Second SSecond Stage Finishes 4 02-Mar-13 05-Mar-13 20-Apr-13 23-Apr-13 42
A44220 Final Coat Paint 4 02-Mar-13 05-Mar-13 20-Apr-13 23-Apr-13 42
Final StaFinal Stage Finishes 2 06-Mar-13 07-Mar-13 24-Apr-13 25-Apr-13 42
A44290 Installation of Sinages 2 06-Mar-13 07-Mar-13 24-Apr-13 25-Apr-13 42
MEP WorkMEP Works 98 23-Oct-12 20-Feb-13 07-Nov-12 23-Apr-13 53
HVACHVAC 20 23-Oct-12 18-Nov-12 07-Nov-12 04-Feb-13 64
A44360 Duct Installation & Insulation 7 23-Oct-12 01-Nov-12 07-Nov-12 14-Nov-12 11
A44370 Chilled Water Pipe Installation & Insulation 7 23-Oct-12 01-Nov-12 07-Nov-12 14-Nov-12 11
A44380 Condensate Pipe Installation 7 23-Oct-12 01-Nov-12 19-Nov-12 26-Nov-12 20
A44390 FCU Installation 5 03-Nov-12 07-Nov-12 27-Nov-12 03-Dec-12 20
A44400 Air-Outlet Installation 8 08-Nov-12 18-Nov-12 27-Jan-13 04-Feb-13 64
ElectricalElectrical 82 23-Oct-12 02-Feb-13 30-Dec-12 05-Mar-13 27
A44260 Install Conduits in Wall 6 23-Oct-12 31-Oct-12 30-Dec-12 06-Jan-13 54
A44270 Wiring for Lighting & Power 6 31-Dec-12 07-Jan-13 14-Jan-13 20-Jan-13 11
A44280 Installation of Lighting Fittings 8 23-Jan-13 02-Feb-13 25-Feb-13 05-Mar-13 27
PlumbingPlumbing 74 23-Oct-12 22-Jan-13 20-Feb-13 05-Mar-13 35
A44470 H/L Drainage Pipes Installation 8 23-Oct-12 03-Nov-12 20-Feb-13 28-Feb-13 97
A44480 H/L Hot&Cold Water Pipe Installation 8 23-Oct-12 03-Nov-12 20-Feb-13 28-Feb-13 97
A44490 Drainage&Water Pipes Testing 4 04-Nov-12 07-Nov-12 02-Mar-13 05-Mar-13 97
A44510 Floor Drain Fixning 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35
Fire FighFire Fighting 23 23-Oct-12 21-Nov-12 10-Nov-12 23-Apr-13 128
A44410 Fire Fighting Pipe 7 23-Oct-12 01-Nov-12 10-Nov-12 18-Nov-12 13
A44420 Hydro Static Test for Pipes 4 03-Nov-12 06-Nov-12 29-Jan-13 02-Feb-13 71
A44430 Sprinkler Fixing 7 07-Nov-12 14-Nov-12 03-Feb-13 10-Feb-13 71
A44450 Installation of Fire Extingusher&Blanket 2 17-Nov-12 18-Nov-12 22-Apr-13 23-Apr-13 131
A44310 Fire Alarm Devices 5 17-Nov-12 21-Nov-12 23-Mar-13 27-Mar-13 105
SwimminSwimming Pool 26 21-Jan-13 20-Feb-13 04-Feb-13 05-Mar-13 11
A44440 Installation of GRP Tank 10 21-Jan-13 02-Feb-13 04-Feb-13 14-Feb-13 11
A45060 Installation of Heat Exchanger 10 21-Jan-13 02-Feb-13 04-Feb-13 14-Feb-13 11
A44350 Installation of Swimming Pool Pipes&Fittings 15 21-Jan-13 07-Feb-13 17-Feb-13 05-Mar-13 22
A44460 Installation of Pumps 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11
A44500 Installation of Filter 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11
A44650 Installation of Electrical Heater 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11
A45180 Installation of Chemical Tank 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11
A45190 Installation of Control Panel 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11
Pump RooPump Room 103 23-Oct-12 26-Feb-13 07-Nov-12 25-Apr-13 50
FinishingFinishing Works 103 23-Oct-12 26-Feb-13 07-Nov-12 25-Apr-13 50
Wet WorWet Works 70 23-Oct-12 17-Jan-13 07-Nov-12 18-Apr-13 77
A44570 Block Works 4 23-Oct-12 29-Oct-12 07-Nov-12 11-Nov-12 11
A44520 Plaster Works 5 18-Dec-12 23-Dec-12 31-Dec-12 06-Jan-13 11
A44540 1st Coat Paint 6 31-Dec-12 07-Jan-13 14-Jan-13 20-Jan-13 11
A44530 Installation of Doors& Windows Sub-frame 1 17-Jan-13 17-Jan-13 18-Apr-13 18-Apr-13 77
Fisrt StaFisrt Stage Finishes 9 11-Feb-13 20-Feb-13 09-Apr-13 23-Apr-13 53
A44560 Installation of Doors 2 11-Feb-13 12-Feb-13 20-Apr-13 21-Apr-13 58
A44580 Doors Ironmongery 2 11-Feb-13 12-Feb-13 22-Apr-13 23-Apr-13 60
A44630 Epoxy Paint Works 2 19-Feb-13 20-Feb-13 09-Apr-13 10-Apr-13 42
Second SSecond Stage Finishes 3 21-Feb-13 24-Feb-13 21-Apr-13 23-Apr-13 50
A44550 Final Coat Paint 3 21-Feb-13 24-Feb-13 21-Apr-13 23-Apr-13 50
Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 24-Apr-13 25-Apr-13 50
A44620 Installation of Sinages 2 25-Feb-13 26-Feb-13 24-Apr-13 25-Apr-13 50
MEP WorkMEP Works 92 30-Oct-12 18-Feb-13 17-Nov-12 23-Apr-13 55
HVACHVAC 92 30-Oct-12 18-Feb-13 17-Nov-12 05-Mar-13 13
A44680 Condensate Pipe Installation 7 30-Oct-12 06-Nov-12 25-Nov-12 03-Dec-12 21
A44660 Duct Installation & Insulation 7 03-Nov-12 10-Nov-12 17-Nov-12 24-Nov-12 11
A44670 Chilled Water Pipe Installation & Insulation 7 03-Nov-12 10-Nov-12 17-Nov-12 24-Nov-12 11
A44690 FCU Installation 5 11-Nov-12 17-Nov-12 04-Dec-12 09-Dec-12 18
A44700 Air-Outlet Installation 7 19-Nov-12 26-Nov-12 05-Feb-13 12-Feb-13 64
A44790 Installation of Primary Chilled Water Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13
A114240 Installation of Heat Exchanger Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13
A114250 Installation of Heat Exchanger 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13
A114260 Installation of Secondary Chilled Water Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13
ElectricalElectrical 70 30-Oct-12 22-Jan-13 27-Dec-12 24-Feb-13 27
A44590 Install Conduits in Wall 3 30-Oct-12 01-Nov-12 27-Dec-12 30-Dec-12 48
A44600 Wiring for Lighting & Power 3 24-Dec-12 26-Dec-12 10-Jan-13 13-Jan-13 14
A44610 Installation of Lighting Fittings 5 17-Jan-13 22-Jan-13 19-Feb-13 24-Feb-13 27
PlumbingPlumbing 72 30-Oct-12 26-Jan-13 17-Feb-13 05-Mar-13 33
A44760 H/L Hot&Cold Water Pipe Installation 4 30-Oct-12 03-Nov-12 23-Feb-13 26-Feb-13 95
A44750 H/L Drainage Pipes Installation 7 30-Oct-12 06-Nov-12 19-Feb-13 26-Feb-13 92
A44770 Drainage&Water Pipes Testing 6 07-Nov-12 13-Nov-12 27-Feb-13 05-Mar-13 92
A44780 Floor Drain Fixning 6 08-Jan-13 14-Jan-13 27-Feb-13 05-Mar-13 42
A45200 Installation of Booster Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33
A45210 Installation of Primary Chilled Water Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33
A45310 Installation of SecondaryChilled Water Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33
A45320 Installation of Heat Exchanger 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33
A45330 Installation of Heat Exchanger Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33
Fire FighFire Fighting 25 03-Nov-12 03-Dec-12 19-Nov-12 23-Apr-13 119
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Water Pipes in Wall
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Installation of GRP Tank
Installation of Heat Exchanger
Installation of Swimming Pool Pipes&Fittings
Installation of Pumps
Installation of Filter
Installation of Electrical Heater
Installation of Chemical Tank
Installation of Control Panel
Block Works
Plaster Works
1st Coat Paint
Installation of Doors& Windows Sub-frame
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Installation of Primary Chilled Water Pumps
Installation of Heat Exchanger Pumps
Installation of Heat Exchanger
Installation of Secondary Chilled Water Pumps
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Booster Pump
Installation of Primary Chilled Water Pump
Installation of SecondaryChilled Water Pump
Installation of Heat Exchanger
Installation of Heat Exchanger Pump
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 49 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A44740 Fire Fighting Pipe 7 03-Nov-12 10-Nov-12 19-Nov-12 26-Nov-12 13
A44730 Hydro Static Test for Pipes 7 11-Nov-12 19-Nov-12 03-Feb-13 10-Feb-13 68
A44720 Sprinkler Fixing 5 20-Nov-12 25-Nov-12 11-Feb-13 16-Feb-13 68
A44710 Installation of Fire Extingusher&Blanket 3 26-Nov-12 28-Nov-12 21-Apr-13 23-Apr-13 122
A44640 Fire Alarm Devices 6 26-Nov-12 03-Dec-12 28-Mar-13 03-Apr-13 102
ElectricalElectrical - GSM - Telephone Rooms 103 30-Oct-12 03-Mar-13 12-Nov-12 25-Apr-13 46
FinishingFinishing Works 103 30-Oct-12 03-Mar-13 12-Nov-12 25-Apr-13 46
Wet WorWet Works 65 30-Oct-12 16-Jan-13 12-Nov-12 16-Apr-13 76
A44850 Block Works 6 30-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 11
A44800 Plaster Works 7 10-Dec-12 17-Dec-12 23-Dec-12 30-Dec-12 11
A44820 1st Coat Paint 8 22-Dec-12 30-Dec-12 05-Jan-13 13-Jan-13 11
A44810 Installation of Doors& Windows Sub-frame 2 15-Jan-13 16-Jan-13 15-Apr-13 16-Apr-13 76
Fisrt StaFisrt Stage Finishes 13 09-Feb-13 23-Feb-13 11-Apr-13 23-Apr-13 51
A44840 Installation of Doors 2 09-Feb-13 10-Feb-13 17-Apr-13 18-Apr-13 58
A44860 Doors Ironmongery 2 09-Feb-13 10-Feb-13 22-Apr-13 23-Apr-13 62
A44910 Epoxy Paint Works 2 21-Feb-13 23-Feb-13 11-Apr-13 13-Apr-13 42
Second SSecond Stage Finishes 5 24-Feb-13 28-Feb-13 18-Apr-13 23-Apr-13 46
A44830 Final Coat Paint 5 24-Feb-13 28-Feb-13 18-Apr-13 23-Apr-13 46
Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 24-Apr-13 25-Apr-13 46
A44900 Installation of Sinages 2 02-Mar-13 03-Mar-13 24-Apr-13 25-Apr-13 46
MEP WorkMEP Works 88 06-Nov-12 20-Feb-13 20-Dec-12 10-Apr-13 42
HVACHVAC 2 05-Jan-13 06-Jan-13 24-Feb-13 25-Feb-13 42
A44940 Air-Outlet Installation 2 05-Jan-13 06-Jan-13 24-Feb-13 25-Feb-13 42
ElectricalElectrical 88 06-Nov-12 20-Feb-13 20-Dec-12 05-Mar-13 11
A44870 Install Conduits in Wall 2 06-Nov-12 07-Nov-12 20-Dec-12 22-Dec-12 36
A44880 Wiring for Lighting & Power 2 18-Dec-12 19-Dec-12 02-Jan-13 03-Jan-13 12
A44930 Installation of SMDBs 7 31-Dec-12 08-Jan-13 03-Feb-13 10-Feb-13 27
A44890 Installation of Lighting Fittings 2 09-Jan-13 10-Jan-13 11-Feb-13 12-Feb-13 27
A114890 Installation of Telephone System 21 31-Dec-12 26-Jan-13 10-Feb-13 05-Mar-13 33
A114590 Installation of GSM System 43 31-Dec-12 20-Feb-13 14-Jan-13 05-Mar-13 11
Fire FighFire Fighting 2 12-Jan-13 13-Jan-13 09-Apr-13 10-Apr-13 74
A44920 Fire Alarm Devices 2 12-Jan-13 13-Jan-13 09-Apr-13 10-Apr-13 74
Gym RoomGym Room 257 06-Nov-12 08-Sep-13 20-Nov-12 02-Oct-13 21
FinishingFinishing Works 257 06-Nov-12 08-Sep-13 20-Nov-12 02-Oct-13 21
Wet WorWet Works 57 06-Nov-12 14-Jan-13 20-Nov-12 14-Apr-13 76
A45000 Block Works 3 06-Nov-12 08-Nov-12 20-Nov-12 22-Nov-12 11
A44950 Plaster Works 5 24-Nov-12 28-Nov-12 08-Dec-12 12-Dec-12 11
A44960 Installation of Doors& Windows Sub-frame 2 13-Jan-13 14-Jan-13 13-Apr-13 14-Apr-13 76
Fisrt StaFisrt Stage Finishes 35 29-Nov-12 10-Jan-13 19-Dec-12 14-Apr-13 79
A45230 Installation of Suspended Ceiling Grid 5 29-Nov-12 05-Dec-12 19-Dec-12 24-Dec-12 16
A44970 1st Coat Paint 8 12-Dec-12 20-Dec-12 25-Dec-12 03-Jan-13 11
A45240 Suspended Ceiling Tiles 5 22-Dec-12 26-Dec-12 29-Jan-13 03-Feb-13 31
A45280 Screed Works 3 27-Dec-12 30-Dec-12 01-Apr-13 03-Apr-13 79
A45270 Wall Tiles Work 4 31-Dec-12 05-Jan-13 04-Apr-13 08-Apr-13 79
A45260 Floor Tiles Work 5 06-Jan-13 10-Jan-13 09-Apr-13 14-Apr-13 79
Second SSecond Stage Finishes 23 12-Jan-13 07-Feb-13 15-Apr-13 25-Apr-13 66
A44980 Final Coat Paint 3 12-Jan-13 14-Jan-13 16-Apr-13 18-Apr-13 80
A45250 Installation of Mirrors 6 15-Jan-13 21-Jan-13 20-Apr-13 25-Apr-13 80
A44990 Installation of Doors 2 06-Feb-13 07-Feb-13 15-Apr-13 16-Apr-13 58
A45010 Doors Ironmongery 2 06-Feb-13 07-Feb-13 22-Apr-13 23-Apr-13 64
Final StaFinal Stage Finishes 180 09-Feb-13 08-Sep-13 24-Apr-13 02-Oct-13 21
A45050 Installation of Sinages 2 09-Feb-13 10-Feb-13 24-Apr-13 25-Apr-13 64
A45080 Installation of GYM Equipments 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 50 10-Nov-12 09-Jan-13 25-Nov-12 18-Apr-13 84
HVACHVAC 45 10-Nov-12 03-Jan-13 25-Nov-12 23-Feb-13 42
A45110 Condensate Pipe Installation 8 10-Nov-12 19-Nov-12 29-Nov-12 09-Dec-12 16
A45090 Duct Installation & Insulation 8 11-Nov-12 20-Nov-12 25-Nov-12 04-Dec-12 11
A45100 Chilled Water Pipe Installation & Insulation 8 11-Nov-12 20-Nov-12 25-Nov-12 04-Dec-12 11
A45120 FCU Installation 3 21-Nov-12 24-Nov-12 10-Dec-12 12-Dec-12 15
A45130 Air-Outlet Installation 6 27-Dec-12 03-Jan-13 17-Feb-13 23-Feb-13 42
ElectricalElectrical 45 10-Nov-12 03-Jan-13 03-Dec-12 10-Feb-13 31
A45020 Install Conduits in Wall 4 10-Nov-12 13-Nov-12 03-Dec-12 06-Dec-12 18
A45030 Wiring for Lighting & Power 4 29-Nov-12 04-Dec-12 20-Dec-12 24-Dec-12 17
A45040 Installation of Lighting Fittings 6 27-Dec-12 03-Jan-13 04-Feb-13 10-Feb-13 31
Fire FighFire Fighting 49 11-Nov-12 09-Jan-13 27-Nov-12 18-Apr-13 84
A45170 Fire Fighting Pipe 7 11-Nov-12 19-Nov-12 27-Nov-12 05-Dec-12 13
A45160 Hydro Static Test for Pipes 5 20-Nov-12 25-Nov-12 13-Dec-12 18-Dec-12 19
A45150 Sprinkler Fixing 7 27-Dec-12 05-Jan-13 17-Feb-13 24-Feb-13 42
A45140 Installation of Fire Extingusher&Blanket 2 06-Jan-13 07-Jan-13 17-Apr-13 18-Apr-13 86
A45070 Fire Alarm Devices 4 06-Jan-13 09-Jan-13 04-Apr-13 08-Apr-13 75
TolietsToliets 83 10-Nov-12 18-Feb-13 24-Nov-12 25-Apr-13 57
FinishingFinishing Works 83 10-Nov-12 18-Feb-13 24-Nov-12 25-Apr-13 57
Wet WorWet Works 52 10-Nov-12 12-Jan-13 24-Nov-12 09-Apr-13 74
A45440 Block Works 4 10-Nov-12 13-Nov-12 24-Nov-12 27-Nov-12 11
A45290 Plaster Works 8 29-Nov-12 09-Dec-12 13-Dec-12 22-Dec-12 11
A45770 Wall Tiles Work (Wet Area) 9 10-Dec-12 19-Dec-12 13-Jan-13 22-Jan-13 28
A45300 Installation of Doors& Windows Sub-frame 3 09-Jan-13 12-Jan-13 07-Apr-13 09-Apr-13 74
Fisrt StaFisrt Stage Finishes 21 20-Dec-12 14-Jan-13 23-Jan-13 09-Apr-13 72
A45760 Screed Works 3 20-Dec-12 23-Dec-12 23-Jan-13 27-Jan-13 28
A45360 Water Proofing for Wet Area 4 24-Dec-12 27-Dec-12 28-Jan-13 31-Jan-13 28
A45800 Installation of Suspended Ceiling Grid (Wet Area) 5 29-Dec-12 03-Jan-13 02-Feb-13 06-Feb-13 28
A45790 Suspended Ceiling Tiles (Wet Area) 5 05-Jan-13 09-Jan-13 07-Feb-13 12-Feb-13 28
A45780 Floor Tiles Work (Wet Area) 4 10-Jan-13 14-Jan-13 06-Apr-13 09-Apr-13 72
Second SSecond Stage Finishes 10 03-Feb-13 13-Feb-13 10-Apr-13 21-Apr-13 57
A45380 Installation of Doors 3 03-Feb-13 05-Feb-13 10-Apr-13 13-Apr-13 57
A45450 Doors Ironmongery 3 03-Feb-13 05-Feb-13 18-Apr-13 21-Apr-13 64
A45430 Installation of Vanity Counter 3 06-Feb-13 09-Feb-13 18-Apr-13 21-Apr-13 61
A45740 Installation of Toliets Accessories 5 06-Feb-13 11-Feb-13 16-Apr-13 21-Apr-13 59
A45390 Installation of Mirrors 7 06-Feb-13 13-Feb-13 14-Apr-13 21-Apr-13 57
Final StaFinal Stage Finishes 4 14-Feb-13 18-Feb-13 22-Apr-13 25-Apr-13 57
A45340 Final Coat Paint 2 14-Feb-13 16-Feb-13 22-Apr-13 23-Apr-13 57
A45750 Installation of Sinages 2 17-Feb-13 18-Feb-13 24-Apr-13 25-Apr-13 57
MEP WorkMEP Works 71 14-Nov-12 09-Feb-13 05-Dec-12 23-Apr-13 63
HVACHVAC 53 14-Nov-12 17-Jan-13 05-Dec-12 05-Mar-13 39
A45490 Condensate Pipe Installation 4 14-Nov-12 19-Nov-12 09-Dec-12 12-Dec-12 19
A45470 Duct Installation & Insulation 4 21-Nov-12 25-Nov-12 05-Dec-12 09-Dec-12 11
A45480 Chilled Water Pipe Installation & Insulation 4 21-Nov-12 25-Nov-12 05-Dec-12 09-Dec-12 11
A45500 FCU Installation 2 26-Nov-12 27-Nov-12 13-Dec-12 15-Dec-12 14
A45510 Air-Outlet Installation 7 10-Jan-13 17-Jan-13 26-Feb-13 05-Mar-13 39
ElectricalElectrical 52 14-Nov-12 16-Jan-13 09-Dec-12 18-Feb-13 27
A45520 Install Conduits in Wall 4 14-Nov-12 19-Nov-12 09-Dec-12 12-Dec-12 19
A45540 Wiring for Lighting & Power 4 10-Dec-12 13-Dec-12 28-Jan-13 31-Jan-13 40
A45600 Installation of Lighting Fittings 5 12-Jan-13 16-Jan-13 13-Feb-13 18-Feb-13 27
PlumbingPlumbing 71 14-Nov-12 09-Feb-13 10-Dec-12 21-Apr-13 61
A45620 Drainge Pipes in Wall 3 14-Nov-12 18-Nov-12 10-Dec-12 12-Dec-12 20
A45690 Water Pipes in Wall 3 14-Nov-12 18-Nov-12 10-Dec-12 12-Dec-12 20
A45630 H/L Drainage Pipes Installation 4 14-Nov-12 19-Nov-12 23-Jan-13 28-Jan-13 57
A45640 H/L Hot&Cold Water Pipe Installation 4 14-Nov-12 19-Nov-12 23-Jan-13 28-Jan-13 57
A45660 ElectricalWater Heater Installation 2 20-Nov-12 21-Nov-12 30-Jan-13 31-Jan-13 58
A45650 Drainage&Water Pipes Testing 3 20-Nov-12 22-Nov-12 29-Jan-13 31-Jan-13 57
A45670 Floor Drain Fixning 2 23-Dec-12 24-Dec-12 04-Mar-13 05-Mar-13 59
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
1st Coat Paint
Installation of Doors& Windows Sub-frame
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Installation of GSM System
Fire Alarm Devices
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Final Coat Paint
Installation of Mirrors
Installation of Doors
Doors Ironmongery
Installation of Sinages
Installation of GYM Eq
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Doors& Windows Sub-frame
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Doors
Doors Ironmongery
Installation of Vanity Counter
Installation of Toliets Accessories
Installation of Mirrors
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Electrical Water Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 50 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A45680 Installation of Sanitaryware 3 06-Feb-13 09-Feb-13 18-Apr-13 21-Apr-13 61
Fire FighFire Fighting 49 20-Nov-12 17-Jan-13 06-Dec-12 23-Apr-13 81
A45730 Fire Fighting Pipe 3 20-Nov-12 22-Nov-12 06-Dec-12 09-Dec-12 13
A45720 Hydro Static Test for Pipes 3 24-Nov-12 26-Nov-12 29-Jan-13 31-Jan-13 54
A45710 Sprinkler Fixing 3 12-Jan-13 14-Jan-13 03-Mar-13 05-Mar-13 42
A45700 Installation of Fire Extingusher&Blanket 2 15-Jan-13 16-Jan-13 22-Apr-13 23-Apr-13 82
A45810 Fire Alarm Devices 4 14-Jan-13 17-Jan-13 13-Apr-13 16-Apr-13 75
Lift LobbyLift Lobby 65 14-Nov-12 02-Feb-13 28-Nov-12 25-Apr-13 71
FinishingFinishing Works 65 14-Nov-12 02-Feb-13 28-Nov-12 25-Apr-13 71
Wet WorWet Works 22 14-Nov-12 11-Dec-12 28-Nov-12 24-Dec-12 11
A45880 Block Works 2 14-Nov-12 17-Nov-12 28-Nov-12 29-Nov-12 11
A45820 Plaster Works 3 20-Nov-12 22-Nov-12 04-Dec-12 06-Dec-12 11
A45840 Installation of Suspended Ceiling Grid 2 06-Dec-12 08-Dec-12 19-Dec-12 20-Dec-12 11
A45830 1st Coat Paint 3 09-Dec-12 11-Dec-12 22-Dec-12 24-Dec-12 11
Fisrt StaFisrt Stage Finishes 9 12-Dec-12 22-Dec-12 27-Jan-13 02-Apr-13 85
A45850 Suspended Ceiling Tiles 2 12-Dec-12 13-Dec-12 27-Jan-13 28-Jan-13 37
A46140 MDF for Lift Lobby Wall 7 12-Dec-12 19-Dec-12 24-Mar-13 31-Mar-13 85
A46120 Screed Works 2 20-Dec-12 22-Dec-12 01-Apr-13 02-Apr-13 85
Second SSecond Stage Finishes 4 23-Dec-12 26-Dec-12 03-Apr-13 07-Apr-13 85
A46130 Wall Tiles Work 2 23-Dec-12 24-Dec-12 03-Apr-13 04-Apr-13 85
A46160 Floor Tiles Work 2 25-Dec-12 26-Dec-12 06-Apr-13 07-Apr-13 85
Final StaFinal Stage Finishes 8 23-Jan-13 02-Feb-13 08-Apr-13 25-Apr-13 71
A46170 Final Coat Paint 2 23-Jan-13 26-Jan-13 22-Apr-13 23-Apr-13 75
A45860 Installation of Doors 2 31-Jan-13 02-Feb-13 08-Apr-13 09-Apr-13 57
A45890 Doors Ironmongery 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71
A46110 Installation of Sinages 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71
MEP WorkMEP Works 55 18-Nov-12 22-Jan-13 01-Dec-12 21-Apr-13 75
HVACHVAC 25 18-Nov-12 17-Dec-12 10-Dec-12 16-Feb-13 50
A45920 Condensate Pipe Installation 5 18-Nov-12 22-Nov-12 10-Dec-12 15-Dec-12 18
A45900 Duct Installation & Insulation 5 26-Nov-12 01-Dec-12 10-Dec-12 15-Dec-12 11
A45910 Chilled Water Pipe Installation & Insulation 5 26-Nov-12 01-Dec-12 10-Dec-12 15-Dec-12 11
A45930 FCU Installation 3 03-Dec-12 05-Dec-12 16-Dec-12 18-Dec-12 11
A45940 Air-Outlet Installation 3 15-Dec-12 17-Dec-12 13-Feb-13 16-Feb-13 50
ElectricalElectrical 27 18-Nov-12 19-Dec-12 01-Dec-12 05-Mar-13 63
A45950 Install Conduits in Wall 2 18-Nov-12 19-Nov-12 01-Dec-12 03-Dec-12 11
A45960 Install Cable Trays & Trunking 2 18-Nov-12 19-Nov-12 03-Dec-12 04-Dec-12 12
A46000 Cable Laying for Low Current System 2 20-Nov-12 21-Nov-12 19-Dec-12 20-Dec-12 24
A46010 Cable Laying for Power 4 20-Nov-12 24-Nov-12 17-Dec-12 20-Dec-12 22
A45970 Wiring for Lighting & Power 3 24-Nov-12 26-Nov-12 16-Dec-12 18-Dec-12 18
A45980 Wiring for Low Current System 4 24-Nov-12 27-Nov-12 15-Dec-12 18-Dec-12 17
A46040 Installation of Sockets 3 15-Dec-12 17-Dec-12 03-Mar-13 05-Mar-13 65
A46030 Installation of Lighting Fittings 5 15-Dec-12 19-Dec-12 29-Jan-13 03-Feb-13 37
PlumbingPlumbing 5 18-Nov-12 22-Nov-12 13-Dec-12 18-Dec-12 21
A46050 H/L Hot&Cold Water Pipe Installation 5 18-Nov-12 22-Nov-12 13-Dec-12 18-Dec-12 21
Fire FighFire Fighting 50 24-Nov-12 22-Jan-13 10-Dec-12 21-Apr-13 75
A46100 Fire Fighting Pipe 4 24-Nov-12 27-Nov-12 10-Dec-12 13-Dec-12 13
A46090 Hydro Static Test for Pipes 4 28-Nov-12 03-Dec-12 15-Dec-12 18-Dec-12 13
A46080 Sprinkler Fixing 5 06-Jan-13 10-Jan-13 25-Feb-13 02-Mar-13 42
A46150 Fire Alarm Devices 4 19-Jan-13 22-Jan-13 17-Apr-13 21-Apr-13 75
Chillers RoChillers Room 116 13-Sep-12 02-Feb-13 18-Nov-12 25-Apr-13 71
FinishingFinishing Works 116 13-Sep-12 02-Feb-13 18-Nov-12 25-Apr-13 71
Wet WorWet Works 7 13-Sep-12 20-Sep-12 18-Nov-12 16-Mar-13 145
A46230 Block Works 2 13-Sep-12 15-Sep-12 14-Mar-13 16-Mar-13 150
A46290 Water Proofing Works 7 13-Sep-12 20-Sep-12 18-Nov-12 25-Nov-12 53
Fisrt StaFisrt Stage Finishes 19 08-Jan-13 30-Jan-13 17-Mar-13 23-Apr-13 71
A46190 Installation of Doors& Windows Sub-frame 1 08-Jan-13 08-Jan-13 03-Apr-13 03-Apr-13 72
A46180 Plaster Works 2 08-Jan-13 09-Jan-13 17-Mar-13 18-Mar-13 57
A46200 1st Coat Paint 3 10-Jan-13 13-Jan-13 19-Mar-13 21-Mar-13 57
A46450 Floor Tiles Works 11 14-Jan-13 27-Jan-13 23-Mar-13 03-Apr-13 57
A46220 Installation of Doors 3 28-Jan-13 30-Jan-13 04-Apr-13 07-Apr-13 57
A46240 Doors Ironmongery 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71
Second SSecond Stage Finishes 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71
A46210 Final Coat Paint 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71
Final StaFinal Stage Finishes 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71
A46280 Installation of Sinages 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71
MEP WorkMEP Works 83 27-Sep-12 07-Jan-13 26-Nov-12 05-Mar-13 48
HVACHVAC 83 27-Sep-12 07-Jan-13 26-Nov-12 05-Mar-13 48
A46320 Chilled Water Pipe Installation & Insulation 51 27-Sep-12 28-Nov-12 26-Nov-12 27-Jan-13 48
A46440 Installation of Chillers 51 27-Sep-12 28-Nov-12 26-Nov-12 27-Jan-13 48
A46509 Flushing for Chiled Water Pipes 32 29-Nov-12 07-Jan-13 28-Jan-13 05-Mar-13 48
StaircaseStaircase 45 04-Feb-13 27-Mar-13 05-Mar-13 25-Apr-13 25
Stair 2Stair 2 45 04-Feb-13 27-Mar-13 05-Mar-13 25-Apr-13 25
A109070 Floor Screed 3 04-Feb-13 06-Feb-13 05-Mar-13 07-Mar-13 25
A109080 Install Handrails 4 07-Feb-13 11-Feb-13 09-Mar-13 12-Mar-13 25
A109090 Ceiling 1st Coat Paint 7 12-Feb-13 19-Feb-13 13-Mar-13 20-Mar-13 25
A109100 Wall 1st Coat Paint 7 20-Feb-13 27-Feb-13 21-Mar-13 28-Mar-13 25
A109110 Install Granite/Terrazo 12 28-Feb-13 13-Mar-13 30-Mar-13 11-Apr-13 25
A109120 Final Coat Paint 12 14-Mar-13 27-Mar-13 13-Apr-13 25-Apr-13 25
Upper Roof LUpper Roof Level 294 22-Sep-12 08-Sep-13 30-Jan-13 02-Oct-13 21
Public AreaPublic Area 294 22-Sep-12 08-Sep-13 30-Jan-13 02-Oct-13 21
SwimmingSwimming Pool Deck 294 22-Sep-12 08-Sep-13 06-Mar-13 02-Oct-13 21
FinishingFinishing Works 294 22-Sep-12 08-Sep-13 06-Mar-13 02-Oct-13 21
A53830 Block Works 3 22-Sep-12 24-Sep-12 06-Mar-13 09-Mar-13 136
A53840 Plaster Works 4 25-Sep-12 29-Sep-12 10-Mar-13 13-Mar-13 136
A53850 1st Coat Paint 4 30-Sep-12 03-Oct-12 14-Mar-13 18-Mar-13 136
A53910 Instaaltion of Wooden Pergola 10 04-Oct-12 15-Oct-12 19-Mar-13 30-Mar-13 136
A53860 Floor Tiles Work 10 20-Oct-12 01-Nov-12 31-Mar-13 10-Apr-13 133
A53870 Installation of Doors 3 03-Nov-12 05-Nov-12 11-Apr-13 14-Apr-13 133
A53880 Doors Ironmongery 3 06-Nov-12 08-Nov-12 15-Apr-13 17-Apr-13 133
A53890 Final Coat Paint 3 10-Nov-12 12-Nov-12 18-Apr-13 21-Apr-13 133
A53900 Installation of Sinages 2 13-Nov-12 14-Nov-12 24-Apr-13 25-Apr-13 135
A53820 Installation of Metal Kitchen Cabinet , Bar , B.B.Q 4 13-Nov-12 18-Nov-12 22-Apr-13 25-Apr-13 133
A53920 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
SwimmingSwimming Pool 59 26-Sep-12 08-Dec-12 17-Feb-13 25-Apr-13 117
FinishingFinishing Works 59 26-Sep-12 08-Dec-12 17-Feb-13 25-Apr-13 117
A50630 Pouring of Screed 4 26-Sep-12 30-Sep-12 17-Feb-13 20-Feb-13 117
A50640 Laying of Waterproofing 4 01-Oct-12 04-Oct-12 21-Feb-13 25-Feb-13 117
A50650 Pouring of Guniting 5 06-Oct-12 10-Oct-12 26-Feb-13 03-Mar-13 117
A50660 Laying of Waterproofing 4 11-Oct-12 15-Oct-12 04-Mar-13 07-Mar-13 117
A50670 Waterproofing Plastering 15 16-Oct-12 04-Nov-12 09-Mar-13 25-Mar-13 117
A50680 Fix the Tiles 20 05-Nov-12 28-Nov-12 26-Mar-13 17-Apr-13 117
A50860 Installation of Stairs - Gratings -Nozzles 7 29-Nov-12 08-Dec-12 18-Apr-13 25-Apr-13 117
A50890 Installatiof of Lights 7 29-Nov-12 08-Dec-12 18-Apr-13 25-Apr-13 117
LPG Tank ALPG Tank Area 56 22-Sep-12 28-Nov-12 20-Feb-13 25-Apr-13 124
FinishingFinishing Works 56 22-Sep-12 28-Nov-12 20-Feb-13 25-Apr-13 124
A90990 Water Proofing for Roof Area 10 22-Sep-12 02-Oct-12 20-Feb-13 03-Mar-13 124
A91000 Floor Tiles Work 10 03-Oct-12 14-Oct-12 04-Mar-13 14-Mar-13 124
A90970 Installation of Steel Support 9 04-Nov-12 13-Nov-12 02-Apr-13 11-Apr-13 124
A90980 Installation of Louver 12 14-Nov-12 28-Nov-12 13-Apr-13 25-Apr-13 124
GRP WaterGRP Water Tank 30 22-Sep-12 28-Oct-12 30-Jan-13 05-Mar-13 106
FinishingFinishing Works 18 22-Sep-12 11-Oct-12 30-Jan-13 19-Feb-13 106
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
Wall Tiles Work
Floor Tiles Work
Final Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Water Proofing Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Floor Tiles Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Installation of Chillers
Flushing for Chiled Water Pipes
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
1st Coat Paint
Instaaltion of Wooden Pergola
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Metal Kitchen Cabinet , Bar , B.B.Q
Installation of Furnitur
Pouring of Screed
Laying of Waterproofing
Pouring of Guniting
Laying of Waterproofing
Waterproofing Plastering
Fix the Tiles
Installation of Stairs - Gratings -Nozzles
Installatiof of Lights
Water Proofing for Roof Area
Floor Tiles Work
Installation of Steel Support
Installation of Louver
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 51 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A91020 Water Proofing for Roof Area 8 22-Sep-12 30-Sep-12 30-Jan-13 07-Feb-13 106
A91030 Floor Tiles Work 10 01-Oct-12 11-Oct-12 09-Feb-13 19-Feb-13 106
MEP WorkMEP Works 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106
PlumbingPlumbing 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106
A91010 Installation of GRP Tank 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106
Hotel (BlockHotel (Block B) 369 24-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21
2nd Basemen2nd Basement Floor 193 24-Jun-12 12-Feb-13 06-Dec-12 28-Apr-13 64
Public AreaPublic Area 193 24-Jun-12 12-Feb-13 06-Dec-12 28-Apr-13 64
Parking ArParking Area 193 24-Jun-12 12-Feb-13 10-Jan-13 28-Apr-13 64
FinishingFinishing Works 184 04-Jul-12 12-Feb-13 05-Feb-13 28-Apr-13 64
Wet WorWet Works 127 04-Jul-12 05-Dec-12 05-Feb-13 24-Feb-13 67
A54800 Plaster Works 5 04-Jul-12 09-Jul-12 05-Feb-13 10-Feb-13 177
A54810 1st Coat Paint 12 21-Nov-12 05-Dec-12 11-Feb-13 24-Feb-13 67
Traffic DTraffic Deck Coating 52 06-Dec-12 06-Feb-13 25-Feb-13 28-Apr-13 69
A115780 Installation of Kerbs 8 06-Dec-12 15-Dec-12 25-Feb-13 05-Mar-13 67
A115790 Installation of Interlocking Tiles 8 16-Dec-12 24-Dec-12 06-Mar-13 14-Mar-13 67
A54740 Surface Preparation (including Grinding & Repairing) 8 29-Dec-12 07-Jan-13 16-Mar-13 24-Mar-13 64
A54750 Application of 1st Coat 7 05-Jan-13 12-Jan-13 21-Mar-13 28-Mar-13 64
A54790 Application of Final Coat 7 13-Jan-13 20-Jan-13 30-Mar-13 06-Apr-13 64
A54770 Road Marking & Arrows 7 21-Jan-13 29-Jan-13 07-Apr-13 14-Apr-13 64
A115800 Installation of Speed Hump 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69
Final StaFinal Stage Finishes 12 30-Jan-13 12-Feb-13 15-Apr-13 28-Apr-13 64
A54820 Final Coat Paint 5 30-Jan-13 04-Feb-13 15-Apr-13 20-Apr-13 64
A54840 Installation of Sinages 7 05-Feb-13 12-Feb-13 21-Apr-13 28-Apr-13 64
MEP WorkMEP Works 124 24-Jun-12 20-Nov-12 10-Jan-13 10-Feb-13 67
HVACHVAC 10 24-Jun-12 04-Jul-12 30-Jan-13 10-Feb-13 181
A54860 Chilled Water Pipe Installation & Insulation 7 24-Jun-12 01-Jul-12 30-Jan-13 06-Feb-13 181
A54870 Condensate Pipe Installation 7 24-Jun-12 01-Jul-12 30-Jan-13 06-Feb-13 181
A54970 FCU Installation 3 02-Jul-12 04-Jul-12 07-Feb-13 10-Feb-13 181
A55210 Installation of Induction Fan 3 02-Jul-12 04-Jul-12 07-Feb-13 10-Feb-13 181
ElectricalElectrical 115 04-Jul-12 20-Nov-12 10-Jan-13 10-Feb-13 67
A115810 Instalaltion of Cable Trays 10 04-Jul-12 15-Jul-12 10-Jan-13 21-Jan-13 156
A115820 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 21-Jan-13 07-Feb-13 67
A115830 Cable Pulling 10 06-Nov-12 18-Nov-12 28-Jan-13 07-Feb-13 67
A54830 Installation of Lighting Fittings 2 19-Nov-12 20-Nov-12 09-Feb-13 10-Feb-13 67
PlumbingPlumbing 11 04-Jul-12 16-Jul-12 29-Jan-13 10-Feb-13 171
A54910 H/L Hot&Cold Water Pipe Installation 7 04-Jul-12 11-Jul-12 29-Jan-13 05-Feb-13 171
A54930 Floor Drain Fixning 7 04-Jul-12 11-Jul-12 03-Feb-13 10-Feb-13 175
A54950 H/L Drainage Pipes Installation 7 04-Jul-12 11-Jul-12 29-Jan-13 05-Feb-13 171
A54980 Installation of Sump Pumps 9 04-Jul-12 14-Jul-12 31-Jan-13 10-Feb-13 173
A54920 Water Pipes Testing 4 12-Jul-12 16-Jul-12 06-Feb-13 10-Feb-13 171
A54960 Drainage&Water Pipes Testing 4 12-Jul-12 16-Jul-12 06-Feb-13 10-Feb-13 171
Fire FighFire Fighting 26 04-Jul-12 02-Aug-12 10-Jan-13 10-Feb-13 156
A54900 Fire Fighting Pipe 8 04-Jul-12 12-Jul-12 10-Jan-13 19-Jan-13 156
A54890 Hydro Static Test for Pipes 5 14-Jul-12 18-Jul-12 20-Jan-13 26-Jan-13 156
A54880 Sprinkler Fixing 7 19-Jul-12 26-Jul-12 27-Jan-13 03-Feb-13 156
A54850 Fire Alarm Devices 6 28-Jul-12 02-Aug-12 04-Feb-13 10-Feb-13 156
RampRamp 114 20-Sep-12 06-Feb-13 03-Mar-13 28-Apr-13 69
A115840 Install Handrail 7 20-Sep-12 27-Sep-12 03-Mar-13 10-Mar-13 134
A115850 1st Coat Paint 10 24-Nov-12 05-Dec-12 11-Mar-13 21-Mar-13 89
A115860 Surface Preparation (including Grinding & Repairing) 8 29-Dec-12 07-Jan-13 23-Mar-13 31-Mar-13 70
A115870 Application of 1st Coat 5 08-Jan-13 13-Jan-13 01-Apr-13 06-Apr-13 70
A115880 Application of Final Coat 5 15-Jan-13 20-Jan-13 07-Apr-13 11-Apr-13 69
A115890 Road Marking & Arrows 7 21-Jan-13 29-Jan-13 13-Apr-13 20-Apr-13 69
A115900 Final Coat Paint 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69
Boiler RooBoiler Room 95 25-Jun-12 15-Oct-12 22-Dec-12 28-Apr-13 161
FinishingFinishing Works 95 25-Jun-12 15-Oct-12 22-Dec-12 28-Apr-13 161
Wet WorWet Works 34 25-Jun-12 02-Aug-12 22-Dec-12 12-Mar-13 182
A54270 Block Works 8 25-Jun-12 03-Jul-12 22-Dec-12 30-Dec-12 148
A54230 Installation of Doors& Windows Sub-frame 1 10-Jul-12 10-Jul-12 12-Mar-13 12-Mar-13 202
A54220 Plaster Works 7 10-Jul-12 17-Jul-12 07-Jan-13 14-Jan-13 148
A54240 1st Coat Paint 9 24-Jul-12 02-Aug-12 21-Jan-13 31-Jan-13 148
Fisrt StaFisrt Stage Finishes 8 08-Sep-12 16-Sep-12 10-Mar-13 25-Apr-13 184
A54330 Epoxy Paint Works 3 08-Sep-12 10-Sep-12 10-Mar-13 12-Mar-13 151
A54260 Installation of Doors 2 11-Sep-12 12-Sep-12 13-Mar-13 14-Mar-13 151
A54280 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Second SSecond Stage Finishes 6 11-Sep-12 17-Sep-12 20-Apr-13 25-Apr-13 183
A54250 Final Coat Paint 6 11-Sep-12 17-Sep-12 20-Apr-13 25-Apr-13 183
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A54320 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 54 04-Jul-12 06-Sep-12 31-Dec-12 24-Apr-13 191
HVACHVAC 14 04-Jul-12 19-Jul-12 18-Feb-13 05-Mar-13 188
A54350 Duct Installation & Insulation 7 04-Jul-12 11-Jul-12 18-Feb-13 25-Feb-13 188
A54390 Air-Outlet Installation 7 12-Jul-12 19-Jul-12 26-Feb-13 05-Mar-13 188
ElectricalElectrical 32 04-Jul-12 09-Aug-12 31-Dec-12 05-Mar-13 170
A54290 Install Conduits in Wall 5 04-Jul-12 09-Jul-12 31-Dec-12 06-Jan-13 148
A54300 Wiring for Lighting & Power 5 18-Jul-12 23-Jul-12 15-Jan-13 20-Jan-13 148
A54310 Installation of Lighting Fittings 6 04-Aug-12 09-Aug-12 27-Feb-13 05-Mar-13 170
PlumbingPlumbing 28 04-Aug-12 06-Sep-12 02-Feb-13 05-Mar-13 148
A54180 Installation of Hot Water Boiler 7 04-Aug-12 11-Aug-12 02-Feb-13 09-Feb-13 148
A54440 Floor Drain Fixning 7 04-Aug-12 11-Aug-12 26-Feb-13 05-Mar-13 169
A54190 Installation of Hot Water Tank 7 12-Aug-12 21-Aug-12 10-Feb-13 17-Feb-13 148
A54200 Installation of Hot Water Pump 7 22-Aug-12 29-Aug-12 18-Feb-13 25-Feb-13 148
A54210 Installation of Pipes 7 30-Aug-12 06-Sep-12 26-Feb-13 05-Mar-13 148
Fire FighFire Fighting 23 04-Jul-12 30-Jul-12 14-Feb-13 24-Apr-13 222
A54430 Fire Fighting Pipe 6 04-Jul-12 10-Jul-12 14-Feb-13 20-Feb-13 185
A54420 Hydro Static Test for Pipes 3 11-Jul-12 14-Jul-12 21-Feb-13 24-Feb-13 185
A54410 Sprinkler Fixing 4 15-Jul-12 18-Jul-12 25-Feb-13 28-Feb-13 185
A54340 Fire Alarm Devices 7 19-Jul-12 26-Jul-12 02-Mar-13 09-Mar-13 185
A54400 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 23-Apr-13 24-Apr-13 222
Water TankWater Tank 1 & 2 (Block A) 29 28-Jul-12 01-Sep-12 31-Jan-13 05-Mar-13 153
FinishingFinishing Works 21 28-Jul-12 22-Aug-12 31-Jan-13 24-Feb-13 153
A53960 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 31-Jan-13 07-Feb-13 153
A53950 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 09-Feb-13 16-Feb-13 153
A53970 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 17-Feb-13 24-Feb-13 153
MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153
ElectricalElectrical 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
A54160 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
PlumbingPlumbing 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153
A54090 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 25-Feb-13 02-Mar-13 153
A54070 Installation of Sump Pump 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
A54100 Install of Water Meter 3 29-Aug-12 01-Sep-12 03-Mar-13 05-Mar-13 153
Water TankWater Tank 1 & 2 (Block B) 29 28-Jul-12 01-Sep-12 31-Jan-13 05-Mar-13 153
FinishingFinishing Works 21 28-Jul-12 22-Aug-12 31-Jan-13 24-Feb-13 153
A54030 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 31-Jan-13 07-Feb-13 153
A54020 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 09-Feb-13 16-Feb-13 153
A54010 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 17-Feb-13 24-Feb-13 153
MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153
ElectricalElectrical 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
A54170 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
PlumbingPlumbing 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Water Proofing for Roof Area
Floor Tiles Work
Installation of GRP Tank
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Installation of Induction Fan
Instalaltion of Cable Trays
Instalaltion of Bus Bars
Cable Pulling
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Floor Drain Fixning
H/L Drainage Pipes Installation
Installation of Sump Pumps
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Hot Water Boiler
Floor Drain Fixning
Installation of Hot Water Tank
Installation of Hot Water Pump
Installation of Pipes
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
GRP Lining on the Ceiling
GRP Lining on the Wall
Reinforced Plastic on the Floor
Installation of Lighting Fittings
Installation of Water Supply Pipes&Fittings
Installation of Sump Pump
Install of Water Meter
GRP Lining on the Ceiling
GRP Lining on the Wall
Reinforced Plastic on the Floor
Installation of Lighting Fittings
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 52 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A54120 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 25-Feb-13 02-Mar-13 153
A54110 Installation of Sump Pump 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
A54130 Install of Water Meter 3 29-Aug-12 01-Sep-12 03-Mar-13 05-Mar-13 153
GSM RoomGSM Rooms 95 25-Jun-12 15-Oct-12 06-Dec-12 28-Apr-13 161
FinishingFinishing Works 95 25-Jun-12 15-Oct-12 06-Dec-12 28-Apr-13 161
Wet WorWet Works 30 25-Jun-12 29-Jul-12 06-Dec-12 12-Mar-13 186
A54500 Block Works 5 25-Jun-12 30-Jun-12 06-Dec-12 11-Dec-12 135
A54460 Installation of Doors& Windows Sub-frame 2 07-Jul-12 08-Jul-12 11-Mar-13 12-Mar-13 204
A54450 Plaster Works 8 07-Jul-12 15-Jul-12 18-Dec-12 26-Dec-12 135
A54470 1st Coat Paint 7 22-Jul-12 29-Jul-12 03-Jan-13 10-Jan-13 135
Fisrt StaFisrt Stage Finishes 68 09-Jul-12 27-Sep-12 13-Mar-13 25-Apr-13 174
A54490 Installation of Doors 2 09-Jul-12 10-Jul-12 13-Mar-13 14-Mar-13 204
A54510 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A54560 Epoxy Paint Works 2 26-Sep-12 27-Sep-12 13-Mar-13 14-Mar-13 138
Second SSecond Stage Finishes 3 29-Sep-12 01-Oct-12 23-Apr-13 25-Apr-13 171
A54480 Final Coat Paint 3 29-Sep-12 01-Oct-12 23-Apr-13 25-Apr-13 171
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A54550 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 73 01-Jul-12 25-Sep-12 12-Dec-12 12-Mar-13 138
HVACHVAC 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175
A54610 Air-Outlet Installation 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175
ElectricalElectrical 73 01-Jul-12 25-Sep-12 12-Dec-12 05-Mar-13 132
A54520 Install Conduits in Wall 5 01-Jul-12 05-Jul-12 12-Dec-12 17-Dec-12 135
A54530 Wiring for Lighting & Power 5 16-Jul-12 21-Jul-12 27-Dec-12 02-Jan-13 135
A54540 Installation of Lighting Fittings 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175
A1155 Installation of GSM System 45 02-Aug-12 25-Sep-12 12-Jan-13 05-Mar-13 132
Fire FighFire Fighting 5 30-Jul-12 04-Aug-12 07-Mar-13 12-Mar-13 181
A54570 Fire Alarm Devices 5 30-Jul-12 04-Aug-12 07-Mar-13 12-Mar-13 181
MechanicaMechanical Room 95 25-Jun-12 15-Oct-12 08-Jan-13 28-Apr-13 161
FinishingFinishing Works 95 25-Jun-12 15-Oct-12 08-Jan-13 28-Apr-13 161
Wet WorWet Works 13 25-Jun-12 09-Jul-12 08-Jan-13 12-Mar-13 203
A105090 Block Works 2 25-Jun-12 26-Jun-12 08-Jan-13 09-Jan-13 162
A54630 Installation of Doors& Windows Sub-frame 2 27-Jun-12 28-Jun-12 11-Mar-13 12-Mar-13 212
A54620 Plaster Works 5 27-Jun-12 02-Jul-12 28-Feb-13 05-Mar-13 203
A54640 1st Coat Paint 6 03-Jul-12 09-Jul-12 06-Mar-13 12-Mar-13 203
Fisrt StaFisrt Stage Finishes 66 30-Jun-12 16-Sep-12 13-Mar-13 25-Apr-13 184
A54660 Installation of Doors 2 30-Jun-12 01-Jul-12 13-Mar-13 14-Mar-13 212
A54730 Epoxy Paint Works 2 10-Jul-12 11-Jul-12 13-Mar-13 14-Mar-13 203
A54680 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Second SSecond Stage Finishes 2 12-Jul-12 14-Jul-12 24-Apr-13 25-Apr-13 237
A54650 Final Coat Paint 2 12-Jul-12 14-Jul-12 24-Apr-13 25-Apr-13 237
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A54720 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
StaircaseStaircase 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173
Stairs 1Stairs 1 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173
A109270 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147
A109280 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147
A109290 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109300 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109310 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147
A109320 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173
Stairs 2Stairs 2 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173
A109330 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147
A109340 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147
A109350 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109360 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109370 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147
A109380 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173
Stairs 3Stairs 3 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173
A109390 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147
A109400 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147
A109410 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109420 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147
A109430 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147
A109440 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173
1st Basemen1st Basement Floor 207 23-Jul-12 30-Mar-13 04-Oct-12 28-Apr-13 25
Public AreaPublic Area 207 23-Jul-12 30-Mar-13 04-Oct-12 28-Apr-13 25
Parking ArParking Area 87 13-Dec-12 26-Mar-13 13-Jan-13 28-Apr-13 28
FinishingFinishing Works 87 13-Dec-12 26-Mar-13 12-Feb-13 28-Apr-13 28
Wet WorWet Works 42 13-Dec-12 02-Feb-13 12-Feb-13 03-Mar-13 25
A59680 Plaster Works 5 13-Dec-12 18-Dec-12 12-Feb-13 17-Feb-13 50
A59690 1st Coat Paint 12 19-Jan-13 02-Feb-13 18-Feb-13 03-Mar-13 25
Traffic DTraffic Deck Coating 41 30-Jan-13 18-Mar-13 04-Mar-13 28-Apr-13 35
A115930 Installation of Speed Hump 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69
A115910 Installation of Kerbs 8 03-Feb-13 11-Feb-13 04-Mar-13 12-Mar-13 25
A115920 Installation of Interlocking Tiles 8 12-Feb-13 20-Feb-13 13-Mar-13 21-Mar-13 25
A59620 Surface Preparation (including Grinding & Repairing) 8 21-Feb-13 02-Mar-13 23-Mar-13 31-Mar-13 25
A59630 Application of 1st Coat 5 27-Feb-13 04-Mar-13 01-Apr-13 06-Apr-13 28
A59670 Application of Final Coat 5 05-Mar-13 10-Mar-13 07-Apr-13 11-Apr-13 28
A59650 Road Marking & Arrows 7 11-Mar-13 18-Mar-13 13-Apr-13 20-Apr-13 28
Final StaFinal Stage Finishes 7 19-Mar-13 26-Mar-13 21-Apr-13 28-Apr-13 28
A59700 Final Coat Paint 5 19-Mar-13 24-Mar-13 21-Apr-13 25-Apr-13 28
A59720 Installation of Sinages 2 25-Mar-13 26-Mar-13 27-Apr-13 28-Apr-13 28
MEP WorkMEP Works 30 13-Dec-12 17-Jan-13 13-Jan-13 17-Feb-13 25
HVACHVAC 10 13-Dec-12 24-Dec-12 06-Feb-13 17-Feb-13 45
A59740 Chilled Water Pipe Installation & Insulation 7 13-Dec-12 20-Dec-12 06-Feb-13 13-Feb-13 45
A59750 Condensate Pipe Installation 7 13-Dec-12 20-Dec-12 06-Feb-13 13-Feb-13 45
A59820 Installation of Fan Induction 3 22-Dec-12 24-Dec-12 14-Feb-13 17-Feb-13 45
ElectricalElectrical 30 13-Dec-12 17-Jan-13 13-Jan-13 17-Feb-13 25
A115940 Instalaltion of Cable Trays 10 13-Dec-12 24-Dec-12 13-Jan-13 23-Jan-13 25
A115950 Instalaltion of Bus Bars 15 13-Dec-12 30-Dec-12 19-Jan-13 05-Feb-13 30
A115960 Cable Pulling 10 25-Dec-12 06-Jan-13 26-Jan-13 05-Feb-13 25
A59710 Installation of Lighting Fittings 10 07-Jan-13 17-Jan-13 06-Feb-13 17-Feb-13 25
PlumbingPlumbing 11 13-Dec-12 25-Dec-12 05-Feb-13 17-Feb-13 44
A59810 Floor Drain Fixning 5 13-Dec-12 18-Dec-12 12-Feb-13 17-Feb-13 50
A59790 H/L Hot&Cold Water Pipe Installation 7 13-Dec-12 20-Dec-12 05-Feb-13 12-Feb-13 44
A59830 H/L Drainage Pipes Installation 7 13-Dec-12 20-Dec-12 05-Feb-13 12-Feb-13 44
A59800 Water Pipes Testing 4 22-Dec-12 25-Dec-12 13-Feb-13 17-Feb-13 44
A59840 Drainage&Water Pipes Testing 4 22-Dec-12 25-Dec-12 13-Feb-13 17-Feb-13 44
Fire FighFire Fighting 26 13-Dec-12 13-Jan-13 17-Jan-13 17-Feb-13 29
A59780 Fire Fighting Pipe 8 13-Dec-12 22-Dec-12 17-Jan-13 27-Jan-13 29
A59770 Hydro Static Test for Pipes 5 23-Dec-12 27-Dec-12 28-Jan-13 02-Feb-13 29
A59760 Sprinkler Fixing 7 29-Dec-12 06-Jan-13 03-Feb-13 10-Feb-13 29
A59730 Fire Alarm Devices 6 07-Jan-13 13-Jan-13 11-Feb-13 17-Feb-13 29
RampRamp 85 19-Dec-12 30-Mar-13 03-Mar-13 28-Apr-13 25
A115970 Install Handrail 7 19-Dec-12 26-Dec-12 03-Mar-13 10-Mar-13 61
A115980 1st Coat Paint 10 27-Dec-12 08-Jan-13 11-Mar-13 21-Mar-13 61
A115990 Surface Preparation (including Grinding & Repairing) 8 21-Feb-13 02-Mar-13 23-Mar-13 31-Mar-13 25
A116000 Application of 1st Coat 5 03-Mar-13 07-Mar-13 01-Apr-13 06-Apr-13 25
A116010 Application of Final Coat 5 09-Mar-13 13-Mar-13 07-Apr-13 11-Apr-13 25
A116020 Road Marking & Arrows 7 14-Mar-13 21-Mar-13 13-Apr-13 20-Apr-13 25
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Water Supply Pipes&Fittings
Installation of Sump Pump
Install of Water Meter
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of GSM System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Plaster Works
1st Coat Paint
Installation of Speed Hump
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Installation of Fan Induction
Instalaltion of Cable Trays
Instalaltion of Bus Bars
Cable Pulling
Installation of Lighting Fittings
Floor Drain Fixning
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 53 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A116030 Final Coat Paint 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25
Lift LobbyLift Lobby 71 23-Jul-12 15-Oct-12 08-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 08-Jan-13 28-Apr-13 161
Wet WorWet Works 30 23-Jul-12 28-Aug-12 08-Jan-13 20-Feb-13 145
A59120 Block Works 4 23-Jul-12 26-Jul-12 08-Jan-13 12-Jan-13 138
A59070 Plaster Works 7 31-Jul-12 07-Aug-12 26-Jan-13 02-Feb-13 145
A59090 Installation of Suspended Ceiling Grid 5 14-Aug-12 21-Aug-12 09-Feb-13 13-Feb-13 145
A59080 1st Coat Paint 6 22-Aug-12 28-Aug-12 14-Feb-13 20-Feb-13 145
Fisrt StaFisrt Stage Finishes 9 29-Aug-12 08-Sep-12 21-Feb-13 03-Mar-13 145
A59100 Suspended Ceiling Tiles 5 29-Aug-12 03-Sep-12 21-Feb-13 26-Feb-13 145
A59340 MDF for Lift Lobby Wall 7 29-Aug-12 05-Sep-12 21-Feb-13 28-Feb-13 145
A59320 Screed Works 2 06-Sep-12 08-Sep-12 02-Mar-13 03-Mar-13 145
Second SSecond Stage Finishes 14 09-Sep-12 24-Sep-12 04-Mar-13 19-Mar-13 145
A59330 Wall Tiles Work 7 09-Sep-12 16-Sep-12 04-Mar-13 11-Mar-13 145
A59360 Floor Tiles Work 7 17-Sep-12 24-Sep-12 12-Mar-13 19-Mar-13 145
Final StaFinal Stage Finishes 18 25-Sep-12 15-Oct-12 20-Mar-13 28-Apr-13 161
A59110 Installation of Doors 2 25-Sep-12 26-Sep-12 20-Mar-13 21-Mar-13 145
A59130 Doors Ironmongery 2 25-Sep-12 26-Sep-12 27-Apr-13 28-Apr-13 177
A59370 Final Coat Paint 3 25-Sep-12 27-Sep-12 23-Apr-13 25-Apr-13 174
A59310 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 38 28-Jul-12 11-Sep-12 21-Jan-13 22-Apr-13 185
HVACHVAC 33 28-Jul-12 05-Sep-12 30-Jan-13 05-Mar-13 149
A59140 Duct Installation & Insulation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152
A59150 Chilled Water Pipe Installation & Insulation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152
A59160 Condensate Pipe Installation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152
A59170 FCU Installation 3 02-Aug-12 05-Aug-12 05-Feb-13 07-Feb-13 152
A59180 Air-Outlet Installation 2 04-Sep-12 05-Sep-12 04-Mar-13 05-Mar-13 149
ElectricalElectrical 37 28-Jul-12 10-Sep-12 21-Jan-13 05-Mar-13 145
A59190 Install Conduits in Wall 3 28-Jul-12 30-Jul-12 21-Jan-13 23-Jan-13 145
A59200 Install Cable Trays & Trunking 3 28-Jul-12 30-Jul-12 28-Jan-13 30-Jan-13 150
A59240 Cable Laying for Low Current System 3 31-Jul-12 02-Aug-12 11-Feb-13 13-Feb-13 159
A59250 Cable Laying for Power 3 31-Jul-12 02-Aug-12 11-Feb-13 13-Feb-13 159
A59210 Wiring for Lighting & Power 5 08-Aug-12 13-Aug-12 03-Feb-13 07-Feb-13 145
A59220 Wiring for Low Current System 5 08-Aug-12 13-Aug-12 03-Feb-13 07-Feb-13 145
A59270 Installation of Lighting Fittings 6 04-Sep-12 10-Sep-12 27-Feb-13 05-Mar-13 145
Fire FighFire Fighting 38 28-Jul-12 11-Sep-12 26-Jan-13 22-Apr-13 185
A59300 Fire Fighting Pipe 7 28-Jul-12 04-Aug-12 26-Jan-13 02-Feb-13 148
A59290 Hydro Static Test for Pipes 5 05-Aug-12 09-Aug-12 03-Feb-13 07-Feb-13 148
A59280 Sprinkler Fixing 5 04-Sep-12 09-Sep-12 28-Feb-13 05-Mar-13 146
A59350 Fire Alarm Devices 7 04-Sep-12 11-Sep-12 15-Apr-13 22-Apr-13 185
CorridorCorridor 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
Wet WorWet Works 24 23-Jul-12 21-Aug-12 09-Jan-13 21-Feb-13 152
A59430 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139
A59380 Plaster Works 5 30-Jul-12 04-Aug-12 02-Feb-13 06-Feb-13 152
A59400 Installation of Suspended Ceiling Grid 5 08-Aug-12 13-Aug-12 11-Feb-13 16-Feb-13 152
A59390 1st Coat Paint 5 14-Aug-12 21-Aug-12 17-Feb-13 21-Feb-13 152
Fisrt StaFisrt Stage Finishes 14 22-Aug-12 06-Sep-12 23-Feb-13 19-Mar-13 160
A59410 Suspended Ceiling Tiles 5 22-Aug-12 27-Aug-12 23-Feb-13 27-Feb-13 152
A59580 Epoxy Paint Works 3 04-Sep-12 06-Sep-12 17-Mar-13 19-Mar-13 160
Second SSecond Stage Finishes 8 08-Sep-12 16-Sep-12 20-Mar-13 25-Apr-13 184
A59420 Installation of Doors 2 08-Sep-12 09-Sep-12 20-Mar-13 21-Mar-13 160
A59440 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A59570 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 32 26-Jul-12 03-Sep-12 29-Jan-13 16-Mar-13 160
HVACHVAC 31 26-Jul-12 02-Sep-12 31-Jan-13 05-Mar-13 152
A59450 Duct Installation & Insulation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154
A59460 Chilled Water Pipe Installation & Insulation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154
A59470 Condensate Pipe Installation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154
A59480 FCU Installation 4 01-Aug-12 05-Aug-12 06-Feb-13 10-Feb-13 154
A59490 Air-Outlet Installation 5 28-Aug-12 02-Sep-12 28-Feb-13 05-Mar-13 152
ElectricalElectrical 29 26-Jul-12 30-Aug-12 29-Jan-13 05-Mar-13 154
A59500 Install Conduits in Wall 3 26-Jul-12 29-Jul-12 29-Jan-13 31-Jan-13 152
A59510 Wiring for Lighting & Power 3 05-Aug-12 07-Aug-12 07-Feb-13 10-Feb-13 152
A59520 Installation of Lighting Fittings 3 28-Aug-12 30-Aug-12 03-Mar-13 05-Mar-13 154
PlumbingPlumbing 10 26-Jul-12 06-Aug-12 30-Jan-13 10-Feb-13 153
A59600 H/L Hot&Cold Water Pipe Installation 5 26-Jul-12 31-Jul-12 30-Jan-13 04-Feb-13 153
A59610 Water Pipes Testing 5 01-Aug-12 06-Aug-12 05-Feb-13 10-Feb-13 153
Fire FighFire Fighting 32 26-Jul-12 03-Sep-12 31-Jan-13 16-Mar-13 160
A59560 Fire Fighting Pipe 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154
A59550 Hydro Static Test for Pipes 4 01-Aug-12 05-Aug-12 06-Feb-13 10-Feb-13 154
A59540 Sprinkler Fixing 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
A59590 Fire Alarm Devices 5 28-Aug-12 02-Sep-12 11-Mar-13 16-Mar-13 161
A59530 Installation of Fire Extingusher&Blanket 2 02-Sep-12 03-Sep-12 14-Mar-13 16-Mar-13 160
LV Room (LV Room (Block B) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173
A56450 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136
A56410 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187
A56400 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136
A56420 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136
Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178
A56440 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187
A56460 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A56510 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148
Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
A56430 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A56500 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148
HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A56540 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136
A56470 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136
A56480 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136
A56490 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A114600 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136
A56550 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136
A114610 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136
A114620 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136
Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
A56520 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
LV Room 1LV Room 1 (Block C) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173
A56610 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136
A56570 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187
A56560 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136
A56580 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136
Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178
A56600 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Laying of LV Cables
Installation of MDBs
Test of LV Cables
Termination of LV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 54 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A56620 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A56670 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148
Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
A56590 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A56660 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148
HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A56690 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136
A56630 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136
A56640 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136
A56650 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A114630 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136
A56700 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136
A114640 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136
A114650 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136
Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
A56680 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
LV Room 2LV Room 2 (Block C) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173
A56760 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136
A56720 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187
A56710 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136
A56730 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136
Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178
A56750 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187
A56770 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A56820 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148
Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
A56740 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A56810 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148
HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A56840 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136
A56780 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136
A56790 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136
A56800 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A114660 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136
A56850 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136
A114670 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136
A114680 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136
Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
A56830 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163
LaundryLaundry 102 31-Oct-12 03-Mar-13 14-Nov-12 28-Apr-13 48
FinishingFinishing Works 77 01-Dec-12 03-Mar-13 16-Dec-12 28-Apr-13 48
Wet WorWet Works 30 01-Dec-12 06-Jan-13 16-Dec-12 20-Jan-13 12
A58270 Block Works 10 01-Dec-12 12-Dec-12 16-Dec-12 26-Dec-12 12
A58220 Plaster Works 10 23-Dec-12 03-Jan-13 07-Jan-13 17-Jan-13 12
A58230 1st Coat Paint 6 30-Dec-12 06-Jan-13 14-Jan-13 20-Jan-13 12
Fisrt StaFisrt Stage Finishes 17 06-Feb-13 25-Feb-13 20-Feb-13 22-Apr-13 48
A58240 Installation of Suspended Ceiling Grid 7 06-Feb-13 13-Feb-13 20-Feb-13 27-Feb-13 12
A58250 Suspended Ceiling Tiles 6 10-Feb-13 16-Feb-13 24-Feb-13 02-Mar-13 12
A58420 Epoxy Paint Works 5 20-Feb-13 25-Feb-13 17-Apr-13 22-Apr-13 48
Second SSecond Stage Finishes 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48
A58260 Installation of Doors 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48
A58280 Doors Ironmongery 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48
Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48
A58410 Installation of Sinages 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48
MEP WorkMEP Works 92 31-Oct-12 19-Feb-13 14-Nov-12 16-Apr-13 48
HVACHVAC 57 13-Dec-12 19-Feb-13 21-Jan-13 05-Mar-13 12
A58290 Duct Installation & Insulation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40
A58300 Chilled Water Pipe Installation & Insulation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40
A58310 Condensate Pipe Installation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40
A58320 FCU Installation 7 25-Dec-12 02-Jan-13 12-Feb-13 19-Feb-13 40
A58720 Installation of FAHU 25 07-Jan-13 05-Feb-13 21-Jan-13 19-Feb-13 12
A58330 Air-Outlet Installation 5 14-Feb-13 19-Feb-13 28-Feb-13 05-Mar-13 12
ElectricalElectrical 56 13-Dec-12 18-Feb-13 27-Dec-12 05-Mar-13 13
A58340 Install Conduits in Wall 8 13-Dec-12 22-Dec-12 27-Dec-12 06-Jan-13 12
A58350 Wiring for Lighting & Power 8 05-Jan-13 13-Jan-13 11-Feb-13 19-Feb-13 31
A58360 Installation of Lighting Fittings 5 13-Feb-13 18-Feb-13 28-Feb-13 05-Mar-13 13
PlumbingPlumbing 15 13-Dec-12 30-Dec-12 03-Feb-13 19-Feb-13 42
A58440 H/L Hot&Cold Water Pipe Installation 10 13-Dec-12 24-Dec-12 03-Feb-13 13-Feb-13 42
A58450 Water Pipes Testing 5 25-Dec-12 30-Dec-12 14-Feb-13 19-Feb-13 42
Fire FighFire Fighting 55 13-Dec-12 17-Feb-13 02-Feb-13 16-Apr-13 50
A58400 Fire Fighting Pipe 10 13-Dec-12 24-Dec-12 02-Feb-13 12-Feb-13 41
A58390 Hydro Static Test for Pipes 6 25-Dec-12 31-Dec-12 13-Feb-13 19-Feb-13 41
A58370 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51
A58380 Sprinkler Fixing 3 13-Feb-13 16-Feb-13 03-Mar-13 05-Mar-13 15
A58430 Fire Alarm Devices 4 13-Feb-13 17-Feb-13 13-Apr-13 16-Apr-13 50
LaundryLaundry Equipments 50 31-Oct-12 30-Dec-12 14-Nov-12 14-Jan-13 12
A105460 Installation of Laundry Equipments 50 31-Oct-12 30-Dec-12 14-Nov-12 14-Jan-13 12
ELV RoomsELV Rooms 116 23-Jul-12 11-Dec-12 24-Oct-12 28-Apr-13 116
FinishingFinishing Works 116 23-Jul-12 11-Dec-12 24-Oct-12 28-Apr-13 116
Wet WorWet Works 28 23-Jul-12 26-Aug-12 24-Oct-12 19-Mar-13 170
A56910 Block Works 4 23-Jul-12 26-Jul-12 24-Oct-12 30-Oct-12 78
A56870 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187
A56860 Plaster Works 7 02-Aug-12 09-Aug-12 06-Nov-12 13-Nov-12 78
A56880 1st Coat Paint 7 16-Aug-12 26-Aug-12 21-Nov-12 28-Nov-12 78
Fisrt StaFisrt Stage Finishes 100 05-Aug-12 05-Dec-12 20-Mar-13 25-Apr-13 119
A56900 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187
A56920 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A56970 Epoxy Paint Works 2 04-Dec-12 05-Dec-12 20-Mar-13 21-Mar-13 89
Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 23-Apr-13 25-Apr-13 116
A56890 Final Coat Paint 3 06-Dec-12 09-Dec-12 23-Apr-13 25-Apr-13 116
Final StaFinal Stage Finishes 2 10-Dec-12 11-Dec-12 27-Apr-13 28-Apr-13 116
A56960 Installation of Sinages 2 10-Dec-12 11-Dec-12 27-Apr-13 28-Apr-13 116
MEP WorkMEP Works 105 28-Jul-12 03-Dec-12 31-Oct-12 19-Mar-13 89
HVACHVAC 7 27-Aug-12 03-Sep-12 26-Feb-13 05-Mar-13 151
A57000 Air-Outlet Installation 7 27-Aug-12 03-Sep-12 26-Feb-13 05-Mar-13 151
ElectricalElectrical 105 28-Jul-12 03-Dec-12 31-Oct-12 05-Mar-13 77
A56930 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 31-Oct-12 05-Nov-12 78
A56940 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 14-Nov-12 20-Nov-12 78
A56950 Installation of Lighting Fittings 5 27-Aug-12 01-Sep-12 28-Feb-13 05-Mar-13 153
A114330 Installation of MATC,TV System 80 27-Aug-12 01-Dec-12 29-Nov-12 05-Mar-13 78
A114320 Installation of Access ControlSystem 80 28-Aug-12 03-Dec-12 29-Nov-12 05-Mar-13 77
Fire FighFire Fighting 8 27-Aug-12 04-Sep-12 11-Mar-13 19-Mar-13 162
A56980 Fire Alarm Devices 8 27-Aug-12 04-Sep-12 11-Mar-13 19-Mar-13 162
StoresStores 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Laying of LV Cables
Installation of MDBs
Test of LV Cables
Termination of LV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Laying of LV Cables
Installation of MDBs
Test of LV Cables
Termination of LV Cables
Fire Alarm Devices
Block Works
Plaster Works
1st Coat Paint
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Installation of FAHU
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Installation of Laundry Equipments
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of MATC,TV System
Installation of Access ControlSystem
Fire Alarm Devices
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 55 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
Wet WorWet Works 24 23-Jul-12 21-Aug-12 09-Jan-13 19-Feb-13 150
A57950 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139
A57890 Plaster Works 3 31-Jul-12 02-Aug-12 31-Jan-13 03-Feb-13 150
A57910 Installation of Suspended Ceiling Grid 6 08-Aug-12 14-Aug-12 09-Feb-13 14-Feb-13 150
A57900 1st Coat Paint 4 15-Aug-12 21-Aug-12 16-Feb-13 19-Feb-13 150
Fisrt StaFisrt Stage Finishes 17 22-Aug-12 10-Sep-12 20-Feb-13 19-Mar-13 157
A57920 Suspended Ceiling Tiles 5 22-Aug-12 27-Aug-12 20-Feb-13 25-Feb-13 150
A58180 Epoxy Paint Works 3 08-Sep-12 10-Sep-12 17-Mar-13 19-Mar-13 157
Second SSecond Stage Finishes 5 11-Sep-12 16-Sep-12 20-Mar-13 25-Apr-13 184
A57930 Installation of Doors 2 11-Sep-12 12-Sep-12 20-Mar-13 21-Mar-13 157
A57960 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A58170 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 35 26-Jul-12 06-Sep-12 27-Jan-13 16-Mar-13 157
HVACHVAC 30 26-Jul-12 01-Sep-12 29-Jan-13 05-Mar-13 153
A57970 Duct Installation & Insulation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152
A57980 Chilled Water Pipe Installation & Insulation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152
A57990 Condensate Pipe Installation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152
A58000 FCU Installation 4 01-Aug-12 05-Aug-12 04-Feb-13 07-Feb-13 152
A58010 Air-Outlet Installation 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
ElectricalElectrical 31 26-Jul-12 02-Sep-12 27-Jan-13 05-Mar-13 152
A58020 Install Conduits in Wall 4 26-Jul-12 30-Jul-12 27-Jan-13 30-Jan-13 150
A58040 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 04-Feb-13 07-Feb-13 150
A58100 Installation of Lighting Fittings 5 28-Aug-12 02-Sep-12 28-Feb-13 05-Mar-13 152
Fire FighFire Fighting 35 26-Jul-12 06-Sep-12 27-Jan-13 16-Mar-13 157
A58160 Fire Fighting Pipe 7 26-Jul-12 02-Aug-12 27-Jan-13 03-Feb-13 150
A58150 Hydro Static Test for Pipes 4 04-Aug-12 07-Aug-12 04-Feb-13 07-Feb-13 150
A58140 Sprinkler Fixing 7 28-Aug-12 04-Sep-12 26-Feb-13 05-Mar-13 150
A58210 Fire Alarm Devices 7 28-Aug-12 04-Sep-12 09-Mar-13 16-Mar-13 159
A58130 Installation of Fire Extingusher&Blanket 2 05-Sep-12 06-Sep-12 14-Mar-13 16-Mar-13 157
Staff LockeStaff Lockers 108 23-Jul-12 01-Dec-12 09-Dec-12 28-Apr-13 124
FinishingFinishing Works 108 23-Jul-12 01-Dec-12 09-Dec-12 28-Apr-13 124
Wet WorWet Works 28 23-Jul-12 26-Aug-12 09-Dec-12 13-Mar-13 165
A58770 Block Works 7 23-Jul-12 30-Jul-12 09-Dec-12 16-Dec-12 113
A58690 Plaster Works 7 08-Aug-12 15-Aug-12 25-Dec-12 02-Jan-13 113
A58700 Installation of Doors& Windows Sub-frame 7 08-Aug-12 15-Aug-12 06-Mar-13 13-Mar-13 172
A59020 Wall Tiles Work 7 16-Aug-12 26-Aug-12 03-Jan-13 10-Jan-13 113
Fisrt StaFisrt Stage Finishes 14 27-Aug-12 11-Sep-12 12-Jan-13 28-Jan-13 113
A59010 Screed Works 7 27-Aug-12 03-Sep-12 12-Jan-13 19-Jan-13 113
A58730 Water Proofing for Wet Area 7 04-Sep-12 11-Sep-12 20-Jan-13 28-Jan-13 113
Second SSecond Stage Finishes 38 12-Sep-12 28-Oct-12 29-Jan-13 13-Mar-13 113
A59050 Installation of Suspended Ceiling Grid 7 12-Sep-12 19-Sep-12 29-Jan-13 05-Feb-13 113
A59040 Suspended Ceiling Tiles 7 20-Sep-12 27-Sep-12 06-Feb-13 13-Feb-13 113
A59920 Instllation of Lockers 10 29-Sep-12 09-Oct-12 14-Feb-13 25-Feb-13 113
A59030 Floor Tiles Work 7 18-Oct-12 28-Oct-12 06-Mar-13 13-Mar-13 113
Final StaFinal Stage Finishes 14 14-Nov-12 01-Dec-12 14-Mar-13 28-Apr-13 124
A58740 Installation of Windows&Doors 7 14-Nov-12 22-Nov-12 14-Mar-13 21-Mar-13 99
A58780 Doors Ironmongery 7 14-Nov-12 22-Nov-12 13-Apr-13 20-Apr-13 124
A59000 Installation of Sinages 7 24-Nov-12 01-Dec-12 21-Apr-13 28-Apr-13 124
MEP WorkMEP Works 66 31-Jul-12 17-Oct-12 17-Dec-12 24-Apr-13 156
HVACHVAC 56 31-Jul-12 06-Oct-12 12-Jan-13 05-Mar-13 123
A58790 Duct Installation & Insulation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58800 Chilled Water Pipe Installation & Insulation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58810 Condensate Pipe Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58820 FCU Installation 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134
A58830 Air-Outlet Installation 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123
ElectricalElectrical 56 31-Jul-12 06-Oct-12 17-Dec-12 05-Mar-13 123
A58840 Install Conduits in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113
A58850 Wiring for Lighting & Power 7 16-Aug-12 26-Aug-12 20-Jan-13 28-Jan-13 127
A58860 Installation of Lighting Fittings 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123
PlumbingPlumbing 66 31-Jul-12 17-Oct-12 17-Dec-12 05-Mar-13 113
A58870 Drainge Pipes in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113
A58880 H/L Drainage Pipes Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58890 H/L Hot&Cold Water Pipe Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58940 Water Pipes in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113
A58900 Drainage&Water Pipes Testing 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134
A58910 ElectricalWater Heater Installation 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134
A58920 Floor Drain Fixning 7 29-Aug-12 05-Sep-12 26-Feb-13 05-Mar-13 149
A58930 Installation of Sanitaryware 7 10-Oct-12 17-Oct-12 26-Feb-13 05-Mar-13 113
Fire FighFire Fighting 63 31-Jul-12 14-Oct-12 12-Jan-13 24-Apr-13 159
A58980 Fire Fighting Pipe 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134
A58970 Hydro Static Test for Pipes 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134
A58960 Sprinkler Fixing 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123
A59060 Fire Alarm Devices 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123
A58950 Installation of Fire Extingusher&Blanket 7 07-Oct-12 14-Oct-12 17-Apr-13 24-Apr-13 159
Pump RooPump Room 1 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161
Wet WorWet Works 24 23-Jul-12 21-Aug-12 25-Dec-12 19-Mar-13 174
A55040 Block Works 6 23-Jul-12 29-Jul-12 25-Dec-12 31-Dec-12 127
A55000 Installation of Doors& Windows Sub-frame 1 02-Aug-12 02-Aug-12 19-Mar-13 19-Mar-13 188
A54990 Plaster Works 6 02-Aug-12 08-Aug-12 06-Jan-13 12-Jan-13 127
A55010 1st Coat Paint 6 13-Aug-12 21-Aug-12 16-Jan-13 22-Jan-13 127
Fisrt StaFisrt Stage Finishes 51 04-Aug-12 03-Oct-12 20-Mar-13 25-Apr-13 169
A55030 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188
A55050 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A55100 Epoxy Paint Works 2 02-Oct-12 03-Oct-12 20-Mar-13 21-Mar-13 139
Second SSecond Stage Finishes 3 04-Oct-12 07-Oct-12 23-Apr-13 25-Apr-13 166
A55020 Final Coat Paint 3 04-Oct-12 07-Oct-12 23-Apr-13 25-Apr-13 166
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A55090 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 53 30-Jul-12 01-Oct-12 02-Jan-13 24-Apr-13 170
HVACHVAC 53 30-Jul-12 01-Oct-12 23-Jan-13 05-Mar-13 127
A55120 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55130 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55140 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55150 FCU Installation 5 07-Aug-12 12-Aug-12 20-Feb-13 25-Feb-13 161
A55160 Air-Outlet Installation 7 13-Aug-12 22-Aug-12 26-Feb-13 05-Mar-13 161
A105410 Installation of Pumps 35 22-Aug-12 01-Oct-12 23-Jan-13 05-Mar-13 127
ElectricalElectrical 23 30-Jul-12 27-Aug-12 02-Jan-13 05-Mar-13 157
A55060 Install Conduits in Wall 3 30-Jul-12 01-Aug-12 02-Jan-13 05-Jan-13 127
A55070 Wiring for Lighting & Power 3 09-Aug-12 12-Aug-12 13-Jan-13 15-Jan-13 127
A55080 Installation of Lighting Fittings 5 22-Aug-12 27-Aug-12 28-Feb-13 05-Mar-13 157
PlumbingPlumbing 33 30-Jul-12 08-Sep-12 17-Feb-13 05-Mar-13 147
A55220 H/L Hot&Cold Water Pipe Installation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168
A55230 Water Pipes Testing 5 07-Aug-12 12-Aug-12 28-Feb-13 05-Mar-13 168
A55240 Installation of Transfer Pump 15 22-Aug-12 08-Sep-12 17-Feb-13 05-Mar-13 147
Fire FighFire Fighting 48 30-Jul-12 25-Sep-12 30-Jan-13 24-Apr-13 175
A55200 Fire Fighting Pipe 7 30-Jul-12 06-Aug-12 16-Feb-13 23-Feb-13 164
A55190 Hydro Static Test for Pipes 4 07-Aug-12 11-Aug-12 24-Feb-13 27-Feb-13 164
A55180 Sprinkler Fixing 5 12-Aug-12 16-Aug-12 28-Feb-13 05-Mar-13 164
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Instllation of Lockers
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Installation of Pumps
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Installation of Transfer Pump
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 56 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A55170 Installation of Fire Extingusher&Blanket 3 18-Aug-12 22-Aug-12 22-Apr-13 24-Apr-13 204
A55110 Fire Alarm Devices 6 18-Aug-12 26-Aug-12 13-Mar-13 19-Mar-13 170
A55530 Installation of Fire Fighting Pump 30 22-Aug-12 25-Sep-12 30-Jan-13 05-Mar-13 132
Pump RooPump Room 2 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 26 23-Jul-12 23-Aug-12 06-Jan-13 19-Mar-13 172
A55590 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136
A55550 Installation of Doors& Windows Sub-frame 1 02-Aug-12 02-Aug-12 19-Mar-13 19-Mar-13 188
A55540 Plaster Works 6 02-Aug-12 08-Aug-12 28-Jan-13 03-Feb-13 145
A55560 1st Coat Paint 6 15-Aug-12 23-Aug-12 10-Feb-13 16-Feb-13 145
Fisrt StaFisrt Stage Finishes 36 04-Aug-12 16-Sep-12 20-Mar-13 25-Apr-13 184
A55580 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188
A55650 Epoxy Paint Works 2 11-Sep-12 12-Sep-12 20-Mar-13 21-Mar-13 157
A55600 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Second SSecond Stage Finishes 3 13-Sep-12 16-Sep-12 23-Apr-13 25-Apr-13 184
A55570 Final Coat Paint 3 13-Sep-12 16-Sep-12 23-Apr-13 25-Apr-13 184
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A55640 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 35 30-Jul-12 10-Sep-12 23-Jan-13 24-Apr-13 188
HVACHVAC 19 30-Jul-12 22-Aug-12 12-Feb-13 05-Mar-13 161
A55670 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55680 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55690 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161
A55700 FCU Installation 5 07-Aug-12 12-Aug-12 20-Feb-13 25-Feb-13 161
A55710 Air-Outlet Installation 7 13-Aug-12 22-Aug-12 26-Feb-13 05-Mar-13 161
ElectricalElectrical 25 30-Jul-12 29-Aug-12 23-Jan-13 05-Mar-13 155
A55610 Install Conduits in Wall 3 30-Jul-12 01-Aug-12 23-Jan-13 27-Jan-13 145
A55620 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 04-Feb-13 09-Feb-13 145
A55630 Installation of Lighting Fittings 5 25-Aug-12 29-Aug-12 28-Feb-13 05-Mar-13 155
PlumbingPlumbing 35 30-Jul-12 10-Sep-12 17-Feb-13 05-Mar-13 145
A55760 H/L Hot&Cold Water Pipe Installation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168
A55770 Water Pipes Testing 5 07-Aug-12 12-Aug-12 28-Feb-13 05-Mar-13 168
A55780 Installation of Transfer Pump 15 25-Aug-12 10-Sep-12 17-Feb-13 05-Mar-13 145
Fire FighFire Fighting 27 30-Jul-12 01-Sep-12 16-Feb-13 24-Apr-13 196
A55750 Fire Fighting Pipe 7 30-Jul-12 06-Aug-12 16-Feb-13 23-Feb-13 164
A55740 Hydro Static Test for Pipes 4 07-Aug-12 11-Aug-12 24-Feb-13 27-Feb-13 164
A55730 Sprinkler Fixing 5 12-Aug-12 16-Aug-12 28-Feb-13 05-Mar-13 164
A55720 Installation of Fire Extingusher&Blanket 3 18-Aug-12 22-Aug-12 22-Apr-13 24-Apr-13 204
A55660 Fire Alarm Devices 6 18-Aug-12 26-Aug-12 13-Mar-13 19-Mar-13 170
A55790 Installation of Fire Fighting Pump 7 25-Aug-12 01-Sep-12 26-Feb-13 05-Mar-13 153
AHU RoomAHU Room 75 23-Jul-12 20-Oct-12 17-Dec-12 28-Apr-13 157
FinishingFinishing Works 75 23-Jul-12 20-Oct-12 17-Dec-12 28-Apr-13 157
Wet WorWet Works 36 23-Jul-12 04-Sep-12 17-Dec-12 19-Mar-13 162
A55850 Block Works 8 23-Jul-12 31-Jul-12 17-Dec-12 25-Dec-12 120
A55810 Installation of Doors& Windows Sub-frame 1 09-Aug-12 09-Aug-12 19-Mar-13 19-Mar-13 182
A55800 Plaster Works 7 09-Aug-12 16-Aug-12 05-Jan-13 12-Jan-13 120
A55820 1st Coat Paint 7 28-Aug-12 04-Sep-12 21-Jan-13 29-Jan-13 120
Fisrt StaFisrt Stage Finishes 52 11-Aug-12 11-Oct-12 20-Mar-13 25-Apr-13 162
A55840 Installation of Doors 2 11-Aug-12 12-Aug-12 20-Mar-13 21-Mar-13 182
A55860 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A55910 Epoxy Paint Works 2 10-Oct-12 11-Oct-12 20-Mar-13 21-Mar-13 132
Second SSecond Stage Finishes 5 13-Oct-12 17-Oct-12 21-Apr-13 25-Apr-13 157
A55830 Final Coat Paint 5 13-Oct-12 17-Oct-12 21-Apr-13 25-Apr-13 157
Final StaFinal Stage Finishes 2 18-Oct-12 20-Oct-12 27-Apr-13 28-Apr-13 157
A55900 Installation of Sinages 2 18-Oct-12 20-Oct-12 27-Apr-13 28-Apr-13 157
MEP WorkMEP Works 58 01-Aug-12 09-Oct-12 26-Dec-12 24-Apr-13 163
HVACHVAC 58 01-Aug-12 09-Oct-12 30-Jan-13 05-Mar-13 120
A55930 Duct Installation & Insulation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171
A55940 Chilled Water Pipe Installation & Insulation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171
A55950 Condensate Pipe Installation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171
A56060 Installation of AHU 30 05-Sep-12 09-Oct-12 30-Jan-13 05-Mar-13 120
ElectricalElectrical 34 01-Aug-12 11-Sep-12 26-Dec-12 05-Mar-13 144
A55870 Install Conduits in Wall 7 01-Aug-12 08-Aug-12 26-Dec-12 03-Jan-13 120
A55880 Wiring for Lighting & Power 7 18-Aug-12 27-Aug-12 13-Jan-13 20-Jan-13 120
A55890 Installation of Lighting Fittings 6 05-Sep-12 11-Sep-12 27-Feb-13 05-Mar-13 144
PlumbingPlumbing 30 01-Aug-12 06-Sep-12 20-Feb-13 05-Mar-13 148
A56020 H/L Drainage Pipes Installation 7 01-Aug-12 08-Aug-12 20-Feb-13 27-Feb-13 166
A56030 H/L Hot&Cold Water Pipe Installation 7 01-Aug-12 08-Aug-12 20-Feb-13 27-Feb-13 166
A56040 Drainage&Water Pipes Testing 5 09-Aug-12 14-Aug-12 28-Feb-13 05-Mar-13 166
A56050 Floor Drain Fixning 2 05-Sep-12 06-Sep-12 04-Mar-13 05-Mar-13 148
Fire FighFire Fighting 22 01-Aug-12 28-Aug-12 16-Feb-13 24-Apr-13 199
A56010 Fire Fighting Pipe 7 01-Aug-12 08-Aug-12 16-Feb-13 23-Feb-13 162
A56000 Hydro Static Test for Pipes 4 09-Aug-12 13-Aug-12 24-Feb-13 27-Feb-13 162
A55990 Sprinkler Fixing 5 14-Aug-12 21-Aug-12 28-Feb-13 05-Mar-13 162
A55980 Installation of Fire Extingusher&Blanket 2 22-Aug-12 23-Aug-12 23-Apr-13 24-Apr-13 203
A55920 Fire Alarm Devices 6 22-Aug-12 28-Aug-12 13-Mar-13 19-Mar-13 168
BMS RoomBMS Room 98 23-Jul-12 19-Nov-12 20-Nov-12 28-Apr-13 134
FinishingFinishing Works 98 23-Jul-12 19-Nov-12 20-Nov-12 28-Apr-13 134
Wet WorWet Works 11 23-Jul-12 04-Aug-12 20-Nov-12 18-Mar-13 186
A58510 Block Works 2 23-Jul-12 24-Jul-12 20-Nov-12 21-Nov-12 98
A58470 Installation of Doors& Windows Sub-frame 1 28-Jul-12 28-Jul-12 18-Mar-13 18-Mar-13 192
A58460 Plaster Works 2 28-Jul-12 29-Jul-12 25-Nov-12 26-Nov-12 98
A58480 1st Coat Paint 3 01-Aug-12 04-Aug-12 29-Nov-12 03-Dec-12 98
Fisrt StaFisrt Stage Finishes 22 16-Oct-12 12-Nov-12 14-Feb-13 18-Mar-13 104
A58630 Installation of Suspended Ceiling Grid 7 16-Oct-12 23-Oct-12 14-Feb-13 21-Feb-13 98
A58640 Suspended Ceiling Tiles 7 24-Oct-12 03-Nov-12 23-Feb-13 02-Mar-13 98
A58660 Screed Works 4 04-Nov-12 07-Nov-12 10-Mar-13 13-Mar-13 104
A58650 Floor Tiles Work 4 08-Nov-12 12-Nov-12 14-Mar-13 18-Mar-13 104
Second SSecond Stage Finishes 3 13-Nov-12 17-Nov-12 19-Mar-13 25-Apr-13 134
A58490 Final Coat Paint 3 13-Nov-12 17-Nov-12 23-Apr-13 25-Apr-13 134
A58500 Installation of Doors 3 13-Nov-12 17-Nov-12 19-Mar-13 21-Mar-13 104
A58520 Doors Ironmongery 3 13-Nov-12 17-Nov-12 23-Apr-13 25-Apr-13 134
Final StaFinal Stage Finishes 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134
A58560 Installation of Sinages 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134
MEP WorkMEP Works 92 25-Jul-12 13-Nov-12 22-Nov-12 24-Apr-13 135
HVACHVAC 86 25-Jul-12 06-Nov-12 07-Feb-13 05-Mar-13 98
A58580 Chilled Water Pipe Installation & Insulation 3 25-Jul-12 28-Jul-12 07-Feb-13 10-Feb-13 161
A58590 Condensate Pipe Installation 3 25-Jul-12 28-Jul-12 07-Feb-13 10-Feb-13 161
A58600 FCU Installation 3 29-Jul-12 31-Jul-12 11-Feb-13 13-Feb-13 161
A58610 Air-Outlet Installation 3 04-Nov-12 06-Nov-12 03-Mar-13 05-Mar-13 98
ElectricalElectrical 85 25-Jul-12 05-Nov-12 22-Nov-12 05-Mar-13 99
A58530 Install Conduits in Wall 2 25-Jul-12 26-Jul-12 22-Nov-12 24-Nov-12 98
A58540 Wiring for Lighting & Power 2 30-Jul-12 31-Jul-12 27-Nov-12 28-Nov-12 98
A58710 Installation of BMS System 60 05-Aug-12 15-Oct-12 04-Dec-12 13-Feb-13 98
A58550 Installation of Lighting Fittings 2 04-Nov-12 05-Nov-12 04-Mar-13 05-Mar-13 99
PlumbingPlumbing 14 25-Jul-12 09-Aug-12 29-Jan-13 13-Feb-13 153
A58670 H/L Hot&Cold Water Pipe Installation 7 25-Jul-12 01-Aug-12 29-Jan-13 05-Feb-13 153
A58680 Water Pipes Testing 7 02-Aug-12 09-Aug-12 06-Feb-13 13-Feb-13 153
Fire FighFire Fighting 9 04-Nov-12 13-Nov-12 15-Apr-13 24-Apr-13 135
A58570 Fire Alarm Devices 2 04-Nov-12 05-Nov-12 15-Apr-13 16-Apr-13 135
A58620 Installation of Fire Extingusher&Blanket 7 06-Nov-12 13-Nov-12 17-Apr-13 24-Apr-13 135
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Installation of Fire Fighting Pump
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Installation of Transfer Pump
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Installation of Fire Fighting Pump
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Installation of AHU
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Final Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of BMS System
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 57 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Server RooServer Room 131 23-Jul-12 29-Dec-12 07-Oct-12 28-Apr-13 101
FinishingFinishing Works 131 23-Jul-12 29-Dec-12 07-Oct-12 28-Apr-13 101
Wet WorWet Works 28 23-Jul-12 26-Aug-12 07-Oct-12 19-Mar-13 170
A57370 Block Works 6 23-Jul-12 29-Jul-12 07-Oct-12 13-Oct-12 63
A57300 Installation of Doors& Windows Sub-frame 2 04-Aug-12 05-Aug-12 18-Mar-13 19-Mar-13 186
A57290 Plaster Works 10 04-Aug-12 14-Aug-12 18-Oct-12 31-Oct-12 63
A57310 1st Coat Paint 8 15-Aug-12 26-Aug-12 01-Nov-12 10-Nov-12 63
Fisrt StaFisrt Stage Finishes 14 04-Dec-12 19-Dec-12 17-Feb-13 19-Mar-13 75
A57320 Installation of Suspended Ceiling Grid 5 04-Dec-12 09-Dec-12 17-Feb-13 21-Feb-13 62
A57330 Suspended Ceiling Tiles 5 10-Dec-12 15-Dec-12 23-Feb-13 27-Feb-13 62
A57570 Screed Works 2 16-Dec-12 17-Dec-12 16-Mar-13 17-Mar-13 75
A57350 Floor Tiles Work 2 18-Dec-12 19-Dec-12 18-Mar-13 19-Mar-13 75
Second SSecond Stage Finishes 6 20-Dec-12 26-Dec-12 20-Mar-13 28-Apr-13 103
A57360 Installation of Windows&Doors 2 20-Dec-12 22-Dec-12 20-Mar-13 21-Mar-13 75
A57380 Doors Ironmongery 2 20-Dec-12 22-Dec-12 27-Apr-13 28-Apr-13 107
A57340 Final Coat Paint 3 24-Dec-12 26-Dec-12 23-Apr-13 25-Apr-13 101
Final StaFinal Stage Finishes 2 27-Dec-12 29-Dec-12 27-Apr-13 28-Apr-13 101
A57560 Installation of Sinages 2 27-Dec-12 29-Dec-12 27-Apr-13 28-Apr-13 101
MEP WorkMEP Works 120 30-Jul-12 23-Dec-12 14-Oct-12 22-Apr-13 101
HVACHVAC 116 30-Jul-12 18-Dec-12 04-Feb-13 05-Mar-13 64
A57410 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 04-Feb-13 11-Feb-13 154
A57420 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 04-Feb-13 11-Feb-13 154
A57430 FCU Installation 4 07-Aug-12 11-Aug-12 12-Feb-13 16-Feb-13 154
A57440 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
ElectricalElectrical 118 30-Jul-12 20-Dec-12 14-Oct-12 05-Mar-13 62
A57450 Install Conduits in Wall 4 30-Jul-12 02-Aug-12 14-Oct-12 17-Oct-12 63
A57470 Wiring for Lighting & Power 4 15-Aug-12 21-Aug-12 12-Feb-13 16-Feb-13 147
A105450 Installation of Server System 80 28-Aug-12 03-Dec-12 11-Nov-12 16-Feb-13 62
A57510 Installation of Lighting Fittings 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62
Fire FighFire Fighting 7 16-Dec-12 23-Dec-12 15-Apr-13 22-Apr-13 101
A57580 Fire Alarm Devices 7 16-Dec-12 23-Dec-12 15-Apr-13 22-Apr-13 101
Sub-StatioSub-Station 2 129 23-Jul-12 26-Dec-12 06-Jan-13 28-Apr-13 103
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 30 23-Jul-12 28-Aug-12 06-Jan-13 19-Mar-13 168
A56120 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136
A56080 Installation of Doors& Windows Sub-frame 2 05-Aug-12 06-Aug-12 18-Mar-13 19-Mar-13 185
A56070 Plaster Works 5 05-Aug-12 09-Aug-12 20-Jan-13 26-Jan-13 137
A56090 1st Coat Paint 9 16-Aug-12 28-Aug-12 02-Feb-13 11-Feb-13 137
Fisrt StaFisrt Stage Finishes 34 07-Aug-12 17-Sep-12 28-Feb-13 25-Apr-13 183
A56110 Installation of Doors 2 07-Aug-12 08-Aug-12 20-Mar-13 21-Mar-13 185
A56130 Doors Ironmongery 2 07-Aug-12 08-Aug-12 24-Apr-13 25-Apr-13 215
A56180 Epoxy Paint Works 3 15-Sep-12 17-Sep-12 28-Feb-13 03-Mar-13 137
Second SSecond Stage Finishes 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137
A56100 Final Coat Paint 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A56170 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71
HVACHVAC 31 30-Jul-12 05-Sep-12 20-Feb-13 27-Feb-13 144
A56200 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168
A56240 Air-Outlet Installation 7 29-Aug-12 05-Sep-12 20-Feb-13 27-Feb-13 144
ElectricalElectrical 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71
LightLight 29 30-Jul-12 03-Sep-12 14-Jan-13 27-Feb-13 146
A56140 Install Conduits in Wall 5 30-Jul-12 04-Aug-12 14-Jan-13 19-Jan-13 137
A56150 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 27-Jan-13 31-Jan-13 137
A56160 Installation of Lighting Fittings 5 29-Aug-12 03-Sep-12 23-Feb-13 27-Feb-13 146
TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71
A105260 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71
A105250 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87
A105270 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
A105280 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
A105290 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A105310 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A105300 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
A105320 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
Fire FighFire Fighting 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137
A56190 Fire Alarm Devices 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137
Sub-StatioSub-Station 3 129 23-Jul-12 26-Dec-12 06-Jan-13 28-Apr-13 103
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161
Wet WorWet Works 30 23-Jul-12 28-Aug-12 06-Jan-13 19-Mar-13 168
A56300 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136
A56260 Installation of Doors& Windows Sub-frame 2 05-Aug-12 06-Aug-12 18-Mar-13 19-Mar-13 185
A56250 Plaster Works 5 05-Aug-12 09-Aug-12 20-Jan-13 26-Jan-13 137
A56270 1st Coat Paint 9 16-Aug-12 28-Aug-12 02-Feb-13 11-Feb-13 137
Fisrt StaFisrt Stage Finishes 34 07-Aug-12 17-Sep-12 28-Feb-13 25-Apr-13 183
A56290 Installation of Doors 2 07-Aug-12 08-Aug-12 20-Mar-13 21-Mar-13 185
A56310 Doors Ironmongery 2 07-Aug-12 08-Aug-12 24-Apr-13 25-Apr-13 215
A56360 Epoxy Paint Works 3 15-Sep-12 17-Sep-12 28-Feb-13 03-Mar-13 137
Second SSecond Stage Finishes 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137
A56280 Final Coat Paint 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A56350 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71
HVACHVAC 31 30-Jul-12 05-Sep-12 20-Feb-13 27-Feb-13 144
A56380 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168
A56390 Air-Outlet Installation 7 29-Aug-12 05-Sep-12 20-Feb-13 27-Feb-13 144
ElectricalElectrical 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71
LightLight 29 30-Jul-12 03-Sep-12 14-Jan-13 27-Feb-13 146
A56320 Install Conduits in Wall 5 30-Jul-12 04-Aug-12 14-Jan-13 19-Jan-13 137
A56330 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 27-Jan-13 31-Jan-13 137
A56340 Installation of Lighting Fittings 5 29-Aug-12 03-Sep-12 23-Feb-13 27-Feb-13 146
TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71
A105340 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71
A105330 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87
A105350 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
A105360 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71
A105370 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A105390 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71
A105380 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
A105400 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71
Fire FighFire Fighting 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137
A56370 Fire Alarm Devices 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137
Genset RoGenset Rooms 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161
Wet WorWet Works 29 23-Jul-12 27-Aug-12 25-Dec-12 19-Mar-13 169
A57200 Block Works 4 23-Jul-12 26-Jul-12 25-Dec-12 29-Dec-12 127
A57160 Installation of Doors& Windows Sub-frame 1 01-Aug-12 01-Aug-12 19-Mar-13 19-Mar-13 189
A57150 Plaster Works 8 01-Aug-12 09-Aug-12 05-Jan-13 13-Jan-13 127
A57170 1st Coat Paint 9 15-Aug-12 27-Aug-12 19-Jan-13 29-Jan-13 127
Fisrt StaFisrt Stage Finishes 52 02-Aug-12 03-Oct-12 20-Mar-13 25-Apr-13 169
A57190 Installation of Doors 2 02-Aug-12 04-Aug-12 20-Mar-13 21-Mar-13 189
A57210 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
A57260 Epoxy Paint Works 2 02-Oct-12 03-Oct-12 20-Mar-13 21-Mar-13 139
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Server System
Installation of Lighting Fittings
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Install Cable Tray & Trunking
Installation of Transformer
Install of LV Cables
Install of MV Cables
Test of LV Cables
Test of MV Cables
Termination of LV Cables
Termination of MV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Install Cable Tray & Trunking
Installation of Transformer
Install of LV Cables
Install of MV Cables
Test of LV Cables
Test of MV Cables
Termination of LV Cables
Termination of MV Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 58 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Second SSecond Stage Finishes 4 04-Oct-12 08-Oct-12 22-Apr-13 25-Apr-13 165
A57180 Final Coat Paint 4 04-Oct-12 08-Oct-12 22-Apr-13 25-Apr-13 165
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A57250 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 55 28-Jul-12 01-Oct-12 30-Dec-12 19-Mar-13 139
HVACHVAC 7 28-Jul-12 04-Aug-12 26-Feb-13 05-Mar-13 175
A57280 Duct Installation & Insulation 7 28-Jul-12 04-Aug-12 26-Feb-13 05-Mar-13 175
ElectricalElectrical 55 28-Jul-12 01-Oct-12 30-Dec-12 05-Mar-13 127
A57220 Install Conduits in Wall 4 28-Jul-12 31-Jul-12 30-Dec-12 03-Jan-13 127
A57230 Wiring for Lighting & Power 4 11-Aug-12 14-Aug-12 14-Jan-13 17-Jan-13 127
A57240 Installation of Lighting Fittings 7 28-Aug-12 04-Sep-12 26-Feb-13 05-Mar-13 150
A105420 Installation of Generator 30 28-Aug-12 01-Oct-12 30-Jan-13 05-Mar-13 127
Fire FighFire Fighting 7 28-Aug-12 04-Sep-12 12-Mar-13 19-Mar-13 162
A57270 Fire Alarm Devices 7 28-Aug-12 04-Sep-12 12-Mar-13 19-Mar-13 162
CBS RoomCBS Room 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161
Wet WorWet Works 25 23-Jul-12 22-Aug-12 09-Jan-13 19-Mar-13 173
A57060 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139
A57020 Installation of Doors& Windows Sub-frame 2 01-Aug-12 02-Aug-12 18-Mar-13 19-Mar-13 188
A57010 Plaster Works 6 01-Aug-12 07-Aug-12 29-Jan-13 04-Feb-13 147
A57030 1st Coat Paint 6 14-Aug-12 22-Aug-12 11-Feb-13 17-Feb-13 147
Fisrt StaFisrt Stage Finishes 36 04-Aug-12 16-Sep-12 20-Mar-13 25-Apr-13 184
A57050 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188
A57120 Epoxy Paint Works 2 09-Sep-12 10-Sep-12 20-Mar-13 21-Mar-13 159
A57070 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184
Second SSecond Stage Finishes 2 11-Sep-12 12-Sep-12 24-Apr-13 25-Apr-13 187
A57040 Final Coat Paint 2 11-Sep-12 12-Sep-12 24-Apr-13 25-Apr-13 187
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
A57110 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161
MEP WorkMEP Works 36 26-Jul-12 08-Sep-12 22-Jan-13 19-Mar-13 159
HVACHVAC 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
A57140 Air-Outlet Installation 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154
ElectricalElectrical 36 26-Jul-12 08-Sep-12 22-Jan-13 05-Mar-13 147
A57080 Install Conduits in Wall 5 26-Jul-12 31-Jul-12 22-Jan-13 28-Jan-13 147
A57090 Wiring for Lighting & Power 5 08-Aug-12 13-Aug-12 05-Feb-13 10-Feb-13 147
A57100 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156
A105430 Instalaltion of Centeral Bettery System 14 23-Aug-12 08-Sep-12 18-Feb-13 05-Mar-13 147
Fire FighFire Fighting 5 23-Aug-12 28-Aug-12 14-Mar-13 19-Mar-13 168
A57130 Fire Alarm Devices 5 23-Aug-12 28-Aug-12 14-Mar-13 19-Mar-13 168
CCTV ConCCTV Control Room 132 23-Jul-12 30-Dec-12 04-Oct-12 28-Apr-13 100
FinishingFinishing Works 132 23-Jul-12 30-Dec-12 04-Oct-12 28-Apr-13 100
Wet WorWet Works 29 23-Jul-12 27-Aug-12 04-Oct-12 19-Mar-13 169
A57670 Block Works 5 23-Jul-12 28-Jul-12 04-Oct-12 09-Oct-12 61
A57600 Installation of Doors& Windows Sub-frame 2 06-Aug-12 07-Aug-12 18-Mar-13 19-Mar-13 184
A57590 Plaster Works 10 06-Aug-12 16-Aug-12 18-Oct-12 31-Oct-12 61
A57610 1st Coat Paint 7 18-Aug-12 27-Aug-12 01-Nov-12 08-Nov-12 61
Fisrt StaFisrt Stage Finishes 18 04-Dec-12 24-Dec-12 16-Feb-13 19-Mar-13 71
A57620 Installation of Suspended Ceiling Grid 4 04-Dec-12 08-Dec-12 16-Feb-13 19-Feb-13 61
A57630 Suspended Ceiling Tiles 5 09-Dec-12 13-Dec-12 20-Feb-13 25-Feb-13 61
A57650 Epoxy Paint Works 2 23-Dec-12 24-Dec-12 18-Mar-13 19-Mar-13 71
Second SSecond Stage Finishes 3 25-Dec-12 27-Dec-12 20-Mar-13 28-Apr-13 102
A57660 Installation of Windows&Doors 2 25-Dec-12 26-Dec-12 20-Mar-13 21-Mar-13 71
A57680 Doors Ironmongery 2 25-Dec-12 26-Dec-12 27-Apr-13 28-Apr-13 103
A57640 Final Coat Paint 3 25-Dec-12 27-Dec-12 23-Apr-13 25-Apr-13 100
Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
A57860 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
MEP WorkMEP Works 120 29-Jul-12 22-Dec-12 10-Oct-12 17-Mar-13 71
HVACHVAC 7 28-Aug-12 04-Sep-12 07-Feb-13 14-Feb-13 134
A57730 FCU Installation 7 28-Aug-12 04-Sep-12 07-Feb-13 14-Feb-13 134
ElectricalElectrical 120 29-Jul-12 22-Dec-12 10-Oct-12 05-Mar-13 61
A57750 Install Conduits in Wall 7 29-Jul-12 05-Aug-12 10-Oct-12 17-Oct-12 61
A57770 Wiring for Lighting & Power 7 18-Aug-12 27-Aug-12 07-Feb-13 14-Feb-13 141
A124640 Installation of UPS 15 28-Aug-12 13-Sep-12 29-Jan-13 14-Feb-13 126
A57820 Installation of CCTV System 80 28-Aug-12 03-Dec-12 10-Nov-12 14-Feb-13 61
A57810 Installation of Lighting Fittings 7 15-Dec-12 22-Dec-12 26-Feb-13 05-Mar-13 61
Fire FighFire Fighting 7 15-Dec-12 22-Dec-12 10-Mar-13 17-Mar-13 71
A57880 Fire Alarm Devices 7 15-Dec-12 22-Dec-12 10-Mar-13 17-Mar-13 71
StaircaseStaircase 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152
Stairs 1Stairs 1 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152
A109450 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132
A109460 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132
A109470 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109480 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109490 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132
A109500 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152
Stairs 2Stairs 2 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152
A109510 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132
A109520 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132
A109530 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109540 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109550 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132
A109560 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152
Stairs 3Stairs 3 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152
A109570 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132
A109580 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132
A109590 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109600 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132
A109610 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132
A109620 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152
Ground FloorGround Floor 323 16-Aug-12 08-Sep-13 24-Oct-12 02-Oct-13 21
Public AreaPublic Area 323 16-Aug-12 08-Sep-13 24-Oct-12 02-Oct-13 21
ParkingParking 69 25-Dec-12 17-Mar-13 04-Feb-13 28-Apr-13 36
FinishingFinishing Works 69 25-Dec-12 17-Mar-13 18-Feb-13 28-Apr-13 36
Wet WorWet Works 24 25-Dec-12 22-Jan-13 18-Feb-13 03-Mar-13 33
A66730 Plaster Works 5 25-Dec-12 30-Dec-12 18-Feb-13 23-Feb-13 45
A66740 1st Coat Paint 7 15-Jan-13 22-Jan-13 24-Feb-13 03-Mar-13 33
Traffic DTraffic Deck Coating 45 23-Jan-13 17-Mar-13 04-Mar-13 28-Apr-13 36
A116040 Installation of Kerbs 8 23-Jan-13 02-Feb-13 04-Mar-13 12-Mar-13 33
A116050 Installation of Interlocking Tiles 8 03-Feb-13 11-Feb-13 13-Mar-13 21-Mar-13 33
A66670 Surface Preparation (including Grinding & Repairing) 8 12-Feb-13 20-Feb-13 23-Mar-13 31-Mar-13 33
A66680 Application of 1st Coat 5 18-Feb-13 23-Feb-13 01-Apr-13 06-Apr-13 36
A66720 Application of Final Coat 5 24-Feb-13 28-Feb-13 07-Apr-13 11-Apr-13 36
A66700 Road Marking & Arrows 7 02-Mar-13 09-Mar-13 13-Apr-13 20-Apr-13 36
A116060 Installation of Speed Hump 7 10-Mar-13 17-Mar-13 21-Apr-13 28-Apr-13 36
Final StaFinal Stage Finishes 7 10-Mar-13 17-Mar-13 21-Apr-13 28-Apr-13 36
A66750 Final Coat Paint 5 10-Mar-13 14-Mar-13 21-Apr-13 25-Apr-13 36
A66770 Installation of Sinages 2 16-Mar-13 17-Mar-13 27-Apr-13 28-Apr-13 36
MEP WorkMEP Works 17 25-Dec-12 14-Jan-13 04-Feb-13 23-Feb-13 33
HVACHVAC 17 25-Dec-12 14-Jan-13 04-Feb-13 23-Feb-13 33
A66900 Duct Installation & Insulation 7 25-Dec-12 02-Jan-13 04-Feb-13 11-Feb-13 33
A66870 Installation of Plenum Boxes 10 03-Jan-13 14-Jan-13 12-Feb-13 23-Feb-13 33
ElectricalElectrical 14 25-Dec-12 10-Jan-13 07-Feb-13 23-Feb-13 36
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Generator
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Instalaltion of Centeral Bettery System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of UPS
Installation of CCTV System
Installation of Lighting Fittings
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Installation of Plenum Boxes
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 59 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A116070 Instalaltion of Cable Trays 5 25-Dec-12 30-Dec-12 07-Feb-13 12-Feb-13 36
A116080 Instalaltion of Bus Bars 7 25-Dec-12 02-Jan-13 11-Feb-13 18-Feb-13 39
A116090 Cable Pulling 5 31-Dec-12 06-Jan-13 13-Feb-13 18-Feb-13 36
A66760 Installation of Lighting Fittings 4 07-Jan-13 10-Jan-13 19-Feb-13 23-Feb-13 36
PlumbingPlumbing 7 25-Dec-12 02-Jan-13 16-Feb-13 23-Feb-13 43
A66840 H/L Hot&Cold Water Pipe Installation 4 25-Dec-12 29-Dec-12 16-Feb-13 19-Feb-13 43
A66860 Floor Drain Fixning 4 25-Dec-12 29-Dec-12 19-Feb-13 23-Feb-13 46
A66880 H/L Drainage Pipes Installation 4 25-Dec-12 29-Dec-12 16-Feb-13 19-Feb-13 43
A66850 Water Pipes Testing 3 30-Dec-12 02-Jan-13 20-Feb-13 23-Feb-13 43
A66890 Drainage&Water Pipes Testing 3 30-Dec-12 02-Jan-13 20-Feb-13 23-Feb-13 43
Fire FighFire Fighting 14 25-Dec-12 10-Jan-13 07-Feb-13 23-Feb-13 36
A66830 Fire Fighting Pipe 4 25-Dec-12 29-Dec-12 07-Feb-13 11-Feb-13 36
A66820 Hydro Static Test for Pipes 4 30-Dec-12 03-Jan-13 12-Feb-13 16-Feb-13 36
A66810 Sprinkler Fixing 4 05-Jan-13 08-Jan-13 17-Feb-13 20-Feb-13 36
A66780 Fire Alarm Devices 2 09-Jan-13 10-Jan-13 21-Feb-13 23-Feb-13 36
RampRamp 67 31-Dec-12 20-Mar-13 03-Mar-13 28-Apr-13 33
A116100 Install Handrail 7 31-Dec-12 08-Jan-13 03-Mar-13 10-Mar-13 51
A116110 1st Coat Paint 10 12-Jan-13 22-Jan-13 11-Mar-13 21-Mar-13 49
A116120 Surface Preparation (including Grinding & Repairing) 8 12-Feb-13 20-Feb-13 23-Mar-13 31-Mar-13 33
A116130 Application of 1st Coat 5 21-Feb-13 26-Feb-13 01-Apr-13 06-Apr-13 33
A116140 Application of Final Coat 5 27-Feb-13 04-Mar-13 07-Apr-13 11-Apr-13 33
A116150 Road Marking & Arrows 7 05-Mar-13 12-Mar-13 13-Apr-13 20-Apr-13 33
A116160 Final Coat Paint 7 13-Mar-13 20-Mar-13 21-Apr-13 28-Apr-13 33
Lift LobbyLift Lobby - Corridor 323 16-Aug-12 08-Sep-13 02-Jan-13 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 02-Jan-13 02-Oct-13 21
Wet WorWet Works 40 16-Aug-12 03-Oct-12 02-Jan-13 25-Apr-13 169
A66430 Block Works 7 16-Aug-12 26-Aug-12 02-Jan-13 09-Jan-13 112
A66360 Installation of Doors& Windows Sub-frame 2 04-Sep-12 05-Sep-12 24-Apr-13 25-Apr-13 193
A66350 Plaster Works 7 04-Sep-12 11-Sep-12 19-Jan-13 27-Jan-13 112
A66380 Installation of Suspended Ceiling Grid 7 19-Sep-12 26-Sep-12 04-Feb-13 11-Feb-13 112
A66370 1st Coat Paint 6 27-Sep-12 03-Oct-12 12-Feb-13 18-Feb-13 112
Fisrt StaFisrt Stage Finishes 16 04-Oct-12 22-Oct-12 19-Feb-13 13-Apr-13 142
A66390 Suspended Ceiling Tiles 6 04-Oct-12 10-Oct-12 19-Feb-13 25-Feb-13 112
A66610 Screed Works 3 11-Oct-12 14-Oct-12 02-Apr-13 04-Apr-13 142
A66410 Floor Tiles Work 7 15-Oct-12 22-Oct-12 06-Apr-13 13-Apr-13 142
Second SSecond Stage Finishes 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153
A66420 Installation of Windows&Doors 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153
A66440 Doors Ironmongery 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153
Final StaFinal Stage Finishes 267 23-Oct-12 08-Sep-13 14-Apr-13 02-Oct-13 21
A66400 Final Coat Paint 6 23-Oct-12 31-Oct-12 14-Apr-13 20-Apr-13 142
A66600 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A66630 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A66450 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 48 27-Aug-12 21-Oct-12 10-Jan-13 20-Apr-13 149
HVACHVAC 46 27-Aug-12 18-Oct-12 22-Jan-13 05-Mar-13 112
A66640 Chilled Water Pipe Installation & Insulation 5 27-Aug-12 01-Sep-12 22-Jan-13 28-Jan-13 122
A66650 Condensate Pipe Installation 5 27-Aug-12 01-Sep-12 22-Jan-13 28-Jan-13 122
A66460 Duct Installation & Insulation 7 27-Aug-12 03-Sep-12 18-Feb-13 25-Feb-13 144
A66660 FCU Installation 5 02-Sep-12 06-Sep-12 29-Jan-13 03-Feb-13 122
A66470 Air-Outlet Installation 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112
ElectricalElectrical 46 27-Aug-12 18-Oct-12 10-Jan-13 05-Mar-13 112
A66480 Install Conduits in Wall 7 27-Aug-12 03-Sep-12 10-Jan-13 17-Jan-13 112
A66490 Install Cable Trays & Trunking 7 27-Aug-12 03-Sep-12 16-Jan-13 23-Jan-13 117
A66520 Cable Laying for Low Current System 7 04-Sep-12 11-Sep-12 04-Feb-13 11-Feb-13 125
A66530 Cable Laying for Power 7 04-Sep-12 11-Sep-12 04-Feb-13 11-Feb-13 125
A66500 Wiring for Lighting & Power 6 12-Sep-12 18-Sep-12 28-Jan-13 03-Feb-13 112
A66510 Wiring for Low Current System 6 12-Sep-12 18-Sep-12 28-Jan-13 03-Feb-13 112
A66550 Installation of Sockets 5 11-Oct-12 16-Oct-12 28-Feb-13 05-Mar-13 114
A66540 Installation of Lighting Fittings 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112
Fire FighFire Fighting 48 27-Aug-12 21-Oct-12 20-Jan-13 20-Apr-13 149
A66590 Fire Fighting Pipe 7 27-Aug-12 03-Sep-12 20-Jan-13 28-Jan-13 120
A66580 Hydro Static Test for Pipes 5 04-Sep-12 09-Sep-12 29-Jan-13 03-Feb-13 120
A66570 Sprinkler Fixing 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112
A66620 Fire Alarm Devices 7 11-Oct-12 18-Oct-12 06-Apr-13 13-Apr-13 145
A66560 Installation of Fire Extingusher&Blanket 2 20-Oct-12 21-Oct-12 18-Apr-13 20-Apr-13 149
Kitchen ArKitchen Area 323 16-Aug-12 08-Sep-13 18-Nov-12 02-Oct-13 21
KitchenKitchen 96 31-Oct-12 24-Feb-13 18-Nov-12 28-Apr-13 54
FinishingFinishing Works 61 13-Dec-12 24-Feb-13 30-Dec-12 28-Apr-13 54
Wet WoWet Works 32 13-Dec-12 20-Jan-13 30-Dec-12 20-Apr-13 76
A61270 Block Works 10 13-Dec-12 24-Dec-12 30-Dec-12 10-Jan-13 14
A61230 Installation of Doors& Windows Sub-frame 3 03-Jan-13 06-Jan-13 17-Apr-13 20-Apr-13 88
A61220 Plaster Works 10 03-Jan-13 14-Jan-13 20-Jan-13 31-Jan-13 14
A61510 Wall Tiles Work 5 15-Jan-13 20-Jan-13 02-Feb-13 06-Feb-13 14
Fisrt StaFisrt Stage Finishes 4 21-Jan-13 26-Jan-13 07-Feb-13 11-Feb-13 14
A61500 Screed Works 4 21-Jan-13 26-Jan-13 07-Feb-13 11-Feb-13 14
SecondSecond Stage Finishes 18 27-Jan-13 16-Feb-13 12-Feb-13 20-Apr-13 54
A61540 Installation of Suspended Ceiling Grid 9 27-Jan-13 05-Feb-13 12-Feb-13 21-Feb-13 14
A61530 Suspended Ceiling Tiles 7 02-Feb-13 09-Feb-13 18-Feb-13 25-Feb-13 14
A61520 Floor Tiles Work 6 10-Feb-13 16-Feb-13 14-Apr-13 20-Apr-13 54
Final StFinal Stage Finishes 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54
A61240 Final Coat Paint 2 18-Feb-13 19-Feb-13 24-Apr-13 25-Apr-13 56
A61260 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54
A61280 Doors Ironmongery 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54
A61490 Installation of Sinages 2 23-Feb-13 24-Feb-13 27-Apr-13 28-Apr-13 54
MEP WoMEP Works 90 31-Oct-12 17-Feb-13 18-Nov-12 24-Apr-13 57
HVACHVAC 45 25-Dec-12 17-Feb-13 22-Jan-13 05-Mar-13 14
A61290 Duct Installation & Insulation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23
A61300 Chilled Water Pipe Installation & Insulation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23
A61310 Condensate Pipe Installation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23
A61320 FCU Installation 7 07-Jan-13 14-Jan-13 04-Feb-13 11-Feb-13 23
A61330 Air-Outlet Installation 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14
ElectricElectrical 50 19-Dec-12 17-Feb-13 12-Jan-13 05-Mar-13 14
A61340 Install Conduits in Wall 7 19-Dec-12 26-Dec-12 12-Jan-13 19-Jan-13 19
A61350 Wiring for Lighting & Power 7 15-Jan-13 22-Jan-13 04-Feb-13 11-Feb-13 16
A61360 Installation of Lighting Fittings 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14
PlumbinPlumbing 27 25-Dec-12 27-Jan-13 12-Jan-13 05-Mar-13 32
A61370 Drainge Pipes in Wall 7 25-Dec-12 02-Jan-13 12-Jan-13 19-Jan-13 14
A61380 H/L Drainage Pipes Installation 7 25-Dec-12 02-Jan-13 31-Jan-13 07-Feb-13 30
A61390 H/L Hot&Cold Water Pipe Installation 7 25-Dec-12 02-Jan-13 31-Jan-13 07-Feb-13 30
A61440 Water Pipes in Wall 7 25-Dec-12 02-Jan-13 12-Jan-13 19-Jan-13 14
A61400 Drainage&Water Pipes Testing 3 03-Jan-13 06-Jan-13 09-Feb-13 11-Feb-13 30
A61420 Floor Drain Fixning 3 23-Jan-13 27-Jan-13 03-Mar-13 05-Mar-13 32
Fire FigFire Fighting 45 25-Dec-12 17-Feb-13 30-Jan-13 24-Apr-13 57
A61480 Fire Fighting Pipe 7 25-Dec-12 02-Jan-13 30-Jan-13 06-Feb-13 29
A61470 Hydro Static Test for Pipes 4 03-Jan-13 07-Jan-13 07-Feb-13 11-Feb-13 29
A61450 Installation of Fire Extingusher&Blanket 2 16-Feb-13 17-Feb-13 23-Apr-13 24-Apr-13 57
A61460 Sprinkler Fixing 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14
A61550 Fire Alarm Devices 7 10-Feb-13 17-Feb-13 16-Apr-13 23-Apr-13 56
KitchenKitchen Equipments 75 31-Oct-12 30-Jan-13 18-Nov-12 16-Feb-13 14
A61430 Installation of Kitchen Equipments 75 31-Oct-12 30-Jan-13 18-Nov-12 16-Feb-13 14
Staff DininStaff Dining Area 323 16-Aug-12 08-Sep-13 10-Jan-13 02-Oct-13 21
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Instalaltion of Cable Trays
Instalaltion of Bus Bars
Cable Pulling
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Floor Drain Fixning
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Install Handrail
1st Coat Paint
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Carpets
Installation of Furnitur
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
Screed Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Floor Tiles Work
Final Coat Paint
Installation of Windows&Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Installation of Kitchen Equipments
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 60 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 10-Jan-13 02-Oct-13 21
Wet WoWet Works 35 16-Aug-12 27-Sep-12 10-Jan-13 04-Apr-13 156
A62750 Block Works 8 16-Aug-12 27-Aug-12 10-Jan-13 19-Jan-13 119
A62640 Installation of Doors& Windows Sub-frame 2 03-Sep-12 04-Sep-12 03-Apr-13 04-Apr-13 176
A62630 Plaster Works 8 03-Sep-12 11-Sep-12 27-Jan-13 04-Feb-13 119
A62660 Installation of Suspended Ceiling Grid 4 17-Sep-12 20-Sep-12 10-Feb-13 13-Feb-13 119
A62650 1st Coat Paint 6 22-Sep-12 27-Sep-12 14-Feb-13 20-Feb-13 119
Fisrt StaFisrt Stage Finishes 10 29-Sep-12 09-Oct-12 21-Feb-13 04-Apr-13 146
A62670 Suspended Ceiling Tiles 4 29-Sep-12 02-Oct-12 21-Feb-13 25-Feb-13 119
A63050 Screed Works 2 03-Oct-12 04-Oct-12 02-Mar-13 03-Mar-13 122
A62690 Floor Tiles Work 4 06-Oct-12 09-Oct-12 01-Apr-13 04-Apr-13 146
SecondSecond Stage Finishes 2 23-Oct-12 24-Oct-12 06-Apr-13 28-Apr-13 153
A62720 Installation of Windows&Doors 2 23-Oct-12 24-Oct-12 06-Apr-13 07-Apr-13 135
A62760 Doors Ironmongery 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153
Final StFinal Stage Finishes 258 05-Nov-12 08-Sep-13 16-Apr-13 02-Oct-13 21
A62680 Final Coat Paint 4 05-Nov-12 08-Nov-12 16-Apr-13 20-Apr-13 135
A63040 Installation of Sinages 7 10-Nov-12 18-Nov-12 21-Apr-13 28-Apr-13 135
A62770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WoMEP Works 57 28-Aug-12 04-Nov-12 20-Jan-13 20-Apr-13 139
HVACHVAC 37 28-Aug-12 09-Oct-12 31-Jan-13 05-Mar-13 120
A62780 Duct Installation & Insulation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128
A62790 Chilled Water Pipe Installation & Insulation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128
A62800 Condensate Pipe Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128
A62810 FCU Installation 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128
A62820 Air-Outlet Installation 6 03-Oct-12 09-Oct-12 27-Feb-13 05-Mar-13 120
ElectricElectrical 37 28-Aug-12 09-Oct-12 20-Jan-13 05-Mar-13 120
A62830 Install Conduits in Wall 5 28-Aug-12 02-Sep-12 20-Jan-13 26-Jan-13 119
A62840 Install Cable Trays & Trunking 5 28-Aug-12 02-Sep-12 28-Jan-13 02-Feb-13 125
A62870 Cable Laying for Low Current System 5 03-Sep-12 08-Sep-12 09-Feb-13 13-Feb-13 130
A62880 Cable Laying for Power 5 03-Sep-12 08-Sep-12 09-Feb-13 13-Feb-13 130
A62850 Wiring for Lighting & Power 4 12-Sep-12 16-Sep-12 05-Feb-13 09-Feb-13 119
A62860 Wiring for Low Current System 4 12-Sep-12 16-Sep-12 05-Feb-13 09-Feb-13 119
A62900 Installation of Sockets 4 03-Oct-12 07-Oct-12 02-Mar-13 05-Mar-13 122
A62890 Installation of Lighting Fittings 6 03-Oct-12 09-Oct-12 27-Feb-13 05-Mar-13 120
PlumbinPlumbing 57 28-Aug-12 04-Nov-12 21-Jan-13 15-Apr-13 135
A62910 Drainge Pipes in Wall 4 28-Aug-12 01-Sep-12 21-Jan-13 26-Jan-13 120
A62980 Water Pipes in Wall 4 28-Aug-12 01-Sep-12 21-Jan-13 26-Jan-13 120
A62920 H/L Drainage Pipes Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128
A62930 H/L Hot&Cold Water Pipe Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128
A62940 Drainage&Water Pipes Testing 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128
A62950 ElectricalWater Heater Installation 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128
A62960 Floor Drain Fixning 2 06-Oct-12 07-Oct-12 04-Mar-13 05-Mar-13 122
A62970 Installation of Sanitaryware 7 28-Oct-12 04-Nov-12 08-Apr-13 15-Apr-13 135
Fire FigFire Fighting 40 28-Aug-12 13-Oct-12 29-Jan-13 20-Apr-13 156
A63020 Fire Fighting Pipe 6 28-Aug-12 03-Sep-12 29-Jan-13 04-Feb-13 126
A63010 Hydro Static Test for Pipes 4 04-Sep-12 08-Sep-12 05-Feb-13 09-Feb-13 126
A63000 Sprinkler Fixing 7 03-Oct-12 10-Oct-12 26-Feb-13 05-Mar-13 119
A63100 Fire Alarm Devices 7 03-Oct-12 10-Oct-12 08-Apr-13 15-Apr-13 154
A62990 Installation of Fire Extingusher&Blanket 2 11-Oct-12 13-Oct-12 18-Apr-13 20-Apr-13 156
Lobby ToliLobby Toliets 81 16-Aug-12 24-Nov-12 31-Dec-12 28-Apr-13 130
FinishingFinishing Works 81 16-Aug-12 24-Nov-12 31-Dec-12 28-Apr-13 130
Wet WorWet Works 30 16-Aug-12 22-Sep-12 31-Dec-12 11-Apr-13 167
A65740 Block Works 9 16-Aug-12 28-Aug-12 31-Dec-12 10-Jan-13 111
A65680 Installation of Doors& Windows Sub-frame 3 03-Sep-12 05-Sep-12 09-Apr-13 11-Apr-13 181
A65670 Plaster Works 8 03-Sep-12 11-Sep-12 16-Jan-13 26-Jan-13 111
A65990 Wall Tiles Work (Wet Area) 9 12-Sep-12 22-Sep-12 27-Jan-13 05-Feb-13 111
Fisrt StaFisrt Stage Finishes 22 23-Sep-12 17-Oct-12 06-Feb-13 11-Apr-13 145
A65980 Screed Works 3 23-Sep-12 25-Sep-12 06-Feb-13 09-Feb-13 111
A65700 Water Proofing for Wet Area 4 26-Sep-12 30-Sep-12 10-Feb-13 13-Feb-13 111
A66020 Installation of Suspended Ceiling Grid (Wet Area) 5 01-Oct-12 06-Oct-12 14-Feb-13 19-Feb-13 111
A66010 Suspended Ceiling Tiles (Wet Area) 5 07-Oct-12 11-Oct-12 20-Feb-13 25-Feb-13 111
A66000 Floor Tiles Work (Wet Area) 5 13-Oct-12 17-Oct-12 07-Apr-13 11-Apr-13 145
Second SSecond Stage Finishes 21 23-Oct-12 19-Nov-12 13-Apr-13 28-Apr-13 134
A65710 Installation of Windows&Doors 3 23-Oct-12 28-Oct-12 13-Apr-13 15-Apr-13 141
A65750 Doors Ironmongery 3 23-Oct-12 28-Oct-12 25-Apr-13 28-Apr-13 152
A65960 Installation of Toliets Accessories 5 29-Oct-12 03-Nov-12 18-Apr-13 23-Apr-13 143
A65720 Installation of Mirrors 7 29-Oct-12 05-Nov-12 16-Apr-13 23-Apr-13 141
A65730 Installation of Vanity Counter 4 14-Nov-12 19-Nov-12 20-Apr-13 23-Apr-13 130
Final StaFinal Stage Finishes 4 20-Nov-12 24-Nov-12 24-Apr-13 28-Apr-13 130
A65690 Final Coat Paint 2 20-Nov-12 21-Nov-12 24-Apr-13 25-Apr-13 130
A65970 Installation of Sinages 2 22-Nov-12 24-Nov-12 27-Apr-13 28-Apr-13 130
MEP WorkMEP Works 53 29-Aug-12 31-Oct-12 12-Jan-13 23-Apr-13 145
HVACHVAC 45 29-Aug-12 20-Oct-12 06-Feb-13 05-Mar-13 111
A65760 Duct Installation & Insulation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65770 Chilled Water Pipe Installation & Insulation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65780 Condensate Pipe Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65790 FCU Installation 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132
A65800 Air-Outlet Installation 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111
ElectricalElectrical 43 29-Aug-12 17-Oct-12 12-Jan-13 05-Mar-13 113
A65810 Install Conduits in Wall 4 29-Aug-12 02-Sep-12 12-Jan-13 15-Jan-13 111
A65820 Wiring for Lighting & Power 4 12-Sep-12 16-Sep-12 10-Feb-13 13-Feb-13 123
A65830 Installation of Lighting Fittings 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113
PlumbingPlumbing 53 29-Aug-12 31-Oct-12 13-Jan-13 23-Apr-13 145
A65840 Drainge Pipes in Wall 3 29-Aug-12 01-Sep-12 13-Jan-13 15-Jan-13 112
A65910 Water Pipes in Wall 3 29-Aug-12 01-Sep-12 13-Jan-13 15-Jan-13 112
A65850 H/L Drainage Pipes Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65860 H/L Hot&Cold Water Pipe Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65880 ElectricalWater Heater Installation 2 03-Sep-12 04-Sep-12 12-Feb-13 13-Feb-13 133
A65870 Drainage&Water Pipes Testing 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132
A65890 Floor Drain Fixning 2 25-Sep-12 26-Sep-12 04-Mar-13 05-Mar-13 131
A65900 Installation of Sanitaryware 3 29-Oct-12 31-Oct-12 21-Apr-13 23-Apr-13 145
Fire FighFire Fighting 42 29-Aug-12 16-Oct-12 06-Feb-13 23-Apr-13 156
A65950 Fire Fighting Pipe 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132
A65940 Hydro Static Test for Pipes 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132
A65930 Sprinkler Fixing 3 13-Oct-12 15-Oct-12 03-Mar-13 05-Mar-13 115
A66030 Fire Alarm Devices 4 13-Oct-12 16-Oct-12 20-Apr-13 23-Apr-13 156
RestaurantRestaurant & Displayed Kitchen 323 16-Aug-12 08-Sep-13 15-Dec-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 15-Dec-12 02-Oct-13 21
Wet WorWet Works 46 16-Aug-12 10-Oct-12 15-Dec-12 07-Feb-13 97
A65380 Block Works 6 16-Aug-12 25-Aug-12 15-Dec-12 20-Dec-12 97
A65330 Plaster Works 9 03-Sep-12 12-Sep-12 30-Dec-12 09-Jan-13 97
A65350 Installation of Suspended Ceiling Grid 11 20-Sep-12 02-Oct-12 17-Jan-13 30-Jan-13 97
A65340 1st Coat Paint 7 03-Oct-12 10-Oct-12 31-Jan-13 07-Feb-13 97
Fisrt StaFisrt Stage Finishes 22 11-Oct-12 07-Nov-12 09-Feb-13 05-Mar-13 97
A65360 Suspended Ceiling Tiles 11 11-Oct-12 23-Oct-12 09-Feb-13 20-Feb-13 97
A65530 Screed Works 5 24-Oct-12 31-Oct-12 21-Feb-13 26-Feb-13 97
A65540 Wall Tiles Work 6 01-Nov-12 07-Nov-12 27-Feb-13 05-Mar-13 97
Second SSecond Stage Finishes 12 08-Nov-12 22-Nov-12 06-Mar-13 28-Apr-13 131
A65560 Floor Tiles Work 8 08-Nov-12 18-Nov-12 06-Mar-13 14-Mar-13 97
A65370 Installation of Doors 2 19-Nov-12 20-Nov-12 10-Apr-13 11-Apr-13 119
A65390 Doors Ironmongery 2 19-Nov-12 20-Nov-12 27-Apr-13 28-Apr-13 133
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Toliets Accessories
Installation of Mirrors
Installation of Vanity Counter
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
ElectricalWater Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 61 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A65570 Final Coat Paint 4 19-Nov-12 22-Nov-12 16-Mar-13 19-Mar-13 97
Final StaFinal Stage Finishes 243 24-Nov-12 08-Sep-13 20-Mar-13 02-Oct-13 21
A65580 Installation of Mirrors&Glass 7 24-Nov-12 01-Dec-12 10-Apr-13 17-Apr-13 115
A66120 Instllation of Displayed Kitchen 25 03-Dec-12 31-Dec-12 20-Mar-13 17-Apr-13 90
A65600 Installation of Carpets 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24
A65520 Installation of Sinages 2 30-Mar-13 31-Mar-13 27-Apr-13 28-Apr-13 24
A65590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 58 26-Aug-12 03-Nov-12 22-Dec-12 14-Mar-13 109
HVACHVAC 58 26-Aug-12 03-Nov-12 31-Dec-12 05-Mar-13 101
A65400 Duct Installation & Insulation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105
A65410 Chilled Water Pipe Installation & Insulation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105
A65420 Condensate Pipe Installation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105
A65430 FCU Installation 7 03-Sep-12 10-Sep-12 09-Jan-13 16-Jan-13 105
A65440 Air-Outlet Installation 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101
ElectricalElectrical 58 26-Aug-12 03-Nov-12 22-Dec-12 05-Mar-13 101
A65450 Install Conduits in Wall 7 26-Aug-12 02-Sep-12 22-Dec-12 29-Dec-12 97
A65460 Install Cable Trays & Trunking 7 26-Aug-12 02-Sep-12 30-Dec-12 07-Jan-13 104
A65490 Cable Laying for Low Current System 6 03-Sep-12 09-Sep-12 23-Jan-13 30-Jan-13 117
A65500 Cable Laying for Power 6 03-Sep-12 09-Sep-12 23-Jan-13 30-Jan-13 117
A65470 Wiring for Lighting & Power 6 13-Sep-12 19-Sep-12 10-Jan-13 16-Jan-13 97
A65480 Wiring for Low Current System 6 13-Sep-12 19-Sep-12 10-Jan-13 16-Jan-13 97
A65510 Installation of Lighting Fittings 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101
PlumbingPlumbing 11 26-Aug-12 06-Sep-12 05-Jan-13 16-Jan-13 108
A65610 H/L Drainage Pipes Installation 6 26-Aug-12 01-Sep-12 05-Jan-13 10-Jan-13 108
A65620 H/L Hot&Cold Water Pipe Installation 6 26-Aug-12 01-Sep-12 05-Jan-13 10-Jan-13 108
A65630 Drainage&Water Pipes Testing 5 02-Sep-12 06-Sep-12 12-Jan-13 16-Jan-13 108
Fire FighFire Fighting 58 26-Aug-12 03-Nov-12 03-Jan-13 14-Mar-13 109
A65640 Fire Fighting Pipe 7 26-Aug-12 02-Sep-12 03-Jan-13 10-Jan-13 107
A65650 Hydro Static Test for Pipes 5 03-Sep-12 08-Sep-12 12-Jan-13 16-Jan-13 107
A65550 Fire Alarm Devices 7 24-Oct-12 03-Nov-12 07-Mar-13 14-Mar-13 109
A65660 Sprinkler Fixing 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101
Coffe andCoffe and Baverage Bar (Lounge) 323 16-Aug-12 08-Sep-13 19-Dec-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 19-Dec-12 02-Oct-13 21
Wet WorWet Works 47 16-Aug-12 11-Oct-12 19-Dec-12 13-Feb-13 101
A66090 Block Works 9 16-Aug-12 28-Aug-12 19-Dec-12 29-Dec-12 101
A66040 Plaster Works 11 03-Sep-12 15-Sep-12 05-Jan-13 16-Jan-13 101
A66060 Installation of Suspended Ceiling Grid 10 20-Sep-12 01-Oct-12 22-Jan-13 03-Feb-13 101
A66050 1st Coat Paint 9 02-Oct-12 11-Oct-12 04-Feb-13 13-Feb-13 101
Fisrt StaFisrt Stage Finishes 23 13-Oct-12 10-Nov-12 14-Feb-13 20-Mar-13 108
A66070 Suspended Ceiling Tiles 10 13-Oct-12 23-Oct-12 14-Feb-13 25-Feb-13 101
A66240 Screed Works 4 24-Oct-12 30-Oct-12 06-Mar-13 10-Mar-13 108
A66250 Wall Tiles Work 9 31-Oct-12 10-Nov-12 11-Mar-13 20-Mar-13 108
Second SSecond Stage Finishes 17 11-Nov-12 01-Dec-12 21-Mar-13 28-Apr-13 124
A66270 Floor Tiles Work 10 11-Nov-12 22-Nov-12 21-Mar-13 01-Apr-13 108
A66080 Installation of Doors 2 24-Nov-12 25-Nov-12 10-Apr-13 11-Apr-13 115
A66100 Doors Ironmongery 2 24-Nov-12 25-Nov-12 27-Apr-13 28-Apr-13 129
A66280 Final Coat Paint 7 24-Nov-12 01-Dec-12 02-Apr-13 09-Apr-13 108
Final StaFinal Stage Finishes 236 03-Dec-12 08-Sep-13 10-Apr-13 02-Oct-13 21
A66290 Installation of Mirrors&Glass 7 03-Dec-12 10-Dec-12 10-Apr-13 17-Apr-13 108
A66310 Installation of Carpets 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24
A66230 Installation of Sinages 2 30-Mar-13 31-Mar-13 27-Apr-13 28-Apr-13 24
A66300 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 55 29-Aug-12 03-Nov-12 30-Dec-12 01-Apr-13 124
HVACHVAC 55 29-Aug-12 03-Nov-12 16-Jan-13 05-Mar-13 101
A66110 Duct Installation & Insulation 5 29-Aug-12 03-Sep-12 16-Jan-13 21-Jan-13 115
A66150 Air-Outlet Installation 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101
ElectricalElectrical 53 29-Aug-12 31-Oct-12 30-Dec-12 05-Mar-13 103
A66160 Install Conduits in Wall 4 29-Aug-12 02-Sep-12 30-Dec-12 03-Jan-13 101
A66170 Install Cable Trays & Trunking 4 29-Aug-12 02-Sep-12 10-Jan-13 14-Jan-13 110
A66200 Cable Laying for Low Current System 4 03-Sep-12 06-Sep-12 30-Jan-13 03-Feb-13 122
A66210 Cable Laying for Power 4 03-Sep-12 06-Sep-12 30-Jan-13 03-Feb-13 122
A66180 Wiring for Lighting & Power 4 16-Sep-12 19-Sep-12 17-Jan-13 21-Jan-13 101
A66190 Wiring for Low Current System 4 16-Sep-12 19-Sep-12 17-Jan-13 21-Jan-13 101
A66220 Installation of Lighting Fittings 5 24-Oct-12 31-Oct-12 28-Feb-13 05-Mar-13 103
PlumbingPlumbing 12 29-Aug-12 11-Sep-12 08-Jan-13 21-Jan-13 108
A66320 H/L Drainage Pipes Installation 6 29-Aug-12 04-Sep-12 08-Jan-13 14-Jan-13 108
A66340 Drainage&Water Pipes Testing 6 05-Sep-12 11-Sep-12 15-Jan-13 21-Jan-13 108
Fire FighFire Fighting 7 24-Oct-12 03-Nov-12 25-Mar-13 01-Apr-13 124
A66260 Fire Alarm Devices 7 24-Oct-12 03-Nov-12 25-Mar-13 01-Apr-13 124
VestibuleVestibule 323 16-Aug-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 28 16-Aug-12 19-Sep-12 20-Jan-13 21-Feb-13 127
A65070 Block Works 4 16-Aug-12 22-Aug-12 20-Jan-13 23-Jan-13 127
A65020 Plaster Works 6 29-Aug-12 04-Sep-12 31-Jan-13 06-Feb-13 127
A65040 Installation of Suspended Ceiling Grid 4 10-Sep-12 13-Sep-12 12-Feb-13 16-Feb-13 127
A65030 1st Coat Paint 5 15-Sep-12 19-Sep-12 17-Feb-13 21-Feb-13 127
Fisrt StaFisrt Stage Finishes 10 20-Sep-12 01-Oct-12 23-Feb-13 14-Apr-13 161
A65050 Suspended Ceiling Tiles 3 20-Sep-12 23-Sep-12 23-Feb-13 25-Feb-13 127
A65220 Screed Works 2 24-Sep-12 25-Sep-12 07-Apr-13 08-Apr-13 161
A65230 Wall Tiles Work 5 26-Sep-12 01-Oct-12 09-Apr-13 14-Apr-13 161
Second SSecond Stage Finishes 5 14-Oct-12 18-Oct-12 15-Apr-13 28-Apr-13 158
A65250 Floor Tiles Work 3 14-Oct-12 16-Oct-12 15-Apr-13 17-Apr-13 151
A65060 Installation of Doors 2 17-Oct-12 18-Oct-12 27-Apr-13 28-Apr-13 158
A65080 Doors Ironmongery 2 17-Oct-12 18-Oct-12 27-Apr-13 28-Apr-13 158
A65260 Final Coat Paint 2 17-Oct-12 18-Oct-12 18-Apr-13 20-Apr-13 151
Final StaFinal Stage Finishes 147 19-Mar-13 08-Sep-13 27-Apr-13 02-Oct-13 21
A65210 Installation of Sinages 2 19-Mar-13 20-Mar-13 27-Apr-13 28-Apr-13 33
A65290 Installation of Carpets 3 21-Mar-13 24-Mar-13 27-Jul-13 29-Jul-13 108
A65280 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 34 23-Aug-12 01-Oct-12 26-Jan-13 17-Apr-13 164
HVACHVAC 29 23-Aug-12 25-Sep-12 05-Feb-13 05-Mar-13 132
A65090 Duct Installation & Insulation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136
A65100 Chilled Water Pipe Installation & Insulation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136
A65110 Condensate Pipe Installation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136
A65120 FCU Installation 2 28-Aug-12 29-Aug-12 10-Feb-13 11-Feb-13 136
A65130 Air-Outlet Installation 2 24-Sep-12 25-Sep-12 04-Mar-13 05-Mar-13 132
ElectricalElectrical 34 23-Aug-12 01-Oct-12 26-Jan-13 05-Mar-13 127
A65140 Install Conduits in Wall 5 23-Aug-12 28-Aug-12 26-Jan-13 30-Jan-13 127
A65150 Install Cable Trays & Trunking 5 23-Aug-12 28-Aug-12 30-Jan-13 04-Feb-13 131
A65180 Cable Laying for Low Current System 4 29-Aug-12 02-Sep-12 12-Feb-13 16-Feb-13 137
A65190 Cable Laying for Power 4 29-Aug-12 02-Sep-12 12-Feb-13 16-Feb-13 137
A65160 Wiring for Lighting & Power 4 05-Sep-12 09-Sep-12 07-Feb-13 11-Feb-13 127
A65170 Wiring for Low Current System 4 05-Sep-12 09-Sep-12 07-Feb-13 11-Feb-13 127
A65200 Installation of Lighting Fittings 7 24-Sep-12 01-Oct-12 26-Feb-13 05-Mar-13 127
Fire FighFire Fighting 32 23-Aug-12 29-Sep-12 04-Feb-13 17-Apr-13 166
A65300 Fire Fighting Pipe 5 23-Aug-12 28-Aug-12 04-Feb-13 09-Feb-13 135
A65310 Hydro Static Test for Pipes 2 29-Aug-12 30-Aug-12 10-Feb-13 11-Feb-13 135
A65240 Fire Alarm Devices 5 24-Sep-12 29-Sep-12 13-Apr-13 17-Apr-13 166
A65320 Sprinkler Fixing 5 24-Sep-12 29-Sep-12 28-Feb-13 05-Mar-13 129
BussinissBussiniss Centre & Lobby 323 16-Aug-12 08-Sep-13 31-Oct-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 31-Oct-12 02-Oct-13 21
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Final Coat Paint
Installation of Mirrors&Glass
Instllation of Displayed Kitchen
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Mirrors&Glass
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
H/L Drainage Pipes Installation
Drainage&Water Pipes Testing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Carpets
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 62 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Wet WorWet Works 61 16-Aug-12 30-Oct-12 31-Oct-12 13-Jan-13 61
A64380 Block Works 14 16-Aug-12 03-Sep-12 31-Oct-12 17-Nov-12 61
A64330 Plaster Works 13 16-Sep-12 30-Sep-12 29-Nov-12 15-Dec-12 61
A64350 Installation of Suspended Ceiling Grid 9 13-Oct-12 22-Oct-12 27-Dec-12 07-Jan-13 61
A64340 1st Coat Paint 5 23-Oct-12 30-Oct-12 08-Jan-13 13-Jan-13 61
Fisrt StaFisrt Stage Finishes 29 31-Oct-12 05-Dec-12 14-Jan-13 17-Feb-13 61
A64360 Suspended Ceiling Tiles 9 31-Oct-12 10-Nov-12 14-Jan-13 23-Jan-13 61
A64560 Screed Works 7 11-Nov-12 19-Nov-12 26-Jan-13 02-Feb-13 61
A64570 Wall Tiles Work 13 20-Nov-12 05-Dec-12 03-Feb-13 17-Feb-13 61
Second SSecond Stage Finishes 11 06-Dec-12 18-Dec-12 18-Feb-13 28-Apr-13 110
A64600 Floor Tiles Work 8 06-Dec-12 15-Dec-12 18-Feb-13 26-Feb-13 61
A64370 Installation of Doors 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
A64390 Doors Ironmongery 3 16-Dec-12 18-Dec-12 25-Apr-13 28-Apr-13 110
A64610 Final Coat Paint 3 16-Dec-12 18-Dec-12 27-Feb-13 02-Mar-13 61
Final StaFinal Stage Finishes 222 19-Dec-12 08-Sep-13 03-Mar-13 02-Oct-13 21
A64620 Installation of Mirrors&Glass 20 19-Dec-12 12-Jan-13 03-Mar-13 25-Mar-13 61
A64650 Installation of Carpets 20 21-Mar-13 13-Apr-13 26-Mar-13 17-Apr-13 4
A64550 Installation of Sinages 9 14-Apr-13 23-Apr-13 18-Apr-13 28-Apr-13 4
A64640 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
A114070 Installation of Reception Counter 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 68 04-Sep-12 25-Nov-12 18-Nov-12 26-Feb-13 77
HVACHVAC 63 04-Sep-12 19-Nov-12 13-Dec-12 26-Feb-13 82
A64400 Duct Installation & Insulation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82
A64410 Chilled Water Pipe Installation & Insulation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82
A64420 Condensate Pipe Installation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82
A64430 FCU Installation 7 10-Sep-12 17-Sep-12 19-Dec-12 26-Dec-12 82
A64440 Air-Outlet Installation 7 11-Nov-12 19-Nov-12 19-Feb-13 26-Feb-13 82
ElectricalElectrical 67 04-Sep-12 24-Nov-12 18-Nov-12 26-Feb-13 78
A64450 Install Conduits in Wall 10 04-Sep-12 15-Sep-12 18-Nov-12 28-Nov-12 61
A64460 Install Cable Trays & Trunking 10 04-Sep-12 15-Sep-12 01-Dec-12 12-Dec-12 72
A64490 Cable Laying for Low Current System 10 16-Sep-12 26-Sep-12 26-Dec-12 07-Jan-13 83
A64500 Cable Laying for Power 10 16-Sep-12 26-Sep-12 26-Dec-12 07-Jan-13 83
A64470 Wiring for Lighting & Power 10 01-Oct-12 11-Oct-12 16-Dec-12 26-Dec-12 61
A64480 Wiring for Low Current System 10 01-Oct-12 11-Oct-12 16-Dec-12 26-Dec-12 61
A64510 Installation of Lighting Fittings 11 11-Nov-12 24-Nov-12 14-Feb-13 26-Feb-13 78
PlumbingPlumbing 14 04-Sep-12 19-Sep-12 11-Dec-12 26-Dec-12 80
A64670 H/L Drainage Pipes Installation 7 04-Sep-12 11-Sep-12 11-Dec-12 18-Dec-12 80
A64680 H/L Hot&Cold Water Pipe Installation 7 04-Sep-12 11-Sep-12 11-Dec-12 18-Dec-12 80
A64690 Drainage&Water Pipes Testing 7 12-Sep-12 19-Sep-12 19-Dec-12 26-Dec-12 80
Fire FighFire Fighting 12 11-Nov-12 25-Nov-12 13-Feb-13 26-Feb-13 77
A64590 Fire Alarm Devices 12 11-Nov-12 25-Nov-12 13-Feb-13 26-Feb-13 77
RetailRetail 323 16-Aug-12 08-Sep-13 21-Jan-13 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 21-Jan-13 02-Oct-13 21
Wet WorWet Works 27 16-Aug-12 18-Sep-12 21-Jan-13 25-Apr-13 182
A64780 Block Works 4 16-Aug-12 22-Aug-12 21-Jan-13 26-Jan-13 128
A64710 Installation of Doors& Windows Sub-frame 2 28-Aug-12 29-Aug-12 24-Apr-13 25-Apr-13 199
A64700 Plaster Works 6 28-Aug-12 03-Sep-12 31-Jan-13 06-Feb-13 128
A64730 Installation of Suspended Ceiling Grid 4 09-Sep-12 12-Sep-12 12-Feb-13 16-Feb-13 128
A64720 1st Coat Paint 5 13-Sep-12 18-Sep-12 17-Feb-13 21-Feb-13 128
Fisrt StaFisrt Stage Finishes 13 19-Sep-12 03-Oct-12 23-Feb-13 17-Apr-13 162
A64740 Suspended Ceiling Tiles 3 19-Sep-12 22-Sep-12 23-Feb-13 25-Feb-13 128
A64960 Screed Works 2 23-Sep-12 24-Sep-12 14-Apr-13 15-Apr-13 168
A64760 Floor Tiles Work 2 02-Oct-12 03-Oct-12 16-Apr-13 17-Apr-13 162
Second SSecond Stage Finishes 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
A64770 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
A64790 Doors Ironmongery 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
Final StaFinal Stage Finishes 283 04-Oct-12 08-Sep-13 18-Apr-13 02-Oct-13 21
A64750 Final Coat Paint 2 04-Oct-12 06-Oct-12 18-Apr-13 20-Apr-13 162
A64950 Installation of Sinages 2 21-Mar-13 23-Mar-13 27-Apr-13 28-Apr-13 31
A64980 Installation of Carpets 2 21-Mar-13 23-Mar-13 27-Apr-13 28-Apr-13 31
A64800 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 33 23-Aug-12 30-Sep-12 27-Jan-13 20-Apr-13 167
HVACHVAC 10 23-Aug-12 03-Sep-12 31-Jan-13 11-Feb-13 132
A64990 Chilled Water Pipe Installation & Insulation 5 23-Aug-12 28-Aug-12 31-Jan-13 05-Feb-13 132
A65000 Condensate Pipe Installation 5 23-Aug-12 28-Aug-12 31-Jan-13 05-Feb-13 132
A65010 FCU Installation 5 29-Aug-12 03-Sep-12 06-Feb-13 11-Feb-13 132
ElectricalElectrical 33 23-Aug-12 30-Sep-12 27-Jan-13 05-Mar-13 128
A64830 Install Conduits in Wall 4 23-Aug-12 27-Aug-12 27-Jan-13 30-Jan-13 128
A64840 Install Cable Trays & Trunking 4 23-Aug-12 27-Aug-12 31-Jan-13 04-Feb-13 132
A64870 Cable Laying for Low Current System 4 28-Aug-12 01-Sep-12 12-Feb-13 16-Feb-13 138
A64880 Cable Laying for Power 4 28-Aug-12 01-Sep-12 12-Feb-13 16-Feb-13 138
A64850 Wiring for Lighting & Power 4 04-Sep-12 08-Sep-12 07-Feb-13 11-Feb-13 128
A64860 Wiring for Low Current System 4 04-Sep-12 08-Sep-12 07-Feb-13 11-Feb-13 128
A64900 Installation of Sockets 3 23-Sep-12 25-Sep-12 03-Mar-13 05-Mar-13 132
A64890 Installation of Lighting Fittings 7 23-Sep-12 30-Sep-12 26-Feb-13 05-Mar-13 128
Fire FighFire Fighting 33 23-Aug-12 30-Sep-12 02-Feb-13 20-Apr-13 167
A64940 Fire Fighting Pipe 5 23-Aug-12 28-Aug-12 02-Feb-13 06-Feb-13 133
A64930 Hydro Static Test for Pipes 4 29-Aug-12 02-Sep-12 07-Feb-13 11-Feb-13 133
A64920 Sprinkler Fixing 5 23-Sep-12 27-Sep-12 28-Feb-13 05-Mar-13 130
A64910 Installation of Fire Extingusher&Blanket 2 29-Sep-12 30-Sep-12 18-Apr-13 20-Apr-13 167
A64970 Fire Alarm Devices 7 23-Sep-12 30-Sep-12 10-Apr-13 17-Apr-13 165
Meeting RoMeeting Rooms 323 16-Aug-12 08-Sep-13 04-Dec-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 04-Dec-12 02-Oct-13 21
Wet WorWet Works 58 16-Aug-12 24-Oct-12 04-Dec-12 24-Apr-13 150
A60000 Block Works 14 16-Aug-12 03-Sep-12 04-Dec-12 19-Dec-12 88
A59860 Installation of Doors& Windows Sub-frame 3 12-Sep-12 15-Sep-12 22-Apr-13 24-Apr-13 184
A59850 Plaster Works 12 12-Sep-12 25-Sep-12 29-Dec-12 12-Jan-13 88
A59880 Installation of Suspended Ceiling Grid 12 02-Oct-12 15-Oct-12 19-Jan-13 02-Feb-13 88
A59870 1st Coat Paint 8 16-Oct-12 24-Oct-12 03-Feb-13 11-Feb-13 88
Fisrt StaFisrt Stage Finishes 32 28-Oct-12 05-Dec-12 12-Feb-13 15-Apr-13 110
A59890 Suspended Ceiling Tiles 12 28-Oct-12 10-Nov-12 12-Feb-13 25-Feb-13 88
A60320 Screed Works 6 11-Nov-12 18-Nov-12 24-Mar-13 30-Mar-13 110
A59910 Wall Tiles Work 14 19-Nov-12 05-Dec-12 31-Mar-13 15-Apr-13 110
Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 16-Apr-13 28-Apr-13 118
A59900 Final Coat Paint 1 06-Dec-12 06-Dec-12 16-Apr-13 16-Apr-13 110
A59940 Installation of Windows&Doors 3 06-Dec-12 09-Dec-12 25-Apr-13 28-Apr-13 118
A60010 Doors Ironmongery 3 06-Dec-12 09-Dec-12 25-Apr-13 28-Apr-13 118
Final StaFinal Stage Finishes 145 21-Mar-13 08-Sep-13 17-Apr-13 02-Oct-13 21
A59970 Installation of Carpets 7 21-Mar-13 28-Mar-13 17-Apr-13 24-Apr-13 23
A60310 Installation of Sinages 3 30-Mar-13 01-Apr-13 25-Apr-13 28-Apr-13 23
A60020 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 69 04-Sep-12 26-Nov-12 20-Dec-12 15-Apr-13 117
HVACHVAC 63 04-Sep-12 19-Nov-12 10-Jan-13 05-Mar-13 88
A60030 Duct Installation & Insulation 7 04-Sep-12 11-Sep-12 10-Jan-13 17-Jan-13 105
A60070 Air-Outlet Installation 7 11-Nov-12 19-Nov-12 26-Feb-13 05-Mar-13 88
ElectricalElectrical 62 04-Sep-12 18-Nov-12 20-Dec-12 05-Mar-13 89
A60090 Install Cable Trays & Trunking 6 04-Sep-12 10-Sep-12 03-Jan-13 09-Jan-13 99
A60080 Install Conduits in Wall 7 04-Sep-12 11-Sep-12 20-Dec-12 27-Dec-12 88
A60130 Cable Laying for Low Current System 5 11-Sep-12 16-Sep-12 28-Jan-13 02-Feb-13 113
A60140 Cable Laying for Power 5 11-Sep-12 16-Sep-12 28-Jan-13 02-Feb-13 113
A60100 Wiring for Lighting & Power 5 26-Sep-12 01-Oct-12 13-Jan-13 17-Jan-13 88
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Mirrors&Glass
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Installation of Recepti
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Carpets
Installation of Furnitur
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Final Coat Paint
Installation of Windows&Doors
Doors Ironmongery
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Air-Outlet Installation
Install Cable Trays & Trunking
Install Conduits in Wall
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 63 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A60110 Wiring for Low Current System 5 26-Sep-12 01-Oct-12 13-Jan-13 17-Jan-13 88
A60170 Installation of Sockets 5 11-Nov-12 17-Nov-12 28-Feb-13 05-Mar-13 90
A60160 Installation of Lighting Fittings 6 11-Nov-12 18-Nov-12 27-Feb-13 05-Mar-13 89
Fire FighFire Fighting 69 04-Sep-12 26-Nov-12 05-Jan-13 15-Apr-13 117
A60290 Fire Fighting Pipe 7 04-Sep-12 11-Sep-12 05-Jan-13 12-Jan-13 100
A60280 Hydro Static Test for Pipes 5 12-Sep-12 17-Sep-12 13-Jan-13 17-Jan-13 100
A60270 Sprinkler Fixing 6 11-Nov-12 18-Nov-12 27-Feb-13 05-Mar-13 89
A60370 Fire Alarm Devices 7 19-Nov-12 26-Nov-12 08-Apr-13 15-Apr-13 117
RMU RoomRMU Room 109 16-Aug-12 27-Dec-12 23-Jan-13 28-Apr-13 102
FinishingFinishing Works 73 16-Aug-12 13-Nov-12 23-Jan-13 28-Apr-13 138
Wet WorWet Works 24 16-Aug-12 15-Sep-12 23-Jan-13 08-Apr-13 170
A63160 Block Works 5 16-Aug-12 23-Aug-12 23-Jan-13 29-Jan-13 130
A63120 Installation of Doors& Windows Sub-frame 2 28-Aug-12 29-Aug-12 07-Apr-13 08-Apr-13 184
A63110 Plaster Works 7 28-Aug-12 04-Sep-12 03-Feb-13 10-Feb-13 130
A63130 1st Coat Paint 7 08-Sep-12 15-Sep-12 13-Feb-13 20-Feb-13 130
Fisrt StaFisrt Stage Finishes 40 24-Sep-12 11-Nov-12 02-Mar-13 25-Apr-13 138
A63220 Epoxy Paint Works 2 24-Sep-12 25-Sep-12 02-Mar-13 03-Mar-13 130
A63150 Installation of Doors 15 23-Oct-12 11-Nov-12 09-Apr-13 25-Apr-13 138
A63170 Doors Ironmongery 15 23-Oct-12 11-Nov-12 09-Apr-13 25-Apr-13 138
Second SSecond Stage Finishes 4 26-Sep-12 30-Sep-12 04-Mar-13 07-Mar-13 130
A63140 Final Coat Paint 4 26-Sep-12 30-Sep-12 04-Mar-13 07-Mar-13 130
Final StaFinal Stage Finishes 2 12-Nov-12 13-Nov-12 27-Apr-13 28-Apr-13 138
A63210 Installation of Sinages 2 12-Nov-12 13-Nov-12 27-Apr-13 28-Apr-13 138
MEP WorkMEP Works 106 22-Aug-12 27-Dec-12 28-Jan-13 21-Mar-13 70
HVACHVAC 12 25-Aug-12 06-Sep-12 16-Feb-13 28-Feb-13 144
A63250 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 16-Feb-13 23-Feb-13 144
A63260 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 16-Feb-13 23-Feb-13 144
A63270 FCU Installation 5 02-Sep-12 06-Sep-12 24-Feb-13 28-Feb-13 144
ElectricalElectrical 106 22-Aug-12 27-Dec-12 28-Jan-13 21-Mar-13 70
Light &Light & Power 26 22-Aug-12 20-Sep-12 28-Jan-13 28-Feb-13 132
A63180 Install Conduits in Wall 5 22-Aug-12 27-Aug-12 28-Jan-13 02-Feb-13 130
A63280 Install Cable Trays & Trunking 7 25-Aug-12 01-Sep-12 13-Feb-13 20-Feb-13 142
A63190 Wiring for Lighting & Power 4 03-Sep-12 06-Sep-12 09-Feb-13 12-Feb-13 130
A63290 Cable Laying for Power 7 02-Sep-12 09-Sep-12 21-Feb-13 28-Feb-13 142
A63200 Installation of Lighting Fittings 5 16-Sep-12 20-Sep-12 24-Feb-13 28-Feb-13 132
RMU UnRMU Unit 29 24-Nov-12 27-Dec-12 17-Feb-13 21-Mar-13 70
A114700 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 17-Feb-13 21-Feb-13 70
A114690 Installation of RMU Unit 12 24-Nov-12 08-Dec-12 02-Mar-13 14-Mar-13 81
A114720 Install of Cables 12 29-Nov-12 13-Dec-12 23-Feb-13 07-Mar-13 70
A114750 Test of Cables 6 15-Dec-12 20-Dec-12 09-Mar-13 14-Mar-13 70
A114760 Termination of Cables 6 22-Dec-12 27-Dec-12 16-Mar-13 21-Mar-13 70
Fire FighFire Fighting 7 16-Sep-12 23-Sep-12 21-Feb-13 28-Feb-13 130
A63230 Fire Alarm Devices 7 16-Sep-12 23-Sep-12 21-Feb-13 28-Feb-13 130
AdminstraAdminstration Offices 323 16-Aug-12 08-Sep-13 31-Dec-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 31-Dec-12 02-Oct-13 21
Wet WorWet Works 40 16-Aug-12 03-Oct-12 31-Dec-12 25-Apr-13 169
A63530 Block Works 8 16-Aug-12 27-Aug-12 31-Dec-12 09-Jan-13 111
A63460 Installation of Doors& Windows Sub-frame 2 02-Sep-12 03-Sep-12 24-Apr-13 25-Apr-13 195
A63450 Plaster Works 7 02-Sep-12 09-Sep-12 15-Jan-13 22-Jan-13 111
A63480 Installation of Suspended Ceiling Grid 7 15-Sep-12 22-Sep-12 29-Jan-13 05-Feb-13 111
A63470 1st Coat Paint 10 23-Sep-12 03-Oct-12 06-Feb-13 17-Feb-13 111
Fisrt StaFisrt Stage Finishes 16 04-Oct-12 22-Oct-12 18-Feb-13 15-Apr-13 144
A63490 Suspended Ceiling Tiles 7 04-Oct-12 11-Oct-12 18-Feb-13 25-Feb-13 111
A63820 Screed Works 2 13-Oct-12 14-Oct-12 06-Apr-13 07-Apr-13 144
A63510 Floor Tiles Work 7 15-Oct-12 22-Oct-12 08-Apr-13 15-Apr-13 144
Second SSecond Stage Finishes 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
A63520 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
A63540 Doors Ironmongery 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136
Final StaFinal Stage Finishes 267 23-Oct-12 08-Sep-13 16-Apr-13 02-Oct-13 21
A63500 Final Coat Paint 4 23-Oct-12 29-Oct-12 16-Apr-13 20-Apr-13 144
A63810 Installation of Sinages 2 27-Mar-13 28-Mar-13 27-Apr-13 28-Apr-13 26
A63840 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A63550 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 48 28-Aug-12 22-Oct-12 10-Jan-13 20-Apr-13 148
HVACHVAC 44 28-Aug-12 17-Oct-12 20-Feb-13 05-Mar-13 113
A63560 Duct Installation & Insulation 7 28-Aug-12 04-Sep-12 20-Feb-13 27-Feb-13 145
A63600 Air-Outlet Installation 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113
ElectricalElectrical 44 28-Aug-12 17-Oct-12 10-Jan-13 05-Mar-13 113
A63610 Install Conduits in Wall 4 28-Aug-12 01-Sep-12 10-Jan-13 14-Jan-13 111
A63620 Install Cable Trays & Trunking 4 28-Aug-12 01-Sep-12 16-Jan-13 20-Jan-13 116
A63650 Cable Laying for Low Current System 5 02-Sep-12 06-Sep-12 31-Jan-13 05-Feb-13 124
A63660 Cable Laying for Power 5 02-Sep-12 06-Sep-12 31-Jan-13 05-Feb-13 124
A63630 Wiring for Lighting & Power 4 10-Sep-12 13-Sep-12 23-Jan-13 28-Jan-13 111
A63640 Wiring for Low Current System 4 10-Sep-12 13-Sep-12 23-Jan-13 28-Jan-13 111
A63680 Installation of Sockets 4 13-Oct-12 16-Oct-12 02-Mar-13 05-Mar-13 114
A63670 Installation of Lighting Fittings 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113
Fire FighFire Fighting 48 28-Aug-12 22-Oct-12 15-Jan-13 20-Apr-13 148
A63800 Fire Fighting Pipe 7 28-Aug-12 04-Sep-12 15-Jan-13 22-Jan-13 115
A63790 Hydro Static Test for Pipes 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115
A63780 Sprinkler Fixing 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111
A63830 Fire Alarm Devices 7 13-Oct-12 20-Oct-12 08-Apr-13 15-Apr-13 146
A63770 Installation of Fire Extingusher&Blanket 2 21-Oct-12 22-Oct-12 18-Apr-13 20-Apr-13 148
Drivers RoDrivers Room 323 16-Aug-12 08-Sep-13 29-Dec-12 02-Oct-13 21
FinishingFinishing Works 323 16-Aug-12 08-Sep-13 29-Dec-12 02-Oct-13 21
Wet WorWet Works 28 16-Aug-12 19-Sep-12 29-Dec-12 07-Apr-13 165
A61970 Block Works 5 16-Aug-12 23-Aug-12 29-Dec-12 03-Jan-13 109
A61830 Installation of Doors& Windows Sub-frame 2 29-Aug-12 30-Aug-12 06-Apr-13 07-Apr-13 182
A61820 Plaster Works 5 29-Aug-12 03-Sep-12 09-Jan-13 14-Jan-13 109
A62300 Wall Tiles Work (Wet Area) 5 04-Sep-12 09-Sep-12 06-Feb-13 11-Feb-13 127
A61850 Installation of Suspended Ceiling Grid (Dry Area) 5 09-Sep-12 13-Sep-12 20-Jan-13 26-Jan-13 109
A61840 1st Coat Paint 5 15-Sep-12 19-Sep-12 27-Jan-13 31-Jan-13 109
Fisrt StaFisrt Stage Finishes 40 20-Sep-12 07-Nov-12 02-Feb-13 14-Apr-13 131
A61860 Suspended Ceiling Tiles (DryArea) 4 20-Sep-12 24-Sep-12 02-Feb-13 05-Feb-13 109
A61900 Installation of Wardrobes 5 08-Oct-12 13-Oct-12 06-Feb-13 11-Feb-13 98
A62290 Screed Works 2 14-Oct-12 15-Oct-12 12-Feb-13 13-Feb-13 98
A61890 Water Proofing for Wet Area 3 16-Oct-12 18-Oct-12 14-Feb-13 17-Feb-13 98
A61880 Floor & Wall Tiles Work (Dry Area) 5 16-Oct-12 21-Oct-12 09-Apr-13 14-Apr-13 144
A62330 Installation of Suspended Ceiling Grid (Wet Area) 5 20-Oct-12 24-Oct-12 18-Feb-13 23-Feb-13 98
A62320 Suspended Ceiling Tiles (Wet Area) 5 28-Oct-12 01-Nov-12 24-Feb-13 28-Feb-13 98
A62310 Floor Tiles Work (Wet Area) 5 03-Nov-12 07-Nov-12 02-Apr-13 07-Apr-13 125
Second SSecond Stage Finishes 6 14-Nov-12 21-Nov-12 08-Apr-13 14-Apr-13 120
A61910 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 08-Apr-13 09-Apr-13 120
A61980 Doors Ironmongery 2 14-Nov-12 17-Nov-12 13-Apr-13 14-Apr-13 124
A61960 Installation of Vanity Counter 2 18-Nov-12 19-Nov-12 13-Apr-13 14-Apr-13 122
A62270 Installation of Toliets Accessories 2 18-Nov-12 19-Nov-12 13-Apr-13 14-Apr-13 122
A61920 Installation of Mirrors 4 18-Nov-12 21-Nov-12 10-Apr-13 14-Apr-13 120
Final StaFinal Stage Finishes 244 22-Nov-12 08-Sep-13 15-Apr-13 02-Oct-13 21
A61870 Final Coat Paint 5 22-Nov-12 27-Nov-12 15-Apr-13 20-Apr-13 120
A62280 Installation of Sinages 2 28-Nov-12 29-Nov-12 27-Apr-13 28-Apr-13 125
A61990 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 74 25-Aug-12 21-Nov-12 05-Jan-13 20-Apr-13 125
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Wiring for Lighting & Power
Cable Laying for Power
Installation of Lighting Fittings
Install Cable Tray & Trunking
Installation of RMU Unit
Install of Cables
Test of Cables
Termination of Cables
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Carpets
Installation of Furnitur
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Vanity Counter
Installation of Toliets Accessories
Installation of Mirrors
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 64 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
HVACHVAC 61 25-Aug-12 05-Nov-12 09-Jan-13 05-Mar-13 99
A62000 Duct Installation & Insulation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113
A62010 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113
A62020 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113
A62030 FCU Installation 2 02-Sep-12 03-Sep-12 17-Jan-13 19-Jan-13 113
A62040 Air-Outlet Installation 3 03-Nov-12 05-Nov-12 03-Mar-13 05-Mar-13 99
ElectricalElectrical 62 25-Aug-12 06-Nov-12 05-Jan-13 05-Mar-13 98
A62060 Install Cable Trays & Trunking 3 25-Aug-12 27-Aug-12 09-Jan-13 12-Jan-13 113
A62050 Install Conduits in Wall 4 25-Aug-12 28-Aug-12 05-Jan-13 08-Jan-13 109
A62100 Cable Laying for Low Current System 3 28-Aug-12 30-Aug-12 22-Jan-13 26-Jan-13 121
A62110 Cable Laying for Power 3 28-Aug-12 30-Aug-12 22-Jan-13 26-Jan-13 121
A62070 Wiring for Lighting & Power 4 04-Sep-12 08-Sep-12 15-Jan-13 19-Jan-13 109
A62080 Wiring for Low Current System 4 04-Sep-12 08-Sep-12 15-Jan-13 19-Jan-13 109
A62140 Installation of Sockets 2 03-Nov-12 04-Nov-12 04-Mar-13 05-Mar-13 100
A62130 Installation of Lighting Fittings 4 03-Nov-12 06-Nov-12 02-Mar-13 05-Mar-13 98
PlumbingPlumbing 74 25-Aug-12 21-Nov-12 07-Jan-13 14-Apr-13 120
A62150 Drainge Pipes in Wall 2 25-Aug-12 26-Aug-12 07-Jan-13 08-Jan-13 111
A62220 Water Pipes in Wall 2 25-Aug-12 26-Aug-12 07-Jan-13 08-Jan-13 111
A62160 H/L Drainage Pipes Installation 4 25-Aug-12 28-Aug-12 10-Feb-13 13-Feb-13 139
A62170 H/L Hot&Cold Water Pipe Installation 4 25-Aug-12 28-Aug-12 10-Feb-13 13-Feb-13 139
A62180 Drainage&Water Pipes Testing 3 29-Aug-12 01-Sep-12 14-Feb-13 17-Feb-13 139
A62190 ElectricalWater Heater Installation 3 29-Aug-12 01-Sep-12 14-Feb-13 17-Feb-13 139
A62200 Floor Drain Fixning 2 16-Oct-12 17-Oct-12 04-Mar-13 05-Mar-13 113
A62210 Installation of Sanitaryware 4 18-Nov-12 21-Nov-12 10-Apr-13 14-Apr-13 120
Fire FighFire Fighting 63 25-Aug-12 07-Nov-12 13-Jan-13 20-Apr-13 136
A62260 Fire Fighting Pipe 3 25-Aug-12 27-Aug-12 13-Jan-13 15-Jan-13 116
A62250 Hydro Static Test for Pipes 3 28-Aug-12 30-Aug-12 16-Jan-13 19-Jan-13 116
A62240 Sprinkler Fixing 3 03-Nov-12 05-Nov-12 03-Mar-13 05-Mar-13 99
A62340 Fire Alarm Devices 3 03-Nov-12 05-Nov-12 11-Apr-13 14-Apr-13 133
A62230 Installation of Fire Extingusher&Blanket 2 06-Nov-12 07-Nov-12 18-Apr-13 20-Apr-13 136
ELV RoomELV Room 115 16-Aug-12 05-Jan-13 24-Oct-12 28-Apr-13 96
FinishingFinishing Works 115 16-Aug-12 05-Jan-13 24-Oct-12 28-Apr-13 96
Wet WorWet Works 28 16-Aug-12 19-Sep-12 24-Oct-12 23-Apr-13 179
A62540 Block Works 4 16-Aug-12 22-Aug-12 24-Oct-12 30-Oct-12 57
A62500 Installation of Doors& Windows Sub-frame 2 29-Aug-12 30-Aug-12 22-Apr-13 23-Apr-13 196
A62490 Plaster Works 7 29-Aug-12 05-Sep-12 06-Nov-12 13-Nov-12 57
A62510 1st Coat Paint 7 12-Sep-12 19-Sep-12 21-Nov-12 28-Nov-12 57
Fisrt StaFisrt Stage Finishes 54 23-Oct-12 29-Dec-12 15-Apr-13 25-Apr-13 99
A62530 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
A62550 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
A62600 Epoxy Paint Works 2 27-Dec-12 29-Dec-12 15-Apr-13 16-Apr-13 91
Second SSecond Stage Finishes 3 30-Dec-12 02-Jan-13 17-Apr-13 20-Apr-13 91
A62520 Final Coat Paint 3 30-Dec-12 02-Jan-13 17-Apr-13 20-Apr-13 91
Final StaFinal Stage Finishes 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96
A62590 Installation of Sinages 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96
MEP WorkMEP Works 104 23-Aug-12 26-Dec-12 31-Oct-12 14-Apr-13 91
HVACHVAC 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130
A62620 Air-Outlet Installation 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130
ElectricalElectrical 104 23-Aug-12 26-Dec-12 31-Oct-12 05-Mar-13 57
A62560 Install Conduits in Wall 5 23-Aug-12 28-Aug-12 31-Oct-12 05-Nov-12 57
A62570 Wiring for Lighting & Power 5 06-Sep-12 11-Sep-12 14-Nov-12 20-Nov-12 57
A62580 Installation of Lighting Fittings 5 20-Sep-12 25-Sep-12 28-Feb-13 05-Mar-13 132
A114340 Installation of Access ControlSystem 80 20-Sep-12 26-Dec-12 29-Nov-12 05-Mar-13 57
A114350 Installation of MATC,TV System 80 20-Sep-12 26-Dec-12 29-Nov-12 05-Mar-13 57
Fire FighFire Fighting 8 20-Sep-12 29-Sep-12 06-Apr-13 14-Apr-13 163
A62610 Fire Alarm Devices 8 20-Sep-12 29-Sep-12 06-Apr-13 14-Apr-13 163
Electrical /Electrical / Telephone Rooms 60 16-Aug-12 29-Oct-12 31-Jan-13 28-Apr-13 151
FinishingFinishing Works 60 16-Aug-12 29-Oct-12 31-Jan-13 28-Apr-13 151
Wet WorWet Works 14 16-Aug-12 03-Sep-12 31-Jan-13 23-Apr-13 193
A62400 Block Works 3 16-Aug-12 21-Aug-12 31-Jan-13 03-Feb-13 136
A62360 Installation of Doors& Windows Sub-frame 1 25-Aug-12 25-Aug-12 23-Apr-13 23-Apr-13 201
A62350 Plaster Works 4 25-Aug-12 28-Aug-12 06-Feb-13 10-Feb-13 136
A62370 1st Coat Paint 3 01-Sep-12 03-Sep-12 13-Feb-13 16-Feb-13 136
Fisrt StaFisrt Stage Finishes 29 22-Sep-12 24-Oct-12 16-Apr-13 25-Apr-13 151
A62460 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 16-Apr-13 17-Apr-13 171
A62390 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
A62410 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
Second SSecond Stage Finishes 2 24-Sep-12 25-Sep-12 18-Apr-13 20-Apr-13 171
A62380 Final Coat Paint 2 24-Sep-12 25-Sep-12 18-Apr-13 20-Apr-13 171
Final StaFinal Stage Finishes 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151
A62450 Installation of Sinages 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151
MEP WorkMEP Works 26 22-Aug-12 20-Sep-12 04-Feb-13 15-Apr-13 171
HVACHVAC 7 04-Sep-12 11-Sep-12 26-Feb-13 05-Mar-13 144
A62480 Air-Outlet Installation 7 04-Sep-12 11-Sep-12 26-Feb-13 05-Mar-13 144
ElectricalElectrical 26 22-Aug-12 20-Sep-12 04-Feb-13 05-Mar-13 136
A62420 Install Conduits in Wall 2 22-Aug-12 23-Aug-12 04-Feb-13 05-Feb-13 136
A62430 Wiring for Lighting & Power 2 29-Aug-12 30-Aug-12 11-Feb-13 12-Feb-13 136
A105480 Installation of SMDBs 7 04-Sep-12 11-Sep-12 24-Feb-13 03-Mar-13 142
A62440 Installation of Lighting Fittings 2 12-Sep-12 13-Sep-12 04-Mar-13 05-Mar-13 142
A114770 Installation of Telephone System 15 04-Sep-12 20-Sep-12 17-Feb-13 05-Mar-13 136
Fire FighFire Fighting 2 04-Sep-12 05-Sep-12 14-Apr-13 15-Apr-13 184
A62470 Fire Alarm Devices 2 04-Sep-12 05-Sep-12 14-Apr-13 15-Apr-13 184
Luggage RLuggage Room 60 16-Aug-12 29-Oct-12 10-Feb-13 28-Apr-13 151
FinishingFinishing Works 60 16-Aug-12 29-Oct-12 10-Feb-13 28-Apr-13 151
Wet WorWet Works 19 16-Aug-12 09-Sep-12 10-Feb-13 23-Apr-13 188
A63900 Block Works 5 16-Aug-12 23-Aug-12 10-Feb-13 14-Feb-13 144
A63860 Installation of Doors& Windows Sub-frame 1 27-Aug-12 27-Aug-12 23-Apr-13 23-Apr-13 199
A63850 Plaster Works 5 27-Aug-12 01-Sep-12 18-Feb-13 23-Feb-13 144
A63870 1st Coat Paint 5 04-Sep-12 09-Sep-12 26-Feb-13 03-Mar-13 144
Fisrt StaFisrt Stage Finishes 37 12-Sep-12 24-Oct-12 16-Apr-13 25-Apr-13 151
A63960 Epoxy Paint Works 2 12-Sep-12 13-Sep-12 16-Apr-13 17-Apr-13 179
A63890 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
A63910 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151
Second SSecond Stage Finishes 2 15-Sep-12 16-Sep-12 18-Apr-13 20-Apr-13 179
A63880 Final Coat Paint 2 15-Sep-12 16-Sep-12 18-Apr-13 20-Apr-13 179
Final StaFinal Stage Finishes 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151
A63950 Installation of Sinages 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151
MEP WorkMEP Works 16 25-Aug-12 11-Sep-12 16-Feb-13 20-Apr-13 183
HVACHVAC 9 25-Aug-12 03-Sep-12 24-Feb-13 05-Mar-13 151
A63980 Duct Installation & Insulation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151
A63990 Chilled Water Pipe Installation & Insulation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151
A64000 Condensate Pipe Installation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151
A64010 FCU Installation 2 30-Aug-12 01-Sep-12 02-Mar-13 03-Mar-13 151
A64020 Air-Outlet Installation 2 02-Sep-12 03-Sep-12 04-Mar-13 05-Mar-13 151
ElectricalElectrical 16 25-Aug-12 11-Sep-12 16-Feb-13 05-Mar-13 144
A63920 Install Conduits in Wall 2 25-Aug-12 26-Aug-12 16-Feb-13 17-Feb-13 144
A63930 Wiring for Lighting & Power 2 02-Sep-12 03-Sep-12 24-Feb-13 25-Feb-13 144
A63940 Installation of Lighting Fittings 2 10-Sep-12 11-Sep-12 04-Mar-13 05-Mar-13 144
PlumbingPlumbing 8 25-Aug-12 02-Sep-12 25-Feb-13 05-Mar-13 152
A64070 H/L Hot&Cold Water Pipe Installation 5 25-Aug-12 29-Aug-12 25-Feb-13 02-Mar-13 152
A64080 Water Pipes Testing 3 30-Aug-12 02-Sep-12 03-Mar-13 05-Mar-13 152
Fire FighFire Fighting 14 25-Aug-12 09-Sep-12 21-Feb-13 20-Apr-13 185
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Cable Trays & Trunking
Install Conduits in Wall
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Access ControlSystem
Installation of MATC,TV System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 65 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A64060 Fire Fighting Pipe 5 25-Aug-12 29-Aug-12 21-Feb-13 26-Feb-13 149
A64050 Hydro Static Test for Pipes 3 30-Aug-12 02-Sep-12 27-Feb-13 02-Mar-13 149
A64040 Sprinkler Fixing 3 03-Sep-12 05-Sep-12 03-Mar-13 05-Mar-13 149
A64030 Installation of Fire Extingusher&Blanket 2 06-Sep-12 08-Sep-12 18-Apr-13 20-Apr-13 186
A63970 Fire Alarm Devices 3 06-Sep-12 09-Sep-12 13-Apr-13 15-Apr-13 181
Loading DoLoading Dock Area 62 16-Aug-12 31-Oct-12 29-Dec-12 28-Apr-13 149
FinishingFinishing Works 62 16-Aug-12 31-Oct-12 29-Dec-12 28-Apr-13 149
Wet WorWet Works 44 16-Aug-12 08-Oct-12 29-Dec-12 19-Feb-13 109
A64160 Block Works 6 16-Aug-12 25-Aug-12 29-Dec-12 05-Jan-13 109
A64110 Plaster Works 11 03-Sep-12 15-Sep-12 14-Jan-13 27-Jan-13 109
A64130 Installation of Suspended Ceiling Grid 5 24-Sep-12 29-Sep-12 05-Feb-13 10-Feb-13 109
A64120 1st Coat Paint 8 30-Sep-12 08-Oct-12 11-Feb-13 19-Feb-13 109
Fisrt StaFisrt Stage Finishes 14 09-Oct-12 24-Oct-12 20-Feb-13 20-Apr-13 146
A64140 Suspended Ceiling Tiles 5 09-Oct-12 14-Oct-12 20-Feb-13 25-Feb-13 109
A64310 Epoxy Paint Works 2 23-Oct-12 24-Oct-12 18-Apr-13 20-Apr-13 146
Second SSecond Stage Finishes 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149
A64150 Installation of Doors 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149
A64170 Doors Ironmongery 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149
Final StaFinal Stage Finishes 2 30-Oct-12 31-Oct-12 27-Apr-13 28-Apr-13 149
A64300 Installation of Sinages 2 30-Oct-12 31-Oct-12 27-Apr-13 28-Apr-13 149
MEP WorkMEP Works 50 26-Aug-12 22-Oct-12 06-Jan-13 17-Apr-13 146
HVACHVAC 50 26-Aug-12 22-Oct-12 27-Jan-13 05-Mar-13 109
A64180 Duct Installation & Insulation 8 26-Aug-12 03-Sep-12 27-Jan-13 04-Feb-13 126
A64220 Air-Outlet Installation 7 15-Oct-12 22-Oct-12 26-Feb-13 05-Mar-13 109
ElectricalElectrical 50 26-Aug-12 22-Oct-12 06-Jan-13 05-Mar-13 109
A64230 Install Conduits in Wall 7 26-Aug-12 02-Sep-12 06-Jan-13 13-Jan-13 109
A64240 Wiring for Lighting & Power 7 16-Sep-12 23-Sep-12 28-Jan-13 04-Feb-13 109
A64250 Installation of Lighting Fittings 7 15-Oct-12 22-Oct-12 26-Feb-13 05-Mar-13 109
Fire FighFire Fighting 50 26-Aug-12 22-Oct-12 22-Jan-13 17-Apr-13 146
A64290 Fire Fighting Pipe 7 26-Aug-12 02-Sep-12 22-Jan-13 30-Jan-13 123
A64280 Hydro Static Test for Pipes 4 03-Sep-12 06-Sep-12 31-Jan-13 04-Feb-13 123
A64270 Sprinkler Fixing 5 15-Oct-12 20-Oct-12 28-Feb-13 05-Mar-13 111
A64260 Installation of Fire Extingusher&Blanket 2 21-Oct-12 22-Oct-12 16-Apr-13 17-Apr-13 146
A64320 Fire Alarm Devices 7 15-Oct-12 22-Oct-12 10-Apr-13 17-Apr-13 146
Hotel GarbHotel Garbage Room 120 16-Aug-12 10-Jan-13 27-Dec-12 28-Apr-13 91
FinishingFinishing Works 120 16-Aug-12 10-Jan-13 27-Dec-12 28-Apr-13 91
Wet WorWet Works 25 16-Aug-12 16-Sep-12 27-Dec-12 25-Apr-13 184
A61620 Block Works 9 16-Aug-12 28-Aug-12 27-Dec-12 07-Jan-13 108
A61560 Plaster Works 1 06-Sep-12 06-Sep-12 16-Jan-13 16-Jan-13 108
A61570 Installation of Doors& Windows Sub-frame 2 06-Sep-12 08-Sep-12 24-Apr-13 25-Apr-13 191
A61790 Wall Tiles Work 6 08-Sep-12 13-Sep-12 17-Jan-13 23-Jan-13 108
A61780 Screed Works 2 15-Sep-12 16-Sep-12 26-Jan-13 27-Jan-13 108
Fisrt StaFisrt Stage Finishes 88 17-Sep-12 02-Jan-13 28-Jan-13 25-Apr-13 96
A61580 1st Coat Paint 3 17-Sep-12 19-Sep-12 28-Jan-13 30-Jan-13 108
A61800 Floor Tiles Work 3 30-Dec-12 02-Jan-13 23-Apr-13 25-Apr-13 96
Second SSecond Stage Finishes 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96
A61600 Installation of Doors 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96
A61630 Doors Ironmongery 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96
Final StaFinal Stage Finishes 70 16-Oct-12 10-Jan-13 31-Jan-13 28-Apr-13 91
A61610 Installation of Equipments 60 16-Oct-12 29-Dec-12 31-Jan-13 10-Apr-13 86
A61590 Final Coat Paint 8 30-Dec-12 08-Jan-13 11-Apr-13 20-Apr-13 86
A124210 Installation of Sinages 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91
MEP WorkMEP Works 28 29-Aug-12 30-Sep-12 08-Jan-13 10-Apr-13 159
ElectricalElectrical 22 29-Aug-12 23-Sep-12 08-Jan-13 05-Mar-13 134
A61670 Install Conduits in Wall 7 29-Aug-12 05-Sep-12 08-Jan-13 15-Jan-13 108
A61680 Wiring for Lighting & Power 7 08-Sep-12 15-Sep-12 18-Feb-13 25-Feb-13 134
A61690 Installation of Lighting Fittings 7 16-Sep-12 23-Sep-12 26-Feb-13 05-Mar-13 134
Fire FighFire Fighting 28 29-Aug-12 30-Sep-12 13-Feb-13 10-Apr-13 159
A61770 Fire Fighting Pipe 7 29-Aug-12 05-Sep-12 13-Feb-13 20-Feb-13 138
A61760 Hydro Static Test for Pipes 4 06-Sep-12 10-Sep-12 21-Feb-13 25-Feb-13 138
A61750 Sprinkler Fixing 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130
A61810 Fire Alarm Devices 7 20-Sep-12 27-Sep-12 03-Apr-13 10-Apr-13 161
A61740 Installation of Fire Extingusher&Blanket 2 29-Sep-12 30-Sep-12 09-Apr-13 10-Apr-13 159
StaircaseStaircase 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132
Stairs 1Stairs 1 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132
A109630 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132
A109640 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132
A109650 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109660 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109670 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132
A109680 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132
Stairs 2Stairs 2 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132
A109690 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132
A109700 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132
A109710 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109720 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109730 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132
A109740 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132
Stairs 3Stairs 3 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132
A109750 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132
A109760 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132
A109770 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109780 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109790 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132
A109800 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132
Stairs 4Stairs 4 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132
A109810 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132
A109820 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132
A109830 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109840 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132
A109850 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132
A109860 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132
1st Floor1st Floor 303 11-Sep-12 08-Sep-13 06-Oct-12 02-Oct-13 21
Public AreaPublic Area 303 11-Sep-12 08-Sep-13 06-Oct-12 02-Oct-13 21
SwimmingSwimming Pool Room 146 11-Sep-12 06-Mar-13 06-Oct-12 28-Apr-13 45
FinishingFinishing Works 146 11-Sep-12 06-Mar-13 06-Oct-12 28-Apr-13 45
Wet WorWet Works 64 11-Sep-12 27-Nov-12 06-Oct-12 23-Apr-13 123
A100770 Block Works 16 11-Sep-12 29-Sep-12 06-Oct-12 23-Oct-12 21
A100730 Installation of Doors& Windows Sub-frame 2 07-Oct-12 08-Oct-12 22-Apr-13 23-Apr-13 163
A100720 Plaster Works 15 07-Oct-12 23-Oct-12 03-Nov-12 20-Nov-12 21
A100740 1st Coat Paint 21 03-Nov-12 27-Nov-12 28-Nov-12 23-Dec-12 21
Fisrt StaFisrt Stage Finishes 107 09-Oct-12 17-Feb-13 03-Apr-13 25-Apr-13 58
A100760 Installation of Doors 2 09-Oct-12 10-Oct-12 24-Apr-13 25-Apr-13 163
A100780 Doors Ironmongery 2 09-Oct-12 10-Oct-12 24-Apr-13 25-Apr-13 163
A100830 Epoxy Paint Works 7 10-Feb-13 17-Feb-13 03-Apr-13 10-Apr-13 45
Second SSecond Stage Finishes 13 18-Feb-13 04-Mar-13 11-Apr-13 25-Apr-13 45
A100750 Final Coat Paint 13 18-Feb-13 04-Mar-13 11-Apr-13 25-Apr-13 45
Final StaFinal Stage Finishes 2 05-Mar-13 06-Mar-13 27-Apr-13 28-Apr-13 45
A100820 Installation of Sinages 2 05-Mar-13 06-Mar-13 27-Apr-13 28-Apr-13 45
MEP WorkMEP Works 108 30-Sep-12 09-Feb-13 24-Oct-12 24-Apr-13 64
HVACHVAC 20 30-Sep-12 22-Oct-12 11-Feb-13 05-Mar-13 109
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work
Screed Works
1st Coat Paint
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Installation of Equipments
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 66 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A100860 Duct Installation & Insulation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109
A100870 Chilled Water Pipe Installation & Insulation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109
A100880 Condensate Pipe Installation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109
A100890 FCU Installation 5 08-Oct-12 13-Oct-12 19-Feb-13 24-Feb-13 109
A100900 Air-Outlet Installation 8 14-Oct-12 22-Oct-12 25-Feb-13 05-Mar-13 109
ElectricalElectrical 56 30-Sep-12 08-Dec-12 24-Oct-12 05-Mar-13 73
A100790 Install Conduits in Wall 6 30-Sep-12 06-Oct-12 24-Oct-12 01-Nov-12 21
A100800 Wiring for Lighting & Power 6 24-Oct-12 01-Nov-12 21-Nov-12 27-Nov-12 21
A100810 Installation of Lighting Fittings 8 28-Nov-12 08-Dec-12 25-Feb-13 05-Mar-13 73
PlumbingPlumbing 50 30-Sep-12 29-Nov-12 20-Feb-13 05-Mar-13 79
A100950 H/L Drainage Pipes Installation 8 30-Sep-12 08-Oct-12 20-Feb-13 28-Feb-13 117
A100960 H/L Hot&Cold Water Pipe Installation 8 30-Sep-12 08-Oct-12 20-Feb-13 28-Feb-13 117
A100970 Drainage&Water Pipes Testing 4 09-Oct-12 13-Oct-12 02-Mar-13 05-Mar-13 117
A100980 Floor Drain Fixning 2 28-Nov-12 29-Nov-12 04-Mar-13 05-Mar-13 79
Fire FighFire Fighting 23 30-Sep-12 28-Oct-12 13-Feb-13 24-Apr-13 149
A100940 Fire Fighting Pipe 7 30-Sep-12 07-Oct-12 13-Feb-13 20-Feb-13 111
A100930 Hydro Static Test for Pipes 4 08-Oct-12 11-Oct-12 21-Feb-13 25-Feb-13 111
A100920 Sprinkler Fixing 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111
A100840 Fire Alarm Devices 2 21-Oct-12 22-Oct-12 01-Apr-13 02-Apr-13 133
A100910 Installation of Fire Extingusher&Blanket 5 21-Oct-12 28-Oct-12 20-Apr-13 24-Apr-13 149
SwimminSwimming Pool Equipments 60 28-Nov-12 09-Feb-13 24-Dec-12 05-Mar-13 21
A100990 Installation of GRP Tank 15 28-Nov-12 16-Dec-12 24-Dec-12 10-Jan-13 21
A101030 Installation of Heat Exchanger 15 28-Nov-12 16-Dec-12 12-Jan-13 29-Jan-13 36
A100850 Installation of Swimming Pool Pipes&Fittings 20 28-Nov-12 22-Dec-12 11-Feb-13 05-Mar-13 61
A101000 Installation of Pumps 15 17-Dec-12 03-Jan-13 12-Jan-13 29-Jan-13 21
A101040 Installation of Chemical Tank 15 17-Dec-12 03-Jan-13 30-Jan-13 16-Feb-13 36
A101010 Installation of Filter 15 05-Jan-13 21-Jan-13 30-Jan-13 16-Feb-13 21
A101050 Installation of Control Panel 15 05-Jan-13 21-Jan-13 17-Feb-13 05-Mar-13 36
A101020 Installation of Electrical Heater 15 22-Jan-13 09-Feb-13 17-Feb-13 05-Mar-13 21
Gym AreaGym Area 303 11-Sep-12 08-Sep-13 14-Jan-13 02-Oct-13 21
FinishingFinishing Works 303 11-Sep-12 08-Sep-13 14-Jan-13 02-Oct-13 21
Wet WorWet Works 15 11-Sep-12 27-Sep-12 14-Jan-13 23-Apr-13 172
A115420 Block Works 6 11-Sep-12 17-Sep-12 14-Jan-13 20-Jan-13 102
A115380 Installation of Doors& Windows Sub-frame 2 23-Sep-12 24-Sep-12 22-Apr-13 23-Apr-13 175
A115370 Plaster Works 5 23-Sep-12 27-Sep-12 30-Jan-13 04-Feb-13 105
Fisrt StaFisrt Stage Finishes 30 02-Oct-12 07-Nov-12 05-Feb-13 15-Apr-13 132
A115590 Installation of Suspended Ceiling Grid 5 02-Oct-12 07-Oct-12 05-Feb-13 10-Feb-13 102
A115390 1st Coat Paint 8 08-Oct-12 16-Oct-12 11-Feb-13 19-Feb-13 102
A115600 Suspended Ceiling Tiles 5 17-Oct-12 22-Oct-12 20-Feb-13 25-Feb-13 102
A115640 Screed Works 3 23-Oct-12 28-Oct-12 02-Apr-13 04-Apr-13 132
A115630 Wall Tiles Work 4 29-Oct-12 01-Nov-12 06-Apr-13 09-Apr-13 132
A115620 Floor Tiles Work 5 03-Nov-12 07-Nov-12 10-Apr-13 15-Apr-13 132
Second SSecond Stage Finishes 9 08-Nov-12 19-Nov-12 16-Apr-13 25-Apr-13 132
A115410 Installation of Doors 2 08-Nov-12 10-Nov-12 24-Apr-13 25-Apr-13 139
A115430 Doors Ironmongery 2 08-Nov-12 10-Nov-12 24-Apr-13 25-Apr-13 139
A115400 Final Coat Paint 3 08-Nov-12 11-Nov-12 16-Apr-13 18-Apr-13 132
A115610 Installation of Mirrors 6 12-Nov-12 19-Nov-12 20-Apr-13 25-Apr-13 132
Final StaFinal Stage Finishes 246 20-Nov-12 08-Sep-13 27-Apr-13 02-Oct-13 21
A115470 Installation of Sinages 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132
A115490 Installation of GYM Equipments 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 41 18-Sep-12 06-Nov-12 21-Jan-13 18-Apr-13 136
HVACHVAC 36 18-Sep-12 31-Oct-12 22-Jan-13 05-Mar-13 103
A115500 Duct Installation & Insulation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103
A115510 Chilled Water Pipe Installation & Insulation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103
A115520 Condensate Pipe Installation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103
A115530 FCU Installation 3 27-Sep-12 30-Sep-12 02-Feb-13 04-Feb-13 103
A115540 Air-Outlet Installation 6 23-Oct-12 31-Oct-12 27-Feb-13 05-Mar-13 103
ElectricalElectrical 36 18-Sep-12 31-Oct-12 26-Jan-13 05-Mar-13 103
A115440 Install Conduits in Wall 4 18-Sep-12 22-Sep-12 26-Jan-13 29-Jan-13 105
A115450 Wiring for Lighting & Power 4 29-Sep-12 02-Oct-12 06-Feb-13 10-Feb-13 106
A115460 Installation of Lighting Fittings 6 23-Oct-12 31-Oct-12 27-Feb-13 05-Mar-13 103
Fire FighFire Fighting 41 18-Sep-12 06-Nov-12 21-Jan-13 18-Apr-13 136
A115580 Fire Fighting Pipe 7 18-Sep-12 25-Sep-12 21-Jan-13 29-Jan-13 102
A115570 Hydro Static Test for Pipes 5 26-Sep-12 01-Oct-12 30-Jan-13 04-Feb-13 102
A115560 Sprinkler Fixing 7 23-Oct-12 01-Nov-12 26-Feb-13 05-Mar-13 102
A115480 Fire Alarm Devices 2 03-Nov-12 04-Nov-12 17-Apr-13 18-Apr-13 138
A115550 Installation of Fire Extingusher&Blanket 4 03-Nov-12 06-Nov-12 15-Apr-13 18-Apr-13 136
TolietsToliets 67 11-Sep-12 01-Dec-12 31-Dec-12 28-Apr-13 124
FinishingFinishing Works 67 11-Sep-12 01-Dec-12 31-Dec-12 28-Apr-13 124
Wet WorWet Works 30 11-Sep-12 15-Oct-12 31-Dec-12 11-Apr-13 147
A116360 Block Works 9 11-Sep-12 20-Sep-12 31-Dec-12 10-Jan-13 91
A116300 Installation of Doors& Windows Sub-frame 3 26-Sep-12 29-Sep-12 09-Apr-13 11-Apr-13 161
A116290 Plaster Works 8 26-Sep-12 04-Oct-12 16-Jan-13 26-Jan-13 91
A116600 Wall Tiles Work (Wet Area) 9 06-Oct-12 15-Oct-12 27-Jan-13 05-Feb-13 91
Fisrt StaFisrt Stage Finishes 21 16-Oct-12 11-Nov-12 06-Feb-13 11-Apr-13 126
A116590 Screed Works 3 16-Oct-12 18-Oct-12 06-Feb-13 09-Feb-13 91
A116320 Water Proofing for Wet Area 4 20-Oct-12 23-Oct-12 10-Feb-13 13-Feb-13 91
A116630 Installation of Suspended Ceiling Grid (Wet Area) 5 24-Oct-12 31-Oct-12 14-Feb-13 19-Feb-13 91
A116620 Suspended Ceiling Tiles (Wet Area) 5 01-Nov-12 06-Nov-12 20-Feb-13 25-Feb-13 91
A116610 Floor Tiles Work (Wet Area) 4 07-Nov-12 11-Nov-12 08-Apr-13 11-Apr-13 126
Second SSecond Stage Finishes 10 14-Nov-12 26-Nov-12 13-Apr-13 23-Apr-13 124
A116330 Installation of Doors 3 14-Nov-12 18-Nov-12 13-Apr-13 15-Apr-13 124
A116370 Doors Ironmongery 3 14-Nov-12 18-Nov-12 21-Apr-13 23-Apr-13 131
A116350 Installation of Vanity Counter 3 19-Nov-12 21-Nov-12 21-Apr-13 23-Apr-13 128
A116570 Installation of Toliets Accessories 5 19-Nov-12 24-Nov-12 18-Apr-13 23-Apr-13 126
A116340 Installation of Mirrors 7 19-Nov-12 26-Nov-12 16-Apr-13 23-Apr-13 124
Final StaFinal Stage Finishes 4 27-Nov-12 01-Dec-12 24-Apr-13 28-Apr-13 124
A116310 Final Coat Paint 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124
A116580 Installation of Sinages 2 29-Nov-12 01-Dec-12 27-Apr-13 28-Apr-13 124
MEP WorkMEP Works 50 22-Sep-12 21-Nov-12 12-Jan-13 23-Apr-13 128
HVACHVAC 45 22-Sep-12 14-Nov-12 07-Feb-13 05-Mar-13 91
A116380 Duct Installation & Insulation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113
A116390 Chilled Water Pipe Installation & Insulation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113
A116400 Condensate Pipe Installation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113
A116410 FCU Installation 2 26-Sep-12 27-Sep-12 12-Feb-13 13-Feb-13 113
A116420 Air-Outlet Installation 7 07-Nov-12 14-Nov-12 26-Feb-13 05-Mar-13 91
ElectricalElectrical 43 22-Sep-12 12-Nov-12 12-Jan-13 05-Mar-13 93
A116430 Install Conduits in Wall 4 22-Sep-12 25-Sep-12 12-Jan-13 15-Jan-13 91
A116440 Wiring for Lighting & Power 4 06-Oct-12 09-Oct-12 10-Feb-13 13-Feb-13 103
A116450 Installation of Lighting Fittings 5 07-Nov-12 12-Nov-12 28-Feb-13 05-Mar-13 93
PlumbingPlumbing 50 22-Sep-12 21-Nov-12 13-Jan-13 23-Apr-13 128
A116460 Drainge Pipes in Wall 3 22-Sep-12 24-Sep-12 13-Jan-13 15-Jan-13 92
A116530 Water Pipes in Wall 3 22-Sep-12 24-Sep-12 13-Jan-13 15-Jan-13 92
A116470 H/L Drainage Pipes Installation 4 22-Sep-12 25-Sep-12 06-Feb-13 10-Feb-13 112
A116480 H/L Hot&Cold Water Pipe Installation 4 22-Sep-12 25-Sep-12 06-Feb-13 10-Feb-13 112
A116500 ElectricalWater Heater Installation 2 26-Sep-12 27-Sep-12 12-Feb-13 13-Feb-13 113
A116490 Drainage&Water Pipes Testing 3 26-Sep-12 29-Sep-12 11-Feb-13 13-Feb-13 112
A116510 Floor Drain Fixning 2 18-Oct-12 20-Oct-12 04-Mar-13 05-Mar-13 111
A116520 Installation of Sanitaryware 3 19-Nov-12 21-Nov-12 21-Apr-13 23-Apr-13 128
Fire FighFire Fighting 42 22-Sep-12 11-Nov-12 07-Feb-13 23-Apr-13 136
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Installation of GRP Tank
Installation of Heat Exchanger
Installation of Swimming Pool Pipes&Fittings
Installation of Pumps
Installation of Chemical Tank
Installation of Filter
Installation of Control Panel
Installation of Electrical Heater
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Mirrors
Installation of Sinages
Installation of GYM Eq
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Doors
Doors Ironmongery
Installation of Vanity Counter
Installation of Toliets Accessories
Installation of Mirrors
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
ElectricalWater Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Sanitaryware
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 67 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A116560 Fire Fighting Pipe 3 22-Sep-12 24-Sep-12 07-Feb-13 10-Feb-13 113
A116550 Hydro Static Test for Pipes 3 25-Sep-12 27-Sep-12 11-Feb-13 13-Feb-13 113
A116540 Sprinkler Fixing 3 07-Nov-12 10-Nov-12 03-Mar-13 05-Mar-13 95
A116640 Fire Alarm Devices 4 07-Nov-12 11-Nov-12 20-Apr-13 23-Apr-13 136
House KeeHouse Keeping Room 303 11-Sep-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 303 11-Sep-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 11-Sep-12 10-Oct-12 20-Jan-13 22-Apr-13 160
A116730 Block Works 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107
A116660 Installation of Doors& Windows Sub-frame 1 20-Sep-12 20-Sep-12 22-Apr-13 22-Apr-13 177
A116650 Plaster Works 4 20-Sep-12 24-Sep-12 30-Jan-13 03-Feb-13 107
A116680 Installation of Suspended Ceiling Grid 7 30-Sep-12 07-Oct-12 09-Feb-13 16-Feb-13 107
A116670 1st Coat Paint 3 08-Oct-12 10-Oct-12 17-Feb-13 19-Feb-13 107
Fisrt StaFisrt Stage Finishes 16 11-Oct-12 31-Oct-12 20-Feb-13 22-Apr-13 144
A116690 Suspended Ceiling Tiles 7 11-Oct-12 18-Oct-12 20-Feb-13 27-Feb-13 107
A116970 Screed Works 5 20-Oct-12 24-Oct-12 02-Mar-13 06-Mar-13 108
A116710 Floor Tiles Work 4 28-Oct-12 31-Oct-12 18-Apr-13 22-Apr-13 144
Second SSecond Stage Finishes 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133
A116720 Installation of Windows&Doors 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133
A116740 Doors Ironmongery 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133
Final StaFinal Stage Finishes 249 17-Nov-12 08-Sep-13 24-Apr-13 02-Oct-13 21
A116700 Final Coat Paint 2 17-Nov-12 18-Nov-12 24-Apr-13 25-Apr-13 133
A116960 Installation of Sinages 2 19-Nov-12 20-Nov-12 27-Apr-13 28-Apr-13 133
A116750 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 16-Sep-12 28-Oct-12 26-Jan-13 24-Apr-13 149
HVACHVAC 32 16-Sep-12 22-Oct-12 29-Jan-13 05-Mar-13 109
A116760 Duct Installation & Insulation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110
A116770 Chilled Water Pipe Installation & Insulation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110
A116780 Condensate Pipe Installation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110
A116790 FCU Installation 2 24-Sep-12 25-Sep-12 06-Feb-13 07-Feb-13 110
A116800 Air-Outlet Installation 3 20-Oct-12 22-Oct-12 03-Mar-13 05-Mar-13 109
ElectricalElectrical 34 16-Sep-12 24-Oct-12 26-Jan-13 05-Mar-13 107
A116810 Install Conduits in Wall 4 16-Sep-12 19-Sep-12 26-Jan-13 29-Jan-13 107
A116820 Install Cable Trays & Trunking 4 16-Sep-12 19-Sep-12 28-Jan-13 31-Jan-13 109
A116840 Cable Laying for Power 4 20-Sep-12 24-Sep-12 12-Feb-13 16-Feb-13 118
A116830 Wiring for Lighting & Power 4 25-Sep-12 29-Sep-12 04-Feb-13 07-Feb-13 107
A116860 Installation of Sockets 3 20-Oct-12 22-Oct-12 03-Mar-13 05-Mar-13 109
A116850 Installation of Lighting Fittings 5 20-Oct-12 24-Oct-12 28-Feb-13 05-Mar-13 107
PlumbingPlumbing 33 16-Sep-12 23-Oct-12 31-Jan-13 05-Mar-13 108
A116870 H/L Drainage Pipes Installation 3 16-Sep-12 18-Sep-12 31-Jan-13 03-Feb-13 112
A116880 H/L Hot&Cold Water Pipe Installation 3 16-Sep-12 18-Sep-12 31-Jan-13 03-Feb-13 112
A116890 Drainage&Water Pipes Testing 3 19-Sep-12 22-Sep-12 04-Feb-13 06-Feb-13 112
A116900 ElectricalWater Heater Installation 4 19-Sep-12 23-Sep-12 04-Feb-13 07-Feb-13 112
A116910 Floor Drain Fixning 2 22-Oct-12 23-Oct-12 04-Mar-13 05-Mar-13 108
Fire FighFire Fighting 35 16-Sep-12 28-Oct-12 31-Jan-13 24-Apr-13 149
A116950 Fire Fighting Pipe 4 16-Sep-12 19-Sep-12 31-Jan-13 04-Feb-13 112
A116940 Hydro Static Test for Pipes 3 20-Sep-12 23-Sep-12 05-Feb-13 07-Feb-13 112
A116930 Sprinkler Fixing 4 20-Oct-12 23-Oct-12 02-Mar-13 05-Mar-13 108
A116980 Fire Alarm Devices 4 20-Oct-12 23-Oct-12 20-Apr-13 23-Apr-13 150
A116920 Installation of Fire Extingusher&Blanket 2 24-Oct-12 28-Oct-12 23-Apr-13 24-Apr-13 149
PlantersPlanters 153 11-Sep-12 14-Mar-13 12-Nov-12 28-Apr-13 38
FinishingFinishing Works 153 11-Sep-12 14-Mar-13 12-Nov-12 28-Apr-13 38
A1033 Water Proof Membrane 20 11-Sep-12 03-Oct-12 12-Nov-12 06-Dec-12 51
A1034 Drainage Gravel 20 20-Oct-12 13-Nov-12 08-Dec-12 30-Dec-12 38
A1035 Geptextile Membrane 20 14-Nov-12 09-Dec-12 31-Dec-12 23-Jan-13 38
A1036 Sweet Soil 20 10-Dec-12 02-Jan-13 26-Jan-13 17-Feb-13 38
A1043 Installation of Sand Stone Coping 9 03-Jan-13 13-Jan-13 18-Apr-13 28-Apr-13 89
A107910 Installation of Lighitngs 30 03-Jan-13 07-Feb-13 25-Mar-13 28-Apr-13 68
A1037 Installation of Planting Items 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38
A1047 Instllation of Wood Gazebo 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38
A107880 Installation of Irrigation System 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38
Electrical RElectrical Room / Telephone Room 57 11-Sep-12 19-Nov-12 31-Jan-13 28-Apr-13 134
FinishingFinishing Works 57 11-Sep-12 19-Nov-12 31-Jan-13 28-Apr-13 134
Wet WorWet Works 14 11-Sep-12 26-Sep-12 31-Jan-13 23-Apr-13 173
A104910 Block Works 3 11-Sep-12 13-Sep-12 31-Jan-13 03-Feb-13 116
A104870 Installation of Doors& Windows Sub-frame 1 17-Sep-12 17-Sep-12 23-Apr-13 23-Apr-13 181
A104860 Plaster Works 4 17-Sep-12 20-Sep-12 06-Feb-13 10-Feb-13 116
A104880 1st Coat Paint 3 24-Sep-12 26-Sep-12 13-Feb-13 16-Feb-13 116
Fisrt StaFisrt Stage Finishes 26 15-Oct-12 17-Nov-12 22-Apr-13 25-Apr-13 134
A104970 Epoxy Paint Works 2 15-Oct-12 16-Oct-12 22-Apr-13 23-Apr-13 156
A104900 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A104920 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
Second SSecond Stage Finishes 2 17-Oct-12 18-Oct-12 24-Apr-13 25-Apr-13 156
A104890 Final Coat Paint 2 17-Oct-12 18-Oct-12 24-Apr-13 25-Apr-13 156
Final StaFinal Stage Finishes 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134
A104960 Installation of Sinages 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134
MEP WorkMEP Works 26 15-Sep-12 14-Oct-12 04-Feb-13 21-Apr-13 156
HVACHVAC 2 27-Sep-12 29-Sep-12 04-Mar-13 05-Mar-13 129
A105000 Air-Outlet Installation 2 27-Sep-12 29-Sep-12 04-Mar-13 05-Mar-13 129
ElectricalElectrical 26 15-Sep-12 14-Oct-12 04-Feb-13 05-Mar-13 116
A104930 Install Conduits in Wall 2 15-Sep-12 16-Sep-12 04-Feb-13 05-Feb-13 116
A104940 Wiring for Lighting & Power 2 22-Sep-12 23-Sep-12 11-Feb-13 12-Feb-13 116
A104990 Installation of SMDBs 7 27-Sep-12 04-Oct-12 24-Feb-13 03-Mar-13 122
A104950 Installation of Lighting Fittings 2 06-Oct-12 07-Oct-12 04-Mar-13 05-Mar-13 122
A114780 Installation of Telephone System 15 27-Sep-12 14-Oct-12 17-Feb-13 05-Mar-13 116
Fire FighFire Fighting 2 08-Oct-12 09-Oct-12 20-Apr-13 21-Apr-13 160
A104980 Fire Alarm Devices 2 08-Oct-12 09-Oct-12 20-Apr-13 21-Apr-13 160
StaircaseStaircase 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119
Stairs 1Stairs 1 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119
A109870 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119
A109880 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119
A109890 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A109900 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A109910 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119
A109920 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119
Stairs 2Stairs 2 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119
A109930 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119
A109940 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119
A109950 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A109960 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A109970 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119
A109980 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119
Stairs 3Stairs 3 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119
A109990 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119
A110000 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119
A110010 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A110020 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119
A110030 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119
A110040 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119
Sky LightSky Light 30 27-Dec-12 02-Feb-13 25-Mar-13 28-Apr-13 73
A1156 Instalaltion of Sky Light 30 27-Dec-12 02-Feb-13 25-Mar-13 28-Apr-13 73
Rooms AreaRooms Area 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Water Proof Membrane
Drainage Gravel
Geptextile Membrane
Sweet Soil
Installation of Sand Stone Coping
Installation of Lighitngs
Installation of Planting Items
Instllation of Wood Gazebo
Installation of Irrigation System
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Instalaltion of Sky Light
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 68 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Guest RooGuest Rooms 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21
FinishingFinishing Works 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21
Wet WorWet Works 71 11-Sep-12 06-Dec-12 29-Oct-12 10-Mar-13 78
A12990 Block Works 14 11-Sep-12 26-Sep-12 29-Oct-12 13-Nov-12 39
A12840 Plaster Works 23 01-Oct-12 29-Oct-12 19-Nov-12 16-Dec-12 39
A12850 Installation of Doors& Windows Sub-frame 26 01-Oct-12 01-Nov-12 09-Feb-13 10-Mar-13 106
A13320 Wall Tiles Work (Wet Area) 16 15-Oct-12 04-Nov-12 10-Jan-13 29-Jan-13 70
A12870 Installation of Suspended Ceiling Grid (Dry Area) 15 03-Nov-12 20-Nov-12 20-Dec-12 07-Jan-13 39
A12860 1st Coat Paint 21 11-Nov-12 06-Dec-12 29-Dec-12 22-Jan-13 39
Fisrt StaFisrt Stage Finishes 37 03-Dec-12 15-Jan-13 19-Jan-13 01-Apr-13 64
A12880 Suspended Ceiling Tiles (DryArea) 7 03-Dec-12 10-Dec-12 19-Jan-13 27-Jan-13 39
A12920 Installation of Wardrobes 12 08-Dec-12 20-Dec-12 23-Jan-13 06-Feb-13 39
A13310 Screed Works 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39
A12910 Water Proofing for Wet Area 8 20-Dec-12 29-Dec-12 06-Feb-13 14-Feb-13 39
A12900 Floor & Wall Tiles Work (Dry Area) 12 19-Dec-12 02-Jan-13 19-Mar-13 01-Apr-13 75
A13350 Installation of Suspended Ceiling Grid (Wet Area) 6 26-Dec-12 02-Jan-13 12-Feb-13 18-Feb-13 39
A13340 Suspended Ceiling Tiles (Wet Area) 7 31-Dec-12 08-Jan-13 17-Feb-13 24-Feb-13 39
A13330 Floor Tiles Work (Wet Area) 9 06-Jan-13 15-Jan-13 05-Mar-13 14-Mar-13 49
Second SSecond Stage Finishes 17 12-Jan-13 31-Jan-13 11-Mar-13 01-Apr-13 51
A12930 Installation of Windows&Doors 11 12-Jan-13 23-Jan-13 11-Mar-13 23-Mar-13 49
A12970 Installation of Balustrades& Handrails 7 17-Jan-13 26-Jan-13 25-Mar-13 01-Apr-13 56
A13000 Doors Ironmongery 13 12-Jan-13 27-Jan-13 18-Mar-13 01-Apr-13 55
A12940 Installation of Mirrors 9 17-Jan-13 28-Jan-13 23-Mar-13 01-Apr-13 54
A12980 Installation of Vanity Counter 9 17-Jan-13 28-Jan-13 23-Mar-13 01-Apr-13 54
A13290 Installation of Toliets Accessories 12 17-Jan-13 31-Jan-13 19-Mar-13 01-Apr-13 51
Final StaFinal Stage Finishes 184 04-Feb-13 08-Sep-13 02-Apr-13 02-Oct-13 21
A12890 Final Coat Paint 11 04-Feb-13 16-Feb-13 02-Apr-13 14-Apr-13 49
A12960 Installation of Carpets 7 21-Mar-13 28-Mar-13 15-Apr-13 22-Apr-13 21
A13300 Installation of Sinages 5 30-Mar-13 03-Apr-13 23-Apr-13 28-Apr-13 21
A13010 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 112 19-Sep-12 03-Feb-13 06-Nov-12 14-Apr-13 60
HVACHVAC 90 27-Sep-12 15-Jan-13 26-Nov-12 05-Mar-13 41
A13040 Condensate Pipe Installation 10 27-Sep-12 08-Oct-12 28-Nov-12 10-Dec-12 50
A13020 Duct Installation & Insulation 12 27-Sep-12 10-Oct-12 26-Nov-12 10-Dec-12 48
A13030 Chilled Water Pipe Installation & Insulation 12 27-Sep-12 10-Oct-12 26-Nov-12 10-Dec-12 48
A13050 FCU Installation 8 11-Oct-12 20-Oct-12 11-Dec-12 19-Dec-12 48
A13060 Air-Outlet Installation 6 09-Jan-13 15-Jan-13 27-Feb-13 05-Mar-13 41
ElectricalElectrical 99 19-Sep-12 17-Jan-13 06-Nov-12 05-Mar-13 39
A13070 Install Conduits in Wall 10 19-Sep-12 30-Sep-12 06-Nov-12 18-Nov-12 39
A13080 Install Cable Trays & Trunking 10 19-Sep-12 30-Sep-12 03-Dec-12 13-Dec-12 60
A13120 Cable Laying for Low Current System 6 25-Sep-12 01-Oct-12 31-Dec-12 07-Jan-13 79
A13130 Cable Laying for Power 6 25-Sep-12 01-Oct-12 31-Dec-12 07-Jan-13 79
A13090 Wiring for Lighting & Power 14 15-Oct-12 01-Nov-12 04-Dec-12 19-Dec-12 39
A13100 Wiring for Low Current System 14 15-Oct-12 01-Nov-12 04-Dec-12 19-Dec-12 39
A13110 DB installation,Dressing & Termination 14 24-Nov-12 10-Dec-12 10-Jan-13 27-Jan-13 39
A13160 Installation of Sockets 7 09-Jan-13 16-Jan-13 26-Feb-13 05-Mar-13 40
A13150 Installation of Lighting Fittings 8 09-Jan-13 17-Jan-13 25-Feb-13 05-Mar-13 39
PlumbingPlumbing 111 20-Sep-12 03-Feb-13 12-Nov-12 01-Apr-13 49
A13170 Drainge Pipes in Wall 10 20-Sep-12 01-Oct-12 12-Nov-12 24-Nov-12 43
A13240 Water Pipes in Wall 10 20-Sep-12 01-Oct-12 12-Nov-12 24-Nov-12 43
A13180 H/L Drainage Pipes Installation 10 27-Sep-12 08-Oct-12 27-Jan-13 06-Feb-13 98
A13190 H/L Hot&Cold Water Pipe Installation 10 27-Sep-12 08-Oct-12 27-Jan-13 06-Feb-13 98
A13200 Drainage&Water Pipes Testing 4 09-Oct-12 13-Oct-12 07-Feb-13 11-Feb-13 98
A13210 ElectricalWater Heater Installation 4 09-Oct-12 13-Oct-12 07-Feb-13 11-Feb-13 98
A13220 Floor Drain Fixning 8 16-Dec-12 24-Dec-12 25-Feb-13 05-Mar-13 59
A13230 Installation of Sanitaryware 8 26-Jan-13 03-Feb-13 24-Mar-13 01-Apr-13 49
Fire FighFire Fighting 97 27-Sep-12 23-Jan-13 05-Dec-12 14-Apr-13 68
A13280 Fire Fighting Pipe 10 27-Sep-12 08-Oct-12 05-Dec-12 16-Dec-12 55
A13270 Hydro Static Test for Pipes 3 09-Oct-12 11-Oct-12 17-Dec-12 19-Dec-12 55
A13260 Sprinkler Fixing 8 09-Jan-13 17-Jan-13 25-Feb-13 05-Mar-13 39
A13360 Fire Alarm Devices 8 09-Jan-13 17-Jan-13 24-Mar-13 01-Apr-13 62
A13250 Installation of Fire Extingusher&Blanket 5 19-Jan-13 23-Jan-13 09-Apr-13 14-Apr-13 68
2nd Floor2nd Floor 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Public AreaPublic Area 290 26-Sep-12 08-Sep-13 22-Dec-12 02-Oct-13 21
SwimmingSwimming Pool Deck 290 26-Sep-12 08-Sep-13 12-Feb-13 02-Oct-13 21
FinishingFinishing Works 290 26-Sep-12 08-Sep-13 12-Feb-13 02-Oct-13 21
A104710 Block Works 5 26-Sep-12 01-Oct-12 12-Feb-13 17-Feb-13 113
A104720 Plaster Works 7 02-Oct-12 09-Oct-12 18-Feb-13 25-Feb-13 113
A104730 1st Coat Paint 7 10-Oct-12 17-Oct-12 26-Feb-13 05-Mar-13 113
A104700 Installation of Metal Kitchen Cabinet , Bar , B.B.Q 4 18-Oct-12 22-Oct-12 24-Apr-13 28-Apr-13 155
A104790 Instaaltion of Wooden Pergola 15 18-Oct-12 06-Nov-12 06-Mar-13 23-Mar-13 113
A104760 Floor Tiles Work 18 07-Nov-12 28-Nov-12 24-Mar-13 13-Apr-13 113
A104740 Installation of Doors 3 29-Nov-12 03-Dec-12 14-Apr-13 16-Apr-13 113
A105010 Installation of Lightings 5 29-Nov-12 05-Dec-12 23-Apr-13 28-Apr-13 121
A104750 Doors Ironmongery 3 04-Dec-12 06-Dec-12 17-Apr-13 20-Apr-13 113
A104770 Final Coat Paint 5 08-Dec-12 12-Dec-12 21-Apr-13 25-Apr-13 113
A104780 Installation of Sinages 2 13-Dec-12 15-Dec-12 27-Apr-13 28-Apr-13 113
A104800 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
SwimmingSwimming Pool 75 26-Sep-12 26-Dec-12 31-Jan-13 28-Apr-13 103
FinishingFinishing Works 75 26-Sep-12 26-Dec-12 31-Jan-13 28-Apr-13 103
A104620 Pouring of Screed 5 26-Sep-12 01-Oct-12 31-Jan-13 05-Feb-13 103
A104630 Laying of Waterproofing 5 02-Oct-12 07-Oct-12 06-Feb-13 11-Feb-13 103
A104640 Pouring of Guniting 6 08-Oct-12 14-Oct-12 12-Feb-13 18-Feb-13 103
A104650 Laying of Waterproofing 5 15-Oct-12 20-Oct-12 19-Feb-13 24-Feb-13 103
A104660 Waterproofing Plastering 20 21-Oct-12 14-Nov-12 25-Feb-13 19-Mar-13 103
A104670 Fix the Tiles 25 17-Nov-12 16-Dec-12 20-Mar-13 17-Apr-13 103
A104680 Installation of Stairs - Gratings -Nozzles 9 17-Dec-12 26-Dec-12 18-Apr-13 28-Apr-13 103
A104690 Installatiof of Lights 9 17-Dec-12 26-Dec-12 18-Apr-13 28-Apr-13 103
PlantersPlanters 116 26-Sep-12 14-Feb-13 22-Dec-12 28-Apr-13 62
FinishingFinishing Works 116 26-Sep-12 14-Feb-13 22-Dec-12 28-Apr-13 62
A104810 Water Proof Membrane 12 26-Sep-12 09-Oct-12 22-Dec-12 05-Jan-13 70
A104820 Drainage Gravel 12 20-Oct-12 04-Nov-12 06-Jan-13 19-Jan-13 62
A104830 Geptextile Membrane 12 05-Nov-12 19-Nov-12 20-Jan-13 03-Feb-13 62
A104840 Sweet Soil 12 20-Nov-12 04-Dec-12 04-Feb-13 17-Feb-13 62
A107920 Installation of Lighitngs 30 05-Dec-12 09-Jan-13 25-Mar-13 28-Apr-13 92
A104850 Instllation of Planting Items 60 05-Dec-12 14-Feb-13 18-Feb-13 28-Apr-13 62
A105020 Installation of Irrigation System 60 05-Dec-12 14-Feb-13 18-Feb-13 28-Apr-13 62
StaircaseStaircase 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108
Stairs 1Stairs 1 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108
A110110 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108
A110120 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108
A110130 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
A110140 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
A110150 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108
A110160 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108
Stairs 2Stairs 2 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108
A110170 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108
A110180 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108
A110190 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
A110200 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Installation of Balustrades& Handrails
Doors Ironmongery
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
1st Coat Paint
Installation of Metal Kitchen Cabinet , Bar , B.B.Q
Instaaltion of Wooden Pergola
Floor Tiles Work
Installation of Doors
Installation of Lightings
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Pouring of Screed
Laying of Waterproofing
Pouring of Guniting
Laying of Waterproofing
Waterproofing Plastering
Fix the Tiles
Installation of Stairs - Gratings -Nozzles
Installatiof of Lights
Water Proof Membrane
Drainage Gravel
Geptextile Membrane
Sweet Soil
Installation of Lighitngs
Instllation of Planting Items
Installation of Irrigation System
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 69 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A110210 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108
A110220 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108
Stairs 3Stairs 3 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108
A110230 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108
A110240 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108
A110250 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
A110260 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108
A110270 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108
A110280 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108
Rooms AreaRooms Area 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Guest RooGuest Rooms 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21
FinishingFinishing Works 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Wet WorWet Works 78 26-Sep-12 30-Dec-12 21-Oct-12 20-Mar-13 67
A92010 Block Works 12 26-Sep-12 09-Oct-12 21-Oct-12 05-Nov-12 21
A91870 Plaster Works 31 18-Oct-12 26-Nov-12 14-Nov-12 22-Dec-12 21
A91880 Installation of Doors& Windows Sub-frame 22 04-Nov-12 29-Nov-12 24-Feb-13 20-Mar-13 92
A92340 Wall Tiles Work (Wet Area) 22 07-Nov-12 04-Dec-12 02-Jan-13 28-Jan-13 45
A91900 Installation of Suspended Ceiling Grid (Dry Area) 10 27-Nov-12 09-Dec-12 23-Dec-12 03-Jan-13 21
A91890 1st Coat Paint 22 05-Dec-12 30-Dec-12 30-Dec-12 26-Jan-13 21
Fisrt StaFisrt Stage Finishes 37 24-Dec-12 06-Feb-13 19-Jan-13 10-Apr-13 54
A91910 Suspended Ceiling Tiles (DryArea) 8 24-Dec-12 02-Jan-13 19-Jan-13 28-Jan-13 21
A91950 Installation of Wardrobes 7 30-Dec-12 07-Jan-13 26-Jan-13 02-Feb-13 21
A92330 Screed Works 15 03-Jan-13 20-Jan-13 29-Jan-13 14-Feb-13 21
A91940 Water Proofing for Wet Area 11 12-Jan-13 23-Jan-13 06-Feb-13 18-Feb-13 21
A92370 Installation of Suspended Ceiling Grid (Wet Area) 7 16-Jan-13 23-Jan-13 11-Feb-13 18-Feb-13 21
A91930 Floor & Wall Tiles Work (Dry Area) 12 12-Jan-13 26-Jan-13 28-Mar-13 10-Apr-13 64
A92360 Suspended Ceiling Tiles (Wet Area) 7 22-Jan-13 30-Jan-13 17-Feb-13 24-Feb-13 21
A92350 Floor Tiles Work (Wet Area) 8 29-Jan-13 06-Feb-13 16-Mar-13 24-Mar-13 39
Second SSecond Stage Finishes 18 04-Feb-13 24-Feb-13 21-Mar-13 17-Apr-13 45
A91960 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 21-Mar-13 28-Mar-13 39
A92020 Doors Ironmongery 7 04-Feb-13 11-Feb-13 03-Apr-13 10-Apr-13 50
A91990 Installation of Balustrades& Handrails 7 12-Feb-13 19-Feb-13 03-Apr-13 10-Apr-13 43
A92310 Installation of Toliets Accessories 12 09-Feb-13 21-Feb-13 04-Apr-13 17-Apr-13 47
A92000 Installation of Vanity Counter 10 12-Feb-13 23-Feb-13 31-Mar-13 10-Apr-13 40
A91970 Installation of Mirrors 11 12-Feb-13 24-Feb-13 30-Mar-13 10-Apr-13 39
Final StaFinal Stage Finishes 166 25-Feb-13 08-Sep-13 11-Apr-13 02-Oct-13 21
A91920 Final Coat Paint 8 25-Feb-13 05-Mar-13 11-Apr-13 20-Apr-13 39
A91980 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A92320 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A92030 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 113 06-Oct-12 20-Feb-13 06-Nov-12 20-Apr-13 50
HVACHVAC 97 10-Oct-12 06-Feb-13 28-Nov-12 05-Mar-13 23
A92060 Condensate Pipe Installation 10 10-Oct-12 21-Oct-12 01-Dec-12 12-Dec-12 41
A92040 Duct Installation & Insulation 12 10-Oct-12 23-Oct-12 28-Nov-12 12-Dec-12 39
A92050 Chilled Water Pipe Installation & Insulation 12 10-Oct-12 23-Oct-12 28-Nov-12 12-Dec-12 39
A92070 FCU Installation 8 24-Oct-12 04-Nov-12 13-Dec-12 22-Dec-12 39
A92080 Air-Outlet Installation 6 31-Jan-13 06-Feb-13 27-Feb-13 05-Mar-13 23
ElectricalElectrical 99 10-Oct-12 09-Feb-13 06-Nov-12 05-Mar-13 21
A92090 Install Conduits in Wall 14 10-Oct-12 28-Oct-12 06-Nov-12 22-Nov-12 21
A92100 Install Cable Trays & Trunking 14 10-Oct-12 28-Oct-12 04-Dec-12 19-Dec-12 43
A92140 Cable Laying for Low Current System 6 29-Oct-12 04-Nov-12 27-Dec-12 03-Jan-13 49
A92150 Cable Laying for Power 6 29-Oct-12 04-Nov-12 27-Dec-12 03-Jan-13 49
A92110 Wiring for Lighting & Power 8 07-Nov-12 17-Nov-12 15-Dec-12 23-Dec-12 30
A92120 Wiring for Low Current System 8 07-Nov-12 17-Nov-12 15-Dec-12 23-Dec-12 30
A92130 DB installation,Dressing & Termination 14 17-Dec-12 02-Jan-13 12-Jan-13 28-Jan-13 21
A92180 Installation of Sockets 7 31-Jan-13 07-Feb-13 26-Feb-13 05-Mar-13 22
A92170 Installation of Lighting Fittings 8 31-Jan-13 09-Feb-13 25-Feb-13 05-Mar-13 21
PlumbingPlumbing 113 06-Oct-12 20-Feb-13 06-Nov-12 10-Apr-13 42
A92190 Drainge Pipes in Wall 14 06-Oct-12 21-Oct-12 06-Nov-12 22-Nov-12 25
A92200 H/L Drainage Pipes Installation 10 10-Oct-12 21-Oct-12 22-Jan-13 03-Feb-13 84
A92210 H/L Hot&Cold Water Pipe Installation 10 10-Oct-12 21-Oct-12 22-Jan-13 03-Feb-13 84
A92260 Water Pipes in Wall 14 06-Oct-12 21-Oct-12 06-Nov-12 22-Nov-12 25
A92220 Drainage&Water Pipes Testing 4 22-Oct-12 28-Oct-12 04-Feb-13 07-Feb-13 84
A92230 ElectricalWater Heater Installation 6 22-Oct-12 30-Oct-12 04-Feb-13 10-Feb-13 84
A92240 Floor Drain Fixning 8 06-Jan-13 14-Jan-13 25-Feb-13 05-Mar-13 42
A92250 Installation of Sanitaryware 8 12-Feb-13 20-Feb-13 02-Apr-13 10-Apr-13 42
Fire FighFire Fighting 104 10-Oct-12 14-Feb-13 08-Dec-12 20-Apr-13 55
A92300 Fire Fighting Pipe 10 10-Oct-12 21-Oct-12 08-Dec-12 18-Dec-12 46
A92290 Hydro Static Test for Pipes 3 22-Oct-12 24-Oct-12 19-Dec-12 22-Dec-12 46
A92280 Sprinkler Fixing 8 31-Jan-13 09-Feb-13 25-Feb-13 05-Mar-13 21
A92380 Fire Alarm Devices 8 31-Jan-13 09-Feb-13 02-Apr-13 10-Apr-13 52
A92270 Installation of Fire Extingusher&Blanket 5 10-Feb-13 14-Feb-13 15-Apr-13 20-Apr-13 55
3rd Floor3rd Floor 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Public AreaPublic Area 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Lift LobbyLift Lobby - Corridor 153 09-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14
FinishingFinishing Works 153 09-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14
Wet WorWet Works 34 09-Oct-12 20-Nov-12 21-Jan-13 27-Mar-13 106
A95380 Block Works 8 09-Oct-12 17-Oct-12 21-Jan-13 30-Jan-13 84
A95320 Plaster Works 7 21-Oct-12 30-Oct-12 03-Feb-13 10-Feb-13 84
A95340 Installation of Suspended Ceiling Grid 6 05-Nov-12 11-Nov-12 16-Feb-13 21-Feb-13 84
A95350 Suspended Ceiling Tiles 6 12-Nov-12 19-Nov-12 23-Feb-13 28-Feb-13 84
A95630 MDF for Lift Lobby Wall 7 12-Nov-12 20-Nov-12 20-Mar-13 27-Mar-13 106
Fisrt StaFisrt Stage Finishes 12 21-Nov-12 05-Dec-12 28-Mar-13 06-Apr-13 102
A95610 Screed Works 3 21-Nov-12 24-Nov-12 28-Mar-13 31-Mar-13 106
A95330 1st Coat Paint 5 29-Nov-12 05-Dec-12 01-Apr-13 06-Apr-13 102
Second SSecond Stage Finishes 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119
A95360 Installation of Doors 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119
A95390 Doors Ironmongery 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119
Final StaFinal Stage Finishes 19 21-Mar-13 11-Apr-13 07-Apr-13 28-Apr-13 14
A95370 Installation of Carpets 10 21-Mar-13 01-Apr-13 07-Apr-13 17-Apr-13 14
A95620 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 18-Apr-13 25-Apr-13 14
A95600 Installation of Sinages 2 10-Apr-13 11-Apr-13 27-Apr-13 28-Apr-13 14
MEP WorkMEP Works 33 18-Oct-12 28-Nov-12 31-Jan-13 31-Mar-13 102
HVACHVAC 28 18-Oct-12 22-Nov-12 06-Feb-13 05-Mar-13 85
A95400 Duct Installation & Insulation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89
A95410 Chilled Water Pipe Installation & Insulation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89
A95420 Condensate Pipe Installation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89
A95430 FCU Installation 3 24-Oct-12 29-Oct-12 12-Feb-13 14-Feb-13 89
A95440 Air-Outlet Installation 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85
ElectricalElectrical 29 18-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84
A95450 Install Conduits in Wall 2 18-Oct-12 20-Oct-12 31-Jan-13 02-Feb-13 84
A95460 Install Cable Trays & Trunking 2 18-Oct-12 20-Oct-12 06-Feb-13 07-Feb-13 89
A95500 Cable Laying for Low Current System 2 21-Oct-12 22-Oct-12 20-Feb-13 21-Feb-13 99
A95510 Cable Laying for Power 3 21-Oct-12 23-Oct-12 19-Feb-13 21-Feb-13 98
A95470 Wiring for Lighting & Power 3 31-Oct-12 03-Nov-12 12-Feb-13 14-Feb-13 85
A95480 Wiring for Low Current System 4 31-Oct-12 04-Nov-12 11-Feb-13 14-Feb-13 84
A95490 DB installation,Dressing & Termination 3 12-Nov-12 14-Nov-12 26-Feb-13 28-Feb-13 87
A95530 Installation of Lighting Fittings 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85
A95540 Installation of Sockets 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84
PlumbingPlumbing 5 18-Oct-12 23-Oct-12 10-Feb-13 14-Feb-13 92
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 70 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A95550 H/L Hot&Cold Water Pipe Installation 5 18-Oct-12 23-Oct-12 10-Feb-13 14-Feb-13 92
Fire FighFire Fighting 33 18-Oct-12 28-Nov-12 06-Feb-13 31-Mar-13 102
A95590 Fire Fighting Pipe 4 18-Oct-12 22-Oct-12 06-Feb-13 10-Feb-13 89
A95580 Hydro Static Test for Pipes 4 23-Oct-12 29-Oct-12 11-Feb-13 14-Feb-13 89
A95570 Sprinkler Fixing 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84
A95640 Fire Alarm Devices 5 20-Nov-12 25-Nov-12 26-Mar-13 31-Mar-13 105
A95560 Installation of Fire Extingusher&Blanket 4 25-Nov-12 28-Nov-12 27-Mar-13 31-Mar-13 102
Electrical /Electrical / Telephone Room 35 09-Oct-12 21-Nov-12 31-Jan-13 28-Apr-13 132
FinishingFinishing Works 35 09-Oct-12 21-Nov-12 31-Jan-13 28-Apr-13 132
Wet WorWet Works 14 09-Oct-12 24-Oct-12 31-Jan-13 23-Apr-13 149
A97020 Block Works 3 09-Oct-12 11-Oct-12 31-Jan-13 03-Feb-13 92
A96980 Installation of Doors& Windows Sub-frame 1 15-Oct-12 15-Oct-12 23-Apr-13 23-Apr-13 157
A96970 Plaster Works 4 15-Oct-12 18-Oct-12 06-Feb-13 10-Feb-13 92
A96990 1st Coat Paint 3 22-Oct-12 24-Oct-12 13-Feb-13 16-Feb-13 92
Fisrt StaFisrt Stage Finishes 2 14-Nov-12 17-Nov-12 02-Apr-13 25-Apr-13 134
A97010 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A97030 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A97080 Epoxy Paint Works 2 14-Nov-12 17-Nov-12 02-Apr-13 03-Apr-13 115
Second SSecond Stage Finishes 2 18-Nov-12 19-Nov-12 04-Apr-13 06-Apr-13 115
A97000 Final Coat Paint 2 18-Nov-12 19-Nov-12 04-Apr-13 06-Apr-13 115
Final StaFinal Stage Finishes 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132
A97070 Installation of Sinages 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132
MEP WorkMEP Works 26 13-Oct-12 13-Nov-12 04-Feb-13 01-Apr-13 115
HVACHVAC 2 28-Oct-12 29-Oct-12 04-Mar-13 05-Mar-13 105
A97100 Air-Outlet Installation 2 28-Oct-12 29-Oct-12 04-Mar-13 05-Mar-13 105
ElectricalElectrical 26 13-Oct-12 13-Nov-12 04-Feb-13 05-Mar-13 92
A97040 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 04-Feb-13 05-Feb-13 92
A97050 Wiring for Lighting & Power 2 20-Oct-12 21-Oct-12 11-Feb-13 12-Feb-13 92
A114800 Installation of SMDBs 7 28-Oct-12 04-Nov-12 24-Feb-13 03-Mar-13 98
A97060 Installation of Lighting Fittings 2 05-Nov-12 06-Nov-12 04-Mar-13 05-Mar-13 98
A114790 Installation of Telephone System 15 28-Oct-12 13-Nov-12 17-Feb-13 05-Mar-13 92
Fire FighFire Fighting 2 28-Oct-12 29-Oct-12 31-Mar-13 01-Apr-13 128
A97090 Fire Alarm Devices 2 28-Oct-12 29-Oct-12 31-Mar-13 01-Apr-13 128
House KeeHouse Keeping Room 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 09-Oct-12 10-Nov-12 20-Jan-13 25-Apr-13 139
A97430 Block Works 4 09-Oct-12 13-Oct-12 20-Jan-13 23-Jan-13 83
A97360 Installation of Doors& Windows Sub-frame 1 18-Oct-12 18-Oct-12 25-Apr-13 25-Apr-13 156
A97350 Plaster Works 4 18-Oct-12 22-Oct-12 30-Jan-13 03-Feb-13 83
A97380 Installation of Suspended Ceiling Grid 7 30-Oct-12 06-Nov-12 09-Feb-13 16-Feb-13 83
A97370 1st Coat Paint 3 07-Nov-12 10-Nov-12 17-Feb-13 19-Feb-13 83
Fisrt StaFisrt Stage Finishes 16 11-Nov-12 29-Nov-12 20-Feb-13 03-Apr-13 104
A97390 Suspended Ceiling Tiles 7 11-Nov-12 19-Nov-12 20-Feb-13 27-Feb-13 83
A97720 Screed Works 5 20-Nov-12 25-Nov-12 02-Mar-13 06-Mar-13 84
A97410 Floor Tiles Work 4 26-Nov-12 29-Nov-12 31-Mar-13 03-Apr-13 104
Second SSecond Stage Finishes 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123
A97420 Installation of Windows&Doors 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123
A97440 Doors Ironmongery 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123
Final StaFinal Stage Finishes 237 01-Dec-12 08-Sep-13 04-Apr-13 02-Oct-13 21
A97400 Final Coat Paint 2 01-Dec-12 03-Dec-12 04-Apr-13 06-Apr-13 104
A97710 Installation of Sinages 2 04-Dec-12 05-Dec-12 27-Apr-13 28-Apr-13 121
A97450 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 14-Oct-12 26-Nov-12 26-Jan-13 06-Apr-13 109
HVACHVAC 32 14-Oct-12 22-Nov-12 29-Jan-13 05-Mar-13 85
A97460 Duct Installation & Insulation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86
A97470 Chilled Water Pipe Installation & Insulation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86
A97480 Condensate Pipe Installation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86
A97490 FCU Installation 2 22-Oct-12 23-Oct-12 06-Feb-13 07-Feb-13 86
A97500 Air-Outlet Installation 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85
ElectricalElectrical 34 14-Oct-12 25-Nov-12 26-Jan-13 05-Mar-13 83
A97510 Install Conduits in Wall 4 14-Oct-12 17-Oct-12 26-Jan-13 29-Jan-13 83
A97520 Install Cable Trays & Trunking 4 14-Oct-12 17-Oct-12 28-Jan-13 31-Jan-13 85
A97560 Cable Laying for Power 4 18-Oct-12 22-Oct-12 12-Feb-13 16-Feb-13 94
A97530 Wiring for Lighting & Power 4 23-Oct-12 29-Oct-12 04-Feb-13 07-Feb-13 83
A97580 Installation of Sockets 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85
A97570 Installation of Lighting Fittings 5 20-Nov-12 25-Nov-12 28-Feb-13 05-Mar-13 83
PlumbingPlumbing 33 14-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84
A97600 H/L Drainage Pipes Installation 3 14-Oct-12 16-Oct-12 31-Jan-13 03-Feb-13 88
A97610 H/L Hot&Cold Water Pipe Installation 3 14-Oct-12 16-Oct-12 31-Jan-13 03-Feb-13 88
A97620 Drainage&Water Pipes Testing 3 17-Oct-12 20-Oct-12 04-Feb-13 06-Feb-13 88
A97630 ElectricalWater Heater Installation 4 17-Oct-12 21-Oct-12 04-Feb-13 07-Feb-13 88
A97640 Floor Drain Fixning 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84
Fire FighFire Fighting 35 14-Oct-12 26-Nov-12 31-Jan-13 06-Apr-13 109
A97700 Fire Fighting Pipe 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88
A97690 Hydro Static Test for Pipes 3 18-Oct-12 21-Oct-12 05-Feb-13 07-Feb-13 88
A97680 Sprinkler Fixing 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84
A97730 Fire Alarm Devices 4 20-Nov-12 24-Nov-12 31-Mar-13 03-Apr-13 109
A97670 Installation of Fire Extingusher&Blanket 2 25-Nov-12 26-Nov-12 04-Apr-13 06-Apr-13 109
Storage RoStorage Room 45 09-Oct-12 04-Dec-12 20-Jan-13 28-Apr-13 122
FinishingFinishing Works 45 09-Oct-12 04-Dec-12 20-Jan-13 28-Apr-13 122
Wet WorWet Works 29 09-Oct-12 13-Nov-12 20-Jan-13 23-Feb-13 83
A97160 Block Works 5 09-Oct-12 14-Oct-12 20-Jan-13 26-Jan-13 83
A97110 Plaster Works 5 20-Oct-12 24-Oct-12 31-Jan-13 05-Feb-13 83
A97130 Installation of Suspended Ceiling Grid 5 01-Nov-12 06-Nov-12 11-Feb-13 16-Feb-13 83
A97120 1st Coat Paint 6 07-Nov-12 13-Nov-12 17-Feb-13 23-Feb-13 83
Fisrt StaFisrt Stage Finishes 13 14-Nov-12 29-Nov-12 24-Feb-13 04-Apr-13 105
A97140 Suspended Ceiling Tiles 5 14-Nov-12 20-Nov-12 24-Feb-13 28-Feb-13 83
A97310 Epoxy Paint Works 2 28-Nov-12 29-Nov-12 03-Apr-13 04-Apr-13 105
Second SSecond Stage Finishes 1 01-Dec-12 01-Dec-12 06-Apr-13 25-Apr-13 122
A97150 Installation of Doors 1 01-Dec-12 01-Dec-12 06-Apr-13 06-Apr-13 105
A97170 Doors Ironmongery 1 01-Dec-12 01-Dec-12 25-Apr-13 25-Apr-13 122
Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122
A97300 Installation of Sinages 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122
MEP WorkMEP Works 35 15-Oct-12 27-Nov-12 27-Jan-13 02-Apr-13 105
HVACHVAC 32 15-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84
A97180 Duct Installation & Insulation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87
A97190 Chilled Water Pipe Installation & Insulation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87
A97200 Condensate Pipe Installation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87
A97210 FCU Installation 2 23-Oct-12 24-Oct-12 09-Feb-13 10-Feb-13 87
A97220 Air-Outlet Installation 3 21-Nov-12 24-Nov-12 03-Mar-13 05-Mar-13 84
ElectricalElectrical 33 15-Oct-12 25-Nov-12 27-Jan-13 05-Mar-13 83
A97230 Install Conduits in Wall 4 15-Oct-12 18-Oct-12 27-Jan-13 30-Jan-13 83
A97240 Wiring for Lighting & Power 4 28-Oct-12 31-Oct-12 06-Feb-13 10-Feb-13 83
A97250 Installation of Lighting Fittings 4 21-Nov-12 25-Nov-12 02-Mar-13 05-Mar-13 83
PlumbingPlumbing 8 15-Oct-12 23-Oct-12 02-Feb-13 10-Feb-13 88
A97330 H/L Hot&Cold Water Pipe Installation 4 15-Oct-12 18-Oct-12 02-Feb-13 05-Feb-13 88
A97740 H/L Drainage Pipes Installation 4 15-Oct-12 18-Oct-12 02-Feb-13 05-Feb-13 88
A97340 Water Pipes Testing 4 20-Oct-12 23-Oct-12 06-Feb-13 10-Feb-13 88
A97750 Drainage&Water Pipes Testing 4 20-Oct-12 23-Oct-12 06-Feb-13 10-Feb-13 88
Fire FighFire Fighting 35 15-Oct-12 27-Nov-12 03-Feb-13 02-Apr-13 105
A97290 Fire Fighting Pipe 4 15-Oct-12 18-Oct-12 03-Feb-13 06-Feb-13 89
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 71 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A97280 Hydro Static Test for Pipes 3 20-Oct-12 22-Oct-12 07-Feb-13 10-Feb-13 89
A97270 Sprinkler Fixing 4 21-Nov-12 25-Nov-12 02-Mar-13 05-Mar-13 83
A97320 Fire Alarm Devices 4 21-Nov-12 25-Nov-12 30-Mar-13 02-Apr-13 107
A97260 Installation of Fire Extingusher&Blanket 2 26-Nov-12 27-Nov-12 01-Apr-13 02-Apr-13 105
StaircaseStaircase 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79
Stairs 1Stairs 1 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79
A110290 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79
A110300 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79
A110310 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110320 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110330 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79
A110340 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79
Stairs 2Stairs 2 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79
A110350 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79
A110360 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79
A110370 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110380 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110390 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79
A110400 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79
Stairs 3Stairs 3 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79
A110410 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79
A110420 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79
A110430 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110440 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79
A110450 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79
A110460 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79
Rooms AreaRooms Area 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Guest RooGuest Rooms 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
FinishingFinishing Works 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21
Wet WorWet Works 78 09-Oct-12 13-Jan-13 21-Oct-12 06-Mar-13 44
A92530 Block Works 12 09-Oct-12 22-Oct-12 21-Oct-12 05-Nov-12 10
A92390 Plaster Works 31 03-Nov-12 10-Dec-12 14-Nov-12 22-Dec-12 10
A92400 Installation of Doors& Windows Sub-frame 22 18-Nov-12 13-Dec-12 10-Feb-13 06-Mar-13 69
A92860 Wall Tiles Work (Wet Area) 22 21-Nov-12 17-Dec-12 02-Jan-13 28-Jan-13 34
A92420 Installation of Suspended Ceiling Grid (Dry Area) 10 11-Dec-12 22-Dec-12 23-Dec-12 03-Jan-13 10
A92410 1st Coat Paint 22 18-Dec-12 13-Jan-13 30-Dec-12 26-Jan-13 10
Fisrt StaFisrt Stage Finishes 37 07-Jan-13 19-Feb-13 19-Jan-13 27-Mar-13 31
A92430 Suspended Ceiling Tiles (DryArea) 8 07-Jan-13 15-Jan-13 19-Jan-13 28-Jan-13 10
A92470 Installation of Wardrobes 7 13-Jan-13 20-Jan-13 26-Jan-13 02-Feb-13 10
A92850 Screed Works 15 16-Jan-13 03-Feb-13 29-Jan-13 14-Feb-13 10
A92460 Water Proofing for Wet Area 11 26-Jan-13 06-Feb-13 06-Feb-13 18-Feb-13 10
A92890 Installation of Suspended Ceiling Grid (Wet Area) 7 30-Jan-13 06-Feb-13 11-Feb-13 18-Feb-13 10
A92450 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 14-Mar-13 27-Mar-13 41
A92880 Suspended Ceiling Tiles (Wet Area) 7 05-Feb-13 12-Feb-13 17-Feb-13 24-Feb-13 10
A92870 Floor Tiles Work (Wet Area) 8 11-Feb-13 19-Feb-13 03-Mar-13 11-Mar-13 17
Second SSecond Stage Finishes 18 16-Feb-13 07-Mar-13 07-Mar-13 03-Apr-13 23
A92480 Installation of Windows&Doors 7 16-Feb-13 23-Feb-13 07-Mar-13 14-Mar-13 17
A92540 Doors Ironmongery 7 16-Feb-13 23-Feb-13 20-Mar-13 27-Mar-13 28
A92510 Installation of Balustrades& Handrails 7 24-Feb-13 03-Mar-13 20-Mar-13 27-Mar-13 21
A92830 Installation of Toliets Accessories 12 20-Feb-13 05-Mar-13 21-Mar-13 03-Apr-13 25
A92520 Installation of Vanity Counter 10 24-Feb-13 06-Mar-13 17-Mar-13 27-Mar-13 18
A92490 Installation of Mirrors 11 24-Feb-13 07-Mar-13 16-Mar-13 27-Mar-13 17
Final StaFinal Stage Finishes 156 09-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21
A92440 Final Coat Paint 8 09-Mar-13 17-Mar-13 28-Mar-13 06-Apr-13 17
A92500 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A92840 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26
A92550 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 112 18-Oct-12 04-Mar-13 06-Nov-12 06-Apr-13 28
HVACHVAC 97 23-Oct-12 19-Feb-13 28-Nov-12 05-Mar-13 12
A92580 Condensate Pipe Installation 10 23-Oct-12 05-Nov-12 01-Dec-12 12-Dec-12 30
A92560 Duct Installation & Insulation 12 23-Oct-12 07-Nov-12 28-Nov-12 12-Dec-12 28
A92570 Chilled Water Pipe Installation & Insulation 12 23-Oct-12 07-Nov-12 28-Nov-12 12-Dec-12 28
A92590 FCU Installation 8 08-Nov-12 18-Nov-12 13-Dec-12 22-Dec-12 28
A92600 Air-Outlet Installation 6 13-Feb-13 19-Feb-13 27-Feb-13 05-Mar-13 12
ElectricalElectrical 99 23-Oct-12 21-Feb-13 06-Nov-12 05-Mar-13 10
A92610 Install Conduits in Wall 14 23-Oct-12 10-Nov-12 06-Nov-12 22-Nov-12 10
A92620 Install Cable Trays & Trunking 14 23-Oct-12 10-Nov-12 04-Dec-12 19-Dec-12 32
A92660 Cable Laying for Low Current System 6 11-Nov-12 18-Nov-12 27-Dec-12 03-Jan-13 38
A92670 Cable Laying for Power 6 11-Nov-12 18-Nov-12 27-Dec-12 03-Jan-13 38
A92640 Wiring for Low Current System 8 18-Nov-12 26-Nov-12 17-Dec-12 25-Dec-12 24
A92630 Wiring for Lighting & Power 8 21-Nov-12 29-Nov-12 15-Dec-12 23-Dec-12 19
A92650 DB installation,Dressing & Termination 14 30-Dec-12 15-Jan-13 12-Jan-13 28-Jan-13 10
A92700 Installation of Sockets 7 13-Feb-13 20-Feb-13 26-Feb-13 05-Mar-13 11
A92690 Installation of Lighting Fittings 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10
PlumbingPlumbing 112 18-Oct-12 04-Mar-13 08-Nov-12 27-Mar-13 20
A92710 Drainge Pipes in Wall 14 18-Oct-12 05-Nov-12 08-Nov-12 25-Nov-12 16
A92720 H/L Drainage Pipes Installation 10 23-Oct-12 05-Nov-12 22-Jan-13 03-Feb-13 73
A92730 H/L Hot&Cold Water Pipe Installation 10 23-Oct-12 05-Nov-12 22-Jan-13 03-Feb-13 73
A92780 Water Pipes in Wall 14 18-Oct-12 05-Nov-12 08-Nov-12 25-Nov-12 16
A92740 Drainage&Water Pipes Testing 4 06-Nov-12 10-Nov-12 04-Feb-13 07-Feb-13 73
A92750 ElectricalWater Heater Installation 6 06-Nov-12 12-Nov-12 04-Feb-13 10-Feb-13 73
A92760 Floor Drain Fixning 8 19-Jan-13 28-Jan-13 25-Feb-13 05-Mar-13 31
A92770 Installation of Sanitaryware 8 24-Feb-13 04-Mar-13 19-Mar-13 27-Mar-13 20
Fire FighFire Fighting 104 23-Oct-12 27-Feb-13 08-Dec-12 06-Apr-13 32
A92820 Fire Fighting Pipe 10 23-Oct-12 05-Nov-12 08-Dec-12 18-Dec-12 35
A92810 Hydro Static Test for Pipes 3 06-Nov-12 08-Nov-12 19-Dec-12 22-Dec-12 35
A92800 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10
A92900 Fire Alarm Devices 8 13-Feb-13 21-Feb-13 19-Mar-13 27-Mar-13 29
A92790 Installation of Fire Extingusher&Blanket 5 23-Feb-13 27-Feb-13 01-Apr-13 06-Apr-13 32
4th Floor4th Floor 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21
Public AreaPublic Area 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Lift LobbyLift Lobby - Corridor 143 21-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14
FinishingFinishing Works 143 21-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14
Wet WorWet Works 34 21-Oct-12 03-Dec-12 21-Jan-13 27-Mar-13 96
A96700 Block Works 8 21-Oct-12 31-Oct-12 21-Jan-13 30-Jan-13 74
A96640 Plaster Works 7 04-Nov-12 11-Nov-12 03-Feb-13 10-Feb-13 74
A96660 Installation of Suspended Ceiling Grid 6 18-Nov-12 24-Nov-12 16-Feb-13 21-Feb-13 74
A96670 Suspended Ceiling Tiles 6 25-Nov-12 01-Dec-12 23-Feb-13 28-Feb-13 74
A96950 MDF for Lift Lobby Wall 7 25-Nov-12 03-Dec-12 20-Mar-13 27-Mar-13 96
Fisrt StaFisrt Stage Finishes 12 04-Dec-12 17-Dec-12 28-Mar-13 06-Apr-13 92
A96930 Screed Works 3 04-Dec-12 06-Dec-12 28-Mar-13 31-Mar-13 96
A96650 1st Coat Paint 5 12-Dec-12 17-Dec-12 01-Apr-13 06-Apr-13 92
Second SSecond Stage Finishes 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109
A96680 Installation of Doors 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109
A96710 Doors Ironmongery 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109
Final StaFinal Stage Finishes 19 21-Mar-13 11-Apr-13 07-Apr-13 28-Apr-13 14
A96690 Installation of Carpets 10 21-Mar-13 01-Apr-13 07-Apr-13 17-Apr-13 14
A96940 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 18-Apr-13 25-Apr-13 14
A96920 Installation of Sinages 2 10-Apr-13 11-Apr-13 27-Apr-13 28-Apr-13 14
MEP WorkMEP Works 33 01-Nov-12 11-Dec-12 31-Jan-13 31-Mar-13 92
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Low Current System
Wiring for Lighting & Power
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 72 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
HVACHVAC 28 01-Nov-12 05-Dec-12 06-Feb-13 05-Mar-13 75
A96720 Duct Installation & Insulation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79
A96730 Chilled Water Pipe Installation & Insulation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79
A96740 Condensate Pipe Installation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79
A96750 FCU Installation 3 07-Nov-12 10-Nov-12 12-Feb-13 14-Feb-13 79
A96760 Air-Outlet Installation 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75
ElectricalElectrical 29 01-Nov-12 06-Dec-12 31-Jan-13 05-Mar-13 74
A96770 Install Conduits in Wall 2 01-Nov-12 03-Nov-12 31-Jan-13 02-Feb-13 74
A96780 Install Cable Trays & Trunking 2 01-Nov-12 03-Nov-12 06-Feb-13 07-Feb-13 79
A96820 Cable Laying for Low Current System 2 04-Nov-12 05-Nov-12 20-Feb-13 21-Feb-13 89
A96830 Cable Laying for Power 3 04-Nov-12 06-Nov-12 19-Feb-13 21-Feb-13 88
A96790 Wiring for Lighting & Power 3 12-Nov-12 14-Nov-12 12-Feb-13 14-Feb-13 75
A96800 Wiring for Low Current System 4 12-Nov-12 17-Nov-12 11-Feb-13 14-Feb-13 74
A96810 DB installation,Dressing & Termination 3 25-Nov-12 27-Nov-12 26-Feb-13 28-Feb-13 77
A96850 Installation of Lighting Fittings 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75
A96860 Installation of Sockets 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74
PlumbingPlumbing 5 01-Nov-12 06-Nov-12 10-Feb-13 14-Feb-13 82
A96870 H/L Hot&Cold Water Pipe Installation 5 01-Nov-12 06-Nov-12 10-Feb-13 14-Feb-13 82
Fire FighFire Fighting 33 01-Nov-12 11-Dec-12 06-Feb-13 31-Mar-13 92
A96910 Fire Fighting Pipe 4 01-Nov-12 05-Nov-12 06-Feb-13 10-Feb-13 79
A96900 Hydro Static Test for Pipes 4 06-Nov-12 10-Nov-12 11-Feb-13 14-Feb-13 79
A96890 Sprinkler Fixing 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74
A96960 Fire Alarm Devices 5 03-Dec-12 08-Dec-12 26-Mar-13 31-Mar-13 95
A96880 Installation of Fire Extingusher&Blanket 4 08-Dec-12 11-Dec-12 27-Mar-13 31-Mar-13 92
Electrical /Electrical / Telephone Rooms 35 21-Oct-12 04-Dec-12 31-Jan-13 28-Apr-13 122
FinishingFinishing Works 35 21-Oct-12 04-Dec-12 31-Jan-13 28-Apr-13 122
Wet WorWet Works 14 21-Oct-12 07-Nov-12 31-Jan-13 23-Apr-13 139
A97810 Block Works 3 21-Oct-12 23-Oct-12 31-Jan-13 03-Feb-13 82
A97770 Installation of Doors& Windows Sub-frame 1 29-Oct-12 29-Oct-12 23-Apr-13 23-Apr-13 147
A97760 Plaster Works 4 29-Oct-12 01-Nov-12 06-Feb-13 10-Feb-13 82
A97780 1st Coat Paint 3 05-Nov-12 07-Nov-12 13-Feb-13 16-Feb-13 82
Fisrt StaFisrt Stage Finishes 12 14-Nov-12 28-Nov-12 02-Apr-13 25-Apr-13 124
A97800 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A97820 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A97870 Epoxy Paint Works 2 27-Nov-12 28-Nov-12 02-Apr-13 03-Apr-13 105
Second SSecond Stage Finishes 2 29-Nov-12 01-Dec-12 04-Apr-13 06-Apr-13 105
A97790 Final Coat Paint 2 29-Nov-12 01-Dec-12 04-Apr-13 06-Apr-13 105
Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122
A97860 Installation of Sinages 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122
MEP WorkMEP Works 26 24-Oct-12 26-Nov-12 04-Feb-13 01-Apr-13 105
HVACHVAC 2 08-Nov-12 10-Nov-12 04-Mar-13 05-Mar-13 95
A97890 Air-Outlet Installation 2 08-Nov-12 10-Nov-12 04-Mar-13 05-Mar-13 95
ElectricalElectrical 26 24-Oct-12 26-Nov-12 04-Feb-13 05-Mar-13 82
A97830 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 04-Feb-13 05-Feb-13 82
A97840 Wiring for Lighting & Power 2 03-Nov-12 04-Nov-12 11-Feb-13 12-Feb-13 82
A114820 Installation of SMDBs 7 08-Nov-12 17-Nov-12 24-Feb-13 03-Mar-13 88
A97850 Installation of Lighting Fittings 2 18-Nov-12 19-Nov-12 04-Mar-13 05-Mar-13 88
A114810 Installation of Telephone System 15 08-Nov-12 26-Nov-12 17-Feb-13 05-Mar-13 82
Fire FighFire Fighting 2 08-Nov-12 10-Nov-12 31-Mar-13 01-Apr-13 118
A97880 Fire Alarm Devices 2 08-Nov-12 10-Nov-12 31-Mar-13 01-Apr-13 118
House KeeHouse Keeping Room 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 21-Oct-12 22-Nov-12 20-Jan-13 27-Apr-13 130
A98640 Block Works 4 21-Oct-12 24-Oct-12 20-Jan-13 23-Jan-13 73
A98570 Installation of Doors& Windows Sub-frame 1 01-Nov-12 01-Nov-12 27-Apr-13 27-Apr-13 147
A98560 Plaster Works 4 01-Nov-12 05-Nov-12 30-Jan-13 03-Feb-13 73
A98590 Installation of Suspended Ceiling Grid 7 11-Nov-12 19-Nov-12 09-Feb-13 16-Feb-13 73
A98580 1st Coat Paint 3 20-Nov-12 22-Nov-12 17-Feb-13 19-Feb-13 73
Fisrt StaFisrt Stage Finishes 16 24-Nov-12 12-Dec-12 20-Feb-13 03-Apr-13 94
A98600 Suspended Ceiling Tiles 7 24-Nov-12 01-Dec-12 20-Feb-13 27-Feb-13 73
A98880 Screed Works 5 03-Dec-12 08-Dec-12 02-Mar-13 06-Mar-13 74
A98620 Floor Tiles Work 4 09-Dec-12 12-Dec-12 31-Mar-13 03-Apr-13 94
Second SSecond Stage Finishes 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114
A98630 Installation of Windows&Doors 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114
A98650 Doors Ironmongery 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114
Final StaFinal Stage Finishes 227 13-Dec-12 08-Sep-13 04-Apr-13 02-Oct-13 21
A98610 Final Coat Paint 2 13-Dec-12 15-Dec-12 04-Apr-13 06-Apr-13 94
A98870 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111
A98660 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 28-Oct-12 09-Dec-12 26-Jan-13 06-Apr-13 99
HVACHVAC 32 28-Oct-12 05-Dec-12 29-Jan-13 05-Mar-13 75
A98670 Duct Installation & Insulation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76
A98680 Chilled Water Pipe Installation & Insulation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76
A98690 Condensate Pipe Installation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76
A98700 FCU Installation 2 05-Nov-12 06-Nov-12 06-Feb-13 07-Feb-13 76
A98710 Air-Outlet Installation 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75
ElectricalElectrical 34 28-Oct-12 08-Dec-12 26-Jan-13 05-Mar-13 73
A98720 Install Conduits in Wall 4 28-Oct-12 31-Oct-12 26-Jan-13 29-Jan-13 73
A98730 Install Cable Trays & Trunking 4 28-Oct-12 31-Oct-12 28-Jan-13 31-Jan-13 75
A98750 Cable Laying for Power 4 01-Nov-12 05-Nov-12 12-Feb-13 16-Feb-13 84
A98740 Wiring for Lighting & Power 4 06-Nov-12 10-Nov-12 04-Feb-13 07-Feb-13 73
A98770 Installation of Sockets 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75
A98760 Installation of Lighting Fittings 5 03-Dec-12 08-Dec-12 28-Feb-13 05-Mar-13 73
PlumbingPlumbing 33 28-Oct-12 06-Dec-12 31-Jan-13 05-Mar-13 74
A98780 H/L Drainage Pipes Installation 3 28-Oct-12 30-Oct-12 31-Jan-13 03-Feb-13 78
A98790 H/L Hot&Cold Water Pipe Installation 3 28-Oct-12 30-Oct-12 31-Jan-13 03-Feb-13 78
A98800 Drainage&Water Pipes Testing 3 31-Oct-12 03-Nov-12 04-Feb-13 06-Feb-13 78
A98810 ElectricalWater Heater Installation 4 31-Oct-12 04-Nov-12 04-Feb-13 07-Feb-13 78
A98820 Floor Drain Fixning 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74
Fire FighFire Fighting 35 28-Oct-12 09-Dec-12 31-Jan-13 06-Apr-13 99
A98860 Fire Fighting Pipe 4 28-Oct-12 31-Oct-12 31-Jan-13 04-Feb-13 78
A98850 Hydro Static Test for Pipes 3 01-Nov-12 04-Nov-12 05-Feb-13 07-Feb-13 78
A98840 Sprinkler Fixing 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74
A98890 Fire Alarm Devices 4 03-Dec-12 06-Dec-12 31-Mar-13 03-Apr-13 99
A98830 Installation of Fire Extingusher&Blanket 2 08-Dec-12 09-Dec-12 04-Apr-13 06-Apr-13 99
Storage RoStorage Room 46 21-Oct-12 17-Dec-12 20-Jan-13 28-Apr-13 111
FinishingFinishing Works 46 21-Oct-12 17-Dec-12 20-Jan-13 28-Apr-13 111
Wet WorWet Works 29 21-Oct-12 26-Nov-12 20-Jan-13 23-Feb-13 73
A98370 Block Works 5 21-Oct-12 28-Oct-12 20-Jan-13 26-Jan-13 73
A98320 Plaster Works 5 03-Nov-12 07-Nov-12 31-Jan-13 05-Feb-13 73
A98340 Installation of Suspended Ceiling Grid 5 13-Nov-12 19-Nov-12 11-Feb-13 16-Feb-13 73
A98330 1st Coat Paint 6 20-Nov-12 26-Nov-12 17-Feb-13 23-Feb-13 73
Fisrt StaFisrt Stage Finishes 13 27-Nov-12 12-Dec-12 24-Feb-13 03-Apr-13 94
A98350 Suspended Ceiling Tiles 5 27-Nov-12 03-Dec-12 24-Feb-13 28-Feb-13 73
A98520 Epoxy Paint Works 2 11-Dec-12 12-Dec-12 02-Apr-13 03-Apr-13 94
Second SSecond Stage Finishes 2 13-Dec-12 15-Dec-12 04-Apr-13 25-Apr-13 111
A98360 Installation of Doors 2 13-Dec-12 15-Dec-12 04-Apr-13 06-Apr-13 94
A98380 Doors Ironmongery 2 13-Dec-12 15-Dec-12 24-Apr-13 25-Apr-13 111
Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111
A98510 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111
MEP WorkMEP Works 35 29-Oct-12 10-Dec-12 27-Jan-13 01-Apr-13 94
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 73 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
HVACHVAC 32 29-Oct-12 06-Dec-12 31-Jan-13 05-Mar-13 74
A98390 Duct Installation & Insulation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77
A98400 Chilled Water Pipe Installation & Insulation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77
A98410 Condensate Pipe Installation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77
A98420 FCU Installation 2 06-Nov-12 07-Nov-12 09-Feb-13 10-Feb-13 77
A98430 Air-Outlet Installation 3 04-Dec-12 06-Dec-12 03-Mar-13 05-Mar-13 74
ElectricalElectrical 33 29-Oct-12 08-Dec-12 27-Jan-13 05-Mar-13 73
A98440 Install Conduits in Wall 4 29-Oct-12 01-Nov-12 27-Jan-13 30-Jan-13 73
A98450 Wiring for Lighting & Power 4 08-Nov-12 12-Nov-12 06-Feb-13 10-Feb-13 73
A98460 Installation of Lighting Fittings 4 04-Dec-12 08-Dec-12 02-Mar-13 05-Mar-13 73
PlumbingPlumbing 8 29-Oct-12 06-Nov-12 02-Feb-13 10-Feb-13 78
A98540 H/L Hot&Cold Water Pipe Installation 4 29-Oct-12 01-Nov-12 02-Feb-13 05-Feb-13 78
A98900 H/L Drainage Pipes Installation 4 29-Oct-12 01-Nov-12 02-Feb-13 05-Feb-13 78
A98550 Water Pipes Testing 4 03-Nov-12 06-Nov-12 06-Feb-13 10-Feb-13 78
A98910 Drainage&Water Pipes Testing 4 03-Nov-12 06-Nov-12 06-Feb-13 10-Feb-13 78
Fire FighFire Fighting 35 29-Oct-12 10-Dec-12 03-Feb-13 01-Apr-13 94
A98500 Fire Fighting Pipe 4 29-Oct-12 01-Nov-12 03-Feb-13 06-Feb-13 79
A98490 Hydro Static Test for Pipes 3 03-Nov-12 05-Nov-12 07-Feb-13 10-Feb-13 79
A98480 Sprinkler Fixing 4 04-Dec-12 08-Dec-12 02-Mar-13 05-Mar-13 73
A98530 Fire Alarm Devices 4 04-Dec-12 08-Dec-12 28-Mar-13 01-Apr-13 96
A98470 Installation of Fire Extingusher&Blanket 2 09-Dec-12 10-Dec-12 31-Mar-13 01-Apr-13 94
StaircaseStaircase 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68
Stairs 1Stairs 1 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68
A110470 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68
A110480 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68
A110490 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110500 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110510 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68
A110520 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68
Stairs 2Stairs 2 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68
A110530 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68
A110540 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68
A110550 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110560 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110570 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68
A110580 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68
Stairs 3Stairs 3 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68
A110590 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68
A110600 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68
A110610 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110620 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68
A110630 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68
A110640 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68
Rooms AreaRooms Area 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21
Guest RooGuest Rooms 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21
FinishingFinishing Works 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21
Wet WorWet Works 63 21-Oct-12 07-Jan-13 11-Nov-12 06-Mar-13 49
A93050 Block Works 12 21-Oct-12 05-Nov-12 11-Nov-12 25-Nov-12 16
A92910 Plaster Works 31 07-Nov-12 15-Dec-12 27-Nov-12 03-Jan-13 16
A92940 Installation of Suspended Ceiling Grid (Dry Area) 10 05-Dec-12 16-Dec-12 24-Dec-12 05-Jan-13 16
A92920 Installation of Doors& Windows Sub-frame 22 22-Nov-12 18-Dec-12 10-Feb-13 06-Mar-13 65
A93380 Wall Tiles Work (Wet Area) 22 26-Nov-12 22-Dec-12 03-Jan-13 29-Jan-13 31
A92930 1st Coat Paint 22 12-Dec-12 07-Jan-13 31-Dec-12 27-Jan-13 16
Fisrt StaFisrt Stage Finishes 36 31-Dec-12 12-Feb-13 20-Jan-13 27-Mar-13 37
A92950 Suspended Ceiling Tiles (DryArea) 8 31-Dec-12 09-Jan-13 20-Jan-13 29-Jan-13 16
A92990 Installation of Wardrobes 7 07-Jan-13 14-Jan-13 27-Jan-13 03-Feb-13 16
A93370 Screed Works 15 10-Jan-13 28-Jan-13 30-Jan-13 16-Feb-13 16
A92980 Water Proofing for Wet Area 11 19-Jan-13 31-Jan-13 07-Feb-13 19-Feb-13 16
A93410 Installation of Suspended Ceiling Grid (Wet Area) 7 23-Jan-13 31-Jan-13 12-Feb-13 19-Feb-13 16
A92970 Floor & Wall Tiles Work (Dry Area) 12 19-Jan-13 02-Feb-13 14-Mar-13 27-Mar-13 46
A93400 Suspended Ceiling Tiles (Wet Area) 7 29-Jan-13 05-Feb-13 17-Feb-13 24-Feb-13 16
A93390 Floor Tiles Work (Wet Area) 8 04-Feb-13 12-Feb-13 02-Mar-13 10-Mar-13 22
Second SSecond Stage Finishes 18 10-Feb-13 02-Mar-13 07-Mar-13 03-Apr-13 28
A93000 Installation of Windows&Doors 7 10-Feb-13 17-Feb-13 07-Mar-13 14-Mar-13 22
A93060 Doors Ironmongery 7 10-Feb-13 17-Feb-13 20-Mar-13 27-Mar-13 33
A93030 Installation of Balustrades& Handrails 7 18-Feb-13 25-Feb-13 20-Mar-13 27-Mar-13 26
A93350 Installation of Toliets Accessories 12 14-Feb-13 27-Feb-13 21-Mar-13 03-Apr-13 30
A93040 Installation of Vanity Counter 10 18-Feb-13 28-Feb-13 17-Mar-13 27-Mar-13 23
A93010 Installation of Mirrors 11 18-Feb-13 02-Mar-13 16-Mar-13 27-Mar-13 22
Final StaFinal Stage Finishes 161 03-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21
A92960 Final Coat Paint 8 03-Mar-13 11-Mar-13 28-Mar-13 06-Apr-13 22
A93020 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25
A93360 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25
A93070 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 99 30-Oct-12 26-Feb-13 19-Nov-12 06-Apr-13 33
HVACHVAC 78 06-Nov-12 09-Feb-13 29-Nov-12 05-Mar-13 21
A93100 Condensate Pipe Installation 10 06-Nov-12 18-Nov-12 03-Dec-12 13-Dec-12 21
A93080 Duct Installation & Insulation 12 06-Nov-12 20-Nov-12 29-Nov-12 13-Dec-12 19
A93090 Chilled Water Pipe Installation & Insulation 12 06-Nov-12 20-Nov-12 29-Nov-12 13-Dec-12 19
A93110 FCU Installation 8 21-Nov-12 29-Nov-12 15-Dec-12 23-Dec-12 19
A93120 Air-Outlet Installation 6 03-Feb-13 09-Feb-13 27-Feb-13 05-Mar-13 21
ElectricalElectrical 86 30-Oct-12 11-Feb-13 19-Nov-12 05-Mar-13 19
A93130 Install Conduits in Wall 14 30-Oct-12 14-Nov-12 19-Nov-12 05-Dec-12 16
A93140 Install Cable Trays & Trunking 14 06-Nov-12 22-Nov-12 12-Dec-12 27-Dec-12 29
A93180 Cable Laying for Low Current System 6 24-Nov-12 29-Nov-12 29-Dec-12 05-Jan-13 29
A93190 Cable Laying for Power 6 24-Nov-12 29-Nov-12 29-Dec-12 05-Jan-13 29
A93160 Wiring for Low Current System 8 22-Nov-12 01-Dec-12 18-Dec-12 26-Dec-12 21
A93150 Wiring for Lighting & Power 8 26-Nov-12 05-Dec-12 16-Dec-12 24-Dec-12 16
A93170 DB installation,Dressing & Termination 14 24-Dec-12 09-Jan-13 13-Jan-13 29-Jan-13 16
A93220 Installation of Sockets 7 03-Feb-13 10-Feb-13 26-Feb-13 05-Mar-13 20
A93210 Installation of Lighting Fittings 8 03-Feb-13 11-Feb-13 25-Feb-13 05-Mar-13 19
PlumbingPlumbing 97 01-Nov-12 26-Feb-13 21-Nov-12 27-Mar-13 25
A93230 Drainge Pipes in Wall 14 01-Nov-12 18-Nov-12 21-Nov-12 08-Dec-12 16
A93240 H/L Drainage Pipes Installation 10 06-Nov-12 18-Nov-12 23-Jan-13 04-Feb-13 64
A93250 H/L Hot&Cold Water Pipe Installation 10 06-Nov-12 18-Nov-12 23-Jan-13 04-Feb-13 64
A93300 Water Pipes in Wall 14 01-Nov-12 18-Nov-12 21-Nov-12 08-Dec-12 16
A93260 Drainage&Water Pipes Testing 4 19-Nov-12 22-Nov-12 05-Feb-13 09-Feb-13 64
A93270 ElectricalWater Heater Installation 6 19-Nov-12 25-Nov-12 05-Feb-13 11-Feb-13 64
A93280 Floor Drain Fixning 8 13-Jan-13 21-Jan-13 25-Feb-13 05-Mar-13 36
A93290 Installation of Sanitaryware 8 18-Feb-13 26-Feb-13 19-Mar-13 27-Mar-13 25
Fire FighFire Fighting 88 06-Nov-12 20-Feb-13 09-Dec-12 06-Apr-13 38
A93340 Fire Fighting Pipe 10 06-Nov-12 18-Nov-12 09-Dec-12 19-Dec-12 26
A93330 Hydro Static Test for Pipes 3 19-Nov-12 21-Nov-12 20-Dec-12 23-Dec-12 26
A93320 Sprinkler Fixing 8 06-Feb-13 14-Feb-13 25-Feb-13 05-Mar-13 16
A93420 Fire Alarm Devices 8 06-Feb-13 14-Feb-13 19-Mar-13 27-Mar-13 35
A93310 Installation of Fire Extingusher&Blanket 5 16-Feb-13 20-Feb-13 01-Apr-13 06-Apr-13 38
5th Floor5th Floor 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21
Public AreaPublic Area 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Lift LobbyLift Lobby - Corridor 135 05-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11
FinishingFinishing Works 135 05-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Low Current System
Wiring for Lighting & Power
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 74 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Wet WorWet Works 34 05-Nov-12 16-Dec-12 21-Jan-13 24-Mar-13 82
A95710 Block Works 8 05-Nov-12 13-Nov-12 21-Jan-13 30-Jan-13 63
A95650 Plaster Works 7 18-Nov-12 25-Nov-12 03-Feb-13 10-Feb-13 63
A95670 Installation of Suspended Ceiling Grid 6 01-Dec-12 08-Dec-12 16-Feb-13 21-Feb-13 63
A95680 Suspended Ceiling Tiles 6 09-Dec-12 15-Dec-12 23-Feb-13 28-Feb-13 63
A95960 MDF for Lift Lobby Wall 7 09-Dec-12 16-Dec-12 17-Mar-13 24-Mar-13 82
Fisrt StaFisrt Stage Finishes 12 17-Dec-12 30-Dec-12 25-Mar-13 02-Apr-13 78
A95940 Screed Works 3 17-Dec-12 19-Dec-12 25-Mar-13 27-Mar-13 82
A95660 1st Coat Paint 5 25-Dec-12 30-Dec-12 28-Mar-13 02-Apr-13 78
Second SSecond Stage Finishes 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98
A95690 Installation of Doors 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98
A95720 Doors Ironmongery 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98
Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11
A95700 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11
A95950 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11
A95930 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11
MEP WorkMEP Works 33 14-Nov-12 24-Dec-12 31-Jan-13 27-Mar-13 78
HVACHVAC 28 14-Nov-12 18-Dec-12 06-Feb-13 05-Mar-13 64
A95730 Duct Installation & Insulation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68
A95740 Chilled Water Pipe Installation & Insulation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68
A95750 Condensate Pipe Installation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68
A95760 FCU Installation 3 21-Nov-12 24-Nov-12 12-Feb-13 14-Feb-13 68
A95770 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
ElectricalElectrical 29 14-Nov-12 19-Dec-12 31-Jan-13 05-Mar-13 63
A95780 Install Conduits in Wall 2 14-Nov-12 17-Nov-12 31-Jan-13 02-Feb-13 63
A95790 Install Cable Trays & Trunking 2 14-Nov-12 17-Nov-12 06-Feb-13 07-Feb-13 68
A95830 Cable Laying for Low Current System 2 18-Nov-12 19-Nov-12 20-Feb-13 21-Feb-13 78
A95840 Cable Laying for Power 3 18-Nov-12 20-Nov-12 19-Feb-13 21-Feb-13 77
A95800 Wiring for Lighting & Power 3 26-Nov-12 28-Nov-12 12-Feb-13 14-Feb-13 64
A95810 Wiring for Low Current System 4 26-Nov-12 29-Nov-12 11-Feb-13 14-Feb-13 63
A95820 DB installation,Dressing & Termination 3 09-Dec-12 11-Dec-12 26-Feb-13 28-Feb-13 66
A95860 Installation of Lighting Fittings 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
A95870 Installation of Sockets 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63
PlumbingPlumbing 5 14-Nov-12 20-Nov-12 10-Feb-13 14-Feb-13 71
A95880 H/L Hot&Cold Water Pipe Installation 5 14-Nov-12 20-Nov-12 10-Feb-13 14-Feb-13 71
Fire FighFire Fighting 33 14-Nov-12 24-Dec-12 06-Feb-13 27-Mar-13 78
A95920 Fire Fighting Pipe 4 14-Nov-12 19-Nov-12 06-Feb-13 10-Feb-13 68
A95910 Hydro Static Test for Pipes 4 20-Nov-12 24-Nov-12 11-Feb-13 14-Feb-13 68
A95900 Sprinkler Fixing 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63
A95970 Fire Alarm Devices 5 16-Dec-12 20-Dec-12 23-Mar-13 27-Mar-13 81
A95890 Installation of Fire Extingusher&Blanket 4 20-Dec-12 24-Dec-12 24-Mar-13 27-Mar-13 78
Electrical /Electrical / Telephone Rooms 35 05-Nov-12 17-Dec-12 31-Jan-13 28-Apr-13 111
FinishingFinishing Works 35 05-Nov-12 17-Dec-12 31-Jan-13 28-Apr-13 111
Wet WorWet Works 14 05-Nov-12 21-Nov-12 31-Jan-13 23-Apr-13 128
A97950 Block Works 3 05-Nov-12 07-Nov-12 31-Jan-13 03-Feb-13 71
A97910 Installation of Doors& Windows Sub-frame 1 11-Nov-12 11-Nov-12 23-Apr-13 23-Apr-13 136
A97900 Plaster Works 4 11-Nov-12 14-Nov-12 06-Feb-13 10-Feb-13 71
A97920 1st Coat Paint 3 19-Nov-12 21-Nov-12 13-Feb-13 16-Feb-13 71
Fisrt StaFisrt Stage Finishes 23 14-Nov-12 12-Dec-12 30-Mar-13 25-Apr-13 113
A97940 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A97960 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134
A98010 Epoxy Paint Works 2 11-Dec-12 12-Dec-12 30-Mar-13 31-Mar-13 91
Second SSecond Stage Finishes 2 13-Dec-12 15-Dec-12 01-Apr-13 02-Apr-13 91
A97930 Final Coat Paint 2 13-Dec-12 15-Dec-12 01-Apr-13 02-Apr-13 91
Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111
A98000 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111
MEP WorkMEP Works 26 08-Nov-12 10-Dec-12 04-Feb-13 28-Mar-13 91
HVACHVAC 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84
A98030 Air-Outlet Installation 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84
ElectricalElectrical 26 08-Nov-12 10-Dec-12 04-Feb-13 05-Mar-13 71
A97970 Install Conduits in Wall 2 08-Nov-12 10-Nov-12 04-Feb-13 05-Feb-13 71
A97980 Wiring for Lighting & Power 2 17-Nov-12 18-Nov-12 11-Feb-13 12-Feb-13 71
A114830 Installation of SMDBs 7 22-Nov-12 29-Nov-12 24-Feb-13 03-Mar-13 77
A97990 Installation of Lighting Fittings 2 01-Dec-12 03-Dec-12 04-Mar-13 05-Mar-13 77
A114840 Installation of Telephone System 15 22-Nov-12 10-Dec-12 17-Feb-13 05-Mar-13 71
Fire FighFire Fighting 2 22-Nov-12 24-Nov-12 27-Mar-13 28-Mar-13 104
A98020 Fire Alarm Devices 2 22-Nov-12 24-Nov-12 27-Mar-13 28-Mar-13 104
House KeeHouse Keeping Room 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 05-Nov-12 06-Dec-12 20-Jan-13 27-Apr-13 119
A99240 Block Works 4 05-Nov-12 08-Nov-12 20-Jan-13 23-Jan-13 62
A99170 Installation of Doors& Windows Sub-frame 1 14-Nov-12 14-Nov-12 27-Apr-13 27-Apr-13 136
A99160 Plaster Works 4 14-Nov-12 19-Nov-12 30-Jan-13 03-Feb-13 62
A99190 Installation of Suspended Ceiling Grid 7 25-Nov-12 03-Dec-12 09-Feb-13 16-Feb-13 62
A99180 1st Coat Paint 3 04-Dec-12 06-Dec-12 17-Feb-13 19-Feb-13 62
Fisrt StaFisrt Stage Finishes 16 08-Dec-12 25-Dec-12 20-Feb-13 31-Mar-13 80
A99200 Suspended Ceiling Tiles 7 08-Dec-12 15-Dec-12 20-Feb-13 27-Feb-13 62
A99480 Screed Works 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62
A99220 Floor Tiles Work 4 22-Dec-12 25-Dec-12 27-Mar-13 31-Mar-13 80
Second SSecond Stage Finishes 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103
A99230 Installation of Windows&Doors 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103
A99250 Doors Ironmongery 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103
Final StaFinal Stage Finishes 216 26-Dec-12 08-Sep-13 01-Apr-13 02-Oct-13 21
A99210 Final Coat Paint 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80
A99470 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
A99260 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 10-Nov-12 22-Dec-12 26-Jan-13 02-Apr-13 85
HVACHVAC 32 10-Nov-12 18-Dec-12 29-Jan-13 05-Mar-13 64
A99270 Duct Installation & Insulation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65
A99280 Chilled Water Pipe Installation & Insulation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65
A99290 Condensate Pipe Installation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65
A99300 FCU Installation 2 19-Nov-12 20-Nov-12 06-Feb-13 07-Feb-13 65
A99310 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
ElectricalElectrical 34 10-Nov-12 20-Dec-12 26-Jan-13 05-Mar-13 62
A99320 Install Conduits in Wall 4 10-Nov-12 13-Nov-12 26-Jan-13 29-Jan-13 62
A99330 Install Cable Trays & Trunking 4 10-Nov-12 13-Nov-12 28-Jan-13 31-Jan-13 64
A99350 Cable Laying for Power 4 14-Nov-12 19-Nov-12 12-Feb-13 16-Feb-13 73
A99340 Wiring for Lighting & Power 4 20-Nov-12 24-Nov-12 04-Feb-13 07-Feb-13 62
A99370 Installation of Sockets 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64
A99360 Installation of Lighting Fittings 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62
PlumbingPlumbing 34 10-Nov-12 20-Dec-12 31-Jan-13 05-Mar-13 62
A99380 H/L Drainage Pipes Installation 3 10-Nov-12 12-Nov-12 31-Jan-13 03-Feb-13 67
A99390 H/L Hot&Cold Water Pipe Installation 3 10-Nov-12 12-Nov-12 31-Jan-13 03-Feb-13 67
A99400 Drainage&Water Pipes Testing 3 13-Nov-12 17-Nov-12 04-Feb-13 06-Feb-13 67
A99410 ElectricalWater Heater Installation 4 13-Nov-12 18-Nov-12 04-Feb-13 07-Feb-13 67
A99420 Floor Drain Fixning 3 18-Dec-12 20-Dec-12 03-Mar-13 05-Mar-13 62
Fire FighFire Fighting 35 10-Nov-12 22-Dec-12 31-Jan-13 02-Apr-13 85
A99460 Fire Fighting Pipe 4 10-Nov-12 13-Nov-12 31-Jan-13 04-Feb-13 67
A99450 Hydro Static Test for Pipes 3 14-Nov-12 18-Nov-12 05-Feb-13 07-Feb-13 67
A99440 Sprinkler Fixing 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63
A99490 Fire Alarm Devices 4 16-Dec-12 19-Dec-12 27-Mar-13 31-Mar-13 85
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 75 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A99430 Installation of Fire Extingusher&Blanket 2 20-Dec-12 22-Dec-12 01-Apr-13 02-Apr-13 85
Storage RoStorage Room 46 05-Nov-12 30-Dec-12 20-Jan-13 28-Apr-13 100
FinishingFinishing Works 46 05-Nov-12 30-Dec-12 20-Jan-13 28-Apr-13 100
Wet WorWet Works 29 05-Nov-12 10-Dec-12 20-Jan-13 23-Feb-13 62
A98970 Block Works 5 05-Nov-12 10-Nov-12 20-Jan-13 26-Jan-13 62
A98920 Plaster Works 5 17-Nov-12 21-Nov-12 31-Jan-13 05-Feb-13 62
A98940 Installation of Suspended Ceiling Grid 5 27-Nov-12 03-Dec-12 11-Feb-13 16-Feb-13 62
A98930 1st Coat Paint 6 04-Dec-12 10-Dec-12 17-Feb-13 23-Feb-13 62
Fisrt StaFisrt Stage Finishes 13 11-Dec-12 25-Dec-12 24-Feb-13 31-Mar-13 80
A98950 Suspended Ceiling Tiles 5 11-Dec-12 16-Dec-12 24-Feb-13 28-Feb-13 62
A99120 Epoxy Paint Works 2 24-Dec-12 25-Dec-12 30-Mar-13 31-Mar-13 80
Second SSecond Stage Finishes 2 26-Dec-12 27-Dec-12 01-Apr-13 25-Apr-13 100
A98960 Installation of Doors 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80
A98980 Doors Ironmongery 2 26-Dec-12 27-Dec-12 24-Apr-13 25-Apr-13 100
Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
A99110 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
MEP WorkMEP Works 35 11-Nov-12 23-Dec-12 27-Jan-13 28-Mar-13 80
HVACHVAC 32 11-Nov-12 19-Dec-12 31-Jan-13 05-Mar-13 63
A98990 Duct Installation & Insulation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66
A99000 Chilled Water Pipe Installation & Insulation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66
A99010 Condensate Pipe Installation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66
A99020 FCU Installation 2 20-Nov-12 21-Nov-12 09-Feb-13 10-Feb-13 66
A99030 Air-Outlet Installation 3 17-Dec-12 19-Dec-12 03-Mar-13 05-Mar-13 63
ElectricalElectrical 33 11-Nov-12 20-Dec-12 27-Jan-13 05-Mar-13 62
A99040 Install Conduits in Wall 4 11-Nov-12 14-Nov-12 27-Jan-13 30-Jan-13 62
A99050 Wiring for Lighting & Power 4 22-Nov-12 26-Nov-12 06-Feb-13 10-Feb-13 62
A99060 Installation of Lighting Fittings 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62
PlumbingPlumbing 8 11-Nov-12 20-Nov-12 02-Feb-13 10-Feb-13 67
A99140 H/L Hot&Cold Water Pipe Installation 4 11-Nov-12 14-Nov-12 02-Feb-13 05-Feb-13 67
A99500 H/L Drainage Pipes Installation 4 11-Nov-12 14-Nov-12 02-Feb-13 05-Feb-13 67
A99150 Water Pipes Testing 4 17-Nov-12 20-Nov-12 06-Feb-13 10-Feb-13 67
A99510 Drainage&Water Pipes Testing 4 17-Nov-12 20-Nov-12 06-Feb-13 10-Feb-13 67
Fire FighFire Fighting 35 11-Nov-12 23-Dec-12 03-Feb-13 28-Mar-13 80
A99100 Fire Fighting Pipe 4 11-Nov-12 14-Nov-12 03-Feb-13 06-Feb-13 68
A99090 Hydro Static Test for Pipes 3 17-Nov-12 19-Nov-12 07-Feb-13 10-Feb-13 68
A99080 Sprinkler Fixing 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62
A99130 Fire Alarm Devices 4 17-Dec-12 20-Dec-12 25-Mar-13 28-Mar-13 82
A99070 Installation of Fire Extingusher&Blanket 2 22-Dec-12 23-Dec-12 27-Mar-13 28-Mar-13 80
StaircaseStaircase 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54
Stairs 1Stairs 1 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54
A110650 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54
A110660 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54
A110670 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110680 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110690 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54
A110700 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54
Stairs 2Stairs 2 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54
A110710 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54
A110720 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54
A110730 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110740 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110750 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54
A110760 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54
Stairs 3Stairs 3 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54
A110770 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54
A110780 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54
A110790 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110800 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54
A110810 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54
A110820 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54
Rooms AreaRooms Area 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21
Guest RooGuest Rooms 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21
FinishingFinishing Works 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21
Wet WorWet Works 63 05-Nov-12 20-Jan-13 18-Nov-12 03-Mar-13 35
A93570 Block Works 12 05-Nov-12 19-Nov-12 18-Nov-12 01-Dec-12 10
A93430 Plaster Works 31 21-Nov-12 27-Dec-12 04-Dec-12 09-Jan-13 10
A93460 Installation of Suspended Ceiling Grid (Dry Area) 10 18-Dec-12 29-Dec-12 30-Dec-12 10-Jan-13 10
A93440 Installation of Doors& Windows Sub-frame 22 06-Dec-12 31-Dec-12 06-Feb-13 03-Mar-13 51
A93900 Wall Tiles Work (Wet Area) 22 10-Dec-12 05-Jan-13 07-Jan-13 02-Feb-13 23
A93450 1st Coat Paint 22 25-Dec-12 20-Jan-13 07-Jan-13 02-Feb-13 10
Fisrt StaFisrt Stage Finishes 34 12-Jan-13 20-Feb-13 23-Jan-13 24-Mar-13 27
A93470 Suspended Ceiling Tiles (DryArea) 8 12-Jan-13 20-Jan-13 23-Jan-13 02-Feb-13 10
A93510 Installation of Wardrobes 7 17-Jan-13 26-Jan-13 30-Jan-13 06-Feb-13 10
A93890 Screed Works 15 21-Jan-13 07-Feb-13 03-Feb-13 19-Feb-13 10
A93500 Water Proofing for Wet Area 11 29-Jan-13 10-Feb-13 10-Feb-13 21-Feb-13 10
A93930 Installation of Suspended Ceiling Grid (Wet Area) 7 03-Feb-13 10-Feb-13 14-Feb-13 21-Feb-13 10
A93490 Floor & Wall Tiles Work (Dry Area) 12 30-Jan-13 12-Feb-13 11-Mar-13 24-Mar-13 34
A93920 Suspended Ceiling Tiles (Wet Area) 7 07-Feb-13 14-Feb-13 19-Feb-13 26-Feb-13 10
A93910 Floor Tiles Work (Wet Area) 8 12-Feb-13 20-Feb-13 27-Feb-13 07-Mar-13 13
Second SSecond Stage Finishes 18 17-Feb-13 09-Mar-13 04-Mar-13 28-Apr-13 43
A93520 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 04-Mar-13 11-Mar-13 13
A93580 Doors Ironmongery 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54
A93550 Installation of Balustrades& Handrails 7 25-Feb-13 04-Mar-13 17-Mar-13 24-Mar-13 17
A93870 Installation of Toliets Accessories 12 21-Feb-13 06-Mar-13 18-Mar-13 31-Mar-13 21
A93560 Installation of Vanity Counter 10 25-Feb-13 07-Mar-13 13-Mar-13 24-Mar-13 14
A93530 Installation of Mirrors 11 25-Feb-13 09-Mar-13 12-Mar-13 24-Mar-13 13
Final StaFinal Stage Finishes 155 10-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21
A93480 Final Coat Paint 8 10-Mar-13 18-Mar-13 25-Mar-13 02-Apr-13 13
A93540 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25
A93880 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25
A93590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 94 12-Nov-12 05-Mar-13 25-Nov-12 02-Apr-13 24
HVACHVAC 74 20-Nov-12 17-Feb-13 06-Dec-12 05-Mar-13 14
A93620 Condensate Pipe Installation 10 20-Nov-12 01-Dec-12 09-Dec-12 19-Dec-12 15
A93600 Duct Installation & Insulation 12 20-Nov-12 04-Dec-12 06-Dec-12 19-Dec-12 13
A93610 Chilled Water Pipe Installation & Insulation 12 20-Nov-12 04-Dec-12 06-Dec-12 19-Dec-12 13
A93630 FCU Installation 8 05-Dec-12 13-Dec-12 20-Dec-12 29-Dec-12 13
A93640 Air-Outlet Installation 6 11-Feb-13 17-Feb-13 27-Feb-13 05-Mar-13 14
ElectricalElectrical 86 12-Nov-12 24-Feb-13 25-Nov-12 02-Apr-13 32
A93650 Install Conduits in Wall 14 12-Nov-12 28-Nov-12 25-Nov-12 11-Dec-12 10
A93660 Install Cable Trays & Trunking 14 20-Nov-12 06-Dec-12 18-Dec-12 03-Jan-13 23
A93700 Cable Laying for Low Current System 6 08-Dec-12 13-Dec-12 05-Jan-13 10-Jan-13 23
A93710 Cable Laying for Power 6 08-Dec-12 13-Dec-12 05-Jan-13 10-Jan-13 23
A93680 Wiring for Low Current System 8 06-Dec-12 15-Dec-12 24-Dec-12 02-Jan-13 15
A93670 Wiring for Lighting & Power 8 10-Dec-12 18-Dec-12 22-Dec-12 30-Dec-12 10
A93690 DB installation,Dressing & Termination 12 07-Jan-13 20-Jan-13 19-Jan-13 02-Feb-13 10
A93740 Installation of Sockets 7 13-Feb-13 20-Feb-13 26-Feb-13 05-Mar-13 11
A93730 Installation of Lighting Fittings 8 16-Feb-13 24-Feb-13 25-Mar-13 02-Apr-13 32
PlumbingPlumbing 92 14-Nov-12 05-Mar-13 27-Nov-12 24-Mar-13 16
A93750 Drainge Pipes in Wall 14 14-Nov-12 01-Dec-12 27-Nov-12 13-Dec-12 10
A93760 H/L Drainage Pipes Installation 10 20-Nov-12 01-Dec-12 27-Jan-13 06-Feb-13 55
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Low Current System
Wiring for Lighting & Power
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 76 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A93770 H/L Hot&Cold Water Pipe Installation 10 20-Nov-12 01-Dec-12 27-Jan-13 06-Feb-13 55
A93820 Water Pipes in Wall 14 14-Nov-12 01-Dec-12 27-Nov-12 13-Dec-12 10
A93780 Drainage&Water Pipes Testing 4 03-Dec-12 06-Dec-12 07-Feb-13 11-Feb-13 55
A93790 ElectricalWater Heater Installation 6 03-Dec-12 09-Dec-12 07-Feb-13 13-Feb-13 55
A93800 Floor Drain Fixning 8 23-Jan-13 02-Feb-13 24-Feb-13 04-Mar-13 26
A93810 Installation of Sanitaryware 8 25-Feb-13 05-Mar-13 16-Mar-13 24-Mar-13 16
Fire FighFire Fighting 80 20-Nov-12 24-Feb-13 09-Dec-12 02-Apr-13 32
A93860 Fire Fighting Pipe 10 20-Nov-12 01-Dec-12 09-Dec-12 19-Dec-12 15
A93850 Hydro Static Test for Pipes 8 03-Dec-12 11-Dec-12 20-Dec-12 29-Dec-12 15
A93830 Installation of Fire Extingusher&Blanket 5 13-Feb-13 18-Feb-13 28-Mar-13 02-Apr-13 37
A93840 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10
A93940 Fire Alarm Devices 8 16-Feb-13 24-Feb-13 16-Mar-13 24-Mar-13 24
6th Floor6th Floor 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21
Public AreaPublic Area 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Lift LobbyLift Lobby - Corridor 124 19-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11
FinishingFinishing Works 124 19-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11
Wet WorWet Works 34 19-Nov-12 29-Dec-12 21-Jan-13 24-Mar-13 71
A96040 Block Works 8 19-Nov-12 27-Nov-12 21-Jan-13 30-Jan-13 52
A95980 Plaster Works 7 01-Dec-12 09-Dec-12 03-Feb-13 10-Feb-13 52
A96000 Installation of Suspended Ceiling Grid 6 15-Dec-12 20-Dec-12 16-Feb-13 21-Feb-13 52
A96010 Suspended Ceiling Tiles 6 22-Dec-12 27-Dec-12 23-Feb-13 28-Feb-13 52
A96290 MDF for Lift Lobby Wall 7 22-Dec-12 29-Dec-12 17-Mar-13 24-Mar-13 71
Fisrt StaFisrt Stage Finishes 10 30-Dec-12 10-Jan-13 25-Mar-13 02-Apr-13 69
A96270 Screed Works 3 30-Dec-12 02-Jan-13 25-Mar-13 27-Mar-13 71
A95990 1st Coat Paint 5 06-Jan-13 10-Jan-13 28-Mar-13 02-Apr-13 69
Second SSecond Stage Finishes 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
A96020 Installation of Doors 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
A96050 Doors Ironmongery 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11
A96030 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11
A96280 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11
A96260 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11
MEP WorkMEP Works 31 28-Nov-12 05-Jan-13 31-Jan-13 27-Mar-13 69
HVACHVAC 28 28-Nov-12 31-Dec-12 06-Feb-13 05-Mar-13 53
A96060 Duct Installation & Insulation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57
A96070 Chilled Water Pipe Installation & Insulation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57
A96080 Condensate Pipe Installation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57
A96090 FCU Installation 3 05-Dec-12 08-Dec-12 12-Feb-13 14-Feb-13 57
A96100 Air-Outlet Installation 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53
ElectricalElectrical 29 28-Nov-12 02-Jan-13 31-Jan-13 05-Mar-13 52
A96110 Install Conduits in Wall 2 28-Nov-12 29-Nov-12 31-Jan-13 02-Feb-13 52
A96120 Install Cable Trays & Trunking 2 28-Nov-12 29-Nov-12 06-Feb-13 07-Feb-13 57
A96160 Cable Laying for Low Current System 2 01-Dec-12 03-Dec-12 20-Feb-13 21-Feb-13 67
A96170 Cable Laying for Power 3 01-Dec-12 04-Dec-12 19-Feb-13 21-Feb-13 66
A96130 Wiring for Lighting & Power 3 10-Dec-12 12-Dec-12 12-Feb-13 14-Feb-13 53
A96140 Wiring for Low Current System 4 10-Dec-12 13-Dec-12 11-Feb-13 14-Feb-13 52
A96150 DB installation,Dressing & Termination 3 22-Dec-12 24-Dec-12 26-Feb-13 28-Feb-13 55
A96190 Installation of Lighting Fittings 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53
A96200 Installation of Sockets 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52
PlumbingPlumbing 5 28-Nov-12 04-Dec-12 10-Feb-13 14-Feb-13 60
A96210 H/L Hot&Cold Water Pipe Installation 5 28-Nov-12 04-Dec-12 10-Feb-13 14-Feb-13 60
Fire FighFire Fighting 31 28-Nov-12 05-Jan-13 06-Feb-13 27-Mar-13 69
A96250 Fire Fighting Pipe 4 28-Nov-12 03-Dec-12 06-Feb-13 10-Feb-13 57
A96240 Hydro Static Test for Pipes 4 04-Dec-12 08-Dec-12 11-Feb-13 14-Feb-13 57
A96230 Sprinkler Fixing 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52
A96300 Fire Alarm Devices 5 29-Dec-12 03-Jan-13 23-Mar-13 27-Mar-13 70
A96220 Installation of Fire Extingusher&Blanket 2 03-Jan-13 05-Jan-13 26-Mar-13 27-Mar-13 69
Electrical /Electrical /Telephone Rooms 35 19-Nov-12 30-Dec-12 31-Jan-13 28-Apr-13 100
FinishingFinishing Works 35 19-Nov-12 30-Dec-12 31-Jan-13 28-Apr-13 100
Wet WorWet Works 14 19-Nov-12 05-Dec-12 31-Jan-13 23-Apr-13 117
A98090 Block Works 3 19-Nov-12 21-Nov-12 31-Jan-13 03-Feb-13 60
A98050 Installation of Doors& Windows Sub-frame 1 25-Nov-12 25-Nov-12 23-Apr-13 23-Apr-13 125
A98040 Plaster Works 4 25-Nov-12 28-Nov-12 06-Feb-13 10-Feb-13 60
A98060 1st Coat Paint 3 03-Dec-12 05-Dec-12 13-Feb-13 16-Feb-13 60
Fisrt StaFisrt Stage Finishes 25 26-Nov-12 25-Dec-12 30-Mar-13 25-Apr-13 102
A98080 Installation of Doors 2 26-Nov-12 27-Nov-12 24-Apr-13 25-Apr-13 125
A98100 Doors Ironmongery 2 26-Nov-12 27-Nov-12 24-Apr-13 25-Apr-13 125
A98150 Epoxy Paint Works 2 24-Dec-12 25-Dec-12 30-Mar-13 31-Mar-13 80
Second SSecond Stage Finishes 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80
A98070 Final Coat Paint 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80
Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
A98140 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100
MEP WorkMEP Works 26 22-Nov-12 23-Dec-12 04-Feb-13 28-Mar-13 80
HVACHVAC 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
A98170 Air-Outlet Installation 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73
ElectricalElectrical 26 22-Nov-12 23-Dec-12 04-Feb-13 05-Mar-13 60
A98110 Install Conduits in Wall 2 22-Nov-12 24-Nov-12 04-Feb-13 05-Feb-13 60
A98120 Wiring for Lighting & Power 2 29-Nov-12 01-Dec-12 11-Feb-13 12-Feb-13 60
A114850 Installation of SMDBs 7 06-Dec-12 13-Dec-12 24-Feb-13 03-Mar-13 66
A98130 Installation of Lighting Fittings 2 15-Dec-12 16-Dec-12 04-Mar-13 05-Mar-13 66
A114860 Installation of Telephone System 15 06-Dec-12 23-Dec-12 17-Feb-13 05-Mar-13 60
Fire FighFire Fighting 2 06-Dec-12 08-Dec-12 27-Mar-13 28-Mar-13 93
A98160 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 27-Mar-13 28-Mar-13 93
House KeeHouse Keeping Room 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 19-Nov-12 19-Dec-12 20-Jan-13 25-Apr-13 107
A99840 Block Works 4 19-Nov-12 22-Nov-12 20-Jan-13 23-Jan-13 51
A99770 Installation of Doors& Windows Sub-frame 1 28-Nov-12 28-Nov-12 25-Apr-13 25-Apr-13 124
A99760 Plaster Works 4 28-Nov-12 03-Dec-12 30-Jan-13 03-Feb-13 51
A99790 Installation of Suspended Ceiling Grid 7 09-Dec-12 16-Dec-12 09-Feb-13 16-Feb-13 51
A99780 1st Coat Paint 3 17-Dec-12 19-Dec-12 17-Feb-13 19-Feb-13 51
Fisrt StaFisrt Stage Finishes 16 20-Dec-12 08-Jan-13 20-Feb-13 31-Mar-13 69
A99800 Suspended Ceiling Tiles 7 20-Dec-12 27-Dec-12 20-Feb-13 27-Feb-13 51
A100080 Screed Works 5 29-Dec-12 03-Jan-13 28-Feb-13 05-Mar-13 51
A99820 Floor Tiles Work 4 05-Jan-13 08-Jan-13 27-Mar-13 31-Mar-13 69
Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91
A99830 Installation of Windows&Doors 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91
A99850 Doors Ironmongery 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91
Final StaFinal Stage Finishes 205 09-Jan-13 08-Sep-13 01-Apr-13 02-Oct-13 21
A99810 Final Coat Paint 2 09-Jan-13 10-Jan-13 01-Apr-13 02-Apr-13 69
A100070 Installation of Sinages 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
A99860 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 24-Nov-12 05-Jan-13 26-Jan-13 02-Apr-13 74
HVACHVAC 32 24-Nov-12 31-Dec-12 29-Jan-13 05-Mar-13 53
A99870 Duct Installation & Insulation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54
A99880 Chilled Water Pipe Installation & Insulation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54
A99890 Condensate Pipe Installation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54
A99900 FCU Installation 2 03-Dec-12 04-Dec-12 06-Feb-13 07-Feb-13 54
A99910 Air-Outlet Installation 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53
ElectricalElectrical 34 24-Nov-12 03-Jan-13 26-Jan-13 05-Mar-13 51
A99920 Install Conduits in Wall 4 24-Nov-12 27-Nov-12 26-Jan-13 29-Jan-13 51
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 77 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A99930 Install Cable Trays & Trunking 4 24-Nov-12 27-Nov-12 28-Jan-13 31-Jan-13 53
A99950 Cable Laying for Power 4 28-Nov-12 03-Dec-12 12-Feb-13 16-Feb-13 62
A99940 Wiring for Lighting & Power 4 04-Dec-12 08-Dec-12 04-Feb-13 07-Feb-13 51
A99970 Installation of Sockets 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53
A99960 Installation of Lighting Fittings 5 29-Dec-12 03-Jan-13 28-Feb-13 05-Mar-13 51
PlumbingPlumbing 34 24-Nov-12 03-Jan-13 31-Jan-13 05-Mar-13 51
A99980 H/L Drainage Pipes Installation 3 24-Nov-12 26-Nov-12 31-Jan-13 03-Feb-13 56
A99990 H/L Hot&Cold Water Pipe Installation 3 24-Nov-12 26-Nov-12 31-Jan-13 03-Feb-13 56
A100000 Drainage&Water Pipes Testing 3 27-Nov-12 29-Nov-12 04-Feb-13 06-Feb-13 56
A100010 ElectricalWater Heater Installation 4 27-Nov-12 01-Dec-12 04-Feb-13 07-Feb-13 56
A100020 Floor Drain Fixning 3 31-Dec-12 03-Jan-13 03-Mar-13 05-Mar-13 51
Fire FighFire Fighting 35 24-Nov-12 05-Jan-13 31-Jan-13 02-Apr-13 74
A100060 Fire Fighting Pipe 4 24-Nov-12 27-Nov-12 31-Jan-13 04-Feb-13 56
A100050 Hydro Static Test for Pipes 3 28-Nov-12 01-Dec-12 05-Feb-13 07-Feb-13 56
A100040 Sprinkler Fixing 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52
A100090 Fire Alarm Devices 4 29-Dec-12 02-Jan-13 27-Mar-13 31-Mar-13 74
A100030 Installation of Fire Extingusher&Blanket 2 03-Jan-13 05-Jan-13 01-Apr-13 02-Apr-13 74
Storage RoStorage Room 46 19-Nov-12 13-Jan-13 20-Jan-13 28-Apr-13 89
FinishingFinishing Works 46 19-Nov-12 13-Jan-13 20-Jan-13 28-Apr-13 89
Wet WorWet Works 29 19-Nov-12 23-Dec-12 20-Jan-13 23-Feb-13 51
A99570 Block Works 5 19-Nov-12 24-Nov-12 20-Jan-13 26-Jan-13 51
A99520 Plaster Works 5 29-Nov-12 05-Dec-12 31-Jan-13 05-Feb-13 51
A99540 Installation of Suspended Ceiling Grid 5 11-Dec-12 16-Dec-12 11-Feb-13 16-Feb-13 51
A99530 1st Coat Paint 6 17-Dec-12 23-Dec-12 17-Feb-13 23-Feb-13 51
Fisrt StaFisrt Stage Finishes 13 24-Dec-12 08-Jan-13 24-Feb-13 31-Mar-13 69
A99550 Suspended Ceiling Tiles 5 24-Dec-12 29-Dec-12 24-Feb-13 28-Feb-13 51
A99720 Epoxy Paint Works 2 07-Jan-13 08-Jan-13 30-Mar-13 31-Mar-13 69
Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 01-Apr-13 25-Apr-13 89
A99560 Installation of Doors 2 09-Jan-13 10-Jan-13 01-Apr-13 02-Apr-13 69
A99580 Doors Ironmongery 2 09-Jan-13 10-Jan-13 24-Apr-13 25-Apr-13 89
Final StaFinal Stage Finishes 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
A99710 Installation of Sinages 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89
MEP WorkMEP Works 35 25-Nov-12 06-Jan-13 27-Jan-13 28-Mar-13 69
HVACHVAC 32 25-Nov-12 02-Jan-13 31-Jan-13 05-Mar-13 52
A99590 Duct Installation & Insulation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55
A99600 Chilled Water Pipe Installation & Insulation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55
A99610 Condensate Pipe Installation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55
A99620 FCU Installation 2 04-Dec-12 05-Dec-12 09-Feb-13 10-Feb-13 55
A99630 Air-Outlet Installation 3 30-Dec-12 02-Jan-13 03-Mar-13 05-Mar-13 52
ElectricalElectrical 33 25-Nov-12 03-Jan-13 27-Jan-13 05-Mar-13 51
A99640 Install Conduits in Wall 4 25-Nov-12 28-Nov-12 27-Jan-13 30-Jan-13 51
A99650 Wiring for Lighting & Power 4 06-Dec-12 10-Dec-12 06-Feb-13 10-Feb-13 51
A99660 Installation of Lighting Fittings 4 30-Dec-12 03-Jan-13 02-Mar-13 05-Mar-13 51
PlumbingPlumbing 8 25-Nov-12 04-Dec-12 02-Feb-13 10-Feb-13 56
A99740 H/L Hot&Cold Water Pipe Installation 4 25-Nov-12 28-Nov-12 02-Feb-13 05-Feb-13 56
A100100 H/L Drainage Pipes Installation 4 25-Nov-12 28-Nov-12 02-Feb-13 05-Feb-13 56
A99750 Water Pipes Testing 4 29-Nov-12 04-Dec-12 06-Feb-13 10-Feb-13 56
A100110 Drainage&Water Pipes Testing 4 29-Nov-12 04-Dec-12 06-Feb-13 10-Feb-13 56
Fire FighFire Fighting 35 25-Nov-12 06-Jan-13 03-Feb-13 28-Mar-13 69
A99700 Fire Fighting Pipe 4 25-Nov-12 28-Nov-12 03-Feb-13 06-Feb-13 57
A99690 Hydro Static Test for Pipes 3 29-Nov-12 03-Dec-12 07-Feb-13 10-Feb-13 57
A99680 Sprinkler Fixing 4 30-Dec-12 03-Jan-13 02-Mar-13 05-Mar-13 51
A99730 Fire Alarm Devices 4 30-Dec-12 03-Jan-13 25-Mar-13 28-Mar-13 71
A99670 Installation of Fire Extingusher&Blanket 2 05-Jan-13 06-Jan-13 27-Mar-13 28-Mar-13 69
StaircaseStaircase 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37
Stairs 1Stairs 1 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37
A110830 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37
A110840 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37
A110850 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110860 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110870 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37
A110880 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37
Stairs 2Stairs 2 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37
A110890 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37
A110900 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37
A110910 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110920 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110930 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37
A110940 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37
Stairs 3Stairs 3 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37
A110950 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37
A110960 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37
A110970 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110980 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
A110990 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37
A111000 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37
Rooms AreaRooms Area 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21
Guest RooGuest Rooms 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21
FinishingFinishing Works 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21
Wet WorWet Works 63 19-Nov-12 03-Feb-13 03-Dec-12 03-Mar-13 24
A94090 Block Works 12 19-Nov-12 03-Dec-12 03-Dec-12 16-Dec-12 11
A93950 Plaster Works 31 05-Dec-12 10-Jan-13 18-Dec-12 23-Jan-13 11
A93980 Installation of Suspended Ceiling Grid (Dry Area) 10 31-Dec-12 12-Jan-13 14-Jan-13 26-Jan-13 11
A93960 Installation of Doors& Windows Sub-frame 22 19-Dec-12 14-Jan-13 06-Feb-13 03-Mar-13 40
A94420 Wall Tiles Work (Wet Area) 22 23-Dec-12 17-Jan-13 10-Jan-13 05-Feb-13 15
A93970 1st Coat Paint 22 08-Jan-13 03-Feb-13 21-Jan-13 16-Feb-13 11
Fisrt StaFisrt Stage Finishes 29 16-Jan-13 19-Feb-13 30-Jan-13 24-Mar-13 28
A93990 Suspended Ceiling Tiles (DryArea) 8 16-Jan-13 26-Jan-13 30-Jan-13 07-Feb-13 11
A94030 Installation of Wardrobes 7 20-Jan-13 28-Jan-13 03-Feb-13 10-Feb-13 11
A94020 Water Proofing for Wet Area 11 29-Jan-13 10-Feb-13 11-Feb-13 23-Feb-13 11
A94410 Screed Works 15 23-Jan-13 10-Feb-13 06-Feb-13 23-Feb-13 11
A94450 Installation of Suspended Ceiling Grid (Wet Area) 7 03-Feb-13 10-Feb-13 16-Feb-13 23-Feb-13 11
A94440 Suspended Ceiling Tiles (Wet Area) 7 06-Feb-13 13-Feb-13 19-Feb-13 26-Feb-13 11
A94010 Floor & Wall Tiles Work (Dry Area) 12 02-Feb-13 14-Feb-13 11-Mar-13 24-Mar-13 32
A94430 Floor Tiles Work (Wet Area) 8 11-Feb-13 19-Feb-13 27-Feb-13 07-Mar-13 14
Second SSecond Stage Finishes 18 16-Feb-13 07-Mar-13 04-Mar-13 28-Apr-13 44
A94040 Installation of Windows&Doors 7 16-Feb-13 23-Feb-13 04-Mar-13 11-Mar-13 14
A94100 Doors Ironmongery 7 16-Feb-13 23-Feb-13 21-Apr-13 28-Apr-13 55
A94070 Installation of Balustrades& Handrails 7 24-Feb-13 03-Mar-13 17-Mar-13 24-Mar-13 18
A94390 Installation of Toliets Accessories 12 20-Feb-13 05-Mar-13 18-Mar-13 31-Mar-13 22
A94080 Installation of Vanity Counter 10 24-Feb-13 06-Mar-13 13-Mar-13 24-Mar-13 15
A94050 Installation of Mirrors 11 24-Feb-13 07-Mar-13 12-Mar-13 24-Mar-13 14
Final StaFinal Stage Finishes 156 09-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21
A94000 Final Coat Paint 8 09-Mar-13 17-Mar-13 25-Mar-13 02-Apr-13 14
A94060 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25
A94400 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25
A94110 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 82 26-Nov-12 04-Mar-13 10-Dec-12 02-Apr-13 25
HVACHVAC 62 04-Dec-12 16-Feb-13 20-Dec-12 05-Mar-13 15
A94140 Condensate Pipe Installation 10 04-Dec-12 15-Dec-12 23-Dec-12 03-Jan-13 16
A94120 Duct Installation & Insulation 12 04-Dec-12 17-Dec-12 20-Dec-12 03-Jan-13 14
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Suspended Ceiling Grid (Dry Area)
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Water Proofing for Wet Area
Screed Works
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Final Coat Paint
Installation of Carpets
Installation of Sinages
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 78 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A94130 Chilled Water Pipe Installation & Insulation 12 04-Dec-12 17-Dec-12 20-Dec-12 03-Jan-13 14
A94150 FCU Installation 8 18-Dec-12 26-Dec-12 05-Jan-13 13-Jan-13 14
A94160 Air-Outlet Installation 6 10-Feb-13 16-Feb-13 27-Feb-13 05-Mar-13 15
ElectricalElectrical 70 26-Nov-12 18-Feb-13 10-Dec-12 05-Mar-13 13
A94170 Install Conduits in Wall 14 26-Nov-12 12-Dec-12 10-Dec-12 25-Dec-12 11
A94180 Install Cable Trays & Trunking 14 04-Dec-12 19-Dec-12 02-Jan-13 17-Jan-13 24
A94220 Cable Laying for Low Current System 6 20-Dec-12 26-Dec-12 19-Jan-13 26-Jan-13 24
A94230 Cable Laying for Power 6 20-Dec-12 26-Dec-12 19-Jan-13 26-Jan-13 24
A94200 Wiring for Low Current System 8 19-Dec-12 27-Dec-12 08-Jan-13 16-Jan-13 16
A94190 Wiring for Lighting & Power 8 23-Dec-12 31-Dec-12 06-Jan-13 14-Jan-13 11
A94210 DB installation,Dressing & Termination 10 14-Jan-13 26-Jan-13 28-Jan-13 07-Feb-13 11
A94260 Installation of Sockets 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14
A94250 Installation of Lighting Fittings 8 10-Feb-13 18-Feb-13 25-Feb-13 05-Mar-13 13
PlumbingPlumbing 80 28-Nov-12 04-Mar-13 12-Dec-12 24-Mar-13 17
A94270 Drainge Pipes in Wall 14 28-Nov-12 15-Dec-12 12-Dec-12 27-Dec-12 11
A94280 H/L Drainage Pipes Installation 10 04-Dec-12 15-Dec-12 28-Jan-13 07-Feb-13 45
A94290 H/L Hot&Cold Water Pipe Installation 10 04-Dec-12 15-Dec-12 28-Jan-13 07-Feb-13 45
A94340 Water Pipes in Wall 14 28-Nov-12 15-Dec-12 12-Dec-12 27-Dec-12 11
A94300 Drainage&Water Pipes Testing 4 16-Dec-12 19-Dec-12 09-Feb-13 12-Feb-13 45
A94310 ElectricalWater Heater Installation 6 16-Dec-12 22-Dec-12 09-Feb-13 14-Feb-13 45
A94320 Floor Drain Fixning 8 27-Jan-13 04-Feb-13 24-Feb-13 04-Mar-13 24
A94330 Installation of Sanitaryware 8 24-Feb-13 04-Mar-13 16-Mar-13 24-Mar-13 17
Fire FighFire Fighting 71 04-Dec-12 26-Feb-13 23-Dec-12 02-Apr-13 30
A94380 Fire Fighting Pipe 10 04-Dec-12 15-Dec-12 23-Dec-12 03-Jan-13 16
A94370 Hydro Static Test for Pipes 8 16-Dec-12 24-Dec-12 05-Jan-13 13-Jan-13 16
A94360 Sprinkler Fixing 8 12-Feb-13 20-Feb-13 25-Feb-13 05-Mar-13 11
A94460 Fire Alarm Devices 8 14-Feb-13 23-Feb-13 16-Mar-13 24-Mar-13 25
A94350 Installation of Fire Extingusher&Blanket 5 21-Feb-13 26-Feb-13 28-Mar-13 02-Apr-13 30
7th Floor7th Floor 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21
Public AreaPublic Area 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Lift LobbyLift Lobby - Corridor 112 04-Dec-12 15-Apr-13 26-Jan-13 28-Apr-13 11
FinishingFinishing Works 112 04-Dec-12 15-Apr-13 26-Jan-13 28-Apr-13 11
Wet WorWet Works 31 04-Dec-12 09-Jan-13 26-Jan-13 24-Mar-13 62
A96370 Block Works 8 04-Dec-12 12-Dec-12 26-Jan-13 03-Feb-13 43
A96310 Plaster Works 7 16-Dec-12 23-Dec-12 06-Feb-13 13-Feb-13 43
A96330 Installation of Suspended Ceiling Grid 6 25-Dec-12 31-Dec-12 16-Feb-13 21-Feb-13 43
A96340 Suspended Ceiling Tiles 6 02-Jan-13 08-Jan-13 23-Feb-13 28-Feb-13 43
A96620 MDF for Lift Lobby Wall 7 02-Jan-13 09-Jan-13 17-Mar-13 24-Mar-13 62
Fisrt StaFisrt Stage Finishes 10 10-Jan-13 21-Jan-13 25-Mar-13 02-Apr-13 60
A96600 Screed Works 3 10-Jan-13 13-Jan-13 25-Mar-13 27-Mar-13 62
A96320 1st Coat Paint 5 16-Jan-13 21-Jan-13 28-Mar-13 02-Apr-13 60
Second SSecond Stage Finishes 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80
A96350 Installation of Doors 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80
A96380 Doors Ironmongery 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80
Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11
A96360 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11
A96610 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11
A96590 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11
MEP WorkMEP Works 28 13-Dec-12 15-Jan-13 04-Feb-13 27-Mar-13 60
HVACHVAC 25 13-Dec-12 12-Jan-13 06-Feb-13 05-Mar-13 44
A96390 Duct Installation & Insulation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45
A96400 Chilled Water Pipe Installation & Insulation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45
A96410 Condensate Pipe Installation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45
A96420 FCU Installation 3 19-Dec-12 22-Dec-12 12-Feb-13 14-Feb-13 45
A96430 Air-Outlet Installation 3 09-Jan-13 12-Jan-13 03-Mar-13 05-Mar-13 44
ElectricalElectrical 26 13-Dec-12 13-Jan-13 04-Feb-13 05-Mar-13 43
A96440 Install Conduits in Wall 2 13-Dec-12 15-Dec-12 04-Feb-13 05-Feb-13 43
A96450 Install Cable Trays & Trunking 2 13-Dec-12 15-Dec-12 10-Feb-13 11-Feb-13 48
A96490 Cable Laying for Low Current System 2 16-Dec-12 17-Dec-12 20-Feb-13 21-Feb-13 55
A96500 Cable Laying for Power 3 16-Dec-12 18-Dec-12 19-Feb-13 21-Feb-13 54
A96460 Wiring for Lighting & Power 3 22-Dec-12 24-Dec-12 12-Feb-13 14-Feb-13 43
A96470 Wiring for Low Current System 3 22-Dec-12 24-Dec-12 12-Feb-13 14-Feb-13 43
A96480 DB installation,Dressing & Termination 3 02-Jan-13 05-Jan-13 26-Feb-13 28-Feb-13 46
A96520 Installation of Lighting Fittings 3 09-Jan-13 12-Jan-13 03-Mar-13 05-Mar-13 44
A96530 Installation of Sockets 4 09-Jan-13 13-Jan-13 02-Mar-13 05-Mar-13 43
PlumbingPlumbing 5 13-Dec-12 18-Dec-12 10-Feb-13 14-Feb-13 48
A96540 H/L Hot&Cold Water Pipe Installation 5 13-Dec-12 18-Dec-12 10-Feb-13 14-Feb-13 48
Fire FighFire Fighting 28 13-Dec-12 15-Jan-13 06-Feb-13 27-Mar-13 60
A96580 Fire Fighting Pipe 4 13-Dec-12 17-Dec-12 06-Feb-13 10-Feb-13 45
A96570 Hydro Static Test for Pipes 4 18-Dec-12 22-Dec-12 11-Feb-13 14-Feb-13 45
A96560 Sprinkler Fixing 4 09-Jan-13 13-Jan-13 02-Mar-13 05-Mar-13 43
A96630 Fire Alarm Devices 5 09-Jan-13 14-Jan-13 23-Mar-13 27-Mar-13 61
A96550 Installation of Fire Extingusher&Blanket 2 14-Jan-13 15-Jan-13 26-Mar-13 27-Mar-13 60
Electrical /Electrical /Telephone Rooms 35 04-Dec-12 14-Jan-13 31-Jan-13 28-Apr-13 88
FinishingFinishing Works 35 04-Dec-12 14-Jan-13 31-Jan-13 28-Apr-13 88
Wet WorWet Works 14 04-Dec-12 19-Dec-12 31-Jan-13 23-Apr-13 105
A98230 Block Works 3 04-Dec-12 06-Dec-12 31-Jan-13 03-Feb-13 48
A98190 Installation of Doors& Windows Sub-frame 1 10-Dec-12 10-Dec-12 23-Apr-13 23-Apr-13 113
A98180 Plaster Works 4 10-Dec-12 13-Dec-12 06-Feb-13 10-Feb-13 48
A98200 1st Coat Paint 3 17-Dec-12 19-Dec-12 13-Feb-13 16-Feb-13 48
Fisrt StaFisrt Stage Finishes 25 11-Dec-12 09-Jan-13 30-Mar-13 25-Apr-13 90
A98220 Installation of Doors 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113
A98240 Doors Ironmongery 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113
A98290 Epoxy Paint Works 2 08-Jan-13 09-Jan-13 30-Mar-13 31-Mar-13 68
Second SSecond Stage Finishes 2 10-Jan-13 12-Jan-13 01-Apr-13 02-Apr-13 68
A98210 Final Coat Paint 2 10-Jan-13 12-Jan-13 01-Apr-13 02-Apr-13 68
Final StaFinal Stage Finishes 2 13-Jan-13 14-Jan-13 27-Apr-13 28-Apr-13 88
A98280 Installation of Sinages 2 13-Jan-13 14-Jan-13 27-Apr-13 28-Apr-13 88
MEP WorkMEP Works 26 08-Dec-12 07-Jan-13 04-Feb-13 28-Mar-13 68
HVACHVAC 2 20-Dec-12 22-Dec-12 04-Mar-13 05-Mar-13 61
A98310 Air-Outlet Installation 2 20-Dec-12 22-Dec-12 04-Mar-13 05-Mar-13 61
ElectricalElectrical 26 08-Dec-12 07-Jan-13 04-Feb-13 05-Mar-13 48
A98250 Install Conduits in Wall 2 08-Dec-12 09-Dec-12 04-Feb-13 05-Feb-13 48
A98260 Wiring for Lighting & Power 2 15-Dec-12 16-Dec-12 11-Feb-13 12-Feb-13 48
A114870 Installation of SMDBs 7 20-Dec-12 27-Dec-12 24-Feb-13 03-Mar-13 54
A98270 Installation of Lighting Fittings 2 29-Dec-12 30-Dec-12 04-Mar-13 05-Mar-13 54
A114880 Installation of Telephone System 15 20-Dec-12 07-Jan-13 17-Feb-13 05-Mar-13 48
Fire FighFire Fighting 2 20-Dec-12 22-Dec-12 27-Mar-13 28-Mar-13 81
A98300 Fire Alarm Devices 2 20-Dec-12 22-Dec-12 27-Mar-13 28-Mar-13 81
House KeeHouse Keeping Room 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21
FinishingFinishing Works 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21
Wet WorWet Works 26 04-Dec-12 03-Jan-13 20-Jan-13 25-Apr-13 95
A100440 Block Works 4 04-Dec-12 08-Dec-12 20-Jan-13 23-Jan-13 39
A100370 Installation of Doors& Windows Sub-frame 1 13-Dec-12 13-Dec-12 25-Apr-13 25-Apr-13 112
A100360 Plaster Works 4 13-Dec-12 17-Dec-12 30-Jan-13 03-Feb-13 39
A100390 Installation of Suspended Ceiling Grid 7 23-Dec-12 30-Dec-12 09-Feb-13 16-Feb-13 39
A100380 1st Coat Paint 3 31-Dec-12 03-Jan-13 17-Feb-13 19-Feb-13 39
Fisrt StaFisrt Stage Finishes 16 05-Jan-13 22-Jan-13 20-Feb-13 31-Mar-13 57
A100400 Suspended Ceiling Tiles 7 05-Jan-13 12-Jan-13 20-Feb-13 27-Feb-13 39
A100680 Screed Works 5 13-Jan-13 17-Jan-13 28-Feb-13 05-Mar-13 39
A100420 Floor Tiles Work 4 19-Jan-13 22-Jan-13 27-Mar-13 31-Mar-13 57
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Low Current System
Wiring for Lighting & Power
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Installation of Carpets
Fixing of Wall Covering
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Installation of Sockets
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 79 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Second SSecond Stage Finishes 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79
A100430 Installation of Windows&Doors 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79
A100450 Doors Ironmongery 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79
Final StaFinal Stage Finishes 193 23-Jan-13 08-Sep-13 01-Apr-13 02-Oct-13 21
A100410 Final Coat Paint 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57
A100670 Installation of Sinages 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77
A100460 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 35 09-Dec-12 19-Jan-13 26-Jan-13 02-Apr-13 62
HVACHVAC 32 09-Dec-12 15-Jan-13 29-Jan-13 05-Mar-13 41
A100470 Duct Installation & Insulation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42
A100480 Chilled Water Pipe Installation & Insulation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42
A100490 Condensate Pipe Installation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42
A100500 FCU Installation 2 17-Dec-12 18-Dec-12 06-Feb-13 07-Feb-13 42
A100510 Air-Outlet Installation 3 13-Jan-13 15-Jan-13 03-Mar-13 05-Mar-13 41
ElectricalElectrical 34 09-Dec-12 17-Jan-13 26-Jan-13 05-Mar-13 39
A100520 Install Conduits in Wall 4 09-Dec-12 12-Dec-12 26-Jan-13 29-Jan-13 39
A100530 Install Cable Trays & Trunking 4 09-Dec-12 12-Dec-12 28-Jan-13 31-Jan-13 41
A100550 Cable Laying for Power 4 13-Dec-12 17-Dec-12 12-Feb-13 16-Feb-13 50
A100540 Wiring for Lighting & Power 4 18-Dec-12 22-Dec-12 04-Feb-13 07-Feb-13 39
A100560 Installation of Lighting Fittings 3 13-Jan-13 15-Jan-13 03-Mar-13 05-Mar-13 41
A100570 Installation of Sockets 5 13-Jan-13 17-Jan-13 28-Feb-13 05-Mar-13 39
PlumbingPlumbing 34 09-Dec-12 17-Jan-13 31-Jan-13 05-Mar-13 39
A100580 H/L Drainage Pipes Installation 3 09-Dec-12 11-Dec-12 31-Jan-13 03-Feb-13 44
A100590 H/L Hot&Cold Water Pipe Installation 3 09-Dec-12 11-Dec-12 31-Jan-13 03-Feb-13 44
A100600 Drainage&Water Pipes Testing 3 12-Dec-12 15-Dec-12 04-Feb-13 06-Feb-13 44
A100610 ElectricalWater Heater Installation 4 12-Dec-12 16-Dec-12 04-Feb-13 07-Feb-13 44
A100620 Floor Drain Fixning 3 15-Jan-13 17-Jan-13 03-Mar-13 05-Mar-13 39
Fire FighFire Fighting 35 09-Dec-12 19-Jan-13 31-Jan-13 02-Apr-13 62
A100660 Fire Fighting Pipe 4 09-Dec-12 12-Dec-12 31-Jan-13 04-Feb-13 44
A100650 Hydro Static Test for Pipes 3 13-Dec-12 16-Dec-12 05-Feb-13 07-Feb-13 44
A100640 Sprinkler Fixing 4 13-Jan-13 16-Jan-13 02-Mar-13 05-Mar-13 40
A100690 Fire Alarm Devices 4 13-Jan-13 16-Jan-13 27-Mar-13 31-Mar-13 62
A100630 Installation of Fire Extingusher&Blanket 2 17-Jan-13 19-Jan-13 01-Apr-13 02-Apr-13 62
Storage RoStorage Room 46 04-Dec-12 28-Jan-13 20-Jan-13 28-Apr-13 77
FinishingFinishing Works 46 04-Dec-12 28-Jan-13 20-Jan-13 28-Apr-13 77
Wet WorWet Works 29 04-Dec-12 07-Jan-13 20-Jan-13 23-Feb-13 39
A100170 Block Works 5 04-Dec-12 09-Dec-12 20-Jan-13 26-Jan-13 39
A100120 Plaster Works 5 15-Dec-12 19-Dec-12 31-Jan-13 05-Feb-13 39
A100140 Installation of Suspended Ceiling Grid 5 25-Dec-12 30-Dec-12 11-Feb-13 16-Feb-13 39
A100130 1st Coat Paint 6 31-Dec-12 07-Jan-13 17-Feb-13 23-Feb-13 39
Fisrt StaFisrt Stage Finishes 13 08-Jan-13 22-Jan-13 24-Feb-13 31-Mar-13 57
A100150 Suspended Ceiling Tiles 5 08-Jan-13 13-Jan-13 24-Feb-13 28-Feb-13 39
A100320 Epoxy Paint Works 2 21-Jan-13 22-Jan-13 30-Mar-13 31-Mar-13 57
Second SSecond Stage Finishes 2 23-Jan-13 26-Jan-13 01-Apr-13 25-Apr-13 77
A100160 Installation of Doors 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57
A100180 Doors Ironmongery 2 23-Jan-13 26-Jan-13 24-Apr-13 25-Apr-13 77
Final StaFinal Stage Finishes 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77
A100310 Installation of Sinages 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77
MEP WorkMEP Works 35 10-Dec-12 20-Jan-13 27-Jan-13 28-Mar-13 57
HVACHVAC 32 10-Dec-12 16-Jan-13 31-Jan-13 05-Mar-13 40
A100190 Duct Installation & Insulation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43
A100200 Chilled Water Pipe Installation & Insulation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43
A100210 Condensate Pipe Installation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43
A100220 FCU Installation 2 18-Dec-12 19-Dec-12 09-Feb-13 10-Feb-13 43
A100230 Air-Outlet Installation 3 14-Jan-13 16-Jan-13 03-Mar-13 05-Mar-13 40
ElectricalElectrical 33 10-Dec-12 17-Jan-13 27-Jan-13 05-Mar-13 39
A100240 Install Conduits in Wall 4 10-Dec-12 13-Dec-12 27-Jan-13 30-Jan-13 39
A100250 Wiring for Lighting & Power 4 20-Dec-12 24-Dec-12 06-Feb-13 10-Feb-13 39
A100260 Installation of Lighting Fittings 4 14-Jan-13 17-Jan-13 02-Mar-13 05-Mar-13 39
PlumbingPlumbing 8 10-Dec-12 18-Dec-12 02-Feb-13 10-Feb-13 44
A100340 H/L Hot&Cold Water Pipe Installation 4 10-Dec-12 13-Dec-12 02-Feb-13 05-Feb-13 44
A100700 H/L Drainage Pipes Installation 4 10-Dec-12 13-Dec-12 02-Feb-13 05-Feb-13 44
A100350 Water Pipes Testing 4 15-Dec-12 18-Dec-12 06-Feb-13 10-Feb-13 44
A100710 Drainage&Water Pipes Testing 4 15-Dec-12 18-Dec-12 06-Feb-13 10-Feb-13 44
Fire FighFire Fighting 35 10-Dec-12 20-Jan-13 03-Feb-13 28-Mar-13 57
A100300 Fire Fighting Pipe 4 10-Dec-12 13-Dec-12 03-Feb-13 06-Feb-13 45
A100290 Hydro Static Test for Pipes 3 15-Dec-12 17-Dec-12 07-Feb-13 10-Feb-13 45
A100280 Sprinkler Fixing 4 14-Jan-13 17-Jan-13 02-Mar-13 05-Mar-13 39
A100330 Fire Alarm Devices 4 14-Jan-13 17-Jan-13 25-Mar-13 28-Mar-13 59
A100270 Installation of Fire Extingusher&Blanket 2 19-Jan-13 20-Jan-13 27-Mar-13 28-Mar-13 57
StaircaseStaircase 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32
Stairs 1Stairs 1 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32
A111010 Floor Screed 3 05-Jan-13 07-Jan-13 12-Feb-13 14-Feb-13 32
A111020 Install Handrails 4 08-Jan-13 12-Jan-13 16-Feb-13 19-Feb-13 32
A111030 Ceiling 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32
A111040 Wall 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32
A111050 Install Granite/Terrazo 12 28-Jan-13 10-Feb-13 06-Mar-13 19-Mar-13 32
A111060 Final Coat Paint 12 11-Feb-13 24-Feb-13 20-Mar-13 02-Apr-13 32
Stairs 2Stairs 2 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32
A111070 Floor Screed 3 05-Jan-13 07-Jan-13 12-Feb-13 14-Feb-13 32
A111080 Install Handrails 4 08-Jan-13 12-Jan-13 16-Feb-13 19-Feb-13 32
A111090 Ceiling 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32
A111100 Wall 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32
A111110 Install Granite/Terrazo 12 28-Jan-13 10-Feb-13 06-Mar-13 19-Mar-13 32
A111120 Final Coat Paint 12 11-Feb-13 24-Feb-13 20-Mar-13 02-Apr-13 32
Rooms AreaRooms Area 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21
Guest RooGuest Rooms 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21
FinishingFinishing Works 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21
Wet WorWet Works 52 04-Dec-12 04-Feb-13 16-Dec-12 03-Mar-13 23
A94610 Block Works 12 04-Dec-12 17-Dec-12 16-Dec-12 29-Dec-12 10
A94500 Installation of Suspended Ceiling Grid (Dry Area) 10 05-Jan-13 15-Jan-13 16-Jan-13 28-Jan-13 10
A94470 Plaster Works 31 19-Dec-12 26-Jan-13 31-Dec-12 06-Feb-13 10
A94480 Installation of Doors& Windows Sub-frame 22 03-Jan-13 29-Jan-13 06-Feb-13 03-Mar-13 28
A94940 Wall Tiles Work (Wet Area) 22 07-Jan-13 02-Feb-13 05-Feb-13 02-Mar-13 24
A94490 1st Coat Paint 22 09-Jan-13 04-Feb-13 21-Jan-13 16-Feb-13 10
Fisrt StaFisrt Stage Finishes 28 19-Jan-13 20-Feb-13 31-Jan-13 24-Mar-13 27
A94510 Suspended Ceiling Tiles (DryArea) 8 19-Jan-13 28-Jan-13 31-Jan-13 09-Feb-13 10
A94550 Installation of Wardrobes 7 23-Jan-13 31-Jan-13 05-Feb-13 12-Feb-13 10
A94970 Installation of Suspended Ceiling Grid (Wet Area) 7 04-Feb-13 11-Feb-13 16-Feb-13 23-Feb-13 10
A94540 Water Proofing for Wet Area 11 31-Jan-13 12-Feb-13 12-Feb-13 24-Feb-13 10
A94930 Screed Works 15 28-Jan-13 13-Feb-13 09-Feb-13 25-Feb-13 10
A94960 Suspended Ceiling Tiles (Wet Area) 7 07-Feb-13 14-Feb-13 19-Feb-13 26-Feb-13 10
A94530 Floor & Wall Tiles Work (Dry Area) 12 05-Feb-13 18-Feb-13 11-Mar-13 24-Mar-13 29
A94950 Floor Tiles Work (Wet Area) 8 12-Feb-13 20-Feb-13 27-Feb-13 07-Mar-13 13
Second SSecond Stage Finishes 18 17-Feb-13 09-Mar-13 04-Mar-13 31-Mar-13 19
A94560 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 04-Mar-13 11-Mar-13 13
A94620 Doors Ironmongery 7 17-Feb-13 24-Feb-13 17-Mar-13 24-Mar-13 24
A94590 Installation of Balustrades& Handrails 7 25-Feb-13 04-Mar-13 17-Mar-13 24-Mar-13 17
A94910 Installation of Toliets Accessories 12 21-Feb-13 06-Mar-13 18-Mar-13 31-Mar-13 21
A94600 Installation of Vanity Counter 10 25-Feb-13 07-Mar-13 13-Mar-13 24-Mar-13 14
A94570 Installation of Mirrors 11 25-Feb-13 09-Mar-13 12-Mar-13 24-Mar-13 13
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Windows&Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Installation of Furnitur
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Power
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Sockets
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Suspended Ceiling Grid (Dry Area)
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work (Wet Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Installation of Suspended Ceiling Grid (Wet Area)
Water Proofing for Wet Area
Screed Works
Suspended Ceiling Tiles (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Toliets Accessories
Installation of Vanity Counter
Installation of Mirrors
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 80 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Final StaFinal Stage Finishes 155 10-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21
A94520 Final Coat Paint 8 10-Mar-13 18-Mar-13 25-Mar-13 02-Apr-13 13
A94920 Installation of Sinages 7 19-Mar-13 26-Mar-13 21-Apr-13 28-Apr-13 28
A94580 Installation of Carpets 8 21-Mar-13 30-Mar-13 21-Jul-13 29-Jul-13 103
A94630 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21
MEP WorkMEP Works 72 10-Dec-12 05-Mar-13 23-Dec-12 02-Apr-13 24
HVACHVAC 51 18-Dec-12 17-Feb-13 02-Jan-13 05-Mar-13 14
A94660 Condensate Pipe Installation 10 18-Dec-12 29-Dec-12 12-Jan-13 22-Jan-13 20
A94640 Duct Installation & Insulation 12 18-Dec-12 31-Dec-12 02-Jan-13 15-Jan-13 12
A94650 Chilled Water Pipe Installation & Insulation 12 18-Dec-12 31-Dec-12 02-Jan-13 15-Jan-13 12
A94670 FCU Installation 8 27-Dec-12 06-Jan-13 12-Jan-13 20-Jan-13 12
A94680 Air-Outlet Installation 6 11-Feb-13 17-Feb-13 27-Feb-13 05-Mar-13 14
ElectricalElectrical 60 10-Dec-12 19-Feb-13 23-Dec-12 05-Mar-13 12
A94690 Install Conduits in Wall 14 10-Dec-12 25-Dec-12 23-Dec-12 08-Jan-13 11
A94700 Install Cable Trays & Trunking 14 18-Dec-12 03-Jan-13 05-Jan-13 20-Jan-13 14
A94710 Wiring for Lighting & Power 8 27-Dec-12 06-Jan-13 09-Jan-13 17-Jan-13 10
A94720 Wiring for Low Current System 8 27-Dec-12 06-Jan-13 12-Jan-13 20-Jan-13 12
A94740 Cable Laying for Low Current System 6 05-Jan-13 10-Jan-13 21-Jan-13 28-Jan-13 14
A94750 Cable Laying for Power 6 05-Jan-13 10-Jan-13 21-Jan-13 28-Jan-13 14
A94730 DB installation,Dressing & Termination 12 14-Jan-13 28-Jan-13 27-Jan-13 09-Feb-13 10
A94780 Installation of Sockets 7 11-Feb-13 18-Feb-13 26-Feb-13 05-Mar-13 13
A94770 Installation of Lighting Fittings 8 11-Feb-13 19-Feb-13 25-Feb-13 05-Mar-13 12
PlumbingPlumbing 69 13-Dec-12 05-Mar-13 25-Dec-12 24-Mar-13 16
A94790 Drainge Pipes in Wall 14 13-Dec-12 29-Dec-12 25-Dec-12 10-Jan-13 10
A94800 H/L Drainage Pipes Installation 10 18-Dec-12 29-Dec-12 28-Jan-13 07-Feb-13 33
A94810 H/L Hot&Cold Water Pipe Installation 10 18-Dec-12 29-Dec-12 28-Jan-13 07-Feb-13 33
A94860 Water Pipes in Wall 14 13-Dec-12 29-Dec-12 25-Dec-12 10-Jan-13 10
A94820 Drainage&Water Pipes Testing 4 30-Dec-12 03-Jan-13 09-Feb-13 12-Feb-13 33
A94830 ElectricalWater Heater Installation 6 30-Dec-12 06-Jan-13 09-Feb-13 14-Feb-13 33
A94840 Floor Drain Fixning 8 30-Jan-13 07-Feb-13 24-Feb-13 04-Mar-13 21
A94850 Installation of Sanitaryware 8 25-Feb-13 05-Mar-13 16-Mar-13 24-Mar-13 16
Fire FighFire Fighting 57 18-Dec-12 24-Feb-13 30-Dec-12 02-Apr-13 32
A94900 Fire Fighting Pipe 10 18-Dec-12 29-Dec-12 30-Dec-12 10-Jan-13 10
A94890 Hydro Static Test for Pipes 8 30-Dec-12 08-Jan-13 12-Jan-13 20-Jan-13 10
A94870 Installation of Fire Extingusher&Blanket 5 13-Feb-13 18-Feb-13 28-Mar-13 02-Apr-13 37
A94880 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10
A94980 Fire Alarm Devices 8 16-Feb-13 24-Feb-13 16-Mar-13 24-Mar-13 24
Roof LevelRoof Level 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35
Public AreaPublic Area 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35
Pump RooPump Room 46 16-Dec-12 09-Feb-13 19-Jan-13 28-Apr-13 67
FinishingFinishing Works 46 16-Dec-12 09-Feb-13 19-Jan-13 28-Apr-13 67
Wet WorWet Works 24 16-Dec-12 13-Jan-13 19-Jan-13 23-Apr-13 85
A91270 Block Works 6 16-Dec-12 22-Dec-12 19-Jan-13 26-Jan-13 28
A91230 Installation of Doors& Windows Sub-frame 1 26-Dec-12 26-Dec-12 23-Apr-13 23-Apr-13 99
A91220 Plaster Works 6 26-Dec-12 02-Jan-13 30-Jan-13 05-Feb-13 28
A91240 1st Coat Paint 6 07-Jan-13 13-Jan-13 10-Feb-13 16-Feb-13 28
Fisrt StaFisrt Stage Finishes 31 27-Dec-12 03-Feb-13 21-Apr-13 25-Apr-13 70
A91260 Installation of Doors 2 27-Dec-12 29-Dec-12 24-Apr-13 25-Apr-13 99
A91280 Doors Ironmongery 2 27-Dec-12 29-Dec-12 24-Apr-13 25-Apr-13 99
A91330 Epoxy Paint Works 2 02-Feb-13 03-Feb-13 21-Apr-13 22-Apr-13 67
Second SSecond Stage Finishes 3 04-Feb-13 06-Feb-13 23-Apr-13 25-Apr-13 67
A91250 Final Coat Paint 3 04-Feb-13 06-Feb-13 23-Apr-13 25-Apr-13 67
Final StaFinal Stage Finishes 2 07-Feb-13 09-Feb-13 27-Apr-13 28-Apr-13 67
A91320 Installation of Sinages 2 07-Feb-13 09-Feb-13 27-Apr-13 28-Apr-13 67
MEP WorkMEP Works 33 23-Dec-12 31-Jan-13 27-Jan-13 24-Apr-13 71
HVACHVAC 33 23-Dec-12 31-Jan-13 12-Feb-13 05-Mar-13 28
A91350 Duct Installation & Insulation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42
A91360 Chilled Water Pipe Installation & Insulation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42
A91370 Condensate Pipe Installation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42
A91380 FCU Installation 5 31-Dec-12 06-Jan-13 20-Feb-13 25-Feb-13 42
A91390 Air-Outlet Installation 7 07-Jan-13 14-Jan-13 26-Feb-13 05-Mar-13 42
A115120 Installation of Primary Chilled Water Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28
A115130 Installation of SecondaryChilled Water Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28
A115140 Installation of Heat Exchanger 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28
A115150 Installation of Heat Exchanger Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28
ElectricalElectrical 23 23-Dec-12 19-Jan-13 27-Jan-13 05-Mar-13 38
A91290 Install Conduits in Wall 3 23-Dec-12 25-Dec-12 27-Jan-13 29-Jan-13 28
A91300 Wiring for Lighting & Power 3 03-Jan-13 06-Jan-13 06-Feb-13 09-Feb-13 28
A91310 Installation of Lighting Fittings 5 14-Jan-13 19-Jan-13 28-Feb-13 05-Mar-13 38
PlumbingPlumbing 24 23-Dec-12 20-Jan-13 19-Feb-13 05-Mar-13 37
A91440 H/L Drainage Pipes Installation 4 23-Dec-12 26-Dec-12 23-Feb-13 26-Feb-13 51
A91450 H/L Hot&Cold Water Pipe Installation 7 23-Dec-12 30-Dec-12 19-Feb-13 26-Feb-13 48
A91460 Drainage&Water Pipes Testing 6 31-Dec-12 07-Jan-13 27-Feb-13 05-Mar-13 48
A91470 Floor Drain Fixning 6 14-Jan-13 20-Jan-13 27-Feb-13 05-Mar-13 37
Fire FighFire Fighting 25 23-Dec-12 21-Jan-13 12-Feb-13 24-Apr-13 79
A91430 Fire Fighting Pipe 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42
A91420 Hydro Static Test for Pipes 7 31-Dec-12 08-Jan-13 20-Feb-13 27-Feb-13 42
A91410 Sprinkler Fixing 5 09-Jan-13 14-Jan-13 28-Feb-13 05-Mar-13 42
A91400 Installation of Fire Extingusher&Blanket 3 15-Jan-13 17-Jan-13 22-Apr-13 24-Apr-13 82
A91340 Fire Alarm Devices 6 15-Jan-13 21-Jan-13 14-Apr-13 20-Apr-13 75
Electrical /Electrical / GSM / Telephone Room 65 16-Dec-12 03-Mar-13 29-Dec-12 28-Apr-13 48
FinishingFinishing Works 65 16-Dec-12 03-Mar-13 29-Dec-12 28-Apr-13 48
Wet WorWet Works 31 16-Dec-12 21-Jan-13 29-Dec-12 23-Apr-13 78
A91120 Block Works 10 16-Dec-12 26-Dec-12 29-Dec-12 09-Jan-13 11
A91080 Installation of Doors& Windows Sub-frame 2 30-Dec-12 31-Dec-12 22-Apr-13 23-Apr-13 95
A91070 Plaster Works 9 30-Dec-12 09-Jan-13 13-Jan-13 22-Jan-13 11
A91090 1st Coat Paint 8 13-Jan-13 21-Jan-13 27-Jan-13 04-Feb-13 11
Fisrt StaFisrt Stage Finishes 44 02-Jan-13 23-Feb-13 18-Apr-13 25-Apr-13 53
A91110 Installation of Doors 2 02-Jan-13 03-Jan-13 24-Apr-13 25-Apr-13 95
A91130 Doors Ironmongery 2 02-Jan-13 03-Jan-13 24-Apr-13 25-Apr-13 95
A91180 Epoxy Paint Works 2 21-Feb-13 23-Feb-13 18-Apr-13 20-Apr-13 48
Second SSecond Stage Finishes 5 24-Feb-13 28-Feb-13 21-Apr-13 25-Apr-13 48
A91100 Final Coat Paint 5 24-Feb-13 28-Feb-13 21-Apr-13 25-Apr-13 48
Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48
A91170 Installation of Sinages 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48
MEP WorkMEP Works 46 27-Dec-12 20-Feb-13 10-Jan-13 17-Apr-13 48
HVACHVAC 2 22-Jan-13 23-Jan-13 04-Mar-13 05-Mar-13 34
A91210 Air-Outlet Installation 2 22-Jan-13 23-Jan-13 04-Mar-13 05-Mar-13 34
ElectricalElectrical 46 27-Dec-12 20-Feb-13 10-Jan-13 05-Mar-13 11
A91140 Install Conduits in Wall 2 27-Dec-12 29-Dec-12 10-Jan-13 12-Jan-13 11
A91150 Wiring for Lighting & Power 2 10-Jan-13 12-Jan-13 23-Jan-13 26-Jan-13 11
A91200 Installation of SMDBs 7 22-Jan-13 30-Jan-13 24-Feb-13 03-Mar-13 27
A91160 Installation of Lighting Fittings 2 31-Jan-13 02-Feb-13 04-Mar-13 05-Mar-13 27
A114910 Installation of Telephone System 21 22-Jan-13 16-Feb-13 10-Feb-13 05-Mar-13 15
A114920 Installation of GSM System 25 22-Jan-13 20-Feb-13 05-Feb-13 05-Mar-13 11
Fire FighFire Fighting 2 03-Feb-13 04-Feb-13 16-Apr-13 17-Apr-13 62
A91190 Fire Alarm Devices 2 03-Feb-13 04-Feb-13 16-Apr-13 17-Apr-13 62
ELV RoomELV Room 49 16-Dec-12 12-Feb-13 15-Jan-13 28-Apr-13 64
FinishingFinishing Works 49 16-Dec-12 12-Feb-13 15-Jan-13 28-Apr-13 64
Wet WorWet Works 22 16-Dec-12 10-Jan-13 15-Jan-13 23-Apr-13 87
A91540 Block Works 4 16-Dec-12 19-Dec-12 15-Jan-13 19-Jan-13 25
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Final Coat Paint
Installation of Sinages
Installation of Carpets
Installation of Furnitur
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Wiring for Lighting & Power
Wiring for Low Current System
Cable Laying for Low Current System
Cable Laying for Power
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Installation of Primary Chilled Water Pump
Installation of SecondaryChilled Water Pump
Installation of Heat Exchanger
Installation of Heat Exchanger Pump
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Installation of GSM System
Fire Alarm Devices
Block Works
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 81 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A91500 Installation of Doors& Windows Sub-frame 2 23-Dec-12 24-Dec-12 22-Apr-13 23-Apr-13 101
A91490 Plaster Works 7 23-Dec-12 30-Dec-12 22-Jan-13 30-Jan-13 25
A91510 1st Coat Paint 7 03-Jan-13 10-Jan-13 03-Feb-13 10-Feb-13 25
Fisrt StaFisrt Stage Finishes 36 25-Dec-12 06-Feb-13 21-Apr-13 25-Apr-13 67
A91530 Installation of Doors 2 25-Dec-12 26-Dec-12 24-Apr-13 25-Apr-13 101
A91550 Doors Ironmongery 2 25-Dec-12 26-Dec-12 24-Apr-13 25-Apr-13 101
A91600 Epoxy Paint Works 2 05-Feb-13 06-Feb-13 21-Apr-13 22-Apr-13 64
Second SSecond Stage Finishes 3 07-Feb-13 10-Feb-13 23-Apr-13 25-Apr-13 64
A91520 Final Coat Paint 3 07-Feb-13 10-Feb-13 23-Apr-13 25-Apr-13 64
Final StaFinal Stage Finishes 2 11-Feb-13 12-Feb-13 27-Apr-13 28-Apr-13 64
A91590 Installation of Sinages 2 11-Feb-13 12-Feb-13 27-Apr-13 28-Apr-13 64
MEP WorkMEP Works 38 20-Dec-12 04-Feb-13 20-Jan-13 20-Apr-13 64
HVACHVAC 6 12-Jan-13 17-Jan-13 27-Feb-13 05-Mar-13 39
A91630 Air-Outlet Installation 6 12-Jan-13 17-Jan-13 27-Feb-13 05-Mar-13 39
ElectricalElectrical 38 20-Dec-12 04-Feb-13 20-Jan-13 05-Mar-13 25
A91560 Install Conduits in Wall 2 20-Dec-12 22-Dec-12 20-Jan-13 21-Jan-13 25
A91570 Wiring for Lighting & Power 2 31-Dec-12 02-Jan-13 31-Jan-13 02-Feb-13 25
A91580 Installation of Lighting Fittings 2 12-Jan-13 13-Jan-13 04-Mar-13 05-Mar-13 43
A114930 Installation of Access ControlSystem 20 12-Jan-13 04-Feb-13 11-Feb-13 05-Mar-13 25
A114940 Installation of MATC,TV System 20 12-Jan-13 04-Feb-13 11-Feb-13 05-Mar-13 25
Fire FighFire Fighting 8 14-Jan-13 22-Jan-13 11-Apr-13 20-Apr-13 74
A91610 Fire Alarm Devices 8 14-Jan-13 22-Jan-13 11-Apr-13 20-Apr-13 74
Chillers RoChillers Room 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35
FinishingFinishing Works 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35
Wet WorWet Works 6 13-Nov-12 20-Nov-12 27-Nov-12 24-Mar-13 103
A91690 Block Works 2 13-Nov-12 14-Nov-12 23-Mar-13 24-Mar-13 107
A91720 Water Proofing Works 6 13-Nov-12 20-Nov-12 27-Nov-12 04-Dec-12 11
Fisrt StaFisrt Stage Finishes 19 21-Feb-13 14-Mar-13 03-Apr-13 24-Apr-13 35
A91650 Installation of Doors& Windows Sub-frame 1 21-Feb-13 21-Feb-13 21-Apr-13 21-Apr-13 50
A91640 Plaster Works 2 21-Feb-13 23-Feb-13 03-Apr-13 04-Apr-13 35
A91660 1st Coat Paint 3 24-Feb-13 26-Feb-13 06-Apr-13 08-Apr-13 35
A91750 Floor Tiles Works 11 27-Feb-13 11-Mar-13 09-Apr-13 21-Apr-13 35
A91680 Installation of Doors 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35
A91700 Doors Ironmongery 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35
Second SSecond Stage Finishes 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35
A91670 Final Coat Paint 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35
Final StaFinal Stage Finishes 3 16-Mar-13 18-Mar-13 25-Apr-13 28-Apr-13 35
A91710 Installation of Sinages 3 16-Mar-13 18-Mar-13 25-Apr-13 28-Apr-13 35
MEP WorkMEP Works 76 21-Nov-12 20-Feb-13 05-Dec-12 05-Mar-13 11
HVACHVAC 76 21-Nov-12 20-Feb-13 05-Dec-12 05-Mar-13 11
A91730 Chilled Water Pipe Installation & Insulation 51 21-Nov-12 21-Jan-13 05-Dec-12 04-Feb-13 11
A91740 Installation of Chillers 51 21-Nov-12 21-Jan-13 05-Dec-12 04-Feb-13 11
A91820 Flushing for Chiled Water Pipes 25 22-Jan-13 20-Feb-13 05-Feb-13 05-Mar-13 11
GRP TankGRP Tank 35 16-Dec-12 27-Jan-13 23-Jan-13 05-Mar-13 32
FinishingFinishing Works 20 16-Dec-12 08-Jan-13 23-Jan-13 16-Feb-13 32
A91770 Water Proofing for Roof Area 10 16-Dec-12 26-Dec-12 23-Jan-13 04-Feb-13 32
A91780 Floor Tiles Work 10 27-Dec-12 08-Jan-13 05-Feb-13 16-Feb-13 32
MEP WorkMEP Works 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32
PlumbingPlumbing 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32
A91760 Installation of GRP Tank 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32
Boiler RooBoiler Room 57 16-Dec-12 21-Feb-13 21-Jan-13 28-Apr-13 56
FinishingFinishing Works 57 16-Dec-12 21-Feb-13 21-Jan-13 28-Apr-13 56
A91790 Water Proofing for Boiler Area 9 16-Dec-12 25-Dec-12 21-Jan-13 31-Jan-13 30
A91800 Installation of Steel Support 10 30-Jan-13 10-Feb-13 06-Apr-13 16-Apr-13 56
A91810 Installation of Louver 10 11-Feb-13 21-Feb-13 17-Apr-13 28-Apr-13 56
MEP WorkMEP Works 45 26-Dec-12 18-Feb-13 02-Feb-13 24-Apr-13 56
PlumbingPlumbing 28 26-Dec-12 29-Jan-13 02-Feb-13 05-Mar-13 30
A105100 Installation of Hot Water Boiler 7 26-Dec-12 03-Jan-13 02-Feb-13 09-Feb-13 30
A105240 Floor Drain Fixning 7 26-Dec-12 03-Jan-13 26-Feb-13 05-Mar-13 51
A105110 Installation of Hot Water Tank 7 05-Jan-13 12-Jan-13 10-Feb-13 17-Feb-13 30
A105120 Installation of Hot Water Pump 7 13-Jan-13 20-Jan-13 18-Feb-13 25-Feb-13 30
A105130 Installation of Pipes 7 21-Jan-13 29-Jan-13 26-Feb-13 05-Mar-13 30
Fire FighFire Fighting 7 11-Feb-13 18-Feb-13 17-Apr-13 24-Apr-13 56
A105170 Fire Alarm Devices 7 11-Feb-13 18-Feb-13 17-Apr-13 24-Apr-13 56
Upper Roof LUpper Roof Level 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104
Public AreaPublic Area 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104
Roof AreaRoof Area 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104
FinishingFinishing Works 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104
A91050 Water Proofing for Roof Area 15 20-Nov-12 08-Dec-12 07-Mar-13 24-Mar-13 89
A91060 Floor Tiles Work 15 09-Dec-12 25-Dec-12 11-Apr-13 28-Apr-13 104
ResidentialResidential (Block C) 389 02-Jun-12 10-Sep-13 29-Aug-12 02-Oct-13 19
2nd Basemen2nd Basement Floor 226 02-Jun-12 02-Mar-13 10-Oct-12 16-Apr-13 39
Public AreaPublic Area 226 02-Jun-12 02-Mar-13 10-Oct-12 16-Apr-13 39
Parking ArParking Area 213 18-Jun-12 02-Mar-13 28-Oct-12 16-Apr-13 39
FinishingFinishing Works 213 18-Jun-12 02-Mar-13 28-Oct-12 16-Apr-13 39
Wet WorWet Works 159 18-Jun-12 26-Dec-12 28-Oct-12 12-Feb-13 39
A67900 Plaster Works 5 18-Jun-12 23-Jun-12 28-Oct-12 01-Nov-12 109
A67910 1st Coat Paint 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39
Traffic DTraffic Deck Coating 49 27-Dec-12 24-Feb-13 13-Feb-13 16-Apr-13 44
A116170 Installation of Kerbs 8 27-Dec-12 06-Jan-13 13-Feb-13 21-Feb-13 39
A116180 Installation of Interlocking Tiles 8 07-Jan-13 15-Jan-13 23-Feb-13 03-Mar-13 39
A67840 Surface Preparation (including Grinding & Repairing) 8 16-Jan-13 26-Jan-13 04-Mar-13 12-Mar-13 39
A67850 Application of 1st Coat 7 22-Jan-13 30-Jan-13 10-Mar-13 17-Mar-13 39
A67890 Application of Final Coat 7 31-Jan-13 07-Feb-13 18-Mar-13 25-Mar-13 39
A67870 Road Marking & Arrows 7 09-Feb-13 16-Feb-13 26-Mar-13 02-Apr-13 39
A116190 Installation of Speed Hump 7 17-Feb-13 24-Feb-13 09-Apr-13 16-Apr-13 44
Final StaFinal Stage Finishes 12 17-Feb-13 02-Mar-13 03-Apr-13 16-Apr-13 39
A67920 Final Coat Paint 5 17-Feb-13 21-Feb-13 03-Apr-13 08-Apr-13 39
A67940 Installation of Sinages 7 23-Feb-13 02-Mar-13 09-Apr-13 16-Apr-13 39
MEP WorkMEP Works 147 18-Jun-12 12-Dec-12 13-Dec-12 29-Jan-13 39
HVACHVAC 12 08-Jul-12 21-Jul-12 15-Jan-13 29-Jan-13 157
A67960 Chilled Water Pipe Installation & Insulation 7 08-Jul-12 15-Jul-12 15-Jan-13 22-Jan-13 157
A67970 Condensate Pipe Installation 7 08-Jul-12 15-Jul-12 17-Jan-13 26-Jan-13 159
A68040 Installation of Induction Fans 3 16-Jul-12 18-Jul-12 27-Jan-13 29-Jan-13 159
A67520 Diesil Engine Exhust 12 08-Jul-12 21-Jul-12 15-Jan-13 29-Jan-13 157
ElectricalElectrical 147 18-Jun-12 12-Dec-12 13-Dec-12 29-Jan-13 39
A116200 Instalaltion of Cable Trays 10 18-Jun-12 28-Jun-12 13-Dec-12 24-Dec-12 147
A116210 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 18-Dec-12 05-Jan-13 39
A116220 Cable Pulling 10 19-Nov-12 29-Nov-12 06-Jan-13 16-Jan-13 39
A67930 Installation of Lighting Fittings 10 01-Dec-12 12-Dec-12 17-Jan-13 29-Jan-13 39
PlumbingPlumbing 12 18-Jun-12 01-Jul-12 15-Jan-13 29-Jan-13 174
A68030 Floor Drain Fixning 4 18-Jun-12 21-Jun-12 26-Jan-13 29-Jan-13 182
A68010 H/L Hot&Cold Water Pipe Installation 7 18-Jun-12 25-Jun-12 15-Jan-13 22-Jan-13 174
A68020 Water Pipes Testing 5 26-Jun-12 01-Jul-12 23-Jan-13 29-Jan-13 174
Fire FighFire Fighting 39 20-Jun-12 04-Aug-12 13-Dec-12 29-Jan-13 145
A68000 Fire Fighting Pipe 8 20-Jun-12 28-Jun-12 13-Dec-12 22-Dec-12 145
A67990 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 08-Jan-13 13-Jan-13 158
A67980 Sprinkler Fixing 7 05-Jul-12 12-Jul-12 14-Jan-13 21-Jan-13 158
A67950 Fire Alarm Devices 6 29-Jul-12 04-Aug-12 22-Jan-13 29-Jan-13 145
Lift LobbyLift Lobby 119 02-Jun-12 21-Oct-12 10-Oct-12 16-Apr-13 146
FinishingFinishing Works 119 02-Jun-12 21-Oct-12 10-Oct-12 16-Apr-13 146
Wet WorWet Works 53 02-Jun-12 02-Aug-12 10-Oct-12 30-Dec-12 122
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Installation of Access Control System
Installation of MATC,TV System
Fire Alarm Devices
Block Works
Water Proofing Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Floor Tiles Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Installation of Chillers
Flushing for Chiled Water Pipes
Water Proofing for Roof Area
Floor Tiles Work
Installation of GRP Tank
Water Proofing for Boiler Area
Installation of Steel Support
Installation of Louver
Installation of Hot Water Boiler
Floor Drain Fixning
Installation of Hot Water Tank
Installation of Hot Water Pump
Installation of Pipes
Fire Alarm Devices
Water Proofing for Roof Area
Floor Tiles Work
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Installation of Induction Fans
Diesil Engine Exhust
Instalaltion of Cable Trays
Instalaltion of Bus Bars
Cable Pulling
Installation of Lighting Fittings
Floor Drain Fixning
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 82 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A67580 Block Works 5 02-Jun-12 06-Jun-12 10-Oct-12 15-Oct-12 109
A67530 Plaster Works 7 24-Jun-12 01-Jul-12 03-Nov-12 10-Nov-12 109
A67550 Installation of Suspended Ceiling Grid 7 16-Jul-12 23-Jul-12 15-Dec-12 22-Dec-12 124
A67540 1st Coat Paint 7 26-Jul-12 02-Aug-12 23-Dec-12 30-Dec-12 122
Fisrt StaFisrt Stage Finishes 23 04-Aug-12 01-Sep-12 31-Dec-12 06-Feb-13 130
A67560 Suspended Ceiling Tiles 7 04-Aug-12 11-Aug-12 31-Dec-12 08-Jan-13 122
A67800 MDF for Lift Lobby Wall 7 14-Aug-12 23-Aug-12 21-Jan-13 29-Jan-13 130
A67780 Screed Works 7 25-Aug-12 01-Sep-12 30-Jan-13 06-Feb-13 130
Second SSecond Stage Finishes 14 02-Sep-12 17-Sep-12 07-Feb-13 23-Feb-13 130
A67790 Wall Tiles Work 7 02-Sep-12 09-Sep-12 07-Feb-13 14-Feb-13 130
A67820 Floor Tiles Work 7 10-Sep-12 17-Sep-12 16-Feb-13 23-Feb-13 130
Final StaFinal Stage Finishes 29 18-Sep-12 21-Oct-12 24-Feb-13 16-Apr-13 146
A67570 Installation of Doors 7 18-Sep-12 25-Sep-12 24-Feb-13 03-Mar-13 130
A67590 Doors Ironmongery 7 19-Sep-12 26-Sep-12 09-Apr-13 16-Apr-13 167
A67830 Final Coat Paint 7 03-Oct-12 10-Oct-12 26-Mar-13 02-Apr-13 143
A67770 Installation of Sinages 7 14-Oct-12 21-Oct-12 09-Apr-13 16-Apr-13 146
MEP WorkMEP Works 98 07-Jun-12 02-Oct-12 23-Oct-12 25-Mar-13 143
HVACHVAC 49 24-Jun-12 21-Aug-12 29-Nov-12 05-Mar-13 162
A67600 Duct Installation & Insulation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131
A67610 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131
A67620 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131
A67630 FCU Installation 7 30-Jun-12 07-Jul-12 06-Dec-12 13-Dec-12 131
A67640 Air-Outlet Installation 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162
ElectricalElectrical 98 07-Jun-12 02-Oct-12 23-Oct-12 16-Jan-13 86
A67650 Install Conduits in Wall 7 07-Jun-12 14-Jun-12 23-Oct-12 01-Nov-12 115
A67660 Install Cable Trays & Trunking 7 07-Jun-12 14-Jun-12 31-Oct-12 07-Nov-12 120
A67700 Cable Laying for Low Current System 7 16-Jun-12 24-Jun-12 15-Dec-12 22-Dec-12 149
A67710 Cable Laying for Power 7 16-Jun-12 24-Jun-12 15-Dec-12 22-Dec-12 149
A67670 Wiring for Lighting & Power 7 02-Jul-12 09-Jul-12 06-Dec-12 13-Dec-12 129
A67680 Wiring for Low Current System 7 02-Jul-12 09-Jul-12 06-Dec-12 13-Dec-12 129
A67690 DB installation,Dressing & Termination 7 24-Jul-12 31-Jul-12 31-Dec-12 08-Jan-13 131
A67730 Installation of Lighting Fittings 7 25-Sep-12 02-Oct-12 09-Jan-13 16-Jan-13 86
Fire FighFire Fighting 59 11-Jun-12 21-Aug-12 27-Nov-12 25-Mar-13 179
A67760 Fire Fighting Pipe 7 11-Jun-12 19-Jun-12 27-Nov-12 05-Dec-12 139
A67750 Hydro Static Test for Pipes 7 20-Jun-12 27-Jun-12 06-Dec-12 13-Dec-12 139
A67740 Sprinkler Fixing 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162
A67810 Fire Alarm Devices 7 12-Aug-12 21-Aug-12 18-Mar-13 25-Mar-13 179
MechanicaMechanical Rooms 109 07-Jun-12 15-Oct-12 16-Oct-12 16-Apr-13 151
FinishingFinishing Works 109 07-Jun-12 15-Oct-12 16-Oct-12 16-Apr-13 151
Wet WorWet Works 35 07-Jun-12 18-Jul-12 16-Oct-12 18-Feb-13 176
A67170 Block Works 2 07-Jun-12 09-Jun-12 16-Oct-12 17-Oct-12 109
A67130 Installation of Doors& Windows Sub-frame 2 02-Jul-12 03-Jul-12 17-Feb-13 18-Feb-13 189
A67120 Plaster Works 5 02-Jul-12 07-Jul-12 11-Nov-12 17-Nov-12 109
A67140 1st Coat Paint 6 12-Jul-12 18-Jul-12 22-Nov-12 28-Nov-12 109
Fisrt StaFisrt Stage Finishes 34 06-Aug-12 16-Sep-12 19-Feb-13 06-Apr-13 167
A67160 Installation of Doors 2 06-Aug-12 07-Aug-12 19-Feb-13 20-Feb-13 161
A67230 Epoxy Paint Works 2 11-Aug-12 12-Aug-12 27-Feb-13 28-Feb-13 164
A67180 Doors Ironmongery 2 15-Sep-12 16-Sep-12 04-Apr-13 06-Apr-13 167
Second SSecond Stage Finishes 2 13-Aug-12 14-Aug-12 20-Mar-13 21-Mar-13 180
A67150 Final Coat Paint 2 13-Aug-12 14-Aug-12 20-Mar-13 21-Mar-13 180
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151
A67220 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151
MEP WorkMEP Works 47 16-Jun-12 09-Aug-12 06-Nov-12 26-Feb-13 164
HVACHVAC 15 19-Jul-12 05-Aug-12 29-Nov-12 17-Dec-12 109
A67240 Shaft Works 15 19-Jul-12 05-Aug-12 29-Nov-12 17-Dec-12 109
ElectricalElectrical 47 16-Jun-12 09-Aug-12 06-Nov-12 22-Dec-12 109
A67190 Install Conduits in Wall 4 16-Jun-12 20-Jun-12 06-Nov-12 10-Nov-12 118
A67200 Wiring for Lighting & Power 4 08-Jul-12 11-Jul-12 18-Nov-12 21-Nov-12 109
A67210 Installation of Lighting Fittings 4 06-Aug-12 09-Aug-12 18-Dec-12 22-Dec-12 109
PlumbingPlumbing 3 19-Jul-12 22-Jul-12 24-Feb-13 26-Feb-13 180
A67250 Floor Drain Fixning 3 19-Jul-12 22-Jul-12 24-Feb-13 26-Feb-13 180
Pump RooPump Room 107 10-Jun-12 15-Oct-12 18-Oct-12 16-Apr-13 151
FinishingFinishing Works 107 10-Jun-12 15-Oct-12 18-Oct-12 16-Apr-13 151
Wet WorWet Works 39 10-Jun-12 25-Jul-12 18-Oct-12 20-Feb-13 172
A67310 Block Works 6 10-Jun-12 16-Jun-12 18-Oct-12 24-Oct-12 109
A67270 Installation of Doors& Windows Sub-frame 2 08-Jul-12 09-Jul-12 19-Feb-13 20-Feb-13 186
A67260 Plaster Works 6 08-Jul-12 14-Jul-12 24-Nov-12 29-Nov-12 114
A67280 1st Coat Paint 6 19-Jul-12 25-Jul-12 05-Dec-12 11-Dec-12 113
Fisrt StaFisrt Stage Finishes 34 08-Aug-12 18-Sep-12 21-Feb-13 08-Apr-13 167
A67300 Installation of Doors 2 08-Aug-12 09-Aug-12 21-Feb-13 23-Feb-13 161
A67370 Epoxy Paint Works 2 23-Aug-12 25-Aug-12 02-Mar-13 03-Mar-13 157
A67320 Doors Ironmongery 2 17-Sep-12 18-Sep-12 07-Apr-13 08-Apr-13 167
Second SSecond Stage Finishes 3 26-Aug-12 28-Aug-12 23-Mar-13 25-Mar-13 173
A67290 Final Coat Paint 3 26-Aug-12 28-Aug-12 23-Mar-13 25-Mar-13 173
Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151
A67360 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151
MEP WorkMEP Works 55 18-Jun-12 22-Aug-12 20-Nov-12 25-Mar-13 178
HVACHVAC 19 30-Jun-12 21-Jul-12 07-Jan-13 25-Feb-13 180
A67390 Duct Installation & Insulation 7 30-Jun-12 07-Jul-12 17-Jan-13 26-Jan-13 166
A67400 Chilled Water Pipe Installation & Insulation 7 30-Jun-12 07-Jul-12 07-Jan-13 14-Jan-13 157
A67410 Condensate Pipe Installation 7 30-Jun-12 07-Jul-12 09-Jan-13 16-Jan-13 159
A67420 FCU Installation 5 08-Jul-12 12-Jul-12 12-Feb-13 17-Feb-13 180
A67430 Air-Outlet Installation 7 14-Jul-12 21-Jul-12 18-Feb-13 25-Feb-13 180
ElectricalElectrical 35 21-Jun-12 31-Jul-12 20-Nov-12 17-Dec-12 113
A67330 Install Conduits in Wall 3 21-Jun-12 24-Jun-12 20-Nov-12 22-Nov-12 125
A67340 Wiring for Lighting & Power 3 15-Jul-12 17-Jul-12 01-Dec-12 04-Dec-12 114
A67350 Installation of Lighting Fittings 5 26-Jul-12 31-Jul-12 12-Dec-12 17-Dec-12 113
PlumbingPlumbing 39 18-Jun-12 01-Aug-12 17-Feb-13 28-Feb-13 173
A67480 H/L Hot&Cold Water Pipe Installation 7 18-Jun-12 25-Jun-12 17-Feb-13 24-Feb-13 201
A67490 Water Pipes Testing 4 26-Jun-12 30-Jun-12 25-Feb-13 28-Feb-13 201
A67010 Installation of Sump Pump 6 26-Jul-12 01-Aug-12 23-Feb-13 28-Feb-13 173
A67500 Installation of Transfer Pump 6 26-Jul-12 01-Aug-12 23-Feb-13 28-Feb-13 173
Fire FighFire Fighting 45 30-Jun-12 22-Aug-12 23-Dec-12 25-Mar-13 178
A67470 Fire Fighting Pipe 7 30-Jun-12 07-Jul-12 23-Dec-12 30-Dec-12 145
A67460 Hydro Static Test for Pipes 7 08-Jul-12 15-Jul-12 31-Dec-12 08-Jan-13 145
A67450 Sprinkler Fixing 5 16-Jul-12 21-Jul-12 09-Jan-13 14-Jan-13 145
A67380 Fire Alarm Devices 6 22-Jul-12 28-Jul-12 15-Jan-13 21-Jan-13 145
A67440 Installation of Fire Extingusher&Blanket 3 29-Jul-12 31-Jul-12 23-Mar-13 25-Mar-13 195
A67510 Installation of Fire Fighting Pump 10 09-Aug-12 22-Aug-12 18-Feb-13 28-Feb-13 157
Water TankWater Tank 1 (Block C1) 29 28-Jul-12 01-Sep-12 10-Nov-12 24-Feb-13 145
FinishingFinishing Works 21 28-Jul-12 22-Aug-12 10-Nov-12 05-Dec-12 86
A66990 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 10-Nov-12 18-Nov-12 86
A66980 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 19-Nov-12 26-Nov-12 86
A67000 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 27-Nov-12 05-Dec-12 86
MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 23-Dec-12 24-Feb-13 145
ElectricalElectrical 7 23-Aug-12 30-Aug-12 23-Dec-12 30-Dec-12 100
A67040 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 23-Dec-12 30-Dec-12 100
PlumbingPlumbing 8 23-Aug-12 01-Sep-12 16-Feb-13 24-Feb-13 145
A67020 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 16-Feb-13 20-Feb-13 145
A67030 Install of Water Meter 3 29-Aug-12 01-Sep-12 21-Feb-13 24-Feb-13 145
Water TankWater Tank 2 (Block C2) 29 23-Aug-12 25-Sep-12 06-Dec-12 05-Mar-13 132
FinishingFinishing Works 21 23-Aug-12 16-Sep-12 06-Dec-12 30-Dec-12 86
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
MDF for Lift Lobby Wall
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Shaft Works
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Floor Drain Fixning
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Epoxy Paint Works
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes Testing
Installation of Sump Pump
Installation of Transfer Pump
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Installation of Fire Fighting Pump
GRP Lining on the Ceiling
GRP Lining on the Wall
Reinforced Plastic on the Floor
Installation of Lighting Fittings
Installation of Water Supply Pipes&Fittings
Install of Water Meter
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 83 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A67060 GRP Lining on the Ceiling 7 23-Aug-12 30-Aug-12 06-Dec-12 13-Dec-12 86
A67050 GRP Lining on the Wall 7 01-Sep-12 08-Sep-12 15-Dec-12 22-Dec-12 86
A67070 Reinforced Plastic on the Floor 7 09-Sep-12 16-Sep-12 23-Dec-12 30-Dec-12 86
MEP WorkMEP Works 8 17-Sep-12 25-Sep-12 31-Dec-12 05-Mar-13 132
ElectricalElectrical 7 17-Sep-12 24-Sep-12 31-Dec-12 08-Jan-13 86
A67110 Installation of Lighting Fittings 7 17-Sep-12 24-Sep-12 31-Dec-12 08-Jan-13 86
PlumbingPlumbing 8 17-Sep-12 25-Sep-12 25-Feb-13 05-Mar-13 132
A67090 Installation of Water Supply Pipes&Fittings 5 17-Sep-12 22-Sep-12 25-Feb-13 02-Mar-13 132
A67100 Install of Water Meter 3 23-Sep-12 25-Sep-12 03-Mar-13 05-Mar-13 132
StaircaseStaircase 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192
Stairs 1Stairs 1 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192
A111210 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166
A111250 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166
A111220 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111230 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111240 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166
A111260 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192
Stairs 2Stairs 2 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192
A111270 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166
A111310 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166
A111280 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111290 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111300 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166
A111320 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192
Stairs 3Stairs 3 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192
A111330 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166
A111370 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166
A111340 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111350 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166
A111360 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166
A111380 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192
1st Basemen1st Basement Floor 206 01-Jul-12 06-Mar-13 10-Nov-12 16-Apr-13 35
Public AreaPublic Area 206 01-Jul-12 06-Mar-13 10-Nov-12 16-Apr-13 35
Parking ArParking Area 196 12-Jul-12 06-Mar-13 22-Nov-12 16-Apr-13 35
FinishingFinishing Works 196 12-Jul-12 06-Mar-13 22-Nov-12 16-Apr-13 35
Wet WorWet Works 138 12-Jul-12 26-Dec-12 22-Nov-12 12-Feb-13 39
A68990 Plaster Works 5 12-Jul-12 17-Jul-12 22-Nov-12 27-Nov-12 109
A69000 1st Coat Paint 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39
Traffic DTraffic Deck Coating 53 27-Dec-12 28-Feb-13 13-Feb-13 16-Apr-13 40
A116260 Installation of Kerbs 8 27-Dec-12 06-Jan-13 13-Feb-13 21-Feb-13 39
A116270 Installation of Interlocking Tiles 8 07-Jan-13 15-Jan-13 23-Feb-13 03-Mar-13 39
A68930 Surface Preparation (including Grinding & Repairing) 8 21-Jan-13 30-Jan-13 04-Mar-13 12-Mar-13 35
A68940 Application of 1st Coat 7 28-Jan-13 04-Feb-13 10-Mar-13 17-Mar-13 35
A68980 Application of Final Coat 7 05-Feb-13 12-Feb-13 18-Mar-13 25-Mar-13 35
A68960 Road Marking & Arrows 7 13-Feb-13 20-Feb-13 26-Mar-13 02-Apr-13 35
A116280 Installation of Speed Hump 7 21-Feb-13 28-Feb-13 09-Apr-13 16-Apr-13 40
Final StaFinal Stage Finishes 12 21-Feb-13 06-Mar-13 03-Apr-13 16-Apr-13 35
A69010 Final Coat Paint 5 21-Feb-13 26-Feb-13 03-Apr-13 08-Apr-13 35
A69030 Installation of Sinages 7 27-Feb-13 06-Mar-13 09-Apr-13 16-Apr-13 35
MEP WorkMEP Works 126 12-Jul-12 12-Dec-12 18-Dec-12 29-Jan-13 39
HVACHVAC 10 12-Jul-12 23-Jul-12 17-Jan-13 29-Jan-13 155
A69050 Chilled Water Pipe Installation & Insulation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155
A69060 Condensate Pipe Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155
A69130 Installation of Induction Fans 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155
ElectricalElectrical 126 12-Jul-12 12-Dec-12 18-Dec-12 29-Jan-13 39
A116230 Instalaltion of Cable Trays 10 12-Jul-12 23-Jul-12 29-Dec-12 09-Jan-13 139
A116240 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 18-Dec-12 05-Jan-13 39
A116250 Cable Pulling 10 19-Nov-12 29-Nov-12 06-Jan-13 16-Jan-13 39
A69020 Installation of Lighting Fittings 10 01-Dec-12 12-Dec-12 17-Jan-13 29-Jan-13 39
PlumbingPlumbing 10 12-Jul-12 23-Jul-12 17-Jan-13 29-Jan-13 155
A69100 H/L Hot&Cold Water Pipe Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155
A69120 Floor Drain Fixning 7 12-Jul-12 19-Jul-12 21-Jan-13 29-Jan-13 158
A69140 H/L Drainage Pipes Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155
A69110 Water Pipes Testing 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155
A69150 Drainage&Water Pipes Testing 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155
Fire FighFire Fighting 26 21-Jul-12 21-Aug-12 29-Dec-12 29-Jan-13 132
A69090 Fire Fighting Pipe 8 21-Jul-12 29-Jul-12 29-Dec-12 07-Jan-13 132
A69080 Hydro Static Test for Pipes 5 30-Jul-12 04-Aug-12 08-Jan-13 13-Jan-13 132
A69070 Sprinkler Fixing 7 05-Aug-12 12-Aug-12 14-Jan-13 21-Jan-13 132
A69040 Fire Alarm Devices 6 13-Aug-12 21-Aug-12 22-Jan-13 29-Jan-13 132
Lift LobbyLift Lobby 86 05-Jul-12 15-Oct-12 14-Nov-12 16-Apr-13 151
FinishingFinishing Works 86 05-Jul-12 15-Oct-12 14-Nov-12 16-Apr-13 151
Wet WorWet Works 40 05-Jul-12 22-Aug-12 14-Nov-12 02-Jan-13 109
A68660 Block Works 6 05-Jul-12 11-Jul-12 14-Nov-12 21-Nov-12 109
A68610 Plaster Works 7 18-Jul-12 25-Jul-12 28-Nov-12 06-Dec-12 109
A68630 Installation of Suspended Ceiling Grid 2 30-Jul-12 31-Jul-12 25-Dec-12 26-Dec-12 121
A68620 1st Coat Paint 5 15-Aug-12 22-Aug-12 27-Dec-12 02-Jan-13 109
Fisrt StaFisrt Stage Finishes 9 23-Aug-12 02-Sep-12 03-Jan-13 13-Feb-13 135
A68880 MDF for Lift Lobby Wall 2 23-Aug-12 25-Aug-12 09-Feb-13 10-Feb-13 139
A68640 Suspended Ceiling Tiles 6 23-Aug-12 29-Aug-12 03-Jan-13 09-Jan-13 109
A68860 Screed Works 3 30-Aug-12 02-Sep-12 11-Feb-13 13-Feb-13 135
Second SSecond Stage Finishes 10 03-Sep-12 13-Sep-12 14-Feb-13 25-Feb-13 135
A68870 Wall Tiles Work 5 03-Sep-12 08-Sep-12 14-Feb-13 19-Feb-13 135
A68900 Floor Tiles Work 5 09-Sep-12 13-Sep-12 20-Feb-13 25-Feb-13 135
Final StaFinal Stage Finishes 27 15-Sep-12 15-Oct-12 26-Feb-13 16-Apr-13 151
A68650 Installation of Doors 2 15-Sep-12 16-Sep-12 26-Feb-13 27-Feb-13 135
A68670 Doors Ironmongery 2 15-Sep-12 16-Sep-12 09-Apr-13 10-Apr-13 171
A68910 Final Coat Paint 5 15-Sep-12 19-Sep-12 24-Mar-13 28-Mar-13 157
A68850 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151
MEP WorkMEP Works 47 12-Jul-12 06-Sep-12 25-Nov-12 23-Mar-13 163
HVACHVAC 47 12-Jul-12 06-Sep-12 11-Dec-12 05-Mar-13 148
A68680 Duct Installation & Insulation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124
A68690 Chilled Water Pipe Installation & Insulation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124
A68700 Condensate Pipe Installation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124
A68710 FCU Installation 7 18-Jul-12 25-Jul-12 17-Dec-12 24-Dec-12 124
A68720 Air-Outlet Installation 7 30-Aug-12 06-Sep-12 26-Feb-13 05-Mar-13 148
ElectricalElectrical 46 12-Jul-12 05-Sep-12 25-Nov-12 16-Jan-13 109
A68730 Install Conduits in Wall 3 12-Jul-12 15-Jul-12 25-Nov-12 27-Nov-12 111
A68740 Install Cable Trays & Trunking 4 12-Jul-12 16-Jul-12 29-Nov-12 04-Dec-12 115
A68780 Cable Laying for Low Current System 3 17-Jul-12 19-Jul-12 24-Dec-12 26-Dec-12 131
A68790 Cable Laying for Power 3 17-Jul-12 19-Jul-12 24-Dec-12 26-Dec-12 131
A68750 Wiring for Lighting & Power 3 26-Jul-12 29-Jul-12 22-Dec-12 24-Dec-12 121
A68760 Wiring for Low Current System 3 26-Jul-12 29-Jul-12 22-Dec-12 24-Dec-12 121
A68770 DB installation,Dressing & Termination 4 01-Aug-12 05-Aug-12 06-Jan-13 09-Jan-13 128
A68810 Installation of Lighting Fittings 6 30-Aug-12 05-Sep-12 10-Jan-13 16-Jan-13 109
Fire FighFire Fighting 47 12-Jul-12 06-Sep-12 12-Dec-12 23-Mar-13 163
A68840 Fire Fighting Pipe 7 12-Jul-12 19-Jul-12 12-Dec-12 19-Dec-12 125
A68830 Hydro Static Test for Pipes 4 21-Jul-12 24-Jul-12 20-Dec-12 24-Dec-12 125
A68820 Sprinkler Fixing 6 30-Aug-12 05-Sep-12 27-Feb-13 05-Mar-13 149
A68890 Fire Alarm Devices 7 30-Aug-12 06-Sep-12 16-Mar-13 23-Mar-13 163
MechanicaMechanical Rooms 149 01-Jul-12 27-Dec-12 10-Nov-12 16-Apr-13 92
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
GRP Lining on the Ceiling
GRP Lining on the Wall
Reinforced Plastic on the Floor
Installation of Lighting Fittings
Installation of Water Supply Pipes&Fittings
Install of Water Meter
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Plaster Works
1st Coat Paint
Installation of Kerbs
Installation of Interlocking Tiles
Surface Preparation (including Grinding & Repairing)
Application of 1st Coat
Application of Final Coat
Road Marking & Arrows
Installation of Speed Hump
Final Coat Paint
Installation of Sinages
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Installation of Induction Fans
Instalaltion of Cable Trays
Instalaltion of Bus Bars
Cable Pulling
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Floor Drain Fixning
H/L Drainage Pipes Installation
Water Pipes Testing
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
MDF for Lift Lobby Wall
Suspended Ceiling Tiles
Screed Works
Wall Tiles Work
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Lighting Fittings
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 84 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
FinishingFinishing Works 149 01-Jul-12 27-Dec-12 10-Nov-12 16-Apr-13 92
Wet WorWet Works 39 01-Jul-12 14-Aug-12 10-Nov-12 27-Feb-13 161
A68100 Block Works 4 01-Jul-12 04-Jul-12 10-Nov-12 13-Nov-12 109
A68060 Installation of Doors& Windows Sub-frame 3 26-Jul-12 29-Jul-12 25-Feb-13 27-Feb-13 175
A68050 Plaster Works 7 26-Jul-12 02-Aug-12 08-Dec-12 15-Dec-12 109
A68070 1st Coat Paint 6 08-Aug-12 14-Aug-12 20-Dec-12 26-Dec-12 109
Fisrt StaFisrt Stage Finishes 78 17-Sep-12 20-Dec-12 28-Feb-13 14-Apr-13 96
A68090 Installation of Doors 3 17-Sep-12 19-Sep-12 28-Feb-13 03-Mar-13 135
A68110 Doors Ironmongery 3 17-Sep-12 19-Sep-12 11-Apr-13 14-Apr-13 171
A68160 Epoxy Paint Works 3 18-Dec-12 20-Dec-12 28-Feb-13 03-Mar-13 60
Second SSecond Stage Finishes 4 22-Dec-12 25-Dec-12 30-Mar-13 02-Apr-13 82
A68080 Final Coat Paint 4 22-Dec-12 25-Dec-12 30-Mar-13 02-Apr-13 82
Final StaFinal Stage Finishes 2 26-Dec-12 27-Dec-12 15-Apr-13 16-Apr-13 92
A68150 Installation of Sinages 2 26-Dec-12 27-Dec-12 15-Apr-13 16-Apr-13 92
MEP WorkMEP Works 136 05-Jul-12 17-Dec-12 03-Dec-12 27-Feb-13 60
HVACHVAC 15 15-Aug-12 03-Sep-12 06-Feb-13 23-Feb-13 142
A68170 Shaft Works 15 15-Aug-12 03-Sep-12 06-Feb-13 23-Feb-13 142
ElectricalElectrical 136 05-Jul-12 17-Dec-12 03-Dec-12 27-Feb-13 60
A68120 Install Conduits in Wall 4 05-Jul-12 09-Jul-12 03-Dec-12 06-Dec-12 123
A68130 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 16-Dec-12 19-Dec-12 109
A68140 Installation of Lighting Fittings 4 13-Dec-12 17-Dec-12 24-Feb-13 27-Feb-13 60
PlumbingPlumbing 7 15-Aug-12 25-Aug-12 20-Feb-13 27-Feb-13 154
A68180 Floor Drain Fixning 7 15-Aug-12 25-Aug-12 20-Feb-13 27-Feb-13 154
StaircaseStaircase 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174
Stairs 1Stairs 1 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174
A111390 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148
A111430 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148
A111400 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111410 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111420 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148
A111440 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174
Stairs 2Stairs 2 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174
A111450 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148
A111490 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148
A111460 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111470 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111480 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148
A111500 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174
Stairs 3Stairs 3 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174
A111510 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148
A111550 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148
A111520 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111530 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148
A111540 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148
A111560 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174
Ground FloorGround Floor 134 22-Jul-12 31-Dec-12 03-Dec-12 16-Apr-13 89
Public AreaPublic Area 134 22-Jul-12 31-Dec-12 03-Dec-12 16-Apr-13 89
Super MarSuper Market 91 11-Sep-12 30-Dec-12 22-Jan-13 16-Apr-13 90
FinishingFinishing Works 91 11-Sep-12 30-Dec-12 22-Jan-13 16-Apr-13 90
Wet WorWet Works 26 11-Sep-12 10-Oct-12 22-Jan-13 30-Mar-13 140
A71470 Block Works 21 11-Sep-12 04-Oct-12 22-Jan-13 16-Feb-13 109
A71450 Installation of Doors& Windows Sub-frame 5 06-Oct-12 10-Oct-12 25-Mar-13 30-Mar-13 140
Final StaFinal Stage Finishes 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90
A71460 Installation of Windows&Doors 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90
A71480 Doors Ironmongery 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90
MEP WorkMEP Works 19 06-Oct-12 29-Oct-12 17-Feb-13 16-Apr-13 141
HVACHVAC 15 06-Oct-12 22-Oct-12 17-Feb-13 05-Mar-13 109
A71490 Chilled Water Pipe Installation & Insulation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109
A71500 Condensate Pipe Installation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109
A71640 Duct Installation & Insulation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109
A71510 FCU Installation 5 17-Oct-12 22-Oct-12 28-Feb-13 05-Mar-13 109
ElectricalElectrical 10 06-Oct-12 16-Oct-12 23-Feb-13 05-Mar-13 114
A71520 Install Conduits in Wall 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114
A71530 Wiring for Lighting & Power 3 14-Oct-12 16-Oct-12 03-Mar-13 05-Mar-13 114
PlumbingPlumbing 10 06-Oct-12 16-Oct-12 23-Feb-13 05-Mar-13 114
A71540 Drainge Pipes in Wall 7 06-Oct-12 13-Oct-12 26-Feb-13 05-Mar-13 117
A71550 H/L Drainage Pipes Installation 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114
A71560 H/L Hot&Cold Water Pipe Installation 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114
A71580 Water Pipes in Wall 7 06-Oct-12 13-Oct-12 26-Feb-13 05-Mar-13 117
A71570 Drainage&Water Pipes Testing 3 14-Oct-12 16-Oct-12 03-Mar-13 05-Mar-13 114
Fire FighFire Fighting 19 06-Oct-12 29-Oct-12 18-Feb-13 16-Apr-13 141
A71620 Fire Fighting Pipe 7 06-Oct-12 13-Oct-12 18-Feb-13 25-Feb-13 110
A71610 Hydro Static Test for Pipes 4 14-Oct-12 17-Oct-12 26-Feb-13 02-Mar-13 110
A71600 Sprinkler Fixing 3 18-Oct-12 21-Oct-12 03-Mar-13 05-Mar-13 110
A71590 Installation of Fire Extingusher&Blanket 2 22-Oct-12 23-Oct-12 15-Apr-13 16-Apr-13 144
A71630 Fire Alarm Devices 5 22-Oct-12 29-Oct-12 11-Apr-13 16-Apr-13 141
EnteranceEnterance - Lift Lobby - Super Market Corridor 112 11-Aug-12 25-Dec-12 23-Dec-12 16-Apr-13 94
FinishingFinishing Works 112 11-Aug-12 25-Dec-12 23-Dec-12 16-Apr-13 94
Wet WorWet Works 32 11-Aug-12 18-Sep-12 23-Dec-12 10-Feb-13 118
A71700 Block Works 5 11-Aug-12 15-Aug-12 23-Dec-12 27-Dec-12 109
A71650 Plaster Works 5 26-Aug-12 30-Aug-12 13-Jan-13 17-Jan-13 115
A71670 Installation of Suspended Ceiling Grid 7 04-Sep-12 11-Sep-12 22-Jan-13 30-Jan-13 115
A71660 1st Coat Paint 6 12-Sep-12 18-Sep-12 04-Feb-13 10-Feb-13 118
Fisrt StaFisrt Stage Finishes 8 23-Sep-12 01-Oct-12 11-Feb-13 18-Mar-13 138
A71680 Suspended Ceiling Tiles 6 23-Sep-12 29-Sep-12 11-Feb-13 17-Feb-13 115
A71880 Screed Works 2 30-Sep-12 01-Oct-12 17-Mar-13 18-Mar-13 138
Second SSecond Stage Finishes 58 02-Oct-12 12-Dec-12 19-Mar-13 30-Mar-13 90
A71920 Floor Tiles Work 6 02-Oct-12 08-Oct-12 19-Mar-13 25-Mar-13 138
A71710 Doors Ironmongery 3 09-Dec-12 11-Dec-12 27-Mar-13 30-Mar-13 91
A71690 Installation of Doors 4 09-Dec-12 12-Dec-12 26-Mar-13 30-Mar-13 90
Final StaFinal Stage Finishes 11 13-Dec-12 25-Dec-12 04-Apr-13 16-Apr-13 94
A71930 Final Coat Paint 7 13-Dec-12 20-Dec-12 04-Apr-13 11-Apr-13 94
A71870 Installation of Sinages 4 22-Dec-12 25-Dec-12 13-Apr-13 16-Apr-13 94
MEP WorkMEP Works 45 16-Aug-12 09-Oct-12 06-Jan-13 05-Mar-13 120
HVACHVAC 43 16-Aug-12 07-Oct-12 08-Jan-13 25-Feb-13 115
A71720 Duct Installation & Insulation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117
A71730 Chilled Water Pipe Installation & Insulation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117
A71740 Condensate Pipe Installation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117
A71750 FCU Installation 5 27-Aug-12 01-Sep-12 16-Jan-13 21-Jan-13 117
A71760 Air-Outlet Installation 7 30-Sep-12 07-Oct-12 18-Feb-13 25-Feb-13 115
ElectricalElectrical 42 16-Aug-12 06-Oct-12 09-Jan-13 05-Mar-13 123
A71770 Install Conduits in Wall 3 16-Aug-12 21-Aug-12 09-Jan-13 12-Jan-13 118
A71780 Install Cable Trays & Trunking 3 16-Aug-12 21-Aug-12 13-Jan-13 15-Jan-13 121
A71810 Cable Laying for Low Current System 5 22-Aug-12 27-Aug-12 26-Jan-13 30-Jan-13 128
A71820 Cable Laying for Power 5 22-Aug-12 27-Aug-12 26-Jan-13 30-Jan-13 128
A71790 Wiring for Lighting & Power 3 01-Sep-12 03-Sep-12 19-Jan-13 21-Jan-13 115
A71800 Wiring for Low Current System 3 01-Sep-12 03-Sep-12 19-Jan-13 21-Jan-13 115
A71830 Installation of Lighting Fittings 6 30-Sep-12 06-Oct-12 27-Feb-13 05-Mar-13 123
PlumbingPlumbing 14 16-Aug-12 03-Sep-12 26-Jan-13 10-Feb-13 131
A71970 H/L Hot&Cold Water Pipe Installation 7 16-Aug-12 26-Aug-12 26-Jan-13 02-Feb-13 131
A71980 Water Pipes in Wall 7 27-Aug-12 03-Sep-12 03-Feb-13 10-Feb-13 131
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Shaft Works
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Floor Drain Fixning
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Installation of Windows&Doors
Doors Ironmongery
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 85 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
Fire FighFire Fighting 45 16-Aug-12 09-Oct-12 06-Jan-13 05-Mar-13 120
A71860 Fire Fighting Pipe 7 16-Aug-12 26-Aug-12 06-Jan-13 13-Jan-13 115
A71850 Hydro Static Test for Pipes 7 27-Aug-12 03-Sep-12 14-Jan-13 21-Jan-13 115
A71840 Sprinkler Fixing 5 01-Oct-12 06-Oct-12 25-Feb-13 02-Mar-13 120
A71910 Fire Alarm Devices 7 30-Sep-12 07-Oct-12 24-Feb-13 03-Mar-13 120
A71950 Installation of Fire Hose Cabinet & Landing Valve 2 08-Oct-12 09-Oct-12 04-Mar-13 05-Mar-13 120
Retails - (1Retails - (1 - 8) 92 16-Aug-12 08-Dec-12 29-Dec-12 16-Apr-13 109
FinishingFinishing Works 92 16-Aug-12 08-Dec-12 29-Dec-12 26-Mar-13 91
Wet WorWet Works 32 16-Aug-12 24-Sep-12 29-Dec-12 11-Mar-13 138
A69180 Block Works 20 16-Aug-12 10-Sep-12 29-Dec-12 21-Jan-13 109
A69160 Installation of Doors& Windows Sub-frame 12 11-Sep-12 24-Sep-12 26-Feb-13 11-Mar-13 138
Final StaFinal Stage Finishes 12 24-Nov-12 08-Dec-12 12-Mar-13 26-Mar-13 91
A69170 Installation of Windows&Doors 12 24-Nov-12 08-Dec-12 12-Mar-13 25-Mar-13 90
A69190 Doors Ironmongery 10 26-Nov-12 08-Dec-12 16-Mar-13 26-Mar-13 91
MEP WorkMEP Works 19 11-Sep-12 02-Oct-12 05-Feb-13 16-Apr-13 162
HVACHVAC 15 11-Sep-12 27-Sep-12 05-Feb-13 27-Feb-13 125
A69200 Chilled Water Pipe Installation & Insulation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120
A69210 Condensate Pipe Installation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120
A69350 Duct Installation & Insulation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120
A69220 FCU Installation 5 23-Sep-12 27-Sep-12 23-Feb-13 27-Feb-13 125
ElectricalElectrical 10 11-Sep-12 22-Sep-12 23-Feb-13 05-Mar-13 135
A69230 Install Conduits in Wall 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135
A69240 Wiring for Lighting & Power 3 19-Sep-12 22-Sep-12 03-Mar-13 05-Mar-13 135
PlumbingPlumbing 10 11-Sep-12 22-Sep-12 23-Feb-13 05-Mar-13 135
A69250 Drainge Pipes in Wall 7 11-Sep-12 18-Sep-12 26-Feb-13 05-Mar-13 138
A69260 H/L Drainage Pipes Installation 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135
A69270 H/L Hot&Cold Water Pipe Installation 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135
A69290 Water Pipes in Wall 7 11-Sep-12 18-Sep-12 26-Feb-13 05-Mar-13 138
A69280 Drainage&Water Pipes Testing 3 19-Sep-12 22-Sep-12 03-Mar-13 05-Mar-13 135
Fire FighFire Fighting 19 11-Sep-12 02-Oct-12 05-Feb-13 16-Apr-13 162
A69330 Fire Fighting Pipe 7 11-Sep-12 18-Sep-12 05-Feb-13 12-Feb-13 120
A69320 Hydro Static Test for Pipes 4 19-Sep-12 23-Sep-12 13-Feb-13 17-Feb-13 120
A69310 Sprinkler Fixing 3 24-Sep-12 26-Sep-12 18-Feb-13 20-Feb-13 120
A69300 Installation of Fire Extingusher&Blanket 2 27-Sep-12 29-Sep-12 15-Apr-13 16-Apr-13 165
A69340 Fire Alarm Devices 5 27-Sep-12 02-Oct-12 11-Apr-13 16-Apr-13 162
Electrical /Electrical /Telephone / GSM Rooms 110 22-Jul-12 03-Dec-12 03-Dec-12 16-Apr-13 113
FinishingFinishing Works 110 22-Jul-12 03-Dec-12 03-Dec-12 16-Apr-13 113
Wet WorWet Works 21 22-Jul-12 14-Aug-12 03-Dec-12 21-Feb-13 156
A70810 Block Works 6 22-Jul-12 28-Jul-12 03-Dec-12 09-Dec-12 109
A70770 Installation of Doors& Windows Sub-frame 2 01-Aug-12 02-Aug-12 20-Feb-13 21-Feb-13 166
A70760 Plaster Works 5 01-Aug-12 06-Aug-12 20-Dec-12 25-Dec-12 115
A70780 1st Coat Paint 4 11-Aug-12 14-Aug-12 30-Dec-12 03-Jan-13 115
Fisrt StaFisrt Stage Finishes 38 09-Oct-12 25-Nov-12 27-Feb-13 14-Mar-13 91
A70870 Epoxy Paint Works 2 09-Oct-12 10-Oct-12 27-Feb-13 28-Feb-13 115
A70800 Installation of Doors 2 11-Oct-12 13-Oct-12 02-Mar-13 03-Mar-13 115
A70820 Doors Ironmongery 2 24-Nov-12 25-Nov-12 13-Mar-13 14-Mar-13 91
Second SSecond Stage Finishes 3 11-Oct-12 14-Oct-12 30-Mar-13 01-Apr-13 139
A70790 Final Coat Paint 3 11-Oct-12 14-Oct-12 30-Mar-13 01-Apr-13 139
Final StaFinal Stage Finishes 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113
A70860 Installation of Sinages 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113
MEP WorkMEP Works 60 29-Jul-12 08-Oct-12 17-Dec-12 01-Apr-13 144
HVACHVAC 7 15-Aug-12 25-Aug-12 10-Feb-13 17-Feb-13 145
A70890 Air-Outlet Installation 7 15-Aug-12 25-Aug-12 10-Feb-13 17-Feb-13 145
ElectricalElectrical 60 29-Jul-12 08-Oct-12 17-Dec-12 26-Feb-13 115
A70830 Install Conduits in Wall 3 29-Jul-12 31-Jul-12 17-Dec-12 19-Dec-12 115
A70840 Wiring for Lighting & Power 3 07-Aug-12 09-Aug-12 26-Dec-12 29-Dec-12 115
A114950 Installation of SMDBs 7 15-Aug-12 25-Aug-12 14-Feb-13 21-Feb-13 149
A70850 Installation of Lighting Fittings 4 26-Aug-12 29-Aug-12 23-Feb-13 26-Feb-13 149
A114960 Installation of Telephone System 21 15-Aug-12 10-Sep-12 03-Feb-13 26-Feb-13 139
A114970 Installation of GSM System 45 15-Aug-12 08-Oct-12 05-Jan-13 26-Feb-13 115
Fire FighFire Fighting 8 15-Aug-12 26-Aug-12 20-Feb-13 01-Apr-13 181
A70880 Fire Alarm Devices 6 15-Aug-12 23-Aug-12 20-Feb-13 26-Feb-13 154
A70900 Installation of Fire Extingusher&Blanket 2 25-Aug-12 26-Aug-12 31-Mar-13 01-Apr-13 181
Main GarbMain Garbage Room 128 29-Jul-12 31-Dec-12 10-Dec-12 16-Apr-13 89
FinishingFinishing Works 128 29-Jul-12 31-Dec-12 10-Dec-12 16-Apr-13 89
Wet WorWet Works 26 29-Jul-12 29-Aug-12 10-Dec-12 23-Feb-13 146
A70970 Block Works 4 29-Jul-12 01-Aug-12 10-Dec-12 13-Dec-12 109
A70920 Installation of Doors& Windows Sub-frame 1 07-Aug-12 07-Aug-12 23-Feb-13 23-Feb-13 163
A70910 Plaster Works 5 07-Aug-12 12-Aug-12 26-Dec-12 31-Dec-12 115
A71140 Wall Tiles Work 8 13-Aug-12 23-Aug-12 02-Jan-13 10-Jan-13 115
A70930 1st Coat Paint 3 27-Aug-12 29-Aug-12 14-Jan-13 16-Jan-13 115
Fisrt StaFisrt Stage Finishes 7 25-Aug-12 01-Sep-12 12-Jan-13 19-Jan-13 115
A71130 Screed Works 2 25-Aug-12 26-Aug-12 12-Jan-13 13-Jan-13 115
A71150 Floor Tiles Work 2 30-Aug-12 01-Sep-12 17-Jan-13 19-Jan-13 115
Second SSecond Stage Finishes 60 16-Oct-12 29-Dec-12 04-Feb-13 14-Apr-13 89
A70960 Installation of Equipments 60 16-Oct-12 29-Dec-12 04-Feb-13 14-Apr-13 89
Final StaFinal Stage Finishes 37 18-Nov-12 31-Dec-12 06-Mar-13 16-Apr-13 89
A70950 Installation of Doors 5 18-Nov-12 22-Nov-12 06-Mar-13 11-Mar-13 90
A70980 Doors Ironmongery 5 18-Nov-12 22-Nov-12 07-Mar-13 12-Mar-13 91
A70940 Final Coat Paint 2 30-Dec-12 31-Dec-12 15-Apr-13 16-Apr-13 89
MEP WorkMEP Works 29 02-Aug-12 06-Sep-12 22-Dec-12 14-Apr-13 182
HVACHVAC 7 02-Aug-12 09-Aug-12 29-Dec-12 13-Jan-13 127
A70990 Chilled Water Pipe Installation & Insulation 4 02-Aug-12 06-Aug-12 29-Dec-12 02-Jan-13 121
A71000 Condensate Pipe Installation 4 02-Aug-12 06-Aug-12 29-Dec-12 02-Jan-13 121
A71010 FCU Installation 3 07-Aug-12 09-Aug-12 10-Jan-13 13-Jan-13 127
ElectricalElectrical 17 02-Aug-12 23-Aug-12 22-Dec-12 05-Mar-13 160
A71020 Install Conduits in Wall 4 02-Aug-12 06-Aug-12 22-Dec-12 25-Dec-12 115
A71030 Wiring for Lighting & Power 4 13-Aug-12 16-Aug-12 25-Feb-13 28-Feb-13 160
A71040 Installation of Lighting Fittings 4 18-Aug-12 23-Aug-12 02-Mar-13 05-Mar-13 160
PlumbingPlumbing 7 02-Aug-12 09-Aug-12 23-Dec-12 31-Dec-12 117
A71080 Water Pipes in Wall 3 02-Aug-12 05-Aug-12 23-Dec-12 25-Dec-12 116
A71050 H/L Drainage Pipes Installation 4 02-Aug-12 06-Aug-12 24-Dec-12 27-Dec-12 117
A71060 H/L Hot&Cold Water Pipe Installation 4 02-Aug-12 06-Aug-12 24-Dec-12 27-Dec-12 117
A71070 Drainage&Water Pipes Testing 3 07-Aug-12 09-Aug-12 29-Dec-12 31-Dec-12 117
Fire FighFire Fighting 29 02-Aug-12 06-Sep-12 26-Dec-12 14-Apr-13 182
A71120 Fire Fighting Pipe 5 02-Aug-12 07-Aug-12 26-Dec-12 31-Dec-12 119
A71110 Hydro Static Test for Pipes 5 08-Aug-12 13-Aug-12 06-Feb-13 11-Feb-13 148
A71100 Sprinkler Fixing 5 30-Aug-12 04-Sep-12 12-Feb-13 17-Feb-13 136
A71160 Fire Alarm Devices 5 30-Aug-12 04-Sep-12 09-Apr-13 14-Apr-13 184
A71090 Installation of Fire Extingusher&Blanket 2 05-Sep-12 06-Sep-12 13-Apr-13 14-Apr-13 182
ToiletsToilets 100 02-Aug-12 03-Dec-12 15-Dec-12 16-Apr-13 113
FinishingFinishing Works 100 02-Aug-12 03-Dec-12 15-Dec-12 16-Apr-13 113
Wet WorWet Works 29 02-Aug-12 06-Sep-12 15-Dec-12 25-Feb-13 141
A72380 Block Works 7 02-Aug-12 09-Aug-12 15-Dec-12 22-Dec-12 109
A72320 Installation of Doors& Windows Sub-frame 2 15-Aug-12 16-Aug-12 24-Feb-13 25-Feb-13 157
A72310 Plaster Works 7 15-Aug-12 25-Aug-12 05-Jan-13 12-Jan-13 115
A72630 Wall Tiles Work 5 02-Sep-12 06-Sep-12 20-Jan-13 26-Jan-13 115
Fisrt StaFisrt Stage Finishes 17 08-Sep-12 26-Sep-12 27-Jan-13 03-Mar-13 129
A72620 Screed Works 2 08-Sep-12 09-Sep-12 27-Jan-13 28-Jan-13 115
A72340 Water Proofing for Wet Area 2 10-Sep-12 11-Sep-12 29-Jan-13 30-Jan-13 115
A72660 Installation of Suspended Ceiling Grid 4 12-Sep-12 16-Sep-12 31-Jan-13 04-Feb-13 115
A72650 Suspended Ceiling Tiles 5 17-Sep-12 22-Sep-12 05-Feb-13 10-Feb-13 115
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Hose Cabinet & Landing Valve
Block Works
Installation of Doors& Windows Sub-frame
Installation of Windows&Doors
Doors Ironmongery
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
Duct Installation & Insulation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Drainge Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Water Pipes in Wall
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Installation of GSM System
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Equipments
Installation of Doors
Doors Ironmongery
Final Coat Paint
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid
Suspended Ceiling Tiles
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 86 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A72640 Floor Tiles Work 4 23-Sep-12 26-Sep-12 27-Feb-13 03-Mar-13 129
Second SSecond Stage Finishes 4 14-Nov-12 19-Nov-12 04-Mar-13 01-Apr-13 111
A72350 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 04-Mar-13 05-Mar-13 90
A72390 Doors Ironmongery 2 14-Nov-12 17-Nov-12 05-Mar-13 06-Mar-13 91
A72360 Installation of Mirrors 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111
A72370 Installation of Vanity Counter 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111
A72600 Installation of Toliets Accessories 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111
Final StaFinal Stage Finishes 11 20-Nov-12 03-Dec-12 02-Apr-13 16-Apr-13 113
A72330 Final Coat Paint 2 20-Nov-12 21-Nov-12 02-Apr-13 03-Apr-13 111
A72610 Installation of Sinages 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113
MEP WorkMEP Works 55 11-Aug-12 15-Oct-12 30-Dec-12 03-Apr-13 140
HVACHVAC 55 11-Aug-12 15-Oct-12 03-Jan-13 05-Mar-13 115
A72400 Duct Installation & Insulation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118
A72410 Chilled Water Pipe Installation & Insulation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118
A72420 Condensate Pipe Installation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118
A72430 FCU Installation 2 15-Aug-12 16-Aug-12 14-Jan-13 15-Jan-13 123
A72440 Air-Outlet Installation 7 08-Oct-12 15-Oct-12 26-Feb-13 05-Mar-13 115
ElectricalElectrical 40 11-Aug-12 27-Sep-12 30-Dec-12 05-Mar-13 130
A72450 Install Conduits in Wall 4 11-Aug-12 14-Aug-12 30-Dec-12 03-Jan-13 115
A72460 Wiring for Lighting & Power 4 26-Aug-12 29-Aug-12 27-Jan-13 30-Jan-13 126
A72470 Installation of Lighting Fittings 5 23-Sep-12 27-Sep-12 28-Feb-13 05-Mar-13 130
PlumbingPlumbing 42 11-Aug-12 30-Sep-12 31-Dec-12 01-Apr-13 151
A72480 Drainge Pipes in Wall 3 11-Aug-12 13-Aug-12 31-Dec-12 03-Jan-13 116
A72550 Water Pipes in Wall 3 11-Aug-12 13-Aug-12 31-Dec-12 03-Jan-13 116
A72490 H/L Drainage Pipes Installation 4 11-Aug-12 14-Aug-12 22-Jan-13 27-Jan-13 134
A72500 H/L Hot&Cold Water Pipe Installation 4 11-Aug-12 14-Aug-12 22-Jan-13 27-Jan-13 134
A72520 ElectricalWater Heater Installation 2 15-Aug-12 16-Aug-12 29-Jan-13 30-Jan-13 135
A72510 Drainage&Water Pipes Testing 3 15-Aug-12 18-Aug-12 28-Jan-13 30-Jan-13 134
A72530 Floor Drain Fixning 2 10-Sep-12 11-Sep-12 26-Feb-13 27-Feb-13 139
A72540 Installation of Sanitaryware 3 27-Sep-12 30-Sep-12 30-Mar-13 01-Apr-13 151
Fire FighFire Fighting 44 11-Aug-12 02-Oct-12 02-Jan-13 03-Apr-13 151
A72590 Fire Fighting Pipe 3 11-Aug-12 13-Aug-12 02-Jan-13 05-Jan-13 117
A72580 Hydro Static Test for Pipes 3 14-Aug-12 16-Aug-12 28-Jan-13 30-Jan-13 135
A72670 Fire Alarm Devices 4 23-Sep-12 26-Sep-12 28-Mar-13 01-Apr-13 154
A72570 Sprinkler Fixing 3 27-Sep-12 30-Sep-12 21-Feb-13 24-Feb-13 120
A72560 Installation of Fire Extingusher&Blanket 2 01-Oct-12 02-Oct-12 02-Apr-13 03-Apr-13 151
StaircaseStaircase 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153
Stairs 1Stairs 1 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153
A111570 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153
A111610 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
A111580 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111590 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111600 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153
A111620 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153
Stairs 2Stairs 2 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153
A111630 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153
A111670 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
A111640 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111650 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111660 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153
A111680 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153
Stairs 3Stairs 3 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153
A111690 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153
A111730 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
A111700 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111710 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A111720 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153
A111740 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153
Stairs 4Stairs 4 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153
A112110 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153
A112150 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153
A112120 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A112130 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153
A112140 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153
A112160 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153
1st Floor1st Floor 187 15-Aug-12 30-Mar-13 29-Aug-12 16-Apr-13 15
Public AreaPublic Area 187 15-Aug-12 30-Mar-13 28-Nov-12 16-Apr-13 15
Garbage RGarbage Room 137 06-Oct-12 20-Mar-13 15-Jan-13 16-Apr-13 23
FinishingFinishing Works 137 06-Oct-12 20-Mar-13 15-Jan-13 16-Apr-13 23
Wet WorWet Works 65 06-Oct-12 24-Dec-12 15-Jan-13 07-Apr-13 87
A72740 Block Works 3 06-Oct-12 08-Oct-12 15-Jan-13 17-Jan-13 82
A72680 Plaster Works 3 17-Nov-12 19-Nov-12 23-Jan-13 27-Jan-13 56
A72690 Installation of Doors& Windows Sub-frame 1 21-Nov-12 21-Nov-12 07-Apr-13 07-Apr-13 114
A72720 Wall Tiles Work 4 22-Nov-12 26-Nov-12 30-Jan-13 03-Feb-13 56
A72700 1st Coat Paint 2 23-Dec-12 24-Dec-12 04-Feb-13 05-Feb-13 35
Fisrt StaFisrt Stage Finishes 25 17-Jan-13 16-Feb-13 12-Feb-13 15-Apr-13 50
A72870 Screed Works 2 17-Jan-13 19-Jan-13 12-Feb-13 13-Feb-13 21
A72890 Floor Tiles Work 2 21-Jan-13 22-Jan-13 16-Feb-13 17-Feb-13 21
A72750 Doors Ironmongery 1 14-Feb-13 14-Feb-13 15-Apr-13 15-Apr-13 51
A72730 Installation of Doors 2 14-Feb-13 16-Feb-13 08-Apr-13 09-Apr-13 45
Second SSecond Stage Finishes 2 18-Mar-13 19-Mar-13 04-Apr-13 06-Apr-13 15
A72710 Final Coat Paint 2 18-Mar-13 19-Mar-13 04-Apr-13 06-Apr-13 15
Final StaFinal Stage Finishes 1 20-Mar-13 20-Mar-13 16-Apr-13 16-Apr-13 23
A72860 Installation of Sinages 1 20-Mar-13 20-Mar-13 16-Apr-13 16-Apr-13 23
MEP WorkMEP Works 88 09-Oct-12 26-Jan-13 19-Jan-13 05-Mar-13 33
ElectricalElectrical 88 09-Oct-12 26-Jan-13 21-Jan-13 05-Mar-13 33
A72760 Install Conduits in Wall 2 09-Oct-12 10-Oct-12 21-Jan-13 22-Jan-13 84
A72770 Wiring for Lighting & Power 2 20-Nov-12 21-Nov-12 28-Jan-13 29-Jan-13 56
A72780 Installation of Lighting Fittings 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33
PlumbingPlumbing 84 09-Oct-12 20-Jan-13 19-Jan-13 14-Feb-13 21
A72790 Drainge Pipes in Wall 2 09-Oct-12 10-Oct-12 19-Jan-13 20-Jan-13 82
A72820 Water Pipes in Wall 2 09-Oct-12 10-Oct-12 19-Jan-13 20-Jan-13 82
A72800 Drainage&Water Pipes Testing 2 11-Oct-12 13-Oct-12 21-Jan-13 22-Jan-13 82
A72810 Floor Drain Fixning 1 20-Jan-13 20-Jan-13 14-Feb-13 14-Feb-13 21
Fire FighFire Fighting 87 10-Oct-12 26-Jan-13 13-Feb-13 27-Feb-13 28
A72850 Fire Fighting Pipe 2 10-Oct-12 11-Oct-12 13-Feb-13 14-Feb-13 102
A72840 Hydro Static Test for Pipes 2 13-Oct-12 14-Oct-12 16-Feb-13 17-Feb-13 102
A72830 Sprinkler Fixing 2 23-Jan-13 26-Jan-13 18-Feb-13 19-Feb-13 21
A72880 Fire Alarm Devices 2 23-Jan-13 26-Jan-13 26-Feb-13 27-Feb-13 28
Corridor &Corridor & Lift Lobby 153 26-Sep-12 30-Mar-13 20-Dec-12 16-Apr-13 15
FinishingFinishing Works 153 26-Sep-12 30-Mar-13 20-Dec-12 16-Apr-13 15
Wet WorWet Works 79 26-Sep-12 31-Dec-12 20-Dec-12 04-Feb-13 28
A72960 Block Works 8 26-Sep-12 04-Oct-12 20-Dec-12 29-Dec-12 69
A72900 Plaster Works 7 07-Nov-12 14-Nov-12 02-Jan-13 09-Jan-13 45
A72920 Installation of Suspended Ceiling Grid 6 22-Nov-12 28-Nov-12 15-Jan-13 21-Jan-13 44
A72910 1st Coat Paint 5 17-Dec-12 22-Dec-12 22-Jan-13 28-Jan-13 30
A72930 Suspended Ceiling Tiles 6 25-Dec-12 31-Dec-12 29-Jan-13 04-Feb-13 28
Fisrt StaFisrt Stage Finishes 61 14-Jan-13 26-Mar-13 09-Feb-13 13-Apr-13 15
A73190 Screed Works 3 14-Jan-13 16-Jan-13 09-Feb-13 11-Feb-13 21
A73200 Floor Tiles Work 5 20-Mar-13 25-Mar-13 07-Apr-13 11-Apr-13 15
A72940 Installation of Doors 3 24-Mar-13 26-Mar-13 10-Apr-13 13-Apr-13 15
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Floor Tiles Work
Installation of Windows&Doors
Doors Ironmongery
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
ElectricalWater Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Doors
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 87 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A72970 Doors Ironmongery 3 24-Mar-13 26-Mar-13 10-Apr-13 13-Apr-13 15
Second SSecond Stage Finishes 5 25-Mar-13 30-Mar-13 11-Apr-13 16-Apr-13 15
A73210 Final Coat Paint 5 25-Mar-13 30-Mar-13 11-Apr-13 16-Apr-13 15
Final StaFinal Stage Finishes 3 27-Mar-13 30-Mar-13 14-Apr-13 16-Apr-13 15
A73180 Installation of Sinages 3 27-Mar-13 30-Mar-13 14-Apr-13 16-Apr-13 15
MEP WorkMEP Works 80 06-Oct-12 12-Jan-13 30-Dec-12 10-Apr-13 75
HVACHVAC 74 06-Oct-12 05-Jan-13 06-Jan-13 19-Feb-13 38
A73000 Condensate Pipe Installation 5 06-Oct-12 10-Oct-12 06-Jan-13 10-Jan-13 74
A72980 Duct Installation & Insulation 5 29-Oct-12 03-Nov-12 06-Jan-13 10-Jan-13 56
A72990 Chilled Water Pipe Installation & Insulation 5 29-Oct-12 03-Nov-12 06-Jan-13 10-Jan-13 56
A73010 FCU Installation 3 04-Nov-12 06-Nov-12 12-Jan-13 14-Jan-13 56
A73020 Air-Outlet Installation 3 02-Jan-13 05-Jan-13 17-Feb-13 19-Feb-13 38
ElectricalElectrical 76 06-Oct-12 07-Jan-13 30-Dec-12 05-Mar-13 48
A73030 Install Conduits in Wall 2 06-Oct-12 07-Oct-12 30-Dec-12 31-Dec-12 69
A73040 Install Cable Trays & Trunking 2 06-Oct-12 07-Oct-12 06-Jan-13 07-Jan-13 74
A73080 Cable Laying for Low Current System 2 08-Oct-12 09-Oct-12 20-Jan-13 21-Jan-13 84
A73090 Cable Laying for Power 3 08-Oct-12 10-Oct-12 19-Jan-13 21-Jan-13 83
A73050 Wiring for Lighting & Power 3 17-Nov-12 19-Nov-12 12-Jan-13 14-Jan-13 46
A73060 Wiring for Low Current System 4 17-Nov-12 20-Nov-12 10-Jan-13 14-Jan-13 45
A73070 DB installation,Dressing & Termination 7 29-Nov-12 08-Dec-12 28-Jan-13 04-Feb-13 48
A73120 Installation of Sockets 3 02-Jan-13 05-Jan-13 03-Mar-13 05-Mar-13 50
A73110 Installation of Lighting Fittings 5 02-Jan-13 07-Jan-13 28-Feb-13 05-Mar-13 48
PlumbingPlumbing 5 06-Oct-12 10-Oct-12 09-Jan-13 14-Jan-13 77
A73130 H/L Hot&Cold Water Pipe Installation 5 06-Oct-12 10-Oct-12 09-Jan-13 14-Jan-13 77
Fire FighFire Fighting 80 06-Oct-12 12-Jan-13 06-Jan-13 10-Apr-13 75
A73170 Fire Fighting Pipe 4 06-Oct-12 09-Oct-12 06-Jan-13 09-Jan-13 74
A73160 Hydro Static Test for Pipes 4 10-Oct-12 14-Oct-12 10-Jan-13 14-Jan-13 74
A73220 Fire Alarm Devices 4 02-Jan-13 06-Jan-13 19-Feb-13 23-Feb-13 40
A73150 Sprinkler Fixing 5 02-Jan-13 07-Jan-13 12-Feb-13 17-Feb-13 34
A73140 Installation of Fire Extingusher&Blanket 4 08-Jan-13 12-Jan-13 07-Apr-13 10-Apr-13 75
Electrical /Electrical /Meter/ Telephone Rooms 106 09-Oct-12 16-Feb-13 23-Jan-13 16-Apr-13 51
FinishingFinishing Works 106 09-Oct-12 16-Feb-13 23-Jan-13 16-Apr-13 51
Wet WorWet Works 65 09-Oct-12 27-Dec-12 23-Jan-13 04-Apr-13 82
A73280 Block Works 3 09-Oct-12 11-Oct-12 23-Jan-13 27-Jan-13 86
A73240 Installation of Doors& Windows Sub-frame 1 20-Nov-12 20-Nov-12 04-Apr-13 04-Apr-13 113
A73230 Plaster Works 4 20-Nov-12 24-Nov-12 30-Jan-13 03-Feb-13 58
A73250 1st Coat Paint 3 25-Dec-12 27-Dec-12 06-Feb-13 09-Feb-13 35
Fisrt StaFisrt Stage Finishes 18 23-Jan-13 13-Feb-13 02-Apr-13 14-Apr-13 51
A73340 Epoxy Paint Works 2 23-Jan-13 26-Jan-13 02-Apr-13 03-Apr-13 58
A73270 Installation of Doors 2 12-Feb-13 13-Feb-13 06-Apr-13 07-Apr-13 45
A73290 Doors Ironmongery 2 12-Feb-13 13-Feb-13 13-Apr-13 14-Apr-13 51
Second SSecond Stage Finishes 2 27-Jan-13 28-Jan-13 04-Apr-13 06-Apr-13 58
A73260 Final Coat Paint 2 27-Jan-13 28-Jan-13 04-Apr-13 06-Apr-13 58
Final StaFinal Stage Finishes 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51
A73330 Installation of Sinages 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51
MEP WorkMEP Works 83 13-Oct-12 22-Jan-13 28-Jan-13 05-Mar-13 35
HVACHVAC 2 06-Jan-13 07-Jan-13 20-Feb-13 21-Feb-13 38
A73370 Air-Outlet Installation 2 06-Jan-13 07-Jan-13 20-Feb-13 21-Feb-13 38
ElectricalElectrical 83 13-Oct-12 22-Jan-13 28-Jan-13 05-Mar-13 35
A73300 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 28-Jan-13 29-Jan-13 86
A73310 Wiring for Lighting & Power 2 25-Nov-12 26-Nov-12 04-Feb-13 05-Feb-13 58
A73360 Installation of SMDBs 7 29-Dec-12 06-Jan-13 13-Feb-13 20-Feb-13 38
A73320 Installation of Lighting Fittings 2 07-Jan-13 08-Jan-13 21-Feb-13 23-Feb-13 38
A114980 Installation of Telephone System 21 29-Dec-12 22-Jan-13 10-Feb-13 05-Mar-13 35
Fire FighFire Fighting 2 09-Jan-13 10-Jan-13 24-Feb-13 25-Feb-13 38
A73350 Fire Alarm Devices 2 09-Jan-13 10-Jan-13 24-Feb-13 25-Feb-13 38
PlantersPlanters 150 15-Aug-12 14-Feb-13 28-Nov-12 16-Apr-13 52
FinishingFinishing Works 150 15-Aug-12 14-Feb-13 28-Nov-12 16-Apr-13 52
A105040 Water Proof Membrane 12 15-Aug-12 30-Aug-12 28-Nov-12 12-Dec-12 85
A105050 Drainage Gravel 12 20-Oct-12 04-Nov-12 13-Dec-12 26-Dec-12 43
A105060 Geptextile Membrane 12 05-Nov-12 19-Nov-12 27-Dec-12 10-Jan-13 43
A105070 Sweet Soil 12 20-Nov-12 04-Dec-12 12-Jan-13 26-Jan-13 43
A107900 Installation of Lighitngs 30 05-Dec-12 09-Jan-13 13-Mar-13 16-Apr-13 82
A105080 Instllation of Planting Items 50 05-Dec-12 03-Feb-13 27-Jan-13 25-Mar-13 43
A107890 Installation of Irrigation System 60 05-Dec-12 14-Feb-13 27-Jan-13 06-Apr-13 43
StaircaseStaircase 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133
Stairs 1Stairs 1 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133
A111750 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133
A111790 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133
A111760 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111770 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111780 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133
A111800 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133
Stairs 2Stairs 2 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133
A111810 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133
A111850 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133
A111820 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111830 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111840 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133
A111860 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133
Stairs 3Stairs 3 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133
A111870 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133
A111910 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133
A111880 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111890 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133
A111900 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133
A111920 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133
ApartementsApartements 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26
One BedroOne Bedroom Flats 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31
ApartemeApartement .1 - 5 (1 BR) 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31
FinishingFinishing Works 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31
Wet WoWet Works 76 15-Sep-12 16-Dec-12 04-Nov-12 27-Feb-13 61
A73530 Block Works 10 15-Sep-12 25-Sep-12 04-Nov-12 14-Nov-12 41
A73390 Installation of Doors& Windows Sub-frame 2 24-Oct-12 28-Oct-12 26-Feb-13 27-Feb-13 101
A73380 Plaster Works 10 24-Oct-12 06-Nov-12 26-Nov-12 08-Dec-12 25
A73860 Wall Tiles Work (Wet Area) 6 08-Nov-12 14-Nov-12 10-Jan-13 16-Jan-13 51
A73410 Installation of Suspended Ceiling Grid (Dry Area) 5 17-Nov-12 21-Nov-12 15-Dec-12 19-Dec-12 23
A73400 1st Coat Paint 11 04-Dec-12 16-Dec-12 20-Dec-12 02-Jan-13 14
Fisrt StaFisrt Stage Finishes 42 19-Dec-12 07-Feb-13 06-Jan-13 27-Feb-13 17
A73420 Suspended Ceiling Tiles (DryArea) 5 19-Dec-12 24-Dec-12 06-Jan-13 10-Jan-13 14
A73460 Installation of Wardrobes 5 26-Dec-12 31-Dec-12 12-Jan-13 16-Jan-13 13
A73850 Screed Works 7 06-Jan-13 13-Jan-13 17-Jan-13 26-Jan-13 10
A73450 Water Proofing for Wet Area 4 14-Jan-13 17-Jan-13 27-Jan-13 30-Jan-13 10
A73890 Installation of Suspended Ceiling Grid (Wet Area) 4 19-Jan-13 22-Jan-13 31-Jan-13 04-Feb-13 10
A73880 Suspended Ceiling Tiles (Wet Area) 5 23-Jan-13 29-Jan-13 05-Feb-13 10-Feb-13 10
A73440 Floor & Wall Tiles Work (Dry Area) 11 17-Jan-13 30-Jan-13 07-Feb-13 19-Feb-13 17
A73870 Floor Tiles Work (Wet Area) 7 31-Jan-13 07-Feb-13 20-Feb-13 27-Feb-13 17
SecondSecond Stage Finishes 18 09-Feb-13 28-Feb-13 28-Feb-13 28-Mar-13 24
A73470 Installation of Windows&Doors 3 09-Feb-13 11-Feb-13 28-Feb-13 03-Mar-13 17
A73540 Doors Ironmongery 3 09-Feb-13 11-Feb-13 26-Mar-13 28-Mar-13 39
A73510 Installation of Balustrades& Handrails 2 12-Feb-13 13-Feb-13 27-Mar-13 28-Mar-13 37
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Fire Alarm Devices
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Epoxy Paint Works
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Water Proof Membrane
Drainage Gravel
Geptextile Membrane
Sweet Soil
Installation of Lighitngs
Instllation of Planting Items
Installation of Irrigation System
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 88 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A73480 Installation of Mirrors 4 12-Feb-13 16-Feb-13 07-Mar-13 11-Mar-13 20
A73520 Installation of Vanity Counter 4 12-Feb-13 16-Feb-13 07-Mar-13 11-Mar-13 20
A73830 Installation of Toliets Accessories 5 12-Feb-13 17-Feb-13 04-Mar-13 09-Mar-13 17
A73490 Installation of Kitchen Cabinets 4 25-Feb-13 28-Feb-13 25-Mar-13 28-Mar-13 24
Final StFinal Stage Finishes 9 02-Mar-13 11-Mar-13 30-Mar-13 16-Apr-13 31
A73430 Final Coat Paint 7 02-Mar-13 09-Mar-13 30-Mar-13 06-Apr-13 24
A73840 Installation of Sinages 2 10-Mar-13 11-Mar-13 15-Apr-13 16-Apr-13 31
MEP WoMEP Works 116 26-Sep-12 14-Feb-13 17-Nov-12 06-Apr-13 43
HVACHVAC 105 26-Sep-12 02-Feb-13 24-Nov-12 25-Feb-13 20
A73580 Condensate Pipe Installation 12 26-Sep-12 09-Oct-12 24-Nov-12 08-Dec-12 47
A73560 Duct Installation & Insulation 12 13-Oct-12 28-Oct-12 24-Nov-12 08-Dec-12 33
A73570 Chilled Water Pipe Installation & Insulation 12 13-Oct-12 28-Oct-12 24-Nov-12 08-Dec-12 33
A73590 FCU Installation 5 29-Oct-12 03-Nov-12 09-Dec-12 13-Dec-12 33
A73600 Air-Outlet Installation 3 30-Jan-13 02-Feb-13 23-Feb-13 25-Feb-13 20
ElectricElectrical 106 26-Sep-12 03-Feb-13 17-Nov-12 05-Mar-13 26
A73610 Install Conduits in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41
A73620 Install Cable Trays & Trunking 8 26-Sep-12 04-Oct-12 26-Nov-12 05-Dec-12 49
A73660 Cable Laying for Low Current System 8 06-Oct-12 14-Oct-12 11-Dec-12 19-Dec-12 53
A73670 Cable Laying for Power 8 06-Oct-12 14-Oct-12 11-Dec-12 19-Dec-12 53
A73630 Wiring for Lighting & Power 5 07-Nov-12 12-Nov-12 09-Dec-12 13-Dec-12 25
A73640 Wiring for Low Current System 5 07-Nov-12 12-Nov-12 09-Dec-12 13-Dec-12 25
A73650 DB installation,Dressing & Termination 7 17-Dec-12 24-Dec-12 03-Jan-13 10-Jan-13 14
A73700 Installation of Sockets 3 30-Jan-13 02-Feb-13 03-Mar-13 05-Mar-13 27
A73690 Installation of Lighting Fittings 4 30-Jan-13 03-Feb-13 02-Mar-13 05-Mar-13 26
PlumbinPlumbing 116 26-Sep-12 14-Feb-13 17-Nov-12 28-Mar-13 36
A73710 Drainge Pipes in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41
A73780 Water Pipes in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41
A73720 H/L Drainage Pipes Installation 12 26-Sep-12 09-Oct-12 12-Jan-13 26-Jan-13 87
A73730 H/L Hot&Cold Water Pipe Installation 12 26-Sep-12 09-Oct-12 12-Jan-13 26-Jan-13 87
A73740 Drainage&Water Pipes Testing 3 10-Oct-12 13-Oct-12 27-Jan-13 29-Jan-13 87
A73750 ElectricalWater Heater Installation 4 10-Oct-12 14-Oct-12 27-Jan-13 30-Jan-13 87
A73760 Floor Drain Fixning 2 08-Jan-13 09-Jan-13 23-Feb-13 24-Feb-13 38
A73770 Installation of Sanitaryware 3 12-Feb-13 14-Feb-13 26-Mar-13 28-Mar-13 36
Fire FigFire Fighting 108 27-Sep-12 06-Feb-13 29-Nov-12 06-Apr-13 50
A73820 Fire Fighting Pipe 7 27-Sep-12 04-Oct-12 29-Nov-12 08-Dec-12 51
A73810 Hydro Static Test for Pipes 5 06-Oct-12 10-Oct-12 09-Dec-12 13-Dec-12 51
A73800 Sprinkler Fixing 5 30-Jan-13 04-Feb-13 20-Feb-13 25-Feb-13 18
A73900 Fire Alarm Devices 5 30-Jan-13 04-Feb-13 28-Feb-13 05-Mar-13 25
A73790 Installation of Fire Extingusher&Blanket 2 05-Feb-13 06-Feb-13 04-Apr-13 06-Apr-13 50
Two BedroTwo Bedroom Flats 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34
ApartemeApartement .1 -11 (2 BR) 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34
FinishingFinishing Works 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34
Wet WoWet Works 77 01-Sep-12 03-Dec-12 19-Sep-12 25-Feb-13 70
A74060 Block Works 12 01-Sep-12 13-Sep-12 19-Sep-12 02-Oct-12 16
A73920 Installation of Doors& Windows Sub-frame 6 04-Oct-12 10-Oct-12 19-Feb-13 25-Feb-13 112
A73910 Plaster Works 17 04-Oct-12 23-Oct-12 17-Oct-12 07-Nov-12 11
A74390 Wall Tiles Work (Wet Area) 11 24-Oct-12 07-Nov-12 25-Dec-12 07-Jan-13 49
A73940 Installation of Suspended Ceiling Grid (Dry Area) 7 07-Nov-12 14-Nov-12 21-Nov-12 28-Nov-12 11
A73930 1st Coat Paint 13 18-Nov-12 03-Dec-12 29-Nov-12 15-Dec-12 10
Fisrt StaFisrt Stage Finishes 54 06-Dec-12 09-Feb-13 18-Dec-12 26-Feb-13 15
A73950 Suspended Ceiling Tiles (DryArea) 10 06-Dec-12 17-Dec-12 18-Dec-12 29-Dec-12 10
A73990 Installation of Wardrobes 7 18-Dec-12 25-Dec-12 30-Dec-12 07-Jan-13 10
A74380 Screed Works 8 26-Dec-12 05-Jan-13 08-Jan-13 16-Jan-13 10
A73980 Water Proofing for Wet Area 8 06-Jan-13 14-Jan-13 29-Jan-13 06-Feb-13 19
A73970 Floor & Wall Tiles Work (Dry Area) 10 06-Jan-13 16-Jan-13 27-Jan-13 06-Feb-13 17
A74420 Installation of Suspended Ceiling Grid (Wet Area) 6 23-Jan-13 30-Jan-13 07-Feb-13 13-Feb-13 12
A74410 Suspended Ceiling Tiles (Wet Area) 5 30-Jan-13 04-Feb-13 11-Feb-13 16-Feb-13 10
A74400 Floor Tiles Work (Wet Area) 4 05-Feb-13 09-Feb-13 23-Feb-13 26-Feb-13 15
SecondSecond Stage Finishes 17 10-Feb-13 28-Feb-13 27-Feb-13 20-Mar-13 17
A74000 Installation of Windows&Doors 5 10-Feb-13 14-Feb-13 27-Feb-13 04-Mar-13 15
A74070 Doors Ironmongery 5 10-Feb-13 14-Feb-13 11-Mar-13 16-Mar-13 25
A74040 Installation of Balustrades& Handrails 5 16-Feb-13 20-Feb-13 11-Mar-13 16-Mar-13 20
A74020 Installation of Kitchen Cabinets 8 16-Feb-13 24-Feb-13 07-Mar-13 16-Mar-13 17
A74010 Installation of Mirrors 8 17-Feb-13 25-Feb-13 12-Mar-13 20-Mar-13 20
A74050 Installation of Vanity Counter 8 17-Feb-13 25-Feb-13 12-Mar-13 20-Mar-13 20
A74360 Installation of Toliets Accessories 10 18-Feb-13 28-Feb-13 10-Mar-13 20-Mar-13 17
Final StFinal Stage Finishes 8 27-Feb-13 07-Mar-13 17-Mar-13 16-Apr-13 34
A73960 Final Coat Paint 8 27-Feb-13 07-Mar-13 17-Mar-13 25-Mar-13 15
A74370 Installation of Sinages 2 06-Mar-13 07-Mar-13 15-Apr-13 16-Apr-13 34
MEP WoMEP Works 136 15-Sep-12 26-Feb-13 03-Oct-12 25-Mar-13 23
HVACHVAC 124 15-Sep-12 12-Feb-13 16-Oct-12 05-Mar-13 18
A74110 Condensate Pipe Installation 18 15-Sep-12 04-Oct-12 16-Oct-12 07-Nov-12 27
A74090 Duct Installation & Insulation 18 22-Sep-12 11-Oct-12 16-Oct-12 07-Nov-12 21
A74100 Chilled Water Pipe Installation & Insulation 18 22-Sep-12 11-Oct-12 16-Oct-12 07-Nov-12 21
A74120 FCU Installation 10 13-Oct-12 23-Oct-12 08-Nov-12 20-Nov-12 21
A74130 Air-Outlet Installation 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18
ElectricElectrical 132 15-Sep-12 21-Feb-13 03-Oct-12 05-Mar-13 10
A74140 Install Conduits in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16
A74150 Install Cable Trays & Trunking 12 15-Sep-12 27-Sep-12 21-Oct-12 05-Nov-12 31
A74190 Cable Laying for Low Current System 15 29-Sep-12 15-Oct-12 11-Nov-12 28-Nov-12 35
A74200 Cable Laying for Power 15 29-Sep-12 15-Oct-12 11-Nov-12 28-Nov-12 35
A74160 Wiring for Lighting & Power 10 24-Oct-12 06-Nov-12 08-Nov-12 20-Nov-12 11
A74170 Wiring for Low Current System 10 24-Oct-12 06-Nov-12 08-Nov-12 20-Nov-12 11
A74180 DB installation,Dressing & Termination 12 04-Dec-12 17-Dec-12 16-Dec-12 29-Dec-12 10
A74230 Installation of Sockets 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18
A74220 Installation of Lighting Fittings 15 05-Feb-13 21-Feb-13 17-Feb-13 05-Mar-13 10
PlumbinPlumbing 136 15-Sep-12 26-Feb-13 03-Oct-12 16-Mar-13 15
A74250 H/L Drainage Pipes Installation 11 15-Sep-12 26-Sep-12 05-Jan-13 16-Jan-13 91
A74260 H/L Hot&Cold Water Pipe Installation 11 15-Sep-12 26-Sep-12 05-Jan-13 16-Jan-13 91
A74240 Drainge Pipes in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16
A74310 Water Pipes in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16
A74270 Drainage&Water Pipes Testing 7 27-Sep-12 04-Oct-12 17-Jan-13 26-Jan-13 91
A74280 ElectricalWater Heater Installation 7 27-Sep-12 04-Oct-12 17-Jan-13 26-Jan-13 91
A74290 Floor Drain Fixning 4 29-Dec-12 02-Jan-13 19-Feb-13 23-Feb-13 43
A74300 Installation of Sanitaryware 10 16-Feb-13 26-Feb-13 05-Mar-13 16-Mar-13 15
Fire FigFire Fighting 126 15-Sep-12 14-Feb-13 30-Oct-12 25-Mar-13 33
A74350 Fire Fighting Pipe 11 15-Sep-12 26-Sep-12 30-Oct-12 11-Nov-12 37
A74340 Hydro Static Test for Pipes 7 27-Sep-12 04-Oct-12 12-Nov-12 20-Nov-12 37
A74330 Sprinkler Fixing 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18
A74430 Fire Alarm Devices 7 05-Feb-13 12-Feb-13 06-Mar-13 13-Mar-13 25
A74320 Installation of Fire Extingusher&Blanket 2 13-Feb-13 14-Feb-13 24-Mar-13 25-Mar-13 33
Three BedrThree Bedroom Flats 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26
ApartemeApartement .1 -3 (3 BR) 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26
FinishingFinishing Works 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26
Wet WoWet Works 76 15-Aug-12 17-Nov-12 29-Aug-12 18-Feb-13 77
A74590 Block Works 12 15-Aug-12 30-Aug-12 29-Aug-12 11-Sep-12 10
A74450 Installation of Doors& Windows Sub-frame 6 15-Sep-12 20-Sep-12 12-Feb-13 18-Feb-13 123
A74440 Plaster Works 17 15-Sep-12 03-Oct-12 26-Sep-12 15-Oct-12 10
A74920 Wall Tiles Work (Wet Area) 11 04-Oct-12 16-Oct-12 12-Dec-12 24-Dec-12 55
A74470 Installation of Suspended Ceiling Grid (Dry Area) 7 18-Oct-12 28-Oct-12 01-Nov-12 08-Nov-12 10
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Installation of Kitchen Cabinets
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
ElectricalWater Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Kitchen Cabinets
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Condensate Pipe Installation
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 89 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A74460 1st Coat Paint 16 29-Oct-12 17-Nov-12 10-Nov-12 28-Nov-12 10
Fisrt StaFisrt Stage Finishes 45 18-Nov-12 10-Jan-13 06-Dec-12 19-Feb-13 33
A74480 Suspended Ceiling Tiles (DryArea) 10 18-Nov-12 28-Nov-12 06-Dec-12 17-Dec-12 15
A74520 Installation of Wardrobes 7 29-Nov-12 08-Dec-12 20-Dec-12 27-Dec-12 17
A74910 Screed Works 8 09-Dec-12 17-Dec-12 29-Dec-12 07-Jan-13 17
A74510 Water Proofing for Wet Area 8 18-Dec-12 26-Dec-12 28-Jan-13 05-Feb-13 33
A74500 Floor & Wall Tiles Work (Dry Area) 10 18-Dec-12 29-Dec-12 14-Jan-13 26-Jan-13 22
A74950 Installation of Suspended Ceiling Grid (Wet Area) 6 27-Dec-12 03-Jan-13 06-Feb-13 12-Feb-13 33
A74940 Suspended Ceiling Tiles (Wet Area) 5 31-Dec-12 06-Jan-13 10-Feb-13 14-Feb-13 33
A74930 Floor Tiles Work (Wet Area) 4 07-Jan-13 10-Jan-13 16-Feb-13 19-Feb-13 33
SecondSecond Stage Finishes 51 12-Jan-13 12-Mar-13 20-Feb-13 01-Apr-13 17
A74530 Installation of Windows&Doors 5 12-Jan-13 16-Jan-13 20-Feb-13 25-Feb-13 33
A74600 Doors Ironmongery 5 12-Jan-13 16-Jan-13 20-Mar-13 25-Mar-13 57
A74570 Installation of Balustrades& Handrails 5 17-Jan-13 22-Jan-13 20-Mar-13 25-Mar-13 52
A74550 Installation of Kitchen Cabinets 8 17-Jan-13 27-Jan-13 26-Feb-13 06-Mar-13 33
A74540 Installation of Mirrors 8 26-Feb-13 06-Mar-13 21-Mar-13 30-Mar-13 20
A74580 Installation of Vanity Counter 8 26-Feb-13 06-Mar-13 21-Mar-13 30-Mar-13 20
A74890 Installation of Toliets Accessories 10 02-Mar-13 12-Mar-13 21-Mar-13 01-Apr-13 17
Final StFinal Stage Finishes 8 09-Mar-13 17-Mar-13 26-Mar-13 16-Apr-13 26
A74490 Final Coat Paint 8 09-Mar-13 17-Mar-13 26-Mar-13 03-Apr-13 15
A74900 Installation of Sinages 3 14-Mar-13 17-Mar-13 14-Apr-13 16-Apr-13 26
MEP WoMEP Works 152 25-Aug-12 24-Feb-13 12-Sep-12 03-Apr-13 33
HVACHVAC 115 01-Sep-12 17-Jan-13 24-Sep-12 05-Mar-13 39
A74620 Duct Installation & Insulation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20
A74630 Chilled Water Pipe Installation & Insulation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20
A74640 Condensate Pipe Installation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20
A74650 FCU Installation 13 22-Sep-12 06-Oct-12 15-Oct-12 31-Oct-12 20
A74660 Air-Outlet Installation 10 07-Jan-13 17-Jan-13 23-Feb-13 05-Mar-13 39
ElectricElectrical 123 25-Aug-12 20-Jan-13 12-Sep-12 05-Mar-13 37
A74670 Install Conduits in Wall 12 25-Aug-12 06-Sep-12 12-Sep-12 25-Sep-12 16
A74680 Install Cable Trays & Trunking 12 01-Sep-12 13-Sep-12 30-Sep-12 13-Oct-12 25
A74720 Cable Laying for Low Current System 15 15-Sep-12 01-Oct-12 21-Oct-12 08-Nov-12 31
A74730 Cable Laying for Power 15 15-Sep-12 01-Oct-12 21-Oct-12 08-Nov-12 31
A74690 Wiring for Lighting & Power 12 04-Oct-12 17-Oct-12 16-Oct-12 31-Oct-12 10
A74700 Wiring for Low Current System 12 04-Oct-12 17-Oct-12 16-Oct-12 31-Oct-12 10
A74710 DB installation,Dressing & Termination 10 18-Nov-12 28-Nov-12 06-Dec-12 17-Dec-12 15
A74760 Installation of Sockets 7 07-Jan-13 14-Jan-13 26-Feb-13 05-Mar-13 42
A74750 Installation of Lighting Fittings 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37
PlumbinPlumbing 126 01-Sep-12 31-Jan-13 12-Sep-12 25-Mar-13 45
A74780 H/L Drainage Pipes Installation 11 01-Sep-12 12-Sep-12 23-Dec-12 05-Jan-13 93
A74790 H/L Hot&Cold Water Pipe Installation 11 01-Sep-12 12-Sep-12 23-Dec-12 05-Jan-13 93
A74770 Drainge Pipes in Wall 12 01-Sep-12 13-Sep-12 12-Sep-12 25-Sep-12 10
A74840 Water Pipes in Wall 12 01-Sep-12 13-Sep-12 12-Sep-12 25-Sep-12 10
A74800 Drainage&Water Pipes Testing 7 13-Sep-12 20-Sep-12 06-Jan-13 13-Jan-13 93
A74810 ElectricalWater Heater Installation 10 13-Sep-12 24-Sep-12 06-Jan-13 16-Jan-13 93
A74820 Floor Drain Fixning 8 11-Dec-12 19-Dec-12 07-Feb-13 16-Feb-13 48
A74830 Installation of Sanitaryware 12 17-Jan-13 31-Jan-13 12-Mar-13 25-Mar-13 45
Fire FigFire Fighting 146 01-Sep-12 24-Feb-13 09-Oct-12 03-Apr-13 33
A74880 Fire Fighting Pipe 11 01-Sep-12 12-Sep-12 09-Oct-12 21-Oct-12 33
A74870 Hydro Static Test for Pipes 7 13-Sep-12 20-Sep-12 22-Oct-12 31-Oct-12 33
A74860 Sprinkler Fixing 10 07-Jan-13 17-Jan-13 23-Feb-13 05-Mar-13 39
A74850 Installation of Fire Extingusher&Blanket 2 19-Jan-13 20-Jan-13 02-Apr-13 03-Apr-13 62
A74960 Fire Alarm Devices 10 13-Feb-13 24-Feb-13 14-Mar-13 25-Mar-13 25
2nd Floor2nd Floor 174 30-Aug-12 27-Mar-13 12-Sep-12 16-Apr-13 17
Public AreaPublic Area 156 20-Sep-12 27-Mar-13 26-Dec-12 16-Apr-13 17
Garbage RGarbage Room 102 24-Oct-12 26-Feb-13 15-Jan-13 16-Apr-13 42
FinishingFinishing Works 102 24-Oct-12 26-Feb-13 15-Jan-13 16-Apr-13 42
Wet WorWet Works 72 24-Oct-12 21-Jan-13 15-Jan-13 09-Mar-13 39
A76620 Block Works 3 24-Oct-12 29-Oct-12 15-Jan-13 17-Jan-13 66
A76560 Plaster Works 3 10-Dec-12 12-Dec-12 23-Jan-13 27-Jan-13 37
A76570 Installation of Doors& Windows Sub-frame 1 15-Dec-12 15-Dec-12 09-Mar-13 09-Mar-13 70
A76600 Wall Tiles Work 4 16-Dec-12 19-Dec-12 30-Jan-13 03-Feb-13 37
A76580 1st Coat Paint 2 20-Jan-13 21-Jan-13 04-Feb-13 05-Feb-13 12
Fisrt StaFisrt Stage Finishes 7 11-Feb-13 18-Feb-13 26-Feb-13 14-Apr-13 47
A76750 Screed Works 2 11-Feb-13 12-Feb-13 26-Feb-13 27-Feb-13 13
A76770 Floor Tiles Work 2 14-Feb-13 16-Feb-13 02-Mar-13 03-Mar-13 13
A76610 Installation of Doors 2 17-Feb-13 18-Feb-13 10-Mar-13 11-Mar-13 18
A76630 Doors Ironmongery 2 17-Feb-13 18-Feb-13 13-Apr-13 14-Apr-13 47
Second SSecond Stage Finishes 2 25-Feb-13 26-Feb-13 04-Apr-13 06-Apr-13 33
A76590 Final Coat Paint 2 25-Feb-13 26-Feb-13 04-Apr-13 06-Apr-13 33
Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42
A76740 Installation of Sinages 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42
MEP WorkMEP Works 92 30-Oct-12 18-Feb-13 19-Jan-13 14-Mar-13 21
ElectricalElectrical 90 01-Nov-12 18-Feb-13 21-Jan-13 05-Mar-13 13
A76640 Install Conduits in Wall 2 01-Nov-12 03-Nov-12 21-Jan-13 22-Jan-13 66
A76650 Wiring for Lighting & Power 2 13-Dec-12 15-Dec-12 28-Jan-13 29-Jan-13 37
A76660 Installation of Lighting Fittings 2 17-Feb-13 18-Feb-13 04-Mar-13 05-Mar-13 13
PlumbingPlumbing 88 30-Oct-12 13-Feb-13 19-Jan-13 28-Feb-13 13
A76670 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 19-Jan-13 20-Jan-13 66
A76700 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 19-Jan-13 20-Jan-13 66
A76680 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 21-Jan-13 22-Jan-13 66
A76690 Floor Drain Fixning 1 13-Feb-13 13-Feb-13 28-Feb-13 28-Feb-13 13
Fire FighFire Fighting 90 01-Nov-12 18-Feb-13 27-Feb-13 14-Mar-13 21
A76730 Fire Fighting Pipe 2 01-Nov-12 03-Nov-12 27-Feb-13 28-Feb-13 97
A76720 Hydro Static Test for Pipes 2 04-Nov-12 05-Nov-12 02-Mar-13 03-Mar-13 97
A76710 Sprinkler Fixing 2 17-Feb-13 18-Feb-13 04-Mar-13 05-Mar-13 13
A76760 Fire Alarm Devices 2 17-Feb-13 18-Feb-13 13-Mar-13 14-Mar-13 21
Corridor &Corridor & Lift Lobby 135 15-Oct-12 27-Mar-13 26-Dec-12 16-Apr-13 17
FinishingFinishing Works 135 15-Oct-12 27-Mar-13 26-Dec-12 16-Apr-13 17
Wet WorWet Works 86 15-Oct-12 29-Jan-13 26-Dec-12 21-Feb-13 20
A76830 Block Works 8 15-Oct-12 23-Oct-12 26-Dec-12 05-Jan-13 58
A76780 Plaster Works 7 01-Dec-12 09-Dec-12 08-Jan-13 15-Jan-13 31
A76800 Installation of Suspended Ceiling Grid 6 15-Dec-12 20-Dec-12 21-Jan-13 28-Jan-13 31
A76790 1st Coat Paint 5 14-Jan-13 19-Jan-13 29-Jan-13 03-Feb-13 12
A76810 Suspended Ceiling Tiles 6 22-Jan-13 29-Jan-13 16-Feb-13 21-Feb-13 20
Fisrt StaFisrt Stage Finishes 38 07-Feb-13 23-Mar-13 23-Feb-13 11-Apr-13 17
A77060 Screed Works 3 07-Feb-13 10-Feb-13 23-Feb-13 25-Feb-13 13
A77080 Floor Tiles Work 5 18-Mar-13 23-Mar-13 07-Apr-13 11-Apr-13 17
Second SSecond Stage Finishes 6 21-Mar-13 27-Mar-13 10-Apr-13 16-Apr-13 17
A76820 Installation of Doors 3 21-Mar-13 24-Mar-13 10-Apr-13 13-Apr-13 17
A76840 Doors Ironmongery 3 21-Mar-13 24-Mar-13 10-Apr-13 13-Apr-13 17
A77090 Final Coat Paint 5 23-Mar-13 27-Mar-13 11-Apr-13 16-Apr-13 17
Final StaFinal Stage Finishes 3 25-Mar-13 27-Mar-13 14-Apr-13 16-Apr-13 17
A77050 Installation of Sinages 3 25-Mar-13 27-Mar-13 14-Apr-13 16-Apr-13 17
MEP WorkMEP Works 86 24-Oct-12 07-Feb-13 06-Jan-13 10-Apr-13 53
HVACHVAC 81 24-Oct-12 02-Feb-13 12-Jan-13 27-Feb-13 22
A76850 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63
A76860 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63
A76870 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63
A76880 FCU Installation 3 01-Nov-12 04-Nov-12 17-Jan-13 20-Jan-13 63
A76890 Air-Outlet Installation 3 30-Jan-13 02-Feb-13 25-Feb-13 27-Feb-13 22
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Kitchen Cabinets
Installation of Mirrors
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Plaster Works
Installation of Doors& Windows Sub-frame
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 90 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
ElectricalElectrical 83 24-Oct-12 04-Feb-13 06-Jan-13 02-Mar-13 22
A76910 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 12-Jan-13 13-Jan-13 63
A76950 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 27-Jan-13 28-Jan-13 73
A76900 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 06-Jan-13 07-Jan-13 55
A76960 Cable Laying for Power 3 29-Oct-12 31-Oct-12 26-Jan-13 28-Jan-13 72
A76920 Wiring for Lighting & Power 3 10-Dec-12 12-Dec-12 17-Jan-13 20-Jan-13 32
A76930 Wiring for Low Current System 4 10-Dec-12 13-Dec-12 16-Jan-13 20-Jan-13 31
A76940 DB installation,Dressing & Termination 7 22-Dec-12 29-Dec-12 14-Feb-13 21-Feb-13 45
A76990 Installation of Sockets 3 30-Jan-13 02-Feb-13 27-Feb-13 02-Mar-13 24
A76980 Installation of Lighting Fittings 5 30-Jan-13 04-Feb-13 24-Feb-13 28-Feb-13 21
PlumbingPlumbing 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66
A77000 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66
Fire FighFire Fighting 85 28-Oct-12 07-Feb-13 12-Jan-13 10-Apr-13 53
A77040 Fire Fighting Pipe 4 28-Oct-12 31-Oct-12 12-Jan-13 15-Jan-13 62
A77030 Hydro Static Test for Pipes 4 01-Nov-12 05-Nov-12 16-Jan-13 20-Jan-13 62
A77020 Sprinkler Fixing 4 30-Jan-13 03-Feb-13 27-Feb-13 03-Mar-13 24
A77070 Fire Alarm Devices 5 30-Jan-13 04-Feb-13 05-Mar-13 10-Mar-13 29
A77010 Installation of Fire Extingusher&Blanket 4 04-Feb-13 07-Feb-13 07-Apr-13 10-Apr-13 53
Electrical /Electrical /Meter/ Telephone Rooms 99 30-Oct-12 26-Feb-13 23-Jan-13 16-Apr-13 42
FinishingFinishing Works 99 30-Oct-12 26-Feb-13 23-Jan-13 16-Apr-13 42
Wet WorWet Works 72 30-Oct-12 26-Jan-13 23-Jan-13 06-Mar-13 34
A77150 Block Works 3 30-Oct-12 01-Nov-12 23-Jan-13 27-Jan-13 70
A77110 Installation of Doors& Windows Sub-frame 1 13-Dec-12 13-Dec-12 06-Mar-13 06-Mar-13 69
A77100 Plaster Works 4 13-Dec-12 17-Dec-12 30-Jan-13 03-Feb-13 39
A77120 1st Coat Paint 3 22-Jan-13 26-Jan-13 06-Feb-13 09-Feb-13 12
Fisrt StaFisrt Stage Finishes 58 15-Dec-12 21-Feb-13 07-Mar-13 14-Apr-13 44
A77140 Installation of Doors 2 15-Dec-12 16-Dec-12 07-Mar-13 09-Mar-13 69
A77160 Doors Ironmongery 2 15-Dec-12 16-Dec-12 13-Apr-13 14-Apr-13 100
A77210 Epoxy Paint Works 2 20-Feb-13 21-Feb-13 31-Mar-13 01-Apr-13 33
Second SSecond Stage Finishes 2 23-Feb-13 24-Feb-13 02-Apr-13 03-Apr-13 33
A77130 Final Coat Paint 2 23-Feb-13 24-Feb-13 02-Apr-13 03-Apr-13 33
Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42
A77200 Installation of Sinages 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42
MEP WorkMEP Works 89 04-Nov-12 19-Feb-13 28-Jan-13 12-Mar-13 18
HVACHVAC 2 03-Feb-13 04-Feb-13 28-Feb-13 02-Mar-13 22
A77240 Air-Outlet Installation 2 03-Feb-13 04-Feb-13 28-Feb-13 02-Mar-13 22
ElectricalElectrical 89 04-Nov-12 19-Feb-13 28-Jan-13 05-Mar-13 12
A77170 Install Conduits in Wall 2 04-Nov-12 05-Nov-12 28-Jan-13 29-Jan-13 69
A77180 Wiring for Lighting & Power 2 18-Dec-12 19-Dec-12 04-Feb-13 05-Feb-13 39
A77230 Installation of SMDBs 7 27-Jan-13 03-Feb-13 21-Feb-13 28-Feb-13 22
A77190 Installation of Lighting Fittings 2 05-Feb-13 06-Feb-13 02-Mar-13 03-Mar-13 21
A114990 Installation of Telephone System 21 27-Jan-13 19-Feb-13 10-Feb-13 05-Mar-13 12
Fire FighFire Fighting 2 07-Feb-13 09-Feb-13 11-Mar-13 12-Mar-13 27
A77220 Fire Alarm Devices 2 07-Feb-13 09-Feb-13 11-Mar-13 12-Mar-13 27
StaircaseStaircase 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121
Stairs 1Stairs 1 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121
A111930 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121
A111970 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121
A111940 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A111950 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A111960 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121
A111980 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121
Stairs 2Stairs 2 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121
A111990 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121
A112030 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121
A112000 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A112010 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A112020 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121
A112040 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121
Stairs 3Stairs 3 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121
A112050 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121
A112090 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121
A112060 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A112070 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121
A112080 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121
A112100 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121
ApartementsApartements 165 30-Aug-12 17-Mar-13 12-Sep-12 16-Apr-13 26
One BedroOne Bedroom Flats 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36
ApartemeApartement .1- 5 (1 BR) 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36
FinishingFinishing Works 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36
Wet WoWet Works 82 04-Oct-12 13-Jan-13 28-Nov-12 05-Mar-13 43
A75120 Block Works 9 04-Oct-12 14-Oct-12 28-Nov-12 09-Dec-12 44
A74980 Installation of Doors& Windows Sub-frame 2 14-Nov-12 17-Nov-12 04-Mar-13 05-Mar-13 90
A74970 Plaster Works 13 14-Nov-12 29-Nov-12 19-Dec-12 03-Jan-13 28
A75450 Wall Tiles Work (Wet Area) 4 01-Dec-12 05-Dec-12 06-Feb-13 10-Feb-13 55
A75000 Installation of Suspended Ceiling Grid (Dry Area) 4 08-Dec-12 11-Dec-12 10-Jan-13 14-Jan-13 28
A74990 1st Coat Paint 11 31-Dec-12 13-Jan-13 15-Jan-13 28-Jan-13 12
Fisrt StaFisrt Stage Finishes 28 17-Jan-13 19-Feb-13 02-Feb-13 20-Mar-13 25
A75010 Suspended Ceiling Tiles (DryArea) 4 17-Jan-13 21-Jan-13 02-Feb-13 05-Feb-13 12
A75050 Installation of Wardrobes 4 22-Jan-13 27-Jan-13 06-Feb-13 10-Feb-13 12
A75040 Water Proofing for Wet Area 3 03-Feb-13 05-Feb-13 17-Feb-13 19-Feb-13 12
A75440 Screed Works 9 28-Jan-13 06-Feb-13 11-Feb-13 20-Feb-13 12
A75480 Installation of Suspended Ceiling Grid (Wet Area) 4 05-Feb-13 09-Feb-13 19-Feb-13 23-Feb-13 12
A75030 Floor & Wall Tiles Work (Dry Area) 4 07-Feb-13 11-Feb-13 17-Mar-13 20-Mar-13 32
A75470 Suspended Ceiling Tiles (Wet Area) 4 10-Feb-13 13-Feb-13 24-Feb-13 27-Feb-13 12
A75460 Floor Tiles Work (Wet Area) 5 14-Feb-13 19-Feb-13 06-Mar-13 11-Mar-13 17
SecondSecond Stage Finishes 7 20-Feb-13 27-Feb-13 12-Mar-13 20-Mar-13 18
A75060 Installation of Windows&Doors 3 20-Feb-13 23-Feb-13 12-Mar-13 14-Mar-13 17
A75130 Doors Ironmongery 3 20-Feb-13 23-Feb-13 18-Mar-13 20-Mar-13 22
A75100 Installation of Balustrades& Handrails 2 24-Feb-13 25-Feb-13 19-Mar-13 20-Mar-13 20
A75070 Installation of Mirrors 3 24-Feb-13 26-Feb-13 17-Mar-13 19-Mar-13 18
A75080 Installation of Kitchen Cabinets 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19
A75110 Installation of Vanity Counter 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19
A75420 Installation of Toliets Accessories 4 24-Feb-13 27-Feb-13 16-Mar-13 19-Mar-13 17
Final StFinal Stage Finishes 5 28-Feb-13 05-Mar-13 21-Mar-13 16-Apr-13 36
A75020 Final Coat Paint 5 28-Feb-13 05-Mar-13 21-Mar-13 26-Mar-13 18
A75430 Installation of Sinages 2 04-Mar-13 05-Mar-13 15-Apr-13 16-Apr-13 36
MEP WoMEP Works 110 15-Oct-12 26-Feb-13 10-Dec-12 26-Mar-13 24
HVACHVAC 102 15-Oct-12 17-Feb-13 20-Dec-12 05-Mar-13 14
A75150 Duct Installation & Insulation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53
A75160 Chilled Water Pipe Installation & Insulation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53
A75170 Condensate Pipe Installation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53
A75180 FCU Installation 5 31-Oct-12 05-Nov-12 05-Jan-13 09-Jan-13 53
A75190 Air-Outlet Installation 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14
ElectricElectrical 103 15-Oct-12 18-Feb-13 10-Dec-12 05-Mar-13 13
A75210 Install Cable Trays & Trunking 8 15-Oct-12 23-Oct-12 23-Dec-12 31-Dec-12 55
A75200 Install Conduits in Wall 8 18-Oct-12 29-Oct-12 10-Dec-12 18-Dec-12 41
A75250 Cable Laying for Low Current System 8 24-Oct-12 04-Nov-12 06-Jan-13 14-Jan-13 58
A75260 Cable Laying for Power 8 24-Oct-12 04-Nov-12 06-Jan-13 14-Jan-13 58
A75220 Wiring for Lighting & Power 5 01-Dec-12 06-Dec-12 05-Jan-13 09-Jan-13 28
A75230 Wiring for Low Current System 5 01-Dec-12 06-Dec-12 05-Jan-13 09-Jan-13 28
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Install Cable Trays & Trunking
Cable Laying for Low Current System
Install Conduits in Wall
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
1st Coat Paint
Installation of Doors
Doors Ironmongery
Epoxy Paint Works
Final Coat Paint
Installation of Sinages
Air-Outlet Installation
Install Conduits in Wall
Wiring for Lighting & Power
Installation of SMDBs
Installation of Lighting Fittings
Installation of Telephone System
Fire Alarm Devices
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Floor Screed
Install Handrails
Ceiling 1st Coat Paint
Wall 1st Coat Paint
Install Granite/Terrazo
Final Coat Paint
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Water Proofing for Wet Area
Screed Works
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Suspended Ceiling Tiles (Wet Area)
Floor Tiles Work (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Vanity Counter
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Cable Trays & Trunking
Install Conduits in Wall
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 91 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A75240 DB installation,Dressing & Termination 7 14-Jan-13 21-Jan-13 29-Jan-13 05-Feb-13 12
A75290 Installation of Sockets 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14
A75280 Installation of Lighting Fittings 4 14-Feb-13 18-Feb-13 02-Mar-13 05-Mar-13 13
PlumbinPlumbing 110 15-Oct-12 26-Feb-13 10-Dec-12 20-Mar-13 19
A75300 Drainge Pipes in Wall 8 15-Oct-12 23-Oct-12 10-Dec-12 18-Dec-12 44
A75370 Water Pipes in Wall 8 15-Oct-12 23-Oct-12 10-Dec-12 18-Dec-12 44
A75310 H/L Drainage Pipes Installation 12 15-Oct-12 30-Oct-12 31-Jan-13 13-Feb-13 87
A75320 H/L Hot&Cold Water Pipe Installation 12 15-Oct-12 30-Oct-12 31-Jan-13 13-Feb-13 87
A75330 Drainage&Water Pipes Testing 3 31-Oct-12 03-Nov-12 14-Feb-13 17-Feb-13 87
A75340 ElectricalWater Heater Installation 4 31-Oct-12 04-Nov-12 14-Feb-13 18-Feb-13 87
A75350 Floor Drain Fixning 2 30-Jan-13 31-Jan-13 04-Mar-13 05-Mar-13 28
A75360 Installation of Sanitaryware 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19
Fire FigFire Fighting 106 17-Oct-12 24-Feb-13 26-Dec-12 26-Mar-13 26
A75410 Fire Fighting Pipe 7 17-Oct-12 24-Oct-12 26-Dec-12 03-Jan-13 56
A75400 Hydro Static Test for Pipes 5 28-Oct-12 01-Nov-12 05-Jan-13 09-Jan-13 56
A75390 Sprinkler Fixing 5 14-Feb-13 19-Feb-13 28-Feb-13 05-Mar-13 12
A75380 Installation of Fire Extingusher&Blanket 2 20-Feb-13 21-Feb-13 25-Mar-13 26-Mar-13 28
A75490 Fire Alarm Devices 5 19-Feb-13 24-Feb-13 16-Mar-13 20-Mar-13 21
Two BedroTwo Bedroom Flats 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26
ApartemeApartement .1 - 10 (2 BR) 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26
FinishingFinishing Works 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26
Wet WoWet Works 86 17-Sep-12 30-Dec-12 07-Oct-12 03-Mar-13 52
A75650 Block Works 15 17-Sep-12 03-Oct-12 07-Oct-12 23-Oct-12 17
A75510 Installation of Doors& Windows Sub-frame 7 22-Oct-12 31-Oct-12 24-Feb-13 03-Mar-13 101
A75500 Plaster Works 18 22-Oct-12 13-Nov-12 10-Nov-12 01-Dec-12 14
A75980 Wall Tiles Work (Wet Area) 13 14-Nov-12 29-Nov-12 12-Jan-13 27-Jan-13 47
A75530 Installation of Suspended Ceiling Grid (Dry Area) 8 27-Nov-12 06-Dec-12 15-Dec-12 23-Dec-12 14
A75520 1st Coat Paint 18 10-Dec-12 30-Dec-12 24-Dec-12 14-Jan-13 12
Fisrt StaFisrt Stage Finishes 35 31-Dec-12 11-Feb-13 15-Jan-13 26-Mar-13 37
A75540 Suspended Ceiling Tiles (DryArea) 12 31-Dec-12 14-Jan-13 15-Jan-13 29-Jan-13 12
A75580 Installation of Wardrobes 8 08-Jan-13 16-Jan-13 22-Jan-13 31-Jan-13 12
A75970 Screed Works 9 14-Jan-13 23-Jan-13 28-Jan-13 06-Feb-13 11
A75570 Water Proofing for Wet Area 9 20-Jan-13 30-Jan-13 03-Feb-13 12-Feb-13 11
A76010 Installation of Suspended Ceiling Grid (Wet Area) 7 27-Jan-13 03-Feb-13 09-Feb-13 16-Feb-13 11
A75560 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 13-Mar-13 26-Mar-13 40
A75990 Floor Tiles Work (Wet Area) 5 06-Feb-13 11-Feb-13 10-Mar-13 14-Mar-13 27
A76000 Suspended Ceiling Tiles (Wet Area) 10 31-Jan-13 11-Feb-13 13-Feb-13 24-Feb-13 11
SecondSecond Stage Finishes 28 10-Feb-13 13-Mar-13 13-Mar-13 02-Apr-13 17
A75590 Installation of Windows&Doors 7 10-Feb-13 17-Feb-13 13-Mar-13 20-Mar-13 27
A75660 Doors Ironmongery 8 10-Feb-13 18-Feb-13 18-Mar-13 26-Mar-13 31
A75630 Installation of Balustrades& Handrails 5 18-Feb-13 23-Feb-13 21-Mar-13 26-Mar-13 27
A75600 Installation of Mirrors 9 27-Feb-13 09-Mar-13 20-Mar-13 30-Mar-13 18
A75640 Installation of Vanity Counter 9 27-Feb-13 09-Mar-13 23-Mar-13 01-Apr-13 20
A75610 Installation of Kitchen Cabinets 10 27-Feb-13 10-Mar-13 23-Mar-13 02-Apr-13 20
A75950 Installation of Toliets Accessories 12 28-Feb-13 13-Mar-13 20-Mar-13 02-Apr-13 17
Final StFinal Stage Finishes 9 07-Mar-13 17-Mar-13 27-Mar-13 16-Apr-13 26
A75550 Final Coat Paint 9 07-Mar-13 17-Mar-13 27-Mar-13 06-Apr-13 17
A75960 Installation of Sinages 7 10-Mar-13 17-Mar-13 09-Apr-13 16-Apr-13 26
MEP WoMEP Works 114 04-Oct-12 20-Feb-13 24-Oct-12 06-Apr-13 38
HVACHVAC 107 04-Oct-12 12-Feb-13 10-Nov-12 05-Mar-13 18
A75680 Duct Installation & Insulation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29
A75690 Chilled Water Pipe Installation & Insulation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29
A75700 Condensate Pipe Installation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29
A75710 FCU Installation 10 28-Oct-12 07-Nov-12 03-Dec-12 13-Dec-12 29
A75720 Air-Outlet Installation 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18
ElectricElectrical 114 04-Oct-12 20-Feb-13 24-Oct-12 05-Mar-13 11
A75730 Install Conduits in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17
A75740 Install Cable Trays & Trunking 12 04-Oct-12 17-Oct-12 14-Nov-12 28-Nov-12 33
A75780 Cable Laying for Low Current System 15 18-Oct-12 06-Nov-12 06-Dec-12 23-Dec-12 38
A75790 Cable Laying for Power 15 18-Oct-12 06-Nov-12 06-Dec-12 23-Dec-12 38
A75750 Wiring for Lighting & Power 10 14-Nov-12 26-Nov-12 03-Dec-12 13-Dec-12 14
A75760 Wiring for Low Current System 10 14-Nov-12 26-Nov-12 03-Dec-12 13-Dec-12 14
A75770 DB installation,Dressing & Termination 12 31-Dec-12 14-Jan-13 15-Jan-13 29-Jan-13 12
A75820 Installation of Sockets 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16
A75810 Installation of Lighting Fittings 13 06-Feb-13 20-Feb-13 19-Feb-13 05-Mar-13 11
PlumbinPlumbing 114 04-Oct-12 20-Feb-13 24-Oct-12 26-Mar-13 29
A75840 H/L Drainage Pipes Installation 11 04-Oct-12 16-Oct-12 17-Jan-13 30-Jan-13 85
A75850 H/L Hot&Cold Water Pipe Installation 11 04-Oct-12 16-Oct-12 17-Jan-13 30-Jan-13 85
A75830 Drainge Pipes in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17
A75900 Water Pipes in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17
A75870 ElectricalWater Heater Installation 4 17-Oct-12 21-Oct-12 04-Feb-13 07-Feb-13 88
A75860 Drainage&Water Pipes Testing 7 17-Oct-12 24-Oct-12 31-Jan-13 07-Feb-13 85
A75880 Floor Drain Fixning 2 16-Jan-13 17-Jan-13 04-Mar-13 05-Mar-13 39
A75890 Installation of Sanitaryware 3 18-Feb-13 20-Feb-13 24-Mar-13 26-Mar-13 29
Fire FigFire Fighting 113 04-Oct-12 19-Feb-13 22-Nov-12 06-Apr-13 39
A75940 Fire Fighting Pipe 11 04-Oct-12 16-Oct-12 22-Nov-12 05-Dec-12 39
A75930 Hydro Static Test for Pipes 7 17-Oct-12 24-Oct-12 06-Dec-12 13-Dec-12 39
A75910 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 04-Apr-13 06-Apr-13 49
A75920 Sprinkler Fixing 7 06-Feb-13 13-Feb-13 26-Feb-13 05-Mar-13 17
A76020 Fire Alarm Devices 7 12-Feb-13 19-Feb-13 19-Mar-13 26-Mar-13 30
Three BedrThree Bedroom Flats 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38
ApartemeApartement .1 -4 (3 BR) 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38
FinishingFinishing Works 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38
Wet WoWet Works 83 30-Aug-12 09-Dec-12 12-Sep-12 23-Feb-13 63
A76180 Block Works 15 30-Aug-12 16-Sep-12 12-Sep-12 29-Sep-12 11
A76040 Installation of Doors& Windows Sub-frame 7 01-Oct-12 08-Oct-12 16-Feb-13 23-Feb-13 112
A76030 Plaster Works 18 01-Oct-12 21-Oct-12 14-Oct-12 05-Nov-12 11
A76510 Wall Tiles Work (Wet Area) 13 22-Oct-12 07-Nov-12 31-Dec-12 15-Jan-13 56
A76060 Installation of Suspended Ceiling Grid (Dry Area) 8 07-Nov-12 17-Nov-12 21-Nov-12 29-Nov-12 11
A76050 1st Coat Paint 18 18-Nov-12 09-Dec-12 01-Dec-12 22-Dec-12 11
Fisrt StaFisrt Stage Finishes 47 10-Dec-12 04-Feb-13 23-Dec-12 26-Mar-13 43
A76070 Suspended Ceiling Tiles (DryArea) 12 10-Dec-12 23-Dec-12 23-Dec-12 06-Jan-13 11
A76110 Installation of Wardrobes 8 24-Dec-12 02-Jan-13 07-Jan-13 15-Jan-13 11
A76500 Screed Works 9 03-Jan-13 13-Jan-13 16-Jan-13 27-Jan-13 11
A76100 Water Proofing for Wet Area 9 14-Jan-13 23-Jan-13 30-Jan-13 09-Feb-13 13
A76090 Floor & Wall Tiles Work (Dry Area) 12 14-Jan-13 28-Jan-13 13-Mar-13 26-Mar-13 49
A76540 Installation of Suspended Ceiling Grid (Wet Area) 7 20-Jan-13 28-Jan-13 05-Feb-13 12-Feb-13 13
A76520 Floor Tiles Work (Wet Area) 5 30-Jan-13 04-Feb-13 05-Mar-13 10-Mar-13 29
A76530 Suspended Ceiling Tiles (Wet Area) 10 23-Jan-13 04-Feb-13 09-Feb-13 19-Feb-13 13
SecondSecond Stage Finishes 19 04-Feb-13 25-Feb-13 10-Mar-13 04-Apr-13 33
A76120 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 10-Mar-13 17-Mar-13 29
A76190 Doors Ironmongery 9 04-Feb-13 13-Feb-13 17-Mar-13 26-Mar-13 35
A76160 Installation of Balustrades& Handrails 5 12-Feb-13 17-Feb-13 21-Mar-13 26-Mar-13 32
A76170 Installation of Vanity Counter 9 07-Feb-13 17-Feb-13 21-Mar-13 31-Mar-13 36
A76130 Installation of Mirrors 9 12-Feb-13 21-Feb-13 21-Mar-13 31-Mar-13 32
A76140 Installation of Kitchen Cabinets 10 12-Feb-13 23-Feb-13 21-Mar-13 01-Apr-13 32
A76480 Installation of Toliets Accessories 12 12-Feb-13 25-Feb-13 23-Mar-13 04-Apr-13 33
Final StFinal Stage Finishes 9 21-Feb-13 03-Mar-13 27-Mar-13 16-Apr-13 38
A76080 Final Coat Paint 9 21-Feb-13 03-Mar-13 27-Mar-13 06-Apr-13 29
A76490 Installation of Sinages 5 26-Feb-13 03-Mar-13 11-Apr-13 16-Apr-13 38
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Installation of Fire Extingusher&Blanket
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Installation of Suspended Ceiling Grid (Wet Area)
Floor & Wall Tiles Work (Dry Area)
Floor Tiles Work (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Mirrors
Installation of Vanity Counter
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
Electrical Water Heater Installation
Drainage&Water Pipes Testing
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work (Wet Area)
Installation of Suspended Ceiling Grid (Dry Area)
1st Coat Paint
Suspended Ceiling Tiles (DryArea)
Installation of Wardrobes
Screed Works
Water Proofing for Wet Area
Floor & Wall Tiles Work (Dry Area)
Installation of Suspended Ceiling Grid (Wet Area)
Floor Tiles Work (Wet Area)
Suspended Ceiling Tiles (Wet Area)
Installation of Windows&Doors
Doors Ironmongery
Installation of Balustrades& Handrails
Installation of Vanity Counter
Installation of Mirrors
Installation of Kitchen Cabinets
Installation of Toliets Accessories
Final Coat Paint
Installation of Sinages
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 92 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
MEP WoMEP Works 133 17-Sep-12 25-Feb-13 30-Sep-12 06-Apr-13 34
HVACHVAC 125 17-Sep-12 16-Feb-13 13-Oct-12 05-Mar-13 15
A76210 Duct Installation & Insulation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22
A76220 Chilled Water Pipe Installation & Insulation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22
A76230 Condensate Pipe Installation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22
A76240 FCU Installation 13 08-Oct-12 22-Oct-12 05-Nov-12 20-Nov-12 22
A76250 Air-Outlet Installation 10 05-Feb-13 16-Feb-13 23-Feb-13 05-Mar-13 15
ElectricElectrical 127 17-Sep-12 18-Feb-13 30-Sep-12 05-Mar-13 13
A76260 Install Conduits in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11
A76270 Install Cable Trays & Trunking 12 17-Sep-12 30-Sep-12 18-Oct-12 03-Nov-12 27
A76310 Cable Laying for Low Current System 15 01-Oct-12 17-Oct-12 12-Nov-12 29-Nov-12 34
A76320 Cable Laying for Power 15 01-Oct-12 17-Oct-12 12-Nov-12 29-Nov-12 34
A76280 Wiring for Lighting & Power 12 22-Oct-12 06-Nov-12 06-Nov-12 20-Nov-12 11
A76290 Wiring for Low Current System 12 22-Oct-12 06-Nov-12 06-Nov-12 20-Nov-12 11
A76300 DB installation,Dressing & Termination 10 10-Dec-12 20-Dec-12 25-Dec-12 06-Jan-13 13
A76350 Installation of Sockets 9 05-Feb-13 14-Feb-13 24-Feb-13 05-Mar-13 16
A76340 Installation of Lighting Fittings 12 05-Feb-13 18-Feb-13 20-Feb-13 05-Mar-13 13
PlumbinPlumbing 133 17-Sep-12 25-Feb-13 30-Sep-12 31-Mar-13 29
A76370 H/L Drainage Pipes Installation 11 17-Sep-12 29-Sep-12 10-Jan-13 22-Jan-13 94
A76380 H/L Hot&Cold Water Pipe Installation 11 17-Sep-12 29-Sep-12 10-Jan-13 22-Jan-13 94
A76360 Drainge Pipes in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11
A76430 Water Pipes in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11
A76390 Drainage&Water Pipes Testing 7 30-Sep-12 07-Oct-12 23-Jan-13 31-Jan-13 94
A76400 ElectricalWater Heater Installation 10 30-Sep-12 10-Oct-12 23-Jan-13 04-Feb-13 94
A76410 Floor Drain Fixning 9 06-Jan-13 15-Jan-13 24-Feb-13 05-Mar-13 41
A76420 Installation of Sanitaryware 12 12-Feb-13 25-Feb-13 18-Mar-13 31-Mar-13 29
Fire FigFire Fighting 125 17-Sep-12 16-Feb-13 30-Oct-12 06-Apr-13 42
A76470 Fire Fighting Pipe 11 17-Sep-12 29-Sep-12 30-Oct-12 11-Nov-12 35
A76460 Hydro Static Test for Pipes 7 30-Sep-12 07-Oct-12 12-Nov-12 20-Nov-12 35
A76440 Installation of Fire Extingusher&Blanket 2 05-Feb-13 06-Feb-13 04-Apr-13 06-Apr-13 50
A76450 Sprinkler Fixing 10 05-Feb-13 16-Feb-13 23-Feb-13 05-Mar-13 15
A76550 Fire Alarm Devices 10 05-Feb-13 16-Feb-13 16-Mar-13 26-Mar-13 33
3rd Floor3rd Floor 161 13-Sep-12 26-Mar-13 27-Sep-12 16-Apr-13 18
Public AreaPublic Area 141 07-Oct-12 26-Mar-13 26-Dec-12 16-Apr-13 18
Garbage RGarbage Room 89 24-Oct-12 11-Feb-13 05-Feb-13 16-Apr-13 55
FinishingFinishing Works 89 24-Oct-12 11-Feb-13 05-Feb-13 16-Apr-13 55
Wet WorWet Works 68 24-Oct-12 16-Jan-13 05-Feb-13 07-Apr-13 68
A78900 Block Works 3 24-Oct-12 29-Oct-12 05-Feb-13 07-Feb-13 83
A78850 Installation of Doors& Windows Sub-frame 1 08-Dec-12 08-Dec-12 07-Apr-13 07-Apr-13 101
A78840 Plaster Works 3 08-Dec-12 10-Dec-12 13-Feb-13 16-Feb-13 56
A78880 Wall Tiles Work 4 13-Dec-12 17-Dec-12 19-Feb-13 23-Feb-13 56
A78860 1st Coat Paint 2 15-Jan-13 16-Jan-13 24-Feb-13 25-Feb-13 33
Fisrt StaFisrt Stage Finishes 20 17-Jan-13 10-Feb-13 26-Feb-13 15-Apr-13 55
A79030 Screed Works 2 17-Jan-13 19-Jan-13 26-Feb-13 27-Feb-13 33
A79050 Floor Tiles Work 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33
A78910 Doors Ironmongery 1 09-Feb-13 09-Feb-13 15-Apr-13 15-Apr-13 56
A78890 Installation of Doors 2 09-Feb-13 10-Feb-13 08-Apr-13 09-Apr-13 50
Second SSecond Stage Finishes 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45
A78870 Final Coat Paint 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45
Final StaFinal Stage Finishes 1 11-Feb-13 11-Feb-13 16-Apr-13 16-Apr-13 55
A79020 Installation of Sinages 1 11-Feb-13 11-Feb-13 16-Apr-13 16-Apr-13 55
MEP WorkMEP Works 72 30-Oct-12 26-Jan-13 09-Feb-13 01-Apr-13 56
ElectricalElectrical 72 30-Oct-12 26-Jan-13 11-Feb-13 05-Mar-13 33
A78920 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 11-Feb-13 12-Feb-13 85
A78930 Wiring for Lighting & Power 2 11-Dec-12 12-Dec-12 17-Feb-13 18-Feb-13 56
A78940 Installation of Lighting Fittings 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33
PlumbingPlumbing 68 30-Oct-12 20-Jan-13 09-Feb-13 28-Feb-13 33
A78950 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 09-Feb-13 10-Feb-13 83
A78980 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 09-Feb-13 10-Feb-13 83
A78960 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 11-Feb-13 12-Feb-13 83
A78970 Floor Drain Fixning 1 20-Jan-13 20-Jan-13 28-Feb-13 28-Feb-13 33
Fire FighFire Fighting 72 30-Oct-12 26-Jan-13 27-Feb-13 01-Apr-13 56
A79010 Fire Fighting Pipe 2 30-Oct-12 31-Oct-12 27-Feb-13 28-Feb-13 99
A79000 Hydro Static Test for Pipes 2 01-Nov-12 03-Nov-12 02-Mar-13 03-Mar-13 99
A78990 Sprinkler Fixing 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33
A79040 Fire Alarm Devices 2 23-Jan-13 26-Jan-13 31-Mar-13 01-Apr-13 56
Corridor &Corridor & Lift Lobby 134 15-Oct-12 26-Mar-13 30-Dec-12 16-Apr-13 18
FinishingFinishing Works 134 15-Oct-12 26-Mar-13 30-Dec-12 16-Apr-13 18
Wet WorWet Works 80 15-Oct-12 21-Jan-13 30-Dec-12 27-Feb-13 31
A79110 Block Works 8 15-Oct-12 23-Oct-12 30-Dec-12 08-Jan-13 61
A79060 Plaster Works 7 28-Nov-12 06-Dec-12 12-Jan-13 19-Jan-13 36
A79080 Installation of Suspended Ceiling Grid 6 12-Dec-12 18-Dec-12 26-Jan-13 31-Jan-13 36
A79070 1st Coat Paint 5 09-Jan-13 14-Jan-13 16-Feb-13 20-Feb-13 31
A79090 Suspended Ceiling Tiles 6 15-Jan-13 21-Jan-13 21-Feb-13 27-Feb-13 31
Fisrt StaFisrt Stage Finishes 48 22-Jan-13 19-Mar-13 01-Apr-13 09-Apr-13 18
A79340 Screed Works 3 22-Jan-13 26-Jan-13 01-Apr-13 03-Apr-13 58
A79360 Floor Tiles Work 5 14-Mar-13 19-Mar-13 04-Apr-13 09-Apr-13 18
Second SSecond Stage Finishes 6 20-Mar-13 26-Mar-13 10-Apr-13 16-Apr-13 18
A79100 Installation of Doors 3 20-Mar-13 23-Mar-13 10-Apr-13 13-Apr-13 18
A79120 Doors Ironmongery 3 20-Mar-13 23-Mar-13 10-Apr-13 13-Apr-13 18
A79370 Final Coat Paint 5 21-Mar-13 26-Mar-13 11-Apr-13 16-Apr-13 18
Final StaFinal Stage Finishes 3 24-Mar-13 26-Mar-13 14-Apr-13 16-Apr-13 18
A79330 Installation of Sinages 3 24-Mar-13 26-Mar-13 14-Apr-13 16-Apr-13 18
MEP WorkMEP Works 80 24-Oct-12 31-Jan-13 09-Jan-13 10-Apr-13 59
HVACHVAC 75 24-Oct-12 26-Jan-13 15-Jan-13 05-Mar-13 33
A79130 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66
A79140 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66
A79150 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66
A79160 FCU Installation 3 01-Nov-12 04-Nov-12 21-Jan-13 23-Jan-13 66
A79170 Air-Outlet Installation 3 22-Jan-13 26-Jan-13 03-Mar-13 05-Mar-13 33
ElectricalElectrical 77 24-Oct-12 28-Jan-13 09-Jan-13 05-Mar-13 31
A79180 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 09-Jan-13 10-Jan-13 61
A79190 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 15-Jan-13 16-Jan-13 66
A79230 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 30-Jan-13 31-Jan-13 76
A79240 Cable Laying for Power 3 29-Oct-12 31-Oct-12 29-Jan-13 31-Jan-13 75
A79200 Wiring for Lighting & Power 3 08-Dec-12 10-Dec-12 21-Jan-13 23-Jan-13 37
A79210 Wiring for Low Current System 4 08-Dec-12 11-Dec-12 20-Jan-13 23-Jan-13 36
A79220 DB installation,Dressing & Termination 7 19-Dec-12 26-Dec-12 20-Feb-13 27-Feb-13 52
A79270 Installation of Sockets 3 22-Jan-13 26-Jan-13 03-Mar-13 05-Mar-13 33
A79260 Installation of Lighting Fittings 5 22-Jan-13 28-Jan-13 28-Feb-13 05-Mar-13 31
PlumbingPlumbing 5 24-Oct-12 31-Oct-12 19-Jan-13 23-Jan-13 69
A79280 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 19-Jan-13 23-Jan-13 69
Fire FighFire Fighting 80 24-Oct-12 31-Jan-13 15-Jan-13 10-Apr-13 59
A79320 Fire Fighting Pipe 4 24-Oct-12 30-Oct-12 15-Jan-13 19-Jan-13 66
A79310 Hydro Static Test for Pipes 4 31-Oct-12 04-Nov-12 20-Jan-13 23-Jan-13 66
A79300 Sprinkler Fixing 4 22-Jan-13 27-Jan-13 02-Mar-13 05-Mar-13 32
A79350 Fire Alarm Devices 5 22-Jan-13 28-Jan-13 06-Apr-13 10-Apr-13 62
A79290 Installation of Fire Extingusher&Blanket 4 28-Jan-13 31-Jan-13 07-Apr-13 10-Apr-13 59
Electrical /Electrical /Meter/ Telephone Rooms 99 11-Oct-12 10-Feb-13 26-Dec-12 16-Apr-13 56
FinishingFinishing Works 99 11-Oct-12 10-Feb-13 26-Dec-12 16-Apr-13 56
Wet WorWet Works 72 11-Oct-12 08-Jan-13 26-Dec-12 20-Feb-13 36
ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2012 2013
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Drainage Pipes Installation
H/L Hot&Cold Water Pipe Installation
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Electrical Water Heater Installation
Floor Drain Fixning
Installation of Sanitaryware
Fire Fighting Pipe
Hydro Static Test for Pipes
Installation of Fire Extingusher&Blanket
Sprinkler Fixing
Fire Alarm Devices
Block Works
Installation of Doors& Windows Sub-frame
Plaster Works
Wall Tiles Work
1st Coat Paint
Screed Works
Floor Tiles Work
Doors Ironmongery
Installation of Doors
Final Coat Paint
Installation of Sinages
Install Conduits in Wall
Wiring for Lighting & Power
Installation of Lighting Fittings
Drainge Pipes in Wall
Water Pipes in Wall
Drainage&Water Pipes Testing
Floor Drain Fixning
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Block Works
Plaster Works
Installation of Suspended Ceiling Grid
1st Coat Paint
Suspended Ceiling Tiles
Screed Works
Floor Tiles Work
Installation of Doors
Doors Ironmongery
Final Coat Paint
Installation of Sinages
Duct Installation & Insulation
Chilled Water Pipe Installation & Insulation
Condensate Pipe Installation
FCU Installation
Air-Outlet Installation
Install Conduits in Wall
Install Cable Trays & Trunking
Cable Laying for Low Current System
Cable Laying for Power
Wiring for Lighting & Power
Wiring for Low Current System
DB installation,Dressing & Termination
Installation of Sockets
Installation of Lighting Fittings
H/L Hot&Cold Water Pipe Installation
Fire Fighting Pipe
Hydro Static Test for Pipes
Sprinkler Fixing
Fire Alarm Devices
Installation of Fire Extingusher&Blanket
Asset Management Group (Wasl) 
Al Muraqqabat Mixed Use Development
Data Date : 01-Jan-12
Page : 93 of 114
Printed On : 02-Feb-12
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Critical Milestones
Project Implementation Schedule
Overall Schedule
Date Revision Chec... Approved
25-Jan-12 Project Implementation Schedule - Rev 00
Activity ID Activity Name Original
Duration
Early Start Early Finish Late Start Late Finish Total Float
A79430 Block Works 3 11-Oct-12 14-Oct-12 26-Dec-12 29-Dec-12 61
A79390 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 20-Feb-13 20-Feb-13 73
A79380 Plaster Works 4 24-Nov-12 27-Nov-12 07-Jan-13 10-Jan-13 36
A79400 1st Coat Paint 3 06-Jan-13 08-Jan-13 06-Feb-13 09-Feb-13 26
Fisrt StaFisrt Stage Finishes 57 28-Nov-12 05-Feb-13 21-Feb-13 14-Apr-13 58
A79420 Installation of Doors 2 28-Nov-12 29-Nov-12 21-Feb-13 23-Feb-13 70
A79440 Doors Ironmongery 2 28-Nov-12 29-Nov-12 13-Apr-13 14-Apr-13 113
A79490 Epoxy Paint Works 2 04-Feb-13 05-Feb-13 28-Mar-13 30-Mar-13 45
Second SSecond Stage Finishes 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45
A79410 Final Coat Paint 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45
Final StaFinal Stage Finishes 2 09-Feb-13 10-Feb-13 15-Apr-13 16-Apr-13 56
A79480 Installation of Sinages 2 09-Feb-13 10-Feb-13 15-Apr-13 16-Apr-13 56
MEP WorkMEP Works 90 15-Oct-12 03-Feb-13 05-Jan-13 27-Mar-13 45
HVACHVAC 2 09-Jan-13 10-Jan-13 04-Mar-13 05-Mar-13 45
A79520 Air-Outlet Installation 2 09-Jan-13 10-Jan-13 04-Mar-13 05-Mar-13 45
ElectricalElectrical 90 15-Oct-12 03-Feb-13 05-Jan-13 05-Mar-13 26
A79450 Install Conduits in Wall 2 15-Oct-12 16-Oct-12 05-Jan-13 06-Jan-13 65
A79460 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 04-Feb-13 05-Feb-13 55
A79510 Installation of SMDBs 7 09-Jan-13 16-Jan-13 24-Feb-13 03-Mar-13 38
A79470 Installation of Lighting Fittings 2 17-Jan-13 19-Jan-13 04-Mar-13 05-Mar-13 38
A115000 Installation of Telephone System 21 09-Jan-13 03-Feb-13 10-Feb-13 05-Mar-13 26
Fire FighFire Fighting 2 20-Jan-13 21-Jan-13 26-Mar-13 27-Mar-13 55
A79500 Fire Alarm Devices 2 20-Jan-13 21-Jan-13 26-Mar-13 27-Mar-13 55
StaircaseStaircase 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105
Stairs 1Stairs 1 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105
A112170 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105
A112210 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105
A112180 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112190 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112200 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105
A112220 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105
Stairs 2Stairs 2 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105
A112230 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105
A112270 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105
A112240 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112250 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112260 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105
A112280 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105
Stairs 3Stairs 3 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105
A112290 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105
A112330 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105
A112300 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112310 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105
A112320 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105
A112340 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105
ApartementsApartements 157 13-Sep-12 21-Mar-13 27-Sep-12 16-Apr-13 22
One BedroOne Bedroom Flats 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61
ApartemeApartement .1- 5 (1 BR) 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61
FinishingFinishing Works 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61
Wet WoWet Works 60 01-Oct-12 13-Dec-12 12-Nov-12 19-Feb-13 56
A77400 Block Works 9 01-Oct-12 10-Oct-12 12-Nov-12 22-Nov-12 34
A77260 Installation of Doors& Windows Sub-frame 2 07-Nov-12 08-Nov-12 18-Feb-13 19-Feb-13 84
A77250 Plaster Works 13 07-Nov-12 22-Nov-12 28-Nov-12 13-Dec-12 17
A77280 Installation of Suspended Ceiling Grid (Dry Area) 4 27-Nov-12 01-Dec-12 18-Dec-12 22-Dec-12 17
A77730 Wall Tiles Work (Wet Area) 9 24-Nov-12 04-Dec-12 31-Dec-12 10-Jan-13 31
A77270 1st Coat Paint 11 01-Dec-12 13-Dec-12 22-Dec-12 03-Jan-13 17
Fisrt StaFisrt Stage Finishes 31 12-Dec-12 17-Jan-13 03-Jan-13 24-Feb-13 31
A77290 Suspended Ceiling Tiles (DryArea) 4 12-Dec-12 16-Dec-12 03-Jan-13 07-Jan-13 18
A77330 Installation of Wardrobes 4 16-Dec-12 19-Dec-12 13-Jan-13 16-Jan-13 23
A77720 Screed Works 9 19-Dec-12 29-Dec-12 16-Jan-13 27-Jan-13 23
A77320 Water Proofing for Wet Area 3 30-Dec-12 02-Jan-13 29-Jan-13 31-Jan-13 24
A77310 Floor & Wall Tiles Work (Dry Area) 4 30-Dec-12 03-Jan-13 20-Feb-13 24-Feb-13 43
A77760 Installation of Suspended Ceiling Grid (Wet Area) 4 03-Jan-13 07-Jan-13 02-Feb-13 05-Feb-13 24
A77750 Suspended Ceiling Tiles (Wet Area) 4 08-Jan-13 12-Jan-13 06-Feb-13 10-Feb-13 24
A77740 Floor Tiles Work (Wet Area) 5 13-Jan-13 17-Jan-13 18-Feb-13 23-Feb-13 30
SecondSecond Stage Finishes 7 19-Jan-13 27-Jan-13 24-Feb-13 07-Mar-13 34
A77340 Installation of Windows&Doors 3 19-Jan-13 21-Jan-13 24-Feb-13 26-Feb-13 30
A77410 Doors Ironmongery 3 19-Jan-13 21-Jan-13 05-Mar-13 07-Mar-13 38
A77380 Installation of Balustrades& Handrails 2 22-Jan-13 23-Jan-13 06-Mar-13 07-Mar-13 36
A77350 Installation of Mirrors 3 22-Jan-13 26-Jan-13 05-Mar-13 07-Mar-13 35
A77360 Installation of Kitchen Cabinets 3 22-Jan-13 26-Jan-1
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme -  Rev 00

More Related Content

PDF
Contract 2 - Project Progress Status. Oct-13
PDF
Window Analysis @ 30-June-2012
PDF
10. Overall Implementation Programme
PDF
Monthly Progress Report No.13 - September 2011
PDF
Wreport
PPT
Power Point BLCC End of year Review
Contract 2 - Project Progress Status. Oct-13
Window Analysis @ 30-June-2012
10. Overall Implementation Programme
Monthly Progress Report No.13 - September 2011
Wreport
Power Point BLCC End of year Review

What's hot (16)

PDF
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
PDF
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
PPTX
Project Controls planning & Scheduling Engineer-Portfolio
PDF
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
PDF
Project Schedule - Level IV Schedule
PPT
C&ess presentation drm (30.10.13)
DOCX
jahangir
PDF
Mauli Engineering Services Presentation
DOC
Curriculum Vitae 16 08 15
DOCX
Case study 1 effective and efficient communication
PDF
Kalyan Chunchu Resume
PDF
Payment Method for Work item Studies and Design November 26, 2010.
PDF
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
PDF
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
DOC
CV Pete Mcelwee 2016
PDF
Single Family Gantt Chart-John Mueller
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
Project Controls planning & Scheduling Engineer-Portfolio
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Project Schedule - Level IV Schedule
C&ess presentation drm (30.10.13)
jahangir
Mauli Engineering Services Presentation
Curriculum Vitae 16 08 15
Case study 1 effective and efficient communication
Kalyan Chunchu Resume
Payment Method for Work item Studies and Design November 26, 2010.
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
CV Pete Mcelwee 2016
Single Family Gantt Chart-John Mueller
Ad

Similar to 01. P269 - Project Implementation Programme - Rev 00 (20)

PDF
ADIB Time Schedule V4.0
PDF
MS project Sample gantt chart
PDF
MS Projects - 10 MW Implementation Schedule
PDF
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
PDF
Nbourdier-lab2-gantt chart with activities-
PDF
PDF
Microsoft Project Network Diagram
PDF
Weekly report no 19
PDF
Engineering Design Center Project Schedule
PDF
Offshore Programme using QP-P3 protocol
PDF
PDF
ARB JANADREA 25.01.16 UPDATE PM
PDF
ICOM Schedule & Logistics (1)
PDF
Sample MSProject with 16 DivisionFormat Variation(EOT)
PDF
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
PPTX
Mikazuki Slide.pptx
PDF
Final Majarrah rev 0
PDF
As plan v as-built graphical analysis (11 jun19)
DOCX
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
ADIB Time Schedule V4.0
MS project Sample gantt chart
MS Projects - 10 MW Implementation Schedule
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Nbourdier-lab2-gantt chart with activities-
Microsoft Project Network Diagram
Weekly report no 19
Engineering Design Center Project Schedule
Offshore Programme using QP-P3 protocol
ARB JANADREA 25.01.16 UPDATE PM
ICOM Schedule & Logistics (1)
Sample MSProject with 16 DivisionFormat Variation(EOT)
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Mikazuki Slide.pptx
Final Majarrah rev 0
As plan v as-built graphical analysis (11 jun19)
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Ad

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

PDF
Kandil Mohammed Ibrahim_Sameh_Dissertation
PDF
Summary Progress Of Facade Works
PDF
Summary Progress Of Concrete Works
PDF
Progress Of Ceiling Per Floors
PDF
Overall Progress S-Curve For Ceiling
PDF
Overall Progress S-Curve For Facades
PDF
Overall Progress S-Curve For Elevators
PDF
Overall Progres S-Curve For Concrete Works
PDF
Building-Structure Planning Model
DOC
Rihan Height Project Execution Plan-Rev00
PDF
Resources Calculations for Bldg. A
Kandil Mohammed Ibrahim_Sameh_Dissertation
Summary Progress Of Facade Works
Summary Progress Of Concrete Works
Progress Of Ceiling Per Floors
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For Facades
Overall Progress S-Curve For Elevators
Overall Progres S-Curve For Concrete Works
Building-Structure Planning Model
Rihan Height Project Execution Plan-Rev00
Resources Calculations for Bldg. A

01. P269 - Project Implementation Programme - Rev 00

  • 1. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Al MuraqqAl Muraqqabat Mixed Use Development 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 GeneralGeneral 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 ContractualContractual Milestones 537 02-Jan-12 02-Oct-13 31-Dec-11 02-Oct-13 0 A1000 Project Commencement Date 0 02-Jan-12 31-Dec-11 0 A1030 Completion Date of Phase 1 0 04-Jul-13 04-Jul-13 0 A1050 Overall Duration of Phase 1 550 02-Jan-12 04-Jul-13 01-Apr-12 02-Oct-13 90 A1010 Completion Date of Phase 2 0 02-Oct-13 02-Oct-13 0 A1020 Overall Duration of Phase 2 640 02-Jan-12 02-Oct-13 02-Jan-12 02-Oct-13 0 Control MileControl Milestones 367 24-Apr-12 08-Jul-13 15-Dec-12 02-Oct-13 74 Civil WorksCivil Works Completion Milestones 158 08-May-12 14-Nov-12 02-Oct-13 02-Oct-13 270 A9066 Completion of Raft Slab (Block A,B,C) 0 08-May-12 02-Oct-13 428 A9067 Completion of Ground Floor Slab (Block A,B,C) 0 23-Jun-12 02-Oct-13 390 A9068 Completion of the Skeleton for Block A 0 17-Sep-12 02-Oct-13 318 A9089 Completion of the Skeleton for Block C 0 30-Oct-12 02-Oct-13 283 A9069 Completion of the Skeleton for Block B 0 14-Nov-12 02-Oct-13 270 ArchitecturaArchitectural Works Milestones 81 24-Apr-12 29-Jul-12 15-Dec-12 16-Dec-12 114 A9182 Start of Block Works @ Basements 0 24-Apr-12 16-Dec-12 195 A9183 Start of Block Works @ 1st Floor 0 29-Jul-12 15-Dec-12 113 Fit Out andFit Out and FF&E Milestones 78 06-Apr-13 08-Jul-13 16-Apr-13 02-Oct-13 74 Fit Out MilestFit Out Milestones 15 06-Apr-13 23-Apr-13 16-Apr-13 28-Apr-13 4 A9360 Completion of Fit Out for Block C 0 06-Apr-13 16-Apr-13 9 A9340 Completion of Fit Out for Block A 0 17-Apr-13 25-Apr-13 7 A9350 Completion of Fit Out for Block B 0 23-Apr-13 28-Apr-13 4 FF & E MilestFF & E Milestones 2 06-Jul-13 08-Jul-13 02-Oct-13 02-Oct-13 74 A9370 Commencement of FF&E @ Block A 0 06-Jul-13 02-Oct-13 76 A1232 Commencement of FF&E @ Block B 0 06-Jul-13 02-Oct-13 76 A1222 Commencement of FF&E @ Block C 0 08-Jul-13 02-Oct-13 74 MEP WorksMEP Works Milestones 67 26-Jan-13 14-Apr-13 05-Mar-13 24-Apr-13 9 A9226 Completion of LPG System 0 26-Jan-13 10-Apr-13 64 A9256 Completion of MEP Works ( Related to Temporary Power) 0 21-Feb-13 05-Mar-13 10 A9196 Completion of Elevators 0 14-Mar-13 23-Mar-13 7 A9216 Completion of Garbage & Linen Chute 0 14-Apr-13 24-Apr-13 9 Facade WorFacade Works Milestones 69 02-Apr-13 23-Jun-13 04-Jul-13 04-Jul-13 10 A9236 Completion of Facade Cleaning System 0 02-Apr-13 04-Jul-13 79 A9206 Completion of Facade Glazing 0 22-Jun-13 04-Jul-13 11 A9246 Completion of Facade Lighting System 0 23-Jun-13 04-Jul-13 10 Authorities AAuthorities Approvals 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10 SwimmimngSwimmimng Pool 86 08-Jul-12 17-Oct-12 17-Jul-12 01-Nov-12 11 A1435 EHS Approval for Pouring Pools Slab - Block B 10 08-Jul-12 18-Jul-12 17-Jul-12 28-Jul-12 8 A1436 EHS Approval for Pouring Pools Slab - Block A 10 27-Aug-12 06-Sep-12 10-Sep-12 20-Sep-12 12 A1438 EHS Approval for Pouring Pools Slab - Block C 10 07-Oct-12 17-Oct-12 20-Oct-12 01-Nov-12 11 Temporary PTemporary Power Connection 338 30-Jan-12 11-Mar-13 17-Mar-12 23-Mar-13 10 A1348 Receipt of Design NOC for Electrical Drawings 0 30-Jan-12 17-Mar-12 39 A1358 Confirmation of RMU & Transformers Rooms Layout 0 30-Jan-12 17-Jul-12 143 A1368 Submission & Approval of Electrical Drawings 25 02-Jun-12 01-Jul-12 18-Jul-12 15-Aug-12 39 A1408 Application for Fee Estimation 11 21-Jul-12 01-Aug-12 13-Oct-12 24-Oct-12 70 A1418 Fee Payment by Client to DEWA 12 02-Aug-12 15-Aug-12 28-Oct-12 10-Nov-12 70 A1378 Substation Inspection Invitation to DEWA 6 01-Oct-12 07-Oct-12 09-Mar-13 14-Mar-13 130 A1388 Civil Work Inspection by DEWA 6 08-Oct-12 14-Oct-12 16-Mar-13 21-Mar-13 130 A1398 Approval & Handover Substations to DEWA 0 14-Oct-12 21-Mar-13 130 A1428 Delivery- Installation - Termination of Transformers - RMU 0 27-Dec-12 21-Mar-13 70 A1458 Invitation to DEWA for MEP Work Inspection 2 23-Feb-13 24-Feb-13 06-Mar-13 07-Mar-13 10 A1468 1st MEP Inspection & Comments by DEWA 2 25-Feb-13 26-Feb-13 09-Mar-13 10-Mar-13 10 A1478 Attend DEWA Comments 10 27-Feb-13 10-Mar-13 11-Mar-13 21-Mar-13 10 A1488 Final MEP Inspection & Approval By DEWA 1 11-Mar-13 11-Mar-13 23-Mar-13 23-Mar-13 10 A1518 Release DEWA Temporary Power for T & C 0 11-Mar-13 23-Mar-13 10 Utilities ConUtilities Connection 118 16-Feb-13 04-Jul-13 26-Mar-13 04-Jul-13 0 Gas ConnecGas Connection 0 28-Feb-13 28-Feb-13 26-Mar-13 26-Mar-13 22 A2970 Gas Supply Connection 0 28-Feb-13 26-Mar-13 22 Water SuppWater Supply Connection 0 07-Mar-13 07-Mar-13 01-May-13 01-May-13 47 A2950 Water Supply Connection 0 07-Mar-13 01-May-13 47 Sewage ConSewage Connection 0 16-Feb-13 16-Feb-13 16-Apr-13 16-Apr-13 51 A2960 Sewage Connection 0 16-Feb-13 16-Apr-13 51 PermenanetPermenanet Power Connection 0 04-Jul-13 04-Jul-13 04-Jul-13 04-Jul-13 0 A1528 Release of Permanent Power By DEWA 0 04-Jul-13 04-Jul-13 0 Client SubmClient Submissions 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43 Awarding ofAwarding of Provisional Sum Packages 215 15-Apr-12 30-Dec-12 29-Apr-12 20-Feb-13 43 A1456 Awarding of Kitchen Equipments Package to ASGC 0 15-Apr-12 30-Apr-12 13 A1466 Awarding of Laundry Equipments Package to ASGC 0 15-Apr-12 29-Apr-12 12 A1476 Awarding of Facade Lighting Package to ASGC 0 21-Apr-12 14-May-12 20 A1489 Awarding of Cooking StationPackage to ASGC 0 30-Apr-12 14-Aug-12 90 A1486 Awarding of Gymnasium Equipments Package to ASGC 0 30-Dec-12 20-Feb-13 43 Technical DTechnical Data for Prime Cost Items 134 23-May-12 31-Oct-12 23-Sep-12 02-Feb-13 76 A1257 Submit the Techincal Data for Porcalin Tiles 7 23-May-12 30-May-12 23-Sep-12 30-Sep-12 102 A1247 Submit the Techincal Data for Ironmongery 7 24-Jul-12 31-Jul-12 10-Jan-13 17-Jan-13 139 A1277 Submit the Techincal Data for Wooden Parquet 7 24-Jul-12 31-Jul-12 19-Dec-12 26-Dec-12 121 A1267 Submit the Techincal Data for Carpet 7 23-Sep-12 30-Sep-12 15-Dec-12 22-Dec-12 67 A1287 Submit the Techincal Data for Kitchen Appliances 7 22-Oct-12 31-Oct-12 26-Jan-13 02-Feb-13 76 MobilizationMobilization 121 02-Jan-12 22-May-12 22-Jan-12 06-Jun-12 13 Project SiteProject Site 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17 A8950 Installation of Site Gate 5 02-Jan-12 07-Jan-12 02-Feb-12 08-Feb-12 27 A5490 Installation of Project Signboard 6 02-Jan-12 08-Jan-12 01-Feb-12 08-Feb-12 26 A5460 Installation of Generator 7 02-Jan-12 09-Jan-12 23-Jan-12 30-Jan-12 18 A5410 Installation of Fence 8 02-Jan-12 10-Jan-12 30-Jan-12 08-Feb-12 24 A5480 Installation of Store Yard 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22 A8920 Installation of Workshop 10 02-Jan-12 12-Jan-12 28-Jan-12 08-Feb-12 22 A5470 Installation of Septic Tank & Water Tank 7 10-Jan-12 17-Jan-12 31-Jan-12 08-Feb-12 18 A5450 Installation of Site Offices 15 02-Jan-12 18-Jan-12 22-Jan-12 08-Feb-12 17 Tower CraneTower Cranes 85 14-Feb-12 22-May-12 05-Mar-12 06-Jun-12 13 A5420 Installation of Tower Crane 1 12 14-Feb-12 27-Feb-12 05-Mar-12 18-Mar-12 17 A5467 Installation of Tower Crane 4 12 22-Feb-12 06-Mar-12 28-Apr-12 10-May-12 56 A5430 Installation of Tower Crane 2 12 28-Apr-12 10-May-12 24-May-12 06-Jun-12 23 A5440 Installation of Tower Crane 3 12 09-May-12 22-May-12 24-May-12 06-Jun-12 13 EngineerinEngineering 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19 Shop DrawinShop Drawings 463 02-Jan-12 07-Jul-13 02-Jan-12 29-Jul-13 19 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Project Commencement Date Completion Date of Phase 1 Overall Duration of Phase 1 Completion Date Overall Duration Completion of Raft Slab (Block A,B,C) Completion of Ground Floor Slab (Block A,B,C) Completion of the Skeleton for Block A Completion of the Skeleton for Block C Completion of the Skeleton for Block B Start of Block Works @ Basements Start of Block Works @ 1st Floor Completion of Fit Out for Block C Completion of Fit Out for Block A Completion of Fit Out for Block B Commencement of FF&E @ Block Commencement of FF&E @ Block Commencement of FF&E @ Block Completion of LPG System Completion of MEP Works ( Related to Temporary Power) Completion of Elevators Completion of Garbage & Linen Chute Completion of Facade Cleaning System Completion of Facade Glazing Completion of Facade Lighting Syste EHS Approval for Pouring Pools Slab - Block B EHS Approval for Pouring Pools Slab - Block A EHS Approval for Pouring Pools Slab - Block C Receipt of Design NOC for Electrical Drawings Confirmation of RMU & Transformers Rooms Layout Submission & Approval of Electrical Drawings Application for Fee Estimation Fee Payment by Client to DEWA Substation Inspection Invitation to DEWA Civil Work Inspection by DEWA Approval & Handover Substations to DEWA Delivery- Installation - Termination of Transformers - RMU Invitation to DEWA for MEP Work Inspection 1st MEP Inspection & Comments by DEWA Attend DEWA Comments Final MEP Inspection & Approval By DEWA Release DEWA Temporary Power for T & C Gas Supply Connection Water Supply Connection Sewage Connection Release of Permanent Power By D Awarding of Kitchen Equipments Package to ASGC Awarding of Laundry Equipments Package to ASGC Awarding of Facade Lighting Package to ASGC Awarding of Cooking StationPackage to ASGC Awarding of Gymnasium Equipments Package to ASGC Submit the Techincal Data for Porcalin Tiles Submit the Techincal Data for Ironmongery Submit the Techincal Data for Wooden Parquet Submit the Techincal Data for Carpet Submit the Techincal Data for Kitchen Appliances Installation of Site Gate Installation of Project Signboard Installation of Generator Installation of Fence Installation of Store Yard Installation of Workshop Installation of Septic Tank & Water Tank Installation of Site Offices Installation of Tower Crane 1 Installation of Tower Crane 4 Installation of Tower Crane 2 Installation of Tower Crane 3 Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 1 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 2. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float CivilCivil 296 02-Jan-12 20-Dec-12 02-Jan-12 23-May-13 130 GeneralGeneral 35 02-Jan-12 12-Feb-12 02-Jan-12 04-Mar-12 18 SubmissionSubmission 19 02-Jan-12 23-Jan-12 02-Jan-12 13-Feb-12 17 A46740 Submission of Excavation Level 1 02-Jan-12 02-Jan-12 02-Jan-12 02-Jan-12 0 A46770 Submission of Raft Construction Joint Layout 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0 A46750 Submission of Water Proofing Details 7 02-Jan-12 09-Jan-12 02-Jan-12 09-Jan-12 0 A46760 Submission of Tower Crane Layout 7 10-Jan-12 17-Jan-12 06-Feb-12 13-Feb-12 22 A46780 Submission of Retaining Wall Joint Layout 7 16-Jan-12 23-Jan-12 18-Jan-12 25-Jan-12 2 ApprovalApproval 29 03-Jan-12 12-Feb-12 03-Jan-12 04-Mar-12 15 A117180 Approval of Excavation Level 1 03-Jan-12 03-Jan-12 03-Jan-12 03-Jan-12 0 A117190 Approval of Water Proofing Details 7 10-Jan-12 18-Jan-12 10-Jan-12 18-Jan-12 0 A117210 Approval of Raft Construction Joint Layout 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0 A117200 Approval of Tower Crane Layout 14 18-Jan-12 06-Feb-12 14-Feb-12 04-Mar-12 19 A117220 Approval of Retaining Wall Joint Layout 14 24-Jan-12 12-Feb-12 26-Jan-12 14-Feb-12 2 Hotel ApartemHotel Apartements (Block A) 219 02-Jan-12 17-Sep-12 02-Jan-12 23-May-13 207 Deep FoundDeep Foundation 20 02-Jan-12 24-Jan-12 02-Jan-12 24-Jan-12 0 SubmissionSubmission 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0 A46720 Submission of Structural Dwgs. for Raft 3 02-Jan-12 04-Jan-12 02-Jan-12 04-Jan-12 0 ApprovalApproval 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0 A46730 Approval of Structural Dwgs. for Raft 14 05-Jan-12 24-Jan-12 05-Jan-12 24-Jan-12 0 1st Baseme1st Basement Floor Slab 60 11-Jan-12 21-Mar-12 15-Jan-12 06-Sep-12 142 SubmissionSubmission 44 11-Jan-12 03-Mar-12 15-Jan-12 15-Aug-12 141 A101070 Submission of Structural Dwgs. for Ret. Walls -Columns 7 11-Jan-12 18-Jan-12 15-Jan-12 22-Jan-12 3 A101080 Submission of Structural Dwgs. for Core Walls 7 16-Jan-12 23-Jan-12 21-Jan-12 28-Jan-12 4 A101060 Submission of Structural Dwgs. for Slab 7 19-Jan-12 26-Jan-12 23-Jan-12 30-Jan-12 3 A101090 Submission of Structural Dwgs. for Ramp 7 19-Jan-12 26-Jan-12 29-Jan-12 06-Feb-12 8 A101140 Submission of Structural Dwgs. for Staircase 7 25-Feb-12 03-Mar-12 08-Aug-12 15-Aug-12 141 ApprovalApproval 45 19-Jan-12 21-Mar-12 26-Jan-12 06-Sep-12 118 A101110 Approval of Structural Dwgs. for Ret. Walls -Columns 14 19-Jan-12 07-Feb-12 26-Jan-12 14-Feb-12 5 A101120 Approval of Structural Dwgs. for Core Walls 14 24-Jan-12 12-Feb-12 29-Jan-12 15-Feb-12 3 A101100 Approval of Structural Dwgs. for Slab 14 29-Jan-12 15-Feb-12 31-Jan-12 19-Feb-12 2 A101130 Approval of Structural Dwgs. for Ramp 14 29-Jan-12 15-Feb-12 07-Feb-12 26-Feb-12 7 A101150 Approval of Structural Dwgs. for Staircase 14 04-Mar-12 21-Mar-12 16-Aug-12 06-Sep-12 118 Ground FloGround Floor Slab 66 31-Jan-12 17-Apr-12 06-Feb-12 11-Sep-12 123 SubmissionSubmission 49 31-Jan-12 28-Mar-12 06-Feb-12 22-Aug-12 123 A101170 Submission of Structural Dwgs. for Ret. Walls -Columns 7 31-Jan-12 08-Feb-12 06-Feb-12 13-Feb-12 4 A101180 Submission of Structural Dwgs. for Core Walls 7 31-Jan-12 08-Feb-12 15-Feb-12 22-Feb-12 12 A102200 Submission of Structural Dwgs. for Ramp 7 07-Feb-12 14-Feb-12 26-Feb-12 04-Mar-12 16 A101160 Submission of Structural Dwgs. for Slab 7 15-Feb-12 22-Feb-12 20-Feb-12 27-Feb-12 4 A101240 Submission of Structural Dwgs. for Staircase 7 21-Mar-12 28-Mar-12 13-Aug-12 22-Aug-12 123 ApprovalApproval 49 09-Feb-12 17-Apr-12 22-Feb-12 11-Sep-12 102 A101210 Approval of Structural Dwgs. for Ret. Walls -Columns 14 09-Feb-12 28-Feb-12 22-Feb-12 12-Mar-12 9 A101220 Approval of Structural Dwgs. for Core Walls 14 09-Feb-12 28-Feb-12 23-Feb-12 13-Mar-12 10 A102210 Approval of Structural Dwgs. for Ramp 14 15-Feb-12 05-Mar-12 05-Mar-12 22-Mar-12 13 A101200 Approval of Structural Dwgs. for Slab 14 23-Feb-12 13-Mar-12 28-Feb-12 18-Mar-12 3 A101250 Approval of Structural Dwgs. for Staircase 14 29-Mar-12 17-Apr-12 23-Aug-12 11-Sep-12 102 1st Floor Sl1st Floor Slab 61 04-Mar-12 13-May-12 11-Mar-12 13-Sep-12 103 SubmissionSubmission 44 04-Mar-12 23-Apr-12 11-Mar-12 26-Aug-12 104 A101270 Submission of Structural Dwgs. for Columns 7 04-Mar-12 11-Mar-12 11-Mar-12 18-Mar-12 6 A101280 Submission of Structural Dwgs. for Core Walls 7 04-Mar-12 11-Mar-12 11-Mar-12 18-Mar-12 6 A101260 Submission of Structural Dwgs. for Slab 7 12-Mar-12 19-Mar-12 19-Mar-12 26-Mar-12 6 A101340 Submission of Structural Dwgs. for Staircase 7 16-Apr-12 23-Apr-12 16-Aug-12 26-Aug-12 104 ApprovalApproval 45 12-Mar-12 13-May-12 21-Mar-12 13-Sep-12 86 A101310 Approval of Structural Dwgs. for Columns 14 12-Mar-12 29-Mar-12 21-Mar-12 09-Apr-12 7 A101320 Approval of Structural Dwgs. for Core Walls 14 12-Mar-12 29-Mar-12 21-Mar-12 09-Apr-12 7 A101300 Approval of Structural Dwgs. for Slab 14 20-Mar-12 08-Apr-12 27-Mar-12 15-Apr-12 5 A101350 Approval of Structural Dwgs. for Staircase 14 24-Apr-12 13-May-12 27-Aug-12 13-Sep-12 86 2nd Floor S2nd Floor Slab 60 24-Mar-12 31-May-12 02-Apr-12 25-Sep-12 97 SubmissionSubmission 44 24-Mar-12 13-May-12 02-Apr-12 05-Sep-12 96 A102230 Submission of Structural Dwgs. for Columns 7 24-Mar-12 31-Mar-12 02-Apr-12 09-Apr-12 8 A102240 Submission of Structural Dwgs. for Core Walls 7 24-Mar-12 31-Mar-12 08-Apr-12 15-Apr-12 13 A102220 Submission of Structural Dwgs. for Slab 7 01-Apr-12 08-Apr-12 16-Apr-12 23-Apr-12 13 A102280 Submission of Structural Dwgs. for Staircase 7 06-May-12 13-May-12 29-Aug-12 05-Sep-12 96 ApprovalApproval 45 01-Apr-12 31-May-12 18-Apr-12 25-Sep-12 80 A102260 Approval of Structural Dwgs. for Columns 14 01-Apr-12 18-Apr-12 18-Apr-12 07-May-12 13 A102270 Approval of Structural Dwgs. for Core Walls 14 01-Apr-12 18-Apr-12 18-Apr-12 07-May-12 13 A102250 Approval of Structural Dwgs. for Slab 14 09-Apr-12 26-Apr-12 24-Apr-12 13-May-12 11 A102290 Approval of Structural Dwgs. for Staircase 14 14-May-12 31-May-12 06-Sep-12 25-Sep-12 80 3rd & 4th Fl3rd & 4th Floor Slab 61 18-Apr-12 28-Jun-12 28-Apr-12 02-Oct-12 80 SubmissionSubmission 44 18-Apr-12 07-Jun-12 28-Apr-12 12-Sep-12 80 A101370 Submission of Structural Dwgs. for Columns 7 18-Apr-12 25-Apr-12 28-Apr-12 05-May-12 8 A101380 Submission of Structural Dwgs. for Core Walls 7 18-Apr-12 25-Apr-12 05-May-12 12-May-12 14 A101360 Submission of Structural Dwgs. for Slab 7 26-Apr-12 03-May-12 13-May-12 20-May-12 14 A101440 Submission of Structural Dwgs. for Staircase 7 31-May-12 07-Jun-12 05-Sep-12 12-Sep-12 80 ApprovalApproval 45 26-Apr-12 28-Jun-12 16-May-12 02-Oct-12 66 A101410 Approval of Structural Dwgs. for Columns 14 26-Apr-12 15-May-12 16-May-12 04-Jun-12 14 A101420 Approval of Structural Dwgs. for Core Walls 14 26-Apr-12 15-May-12 16-May-12 04-Jun-12 14 A101400 Approval of Structural Dwgs. for Slab 14 06-May-12 23-May-12 21-May-12 07-Jun-12 11 A101450 Approval of Structural Dwgs. for Staircase 14 10-Jun-12 28-Jun-12 13-Sep-12 02-Oct-12 66 5th & 6th Fl5th & 6th Floor Slab 60 31-May-12 09-Aug-12 10-Jun-12 16-Oct-12 56 SubmissionSubmission 44 31-May-12 22-Jul-12 10-Jun-12 26-Sep-12 55 A102390 Submission of Structural Dwgs. for Columns 7 31-May-12 07-Jun-12 10-Jun-12 18-Jun-12 8 A102400 Submission of Structural Dwgs. for Core Walls 7 31-May-12 07-Jun-12 10-Jun-12 18-Jun-12 8 A102380 Submission of Structural Dwgs. for Slab 7 09-Jun-12 16-Jun-12 19-Jun-12 26-Jun-12 8 A102440 Submission of Structural Dwgs. for Staircase 7 15-Jul-12 22-Jul-12 19-Sep-12 26-Sep-12 55 ApprovalApproval 44 10-Jun-12 09-Aug-12 25-Jun-12 16-Oct-12 46 A102420 Approval of Structural Dwgs. for Columns 14 10-Jun-12 28-Jun-12 25-Jun-12 12-Jul-12 10 A102430 Approval of Structural Dwgs. for Core Walls 14 10-Jun-12 28-Jun-12 25-Jun-12 12-Jul-12 10 A102410 Approval of Structural Dwgs. for Slab 14 18-Jun-12 05-Jul-12 27-Jun-12 16-Jul-12 7 A102450 Approval of Structural Dwgs. for Staircase 14 23-Jul-12 09-Aug-12 27-Sep-12 16-Oct-12 46 7th Floor Sl7th Floor Slab 51 27-Jun-12 27-Aug-12 12-Jul-12 04-Nov-12 57 SubmissionSubmission 34 27-Jun-12 05-Aug-12 12-Jul-12 14-Oct-12 58 A102470 Submission of Structural Dwgs. for Columns 7 27-Jun-12 04-Jul-12 12-Jul-12 19-Jul-12 13 A102480 Submission of Structural Dwgs. for Core Walls 7 27-Jun-12 04-Jul-12 14-Jul-12 21-Jul-12 14 A102460 Submission of Structural Dwgs. for Slab 7 05-Jul-12 12-Jul-12 22-Jul-12 29-Jul-12 14 A102520 Submission of Structural Dwgs. for Staircase 7 29-Jul-12 05-Aug-12 07-Oct-12 14-Oct-12 58 ApprovalApproval 36 05-Jul-12 27-Aug-12 24-Jul-12 04-Nov-12 48 A102500 Approval of Structural Dwgs. for Columns 14 05-Jul-12 24-Jul-12 24-Jul-12 12-Aug-12 13 A102510 Approval of Structural Dwgs. for Core Walls 14 05-Jul-12 24-Jul-12 24-Jul-12 12-Aug-12 13 A102490 Approval of Structural Dwgs. for Slab 14 15-Jul-12 01-Aug-12 30-Jul-12 16-Aug-12 11 A102530 Approval of Structural Dwgs. for Staircase 14 06-Aug-12 27-Aug-12 15-Oct-12 04-Nov-12 48 Roof FloorRoof Floor Slab 45 14-Jul-12 05-Sep-12 29-Jul-12 23-May-13 217 SubmissionSubmission 28 14-Jul-12 14-Aug-12 29-Jul-12 05-May-13 218 A101470 Submission of Structural Dwgs. for Columns 7 14-Jul-12 21-Jul-12 29-Jul-12 05-Aug-12 13 A101480 Submission of Structural Dwgs. for Core Walls 7 14-Jul-12 21-Jul-12 30-Jul-12 06-Aug-12 14 A101460 Submission of Structural Dwgs. for Slab 7 22-Jul-12 29-Jul-12 07-Aug-12 14-Aug-12 14 A101540 Submission of Structural Dwgs. for Staircase 7 22-Jul-12 29-Jul-12 10-Nov-12 18-Nov-12 91 A117120 Submission of Structural Dwgs. for Chillers Foundations 14 22-Jul-12 06-Aug-12 04-Oct-12 20-Oct-12 62 A117020 Submission of Structural Dwgs. for Parapets 14 30-Jul-12 14-Aug-12 20-Apr-13 05-May-13 218 ApprovalApproval 32 22-Jul-12 05-Sep-12 08-Aug-12 23-May-13 181 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Submission of Excavation Level Submission of Raft Construction Joint Layout Submission of Water Proofing Details Submission of Tower Crane Layout Submission of Retaining Wall Joint Layout Approval of Excavation Level Approval of Water Proofing Details Approval of Raft Construction Joint Layout Approval of Tower Crane Layout Approval of Retaining Wall Joint Layout Submission of Structural Dwgs. for Raft Approval of Structural Dwgs. for Raft Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Ramp Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Ramp Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Ramp Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Ramp Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Chillers Foundations Submission of Structural Dwgs. for Parapets Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 2 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 3. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A101510 Approval of Structural Dwgs. for Columns 14 22-Jul-12 08-Aug-12 12-Aug-12 02-Sep-12 15 A101520 Approval of Structural Dwgs. for Core Walls 14 22-Jul-12 08-Aug-12 08-Aug-12 29-Aug-12 13 A101500 Approval of Structural Dwgs. for Slab 14 30-Jul-12 16-Aug-12 15-Aug-12 05-Sep-12 12 A101550 Approval of Structural Dwgs. for Staircase 14 30-Jul-12 16-Aug-12 19-Nov-12 09-Dec-12 76 A117130 Approval of Structural Dwgs. for Chillers Foundations 14 07-Aug-12 28-Aug-12 21-Oct-12 08-Nov-12 51 A117010 Approval of Structural Dwgs. for Parapets 14 15-Aug-12 05-Sep-12 06-May-13 23-May-13 181 Upper RoofUpper Roof Floor Slab 40 31-Jul-12 17-Sep-12 15-Aug-12 13-Feb-13 122 SubmissionSubmission 23 31-Jul-12 28-Aug-12 15-Aug-12 26-Jan-13 123 A101570 Submission of Structural Dwgs. for Columns 7 31-Jul-12 07-Aug-12 15-Aug-12 25-Aug-12 13 A101560 Submission of Structural Dwgs. for Slab 7 08-Aug-12 15-Aug-12 26-Aug-12 02-Sep-12 13 A101640 Submission of Structural Dwgs. for Staircase 7 21-Aug-12 28-Aug-12 17-Jan-13 26-Jan-13 123 ApprovalApproval 27 08-Aug-12 17-Sep-12 28-Aug-12 13-Feb-13 102 A101610 Approval of Structural Dwgs. for Columns 14 08-Aug-12 29-Aug-12 28-Aug-12 16-Sep-12 12 A101600 Approval of Structural Dwgs. for Slab 14 16-Aug-12 06-Sep-12 03-Sep-12 20-Sep-12 10 A101650 Approval of Structural Dwgs. for Staircase 14 29-Aug-12 17-Sep-12 27-Jan-13 13-Feb-13 102 Hotel (BlockHotel (Block B) 270 01-Feb-12 20-Dec-12 15-Feb-12 23-May-13 130 Deep FoundDeep Foundation 24 01-Feb-12 29-Feb-12 15-Feb-12 12-Apr-12 37 SubmissionSubmission 7 01-Feb-12 09-Feb-12 15-Feb-12 22-Feb-12 11 A102540 Submission of Structural Dwgs. for Raft 7 01-Feb-12 09-Feb-12 15-Feb-12 22-Feb-12 11 ApprovalApproval 14 12-Feb-12 29-Feb-12 26-Mar-12 12-Apr-12 31 A102550 Approval of Structural Dwgs. for Raft 14 12-Feb-12 29-Feb-12 26-Mar-12 12-Apr-12 31 1st Baseme1st Basement Floor Slab 67 22-Feb-12 09-May-12 06-Mar-12 17-Jan-13 209 SubmissionSubmission 51 22-Feb-12 21-Apr-12 06-Mar-12 29-Dec-12 209 A102570 Submission of Structural Dwgs. for Ret. Walls -Columns 7 22-Feb-12 29-Feb-12 06-Mar-12 13-Mar-12 11 A102580 Submission of Structural Dwgs. for Core Walls 7 22-Feb-12 29-Feb-12 07-Apr-12 14-Apr-12 38 A104100 Submission of Structural Dwgs. for Water Tank 7 25-Feb-12 03-Mar-12 09-Apr-12 16-Apr-12 38 A102590 Submission of Structural Dwgs. for Ramp 7 01-Mar-12 08-Mar-12 07-Apr-12 14-Apr-12 31 A102560 Submission of Structural Dwgs. for Slab 7 10-Mar-12 17-Mar-12 15-Apr-12 22-Apr-12 31 A102640 Submission of Structural Dwgs. for Staircase 7 14-Apr-12 21-Apr-12 22-Dec-12 29-Dec-12 209 ApprovalApproval 50 01-Mar-12 09-May-12 16-Apr-12 17-Jan-13 174 A102610 Approval of Structural Dwgs. for Ret. Walls -Columns 14 01-Mar-12 20-Mar-12 16-Apr-12 03-May-12 32 A102620 Approval of Structural Dwgs. for Core Walls 14 01-Mar-12 20-Mar-12 18-Apr-12 07-May-12 34 A104110 Approval of Structural Dwgs. for Water Tank 14 04-Mar-12 21-Mar-12 17-Apr-12 06-May-12 32 A102630 Approval of Structural Dwgs. for Ramp 14 11-Mar-12 28-Mar-12 01-May-12 20-May-12 37 A102600 Approval of Structural Dwgs. for Slab 14 18-Mar-12 04-Apr-12 23-Apr-12 10-May-12 26 A102650 Approval of Structural Dwgs. for Staircase 14 22-Apr-12 09-May-12 30-Dec-12 17-Jan-13 174 Ground FloGround Floor Slab 66 17-Apr-12 03-Jul-12 30-Apr-12 23-Jan-13 168 SubmissionSubmission 49 17-Apr-12 12-Jun-12 30-Apr-12 05-Jan-13 169 A102670 Submission of Structural Dwgs. for Ret. Walls -Columns 7 17-Apr-12 24-Apr-12 30-Apr-12 07-May-12 11 A102680 Submission of Structural Dwgs. for Core Walls 7 17-Apr-12 24-Apr-12 03-May-12 10-May-12 14 A103060 Submission of Structural Dwgs. for Ramp 7 17-Apr-12 24-Apr-12 20-May-12 27-May-12 28 A102660 Submission of Structural Dwgs. for Slab 7 25-Apr-12 02-May-12 12-May-12 19-May-12 14 A102720 Submission of Structural Dwgs. for Staircase 7 05-Jun-12 12-Jun-12 27-Dec-12 05-Jan-13 169 ApprovalApproval 49 25-Apr-12 03-Jul-12 14-May-12 23-Jan-13 140 A102700 Approval of Structural Dwgs. for Ret. Walls -Columns 14 25-Apr-12 14-May-12 14-May-12 31-May-12 13 A102710 Approval of Structural Dwgs. for Core Walls 14 25-Apr-12 14-May-12 15-May-12 03-Jun-12 14 A103070 Approval of Structural Dwgs. for Ramp 14 25-Apr-12 14-May-12 28-May-12 14-Jun-12 23 A102690 Approval of Structural Dwgs. for Slab 14 03-May-12 22-May-12 20-May-12 06-Jun-12 11 A102730 Approval of Structural Dwgs. for Staircase 14 13-Jun-12 03-Jul-12 06-Jan-13 23-Jan-13 140 1st Floor Sl1st Floor Slab 70 13-May-12 02-Aug-12 26-May-12 18-Feb-13 163 SubmissionSubmission 54 13-May-12 15-Jul-12 26-May-12 29-Jan-13 162 A102750 Submission of Structural Dwgs. for Columns 7 13-May-12 20-May-12 26-May-12 02-Jun-12 11 A102760 Submission of Structural Dwgs. for Core Walls 7 13-May-12 20-May-12 31-May-12 07-Jun-12 16 A102740 Submission of Structural Dwgs. for Slab 7 21-May-12 28-May-12 09-Jun-12 16-Jun-12 16 A102800 Submission of Structural Dwgs. for Staircase 7 08-Jul-12 15-Jul-12 21-Jan-13 29-Jan-13 162 ApprovalApproval 53 21-May-12 02-Aug-12 11-Jun-12 18-Feb-13 135 A102780 Approval of Structural Dwgs. for Columns 14 21-May-12 07-Jun-12 11-Jun-12 01-Jul-12 15 A102790 Approval of Structural Dwgs. for Core Walls 14 21-May-12 07-Jun-12 11-Jun-12 01-Jul-12 15 A102770 Approval of Structural Dwgs. for Slab 14 29-May-12 18-Jun-12 18-Jun-12 05-Jul-12 13 A102810 Approval of Structural Dwgs. for Staircase 14 16-Jul-12 02-Aug-12 30-Jan-13 18-Feb-13 135 2nd Floor S2nd Floor Slab 81 07-Jun-12 12-Sep-12 21-Jun-12 18-Feb-13 130 SubmissionSubmission 64 07-Jun-12 23-Aug-12 21-Jun-12 29-Jan-13 130 A103090 Submission of Structural Dwgs. for Columns 7 07-Jun-12 14-Jun-12 21-Jun-12 28-Jun-12 11 A103100 Submission of Structural Dwgs. for Core Walls 7 07-Jun-12 14-Jun-12 23-Jun-12 30-Jun-12 12 A103080 Submission of Structural Dwgs. for Slab 7 16-Jun-12 24-Jun-12 01-Jul-12 08-Jul-12 12 A103140 Submission of Structural Dwgs. for Staircase 7 14-Aug-12 23-Aug-12 21-Jan-13 29-Jan-13 130 ApprovalApproval 61 18-Jun-12 12-Sep-12 04-Jul-12 18-Feb-13 108 A103120 Approval of Structural Dwgs. for Columns 14 18-Jun-12 05-Jul-12 04-Jul-12 23-Jul-12 12 A103130 Approval of Structural Dwgs. for Core Walls 14 18-Jun-12 05-Jul-12 04-Jul-12 23-Jul-12 12 A103110 Approval of Structural Dwgs. for Slab 14 25-Jun-12 12-Jul-12 09-Jul-12 26-Jul-12 10 A103150 Approval of Structural Dwgs. for Staircase 14 26-Aug-12 12-Sep-12 30-Jan-13 18-Feb-13 108 3rd & 4th Fl3rd & 4th Floor Slab 81 04-Jul-12 08-Oct-12 17-Jul-12 27-Jan-13 89 SubmissionSubmission 64 04-Jul-12 18-Sep-12 17-Jul-12 06-Jan-13 89 A102830 Submission of Structural Dwgs. for Columns 7 04-Jul-12 11-Jul-12 17-Jul-12 24-Jul-12 11 A102840 Submission of Structural Dwgs. for Core Walls 7 04-Jul-12 11-Jul-12 17-Jul-12 24-Jul-12 11 A102820 Submission of Structural Dwgs. for Slab 7 12-Jul-12 19-Jul-12 25-Jul-12 01-Aug-12 11 A102880 Submission of Structural Dwgs. for Staircase 7 11-Sep-12 18-Sep-12 29-Dec-12 06-Jan-13 89 ApprovalApproval 61 12-Jul-12 08-Oct-12 30-Jul-12 27-Jan-13 74 A102860 Approval of Structural Dwgs. for Columns 14 12-Jul-12 31-Jul-12 30-Jul-12 16-Aug-12 12 A102870 Approval of Structural Dwgs. for Core Walls 14 12-Jul-12 31-Jul-12 30-Jul-12 16-Aug-12 12 A102850 Approval of Structural Dwgs. for Slab 14 22-Jul-12 08-Aug-12 02-Aug-12 23-Aug-12 9 A102890 Approval of Structural Dwgs. for Staircase 14 19-Sep-12 08-Oct-12 07-Jan-13 27-Jan-13 74 5th & 6th Fl5th & 6th Floor Slab 80 30-Jul-12 04-Nov-12 12-Aug-12 22-Jan-13 65 SubmissionSubmission 64 30-Jul-12 14-Oct-12 12-Aug-12 02-Jan-13 64 A103170 Submission of Structural Dwgs. for Columns 7 30-Jul-12 06-Aug-12 12-Aug-12 21-Aug-12 11 A103180 Submission of Structural Dwgs. for Core Walls 7 30-Jul-12 06-Aug-12 14-Aug-12 23-Aug-12 13 A103160 Submission of Structural Dwgs. for Slab 7 07-Aug-12 14-Aug-12 25-Aug-12 01-Sep-12 13 A103220 Submission of Structural Dwgs. for Staircase 7 07-Oct-12 14-Oct-12 25-Dec-12 02-Jan-13 64 ApprovalApproval 61 07-Aug-12 04-Nov-12 28-Aug-12 22-Jan-13 54 A103200 Approval of Structural Dwgs. for Columns 14 07-Aug-12 28-Aug-12 28-Aug-12 16-Sep-12 13 A103210 Approval of Structural Dwgs. for Core Walls 14 07-Aug-12 28-Aug-12 28-Aug-12 16-Sep-12 13 A103190 Approval of Structural Dwgs. for Slab 14 15-Aug-12 05-Sep-12 02-Sep-12 19-Sep-12 10 A103230 Approval of Structural Dwgs. for Staircase 14 15-Oct-12 04-Nov-12 03-Jan-13 22-Jan-13 54 7th Floor Sl7th Floor Slab 86 27-Aug-12 09-Dec-12 09-Sep-12 22-Jan-13 37 SubmissionSubmission 69 27-Aug-12 18-Nov-12 09-Sep-12 02-Jan-13 37 A103250 Submission of Structural Dwgs. for Columns 7 27-Aug-12 03-Sep-12 09-Sep-12 16-Sep-12 11 A103260 Submission of Structural Dwgs. for Core Walls 7 27-Aug-12 03-Sep-12 15-Sep-12 22-Sep-12 16 A103240 Submission of Structural Dwgs. for Slab 7 04-Sep-12 11-Sep-12 23-Sep-12 30-Sep-12 16 A103300 Submission of Structural Dwgs. for Staircase 7 10-Nov-12 18-Nov-12 25-Dec-12 02-Jan-13 37 ApprovalApproval 66 04-Sep-12 09-Dec-12 24-Sep-12 22-Jan-13 31 A103280 Approval of Structural Dwgs. for Columns 14 04-Sep-12 23-Sep-12 26-Sep-12 15-Oct-12 16 A103290 Approval of Structural Dwgs. for Core Walls 14 04-Sep-12 23-Sep-12 24-Sep-12 11-Oct-12 14 A103270 Approval of Structural Dwgs. for Slab 14 12-Sep-12 01-Oct-12 01-Oct-12 18-Oct-12 13 A103310 Approval of Structural Dwgs. for Staircase 14 19-Nov-12 09-Dec-12 03-Jan-13 22-Jan-13 31 Roof FloorRoof Floor Slab 79 16-Sep-12 20-Dec-12 29-Sep-12 23-May-13 130 SubmissionSubmission 71 16-Sep-12 11-Dec-12 29-Sep-12 14-May-13 130 A102910 Submission of Structural Dwgs. for Columns 7 16-Sep-12 23-Sep-12 29-Sep-12 06-Oct-12 11 A102900 Submission of Structural Dwgs. for Slab 7 24-Sep-12 01-Oct-12 07-Oct-12 14-Oct-12 11 A102960 Submission of Structural Dwgs. for Staircase 7 24-Sep-12 01-Oct-12 25-Dec-12 02-Jan-13 75 A117150 Submission of Structural Dwgs. for Chillers Foundations 14 30-Sep-12 15-Oct-12 13-Oct-12 30-Oct-12 11 A117030 Submission of Structural Dwgs. for Parapets 7 04-Dec-12 11-Dec-12 07-May-13 14-May-13 130 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Chillers Foundations Approval of Structural Dwgs. for Parapets Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Raft Approval of Structural Dwgs. for Raft Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Water Tank Submission of Structural Dwgs. for Ramp Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Water Tank Approval of Structural Dwgs. for Ramp Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Ramp Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Ramp Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Chillers Foundations Submission of Structural Dwgs. for Parapets Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 3 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 4. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float ApprovalApproval 61 24-Sep-12 20-Dec-12 14-Oct-12 23-May-13 108 A102940 Approval of Structural Dwgs. for Columns 14 24-Sep-12 11-Oct-12 14-Oct-12 01-Nov-12 14 A102930 Approval of Structural Dwgs. for Slab 14 02-Oct-12 21-Oct-12 16-Oct-12 05-Nov-12 10 A102970 Approval of Structural Dwgs. for Staircase 14 02-Oct-12 21-Oct-12 03-Jan-13 22-Jan-13 63 A117140 Approval of Structural Dwgs. for Chillers Foundations 14 16-Oct-12 05-Nov-12 31-Oct-12 20-Nov-12 10 A117040 Approval of Structural Dwgs. for Parapets 7 12-Dec-12 20-Dec-12 15-May-13 23-May-13 108 Upper RoofUpper Roof Floor Slab 30 30-Sep-12 05-Nov-12 13-Oct-12 20-Nov-12 12 SubmissionSubmission 14 30-Sep-12 15-Oct-12 13-Oct-12 30-Oct-12 11 A102990 Submission of Structural Dwgs. for Columns 7 30-Sep-12 07-Oct-12 13-Oct-12 20-Oct-12 11 A102980 Submission of Structural Dwgs. for Slab 7 08-Oct-12 15-Oct-12 21-Oct-12 30-Oct-12 11 ApprovalApproval 20 08-Oct-12 05-Nov-12 28-Oct-12 20-Nov-12 10 A103020 Approval of Structural Dwgs. for Columns 14 08-Oct-12 28-Oct-12 28-Oct-12 14-Nov-12 13 A103010 Approval of Structural Dwgs. for Slab 14 16-Oct-12 05-Nov-12 31-Oct-12 20-Nov-12 10 Residentail (BResidentail (Block C) 260 02-Jan-12 06-Nov-12 14-Jan-12 23-May-13 166 Deep FoundDeep Foundation 24 02-Jan-12 29-Jan-12 14-Jan-12 08-Feb-12 8 SubmissionSubmission 7 02-Jan-12 09-Jan-12 14-Jan-12 21-Jan-12 10 A103320 Submission of Structural Dwgs. for Raft 7 02-Jan-12 09-Jan-12 14-Jan-12 21-Jan-12 10 ApprovalApproval 14 10-Jan-12 29-Jan-12 22-Jan-12 08-Feb-12 8 A103330 Approval of Structural Dwgs. for Raft 14 10-Jan-12 29-Jan-12 22-Jan-12 08-Feb-12 8 1st Baseme1st Basement Floor Slab 60 19-Jan-12 29-Mar-12 13-Feb-12 17-Jan-13 244 SubmissionSubmission 44 19-Jan-12 11-Mar-12 13-Feb-12 29-Dec-12 244 A103350 Submission of Structural Dwgs. for Ret. Walls -Columns 7 19-Jan-12 26-Jan-12 13-Feb-12 20-Feb-12 20 A103360 Submission of Structural Dwgs. for Core Walls 7 19-Jan-12 26-Jan-12 22-Feb-12 29-Feb-12 28 A103370 Submission of Structural Dwgs. for Water Tank 7 19-Jan-12 26-Jan-12 22-Feb-12 29-Feb-12 28 A103340 Submission of Structural Dwgs. for Slab 7 28-Jan-12 05-Feb-12 05-Mar-12 12-Mar-12 31 A103420 Submission of Structural Dwgs. for Staircase 7 04-Mar-12 11-Mar-12 22-Dec-12 29-Dec-12 244 ApprovalApproval 45 29-Jan-12 29-Mar-12 01-Mar-12 17-Jan-13 203 A103390 Approval of Structural Dwgs. for Ret. Walls -Columns 14 29-Jan-12 15-Feb-12 04-Mar-12 21-Mar-12 25 A103400 Approval of Structural Dwgs. for Core Walls 14 29-Jan-12 15-Feb-12 01-Mar-12 20-Mar-12 24 A103410 Approval of Structural Dwgs. for Water Tank 14 29-Jan-12 15-Feb-12 01-Mar-12 20-Mar-12 24 A103380 Approval of Structural Dwgs. for Slab 14 06-Feb-12 23-Feb-12 13-Mar-12 01-Apr-12 26 A103430 Approval of Structural Dwgs. for Staircase 14 12-Mar-12 29-Mar-12 30-Dec-12 17-Jan-13 203 Ground FloGround Floor Slab 51 10-Mar-12 07-May-12 02-Apr-12 17-Jan-13 211 SubmissionSubmission 34 10-Mar-12 17-Apr-12 02-Apr-12 29-Dec-12 212 A103450 Submission of Structural Dwgs. for Ret. Walls -Columns 7 10-Mar-12 17-Mar-12 02-Apr-12 09-Apr-12 20 A103460 Submission of Structural Dwgs. for Core Walls 7 10-Mar-12 17-Mar-12 07-Apr-12 14-Apr-12 24 A103440 Submission of Structural Dwgs. for Slab 7 18-Mar-12 25-Mar-12 15-Apr-12 22-Apr-12 24 A103500 Submission of Structural Dwgs. for Staircase 7 10-Apr-12 17-Apr-12 22-Dec-12 29-Dec-12 212 ApprovalApproval 37 18-Mar-12 07-May-12 17-Apr-12 17-Jan-13 176 A103480 Approval of Structural Dwgs. for Ret. Walls -Columns 14 18-Mar-12 04-Apr-12 17-Apr-12 06-May-12 22 A103490 Approval of Structural Dwgs. for Core Walls 14 18-Mar-12 04-Apr-12 18-Apr-12 07-May-12 23 A103470 Approval of Structural Dwgs. for Slab 14 26-Mar-12 12-Apr-12 23-Apr-12 10-May-12 20 A103510 Approval of Structural Dwgs. for Staircase 14 18-Apr-12 07-May-12 30-Dec-12 17-Jan-13 176 1st Floor Sl1st Floor Slab 61 10-Apr-12 20-Jun-12 03-May-12 18-Feb-13 200 SubmissionSubmission 44 10-Apr-12 30-May-12 03-May-12 29-Jan-13 200 A103530 Submission of Structural Dwgs. for Columns 7 10-Apr-12 17-Apr-12 03-May-12 10-May-12 20 A103540 Submission of Structural Dwgs. for Core Walls 7 10-Apr-12 17-Apr-12 05-May-12 12-May-12 21 A103520 Submission of Structural Dwgs. for Slab 7 18-Apr-12 25-Apr-12 13-May-12 20-May-12 21 A103580 Submission of Structural Dwgs. for Staircase 7 23-May-12 30-May-12 21-Jan-13 29-Jan-13 200 ApprovalApproval 45 18-Apr-12 20-Jun-12 16-May-12 18-Feb-13 166 A103560 Approval of Structural Dwgs. for Columns 14 18-Apr-12 07-May-12 16-May-12 04-Jun-12 20 A103570 Approval of Structural Dwgs. for Core Walls 14 18-Apr-12 07-May-12 16-May-12 04-Jun-12 20 A103550 Approval of Structural Dwgs. for Slab 14 26-Apr-12 15-May-12 21-May-12 07-Jun-12 17 A103590 Approval of Structural Dwgs. for Staircase 14 31-May-12 20-Jun-12 30-Jan-13 18-Feb-13 166 2nd Floor S2nd Floor Slab 65 03-May-12 18-Jul-12 27-May-12 07-Feb-13 167 SubmissionSubmission 49 03-May-12 30-Jun-12 27-May-12 19-Jan-13 167 A103870 Submission of Structural Dwgs. for Columns 7 03-May-12 10-May-12 27-May-12 03-Jun-12 20 A103880 Submission of Structural Dwgs. for Core Walls 7 03-May-12 10-May-12 28-May-12 04-Jun-12 21 A103860 Submission of Structural Dwgs. for Slab 7 12-May-12 19-May-12 05-Jun-12 12-Jun-12 21 A103920 Submission of Structural Dwgs. for Staircase 7 23-Jun-12 30-Jun-12 12-Jan-13 19-Jan-13 167 ApprovalApproval 48 13-May-12 18-Jul-12 10-Jun-12 07-Feb-13 139 A103900 Approval of Structural Dwgs. for Columns 14 13-May-12 30-May-12 10-Jun-12 28-Jun-12 20 A103910 Approval of Structural Dwgs. for Core Walls 14 13-May-12 30-May-12 10-Jun-12 28-Jun-12 20 A103890 Approval of Structural Dwgs. for Slab 14 20-May-12 06-Jun-12 13-Jun-12 03-Jul-12 18 A103930 Approval of Structural Dwgs. for Staircase 14 01-Jul-12 18-Jul-12 20-Jan-13 07-Feb-13 139 3rd & 4th Fl3rd & 4th Floor Slab 76 29-May-12 28-Aug-12 23-Jun-12 05-Feb-13 132 SubmissionSubmission 59 29-May-12 06-Aug-12 23-Jun-12 15-Jan-13 132 A103610 Submission of Structural Dwgs. for Columns 7 29-May-12 05-Jun-12 23-Jun-12 30-Jun-12 20 A103620 Submission of Structural Dwgs. for Core Walls 7 29-May-12 05-Jun-12 23-Jun-12 30-Jun-12 20 A103600 Submission of Structural Dwgs. for Slab 7 06-Jun-12 13-Jun-12 01-Jul-12 08-Jul-12 20 A103660 Submission of Structural Dwgs. for Staircase 7 30-Jul-12 06-Aug-12 08-Jan-13 15-Jan-13 132 ApprovalApproval 57 06-Jun-12 28-Aug-12 03-Jul-12 05-Feb-13 110 A103640 Approval of Structural Dwgs. for Columns 14 06-Jun-12 26-Jun-12 03-Jul-12 22-Jul-12 18 A103650 Approval of Structural Dwgs. for Core Walls 14 06-Jun-12 26-Jun-12 03-Jul-12 22-Jul-12 18 A103630 Approval of Structural Dwgs. for Slab 14 14-Jun-12 04-Jul-12 09-Jul-12 26-Jul-12 16 A103670 Approval of Structural Dwgs. for Staircase 14 07-Aug-12 28-Aug-12 16-Jan-13 05-Feb-13 110 5th & 6th Fl5th & 6th Floor Slab 66 25-Jun-12 11-Sep-12 21-Jul-12 04-Feb-13 119 SubmissionSubmission 49 25-Jun-12 22-Aug-12 21-Jul-12 14-Jan-13 119 A103950 Submission of Structural Dwgs. for Columns 7 25-Jun-12 02-Jul-12 21-Jul-12 28-Jul-12 22 A103960 Submission of Structural Dwgs. for Core Walls 7 25-Jun-12 02-Jul-12 21-Jul-12 28-Jul-12 22 A103940 Submission of Structural Dwgs. for Slab 7 03-Jul-12 10-Jul-12 29-Jul-12 05-Aug-12 22 A104000 Submission of Structural Dwgs. for Staircase 7 13-Aug-12 22-Aug-12 07-Jan-13 14-Jan-13 119 ApprovalApproval 49 03-Jul-12 11-Sep-12 02-Aug-12 04-Feb-13 99 A103980 Approval of Structural Dwgs. for Columns 14 03-Jul-12 22-Jul-12 02-Aug-12 23-Aug-12 22 A103990 Approval of Structural Dwgs. for Core Walls 14 03-Jul-12 22-Jul-12 02-Aug-12 23-Aug-12 22 A103970 Approval of Structural Dwgs. for Slab 14 11-Jul-12 30-Jul-12 06-Aug-12 27-Aug-12 18 A104010 Approval of Structural Dwgs. for Staircase 14 23-Aug-12 11-Sep-12 15-Jan-13 04-Feb-13 99 7th Floor Sl7th Floor Slab 61 26-Jul-12 07-Oct-12 23-Aug-12 30-Jan-13 93 SubmissionSubmission 44 26-Jul-12 17-Sep-12 23-Aug-12 09-Jan-13 93 A104030 Submission of Structural Dwgs. for Columns 7 26-Jul-12 02-Aug-12 23-Aug-12 30-Aug-12 22 A104040 Submission of Structural Dwgs. for Core Walls 7 26-Jul-12 02-Aug-12 23-Aug-12 30-Aug-12 22 A104020 Submission of Structural Dwgs. for Slab 7 04-Aug-12 11-Aug-12 01-Sep-12 08-Sep-12 22 A104080 Submission of Structural Dwgs. for Staircase 7 10-Sep-12 17-Sep-12 02-Jan-13 09-Jan-13 93 ApprovalApproval 44 05-Aug-12 07-Oct-12 03-Sep-12 30-Jan-13 78 A104060 Approval of Structural Dwgs. for Columns 14 05-Aug-12 26-Aug-12 03-Sep-12 20-Sep-12 19 A104070 Approval of Structural Dwgs. for Core Walls 14 05-Aug-12 26-Aug-12 03-Sep-12 20-Sep-12 19 A104050 Approval of Structural Dwgs. for Slab 14 12-Aug-12 02-Sep-12 09-Sep-12 26-Sep-12 18 A104090 Approval of Structural Dwgs. for Staircase 14 18-Sep-12 07-Oct-12 10-Jan-13 30-Jan-13 78 Roof FloorRoof Floor Slab 72 11-Aug-12 06-Nov-12 09-Sep-12 23-May-13 166 SubmissionSubmission 56 11-Aug-12 16-Oct-12 09-Sep-12 05-May-13 166 A103690 Submission of Structural Dwgs. for Columns 7 11-Aug-12 18-Aug-12 09-Sep-12 16-Sep-12 23 A103700 Submission of Structural Dwgs. for Core Walls 7 11-Aug-12 18-Aug-12 09-Sep-12 16-Sep-12 23 A103680 Submission of Structural Dwgs. for Slab 7 21-Aug-12 28-Aug-12 17-Sep-12 24-Sep-12 23 A117170 Submission of Structural Dwgs. for Chillers Foundations 14 21-Aug-12 05-Sep-12 06-Oct-12 21-Oct-12 39 A103740 Submission of Structural Dwgs. for Staircase 7 01-Oct-12 08-Oct-12 08-Jan-13 15-Jan-13 80 A117070 Submission of Structural Dwgs. for Parapets 7 09-Oct-12 16-Oct-12 28-Apr-13 05-May-13 166 ApprovalApproval 55 21-Aug-12 06-Nov-12 18-Sep-12 23-May-13 138 A103720 Approval of Structural Dwgs. for Columns 14 21-Aug-12 09-Sep-12 20-Sep-12 09-Oct-12 22 A103730 Approval of Structural Dwgs. for Core Walls 14 21-Aug-12 09-Sep-12 18-Sep-12 07-Oct-12 20 A103710 Approval of Structural Dwgs. for Slab 14 29-Aug-12 17-Sep-12 25-Sep-12 14-Oct-12 19 A117160 Approval of Structural Dwgs. for Chillers Foundations 14 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Chillers Foundations Approval of Structural Dwgs. for Parapets Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Slab Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Slab Submission of Structural Dwgs. for Raft Approval of Structural Dwgs. for Raft Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Water Tank Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Water Tank Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Ret. Walls -Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Ret. Walls -Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Core Walls Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Chillers Foundations Submission of Structural Dwgs. for Staircase Submission of Structural Dwgs. for Parapets Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Core Walls Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Chillers Foundations Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 4 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 5. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A103750 Approval of Structural Dwgs. for Staircase 14 09-Oct-12 29-Oct-12 16-Jan-13 05-Feb-13 67 A117080 Approval of Structural Dwgs. for Parapets 14 17-Oct-12 06-Nov-12 06-May-13 23-May-13 138 Upper RoofUpper Roof Floor Slab 60 21-Aug-12 31-Oct-12 27-Sep-12 18-Feb-13 90 SubmissionSubmission 44 21-Aug-12 10-Oct-12 27-Sep-12 29-Jan-13 89 A103770 Submission of Structural Dwgs. for Columns 7 21-Aug-12 28-Aug-12 27-Sep-12 04-Oct-12 32 A103760 Submission of Structural Dwgs. for Slab 7 29-Aug-12 05-Sep-12 06-Oct-12 13-Oct-12 32 A103820 Submission of Structural Dwgs. for Staircase 7 03-Oct-12 10-Oct-12 21-Jan-13 29-Jan-13 89 ApprovalApproval 45 29-Aug-12 31-Oct-12 08-Oct-12 18-Feb-13 74 A103800 Approval of Structural Dwgs. for Columns 14 29-Aug-12 17-Sep-12 08-Oct-12 28-Oct-12 28 A103790 Approval of Structural Dwgs. for Slab 14 06-Sep-12 25-Sep-12 14-Oct-12 01-Nov-12 26 A103830 Approval of Structural Dwgs. for Staircase 14 11-Oct-12 31-Oct-12 30-Jan-13 18-Feb-13 74 ArchitecturalArchitectural 403 13-Mar-12 07-Jul-13 24-Mar-12 29-Jul-13 19 Hotel ApartemHotel Apartements (Block A) 383 13-Mar-12 13-Jun-13 24-Mar-12 29-Jul-13 39 2nd Baseme2nd Basement Floor 223 13-Mar-12 05-Dec-12 24-Mar-12 17-Apr-13 112 SubmissionSubmission 206 13-Mar-12 13-Nov-12 24-Mar-12 30-Mar-13 113 A119010 Submission of Block Work Setting Out Plan for 2nd Basement 8 13-Mar-12 21-Mar-12 24-Mar-12 01-Apr-12 9 A119130 Submission of Staircase Layout & Details 8 26-Apr-12 05-May-12 30-Aug-12 08-Sep-12 105 A119060 Submission of Doors Details 8 08-May-12 16-May-12 05-Feb-13 13-Feb-13 225 A119040 Submission of Flooring 8 20-May-12 28-May-12 07-Feb-13 16-Feb-13 217 A119050 Submission of Reflected Ceiling Layout 8 31-May-12 09-Jun-12 26-Dec-12 05-Jan-13 172 A119140 Submission of Handrail Layout & Details 8 18-Jul-12 26-Jul-12 24-Sep-12 02-Oct-12 56 A119100 Submission of Sinage Layout and Details 8 11-Aug-12 21-Aug-12 21-Mar-13 30-Mar-13 183 A119080 Submission of Parking Layout 8 05-Nov-12 13-Nov-12 12-Feb-13 20-Feb-13 81 A119090 Submission of Traffic Sign Layout 8 05-Nov-12 13-Nov-12 12-Feb-13 20-Feb-13 81 ApprovalApproval 179 22-Mar-12 05-Dec-12 09-Sep-12 17-Apr-13 93 A119290 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Mar-12 10-Apr-12 12-Sep-12 01-Oct-12 121 A119270 Approval of Staircase Layout & Details 14 06-May-12 23-May-12 09-Sep-12 26-Sep-12 87 A119340 Approval of Doors Details 14 17-May-12 05-Jun-12 14-Feb-13 05-Mar-13 187 A119320 Approval of Flooring 14 29-May-12 18-Jun-12 17-Feb-13 06-Mar-13 180 A119330 Approval of Reflected Ceiling Layout 14 10-Jun-12 28-Jun-12 06-Jan-13 23-Jan-13 143 A119280 Approval of Handrail Layout & Details 14 29-Jul-12 15-Aug-12 03-Oct-12 22-Oct-12 46 A119400 Approval of Sinage Layout and Details 14 22-Aug-12 10-Sep-12 31-Mar-13 17-Apr-13 152 A119360 Approval of Parking Layout 14 14-Nov-12 05-Dec-12 21-Feb-13 12-Mar-13 67 A119370 Approval of Traffic Sign Layout 14 14-Nov-12 05-Dec-12 21-Feb-13 12-Mar-13 67 1st Baseme1st Basement Floor 222 22-Mar-12 13-Dec-12 02-Apr-12 23-Apr-13 110 SubmissionSubmission 206 22-Mar-12 24-Nov-12 02-Apr-12 03-Apr-13 109 A119410 Submission of Block Work Setting Out Plan for 1st Basement 8 22-Mar-12 31-Mar-12 02-Apr-12 10-Apr-12 9 A119520 Submission of Staircase Layout & Details 8 06-May-12 14-May-12 02-Sep-12 10-Sep-12 99 A119460 Submission of Doors Details 8 17-May-12 26-May-12 23-Jan-13 02-Feb-13 207 A119440 Submission of Flooring 8 04-Jun-12 12-Jun-12 13-Jan-13 21-Jan-13 183 A119450 Submission of Reflected Ceiling Layout 8 10-Jun-12 19-Jun-12 17-Oct-12 28-Oct-12 108 A119530 Submission of Handrail Layout & Details 8 28-Jul-12 05-Aug-12 08-Oct-12 16-Oct-12 60 A119540 Submission of Sinage Layout and Details 8 22-Aug-12 30-Aug-12 26-Mar-13 03-Apr-13 179 A119480 Submission of Parking Layout 8 14-Nov-12 24-Nov-12 12-Feb-13 20-Feb-13 73 A119490 Submission of Traffic Sign Layout 8 14-Nov-12 24-Nov-12 12-Feb-13 20-Feb-13 73 ApprovalApproval 179 01-Apr-12 13-Dec-12 15-Jul-12 23-Apr-13 91 A119550 Approval of Block Work Setting Out Plan for 1st Basement 14 01-Apr-12 18-Apr-12 15-Jul-12 01-Aug-12 74 A119600 Approval of Staircase Layout & Details 14 15-May-12 03-Jun-12 11-Sep-12 30-Sep-12 82 A119620 Approval of Doors Details 14 27-May-12 13-Jun-12 03-Feb-13 20-Feb-13 172 A119580 Approval of Flooring 14 13-Jun-12 03-Jul-12 22-Jan-13 11-Feb-13 152 A119590 Approval of Reflected Ceiling Layout 14 20-Jun-12 09-Jul-12 29-Oct-12 18-Nov-12 90 A119610 Approval of Handrail Layout & Details 14 06-Aug-12 27-Aug-12 17-Oct-12 06-Nov-12 50 A119680 Approval of Sinage Layout and Details 14 02-Sep-12 19-Sep-12 04-Apr-13 23-Apr-13 149 A119640 Approval of Parking Layout 14 25-Nov-12 13-Dec-12 21-Feb-13 12-Mar-13 61 A119650 Approval of Traffic Sign Layout 14 25-Nov-12 13-Dec-12 21-Feb-13 12-Mar-13 61 Ground FloGround Floor 333 24-Apr-12 27-May-13 05-May-12 29-Jul-13 53 SubmissionSubmission 316 24-Apr-12 07-May-13 05-May-12 09-Jul-13 53 A118450 Submission of Block Work Setting Out Plan for Ground 8 24-Apr-12 02-May-12 05-May-12 13-May-12 9 A119150 Submission of Staircase Layout & Details 8 07-Jun-12 16-Jun-12 06-Sep-12 15-Sep-12 75 A118370 Submission of Reflected Ceiling Layout 8 20-Jun-12 28-Jun-12 22-Dec-12 30-Dec-12 152 A118380 Submission of Flooring Layout 8 20-Jun-12 28-Jun-12 16-Dec-12 24-Dec-12 147 A118420 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 25-Jul-12 02-Aug-12 21-Jan-13 30-Jan-13 147 A119160 Submission of Handrail Layout & Details 8 01-Sep-12 09-Sep-12 20-Oct-12 30-Oct-12 42 A118400 Submission of Doors Details 8 06-Oct-12 14-Oct-12 28-Jan-13 05-Feb-13 92 A118410 Submission of Sinage Layout and Details 8 17-Oct-12 28-Oct-12 26-Mar-13 03-Apr-13 131 A118440 Submission of Furniture Layout and Details 8 29-Apr-13 07-May-13 01-Jul-13 09-Jul-13 53 ApprovalApproval 270 03-May-12 27-May-13 16-Sep-12 29-Jul-13 44 A118480 Approval of Block Work Setting Out Plan for Ground 14 03-May-12 22-May-12 07-Nov-12 27-Nov-12 130 A119250 Approval of Staircase Layout & Details 14 18-Jun-12 05-Jul-12 16-Sep-12 03-Oct-12 62 A118490 Approval of Reflected Ceiling Layout 14 01-Jul-12 18-Jul-12 31-Dec-12 20-Jan-13 126 A118500 Approval of Flooring Layout 14 01-Jul-12 18-Jul-12 25-Dec-12 14-Jan-13 122 A118510 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 05-Aug-12 26-Aug-12 31-Jan-13 19-Feb-13 122 A119260 Approval of Handrail Layout & Details 14 10-Sep-12 27-Sep-12 31-Oct-12 20-Nov-12 36 A118530 Approval of Doors Details 14 15-Oct-12 04-Nov-12 06-Feb-13 25-Feb-13 77 A118550 Approval of Sinage Layout and Details 14 29-Oct-12 18-Nov-12 04-Apr-13 23-Apr-13 109 A118540 Approval of Furniture Layout and Details 14 08-May-13 27-May-13 10-Jul-13 29-Jul-13 44 Typical FlooTypical Floors 333 03-May-12 05-Jun-13 14-May-12 29-Jul-13 45 GeneralGeneral 109 03-May-12 10-Sep-12 14-May-12 23-Dec-12 85 SubmissiSubmission 92 03-May-12 21-Aug-12 14-May-12 03-Dec-12 85 A117470 Submission of Block Work Setting Out Plan for 1st Floor 8 03-May-12 12-May-12 14-May-12 22-May-12 9 A117230 Submission of Block Work Setting Out Plan for 2nd Floor 8 30-May-12 07-Jun-12 10-Jun-12 19-Jun-12 9 A117240 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 27-Jun-12 05-Jul-12 08-Jul-12 16-Jul-12 9 A117250 Submission of Block Work Setting Out Plan for 7th Floor 8 11-Aug-12 21-Aug-12 24-Nov-12 03-Dec-12 85 ApprovalApproval 84 13-May-12 10-Sep-12 09-Jul-12 23-Dec-12 71 A117480 Approval of Block Work Setting Out Plan for 1st Floor 14 13-May-12 30-May-12 09-Jul-12 26-Jul-12 40 A117490 Approval of Block Work Setting Out Plan for 2nd Floor 14 10-Jun-12 28-Jun-12 12-Jul-12 31-Jul-12 23 A117500 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 A117510 Approval of Block Work Setting Out Plan for 7th Floor 14 22-Aug-12 10-Sep-12 04-Dec-12 23-Dec-12 71 Corridor / GCorridor / General 184 30-Jun-12 07-Feb-13 16-Sep-12 15-Apr-13 57 SubmissiSubmission 168 30-Jun-12 19-Jan-13 16-Sep-12 26-Mar-13 56 A119170 Submission of Staircase Layout & Details 8 30-Jun-12 08-Jul-12 16-Sep-12 24-Sep-12 65 A117430 Submission of Reflected Ceiling Layout 8 11-Jul-12 19-Jul-12 26-Nov-12 05-Dec-12 113 A119180 Submission of Handrail Layout & Details 8 15-Aug-12 26-Aug-12 17-Oct-12 28-Oct-12 52 A117450 Submission of Flooring Layout 8 10-Sep-12 18-Sep-12 22-Dec-12 30-Dec-12 84 A117400 Submission of Doors Details 8 03-Oct-12 11-Oct-12 10-Jan-13 19-Jan-13 80 A117420 Submission of Sinage Layout and Details 8 10-Nov-12 19-Nov-12 18-Mar-13 26-Mar-13 106 A117410 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 05-Mar-13 13-Mar-13 45 ApprovalApproval 147 09-Jul-12 07-Feb-13 25-Sep-12 15-Apr-13 47 A119230 Approval of Staircase Layout & Details 14 09-Jul-12 26-Jul-12 25-Sep-12 14-Oct-12 54 A117520 Approval of Reflected Ceiling Layout 14 22-Jul-12 08-Aug-12 06-Dec-12 25-Dec-12 94 A119240 Approval of Handrail Layout & Details 14 27-Aug-12 13-Sep-12 29-Oct-12 18-Nov-12 44 A117530 Approval of Flooring Layout 14 19-Sep-12 08-Oct-12 31-Dec-12 20-Jan-13 70 A117550 Approval of Doors Details 14 14-Oct-12 01-Nov-12 20-Jan-13 07-Feb-13 66 A117580 Approval of Sinage Layout and Details 14 20-Nov-12 10-Dec-12 27-Mar-13 15-Apr-13 88 A117570 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 14-Mar-13 02-Apr-13 38 Studio ApaStudio Apartements 285 30-Jun-12 05-Jun-13 18-Sep-12 29-Jul-13 45 SubmissiSubmission 268 30-Jun-12 16-May-13 18-Sep-12 09-Jul-13 45 A117340 Submission of Wet Area Ceramic & Pocalin Layout 8 30-Jun-12 08-Jul-12 01-Oct-12 09-Oct-12 78 A117300 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 18-Sep-12 26-Sep-12 47 A117280 Submission of Waredrobe Details 8 03-Oct-12 11-Oct-12 04-Nov-12 12-Nov-12 25 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Approval of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Parapets Submission of Structural Dwgs. for Columns Submission of Structural Dwgs. for Slab Submission of Structural Dwgs. for Staircase Approval of Structural Dwgs. for Columns Approval of Structural Dwgs. for Slab Approval of Structural Dwgs. for Staircase Submission of Block Work Setting Out Plan for 2nd Basement Submission of Staircase Layout & Details Submission of Doors Details Submission of Flooring Submission of Reflected Ceiling Layout Submission of Handrail Layout & Details Submission of Sinage Layout and Details Submission of Parking Layout Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 2nd Basement Approval of Staircase Layout & Details Approval of Doors Details Approval of Flooring Approval of Reflected Ceiling Layout Approval of Handrail Layout & Details Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for 1st Basement Submission of Staircase Layout & Details Submission of Doors Details Submission of Flooring Submission of Reflected Ceiling Layout Submission of Handrail Layout & Details Submission of Sinage Layout and Details Submission of Parking Layout Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 1st Basement Approval of Staircase Layout & Details Approval of Doors Details Approval of Flooring Approval of Reflected Ceiling Layout Approval of Handrail Layout & Details Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for Ground Submission of Staircase Layout & Details Submission of Reflected Ceiling Layout Submission of Flooring Layout Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Handrail Layout & Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Furniture Layout and Details Approval of Block Work Setting Out Plan for Ground Approval of Staircase Layout & Details Approval of Reflected Ceiling Layout Approval of Flooring Layout Approval of Wet Area Ceramic & Pocalin Layout for Toilets Approval of Handrail Layout & Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Furniture Layout and Details Submission of Block Work Setting Out Plan for 1st Floor Submission of Block Work Setting Out Plan for 2nd Floor Submission of Block Work Setting Out Plan for 3rd to 6th Floor Submission of Block Work Setting Out Plan for 7th Floor Approval of Block Work Setting Out Plan for 1st Floor Approval of Block Work Setting Out Plan for 2nd Floor Approval of Block Work Setting Out Plan for 3rd to 6th Floor Approval of Block Work Setting Out Plan for 7th Floor Submission of Staircase Layout & Details Submission of Reflected Ceiling Layout Submission of Handrail Layout & Details Submission of Flooring Layout Submission of Doors Details Submission of Sinage Layout and Details Submission of Carpet Flooring Details Approval of Staircase Layout & Details Approval of Reflected Ceiling Layout Approval of Handrail Layout & Details Approval of Flooring Layout Approval of Doors Details Approval of Sinage Layout and Details Approval of Carpet Flooring Details Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Waredrobe Details Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 5 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 6. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A117320 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 23-Dec-12 31-Dec-12 55 A117260 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 09-Feb-13 17-Feb-13 74 A117270 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 09-Feb-13 17-Feb-13 74 A117370 Submission of Sinage Layout and Details 8 10-Nov-12 19-Nov-12 21-Mar-13 30-Mar-13 109 A117290 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 09-Feb-13 17-Feb-13 64 A117310 Submission of Doors Details 8 22-Nov-12 01-Dec-12 19-Jan-13 28-Jan-13 47 A117330 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 24-Mar-13 01-Apr-13 61 A117380 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45 ApprovalApproval 231 09-Jul-12 05-Jun-13 27-Sep-12 29-Jul-13 37 A117600 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Jul-12 26-Jul-12 10-Oct-12 30-Oct-12 65 A117620 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 27-Sep-12 16-Oct-12 39 A117650 Approval of Wardrobe Details 14 14-Oct-12 01-Nov-12 13-Nov-12 04-Dec-12 21 A117660 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 02-Jan-13 21-Jan-13 46 A117630 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 18-Feb-13 07-Mar-13 61 A117640 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 18-Feb-13 07-Mar-13 61 A117710 Approval of Sinage Layout and Details 14 20-Nov-12 10-Dec-12 31-Mar-13 17-Apr-13 90 A117690 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 18-Feb-13 07-Mar-13 53 A117670 Approval of Doors Details 14 03-Dec-12 20-Dec-12 29-Jan-13 17-Feb-13 39 A117700 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 02-Apr-13 21-Apr-13 51 A117720 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37 One Bed ROne Bed Room Apartements 285 30-Jun-12 05-Jun-13 09-Sep-12 29-Jul-13 45 SubmissiSubmission 268 30-Jun-12 16-May-13 09-Sep-12 09-Jul-13 45 A117730 Submission of Wet Area Ceramic & Pocalin Layout 8 30-Jun-12 08-Jul-12 13-Jan-13 21-Jan-13 162 A117750 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 09-Sep-12 17-Sep-12 39 A117780 Submission of Wardrobe Details 8 03-Oct-12 11-Oct-12 04-Nov-12 12-Nov-12 25 A117790 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 27-Dec-12 06-Jan-13 59 A117760 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 11-Feb-13 19-Feb-13 76 A117770 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 14-Feb-13 23-Feb-13 79 A117820 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 14-Feb-13 23-Feb-13 69 A117800 Submission of Doors Details 8 22-Nov-12 01-Dec-12 21-Jan-13 30-Jan-13 49 A117840 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 21-Mar-13 30-Mar-13 89 A117830 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 19-Mar-13 27-Mar-13 57 A117850 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45 ApprovalApproval 231 09-Jul-12 05-Jun-13 18-Sep-12 29-Jul-13 37 A117860 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Jul-12 26-Jul-12 22-Jan-13 11-Feb-13 135 A117880 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 18-Sep-12 07-Oct-12 32 A117910 Approval of Wardrobe Details 14 14-Oct-12 01-Nov-12 13-Nov-12 04-Dec-12 21 A117920 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 07-Jan-13 27-Jan-13 49 A117890 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 20-Feb-13 11-Mar-13 63 A117900 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 24-Feb-13 13-Mar-13 65 A117950 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 24-Feb-13 13-Mar-13 57 A117930 Approval of Doors Details 14 03-Dec-12 20-Dec-12 31-Jan-13 19-Feb-13 41 A117970 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 31-Mar-13 17-Apr-13 73 A117960 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 28-Mar-13 16-Apr-13 48 A117980 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37 Two Bed RTwo Bed Room Apartements 275 11-Jul-12 05-Jun-13 16-Aug-12 29-Jul-13 45 SubmissiSubmission 258 11-Jul-12 16-May-13 16-Aug-12 09-Jul-13 45 A117990 Submission of Wet Area Ceramic & Pocalin Layout 8 11-Jul-12 19-Jul-12 14-Jan-13 22-Jan-13 153 A118010 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 16-Aug-12 27-Aug-12 21 A118040 Submission of Wardrobe Details 8 29-Aug-12 06-Sep-12 21-Oct-12 31-Oct-12 45 A118050 Submission of Floors Layout and Details 8 15-Oct-12 23-Oct-12 03-Jan-13 12-Jan-13 64 A118020 Submission of Vanity Counter Details 8 10-Nov-12 19-Nov-12 03-Feb-13 11-Feb-13 69 A118030 Submission of Kitchen Cabinet Details 8 10-Nov-12 19-Nov-12 03-Feb-13 11-Feb-13 69 A118080 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 03-Feb-13 11-Feb-13 59 A118060 Submission of Doors Details 8 22-Nov-12 01-Dec-12 23-Jan-13 02-Feb-13 51 A118100 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 21-Mar-13 30-Mar-13 89 A118090 Submission of Carpet Flooring Details 8 10-Jan-13 19-Jan-13 16-Mar-13 24-Mar-13 54 A118110 Submission of Furniture Layout and Detals 8 08-May-13 16-May-13 01-Jul-13 09-Jul-13 45 ApprovalApproval 222 22-Jul-12 05-Jun-13 28-Aug-12 29-Jul-13 37 A118120 Approval of Wet Area Ceramic & Pocalin Layout 14 22-Jul-12 08-Aug-12 23-Jan-13 12-Feb-13 127 A118140 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 28-Aug-12 16-Sep-12 17 A118170 Approval of Wardrobe Details 14 09-Sep-12 26-Sep-12 01-Nov-12 21-Nov-12 38 A118180 Approval of Floors Layout and Details 14 24-Oct-12 13-Nov-12 13-Jan-13 31-Jan-13 53 A118150 Approval of Vanity Counter Details 14 20-Nov-12 10-Dec-12 12-Feb-13 03-Mar-13 57 A118160 Approval of Kitchen Cabinet Details 14 20-Nov-12 10-Dec-12 12-Feb-13 03-Mar-13 57 A118210 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 12-Feb-13 03-Mar-13 49 A118190 Approval of Doors Details 14 03-Dec-12 20-Dec-12 03-Feb-13 20-Feb-13 42 A118230 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 31-Mar-13 17-Apr-13 73 A118220 Approval of Carpet Flooring Details 14 20-Jan-13 07-Feb-13 25-Mar-13 11-Apr-13 45 A118240 Approval of Furniture Layout and Detals 14 19-May-13 05-Jun-13 10-Jul-13 29-Jul-13 37 Roof - UppeRoof - Upper Roof Floor 271 23-Jul-12 13-Jun-13 09-Sep-12 29-Jul-13 39 GeneralGeneral 124 23-Jul-12 20-Dec-12 09-Sep-12 04-Apr-13 88 SubmissiSubmission 108 23-Jul-12 01-Dec-12 09-Sep-12 17-Mar-13 88 A118640 Submission of Block Work Setting Out Plan for Roof & upper ... 8 23-Jul-12 31-Jul-12 09-Sep-12 17-Sep-12 39 A118570 Submission of Roof's Water Proofing System 8 01-Aug-12 09-Aug-12 30-Dec-12 08-Jan-13 123 A118580 Submission of Pool Deck Layout 8 07-Aug-12 15-Aug-12 18-Feb-13 26-Feb-13 159 A118620 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 20-Nov-12 28-Nov-12 09-Mar-13 17-Mar-13 90 A118630 Submission of Flooring Layout 8 20-Nov-12 28-Nov-12 23-Feb-13 03-Mar-13 78 A119190 Submission of Staircase Layout & Details 8 20-Nov-12 28-Nov-12 04-Feb-13 12-Feb-13 62 A119200 Submission of Handrail Layout & Details 8 20-Nov-12 28-Nov-12 09-Feb-13 17-Feb-13 66 A118590 Submission of Doors Details 8 22-Nov-12 01-Dec-12 07-Mar-13 16-Mar-13 87 ApprovalApproval 97 01-Aug-12 20-Dec-12 14-Oct-12 04-Apr-13 73 A118700 Approval of Block Work Setting Out Plan for Roof & Upper Roof 14 01-Aug-12 22-Aug-12 14-Oct-12 01-Nov-12 50 A118710 Approval of Roof's Water Proofing System 14 12-Aug-12 02-Sep-12 09-Jan-13 29-Jan-13 102 A118690 Approval of Pool Deck Layout 14 16-Aug-12 06-Sep-12 27-Feb-13 18-Mar-13 132 A118720 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 29-Nov-12 19-Dec-12 18-Mar-13 04-Apr-13 74 A118730 Approval of Flooring Layout 14 29-Nov-12 19-Dec-12 04-Mar-13 21-Mar-13 64 A119210 Approval of Staircase Layout & Details 14 29-Nov-12 19-Dec-12 13-Feb-13 04-Mar-13 51 A119220 Approval of Handrail Layout & Details 14 29-Nov-12 19-Dec-12 18-Feb-13 07-Mar-13 54 A118740 Approval of Doors Details 14 03-Dec-12 20-Dec-12 17-Mar-13 03-Apr-13 72 GymnasiumGymnasium 243 27-Aug-12 13-Jun-13 19-Nov-12 29-Jul-13 39 SubmissiSubmission 226 27-Aug-12 23-May-13 19-Nov-12 09-Jul-13 39 A118650 Submission of Reflected Ceiling Layout 8 27-Aug-12 04-Sep-12 19-Nov-12 27-Nov-12 69 A118680 Submission of Vinyl Floor Detals 8 03-Dec-12 11-Dec-12 19-Jan-13 28-Jan-13 39 A118660 Submission of Furniture Layout and Detals 8 15-May-13 23-May-13 01-Jul-13 09-Jul-13 39 ApprovalApproval 196 05-Sep-12 13-Jun-13 28-Nov-12 29-Jul-13 32 A118770 Approval of Reflected Ceiling Layout 14 05-Sep-12 24-Sep-12 28-Nov-12 18-Dec-12 58 A118780 Approval of Vinyl Floor Detals 14 12-Dec-12 31-Dec-12 20-Mar-13 08-Apr-13 68 A118790 Approval of Furniture Layout and Detals 14 26-May-13 13-Jun-13 10-Jul-13 29-Jul-13 32 Hotel (BlockHotel (Block B) 377 05-Apr-12 30-Jun-13 23-Apr-12 29-Jul-13 25 2nd Baseme2nd Basement Floor 222 05-Apr-12 27-Dec-12 23-Apr-12 25-Apr-13 100 SubmissionSubmission 206 05-Apr-12 09-Dec-12 23-Apr-12 07-Apr-13 100 A123210 Submission of Block Work Setting Out Plan for 2nd Basement 8 05-Apr-12 14-Apr-12 23-Apr-12 01-May-12 15 A123250 Submission of Doors Details 8 20-May-12 28-May-12 12-Feb-13 20-Feb-13 221 A123240 Submission of Flooring 8 31-May-12 09-Jun-12 09-Feb-13 17-Feb-13 208 A123330 Submission of Staircase Layout & Details 8 25-Jun-12 03-Jul-12 08-Jan-13 16-Jan-13 162 A123340 Submission of Handrail Layout & Details 8 25-Jun-12 03-Jul-12 12-Jan-13 20-Jan-13 165 A123300 Submission of Sinage Layout and Details 8 05-Sep-12 13-Sep-12 30-Mar-13 07-Apr-13 170 A123280 Submission of Parking Layout 8 29-Nov-12 09-Dec-12 16-Feb-13 24-Feb-13 64 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Kitchen Cabinet Details Submission of Sinage Layout and Details Submission of Mirror Details Submission of Doors Details Submission of Carpet Flooring Details Submission of Furniture Layout and Detals Approval of Wet Area Ceramic & Pocalin Layout Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Kitchen Cabinet Details Approval of Sinage Layout and Details Approval of Mirror Details Approval of Doors Details Approval of Carpet Flooring Details Approval of Furniture Layout and Detals Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Kitchen Cabinet Details Submission of Mirror Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Carpet Flooring Details Submission of Furniture Layout and Detals Approval of Wet Area Ceramic & Pocalin Layout Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Kitchen Cabinet Details Approval of Mirror Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Carpet Flooring Details Approval of Furniture Layout and Detals Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Kitchen Cabinet Details Submission of Mirror Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Carpet Flooring Details Submission of Furniture Layout and Detals Approval of Wet Area Ceramic & Pocalin Layout Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Kitchen Cabinet Details Approval of Mirror Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Carpet Flooring Details Approval of Furniture Layout and Detals Submission of Block Work Setting Out Plan for Roof & upper Roof Submission of Roof's Water Proofing System Submission of Pool Deck Layout Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Flooring Layout Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Doors Details Approval of Block Work Setting Out Plan for Roof & Upper Roof Approval of Roof's Water Proofing System Approval of Pool Deck Layout Approval of Wet Area Ceramic & Pocalin Layout for Toilets Approval of Flooring Layout Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Doors Details Submission of Reflected Ceiling Layout Submission of Vinyl Floor Detals Submission of Furniture Layout and Detals Approval of Reflected Ceiling Layout Approval of Vinyl Floor Detals Approval of Furniture Layout and Detals Submission of Block Work Setting Out Plan for 2nd Basement Submission of Doors Details Submission of Flooring Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Sinage Layout and Details Submission of Parking Layout Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 6 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 7. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A123290 Submission of Traffic Sign Layout 8 29-Nov-12 09-Dec-12 16-Feb-13 24-Feb-13 64 ApprovalApproval 179 15-Apr-12 27-Dec-12 14-Nov-12 25-Apr-13 83 A123490 Approval of Block Work Setting Out Plan for 2nd Basement 14 15-Apr-12 02-May-12 14-Nov-12 05-Dec-12 149 A123530 Approval of Doors Details 14 29-May-12 18-Jun-12 21-Feb-13 12-Mar-13 184 A123520 Approval of Flooring 14 10-Jun-12 28-Jun-12 18-Feb-13 07-Mar-13 173 A123470 Approval of Staircase Layout & Details 14 04-Jul-12 23-Jul-12 17-Jan-13 06-Feb-13 135 A123480 Approval of Handrail Layout & Details 14 04-Jul-12 23-Jul-12 21-Jan-13 10-Feb-13 137 A123580 Approval of Sinage Layout and Details 14 16-Sep-12 03-Oct-12 08-Apr-13 25-Apr-13 141 A123560 Approval of Parking Layout 14 10-Dec-12 27-Dec-12 25-Feb-13 14-Mar-13 53 A123570 Approval of Traffic Sign Layout 14 10-Dec-12 27-Dec-12 25-Feb-13 14-Mar-13 53 1st Baseme1st Basement Floor 193 20-May-12 08-Jan-13 06-Jun-12 18-Apr-13 85 SubmissionSubmission 176 20-May-12 18-Dec-12 06-Jun-12 31-Mar-13 86 A123610 Submission of Block Work Setting Out Plan for 1st Basement 8 20-May-12 28-May-12 06-Jun-12 14-Jun-12 15 A123650 Submission of Doors Details 8 23-Jun-12 01-Jul-12 18-Feb-13 26-Feb-13 198 A123660 Submission of Reflected Ceiling Layout 8 04-Jul-12 12-Jul-12 29-Dec-12 07-Jan-13 146 A123730 Submission of Staircase Layout & Details 8 04-Jul-12 12-Jul-12 16-Jan-13 26-Jan-13 161 A123640 Submission of Flooring 8 16-Jul-12 24-Jul-12 31-Jan-13 09-Feb-13 163 A123740 Submission of Handrail Layout & Details 8 16-Jul-12 24-Jul-12 19-Jan-13 28-Jan-13 153 A123700 Submission of Sinage Layout and Details 8 03-Sep-12 11-Sep-12 23-Mar-13 31-Mar-13 166 A123680 Submission of Parking Layout 8 10-Dec-12 18-Dec-12 23-Feb-13 03-Mar-13 62 A123690 Submission of Traffic Sign Layout 8 10-Dec-12 18-Dec-12 23-Feb-13 03-Mar-13 62 ApprovalApproval 154 29-May-12 08-Jan-13 16-Sep-12 18-Apr-13 71 A123770 Approval of Block Work Setting Out Plan for 1st Basement 14 29-May-12 18-Jun-12 16-Sep-12 03-Oct-12 75 A123810 Approval of Doors Details 14 02-Jul-12 19-Jul-12 27-Feb-13 18-Mar-13 165 A123750 Approval of Staircase Layout & Details 14 15-Jul-12 01-Aug-12 27-Jan-13 13-Feb-13 133 A123820 Approval of Reflected Ceiling Layout 14 15-Jul-12 01-Aug-12 08-Jan-13 28-Jan-13 121 A123760 Approval of Handrail Layout & Details 14 25-Jul-12 13-Aug-12 29-Jan-13 17-Feb-13 127 A123800 Approval of Flooring 14 25-Jul-12 13-Aug-12 10-Feb-13 27-Feb-13 135 A123860 Approval of Sinage Layout and Details 14 12-Sep-12 01-Oct-12 01-Apr-13 18-Apr-13 138 A123840 Approval of Parking Layout 14 19-Dec-12 08-Jan-13 04-Mar-13 21-Mar-13 51 A123850 Approval of Traffic Sign Layout 14 19-Dec-12 08-Jan-13 04-Mar-13 21-Mar-13 51 Ground FloGround Floor 293 04-Jul-12 20-Jun-13 22-Jul-12 29-Jul-13 33 Public ArePublic Areas 283 04-Jul-12 09-Jun-13 22-Jul-12 29-Jul-13 43 SubmissiSubmission 266 04-Jul-12 19-May-13 22-Jul-12 09-Jul-13 43 A122880 Submission of Block Work Setting Out Plan for Ground 8 04-Jul-12 12-Jul-12 22-Jul-12 30-Jul-12 15 A122840 Submission of Reflected Ceiling Layout 8 06-Aug-12 14-Aug-12 20-Dec-12 29-Dec-12 111 A122850 Submission of Flooring Layout 8 06-Aug-12 14-Aug-12 02-Feb-13 10-Feb-13 146 A122860 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 06-Aug-12 14-Aug-12 26-Dec-12 05-Jan-13 116 A123350 Submission of Staircase Layout & Details 8 18-Aug-12 28-Aug-12 09-Feb-13 17-Feb-13 142 A123360 Submission of Handrail Layout & Details 8 18-Aug-12 28-Aug-12 12-Feb-13 20-Feb-13 145 A122820 Submission of Doors Details 8 24-Sep-12 02-Oct-12 09-Mar-13 17-Mar-13 136 A122830 Submission of Sinage Layout and Details 8 24-Sep-12 02-Oct-12 23-Mar-13 31-Mar-13 148 A122890 Submission of Crapet Flooring Details 8 06-Feb-13 14-Feb-13 19-Mar-13 27-Mar-13 35 A122870 Submission of Furniture Layout and Detals 8 11-May-13 19-May-13 01-Jul-13 09-Jul-13 43 ApprovalApproval 228 15-Jul-12 09-Jun-13 27-Aug-12 29-Jul-13 36 A122960 Approval of Block Work Setting Out Plan for Ground 14 15-Jul-12 01-Aug-12 27-Aug-12 13-Sep-12 29 A122920 Approval of Reflected Ceiling Layout 14 15-Aug-12 05-Sep-12 30-Dec-12 17-Jan-13 92 A122930 Approval of Flooring Layout 14 15-Aug-12 05-Sep-12 11-Feb-13 28-Feb-13 121 A122940 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 15-Aug-12 05-Sep-12 06-Jan-13 23-Jan-13 96 A123450 Approval of Staircase Layout & Details 14 29-Aug-12 17-Sep-12 18-Feb-13 07-Mar-13 118 A123460 Approval of Handrail Layout & Details 14 29-Aug-12 17-Sep-12 21-Feb-13 12-Mar-13 121 A122900 Approval of Doors Details 14 03-Oct-12 22-Oct-12 18-Mar-13 04-Apr-13 113 A122910 Approval of Sinage Layout and Details 14 03-Oct-12 22-Oct-12 01-Apr-13 18-Apr-13 123 A123950 Approval of Carpet Flooring Details 14 17-Feb-13 06-Mar-13 28-Mar-13 16-Apr-13 29 A122950 Approval of Furniture Layout and Detals 14 20-May-13 09-Jun-13 10-Jul-13 29-Jul-13 36 RestaurantRestaurant 266 02-Aug-12 18-Jun-13 18-Dec-12 29-Jul-13 35 SubmissiSubmission 249 02-Aug-12 28-May-13 18-Dec-12 09-Jul-13 35 A123980 Submission of Reflected Ceiling Layout 8 02-Aug-12 11-Aug-12 18-Dec-12 26-Dec-12 112 A123990 Submission of Flooring Layout 8 02-Aug-12 11-Aug-12 05-Feb-13 13-Feb-13 152 A123960 Submission of Sinage Layout and Details 8 27-Dec-12 06-Jan-13 30-Mar-13 07-Apr-13 77 A123970 Submission of Furniture Layout and Details 8 20-May-13 28-May-13 01-Jul-13 09-Jul-13 35 ApprovalApproval 215 12-Aug-12 18-Jun-13 27-Dec-12 29-Jul-13 29 A124020 Approval of Reflected Ceiling Layout 14 12-Aug-12 02-Sep-12 27-Dec-12 16-Jan-13 94 A124030 Approval of Flooring Layout 14 12-Aug-12 02-Sep-12 14-Feb-13 05-Mar-13 127 A124000 Approval of Sinage Layout and Details 14 07-Jan-13 27-Jan-13 08-Apr-13 25-Apr-13 64 A124010 Approval of Furniture Layout and Detals 14 29-May-13 18-Jun-13 10-Jul-13 29-Jul-13 29 BussinessBussiness Center & Retail 275 14-Jul-12 09-Jun-13 28-Nov-12 29-Jul-13 43 SubmissiSubmission 258 14-Jul-12 19-May-13 28-Nov-12 09-Jul-13 43 A124040 Submission of Reflected Ceiling Layout 8 14-Jul-12 22-Jul-12 28-Nov-12 08-Dec-12 113 A124050 Submission of Flooring Layout 8 18-Aug-12 28-Aug-12 19-Jan-13 28-Jan-13 125 A124070 Submission of Sinage Layout and Details 8 18-Feb-13 26-Feb-13 21-Mar-13 30-Mar-13 27 A124060 Submission of Furniture Layout and Details 8 11-May-13 19-May-13 01-Jul-13 09-Jul-13 43 ApprovalApproval 222 23-Jul-12 09-Jun-13 09-Dec-12 29-Jul-13 36 A124080 Approval of Reflected Ceiling Layout 14 23-Jul-12 09-Aug-12 09-Dec-12 26-Dec-12 94 A124090 Approval of Flooring Layout 14 29-Aug-12 17-Sep-12 29-Jan-13 17-Feb-13 104 A124110 Approval of Sinage Layout and Details 14 27-Feb-13 18-Mar-13 31-Mar-13 17-Apr-13 22 A124100 Approval of Furniture Layout and Detals 14 20-May-13 09-Jun-13 10-Jul-13 29-Jul-13 36 EnteranceEnterance Lobby & Lounge 285 14-Jul-12 20-Jun-13 23-Dec-12 29-Jul-13 33 SubmissiSubmission 268 14-Jul-12 30-May-13 23-Dec-12 09-Jul-13 33 A124120 Submission of Reflected Ceiling Layout 8 14-Jul-12 22-Jul-12 23-Dec-12 31-Dec-12 133 A124130 Submission of Flooring Layout 8 18-Aug-12 28-Aug-12 21-Feb-13 02-Mar-13 153 A124150 Submission of Sinage Layout and Details 8 18-Feb-13 26-Feb-13 30-Mar-13 07-Apr-13 34 A124140 Submission of Furniture Layout and Details 8 22-May-13 30-May-13 01-Jul-13 09-Jul-13 33 ApprovalApproval 231 23-Jul-12 20-Jun-13 02-Jan-13 29-Jul-13 27 A124160 Approval of Reflected Ceiling Layout 14 23-Jul-12 09-Aug-12 02-Jan-13 21-Jan-13 111 A124170 Approval of Flooring Layout 14 29-Aug-12 17-Sep-12 03-Mar-13 20-Mar-13 127 A124190 Approval of Sinage Layout and Details 14 27-Feb-13 18-Mar-13 08-Apr-13 25-Apr-13 28 A124180 Approval of Furniture Layout and Detals 14 02-Jun-13 20-Jun-13 10-Jul-13 29-Jul-13 27 Typical FlooTypical Floors 293 14-Jul-12 30-Jun-13 31-Jul-12 29-Jul-13 25 GeneralGeneral 74 14-Jul-12 09-Oct-12 31-Jul-12 11-Feb-13 101 SubmissiSubmission 57 14-Jul-12 19-Sep-12 31-Jul-12 29-Dec-12 82 A122030 Submission of Block Work Setting Out Plan for 1st Floor 8 14-Jul-12 22-Jul-12 31-Jul-12 08-Aug-12 15 A121790 Submission of Block Work Setting Out Plan for 2nd Floor 8 23-Jul-12 31-Jul-12 31-Oct-12 08-Nov-12 82 A121800 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 01-Aug-12 09-Aug-12 10-Nov-12 19-Nov-12 82 A121810 Submission of Block Work Setting Out Plan for 7th Floor 8 11-Sep-12 19-Sep-12 20-Dec-12 29-Dec-12 82 ApprovalApproval 55 23-Jul-12 09-Oct-12 17-Sep-12 11-Feb-13 84 A122070 Approval of Block Work Setting Out Plan for 1st Floor 14 23-Jul-12 09-Aug-12 17-Sep-12 04-Oct-12 38 A122040 Approval of Block Work Setting Out Plan for 2nd Floor 14 01-Aug-12 22-Aug-12 22-Jan-13 11-Feb-13 118 A122050 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 12-Aug-12 02-Sep-12 30-Dec-12 17-Jan-13 95 A122060 Approval of Block Work Setting Out Plan for 7th Floor 14 20-Sep-12 09-Oct-12 30-Dec-12 17-Jan-13 68 Corridor / PCorridor / Public Areas 285 23-Jul-12 30-Jun-13 13-Oct-12 29-Jul-13 25 SubmissiSubmission 268 23-Jul-12 10-Jun-13 13-Oct-12 09-Jul-13 25 A121990 Submission of Reflected Ceiling Layout 8 23-Jul-12 31-Jul-12 06-Jan-13 14-Jan-13 136 A122310 Submission of Landscaping's Water Proofing Details 8 23-Jul-12 31-Jul-12 13-Oct-12 21-Oct-12 68 A121960 Submission of Doors Details 8 23-Aug-12 01-Sep-12 03-Mar-13 11-Mar-13 158 A122290 Submission of Landscaping Layout & Details 8 23-Aug-12 01-Sep-12 01-Dec-12 10-Dec-12 82 A123370 Submission of Staircase Layout & Details 8 29-Aug-12 06-Sep-12 13-Jan-13 21-Jan-13 112 A123380 Submission of Handrail Layout & Details 8 29-Aug-12 06-Sep-12 17-Jan-13 27-Jan-13 116 A122010 Submission of Flooring Layout 8 04-Sep-12 12-Sep-12 19-Feb-13 27-Feb-13 138 A123890 Submission of Pool Deck Layout 8 10-Sep-12 18-Sep-12 14-Feb-13 23-Feb-13 129 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 2nd Basement Approval of Doors Details Approval of Flooring Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for 1st Basement Submission of Doors Details Submission of Reflected Ceiling Layout Submission of Staircase Layout & Details Submission of Flooring Submission of Handrail Layout & Details Submission of Sinage Layout and Details Submission of Parking Layout Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 1st Basement Approval of Doors Details Approval of Staircase Layout & Details Approval of Reflected Ceiling Layout Approval of Handrail Layout & Details Approval of Flooring Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for Ground Submission of Reflected Ceiling Layout Submission of Flooring Layout Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Crapet Flooring Details Submission of Furniture Layout and Detals Approval of Block Work Setting Out Plan for Ground Approval of Reflected Ceiling Layout Approval of Flooring Layout Approval of Wet Area Ceramic & Pocalin Layout for Toilets Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Carpet Flooring Details Approval of Furniture Layout and Detals Submission of Reflected Ceiling Layout Submission of Flooring Layout Submission of Sinage Layout and Details Submission of Furniture Layout and Details Approval of Reflected Ceiling Layout Approval of Flooring Layout Approval of Sinage Layout and Details Approval of Furniture Layout and Deta Submission of Reflected Ceiling Layout Submission of Flooring Layout Submission of Sinage Layout and Details Submission of Furniture Layout and Details Approval of Reflected Ceiling Layout Approval of Flooring Layout Approval of Sinage Layout and Details Approval of Furniture Layout and Detals Submission of Reflected Ceiling Layout Submission of Flooring Layout Submission of Sinage Layout and Details Submission of Furniture Layout and Detail Approval of Reflected Ceiling Layout Approval of Flooring Layout Approval of Sinage Layout and Details Approval of Furniture Layout and Deta Submission of Block Work Setting Out Plan for 1st Floor Submission of Block Work Setting Out Plan for 2nd Floor Submission of Block Work Setting Out Plan for 3rd to 6th Floor Submission of Block Work Setting Out Plan for 7th Floor Approval of Block Work Setting Out Plan for 1st Floor Approval of Block Work Setting Out Plan for 2nd Floor Approval of Block Work Setting Out Plan for 3rd to 6th Floor Approval of Block Work Setting Out Plan for 7th Floor Submission of Reflected Ceiling Layout Submission of Landscaping's Water Proofing Details Submission of Doors Details Submission of Landscaping Layout & Details Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Flooring Layout Submission of Pool Deck Layout Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 7 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 8. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A121980 Submission of Sinage Layout and Details 8 15-Oct-12 23-Oct-12 25-Mar-13 02-Apr-13 132 A122300 Submission of Irrigation Layout & Details 8 15-Oct-12 23-Oct-12 19-Jan-13 28-Jan-13 77 A122320 Submission of Sky Light Details 8 22-Nov-12 01-Dec-12 24-Feb-13 04-Mar-13 77 A121970 Submission of Carpet Flooring Details 8 16-Feb-13 24-Feb-13 05-Mar-13 13-Mar-13 15 A122000 Submission of Furniture Layout and Details 8 01-Jun-13 10-Jun-13 01-Jul-13 09-Jul-13 25 ApprovalApproval 230 01-Aug-12 30-Jun-13 22-Oct-12 29-Jul-13 21 A122120 Approval of Reflected Ceiling Layout 14 01-Aug-12 22-Aug-12 15-Jan-13 04-Feb-13 113 A123930 Approval of Landscaping's Water Proofing Details 14 01-Aug-12 22-Aug-12 22-Oct-12 11-Nov-12 56 A122090 Approval of Doors Details 14 02-Sep-12 19-Sep-12 12-Mar-13 31-Mar-13 132 A123910 Approval of Landscaping Layout & Details 14 02-Sep-12 19-Sep-12 11-Dec-12 30-Dec-12 69 A123430 Approval of Staircase Layout & Details 14 09-Sep-12 26-Sep-12 22-Jan-13 11-Feb-13 93 A123440 Approval of Handrail Layout & Details 14 09-Sep-12 26-Sep-12 28-Jan-13 14-Feb-13 96 A123900 Approval of Pool Deck Layout 8 19-Sep-12 30-Sep-12 24-Feb-13 05-Mar-13 107 A122140 Approval of Flooring Layout 14 13-Sep-12 02-Oct-12 28-Feb-13 19-Mar-13 115 A122110 Approval of Sinage Layout and Details 14 24-Oct-12 13-Nov-12 03-Apr-13 22-Apr-13 110 A123920 Approval of Irrigation Layout & Details 14 24-Oct-12 13-Nov-12 29-Jan-13 17-Feb-13 64 A123940 Approval of Sky Light Details 14 03-Dec-12 20-Dec-12 05-Mar-13 24-Mar-13 64 A122100 Approval of Carpet Flooring Details 14 25-Feb-13 14-Mar-13 14-Mar-13 02-Apr-13 13 A122130 Approval of Furniture Layout and Detals 14 11-Jun-13 30-Jun-13 10-Jul-13 29-Jul-13 21 Hotel RoomHotel Rooms 255 29-Aug-12 30-Jun-13 20-Nov-12 29-Jul-13 25 SubmissiSubmission 238 29-Aug-12 10-Jun-13 20-Nov-12 09-Jul-13 25 A121860 Submission of Reflected Ceiling Layout 8 29-Aug-12 06-Sep-12 20-Nov-12 28-Nov-12 68 A121900 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 29-Aug-12 06-Sep-12 03-Dec-12 11-Dec-12 78 A121840 Submission of Wardrobe Details 8 15-Oct-12 23-Oct-12 24-Dec-12 02-Jan-13 56 A121880 Submission of Floors Layout and Details 8 29-Oct-12 06-Nov-12 10-Feb-13 18-Feb-13 85 A121850 Submission of Mirror Details 8 22-Nov-12 01-Dec-12 11-Feb-13 19-Feb-13 66 A121870 Submission of Doors Details 8 22-Nov-12 01-Dec-12 03-Feb-13 11-Feb-13 59 A121820 Submission of Vanity Counter Details 8 17-Dec-12 25-Dec-12 12-Feb-13 20-Feb-13 47 A121890 Submission of Carpet Flooring Details 8 16-Feb-13 24-Feb-13 17-Mar-13 25-Mar-13 25 A121930 Submission of Sinage Layout and Details 8 16-Feb-13 24-Feb-13 23-Mar-13 31-Mar-13 30 A121940 Submission of Furniture Layout and Detals 8 01-Jun-13 10-Jun-13 01-Jul-13 09-Jul-13 25 ApprovalApproval 205 09-Sep-12 30-Jun-13 29-Nov-12 29-Jul-13 21 A122200 Approval of Reflected Ceiling Layout 14 09-Sep-12 26-Sep-12 29-Nov-12 19-Dec-12 57 A122240 Approval of Wet Area Ceramic & Pocalin Layout 14 09-Sep-12 26-Sep-12 12-Dec-12 31-Dec-12 65 A122180 Approval of Wardrobe Details 14 24-Oct-12 13-Nov-12 03-Jan-13 22-Jan-13 47 A122220 Approval of Floors Layout and Details 14 07-Nov-12 27-Nov-12 19-Feb-13 10-Mar-13 70 A122190 Approval of Mirror Details 14 03-Dec-12 20-Dec-12 20-Feb-13 11-Mar-13 55 A122210 Approval of Doors Details 14 03-Dec-12 20-Dec-12 12-Feb-13 03-Mar-13 49 A122160 Approval of Vanity Counter Details 14 26-Dec-12 15-Jan-13 21-Feb-13 12-Mar-13 39 A122230 Approval of Carpet Flooring Details 14 25-Feb-13 14-Mar-13 26-Mar-13 14-Apr-13 21 A122270 Approval of Sinage Layout and Details 14 25-Feb-13 14-Mar-13 01-Apr-13 18-Apr-13 25 A122280 Approval of Furniture Layout and Detals 14 11-Jun-13 30-Jun-13 10-Jul-13 29-Jul-13 21 Roof - UppeRoof - Upper Roof Floor 32 29-Aug-12 04-Oct-12 29-Nov-12 21-Apr-13 164 GeneralGeneral 32 29-Aug-12 04-Oct-12 29-Nov-12 21-Apr-13 164 SubmissiSubmission 16 29-Aug-12 16-Sep-12 29-Nov-12 01-Apr-13 163 A123070 Submission of Block Work Setting Out Plan for Roof&Upper ... 8 29-Aug-12 06-Sep-12 29-Nov-12 09-Dec-12 76 A122970 Submission of Roof's Water Proofing System 8 08-Sep-12 16-Sep-12 07-Feb-13 16-Feb-13 125 A123000 Submission of Doors Details 8 08-Sep-12 16-Sep-12 24-Mar-13 01-Apr-13 163 A123030 Submission of Flooring Layout 8 08-Sep-12 16-Sep-12 06-Jan-13 14-Jan-13 98 ApprovalApproval 20 09-Sep-12 04-Oct-12 10-Dec-12 21-Apr-13 136 A123160 Approval of Block Work Setting Out Plan for for Roof&Upper ... 14 09-Sep-12 26-Sep-12 10-Dec-12 27-Dec-12 63 A123090 Approval of Roof's Water Proofing System 14 17-Sep-12 04-Oct-12 17-Feb-13 06-Mar-13 104 A123120 Approval of Doors Details 14 17-Sep-12 04-Oct-12 02-Apr-13 21-Apr-13 136 A123150 Approval of Flooring Layout 14 17-Sep-12 04-Oct-12 15-Jan-13 04-Feb-13 82 Residentail (BResidentail (Block C) 383 05-Apr-12 07-Jul-13 26-Apr-12 29-Jul-13 19 2nd Baseme2nd Basement Floor 222 05-Apr-12 27-Dec-12 26-Apr-12 08-Apr-13 85 SubmissionSubmission 206 05-Apr-12 09-Dec-12 26-Apr-12 19-Mar-13 84 A121110 Submission of Block Work Setting Out Plan for 2nd Basement 8 05-Apr-12 14-Apr-12 26-Apr-12 05-May-12 18 A121230 Submission of Staircase Layout & Details 8 20-May-12 28-May-12 26-Dec-12 05-Jan-13 182 A121150 Submission of Doors Details 8 31-May-12 09-Jun-12 20-Jan-13 29-Jan-13 192 A121240 Submission of Handrail Layout & Details 8 31-May-12 09-Jun-12 30-Dec-12 08-Jan-13 175 A121140 Submission of Flooring 8 12-Jun-12 21-Jun-12 17-Jan-13 27-Jan-13 180 A121160 Submission of Reflected Ceiling Layout 8 12-Jun-12 21-Jun-12 14-Nov-12 24-Nov-12 128 A121200 Submission of Sinage Layout and Details 8 05-Sep-12 13-Sep-12 11-Mar-13 19-Mar-13 154 A121180 Submission of Parking Layout 8 29-Nov-12 09-Dec-12 03-Feb-13 11-Feb-13 53 A121190 Submission of Traffic Sign Layout 8 29-Nov-12 09-Dec-12 03-Feb-13 11-Feb-13 53 ApprovalApproval 179 15-Apr-12 27-Dec-12 20-Sep-12 08-Apr-13 70 A121390 Approval of Block Work Setting Out Plan for 2nd Basement 14 15-Apr-12 02-May-12 20-Sep-12 09-Oct-12 111 A121370 Approval of Staircase Layout & Details 14 29-May-12 18-Jun-12 06-Jan-13 23-Jan-13 151 A121380 Approval of Handrail Layout & Details 14 10-Jun-12 28-Jun-12 09-Jan-13 29-Jan-13 146 A121430 Approval of Doors Details 14 10-Jun-12 28-Jun-12 30-Jan-13 18-Feb-13 160 A121420 Approval of Flooring 14 24-Jun-12 11-Jul-12 28-Jan-13 14-Feb-13 149 A121440 Approval of Reflected Ceiling Layout 14 24-Jun-12 11-Jul-12 25-Nov-12 13-Dec-12 106 A121480 Approval of Sinage Layout and Details 14 16-Sep-12 03-Oct-12 20-Mar-13 08-Apr-13 128 A121460 Approval of Parking Layout 14 10-Dec-12 27-Dec-12 12-Feb-13 03-Mar-13 44 A121470 Approval of Traffic Sign Layout 14 10-Dec-12 27-Dec-12 12-Feb-13 03-Mar-13 44 1st Baseme1st Basement Floor 203 20-May-12 20-Jan-13 10-Jun-12 14-Apr-13 71 SubmissionSubmission 186 20-May-12 30-Dec-12 10-Jun-12 25-Mar-13 71 A121510 Submission of Block Work Setting Out Plan for 1st Basement 8 20-May-12 28-May-12 10-Jun-12 19-Jun-12 18 A121560 Submission of Reflected Ceiling Layout 8 23-Jun-12 01-Jul-12 25-Nov-12 04-Dec-12 128 A121630 Submission of Staircase Layout & Details 8 23-Jun-12 01-Jul-12 26-Dec-12 05-Jan-13 154 A121640 Submission of Handrail Layout & Details 8 23-Jun-12 01-Jul-12 30-Dec-12 08-Jan-13 157 A121540 Submission of Flooring 8 04-Jul-12 12-Jul-12 21-Jan-13 30-Jan-13 165 A121550 Submission of Doors Details 8 16-Jul-12 24-Jul-12 28-Jan-13 05-Feb-13 160 A121600 Submission of Sinage Layout and Details 8 15-Sep-12 23-Sep-12 17-Mar-13 25-Mar-13 151 A121580 Submission of Parking Layout 8 22-Dec-12 30-Dec-12 03-Feb-13 11-Feb-13 35 A121590 Submission of Traffic Sign Layout 8 22-Dec-12 30-Dec-12 03-Feb-13 11-Feb-13 35 ApprovalApproval 162 29-May-12 20-Jan-13 21-Oct-12 14-Apr-13 59 A121670 Approval of Block Work Setting Out Plan for 1st Basement 14 29-May-12 18-Jun-12 21-Oct-12 08-Nov-12 100 A121650 Approval of Staircase Layout & Details 14 02-Jul-12 19-Jul-12 06-Jan-13 23-Jan-13 128 A121660 Approval of Handrail Layout & Details 14 02-Jul-12 19-Jul-12 09-Jan-13 29-Jan-13 131 A121720 Approval of Reflected Ceiling Layout 14 02-Jul-12 19-Jul-12 05-Dec-12 24-Dec-12 107 A121700 Approval of Flooring 14 15-Jul-12 01-Aug-12 31-Jan-13 19-Feb-13 137 A121710 Approval of Doors Details 14 25-Jul-12 13-Aug-12 06-Feb-13 25-Feb-13 133 A121760 Approval of Sinage Layout and Details 14 24-Sep-12 11-Oct-12 26-Mar-13 14-Apr-13 126 A121740 Approval of Parking Layout 14 31-Dec-12 20-Jan-13 12-Feb-13 03-Mar-13 29 A121750 Approval of Traffic Sign Layout 14 31-Dec-12 20-Jan-13 12-Feb-13 03-Mar-13 29 Ground FloGround Floor 133 23-Jun-12 29-Nov-12 14-Jul-12 11-Apr-13 111 SubmissionSubmission 116 23-Jun-12 08-Nov-12 14-Jul-12 24-Mar-13 112 A120780 Submission of Block Work Setting Out Plan for Ground 8 23-Jun-12 01-Jul-12 14-Jul-12 22-Jul-12 18 A121250 Submission of Staircase Layout & Details 8 02-Jul-12 10-Jul-12 28-Jan-13 05-Feb-13 172 A120750 Submission of Flooring Layout 8 08-Jul-12 16-Jul-12 18-Dec-12 26-Dec-12 134 A120740 Submission of Reflected Ceiling Layout 8 19-Jul-12 28-Jul-12 23-Dec-12 31-Dec-12 128 A121260 Submission of Handrail Layout & Details 8 19-Jul-12 28-Jul-12 02-Feb-13 10-Feb-13 161 A120760 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 06-Aug-12 14-Aug-12 29-Jan-13 06-Feb-13 143 A120720 Submission of Doors Details 8 01-Sep-12 09-Sep-12 02-Feb-13 10-Feb-13 126 A120730 Submission of Sinage Layout and Details 8 31-Oct-12 08-Nov-12 16-Mar-13 24-Mar-13 112 ApprovalApproval 105 02-Jul-12 29-Nov-12 11-Nov-12 11-Apr-13 92 A120860 Approval of Block Work Setting Out Plan for Ground 14 02-Jul-12 19-Jul-12 11-Nov-12 29-Nov-12 91 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Submission of Sinage Layout and Details Submission of Irrigation Layout & Details Submission of Sky Light Details Submission of Carpet Flooring Details Submission of Furniture Layout and Det Approval of Reflected Ceiling Layout Approval of Landscaping's Water Proofing Details Approval of Doors Details Approval of Landscaping Layout & Details Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Pool Deck Layout Approval of Flooring Layout Approval of Sinage Layout and Details Approval of Irrigation Layout & Details Approval of Sky Light Details Approval of Carpet Flooring Details Approval of Furniture Layout and De Submission of Reflected Ceiling Layout Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Mirror Details Submission of Doors Details Submission of Vanity Counter Details Submission of Carpet Flooring Details Submission of Sinage Layout and Details Submission of Furniture Layout and Det Approval of Reflected Ceiling Layout Approval of Wet Area Ceramic & Pocalin Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Mirror Details Approval of Doors Details Approval of Vanity Counter Details Approval of Carpet Flooring Details Approval of Sinage Layout and Details Approval of Furniture Layout and De Submission of Block Work Setting Out Plan for Roof&Upper Roof Submission of Roof's Water Proofing System Submission of Doors Details Submission of Flooring Layout Approval of Block Work Setting Out Plan for for Roof&Upper Roof Approval of Roof's Water Proofing System Approval of Doors Details Approval of Flooring Layout Submission of Block Work Setting Out Plan for 2nd Basement Submission of Staircase Layout & Details Submission of Doors Details Submission of Handrail Layout & Details Submission of Flooring Submission of Reflected Ceiling Layout Submission of Sinage Layout and Details Submission of Parking Layout Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 2nd Basement Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Doors Details Approval of Flooring Approval of Reflected Ceiling Layout Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for 1st Basement Submission of Reflected Ceiling Layout Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Flooring Submission of Doors Details Submission of Sinage Layout and Details Submission of Parking Layout Submission of Traffic Sign Layout Approval of Block Work Setting Out Plan for 1st Basement Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Reflected Ceiling Layout Approval of Flooring Approval of Doors Details Approval of Sinage Layout and Details Approval of Parking Layout Approval of Traffic Sign Layout Submission of Block Work Setting Out Plan for Ground Submission of Staircase Layout & Details Submission of Flooring Layout Submission of Reflected Ceiling Layout Submission of Handrail Layout & Details Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Doors Details Submission of Sinage Layout and Details Approval of Block Work Setting Out Plan for Ground Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 8 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 9. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A121350 Approval of Staircase Layout & Details 14 11-Jul-12 30-Jul-12 06-Feb-13 25-Feb-13 143 A120830 Approval of Flooring Layout 14 17-Jul-12 05-Aug-12 27-Dec-12 16-Jan-13 112 A120820 Approval of Reflected Ceiling Layout 14 29-Jul-12 15-Aug-12 02-Jan-13 21-Jan-13 107 A121360 Approval of Handrail Layout & Details 14 29-Jul-12 15-Aug-12 11-Feb-13 28-Feb-13 134 A120840 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 15-Aug-12 05-Sep-12 07-Feb-13 26-Feb-13 119 A120800 Approval of Doors Details 14 10-Sep-12 27-Sep-12 11-Feb-13 28-Feb-13 105 A120810 Approval of Sinage Layout and Details 14 11-Nov-12 29-Nov-12 25-Mar-13 11-Apr-13 92 Typical FlooTypical Floors 163 02-Jul-12 15-Jan-13 23-Jul-12 14-Apr-13 75 GeneralGeneral 79 02-Jul-12 03-Oct-12 23-Jul-12 27-Nov-12 44 SubmissiSubmission 62 02-Jul-12 13-Sep-12 23-Jul-12 06-Nov-12 44 A119930 Submission of Block Work Setting Out Plan for 1st Floor 8 02-Jul-12 10-Jul-12 23-Jul-12 31-Jul-12 18 A119690 Submission of Block Work Setting Out Plan for 2nd Floor 8 11-Jul-12 19-Jul-12 12-Aug-12 22-Aug-12 27 A119700 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 21-Jul-12 29-Jul-12 30-Aug-12 08-Sep-12 33 A119710 Submission of Block Work Setting Out Plan for 7th Floor 8 05-Sep-12 13-Sep-12 29-Oct-12 06-Nov-12 44 ApprovalApproval 59 11-Jul-12 03-Oct-12 07-Aug-12 27-Nov-12 37 A119970 Approval of Block Work Setting Out Plan for 1st Floor 14 11-Jul-12 30-Jul-12 07-Aug-12 28-Aug-12 19 A119940 Approval of Block Work Setting Out Plan for 2nd Floor 14 22-Jul-12 08-Aug-12 23-Aug-12 11-Sep-12 22 A119950 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 30-Jul-12 16-Aug-12 09-Sep-12 26-Sep-12 27 A119960 Approval of Block Work Setting Out Plan for 7th Floor 14 16-Sep-12 03-Oct-12 07-Nov-12 27-Nov-12 37 Corridor / GCorridor / General 105 04-Aug-12 10-Dec-12 08-Dec-12 11-Apr-13 103 SubmissiSubmission 88 04-Aug-12 19-Nov-12 08-Dec-12 24-Mar-13 104 A121270 Submission of Staircase Layout & Details 8 04-Aug-12 12-Aug-12 08-Jan-13 16-Jan-13 128 A121280 Submission of Handrail Layout & Details 8 04-Aug-12 12-Aug-12 12-Jan-13 20-Jan-13 131 A119890 Submission of Reflected Ceiling Layout 8 16-Sep-12 24-Sep-12 08-Dec-12 16-Dec-12 67 A119860 Submission of Doors Details 8 29-Oct-12 06-Nov-12 21-Jan-13 30-Jan-13 69 A119880 Submission of Sinage Layout and Details 8 29-Oct-12 06-Nov-12 16-Mar-13 24-Mar-13 114 A119910 Submission of Flooring Layout 8 10-Nov-12 19-Nov-12 17-Jan-13 27-Jan-13 56 ApprovalApproval 81 13-Aug-12 10-Dec-12 17-Dec-12 11-Apr-13 86 A121330 Approval of Staircase Layout & Details 14 13-Aug-12 03-Sep-12 17-Jan-13 06-Feb-13 107 A121340 Approval of Handrail Layout & Details 14 13-Aug-12 03-Sep-12 21-Jan-13 10-Feb-13 109 A120020 Approval of Reflected Ceiling Layout 14 25-Sep-12 14-Oct-12 17-Dec-12 06-Jan-13 56 A119990 Approval of Doors Details 14 07-Nov-12 27-Nov-12 31-Jan-13 19-Feb-13 57 A120010 Approval of Sinage Layout and Details 14 07-Nov-12 27-Nov-12 25-Mar-13 11-Apr-13 94 A120040 Approval of Flooring Layout 14 20-Nov-12 10-Dec-12 28-Jan-13 14-Feb-13 46 One Bed ROne Bed Room Apartements 105 10-Sep-12 15-Jan-13 14-Nov-12 14-Apr-13 75 SubmissiSubmission 88 10-Sep-12 25-Dec-12 14-Nov-12 25-Mar-13 75 A119800 Submission of Wet Area Ceramic & Pocalin Layout 8 10-Sep-12 18-Sep-12 19-Jan-13 28-Jan-13 107 A119760 Submission of Reflected Ceiling Layout 8 22-Sep-12 30-Sep-12 14-Nov-12 24-Nov-12 44 A119740 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 13-Dec-12 22-Dec-12 37 A119780 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 08-Jan-13 16-Jan-13 48 A119720 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 04-Feb-13 12-Feb-13 50 A119750 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 04-Feb-13 12-Feb-13 50 A119770 Submission of Doors Details 8 05-Dec-12 13-Dec-12 26-Jan-13 03-Feb-13 42 A119830 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 17-Mar-13 25-Mar-13 85 A119730 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 03-Feb-13 11-Feb-13 39 ApprovalApproval 81 19-Sep-12 15-Jan-13 25-Nov-12 14-Apr-13 62 A120140 Approval of Wet Area Ceramic & Pocalin Layout 14 19-Sep-12 08-Oct-12 29-Jan-13 17-Feb-13 89 A120100 Approval of Reflected Ceiling Layout 14 01-Oct-12 18-Oct-12 25-Nov-12 13-Dec-12 37 A120080 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 23-Dec-12 10-Jan-13 30 A120120 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 17-Jan-13 06-Feb-13 40 A120060 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 13-Feb-13 04-Mar-13 41 A120090 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 13-Feb-13 04-Mar-13 41 A120110 Approval of Doors Details 14 16-Dec-12 03-Jan-13 04-Feb-13 21-Feb-13 34 A120170 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 26-Mar-13 14-Apr-13 70 A120070 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 12-Feb-13 03-Mar-13 32 Two Bed RTwo Bed Room Apartements 125 15-Aug-12 15-Jan-13 20-Oct-12 08-Apr-13 70 SubmissiSubmission 108 15-Aug-12 25-Dec-12 20-Oct-12 19-Mar-13 70 A120270 Submission of Wet Area Ceramic & Pocalin Layout 8 15-Aug-12 26-Aug-12 23-Jan-13 02-Feb-13 131 A120230 Submission of Reflected Ceiling Layout 8 22-Sep-12 30-Sep-12 20-Oct-12 30-Oct-12 24 A120210 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 29-Nov-12 09-Dec-12 26 A120250 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 26-Dec-12 05-Jan-13 38 A120190 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 11-Feb-13 19-Feb-13 56 A120220 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54 A120240 Submission of Doors Details 8 05-Dec-12 13-Dec-12 27-Jan-13 04-Feb-13 43 A120300 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 11-Mar-13 19-Mar-13 80 A120200 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 07-Feb-13 16-Feb-13 43 ApprovalApproval 98 27-Aug-12 15-Jan-13 31-Oct-12 08-Apr-13 58 A120400 Approval of Wet Area Ceramic & Pocalin Layout 14 27-Aug-12 13-Sep-12 03-Feb-13 20-Feb-13 109 A120360 Approval of Reflected Ceiling Layout 14 01-Oct-12 18-Oct-12 31-Oct-12 20-Nov-12 21 A120340 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 10-Dec-12 27-Dec-12 21 A120380 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 06-Jan-13 23-Jan-13 31 A120320 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 20-Feb-13 11-Mar-13 46 A120350 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44 A120370 Approval of Doors Details 14 16-Dec-12 03-Jan-13 05-Feb-13 24-Feb-13 35 A120430 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 20-Mar-13 08-Apr-13 66 A120330 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 17-Feb-13 06-Mar-13 35 Three BedThree Bed Room Apartements 125 15-Aug-12 15-Jan-13 02-Oct-12 08-Apr-13 70 SubmissiSubmission 108 15-Aug-12 25-Dec-12 02-Oct-12 19-Mar-13 70 A120530 Submission of Wet Area Ceramic & Pocalin Layout 8 15-Aug-12 26-Aug-12 17-Jan-13 27-Jan-13 126 A120490 Submission of Reflected Ceiling Layout 8 29-Aug-12 06-Sep-12 02-Oct-12 10-Oct-12 29 A120470 Submission of Wardrobe Details 8 29-Oct-12 06-Nov-12 20-Nov-12 28-Nov-12 18 A120510 Submission of Floors Layout and Details 8 10-Nov-12 19-Nov-12 15-Dec-12 23-Dec-12 28 A120450 Submission of Vanity Counter Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54 A120480 Submission of Mirror Details 8 05-Dec-12 13-Dec-12 09-Feb-13 17-Feb-13 54 A120500 Submission of Doors Details 8 05-Dec-12 13-Dec-12 21-Jan-13 30-Jan-13 39 A120560 Submission of Sinage Layout and Details 8 05-Dec-12 13-Dec-12 11-Mar-13 19-Mar-13 80 A120460 Submission of Kitchen Cabinet Details 8 17-Dec-12 25-Dec-12 28-Jan-13 05-Feb-13 34 ApprovalApproval 98 27-Aug-12 15-Jan-13 11-Oct-12 08-Apr-13 58 A120660 Approval of Wet Area Ceramic & Pocalin Layout for 14 27-Aug-12 13-Sep-12 28-Jan-13 14-Feb-13 105 A120620 Approval of Reflected Ceiling Layout 14 09-Sep-12 26-Sep-12 11-Oct-12 31-Oct-12 24 A120600 Approval of Wardrobe Details 14 07-Nov-12 27-Nov-12 29-Nov-12 19-Dec-12 15 A120640 Approval of Floors Layout and Details 14 20-Nov-12 10-Dec-12 24-Dec-12 13-Jan-13 23 A120580 Approval of Vanity Counter Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44 A120610 Approval of Mirror Details 14 16-Dec-12 03-Jan-13 18-Feb-13 07-Mar-13 44 A120630 Approval of Doors Details 14 16-Dec-12 03-Jan-13 31-Jan-13 19-Feb-13 32 A120690 Approval of Sinage Layout and Details 14 16-Dec-12 03-Jan-13 20-Mar-13 08-Apr-13 66 A120590 Approval of Kitchen Cabinet Details 14 26-Dec-12 15-Jan-13 06-Feb-13 25-Feb-13 28 Roof - UppeRoof - Upper Roof Floor 241 22-Sep-12 07-Jul-13 14-Oct-12 29-Jul-13 19 GeneralGeneral 83 22-Sep-12 31-Dec-12 14-Oct-12 27-Mar-13 72 SubmissiSubmission 66 22-Sep-12 11-Dec-12 14-Oct-12 09-Mar-13 73 A120970 Submission of Block Work Setting Out Plan for Roof & upper ... 8 22-Sep-12 30-Sep-12 14-Oct-12 22-Oct-12 19 A120870 Submission of Roof's Water Proofing System 8 01-Oct-12 09-Oct-12 06-Jan-13 14-Jan-13 78 A120880 Submission of Pool Deck Layout 8 07-Oct-12 15-Oct-12 09-Feb-13 17-Feb-13 101 A120900 Submission of Doors Details 8 07-Nov-12 17-Nov-12 23-Feb-13 03-Mar-13 88 A121290 Submission of Staircase Layout & Details 8 07-Nov-12 17-Nov-12 28-Jan-13 05-Feb-13 66 A120920 Submission of Wet Area Ceramic & Pocalin Layout for Toilets 8 03-Dec-12 11-Dec-12 25-Feb-13 05-Mar-13 70 A120930 Submission of Flooring Layout 8 03-Dec-12 11-Dec-12 28-Feb-13 09-Mar-13 73 A121300 Submission of Handrail Layout & Details 8 03-Dec-12 11-Dec-12 02-Feb-13 10-Feb-13 50 ApprovalApproval 63 01-Oct-12 31-Dec-12 25-Nov-12 27-Mar-13 60 A121060 Approval of Block Work Setting Out Plan for Ground 14 01-Oct-12 18-Oct-12 25-Nov-12 13-Dec-12 37 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Approval of Staircase Layout & Details Approval of Flooring Layout Approval of Reflected Ceiling Layout Approval of Handrail Layout & Details Approval of Wet Area Ceramic & Pocalin Layout for Toilets Approval of Doors Details Approval of Sinage Layout and Details Submission of Block Work Setting Out Plan for 1st Floor Submission of Block Work Setting Out Plan for 2nd Floor Submission of Block Work Setting Out Plan for 3rd to 6th Floor Submission of Block Work Setting Out Plan for 7th Floor Approval of Block Work Setting Out Plan for 1st Floor Approval of Block Work Setting Out Plan for 2nd Floor Approval of Block Work Setting Out Plan for 3rd to 6th Floor Approval of Block Work Setting Out Plan for 7th Floor Submission of Staircase Layout & Details Submission of Handrail Layout & Details Submission of Reflected Ceiling Layout Submission of Doors Details Submission of Sinage Layout and Details Submission of Flooring Layout Approval of Staircase Layout & Details Approval of Handrail Layout & Details Approval of Reflected Ceiling Layout Approval of Doors Details Approval of Sinage Layout and Details Approval of Flooring Layout Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Mirror Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Kitchen Cabinet Details Approval of Wet Area Ceramic & Pocalin Layout Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Mirror Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Kitchen Cabinet Details Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Mirror Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Kitchen Cabinet Details Approval of Wet Area Ceramic & Pocalin Layout Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Mirror Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Kitchen Cabinet Details Submission of Wet Area Ceramic & Pocalin Layout Submission of Reflected Ceiling Layout Submission of Wardrobe Details Submission of Floors Layout and Details Submission of Vanity Counter Details Submission of Mirror Details Submission of Doors Details Submission of Sinage Layout and Details Submission of Kitchen Cabinet Details Approval of Wet Area Ceramic & Pocalin Layout for Approval of Reflected Ceiling Layout Approval of Wardrobe Details Approval of Floors Layout and Details Approval of Vanity Counter Details Approval of Mirror Details Approval of Doors Details Approval of Sinage Layout and Details Approval of Kitchen Cabinet Details Submission of Block Work Setting Out Plan for Roof & upper Roof Submission of Roof's Water Proofing System Submission of Pool Deck Layout Submission of Doors Details Submission of Staircase Layout & Details Submission of Wet Area Ceramic & Pocalin Layout for Toilets Submission of Flooring Layout Submission of Handrail Layout & Details Approval of Block Work Setting Out Plan for Ground Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 9 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 10. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A120990 Approval of Roof's Water Proofing System 14 10-Oct-12 30-Oct-12 15-Jan-13 04-Feb-13 65 A121000 Approval of Pool Deck Layout 14 16-Oct-12 05-Nov-12 18-Feb-13 07-Mar-13 84 A121020 Approval of Doors Details 14 18-Nov-12 06-Dec-12 04-Mar-13 21-Mar-13 73 A121310 Approval of Staircase Layout & Details 14 18-Nov-12 06-Dec-12 06-Feb-13 25-Feb-13 55 A121040 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 12-Dec-12 31-Dec-12 06-Mar-13 25-Mar-13 58 A121050 Approval of Flooring Layout 14 12-Dec-12 31-Dec-12 10-Mar-13 27-Mar-13 60 A121320 Approval of Handrail Layout & Details 14 12-Dec-12 31-Dec-12 11-Feb-13 28-Feb-13 41 GymnasiumGymnasium 213 24-Oct-12 07-Jul-13 27-Dec-12 29-Jul-13 19 SubmissiSubmission 196 24-Oct-12 17-Jun-13 27-Dec-12 09-Jul-13 19 A120950 Submission of Reflected Ceiling Layout 8 24-Oct-12 04-Nov-12 27-Dec-12 06-Jan-13 51 A120980 Submission of Vinyl Floor Detals 8 08-Jan-13 16-Jan-13 31-Jan-13 09-Feb-13 19 A120960 Submission of Furniture Layout and Details 8 09-Jun-13 17-Jun-13 01-Jul-13 09-Jul-13 19 ApprovalApproval 170 05-Nov-12 07-Jul-13 07-Jan-13 29-Jul-13 16 A121080 Approval of Reflected Ceiling Layout 14 05-Nov-12 25-Nov-12 07-Jan-13 27-Jan-13 42 A121100 Approval of Vinyl Floor Detals 14 17-Jan-13 06-Feb-13 10-Mar-13 27-Mar-13 35 A121090 Approval of Furniture Layout and Detals 14 18-Jun-13 07-Jul-13 10-Jul-13 29-Jul-13 16 Speciality WSpeciality Works 235 05-May-12 12-Feb-13 07-Jun-12 05-Jun-13 97 Swimming PoSwimming Pool 78 03-Jul-12 03-Oct-12 26-Dec-12 20-Feb-13 114 SubmissionSubmission 62 03-Jul-12 15-Sep-12 26-Dec-12 02-Feb-13 114 A53720 Submission of Swimming Pool Layout & Details for Block A 12 03-Jul-12 16-Jul-12 13-Jan-13 27-Jan-13 159 A53730 Submission of Swimming Pool 's Water Prrofing for Block A 12 03-Jul-12 16-Jul-12 19-Jan-13 02-Feb-13 164 A118850 Submission of Swimming Pool Layout & Details for Block B 12 03-Jul-12 16-Jul-12 26-Dec-12 09-Jan-13 145 A118860 Submission of Swimming Pool 's Water Prrofing for Block B 12 03-Jul-12 16-Jul-12 02-Jan-13 15-Jan-13 150 A118870 Submission of Swimming Pool Layout & Details for Block C 12 02-Sep-12 15-Sep-12 03-Jan-13 16-Jan-13 101 A118880 Submission of Swimming Pool 's Water Prrofing for Block C 12 02-Sep-12 15-Sep-12 08-Jan-13 21-Jan-13 105 ApprovalApproval 55 17-Jul-12 03-Oct-12 10-Jan-13 20-Feb-13 95 A118900 Approval of Swimming Pool Layout & Details for Block A 14 17-Jul-12 05-Aug-12 28-Jan-13 14-Feb-13 132 A118910 Approval of Swimming Pool 's Water Prrofing for Block A 14 17-Jul-12 05-Aug-12 03-Feb-13 20-Feb-13 136 A118920 Approval of Swimming Pool Layout & Details for Block B 14 17-Jul-12 05-Aug-12 10-Jan-13 30-Jan-13 121 A118930 Approval of Swimming Pool 's Water Proofing for Block B 14 17-Jul-12 05-Aug-12 16-Jan-13 05-Feb-13 125 A118940 Approval of Swimming Pool Layout & Details for Block C 14 16-Sep-12 03-Oct-12 17-Jan-13 06-Feb-13 85 A118950 Approval of Swimming Pool 's Water Proofing for Block C 14 16-Sep-12 03-Oct-12 22-Jan-13 11-Feb-13 88 External FacaExternal Facade 165 26-Jul-12 12-Feb-13 16-Oct-12 15-May-13 79 Hotel ApartHotel Apartements (Block A) 135 26-Jul-12 07-Jan-13 16-Oct-12 27-Mar-13 67 SubmissionSubmission 118 26-Jul-12 17-Dec-12 16-Oct-12 09-Mar-13 68 A118250 Submission of External Elevation - North 10 26-Jul-12 06-Aug-12 16-Oct-12 29-Oct-12 68 A118260 Submission of External Elevation - South 10 26-Jul-12 06-Aug-12 14-Jan-13 26-Jan-13 140 A118290 Submission of Aluminum Curtain Wall Layout & Details 10 26-Jul-12 06-Aug-12 16-Oct-12 29-Oct-12 68 A118270 Submission of External Elevation - East 10 07-Aug-12 18-Aug-12 27-Jan-13 06-Feb-13 140 A118280 Submission of External Elevation - West 10 07-Aug-12 18-Aug-12 27-Jan-13 06-Feb-13 140 A118300 Submission of GRC Layout & Details 8 09-Dec-12 17-Dec-12 28-Feb-13 09-Mar-13 68 ApprovalApproval 104 07-Aug-12 07-Jan-13 07-Feb-13 27-Mar-13 56 A118310 Approval of External Elevation - North 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125 A118320 Approval of External Elevation - South 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125 A118350 Approval of Aluminum Curtain Wall Layout & Details 14 07-Aug-12 28-Aug-12 07-Feb-13 26-Feb-13 125 A118330 Approval of External Elevation - East 14 21-Aug-12 09-Sep-12 07-Feb-13 26-Feb-13 117 A118340 Approval of External Elevation - West 14 21-Aug-12 09-Sep-12 07-Feb-13 26-Feb-13 117 A118360 Approval of GRC Layout & Details 14 18-Dec-12 07-Jan-13 10-Mar-13 27-Mar-13 56 Hotel (BlocHotel (Block B) 135 02-Sep-12 12-Feb-13 09-Dec-12 15-May-13 79 SubmissionSubmission 118 02-Sep-12 22-Jan-13 09-Dec-12 27-Apr-13 80 A124230 Submission of External Elevation - North 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80 A124240 Submission of External Elevation - South 10 02-Sep-12 12-Sep-12 14-Jan-13 26-Jan-13 110 A124270 Submission of Aluminum Curtain Wall Layout & Details 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80 A124250 Submission of External Elevation - East 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110 A124260 Submission of External Elevation - West 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110 A124280 Submission of GRC Layout & Details 8 14-Jan-13 22-Jan-13 18-Apr-13 27-Apr-13 80 ApprovalApproval 104 13-Sep-12 12-Feb-13 07-Feb-13 15-May-13 66 A124290 Approval of External Elevation - North 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124300 Approval of External Elevation - South 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124330 Approval of Aluminum Curtain Wall Layout & Details 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124310 Approval of External Elevation - East 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92 A124320 Approval of External Elevation - West 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92 A124340 Approval of GRC Layout & Details 14 23-Jan-13 12-Feb-13 28-Apr-13 15-May-13 66 ResidentailResidentail (Block C) 135 02-Sep-12 12-Feb-13 09-Dec-12 15-May-13 79 SubmissionSubmission 118 02-Sep-12 22-Jan-13 09-Dec-12 27-Apr-13 80 A124350 Submission of External Elevation - North 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80 A124360 Submission of External Elevation - South 10 02-Sep-12 12-Sep-12 14-Jan-13 26-Jan-13 110 A124390 Submission of Aluminum Curtain Wall Layout & Details 10 02-Sep-12 12-Sep-12 09-Dec-12 19-Dec-12 80 A124370 Submission of External Elevation - East 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110 A124380 Submission of External Elevation - West 10 13-Sep-12 24-Sep-12 27-Jan-13 06-Feb-13 110 A124400 Submission of GRC Layout & Details 8 14-Jan-13 22-Jan-13 18-Apr-13 27-Apr-13 80 ApprovalApproval 104 13-Sep-12 12-Feb-13 07-Feb-13 15-May-13 66 A124410 Approval of External Elevation - North 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124420 Approval of External Elevation - South 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124450 Approval of Aluminum Curtain Wall Layout & Details 14 13-Sep-12 02-Oct-12 07-Feb-13 26-Feb-13 100 A124430 Approval of External Elevation - East 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92 A124440 Approval of External Elevation - West 14 25-Sep-12 14-Oct-12 07-Feb-13 26-Feb-13 92 A124460 Approval of GRC Layout & Details 14 23-Jan-13 12-Feb-13 28-Apr-13 15-May-13 66 Facade CleanFacade Cleaning 32 26-Nov-12 03-Jan-13 01-May-13 05-Jun-13 130 SubmissionSubmission 15 26-Nov-12 13-Dec-12 01-May-13 18-May-13 131 A118560 Submission of Glass Cleaning Machine 15 26-Nov-12 13-Dec-12 01-May-13 18-May-13 131 ApprovalApproval 14 16-Dec-12 03-Jan-13 19-May-13 05-Jun-13 108 A118960 Approval of Glass Cleaning Machine 14 16-Dec-12 03-Jan-13 19-May-13 05-Jun-13 108 Garbage ChuGarbage Chute 141 05-May-12 18-Oct-12 07-Jun-12 28-Nov-12 32 SubmissionSubmission 125 05-May-12 30-Sep-12 07-Jun-12 05-Nov-12 29 A118810 Submission of Garbage Chute Layout & Details for Block A 15 05-May-12 21-May-12 07-Jun-12 25-Jun-12 29 A118820 Submission of Garbage Chute Layout & Details for Block B 15 09-Jul-12 25-Jul-12 12-Aug-12 30-Aug-12 29 A118830 Submission of Garbage Chute Layout & Details for Block C 15 13-Sep-12 30-Sep-12 17-Oct-12 05-Nov-12 29 ApprovalApproval 105 22-May-12 18-Oct-12 24-Oct-12 28-Nov-12 27 A118970 Approval of Garbage Chute Layout & Details for Block A 14 22-May-12 10-Jun-12 24-Oct-12 13-Nov-12 108 A118980 Approval of Garbage Chute Layout & Details for Block B 14 26-Jul-12 14-Aug-12 08-Nov-12 28-Nov-12 72 A118990 Approval of Garbage Chute Layout & Details for Block C 14 01-Oct-12 18-Oct-12 06-Nov-12 26-Nov-12 25 Linen ChuteLinen Chute 32 03-Jul-12 08-Aug-12 20-Oct-12 28-Nov-12 91 SubmissionSubmission 15 03-Jul-12 19-Jul-12 20-Oct-12 07-Nov-12 91 A118840 Submission of Linen Chute Layout & Details for Block B 15 03-Jul-12 19-Jul-12 20-Oct-12 07-Nov-12 91 ApprovalApproval 14 22-Jul-12 08-Aug-12 08-Nov-12 28-Nov-12 76 A119000 Approval of Linen Chute Layout & Details for Block B 14 22-Jul-12 08-Aug-12 08-Nov-12 28-Nov-12 76 ProvisionalProvisional Sum 249 10-May-12 06-Mar-13 24-May-12 25-Apr-13 43 Kitchen EquiKitchen Equipments 36 10-May-12 21-Jun-12 26-May-12 08-Jul-12 14 SubmissionSubmission 20 10-May-12 02-Jun-12 26-May-12 18-Jun-12 13 A9983 Submission of Kitchen Equipments Drawings 20 10-May-12 02-Jun-12 26-May-12 18-Jun-12 13 ApprovalApproval 14 03-Jun-12 21-Jun-12 19-Jun-12 08-Jul-12 11 A9984 Approval of Kitchen Equipments Drawings 14 03-Jun-12 21-Jun-12 19-Jun-12 08-Jul-12 11 Lundary EquLundary Equipments 36 10-May-12 21-Jun-12 24-May-12 05-Jul-12 12 SubmissionSubmission 20 10-May-12 02-Jun-12 24-May-12 16-Jun-12 12 A9986 Submission of Laundary Equipments Drawings 20 10-May-12 02-Jun-12 24-May-12 16-Jun-12 12 ApprovalApproval 14 03-Jun-12 21-Jun-12 18-Jun-12 05-Jul-12 10 A9987 Approval of Laundary Equipments Drawings 14 03-Jun-12 21-Jun-12 18-Jun-12 05-Jul-12 10 Facade LightFacade Lighting 37 16-May-12 28-Jun-12 09-Jun-12 22-Jul-12 20 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Approval of Roof's Water Proofing System Approval of Pool Deck Layout Approval of Doors Details Approval of Staircase Layout & Details Approval of Wet Area Ceramic & Pocalin Layout for Toilets Approval of Flooring Layout Approval of Handrail Layout & Details Submission of Reflected Ceiling Layout Submission of Vinyl Floor Detals Submission of Furniture Layout and De Approval of Reflected Ceiling Layout Approval of VinylFloor Detals Approval of Furniture Layout and D Submission of Swimming Pool Layout & Details for Block A Submission of Swimming Pool 's Water Prrofing for Block A Submission of Swimming Pool Layout & Details for Block B Submission of Swimming Pool 's Water Prrofing for Block B Submission of Swimming Pool Layout & Details for Block C Submission of Swimming Pool 's Water Prrofing for Block C Approval of Swimming Pool Layout & Details for Block A Approval of Swimming Pool 's Water Prrofing for Block A Approval of Swimming Pool Layout & Details for Block B Approval of Swimming Pool 's Water Proofing for Block B Approval of Swimming Pool Layout & Details for Block C Approval of Swimming Pool 's Water Proofing for Block C Submission of External Elevation - North Submission of External Elevation - South Submission of Aluminum Curtain Wall Layout & Details Submission of External Elevation - East Submission of External Elevation - West Submission of GRC Layout & Details Approval of External Elevation - North Approval of External Elevation - South Approval of Aluminum Curtain Wall Layout & Details Approval of External Elevation - East Approval of External Elevation - West Approval of GRC Layout & Details Submission of External Elevation - North Submission of External Elevation - South Submission of Aluminum Curtain Wall Layout & Details Submission of External Elevation - East Submission of External Elevation - West Submission of GRC Layout & Details Approval of External Elevation - North Approval of External Elevation - South Approval of Aluminum Curtain Wall Layout & Details Approval of External Elevation - East Approval of External Elevation - West Approval of GRC Layout & Details Submission of External Elevation - North Submission of External Elevation - South Submission of Aluminum Curtain Wall Layout & Details Submission of External Elevation - East Submission of External Elevation - West Submission of GRC Layout & Details Approval of External Elevation - North Approval of External Elevation - South Approval of Aluminum Curtain Wall Layout & Details Approval of External Elevation - East Approval of External Elevation - West Approval of GRC Layout & Details Submission of Glass Cleaning Machine Approval of Glass Cleaning Machine Submission of Garbage Chute Layout & Details for Block A Submission of Garbage Chute Layout & Details for Block B Submission of Garbage Chute Layout & Details for Block C Approval of Garbage Chute Layout & Details for Block A Approval of Garbage Chute Layout & Details for Block B Approval of Garbage Chute Layout & Details for Block C Submission of Linen Chute Layout & Details for Block B Approval of Linen Chute Layout & Details for Block B Submission of Kitchen Equipments Drawings Approval of Kitchen Equipments Drawings Submission of Laundary Equipments Drawings Approval of Laundary Equipments Drawings Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 10 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 11. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float SubmissionSubmission 20 16-May-12 07-Jun-12 09-Jun-12 02-Jul-12 20 A9988 Submission of Facade Lighitng Drawings 20 16-May-12 07-Jun-12 09-Jun-12 02-Jul-12 20 ApprovalApproval 14 10-Jun-12 28-Jun-12 03-Jul-12 22-Jul-12 16 A9991 Approval of Facade Lighitng Drawings 14 10-Jun-12 28-Jun-12 03-Jul-12 22-Jul-12 16 Cooking StatCooking Station 37 26-May-12 08-Jul-12 11-Sep-12 23-Oct-12 90 SubmissionSubmission 20 26-May-12 18-Jun-12 11-Sep-12 03-Oct-12 90 A124680 Submission of Cooking Station Drawings 20 26-May-12 18-Jun-12 11-Sep-12 03-Oct-12 90 ApprovalApproval 14 19-Jun-12 08-Jul-12 04-Oct-12 23-Oct-12 75 A124690 Approval of Cooking Station Drawings 14 19-Jun-12 08-Jul-12 04-Oct-12 23-Oct-12 75 Gymnasium EGymnasium Equipments 34 27-Jan-13 06-Mar-13 18-Mar-13 25-Apr-13 43 SubmissionSubmission 20 27-Jan-13 18-Feb-13 18-Mar-13 09-Apr-13 43 A9977 Submission of Gymnasium Drawings 20 27-Jan-13 18-Feb-13 18-Mar-13 09-Apr-13 43 ApprovalApproval 14 19-Feb-13 06-Mar-13 10-Apr-13 25-Apr-13 43 A9944 Approval of Gymnasium Drawings 14 19-Feb-13 06-Mar-13 10-Apr-13 25-Apr-13 43 Method 0f SMethod 0f Statements 333 04-Jan-12 06-Feb-13 09-Jan-12 05-Jun-13 102 CivilCivil 98 04-Jan-12 28-Apr-12 09-Jan-12 09-Sep-12 112 A46480 Sub & App- MOS for Raft Slab Construction 14 04-Jan-12 19-Jan-12 09-Jan-12 24-Jan-12 4 A46520 Sub & App- MOS for Columns Construction 30 04-Jan-12 08-Feb-12 10-Jan-12 14-Feb-12 5 A46530 Sub & App- MOS for Retaining Walls Construction 30 04-Jan-12 08-Feb-12 10-Jan-12 14-Feb-12 5 A46560 Sub & App- MOS for Core Walls Constrcution 30 05-Jan-12 09-Feb-12 11-Jan-12 15-Feb-12 5 A46510 Sub & App- MOS for Slabs Construction 30 07-Jan-12 11-Feb-12 15-Jan-12 19-Feb-12 7 A46540 Sub & App- MOS for Ramp Construction 30 08-Jan-12 12-Feb-12 22-Jan-12 26-Feb-12 12 A46500 Sub & App- MOS for Backfilling 30 13-Mar-12 16-Apr-12 04-Aug-12 09-Sep-12 122 A46550 Sub & App- MOS for Staircase Construction 30 25-Mar-12 28-Apr-12 02-Aug-12 08-Sep-12 111 ArchitecturalArchitectural 135 07-Feb-12 14-Jul-12 23-Aug-12 05-Mar-13 193 A46570 Sub & App- MOS for Blocks Works 30 07-Feb-12 12-Mar-12 28-Aug-12 01-Oct-12 171 A46580 Sub & App- MOS for Plaster Works 30 07-Feb-12 12-Mar-12 10-Sep-12 14-Oct-12 182 A46600 Sub & App- MOS for Panintng 30 13-Mar-12 16-Apr-12 11-Oct-12 18-Nov-12 179 A46610 Sub & App- MOS for Wall&Floor Tiles 30 25-Mar-12 28-Apr-12 23-Aug-12 26-Sep-12 127 A46620 Sub & App- MOS for Suspended Ceiling System 30 11-Apr-12 15-May-12 20-Dec-12 26-Jan-13 210 A46650 Sub & App- MOS for Doors 30 17-Apr-12 21-May-12 30-Jan-13 05-Mar-13 238 A46630 Sub & App- MOS for Water Proofing for Wet Areas 30 19-Apr-12 23-May-12 25-Dec-12 30-Jan-13 207 A46590 Sub & App- MOS for GRP Lining 30 09-Jun-12 14-Jul-12 03-Oct-12 08-Nov-12 97 MEPMEP 130 01-Feb-12 03-Jul-12 26-Nov-12 25-Feb-13 195 HVACHVAC 60 12-Apr-12 21-Jun-12 06-Dec-12 21-Jan-13 176 A113860 Sub & App- MOS for Piping Works 30 12-Apr-12 16-May-12 06-Dec-12 10-Jan-13 197 A113840 Sub & App- MOS for Duct Works 30 24-Apr-12 28-May-12 11-Dec-12 15-Jan-13 191 A113850 Sub & App- MOS for Fan Coil Instllation 30 17-May-12 21-Jun-12 17-Dec-12 21-Jan-13 176 ElectricalElectrical 30 17-May-12 21-Jun-12 05-Dec-12 09-Jan-13 166 A113870 Sub & App- MOS for MDBs,SMDBs,DBs Installation 30 17-May-12 21-Jun-12 05-Dec-12 09-Jan-13 166 PlumbingPlumbing 130 01-Feb-12 03-Jul-12 19-Dec-12 25-Feb-13 195 A113880 Sub & App- MOS for Pipings 30 01-Feb-12 07-Mar-12 19-Dec-12 23-Jan-13 268 A113890 Sub & App- MOS for Sanitarywares 30 29-May-12 03-Jul-12 21-Jan-13 25-Feb-13 195 Fire FightingFire Fighting 60 12-Apr-12 21-Jun-12 26-Nov-12 31-Jan-13 184 A113910 Sub & App- MOS for Pipings 30 12-Apr-12 16-May-12 26-Nov-12 31-Dec-12 189 A113920 Sub & App- MOS for Testing 30 12-Apr-12 16-May-12 12-Dec-12 16-Jan-13 202 A113930 Sub & App- MOS for Fire Alarm Devices Fixing 30 17-May-12 21-Jun-12 26-Dec-12 31-Jan-13 184 Speciality WSpeciality Works 160 26-Jul-12 06-Feb-13 08-Oct-12 05-Jun-13 102 SwimmimngSwimmimng Pool 49 07-Aug-12 04-Oct-12 31-Dec-12 16-Mar-13 133 A113810 Sub & App- MOS for Water Proofing 30 07-Aug-12 12-Sep-12 31-Dec-12 05-Feb-13 119 A113820 Sub & App- MOS for Tiling 30 01-Sep-12 04-Oct-12 10-Feb-13 16-Mar-13 133 Facade CleanFacade Cleaning System 30 02-Jan-13 06-Feb-13 02-May-13 05-Jun-13 102 A124200 Sub & App- MOS for Facade Cleaning 30 02-Jan-13 06-Feb-13 02-May-13 05-Jun-13 102 Linen ChuteLinen Chute System 50 26-Jul-12 24-Sep-12 08-Oct-12 20-Dec-12 71 A113790 Sub & App- MOS for Piping Installation 30 26-Jul-12 01-Sep-12 08-Oct-12 13-Nov-12 61 A113800 Sub & App- MOS for Equipment Installation 30 21-Aug-12 24-Sep-12 14-Nov-12 20-Dec-12 71 Garbage ChuGarbage Chutes System 50 07-Aug-12 06-Oct-12 22-Oct-12 05-Jan-13 73 A53930 Sub & App- MOS for Piping Installation 30 07-Aug-12 12-Sep-12 22-Oct-12 28-Nov-12 63 A104200 Sub & App- MOS for Equipment Installation 30 02-Sep-12 06-Oct-12 29-Nov-12 05-Jan-13 73 ProcuremeProcurement 441 02-Jan-12 11-Jun-13 09-Jan-12 29-Jul-13 41 Submittion &Submittion & Approval of Prequalification 325 02-Jan-12 26-Jan-13 09-Jan-12 17-Mar-13 43 Domestic SuDomestic Sub Contractors 165 02-Jan-12 14-Jul-12 09-Jan-12 03-Nov-12 92 A8500 Sub & App- Water Proofing Works Subcontractor 2 02-Jan-12 03-Jan-12 09-Jan-12 10-Jan-12 6 A8600 Sub & App- LPG System Subcontractor 21 02-Jan-12 25-Jan-12 20-Jun-12 14-Jul-12 144 A8460 Sub & App- MEP Subcontractor 21 08-Jan-12 31-Jan-12 05-Mar-12 28-Mar-12 48 A8540 Sub & App- Susbended Ceilings Subcontractor 35 02-Jan-12 12-Feb-12 04-Mar-12 12-Apr-12 52 A8480 Sub & App- Garbage Chute System Subcontractor 35 07-Feb-12 18-Mar-12 12-Mar-12 21-Apr-12 29 A8470 Sub & App- Elevators Subcontractor 35 19-Feb-12 29-Mar-12 21-Mar-12 30-Apr-12 27 A8560 Sub & App- GRP Lining Subcontractor 35 13-Mar-12 22-Apr-12 23-Jun-12 01-Aug-12 86 A8444 Sub & App- Linen Chute System Subcontractor 35 13-Mar-12 22-Apr-12 02-Apr-12 12-May-12 17 A8490 Sub & App- Swimming PoolWorks Subcontractor 35 17-Apr-12 27-May-12 26-Apr-12 05-Jun-12 8 A8530 Sub & App- Wood & Joinery Subcontractor 35 17-Apr-12 27-May-12 29-May-12 09-Jul-12 36 A8590 Sub & App- Landscaping Subcontractor 35 17-Apr-12 27-May-12 31-May-12 11-Jul-12 38 A8520 Sub & App- Aluminum&Glazing Works Subcontractor 35 10-May-12 20-Jun-12 30-Jul-12 10-Sep-12 68 A8510 Sub & App- Facade Cleanining Subcontractor 35 22-May-12 02-Jul-12 22-Sep-12 03-Nov-12 102 A8580 Sub & App- Traffic Deck Coating Subcontractor 35 03-Jun-12 14-Jul-12 22-Aug-12 01-Oct-12 66 A8999 Sub & App- Irrigation Works Subcontractor 35 03-Jun-12 14-Jul-12 27-Aug-12 06-Oct-12 70 Nominated SNominated Sub Contractors 236 16-Apr-12 26-Jan-13 30-Apr-12 17-Mar-13 43 Kitchen EquiKitchen Equipments 21 16-Apr-12 09-May-12 01-May-12 24-May-12 13 A8610 Sub & App- Kitchen Equipments Subcontractor 21 16-Apr-12 09-May-12 01-May-12 24-May-12 13 Lundary EquLundary Equipments 21 16-Apr-12 09-May-12 30-Apr-12 23-May-12 12 A114230 Sub & App- Laundary Equipments Subcontractor 21 16-Apr-12 09-May-12 30-Apr-12 23-May-12 12 Facade LightFacade Lighting 21 22-Apr-12 15-May-12 15-May-12 07-Jun-12 20 A8533 Sub & App- Facade Lighting Subcontractor 21 22-Apr-12 15-May-12 15-May-12 07-Jun-12 20 Cooking StatCooking Station 21 01-May-12 24-May-12 15-Aug-12 10-Sep-12 90 A124700 Sub & App- Cooking Station Subcontractor 21 01-May-12 24-May-12 15-Aug-12 10-Sep-12 90 Gymnasium EGymnasium Equipments 21 31-Dec-12 26-Jan-13 21-Feb-13 17-Mar-13 43 A1142 Sub & App- Gym Equipments Subcontractor 21 31-Dec-12 26-Jan-13 21-Feb-13 17-Mar-13 43 Submittion &Submittion & Approval of Material Submittal 344 04-Jan-12 19-Feb-13 11-Jan-12 25-Apr-13 56 CivilCivil 198 04-Jan-12 26-Aug-12 11-Jan-12 13-Nov-12 66 A7630 Sub & App- Water Proofing for Substructure 2 04-Jan-12 05-Jan-12 11-Jan-12 12-Jan-12 6 A7610 Sub & App- Concerete - 1st Pour 5 08-Jan-12 12-Jan-12 11-Jan-12 16-Jan-12 3 A7620 Sub & App- Steel Reinforcement - 1st Patch 5 08-Jan-12 12-Jan-12 11-Jan-12 16-Jan-12 3 A8190 Sub & App- Water Proofing for Wet Areas 21 04-Mar-12 27-Mar-12 01-Aug-12 27-Aug-12 128 A113940 Sub & App- Water Proofing for Roof 21 02-Apr-12 25-Apr-12 24-Jun-12 17-Jul-12 70 A7640 Sub & App- GRP Lining 21 23-Apr-12 16-May-12 02-Aug-12 28-Aug-12 86 A8210 Sub & App- Traffic Coating 35 15-Jul-12 26-Aug-12 02-Oct-12 13-Nov-12 66 ArchitecturalArchitectural 266 19-Jan-12 03-Dec-12 14-Apr-12 10-Mar-13 81 Wet WorksWet Works 36 19-Jan-12 01-Mar-12 28-May-12 17-Jul-12 117 A7310 Sub & App- Blocks 21 19-Jan-12 13-Feb-12 28-May-12 21-Jun-12 110 A7240 Sub & App- Paint Materials 21 31-Jan-12 25-Feb-12 20-Jun-12 14-Jul-12 119 A7300 Sub & App- Plaster Materials 21 07-Feb-12 01-Mar-12 24-Jun-12 17-Jul-12 117 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Submission of Facade Lighitng Drawings Approval of Facade Lighitng Drawings Submission of Cooking Station Drawings Approval of Cooking Station Drawings Submission of Gymnasium Drawings Approval of Gymnasium Drawings Sub & App- MOS for Raft Slab Construction Sub & App- MOS for Columns Construction Sub & App- MOS for Retaining Walls Construction Sub & App- MOS for Core Walls Constrcution Sub & App- MOS for Slabs Construction Sub & App- MOS for Ramp Construction Sub & App- MOS for Backfilling Sub & App- MOS for Staircase Construction Sub & App- MOS for Blocks Works Sub & App- MOS for Plaster Works Sub & App- MOS for Panintng Sub & App- MOS for Wall&Floor Tiles Sub & App- MOS for Suspended Ceiling System Sub & App- MOS for Doors Sub & App- MOS for Water Proofing for Wet Areas Sub & App- MOS for GRP Lining Sub & App- MOS for Piping Works Sub & App- MOS for Duct Works Sub & App- MOS for Fan Coil Instllation Sub & App- MOS for MDBs,SMDBs,DBs Installation Sub & App- MOS for Pipings Sub & App- MOS for Sanitarywares Sub & App- MOS for Pipings Sub & App- MOS for Testing Sub & App- MOS for Fire Alarm Devices Fixing Sub & App- MOS for Water Proofing Sub & App- MOS for Tiling Sub & App- MOS for Facade Cleaning Sub & App- MOS for Piping Installation Sub & App- MOS for Equipment Installation Sub & App- MOS for Piping Installation Sub & App- MOS for Equipment Installation Sub & App- Water Proofing Works Subcontractor Sub & App- LPG System Subcontractor Sub & App- MEP Subcontractor Sub & App- Susbended Ceilings Subcontractor Sub & App- Garbage Chute System Subcontractor Sub & App- Elevators Subcontractor Sub & App- GRP Lining Subcontractor Sub & App- Linen Chute System Subcontractor Sub & App- Swimming Pool Works Subcontractor Sub & App- Wood & Joinery Subcontractor Sub & App- Landscaping Subcontractor Sub & App- Aluminum&Glazing Works Subcontractor Sub & App- Facade Cleanining Subcontractor Sub & App- Traffic Deck Coating Subcontractor Sub & App- Irrigation Works Subcontractor Sub & App- Kitchen Equipments Subcontractor Sub & App- Laundary Equipments Subcontractor Sub & App- Facade Lighting Subcontractor Sub & App- Cooking Station Subcontractor Sub & App- Gym Equipments Subcontractor Sub & App- Water Proofing for Substructure Sub & App- Concerete - 1st Pour Sub & App- Steel Reinforcement - 1st Patch Sub & App- Water Proofing for Wet Areas Sub & App- Water Proofing for Roof Sub & App- GRP Lining Sub & App- Traffic Coating Sub & App- Blocks Sub & App- Paint Materials Sub & App- Plaster Materials Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 11 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 12. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float CeilingCeiling 21 13-Feb-12 07-Mar-12 14-Apr-12 07-May-12 52 A7260 Sub & App- Ceiling Suspension System 21 13-Feb-12 07-Mar-12 14-Apr-12 07-May-12 52 Walls & FlooWalls & Floors 211 13-Mar-12 20-Nov-12 31-May-12 20-Dec-12 25 A7230 Sub & App- Porcelain Tiles 21 13-Mar-12 05-Apr-12 31-May-12 25-Jun-12 68 A7490 Sub & App- Ceramic Tiles 21 13-Mar-12 05-Apr-12 31-Jul-12 26-Aug-12 119 A7270 Sub & App- Granite Tiles 21 25-Mar-12 17-Apr-12 16-Oct-12 11-Nov-12 173 A8370 Sub & App- MDF Cladding 21 25-Mar-12 17-Apr-12 16-Aug-12 11-Sep-12 123 A114010 Sub & App- Natural Stone 21 25-Mar-12 17-Apr-12 26-Sep-12 20-Oct-12 156 A113970 Sub & App- Carpet Tiles 21 05-Apr-12 29-Apr-12 06-Oct-12 31-Oct-12 154 A114040 Sub & App- Veneer Cladding 21 05-Apr-12 29-Apr-12 18-Aug-12 12-Sep-12 114 A7480 Sub & App- Terrazo Tiles 21 29-Apr-12 22-May-12 22-Sep-12 15-Oct-12 122 A7500 Sub & App- Marble Tiles 21 29-Apr-12 22-May-12 06-Nov-12 01-Dec-12 159 A7660 Sub & App- Vinyel Sheet 21 29-Apr-12 22-May-12 14-Oct-12 08-Nov-12 141 A114030 Sub & App- Raised Floor Tiles 21 29-Apr-12 22-May-12 04-Nov-12 28-Nov-12 157 A114050 Sub & App- Wenge cCladding 21 29-Apr-12 22-May-12 13-Sep-12 07-Oct-12 115 A113990 Sub & App- Honed Limestone 21 22-May-12 14-Jun-12 04-Oct-12 30-Oct-12 113 A114000 Sub & App- Mosiac Tiles 21 22-May-12 14-Jun-12 07-Aug-12 02-Sep-12 65 A7520 Sub & App- Wooden Floor 21 28-May-12 21-Jun-12 08-Sep-12 01-Oct-12 85 A114020 Sub & App- Polished Moche Tiles 21 03-Jun-12 27-Jun-12 04-Oct-12 30-Oct-12 103 A7670 Sub & App- Precast Conc. Interlocking Paving 21 09-Jul-12 01-Aug-12 09-Oct-12 04-Nov-12 77 A7680 Sub & App- Precast Conc. Kerbs 21 09-Jul-12 01-Aug-12 30-Sep-12 23-Oct-12 69 A113950 Sub & App- Heavy Duty Tiles 21 01-Aug-12 27-Aug-12 26-Nov-12 20-Dec-12 95 A8360 Sub & App- Vinyl Wall Covering 21 08-Sep-12 01-Oct-12 13-Nov-12 09-Dec-12 55 A7510 Sub & App- Carpet 21 24-Oct-12 20-Nov-12 31-Oct-12 25-Nov-12 4 Doors & WinDoors & Windows 146 25-Jan-12 15-Jul-12 22-Aug-12 17-Nov-12 102 A7430 Sub & App- Aluminum Louver Doors 21 25-Jan-12 19-Feb-12 06-Oct-12 31-Oct-12 214 A7450 Sub & App- Fire Rated Doors 21 25-Jan-12 19-Feb-12 08-Oct-12 03-Nov-12 216 A7350 Sub & App- Galzed Aluminum Doors 21 25-Mar-12 17-Apr-12 10-Oct-12 05-Nov-12 168 A114060 Sub & App- Ironmongery 21 17-Apr-12 10-May-12 11-Sep-12 04-Oct-12 123 A7340 Sub & App- Wooden Doors 21 28-May-12 21-Jun-12 22-Aug-12 15-Sep-12 71 A7470 Sub & App- Curtain Wall&Glazing 21 21-Jun-12 15-Jul-12 21-Oct-12 17-Nov-12 102 MetalMetal 41 05-Apr-12 22-May-12 30-Apr-12 14-Nov-12 146 A7420 Sub & App- Balustrades and Handrails 21 05-Apr-12 29-Apr-12 30-Apr-12 23-May-12 21 A7280 Sub & App- Sinages 21 29-Apr-12 22-May-12 20-Oct-12 14-Nov-12 146 FurnitureFurniture 31 24-Oct-12 03-Dec-12 16-Dec-12 10-Mar-13 81 A8330 Sub & App- Furniture 21 24-Oct-12 20-Nov-12 16-Dec-12 09-Jan-13 41 A7390 Sub & App- Reception Counter 21 07-Nov-12 03-Dec-12 14-Feb-13 10-Mar-13 81 Soft LandscpSoft Landscping 41 28-May-12 15-Jul-12 12-Jul-12 30-Oct-12 88 A114080 Sub & App- Soft Landscping Items 21 28-May-12 21-Jun-12 12-Jul-12 05-Aug-12 38 A8390 Sub & App- Landscaping Light 21 21-Jun-12 15-Jul-12 04-Oct-12 30-Oct-12 88 OthersOthers 151 17-Apr-12 13-Oct-12 10-Jul-12 03-Jan-13 66 A7250 Sub & App- Toliets Accessories 21 17-Apr-12 10-May-12 03-Oct-12 29-Oct-12 142 A7290 Sub & App- Mirrors & Glasses 21 29-Apr-12 22-May-12 06-Oct-12 31-Oct-12 134 A124220 Sub & App- Sky Light 21 29-Apr-12 22-May-12 24-Jul-12 16-Aug-12 73 A7370 Sub & App- Waredrobes 21 28-May-12 21-Jun-12 10-Jul-12 02-Aug-12 36 A7360 Sub & App- Kitchen Cabinets 30 28-May-12 02-Jul-12 02-Oct-12 07-Nov-12 106 A7380 Sub & App- Vanity Counters 21 21-Jun-12 15-Jul-12 07-Oct-12 01-Nov-12 90 A115280 Sub & App- GRC 21 27-Aug-12 19-Sep-12 14-Nov-12 10-Dec-12 66 A114090 Sub & App- Hump 21 19-Sep-12 13-Oct-12 10-Dec-12 03-Jan-13 66 MechanicalMechanical 166 01-Feb-12 14-Aug-12 29-Mar-12 07-Feb-13 144 HVACHVAC 146 01-Feb-12 22-Jul-12 29-Mar-12 22-Oct-12 77 A8290 Sub & App- Chiller 21 01-Feb-12 26-Feb-12 29-Mar-12 22-Apr-12 48 A8060 Sub & App- HAVC Ducts 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62 A8100 Sub & App- Chilled Water Pipes-Fittings-Valves 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62 A8120 Sub & App- Condensate Pipes-Fittings-Valves 21 14-Feb-12 08-Mar-12 26-Apr-12 20-May-12 62 A8070 Sub & App- FCUs 21 20-Feb-12 14-Mar-12 22-May-12 14-Jun-12 79 A8160 Sub & App- Air Oulets 21 20-Feb-12 14-Mar-12 29-Sep-12 22-Oct-12 187 A8080 Sub & App- AHU 21 26-Feb-12 20-Mar-12 17-Jul-12 09-Aug-12 121 A8090 Sub & App- FAHU 21 26-Feb-12 20-Mar-12 21-Jul-12 13-Aug-12 124 A8140 Sub & App- Chilled Pipes Insulation 21 01-Apr-12 24-Apr-12 07-Jul-12 30-Jul-12 82 A8130 Sub & App- Ducts Insulation 21 24-Apr-12 17-May-12 24-Jul-12 16-Aug-12 77 A8150 Sub & App- Condensate Pipes Insulation 21 24-Apr-12 17-May-12 24-Jul-12 16-Aug-12 77 A8300 Sub & App- Primary Chilled Water Pump 35 10-Jun-12 21-Jul-12 25-Aug-12 03-Oct-12 62 A8270 Sub & App- Heat Exchanger (HEX) 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61 A8280 Sub & App- Pumps for HEX 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61 A8310 Sub & App- Secpndry Chilled Water Pump 21 28-Jun-12 22-Jul-12 10-Sep-12 03-Oct-12 61 PlumbingPlumbing 141 01-Feb-12 16-Jul-12 11-Jun-12 15-Dec-12 124 A7900 Sub & App- Floor Drains 21 01-Feb-12 26-Feb-12 20-Nov-12 15-Dec-12 244 A104240 Sub & App- Water Boiler Tank 21 08-Feb-12 03-Mar-12 26-Sep-12 20-Oct-12 195 A7930 Sub & App- PPR Pipes -Fittings-Valves (Water) 21 13-Feb-12 07-Mar-12 13-Jun-12 08-Jul-12 104 A7910 Sub & App- Sump Pump 21 14-Feb-12 08-Mar-12 22-Oct-12 18-Nov-12 212 A104260 Sub & App- Water Boiler 21 26-Feb-12 20-Mar-12 18-Sep-12 11-Oct-12 173 A104270 Sub & App- Water Boiler Pump 21 03-Mar-12 26-Mar-12 11-Nov-12 06-Dec-12 212 A7940 Sub & App- Transfer Pump 21 08-Mar-12 01-Apr-12 03-Oct-12 29-Oct-12 176 A7960 Sub & App- Steam Pipes for Boilers 21 08-Mar-12 01-Apr-12 13-Oct-12 07-Nov-12 184 A7890 Sub & App- uPVC Pipes-Fittings-Valves(Drainge) 21 20-Mar-12 12-Apr-12 11-Jun-12 05-Jul-12 71 A104250 Sub & App- Sanitarywares 21 06-May-12 29-May-12 13-Oct-12 07-Nov-12 134 A104340 Sub & App- GRP Water Tank 21 17-May-12 10-Jun-12 22-Sep-12 15-Oct-12 106 A115100 Sub & App- Booster Pump 21 23-Jun-12 16-Jul-12 03-Oct-12 29-Oct-12 86 Fire FighitngFire Fighitng 61 01-Feb-12 12-Apr-12 15-Apr-12 07-Nov-12 174 A7970 Sub & App- Fire Pipes-Fittings-Valves 21 01-Feb-12 26-Feb-12 15-Apr-12 08-May-12 62 A7990 Sub & App- Sprinklers 21 01-Feb-12 26-Feb-12 27-Aug-12 19-Sep-12 174 A8010 Sub & App- Landing Valves 21 01-Feb-12 26-Feb-12 18-Sep-12 11-Oct-12 193 A7780 Sub & App- Fire Alram Devices 30 01-Feb-12 07-Mar-12 18-Jul-12 23-Aug-12 142 A7980 Sub & App- Fire Pump 21 14-Feb-12 08-Mar-12 29-Jul-12 23-Aug-12 141 A8040 Sub & App- Foam Spary System for Generators 21 08-Mar-12 01-Apr-12 13-Oct-12 07-Nov-12 184 A8000 Sub & App- Fire Extinguishers & Banket 21 20-Mar-12 12-Apr-12 06-Sep-12 30-Sep-12 143 A8020 Sub & App- Fire Hose Cabinets 21 20-Mar-12 12-Apr-12 18-Sep-12 11-Oct-12 153 LPG SystemLPG System 116 01-Apr-12 14-Aug-12 18-Dec-12 07-Feb-13 144 A8430 Sub & App- LPG Pipes-Fittings-Valves 21 01-Apr-12 24-Apr-12 18-Dec-12 12-Jan-13 217 A8440 Sub & App- LPG Tanks( 2000 Gallons) 21 22-Jul-12 14-Aug-12 14-Jan-13 07-Feb-13 144 Coveying SysCoveying System 21 31-Mar-12 23-Apr-12 01-May-12 05-Jul-12 62 A7550 Sub & App- Passenger Lifts 21 31-Mar-12 23-Apr-12 11-Jun-12 05-Jul-12 62 A114290 Sub & App- Brakets,Guide Rails and Others 21 31-Mar-12 23-Apr-12 01-May-12 24-May-12 27 ElectricalElectrical 65 01-Feb-12 17-Apr-12 26-Apr-12 13-Nov-12 175 Cable Trays -Cable Trays - Cables 35 08-Feb-12 19-Mar-12 02-Jun-12 15-Aug-12 127 A7760 Sub & App- Cable Trays 30 08-Feb-12 13-Mar-12 07-Jun-12 12-Jul-12 103 A7700 Sub & App- Bus Bars 35 08-Feb-12 19-Mar-12 07-Jul-12 15-Aug-12 127 A7740 Sub & App- LV Cable 35 08-Feb-12 19-Mar-12 18-Jun-12 28-Jul-12 111 A7770 Sub & App- Trunking 35 08-Feb-12 19-Mar-12 02-Jun-12 12-Jul-12 98 Low CurrentLow Current Systems 65 01-Feb-12 17-Apr-12 26-Apr-12 22-Sep-12 132 A7820 Sub & App- CCTV System 35 01-Feb-12 13-Mar-12 01-May-12 10-Jun-12 76 A7830 Sub & App- Access Control System 35 01-Feb-12 13-Mar-12 26-Apr-12 05-Jun-12 72 A7840 Sub & App- Central Battery System 35 01-Feb-12 13-Mar-12 01-Aug-12 12-Sep-12 154 A7870 Sub & App- BMS 35 01-Feb-12 13-Mar-12 09-Jul-12 18-Aug-12 134 A8400 Sub & App- MATV/ Interactive TV System 35 01-Feb-12 13-Mar-12 30-Jul-12 10-Sep-12 152 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Sub & App- Ceiling Suspension System Sub & App- Porcelain Tiles Sub & App- Ceramic Tiles Sub & App- Granite Tiles Sub & App- MDF Cladding Sub & App- Natural Stone Sub & App- Carpet Tiles Sub & App- Veneer Cladding Sub & App- Terrazo Tiles Sub & App- Marble Tiles Sub & App- VinyelSheet Sub & App- Raised Floor Tiles Sub & App- Wenge cCladding Sub & App- Honed Limestone Sub & App- Mosiac Tiles Sub & App- Wooden Floor Sub & App- Polished Moche Tiles Sub & App- Precast Conc. Interlocking Paving Sub & App- Precast Conc. Kerbs Sub & App- Heavy Duty Tiles Sub & App- Vinyl Wall Covering Sub & App- Carpet Sub & App- Aluminum Louver Doors Sub & App- Fire Rated Doors Sub & App- Galzed Aluminum Doors Sub & App- Ironmongery Sub & App- Wooden Doors Sub & App- Curtain Wall&Glazing Sub & App- Balustrades and Handrails Sub & App- Sinages Sub & App- Furniture Sub & App- Reception Counter Sub & App- Soft Landscping Items Sub & App- Landscaping Light Sub & App- Toliets Accessories Sub & App- Mirrors & Glasses Sub & App- Sky Light Sub & App- Waredrobes Sub & App- Kitchen Cabinets Sub & App- Vanity Counters Sub & App- GRC Sub & App- Hump Sub & App- Chiller Sub & App- HAVC Ducts Sub & App- Chilled Water Pipes-Fittings-Valves Sub & App- Condensate Pipes-Fittings-Valves Sub & App- FCUs Sub & App- Air Oulets Sub & App- AHU Sub & App- FAHU Sub & App- Chilled Pipes Insulation Sub & App- Ducts Insulation Sub & App- Condensate Pipes Insulation Sub & App- Primary Chilled Water Pump Sub & App- Heat Exchanger (HEX) Sub & App- Pumps for HEX Sub & App- Secpndry Chilled Water Pump Sub & App- Floor Drains Sub & App- Water Boiler Tank Sub & App- PPR Pipes -Fittings-Valves (Water) Sub & App- Sump Pump Sub & App- Water Boiler Sub & App- Water Boiler Pump Sub & App- Transfer Pump Sub & App- Steam Pipes for Boilers Sub & App- uPVC Pipes-Fittings-Valves(Drainge) Sub & App- Sanitarywares Sub & App- GRP Water Tank Sub & App- Booster Pump Sub & App- Fire Pipes-Fittings-Valves Sub & App- Sprinklers Sub & App- Landing Valves Sub & App- Fire Alram Devices Sub & App- Fire Pump Sub & App- Foam Spary System for Generators Sub & App- Fire Extinguishers & Banket Sub & App- Fire Hose Cabinets Sub & App- LPG Pipes-Fittings-Valves Sub & App- LPG Tanks( 2000 Gallons) Sub & App- Passenger Lifts Sub & App- Brakets,Guide Rails and Others Sub & App- Cable Trays Sub & App- Bus Bars Sub & App- LV Cable Sub & App- Trunking Sub & App- CCTV System Sub & App- Access Control System Sub & App- Central Battery System Sub & App- BMS Sub & App- MATV/ Interactive TV System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 12 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 13. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A8240 Sub & App- GSM System 35 08-Mar-12 17-Apr-12 11-Aug-12 22-Sep-12 132 Electrical EquElectrical Equipments 61 01-Feb-12 12-Apr-12 23-May-12 13-Nov-12 179 A7710 Sub & App- MDBs 35 01-Feb-12 13-Mar-12 17-Jul-12 28-Aug-12 141 A7720 Sub & App- SMDBs 35 01-Feb-12 13-Mar-12 08-Aug-12 19-Sep-12 160 A7730 Sub & App- DBs 35 01-Feb-12 13-Mar-12 23-May-12 03-Jul-12 95 A7800 Sub & App- Generators 35 01-Feb-12 13-Mar-12 04-Jul-12 13-Aug-12 130 A7860 Sub & App- UPS 35 01-Feb-12 13-Mar-12 11-Jul-12 22-Aug-12 136 A8670 Sub & App- Telephone System 35 01-Feb-12 13-Mar-12 18-Jun-12 28-Jul-12 116 A8260 Sub & App- ElectricalHeaters 21 20-Mar-12 12-Apr-12 18-Oct-12 13-Nov-12 179 OthersOthers 35 01-Feb-12 13-Mar-12 05-Aug-12 16-Sep-12 157 A7880 Sub & App- Light Fixtures 35 01-Feb-12 13-Mar-12 05-Aug-12 16-Sep-12 157 Speciality WSpeciality Works 111 19-Mar-12 26-Jul-12 06-May-12 28-Jan-13 151 Swimming PoSwimming Pool 21 28-May-12 21-Jun-12 05-Jul-12 08-Nov-12 116 A7560 Sub & App- Pool Finishes 21 28-May-12 21-Jun-12 29-Sep-12 22-Oct-12 103 A7570 Sub & App- Pool Equipments 21 28-May-12 21-Jun-12 05-Jul-12 29-Jul-12 32 A8180 Sub & App- Water Proofing for Swimming Pool 21 28-May-12 21-Jun-12 04-Oct-12 30-Oct-12 108 A104220 Sub & App- Pool Electrical Items 21 28-May-12 21-Jun-12 14-Oct-12 08-Nov-12 116 Garbage ChuGarbage Chute System 40 19-Mar-12 03-May-12 06-May-12 30-Jul-12 74 A7580 Sub & App- Pipes & Fittings 21 19-Mar-12 11-Apr-12 21-Jun-12 15-Jul-12 80 A104180 Sub & App- Equipments 28 19-Mar-12 19-Apr-12 28-Jun-12 30-Jul-12 86 A104190 Sub & App- Garbage Chutes 40 19-Mar-12 03-May-12 06-May-12 21-Jun-12 41 Linen ChuteLinen Chute System 40 23-Apr-12 07-Jun-12 13-May-12 05-Jul-12 23 A114140 Sub & App- Pipes & Fittings 21 23-Apr-12 16-May-12 13-May-12 05-Jun-12 17 A114120 Sub & App- Equipments 28 23-Apr-12 24-May-12 26-May-12 27-Jun-12 28 A114130 Sub & App- Linen Chutes 40 23-Apr-12 07-Jun-12 20-May-12 05-Jul-12 23 Facade CleanFacade Cleaning System 21 03-Jul-12 26-Jul-12 03-Jan-13 28-Jan-13 151 A7600 Sub & App- Cleaning System 21 03-Jul-12 26-Jul-12 03-Jan-13 28-Jan-13 151 ProvisionalProvisional Sum 236 10-May-12 19-Feb-13 11-Jun-12 25-Apr-13 56 Kitchen EquiKitchen Equipments 21 10-May-12 03-Jun-12 13-Jun-12 08-Jul-12 29 A8650 Sub & App- Kitchen Equipments 21 10-May-12 03-Jun-12 13-Jun-12 08-Jul-12 29 Laundary EqLaundary Equipments 21 10-May-12 03-Jun-12 11-Jun-12 05-Jul-12 27 A114220 Sub & App- Laundary Equipments 21 10-May-12 03-Jun-12 11-Jun-12 05-Jul-12 27 Facade LightFacade Lighting 21 16-May-12 09-Jun-12 28-Jun-12 22-Jul-12 36 A115260 Sub & App- Facade Lighting 21 16-May-12 09-Jun-12 28-Jun-12 22-Jul-12 36 Cooking StatCooking Station 21 26-May-12 19-Jun-12 30-Sep-12 23-Oct-12 106 A124710 Sub & App- Cooking Station 21 26-May-12 19-Jun-12 30-Sep-12 23-Oct-12 106 Gymnasium EGymnasium Equipments 21 27-Jan-13 19-Feb-13 02-Apr-13 25-Apr-13 56 A114270 Sub & App- Gym Equipments 21 27-Jan-13 19-Feb-13 02-Apr-13 25-Apr-13 56 ProcuremenProcurement and Delivery 437 07-Jan-12 11-Jun-13 14-Jan-12 29-Jul-13 41 CivilCivil 286 07-Jan-12 13-Dec-12 14-Jan-12 03-Mar-13 66 A6390 Order&Delivery- Water Proofing for Substructure 5 07-Jan-12 11-Jan-12 14-Jan-12 18-Jan-12 6 A6370 Order&Delivery- Conceret - 1st Pour 7 14-Jan-12 21-Jan-12 17-Jan-12 24-Jan-12 3 A6380 Order&Delivery- Steel Reinforcement - 1st Patch 7 14-Jan-12 21-Jan-12 17-Jan-12 24-Jan-12 3 A6930 Order&Delivery- Water Proofing for Wet Areas 90 28-Mar-12 11-Jul-12 28-Aug-12 15-Dec-12 128 A6400 Order&Delivery- GRP Lining 60 17-May-12 26-Jul-12 29-Aug-12 08-Nov-12 86 A9170 Order&Delivery- Reinforced Plastic 60 17-May-12 26-Jul-12 15-Sep-12 26-Nov-12 100 A46460 Order&Delivery- Water Proofing for Roof 100 26-Apr-12 23-Aug-12 18-Jul-12 17-Nov-12 70 A6950 Order&Delivery- Traffic Coating 90 27-Aug-12 13-Dec-12 14-Nov-12 03-Mar-13 66 ArchitecturalArchitectural 405 14-Feb-12 11-Jun-13 24-May-12 29-Jul-13 41 Wet WorksWet Works 70 14-Feb-12 05-May-12 23-Jun-12 24-Sep-12 119 A5580 Order&Delivery- Blocks 30 14-Feb-12 19-Mar-12 23-Jun-12 26-Jul-12 110 A5570 Order&Delivery- Plaster Materials 30 03-Mar-12 05-Apr-12 18-Jul-12 23-Aug-12 117 A5510 Order&Delivery- Paint Materials 60 26-Feb-12 05-May-12 15-Jul-12 24-Sep-12 119 CeilingCeiling 140 01-Mar-12 12-Aug-12 31-May-12 27-Jan-13 136 A9130 Order&Delivery- Metal Celing System 90 01-Mar-12 13-Jun-12 31-Jul-12 18-Nov-12 129 A5720 Order&Delivery- Fibre Celing System 90 25-Mar-12 08-Jul-12 08-Oct-12 27-Jan-13 166 A5530 Order&Delivery- Gybsum Ceiling System 90 01-Apr-12 15-Jul-12 31-May-12 16-Sep-12 52 A9270 Order&Delivery- Aluminum Ceiling Tiles 90 17-Apr-12 31-Jul-12 03-Oct-12 21-Jan-13 142 A9330 Order&Delivery- MDF Ceiling System 90 29-Apr-12 12-Aug-12 29-Sep-12 16-Jan-13 128 Walls & FlooWalls & Floors 290 07-Apr-12 20-Mar-13 26-Jun-12 13-Apr-13 20 A5500 Order&Delivery- Porcelain Tiles 105 07-Apr-12 07-Aug-12 26-Jun-12 30-Oct-12 68 A5760 Order&Delivery- Ceramic Tiles 105 07-Apr-12 07-Aug-12 27-Aug-12 31-Dec-12 119 A5840 Order&Delivery- Natural Stone 95 18-Apr-12 07-Aug-12 21-Oct-12 14-Feb-13 156 A7120 Order&Delivery- MDF Cladding 100 18-Apr-12 13-Aug-12 12-Sep-12 12-Jan-13 123 A5540 Order&Delivery- Granite Tiles 105 18-Apr-12 21-Aug-12 12-Nov-12 18-Mar-13 173 A9140 Order&Delivery- Carpet Tiles 95 30-Apr-12 21-Aug-12 01-Nov-12 24-Feb-13 154 A5750 Order&Delivery- Terrazo Tiles 90 23-May-12 08-Sep-12 16-Oct-12 04-Feb-13 122 A9240 Order&Delivery- Raised Floor Tiles 90 23-May-12 08-Sep-12 29-Nov-12 17-Mar-13 157 A9250 Order&Delivery- Veneer Cladding 110 30-Apr-12 08-Sep-12 13-Sep-12 26-Jan-13 114 A6110 Order&Delivery- VinyelSheet 95 23-May-12 13-Sep-12 10-Nov-12 04-Mar-13 141 A9320 Order&Delivery- Wenge Cladding 95 23-May-12 13-Sep-12 08-Oct-12 02-Feb-13 115 A5770 Order&Delivery- Marble Tiles 105 23-May-12 25-Sep-12 03-Dec-12 06-Apr-13 159 A9290 Order&Delivery- Honed Limestone Tiles 90 16-Jun-12 01-Oct-12 31-Oct-12 17-Feb-13 113 A5790 Order&Delivery- Wooden Floor 95 23-Jun-12 13-Oct-12 02-Oct-12 27-Jan-13 85 A9300 Order&Delivery- Polished Moche Tiles 90 28-Jun-12 13-Oct-12 31-Oct-12 17-Feb-13 103 A9120 Order&Delivery- Mosiac Tiles 105 16-Jun-12 18-Oct-12 03-Sep-12 08-Jan-13 65 A9310 Order&Delivery- Water Jet Limestone Tiles 90 01-Aug-12 19-Nov-12 31-Oct-12 17-Feb-13 74 A6320 Order&Delivery- Precast Conc. Interlocking Paving 90 02-Aug-12 20-Nov-12 05-Nov-12 21-Feb-13 77 A6420 Order&Delivery- Precast Conc. Kerbs 90 02-Aug-12 20-Nov-12 24-Oct-12 12-Feb-13 69 A9260 Order&Delivery- Heavy Duty Tiles 95 28-Aug-12 20-Dec-12 22-Dec-12 13-Apr-13 95 A7110 Order&Delivery- Vinyl Wall Covering 100 02-Oct-12 02-Feb-13 10-Dec-12 07-Apr-13 55 A5780 Order&Delivery- Carpet 100 21-Nov-12 20-Mar-13 26-Nov-12 25-Mar-13 4 Doors & WinDoors & Windows 225 20-Feb-12 13-Nov-12 16-Sep-12 23-Feb-13 83 A5700 Order&Delivery- Aluminum Louver Doors 90 20-Feb-12 03-Jun-12 01-Nov-12 18-Feb-13 214 A5710 Order&Delivery- Fire Rated Doors 90 20-Feb-12 03-Jun-12 04-Nov-12 20-Feb-13 216 A5620 Order&Delivery- Galzed Aluminum Doors 90 18-Apr-12 01-Aug-12 06-Nov-12 23-Feb-13 168 A6220 Order&Delivery- Ironmongery 105 12-May-12 13-Sep-12 06-Oct-12 11-Feb-13 123 A5610 Order&Delivery- Wooden Doors 120 23-Jun-12 13-Nov-12 16-Sep-12 09-Feb-13 71 MetalMetal 140 30-Apr-12 13-Oct-12 24-May-12 08-Apr-13 146 A5690 Order&Delivery- Balustrades and Handrails 120 30-Apr-12 19-Sep-12 24-May-12 14-Oct-12 21 A5550 Order&Delivery- Sinages 120 23-May-12 13-Oct-12 17-Nov-12 08-Apr-13 146 FurnitureFurniture 170 21-Nov-12 11-Jun-13 10-Jan-13 29-Jul-13 41 A5660 Order&Delivery- Reception Counter 120 04-Dec-12 24-Apr-13 11-Mar-13 29-Jul-13 81 A7010 Order&Delivery- Furniture 170 21-Nov-12 11-Jun-13 10-Jan-13 29-Jul-13 41 Soft LandscpSoft Landscping 130 23-Jun-12 26-Nov-12 06-Aug-12 12-Mar-13 88 A5590 Order&Delivery- Soft Landscping Items 100 23-Jun-12 18-Oct-12 06-Aug-12 06-Dec-12 38 A7140 Order&Delivery- Landscaping Light 110 16-Jul-12 26-Nov-12 31-Oct-12 12-Mar-13 88 OthersOthers 210 12-May-12 20-Jan-13 04-Aug-12 08-Apr-13 66 A5520 Order&Delivery- Toliets Accessories 100 12-May-12 08-Sep-12 30-Oct-12 27-Feb-13 142 A5730 Order&Delivery- Sky Light 90 23-May-12 08-Sep-12 18-Aug-12 06-Dec-12 73 A5560 Order&Delivery- Mirrors & Glasses 100 23-May-12 19-Sep-12 01-Nov-12 02-Mar-13 134 A5640 Order&Delivery- Waredrobes 90 23-Jun-12 07-Oct-12 04-Aug-12 21-Nov-12 36 A5630 Order&Delivery- Kitchen Cabinets 90 03-Jul-12 17-Oct-12 08-Nov-12 25-Feb-13 106 A51060 Order&Delivery- Irrigation System 90 15-Jul-12 31-Oct-12 07-Oct-12 26-Jan-13 70 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Sub & App- GSM System Sub & App- MDBs Sub & App- SMDBs Sub & App- DBs Sub & App- Generators Sub & App- UPS Sub & App- Telephone System Sub & App- ElectricalHeaters Sub & App- Light Fixtures Sub & App- Pool Finishes Sub & App- Pool Equipments Sub & App- Water Proofing for Swimming Pool Sub & App- Pool Electrical Items Sub & App- Pipes & Fittings Sub & App- Equipments Sub & App- Garbage Chutes Sub & App- Pipes & Fittings Sub & App- Equipments Sub & App- Linen Chutes Sub & App- Cleaning System Sub & App- Kitchen Equipments Sub & App- Laundary Equipments Sub & App- Facade Lighting Sub & App- Cooking Station Sub & App- Gym Equipments Order&Delivery- Water Proofing for Substructure Order&Delivery- Conceret - 1st Pour Order&Delivery- Steel Reinforcement - 1st Patch Order&Delivery- Water Proofing for Wet Areas Order&Delivery- GRP Lining Order&Delivery- Reinforced Plastic Order&Delivery- Water Proofing for Roof Order&Delivery- Traffic Coating Order&Delivery- Blocks Order&Delivery- Plaster Materials Order&Delivery- Paint Materials Order&Delivery- Metal Celing System Order&Delivery- Fibre Celing System Order&Delivery- Gybsum Ceiling System Order&Delivery- Aluminum Ceiling Tiles Order&Delivery- MDF Ceiling System Order&Delivery- Porcelain Tiles Order&Delivery- Ceramic Tiles Order&Delivery- Natural Stone Order&Delivery- MDF Cladding Order&Delivery- Granite Tiles Order&Delivery- Carpet Tiles Order&Delivery- Terrazo Tiles Order&Delivery- Raised Floor Tiles Order&Delivery- Veneer Cladding Order&Delivery- Vinyel Sheet Order&Delivery- Wenge Cladding Order&Delivery- Marble Tiles Order&Delivery- Honed Limestone Tiles Order&Delivery- Wooden Floor Order&Delivery- Polished Moche Tiles Order&Delivery- Mosiac Tiles Order&Delivery- Water Jet Limestone Tiles Order&Delivery- Precast Conc. Interlocking Paving Order&Delivery- Precast Conc. Kerbs Order&Delivery- Heavy Duty Tiles Order&Delivery- Vinyl Wall Covering Order&Delivery- Carpet Order&Delivery- Aluminum Louver Doors Order&Delivery- Fire Rated Doors Order&Delivery- Galzed Aluminum Doors Order&Delivery- Ironmongery Order&Delivery- Wooden Doors Order&Delivery- Balustrades and Handrails Order&Delivery- Sinages Order&Delivery- Reception Counter Order&Delivery- Furniture Order&Delivery- Soft Landscping Items Order&Delivery- Landscaping Light Order&Delivery- Toliets Accessories Order&Delivery- Sky Light Order&Delivery- Mirrors & Glasses Order&Delivery- Waredrobes Order&Delivery- Kitchen Cabinets Order&Delivery- Irrigation System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 13 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 14. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A5650 Order&Delivery- Vanity Counters 100 16-Jul-12 13-Nov-12 03-Nov-12 03-Mar-13 90 A50690 Order&Delivery- Hump 80 14-Oct-12 20-Jan-13 05-Jan-13 08-Apr-13 66 MechanicalMechanical 239 27-Feb-12 09-Dec-12 23-Apr-12 24-Mar-13 88 HVACHVAC 215 27-Feb-12 08-Nov-12 23-Apr-12 29-Jan-13 66 A6900 Order&Delivery- Air Oulets 60 15-Mar-12 23-May-12 23-Oct-12 06-Jan-13 187 A6880 Order&Delivery- Chilled Pipes Insulation 30 25-Apr-12 29-May-12 31-Jul-12 05-Sep-12 82 A6870 Order&Delivery- Ducts Insulation 15 19-May-12 04-Jun-12 18-Aug-12 05-Sep-12 77 A6890 Order&Delivery- Condensate Pipes Insulation 15 19-May-12 04-Jun-12 18-Aug-12 05-Sep-12 77 A6810 Order&Delivery- FCUs 75 15-Mar-12 10-Jun-12 16-Jun-12 13-Sep-12 79 A6800 Order&Delivery- HAVC Ducts 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62 A6840 Order&Delivery- Chilled Water Pipes-Fittings-Valves 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62 A6860 Order&Delivery- Condensate Pipes-Fittings-Valves 90 10-Mar-12 23-Jun-12 21-May-12 05-Sep-12 62 A6830 Order&Delivery- FAHU 100 25-Apr-12 22-Aug-12 20-Sep-12 20-Jan-13 124 A6820 Order&Delivery- AHU 110 25-Apr-12 03-Sep-12 17-Sep-12 29-Jan-13 121 A7050 Order&Delivery- Chiller 180 27-Feb-12 26-Sep-12 23-Apr-12 25-Nov-12 48 A7060 Order&Delivery- Primary Chilled Water Pump 90 22-Jul-12 07-Nov-12 04-Oct-12 22-Jan-13 62 A7030 Order&Delivery- Heat Exchanger (HEX) 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61 A7040 Order&Delivery- Pumps for HEX 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61 A7070 Order&Delivery- Secpndry Chilled Water Pump 90 23-Jul-12 08-Nov-12 04-Oct-12 22-Jan-13 61 PlumbingPlumbing 210 27-Feb-12 03-Nov-12 07-Jul-12 25-Feb-13 94 A6640 Order&Delivery- Floor Drains 30 27-Feb-12 01-Apr-12 16-Dec-12 20-Jan-13 244 A6670 Order&Delivery-PPR Pipes -Fittings-Valves (Water) 30 08-Mar-12 11-Apr-12 09-Jul-12 12-Aug-12 104 A6630 Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge) 30 14-Apr-12 17-May-12 07-Jul-12 09-Aug-12 71 A6650 Order&Delivery- Sump Pump 60 10-Mar-12 17-May-12 19-Nov-12 30-Jan-13 212 A7020 Order&Delivery- ElectricalHeaters 30 14-Apr-12 17-May-12 14-Nov-12 20-Dec-12 179 A9200 Order&Delivery- Water Boiler Pump 60 27-Mar-12 04-Jun-12 08-Dec-12 17-Feb-13 212 A9190 Order&Delivery- Water Boiler Tank 90 04-Mar-12 16-Jun-12 21-Oct-12 09-Feb-13 195 A9180 Order&Delivery- Water Boiler 90 21-Mar-12 04-Jul-12 13-Oct-12 31-Jan-13 173 A9210 Order&Delivery- Steam Pipes for Boilers 90 02-Apr-12 16-Jul-12 08-Nov-12 25-Feb-13 184 A9220 Order&Delivery- Transfer Pump 90 02-Apr-12 16-Jul-12 30-Oct-12 16-Feb-13 176 A8790 Order&Delivery- Sanitarywares 90 30-May-12 15-Sep-12 08-Nov-12 25-Feb-13 134 A9400 Order&Delivery- GRP Water Tank 100 11-Jun-12 08-Oct-12 16-Oct-12 16-Feb-13 106 A115090 Order&Delivery- Booster Pump 90 17-Jul-12 03-Nov-12 30-Oct-12 16-Feb-13 86 Fire FighitngFire Fighitng 140 27-Feb-12 08-Aug-12 09-May-12 31-Jan-13 143 A6710 Order&Delivery- Fire Pipes-Fittings-Valves 90 27-Feb-12 10-Jun-12 09-May-12 25-Aug-12 62 A6730 Order&Delivery- Sprinklers 90 27-Feb-12 10-Jun-12 20-Sep-12 08-Jan-13 174 A6750 Order&Delivery- Landing Valves 90 27-Feb-12 10-Jun-12 13-Oct-12 31-Jan-13 193 A6780 Order&Delivery- Foam Spary System for Generators 60 02-Apr-12 10-Jun-12 08-Nov-12 20-Jan-13 184 A9000 Order&Delivery- Fire Alarm Devices 90 08-Mar-12 21-Jun-12 25-Aug-12 11-Dec-12 142 A6740 Order&Delivery- Fire Extinguishers & Banket 90 14-Apr-12 28-Jul-12 01-Oct-12 19-Jan-13 143 A6760 Order&Delivery- Fire Hose Cabinets 90 14-Apr-12 28-Jul-12 13-Oct-12 31-Jan-13 153 A9230 Order&Delivery- Fire Fighting Pump 130 10-Mar-12 08-Aug-12 25-Aug-12 29-Jan-13 141 LPG SystemLPG System 125 25-Apr-12 20-Sep-12 13-Jan-13 24-Mar-13 152 A7180 Order&Delivery- LPG Pipes-Fittings-Valves 60 25-Apr-12 04-Jul-12 13-Jan-13 24-Mar-13 217 A7190 Order&Delivery- LPG Tanks( 2000 Gallons) 30 15-Aug-12 20-Sep-12 09-Feb-13 14-Mar-13 144 Coveying SysCoveying System 190 24-Apr-12 09-Dec-12 26-May-12 21-Feb-13 62 A1143 Order&Delivery- Brakets,Guide Rails and Others 100 24-Apr-12 21-Aug-12 26-May-12 22-Sep-12 27 A5820 Order&Delivery- Passenger Lifts 120 16-Jul-12 09-Dec-12 29-Sep-12 21-Feb-13 62 ElectricalElectrical 212 14-Mar-12 22-Nov-12 04-Jul-12 17-Feb-13 71 Cable Trays -Cable Trays - Cables 193 14-Mar-12 30-Oct-12 14-Jul-12 17-Dec-12 39 A6500 Order&Delivery- Cable Trays 45 14-Mar-12 05-May-12 14-Jul-12 05-Sep-12 103 A6480 Order&Delivery- LV Cable 45 20-Mar-12 10-May-12 29-Jul-12 20-Sep-12 111 A6510 Order&Delivery- Trunking 45 20-Mar-12 10-May-12 14-Jul-12 05-Sep-12 98 A6440 Order&Delivery- Bus Bars 100 02-Jul-12 30-Oct-12 16-Aug-12 17-Dec-12 39 Low CurrentLow Current Systems 140 14-Mar-12 27-Aug-12 23-Jul-12 06-Feb-13 134 A7150 Order&Delivery- MATV/ Interactive TV System 60 14-Mar-12 22-May-12 11-Sep-12 22-Nov-12 152 A6610 Order&Delivery- BMS 70 26-Mar-12 14-Jun-12 02-Sep-12 25-Nov-12 134 A6580 Order&Delivery- Central Battery System 90 18-Apr-12 01-Aug-12 18-Oct-12 06-Feb-13 154 A6990 Order&Delivery- GSM System 90 18-Apr-12 01-Aug-12 23-Sep-12 10-Jan-13 132 A6560 Order&Delivery- CCTV System 90 24-Apr-12 07-Aug-12 23-Jul-12 08-Nov-12 76 A6570 Order&Delivery- Access Control System 90 12-May-12 27-Aug-12 05-Aug-12 22-Nov-12 72 Electrical EquElectrical Equipments 212 14-Mar-12 22-Nov-12 04-Jul-12 17-Feb-13 71 A6470 Order&Delivery- DBs 100 14-Mar-12 09-Jul-12 04-Jul-12 01-Nov-12 95 A6450 Order&Delivery- MDBs 110 14-Mar-12 21-Jul-12 29-Aug-12 09-Jan-13 141 A6460 Order&Delivery- SMDBs 110 14-Mar-12 21-Jul-12 20-Sep-12 02-Feb-13 160 A6540 Order&Delivery- Generators 120 26-Mar-12 13-Aug-12 28-Aug-12 20-Jan-13 130 A6600 Order&Delivery- UPS 60 04-Jun-12 13-Aug-12 17-Nov-12 28-Jan-13 136 A1334 Order&Delivery- Telephone System 60 04-Jun-12 13-Aug-12 21-Oct-12 03-Jan-13 116 A6430 Order&Delivery- Transformers 80 16-Aug-12 22-Nov-12 12-Nov-12 17-Feb-13 71 A2345 Order&Delivery- RMU Unit 80 16-Aug-12 22-Nov-12 11-Nov-12 16-Feb-13 70 OthersOthers 70 14-Mar-12 03-Jun-12 17-Sep-12 11-Dec-12 157 A6620 Order&Delivery- Light Fixtures 70 14-Mar-12 03-Jun-12 17-Sep-12 11-Dec-12 157 Speciality WSpeciality Works 237 12-Apr-12 22-Jan-13 23-Jun-12 05-Jun-13 114 Swimming PoSwimming Pool 120 23-Jun-12 13-Nov-12 30-Jul-12 23-Mar-13 107 A5830 Order&Delivery- Finishes Items 80 23-Jun-12 25-Sep-12 23-Oct-12 30-Jan-13 103 A6920 Order&Delivery- Water Proofing for Swimming Pool 80 23-Jun-12 25-Sep-12 31-Oct-12 05-Feb-13 108 A9150 Order&Delivery- ElectricalItems 80 23-Jun-12 25-Sep-12 10-Nov-12 14-Feb-13 116 A9280 Order&Delivery- Sand Stone Pavers 80 23-Jun-12 25-Sep-12 18-Dec-12 23-Mar-13 147 A9160 Order&Delivery- Pocalin for Pool Deck 100 23-Jun-12 18-Oct-12 21-Nov-12 20-Mar-13 125 A44340 Order&Delivery- Swimming Pool Equipments 120 23-Jun-12 13-Nov-12 30-Jul-12 23-Dec-12 32 External FacaExternal Facade 145 16-Jul-12 08-Jan-13 18-Nov-12 28-Mar-13 67 A5740 Order&Delivery- Curtain Wall&Glazing 110 16-Jul-12 26-Nov-12 18-Nov-12 28-Mar-13 102 A5678 Order&Delivery- GRC 90 20-Sep-12 08-Jan-13 11-Dec-12 27-Mar-13 66 Facade CleanFacade Cleaning 110 28-Jul-12 09-Dec-12 29-Jan-13 05-Jun-13 151 A5870 Order&Delivery- Facade Cleaning System 110 28-Jul-12 09-Dec-12 29-Jan-13 05-Jun-13 151 Garbage ChuGarbage Chute 169 12-Apr-12 31-Oct-12 23-Jun-12 30-Jan-13 74 A5850 Order&Delivery- Pipes & Fittings 100 12-Apr-12 07-Aug-12 16-Jul-12 13-Nov-12 80 A9380 Order&Delivery- Equipments 150 21-Apr-12 15-Oct-12 31-Jul-12 30-Jan-13 86 A9390 Order&Delivery- Garbage Chutes 150 05-May-12 31-Oct-12 23-Jun-12 20-Dec-12 41 Linen ChuteLinen Chute 188 09-Jun-12 22-Jan-13 07-Jul-12 25-Feb-13 28 A114180 Order&Delivery- Pipes & Fittings 100 10-Jul-12 07-Nov-12 30-Jul-12 28-Nov-12 17 A114200 Order&Delivery- Linen Chutes 150 09-Jun-12 08-Dec-12 07-Jul-12 05-Jan-13 23 A114190 Order&Delivery- Equipments 150 24-Jul-12 22-Jan-13 28-Aug-12 25-Feb-13 28 ProvisionalProvisional Sum 293 23-Jun-12 09-Jun-13 07-Jul-12 29-Jul-13 43 Kitchen EquiKitchen Equipments 108 23-Jun-12 30-Oct-12 09-Jul-12 17-Nov-12 14 A8640 Order&Delivery- Kitchen Equipments 108 23-Jun-12 30-Oct-12 09-Jul-12 17-Nov-12 14 Lundary EquLundary Equipments 108 23-Jun-12 30-Oct-12 07-Jul-12 13-Nov-12 12 A114210 Order&Delivery- Laundary Equipments 108 23-Jun-12 30-Oct-12 07-Jul-12 13-Nov-12 12 Facade LightFacade Lighting 90 30-Jun-12 14-Oct-12 23-Jul-12 08-Nov-12 20 A115270 Order&Delivery- Facade Lighting 90 30-Jun-12 14-Oct-12 23-Jul-12 08-Nov-12 20 Cooking StatCooking Station 120 09-Jul-12 01-Dec-12 24-Oct-12 19-Mar-13 90 A124670 Order&Delivery- Cooking Station 120 09-Jul-12 01-Dec-12 24-Oct-12 19-Mar-13 90 Gymnasium EGymnasium Equipments 80 07-Mar-13 09-Jun-13 27-Apr-13 29-Jul-13 43 A45220 Order&Delivery- Gym Equipments 80 07-Mar-13 09-Jun-13 27-Apr-13 29-Jul-13 43 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Order&Delivery- Vanity Counters Order&Delivery- Hump Order&Delivery- Air Oulets Order&Delivery- Chilled Pipes Insulation Order&Delivery- Ducts Insulation Order&Delivery- Condensate Pipes Insulation Order&Delivery- FCUs Order&Delivery- HAVC Ducts Order&Delivery- Chilled Water Pipes-Fittings-Valves Order&Delivery- Condensate Pipes-Fittings-Valves Order&Delivery- FAHU Order&Delivery- AHU Order&Delivery- Chiller Order&Delivery- Primary Chilled Water Pump Order&Delivery- Heat Exchanger (HEX) Order&Delivery- Pumps for HEX Order&Delivery- Secpndry Chilled Water Pump Order&Delivery- Floor Drains Order&Delivery-PPR Pipes -Fittings-Valves (Water) Order&Delivery- uPVC Pipes-Fittings-Valves(Drainge) Order&Delivery- Sump Pump Order&Delivery- ElectricalHeaters Order&Delivery- Water Boiler Pump Order&Delivery- Water Boiler Tank Order&Delivery- Water Boiler Order&Delivery- Steam Pipes for Boilers Order&Delivery- Transfer Pump Order&Delivery- Sanitarywares Order&Delivery- GRP Water Tank Order&Delivery- Booster Pump Order&Delivery- Fire Pipes-Fittings-Valves Order&Delivery- Sprinklers Order&Delivery- Landing Valves Order&Delivery- Foam Spary System for Generators Order&Delivery- Fire Alarm Devices Order&Delivery- Fire Extinguishers & Banket Order&Delivery- Fire Hose Cabinets Order&Delivery- Fire Fighting Pump Order&Delivery- LPG Pipes-Fittings-Valves Order&Delivery- LPG Tanks( 2000 Gallons) Order&Delivery- Brakets,Guide Rails and Others Order&Delivery- Passenger Lifts Order&Delivery- Cable Trays Order&Delivery- LV Cable Order&Delivery- Trunking Order&Delivery- Bus Bars Order&Delivery- MATV/ Interactive TV System Order&Delivery- BMS Order&Delivery- Central Battery System Order&Delivery- GSM System Order&Delivery- CCTV System Order&Delivery- Access Control System Order&Delivery- DBs Order&Delivery- MDBs Order&Delivery- SMDBs Order&Delivery- Generators Order&Delivery- UPS Order&Delivery- Telephone System Order&Delivery- Transformers Order&Delivery- RMU Unit Order&Delivery- Light Fixtures Order&Delivery- Finishes Items Order&Delivery- Water Proofing for Swimming Pool Order&Delivery- Electrical Items Order&Delivery- Sand Stone Pavers Order&Delivery- Pocalin for Pool Deck Order&Delivery- Swimming Pool Equipments Order&Delivery- Curtain Wall&Glazing Order&Delivery- GRC Order&Delivery- Facade Cleaning System Order&Delivery- Pipes & Fittings Order&Delivery- Equipments Order&Delivery- Garbage Chutes Order&Delivery- Pipes & Fittings Order&Delivery- Linen Chutes Order&Delivery- Equipments Order&Delivery- Kitchen Equipments Order&Delivery- Laundary Equipments Order&Delivery- Facade Lighting Order&Delivery- Cooking Station Order&Delivery- Gym Equipments Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 14 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 15. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float ConstructiConstruction 516 04-Jan-12 10-Sep-13 04-Jan-12 02-Oct-13 19 Civil PackagCivil Package 304 04-Jan-12 02-Jan-13 04-Jan-12 05-Jun-13 131 Hotel AparteHotel Apartements (Block A) 249 04-Jan-12 24-Oct-12 04-Jan-12 05-Jun-13 186 Foundation LFoundation Level 34 04-Jan-12 13-Feb-12 04-Jan-12 13-Feb-12 0 Earth WorksEarth Works 12 04-Jan-12 17-Jan-12 04-Jan-12 17-Jan-12 0 A1370 Excavation and Compaction 7 04-Jan-12 11-Jan-12 04-Jan-12 11-Jan-12 0 A1400 Base Coarse and Compaction 8 09-Jan-12 17-Jan-12 09-Jan-12 17-Jan-12 0 Deep FoundDeep Foundation 25 15-Jan-12 13-Feb-12 15-Jan-12 13-Feb-12 0 A1060 Laying Polythene Sheet & Blinding 7 15-Jan-12 22-Jan-12 15-Jan-12 22-Jan-12 0 A1080 Water Proofing & Screed 8 19-Jan-12 28-Jan-12 19-Jan-12 28-Jan-12 0 A1160 MEP Works inside Raft Slab 7 29-Jan-12 06-Feb-12 06-Feb-12 13-Feb-12 6 A1100 Raft Slab 1000 mm RC Works 16 25-Jan-12 13-Feb-12 25-Jan-12 13-Feb-12 0 1st Basemen1st Basement Floor Slab 80 14-Feb-12 16-May-12 15-Feb-12 15-Sep-12 101 Walls and CWalls and Columns 15 14-Feb-12 01-Mar-12 15-Feb-12 04-Mar-12 2 A1110 Core Wall RC Works 6 16-Feb-12 22-Feb-12 16-Feb-12 22-Feb-12 0 A1130 Ramp Wall RC Works 6 19-Feb-12 25-Feb-12 27-Feb-12 04-Mar-12 7 A1140 Columns RC Works 10 14-Feb-12 25-Feb-12 15-Feb-12 26-Feb-12 1 A1120 Retaining Wall 250 mm RC Works 15 14-Feb-12 01-Mar-12 15-Feb-12 03-Mar-12 1 SlabSlab 73 20-Feb-12 14-May-12 20-Feb-12 15-Sep-12 103 A1200 Ramp Slab RC Works 7 26-Feb-12 04-Mar-12 05-Mar-12 12-Mar-12 7 A1150 MEP Works inside Slab 7 03-Mar-12 10-Mar-12 05-Mar-12 12-Mar-12 2 A1170 1st Basement Floor Slab RC Works 19 20-Feb-12 12-Mar-12 20-Feb-12 12-Mar-12 0 A1180 Curing for Slab 3 13-Mar-12 15-Mar-12 06-Aug-12 08-Aug-12 124 A1190 Strike Formwork 3 10-Apr-12 12-Apr-12 09-Aug-12 12-Aug-12 103 A1210 Pouring of Light Weight Concrete 2 14-Apr-12 15-Apr-12 13-Aug-12 14-Aug-12 103 A1320 Water Proofing Membrane for Ret. Walls 10 16-Apr-12 26-Apr-12 15-Aug-12 28-Aug-12 103 A1330 Gunited Concrete 50 mm for Ret. Walls 10 28-Apr-12 08-May-12 29-Aug-12 09-Sep-12 103 A1360 Backfilling 5 09-May-12 14-May-12 10-Sep-12 15-Sep-12 103 StairsStairs 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101 Stairs 1Stairs 1 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101 A1380 Stairs RC Works (2nd Basement to 1st Basement) 6 10-May-12 16-May-12 09-Sep-12 15-Sep-12 101 Ground FloorGround Floor Slab 81 13-Mar-12 14-Jun-12 13-Mar-12 18-Sep-12 79 Walls and CWalls and Columns 15 13-Mar-12 29-Mar-12 13-Mar-12 01-Apr-12 2 A1220 Core Wall RC Works 6 14-Mar-12 20-Mar-12 14-Mar-12 20-Mar-12 0 A1240 Ramp Wall RC Works 7 17-Mar-12 24-Mar-12 25-Mar-12 01-Apr-12 7 A1250 Columns RC Works 10 13-Mar-12 24-Mar-12 13-Mar-12 24-Mar-12 0 A1230 Retaining Wall 250 mm RC Works 15 13-Mar-12 29-Mar-12 13-Mar-12 29-Mar-12 0 SlabSlab 72 19-Mar-12 10-Jun-12 19-Mar-12 18-Sep-12 83 A1300 Ramp Slab RC Works 7 25-Mar-12 01-Apr-12 02-Apr-12 09-Apr-12 7 A1260 MEP Works inside Slab 6 31-Mar-12 05-Apr-12 03-Apr-12 09-Apr-12 3 A1270 Ground Floor Slab RC Works 19 19-Mar-12 09-Apr-12 19-Mar-12 09-Apr-12 0 A1280 Curing for Slab 3 10-Apr-12 12-Apr-12 26-Jul-12 29-Jul-12 91 A1290 Strike Formwork 3 07-May-12 09-May-12 30-Jul-12 01-Aug-12 71 A1310 Pouring of Light Weight Concrete 2 10-May-12 12-May-12 16-Aug-12 18-Aug-12 83 A1340 Water Proofing Membrane for Ret. Walls 10 13-May-12 23-May-12 21-Aug-12 01-Sep-12 83 A1350 Gunited Concrete 50 mm for Ret. Walls 10 24-May-12 04-Jun-12 02-Sep-12 12-Sep-12 83 A1520 Backfilling 5 05-Jun-12 10-Jun-12 13-Sep-12 18-Sep-12 83 StairsStairs 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79 Stair 1Stair 1 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79 A1530 Stairs RC Works (1st Basement to Ground) 6 09-Jun-12 14-Jun-12 12-Sep-12 18-Sep-12 79 1st Floor Slab1st Floor Slab 78 10-Apr-12 10-Jul-12 10-Apr-12 29-Sep-12 67 Walls and CWalls and Columns 9 10-Apr-12 19-Apr-12 10-Apr-12 19-Apr-12 0 A1390 Core Wall RC Works 6 10-Apr-12 16-Apr-12 10-Apr-12 16-Apr-12 0 A1420 Columns RC Works 9 10-Apr-12 19-Apr-12 10-Apr-12 19-Apr-12 0 SlabSlab 46 16-Apr-12 07-Jun-12 16-Apr-12 11-Sep-12 79 A1430 MEP Works inside Slab 5 21-Apr-12 25-Apr-12 02-May-12 07-May-12 10 A1440 1st Floor Slab RC Works 19 16-Apr-12 07-May-12 16-Apr-12 07-May-12 0 A1450 Curing for Slab 3 08-May-12 10-May-12 05-Sep-12 08-Sep-12 100 A1460 Strike Formwork 3 05-Jun-12 07-Jun-12 09-Sep-12 11-Sep-12 79 StairsStairs 6 04-Jul-12 10-Jul-12 16-Sep-12 29-Sep-12 67 Stair 1Stair 1 6 04-Jul-12 10-Jul-12 16-Sep-12 22-Sep-12 61 A1540 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 16-Sep-12 22-Sep-12 61 Stair 2Stair 2 6 04-Jul-12 10-Jul-12 19-Sep-12 25-Sep-12 64 A1550 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 19-Sep-12 25-Sep-12 64 Stair 3Stair 3 6 04-Jul-12 10-Jul-12 23-Sep-12 29-Sep-12 67 A111130 Stairs RC Works (Ground to 1st floor) 6 04-Jul-12 10-Jul-12 23-Sep-12 29-Sep-12 67 2nd Floor Sl2nd Floor Slab 70 08-May-12 29-Jul-12 08-May-12 06-Oct-12 57 Walls and CWalls and Columns 9 08-May-12 17-May-12 08-May-12 17-May-12 0 A1560 Core Wall RC Works 6 08-May-12 14-May-12 08-May-12 14-May-12 0 A1570 Columns RC Works 9 08-May-12 17-May-12 08-May-12 17-May-12 0 SlabSlab 43 14-May-12 03-Jul-12 14-May-12 26-Jul-12 20 A1580 MEP Works inside Slab 5 19-May-12 23-May-12 30-May-12 04-Jun-12 10 A1590 2nd Floor Slab RC Works 19 14-May-12 04-Jun-12 14-May-12 04-Jun-12 0 A1600 Curing for Slab 3 05-Jun-12 07-Jun-12 21-Jul-12 23-Jul-12 38 A1610 Strike Formwork 3 01-Jul-12 03-Jul-12 24-Jul-12 26-Jul-12 20 StairsStairs 6 23-Jul-12 29-Jul-12 26-Sep-12 06-Oct-12 57 Stair 1Stair 1 6 23-Jul-12 29-Jul-12 26-Sep-12 02-Oct-12 54 A1630 Stairs RC Works (1st to 2nd) 6 23-Jul-12 29-Jul-12 26-Sep-12 02-Oct-12 54 Stair 2Stair 2 6 23-Jul-12 29-Jul-12 30-Sep-12 06-Oct-12 57 A1640 Stairs RC Works (1st to 2nd) 6 23-Jul-12 29-Jul-12 30-Sep-12 06-Oct-12 57 3rd Floor Slab3rd Floor Slab 58 05-Jun-12 12-Aug-12 05-Jun-12 13-Oct-12 51 Walls and CWalls and Columns 9 05-Jun-12 14-Jun-12 05-Jun-12 14-Jun-12 0 A1650 Core Wall RC Works 6 05-Jun-12 11-Jun-12 05-Jun-12 11-Jun-12 0 A1660 Columns RC Works 9 05-Jun-12 14-Jun-12 05-Jun-12 14-Jun-12 0 SlabSlab 36 10-Jun-12 22-Jul-12 10-Jun-12 31-Jul-12 8 A1670 MEP Works inside Slab 5 14-Jun-12 20-Jun-12 14-Jun-12 20-Jun-12 0 A1680 3rd Floor Slab RC Works 9 10-Jun-12 20-Jun-12 10-Jun-12 20-Jun-12 0 A1690 Curing for Slab 3 21-Jun-12 24-Jun-12 25-Jul-12 28-Jul-12 29 A1700 Strike Formwork 3 19-Jul-12 22-Jul-12 29-Jul-12 31-Jul-12 8 StairsStairs 6 06-Aug-12 12-Aug-12 03-Oct-12 13-Oct-12 51 Stair 1Stair 1 6 06-Aug-12 12-Aug-12 03-Oct-12 09-Oct-12 48 A1710 Stairs RC Works (2nd to 3rd) 6 06-Aug-12 12-Aug-12 03-Oct-12 09-Oct-12 48 Stair 2Stair 2 6 06-Aug-12 12-Aug-12 07-Oct-12 13-Oct-12 51 A1720 Stairs RC Works (2nd to 3rd) 6 06-Aug-12 12-Aug-12 07-Oct-12 13-Oct-12 51 4th Floor Slab4th Floor Slab 57 21-Jun-12 28-Aug-12 21-Jun-12 20-Oct-12 45 Walls and CWalls and Columns 9 21-Jun-12 01-Jul-12 21-Jun-12 01-Jul-12 0 A1730 Core Wall RC Works 6 21-Jun-12 27-Jun-12 21-Jun-12 27-Jun-12 0 A1740 Columns RC Works 9 21-Jun-12 01-Jul-12 21-Jun-12 01-Jul-12 0 SlabSlab 35 26-Jun-12 05-Aug-12 26-Jun-12 05-Aug-12 0 A1750 MEP Works inside Slab 5 30-Jun-12 04-Jul-12 30-Jun-12 04-Jul-12 0 A1760 4th Slab RC Works 8 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 A1770 Curing for Slab 3 05-Jul-12 08-Jul-12 30-Jul-12 01-Aug-12 21 A1780 Strike Formwork 3 02-Aug-12 05-Aug-12 02-Aug-12 05-Aug-12 0 StairsStairs 6 22-Aug-12 28-Aug-12 10-Oct-12 20-Oct-12 45 Stair 1Stair 1 6 22-Aug-12 28-Aug-12 10-Oct-12 16-Oct-12 42 A1790 Stairs RC Works (3rd to 4th) 6 22-Aug-12 28-Aug-12 10-Oct-12 16-Oct-12 42 Stair 2Stair 2 6 22-Aug-12 28-Aug-12 14-Oct-12 20-Oct-12 45 A1800 Stairs RC Works (3rd to 4th) 6 22-Aug-12 28-Aug-12 14-Oct-12 20-Oct-12 45 5th Floor Slab5th Floor Slab 57 05-Jul-12 11-Sep-12 14-Jul-12 29-Oct-12 39 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Excavation and Compaction Base Coarse and Compaction Laying Polythene Sheet & Blinding Water Proofing & Screed MEP Works inside Raft Slab Raft Slab 1000 mm RC Works Core Wall RC Works Ramp Wall RC Works Columns RC Works Retaining Wall 250 mm RC Works Ramp Slab RC Works MEP Works inside Slab 1st Basement Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (2nd Basement to 1st Basement) Core Wall RC Works Ramp Wall RC Works Columns RC Works Retaining Wall 250 mm RC Works Ramp Slab RC Works MEP Works inside Slab Ground Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (1st Basement to Ground) Core Wall RC Works Columns RC Works MEP Works inside Slab 1st Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Core Wall RC Works Columns RC Works MEP Works inside Slab 2nd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (1st to 2nd) Stairs RC Works (1st to 2nd) Core Wall RC Works Columns RC Works MEP Works inside Slab 3rd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (2nd to 3rd) Stairs RC Works (2nd to 3rd) Core Wall RC Works Columns RC Works MEP Works inside Slab 4th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (3rd to 4th) Stairs RC Works (3rd to 4th) Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 15 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 16. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Walls and CWalls and Columns 9 05-Jul-12 15-Jul-12 14-Jul-12 23-Jul-12 7 A1810 Core Wall RC Works 6 05-Jul-12 11-Jul-12 14-Jul-12 19-Jul-12 7 A1820 Columns RC Works 9 05-Jul-12 15-Jul-12 14-Jul-12 23-Jul-12 7 SlabSlab 36 09-Jul-12 21-Aug-12 17-Jul-12 06-Sep-12 14 A1830 MEP Works inside Slab 5 14-Jul-12 18-Jul-12 23-Jul-12 28-Jul-12 8 A1840 5th Slab RC Works 10 09-Jul-12 19-Jul-12 17-Jul-12 28-Jul-12 7 A1850 Curing for Slab 3 21-Jul-12 23-Jul-12 01-Sep-12 03-Sep-12 34 A1860 Strike Formwork 3 16-Aug-12 21-Aug-12 04-Sep-12 06-Sep-12 14 StairsStairs 6 05-Sep-12 11-Sep-12 17-Oct-12 29-Oct-12 39 Stair 1Stair 1 6 05-Sep-12 11-Sep-12 17-Oct-12 23-Oct-12 36 A1870 Stairs RC Works (4th to 5th) 6 05-Sep-12 11-Sep-12 17-Oct-12 23-Oct-12 36 Stair 2Stair 2 6 05-Sep-12 11-Sep-12 21-Oct-12 29-Oct-12 39 A1880 Stairs RC Works (4th to 5th) 6 05-Sep-12 11-Sep-12 21-Oct-12 29-Oct-12 39 6th Floor Slab6th Floor Slab 57 21-Jul-12 26-Sep-12 29-Jul-12 06-Nov-12 33 Walls and CWalls and Columns 9 21-Jul-12 30-Jul-12 29-Jul-12 07-Aug-12 7 A1890 Core Wall RC Works 6 21-Jul-12 26-Jul-12 29-Jul-12 04-Aug-12 7 A1900 Columns RC Works 9 21-Jul-12 30-Jul-12 29-Jul-12 07-Aug-12 7 SlabSlab 34 25-Jul-12 04-Sep-12 02-Aug-12 20-Sep-12 14 A1910 MEP Works inside Slab 5 29-Jul-12 02-Aug-12 07-Aug-12 12-Aug-12 8 A1920 6th Slab RC Works (L + 9.20) 9 25-Jul-12 04-Aug-12 02-Aug-12 12-Aug-12 7 A1930 Curing for Slab 3 05-Aug-12 07-Aug-12 15-Sep-12 17-Sep-12 33 A1940 Strike Formwork 3 02-Sep-12 04-Sep-12 18-Sep-12 20-Sep-12 14 StairsStairs 6 20-Sep-12 26-Sep-12 24-Oct-12 06-Nov-12 33 Stair 1Stair 1 6 20-Sep-12 26-Sep-12 24-Oct-12 01-Nov-12 29 A1950 Stairs RC Works (5th to 6th) 6 20-Sep-12 26-Sep-12 24-Oct-12 01-Nov-12 29 Stair 2Stair 2 6 20-Sep-12 26-Sep-12 31-Oct-12 06-Nov-12 33 A1960 Stairs RC Works (5th to 6th) 6 20-Sep-12 26-Sep-12 31-Oct-12 06-Nov-12 33 7th Floor Slab7th Floor Slab 56 05-Aug-12 10-Oct-12 13-Aug-12 28-Nov-12 39 Walls and CWalls and Columns 9 05-Aug-12 14-Aug-12 13-Aug-12 25-Aug-12 7 A1970 Core Wall RC Works 6 05-Aug-12 11-Aug-12 13-Aug-12 21-Aug-12 7 A1980 Columns RC Works 9 05-Aug-12 14-Aug-12 13-Aug-12 25-Aug-12 7 SlabSlab 34 09-Aug-12 19-Sep-12 18-Aug-12 27-Sep-12 7 A1990 MEP Works inside Slab 5 13-Aug-12 18-Aug-12 25-Aug-12 29-Aug-12 8 A2000 7th Slab RC Works 9 09-Aug-12 21-Aug-12 18-Aug-12 29-Aug-12 7 A2010 Curing for Slab 3 22-Aug-12 25-Aug-12 22-Sep-12 24-Sep-12 26 A2020 Strike Formwork 3 17-Sep-12 19-Sep-12 25-Sep-12 27-Sep-12 7 StairsStairs 6 04-Oct-12 10-Oct-12 05-Nov-12 28-Nov-12 39 Stair 1Stair 1 6 04-Oct-12 10-Oct-12 05-Nov-12 11-Nov-12 25 A2030 Stairs RC Works (6th to 7th) 6 04-Oct-12 10-Oct-12 05-Nov-12 11-Nov-12 25 Stair 2Stair 2 6 04-Oct-12 10-Oct-12 22-Nov-12 28-Nov-12 39 A2040 Stairs RC Works (6th to 7th) 6 04-Oct-12 10-Oct-12 22-Nov-12 28-Nov-12 39 Roof Floor SlRoof Floor Slab 55 22-Aug-12 24-Oct-12 30-Aug-12 05-Jun-13 186 Walls and CWalls and Columns 8 22-Aug-12 30-Aug-12 30-Aug-12 11-Sep-12 10 A2050 Core Wall RC Works 5 22-Aug-12 27-Aug-12 30-Aug-12 04-Sep-12 7 A2060 Columns RC Works 8 22-Aug-12 30-Aug-12 03-Sep-12 11-Sep-12 10 SlabSlab 34 26-Aug-12 03-Oct-12 06-Sep-12 10-Nov-12 30 A2070 MEP Works inside Slab 4 29-Aug-12 02-Sep-12 11-Sep-12 15-Sep-12 11 A2080 Roof Floor Slab RC Works 8 26-Aug-12 03-Sep-12 06-Sep-12 15-Sep-12 10 A2090 Curing for Slab 3 04-Sep-12 06-Sep-12 07-Nov-12 10-Nov-12 53 A2100 Strike Formwork 3 01-Oct-12 03-Oct-12 13-Oct-12 15-Oct-12 10 ParapetsParapets 10 08-Sep-12 18-Sep-12 26-May-13 05-Jun-13 217 A104120 Parapets RC Works 10 08-Sep-12 18-Sep-12 26-May-13 05-Jun-13 217 Chillers FouChillers Foundation 5 08-Sep-12 12-Sep-12 11-Nov-12 17-Nov-12 53 A117090 Chillers Foundations RC Works 5 08-Sep-12 12-Sep-12 11-Nov-12 17-Nov-12 53 StairsStairs 6 18-Oct-12 24-Oct-12 10-Dec-12 02-Jan-13 55 Stair 1Stair 1 6 18-Oct-12 24-Oct-12 10-Dec-12 16-Dec-12 41 A2110 Stairs RC Works (7th to Roof) 6 18-Oct-12 24-Oct-12 10-Dec-12 16-Dec-12 41 Stair 2Stair 2 6 18-Oct-12 24-Oct-12 26-Dec-12 02-Jan-13 55 A2120 Stairs RC Works (7th to Roof) 6 18-Oct-12 24-Oct-12 26-Dec-12 02-Jan-13 55 Upper Roof LUpper Roof Level 44 04-Sep-12 24-Oct-12 17-Sep-12 20-Feb-13 96 ColumnsColumns 9 04-Sep-12 13-Sep-12 17-Sep-12 26-Sep-12 11 A2140 Columns RC Works 9 04-Sep-12 13-Sep-12 17-Sep-12 26-Sep-12 11 SlabsSlabs 34 09-Sep-12 17-Oct-12 22-Sep-12 29-Jan-13 83 A2150 MEP Works inside Slab 4 12-Sep-12 16-Sep-12 26-Sep-12 30-Sep-12 12 A2160 Upper Roof Level Slab RC Works 8 09-Sep-12 17-Sep-12 22-Sep-12 30-Sep-12 11 A2170 Curing for Slab 3 18-Sep-12 20-Sep-12 27-Jan-13 29-Jan-13 106 A2180 Strike Formwork 3 15-Oct-12 17-Oct-12 30-Oct-12 01-Nov-12 11 StairsStairs 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96 Stair 2Stair 2 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96 A2200 Stairs RC Works (Roof to Upper Roof) 6 18-Oct-12 24-Oct-12 14-Feb-13 20-Feb-13 96 Hotel (BlockHotel (Block B) 241 19-Mar-12 02-Jan-13 27-Mar-12 05-Jun-13 131 Foundation LFoundation Level 44 19-Mar-12 08-May-12 27-Mar-12 20-May-12 10 Earth WorksEarth Works 13 19-Mar-12 02-Apr-12 27-Mar-12 24-Apr-12 19 Part 1 (B1)Part 1 (B1) 13 19-Mar-12 02-Apr-12 27-Mar-12 10-Apr-12 7 A12320 Excavation and Compaction 8 19-Mar-12 27-Mar-12 27-Mar-12 04-Apr-12 7 A12330 Base Coarse and Compaction 8 25-Mar-12 02-Apr-12 02-Apr-12 10-Apr-12 7 Part 2 (B2)Part 2 (B2) 13 19-Mar-12 02-Apr-12 10-Apr-12 24-Apr-12 19 A12730 Excavation and Compaction 8 19-Mar-12 27-Mar-12 10-Apr-12 18-Apr-12 19 A12740 Base Coarse and Compaction 8 25-Mar-12 02-Apr-12 16-Apr-12 24-Apr-12 19 Deep FoundDeep Foundation 35 29-Mar-12 08-May-12 07-Apr-12 20-May-12 10 Part 1 (B1)Part 1 (B1) 25 29-Mar-12 26-Apr-12 07-Apr-12 05-May-12 7 A11520 Laying Polythene Sheet & Blinding 5 29-Mar-12 03-Apr-12 07-Apr-12 11-Apr-12 7 A11530 Water Proofing & Screed 7 02-Apr-12 09-Apr-12 10-Apr-12 17-Apr-12 7 A11580 MEP Works inside Raft Slab 7 10-Apr-12 17-Apr-12 28-Apr-12 05-May-12 15 A11540 Raft Slab 1000 mm RC Works (Part 1) 18 07-Apr-12 26-Apr-12 15-Apr-12 05-May-12 7 Part 2 (B2)Part 2 (B2) 35 29-Mar-12 08-May-12 21-Apr-12 20-May-12 10 A12750 Laying Polythene Sheet & Blinding 4 29-Mar-12 02-Apr-12 21-Apr-12 24-Apr-12 19 A12760 Water Proofing & Screed 6 02-Apr-12 08-Apr-12 24-Apr-12 30-Apr-12 19 A12770 MEP Works inside Raft Slab 10 18-Apr-12 29-Apr-12 09-May-12 20-May-12 18 A12780 Raft Slab 1000 mm RC Works (Part 2) 18 18-Apr-12 08-May-12 30-Apr-12 20-May-12 10 1st Basemen1st Basement Floor Slab 79 28-Apr-12 29-Jul-12 06-May-12 26-Jan-13 147 Walls and CWalls and Columns 20 28-Apr-12 20-May-12 06-May-12 05-Jun-12 14 Part 1 (B1)Part 1 (B1) 10 28-Apr-12 08-May-12 06-May-12 16-May-12 7 A11570 Columns RC Works 6 28-Apr-12 03-May-12 07-May-12 13-May-12 8 A12340 Tank Wall RC Works 6 29-Apr-12 05-May-12 07-May-12 13-May-12 7 A11550 Core Wall RC Works 8 30-Apr-12 08-May-12 08-May-12 16-May-12 7 A11560 Retaining Wall 250 mm RC Works (Part 1) 10 28-Apr-12 08-May-12 06-May-12 16-May-12 7 Part 2 (B2)Part 2 (B2) 10 09-May-12 20-May-12 21-May-12 05-Jun-12 14 A12610 Ramp Wall RC Works 5 09-May-12 14-May-12 21-May-12 26-May-12 10 A12790 Columns RC Works 6 09-May-12 15-May-12 21-May-12 27-May-12 10 A12800 Tank Wall RC Works 6 10-May-12 16-May-12 28-May-12 03-Jun-12 15 A12810 Core Wall RC Works 6 12-May-12 17-May-12 28-May-12 03-Jun-12 14 A12820 Retaining Wall 250 mm RC Works (Part 2) 8 12-May-12 20-May-12 28-May-12 05-Jun-12 14 SlabSlab 63 03-May-12 16-Jul-12 12-May-12 26-Jan-13 158 A11590 MEP Works inside Slab 5 12-May-12 16-May-12 28-May-12 02-Jun-12 14 A12200 Ramp Slab RC Works 6 15-May-12 21-May-12 27-May-12 02-Jun-12 10 A11600 1st Basement Floor Slab RC Works 19 03-May-12 24-May-12 12-May-12 02-Jun-12 7 A11610 Curing for Slab 3 26-May-12 28-May-12 28-Nov-12 01-Dec-12 154 A11620 Strike Formwork 3 21-Jun-12 24-Jun-12 03-Dec-12 05-Dec-12 135 A11630 Pouring of Light Weight Concrete 2 25-Jun-12 26-Jun-12 03-Jan-13 05-Jan-13 158 A11720 Water Proofing Membrane for Ret. Walls 7 27-Jun-12 04-Jul-12 06-Jan-13 13-Jan-13 158 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Core Wall RC Works Columns RC Works MEP Works inside Slab 5th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (4th to 5th) Stairs RC Works (4th to 5th) Core Wall RC Works Columns RC Works MEP Works inside Slab 6th Slab RC Works (L + 9.20) Curing for Slab Strike Formwork Stairs RC Works (5th to 6th) Stairs RC Works (5th to 6th) Core Wall RC Works Columns RC Works MEP Works inside Slab 7th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (6th to 7th) Stairs RC Works (6th to 7th) Core Wall RC Works Columns RC Works MEP Works inside Slab Roof Floor Slab RC Works Curing for Slab Strike Formwork Parapets RC Works Chillers Foundations RC Works Stairs RC Works (7th to Roof) Stairs RC Works (7th to Roof) Columns RC Works MEP Works inside Slab Upper Roof Level Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (Roof to Upper Roof) Excavation and Compaction Base Coarse and Compaction Excavation and Compaction Base Coarse and Compaction Laying Polythene Sheet & Blinding Water Proofing & Screed MEP Works inside Raft Slab Raft Slab 1000 mm RC Works (Part 1) Laying Polythene Sheet & Blinding Water Proofing & Screed MEP Works inside Raft Slab Raft Slab 1000 mm RC Works (Part 2) Columns RC Works Tank WallRC Works Core Wall RC Works Retaining Wall 250 mm RC Works (Part 1) Ramp Wall RC Works Columns RC Works Tank WallRC Works Core Wall RC Works Retaining Wall 250 mm RC Works (Part 2) MEP Works inside Slab Ramp Slab RC Works 1st Basement Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 16 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 17. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A11730 Gunited Concrete 50 mm for Ret. Walls 7 05-Jul-12 12-Jul-12 14-Jan-13 21-Jan-13 158 A11820 Backfilling 3 14-Jul-12 16-Jul-12 22-Jan-13 26-Jan-13 158 StairsStairs 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 Stairs 1Stairs 1 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 A12350 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 Stairs 2Stairs 2 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 A12360 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 Stairs 3Stairs 3 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 A12370 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Jul-12 29-Jul-12 19-Jan-13 26-Jan-13 147 Ground FloorGround Floor Slab 76 26-May-12 25-Aug-12 03-Jun-12 02-Feb-13 132 Walls and CWalls and Columns 21 26-May-12 19-Jun-12 03-Jun-12 27-Jun-12 7 A117050 Ramp Wall RC Works 6 26-May-12 31-May-12 16-Jun-12 23-Jun-12 18 A11660 Columns RC Works 11 26-May-12 06-Jun-12 03-Jun-12 14-Jun-12 7 A11640 Core Wall RC Works 15 27-May-12 12-Jun-12 04-Jun-12 21-Jun-12 7 A11650 Retaining Wall 250 mm RC Works 21 26-May-12 19-Jun-12 03-Jun-12 27-Jun-12 7 SlabSlab 64 30-May-12 13-Aug-12 07-Jun-12 02-Feb-13 140 A117060 Ramp Slab RC Works 7 02-Jun-12 09-Jun-12 24-Jun-12 01-Jul-12 18 A11670 MEP Works inside Slab 10 02-Jun-12 12-Jun-12 20-Jun-12 01-Jul-12 15 A11680 Ground Floor Slab RC Works 20 30-May-12 23-Jun-12 07-Jun-12 01-Jul-12 7 A11690 Curing for Slab 3 24-Jun-12 26-Jun-12 27-Sep-12 30-Sep-12 80 A11700 Strike Formwork 3 19-Jul-12 22-Jul-12 01-Oct-12 03-Oct-12 61 A11710 Pouring of Light Weight Concrete 2 23-Jul-12 24-Jul-12 10-Jan-13 12-Jan-13 140 A11740 Water Proofing Membrane for Ret. Walls 7 25-Jul-12 01-Aug-12 13-Jan-13 20-Jan-13 140 A11750 Gunited Concrete 50 mm for Ret. Walls 7 02-Aug-12 09-Aug-12 21-Jan-13 29-Jan-13 140 A11830 Backfilling 3 11-Aug-12 13-Aug-12 30-Jan-13 02-Feb-13 140 StairsStairs 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 Stairs 1Stairs 1 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 A12380 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 Stairs 2Stairs 2 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 A12390 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 Stairs 3Stairs 3 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 A12400 Stairs RC Works (1st Basement toGround) 6 16-Aug-12 25-Aug-12 27-Jan-13 02-Feb-13 132 1st Floor Slab1st Floor Slab 72 24-Jun-12 17-Sep-12 02-Jul-12 25-Feb-13 132 Walls and CWalls and Columns 9 24-Jun-12 03-Jul-12 02-Jul-12 11-Jul-12 7 A11760 Core Wall RC Works 6 24-Jun-12 30-Jun-12 02-Jul-12 08-Jul-12 7 A11770 Columns RC Works 9 24-Jun-12 03-Jul-12 02-Jul-12 11-Jul-12 7 SlabSlab 42 28-Jun-12 15-Aug-12 07-Jul-12 23-Oct-12 57 A11780 MEP Works inside Slab 5 04-Jul-12 09-Jul-12 18-Jul-12 23-Jul-12 12 A11790 1st Floor Slab RC Works 15 28-Jun-12 15-Jul-12 07-Jul-12 23-Jul-12 7 A11800 Curing for Slab 3 16-Jul-12 18-Jul-12 17-Oct-12 20-Oct-12 78 A11810 Strike Formwork 3 13-Aug-12 15-Aug-12 21-Oct-12 23-Oct-12 57 StairsStairs 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 Stairs 1Stairs 1 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 A12410 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 Stairs 2Stairs 2 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 A12420 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 Stairs 3Stairs 3 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 A12430 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 Stairs 4Stairs 4 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 A109130 Stairs RC Works (Ground to 1st floor) 6 11-Sep-12 17-Sep-12 19-Feb-13 25-Feb-13 132 2nd Floor Sl2nd Floor Slab 66 16-Jul-12 02-Oct-12 24-Jul-12 25-Feb-13 119 Walls and CWalls and Columns 9 16-Jul-12 25-Jul-12 24-Jul-12 02-Aug-12 7 A11840 Core Wall RC Works 6 16-Jul-12 22-Jul-12 24-Jul-12 30-Jul-12 7 A11850 Columns RC Works 9 16-Jul-12 25-Jul-12 24-Jul-12 02-Aug-12 7 SlabSlab 43 21-Jul-12 10-Sep-12 29-Jul-12 04-Oct-12 21 A11860 MEP Works inside Slab 5 26-Jul-12 31-Jul-12 13-Aug-12 18-Aug-12 15 A11870 2nd Floor Slab RC Works 18 21-Jul-12 09-Aug-12 29-Jul-12 18-Aug-12 7 A11880 Curing for Slab 3 11-Aug-12 13-Aug-12 29-Sep-12 01-Oct-12 40 A11890 Strike Formwork 3 08-Sep-12 10-Sep-12 02-Oct-12 04-Oct-12 21 StairsStairs 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 Stairs 1Stairs 1 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 A12440 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 Stairs 2Stairs 2 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 A12450 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 Stairs 3Stairs 3 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 A12460 Stairs RC Works (1st to 2nd) 6 26-Sep-12 02-Oct-12 19-Feb-13 25-Feb-13 119 3rd Floor Slab3rd Floor Slab 55 11-Aug-12 15-Oct-12 21-Aug-12 25-Feb-13 108 Walls and CWalls and Columns 6 11-Aug-12 16-Aug-12 21-Aug-12 27-Aug-12 7 A11900 Core Wall RC Works 3 11-Aug-12 13-Aug-12 21-Aug-12 23-Aug-12 7 A11910 Columns RC Works 6 11-Aug-12 16-Aug-12 21-Aug-12 27-Aug-12 7 SlabSlab 35 14-Aug-12 25-Sep-12 25-Aug-12 20-Oct-12 21 A11920 MEP Works inside Slab 3 18-Aug-12 22-Aug-12 30-Aug-12 02-Sep-12 9 A11930 3rd Floor Slab RC Works 8 14-Aug-12 25-Aug-12 25-Aug-12 02-Sep-12 7 A11940 Curing for Slab 3 26-Aug-12 28-Aug-12 14-Oct-12 16-Oct-12 42 A11950 Strike Formwork 3 23-Sep-12 25-Sep-12 17-Oct-12 20-Oct-12 21 StairsStairs 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 Stairs 1Stairs 1 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 A12470 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 Stairs 2Stairs 2 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 A12480 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 Stairs 3Stairs 3 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 A12490 Stairs RC Works (2nd to 3rd) 6 09-Oct-12 15-Oct-12 19-Feb-13 25-Feb-13 108 4th Floor Slab4th Floor Slab 54 26-Aug-12 29-Oct-12 03-Sep-12 03-Feb-13 79 Walls and CWalls and Columns 6 26-Aug-12 01-Sep-12 03-Sep-12 09-Sep-12 7 A11960 Core Wall RC Works 3 26-Aug-12 28-Aug-12 03-Sep-12 05-Sep-12 7 A11970 Columns RC Works 6 26-Aug-12 01-Sep-12 03-Sep-12 09-Sep-12 7 SlabSlab 35 29-Aug-12 08-Oct-12 06-Sep-12 20-Oct-12 10 A11980 MEP Works inside Slab 5 02-Sep-12 06-Sep-12 11-Sep-12 16-Sep-12 8 A11990 4th Slab RC Works 9 29-Aug-12 08-Sep-12 06-Sep-12 16-Sep-12 7 A12000 Curing for Slab 3 09-Sep-12 11-Sep-12 14-Oct-12 16-Oct-12 30 A12010 Strike Formwork 3 06-Oct-12 08-Oct-12 17-Oct-12 20-Oct-12 10 StairsStairs 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 Stairs 1Stairs 1 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 A12500 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 Stairs 2Stairs 2 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 A12510 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 Stairs 3Stairs 3 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 A12520 Stairs RC Works (3rd to 4th) 6 21-Oct-12 29-Oct-12 28-Jan-13 03-Feb-13 79 5th Floor Slab5th Floor Slab 53 09-Sep-12 11-Nov-12 17-Sep-12 03-Feb-13 68 Walls and CWalls and Columns 6 09-Sep-12 15-Sep-12 17-Sep-12 23-Sep-12 7 A12020 Core Wall RC Works 3 09-Sep-12 11-Sep-12 17-Sep-12 19-Sep-12 7 A12030 Columns RC Works 6 09-Sep-12 15-Sep-12 17-Sep-12 23-Sep-12 7 SlabSlab 33 12-Sep-12 20-Oct-12 20-Sep-12 10-Nov-12 16 A12040 MEP Works inside Slab 3 16-Sep-12 18-Sep-12 26-Sep-12 29-Sep-12 9 A12050 5th Slab RC Works 8 12-Sep-12 20-Sep-12 20-Sep-12 29-Sep-12 7 A12060 Curing for Slab 3 22-Sep-12 24-Sep-12 04-Nov-12 06-Nov-12 35 A12070 Strike Formwork 3 17-Oct-12 20-Oct-12 07-Nov-12 10-Nov-12 16 StairsStairs 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 Stairs 1Stairs 1 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 A12530 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 Stairs 2Stairs 2 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (2nd Basement to 1st Basement) Stairs RC Works (2nd Basement to 1st Basement) Stairs RC Works (2nd Basement to 1st Basement) Ramp Wall RC Works Columns RC Works Core Wall RC Works Retaining Wall 250 mm RC Works Ramp Slab RC Works MEP Works inside Slab Ground Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (1st Basement toGround) Stairs RC Works (1st Basement toGround) Stairs RC Works (1st Basement toGround) Core Wall RC Works Columns RC Works MEP Works inside Slab 1st Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Core Wall RC Works Columns RC Works MEP Works inside Slab 2nd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (1st to 2nd) Stairs RC Works (1st to 2nd) Stairs RC Works (1st to 2nd) Core Wall RC Works Columns RC Works MEP Works inside Slab 3rd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (2nd to 3rd) Stairs RC Works (2nd to 3rd) Stairs RC Works (2nd to 3rd) Core Wall RC Works Columns RC Works MEP Works inside Slab 4th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (3rd to 4th) Stairs RC Works (3rd to 4th) Stairs RC Works (3rd to 4th) Core Wall RC Works Columns RC Works MEP Works inside Slab 5th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (4th to 5th) Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 17 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 18. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A12540 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 Stairs 3Stairs 3 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 A12550 Stairs RC Works (4th to 5th) 6 05-Nov-12 11-Nov-12 28-Jan-13 03-Feb-13 68 6th Floor Slab6th Floor Slab 53 22-Sep-12 25-Nov-12 30-Sep-12 30-Jan-13 54 Walls and CWalls and Columns 6 22-Sep-12 27-Sep-12 30-Sep-12 06-Oct-12 7 A12080 Core Wall RC Works 3 22-Sep-12 24-Sep-12 30-Sep-12 02-Oct-12 7 A12090 Columns RC Works 6 22-Sep-12 27-Sep-12 30-Sep-12 06-Oct-12 7 SlabSlab 32 26-Sep-12 04-Nov-12 04-Oct-12 17-Nov-12 10 A12100 MEP Works inside Slab 3 29-Sep-12 01-Oct-12 10-Oct-12 13-Oct-12 10 A12110 6th Slab RC Works 8 26-Sep-12 04-Oct-12 04-Oct-12 13-Oct-12 7 A12120 Curing for Slab 3 06-Oct-12 08-Oct-12 10-Nov-12 12-Nov-12 28 A12130 Strike Formwork 3 01-Nov-12 04-Nov-12 13-Nov-12 17-Nov-12 10 StairsStairs 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 Stairs 1Stairs 1 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 A12560 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 Stairs 2Stairs 2 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 A12570 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 Stairs 3Stairs 3 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 A12580 Stairs RC Works (5th to 6th) 6 19-Nov-12 25-Nov-12 23-Jan-13 30-Jan-13 54 7th Floor Slab7th Floor Slab 58 06-Oct-12 16-Dec-12 14-Oct-12 30-Jan-13 37 Walls and CWalls and Columns 6 06-Oct-12 11-Oct-12 14-Oct-12 22-Oct-12 9 A12140 Core Wall RC Works 3 06-Oct-12 08-Oct-12 14-Oct-12 16-Oct-12 7 A12150 Columns RC Works 6 06-Oct-12 11-Oct-12 16-Oct-12 22-Oct-12 9 SlabSlab 31 10-Oct-12 18-Nov-12 21-Oct-12 28-Nov-12 9 A12160 MEP Works inside Slab 3 13-Oct-12 15-Oct-12 29-Oct-12 31-Oct-12 12 A12170 7th Slab RC Works 8 10-Oct-12 18-Oct-12 21-Oct-12 31-Oct-12 9 A12180 Curing for Slab 3 20-Oct-12 22-Oct-12 22-Nov-12 25-Nov-12 26 A12190 Strike Formwork 3 14-Nov-12 18-Nov-12 26-Nov-12 28-Nov-12 9 StairsStairs 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 Stairs 1Stairs 1 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 A12590 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 Stairs 2Stairs 2 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 A12600 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 Stairs 3Stairs 3 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 A109150 Stairs RC Works (6th to 7th) 6 10-Dec-12 16-Dec-12 23-Jan-13 30-Jan-13 37 Roof Floor SlRoof Floor Slab 60 20-Oct-12 02-Jan-13 03-Nov-12 05-Jun-13 131 ColumnsColumns 6 20-Oct-12 28-Oct-12 03-Nov-12 08-Nov-12 10 A12210 Columns RC Works 6 20-Oct-12 28-Oct-12 03-Nov-12 08-Nov-12 10 SlabSlab 32 23-Oct-12 03-Dec-12 06-Nov-12 15-Dec-12 10 A12220 MEP Works inside Slab 3 29-Oct-12 31-Oct-12 12-Nov-12 14-Nov-12 12 A12230 Roof Floor Slab RC Works 8 23-Oct-12 03-Nov-12 06-Nov-12 14-Nov-12 10 A12240 Curing for Slab 3 04-Nov-12 06-Nov-12 18-Nov-12 20-Nov-12 11 A12250 Strike Formwork 3 29-Nov-12 03-Dec-12 12-Dec-12 15-Dec-12 10 ParapetsParapets 10 22-Dec-12 02-Jan-13 26-May-13 05-Jun-13 131 A104150 Parapets RC Works 10 22-Dec-12 02-Jan-13 26-May-13 05-Jun-13 131 Chillers FouChillers Foundation 5 07-Nov-12 12-Nov-12 21-Nov-12 26-Nov-12 11 A117100 Chillers Foundations RC Works 5 07-Nov-12 12-Nov-12 21-Nov-12 26-Nov-12 11 StairsStairs 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32 Stairs 1Stairs 1 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32 A109160 Stairs RC Works (7th to Roof) 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32 Stairs 2Stairs 2 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32 A109170 Stairs RC Works (7th to Roof) 6 16-Dec-12 22-Dec-12 23-Jan-13 30-Jan-13 32 Upper Roof LUpper Roof Level 34 04-Nov-12 15-Dec-12 18-Nov-12 27-Dec-12 11 ColumnsColumns 6 04-Nov-12 10-Nov-12 18-Nov-12 24-Nov-12 11 A12270 Columns RC Works 6 04-Nov-12 10-Nov-12 18-Nov-12 24-Nov-12 11 SlabsSlabs 31 07-Nov-12 15-Dec-12 21-Nov-12 27-Dec-12 11 A12280 MEP Works inside Slab 3 11-Nov-12 13-Nov-12 26-Nov-12 28-Nov-12 12 A12290 Upper Roof Level Slab RC Works 7 07-Nov-12 14-Nov-12 21-Nov-12 28-Nov-12 11 A12300 Curing for Slab 3 17-Nov-12 19-Nov-12 22-Dec-12 24-Dec-12 29 A12310 Strike Formwork 3 12-Dec-12 15-Dec-12 25-Dec-12 27-Dec-12 11 ResidentialResidential (Block C) 275 15-Jan-12 09-Dec-12 23-Jan-12 05-Jun-13 151 Foundation LFoundation Level 51 15-Jan-12 14-Mar-12 23-Jan-12 22-Mar-12 7 Earth WorksEarth Works 11 15-Jan-12 26-Jan-12 23-Jan-12 22-Feb-12 22 Part 1 (C1)Part 1 (C1) 11 15-Jan-12 26-Jan-12 23-Jan-12 05-Feb-12 7 A12660 Excavation and Compaction 8 15-Jan-12 23-Jan-12 23-Jan-12 31-Jan-12 7 A12670 Base Coarse and Compaction 8 18-Jan-12 26-Jan-12 26-Jan-12 05-Feb-12 7 Part 2 (C2)Part 2 (C2) 7 15-Jan-12 22-Jan-12 15-Feb-12 22-Feb-12 26 A11200 Excavation and Compaction 5 15-Jan-12 19-Jan-12 15-Feb-12 20-Feb-12 26 A11210 Base Coarse and Compaction 5 17-Jan-12 22-Jan-12 18-Feb-12 22-Feb-12 26 Deep FoundDeep Foundation 44 23-Jan-12 14-Mar-12 31-Jan-12 22-Mar-12 7 Part 1 (C1)Part 1 (C1) 44 23-Jan-12 14-Mar-12 31-Jan-12 22-Mar-12 7 A12620 Laying Polythene Sheet & Blinding 5 23-Jan-12 28-Jan-12 31-Jan-12 06-Feb-12 7 A12630 Water Proofing & Screed 8 26-Jan-12 05-Feb-12 05-Feb-12 13-Feb-12 7 A12640 MEP Works inside Raft Slab 7 06-Feb-12 13-Feb-12 22-Feb-12 29-Feb-12 14 A12650 Raft Slab 1000 mm RC Works (Part 1) 18 31-Jan-12 21-Feb-12 09-Feb-12 29-Feb-12 7 A12680 Ramp Cutting 19 22-Feb-12 14-Mar-12 01-Mar-12 22-Mar-12 7 Part 2 (C2)Part 2 (C2) 43 23-Jan-12 13-Mar-12 23-Feb-12 21-Mar-12 7 A10170 Laying Polythene Sheet & Blinding 3 23-Jan-12 25-Jan-12 23-Feb-12 26-Feb-12 26 A10180 Water Proofing & Screed 5 26-Jan-12 31-Jan-12 27-Feb-12 03-Mar-12 26 A10240 MEP Works inside Raft Slab 4 14-Feb-12 18-Feb-12 18-Mar-12 21-Mar-12 28 A10190 Raft Slab 1000 mm RC Works (Part 2) 18 22-Feb-12 13-Mar-12 01-Mar-12 21-Mar-12 7 1st Basemen1st Basement Floor Slab 116 22-Feb-12 07-Jul-12 21-Mar-12 26-Jan-13 166 Walls and CWalls and Columns 27 22-Feb-12 24-Mar-12 21-Mar-12 25-Apr-12 28 Part 1 (C1)Part 1 (C1) 12 22-Feb-12 06-Mar-12 21-Mar-12 10-Apr-12 30 A10230 Columns RC Works 8 22-Feb-12 01-Mar-12 28-Mar-12 05-Apr-12 30 A11220 Tank Wall RC Works 10 23-Feb-12 05-Mar-12 21-Mar-12 01-Apr-12 23 A10200 Core Wall RC Works 10 25-Feb-12 06-Mar-12 21-Mar-12 01-Apr-12 22 A10210 Retaining Wall 250 mm RC Works 12 22-Feb-12 06-Mar-12 28-Mar-12 10-Apr-12 30 Part 2 (C2)Part 2 (C2) 9 14-Mar-12 24-Mar-12 22-Mar-12 25-Apr-12 28 A12690 Columns RC Works 4 14-Mar-12 18-Mar-12 22-Apr-12 25-Apr-12 33 A12710 Core Wall RC Works 6 17-Mar-12 22-Mar-12 19-Apr-12 25-Apr-12 29 A12720 Retaining Wall 250 mm RC Works 9 14-Mar-12 24-Mar-12 22-Mar-12 01-Apr-12 7 SlabSlab 78 25-Mar-12 24-Jun-12 02-Apr-12 26-Jan-13 177 A10250 MEP Works inside Slab 8 25-Mar-12 02-Apr-12 28-Apr-12 06-May-12 29 A10260 1st Basement Floor Slab RC Works 30 25-Mar-12 28-Apr-12 02-Apr-12 06-May-12 7 A10270 Curing for Slab 3 29-Apr-12 01-May-12 03-Oct-12 06-Oct-12 132 A10280 Strike Formwork 3 29-May-12 31-May-12 07-Oct-12 09-Oct-12 109 A10300 Pouring of Light Weight Concrete 2 02-Jun-12 03-Jun-12 03-Jan-13 05-Jan-13 177 A10410 Water Proofing Membrane for Ret. Walls 7 04-Jun-12 11-Jun-12 06-Jan-13 13-Jan-13 177 A10420 Gunited Concrete 50 mm for Ret. Walls 7 12-Jun-12 20-Jun-12 14-Jan-13 21-Jan-13 177 A10520 Backfilling 3 21-Jun-12 24-Jun-12 22-Jan-13 26-Jan-13 177 StairsStairs 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 Stairs 1Stairs 1 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 A11230 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 Stairs 2Stairs 2 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 A11240 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 Stairs 3Stairs 3 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 A11250 Stairs RC Works (2nd Basement to 1st Basement) 6 01-Jul-12 07-Jul-12 19-Jan-13 26-Jan-13 166 Ground FloorGround Floor Slab 77 29-Apr-12 28-Jul-12 07-May-12 26-Jan-13 148 Walls and CWalls and Columns 21 29-Apr-12 22-May-12 07-May-12 30-May-12 7 A10340 Columns RC Works 11 29-Apr-12 10-May-12 07-May-12 19-May-12 7 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Stairs RC Works (4th to 5th) Stairs RC Works (4th to 5th) Core Wall RC Works Columns RC Works MEP Works inside Slab 6th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (5th to 6th) Stairs RC Works (5th to 6th) Stairs RC Works (5th to 6th) Core Wall RC Works Columns RC Works MEP Works inside Slab 7th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (6th to 7th) Stairs RC Works (6th to 7th) Stairs RC Works (6th to 7th) Columns RC Works MEP Works inside Slab Roof Floor Slab RC Works Curing for Slab Strike Formwork Parapets RC Works Chillers Foundations RC Works Stairs RC Works (7th to Roof) Stairs RC Works (7th to Roof) Columns RC Works MEP Works inside Slab Upper Roof LevelSlab RC Works Curing for Slab Strike Formwork Excavation and Compaction Base Coarse and Compaction Excavation and Compaction Base Coarse and Compaction Laying Polythene Sheet & Blinding Water Proofing & Screed MEP Works inside Raft Slab Raft Slab 1000 mm RC Works (Part 1) Ramp Cutting Laying Polythene Sheet & Blinding Water Proofing & Screed MEP Works inside Raft Slab Raft Slab 1000 mm RC Works (Part 2) Columns RC Works Tank WallRC Works Core Wall RC Works Retaining Wall 250 mm RC Works Columns RC Works Core Wall RC Works Retaining Wall 250 mm RC Works MEP Works inside Slab 1st Basement Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (2nd Basement to 1st Basement) Stairs RC Works (2nd Basement to 1st Basement) Stairs RC Works (2nd Basement to 1st Basement) Columns RC Works Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 18 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 19. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A10310 Core Wall RC Works 15 30-Apr-12 16-May-12 08-May-12 24-May-12 7 A10320 Retaining Wall 250 mm RC Works 21 29-Apr-12 22-May-12 07-May-12 30-May-12 7 SlabSlab 68 03-May-12 22-Jul-12 12-May-12 26-Jan-13 153 A10350 MEP Works inside Slab 8 13-May-12 21-May-12 27-May-12 04-Jun-12 12 A10360 Ground Floor Slab RC Works 21 03-May-12 27-May-12 12-May-12 04-Jun-12 7 A10370 Curing for Slab 3 28-May-12 30-May-12 03-Nov-12 05-Nov-12 131 A10380 Strike Formwork 3 27-Jun-12 30-Jun-12 06-Nov-12 08-Nov-12 109 A10400 Pouring of Light Weight Concrete 2 01-Jul-12 02-Jul-12 03-Jan-13 05-Jan-13 153 A10430 Water Proofing Membrane for Ret. Walls 7 03-Jul-12 10-Jul-12 06-Jan-13 13-Jan-13 153 A10440 Gunited Concrete 50 mm for Ret. Walls 7 11-Jul-12 18-Jul-12 14-Jan-13 21-Jan-13 153 A10530 Backfilling 3 19-Jul-12 22-Jul-12 22-Jan-13 26-Jan-13 153 StairsStairs 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 Stairs 1Stairs 1 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 A11260 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 Stairs 2Stairs 2 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 A11270 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 Stairs 3Stairs 3 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 A11280 Stairs RC Works (1st Basement toGround) 6 22-Jul-12 28-Jul-12 19-Jan-13 26-Jan-13 148 1st Floor Slab1st Floor Slab 73 28-May-12 23-Aug-12 05-Jun-12 25-Feb-13 153 Walls and CWalls and Columns 9 28-May-12 06-Jun-12 05-Jun-12 14-Jun-12 7 A10460 Core Wall RC Works 6 28-May-12 03-Jun-12 05-Jun-12 11-Jun-12 7 A10470 Columns RC Works 9 28-May-12 06-Jun-12 05-Jun-12 14-Jun-12 7 SlabSlab 42 02-Jun-12 21-Jul-12 10-Jun-12 01-Dec-12 109 A10480 MEP Works inside Slab 5 07-Jun-12 12-Jun-12 24-Jun-12 28-Jun-12 13 A10490 1st Floor Slab RC Works 16 02-Jun-12 20-Jun-12 10-Jun-12 28-Jun-12 7 A10500 Curing for Slab 3 21-Jun-12 24-Jun-12 25-Nov-12 27-Nov-12 129 A10510 Strike Formwork 3 18-Jul-12 21-Jul-12 28-Nov-12 01-Dec-12 109 StairsStairs 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 Stairs 1Stairs 1 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 A11290 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 Stairs 2Stairs 2 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 A11300 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 Stairs 3Stairs 3 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 A11310 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 Stairs 4Stairs 4 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 A109210 Stairs RC Works (Ground to 1st floor) 6 15-Aug-12 23-Aug-12 19-Feb-13 25-Feb-13 153 2nd Floor Sl2nd Floor Slab 64 21-Jun-12 05-Sep-12 30-Jun-12 14-Feb-13 133 Walls and CWalls and Columns 9 21-Jun-12 01-Jul-12 30-Jun-12 09-Jul-12 7 A10570 Core Wall RC Works 6 21-Jun-12 27-Jun-12 30-Jun-12 05-Jul-12 7 A10580 Columns RC Works 9 21-Jun-12 01-Jul-12 30-Jun-12 09-Jul-12 7 SlabSlab 43 26-Jun-12 14-Aug-12 04-Jul-12 28-Aug-12 10 A10590 MEP Works inside Slab 5 02-Jul-12 07-Jul-12 17-Jul-12 22-Jul-12 13 A10600 2nd Floor Slab RC Works 16 26-Jun-12 14-Jul-12 04-Jul-12 22-Jul-12 7 A10610 Curing for Slab 3 15-Jul-12 17-Jul-12 22-Aug-12 25-Aug-12 31 A10620 Strike Formwork 3 12-Aug-12 14-Aug-12 26-Aug-12 28-Aug-12 10 StairsStairs 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 Stairs 1Stairs 1 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 A11320 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 Stairs 2Stairs 2 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 A11330 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 Stairs 3Stairs 3 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 A11340 Stairs RC Works (1st to 2nd) 6 30-Aug-12 05-Sep-12 09-Feb-13 14-Feb-13 133 3rd Floor Slab3rd Floor Slab 56 15-Jul-12 19-Sep-12 23-Jul-12 14-Feb-13 121 Walls and CWalls and Columns 9 15-Jul-12 24-Jul-12 23-Jul-12 01-Aug-12 7 A10650 Core Wall RC Works 6 15-Jul-12 21-Jul-12 23-Jul-12 29-Jul-12 7 A10660 Columns RC Works 9 15-Jul-12 24-Jul-12 23-Jul-12 01-Aug-12 7 SlabSlab 34 19-Jul-12 29-Aug-12 28-Jul-12 11-Sep-12 11 A10670 MEP Works inside Slab 5 22-Jul-12 26-Jul-12 01-Aug-12 06-Aug-12 9 A10680 3rd Floor Slab RC Works 9 19-Jul-12 29-Jul-12 28-Jul-12 06-Aug-12 7 A10690 Curing for Slab 3 30-Jul-12 01-Aug-12 05-Sep-12 08-Sep-12 30 A10700 Strike Formwork 3 27-Aug-12 29-Aug-12 09-Sep-12 11-Sep-12 11 StairsStairs 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 Stairs 1Stairs 1 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 A11350 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 Stairs 2Stairs 2 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 A11360 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 Stairs 3Stairs 3 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 A11370 Stairs RC Works (2nd to 3rd) 6 13-Sep-12 19-Sep-12 09-Feb-13 14-Feb-13 121 4th Floor Slab4th Floor Slab 57 30-Jul-12 06-Oct-12 07-Aug-12 12-Feb-13 105 Walls and CWalls and Columns 9 30-Jul-12 08-Aug-12 07-Aug-12 16-Aug-12 7 A10730 Core Wall RC Works 6 30-Jul-12 05-Aug-12 07-Aug-12 13-Aug-12 7 A10740 Columns RC Works 9 30-Jul-12 08-Aug-12 07-Aug-12 16-Aug-12 7 SlabSlab 33 04-Aug-12 12-Sep-12 12-Aug-12 26-Sep-12 12 A10750 MEP Works inside Slab 5 08-Aug-12 13-Aug-12 16-Aug-12 23-Aug-12 7 A10760 4th Slab RC Works 9 04-Aug-12 13-Aug-12 12-Aug-12 23-Aug-12 7 A10770 Curing for Slab 3 14-Aug-12 16-Aug-12 20-Sep-12 23-Sep-12 30 A10780 Strike Formwork 3 10-Sep-12 12-Sep-12 24-Sep-12 26-Sep-12 12 StairsStairs 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 Stairs 1Stairs 1 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 A11380 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 Stairs 2Stairs 2 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 A11390 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 Stairs 3Stairs 3 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 A11400 Stairs RC Works (3rd to 4th) 6 30-Sep-12 06-Oct-12 06-Feb-13 12-Feb-13 105 5th Floor Slab5th Floor Slab 56 14-Aug-12 20-Oct-12 25-Aug-12 11-Feb-13 92 Walls and CWalls and Columns 9 14-Aug-12 26-Aug-12 25-Aug-12 03-Sep-12 7 A10810 Core Wall RC Works 6 14-Aug-12 22-Aug-12 25-Aug-12 30-Aug-12 7 A10820 Columns RC Works 9 14-Aug-12 26-Aug-12 25-Aug-12 03-Sep-12 7 SlabSlab 35 18-Aug-12 29-Sep-12 28-Aug-12 13-Oct-12 12 A10830 MEP Works inside Slab 5 23-Aug-12 28-Aug-12 02-Sep-12 06-Sep-12 8 A10840 5th Slab RC Works 9 18-Aug-12 29-Aug-12 28-Aug-12 06-Sep-12 7 A10850 Curing for Slab 3 30-Aug-12 02-Sep-12 07-Oct-12 09-Oct-12 32 A10860 Strike Formwork 3 26-Sep-12 29-Sep-12 10-Oct-12 13-Oct-12 12 StairsStairs 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 Stairs 1Stairs 1 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 A11410 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 Stairs 2Stairs 2 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 A11420 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 Stairs 3Stairs 3 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 A11430 Stairs RC Works (4th to 5th) 6 14-Oct-12 20-Oct-12 05-Feb-13 11-Feb-13 92 6th Floor Slab6th Floor Slab 57 30-Aug-12 06-Nov-12 08-Sep-12 13-Feb-13 81 Walls and CWalls and Columns 9 30-Aug-12 09-Sep-12 08-Sep-12 17-Sep-12 7 A10890 Core Wall RC Works 6 30-Aug-12 05-Sep-12 08-Sep-12 13-Sep-12 7 A10900 Columns RC Works 9 30-Aug-12 09-Sep-12 08-Sep-12 17-Sep-12 7 SlabSlab 34 04-Sep-12 13-Oct-12 12-Sep-12 28-Oct-12 11 A10910 MEP Works inside Slab 5 09-Sep-12 13-Sep-12 17-Sep-12 22-Sep-12 7 A10920 6th Slab RC Works 9 04-Sep-12 13-Sep-12 12-Sep-12 22-Sep-12 7 A10930 Curing for Slab 3 15-Sep-12 17-Sep-12 20-Oct-12 22-Oct-12 30 A10940 Strike Formwork 3 10-Oct-12 13-Oct-12 23-Oct-12 28-Oct-12 11 StairsStairs 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 Stairs 1Stairs 1 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Core Wall RC Works Retaining Wall 250 mm RC Works MEP Works inside Slab Ground Floor Slab RC Works Curing for Slab Strike Formwork Pouring of Light Weight Concrete Water Proofing Membrane for Ret. Walls Gunited Concrete 50 mm for Ret. Walls Backfilling Stairs RC Works (1st Basement toGround) Stairs RC Works (1st Basement toGround) Stairs RC Works (1st Basement toGround) Core Wall RC Works Columns RC Works MEP Works inside Slab 1st Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Stairs RC Works (Ground to 1st floor) Core Wall RC Works Columns RC Works MEP Works inside Slab 2nd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (1st to 2nd) Stairs RC Works (1st to 2nd) Stairs RC Works (1st to 2nd) Core Wall RC Works Columns RC Works MEP Works inside Slab 3rd Floor Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (2nd to 3rd) Stairs RC Works (2nd to 3rd) Stairs RC Works (2nd to 3rd) Core Wall RC Works Columns RC Works MEP Works inside Slab 4th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (3rd to 4th) Stairs RC Works (3rd to 4th) Stairs RC Works (3rd to 4th) Core Wall RC Works Columns RC Works MEP Works inside Slab 5th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (4th to 5th) Stairs RC Works (4th to 5th) Stairs RC Works (4th to 5th) Core Wall RC Works Columns RC Works MEP Works inside Slab 6th Slab RC Works Curing for Slab Strike Formwork Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 19 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 20. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A11440 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 Stairs 2Stairs 2 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 A11450 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 Stairs 3Stairs 3 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 A11460 Stairs RC Works (5th to 6th) 6 31-Oct-12 06-Nov-12 07-Feb-13 13-Feb-13 81 7th Floor Slab7th Floor Slab 57 15-Sep-12 22-Nov-12 23-Sep-12 06-Feb-13 62 Walls and CWalls and Columns 9 15-Sep-12 24-Sep-12 23-Sep-12 02-Oct-12 7 A10970 Core Wall RC Works 6 15-Sep-12 20-Sep-12 23-Sep-12 29-Sep-12 7 A10980 Columns RC Works 9 15-Sep-12 24-Sep-12 23-Sep-12 02-Oct-12 7 SlabSlab 34 19-Sep-12 30-Oct-12 27-Sep-12 10-Nov-12 9 A10990 MEP Works inside Slab 5 24-Sep-12 29-Sep-12 02-Oct-12 07-Oct-12 7 A11000 7th Slab RC Works 9 19-Sep-12 29-Sep-12 27-Sep-12 07-Oct-12 7 A11010 Curing for Slab 3 30-Sep-12 02-Oct-12 04-Nov-12 06-Nov-12 28 A11020 Strike Formwork 3 28-Oct-12 30-Oct-12 07-Nov-12 10-Nov-12 9 StairsStairs 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 Stairs 1Stairs 1 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 A11470 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 Stairs 2Stairs 2 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 A11480 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 Stairs 3Stairs 3 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 A11490 Stairs RC Works (6th to 7th) 6 17-Nov-12 22-Nov-12 31-Jan-13 06-Feb-13 62 Roof Floor SlRoof Floor Slab 57 30-Sep-12 09-Dec-12 08-Oct-12 05-Jun-13 151 Walls and CWalls and Columns 9 30-Sep-12 09-Oct-12 08-Oct-12 20-Oct-12 9 A11050 Core Wall RC Works 6 30-Sep-12 06-Oct-12 08-Oct-12 14-Oct-12 7 A11060 Columns RC Works 9 30-Sep-12 09-Oct-12 10-Oct-12 20-Oct-12 9 SlabSlab 34 04-Oct-12 14-Nov-12 15-Oct-12 26-Nov-12 9 A11070 MEP Works inside Slab 5 09-Oct-12 14-Oct-12 20-Oct-12 24-Oct-12 9 A11080 Roof Floor Slab RC Works 9 04-Oct-12 14-Oct-12 15-Oct-12 24-Oct-12 9 A11090 Curing for Slab 3 15-Oct-12 17-Oct-12 08-Nov-12 11-Nov-12 19 A11100 Strike Formwork 3 12-Nov-12 14-Nov-12 24-Nov-12 26-Nov-12 9 ParapetsParapets 10 07-Nov-12 19-Nov-12 26-May-13 05-Jun-13 167 A104160 Parapets RC Works 10 07-Nov-12 19-Nov-12 26-May-13 05-Jun-13 167 Chillers FouChillers Foundation 5 18-Oct-12 23-Oct-12 12-Nov-12 18-Nov-12 19 A117110 Chillers Foundations RC Works 5 18-Oct-12 23-Oct-12 12-Nov-12 18-Nov-12 19 StairsStairs 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 Stairs 1Stairs 1 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 A109230 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 Stairs 2Stairs 2 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 A109240 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 Stairs 3Stairs 3 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 A111200 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 Stairs 4Stairs 4 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 A113370 Stairs RC Works (7th to Roof) 6 03-Dec-12 09-Dec-12 06-Feb-13 12-Feb-13 54 Upper Roof LUpper Roof Level 44 15-Oct-12 09-Dec-12 29-Oct-12 25-Feb-13 65 ColumnsColumns 9 15-Oct-12 24-Oct-12 29-Oct-12 07-Nov-12 10 A11140 Columns RC Works 9 15-Oct-12 24-Oct-12 29-Oct-12 07-Nov-12 10 SlabsSlabs 34 20-Oct-12 01-Dec-12 03-Nov-12 04-Feb-13 53 A11150 MEP Works inside Slab 4 24-Oct-12 30-Oct-12 07-Nov-12 11-Nov-12 10 A11160 Upper Roof Level Slab RC Works 8 20-Oct-12 30-Oct-12 03-Nov-12 11-Nov-12 10 A11170 Curing for Slab 3 31-Oct-12 03-Nov-12 02-Feb-13 04-Feb-13 76 A11180 Strike Formwork 3 28-Nov-12 01-Dec-12 11-Dec-12 13-Dec-12 10 StairsStairs 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65 Stairs 4Stairs 4 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65 A109260 Stairs RC Works (Roof to Upper Roof) 6 03-Dec-12 09-Dec-12 19-Feb-13 25-Feb-13 65 ArchitecturaArchitectural & MEP Package 431 14-Apr-12 10-Sep-13 28-Jul-12 02-Oct-13 19 Hotel AparteHotel Apartements (Block A) 429 14-Apr-12 08-Sep-13 28-Jul-12 02-Oct-13 21 2nd Basemen2nd Basement Floor 258 14-Apr-12 18-Feb-13 27-Sep-12 25-Apr-13 57 Public AreaPublic Area 258 14-Apr-12 18-Feb-13 27-Sep-12 25-Apr-13 57 Parking ArParking Area 247 26-Apr-12 18-Feb-13 15-Oct-12 25-Apr-13 57 FinishingFinishing Works 247 26-Apr-12 18-Feb-13 15-Oct-12 25-Apr-13 57 Wet WorWet Works 193 26-Apr-12 15-Dec-12 15-Oct-12 21-Feb-13 57 A47830 Plaster Works 5 26-Apr-12 01-May-12 15-Oct-12 20-Oct-12 144 A47850 1st Coat Paint 12 01-Dec-12 15-Dec-12 09-Feb-13 21-Feb-13 57 Traffic DTraffic Deck Coating 42 16-Dec-12 04-Feb-13 23-Feb-13 25-Apr-13 69 A47630 Installation of Kerbs 8 16-Dec-12 24-Dec-12 23-Feb-13 03-Mar-13 57 A47620 Installation of Interlocking Tiles 8 25-Dec-12 03-Jan-13 04-Mar-13 12-Mar-13 57 A47550 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 13-Mar-13 21-Mar-13 57 A47560 Application of 1st Coat 7 10-Jan-13 17-Jan-13 19-Mar-13 26-Mar-13 57 A47600 Application of Final Coat 7 19-Jan-13 27-Jan-13 27-Mar-13 03-Apr-13 57 A47580 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 04-Apr-13 11-Apr-13 57 A47610 Installation of Speed Hump 7 28-Jan-13 04-Feb-13 18-Apr-13 25-Apr-13 69 Final StaFinal Stage Finishes 12 05-Feb-13 18-Feb-13 13-Apr-13 25-Apr-13 57 A47860 Final Coat Paint 5 05-Feb-13 10-Feb-13 13-Apr-13 17-Apr-13 57 A47930 Installation of Sinages 7 11-Feb-13 18-Feb-13 18-Apr-13 25-Apr-13 57 MEP WorkMEP Works 234 26-Apr-12 03-Feb-13 02-Jan-13 24-Apr-13 69 HVACHVAC 10 04-Jul-12 15-Jul-12 28-Jan-13 07-Feb-13 170 A47970 Chilled Water Pipe Installation & Insulation 7 04-Jul-12 11-Jul-12 28-Jan-13 04-Feb-13 170 A47980 Condensate Pipe Installation 7 04-Jul-12 11-Jul-12 28-Jan-13 04-Feb-13 170 A47990 Installation of Induction Fan 3 12-Jul-12 15-Jul-12 05-Feb-13 07-Feb-13 170 ElectricalElectrical 173 06-May-12 29-Nov-12 03-Jan-13 07-Feb-13 57 A48000 Installation of Cable Trays 10 06-May-12 16-May-12 03-Jan-13 14-Jan-13 200 A47940 Installation of Bus Bars 15 31-Oct-12 18-Nov-12 09-Jan-13 27-Jan-13 57 A48010 Cable Pulling 10 06-Nov-12 18-Nov-12 15-Jan-13 27-Jan-13 57 A47920 Installation of Lighting Fittings 10 19-Nov-12 29-Nov-12 28-Jan-13 07-Feb-13 57 PlumbingPlumbing 12 26-Apr-12 09-May-12 26-Jan-13 07-Feb-13 226 A48060 H/L Hot&Cold Water Pipe Installation 7 26-Apr-12 03-May-12 26-Jan-13 02-Feb-13 226 A48070 Water Pipes Testing 5 05-May-12 09-May-12 03-Feb-13 07-Feb-13 226 A48080 Floor Drain Fixing 4 06-May-12 09-May-12 04-Feb-13 07-Feb-13 226 Fire FighFire Fighting 195 11-Jun-12 03-Feb-13 02-Jan-13 24-Apr-13 69 A48040 Fire Fighting Pipe 8 11-Jun-12 20-Jun-12 02-Jan-13 10-Jan-13 168 A48030 Hydro Static Test for Pipes 5 21-Jun-12 26-Jun-12 17-Jan-13 22-Jan-13 173 A48020 Sprinkler Fixing 7 27-Jun-12 04-Jul-12 23-Jan-13 31-Jan-13 173 A47950 Fire Alarm Devices 6 05-Jul-12 11-Jul-12 02-Feb-13 07-Feb-13 173 A47960 Installation of Fire Hose Cabinet & Landing Valve 6 28-Jan-13 03-Feb-13 18-Apr-13 24-Apr-13 69 RampRamp 117 20-Sep-12 10-Feb-13 15-Oct-12 25-Apr-13 64 FinishingFinishing Works 117 20-Sep-12 10-Feb-13 15-Oct-12 25-Apr-13 64 A8730 Install Handrail 7 20-Sep-12 27-Sep-12 15-Oct-12 22-Oct-12 21 A8720 1st Coat Paint 10 04-Dec-12 15-Dec-12 11-Mar-13 21-Mar-13 81 A1136 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 23-Mar-13 31-Mar-13 65 A1138 Application of 1st Coat 5 14-Jan-13 19-Jan-13 01-Apr-13 06-Apr-13 65 A1134 Application of Final Coat 5 21-Jan-13 27-Jan-13 07-Apr-13 11-Apr-13 64 A1132 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 13-Apr-13 20-Apr-13 64 A8760 Final Coat Paint 5 05-Feb-13 10-Feb-13 21-Apr-13 25-Apr-13 64 Lift LobbyLift Lobby 203 14-Apr-12 13-Dec-12 02-Oct-12 25-Apr-13 112 FinishingFinishing Works 203 14-Apr-12 13-Dec-12 02-Oct-12 25-Apr-13 112 Wet WorWet Works 90 14-Apr-12 28-Jul-12 02-Oct-12 07-Feb-13 159 A48140 Block Works 4 14-Apr-12 17-Apr-12 02-Oct-12 06-Oct-12 144 A48090 Plaster Works 7 17-May-12 24-May-12 14-Jan-13 21-Jan-13 199 A48110 Installation of Suspended Ceiling Grid 5 16-Jul-12 21-Jul-12 27-Jan-13 31-Jan-13 159 A48100 1st Coat Paint 6 22-Jul-12 28-Jul-12 02-Feb-13 07-Feb-13 159 Fisrt StaFisrt Stage Finishes 23 29-Jul-12 26-Aug-12 19-Feb-13 28-Feb-13 154 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Stairs RC Works (5th to 6th) Stairs RC Works (5th to 6th) Stairs RC Works (5th to 6th) Core Wall RC Works Columns RC Works MEP Works inside Slab 7th Slab RC Works Curing for Slab Strike Formwork Stairs RC Works (6th to 7th) Stairs RC Works (6th to 7th) Stairs RC Works (6th to 7th) Core Wall RC Works Columns RC Works MEP Works inside Slab Roof Floor Slab RC Works Curing for Slab Strike Formwork Parapets RC Works Chillers Foundations RC Works Stairs RC Works (7th to Roof) Stairs RC Works (7th to Roof) Stairs RC Works (7th to Roof) Stairs RC Works (7th to Roof) Columns RC Works MEP Works inside Slab Upper Roof LevelSlab RC Works Curing for Slab Strike Formwork Stairs RC Works (Roof to Upper Roof) Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Installation of Induction Fan Installation of Cable Trays Installation of Bus Bars Cable Pulling Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Floor Drain Fixing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Hose Cabinet & Landing Valve Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 20 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 21. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A48120 Suspended Ceiling Tiles 5 29-Jul-12 02-Aug-12 19-Feb-13 24-Feb-13 168 A48380 MDF for Lift Lobby Wall 7 14-Aug-12 23-Aug-12 19-Feb-13 26-Feb-13 154 A48360 Screed Works 2 25-Aug-12 26-Aug-12 27-Feb-13 28-Feb-13 154 Second SSecond Stage Finishes 8 27-Aug-12 04-Sep-12 02-Mar-13 10-Mar-13 154 A48370 Wall Tiles Work 5 27-Aug-12 01-Sep-12 02-Mar-13 06-Mar-13 154 A48400 Floor Tiles Work 3 02-Sep-12 04-Sep-12 07-Mar-13 10-Mar-13 154 Final StaFinal Stage Finishes 82 05-Sep-12 13-Dec-12 11-Mar-13 25-Apr-13 112 A48130 Installation of Doors 2 05-Sep-12 06-Sep-12 11-Mar-13 12-Mar-13 154 A48150 Doors Ironmongery 2 15-Sep-12 16-Sep-12 17-Apr-13 18-Apr-13 178 A48410 Final Coat Paint 3 09-Dec-12 11-Dec-12 06-Apr-13 08-Apr-13 99 A48350 Installation of Sinages 2 12-Dec-12 13-Dec-12 24-Apr-13 25-Apr-13 112 MEP WorkMEP Works 194 18-Apr-12 08-Dec-12 26-Nov-12 04-Apr-13 99 HVACHVAC 37 24-Jun-12 05-Aug-12 16-Jan-13 05-Mar-13 174 A48160 Duct Installation & Insulation 5 24-Jun-12 28-Jun-12 16-Jan-13 21-Jan-13 170 A48180 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 16-Jan-13 21-Jan-13 170 A48170 Chilled Water Pipe Installation & Insulation 5 28-Jun-12 03-Jul-12 16-Jan-13 21-Jan-13 166 A48190 FCU Installation 3 04-Jul-12 07-Jul-12 22-Jan-13 26-Jan-13 166 A48200 Air-Outlet Installation 2 04-Aug-12 05-Aug-12 04-Mar-13 05-Mar-13 174 ElectricalElectrical 194 18-Apr-12 08-Dec-12 26-Nov-12 05-Mar-13 73 A48210 Install Conduits in Wall 3 18-Apr-12 21-Apr-12 26-Nov-12 28-Nov-12 184 A48220 Install Cable Trays & Trunking 3 06-May-12 08-May-12 16-Jan-13 19-Jan-13 211 A48260 Cable Laying for Low Current System 5 12-May-12 16-May-12 27-Jan-13 31-Jan-13 214 A48270 Cable Laying for Power 5 12-May-12 16-May-12 27-Jan-13 31-Jan-13 214 A48230 Wiring for Lighting & Power 3 26-May-12 28-May-12 22-Jan-13 26-Jan-13 199 A48240 Wiring for Low Current System 3 26-May-12 28-May-12 22-Jan-13 26-Jan-13 199 A48290 Installation of Lighting Fittings 6 01-Dec-12 08-Dec-12 27-Feb-13 05-Mar-13 73 Fire FighFire Fighting 44 21-Jun-12 11-Aug-12 12-Jan-13 04-Apr-13 195 A48340 Fire Fighting Pipe 7 21-Jun-12 28-Jun-12 12-Jan-13 19-Jan-13 168 A48330 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 20-Jan-13 26-Jan-13 168 A48390 Fire Alarm Devices 5 04-Aug-12 08-Aug-12 31-Mar-13 04-Apr-13 197 A48320 Sprinkler Fixing 7 04-Aug-12 11-Aug-12 26-Feb-13 05-Mar-13 169 GSM RoomGSM Rooms 202 18-Apr-12 17-Dec-12 07-Oct-12 25-Apr-13 109 FinishingFinishing Works 202 18-Apr-12 17-Dec-12 07-Oct-12 25-Apr-13 109 Wet WorWet Works 42 18-Apr-12 05-Jun-12 07-Oct-12 03-Mar-13 223 A47420 Block Works 5 18-Apr-12 23-Apr-12 07-Oct-12 11-Oct-12 144 A47380 Installation of Doors& Windows Sub-frame 2 02-May-12 03-May-12 02-Mar-13 03-Mar-13 251 A47370 Plaster Works 8 02-May-12 10-May-12 06-Dec-12 15-Dec-12 180 A47390 1st Coat Paint 7 29-May-12 05-Jun-12 03-Jan-13 10-Jan-13 180 Fisrt StaFisrt Stage Finishes 85 19-Jun-12 27-Sep-12 09-Mar-13 21-Apr-13 170 A47410 Installation of Doors 2 19-Jun-12 20-Jun-12 09-Mar-13 10-Mar-13 217 A47430 Doors Ironmongery 2 17-Sep-12 18-Sep-12 20-Apr-13 21-Apr-13 178 A47480 Epoxy Paint Works 2 26-Sep-12 27-Sep-12 11-Mar-13 12-Mar-13 136 Second SSecond Stage Finishes 3 12-Dec-12 15-Dec-12 09-Apr-13 11-Apr-13 99 A47400 Final Coat Paint 3 12-Dec-12 15-Dec-12 09-Apr-13 11-Apr-13 99 Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109 A47470 Installation of Sinages 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109 MEP WorkMEP Works 130 24-Apr-12 25-Sep-12 29-Nov-12 10-Mar-13 136 HVACHVAC 21 24-Jun-12 17-Jul-12 12-Jan-13 03-Mar-13 188 A47510 Chilled Water Pipe Installation & Insulation 4 24-Jun-12 27-Jun-12 12-Jan-13 15-Jan-13 166 A47520 Condensate Pipe Installation 4 30-Jun-12 03-Jul-12 22-Jan-13 27-Jan-13 170 A47530 FCU Installation 4 08-Jul-12 11-Jul-12 21-Feb-13 25-Feb-13 188 A47540 Air-Outlet Installation 5 12-Jul-12 17-Jul-12 26-Feb-13 03-Mar-13 188 ElectricalElectrical 130 24-Apr-12 25-Sep-12 29-Nov-12 05-Mar-13 132 A47440 Install Conduits in Wall 5 24-Apr-12 29-Apr-12 29-Nov-12 05-Dec-12 182 A47450 Wiring for Lighting & Power 5 12-May-12 16-May-12 27-Dec-12 02-Jan-13 190 A47460 Installation of Lighting Fittings 5 06-Jun-12 11-Jun-12 16-Jan-13 21-Jan-13 184 A47500 Installation of GSM System 45 02-Aug-12 25-Sep-12 12-Jan-13 05-Mar-13 132 Fire FighFire Fighting 5 12-Jul-12 17-Jul-12 05-Mar-13 10-Mar-13 194 A47490 Fire Alarm Devices 5 12-Jul-12 17-Jul-12 05-Mar-13 10-Mar-13 194 MechanicaMechanical Rooms 147 24-Apr-12 15-Oct-12 13-Oct-12 25-Apr-13 159 FinishingFinishing Works 147 24-Apr-12 15-Oct-12 13-Oct-12 25-Apr-13 159 Wet WorWet Works 30 24-Apr-12 28-May-12 13-Oct-12 05-Mar-13 232 A47230 Block Works 2 24-Apr-12 25-Apr-12 13-Oct-12 14-Oct-12 144 A47190 Installation of Doors& Windows Sub-frame 2 12-May-12 13-May-12 04-Mar-13 05-Mar-13 245 A47180 Plaster Works 5 12-May-12 16-May-12 16-Dec-12 20-Dec-12 180 A47200 1st Coat Paint 6 22-May-12 28-May-12 26-Dec-12 02-Jan-13 180 Fisrt StaFisrt Stage Finishes 81 16-Jun-12 20-Sep-12 06-Mar-13 23-Apr-13 178 A47220 Installation of Doors 2 16-Jun-12 18-Jun-12 06-Mar-13 07-Mar-13 217 A47290 Epoxy Paint Works 2 21-Jun-12 23-Jun-12 09-Mar-13 10-Mar-13 215 A47240 Doors Ironmongery 2 19-Sep-12 20-Sep-12 22-Apr-13 23-Apr-13 178 Second SSecond Stage Finishes 2 24-Jun-12 25-Jun-12 03-Apr-13 04-Apr-13 235 A47210 Final Coat Paint 2 24-Jun-12 25-Jun-12 03-Apr-13 04-Apr-13 235 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 A47280 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 MEP WorkMEP Works 44 30-Apr-12 20-Jun-12 11-Dec-12 05-Mar-13 213 HVACHVAC 15 29-May-12 14-Jun-12 05-Jan-13 21-Jan-13 181 A47320 Shaft Works 15 29-May-12 14-Jun-12 05-Jan-13 21-Jan-13 181 ElectricalElectrical 44 30-Apr-12 20-Jun-12 11-Dec-12 27-Jan-13 181 A47250 Install Conduits in Wall 4 30-Apr-12 03-May-12 11-Dec-12 15-Dec-12 186 A47260 Wiring for Lighting & Power 4 17-May-12 21-May-12 22-Dec-12 25-Dec-12 180 A47270 Installation of Lighting Fittings 4 16-Jun-12 20-Jun-12 22-Jan-13 27-Jan-13 181 PlumbingPlumbing 3 29-May-12 31-May-12 03-Mar-13 05-Mar-13 229 A47360 Floor Drain Fixing 3 29-May-12 31-May-12 03-Mar-13 05-Mar-13 229 StaircaseStaircase 144 29-May-12 19-Nov-12 27-Sep-12 25-Apr-13 132 Stair 1Stair 1 144 29-May-12 19-Nov-12 27-Sep-12 25-Apr-13 132 A107930 Floor Screed 3 29-May-12 31-May-12 27-Sep-12 30-Sep-12 101 A107940 Install Handrails 4 29-Sep-12 02-Oct-12 23-Oct-12 29-Oct-12 21 A107950 Ceiling 1st Coat Paint 7 03-Oct-12 10-Oct-12 19-Nov-12 26-Nov-12 37 A107960 Wall 1st Coat Paint 7 11-Oct-12 18-Oct-12 27-Nov-12 05-Dec-12 37 A107970 Install Granite/Terrazo 12 20-Oct-12 04-Nov-12 20-Dec-12 03-Jan-13 49 A107980 Final Coat Paint 12 05-Nov-12 19-Nov-12 13-Apr-13 25-Apr-13 132 1st Basemen1st Basement Floor 235 10-May-12 18-Feb-13 02-Aug-12 25-Apr-13 57 Public AreaPublic Area 235 10-May-12 18-Feb-13 02-Aug-12 25-Apr-13 57 Parking ArParking Area 200 14-Jun-12 12-Feb-13 30-Oct-12 25-Apr-13 62 FinishingFinishing Works 158 04-Aug-12 12-Feb-13 30-Oct-12 25-Apr-13 62 Wet WorWet Works 109 04-Aug-12 15-Dec-12 30-Oct-12 21-Feb-13 57 A50110 Plaster Works 5 04-Aug-12 08-Aug-12 30-Oct-12 04-Nov-12 71 A50120 1st Coat Paint 12 01-Dec-12 15-Dec-12 09-Feb-13 21-Feb-13 57 Traffic DTraffic Deck Coating 49 16-Dec-12 12-Feb-13 23-Feb-13 25-Apr-13 62 A115650 Installation of Kerbs 8 16-Dec-12 24-Dec-12 23-Feb-13 03-Mar-13 57 A115660 Installation of Interlocking Tiles 8 25-Dec-12 03-Jan-13 04-Mar-13 12-Mar-13 57 A50050 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 13-Mar-13 21-Mar-13 57 A50060 Application of 1st Coat 7 10-Jan-13 17-Jan-13 19-Mar-13 26-Mar-13 57 A50100 Application of Final Coat 7 19-Jan-13 27-Jan-13 27-Mar-13 03-Apr-13 57 A50080 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 04-Apr-13 11-Apr-13 57 A115670 Installation of Speed Hump 7 05-Feb-13 12-Feb-13 18-Apr-13 25-Apr-13 62 Final StaFinal Stage Finishes 7 05-Feb-13 12-Feb-13 13-Apr-13 25-Apr-13 62 A50130 Final Coat Paint 5 05-Feb-13 10-Feb-13 13-Apr-13 17-Apr-13 57 A50150 Installation of Sinages 2 11-Feb-13 12-Feb-13 24-Apr-13 25-Apr-13 62 MEP WorkMEP Works 139 14-Jun-12 29-Nov-12 03-Jan-13 07-Feb-13 57 HVACHVAC 28 24-Jun-12 25-Jul-12 28-Jan-13 07-Feb-13 161 A50170 Chilled Water Pipe Installation & Insulation 7 24-Jun-12 01-Jul-12 28-Jan-13 04-Feb-13 179 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Condensate Pipe Installation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of GSM System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Shaft Works Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Floor Drain Fixing Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 21 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 22. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A50180 Condensate Pipe Installation 7 15-Jul-12 22-Jul-12 28-Jan-13 04-Feb-13 161 A50250 Installation of Induction Fans 3 23-Jul-12 25-Jul-12 05-Feb-13 07-Feb-13 161 ElectricalElectrical 139 14-Jun-12 29-Nov-12 03-Jan-13 07-Feb-13 57 A115680 Installation of Cable Trays 10 14-Jun-12 26-Jun-12 03-Jan-13 14-Jan-13 166 A115690 Installation of Bus Bars 15 31-Oct-12 18-Nov-12 09-Jan-13 27-Jan-13 57 A115700 Cable Pulling 10 06-Nov-12 18-Nov-12 15-Jan-13 27-Jan-13 57 A50140 Installation of Lighting Fittings 10 19-Nov-12 29-Nov-12 28-Jan-13 07-Feb-13 57 PlumbingPlumbing 10 14-Jun-12 26-Jun-12 28-Jan-13 07-Feb-13 186 A50220 H/L Hot&Cold Water Pipe Installation 7 14-Jun-12 23-Jun-12 28-Jan-13 04-Feb-13 186 A50240 Floor Drain Fixing 7 14-Jun-12 23-Jun-12 31-Jan-13 07-Feb-13 189 A50260 H/L Drainage Pipes Installation 7 14-Jun-12 23-Jun-12 28-Jan-13 04-Feb-13 186 A50230 Water Pipes Testing 3 24-Jun-12 26-Jun-12 05-Feb-13 07-Feb-13 186 A50270 Drainage&Water Pipes Testing 3 24-Jun-12 26-Jun-12 05-Feb-13 07-Feb-13 186 Fire FighFire Fighting 61 20-Jun-12 01-Sep-12 08-Jan-13 07-Feb-13 131 A50210 Fire Fighting Pipe 8 20-Jun-12 28-Jun-12 08-Jan-13 16-Jan-13 166 A50200 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 17-Jan-13 22-Jan-13 166 A50190 Sprinkler Fixing 7 05-Jul-12 12-Jul-12 23-Jan-13 31-Jan-13 166 A115200 Installation of Fire Hose Cabinet & Landing Valve 6 29-Jul-12 04-Aug-12 02-Feb-13 07-Feb-13 153 A50160 Fire Alarm Devices 6 26-Aug-12 01-Sep-12 02-Feb-13 07-Feb-13 131 RampRamp 113 03-Oct-12 18-Feb-13 30-Oct-12 25-Apr-13 57 FinishingFinishing Works 113 03-Oct-12 18-Feb-13 30-Oct-12 25-Apr-13 57 A113690 Install Handrail 7 03-Oct-12 10-Oct-12 30-Oct-12 06-Nov-12 21 A113700 1st Coat Paint 10 16-Dec-12 26-Dec-12 09-Mar-13 19-Mar-13 69 A113710 Surface Preparation (including Grinding & Repairing) 8 05-Jan-13 13-Jan-13 20-Mar-13 28-Mar-13 63 A113720 Application of 1st Coat 5 14-Jan-13 19-Jan-13 30-Mar-13 03-Apr-13 63 A113740 Application of Final Coat 5 21-Jan-13 27-Jan-13 04-Apr-13 09-Apr-13 62 A113760 Road Marking & Arrows 7 28-Jan-13 04-Feb-13 10-Apr-13 17-Apr-13 62 A113770 Final Coat Paint 7 11-Feb-13 18-Feb-13 18-Apr-13 25-Apr-13 57 Genset RoGenset Room 170 28-May-12 19-Dec-12 25-Aug-12 25-Apr-13 107 FinishingFinishing Works 170 28-May-12 19-Dec-12 25-Aug-12 25-Apr-13 107 Wet WorWet Works 70 28-May-12 18-Aug-12 25-Aug-12 10-Mar-13 167 A49500 Block Works 4 28-May-12 31-May-12 25-Aug-12 28-Aug-12 73 A49460 Installation of Doors& Windows Sub-frame 1 25-Jul-12 25-Jul-12 10-Mar-13 10-Mar-13 187 A49450 Plaster Works 8 25-Jul-12 02-Aug-12 18-Oct-12 29-Oct-12 71 A49470 1st Coat Paint 9 08-Aug-12 18-Aug-12 08-Jan-13 17-Jan-13 124 Fisrt StaFisrt Stage Finishes 68 25-Sep-12 17-Dec-12 26-Feb-13 23-Apr-13 107 A49560 Epoxy Paint Works 2 25-Sep-12 26-Sep-12 26-Feb-13 27-Feb-13 126 A49490 Installation of Doors 2 15-Dec-12 16-Dec-12 11-Mar-13 12-Mar-13 72 A49510 Doors Ironmongery 2 16-Dec-12 17-Dec-12 22-Apr-13 23-Apr-13 107 Second SSecond Stage Finishes 4 27-Sep-12 01-Oct-12 02-Apr-13 06-Apr-13 154 A49480 Final Coat Paint 4 27-Sep-12 01-Oct-12 02-Apr-13 06-Apr-13 154 Final StaFinal Stage Finishes 2 18-Dec-12 19-Dec-12 24-Apr-13 25-Apr-13 107 A49550 Installation of Sinages 2 18-Dec-12 19-Dec-12 24-Apr-13 25-Apr-13 107 MEP WorkMEP Works 94 04-Jun-12 24-Sep-12 29-Aug-12 06-Apr-13 160 HVACHVAC 40 02-Jul-12 16-Aug-12 20-Jan-13 25-Feb-13 157 A49580 Duct Installation & Insulation 7 02-Jul-12 09-Jul-12 20-Jan-13 28-Jan-13 166 A49620 Air-Outlet Installation 7 09-Aug-12 16-Aug-12 18-Feb-13 25-Feb-13 157 ElectricalElectrical 94 04-Jun-12 24-Sep-12 29-Aug-12 25-Feb-13 126 A49520 Install Conduits in Wall 4 04-Jun-12 07-Jun-12 29-Aug-12 02-Sep-12 71 A49530 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 03-Jan-13 07-Jan-13 124 A49540 Installation of Lighting Fittings 7 21-Aug-12 28-Aug-12 19-Jan-13 27-Jan-13 124 A49590 Installation of Generator 30 21-Aug-12 24-Sep-12 21-Jan-13 25-Feb-13 126 Fire FighFire Fighting 14 02-Sep-12 17-Sep-12 18-Feb-13 06-Apr-13 166 A49570 Fire Alarm Devices 7 02-Sep-12 09-Sep-12 18-Feb-13 25-Feb-13 139 A49630 Installation of Fire Extingusher&Blanket 7 10-Sep-12 17-Sep-12 30-Mar-13 06-Apr-13 166 BMS RoomBMS Room 164 02-Jun-12 17-Dec-12 30-Aug-12 25-Apr-13 109 FinishingFinishing Works 164 02-Jun-12 17-Dec-12 30-Aug-12 25-Apr-13 109 Wet WorWet Works 45 02-Jun-12 24-Jul-12 30-Aug-12 06-Mar-13 185 A49690 Block Works 2 02-Jun-12 03-Jun-12 30-Aug-12 01-Sep-12 74 A49650 Installation of Doors& Windows Sub-frame 1 19-Jul-12 19-Jul-12 06-Mar-13 06-Mar-13 189 A49640 Plaster Works 5 19-Jul-12 24-Jul-12 13-Oct-12 17-Oct-12 71 Fisrt StaFisrt Stage Finishes 95 25-Jul-12 18-Nov-12 19-Nov-12 06-Mar-13 90 A49860 Installation of Suspended Ceiling Grid 2 25-Jul-12 26-Jul-12 19-Nov-12 20-Nov-12 95 A49660 1st Coat Paint 4 02-Aug-12 06-Aug-12 21-Nov-12 25-Nov-12 90 A49870 Suspended Ceiling Tiles 2 07-Aug-12 08-Aug-12 14-Jan-13 15-Jan-13 130 A49910 Screed Works 2 13-Nov-12 14-Nov-12 03-Mar-13 04-Mar-13 90 A49890 Floor Tiles Work 2 17-Nov-12 18-Nov-12 05-Mar-13 06-Mar-13 90 Second SSecond Stage Finishes 22 19-Nov-12 15-Dec-12 07-Mar-13 21-Apr-13 107 A49670 Final Coat Paint 2 19-Nov-12 20-Nov-12 07-Apr-13 08-Apr-13 116 A49680 Installation of Doors 3 11-Dec-12 13-Dec-12 07-Mar-13 10-Mar-13 72 A49700 Doors Ironmongery 4 11-Dec-12 15-Dec-12 17-Apr-13 21-Apr-13 107 Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109 A49740 Installation of Sinages 2 16-Dec-12 17-Dec-12 24-Apr-13 25-Apr-13 109 MEP WorkMEP Works 130 09-Jun-12 12-Nov-12 03-Sep-12 08-Apr-13 122 HVACHVAC 50 24-Jun-12 22-Aug-12 11-Nov-12 05-Mar-13 161 A49780 Chilled Water Pipe Installation & Insulation 3 24-Jun-12 26-Jun-12 11-Nov-12 13-Nov-12 116 A49790 Condensate Pipe Installation 3 30-Jun-12 02-Jul-12 11-Nov-12 13-Nov-12 111 A49800 FCU Installation 3 03-Jul-12 05-Jul-12 14-Nov-12 18-Nov-12 111 A49810 Air-Outlet Installation 3 18-Aug-12 22-Aug-12 03-Mar-13 05-Mar-13 161 ElectricalElectrical 130 09-Jun-12 12-Nov-12 03-Sep-12 02-Mar-13 90 A49710 Install Conduits in Wall 2 09-Jun-12 10-Jun-12 03-Sep-12 04-Sep-12 71 A49720 Wiring for Lighting & Power 2 25-Jul-12 26-Jul-12 19-Nov-12 20-Nov-12 95 A49730 Installation of Lighting Fittings 2 13-Aug-12 14-Aug-12 16-Jan-13 17-Jan-13 127 A49760 Installation of BMS System 80 07-Aug-12 12-Nov-12 26-Nov-12 02-Mar-13 90 Fire FighFire Fighting 12 18-Aug-12 02-Sep-12 27-Jan-13 08-Apr-13 181 A49750 Fire Alarm Devices 5 18-Aug-12 25-Aug-12 27-Jan-13 31-Jan-13 131 A49820 Installation of Fire Extinguisher&Blanket 7 26-Aug-12 02-Sep-12 01-Apr-13 08-Apr-13 181 CBS RoomCBS Room 158 04-Jun-12 12-Dec-12 02-Sep-12 25-Apr-13 113 FinishingFinishing Works 158 04-Jun-12 12-Dec-12 02-Sep-12 25-Apr-13 113 Wet WorWet Works 42 04-Jun-12 23-Jul-12 02-Sep-12 04-Mar-13 184 A48470 Block Works 3 04-Jun-12 06-Jun-12 02-Sep-12 04-Sep-12 74 A48420 Plaster Works 6 04-Jul-12 10-Jul-12 27-Sep-12 03-Oct-12 71 A48430 Installation of Doors& Windows Sub-frame 2 14-Jul-12 15-Jul-12 03-Mar-13 04-Mar-13 191 A48440 1st Coat Paint 6 17-Jul-12 23-Jul-12 05-Nov-12 11-Nov-12 91 Fisrt StaFisrt Stage Finishes 79 05-Sep-12 10-Dec-12 24-Feb-13 16-Apr-13 107 A48530 Epoxy Paint Works 2 05-Sep-12 06-Sep-12 24-Feb-13 25-Feb-13 141 A48460 Installation of Doors 2 09-Dec-12 10-Dec-12 05-Mar-13 06-Mar-13 72 A48480 Doors Ironmongery 2 09-Dec-12 10-Dec-12 15-Apr-13 16-Apr-13 107 Second SSecond Stage Finishes 2 09-Sep-12 10-Sep-12 31-Mar-13 01-Apr-13 168 A48450 Final Coat Paint 2 09-Sep-12 10-Sep-12 31-Mar-13 01-Apr-13 168 Final StaFinal Stage Finishes 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113 A48520 Installation of Sinages 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113 MEP WorkMEP Works 58 11-Jun-12 18-Aug-12 05-Sep-12 23-Feb-13 154 HVACHVAC 33 24-Jun-12 31-Jul-12 15-Jan-13 09-Feb-13 157 A48550 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 22-Jan-13 28-Jan-13 175 A48560 Condensate Pipe Installation 5 03-Jul-12 08-Jul-12 15-Jan-13 20-Jan-13 161 A48570 FCU Installation 3 09-Jul-12 11-Jul-12 29-Jan-13 31-Jan-13 167 A48580 Air-Outlet Installation 7 24-Jul-12 31-Jul-12 02-Feb-13 09-Feb-13 157 ElectricalElectrical 58 11-Jun-12 18-Aug-12 05-Sep-12 23-Feb-13 154 A48490 Install Conduits in Wall 5 11-Jun-12 16-Jun-12 05-Sep-12 10-Sep-12 71 A48500 Wiring for Lighting & Power 5 11-Jul-12 16-Jul-12 30-Oct-12 04-Nov-12 91 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Condensate Pipe Installation Installation of Induction Fans Installation of Cable Trays Installation of Bus Bars Cable Pulling Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Floor Drain Fixing H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Hose Cabinet & Landing Valve Fire Alarm Devices Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of Generator Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Final Coat Paint Installation of Doors Doors Ironmongery Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of BMS System Fire Alarm Devices Installation of Fire Extinguisher&Blanket Block Works Plaster Works Installation of Doors& Windows Sub-frame 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 22 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 23. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A48510 Installation of Lighting Fittings 5 24-Jul-12 29-Jul-12 30-Dec-12 05-Jan-13 130 A48730 Installation of Centeral Battery System 14 02-Aug-12 18-Aug-12 07-Feb-13 23-Feb-13 154 Fire FighFire Fighting 5 12-Aug-12 16-Aug-12 20-Jan-13 26-Jan-13 131 A48540 Fire Alarm Devices 5 12-Aug-12 16-Aug-12 20-Jan-13 26-Jan-13 131 ELV RoomELV Room 154 07-Jun-12 11-Dec-12 06-Sep-12 25-Apr-13 114 FinishingFinishing Works 154 07-Jun-12 11-Dec-12 06-Sep-12 25-Apr-13 114 Wet WorWet Works 47 07-Jun-12 01-Aug-12 06-Sep-12 02-Mar-13 174 A49310 Block Works 4 07-Jun-12 11-Jun-12 06-Sep-12 10-Sep-12 75 A49270 Installation of Doors& Windows Sub-frame 2 11-Jul-12 12-Jul-12 28-Feb-13 02-Mar-13 191 A49260 Plaster Works 7 11-Jul-12 18-Jul-12 04-Oct-12 11-Oct-12 71 A49280 1st Coat Paint 7 25-Jul-12 01-Aug-12 12-Nov-12 20-Nov-12 90 Fisrt StaFisrt Stage Finishes 4 04-Dec-12 08-Dec-12 28-Feb-13 14-Apr-13 107 A49370 Epoxy Paint Works 2 04-Dec-12 05-Dec-12 28-Feb-13 02-Mar-13 72 A49300 Installation of Doors 2 06-Dec-12 08-Dec-12 03-Mar-13 04-Mar-13 72 A49320 Doors Ironmongery 2 06-Dec-12 08-Dec-12 13-Apr-13 14-Apr-13 107 Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 09-Apr-13 11-Apr-13 104 A49290 Final Coat Paint 3 06-Dec-12 09-Dec-12 09-Apr-13 11-Apr-13 104 Final StaFinal Stage Finishes 2 10-Dec-12 11-Dec-12 24-Apr-13 25-Apr-13 114 A49360 Installation of Sinages 2 10-Dec-12 11-Dec-12 24-Apr-13 25-Apr-13 114 MEP WorkMEP Works 139 18-Jun-12 03-Dec-12 11-Sep-12 11-Apr-13 109 HVACHVAC 40 24-Jun-12 08-Aug-12 21-Jan-13 17-Feb-13 157 A49400 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 30-Jan-13 04-Feb-13 181 A49410 Condensate Pipe Installation 5 09-Jul-12 14-Jul-12 21-Jan-13 27-Jan-13 161 A49390 Duct Installation & Insulation 6 10-Jul-12 16-Jul-12 29-Jan-13 04-Feb-13 166 A49420 FCU Installation 4 17-Jul-12 21-Jul-12 05-Feb-13 09-Feb-13 166 A49430 Air-Outlet Installation 7 01-Aug-12 08-Aug-12 10-Feb-13 17-Feb-13 157 ElectricalElectrical 139 18-Jun-12 03-Dec-12 11-Sep-12 27-Feb-13 72 A49330 Install Conduits in Wall 5 18-Jun-12 23-Jun-12 11-Sep-12 16-Sep-12 71 A49340 Wiring for Lighting & Power 5 19-Jul-12 24-Jul-12 06-Nov-12 11-Nov-12 90 A49350 Installation of Lighting Fittings 5 02-Aug-12 07-Aug-12 06-Jan-13 10-Jan-13 127 A114310 Installation of MATC,TV System 80 02-Aug-12 07-Nov-12 24-Nov-12 27-Feb-13 92 A49600 Installation of Access ControlSystem 80 28-Aug-12 03-Dec-12 24-Nov-12 27-Feb-13 72 Fire FighFire Fighting 15 02-Aug-12 21-Aug-12 10-Jan-13 11-Apr-13 194 A49380 Fire Alarm Devices 8 02-Aug-12 11-Aug-12 10-Jan-13 19-Jan-13 131 A49440 Installation of Fire Extinguisher&Blanket 7 12-Aug-12 21-Aug-12 04-Apr-13 11-Apr-13 194 MechanicaMechanical Rooms 105 12-Jun-12 15-Oct-12 15-Sep-12 25-Apr-13 159 FinishingFinishing Works 105 12-Jun-12 15-Oct-12 15-Sep-12 25-Apr-13 159 Wet WorWet Works 28 12-Jun-12 15-Jul-12 15-Sep-12 27-Feb-13 187 A49970 Block Works 2 12-Jun-12 13-Jun-12 15-Sep-12 16-Sep-12 78 A49930 Installation of Doors& Windows Sub-frame 2 28-Jun-12 30-Jun-12 26-Feb-13 27-Feb-13 200 A49920 Plaster Works 5 28-Jun-12 03-Jul-12 22-Sep-12 26-Sep-12 71 A49940 1st Coat Paint 6 09-Jul-12 15-Jul-12 29-Oct-12 04-Nov-12 92 Fisrt StaFisrt Stage Finishes 30 13-Aug-12 18-Sep-12 19-Feb-13 11-Apr-13 170 A50030 Epoxy Paint Works 2 13-Aug-12 14-Aug-12 19-Feb-13 20-Feb-13 155 A49960 Installation of Doors 2 08-Sep-12 09-Sep-12 28-Feb-13 02-Mar-13 143 A49980 Doors Ironmongery 2 17-Sep-12 18-Sep-12 10-Apr-13 11-Apr-13 170 Second SSecond Stage Finishes 2 15-Aug-12 16-Aug-12 25-Mar-13 26-Mar-13 182 A49950 Final Coat Paint 2 15-Aug-12 16-Aug-12 25-Mar-13 26-Mar-13 182 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 A50020 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 MEP WorkMEP Works 43 24-Jun-12 12-Aug-12 17-Sep-12 15-Jan-13 127 HVACHVAC 15 16-Jul-12 01-Aug-12 24-Dec-12 10-Jan-13 132 A50040 Shaft Works 15 16-Jul-12 01-Aug-12 24-Dec-12 10-Jan-13 132 ElectricalElectrical 43 24-Jun-12 12-Aug-12 17-Sep-12 15-Jan-13 127 A49990 Install Conduits in Wall 4 24-Jun-12 27-Jun-12 17-Sep-12 20-Sep-12 71 A50000 Wiring for Lighting & Power 4 04-Jul-12 08-Jul-12 22-Oct-12 28-Oct-12 92 A50010 Installation of Lighting Fittings 4 08-Aug-12 12-Aug-12 12-Jan-13 15-Jan-13 127 LV Room (LV Room (Block A) 122 23-May-12 15-Oct-12 16-Aug-12 25-Apr-13 159 FinishingFinishing Works 122 23-May-12 15-Oct-12 16-Aug-12 25-Apr-13 159 Wet WorWet Works 34 23-May-12 02-Jul-12 16-Aug-12 25-Feb-13 196 A48640 Block Works 4 23-May-12 27-May-12 16-Aug-12 22-Aug-12 72 A48600 Installation of Doors& Windows Sub-frame 2 06-Jun-12 07-Jun-12 24-Feb-13 25-Feb-13 216 A48590 Plaster Works 6 06-Jun-12 12-Jun-12 15-Sep-12 20-Sep-12 83 A48610 1st Coat Paint 5 27-Jun-12 02-Jul-12 21-Oct-12 28-Oct-12 97 Fisrt StaFisrt Stage Finishes 12 03-Sep-12 16-Sep-12 21-Feb-13 09-Apr-13 170 A48700 Epoxy Paint Works 2 03-Sep-12 04-Sep-12 21-Feb-13 23-Feb-13 141 A48630 Installation of Doors 2 05-Sep-12 06-Sep-12 26-Feb-13 27-Feb-13 143 A48650 Doors Ironmongery 2 15-Sep-12 16-Sep-12 08-Apr-13 09-Apr-13 170 Second SSecond Stage Finishes 3 05-Sep-12 08-Sep-12 27-Mar-13 30-Mar-13 168 A48620 Final Coat Paint 3 05-Sep-12 08-Sep-12 27-Mar-13 30-Mar-13 168 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 A48690 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 MEP WorkMEP Works 84 24-May-12 02-Sep-12 23-Aug-12 20-Feb-13 141 HVACHVAC 5 24-May-12 29-May-12 07-Jan-13 12-Jan-13 187 A48750 Air-Outlet Installation 5 24-May-12 29-May-12 07-Jan-13 12-Jan-13 187 ElectricalElectrical 80 29-May-12 02-Sep-12 23-Aug-12 20-Feb-13 141 A48660 Install Conduits in Wall 5 29-May-12 03-Jun-12 23-Aug-12 28-Aug-12 71 A48670 Wiring for Lighting & Power 5 13-Jun-12 19-Jun-12 15-Oct-12 20-Oct-12 103 A48680 Installation of Lighting Fittings 5 03-Jul-12 08-Jul-12 24-Dec-12 29-Dec-12 143 A114360 Laying of LV Cables 15 03-Jul-12 19-Jul-12 22-Jan-13 09-Feb-13 167 A114370 Test of LV Cables 5 21-Jul-12 25-Jul-12 10-Feb-13 14-Feb-13 167 A48720 Installation of MDBs 30 22-Jul-12 27-Aug-12 10-Jan-13 14-Feb-13 141 A114380 Termination of LV Cables 5 28-Aug-12 02-Sep-12 16-Feb-13 20-Feb-13 141 Fire FighFire Fighting 10 14-Jul-12 24-Jul-12 29-Dec-12 09-Jan-13 138 A48710 Fire Alarm Devices 10 14-Jul-12 24-Jul-12 29-Dec-12 09-Jan-13 138 Sub-StatioSub-Station 1 186 16-May-12 26-Dec-12 08-Aug-12 25-Apr-13 101 FinishingFinishing Works 128 16-May-12 15-Oct-12 08-Aug-12 25-Apr-13 159 Wet WorWet Works 35 16-May-12 26-Jun-12 08-Aug-12 23-Feb-13 199 A48810 Block Works 6 16-May-12 22-May-12 08-Aug-12 14-Aug-12 71 A48770 Installation of Doors& Windows Sub-frame 2 31-May-12 02-Jun-12 21-Feb-13 23-Feb-13 219 A48760 Plaster Works 5 31-May-12 05-Jun-12 09-Sep-12 13-Sep-12 83 A48780 1st Coat Paint 9 16-Jun-12 26-Jun-12 10-Oct-12 20-Oct-12 97 Fisrt StaFisrt Stage Finishes 5 24-Jul-12 29-Jul-12 16-Feb-13 07-Apr-13 208 A48870 Epoxy Paint Works 3 24-Jul-12 26-Jul-12 16-Feb-13 18-Feb-13 169 A48800 Installation of Doors 2 28-Jul-12 29-Jul-12 24-Feb-13 25-Feb-13 173 A48820 Doors Ironmongery 2 28-Jul-12 29-Jul-12 06-Apr-13 07-Apr-13 208 Second SSecond Stage Finishes 4 31-Jul-12 04-Aug-12 04-Mar-13 07-Mar-13 177 A48790 Final Coat Paint 4 31-Jul-12 04-Aug-12 04-Mar-13 07-Mar-13 177 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 A48860 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 MEP WorkMEP Works 180 23-May-12 26-Dec-12 15-Aug-12 21-Mar-13 71 HVACHVAC 12 10-Jul-12 23-Jul-12 17-Jan-13 31-Jan-13 157 A48890 Air-Outlet Installation 12 10-Jul-12 23-Jul-12 17-Jan-13 31-Jan-13 157 ElectricalElectrical 180 23-May-12 26-Dec-12 15-Aug-12 21-Mar-13 71 Light &Light & Power 34 23-May-12 02-Jul-12 15-Aug-12 23-Dec-12 143 A48830 Install Conduits in Wall 5 23-May-12 28-May-12 15-Aug-12 22-Aug-12 71 A48840 Wiring for Lighting & Power 5 06-Jun-12 11-Jun-12 04-Oct-12 09-Oct-12 100 A48850 Installation of Lighting Fittings 5 27-Jun-12 02-Jul-12 18-Dec-12 23-Dec-12 143 TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71 A48910 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71 A48900 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87 A48920 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Lighting Fittings Installation of Centeral Battery System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of MATC,TV System Installation of Access ControlSystem Fire Alarm Devices Installation of Fire Extinguisher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Shaft Works Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Laying of LV Cables Test of LV Cables Installation of MDBs Termination of LV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Install Cable Tray & Trunking Installation of Transformer Install of LV Cables Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 23 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 24. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A48930 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 A48940 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A48970 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A48960 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 A48980 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 Fire FighFire Fighting 14 27-Jun-12 12-Jul-12 12-Dec-12 27-Dec-12 138 A48880 Fire Alarm Devices 14 27-Jun-12 12-Jul-12 12-Dec-12 27-Dec-12 138 House keeHouse keeping Room 133 10-May-12 15-Oct-12 02-Aug-12 25-Apr-13 159 FinishingFinishing Works 133 10-May-12 15-Oct-12 02-Aug-12 25-Apr-13 159 Wet WorWet Works 31 10-May-12 14-Jun-12 02-Aug-12 20-Feb-13 206 A49040 Block Works 5 10-May-12 15-May-12 02-Aug-12 07-Aug-12 71 A49000 Installation of Doors& Windows Sub-frame 2 21-May-12 22-May-12 19-Feb-13 20-Feb-13 226 A48990 Plaster Works 9 21-May-12 30-May-12 29-Aug-12 08-Sep-12 83 A49010 1st Coat Paint 9 05-Jun-12 14-Jun-12 30-Sep-12 09-Oct-12 97 Fisrt StaFisrt Stage Finishes 57 10-Jul-12 16-Sep-12 12-Feb-13 12-Mar-13 146 A49100 Epoxy Paint Works 3 10-Jul-12 12-Jul-12 12-Feb-13 14-Feb-13 178 A49030 Installation of Doors 2 14-Jul-12 15-Jul-12 21-Feb-13 23-Feb-13 183 A49050 Doors Ironmongery 2 15-Sep-12 16-Sep-12 11-Mar-13 12-Mar-13 146 Second SSecond Stage Finishes 4 26-Jul-12 30-Jul-12 27-Feb-13 03-Mar-13 177 A49020 Final Coat Paint 4 26-Jul-12 30-Jul-12 27-Feb-13 03-Mar-13 177 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 A49090 Installation of Sinages 2 14-Oct-12 15-Oct-12 24-Apr-13 25-Apr-13 159 MEP WorkMEP Works 64 16-May-12 30-Jul-12 11-Aug-12 03-Mar-13 177 HVACHVAC 14 24-Jun-12 09-Jul-12 05-Nov-12 16-Jan-13 157 A49140 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 03-Jan-13 08-Jan-13 159 A49150 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 05-Nov-12 10-Nov-12 111 A49130 Duct Installation & Insulation 7 24-Jun-12 01-Jul-12 31-Dec-12 08-Jan-13 157 A49160 FCU Installation 3 02-Jul-12 04-Jul-12 09-Jan-13 12-Jan-13 157 A49170 Air-Outlet Installation 4 05-Jul-12 09-Jul-12 13-Jan-13 16-Jan-13 157 ElectricalElectrical 31 16-May-12 21-Jun-12 11-Aug-12 11-Feb-13 193 A49060 Install Conduits in Wall 4 16-May-12 20-May-12 11-Aug-12 14-Aug-12 73 A49070 Wiring for Lighting & Power 4 31-May-12 04-Jun-12 25-Sep-12 29-Sep-12 97 A49080 Installation of Lighting Fittings 5 16-Jun-12 21-Jun-12 06-Feb-13 11-Feb-13 193 PlumbingPlumbing 3 16-Jun-12 19-Jun-12 09-Feb-13 11-Feb-13 195 A49250 Floor Drain Fixning 3 16-Jun-12 19-Jun-12 09-Feb-13 11-Feb-13 195 Fire FighFire Fighting 42 11-Jun-12 30-Jul-12 30-Dec-12 03-Mar-13 177 A49210 Fire Fighting Pipe 7 11-Jun-12 19-Jun-12 30-Dec-12 07-Jan-13 166 A49200 Hydro Static Test for Pipes 3 20-Jun-12 23-Jun-12 23-Jan-13 27-Jan-13 179 A49190 Sprinkler Fixing 6 24-Jun-12 30-Jun-12 28-Jan-13 03-Feb-13 179 A49110 Fire Alarm Devices 7 01-Jul-12 08-Jul-12 04-Feb-13 11-Feb-13 179 A49180 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 02-Mar-13 03-Mar-13 177 StaircaseStaircase 133 28-Jun-12 06-Dec-12 01-Oct-12 25-Apr-13 118 Stair 1Stair 1 133 28-Jun-12 06-Dec-12 01-Oct-12 25-Apr-13 118 A107990 Floor Screed 3 28-Jun-12 01-Jul-12 01-Oct-12 03-Oct-12 79 A108000 Install Handrails 4 11-Oct-12 15-Oct-12 07-Nov-12 11-Nov-12 21 A108010 Ceiling 1st Coat Paint 7 20-Oct-12 29-Oct-12 06-Dec-12 13-Dec-12 37 A108020 Wall 1st Coat Paint 7 30-Oct-12 06-Nov-12 15-Dec-12 22-Dec-12 37 A108030 Install Granite/Terrazo 12 07-Nov-12 21-Nov-12 05-Jan-13 17-Jan-13 47 A108040 Final Coat Paint 12 22-Nov-12 06-Dec-12 13-Apr-13 25-Apr-13 118 Ground FloorGround Floor 381 09-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21 Public AreaPublic Area 381 09-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21 RampRamp 103 16-Oct-12 19-Feb-13 12-Nov-12 22-Apr-13 53 A115710 Install Handrail 7 16-Oct-12 23-Oct-12 12-Nov-12 20-Nov-12 21 A115720 1st Coat Paint 10 24-Oct-12 06-Nov-12 05-Mar-13 16-Mar-13 107 A115730 Surface Preparation (including Grinding & Repairing) 8 13-Jan-13 21-Jan-13 17-Mar-13 25-Mar-13 53 A115740 Application of 1st Coat 5 22-Jan-13 28-Jan-13 26-Mar-13 31-Mar-13 53 A115750 Application of Final Coat 5 29-Jan-13 03-Feb-13 01-Apr-13 06-Apr-13 53 A115760 Road Marking & Arrows 7 04-Feb-13 11-Feb-13 07-Apr-13 14-Apr-13 53 A115770 Final Coat Paint 7 12-Feb-13 19-Feb-13 15-Apr-13 22-Apr-13 53 Retail 1Retail 1 118 14-Jul-12 04-Dec-12 03-Jan-13 25-Apr-13 120 FinishingFinishing Works 118 14-Jul-12 04-Dec-12 03-Jan-13 25-Apr-13 120 Wet WorWet Works 12 14-Jul-12 26-Jul-12 03-Jan-13 23-Feb-13 173 A53150 Block Works 10 14-Jul-12 24-Jul-12 03-Jan-13 14-Jan-13 142 A53010 Installation of Doors& Windows Sub-frame 2 25-Jul-12 26-Jul-12 21-Feb-13 23-Feb-13 173 Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 14-Mar-13 25-Apr-13 120 A53090 Installation of Windows&Doors 2 03-Dec-12 04-Dec-12 14-Mar-13 16-Mar-13 85 A53160 Doors Ironmongery 2 03-Dec-12 04-Dec-12 24-Apr-13 25-Apr-13 120 MEP WorkMEP Works 23 25-Jul-12 22-Aug-12 15-Jan-13 05-Mar-13 161 HVACHVAC 23 25-Jul-12 22-Aug-12 19-Jan-13 05-Feb-13 137 A53200 Condensate Pipe Installation 10 25-Jul-12 05-Aug-12 19-Jan-13 30-Jan-13 145 A53190 Chilled Water Pipe Installation & Insulation 10 04-Aug-12 14-Aug-12 19-Jan-13 30-Jan-13 137 A53210 FCU Installation 5 15-Aug-12 22-Aug-12 31-Jan-13 05-Feb-13 137 ElectricalElectrical 10 25-Jul-12 05-Aug-12 23-Feb-13 05-Mar-13 174 A53230 Install Conduits in Wall 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174 A53250 Wiring for Lighting & Power 3 02-Aug-12 05-Aug-12 03-Mar-13 05-Mar-13 174 PlumbingPlumbing 10 25-Jul-12 05-Aug-12 23-Feb-13 05-Mar-13 174 A53330 Drainge Pipes in Wall 7 25-Jul-12 01-Aug-12 26-Feb-13 05-Mar-13 177 A53340 H/L Drainage Pipes Installation 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174 A53350 H/L Hot&Cold Water Pipe Installation 7 25-Jul-12 01-Aug-12 23-Feb-13 02-Mar-13 174 A53400 Water Pipes in Wall 7 25-Jul-12 01-Aug-12 26-Feb-13 05-Mar-13 177 A53360 Drainage&Water Pipes Testing 3 02-Aug-12 05-Aug-12 03-Mar-13 05-Mar-13 174 Fire FighFire Fighting 20 25-Jul-12 16-Aug-12 15-Jan-13 05-Mar-13 164 A53440 Fire Fighting Pipe 7 25-Jul-12 01-Aug-12 15-Jan-13 22-Jan-13 142 A53430 Hydro Static Test for Pipes 4 02-Aug-12 06-Aug-12 23-Jan-13 28-Jan-13 142 A53420 Sprinkler Fixing 3 07-Aug-12 09-Aug-12 29-Jan-13 31-Jan-13 142 A53520 Fire Alarm Devices 5 11-Aug-12 15-Aug-12 02-Feb-13 06-Feb-13 142 A115210 Installation of Fire Hose Cabinet & Landing Valve 6 11-Aug-12 16-Aug-12 27-Feb-13 05-Mar-13 164 Retail 2Retail 2 127 01-Jul-12 01-Dec-12 20-Dec-12 23-Apr-13 120 FinishingFinishing Works 127 01-Jul-12 01-Dec-12 20-Dec-12 23-Apr-13 120 Wet WorWet Works 13 01-Jul-12 15-Jul-12 20-Dec-12 20-Feb-13 181 A53550 Block Works 11 01-Jul-12 12-Jul-12 20-Dec-12 02-Jan-13 142 A53530 Installation of Doors& Windows Sub-frame 2 14-Jul-12 15-Jul-12 19-Feb-13 20-Feb-13 181 Final StaFinal Stage Finishes 2 29-Nov-12 01-Dec-12 12-Mar-13 23-Apr-13 120 A53540 Installation of Windows&Doors 2 29-Nov-12 01-Dec-12 12-Mar-13 13-Mar-13 85 A53560 Doors Ironmongery 2 29-Nov-12 01-Dec-12 22-Apr-13 23-Apr-13 120 MEP WorkMEP Works 25 14-Jul-12 11-Aug-12 07-Jan-13 05-Mar-13 169 HVACHVAC 23 14-Jul-12 08-Aug-12 07-Jan-13 30-Jan-13 142 A53580 Condensate Pipe Installation 10 14-Jul-12 24-Jul-12 07-Jan-13 17-Jan-13 145 A53570 Chilled Water Pipe Installation & Insulation 10 23-Jul-12 02-Aug-12 07-Jan-13 17-Jan-13 137 A53590 FCU Installation 5 04-Aug-12 08-Aug-12 26-Jan-13 30-Jan-13 142 ElectricalElectrical 10 14-Jul-12 24-Jul-12 14-Feb-13 05-Mar-13 184 A53600 Install Conduits in Wall 7 14-Jul-12 21-Jul-12 14-Feb-13 21-Feb-13 177 A53610 Wiring for Lighting & Power 3 22-Jul-12 24-Jul-12 03-Mar-13 05-Mar-13 184 PlumbingPlumbing 10 14-Jul-12 24-Jul-12 23-Feb-13 05-Mar-13 184 A53620 Drainge Pipes in Wall 7 14-Jul-12 21-Jul-12 26-Feb-13 05-Mar-13 187 A53630 H/L Drainage Pipes Installation 7 14-Jul-12 21-Jul-12 23-Feb-13 02-Mar-13 184 A53640 H/L Hot&Cold Water Pipe Installation 7 14-Jul-12 21-Jul-12 23-Feb-13 02-Mar-13 184 A53660 Water Pipes in Wall 7 14-Jul-12 21-Jul-12 26-Feb-13 05-Mar-13 187 A53650 Drainage&Water Pipes Testing 3 22-Jul-12 24-Jul-12 03-Mar-13 05-Mar-13 184 Fire FighFire Fighting 25 14-Jul-12 11-Aug-12 07-Jan-13 05-Mar-13 169 A53700 Fire Fighting Pipe 7 14-Jul-12 21-Jul-12 07-Jan-13 14-Jan-13 145 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install of MV Cables Test of LV Cables Test of MV Cables Termination of LV Cables Termination of MV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Installation of Windows&Doors Doors Ironmongery Condensate Pipe Installation Chilled Water Pipe Installation & Insulation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Hose Cabinet & Landing Valve Block Works Installation of Doors& Windows Sub-frame Installation of Windows&Doors Doors Ironmongery Condensate Pipe Installation Chilled Water Pipe Installation & Insulation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Fire Fighting Pipe Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 24 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 25. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A53690 Hydro Static Test for Pipes 4 22-Jul-12 25-Jul-12 17-Jan-13 21-Jan-13 147 A53680 Sprinkler Fixing 3 26-Jul-12 29-Jul-12 22-Jan-13 26-Jan-13 147 A53710 Fire Alarm Devices 5 30-Jul-12 04-Aug-12 27-Jan-13 31-Jan-13 147 A115220 Installation of Fire Hose Cabinet & Landing Valve 6 05-Aug-12 11-Aug-12 27-Feb-13 05-Mar-13 169 EnteranceEnterance & Lift Lobby 368 25-Jun-12 08-Sep-13 15-Dec-12 02-Oct-13 21 FinishingFinishing Works 368 25-Jun-12 08-Sep-13 15-Dec-12 02-Oct-13 21 Wet WorWet Works 62 25-Jun-12 06-Sep-12 15-Dec-12 16-Feb-13 133 A50750 Block Works 5 25-Jun-12 30-Jun-12 15-Dec-12 19-Dec-12 142 A50700 Plaster Works 4 12-Jul-12 16-Jul-12 13-Jan-13 16-Jan-13 151 A50720 Installation of Suspended Ceiling Grid 5 29-Jul-12 02-Aug-12 21-Jan-13 27-Jan-13 144 A50710 1st Coat Paint 6 01-Sep-12 06-Sep-12 10-Feb-13 16-Feb-13 133 Fisrt StaFisrt Stage Finishes 9 08-Sep-12 17-Sep-12 17-Feb-13 26-Feb-13 133 A50730 Suspended Ceiling Tiles 5 08-Sep-12 12-Sep-12 17-Feb-13 21-Feb-13 133 A50970 MDF for Lift Lobby Wall 7 08-Sep-12 15-Sep-12 17-Feb-13 24-Feb-13 133 A50950 Screed Works 2 16-Sep-12 17-Sep-12 25-Feb-13 26-Feb-13 133 Second SSecond Stage Finishes 9 18-Sep-12 27-Sep-12 27-Feb-13 09-Mar-13 133 A50960 Wall Tiles Work 5 18-Sep-12 23-Sep-12 27-Feb-13 04-Mar-13 133 A50990 Floor Tiles Work 4 24-Sep-12 27-Sep-12 05-Mar-13 09-Mar-13 133 Final StaFinal Stage Finishes 240 27-Nov-12 08-Sep-13 10-Mar-13 02-Oct-13 21 A50740 Installation of Doors 2 27-Nov-12 28-Nov-12 10-Mar-13 11-Mar-13 85 A50760 Doors Ironmongery 2 27-Nov-12 28-Nov-12 20-Apr-13 21-Apr-13 120 A51010 Installation of Mirrors 5 27-Nov-12 03-Dec-12 06-Apr-13 10-Apr-13 108 A51000 Final Coat Paint 3 04-Dec-12 06-Dec-12 11-Apr-13 14-Apr-13 108 A50940 Installation of Sinages 2 08-Dec-12 09-Dec-12 24-Apr-13 25-Apr-13 116 A53770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 71 01-Jul-12 23-Sep-12 29-Dec-12 05-Mar-13 134 HVACHVAC 67 03-Jul-12 20-Sep-12 29-Dec-12 05-Mar-13 136 A50790 Condensate Pipe Installation 7 03-Jul-12 10-Jul-12 29-Dec-12 06-Jan-13 147 A50770 Duct Installation & Insulation 7 10-Jul-12 17-Jul-12 07-Jan-13 14-Jan-13 148 A50780 Chilled Water Pipe Installation & Insulation 7 15-Jul-12 22-Jul-12 29-Dec-12 06-Jan-13 137 A50800 FCU Installation 5 23-Jul-12 28-Jul-12 15-Jan-13 20-Jan-13 144 A50810 Air-Outlet Installation 7 13-Sep-12 20-Sep-12 26-Feb-13 05-Mar-13 136 ElectricalElectrical 68 01-Jul-12 19-Sep-12 09-Jan-13 05-Mar-13 137 A50820 Install Conduits in Wall 3 01-Jul-12 03-Jul-12 09-Jan-13 12-Jan-13 158 A50830 Install Cable Trays & Trunking 3 01-Jul-12 03-Jul-12 12-Jan-13 14-Jan-13 160 A50870 Cable Laying for Low Current System 5 04-Jul-12 09-Jul-12 21-Jan-13 27-Jan-13 165 A50880 Cable Laying for Power 5 04-Jul-12 09-Jul-12 21-Jan-13 27-Jan-13 165 A50840 Wiring for Lighting & Power 3 17-Jul-12 19-Jul-12 17-Jan-13 20-Jan-13 151 A50850 Wiring for Low Current System 3 17-Jul-12 19-Jul-12 17-Jan-13 20-Jan-13 151 A50900 Installation of Lighting Fittings 6 13-Sep-12 19-Sep-12 27-Feb-13 05-Mar-13 137 Fire FighFire Fighting 71 01-Jul-12 23-Sep-12 29-Dec-12 05-Mar-13 134 A50930 Fire Fighting Pipe 7 01-Jul-12 08-Jul-12 29-Dec-12 06-Jan-13 149 A50920 Hydro Static Test for Pipes 7 09-Jul-12 16-Jul-12 13-Jan-13 20-Jan-13 154 A50910 Sprinkler Fixing 5 13-Sep-12 18-Sep-12 26-Feb-13 03-Mar-13 136 A50980 Fire Alarm Devices 7 13-Sep-12 20-Sep-12 24-Feb-13 03-Mar-13 134 A51020 Installation of Fire Hose Cabinet & Landing Valve 2 22-Sep-12 23-Sep-12 04-Mar-13 05-Mar-13 134 Electrical -Electrical -Telephone Room 133 21-Jun-12 28-Nov-12 11-Dec-12 25-Apr-13 124 FinishingFinishing Works 133 21-Jun-12 28-Nov-12 11-Dec-12 25-Apr-13 124 Wet WorWet Works 25 21-Jun-12 19-Jul-12 11-Dec-12 18-Feb-13 175 A51610 Block Works 3 21-Jun-12 24-Jun-12 11-Dec-12 13-Dec-12 142 A51570 Installation of Doors& Windows Sub-frame 2 08-Jul-12 09-Jul-12 17-Feb-13 18-Feb-13 184 A51560 Plaster Works 4 08-Jul-12 11-Jul-12 06-Jan-13 09-Jan-13 149 A51580 1st Coat Paint 4 16-Jul-12 19-Jul-12 14-Jan-13 17-Jan-13 149 Fisrt StaFisrt Stage Finishes 70 03-Sep-12 26-Nov-12 05-Mar-13 18-Apr-13 120 A51670 Epoxy Paint Works 2 03-Sep-12 04-Sep-12 05-Mar-13 06-Mar-13 151 A51600 Installation of Doors 2 25-Nov-12 26-Nov-12 07-Mar-13 09-Mar-13 85 A51620 Doors Ironmongery 2 25-Nov-12 26-Nov-12 17-Apr-13 18-Apr-13 120 Second SSecond Stage Finishes 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167 A51590 Final Coat Paint 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167 Final StaFinal Stage Finishes 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124 A51660 Installation of Sinages 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124 MEP WorkMEP Works 58 25-Jun-12 02-Sep-12 02-Jan-13 08-Apr-13 181 HVACHVAC 7 25-Jul-12 01-Aug-12 04-Feb-13 11-Feb-13 158 A51700 Air-Outlet Installation 7 25-Jul-12 01-Aug-12 04-Feb-13 11-Feb-13 158 ElectricalElectrical 58 25-Jun-12 02-Sep-12 02-Jan-13 04-Mar-13 151 A51630 Install Conduits in Wall 3 25-Jun-12 27-Jun-12 02-Jan-13 05-Jan-13 157 A51640 Wiring for Lighting & Power 3 12-Jul-12 15-Jul-12 10-Jan-13 13-Jan-13 149 A51650 Installation of Lighting Fittings 4 21-Jul-12 24-Jul-12 28-Feb-13 04-Mar-13 183 A51690 Installation of SMDBs 7 22-Jul-12 29-Jul-12 25-Feb-13 04-Mar-13 179 A51740 Installation of Telephone System 15 14-Aug-12 02-Sep-12 16-Feb-13 04-Mar-13 151 Fire FighFire Fighting 9 21-Jul-12 30-Jul-12 19-Jan-13 08-Apr-13 208 A51680 Fire Alarm Devices 6 21-Jul-12 26-Jul-12 19-Jan-13 26-Jan-13 149 A51710 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 07-Apr-13 08-Apr-13 208 Main GarbMain Garbage Room 213 09-Jun-12 21-Feb-13 28-Nov-12 24-Apr-13 53 FinishingFinishing Works 213 09-Jun-12 21-Feb-13 28-Nov-12 24-Apr-13 53 Wet WorWet Works 64 09-Jun-12 25-Aug-12 28-Nov-12 11-Feb-13 140 A51180 Block Works 2 09-Jun-12 10-Jun-12 28-Nov-12 29-Nov-12 142 A51040 Installation of Doors& Windows Sub-frame 1 14-Jun-12 14-Jun-12 11-Feb-13 11-Feb-13 198 A51030 Plaster Works 3 14-Jun-12 18-Jun-12 16-Dec-12 18-Dec-12 151 A51510 Wall Tiles Work 8 14-Aug-12 25-Aug-12 21-Jan-13 30-Jan-13 130 Fisrt StaFisrt Stage Finishes 10 26-Aug-12 05-Sep-12 31-Jan-13 11-Feb-13 130 A51500 Screed Works 2 26-Aug-12 27-Aug-12 31-Jan-13 02-Feb-13 130 A51050 1st Coat Paint 3 28-Aug-12 30-Aug-12 03-Feb-13 05-Feb-13 130 A51520 Floor Tiles Work 2 04-Sep-12 05-Sep-12 10-Feb-13 11-Feb-13 130 Second SSecond Stage Finishes 2 22-Nov-12 24-Nov-12 05-Mar-13 16-Apr-13 120 A51120 Installation of Doors 2 22-Nov-12 24-Nov-12 05-Mar-13 06-Mar-13 85 A51190 Doors Ironmongery 2 22-Nov-12 24-Nov-12 15-Apr-13 16-Apr-13 120 Final StaFinal Stage Finishes 105 16-Oct-12 21-Feb-13 12-Feb-13 24-Apr-13 53 A51150 Installation of Equipments 60 16-Oct-12 29-Dec-12 12-Feb-13 22-Apr-13 96 A51080 Final Coat Paint 2 20-Feb-13 21-Feb-13 23-Apr-13 24-Apr-13 53 MEP WorkMEP Works 211 11-Jun-12 21-Feb-13 08-Dec-12 24-Apr-13 53 HVACHVAC 60 24-Jun-12 03-Sep-12 08-Dec-12 09-Feb-13 130 A51220 Chilled Water Pipe Installation & Insulation 4 24-Jun-12 27-Jun-12 08-Dec-12 11-Dec-12 137 A51230 Condensate Pipe Installation 4 24-Jun-12 27-Jun-12 19-Dec-12 23-Dec-12 147 A51240 FCU Installation 3 01-Sep-12 03-Sep-12 06-Feb-13 09-Feb-13 130 ElectricalElectrical 70 11-Jun-12 03-Sep-12 12-Dec-12 05-Mar-13 151 A51260 Install Conduits in Wall 3 11-Jun-12 13-Jun-12 12-Dec-12 15-Dec-12 151 A51280 Wiring for Lighting & Power 3 19-Jun-12 21-Jun-12 30-Jan-13 02-Feb-13 185 A51340 Installation of Lighting Fittings 3 01-Sep-12 03-Sep-12 03-Mar-13 05-Mar-13 151 PlumbingPlumbing 7 11-Jun-12 19-Jun-12 12-Dec-12 02-Feb-13 187 A51430 Water Pipes in Wall 3 11-Jun-12 13-Jun-12 12-Dec-12 15-Dec-12 151 A51370 H/L Drainage Pipes Installation 4 11-Jun-12 14-Jun-12 26-Jan-13 29-Jan-13 187 A51380 H/L Hot&Cold Water Pipe Installation 4 11-Jun-12 14-Jun-12 26-Jan-13 29-Jan-13 187 A51390 Drainage&Water Pipes Testing 3 16-Jun-12 19-Jun-12 30-Jan-13 02-Feb-13 187 Fire FighFire Fighting 211 11-Jun-12 21-Feb-13 19-Dec-12 24-Apr-13 53 A51470 Fire Fighting Pipe 5 11-Jun-12 16-Jun-12 19-Dec-12 24-Dec-12 157 A51460 Hydro Static Test for Pipes 5 18-Jun-12 23-Jun-12 11-Feb-13 16-Feb-13 196 A51450 Sprinkler Fixing 5 01-Sep-12 05-Sep-12 17-Feb-13 21-Feb-13 139 A51550 Fire Alarm Devices 5 05-Sep-12 10-Sep-12 18-Feb-13 23-Feb-13 136 A51440 Installation of Fire Extingusher&Blanket 2 20-Feb-13 21-Feb-13 23-Apr-13 24-Apr-13 53 ToiletsToilets 141 11-Jun-12 28-Nov-12 01-Dec-12 25-Apr-13 124 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Hose Cabinet & Landing Valve Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Installation of Mirrors Final Coat Paint Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Hose Cabinet & Landing Valve Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of SMDBs Installation of Telephone System Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work Screed Works 1st Coat Paint Floor Tiles Work Installation of Doors Doors Ironmongery Installation of Equipments Final Coat Paint Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 25 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 26. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float FinishingFinishing Works 141 11-Jun-12 28-Nov-12 01-Dec-12 25-Apr-13 124 Wet WorWet Works 54 11-Jun-12 13-Aug-12 01-Dec-12 13-Feb-13 150 A51870 Block Works 4 11-Jun-12 14-Jun-12 01-Dec-12 05-Dec-12 142 A51730 Installation of Doors& Windows Sub-frame 2 21-Jun-12 23-Jun-12 12-Feb-13 13-Feb-13 194 A51720 Plaster Works 7 21-Jun-12 28-Jun-12 19-Dec-12 26-Dec-12 149 A52200 Wall Tiles Work 5 08-Aug-12 13-Aug-12 15-Jan-13 20-Jan-13 130 Fisrt StaFisrt Stage Finishes 22 14-Aug-12 10-Sep-12 29-Jan-13 24-Feb-13 137 A52190 Screed Works 2 14-Aug-12 15-Aug-12 29-Jan-13 30-Jan-13 136 A51790 Water Proofing for Wet Area 2 16-Aug-12 18-Aug-12 31-Jan-13 02-Feb-13 136 A52230 Installation of Suspended Ceiling Grid 4 21-Aug-12 25-Aug-12 03-Feb-13 06-Feb-13 136 A52220 Suspended Ceiling Tiles 5 26-Aug-12 30-Aug-12 07-Feb-13 12-Feb-13 136 A52210 Floor & Wall Tiles Work 4 06-Sep-12 10-Sep-12 20-Feb-13 24-Feb-13 137 Second SSecond Stage Finishes 4 20-Nov-12 24-Nov-12 03-Mar-13 14-Apr-13 118 A51810 Installation of Doors 2 20-Nov-12 21-Nov-12 03-Mar-13 04-Mar-13 85 A51880 Doors Ironmongery 2 20-Nov-12 21-Nov-12 13-Apr-13 14-Apr-13 120 A51820 Installation of Mirrors 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113 A51860 Installation of Vanity Counter 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113 A52170 Installation of Toliets Accessories 2 22-Nov-12 24-Nov-12 07-Apr-13 08-Apr-13 113 Final StaFinal Stage Finishes 4 25-Nov-12 28-Nov-12 09-Apr-13 25-Apr-13 124 A51770 Final Coat Paint 2 25-Nov-12 26-Nov-12 09-Apr-13 10-Apr-13 113 A52180 Installation of Sinages 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124 MEP WorkMEP Works 79 16-Jun-12 18-Sep-12 12-Dec-12 10-Apr-13 169 HVACHVAC 64 24-Jun-12 08-Sep-12 12-Dec-12 25-Feb-13 140 A51900 Duct Installation & Insulation 4 24-Jun-12 27-Jun-12 20-Dec-12 24-Dec-12 148 A51910 Chilled Water Pipe Installation & Insulation 4 28-Jun-12 02-Jul-12 12-Dec-12 16-Dec-12 137 A51920 Condensate Pipe Installation 4 28-Jun-12 02-Jul-12 24-Dec-12 27-Dec-12 147 A51930 FCU Installation 2 03-Jul-12 04-Jul-12 13-Jan-13 14-Jan-13 159 A51940 Air-Outlet Installation 7 01-Sep-12 08-Sep-12 18-Feb-13 25-Feb-13 140 ElectricalElectrical 68 16-Jun-12 05-Sep-12 15-Dec-12 05-Mar-13 149 A51950 Install Conduits in Wall 4 16-Jun-12 20-Jun-12 15-Dec-12 18-Dec-12 149 A51970 Wiring for Lighting & Power 4 30-Jun-12 03-Jul-12 29-Jan-13 02-Feb-13 175 A52030 Installation of Lighting Fittings 5 01-Sep-12 05-Sep-12 28-Feb-13 05-Mar-13 149 PlumbingPlumbing 79 16-Jun-12 18-Sep-12 16-Dec-12 08-Apr-13 167 A52050 Drainge Pipes in Wall 3 16-Jun-12 19-Jun-12 16-Dec-12 18-Dec-12 150 A52120 Water Pipes in Wall 3 16-Jun-12 19-Jun-12 16-Dec-12 18-Dec-12 150 A52060 H/L Drainage Pipes Installation 4 16-Jun-12 20-Jun-12 26-Jan-13 29-Jan-13 183 A52070 H/L Hot&Cold Water Pipe Installation 4 16-Jun-12 20-Jun-12 26-Jan-13 29-Jan-13 183 A52090 ElectricalWater Heater Installation 2 21-Jun-12 23-Jun-12 31-Jan-13 02-Feb-13 184 A52080 Drainage&Water Pipes Testing 3 21-Jun-12 24-Jun-12 30-Jan-13 02-Feb-13 183 A52100 Floor Drain Fixning 2 16-Aug-12 18-Aug-12 19-Feb-13 20-Feb-13 152 A52110 Installation of Sanitaryware 3 16-Sep-12 18-Sep-12 06-Apr-13 08-Apr-13 167 Fire FighFire Fighting 72 18-Jun-12 11-Sep-12 25-Dec-12 10-Apr-13 175 A52160 Fire Fighting Pipe 3 18-Jun-12 20-Jun-12 25-Dec-12 27-Dec-12 157 A52150 Hydro Static Test for Pipes 3 21-Jun-12 24-Jun-12 30-Jan-13 02-Feb-13 183 A52240 Fire Alarm Devices 4 01-Sep-12 04-Sep-12 13-Feb-13 17-Feb-13 136 A52140 Sprinkler Fixing 3 06-Sep-12 09-Sep-12 23-Feb-13 25-Feb-13 139 A52130 Installation of Fire Extingusher&Blanket 2 10-Sep-12 11-Sep-12 09-Apr-13 10-Apr-13 175 OfficeOffice 375 16-Jun-12 08-Sep-13 06-Dec-12 02-Oct-13 21 FinishingFinishing Works 375 16-Jun-12 08-Sep-13 06-Dec-12 02-Oct-13 21 Wet WorWet Works 46 16-Jun-12 08-Aug-12 06-Dec-12 16-Feb-13 156 A52400 Block Works 2 16-Jun-12 18-Jun-12 06-Dec-12 08-Dec-12 142 A52260 Installation of Doors& Windows Sub-frame 2 30-Jun-12 01-Jul-12 14-Feb-13 16-Feb-13 189 A52250 Plaster Works 3 30-Jun-12 02-Jul-12 27-Dec-12 30-Dec-12 149 A52280 Installation of Suspended Ceiling Grid 2 04-Aug-12 05-Aug-12 28-Jan-13 29-Jan-13 144 A52270 1st Coat Paint 3 06-Aug-12 08-Aug-12 30-Jan-13 02-Feb-13 144 Fisrt StaFisrt Stage Finishes 28 09-Aug-12 12-Sep-12 05-Feb-13 26-Feb-13 137 A52290 Suspended Ceiling Tiles 2 09-Aug-12 11-Aug-12 05-Feb-13 06-Feb-13 146 A52720 Screed Works 2 12-Aug-12 13-Aug-12 23-Feb-13 24-Feb-13 159 A52310 Floor Tiles Work 2 11-Sep-12 12-Sep-12 25-Feb-13 26-Feb-13 137 Second SSecond Stage Finishes 55 13-Sep-12 19-Nov-12 28-Feb-13 11-Apr-13 120 A52300 Final Coat Paint 2 13-Sep-12 15-Sep-12 03-Apr-13 04-Apr-13 167 A52340 Installation of Windows&Doors 2 18-Nov-12 19-Nov-12 28-Feb-13 02-Mar-13 85 A52410 Doors Ironmongery 2 18-Nov-12 19-Nov-12 10-Apr-13 11-Apr-13 120 Final StaFinal Stage Finishes 247 19-Nov-12 08-Sep-13 24-Apr-13 02-Oct-13 21 A52710 Installation of Sinages 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131 A52420 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 55 19-Jun-12 23-Aug-12 17-Dec-12 04-Apr-13 186 HVACHVAC 47 24-Jun-12 16-Aug-12 17-Dec-12 17-Feb-13 150 A52450 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 14-Jan-13 19-Jan-13 168 A52430 Duct Installation & Insulation 5 28-Jun-12 03-Jul-12 25-Dec-12 30-Dec-12 148 A52440 Chilled Water Pipe Installation & Insulation 5 03-Jul-12 08-Jul-12 17-Dec-12 22-Dec-12 137 A52460 FCU Installation 6 09-Jul-12 15-Jul-12 20-Jan-13 27-Jan-13 160 A52470 Air-Outlet Installation 5 12-Aug-12 16-Aug-12 12-Feb-13 17-Feb-13 150 ElectricalElectrical 53 19-Jun-12 21-Aug-12 24-Dec-12 05-Mar-13 162 A52480 Install Conduits in Wall 3 19-Jun-12 21-Jun-12 24-Dec-12 26-Dec-12 155 A52490 Install Cable Trays & Trunking 4 19-Jun-12 23-Jun-12 24-Dec-12 27-Dec-12 155 A52530 Cable Laying for Low Current System 4 24-Jun-12 27-Jun-12 26-Jan-13 29-Jan-13 177 A52540 Cable Laying for Power 4 24-Jun-12 27-Jun-12 26-Jan-13 29-Jan-13 177 A52500 Wiring for Lighting & Power 3 03-Jul-12 05-Jul-12 23-Jan-13 27-Jan-13 168 A52510 Wiring for Low Current System 3 03-Jul-12 05-Jul-12 23-Jan-13 27-Jan-13 168 A52560 Installation of Lighting Fittings 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162 Fire FighFire Fighting 55 19-Jun-12 23-Aug-12 16-Jan-13 04-Apr-13 186 A52690 Fire Fighting Pipe 5 19-Jun-12 24-Jun-12 16-Jan-13 21-Jan-13 174 A52680 Hydro Static Test for Pipes 4 25-Jun-12 28-Jun-12 22-Jan-13 27-Jan-13 174 A52670 Sprinkler Fixing 6 12-Aug-12 18-Aug-12 27-Feb-13 05-Mar-13 163 A52660 Installation of Fire Extingusher&Blanket 2 21-Aug-12 22-Aug-12 03-Apr-13 04-Apr-13 187 A52770 Fire Alarm Devices 5 16-Aug-12 23-Aug-12 07-Feb-13 12-Feb-13 142 Luggae StoLuggae Storage 128 19-Jun-12 20-Nov-12 09-Dec-12 25-Apr-13 131 FinishingFinishing Works 128 19-Jun-12 20-Nov-12 09-Dec-12 25-Apr-13 131 Wet WorWet Works 35 19-Jun-12 29-Jul-12 09-Dec-12 25-Feb-13 173 A52830 Block Works 2 19-Jun-12 20-Jun-12 09-Dec-12 10-Dec-12 142 A52780 Plaster Works 4 03-Jul-12 07-Jul-12 31-Dec-12 05-Jan-13 149 A52800 1st Coat Paint 4 10-Jul-12 14-Jul-12 09-Jan-13 13-Jan-13 150 A52790 Installation of Doors& Windows Sub-frame 2 28-Jul-12 29-Jul-12 24-Feb-13 25-Feb-13 173 Fisrt StaFisrt Stage Finishes 94 25-Jul-12 17-Nov-12 24-Feb-13 09-Apr-13 120 A52890 Epoxy Paint Works 2 25-Jul-12 26-Jul-12 24-Feb-13 25-Feb-13 175 A52820 Installation of Doors 2 14-Nov-12 17-Nov-12 26-Feb-13 27-Feb-13 85 A52840 Doors Ironmongery 2 14-Nov-12 17-Nov-12 08-Apr-13 09-Apr-13 120 Second SSecond Stage Finishes 3 28-Jul-12 30-Jul-12 31-Mar-13 02-Apr-13 203 A52810 Final Coat Paint 3 28-Jul-12 30-Jul-12 31-Mar-13 02-Apr-13 203 Final StaFinal Stage Finishes 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131 A52880 Installation of Sinages 2 19-Nov-12 20-Nov-12 24-Apr-13 25-Apr-13 131 MEP WorkMEP Works 34 21-Jun-12 30-Jul-12 23-Dec-12 02-Apr-13 203 HVACHVAC 27 24-Jun-12 24-Jul-12 23-Dec-12 03-Feb-13 158 A52930 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 17-Jan-13 22-Jan-13 171 A52910 Duct Installation & Insulation 5 04-Jul-12 09-Jul-12 31-Dec-12 06-Jan-13 148 A52920 Chilled Water Pipe Installation & Insulation 5 09-Jul-12 14-Jul-12 23-Dec-12 27-Dec-12 137 A52940 FCU Installation 3 15-Jul-12 17-Jul-12 23-Jan-13 27-Jan-13 158 A52950 Air-Outlet Installation 6 18-Jul-12 24-Jul-12 28-Jan-13 03-Feb-13 158 ElectricalElectrical 23 21-Jun-12 17-Jul-12 27-Dec-12 23-Feb-13 181 A52850 Install Conduits in Wall 3 21-Jun-12 24-Jun-12 27-Dec-12 30-Dec-12 156 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Floor & Wall Tiles Work Installation of Doors Doors Ironmongery Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation ElectricalWater Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Final Coat Paint Installation of Windows&Doors Doors Ironmongery Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works 1st Coat Paint Installation of Doors& Windows Sub-frame Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 26 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 27. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A52860 Wiring for Lighting & Power 2 08-Jul-12 09-Jul-12 07-Jan-13 08-Jan-13 150 A52870 Installation of Lighting Fittings 3 15-Jul-12 17-Jul-12 20-Feb-13 23-Feb-13 181 Fire FighFire Fighting 34 21-Jun-12 30-Jul-12 29-Dec-12 02-Apr-13 203 A52990 Fire Fighting Pipe 5 21-Jun-12 26-Jun-12 29-Dec-12 03-Jan-13 157 A52980 Hydro Static Test for Pipes 4 27-Jun-12 01-Jul-12 05-Jan-13 08-Jan-13 157 A52970 Sprinkler Fixing 4 02-Jul-12 05-Jul-12 09-Jan-13 13-Jan-13 157 A52900 Fire Alarm Devices 4 07-Jul-12 10-Jul-12 14-Jan-13 17-Jan-13 157 A52960 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 01-Apr-13 02-Apr-13 203 StaircaseStaircase 154 23-Jul-12 27-Jan-13 04-Oct-12 25-Apr-13 76 Stair 1Stair 1 126 23-Jul-12 23-Dec-12 04-Oct-12 25-Apr-13 104 A108050 Floor Screed 3 23-Jul-12 25-Jul-12 04-Oct-12 07-Oct-12 61 A108060 Install Handrails 4 24-Oct-12 30-Oct-12 21-Nov-12 25-Nov-12 21 A108070 Ceiling 1st Coat Paint 7 07-Nov-12 14-Nov-12 23-Dec-12 30-Dec-12 37 A108080 Wall 1st Coat Paint 7 17-Nov-12 24-Nov-12 31-Dec-12 08-Jan-13 37 A108090 Install Granite/Terrazo 12 25-Nov-12 09-Dec-12 19-Jan-13 02-Feb-13 45 A108100 Final Coat Paint 12 10-Dec-12 23-Dec-12 13-Apr-13 25-Apr-13 104 Stair 2Stair 2 137 26-Jul-12 09-Jan-13 08-Oct-12 25-Apr-13 90 A108110 Floor Screed 3 26-Jul-12 29-Jul-12 08-Oct-12 10-Oct-12 61 A108120 Install Handrails 4 31-Oct-12 04-Nov-12 26-Nov-12 29-Nov-12 21 A108130 Ceiling 1st Coat Paint 7 25-Nov-12 03-Dec-12 09-Jan-13 16-Jan-13 37 A108140 Wall 1st Coat Paint 7 04-Dec-12 11-Dec-12 17-Jan-13 26-Jan-13 37 A108150 Install Granite/Terrazo 12 12-Dec-12 25-Dec-12 03-Feb-13 16-Feb-13 43 A108160 Final Coat Paint 12 26-Dec-12 09-Jan-13 13-Apr-13 25-Apr-13 90 Stair 3Stair 3 148 30-Jul-12 27-Jan-13 11-Oct-12 25-Apr-13 76 A111140 Floor Screed 3 30-Jul-12 01-Aug-12 11-Oct-12 14-Oct-12 61 A111180 Install Handrails 4 05-Nov-12 08-Nov-12 01-Dec-12 05-Dec-12 21 A111150 Ceiling 1st Coat Paint 7 12-Dec-12 19-Dec-12 27-Jan-13 03-Feb-13 37 A111160 Wall 1st Coat Paint 7 20-Dec-12 27-Dec-12 04-Feb-13 11-Feb-13 37 A111170 Install Granite/Terrazo 12 29-Dec-12 12-Jan-13 17-Feb-13 02-Mar-13 41 A111190 Final Coat Paint 12 13-Jan-13 27-Jan-13 13-Apr-13 25-Apr-13 76 1st Floor1st Floor 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21 Public AreaPublic Area 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20 Garbage RGarbage Room 170 01-Aug-12 24-Feb-13 02-Sep-12 25-Apr-13 52 FinishingFinishing Works 170 01-Aug-12 24-Feb-13 02-Sep-12 25-Apr-13 52 Wet WorWet Works 149 01-Aug-12 30-Jan-13 02-Sep-12 22-Apr-13 70 A14500 Block Works 3 01-Aug-12 04-Aug-12 02-Sep-12 04-Sep-12 25 A14440 Plaster Works 3 16-Aug-12 21-Aug-12 27-Jan-13 29-Jan-13 132 A14450 Installation of Doors& Windows Sub-frame 1 01-Sep-12 01-Sep-12 22-Apr-13 22-Apr-13 194 A14480 Wall Tiles Work 4 19-Jan-13 22-Jan-13 17-Feb-13 20-Feb-13 24 A14460 1st Coat Paint 2 29-Jan-13 30-Jan-13 21-Feb-13 23-Feb-13 20 Fisrt StaFisrt Stage Finishes 15 31-Jan-13 17-Feb-13 24-Feb-13 24-Apr-13 57 A14790 Screed Works 2 31-Jan-13 02-Feb-13 24-Feb-13 25-Feb-13 20 A14810 Floor Tiles Work 2 04-Feb-13 05-Feb-13 27-Feb-13 28-Feb-13 20 A14510 Doors Ironmongery 1 16-Feb-13 16-Feb-13 24-Apr-13 24-Apr-13 58 A14490 Installation of Doors 2 16-Feb-13 17-Feb-13 23-Apr-13 24-Apr-13 57 Second SSecond Stage Finishes 2 21-Feb-13 23-Feb-13 09-Apr-13 10-Apr-13 40 A14470 Final Coat Paint 2 21-Feb-13 23-Feb-13 09-Apr-13 10-Apr-13 40 Final StaFinal Stage Finishes 1 24-Feb-13 24-Feb-13 25-Apr-13 25-Apr-13 52 A14780 Installation of Sinages 1 24-Feb-13 24-Feb-13 25-Apr-13 25-Apr-13 52 MEP WorkMEP Works 153 05-Aug-12 07-Feb-13 10-Sep-12 01-Apr-13 45 ElectricalElectrical 153 05-Aug-12 07-Feb-13 23-Jan-13 05-Mar-13 22 A14570 Install Conduits in Wall 2 05-Aug-12 06-Aug-12 23-Jan-13 26-Jan-13 140 A14590 Wiring for Lighting & Power 2 22-Aug-12 23-Aug-12 14-Feb-13 16-Feb-13 145 A14640 Installation of Lighting Fittings 2 06-Feb-13 07-Feb-13 04-Mar-13 05-Mar-13 22 PlumbingPlumbing 149 05-Aug-12 03-Feb-13 21-Jan-13 26-Feb-13 20 A14660 Drainge Pipes in Wall 2 05-Aug-12 06-Aug-12 21-Jan-13 22-Jan-13 138 A14730 Water Pipes in Wall 2 05-Aug-12 06-Aug-12 21-Jan-13 22-Jan-13 138 A14690 Drainage&Water Pipes Testing 2 14-Aug-12 15-Aug-12 23-Jan-13 26-Jan-13 132 A14710 Floor Drain Fixning 1 03-Feb-13 03-Feb-13 26-Feb-13 26-Feb-13 20 Fire FighFire Fighting 152 06-Aug-12 07-Feb-13 10-Sep-12 01-Apr-13 45 A14770 Fire Fighting Pipe 2 06-Aug-12 07-Aug-12 10-Sep-12 11-Sep-12 28 A14760 Hydro Static Test for Pipes 2 14-Aug-12 15-Aug-12 27-Feb-13 28-Feb-13 161 A14750 Sprinkler Fixing 2 06-Feb-13 07-Feb-13 02-Mar-13 03-Mar-13 20 A14800 Fire Alarm Devices 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45 Corridor &Corridor & Lift Lobby 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20 FinishingFinishing Works 205 29-Jul-12 02-Apr-13 29-Aug-12 25-Apr-13 20 Wet WorWet Works 142 29-Jul-12 17-Jan-13 29-Aug-12 11-Feb-13 20 A9810 Block Works 3 29-Jul-12 31-Jul-12 29-Aug-12 01-Sep-12 25 A9660 Plaster Works 6 04-Aug-12 09-Aug-12 15-Dec-12 20-Dec-12 108 A9690 Installation of Suspended Ceiling Grid 6 17-Sep-12 23-Sep-12 26-Dec-12 02-Jan-13 82 A9700 Suspended Ceiling Tiles 6 10-Jan-13 16-Jan-13 04-Feb-13 10-Feb-13 20 A10150 MDF for Lift Lobby Wall 7 10-Jan-13 17-Jan-13 04-Feb-13 11-Feb-13 20 Fisrt StaFisrt Stage Finishes 8 19-Jan-13 28-Jan-13 12-Feb-13 20-Feb-13 20 A10140 Screed Works 3 19-Jan-13 21-Jan-13 12-Feb-13 14-Feb-13 20 A9680 1st Coat Paint 5 22-Jan-13 28-Jan-13 16-Feb-13 20-Feb-13 20 Second SSecond Stage Finishes 2 13-Feb-13 14-Feb-13 11-Apr-13 25-Apr-13 60 A9750 Installation of Doors 2 13-Feb-13 14-Feb-13 11-Apr-13 13-Apr-13 49 A9820 Doors Ironmongery 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60 Final StaFinal Stage Finishes 11 21-Mar-13 02-Apr-13 14-Apr-13 25-Apr-13 20 A9780 Installation of Carpets 4 21-Mar-13 25-Mar-13 14-Apr-13 17-Apr-13 20 A9720 Fixing of Wall Covering 5 26-Mar-13 31-Mar-13 18-Apr-13 23-Apr-13 20 A10130 Installation of Sinages 2 01-Apr-13 02-Apr-13 24-Apr-13 25-Apr-13 20 MEP WorkMEP Works 147 01-Aug-12 28-Jan-13 05-Sep-12 05-Mar-13 31 HVACHVAC 141 01-Aug-12 20-Jan-13 17-Dec-12 20-Feb-13 26 A9860 Condensate Pipe Installation 5 01-Aug-12 06-Aug-12 17-Dec-12 22-Dec-12 112 A9840 Duct Installation & Insulation 5 12-Aug-12 16-Aug-12 17-Dec-12 22-Dec-12 103 A9850 Chilled Water Pipe Installation & Insulation 5 12-Aug-12 16-Aug-12 17-Dec-12 22-Dec-12 103 A9870 FCU Installation 3 18-Aug-12 22-Aug-12 23-Dec-12 25-Dec-12 103 A9880 Air-Outlet Installation 3 17-Jan-13 20-Jan-13 18-Feb-13 20-Feb-13 26 ElectricalElectrical 143 01-Aug-12 22-Jan-13 12-Dec-12 05-Mar-13 35 A9890 Install Conduits in Wall 2 01-Aug-12 02-Aug-12 12-Dec-12 13-Dec-12 108 A9900 Install Cable Trays & Trunking 2 01-Aug-12 02-Aug-12 17-Dec-12 18-Dec-12 112 A9940 Cable Laying for Low Current System 2 04-Aug-12 05-Aug-12 31-Dec-12 02-Jan-13 122 A9950 Cable Laying for Power 4 04-Aug-12 07-Aug-12 29-Dec-12 02-Jan-13 120 A9910 Wiring for Lighting & Power 3 11-Aug-12 13-Aug-12 23-Dec-12 25-Dec-12 109 A9920 Wiring for Low Current System 4 11-Aug-12 14-Aug-12 22-Dec-12 25-Dec-12 108 A9930 DB installation,Dressing & Termination 6 24-Sep-12 30-Sep-12 04-Feb-13 10-Feb-13 108 A9990 Installation of Sockets 3 17-Jan-13 20-Jan-13 03-Mar-13 05-Mar-13 37 A9970 Installation of Lighting Fittings 5 17-Jan-13 22-Jan-13 28-Feb-13 05-Mar-13 35 PlumbingPlumbing 5 04-Aug-12 08-Aug-12 20-Dec-12 25-Dec-12 113 A10020 H/L Hot&Cold Water Pipe Installation 5 04-Aug-12 08-Aug-12 20-Dec-12 25-Dec-12 113 Fire FighFire Fighting 147 01-Aug-12 28-Jan-13 05-Sep-12 20-Feb-13 20 A10110 Fire Fighting Pipe 4 01-Aug-12 05-Aug-12 05-Sep-12 09-Sep-12 28 A10100 Hydro Static Test for Pipes 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107 A10090 Sprinkler Fixing 5 17-Jan-13 22-Jan-13 11-Feb-13 16-Feb-13 20 A13900 Fire Alarm Devices 4 21-Jan-13 26-Jan-13 14-Feb-13 18-Feb-13 20 A10080 Installation of Fire Extingusher&Blanket 4 23-Jan-13 28-Jan-13 17-Feb-13 20-Feb-13 20 A115230 Installation of Fire Hose Cabinet & Landing Valve 6 21-Jan-13 28-Jan-13 14-Feb-13 20-Feb-13 20 Electrical /Electrical /Telephone/ELV Rooms 170 05-Aug-12 27-Feb-13 05-Sep-12 25-Apr-13 49 FinishingFinishing Works 170 05-Aug-12 27-Feb-13 05-Sep-12 25-Apr-13 49 Wet WorWet Works 22 05-Aug-12 01-Sep-12 05-Sep-12 08-Apr-13 182 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Installation of Fire Hose Cabinet & Landing Valve Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 27 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 28. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A14880 Block Works 3 05-Aug-12 07-Aug-12 05-Sep-12 08-Sep-12 25 A14820 Plaster Works 3 22-Aug-12 25-Aug-12 30-Jan-13 02-Feb-13 132 A14830 Installation of Doors& Windows Sub-frame 1 30-Aug-12 30-Aug-12 08-Apr-13 08-Apr-13 183 A14840 1st Coat Paint 3 29-Aug-12 01-Sep-12 06-Feb-13 09-Feb-13 132 Fisrt StaFisrt Stage Finishes 2 11-Feb-13 12-Feb-13 09-Apr-13 23-Apr-13 60 A14870 Installation of Doors 2 11-Feb-13 12-Feb-13 09-Apr-13 10-Apr-13 49 A14890 Doors Ironmongery 2 11-Feb-13 12-Feb-13 22-Apr-13 23-Apr-13 60 A15010 Epoxy Paint Works 2 11-Feb-13 12-Feb-13 09-Apr-13 10-Apr-13 49 Second SSecond Stage Finishes 2 24-Feb-13 25-Feb-13 11-Apr-13 13-Apr-13 40 A14850 Final Coat Paint 2 24-Feb-13 25-Feb-13 11-Apr-13 13-Apr-13 40 Final StaFinal Stage Finishes 2 26-Feb-13 27-Feb-13 24-Apr-13 25-Apr-13 49 A15000 Installation of Sinages 2 26-Feb-13 27-Feb-13 24-Apr-13 25-Apr-13 49 MEP WorkMEP Works 152 08-Aug-12 10-Feb-13 27-Jan-13 03-Apr-13 45 HVACHVAC 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33 A15050 Air-Outlet Installation 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33 ElectricalElectrical 40 08-Aug-12 25-Sep-12 27-Jan-13 05-Mar-13 132 A14900 Install Conduits in Wall 3 08-Aug-12 11-Aug-12 27-Jan-13 29-Jan-13 139 A14910 Wiring for Lighting & Power 3 26-Aug-12 28-Aug-12 03-Feb-13 05-Feb-13 132 A14930 Installation of SMDBs 7 02-Sep-12 09-Sep-12 24-Feb-13 03-Mar-13 144 A14920 Installation of Lighting Fittings 2 10-Sep-12 11-Sep-12 04-Mar-13 05-Mar-13 144 A114400 Installation of Access ControlSystem 20 02-Sep-12 24-Sep-12 11-Feb-13 05-Mar-13 133 A114390 Installation of MATC,TV System 20 02-Sep-12 24-Sep-12 11-Feb-13 05-Mar-13 133 A14940 Installation of Telephone System 21 02-Sep-12 25-Sep-12 10-Feb-13 05-Mar-13 132 Fire FighFire Fighting 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45 A15020 Fire Alarm Devices 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45 Room ServRoom Service 162 08-Aug-12 21-Feb-13 09-Sep-12 25-Apr-13 54 FinishingFinishing Works 162 08-Aug-12 21-Feb-13 09-Sep-12 25-Apr-13 54 Wet WorWet Works 22 08-Aug-12 04-Sep-12 09-Sep-12 06-Apr-13 177 A15120 Block Works 3 08-Aug-12 11-Aug-12 09-Sep-12 11-Sep-12 25 A15060 Plaster Works 3 26-Aug-12 28-Aug-12 16-Feb-13 18-Feb-13 143 A15070 Installation of Doors& Windows Sub-frame 1 29-Aug-12 29-Aug-12 06-Apr-13 06-Apr-13 182 A15080 1st Coat Paint 3 02-Sep-12 04-Sep-12 21-Feb-13 24-Feb-13 142 Fisrt StaFisrt Stage Finishes 130 05-Sep-12 10-Feb-13 25-Feb-13 24-Apr-13 63 A15250 Screed Works 2 05-Sep-12 06-Sep-12 25-Feb-13 26-Feb-13 142 A15270 Floor Tiles Work 3 05-Feb-13 07-Feb-13 28-Feb-13 03-Mar-13 20 A15110 Installation of Doors 2 09-Feb-13 10-Feb-13 07-Apr-13 08-Apr-13 49 A15130 Doors Ironmongery 2 09-Feb-13 10-Feb-13 23-Apr-13 24-Apr-13 63 Second SSecond Stage Finishes 2 19-Feb-13 20-Feb-13 07-Apr-13 08-Apr-13 40 A15090 Final Coat Paint 2 19-Feb-13 20-Feb-13 07-Apr-13 08-Apr-13 40 Final StaFinal Stage Finishes 1 21-Feb-13 21-Feb-13 25-Apr-13 25-Apr-13 54 A15240 Installation of Sinages 1 21-Feb-13 21-Feb-13 25-Apr-13 25-Apr-13 54 MEP WorkMEP Works 151 12-Aug-12 12-Feb-13 12-Sep-12 06-Apr-13 45 HVACHVAC 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33 A15280 Air-Outlet Installation 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33 ElectricalElectrical 149 12-Aug-12 10-Feb-13 13-Feb-13 05-Mar-13 20 A15140 Install Conduits in Wall 2 12-Aug-12 13-Aug-12 13-Feb-13 14-Feb-13 151 A15150 Wiring for Lighting & Power 2 29-Aug-12 30-Aug-12 19-Feb-13 20-Feb-13 143 A15160 Installation of Lighting Fittings 2 09-Feb-13 10-Feb-13 04-Mar-13 05-Mar-13 20 PlumbingPlumbing 144 12-Aug-12 04-Feb-13 22-Dec-12 27-Feb-13 20 A15170 Drainge Pipes in Wall 2 12-Aug-12 13-Aug-12 22-Dec-12 23-Dec-12 107 A15200 Water Pipes in Wall 2 12-Aug-12 13-Aug-12 22-Dec-12 23-Dec-12 107 A15180 Drainage&Water Pipes Testing 2 14-Aug-12 15-Aug-12 24-Dec-12 25-Dec-12 107 A15190 Floor Drain Fixning 1 04-Feb-13 04-Feb-13 27-Feb-13 27-Feb-13 20 Fire FighFire Fighting 151 12-Aug-12 12-Feb-13 12-Sep-12 06-Apr-13 45 A15230 Fire Fighting Pipe 2 12-Aug-12 13-Aug-12 12-Sep-12 13-Sep-12 25 A15220 Hydro Static Test for Pipes 2 14-Aug-12 15-Aug-12 15-Sep-12 16-Sep-12 25 A15210 Sprinkler Fixing 2 09-Feb-13 10-Feb-13 04-Mar-13 05-Mar-13 20 A15260 Fire Alarm Devices 2 11-Feb-13 12-Feb-13 04-Apr-13 06-Apr-13 45 StaircaseStaircase 166 11-Aug-12 28-Feb-13 15-Oct-12 13-Apr-13 37 Stair 1Stair 1 152 11-Aug-12 12-Feb-13 15-Oct-12 30-Mar-13 39 A108170 Floor Screed 3 11-Aug-12 13-Aug-12 15-Oct-12 17-Oct-12 54 A108180 Install Handrails 4 10-Nov-12 13-Nov-12 06-Dec-12 10-Dec-12 21 A108190 Ceiling 1st Coat Paint 7 29-Dec-12 06-Jan-13 12-Feb-13 19-Feb-13 37 A108200 Wall 1st Coat Paint 7 07-Jan-13 14-Jan-13 20-Feb-13 27-Feb-13 37 A108210 Install Granite/Terrazo 12 15-Jan-13 29-Jan-13 03-Mar-13 16-Mar-13 39 A108220 Final Coat Paint 12 30-Jan-13 12-Feb-13 17-Mar-13 30-Mar-13 39 Stair 2Stair 2 163 14-Aug-12 28-Feb-13 18-Oct-12 13-Apr-13 37 A108230 Floor Screed 3 14-Aug-12 16-Aug-12 18-Oct-12 21-Oct-12 54 A108240 Install Handrails 4 14-Nov-12 19-Nov-12 11-Dec-12 15-Dec-12 21 A108250 Ceiling 1st Coat Paint 7 15-Jan-13 22-Jan-13 28-Feb-13 07-Mar-13 37 A108260 Wall 1st Coat Paint 7 23-Jan-13 31-Jan-13 09-Mar-13 16-Mar-13 37 A108270 Install Granite/Terrazo 12 02-Feb-13 14-Feb-13 17-Mar-13 30-Mar-13 37 A108280 Final Coat Paint 12 16-Feb-13 28-Feb-13 31-Mar-13 13-Apr-13 37 ApartementsApartements 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21 Studio FlatsStudio Flats 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21 FinishingFinishing Works 342 25-Jul-12 08-Sep-13 26-Aug-12 02-Oct-13 21 Wet WoWet Works 62 25-Jul-12 07-Oct-12 26-Aug-12 24-Mar-13 138 A6040 Block Works 3 25-Jul-12 28-Jul-12 26-Aug-12 28-Aug-12 25 A5880 Plaster Works 7 01-Aug-12 08-Aug-12 08-Oct-12 15-Oct-12 56 A8780 Wall Tiles Work (Wet Area) 8 09-Aug-12 18-Aug-12 31-Oct-12 08-Nov-12 67 A5890 Installation of Doors& Windows Sub-frame 3 26-Aug-12 28-Aug-12 21-Mar-13 24-Mar-13 172 A5910 Installation of Suspended Ceiling Grid (Dry Area) 6 10-Sep-12 16-Sep-12 17-Oct-12 23-Oct-12 32 A5900 1st Coat Paint 6 01-Oct-12 07-Oct-12 24-Oct-12 01-Nov-12 20 Fisrt StaFisrt Stage Finishes 79 13-Oct-12 17-Jan-13 07-Nov-12 27-Feb-13 34 A5920 Suspended Ceiling Tiles (DryArea) 2 13-Oct-12 14-Oct-12 07-Nov-12 08-Nov-12 20 A5960 Installation of Wardrobes 2 12-Nov-12 13-Nov-12 22-Dec-12 23-Dec-12 32 A8770 Screed Works 5 29-Nov-12 05-Dec-12 24-Dec-12 29-Dec-12 20 A5950 Water Proofing for Wet Area 3 06-Dec-12 09-Dec-12 30-Dec-12 02-Jan-13 20 A5940 Floor & Wall Tiles Work (Dry Area) 4 06-Dec-12 10-Dec-12 22-Jan-13 27-Jan-13 39 A9110 Installation of Suspended Ceiling Grid (Wet Area) 3 10-Dec-12 12-Dec-12 03-Jan-13 06-Jan-13 20 A8990 Suspended Ceiling Tiles (Wet Area) 2 08-Jan-13 09-Jan-13 02-Feb-13 03-Feb-13 20 A8970 Floor Tiles Work (Wet Area) 2 16-Jan-13 17-Jan-13 26-Feb-13 27-Feb-13 34 SecondSecond Stage Finishes 11 20-Jan-13 02-Feb-13 25-Mar-13 25-Apr-13 71 A5970 Installation of Windows&Doors 2 20-Jan-13 21-Jan-13 25-Mar-13 26-Mar-13 54 A6050 Doors Ironmongery 2 20-Jan-13 21-Jan-13 24-Apr-13 25-Apr-13 80 A6020 Installation of Balustrades& Handrails 2 22-Jan-13 23-Jan-13 28-Mar-13 30-Mar-13 55 A5990 Installation of Mirrors 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51 A6000 Installation of Kitchen Cabinets 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51 A6030 Installation of Vanity Counter 2 28-Jan-13 29-Jan-13 28-Mar-13 30-Mar-13 51 A6960 Installation of Toliets Accessories 2 31-Jan-13 02-Feb-13 28-Mar-13 30-Mar-13 48 Final StFinal Stage Finishes 177 12-Feb-13 08-Sep-13 31-Mar-13 02-Oct-13 21 A5930 Final Coat Paint 6 12-Feb-13 18-Feb-13 31-Mar-13 06-Apr-13 40 A6010 Installation of Carpets 4 31-Mar-13 03-Apr-13 22-Apr-13 25-Apr-13 19 A6970 Installation of Sinages 7 27-Mar-13 03-Apr-13 18-Apr-13 25-Apr-13 19 A6060 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 148 29-Jul-12 26-Jan-13 02-Sep-12 06-Apr-13 60 HVACHVAC 139 29-Jul-12 14-Jan-13 07-Oct-12 17-Feb-13 28 A6090 Condensate Pipe Installation 7 29-Jul-12 05-Aug-12 07-Oct-12 14-Oct-12 58 A6070 Duct Installation & Insulation 7 04-Aug-12 11-Aug-12 07-Oct-12 14-Oct-12 53 A6080 Chilled Water Pipe Installation & Insulation 7 04-Aug-12 11-Aug-12 07-Oct-12 14-Oct-12 53 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Doors& Windows Sub-frame 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Plaster Works Installation of Doors& Windows Sub-frame 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Wall Tiles Work (Wet Area) Installation of Doors& Windows Sub-frame Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 28 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 29. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A6100 FCU Installation 2 12-Aug-12 13-Aug-12 15-Oct-12 16-Oct-12 53 A6120 Air-Outlet Installation 3 12-Jan-13 14-Jan-13 14-Feb-13 17-Feb-13 28 ElectricElectrical 139 29-Jul-12 14-Jan-13 04-Oct-12 05-Mar-13 42 A6130 Install Conduits in Wall 3 29-Jul-12 31-Jul-12 04-Oct-12 07-Oct-12 56 A6140 Install Cable Trays & Trunking 4 29-Jul-12 01-Aug-12 09-Oct-12 13-Oct-12 60 A6180 Cable Laying for Low Current System 3 02-Aug-12 05-Aug-12 21-Oct-12 23-Oct-12 66 A6190 Cable Laying for Power 3 02-Aug-12 05-Aug-12 21-Oct-12 23-Oct-12 66 A6150 Wiring for Lighting & Power 3 07-Aug-12 09-Aug-12 14-Oct-12 16-Oct-12 56 A6160 Wiring for Low Current System 3 07-Aug-12 09-Aug-12 14-Oct-12 16-Oct-12 56 A6170 DB installation,Dressing & Termination 6 08-Oct-12 14-Oct-12 03-Nov-12 08-Nov-12 20 A6230 Installation of Sockets 3 10-Jan-13 13-Jan-13 03-Mar-13 05-Mar-13 43 A6210 Installation of Lighting Fittings 4 10-Jan-13 14-Jan-13 02-Mar-13 05-Mar-13 42 PlumbinPlumbing 148 29-Jul-12 26-Jan-13 04-Oct-12 30-Mar-13 54 A6240 Drainge Pipes in Wall 4 29-Jul-12 01-Aug-12 04-Oct-12 08-Oct-12 56 A6310 Water Pipes in Wall 4 29-Jul-12 01-Aug-12 04-Oct-12 08-Oct-12 56 A6250 H/L Drainage Pipes Installation 4 30-Jul-12 02-Aug-12 24-Dec-12 27-Dec-12 120 A6260 H/L Hot&Cold Water Pipe Installation 4 30-Jul-12 02-Aug-12 16-Dec-12 19-Dec-12 113 A6270 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 29-Dec-12 02-Jan-13 113 A6280 ElectricalWater Heater Installation 2 23-Aug-12 25-Aug-12 31-Dec-12 02-Jan-13 107 A6290 Floor Drain Fixning 2 03-Dec-12 04-Dec-12 23-Feb-13 24-Feb-13 68 A6300 Installation of Sanitaryware 3 22-Jan-13 26-Jan-13 27-Mar-13 30-Mar-13 54 Fire FigFire Fighting 141 29-Jul-12 16-Jan-13 02-Sep-12 06-Apr-13 67 A6360 Fire Fighting Pipe 3 29-Jul-12 31-Jul-12 02-Sep-12 04-Sep-12 28 A6350 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 14-Oct-12 16-Oct-12 51 A12830 Fire Alarm Devices 3 10-Jan-13 13-Jan-13 04-Feb-13 06-Feb-13 20 A6340 Sprinkler Fixing 3 12-Jan-13 14-Jan-13 07-Feb-13 10-Feb-13 22 A6330 Installation of Fire Extingusher&Blanket 2 15-Jan-13 16-Jan-13 04-Apr-13 06-Apr-13 67 One BedroOne Bedroom Flats 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 (1 BR) 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21 FinishingFinishing Works 348 18-Jul-12 08-Sep-13 16-Aug-12 02-Oct-13 21 Wet WoWet Works 62 18-Jul-12 30-Sep-12 16-Aug-12 12-Mar-13 134 A22080 Block Works 6 18-Jul-12 24-Jul-12 16-Aug-12 25-Aug-12 25 A21940 Installation of Doors& Windows Sub-frame 4 21-Aug-12 25-Aug-12 09-Mar-13 12-Mar-13 165 A21930 Plaster Works 9 21-Aug-12 30-Aug-12 24-Sep-12 03-Oct-12 29 A22410 Wall Tiles Work (Wet Area) 6 01-Sep-12 06-Sep-12 10-Nov-12 17-Nov-12 58 A21960 Installation of Suspended Ceiling Grid (Dry Area) 5 04-Sep-12 09-Sep-12 08-Oct-12 13-Oct-12 29 A21950 1st Coat Paint 9 20-Sep-12 30-Sep-12 14-Oct-12 23-Oct-12 20 Fisrt StaFisrt Stage Finishes 75 15-Oct-12 15-Jan-13 10-Nov-12 25-Feb-13 34 A21970 Suspended Ceiling Tiles (DryArea) 3 15-Oct-12 17-Oct-12 10-Nov-12 12-Nov-12 20 A22010 Installation of Wardrobes 5 06-Nov-12 11-Nov-12 05-Dec-12 10-Dec-12 23 A22400 Screed Works 11 17-Nov-12 28-Nov-12 11-Dec-12 23-Dec-12 20 A22000 Water Proofing for Wet Area 4 29-Nov-12 04-Dec-12 25-Dec-12 29-Dec-12 21 A21990 Floor & Wall Tiles Work (Dry Area) 4 11-Dec-12 15-Dec-12 28-Jan-13 31-Jan-13 39 A22440 Installation of Suspended Ceiling Grid (Wet Area) 5 13-Dec-12 18-Dec-12 07-Jan-13 12-Jan-13 20 A22430 Suspended Ceiling Tiles (Wet Area) 5 02-Jan-13 07-Jan-13 27-Jan-13 31-Jan-13 20 A22420 Floor Tiles Work (Wet Area) 7 08-Jan-13 15-Jan-13 18-Feb-13 25-Feb-13 34 SecondSecond Stage Finishes 12 16-Jan-13 30-Jan-13 13-Mar-13 21-Mar-13 43 A22020 Installation of Windows&Doors 3 16-Jan-13 19-Jan-13 13-Mar-13 16-Mar-13 47 A22090 Doors Ironmongery 3 16-Jan-13 19-Jan-13 19-Mar-13 21-Mar-13 52 A22060 Installation of Balustrades& Handrails 2 20-Jan-13 21-Jan-13 20-Mar-13 21-Mar-13 50 A22030 Installation of Mirrors 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46 A22040 Installation of Kitchen Cabinets 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46 A22070 Installation of Vanity Counter 4 22-Jan-13 27-Jan-13 18-Mar-13 21-Mar-13 46 A22380 Installation of Toliets Accessories 5 26-Jan-13 30-Jan-13 17-Mar-13 21-Mar-13 43 Final StFinal Stage Finishes 184 04-Feb-13 08-Sep-13 23-Mar-13 02-Oct-13 21 A21980 Final Coat Paint 7 04-Feb-13 11-Feb-13 23-Mar-13 30-Mar-13 40 A22050 Installation of Carpets 4 26-Mar-13 30-Mar-13 17-Apr-13 21-Apr-13 19 A22390 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23 A22100 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 149 25-Jul-12 22-Jan-13 29-Aug-12 30-Mar-13 56 HVACHVAC 139 25-Jul-12 10-Jan-13 27-Sep-12 13-Feb-13 28 A22130 Condensate Pipe Installation 7 25-Jul-12 01-Aug-12 27-Sep-12 04-Oct-12 53 A22110 Duct Installation & Insulation 7 26-Jul-12 02-Aug-12 27-Sep-12 04-Oct-12 52 A22120 Chilled Water Pipe Installation & Insulation 7 26-Jul-12 02-Aug-12 27-Sep-12 04-Oct-12 52 A22140 FCU Installation 2 04-Aug-12 05-Aug-12 06-Oct-12 07-Oct-12 52 A22150 Air-Outlet Installation 3 08-Jan-13 10-Jan-13 11-Feb-13 13-Feb-13 28 ElectricElectrical 140 25-Jul-12 12-Jan-13 20-Sep-12 05-Mar-13 44 A22160 Install Conduits in Wall 3 25-Jul-12 28-Jul-12 20-Sep-12 23-Sep-12 47 A22170 Install Cable Trays & Trunking 4 25-Jul-12 29-Jul-12 27-Sep-12 01-Oct-12 53 A22210 Cable Laying for Low Current System 3 30-Jul-12 01-Aug-12 10-Oct-12 13-Oct-12 60 A22220 Cable Laying for Power 3 30-Jul-12 01-Aug-12 10-Oct-12 13-Oct-12 60 A22180 Wiring for Lighting & Power 3 01-Sep-12 03-Sep-12 04-Oct-12 07-Oct-12 29 A22190 Wiring for Low Current System 3 01-Sep-12 03-Sep-12 04-Oct-12 07-Oct-12 29 A22200 DB installation,Dressing & Termination 6 01-Oct-12 07-Oct-12 06-Nov-12 12-Nov-12 29 A22250 Installation of Sockets 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45 A22240 Installation of Lighting Fittings 4 08-Jan-13 12-Jan-13 02-Mar-13 05-Mar-13 44 PlumbinPlumbing 149 25-Jul-12 22-Jan-13 15-Sep-12 21-Mar-13 49 A22270 H/L Drainage Pipes Installation 4 25-Jul-12 29-Jul-12 19-Dec-12 23-Dec-12 120 A22280 H/L Hot&Cold Water Pipe Installation 4 25-Jul-12 29-Jul-12 11-Dec-12 15-Dec-12 113 A22260 Drainge Pipes in Wall 8 25-Jul-12 02-Aug-12 15-Sep-12 23-Sep-12 42 A22330 Water Pipes in Wall 8 25-Jul-12 02-Aug-12 15-Sep-12 23-Sep-12 42 A22290 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 26-Dec-12 30-Dec-12 111 A22300 ElectricalWater Heater Installation 4 16-Aug-12 22-Aug-12 26-Dec-12 30-Dec-12 107 A22310 Floor Drain Fixning 2 19-Nov-12 20-Nov-12 20-Feb-13 21-Feb-13 77 A22320 Installation of Sanitaryware 3 20-Jan-13 22-Jan-13 19-Mar-13 21-Mar-13 49 Fire FigFire Fighting 144 25-Jul-12 16-Jan-13 29-Aug-12 30-Mar-13 61 A22370 Fire Fighting Pipe 3 25-Jul-12 28-Jul-12 29-Aug-12 01-Sep-12 28 A22360 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 04-Oct-12 07-Oct-12 43 A22350 Sprinkler Fixing 3 08-Jan-13 10-Jan-13 04-Feb-13 06-Feb-13 22 A22340 Installation of Fire Extingusher&Blanket 2 12-Jan-13 13-Jan-13 28-Mar-13 30-Mar-13 64 A22450 Fire Alarm Devices 3 14-Jan-13 16-Jan-13 07-Feb-13 10-Feb-13 20 Two BedroTwo Bedroom Flats 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 (2 BR) 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21 FinishingFinishing Works 360 04-Jul-12 08-Sep-13 28-Jul-12 02-Oct-13 21 Wet WoWet Works 65 04-Jul-12 19-Sep-12 28-Jul-12 23-Feb-13 128 A24730 Block Works 12 04-Jul-12 17-Jul-12 28-Jul-12 09-Aug-12 20 A24590 Installation of Doors& Windows Sub-frame 6 30-Jul-12 05-Aug-12 17-Feb-13 23-Feb-13 165 A24580 Plaster Works 17 30-Jul-12 18-Aug-12 25-Aug-12 12-Sep-12 20 A24610 Installation of Suspended Ceiling Grid (Dry Area) 7 25-Aug-12 01-Sep-12 17-Sep-12 24-Sep-12 20 A24600 1st Coat Paint 16 02-Sep-12 19-Sep-12 25-Sep-12 13-Oct-12 20 A25060 Wall Tiles Work (Wet Area) 11 08-Sep-12 19-Sep-12 18-Nov-12 29-Nov-12 58 Fisrt StaFisrt Stage Finishes 64 18-Oct-12 06-Jan-13 13-Nov-12 17-Feb-13 35 A24620 Suspended Ceiling Tiles (DryArea) 7 18-Oct-12 28-Oct-12 13-Nov-12 21-Nov-12 20 A24660 Installation of Wardrobes 7 29-Oct-12 05-Nov-12 22-Nov-12 29-Nov-12 20 A25050 Screed Works 8 06-Nov-12 14-Nov-12 01-Dec-12 10-Dec-12 20 A24650 Water Proofing for Wet Area 8 17-Nov-12 25-Nov-12 16-Dec-12 24-Dec-12 24 A25090 Installation of Suspended Ceiling Grid (Wet Area) 6 19-Dec-12 25-Dec-12 13-Jan-13 19-Jan-13 20 A24640 Floor & Wall Tiles Work (Dry Area) 10 16-Dec-12 26-Dec-12 02-Feb-13 12-Feb-13 39 A25080 Suspended Ceiling Tiles (Wet Area) 5 26-Dec-12 31-Dec-12 20-Jan-13 26-Jan-13 20 A25070 Floor Tiles Work (Wet Area) 4 02-Jan-13 06-Jan-13 13-Feb-13 17-Feb-13 35 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Wall Tiles Work (Wet Area) Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 29 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 30. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float SecondSecond Stage Finishes 15 07-Jan-13 23-Jan-13 24-Feb-13 12-Mar-13 40 A24670 Installation of Windows&Doors 5 07-Jan-13 12-Jan-13 24-Feb-13 28-Feb-13 40 A24740 Doors Ironmongery 5 07-Jan-13 12-Jan-13 07-Mar-13 12-Mar-13 50 A24710 Installation of Balustrades& Handrails 5 13-Jan-13 17-Jan-13 07-Mar-13 12-Mar-13 45 A24680 Installation of Mirrors 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42 A24690 Installation of Kitchen Cabinets 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42 A24720 Installation of Vanity Counter 8 13-Jan-13 21-Jan-13 04-Mar-13 12-Mar-13 42 A25030 Installation of Toliets Accessories 10 13-Jan-13 23-Jan-13 02-Mar-13 12-Mar-13 40 Final StFinal Stage Finishes 192 26-Jan-13 08-Sep-13 13-Mar-13 02-Oct-13 21 A24630 Final Coat Paint 8 26-Jan-13 03-Feb-13 13-Mar-13 21-Mar-13 40 A24700 Installation of Carpets 4 21-Mar-13 25-Mar-13 13-Apr-13 16-Apr-13 19 A25040 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A24750 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 153 18-Jul-12 20-Jan-13 11-Aug-12 21-Mar-13 51 HVACHVAC 140 18-Jul-12 05-Jan-13 06-Sep-12 10-Feb-13 30 A24760 Duct Installation & Insulation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41 A24770 Chilled Water Pipe Installation & Insulation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41 A24780 Condensate Pipe Installation 7 18-Jul-12 25-Jul-12 06-Sep-12 13-Sep-12 41 A24790 FCU Installation 2 26-Jul-12 28-Jul-12 15-Sep-12 16-Sep-12 41 A24800 Air-Outlet Installation 3 02-Jan-13 05-Jan-13 07-Feb-13 10-Feb-13 30 ElectricElectrical 141 18-Jul-12 06-Jan-13 21-Aug-12 05-Mar-13 49 A24810 Install Conduits in Wall 3 18-Jul-12 21-Jul-12 21-Aug-12 23-Aug-12 27 A24820 Install Cable Trays & Trunking 4 18-Jul-12 22-Jul-12 06-Sep-12 10-Sep-12 41 A24860 Cable Laying for Low Current System 3 23-Jul-12 25-Jul-12 22-Sep-12 24-Sep-12 50 A24870 Cable Laying for Power 3 23-Jul-12 25-Jul-12 22-Sep-12 24-Sep-12 50 A24830 Wiring for Lighting & Power 3 21-Aug-12 23-Aug-12 13-Sep-12 16-Sep-12 20 A24840 Wiring for Low Current System 3 21-Aug-12 23-Aug-12 13-Sep-12 16-Sep-12 20 A24850 DB installation,Dressing & Termination 6 20-Sep-12 26-Sep-12 14-Nov-12 21-Nov-12 45 A24900 Installation of Sockets 3 02-Jan-13 05-Jan-13 03-Mar-13 05-Mar-13 50 A24890 Installation of Lighting Fittings 4 02-Jan-13 06-Jan-13 02-Mar-13 05-Mar-13 49 PlumbinPlumbing 149 18-Jul-12 15-Jan-13 11-Aug-12 12-Mar-13 47 A24920 H/L Drainage Pipes Installation 4 18-Jul-12 22-Jul-12 15-Dec-12 18-Dec-12 122 A24930 H/L Hot&Cold Water Pipe Installation 4 18-Jul-12 22-Jul-12 06-Dec-12 10-Dec-12 115 A24980 Water Pipes in Wall 8 18-Jul-12 26-Jul-12 13-Aug-12 23-Aug-12 22 A24910 Drainge Pipes in Wall 10 18-Jul-12 29-Jul-12 11-Aug-12 23-Aug-12 20 A24940 Drainage&Water Pipes Testing 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107 A24950 ElectricalWater Heater Installation 4 12-Aug-12 15-Aug-12 22-Dec-12 25-Dec-12 107 A24960 Floor Drain Fixning 2 08-Nov-12 10-Nov-12 12-Feb-13 13-Feb-13 78 A24970 Installation of Sanitaryware 3 13-Jan-13 15-Jan-13 10-Mar-13 12-Mar-13 47 Fire FigFire Fighting 153 18-Jul-12 20-Jan-13 26-Aug-12 21-Mar-13 51 A25020 Fire Fighting Pipe 3 18-Jul-12 21-Jul-12 26-Aug-12 28-Aug-12 31 A25010 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 13-Sep-12 16-Sep-12 25 A25000 Sprinkler Fixing 3 02-Jan-13 05-Jan-13 31-Jan-13 03-Feb-13 24 A24990 Installation of Fire Extingusher&Blanket 2 06-Jan-13 07-Jan-13 20-Mar-13 21-Mar-13 62 A25100 Fire Alarm Devices 3 17-Jan-13 20-Jan-13 11-Feb-13 13-Feb-13 20 2nd Floor2nd Floor 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21 Public AreaPublic Area 196 25-Aug-12 16-Apr-13 22-Oct-12 25-Apr-13 8 Garbage RGarbage Room 125 03-Sep-12 02-Feb-13 17-Dec-12 25-Apr-13 71 FinishingFinishing Works 125 03-Sep-12 02-Feb-13 17-Dec-12 25-Apr-13 71 Wet WorWet Works 115 03-Sep-12 20-Jan-13 17-Dec-12 07-Feb-13 15 A15690 Block Works 3 03-Sep-12 05-Sep-12 17-Dec-12 19-Dec-12 86 A15640 Installation of Doors& Windows Sub-frame 1 10-Oct-12 10-Oct-12 07-Feb-13 07-Feb-13 97 A15630 Plaster Works 3 10-Oct-12 13-Oct-12 21-Jan-13 23-Jan-13 83 A15670 Wall Tiles Work 4 16-Oct-12 20-Oct-12 28-Jan-13 31-Jan-13 83 A15650 1st Coat Paint 2 19-Jan-13 20-Jan-13 02-Feb-13 03-Feb-13 11 Fisrt StaFisrt Stage Finishes 7 21-Jan-13 29-Jan-13 09-Feb-13 24-Apr-13 73 A15820 Screed Works 2 21-Jan-13 22-Jan-13 09-Feb-13 10-Feb-13 15 A15840 Floor Tiles Work 2 26-Jan-13 27-Jan-13 02-Mar-13 03-Mar-13 30 A15700 Doors Ironmongery 1 28-Jan-13 28-Jan-13 24-Apr-13 24-Apr-13 74 A15680 Installation of Doors 2 28-Jan-13 29-Jan-13 23-Apr-13 24-Apr-13 73 Second SSecond Stage Finishes 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52 A15660 Final Coat Paint 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52 Final StaFinal Stage Finishes 1 02-Feb-13 02-Feb-13 25-Apr-13 25-Apr-13 71 A15810 Installation of Sinages 1 02-Feb-13 02-Feb-13 25-Apr-13 25-Apr-13 71 MEP WorkMEP Works 119 06-Sep-12 29-Jan-13 20-Dec-12 31-Mar-13 52 ElectricalElectrical 119 06-Sep-12 29-Jan-13 19-Jan-13 05-Mar-13 30 A15710 Install Conduits in Wall 2 06-Sep-12 08-Sep-12 19-Jan-13 20-Jan-13 110 A15720 Wiring for Lighting & Power 2 14-Oct-12 15-Oct-12 26-Jan-13 27-Jan-13 83 A15730 Installation of Lighting Fittings 2 28-Jan-13 29-Jan-13 04-Mar-13 05-Mar-13 30 PlumbingPlumbing 115 06-Sep-12 23-Jan-13 16-Jan-13 28-Feb-13 30 A15740 Drainge Pipes in Wall 2 06-Sep-12 08-Sep-12 16-Jan-13 17-Jan-13 108 A15770 Water Pipes in Wall 2 06-Sep-12 08-Sep-12 16-Jan-13 17-Jan-13 108 A15750 Drainage&Water Pipes Testing 2 09-Sep-12 10-Sep-12 19-Jan-13 20-Jan-13 108 A15760 Floor Drain Fixning 1 23-Jan-13 23-Jan-13 28-Feb-13 28-Feb-13 30 Fire FighFire Fighting 119 06-Sep-12 29-Jan-13 20-Dec-12 31-Mar-13 52 A15800 Fire Fighting Pipe 2 06-Sep-12 08-Sep-12 20-Dec-12 22-Dec-12 86 A15790 Hydro Static Test for Pipes 2 09-Sep-12 10-Sep-12 02-Mar-13 03-Mar-13 143 A15780 Sprinkler Fixing 2 28-Jan-13 29-Jan-13 04-Mar-13 05-Mar-13 30 A15830 Fire Alarm Devices 2 28-Jan-13 29-Jan-13 30-Mar-13 31-Mar-13 52 Corridor &Corridor & Lift Lobby 196 25-Aug-12 16-Apr-13 08-Dec-12 25-Apr-13 8 FinishingFinishing Works 196 25-Aug-12 16-Apr-13 08-Dec-12 25-Apr-13 8 Wet WorWet Works 57 25-Aug-12 31-Oct-12 08-Dec-12 21-Jan-13 67 A15350 Block Works 8 25-Aug-12 02-Sep-12 08-Dec-12 16-Dec-12 86 A15290 Plaster Works 7 02-Oct-12 09-Oct-12 19-Dec-12 26-Dec-12 63 A15310 Installation of Suspended Ceiling Grid 6 15-Oct-12 21-Oct-12 02-Jan-13 08-Jan-13 63 A15320 Suspended Ceiling Tiles 6 22-Oct-12 30-Oct-12 09-Jan-13 15-Jan-13 63 A15610 MDF for Lift Lobby Wall 7 22-Oct-12 31-Oct-12 14-Jan-13 21-Jan-13 67 Fisrt StaFisrt Stage Finishes 8 09-Jan-13 17-Jan-13 22-Jan-13 31-Jan-13 11 A15590 Screed Works 3 09-Jan-13 12-Jan-13 22-Jan-13 26-Jan-13 11 A15300 1st Coat Paint 5 13-Jan-13 17-Jan-13 27-Jan-13 31-Jan-13 11 Second SSecond Stage Finishes 2 19-Jan-13 20-Jan-13 13-Feb-13 25-Apr-13 81 A15330 Installation of Doors 2 19-Jan-13 20-Jan-13 13-Feb-13 14-Feb-13 21 A15360 Doors Ironmongery 2 19-Jan-13 20-Jan-13 24-Apr-13 25-Apr-13 81 Final StaFinal Stage Finishes 20 25-Mar-13 16-Apr-13 03-Apr-13 25-Apr-13 8 A15340 Installation of Carpets 4 25-Mar-13 28-Mar-13 03-Apr-13 07-Apr-13 8 A15600 Fixing of Wall Covering 7 30-Mar-13 06-Apr-13 08-Apr-13 15-Apr-13 8 A15580 Installation of Sinages 9 07-Apr-13 16-Apr-13 16-Apr-13 25-Apr-13 8 MEP WorkMEP Works 56 03-Sep-12 08-Nov-12 17-Dec-12 05-Mar-13 96 HVACHVAC 51 03-Sep-12 03-Nov-12 23-Dec-12 26-Jan-13 68 A15370 Duct Installation & Insulation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91 A15380 Chilled Water Pipe Installation & Insulation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91 A15390 Condensate Pipe Installation 5 03-Sep-12 08-Sep-12 23-Dec-12 27-Dec-12 91 A15400 FCU Installation 3 09-Sep-12 11-Sep-12 29-Dec-12 31-Dec-12 91 A15410 Air-Outlet Installation 3 31-Oct-12 03-Nov-12 22-Jan-13 26-Jan-13 68 ElectricalElectrical 53 03-Sep-12 05-Nov-12 17-Dec-12 05-Mar-13 99 A15420 Install Conduits in Wall 2 03-Sep-12 04-Sep-12 17-Dec-12 18-Dec-12 86 A15430 Install Cable Trays & Trunking 2 03-Sep-12 04-Sep-12 23-Dec-12 24-Dec-12 91 A15470 Cable Laying for Low Current System 2 05-Sep-12 06-Sep-12 07-Jan-13 08-Jan-13 101 A15480 Cable Laying for Power 3 05-Sep-12 08-Sep-12 06-Jan-13 08-Jan-13 100 A15440 Wiring for Lighting & Power 3 10-Oct-12 13-Oct-12 29-Dec-12 31-Dec-12 64 A15450 Wiring for Low Current System 4 10-Oct-12 14-Oct-12 27-Dec-12 31-Dec-12 63 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 30 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 31. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A15460 DB installation,Dressing & Termination 6 22-Oct-12 30-Oct-12 09-Jan-13 15-Jan-13 63 A15500 Installation of Lighting Fittings 3 31-Oct-12 03-Nov-12 03-Mar-13 05-Mar-13 101 A15510 Installation of Sockets 5 31-Oct-12 05-Nov-12 28-Feb-13 05-Mar-13 99 PlumbingPlumbing 5 03-Sep-12 08-Sep-12 26-Dec-12 31-Dec-12 94 A15520 H/L Hot&Cold Water Pipe Installation 5 03-Sep-12 08-Sep-12 26-Dec-12 31-Dec-12 94 Fire FighFire Fighting 51 09-Sep-12 08-Nov-12 23-Dec-12 26-Jan-13 63 A15570 Fire Fighting Pipe 4 09-Sep-12 12-Sep-12 23-Dec-12 26-Dec-12 86 A15560 Hydro Static Test for Pipes 4 13-Sep-12 17-Sep-12 27-Dec-12 31-Dec-12 86 A15550 Sprinkler Fixing 4 31-Oct-12 04-Nov-12 16-Jan-13 20-Jan-13 63 A15620 Fire Alarm Devices 5 31-Oct-12 05-Nov-12 20-Jan-13 26-Jan-13 66 A15540 Installation of Fire Extingusher&Blanket 4 05-Nov-12 08-Nov-12 21-Jan-13 26-Jan-13 63 Electrical /Electrical /Telephone/ELV Rooms 142 06-Sep-12 25-Feb-13 20-Jan-13 25-Apr-13 51 FinishingFinishing Works 142 06-Sep-12 25-Feb-13 20-Jan-13 25-Apr-13 51 Wet WorWet Works 115 06-Sep-12 23-Jan-13 20-Jan-13 09-Feb-13 13 A15900 Block Works 3 06-Sep-12 09-Sep-12 20-Jan-13 22-Jan-13 111 A15860 Installation of Doors& Windows Sub-frame 1 11-Oct-12 11-Oct-12 09-Feb-13 09-Feb-13 97 A15850 Plaster Works 4 10-Oct-12 14-Oct-12 27-Jan-13 30-Jan-13 87 A15870 1st Coat Paint 3 21-Jan-13 23-Jan-13 04-Feb-13 06-Feb-13 11 Fisrt StaFisrt Stage Finishes 26 21-Jan-13 20-Feb-13 16-Feb-13 23-Apr-13 53 A15890 Installation of Doors 2 21-Jan-13 22-Jan-13 16-Feb-13 17-Feb-13 21 A15910 Doors Ironmongery 2 21-Jan-13 22-Jan-13 22-Apr-13 23-Apr-13 77 A15960 Epoxy Paint Works 2 19-Feb-13 20-Feb-13 30-Mar-13 31-Mar-13 33 Second SSecond Stage Finishes 2 21-Feb-13 23-Feb-13 01-Apr-13 02-Apr-13 33 A15880 Final Coat Paint 2 21-Feb-13 23-Feb-13 01-Apr-13 02-Apr-13 33 Final StaFinal Stage Finishes 2 24-Feb-13 25-Feb-13 24-Apr-13 25-Apr-13 51 A15950 Installation of Sinages 2 24-Feb-13 25-Feb-13 24-Apr-13 25-Apr-13 51 MEP WorkMEP Works 133 10-Sep-12 18-Feb-13 23-Jan-13 28-Mar-13 33 HVACHVAC 2 26-Jan-13 27-Jan-13 04-Mar-13 05-Mar-13 32 A15990 Air-Outlet Installation 2 26-Jan-13 27-Jan-13 04-Mar-13 05-Mar-13 32 ElectricalElectrical 133 10-Sep-12 18-Feb-13 23-Jan-13 05-Mar-13 13 A15920 Install Conduits in Wall 2 10-Sep-12 11-Sep-12 23-Jan-13 26-Jan-13 111 A15930 Wiring for Lighting & Power 2 15-Oct-12 16-Oct-12 02-Feb-13 03-Feb-13 88 A15980 Installation of SMDBs 7 26-Jan-13 02-Feb-13 24-Feb-13 03-Mar-13 25 A15940 Installation of Lighting Fittings 2 03-Feb-13 04-Feb-13 04-Mar-13 05-Mar-13 25 A114430 Installation of Access ControlSystem 20 26-Jan-13 17-Feb-13 11-Feb-13 05-Mar-13 14 A114410 Installation of MATC,TV System 20 26-Jan-13 17-Feb-13 11-Feb-13 05-Mar-13 14 A114420 Installation of Telephone System 21 26-Jan-13 18-Feb-13 10-Feb-13 05-Mar-13 13 Fire FighFire Fighting 5 05-Feb-13 10-Feb-13 24-Mar-13 28-Mar-13 40 A15970 Fire Alarm Devices 5 05-Feb-13 10-Feb-13 24-Mar-13 28-Mar-13 40 Room ServRoom Service 130 10-Sep-12 14-Feb-13 23-Jan-13 25-Apr-13 60 FinishingFinishing Works 130 10-Sep-12 14-Feb-13 23-Jan-13 25-Apr-13 60 Wet WorWet Works 115 10-Sep-12 28-Jan-13 23-Jan-13 11-Feb-13 12 A16050 Block Works 2 10-Sep-12 11-Sep-12 23-Jan-13 26-Jan-13 111 A16010 Installation of Doors& Windows Sub-frame 2 15-Oct-12 16-Oct-12 10-Feb-13 11-Feb-13 95 A16000 Plaster Works 4 15-Oct-12 18-Oct-12 31-Jan-13 04-Feb-13 87 A16020 1st Coat Paint 3 26-Jan-13 28-Jan-13 07-Feb-13 10-Feb-13 11 Fisrt StaFisrt Stage Finishes 8 29-Jan-13 06-Feb-13 11-Feb-13 23-Apr-13 65 A16180 Screed Works 2 29-Jan-13 30-Jan-13 11-Feb-13 12-Feb-13 11 A16200 Floor Tiles Work 3 02-Feb-13 04-Feb-13 14-Feb-13 17-Feb-13 11 A16040 Installation of Doors 2 05-Feb-13 06-Feb-13 18-Feb-13 19-Feb-13 11 A16060 Doors Ironmongery 2 05-Feb-13 06-Feb-13 22-Apr-13 23-Apr-13 65 Second SSecond Stage Finishes 5 07-Feb-13 12-Feb-13 28-Mar-13 02-Apr-13 42 A16030 Final Coat Paint 5 07-Feb-13 12-Feb-13 28-Mar-13 02-Apr-13 42 Final StaFinal Stage Finishes 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60 A16170 Installation of Sinages 2 13-Feb-13 14-Feb-13 24-Apr-13 25-Apr-13 60 MEP WorkMEP Works 121 12-Sep-12 06-Feb-13 27-Jan-13 27-Mar-13 42 HVACHVAC 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23 A16210 Air-Outlet Installation 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23 ElectricalElectrical 121 12-Sep-12 06-Feb-13 29-Jan-13 05-Mar-13 23 A16070 Install Conduits in Wall 2 12-Sep-12 13-Sep-12 29-Jan-13 30-Jan-13 113 A16080 Wiring for Lighting & Power 2 20-Oct-12 21-Oct-12 05-Feb-13 06-Feb-13 87 A16090 Installation of Lighting Fittings 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23 PlumbingPlumbing 116 12-Sep-12 31-Jan-13 27-Jan-13 13-Feb-13 11 A16100 Drainge Pipes in Wall 2 12-Sep-12 13-Sep-12 27-Jan-13 28-Jan-13 111 A16130 Water Pipes in Wall 2 12-Sep-12 13-Sep-12 27-Jan-13 28-Jan-13 111 A16110 Drainage&Water Pipes Testing 2 15-Sep-12 16-Sep-12 29-Jan-13 30-Jan-13 111 A16120 Floor Drain Fixning 1 31-Jan-13 31-Jan-13 13-Feb-13 13-Feb-13 11 Fire FighFire Fighting 120 13-Sep-12 06-Feb-13 27-Feb-13 27-Mar-13 42 A16160 Fire Fighting Pipe 2 13-Sep-12 15-Sep-12 27-Feb-13 28-Feb-13 137 A16150 Hydro Static Test for Pipes 2 16-Sep-12 17-Sep-12 02-Mar-13 03-Mar-13 137 A16140 Sprinkler Fixing 2 05-Feb-13 06-Feb-13 04-Mar-13 05-Mar-13 23 A16190 Fire Alarm Devices 2 05-Feb-13 06-Feb-13 26-Mar-13 27-Mar-13 42 StaircaseStaircase 126 27-Aug-12 27-Jan-13 22-Oct-12 02-Apr-13 56 Stair 1Stair 1 112 27-Aug-12 09-Jan-13 22-Oct-12 19-Mar-13 58 A108290 Floor Screed 3 27-Aug-12 29-Aug-12 22-Oct-12 24-Oct-12 48 A108300 Install Handrails 4 20-Nov-12 24-Nov-12 16-Dec-12 19-Dec-12 21 A108310 Ceiling 1st Coat Paint 7 25-Nov-12 03-Dec-12 12-Jan-13 19-Jan-13 39 A108320 Wall 1st Coat Paint 7 04-Dec-12 11-Dec-12 20-Jan-13 28-Jan-13 39 A108330 Install Granite/Terrazo 12 12-Dec-12 25-Dec-12 20-Feb-13 05-Mar-13 58 A108340 Final Coat Paint 12 26-Dec-12 09-Jan-13 06-Mar-13 19-Mar-13 58 Stair 2Stair 2 123 30-Aug-12 27-Jan-13 28-Oct-12 02-Apr-13 56 A108350 Floor Screed 3 30-Aug-12 02-Sep-12 28-Oct-12 30-Oct-12 48 A108360 Install Handrails 4 25-Nov-12 28-Nov-12 20-Dec-12 24-Dec-12 21 A108380 Wall 1st Coat Paint 7 12-Dec-12 19-Dec-12 29-Jan-13 05-Feb-13 39 A108370 Ceiling 1st Coat Paint 7 20-Dec-12 27-Dec-12 06-Feb-13 13-Feb-13 39 A108390 Install Granite/Terrazo 12 29-Dec-12 12-Jan-13 06-Mar-13 19-Mar-13 56 A108400 Final Coat Paint 12 13-Jan-13 27-Jan-13 20-Mar-13 02-Apr-13 56 ApartementsApartements 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21 Studio FlatsStudio Flats 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 14-Oct-12 02-Oct-13 21 Wet WoWet Works 65 16-Aug-12 04-Nov-12 14-Oct-12 13-Feb-13 83 A34800 Block Works 5 16-Aug-12 23-Aug-12 14-Oct-12 18-Oct-12 48 A34650 Plaster Works 7 24-Sep-12 01-Oct-12 24-Oct-12 03-Nov-12 26 A34680 Installation of Suspended Ceiling Grid (Dry Area) 2 06-Oct-12 07-Oct-12 07-Nov-12 08-Nov-12 26 A35130 Wall Tiles Work (Wet Area) 8 02-Oct-12 10-Oct-12 21-Nov-12 29-Nov-12 40 A34660 Installation of Doors& Windows Sub-frame 2 17-Oct-12 18-Oct-12 12-Feb-13 13-Feb-13 95 A34670 1st Coat Paint 4 31-Oct-12 04-Nov-12 10-Nov-12 13-Nov-12 8 Fisrt StaFisrt Stage Finishes 67 10-Nov-12 30-Jan-13 20-Nov-12 04-Mar-13 28 A34690 Suspended Ceiling Tiles (DryArea) 2 10-Nov-12 11-Nov-12 20-Nov-12 21-Nov-12 8 A34730 Installation of Wardrobes 3 17-Dec-12 19-Dec-12 09-Jan-13 12-Jan-13 19 A35120 Screed Works 5 03-Jan-13 08-Jan-13 13-Jan-13 17-Jan-13 8 A34720 Water Proofing for Wet Area 3 09-Jan-13 12-Jan-13 19-Jan-13 21-Jan-13 8 A34710 Floor & Wall Tiles Work (Dry Area) 4 09-Jan-13 13-Jan-13 28-Feb-13 04-Mar-13 42 A35160 Installation of Suspended Ceiling Grid (Wet Area) 3 13-Jan-13 15-Jan-13 22-Jan-13 26-Jan-13 8 A35150 Suspended Ceiling Tiles (Wet Area) 2 27-Jan-13 28-Jan-13 10-Feb-13 11-Feb-13 12 A35140 Floor Tiles Work (Wet Area) 2 29-Jan-13 30-Jan-13 12-Feb-13 13-Feb-13 12 SecondSecond Stage Finishes 33 07-Feb-13 17-Mar-13 20-Feb-13 26-Mar-13 8 A34740 Installation of Windows&Doors 2 07-Feb-13 09-Feb-13 20-Feb-13 21-Feb-13 11 A34810 Doors Ironmongery 2 07-Feb-13 09-Feb-13 25-Mar-13 26-Mar-13 39 A34750 Installation of Mirrors 2 10-Feb-13 11-Feb-13 25-Mar-13 26-Mar-13 37 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Wall 1st Coat Paint Ceiling 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) Installation of Doors& Windows Sub-frame 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 31 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 32. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A34780 Installation of Balustrades& Handrails 2 10-Feb-13 11-Feb-13 25-Mar-13 26-Mar-13 37 A34790 Installation of Vanity Counter 2 11-Mar-13 12-Mar-13 25-Mar-13 26-Mar-13 12 A34760 Installation of Kitchen Cabinets 3 12-Mar-13 14-Mar-13 24-Mar-13 26-Mar-13 10 A35100 Installation of Toliets Accessories 2 16-Mar-13 17-Mar-13 25-Mar-13 26-Mar-13 8 Final StFinal Stage Finishes 148 18-Mar-13 08-Sep-13 27-Mar-13 02-Oct-13 21 A34700 Final Coat Paint 6 18-Mar-13 24-Mar-13 27-Mar-13 02-Apr-13 8 A34770 Installation of Carpets 4 25-Mar-13 28-Mar-13 22-Apr-13 25-Apr-13 24 A35110 Installation of Sinages 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24 A34820 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 142 25-Aug-12 12-Feb-13 20-Oct-12 02-Apr-13 42 HVACHVAC 132 25-Aug-12 31-Jan-13 28-Oct-12 05-Mar-13 28 A34830 Duct Installation & Insulation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53 A34840 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53 A34850 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 28-Oct-12 04-Nov-12 53 A34860 FCU Installation 2 02-Sep-12 03-Sep-12 05-Nov-12 06-Nov-12 53 A34870 Air-Outlet Installation 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 ElectricElectrical 133 25-Aug-12 02-Feb-13 21-Oct-12 05-Mar-13 27 A34880 Install Conduits in Wall 3 25-Aug-12 27-Aug-12 21-Oct-12 23-Oct-12 49 A34890 Install Cable Trays & Trunking 4 25-Aug-12 28-Aug-12 28-Oct-12 31-Oct-12 53 A34930 Cable Laying for Low Current System 3 29-Aug-12 01-Sep-12 06-Nov-12 08-Nov-12 57 A34940 Cable Laying for Power 3 29-Aug-12 01-Sep-12 06-Nov-12 08-Nov-12 57 A34900 Wiring for Lighting & Power 3 02-Oct-12 04-Oct-12 04-Nov-12 06-Nov-12 26 A34910 Wiring for Low Current System 3 02-Oct-12 04-Oct-12 04-Nov-12 06-Nov-12 26 A34920 DB installation,Dressing & Termination 6 05-Nov-12 11-Nov-12 14-Nov-12 21-Nov-12 8 A34970 Installation of Sockets 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 A34960 Installation of Lighting Fittings 4 29-Jan-13 02-Feb-13 02-Mar-13 05-Mar-13 27 PlumbinPlumbing 142 25-Aug-12 12-Feb-13 20-Oct-12 26-Mar-13 36 A34980 Drainge Pipes in Wall 4 25-Aug-12 28-Aug-12 20-Oct-12 23-Oct-12 48 A34990 H/L Drainage Pipes Installation 4 25-Aug-12 28-Aug-12 13-Jan-13 16-Jan-13 116 A35000 H/L Hot&Cold Water Pipe Installation 4 25-Aug-12 28-Aug-12 13-Jan-13 16-Jan-13 116 A35050 Water Pipes in Wall 4 25-Aug-12 28-Aug-12 20-Oct-12 23-Oct-12 48 A35010 Drainage&Water Pipes Testing 4 29-Aug-12 02-Sep-12 17-Jan-13 21-Jan-13 116 A35020 ElectricalWater Heater Installation 4 29-Aug-12 02-Sep-12 17-Jan-13 21-Jan-13 116 A35030 Floor Drain Fixning 2 06-Jan-13 07-Jan-13 09-Feb-13 10-Feb-13 28 A35040 Installation of Sanitaryware 3 10-Feb-13 12-Feb-13 24-Mar-13 26-Mar-13 36 Fire FigFire Fighting 134 25-Aug-12 03-Feb-13 31-Oct-12 02-Apr-13 50 A35090 Fire Fighting Pipe 3 25-Aug-12 27-Aug-12 31-Oct-12 03-Nov-12 56 A35080 Hydro Static Test for Pipes 3 28-Aug-12 30-Aug-12 04-Nov-12 06-Nov-12 56 A35070 Sprinkler Fixing 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 A35170 Fire Alarm Devices 3 29-Jan-13 31-Jan-13 24-Mar-13 26-Mar-13 46 A35060 Installation of Fire Extingusher&Blanket 2 02-Feb-13 03-Feb-13 01-Apr-13 02-Apr-13 50 One BedroOne Bedroom Flats 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21 FinishingFinishing Works 329 09-Aug-12 08-Sep-13 29-Sep-12 02-Oct-13 21 Wet WoWet Works 67 09-Aug-12 30-Oct-12 29-Sep-12 17-Feb-13 90 A35330 Block Works 6 09-Aug-12 15-Aug-12 29-Sep-12 04-Oct-12 41 A35180 Plaster Works 7 16-Sep-12 23-Sep-12 15-Oct-12 22-Oct-12 25 A35210 Installation of Suspended Ceiling Grid (Dry Area) 3 30-Sep-12 02-Oct-12 29-Oct-12 31-Oct-12 23 A35660 Wall Tiles Work (Wet Area) 4 11-Oct-12 15-Oct-12 01-Dec-12 05-Dec-12 40 A35190 Installation of Doors& Windows Sub-frame 3 20-Oct-12 22-Oct-12 14-Feb-13 17-Feb-13 95 A35200 1st Coat Paint 7 21-Oct-12 30-Oct-12 01-Nov-12 08-Nov-12 8 Fisrt StaFisrt Stage Finishes 70 12-Nov-12 05-Feb-13 22-Nov-12 09-Mar-13 27 A35220 Suspended Ceiling Tiles (DryArea) 4 12-Nov-12 17-Nov-12 22-Nov-12 26-Nov-12 8 A35260 Installation of Wardrobes 4 12-Dec-12 16-Dec-12 27-Dec-12 31-Dec-12 13 A35650 Screed Works 9 23-Dec-12 02-Jan-13 02-Jan-13 12-Jan-13 8 A35250 Water Proofing for Wet Area 3 03-Jan-13 06-Jan-13 22-Jan-13 26-Jan-13 16 A35240 Floor & Wall Tiles Work (Dry Area) 4 14-Jan-13 17-Jan-13 05-Mar-13 09-Mar-13 42 A35690 Installation of Suspended Ceiling Grid (Wet Area) 4 16-Jan-13 20-Jan-13 27-Jan-13 30-Jan-13 8 A35680 Suspended Ceiling Tiles (Wet Area) 4 21-Jan-13 26-Jan-13 05-Feb-13 09-Feb-13 12 A35670 Floor Tiles Work (Wet Area) 5 31-Jan-13 05-Feb-13 14-Feb-13 19-Feb-13 12 SecondSecond Stage Finishes 29 10-Feb-13 14-Mar-13 23-Feb-13 27-Mar-13 11 A35270 Installation of Windows&Doors 3 10-Feb-13 12-Feb-13 23-Feb-13 25-Feb-13 11 A35340 Doors Ironmongery 3 10-Feb-13 12-Feb-13 25-Mar-13 27-Mar-13 37 A35310 Installation of Balustrades& Handrails 2 13-Feb-13 14-Feb-13 26-Mar-13 27-Mar-13 35 A35280 Installation of Mirrors 3 13-Feb-13 16-Feb-13 25-Mar-13 27-Mar-13 34 A35320 Installation of Vanity Counter 3 07-Mar-13 10-Mar-13 21-Mar-13 24-Mar-13 12 A35290 Installation of Kitchen Cabinets 3 09-Mar-13 11-Mar-13 20-Mar-13 23-Mar-13 10 A35630 Installation of Toliets Accessories 4 11-Mar-13 14-Mar-13 20-Mar-13 24-Mar-13 8 Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21 A35230 Final Coat Paint 5 16-Mar-13 20-Mar-13 28-Mar-13 02-Apr-13 11 A35300 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A35640 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A35350 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 150 16-Aug-12 16-Feb-13 06-Oct-12 02-Apr-13 39 HVACHVAC 135 16-Aug-12 29-Jan-13 16-Oct-12 05-Mar-13 30 A35360 Duct Installation & Insulation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50 A35370 Chilled Water Pipe Installation & Insulation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50 A35380 Condensate Pipe Installation 7 16-Aug-12 26-Aug-12 16-Oct-12 23-Oct-12 50 A35390 FCU Installation 2 27-Aug-12 28-Aug-12 24-Oct-12 28-Oct-12 50 A35400 Air-Outlet Installation 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30 ElectricElectrical 136 16-Aug-12 30-Jan-13 11-Oct-12 05-Mar-13 29 A35410 Install Conduits in Wall 3 16-Aug-12 21-Aug-12 11-Oct-12 14-Oct-12 46 A35420 Install Cable Trays & Trunking 4 16-Aug-12 22-Aug-12 16-Oct-12 20-Oct-12 50 A35460 Cable Laying for Low Current System 3 23-Aug-12 26-Aug-12 29-Oct-12 31-Oct-12 55 A35470 Cable Laying for Power 3 23-Aug-12 26-Aug-12 29-Oct-12 31-Oct-12 55 A35430 Wiring for Lighting & Power 3 24-Sep-12 26-Sep-12 23-Oct-12 28-Oct-12 25 A35440 Wiring for Low Current System 3 24-Sep-12 26-Sep-12 23-Oct-12 28-Oct-12 25 A35450 DB installation,Dressing & Termination 6 31-Oct-12 06-Nov-12 20-Nov-12 26-Nov-12 16 A35500 Installation of Sockets 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30 A35490 Installation of Lighting Fittings 4 27-Jan-13 30-Jan-13 02-Mar-13 05-Mar-13 29 PlumbinPlumbing 150 16-Aug-12 16-Feb-13 06-Oct-12 27-Mar-13 34 A35520 H/L Drainage Pipes Installation 4 16-Aug-12 22-Aug-12 08-Jan-13 12-Jan-13 117 A35530 H/L Hot&Cold Water Pipe Installation 4 16-Aug-12 22-Aug-12 08-Jan-13 12-Jan-13 117 A35510 Drainge Pipes in Wall 8 16-Aug-12 27-Aug-12 06-Oct-12 14-Oct-12 41 A35540 Drainage&Water Pipes Testing 4 23-Aug-12 27-Aug-12 13-Jan-13 16-Jan-13 117 A35550 ElectricalWater Heater Installation 4 23-Aug-12 27-Aug-12 13-Jan-13 16-Jan-13 117 A35580 Water Pipes in Wall 8 16-Aug-12 27-Aug-12 06-Oct-12 14-Oct-12 41 A35560 Floor Drain Fixning 2 25-Dec-12 26-Dec-12 14-Feb-13 16-Feb-13 42 A35570 Installation of Sanitaryware 3 13-Feb-13 16-Feb-13 25-Mar-13 27-Mar-13 34 Fire FigFire Fighting 137 16-Aug-12 31-Jan-13 20-Oct-12 02-Apr-13 52 A35620 Fire Fighting Pipe 3 16-Aug-12 21-Aug-12 20-Oct-12 22-Oct-12 53 A35610 Hydro Static Test for Pipes 3 22-Aug-12 25-Aug-12 23-Oct-12 28-Oct-12 53 A35600 Sprinkler Fixing 3 27-Jan-13 29-Jan-13 03-Mar-13 05-Mar-13 30 A35700 Fire Alarm Devices 3 27-Jan-13 29-Jan-13 25-Mar-13 27-Mar-13 49 A35590 Installation of Fire Extingusher&Blanket 2 30-Jan-13 31-Jan-13 01-Apr-13 02-Apr-13 52 Two BedroTwo Bedroom Flats 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21 FinishingFinishing Works 344 23-Jul-12 08-Sep-13 01-Aug-12 02-Oct-13 21 Wet WoWet Works 84 23-Jul-12 01-Nov-12 01-Aug-12 25-Feb-13 95 A35860 Block Works 15 23-Jul-12 08-Aug-12 01-Aug-12 18-Aug-12 8 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) Installation of Doors& Windows Sub-frame 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 32 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 33. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A35710 Plaster Works 20 23-Aug-12 15-Sep-12 02-Sep-12 24-Sep-12 8 A35740 Installation of Suspended Ceiling Grid (Dry Area) 9 19-Sep-12 29-Sep-12 29-Sep-12 08-Oct-12 8 A35730 1st Coat Paint 18 30-Sep-12 20-Oct-12 09-Oct-12 31-Oct-12 8 A35720 Installation of Doors& Windows Sub-frame 7 23-Oct-12 01-Nov-12 18-Feb-13 25-Feb-13 95 A36190 Wall Tiles Work (Wet Area) 13 16-Oct-12 01-Nov-12 06-Dec-12 20-Dec-12 40 Fisrt StaFisrt Stage Finishes 75 18-Nov-12 16-Feb-13 27-Nov-12 23-Mar-13 30 A35750 Suspended Ceiling Tiles (DryArea) 12 18-Nov-12 01-Dec-12 27-Nov-12 11-Dec-12 8 A35790 Installation of Wardrobes 8 03-Dec-12 11-Dec-12 12-Dec-12 20-Dec-12 8 A36180 Screed Works 9 12-Dec-12 22-Dec-12 22-Dec-12 31-Dec-12 8 A35780 Water Proofing for Wet Area 9 23-Dec-12 02-Jan-13 20-Jan-13 30-Jan-13 23 A36220 Installation of Suspended Ceiling Grid (Wet Area) 7 21-Jan-13 29-Jan-13 31-Jan-13 07-Feb-13 8 A35770 Floor & Wall Tiles Work (Dry Area) 12 19-Jan-13 02-Feb-13 10-Mar-13 23-Mar-13 42 A36210 Suspended Ceiling Tiles (Wet Area) 10 30-Jan-13 10-Feb-13 09-Feb-13 19-Feb-13 8 A36200 Floor Tiles Work (Wet Area) 5 11-Feb-13 16-Feb-13 20-Feb-13 25-Feb-13 8 SecondSecond Stage Finishes 19 17-Feb-13 10-Mar-13 26-Feb-13 23-Mar-13 11 A35800 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 26-Feb-13 05-Mar-13 8 A35870 Doors Ironmongery 5 20-Feb-13 25-Feb-13 18-Mar-13 23-Mar-13 22 A35840 Installation of Balustrades& Handrails 5 25-Feb-13 02-Mar-13 18-Mar-13 23-Mar-13 18 A35810 Installation of Mirrors 9 25-Feb-13 06-Mar-13 13-Mar-13 23-Mar-13 14 A35850 Installation of Vanity Counter 9 25-Feb-13 06-Mar-13 11-Mar-13 20-Mar-13 12 A35820 Installation of Kitchen Cabinets 10 25-Feb-13 07-Mar-13 09-Mar-13 19-Mar-13 10 A36160 Installation of Toliets Accessories 12 25-Feb-13 10-Mar-13 06-Mar-13 19-Mar-13 8 Final StFinal Stage Finishes 154 11-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21 A35760 Final Coat Paint 9 11-Mar-13 20-Mar-13 24-Mar-13 02-Apr-13 11 A35830 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A36170 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A35880 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 166 09-Aug-12 27-Feb-13 21-Aug-12 02-Apr-13 29 HVACHVAC 154 09-Aug-12 13-Feb-13 18-Sep-12 05-Mar-13 17 A35890 Duct Installation & Insulation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32 A35900 Chilled Water Pipe Installation & Insulation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32 A35910 Condensate Pipe Installation 7 09-Aug-12 16-Aug-12 18-Sep-12 25-Sep-12 32 A35920 FCU Installation 2 18-Aug-12 21-Aug-12 26-Sep-12 27-Sep-12 32 A35930 Air-Outlet Installation 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17 ElectricElectrical 155 09-Aug-12 14-Feb-13 29-Aug-12 05-Mar-13 16 A35940 Install Conduits in Wall 3 09-Aug-12 12-Aug-12 29-Aug-12 01-Sep-12 15 A35950 Install Cable Trays & Trunking 4 09-Aug-12 13-Aug-12 18-Sep-12 22-Sep-12 32 A35990 Cable Laying for Low Current System 3 14-Aug-12 16-Aug-12 06-Oct-12 08-Oct-12 43 A36000 Cable Laying for Power 3 14-Aug-12 16-Aug-12 06-Oct-12 08-Oct-12 43 A35960 Wiring for Lighting & Power 3 16-Sep-12 18-Sep-12 25-Sep-12 27-Sep-12 8 A35970 Wiring for Low Current System 3 16-Sep-12 18-Sep-12 25-Sep-12 27-Sep-12 8 A35980 DB installation,Dressing & Termination 6 21-Oct-12 29-Oct-12 05-Dec-12 11-Dec-12 35 A36030 Installation of Sockets 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17 A36020 Installation of Lighting Fittings 4 11-Feb-13 14-Feb-13 02-Mar-13 05-Mar-13 16 PlumbinPlumbing 166 09-Aug-12 27-Feb-13 21-Aug-12 23-Mar-13 20 A36050 H/L Drainage Pipes Installation 4 09-Aug-12 13-Aug-12 21-Jan-13 26-Jan-13 134 A36060 H/L Hot&Cold Water Pipe Installation 4 09-Aug-12 13-Aug-12 21-Jan-13 26-Jan-13 134 A36070 Drainage&Water Pipes Testing 4 14-Aug-12 18-Aug-12 27-Jan-13 30-Jan-13 134 A36110 Water Pipes in Wall 8 09-Aug-12 18-Aug-12 23-Aug-12 01-Sep-12 10 A36040 Drainge Pipes in Wall 10 09-Aug-12 22-Aug-12 21-Aug-12 01-Sep-12 8 A36080 ElectricalWater Heater Installation 4 03-Sep-12 06-Sep-12 27-Jan-13 30-Jan-13 119 A36090 Floor Drain Fixning 2 15-Dec-12 16-Dec-12 20-Feb-13 21-Feb-13 56 A36100 Installation of Sanitaryware 3 25-Feb-13 27-Feb-13 20-Mar-13 23-Mar-13 20 Fire FigFire Fighting 156 09-Aug-12 16-Feb-13 22-Sep-12 02-Apr-13 39 A36150 Fire Fighting Pipe 3 09-Aug-12 12-Aug-12 22-Sep-12 24-Sep-12 35 A36140 Hydro Static Test for Pipes 3 13-Aug-12 15-Aug-12 25-Sep-12 27-Sep-12 35 A36130 Sprinkler Fixing 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17 A36230 Fire Alarm Devices 3 11-Feb-13 13-Feb-13 20-Mar-13 23-Mar-13 32 A36120 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 01-Apr-13 02-Apr-13 39 3rd Floor3rd Floor 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21 Public AreaPublic Area 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8 Garbage RGarbage Room 166 16-Sep-12 03-Apr-13 24-Oct-12 25-Apr-13 19 FinishingFinishing Works 166 16-Sep-12 03-Apr-13 24-Oct-12 25-Apr-13 19 Wet WorWet Works 62 16-Sep-12 29-Nov-12 24-Oct-12 09-Feb-13 58 A16620 Block Works 3 16-Sep-12 18-Sep-12 24-Oct-12 29-Oct-12 33 A16570 Installation of Doors& Windows Sub-frame 1 22-Oct-12 22-Oct-12 09-Feb-13 09-Feb-13 88 A16560 Plaster Works 3 22-Oct-12 24-Oct-12 20-Jan-13 22-Jan-13 72 A16600 Wall Tiles Work 4 30-Oct-12 03-Nov-12 27-Jan-13 30-Jan-13 72 A16580 1st Coat Paint 2 28-Nov-12 29-Nov-12 31-Jan-13 02-Feb-13 52 Fisrt StaFisrt Stage Finishes 7 01-Dec-12 09-Dec-12 04-Feb-13 24-Apr-13 115 A16750 Screed Works 2 01-Dec-12 03-Dec-12 04-Feb-13 05-Feb-13 53 A16770 Floor Tiles Work 2 05-Dec-12 06-Dec-12 07-Feb-13 09-Feb-13 53 A16630 Doors Ironmongery 1 08-Dec-12 08-Dec-12 24-Apr-13 24-Apr-13 116 A16610 Installation of Doors 2 08-Dec-12 09-Dec-12 10-Feb-13 11-Feb-13 53 Second SSecond Stage Finishes 2 01-Apr-13 02-Apr-13 10-Apr-13 11-Apr-13 8 A16590 Final Coat Paint 2 01-Apr-13 02-Apr-13 10-Apr-13 11-Apr-13 8 Final StaFinal Stage Finishes 1 03-Apr-13 03-Apr-13 25-Apr-13 25-Apr-13 19 A16740 Installation of Sinages 1 03-Apr-13 03-Apr-13 25-Apr-13 25-Apr-13 19 MEP WorkMEP Works 66 19-Sep-12 09-Dec-12 30-Oct-12 25-Mar-13 89 ElectricalElectrical 66 19-Sep-12 09-Dec-12 17-Jan-13 28-Feb-13 68 A16640 Install Conduits in Wall 2 19-Sep-12 20-Sep-12 17-Jan-13 19-Jan-13 98 A16650 Wiring for Lighting & Power 2 28-Oct-12 29-Oct-12 23-Jan-13 26-Jan-13 72 A16660 Installation of Lighting Fittings 2 08-Dec-12 09-Dec-12 27-Feb-13 28-Feb-13 68 PlumbingPlumbing 62 19-Sep-12 04-Dec-12 15-Jan-13 06-Feb-13 53 A16670 Drainge Pipes in Wall 2 19-Sep-12 20-Sep-12 15-Jan-13 16-Jan-13 96 A16700 Water Pipes in Wall 2 19-Sep-12 20-Sep-12 15-Jan-13 16-Jan-13 96 A16680 Drainage&Water Pipes Testing 2 22-Sep-12 23-Sep-12 17-Jan-13 19-Jan-13 96 A16690 Floor Drain Fixning 1 04-Dec-12 04-Dec-12 06-Feb-13 06-Feb-13 53 Fire FighFire Fighting 65 20-Sep-12 09-Dec-12 30-Oct-12 25-Mar-13 89 A16730 Fire Fighting Pipe 2 20-Sep-12 22-Sep-12 30-Oct-12 31-Oct-12 32 A16720 Hydro Static Test for Pipes 2 23-Sep-12 24-Sep-12 17-Feb-13 18-Feb-13 120 A16710 Sprinkler Fixing 2 08-Dec-12 09-Dec-12 19-Feb-13 20-Feb-13 61 A16760 Fire Alarm Devices 2 08-Dec-12 09-Dec-12 24-Mar-13 25-Mar-13 89 Corridor &Corridor & Lift Lobby 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8 FinishingFinishing Works 185 06-Sep-12 16-Apr-13 14-Oct-12 25-Apr-13 8 Wet WorWet Works 56 06-Sep-12 12-Nov-12 14-Oct-12 20-Jan-13 56 A16280 Block Works 8 06-Sep-12 15-Sep-12 14-Oct-12 22-Oct-12 32 A16220 Plaster Works 7 14-Oct-12 21-Oct-12 18-Dec-12 25-Dec-12 52 A16240 Installation of Suspended Ceiling Grid 6 29-Oct-12 04-Nov-12 31-Dec-12 07-Jan-13 52 A16250 Suspended Ceiling Tiles 6 05-Nov-12 11-Nov-12 08-Jan-13 14-Jan-13 52 A16540 MDF for Lift Lobby Wall 7 05-Nov-12 12-Nov-12 13-Jan-13 20-Jan-13 56 Fisrt StaFisrt Stage Finishes 12 13-Nov-12 27-Nov-12 21-Jan-13 30-Jan-13 52 A16520 Screed Works 3 13-Nov-12 17-Nov-12 21-Jan-13 23-Jan-13 56 A16230 1st Coat Paint 5 22-Nov-12 27-Nov-12 26-Jan-13 30-Jan-13 52 Second SSecond Stage Finishes 11 28-Nov-12 11-Dec-12 12-Feb-13 13-Feb-13 53 A16260 Installation of Doors 2 28-Nov-12 29-Nov-12 12-Feb-13 13-Feb-13 62 A16290 Doors Ironmongery 2 10-Dec-12 11-Dec-12 12-Feb-13 13-Feb-13 53 Final StaFinal Stage Finishes 9 07-Apr-13 16-Apr-13 16-Apr-13 25-Apr-13 8 A16270 Installation of Carpets 2 07-Apr-13 08-Apr-13 16-Apr-13 17-Apr-13 8 A16530 Fixing of Wall Covering 5 09-Apr-13 14-Apr-13 18-Apr-13 23-Apr-13 8 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Plaster Works Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Water Pipes in Wall Drainge Pipes in Wall Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 33 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 34. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A16510 Installation of Sinages 2 15-Apr-13 16-Apr-13 24-Apr-13 25-Apr-13 8 MEP WorkMEP Works 55 16-Sep-12 21-Nov-12 23-Oct-12 05-Mar-13 86 HVACHVAC 50 16-Sep-12 14-Nov-12 22-Dec-12 23-Jan-13 57 A16300 Duct Installation & Insulation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79 A16310 Chilled Water Pipe Installation & Insulation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79 A16320 Condensate Pipe Installation 5 16-Sep-12 20-Sep-12 22-Dec-12 26-Dec-12 79 A16330 FCU Installation 3 22-Sep-12 24-Sep-12 27-Dec-12 30-Dec-12 79 A16340 Air-Outlet Installation 3 12-Nov-12 14-Nov-12 21-Jan-13 23-Jan-13 57 ElectricalElectrical 52 16-Sep-12 18-Nov-12 16-Dec-12 05-Mar-13 89 A16350 Install Conduits in Wall 2 16-Sep-12 17-Sep-12 16-Dec-12 17-Dec-12 74 A16360 Install Cable Trays & Trunking 2 16-Sep-12 17-Sep-12 22-Dec-12 23-Dec-12 79 A16400 Cable Laying for Low Current System 2 18-Sep-12 19-Sep-12 06-Jan-13 07-Jan-13 89 A16410 Cable Laying for Power 3 18-Sep-12 20-Sep-12 05-Jan-13 07-Jan-13 88 A16370 Wiring for Lighting & Power 3 22-Oct-12 24-Oct-12 27-Dec-12 30-Dec-12 53 A16380 Wiring for Low Current System 4 22-Oct-12 28-Oct-12 26-Dec-12 30-Dec-12 52 A16390 DB installation,Dressing & Termination 6 05-Nov-12 11-Nov-12 08-Jan-13 14-Jan-13 52 A16430 Installation of Lighting Fittings 3 12-Nov-12 14-Nov-12 24-Feb-13 26-Feb-13 85 A16440 Installation of Sockets 5 12-Nov-12 18-Nov-12 28-Feb-13 05-Mar-13 89 PlumbingPlumbing 5 16-Sep-12 20-Sep-12 25-Dec-12 30-Dec-12 82 A16450 H/L Hot&Cold Water Pipe Installation 5 16-Sep-12 20-Sep-12 25-Dec-12 30-Dec-12 82 Fire FighFire Fighting 55 16-Sep-12 21-Nov-12 23-Oct-12 23-Jan-13 52 A16500 Fire Fighting Pipe 4 16-Sep-12 19-Sep-12 23-Oct-12 29-Oct-12 32 A16490 Hydro Static Test for Pipes 4 20-Sep-12 24-Sep-12 26-Dec-12 30-Dec-12 79 A16480 Sprinkler Fixing 4 12-Nov-12 17-Nov-12 15-Jan-13 19-Jan-13 52 A16550 Fire Alarm Devices 5 12-Nov-12 18-Nov-12 19-Jan-13 23-Jan-13 55 A16470 Installation of Fire Extingusher&Blanket 4 18-Nov-12 21-Nov-12 20-Jan-13 23-Jan-13 52 Electrical /Electrical /Telephone/ELV Rooms 167 19-Sep-12 08-Apr-13 19-Jan-13 25-Apr-13 15 FinishingFinishing Works 167 19-Sep-12 08-Apr-13 19-Jan-13 25-Apr-13 15 Wet WorWet Works 62 19-Sep-12 04-Dec-12 19-Jan-13 13-Feb-13 59 A16830 Block Works 3 19-Sep-12 22-Sep-12 19-Jan-13 21-Jan-13 99 A16790 Installation of Doors& Windows Sub-frame 1 28-Oct-12 28-Oct-12 13-Feb-13 13-Feb-13 89 A16780 Plaster Works 4 28-Oct-12 31-Oct-12 26-Jan-13 29-Jan-13 73 A16800 1st Coat Paint 3 01-Dec-12 04-Dec-12 03-Feb-13 05-Feb-13 52 Fisrt StaFisrt Stage Finishes 39 14-Nov-12 31-Dec-12 14-Feb-13 13-Apr-13 86 A16820 Installation of Doors 2 14-Nov-12 17-Nov-12 14-Feb-13 16-Feb-13 75 A16840 Doors Ironmongery 2 12-Dec-12 13-Dec-12 14-Feb-13 16-Feb-13 53 A16890 Epoxy Paint Works 2 30-Dec-12 31-Dec-12 11-Apr-13 13-Apr-13 86 Second SSecond Stage Finishes 2 04-Apr-13 06-Apr-13 14-Apr-13 15-Apr-13 8 A16810 Final Coat Paint 2 04-Apr-13 06-Apr-13 14-Apr-13 15-Apr-13 8 Final StaFinal Stage Finishes 2 07-Apr-13 08-Apr-13 24-Apr-13 25-Apr-13 15 A16880 Installation of Sinages 2 07-Apr-13 08-Apr-13 24-Apr-13 25-Apr-13 15 MEP WorkMEP Works 80 23-Sep-12 29-Dec-12 22-Jan-13 27-Mar-13 74 HVACHVAC 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74 A16920 Air-Outlet Installation 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74 ElectricalElectrical 80 23-Sep-12 29-Dec-12 22-Jan-13 05-Mar-13 55 A16850 Install Conduits in Wall 2 23-Sep-12 24-Sep-12 22-Jan-13 23-Jan-13 99 A16860 Wiring for Lighting & Power 2 01-Nov-12 03-Nov-12 31-Jan-13 02-Feb-13 74 A16910 Installation of SMDBs 7 05-Dec-12 12-Dec-12 21-Feb-13 28-Feb-13 65 A16870 Installation of Lighting Fittings 2 13-Dec-12 15-Dec-12 02-Mar-13 03-Mar-13 65 A114460 Installation of Access ControlSystem 20 05-Dec-12 27-Dec-12 11-Feb-13 05-Mar-13 56 A114440 Installation of MATC,TV System 20 05-Dec-12 27-Dec-12 11-Feb-13 05-Mar-13 56 A114450 Installation of Telephone System 21 05-Dec-12 29-Dec-12 10-Feb-13 05-Mar-13 55 Fire FighFire Fighting 2 16-Dec-12 17-Dec-12 26-Mar-13 27-Mar-13 84 A16900 Fire Alarm Devices 2 16-Dec-12 17-Dec-12 26-Mar-13 27-Mar-13 84 Room ServRoom Service 161 23-Sep-12 04-Apr-13 22-Jan-13 25-Apr-13 18 FinishingFinishing Works 161 23-Sep-12 04-Apr-13 22-Jan-13 25-Apr-13 18 Wet WorWet Works 62 23-Sep-12 08-Dec-12 22-Jan-13 16-Feb-13 58 A16980 Block Works 2 23-Sep-12 24-Sep-12 22-Jan-13 23-Jan-13 99 A16940 Installation of Doors& Windows Sub-frame 1 01-Nov-12 01-Nov-12 16-Feb-13 16-Feb-13 87 A16930 Plaster Works 4 01-Nov-12 05-Nov-12 30-Jan-13 03-Feb-13 73 A16950 1st Coat Paint 3 05-Dec-12 08-Dec-12 06-Feb-13 09-Feb-13 52 Fisrt StaFisrt Stage Finishes 7 09-Dec-12 16-Dec-12 10-Feb-13 24-Apr-13 109 A17110 Screed Works 2 09-Dec-12 10-Dec-12 10-Feb-13 11-Feb-13 52 A17130 Floor Tiles Work 3 12-Dec-12 15-Dec-12 13-Feb-13 16-Feb-13 52 A16970 Installation of Doors 1 16-Dec-12 16-Dec-12 17-Feb-13 17-Feb-13 52 A16990 Doors Ironmongery 1 16-Dec-12 16-Dec-12 24-Apr-13 24-Apr-13 109 Second SSecond Stage Finishes 1 03-Apr-13 03-Apr-13 13-Apr-13 13-Apr-13 8 A16960 Final Coat Paint 1 03-Apr-13 03-Apr-13 13-Apr-13 13-Apr-13 8 Final StaFinal Stage Finishes 1 04-Apr-13 04-Apr-13 25-Apr-13 25-Apr-13 18 A17100 Installation of Sinages 1 04-Apr-13 04-Apr-13 25-Apr-13 25-Apr-13 18 MEP WorkMEP Works 70 25-Sep-12 19-Dec-12 26-Jan-13 30-Mar-13 84 HVACHVAC 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65 A17140 Air-Outlet Installation 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65 ElectricalElectrical 68 25-Sep-12 17-Dec-12 28-Jan-13 05-Mar-13 65 A17000 Install Conduits in Wall 2 25-Sep-12 26-Sep-12 28-Jan-13 29-Jan-13 101 A17010 Wiring for Lighting & Power 2 06-Nov-12 07-Nov-12 04-Feb-13 05-Feb-13 73 A17020 Installation of Lighting Fittings 2 16-Dec-12 17-Dec-12 04-Mar-13 05-Mar-13 65 PlumbingPlumbing 63 25-Sep-12 11-Dec-12 26-Jan-13 12-Feb-13 52 A17030 Drainge Pipes in Wall 2 25-Sep-12 26-Sep-12 26-Jan-13 27-Jan-13 99 A17060 Water Pipes in Wall 2 25-Sep-12 26-Sep-12 26-Jan-13 27-Jan-13 99 A17040 Drainage&Water Pipes Testing 2 27-Sep-12 29-Sep-12 28-Jan-13 29-Jan-13 99 A17050 Floor Drain Fixning 1 11-Dec-12 11-Dec-12 12-Feb-13 12-Feb-13 52 Fire FighFire Fighting 69 26-Sep-12 19-Dec-12 17-Feb-13 30-Mar-13 84 A17090 Fire Fighting Pipe 2 26-Sep-12 27-Sep-12 17-Feb-13 18-Feb-13 117 A17080 Hydro Static Test for Pipes 2 29-Sep-12 30-Sep-12 19-Feb-13 20-Feb-13 117 A17070 Sprinkler Fixing 2 16-Dec-12 17-Dec-12 21-Feb-13 23-Feb-13 56 A17120 Fire Alarm Devices 2 18-Dec-12 19-Dec-12 28-Mar-13 30-Mar-13 84 StaircaseStaircase 142 10-Sep-12 28-Feb-13 31-Oct-12 15-Apr-13 39 Stair 1Stair 1 128 10-Sep-12 12-Feb-13 31-Oct-12 15-Apr-13 53 A108410 Floor Screed 3 10-Sep-12 12-Sep-12 31-Oct-12 03-Nov-12 42 A108420 Install Handrails 4 29-Nov-12 04-Dec-12 25-Dec-12 29-Dec-12 21 A108430 Ceiling 1st Coat Paint 7 29-Dec-12 06-Jan-13 14-Feb-13 21-Feb-13 39 A108440 Wall 1st Coat Paint 7 07-Jan-13 14-Jan-13 23-Feb-13 02-Mar-13 39 A108450 Install Granite/Terrazo 12 15-Jan-13 29-Jan-13 05-Mar-13 18-Mar-13 41 A108460 Final Coat Paint 12 30-Jan-13 12-Feb-13 02-Apr-13 15-Apr-13 53 Stair 2Stair 2 139 13-Sep-12 28-Feb-13 04-Nov-12 15-Apr-13 39 A108470 Floor Screed 3 13-Sep-12 16-Sep-12 04-Nov-12 06-Nov-12 42 A108480 Install Handrails 4 05-Dec-12 09-Dec-12 30-Dec-12 03-Jan-13 21 A108490 Ceiling 1st Coat Paint 7 15-Jan-13 22-Jan-13 03-Mar-13 10-Mar-13 39 A108500 Wall 1st Coat Paint 7 23-Jan-13 31-Jan-13 11-Mar-13 18-Mar-13 39 A108510 Install Granite/Terrazo 12 02-Feb-13 14-Feb-13 19-Mar-13 01-Apr-13 39 A108520 Final Coat Paint 12 16-Feb-13 28-Feb-13 02-Apr-13 15-Apr-13 39 ApartementsApartements 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21 Studio FlatsStudio Flats 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21 FinishingFinishing Works 312 01-Sep-12 08-Sep-13 08-Oct-12 02-Oct-13 21 Wet WoWet Works 62 01-Sep-12 13-Nov-12 08-Oct-12 17-Feb-13 78 A36390 Block Works 5 01-Sep-12 05-Sep-12 08-Oct-12 13-Oct-12 32 A36250 Installation of Doors& Windows Sub-frame 1 06-Oct-12 06-Oct-12 17-Feb-13 17-Feb-13 109 A36240 Plaster Works 7 06-Oct-12 13-Oct-12 28-Oct-12 04-Nov-12 17 A36270 Installation of Suspended Ceiling Grid (Dry Area) 2 17-Oct-12 18-Oct-12 08-Nov-12 10-Nov-12 17 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 34 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 35. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A36720 Wall Tiles Work (Wet Area) 8 14-Oct-12 22-Oct-12 21-Nov-12 29-Nov-12 30 A36260 1st Coat Paint 3 11-Nov-12 13-Nov-12 11-Nov-12 13-Nov-12 0 Fisrt StaFisrt Stage Finishes 73 14-Nov-12 11-Feb-13 14-Nov-12 17-Mar-13 29 A36280 Suspended Ceiling Tiles (DryArea) 6 14-Nov-12 21-Nov-12 14-Nov-12 21-Nov-12 0 A36320 Installation of Wardrobes 2 22-Nov-12 24-Nov-12 05-Dec-12 06-Dec-12 10 A36710 Screed Works 5 25-Nov-12 29-Nov-12 19-Dec-12 24-Dec-12 20 A36310 Water Proofing for Wet Area 3 01-Dec-12 04-Dec-12 25-Dec-12 27-Dec-12 20 A36300 Floor & Wall Tiles Work (Dry Area) 4 01-Dec-12 05-Dec-12 13-Mar-13 17-Mar-13 85 A36750 Installation of Suspended Ceiling Grid (Wet Area) 3 05-Dec-12 08-Dec-12 26-Jan-13 28-Jan-13 42 A36740 Suspended Ceiling Tiles (Wet Area) 2 07-Feb-13 09-Feb-13 07-Feb-13 09-Feb-13 0 A36730 Floor Tiles Work (Wet Area) 2 10-Feb-13 11-Feb-13 10-Feb-13 11-Feb-13 0 SecondSecond Stage Finishes 35 12-Feb-13 24-Mar-13 18-Feb-13 02-Apr-13 8 A36330 Installation of Windows&Doors 2 12-Feb-13 13-Feb-13 18-Feb-13 19-Feb-13 5 A36400 Doors Ironmongery 2 12-Feb-13 13-Feb-13 01-Apr-13 02-Apr-13 41 A36340 Installation of Mirrors 2 14-Feb-13 16-Feb-13 20-Mar-13 21-Mar-13 29 A36370 Installation of Balustrades& Handrails 2 14-Feb-13 16-Feb-13 01-Apr-13 02-Apr-13 39 A36380 Installation of Vanity Counter 2 18-Mar-13 19-Mar-13 01-Apr-13 02-Apr-13 12 A36350 Installation of Kitchen Cabinets 2 19-Mar-13 20-Mar-13 01-Apr-13 02-Apr-13 11 A36690 Installation of Toliets Accessories 2 23-Mar-13 24-Mar-13 01-Apr-13 02-Apr-13 8 Final StFinal Stage Finishes 142 25-Mar-13 08-Sep-13 03-Apr-13 02-Oct-13 21 A36290 Final Coat Paint 6 25-Mar-13 31-Mar-13 03-Apr-13 09-Apr-13 8 A36360 Installation of Carpets 4 01-Apr-13 04-Apr-13 22-Apr-13 25-Apr-13 18 A36700 Installation of Sinages 7 28-Mar-13 04-Apr-13 18-Apr-13 25-Apr-13 18 A36410 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 135 06-Sep-12 17-Feb-13 21-Oct-12 09-Apr-13 44 HVACHVAC 131 06-Sep-12 12-Feb-13 29-Oct-12 05-Mar-13 18 A36420 Duct Installation & Insulation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43 A36430 Chilled Water Pipe Installation & Insulation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43 A36440 Condensate Pipe Installation 7 06-Sep-12 13-Sep-12 29-Oct-12 05-Nov-12 43 A36450 FCU Installation 2 15-Sep-12 16-Sep-12 06-Nov-12 07-Nov-12 43 A36460 Air-Outlet Installation 3 10-Feb-13 12-Feb-13 03-Mar-13 05-Mar-13 18 ElectricElectrical 134 06-Sep-12 16-Feb-13 22-Oct-12 05-Mar-13 15 A36470 Install Conduits in Wall 3 06-Sep-12 09-Sep-12 22-Oct-12 24-Oct-12 39 A36480 Install Cable Trays & Trunking 4 06-Sep-12 10-Sep-12 29-Oct-12 01-Nov-12 43 A36520 Cable Laying for Low Current System 3 11-Sep-12 13-Sep-12 07-Nov-12 10-Nov-12 47 A36530 Cable Laying for Power 3 11-Sep-12 13-Sep-12 07-Nov-12 10-Nov-12 47 A36490 Wiring for Lighting & Power 3 14-Oct-12 16-Oct-12 05-Nov-12 07-Nov-12 17 A36500 Wiring for Low Current System 3 14-Oct-12 16-Oct-12 05-Nov-12 07-Nov-12 17 A36510 DB installation,Dressing & Termination 6 14-Nov-12 21-Nov-12 14-Nov-12 21-Nov-12 0 A36560 Installation of Sockets 3 10-Feb-13 12-Feb-13 03-Mar-13 05-Mar-13 18 A36550 Installation of Lighting Fittings 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15 PlumbinPlumbing 135 06-Sep-12 17-Feb-13 21-Oct-12 02-Apr-13 38 A36580 H/L Drainage Pipes Installation 4 06-Sep-12 10-Sep-12 15-Jan-13 19-Jan-13 107 A36590 H/L Hot&Cold Water Pipe Installation 4 06-Sep-12 10-Sep-12 15-Jan-13 19-Jan-13 107 A36640 Water Pipes in Wall 4 06-Sep-12 10-Sep-12 21-Oct-12 24-Oct-12 38 A36600 Drainage&Water Pipes Testing 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107 A36610 ElectricalWater Heater Installation 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107 A36570 Drainge Pipes in Wall 4 13-Sep-12 17-Sep-12 21-Oct-12 24-Oct-12 32 A36620 Floor Drain Fixning 2 27-Nov-12 28-Nov-12 06-Feb-13 07-Feb-13 58 A36630 Installation of Sanitaryware 3 14-Feb-13 17-Feb-13 31-Mar-13 02-Apr-13 38 Fire FigFire Fighting 120 23-Sep-12 16-Feb-13 01-Nov-12 09-Apr-13 45 A36680 Fire Fighting Pipe 3 23-Sep-12 25-Sep-12 01-Nov-12 04-Nov-12 32 A36670 Hydro Static Test for Pipes 3 26-Sep-12 29-Sep-12 05-Nov-12 07-Nov-12 32 A36660 Sprinkler Fixing 3 11-Feb-13 13-Feb-13 03-Mar-13 05-Mar-13 17 A36760 Fire Alarm Devices 3 11-Feb-13 13-Feb-13 31-Mar-13 02-Apr-13 41 A36650 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 08-Apr-13 09-Apr-13 45 One BedroOne Bedroom Flats 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21 FinishingFinishing Works 317 26-Aug-12 08-Sep-13 15-Sep-12 02-Oct-13 21 Wet WoWet Works 64 26-Aug-12 10-Nov-12 15-Sep-12 19-Feb-13 83 A36920 Block Works 5 26-Aug-12 30-Aug-12 15-Sep-12 19-Sep-12 17 A36780 Installation of Doors& Windows Sub-frame 1 27-Sep-12 27-Sep-12 19-Feb-13 19-Feb-13 118 A36770 Plaster Works 7 27-Sep-12 04-Oct-12 17-Oct-12 24-Oct-12 17 A36800 Installation of Suspended Ceiling Grid (Dry Area) 3 11-Oct-12 14-Oct-12 31-Oct-12 03-Nov-12 15 A37250 Wall Tiles Work (Wet Area) 4 23-Oct-12 29-Oct-12 01-Dec-12 05-Dec-12 30 A36790 1st Coat Paint 6 04-Nov-12 10-Nov-12 04-Nov-12 10-Nov-12 0 Fisrt StaFisrt Stage Finishes 72 22-Nov-12 17-Feb-13 22-Nov-12 21-Mar-13 28 A36810 Suspended Ceiling Tiles (DryArea) 4 22-Nov-12 26-Nov-12 22-Nov-12 26-Nov-12 0 A36850 Installation of Wardrobes 4 27-Nov-12 01-Dec-12 08-Dec-12 11-Dec-12 8 A37240 Screed Works 9 03-Dec-12 12-Dec-12 18-Dec-12 27-Dec-12 13 A36840 Water Proofing for Wet Area 3 13-Dec-12 16-Dec-12 29-Dec-12 31-Dec-12 13 A36830 Floor & Wall Tiles Work (Dry Area) 4 13-Dec-12 17-Dec-12 18-Mar-13 21-Mar-13 79 A37280 Installation of Suspended Ceiling Grid (Wet Area) 4 17-Dec-12 20-Dec-12 29-Jan-13 02-Feb-13 35 A37270 Suspended Ceiling Tiles (Wet Area) 4 03-Feb-13 06-Feb-13 03-Feb-13 06-Feb-13 0 A37260 Floor Tiles Work (Wet Area) 5 12-Feb-13 17-Feb-13 12-Feb-13 17-Feb-13 0 SecondSecond Stage Finishes 28 18-Feb-13 21-Mar-13 20-Feb-13 09-Apr-13 16 A36860 Installation of Windows&Doors 3 18-Feb-13 20-Feb-13 20-Feb-13 23-Feb-13 2 A36930 Doors Ironmongery 3 18-Feb-13 20-Feb-13 07-Apr-13 09-Apr-13 41 A36900 Installation of Balustrades& Handrails 2 21-Feb-13 23-Feb-13 08-Apr-13 09-Apr-13 39 A36870 Installation of Mirrors 3 21-Feb-13 24-Feb-13 23-Mar-13 25-Mar-13 25 A36910 Installation of Vanity Counter 3 14-Mar-13 17-Mar-13 28-Mar-13 31-Mar-13 12 A36880 Installation of Kitchen Cabinets 3 16-Mar-13 18-Mar-13 28-Mar-13 31-Mar-13 11 A37220 Installation of Toliets Accessories 4 18-Mar-13 21-Mar-13 27-Mar-13 31-Mar-13 8 Final StFinal Stage Finishes 144 23-Mar-13 08-Sep-13 10-Apr-13 02-Oct-13 21 A36820 Final Coat Paint 5 23-Mar-13 27-Mar-13 10-Apr-13 15-Apr-13 16 A36890 Installation of Carpets 4 28-Mar-13 01-Apr-13 22-Apr-13 25-Apr-13 21 A37230 Installation of Sinages 7 25-Mar-13 01-Apr-13 18-Apr-13 25-Apr-13 21 A36940 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 146 01-Sep-12 24-Feb-13 20-Sep-12 15-Apr-13 43 HVACHVAC 134 01-Sep-12 10-Feb-13 18-Oct-12 05-Mar-13 20 A36950 Duct Installation & Insulation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41 A36960 Chilled Water Pipe Installation & Insulation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41 A36970 Condensate Pipe Installation 7 01-Sep-12 08-Sep-12 18-Oct-12 28-Oct-12 41 A36980 FCU Installation 2 09-Sep-12 10-Sep-12 29-Oct-12 30-Oct-12 41 A36990 Air-Outlet Installation 3 07-Feb-13 10-Feb-13 03-Mar-13 05-Mar-13 20 ElectricElectrical 135 01-Sep-12 11-Feb-13 14-Oct-12 05-Mar-13 19 A37000 Install Conduits in Wall 3 01-Sep-12 03-Sep-12 14-Oct-12 16-Oct-12 37 A37010 Install Cable Trays & Trunking 4 01-Sep-12 04-Sep-12 18-Oct-12 22-Oct-12 41 A37050 Cable Laying for Low Current System 3 05-Sep-12 08-Sep-12 31-Oct-12 03-Nov-12 46 A37060 Cable Laying for Power 3 05-Sep-12 08-Sep-12 31-Oct-12 03-Nov-12 46 A37020 Wiring for Lighting & Power 3 06-Oct-12 08-Oct-12 28-Oct-12 30-Oct-12 17 A37030 Wiring for Low Current System 3 06-Oct-12 08-Oct-12 28-Oct-12 30-Oct-12 17 A37040 DB installation,Dressing & Termination 6 11-Nov-12 18-Nov-12 20-Nov-12 26-Nov-12 7 A37090 Installation of Sockets 3 07-Feb-13 10-Feb-13 03-Mar-13 05-Mar-13 20 A37080 Installation of Lighting Fittings 4 07-Feb-13 11-Feb-13 25-Feb-13 28-Feb-13 15 PlumbinPlumbing 146 01-Sep-12 24-Feb-13 08-Oct-12 09-Apr-13 38 A37110 H/L Drainage Pipes Installation 4 01-Sep-12 04-Sep-12 10-Jan-13 14-Jan-13 108 A37120 H/L Hot&Cold Water Pipe Installation 4 01-Sep-12 04-Sep-12 19-Jan-13 22-Jan-13 115 A37130 Drainage&Water Pipes Testing 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115 A37140 ElectricalWater Heater Installation 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Drainge Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 35 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 36. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A37170 Water Pipes in Wall 8 01-Sep-12 09-Sep-12 08-Oct-12 16-Oct-12 32 A37100 Drainge Pipes in Wall 8 04-Sep-12 12-Sep-12 08-Oct-12 16-Oct-12 29 A37150 Floor Drain Fixning 3 05-Dec-12 08-Dec-12 11-Feb-13 13-Feb-13 56 A37160 Installation of Sanitaryware 3 21-Feb-13 24-Feb-13 07-Apr-13 09-Apr-13 38 Fire FigFire Fighting 136 01-Sep-12 12-Feb-13 20-Sep-12 15-Apr-13 53 A37210 Fire Fighting Pipe 3 01-Sep-12 03-Sep-12 20-Sep-12 23-Sep-12 17 A37200 Hydro Static Test for Pipes 3 04-Sep-12 06-Sep-12 28-Oct-12 30-Oct-12 44 A37190 Sprinkler Fixing 3 07-Feb-13 10-Feb-13 27-Feb-13 02-Mar-13 17 A37290 Fire Alarm Devices 3 07-Feb-13 10-Feb-13 27-Mar-13 30-Mar-13 41 A37180 Installation of Fire Extingusher&Blanket 2 11-Feb-13 12-Feb-13 14-Apr-13 15-Apr-13 53 Two BedroTwo Bedroom Flats 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21 FinishingFinishing Works 332 06-Aug-12 08-Sep-13 06-Aug-12 02-Oct-13 21 Wet WoWet Works 82 06-Aug-12 13-Nov-12 06-Aug-12 23-Feb-13 83 A37450 Block Works 15 06-Aug-12 25-Aug-12 06-Aug-12 25-Aug-12 0 A37310 Installation of Doors& Windows Sub-frame 7 04-Sep-12 11-Sep-12 16-Feb-13 23-Feb-13 135 A37300 Plaster Works 20 04-Sep-12 26-Sep-12 04-Sep-12 26-Sep-12 0 A37330 Installation of Suspended Ceiling Grid (Dry Area) 9 01-Oct-12 10-Oct-12 01-Oct-12 10-Oct-12 0 A37320 1st Coat Paint 18 11-Oct-12 03-Nov-12 11-Oct-12 03-Nov-12 0 A37780 Wall Tiles Work (Wet Area) 13 30-Oct-12 13-Nov-12 06-Dec-12 20-Dec-12 30 Fisrt StaFisrt Stage Finishes 73 27-Nov-12 23-Feb-13 27-Nov-12 04-Apr-13 35 A37340 Suspended Ceiling Tiles (DryArea) 12 27-Nov-12 11-Dec-12 27-Nov-12 11-Dec-12 0 A37380 Installation of Wardrobes 8 12-Dec-12 20-Dec-12 12-Dec-12 20-Dec-12 0 A37770 Screed Works 9 22-Dec-12 31-Dec-12 22-Dec-12 31-Dec-12 0 A37370 Water Proofing for Wet Area 9 02-Jan-13 12-Jan-13 02-Jan-13 12-Jan-13 0 A37360 Floor & Wall Tiles Work (Dry Area) 12 02-Jan-13 15-Jan-13 23-Mar-13 04-Apr-13 67 A37810 Installation of Suspended Ceiling Grid (Wet Area) 7 13-Jan-13 20-Jan-13 13-Jan-13 20-Jan-13 0 A37800 Suspended Ceiling Tiles (Wet Area) 10 21-Jan-13 02-Feb-13 21-Jan-13 02-Feb-13 0 A37790 Floor Tiles Work (Wet Area) 5 18-Feb-13 23-Feb-13 18-Feb-13 23-Feb-13 0 SecondSecond Stage Finishes 19 24-Feb-13 17-Mar-13 24-Feb-13 04-Apr-13 16 A37390 Installation of Windows&Doors 7 24-Feb-13 03-Mar-13 24-Feb-13 03-Mar-13 0 A37460 Doors Ironmongery 6 27-Feb-13 05-Mar-13 30-Mar-13 04-Apr-13 26 A37430 Installation of Balustrades& Handrails 5 04-Mar-13 09-Mar-13 31-Mar-13 04-Apr-13 23 A37400 Installation of Mirrors 9 04-Mar-13 13-Mar-13 26-Mar-13 04-Apr-13 19 A37440 Installation of Vanity Counter 9 04-Mar-13 13-Mar-13 18-Mar-13 27-Mar-13 12 A37410 Installation of Kitchen Cabinets 10 04-Mar-13 14-Mar-13 17-Mar-13 27-Mar-13 11 A37750 Installation of Toliets Accessories 12 04-Mar-13 17-Mar-13 13-Mar-13 26-Mar-13 8 Final StFinal Stage Finishes 148 18-Mar-13 08-Sep-13 06-Apr-13 02-Oct-13 21 A37350 Final Coat Paint 9 18-Mar-13 27-Mar-13 06-Apr-13 15-Apr-13 16 A37420 Installation of Carpets 4 28-Mar-13 01-Apr-13 22-Apr-13 25-Apr-13 21 A37760 Installation of Sinages 7 25-Mar-13 01-Apr-13 18-Apr-13 25-Apr-13 21 A37470 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 160 26-Aug-12 06-Mar-13 26-Aug-12 15-Apr-13 34 HVACHVAC 135 26-Aug-12 05-Feb-13 20-Sep-12 05-Mar-13 24 A37480 Duct Installation & Insulation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22 A37490 Chilled Water Pipe Installation & Insulation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22 A37500 Condensate Pipe Installation 7 26-Aug-12 02-Sep-12 20-Sep-12 27-Sep-12 22 A37510 FCU Installation 2 03-Sep-12 04-Sep-12 29-Sep-12 30-Sep-12 22 A37520 Air-Outlet Installation 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24 ElectricElectrical 136 26-Aug-12 06-Feb-13 01-Sep-12 05-Mar-13 23 A37530 Install Conduits in Wall 3 26-Aug-12 28-Aug-12 01-Sep-12 03-Sep-12 5 A37540 Install Cable Trays & Trunking 4 26-Aug-12 29-Aug-12 20-Sep-12 24-Sep-12 22 A37580 Cable Laying for Low Current System 3 30-Aug-12 02-Sep-12 08-Oct-12 10-Oct-12 33 A37590 Cable Laying for Power 3 30-Aug-12 02-Sep-12 08-Oct-12 10-Oct-12 33 A37550 Wiring for Lighting & Power 3 27-Sep-12 30-Sep-12 27-Sep-12 30-Sep-12 0 A37560 Wiring for Low Current System 3 27-Sep-12 30-Sep-12 27-Sep-12 30-Sep-12 0 A37570 DB installation,Dressing & Termination 6 04-Nov-12 10-Nov-12 05-Dec-12 11-Dec-12 25 A37620 Installation of Sockets 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24 A37610 Installation of Lighting Fittings 4 03-Feb-13 06-Feb-13 20-Feb-13 24-Feb-13 15 PlumbinPlumbing 160 26-Aug-12 06-Mar-13 26-Aug-12 06-Mar-13 0 A37640 H/L Drainage Pipes Installation 4 26-Aug-12 29-Aug-12 03-Jan-13 07-Jan-13 107 A37650 H/L Hot&Cold Water Pipe Installation 4 26-Aug-12 29-Aug-12 03-Jan-13 07-Jan-13 107 A37630 Drainge Pipes in Wall 8 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0 A37660 Drainage&Water Pipes Testing 4 30-Aug-12 03-Sep-12 08-Jan-13 12-Jan-13 107 A37670 ElectricalWater Heater Installation 4 30-Aug-12 03-Sep-12 08-Jan-13 12-Jan-13 107 A37700 Water Pipes in Wall 8 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0 A37680 Floor Drain Fixning 3 24-Dec-12 26-Dec-12 17-Feb-13 19-Feb-13 45 A37690 Installation of Sanitaryware 3 04-Mar-13 06-Mar-13 04-Mar-13 06-Mar-13 0 Fire FigFire Fighting 129 04-Sep-12 07-Feb-13 24-Sep-12 15-Apr-13 57 A37740 Fire Fighting Pipe 3 04-Sep-12 06-Sep-12 24-Sep-12 26-Sep-12 17 A37730 Hydro Static Test for Pipes 3 08-Sep-12 10-Sep-12 27-Sep-12 30-Sep-12 17 A37720 Sprinkler Fixing 3 03-Feb-13 05-Feb-13 24-Feb-13 26-Feb-13 18 A37820 Fire Alarm Devices 3 03-Feb-13 05-Feb-13 24-Mar-13 26-Mar-13 42 A37710 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 14-Apr-13 15-Apr-13 57 4th Floor4th Floor 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21 Public AreaPublic Area 167 19-Sep-12 08-Apr-13 07-Nov-12 25-Apr-13 15 Garbage RGarbage Room 129 29-Sep-12 04-Mar-13 15-Jan-13 25-Apr-13 45 FinishingFinishing Works 129 29-Sep-12 04-Mar-13 15-Jan-13 25-Apr-13 45 Wet WorWet Works 43 29-Sep-12 20-Nov-12 15-Jan-13 22-Apr-13 128 A17550 Block Works 3 29-Sep-12 01-Oct-12 15-Jan-13 17-Jan-13 88 A17500 Installation of Doors& Windows Sub-frame 1 07-Nov-12 07-Nov-12 22-Apr-13 22-Apr-13 138 A17490 Plaster Works 3 07-Nov-12 10-Nov-12 23-Jan-13 27-Jan-13 63 A17530 Wall Tiles Work 4 13-Nov-12 18-Nov-12 30-Jan-13 03-Feb-13 63 A17510 1st Coat Paint 2 19-Nov-12 20-Nov-12 04-Feb-13 05-Feb-13 63 Fisrt StaFisrt Stage Finishes 85 21-Nov-12 03-Mar-13 23-Feb-13 24-Apr-13 45 A17680 Screed Works 2 21-Nov-12 22-Nov-12 23-Feb-13 24-Feb-13 77 A17700 Floor Tiles Work 2 25-Nov-12 26-Nov-12 26-Feb-13 27-Feb-13 77 A17560 Doors Ironmongery 1 02-Mar-13 02-Mar-13 24-Apr-13 24-Apr-13 46 A17540 Installation of Doors 2 02-Mar-13 03-Mar-13 23-Apr-13 24-Apr-13 45 Second SSecond Stage Finishes 2 29-Nov-12 01-Dec-12 07-Apr-13 08-Apr-13 107 A17520 Final Coat Paint 2 29-Nov-12 01-Dec-12 07-Apr-13 08-Apr-13 107 Final StaFinal Stage Finishes 1 04-Mar-13 04-Mar-13 25-Apr-13 25-Apr-13 45 A17670 Installation of Sinages 1 04-Mar-13 04-Mar-13 25-Apr-13 25-Apr-13 45 MEP WorkMEP Works 47 02-Oct-12 28-Nov-12 19-Jan-13 06-Apr-13 107 ElectricalElectrical 47 02-Oct-12 28-Nov-12 21-Jan-13 05-Mar-13 80 A17570 Install Conduits in Wall 2 02-Oct-12 03-Oct-12 21-Jan-13 22-Jan-13 90 A17580 Wiring for Lighting & Power 2 11-Nov-12 12-Nov-12 28-Jan-13 29-Jan-13 63 A17590 Installation of Lighting Fittings 2 27-Nov-12 28-Nov-12 04-Mar-13 05-Mar-13 80 PlumbingPlumbing 43 02-Oct-12 24-Nov-12 19-Jan-13 25-Feb-13 77 A17600 Drainge Pipes in Wall 2 02-Oct-12 03-Oct-12 19-Jan-13 20-Jan-13 88 A17630 Water Pipes in Wall 2 02-Oct-12 03-Oct-12 19-Jan-13 20-Jan-13 88 A17610 Drainage&Water Pipes Testing 2 04-Oct-12 06-Oct-12 21-Jan-13 22-Jan-13 88 A17620 Floor Drain Fixning 1 24-Nov-12 24-Nov-12 25-Feb-13 25-Feb-13 77 Fire FighFire Fighting 46 03-Oct-12 28-Nov-12 25-Feb-13 06-Apr-13 107 A17660 Fire Fighting Pipe 2 03-Oct-12 04-Oct-12 25-Feb-13 26-Feb-13 118 A17650 Hydro Static Test for Pipes 2 06-Oct-12 07-Oct-12 02-Mar-13 03-Mar-13 120 A17640 Sprinkler Fixing 2 27-Nov-12 28-Nov-12 04-Mar-13 05-Mar-13 80 A17690 Fire Alarm Devices 2 27-Nov-12 28-Nov-12 04-Apr-13 06-Apr-13 107 Corridor &Corridor & Lift Lobby 167 19-Sep-12 08-Apr-13 15-Dec-12 25-Apr-13 15 FinishingFinishing Works 167 19-Sep-12 08-Apr-13 15-Dec-12 25-Apr-13 15 Wet WorWet Works 120 19-Sep-12 12-Feb-13 15-Dec-12 02-Apr-13 42 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Water Pipes in Wall Drainge Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Wall Tiles Work (Wet Area) Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 36 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 37. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A17210 Block Works 8 19-Sep-12 27-Sep-12 15-Dec-12 23-Dec-12 70 A17150 Plaster Works 7 30-Oct-12 06-Nov-12 26-Dec-12 03-Jan-13 47 A17170 Installation of Suspended Ceiling Grid 6 12-Nov-12 19-Nov-12 09-Jan-13 15-Jan-13 47 A17180 Suspended Ceiling Tiles 6 05-Feb-13 11-Feb-13 21-Feb-13 27-Feb-13 14 A17470 MDF for Lift Lobby Wall 7 05-Feb-13 12-Feb-13 26-Mar-13 02-Apr-13 42 Fisrt StaFisrt Stage Finishes 12 13-Feb-13 26-Feb-13 03-Apr-13 11-Apr-13 38 A17450 Screed Works 3 13-Feb-13 16-Feb-13 03-Apr-13 06-Apr-13 42 A17160 1st Coat Paint 5 21-Feb-13 26-Feb-13 07-Apr-13 11-Apr-13 38 Second SSecond Stage Finishes 2 27-Feb-13 28-Feb-13 20-Apr-13 25-Apr-13 48 A17190 Installation of Doors 2 27-Feb-13 28-Feb-13 20-Apr-13 21-Apr-13 44 A17220 Doors Ironmongery 2 27-Feb-13 28-Feb-13 24-Apr-13 25-Apr-13 48 Final StaFinal Stage Finishes 12 26-Mar-13 08-Apr-13 13-Apr-13 25-Apr-13 15 A17200 Installation of Carpets 4 26-Mar-13 30-Mar-13 13-Apr-13 16-Apr-13 15 A17460 Fixing of Wall Covering 5 31-Mar-13 04-Apr-13 17-Apr-13 22-Apr-13 15 A17440 Installation of Sinages 3 06-Apr-13 08-Apr-13 23-Apr-13 25-Apr-13 15 MEP WorkMEP Works 119 29-Sep-12 20-Feb-13 24-Dec-12 06-Apr-13 38 HVACHVAC 114 29-Sep-12 14-Feb-13 30-Dec-12 05-Mar-13 16 A17240 Chilled Water Pipe Installation & Insulation 5 29-Sep-12 03-Oct-12 30-Dec-12 05-Jan-13 75 A17250 Condensate Pipe Installation 5 29-Sep-12 03-Oct-12 30-Dec-12 05-Jan-13 75 A17230 Duct Installation & Insulation 5 03-Oct-12 08-Oct-12 30-Dec-12 05-Jan-13 71 A17260 FCU Installation 3 09-Oct-12 11-Oct-12 06-Jan-13 08-Jan-13 71 A17270 Air-Outlet Installation 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 ElectricalElectrical 116 29-Sep-12 17-Feb-13 24-Dec-12 05-Mar-13 14 A17280 Install Conduits in Wall 2 29-Sep-12 30-Sep-12 24-Dec-12 25-Dec-12 70 A17290 Install Cable Trays & Trunking 2 29-Sep-12 30-Sep-12 30-Dec-12 31-Dec-12 75 A17330 Cable Laying for Low Current System 2 01-Oct-12 02-Oct-12 14-Jan-13 15-Jan-13 85 A17340 Cable Laying for Power 3 01-Oct-12 03-Oct-12 13-Jan-13 15-Jan-13 84 A17300 Wiring for Lighting & Power 3 07-Nov-12 10-Nov-12 06-Jan-13 08-Jan-13 48 A17310 Wiring for Low Current System 4 07-Nov-12 11-Nov-12 05-Jan-13 08-Jan-13 47 A17320 DB installation,Dressing & Termination 6 20-Nov-12 26-Nov-12 21-Feb-13 27-Feb-13 77 A17360 Installation of Lighting Fittings 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 A17370 Installation of Sockets 5 12-Feb-13 17-Feb-13 28-Feb-13 05-Mar-13 14 PlumbingPlumbing 5 29-Sep-12 03-Oct-12 03-Jan-13 08-Jan-13 78 A17380 H/L Hot&Cold Water Pipe Installation 5 29-Sep-12 03-Oct-12 03-Jan-13 08-Jan-13 78 Fire FighFire Fighting 119 29-Sep-12 20-Feb-13 30-Dec-12 06-Apr-13 38 A17430 Fire Fighting Pipe 4 29-Sep-12 02-Oct-12 30-Dec-12 03-Jan-13 75 A17420 Hydro Static Test for Pipes 4 03-Oct-12 07-Oct-12 05-Jan-13 08-Jan-13 75 A17410 Sprinkler Fixing 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15 A17480 Fire Alarm Devices 5 12-Feb-13 17-Feb-13 01-Apr-13 06-Apr-13 41 A17400 Installation of Fire Extingusher&Blanket 4 17-Feb-13 20-Feb-13 02-Apr-13 06-Apr-13 38 Electrical /Electrical /Telephone/ELV Rooms 127 02-Oct-12 05-Mar-13 23-Jan-13 25-Apr-13 44 FinishingFinishing Works 127 02-Oct-12 05-Mar-13 23-Jan-13 25-Apr-13 44 Wet WorWet Works 43 02-Oct-12 24-Nov-12 23-Jan-13 21-Apr-13 124 A17760 Block Works 3 02-Oct-12 04-Oct-12 23-Jan-13 27-Jan-13 92 A17720 Installation of Doors& Windows Sub-frame 1 11-Nov-12 11-Nov-12 21-Apr-13 21-Apr-13 134 A17710 Plaster Works 4 11-Nov-12 14-Nov-12 30-Jan-13 03-Feb-13 65 A17730 1st Coat Paint 3 21-Nov-12 24-Nov-12 06-Feb-13 09-Feb-13 63 Fisrt StaFisrt Stage Finishes 61 20-Dec-12 03-Mar-13 08-Apr-13 23-Apr-13 44 A17820 Epoxy Paint Works 2 20-Dec-12 22-Dec-12 08-Apr-13 09-Apr-13 91 A17750 Installation of Doors 2 02-Mar-13 03-Mar-13 22-Apr-13 23-Apr-13 44 A17770 Doors Ironmongery 2 02-Mar-13 03-Mar-13 22-Apr-13 23-Apr-13 44 Second SSecond Stage Finishes 2 23-Dec-12 24-Dec-12 10-Apr-13 11-Apr-13 91 A17740 Final Coat Paint 2 23-Dec-12 24-Dec-12 10-Apr-13 11-Apr-13 91 Final StaFinal Stage Finishes 2 04-Mar-13 05-Mar-13 24-Apr-13 25-Apr-13 44 A17810 Installation of Sinages 2 04-Mar-13 05-Mar-13 24-Apr-13 25-Apr-13 44 MEP WorkMEP Works 61 06-Oct-12 19-Dec-12 28-Jan-13 07-Apr-13 91 HVACHVAC 2 25-Nov-12 26-Nov-12 04-Mar-13 05-Mar-13 82 A17850 Air-Outlet Installation 2 25-Nov-12 26-Nov-12 04-Mar-13 05-Mar-13 82 ElectricalElectrical 61 06-Oct-12 19-Dec-12 28-Jan-13 05-Mar-13 63 A17780 Install Conduits in Wall 2 06-Oct-12 07-Oct-12 28-Jan-13 29-Jan-13 92 A17790 Wiring for Lighting & Power 2 17-Nov-12 18-Nov-12 04-Feb-13 05-Feb-13 65 A17840 Installation of SMDBs 7 25-Nov-12 03-Dec-12 24-Feb-13 03-Mar-13 75 A17800 Installation of Lighting Fittings 2 04-Dec-12 05-Dec-12 04-Mar-13 05-Mar-13 75 A114490 Installation of Access ControlSystem 20 25-Nov-12 18-Dec-12 11-Feb-13 05-Mar-13 64 A114470 Installation of MATC,TV System 20 25-Nov-12 18-Dec-12 11-Feb-13 05-Mar-13 64 A114480 Installation of Telephone System 21 25-Nov-12 19-Dec-12 10-Feb-13 05-Mar-13 63 Fire FighFire Fighting 2 06-Dec-12 08-Dec-12 06-Apr-13 07-Apr-13 101 A17830 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 06-Apr-13 07-Apr-13 101 Room ServRoom Service 112 06-Oct-12 19-Feb-13 07-Feb-13 25-Apr-13 56 FinishingFinishing Works 112 06-Oct-12 19-Feb-13 07-Feb-13 25-Apr-13 56 Wet WorWet Works 43 06-Oct-12 27-Nov-12 07-Feb-13 17-Apr-13 118 A17910 Block Works 2 06-Oct-12 07-Oct-12 07-Feb-13 09-Feb-13 101 A17870 Installation of Doors& Windows Sub-frame 1 17-Nov-12 17-Nov-12 17-Apr-13 17-Apr-13 127 A17860 Plaster Works 4 17-Nov-12 20-Nov-12 14-Feb-13 18-Feb-13 74 A17880 1st Coat Paint 3 25-Nov-12 27-Nov-12 21-Feb-13 24-Feb-13 73 Fisrt StaFisrt Stage Finishes 68 28-Nov-12 18-Feb-13 25-Feb-13 24-Apr-13 56 A18040 Screed Works 2 28-Nov-12 29-Nov-12 25-Feb-13 26-Feb-13 73 A18060 Floor Tiles Work 3 03-Dec-12 05-Dec-12 28-Feb-13 03-Mar-13 73 A17900 Installation of Doors 1 18-Feb-13 18-Feb-13 18-Apr-13 18-Apr-13 51 A17920 Doors Ironmongery 1 18-Feb-13 18-Feb-13 24-Apr-13 24-Apr-13 56 Second SSecond Stage Finishes 1 09-Dec-12 09-Dec-12 09-Apr-13 09-Apr-13 102 A17890 Final Coat Paint 1 09-Dec-12 09-Dec-12 09-Apr-13 09-Apr-13 102 Final StaFinal Stage Finishes 1 19-Feb-13 19-Feb-13 25-Apr-13 25-Apr-13 56 A18030 Installation of Sinages 1 19-Feb-13 19-Feb-13 25-Apr-13 25-Apr-13 56 MEP WorkMEP Works 49 08-Oct-12 08-Dec-12 10-Feb-13 08-Apr-13 102 HVACHVAC 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 A18070 Air-Outlet Installation 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 ElectricalElectrical 49 08-Oct-12 08-Dec-12 12-Feb-13 05-Mar-13 73 A17930 Install Conduits in Wall 2 08-Oct-12 09-Oct-12 12-Feb-13 13-Feb-13 103 A17940 Wiring for Lighting & Power 2 21-Nov-12 22-Nov-12 19-Feb-13 20-Feb-13 74 A17950 Installation of Lighting Fittings 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 PlumbingPlumbing 44 08-Oct-12 01-Dec-12 10-Feb-13 27-Feb-13 73 A17960 Drainge Pipes in Wall 2 08-Oct-12 09-Oct-12 10-Feb-13 11-Feb-13 101 A17990 Water Pipes in Wall 2 08-Oct-12 09-Oct-12 10-Feb-13 11-Feb-13 101 A17970 Drainage&Water Pipes Testing 2 10-Oct-12 11-Oct-12 12-Feb-13 13-Feb-13 101 A17980 Floor Drain Fixning 1 01-Dec-12 01-Dec-12 27-Feb-13 27-Feb-13 73 Fire FighFire Fighting 49 08-Oct-12 08-Dec-12 27-Feb-13 08-Apr-13 102 A18020 Fire Fighting Pipe 2 08-Oct-12 09-Oct-12 27-Feb-13 28-Feb-13 116 A18010 Hydro Static Test for Pipes 2 10-Oct-12 11-Oct-12 02-Mar-13 03-Mar-13 116 A18000 Sprinkler Fixing 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 A18050 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 07-Apr-13 08-Apr-13 102 StaircaseStaircase 118 24-Sep-12 14-Feb-13 07-Nov-12 11-Apr-13 48 Stair 1Stair 1 104 24-Sep-12 29-Jan-13 07-Nov-12 11-Apr-13 62 A108530 Floor Screed 3 24-Sep-12 26-Sep-12 07-Nov-12 10-Nov-12 36 A108540 Install Handrails 4 10-Dec-12 13-Dec-12 05-Jan-13 08-Jan-13 21 A108550 Ceiling 1st Coat Paint 7 15-Dec-12 22-Dec-12 09-Jan-13 16-Jan-13 21 A108560 Wall 1st Coat Paint 7 23-Dec-12 30-Dec-12 17-Jan-13 26-Jan-13 21 A108570 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 03-Feb-13 16-Feb-13 27 A108580 Final Coat Paint 12 15-Jan-13 29-Jan-13 30-Mar-13 11-Apr-13 62 Stair 2Stair 2 115 27-Sep-12 14-Feb-13 11-Nov-12 11-Apr-13 48 A108590 Floor Screed 3 27-Sep-12 30-Sep-12 11-Nov-12 13-Nov-12 36 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access ControlSystem Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 37 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 38. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A108600 Install Handrails 4 15-Dec-12 18-Dec-12 21-Jan-13 26-Jan-13 31 A108610 Ceiling 1st Coat Paint 7 31-Dec-12 08-Jan-13 27-Jan-13 03-Feb-13 21 A108620 Wall 1st Coat Paint 7 09-Jan-13 16-Jan-13 04-Feb-13 11-Feb-13 21 A108630 Install Granite/Terrazo 12 17-Jan-13 31-Jan-13 17-Feb-13 02-Mar-13 25 A108640 Final Coat Paint 12 02-Feb-13 14-Feb-13 30-Mar-13 11-Apr-13 48 ApartementsApartements 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21 Studio FlatsStudio Flats 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21 FinishingFinishing Works 300 15-Sep-12 08-Sep-13 28-Nov-12 02-Oct-13 21 Wet WoWet Works 62 15-Sep-12 28-Nov-12 28-Nov-12 11-Mar-13 85 A37980 Block Works 4 15-Sep-12 18-Sep-12 28-Nov-12 03-Dec-12 61 A37840 Installation of Doors& Windows Sub-frame 1 20-Oct-12 20-Oct-12 11-Mar-13 11-Mar-13 116 A37830 Plaster Works 7 20-Oct-12 29-Oct-12 09-Dec-12 16-Dec-12 39 A37860 Installation of Suspended Ceiling Grid (Dry Area) 3 03-Nov-12 05-Nov-12 20-Dec-12 23-Dec-12 39 A38310 Wall Tiles Work (Wet Area) 8 03-Nov-12 11-Nov-12 27-Dec-12 06-Jan-13 45 A37850 1st Coat Paint 3 26-Nov-12 28-Nov-12 24-Dec-12 26-Dec-12 23 Fisrt StaFisrt Stage Finishes 54 09-Dec-12 11-Feb-13 27-Dec-12 13-Mar-13 26 A37870 Suspended Ceiling Tiles (DryArea) 6 09-Dec-12 15-Dec-12 27-Dec-12 03-Jan-13 16 A37910 Installation of Wardrobes 2 18-Dec-12 19-Dec-12 05-Jan-13 06-Jan-13 14 A38300 Screed Works 5 20-Dec-12 25-Dec-12 07-Jan-13 12-Jan-13 14 A37900 Water Proofing for Wet Area 3 26-Dec-12 29-Dec-12 13-Jan-13 15-Jan-13 14 A37890 Floor & Wall Tiles Work (Dry Area) 4 26-Dec-12 30-Dec-12 10-Mar-13 13-Mar-13 61 A38340 Installation of Suspended Ceiling Grid (Wet Area) 3 30-Dec-12 02-Jan-13 16-Jan-13 19-Jan-13 14 A38330 Suspended Ceiling Tiles (Wet Area) 2 03-Feb-13 04-Feb-13 19-Feb-13 20-Feb-13 14 A38320 Floor Tiles Work (Wet Area) 2 10-Feb-13 11-Feb-13 10-Mar-13 11-Mar-13 24 SecondSecond Stage Finishes 15 16-Feb-13 04-Mar-13 12-Mar-13 25-Mar-13 18 A37920 Installation of Windows&Doors 2 16-Feb-13 17-Feb-13 12-Mar-13 13-Mar-13 21 A37990 Doors Ironmongery 2 16-Feb-13 17-Feb-13 24-Mar-13 25-Mar-13 31 A37940 Installation of Kitchen Cabinets 2 18-Feb-13 19-Feb-13 14-Mar-13 16-Mar-13 21 A37960 Installation of Balustrades& Handrails 2 18-Feb-13 19-Feb-13 24-Mar-13 25-Mar-13 29 A37970 Installation of Vanity Counter 2 18-Feb-13 19-Feb-13 14-Mar-13 16-Mar-13 21 A37930 Installation of Mirrors 2 26-Feb-13 27-Feb-13 24-Mar-13 25-Mar-13 22 A38280 Installation of Toliets Accessories 2 03-Mar-13 04-Mar-13 24-Mar-13 25-Mar-13 18 Final StFinal Stage Finishes 156 09-Mar-13 08-Sep-13 26-Mar-13 02-Oct-13 21 A37880 Final Coat Paint 6 09-Mar-13 14-Mar-13 26-Mar-13 01-Apr-13 15 A37950 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A38290 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A38000 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 127 19-Sep-12 20-Feb-13 04-Dec-12 01-Apr-13 34 HVACHVAC 116 19-Sep-12 07-Feb-13 10-Dec-12 05-Mar-13 22 A38020 Chilled Water Pipe Installation & Insulation 7 19-Sep-12 26-Sep-12 10-Dec-12 17-Dec-12 66 A38030 Condensate Pipe Installation 7 19-Sep-12 26-Sep-12 10-Dec-12 17-Dec-12 66 A38010 Duct Installation & Insulation 7 25-Sep-12 02-Oct-12 10-Dec-12 17-Dec-12 61 A38040 FCU Installation 2 03-Oct-12 04-Oct-12 18-Dec-12 19-Dec-12 61 A38050 Air-Outlet Installation 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22 ElectricElectrical 117 19-Sep-12 09-Feb-13 05-Dec-12 05-Mar-13 21 A38060 Install Conduits in Wall 3 19-Sep-12 22-Sep-12 05-Dec-12 08-Dec-12 62 A38070 Install Cable Trays & Trunking 4 19-Sep-12 23-Sep-12 10-Dec-12 13-Dec-12 66 A38110 Cable Laying for Low Current System 3 24-Sep-12 26-Sep-12 20-Dec-12 23-Dec-12 71 A38120 Cable Laying for Power 3 24-Sep-12 26-Sep-12 20-Dec-12 23-Dec-12 71 A38080 Wiring for Lighting & Power 3 30-Oct-12 01-Nov-12 17-Dec-12 19-Dec-12 39 A38090 Wiring for Low Current System 3 30-Oct-12 01-Nov-12 17-Dec-12 19-Dec-12 39 A38100 DB installation,Dressing & Termination 6 29-Nov-12 06-Dec-12 27-Dec-12 03-Jan-13 23 A38150 Installation of Sockets 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22 A38140 Installation of Lighting Fittings 4 05-Feb-13 09-Feb-13 02-Mar-13 05-Mar-13 21 PlumbinPlumbing 127 19-Sep-12 20-Feb-13 04-Dec-12 25-Mar-13 28 A38170 H/L Drainage Pipes Installation 4 19-Sep-12 23-Sep-12 07-Jan-13 10-Jan-13 89 A38180 H/L Hot&Cold Water Pipe Installation 4 19-Sep-12 23-Sep-12 07-Jan-13 10-Jan-13 89 A38230 Water Pipes in Wall 4 19-Sep-12 23-Sep-12 04-Dec-12 08-Dec-12 61 A38190 Drainage&Water Pipes Testing 4 24-Sep-12 27-Sep-12 12-Jan-13 15-Jan-13 89 A38200 ElectricalWater Heater Installation 4 24-Sep-12 27-Sep-12 12-Jan-13 15-Jan-13 89 A38160 Drainge Pipes in Wall 4 27-Sep-12 01-Oct-12 04-Dec-12 08-Dec-12 54 A38210 Floor Drain Fixning 3 23-Dec-12 25-Dec-12 03-Mar-13 05-Mar-13 58 A38220 Installation of Sanitaryware 3 18-Feb-13 20-Feb-13 23-Mar-13 25-Mar-13 28 Fire FigFire Fighting 118 19-Sep-12 10-Feb-13 13-Dec-12 01-Apr-13 43 A38270 Fire Fighting Pipe 3 19-Sep-12 22-Sep-12 13-Dec-12 16-Dec-12 69 A38260 Hydro Static Test for Pipes 3 23-Sep-12 25-Sep-12 17-Dec-12 19-Dec-12 69 A38250 Sprinkler Fixing 3 05-Feb-13 07-Feb-13 03-Mar-13 05-Mar-13 22 A38350 Fire Alarm Devices 3 05-Feb-13 07-Feb-13 23-Mar-13 25-Mar-13 39 A38240 Installation of Fire Extingusher&Blanket 2 09-Feb-13 10-Feb-13 31-Mar-13 01-Apr-13 43 One BedroOne Bedroom Flats 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21 FinishingFinishing Works 305 09-Sep-12 08-Sep-13 10-Nov-12 02-Oct-13 21 Wet WoWet Works 64 09-Sep-12 25-Nov-12 10-Nov-12 07-Mar-13 85 A38510 Block Works 5 09-Sep-12 13-Sep-12 10-Nov-12 14-Nov-12 51 A38370 Installation of Doors& Windows Sub-frame 1 11-Oct-12 11-Oct-12 07-Mar-13 07-Mar-13 120 A38360 Plaster Works 7 11-Oct-12 18-Oct-12 26-Nov-12 04-Dec-12 36 A38390 Installation of Suspended Ceiling Grid (Dry Area) 4 28-Oct-12 31-Oct-12 09-Dec-12 12-Dec-12 34 A38840 Wall Tiles Work (Wet Area) 4 29-Oct-12 01-Nov-12 23-Dec-12 26-Dec-12 45 A38380 1st Coat Paint 6 19-Nov-12 25-Nov-12 13-Dec-12 19-Dec-12 20 Fisrt StaFisrt Stage Finishes 56 04-Dec-12 09-Feb-13 23-Dec-12 18-Mar-13 32 A38400 Suspended Ceiling Tiles (DryArea) 4 04-Dec-12 08-Dec-12 23-Dec-12 26-Dec-12 16 A38440 Installation of Wardrobes 4 13-Dec-12 17-Dec-12 30-Dec-12 03-Jan-13 14 A38830 Screed Works 9 18-Dec-12 27-Dec-12 06-Jan-13 15-Jan-13 15 A38430 Water Proofing for Wet Area 3 29-Dec-12 31-Dec-12 16-Jan-13 19-Jan-13 15 A38420 Floor & Wall Tiles Work (Dry Area) 4 31-Dec-12 05-Jan-13 14-Mar-13 18-Mar-13 61 A38870 Installation of Suspended Ceiling Grid (Wet Area) 4 03-Jan-13 07-Jan-13 20-Jan-13 23-Jan-13 14 A38860 Suspended Ceiling Tiles (Wet Area) 4 29-Jan-13 02-Feb-13 14-Feb-13 18-Feb-13 14 A38850 Floor Tiles Work (Wet Area) 5 04-Feb-13 09-Feb-13 03-Mar-13 07-Mar-13 23 SecondSecond Stage Finishes 16 12-Feb-13 02-Mar-13 09-Mar-13 19-Mar-13 15 A38450 Installation of Windows&Doors 3 12-Feb-13 14-Feb-13 09-Mar-13 11-Mar-13 21 A38520 Doors Ironmongery 3 12-Feb-13 14-Feb-13 17-Mar-13 19-Mar-13 28 A38490 Installation of Balustrades& Handrails 2 16-Feb-13 17-Feb-13 18-Mar-13 19-Mar-13 26 A38470 Installation of Kitchen Cabinets 3 20-Feb-13 23-Feb-13 17-Mar-13 19-Mar-13 21 A38500 Installation of Vanity Counter 3 20-Feb-13 23-Feb-13 17-Mar-13 19-Mar-13 21 A38460 Installation of Mirrors 3 23-Feb-13 25-Feb-13 17-Mar-13 19-Mar-13 19 A38810 Installation of Toliets Accessories 4 26-Feb-13 02-Mar-13 16-Mar-13 19-Mar-13 15 Final StFinal Stage Finishes 161 03-Mar-13 08-Sep-13 20-Mar-13 02-Oct-13 21 A38410 Final Coat Paint 5 03-Mar-13 07-Mar-13 20-Mar-13 25-Mar-13 15 A38480 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A38820 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A38530 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 129 15-Sep-12 18-Feb-13 17-Nov-12 25-Mar-13 30 HVACHVAC 118 15-Sep-12 05-Feb-13 27-Nov-12 05-Mar-13 24 A38550 Chilled Water Pipe Installation & Insulation 7 15-Sep-12 22-Sep-12 27-Nov-12 05-Dec-12 60 A38560 Condensate Pipe Installation 7 15-Sep-12 22-Sep-12 27-Nov-12 05-Dec-12 60 A38540 Duct Installation & Insulation 7 17-Sep-12 24-Sep-12 27-Nov-12 05-Dec-12 58 A38570 FCU Installation 2 25-Sep-12 26-Sep-12 06-Dec-12 08-Dec-12 58 A38580 Air-Outlet Installation 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24 ElectricElectrical 119 15-Sep-12 06-Feb-13 22-Nov-12 05-Mar-13 23 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Kitchen Cabinets Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Mirrors Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Drainge Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Mirrors Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 38 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 39. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A38590 Install Conduits in Wall 3 15-Sep-12 17-Sep-12 22-Nov-12 25-Nov-12 56 A38600 Install Cable Trays & Trunking 4 15-Sep-12 18-Sep-12 27-Nov-12 01-Dec-12 60 A38640 Cable Laying for Low Current System 3 19-Sep-12 22-Sep-12 10-Dec-12 12-Dec-12 66 A38650 Cable Laying for Power 3 19-Sep-12 22-Sep-12 10-Dec-12 12-Dec-12 66 A38610 Wiring for Lighting & Power 3 20-Oct-12 22-Oct-12 05-Dec-12 08-Dec-12 36 A38620 Wiring for Low Current System 3 20-Oct-12 22-Oct-12 05-Dec-12 08-Dec-12 36 A38630 DB installation,Dressing & Termination 6 26-Nov-12 03-Dec-12 20-Dec-12 26-Dec-12 20 A38680 Installation of Sockets 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24 A38670 Installation of Lighting Fittings 4 03-Feb-13 06-Feb-13 02-Mar-13 05-Mar-13 23 PlumbinPlumbing 129 15-Sep-12 18-Feb-13 17-Nov-12 19-Mar-13 25 A38700 H/L Drainage Pipes Installation 4 15-Sep-12 18-Sep-12 02-Jan-13 06-Jan-13 89 A38710 H/L Hot&Cold Water Pipe Installation 4 15-Sep-12 18-Sep-12 10-Jan-13 14-Jan-13 96 A38720 Drainage&Water Pipes Testing 4 19-Sep-12 23-Sep-12 15-Jan-13 19-Jan-13 96 A38730 ElectricalWater Heater Installation 4 19-Sep-12 23-Sep-12 15-Jan-13 19-Jan-13 96 A38760 Water Pipes in Wall 8 15-Sep-12 23-Sep-12 17-Nov-12 25-Nov-12 51 A38690 Drainge Pipes in Wall 8 18-Sep-12 26-Sep-12 17-Nov-12 25-Nov-12 48 A38740 Floor Drain Fixning 3 20-Dec-12 23-Dec-12 02-Mar-13 04-Mar-13 59 A38750 Installation of Sanitaryware 3 16-Feb-13 18-Feb-13 17-Mar-13 19-Mar-13 25 Fire FigFire Fighting 120 15-Sep-12 07-Feb-13 01-Dec-12 25-Mar-13 39 A38800 Fire Fighting Pipe 3 15-Sep-12 17-Sep-12 01-Dec-12 04-Dec-12 63 A38790 Hydro Static Test for Pipes 3 18-Sep-12 20-Sep-12 05-Dec-12 08-Dec-12 63 A38780 Sprinkler Fixing 3 03-Feb-13 05-Feb-13 03-Mar-13 05-Mar-13 24 A38880 Fire Alarm Devices 3 03-Feb-13 05-Feb-13 17-Mar-13 19-Mar-13 36 A38770 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 24-Mar-13 25-Mar-13 39 Two BedroTwo Bedroom Flats 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21 FinishingFinishing Works 320 22-Aug-12 08-Sep-13 08-Sep-12 02-Oct-13 21 Wet WoWet Works 73 22-Aug-12 18-Nov-12 08-Sep-12 20-Feb-13 78 A39040 Block Works 15 22-Aug-12 08-Sep-12 08-Sep-12 24-Sep-12 14 A38900 Installation of Doors& Windows Sub-frame 7 18-Sep-12 25-Sep-12 13-Feb-13 20-Feb-13 121 A38890 Plaster Works 20 18-Sep-12 10-Oct-12 04-Oct-12 29-Oct-12 14 A38920 Installation of Suspended Ceiling Grid (Dry Area) 9 15-Oct-12 24-Oct-12 03-Nov-12 12-Nov-12 14 A39370 Wall Tiles Work (Wet Area) 13 11-Oct-12 28-Oct-12 08-Dec-12 22-Dec-12 45 A38910 1st Coat Paint 18 28-Oct-12 18-Nov-12 13-Nov-12 05-Dec-12 14 Fisrt StaFisrt Stage Finishes 63 19-Nov-12 03-Feb-13 06-Dec-12 01-Apr-13 49 A38930 Suspended Ceiling Tiles (DryArea) 12 19-Nov-12 03-Dec-12 06-Dec-12 19-Dec-12 14 A38970 Installation of Wardrobes 8 04-Dec-12 12-Dec-12 20-Dec-12 29-Dec-12 14 A39360 Screed Works 9 13-Dec-12 23-Dec-12 03-Jan-13 13-Jan-13 17 A38960 Water Proofing for Wet Area 9 24-Dec-12 03-Jan-13 14-Jan-13 23-Jan-13 17 A39400 Installation of Suspended Ceiling Grid (Wet Area) 7 08-Jan-13 15-Jan-13 26-Jan-13 02-Feb-13 14 A38950 Floor & Wall Tiles Work (Dry Area) 12 06-Jan-13 19-Jan-13 19-Mar-13 01-Apr-13 61 A39390 Suspended Ceiling Tiles (Wet Area) 10 16-Jan-13 28-Jan-13 03-Feb-13 13-Feb-13 14 A39380 Floor Tiles Work (Wet Area) 5 29-Jan-13 03-Feb-13 16-Feb-13 20-Feb-13 15 SecondSecond Stage Finishes 27 04-Feb-13 06-Mar-13 21-Feb-13 01-Apr-13 22 A38980 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 21-Feb-13 28-Feb-13 15 A39050 Doors Ironmongery 6 07-Feb-13 13-Feb-13 26-Mar-13 01-Apr-13 40 A39020 Installation of Balustrades& Handrails 5 12-Feb-13 17-Feb-13 27-Mar-13 01-Apr-13 37 A38990 Installation of Mirrors 9 12-Feb-13 21-Feb-13 06-Mar-13 16-Mar-13 19 A39340 Installation of Toliets Accessories 12 12-Feb-13 25-Feb-13 02-Mar-13 14-Mar-13 15 A39030 Installation of Vanity Counter 9 24-Feb-13 05-Mar-13 23-Mar-13 01-Apr-13 23 A39000 Installation of Kitchen Cabinets 10 24-Feb-13 06-Mar-13 21-Mar-13 01-Apr-13 22 Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 02-Apr-13 02-Oct-13 21 A38940 Final Coat Paint 9 16-Mar-13 25-Mar-13 02-Apr-13 11-Apr-13 15 A39010 Installation of Carpets 4 26-Mar-13 30-Mar-13 22-Apr-13 25-Apr-13 23 A39350 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23 A39060 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 131 09-Sep-12 14-Feb-13 25-Sep-12 11-Apr-13 48 HVACHVAC 119 09-Sep-12 31-Jan-13 21-Oct-12 05-Mar-13 28 A39070 Duct Installation & Insulation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36 A39080 Chilled Water Pipe Installation & Insulation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36 A39090 Condensate Pipe Installation 7 09-Sep-12 16-Sep-12 21-Oct-12 30-Oct-12 36 A39100 FCU Installation 2 17-Sep-12 18-Sep-12 31-Oct-12 01-Nov-12 36 A39110 Air-Outlet Installation 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 ElectricElectrical 120 09-Sep-12 02-Feb-13 01-Oct-12 05-Mar-13 27 A39120 Install Conduits in Wall 3 09-Sep-12 11-Sep-12 01-Oct-12 03-Oct-12 19 A39130 Install Cable Trays & Trunking 4 09-Sep-12 12-Sep-12 21-Oct-12 24-Oct-12 36 A39170 Cable Laying for Low Current System 3 13-Sep-12 16-Sep-12 10-Nov-12 12-Nov-12 47 A39180 Cable Laying for Power 3 13-Sep-12 16-Sep-12 10-Nov-12 12-Nov-12 47 A39140 Wiring for Lighting & Power 3 11-Oct-12 14-Oct-12 30-Oct-12 01-Nov-12 14 A39150 Wiring for Low Current System 3 11-Oct-12 14-Oct-12 30-Oct-12 01-Nov-12 14 A39160 DB installation,Dressing & Termination 6 19-Nov-12 25-Nov-12 13-Dec-12 19-Dec-12 20 A39210 Installation of Sockets 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 A39200 Installation of Lighting Fittings 4 29-Jan-13 02-Feb-13 02-Mar-13 05-Mar-13 27 PlumbinPlumbing 131 09-Sep-12 14-Feb-13 25-Sep-12 01-Apr-13 39 A39230 H/L Drainage Pipes Installation 4 09-Sep-12 12-Sep-12 27-Dec-12 31-Dec-12 90 A39240 H/L Hot&Cold Water Pipe Installation 4 09-Sep-12 12-Sep-12 15-Jan-13 19-Jan-13 105 A39220 Drainge Pipes in Wall 8 09-Sep-12 17-Sep-12 25-Sep-12 03-Oct-12 14 A39250 Drainage&Water Pipes Testing 4 13-Sep-12 17-Sep-12 20-Jan-13 23-Jan-13 105 A39260 ElectricalWater Heater Installation 4 13-Sep-12 17-Sep-12 20-Jan-13 23-Jan-13 105 A39290 Water Pipes in Wall 8 09-Sep-12 17-Sep-12 25-Sep-12 03-Oct-12 14 A39270 Floor Drain Fixning 3 16-Dec-12 18-Dec-12 14-Feb-13 17-Feb-13 50 A39280 Installation of Sanitaryware 3 12-Feb-13 14-Feb-13 30-Mar-13 01-Apr-13 39 Fire FigFire Fighting 121 09-Sep-12 03-Feb-13 24-Oct-12 11-Apr-13 58 A39330 Fire Fighting Pipe 3 09-Sep-12 11-Sep-12 24-Oct-12 29-Oct-12 39 A39320 Hydro Static Test for Pipes 3 12-Sep-12 15-Sep-12 30-Oct-12 01-Nov-12 39 A39310 Sprinkler Fixing 3 29-Jan-13 31-Jan-13 03-Mar-13 05-Mar-13 28 A39410 Fire Alarm Devices 3 29-Jan-13 31-Jan-13 30-Mar-13 01-Apr-13 51 A39300 Installation of Fire Extingusher&Blanket 2 02-Feb-13 03-Feb-13 10-Apr-13 11-Apr-13 58 5th Floor5th Floor 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21 Public AreaPublic Area 153 03-Oct-12 06-Apr-13 14-Nov-12 25-Apr-13 17 Garbage RGarbage Room 73 13-Oct-12 10-Jan-13 15-Jan-13 25-Apr-13 89 FinishingFinishing Works 73 13-Oct-12 10-Jan-13 15-Jan-13 25-Apr-13 89 Wet WorWet Works 63 13-Oct-12 29-Dec-12 15-Jan-13 28-Feb-13 51 A18480 Block Works 3 13-Oct-12 15-Oct-12 15-Jan-13 17-Jan-13 76 A18430 Installation of Doors& Windows Sub-frame 1 22-Nov-12 22-Nov-12 28-Feb-13 28-Feb-13 81 A18420 Plaster Works 3 22-Nov-12 25-Nov-12 23-Jan-13 27-Jan-13 51 A18460 Wall Tiles Work 4 28-Nov-12 03-Dec-12 30-Jan-13 03-Feb-13 51 A18440 1st Coat Paint 2 27-Dec-12 29-Dec-12 04-Feb-13 05-Feb-13 31 Fisrt StaFisrt Stage Finishes 7 30-Dec-12 07-Jan-13 24-Feb-13 24-Apr-13 91 A18610 Screed Works 2 30-Dec-12 31-Dec-12 24-Feb-13 25-Feb-13 46 A18630 Floor Tiles Work 2 03-Jan-13 05-Jan-13 27-Feb-13 28-Feb-13 46 A18490 Doors Ironmongery 1 06-Jan-13 06-Jan-13 24-Apr-13 24-Apr-13 92 A18470 Installation of Doors 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46 Second SSecond Stage Finishes 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46 A18450 Final Coat Paint 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46 Final StaFinal Stage Finishes 1 10-Jan-13 10-Jan-13 25-Apr-13 25-Apr-13 89 A18600 Installation of Sinages 1 10-Jan-13 10-Jan-13 25-Apr-13 25-Apr-13 89 MEP WorkMEP Works 67 16-Oct-12 07-Jan-13 19-Jan-13 03-Mar-13 46 ElectricalElectrical 67 16-Oct-12 07-Jan-13 21-Jan-13 03-Mar-13 46 A18500 Install Conduits in Wall 2 16-Oct-12 17-Oct-12 21-Jan-13 22-Jan-13 78 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Water Pipes in Wall Drainge Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Toliets Accessories Installation of Vanity Counter Installation of Kitchen Cabinets Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 39 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 40. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A18510 Wiring for Lighting & Power 2 26-Nov-12 27-Nov-12 28-Jan-13 29-Jan-13 51 A18520 Installation of Lighting Fittings 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46 PlumbingPlumbing 63 16-Oct-12 02-Jan-13 19-Jan-13 26-Feb-13 46 A18530 Drainge Pipes in Wall 2 16-Oct-12 17-Oct-12 19-Jan-13 20-Jan-13 76 A18560 Water Pipes in Wall 2 16-Oct-12 17-Oct-12 19-Jan-13 20-Jan-13 76 A18540 Drainage&Water Pipes Testing 2 18-Oct-12 20-Oct-12 21-Jan-13 22-Jan-13 76 A18550 Floor Drain Fixning 1 02-Jan-13 02-Jan-13 26-Feb-13 26-Feb-13 46 Fire FighFire Fighting 66 17-Oct-12 07-Jan-13 25-Feb-13 03-Mar-13 46 A18590 Fire Fighting Pipe 2 17-Oct-12 18-Oct-12 25-Feb-13 26-Feb-13 106 A18580 Hydro Static Test for Pipes 2 20-Oct-12 21-Oct-12 27-Feb-13 28-Feb-13 106 A18570 Sprinkler Fixing 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46 A18620 Fire Alarm Devices 2 06-Jan-13 07-Jan-13 02-Mar-13 03-Mar-13 46 Corridor &Corridor & Lift Lobby 153 03-Oct-12 06-Apr-13 10-Dec-12 25-Apr-13 17 FinishingFinishing Works 153 03-Oct-12 06-Apr-13 10-Dec-12 25-Apr-13 17 Wet WorWet Works 57 03-Oct-12 12-Dec-12 10-Dec-12 23-Jan-13 35 A18140 Block Works 8 03-Oct-12 11-Oct-12 10-Dec-12 18-Dec-12 54 A18080 Plaster Works 7 13-Nov-12 21-Nov-12 22-Dec-12 29-Dec-12 31 A18100 Installation of Suspended Ceiling Grid 6 27-Nov-12 04-Dec-12 05-Jan-13 10-Jan-13 31 A18110 Suspended Ceiling Tiles 6 05-Dec-12 11-Dec-12 12-Jan-13 17-Jan-13 31 A18400 MDF for Lift Lobby Wall 7 05-Dec-12 12-Dec-12 16-Jan-13 23-Jan-13 35 Fisrt StaFisrt Stage Finishes 12 13-Dec-12 26-Dec-12 26-Jan-13 03-Feb-13 31 A18380 Screed Works 3 13-Dec-12 16-Dec-12 26-Jan-13 28-Jan-13 35 A18090 1st Coat Paint 5 22-Dec-12 26-Dec-12 29-Jan-13 03-Feb-13 31 Second SSecond Stage Finishes 2 08-Jan-13 09-Jan-13 04-Mar-13 25-Apr-13 90 A18120 Installation of Doors 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46 A18150 Doors Ironmongery 2 08-Jan-13 09-Jan-13 24-Apr-13 25-Apr-13 90 Final StaFinal Stage Finishes 11 25-Mar-13 06-Apr-13 14-Apr-13 25-Apr-13 17 A18130 Installation of Carpets 4 25-Mar-13 28-Mar-13 14-Apr-13 17-Apr-13 17 A18390 Fixing of Wall Covering 5 30-Mar-13 03-Apr-13 18-Apr-13 23-Apr-13 17 A18370 Installation of Sinages 2 04-Apr-13 06-Apr-13 24-Apr-13 25-Apr-13 17 MEP WorkMEP Works 56 13-Oct-12 20-Dec-12 19-Dec-12 05-Mar-13 62 HVACHVAC 51 13-Oct-12 15-Dec-12 25-Dec-12 28-Jan-13 36 A18160 Duct Installation & Insulation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59 A18170 Chilled Water Pipe Installation & Insulation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59 A18180 Condensate Pipe Installation 5 13-Oct-12 17-Oct-12 25-Dec-12 30-Dec-12 59 A18190 FCU Installation 3 18-Oct-12 21-Oct-12 31-Dec-12 03-Jan-13 59 A18200 Air-Outlet Installation 3 12-Dec-12 15-Dec-12 26-Jan-13 28-Jan-13 36 ElectricalElectrical 52 13-Oct-12 16-Dec-12 19-Dec-12 05-Mar-13 66 A18210 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 19-Dec-12 20-Dec-12 54 A18220 Install Cable Trays & Trunking 2 13-Oct-12 14-Oct-12 25-Dec-12 26-Dec-12 59 A18260 Cable Laying for Low Current System 2 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 69 A18270 Cable Laying for Power 3 15-Oct-12 17-Oct-12 08-Jan-13 10-Jan-13 68 A18230 Wiring for Lighting & Power 3 22-Nov-12 25-Nov-12 31-Dec-12 03-Jan-13 32 A18240 Wiring for Low Current System 4 22-Nov-12 26-Nov-12 30-Dec-12 03-Jan-13 31 A18250 DB installation,Dressing & Termination 6 05-Dec-12 11-Dec-12 12-Jan-13 17-Jan-13 31 A18290 Installation of Lighting Fittings 3 12-Dec-12 15-Dec-12 03-Mar-13 05-Mar-13 67 A18300 Installation of Sockets 4 12-Dec-12 16-Dec-12 02-Mar-13 05-Mar-13 66 PlumbingPlumbing 5 13-Oct-12 17-Oct-12 29-Dec-12 03-Jan-13 62 A18310 H/L Hot&Cold Water Pipe Installation 5 13-Oct-12 17-Oct-12 29-Dec-12 03-Jan-13 62 Fire FighFire Fighting 56 13-Oct-12 20-Dec-12 25-Dec-12 28-Jan-13 31 A18360 Fire Fighting Pipe 4 13-Oct-12 16-Oct-12 25-Dec-12 29-Dec-12 59 A18350 Hydro Static Test for Pipes 4 17-Oct-12 21-Oct-12 30-Dec-12 03-Jan-13 59 A18340 Sprinkler Fixing 4 12-Dec-12 16-Dec-12 19-Jan-13 22-Jan-13 31 A18410 Fire Alarm Devices 5 12-Dec-12 17-Dec-12 22-Jan-13 28-Jan-13 34 A18330 Installation of Fire Extingusher&Blanket 4 17-Dec-12 20-Dec-12 23-Jan-13 28-Jan-13 31 Electrical /Electrical /Telephone/ELV Rooms 90 16-Oct-12 04-Feb-13 23-Jan-13 25-Apr-13 69 FinishingFinishing Works 90 16-Oct-12 04-Feb-13 23-Jan-13 25-Apr-13 69 Wet WorWet Works 63 16-Oct-12 02-Jan-13 23-Jan-13 05-Mar-13 52 A18690 Block Works 3 16-Oct-12 18-Oct-12 23-Jan-13 27-Jan-13 80 A18650 Installation of Doors& Windows Sub-frame 1 26-Nov-12 26-Nov-12 05-Mar-13 05-Mar-13 82 A18640 Plaster Works 4 26-Nov-12 29-Nov-12 30-Jan-13 03-Feb-13 53 A18660 1st Coat Paint 3 30-Dec-12 02-Jan-13 06-Feb-13 09-Feb-13 31 Fisrt StaFisrt Stage Finishes 17 10-Jan-13 30-Jan-13 06-Mar-13 23-Apr-13 71 A18680 Installation of Doors 2 10-Jan-13 12-Jan-13 06-Mar-13 07-Mar-13 46 A18700 Doors Ironmongery 2 10-Jan-13 12-Jan-13 22-Apr-13 23-Apr-13 86 A18750 Epoxy Paint Works 2 29-Jan-13 30-Jan-13 09-Apr-13 10-Apr-13 60 Second SSecond Stage Finishes 2 31-Jan-13 02-Feb-13 11-Apr-13 13-Apr-13 60 A18670 Final Coat Paint 2 31-Jan-13 02-Feb-13 11-Apr-13 13-Apr-13 60 Final StaFinal Stage Finishes 2 03-Feb-13 04-Feb-13 24-Apr-13 25-Apr-13 69 A18740 Installation of Sinages 2 03-Feb-13 04-Feb-13 24-Apr-13 25-Apr-13 69 MEP WorkMEP Works 81 20-Oct-12 28-Jan-13 28-Jan-13 08-Apr-13 60 HVACHVAC 2 03-Jan-13 05-Jan-13 04-Mar-13 05-Mar-13 50 A18780 Air-Outlet Installation 2 03-Jan-13 05-Jan-13 04-Mar-13 05-Mar-13 50 ElectricalElectrical 81 20-Oct-12 28-Jan-13 28-Jan-13 05-Mar-13 31 A18710 Install Conduits in Wall 2 20-Oct-12 21-Oct-12 28-Jan-13 29-Jan-13 80 A18720 Wiring for Lighting & Power 2 01-Dec-12 03-Dec-12 04-Feb-13 05-Feb-13 53 A18770 Installation of SMDBs 7 03-Jan-13 10-Jan-13 24-Feb-13 03-Mar-13 43 A18730 Installation of Lighting Fittings 2 12-Jan-13 13-Jan-13 04-Mar-13 05-Mar-13 43 A114520 Installation of Access ControlSystem 20 03-Jan-13 27-Jan-13 11-Feb-13 05-Mar-13 32 A114500 Installation of MATC,TV System 20 03-Jan-13 27-Jan-13 11-Feb-13 05-Mar-13 32 A114510 Installation of Telephone System 21 03-Jan-13 28-Jan-13 10-Feb-13 05-Mar-13 31 Fire FighFire Fighting 2 14-Jan-13 15-Jan-13 07-Apr-13 08-Apr-13 70 A18760 Fire Alarm Devices 2 14-Jan-13 15-Jan-13 07-Apr-13 08-Apr-13 70 Room ServRoom Service 73 20-Oct-12 17-Jan-13 07-Feb-13 25-Apr-13 83 FinishingFinishing Works 73 20-Oct-12 17-Jan-13 07-Feb-13 25-Apr-13 83 Wet WorWet Works 63 20-Oct-12 06-Jan-13 07-Feb-13 07-Mar-13 51 A18840 Block Works 2 20-Oct-12 21-Oct-12 07-Feb-13 09-Feb-13 89 A18800 Installation of Doors& Windows Sub-frame 1 01-Dec-12 01-Dec-12 07-Mar-13 07-Mar-13 80 A18790 Plaster Works 4 01-Dec-12 05-Dec-12 14-Feb-13 18-Feb-13 62 A18810 1st Coat Paint 3 03-Jan-13 06-Jan-13 21-Feb-13 24-Feb-13 41 Fisrt StaFisrt Stage Finishes 7 07-Jan-13 14-Jan-13 25-Feb-13 24-Apr-13 85 A18970 Screed Works 2 07-Jan-13 08-Jan-13 25-Feb-13 26-Feb-13 41 A18990 Floor Tiles Work 3 10-Jan-13 13-Jan-13 28-Feb-13 03-Mar-13 41 A18830 Installation of Doors 1 14-Jan-13 14-Jan-13 09-Mar-13 09-Mar-13 45 A18850 Doors Ironmongery 1 14-Jan-13 14-Jan-13 24-Apr-13 24-Apr-13 85 Second SSecond Stage Finishes 1 16-Jan-13 16-Jan-13 13-Apr-13 13-Apr-13 73 A18820 Final Coat Paint 1 16-Jan-13 16-Jan-13 13-Apr-13 13-Apr-13 73 Final StaFinal Stage Finishes 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83 A18960 Installation of Sinages 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83 MEP WorkMEP Works 69 22-Oct-12 15-Jan-13 10-Feb-13 11-Apr-13 73 HVACHVAC 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41 A19000 Air-Outlet Installation 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41 ElectricalElectrical 69 22-Oct-12 15-Jan-13 12-Feb-13 05-Mar-13 41 A18860 Install Conduits in Wall 2 22-Oct-12 23-Oct-12 12-Feb-13 13-Feb-13 91 A18870 Wiring for Lighting & Power 2 06-Dec-12 08-Dec-12 19-Feb-13 20-Feb-13 62 A18880 Installation of Lighting Fittings 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41 PlumbingPlumbing 64 22-Oct-12 09-Jan-13 10-Feb-13 27-Feb-13 41 A18890 Drainge Pipes in Wall 2 22-Oct-12 23-Oct-12 10-Feb-13 11-Feb-13 89 A18920 Water Pipes in Wall 2 22-Oct-12 23-Oct-12 10-Feb-13 11-Feb-13 89 A18900 Drainage&Water Pipes Testing 2 24-Oct-12 28-Oct-12 12-Feb-13 13-Feb-13 89 A18910 Floor Drain Fixning 1 09-Jan-13 09-Jan-13 27-Feb-13 27-Feb-13 41 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 40 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 41. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Fire FighFire Fighting 69 22-Oct-12 15-Jan-13 27-Feb-13 11-Apr-13 73 A18950 Fire Fighting Pipe 2 22-Oct-12 23-Oct-12 27-Feb-13 28-Feb-13 104 A18940 Hydro Static Test for Pipes 2 24-Oct-12 28-Oct-12 02-Mar-13 03-Mar-13 104 A18930 Sprinkler Fixing 2 14-Jan-13 15-Jan-13 04-Mar-13 05-Mar-13 41 A18980 Fire Alarm Devices 2 14-Jan-13 15-Jan-13 10-Apr-13 11-Apr-13 73 StaircaseStaircase 133 09-Oct-12 19-Mar-13 14-Nov-12 13-Apr-13 21 Stair 1Stair 1 119 09-Oct-12 03-Mar-13 14-Nov-12 13-Apr-13 35 A108650 Floor Screed 3 09-Oct-12 11-Oct-12 14-Nov-12 18-Nov-12 29 A108660 Install Handrails 4 13-Oct-12 16-Oct-12 19-Nov-12 22-Nov-12 29 A108670 Ceiling 1st Coat Paint 7 17-Jan-13 26-Jan-13 12-Feb-13 19-Feb-13 21 A108680 Wall 1st Coat Paint 7 27-Jan-13 03-Feb-13 20-Feb-13 27-Feb-13 21 A108690 Install Granite/Terrazo 12 04-Feb-13 17-Feb-13 03-Mar-13 16-Mar-13 23 A108700 Final Coat Paint 12 18-Feb-13 03-Mar-13 31-Mar-13 13-Apr-13 35 Stair 2Stair 2 130 13-Oct-12 19-Mar-13 20-Nov-12 13-Apr-13 21 A108710 Floor Screed 3 13-Oct-12 15-Oct-12 20-Nov-12 22-Nov-12 30 A108720 Install Handrails 4 17-Oct-12 21-Oct-12 24-Nov-12 27-Nov-12 29 A108730 Ceiling 1st Coat Paint 7 04-Feb-13 11-Feb-13 28-Feb-13 07-Mar-13 21 A108740 Wall 1st Coat Paint 7 12-Feb-13 19-Feb-13 09-Mar-13 16-Mar-13 21 A108750 Install Granite/Terrazo 12 20-Feb-13 05-Mar-13 17-Mar-13 30-Mar-13 21 A108760 Final Coat Paint 12 06-Mar-13 19-Mar-13 31-Mar-13 13-Apr-13 21 ApartementsApartements 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21 Studio FlatsStudio Flats 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21 FinishingFinishing Works 288 29-Sep-12 08-Sep-13 27-Nov-12 02-Oct-13 21 Wet WoWet Works 61 29-Sep-12 12-Dec-12 27-Nov-12 09-Mar-13 72 A39570 Block Works 4 29-Sep-12 02-Oct-12 27-Nov-12 01-Dec-12 48 A39430 Installation of Doors& Windows Sub-frame 1 05-Nov-12 05-Nov-12 09-Mar-13 09-Mar-13 102 A39420 Plaster Works 7 05-Nov-12 12-Nov-12 08-Dec-12 15-Dec-12 26 A39900 Wall Tiles Work (Wet Area) 8 13-Nov-12 22-Nov-12 06-Jan-13 14-Jan-13 43 A39450 Installation of Suspended Ceiling Grid (Dry Area) 6 18-Nov-12 24-Nov-12 19-Dec-12 25-Dec-12 26 A39440 1st Coat Paint 3 10-Dec-12 12-Dec-12 26-Dec-12 29-Dec-12 14 Fisrt StaFisrt Stage Finishes 23 13-Dec-12 09-Jan-13 30-Dec-12 16-Mar-13 55 A39460 Suspended Ceiling Tiles (DryArea) 6 13-Dec-12 19-Dec-12 30-Dec-12 06-Jan-13 14 A39500 Installation of Wardrobes 2 20-Dec-12 22-Dec-12 16-Jan-13 17-Jan-13 22 A39890 Screed Works 5 23-Dec-12 27-Dec-12 26-Jan-13 30-Jan-13 27 A39490 Water Proofing for Wet Area 3 29-Dec-12 31-Dec-12 31-Jan-13 03-Feb-13 27 A39480 Floor & Wall Tiles Work (Dry Area) 4 29-Dec-12 02-Jan-13 12-Mar-13 16-Mar-13 61 A39930 Installation of Suspended Ceiling Grid (Wet Area) 3 02-Jan-13 05-Jan-13 06-Feb-13 09-Feb-13 29 A39920 Suspended Ceiling Tiles (Wet Area) 2 06-Jan-13 07-Jan-13 12-Feb-13 13-Feb-13 31 A39910 Floor Tiles Work (Wet Area) 2 08-Jan-13 09-Jan-13 26-Feb-13 27-Feb-13 41 SecondSecond Stage Finishes 4 15-Jan-13 19-Jan-13 10-Mar-13 06-Apr-13 65 A39510 Installation of Windows&Doors 2 15-Jan-13 16-Jan-13 10-Mar-13 11-Mar-13 45 A39580 Doors Ironmongery 2 15-Jan-13 16-Jan-13 04-Apr-13 06-Apr-13 67 A39520 Installation of Mirrors 2 17-Jan-13 19-Jan-13 18-Mar-13 19-Mar-13 50 A39530 Installation of Kitchen Cabinets 2 17-Jan-13 19-Jan-13 17-Mar-13 18-Mar-13 49 A39550 Installation of Balustrades& Handrails 2 17-Jan-13 19-Jan-13 04-Apr-13 06-Apr-13 65 A39560 Installation of Vanity Counter 2 17-Jan-13 19-Jan-13 19-Mar-13 20-Mar-13 51 A39870 Installation of Toliets Accessories 2 17-Jan-13 19-Jan-13 13-Mar-13 14-Mar-13 46 Final StFinal Stage Finishes 195 21-Jan-13 08-Sep-13 07-Apr-13 02-Oct-13 21 A39470 Final Coat Paint 6 21-Jan-13 28-Jan-13 07-Apr-13 13-Apr-13 64 A39540 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A39880 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A39590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 89 03-Oct-12 20-Jan-13 03-Dec-12 13-Apr-13 70 HVACHVAC 81 03-Oct-12 10-Jan-13 09-Dec-12 05-Mar-13 45 A39600 Duct Installation & Insulation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53 A39610 Chilled Water Pipe Installation & Insulation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53 A39620 Condensate Pipe Installation 7 03-Oct-12 10-Oct-12 09-Dec-12 16-Dec-12 53 A39630 FCU Installation 2 11-Oct-12 13-Oct-12 17-Dec-12 18-Dec-12 53 A39640 Air-Outlet Installation 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45 ElectricElectrical 82 03-Oct-12 12-Jan-13 04-Dec-12 05-Mar-13 44 A39650 Install Conduits in Wall 3 03-Oct-12 06-Oct-12 04-Dec-12 06-Dec-12 49 A39660 Install Cable Trays & Trunking 4 03-Oct-12 07-Oct-12 09-Dec-12 12-Dec-12 53 A39700 Cable Laying for Low Current System 3 08-Oct-12 10-Oct-12 23-Dec-12 25-Dec-12 61 A39710 Cable Laying for Power 3 08-Oct-12 10-Oct-12 23-Dec-12 25-Dec-12 61 A39670 Wiring for Lighting & Power 3 13-Nov-12 17-Nov-12 16-Dec-12 18-Dec-12 26 A39680 Wiring for Low Current System 3 13-Nov-12 17-Nov-12 16-Dec-12 18-Dec-12 26 A39690 DB installation,Dressing & Termination 6 13-Dec-12 19-Dec-12 30-Dec-12 06-Jan-13 14 A39740 Installation of Sockets 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45 A39730 Installation of Lighting Fittings 4 08-Jan-13 12-Jan-13 02-Mar-13 05-Mar-13 44 PlumbinPlumbing 89 03-Oct-12 20-Jan-13 03-Dec-12 06-Apr-13 64 A39750 Drainge Pipes in Wall 4 03-Oct-12 07-Oct-12 03-Dec-12 06-Dec-12 48 A39760 H/L Drainage Pipes Installation 4 03-Oct-12 07-Oct-12 28-Jan-13 31-Jan-13 94 A39770 H/L Hot&Cold Water Pipe Installation 4 03-Oct-12 07-Oct-12 28-Jan-13 31-Jan-13 94 A39820 Water Pipes in Wall 4 03-Oct-12 07-Oct-12 03-Dec-12 06-Dec-12 48 A39780 Drainage&Water Pipes Testing 4 08-Oct-12 11-Oct-12 02-Feb-13 05-Feb-13 94 A39790 ElectricalWater Heater Installation 4 08-Oct-12 11-Oct-12 02-Feb-13 05-Feb-13 94 A39800 Floor Drain Fixning 3 25-Dec-12 27-Dec-12 21-Feb-13 24-Feb-13 48 A39810 Installation of Sanitaryware 3 17-Jan-13 20-Jan-13 03-Apr-13 06-Apr-13 64 Fire FigFire Fighting 83 03-Oct-12 13-Jan-13 12-Dec-12 13-Apr-13 76 A39860 Fire Fighting Pipe 3 03-Oct-12 06-Oct-12 12-Dec-12 15-Dec-12 56 A39850 Hydro Static Test for Pipes 3 07-Oct-12 09-Oct-12 16-Dec-12 18-Dec-12 56 A39840 Sprinkler Fixing 3 08-Jan-13 10-Jan-13 03-Mar-13 05-Mar-13 45 A39940 Fire Alarm Devices 3 08-Jan-13 10-Jan-13 03-Apr-13 06-Apr-13 72 A39830 Installation of Fire Extingusher&Blanket 2 12-Jan-13 13-Jan-13 11-Apr-13 13-Apr-13 76 One BedroOne Bedroom Flats 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21 FinishingFinishing Works 293 23-Sep-12 08-Sep-13 12-Nov-12 02-Oct-13 21 Wet WoWet Works 63 23-Sep-12 09-Dec-12 12-Nov-12 11-Mar-13 77 A40100 Block Works 5 23-Sep-12 27-Sep-12 12-Nov-12 18-Nov-12 41 A39960 Installation of Doors& Windows Sub-frame 1 28-Oct-12 28-Oct-12 11-Mar-13 11-Mar-13 111 A39950 Plaster Works 7 28-Oct-12 04-Nov-12 28-Nov-12 06-Dec-12 26 A39980 Installation of Suspended Ceiling Grid (Dry Area) 4 10-Nov-12 13-Nov-12 15-Dec-12 18-Dec-12 28 A40430 Wall Tiles Work (Wet Area) 4 24-Nov-12 27-Nov-12 15-Jan-13 19-Jan-13 43 A39970 1st Coat Paint 6 03-Dec-12 09-Dec-12 19-Dec-12 25-Dec-12 14 Fisrt StaFisrt Stage Finishes 34 20-Dec-12 30-Jan-13 07-Jan-13 19-Mar-13 41 A39990 Suspended Ceiling Tiles (DryArea) 4 20-Dec-12 24-Dec-12 07-Jan-13 10-Jan-13 14 A40030 Installation of Wardrobes 4 25-Dec-12 29-Dec-12 19-Jan-13 22-Jan-13 20 A40420 Screed Works 9 30-Dec-12 09-Jan-13 23-Jan-13 03-Feb-13 20 A40010 Floor & Wall Tiles Work (Dry Area) 3 10-Jan-13 13-Jan-13 17-Mar-13 19-Mar-13 55 A40020 Water Proofing for Wet Area 4 10-Jan-13 14-Jan-13 04-Feb-13 07-Feb-13 20 A40460 Installation of Suspended Ceiling Grid (Wet Area) 4 15-Jan-13 19-Jan-13 10-Feb-13 13-Feb-13 21 A40450 Suspended Ceiling Tiles (Wet Area) 4 20-Jan-13 23-Jan-13 14-Feb-13 18-Feb-13 21 A40440 Floor Tiles Work (Wet Area) 5 26-Jan-13 30-Jan-13 28-Feb-13 05-Mar-13 29 SecondSecond Stage Finishes 7 31-Jan-13 07-Feb-13 12-Mar-13 07-Apr-13 50 A40040 Installation of Windows&Doors 3 31-Jan-13 03-Feb-13 12-Mar-13 14-Mar-13 34 A40110 Doors Ironmongery 3 31-Jan-13 03-Feb-13 04-Apr-13 07-Apr-13 54 A40090 Installation of Vanity Counter 2 04-Feb-13 05-Feb-13 21-Mar-13 23-Mar-13 39 A40050 Installation of Mirrors 3 04-Feb-13 06-Feb-13 20-Mar-13 23-Mar-13 38 A40060 Installation of Kitchen Cabinets 3 04-Feb-13 06-Feb-13 19-Mar-13 21-Mar-13 37 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Installation of Kitchen Cabinets Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Floor & Wall Tiles Work (Dry Area) Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Vanity Counter Installation of Mirrors Installation of Kitchen Cabinets Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 41 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 42. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A40080 Installation of Balustrades& Handrails 3 04-Feb-13 06-Feb-13 04-Apr-13 07-Apr-13 51 A40400 Installation of Toliets Accessories 4 04-Feb-13 07-Feb-13 16-Mar-13 19-Mar-13 34 Final StFinal Stage Finishes 180 09-Feb-13 08-Sep-13 08-Apr-13 02-Oct-13 21 A40000 Final Coat Paint 5 09-Feb-13 13-Feb-13 08-Apr-13 13-Apr-13 50 A40070 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A40410 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A40120 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 107 29-Sep-12 06-Feb-13 19-Nov-12 13-Apr-13 56 HVACHVAC 99 29-Sep-12 28-Jan-13 04-Dec-12 05-Mar-13 31 A40130 Duct Installation & Insulation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53 A40140 Chilled Water Pipe Installation & Insulation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53 A40150 Condensate Pipe Installation 7 29-Sep-12 06-Oct-12 04-Dec-12 11-Dec-12 53 A40160 FCU Installation 2 07-Oct-12 08-Oct-12 12-Dec-12 13-Dec-12 53 A40170 Air-Outlet Installation 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31 ElectricElectrical 100 29-Sep-12 29-Jan-13 25-Nov-12 05-Mar-13 30 A40180 Install Conduits in Wall 3 29-Sep-12 01-Oct-12 25-Nov-12 27-Nov-12 46 A40190 Install Cable Trays & Trunking 4 29-Sep-12 02-Oct-12 29-Nov-12 04-Dec-12 50 A40230 Cable Laying for Low Current System 3 03-Oct-12 06-Oct-12 16-Dec-12 18-Dec-12 59 A40240 Cable Laying for Power 3 03-Oct-12 06-Oct-12 16-Dec-12 18-Dec-12 59 A40200 Wiring for Lighting & Power 3 05-Nov-12 07-Nov-12 11-Dec-12 13-Dec-12 29 A40210 Wiring for Low Current System 3 05-Nov-12 07-Nov-12 11-Dec-12 13-Dec-12 29 A40220 DB installation,Dressing & Termination 6 10-Dec-12 16-Dec-12 05-Jan-13 10-Jan-13 21 A40270 Installation of Sockets 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31 A40260 Installation of Lighting Fittings 4 26-Jan-13 29-Jan-13 02-Mar-13 05-Mar-13 30 PlumbinPlumbing 107 29-Sep-12 06-Feb-13 19-Nov-12 07-Apr-13 51 A40290 H/L Drainage Pipes Installation 4 29-Sep-12 02-Oct-12 22-Jan-13 27-Jan-13 94 A40300 H/L Hot&Cold Water Pipe Installation 4 29-Sep-12 02-Oct-12 31-Jan-13 04-Feb-13 101 A40280 Drainge Pipes in Wall 8 29-Sep-12 07-Oct-12 19-Nov-12 27-Nov-12 41 A40310 Drainage&Water Pipes Testing 4 03-Oct-12 07-Oct-12 05-Feb-13 09-Feb-13 101 A40320 ElectricalWater Heater Installation 4 03-Oct-12 07-Oct-12 05-Feb-13 09-Feb-13 101 A40350 Water Pipes in Wall 8 29-Sep-12 07-Oct-12 19-Nov-12 27-Nov-12 41 A40330 Floor Drain Fixning 3 02-Jan-13 05-Jan-13 27-Feb-13 02-Mar-13 47 A40340 Installation of Sanitaryware 3 04-Feb-13 06-Feb-13 04-Apr-13 07-Apr-13 51 Fire FigFire Fighting 101 29-Sep-12 30-Jan-13 08-Dec-12 13-Apr-13 62 A40390 Fire Fighting Pipe 3 29-Sep-12 01-Oct-12 08-Dec-12 10-Dec-12 56 A40380 Hydro Static Test for Pipes 3 02-Oct-12 04-Oct-12 11-Dec-12 13-Dec-12 56 A40370 Sprinkler Fixing 3 26-Jan-13 28-Jan-13 03-Mar-13 05-Mar-13 31 A40470 Fire Alarm Devices 3 26-Jan-13 28-Jan-13 04-Apr-13 07-Apr-13 59 A40360 Installation of Fire Extingusher&Blanket 2 29-Jan-13 30-Jan-13 11-Apr-13 13-Apr-13 62 Two BedroTwo Bedroom Flats 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21 FinishingFinishing Works 308 05-Sep-12 08-Sep-13 22-Sep-12 02-Oct-13 21 Wet WoWet Works 82 05-Sep-12 13-Dec-12 22-Sep-12 11-Mar-13 73 A40630 Block Works 15 05-Sep-12 22-Sep-12 22-Sep-12 08-Oct-12 14 A40490 Installation of Doors& Windows Sub-frame 7 02-Oct-12 09-Oct-12 04-Mar-13 11-Mar-13 125 A40480 Plaster Works 20 02-Oct-12 24-Oct-12 18-Oct-12 12-Nov-12 14 A40510 Installation of Suspended Ceiling Grid (Dry Area) 8 31-Oct-12 08-Nov-12 18-Nov-12 26-Nov-12 14 A40500 1st Coat Paint 18 10-Nov-12 01-Dec-12 27-Nov-12 18-Dec-12 14 A40960 Wall Tiles Work (Wet Area) 13 28-Nov-12 13-Dec-12 20-Jan-13 04-Feb-13 43 Fisrt StaFisrt Stage Finishes 47 25-Dec-12 19-Feb-13 12-Jan-13 02-Apr-13 36 A40520 Suspended Ceiling Tiles (DryArea) 12 25-Dec-12 08-Jan-13 12-Jan-13 26-Jan-13 14 A40560 Installation of Wardrobes 8 09-Jan-13 17-Jan-13 27-Jan-13 04-Feb-13 14 A40950 Screed Works 9 19-Jan-13 29-Jan-13 05-Feb-13 14-Feb-13 14 A40550 Water Proofing for Wet Area 9 22-Jan-13 02-Feb-13 09-Feb-13 18-Feb-13 14 A40990 Installation of Suspended Ceiling Grid (Wet Area) 7 29-Jan-13 05-Feb-13 14-Feb-13 21-Feb-13 14 A40540 Floor & Wall Tiles Work (Dry Area) 12 30-Jan-13 12-Feb-13 20-Mar-13 02-Apr-13 42 A40980 Suspended Ceiling Tiles (Wet Area) 10 03-Feb-13 13-Feb-13 19-Feb-13 02-Mar-13 14 A40970 Floor Tiles Work (Wet Area) 5 14-Feb-13 19-Feb-13 06-Mar-13 11-Mar-13 17 SecondSecond Stage Finishes 19 20-Feb-13 13-Mar-13 12-Mar-13 02-Apr-13 17 A40640 Doors Ironmongery 6 20-Feb-13 26-Feb-13 27-Mar-13 02-Apr-13 30 A40570 Installation of Windows&Doors 7 20-Feb-13 27-Feb-13 12-Mar-13 19-Mar-13 17 A40610 Installation of Balustrades& Handrails 5 28-Feb-13 05-Mar-13 28-Mar-13 02-Apr-13 24 A40580 Installation of Mirrors 9 28-Feb-13 10-Mar-13 24-Mar-13 02-Apr-13 20 A40620 Installation of Vanity Counter 9 28-Feb-13 10-Mar-13 24-Mar-13 02-Apr-13 20 A40590 Installation of Kitchen Cabinets 10 28-Feb-13 11-Mar-13 23-Mar-13 02-Apr-13 19 A40930 Installation of Toliets Accessories 12 28-Feb-13 13-Mar-13 20-Mar-13 02-Apr-13 17 Final StFinal Stage Finishes 151 14-Mar-13 08-Sep-13 03-Apr-13 02-Oct-13 21 A40530 Final Coat Paint 9 14-Mar-13 24-Mar-13 03-Apr-13 13-Apr-13 17 A40600 Installation of Carpets 4 25-Mar-13 28-Mar-13 22-Apr-13 25-Apr-13 24 A40940 Installation of Sinages 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24 A40650 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 133 23-Sep-12 03-Mar-13 09-Oct-12 13-Apr-13 35 HVACHVAC 116 23-Sep-12 11-Feb-13 06-Nov-12 05-Mar-13 19 A40660 Duct Installation & Insulation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36 A40670 Chilled Water Pipe Installation & Insulation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36 A40680 Condensate Pipe Installation 7 23-Sep-12 30-Sep-12 06-Nov-12 13-Nov-12 36 A40690 FCU Installation 2 01-Oct-12 02-Oct-12 14-Nov-12 17-Nov-12 36 A40700 Air-Outlet Installation 3 09-Feb-13 11-Feb-13 03-Mar-13 05-Mar-13 19 ElectricElectrical 117 23-Sep-12 12-Feb-13 15-Oct-12 05-Mar-13 18 A40710 Install Conduits in Wall 3 23-Sep-12 25-Sep-12 15-Oct-12 17-Oct-12 19 A40720 Install Cable Trays & Trunking 4 23-Sep-12 26-Sep-12 06-Nov-12 10-Nov-12 36 A40760 Cable Laying for Low Current System 3 27-Sep-12 30-Sep-12 24-Nov-12 26-Nov-12 46 A40770 Cable Laying for Power 3 27-Sep-12 30-Sep-12 24-Nov-12 26-Nov-12 46 A40730 Wiring for Lighting & Power 3 28-Oct-12 30-Oct-12 13-Nov-12 17-Nov-12 14 A40740 Wiring for Low Current System 3 28-Oct-12 30-Oct-12 13-Nov-12 17-Nov-12 14 A40750 DB installation,Dressing & Termination 6 03-Dec-12 09-Dec-12 19-Jan-13 26-Jan-13 39 A40800 Installation of Sockets 3 09-Feb-13 11-Feb-13 03-Mar-13 05-Mar-13 19 A40790 Installation of Lighting Fittings 4 09-Feb-13 12-Feb-13 02-Mar-13 05-Mar-13 18 PlumbinPlumbing 133 23-Sep-12 03-Mar-13 09-Oct-12 02-Apr-13 26 A40820 H/L Drainage Pipes Installation 4 23-Sep-12 26-Sep-12 17-Jan-13 21-Jan-13 95 A40830 H/L Hot&Cold Water Pipe Installation 4 23-Sep-12 26-Sep-12 05-Feb-13 09-Feb-13 110 A40810 Drainge Pipes in Wall 8 23-Sep-12 01-Oct-12 09-Oct-12 17-Oct-12 14 A40840 Drainage&Water Pipes Testing 4 27-Sep-12 01-Oct-12 10-Feb-13 13-Feb-13 110 A40850 ElectricalWater Heater Installation 4 27-Sep-12 01-Oct-12 10-Feb-13 13-Feb-13 110 A40880 Water Pipes in Wall 8 23-Sep-12 01-Oct-12 09-Oct-12 17-Oct-12 14 A40860 Floor Drain Fixning 3 21-Jan-13 23-Jan-13 03-Mar-13 05-Mar-13 34 A40870 Installation of Sanitaryware 3 28-Feb-13 03-Mar-13 31-Mar-13 02-Apr-13 26 Fire FigFire Fighting 123 23-Sep-12 19-Feb-13 10-Nov-12 13-Apr-13 45 A40920 Fire Fighting Pipe 3 23-Sep-12 25-Sep-12 10-Nov-12 12-Nov-12 39 A40910 Hydro Static Test for Pipes 3 26-Sep-12 29-Sep-12 13-Nov-12 17-Nov-12 39 A40900 Sprinkler Fixing 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14 A41000 Fire Alarm Devices 3 14-Feb-13 17-Feb-13 31-Mar-13 02-Apr-13 38 A40890 Installation of Fire Extingusher&Blanket 2 18-Feb-13 19-Feb-13 11-Apr-13 13-Apr-13 45 6th Floor6th Floor 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21 Public AreaPublic Area 150 18-Oct-12 17-Apr-13 25-Nov-12 25-Apr-13 7 Garbage RGarbage Room 66 30-Oct-12 17-Jan-13 15-Jan-13 25-Apr-13 83 FinishingFinishing Works 66 30-Oct-12 17-Jan-13 15-Jan-13 25-Apr-13 83 Wet WorWet Works 56 30-Oct-12 06-Jan-13 15-Jan-13 14-Feb-13 33 A19410 Block Works 3 30-Oct-12 01-Nov-12 15-Jan-13 17-Jan-13 63 A19360 Installation of Doors& Windows Sub-frame 1 20-Nov-12 20-Nov-12 14-Feb-13 14-Feb-13 71 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Balustrades& Handrails Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Wall Tiles Work (Wet Area) Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Doors Ironmongery Installation of Windows&Doors Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 42 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 43. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A19350 Plaster Works 3 20-Nov-12 22-Nov-12 23-Jan-13 27-Jan-13 53 A19390 Wall Tiles Work 4 26-Nov-12 29-Nov-12 30-Jan-13 03-Feb-13 53 A19370 1st Coat Paint 2 05-Jan-13 06-Jan-13 04-Feb-13 05-Feb-13 25 Fisrt StaFisrt Stage Finishes 7 07-Jan-13 14-Jan-13 10-Feb-13 24-Apr-13 85 A19540 Screed Works 2 07-Jan-13 08-Jan-13 10-Feb-13 11-Feb-13 28 A19560 Floor Tiles Work 2 10-Jan-13 12-Jan-13 13-Feb-13 14-Feb-13 28 A19420 Doors Ironmongery 1 13-Jan-13 13-Jan-13 24-Apr-13 24-Apr-13 86 A19400 Installation of Doors 2 13-Jan-13 14-Jan-13 16-Feb-13 17-Feb-13 28 Second SSecond Stage Finishes 2 15-Jan-13 16-Jan-13 01-Apr-13 02-Apr-13 64 A19380 Final Coat Paint 2 15-Jan-13 16-Jan-13 01-Apr-13 02-Apr-13 64 Final StaFinal Stage Finishes 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83 A19530 Installation of Sinages 1 17-Jan-13 17-Jan-13 25-Apr-13 25-Apr-13 83 MEP WorkMEP Works 60 03-Nov-12 14-Jan-13 19-Jan-13 31-Mar-13 64 ElectricalElectrical 60 03-Nov-12 14-Jan-13 21-Jan-13 05-Mar-13 42 A19430 Install Conduits in Wall 2 03-Nov-12 04-Nov-12 21-Jan-13 22-Jan-13 65 A19440 Wiring for Lighting & Power 2 24-Nov-12 25-Nov-12 28-Jan-13 29-Jan-13 53 A19450 Installation of Lighting Fittings 2 13-Jan-13 14-Jan-13 04-Mar-13 05-Mar-13 42 PlumbingPlumbing 56 03-Nov-12 09-Jan-13 19-Jan-13 12-Feb-13 28 A19460 Drainge Pipes in Wall 2 03-Nov-12 04-Nov-12 19-Jan-13 20-Jan-13 63 A19490 Water Pipes in Wall 2 03-Nov-12 04-Nov-12 19-Jan-13 20-Jan-13 63 A19470 Drainage&Water Pipes Testing 2 05-Nov-12 06-Nov-12 21-Jan-13 22-Jan-13 63 A19480 Floor Drain Fixning 1 09-Jan-13 09-Jan-13 12-Feb-13 12-Feb-13 28 Fire FighFire Fighting 59 04-Nov-12 14-Jan-13 25-Feb-13 31-Mar-13 64 A19520 Fire Fighting Pipe 2 04-Nov-12 05-Nov-12 25-Feb-13 26-Feb-13 93 A19510 Hydro Static Test for Pipes 2 06-Nov-12 07-Nov-12 02-Mar-13 03-Mar-13 95 A19500 Sprinkler Fixing 2 13-Jan-13 14-Jan-13 04-Mar-13 05-Mar-13 42 A19550 Fire Alarm Devices 2 13-Jan-13 14-Jan-13 30-Mar-13 31-Mar-13 64 Corridor &Corridor & Lift Lobby 150 18-Oct-12 17-Apr-13 10-Dec-12 25-Apr-13 7 FinishingFinishing Works 150 18-Oct-12 17-Apr-13 10-Dec-12 25-Apr-13 7 Wet WorWet Works 50 18-Oct-12 19-Dec-12 10-Dec-12 23-Jan-13 29 A19070 Block Works 8 18-Oct-12 29-Oct-12 10-Dec-12 18-Dec-12 41 A19010 Plaster Works 7 11-Nov-12 19-Nov-12 22-Dec-12 29-Dec-12 33 A19030 Installation of Suspended Ceiling Grid 6 05-Dec-12 11-Dec-12 05-Jan-13 10-Jan-13 25 A19040 Suspended Ceiling Tiles 6 12-Dec-12 18-Dec-12 12-Jan-13 17-Jan-13 25 A19330 MDF for Lift Lobby Wall 7 12-Dec-12 19-Dec-12 16-Jan-13 23-Jan-13 29 Fisrt StaFisrt Stage Finishes 12 20-Dec-12 03-Jan-13 26-Jan-13 03-Feb-13 25 A19310 Screed Works 3 20-Dec-12 23-Dec-12 26-Jan-13 28-Jan-13 29 A19020 1st Coat Paint 5 29-Dec-12 03-Jan-13 29-Jan-13 03-Feb-13 25 Second SSecond Stage Finishes 2 15-Jan-13 16-Jan-13 18-Feb-13 25-Apr-13 84 A19050 Installation of Doors 2 15-Jan-13 16-Jan-13 18-Feb-13 19-Feb-13 28 A19080 Doors Ironmongery 2 15-Jan-13 16-Jan-13 24-Apr-13 25-Apr-13 84 Final StaFinal Stage Finishes 20 26-Mar-13 17-Apr-13 03-Apr-13 25-Apr-13 7 A19060 Installation of Carpets 4 26-Mar-13 30-Mar-13 03-Apr-13 07-Apr-13 7 A19320 Fixing of Wall Covering 7 31-Mar-13 07-Apr-13 08-Apr-13 15-Apr-13 7 A19300 Installation of Sinages 9 08-Apr-13 17-Apr-13 16-Apr-13 25-Apr-13 7 MEP WorkMEP Works 49 30-Oct-12 27-Dec-12 19-Dec-12 05-Mar-13 56 HVACHVAC 44 30-Oct-12 22-Dec-12 25-Dec-12 28-Jan-13 30 A19090 Duct Installation & Insulation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46 A19100 Chilled Water Pipe Installation & Insulation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46 A19110 Condensate Pipe Installation 5 30-Oct-12 04-Nov-12 25-Dec-12 30-Dec-12 46 A19120 FCU Installation 3 05-Nov-12 07-Nov-12 31-Dec-12 03-Jan-13 46 A19130 Air-Outlet Installation 3 19-Dec-12 22-Dec-12 26-Jan-13 28-Jan-13 30 ElectricalElectrical 45 30-Oct-12 23-Dec-12 19-Dec-12 05-Mar-13 60 A19140 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 19-Dec-12 20-Dec-12 41 A19150 Install Cable Trays & Trunking 2 30-Oct-12 31-Oct-12 25-Dec-12 26-Dec-12 46 A19190 Cable Laying for Low Current System 2 01-Nov-12 03-Nov-12 09-Jan-13 10-Jan-13 56 A19200 Cable Laying for Power 3 01-Nov-12 04-Nov-12 08-Jan-13 10-Jan-13 55 A19160 Wiring for Lighting & Power 3 20-Nov-12 22-Nov-12 31-Dec-12 03-Jan-13 34 A19170 Wiring for Low Current System 4 20-Nov-12 24-Nov-12 30-Dec-12 03-Jan-13 33 A19180 DB installation,Dressing & Termination 6 12-Dec-12 18-Dec-12 12-Jan-13 17-Jan-13 25 A19220 Installation of Lighting Fittings 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61 A19230 Installation of Sockets 4 19-Dec-12 23-Dec-12 02-Mar-13 05-Mar-13 60 PlumbingPlumbing 5 30-Oct-12 04-Nov-12 29-Dec-12 03-Jan-13 49 A19240 H/L Hot&Cold Water Pipe Installation 5 30-Oct-12 04-Nov-12 29-Dec-12 03-Jan-13 49 Fire FighFire Fighting 49 30-Oct-12 27-Dec-12 25-Dec-12 28-Jan-13 25 A19290 Fire Fighting Pipe 4 30-Oct-12 03-Nov-12 25-Dec-12 29-Dec-12 46 A19280 Hydro Static Test for Pipes 4 04-Nov-12 07-Nov-12 30-Dec-12 03-Jan-13 46 A19270 Sprinkler Fixing 4 19-Dec-12 23-Dec-12 19-Jan-13 22-Jan-13 25 A19340 Fire Alarm Devices 5 19-Dec-12 24-Dec-12 22-Jan-13 28-Jan-13 28 A19260 Installation of Fire Extingusher&Blanket 4 24-Dec-12 27-Dec-12 23-Jan-13 28-Jan-13 25 Electrical /Electrical /Telephone/ELV Rooms 83 03-Nov-12 11-Feb-13 23-Jan-13 25-Apr-13 63 FinishingFinishing Works 83 03-Nov-12 11-Feb-13 23-Jan-13 25-Apr-13 63 Wet WorWet Works 56 03-Nov-12 09-Jan-13 23-Jan-13 19-Feb-13 34 A19620 Block Works 3 03-Nov-12 05-Nov-12 23-Jan-13 27-Jan-13 67 A19580 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 19-Feb-13 19-Feb-13 72 A19570 Plaster Works 4 24-Nov-12 27-Nov-12 30-Jan-13 03-Feb-13 55 A19590 1st Coat Paint 3 07-Jan-13 09-Jan-13 06-Feb-13 09-Feb-13 25 Fisrt StaFisrt Stage Finishes 17 17-Jan-13 06-Feb-13 20-Feb-13 23-Apr-13 65 A19610 Installation of Doors 2 17-Jan-13 19-Jan-13 20-Feb-13 21-Feb-13 28 A19630 Doors Ironmongery 2 17-Jan-13 19-Jan-13 22-Apr-13 23-Apr-13 80 A19680 Epoxy Paint Works 2 05-Feb-13 06-Feb-13 30-Mar-13 31-Mar-13 45 Second SSecond Stage Finishes 2 07-Feb-13 09-Feb-13 01-Apr-13 02-Apr-13 45 A19600 Final Coat Paint 2 07-Feb-13 09-Feb-13 01-Apr-13 02-Apr-13 45 Final StaFinal Stage Finishes 2 10-Feb-13 11-Feb-13 24-Apr-13 25-Apr-13 63 A19670 Installation of Sinages 2 10-Feb-13 11-Feb-13 24-Apr-13 25-Apr-13 63 MEP WorkMEP Works 74 06-Nov-12 04-Feb-13 28-Jan-13 28-Mar-13 45 HVACHVAC 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 A19710 Air-Outlet Installation 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 ElectricalElectrical 74 06-Nov-12 04-Feb-13 28-Jan-13 05-Mar-13 25 A19640 Install Conduits in Wall 2 06-Nov-12 07-Nov-12 28-Jan-13 29-Jan-13 67 A19650 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 04-Feb-13 05-Feb-13 55 A19700 Installation of SMDBs 7 10-Jan-13 17-Jan-13 24-Feb-13 03-Mar-13 37 A19660 Installation of Lighting Fittings 2 19-Jan-13 20-Jan-13 04-Mar-13 05-Mar-13 37 A114550 Installation of Access ControlSystem 20 10-Jan-13 03-Feb-13 11-Feb-13 05-Mar-13 26 A114530 Installation of MATC,TV System 20 10-Jan-13 03-Feb-13 11-Feb-13 05-Mar-13 26 A114540 Installation of Telephone System 21 10-Jan-13 04-Feb-13 10-Feb-13 05-Mar-13 25 Fire FighFire Fighting 2 21-Jan-13 22-Jan-13 27-Mar-13 28-Mar-13 55 A19690 Fire Alarm Devices 2 21-Jan-13 22-Jan-13 27-Mar-13 28-Mar-13 55 Room ServRoom Service 66 06-Nov-12 26-Jan-13 29-Jan-13 25-Apr-13 77 FinishingFinishing Works 66 06-Nov-12 26-Jan-13 29-Jan-13 25-Apr-13 77 Wet WorWet Works 56 06-Nov-12 13-Jan-13 29-Jan-13 21-Feb-13 33 A19770 Block Works 2 06-Nov-12 07-Nov-12 29-Jan-13 30-Jan-13 68 A19730 Installation of Doors& Windows Sub-frame 1 28-Nov-12 28-Nov-12 21-Feb-13 21-Feb-13 70 A19720 Plaster Works 4 28-Nov-12 03-Dec-12 05-Feb-13 09-Feb-13 56 A19740 1st Coat Paint 3 10-Jan-13 13-Jan-13 12-Feb-13 14-Feb-13 27 Fisrt StaFisrt Stage Finishes 7 14-Jan-13 21-Jan-13 16-Feb-13 24-Apr-13 79 A19900 Screed Works 2 14-Jan-13 15-Jan-13 16-Feb-13 17-Feb-13 27 A19920 Floor Tiles Work 3 17-Jan-13 20-Jan-13 19-Feb-13 21-Feb-13 27 A19760 Installation of Doors 1 21-Jan-13 21-Jan-13 23-Feb-13 23-Feb-13 27 A19780 Doors Ironmongery 1 21-Jan-13 21-Jan-13 24-Apr-13 24-Apr-13 79 Second SSecond Stage Finishes 1 23-Jan-13 23-Jan-13 02-Apr-13 02-Apr-13 58 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access ControlSystem Installation of MATC,TV System Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 43 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 44. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A19750 Final Coat Paint 1 23-Jan-13 23-Jan-13 02-Apr-13 02-Apr-13 58 Final StaFinal Stage Finishes 1 26-Jan-13 26-Jan-13 25-Apr-13 25-Apr-13 77 A19890 Installation of Sinages 1 26-Jan-13 26-Jan-13 25-Apr-13 25-Apr-13 77 MEP WorkMEP Works 62 08-Nov-12 22-Jan-13 31-Jan-13 01-Apr-13 58 HVACHVAC 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35 A19930 Air-Outlet Installation 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35 ElectricalElectrical 62 08-Nov-12 22-Jan-13 03-Feb-13 05-Mar-13 35 A19790 Install Conduits in Wall 2 08-Nov-12 10-Nov-12 03-Feb-13 04-Feb-13 70 A19800 Wiring for Lighting & Power 2 04-Dec-12 05-Dec-12 10-Feb-13 11-Feb-13 56 A19810 Installation of Lighting Fittings 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35 PlumbingPlumbing 57 08-Nov-12 16-Jan-13 31-Jan-13 18-Feb-13 27 A19820 Drainge Pipes in Wall 2 08-Nov-12 10-Nov-12 31-Jan-13 02-Feb-13 68 A19850 Water Pipes in Wall 2 08-Nov-12 10-Nov-12 31-Jan-13 02-Feb-13 68 A19830 Drainage&Water Pipes Testing 2 11-Nov-12 12-Nov-12 03-Feb-13 04-Feb-13 68 A19840 Floor Drain Fixning 1 16-Jan-13 16-Jan-13 18-Feb-13 18-Feb-13 27 Fire FighFire Fighting 62 08-Nov-12 22-Jan-13 27-Feb-13 01-Apr-13 58 A19880 Fire Fighting Pipe 2 08-Nov-12 10-Nov-12 27-Feb-13 28-Feb-13 91 A19870 Hydro Static Test for Pipes 2 11-Nov-12 12-Nov-12 02-Mar-13 03-Mar-13 91 A19860 Sprinkler Fixing 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35 A19910 Fire Alarm Devices 2 21-Jan-13 22-Jan-13 31-Mar-13 01-Apr-13 58 StaircaseStaircase 59 23-Oct-12 05-Jan-13 25-Nov-12 02-Apr-13 74 Stair 1Stair 1 45 23-Oct-12 18-Dec-12 25-Nov-12 02-Apr-13 88 A108770 Floor Screed 3 23-Oct-12 28-Oct-12 25-Nov-12 27-Nov-12 25 A108780 Install Handrails 4 29-Oct-12 01-Nov-12 28-Nov-12 03-Dec-12 25 A108790 Ceiling 1st Coat Paint 7 03-Nov-12 10-Nov-12 04-Dec-12 11-Dec-12 25 A108800 Wall 1st Coat Paint 7 11-Nov-12 19-Nov-12 12-Dec-12 19-Dec-12 25 A108810 Install Granite/Terrazo 12 20-Nov-12 04-Dec-12 29-Dec-12 12-Jan-13 32 A108820 Final Coat Paint 12 05-Dec-12 18-Dec-12 20-Mar-13 02-Apr-13 88 Stair 2Stair 2 56 29-Oct-12 05-Jan-13 12-Dec-12 02-Apr-13 74 A108830 Floor Screed 3 29-Oct-12 31-Oct-12 12-Dec-12 15-Dec-12 36 A108840 Install Handrails 4 03-Nov-12 06-Nov-12 16-Dec-12 19-Dec-12 35 A108850 Ceiling 1st Coat Paint 7 20-Nov-12 27-Nov-12 20-Dec-12 27-Dec-12 25 A108860 Wall 1st Coat Paint 7 28-Nov-12 06-Dec-12 29-Dec-12 06-Jan-13 25 A108870 Install Granite/Terrazo 12 08-Dec-12 20-Dec-12 13-Jan-13 27-Jan-13 30 A108880 Final Coat Paint 12 22-Dec-12 05-Jan-13 20-Mar-13 02-Apr-13 74 ApartementsApartements 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21 Studio FlatsStudio Flats 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21 FinishingFinishing Works 275 14-Oct-12 08-Sep-13 13-Nov-12 02-Oct-13 21 Wet WoWet Works 44 14-Oct-12 08-Dec-12 13-Nov-12 23-Feb-13 64 A41160 Block Works 4 14-Oct-12 17-Oct-12 13-Nov-12 18-Nov-12 24 A41020 Installation of Doors& Windows Sub-frame 1 03-Nov-12 03-Nov-12 23-Feb-13 23-Feb-13 92 A41010 Plaster Works 7 03-Nov-12 10-Nov-12 24-Nov-12 01-Dec-12 17 A41040 Installation of Suspended Ceiling Grid (Dry Area) 6 27-Nov-12 04-Dec-12 06-Dec-12 12-Dec-12 7 A41490 Wall Tiles Work (Wet Area) 8 25-Nov-12 04-Dec-12 16-Jan-13 26-Jan-13 43 A41030 1st Coat Paint 3 05-Dec-12 08-Dec-12 13-Dec-12 16-Dec-12 7 Fisrt StaFisrt Stage Finishes 23 09-Dec-12 05-Jan-13 17-Dec-12 05-Mar-13 50 A41050 Suspended Ceiling Tiles (DryArea) 6 09-Dec-12 15-Dec-12 17-Dec-12 23-Dec-12 7 A41090 Installation of Wardrobes 2 16-Dec-12 17-Dec-12 06-Jan-13 07-Jan-13 17 A41480 Screed Works 5 18-Dec-12 23-Dec-12 27-Jan-13 31-Jan-13 32 A41080 Water Proofing for Wet Area 3 24-Dec-12 26-Dec-12 02-Feb-13 04-Feb-13 32 A41070 Floor & Wall Tiles Work (Dry Area) 4 24-Dec-12 27-Dec-12 02-Mar-13 05-Mar-13 56 A41520 Installation of Suspended Ceiling Grid (Wet Area) 3 27-Dec-12 30-Dec-12 05-Feb-13 07-Feb-13 32 A41510 Suspended Ceiling Tiles (Wet Area) 2 31-Dec-12 02-Jan-13 11-Feb-13 12-Feb-13 34 A41500 Floor Tiles Work (Wet Area) 2 03-Jan-13 05-Jan-13 16-Feb-13 17-Feb-13 36 SecondSecond Stage Finishes 4 22-Jan-13 27-Jan-13 24-Feb-13 26-Mar-13 50 A41100 Installation of Windows&Doors 2 22-Jan-13 23-Jan-13 24-Feb-13 25-Feb-13 27 A41170 Doors Ironmongery 2 22-Jan-13 23-Jan-13 25-Mar-13 26-Mar-13 52 A41110 Installation of Mirrors 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50 A41120 Installation of Kitchen Cabinets 2 26-Jan-13 27-Jan-13 12-Mar-13 13-Mar-13 39 A41140 Installation of Balustrades& Handrails 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50 A41150 Installation of Vanity Counter 2 26-Jan-13 27-Jan-13 23-Mar-13 24-Mar-13 48 A41460 Installation of Toliets Accessories 2 26-Jan-13 27-Jan-13 25-Mar-13 26-Mar-13 50 Final StFinal Stage Finishes 189 29-Jan-13 08-Sep-13 27-Mar-13 02-Oct-13 21 A41060 Final Coat Paint 6 29-Jan-13 04-Feb-13 27-Mar-13 02-Apr-13 49 A41130 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A41470 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A41180 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 82 18-Oct-12 28-Jan-13 19-Nov-12 02-Apr-13 55 HVACHVAC 64 18-Oct-12 06-Jan-13 25-Nov-12 05-Mar-13 49 A41190 Duct Installation & Insulation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29 A41200 Chilled Water Pipe Installation & Insulation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29 A41210 Condensate Pipe Installation 7 18-Oct-12 28-Oct-12 25-Nov-12 03-Dec-12 29 A41220 FCU Installation 2 29-Oct-12 30-Oct-12 04-Dec-12 05-Dec-12 29 A41230 Air-Outlet Installation 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49 ElectricElectrical 65 18-Oct-12 07-Jan-13 20-Nov-12 05-Mar-13 48 A41240 Install Conduits in Wall 3 18-Oct-12 21-Oct-12 20-Nov-12 22-Nov-12 25 A41250 Install Cable Trays & Trunking 4 18-Oct-12 22-Oct-12 25-Nov-12 28-Nov-12 29 A41290 Cable Laying for Low Current System 3 23-Oct-12 28-Oct-12 10-Dec-12 12-Dec-12 37 A41300 Cable Laying for Power 3 23-Oct-12 28-Oct-12 10-Dec-12 12-Dec-12 37 A41260 Wiring for Lighting & Power 3 11-Nov-12 13-Nov-12 03-Dec-12 05-Dec-12 17 A41270 Wiring for Low Current System 3 11-Nov-12 13-Nov-12 03-Dec-12 05-Dec-12 17 A41280 DB installation,Dressing & Termination 6 09-Dec-12 15-Dec-12 17-Dec-12 23-Dec-12 7 A41330 Installation of Sockets 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49 A41320 Installation of Lighting Fittings 4 03-Jan-13 07-Jan-13 02-Mar-13 05-Mar-13 48 PlumbinPlumbing 82 18-Oct-12 28-Jan-13 19-Nov-12 26-Mar-13 49 A41340 Drainge Pipes in Wall 4 18-Oct-12 22-Oct-12 19-Nov-12 22-Nov-12 24 A41350 H/L Drainage Pipes Installation 4 18-Oct-12 22-Oct-12 27-Jan-13 30-Jan-13 80 A41360 H/L Hot&Cold Water Pipe Installation 4 18-Oct-12 22-Oct-12 27-Jan-13 30-Jan-13 80 A41410 Water Pipes in Wall 4 18-Oct-12 22-Oct-12 19-Nov-12 22-Nov-12 24 A41370 Drainage&Water Pipes Testing 4 23-Oct-12 29-Oct-12 31-Jan-13 04-Feb-13 80 A41380 ElectricalWater Heater Installation 4 23-Oct-12 29-Oct-12 31-Jan-13 04-Feb-13 80 A41390 Floor Drain Fixning 3 20-Dec-12 23-Dec-12 11-Feb-13 13-Feb-13 43 A41400 Installation of Sanitaryware 3 26-Jan-13 28-Jan-13 24-Mar-13 26-Mar-13 49 Fire FigFire Fighting 66 18-Oct-12 08-Jan-13 28-Nov-12 02-Apr-13 71 A41450 Fire Fighting Pipe 3 18-Oct-12 21-Oct-12 28-Nov-12 01-Dec-12 32 A41440 Hydro Static Test for Pipes 3 22-Oct-12 24-Oct-12 03-Dec-12 05-Dec-12 32 A41430 Sprinkler Fixing 3 03-Jan-13 06-Jan-13 03-Mar-13 05-Mar-13 49 A41530 Fire Alarm Devices 3 03-Jan-13 06-Jan-13 24-Mar-13 26-Mar-13 67 A41420 Installation of Fire Extingusher&Blanket 2 07-Jan-13 08-Jan-13 01-Apr-13 02-Apr-13 71 One BedroOne Bedroom Flats 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21 FinishingFinishing Works 280 08-Oct-12 08-Sep-13 30-Oct-12 02-Oct-13 21 Wet WoWet Works 46 08-Oct-12 04-Dec-12 30-Oct-12 25-Feb-13 69 A41690 Block Works 5 08-Oct-12 13-Oct-12 30-Oct-12 04-Nov-12 17 A41550 Installation of Doors& Windows Sub-frame 1 23-Oct-12 23-Oct-12 25-Feb-13 25-Feb-13 101 A41540 Plaster Works 7 23-Oct-12 01-Nov-12 14-Nov-12 22-Nov-12 17 A42020 Wall Tiles Work (Wet Area) 4 03-Nov-12 06-Nov-12 26-Dec-12 30-Dec-12 44 A41570 Installation of Suspended Ceiling Grid (Dry Area) 4 22-Nov-12 26-Nov-12 01-Dec-12 05-Dec-12 7 A41560 1st Coat Paint 6 27-Nov-12 04-Dec-12 06-Dec-12 12-Dec-12 7 Fisrt StaFisrt Stage Finishes 34 16-Dec-12 26-Jan-13 24-Dec-12 09-Mar-13 36 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Installation of Kitchen Cabinets Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 44 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 45. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A41580 Suspended Ceiling Tiles (DryArea) 4 16-Dec-12 19-Dec-12 24-Dec-12 27-Dec-12 7 A41620 Installation of Wardrobes 4 20-Dec-12 24-Dec-12 08-Jan-13 12-Jan-13 15 A42010 Screed Works 9 25-Dec-12 05-Jan-13 23-Jan-13 03-Feb-13 24 A41600 Floor & Wall Tiles Work (Dry Area) 3 06-Jan-13 08-Jan-13 06-Mar-13 09-Mar-13 50 A41610 Water Proofing for Wet Area 4 06-Jan-13 09-Jan-13 04-Feb-13 07-Feb-13 24 A42050 Installation of Suspended Ceiling Grid (Wet Area) 4 10-Jan-13 14-Jan-13 09-Feb-13 12-Feb-13 24 A42040 Suspended Ceiling Tiles (Wet Area) 4 15-Jan-13 19-Jan-13 13-Feb-13 17-Feb-13 24 A42030 Floor Tiles Work (Wet Area) 5 20-Jan-13 26-Jan-13 18-Feb-13 23-Feb-13 24 SecondSecond Stage Finishes 7 27-Jan-13 03-Feb-13 26-Feb-13 27-Mar-13 45 A41630 Installation of Windows&Doors 3 27-Jan-13 29-Jan-13 26-Feb-13 28-Feb-13 26 A41700 Doors Ironmongery 3 27-Jan-13 29-Jan-13 25-Mar-13 27-Mar-13 49 A41670 Installation of Balustrades& Handrails 2 30-Jan-13 31-Jan-13 26-Mar-13 27-Mar-13 47 A41640 Installation of Mirrors 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46 A41650 Installation of Kitchen Cabinets 3 30-Jan-13 02-Feb-13 14-Mar-13 17-Mar-13 37 A41680 Installation of Vanity Counter 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46 A41990 Installation of Toliets Accessories 4 30-Jan-13 03-Feb-13 24-Mar-13 27-Mar-13 45 Final StFinal Stage Finishes 184 04-Feb-13 08-Sep-13 28-Mar-13 02-Oct-13 21 A41590 Final Coat Paint 5 04-Feb-13 09-Feb-13 28-Mar-13 02-Apr-13 45 A41660 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A42000 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A41710 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 90 14-Oct-12 02-Feb-13 05-Nov-12 02-Apr-13 51 HVACHVAC 82 14-Oct-12 22-Jan-13 20-Nov-12 05-Mar-13 35 A41720 Duct Installation & Insulation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29 A41730 Chilled Water Pipe Installation & Insulation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29 A41740 Condensate Pipe Installation 7 14-Oct-12 21-Oct-12 20-Nov-12 27-Nov-12 29 A41750 FCU Installation 2 22-Oct-12 23-Oct-12 28-Nov-12 29-Nov-12 29 A41760 Air-Outlet Installation 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35 ElectricElectrical 83 14-Oct-12 23-Jan-13 11-Nov-12 05-Mar-13 34 A41770 Install Conduits in Wall 3 14-Oct-12 16-Oct-12 11-Nov-12 13-Nov-12 22 A41780 Install Cable Trays & Trunking 4 14-Oct-12 17-Oct-12 17-Nov-12 20-Nov-12 26 A41820 Cable Laying for Low Current System 3 18-Oct-12 21-Oct-12 03-Dec-12 05-Dec-12 35 A41830 Cable Laying for Power 3 18-Oct-12 21-Oct-12 03-Dec-12 05-Dec-12 35 A41790 Wiring for Lighting & Power 3 03-Nov-12 05-Nov-12 27-Nov-12 29-Nov-12 20 A41800 Wiring for Low Current System 3 03-Nov-12 05-Nov-12 27-Nov-12 29-Nov-12 20 A41810 DB installation,Dressing & Termination 6 05-Dec-12 11-Dec-12 22-Dec-12 27-Dec-12 14 A41860 Installation of Sockets 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35 A41850 Installation of Lighting Fittings 4 20-Jan-13 23-Jan-13 02-Mar-13 05-Mar-13 34 PlumbinPlumbing 90 14-Oct-12 02-Feb-13 05-Nov-12 27-Mar-13 46 A41880 H/L Drainage Pipes Installation 4 14-Oct-12 17-Oct-12 30-Jan-13 03-Feb-13 87 A41890 H/L Hot&Cold Water Pipe Installation 4 14-Oct-12 17-Oct-12 30-Jan-13 03-Feb-13 87 A41870 Drainge Pipes in Wall 8 14-Oct-12 22-Oct-12 05-Nov-12 13-Nov-12 17 A41900 Drainage&Water Pipes Testing 4 18-Oct-12 22-Oct-12 04-Feb-13 07-Feb-13 87 A41910 ElectricalWater Heater Installation 4 18-Oct-12 22-Oct-12 04-Feb-13 07-Feb-13 87 A41940 Water Pipes in Wall 8 14-Oct-12 22-Oct-12 05-Nov-12 13-Nov-12 17 A41920 Floor Drain Fixning 3 27-Dec-12 30-Dec-12 17-Feb-13 19-Feb-13 42 A41930 Installation of Sanitaryware 3 30-Jan-13 02-Feb-13 25-Mar-13 27-Mar-13 46 Fire FigFire Fighting 84 14-Oct-12 26-Jan-13 24-Nov-12 02-Apr-13 57 A41980 Fire Fighting Pipe 3 14-Oct-12 16-Oct-12 24-Nov-12 26-Nov-12 32 A41970 Hydro Static Test for Pipes 3 17-Oct-12 20-Oct-12 27-Nov-12 29-Nov-12 32 A41960 Sprinkler Fixing 3 20-Jan-13 22-Jan-13 03-Mar-13 05-Mar-13 35 A42060 Fire Alarm Devices 3 20-Jan-13 22-Jan-13 25-Mar-13 27-Mar-13 54 A41950 Installation of Fire Extingusher&Blanket 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57 Two BedroTwo Bedroom Flats 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21 FinishingFinishing Works 295 20-Sep-12 08-Sep-13 29-Sep-12 02-Oct-13 21 Wet WoWet Works 69 20-Sep-12 13-Dec-12 29-Sep-12 28-Feb-13 64 A42220 Block Works 15 20-Sep-12 07-Oct-12 29-Sep-12 15-Oct-12 7 A42080 Installation of Doors& Windows Sub-frame 7 14-Oct-12 21-Oct-12 21-Feb-13 28-Feb-13 106 A42070 Plaster Works 20 14-Oct-12 07-Nov-12 22-Oct-12 17-Nov-12 7 A42100 Installation of Suspended Ceiling Grid (Dry Area) 8 12-Nov-12 21-Nov-12 21-Nov-12 29-Nov-12 7 A42550 Wall Tiles Work (Wet Area) 13 08-Nov-12 24-Nov-12 31-Dec-12 15-Jan-13 43 A42090 1st Coat Paint 18 22-Nov-12 13-Dec-12 08-Dec-12 27-Dec-12 12 Fisrt StaFisrt Stage Finishes 52 20-Dec-12 20-Feb-13 29-Dec-12 23-Mar-13 26 A42110 Suspended Ceiling Tiles (DryArea) 12 20-Dec-12 03-Jan-13 29-Dec-12 12-Jan-13 7 A42150 Installation of Wardrobes 8 05-Jan-13 13-Jan-13 13-Jan-13 21-Jan-13 7 A42540 Screed Works 9 14-Jan-13 23-Jan-13 22-Jan-13 02-Feb-13 7 A42140 Water Proofing for Wet Area 9 26-Jan-13 04-Feb-13 03-Feb-13 12-Feb-13 7 A42130 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 10-Mar-13 23-Mar-13 37 A42580 Installation of Suspended Ceiling Grid (Wet Area) 7 05-Feb-13 12-Feb-13 13-Feb-13 20-Feb-13 7 A42560 Floor Tiles Work (Wet Area) 5 16-Feb-13 20-Feb-13 24-Feb-13 28-Feb-13 7 A42570 Suspended Ceiling Tiles (Wet Area) 10 10-Feb-13 20-Feb-13 18-Feb-13 28-Feb-13 7 SecondSecond Stage Finishes 19 21-Feb-13 14-Mar-13 02-Mar-13 23-Mar-13 7 A42160 Installation of Windows&Doors 7 21-Feb-13 28-Feb-13 02-Mar-13 09-Mar-13 7 A42230 Doors Ironmongery 6 26-Feb-13 04-Mar-13 17-Mar-13 23-Mar-13 16 A42180 Installation of Kitchen Cabinets 5 02-Mar-13 06-Mar-13 18-Mar-13 23-Mar-13 14 A42210 Installation of Vanity Counter 7 02-Mar-13 09-Mar-13 16-Mar-13 23-Mar-13 12 A42170 Installation of Mirrors 9 02-Mar-13 11-Mar-13 13-Mar-13 23-Mar-13 10 A42200 Installation of Balustrades& Handrails 9 02-Mar-13 11-Mar-13 13-Mar-13 23-Mar-13 10 A42520 Installation of Toliets Accessories 12 02-Mar-13 14-Mar-13 10-Mar-13 23-Mar-13 7 Final StFinal Stage Finishes 150 16-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21 A42120 Final Coat Paint 9 16-Mar-13 25-Mar-13 24-Mar-13 02-Apr-13 7 A42190 Installation of Carpets 4 26-Mar-13 30-Mar-13 22-Apr-13 25-Apr-13 23 A42530 Installation of Sinages 7 23-Mar-13 30-Mar-13 18-Apr-13 25-Apr-13 23 A42240 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 121 08-Oct-12 04-Mar-13 16-Oct-12 02-Apr-13 25 HVACHVAC 109 08-Oct-12 18-Feb-13 10-Nov-12 05-Mar-13 13 A42250 Duct Installation & Insulation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26 A42260 Chilled Water Pipe Installation & Insulation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26 A42270 Condensate Pipe Installation 7 08-Oct-12 15-Oct-12 10-Nov-12 18-Nov-12 26 A42280 FCU Installation 2 16-Oct-12 17-Oct-12 19-Nov-12 20-Nov-12 26 A42290 Air-Outlet Installation 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13 ElectricElectrical 110 08-Oct-12 19-Feb-13 18-Oct-12 05-Mar-13 12 A42300 Install Conduits in Wall 3 08-Oct-12 10-Oct-12 18-Oct-12 21-Oct-12 9 A42310 Install Cable Trays & Trunking 4 08-Oct-12 11-Oct-12 10-Nov-12 13-Nov-12 26 A42350 Cable Laying for Low Current System 3 13-Oct-12 15-Oct-12 27-Nov-12 29-Nov-12 36 A42360 Cable Laying for Power 3 13-Oct-12 15-Oct-12 27-Nov-12 29-Nov-12 36 A42320 Wiring for Lighting & Power 3 08-Nov-12 11-Nov-12 18-Nov-12 20-Nov-12 7 A42330 Wiring for Low Current System 3 08-Nov-12 11-Nov-12 18-Nov-12 20-Nov-12 7 A42340 DB installation,Dressing & Termination 6 15-Dec-12 20-Dec-12 06-Jan-13 12-Jan-13 18 A42390 Installation of Sockets 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13 A42380 Installation of Lighting Fittings 4 16-Feb-13 19-Feb-13 02-Mar-13 05-Mar-13 12 PlumbinPlumbing 121 08-Oct-12 04-Mar-13 16-Oct-12 23-Mar-13 16 A42410 H/L Drainage Pipes Installation 4 08-Oct-12 11-Oct-12 04-Feb-13 07-Feb-13 96 A42420 H/L Hot&Cold Water Pipe Installation 4 08-Oct-12 11-Oct-12 04-Feb-13 07-Feb-13 96 A42470 Water Pipes in Wall 4 08-Oct-12 11-Oct-12 17-Oct-12 21-Oct-12 8 A42400 Drainge Pipes in Wall 5 08-Oct-12 13-Oct-12 16-Oct-12 21-Oct-12 7 A42430 Drainage&Water Pipes Testing 4 13-Oct-12 16-Oct-12 09-Feb-13 12-Feb-13 96 A42440 ElectricalWater Heater Installation 4 13-Oct-12 16-Oct-12 09-Feb-13 12-Feb-13 96 A42450 Floor Drain Fixning 3 16-Jan-13 19-Jan-13 23-Feb-13 25-Feb-13 31 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Floor & Wall Tiles Work (Dry Area) Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Water Pipes in Wall Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Floor Tiles Work (Wet Area) Suspended Ceiling Tiles (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Mirrors Installation of Balustrades& Handrails Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainge Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 45 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 46. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A42460 Installation of Sanitaryware 3 02-Mar-13 04-Mar-13 20-Mar-13 23-Mar-13 16 Fire FigFire Fighting 114 08-Oct-12 24-Feb-13 13-Nov-12 02-Apr-13 32 A42510 Fire Fighting Pipe 3 08-Oct-12 10-Oct-12 13-Nov-12 17-Nov-12 29 A42500 Hydro Static Test for Pipes 3 11-Oct-12 14-Oct-12 18-Nov-12 20-Nov-12 29 A42490 Sprinkler Fixing 3 16-Feb-13 18-Feb-13 03-Mar-13 05-Mar-13 13 A42480 Installation of Fire Extingusher&Blanket 2 19-Feb-13 20-Feb-13 01-Apr-13 02-Apr-13 35 A42590 Fire Alarm Devices 3 21-Feb-13 24-Feb-13 20-Mar-13 23-Mar-13 23 7th Floor7th Floor 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21 Public AreaPublic Area 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10 Garbage RGarbage Room 60 24-Oct-12 07-Jan-13 14-Jan-13 25-Apr-13 92 FinishingFinishing Works 60 24-Oct-12 07-Jan-13 14-Jan-13 25-Apr-13 92 Wet WorWet Works 50 24-Oct-12 25-Dec-12 14-Jan-13 14-Feb-13 42 A20340 Block Works 3 24-Oct-12 29-Oct-12 14-Jan-13 16-Jan-13 65 A20290 Installation of Doors& Windows Sub-frame 1 14-Nov-12 14-Nov-12 14-Feb-13 14-Feb-13 75 A20280 Plaster Works 3 14-Nov-12 18-Nov-12 22-Jan-13 26-Jan-13 56 A20320 Wall Tiles Work 4 21-Nov-12 25-Nov-12 29-Jan-13 02-Feb-13 56 A20300 1st Coat Paint 2 24-Dec-12 25-Dec-12 03-Feb-13 04-Feb-13 33 Fisrt StaFisrt Stage Finishes 7 26-Dec-12 03-Jan-13 10-Feb-13 24-Apr-13 94 A20470 Screed Works 2 26-Dec-12 27-Dec-12 10-Feb-13 11-Feb-13 37 A20490 Floor Tiles Work 2 30-Dec-12 31-Dec-12 13-Feb-13 14-Feb-13 37 A20350 Doors Ironmongery 1 02-Jan-13 02-Jan-13 24-Apr-13 24-Apr-13 95 A20330 Installation of Doors 2 02-Jan-13 03-Jan-13 16-Feb-13 17-Feb-13 37 Second SSecond Stage Finishes 2 05-Jan-13 06-Jan-13 01-Apr-13 02-Apr-13 73 A20310 Final Coat Paint 2 05-Jan-13 06-Jan-13 01-Apr-13 02-Apr-13 73 Final StaFinal Stage Finishes 1 07-Jan-13 07-Jan-13 25-Apr-13 25-Apr-13 92 A20460 Installation of Sinages 1 07-Jan-13 07-Jan-13 25-Apr-13 25-Apr-13 92 MEP WorkMEP Works 54 30-Oct-12 03-Jan-13 17-Jan-13 31-Mar-13 73 ElectricalElectrical 54 30-Oct-12 03-Jan-13 20-Jan-13 05-Mar-13 51 A20360 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 20-Jan-13 21-Jan-13 67 A20370 Wiring for Lighting & Power 2 19-Nov-12 20-Nov-12 27-Jan-13 28-Jan-13 56 A20380 Installation of Lighting Fittings 2 02-Jan-13 03-Jan-13 04-Mar-13 05-Mar-13 51 PlumbingPlumbing 50 30-Oct-12 29-Dec-12 17-Jan-13 12-Feb-13 37 A20390 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 17-Jan-13 19-Jan-13 65 A20420 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 17-Jan-13 19-Jan-13 65 A20400 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 20-Jan-13 21-Jan-13 65 A20410 Floor Drain Fixning 1 29-Dec-12 29-Dec-12 12-Feb-13 12-Feb-13 37 Fire FighFire Fighting 54 30-Oct-12 03-Jan-13 27-Feb-13 31-Mar-13 73 A20450 Fire Fighting Pipe 2 30-Oct-12 31-Oct-12 27-Feb-13 28-Feb-13 99 A20440 Hydro Static Test for Pipes 2 01-Nov-12 03-Nov-12 02-Mar-13 03-Mar-13 99 A20430 Sprinkler Fixing 2 02-Jan-13 03-Jan-13 04-Mar-13 05-Mar-13 51 A20480 Fire Alarm Devices 2 02-Jan-13 03-Jan-13 30-Mar-13 31-Mar-13 73 Corridor &Corridor & Lift Lobby 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10 FinishingFinishing Works 150 15-Oct-12 14-Apr-13 24-Dec-12 25-Apr-13 10 Wet WorWet Works 51 15-Oct-12 17-Dec-12 24-Dec-12 07-Feb-13 43 A20000 Block Works 8 15-Oct-12 23-Oct-12 24-Dec-12 02-Jan-13 56 A19940 Plaster Works 7 06-Nov-12 13-Nov-12 06-Jan-13 13-Jan-13 49 A19960 Installation of Suspended Ceiling Grid 6 03-Dec-12 09-Dec-12 19-Jan-13 26-Jan-13 39 A19970 Suspended Ceiling Tiles 6 10-Dec-12 16-Dec-12 27-Jan-13 02-Feb-13 39 A20260 MDF for Lift Lobby Wall 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43 Fisrt StaFisrt Stage Finishes 18 18-Dec-12 08-Jan-13 09-Feb-13 17-Feb-13 33 A20240 Screed Works 3 18-Dec-12 20-Dec-12 09-Feb-13 11-Feb-13 43 A19950 1st Coat Paint 5 03-Jan-13 08-Jan-13 12-Feb-13 17-Feb-13 33 Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 18-Feb-13 25-Apr-13 89 A19980 Installation of Doors 2 09-Jan-13 10-Jan-13 18-Feb-13 19-Feb-13 33 A20010 Doors Ironmongery 2 09-Jan-13 10-Jan-13 24-Apr-13 25-Apr-13 89 Final StaFinal Stage Finishes 20 23-Mar-13 14-Apr-13 03-Apr-13 25-Apr-13 10 A19990 Installation of Carpets 4 23-Mar-13 26-Mar-13 03-Apr-13 07-Apr-13 10 A20250 Fixing of Wall Covering 7 27-Mar-13 03-Apr-13 08-Apr-13 15-Apr-13 10 A20230 Installation of Sinages 9 04-Apr-13 14-Apr-13 16-Apr-13 25-Apr-13 10 MEP WorkMEP Works 50 24-Oct-12 25-Dec-12 03-Jan-13 05-Mar-13 58 HVACHVAC 45 24-Oct-12 19-Dec-12 09-Jan-13 11-Feb-13 44 A20020 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61 A20030 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61 A20040 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 09-Jan-13 14-Jan-13 61 A20050 FCU Installation 3 01-Nov-12 04-Nov-12 15-Jan-13 17-Jan-13 61 A20060 Air-Outlet Installation 3 17-Dec-12 19-Dec-12 09-Feb-13 11-Feb-13 44 ElectricalElectrical 46 24-Oct-12 20-Dec-12 03-Jan-13 05-Mar-13 62 A20070 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 03-Jan-13 05-Jan-13 56 A20080 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 09-Jan-13 10-Jan-13 61 A20120 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 23-Jan-13 26-Jan-13 71 A20130 Cable Laying for Power 3 29-Oct-12 31-Oct-12 22-Jan-13 26-Jan-13 70 A20090 Wiring for Lighting & Power 3 14-Nov-12 18-Nov-12 15-Jan-13 17-Jan-13 50 A20100 Wiring for Low Current System 4 14-Nov-12 19-Nov-12 14-Jan-13 17-Jan-13 49 A20110 DB installation,Dressing & Termination 6 10-Dec-12 16-Dec-12 27-Jan-13 02-Feb-13 39 A20150 Installation of Lighting Fittings 3 17-Dec-12 19-Dec-12 03-Mar-13 05-Mar-13 63 A20160 Installation of Sockets 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62 PlumbingPlumbing 5 24-Oct-12 31-Oct-12 13-Jan-13 17-Jan-13 64 A20170 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 13-Jan-13 17-Jan-13 64 Fire FighFire Fighting 50 24-Oct-12 25-Dec-12 09-Jan-13 11-Feb-13 39 A20220 Fire Fighting Pipe 4 24-Oct-12 30-Oct-12 09-Jan-13 13-Jan-13 61 A20210 Hydro Static Test for Pipes 4 31-Oct-12 04-Nov-12 14-Jan-13 17-Jan-13 61 A20200 Sprinkler Fixing 4 17-Dec-12 20-Dec-12 03-Feb-13 06-Feb-13 39 A20270 Fire Alarm Devices 5 17-Dec-12 22-Dec-12 06-Feb-13 11-Feb-13 42 A20190 Installation of Fire Extingusher&Blanket 4 22-Dec-12 25-Dec-12 07-Feb-13 11-Feb-13 39 Electrical /Electrical /Telephone/ELV Rooms 77 30-Oct-12 31-Jan-13 21-Jan-13 25-Apr-13 72 FinishingFinishing Works 77 30-Oct-12 31-Jan-13 21-Jan-13 25-Apr-13 72 Wet WorWet Works 50 30-Oct-12 29-Dec-12 21-Jan-13 19-Feb-13 43 A20550 Block Works 3 30-Oct-12 01-Nov-12 21-Jan-13 23-Jan-13 68 A20510 Installation of Doors& Windows Sub-frame 1 19-Nov-12 19-Nov-12 19-Feb-13 19-Feb-13 76 A20500 Plaster Works 4 19-Nov-12 22-Nov-12 28-Jan-13 31-Jan-13 57 A20520 1st Coat Paint 3 26-Dec-12 29-Dec-12 05-Feb-13 07-Feb-13 33 Fisrt StaFisrt Stage Finishes 13 12-Jan-13 27-Jan-13 20-Feb-13 23-Apr-13 74 A20540 Installation of Doors 2 12-Jan-13 13-Jan-13 20-Feb-13 21-Feb-13 33 A20560 Doors Ironmongery 2 12-Jan-13 13-Jan-13 22-Apr-13 23-Apr-13 85 A20610 Epoxy Paint Works 2 26-Jan-13 27-Jan-13 30-Mar-13 31-Mar-13 54 Second SSecond Stage Finishes 2 28-Jan-13 29-Jan-13 01-Apr-13 02-Apr-13 54 A20530 Final Coat Paint 2 28-Jan-13 29-Jan-13 01-Apr-13 02-Apr-13 54 Final StaFinal Stage Finishes 2 30-Jan-13 31-Jan-13 24-Apr-13 25-Apr-13 72 A20600 Installation of Sinages 2 30-Jan-13 31-Jan-13 24-Apr-13 25-Apr-13 72 MEP WorkMEP Works 68 03-Nov-12 23-Jan-13 26-Jan-13 28-Mar-13 54 HVACHVAC 2 30-Dec-12 31-Dec-12 04-Mar-13 05-Mar-13 53 A20640 Air-Outlet Installation 2 30-Dec-12 31-Dec-12 04-Mar-13 05-Mar-13 53 ElectricalElectrical 68 03-Nov-12 23-Jan-13 26-Jan-13 05-Mar-13 34 A20570 Install Conduits in Wall 2 03-Nov-12 04-Nov-12 26-Jan-13 27-Jan-13 68 A20580 Wiring for Lighting & Power 2 24-Nov-12 25-Nov-12 03-Feb-13 04-Feb-13 58 A20630 Installation of SMDBs 7 30-Dec-12 07-Jan-13 24-Feb-13 03-Mar-13 46 A20590 Installation of Lighting Fittings 2 08-Jan-13 09-Jan-13 04-Mar-13 05-Mar-13 46 A114580 Installation of Access ControlSystem 20 30-Dec-12 22-Jan-13 11-Feb-13 05-Mar-13 35 A114560 Installation of MATC,TV System 20 30-Dec-12 22-Jan-13 11-Feb-13 05-Mar-13 35 A114570 Installation of Telephone System 21 30-Dec-12 23-Jan-13 10-Feb-13 05-Mar-13 34 Fire FighFire Fighting 2 10-Jan-13 12-Jan-13 27-Mar-13 28-Mar-13 64 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Installation of Telephone System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 46 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 47. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A20620 Fire Alarm Devices 2 10-Jan-13 12-Jan-13 27-Mar-13 28-Mar-13 64 Room ServRoom Service 61 03-Nov-12 15-Jan-13 26-Jan-13 25-Apr-13 85 FinishingFinishing Works 61 03-Nov-12 15-Jan-13 26-Jan-13 25-Apr-13 85 Wet WorWet Works 50 03-Nov-12 02-Jan-13 26-Jan-13 21-Feb-13 42 A20700 Block Works 2 03-Nov-12 04-Nov-12 26-Jan-13 27-Jan-13 68 A20660 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 21-Feb-13 21-Feb-13 74 A20650 Plaster Works 4 24-Nov-12 27-Nov-12 02-Feb-13 05-Feb-13 57 A20670 1st Coat Paint 3 30-Dec-12 02-Jan-13 09-Feb-13 11-Feb-13 33 Fisrt StaFisrt Stage Finishes 10 03-Jan-13 14-Jan-13 16-Feb-13 24-Apr-13 85 A20830 Screed Works 2 03-Jan-13 05-Jan-13 16-Feb-13 17-Feb-13 36 A20850 Floor Tiles Work 3 07-Jan-13 09-Jan-13 19-Feb-13 21-Feb-13 36 A20690 Installation of Doors 1 14-Jan-13 14-Jan-13 23-Feb-13 23-Feb-13 33 A20710 Doors Ironmongery 1 14-Jan-13 14-Jan-13 24-Apr-13 24-Apr-13 85 Second SSecond Stage Finishes 1 13-Jan-13 13-Jan-13 02-Apr-13 02-Apr-13 67 A20680 Final Coat Paint 1 13-Jan-13 13-Jan-13 02-Apr-13 02-Apr-13 67 Final StaFinal Stage Finishes 1 15-Jan-13 15-Jan-13 25-Apr-13 25-Apr-13 85 A20820 Installation of Sinages 1 15-Jan-13 15-Jan-13 25-Apr-13 25-Apr-13 85 MEP WorkMEP Works 56 05-Nov-12 12-Jan-13 28-Jan-13 01-Apr-13 67 HVACHVAC 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 A20860 Air-Outlet Installation 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 ElectricalElectrical 56 05-Nov-12 12-Jan-13 30-Jan-13 05-Mar-13 44 A20720 Install Conduits in Wall 2 05-Nov-12 06-Nov-12 30-Jan-13 31-Jan-13 70 A20730 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 06-Feb-13 07-Feb-13 57 A20740 Installation of Lighting Fittings 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 PlumbingPlumbing 51 05-Nov-12 06-Jan-13 28-Jan-13 18-Feb-13 36 A20750 Drainge Pipes in Wall 2 05-Nov-12 06-Nov-12 28-Jan-13 29-Jan-13 68 A20780 Water Pipes in Wall 2 05-Nov-12 06-Nov-12 28-Jan-13 29-Jan-13 68 A20760 Drainage&Water Pipes Testing 2 07-Nov-12 08-Nov-12 30-Jan-13 31-Jan-13 68 A20770 Floor Drain Fixning 1 06-Jan-13 06-Jan-13 18-Feb-13 18-Feb-13 36 Fire FighFire Fighting 56 05-Nov-12 12-Jan-13 27-Feb-13 01-Apr-13 67 A20810 Fire Fighting Pipe 2 05-Nov-12 06-Nov-12 27-Feb-13 28-Feb-13 94 A20800 Hydro Static Test for Pipes 2 07-Nov-12 08-Nov-12 02-Mar-13 03-Mar-13 94 A20790 Sprinkler Fixing 2 10-Jan-13 12-Jan-13 04-Mar-13 05-Mar-13 44 A20840 Fire Alarm Devices 2 10-Jan-13 12-Jan-13 31-Mar-13 01-Apr-13 67 StaircaseStaircase 71 08-Nov-12 03-Feb-13 29-Dec-12 02-Apr-13 50 Stair 1Stair 1 57 08-Nov-12 16-Jan-13 29-Dec-12 02-Apr-13 64 A108890 Floor Screed 3 08-Nov-12 11-Nov-12 29-Dec-12 31-Dec-12 41 A108900 Install Handrails 4 12-Nov-12 17-Nov-12 02-Jan-13 06-Jan-13 41 A108910 Ceiling 1st Coat Paint 7 08-Dec-12 15-Dec-12 07-Jan-13 14-Jan-13 25 A108920 Wall 1st Coat Paint 7 16-Dec-12 23-Dec-12 15-Jan-13 22-Jan-13 25 A108930 Install Granite/Terrazo 11 24-Dec-12 06-Jan-13 28-Jan-13 09-Feb-13 28 A108940 Final Coat Paint 9 07-Jan-13 16-Jan-13 24-Mar-13 02-Apr-13 64 Stair 2Stair 2 68 12-Nov-12 03-Feb-13 15-Jan-13 04-Mar-13 25 A108950 Floor Screed 3 12-Nov-12 14-Nov-12 15-Jan-13 17-Jan-13 52 A108960 Install Handrails 4 18-Nov-12 21-Nov-12 19-Jan-13 22-Jan-13 51 A108970 Ceiling 1st Coat Paint 7 24-Dec-12 31-Dec-12 23-Jan-13 31-Jan-13 25 A108980 Wall 1st Coat Paint 7 02-Jan-13 09-Jan-13 02-Feb-13 09-Feb-13 25 A108990 Install Granite/Terrazo 11 10-Jan-13 22-Jan-13 10-Feb-13 21-Feb-13 25 A109000 Final Coat Paint 9 23-Jan-13 03-Feb-13 23-Feb-13 04-Mar-13 25 ApartementsApartements 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21 Studio FlatsStudio Flats 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (Studio) 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 FinishingFinishing Works 283 04-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Wet WoWet Works 38 04-Oct-12 20-Nov-12 21-Oct-12 23-Feb-13 78 A42750 Block Works 4 04-Oct-12 08-Oct-12 21-Oct-12 24-Oct-12 14 A42610 Installation of Doors& Windows Sub-frame 1 29-Oct-12 29-Oct-12 23-Feb-13 23-Feb-13 96 A42600 Plaster Works 7 29-Oct-12 05-Nov-12 14-Nov-12 22-Nov-12 14 A43080 Wall Tiles Work (Wet Area) 8 06-Nov-12 14-Nov-12 30-Dec-12 08-Jan-13 44 A42630 Installation of Suspended Ceiling Grid (Dry Area) 6 10-Nov-12 17-Nov-12 27-Nov-12 04-Dec-12 14 A42620 1st Coat Paint 3 18-Nov-12 20-Nov-12 11-Dec-12 13-Dec-12 19 Fisrt StaFisrt Stage Finishes 25 21-Nov-12 20-Dec-12 10-Jan-13 05-Mar-13 62 A42640 Suspended Ceiling Tiles (DryArea) 6 21-Nov-12 27-Nov-12 10-Jan-13 16-Jan-13 41 A42680 Installation of Wardrobes 2 28-Nov-12 29-Nov-12 17-Jan-13 19-Jan-13 41 A43070 Screed Works 5 01-Dec-12 06-Dec-12 27-Jan-13 31-Jan-13 46 A42670 Water Proofing for Wet Area 3 08-Dec-12 10-Dec-12 02-Feb-13 04-Feb-13 46 A42660 Floor & Wall Tiles Work (Dry Area) 4 08-Dec-12 11-Dec-12 02-Mar-13 05-Mar-13 70 A43110 Installation of Suspended Ceiling Grid (Wet Area) 3 11-Dec-12 13-Dec-12 05-Feb-13 07-Feb-13 46 A43100 Suspended Ceiling Tiles (Wet Area) 2 17-Dec-12 18-Dec-12 11-Feb-13 12-Feb-13 46 A43090 Floor Tiles Work (Wet Area) 2 19-Dec-12 20-Dec-12 16-Feb-13 17-Feb-13 48 SecondSecond Stage Finishes 4 15-Jan-13 19-Jan-13 24-Feb-13 10-Mar-13 42 A42690 Installation of Windows&Doors 2 15-Jan-13 16-Jan-13 24-Feb-13 25-Feb-13 33 A42760 Doors Ironmongery 2 15-Jan-13 16-Jan-13 09-Mar-13 10-Mar-13 44 A42700 Installation of Mirrors 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42 A42710 Installation of Kitchen Cabinets 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42 A42730 Installation of Balustrades& Handrails 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42 A42740 Installation of Vanity Counter 2 17-Jan-13 19-Jan-13 09-Mar-13 10-Mar-13 42 A43050 Installation of Toliets Accessories 2 17-Jan-13 19-Jan-13 03-Mar-13 04-Mar-13 37 Final StFinal Stage Finishes 195 21-Jan-13 08-Sep-13 11-Mar-13 02-Oct-13 21 A42650 Final Coat Paint 6 21-Jan-13 28-Jan-13 11-Mar-13 17-Mar-13 41 A42720 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A43060 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A42770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 84 09-Oct-12 20-Jan-13 10-Nov-12 17-Mar-13 47 HVACHVAC 60 09-Oct-12 22-Dec-12 17-Nov-12 05-Mar-13 61 A42780 Duct Installation & Insulation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30 A42790 Chilled Water Pipe Installation & Insulation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30 A42800 Condensate Pipe Installation 7 09-Oct-12 16-Oct-12 17-Nov-12 24-Nov-12 30 A42810 FCU Installation 2 17-Oct-12 18-Oct-12 25-Nov-12 26-Nov-12 30 A42820 Air-Outlet Installation 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61 ElectricElectrical 61 09-Oct-12 23-Dec-12 11-Nov-12 05-Mar-13 60 A42830 Install Conduits in Wall 3 09-Oct-12 11-Oct-12 11-Nov-12 13-Nov-12 26 A42840 Install Cable Trays & Trunking 4 09-Oct-12 13-Oct-12 17-Nov-12 20-Nov-12 30 A42880 Cable Laying for Low Current System 3 14-Oct-12 16-Oct-12 01-Dec-12 04-Dec-12 38 A42890 Cable Laying for Power 3 14-Oct-12 16-Oct-12 01-Dec-12 04-Dec-12 38 A42850 Wiring for Lighting & Power 3 06-Nov-12 08-Nov-12 24-Nov-12 26-Nov-12 14 A42860 Wiring for Low Current System 3 06-Nov-12 08-Nov-12 24-Nov-12 26-Nov-12 14 A42870 DB installation,Dressing & Termination 6 21-Nov-12 27-Nov-12 10-Jan-13 16-Jan-13 41 A42920 Installation of Sockets 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61 A42910 Installation of Lighting Fittings 4 19-Dec-12 23-Dec-12 02-Mar-13 05-Mar-13 60 PlumbinPlumbing 84 09-Oct-12 20-Jan-13 10-Nov-12 10-Mar-13 41 A42930 Drainge Pipes in Wall 4 09-Oct-12 13-Oct-12 10-Nov-12 13-Nov-12 25 A42940 H/L Drainage Pipes Installation 4 09-Oct-12 13-Oct-12 27-Jan-13 30-Jan-13 88 A42950 H/L Hot&Cold Water Pipe Installation 4 09-Oct-12 13-Oct-12 27-Jan-13 30-Jan-13 88 A43000 Water Pipes in Wall 4 09-Oct-12 13-Oct-12 10-Nov-12 13-Nov-12 25 A42960 Drainage&Water Pipes Testing 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88 A42970 ElectricalWater Heater Installation 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88 A42980 Floor Drain Fixning 3 04-Dec-12 06-Dec-12 11-Feb-13 13-Feb-13 57 A42990 Installation of Sanitaryware 3 17-Jan-13 20-Jan-13 07-Mar-13 10-Mar-13 41 Fire FigFire Fighting 62 09-Oct-12 24-Dec-12 20-Nov-12 17-Mar-13 69 A43040 Fire Fighting Pipe 3 09-Oct-12 11-Oct-12 20-Nov-12 22-Nov-12 33 A43030 Hydro Static Test for Pipes 3 13-Oct-12 15-Oct-12 24-Nov-12 26-Nov-12 33 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Installation of Kitchen Cabinets Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 47 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 48. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A43020 Sprinkler Fixing 3 19-Dec-12 22-Dec-12 03-Mar-13 05-Mar-13 61 A43120 Fire Alarm Devices 3 19-Dec-12 22-Dec-12 07-Mar-13 10-Mar-13 65 A43010 Installation of Fire Extingusher&Blanket 2 23-Dec-12 24-Dec-12 16-Mar-13 17-Mar-13 69 One BedroOne Bedroom Flats 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 (1 BR) 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21 FinishingFinishing Works 279 09-Oct-12 08-Sep-13 28-Oct-12 02-Oct-13 21 Wet WoWet Works 34 09-Oct-12 20-Nov-12 28-Oct-12 25-Feb-13 80 A43280 Block Works 5 09-Oct-12 14-Oct-12 28-Oct-12 01-Nov-12 14 A43140 Installation of Doors& Windows Sub-frame 1 18-Oct-12 18-Oct-12 25-Feb-13 25-Feb-13 105 A43130 Plaster Works 7 18-Oct-12 28-Oct-12 06-Nov-12 13-Nov-12 14 A43160 Installation of Suspended Ceiling Grid (Dry Area) 4 01-Nov-12 05-Nov-12 22-Nov-12 26-Nov-12 17 A43150 1st Coat Paint 6 06-Nov-12 12-Nov-12 04-Dec-12 10-Dec-12 22 A43610 Wall Tiles Work (Wet Area) 4 17-Nov-12 20-Nov-12 09-Jan-13 13-Jan-13 44 Fisrt StaFisrt Stage Finishes 36 17-Nov-12 29-Dec-12 06-Jan-13 09-Mar-13 58 A43170 Suspended Ceiling Tiles (DryArea) 4 17-Nov-12 20-Nov-12 06-Jan-13 09-Jan-13 41 A43210 Installation of Wardrobes 4 21-Nov-12 25-Nov-12 13-Jan-13 16-Jan-13 43 A43600 Screed Works 9 26-Nov-12 06-Dec-12 23-Jan-13 03-Feb-13 48 A43200 Water Proofing for Wet Area 4 08-Dec-12 11-Dec-12 04-Feb-13 07-Feb-13 48 A43190 Floor & Wall Tiles Work (Dry Area) 3 12-Dec-12 15-Dec-12 06-Mar-13 09-Mar-13 70 A43640 Installation of Suspended Ceiling Grid (Wet Area) 4 15-Dec-12 18-Dec-12 09-Feb-13 12-Feb-13 46 A43630 Suspended Ceiling Tiles (Wet Area) 4 19-Dec-12 23-Dec-12 13-Feb-13 17-Feb-13 46 A43620 Floor Tiles Work (Wet Area) 5 24-Dec-12 29-Dec-12 18-Feb-13 23-Feb-13 46 SecondSecond Stage Finishes 7 17-Jan-13 26-Jan-13 26-Feb-13 17-Mar-13 43 A43220 Installation of Windows&Doors 3 17-Jan-13 20-Jan-13 26-Feb-13 28-Feb-13 33 A43290 Doors Ironmongery 3 17-Jan-13 20-Jan-13 14-Mar-13 17-Mar-13 47 A43260 Installation of Balustrades& Handrails 2 21-Jan-13 22-Jan-13 16-Mar-13 17-Mar-13 45 A43230 Installation of Mirrors 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44 A43240 Installation of Kitchen Cabinets 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44 A43270 Installation of Vanity Counter 3 21-Jan-13 23-Jan-13 12-Mar-13 14-Mar-13 42 A43580 Installation of Toliets Accessories 4 21-Jan-13 26-Jan-13 05-Mar-13 09-Mar-13 36 Final StFinal Stage Finishes 189 29-Jan-13 08-Sep-13 18-Mar-13 02-Oct-13 21 A43180 Final Coat Paint 5 29-Jan-13 03-Feb-13 18-Mar-13 23-Mar-13 41 A43250 Installation of Carpets 4 21-Mar-13 25-Mar-13 22-Apr-13 25-Apr-13 27 A43590 Installation of Sinages 7 18-Mar-13 25-Mar-13 18-Apr-13 25-Apr-13 27 A43300 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 82 15-Oct-12 23-Jan-13 03-Nov-12 23-Mar-13 49 HVACHVAC 59 15-Oct-12 26-Dec-12 11-Nov-12 05-Mar-13 57 A43310 Duct Installation & Insulation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21 A43320 Chilled Water Pipe Installation & Insulation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21 A43330 Condensate Pipe Installation 7 15-Oct-12 22-Oct-12 11-Nov-12 19-Nov-12 21 A43340 FCU Installation 2 23-Oct-12 24-Oct-12 20-Nov-12 21-Nov-12 21 A43350 Air-Outlet Installation 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57 ElectricElectrical 60 15-Oct-12 27-Dec-12 03-Nov-12 05-Mar-13 56 A43360 Install Conduits in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14 A43370 Install Cable Trays & Trunking 4 15-Oct-12 18-Oct-12 07-Nov-12 11-Nov-12 18 A43410 Cable Laying for Low Current System 3 20-Oct-12 22-Oct-12 24-Nov-12 26-Nov-12 27 A43420 Cable Laying for Power 3 20-Oct-12 22-Oct-12 24-Nov-12 26-Nov-12 27 A43380 Wiring for Lighting & Power 3 29-Oct-12 31-Oct-12 19-Nov-12 21-Nov-12 17 A43390 Wiring for Low Current System 3 29-Oct-12 31-Oct-12 19-Nov-12 21-Nov-12 17 A43400 DB installation,Dressing & Termination 6 13-Nov-12 20-Nov-12 03-Jan-13 09-Jan-13 41 A43450 Installation of Sockets 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57 A43440 Installation of Lighting Fittings 4 24-Dec-12 27-Dec-12 02-Mar-13 05-Mar-13 56 PlumbinPlumbing 82 15-Oct-12 23-Jan-13 03-Nov-12 17-Mar-13 44 A43460 Drainge Pipes in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14 A43530 Water Pipes in Wall 3 15-Oct-12 17-Oct-12 03-Nov-12 05-Nov-12 14 A43470 H/L Drainage Pipes Installation 4 15-Oct-12 18-Oct-12 30-Jan-13 03-Feb-13 86 A43480 H/L Hot&Cold Water Pipe Installation 4 15-Oct-12 18-Oct-12 30-Jan-13 03-Feb-13 86 A43490 Drainage&Water Pipes Testing 4 20-Oct-12 23-Oct-12 04-Feb-13 07-Feb-13 86 A43500 ElectricalWater Heater Installation 4 20-Oct-12 23-Oct-12 04-Feb-13 07-Feb-13 86 A43510 Floor Drain Fixning 3 28-Nov-12 01-Dec-12 17-Feb-13 19-Feb-13 66 A43520 Installation of Sanitaryware 3 21-Jan-13 23-Jan-13 14-Mar-13 17-Mar-13 44 Fire FigFire Fighting 61 15-Oct-12 29-Dec-12 14-Nov-12 23-Mar-13 70 A43570 Fire Fighting Pipe 3 15-Oct-12 17-Oct-12 14-Nov-12 18-Nov-12 24 A43560 Hydro Static Test for Pipes 3 18-Oct-12 21-Oct-12 19-Nov-12 21-Nov-12 24 A43550 Sprinkler Fixing 3 24-Dec-12 26-Dec-12 03-Mar-13 05-Mar-13 57 A43650 Fire Alarm Devices 3 24-Dec-12 26-Dec-12 14-Mar-13 17-Mar-13 67 A43540 Installation of Fire Extingusher&Blanket 2 27-Dec-12 29-Dec-12 21-Mar-13 23-Mar-13 70 Two BedroTwo Bedroom Flats 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21 ApartemeApartement .1 - 2 - 3 - 4 - 5 - 6 (2 BR) 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21 FinishingFinishing Works 283 04-Oct-12 08-Sep-13 16-Oct-12 02-Oct-13 21 Wet WoWet Works 65 04-Oct-12 23-Dec-12 16-Oct-12 28-Feb-13 56 A43810 Block Works 15 04-Oct-12 21-Oct-12 16-Oct-12 04-Nov-12 10 A43670 Installation of Doors& Windows Sub-frame 7 28-Oct-12 04-Nov-12 21-Feb-13 28-Feb-13 96 A43660 Plaster Works 18 28-Oct-12 18-Nov-12 08-Nov-12 29-Nov-12 10 A43690 Installation of Suspended Ceiling Grid (Dry Area) 8 22-Nov-12 01-Dec-12 05-Dec-12 13-Dec-12 10 A44140 Wall Tiles Work (Wet Area) 13 21-Nov-12 06-Dec-12 14-Jan-13 29-Jan-13 44 A43680 1st Coat Paint 18 03-Dec-12 23-Dec-12 15-Dec-12 05-Jan-13 10 Fisrt StaFisrt Stage Finishes 46 24-Dec-12 17-Feb-13 06-Jan-13 23-Mar-13 29 A43700 Suspended Ceiling Tiles (DryArea) 12 24-Dec-12 07-Jan-13 06-Jan-13 19-Jan-13 10 A43740 Installation of Wardrobes 8 08-Jan-13 16-Jan-13 20-Jan-13 29-Jan-13 10 A44130 Screed Works 9 17-Jan-13 28-Jan-13 30-Jan-13 09-Feb-13 10 A43730 Water Proofing for Wet Area 9 22-Jan-13 02-Feb-13 04-Feb-13 13-Feb-13 10 A44170 Installation of Suspended Ceiling Grid (Wet Area) 7 28-Jan-13 04-Feb-13 09-Feb-13 16-Feb-13 10 A43720 Floor & Wall Tiles Work (Dry Area) 12 29-Jan-13 11-Feb-13 10-Mar-13 23-Mar-13 34 A44160 Suspended Ceiling Tiles (Wet Area) 10 31-Jan-13 11-Feb-13 12-Feb-13 23-Feb-13 10 A44150 Floor Tiles Work (Wet Area) 5 12-Feb-13 17-Feb-13 24-Feb-13 28-Feb-13 10 SecondSecond Stage Finishes 19 18-Feb-13 11-Mar-13 02-Mar-13 23-Mar-13 10 A43750 Installation of Windows&Doors 7 18-Feb-13 25-Feb-13 02-Mar-13 09-Mar-13 10 A43820 Doors Ironmongery 6 21-Feb-13 27-Feb-13 17-Mar-13 23-Mar-13 20 A43770 Installation of Kitchen Cabinets 5 26-Feb-13 03-Mar-13 18-Mar-13 23-Mar-13 17 A43800 Installation of Vanity Counter 7 26-Feb-13 05-Mar-13 16-Mar-13 23-Mar-13 15 A43760 Installation of Mirrors 9 26-Feb-13 07-Mar-13 13-Mar-13 23-Mar-13 13 A43790 Installation of Balustrades& Handrails 9 26-Feb-13 07-Mar-13 13-Mar-13 23-Mar-13 13 A44110 Installation of Toliets Accessories 12 26-Feb-13 11-Mar-13 10-Mar-13 23-Mar-13 10 Final StFinal Stage Finishes 153 12-Mar-13 08-Sep-13 24-Mar-13 02-Oct-13 21 A43710 Final Coat Paint 9 12-Mar-13 21-Mar-13 24-Mar-13 02-Apr-13 10 A43780 Installation of Carpets 4 23-Mar-13 26-Mar-13 22-Apr-13 25-Apr-13 26 A44120 Installation of Sinages 7 19-Mar-13 26-Mar-13 18-Apr-13 25-Apr-13 26 A43830 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 116 10-Oct-12 28-Feb-13 05-Nov-12 02-Apr-13 28 HVACHVAC 94 22-Oct-12 14-Feb-13 24-Nov-12 05-Mar-13 16 A43840 Duct Installation & Insulation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25 A43850 Chilled Water Pipe Installation & Insulation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25 A43860 Condensate Pipe Installation 7 22-Oct-12 31-Oct-12 24-Nov-12 01-Dec-12 25 A43870 FCU Installation 2 01-Nov-12 03-Nov-12 03-Dec-12 04-Dec-12 25 A43880 Air-Outlet Installation 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 ElectricElectrical 95 22-Oct-12 16-Feb-13 05-Nov-12 05-Mar-13 15 A43890 Install Conduits in Wall 3 22-Oct-12 24-Oct-12 05-Nov-12 07-Nov-12 10 A43900 Install Cable Trays & Trunking 4 22-Oct-12 28-Oct-12 24-Nov-12 27-Nov-12 25 A43940 Cable Laying for Low Current System 3 29-Oct-12 31-Oct-12 11-Dec-12 13-Dec-12 35 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Wall Tiles Work (Wet Area) Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Mirrors Installation of Balustrades& Handrails Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 48 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 49. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A43950 Cable Laying for Power 3 29-Oct-12 31-Oct-12 11-Dec-12 13-Dec-12 35 A43910 Wiring for Lighting & Power 3 19-Nov-12 21-Nov-12 01-Dec-12 04-Dec-12 10 A43920 Wiring for Low Current System 3 19-Nov-12 21-Nov-12 01-Dec-12 04-Dec-12 10 A43930 DB installation,Dressing & Termination 6 24-Dec-12 30-Dec-12 13-Jan-13 19-Jan-13 16 A43980 Installation of Sockets 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 A43970 Installation of Lighting Fittings 4 12-Feb-13 16-Feb-13 02-Mar-13 05-Mar-13 15 PlumbinPlumbing 116 10-Oct-12 28-Feb-13 05-Nov-12 23-Mar-13 19 A44060 Water Pipes in Wall 3 10-Oct-12 13-Oct-12 05-Nov-12 07-Nov-12 20 A43990 Drainge Pipes in Wall 3 22-Oct-12 24-Oct-12 05-Nov-12 07-Nov-12 10 A44000 H/L Drainage Pipes Installation 4 22-Oct-12 28-Oct-12 30-Jan-13 03-Feb-13 80 A44010 H/L Hot&Cold Water Pipe Installation 4 22-Oct-12 28-Oct-12 30-Jan-13 03-Feb-13 80 A44020 Drainage&Water Pipes Testing 4 29-Oct-12 01-Nov-12 04-Feb-13 07-Feb-13 80 A44030 ElectricalWater Heater Installation 4 29-Oct-12 01-Nov-12 04-Feb-13 07-Feb-13 80 A44040 Floor Drain Fixning 3 20-Jan-13 22-Jan-13 23-Feb-13 25-Feb-13 28 A44050 Installation of Sanitaryware 3 26-Feb-13 28-Feb-13 20-Mar-13 23-Mar-13 19 Fire FigFire Fighting 96 22-Oct-12 17-Feb-13 27-Nov-12 02-Apr-13 38 A44100 Fire Fighting Pipe 3 22-Oct-12 24-Oct-12 27-Nov-12 29-Nov-12 28 A44090 Hydro Static Test for Pipes 3 28-Oct-12 30-Oct-12 01-Dec-12 04-Dec-12 28 A44080 Sprinkler Fixing 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 A44180 Fire Alarm Devices 3 12-Feb-13 14-Feb-13 20-Mar-13 23-Mar-13 31 A44070 Installation of Fire Extingusher&Blanket 2 16-Feb-13 17-Feb-13 01-Apr-13 02-Apr-13 38 Roof LevelRoof Level 301 13-Sep-12 08-Sep-13 03-Nov-12 02-Oct-13 21 Public AreaPublic Area 301 13-Sep-12 08-Sep-13 03-Nov-12 02-Oct-13 21 SwimmimgSwimmimg Pool Room 115 18-Oct-12 07-Mar-13 03-Nov-12 25-Apr-13 42 FinishingFinishing Works 115 18-Oct-12 07-Mar-13 03-Nov-12 25-Apr-13 42 Wet WorWet Works 76 18-Oct-12 20-Jan-13 03-Nov-12 21-Apr-13 77 A44240 Block Works 4 18-Oct-12 22-Oct-12 03-Nov-12 06-Nov-12 11 A44190 Plaster Works 6 24-Dec-12 30-Dec-12 07-Jan-13 13-Jan-13 11 A44200 Installation of Doors& Windows Sub-frame 1 19-Jan-13 19-Jan-13 21-Apr-13 21-Apr-13 78 A44210 1st Coat Paint 11 08-Jan-13 20-Jan-13 21-Jan-13 03-Feb-13 11 Fisrt StaFisrt Stage Finishes 14 13-Feb-13 28-Feb-13 14-Apr-13 23-Apr-13 46 A44230 Installation of Doors 2 13-Feb-13 14-Feb-13 22-Apr-13 23-Apr-13 58 A44250 Doors Ironmongery 2 13-Feb-13 14-Feb-13 22-Apr-13 23-Apr-13 58 A44300 Epoxy Paint Works 5 24-Feb-13 28-Feb-13 14-Apr-13 18-Apr-13 42 Second SSecond Stage Finishes 4 02-Mar-13 05-Mar-13 20-Apr-13 23-Apr-13 42 A44220 Final Coat Paint 4 02-Mar-13 05-Mar-13 20-Apr-13 23-Apr-13 42 Final StaFinal Stage Finishes 2 06-Mar-13 07-Mar-13 24-Apr-13 25-Apr-13 42 A44290 Installation of Sinages 2 06-Mar-13 07-Mar-13 24-Apr-13 25-Apr-13 42 MEP WorkMEP Works 98 23-Oct-12 20-Feb-13 07-Nov-12 23-Apr-13 53 HVACHVAC 20 23-Oct-12 18-Nov-12 07-Nov-12 04-Feb-13 64 A44360 Duct Installation & Insulation 7 23-Oct-12 01-Nov-12 07-Nov-12 14-Nov-12 11 A44370 Chilled Water Pipe Installation & Insulation 7 23-Oct-12 01-Nov-12 07-Nov-12 14-Nov-12 11 A44380 Condensate Pipe Installation 7 23-Oct-12 01-Nov-12 19-Nov-12 26-Nov-12 20 A44390 FCU Installation 5 03-Nov-12 07-Nov-12 27-Nov-12 03-Dec-12 20 A44400 Air-Outlet Installation 8 08-Nov-12 18-Nov-12 27-Jan-13 04-Feb-13 64 ElectricalElectrical 82 23-Oct-12 02-Feb-13 30-Dec-12 05-Mar-13 27 A44260 Install Conduits in Wall 6 23-Oct-12 31-Oct-12 30-Dec-12 06-Jan-13 54 A44270 Wiring for Lighting & Power 6 31-Dec-12 07-Jan-13 14-Jan-13 20-Jan-13 11 A44280 Installation of Lighting Fittings 8 23-Jan-13 02-Feb-13 25-Feb-13 05-Mar-13 27 PlumbingPlumbing 74 23-Oct-12 22-Jan-13 20-Feb-13 05-Mar-13 35 A44470 H/L Drainage Pipes Installation 8 23-Oct-12 03-Nov-12 20-Feb-13 28-Feb-13 97 A44480 H/L Hot&Cold Water Pipe Installation 8 23-Oct-12 03-Nov-12 20-Feb-13 28-Feb-13 97 A44490 Drainage&Water Pipes Testing 4 04-Nov-12 07-Nov-12 02-Mar-13 05-Mar-13 97 A44510 Floor Drain Fixning 2 21-Jan-13 22-Jan-13 04-Mar-13 05-Mar-13 35 Fire FighFire Fighting 23 23-Oct-12 21-Nov-12 10-Nov-12 23-Apr-13 128 A44410 Fire Fighting Pipe 7 23-Oct-12 01-Nov-12 10-Nov-12 18-Nov-12 13 A44420 Hydro Static Test for Pipes 4 03-Nov-12 06-Nov-12 29-Jan-13 02-Feb-13 71 A44430 Sprinkler Fixing 7 07-Nov-12 14-Nov-12 03-Feb-13 10-Feb-13 71 A44450 Installation of Fire Extingusher&Blanket 2 17-Nov-12 18-Nov-12 22-Apr-13 23-Apr-13 131 A44310 Fire Alarm Devices 5 17-Nov-12 21-Nov-12 23-Mar-13 27-Mar-13 105 SwimminSwimming Pool 26 21-Jan-13 20-Feb-13 04-Feb-13 05-Mar-13 11 A44440 Installation of GRP Tank 10 21-Jan-13 02-Feb-13 04-Feb-13 14-Feb-13 11 A45060 Installation of Heat Exchanger 10 21-Jan-13 02-Feb-13 04-Feb-13 14-Feb-13 11 A44350 Installation of Swimming Pool Pipes&Fittings 15 21-Jan-13 07-Feb-13 17-Feb-13 05-Mar-13 22 A44460 Installation of Pumps 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11 A44500 Installation of Filter 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11 A44650 Installation of Electrical Heater 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11 A45180 Installation of Chemical Tank 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11 A45190 Installation of Control Panel 16 03-Feb-13 20-Feb-13 16-Feb-13 05-Mar-13 11 Pump RooPump Room 103 23-Oct-12 26-Feb-13 07-Nov-12 25-Apr-13 50 FinishingFinishing Works 103 23-Oct-12 26-Feb-13 07-Nov-12 25-Apr-13 50 Wet WorWet Works 70 23-Oct-12 17-Jan-13 07-Nov-12 18-Apr-13 77 A44570 Block Works 4 23-Oct-12 29-Oct-12 07-Nov-12 11-Nov-12 11 A44520 Plaster Works 5 18-Dec-12 23-Dec-12 31-Dec-12 06-Jan-13 11 A44540 1st Coat Paint 6 31-Dec-12 07-Jan-13 14-Jan-13 20-Jan-13 11 A44530 Installation of Doors& Windows Sub-frame 1 17-Jan-13 17-Jan-13 18-Apr-13 18-Apr-13 77 Fisrt StaFisrt Stage Finishes 9 11-Feb-13 20-Feb-13 09-Apr-13 23-Apr-13 53 A44560 Installation of Doors 2 11-Feb-13 12-Feb-13 20-Apr-13 21-Apr-13 58 A44580 Doors Ironmongery 2 11-Feb-13 12-Feb-13 22-Apr-13 23-Apr-13 60 A44630 Epoxy Paint Works 2 19-Feb-13 20-Feb-13 09-Apr-13 10-Apr-13 42 Second SSecond Stage Finishes 3 21-Feb-13 24-Feb-13 21-Apr-13 23-Apr-13 50 A44550 Final Coat Paint 3 21-Feb-13 24-Feb-13 21-Apr-13 23-Apr-13 50 Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 24-Apr-13 25-Apr-13 50 A44620 Installation of Sinages 2 25-Feb-13 26-Feb-13 24-Apr-13 25-Apr-13 50 MEP WorkMEP Works 92 30-Oct-12 18-Feb-13 17-Nov-12 23-Apr-13 55 HVACHVAC 92 30-Oct-12 18-Feb-13 17-Nov-12 05-Mar-13 13 A44680 Condensate Pipe Installation 7 30-Oct-12 06-Nov-12 25-Nov-12 03-Dec-12 21 A44660 Duct Installation & Insulation 7 03-Nov-12 10-Nov-12 17-Nov-12 24-Nov-12 11 A44670 Chilled Water Pipe Installation & Insulation 7 03-Nov-12 10-Nov-12 17-Nov-12 24-Nov-12 11 A44690 FCU Installation 5 11-Nov-12 17-Nov-12 04-Dec-12 09-Dec-12 18 A44700 Air-Outlet Installation 7 19-Nov-12 26-Nov-12 05-Feb-13 12-Feb-13 64 A44790 Installation of Primary Chilled Water Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13 A114240 Installation of Heat Exchanger Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13 A114250 Installation of Heat Exchanger 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13 A114260 Installation of Secondary Chilled Water Pumps 35 08-Jan-13 18-Feb-13 23-Jan-13 05-Mar-13 13 ElectricalElectrical 70 30-Oct-12 22-Jan-13 27-Dec-12 24-Feb-13 27 A44590 Install Conduits in Wall 3 30-Oct-12 01-Nov-12 27-Dec-12 30-Dec-12 48 A44600 Wiring for Lighting & Power 3 24-Dec-12 26-Dec-12 10-Jan-13 13-Jan-13 14 A44610 Installation of Lighting Fittings 5 17-Jan-13 22-Jan-13 19-Feb-13 24-Feb-13 27 PlumbingPlumbing 72 30-Oct-12 26-Jan-13 17-Feb-13 05-Mar-13 33 A44760 H/L Hot&Cold Water Pipe Installation 4 30-Oct-12 03-Nov-12 23-Feb-13 26-Feb-13 95 A44750 H/L Drainage Pipes Installation 7 30-Oct-12 06-Nov-12 19-Feb-13 26-Feb-13 92 A44770 Drainage&Water Pipes Testing 6 07-Nov-12 13-Nov-12 27-Feb-13 05-Mar-13 92 A44780 Floor Drain Fixning 6 08-Jan-13 14-Jan-13 27-Feb-13 05-Mar-13 42 A45200 Installation of Booster Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33 A45210 Installation of Primary Chilled Water Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33 A45310 Installation of SecondaryChilled Water Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33 A45320 Installation of Heat Exchanger 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33 A45330 Installation of Heat Exchanger Pump 15 08-Jan-13 26-Jan-13 17-Feb-13 05-Mar-13 33 Fire FighFire Fighting 25 03-Nov-12 03-Dec-12 19-Nov-12 23-Apr-13 119 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Water Pipes in Wall Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Doors& Windows Sub-frame 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Installation of GRP Tank Installation of Heat Exchanger Installation of Swimming Pool Pipes&Fittings Installation of Pumps Installation of Filter Installation of Electrical Heater Installation of Chemical Tank Installation of Control Panel Block Works Plaster Works 1st Coat Paint Installation of Doors& Windows Sub-frame Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Installation of Primary Chilled Water Pumps Installation of Heat Exchanger Pumps Installation of Heat Exchanger Installation of Secondary Chilled Water Pumps Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Booster Pump Installation of Primary Chilled Water Pump Installation of SecondaryChilled Water Pump Installation of Heat Exchanger Installation of Heat Exchanger Pump Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 49 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 50. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A44740 Fire Fighting Pipe 7 03-Nov-12 10-Nov-12 19-Nov-12 26-Nov-12 13 A44730 Hydro Static Test for Pipes 7 11-Nov-12 19-Nov-12 03-Feb-13 10-Feb-13 68 A44720 Sprinkler Fixing 5 20-Nov-12 25-Nov-12 11-Feb-13 16-Feb-13 68 A44710 Installation of Fire Extingusher&Blanket 3 26-Nov-12 28-Nov-12 21-Apr-13 23-Apr-13 122 A44640 Fire Alarm Devices 6 26-Nov-12 03-Dec-12 28-Mar-13 03-Apr-13 102 ElectricalElectrical - GSM - Telephone Rooms 103 30-Oct-12 03-Mar-13 12-Nov-12 25-Apr-13 46 FinishingFinishing Works 103 30-Oct-12 03-Mar-13 12-Nov-12 25-Apr-13 46 Wet WorWet Works 65 30-Oct-12 16-Jan-13 12-Nov-12 16-Apr-13 76 A44850 Block Works 6 30-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 11 A44800 Plaster Works 7 10-Dec-12 17-Dec-12 23-Dec-12 30-Dec-12 11 A44820 1st Coat Paint 8 22-Dec-12 30-Dec-12 05-Jan-13 13-Jan-13 11 A44810 Installation of Doors& Windows Sub-frame 2 15-Jan-13 16-Jan-13 15-Apr-13 16-Apr-13 76 Fisrt StaFisrt Stage Finishes 13 09-Feb-13 23-Feb-13 11-Apr-13 23-Apr-13 51 A44840 Installation of Doors 2 09-Feb-13 10-Feb-13 17-Apr-13 18-Apr-13 58 A44860 Doors Ironmongery 2 09-Feb-13 10-Feb-13 22-Apr-13 23-Apr-13 62 A44910 Epoxy Paint Works 2 21-Feb-13 23-Feb-13 11-Apr-13 13-Apr-13 42 Second SSecond Stage Finishes 5 24-Feb-13 28-Feb-13 18-Apr-13 23-Apr-13 46 A44830 Final Coat Paint 5 24-Feb-13 28-Feb-13 18-Apr-13 23-Apr-13 46 Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 24-Apr-13 25-Apr-13 46 A44900 Installation of Sinages 2 02-Mar-13 03-Mar-13 24-Apr-13 25-Apr-13 46 MEP WorkMEP Works 88 06-Nov-12 20-Feb-13 20-Dec-12 10-Apr-13 42 HVACHVAC 2 05-Jan-13 06-Jan-13 24-Feb-13 25-Feb-13 42 A44940 Air-Outlet Installation 2 05-Jan-13 06-Jan-13 24-Feb-13 25-Feb-13 42 ElectricalElectrical 88 06-Nov-12 20-Feb-13 20-Dec-12 05-Mar-13 11 A44870 Install Conduits in Wall 2 06-Nov-12 07-Nov-12 20-Dec-12 22-Dec-12 36 A44880 Wiring for Lighting & Power 2 18-Dec-12 19-Dec-12 02-Jan-13 03-Jan-13 12 A44930 Installation of SMDBs 7 31-Dec-12 08-Jan-13 03-Feb-13 10-Feb-13 27 A44890 Installation of Lighting Fittings 2 09-Jan-13 10-Jan-13 11-Feb-13 12-Feb-13 27 A114890 Installation of Telephone System 21 31-Dec-12 26-Jan-13 10-Feb-13 05-Mar-13 33 A114590 Installation of GSM System 43 31-Dec-12 20-Feb-13 14-Jan-13 05-Mar-13 11 Fire FighFire Fighting 2 12-Jan-13 13-Jan-13 09-Apr-13 10-Apr-13 74 A44920 Fire Alarm Devices 2 12-Jan-13 13-Jan-13 09-Apr-13 10-Apr-13 74 Gym RoomGym Room 257 06-Nov-12 08-Sep-13 20-Nov-12 02-Oct-13 21 FinishingFinishing Works 257 06-Nov-12 08-Sep-13 20-Nov-12 02-Oct-13 21 Wet WorWet Works 57 06-Nov-12 14-Jan-13 20-Nov-12 14-Apr-13 76 A45000 Block Works 3 06-Nov-12 08-Nov-12 20-Nov-12 22-Nov-12 11 A44950 Plaster Works 5 24-Nov-12 28-Nov-12 08-Dec-12 12-Dec-12 11 A44960 Installation of Doors& Windows Sub-frame 2 13-Jan-13 14-Jan-13 13-Apr-13 14-Apr-13 76 Fisrt StaFisrt Stage Finishes 35 29-Nov-12 10-Jan-13 19-Dec-12 14-Apr-13 79 A45230 Installation of Suspended Ceiling Grid 5 29-Nov-12 05-Dec-12 19-Dec-12 24-Dec-12 16 A44970 1st Coat Paint 8 12-Dec-12 20-Dec-12 25-Dec-12 03-Jan-13 11 A45240 Suspended Ceiling Tiles 5 22-Dec-12 26-Dec-12 29-Jan-13 03-Feb-13 31 A45280 Screed Works 3 27-Dec-12 30-Dec-12 01-Apr-13 03-Apr-13 79 A45270 Wall Tiles Work 4 31-Dec-12 05-Jan-13 04-Apr-13 08-Apr-13 79 A45260 Floor Tiles Work 5 06-Jan-13 10-Jan-13 09-Apr-13 14-Apr-13 79 Second SSecond Stage Finishes 23 12-Jan-13 07-Feb-13 15-Apr-13 25-Apr-13 66 A44980 Final Coat Paint 3 12-Jan-13 14-Jan-13 16-Apr-13 18-Apr-13 80 A45250 Installation of Mirrors 6 15-Jan-13 21-Jan-13 20-Apr-13 25-Apr-13 80 A44990 Installation of Doors 2 06-Feb-13 07-Feb-13 15-Apr-13 16-Apr-13 58 A45010 Doors Ironmongery 2 06-Feb-13 07-Feb-13 22-Apr-13 23-Apr-13 64 Final StaFinal Stage Finishes 180 09-Feb-13 08-Sep-13 24-Apr-13 02-Oct-13 21 A45050 Installation of Sinages 2 09-Feb-13 10-Feb-13 24-Apr-13 25-Apr-13 64 A45080 Installation of GYM Equipments 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 50 10-Nov-12 09-Jan-13 25-Nov-12 18-Apr-13 84 HVACHVAC 45 10-Nov-12 03-Jan-13 25-Nov-12 23-Feb-13 42 A45110 Condensate Pipe Installation 8 10-Nov-12 19-Nov-12 29-Nov-12 09-Dec-12 16 A45090 Duct Installation & Insulation 8 11-Nov-12 20-Nov-12 25-Nov-12 04-Dec-12 11 A45100 Chilled Water Pipe Installation & Insulation 8 11-Nov-12 20-Nov-12 25-Nov-12 04-Dec-12 11 A45120 FCU Installation 3 21-Nov-12 24-Nov-12 10-Dec-12 12-Dec-12 15 A45130 Air-Outlet Installation 6 27-Dec-12 03-Jan-13 17-Feb-13 23-Feb-13 42 ElectricalElectrical 45 10-Nov-12 03-Jan-13 03-Dec-12 10-Feb-13 31 A45020 Install Conduits in Wall 4 10-Nov-12 13-Nov-12 03-Dec-12 06-Dec-12 18 A45030 Wiring for Lighting & Power 4 29-Nov-12 04-Dec-12 20-Dec-12 24-Dec-12 17 A45040 Installation of Lighting Fittings 6 27-Dec-12 03-Jan-13 04-Feb-13 10-Feb-13 31 Fire FighFire Fighting 49 11-Nov-12 09-Jan-13 27-Nov-12 18-Apr-13 84 A45170 Fire Fighting Pipe 7 11-Nov-12 19-Nov-12 27-Nov-12 05-Dec-12 13 A45160 Hydro Static Test for Pipes 5 20-Nov-12 25-Nov-12 13-Dec-12 18-Dec-12 19 A45150 Sprinkler Fixing 7 27-Dec-12 05-Jan-13 17-Feb-13 24-Feb-13 42 A45140 Installation of Fire Extingusher&Blanket 2 06-Jan-13 07-Jan-13 17-Apr-13 18-Apr-13 86 A45070 Fire Alarm Devices 4 06-Jan-13 09-Jan-13 04-Apr-13 08-Apr-13 75 TolietsToliets 83 10-Nov-12 18-Feb-13 24-Nov-12 25-Apr-13 57 FinishingFinishing Works 83 10-Nov-12 18-Feb-13 24-Nov-12 25-Apr-13 57 Wet WorWet Works 52 10-Nov-12 12-Jan-13 24-Nov-12 09-Apr-13 74 A45440 Block Works 4 10-Nov-12 13-Nov-12 24-Nov-12 27-Nov-12 11 A45290 Plaster Works 8 29-Nov-12 09-Dec-12 13-Dec-12 22-Dec-12 11 A45770 Wall Tiles Work (Wet Area) 9 10-Dec-12 19-Dec-12 13-Jan-13 22-Jan-13 28 A45300 Installation of Doors& Windows Sub-frame 3 09-Jan-13 12-Jan-13 07-Apr-13 09-Apr-13 74 Fisrt StaFisrt Stage Finishes 21 20-Dec-12 14-Jan-13 23-Jan-13 09-Apr-13 72 A45760 Screed Works 3 20-Dec-12 23-Dec-12 23-Jan-13 27-Jan-13 28 A45360 Water Proofing for Wet Area 4 24-Dec-12 27-Dec-12 28-Jan-13 31-Jan-13 28 A45800 Installation of Suspended Ceiling Grid (Wet Area) 5 29-Dec-12 03-Jan-13 02-Feb-13 06-Feb-13 28 A45790 Suspended Ceiling Tiles (Wet Area) 5 05-Jan-13 09-Jan-13 07-Feb-13 12-Feb-13 28 A45780 Floor Tiles Work (Wet Area) 4 10-Jan-13 14-Jan-13 06-Apr-13 09-Apr-13 72 Second SSecond Stage Finishes 10 03-Feb-13 13-Feb-13 10-Apr-13 21-Apr-13 57 A45380 Installation of Doors 3 03-Feb-13 05-Feb-13 10-Apr-13 13-Apr-13 57 A45450 Doors Ironmongery 3 03-Feb-13 05-Feb-13 18-Apr-13 21-Apr-13 64 A45430 Installation of Vanity Counter 3 06-Feb-13 09-Feb-13 18-Apr-13 21-Apr-13 61 A45740 Installation of Toliets Accessories 5 06-Feb-13 11-Feb-13 16-Apr-13 21-Apr-13 59 A45390 Installation of Mirrors 7 06-Feb-13 13-Feb-13 14-Apr-13 21-Apr-13 57 Final StaFinal Stage Finishes 4 14-Feb-13 18-Feb-13 22-Apr-13 25-Apr-13 57 A45340 Final Coat Paint 2 14-Feb-13 16-Feb-13 22-Apr-13 23-Apr-13 57 A45750 Installation of Sinages 2 17-Feb-13 18-Feb-13 24-Apr-13 25-Apr-13 57 MEP WorkMEP Works 71 14-Nov-12 09-Feb-13 05-Dec-12 23-Apr-13 63 HVACHVAC 53 14-Nov-12 17-Jan-13 05-Dec-12 05-Mar-13 39 A45490 Condensate Pipe Installation 4 14-Nov-12 19-Nov-12 09-Dec-12 12-Dec-12 19 A45470 Duct Installation & Insulation 4 21-Nov-12 25-Nov-12 05-Dec-12 09-Dec-12 11 A45480 Chilled Water Pipe Installation & Insulation 4 21-Nov-12 25-Nov-12 05-Dec-12 09-Dec-12 11 A45500 FCU Installation 2 26-Nov-12 27-Nov-12 13-Dec-12 15-Dec-12 14 A45510 Air-Outlet Installation 7 10-Jan-13 17-Jan-13 26-Feb-13 05-Mar-13 39 ElectricalElectrical 52 14-Nov-12 16-Jan-13 09-Dec-12 18-Feb-13 27 A45520 Install Conduits in Wall 4 14-Nov-12 19-Nov-12 09-Dec-12 12-Dec-12 19 A45540 Wiring for Lighting & Power 4 10-Dec-12 13-Dec-12 28-Jan-13 31-Jan-13 40 A45600 Installation of Lighting Fittings 5 12-Jan-13 16-Jan-13 13-Feb-13 18-Feb-13 27 PlumbingPlumbing 71 14-Nov-12 09-Feb-13 10-Dec-12 21-Apr-13 61 A45620 Drainge Pipes in Wall 3 14-Nov-12 18-Nov-12 10-Dec-12 12-Dec-12 20 A45690 Water Pipes in Wall 3 14-Nov-12 18-Nov-12 10-Dec-12 12-Dec-12 20 A45630 H/L Drainage Pipes Installation 4 14-Nov-12 19-Nov-12 23-Jan-13 28-Jan-13 57 A45640 H/L Hot&Cold Water Pipe Installation 4 14-Nov-12 19-Nov-12 23-Jan-13 28-Jan-13 57 A45660 ElectricalWater Heater Installation 2 20-Nov-12 21-Nov-12 30-Jan-13 31-Jan-13 58 A45650 Drainage&Water Pipes Testing 3 20-Nov-12 22-Nov-12 29-Jan-13 31-Jan-13 57 A45670 Floor Drain Fixning 2 23-Dec-12 24-Dec-12 04-Mar-13 05-Mar-13 59 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works 1st Coat Paint Installation of Doors& Windows Sub-frame Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Installation of GSM System Fire Alarm Devices Block Works Plaster Works Installation of Doors& Windows Sub-frame Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Final Coat Paint Installation of Mirrors Installation of Doors Doors Ironmongery Installation of Sinages Installation of GYM Eq Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Wall Tiles Work (Wet Area) Installation of Doors& Windows Sub-frame Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Doors Doors Ironmongery Installation of Vanity Counter Installation of Toliets Accessories Installation of Mirrors Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Electrical Water Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 50 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 51. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A45680 Installation of Sanitaryware 3 06-Feb-13 09-Feb-13 18-Apr-13 21-Apr-13 61 Fire FighFire Fighting 49 20-Nov-12 17-Jan-13 06-Dec-12 23-Apr-13 81 A45730 Fire Fighting Pipe 3 20-Nov-12 22-Nov-12 06-Dec-12 09-Dec-12 13 A45720 Hydro Static Test for Pipes 3 24-Nov-12 26-Nov-12 29-Jan-13 31-Jan-13 54 A45710 Sprinkler Fixing 3 12-Jan-13 14-Jan-13 03-Mar-13 05-Mar-13 42 A45700 Installation of Fire Extingusher&Blanket 2 15-Jan-13 16-Jan-13 22-Apr-13 23-Apr-13 82 A45810 Fire Alarm Devices 4 14-Jan-13 17-Jan-13 13-Apr-13 16-Apr-13 75 Lift LobbyLift Lobby 65 14-Nov-12 02-Feb-13 28-Nov-12 25-Apr-13 71 FinishingFinishing Works 65 14-Nov-12 02-Feb-13 28-Nov-12 25-Apr-13 71 Wet WorWet Works 22 14-Nov-12 11-Dec-12 28-Nov-12 24-Dec-12 11 A45880 Block Works 2 14-Nov-12 17-Nov-12 28-Nov-12 29-Nov-12 11 A45820 Plaster Works 3 20-Nov-12 22-Nov-12 04-Dec-12 06-Dec-12 11 A45840 Installation of Suspended Ceiling Grid 2 06-Dec-12 08-Dec-12 19-Dec-12 20-Dec-12 11 A45830 1st Coat Paint 3 09-Dec-12 11-Dec-12 22-Dec-12 24-Dec-12 11 Fisrt StaFisrt Stage Finishes 9 12-Dec-12 22-Dec-12 27-Jan-13 02-Apr-13 85 A45850 Suspended Ceiling Tiles 2 12-Dec-12 13-Dec-12 27-Jan-13 28-Jan-13 37 A46140 MDF for Lift Lobby Wall 7 12-Dec-12 19-Dec-12 24-Mar-13 31-Mar-13 85 A46120 Screed Works 2 20-Dec-12 22-Dec-12 01-Apr-13 02-Apr-13 85 Second SSecond Stage Finishes 4 23-Dec-12 26-Dec-12 03-Apr-13 07-Apr-13 85 A46130 Wall Tiles Work 2 23-Dec-12 24-Dec-12 03-Apr-13 04-Apr-13 85 A46160 Floor Tiles Work 2 25-Dec-12 26-Dec-12 06-Apr-13 07-Apr-13 85 Final StaFinal Stage Finishes 8 23-Jan-13 02-Feb-13 08-Apr-13 25-Apr-13 71 A46170 Final Coat Paint 2 23-Jan-13 26-Jan-13 22-Apr-13 23-Apr-13 75 A45860 Installation of Doors 2 31-Jan-13 02-Feb-13 08-Apr-13 09-Apr-13 57 A45890 Doors Ironmongery 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71 A46110 Installation of Sinages 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71 MEP WorkMEP Works 55 18-Nov-12 22-Jan-13 01-Dec-12 21-Apr-13 75 HVACHVAC 25 18-Nov-12 17-Dec-12 10-Dec-12 16-Feb-13 50 A45920 Condensate Pipe Installation 5 18-Nov-12 22-Nov-12 10-Dec-12 15-Dec-12 18 A45900 Duct Installation & Insulation 5 26-Nov-12 01-Dec-12 10-Dec-12 15-Dec-12 11 A45910 Chilled Water Pipe Installation & Insulation 5 26-Nov-12 01-Dec-12 10-Dec-12 15-Dec-12 11 A45930 FCU Installation 3 03-Dec-12 05-Dec-12 16-Dec-12 18-Dec-12 11 A45940 Air-Outlet Installation 3 15-Dec-12 17-Dec-12 13-Feb-13 16-Feb-13 50 ElectricalElectrical 27 18-Nov-12 19-Dec-12 01-Dec-12 05-Mar-13 63 A45950 Install Conduits in Wall 2 18-Nov-12 19-Nov-12 01-Dec-12 03-Dec-12 11 A45960 Install Cable Trays & Trunking 2 18-Nov-12 19-Nov-12 03-Dec-12 04-Dec-12 12 A46000 Cable Laying for Low Current System 2 20-Nov-12 21-Nov-12 19-Dec-12 20-Dec-12 24 A46010 Cable Laying for Power 4 20-Nov-12 24-Nov-12 17-Dec-12 20-Dec-12 22 A45970 Wiring for Lighting & Power 3 24-Nov-12 26-Nov-12 16-Dec-12 18-Dec-12 18 A45980 Wiring for Low Current System 4 24-Nov-12 27-Nov-12 15-Dec-12 18-Dec-12 17 A46040 Installation of Sockets 3 15-Dec-12 17-Dec-12 03-Mar-13 05-Mar-13 65 A46030 Installation of Lighting Fittings 5 15-Dec-12 19-Dec-12 29-Jan-13 03-Feb-13 37 PlumbingPlumbing 5 18-Nov-12 22-Nov-12 13-Dec-12 18-Dec-12 21 A46050 H/L Hot&Cold Water Pipe Installation 5 18-Nov-12 22-Nov-12 13-Dec-12 18-Dec-12 21 Fire FighFire Fighting 50 24-Nov-12 22-Jan-13 10-Dec-12 21-Apr-13 75 A46100 Fire Fighting Pipe 4 24-Nov-12 27-Nov-12 10-Dec-12 13-Dec-12 13 A46090 Hydro Static Test for Pipes 4 28-Nov-12 03-Dec-12 15-Dec-12 18-Dec-12 13 A46080 Sprinkler Fixing 5 06-Jan-13 10-Jan-13 25-Feb-13 02-Mar-13 42 A46150 Fire Alarm Devices 4 19-Jan-13 22-Jan-13 17-Apr-13 21-Apr-13 75 Chillers RoChillers Room 116 13-Sep-12 02-Feb-13 18-Nov-12 25-Apr-13 71 FinishingFinishing Works 116 13-Sep-12 02-Feb-13 18-Nov-12 25-Apr-13 71 Wet WorWet Works 7 13-Sep-12 20-Sep-12 18-Nov-12 16-Mar-13 145 A46230 Block Works 2 13-Sep-12 15-Sep-12 14-Mar-13 16-Mar-13 150 A46290 Water Proofing Works 7 13-Sep-12 20-Sep-12 18-Nov-12 25-Nov-12 53 Fisrt StaFisrt Stage Finishes 19 08-Jan-13 30-Jan-13 17-Mar-13 23-Apr-13 71 A46190 Installation of Doors& Windows Sub-frame 1 08-Jan-13 08-Jan-13 03-Apr-13 03-Apr-13 72 A46180 Plaster Works 2 08-Jan-13 09-Jan-13 17-Mar-13 18-Mar-13 57 A46200 1st Coat Paint 3 10-Jan-13 13-Jan-13 19-Mar-13 21-Mar-13 57 A46450 Floor Tiles Works 11 14-Jan-13 27-Jan-13 23-Mar-13 03-Apr-13 57 A46220 Installation of Doors 3 28-Jan-13 30-Jan-13 04-Apr-13 07-Apr-13 57 A46240 Doors Ironmongery 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71 Second SSecond Stage Finishes 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71 A46210 Final Coat Paint 3 28-Jan-13 30-Jan-13 21-Apr-13 23-Apr-13 71 Final StaFinal Stage Finishes 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71 A46280 Installation of Sinages 2 31-Jan-13 02-Feb-13 24-Apr-13 25-Apr-13 71 MEP WorkMEP Works 83 27-Sep-12 07-Jan-13 26-Nov-12 05-Mar-13 48 HVACHVAC 83 27-Sep-12 07-Jan-13 26-Nov-12 05-Mar-13 48 A46320 Chilled Water Pipe Installation & Insulation 51 27-Sep-12 28-Nov-12 26-Nov-12 27-Jan-13 48 A46440 Installation of Chillers 51 27-Sep-12 28-Nov-12 26-Nov-12 27-Jan-13 48 A46509 Flushing for Chiled Water Pipes 32 29-Nov-12 07-Jan-13 28-Jan-13 05-Mar-13 48 StaircaseStaircase 45 04-Feb-13 27-Mar-13 05-Mar-13 25-Apr-13 25 Stair 2Stair 2 45 04-Feb-13 27-Mar-13 05-Mar-13 25-Apr-13 25 A109070 Floor Screed 3 04-Feb-13 06-Feb-13 05-Mar-13 07-Mar-13 25 A109080 Install Handrails 4 07-Feb-13 11-Feb-13 09-Mar-13 12-Mar-13 25 A109090 Ceiling 1st Coat Paint 7 12-Feb-13 19-Feb-13 13-Mar-13 20-Mar-13 25 A109100 Wall 1st Coat Paint 7 20-Feb-13 27-Feb-13 21-Mar-13 28-Mar-13 25 A109110 Install Granite/Terrazo 12 28-Feb-13 13-Mar-13 30-Mar-13 11-Apr-13 25 A109120 Final Coat Paint 12 14-Mar-13 27-Mar-13 13-Apr-13 25-Apr-13 25 Upper Roof LUpper Roof Level 294 22-Sep-12 08-Sep-13 30-Jan-13 02-Oct-13 21 Public AreaPublic Area 294 22-Sep-12 08-Sep-13 30-Jan-13 02-Oct-13 21 SwimmingSwimming Pool Deck 294 22-Sep-12 08-Sep-13 06-Mar-13 02-Oct-13 21 FinishingFinishing Works 294 22-Sep-12 08-Sep-13 06-Mar-13 02-Oct-13 21 A53830 Block Works 3 22-Sep-12 24-Sep-12 06-Mar-13 09-Mar-13 136 A53840 Plaster Works 4 25-Sep-12 29-Sep-12 10-Mar-13 13-Mar-13 136 A53850 1st Coat Paint 4 30-Sep-12 03-Oct-12 14-Mar-13 18-Mar-13 136 A53910 Instaaltion of Wooden Pergola 10 04-Oct-12 15-Oct-12 19-Mar-13 30-Mar-13 136 A53860 Floor Tiles Work 10 20-Oct-12 01-Nov-12 31-Mar-13 10-Apr-13 133 A53870 Installation of Doors 3 03-Nov-12 05-Nov-12 11-Apr-13 14-Apr-13 133 A53880 Doors Ironmongery 3 06-Nov-12 08-Nov-12 15-Apr-13 17-Apr-13 133 A53890 Final Coat Paint 3 10-Nov-12 12-Nov-12 18-Apr-13 21-Apr-13 133 A53900 Installation of Sinages 2 13-Nov-12 14-Nov-12 24-Apr-13 25-Apr-13 135 A53820 Installation of Metal Kitchen Cabinet , Bar , B.B.Q 4 13-Nov-12 18-Nov-12 22-Apr-13 25-Apr-13 133 A53920 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 SwimmingSwimming Pool 59 26-Sep-12 08-Dec-12 17-Feb-13 25-Apr-13 117 FinishingFinishing Works 59 26-Sep-12 08-Dec-12 17-Feb-13 25-Apr-13 117 A50630 Pouring of Screed 4 26-Sep-12 30-Sep-12 17-Feb-13 20-Feb-13 117 A50640 Laying of Waterproofing 4 01-Oct-12 04-Oct-12 21-Feb-13 25-Feb-13 117 A50650 Pouring of Guniting 5 06-Oct-12 10-Oct-12 26-Feb-13 03-Mar-13 117 A50660 Laying of Waterproofing 4 11-Oct-12 15-Oct-12 04-Mar-13 07-Mar-13 117 A50670 Waterproofing Plastering 15 16-Oct-12 04-Nov-12 09-Mar-13 25-Mar-13 117 A50680 Fix the Tiles 20 05-Nov-12 28-Nov-12 26-Mar-13 17-Apr-13 117 A50860 Installation of Stairs - Gratings -Nozzles 7 29-Nov-12 08-Dec-12 18-Apr-13 25-Apr-13 117 A50890 Installatiof of Lights 7 29-Nov-12 08-Dec-12 18-Apr-13 25-Apr-13 117 LPG Tank ALPG Tank Area 56 22-Sep-12 28-Nov-12 20-Feb-13 25-Apr-13 124 FinishingFinishing Works 56 22-Sep-12 28-Nov-12 20-Feb-13 25-Apr-13 124 A90990 Water Proofing for Roof Area 10 22-Sep-12 02-Oct-12 20-Feb-13 03-Mar-13 124 A91000 Floor Tiles Work 10 03-Oct-12 14-Oct-12 04-Mar-13 14-Mar-13 124 A90970 Installation of Steel Support 9 04-Nov-12 13-Nov-12 02-Apr-13 11-Apr-13 124 A90980 Installation of Louver 12 14-Nov-12 28-Nov-12 13-Apr-13 25-Apr-13 124 GRP WaterGRP Water Tank 30 22-Sep-12 28-Oct-12 30-Jan-13 05-Mar-13 106 FinishingFinishing Works 18 22-Sep-12 11-Oct-12 30-Jan-13 19-Feb-13 106 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works Wall Tiles Work Floor Tiles Work Final Coat Paint Installation of Doors Doors Ironmongery Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Water Proofing Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Floor Tiles Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Installation of Chillers Flushing for Chiled Water Pipes Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works 1st Coat Paint Instaaltion of Wooden Pergola Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Metal Kitchen Cabinet , Bar , B.B.Q Installation of Furnitur Pouring of Screed Laying of Waterproofing Pouring of Guniting Laying of Waterproofing Waterproofing Plastering Fix the Tiles Installation of Stairs - Gratings -Nozzles Installatiof of Lights Water Proofing for Roof Area Floor Tiles Work Installation of Steel Support Installation of Louver Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 51 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 52. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A91020 Water Proofing for Roof Area 8 22-Sep-12 30-Sep-12 30-Jan-13 07-Feb-13 106 A91030 Floor Tiles Work 10 01-Oct-12 11-Oct-12 09-Feb-13 19-Feb-13 106 MEP WorkMEP Works 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106 PlumbingPlumbing 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106 A91010 Installation of GRP Tank 12 13-Oct-12 28-Oct-12 20-Feb-13 05-Mar-13 106 Hotel (BlockHotel (Block B) 369 24-Jun-12 08-Sep-13 04-Oct-12 02-Oct-13 21 2nd Basemen2nd Basement Floor 193 24-Jun-12 12-Feb-13 06-Dec-12 28-Apr-13 64 Public AreaPublic Area 193 24-Jun-12 12-Feb-13 06-Dec-12 28-Apr-13 64 Parking ArParking Area 193 24-Jun-12 12-Feb-13 10-Jan-13 28-Apr-13 64 FinishingFinishing Works 184 04-Jul-12 12-Feb-13 05-Feb-13 28-Apr-13 64 Wet WorWet Works 127 04-Jul-12 05-Dec-12 05-Feb-13 24-Feb-13 67 A54800 Plaster Works 5 04-Jul-12 09-Jul-12 05-Feb-13 10-Feb-13 177 A54810 1st Coat Paint 12 21-Nov-12 05-Dec-12 11-Feb-13 24-Feb-13 67 Traffic DTraffic Deck Coating 52 06-Dec-12 06-Feb-13 25-Feb-13 28-Apr-13 69 A115780 Installation of Kerbs 8 06-Dec-12 15-Dec-12 25-Feb-13 05-Mar-13 67 A115790 Installation of Interlocking Tiles 8 16-Dec-12 24-Dec-12 06-Mar-13 14-Mar-13 67 A54740 Surface Preparation (including Grinding & Repairing) 8 29-Dec-12 07-Jan-13 16-Mar-13 24-Mar-13 64 A54750 Application of 1st Coat 7 05-Jan-13 12-Jan-13 21-Mar-13 28-Mar-13 64 A54790 Application of Final Coat 7 13-Jan-13 20-Jan-13 30-Mar-13 06-Apr-13 64 A54770 Road Marking & Arrows 7 21-Jan-13 29-Jan-13 07-Apr-13 14-Apr-13 64 A115800 Installation of Speed Hump 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69 Final StaFinal Stage Finishes 12 30-Jan-13 12-Feb-13 15-Apr-13 28-Apr-13 64 A54820 Final Coat Paint 5 30-Jan-13 04-Feb-13 15-Apr-13 20-Apr-13 64 A54840 Installation of Sinages 7 05-Feb-13 12-Feb-13 21-Apr-13 28-Apr-13 64 MEP WorkMEP Works 124 24-Jun-12 20-Nov-12 10-Jan-13 10-Feb-13 67 HVACHVAC 10 24-Jun-12 04-Jul-12 30-Jan-13 10-Feb-13 181 A54860 Chilled Water Pipe Installation & Insulation 7 24-Jun-12 01-Jul-12 30-Jan-13 06-Feb-13 181 A54870 Condensate Pipe Installation 7 24-Jun-12 01-Jul-12 30-Jan-13 06-Feb-13 181 A54970 FCU Installation 3 02-Jul-12 04-Jul-12 07-Feb-13 10-Feb-13 181 A55210 Installation of Induction Fan 3 02-Jul-12 04-Jul-12 07-Feb-13 10-Feb-13 181 ElectricalElectrical 115 04-Jul-12 20-Nov-12 10-Jan-13 10-Feb-13 67 A115810 Instalaltion of Cable Trays 10 04-Jul-12 15-Jul-12 10-Jan-13 21-Jan-13 156 A115820 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 21-Jan-13 07-Feb-13 67 A115830 Cable Pulling 10 06-Nov-12 18-Nov-12 28-Jan-13 07-Feb-13 67 A54830 Installation of Lighting Fittings 2 19-Nov-12 20-Nov-12 09-Feb-13 10-Feb-13 67 PlumbingPlumbing 11 04-Jul-12 16-Jul-12 29-Jan-13 10-Feb-13 171 A54910 H/L Hot&Cold Water Pipe Installation 7 04-Jul-12 11-Jul-12 29-Jan-13 05-Feb-13 171 A54930 Floor Drain Fixning 7 04-Jul-12 11-Jul-12 03-Feb-13 10-Feb-13 175 A54950 H/L Drainage Pipes Installation 7 04-Jul-12 11-Jul-12 29-Jan-13 05-Feb-13 171 A54980 Installation of Sump Pumps 9 04-Jul-12 14-Jul-12 31-Jan-13 10-Feb-13 173 A54920 Water Pipes Testing 4 12-Jul-12 16-Jul-12 06-Feb-13 10-Feb-13 171 A54960 Drainage&Water Pipes Testing 4 12-Jul-12 16-Jul-12 06-Feb-13 10-Feb-13 171 Fire FighFire Fighting 26 04-Jul-12 02-Aug-12 10-Jan-13 10-Feb-13 156 A54900 Fire Fighting Pipe 8 04-Jul-12 12-Jul-12 10-Jan-13 19-Jan-13 156 A54890 Hydro Static Test for Pipes 5 14-Jul-12 18-Jul-12 20-Jan-13 26-Jan-13 156 A54880 Sprinkler Fixing 7 19-Jul-12 26-Jul-12 27-Jan-13 03-Feb-13 156 A54850 Fire Alarm Devices 6 28-Jul-12 02-Aug-12 04-Feb-13 10-Feb-13 156 RampRamp 114 20-Sep-12 06-Feb-13 03-Mar-13 28-Apr-13 69 A115840 Install Handrail 7 20-Sep-12 27-Sep-12 03-Mar-13 10-Mar-13 134 A115850 1st Coat Paint 10 24-Nov-12 05-Dec-12 11-Mar-13 21-Mar-13 89 A115860 Surface Preparation (including Grinding & Repairing) 8 29-Dec-12 07-Jan-13 23-Mar-13 31-Mar-13 70 A115870 Application of 1st Coat 5 08-Jan-13 13-Jan-13 01-Apr-13 06-Apr-13 70 A115880 Application of Final Coat 5 15-Jan-13 20-Jan-13 07-Apr-13 11-Apr-13 69 A115890 Road Marking & Arrows 7 21-Jan-13 29-Jan-13 13-Apr-13 20-Apr-13 69 A115900 Final Coat Paint 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69 Boiler RooBoiler Room 95 25-Jun-12 15-Oct-12 22-Dec-12 28-Apr-13 161 FinishingFinishing Works 95 25-Jun-12 15-Oct-12 22-Dec-12 28-Apr-13 161 Wet WorWet Works 34 25-Jun-12 02-Aug-12 22-Dec-12 12-Mar-13 182 A54270 Block Works 8 25-Jun-12 03-Jul-12 22-Dec-12 30-Dec-12 148 A54230 Installation of Doors& Windows Sub-frame 1 10-Jul-12 10-Jul-12 12-Mar-13 12-Mar-13 202 A54220 Plaster Works 7 10-Jul-12 17-Jul-12 07-Jan-13 14-Jan-13 148 A54240 1st Coat Paint 9 24-Jul-12 02-Aug-12 21-Jan-13 31-Jan-13 148 Fisrt StaFisrt Stage Finishes 8 08-Sep-12 16-Sep-12 10-Mar-13 25-Apr-13 184 A54330 Epoxy Paint Works 3 08-Sep-12 10-Sep-12 10-Mar-13 12-Mar-13 151 A54260 Installation of Doors 2 11-Sep-12 12-Sep-12 13-Mar-13 14-Mar-13 151 A54280 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Second SSecond Stage Finishes 6 11-Sep-12 17-Sep-12 20-Apr-13 25-Apr-13 183 A54250 Final Coat Paint 6 11-Sep-12 17-Sep-12 20-Apr-13 25-Apr-13 183 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A54320 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 54 04-Jul-12 06-Sep-12 31-Dec-12 24-Apr-13 191 HVACHVAC 14 04-Jul-12 19-Jul-12 18-Feb-13 05-Mar-13 188 A54350 Duct Installation & Insulation 7 04-Jul-12 11-Jul-12 18-Feb-13 25-Feb-13 188 A54390 Air-Outlet Installation 7 12-Jul-12 19-Jul-12 26-Feb-13 05-Mar-13 188 ElectricalElectrical 32 04-Jul-12 09-Aug-12 31-Dec-12 05-Mar-13 170 A54290 Install Conduits in Wall 5 04-Jul-12 09-Jul-12 31-Dec-12 06-Jan-13 148 A54300 Wiring for Lighting & Power 5 18-Jul-12 23-Jul-12 15-Jan-13 20-Jan-13 148 A54310 Installation of Lighting Fittings 6 04-Aug-12 09-Aug-12 27-Feb-13 05-Mar-13 170 PlumbingPlumbing 28 04-Aug-12 06-Sep-12 02-Feb-13 05-Mar-13 148 A54180 Installation of Hot Water Boiler 7 04-Aug-12 11-Aug-12 02-Feb-13 09-Feb-13 148 A54440 Floor Drain Fixning 7 04-Aug-12 11-Aug-12 26-Feb-13 05-Mar-13 169 A54190 Installation of Hot Water Tank 7 12-Aug-12 21-Aug-12 10-Feb-13 17-Feb-13 148 A54200 Installation of Hot Water Pump 7 22-Aug-12 29-Aug-12 18-Feb-13 25-Feb-13 148 A54210 Installation of Pipes 7 30-Aug-12 06-Sep-12 26-Feb-13 05-Mar-13 148 Fire FighFire Fighting 23 04-Jul-12 30-Jul-12 14-Feb-13 24-Apr-13 222 A54430 Fire Fighting Pipe 6 04-Jul-12 10-Jul-12 14-Feb-13 20-Feb-13 185 A54420 Hydro Static Test for Pipes 3 11-Jul-12 14-Jul-12 21-Feb-13 24-Feb-13 185 A54410 Sprinkler Fixing 4 15-Jul-12 18-Jul-12 25-Feb-13 28-Feb-13 185 A54340 Fire Alarm Devices 7 19-Jul-12 26-Jul-12 02-Mar-13 09-Mar-13 185 A54400 Installation of Fire Extingusher&Blanket 2 29-Jul-12 30-Jul-12 23-Apr-13 24-Apr-13 222 Water TankWater Tank 1 & 2 (Block A) 29 28-Jul-12 01-Sep-12 31-Jan-13 05-Mar-13 153 FinishingFinishing Works 21 28-Jul-12 22-Aug-12 31-Jan-13 24-Feb-13 153 A53960 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 31-Jan-13 07-Feb-13 153 A53950 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 09-Feb-13 16-Feb-13 153 A53970 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 17-Feb-13 24-Feb-13 153 MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153 ElectricalElectrical 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 A54160 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 PlumbingPlumbing 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153 A54090 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 25-Feb-13 02-Mar-13 153 A54070 Installation of Sump Pump 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 A54100 Install of Water Meter 3 29-Aug-12 01-Sep-12 03-Mar-13 05-Mar-13 153 Water TankWater Tank 1 & 2 (Block B) 29 28-Jul-12 01-Sep-12 31-Jan-13 05-Mar-13 153 FinishingFinishing Works 21 28-Jul-12 22-Aug-12 31-Jan-13 24-Feb-13 153 A54030 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 31-Jan-13 07-Feb-13 153 A54020 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 09-Feb-13 16-Feb-13 153 A54010 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 17-Feb-13 24-Feb-13 153 MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153 ElectricalElectrical 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 A54170 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 PlumbingPlumbing 8 23-Aug-12 01-Sep-12 25-Feb-13 05-Mar-13 153 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Water Proofing for Roof Area Floor Tiles Work Installation of GRP Tank Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Installation of Induction Fan Instalaltion of Cable Trays Instalaltion of Bus Bars Cable Pulling Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Floor Drain Fixning H/L Drainage Pipes Installation Installation of Sump Pumps Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of Hot Water Boiler Floor Drain Fixning Installation of Hot Water Tank Installation of Hot Water Pump Installation of Pipes Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket GRP Lining on the Ceiling GRP Lining on the Wall Reinforced Plastic on the Floor Installation of Lighting Fittings Installation of Water Supply Pipes&Fittings Installation of Sump Pump Install of Water Meter GRP Lining on the Ceiling GRP Lining on the Wall Reinforced Plastic on the Floor Installation of Lighting Fittings Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 52 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 53. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A54120 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 25-Feb-13 02-Mar-13 153 A54110 Installation of Sump Pump 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 A54130 Install of Water Meter 3 29-Aug-12 01-Sep-12 03-Mar-13 05-Mar-13 153 GSM RoomGSM Rooms 95 25-Jun-12 15-Oct-12 06-Dec-12 28-Apr-13 161 FinishingFinishing Works 95 25-Jun-12 15-Oct-12 06-Dec-12 28-Apr-13 161 Wet WorWet Works 30 25-Jun-12 29-Jul-12 06-Dec-12 12-Mar-13 186 A54500 Block Works 5 25-Jun-12 30-Jun-12 06-Dec-12 11-Dec-12 135 A54460 Installation of Doors& Windows Sub-frame 2 07-Jul-12 08-Jul-12 11-Mar-13 12-Mar-13 204 A54450 Plaster Works 8 07-Jul-12 15-Jul-12 18-Dec-12 26-Dec-12 135 A54470 1st Coat Paint 7 22-Jul-12 29-Jul-12 03-Jan-13 10-Jan-13 135 Fisrt StaFisrt Stage Finishes 68 09-Jul-12 27-Sep-12 13-Mar-13 25-Apr-13 174 A54490 Installation of Doors 2 09-Jul-12 10-Jul-12 13-Mar-13 14-Mar-13 204 A54510 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A54560 Epoxy Paint Works 2 26-Sep-12 27-Sep-12 13-Mar-13 14-Mar-13 138 Second SSecond Stage Finishes 3 29-Sep-12 01-Oct-12 23-Apr-13 25-Apr-13 171 A54480 Final Coat Paint 3 29-Sep-12 01-Oct-12 23-Apr-13 25-Apr-13 171 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A54550 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 73 01-Jul-12 25-Sep-12 12-Dec-12 12-Mar-13 138 HVACHVAC 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175 A54610 Air-Outlet Installation 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175 ElectricalElectrical 73 01-Jul-12 25-Sep-12 12-Dec-12 05-Mar-13 132 A54520 Install Conduits in Wall 5 01-Jul-12 05-Jul-12 12-Dec-12 17-Dec-12 135 A54530 Wiring for Lighting & Power 5 16-Jul-12 21-Jul-12 27-Dec-12 02-Jan-13 135 A54540 Installation of Lighting Fittings 5 30-Jul-12 04-Aug-12 28-Feb-13 05-Mar-13 175 A1155 Installation of GSM System 45 02-Aug-12 25-Sep-12 12-Jan-13 05-Mar-13 132 Fire FighFire Fighting 5 30-Jul-12 04-Aug-12 07-Mar-13 12-Mar-13 181 A54570 Fire Alarm Devices 5 30-Jul-12 04-Aug-12 07-Mar-13 12-Mar-13 181 MechanicaMechanical Room 95 25-Jun-12 15-Oct-12 08-Jan-13 28-Apr-13 161 FinishingFinishing Works 95 25-Jun-12 15-Oct-12 08-Jan-13 28-Apr-13 161 Wet WorWet Works 13 25-Jun-12 09-Jul-12 08-Jan-13 12-Mar-13 203 A105090 Block Works 2 25-Jun-12 26-Jun-12 08-Jan-13 09-Jan-13 162 A54630 Installation of Doors& Windows Sub-frame 2 27-Jun-12 28-Jun-12 11-Mar-13 12-Mar-13 212 A54620 Plaster Works 5 27-Jun-12 02-Jul-12 28-Feb-13 05-Mar-13 203 A54640 1st Coat Paint 6 03-Jul-12 09-Jul-12 06-Mar-13 12-Mar-13 203 Fisrt StaFisrt Stage Finishes 66 30-Jun-12 16-Sep-12 13-Mar-13 25-Apr-13 184 A54660 Installation of Doors 2 30-Jun-12 01-Jul-12 13-Mar-13 14-Mar-13 212 A54730 Epoxy Paint Works 2 10-Jul-12 11-Jul-12 13-Mar-13 14-Mar-13 203 A54680 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Second SSecond Stage Finishes 2 12-Jul-12 14-Jul-12 24-Apr-13 25-Apr-13 237 A54650 Final Coat Paint 2 12-Jul-12 14-Jul-12 24-Apr-13 25-Apr-13 237 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A54720 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 StaircaseStaircase 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173 Stairs 1Stairs 1 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173 A109270 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147 A109280 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147 A109290 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109300 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109310 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147 A109320 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173 Stairs 2Stairs 2 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173 A109330 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147 A109340 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147 A109350 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109360 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109370 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147 A109380 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173 Stairs 3Stairs 3 43 11-Aug-12 01-Oct-12 07-Feb-13 28-Apr-13 173 A109390 Floor Screed 3 11-Aug-12 13-Aug-12 07-Feb-13 10-Feb-13 147 A109400 Install Handrails 4 14-Aug-12 18-Aug-12 11-Feb-13 14-Feb-13 147 A109410 Ceiling 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109420 Wall 1st Coat Paint 12 21-Aug-12 03-Sep-12 16-Feb-13 28-Feb-13 147 A109430 Install Granite/Terrazo 12 04-Sep-12 17-Sep-12 02-Mar-13 14-Mar-13 147 A109440 Final Coat Paint 12 18-Sep-12 01-Oct-12 15-Apr-13 28-Apr-13 173 1st Basemen1st Basement Floor 207 23-Jul-12 30-Mar-13 04-Oct-12 28-Apr-13 25 Public AreaPublic Area 207 23-Jul-12 30-Mar-13 04-Oct-12 28-Apr-13 25 Parking ArParking Area 87 13-Dec-12 26-Mar-13 13-Jan-13 28-Apr-13 28 FinishingFinishing Works 87 13-Dec-12 26-Mar-13 12-Feb-13 28-Apr-13 28 Wet WorWet Works 42 13-Dec-12 02-Feb-13 12-Feb-13 03-Mar-13 25 A59680 Plaster Works 5 13-Dec-12 18-Dec-12 12-Feb-13 17-Feb-13 50 A59690 1st Coat Paint 12 19-Jan-13 02-Feb-13 18-Feb-13 03-Mar-13 25 Traffic DTraffic Deck Coating 41 30-Jan-13 18-Mar-13 04-Mar-13 28-Apr-13 35 A115930 Installation of Speed Hump 7 30-Jan-13 06-Feb-13 21-Apr-13 28-Apr-13 69 A115910 Installation of Kerbs 8 03-Feb-13 11-Feb-13 04-Mar-13 12-Mar-13 25 A115920 Installation of Interlocking Tiles 8 12-Feb-13 20-Feb-13 13-Mar-13 21-Mar-13 25 A59620 Surface Preparation (including Grinding & Repairing) 8 21-Feb-13 02-Mar-13 23-Mar-13 31-Mar-13 25 A59630 Application of 1st Coat 5 27-Feb-13 04-Mar-13 01-Apr-13 06-Apr-13 28 A59670 Application of Final Coat 5 05-Mar-13 10-Mar-13 07-Apr-13 11-Apr-13 28 A59650 Road Marking & Arrows 7 11-Mar-13 18-Mar-13 13-Apr-13 20-Apr-13 28 Final StaFinal Stage Finishes 7 19-Mar-13 26-Mar-13 21-Apr-13 28-Apr-13 28 A59700 Final Coat Paint 5 19-Mar-13 24-Mar-13 21-Apr-13 25-Apr-13 28 A59720 Installation of Sinages 2 25-Mar-13 26-Mar-13 27-Apr-13 28-Apr-13 28 MEP WorkMEP Works 30 13-Dec-12 17-Jan-13 13-Jan-13 17-Feb-13 25 HVACHVAC 10 13-Dec-12 24-Dec-12 06-Feb-13 17-Feb-13 45 A59740 Chilled Water Pipe Installation & Insulation 7 13-Dec-12 20-Dec-12 06-Feb-13 13-Feb-13 45 A59750 Condensate Pipe Installation 7 13-Dec-12 20-Dec-12 06-Feb-13 13-Feb-13 45 A59820 Installation of Fan Induction 3 22-Dec-12 24-Dec-12 14-Feb-13 17-Feb-13 45 ElectricalElectrical 30 13-Dec-12 17-Jan-13 13-Jan-13 17-Feb-13 25 A115940 Instalaltion of Cable Trays 10 13-Dec-12 24-Dec-12 13-Jan-13 23-Jan-13 25 A115950 Instalaltion of Bus Bars 15 13-Dec-12 30-Dec-12 19-Jan-13 05-Feb-13 30 A115960 Cable Pulling 10 25-Dec-12 06-Jan-13 26-Jan-13 05-Feb-13 25 A59710 Installation of Lighting Fittings 10 07-Jan-13 17-Jan-13 06-Feb-13 17-Feb-13 25 PlumbingPlumbing 11 13-Dec-12 25-Dec-12 05-Feb-13 17-Feb-13 44 A59810 Floor Drain Fixning 5 13-Dec-12 18-Dec-12 12-Feb-13 17-Feb-13 50 A59790 H/L Hot&Cold Water Pipe Installation 7 13-Dec-12 20-Dec-12 05-Feb-13 12-Feb-13 44 A59830 H/L Drainage Pipes Installation 7 13-Dec-12 20-Dec-12 05-Feb-13 12-Feb-13 44 A59800 Water Pipes Testing 4 22-Dec-12 25-Dec-12 13-Feb-13 17-Feb-13 44 A59840 Drainage&Water Pipes Testing 4 22-Dec-12 25-Dec-12 13-Feb-13 17-Feb-13 44 Fire FighFire Fighting 26 13-Dec-12 13-Jan-13 17-Jan-13 17-Feb-13 29 A59780 Fire Fighting Pipe 8 13-Dec-12 22-Dec-12 17-Jan-13 27-Jan-13 29 A59770 Hydro Static Test for Pipes 5 23-Dec-12 27-Dec-12 28-Jan-13 02-Feb-13 29 A59760 Sprinkler Fixing 7 29-Dec-12 06-Jan-13 03-Feb-13 10-Feb-13 29 A59730 Fire Alarm Devices 6 07-Jan-13 13-Jan-13 11-Feb-13 17-Feb-13 29 RampRamp 85 19-Dec-12 30-Mar-13 03-Mar-13 28-Apr-13 25 A115970 Install Handrail 7 19-Dec-12 26-Dec-12 03-Mar-13 10-Mar-13 61 A115980 1st Coat Paint 10 27-Dec-12 08-Jan-13 11-Mar-13 21-Mar-13 61 A115990 Surface Preparation (including Grinding & Repairing) 8 21-Feb-13 02-Mar-13 23-Mar-13 31-Mar-13 25 A116000 Application of 1st Coat 5 03-Mar-13 07-Mar-13 01-Apr-13 06-Apr-13 25 A116010 Application of Final Coat 5 09-Mar-13 13-Mar-13 07-Apr-13 11-Apr-13 25 A116020 Road Marking & Arrows 7 14-Mar-13 21-Mar-13 13-Apr-13 20-Apr-13 25 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Water Supply Pipes&Fittings Installation of Sump Pump Install of Water Meter Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of GSM System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Plaster Works 1st Coat Paint Installation of Speed Hump Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Installation of Fan Induction Instalaltion of Cable Trays Instalaltion of Bus Bars Cable Pulling Installation of Lighting Fittings Floor Drain Fixning H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 53 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 54. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A116030 Final Coat Paint 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25 Lift LobbyLift Lobby 71 23-Jul-12 15-Oct-12 08-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 08-Jan-13 28-Apr-13 161 Wet WorWet Works 30 23-Jul-12 28-Aug-12 08-Jan-13 20-Feb-13 145 A59120 Block Works 4 23-Jul-12 26-Jul-12 08-Jan-13 12-Jan-13 138 A59070 Plaster Works 7 31-Jul-12 07-Aug-12 26-Jan-13 02-Feb-13 145 A59090 Installation of Suspended Ceiling Grid 5 14-Aug-12 21-Aug-12 09-Feb-13 13-Feb-13 145 A59080 1st Coat Paint 6 22-Aug-12 28-Aug-12 14-Feb-13 20-Feb-13 145 Fisrt StaFisrt Stage Finishes 9 29-Aug-12 08-Sep-12 21-Feb-13 03-Mar-13 145 A59100 Suspended Ceiling Tiles 5 29-Aug-12 03-Sep-12 21-Feb-13 26-Feb-13 145 A59340 MDF for Lift Lobby Wall 7 29-Aug-12 05-Sep-12 21-Feb-13 28-Feb-13 145 A59320 Screed Works 2 06-Sep-12 08-Sep-12 02-Mar-13 03-Mar-13 145 Second SSecond Stage Finishes 14 09-Sep-12 24-Sep-12 04-Mar-13 19-Mar-13 145 A59330 Wall Tiles Work 7 09-Sep-12 16-Sep-12 04-Mar-13 11-Mar-13 145 A59360 Floor Tiles Work 7 17-Sep-12 24-Sep-12 12-Mar-13 19-Mar-13 145 Final StaFinal Stage Finishes 18 25-Sep-12 15-Oct-12 20-Mar-13 28-Apr-13 161 A59110 Installation of Doors 2 25-Sep-12 26-Sep-12 20-Mar-13 21-Mar-13 145 A59130 Doors Ironmongery 2 25-Sep-12 26-Sep-12 27-Apr-13 28-Apr-13 177 A59370 Final Coat Paint 3 25-Sep-12 27-Sep-12 23-Apr-13 25-Apr-13 174 A59310 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 38 28-Jul-12 11-Sep-12 21-Jan-13 22-Apr-13 185 HVACHVAC 33 28-Jul-12 05-Sep-12 30-Jan-13 05-Mar-13 149 A59140 Duct Installation & Insulation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152 A59150 Chilled Water Pipe Installation & Insulation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152 A59160 Condensate Pipe Installation 5 28-Jul-12 01-Aug-12 30-Jan-13 04-Feb-13 152 A59170 FCU Installation 3 02-Aug-12 05-Aug-12 05-Feb-13 07-Feb-13 152 A59180 Air-Outlet Installation 2 04-Sep-12 05-Sep-12 04-Mar-13 05-Mar-13 149 ElectricalElectrical 37 28-Jul-12 10-Sep-12 21-Jan-13 05-Mar-13 145 A59190 Install Conduits in Wall 3 28-Jul-12 30-Jul-12 21-Jan-13 23-Jan-13 145 A59200 Install Cable Trays & Trunking 3 28-Jul-12 30-Jul-12 28-Jan-13 30-Jan-13 150 A59240 Cable Laying for Low Current System 3 31-Jul-12 02-Aug-12 11-Feb-13 13-Feb-13 159 A59250 Cable Laying for Power 3 31-Jul-12 02-Aug-12 11-Feb-13 13-Feb-13 159 A59210 Wiring for Lighting & Power 5 08-Aug-12 13-Aug-12 03-Feb-13 07-Feb-13 145 A59220 Wiring for Low Current System 5 08-Aug-12 13-Aug-12 03-Feb-13 07-Feb-13 145 A59270 Installation of Lighting Fittings 6 04-Sep-12 10-Sep-12 27-Feb-13 05-Mar-13 145 Fire FighFire Fighting 38 28-Jul-12 11-Sep-12 26-Jan-13 22-Apr-13 185 A59300 Fire Fighting Pipe 7 28-Jul-12 04-Aug-12 26-Jan-13 02-Feb-13 148 A59290 Hydro Static Test for Pipes 5 05-Aug-12 09-Aug-12 03-Feb-13 07-Feb-13 148 A59280 Sprinkler Fixing 5 04-Sep-12 09-Sep-12 28-Feb-13 05-Mar-13 146 A59350 Fire Alarm Devices 7 04-Sep-12 11-Sep-12 15-Apr-13 22-Apr-13 185 CorridorCorridor 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 Wet WorWet Works 24 23-Jul-12 21-Aug-12 09-Jan-13 21-Feb-13 152 A59430 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139 A59380 Plaster Works 5 30-Jul-12 04-Aug-12 02-Feb-13 06-Feb-13 152 A59400 Installation of Suspended Ceiling Grid 5 08-Aug-12 13-Aug-12 11-Feb-13 16-Feb-13 152 A59390 1st Coat Paint 5 14-Aug-12 21-Aug-12 17-Feb-13 21-Feb-13 152 Fisrt StaFisrt Stage Finishes 14 22-Aug-12 06-Sep-12 23-Feb-13 19-Mar-13 160 A59410 Suspended Ceiling Tiles 5 22-Aug-12 27-Aug-12 23-Feb-13 27-Feb-13 152 A59580 Epoxy Paint Works 3 04-Sep-12 06-Sep-12 17-Mar-13 19-Mar-13 160 Second SSecond Stage Finishes 8 08-Sep-12 16-Sep-12 20-Mar-13 25-Apr-13 184 A59420 Installation of Doors 2 08-Sep-12 09-Sep-12 20-Mar-13 21-Mar-13 160 A59440 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A59570 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 32 26-Jul-12 03-Sep-12 29-Jan-13 16-Mar-13 160 HVACHVAC 31 26-Jul-12 02-Sep-12 31-Jan-13 05-Mar-13 152 A59450 Duct Installation & Insulation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154 A59460 Chilled Water Pipe Installation & Insulation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154 A59470 Condensate Pipe Installation 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154 A59480 FCU Installation 4 01-Aug-12 05-Aug-12 06-Feb-13 10-Feb-13 154 A59490 Air-Outlet Installation 5 28-Aug-12 02-Sep-12 28-Feb-13 05-Mar-13 152 ElectricalElectrical 29 26-Jul-12 30-Aug-12 29-Jan-13 05-Mar-13 154 A59500 Install Conduits in Wall 3 26-Jul-12 29-Jul-12 29-Jan-13 31-Jan-13 152 A59510 Wiring for Lighting & Power 3 05-Aug-12 07-Aug-12 07-Feb-13 10-Feb-13 152 A59520 Installation of Lighting Fittings 3 28-Aug-12 30-Aug-12 03-Mar-13 05-Mar-13 154 PlumbingPlumbing 10 26-Jul-12 06-Aug-12 30-Jan-13 10-Feb-13 153 A59600 H/L Hot&Cold Water Pipe Installation 5 26-Jul-12 31-Jul-12 30-Jan-13 04-Feb-13 153 A59610 Water Pipes Testing 5 01-Aug-12 06-Aug-12 05-Feb-13 10-Feb-13 153 Fire FighFire Fighting 32 26-Jul-12 03-Sep-12 31-Jan-13 16-Mar-13 160 A59560 Fire Fighting Pipe 5 26-Jul-12 31-Jul-12 31-Jan-13 05-Feb-13 154 A59550 Hydro Static Test for Pipes 4 01-Aug-12 05-Aug-12 06-Feb-13 10-Feb-13 154 A59540 Sprinkler Fixing 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 A59590 Fire Alarm Devices 5 28-Aug-12 02-Sep-12 11-Mar-13 16-Mar-13 161 A59530 Installation of Fire Extingusher&Blanket 2 02-Sep-12 03-Sep-12 14-Mar-13 16-Mar-13 160 LV Room (LV Room (Block B) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173 A56450 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136 A56410 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187 A56400 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136 A56420 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136 Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178 A56440 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187 A56460 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A56510 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148 Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 A56430 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A56500 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148 HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A56540 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136 A56470 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136 A56480 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136 A56490 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A114600 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136 A56550 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136 A114610 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136 A114620 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136 Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 A56520 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 LV Room 1LV Room 1 (Block C) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173 A56610 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136 A56570 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187 A56560 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136 A56580 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136 Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178 A56600 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Laying of LV Cables Installation of MDBs Test of LV Cables Termination of LV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 54 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 55. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A56620 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A56670 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148 Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 A56590 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A56660 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148 HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A56690 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136 A56630 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136 A56640 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136 A56650 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A114630 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136 A56700 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136 A114640 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136 A114650 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136 Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 A56680 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 LV Room 2LV Room 2 (Block C) 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 25 23-Jul-12 22-Aug-12 06-Jan-13 19-Mar-13 173 A56760 Block Works 4 23-Jul-12 26-Jul-12 06-Jan-13 09-Jan-13 136 A56720 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187 A56710 Plaster Works 6 02-Aug-12 08-Aug-12 16-Jan-13 22-Jan-13 136 A56730 1st Coat Paint 5 15-Aug-12 22-Aug-12 30-Jan-13 04-Feb-13 136 Fisrt StaFisrt Stage Finishes 41 05-Aug-12 23-Sep-12 20-Mar-13 25-Apr-13 178 A56750 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187 A56770 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A56820 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 20-Mar-13 21-Mar-13 148 Second SSecond Stage Finishes 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 A56740 Final Coat Paint 3 24-Sep-12 26-Sep-12 23-Apr-13 25-Apr-13 175 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A56810 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 46 28-Jul-12 20-Sep-12 10-Jan-13 19-Mar-13 148 HVACHVAC 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A56840 Air-Outlet Installation 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 ElectricalElectrical 46 28-Jul-12 20-Sep-12 10-Jan-13 05-Mar-13 136 A56780 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 10-Jan-13 15-Jan-13 136 A56790 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 23-Jan-13 29-Jan-13 136 A56800 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A114660 Laying of LV Cables 15 23-Aug-12 09-Sep-12 05-Feb-13 21-Feb-13 136 A56850 Installation of MDBs 20 23-Aug-12 15-Sep-12 05-Feb-13 27-Feb-13 136 A114670 Test of LV Cables 5 10-Sep-12 15-Sep-12 23-Feb-13 27-Feb-13 136 A114680 Termination of LV Cables 5 16-Sep-12 20-Sep-12 28-Feb-13 05-Mar-13 136 Fire FighFire Fighting 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 A56830 Fire Alarm Devices 10 23-Aug-12 03-Sep-12 09-Mar-13 19-Mar-13 163 LaundryLaundry 102 31-Oct-12 03-Mar-13 14-Nov-12 28-Apr-13 48 FinishingFinishing Works 77 01-Dec-12 03-Mar-13 16-Dec-12 28-Apr-13 48 Wet WorWet Works 30 01-Dec-12 06-Jan-13 16-Dec-12 20-Jan-13 12 A58270 Block Works 10 01-Dec-12 12-Dec-12 16-Dec-12 26-Dec-12 12 A58220 Plaster Works 10 23-Dec-12 03-Jan-13 07-Jan-13 17-Jan-13 12 A58230 1st Coat Paint 6 30-Dec-12 06-Jan-13 14-Jan-13 20-Jan-13 12 Fisrt StaFisrt Stage Finishes 17 06-Feb-13 25-Feb-13 20-Feb-13 22-Apr-13 48 A58240 Installation of Suspended Ceiling Grid 7 06-Feb-13 13-Feb-13 20-Feb-13 27-Feb-13 12 A58250 Suspended Ceiling Tiles 6 10-Feb-13 16-Feb-13 24-Feb-13 02-Mar-13 12 A58420 Epoxy Paint Works 5 20-Feb-13 25-Feb-13 17-Apr-13 22-Apr-13 48 Second SSecond Stage Finishes 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48 A58260 Installation of Doors 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48 A58280 Doors Ironmongery 3 26-Feb-13 28-Feb-13 23-Apr-13 25-Apr-13 48 Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48 A58410 Installation of Sinages 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48 MEP WorkMEP Works 92 31-Oct-12 19-Feb-13 14-Nov-12 16-Apr-13 48 HVACHVAC 57 13-Dec-12 19-Feb-13 21-Jan-13 05-Mar-13 12 A58290 Duct Installation & Insulation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40 A58300 Chilled Water Pipe Installation & Insulation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40 A58310 Condensate Pipe Installation 10 13-Dec-12 24-Dec-12 31-Jan-13 11-Feb-13 40 A58320 FCU Installation 7 25-Dec-12 02-Jan-13 12-Feb-13 19-Feb-13 40 A58720 Installation of FAHU 25 07-Jan-13 05-Feb-13 21-Jan-13 19-Feb-13 12 A58330 Air-Outlet Installation 5 14-Feb-13 19-Feb-13 28-Feb-13 05-Mar-13 12 ElectricalElectrical 56 13-Dec-12 18-Feb-13 27-Dec-12 05-Mar-13 13 A58340 Install Conduits in Wall 8 13-Dec-12 22-Dec-12 27-Dec-12 06-Jan-13 12 A58350 Wiring for Lighting & Power 8 05-Jan-13 13-Jan-13 11-Feb-13 19-Feb-13 31 A58360 Installation of Lighting Fittings 5 13-Feb-13 18-Feb-13 28-Feb-13 05-Mar-13 13 PlumbingPlumbing 15 13-Dec-12 30-Dec-12 03-Feb-13 19-Feb-13 42 A58440 H/L Hot&Cold Water Pipe Installation 10 13-Dec-12 24-Dec-12 03-Feb-13 13-Feb-13 42 A58450 Water Pipes Testing 5 25-Dec-12 30-Dec-12 14-Feb-13 19-Feb-13 42 Fire FighFire Fighting 55 13-Dec-12 17-Feb-13 02-Feb-13 16-Apr-13 50 A58400 Fire Fighting Pipe 10 13-Dec-12 24-Dec-12 02-Feb-13 12-Feb-13 41 A58390 Hydro Static Test for Pipes 6 25-Dec-12 31-Dec-12 13-Feb-13 19-Feb-13 41 A58370 Installation of Fire Extingusher&Blanket 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51 A58380 Sprinkler Fixing 3 13-Feb-13 16-Feb-13 03-Mar-13 05-Mar-13 15 A58430 Fire Alarm Devices 4 13-Feb-13 17-Feb-13 13-Apr-13 16-Apr-13 50 LaundryLaundry Equipments 50 31-Oct-12 30-Dec-12 14-Nov-12 14-Jan-13 12 A105460 Installation of Laundry Equipments 50 31-Oct-12 30-Dec-12 14-Nov-12 14-Jan-13 12 ELV RoomsELV Rooms 116 23-Jul-12 11-Dec-12 24-Oct-12 28-Apr-13 116 FinishingFinishing Works 116 23-Jul-12 11-Dec-12 24-Oct-12 28-Apr-13 116 Wet WorWet Works 28 23-Jul-12 26-Aug-12 24-Oct-12 19-Mar-13 170 A56910 Block Works 4 23-Jul-12 26-Jul-12 24-Oct-12 30-Oct-12 78 A56870 Installation of Doors& Windows Sub-frame 2 02-Aug-12 04-Aug-12 18-Mar-13 19-Mar-13 187 A56860 Plaster Works 7 02-Aug-12 09-Aug-12 06-Nov-12 13-Nov-12 78 A56880 1st Coat Paint 7 16-Aug-12 26-Aug-12 21-Nov-12 28-Nov-12 78 Fisrt StaFisrt Stage Finishes 100 05-Aug-12 05-Dec-12 20-Mar-13 25-Apr-13 119 A56900 Installation of Doors 2 05-Aug-12 06-Aug-12 20-Mar-13 21-Mar-13 187 A56920 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A56970 Epoxy Paint Works 2 04-Dec-12 05-Dec-12 20-Mar-13 21-Mar-13 89 Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 23-Apr-13 25-Apr-13 116 A56890 Final Coat Paint 3 06-Dec-12 09-Dec-12 23-Apr-13 25-Apr-13 116 Final StaFinal Stage Finishes 2 10-Dec-12 11-Dec-12 27-Apr-13 28-Apr-13 116 A56960 Installation of Sinages 2 10-Dec-12 11-Dec-12 27-Apr-13 28-Apr-13 116 MEP WorkMEP Works 105 28-Jul-12 03-Dec-12 31-Oct-12 19-Mar-13 89 HVACHVAC 7 27-Aug-12 03-Sep-12 26-Feb-13 05-Mar-13 151 A57000 Air-Outlet Installation 7 27-Aug-12 03-Sep-12 26-Feb-13 05-Mar-13 151 ElectricalElectrical 105 28-Jul-12 03-Dec-12 31-Oct-12 05-Mar-13 77 A56930 Install Conduits in Wall 5 28-Jul-12 01-Aug-12 31-Oct-12 05-Nov-12 78 A56940 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 14-Nov-12 20-Nov-12 78 A56950 Installation of Lighting Fittings 5 27-Aug-12 01-Sep-12 28-Feb-13 05-Mar-13 153 A114330 Installation of MATC,TV System 80 27-Aug-12 01-Dec-12 29-Nov-12 05-Mar-13 78 A114320 Installation of Access ControlSystem 80 28-Aug-12 03-Dec-12 29-Nov-12 05-Mar-13 77 Fire FighFire Fighting 8 27-Aug-12 04-Sep-12 11-Mar-13 19-Mar-13 162 A56980 Fire Alarm Devices 8 27-Aug-12 04-Sep-12 11-Mar-13 19-Mar-13 162 StoresStores 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Laying of LV Cables Installation of MDBs Test of LV Cables Termination of LV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Laying of LV Cables Installation of MDBs Test of LV Cables Termination of LV Cables Fire Alarm Devices Block Works Plaster Works 1st Coat Paint Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Installation of FAHU Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Installation of Laundry Equipments Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of MATC,TV System Installation of Access ControlSystem Fire Alarm Devices Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 55 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 56. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 Wet WorWet Works 24 23-Jul-12 21-Aug-12 09-Jan-13 19-Feb-13 150 A57950 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139 A57890 Plaster Works 3 31-Jul-12 02-Aug-12 31-Jan-13 03-Feb-13 150 A57910 Installation of Suspended Ceiling Grid 6 08-Aug-12 14-Aug-12 09-Feb-13 14-Feb-13 150 A57900 1st Coat Paint 4 15-Aug-12 21-Aug-12 16-Feb-13 19-Feb-13 150 Fisrt StaFisrt Stage Finishes 17 22-Aug-12 10-Sep-12 20-Feb-13 19-Mar-13 157 A57920 Suspended Ceiling Tiles 5 22-Aug-12 27-Aug-12 20-Feb-13 25-Feb-13 150 A58180 Epoxy Paint Works 3 08-Sep-12 10-Sep-12 17-Mar-13 19-Mar-13 157 Second SSecond Stage Finishes 5 11-Sep-12 16-Sep-12 20-Mar-13 25-Apr-13 184 A57930 Installation of Doors 2 11-Sep-12 12-Sep-12 20-Mar-13 21-Mar-13 157 A57960 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A58170 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 35 26-Jul-12 06-Sep-12 27-Jan-13 16-Mar-13 157 HVACHVAC 30 26-Jul-12 01-Sep-12 29-Jan-13 05-Mar-13 153 A57970 Duct Installation & Insulation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152 A57980 Chilled Water Pipe Installation & Insulation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152 A57990 Condensate Pipe Installation 5 26-Jul-12 31-Jul-12 29-Jan-13 03-Feb-13 152 A58000 FCU Installation 4 01-Aug-12 05-Aug-12 04-Feb-13 07-Feb-13 152 A58010 Air-Outlet Installation 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 ElectricalElectrical 31 26-Jul-12 02-Sep-12 27-Jan-13 05-Mar-13 152 A58020 Install Conduits in Wall 4 26-Jul-12 30-Jul-12 27-Jan-13 30-Jan-13 150 A58040 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 04-Feb-13 07-Feb-13 150 A58100 Installation of Lighting Fittings 5 28-Aug-12 02-Sep-12 28-Feb-13 05-Mar-13 152 Fire FighFire Fighting 35 26-Jul-12 06-Sep-12 27-Jan-13 16-Mar-13 157 A58160 Fire Fighting Pipe 7 26-Jul-12 02-Aug-12 27-Jan-13 03-Feb-13 150 A58150 Hydro Static Test for Pipes 4 04-Aug-12 07-Aug-12 04-Feb-13 07-Feb-13 150 A58140 Sprinkler Fixing 7 28-Aug-12 04-Sep-12 26-Feb-13 05-Mar-13 150 A58210 Fire Alarm Devices 7 28-Aug-12 04-Sep-12 09-Mar-13 16-Mar-13 159 A58130 Installation of Fire Extingusher&Blanket 2 05-Sep-12 06-Sep-12 14-Mar-13 16-Mar-13 157 Staff LockeStaff Lockers 108 23-Jul-12 01-Dec-12 09-Dec-12 28-Apr-13 124 FinishingFinishing Works 108 23-Jul-12 01-Dec-12 09-Dec-12 28-Apr-13 124 Wet WorWet Works 28 23-Jul-12 26-Aug-12 09-Dec-12 13-Mar-13 165 A58770 Block Works 7 23-Jul-12 30-Jul-12 09-Dec-12 16-Dec-12 113 A58690 Plaster Works 7 08-Aug-12 15-Aug-12 25-Dec-12 02-Jan-13 113 A58700 Installation of Doors& Windows Sub-frame 7 08-Aug-12 15-Aug-12 06-Mar-13 13-Mar-13 172 A59020 Wall Tiles Work 7 16-Aug-12 26-Aug-12 03-Jan-13 10-Jan-13 113 Fisrt StaFisrt Stage Finishes 14 27-Aug-12 11-Sep-12 12-Jan-13 28-Jan-13 113 A59010 Screed Works 7 27-Aug-12 03-Sep-12 12-Jan-13 19-Jan-13 113 A58730 Water Proofing for Wet Area 7 04-Sep-12 11-Sep-12 20-Jan-13 28-Jan-13 113 Second SSecond Stage Finishes 38 12-Sep-12 28-Oct-12 29-Jan-13 13-Mar-13 113 A59050 Installation of Suspended Ceiling Grid 7 12-Sep-12 19-Sep-12 29-Jan-13 05-Feb-13 113 A59040 Suspended Ceiling Tiles 7 20-Sep-12 27-Sep-12 06-Feb-13 13-Feb-13 113 A59920 Instllation of Lockers 10 29-Sep-12 09-Oct-12 14-Feb-13 25-Feb-13 113 A59030 Floor Tiles Work 7 18-Oct-12 28-Oct-12 06-Mar-13 13-Mar-13 113 Final StaFinal Stage Finishes 14 14-Nov-12 01-Dec-12 14-Mar-13 28-Apr-13 124 A58740 Installation of Windows&Doors 7 14-Nov-12 22-Nov-12 14-Mar-13 21-Mar-13 99 A58780 Doors Ironmongery 7 14-Nov-12 22-Nov-12 13-Apr-13 20-Apr-13 124 A59000 Installation of Sinages 7 24-Nov-12 01-Dec-12 21-Apr-13 28-Apr-13 124 MEP WorkMEP Works 66 31-Jul-12 17-Oct-12 17-Dec-12 24-Apr-13 156 HVACHVAC 56 31-Jul-12 06-Oct-12 12-Jan-13 05-Mar-13 123 A58790 Duct Installation & Insulation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58800 Chilled Water Pipe Installation & Insulation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58810 Condensate Pipe Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58820 FCU Installation 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134 A58830 Air-Outlet Installation 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123 ElectricalElectrical 56 31-Jul-12 06-Oct-12 17-Dec-12 05-Mar-13 123 A58840 Install Conduits in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113 A58850 Wiring for Lighting & Power 7 16-Aug-12 26-Aug-12 20-Jan-13 28-Jan-13 127 A58860 Installation of Lighting Fittings 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123 PlumbingPlumbing 66 31-Jul-12 17-Oct-12 17-Dec-12 05-Mar-13 113 A58870 Drainge Pipes in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113 A58880 H/L Drainage Pipes Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58890 H/L Hot&Cold Water Pipe Installation 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58940 Water Pipes in Wall 7 31-Jul-12 07-Aug-12 17-Dec-12 24-Dec-12 113 A58900 Drainage&Water Pipes Testing 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134 A58910 ElectricalWater Heater Installation 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134 A58920 Floor Drain Fixning 7 29-Aug-12 05-Sep-12 26-Feb-13 05-Mar-13 149 A58930 Installation of Sanitaryware 7 10-Oct-12 17-Oct-12 26-Feb-13 05-Mar-13 113 Fire FighFire Fighting 63 31-Jul-12 14-Oct-12 12-Jan-13 24-Apr-13 159 A58980 Fire Fighting Pipe 7 31-Jul-12 07-Aug-12 12-Jan-13 19-Jan-13 134 A58970 Hydro Static Test for Pipes 7 08-Aug-12 15-Aug-12 20-Jan-13 28-Jan-13 134 A58960 Sprinkler Fixing 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123 A59060 Fire Alarm Devices 7 29-Sep-12 06-Oct-12 26-Feb-13 05-Mar-13 123 A58950 Installation of Fire Extingusher&Blanket 7 07-Oct-12 14-Oct-12 17-Apr-13 24-Apr-13 159 Pump RooPump Room 1 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161 Wet WorWet Works 24 23-Jul-12 21-Aug-12 25-Dec-12 19-Mar-13 174 A55040 Block Works 6 23-Jul-12 29-Jul-12 25-Dec-12 31-Dec-12 127 A55000 Installation of Doors& Windows Sub-frame 1 02-Aug-12 02-Aug-12 19-Mar-13 19-Mar-13 188 A54990 Plaster Works 6 02-Aug-12 08-Aug-12 06-Jan-13 12-Jan-13 127 A55010 1st Coat Paint 6 13-Aug-12 21-Aug-12 16-Jan-13 22-Jan-13 127 Fisrt StaFisrt Stage Finishes 51 04-Aug-12 03-Oct-12 20-Mar-13 25-Apr-13 169 A55030 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188 A55050 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A55100 Epoxy Paint Works 2 02-Oct-12 03-Oct-12 20-Mar-13 21-Mar-13 139 Second SSecond Stage Finishes 3 04-Oct-12 07-Oct-12 23-Apr-13 25-Apr-13 166 A55020 Final Coat Paint 3 04-Oct-12 07-Oct-12 23-Apr-13 25-Apr-13 166 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A55090 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 53 30-Jul-12 01-Oct-12 02-Jan-13 24-Apr-13 170 HVACHVAC 53 30-Jul-12 01-Oct-12 23-Jan-13 05-Mar-13 127 A55120 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55130 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55140 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55150 FCU Installation 5 07-Aug-12 12-Aug-12 20-Feb-13 25-Feb-13 161 A55160 Air-Outlet Installation 7 13-Aug-12 22-Aug-12 26-Feb-13 05-Mar-13 161 A105410 Installation of Pumps 35 22-Aug-12 01-Oct-12 23-Jan-13 05-Mar-13 127 ElectricalElectrical 23 30-Jul-12 27-Aug-12 02-Jan-13 05-Mar-13 157 A55060 Install Conduits in Wall 3 30-Jul-12 01-Aug-12 02-Jan-13 05-Jan-13 127 A55070 Wiring for Lighting & Power 3 09-Aug-12 12-Aug-12 13-Jan-13 15-Jan-13 127 A55080 Installation of Lighting Fittings 5 22-Aug-12 27-Aug-12 28-Feb-13 05-Mar-13 157 PlumbingPlumbing 33 30-Jul-12 08-Sep-12 17-Feb-13 05-Mar-13 147 A55220 H/L Hot&Cold Water Pipe Installation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168 A55230 Water Pipes Testing 5 07-Aug-12 12-Aug-12 28-Feb-13 05-Mar-13 168 A55240 Installation of Transfer Pump 15 22-Aug-12 08-Sep-12 17-Feb-13 05-Mar-13 147 Fire FighFire Fighting 48 30-Jul-12 25-Sep-12 30-Jan-13 24-Apr-13 175 A55200 Fire Fighting Pipe 7 30-Jul-12 06-Aug-12 16-Feb-13 23-Feb-13 164 A55190 Hydro Static Test for Pipes 4 07-Aug-12 11-Aug-12 24-Feb-13 27-Feb-13 164 A55180 Sprinkler Fixing 5 12-Aug-12 16-Aug-12 28-Feb-13 05-Mar-13 164 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Instllation of Lockers Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Installation of Pumps Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Installation of Transfer Pump Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 56 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 57. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A55170 Installation of Fire Extingusher&Blanket 3 18-Aug-12 22-Aug-12 22-Apr-13 24-Apr-13 204 A55110 Fire Alarm Devices 6 18-Aug-12 26-Aug-12 13-Mar-13 19-Mar-13 170 A55530 Installation of Fire Fighting Pump 30 22-Aug-12 25-Sep-12 30-Jan-13 05-Mar-13 132 Pump RooPump Room 2 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 26 23-Jul-12 23-Aug-12 06-Jan-13 19-Mar-13 172 A55590 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136 A55550 Installation of Doors& Windows Sub-frame 1 02-Aug-12 02-Aug-12 19-Mar-13 19-Mar-13 188 A55540 Plaster Works 6 02-Aug-12 08-Aug-12 28-Jan-13 03-Feb-13 145 A55560 1st Coat Paint 6 15-Aug-12 23-Aug-12 10-Feb-13 16-Feb-13 145 Fisrt StaFisrt Stage Finishes 36 04-Aug-12 16-Sep-12 20-Mar-13 25-Apr-13 184 A55580 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188 A55650 Epoxy Paint Works 2 11-Sep-12 12-Sep-12 20-Mar-13 21-Mar-13 157 A55600 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Second SSecond Stage Finishes 3 13-Sep-12 16-Sep-12 23-Apr-13 25-Apr-13 184 A55570 Final Coat Paint 3 13-Sep-12 16-Sep-12 23-Apr-13 25-Apr-13 184 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A55640 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 35 30-Jul-12 10-Sep-12 23-Jan-13 24-Apr-13 188 HVACHVAC 19 30-Jul-12 22-Aug-12 12-Feb-13 05-Mar-13 161 A55670 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55680 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55690 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 12-Feb-13 19-Feb-13 161 A55700 FCU Installation 5 07-Aug-12 12-Aug-12 20-Feb-13 25-Feb-13 161 A55710 Air-Outlet Installation 7 13-Aug-12 22-Aug-12 26-Feb-13 05-Mar-13 161 ElectricalElectrical 25 30-Jul-12 29-Aug-12 23-Jan-13 05-Mar-13 155 A55610 Install Conduits in Wall 3 30-Jul-12 01-Aug-12 23-Jan-13 27-Jan-13 145 A55620 Wiring for Lighting & Power 5 09-Aug-12 14-Aug-12 04-Feb-13 09-Feb-13 145 A55630 Installation of Lighting Fittings 5 25-Aug-12 29-Aug-12 28-Feb-13 05-Mar-13 155 PlumbingPlumbing 35 30-Jul-12 10-Sep-12 17-Feb-13 05-Mar-13 145 A55760 H/L Hot&Cold Water Pipe Installation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168 A55770 Water Pipes Testing 5 07-Aug-12 12-Aug-12 28-Feb-13 05-Mar-13 168 A55780 Installation of Transfer Pump 15 25-Aug-12 10-Sep-12 17-Feb-13 05-Mar-13 145 Fire FighFire Fighting 27 30-Jul-12 01-Sep-12 16-Feb-13 24-Apr-13 196 A55750 Fire Fighting Pipe 7 30-Jul-12 06-Aug-12 16-Feb-13 23-Feb-13 164 A55740 Hydro Static Test for Pipes 4 07-Aug-12 11-Aug-12 24-Feb-13 27-Feb-13 164 A55730 Sprinkler Fixing 5 12-Aug-12 16-Aug-12 28-Feb-13 05-Mar-13 164 A55720 Installation of Fire Extingusher&Blanket 3 18-Aug-12 22-Aug-12 22-Apr-13 24-Apr-13 204 A55660 Fire Alarm Devices 6 18-Aug-12 26-Aug-12 13-Mar-13 19-Mar-13 170 A55790 Installation of Fire Fighting Pump 7 25-Aug-12 01-Sep-12 26-Feb-13 05-Mar-13 153 AHU RoomAHU Room 75 23-Jul-12 20-Oct-12 17-Dec-12 28-Apr-13 157 FinishingFinishing Works 75 23-Jul-12 20-Oct-12 17-Dec-12 28-Apr-13 157 Wet WorWet Works 36 23-Jul-12 04-Sep-12 17-Dec-12 19-Mar-13 162 A55850 Block Works 8 23-Jul-12 31-Jul-12 17-Dec-12 25-Dec-12 120 A55810 Installation of Doors& Windows Sub-frame 1 09-Aug-12 09-Aug-12 19-Mar-13 19-Mar-13 182 A55800 Plaster Works 7 09-Aug-12 16-Aug-12 05-Jan-13 12-Jan-13 120 A55820 1st Coat Paint 7 28-Aug-12 04-Sep-12 21-Jan-13 29-Jan-13 120 Fisrt StaFisrt Stage Finishes 52 11-Aug-12 11-Oct-12 20-Mar-13 25-Apr-13 162 A55840 Installation of Doors 2 11-Aug-12 12-Aug-12 20-Mar-13 21-Mar-13 182 A55860 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A55910 Epoxy Paint Works 2 10-Oct-12 11-Oct-12 20-Mar-13 21-Mar-13 132 Second SSecond Stage Finishes 5 13-Oct-12 17-Oct-12 21-Apr-13 25-Apr-13 157 A55830 Final Coat Paint 5 13-Oct-12 17-Oct-12 21-Apr-13 25-Apr-13 157 Final StaFinal Stage Finishes 2 18-Oct-12 20-Oct-12 27-Apr-13 28-Apr-13 157 A55900 Installation of Sinages 2 18-Oct-12 20-Oct-12 27-Apr-13 28-Apr-13 157 MEP WorkMEP Works 58 01-Aug-12 09-Oct-12 26-Dec-12 24-Apr-13 163 HVACHVAC 58 01-Aug-12 09-Oct-12 30-Jan-13 05-Mar-13 120 A55930 Duct Installation & Insulation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171 A55940 Chilled Water Pipe Installation & Insulation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171 A55950 Condensate Pipe Installation 7 01-Aug-12 08-Aug-12 26-Feb-13 05-Mar-13 171 A56060 Installation of AHU 30 05-Sep-12 09-Oct-12 30-Jan-13 05-Mar-13 120 ElectricalElectrical 34 01-Aug-12 11-Sep-12 26-Dec-12 05-Mar-13 144 A55870 Install Conduits in Wall 7 01-Aug-12 08-Aug-12 26-Dec-12 03-Jan-13 120 A55880 Wiring for Lighting & Power 7 18-Aug-12 27-Aug-12 13-Jan-13 20-Jan-13 120 A55890 Installation of Lighting Fittings 6 05-Sep-12 11-Sep-12 27-Feb-13 05-Mar-13 144 PlumbingPlumbing 30 01-Aug-12 06-Sep-12 20-Feb-13 05-Mar-13 148 A56020 H/L Drainage Pipes Installation 7 01-Aug-12 08-Aug-12 20-Feb-13 27-Feb-13 166 A56030 H/L Hot&Cold Water Pipe Installation 7 01-Aug-12 08-Aug-12 20-Feb-13 27-Feb-13 166 A56040 Drainage&Water Pipes Testing 5 09-Aug-12 14-Aug-12 28-Feb-13 05-Mar-13 166 A56050 Floor Drain Fixning 2 05-Sep-12 06-Sep-12 04-Mar-13 05-Mar-13 148 Fire FighFire Fighting 22 01-Aug-12 28-Aug-12 16-Feb-13 24-Apr-13 199 A56010 Fire Fighting Pipe 7 01-Aug-12 08-Aug-12 16-Feb-13 23-Feb-13 162 A56000 Hydro Static Test for Pipes 4 09-Aug-12 13-Aug-12 24-Feb-13 27-Feb-13 162 A55990 Sprinkler Fixing 5 14-Aug-12 21-Aug-12 28-Feb-13 05-Mar-13 162 A55980 Installation of Fire Extingusher&Blanket 2 22-Aug-12 23-Aug-12 23-Apr-13 24-Apr-13 203 A55920 Fire Alarm Devices 6 22-Aug-12 28-Aug-12 13-Mar-13 19-Mar-13 168 BMS RoomBMS Room 98 23-Jul-12 19-Nov-12 20-Nov-12 28-Apr-13 134 FinishingFinishing Works 98 23-Jul-12 19-Nov-12 20-Nov-12 28-Apr-13 134 Wet WorWet Works 11 23-Jul-12 04-Aug-12 20-Nov-12 18-Mar-13 186 A58510 Block Works 2 23-Jul-12 24-Jul-12 20-Nov-12 21-Nov-12 98 A58470 Installation of Doors& Windows Sub-frame 1 28-Jul-12 28-Jul-12 18-Mar-13 18-Mar-13 192 A58460 Plaster Works 2 28-Jul-12 29-Jul-12 25-Nov-12 26-Nov-12 98 A58480 1st Coat Paint 3 01-Aug-12 04-Aug-12 29-Nov-12 03-Dec-12 98 Fisrt StaFisrt Stage Finishes 22 16-Oct-12 12-Nov-12 14-Feb-13 18-Mar-13 104 A58630 Installation of Suspended Ceiling Grid 7 16-Oct-12 23-Oct-12 14-Feb-13 21-Feb-13 98 A58640 Suspended Ceiling Tiles 7 24-Oct-12 03-Nov-12 23-Feb-13 02-Mar-13 98 A58660 Screed Works 4 04-Nov-12 07-Nov-12 10-Mar-13 13-Mar-13 104 A58650 Floor Tiles Work 4 08-Nov-12 12-Nov-12 14-Mar-13 18-Mar-13 104 Second SSecond Stage Finishes 3 13-Nov-12 17-Nov-12 19-Mar-13 25-Apr-13 134 A58490 Final Coat Paint 3 13-Nov-12 17-Nov-12 23-Apr-13 25-Apr-13 134 A58500 Installation of Doors 3 13-Nov-12 17-Nov-12 19-Mar-13 21-Mar-13 104 A58520 Doors Ironmongery 3 13-Nov-12 17-Nov-12 23-Apr-13 25-Apr-13 134 Final StaFinal Stage Finishes 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134 A58560 Installation of Sinages 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134 MEP WorkMEP Works 92 25-Jul-12 13-Nov-12 22-Nov-12 24-Apr-13 135 HVACHVAC 86 25-Jul-12 06-Nov-12 07-Feb-13 05-Mar-13 98 A58580 Chilled Water Pipe Installation & Insulation 3 25-Jul-12 28-Jul-12 07-Feb-13 10-Feb-13 161 A58590 Condensate Pipe Installation 3 25-Jul-12 28-Jul-12 07-Feb-13 10-Feb-13 161 A58600 FCU Installation 3 29-Jul-12 31-Jul-12 11-Feb-13 13-Feb-13 161 A58610 Air-Outlet Installation 3 04-Nov-12 06-Nov-12 03-Mar-13 05-Mar-13 98 ElectricalElectrical 85 25-Jul-12 05-Nov-12 22-Nov-12 05-Mar-13 99 A58530 Install Conduits in Wall 2 25-Jul-12 26-Jul-12 22-Nov-12 24-Nov-12 98 A58540 Wiring for Lighting & Power 2 30-Jul-12 31-Jul-12 27-Nov-12 28-Nov-12 98 A58710 Installation of BMS System 60 05-Aug-12 15-Oct-12 04-Dec-12 13-Feb-13 98 A58550 Installation of Lighting Fittings 2 04-Nov-12 05-Nov-12 04-Mar-13 05-Mar-13 99 PlumbingPlumbing 14 25-Jul-12 09-Aug-12 29-Jan-13 13-Feb-13 153 A58670 H/L Hot&Cold Water Pipe Installation 7 25-Jul-12 01-Aug-12 29-Jan-13 05-Feb-13 153 A58680 Water Pipes Testing 7 02-Aug-12 09-Aug-12 06-Feb-13 13-Feb-13 153 Fire FighFire Fighting 9 04-Nov-12 13-Nov-12 15-Apr-13 24-Apr-13 135 A58570 Fire Alarm Devices 2 04-Nov-12 05-Nov-12 15-Apr-13 16-Apr-13 135 A58620 Installation of Fire Extingusher&Blanket 7 06-Nov-12 13-Nov-12 17-Apr-13 24-Apr-13 135 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Fire Extingusher&Blanket Fire Alarm Devices Installation of Fire Fighting Pump Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Installation of Transfer Pump Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Installation of Fire Fighting Pump Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Installation of AHU Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Screed Works Floor Tiles Work Final Coat Paint Installation of Doors Doors Ironmongery Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of BMS System Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Fire Alarm Devices Installation of Fire Extingusher&Blanket Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 57 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 58. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Server RooServer Room 131 23-Jul-12 29-Dec-12 07-Oct-12 28-Apr-13 101 FinishingFinishing Works 131 23-Jul-12 29-Dec-12 07-Oct-12 28-Apr-13 101 Wet WorWet Works 28 23-Jul-12 26-Aug-12 07-Oct-12 19-Mar-13 170 A57370 Block Works 6 23-Jul-12 29-Jul-12 07-Oct-12 13-Oct-12 63 A57300 Installation of Doors& Windows Sub-frame 2 04-Aug-12 05-Aug-12 18-Mar-13 19-Mar-13 186 A57290 Plaster Works 10 04-Aug-12 14-Aug-12 18-Oct-12 31-Oct-12 63 A57310 1st Coat Paint 8 15-Aug-12 26-Aug-12 01-Nov-12 10-Nov-12 63 Fisrt StaFisrt Stage Finishes 14 04-Dec-12 19-Dec-12 17-Feb-13 19-Mar-13 75 A57320 Installation of Suspended Ceiling Grid 5 04-Dec-12 09-Dec-12 17-Feb-13 21-Feb-13 62 A57330 Suspended Ceiling Tiles 5 10-Dec-12 15-Dec-12 23-Feb-13 27-Feb-13 62 A57570 Screed Works 2 16-Dec-12 17-Dec-12 16-Mar-13 17-Mar-13 75 A57350 Floor Tiles Work 2 18-Dec-12 19-Dec-12 18-Mar-13 19-Mar-13 75 Second SSecond Stage Finishes 6 20-Dec-12 26-Dec-12 20-Mar-13 28-Apr-13 103 A57360 Installation of Windows&Doors 2 20-Dec-12 22-Dec-12 20-Mar-13 21-Mar-13 75 A57380 Doors Ironmongery 2 20-Dec-12 22-Dec-12 27-Apr-13 28-Apr-13 107 A57340 Final Coat Paint 3 24-Dec-12 26-Dec-12 23-Apr-13 25-Apr-13 101 Final StaFinal Stage Finishes 2 27-Dec-12 29-Dec-12 27-Apr-13 28-Apr-13 101 A57560 Installation of Sinages 2 27-Dec-12 29-Dec-12 27-Apr-13 28-Apr-13 101 MEP WorkMEP Works 120 30-Jul-12 23-Dec-12 14-Oct-12 22-Apr-13 101 HVACHVAC 116 30-Jul-12 18-Dec-12 04-Feb-13 05-Mar-13 64 A57410 Chilled Water Pipe Installation & Insulation 7 30-Jul-12 06-Aug-12 04-Feb-13 11-Feb-13 154 A57420 Condensate Pipe Installation 7 30-Jul-12 06-Aug-12 04-Feb-13 11-Feb-13 154 A57430 FCU Installation 4 07-Aug-12 11-Aug-12 12-Feb-13 16-Feb-13 154 A57440 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 ElectricalElectrical 118 30-Jul-12 20-Dec-12 14-Oct-12 05-Mar-13 62 A57450 Install Conduits in Wall 4 30-Jul-12 02-Aug-12 14-Oct-12 17-Oct-12 63 A57470 Wiring for Lighting & Power 4 15-Aug-12 21-Aug-12 12-Feb-13 16-Feb-13 147 A105450 Installation of Server System 80 28-Aug-12 03-Dec-12 11-Nov-12 16-Feb-13 62 A57510 Installation of Lighting Fittings 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62 Fire FighFire Fighting 7 16-Dec-12 23-Dec-12 15-Apr-13 22-Apr-13 101 A57580 Fire Alarm Devices 7 16-Dec-12 23-Dec-12 15-Apr-13 22-Apr-13 101 Sub-StatioSub-Station 2 129 23-Jul-12 26-Dec-12 06-Jan-13 28-Apr-13 103 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 30 23-Jul-12 28-Aug-12 06-Jan-13 19-Mar-13 168 A56120 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136 A56080 Installation of Doors& Windows Sub-frame 2 05-Aug-12 06-Aug-12 18-Mar-13 19-Mar-13 185 A56070 Plaster Works 5 05-Aug-12 09-Aug-12 20-Jan-13 26-Jan-13 137 A56090 1st Coat Paint 9 16-Aug-12 28-Aug-12 02-Feb-13 11-Feb-13 137 Fisrt StaFisrt Stage Finishes 34 07-Aug-12 17-Sep-12 28-Feb-13 25-Apr-13 183 A56110 Installation of Doors 2 07-Aug-12 08-Aug-12 20-Mar-13 21-Mar-13 185 A56130 Doors Ironmongery 2 07-Aug-12 08-Aug-12 24-Apr-13 25-Apr-13 215 A56180 Epoxy Paint Works 3 15-Sep-12 17-Sep-12 28-Feb-13 03-Mar-13 137 Second SSecond Stage Finishes 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137 A56100 Final Coat Paint 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A56170 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71 HVACHVAC 31 30-Jul-12 05-Sep-12 20-Feb-13 27-Feb-13 144 A56200 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168 A56240 Air-Outlet Installation 7 29-Aug-12 05-Sep-12 20-Feb-13 27-Feb-13 144 ElectricalElectrical 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71 LightLight 29 30-Jul-12 03-Sep-12 14-Jan-13 27-Feb-13 146 A56140 Install Conduits in Wall 5 30-Jul-12 04-Aug-12 14-Jan-13 19-Jan-13 137 A56150 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 27-Jan-13 31-Jan-13 137 A56160 Installation of Lighting Fittings 5 29-Aug-12 03-Sep-12 23-Feb-13 27-Feb-13 146 TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71 A105260 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71 A105250 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87 A105270 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 A105280 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 A105290 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A105310 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A105300 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 A105320 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 Fire FighFire Fighting 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137 A56190 Fire Alarm Devices 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137 Sub-StatioSub-Station 3 129 23-Jul-12 26-Dec-12 06-Jan-13 28-Apr-13 103 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 06-Jan-13 28-Apr-13 161 Wet WorWet Works 30 23-Jul-12 28-Aug-12 06-Jan-13 19-Mar-13 168 A56300 Block Works 6 23-Jul-12 29-Jul-12 06-Jan-13 12-Jan-13 136 A56260 Installation of Doors& Windows Sub-frame 2 05-Aug-12 06-Aug-12 18-Mar-13 19-Mar-13 185 A56250 Plaster Works 5 05-Aug-12 09-Aug-12 20-Jan-13 26-Jan-13 137 A56270 1st Coat Paint 9 16-Aug-12 28-Aug-12 02-Feb-13 11-Feb-13 137 Fisrt StaFisrt Stage Finishes 34 07-Aug-12 17-Sep-12 28-Feb-13 25-Apr-13 183 A56290 Installation of Doors 2 07-Aug-12 08-Aug-12 20-Mar-13 21-Mar-13 185 A56310 Doors Ironmongery 2 07-Aug-12 08-Aug-12 24-Apr-13 25-Apr-13 215 A56360 Epoxy Paint Works 3 15-Sep-12 17-Sep-12 28-Feb-13 03-Mar-13 137 Second SSecond Stage Finishes 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137 A56280 Final Coat Paint 4 18-Sep-12 22-Sep-12 04-Mar-13 07-Mar-13 137 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A56350 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71 HVACHVAC 31 30-Jul-12 05-Sep-12 20-Feb-13 27-Feb-13 144 A56380 Duct Installation & Insulation 7 30-Jul-12 06-Aug-12 20-Feb-13 27-Feb-13 168 A56390 Air-Outlet Installation 7 29-Aug-12 05-Sep-12 20-Feb-13 27-Feb-13 144 ElectricalElectrical 123 30-Jul-12 26-Dec-12 14-Jan-13 21-Mar-13 71 LightLight 29 30-Jul-12 03-Sep-12 14-Jan-13 27-Feb-13 146 A56320 Install Conduits in Wall 5 30-Jul-12 04-Aug-12 14-Jan-13 19-Jan-13 137 A56330 Wiring for Lighting & Power 5 11-Aug-12 15-Aug-12 27-Jan-13 31-Jan-13 137 A56340 Installation of Lighting Fittings 5 29-Aug-12 03-Sep-12 23-Feb-13 27-Feb-13 146 TransfoTransformer 28 24-Nov-12 26-Dec-12 18-Feb-13 21-Mar-13 71 A105340 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 18-Feb-13 23-Feb-13 71 A105330 Installation of Transformer 7 24-Nov-12 01-Dec-12 09-Mar-13 16-Mar-13 87 A105350 Install of LV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 A105360 Install of MV Cables 12 29-Nov-12 13-Dec-12 24-Feb-13 09-Mar-13 71 A105370 Test of LV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A105390 Test of MV Cables 6 15-Dec-12 20-Dec-12 10-Mar-13 16-Mar-13 71 A105380 Termination of LV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 A105400 Termination of MV Cables 5 22-Dec-12 26-Dec-12 17-Mar-13 21-Mar-13 71 Fire FighFire Fighting 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137 A56370 Fire Alarm Devices 14 29-Aug-12 13-Sep-12 12-Feb-13 27-Feb-13 137 Genset RoGenset Rooms 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 25-Dec-12 28-Apr-13 161 Wet WorWet Works 29 23-Jul-12 27-Aug-12 25-Dec-12 19-Mar-13 169 A57200 Block Works 4 23-Jul-12 26-Jul-12 25-Dec-12 29-Dec-12 127 A57160 Installation of Doors& Windows Sub-frame 1 01-Aug-12 01-Aug-12 19-Mar-13 19-Mar-13 189 A57150 Plaster Works 8 01-Aug-12 09-Aug-12 05-Jan-13 13-Jan-13 127 A57170 1st Coat Paint 9 15-Aug-12 27-Aug-12 19-Jan-13 29-Jan-13 127 Fisrt StaFisrt Stage Finishes 52 02-Aug-12 03-Oct-12 20-Mar-13 25-Apr-13 169 A57190 Installation of Doors 2 02-Aug-12 04-Aug-12 20-Mar-13 21-Mar-13 189 A57210 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 A57260 Epoxy Paint Works 2 02-Oct-12 03-Oct-12 20-Mar-13 21-Mar-13 139 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Server System Installation of Lighting Fittings Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Install Cable Tray & Trunking Installation of Transformer Install of LV Cables Install of MV Cables Test of LV Cables Test of MV Cables Termination of LV Cables Termination of MV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Install Cable Tray & Trunking Installation of Transformer Install of LV Cables Install of MV Cables Test of LV Cables Test of MV Cables Termination of LV Cables Termination of MV Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 58 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 59. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Second SSecond Stage Finishes 4 04-Oct-12 08-Oct-12 22-Apr-13 25-Apr-13 165 A57180 Final Coat Paint 4 04-Oct-12 08-Oct-12 22-Apr-13 25-Apr-13 165 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A57250 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 55 28-Jul-12 01-Oct-12 30-Dec-12 19-Mar-13 139 HVACHVAC 7 28-Jul-12 04-Aug-12 26-Feb-13 05-Mar-13 175 A57280 Duct Installation & Insulation 7 28-Jul-12 04-Aug-12 26-Feb-13 05-Mar-13 175 ElectricalElectrical 55 28-Jul-12 01-Oct-12 30-Dec-12 05-Mar-13 127 A57220 Install Conduits in Wall 4 28-Jul-12 31-Jul-12 30-Dec-12 03-Jan-13 127 A57230 Wiring for Lighting & Power 4 11-Aug-12 14-Aug-12 14-Jan-13 17-Jan-13 127 A57240 Installation of Lighting Fittings 7 28-Aug-12 04-Sep-12 26-Feb-13 05-Mar-13 150 A105420 Installation of Generator 30 28-Aug-12 01-Oct-12 30-Jan-13 05-Mar-13 127 Fire FighFire Fighting 7 28-Aug-12 04-Sep-12 12-Mar-13 19-Mar-13 162 A57270 Fire Alarm Devices 7 28-Aug-12 04-Sep-12 12-Mar-13 19-Mar-13 162 CBS RoomCBS Room 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 FinishingFinishing Works 71 23-Jul-12 15-Oct-12 09-Jan-13 28-Apr-13 161 Wet WorWet Works 25 23-Jul-12 22-Aug-12 09-Jan-13 19-Mar-13 173 A57060 Block Works 3 23-Jul-12 25-Jul-12 09-Jan-13 12-Jan-13 139 A57020 Installation of Doors& Windows Sub-frame 2 01-Aug-12 02-Aug-12 18-Mar-13 19-Mar-13 188 A57010 Plaster Works 6 01-Aug-12 07-Aug-12 29-Jan-13 04-Feb-13 147 A57030 1st Coat Paint 6 14-Aug-12 22-Aug-12 11-Feb-13 17-Feb-13 147 Fisrt StaFisrt Stage Finishes 36 04-Aug-12 16-Sep-12 20-Mar-13 25-Apr-13 184 A57050 Installation of Doors 2 04-Aug-12 05-Aug-12 20-Mar-13 21-Mar-13 188 A57120 Epoxy Paint Works 2 09-Sep-12 10-Sep-12 20-Mar-13 21-Mar-13 159 A57070 Doors Ironmongery 2 15-Sep-12 16-Sep-12 24-Apr-13 25-Apr-13 184 Second SSecond Stage Finishes 2 11-Sep-12 12-Sep-12 24-Apr-13 25-Apr-13 187 A57040 Final Coat Paint 2 11-Sep-12 12-Sep-12 24-Apr-13 25-Apr-13 187 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 A57110 Installation of Sinages 2 14-Oct-12 15-Oct-12 27-Apr-13 28-Apr-13 161 MEP WorkMEP Works 36 26-Jul-12 08-Sep-12 22-Jan-13 19-Mar-13 159 HVACHVAC 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 A57140 Air-Outlet Installation 7 23-Aug-12 30-Aug-12 26-Feb-13 05-Mar-13 154 ElectricalElectrical 36 26-Jul-12 08-Sep-12 22-Jan-13 05-Mar-13 147 A57080 Install Conduits in Wall 5 26-Jul-12 31-Jul-12 22-Jan-13 28-Jan-13 147 A57090 Wiring for Lighting & Power 5 08-Aug-12 13-Aug-12 05-Feb-13 10-Feb-13 147 A57100 Installation of Lighting Fittings 5 23-Aug-12 28-Aug-12 28-Feb-13 05-Mar-13 156 A105430 Instalaltion of Centeral Bettery System 14 23-Aug-12 08-Sep-12 18-Feb-13 05-Mar-13 147 Fire FighFire Fighting 5 23-Aug-12 28-Aug-12 14-Mar-13 19-Mar-13 168 A57130 Fire Alarm Devices 5 23-Aug-12 28-Aug-12 14-Mar-13 19-Mar-13 168 CCTV ConCCTV Control Room 132 23-Jul-12 30-Dec-12 04-Oct-12 28-Apr-13 100 FinishingFinishing Works 132 23-Jul-12 30-Dec-12 04-Oct-12 28-Apr-13 100 Wet WorWet Works 29 23-Jul-12 27-Aug-12 04-Oct-12 19-Mar-13 169 A57670 Block Works 5 23-Jul-12 28-Jul-12 04-Oct-12 09-Oct-12 61 A57600 Installation of Doors& Windows Sub-frame 2 06-Aug-12 07-Aug-12 18-Mar-13 19-Mar-13 184 A57590 Plaster Works 10 06-Aug-12 16-Aug-12 18-Oct-12 31-Oct-12 61 A57610 1st Coat Paint 7 18-Aug-12 27-Aug-12 01-Nov-12 08-Nov-12 61 Fisrt StaFisrt Stage Finishes 18 04-Dec-12 24-Dec-12 16-Feb-13 19-Mar-13 71 A57620 Installation of Suspended Ceiling Grid 4 04-Dec-12 08-Dec-12 16-Feb-13 19-Feb-13 61 A57630 Suspended Ceiling Tiles 5 09-Dec-12 13-Dec-12 20-Feb-13 25-Feb-13 61 A57650 Epoxy Paint Works 2 23-Dec-12 24-Dec-12 18-Mar-13 19-Mar-13 71 Second SSecond Stage Finishes 3 25-Dec-12 27-Dec-12 20-Mar-13 28-Apr-13 102 A57660 Installation of Windows&Doors 2 25-Dec-12 26-Dec-12 20-Mar-13 21-Mar-13 71 A57680 Doors Ironmongery 2 25-Dec-12 26-Dec-12 27-Apr-13 28-Apr-13 103 A57640 Final Coat Paint 3 25-Dec-12 27-Dec-12 23-Apr-13 25-Apr-13 100 Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 A57860 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 MEP WorkMEP Works 120 29-Jul-12 22-Dec-12 10-Oct-12 17-Mar-13 71 HVACHVAC 7 28-Aug-12 04-Sep-12 07-Feb-13 14-Feb-13 134 A57730 FCU Installation 7 28-Aug-12 04-Sep-12 07-Feb-13 14-Feb-13 134 ElectricalElectrical 120 29-Jul-12 22-Dec-12 10-Oct-12 05-Mar-13 61 A57750 Install Conduits in Wall 7 29-Jul-12 05-Aug-12 10-Oct-12 17-Oct-12 61 A57770 Wiring for Lighting & Power 7 18-Aug-12 27-Aug-12 07-Feb-13 14-Feb-13 141 A124640 Installation of UPS 15 28-Aug-12 13-Sep-12 29-Jan-13 14-Feb-13 126 A57820 Installation of CCTV System 80 28-Aug-12 03-Dec-12 10-Nov-12 14-Feb-13 61 A57810 Installation of Lighting Fittings 7 15-Dec-12 22-Dec-12 26-Feb-13 05-Mar-13 61 Fire FighFire Fighting 7 15-Dec-12 22-Dec-12 10-Mar-13 17-Mar-13 71 A57880 Fire Alarm Devices 7 15-Dec-12 22-Dec-12 10-Mar-13 17-Mar-13 71 StaircaseStaircase 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152 Stairs 1Stairs 1 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152 A109450 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132 A109460 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132 A109470 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109480 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109490 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132 A109500 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152 Stairs 2Stairs 2 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152 A109510 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132 A109520 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132 A109530 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109540 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109550 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132 A109560 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152 Stairs 3Stairs 3 43 06-Sep-12 28-Oct-12 14-Feb-13 28-Apr-13 152 A109570 Floor Screed 3 06-Sep-12 09-Sep-12 14-Feb-13 17-Feb-13 132 A109580 Install Handrails 4 10-Sep-12 13-Sep-12 18-Feb-13 21-Feb-13 132 A109590 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109600 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 23-Feb-13 07-Mar-13 132 A109610 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 09-Mar-13 21-Mar-13 132 A109620 Final Coat Paint 12 13-Oct-12 28-Oct-12 15-Apr-13 28-Apr-13 152 Ground FloorGround Floor 323 16-Aug-12 08-Sep-13 24-Oct-12 02-Oct-13 21 Public AreaPublic Area 323 16-Aug-12 08-Sep-13 24-Oct-12 02-Oct-13 21 ParkingParking 69 25-Dec-12 17-Mar-13 04-Feb-13 28-Apr-13 36 FinishingFinishing Works 69 25-Dec-12 17-Mar-13 18-Feb-13 28-Apr-13 36 Wet WorWet Works 24 25-Dec-12 22-Jan-13 18-Feb-13 03-Mar-13 33 A66730 Plaster Works 5 25-Dec-12 30-Dec-12 18-Feb-13 23-Feb-13 45 A66740 1st Coat Paint 7 15-Jan-13 22-Jan-13 24-Feb-13 03-Mar-13 33 Traffic DTraffic Deck Coating 45 23-Jan-13 17-Mar-13 04-Mar-13 28-Apr-13 36 A116040 Installation of Kerbs 8 23-Jan-13 02-Feb-13 04-Mar-13 12-Mar-13 33 A116050 Installation of Interlocking Tiles 8 03-Feb-13 11-Feb-13 13-Mar-13 21-Mar-13 33 A66670 Surface Preparation (including Grinding & Repairing) 8 12-Feb-13 20-Feb-13 23-Mar-13 31-Mar-13 33 A66680 Application of 1st Coat 5 18-Feb-13 23-Feb-13 01-Apr-13 06-Apr-13 36 A66720 Application of Final Coat 5 24-Feb-13 28-Feb-13 07-Apr-13 11-Apr-13 36 A66700 Road Marking & Arrows 7 02-Mar-13 09-Mar-13 13-Apr-13 20-Apr-13 36 A116060 Installation of Speed Hump 7 10-Mar-13 17-Mar-13 21-Apr-13 28-Apr-13 36 Final StaFinal Stage Finishes 7 10-Mar-13 17-Mar-13 21-Apr-13 28-Apr-13 36 A66750 Final Coat Paint 5 10-Mar-13 14-Mar-13 21-Apr-13 25-Apr-13 36 A66770 Installation of Sinages 2 16-Mar-13 17-Mar-13 27-Apr-13 28-Apr-13 36 MEP WorkMEP Works 17 25-Dec-12 14-Jan-13 04-Feb-13 23-Feb-13 33 HVACHVAC 17 25-Dec-12 14-Jan-13 04-Feb-13 23-Feb-13 33 A66900 Duct Installation & Insulation 7 25-Dec-12 02-Jan-13 04-Feb-13 11-Feb-13 33 A66870 Installation of Plenum Boxes 10 03-Jan-13 14-Jan-13 12-Feb-13 23-Feb-13 33 ElectricalElectrical 14 25-Dec-12 10-Jan-13 07-Feb-13 23-Feb-13 36 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Final Coat Paint Installation of Sinages Duct Installation & Insulation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of Generator Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Instalaltion of Centeral Bettery System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Epoxy Paint Works Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages FCU Installation Install Conduits in Wall Wiring for Lighting & Power Installation of UPS Installation of CCTV System Installation of Lighting Fittings Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Duct Installation & Insulation Installation of Plenum Boxes Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 59 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 60. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A116070 Instalaltion of Cable Trays 5 25-Dec-12 30-Dec-12 07-Feb-13 12-Feb-13 36 A116080 Instalaltion of Bus Bars 7 25-Dec-12 02-Jan-13 11-Feb-13 18-Feb-13 39 A116090 Cable Pulling 5 31-Dec-12 06-Jan-13 13-Feb-13 18-Feb-13 36 A66760 Installation of Lighting Fittings 4 07-Jan-13 10-Jan-13 19-Feb-13 23-Feb-13 36 PlumbingPlumbing 7 25-Dec-12 02-Jan-13 16-Feb-13 23-Feb-13 43 A66840 H/L Hot&Cold Water Pipe Installation 4 25-Dec-12 29-Dec-12 16-Feb-13 19-Feb-13 43 A66860 Floor Drain Fixning 4 25-Dec-12 29-Dec-12 19-Feb-13 23-Feb-13 46 A66880 H/L Drainage Pipes Installation 4 25-Dec-12 29-Dec-12 16-Feb-13 19-Feb-13 43 A66850 Water Pipes Testing 3 30-Dec-12 02-Jan-13 20-Feb-13 23-Feb-13 43 A66890 Drainage&Water Pipes Testing 3 30-Dec-12 02-Jan-13 20-Feb-13 23-Feb-13 43 Fire FighFire Fighting 14 25-Dec-12 10-Jan-13 07-Feb-13 23-Feb-13 36 A66830 Fire Fighting Pipe 4 25-Dec-12 29-Dec-12 07-Feb-13 11-Feb-13 36 A66820 Hydro Static Test for Pipes 4 30-Dec-12 03-Jan-13 12-Feb-13 16-Feb-13 36 A66810 Sprinkler Fixing 4 05-Jan-13 08-Jan-13 17-Feb-13 20-Feb-13 36 A66780 Fire Alarm Devices 2 09-Jan-13 10-Jan-13 21-Feb-13 23-Feb-13 36 RampRamp 67 31-Dec-12 20-Mar-13 03-Mar-13 28-Apr-13 33 A116100 Install Handrail 7 31-Dec-12 08-Jan-13 03-Mar-13 10-Mar-13 51 A116110 1st Coat Paint 10 12-Jan-13 22-Jan-13 11-Mar-13 21-Mar-13 49 A116120 Surface Preparation (including Grinding & Repairing) 8 12-Feb-13 20-Feb-13 23-Mar-13 31-Mar-13 33 A116130 Application of 1st Coat 5 21-Feb-13 26-Feb-13 01-Apr-13 06-Apr-13 33 A116140 Application of Final Coat 5 27-Feb-13 04-Mar-13 07-Apr-13 11-Apr-13 33 A116150 Road Marking & Arrows 7 05-Mar-13 12-Mar-13 13-Apr-13 20-Apr-13 33 A116160 Final Coat Paint 7 13-Mar-13 20-Mar-13 21-Apr-13 28-Apr-13 33 Lift LobbyLift Lobby - Corridor 323 16-Aug-12 08-Sep-13 02-Jan-13 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 02-Jan-13 02-Oct-13 21 Wet WorWet Works 40 16-Aug-12 03-Oct-12 02-Jan-13 25-Apr-13 169 A66430 Block Works 7 16-Aug-12 26-Aug-12 02-Jan-13 09-Jan-13 112 A66360 Installation of Doors& Windows Sub-frame 2 04-Sep-12 05-Sep-12 24-Apr-13 25-Apr-13 193 A66350 Plaster Works 7 04-Sep-12 11-Sep-12 19-Jan-13 27-Jan-13 112 A66380 Installation of Suspended Ceiling Grid 7 19-Sep-12 26-Sep-12 04-Feb-13 11-Feb-13 112 A66370 1st Coat Paint 6 27-Sep-12 03-Oct-12 12-Feb-13 18-Feb-13 112 Fisrt StaFisrt Stage Finishes 16 04-Oct-12 22-Oct-12 19-Feb-13 13-Apr-13 142 A66390 Suspended Ceiling Tiles 6 04-Oct-12 10-Oct-12 19-Feb-13 25-Feb-13 112 A66610 Screed Works 3 11-Oct-12 14-Oct-12 02-Apr-13 04-Apr-13 142 A66410 Floor Tiles Work 7 15-Oct-12 22-Oct-12 06-Apr-13 13-Apr-13 142 Second SSecond Stage Finishes 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153 A66420 Installation of Windows&Doors 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153 A66440 Doors Ironmongery 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153 Final StaFinal Stage Finishes 267 23-Oct-12 08-Sep-13 14-Apr-13 02-Oct-13 21 A66400 Final Coat Paint 6 23-Oct-12 31-Oct-12 14-Apr-13 20-Apr-13 142 A66600 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A66630 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A66450 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 48 27-Aug-12 21-Oct-12 10-Jan-13 20-Apr-13 149 HVACHVAC 46 27-Aug-12 18-Oct-12 22-Jan-13 05-Mar-13 112 A66640 Chilled Water Pipe Installation & Insulation 5 27-Aug-12 01-Sep-12 22-Jan-13 28-Jan-13 122 A66650 Condensate Pipe Installation 5 27-Aug-12 01-Sep-12 22-Jan-13 28-Jan-13 122 A66460 Duct Installation & Insulation 7 27-Aug-12 03-Sep-12 18-Feb-13 25-Feb-13 144 A66660 FCU Installation 5 02-Sep-12 06-Sep-12 29-Jan-13 03-Feb-13 122 A66470 Air-Outlet Installation 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112 ElectricalElectrical 46 27-Aug-12 18-Oct-12 10-Jan-13 05-Mar-13 112 A66480 Install Conduits in Wall 7 27-Aug-12 03-Sep-12 10-Jan-13 17-Jan-13 112 A66490 Install Cable Trays & Trunking 7 27-Aug-12 03-Sep-12 16-Jan-13 23-Jan-13 117 A66520 Cable Laying for Low Current System 7 04-Sep-12 11-Sep-12 04-Feb-13 11-Feb-13 125 A66530 Cable Laying for Power 7 04-Sep-12 11-Sep-12 04-Feb-13 11-Feb-13 125 A66500 Wiring for Lighting & Power 6 12-Sep-12 18-Sep-12 28-Jan-13 03-Feb-13 112 A66510 Wiring for Low Current System 6 12-Sep-12 18-Sep-12 28-Jan-13 03-Feb-13 112 A66550 Installation of Sockets 5 11-Oct-12 16-Oct-12 28-Feb-13 05-Mar-13 114 A66540 Installation of Lighting Fittings 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112 Fire FighFire Fighting 48 27-Aug-12 21-Oct-12 20-Jan-13 20-Apr-13 149 A66590 Fire Fighting Pipe 7 27-Aug-12 03-Sep-12 20-Jan-13 28-Jan-13 120 A66580 Hydro Static Test for Pipes 5 04-Sep-12 09-Sep-12 29-Jan-13 03-Feb-13 120 A66570 Sprinkler Fixing 7 11-Oct-12 18-Oct-12 26-Feb-13 05-Mar-13 112 A66620 Fire Alarm Devices 7 11-Oct-12 18-Oct-12 06-Apr-13 13-Apr-13 145 A66560 Installation of Fire Extingusher&Blanket 2 20-Oct-12 21-Oct-12 18-Apr-13 20-Apr-13 149 Kitchen ArKitchen Area 323 16-Aug-12 08-Sep-13 18-Nov-12 02-Oct-13 21 KitchenKitchen 96 31-Oct-12 24-Feb-13 18-Nov-12 28-Apr-13 54 FinishingFinishing Works 61 13-Dec-12 24-Feb-13 30-Dec-12 28-Apr-13 54 Wet WoWet Works 32 13-Dec-12 20-Jan-13 30-Dec-12 20-Apr-13 76 A61270 Block Works 10 13-Dec-12 24-Dec-12 30-Dec-12 10-Jan-13 14 A61230 Installation of Doors& Windows Sub-frame 3 03-Jan-13 06-Jan-13 17-Apr-13 20-Apr-13 88 A61220 Plaster Works 10 03-Jan-13 14-Jan-13 20-Jan-13 31-Jan-13 14 A61510 Wall Tiles Work 5 15-Jan-13 20-Jan-13 02-Feb-13 06-Feb-13 14 Fisrt StaFisrt Stage Finishes 4 21-Jan-13 26-Jan-13 07-Feb-13 11-Feb-13 14 A61500 Screed Works 4 21-Jan-13 26-Jan-13 07-Feb-13 11-Feb-13 14 SecondSecond Stage Finishes 18 27-Jan-13 16-Feb-13 12-Feb-13 20-Apr-13 54 A61540 Installation of Suspended Ceiling Grid 9 27-Jan-13 05-Feb-13 12-Feb-13 21-Feb-13 14 A61530 Suspended Ceiling Tiles 7 02-Feb-13 09-Feb-13 18-Feb-13 25-Feb-13 14 A61520 Floor Tiles Work 6 10-Feb-13 16-Feb-13 14-Apr-13 20-Apr-13 54 Final StFinal Stage Finishes 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54 A61240 Final Coat Paint 2 18-Feb-13 19-Feb-13 24-Apr-13 25-Apr-13 56 A61260 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54 A61280 Doors Ironmongery 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54 A61490 Installation of Sinages 2 23-Feb-13 24-Feb-13 27-Apr-13 28-Apr-13 54 MEP WoMEP Works 90 31-Oct-12 17-Feb-13 18-Nov-12 24-Apr-13 57 HVACHVAC 45 25-Dec-12 17-Feb-13 22-Jan-13 05-Mar-13 14 A61290 Duct Installation & Insulation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23 A61300 Chilled Water Pipe Installation & Insulation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23 A61310 Condensate Pipe Installation 10 25-Dec-12 06-Jan-13 22-Jan-13 03-Feb-13 23 A61320 FCU Installation 7 07-Jan-13 14-Jan-13 04-Feb-13 11-Feb-13 23 A61330 Air-Outlet Installation 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14 ElectricElectrical 50 19-Dec-12 17-Feb-13 12-Jan-13 05-Mar-13 14 A61340 Install Conduits in Wall 7 19-Dec-12 26-Dec-12 12-Jan-13 19-Jan-13 19 A61350 Wiring for Lighting & Power 7 15-Jan-13 22-Jan-13 04-Feb-13 11-Feb-13 16 A61360 Installation of Lighting Fittings 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14 PlumbinPlumbing 27 25-Dec-12 27-Jan-13 12-Jan-13 05-Mar-13 32 A61370 Drainge Pipes in Wall 7 25-Dec-12 02-Jan-13 12-Jan-13 19-Jan-13 14 A61380 H/L Drainage Pipes Installation 7 25-Dec-12 02-Jan-13 31-Jan-13 07-Feb-13 30 A61390 H/L Hot&Cold Water Pipe Installation 7 25-Dec-12 02-Jan-13 31-Jan-13 07-Feb-13 30 A61440 Water Pipes in Wall 7 25-Dec-12 02-Jan-13 12-Jan-13 19-Jan-13 14 A61400 Drainage&Water Pipes Testing 3 03-Jan-13 06-Jan-13 09-Feb-13 11-Feb-13 30 A61420 Floor Drain Fixning 3 23-Jan-13 27-Jan-13 03-Mar-13 05-Mar-13 32 Fire FigFire Fighting 45 25-Dec-12 17-Feb-13 30-Jan-13 24-Apr-13 57 A61480 Fire Fighting Pipe 7 25-Dec-12 02-Jan-13 30-Jan-13 06-Feb-13 29 A61470 Hydro Static Test for Pipes 4 03-Jan-13 07-Jan-13 07-Feb-13 11-Feb-13 29 A61450 Installation of Fire Extingusher&Blanket 2 16-Feb-13 17-Feb-13 23-Apr-13 24-Apr-13 57 A61460 Sprinkler Fixing 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14 A61550 Fire Alarm Devices 7 10-Feb-13 17-Feb-13 16-Apr-13 23-Apr-13 56 KitchenKitchen Equipments 75 31-Oct-12 30-Jan-13 18-Nov-12 16-Feb-13 14 A61430 Installation of Kitchen Equipments 75 31-Oct-12 30-Jan-13 18-Nov-12 16-Feb-13 14 Staff DininStaff Dining Area 323 16-Aug-12 08-Sep-13 10-Jan-13 02-Oct-13 21 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Instalaltion of Cable Trays Instalaltion of Bus Bars Cable Pulling Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Floor Drain Fixning H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Install Handrail 1st Coat Paint Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Carpets Installation of Furnitur Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work Screed Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Floor Tiles Work Final Coat Paint Installation of Windows&Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Installation of Kitchen Equipments Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 60 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 61. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float FinishingFinishing Works 323 16-Aug-12 08-Sep-13 10-Jan-13 02-Oct-13 21 Wet WoWet Works 35 16-Aug-12 27-Sep-12 10-Jan-13 04-Apr-13 156 A62750 Block Works 8 16-Aug-12 27-Aug-12 10-Jan-13 19-Jan-13 119 A62640 Installation of Doors& Windows Sub-frame 2 03-Sep-12 04-Sep-12 03-Apr-13 04-Apr-13 176 A62630 Plaster Works 8 03-Sep-12 11-Sep-12 27-Jan-13 04-Feb-13 119 A62660 Installation of Suspended Ceiling Grid 4 17-Sep-12 20-Sep-12 10-Feb-13 13-Feb-13 119 A62650 1st Coat Paint 6 22-Sep-12 27-Sep-12 14-Feb-13 20-Feb-13 119 Fisrt StaFisrt Stage Finishes 10 29-Sep-12 09-Oct-12 21-Feb-13 04-Apr-13 146 A62670 Suspended Ceiling Tiles 4 29-Sep-12 02-Oct-12 21-Feb-13 25-Feb-13 119 A63050 Screed Works 2 03-Oct-12 04-Oct-12 02-Mar-13 03-Mar-13 122 A62690 Floor Tiles Work 4 06-Oct-12 09-Oct-12 01-Apr-13 04-Apr-13 146 SecondSecond Stage Finishes 2 23-Oct-12 24-Oct-12 06-Apr-13 28-Apr-13 153 A62720 Installation of Windows&Doors 2 23-Oct-12 24-Oct-12 06-Apr-13 07-Apr-13 135 A62760 Doors Ironmongery 2 23-Oct-12 24-Oct-12 27-Apr-13 28-Apr-13 153 Final StFinal Stage Finishes 258 05-Nov-12 08-Sep-13 16-Apr-13 02-Oct-13 21 A62680 Final Coat Paint 4 05-Nov-12 08-Nov-12 16-Apr-13 20-Apr-13 135 A63040 Installation of Sinages 7 10-Nov-12 18-Nov-12 21-Apr-13 28-Apr-13 135 A62770 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WoMEP Works 57 28-Aug-12 04-Nov-12 20-Jan-13 20-Apr-13 139 HVACHVAC 37 28-Aug-12 09-Oct-12 31-Jan-13 05-Mar-13 120 A62780 Duct Installation & Insulation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128 A62790 Chilled Water Pipe Installation & Insulation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128 A62800 Condensate Pipe Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128 A62810 FCU Installation 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128 A62820 Air-Outlet Installation 6 03-Oct-12 09-Oct-12 27-Feb-13 05-Mar-13 120 ElectricElectrical 37 28-Aug-12 09-Oct-12 20-Jan-13 05-Mar-13 120 A62830 Install Conduits in Wall 5 28-Aug-12 02-Sep-12 20-Jan-13 26-Jan-13 119 A62840 Install Cable Trays & Trunking 5 28-Aug-12 02-Sep-12 28-Jan-13 02-Feb-13 125 A62870 Cable Laying for Low Current System 5 03-Sep-12 08-Sep-12 09-Feb-13 13-Feb-13 130 A62880 Cable Laying for Power 5 03-Sep-12 08-Sep-12 09-Feb-13 13-Feb-13 130 A62850 Wiring for Lighting & Power 4 12-Sep-12 16-Sep-12 05-Feb-13 09-Feb-13 119 A62860 Wiring for Low Current System 4 12-Sep-12 16-Sep-12 05-Feb-13 09-Feb-13 119 A62900 Installation of Sockets 4 03-Oct-12 07-Oct-12 02-Mar-13 05-Mar-13 122 A62890 Installation of Lighting Fittings 6 03-Oct-12 09-Oct-12 27-Feb-13 05-Mar-13 120 PlumbinPlumbing 57 28-Aug-12 04-Nov-12 21-Jan-13 15-Apr-13 135 A62910 Drainge Pipes in Wall 4 28-Aug-12 01-Sep-12 21-Jan-13 26-Jan-13 120 A62980 Water Pipes in Wall 4 28-Aug-12 01-Sep-12 21-Jan-13 26-Jan-13 120 A62920 H/L Drainage Pipes Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128 A62930 H/L Hot&Cold Water Pipe Installation 5 28-Aug-12 02-Sep-12 31-Jan-13 05-Feb-13 128 A62940 Drainage&Water Pipes Testing 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128 A62950 ElectricalWater Heater Installation 3 03-Sep-12 05-Sep-12 06-Feb-13 09-Feb-13 128 A62960 Floor Drain Fixning 2 06-Oct-12 07-Oct-12 04-Mar-13 05-Mar-13 122 A62970 Installation of Sanitaryware 7 28-Oct-12 04-Nov-12 08-Apr-13 15-Apr-13 135 Fire FigFire Fighting 40 28-Aug-12 13-Oct-12 29-Jan-13 20-Apr-13 156 A63020 Fire Fighting Pipe 6 28-Aug-12 03-Sep-12 29-Jan-13 04-Feb-13 126 A63010 Hydro Static Test for Pipes 4 04-Sep-12 08-Sep-12 05-Feb-13 09-Feb-13 126 A63000 Sprinkler Fixing 7 03-Oct-12 10-Oct-12 26-Feb-13 05-Mar-13 119 A63100 Fire Alarm Devices 7 03-Oct-12 10-Oct-12 08-Apr-13 15-Apr-13 154 A62990 Installation of Fire Extingusher&Blanket 2 11-Oct-12 13-Oct-12 18-Apr-13 20-Apr-13 156 Lobby ToliLobby Toliets 81 16-Aug-12 24-Nov-12 31-Dec-12 28-Apr-13 130 FinishingFinishing Works 81 16-Aug-12 24-Nov-12 31-Dec-12 28-Apr-13 130 Wet WorWet Works 30 16-Aug-12 22-Sep-12 31-Dec-12 11-Apr-13 167 A65740 Block Works 9 16-Aug-12 28-Aug-12 31-Dec-12 10-Jan-13 111 A65680 Installation of Doors& Windows Sub-frame 3 03-Sep-12 05-Sep-12 09-Apr-13 11-Apr-13 181 A65670 Plaster Works 8 03-Sep-12 11-Sep-12 16-Jan-13 26-Jan-13 111 A65990 Wall Tiles Work (Wet Area) 9 12-Sep-12 22-Sep-12 27-Jan-13 05-Feb-13 111 Fisrt StaFisrt Stage Finishes 22 23-Sep-12 17-Oct-12 06-Feb-13 11-Apr-13 145 A65980 Screed Works 3 23-Sep-12 25-Sep-12 06-Feb-13 09-Feb-13 111 A65700 Water Proofing for Wet Area 4 26-Sep-12 30-Sep-12 10-Feb-13 13-Feb-13 111 A66020 Installation of Suspended Ceiling Grid (Wet Area) 5 01-Oct-12 06-Oct-12 14-Feb-13 19-Feb-13 111 A66010 Suspended Ceiling Tiles (Wet Area) 5 07-Oct-12 11-Oct-12 20-Feb-13 25-Feb-13 111 A66000 Floor Tiles Work (Wet Area) 5 13-Oct-12 17-Oct-12 07-Apr-13 11-Apr-13 145 Second SSecond Stage Finishes 21 23-Oct-12 19-Nov-12 13-Apr-13 28-Apr-13 134 A65710 Installation of Windows&Doors 3 23-Oct-12 28-Oct-12 13-Apr-13 15-Apr-13 141 A65750 Doors Ironmongery 3 23-Oct-12 28-Oct-12 25-Apr-13 28-Apr-13 152 A65960 Installation of Toliets Accessories 5 29-Oct-12 03-Nov-12 18-Apr-13 23-Apr-13 143 A65720 Installation of Mirrors 7 29-Oct-12 05-Nov-12 16-Apr-13 23-Apr-13 141 A65730 Installation of Vanity Counter 4 14-Nov-12 19-Nov-12 20-Apr-13 23-Apr-13 130 Final StaFinal Stage Finishes 4 20-Nov-12 24-Nov-12 24-Apr-13 28-Apr-13 130 A65690 Final Coat Paint 2 20-Nov-12 21-Nov-12 24-Apr-13 25-Apr-13 130 A65970 Installation of Sinages 2 22-Nov-12 24-Nov-12 27-Apr-13 28-Apr-13 130 MEP WorkMEP Works 53 29-Aug-12 31-Oct-12 12-Jan-13 23-Apr-13 145 HVACHVAC 45 29-Aug-12 20-Oct-12 06-Feb-13 05-Mar-13 111 A65760 Duct Installation & Insulation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65770 Chilled Water Pipe Installation & Insulation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65780 Condensate Pipe Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65790 FCU Installation 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132 A65800 Air-Outlet Installation 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111 ElectricalElectrical 43 29-Aug-12 17-Oct-12 12-Jan-13 05-Mar-13 113 A65810 Install Conduits in Wall 4 29-Aug-12 02-Sep-12 12-Jan-13 15-Jan-13 111 A65820 Wiring for Lighting & Power 4 12-Sep-12 16-Sep-12 10-Feb-13 13-Feb-13 123 A65830 Installation of Lighting Fittings 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113 PlumbingPlumbing 53 29-Aug-12 31-Oct-12 13-Jan-13 23-Apr-13 145 A65840 Drainge Pipes in Wall 3 29-Aug-12 01-Sep-12 13-Jan-13 15-Jan-13 112 A65910 Water Pipes in Wall 3 29-Aug-12 01-Sep-12 13-Jan-13 15-Jan-13 112 A65850 H/L Drainage Pipes Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65860 H/L Hot&Cold Water Pipe Installation 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65880 ElectricalWater Heater Installation 2 03-Sep-12 04-Sep-12 12-Feb-13 13-Feb-13 133 A65870 Drainage&Water Pipes Testing 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132 A65890 Floor Drain Fixning 2 25-Sep-12 26-Sep-12 04-Mar-13 05-Mar-13 131 A65900 Installation of Sanitaryware 3 29-Oct-12 31-Oct-12 21-Apr-13 23-Apr-13 145 Fire FighFire Fighting 42 29-Aug-12 16-Oct-12 06-Feb-13 23-Apr-13 156 A65950 Fire Fighting Pipe 4 29-Aug-12 02-Sep-12 06-Feb-13 10-Feb-13 132 A65940 Hydro Static Test for Pipes 3 03-Sep-12 05-Sep-12 11-Feb-13 13-Feb-13 132 A65930 Sprinkler Fixing 3 13-Oct-12 15-Oct-12 03-Mar-13 05-Mar-13 115 A66030 Fire Alarm Devices 4 13-Oct-12 16-Oct-12 20-Apr-13 23-Apr-13 156 RestaurantRestaurant & Displayed Kitchen 323 16-Aug-12 08-Sep-13 15-Dec-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 15-Dec-12 02-Oct-13 21 Wet WorWet Works 46 16-Aug-12 10-Oct-12 15-Dec-12 07-Feb-13 97 A65380 Block Works 6 16-Aug-12 25-Aug-12 15-Dec-12 20-Dec-12 97 A65330 Plaster Works 9 03-Sep-12 12-Sep-12 30-Dec-12 09-Jan-13 97 A65350 Installation of Suspended Ceiling Grid 11 20-Sep-12 02-Oct-12 17-Jan-13 30-Jan-13 97 A65340 1st Coat Paint 7 03-Oct-12 10-Oct-12 31-Jan-13 07-Feb-13 97 Fisrt StaFisrt Stage Finishes 22 11-Oct-12 07-Nov-12 09-Feb-13 05-Mar-13 97 A65360 Suspended Ceiling Tiles 11 11-Oct-12 23-Oct-12 09-Feb-13 20-Feb-13 97 A65530 Screed Works 5 24-Oct-12 31-Oct-12 21-Feb-13 26-Feb-13 97 A65540 Wall Tiles Work 6 01-Nov-12 07-Nov-12 27-Feb-13 05-Mar-13 97 Second SSecond Stage Finishes 12 08-Nov-12 22-Nov-12 06-Mar-13 28-Apr-13 131 A65560 Floor Tiles Work 8 08-Nov-12 18-Nov-12 06-Mar-13 14-Mar-13 97 A65370 Installation of Doors 2 19-Nov-12 20-Nov-12 10-Apr-13 11-Apr-13 119 A65390 Doors Ironmongery 2 19-Nov-12 20-Nov-12 27-Apr-13 28-Apr-13 133 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Toliets Accessories Installation of Mirrors Installation of Vanity Counter Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation ElectricalWater Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 61 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 62. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A65570 Final Coat Paint 4 19-Nov-12 22-Nov-12 16-Mar-13 19-Mar-13 97 Final StaFinal Stage Finishes 243 24-Nov-12 08-Sep-13 20-Mar-13 02-Oct-13 21 A65580 Installation of Mirrors&Glass 7 24-Nov-12 01-Dec-12 10-Apr-13 17-Apr-13 115 A66120 Instllation of Displayed Kitchen 25 03-Dec-12 31-Dec-12 20-Mar-13 17-Apr-13 90 A65600 Installation of Carpets 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24 A65520 Installation of Sinages 2 30-Mar-13 31-Mar-13 27-Apr-13 28-Apr-13 24 A65590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 58 26-Aug-12 03-Nov-12 22-Dec-12 14-Mar-13 109 HVACHVAC 58 26-Aug-12 03-Nov-12 31-Dec-12 05-Mar-13 101 A65400 Duct Installation & Insulation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105 A65410 Chilled Water Pipe Installation & Insulation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105 A65420 Condensate Pipe Installation 7 26-Aug-12 02-Sep-12 31-Dec-12 08-Jan-13 105 A65430 FCU Installation 7 03-Sep-12 10-Sep-12 09-Jan-13 16-Jan-13 105 A65440 Air-Outlet Installation 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101 ElectricalElectrical 58 26-Aug-12 03-Nov-12 22-Dec-12 05-Mar-13 101 A65450 Install Conduits in Wall 7 26-Aug-12 02-Sep-12 22-Dec-12 29-Dec-12 97 A65460 Install Cable Trays & Trunking 7 26-Aug-12 02-Sep-12 30-Dec-12 07-Jan-13 104 A65490 Cable Laying for Low Current System 6 03-Sep-12 09-Sep-12 23-Jan-13 30-Jan-13 117 A65500 Cable Laying for Power 6 03-Sep-12 09-Sep-12 23-Jan-13 30-Jan-13 117 A65470 Wiring for Lighting & Power 6 13-Sep-12 19-Sep-12 10-Jan-13 16-Jan-13 97 A65480 Wiring for Low Current System 6 13-Sep-12 19-Sep-12 10-Jan-13 16-Jan-13 97 A65510 Installation of Lighting Fittings 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101 PlumbingPlumbing 11 26-Aug-12 06-Sep-12 05-Jan-13 16-Jan-13 108 A65610 H/L Drainage Pipes Installation 6 26-Aug-12 01-Sep-12 05-Jan-13 10-Jan-13 108 A65620 H/L Hot&Cold Water Pipe Installation 6 26-Aug-12 01-Sep-12 05-Jan-13 10-Jan-13 108 A65630 Drainage&Water Pipes Testing 5 02-Sep-12 06-Sep-12 12-Jan-13 16-Jan-13 108 Fire FighFire Fighting 58 26-Aug-12 03-Nov-12 03-Jan-13 14-Mar-13 109 A65640 Fire Fighting Pipe 7 26-Aug-12 02-Sep-12 03-Jan-13 10-Jan-13 107 A65650 Hydro Static Test for Pipes 5 03-Sep-12 08-Sep-12 12-Jan-13 16-Jan-13 107 A65550 Fire Alarm Devices 7 24-Oct-12 03-Nov-12 07-Mar-13 14-Mar-13 109 A65660 Sprinkler Fixing 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101 Coffe andCoffe and Baverage Bar (Lounge) 323 16-Aug-12 08-Sep-13 19-Dec-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 19-Dec-12 02-Oct-13 21 Wet WorWet Works 47 16-Aug-12 11-Oct-12 19-Dec-12 13-Feb-13 101 A66090 Block Works 9 16-Aug-12 28-Aug-12 19-Dec-12 29-Dec-12 101 A66040 Plaster Works 11 03-Sep-12 15-Sep-12 05-Jan-13 16-Jan-13 101 A66060 Installation of Suspended Ceiling Grid 10 20-Sep-12 01-Oct-12 22-Jan-13 03-Feb-13 101 A66050 1st Coat Paint 9 02-Oct-12 11-Oct-12 04-Feb-13 13-Feb-13 101 Fisrt StaFisrt Stage Finishes 23 13-Oct-12 10-Nov-12 14-Feb-13 20-Mar-13 108 A66070 Suspended Ceiling Tiles 10 13-Oct-12 23-Oct-12 14-Feb-13 25-Feb-13 101 A66240 Screed Works 4 24-Oct-12 30-Oct-12 06-Mar-13 10-Mar-13 108 A66250 Wall Tiles Work 9 31-Oct-12 10-Nov-12 11-Mar-13 20-Mar-13 108 Second SSecond Stage Finishes 17 11-Nov-12 01-Dec-12 21-Mar-13 28-Apr-13 124 A66270 Floor Tiles Work 10 11-Nov-12 22-Nov-12 21-Mar-13 01-Apr-13 108 A66080 Installation of Doors 2 24-Nov-12 25-Nov-12 10-Apr-13 11-Apr-13 115 A66100 Doors Ironmongery 2 24-Nov-12 25-Nov-12 27-Apr-13 28-Apr-13 129 A66280 Final Coat Paint 7 24-Nov-12 01-Dec-12 02-Apr-13 09-Apr-13 108 Final StaFinal Stage Finishes 236 03-Dec-12 08-Sep-13 10-Apr-13 02-Oct-13 21 A66290 Installation of Mirrors&Glass 7 03-Dec-12 10-Dec-12 10-Apr-13 17-Apr-13 108 A66310 Installation of Carpets 7 21-Mar-13 28-Mar-13 18-Apr-13 25-Apr-13 24 A66230 Installation of Sinages 2 30-Mar-13 31-Mar-13 27-Apr-13 28-Apr-13 24 A66300 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 55 29-Aug-12 03-Nov-12 30-Dec-12 01-Apr-13 124 HVACHVAC 55 29-Aug-12 03-Nov-12 16-Jan-13 05-Mar-13 101 A66110 Duct Installation & Insulation 5 29-Aug-12 03-Sep-12 16-Jan-13 21-Jan-13 115 A66150 Air-Outlet Installation 7 24-Oct-12 03-Nov-12 26-Feb-13 05-Mar-13 101 ElectricalElectrical 53 29-Aug-12 31-Oct-12 30-Dec-12 05-Mar-13 103 A66160 Install Conduits in Wall 4 29-Aug-12 02-Sep-12 30-Dec-12 03-Jan-13 101 A66170 Install Cable Trays & Trunking 4 29-Aug-12 02-Sep-12 10-Jan-13 14-Jan-13 110 A66200 Cable Laying for Low Current System 4 03-Sep-12 06-Sep-12 30-Jan-13 03-Feb-13 122 A66210 Cable Laying for Power 4 03-Sep-12 06-Sep-12 30-Jan-13 03-Feb-13 122 A66180 Wiring for Lighting & Power 4 16-Sep-12 19-Sep-12 17-Jan-13 21-Jan-13 101 A66190 Wiring for Low Current System 4 16-Sep-12 19-Sep-12 17-Jan-13 21-Jan-13 101 A66220 Installation of Lighting Fittings 5 24-Oct-12 31-Oct-12 28-Feb-13 05-Mar-13 103 PlumbingPlumbing 12 29-Aug-12 11-Sep-12 08-Jan-13 21-Jan-13 108 A66320 H/L Drainage Pipes Installation 6 29-Aug-12 04-Sep-12 08-Jan-13 14-Jan-13 108 A66340 Drainage&Water Pipes Testing 6 05-Sep-12 11-Sep-12 15-Jan-13 21-Jan-13 108 Fire FighFire Fighting 7 24-Oct-12 03-Nov-12 25-Mar-13 01-Apr-13 124 A66260 Fire Alarm Devices 7 24-Oct-12 03-Nov-12 25-Mar-13 01-Apr-13 124 VestibuleVestibule 323 16-Aug-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 28 16-Aug-12 19-Sep-12 20-Jan-13 21-Feb-13 127 A65070 Block Works 4 16-Aug-12 22-Aug-12 20-Jan-13 23-Jan-13 127 A65020 Plaster Works 6 29-Aug-12 04-Sep-12 31-Jan-13 06-Feb-13 127 A65040 Installation of Suspended Ceiling Grid 4 10-Sep-12 13-Sep-12 12-Feb-13 16-Feb-13 127 A65030 1st Coat Paint 5 15-Sep-12 19-Sep-12 17-Feb-13 21-Feb-13 127 Fisrt StaFisrt Stage Finishes 10 20-Sep-12 01-Oct-12 23-Feb-13 14-Apr-13 161 A65050 Suspended Ceiling Tiles 3 20-Sep-12 23-Sep-12 23-Feb-13 25-Feb-13 127 A65220 Screed Works 2 24-Sep-12 25-Sep-12 07-Apr-13 08-Apr-13 161 A65230 Wall Tiles Work 5 26-Sep-12 01-Oct-12 09-Apr-13 14-Apr-13 161 Second SSecond Stage Finishes 5 14-Oct-12 18-Oct-12 15-Apr-13 28-Apr-13 158 A65250 Floor Tiles Work 3 14-Oct-12 16-Oct-12 15-Apr-13 17-Apr-13 151 A65060 Installation of Doors 2 17-Oct-12 18-Oct-12 27-Apr-13 28-Apr-13 158 A65080 Doors Ironmongery 2 17-Oct-12 18-Oct-12 27-Apr-13 28-Apr-13 158 A65260 Final Coat Paint 2 17-Oct-12 18-Oct-12 18-Apr-13 20-Apr-13 151 Final StaFinal Stage Finishes 147 19-Mar-13 08-Sep-13 27-Apr-13 02-Oct-13 21 A65210 Installation of Sinages 2 19-Mar-13 20-Mar-13 27-Apr-13 28-Apr-13 33 A65290 Installation of Carpets 3 21-Mar-13 24-Mar-13 27-Jul-13 29-Jul-13 108 A65280 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 34 23-Aug-12 01-Oct-12 26-Jan-13 17-Apr-13 164 HVACHVAC 29 23-Aug-12 25-Sep-12 05-Feb-13 05-Mar-13 132 A65090 Duct Installation & Insulation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136 A65100 Chilled Water Pipe Installation & Insulation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136 A65110 Condensate Pipe Installation 4 23-Aug-12 27-Aug-12 05-Feb-13 09-Feb-13 136 A65120 FCU Installation 2 28-Aug-12 29-Aug-12 10-Feb-13 11-Feb-13 136 A65130 Air-Outlet Installation 2 24-Sep-12 25-Sep-12 04-Mar-13 05-Mar-13 132 ElectricalElectrical 34 23-Aug-12 01-Oct-12 26-Jan-13 05-Mar-13 127 A65140 Install Conduits in Wall 5 23-Aug-12 28-Aug-12 26-Jan-13 30-Jan-13 127 A65150 Install Cable Trays & Trunking 5 23-Aug-12 28-Aug-12 30-Jan-13 04-Feb-13 131 A65180 Cable Laying for Low Current System 4 29-Aug-12 02-Sep-12 12-Feb-13 16-Feb-13 137 A65190 Cable Laying for Power 4 29-Aug-12 02-Sep-12 12-Feb-13 16-Feb-13 137 A65160 Wiring for Lighting & Power 4 05-Sep-12 09-Sep-12 07-Feb-13 11-Feb-13 127 A65170 Wiring for Low Current System 4 05-Sep-12 09-Sep-12 07-Feb-13 11-Feb-13 127 A65200 Installation of Lighting Fittings 7 24-Sep-12 01-Oct-12 26-Feb-13 05-Mar-13 127 Fire FighFire Fighting 32 23-Aug-12 29-Sep-12 04-Feb-13 17-Apr-13 166 A65300 Fire Fighting Pipe 5 23-Aug-12 28-Aug-12 04-Feb-13 09-Feb-13 135 A65310 Hydro Static Test for Pipes 2 29-Aug-12 30-Aug-12 10-Feb-13 11-Feb-13 135 A65240 Fire Alarm Devices 5 24-Sep-12 29-Sep-12 13-Apr-13 17-Apr-13 166 A65320 Sprinkler Fixing 5 24-Sep-12 29-Sep-12 28-Feb-13 05-Mar-13 129 BussinissBussiniss Centre & Lobby 323 16-Aug-12 08-Sep-13 31-Oct-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 31-Oct-12 02-Oct-13 21 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Final Coat Paint Installation of Mirrors&Glass Instllation of Displayed Kitchen Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Mirrors&Glass Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings H/L Drainage Pipes Installation Drainage&Water Pipes Testing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Carpets Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 62 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 63. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Wet WorWet Works 61 16-Aug-12 30-Oct-12 31-Oct-12 13-Jan-13 61 A64380 Block Works 14 16-Aug-12 03-Sep-12 31-Oct-12 17-Nov-12 61 A64330 Plaster Works 13 16-Sep-12 30-Sep-12 29-Nov-12 15-Dec-12 61 A64350 Installation of Suspended Ceiling Grid 9 13-Oct-12 22-Oct-12 27-Dec-12 07-Jan-13 61 A64340 1st Coat Paint 5 23-Oct-12 30-Oct-12 08-Jan-13 13-Jan-13 61 Fisrt StaFisrt Stage Finishes 29 31-Oct-12 05-Dec-12 14-Jan-13 17-Feb-13 61 A64360 Suspended Ceiling Tiles 9 31-Oct-12 10-Nov-12 14-Jan-13 23-Jan-13 61 A64560 Screed Works 7 11-Nov-12 19-Nov-12 26-Jan-13 02-Feb-13 61 A64570 Wall Tiles Work 13 20-Nov-12 05-Dec-12 03-Feb-13 17-Feb-13 61 Second SSecond Stage Finishes 11 06-Dec-12 18-Dec-12 18-Feb-13 28-Apr-13 110 A64600 Floor Tiles Work 8 06-Dec-12 15-Dec-12 18-Feb-13 26-Feb-13 61 A64370 Installation of Doors 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 A64390 Doors Ironmongery 3 16-Dec-12 18-Dec-12 25-Apr-13 28-Apr-13 110 A64610 Final Coat Paint 3 16-Dec-12 18-Dec-12 27-Feb-13 02-Mar-13 61 Final StaFinal Stage Finishes 222 19-Dec-12 08-Sep-13 03-Mar-13 02-Oct-13 21 A64620 Installation of Mirrors&Glass 20 19-Dec-12 12-Jan-13 03-Mar-13 25-Mar-13 61 A64650 Installation of Carpets 20 21-Mar-13 13-Apr-13 26-Mar-13 17-Apr-13 4 A64550 Installation of Sinages 9 14-Apr-13 23-Apr-13 18-Apr-13 28-Apr-13 4 A64640 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 A114070 Installation of Reception Counter 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 68 04-Sep-12 25-Nov-12 18-Nov-12 26-Feb-13 77 HVACHVAC 63 04-Sep-12 19-Nov-12 13-Dec-12 26-Feb-13 82 A64400 Duct Installation & Insulation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82 A64410 Chilled Water Pipe Installation & Insulation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82 A64420 Condensate Pipe Installation 5 04-Sep-12 09-Sep-12 13-Dec-12 18-Dec-12 82 A64430 FCU Installation 7 10-Sep-12 17-Sep-12 19-Dec-12 26-Dec-12 82 A64440 Air-Outlet Installation 7 11-Nov-12 19-Nov-12 19-Feb-13 26-Feb-13 82 ElectricalElectrical 67 04-Sep-12 24-Nov-12 18-Nov-12 26-Feb-13 78 A64450 Install Conduits in Wall 10 04-Sep-12 15-Sep-12 18-Nov-12 28-Nov-12 61 A64460 Install Cable Trays & Trunking 10 04-Sep-12 15-Sep-12 01-Dec-12 12-Dec-12 72 A64490 Cable Laying for Low Current System 10 16-Sep-12 26-Sep-12 26-Dec-12 07-Jan-13 83 A64500 Cable Laying for Power 10 16-Sep-12 26-Sep-12 26-Dec-12 07-Jan-13 83 A64470 Wiring for Lighting & Power 10 01-Oct-12 11-Oct-12 16-Dec-12 26-Dec-12 61 A64480 Wiring for Low Current System 10 01-Oct-12 11-Oct-12 16-Dec-12 26-Dec-12 61 A64510 Installation of Lighting Fittings 11 11-Nov-12 24-Nov-12 14-Feb-13 26-Feb-13 78 PlumbingPlumbing 14 04-Sep-12 19-Sep-12 11-Dec-12 26-Dec-12 80 A64670 H/L Drainage Pipes Installation 7 04-Sep-12 11-Sep-12 11-Dec-12 18-Dec-12 80 A64680 H/L Hot&Cold Water Pipe Installation 7 04-Sep-12 11-Sep-12 11-Dec-12 18-Dec-12 80 A64690 Drainage&Water Pipes Testing 7 12-Sep-12 19-Sep-12 19-Dec-12 26-Dec-12 80 Fire FighFire Fighting 12 11-Nov-12 25-Nov-12 13-Feb-13 26-Feb-13 77 A64590 Fire Alarm Devices 12 11-Nov-12 25-Nov-12 13-Feb-13 26-Feb-13 77 RetailRetail 323 16-Aug-12 08-Sep-13 21-Jan-13 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 21-Jan-13 02-Oct-13 21 Wet WorWet Works 27 16-Aug-12 18-Sep-12 21-Jan-13 25-Apr-13 182 A64780 Block Works 4 16-Aug-12 22-Aug-12 21-Jan-13 26-Jan-13 128 A64710 Installation of Doors& Windows Sub-frame 2 28-Aug-12 29-Aug-12 24-Apr-13 25-Apr-13 199 A64700 Plaster Works 6 28-Aug-12 03-Sep-12 31-Jan-13 06-Feb-13 128 A64730 Installation of Suspended Ceiling Grid 4 09-Sep-12 12-Sep-12 12-Feb-13 16-Feb-13 128 A64720 1st Coat Paint 5 13-Sep-12 18-Sep-12 17-Feb-13 21-Feb-13 128 Fisrt StaFisrt Stage Finishes 13 19-Sep-12 03-Oct-12 23-Feb-13 17-Apr-13 162 A64740 Suspended Ceiling Tiles 3 19-Sep-12 22-Sep-12 23-Feb-13 25-Feb-13 128 A64960 Screed Works 2 23-Sep-12 24-Sep-12 14-Apr-13 15-Apr-13 168 A64760 Floor Tiles Work 2 02-Oct-12 03-Oct-12 16-Apr-13 17-Apr-13 162 Second SSecond Stage Finishes 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 A64770 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 A64790 Doors Ironmongery 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 Final StaFinal Stage Finishes 283 04-Oct-12 08-Sep-13 18-Apr-13 02-Oct-13 21 A64750 Final Coat Paint 2 04-Oct-12 06-Oct-12 18-Apr-13 20-Apr-13 162 A64950 Installation of Sinages 2 21-Mar-13 23-Mar-13 27-Apr-13 28-Apr-13 31 A64980 Installation of Carpets 2 21-Mar-13 23-Mar-13 27-Apr-13 28-Apr-13 31 A64800 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 33 23-Aug-12 30-Sep-12 27-Jan-13 20-Apr-13 167 HVACHVAC 10 23-Aug-12 03-Sep-12 31-Jan-13 11-Feb-13 132 A64990 Chilled Water Pipe Installation & Insulation 5 23-Aug-12 28-Aug-12 31-Jan-13 05-Feb-13 132 A65000 Condensate Pipe Installation 5 23-Aug-12 28-Aug-12 31-Jan-13 05-Feb-13 132 A65010 FCU Installation 5 29-Aug-12 03-Sep-12 06-Feb-13 11-Feb-13 132 ElectricalElectrical 33 23-Aug-12 30-Sep-12 27-Jan-13 05-Mar-13 128 A64830 Install Conduits in Wall 4 23-Aug-12 27-Aug-12 27-Jan-13 30-Jan-13 128 A64840 Install Cable Trays & Trunking 4 23-Aug-12 27-Aug-12 31-Jan-13 04-Feb-13 132 A64870 Cable Laying for Low Current System 4 28-Aug-12 01-Sep-12 12-Feb-13 16-Feb-13 138 A64880 Cable Laying for Power 4 28-Aug-12 01-Sep-12 12-Feb-13 16-Feb-13 138 A64850 Wiring for Lighting & Power 4 04-Sep-12 08-Sep-12 07-Feb-13 11-Feb-13 128 A64860 Wiring for Low Current System 4 04-Sep-12 08-Sep-12 07-Feb-13 11-Feb-13 128 A64900 Installation of Sockets 3 23-Sep-12 25-Sep-12 03-Mar-13 05-Mar-13 132 A64890 Installation of Lighting Fittings 7 23-Sep-12 30-Sep-12 26-Feb-13 05-Mar-13 128 Fire FighFire Fighting 33 23-Aug-12 30-Sep-12 02-Feb-13 20-Apr-13 167 A64940 Fire Fighting Pipe 5 23-Aug-12 28-Aug-12 02-Feb-13 06-Feb-13 133 A64930 Hydro Static Test for Pipes 4 29-Aug-12 02-Sep-12 07-Feb-13 11-Feb-13 133 A64920 Sprinkler Fixing 5 23-Sep-12 27-Sep-12 28-Feb-13 05-Mar-13 130 A64910 Installation of Fire Extingusher&Blanket 2 29-Sep-12 30-Sep-12 18-Apr-13 20-Apr-13 167 A64970 Fire Alarm Devices 7 23-Sep-12 30-Sep-12 10-Apr-13 17-Apr-13 165 Meeting RoMeeting Rooms 323 16-Aug-12 08-Sep-13 04-Dec-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 04-Dec-12 02-Oct-13 21 Wet WorWet Works 58 16-Aug-12 24-Oct-12 04-Dec-12 24-Apr-13 150 A60000 Block Works 14 16-Aug-12 03-Sep-12 04-Dec-12 19-Dec-12 88 A59860 Installation of Doors& Windows Sub-frame 3 12-Sep-12 15-Sep-12 22-Apr-13 24-Apr-13 184 A59850 Plaster Works 12 12-Sep-12 25-Sep-12 29-Dec-12 12-Jan-13 88 A59880 Installation of Suspended Ceiling Grid 12 02-Oct-12 15-Oct-12 19-Jan-13 02-Feb-13 88 A59870 1st Coat Paint 8 16-Oct-12 24-Oct-12 03-Feb-13 11-Feb-13 88 Fisrt StaFisrt Stage Finishes 32 28-Oct-12 05-Dec-12 12-Feb-13 15-Apr-13 110 A59890 Suspended Ceiling Tiles 12 28-Oct-12 10-Nov-12 12-Feb-13 25-Feb-13 88 A60320 Screed Works 6 11-Nov-12 18-Nov-12 24-Mar-13 30-Mar-13 110 A59910 Wall Tiles Work 14 19-Nov-12 05-Dec-12 31-Mar-13 15-Apr-13 110 Second SSecond Stage Finishes 3 06-Dec-12 09-Dec-12 16-Apr-13 28-Apr-13 118 A59900 Final Coat Paint 1 06-Dec-12 06-Dec-12 16-Apr-13 16-Apr-13 110 A59940 Installation of Windows&Doors 3 06-Dec-12 09-Dec-12 25-Apr-13 28-Apr-13 118 A60010 Doors Ironmongery 3 06-Dec-12 09-Dec-12 25-Apr-13 28-Apr-13 118 Final StaFinal Stage Finishes 145 21-Mar-13 08-Sep-13 17-Apr-13 02-Oct-13 21 A59970 Installation of Carpets 7 21-Mar-13 28-Mar-13 17-Apr-13 24-Apr-13 23 A60310 Installation of Sinages 3 30-Mar-13 01-Apr-13 25-Apr-13 28-Apr-13 23 A60020 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 69 04-Sep-12 26-Nov-12 20-Dec-12 15-Apr-13 117 HVACHVAC 63 04-Sep-12 19-Nov-12 10-Jan-13 05-Mar-13 88 A60030 Duct Installation & Insulation 7 04-Sep-12 11-Sep-12 10-Jan-13 17-Jan-13 105 A60070 Air-Outlet Installation 7 11-Nov-12 19-Nov-12 26-Feb-13 05-Mar-13 88 ElectricalElectrical 62 04-Sep-12 18-Nov-12 20-Dec-12 05-Mar-13 89 A60090 Install Cable Trays & Trunking 6 04-Sep-12 10-Sep-12 03-Jan-13 09-Jan-13 99 A60080 Install Conduits in Wall 7 04-Sep-12 11-Sep-12 20-Dec-12 27-Dec-12 88 A60130 Cable Laying for Low Current System 5 11-Sep-12 16-Sep-12 28-Jan-13 02-Feb-13 113 A60140 Cable Laying for Power 5 11-Sep-12 16-Sep-12 28-Jan-13 02-Feb-13 113 A60100 Wiring for Lighting & Power 5 26-Sep-12 01-Oct-12 13-Jan-13 17-Jan-13 88 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Mirrors&Glass Installation of Carpets Installation of Sinages Installation of Furnitur Installation of Recepti Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Carpets Installation of Furnitur Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Final Coat Paint Installation of Windows&Doors Doors Ironmongery Installation of Carpets Installation of Sinages Installation of Furnitur Duct Installation & Insulation Air-Outlet Installation Install Cable Trays & Trunking Install Conduits in Wall Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 63 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 64. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A60110 Wiring for Low Current System 5 26-Sep-12 01-Oct-12 13-Jan-13 17-Jan-13 88 A60170 Installation of Sockets 5 11-Nov-12 17-Nov-12 28-Feb-13 05-Mar-13 90 A60160 Installation of Lighting Fittings 6 11-Nov-12 18-Nov-12 27-Feb-13 05-Mar-13 89 Fire FighFire Fighting 69 04-Sep-12 26-Nov-12 05-Jan-13 15-Apr-13 117 A60290 Fire Fighting Pipe 7 04-Sep-12 11-Sep-12 05-Jan-13 12-Jan-13 100 A60280 Hydro Static Test for Pipes 5 12-Sep-12 17-Sep-12 13-Jan-13 17-Jan-13 100 A60270 Sprinkler Fixing 6 11-Nov-12 18-Nov-12 27-Feb-13 05-Mar-13 89 A60370 Fire Alarm Devices 7 19-Nov-12 26-Nov-12 08-Apr-13 15-Apr-13 117 RMU RoomRMU Room 109 16-Aug-12 27-Dec-12 23-Jan-13 28-Apr-13 102 FinishingFinishing Works 73 16-Aug-12 13-Nov-12 23-Jan-13 28-Apr-13 138 Wet WorWet Works 24 16-Aug-12 15-Sep-12 23-Jan-13 08-Apr-13 170 A63160 Block Works 5 16-Aug-12 23-Aug-12 23-Jan-13 29-Jan-13 130 A63120 Installation of Doors& Windows Sub-frame 2 28-Aug-12 29-Aug-12 07-Apr-13 08-Apr-13 184 A63110 Plaster Works 7 28-Aug-12 04-Sep-12 03-Feb-13 10-Feb-13 130 A63130 1st Coat Paint 7 08-Sep-12 15-Sep-12 13-Feb-13 20-Feb-13 130 Fisrt StaFisrt Stage Finishes 40 24-Sep-12 11-Nov-12 02-Mar-13 25-Apr-13 138 A63220 Epoxy Paint Works 2 24-Sep-12 25-Sep-12 02-Mar-13 03-Mar-13 130 A63150 Installation of Doors 15 23-Oct-12 11-Nov-12 09-Apr-13 25-Apr-13 138 A63170 Doors Ironmongery 15 23-Oct-12 11-Nov-12 09-Apr-13 25-Apr-13 138 Second SSecond Stage Finishes 4 26-Sep-12 30-Sep-12 04-Mar-13 07-Mar-13 130 A63140 Final Coat Paint 4 26-Sep-12 30-Sep-12 04-Mar-13 07-Mar-13 130 Final StaFinal Stage Finishes 2 12-Nov-12 13-Nov-12 27-Apr-13 28-Apr-13 138 A63210 Installation of Sinages 2 12-Nov-12 13-Nov-12 27-Apr-13 28-Apr-13 138 MEP WorkMEP Works 106 22-Aug-12 27-Dec-12 28-Jan-13 21-Mar-13 70 HVACHVAC 12 25-Aug-12 06-Sep-12 16-Feb-13 28-Feb-13 144 A63250 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 16-Feb-13 23-Feb-13 144 A63260 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 16-Feb-13 23-Feb-13 144 A63270 FCU Installation 5 02-Sep-12 06-Sep-12 24-Feb-13 28-Feb-13 144 ElectricalElectrical 106 22-Aug-12 27-Dec-12 28-Jan-13 21-Mar-13 70 Light &Light & Power 26 22-Aug-12 20-Sep-12 28-Jan-13 28-Feb-13 132 A63180 Install Conduits in Wall 5 22-Aug-12 27-Aug-12 28-Jan-13 02-Feb-13 130 A63280 Install Cable Trays & Trunking 7 25-Aug-12 01-Sep-12 13-Feb-13 20-Feb-13 142 A63190 Wiring for Lighting & Power 4 03-Sep-12 06-Sep-12 09-Feb-13 12-Feb-13 130 A63290 Cable Laying for Power 7 02-Sep-12 09-Sep-12 21-Feb-13 28-Feb-13 142 A63200 Installation of Lighting Fittings 5 16-Sep-12 20-Sep-12 24-Feb-13 28-Feb-13 132 RMU UnRMU Unit 29 24-Nov-12 27-Dec-12 17-Feb-13 21-Mar-13 70 A114700 Install Cable Tray & Trunking 5 24-Nov-12 28-Nov-12 17-Feb-13 21-Feb-13 70 A114690 Installation of RMU Unit 12 24-Nov-12 08-Dec-12 02-Mar-13 14-Mar-13 81 A114720 Install of Cables 12 29-Nov-12 13-Dec-12 23-Feb-13 07-Mar-13 70 A114750 Test of Cables 6 15-Dec-12 20-Dec-12 09-Mar-13 14-Mar-13 70 A114760 Termination of Cables 6 22-Dec-12 27-Dec-12 16-Mar-13 21-Mar-13 70 Fire FighFire Fighting 7 16-Sep-12 23-Sep-12 21-Feb-13 28-Feb-13 130 A63230 Fire Alarm Devices 7 16-Sep-12 23-Sep-12 21-Feb-13 28-Feb-13 130 AdminstraAdminstration Offices 323 16-Aug-12 08-Sep-13 31-Dec-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 31-Dec-12 02-Oct-13 21 Wet WorWet Works 40 16-Aug-12 03-Oct-12 31-Dec-12 25-Apr-13 169 A63530 Block Works 8 16-Aug-12 27-Aug-12 31-Dec-12 09-Jan-13 111 A63460 Installation of Doors& Windows Sub-frame 2 02-Sep-12 03-Sep-12 24-Apr-13 25-Apr-13 195 A63450 Plaster Works 7 02-Sep-12 09-Sep-12 15-Jan-13 22-Jan-13 111 A63480 Installation of Suspended Ceiling Grid 7 15-Sep-12 22-Sep-12 29-Jan-13 05-Feb-13 111 A63470 1st Coat Paint 10 23-Sep-12 03-Oct-12 06-Feb-13 17-Feb-13 111 Fisrt StaFisrt Stage Finishes 16 04-Oct-12 22-Oct-12 18-Feb-13 15-Apr-13 144 A63490 Suspended Ceiling Tiles 7 04-Oct-12 11-Oct-12 18-Feb-13 25-Feb-13 111 A63820 Screed Works 2 13-Oct-12 14-Oct-12 06-Apr-13 07-Apr-13 144 A63510 Floor Tiles Work 7 15-Oct-12 22-Oct-12 08-Apr-13 15-Apr-13 144 Second SSecond Stage Finishes 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 A63520 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 A63540 Doors Ironmongery 2 14-Nov-12 17-Nov-12 27-Apr-13 28-Apr-13 136 Final StaFinal Stage Finishes 267 23-Oct-12 08-Sep-13 16-Apr-13 02-Oct-13 21 A63500 Final Coat Paint 4 23-Oct-12 29-Oct-12 16-Apr-13 20-Apr-13 144 A63810 Installation of Sinages 2 27-Mar-13 28-Mar-13 27-Apr-13 28-Apr-13 26 A63840 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A63550 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 48 28-Aug-12 22-Oct-12 10-Jan-13 20-Apr-13 148 HVACHVAC 44 28-Aug-12 17-Oct-12 20-Feb-13 05-Mar-13 113 A63560 Duct Installation & Insulation 7 28-Aug-12 04-Sep-12 20-Feb-13 27-Feb-13 145 A63600 Air-Outlet Installation 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113 ElectricalElectrical 44 28-Aug-12 17-Oct-12 10-Jan-13 05-Mar-13 113 A63610 Install Conduits in Wall 4 28-Aug-12 01-Sep-12 10-Jan-13 14-Jan-13 111 A63620 Install Cable Trays & Trunking 4 28-Aug-12 01-Sep-12 16-Jan-13 20-Jan-13 116 A63650 Cable Laying for Low Current System 5 02-Sep-12 06-Sep-12 31-Jan-13 05-Feb-13 124 A63660 Cable Laying for Power 5 02-Sep-12 06-Sep-12 31-Jan-13 05-Feb-13 124 A63630 Wiring for Lighting & Power 4 10-Sep-12 13-Sep-12 23-Jan-13 28-Jan-13 111 A63640 Wiring for Low Current System 4 10-Sep-12 13-Sep-12 23-Jan-13 28-Jan-13 111 A63680 Installation of Sockets 4 13-Oct-12 16-Oct-12 02-Mar-13 05-Mar-13 114 A63670 Installation of Lighting Fittings 5 13-Oct-12 17-Oct-12 28-Feb-13 05-Mar-13 113 Fire FighFire Fighting 48 28-Aug-12 22-Oct-12 15-Jan-13 20-Apr-13 148 A63800 Fire Fighting Pipe 7 28-Aug-12 04-Sep-12 15-Jan-13 22-Jan-13 115 A63790 Hydro Static Test for Pipes 4 05-Sep-12 09-Sep-12 23-Jan-13 28-Jan-13 115 A63780 Sprinkler Fixing 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111 A63830 Fire Alarm Devices 7 13-Oct-12 20-Oct-12 08-Apr-13 15-Apr-13 146 A63770 Installation of Fire Extingusher&Blanket 2 21-Oct-12 22-Oct-12 18-Apr-13 20-Apr-13 148 Drivers RoDrivers Room 323 16-Aug-12 08-Sep-13 29-Dec-12 02-Oct-13 21 FinishingFinishing Works 323 16-Aug-12 08-Sep-13 29-Dec-12 02-Oct-13 21 Wet WorWet Works 28 16-Aug-12 19-Sep-12 29-Dec-12 07-Apr-13 165 A61970 Block Works 5 16-Aug-12 23-Aug-12 29-Dec-12 03-Jan-13 109 A61830 Installation of Doors& Windows Sub-frame 2 29-Aug-12 30-Aug-12 06-Apr-13 07-Apr-13 182 A61820 Plaster Works 5 29-Aug-12 03-Sep-12 09-Jan-13 14-Jan-13 109 A62300 Wall Tiles Work (Wet Area) 5 04-Sep-12 09-Sep-12 06-Feb-13 11-Feb-13 127 A61850 Installation of Suspended Ceiling Grid (Dry Area) 5 09-Sep-12 13-Sep-12 20-Jan-13 26-Jan-13 109 A61840 1st Coat Paint 5 15-Sep-12 19-Sep-12 27-Jan-13 31-Jan-13 109 Fisrt StaFisrt Stage Finishes 40 20-Sep-12 07-Nov-12 02-Feb-13 14-Apr-13 131 A61860 Suspended Ceiling Tiles (DryArea) 4 20-Sep-12 24-Sep-12 02-Feb-13 05-Feb-13 109 A61900 Installation of Wardrobes 5 08-Oct-12 13-Oct-12 06-Feb-13 11-Feb-13 98 A62290 Screed Works 2 14-Oct-12 15-Oct-12 12-Feb-13 13-Feb-13 98 A61890 Water Proofing for Wet Area 3 16-Oct-12 18-Oct-12 14-Feb-13 17-Feb-13 98 A61880 Floor & Wall Tiles Work (Dry Area) 5 16-Oct-12 21-Oct-12 09-Apr-13 14-Apr-13 144 A62330 Installation of Suspended Ceiling Grid (Wet Area) 5 20-Oct-12 24-Oct-12 18-Feb-13 23-Feb-13 98 A62320 Suspended Ceiling Tiles (Wet Area) 5 28-Oct-12 01-Nov-12 24-Feb-13 28-Feb-13 98 A62310 Floor Tiles Work (Wet Area) 5 03-Nov-12 07-Nov-12 02-Apr-13 07-Apr-13 125 Second SSecond Stage Finishes 6 14-Nov-12 21-Nov-12 08-Apr-13 14-Apr-13 120 A61910 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 08-Apr-13 09-Apr-13 120 A61980 Doors Ironmongery 2 14-Nov-12 17-Nov-12 13-Apr-13 14-Apr-13 124 A61960 Installation of Vanity Counter 2 18-Nov-12 19-Nov-12 13-Apr-13 14-Apr-13 122 A62270 Installation of Toliets Accessories 2 18-Nov-12 19-Nov-12 13-Apr-13 14-Apr-13 122 A61920 Installation of Mirrors 4 18-Nov-12 21-Nov-12 10-Apr-13 14-Apr-13 120 Final StaFinal Stage Finishes 244 22-Nov-12 08-Sep-13 15-Apr-13 02-Oct-13 21 A61870 Final Coat Paint 5 22-Nov-12 27-Nov-12 15-Apr-13 20-Apr-13 120 A62280 Installation of Sinages 2 28-Nov-12 29-Nov-12 27-Apr-13 28-Apr-13 125 A61990 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 74 25-Aug-12 21-Nov-12 05-Jan-13 20-Apr-13 125 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Install Conduits in Wall Install Cable Trays & Trunking Wiring for Lighting & Power Cable Laying for Power Installation of Lighting Fittings Install Cable Tray & Trunking Installation of RMU Unit Install of Cables Test of Cables Termination of Cables Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Carpets Installation of Furnitur Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Vanity Counter Installation of Toliets Accessories Installation of Mirrors Final Coat Paint Installation of Sinages Installation of Furnitur Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 64 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 65. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float HVACHVAC 61 25-Aug-12 05-Nov-12 09-Jan-13 05-Mar-13 99 A62000 Duct Installation & Insulation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113 A62010 Chilled Water Pipe Installation & Insulation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113 A62020 Condensate Pipe Installation 7 25-Aug-12 01-Sep-12 09-Jan-13 16-Jan-13 113 A62030 FCU Installation 2 02-Sep-12 03-Sep-12 17-Jan-13 19-Jan-13 113 A62040 Air-Outlet Installation 3 03-Nov-12 05-Nov-12 03-Mar-13 05-Mar-13 99 ElectricalElectrical 62 25-Aug-12 06-Nov-12 05-Jan-13 05-Mar-13 98 A62060 Install Cable Trays & Trunking 3 25-Aug-12 27-Aug-12 09-Jan-13 12-Jan-13 113 A62050 Install Conduits in Wall 4 25-Aug-12 28-Aug-12 05-Jan-13 08-Jan-13 109 A62100 Cable Laying for Low Current System 3 28-Aug-12 30-Aug-12 22-Jan-13 26-Jan-13 121 A62110 Cable Laying for Power 3 28-Aug-12 30-Aug-12 22-Jan-13 26-Jan-13 121 A62070 Wiring for Lighting & Power 4 04-Sep-12 08-Sep-12 15-Jan-13 19-Jan-13 109 A62080 Wiring for Low Current System 4 04-Sep-12 08-Sep-12 15-Jan-13 19-Jan-13 109 A62140 Installation of Sockets 2 03-Nov-12 04-Nov-12 04-Mar-13 05-Mar-13 100 A62130 Installation of Lighting Fittings 4 03-Nov-12 06-Nov-12 02-Mar-13 05-Mar-13 98 PlumbingPlumbing 74 25-Aug-12 21-Nov-12 07-Jan-13 14-Apr-13 120 A62150 Drainge Pipes in Wall 2 25-Aug-12 26-Aug-12 07-Jan-13 08-Jan-13 111 A62220 Water Pipes in Wall 2 25-Aug-12 26-Aug-12 07-Jan-13 08-Jan-13 111 A62160 H/L Drainage Pipes Installation 4 25-Aug-12 28-Aug-12 10-Feb-13 13-Feb-13 139 A62170 H/L Hot&Cold Water Pipe Installation 4 25-Aug-12 28-Aug-12 10-Feb-13 13-Feb-13 139 A62180 Drainage&Water Pipes Testing 3 29-Aug-12 01-Sep-12 14-Feb-13 17-Feb-13 139 A62190 ElectricalWater Heater Installation 3 29-Aug-12 01-Sep-12 14-Feb-13 17-Feb-13 139 A62200 Floor Drain Fixning 2 16-Oct-12 17-Oct-12 04-Mar-13 05-Mar-13 113 A62210 Installation of Sanitaryware 4 18-Nov-12 21-Nov-12 10-Apr-13 14-Apr-13 120 Fire FighFire Fighting 63 25-Aug-12 07-Nov-12 13-Jan-13 20-Apr-13 136 A62260 Fire Fighting Pipe 3 25-Aug-12 27-Aug-12 13-Jan-13 15-Jan-13 116 A62250 Hydro Static Test for Pipes 3 28-Aug-12 30-Aug-12 16-Jan-13 19-Jan-13 116 A62240 Sprinkler Fixing 3 03-Nov-12 05-Nov-12 03-Mar-13 05-Mar-13 99 A62340 Fire Alarm Devices 3 03-Nov-12 05-Nov-12 11-Apr-13 14-Apr-13 133 A62230 Installation of Fire Extingusher&Blanket 2 06-Nov-12 07-Nov-12 18-Apr-13 20-Apr-13 136 ELV RoomELV Room 115 16-Aug-12 05-Jan-13 24-Oct-12 28-Apr-13 96 FinishingFinishing Works 115 16-Aug-12 05-Jan-13 24-Oct-12 28-Apr-13 96 Wet WorWet Works 28 16-Aug-12 19-Sep-12 24-Oct-12 23-Apr-13 179 A62540 Block Works 4 16-Aug-12 22-Aug-12 24-Oct-12 30-Oct-12 57 A62500 Installation of Doors& Windows Sub-frame 2 29-Aug-12 30-Aug-12 22-Apr-13 23-Apr-13 196 A62490 Plaster Works 7 29-Aug-12 05-Sep-12 06-Nov-12 13-Nov-12 57 A62510 1st Coat Paint 7 12-Sep-12 19-Sep-12 21-Nov-12 28-Nov-12 57 Fisrt StaFisrt Stage Finishes 54 23-Oct-12 29-Dec-12 15-Apr-13 25-Apr-13 99 A62530 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 A62550 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 A62600 Epoxy Paint Works 2 27-Dec-12 29-Dec-12 15-Apr-13 16-Apr-13 91 Second SSecond Stage Finishes 3 30-Dec-12 02-Jan-13 17-Apr-13 20-Apr-13 91 A62520 Final Coat Paint 3 30-Dec-12 02-Jan-13 17-Apr-13 20-Apr-13 91 Final StaFinal Stage Finishes 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96 A62590 Installation of Sinages 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96 MEP WorkMEP Works 104 23-Aug-12 26-Dec-12 31-Oct-12 14-Apr-13 91 HVACHVAC 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130 A62620 Air-Outlet Installation 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130 ElectricalElectrical 104 23-Aug-12 26-Dec-12 31-Oct-12 05-Mar-13 57 A62560 Install Conduits in Wall 5 23-Aug-12 28-Aug-12 31-Oct-12 05-Nov-12 57 A62570 Wiring for Lighting & Power 5 06-Sep-12 11-Sep-12 14-Nov-12 20-Nov-12 57 A62580 Installation of Lighting Fittings 5 20-Sep-12 25-Sep-12 28-Feb-13 05-Mar-13 132 A114340 Installation of Access ControlSystem 80 20-Sep-12 26-Dec-12 29-Nov-12 05-Mar-13 57 A114350 Installation of MATC,TV System 80 20-Sep-12 26-Dec-12 29-Nov-12 05-Mar-13 57 Fire FighFire Fighting 8 20-Sep-12 29-Sep-12 06-Apr-13 14-Apr-13 163 A62610 Fire Alarm Devices 8 20-Sep-12 29-Sep-12 06-Apr-13 14-Apr-13 163 Electrical /Electrical / Telephone Rooms 60 16-Aug-12 29-Oct-12 31-Jan-13 28-Apr-13 151 FinishingFinishing Works 60 16-Aug-12 29-Oct-12 31-Jan-13 28-Apr-13 151 Wet WorWet Works 14 16-Aug-12 03-Sep-12 31-Jan-13 23-Apr-13 193 A62400 Block Works 3 16-Aug-12 21-Aug-12 31-Jan-13 03-Feb-13 136 A62360 Installation of Doors& Windows Sub-frame 1 25-Aug-12 25-Aug-12 23-Apr-13 23-Apr-13 201 A62350 Plaster Works 4 25-Aug-12 28-Aug-12 06-Feb-13 10-Feb-13 136 A62370 1st Coat Paint 3 01-Sep-12 03-Sep-12 13-Feb-13 16-Feb-13 136 Fisrt StaFisrt Stage Finishes 29 22-Sep-12 24-Oct-12 16-Apr-13 25-Apr-13 151 A62460 Epoxy Paint Works 2 22-Sep-12 23-Sep-12 16-Apr-13 17-Apr-13 171 A62390 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 A62410 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 Second SSecond Stage Finishes 2 24-Sep-12 25-Sep-12 18-Apr-13 20-Apr-13 171 A62380 Final Coat Paint 2 24-Sep-12 25-Sep-12 18-Apr-13 20-Apr-13 171 Final StaFinal Stage Finishes 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151 A62450 Installation of Sinages 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151 MEP WorkMEP Works 26 22-Aug-12 20-Sep-12 04-Feb-13 15-Apr-13 171 HVACHVAC 7 04-Sep-12 11-Sep-12 26-Feb-13 05-Mar-13 144 A62480 Air-Outlet Installation 7 04-Sep-12 11-Sep-12 26-Feb-13 05-Mar-13 144 ElectricalElectrical 26 22-Aug-12 20-Sep-12 04-Feb-13 05-Mar-13 136 A62420 Install Conduits in Wall 2 22-Aug-12 23-Aug-12 04-Feb-13 05-Feb-13 136 A62430 Wiring for Lighting & Power 2 29-Aug-12 30-Aug-12 11-Feb-13 12-Feb-13 136 A105480 Installation of SMDBs 7 04-Sep-12 11-Sep-12 24-Feb-13 03-Mar-13 142 A62440 Installation of Lighting Fittings 2 12-Sep-12 13-Sep-12 04-Mar-13 05-Mar-13 142 A114770 Installation of Telephone System 15 04-Sep-12 20-Sep-12 17-Feb-13 05-Mar-13 136 Fire FighFire Fighting 2 04-Sep-12 05-Sep-12 14-Apr-13 15-Apr-13 184 A62470 Fire Alarm Devices 2 04-Sep-12 05-Sep-12 14-Apr-13 15-Apr-13 184 Luggage RLuggage Room 60 16-Aug-12 29-Oct-12 10-Feb-13 28-Apr-13 151 FinishingFinishing Works 60 16-Aug-12 29-Oct-12 10-Feb-13 28-Apr-13 151 Wet WorWet Works 19 16-Aug-12 09-Sep-12 10-Feb-13 23-Apr-13 188 A63900 Block Works 5 16-Aug-12 23-Aug-12 10-Feb-13 14-Feb-13 144 A63860 Installation of Doors& Windows Sub-frame 1 27-Aug-12 27-Aug-12 23-Apr-13 23-Apr-13 199 A63850 Plaster Works 5 27-Aug-12 01-Sep-12 18-Feb-13 23-Feb-13 144 A63870 1st Coat Paint 5 04-Sep-12 09-Sep-12 26-Feb-13 03-Mar-13 144 Fisrt StaFisrt Stage Finishes 37 12-Sep-12 24-Oct-12 16-Apr-13 25-Apr-13 151 A63960 Epoxy Paint Works 2 12-Sep-12 13-Sep-12 16-Apr-13 17-Apr-13 179 A63890 Installation of Doors 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 A63910 Doors Ironmongery 2 23-Oct-12 24-Oct-12 24-Apr-13 25-Apr-13 151 Second SSecond Stage Finishes 2 15-Sep-12 16-Sep-12 18-Apr-13 20-Apr-13 179 A63880 Final Coat Paint 2 15-Sep-12 16-Sep-12 18-Apr-13 20-Apr-13 179 Final StaFinal Stage Finishes 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151 A63950 Installation of Sinages 2 28-Oct-12 29-Oct-12 27-Apr-13 28-Apr-13 151 MEP WorkMEP Works 16 25-Aug-12 11-Sep-12 16-Feb-13 20-Apr-13 183 HVACHVAC 9 25-Aug-12 03-Sep-12 24-Feb-13 05-Mar-13 151 A63980 Duct Installation & Insulation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151 A63990 Chilled Water Pipe Installation & Insulation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151 A64000 Condensate Pipe Installation 5 25-Aug-12 29-Aug-12 24-Feb-13 28-Feb-13 151 A64010 FCU Installation 2 30-Aug-12 01-Sep-12 02-Mar-13 03-Mar-13 151 A64020 Air-Outlet Installation 2 02-Sep-12 03-Sep-12 04-Mar-13 05-Mar-13 151 ElectricalElectrical 16 25-Aug-12 11-Sep-12 16-Feb-13 05-Mar-13 144 A63920 Install Conduits in Wall 2 25-Aug-12 26-Aug-12 16-Feb-13 17-Feb-13 144 A63930 Wiring for Lighting & Power 2 02-Sep-12 03-Sep-12 24-Feb-13 25-Feb-13 144 A63940 Installation of Lighting Fittings 2 10-Sep-12 11-Sep-12 04-Mar-13 05-Mar-13 144 PlumbingPlumbing 8 25-Aug-12 02-Sep-12 25-Feb-13 05-Mar-13 152 A64070 H/L Hot&Cold Water Pipe Installation 5 25-Aug-12 29-Aug-12 25-Feb-13 02-Mar-13 152 A64080 Water Pipes Testing 3 30-Aug-12 02-Sep-12 03-Mar-13 05-Mar-13 152 Fire FighFire Fighting 14 25-Aug-12 09-Sep-12 21-Feb-13 20-Apr-13 185 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Cable Trays & Trunking Install Conduits in Wall Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of Access ControlSystem Installation of MATC,TV System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 65 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 66. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A64060 Fire Fighting Pipe 5 25-Aug-12 29-Aug-12 21-Feb-13 26-Feb-13 149 A64050 Hydro Static Test for Pipes 3 30-Aug-12 02-Sep-12 27-Feb-13 02-Mar-13 149 A64040 Sprinkler Fixing 3 03-Sep-12 05-Sep-12 03-Mar-13 05-Mar-13 149 A64030 Installation of Fire Extingusher&Blanket 2 06-Sep-12 08-Sep-12 18-Apr-13 20-Apr-13 186 A63970 Fire Alarm Devices 3 06-Sep-12 09-Sep-12 13-Apr-13 15-Apr-13 181 Loading DoLoading Dock Area 62 16-Aug-12 31-Oct-12 29-Dec-12 28-Apr-13 149 FinishingFinishing Works 62 16-Aug-12 31-Oct-12 29-Dec-12 28-Apr-13 149 Wet WorWet Works 44 16-Aug-12 08-Oct-12 29-Dec-12 19-Feb-13 109 A64160 Block Works 6 16-Aug-12 25-Aug-12 29-Dec-12 05-Jan-13 109 A64110 Plaster Works 11 03-Sep-12 15-Sep-12 14-Jan-13 27-Jan-13 109 A64130 Installation of Suspended Ceiling Grid 5 24-Sep-12 29-Sep-12 05-Feb-13 10-Feb-13 109 A64120 1st Coat Paint 8 30-Sep-12 08-Oct-12 11-Feb-13 19-Feb-13 109 Fisrt StaFisrt Stage Finishes 14 09-Oct-12 24-Oct-12 20-Feb-13 20-Apr-13 146 A64140 Suspended Ceiling Tiles 5 09-Oct-12 14-Oct-12 20-Feb-13 25-Feb-13 109 A64310 Epoxy Paint Works 2 23-Oct-12 24-Oct-12 18-Apr-13 20-Apr-13 146 Second SSecond Stage Finishes 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149 A64150 Installation of Doors 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149 A64170 Doors Ironmongery 2 28-Oct-12 29-Oct-12 24-Apr-13 25-Apr-13 149 Final StaFinal Stage Finishes 2 30-Oct-12 31-Oct-12 27-Apr-13 28-Apr-13 149 A64300 Installation of Sinages 2 30-Oct-12 31-Oct-12 27-Apr-13 28-Apr-13 149 MEP WorkMEP Works 50 26-Aug-12 22-Oct-12 06-Jan-13 17-Apr-13 146 HVACHVAC 50 26-Aug-12 22-Oct-12 27-Jan-13 05-Mar-13 109 A64180 Duct Installation & Insulation 8 26-Aug-12 03-Sep-12 27-Jan-13 04-Feb-13 126 A64220 Air-Outlet Installation 7 15-Oct-12 22-Oct-12 26-Feb-13 05-Mar-13 109 ElectricalElectrical 50 26-Aug-12 22-Oct-12 06-Jan-13 05-Mar-13 109 A64230 Install Conduits in Wall 7 26-Aug-12 02-Sep-12 06-Jan-13 13-Jan-13 109 A64240 Wiring for Lighting & Power 7 16-Sep-12 23-Sep-12 28-Jan-13 04-Feb-13 109 A64250 Installation of Lighting Fittings 7 15-Oct-12 22-Oct-12 26-Feb-13 05-Mar-13 109 Fire FighFire Fighting 50 26-Aug-12 22-Oct-12 22-Jan-13 17-Apr-13 146 A64290 Fire Fighting Pipe 7 26-Aug-12 02-Sep-12 22-Jan-13 30-Jan-13 123 A64280 Hydro Static Test for Pipes 4 03-Sep-12 06-Sep-12 31-Jan-13 04-Feb-13 123 A64270 Sprinkler Fixing 5 15-Oct-12 20-Oct-12 28-Feb-13 05-Mar-13 111 A64260 Installation of Fire Extingusher&Blanket 2 21-Oct-12 22-Oct-12 16-Apr-13 17-Apr-13 146 A64320 Fire Alarm Devices 7 15-Oct-12 22-Oct-12 10-Apr-13 17-Apr-13 146 Hotel GarbHotel Garbage Room 120 16-Aug-12 10-Jan-13 27-Dec-12 28-Apr-13 91 FinishingFinishing Works 120 16-Aug-12 10-Jan-13 27-Dec-12 28-Apr-13 91 Wet WorWet Works 25 16-Aug-12 16-Sep-12 27-Dec-12 25-Apr-13 184 A61620 Block Works 9 16-Aug-12 28-Aug-12 27-Dec-12 07-Jan-13 108 A61560 Plaster Works 1 06-Sep-12 06-Sep-12 16-Jan-13 16-Jan-13 108 A61570 Installation of Doors& Windows Sub-frame 2 06-Sep-12 08-Sep-12 24-Apr-13 25-Apr-13 191 A61790 Wall Tiles Work 6 08-Sep-12 13-Sep-12 17-Jan-13 23-Jan-13 108 A61780 Screed Works 2 15-Sep-12 16-Sep-12 26-Jan-13 27-Jan-13 108 Fisrt StaFisrt Stage Finishes 88 17-Sep-12 02-Jan-13 28-Jan-13 25-Apr-13 96 A61580 1st Coat Paint 3 17-Sep-12 19-Sep-12 28-Jan-13 30-Jan-13 108 A61800 Floor Tiles Work 3 30-Dec-12 02-Jan-13 23-Apr-13 25-Apr-13 96 Second SSecond Stage Finishes 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96 A61600 Installation of Doors 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96 A61630 Doors Ironmongery 2 03-Jan-13 05-Jan-13 27-Apr-13 28-Apr-13 96 Final StaFinal Stage Finishes 70 16-Oct-12 10-Jan-13 31-Jan-13 28-Apr-13 91 A61610 Installation of Equipments 60 16-Oct-12 29-Dec-12 31-Jan-13 10-Apr-13 86 A61590 Final Coat Paint 8 30-Dec-12 08-Jan-13 11-Apr-13 20-Apr-13 86 A124210 Installation of Sinages 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91 MEP WorkMEP Works 28 29-Aug-12 30-Sep-12 08-Jan-13 10-Apr-13 159 ElectricalElectrical 22 29-Aug-12 23-Sep-12 08-Jan-13 05-Mar-13 134 A61670 Install Conduits in Wall 7 29-Aug-12 05-Sep-12 08-Jan-13 15-Jan-13 108 A61680 Wiring for Lighting & Power 7 08-Sep-12 15-Sep-12 18-Feb-13 25-Feb-13 134 A61690 Installation of Lighting Fittings 7 16-Sep-12 23-Sep-12 26-Feb-13 05-Mar-13 134 Fire FighFire Fighting 28 29-Aug-12 30-Sep-12 13-Feb-13 10-Apr-13 159 A61770 Fire Fighting Pipe 7 29-Aug-12 05-Sep-12 13-Feb-13 20-Feb-13 138 A61760 Hydro Static Test for Pipes 4 06-Sep-12 10-Sep-12 21-Feb-13 25-Feb-13 138 A61750 Sprinkler Fixing 7 20-Sep-12 27-Sep-12 26-Feb-13 05-Mar-13 130 A61810 Fire Alarm Devices 7 20-Sep-12 27-Sep-12 03-Apr-13 10-Apr-13 161 A61740 Installation of Fire Extingusher&Blanket 2 29-Sep-12 30-Sep-12 09-Apr-13 10-Apr-13 159 StaircaseStaircase 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132 Stairs 1Stairs 1 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132 A109630 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132 A109640 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132 A109650 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109660 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109670 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132 A109680 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132 Stairs 2Stairs 2 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132 A109690 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132 A109700 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132 A109710 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109720 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109730 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132 A109740 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132 Stairs 3Stairs 3 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132 A109750 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132 A109760 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132 A109770 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109780 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109790 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132 A109800 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132 Stairs 4Stairs 4 43 30-Sep-12 21-Nov-12 10-Mar-13 28-Apr-13 132 A109810 Floor Screed 3 30-Sep-12 02-Oct-12 10-Mar-13 12-Mar-13 132 A109820 Install Handrails 4 03-Oct-12 07-Oct-12 13-Mar-13 17-Mar-13 132 A109830 Ceiling 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109840 Wall 1st Coat Paint 12 08-Oct-12 21-Oct-12 18-Mar-13 31-Mar-13 132 A109850 Install Granite/Terrazo 12 22-Oct-12 06-Nov-12 01-Apr-13 14-Apr-13 132 A109860 Final Coat Paint 12 07-Nov-12 21-Nov-12 15-Apr-13 28-Apr-13 132 1st Floor1st Floor 303 11-Sep-12 08-Sep-13 06-Oct-12 02-Oct-13 21 Public AreaPublic Area 303 11-Sep-12 08-Sep-13 06-Oct-12 02-Oct-13 21 SwimmingSwimming Pool Room 146 11-Sep-12 06-Mar-13 06-Oct-12 28-Apr-13 45 FinishingFinishing Works 146 11-Sep-12 06-Mar-13 06-Oct-12 28-Apr-13 45 Wet WorWet Works 64 11-Sep-12 27-Nov-12 06-Oct-12 23-Apr-13 123 A100770 Block Works 16 11-Sep-12 29-Sep-12 06-Oct-12 23-Oct-12 21 A100730 Installation of Doors& Windows Sub-frame 2 07-Oct-12 08-Oct-12 22-Apr-13 23-Apr-13 163 A100720 Plaster Works 15 07-Oct-12 23-Oct-12 03-Nov-12 20-Nov-12 21 A100740 1st Coat Paint 21 03-Nov-12 27-Nov-12 28-Nov-12 23-Dec-12 21 Fisrt StaFisrt Stage Finishes 107 09-Oct-12 17-Feb-13 03-Apr-13 25-Apr-13 58 A100760 Installation of Doors 2 09-Oct-12 10-Oct-12 24-Apr-13 25-Apr-13 163 A100780 Doors Ironmongery 2 09-Oct-12 10-Oct-12 24-Apr-13 25-Apr-13 163 A100830 Epoxy Paint Works 7 10-Feb-13 17-Feb-13 03-Apr-13 10-Apr-13 45 Second SSecond Stage Finishes 13 18-Feb-13 04-Mar-13 11-Apr-13 25-Apr-13 45 A100750 Final Coat Paint 13 18-Feb-13 04-Mar-13 11-Apr-13 25-Apr-13 45 Final StaFinal Stage Finishes 2 05-Mar-13 06-Mar-13 27-Apr-13 28-Apr-13 45 A100820 Installation of Sinages 2 05-Mar-13 06-Mar-13 27-Apr-13 28-Apr-13 45 MEP WorkMEP Works 108 30-Sep-12 09-Feb-13 24-Oct-12 24-Apr-13 64 HVACHVAC 20 30-Sep-12 22-Oct-12 11-Feb-13 05-Mar-13 109 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work Screed Works 1st Coat Paint Floor Tiles Work Installation of Doors Doors Ironmongery Installation of Equipments Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 66 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 67. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A100860 Duct Installation & Insulation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109 A100870 Chilled Water Pipe Installation & Insulation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109 A100880 Condensate Pipe Installation 7 30-Sep-12 07-Oct-12 11-Feb-13 18-Feb-13 109 A100890 FCU Installation 5 08-Oct-12 13-Oct-12 19-Feb-13 24-Feb-13 109 A100900 Air-Outlet Installation 8 14-Oct-12 22-Oct-12 25-Feb-13 05-Mar-13 109 ElectricalElectrical 56 30-Sep-12 08-Dec-12 24-Oct-12 05-Mar-13 73 A100790 Install Conduits in Wall 6 30-Sep-12 06-Oct-12 24-Oct-12 01-Nov-12 21 A100800 Wiring for Lighting & Power 6 24-Oct-12 01-Nov-12 21-Nov-12 27-Nov-12 21 A100810 Installation of Lighting Fittings 8 28-Nov-12 08-Dec-12 25-Feb-13 05-Mar-13 73 PlumbingPlumbing 50 30-Sep-12 29-Nov-12 20-Feb-13 05-Mar-13 79 A100950 H/L Drainage Pipes Installation 8 30-Sep-12 08-Oct-12 20-Feb-13 28-Feb-13 117 A100960 H/L Hot&Cold Water Pipe Installation 8 30-Sep-12 08-Oct-12 20-Feb-13 28-Feb-13 117 A100970 Drainage&Water Pipes Testing 4 09-Oct-12 13-Oct-12 02-Mar-13 05-Mar-13 117 A100980 Floor Drain Fixning 2 28-Nov-12 29-Nov-12 04-Mar-13 05-Mar-13 79 Fire FighFire Fighting 23 30-Sep-12 28-Oct-12 13-Feb-13 24-Apr-13 149 A100940 Fire Fighting Pipe 7 30-Sep-12 07-Oct-12 13-Feb-13 20-Feb-13 111 A100930 Hydro Static Test for Pipes 4 08-Oct-12 11-Oct-12 21-Feb-13 25-Feb-13 111 A100920 Sprinkler Fixing 7 13-Oct-12 20-Oct-12 26-Feb-13 05-Mar-13 111 A100840 Fire Alarm Devices 2 21-Oct-12 22-Oct-12 01-Apr-13 02-Apr-13 133 A100910 Installation of Fire Extingusher&Blanket 5 21-Oct-12 28-Oct-12 20-Apr-13 24-Apr-13 149 SwimminSwimming Pool Equipments 60 28-Nov-12 09-Feb-13 24-Dec-12 05-Mar-13 21 A100990 Installation of GRP Tank 15 28-Nov-12 16-Dec-12 24-Dec-12 10-Jan-13 21 A101030 Installation of Heat Exchanger 15 28-Nov-12 16-Dec-12 12-Jan-13 29-Jan-13 36 A100850 Installation of Swimming Pool Pipes&Fittings 20 28-Nov-12 22-Dec-12 11-Feb-13 05-Mar-13 61 A101000 Installation of Pumps 15 17-Dec-12 03-Jan-13 12-Jan-13 29-Jan-13 21 A101040 Installation of Chemical Tank 15 17-Dec-12 03-Jan-13 30-Jan-13 16-Feb-13 36 A101010 Installation of Filter 15 05-Jan-13 21-Jan-13 30-Jan-13 16-Feb-13 21 A101050 Installation of Control Panel 15 05-Jan-13 21-Jan-13 17-Feb-13 05-Mar-13 36 A101020 Installation of Electrical Heater 15 22-Jan-13 09-Feb-13 17-Feb-13 05-Mar-13 21 Gym AreaGym Area 303 11-Sep-12 08-Sep-13 14-Jan-13 02-Oct-13 21 FinishingFinishing Works 303 11-Sep-12 08-Sep-13 14-Jan-13 02-Oct-13 21 Wet WorWet Works 15 11-Sep-12 27-Sep-12 14-Jan-13 23-Apr-13 172 A115420 Block Works 6 11-Sep-12 17-Sep-12 14-Jan-13 20-Jan-13 102 A115380 Installation of Doors& Windows Sub-frame 2 23-Sep-12 24-Sep-12 22-Apr-13 23-Apr-13 175 A115370 Plaster Works 5 23-Sep-12 27-Sep-12 30-Jan-13 04-Feb-13 105 Fisrt StaFisrt Stage Finishes 30 02-Oct-12 07-Nov-12 05-Feb-13 15-Apr-13 132 A115590 Installation of Suspended Ceiling Grid 5 02-Oct-12 07-Oct-12 05-Feb-13 10-Feb-13 102 A115390 1st Coat Paint 8 08-Oct-12 16-Oct-12 11-Feb-13 19-Feb-13 102 A115600 Suspended Ceiling Tiles 5 17-Oct-12 22-Oct-12 20-Feb-13 25-Feb-13 102 A115640 Screed Works 3 23-Oct-12 28-Oct-12 02-Apr-13 04-Apr-13 132 A115630 Wall Tiles Work 4 29-Oct-12 01-Nov-12 06-Apr-13 09-Apr-13 132 A115620 Floor Tiles Work 5 03-Nov-12 07-Nov-12 10-Apr-13 15-Apr-13 132 Second SSecond Stage Finishes 9 08-Nov-12 19-Nov-12 16-Apr-13 25-Apr-13 132 A115410 Installation of Doors 2 08-Nov-12 10-Nov-12 24-Apr-13 25-Apr-13 139 A115430 Doors Ironmongery 2 08-Nov-12 10-Nov-12 24-Apr-13 25-Apr-13 139 A115400 Final Coat Paint 3 08-Nov-12 11-Nov-12 16-Apr-13 18-Apr-13 132 A115610 Installation of Mirrors 6 12-Nov-12 19-Nov-12 20-Apr-13 25-Apr-13 132 Final StaFinal Stage Finishes 246 20-Nov-12 08-Sep-13 27-Apr-13 02-Oct-13 21 A115470 Installation of Sinages 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132 A115490 Installation of GYM Equipments 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 41 18-Sep-12 06-Nov-12 21-Jan-13 18-Apr-13 136 HVACHVAC 36 18-Sep-12 31-Oct-12 22-Jan-13 05-Mar-13 103 A115500 Duct Installation & Insulation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103 A115510 Chilled Water Pipe Installation & Insulation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103 A115520 Condensate Pipe Installation 8 18-Sep-12 26-Sep-12 22-Jan-13 31-Jan-13 103 A115530 FCU Installation 3 27-Sep-12 30-Sep-12 02-Feb-13 04-Feb-13 103 A115540 Air-Outlet Installation 6 23-Oct-12 31-Oct-12 27-Feb-13 05-Mar-13 103 ElectricalElectrical 36 18-Sep-12 31-Oct-12 26-Jan-13 05-Mar-13 103 A115440 Install Conduits in Wall 4 18-Sep-12 22-Sep-12 26-Jan-13 29-Jan-13 105 A115450 Wiring for Lighting & Power 4 29-Sep-12 02-Oct-12 06-Feb-13 10-Feb-13 106 A115460 Installation of Lighting Fittings 6 23-Oct-12 31-Oct-12 27-Feb-13 05-Mar-13 103 Fire FighFire Fighting 41 18-Sep-12 06-Nov-12 21-Jan-13 18-Apr-13 136 A115580 Fire Fighting Pipe 7 18-Sep-12 25-Sep-12 21-Jan-13 29-Jan-13 102 A115570 Hydro Static Test for Pipes 5 26-Sep-12 01-Oct-12 30-Jan-13 04-Feb-13 102 A115560 Sprinkler Fixing 7 23-Oct-12 01-Nov-12 26-Feb-13 05-Mar-13 102 A115480 Fire Alarm Devices 2 03-Nov-12 04-Nov-12 17-Apr-13 18-Apr-13 138 A115550 Installation of Fire Extingusher&Blanket 4 03-Nov-12 06-Nov-12 15-Apr-13 18-Apr-13 136 TolietsToliets 67 11-Sep-12 01-Dec-12 31-Dec-12 28-Apr-13 124 FinishingFinishing Works 67 11-Sep-12 01-Dec-12 31-Dec-12 28-Apr-13 124 Wet WorWet Works 30 11-Sep-12 15-Oct-12 31-Dec-12 11-Apr-13 147 A116360 Block Works 9 11-Sep-12 20-Sep-12 31-Dec-12 10-Jan-13 91 A116300 Installation of Doors& Windows Sub-frame 3 26-Sep-12 29-Sep-12 09-Apr-13 11-Apr-13 161 A116290 Plaster Works 8 26-Sep-12 04-Oct-12 16-Jan-13 26-Jan-13 91 A116600 Wall Tiles Work (Wet Area) 9 06-Oct-12 15-Oct-12 27-Jan-13 05-Feb-13 91 Fisrt StaFisrt Stage Finishes 21 16-Oct-12 11-Nov-12 06-Feb-13 11-Apr-13 126 A116590 Screed Works 3 16-Oct-12 18-Oct-12 06-Feb-13 09-Feb-13 91 A116320 Water Proofing for Wet Area 4 20-Oct-12 23-Oct-12 10-Feb-13 13-Feb-13 91 A116630 Installation of Suspended Ceiling Grid (Wet Area) 5 24-Oct-12 31-Oct-12 14-Feb-13 19-Feb-13 91 A116620 Suspended Ceiling Tiles (Wet Area) 5 01-Nov-12 06-Nov-12 20-Feb-13 25-Feb-13 91 A116610 Floor Tiles Work (Wet Area) 4 07-Nov-12 11-Nov-12 08-Apr-13 11-Apr-13 126 Second SSecond Stage Finishes 10 14-Nov-12 26-Nov-12 13-Apr-13 23-Apr-13 124 A116330 Installation of Doors 3 14-Nov-12 18-Nov-12 13-Apr-13 15-Apr-13 124 A116370 Doors Ironmongery 3 14-Nov-12 18-Nov-12 21-Apr-13 23-Apr-13 131 A116350 Installation of Vanity Counter 3 19-Nov-12 21-Nov-12 21-Apr-13 23-Apr-13 128 A116570 Installation of Toliets Accessories 5 19-Nov-12 24-Nov-12 18-Apr-13 23-Apr-13 126 A116340 Installation of Mirrors 7 19-Nov-12 26-Nov-12 16-Apr-13 23-Apr-13 124 Final StaFinal Stage Finishes 4 27-Nov-12 01-Dec-12 24-Apr-13 28-Apr-13 124 A116310 Final Coat Paint 2 27-Nov-12 28-Nov-12 24-Apr-13 25-Apr-13 124 A116580 Installation of Sinages 2 29-Nov-12 01-Dec-12 27-Apr-13 28-Apr-13 124 MEP WorkMEP Works 50 22-Sep-12 21-Nov-12 12-Jan-13 23-Apr-13 128 HVACHVAC 45 22-Sep-12 14-Nov-12 07-Feb-13 05-Mar-13 91 A116380 Duct Installation & Insulation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113 A116390 Chilled Water Pipe Installation & Insulation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113 A116400 Condensate Pipe Installation 4 22-Sep-12 25-Sep-12 07-Feb-13 11-Feb-13 113 A116410 FCU Installation 2 26-Sep-12 27-Sep-12 12-Feb-13 13-Feb-13 113 A116420 Air-Outlet Installation 7 07-Nov-12 14-Nov-12 26-Feb-13 05-Mar-13 91 ElectricalElectrical 43 22-Sep-12 12-Nov-12 12-Jan-13 05-Mar-13 93 A116430 Install Conduits in Wall 4 22-Sep-12 25-Sep-12 12-Jan-13 15-Jan-13 91 A116440 Wiring for Lighting & Power 4 06-Oct-12 09-Oct-12 10-Feb-13 13-Feb-13 103 A116450 Installation of Lighting Fittings 5 07-Nov-12 12-Nov-12 28-Feb-13 05-Mar-13 93 PlumbingPlumbing 50 22-Sep-12 21-Nov-12 13-Jan-13 23-Apr-13 128 A116460 Drainge Pipes in Wall 3 22-Sep-12 24-Sep-12 13-Jan-13 15-Jan-13 92 A116530 Water Pipes in Wall 3 22-Sep-12 24-Sep-12 13-Jan-13 15-Jan-13 92 A116470 H/L Drainage Pipes Installation 4 22-Sep-12 25-Sep-12 06-Feb-13 10-Feb-13 112 A116480 H/L Hot&Cold Water Pipe Installation 4 22-Sep-12 25-Sep-12 06-Feb-13 10-Feb-13 112 A116500 ElectricalWater Heater Installation 2 26-Sep-12 27-Sep-12 12-Feb-13 13-Feb-13 113 A116490 Drainage&Water Pipes Testing 3 26-Sep-12 29-Sep-12 11-Feb-13 13-Feb-13 112 A116510 Floor Drain Fixning 2 18-Oct-12 20-Oct-12 04-Mar-13 05-Mar-13 111 A116520 Installation of Sanitaryware 3 19-Nov-12 21-Nov-12 21-Apr-13 23-Apr-13 128 Fire FighFire Fighting 42 22-Sep-12 11-Nov-12 07-Feb-13 23-Apr-13 136 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Installation of GRP Tank Installation of Heat Exchanger Installation of Swimming Pool Pipes&Fittings Installation of Pumps Installation of Chemical Tank Installation of Filter Installation of Control Panel Installation of Electrical Heater Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Mirrors Installation of Sinages Installation of GYM Eq Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Doors Doors Ironmongery Installation of Vanity Counter Installation of Toliets Accessories Installation of Mirrors Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation ElectricalWater Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Sanitaryware Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 67 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 68. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A116560 Fire Fighting Pipe 3 22-Sep-12 24-Sep-12 07-Feb-13 10-Feb-13 113 A116550 Hydro Static Test for Pipes 3 25-Sep-12 27-Sep-12 11-Feb-13 13-Feb-13 113 A116540 Sprinkler Fixing 3 07-Nov-12 10-Nov-12 03-Mar-13 05-Mar-13 95 A116640 Fire Alarm Devices 4 07-Nov-12 11-Nov-12 20-Apr-13 23-Apr-13 136 House KeeHouse Keeping Room 303 11-Sep-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 303 11-Sep-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 11-Sep-12 10-Oct-12 20-Jan-13 22-Apr-13 160 A116730 Block Works 4 11-Sep-12 15-Sep-12 20-Jan-13 23-Jan-13 107 A116660 Installation of Doors& Windows Sub-frame 1 20-Sep-12 20-Sep-12 22-Apr-13 22-Apr-13 177 A116650 Plaster Works 4 20-Sep-12 24-Sep-12 30-Jan-13 03-Feb-13 107 A116680 Installation of Suspended Ceiling Grid 7 30-Sep-12 07-Oct-12 09-Feb-13 16-Feb-13 107 A116670 1st Coat Paint 3 08-Oct-12 10-Oct-12 17-Feb-13 19-Feb-13 107 Fisrt StaFisrt Stage Finishes 16 11-Oct-12 31-Oct-12 20-Feb-13 22-Apr-13 144 A116690 Suspended Ceiling Tiles 7 11-Oct-12 18-Oct-12 20-Feb-13 27-Feb-13 107 A116970 Screed Works 5 20-Oct-12 24-Oct-12 02-Mar-13 06-Mar-13 108 A116710 Floor Tiles Work 4 28-Oct-12 31-Oct-12 18-Apr-13 22-Apr-13 144 Second SSecond Stage Finishes 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133 A116720 Installation of Windows&Doors 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133 A116740 Doors Ironmongery 1 14-Nov-12 14-Nov-12 23-Apr-13 23-Apr-13 133 Final StaFinal Stage Finishes 249 17-Nov-12 08-Sep-13 24-Apr-13 02-Oct-13 21 A116700 Final Coat Paint 2 17-Nov-12 18-Nov-12 24-Apr-13 25-Apr-13 133 A116960 Installation of Sinages 2 19-Nov-12 20-Nov-12 27-Apr-13 28-Apr-13 133 A116750 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 16-Sep-12 28-Oct-12 26-Jan-13 24-Apr-13 149 HVACHVAC 32 16-Sep-12 22-Oct-12 29-Jan-13 05-Mar-13 109 A116760 Duct Installation & Insulation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110 A116770 Chilled Water Pipe Installation & Insulation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110 A116780 Condensate Pipe Installation 7 16-Sep-12 23-Sep-12 29-Jan-13 05-Feb-13 110 A116790 FCU Installation 2 24-Sep-12 25-Sep-12 06-Feb-13 07-Feb-13 110 A116800 Air-Outlet Installation 3 20-Oct-12 22-Oct-12 03-Mar-13 05-Mar-13 109 ElectricalElectrical 34 16-Sep-12 24-Oct-12 26-Jan-13 05-Mar-13 107 A116810 Install Conduits in Wall 4 16-Sep-12 19-Sep-12 26-Jan-13 29-Jan-13 107 A116820 Install Cable Trays & Trunking 4 16-Sep-12 19-Sep-12 28-Jan-13 31-Jan-13 109 A116840 Cable Laying for Power 4 20-Sep-12 24-Sep-12 12-Feb-13 16-Feb-13 118 A116830 Wiring for Lighting & Power 4 25-Sep-12 29-Sep-12 04-Feb-13 07-Feb-13 107 A116860 Installation of Sockets 3 20-Oct-12 22-Oct-12 03-Mar-13 05-Mar-13 109 A116850 Installation of Lighting Fittings 5 20-Oct-12 24-Oct-12 28-Feb-13 05-Mar-13 107 PlumbingPlumbing 33 16-Sep-12 23-Oct-12 31-Jan-13 05-Mar-13 108 A116870 H/L Drainage Pipes Installation 3 16-Sep-12 18-Sep-12 31-Jan-13 03-Feb-13 112 A116880 H/L Hot&Cold Water Pipe Installation 3 16-Sep-12 18-Sep-12 31-Jan-13 03-Feb-13 112 A116890 Drainage&Water Pipes Testing 3 19-Sep-12 22-Sep-12 04-Feb-13 06-Feb-13 112 A116900 ElectricalWater Heater Installation 4 19-Sep-12 23-Sep-12 04-Feb-13 07-Feb-13 112 A116910 Floor Drain Fixning 2 22-Oct-12 23-Oct-12 04-Mar-13 05-Mar-13 108 Fire FighFire Fighting 35 16-Sep-12 28-Oct-12 31-Jan-13 24-Apr-13 149 A116950 Fire Fighting Pipe 4 16-Sep-12 19-Sep-12 31-Jan-13 04-Feb-13 112 A116940 Hydro Static Test for Pipes 3 20-Sep-12 23-Sep-12 05-Feb-13 07-Feb-13 112 A116930 Sprinkler Fixing 4 20-Oct-12 23-Oct-12 02-Mar-13 05-Mar-13 108 A116980 Fire Alarm Devices 4 20-Oct-12 23-Oct-12 20-Apr-13 23-Apr-13 150 A116920 Installation of Fire Extingusher&Blanket 2 24-Oct-12 28-Oct-12 23-Apr-13 24-Apr-13 149 PlantersPlanters 153 11-Sep-12 14-Mar-13 12-Nov-12 28-Apr-13 38 FinishingFinishing Works 153 11-Sep-12 14-Mar-13 12-Nov-12 28-Apr-13 38 A1033 Water Proof Membrane 20 11-Sep-12 03-Oct-12 12-Nov-12 06-Dec-12 51 A1034 Drainage Gravel 20 20-Oct-12 13-Nov-12 08-Dec-12 30-Dec-12 38 A1035 Geptextile Membrane 20 14-Nov-12 09-Dec-12 31-Dec-12 23-Jan-13 38 A1036 Sweet Soil 20 10-Dec-12 02-Jan-13 26-Jan-13 17-Feb-13 38 A1043 Installation of Sand Stone Coping 9 03-Jan-13 13-Jan-13 18-Apr-13 28-Apr-13 89 A107910 Installation of Lighitngs 30 03-Jan-13 07-Feb-13 25-Mar-13 28-Apr-13 68 A1037 Installation of Planting Items 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38 A1047 Instllation of Wood Gazebo 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38 A107880 Installation of Irrigation System 60 03-Jan-13 14-Mar-13 18-Feb-13 28-Apr-13 38 Electrical RElectrical Room / Telephone Room 57 11-Sep-12 19-Nov-12 31-Jan-13 28-Apr-13 134 FinishingFinishing Works 57 11-Sep-12 19-Nov-12 31-Jan-13 28-Apr-13 134 Wet WorWet Works 14 11-Sep-12 26-Sep-12 31-Jan-13 23-Apr-13 173 A104910 Block Works 3 11-Sep-12 13-Sep-12 31-Jan-13 03-Feb-13 116 A104870 Installation of Doors& Windows Sub-frame 1 17-Sep-12 17-Sep-12 23-Apr-13 23-Apr-13 181 A104860 Plaster Works 4 17-Sep-12 20-Sep-12 06-Feb-13 10-Feb-13 116 A104880 1st Coat Paint 3 24-Sep-12 26-Sep-12 13-Feb-13 16-Feb-13 116 Fisrt StaFisrt Stage Finishes 26 15-Oct-12 17-Nov-12 22-Apr-13 25-Apr-13 134 A104970 Epoxy Paint Works 2 15-Oct-12 16-Oct-12 22-Apr-13 23-Apr-13 156 A104900 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A104920 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 Second SSecond Stage Finishes 2 17-Oct-12 18-Oct-12 24-Apr-13 25-Apr-13 156 A104890 Final Coat Paint 2 17-Oct-12 18-Oct-12 24-Apr-13 25-Apr-13 156 Final StaFinal Stage Finishes 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134 A104960 Installation of Sinages 2 18-Nov-12 19-Nov-12 27-Apr-13 28-Apr-13 134 MEP WorkMEP Works 26 15-Sep-12 14-Oct-12 04-Feb-13 21-Apr-13 156 HVACHVAC 2 27-Sep-12 29-Sep-12 04-Mar-13 05-Mar-13 129 A105000 Air-Outlet Installation 2 27-Sep-12 29-Sep-12 04-Mar-13 05-Mar-13 129 ElectricalElectrical 26 15-Sep-12 14-Oct-12 04-Feb-13 05-Mar-13 116 A104930 Install Conduits in Wall 2 15-Sep-12 16-Sep-12 04-Feb-13 05-Feb-13 116 A104940 Wiring for Lighting & Power 2 22-Sep-12 23-Sep-12 11-Feb-13 12-Feb-13 116 A104990 Installation of SMDBs 7 27-Sep-12 04-Oct-12 24-Feb-13 03-Mar-13 122 A104950 Installation of Lighting Fittings 2 06-Oct-12 07-Oct-12 04-Mar-13 05-Mar-13 122 A114780 Installation of Telephone System 15 27-Sep-12 14-Oct-12 17-Feb-13 05-Mar-13 116 Fire FighFire Fighting 2 08-Oct-12 09-Oct-12 20-Apr-13 21-Apr-13 160 A104980 Fire Alarm Devices 2 08-Oct-12 09-Oct-12 20-Apr-13 21-Apr-13 160 StaircaseStaircase 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119 Stairs 1Stairs 1 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119 A109870 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119 A109880 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119 A109890 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A109900 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A109910 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119 A109920 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119 Stairs 2Stairs 2 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119 A109930 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119 A109940 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119 A109950 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A109960 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A109970 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119 A109980 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119 Stairs 3Stairs 3 43 15-Oct-12 08-Dec-12 10-Mar-13 28-Apr-13 119 A109990 Floor Screed 3 15-Oct-12 17-Oct-12 10-Mar-13 12-Mar-13 119 A110000 Install Handrails 4 18-Oct-12 22-Oct-12 13-Mar-13 17-Mar-13 119 A110010 Ceiling 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A110020 Wall 1st Coat Paint 12 23-Oct-12 07-Nov-12 18-Mar-13 31-Mar-13 119 A110030 Install Granite/Terrazo 12 08-Nov-12 22-Nov-12 01-Apr-13 14-Apr-13 119 A110040 Final Coat Paint 12 24-Nov-12 08-Dec-12 15-Apr-13 28-Apr-13 119 Sky LightSky Light 30 27-Dec-12 02-Feb-13 25-Mar-13 28-Apr-13 73 A1156 Instalaltion of Sky Light 30 27-Dec-12 02-Feb-13 25-Mar-13 28-Apr-13 73 Rooms AreaRooms Area 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Water Proof Membrane Drainage Gravel Geptextile Membrane Sweet Soil Installation of Sand Stone Coping Installation of Lighitngs Installation of Planting Items Instllation of Wood Gazebo Installation of Irrigation System Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Instalaltion of Sky Light Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 68 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 69. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Guest RooGuest Rooms 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21 FinishingFinishing Works 303 11-Sep-12 08-Sep-13 29-Oct-12 02-Oct-13 21 Wet WorWet Works 71 11-Sep-12 06-Dec-12 29-Oct-12 10-Mar-13 78 A12990 Block Works 14 11-Sep-12 26-Sep-12 29-Oct-12 13-Nov-12 39 A12840 Plaster Works 23 01-Oct-12 29-Oct-12 19-Nov-12 16-Dec-12 39 A12850 Installation of Doors& Windows Sub-frame 26 01-Oct-12 01-Nov-12 09-Feb-13 10-Mar-13 106 A13320 Wall Tiles Work (Wet Area) 16 15-Oct-12 04-Nov-12 10-Jan-13 29-Jan-13 70 A12870 Installation of Suspended Ceiling Grid (Dry Area) 15 03-Nov-12 20-Nov-12 20-Dec-12 07-Jan-13 39 A12860 1st Coat Paint 21 11-Nov-12 06-Dec-12 29-Dec-12 22-Jan-13 39 Fisrt StaFisrt Stage Finishes 37 03-Dec-12 15-Jan-13 19-Jan-13 01-Apr-13 64 A12880 Suspended Ceiling Tiles (DryArea) 7 03-Dec-12 10-Dec-12 19-Jan-13 27-Jan-13 39 A12920 Installation of Wardrobes 12 08-Dec-12 20-Dec-12 23-Jan-13 06-Feb-13 39 A13310 Screed Works 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39 A12910 Water Proofing for Wet Area 8 20-Dec-12 29-Dec-12 06-Feb-13 14-Feb-13 39 A12900 Floor & Wall Tiles Work (Dry Area) 12 19-Dec-12 02-Jan-13 19-Mar-13 01-Apr-13 75 A13350 Installation of Suspended Ceiling Grid (Wet Area) 6 26-Dec-12 02-Jan-13 12-Feb-13 18-Feb-13 39 A13340 Suspended Ceiling Tiles (Wet Area) 7 31-Dec-12 08-Jan-13 17-Feb-13 24-Feb-13 39 A13330 Floor Tiles Work (Wet Area) 9 06-Jan-13 15-Jan-13 05-Mar-13 14-Mar-13 49 Second SSecond Stage Finishes 17 12-Jan-13 31-Jan-13 11-Mar-13 01-Apr-13 51 A12930 Installation of Windows&Doors 11 12-Jan-13 23-Jan-13 11-Mar-13 23-Mar-13 49 A12970 Installation of Balustrades& Handrails 7 17-Jan-13 26-Jan-13 25-Mar-13 01-Apr-13 56 A13000 Doors Ironmongery 13 12-Jan-13 27-Jan-13 18-Mar-13 01-Apr-13 55 A12940 Installation of Mirrors 9 17-Jan-13 28-Jan-13 23-Mar-13 01-Apr-13 54 A12980 Installation of Vanity Counter 9 17-Jan-13 28-Jan-13 23-Mar-13 01-Apr-13 54 A13290 Installation of Toliets Accessories 12 17-Jan-13 31-Jan-13 19-Mar-13 01-Apr-13 51 Final StaFinal Stage Finishes 184 04-Feb-13 08-Sep-13 02-Apr-13 02-Oct-13 21 A12890 Final Coat Paint 11 04-Feb-13 16-Feb-13 02-Apr-13 14-Apr-13 49 A12960 Installation of Carpets 7 21-Mar-13 28-Mar-13 15-Apr-13 22-Apr-13 21 A13300 Installation of Sinages 5 30-Mar-13 03-Apr-13 23-Apr-13 28-Apr-13 21 A13010 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 112 19-Sep-12 03-Feb-13 06-Nov-12 14-Apr-13 60 HVACHVAC 90 27-Sep-12 15-Jan-13 26-Nov-12 05-Mar-13 41 A13040 Condensate Pipe Installation 10 27-Sep-12 08-Oct-12 28-Nov-12 10-Dec-12 50 A13020 Duct Installation & Insulation 12 27-Sep-12 10-Oct-12 26-Nov-12 10-Dec-12 48 A13030 Chilled Water Pipe Installation & Insulation 12 27-Sep-12 10-Oct-12 26-Nov-12 10-Dec-12 48 A13050 FCU Installation 8 11-Oct-12 20-Oct-12 11-Dec-12 19-Dec-12 48 A13060 Air-Outlet Installation 6 09-Jan-13 15-Jan-13 27-Feb-13 05-Mar-13 41 ElectricalElectrical 99 19-Sep-12 17-Jan-13 06-Nov-12 05-Mar-13 39 A13070 Install Conduits in Wall 10 19-Sep-12 30-Sep-12 06-Nov-12 18-Nov-12 39 A13080 Install Cable Trays & Trunking 10 19-Sep-12 30-Sep-12 03-Dec-12 13-Dec-12 60 A13120 Cable Laying for Low Current System 6 25-Sep-12 01-Oct-12 31-Dec-12 07-Jan-13 79 A13130 Cable Laying for Power 6 25-Sep-12 01-Oct-12 31-Dec-12 07-Jan-13 79 A13090 Wiring for Lighting & Power 14 15-Oct-12 01-Nov-12 04-Dec-12 19-Dec-12 39 A13100 Wiring for Low Current System 14 15-Oct-12 01-Nov-12 04-Dec-12 19-Dec-12 39 A13110 DB installation,Dressing & Termination 14 24-Nov-12 10-Dec-12 10-Jan-13 27-Jan-13 39 A13160 Installation of Sockets 7 09-Jan-13 16-Jan-13 26-Feb-13 05-Mar-13 40 A13150 Installation of Lighting Fittings 8 09-Jan-13 17-Jan-13 25-Feb-13 05-Mar-13 39 PlumbingPlumbing 111 20-Sep-12 03-Feb-13 12-Nov-12 01-Apr-13 49 A13170 Drainge Pipes in Wall 10 20-Sep-12 01-Oct-12 12-Nov-12 24-Nov-12 43 A13240 Water Pipes in Wall 10 20-Sep-12 01-Oct-12 12-Nov-12 24-Nov-12 43 A13180 H/L Drainage Pipes Installation 10 27-Sep-12 08-Oct-12 27-Jan-13 06-Feb-13 98 A13190 H/L Hot&Cold Water Pipe Installation 10 27-Sep-12 08-Oct-12 27-Jan-13 06-Feb-13 98 A13200 Drainage&Water Pipes Testing 4 09-Oct-12 13-Oct-12 07-Feb-13 11-Feb-13 98 A13210 ElectricalWater Heater Installation 4 09-Oct-12 13-Oct-12 07-Feb-13 11-Feb-13 98 A13220 Floor Drain Fixning 8 16-Dec-12 24-Dec-12 25-Feb-13 05-Mar-13 59 A13230 Installation of Sanitaryware 8 26-Jan-13 03-Feb-13 24-Mar-13 01-Apr-13 49 Fire FighFire Fighting 97 27-Sep-12 23-Jan-13 05-Dec-12 14-Apr-13 68 A13280 Fire Fighting Pipe 10 27-Sep-12 08-Oct-12 05-Dec-12 16-Dec-12 55 A13270 Hydro Static Test for Pipes 3 09-Oct-12 11-Oct-12 17-Dec-12 19-Dec-12 55 A13260 Sprinkler Fixing 8 09-Jan-13 17-Jan-13 25-Feb-13 05-Mar-13 39 A13360 Fire Alarm Devices 8 09-Jan-13 17-Jan-13 24-Mar-13 01-Apr-13 62 A13250 Installation of Fire Extingusher&Blanket 5 19-Jan-13 23-Jan-13 09-Apr-13 14-Apr-13 68 2nd Floor2nd Floor 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Public AreaPublic Area 290 26-Sep-12 08-Sep-13 22-Dec-12 02-Oct-13 21 SwimmingSwimming Pool Deck 290 26-Sep-12 08-Sep-13 12-Feb-13 02-Oct-13 21 FinishingFinishing Works 290 26-Sep-12 08-Sep-13 12-Feb-13 02-Oct-13 21 A104710 Block Works 5 26-Sep-12 01-Oct-12 12-Feb-13 17-Feb-13 113 A104720 Plaster Works 7 02-Oct-12 09-Oct-12 18-Feb-13 25-Feb-13 113 A104730 1st Coat Paint 7 10-Oct-12 17-Oct-12 26-Feb-13 05-Mar-13 113 A104700 Installation of Metal Kitchen Cabinet , Bar , B.B.Q 4 18-Oct-12 22-Oct-12 24-Apr-13 28-Apr-13 155 A104790 Instaaltion of Wooden Pergola 15 18-Oct-12 06-Nov-12 06-Mar-13 23-Mar-13 113 A104760 Floor Tiles Work 18 07-Nov-12 28-Nov-12 24-Mar-13 13-Apr-13 113 A104740 Installation of Doors 3 29-Nov-12 03-Dec-12 14-Apr-13 16-Apr-13 113 A105010 Installation of Lightings 5 29-Nov-12 05-Dec-12 23-Apr-13 28-Apr-13 121 A104750 Doors Ironmongery 3 04-Dec-12 06-Dec-12 17-Apr-13 20-Apr-13 113 A104770 Final Coat Paint 5 08-Dec-12 12-Dec-12 21-Apr-13 25-Apr-13 113 A104780 Installation of Sinages 2 13-Dec-12 15-Dec-12 27-Apr-13 28-Apr-13 113 A104800 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 SwimmingSwimming Pool 75 26-Sep-12 26-Dec-12 31-Jan-13 28-Apr-13 103 FinishingFinishing Works 75 26-Sep-12 26-Dec-12 31-Jan-13 28-Apr-13 103 A104620 Pouring of Screed 5 26-Sep-12 01-Oct-12 31-Jan-13 05-Feb-13 103 A104630 Laying of Waterproofing 5 02-Oct-12 07-Oct-12 06-Feb-13 11-Feb-13 103 A104640 Pouring of Guniting 6 08-Oct-12 14-Oct-12 12-Feb-13 18-Feb-13 103 A104650 Laying of Waterproofing 5 15-Oct-12 20-Oct-12 19-Feb-13 24-Feb-13 103 A104660 Waterproofing Plastering 20 21-Oct-12 14-Nov-12 25-Feb-13 19-Mar-13 103 A104670 Fix the Tiles 25 17-Nov-12 16-Dec-12 20-Mar-13 17-Apr-13 103 A104680 Installation of Stairs - Gratings -Nozzles 9 17-Dec-12 26-Dec-12 18-Apr-13 28-Apr-13 103 A104690 Installatiof of Lights 9 17-Dec-12 26-Dec-12 18-Apr-13 28-Apr-13 103 PlantersPlanters 116 26-Sep-12 14-Feb-13 22-Dec-12 28-Apr-13 62 FinishingFinishing Works 116 26-Sep-12 14-Feb-13 22-Dec-12 28-Apr-13 62 A104810 Water Proof Membrane 12 26-Sep-12 09-Oct-12 22-Dec-12 05-Jan-13 70 A104820 Drainage Gravel 12 20-Oct-12 04-Nov-12 06-Jan-13 19-Jan-13 62 A104830 Geptextile Membrane 12 05-Nov-12 19-Nov-12 20-Jan-13 03-Feb-13 62 A104840 Sweet Soil 12 20-Nov-12 04-Dec-12 04-Feb-13 17-Feb-13 62 A107920 Installation of Lighitngs 30 05-Dec-12 09-Jan-13 25-Mar-13 28-Apr-13 92 A104850 Instllation of Planting Items 60 05-Dec-12 14-Feb-13 18-Feb-13 28-Apr-13 62 A105020 Installation of Irrigation System 60 05-Dec-12 14-Feb-13 18-Feb-13 28-Apr-13 62 StaircaseStaircase 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108 Stairs 1Stairs 1 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108 A110110 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108 A110120 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108 A110130 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 A110140 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 A110150 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108 A110160 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108 Stairs 2Stairs 2 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108 A110170 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108 A110180 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108 A110190 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 A110200 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Installation of Balustrades& Handrails Doors Ironmongery Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works 1st Coat Paint Installation of Metal Kitchen Cabinet , Bar , B.B.Q Instaaltion of Wooden Pergola Floor Tiles Work Installation of Doors Installation of Lightings Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Pouring of Screed Laying of Waterproofing Pouring of Guniting Laying of Waterproofing Waterproofing Plastering Fix the Tiles Installation of Stairs - Gratings -Nozzles Installatiof of Lights Water Proof Membrane Drainage Gravel Geptextile Membrane Sweet Soil Installation of Lighitngs Instllation of Planting Items Installation of Irrigation System Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 69 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 70. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A110210 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108 A110220 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108 Stairs 3Stairs 3 43 30-Oct-12 20-Dec-12 10-Mar-13 28-Apr-13 108 A110230 Floor Screed 3 30-Oct-12 01-Nov-12 10-Mar-13 12-Mar-13 108 A110240 Install Handrails 4 03-Nov-12 06-Nov-12 13-Mar-13 17-Mar-13 108 A110250 Ceiling 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 A110260 Wall 1st Coat Paint 12 07-Nov-12 21-Nov-12 18-Mar-13 31-Mar-13 108 A110270 Install Granite/Terrazo 12 22-Nov-12 06-Dec-12 01-Apr-13 14-Apr-13 108 A110280 Final Coat Paint 12 08-Dec-12 20-Dec-12 15-Apr-13 28-Apr-13 108 Rooms AreaRooms Area 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Guest RooGuest Rooms 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21 FinishingFinishing Works 290 26-Sep-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Wet WorWet Works 78 26-Sep-12 30-Dec-12 21-Oct-12 20-Mar-13 67 A92010 Block Works 12 26-Sep-12 09-Oct-12 21-Oct-12 05-Nov-12 21 A91870 Plaster Works 31 18-Oct-12 26-Nov-12 14-Nov-12 22-Dec-12 21 A91880 Installation of Doors& Windows Sub-frame 22 04-Nov-12 29-Nov-12 24-Feb-13 20-Mar-13 92 A92340 Wall Tiles Work (Wet Area) 22 07-Nov-12 04-Dec-12 02-Jan-13 28-Jan-13 45 A91900 Installation of Suspended Ceiling Grid (Dry Area) 10 27-Nov-12 09-Dec-12 23-Dec-12 03-Jan-13 21 A91890 1st Coat Paint 22 05-Dec-12 30-Dec-12 30-Dec-12 26-Jan-13 21 Fisrt StaFisrt Stage Finishes 37 24-Dec-12 06-Feb-13 19-Jan-13 10-Apr-13 54 A91910 Suspended Ceiling Tiles (DryArea) 8 24-Dec-12 02-Jan-13 19-Jan-13 28-Jan-13 21 A91950 Installation of Wardrobes 7 30-Dec-12 07-Jan-13 26-Jan-13 02-Feb-13 21 A92330 Screed Works 15 03-Jan-13 20-Jan-13 29-Jan-13 14-Feb-13 21 A91940 Water Proofing for Wet Area 11 12-Jan-13 23-Jan-13 06-Feb-13 18-Feb-13 21 A92370 Installation of Suspended Ceiling Grid (Wet Area) 7 16-Jan-13 23-Jan-13 11-Feb-13 18-Feb-13 21 A91930 Floor & Wall Tiles Work (Dry Area) 12 12-Jan-13 26-Jan-13 28-Mar-13 10-Apr-13 64 A92360 Suspended Ceiling Tiles (Wet Area) 7 22-Jan-13 30-Jan-13 17-Feb-13 24-Feb-13 21 A92350 Floor Tiles Work (Wet Area) 8 29-Jan-13 06-Feb-13 16-Mar-13 24-Mar-13 39 Second SSecond Stage Finishes 18 04-Feb-13 24-Feb-13 21-Mar-13 17-Apr-13 45 A91960 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 21-Mar-13 28-Mar-13 39 A92020 Doors Ironmongery 7 04-Feb-13 11-Feb-13 03-Apr-13 10-Apr-13 50 A91990 Installation of Balustrades& Handrails 7 12-Feb-13 19-Feb-13 03-Apr-13 10-Apr-13 43 A92310 Installation of Toliets Accessories 12 09-Feb-13 21-Feb-13 04-Apr-13 17-Apr-13 47 A92000 Installation of Vanity Counter 10 12-Feb-13 23-Feb-13 31-Mar-13 10-Apr-13 40 A91970 Installation of Mirrors 11 12-Feb-13 24-Feb-13 30-Mar-13 10-Apr-13 39 Final StaFinal Stage Finishes 166 25-Feb-13 08-Sep-13 11-Apr-13 02-Oct-13 21 A91920 Final Coat Paint 8 25-Feb-13 05-Mar-13 11-Apr-13 20-Apr-13 39 A91980 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A92320 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A92030 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 113 06-Oct-12 20-Feb-13 06-Nov-12 20-Apr-13 50 HVACHVAC 97 10-Oct-12 06-Feb-13 28-Nov-12 05-Mar-13 23 A92060 Condensate Pipe Installation 10 10-Oct-12 21-Oct-12 01-Dec-12 12-Dec-12 41 A92040 Duct Installation & Insulation 12 10-Oct-12 23-Oct-12 28-Nov-12 12-Dec-12 39 A92050 Chilled Water Pipe Installation & Insulation 12 10-Oct-12 23-Oct-12 28-Nov-12 12-Dec-12 39 A92070 FCU Installation 8 24-Oct-12 04-Nov-12 13-Dec-12 22-Dec-12 39 A92080 Air-Outlet Installation 6 31-Jan-13 06-Feb-13 27-Feb-13 05-Mar-13 23 ElectricalElectrical 99 10-Oct-12 09-Feb-13 06-Nov-12 05-Mar-13 21 A92090 Install Conduits in Wall 14 10-Oct-12 28-Oct-12 06-Nov-12 22-Nov-12 21 A92100 Install Cable Trays & Trunking 14 10-Oct-12 28-Oct-12 04-Dec-12 19-Dec-12 43 A92140 Cable Laying for Low Current System 6 29-Oct-12 04-Nov-12 27-Dec-12 03-Jan-13 49 A92150 Cable Laying for Power 6 29-Oct-12 04-Nov-12 27-Dec-12 03-Jan-13 49 A92110 Wiring for Lighting & Power 8 07-Nov-12 17-Nov-12 15-Dec-12 23-Dec-12 30 A92120 Wiring for Low Current System 8 07-Nov-12 17-Nov-12 15-Dec-12 23-Dec-12 30 A92130 DB installation,Dressing & Termination 14 17-Dec-12 02-Jan-13 12-Jan-13 28-Jan-13 21 A92180 Installation of Sockets 7 31-Jan-13 07-Feb-13 26-Feb-13 05-Mar-13 22 A92170 Installation of Lighting Fittings 8 31-Jan-13 09-Feb-13 25-Feb-13 05-Mar-13 21 PlumbingPlumbing 113 06-Oct-12 20-Feb-13 06-Nov-12 10-Apr-13 42 A92190 Drainge Pipes in Wall 14 06-Oct-12 21-Oct-12 06-Nov-12 22-Nov-12 25 A92200 H/L Drainage Pipes Installation 10 10-Oct-12 21-Oct-12 22-Jan-13 03-Feb-13 84 A92210 H/L Hot&Cold Water Pipe Installation 10 10-Oct-12 21-Oct-12 22-Jan-13 03-Feb-13 84 A92260 Water Pipes in Wall 14 06-Oct-12 21-Oct-12 06-Nov-12 22-Nov-12 25 A92220 Drainage&Water Pipes Testing 4 22-Oct-12 28-Oct-12 04-Feb-13 07-Feb-13 84 A92230 ElectricalWater Heater Installation 6 22-Oct-12 30-Oct-12 04-Feb-13 10-Feb-13 84 A92240 Floor Drain Fixning 8 06-Jan-13 14-Jan-13 25-Feb-13 05-Mar-13 42 A92250 Installation of Sanitaryware 8 12-Feb-13 20-Feb-13 02-Apr-13 10-Apr-13 42 Fire FighFire Fighting 104 10-Oct-12 14-Feb-13 08-Dec-12 20-Apr-13 55 A92300 Fire Fighting Pipe 10 10-Oct-12 21-Oct-12 08-Dec-12 18-Dec-12 46 A92290 Hydro Static Test for Pipes 3 22-Oct-12 24-Oct-12 19-Dec-12 22-Dec-12 46 A92280 Sprinkler Fixing 8 31-Jan-13 09-Feb-13 25-Feb-13 05-Mar-13 21 A92380 Fire Alarm Devices 8 31-Jan-13 09-Feb-13 02-Apr-13 10-Apr-13 52 A92270 Installation of Fire Extingusher&Blanket 5 10-Feb-13 14-Feb-13 15-Apr-13 20-Apr-13 55 3rd Floor3rd Floor 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Public AreaPublic Area 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Lift LobbyLift Lobby - Corridor 153 09-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14 FinishingFinishing Works 153 09-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14 Wet WorWet Works 34 09-Oct-12 20-Nov-12 21-Jan-13 27-Mar-13 106 A95380 Block Works 8 09-Oct-12 17-Oct-12 21-Jan-13 30-Jan-13 84 A95320 Plaster Works 7 21-Oct-12 30-Oct-12 03-Feb-13 10-Feb-13 84 A95340 Installation of Suspended Ceiling Grid 6 05-Nov-12 11-Nov-12 16-Feb-13 21-Feb-13 84 A95350 Suspended Ceiling Tiles 6 12-Nov-12 19-Nov-12 23-Feb-13 28-Feb-13 84 A95630 MDF for Lift Lobby Wall 7 12-Nov-12 20-Nov-12 20-Mar-13 27-Mar-13 106 Fisrt StaFisrt Stage Finishes 12 21-Nov-12 05-Dec-12 28-Mar-13 06-Apr-13 102 A95610 Screed Works 3 21-Nov-12 24-Nov-12 28-Mar-13 31-Mar-13 106 A95330 1st Coat Paint 5 29-Nov-12 05-Dec-12 01-Apr-13 06-Apr-13 102 Second SSecond Stage Finishes 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119 A95360 Installation of Doors 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119 A95390 Doors Ironmongery 2 06-Dec-12 08-Dec-12 27-Apr-13 28-Apr-13 119 Final StaFinal Stage Finishes 19 21-Mar-13 11-Apr-13 07-Apr-13 28-Apr-13 14 A95370 Installation of Carpets 10 21-Mar-13 01-Apr-13 07-Apr-13 17-Apr-13 14 A95620 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 18-Apr-13 25-Apr-13 14 A95600 Installation of Sinages 2 10-Apr-13 11-Apr-13 27-Apr-13 28-Apr-13 14 MEP WorkMEP Works 33 18-Oct-12 28-Nov-12 31-Jan-13 31-Mar-13 102 HVACHVAC 28 18-Oct-12 22-Nov-12 06-Feb-13 05-Mar-13 85 A95400 Duct Installation & Insulation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89 A95410 Chilled Water Pipe Installation & Insulation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89 A95420 Condensate Pipe Installation 5 18-Oct-12 23-Oct-12 06-Feb-13 11-Feb-13 89 A95430 FCU Installation 3 24-Oct-12 29-Oct-12 12-Feb-13 14-Feb-13 89 A95440 Air-Outlet Installation 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85 ElectricalElectrical 29 18-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84 A95450 Install Conduits in Wall 2 18-Oct-12 20-Oct-12 31-Jan-13 02-Feb-13 84 A95460 Install Cable Trays & Trunking 2 18-Oct-12 20-Oct-12 06-Feb-13 07-Feb-13 89 A95500 Cable Laying for Low Current System 2 21-Oct-12 22-Oct-12 20-Feb-13 21-Feb-13 99 A95510 Cable Laying for Power 3 21-Oct-12 23-Oct-12 19-Feb-13 21-Feb-13 98 A95470 Wiring for Lighting & Power 3 31-Oct-12 03-Nov-12 12-Feb-13 14-Feb-13 85 A95480 Wiring for Low Current System 4 31-Oct-12 04-Nov-12 11-Feb-13 14-Feb-13 84 A95490 DB installation,Dressing & Termination 3 12-Nov-12 14-Nov-12 26-Feb-13 28-Feb-13 87 A95530 Installation of Lighting Fittings 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85 A95540 Installation of Sockets 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84 PlumbingPlumbing 5 18-Oct-12 23-Oct-12 10-Feb-13 14-Feb-13 92 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 70 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 71. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A95550 H/L Hot&Cold Water Pipe Installation 5 18-Oct-12 23-Oct-12 10-Feb-13 14-Feb-13 92 Fire FighFire Fighting 33 18-Oct-12 28-Nov-12 06-Feb-13 31-Mar-13 102 A95590 Fire Fighting Pipe 4 18-Oct-12 22-Oct-12 06-Feb-13 10-Feb-13 89 A95580 Hydro Static Test for Pipes 4 23-Oct-12 29-Oct-12 11-Feb-13 14-Feb-13 89 A95570 Sprinkler Fixing 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84 A95640 Fire Alarm Devices 5 20-Nov-12 25-Nov-12 26-Mar-13 31-Mar-13 105 A95560 Installation of Fire Extingusher&Blanket 4 25-Nov-12 28-Nov-12 27-Mar-13 31-Mar-13 102 Electrical /Electrical / Telephone Room 35 09-Oct-12 21-Nov-12 31-Jan-13 28-Apr-13 132 FinishingFinishing Works 35 09-Oct-12 21-Nov-12 31-Jan-13 28-Apr-13 132 Wet WorWet Works 14 09-Oct-12 24-Oct-12 31-Jan-13 23-Apr-13 149 A97020 Block Works 3 09-Oct-12 11-Oct-12 31-Jan-13 03-Feb-13 92 A96980 Installation of Doors& Windows Sub-frame 1 15-Oct-12 15-Oct-12 23-Apr-13 23-Apr-13 157 A96970 Plaster Works 4 15-Oct-12 18-Oct-12 06-Feb-13 10-Feb-13 92 A96990 1st Coat Paint 3 22-Oct-12 24-Oct-12 13-Feb-13 16-Feb-13 92 Fisrt StaFisrt Stage Finishes 2 14-Nov-12 17-Nov-12 02-Apr-13 25-Apr-13 134 A97010 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A97030 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A97080 Epoxy Paint Works 2 14-Nov-12 17-Nov-12 02-Apr-13 03-Apr-13 115 Second SSecond Stage Finishes 2 18-Nov-12 19-Nov-12 04-Apr-13 06-Apr-13 115 A97000 Final Coat Paint 2 18-Nov-12 19-Nov-12 04-Apr-13 06-Apr-13 115 Final StaFinal Stage Finishes 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132 A97070 Installation of Sinages 2 20-Nov-12 21-Nov-12 27-Apr-13 28-Apr-13 132 MEP WorkMEP Works 26 13-Oct-12 13-Nov-12 04-Feb-13 01-Apr-13 115 HVACHVAC 2 28-Oct-12 29-Oct-12 04-Mar-13 05-Mar-13 105 A97100 Air-Outlet Installation 2 28-Oct-12 29-Oct-12 04-Mar-13 05-Mar-13 105 ElectricalElectrical 26 13-Oct-12 13-Nov-12 04-Feb-13 05-Mar-13 92 A97040 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 04-Feb-13 05-Feb-13 92 A97050 Wiring for Lighting & Power 2 20-Oct-12 21-Oct-12 11-Feb-13 12-Feb-13 92 A114800 Installation of SMDBs 7 28-Oct-12 04-Nov-12 24-Feb-13 03-Mar-13 98 A97060 Installation of Lighting Fittings 2 05-Nov-12 06-Nov-12 04-Mar-13 05-Mar-13 98 A114790 Installation of Telephone System 15 28-Oct-12 13-Nov-12 17-Feb-13 05-Mar-13 92 Fire FighFire Fighting 2 28-Oct-12 29-Oct-12 31-Mar-13 01-Apr-13 128 A97090 Fire Alarm Devices 2 28-Oct-12 29-Oct-12 31-Mar-13 01-Apr-13 128 House KeeHouse Keeping Room 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 279 09-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 09-Oct-12 10-Nov-12 20-Jan-13 25-Apr-13 139 A97430 Block Works 4 09-Oct-12 13-Oct-12 20-Jan-13 23-Jan-13 83 A97360 Installation of Doors& Windows Sub-frame 1 18-Oct-12 18-Oct-12 25-Apr-13 25-Apr-13 156 A97350 Plaster Works 4 18-Oct-12 22-Oct-12 30-Jan-13 03-Feb-13 83 A97380 Installation of Suspended Ceiling Grid 7 30-Oct-12 06-Nov-12 09-Feb-13 16-Feb-13 83 A97370 1st Coat Paint 3 07-Nov-12 10-Nov-12 17-Feb-13 19-Feb-13 83 Fisrt StaFisrt Stage Finishes 16 11-Nov-12 29-Nov-12 20-Feb-13 03-Apr-13 104 A97390 Suspended Ceiling Tiles 7 11-Nov-12 19-Nov-12 20-Feb-13 27-Feb-13 83 A97720 Screed Works 5 20-Nov-12 25-Nov-12 02-Mar-13 06-Mar-13 84 A97410 Floor Tiles Work 4 26-Nov-12 29-Nov-12 31-Mar-13 03-Apr-13 104 Second SSecond Stage Finishes 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123 A97420 Installation of Windows&Doors 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123 A97440 Doors Ironmongery 2 01-Dec-12 03-Dec-12 27-Apr-13 28-Apr-13 123 Final StaFinal Stage Finishes 237 01-Dec-12 08-Sep-13 04-Apr-13 02-Oct-13 21 A97400 Final Coat Paint 2 01-Dec-12 03-Dec-12 04-Apr-13 06-Apr-13 104 A97710 Installation of Sinages 2 04-Dec-12 05-Dec-12 27-Apr-13 28-Apr-13 121 A97450 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 14-Oct-12 26-Nov-12 26-Jan-13 06-Apr-13 109 HVACHVAC 32 14-Oct-12 22-Nov-12 29-Jan-13 05-Mar-13 85 A97460 Duct Installation & Insulation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86 A97470 Chilled Water Pipe Installation & Insulation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86 A97480 Condensate Pipe Installation 7 14-Oct-12 21-Oct-12 29-Jan-13 05-Feb-13 86 A97490 FCU Installation 2 22-Oct-12 23-Oct-12 06-Feb-13 07-Feb-13 86 A97500 Air-Outlet Installation 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85 ElectricalElectrical 34 14-Oct-12 25-Nov-12 26-Jan-13 05-Mar-13 83 A97510 Install Conduits in Wall 4 14-Oct-12 17-Oct-12 26-Jan-13 29-Jan-13 83 A97520 Install Cable Trays & Trunking 4 14-Oct-12 17-Oct-12 28-Jan-13 31-Jan-13 85 A97560 Cable Laying for Power 4 18-Oct-12 22-Oct-12 12-Feb-13 16-Feb-13 94 A97530 Wiring for Lighting & Power 4 23-Oct-12 29-Oct-12 04-Feb-13 07-Feb-13 83 A97580 Installation of Sockets 3 20-Nov-12 22-Nov-12 03-Mar-13 05-Mar-13 85 A97570 Installation of Lighting Fittings 5 20-Nov-12 25-Nov-12 28-Feb-13 05-Mar-13 83 PlumbingPlumbing 33 14-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84 A97600 H/L Drainage Pipes Installation 3 14-Oct-12 16-Oct-12 31-Jan-13 03-Feb-13 88 A97610 H/L Hot&Cold Water Pipe Installation 3 14-Oct-12 16-Oct-12 31-Jan-13 03-Feb-13 88 A97620 Drainage&Water Pipes Testing 3 17-Oct-12 20-Oct-12 04-Feb-13 06-Feb-13 88 A97630 ElectricalWater Heater Installation 4 17-Oct-12 21-Oct-12 04-Feb-13 07-Feb-13 88 A97640 Floor Drain Fixning 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84 Fire FighFire Fighting 35 14-Oct-12 26-Nov-12 31-Jan-13 06-Apr-13 109 A97700 Fire Fighting Pipe 4 14-Oct-12 17-Oct-12 31-Jan-13 04-Feb-13 88 A97690 Hydro Static Test for Pipes 3 18-Oct-12 21-Oct-12 05-Feb-13 07-Feb-13 88 A97680 Sprinkler Fixing 4 20-Nov-12 24-Nov-12 02-Mar-13 05-Mar-13 84 A97730 Fire Alarm Devices 4 20-Nov-12 24-Nov-12 31-Mar-13 03-Apr-13 109 A97670 Installation of Fire Extingusher&Blanket 2 25-Nov-12 26-Nov-12 04-Apr-13 06-Apr-13 109 Storage RoStorage Room 45 09-Oct-12 04-Dec-12 20-Jan-13 28-Apr-13 122 FinishingFinishing Works 45 09-Oct-12 04-Dec-12 20-Jan-13 28-Apr-13 122 Wet WorWet Works 29 09-Oct-12 13-Nov-12 20-Jan-13 23-Feb-13 83 A97160 Block Works 5 09-Oct-12 14-Oct-12 20-Jan-13 26-Jan-13 83 A97110 Plaster Works 5 20-Oct-12 24-Oct-12 31-Jan-13 05-Feb-13 83 A97130 Installation of Suspended Ceiling Grid 5 01-Nov-12 06-Nov-12 11-Feb-13 16-Feb-13 83 A97120 1st Coat Paint 6 07-Nov-12 13-Nov-12 17-Feb-13 23-Feb-13 83 Fisrt StaFisrt Stage Finishes 13 14-Nov-12 29-Nov-12 24-Feb-13 04-Apr-13 105 A97140 Suspended Ceiling Tiles 5 14-Nov-12 20-Nov-12 24-Feb-13 28-Feb-13 83 A97310 Epoxy Paint Works 2 28-Nov-12 29-Nov-12 03-Apr-13 04-Apr-13 105 Second SSecond Stage Finishes 1 01-Dec-12 01-Dec-12 06-Apr-13 25-Apr-13 122 A97150 Installation of Doors 1 01-Dec-12 01-Dec-12 06-Apr-13 06-Apr-13 105 A97170 Doors Ironmongery 1 01-Dec-12 01-Dec-12 25-Apr-13 25-Apr-13 122 Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122 A97300 Installation of Sinages 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122 MEP WorkMEP Works 35 15-Oct-12 27-Nov-12 27-Jan-13 02-Apr-13 105 HVACHVAC 32 15-Oct-12 24-Nov-12 31-Jan-13 05-Mar-13 84 A97180 Duct Installation & Insulation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87 A97190 Chilled Water Pipe Installation & Insulation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87 A97200 Condensate Pipe Installation 7 15-Oct-12 22-Oct-12 31-Jan-13 07-Feb-13 87 A97210 FCU Installation 2 23-Oct-12 24-Oct-12 09-Feb-13 10-Feb-13 87 A97220 Air-Outlet Installation 3 21-Nov-12 24-Nov-12 03-Mar-13 05-Mar-13 84 ElectricalElectrical 33 15-Oct-12 25-Nov-12 27-Jan-13 05-Mar-13 83 A97230 Install Conduits in Wall 4 15-Oct-12 18-Oct-12 27-Jan-13 30-Jan-13 83 A97240 Wiring for Lighting & Power 4 28-Oct-12 31-Oct-12 06-Feb-13 10-Feb-13 83 A97250 Installation of Lighting Fittings 4 21-Nov-12 25-Nov-12 02-Mar-13 05-Mar-13 83 PlumbingPlumbing 8 15-Oct-12 23-Oct-12 02-Feb-13 10-Feb-13 88 A97330 H/L Hot&Cold Water Pipe Installation 4 15-Oct-12 18-Oct-12 02-Feb-13 05-Feb-13 88 A97740 H/L Drainage Pipes Installation 4 15-Oct-12 18-Oct-12 02-Feb-13 05-Feb-13 88 A97340 Water Pipes Testing 4 20-Oct-12 23-Oct-12 06-Feb-13 10-Feb-13 88 A97750 Drainage&Water Pipes Testing 4 20-Oct-12 23-Oct-12 06-Feb-13 10-Feb-13 88 Fire FighFire Fighting 35 15-Oct-12 27-Nov-12 03-Feb-13 02-Apr-13 105 A97290 Fire Fighting Pipe 4 15-Oct-12 18-Oct-12 03-Feb-13 06-Feb-13 89 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 71 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 72. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A97280 Hydro Static Test for Pipes 3 20-Oct-12 22-Oct-12 07-Feb-13 10-Feb-13 89 A97270 Sprinkler Fixing 4 21-Nov-12 25-Nov-12 02-Mar-13 05-Mar-13 83 A97320 Fire Alarm Devices 4 21-Nov-12 25-Nov-12 30-Mar-13 02-Apr-13 107 A97260 Installation of Fire Extingusher&Blanket 2 26-Nov-12 27-Nov-12 01-Apr-13 02-Apr-13 105 StaircaseStaircase 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79 Stairs 1Stairs 1 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79 A110290 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79 A110300 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79 A110310 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110320 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110330 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79 A110340 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79 Stairs 2Stairs 2 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79 A110350 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79 A110360 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79 A110370 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110380 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110390 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79 A110400 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79 Stairs 3Stairs 3 43 11-Nov-12 02-Jan-13 16-Feb-13 06-Apr-13 79 A110410 Floor Screed 3 11-Nov-12 13-Nov-12 16-Feb-13 18-Feb-13 79 A110420 Install Handrails 4 14-Nov-12 19-Nov-12 19-Feb-13 23-Feb-13 79 A110430 Ceiling 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110440 Wall 1st Coat Paint 12 20-Nov-12 04-Dec-12 24-Feb-13 09-Mar-13 79 A110450 Install Granite/Terrazo 12 05-Dec-12 18-Dec-12 10-Mar-13 23-Mar-13 79 A110460 Final Coat Paint 12 19-Dec-12 02-Jan-13 24-Mar-13 06-Apr-13 79 Rooms AreaRooms Area 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Guest RooGuest Rooms 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 FinishingFinishing Works 279 09-Oct-12 08-Sep-13 21-Oct-12 02-Oct-13 21 Wet WorWet Works 78 09-Oct-12 13-Jan-13 21-Oct-12 06-Mar-13 44 A92530 Block Works 12 09-Oct-12 22-Oct-12 21-Oct-12 05-Nov-12 10 A92390 Plaster Works 31 03-Nov-12 10-Dec-12 14-Nov-12 22-Dec-12 10 A92400 Installation of Doors& Windows Sub-frame 22 18-Nov-12 13-Dec-12 10-Feb-13 06-Mar-13 69 A92860 Wall Tiles Work (Wet Area) 22 21-Nov-12 17-Dec-12 02-Jan-13 28-Jan-13 34 A92420 Installation of Suspended Ceiling Grid (Dry Area) 10 11-Dec-12 22-Dec-12 23-Dec-12 03-Jan-13 10 A92410 1st Coat Paint 22 18-Dec-12 13-Jan-13 30-Dec-12 26-Jan-13 10 Fisrt StaFisrt Stage Finishes 37 07-Jan-13 19-Feb-13 19-Jan-13 27-Mar-13 31 A92430 Suspended Ceiling Tiles (DryArea) 8 07-Jan-13 15-Jan-13 19-Jan-13 28-Jan-13 10 A92470 Installation of Wardrobes 7 13-Jan-13 20-Jan-13 26-Jan-13 02-Feb-13 10 A92850 Screed Works 15 16-Jan-13 03-Feb-13 29-Jan-13 14-Feb-13 10 A92460 Water Proofing for Wet Area 11 26-Jan-13 06-Feb-13 06-Feb-13 18-Feb-13 10 A92890 Installation of Suspended Ceiling Grid (Wet Area) 7 30-Jan-13 06-Feb-13 11-Feb-13 18-Feb-13 10 A92450 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 14-Mar-13 27-Mar-13 41 A92880 Suspended Ceiling Tiles (Wet Area) 7 05-Feb-13 12-Feb-13 17-Feb-13 24-Feb-13 10 A92870 Floor Tiles Work (Wet Area) 8 11-Feb-13 19-Feb-13 03-Mar-13 11-Mar-13 17 Second SSecond Stage Finishes 18 16-Feb-13 07-Mar-13 07-Mar-13 03-Apr-13 23 A92480 Installation of Windows&Doors 7 16-Feb-13 23-Feb-13 07-Mar-13 14-Mar-13 17 A92540 Doors Ironmongery 7 16-Feb-13 23-Feb-13 20-Mar-13 27-Mar-13 28 A92510 Installation of Balustrades& Handrails 7 24-Feb-13 03-Mar-13 20-Mar-13 27-Mar-13 21 A92830 Installation of Toliets Accessories 12 20-Feb-13 05-Mar-13 21-Mar-13 03-Apr-13 25 A92520 Installation of Vanity Counter 10 24-Feb-13 06-Mar-13 17-Mar-13 27-Mar-13 18 A92490 Installation of Mirrors 11 24-Feb-13 07-Mar-13 16-Mar-13 27-Mar-13 17 Final StaFinal Stage Finishes 156 09-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21 A92440 Final Coat Paint 8 09-Mar-13 17-Mar-13 28-Mar-13 06-Apr-13 17 A92500 Installation of Carpets 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A92840 Installation of Sinages 7 21-Mar-13 28-Mar-13 21-Apr-13 28-Apr-13 26 A92550 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 112 18-Oct-12 04-Mar-13 06-Nov-12 06-Apr-13 28 HVACHVAC 97 23-Oct-12 19-Feb-13 28-Nov-12 05-Mar-13 12 A92580 Condensate Pipe Installation 10 23-Oct-12 05-Nov-12 01-Dec-12 12-Dec-12 30 A92560 Duct Installation & Insulation 12 23-Oct-12 07-Nov-12 28-Nov-12 12-Dec-12 28 A92570 Chilled Water Pipe Installation & Insulation 12 23-Oct-12 07-Nov-12 28-Nov-12 12-Dec-12 28 A92590 FCU Installation 8 08-Nov-12 18-Nov-12 13-Dec-12 22-Dec-12 28 A92600 Air-Outlet Installation 6 13-Feb-13 19-Feb-13 27-Feb-13 05-Mar-13 12 ElectricalElectrical 99 23-Oct-12 21-Feb-13 06-Nov-12 05-Mar-13 10 A92610 Install Conduits in Wall 14 23-Oct-12 10-Nov-12 06-Nov-12 22-Nov-12 10 A92620 Install Cable Trays & Trunking 14 23-Oct-12 10-Nov-12 04-Dec-12 19-Dec-12 32 A92660 Cable Laying for Low Current System 6 11-Nov-12 18-Nov-12 27-Dec-12 03-Jan-13 38 A92670 Cable Laying for Power 6 11-Nov-12 18-Nov-12 27-Dec-12 03-Jan-13 38 A92640 Wiring for Low Current System 8 18-Nov-12 26-Nov-12 17-Dec-12 25-Dec-12 24 A92630 Wiring for Lighting & Power 8 21-Nov-12 29-Nov-12 15-Dec-12 23-Dec-12 19 A92650 DB installation,Dressing & Termination 14 30-Dec-12 15-Jan-13 12-Jan-13 28-Jan-13 10 A92700 Installation of Sockets 7 13-Feb-13 20-Feb-13 26-Feb-13 05-Mar-13 11 A92690 Installation of Lighting Fittings 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10 PlumbingPlumbing 112 18-Oct-12 04-Mar-13 08-Nov-12 27-Mar-13 20 A92710 Drainge Pipes in Wall 14 18-Oct-12 05-Nov-12 08-Nov-12 25-Nov-12 16 A92720 H/L Drainage Pipes Installation 10 23-Oct-12 05-Nov-12 22-Jan-13 03-Feb-13 73 A92730 H/L Hot&Cold Water Pipe Installation 10 23-Oct-12 05-Nov-12 22-Jan-13 03-Feb-13 73 A92780 Water Pipes in Wall 14 18-Oct-12 05-Nov-12 08-Nov-12 25-Nov-12 16 A92740 Drainage&Water Pipes Testing 4 06-Nov-12 10-Nov-12 04-Feb-13 07-Feb-13 73 A92750 ElectricalWater Heater Installation 6 06-Nov-12 12-Nov-12 04-Feb-13 10-Feb-13 73 A92760 Floor Drain Fixning 8 19-Jan-13 28-Jan-13 25-Feb-13 05-Mar-13 31 A92770 Installation of Sanitaryware 8 24-Feb-13 04-Mar-13 19-Mar-13 27-Mar-13 20 Fire FighFire Fighting 104 23-Oct-12 27-Feb-13 08-Dec-12 06-Apr-13 32 A92820 Fire Fighting Pipe 10 23-Oct-12 05-Nov-12 08-Dec-12 18-Dec-12 35 A92810 Hydro Static Test for Pipes 3 06-Nov-12 08-Nov-12 19-Dec-12 22-Dec-12 35 A92800 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10 A92900 Fire Alarm Devices 8 13-Feb-13 21-Feb-13 19-Mar-13 27-Mar-13 29 A92790 Installation of Fire Extingusher&Blanket 5 23-Feb-13 27-Feb-13 01-Apr-13 06-Apr-13 32 4th Floor4th Floor 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21 Public AreaPublic Area 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Lift LobbyLift Lobby - Corridor 143 21-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14 FinishingFinishing Works 143 21-Oct-12 11-Apr-13 21-Jan-13 28-Apr-13 14 Wet WorWet Works 34 21-Oct-12 03-Dec-12 21-Jan-13 27-Mar-13 96 A96700 Block Works 8 21-Oct-12 31-Oct-12 21-Jan-13 30-Jan-13 74 A96640 Plaster Works 7 04-Nov-12 11-Nov-12 03-Feb-13 10-Feb-13 74 A96660 Installation of Suspended Ceiling Grid 6 18-Nov-12 24-Nov-12 16-Feb-13 21-Feb-13 74 A96670 Suspended Ceiling Tiles 6 25-Nov-12 01-Dec-12 23-Feb-13 28-Feb-13 74 A96950 MDF for Lift Lobby Wall 7 25-Nov-12 03-Dec-12 20-Mar-13 27-Mar-13 96 Fisrt StaFisrt Stage Finishes 12 04-Dec-12 17-Dec-12 28-Mar-13 06-Apr-13 92 A96930 Screed Works 3 04-Dec-12 06-Dec-12 28-Mar-13 31-Mar-13 96 A96650 1st Coat Paint 5 12-Dec-12 17-Dec-12 01-Apr-13 06-Apr-13 92 Second SSecond Stage Finishes 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109 A96680 Installation of Doors 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109 A96710 Doors Ironmongery 2 18-Dec-12 19-Dec-12 27-Apr-13 28-Apr-13 109 Final StaFinal Stage Finishes 19 21-Mar-13 11-Apr-13 07-Apr-13 28-Apr-13 14 A96690 Installation of Carpets 10 21-Mar-13 01-Apr-13 07-Apr-13 17-Apr-13 14 A96940 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 18-Apr-13 25-Apr-13 14 A96920 Installation of Sinages 2 10-Apr-13 11-Apr-13 27-Apr-13 28-Apr-13 14 MEP WorkMEP Works 33 01-Nov-12 11-Dec-12 31-Jan-13 31-Mar-13 92 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Low Current System Wiring for Lighting & Power DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 72 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 73. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float HVACHVAC 28 01-Nov-12 05-Dec-12 06-Feb-13 05-Mar-13 75 A96720 Duct Installation & Insulation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79 A96730 Chilled Water Pipe Installation & Insulation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79 A96740 Condensate Pipe Installation 5 01-Nov-12 06-Nov-12 06-Feb-13 11-Feb-13 79 A96750 FCU Installation 3 07-Nov-12 10-Nov-12 12-Feb-13 14-Feb-13 79 A96760 Air-Outlet Installation 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75 ElectricalElectrical 29 01-Nov-12 06-Dec-12 31-Jan-13 05-Mar-13 74 A96770 Install Conduits in Wall 2 01-Nov-12 03-Nov-12 31-Jan-13 02-Feb-13 74 A96780 Install Cable Trays & Trunking 2 01-Nov-12 03-Nov-12 06-Feb-13 07-Feb-13 79 A96820 Cable Laying for Low Current System 2 04-Nov-12 05-Nov-12 20-Feb-13 21-Feb-13 89 A96830 Cable Laying for Power 3 04-Nov-12 06-Nov-12 19-Feb-13 21-Feb-13 88 A96790 Wiring for Lighting & Power 3 12-Nov-12 14-Nov-12 12-Feb-13 14-Feb-13 75 A96800 Wiring for Low Current System 4 12-Nov-12 17-Nov-12 11-Feb-13 14-Feb-13 74 A96810 DB installation,Dressing & Termination 3 25-Nov-12 27-Nov-12 26-Feb-13 28-Feb-13 77 A96850 Installation of Lighting Fittings 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75 A96860 Installation of Sockets 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74 PlumbingPlumbing 5 01-Nov-12 06-Nov-12 10-Feb-13 14-Feb-13 82 A96870 H/L Hot&Cold Water Pipe Installation 5 01-Nov-12 06-Nov-12 10-Feb-13 14-Feb-13 82 Fire FighFire Fighting 33 01-Nov-12 11-Dec-12 06-Feb-13 31-Mar-13 92 A96910 Fire Fighting Pipe 4 01-Nov-12 05-Nov-12 06-Feb-13 10-Feb-13 79 A96900 Hydro Static Test for Pipes 4 06-Nov-12 10-Nov-12 11-Feb-13 14-Feb-13 79 A96890 Sprinkler Fixing 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74 A96960 Fire Alarm Devices 5 03-Dec-12 08-Dec-12 26-Mar-13 31-Mar-13 95 A96880 Installation of Fire Extingusher&Blanket 4 08-Dec-12 11-Dec-12 27-Mar-13 31-Mar-13 92 Electrical /Electrical / Telephone Rooms 35 21-Oct-12 04-Dec-12 31-Jan-13 28-Apr-13 122 FinishingFinishing Works 35 21-Oct-12 04-Dec-12 31-Jan-13 28-Apr-13 122 Wet WorWet Works 14 21-Oct-12 07-Nov-12 31-Jan-13 23-Apr-13 139 A97810 Block Works 3 21-Oct-12 23-Oct-12 31-Jan-13 03-Feb-13 82 A97770 Installation of Doors& Windows Sub-frame 1 29-Oct-12 29-Oct-12 23-Apr-13 23-Apr-13 147 A97760 Plaster Works 4 29-Oct-12 01-Nov-12 06-Feb-13 10-Feb-13 82 A97780 1st Coat Paint 3 05-Nov-12 07-Nov-12 13-Feb-13 16-Feb-13 82 Fisrt StaFisrt Stage Finishes 12 14-Nov-12 28-Nov-12 02-Apr-13 25-Apr-13 124 A97800 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A97820 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A97870 Epoxy Paint Works 2 27-Nov-12 28-Nov-12 02-Apr-13 03-Apr-13 105 Second SSecond Stage Finishes 2 29-Nov-12 01-Dec-12 04-Apr-13 06-Apr-13 105 A97790 Final Coat Paint 2 29-Nov-12 01-Dec-12 04-Apr-13 06-Apr-13 105 Final StaFinal Stage Finishes 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122 A97860 Installation of Sinages 2 03-Dec-12 04-Dec-12 27-Apr-13 28-Apr-13 122 MEP WorkMEP Works 26 24-Oct-12 26-Nov-12 04-Feb-13 01-Apr-13 105 HVACHVAC 2 08-Nov-12 10-Nov-12 04-Mar-13 05-Mar-13 95 A97890 Air-Outlet Installation 2 08-Nov-12 10-Nov-12 04-Mar-13 05-Mar-13 95 ElectricalElectrical 26 24-Oct-12 26-Nov-12 04-Feb-13 05-Mar-13 82 A97830 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 04-Feb-13 05-Feb-13 82 A97840 Wiring for Lighting & Power 2 03-Nov-12 04-Nov-12 11-Feb-13 12-Feb-13 82 A114820 Installation of SMDBs 7 08-Nov-12 17-Nov-12 24-Feb-13 03-Mar-13 88 A97850 Installation of Lighting Fittings 2 18-Nov-12 19-Nov-12 04-Mar-13 05-Mar-13 88 A114810 Installation of Telephone System 15 08-Nov-12 26-Nov-12 17-Feb-13 05-Mar-13 82 Fire FighFire Fighting 2 08-Nov-12 10-Nov-12 31-Mar-13 01-Apr-13 118 A97880 Fire Alarm Devices 2 08-Nov-12 10-Nov-12 31-Mar-13 01-Apr-13 118 House KeeHouse Keeping Room 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 269 21-Oct-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 21-Oct-12 22-Nov-12 20-Jan-13 27-Apr-13 130 A98640 Block Works 4 21-Oct-12 24-Oct-12 20-Jan-13 23-Jan-13 73 A98570 Installation of Doors& Windows Sub-frame 1 01-Nov-12 01-Nov-12 27-Apr-13 27-Apr-13 147 A98560 Plaster Works 4 01-Nov-12 05-Nov-12 30-Jan-13 03-Feb-13 73 A98590 Installation of Suspended Ceiling Grid 7 11-Nov-12 19-Nov-12 09-Feb-13 16-Feb-13 73 A98580 1st Coat Paint 3 20-Nov-12 22-Nov-12 17-Feb-13 19-Feb-13 73 Fisrt StaFisrt Stage Finishes 16 24-Nov-12 12-Dec-12 20-Feb-13 03-Apr-13 94 A98600 Suspended Ceiling Tiles 7 24-Nov-12 01-Dec-12 20-Feb-13 27-Feb-13 73 A98880 Screed Works 5 03-Dec-12 08-Dec-12 02-Mar-13 06-Mar-13 74 A98620 Floor Tiles Work 4 09-Dec-12 12-Dec-12 31-Mar-13 03-Apr-13 94 Second SSecond Stage Finishes 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114 A98630 Installation of Windows&Doors 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114 A98650 Doors Ironmongery 1 13-Dec-12 13-Dec-12 28-Apr-13 28-Apr-13 114 Final StaFinal Stage Finishes 227 13-Dec-12 08-Sep-13 04-Apr-13 02-Oct-13 21 A98610 Final Coat Paint 2 13-Dec-12 15-Dec-12 04-Apr-13 06-Apr-13 94 A98870 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111 A98660 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 28-Oct-12 09-Dec-12 26-Jan-13 06-Apr-13 99 HVACHVAC 32 28-Oct-12 05-Dec-12 29-Jan-13 05-Mar-13 75 A98670 Duct Installation & Insulation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76 A98680 Chilled Water Pipe Installation & Insulation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76 A98690 Condensate Pipe Installation 7 28-Oct-12 04-Nov-12 29-Jan-13 05-Feb-13 76 A98700 FCU Installation 2 05-Nov-12 06-Nov-12 06-Feb-13 07-Feb-13 76 A98710 Air-Outlet Installation 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75 ElectricalElectrical 34 28-Oct-12 08-Dec-12 26-Jan-13 05-Mar-13 73 A98720 Install Conduits in Wall 4 28-Oct-12 31-Oct-12 26-Jan-13 29-Jan-13 73 A98730 Install Cable Trays & Trunking 4 28-Oct-12 31-Oct-12 28-Jan-13 31-Jan-13 75 A98750 Cable Laying for Power 4 01-Nov-12 05-Nov-12 12-Feb-13 16-Feb-13 84 A98740 Wiring for Lighting & Power 4 06-Nov-12 10-Nov-12 04-Feb-13 07-Feb-13 73 A98770 Installation of Sockets 3 03-Dec-12 05-Dec-12 03-Mar-13 05-Mar-13 75 A98760 Installation of Lighting Fittings 5 03-Dec-12 08-Dec-12 28-Feb-13 05-Mar-13 73 PlumbingPlumbing 33 28-Oct-12 06-Dec-12 31-Jan-13 05-Mar-13 74 A98780 H/L Drainage Pipes Installation 3 28-Oct-12 30-Oct-12 31-Jan-13 03-Feb-13 78 A98790 H/L Hot&Cold Water Pipe Installation 3 28-Oct-12 30-Oct-12 31-Jan-13 03-Feb-13 78 A98800 Drainage&Water Pipes Testing 3 31-Oct-12 03-Nov-12 04-Feb-13 06-Feb-13 78 A98810 ElectricalWater Heater Installation 4 31-Oct-12 04-Nov-12 04-Feb-13 07-Feb-13 78 A98820 Floor Drain Fixning 2 05-Dec-12 06-Dec-12 04-Mar-13 05-Mar-13 74 Fire FighFire Fighting 35 28-Oct-12 09-Dec-12 31-Jan-13 06-Apr-13 99 A98860 Fire Fighting Pipe 4 28-Oct-12 31-Oct-12 31-Jan-13 04-Feb-13 78 A98850 Hydro Static Test for Pipes 3 01-Nov-12 04-Nov-12 05-Feb-13 07-Feb-13 78 A98840 Sprinkler Fixing 4 03-Dec-12 06-Dec-12 02-Mar-13 05-Mar-13 74 A98890 Fire Alarm Devices 4 03-Dec-12 06-Dec-12 31-Mar-13 03-Apr-13 99 A98830 Installation of Fire Extingusher&Blanket 2 08-Dec-12 09-Dec-12 04-Apr-13 06-Apr-13 99 Storage RoStorage Room 46 21-Oct-12 17-Dec-12 20-Jan-13 28-Apr-13 111 FinishingFinishing Works 46 21-Oct-12 17-Dec-12 20-Jan-13 28-Apr-13 111 Wet WorWet Works 29 21-Oct-12 26-Nov-12 20-Jan-13 23-Feb-13 73 A98370 Block Works 5 21-Oct-12 28-Oct-12 20-Jan-13 26-Jan-13 73 A98320 Plaster Works 5 03-Nov-12 07-Nov-12 31-Jan-13 05-Feb-13 73 A98340 Installation of Suspended Ceiling Grid 5 13-Nov-12 19-Nov-12 11-Feb-13 16-Feb-13 73 A98330 1st Coat Paint 6 20-Nov-12 26-Nov-12 17-Feb-13 23-Feb-13 73 Fisrt StaFisrt Stage Finishes 13 27-Nov-12 12-Dec-12 24-Feb-13 03-Apr-13 94 A98350 Suspended Ceiling Tiles 5 27-Nov-12 03-Dec-12 24-Feb-13 28-Feb-13 73 A98520 Epoxy Paint Works 2 11-Dec-12 12-Dec-12 02-Apr-13 03-Apr-13 94 Second SSecond Stage Finishes 2 13-Dec-12 15-Dec-12 04-Apr-13 25-Apr-13 111 A98360 Installation of Doors 2 13-Dec-12 15-Dec-12 04-Apr-13 06-Apr-13 94 A98380 Doors Ironmongery 2 13-Dec-12 15-Dec-12 24-Apr-13 25-Apr-13 111 Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111 A98510 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111 MEP WorkMEP Works 35 29-Oct-12 10-Dec-12 27-Jan-13 01-Apr-13 94 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 73 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 74. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float HVACHVAC 32 29-Oct-12 06-Dec-12 31-Jan-13 05-Mar-13 74 A98390 Duct Installation & Insulation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77 A98400 Chilled Water Pipe Installation & Insulation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77 A98410 Condensate Pipe Installation 7 29-Oct-12 05-Nov-12 31-Jan-13 07-Feb-13 77 A98420 FCU Installation 2 06-Nov-12 07-Nov-12 09-Feb-13 10-Feb-13 77 A98430 Air-Outlet Installation 3 04-Dec-12 06-Dec-12 03-Mar-13 05-Mar-13 74 ElectricalElectrical 33 29-Oct-12 08-Dec-12 27-Jan-13 05-Mar-13 73 A98440 Install Conduits in Wall 4 29-Oct-12 01-Nov-12 27-Jan-13 30-Jan-13 73 A98450 Wiring for Lighting & Power 4 08-Nov-12 12-Nov-12 06-Feb-13 10-Feb-13 73 A98460 Installation of Lighting Fittings 4 04-Dec-12 08-Dec-12 02-Mar-13 05-Mar-13 73 PlumbingPlumbing 8 29-Oct-12 06-Nov-12 02-Feb-13 10-Feb-13 78 A98540 H/L Hot&Cold Water Pipe Installation 4 29-Oct-12 01-Nov-12 02-Feb-13 05-Feb-13 78 A98900 H/L Drainage Pipes Installation 4 29-Oct-12 01-Nov-12 02-Feb-13 05-Feb-13 78 A98550 Water Pipes Testing 4 03-Nov-12 06-Nov-12 06-Feb-13 10-Feb-13 78 A98910 Drainage&Water Pipes Testing 4 03-Nov-12 06-Nov-12 06-Feb-13 10-Feb-13 78 Fire FighFire Fighting 35 29-Oct-12 10-Dec-12 03-Feb-13 01-Apr-13 94 A98500 Fire Fighting Pipe 4 29-Oct-12 01-Nov-12 03-Feb-13 06-Feb-13 79 A98490 Hydro Static Test for Pipes 3 03-Nov-12 05-Nov-12 07-Feb-13 10-Feb-13 79 A98480 Sprinkler Fixing 4 04-Dec-12 08-Dec-12 02-Mar-13 05-Mar-13 73 A98530 Fire Alarm Devices 4 04-Dec-12 08-Dec-12 28-Mar-13 01-Apr-13 96 A98470 Installation of Fire Extingusher&Blanket 2 09-Dec-12 10-Dec-12 31-Mar-13 01-Apr-13 94 StaircaseStaircase 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68 Stairs 1Stairs 1 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68 A110470 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68 A110480 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68 A110490 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110500 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110510 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68 A110520 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68 Stairs 2Stairs 2 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68 A110530 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68 A110540 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68 A110550 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110560 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110570 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68 A110580 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68 Stairs 3Stairs 3 43 25-Nov-12 15-Jan-13 16-Feb-13 06-Apr-13 68 A110590 Floor Screed 3 25-Nov-12 27-Nov-12 16-Feb-13 18-Feb-13 68 A110600 Install Handrails 4 28-Nov-12 03-Dec-12 19-Feb-13 23-Feb-13 68 A110610 Ceiling 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110620 Wall 1st Coat Paint 12 04-Dec-12 17-Dec-12 24-Feb-13 09-Mar-13 68 A110630 Install Granite/Terrazo 12 18-Dec-12 31-Dec-12 10-Mar-13 23-Mar-13 68 A110640 Final Coat Paint 12 02-Jan-13 15-Jan-13 24-Mar-13 06-Apr-13 68 Rooms AreaRooms Area 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21 Guest RooGuest Rooms 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21 FinishingFinishing Works 269 21-Oct-12 08-Sep-13 11-Nov-12 02-Oct-13 21 Wet WorWet Works 63 21-Oct-12 07-Jan-13 11-Nov-12 06-Mar-13 49 A93050 Block Works 12 21-Oct-12 05-Nov-12 11-Nov-12 25-Nov-12 16 A92910 Plaster Works 31 07-Nov-12 15-Dec-12 27-Nov-12 03-Jan-13 16 A92940 Installation of Suspended Ceiling Grid (Dry Area) 10 05-Dec-12 16-Dec-12 24-Dec-12 05-Jan-13 16 A92920 Installation of Doors& Windows Sub-frame 22 22-Nov-12 18-Dec-12 10-Feb-13 06-Mar-13 65 A93380 Wall Tiles Work (Wet Area) 22 26-Nov-12 22-Dec-12 03-Jan-13 29-Jan-13 31 A92930 1st Coat Paint 22 12-Dec-12 07-Jan-13 31-Dec-12 27-Jan-13 16 Fisrt StaFisrt Stage Finishes 36 31-Dec-12 12-Feb-13 20-Jan-13 27-Mar-13 37 A92950 Suspended Ceiling Tiles (DryArea) 8 31-Dec-12 09-Jan-13 20-Jan-13 29-Jan-13 16 A92990 Installation of Wardrobes 7 07-Jan-13 14-Jan-13 27-Jan-13 03-Feb-13 16 A93370 Screed Works 15 10-Jan-13 28-Jan-13 30-Jan-13 16-Feb-13 16 A92980 Water Proofing for Wet Area 11 19-Jan-13 31-Jan-13 07-Feb-13 19-Feb-13 16 A93410 Installation of Suspended Ceiling Grid (Wet Area) 7 23-Jan-13 31-Jan-13 12-Feb-13 19-Feb-13 16 A92970 Floor & Wall Tiles Work (Dry Area) 12 19-Jan-13 02-Feb-13 14-Mar-13 27-Mar-13 46 A93400 Suspended Ceiling Tiles (Wet Area) 7 29-Jan-13 05-Feb-13 17-Feb-13 24-Feb-13 16 A93390 Floor Tiles Work (Wet Area) 8 04-Feb-13 12-Feb-13 02-Mar-13 10-Mar-13 22 Second SSecond Stage Finishes 18 10-Feb-13 02-Mar-13 07-Mar-13 03-Apr-13 28 A93000 Installation of Windows&Doors 7 10-Feb-13 17-Feb-13 07-Mar-13 14-Mar-13 22 A93060 Doors Ironmongery 7 10-Feb-13 17-Feb-13 20-Mar-13 27-Mar-13 33 A93030 Installation of Balustrades& Handrails 7 18-Feb-13 25-Feb-13 20-Mar-13 27-Mar-13 26 A93350 Installation of Toliets Accessories 12 14-Feb-13 27-Feb-13 21-Mar-13 03-Apr-13 30 A93040 Installation of Vanity Counter 10 18-Feb-13 28-Feb-13 17-Mar-13 27-Mar-13 23 A93010 Installation of Mirrors 11 18-Feb-13 02-Mar-13 16-Mar-13 27-Mar-13 22 Final StaFinal Stage Finishes 161 03-Mar-13 08-Sep-13 28-Mar-13 02-Oct-13 21 A92960 Final Coat Paint 8 03-Mar-13 11-Mar-13 28-Mar-13 06-Apr-13 22 A93020 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25 A93360 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25 A93070 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 99 30-Oct-12 26-Feb-13 19-Nov-12 06-Apr-13 33 HVACHVAC 78 06-Nov-12 09-Feb-13 29-Nov-12 05-Mar-13 21 A93100 Condensate Pipe Installation 10 06-Nov-12 18-Nov-12 03-Dec-12 13-Dec-12 21 A93080 Duct Installation & Insulation 12 06-Nov-12 20-Nov-12 29-Nov-12 13-Dec-12 19 A93090 Chilled Water Pipe Installation & Insulation 12 06-Nov-12 20-Nov-12 29-Nov-12 13-Dec-12 19 A93110 FCU Installation 8 21-Nov-12 29-Nov-12 15-Dec-12 23-Dec-12 19 A93120 Air-Outlet Installation 6 03-Feb-13 09-Feb-13 27-Feb-13 05-Mar-13 21 ElectricalElectrical 86 30-Oct-12 11-Feb-13 19-Nov-12 05-Mar-13 19 A93130 Install Conduits in Wall 14 30-Oct-12 14-Nov-12 19-Nov-12 05-Dec-12 16 A93140 Install Cable Trays & Trunking 14 06-Nov-12 22-Nov-12 12-Dec-12 27-Dec-12 29 A93180 Cable Laying for Low Current System 6 24-Nov-12 29-Nov-12 29-Dec-12 05-Jan-13 29 A93190 Cable Laying for Power 6 24-Nov-12 29-Nov-12 29-Dec-12 05-Jan-13 29 A93160 Wiring for Low Current System 8 22-Nov-12 01-Dec-12 18-Dec-12 26-Dec-12 21 A93150 Wiring for Lighting & Power 8 26-Nov-12 05-Dec-12 16-Dec-12 24-Dec-12 16 A93170 DB installation,Dressing & Termination 14 24-Dec-12 09-Jan-13 13-Jan-13 29-Jan-13 16 A93220 Installation of Sockets 7 03-Feb-13 10-Feb-13 26-Feb-13 05-Mar-13 20 A93210 Installation of Lighting Fittings 8 03-Feb-13 11-Feb-13 25-Feb-13 05-Mar-13 19 PlumbingPlumbing 97 01-Nov-12 26-Feb-13 21-Nov-12 27-Mar-13 25 A93230 Drainge Pipes in Wall 14 01-Nov-12 18-Nov-12 21-Nov-12 08-Dec-12 16 A93240 H/L Drainage Pipes Installation 10 06-Nov-12 18-Nov-12 23-Jan-13 04-Feb-13 64 A93250 H/L Hot&Cold Water Pipe Installation 10 06-Nov-12 18-Nov-12 23-Jan-13 04-Feb-13 64 A93300 Water Pipes in Wall 14 01-Nov-12 18-Nov-12 21-Nov-12 08-Dec-12 16 A93260 Drainage&Water Pipes Testing 4 19-Nov-12 22-Nov-12 05-Feb-13 09-Feb-13 64 A93270 ElectricalWater Heater Installation 6 19-Nov-12 25-Nov-12 05-Feb-13 11-Feb-13 64 A93280 Floor Drain Fixning 8 13-Jan-13 21-Jan-13 25-Feb-13 05-Mar-13 36 A93290 Installation of Sanitaryware 8 18-Feb-13 26-Feb-13 19-Mar-13 27-Mar-13 25 Fire FighFire Fighting 88 06-Nov-12 20-Feb-13 09-Dec-12 06-Apr-13 38 A93340 Fire Fighting Pipe 10 06-Nov-12 18-Nov-12 09-Dec-12 19-Dec-12 26 A93330 Hydro Static Test for Pipes 3 19-Nov-12 21-Nov-12 20-Dec-12 23-Dec-12 26 A93320 Sprinkler Fixing 8 06-Feb-13 14-Feb-13 25-Feb-13 05-Mar-13 16 A93420 Fire Alarm Devices 8 06-Feb-13 14-Feb-13 19-Mar-13 27-Mar-13 35 A93310 Installation of Fire Extingusher&Blanket 5 16-Feb-13 20-Feb-13 01-Apr-13 06-Apr-13 38 5th Floor5th Floor 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21 Public AreaPublic Area 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Lift LobbyLift Lobby - Corridor 135 05-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11 FinishingFinishing Works 135 05-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Low Current System Wiring for Lighting & Power DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 74 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 75. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Wet WorWet Works 34 05-Nov-12 16-Dec-12 21-Jan-13 24-Mar-13 82 A95710 Block Works 8 05-Nov-12 13-Nov-12 21-Jan-13 30-Jan-13 63 A95650 Plaster Works 7 18-Nov-12 25-Nov-12 03-Feb-13 10-Feb-13 63 A95670 Installation of Suspended Ceiling Grid 6 01-Dec-12 08-Dec-12 16-Feb-13 21-Feb-13 63 A95680 Suspended Ceiling Tiles 6 09-Dec-12 15-Dec-12 23-Feb-13 28-Feb-13 63 A95960 MDF for Lift Lobby Wall 7 09-Dec-12 16-Dec-12 17-Mar-13 24-Mar-13 82 Fisrt StaFisrt Stage Finishes 12 17-Dec-12 30-Dec-12 25-Mar-13 02-Apr-13 78 A95940 Screed Works 3 17-Dec-12 19-Dec-12 25-Mar-13 27-Mar-13 82 A95660 1st Coat Paint 5 25-Dec-12 30-Dec-12 28-Mar-13 02-Apr-13 78 Second SSecond Stage Finishes 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98 A95690 Installation of Doors 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98 A95720 Doors Ironmongery 2 31-Dec-12 02-Jan-13 27-Apr-13 28-Apr-13 98 Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11 A95700 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11 A95950 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11 A95930 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11 MEP WorkMEP Works 33 14-Nov-12 24-Dec-12 31-Jan-13 27-Mar-13 78 HVACHVAC 28 14-Nov-12 18-Dec-12 06-Feb-13 05-Mar-13 64 A95730 Duct Installation & Insulation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68 A95740 Chilled Water Pipe Installation & Insulation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68 A95750 Condensate Pipe Installation 5 14-Nov-12 20-Nov-12 06-Feb-13 11-Feb-13 68 A95760 FCU Installation 3 21-Nov-12 24-Nov-12 12-Feb-13 14-Feb-13 68 A95770 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 ElectricalElectrical 29 14-Nov-12 19-Dec-12 31-Jan-13 05-Mar-13 63 A95780 Install Conduits in Wall 2 14-Nov-12 17-Nov-12 31-Jan-13 02-Feb-13 63 A95790 Install Cable Trays & Trunking 2 14-Nov-12 17-Nov-12 06-Feb-13 07-Feb-13 68 A95830 Cable Laying for Low Current System 2 18-Nov-12 19-Nov-12 20-Feb-13 21-Feb-13 78 A95840 Cable Laying for Power 3 18-Nov-12 20-Nov-12 19-Feb-13 21-Feb-13 77 A95800 Wiring for Lighting & Power 3 26-Nov-12 28-Nov-12 12-Feb-13 14-Feb-13 64 A95810 Wiring for Low Current System 4 26-Nov-12 29-Nov-12 11-Feb-13 14-Feb-13 63 A95820 DB installation,Dressing & Termination 3 09-Dec-12 11-Dec-12 26-Feb-13 28-Feb-13 66 A95860 Installation of Lighting Fittings 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 A95870 Installation of Sockets 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63 PlumbingPlumbing 5 14-Nov-12 20-Nov-12 10-Feb-13 14-Feb-13 71 A95880 H/L Hot&Cold Water Pipe Installation 5 14-Nov-12 20-Nov-12 10-Feb-13 14-Feb-13 71 Fire FighFire Fighting 33 14-Nov-12 24-Dec-12 06-Feb-13 27-Mar-13 78 A95920 Fire Fighting Pipe 4 14-Nov-12 19-Nov-12 06-Feb-13 10-Feb-13 68 A95910 Hydro Static Test for Pipes 4 20-Nov-12 24-Nov-12 11-Feb-13 14-Feb-13 68 A95900 Sprinkler Fixing 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63 A95970 Fire Alarm Devices 5 16-Dec-12 20-Dec-12 23-Mar-13 27-Mar-13 81 A95890 Installation of Fire Extingusher&Blanket 4 20-Dec-12 24-Dec-12 24-Mar-13 27-Mar-13 78 Electrical /Electrical / Telephone Rooms 35 05-Nov-12 17-Dec-12 31-Jan-13 28-Apr-13 111 FinishingFinishing Works 35 05-Nov-12 17-Dec-12 31-Jan-13 28-Apr-13 111 Wet WorWet Works 14 05-Nov-12 21-Nov-12 31-Jan-13 23-Apr-13 128 A97950 Block Works 3 05-Nov-12 07-Nov-12 31-Jan-13 03-Feb-13 71 A97910 Installation of Doors& Windows Sub-frame 1 11-Nov-12 11-Nov-12 23-Apr-13 23-Apr-13 136 A97900 Plaster Works 4 11-Nov-12 14-Nov-12 06-Feb-13 10-Feb-13 71 A97920 1st Coat Paint 3 19-Nov-12 21-Nov-12 13-Feb-13 16-Feb-13 71 Fisrt StaFisrt Stage Finishes 23 14-Nov-12 12-Dec-12 30-Mar-13 25-Apr-13 113 A97940 Installation of Doors 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A97960 Doors Ironmongery 2 14-Nov-12 17-Nov-12 24-Apr-13 25-Apr-13 134 A98010 Epoxy Paint Works 2 11-Dec-12 12-Dec-12 30-Mar-13 31-Mar-13 91 Second SSecond Stage Finishes 2 13-Dec-12 15-Dec-12 01-Apr-13 02-Apr-13 91 A97930 Final Coat Paint 2 13-Dec-12 15-Dec-12 01-Apr-13 02-Apr-13 91 Final StaFinal Stage Finishes 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111 A98000 Installation of Sinages 2 16-Dec-12 17-Dec-12 27-Apr-13 28-Apr-13 111 MEP WorkMEP Works 26 08-Nov-12 10-Dec-12 04-Feb-13 28-Mar-13 91 HVACHVAC 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84 A98030 Air-Outlet Installation 2 22-Nov-12 24-Nov-12 04-Mar-13 05-Mar-13 84 ElectricalElectrical 26 08-Nov-12 10-Dec-12 04-Feb-13 05-Mar-13 71 A97970 Install Conduits in Wall 2 08-Nov-12 10-Nov-12 04-Feb-13 05-Feb-13 71 A97980 Wiring for Lighting & Power 2 17-Nov-12 18-Nov-12 11-Feb-13 12-Feb-13 71 A114830 Installation of SMDBs 7 22-Nov-12 29-Nov-12 24-Feb-13 03-Mar-13 77 A97990 Installation of Lighting Fittings 2 01-Dec-12 03-Dec-12 04-Mar-13 05-Mar-13 77 A114840 Installation of Telephone System 15 22-Nov-12 10-Dec-12 17-Feb-13 05-Mar-13 71 Fire FighFire Fighting 2 22-Nov-12 24-Nov-12 27-Mar-13 28-Mar-13 104 A98020 Fire Alarm Devices 2 22-Nov-12 24-Nov-12 27-Mar-13 28-Mar-13 104 House KeeHouse Keeping Room 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 258 05-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 05-Nov-12 06-Dec-12 20-Jan-13 27-Apr-13 119 A99240 Block Works 4 05-Nov-12 08-Nov-12 20-Jan-13 23-Jan-13 62 A99170 Installation of Doors& Windows Sub-frame 1 14-Nov-12 14-Nov-12 27-Apr-13 27-Apr-13 136 A99160 Plaster Works 4 14-Nov-12 19-Nov-12 30-Jan-13 03-Feb-13 62 A99190 Installation of Suspended Ceiling Grid 7 25-Nov-12 03-Dec-12 09-Feb-13 16-Feb-13 62 A99180 1st Coat Paint 3 04-Dec-12 06-Dec-12 17-Feb-13 19-Feb-13 62 Fisrt StaFisrt Stage Finishes 16 08-Dec-12 25-Dec-12 20-Feb-13 31-Mar-13 80 A99200 Suspended Ceiling Tiles 7 08-Dec-12 15-Dec-12 20-Feb-13 27-Feb-13 62 A99480 Screed Works 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62 A99220 Floor Tiles Work 4 22-Dec-12 25-Dec-12 27-Mar-13 31-Mar-13 80 Second SSecond Stage Finishes 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103 A99230 Installation of Windows&Doors 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103 A99250 Doors Ironmongery 1 26-Dec-12 26-Dec-12 28-Apr-13 28-Apr-13 103 Final StaFinal Stage Finishes 216 26-Dec-12 08-Sep-13 01-Apr-13 02-Oct-13 21 A99210 Final Coat Paint 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80 A99470 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 A99260 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 10-Nov-12 22-Dec-12 26-Jan-13 02-Apr-13 85 HVACHVAC 32 10-Nov-12 18-Dec-12 29-Jan-13 05-Mar-13 64 A99270 Duct Installation & Insulation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65 A99280 Chilled Water Pipe Installation & Insulation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65 A99290 Condensate Pipe Installation 7 10-Nov-12 18-Nov-12 29-Jan-13 05-Feb-13 65 A99300 FCU Installation 2 19-Nov-12 20-Nov-12 06-Feb-13 07-Feb-13 65 A99310 Air-Outlet Installation 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 ElectricalElectrical 34 10-Nov-12 20-Dec-12 26-Jan-13 05-Mar-13 62 A99320 Install Conduits in Wall 4 10-Nov-12 13-Nov-12 26-Jan-13 29-Jan-13 62 A99330 Install Cable Trays & Trunking 4 10-Nov-12 13-Nov-12 28-Jan-13 31-Jan-13 64 A99350 Cable Laying for Power 4 14-Nov-12 19-Nov-12 12-Feb-13 16-Feb-13 73 A99340 Wiring for Lighting & Power 4 20-Nov-12 24-Nov-12 04-Feb-13 07-Feb-13 62 A99370 Installation of Sockets 3 16-Dec-12 18-Dec-12 03-Mar-13 05-Mar-13 64 A99360 Installation of Lighting Fittings 5 16-Dec-12 20-Dec-12 28-Feb-13 05-Mar-13 62 PlumbingPlumbing 34 10-Nov-12 20-Dec-12 31-Jan-13 05-Mar-13 62 A99380 H/L Drainage Pipes Installation 3 10-Nov-12 12-Nov-12 31-Jan-13 03-Feb-13 67 A99390 H/L Hot&Cold Water Pipe Installation 3 10-Nov-12 12-Nov-12 31-Jan-13 03-Feb-13 67 A99400 Drainage&Water Pipes Testing 3 13-Nov-12 17-Nov-12 04-Feb-13 06-Feb-13 67 A99410 ElectricalWater Heater Installation 4 13-Nov-12 18-Nov-12 04-Feb-13 07-Feb-13 67 A99420 Floor Drain Fixning 3 18-Dec-12 20-Dec-12 03-Mar-13 05-Mar-13 62 Fire FighFire Fighting 35 10-Nov-12 22-Dec-12 31-Jan-13 02-Apr-13 85 A99460 Fire Fighting Pipe 4 10-Nov-12 13-Nov-12 31-Jan-13 04-Feb-13 67 A99450 Hydro Static Test for Pipes 3 14-Nov-12 18-Nov-12 05-Feb-13 07-Feb-13 67 A99440 Sprinkler Fixing 4 16-Dec-12 19-Dec-12 02-Mar-13 05-Mar-13 63 A99490 Fire Alarm Devices 4 16-Dec-12 19-Dec-12 27-Mar-13 31-Mar-13 85 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 75 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 76. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A99430 Installation of Fire Extingusher&Blanket 2 20-Dec-12 22-Dec-12 01-Apr-13 02-Apr-13 85 Storage RoStorage Room 46 05-Nov-12 30-Dec-12 20-Jan-13 28-Apr-13 100 FinishingFinishing Works 46 05-Nov-12 30-Dec-12 20-Jan-13 28-Apr-13 100 Wet WorWet Works 29 05-Nov-12 10-Dec-12 20-Jan-13 23-Feb-13 62 A98970 Block Works 5 05-Nov-12 10-Nov-12 20-Jan-13 26-Jan-13 62 A98920 Plaster Works 5 17-Nov-12 21-Nov-12 31-Jan-13 05-Feb-13 62 A98940 Installation of Suspended Ceiling Grid 5 27-Nov-12 03-Dec-12 11-Feb-13 16-Feb-13 62 A98930 1st Coat Paint 6 04-Dec-12 10-Dec-12 17-Feb-13 23-Feb-13 62 Fisrt StaFisrt Stage Finishes 13 11-Dec-12 25-Dec-12 24-Feb-13 31-Mar-13 80 A98950 Suspended Ceiling Tiles 5 11-Dec-12 16-Dec-12 24-Feb-13 28-Feb-13 62 A99120 Epoxy Paint Works 2 24-Dec-12 25-Dec-12 30-Mar-13 31-Mar-13 80 Second SSecond Stage Finishes 2 26-Dec-12 27-Dec-12 01-Apr-13 25-Apr-13 100 A98960 Installation of Doors 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80 A98980 Doors Ironmongery 2 26-Dec-12 27-Dec-12 24-Apr-13 25-Apr-13 100 Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 A99110 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 MEP WorkMEP Works 35 11-Nov-12 23-Dec-12 27-Jan-13 28-Mar-13 80 HVACHVAC 32 11-Nov-12 19-Dec-12 31-Jan-13 05-Mar-13 63 A98990 Duct Installation & Insulation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66 A99000 Chilled Water Pipe Installation & Insulation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66 A99010 Condensate Pipe Installation 7 11-Nov-12 19-Nov-12 31-Jan-13 07-Feb-13 66 A99020 FCU Installation 2 20-Nov-12 21-Nov-12 09-Feb-13 10-Feb-13 66 A99030 Air-Outlet Installation 3 17-Dec-12 19-Dec-12 03-Mar-13 05-Mar-13 63 ElectricalElectrical 33 11-Nov-12 20-Dec-12 27-Jan-13 05-Mar-13 62 A99040 Install Conduits in Wall 4 11-Nov-12 14-Nov-12 27-Jan-13 30-Jan-13 62 A99050 Wiring for Lighting & Power 4 22-Nov-12 26-Nov-12 06-Feb-13 10-Feb-13 62 A99060 Installation of Lighting Fittings 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62 PlumbingPlumbing 8 11-Nov-12 20-Nov-12 02-Feb-13 10-Feb-13 67 A99140 H/L Hot&Cold Water Pipe Installation 4 11-Nov-12 14-Nov-12 02-Feb-13 05-Feb-13 67 A99500 H/L Drainage Pipes Installation 4 11-Nov-12 14-Nov-12 02-Feb-13 05-Feb-13 67 A99150 Water Pipes Testing 4 17-Nov-12 20-Nov-12 06-Feb-13 10-Feb-13 67 A99510 Drainage&Water Pipes Testing 4 17-Nov-12 20-Nov-12 06-Feb-13 10-Feb-13 67 Fire FighFire Fighting 35 11-Nov-12 23-Dec-12 03-Feb-13 28-Mar-13 80 A99100 Fire Fighting Pipe 4 11-Nov-12 14-Nov-12 03-Feb-13 06-Feb-13 68 A99090 Hydro Static Test for Pipes 3 17-Nov-12 19-Nov-12 07-Feb-13 10-Feb-13 68 A99080 Sprinkler Fixing 4 17-Dec-12 20-Dec-12 02-Mar-13 05-Mar-13 62 A99130 Fire Alarm Devices 4 17-Dec-12 20-Dec-12 25-Mar-13 28-Mar-13 82 A99070 Installation of Fire Extingusher&Blanket 2 22-Dec-12 23-Dec-12 27-Mar-13 28-Mar-13 80 StaircaseStaircase 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54 Stairs 1Stairs 1 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54 A110650 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54 A110660 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54 A110670 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110680 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110690 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54 A110700 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54 Stairs 2Stairs 2 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54 A110710 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54 A110720 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54 A110730 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110740 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110750 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54 A110760 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54 Stairs 3Stairs 3 43 09-Dec-12 29-Jan-13 12-Feb-13 02-Apr-13 54 A110770 Floor Screed 3 09-Dec-12 11-Dec-12 12-Feb-13 14-Feb-13 54 A110780 Install Handrails 4 12-Dec-12 16-Dec-12 16-Feb-13 19-Feb-13 54 A110790 Ceiling 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110800 Wall 1st Coat Paint 12 17-Dec-12 30-Dec-12 20-Feb-13 05-Mar-13 54 A110810 Install Granite/Terrazo 12 31-Dec-12 14-Jan-13 06-Mar-13 19-Mar-13 54 A110820 Final Coat Paint 12 15-Jan-13 29-Jan-13 20-Mar-13 02-Apr-13 54 Rooms AreaRooms Area 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21 Guest RooGuest Rooms 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21 FinishingFinishing Works 258 05-Nov-12 08-Sep-13 18-Nov-12 02-Oct-13 21 Wet WorWet Works 63 05-Nov-12 20-Jan-13 18-Nov-12 03-Mar-13 35 A93570 Block Works 12 05-Nov-12 19-Nov-12 18-Nov-12 01-Dec-12 10 A93430 Plaster Works 31 21-Nov-12 27-Dec-12 04-Dec-12 09-Jan-13 10 A93460 Installation of Suspended Ceiling Grid (Dry Area) 10 18-Dec-12 29-Dec-12 30-Dec-12 10-Jan-13 10 A93440 Installation of Doors& Windows Sub-frame 22 06-Dec-12 31-Dec-12 06-Feb-13 03-Mar-13 51 A93900 Wall Tiles Work (Wet Area) 22 10-Dec-12 05-Jan-13 07-Jan-13 02-Feb-13 23 A93450 1st Coat Paint 22 25-Dec-12 20-Jan-13 07-Jan-13 02-Feb-13 10 Fisrt StaFisrt Stage Finishes 34 12-Jan-13 20-Feb-13 23-Jan-13 24-Mar-13 27 A93470 Suspended Ceiling Tiles (DryArea) 8 12-Jan-13 20-Jan-13 23-Jan-13 02-Feb-13 10 A93510 Installation of Wardrobes 7 17-Jan-13 26-Jan-13 30-Jan-13 06-Feb-13 10 A93890 Screed Works 15 21-Jan-13 07-Feb-13 03-Feb-13 19-Feb-13 10 A93500 Water Proofing for Wet Area 11 29-Jan-13 10-Feb-13 10-Feb-13 21-Feb-13 10 A93930 Installation of Suspended Ceiling Grid (Wet Area) 7 03-Feb-13 10-Feb-13 14-Feb-13 21-Feb-13 10 A93490 Floor & Wall Tiles Work (Dry Area) 12 30-Jan-13 12-Feb-13 11-Mar-13 24-Mar-13 34 A93920 Suspended Ceiling Tiles (Wet Area) 7 07-Feb-13 14-Feb-13 19-Feb-13 26-Feb-13 10 A93910 Floor Tiles Work (Wet Area) 8 12-Feb-13 20-Feb-13 27-Feb-13 07-Mar-13 13 Second SSecond Stage Finishes 18 17-Feb-13 09-Mar-13 04-Mar-13 28-Apr-13 43 A93520 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 04-Mar-13 11-Mar-13 13 A93580 Doors Ironmongery 7 17-Feb-13 24-Feb-13 21-Apr-13 28-Apr-13 54 A93550 Installation of Balustrades& Handrails 7 25-Feb-13 04-Mar-13 17-Mar-13 24-Mar-13 17 A93870 Installation of Toliets Accessories 12 21-Feb-13 06-Mar-13 18-Mar-13 31-Mar-13 21 A93560 Installation of Vanity Counter 10 25-Feb-13 07-Mar-13 13-Mar-13 24-Mar-13 14 A93530 Installation of Mirrors 11 25-Feb-13 09-Mar-13 12-Mar-13 24-Mar-13 13 Final StaFinal Stage Finishes 155 10-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21 A93480 Final Coat Paint 8 10-Mar-13 18-Mar-13 25-Mar-13 02-Apr-13 13 A93540 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25 A93880 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25 A93590 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 94 12-Nov-12 05-Mar-13 25-Nov-12 02-Apr-13 24 HVACHVAC 74 20-Nov-12 17-Feb-13 06-Dec-12 05-Mar-13 14 A93620 Condensate Pipe Installation 10 20-Nov-12 01-Dec-12 09-Dec-12 19-Dec-12 15 A93600 Duct Installation & Insulation 12 20-Nov-12 04-Dec-12 06-Dec-12 19-Dec-12 13 A93610 Chilled Water Pipe Installation & Insulation 12 20-Nov-12 04-Dec-12 06-Dec-12 19-Dec-12 13 A93630 FCU Installation 8 05-Dec-12 13-Dec-12 20-Dec-12 29-Dec-12 13 A93640 Air-Outlet Installation 6 11-Feb-13 17-Feb-13 27-Feb-13 05-Mar-13 14 ElectricalElectrical 86 12-Nov-12 24-Feb-13 25-Nov-12 02-Apr-13 32 A93650 Install Conduits in Wall 14 12-Nov-12 28-Nov-12 25-Nov-12 11-Dec-12 10 A93660 Install Cable Trays & Trunking 14 20-Nov-12 06-Dec-12 18-Dec-12 03-Jan-13 23 A93700 Cable Laying for Low Current System 6 08-Dec-12 13-Dec-12 05-Jan-13 10-Jan-13 23 A93710 Cable Laying for Power 6 08-Dec-12 13-Dec-12 05-Jan-13 10-Jan-13 23 A93680 Wiring for Low Current System 8 06-Dec-12 15-Dec-12 24-Dec-12 02-Jan-13 15 A93670 Wiring for Lighting & Power 8 10-Dec-12 18-Dec-12 22-Dec-12 30-Dec-12 10 A93690 DB installation,Dressing & Termination 12 07-Jan-13 20-Jan-13 19-Jan-13 02-Feb-13 10 A93740 Installation of Sockets 7 13-Feb-13 20-Feb-13 26-Feb-13 05-Mar-13 11 A93730 Installation of Lighting Fittings 8 16-Feb-13 24-Feb-13 25-Mar-13 02-Apr-13 32 PlumbingPlumbing 92 14-Nov-12 05-Mar-13 27-Nov-12 24-Mar-13 16 A93750 Drainge Pipes in Wall 14 14-Nov-12 01-Dec-12 27-Nov-12 13-Dec-12 10 A93760 H/L Drainage Pipes Installation 10 20-Nov-12 01-Dec-12 27-Jan-13 06-Feb-13 55 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Low Current System Wiring for Lighting & Power DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 76 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 77. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A93770 H/L Hot&Cold Water Pipe Installation 10 20-Nov-12 01-Dec-12 27-Jan-13 06-Feb-13 55 A93820 Water Pipes in Wall 14 14-Nov-12 01-Dec-12 27-Nov-12 13-Dec-12 10 A93780 Drainage&Water Pipes Testing 4 03-Dec-12 06-Dec-12 07-Feb-13 11-Feb-13 55 A93790 ElectricalWater Heater Installation 6 03-Dec-12 09-Dec-12 07-Feb-13 13-Feb-13 55 A93800 Floor Drain Fixning 8 23-Jan-13 02-Feb-13 24-Feb-13 04-Mar-13 26 A93810 Installation of Sanitaryware 8 25-Feb-13 05-Mar-13 16-Mar-13 24-Mar-13 16 Fire FighFire Fighting 80 20-Nov-12 24-Feb-13 09-Dec-12 02-Apr-13 32 A93860 Fire Fighting Pipe 10 20-Nov-12 01-Dec-12 09-Dec-12 19-Dec-12 15 A93850 Hydro Static Test for Pipes 8 03-Dec-12 11-Dec-12 20-Dec-12 29-Dec-12 15 A93830 Installation of Fire Extingusher&Blanket 5 13-Feb-13 18-Feb-13 28-Mar-13 02-Apr-13 37 A93840 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10 A93940 Fire Alarm Devices 8 16-Feb-13 24-Feb-13 16-Mar-13 24-Mar-13 24 6th Floor6th Floor 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21 Public AreaPublic Area 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Lift LobbyLift Lobby - Corridor 124 19-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11 FinishingFinishing Works 124 19-Nov-12 15-Apr-13 21-Jan-13 28-Apr-13 11 Wet WorWet Works 34 19-Nov-12 29-Dec-12 21-Jan-13 24-Mar-13 71 A96040 Block Works 8 19-Nov-12 27-Nov-12 21-Jan-13 30-Jan-13 52 A95980 Plaster Works 7 01-Dec-12 09-Dec-12 03-Feb-13 10-Feb-13 52 A96000 Installation of Suspended Ceiling Grid 6 15-Dec-12 20-Dec-12 16-Feb-13 21-Feb-13 52 A96010 Suspended Ceiling Tiles 6 22-Dec-12 27-Dec-12 23-Feb-13 28-Feb-13 52 A96290 MDF for Lift Lobby Wall 7 22-Dec-12 29-Dec-12 17-Mar-13 24-Mar-13 71 Fisrt StaFisrt Stage Finishes 10 30-Dec-12 10-Jan-13 25-Mar-13 02-Apr-13 69 A96270 Screed Works 3 30-Dec-12 02-Jan-13 25-Mar-13 27-Mar-13 71 A95990 1st Coat Paint 5 06-Jan-13 10-Jan-13 28-Mar-13 02-Apr-13 69 Second SSecond Stage Finishes 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 A96020 Installation of Doors 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 A96050 Doors Ironmongery 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11 A96030 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11 A96280 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11 A96260 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11 MEP WorkMEP Works 31 28-Nov-12 05-Jan-13 31-Jan-13 27-Mar-13 69 HVACHVAC 28 28-Nov-12 31-Dec-12 06-Feb-13 05-Mar-13 53 A96060 Duct Installation & Insulation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57 A96070 Chilled Water Pipe Installation & Insulation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57 A96080 Condensate Pipe Installation 5 28-Nov-12 04-Dec-12 06-Feb-13 11-Feb-13 57 A96090 FCU Installation 3 05-Dec-12 08-Dec-12 12-Feb-13 14-Feb-13 57 A96100 Air-Outlet Installation 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53 ElectricalElectrical 29 28-Nov-12 02-Jan-13 31-Jan-13 05-Mar-13 52 A96110 Install Conduits in Wall 2 28-Nov-12 29-Nov-12 31-Jan-13 02-Feb-13 52 A96120 Install Cable Trays & Trunking 2 28-Nov-12 29-Nov-12 06-Feb-13 07-Feb-13 57 A96160 Cable Laying for Low Current System 2 01-Dec-12 03-Dec-12 20-Feb-13 21-Feb-13 67 A96170 Cable Laying for Power 3 01-Dec-12 04-Dec-12 19-Feb-13 21-Feb-13 66 A96130 Wiring for Lighting & Power 3 10-Dec-12 12-Dec-12 12-Feb-13 14-Feb-13 53 A96140 Wiring for Low Current System 4 10-Dec-12 13-Dec-12 11-Feb-13 14-Feb-13 52 A96150 DB installation,Dressing & Termination 3 22-Dec-12 24-Dec-12 26-Feb-13 28-Feb-13 55 A96190 Installation of Lighting Fittings 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53 A96200 Installation of Sockets 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52 PlumbingPlumbing 5 28-Nov-12 04-Dec-12 10-Feb-13 14-Feb-13 60 A96210 H/L Hot&Cold Water Pipe Installation 5 28-Nov-12 04-Dec-12 10-Feb-13 14-Feb-13 60 Fire FighFire Fighting 31 28-Nov-12 05-Jan-13 06-Feb-13 27-Mar-13 69 A96250 Fire Fighting Pipe 4 28-Nov-12 03-Dec-12 06-Feb-13 10-Feb-13 57 A96240 Hydro Static Test for Pipes 4 04-Dec-12 08-Dec-12 11-Feb-13 14-Feb-13 57 A96230 Sprinkler Fixing 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52 A96300 Fire Alarm Devices 5 29-Dec-12 03-Jan-13 23-Mar-13 27-Mar-13 70 A96220 Installation of Fire Extingusher&Blanket 2 03-Jan-13 05-Jan-13 26-Mar-13 27-Mar-13 69 Electrical /Electrical /Telephone Rooms 35 19-Nov-12 30-Dec-12 31-Jan-13 28-Apr-13 100 FinishingFinishing Works 35 19-Nov-12 30-Dec-12 31-Jan-13 28-Apr-13 100 Wet WorWet Works 14 19-Nov-12 05-Dec-12 31-Jan-13 23-Apr-13 117 A98090 Block Works 3 19-Nov-12 21-Nov-12 31-Jan-13 03-Feb-13 60 A98050 Installation of Doors& Windows Sub-frame 1 25-Nov-12 25-Nov-12 23-Apr-13 23-Apr-13 125 A98040 Plaster Works 4 25-Nov-12 28-Nov-12 06-Feb-13 10-Feb-13 60 A98060 1st Coat Paint 3 03-Dec-12 05-Dec-12 13-Feb-13 16-Feb-13 60 Fisrt StaFisrt Stage Finishes 25 26-Nov-12 25-Dec-12 30-Mar-13 25-Apr-13 102 A98080 Installation of Doors 2 26-Nov-12 27-Nov-12 24-Apr-13 25-Apr-13 125 A98100 Doors Ironmongery 2 26-Nov-12 27-Nov-12 24-Apr-13 25-Apr-13 125 A98150 Epoxy Paint Works 2 24-Dec-12 25-Dec-12 30-Mar-13 31-Mar-13 80 Second SSecond Stage Finishes 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80 A98070 Final Coat Paint 2 26-Dec-12 27-Dec-12 01-Apr-13 02-Apr-13 80 Final StaFinal Stage Finishes 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 A98140 Installation of Sinages 2 29-Dec-12 30-Dec-12 27-Apr-13 28-Apr-13 100 MEP WorkMEP Works 26 22-Nov-12 23-Dec-12 04-Feb-13 28-Mar-13 80 HVACHVAC 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 A98170 Air-Outlet Installation 2 06-Dec-12 08-Dec-12 04-Mar-13 05-Mar-13 73 ElectricalElectrical 26 22-Nov-12 23-Dec-12 04-Feb-13 05-Mar-13 60 A98110 Install Conduits in Wall 2 22-Nov-12 24-Nov-12 04-Feb-13 05-Feb-13 60 A98120 Wiring for Lighting & Power 2 29-Nov-12 01-Dec-12 11-Feb-13 12-Feb-13 60 A114850 Installation of SMDBs 7 06-Dec-12 13-Dec-12 24-Feb-13 03-Mar-13 66 A98130 Installation of Lighting Fittings 2 15-Dec-12 16-Dec-12 04-Mar-13 05-Mar-13 66 A114860 Installation of Telephone System 15 06-Dec-12 23-Dec-12 17-Feb-13 05-Mar-13 60 Fire FighFire Fighting 2 06-Dec-12 08-Dec-12 27-Mar-13 28-Mar-13 93 A98160 Fire Alarm Devices 2 06-Dec-12 08-Dec-12 27-Mar-13 28-Mar-13 93 House KeeHouse Keeping Room 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 247 19-Nov-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 19-Nov-12 19-Dec-12 20-Jan-13 25-Apr-13 107 A99840 Block Works 4 19-Nov-12 22-Nov-12 20-Jan-13 23-Jan-13 51 A99770 Installation of Doors& Windows Sub-frame 1 28-Nov-12 28-Nov-12 25-Apr-13 25-Apr-13 124 A99760 Plaster Works 4 28-Nov-12 03-Dec-12 30-Jan-13 03-Feb-13 51 A99790 Installation of Suspended Ceiling Grid 7 09-Dec-12 16-Dec-12 09-Feb-13 16-Feb-13 51 A99780 1st Coat Paint 3 17-Dec-12 19-Dec-12 17-Feb-13 19-Feb-13 51 Fisrt StaFisrt Stage Finishes 16 20-Dec-12 08-Jan-13 20-Feb-13 31-Mar-13 69 A99800 Suspended Ceiling Tiles 7 20-Dec-12 27-Dec-12 20-Feb-13 27-Feb-13 51 A100080 Screed Works 5 29-Dec-12 03-Jan-13 28-Feb-13 05-Mar-13 51 A99820 Floor Tiles Work 4 05-Jan-13 08-Jan-13 27-Mar-13 31-Mar-13 69 Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91 A99830 Installation of Windows&Doors 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91 A99850 Doors Ironmongery 2 09-Jan-13 10-Jan-13 27-Apr-13 28-Apr-13 91 Final StaFinal Stage Finishes 205 09-Jan-13 08-Sep-13 01-Apr-13 02-Oct-13 21 A99810 Final Coat Paint 2 09-Jan-13 10-Jan-13 01-Apr-13 02-Apr-13 69 A100070 Installation of Sinages 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 A99860 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 24-Nov-12 05-Jan-13 26-Jan-13 02-Apr-13 74 HVACHVAC 32 24-Nov-12 31-Dec-12 29-Jan-13 05-Mar-13 53 A99870 Duct Installation & Insulation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54 A99880 Chilled Water Pipe Installation & Insulation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54 A99890 Condensate Pipe Installation 7 24-Nov-12 01-Dec-12 29-Jan-13 05-Feb-13 54 A99900 FCU Installation 2 03-Dec-12 04-Dec-12 06-Feb-13 07-Feb-13 54 A99910 Air-Outlet Installation 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53 ElectricalElectrical 34 24-Nov-12 03-Jan-13 26-Jan-13 05-Mar-13 51 A99920 Install Conduits in Wall 4 24-Nov-12 27-Nov-12 26-Jan-13 29-Jan-13 51 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 77 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 78. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A99930 Install Cable Trays & Trunking 4 24-Nov-12 27-Nov-12 28-Jan-13 31-Jan-13 53 A99950 Cable Laying for Power 4 28-Nov-12 03-Dec-12 12-Feb-13 16-Feb-13 62 A99940 Wiring for Lighting & Power 4 04-Dec-12 08-Dec-12 04-Feb-13 07-Feb-13 51 A99970 Installation of Sockets 3 29-Dec-12 31-Dec-12 03-Mar-13 05-Mar-13 53 A99960 Installation of Lighting Fittings 5 29-Dec-12 03-Jan-13 28-Feb-13 05-Mar-13 51 PlumbingPlumbing 34 24-Nov-12 03-Jan-13 31-Jan-13 05-Mar-13 51 A99980 H/L Drainage Pipes Installation 3 24-Nov-12 26-Nov-12 31-Jan-13 03-Feb-13 56 A99990 H/L Hot&Cold Water Pipe Installation 3 24-Nov-12 26-Nov-12 31-Jan-13 03-Feb-13 56 A100000 Drainage&Water Pipes Testing 3 27-Nov-12 29-Nov-12 04-Feb-13 06-Feb-13 56 A100010 ElectricalWater Heater Installation 4 27-Nov-12 01-Dec-12 04-Feb-13 07-Feb-13 56 A100020 Floor Drain Fixning 3 31-Dec-12 03-Jan-13 03-Mar-13 05-Mar-13 51 Fire FighFire Fighting 35 24-Nov-12 05-Jan-13 31-Jan-13 02-Apr-13 74 A100060 Fire Fighting Pipe 4 24-Nov-12 27-Nov-12 31-Jan-13 04-Feb-13 56 A100050 Hydro Static Test for Pipes 3 28-Nov-12 01-Dec-12 05-Feb-13 07-Feb-13 56 A100040 Sprinkler Fixing 4 29-Dec-12 02-Jan-13 02-Mar-13 05-Mar-13 52 A100090 Fire Alarm Devices 4 29-Dec-12 02-Jan-13 27-Mar-13 31-Mar-13 74 A100030 Installation of Fire Extingusher&Blanket 2 03-Jan-13 05-Jan-13 01-Apr-13 02-Apr-13 74 Storage RoStorage Room 46 19-Nov-12 13-Jan-13 20-Jan-13 28-Apr-13 89 FinishingFinishing Works 46 19-Nov-12 13-Jan-13 20-Jan-13 28-Apr-13 89 Wet WorWet Works 29 19-Nov-12 23-Dec-12 20-Jan-13 23-Feb-13 51 A99570 Block Works 5 19-Nov-12 24-Nov-12 20-Jan-13 26-Jan-13 51 A99520 Plaster Works 5 29-Nov-12 05-Dec-12 31-Jan-13 05-Feb-13 51 A99540 Installation of Suspended Ceiling Grid 5 11-Dec-12 16-Dec-12 11-Feb-13 16-Feb-13 51 A99530 1st Coat Paint 6 17-Dec-12 23-Dec-12 17-Feb-13 23-Feb-13 51 Fisrt StaFisrt Stage Finishes 13 24-Dec-12 08-Jan-13 24-Feb-13 31-Mar-13 69 A99550 Suspended Ceiling Tiles 5 24-Dec-12 29-Dec-12 24-Feb-13 28-Feb-13 51 A99720 Epoxy Paint Works 2 07-Jan-13 08-Jan-13 30-Mar-13 31-Mar-13 69 Second SSecond Stage Finishes 2 09-Jan-13 10-Jan-13 01-Apr-13 25-Apr-13 89 A99560 Installation of Doors 2 09-Jan-13 10-Jan-13 01-Apr-13 02-Apr-13 69 A99580 Doors Ironmongery 2 09-Jan-13 10-Jan-13 24-Apr-13 25-Apr-13 89 Final StaFinal Stage Finishes 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 A99710 Installation of Sinages 2 12-Jan-13 13-Jan-13 27-Apr-13 28-Apr-13 89 MEP WorkMEP Works 35 25-Nov-12 06-Jan-13 27-Jan-13 28-Mar-13 69 HVACHVAC 32 25-Nov-12 02-Jan-13 31-Jan-13 05-Mar-13 52 A99590 Duct Installation & Insulation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55 A99600 Chilled Water Pipe Installation & Insulation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55 A99610 Condensate Pipe Installation 7 25-Nov-12 03-Dec-12 31-Jan-13 07-Feb-13 55 A99620 FCU Installation 2 04-Dec-12 05-Dec-12 09-Feb-13 10-Feb-13 55 A99630 Air-Outlet Installation 3 30-Dec-12 02-Jan-13 03-Mar-13 05-Mar-13 52 ElectricalElectrical 33 25-Nov-12 03-Jan-13 27-Jan-13 05-Mar-13 51 A99640 Install Conduits in Wall 4 25-Nov-12 28-Nov-12 27-Jan-13 30-Jan-13 51 A99650 Wiring for Lighting & Power 4 06-Dec-12 10-Dec-12 06-Feb-13 10-Feb-13 51 A99660 Installation of Lighting Fittings 4 30-Dec-12 03-Jan-13 02-Mar-13 05-Mar-13 51 PlumbingPlumbing 8 25-Nov-12 04-Dec-12 02-Feb-13 10-Feb-13 56 A99740 H/L Hot&Cold Water Pipe Installation 4 25-Nov-12 28-Nov-12 02-Feb-13 05-Feb-13 56 A100100 H/L Drainage Pipes Installation 4 25-Nov-12 28-Nov-12 02-Feb-13 05-Feb-13 56 A99750 Water Pipes Testing 4 29-Nov-12 04-Dec-12 06-Feb-13 10-Feb-13 56 A100110 Drainage&Water Pipes Testing 4 29-Nov-12 04-Dec-12 06-Feb-13 10-Feb-13 56 Fire FighFire Fighting 35 25-Nov-12 06-Jan-13 03-Feb-13 28-Mar-13 69 A99700 Fire Fighting Pipe 4 25-Nov-12 28-Nov-12 03-Feb-13 06-Feb-13 57 A99690 Hydro Static Test for Pipes 3 29-Nov-12 03-Dec-12 07-Feb-13 10-Feb-13 57 A99680 Sprinkler Fixing 4 30-Dec-12 03-Jan-13 02-Mar-13 05-Mar-13 51 A99730 Fire Alarm Devices 4 30-Dec-12 03-Jan-13 25-Mar-13 28-Mar-13 71 A99670 Installation of Fire Extingusher&Blanket 2 05-Jan-13 06-Jan-13 27-Mar-13 28-Mar-13 69 StaircaseStaircase 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37 Stairs 1Stairs 1 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37 A110830 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37 A110840 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37 A110850 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110860 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110870 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37 A110880 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37 Stairs 2Stairs 2 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37 A110890 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37 A110900 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37 A110910 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110920 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110930 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37 A110940 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37 Stairs 3Stairs 3 43 29-Dec-12 18-Feb-13 12-Feb-13 02-Apr-13 37 A110950 Floor Screed 3 29-Dec-12 31-Dec-12 12-Feb-13 14-Feb-13 37 A110960 Install Handrails 4 02-Jan-13 06-Jan-13 16-Feb-13 19-Feb-13 37 A110970 Ceiling 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110980 Wall 1st Coat Paint 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 A110990 Install Granite/Terrazo 12 21-Jan-13 04-Feb-13 06-Mar-13 19-Mar-13 37 A111000 Final Coat Paint 12 05-Feb-13 18-Feb-13 20-Mar-13 02-Apr-13 37 Rooms AreaRooms Area 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21 Guest RooGuest Rooms 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21 FinishingFinishing Works 247 19-Nov-12 08-Sep-13 03-Dec-12 02-Oct-13 21 Wet WorWet Works 63 19-Nov-12 03-Feb-13 03-Dec-12 03-Mar-13 24 A94090 Block Works 12 19-Nov-12 03-Dec-12 03-Dec-12 16-Dec-12 11 A93950 Plaster Works 31 05-Dec-12 10-Jan-13 18-Dec-12 23-Jan-13 11 A93980 Installation of Suspended Ceiling Grid (Dry Area) 10 31-Dec-12 12-Jan-13 14-Jan-13 26-Jan-13 11 A93960 Installation of Doors& Windows Sub-frame 22 19-Dec-12 14-Jan-13 06-Feb-13 03-Mar-13 40 A94420 Wall Tiles Work (Wet Area) 22 23-Dec-12 17-Jan-13 10-Jan-13 05-Feb-13 15 A93970 1st Coat Paint 22 08-Jan-13 03-Feb-13 21-Jan-13 16-Feb-13 11 Fisrt StaFisrt Stage Finishes 29 16-Jan-13 19-Feb-13 30-Jan-13 24-Mar-13 28 A93990 Suspended Ceiling Tiles (DryArea) 8 16-Jan-13 26-Jan-13 30-Jan-13 07-Feb-13 11 A94030 Installation of Wardrobes 7 20-Jan-13 28-Jan-13 03-Feb-13 10-Feb-13 11 A94020 Water Proofing for Wet Area 11 29-Jan-13 10-Feb-13 11-Feb-13 23-Feb-13 11 A94410 Screed Works 15 23-Jan-13 10-Feb-13 06-Feb-13 23-Feb-13 11 A94450 Installation of Suspended Ceiling Grid (Wet Area) 7 03-Feb-13 10-Feb-13 16-Feb-13 23-Feb-13 11 A94440 Suspended Ceiling Tiles (Wet Area) 7 06-Feb-13 13-Feb-13 19-Feb-13 26-Feb-13 11 A94010 Floor & Wall Tiles Work (Dry Area) 12 02-Feb-13 14-Feb-13 11-Mar-13 24-Mar-13 32 A94430 Floor Tiles Work (Wet Area) 8 11-Feb-13 19-Feb-13 27-Feb-13 07-Mar-13 14 Second SSecond Stage Finishes 18 16-Feb-13 07-Mar-13 04-Mar-13 28-Apr-13 44 A94040 Installation of Windows&Doors 7 16-Feb-13 23-Feb-13 04-Mar-13 11-Mar-13 14 A94100 Doors Ironmongery 7 16-Feb-13 23-Feb-13 21-Apr-13 28-Apr-13 55 A94070 Installation of Balustrades& Handrails 7 24-Feb-13 03-Mar-13 17-Mar-13 24-Mar-13 18 A94390 Installation of Toliets Accessories 12 20-Feb-13 05-Mar-13 18-Mar-13 31-Mar-13 22 A94080 Installation of Vanity Counter 10 24-Feb-13 06-Mar-13 13-Mar-13 24-Mar-13 15 A94050 Installation of Mirrors 11 24-Feb-13 07-Mar-13 12-Mar-13 24-Mar-13 14 Final StaFinal Stage Finishes 156 09-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21 A94000 Final Coat Paint 8 09-Mar-13 17-Mar-13 25-Mar-13 02-Apr-13 14 A94060 Installation of Carpets 8 21-Mar-13 30-Mar-13 20-Apr-13 28-Apr-13 25 A94400 Installation of Sinages 7 23-Mar-13 30-Mar-13 21-Apr-13 28-Apr-13 25 A94110 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 82 26-Nov-12 04-Mar-13 10-Dec-12 02-Apr-13 25 HVACHVAC 62 04-Dec-12 16-Feb-13 20-Dec-12 05-Mar-13 15 A94140 Condensate Pipe Installation 10 04-Dec-12 15-Dec-12 23-Dec-12 03-Jan-13 16 A94120 Duct Installation & Insulation 12 04-Dec-12 17-Dec-12 20-Dec-12 03-Jan-13 14 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Suspended Ceiling Grid (Dry Area) Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Water Proofing for Wet Area Screed Works Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor & Wall Tiles Work (Dry Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Final Coat Paint Installation of Carpets Installation of Sinages Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 78 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 79. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A94130 Chilled Water Pipe Installation & Insulation 12 04-Dec-12 17-Dec-12 20-Dec-12 03-Jan-13 14 A94150 FCU Installation 8 18-Dec-12 26-Dec-12 05-Jan-13 13-Jan-13 14 A94160 Air-Outlet Installation 6 10-Feb-13 16-Feb-13 27-Feb-13 05-Mar-13 15 ElectricalElectrical 70 26-Nov-12 18-Feb-13 10-Dec-12 05-Mar-13 13 A94170 Install Conduits in Wall 14 26-Nov-12 12-Dec-12 10-Dec-12 25-Dec-12 11 A94180 Install Cable Trays & Trunking 14 04-Dec-12 19-Dec-12 02-Jan-13 17-Jan-13 24 A94220 Cable Laying for Low Current System 6 20-Dec-12 26-Dec-12 19-Jan-13 26-Jan-13 24 A94230 Cable Laying for Power 6 20-Dec-12 26-Dec-12 19-Jan-13 26-Jan-13 24 A94200 Wiring for Low Current System 8 19-Dec-12 27-Dec-12 08-Jan-13 16-Jan-13 16 A94190 Wiring for Lighting & Power 8 23-Dec-12 31-Dec-12 06-Jan-13 14-Jan-13 11 A94210 DB installation,Dressing & Termination 10 14-Jan-13 26-Jan-13 28-Jan-13 07-Feb-13 11 A94260 Installation of Sockets 7 10-Feb-13 17-Feb-13 26-Feb-13 05-Mar-13 14 A94250 Installation of Lighting Fittings 8 10-Feb-13 18-Feb-13 25-Feb-13 05-Mar-13 13 PlumbingPlumbing 80 28-Nov-12 04-Mar-13 12-Dec-12 24-Mar-13 17 A94270 Drainge Pipes in Wall 14 28-Nov-12 15-Dec-12 12-Dec-12 27-Dec-12 11 A94280 H/L Drainage Pipes Installation 10 04-Dec-12 15-Dec-12 28-Jan-13 07-Feb-13 45 A94290 H/L Hot&Cold Water Pipe Installation 10 04-Dec-12 15-Dec-12 28-Jan-13 07-Feb-13 45 A94340 Water Pipes in Wall 14 28-Nov-12 15-Dec-12 12-Dec-12 27-Dec-12 11 A94300 Drainage&Water Pipes Testing 4 16-Dec-12 19-Dec-12 09-Feb-13 12-Feb-13 45 A94310 ElectricalWater Heater Installation 6 16-Dec-12 22-Dec-12 09-Feb-13 14-Feb-13 45 A94320 Floor Drain Fixning 8 27-Jan-13 04-Feb-13 24-Feb-13 04-Mar-13 24 A94330 Installation of Sanitaryware 8 24-Feb-13 04-Mar-13 16-Mar-13 24-Mar-13 17 Fire FighFire Fighting 71 04-Dec-12 26-Feb-13 23-Dec-12 02-Apr-13 30 A94380 Fire Fighting Pipe 10 04-Dec-12 15-Dec-12 23-Dec-12 03-Jan-13 16 A94370 Hydro Static Test for Pipes 8 16-Dec-12 24-Dec-12 05-Jan-13 13-Jan-13 16 A94360 Sprinkler Fixing 8 12-Feb-13 20-Feb-13 25-Feb-13 05-Mar-13 11 A94460 Fire Alarm Devices 8 14-Feb-13 23-Feb-13 16-Mar-13 24-Mar-13 25 A94350 Installation of Fire Extingusher&Blanket 5 21-Feb-13 26-Feb-13 28-Mar-13 02-Apr-13 30 7th Floor7th Floor 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21 Public AreaPublic Area 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Lift LobbyLift Lobby - Corridor 112 04-Dec-12 15-Apr-13 26-Jan-13 28-Apr-13 11 FinishingFinishing Works 112 04-Dec-12 15-Apr-13 26-Jan-13 28-Apr-13 11 Wet WorWet Works 31 04-Dec-12 09-Jan-13 26-Jan-13 24-Mar-13 62 A96370 Block Works 8 04-Dec-12 12-Dec-12 26-Jan-13 03-Feb-13 43 A96310 Plaster Works 7 16-Dec-12 23-Dec-12 06-Feb-13 13-Feb-13 43 A96330 Installation of Suspended Ceiling Grid 6 25-Dec-12 31-Dec-12 16-Feb-13 21-Feb-13 43 A96340 Suspended Ceiling Tiles 6 02-Jan-13 08-Jan-13 23-Feb-13 28-Feb-13 43 A96620 MDF for Lift Lobby Wall 7 02-Jan-13 09-Jan-13 17-Mar-13 24-Mar-13 62 Fisrt StaFisrt Stage Finishes 10 10-Jan-13 21-Jan-13 25-Mar-13 02-Apr-13 60 A96600 Screed Works 3 10-Jan-13 13-Jan-13 25-Mar-13 27-Mar-13 62 A96320 1st Coat Paint 5 16-Jan-13 21-Jan-13 28-Mar-13 02-Apr-13 60 Second SSecond Stage Finishes 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80 A96350 Installation of Doors 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80 A96380 Doors Ironmongery 2 22-Jan-13 23-Jan-13 27-Apr-13 28-Apr-13 80 Final StaFinal Stage Finishes 22 21-Mar-13 15-Apr-13 03-Apr-13 28-Apr-13 11 A96360 Installation of Carpets 10 21-Mar-13 01-Apr-13 03-Apr-13 14-Apr-13 11 A96610 Fixing of Wall Covering 7 02-Apr-13 09-Apr-13 15-Apr-13 22-Apr-13 11 A96590 Installation of Sinages 5 10-Apr-13 15-Apr-13 23-Apr-13 28-Apr-13 11 MEP WorkMEP Works 28 13-Dec-12 15-Jan-13 04-Feb-13 27-Mar-13 60 HVACHVAC 25 13-Dec-12 12-Jan-13 06-Feb-13 05-Mar-13 44 A96390 Duct Installation & Insulation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45 A96400 Chilled Water Pipe Installation & Insulation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45 A96410 Condensate Pipe Installation 5 13-Dec-12 18-Dec-12 06-Feb-13 11-Feb-13 45 A96420 FCU Installation 3 19-Dec-12 22-Dec-12 12-Feb-13 14-Feb-13 45 A96430 Air-Outlet Installation 3 09-Jan-13 12-Jan-13 03-Mar-13 05-Mar-13 44 ElectricalElectrical 26 13-Dec-12 13-Jan-13 04-Feb-13 05-Mar-13 43 A96440 Install Conduits in Wall 2 13-Dec-12 15-Dec-12 04-Feb-13 05-Feb-13 43 A96450 Install Cable Trays & Trunking 2 13-Dec-12 15-Dec-12 10-Feb-13 11-Feb-13 48 A96490 Cable Laying for Low Current System 2 16-Dec-12 17-Dec-12 20-Feb-13 21-Feb-13 55 A96500 Cable Laying for Power 3 16-Dec-12 18-Dec-12 19-Feb-13 21-Feb-13 54 A96460 Wiring for Lighting & Power 3 22-Dec-12 24-Dec-12 12-Feb-13 14-Feb-13 43 A96470 Wiring for Low Current System 3 22-Dec-12 24-Dec-12 12-Feb-13 14-Feb-13 43 A96480 DB installation,Dressing & Termination 3 02-Jan-13 05-Jan-13 26-Feb-13 28-Feb-13 46 A96520 Installation of Lighting Fittings 3 09-Jan-13 12-Jan-13 03-Mar-13 05-Mar-13 44 A96530 Installation of Sockets 4 09-Jan-13 13-Jan-13 02-Mar-13 05-Mar-13 43 PlumbingPlumbing 5 13-Dec-12 18-Dec-12 10-Feb-13 14-Feb-13 48 A96540 H/L Hot&Cold Water Pipe Installation 5 13-Dec-12 18-Dec-12 10-Feb-13 14-Feb-13 48 Fire FighFire Fighting 28 13-Dec-12 15-Jan-13 06-Feb-13 27-Mar-13 60 A96580 Fire Fighting Pipe 4 13-Dec-12 17-Dec-12 06-Feb-13 10-Feb-13 45 A96570 Hydro Static Test for Pipes 4 18-Dec-12 22-Dec-12 11-Feb-13 14-Feb-13 45 A96560 Sprinkler Fixing 4 09-Jan-13 13-Jan-13 02-Mar-13 05-Mar-13 43 A96630 Fire Alarm Devices 5 09-Jan-13 14-Jan-13 23-Mar-13 27-Mar-13 61 A96550 Installation of Fire Extingusher&Blanket 2 14-Jan-13 15-Jan-13 26-Mar-13 27-Mar-13 60 Electrical /Electrical /Telephone Rooms 35 04-Dec-12 14-Jan-13 31-Jan-13 28-Apr-13 88 FinishingFinishing Works 35 04-Dec-12 14-Jan-13 31-Jan-13 28-Apr-13 88 Wet WorWet Works 14 04-Dec-12 19-Dec-12 31-Jan-13 23-Apr-13 105 A98230 Block Works 3 04-Dec-12 06-Dec-12 31-Jan-13 03-Feb-13 48 A98190 Installation of Doors& Windows Sub-frame 1 10-Dec-12 10-Dec-12 23-Apr-13 23-Apr-13 113 A98180 Plaster Works 4 10-Dec-12 13-Dec-12 06-Feb-13 10-Feb-13 48 A98200 1st Coat Paint 3 17-Dec-12 19-Dec-12 13-Feb-13 16-Feb-13 48 Fisrt StaFisrt Stage Finishes 25 11-Dec-12 09-Jan-13 30-Mar-13 25-Apr-13 90 A98220 Installation of Doors 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113 A98240 Doors Ironmongery 2 11-Dec-12 12-Dec-12 24-Apr-13 25-Apr-13 113 A98290 Epoxy Paint Works 2 08-Jan-13 09-Jan-13 30-Mar-13 31-Mar-13 68 Second SSecond Stage Finishes 2 10-Jan-13 12-Jan-13 01-Apr-13 02-Apr-13 68 A98210 Final Coat Paint 2 10-Jan-13 12-Jan-13 01-Apr-13 02-Apr-13 68 Final StaFinal Stage Finishes 2 13-Jan-13 14-Jan-13 27-Apr-13 28-Apr-13 88 A98280 Installation of Sinages 2 13-Jan-13 14-Jan-13 27-Apr-13 28-Apr-13 88 MEP WorkMEP Works 26 08-Dec-12 07-Jan-13 04-Feb-13 28-Mar-13 68 HVACHVAC 2 20-Dec-12 22-Dec-12 04-Mar-13 05-Mar-13 61 A98310 Air-Outlet Installation 2 20-Dec-12 22-Dec-12 04-Mar-13 05-Mar-13 61 ElectricalElectrical 26 08-Dec-12 07-Jan-13 04-Feb-13 05-Mar-13 48 A98250 Install Conduits in Wall 2 08-Dec-12 09-Dec-12 04-Feb-13 05-Feb-13 48 A98260 Wiring for Lighting & Power 2 15-Dec-12 16-Dec-12 11-Feb-13 12-Feb-13 48 A114870 Installation of SMDBs 7 20-Dec-12 27-Dec-12 24-Feb-13 03-Mar-13 54 A98270 Installation of Lighting Fittings 2 29-Dec-12 30-Dec-12 04-Mar-13 05-Mar-13 54 A114880 Installation of Telephone System 15 20-Dec-12 07-Jan-13 17-Feb-13 05-Mar-13 48 Fire FighFire Fighting 2 20-Dec-12 22-Dec-12 27-Mar-13 28-Mar-13 81 A98300 Fire Alarm Devices 2 20-Dec-12 22-Dec-12 27-Mar-13 28-Mar-13 81 House KeeHouse Keeping Room 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21 FinishingFinishing Works 235 04-Dec-12 08-Sep-13 20-Jan-13 02-Oct-13 21 Wet WorWet Works 26 04-Dec-12 03-Jan-13 20-Jan-13 25-Apr-13 95 A100440 Block Works 4 04-Dec-12 08-Dec-12 20-Jan-13 23-Jan-13 39 A100370 Installation of Doors& Windows Sub-frame 1 13-Dec-12 13-Dec-12 25-Apr-13 25-Apr-13 112 A100360 Plaster Works 4 13-Dec-12 17-Dec-12 30-Jan-13 03-Feb-13 39 A100390 Installation of Suspended Ceiling Grid 7 23-Dec-12 30-Dec-12 09-Feb-13 16-Feb-13 39 A100380 1st Coat Paint 3 31-Dec-12 03-Jan-13 17-Feb-13 19-Feb-13 39 Fisrt StaFisrt Stage Finishes 16 05-Jan-13 22-Jan-13 20-Feb-13 31-Mar-13 57 A100400 Suspended Ceiling Tiles 7 05-Jan-13 12-Jan-13 20-Feb-13 27-Feb-13 39 A100680 Screed Works 5 13-Jan-13 17-Jan-13 28-Feb-13 05-Mar-13 39 A100420 Floor Tiles Work 4 19-Jan-13 22-Jan-13 27-Mar-13 31-Mar-13 57 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Low Current System Wiring for Lighting & Power DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works 1st Coat Paint Installation of Doors Doors Ironmongery Installation of Carpets Fixing of Wall Covering Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Installation of Sockets H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 79 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 80. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Second SSecond Stage Finishes 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79 A100430 Installation of Windows&Doors 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79 A100450 Doors Ironmongery 2 23-Jan-13 26-Jan-13 27-Apr-13 28-Apr-13 79 Final StaFinal Stage Finishes 193 23-Jan-13 08-Sep-13 01-Apr-13 02-Oct-13 21 A100410 Final Coat Paint 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57 A100670 Installation of Sinages 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77 A100460 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 35 09-Dec-12 19-Jan-13 26-Jan-13 02-Apr-13 62 HVACHVAC 32 09-Dec-12 15-Jan-13 29-Jan-13 05-Mar-13 41 A100470 Duct Installation & Insulation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42 A100480 Chilled Water Pipe Installation & Insulation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42 A100490 Condensate Pipe Installation 7 09-Dec-12 16-Dec-12 29-Jan-13 05-Feb-13 42 A100500 FCU Installation 2 17-Dec-12 18-Dec-12 06-Feb-13 07-Feb-13 42 A100510 Air-Outlet Installation 3 13-Jan-13 15-Jan-13 03-Mar-13 05-Mar-13 41 ElectricalElectrical 34 09-Dec-12 17-Jan-13 26-Jan-13 05-Mar-13 39 A100520 Install Conduits in Wall 4 09-Dec-12 12-Dec-12 26-Jan-13 29-Jan-13 39 A100530 Install Cable Trays & Trunking 4 09-Dec-12 12-Dec-12 28-Jan-13 31-Jan-13 41 A100550 Cable Laying for Power 4 13-Dec-12 17-Dec-12 12-Feb-13 16-Feb-13 50 A100540 Wiring for Lighting & Power 4 18-Dec-12 22-Dec-12 04-Feb-13 07-Feb-13 39 A100560 Installation of Lighting Fittings 3 13-Jan-13 15-Jan-13 03-Mar-13 05-Mar-13 41 A100570 Installation of Sockets 5 13-Jan-13 17-Jan-13 28-Feb-13 05-Mar-13 39 PlumbingPlumbing 34 09-Dec-12 17-Jan-13 31-Jan-13 05-Mar-13 39 A100580 H/L Drainage Pipes Installation 3 09-Dec-12 11-Dec-12 31-Jan-13 03-Feb-13 44 A100590 H/L Hot&Cold Water Pipe Installation 3 09-Dec-12 11-Dec-12 31-Jan-13 03-Feb-13 44 A100600 Drainage&Water Pipes Testing 3 12-Dec-12 15-Dec-12 04-Feb-13 06-Feb-13 44 A100610 ElectricalWater Heater Installation 4 12-Dec-12 16-Dec-12 04-Feb-13 07-Feb-13 44 A100620 Floor Drain Fixning 3 15-Jan-13 17-Jan-13 03-Mar-13 05-Mar-13 39 Fire FighFire Fighting 35 09-Dec-12 19-Jan-13 31-Jan-13 02-Apr-13 62 A100660 Fire Fighting Pipe 4 09-Dec-12 12-Dec-12 31-Jan-13 04-Feb-13 44 A100650 Hydro Static Test for Pipes 3 13-Dec-12 16-Dec-12 05-Feb-13 07-Feb-13 44 A100640 Sprinkler Fixing 4 13-Jan-13 16-Jan-13 02-Mar-13 05-Mar-13 40 A100690 Fire Alarm Devices 4 13-Jan-13 16-Jan-13 27-Mar-13 31-Mar-13 62 A100630 Installation of Fire Extingusher&Blanket 2 17-Jan-13 19-Jan-13 01-Apr-13 02-Apr-13 62 Storage RoStorage Room 46 04-Dec-12 28-Jan-13 20-Jan-13 28-Apr-13 77 FinishingFinishing Works 46 04-Dec-12 28-Jan-13 20-Jan-13 28-Apr-13 77 Wet WorWet Works 29 04-Dec-12 07-Jan-13 20-Jan-13 23-Feb-13 39 A100170 Block Works 5 04-Dec-12 09-Dec-12 20-Jan-13 26-Jan-13 39 A100120 Plaster Works 5 15-Dec-12 19-Dec-12 31-Jan-13 05-Feb-13 39 A100140 Installation of Suspended Ceiling Grid 5 25-Dec-12 30-Dec-12 11-Feb-13 16-Feb-13 39 A100130 1st Coat Paint 6 31-Dec-12 07-Jan-13 17-Feb-13 23-Feb-13 39 Fisrt StaFisrt Stage Finishes 13 08-Jan-13 22-Jan-13 24-Feb-13 31-Mar-13 57 A100150 Suspended Ceiling Tiles 5 08-Jan-13 13-Jan-13 24-Feb-13 28-Feb-13 39 A100320 Epoxy Paint Works 2 21-Jan-13 22-Jan-13 30-Mar-13 31-Mar-13 57 Second SSecond Stage Finishes 2 23-Jan-13 26-Jan-13 01-Apr-13 25-Apr-13 77 A100160 Installation of Doors 2 23-Jan-13 26-Jan-13 01-Apr-13 02-Apr-13 57 A100180 Doors Ironmongery 2 23-Jan-13 26-Jan-13 24-Apr-13 25-Apr-13 77 Final StaFinal Stage Finishes 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77 A100310 Installation of Sinages 2 27-Jan-13 28-Jan-13 27-Apr-13 28-Apr-13 77 MEP WorkMEP Works 35 10-Dec-12 20-Jan-13 27-Jan-13 28-Mar-13 57 HVACHVAC 32 10-Dec-12 16-Jan-13 31-Jan-13 05-Mar-13 40 A100190 Duct Installation & Insulation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43 A100200 Chilled Water Pipe Installation & Insulation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43 A100210 Condensate Pipe Installation 7 10-Dec-12 17-Dec-12 31-Jan-13 07-Feb-13 43 A100220 FCU Installation 2 18-Dec-12 19-Dec-12 09-Feb-13 10-Feb-13 43 A100230 Air-Outlet Installation 3 14-Jan-13 16-Jan-13 03-Mar-13 05-Mar-13 40 ElectricalElectrical 33 10-Dec-12 17-Jan-13 27-Jan-13 05-Mar-13 39 A100240 Install Conduits in Wall 4 10-Dec-12 13-Dec-12 27-Jan-13 30-Jan-13 39 A100250 Wiring for Lighting & Power 4 20-Dec-12 24-Dec-12 06-Feb-13 10-Feb-13 39 A100260 Installation of Lighting Fittings 4 14-Jan-13 17-Jan-13 02-Mar-13 05-Mar-13 39 PlumbingPlumbing 8 10-Dec-12 18-Dec-12 02-Feb-13 10-Feb-13 44 A100340 H/L Hot&Cold Water Pipe Installation 4 10-Dec-12 13-Dec-12 02-Feb-13 05-Feb-13 44 A100700 H/L Drainage Pipes Installation 4 10-Dec-12 13-Dec-12 02-Feb-13 05-Feb-13 44 A100350 Water Pipes Testing 4 15-Dec-12 18-Dec-12 06-Feb-13 10-Feb-13 44 A100710 Drainage&Water Pipes Testing 4 15-Dec-12 18-Dec-12 06-Feb-13 10-Feb-13 44 Fire FighFire Fighting 35 10-Dec-12 20-Jan-13 03-Feb-13 28-Mar-13 57 A100300 Fire Fighting Pipe 4 10-Dec-12 13-Dec-12 03-Feb-13 06-Feb-13 45 A100290 Hydro Static Test for Pipes 3 15-Dec-12 17-Dec-12 07-Feb-13 10-Feb-13 45 A100280 Sprinkler Fixing 4 14-Jan-13 17-Jan-13 02-Mar-13 05-Mar-13 39 A100330 Fire Alarm Devices 4 14-Jan-13 17-Jan-13 25-Mar-13 28-Mar-13 59 A100270 Installation of Fire Extingusher&Blanket 2 19-Jan-13 20-Jan-13 27-Mar-13 28-Mar-13 57 StaircaseStaircase 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32 Stairs 1Stairs 1 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32 A111010 Floor Screed 3 05-Jan-13 07-Jan-13 12-Feb-13 14-Feb-13 32 A111020 Install Handrails 4 08-Jan-13 12-Jan-13 16-Feb-13 19-Feb-13 32 A111030 Ceiling 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32 A111040 Wall 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32 A111050 Install Granite/Terrazo 12 28-Jan-13 10-Feb-13 06-Mar-13 19-Mar-13 32 A111060 Final Coat Paint 12 11-Feb-13 24-Feb-13 20-Mar-13 02-Apr-13 32 Stairs 2Stairs 2 43 05-Jan-13 24-Feb-13 12-Feb-13 02-Apr-13 32 A111070 Floor Screed 3 05-Jan-13 07-Jan-13 12-Feb-13 14-Feb-13 32 A111080 Install Handrails 4 08-Jan-13 12-Jan-13 16-Feb-13 19-Feb-13 32 A111090 Ceiling 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32 A111100 Wall 1st Coat Paint 12 13-Jan-13 27-Jan-13 20-Feb-13 05-Mar-13 32 A111110 Install Granite/Terrazo 12 28-Jan-13 10-Feb-13 06-Mar-13 19-Mar-13 32 A111120 Final Coat Paint 12 11-Feb-13 24-Feb-13 20-Mar-13 02-Apr-13 32 Rooms AreaRooms Area 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21 Guest RooGuest Rooms 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21 FinishingFinishing Works 235 04-Dec-12 08-Sep-13 16-Dec-12 02-Oct-13 21 Wet WorWet Works 52 04-Dec-12 04-Feb-13 16-Dec-12 03-Mar-13 23 A94610 Block Works 12 04-Dec-12 17-Dec-12 16-Dec-12 29-Dec-12 10 A94500 Installation of Suspended Ceiling Grid (Dry Area) 10 05-Jan-13 15-Jan-13 16-Jan-13 28-Jan-13 10 A94470 Plaster Works 31 19-Dec-12 26-Jan-13 31-Dec-12 06-Feb-13 10 A94480 Installation of Doors& Windows Sub-frame 22 03-Jan-13 29-Jan-13 06-Feb-13 03-Mar-13 28 A94940 Wall Tiles Work (Wet Area) 22 07-Jan-13 02-Feb-13 05-Feb-13 02-Mar-13 24 A94490 1st Coat Paint 22 09-Jan-13 04-Feb-13 21-Jan-13 16-Feb-13 10 Fisrt StaFisrt Stage Finishes 28 19-Jan-13 20-Feb-13 31-Jan-13 24-Mar-13 27 A94510 Suspended Ceiling Tiles (DryArea) 8 19-Jan-13 28-Jan-13 31-Jan-13 09-Feb-13 10 A94550 Installation of Wardrobes 7 23-Jan-13 31-Jan-13 05-Feb-13 12-Feb-13 10 A94970 Installation of Suspended Ceiling Grid (Wet Area) 7 04-Feb-13 11-Feb-13 16-Feb-13 23-Feb-13 10 A94540 Water Proofing for Wet Area 11 31-Jan-13 12-Feb-13 12-Feb-13 24-Feb-13 10 A94930 Screed Works 15 28-Jan-13 13-Feb-13 09-Feb-13 25-Feb-13 10 A94960 Suspended Ceiling Tiles (Wet Area) 7 07-Feb-13 14-Feb-13 19-Feb-13 26-Feb-13 10 A94530 Floor & Wall Tiles Work (Dry Area) 12 05-Feb-13 18-Feb-13 11-Mar-13 24-Mar-13 29 A94950 Floor Tiles Work (Wet Area) 8 12-Feb-13 20-Feb-13 27-Feb-13 07-Mar-13 13 Second SSecond Stage Finishes 18 17-Feb-13 09-Mar-13 04-Mar-13 31-Mar-13 19 A94560 Installation of Windows&Doors 7 17-Feb-13 24-Feb-13 04-Mar-13 11-Mar-13 13 A94620 Doors Ironmongery 7 17-Feb-13 24-Feb-13 17-Mar-13 24-Mar-13 24 A94590 Installation of Balustrades& Handrails 7 25-Feb-13 04-Mar-13 17-Mar-13 24-Mar-13 17 A94910 Installation of Toliets Accessories 12 21-Feb-13 06-Mar-13 18-Mar-13 31-Mar-13 21 A94600 Installation of Vanity Counter 10 25-Feb-13 07-Mar-13 13-Mar-13 24-Mar-13 14 A94570 Installation of Mirrors 11 25-Feb-13 09-Mar-13 12-Mar-13 24-Mar-13 13 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Windows&Doors Doors Ironmongery Final Coat Paint Installation of Sinages Installation of Furnitur Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Power Wiring for Lighting & Power Installation of Lighting Fittings Installation of Sockets H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Epoxy Paint Works Installation of Doors Doors Ironmongery Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Suspended Ceiling Grid (Dry Area) Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work (Wet Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Installation of Suspended Ceiling Grid (Wet Area) Water Proofing for Wet Area Screed Works Suspended Ceiling Tiles (Wet Area) Floor & Wall Tiles Work (Dry Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Toliets Accessories Installation of Vanity Counter Installation of Mirrors Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 80 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 81. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Final StaFinal Stage Finishes 155 10-Mar-13 08-Sep-13 25-Mar-13 02-Oct-13 21 A94520 Final Coat Paint 8 10-Mar-13 18-Mar-13 25-Mar-13 02-Apr-13 13 A94920 Installation of Sinages 7 19-Mar-13 26-Mar-13 21-Apr-13 28-Apr-13 28 A94580 Installation of Carpets 8 21-Mar-13 30-Mar-13 21-Jul-13 29-Jul-13 103 A94630 Installation of Furniture 55 06-Jul-13 08-Sep-13 30-Jul-13 02-Oct-13 21 MEP WorkMEP Works 72 10-Dec-12 05-Mar-13 23-Dec-12 02-Apr-13 24 HVACHVAC 51 18-Dec-12 17-Feb-13 02-Jan-13 05-Mar-13 14 A94660 Condensate Pipe Installation 10 18-Dec-12 29-Dec-12 12-Jan-13 22-Jan-13 20 A94640 Duct Installation & Insulation 12 18-Dec-12 31-Dec-12 02-Jan-13 15-Jan-13 12 A94650 Chilled Water Pipe Installation & Insulation 12 18-Dec-12 31-Dec-12 02-Jan-13 15-Jan-13 12 A94670 FCU Installation 8 27-Dec-12 06-Jan-13 12-Jan-13 20-Jan-13 12 A94680 Air-Outlet Installation 6 11-Feb-13 17-Feb-13 27-Feb-13 05-Mar-13 14 ElectricalElectrical 60 10-Dec-12 19-Feb-13 23-Dec-12 05-Mar-13 12 A94690 Install Conduits in Wall 14 10-Dec-12 25-Dec-12 23-Dec-12 08-Jan-13 11 A94700 Install Cable Trays & Trunking 14 18-Dec-12 03-Jan-13 05-Jan-13 20-Jan-13 14 A94710 Wiring for Lighting & Power 8 27-Dec-12 06-Jan-13 09-Jan-13 17-Jan-13 10 A94720 Wiring for Low Current System 8 27-Dec-12 06-Jan-13 12-Jan-13 20-Jan-13 12 A94740 Cable Laying for Low Current System 6 05-Jan-13 10-Jan-13 21-Jan-13 28-Jan-13 14 A94750 Cable Laying for Power 6 05-Jan-13 10-Jan-13 21-Jan-13 28-Jan-13 14 A94730 DB installation,Dressing & Termination 12 14-Jan-13 28-Jan-13 27-Jan-13 09-Feb-13 10 A94780 Installation of Sockets 7 11-Feb-13 18-Feb-13 26-Feb-13 05-Mar-13 13 A94770 Installation of Lighting Fittings 8 11-Feb-13 19-Feb-13 25-Feb-13 05-Mar-13 12 PlumbingPlumbing 69 13-Dec-12 05-Mar-13 25-Dec-12 24-Mar-13 16 A94790 Drainge Pipes in Wall 14 13-Dec-12 29-Dec-12 25-Dec-12 10-Jan-13 10 A94800 H/L Drainage Pipes Installation 10 18-Dec-12 29-Dec-12 28-Jan-13 07-Feb-13 33 A94810 H/L Hot&Cold Water Pipe Installation 10 18-Dec-12 29-Dec-12 28-Jan-13 07-Feb-13 33 A94860 Water Pipes in Wall 14 13-Dec-12 29-Dec-12 25-Dec-12 10-Jan-13 10 A94820 Drainage&Water Pipes Testing 4 30-Dec-12 03-Jan-13 09-Feb-13 12-Feb-13 33 A94830 ElectricalWater Heater Installation 6 30-Dec-12 06-Jan-13 09-Feb-13 14-Feb-13 33 A94840 Floor Drain Fixning 8 30-Jan-13 07-Feb-13 24-Feb-13 04-Mar-13 21 A94850 Installation of Sanitaryware 8 25-Feb-13 05-Mar-13 16-Mar-13 24-Mar-13 16 Fire FighFire Fighting 57 18-Dec-12 24-Feb-13 30-Dec-12 02-Apr-13 32 A94900 Fire Fighting Pipe 10 18-Dec-12 29-Dec-12 30-Dec-12 10-Jan-13 10 A94890 Hydro Static Test for Pipes 8 30-Dec-12 08-Jan-13 12-Jan-13 20-Jan-13 10 A94870 Installation of Fire Extingusher&Blanket 5 13-Feb-13 18-Feb-13 28-Mar-13 02-Apr-13 37 A94880 Sprinkler Fixing 8 13-Feb-13 21-Feb-13 25-Feb-13 05-Mar-13 10 A94980 Fire Alarm Devices 8 16-Feb-13 24-Feb-13 16-Mar-13 24-Mar-13 24 Roof LevelRoof Level 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35 Public AreaPublic Area 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35 Pump RooPump Room 46 16-Dec-12 09-Feb-13 19-Jan-13 28-Apr-13 67 FinishingFinishing Works 46 16-Dec-12 09-Feb-13 19-Jan-13 28-Apr-13 67 Wet WorWet Works 24 16-Dec-12 13-Jan-13 19-Jan-13 23-Apr-13 85 A91270 Block Works 6 16-Dec-12 22-Dec-12 19-Jan-13 26-Jan-13 28 A91230 Installation of Doors& Windows Sub-frame 1 26-Dec-12 26-Dec-12 23-Apr-13 23-Apr-13 99 A91220 Plaster Works 6 26-Dec-12 02-Jan-13 30-Jan-13 05-Feb-13 28 A91240 1st Coat Paint 6 07-Jan-13 13-Jan-13 10-Feb-13 16-Feb-13 28 Fisrt StaFisrt Stage Finishes 31 27-Dec-12 03-Feb-13 21-Apr-13 25-Apr-13 70 A91260 Installation of Doors 2 27-Dec-12 29-Dec-12 24-Apr-13 25-Apr-13 99 A91280 Doors Ironmongery 2 27-Dec-12 29-Dec-12 24-Apr-13 25-Apr-13 99 A91330 Epoxy Paint Works 2 02-Feb-13 03-Feb-13 21-Apr-13 22-Apr-13 67 Second SSecond Stage Finishes 3 04-Feb-13 06-Feb-13 23-Apr-13 25-Apr-13 67 A91250 Final Coat Paint 3 04-Feb-13 06-Feb-13 23-Apr-13 25-Apr-13 67 Final StaFinal Stage Finishes 2 07-Feb-13 09-Feb-13 27-Apr-13 28-Apr-13 67 A91320 Installation of Sinages 2 07-Feb-13 09-Feb-13 27-Apr-13 28-Apr-13 67 MEP WorkMEP Works 33 23-Dec-12 31-Jan-13 27-Jan-13 24-Apr-13 71 HVACHVAC 33 23-Dec-12 31-Jan-13 12-Feb-13 05-Mar-13 28 A91350 Duct Installation & Insulation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42 A91360 Chilled Water Pipe Installation & Insulation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42 A91370 Condensate Pipe Installation 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42 A91380 FCU Installation 5 31-Dec-12 06-Jan-13 20-Feb-13 25-Feb-13 42 A91390 Air-Outlet Installation 7 07-Jan-13 14-Jan-13 26-Feb-13 05-Mar-13 42 A115120 Installation of Primary Chilled Water Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28 A115130 Installation of SecondaryChilled Water Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28 A115140 Installation of Heat Exchanger 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28 A115150 Installation of Heat Exchanger Pump 15 14-Jan-13 31-Jan-13 17-Feb-13 05-Mar-13 28 ElectricalElectrical 23 23-Dec-12 19-Jan-13 27-Jan-13 05-Mar-13 38 A91290 Install Conduits in Wall 3 23-Dec-12 25-Dec-12 27-Jan-13 29-Jan-13 28 A91300 Wiring for Lighting & Power 3 03-Jan-13 06-Jan-13 06-Feb-13 09-Feb-13 28 A91310 Installation of Lighting Fittings 5 14-Jan-13 19-Jan-13 28-Feb-13 05-Mar-13 38 PlumbingPlumbing 24 23-Dec-12 20-Jan-13 19-Feb-13 05-Mar-13 37 A91440 H/L Drainage Pipes Installation 4 23-Dec-12 26-Dec-12 23-Feb-13 26-Feb-13 51 A91450 H/L Hot&Cold Water Pipe Installation 7 23-Dec-12 30-Dec-12 19-Feb-13 26-Feb-13 48 A91460 Drainage&Water Pipes Testing 6 31-Dec-12 07-Jan-13 27-Feb-13 05-Mar-13 48 A91470 Floor Drain Fixning 6 14-Jan-13 20-Jan-13 27-Feb-13 05-Mar-13 37 Fire FighFire Fighting 25 23-Dec-12 21-Jan-13 12-Feb-13 24-Apr-13 79 A91430 Fire Fighting Pipe 7 23-Dec-12 30-Dec-12 12-Feb-13 19-Feb-13 42 A91420 Hydro Static Test for Pipes 7 31-Dec-12 08-Jan-13 20-Feb-13 27-Feb-13 42 A91410 Sprinkler Fixing 5 09-Jan-13 14-Jan-13 28-Feb-13 05-Mar-13 42 A91400 Installation of Fire Extingusher&Blanket 3 15-Jan-13 17-Jan-13 22-Apr-13 24-Apr-13 82 A91340 Fire Alarm Devices 6 15-Jan-13 21-Jan-13 14-Apr-13 20-Apr-13 75 Electrical /Electrical / GSM / Telephone Room 65 16-Dec-12 03-Mar-13 29-Dec-12 28-Apr-13 48 FinishingFinishing Works 65 16-Dec-12 03-Mar-13 29-Dec-12 28-Apr-13 48 Wet WorWet Works 31 16-Dec-12 21-Jan-13 29-Dec-12 23-Apr-13 78 A91120 Block Works 10 16-Dec-12 26-Dec-12 29-Dec-12 09-Jan-13 11 A91080 Installation of Doors& Windows Sub-frame 2 30-Dec-12 31-Dec-12 22-Apr-13 23-Apr-13 95 A91070 Plaster Works 9 30-Dec-12 09-Jan-13 13-Jan-13 22-Jan-13 11 A91090 1st Coat Paint 8 13-Jan-13 21-Jan-13 27-Jan-13 04-Feb-13 11 Fisrt StaFisrt Stage Finishes 44 02-Jan-13 23-Feb-13 18-Apr-13 25-Apr-13 53 A91110 Installation of Doors 2 02-Jan-13 03-Jan-13 24-Apr-13 25-Apr-13 95 A91130 Doors Ironmongery 2 02-Jan-13 03-Jan-13 24-Apr-13 25-Apr-13 95 A91180 Epoxy Paint Works 2 21-Feb-13 23-Feb-13 18-Apr-13 20-Apr-13 48 Second SSecond Stage Finishes 5 24-Feb-13 28-Feb-13 21-Apr-13 25-Apr-13 48 A91100 Final Coat Paint 5 24-Feb-13 28-Feb-13 21-Apr-13 25-Apr-13 48 Final StaFinal Stage Finishes 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48 A91170 Installation of Sinages 2 02-Mar-13 03-Mar-13 27-Apr-13 28-Apr-13 48 MEP WorkMEP Works 46 27-Dec-12 20-Feb-13 10-Jan-13 17-Apr-13 48 HVACHVAC 2 22-Jan-13 23-Jan-13 04-Mar-13 05-Mar-13 34 A91210 Air-Outlet Installation 2 22-Jan-13 23-Jan-13 04-Mar-13 05-Mar-13 34 ElectricalElectrical 46 27-Dec-12 20-Feb-13 10-Jan-13 05-Mar-13 11 A91140 Install Conduits in Wall 2 27-Dec-12 29-Dec-12 10-Jan-13 12-Jan-13 11 A91150 Wiring for Lighting & Power 2 10-Jan-13 12-Jan-13 23-Jan-13 26-Jan-13 11 A91200 Installation of SMDBs 7 22-Jan-13 30-Jan-13 24-Feb-13 03-Mar-13 27 A91160 Installation of Lighting Fittings 2 31-Jan-13 02-Feb-13 04-Mar-13 05-Mar-13 27 A114910 Installation of Telephone System 21 22-Jan-13 16-Feb-13 10-Feb-13 05-Mar-13 15 A114920 Installation of GSM System 25 22-Jan-13 20-Feb-13 05-Feb-13 05-Mar-13 11 Fire FighFire Fighting 2 03-Feb-13 04-Feb-13 16-Apr-13 17-Apr-13 62 A91190 Fire Alarm Devices 2 03-Feb-13 04-Feb-13 16-Apr-13 17-Apr-13 62 ELV RoomELV Room 49 16-Dec-12 12-Feb-13 15-Jan-13 28-Apr-13 64 FinishingFinishing Works 49 16-Dec-12 12-Feb-13 15-Jan-13 28-Apr-13 64 Wet WorWet Works 22 16-Dec-12 10-Jan-13 15-Jan-13 23-Apr-13 87 A91540 Block Works 4 16-Dec-12 19-Dec-12 15-Jan-13 19-Jan-13 25 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Final Coat Paint Installation of Sinages Installation of Carpets Installation of Furnitur Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Wiring for Lighting & Power Wiring for Low Current System Cable Laying for Low Current System Cable Laying for Power DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Installation of Primary Chilled Water Pump Installation of SecondaryChilled Water Pump Installation of Heat Exchanger Installation of Heat Exchanger Pump Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Installation of GSM System Fire Alarm Devices Block Works Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 81 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 82. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A91500 Installation of Doors& Windows Sub-frame 2 23-Dec-12 24-Dec-12 22-Apr-13 23-Apr-13 101 A91490 Plaster Works 7 23-Dec-12 30-Dec-12 22-Jan-13 30-Jan-13 25 A91510 1st Coat Paint 7 03-Jan-13 10-Jan-13 03-Feb-13 10-Feb-13 25 Fisrt StaFisrt Stage Finishes 36 25-Dec-12 06-Feb-13 21-Apr-13 25-Apr-13 67 A91530 Installation of Doors 2 25-Dec-12 26-Dec-12 24-Apr-13 25-Apr-13 101 A91550 Doors Ironmongery 2 25-Dec-12 26-Dec-12 24-Apr-13 25-Apr-13 101 A91600 Epoxy Paint Works 2 05-Feb-13 06-Feb-13 21-Apr-13 22-Apr-13 64 Second SSecond Stage Finishes 3 07-Feb-13 10-Feb-13 23-Apr-13 25-Apr-13 64 A91520 Final Coat Paint 3 07-Feb-13 10-Feb-13 23-Apr-13 25-Apr-13 64 Final StaFinal Stage Finishes 2 11-Feb-13 12-Feb-13 27-Apr-13 28-Apr-13 64 A91590 Installation of Sinages 2 11-Feb-13 12-Feb-13 27-Apr-13 28-Apr-13 64 MEP WorkMEP Works 38 20-Dec-12 04-Feb-13 20-Jan-13 20-Apr-13 64 HVACHVAC 6 12-Jan-13 17-Jan-13 27-Feb-13 05-Mar-13 39 A91630 Air-Outlet Installation 6 12-Jan-13 17-Jan-13 27-Feb-13 05-Mar-13 39 ElectricalElectrical 38 20-Dec-12 04-Feb-13 20-Jan-13 05-Mar-13 25 A91560 Install Conduits in Wall 2 20-Dec-12 22-Dec-12 20-Jan-13 21-Jan-13 25 A91570 Wiring for Lighting & Power 2 31-Dec-12 02-Jan-13 31-Jan-13 02-Feb-13 25 A91580 Installation of Lighting Fittings 2 12-Jan-13 13-Jan-13 04-Mar-13 05-Mar-13 43 A114930 Installation of Access ControlSystem 20 12-Jan-13 04-Feb-13 11-Feb-13 05-Mar-13 25 A114940 Installation of MATC,TV System 20 12-Jan-13 04-Feb-13 11-Feb-13 05-Mar-13 25 Fire FighFire Fighting 8 14-Jan-13 22-Jan-13 11-Apr-13 20-Apr-13 74 A91610 Fire Alarm Devices 8 14-Jan-13 22-Jan-13 11-Apr-13 20-Apr-13 74 Chillers RoChillers Room 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35 FinishingFinishing Works 104 13-Nov-12 18-Mar-13 27-Nov-12 28-Apr-13 35 Wet WorWet Works 6 13-Nov-12 20-Nov-12 27-Nov-12 24-Mar-13 103 A91690 Block Works 2 13-Nov-12 14-Nov-12 23-Mar-13 24-Mar-13 107 A91720 Water Proofing Works 6 13-Nov-12 20-Nov-12 27-Nov-12 04-Dec-12 11 Fisrt StaFisrt Stage Finishes 19 21-Feb-13 14-Mar-13 03-Apr-13 24-Apr-13 35 A91650 Installation of Doors& Windows Sub-frame 1 21-Feb-13 21-Feb-13 21-Apr-13 21-Apr-13 50 A91640 Plaster Works 2 21-Feb-13 23-Feb-13 03-Apr-13 04-Apr-13 35 A91660 1st Coat Paint 3 24-Feb-13 26-Feb-13 06-Apr-13 08-Apr-13 35 A91750 Floor Tiles Works 11 27-Feb-13 11-Mar-13 09-Apr-13 21-Apr-13 35 A91680 Installation of Doors 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35 A91700 Doors Ironmongery 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35 Second SSecond Stage Finishes 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35 A91670 Final Coat Paint 3 12-Mar-13 14-Mar-13 22-Apr-13 24-Apr-13 35 Final StaFinal Stage Finishes 3 16-Mar-13 18-Mar-13 25-Apr-13 28-Apr-13 35 A91710 Installation of Sinages 3 16-Mar-13 18-Mar-13 25-Apr-13 28-Apr-13 35 MEP WorkMEP Works 76 21-Nov-12 20-Feb-13 05-Dec-12 05-Mar-13 11 HVACHVAC 76 21-Nov-12 20-Feb-13 05-Dec-12 05-Mar-13 11 A91730 Chilled Water Pipe Installation & Insulation 51 21-Nov-12 21-Jan-13 05-Dec-12 04-Feb-13 11 A91740 Installation of Chillers 51 21-Nov-12 21-Jan-13 05-Dec-12 04-Feb-13 11 A91820 Flushing for Chiled Water Pipes 25 22-Jan-13 20-Feb-13 05-Feb-13 05-Mar-13 11 GRP TankGRP Tank 35 16-Dec-12 27-Jan-13 23-Jan-13 05-Mar-13 32 FinishingFinishing Works 20 16-Dec-12 08-Jan-13 23-Jan-13 16-Feb-13 32 A91770 Water Proofing for Roof Area 10 16-Dec-12 26-Dec-12 23-Jan-13 04-Feb-13 32 A91780 Floor Tiles Work 10 27-Dec-12 08-Jan-13 05-Feb-13 16-Feb-13 32 MEP WorkMEP Works 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32 PlumbingPlumbing 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32 A91760 Installation of GRP Tank 15 09-Jan-13 27-Jan-13 17-Feb-13 05-Mar-13 32 Boiler RooBoiler Room 57 16-Dec-12 21-Feb-13 21-Jan-13 28-Apr-13 56 FinishingFinishing Works 57 16-Dec-12 21-Feb-13 21-Jan-13 28-Apr-13 56 A91790 Water Proofing for Boiler Area 9 16-Dec-12 25-Dec-12 21-Jan-13 31-Jan-13 30 A91800 Installation of Steel Support 10 30-Jan-13 10-Feb-13 06-Apr-13 16-Apr-13 56 A91810 Installation of Louver 10 11-Feb-13 21-Feb-13 17-Apr-13 28-Apr-13 56 MEP WorkMEP Works 45 26-Dec-12 18-Feb-13 02-Feb-13 24-Apr-13 56 PlumbingPlumbing 28 26-Dec-12 29-Jan-13 02-Feb-13 05-Mar-13 30 A105100 Installation of Hot Water Boiler 7 26-Dec-12 03-Jan-13 02-Feb-13 09-Feb-13 30 A105240 Floor Drain Fixning 7 26-Dec-12 03-Jan-13 26-Feb-13 05-Mar-13 51 A105110 Installation of Hot Water Tank 7 05-Jan-13 12-Jan-13 10-Feb-13 17-Feb-13 30 A105120 Installation of Hot Water Pump 7 13-Jan-13 20-Jan-13 18-Feb-13 25-Feb-13 30 A105130 Installation of Pipes 7 21-Jan-13 29-Jan-13 26-Feb-13 05-Mar-13 30 Fire FighFire Fighting 7 11-Feb-13 18-Feb-13 17-Apr-13 24-Apr-13 56 A105170 Fire Alarm Devices 7 11-Feb-13 18-Feb-13 17-Apr-13 24-Apr-13 56 Upper Roof LUpper Roof Level 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104 Public AreaPublic Area 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104 Roof AreaRoof Area 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104 FinishingFinishing Works 30 20-Nov-12 25-Dec-12 07-Mar-13 28-Apr-13 104 A91050 Water Proofing for Roof Area 15 20-Nov-12 08-Dec-12 07-Mar-13 24-Mar-13 89 A91060 Floor Tiles Work 15 09-Dec-12 25-Dec-12 11-Apr-13 28-Apr-13 104 ResidentialResidential (Block C) 389 02-Jun-12 10-Sep-13 29-Aug-12 02-Oct-13 19 2nd Basemen2nd Basement Floor 226 02-Jun-12 02-Mar-13 10-Oct-12 16-Apr-13 39 Public AreaPublic Area 226 02-Jun-12 02-Mar-13 10-Oct-12 16-Apr-13 39 Parking ArParking Area 213 18-Jun-12 02-Mar-13 28-Oct-12 16-Apr-13 39 FinishingFinishing Works 213 18-Jun-12 02-Mar-13 28-Oct-12 16-Apr-13 39 Wet WorWet Works 159 18-Jun-12 26-Dec-12 28-Oct-12 12-Feb-13 39 A67900 Plaster Works 5 18-Jun-12 23-Jun-12 28-Oct-12 01-Nov-12 109 A67910 1st Coat Paint 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39 Traffic DTraffic Deck Coating 49 27-Dec-12 24-Feb-13 13-Feb-13 16-Apr-13 44 A116170 Installation of Kerbs 8 27-Dec-12 06-Jan-13 13-Feb-13 21-Feb-13 39 A116180 Installation of Interlocking Tiles 8 07-Jan-13 15-Jan-13 23-Feb-13 03-Mar-13 39 A67840 Surface Preparation (including Grinding & Repairing) 8 16-Jan-13 26-Jan-13 04-Mar-13 12-Mar-13 39 A67850 Application of 1st Coat 7 22-Jan-13 30-Jan-13 10-Mar-13 17-Mar-13 39 A67890 Application of Final Coat 7 31-Jan-13 07-Feb-13 18-Mar-13 25-Mar-13 39 A67870 Road Marking & Arrows 7 09-Feb-13 16-Feb-13 26-Mar-13 02-Apr-13 39 A116190 Installation of Speed Hump 7 17-Feb-13 24-Feb-13 09-Apr-13 16-Apr-13 44 Final StaFinal Stage Finishes 12 17-Feb-13 02-Mar-13 03-Apr-13 16-Apr-13 39 A67920 Final Coat Paint 5 17-Feb-13 21-Feb-13 03-Apr-13 08-Apr-13 39 A67940 Installation of Sinages 7 23-Feb-13 02-Mar-13 09-Apr-13 16-Apr-13 39 MEP WorkMEP Works 147 18-Jun-12 12-Dec-12 13-Dec-12 29-Jan-13 39 HVACHVAC 12 08-Jul-12 21-Jul-12 15-Jan-13 29-Jan-13 157 A67960 Chilled Water Pipe Installation & Insulation 7 08-Jul-12 15-Jul-12 15-Jan-13 22-Jan-13 157 A67970 Condensate Pipe Installation 7 08-Jul-12 15-Jul-12 17-Jan-13 26-Jan-13 159 A68040 Installation of Induction Fans 3 16-Jul-12 18-Jul-12 27-Jan-13 29-Jan-13 159 A67520 Diesil Engine Exhust 12 08-Jul-12 21-Jul-12 15-Jan-13 29-Jan-13 157 ElectricalElectrical 147 18-Jun-12 12-Dec-12 13-Dec-12 29-Jan-13 39 A116200 Instalaltion of Cable Trays 10 18-Jun-12 28-Jun-12 13-Dec-12 24-Dec-12 147 A116210 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 18-Dec-12 05-Jan-13 39 A116220 Cable Pulling 10 19-Nov-12 29-Nov-12 06-Jan-13 16-Jan-13 39 A67930 Installation of Lighting Fittings 10 01-Dec-12 12-Dec-12 17-Jan-13 29-Jan-13 39 PlumbingPlumbing 12 18-Jun-12 01-Jul-12 15-Jan-13 29-Jan-13 174 A68030 Floor Drain Fixning 4 18-Jun-12 21-Jun-12 26-Jan-13 29-Jan-13 182 A68010 H/L Hot&Cold Water Pipe Installation 7 18-Jun-12 25-Jun-12 15-Jan-13 22-Jan-13 174 A68020 Water Pipes Testing 5 26-Jun-12 01-Jul-12 23-Jan-13 29-Jan-13 174 Fire FighFire Fighting 39 20-Jun-12 04-Aug-12 13-Dec-12 29-Jan-13 145 A68000 Fire Fighting Pipe 8 20-Jun-12 28-Jun-12 13-Dec-12 22-Dec-12 145 A67990 Hydro Static Test for Pipes 5 30-Jun-12 04-Jul-12 08-Jan-13 13-Jan-13 158 A67980 Sprinkler Fixing 7 05-Jul-12 12-Jul-12 14-Jan-13 21-Jan-13 158 A67950 Fire Alarm Devices 6 29-Jul-12 04-Aug-12 22-Jan-13 29-Jan-13 145 Lift LobbyLift Lobby 119 02-Jun-12 21-Oct-12 10-Oct-12 16-Apr-13 146 FinishingFinishing Works 119 02-Jun-12 21-Oct-12 10-Oct-12 16-Apr-13 146 Wet WorWet Works 53 02-Jun-12 02-Aug-12 10-Oct-12 30-Dec-12 122 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Installation of Access Control System Installation of MATC,TV System Fire Alarm Devices Block Works Water Proofing Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Floor Tiles Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Installation of Chillers Flushing for Chiled Water Pipes Water Proofing for Roof Area Floor Tiles Work Installation of GRP Tank Water Proofing for Boiler Area Installation of Steel Support Installation of Louver Installation of Hot Water Boiler Floor Drain Fixning Installation of Hot Water Tank Installation of Hot Water Pump Installation of Pipes Fire Alarm Devices Water Proofing for Roof Area Floor Tiles Work Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Installation of Induction Fans Diesil Engine Exhust Instalaltion of Cable Trays Instalaltion of Bus Bars Cable Pulling Installation of Lighting Fittings Floor Drain Fixning H/L Hot&Cold Water Pipe Installation Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 82 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 83. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A67580 Block Works 5 02-Jun-12 06-Jun-12 10-Oct-12 15-Oct-12 109 A67530 Plaster Works 7 24-Jun-12 01-Jul-12 03-Nov-12 10-Nov-12 109 A67550 Installation of Suspended Ceiling Grid 7 16-Jul-12 23-Jul-12 15-Dec-12 22-Dec-12 124 A67540 1st Coat Paint 7 26-Jul-12 02-Aug-12 23-Dec-12 30-Dec-12 122 Fisrt StaFisrt Stage Finishes 23 04-Aug-12 01-Sep-12 31-Dec-12 06-Feb-13 130 A67560 Suspended Ceiling Tiles 7 04-Aug-12 11-Aug-12 31-Dec-12 08-Jan-13 122 A67800 MDF for Lift Lobby Wall 7 14-Aug-12 23-Aug-12 21-Jan-13 29-Jan-13 130 A67780 Screed Works 7 25-Aug-12 01-Sep-12 30-Jan-13 06-Feb-13 130 Second SSecond Stage Finishes 14 02-Sep-12 17-Sep-12 07-Feb-13 23-Feb-13 130 A67790 Wall Tiles Work 7 02-Sep-12 09-Sep-12 07-Feb-13 14-Feb-13 130 A67820 Floor Tiles Work 7 10-Sep-12 17-Sep-12 16-Feb-13 23-Feb-13 130 Final StaFinal Stage Finishes 29 18-Sep-12 21-Oct-12 24-Feb-13 16-Apr-13 146 A67570 Installation of Doors 7 18-Sep-12 25-Sep-12 24-Feb-13 03-Mar-13 130 A67590 Doors Ironmongery 7 19-Sep-12 26-Sep-12 09-Apr-13 16-Apr-13 167 A67830 Final Coat Paint 7 03-Oct-12 10-Oct-12 26-Mar-13 02-Apr-13 143 A67770 Installation of Sinages 7 14-Oct-12 21-Oct-12 09-Apr-13 16-Apr-13 146 MEP WorkMEP Works 98 07-Jun-12 02-Oct-12 23-Oct-12 25-Mar-13 143 HVACHVAC 49 24-Jun-12 21-Aug-12 29-Nov-12 05-Mar-13 162 A67600 Duct Installation & Insulation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131 A67610 Chilled Water Pipe Installation & Insulation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131 A67620 Condensate Pipe Installation 5 24-Jun-12 28-Jun-12 29-Nov-12 05-Dec-12 131 A67630 FCU Installation 7 30-Jun-12 07-Jul-12 06-Dec-12 13-Dec-12 131 A67640 Air-Outlet Installation 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162 ElectricalElectrical 98 07-Jun-12 02-Oct-12 23-Oct-12 16-Jan-13 86 A67650 Install Conduits in Wall 7 07-Jun-12 14-Jun-12 23-Oct-12 01-Nov-12 115 A67660 Install Cable Trays & Trunking 7 07-Jun-12 14-Jun-12 31-Oct-12 07-Nov-12 120 A67700 Cable Laying for Low Current System 7 16-Jun-12 24-Jun-12 15-Dec-12 22-Dec-12 149 A67710 Cable Laying for Power 7 16-Jun-12 24-Jun-12 15-Dec-12 22-Dec-12 149 A67670 Wiring for Lighting & Power 7 02-Jul-12 09-Jul-12 06-Dec-12 13-Dec-12 129 A67680 Wiring for Low Current System 7 02-Jul-12 09-Jul-12 06-Dec-12 13-Dec-12 129 A67690 DB installation,Dressing & Termination 7 24-Jul-12 31-Jul-12 31-Dec-12 08-Jan-13 131 A67730 Installation of Lighting Fittings 7 25-Sep-12 02-Oct-12 09-Jan-13 16-Jan-13 86 Fire FighFire Fighting 59 11-Jun-12 21-Aug-12 27-Nov-12 25-Mar-13 179 A67760 Fire Fighting Pipe 7 11-Jun-12 19-Jun-12 27-Nov-12 05-Dec-12 139 A67750 Hydro Static Test for Pipes 7 20-Jun-12 27-Jun-12 06-Dec-12 13-Dec-12 139 A67740 Sprinkler Fixing 7 12-Aug-12 21-Aug-12 26-Feb-13 05-Mar-13 162 A67810 Fire Alarm Devices 7 12-Aug-12 21-Aug-12 18-Mar-13 25-Mar-13 179 MechanicaMechanical Rooms 109 07-Jun-12 15-Oct-12 16-Oct-12 16-Apr-13 151 FinishingFinishing Works 109 07-Jun-12 15-Oct-12 16-Oct-12 16-Apr-13 151 Wet WorWet Works 35 07-Jun-12 18-Jul-12 16-Oct-12 18-Feb-13 176 A67170 Block Works 2 07-Jun-12 09-Jun-12 16-Oct-12 17-Oct-12 109 A67130 Installation of Doors& Windows Sub-frame 2 02-Jul-12 03-Jul-12 17-Feb-13 18-Feb-13 189 A67120 Plaster Works 5 02-Jul-12 07-Jul-12 11-Nov-12 17-Nov-12 109 A67140 1st Coat Paint 6 12-Jul-12 18-Jul-12 22-Nov-12 28-Nov-12 109 Fisrt StaFisrt Stage Finishes 34 06-Aug-12 16-Sep-12 19-Feb-13 06-Apr-13 167 A67160 Installation of Doors 2 06-Aug-12 07-Aug-12 19-Feb-13 20-Feb-13 161 A67230 Epoxy Paint Works 2 11-Aug-12 12-Aug-12 27-Feb-13 28-Feb-13 164 A67180 Doors Ironmongery 2 15-Sep-12 16-Sep-12 04-Apr-13 06-Apr-13 167 Second SSecond Stage Finishes 2 13-Aug-12 14-Aug-12 20-Mar-13 21-Mar-13 180 A67150 Final Coat Paint 2 13-Aug-12 14-Aug-12 20-Mar-13 21-Mar-13 180 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151 A67220 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151 MEP WorkMEP Works 47 16-Jun-12 09-Aug-12 06-Nov-12 26-Feb-13 164 HVACHVAC 15 19-Jul-12 05-Aug-12 29-Nov-12 17-Dec-12 109 A67240 Shaft Works 15 19-Jul-12 05-Aug-12 29-Nov-12 17-Dec-12 109 ElectricalElectrical 47 16-Jun-12 09-Aug-12 06-Nov-12 22-Dec-12 109 A67190 Install Conduits in Wall 4 16-Jun-12 20-Jun-12 06-Nov-12 10-Nov-12 118 A67200 Wiring for Lighting & Power 4 08-Jul-12 11-Jul-12 18-Nov-12 21-Nov-12 109 A67210 Installation of Lighting Fittings 4 06-Aug-12 09-Aug-12 18-Dec-12 22-Dec-12 109 PlumbingPlumbing 3 19-Jul-12 22-Jul-12 24-Feb-13 26-Feb-13 180 A67250 Floor Drain Fixning 3 19-Jul-12 22-Jul-12 24-Feb-13 26-Feb-13 180 Pump RooPump Room 107 10-Jun-12 15-Oct-12 18-Oct-12 16-Apr-13 151 FinishingFinishing Works 107 10-Jun-12 15-Oct-12 18-Oct-12 16-Apr-13 151 Wet WorWet Works 39 10-Jun-12 25-Jul-12 18-Oct-12 20-Feb-13 172 A67310 Block Works 6 10-Jun-12 16-Jun-12 18-Oct-12 24-Oct-12 109 A67270 Installation of Doors& Windows Sub-frame 2 08-Jul-12 09-Jul-12 19-Feb-13 20-Feb-13 186 A67260 Plaster Works 6 08-Jul-12 14-Jul-12 24-Nov-12 29-Nov-12 114 A67280 1st Coat Paint 6 19-Jul-12 25-Jul-12 05-Dec-12 11-Dec-12 113 Fisrt StaFisrt Stage Finishes 34 08-Aug-12 18-Sep-12 21-Feb-13 08-Apr-13 167 A67300 Installation of Doors 2 08-Aug-12 09-Aug-12 21-Feb-13 23-Feb-13 161 A67370 Epoxy Paint Works 2 23-Aug-12 25-Aug-12 02-Mar-13 03-Mar-13 157 A67320 Doors Ironmongery 2 17-Sep-12 18-Sep-12 07-Apr-13 08-Apr-13 167 Second SSecond Stage Finishes 3 26-Aug-12 28-Aug-12 23-Mar-13 25-Mar-13 173 A67290 Final Coat Paint 3 26-Aug-12 28-Aug-12 23-Mar-13 25-Mar-13 173 Final StaFinal Stage Finishes 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151 A67360 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151 MEP WorkMEP Works 55 18-Jun-12 22-Aug-12 20-Nov-12 25-Mar-13 178 HVACHVAC 19 30-Jun-12 21-Jul-12 07-Jan-13 25-Feb-13 180 A67390 Duct Installation & Insulation 7 30-Jun-12 07-Jul-12 17-Jan-13 26-Jan-13 166 A67400 Chilled Water Pipe Installation & Insulation 7 30-Jun-12 07-Jul-12 07-Jan-13 14-Jan-13 157 A67410 Condensate Pipe Installation 7 30-Jun-12 07-Jul-12 09-Jan-13 16-Jan-13 159 A67420 FCU Installation 5 08-Jul-12 12-Jul-12 12-Feb-13 17-Feb-13 180 A67430 Air-Outlet Installation 7 14-Jul-12 21-Jul-12 18-Feb-13 25-Feb-13 180 ElectricalElectrical 35 21-Jun-12 31-Jul-12 20-Nov-12 17-Dec-12 113 A67330 Install Conduits in Wall 3 21-Jun-12 24-Jun-12 20-Nov-12 22-Nov-12 125 A67340 Wiring for Lighting & Power 3 15-Jul-12 17-Jul-12 01-Dec-12 04-Dec-12 114 A67350 Installation of Lighting Fittings 5 26-Jul-12 31-Jul-12 12-Dec-12 17-Dec-12 113 PlumbingPlumbing 39 18-Jun-12 01-Aug-12 17-Feb-13 28-Feb-13 173 A67480 H/L Hot&Cold Water Pipe Installation 7 18-Jun-12 25-Jun-12 17-Feb-13 24-Feb-13 201 A67490 Water Pipes Testing 4 26-Jun-12 30-Jun-12 25-Feb-13 28-Feb-13 201 A67010 Installation of Sump Pump 6 26-Jul-12 01-Aug-12 23-Feb-13 28-Feb-13 173 A67500 Installation of Transfer Pump 6 26-Jul-12 01-Aug-12 23-Feb-13 28-Feb-13 173 Fire FighFire Fighting 45 30-Jun-12 22-Aug-12 23-Dec-12 25-Mar-13 178 A67470 Fire Fighting Pipe 7 30-Jun-12 07-Jul-12 23-Dec-12 30-Dec-12 145 A67460 Hydro Static Test for Pipes 7 08-Jul-12 15-Jul-12 31-Dec-12 08-Jan-13 145 A67450 Sprinkler Fixing 5 16-Jul-12 21-Jul-12 09-Jan-13 14-Jan-13 145 A67380 Fire Alarm Devices 6 22-Jul-12 28-Jul-12 15-Jan-13 21-Jan-13 145 A67440 Installation of Fire Extingusher&Blanket 3 29-Jul-12 31-Jul-12 23-Mar-13 25-Mar-13 195 A67510 Installation of Fire Fighting Pump 10 09-Aug-12 22-Aug-12 18-Feb-13 28-Feb-13 157 Water TankWater Tank 1 (Block C1) 29 28-Jul-12 01-Sep-12 10-Nov-12 24-Feb-13 145 FinishingFinishing Works 21 28-Jul-12 22-Aug-12 10-Nov-12 05-Dec-12 86 A66990 GRP Lining on the Ceiling 7 28-Jul-12 04-Aug-12 10-Nov-12 18-Nov-12 86 A66980 GRP Lining on the Wall 7 05-Aug-12 12-Aug-12 19-Nov-12 26-Nov-12 86 A67000 Reinforced Plastic on the Floor 7 13-Aug-12 22-Aug-12 27-Nov-12 05-Dec-12 86 MEP WorkMEP Works 8 23-Aug-12 01-Sep-12 23-Dec-12 24-Feb-13 145 ElectricalElectrical 7 23-Aug-12 30-Aug-12 23-Dec-12 30-Dec-12 100 A67040 Installation of Lighting Fittings 7 23-Aug-12 30-Aug-12 23-Dec-12 30-Dec-12 100 PlumbingPlumbing 8 23-Aug-12 01-Sep-12 16-Feb-13 24-Feb-13 145 A67020 Installation of Water Supply Pipes&Fittings 5 23-Aug-12 28-Aug-12 16-Feb-13 20-Feb-13 145 A67030 Install of Water Meter 3 29-Aug-12 01-Sep-12 21-Feb-13 24-Feb-13 145 Water TankWater Tank 2 (Block C2) 29 23-Aug-12 25-Sep-12 06-Dec-12 05-Mar-13 132 FinishingFinishing Works 21 23-Aug-12 16-Sep-12 06-Dec-12 30-Dec-12 86 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles MDF for Lift Lobby Wall Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Shaft Works Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Floor Drain Fixning Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Epoxy Paint Works Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes Testing Installation of Sump Pump Installation of Transfer Pump Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Installation of Fire Fighting Pump GRP Lining on the Ceiling GRP Lining on the Wall Reinforced Plastic on the Floor Installation of Lighting Fittings Installation of Water Supply Pipes&Fittings Install of Water Meter Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 83 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 84. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A67060 GRP Lining on the Ceiling 7 23-Aug-12 30-Aug-12 06-Dec-12 13-Dec-12 86 A67050 GRP Lining on the Wall 7 01-Sep-12 08-Sep-12 15-Dec-12 22-Dec-12 86 A67070 Reinforced Plastic on the Floor 7 09-Sep-12 16-Sep-12 23-Dec-12 30-Dec-12 86 MEP WorkMEP Works 8 17-Sep-12 25-Sep-12 31-Dec-12 05-Mar-13 132 ElectricalElectrical 7 17-Sep-12 24-Sep-12 31-Dec-12 08-Jan-13 86 A67110 Installation of Lighting Fittings 7 17-Sep-12 24-Sep-12 31-Dec-12 08-Jan-13 86 PlumbingPlumbing 8 17-Sep-12 25-Sep-12 25-Feb-13 05-Mar-13 132 A67090 Installation of Water Supply Pipes&Fittings 5 17-Sep-12 22-Sep-12 25-Feb-13 02-Mar-13 132 A67100 Install of Water Meter 3 23-Sep-12 25-Sep-12 03-Mar-13 05-Mar-13 132 StaircaseStaircase 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192 Stairs 1Stairs 1 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192 A111210 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166 A111250 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166 A111220 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111230 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111240 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166 A111260 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192 Stairs 2Stairs 2 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192 A111270 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166 A111310 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166 A111280 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111290 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111300 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166 A111320 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192 Stairs 3Stairs 3 43 08-Jul-12 28-Aug-12 27-Jan-13 16-Apr-13 192 A111330 Floor Screed 3 08-Jul-12 10-Jul-12 27-Jan-13 29-Jan-13 166 A111370 Install Handrails 4 11-Jul-12 15-Jul-12 30-Jan-13 03-Feb-13 166 A111340 Ceiling 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111350 Wall 1st Coat Paint 12 16-Jul-12 29-Jul-12 04-Feb-13 17-Feb-13 166 A111360 Install Granite/Terrazo 12 30-Jul-12 12-Aug-12 18-Feb-13 03-Mar-13 166 A111380 Final Coat Paint 12 13-Aug-12 28-Aug-12 03-Apr-13 16-Apr-13 192 1st Basemen1st Basement Floor 206 01-Jul-12 06-Mar-13 10-Nov-12 16-Apr-13 35 Public AreaPublic Area 206 01-Jul-12 06-Mar-13 10-Nov-12 16-Apr-13 35 Parking ArParking Area 196 12-Jul-12 06-Mar-13 22-Nov-12 16-Apr-13 35 FinishingFinishing Works 196 12-Jul-12 06-Mar-13 22-Nov-12 16-Apr-13 35 Wet WorWet Works 138 12-Jul-12 26-Dec-12 22-Nov-12 12-Feb-13 39 A68990 Plaster Works 5 12-Jul-12 17-Jul-12 22-Nov-12 27-Nov-12 109 A69000 1st Coat Paint 12 13-Dec-12 26-Dec-12 30-Jan-13 12-Feb-13 39 Traffic DTraffic Deck Coating 53 27-Dec-12 28-Feb-13 13-Feb-13 16-Apr-13 40 A116260 Installation of Kerbs 8 27-Dec-12 06-Jan-13 13-Feb-13 21-Feb-13 39 A116270 Installation of Interlocking Tiles 8 07-Jan-13 15-Jan-13 23-Feb-13 03-Mar-13 39 A68930 Surface Preparation (including Grinding & Repairing) 8 21-Jan-13 30-Jan-13 04-Mar-13 12-Mar-13 35 A68940 Application of 1st Coat 7 28-Jan-13 04-Feb-13 10-Mar-13 17-Mar-13 35 A68980 Application of Final Coat 7 05-Feb-13 12-Feb-13 18-Mar-13 25-Mar-13 35 A68960 Road Marking & Arrows 7 13-Feb-13 20-Feb-13 26-Mar-13 02-Apr-13 35 A116280 Installation of Speed Hump 7 21-Feb-13 28-Feb-13 09-Apr-13 16-Apr-13 40 Final StaFinal Stage Finishes 12 21-Feb-13 06-Mar-13 03-Apr-13 16-Apr-13 35 A69010 Final Coat Paint 5 21-Feb-13 26-Feb-13 03-Apr-13 08-Apr-13 35 A69030 Installation of Sinages 7 27-Feb-13 06-Mar-13 09-Apr-13 16-Apr-13 35 MEP WorkMEP Works 126 12-Jul-12 12-Dec-12 18-Dec-12 29-Jan-13 39 HVACHVAC 10 12-Jul-12 23-Jul-12 17-Jan-13 29-Jan-13 155 A69050 Chilled Water Pipe Installation & Insulation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155 A69060 Condensate Pipe Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155 A69130 Installation of Induction Fans 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155 ElectricalElectrical 126 12-Jul-12 12-Dec-12 18-Dec-12 29-Jan-13 39 A116230 Instalaltion of Cable Trays 10 12-Jul-12 23-Jul-12 29-Dec-12 09-Jan-13 139 A116240 Instalaltion of Bus Bars 15 31-Oct-12 18-Nov-12 18-Dec-12 05-Jan-13 39 A116250 Cable Pulling 10 19-Nov-12 29-Nov-12 06-Jan-13 16-Jan-13 39 A69020 Installation of Lighting Fittings 10 01-Dec-12 12-Dec-12 17-Jan-13 29-Jan-13 39 PlumbingPlumbing 10 12-Jul-12 23-Jul-12 17-Jan-13 29-Jan-13 155 A69100 H/L Hot&Cold Water Pipe Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155 A69120 Floor Drain Fixning 7 12-Jul-12 19-Jul-12 21-Jan-13 29-Jan-13 158 A69140 H/L Drainage Pipes Installation 7 12-Jul-12 19-Jul-12 17-Jan-13 26-Jan-13 155 A69110 Water Pipes Testing 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155 A69150 Drainage&Water Pipes Testing 3 21-Jul-12 23-Jul-12 27-Jan-13 29-Jan-13 155 Fire FighFire Fighting 26 21-Jul-12 21-Aug-12 29-Dec-12 29-Jan-13 132 A69090 Fire Fighting Pipe 8 21-Jul-12 29-Jul-12 29-Dec-12 07-Jan-13 132 A69080 Hydro Static Test for Pipes 5 30-Jul-12 04-Aug-12 08-Jan-13 13-Jan-13 132 A69070 Sprinkler Fixing 7 05-Aug-12 12-Aug-12 14-Jan-13 21-Jan-13 132 A69040 Fire Alarm Devices 6 13-Aug-12 21-Aug-12 22-Jan-13 29-Jan-13 132 Lift LobbyLift Lobby 86 05-Jul-12 15-Oct-12 14-Nov-12 16-Apr-13 151 FinishingFinishing Works 86 05-Jul-12 15-Oct-12 14-Nov-12 16-Apr-13 151 Wet WorWet Works 40 05-Jul-12 22-Aug-12 14-Nov-12 02-Jan-13 109 A68660 Block Works 6 05-Jul-12 11-Jul-12 14-Nov-12 21-Nov-12 109 A68610 Plaster Works 7 18-Jul-12 25-Jul-12 28-Nov-12 06-Dec-12 109 A68630 Installation of Suspended Ceiling Grid 2 30-Jul-12 31-Jul-12 25-Dec-12 26-Dec-12 121 A68620 1st Coat Paint 5 15-Aug-12 22-Aug-12 27-Dec-12 02-Jan-13 109 Fisrt StaFisrt Stage Finishes 9 23-Aug-12 02-Sep-12 03-Jan-13 13-Feb-13 135 A68880 MDF for Lift Lobby Wall 2 23-Aug-12 25-Aug-12 09-Feb-13 10-Feb-13 139 A68640 Suspended Ceiling Tiles 6 23-Aug-12 29-Aug-12 03-Jan-13 09-Jan-13 109 A68860 Screed Works 3 30-Aug-12 02-Sep-12 11-Feb-13 13-Feb-13 135 Second SSecond Stage Finishes 10 03-Sep-12 13-Sep-12 14-Feb-13 25-Feb-13 135 A68870 Wall Tiles Work 5 03-Sep-12 08-Sep-12 14-Feb-13 19-Feb-13 135 A68900 Floor Tiles Work 5 09-Sep-12 13-Sep-12 20-Feb-13 25-Feb-13 135 Final StaFinal Stage Finishes 27 15-Sep-12 15-Oct-12 26-Feb-13 16-Apr-13 151 A68650 Installation of Doors 2 15-Sep-12 16-Sep-12 26-Feb-13 27-Feb-13 135 A68670 Doors Ironmongery 2 15-Sep-12 16-Sep-12 09-Apr-13 10-Apr-13 171 A68910 Final Coat Paint 5 15-Sep-12 19-Sep-12 24-Mar-13 28-Mar-13 157 A68850 Installation of Sinages 2 14-Oct-12 15-Oct-12 15-Apr-13 16-Apr-13 151 MEP WorkMEP Works 47 12-Jul-12 06-Sep-12 25-Nov-12 23-Mar-13 163 HVACHVAC 47 12-Jul-12 06-Sep-12 11-Dec-12 05-Mar-13 148 A68680 Duct Installation & Insulation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124 A68690 Chilled Water Pipe Installation & Insulation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124 A68700 Condensate Pipe Installation 5 12-Jul-12 17-Jul-12 11-Dec-12 16-Dec-12 124 A68710 FCU Installation 7 18-Jul-12 25-Jul-12 17-Dec-12 24-Dec-12 124 A68720 Air-Outlet Installation 7 30-Aug-12 06-Sep-12 26-Feb-13 05-Mar-13 148 ElectricalElectrical 46 12-Jul-12 05-Sep-12 25-Nov-12 16-Jan-13 109 A68730 Install Conduits in Wall 3 12-Jul-12 15-Jul-12 25-Nov-12 27-Nov-12 111 A68740 Install Cable Trays & Trunking 4 12-Jul-12 16-Jul-12 29-Nov-12 04-Dec-12 115 A68780 Cable Laying for Low Current System 3 17-Jul-12 19-Jul-12 24-Dec-12 26-Dec-12 131 A68790 Cable Laying for Power 3 17-Jul-12 19-Jul-12 24-Dec-12 26-Dec-12 131 A68750 Wiring for Lighting & Power 3 26-Jul-12 29-Jul-12 22-Dec-12 24-Dec-12 121 A68760 Wiring for Low Current System 3 26-Jul-12 29-Jul-12 22-Dec-12 24-Dec-12 121 A68770 DB installation,Dressing & Termination 4 01-Aug-12 05-Aug-12 06-Jan-13 09-Jan-13 128 A68810 Installation of Lighting Fittings 6 30-Aug-12 05-Sep-12 10-Jan-13 16-Jan-13 109 Fire FighFire Fighting 47 12-Jul-12 06-Sep-12 12-Dec-12 23-Mar-13 163 A68840 Fire Fighting Pipe 7 12-Jul-12 19-Jul-12 12-Dec-12 19-Dec-12 125 A68830 Hydro Static Test for Pipes 4 21-Jul-12 24-Jul-12 20-Dec-12 24-Dec-12 125 A68820 Sprinkler Fixing 6 30-Aug-12 05-Sep-12 27-Feb-13 05-Mar-13 149 A68890 Fire Alarm Devices 7 30-Aug-12 06-Sep-12 16-Mar-13 23-Mar-13 163 MechanicaMechanical Rooms 149 01-Jul-12 27-Dec-12 10-Nov-12 16-Apr-13 92 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 GRP Lining on the Ceiling GRP Lining on the Wall Reinforced Plastic on the Floor Installation of Lighting Fittings Installation of Water Supply Pipes&Fittings Install of Water Meter Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Plaster Works 1st Coat Paint Installation of Kerbs Installation of Interlocking Tiles Surface Preparation (including Grinding & Repairing) Application of 1st Coat Application of Final Coat Road Marking & Arrows Installation of Speed Hump Final Coat Paint Installation of Sinages Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Installation of Induction Fans Instalaltion of Cable Trays Instalaltion of Bus Bars Cable Pulling Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Floor Drain Fixning H/L Drainage Pipes Installation Water Pipes Testing Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint MDF for Lift Lobby Wall Suspended Ceiling Tiles Screed Works Wall Tiles Work Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Lighting Fittings Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 84 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 85. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float FinishingFinishing Works 149 01-Jul-12 27-Dec-12 10-Nov-12 16-Apr-13 92 Wet WorWet Works 39 01-Jul-12 14-Aug-12 10-Nov-12 27-Feb-13 161 A68100 Block Works 4 01-Jul-12 04-Jul-12 10-Nov-12 13-Nov-12 109 A68060 Installation of Doors& Windows Sub-frame 3 26-Jul-12 29-Jul-12 25-Feb-13 27-Feb-13 175 A68050 Plaster Works 7 26-Jul-12 02-Aug-12 08-Dec-12 15-Dec-12 109 A68070 1st Coat Paint 6 08-Aug-12 14-Aug-12 20-Dec-12 26-Dec-12 109 Fisrt StaFisrt Stage Finishes 78 17-Sep-12 20-Dec-12 28-Feb-13 14-Apr-13 96 A68090 Installation of Doors 3 17-Sep-12 19-Sep-12 28-Feb-13 03-Mar-13 135 A68110 Doors Ironmongery 3 17-Sep-12 19-Sep-12 11-Apr-13 14-Apr-13 171 A68160 Epoxy Paint Works 3 18-Dec-12 20-Dec-12 28-Feb-13 03-Mar-13 60 Second SSecond Stage Finishes 4 22-Dec-12 25-Dec-12 30-Mar-13 02-Apr-13 82 A68080 Final Coat Paint 4 22-Dec-12 25-Dec-12 30-Mar-13 02-Apr-13 82 Final StaFinal Stage Finishes 2 26-Dec-12 27-Dec-12 15-Apr-13 16-Apr-13 92 A68150 Installation of Sinages 2 26-Dec-12 27-Dec-12 15-Apr-13 16-Apr-13 92 MEP WorkMEP Works 136 05-Jul-12 17-Dec-12 03-Dec-12 27-Feb-13 60 HVACHVAC 15 15-Aug-12 03-Sep-12 06-Feb-13 23-Feb-13 142 A68170 Shaft Works 15 15-Aug-12 03-Sep-12 06-Feb-13 23-Feb-13 142 ElectricalElectrical 136 05-Jul-12 17-Dec-12 03-Dec-12 27-Feb-13 60 A68120 Install Conduits in Wall 4 05-Jul-12 09-Jul-12 03-Dec-12 06-Dec-12 123 A68130 Wiring for Lighting & Power 4 04-Aug-12 07-Aug-12 16-Dec-12 19-Dec-12 109 A68140 Installation of Lighting Fittings 4 13-Dec-12 17-Dec-12 24-Feb-13 27-Feb-13 60 PlumbingPlumbing 7 15-Aug-12 25-Aug-12 20-Feb-13 27-Feb-13 154 A68180 Floor Drain Fixning 7 15-Aug-12 25-Aug-12 20-Feb-13 27-Feb-13 154 StaircaseStaircase 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174 Stairs 1Stairs 1 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174 A111390 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148 A111430 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148 A111400 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111410 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111420 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148 A111440 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174 Stairs 2Stairs 2 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174 A111450 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148 A111490 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148 A111460 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111470 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111480 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148 A111500 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174 Stairs 3Stairs 3 43 29-Jul-12 18-Sep-12 27-Jan-13 16-Apr-13 174 A111510 Floor Screed 3 29-Jul-12 31-Jul-12 27-Jan-13 29-Jan-13 148 A111550 Install Handrails 4 01-Aug-12 05-Aug-12 30-Jan-13 03-Feb-13 148 A111520 Ceiling 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111530 Wall 1st Coat Paint 12 06-Aug-12 21-Aug-12 04-Feb-13 17-Feb-13 148 A111540 Install Granite/Terrazo 12 22-Aug-12 04-Sep-12 18-Feb-13 03-Mar-13 148 A111560 Final Coat Paint 12 05-Sep-12 18-Sep-12 03-Apr-13 16-Apr-13 174 Ground FloorGround Floor 134 22-Jul-12 31-Dec-12 03-Dec-12 16-Apr-13 89 Public AreaPublic Area 134 22-Jul-12 31-Dec-12 03-Dec-12 16-Apr-13 89 Super MarSuper Market 91 11-Sep-12 30-Dec-12 22-Jan-13 16-Apr-13 90 FinishingFinishing Works 91 11-Sep-12 30-Dec-12 22-Jan-13 16-Apr-13 90 Wet WorWet Works 26 11-Sep-12 10-Oct-12 22-Jan-13 30-Mar-13 140 A71470 Block Works 21 11-Sep-12 04-Oct-12 22-Jan-13 16-Feb-13 109 A71450 Installation of Doors& Windows Sub-frame 5 06-Oct-12 10-Oct-12 25-Mar-13 30-Mar-13 140 Final StaFinal Stage Finishes 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90 A71460 Installation of Windows&Doors 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90 A71480 Doors Ironmongery 15 13-Dec-12 30-Dec-12 31-Mar-13 16-Apr-13 90 MEP WorkMEP Works 19 06-Oct-12 29-Oct-12 17-Feb-13 16-Apr-13 141 HVACHVAC 15 06-Oct-12 22-Oct-12 17-Feb-13 05-Mar-13 109 A71490 Chilled Water Pipe Installation & Insulation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109 A71500 Condensate Pipe Installation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109 A71640 Duct Installation & Insulation 10 06-Oct-12 16-Oct-12 17-Feb-13 27-Feb-13 109 A71510 FCU Installation 5 17-Oct-12 22-Oct-12 28-Feb-13 05-Mar-13 109 ElectricalElectrical 10 06-Oct-12 16-Oct-12 23-Feb-13 05-Mar-13 114 A71520 Install Conduits in Wall 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114 A71530 Wiring for Lighting & Power 3 14-Oct-12 16-Oct-12 03-Mar-13 05-Mar-13 114 PlumbingPlumbing 10 06-Oct-12 16-Oct-12 23-Feb-13 05-Mar-13 114 A71540 Drainge Pipes in Wall 7 06-Oct-12 13-Oct-12 26-Feb-13 05-Mar-13 117 A71550 H/L Drainage Pipes Installation 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114 A71560 H/L Hot&Cold Water Pipe Installation 7 06-Oct-12 13-Oct-12 23-Feb-13 02-Mar-13 114 A71580 Water Pipes in Wall 7 06-Oct-12 13-Oct-12 26-Feb-13 05-Mar-13 117 A71570 Drainage&Water Pipes Testing 3 14-Oct-12 16-Oct-12 03-Mar-13 05-Mar-13 114 Fire FighFire Fighting 19 06-Oct-12 29-Oct-12 18-Feb-13 16-Apr-13 141 A71620 Fire Fighting Pipe 7 06-Oct-12 13-Oct-12 18-Feb-13 25-Feb-13 110 A71610 Hydro Static Test for Pipes 4 14-Oct-12 17-Oct-12 26-Feb-13 02-Mar-13 110 A71600 Sprinkler Fixing 3 18-Oct-12 21-Oct-12 03-Mar-13 05-Mar-13 110 A71590 Installation of Fire Extingusher&Blanket 2 22-Oct-12 23-Oct-12 15-Apr-13 16-Apr-13 144 A71630 Fire Alarm Devices 5 22-Oct-12 29-Oct-12 11-Apr-13 16-Apr-13 141 EnteranceEnterance - Lift Lobby - Super Market Corridor 112 11-Aug-12 25-Dec-12 23-Dec-12 16-Apr-13 94 FinishingFinishing Works 112 11-Aug-12 25-Dec-12 23-Dec-12 16-Apr-13 94 Wet WorWet Works 32 11-Aug-12 18-Sep-12 23-Dec-12 10-Feb-13 118 A71700 Block Works 5 11-Aug-12 15-Aug-12 23-Dec-12 27-Dec-12 109 A71650 Plaster Works 5 26-Aug-12 30-Aug-12 13-Jan-13 17-Jan-13 115 A71670 Installation of Suspended Ceiling Grid 7 04-Sep-12 11-Sep-12 22-Jan-13 30-Jan-13 115 A71660 1st Coat Paint 6 12-Sep-12 18-Sep-12 04-Feb-13 10-Feb-13 118 Fisrt StaFisrt Stage Finishes 8 23-Sep-12 01-Oct-12 11-Feb-13 18-Mar-13 138 A71680 Suspended Ceiling Tiles 6 23-Sep-12 29-Sep-12 11-Feb-13 17-Feb-13 115 A71880 Screed Works 2 30-Sep-12 01-Oct-12 17-Mar-13 18-Mar-13 138 Second SSecond Stage Finishes 58 02-Oct-12 12-Dec-12 19-Mar-13 30-Mar-13 90 A71920 Floor Tiles Work 6 02-Oct-12 08-Oct-12 19-Mar-13 25-Mar-13 138 A71710 Doors Ironmongery 3 09-Dec-12 11-Dec-12 27-Mar-13 30-Mar-13 91 A71690 Installation of Doors 4 09-Dec-12 12-Dec-12 26-Mar-13 30-Mar-13 90 Final StaFinal Stage Finishes 11 13-Dec-12 25-Dec-12 04-Apr-13 16-Apr-13 94 A71930 Final Coat Paint 7 13-Dec-12 20-Dec-12 04-Apr-13 11-Apr-13 94 A71870 Installation of Sinages 4 22-Dec-12 25-Dec-12 13-Apr-13 16-Apr-13 94 MEP WorkMEP Works 45 16-Aug-12 09-Oct-12 06-Jan-13 05-Mar-13 120 HVACHVAC 43 16-Aug-12 07-Oct-12 08-Jan-13 25-Feb-13 115 A71720 Duct Installation & Insulation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117 A71730 Chilled Water Pipe Installation & Insulation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117 A71740 Condensate Pipe Installation 7 16-Aug-12 26-Aug-12 08-Jan-13 15-Jan-13 117 A71750 FCU Installation 5 27-Aug-12 01-Sep-12 16-Jan-13 21-Jan-13 117 A71760 Air-Outlet Installation 7 30-Sep-12 07-Oct-12 18-Feb-13 25-Feb-13 115 ElectricalElectrical 42 16-Aug-12 06-Oct-12 09-Jan-13 05-Mar-13 123 A71770 Install Conduits in Wall 3 16-Aug-12 21-Aug-12 09-Jan-13 12-Jan-13 118 A71780 Install Cable Trays & Trunking 3 16-Aug-12 21-Aug-12 13-Jan-13 15-Jan-13 121 A71810 Cable Laying for Low Current System 5 22-Aug-12 27-Aug-12 26-Jan-13 30-Jan-13 128 A71820 Cable Laying for Power 5 22-Aug-12 27-Aug-12 26-Jan-13 30-Jan-13 128 A71790 Wiring for Lighting & Power 3 01-Sep-12 03-Sep-12 19-Jan-13 21-Jan-13 115 A71800 Wiring for Low Current System 3 01-Sep-12 03-Sep-12 19-Jan-13 21-Jan-13 115 A71830 Installation of Lighting Fittings 6 30-Sep-12 06-Oct-12 27-Feb-13 05-Mar-13 123 PlumbingPlumbing 14 16-Aug-12 03-Sep-12 26-Jan-13 10-Feb-13 131 A71970 H/L Hot&Cold Water Pipe Installation 7 16-Aug-12 26-Aug-12 26-Jan-13 02-Feb-13 131 A71980 Water Pipes in Wall 7 27-Aug-12 03-Sep-12 03-Feb-13 10-Feb-13 131 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Shaft Works Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Floor Drain Fixning Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Installation of Windows&Doors Doors Ironmongery Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 85 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 86. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float Fire FighFire Fighting 45 16-Aug-12 09-Oct-12 06-Jan-13 05-Mar-13 120 A71860 Fire Fighting Pipe 7 16-Aug-12 26-Aug-12 06-Jan-13 13-Jan-13 115 A71850 Hydro Static Test for Pipes 7 27-Aug-12 03-Sep-12 14-Jan-13 21-Jan-13 115 A71840 Sprinkler Fixing 5 01-Oct-12 06-Oct-12 25-Feb-13 02-Mar-13 120 A71910 Fire Alarm Devices 7 30-Sep-12 07-Oct-12 24-Feb-13 03-Mar-13 120 A71950 Installation of Fire Hose Cabinet & Landing Valve 2 08-Oct-12 09-Oct-12 04-Mar-13 05-Mar-13 120 Retails - (1Retails - (1 - 8) 92 16-Aug-12 08-Dec-12 29-Dec-12 16-Apr-13 109 FinishingFinishing Works 92 16-Aug-12 08-Dec-12 29-Dec-12 26-Mar-13 91 Wet WorWet Works 32 16-Aug-12 24-Sep-12 29-Dec-12 11-Mar-13 138 A69180 Block Works 20 16-Aug-12 10-Sep-12 29-Dec-12 21-Jan-13 109 A69160 Installation of Doors& Windows Sub-frame 12 11-Sep-12 24-Sep-12 26-Feb-13 11-Mar-13 138 Final StaFinal Stage Finishes 12 24-Nov-12 08-Dec-12 12-Mar-13 26-Mar-13 91 A69170 Installation of Windows&Doors 12 24-Nov-12 08-Dec-12 12-Mar-13 25-Mar-13 90 A69190 Doors Ironmongery 10 26-Nov-12 08-Dec-12 16-Mar-13 26-Mar-13 91 MEP WorkMEP Works 19 11-Sep-12 02-Oct-12 05-Feb-13 16-Apr-13 162 HVACHVAC 15 11-Sep-12 27-Sep-12 05-Feb-13 27-Feb-13 125 A69200 Chilled Water Pipe Installation & Insulation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120 A69210 Condensate Pipe Installation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120 A69350 Duct Installation & Insulation 10 11-Sep-12 22-Sep-12 05-Feb-13 16-Feb-13 120 A69220 FCU Installation 5 23-Sep-12 27-Sep-12 23-Feb-13 27-Feb-13 125 ElectricalElectrical 10 11-Sep-12 22-Sep-12 23-Feb-13 05-Mar-13 135 A69230 Install Conduits in Wall 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135 A69240 Wiring for Lighting & Power 3 19-Sep-12 22-Sep-12 03-Mar-13 05-Mar-13 135 PlumbingPlumbing 10 11-Sep-12 22-Sep-12 23-Feb-13 05-Mar-13 135 A69250 Drainge Pipes in Wall 7 11-Sep-12 18-Sep-12 26-Feb-13 05-Mar-13 138 A69260 H/L Drainage Pipes Installation 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135 A69270 H/L Hot&Cold Water Pipe Installation 7 11-Sep-12 18-Sep-12 23-Feb-13 02-Mar-13 135 A69290 Water Pipes in Wall 7 11-Sep-12 18-Sep-12 26-Feb-13 05-Mar-13 138 A69280 Drainage&Water Pipes Testing 3 19-Sep-12 22-Sep-12 03-Mar-13 05-Mar-13 135 Fire FighFire Fighting 19 11-Sep-12 02-Oct-12 05-Feb-13 16-Apr-13 162 A69330 Fire Fighting Pipe 7 11-Sep-12 18-Sep-12 05-Feb-13 12-Feb-13 120 A69320 Hydro Static Test for Pipes 4 19-Sep-12 23-Sep-12 13-Feb-13 17-Feb-13 120 A69310 Sprinkler Fixing 3 24-Sep-12 26-Sep-12 18-Feb-13 20-Feb-13 120 A69300 Installation of Fire Extingusher&Blanket 2 27-Sep-12 29-Sep-12 15-Apr-13 16-Apr-13 165 A69340 Fire Alarm Devices 5 27-Sep-12 02-Oct-12 11-Apr-13 16-Apr-13 162 Electrical /Electrical /Telephone / GSM Rooms 110 22-Jul-12 03-Dec-12 03-Dec-12 16-Apr-13 113 FinishingFinishing Works 110 22-Jul-12 03-Dec-12 03-Dec-12 16-Apr-13 113 Wet WorWet Works 21 22-Jul-12 14-Aug-12 03-Dec-12 21-Feb-13 156 A70810 Block Works 6 22-Jul-12 28-Jul-12 03-Dec-12 09-Dec-12 109 A70770 Installation of Doors& Windows Sub-frame 2 01-Aug-12 02-Aug-12 20-Feb-13 21-Feb-13 166 A70760 Plaster Works 5 01-Aug-12 06-Aug-12 20-Dec-12 25-Dec-12 115 A70780 1st Coat Paint 4 11-Aug-12 14-Aug-12 30-Dec-12 03-Jan-13 115 Fisrt StaFisrt Stage Finishes 38 09-Oct-12 25-Nov-12 27-Feb-13 14-Mar-13 91 A70870 Epoxy Paint Works 2 09-Oct-12 10-Oct-12 27-Feb-13 28-Feb-13 115 A70800 Installation of Doors 2 11-Oct-12 13-Oct-12 02-Mar-13 03-Mar-13 115 A70820 Doors Ironmongery 2 24-Nov-12 25-Nov-12 13-Mar-13 14-Mar-13 91 Second SSecond Stage Finishes 3 11-Oct-12 14-Oct-12 30-Mar-13 01-Apr-13 139 A70790 Final Coat Paint 3 11-Oct-12 14-Oct-12 30-Mar-13 01-Apr-13 139 Final StaFinal Stage Finishes 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113 A70860 Installation of Sinages 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113 MEP WorkMEP Works 60 29-Jul-12 08-Oct-12 17-Dec-12 01-Apr-13 144 HVACHVAC 7 15-Aug-12 25-Aug-12 10-Feb-13 17-Feb-13 145 A70890 Air-Outlet Installation 7 15-Aug-12 25-Aug-12 10-Feb-13 17-Feb-13 145 ElectricalElectrical 60 29-Jul-12 08-Oct-12 17-Dec-12 26-Feb-13 115 A70830 Install Conduits in Wall 3 29-Jul-12 31-Jul-12 17-Dec-12 19-Dec-12 115 A70840 Wiring for Lighting & Power 3 07-Aug-12 09-Aug-12 26-Dec-12 29-Dec-12 115 A114950 Installation of SMDBs 7 15-Aug-12 25-Aug-12 14-Feb-13 21-Feb-13 149 A70850 Installation of Lighting Fittings 4 26-Aug-12 29-Aug-12 23-Feb-13 26-Feb-13 149 A114960 Installation of Telephone System 21 15-Aug-12 10-Sep-12 03-Feb-13 26-Feb-13 139 A114970 Installation of GSM System 45 15-Aug-12 08-Oct-12 05-Jan-13 26-Feb-13 115 Fire FighFire Fighting 8 15-Aug-12 26-Aug-12 20-Feb-13 01-Apr-13 181 A70880 Fire Alarm Devices 6 15-Aug-12 23-Aug-12 20-Feb-13 26-Feb-13 154 A70900 Installation of Fire Extingusher&Blanket 2 25-Aug-12 26-Aug-12 31-Mar-13 01-Apr-13 181 Main GarbMain Garbage Room 128 29-Jul-12 31-Dec-12 10-Dec-12 16-Apr-13 89 FinishingFinishing Works 128 29-Jul-12 31-Dec-12 10-Dec-12 16-Apr-13 89 Wet WorWet Works 26 29-Jul-12 29-Aug-12 10-Dec-12 23-Feb-13 146 A70970 Block Works 4 29-Jul-12 01-Aug-12 10-Dec-12 13-Dec-12 109 A70920 Installation of Doors& Windows Sub-frame 1 07-Aug-12 07-Aug-12 23-Feb-13 23-Feb-13 163 A70910 Plaster Works 5 07-Aug-12 12-Aug-12 26-Dec-12 31-Dec-12 115 A71140 Wall Tiles Work 8 13-Aug-12 23-Aug-12 02-Jan-13 10-Jan-13 115 A70930 1st Coat Paint 3 27-Aug-12 29-Aug-12 14-Jan-13 16-Jan-13 115 Fisrt StaFisrt Stage Finishes 7 25-Aug-12 01-Sep-12 12-Jan-13 19-Jan-13 115 A71130 Screed Works 2 25-Aug-12 26-Aug-12 12-Jan-13 13-Jan-13 115 A71150 Floor Tiles Work 2 30-Aug-12 01-Sep-12 17-Jan-13 19-Jan-13 115 Second SSecond Stage Finishes 60 16-Oct-12 29-Dec-12 04-Feb-13 14-Apr-13 89 A70960 Installation of Equipments 60 16-Oct-12 29-Dec-12 04-Feb-13 14-Apr-13 89 Final StaFinal Stage Finishes 37 18-Nov-12 31-Dec-12 06-Mar-13 16-Apr-13 89 A70950 Installation of Doors 5 18-Nov-12 22-Nov-12 06-Mar-13 11-Mar-13 90 A70980 Doors Ironmongery 5 18-Nov-12 22-Nov-12 07-Mar-13 12-Mar-13 91 A70940 Final Coat Paint 2 30-Dec-12 31-Dec-12 15-Apr-13 16-Apr-13 89 MEP WorkMEP Works 29 02-Aug-12 06-Sep-12 22-Dec-12 14-Apr-13 182 HVACHVAC 7 02-Aug-12 09-Aug-12 29-Dec-12 13-Jan-13 127 A70990 Chilled Water Pipe Installation & Insulation 4 02-Aug-12 06-Aug-12 29-Dec-12 02-Jan-13 121 A71000 Condensate Pipe Installation 4 02-Aug-12 06-Aug-12 29-Dec-12 02-Jan-13 121 A71010 FCU Installation 3 07-Aug-12 09-Aug-12 10-Jan-13 13-Jan-13 127 ElectricalElectrical 17 02-Aug-12 23-Aug-12 22-Dec-12 05-Mar-13 160 A71020 Install Conduits in Wall 4 02-Aug-12 06-Aug-12 22-Dec-12 25-Dec-12 115 A71030 Wiring for Lighting & Power 4 13-Aug-12 16-Aug-12 25-Feb-13 28-Feb-13 160 A71040 Installation of Lighting Fittings 4 18-Aug-12 23-Aug-12 02-Mar-13 05-Mar-13 160 PlumbingPlumbing 7 02-Aug-12 09-Aug-12 23-Dec-12 31-Dec-12 117 A71080 Water Pipes in Wall 3 02-Aug-12 05-Aug-12 23-Dec-12 25-Dec-12 116 A71050 H/L Drainage Pipes Installation 4 02-Aug-12 06-Aug-12 24-Dec-12 27-Dec-12 117 A71060 H/L Hot&Cold Water Pipe Installation 4 02-Aug-12 06-Aug-12 24-Dec-12 27-Dec-12 117 A71070 Drainage&Water Pipes Testing 3 07-Aug-12 09-Aug-12 29-Dec-12 31-Dec-12 117 Fire FighFire Fighting 29 02-Aug-12 06-Sep-12 26-Dec-12 14-Apr-13 182 A71120 Fire Fighting Pipe 5 02-Aug-12 07-Aug-12 26-Dec-12 31-Dec-12 119 A71110 Hydro Static Test for Pipes 5 08-Aug-12 13-Aug-12 06-Feb-13 11-Feb-13 148 A71100 Sprinkler Fixing 5 30-Aug-12 04-Sep-12 12-Feb-13 17-Feb-13 136 A71160 Fire Alarm Devices 5 30-Aug-12 04-Sep-12 09-Apr-13 14-Apr-13 184 A71090 Installation of Fire Extingusher&Blanket 2 05-Sep-12 06-Sep-12 13-Apr-13 14-Apr-13 182 ToiletsToilets 100 02-Aug-12 03-Dec-12 15-Dec-12 16-Apr-13 113 FinishingFinishing Works 100 02-Aug-12 03-Dec-12 15-Dec-12 16-Apr-13 113 Wet WorWet Works 29 02-Aug-12 06-Sep-12 15-Dec-12 25-Feb-13 141 A72380 Block Works 7 02-Aug-12 09-Aug-12 15-Dec-12 22-Dec-12 109 A72320 Installation of Doors& Windows Sub-frame 2 15-Aug-12 16-Aug-12 24-Feb-13 25-Feb-13 157 A72310 Plaster Works 7 15-Aug-12 25-Aug-12 05-Jan-13 12-Jan-13 115 A72630 Wall Tiles Work 5 02-Sep-12 06-Sep-12 20-Jan-13 26-Jan-13 115 Fisrt StaFisrt Stage Finishes 17 08-Sep-12 26-Sep-12 27-Jan-13 03-Mar-13 129 A72620 Screed Works 2 08-Sep-12 09-Sep-12 27-Jan-13 28-Jan-13 115 A72340 Water Proofing for Wet Area 2 10-Sep-12 11-Sep-12 29-Jan-13 30-Jan-13 115 A72660 Installation of Suspended Ceiling Grid 4 12-Sep-12 16-Sep-12 31-Jan-13 04-Feb-13 115 A72650 Suspended Ceiling Tiles 5 17-Sep-12 22-Sep-12 05-Feb-13 10-Feb-13 115 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Hose Cabinet & Landing Valve Block Works Installation of Doors& Windows Sub-frame Installation of Windows&Doors Doors Ironmongery Chilled Water Pipe Installation & Insulation Condensate Pipe Installation Duct Installation & Insulation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Drainge Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Water Pipes in Wall Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Installation of GSM System Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Installation of Equipments Installation of Doors Doors Ironmongery Final Coat Paint Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid Suspended Ceiling Tiles Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 86 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 87. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A72640 Floor Tiles Work 4 23-Sep-12 26-Sep-12 27-Feb-13 03-Mar-13 129 Second SSecond Stage Finishes 4 14-Nov-12 19-Nov-12 04-Mar-13 01-Apr-13 111 A72350 Installation of Windows&Doors 2 14-Nov-12 17-Nov-12 04-Mar-13 05-Mar-13 90 A72390 Doors Ironmongery 2 14-Nov-12 17-Nov-12 05-Mar-13 06-Mar-13 91 A72360 Installation of Mirrors 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111 A72370 Installation of Vanity Counter 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111 A72600 Installation of Toliets Accessories 2 18-Nov-12 19-Nov-12 31-Mar-13 01-Apr-13 111 Final StaFinal Stage Finishes 11 20-Nov-12 03-Dec-12 02-Apr-13 16-Apr-13 113 A72330 Final Coat Paint 2 20-Nov-12 21-Nov-12 02-Apr-13 03-Apr-13 111 A72610 Installation of Sinages 2 01-Dec-12 03-Dec-12 15-Apr-13 16-Apr-13 113 MEP WorkMEP Works 55 11-Aug-12 15-Oct-12 30-Dec-12 03-Apr-13 140 HVACHVAC 55 11-Aug-12 15-Oct-12 03-Jan-13 05-Mar-13 115 A72400 Duct Installation & Insulation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118 A72410 Chilled Water Pipe Installation & Insulation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118 A72420 Condensate Pipe Installation 4 11-Aug-12 14-Aug-12 03-Jan-13 07-Jan-13 118 A72430 FCU Installation 2 15-Aug-12 16-Aug-12 14-Jan-13 15-Jan-13 123 A72440 Air-Outlet Installation 7 08-Oct-12 15-Oct-12 26-Feb-13 05-Mar-13 115 ElectricalElectrical 40 11-Aug-12 27-Sep-12 30-Dec-12 05-Mar-13 130 A72450 Install Conduits in Wall 4 11-Aug-12 14-Aug-12 30-Dec-12 03-Jan-13 115 A72460 Wiring for Lighting & Power 4 26-Aug-12 29-Aug-12 27-Jan-13 30-Jan-13 126 A72470 Installation of Lighting Fittings 5 23-Sep-12 27-Sep-12 28-Feb-13 05-Mar-13 130 PlumbingPlumbing 42 11-Aug-12 30-Sep-12 31-Dec-12 01-Apr-13 151 A72480 Drainge Pipes in Wall 3 11-Aug-12 13-Aug-12 31-Dec-12 03-Jan-13 116 A72550 Water Pipes in Wall 3 11-Aug-12 13-Aug-12 31-Dec-12 03-Jan-13 116 A72490 H/L Drainage Pipes Installation 4 11-Aug-12 14-Aug-12 22-Jan-13 27-Jan-13 134 A72500 H/L Hot&Cold Water Pipe Installation 4 11-Aug-12 14-Aug-12 22-Jan-13 27-Jan-13 134 A72520 ElectricalWater Heater Installation 2 15-Aug-12 16-Aug-12 29-Jan-13 30-Jan-13 135 A72510 Drainage&Water Pipes Testing 3 15-Aug-12 18-Aug-12 28-Jan-13 30-Jan-13 134 A72530 Floor Drain Fixning 2 10-Sep-12 11-Sep-12 26-Feb-13 27-Feb-13 139 A72540 Installation of Sanitaryware 3 27-Sep-12 30-Sep-12 30-Mar-13 01-Apr-13 151 Fire FighFire Fighting 44 11-Aug-12 02-Oct-12 02-Jan-13 03-Apr-13 151 A72590 Fire Fighting Pipe 3 11-Aug-12 13-Aug-12 02-Jan-13 05-Jan-13 117 A72580 Hydro Static Test for Pipes 3 14-Aug-12 16-Aug-12 28-Jan-13 30-Jan-13 135 A72670 Fire Alarm Devices 4 23-Sep-12 26-Sep-12 28-Mar-13 01-Apr-13 154 A72570 Sprinkler Fixing 3 27-Sep-12 30-Sep-12 21-Feb-13 24-Feb-13 120 A72560 Installation of Fire Extingusher&Blanket 2 01-Oct-12 02-Oct-12 02-Apr-13 03-Apr-13 151 StaircaseStaircase 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153 Stairs 1Stairs 1 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153 A111570 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153 A111610 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 A111580 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111590 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111600 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153 A111620 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153 Stairs 2Stairs 2 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153 A111630 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153 A111670 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 A111640 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111650 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111660 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153 A111680 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153 Stairs 3Stairs 3 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153 A111690 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153 A111730 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 A111700 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111710 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A111720 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153 A111740 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153 Stairs 4Stairs 4 43 25-Aug-12 13-Oct-12 26-Feb-13 16-Apr-13 153 A112110 Floor Screed 3 25-Aug-12 27-Aug-12 26-Feb-13 28-Feb-13 153 A112150 Install Handrails 4 28-Aug-12 01-Sep-12 02-Mar-13 05-Mar-13 153 A112120 Ceiling 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A112130 Wall 1st Coat Paint 12 02-Sep-12 15-Sep-12 06-Mar-13 19-Mar-13 153 A112140 Install Granite/Terrazo 12 16-Sep-12 29-Sep-12 20-Mar-13 02-Apr-13 153 A112160 Final Coat Paint 12 30-Sep-12 13-Oct-12 03-Apr-13 16-Apr-13 153 1st Floor1st Floor 187 15-Aug-12 30-Mar-13 29-Aug-12 16-Apr-13 15 Public AreaPublic Area 187 15-Aug-12 30-Mar-13 28-Nov-12 16-Apr-13 15 Garbage RGarbage Room 137 06-Oct-12 20-Mar-13 15-Jan-13 16-Apr-13 23 FinishingFinishing Works 137 06-Oct-12 20-Mar-13 15-Jan-13 16-Apr-13 23 Wet WorWet Works 65 06-Oct-12 24-Dec-12 15-Jan-13 07-Apr-13 87 A72740 Block Works 3 06-Oct-12 08-Oct-12 15-Jan-13 17-Jan-13 82 A72680 Plaster Works 3 17-Nov-12 19-Nov-12 23-Jan-13 27-Jan-13 56 A72690 Installation of Doors& Windows Sub-frame 1 21-Nov-12 21-Nov-12 07-Apr-13 07-Apr-13 114 A72720 Wall Tiles Work 4 22-Nov-12 26-Nov-12 30-Jan-13 03-Feb-13 56 A72700 1st Coat Paint 2 23-Dec-12 24-Dec-12 04-Feb-13 05-Feb-13 35 Fisrt StaFisrt Stage Finishes 25 17-Jan-13 16-Feb-13 12-Feb-13 15-Apr-13 50 A72870 Screed Works 2 17-Jan-13 19-Jan-13 12-Feb-13 13-Feb-13 21 A72890 Floor Tiles Work 2 21-Jan-13 22-Jan-13 16-Feb-13 17-Feb-13 21 A72750 Doors Ironmongery 1 14-Feb-13 14-Feb-13 15-Apr-13 15-Apr-13 51 A72730 Installation of Doors 2 14-Feb-13 16-Feb-13 08-Apr-13 09-Apr-13 45 Second SSecond Stage Finishes 2 18-Mar-13 19-Mar-13 04-Apr-13 06-Apr-13 15 A72710 Final Coat Paint 2 18-Mar-13 19-Mar-13 04-Apr-13 06-Apr-13 15 Final StaFinal Stage Finishes 1 20-Mar-13 20-Mar-13 16-Apr-13 16-Apr-13 23 A72860 Installation of Sinages 1 20-Mar-13 20-Mar-13 16-Apr-13 16-Apr-13 23 MEP WorkMEP Works 88 09-Oct-12 26-Jan-13 19-Jan-13 05-Mar-13 33 ElectricalElectrical 88 09-Oct-12 26-Jan-13 21-Jan-13 05-Mar-13 33 A72760 Install Conduits in Wall 2 09-Oct-12 10-Oct-12 21-Jan-13 22-Jan-13 84 A72770 Wiring for Lighting & Power 2 20-Nov-12 21-Nov-12 28-Jan-13 29-Jan-13 56 A72780 Installation of Lighting Fittings 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33 PlumbingPlumbing 84 09-Oct-12 20-Jan-13 19-Jan-13 14-Feb-13 21 A72790 Drainge Pipes in Wall 2 09-Oct-12 10-Oct-12 19-Jan-13 20-Jan-13 82 A72820 Water Pipes in Wall 2 09-Oct-12 10-Oct-12 19-Jan-13 20-Jan-13 82 A72800 Drainage&Water Pipes Testing 2 11-Oct-12 13-Oct-12 21-Jan-13 22-Jan-13 82 A72810 Floor Drain Fixning 1 20-Jan-13 20-Jan-13 14-Feb-13 14-Feb-13 21 Fire FighFire Fighting 87 10-Oct-12 26-Jan-13 13-Feb-13 27-Feb-13 28 A72850 Fire Fighting Pipe 2 10-Oct-12 11-Oct-12 13-Feb-13 14-Feb-13 102 A72840 Hydro Static Test for Pipes 2 13-Oct-12 14-Oct-12 16-Feb-13 17-Feb-13 102 A72830 Sprinkler Fixing 2 23-Jan-13 26-Jan-13 18-Feb-13 19-Feb-13 21 A72880 Fire Alarm Devices 2 23-Jan-13 26-Jan-13 26-Feb-13 27-Feb-13 28 Corridor &Corridor & Lift Lobby 153 26-Sep-12 30-Mar-13 20-Dec-12 16-Apr-13 15 FinishingFinishing Works 153 26-Sep-12 30-Mar-13 20-Dec-12 16-Apr-13 15 Wet WorWet Works 79 26-Sep-12 31-Dec-12 20-Dec-12 04-Feb-13 28 A72960 Block Works 8 26-Sep-12 04-Oct-12 20-Dec-12 29-Dec-12 69 A72900 Plaster Works 7 07-Nov-12 14-Nov-12 02-Jan-13 09-Jan-13 45 A72920 Installation of Suspended Ceiling Grid 6 22-Nov-12 28-Nov-12 15-Jan-13 21-Jan-13 44 A72910 1st Coat Paint 5 17-Dec-12 22-Dec-12 22-Jan-13 28-Jan-13 30 A72930 Suspended Ceiling Tiles 6 25-Dec-12 31-Dec-12 29-Jan-13 04-Feb-13 28 Fisrt StaFisrt Stage Finishes 61 14-Jan-13 26-Mar-13 09-Feb-13 13-Apr-13 15 A73190 Screed Works 3 14-Jan-13 16-Jan-13 09-Feb-13 11-Feb-13 21 A73200 Floor Tiles Work 5 20-Mar-13 25-Mar-13 07-Apr-13 11-Apr-13 15 A72940 Installation of Doors 3 24-Mar-13 26-Mar-13 10-Apr-13 13-Apr-13 15 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Floor Tiles Work Installation of Windows&Doors Doors Ironmongery Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation ElectricalWater Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Installation of Fire Extingusher&Blanket Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Doors Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 87 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 88. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A72970 Doors Ironmongery 3 24-Mar-13 26-Mar-13 10-Apr-13 13-Apr-13 15 Second SSecond Stage Finishes 5 25-Mar-13 30-Mar-13 11-Apr-13 16-Apr-13 15 A73210 Final Coat Paint 5 25-Mar-13 30-Mar-13 11-Apr-13 16-Apr-13 15 Final StaFinal Stage Finishes 3 27-Mar-13 30-Mar-13 14-Apr-13 16-Apr-13 15 A73180 Installation of Sinages 3 27-Mar-13 30-Mar-13 14-Apr-13 16-Apr-13 15 MEP WorkMEP Works 80 06-Oct-12 12-Jan-13 30-Dec-12 10-Apr-13 75 HVACHVAC 74 06-Oct-12 05-Jan-13 06-Jan-13 19-Feb-13 38 A73000 Condensate Pipe Installation 5 06-Oct-12 10-Oct-12 06-Jan-13 10-Jan-13 74 A72980 Duct Installation & Insulation 5 29-Oct-12 03-Nov-12 06-Jan-13 10-Jan-13 56 A72990 Chilled Water Pipe Installation & Insulation 5 29-Oct-12 03-Nov-12 06-Jan-13 10-Jan-13 56 A73010 FCU Installation 3 04-Nov-12 06-Nov-12 12-Jan-13 14-Jan-13 56 A73020 Air-Outlet Installation 3 02-Jan-13 05-Jan-13 17-Feb-13 19-Feb-13 38 ElectricalElectrical 76 06-Oct-12 07-Jan-13 30-Dec-12 05-Mar-13 48 A73030 Install Conduits in Wall 2 06-Oct-12 07-Oct-12 30-Dec-12 31-Dec-12 69 A73040 Install Cable Trays & Trunking 2 06-Oct-12 07-Oct-12 06-Jan-13 07-Jan-13 74 A73080 Cable Laying for Low Current System 2 08-Oct-12 09-Oct-12 20-Jan-13 21-Jan-13 84 A73090 Cable Laying for Power 3 08-Oct-12 10-Oct-12 19-Jan-13 21-Jan-13 83 A73050 Wiring for Lighting & Power 3 17-Nov-12 19-Nov-12 12-Jan-13 14-Jan-13 46 A73060 Wiring for Low Current System 4 17-Nov-12 20-Nov-12 10-Jan-13 14-Jan-13 45 A73070 DB installation,Dressing & Termination 7 29-Nov-12 08-Dec-12 28-Jan-13 04-Feb-13 48 A73120 Installation of Sockets 3 02-Jan-13 05-Jan-13 03-Mar-13 05-Mar-13 50 A73110 Installation of Lighting Fittings 5 02-Jan-13 07-Jan-13 28-Feb-13 05-Mar-13 48 PlumbingPlumbing 5 06-Oct-12 10-Oct-12 09-Jan-13 14-Jan-13 77 A73130 H/L Hot&Cold Water Pipe Installation 5 06-Oct-12 10-Oct-12 09-Jan-13 14-Jan-13 77 Fire FighFire Fighting 80 06-Oct-12 12-Jan-13 06-Jan-13 10-Apr-13 75 A73170 Fire Fighting Pipe 4 06-Oct-12 09-Oct-12 06-Jan-13 09-Jan-13 74 A73160 Hydro Static Test for Pipes 4 10-Oct-12 14-Oct-12 10-Jan-13 14-Jan-13 74 A73220 Fire Alarm Devices 4 02-Jan-13 06-Jan-13 19-Feb-13 23-Feb-13 40 A73150 Sprinkler Fixing 5 02-Jan-13 07-Jan-13 12-Feb-13 17-Feb-13 34 A73140 Installation of Fire Extingusher&Blanket 4 08-Jan-13 12-Jan-13 07-Apr-13 10-Apr-13 75 Electrical /Electrical /Meter/ Telephone Rooms 106 09-Oct-12 16-Feb-13 23-Jan-13 16-Apr-13 51 FinishingFinishing Works 106 09-Oct-12 16-Feb-13 23-Jan-13 16-Apr-13 51 Wet WorWet Works 65 09-Oct-12 27-Dec-12 23-Jan-13 04-Apr-13 82 A73280 Block Works 3 09-Oct-12 11-Oct-12 23-Jan-13 27-Jan-13 86 A73240 Installation of Doors& Windows Sub-frame 1 20-Nov-12 20-Nov-12 04-Apr-13 04-Apr-13 113 A73230 Plaster Works 4 20-Nov-12 24-Nov-12 30-Jan-13 03-Feb-13 58 A73250 1st Coat Paint 3 25-Dec-12 27-Dec-12 06-Feb-13 09-Feb-13 35 Fisrt StaFisrt Stage Finishes 18 23-Jan-13 13-Feb-13 02-Apr-13 14-Apr-13 51 A73340 Epoxy Paint Works 2 23-Jan-13 26-Jan-13 02-Apr-13 03-Apr-13 58 A73270 Installation of Doors 2 12-Feb-13 13-Feb-13 06-Apr-13 07-Apr-13 45 A73290 Doors Ironmongery 2 12-Feb-13 13-Feb-13 13-Apr-13 14-Apr-13 51 Second SSecond Stage Finishes 2 27-Jan-13 28-Jan-13 04-Apr-13 06-Apr-13 58 A73260 Final Coat Paint 2 27-Jan-13 28-Jan-13 04-Apr-13 06-Apr-13 58 Final StaFinal Stage Finishes 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51 A73330 Installation of Sinages 2 14-Feb-13 16-Feb-13 15-Apr-13 16-Apr-13 51 MEP WorkMEP Works 83 13-Oct-12 22-Jan-13 28-Jan-13 05-Mar-13 35 HVACHVAC 2 06-Jan-13 07-Jan-13 20-Feb-13 21-Feb-13 38 A73370 Air-Outlet Installation 2 06-Jan-13 07-Jan-13 20-Feb-13 21-Feb-13 38 ElectricalElectrical 83 13-Oct-12 22-Jan-13 28-Jan-13 05-Mar-13 35 A73300 Install Conduits in Wall 2 13-Oct-12 14-Oct-12 28-Jan-13 29-Jan-13 86 A73310 Wiring for Lighting & Power 2 25-Nov-12 26-Nov-12 04-Feb-13 05-Feb-13 58 A73360 Installation of SMDBs 7 29-Dec-12 06-Jan-13 13-Feb-13 20-Feb-13 38 A73320 Installation of Lighting Fittings 2 07-Jan-13 08-Jan-13 21-Feb-13 23-Feb-13 38 A114980 Installation of Telephone System 21 29-Dec-12 22-Jan-13 10-Feb-13 05-Mar-13 35 Fire FighFire Fighting 2 09-Jan-13 10-Jan-13 24-Feb-13 25-Feb-13 38 A73350 Fire Alarm Devices 2 09-Jan-13 10-Jan-13 24-Feb-13 25-Feb-13 38 PlantersPlanters 150 15-Aug-12 14-Feb-13 28-Nov-12 16-Apr-13 52 FinishingFinishing Works 150 15-Aug-12 14-Feb-13 28-Nov-12 16-Apr-13 52 A105040 Water Proof Membrane 12 15-Aug-12 30-Aug-12 28-Nov-12 12-Dec-12 85 A105050 Drainage Gravel 12 20-Oct-12 04-Nov-12 13-Dec-12 26-Dec-12 43 A105060 Geptextile Membrane 12 05-Nov-12 19-Nov-12 27-Dec-12 10-Jan-13 43 A105070 Sweet Soil 12 20-Nov-12 04-Dec-12 12-Jan-13 26-Jan-13 43 A107900 Installation of Lighitngs 30 05-Dec-12 09-Jan-13 13-Mar-13 16-Apr-13 82 A105080 Instllation of Planting Items 50 05-Dec-12 03-Feb-13 27-Jan-13 25-Mar-13 43 A107890 Installation of Irrigation System 60 05-Dec-12 14-Feb-13 27-Jan-13 06-Apr-13 43 StaircaseStaircase 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133 Stairs 1Stairs 1 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133 A111750 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133 A111790 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133 A111760 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111770 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111780 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133 A111800 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133 Stairs 2Stairs 2 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133 A111810 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133 A111850 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133 A111820 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111830 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111840 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133 A111860 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133 Stairs 3Stairs 3 43 06-Sep-12 28-Oct-12 16-Feb-13 06-Apr-13 133 A111870 Floor Screed 3 06-Sep-12 09-Sep-12 16-Feb-13 18-Feb-13 133 A111910 Install Handrails 4 10-Sep-12 13-Sep-12 19-Feb-13 23-Feb-13 133 A111880 Ceiling 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111890 Wall 1st Coat Paint 12 15-Sep-12 27-Sep-12 24-Feb-13 09-Mar-13 133 A111900 Install Granite/Terrazo 12 29-Sep-12 11-Oct-12 10-Mar-13 23-Mar-13 133 A111920 Final Coat Paint 12 13-Oct-12 28-Oct-12 24-Mar-13 06-Apr-13 133 ApartementsApartements 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26 One BedroOne Bedroom Flats 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31 ApartemeApartement .1 - 5 (1 BR) 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31 FinishingFinishing Works 147 15-Sep-12 11-Mar-13 04-Nov-12 16-Apr-13 31 Wet WoWet Works 76 15-Sep-12 16-Dec-12 04-Nov-12 27-Feb-13 61 A73530 Block Works 10 15-Sep-12 25-Sep-12 04-Nov-12 14-Nov-12 41 A73390 Installation of Doors& Windows Sub-frame 2 24-Oct-12 28-Oct-12 26-Feb-13 27-Feb-13 101 A73380 Plaster Works 10 24-Oct-12 06-Nov-12 26-Nov-12 08-Dec-12 25 A73860 Wall Tiles Work (Wet Area) 6 08-Nov-12 14-Nov-12 10-Jan-13 16-Jan-13 51 A73410 Installation of Suspended Ceiling Grid (Dry Area) 5 17-Nov-12 21-Nov-12 15-Dec-12 19-Dec-12 23 A73400 1st Coat Paint 11 04-Dec-12 16-Dec-12 20-Dec-12 02-Jan-13 14 Fisrt StaFisrt Stage Finishes 42 19-Dec-12 07-Feb-13 06-Jan-13 27-Feb-13 17 A73420 Suspended Ceiling Tiles (DryArea) 5 19-Dec-12 24-Dec-12 06-Jan-13 10-Jan-13 14 A73460 Installation of Wardrobes 5 26-Dec-12 31-Dec-12 12-Jan-13 16-Jan-13 13 A73850 Screed Works 7 06-Jan-13 13-Jan-13 17-Jan-13 26-Jan-13 10 A73450 Water Proofing for Wet Area 4 14-Jan-13 17-Jan-13 27-Jan-13 30-Jan-13 10 A73890 Installation of Suspended Ceiling Grid (Wet Area) 4 19-Jan-13 22-Jan-13 31-Jan-13 04-Feb-13 10 A73880 Suspended Ceiling Tiles (Wet Area) 5 23-Jan-13 29-Jan-13 05-Feb-13 10-Feb-13 10 A73440 Floor & Wall Tiles Work (Dry Area) 11 17-Jan-13 30-Jan-13 07-Feb-13 19-Feb-13 17 A73870 Floor Tiles Work (Wet Area) 7 31-Jan-13 07-Feb-13 20-Feb-13 27-Feb-13 17 SecondSecond Stage Finishes 18 09-Feb-13 28-Feb-13 28-Feb-13 28-Mar-13 24 A73470 Installation of Windows&Doors 3 09-Feb-13 11-Feb-13 28-Feb-13 03-Mar-13 17 A73540 Doors Ironmongery 3 09-Feb-13 11-Feb-13 26-Mar-13 28-Mar-13 39 A73510 Installation of Balustrades& Handrails 2 12-Feb-13 13-Feb-13 27-Mar-13 28-Mar-13 37 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Doors Ironmongery Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Fire Alarm Devices Sprinkler Fixing Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Epoxy Paint Works Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Water Proof Membrane Drainage Gravel Geptextile Membrane Sweet Soil Installation of Lighitngs Instllation of Planting Items Installation of Irrigation System Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor & Wall Tiles Work (Dry Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 88 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 89. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A73480 Installation of Mirrors 4 12-Feb-13 16-Feb-13 07-Mar-13 11-Mar-13 20 A73520 Installation of Vanity Counter 4 12-Feb-13 16-Feb-13 07-Mar-13 11-Mar-13 20 A73830 Installation of Toliets Accessories 5 12-Feb-13 17-Feb-13 04-Mar-13 09-Mar-13 17 A73490 Installation of Kitchen Cabinets 4 25-Feb-13 28-Feb-13 25-Mar-13 28-Mar-13 24 Final StFinal Stage Finishes 9 02-Mar-13 11-Mar-13 30-Mar-13 16-Apr-13 31 A73430 Final Coat Paint 7 02-Mar-13 09-Mar-13 30-Mar-13 06-Apr-13 24 A73840 Installation of Sinages 2 10-Mar-13 11-Mar-13 15-Apr-13 16-Apr-13 31 MEP WoMEP Works 116 26-Sep-12 14-Feb-13 17-Nov-12 06-Apr-13 43 HVACHVAC 105 26-Sep-12 02-Feb-13 24-Nov-12 25-Feb-13 20 A73580 Condensate Pipe Installation 12 26-Sep-12 09-Oct-12 24-Nov-12 08-Dec-12 47 A73560 Duct Installation & Insulation 12 13-Oct-12 28-Oct-12 24-Nov-12 08-Dec-12 33 A73570 Chilled Water Pipe Installation & Insulation 12 13-Oct-12 28-Oct-12 24-Nov-12 08-Dec-12 33 A73590 FCU Installation 5 29-Oct-12 03-Nov-12 09-Dec-12 13-Dec-12 33 A73600 Air-Outlet Installation 3 30-Jan-13 02-Feb-13 23-Feb-13 25-Feb-13 20 ElectricElectrical 106 26-Sep-12 03-Feb-13 17-Nov-12 05-Mar-13 26 A73610 Install Conduits in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41 A73620 Install Cable Trays & Trunking 8 26-Sep-12 04-Oct-12 26-Nov-12 05-Dec-12 49 A73660 Cable Laying for Low Current System 8 06-Oct-12 14-Oct-12 11-Dec-12 19-Dec-12 53 A73670 Cable Laying for Power 8 06-Oct-12 14-Oct-12 11-Dec-12 19-Dec-12 53 A73630 Wiring for Lighting & Power 5 07-Nov-12 12-Nov-12 09-Dec-12 13-Dec-12 25 A73640 Wiring for Low Current System 5 07-Nov-12 12-Nov-12 09-Dec-12 13-Dec-12 25 A73650 DB installation,Dressing & Termination 7 17-Dec-12 24-Dec-12 03-Jan-13 10-Jan-13 14 A73700 Installation of Sockets 3 30-Jan-13 02-Feb-13 03-Mar-13 05-Mar-13 27 A73690 Installation of Lighting Fittings 4 30-Jan-13 03-Feb-13 02-Mar-13 05-Mar-13 26 PlumbinPlumbing 116 26-Sep-12 14-Feb-13 17-Nov-12 28-Mar-13 36 A73710 Drainge Pipes in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41 A73780 Water Pipes in Wall 8 26-Sep-12 04-Oct-12 17-Nov-12 25-Nov-12 41 A73720 H/L Drainage Pipes Installation 12 26-Sep-12 09-Oct-12 12-Jan-13 26-Jan-13 87 A73730 H/L Hot&Cold Water Pipe Installation 12 26-Sep-12 09-Oct-12 12-Jan-13 26-Jan-13 87 A73740 Drainage&Water Pipes Testing 3 10-Oct-12 13-Oct-12 27-Jan-13 29-Jan-13 87 A73750 ElectricalWater Heater Installation 4 10-Oct-12 14-Oct-12 27-Jan-13 30-Jan-13 87 A73760 Floor Drain Fixning 2 08-Jan-13 09-Jan-13 23-Feb-13 24-Feb-13 38 A73770 Installation of Sanitaryware 3 12-Feb-13 14-Feb-13 26-Mar-13 28-Mar-13 36 Fire FigFire Fighting 108 27-Sep-12 06-Feb-13 29-Nov-12 06-Apr-13 50 A73820 Fire Fighting Pipe 7 27-Sep-12 04-Oct-12 29-Nov-12 08-Dec-12 51 A73810 Hydro Static Test for Pipes 5 06-Oct-12 10-Oct-12 09-Dec-12 13-Dec-12 51 A73800 Sprinkler Fixing 5 30-Jan-13 04-Feb-13 20-Feb-13 25-Feb-13 18 A73900 Fire Alarm Devices 5 30-Jan-13 04-Feb-13 28-Feb-13 05-Mar-13 25 A73790 Installation of Fire Extingusher&Blanket 2 05-Feb-13 06-Feb-13 04-Apr-13 06-Apr-13 50 Two BedroTwo Bedroom Flats 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34 ApartemeApartement .1 -11 (2 BR) 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34 FinishingFinishing Works 156 01-Sep-12 07-Mar-13 19-Sep-12 16-Apr-13 34 Wet WoWet Works 77 01-Sep-12 03-Dec-12 19-Sep-12 25-Feb-13 70 A74060 Block Works 12 01-Sep-12 13-Sep-12 19-Sep-12 02-Oct-12 16 A73920 Installation of Doors& Windows Sub-frame 6 04-Oct-12 10-Oct-12 19-Feb-13 25-Feb-13 112 A73910 Plaster Works 17 04-Oct-12 23-Oct-12 17-Oct-12 07-Nov-12 11 A74390 Wall Tiles Work (Wet Area) 11 24-Oct-12 07-Nov-12 25-Dec-12 07-Jan-13 49 A73940 Installation of Suspended Ceiling Grid (Dry Area) 7 07-Nov-12 14-Nov-12 21-Nov-12 28-Nov-12 11 A73930 1st Coat Paint 13 18-Nov-12 03-Dec-12 29-Nov-12 15-Dec-12 10 Fisrt StaFisrt Stage Finishes 54 06-Dec-12 09-Feb-13 18-Dec-12 26-Feb-13 15 A73950 Suspended Ceiling Tiles (DryArea) 10 06-Dec-12 17-Dec-12 18-Dec-12 29-Dec-12 10 A73990 Installation of Wardrobes 7 18-Dec-12 25-Dec-12 30-Dec-12 07-Jan-13 10 A74380 Screed Works 8 26-Dec-12 05-Jan-13 08-Jan-13 16-Jan-13 10 A73980 Water Proofing for Wet Area 8 06-Jan-13 14-Jan-13 29-Jan-13 06-Feb-13 19 A73970 Floor & Wall Tiles Work (Dry Area) 10 06-Jan-13 16-Jan-13 27-Jan-13 06-Feb-13 17 A74420 Installation of Suspended Ceiling Grid (Wet Area) 6 23-Jan-13 30-Jan-13 07-Feb-13 13-Feb-13 12 A74410 Suspended Ceiling Tiles (Wet Area) 5 30-Jan-13 04-Feb-13 11-Feb-13 16-Feb-13 10 A74400 Floor Tiles Work (Wet Area) 4 05-Feb-13 09-Feb-13 23-Feb-13 26-Feb-13 15 SecondSecond Stage Finishes 17 10-Feb-13 28-Feb-13 27-Feb-13 20-Mar-13 17 A74000 Installation of Windows&Doors 5 10-Feb-13 14-Feb-13 27-Feb-13 04-Mar-13 15 A74070 Doors Ironmongery 5 10-Feb-13 14-Feb-13 11-Mar-13 16-Mar-13 25 A74040 Installation of Balustrades& Handrails 5 16-Feb-13 20-Feb-13 11-Mar-13 16-Mar-13 20 A74020 Installation of Kitchen Cabinets 8 16-Feb-13 24-Feb-13 07-Mar-13 16-Mar-13 17 A74010 Installation of Mirrors 8 17-Feb-13 25-Feb-13 12-Mar-13 20-Mar-13 20 A74050 Installation of Vanity Counter 8 17-Feb-13 25-Feb-13 12-Mar-13 20-Mar-13 20 A74360 Installation of Toliets Accessories 10 18-Feb-13 28-Feb-13 10-Mar-13 20-Mar-13 17 Final StFinal Stage Finishes 8 27-Feb-13 07-Mar-13 17-Mar-13 16-Apr-13 34 A73960 Final Coat Paint 8 27-Feb-13 07-Mar-13 17-Mar-13 25-Mar-13 15 A74370 Installation of Sinages 2 06-Mar-13 07-Mar-13 15-Apr-13 16-Apr-13 34 MEP WoMEP Works 136 15-Sep-12 26-Feb-13 03-Oct-12 25-Mar-13 23 HVACHVAC 124 15-Sep-12 12-Feb-13 16-Oct-12 05-Mar-13 18 A74110 Condensate Pipe Installation 18 15-Sep-12 04-Oct-12 16-Oct-12 07-Nov-12 27 A74090 Duct Installation & Insulation 18 22-Sep-12 11-Oct-12 16-Oct-12 07-Nov-12 21 A74100 Chilled Water Pipe Installation & Insulation 18 22-Sep-12 11-Oct-12 16-Oct-12 07-Nov-12 21 A74120 FCU Installation 10 13-Oct-12 23-Oct-12 08-Nov-12 20-Nov-12 21 A74130 Air-Outlet Installation 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18 ElectricElectrical 132 15-Sep-12 21-Feb-13 03-Oct-12 05-Mar-13 10 A74140 Install Conduits in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16 A74150 Install Cable Trays & Trunking 12 15-Sep-12 27-Sep-12 21-Oct-12 05-Nov-12 31 A74190 Cable Laying for Low Current System 15 29-Sep-12 15-Oct-12 11-Nov-12 28-Nov-12 35 A74200 Cable Laying for Power 15 29-Sep-12 15-Oct-12 11-Nov-12 28-Nov-12 35 A74160 Wiring for Lighting & Power 10 24-Oct-12 06-Nov-12 08-Nov-12 20-Nov-12 11 A74170 Wiring for Low Current System 10 24-Oct-12 06-Nov-12 08-Nov-12 20-Nov-12 11 A74180 DB installation,Dressing & Termination 12 04-Dec-12 17-Dec-12 16-Dec-12 29-Dec-12 10 A74230 Installation of Sockets 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18 A74220 Installation of Lighting Fittings 15 05-Feb-13 21-Feb-13 17-Feb-13 05-Mar-13 10 PlumbinPlumbing 136 15-Sep-12 26-Feb-13 03-Oct-12 16-Mar-13 15 A74250 H/L Drainage Pipes Installation 11 15-Sep-12 26-Sep-12 05-Jan-13 16-Jan-13 91 A74260 H/L Hot&Cold Water Pipe Installation 11 15-Sep-12 26-Sep-12 05-Jan-13 16-Jan-13 91 A74240 Drainge Pipes in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16 A74310 Water Pipes in Wall 12 15-Sep-12 27-Sep-12 03-Oct-12 16-Oct-12 16 A74270 Drainage&Water Pipes Testing 7 27-Sep-12 04-Oct-12 17-Jan-13 26-Jan-13 91 A74280 ElectricalWater Heater Installation 7 27-Sep-12 04-Oct-12 17-Jan-13 26-Jan-13 91 A74290 Floor Drain Fixning 4 29-Dec-12 02-Jan-13 19-Feb-13 23-Feb-13 43 A74300 Installation of Sanitaryware 10 16-Feb-13 26-Feb-13 05-Mar-13 16-Mar-13 15 Fire FigFire Fighting 126 15-Sep-12 14-Feb-13 30-Oct-12 25-Mar-13 33 A74350 Fire Fighting Pipe 11 15-Sep-12 26-Sep-12 30-Oct-12 11-Nov-12 37 A74340 Hydro Static Test for Pipes 7 27-Sep-12 04-Oct-12 12-Nov-12 20-Nov-12 37 A74330 Sprinkler Fixing 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18 A74430 Fire Alarm Devices 7 05-Feb-13 12-Feb-13 06-Mar-13 13-Mar-13 25 A74320 Installation of Fire Extingusher&Blanket 2 13-Feb-13 14-Feb-13 24-Mar-13 25-Mar-13 33 Three BedrThree Bedroom Flats 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26 ApartemeApartement .1 -3 (3 BR) 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26 FinishingFinishing Works 176 15-Aug-12 17-Mar-13 29-Aug-12 16-Apr-13 26 Wet WoWet Works 76 15-Aug-12 17-Nov-12 29-Aug-12 18-Feb-13 77 A74590 Block Works 12 15-Aug-12 30-Aug-12 29-Aug-12 11-Sep-12 10 A74450 Installation of Doors& Windows Sub-frame 6 15-Sep-12 20-Sep-12 12-Feb-13 18-Feb-13 123 A74440 Plaster Works 17 15-Sep-12 03-Oct-12 26-Sep-12 15-Oct-12 10 A74920 Wall Tiles Work (Wet Area) 11 04-Oct-12 16-Oct-12 12-Dec-12 24-Dec-12 55 A74470 Installation of Suspended Ceiling Grid (Dry Area) 7 18-Oct-12 28-Oct-12 01-Nov-12 08-Nov-12 10 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Installation of Kitchen Cabinets Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing ElectricalWater Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Kitchen Cabinets Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Sinages Condensate Pipe Installation Duct Installation & Insulation Chilled Water Pipe Installation & Insulation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 89 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 90. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A74460 1st Coat Paint 16 29-Oct-12 17-Nov-12 10-Nov-12 28-Nov-12 10 Fisrt StaFisrt Stage Finishes 45 18-Nov-12 10-Jan-13 06-Dec-12 19-Feb-13 33 A74480 Suspended Ceiling Tiles (DryArea) 10 18-Nov-12 28-Nov-12 06-Dec-12 17-Dec-12 15 A74520 Installation of Wardrobes 7 29-Nov-12 08-Dec-12 20-Dec-12 27-Dec-12 17 A74910 Screed Works 8 09-Dec-12 17-Dec-12 29-Dec-12 07-Jan-13 17 A74510 Water Proofing for Wet Area 8 18-Dec-12 26-Dec-12 28-Jan-13 05-Feb-13 33 A74500 Floor & Wall Tiles Work (Dry Area) 10 18-Dec-12 29-Dec-12 14-Jan-13 26-Jan-13 22 A74950 Installation of Suspended Ceiling Grid (Wet Area) 6 27-Dec-12 03-Jan-13 06-Feb-13 12-Feb-13 33 A74940 Suspended Ceiling Tiles (Wet Area) 5 31-Dec-12 06-Jan-13 10-Feb-13 14-Feb-13 33 A74930 Floor Tiles Work (Wet Area) 4 07-Jan-13 10-Jan-13 16-Feb-13 19-Feb-13 33 SecondSecond Stage Finishes 51 12-Jan-13 12-Mar-13 20-Feb-13 01-Apr-13 17 A74530 Installation of Windows&Doors 5 12-Jan-13 16-Jan-13 20-Feb-13 25-Feb-13 33 A74600 Doors Ironmongery 5 12-Jan-13 16-Jan-13 20-Mar-13 25-Mar-13 57 A74570 Installation of Balustrades& Handrails 5 17-Jan-13 22-Jan-13 20-Mar-13 25-Mar-13 52 A74550 Installation of Kitchen Cabinets 8 17-Jan-13 27-Jan-13 26-Feb-13 06-Mar-13 33 A74540 Installation of Mirrors 8 26-Feb-13 06-Mar-13 21-Mar-13 30-Mar-13 20 A74580 Installation of Vanity Counter 8 26-Feb-13 06-Mar-13 21-Mar-13 30-Mar-13 20 A74890 Installation of Toliets Accessories 10 02-Mar-13 12-Mar-13 21-Mar-13 01-Apr-13 17 Final StFinal Stage Finishes 8 09-Mar-13 17-Mar-13 26-Mar-13 16-Apr-13 26 A74490 Final Coat Paint 8 09-Mar-13 17-Mar-13 26-Mar-13 03-Apr-13 15 A74900 Installation of Sinages 3 14-Mar-13 17-Mar-13 14-Apr-13 16-Apr-13 26 MEP WoMEP Works 152 25-Aug-12 24-Feb-13 12-Sep-12 03-Apr-13 33 HVACHVAC 115 01-Sep-12 17-Jan-13 24-Sep-12 05-Mar-13 39 A74620 Duct Installation & Insulation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20 A74630 Chilled Water Pipe Installation & Insulation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20 A74640 Condensate Pipe Installation 18 01-Sep-12 20-Sep-12 24-Sep-12 14-Oct-12 20 A74650 FCU Installation 13 22-Sep-12 06-Oct-12 15-Oct-12 31-Oct-12 20 A74660 Air-Outlet Installation 10 07-Jan-13 17-Jan-13 23-Feb-13 05-Mar-13 39 ElectricElectrical 123 25-Aug-12 20-Jan-13 12-Sep-12 05-Mar-13 37 A74670 Install Conduits in Wall 12 25-Aug-12 06-Sep-12 12-Sep-12 25-Sep-12 16 A74680 Install Cable Trays & Trunking 12 01-Sep-12 13-Sep-12 30-Sep-12 13-Oct-12 25 A74720 Cable Laying for Low Current System 15 15-Sep-12 01-Oct-12 21-Oct-12 08-Nov-12 31 A74730 Cable Laying for Power 15 15-Sep-12 01-Oct-12 21-Oct-12 08-Nov-12 31 A74690 Wiring for Lighting & Power 12 04-Oct-12 17-Oct-12 16-Oct-12 31-Oct-12 10 A74700 Wiring for Low Current System 12 04-Oct-12 17-Oct-12 16-Oct-12 31-Oct-12 10 A74710 DB installation,Dressing & Termination 10 18-Nov-12 28-Nov-12 06-Dec-12 17-Dec-12 15 A74760 Installation of Sockets 7 07-Jan-13 14-Jan-13 26-Feb-13 05-Mar-13 42 A74750 Installation of Lighting Fittings 12 07-Jan-13 20-Jan-13 20-Feb-13 05-Mar-13 37 PlumbinPlumbing 126 01-Sep-12 31-Jan-13 12-Sep-12 25-Mar-13 45 A74780 H/L Drainage Pipes Installation 11 01-Sep-12 12-Sep-12 23-Dec-12 05-Jan-13 93 A74790 H/L Hot&Cold Water Pipe Installation 11 01-Sep-12 12-Sep-12 23-Dec-12 05-Jan-13 93 A74770 Drainge Pipes in Wall 12 01-Sep-12 13-Sep-12 12-Sep-12 25-Sep-12 10 A74840 Water Pipes in Wall 12 01-Sep-12 13-Sep-12 12-Sep-12 25-Sep-12 10 A74800 Drainage&Water Pipes Testing 7 13-Sep-12 20-Sep-12 06-Jan-13 13-Jan-13 93 A74810 ElectricalWater Heater Installation 10 13-Sep-12 24-Sep-12 06-Jan-13 16-Jan-13 93 A74820 Floor Drain Fixning 8 11-Dec-12 19-Dec-12 07-Feb-13 16-Feb-13 48 A74830 Installation of Sanitaryware 12 17-Jan-13 31-Jan-13 12-Mar-13 25-Mar-13 45 Fire FigFire Fighting 146 01-Sep-12 24-Feb-13 09-Oct-12 03-Apr-13 33 A74880 Fire Fighting Pipe 11 01-Sep-12 12-Sep-12 09-Oct-12 21-Oct-12 33 A74870 Hydro Static Test for Pipes 7 13-Sep-12 20-Sep-12 22-Oct-12 31-Oct-12 33 A74860 Sprinkler Fixing 10 07-Jan-13 17-Jan-13 23-Feb-13 05-Mar-13 39 A74850 Installation of Fire Extingusher&Blanket 2 19-Jan-13 20-Jan-13 02-Apr-13 03-Apr-13 62 A74960 Fire Alarm Devices 10 13-Feb-13 24-Feb-13 14-Mar-13 25-Mar-13 25 2nd Floor2nd Floor 174 30-Aug-12 27-Mar-13 12-Sep-12 16-Apr-13 17 Public AreaPublic Area 156 20-Sep-12 27-Mar-13 26-Dec-12 16-Apr-13 17 Garbage RGarbage Room 102 24-Oct-12 26-Feb-13 15-Jan-13 16-Apr-13 42 FinishingFinishing Works 102 24-Oct-12 26-Feb-13 15-Jan-13 16-Apr-13 42 Wet WorWet Works 72 24-Oct-12 21-Jan-13 15-Jan-13 09-Mar-13 39 A76620 Block Works 3 24-Oct-12 29-Oct-12 15-Jan-13 17-Jan-13 66 A76560 Plaster Works 3 10-Dec-12 12-Dec-12 23-Jan-13 27-Jan-13 37 A76570 Installation of Doors& Windows Sub-frame 1 15-Dec-12 15-Dec-12 09-Mar-13 09-Mar-13 70 A76600 Wall Tiles Work 4 16-Dec-12 19-Dec-12 30-Jan-13 03-Feb-13 37 A76580 1st Coat Paint 2 20-Jan-13 21-Jan-13 04-Feb-13 05-Feb-13 12 Fisrt StaFisrt Stage Finishes 7 11-Feb-13 18-Feb-13 26-Feb-13 14-Apr-13 47 A76750 Screed Works 2 11-Feb-13 12-Feb-13 26-Feb-13 27-Feb-13 13 A76770 Floor Tiles Work 2 14-Feb-13 16-Feb-13 02-Mar-13 03-Mar-13 13 A76610 Installation of Doors 2 17-Feb-13 18-Feb-13 10-Mar-13 11-Mar-13 18 A76630 Doors Ironmongery 2 17-Feb-13 18-Feb-13 13-Apr-13 14-Apr-13 47 Second SSecond Stage Finishes 2 25-Feb-13 26-Feb-13 04-Apr-13 06-Apr-13 33 A76590 Final Coat Paint 2 25-Feb-13 26-Feb-13 04-Apr-13 06-Apr-13 33 Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42 A76740 Installation of Sinages 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42 MEP WorkMEP Works 92 30-Oct-12 18-Feb-13 19-Jan-13 14-Mar-13 21 ElectricalElectrical 90 01-Nov-12 18-Feb-13 21-Jan-13 05-Mar-13 13 A76640 Install Conduits in Wall 2 01-Nov-12 03-Nov-12 21-Jan-13 22-Jan-13 66 A76650 Wiring for Lighting & Power 2 13-Dec-12 15-Dec-12 28-Jan-13 29-Jan-13 37 A76660 Installation of Lighting Fittings 2 17-Feb-13 18-Feb-13 04-Mar-13 05-Mar-13 13 PlumbingPlumbing 88 30-Oct-12 13-Feb-13 19-Jan-13 28-Feb-13 13 A76670 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 19-Jan-13 20-Jan-13 66 A76700 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 19-Jan-13 20-Jan-13 66 A76680 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 21-Jan-13 22-Jan-13 66 A76690 Floor Drain Fixning 1 13-Feb-13 13-Feb-13 28-Feb-13 28-Feb-13 13 Fire FighFire Fighting 90 01-Nov-12 18-Feb-13 27-Feb-13 14-Mar-13 21 A76730 Fire Fighting Pipe 2 01-Nov-12 03-Nov-12 27-Feb-13 28-Feb-13 97 A76720 Hydro Static Test for Pipes 2 04-Nov-12 05-Nov-12 02-Mar-13 03-Mar-13 97 A76710 Sprinkler Fixing 2 17-Feb-13 18-Feb-13 04-Mar-13 05-Mar-13 13 A76760 Fire Alarm Devices 2 17-Feb-13 18-Feb-13 13-Mar-13 14-Mar-13 21 Corridor &Corridor & Lift Lobby 135 15-Oct-12 27-Mar-13 26-Dec-12 16-Apr-13 17 FinishingFinishing Works 135 15-Oct-12 27-Mar-13 26-Dec-12 16-Apr-13 17 Wet WorWet Works 86 15-Oct-12 29-Jan-13 26-Dec-12 21-Feb-13 20 A76830 Block Works 8 15-Oct-12 23-Oct-12 26-Dec-12 05-Jan-13 58 A76780 Plaster Works 7 01-Dec-12 09-Dec-12 08-Jan-13 15-Jan-13 31 A76800 Installation of Suspended Ceiling Grid 6 15-Dec-12 20-Dec-12 21-Jan-13 28-Jan-13 31 A76790 1st Coat Paint 5 14-Jan-13 19-Jan-13 29-Jan-13 03-Feb-13 12 A76810 Suspended Ceiling Tiles 6 22-Jan-13 29-Jan-13 16-Feb-13 21-Feb-13 20 Fisrt StaFisrt Stage Finishes 38 07-Feb-13 23-Mar-13 23-Feb-13 11-Apr-13 17 A77060 Screed Works 3 07-Feb-13 10-Feb-13 23-Feb-13 25-Feb-13 13 A77080 Floor Tiles Work 5 18-Mar-13 23-Mar-13 07-Apr-13 11-Apr-13 17 Second SSecond Stage Finishes 6 21-Mar-13 27-Mar-13 10-Apr-13 16-Apr-13 17 A76820 Installation of Doors 3 21-Mar-13 24-Mar-13 10-Apr-13 13-Apr-13 17 A76840 Doors Ironmongery 3 21-Mar-13 24-Mar-13 10-Apr-13 13-Apr-13 17 A77090 Final Coat Paint 5 23-Mar-13 27-Mar-13 11-Apr-13 16-Apr-13 17 Final StaFinal Stage Finishes 3 25-Mar-13 27-Mar-13 14-Apr-13 16-Apr-13 17 A77050 Installation of Sinages 3 25-Mar-13 27-Mar-13 14-Apr-13 16-Apr-13 17 MEP WorkMEP Works 86 24-Oct-12 07-Feb-13 06-Jan-13 10-Apr-13 53 HVACHVAC 81 24-Oct-12 02-Feb-13 12-Jan-13 27-Feb-13 22 A76850 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63 A76860 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63 A76870 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 12-Jan-13 16-Jan-13 63 A76880 FCU Installation 3 01-Nov-12 04-Nov-12 17-Jan-13 20-Jan-13 63 A76890 Air-Outlet Installation 3 30-Jan-13 02-Feb-13 25-Feb-13 27-Feb-13 22 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Kitchen Cabinets Installation of Mirrors Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Plaster Works Installation of Doors& Windows Sub-frame Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 90 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 91. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float ElectricalElectrical 83 24-Oct-12 04-Feb-13 06-Jan-13 02-Mar-13 22 A76910 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 12-Jan-13 13-Jan-13 63 A76950 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 27-Jan-13 28-Jan-13 73 A76900 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 06-Jan-13 07-Jan-13 55 A76960 Cable Laying for Power 3 29-Oct-12 31-Oct-12 26-Jan-13 28-Jan-13 72 A76920 Wiring for Lighting & Power 3 10-Dec-12 12-Dec-12 17-Jan-13 20-Jan-13 32 A76930 Wiring for Low Current System 4 10-Dec-12 13-Dec-12 16-Jan-13 20-Jan-13 31 A76940 DB installation,Dressing & Termination 7 22-Dec-12 29-Dec-12 14-Feb-13 21-Feb-13 45 A76990 Installation of Sockets 3 30-Jan-13 02-Feb-13 27-Feb-13 02-Mar-13 24 A76980 Installation of Lighting Fittings 5 30-Jan-13 04-Feb-13 24-Feb-13 28-Feb-13 21 PlumbingPlumbing 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66 A77000 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66 Fire FighFire Fighting 85 28-Oct-12 07-Feb-13 12-Jan-13 10-Apr-13 53 A77040 Fire Fighting Pipe 4 28-Oct-12 31-Oct-12 12-Jan-13 15-Jan-13 62 A77030 Hydro Static Test for Pipes 4 01-Nov-12 05-Nov-12 16-Jan-13 20-Jan-13 62 A77020 Sprinkler Fixing 4 30-Jan-13 03-Feb-13 27-Feb-13 03-Mar-13 24 A77070 Fire Alarm Devices 5 30-Jan-13 04-Feb-13 05-Mar-13 10-Mar-13 29 A77010 Installation of Fire Extingusher&Blanket 4 04-Feb-13 07-Feb-13 07-Apr-13 10-Apr-13 53 Electrical /Electrical /Meter/ Telephone Rooms 99 30-Oct-12 26-Feb-13 23-Jan-13 16-Apr-13 42 FinishingFinishing Works 99 30-Oct-12 26-Feb-13 23-Jan-13 16-Apr-13 42 Wet WorWet Works 72 30-Oct-12 26-Jan-13 23-Jan-13 06-Mar-13 34 A77150 Block Works 3 30-Oct-12 01-Nov-12 23-Jan-13 27-Jan-13 70 A77110 Installation of Doors& Windows Sub-frame 1 13-Dec-12 13-Dec-12 06-Mar-13 06-Mar-13 69 A77100 Plaster Works 4 13-Dec-12 17-Dec-12 30-Jan-13 03-Feb-13 39 A77120 1st Coat Paint 3 22-Jan-13 26-Jan-13 06-Feb-13 09-Feb-13 12 Fisrt StaFisrt Stage Finishes 58 15-Dec-12 21-Feb-13 07-Mar-13 14-Apr-13 44 A77140 Installation of Doors 2 15-Dec-12 16-Dec-12 07-Mar-13 09-Mar-13 69 A77160 Doors Ironmongery 2 15-Dec-12 16-Dec-12 13-Apr-13 14-Apr-13 100 A77210 Epoxy Paint Works 2 20-Feb-13 21-Feb-13 31-Mar-13 01-Apr-13 33 Second SSecond Stage Finishes 2 23-Feb-13 24-Feb-13 02-Apr-13 03-Apr-13 33 A77130 Final Coat Paint 2 23-Feb-13 24-Feb-13 02-Apr-13 03-Apr-13 33 Final StaFinal Stage Finishes 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42 A77200 Installation of Sinages 2 25-Feb-13 26-Feb-13 15-Apr-13 16-Apr-13 42 MEP WorkMEP Works 89 04-Nov-12 19-Feb-13 28-Jan-13 12-Mar-13 18 HVACHVAC 2 03-Feb-13 04-Feb-13 28-Feb-13 02-Mar-13 22 A77240 Air-Outlet Installation 2 03-Feb-13 04-Feb-13 28-Feb-13 02-Mar-13 22 ElectricalElectrical 89 04-Nov-12 19-Feb-13 28-Jan-13 05-Mar-13 12 A77170 Install Conduits in Wall 2 04-Nov-12 05-Nov-12 28-Jan-13 29-Jan-13 69 A77180 Wiring for Lighting & Power 2 18-Dec-12 19-Dec-12 04-Feb-13 05-Feb-13 39 A77230 Installation of SMDBs 7 27-Jan-13 03-Feb-13 21-Feb-13 28-Feb-13 22 A77190 Installation of Lighting Fittings 2 05-Feb-13 06-Feb-13 02-Mar-13 03-Mar-13 21 A114990 Installation of Telephone System 21 27-Jan-13 19-Feb-13 10-Feb-13 05-Mar-13 12 Fire FighFire Fighting 2 07-Feb-13 09-Feb-13 11-Mar-13 12-Mar-13 27 A77220 Fire Alarm Devices 2 07-Feb-13 09-Feb-13 11-Mar-13 12-Mar-13 27 StaircaseStaircase 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121 Stairs 1Stairs 1 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121 A111930 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121 A111970 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121 A111940 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A111950 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A111960 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121 A111980 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121 Stairs 2Stairs 2 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121 A111990 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121 A112030 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121 A112000 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A112010 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A112020 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121 A112040 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121 Stairs 3Stairs 3 43 20-Sep-12 11-Nov-12 16-Feb-13 06-Apr-13 121 A112050 Floor Screed 3 20-Sep-12 23-Sep-12 16-Feb-13 18-Feb-13 121 A112090 Install Handrails 4 24-Sep-12 27-Sep-12 19-Feb-13 23-Feb-13 121 A112060 Ceiling 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A112070 Wall 1st Coat Paint 12 29-Sep-12 11-Oct-12 24-Feb-13 09-Mar-13 121 A112080 Install Granite/Terrazo 12 13-Oct-12 28-Oct-12 10-Mar-13 23-Mar-13 121 A112100 Final Coat Paint 12 29-Oct-12 11-Nov-12 24-Mar-13 06-Apr-13 121 ApartementsApartements 165 30-Aug-12 17-Mar-13 12-Sep-12 16-Apr-13 26 One BedroOne Bedroom Flats 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36 ApartemeApartement .1- 5 (1 BR) 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36 FinishingFinishing Works 125 04-Oct-12 05-Mar-13 28-Nov-12 16-Apr-13 36 Wet WoWet Works 82 04-Oct-12 13-Jan-13 28-Nov-12 05-Mar-13 43 A75120 Block Works 9 04-Oct-12 14-Oct-12 28-Nov-12 09-Dec-12 44 A74980 Installation of Doors& Windows Sub-frame 2 14-Nov-12 17-Nov-12 04-Mar-13 05-Mar-13 90 A74970 Plaster Works 13 14-Nov-12 29-Nov-12 19-Dec-12 03-Jan-13 28 A75450 Wall Tiles Work (Wet Area) 4 01-Dec-12 05-Dec-12 06-Feb-13 10-Feb-13 55 A75000 Installation of Suspended Ceiling Grid (Dry Area) 4 08-Dec-12 11-Dec-12 10-Jan-13 14-Jan-13 28 A74990 1st Coat Paint 11 31-Dec-12 13-Jan-13 15-Jan-13 28-Jan-13 12 Fisrt StaFisrt Stage Finishes 28 17-Jan-13 19-Feb-13 02-Feb-13 20-Mar-13 25 A75010 Suspended Ceiling Tiles (DryArea) 4 17-Jan-13 21-Jan-13 02-Feb-13 05-Feb-13 12 A75050 Installation of Wardrobes 4 22-Jan-13 27-Jan-13 06-Feb-13 10-Feb-13 12 A75040 Water Proofing for Wet Area 3 03-Feb-13 05-Feb-13 17-Feb-13 19-Feb-13 12 A75440 Screed Works 9 28-Jan-13 06-Feb-13 11-Feb-13 20-Feb-13 12 A75480 Installation of Suspended Ceiling Grid (Wet Area) 4 05-Feb-13 09-Feb-13 19-Feb-13 23-Feb-13 12 A75030 Floor & Wall Tiles Work (Dry Area) 4 07-Feb-13 11-Feb-13 17-Mar-13 20-Mar-13 32 A75470 Suspended Ceiling Tiles (Wet Area) 4 10-Feb-13 13-Feb-13 24-Feb-13 27-Feb-13 12 A75460 Floor Tiles Work (Wet Area) 5 14-Feb-13 19-Feb-13 06-Mar-13 11-Mar-13 17 SecondSecond Stage Finishes 7 20-Feb-13 27-Feb-13 12-Mar-13 20-Mar-13 18 A75060 Installation of Windows&Doors 3 20-Feb-13 23-Feb-13 12-Mar-13 14-Mar-13 17 A75130 Doors Ironmongery 3 20-Feb-13 23-Feb-13 18-Mar-13 20-Mar-13 22 A75100 Installation of Balustrades& Handrails 2 24-Feb-13 25-Feb-13 19-Mar-13 20-Mar-13 20 A75070 Installation of Mirrors 3 24-Feb-13 26-Feb-13 17-Mar-13 19-Mar-13 18 A75080 Installation of Kitchen Cabinets 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19 A75110 Installation of Vanity Counter 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19 A75420 Installation of Toliets Accessories 4 24-Feb-13 27-Feb-13 16-Mar-13 19-Mar-13 17 Final StFinal Stage Finishes 5 28-Feb-13 05-Mar-13 21-Mar-13 16-Apr-13 36 A75020 Final Coat Paint 5 28-Feb-13 05-Mar-13 21-Mar-13 26-Mar-13 18 A75430 Installation of Sinages 2 04-Mar-13 05-Mar-13 15-Apr-13 16-Apr-13 36 MEP WoMEP Works 110 15-Oct-12 26-Feb-13 10-Dec-12 26-Mar-13 24 HVACHVAC 102 15-Oct-12 17-Feb-13 20-Dec-12 05-Mar-13 14 A75150 Duct Installation & Insulation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53 A75160 Chilled Water Pipe Installation & Insulation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53 A75170 Condensate Pipe Installation 12 15-Oct-12 30-Oct-12 20-Dec-12 03-Jan-13 53 A75180 FCU Installation 5 31-Oct-12 05-Nov-12 05-Jan-13 09-Jan-13 53 A75190 Air-Outlet Installation 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14 ElectricElectrical 103 15-Oct-12 18-Feb-13 10-Dec-12 05-Mar-13 13 A75210 Install Cable Trays & Trunking 8 15-Oct-12 23-Oct-12 23-Dec-12 31-Dec-12 55 A75200 Install Conduits in Wall 8 18-Oct-12 29-Oct-12 10-Dec-12 18-Dec-12 41 A75250 Cable Laying for Low Current System 8 24-Oct-12 04-Nov-12 06-Jan-13 14-Jan-13 58 A75260 Cable Laying for Power 8 24-Oct-12 04-Nov-12 06-Jan-13 14-Jan-13 58 A75220 Wiring for Lighting & Power 5 01-Dec-12 06-Dec-12 05-Jan-13 09-Jan-13 28 A75230 Wiring for Low Current System 5 01-Dec-12 06-Dec-12 05-Jan-13 09-Jan-13 28 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Install Cable Trays & Trunking Cable Laying for Low Current System Install Conduits in Wall Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Block Works Installation of Doors& Windows Sub-frame Plaster Works 1st Coat Paint Installation of Doors Doors Ironmongery Epoxy Paint Works Final Coat Paint Installation of Sinages Air-Outlet Installation Install Conduits in Wall Wiring for Lighting & Power Installation of SMDBs Installation of Lighting Fittings Installation of Telephone System Fire Alarm Devices Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Floor Screed Install Handrails Ceiling 1st Coat Paint Wall 1st Coat Paint Install Granite/Terrazo Final Coat Paint Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Water Proofing for Wet Area Screed Works Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Suspended Ceiling Tiles (Wet Area) Floor Tiles Work (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Kitchen Cabinets Installation of Vanity Counter Installation of Toliets Accessories Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Cable Trays & Trunking Install Conduits in Wall Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 91 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 92. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A75240 DB installation,Dressing & Termination 7 14-Jan-13 21-Jan-13 29-Jan-13 05-Feb-13 12 A75290 Installation of Sockets 3 14-Feb-13 17-Feb-13 03-Mar-13 05-Mar-13 14 A75280 Installation of Lighting Fittings 4 14-Feb-13 18-Feb-13 02-Mar-13 05-Mar-13 13 PlumbinPlumbing 110 15-Oct-12 26-Feb-13 10-Dec-12 20-Mar-13 19 A75300 Drainge Pipes in Wall 8 15-Oct-12 23-Oct-12 10-Dec-12 18-Dec-12 44 A75370 Water Pipes in Wall 8 15-Oct-12 23-Oct-12 10-Dec-12 18-Dec-12 44 A75310 H/L Drainage Pipes Installation 12 15-Oct-12 30-Oct-12 31-Jan-13 13-Feb-13 87 A75320 H/L Hot&Cold Water Pipe Installation 12 15-Oct-12 30-Oct-12 31-Jan-13 13-Feb-13 87 A75330 Drainage&Water Pipes Testing 3 31-Oct-12 03-Nov-12 14-Feb-13 17-Feb-13 87 A75340 ElectricalWater Heater Installation 4 31-Oct-12 04-Nov-12 14-Feb-13 18-Feb-13 87 A75350 Floor Drain Fixning 2 30-Jan-13 31-Jan-13 04-Mar-13 05-Mar-13 28 A75360 Installation of Sanitaryware 3 24-Feb-13 26-Feb-13 18-Mar-13 20-Mar-13 19 Fire FigFire Fighting 106 17-Oct-12 24-Feb-13 26-Dec-12 26-Mar-13 26 A75410 Fire Fighting Pipe 7 17-Oct-12 24-Oct-12 26-Dec-12 03-Jan-13 56 A75400 Hydro Static Test for Pipes 5 28-Oct-12 01-Nov-12 05-Jan-13 09-Jan-13 56 A75390 Sprinkler Fixing 5 14-Feb-13 19-Feb-13 28-Feb-13 05-Mar-13 12 A75380 Installation of Fire Extingusher&Blanket 2 20-Feb-13 21-Feb-13 25-Mar-13 26-Mar-13 28 A75490 Fire Alarm Devices 5 19-Feb-13 24-Feb-13 16-Mar-13 20-Mar-13 21 Two BedroTwo Bedroom Flats 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26 ApartemeApartement .1 - 10 (2 BR) 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26 FinishingFinishing Works 150 17-Sep-12 17-Mar-13 07-Oct-12 16-Apr-13 26 Wet WoWet Works 86 17-Sep-12 30-Dec-12 07-Oct-12 03-Mar-13 52 A75650 Block Works 15 17-Sep-12 03-Oct-12 07-Oct-12 23-Oct-12 17 A75510 Installation of Doors& Windows Sub-frame 7 22-Oct-12 31-Oct-12 24-Feb-13 03-Mar-13 101 A75500 Plaster Works 18 22-Oct-12 13-Nov-12 10-Nov-12 01-Dec-12 14 A75980 Wall Tiles Work (Wet Area) 13 14-Nov-12 29-Nov-12 12-Jan-13 27-Jan-13 47 A75530 Installation of Suspended Ceiling Grid (Dry Area) 8 27-Nov-12 06-Dec-12 15-Dec-12 23-Dec-12 14 A75520 1st Coat Paint 18 10-Dec-12 30-Dec-12 24-Dec-12 14-Jan-13 12 Fisrt StaFisrt Stage Finishes 35 31-Dec-12 11-Feb-13 15-Jan-13 26-Mar-13 37 A75540 Suspended Ceiling Tiles (DryArea) 12 31-Dec-12 14-Jan-13 15-Jan-13 29-Jan-13 12 A75580 Installation of Wardrobes 8 08-Jan-13 16-Jan-13 22-Jan-13 31-Jan-13 12 A75970 Screed Works 9 14-Jan-13 23-Jan-13 28-Jan-13 06-Feb-13 11 A75570 Water Proofing for Wet Area 9 20-Jan-13 30-Jan-13 03-Feb-13 12-Feb-13 11 A76010 Installation of Suspended Ceiling Grid (Wet Area) 7 27-Jan-13 03-Feb-13 09-Feb-13 16-Feb-13 11 A75560 Floor & Wall Tiles Work (Dry Area) 12 26-Jan-13 07-Feb-13 13-Mar-13 26-Mar-13 40 A75990 Floor Tiles Work (Wet Area) 5 06-Feb-13 11-Feb-13 10-Mar-13 14-Mar-13 27 A76000 Suspended Ceiling Tiles (Wet Area) 10 31-Jan-13 11-Feb-13 13-Feb-13 24-Feb-13 11 SecondSecond Stage Finishes 28 10-Feb-13 13-Mar-13 13-Mar-13 02-Apr-13 17 A75590 Installation of Windows&Doors 7 10-Feb-13 17-Feb-13 13-Mar-13 20-Mar-13 27 A75660 Doors Ironmongery 8 10-Feb-13 18-Feb-13 18-Mar-13 26-Mar-13 31 A75630 Installation of Balustrades& Handrails 5 18-Feb-13 23-Feb-13 21-Mar-13 26-Mar-13 27 A75600 Installation of Mirrors 9 27-Feb-13 09-Mar-13 20-Mar-13 30-Mar-13 18 A75640 Installation of Vanity Counter 9 27-Feb-13 09-Mar-13 23-Mar-13 01-Apr-13 20 A75610 Installation of Kitchen Cabinets 10 27-Feb-13 10-Mar-13 23-Mar-13 02-Apr-13 20 A75950 Installation of Toliets Accessories 12 28-Feb-13 13-Mar-13 20-Mar-13 02-Apr-13 17 Final StFinal Stage Finishes 9 07-Mar-13 17-Mar-13 27-Mar-13 16-Apr-13 26 A75550 Final Coat Paint 9 07-Mar-13 17-Mar-13 27-Mar-13 06-Apr-13 17 A75960 Installation of Sinages 7 10-Mar-13 17-Mar-13 09-Apr-13 16-Apr-13 26 MEP WoMEP Works 114 04-Oct-12 20-Feb-13 24-Oct-12 06-Apr-13 38 HVACHVAC 107 04-Oct-12 12-Feb-13 10-Nov-12 05-Mar-13 18 A75680 Duct Installation & Insulation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29 A75690 Chilled Water Pipe Installation & Insulation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29 A75700 Condensate Pipe Installation 18 04-Oct-12 24-Oct-12 10-Nov-12 01-Dec-12 29 A75710 FCU Installation 10 28-Oct-12 07-Nov-12 03-Dec-12 13-Dec-12 29 A75720 Air-Outlet Installation 7 05-Feb-13 12-Feb-13 26-Feb-13 05-Mar-13 18 ElectricElectrical 114 04-Oct-12 20-Feb-13 24-Oct-12 05-Mar-13 11 A75730 Install Conduits in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17 A75740 Install Cable Trays & Trunking 12 04-Oct-12 17-Oct-12 14-Nov-12 28-Nov-12 33 A75780 Cable Laying for Low Current System 15 18-Oct-12 06-Nov-12 06-Dec-12 23-Dec-12 38 A75790 Cable Laying for Power 15 18-Oct-12 06-Nov-12 06-Dec-12 23-Dec-12 38 A75750 Wiring for Lighting & Power 10 14-Nov-12 26-Nov-12 03-Dec-12 13-Dec-12 14 A75760 Wiring for Low Current System 10 14-Nov-12 26-Nov-12 03-Dec-12 13-Dec-12 14 A75770 DB installation,Dressing & Termination 12 31-Dec-12 14-Jan-13 15-Jan-13 29-Jan-13 12 A75820 Installation of Sockets 3 12-Feb-13 14-Feb-13 03-Mar-13 05-Mar-13 16 A75810 Installation of Lighting Fittings 13 06-Feb-13 20-Feb-13 19-Feb-13 05-Mar-13 11 PlumbinPlumbing 114 04-Oct-12 20-Feb-13 24-Oct-12 26-Mar-13 29 A75840 H/L Drainage Pipes Installation 11 04-Oct-12 16-Oct-12 17-Jan-13 30-Jan-13 85 A75850 H/L Hot&Cold Water Pipe Installation 11 04-Oct-12 16-Oct-12 17-Jan-13 30-Jan-13 85 A75830 Drainge Pipes in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17 A75900 Water Pipes in Wall 12 04-Oct-12 17-Oct-12 24-Oct-12 08-Nov-12 17 A75870 ElectricalWater Heater Installation 4 17-Oct-12 21-Oct-12 04-Feb-13 07-Feb-13 88 A75860 Drainage&Water Pipes Testing 7 17-Oct-12 24-Oct-12 31-Jan-13 07-Feb-13 85 A75880 Floor Drain Fixning 2 16-Jan-13 17-Jan-13 04-Mar-13 05-Mar-13 39 A75890 Installation of Sanitaryware 3 18-Feb-13 20-Feb-13 24-Mar-13 26-Mar-13 29 Fire FigFire Fighting 113 04-Oct-12 19-Feb-13 22-Nov-12 06-Apr-13 39 A75940 Fire Fighting Pipe 11 04-Oct-12 16-Oct-12 22-Nov-12 05-Dec-12 39 A75930 Hydro Static Test for Pipes 7 17-Oct-12 24-Oct-12 06-Dec-12 13-Dec-12 39 A75910 Installation of Fire Extingusher&Blanket 2 06-Feb-13 07-Feb-13 04-Apr-13 06-Apr-13 49 A75920 Sprinkler Fixing 7 06-Feb-13 13-Feb-13 26-Feb-13 05-Mar-13 17 A76020 Fire Alarm Devices 7 12-Feb-13 19-Feb-13 19-Mar-13 26-Mar-13 30 Three BedrThree Bedroom Flats 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38 ApartemeApartement .1 -4 (3 BR) 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38 FinishingFinishing Works 153 30-Aug-12 03-Mar-13 12-Sep-12 16-Apr-13 38 Wet WoWet Works 83 30-Aug-12 09-Dec-12 12-Sep-12 23-Feb-13 63 A76180 Block Works 15 30-Aug-12 16-Sep-12 12-Sep-12 29-Sep-12 11 A76040 Installation of Doors& Windows Sub-frame 7 01-Oct-12 08-Oct-12 16-Feb-13 23-Feb-13 112 A76030 Plaster Works 18 01-Oct-12 21-Oct-12 14-Oct-12 05-Nov-12 11 A76510 Wall Tiles Work (Wet Area) 13 22-Oct-12 07-Nov-12 31-Dec-12 15-Jan-13 56 A76060 Installation of Suspended Ceiling Grid (Dry Area) 8 07-Nov-12 17-Nov-12 21-Nov-12 29-Nov-12 11 A76050 1st Coat Paint 18 18-Nov-12 09-Dec-12 01-Dec-12 22-Dec-12 11 Fisrt StaFisrt Stage Finishes 47 10-Dec-12 04-Feb-13 23-Dec-12 26-Mar-13 43 A76070 Suspended Ceiling Tiles (DryArea) 12 10-Dec-12 23-Dec-12 23-Dec-12 06-Jan-13 11 A76110 Installation of Wardrobes 8 24-Dec-12 02-Jan-13 07-Jan-13 15-Jan-13 11 A76500 Screed Works 9 03-Jan-13 13-Jan-13 16-Jan-13 27-Jan-13 11 A76100 Water Proofing for Wet Area 9 14-Jan-13 23-Jan-13 30-Jan-13 09-Feb-13 13 A76090 Floor & Wall Tiles Work (Dry Area) 12 14-Jan-13 28-Jan-13 13-Mar-13 26-Mar-13 49 A76540 Installation of Suspended Ceiling Grid (Wet Area) 7 20-Jan-13 28-Jan-13 05-Feb-13 12-Feb-13 13 A76520 Floor Tiles Work (Wet Area) 5 30-Jan-13 04-Feb-13 05-Mar-13 10-Mar-13 29 A76530 Suspended Ceiling Tiles (Wet Area) 10 23-Jan-13 04-Feb-13 09-Feb-13 19-Feb-13 13 SecondSecond Stage Finishes 19 04-Feb-13 25-Feb-13 10-Mar-13 04-Apr-13 33 A76120 Installation of Windows&Doors 7 04-Feb-13 11-Feb-13 10-Mar-13 17-Mar-13 29 A76190 Doors Ironmongery 9 04-Feb-13 13-Feb-13 17-Mar-13 26-Mar-13 35 A76160 Installation of Balustrades& Handrails 5 12-Feb-13 17-Feb-13 21-Mar-13 26-Mar-13 32 A76170 Installation of Vanity Counter 9 07-Feb-13 17-Feb-13 21-Mar-13 31-Mar-13 36 A76130 Installation of Mirrors 9 12-Feb-13 21-Feb-13 21-Mar-13 31-Mar-13 32 A76140 Installation of Kitchen Cabinets 10 12-Feb-13 23-Feb-13 21-Mar-13 01-Apr-13 32 A76480 Installation of Toliets Accessories 12 12-Feb-13 25-Feb-13 23-Mar-13 04-Apr-13 33 Final StFinal Stage Finishes 9 21-Feb-13 03-Mar-13 27-Mar-13 16-Apr-13 38 A76080 Final Coat Paint 9 21-Feb-13 03-Mar-13 27-Mar-13 06-Apr-13 29 A76490 Installation of Sinages 5 26-Feb-13 03-Mar-13 11-Apr-13 16-Apr-13 38 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Installation of Fire Extingusher&Blanket Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Installation of Suspended Ceiling Grid (Wet Area) Floor & Wall Tiles Work (Dry Area) Floor Tiles Work (Wet Area) Suspended Ceiling Tiles (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Mirrors Installation of Vanity Counter Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Water Pipes in Wall Electrical Water Heater Installation Drainage&Water Pipes Testing Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work (Wet Area) Installation of Suspended Ceiling Grid (Dry Area) 1st Coat Paint Suspended Ceiling Tiles (DryArea) Installation of Wardrobes Screed Works Water Proofing for Wet Area Floor & Wall Tiles Work (Dry Area) Installation of Suspended Ceiling Grid (Wet Area) Floor Tiles Work (Wet Area) Suspended Ceiling Tiles (Wet Area) Installation of Windows&Doors Doors Ironmongery Installation of Balustrades& Handrails Installation of Vanity Counter Installation of Mirrors Installation of Kitchen Cabinets Installation of Toliets Accessories Final Coat Paint Installation of Sinages Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 92 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 93. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float MEP WoMEP Works 133 17-Sep-12 25-Feb-13 30-Sep-12 06-Apr-13 34 HVACHVAC 125 17-Sep-12 16-Feb-13 13-Oct-12 05-Mar-13 15 A76210 Duct Installation & Insulation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22 A76220 Chilled Water Pipe Installation & Insulation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22 A76230 Condensate Pipe Installation 18 17-Sep-12 07-Oct-12 13-Oct-12 04-Nov-12 22 A76240 FCU Installation 13 08-Oct-12 22-Oct-12 05-Nov-12 20-Nov-12 22 A76250 Air-Outlet Installation 10 05-Feb-13 16-Feb-13 23-Feb-13 05-Mar-13 15 ElectricElectrical 127 17-Sep-12 18-Feb-13 30-Sep-12 05-Mar-13 13 A76260 Install Conduits in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11 A76270 Install Cable Trays & Trunking 12 17-Sep-12 30-Sep-12 18-Oct-12 03-Nov-12 27 A76310 Cable Laying for Low Current System 15 01-Oct-12 17-Oct-12 12-Nov-12 29-Nov-12 34 A76320 Cable Laying for Power 15 01-Oct-12 17-Oct-12 12-Nov-12 29-Nov-12 34 A76280 Wiring for Lighting & Power 12 22-Oct-12 06-Nov-12 06-Nov-12 20-Nov-12 11 A76290 Wiring for Low Current System 12 22-Oct-12 06-Nov-12 06-Nov-12 20-Nov-12 11 A76300 DB installation,Dressing & Termination 10 10-Dec-12 20-Dec-12 25-Dec-12 06-Jan-13 13 A76350 Installation of Sockets 9 05-Feb-13 14-Feb-13 24-Feb-13 05-Mar-13 16 A76340 Installation of Lighting Fittings 12 05-Feb-13 18-Feb-13 20-Feb-13 05-Mar-13 13 PlumbinPlumbing 133 17-Sep-12 25-Feb-13 30-Sep-12 31-Mar-13 29 A76370 H/L Drainage Pipes Installation 11 17-Sep-12 29-Sep-12 10-Jan-13 22-Jan-13 94 A76380 H/L Hot&Cold Water Pipe Installation 11 17-Sep-12 29-Sep-12 10-Jan-13 22-Jan-13 94 A76360 Drainge Pipes in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11 A76430 Water Pipes in Wall 12 17-Sep-12 30-Sep-12 30-Sep-12 13-Oct-12 11 A76390 Drainage&Water Pipes Testing 7 30-Sep-12 07-Oct-12 23-Jan-13 31-Jan-13 94 A76400 ElectricalWater Heater Installation 10 30-Sep-12 10-Oct-12 23-Jan-13 04-Feb-13 94 A76410 Floor Drain Fixning 9 06-Jan-13 15-Jan-13 24-Feb-13 05-Mar-13 41 A76420 Installation of Sanitaryware 12 12-Feb-13 25-Feb-13 18-Mar-13 31-Mar-13 29 Fire FigFire Fighting 125 17-Sep-12 16-Feb-13 30-Oct-12 06-Apr-13 42 A76470 Fire Fighting Pipe 11 17-Sep-12 29-Sep-12 30-Oct-12 11-Nov-12 35 A76460 Hydro Static Test for Pipes 7 30-Sep-12 07-Oct-12 12-Nov-12 20-Nov-12 35 A76440 Installation of Fire Extingusher&Blanket 2 05-Feb-13 06-Feb-13 04-Apr-13 06-Apr-13 50 A76450 Sprinkler Fixing 10 05-Feb-13 16-Feb-13 23-Feb-13 05-Mar-13 15 A76550 Fire Alarm Devices 10 05-Feb-13 16-Feb-13 16-Mar-13 26-Mar-13 33 3rd Floor3rd Floor 161 13-Sep-12 26-Mar-13 27-Sep-12 16-Apr-13 18 Public AreaPublic Area 141 07-Oct-12 26-Mar-13 26-Dec-12 16-Apr-13 18 Garbage RGarbage Room 89 24-Oct-12 11-Feb-13 05-Feb-13 16-Apr-13 55 FinishingFinishing Works 89 24-Oct-12 11-Feb-13 05-Feb-13 16-Apr-13 55 Wet WorWet Works 68 24-Oct-12 16-Jan-13 05-Feb-13 07-Apr-13 68 A78900 Block Works 3 24-Oct-12 29-Oct-12 05-Feb-13 07-Feb-13 83 A78850 Installation of Doors& Windows Sub-frame 1 08-Dec-12 08-Dec-12 07-Apr-13 07-Apr-13 101 A78840 Plaster Works 3 08-Dec-12 10-Dec-12 13-Feb-13 16-Feb-13 56 A78880 Wall Tiles Work 4 13-Dec-12 17-Dec-12 19-Feb-13 23-Feb-13 56 A78860 1st Coat Paint 2 15-Jan-13 16-Jan-13 24-Feb-13 25-Feb-13 33 Fisrt StaFisrt Stage Finishes 20 17-Jan-13 10-Feb-13 26-Feb-13 15-Apr-13 55 A79030 Screed Works 2 17-Jan-13 19-Jan-13 26-Feb-13 27-Feb-13 33 A79050 Floor Tiles Work 2 21-Jan-13 22-Jan-13 02-Mar-13 03-Mar-13 33 A78910 Doors Ironmongery 1 09-Feb-13 09-Feb-13 15-Apr-13 15-Apr-13 56 A78890 Installation of Doors 2 09-Feb-13 10-Feb-13 08-Apr-13 09-Apr-13 50 Second SSecond Stage Finishes 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45 A78870 Final Coat Paint 2 09-Feb-13 10-Feb-13 02-Apr-13 03-Apr-13 45 Final StaFinal Stage Finishes 1 11-Feb-13 11-Feb-13 16-Apr-13 16-Apr-13 55 A79020 Installation of Sinages 1 11-Feb-13 11-Feb-13 16-Apr-13 16-Apr-13 55 MEP WorkMEP Works 72 30-Oct-12 26-Jan-13 09-Feb-13 01-Apr-13 56 ElectricalElectrical 72 30-Oct-12 26-Jan-13 11-Feb-13 05-Mar-13 33 A78920 Install Conduits in Wall 2 30-Oct-12 31-Oct-12 11-Feb-13 12-Feb-13 85 A78930 Wiring for Lighting & Power 2 11-Dec-12 12-Dec-12 17-Feb-13 18-Feb-13 56 A78940 Installation of Lighting Fittings 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33 PlumbingPlumbing 68 30-Oct-12 20-Jan-13 09-Feb-13 28-Feb-13 33 A78950 Drainge Pipes in Wall 2 30-Oct-12 31-Oct-12 09-Feb-13 10-Feb-13 83 A78980 Water Pipes in Wall 2 30-Oct-12 31-Oct-12 09-Feb-13 10-Feb-13 83 A78960 Drainage&Water Pipes Testing 2 01-Nov-12 03-Nov-12 11-Feb-13 12-Feb-13 83 A78970 Floor Drain Fixning 1 20-Jan-13 20-Jan-13 28-Feb-13 28-Feb-13 33 Fire FighFire Fighting 72 30-Oct-12 26-Jan-13 27-Feb-13 01-Apr-13 56 A79010 Fire Fighting Pipe 2 30-Oct-12 31-Oct-12 27-Feb-13 28-Feb-13 99 A79000 Hydro Static Test for Pipes 2 01-Nov-12 03-Nov-12 02-Mar-13 03-Mar-13 99 A78990 Sprinkler Fixing 2 23-Jan-13 26-Jan-13 04-Mar-13 05-Mar-13 33 A79040 Fire Alarm Devices 2 23-Jan-13 26-Jan-13 31-Mar-13 01-Apr-13 56 Corridor &Corridor & Lift Lobby 134 15-Oct-12 26-Mar-13 30-Dec-12 16-Apr-13 18 FinishingFinishing Works 134 15-Oct-12 26-Mar-13 30-Dec-12 16-Apr-13 18 Wet WorWet Works 80 15-Oct-12 21-Jan-13 30-Dec-12 27-Feb-13 31 A79110 Block Works 8 15-Oct-12 23-Oct-12 30-Dec-12 08-Jan-13 61 A79060 Plaster Works 7 28-Nov-12 06-Dec-12 12-Jan-13 19-Jan-13 36 A79080 Installation of Suspended Ceiling Grid 6 12-Dec-12 18-Dec-12 26-Jan-13 31-Jan-13 36 A79070 1st Coat Paint 5 09-Jan-13 14-Jan-13 16-Feb-13 20-Feb-13 31 A79090 Suspended Ceiling Tiles 6 15-Jan-13 21-Jan-13 21-Feb-13 27-Feb-13 31 Fisrt StaFisrt Stage Finishes 48 22-Jan-13 19-Mar-13 01-Apr-13 09-Apr-13 18 A79340 Screed Works 3 22-Jan-13 26-Jan-13 01-Apr-13 03-Apr-13 58 A79360 Floor Tiles Work 5 14-Mar-13 19-Mar-13 04-Apr-13 09-Apr-13 18 Second SSecond Stage Finishes 6 20-Mar-13 26-Mar-13 10-Apr-13 16-Apr-13 18 A79100 Installation of Doors 3 20-Mar-13 23-Mar-13 10-Apr-13 13-Apr-13 18 A79120 Doors Ironmongery 3 20-Mar-13 23-Mar-13 10-Apr-13 13-Apr-13 18 A79370 Final Coat Paint 5 21-Mar-13 26-Mar-13 11-Apr-13 16-Apr-13 18 Final StaFinal Stage Finishes 3 24-Mar-13 26-Mar-13 14-Apr-13 16-Apr-13 18 A79330 Installation of Sinages 3 24-Mar-13 26-Mar-13 14-Apr-13 16-Apr-13 18 MEP WorkMEP Works 80 24-Oct-12 31-Jan-13 09-Jan-13 10-Apr-13 59 HVACHVAC 75 24-Oct-12 26-Jan-13 15-Jan-13 05-Mar-13 33 A79130 Duct Installation & Insulation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66 A79140 Chilled Water Pipe Installation & Insulation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66 A79150 Condensate Pipe Installation 5 24-Oct-12 31-Oct-12 15-Jan-13 20-Jan-13 66 A79160 FCU Installation 3 01-Nov-12 04-Nov-12 21-Jan-13 23-Jan-13 66 A79170 Air-Outlet Installation 3 22-Jan-13 26-Jan-13 03-Mar-13 05-Mar-13 33 ElectricalElectrical 77 24-Oct-12 28-Jan-13 09-Jan-13 05-Mar-13 31 A79180 Install Conduits in Wall 2 24-Oct-12 28-Oct-12 09-Jan-13 10-Jan-13 61 A79190 Install Cable Trays & Trunking 2 24-Oct-12 28-Oct-12 15-Jan-13 16-Jan-13 66 A79230 Cable Laying for Low Current System 2 29-Oct-12 30-Oct-12 30-Jan-13 31-Jan-13 76 A79240 Cable Laying for Power 3 29-Oct-12 31-Oct-12 29-Jan-13 31-Jan-13 75 A79200 Wiring for Lighting & Power 3 08-Dec-12 10-Dec-12 21-Jan-13 23-Jan-13 37 A79210 Wiring for Low Current System 4 08-Dec-12 11-Dec-12 20-Jan-13 23-Jan-13 36 A79220 DB installation,Dressing & Termination 7 19-Dec-12 26-Dec-12 20-Feb-13 27-Feb-13 52 A79270 Installation of Sockets 3 22-Jan-13 26-Jan-13 03-Mar-13 05-Mar-13 33 A79260 Installation of Lighting Fittings 5 22-Jan-13 28-Jan-13 28-Feb-13 05-Mar-13 31 PlumbingPlumbing 5 24-Oct-12 31-Oct-12 19-Jan-13 23-Jan-13 69 A79280 H/L Hot&Cold Water Pipe Installation 5 24-Oct-12 31-Oct-12 19-Jan-13 23-Jan-13 69 Fire FighFire Fighting 80 24-Oct-12 31-Jan-13 15-Jan-13 10-Apr-13 59 A79320 Fire Fighting Pipe 4 24-Oct-12 30-Oct-12 15-Jan-13 19-Jan-13 66 A79310 Hydro Static Test for Pipes 4 31-Oct-12 04-Nov-12 20-Jan-13 23-Jan-13 66 A79300 Sprinkler Fixing 4 22-Jan-13 27-Jan-13 02-Mar-13 05-Mar-13 32 A79350 Fire Alarm Devices 5 22-Jan-13 28-Jan-13 06-Apr-13 10-Apr-13 62 A79290 Installation of Fire Extingusher&Blanket 4 28-Jan-13 31-Jan-13 07-Apr-13 10-Apr-13 59 Electrical /Electrical /Meter/ Telephone Rooms 99 11-Oct-12 10-Feb-13 26-Dec-12 16-Apr-13 56 FinishingFinishing Works 99 11-Oct-12 10-Feb-13 26-Dec-12 16-Apr-13 56 Wet WorWet Works 72 11-Oct-12 08-Jan-13 26-Dec-12 20-Feb-13 36 ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2012 2013 Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Drainage Pipes Installation H/L Hot&Cold Water Pipe Installation Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Electrical Water Heater Installation Floor Drain Fixning Installation of Sanitaryware Fire Fighting Pipe Hydro Static Test for Pipes Installation of Fire Extingusher&Blanket Sprinkler Fixing Fire Alarm Devices Block Works Installation of Doors& Windows Sub-frame Plaster Works Wall Tiles Work 1st Coat Paint Screed Works Floor Tiles Work Doors Ironmongery Installation of Doors Final Coat Paint Installation of Sinages Install Conduits in Wall Wiring for Lighting & Power Installation of Lighting Fittings Drainge Pipes in Wall Water Pipes in Wall Drainage&Water Pipes Testing Floor Drain Fixning Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Block Works Plaster Works Installation of Suspended Ceiling Grid 1st Coat Paint Suspended Ceiling Tiles Screed Works Floor Tiles Work Installation of Doors Doors Ironmongery Final Coat Paint Installation of Sinages Duct Installation & Insulation Chilled Water Pipe Installation & Insulation Condensate Pipe Installation FCU Installation Air-Outlet Installation Install Conduits in Wall Install Cable Trays & Trunking Cable Laying for Low Current System Cable Laying for Power Wiring for Lighting & Power Wiring for Low Current System DB installation,Dressing & Termination Installation of Sockets Installation of Lighting Fittings H/L Hot&Cold Water Pipe Installation Fire Fighting Pipe Hydro Static Test for Pipes Sprinkler Fixing Fire Alarm Devices Installation of Fire Extingusher&Blanket Asset Management Group (Wasl)  Al Muraqqabat Mixed Use Development Data Date : 01-Jan-12 Page : 93 of 114 Printed On : 02-Feb-12 Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Project Implementation Schedule Overall Schedule Date Revision Chec... Approved 25-Jan-12 Project Implementation Schedule - Rev 00
  • 94. Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float A79430 Block Works 3 11-Oct-12 14-Oct-12 26-Dec-12 29-Dec-12 61 A79390 Installation of Doors& Windows Sub-frame 1 24-Nov-12 24-Nov-12 20-Feb-13 20-Feb-13 73 A79380 Plaster Works 4 24-Nov-12 27-Nov-12 07-Jan-13 10-Jan-13 36 A79400 1st Coat Paint 3 06-Jan-13 08-Jan-13 06-Feb-13 09-Feb-13 26 Fisrt StaFisrt Stage Finishes 57 28-Nov-12 05-Feb-13 21-Feb-13 14-Apr-13 58 A79420 Installation of Doors 2 28-Nov-12 29-Nov-12 21-Feb-13 23-Feb-13 70 A79440 Doors Ironmongery 2 28-Nov-12 29-Nov-12 13-Apr-13 14-Apr-13 113 A79490 Epoxy Paint Works 2 04-Feb-13 05-Feb-13 28-Mar-13 30-Mar-13 45 Second SSecond Stage Finishes 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45 A79410 Final Coat Paint 2 06-Feb-13 07-Feb-13 31-Mar-13 01-Apr-13 45 Final StaFinal Stage Finishes 2 09-Feb-13 10-Feb-13 15-Apr-13 16-Apr-13 56 A79480 Installation of Sinages 2 09-Feb-13 10-Feb-13 15-Apr-13 16-Apr-13 56 MEP WorkMEP Works 90 15-Oct-12 03-Feb-13 05-Jan-13 27-Mar-13 45 HVACHVAC 2 09-Jan-13 10-Jan-13 04-Mar-13 05-Mar-13 45 A79520 Air-Outlet Installation 2 09-Jan-13 10-Jan-13 04-Mar-13 05-Mar-13 45 ElectricalElectrical 90 15-Oct-12 03-Feb-13 05-Jan-13 05-Mar-13 26 A79450 Install Conduits in Wall 2 15-Oct-12 16-Oct-12 05-Jan-13 06-Jan-13 65 A79460 Wiring for Lighting & Power 2 28-Nov-12 29-Nov-12 04-Feb-13 05-Feb-13 55 A79510 Installation of SMDBs 7 09-Jan-13 16-Jan-13 24-Feb-13 03-Mar-13 38 A79470 Installation of Lighting Fittings 2 17-Jan-13 19-Jan-13 04-Mar-13 05-Mar-13 38 A115000 Installation of Telephone System 21 09-Jan-13 03-Feb-13 10-Feb-13 05-Mar-13 26 Fire FighFire Fighting 2 20-Jan-13 21-Jan-13 26-Mar-13 27-Mar-13 55 A79500 Fire Alarm Devices 2 20-Jan-13 21-Jan-13 26-Mar-13 27-Mar-13 55 StaircaseStaircase 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105 Stairs 1Stairs 1 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105 A112170 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105 A112210 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105 A112180 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112190 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112200 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105 A112220 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105 Stairs 2Stairs 2 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105 A112230 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105 A112270 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105 A112240 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112250 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112260 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105 A112280 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105 Stairs 3Stairs 3 43 07-Oct-12 28-Nov-12 13-Feb-13 03-Apr-13 105 A112290 Floor Screed 3 07-Oct-12 09-Oct-12 13-Feb-13 16-Feb-13 105 A112330 Install Handrails 4 10-Oct-12 14-Oct-12 17-Feb-13 20-Feb-13 105 A112300 Ceiling 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112310 Wall 1st Coat Paint 12 15-Oct-12 30-Oct-12 21-Feb-13 06-Mar-13 105 A112320 Install Granite/Terrazo 12 31-Oct-12 13-Nov-12 07-Mar-13 20-Mar-13 105 A112340 Final Coat Paint 12 14-Nov-12 28-Nov-12 21-Mar-13 03-Apr-13 105 ApartementsApartements 157 13-Sep-12 21-Mar-13 27-Sep-12 16-Apr-13 22 One BedroOne Bedroom Flats 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61 ApartemeApartement .1- 5 (1 BR) 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61 FinishingFinishing Works 103 01-Oct-12 04-Feb-13 12-Nov-12 16-Apr-13 61 Wet WoWet Works 60 01-Oct-12 13-Dec-12 12-Nov-12 19-Feb-13 56 A77400 Block Works 9 01-Oct-12 10-Oct-12 12-Nov-12 22-Nov-12 34 A77260 Installation of Doors& Windows Sub-frame 2 07-Nov-12 08-Nov-12 18-Feb-13 19-Feb-13 84 A77250 Plaster Works 13 07-Nov-12 22-Nov-12 28-Nov-12 13-Dec-12 17 A77280 Installation of Suspended Ceiling Grid (Dry Area) 4 27-Nov-12 01-Dec-12 18-Dec-12 22-Dec-12 17 A77730 Wall Tiles Work (Wet Area) 9 24-Nov-12 04-Dec-12 31-Dec-12 10-Jan-13 31 A77270 1st Coat Paint 11 01-Dec-12 13-Dec-12 22-Dec-12 03-Jan-13 17 Fisrt StaFisrt Stage Finishes 31 12-Dec-12 17-Jan-13 03-Jan-13 24-Feb-13 31 A77290 Suspended Ceiling Tiles (DryArea) 4 12-Dec-12 16-Dec-12 03-Jan-13 07-Jan-13 18 A77330 Installation of Wardrobes 4 16-Dec-12 19-Dec-12 13-Jan-13 16-Jan-13 23 A77720 Screed Works 9 19-Dec-12 29-Dec-12 16-Jan-13 27-Jan-13 23 A77320 Water Proofing for Wet Area 3 30-Dec-12 02-Jan-13 29-Jan-13 31-Jan-13 24 A77310 Floor & Wall Tiles Work (Dry Area) 4 30-Dec-12 03-Jan-13 20-Feb-13 24-Feb-13 43 A77760 Installation of Suspended Ceiling Grid (Wet Area) 4 03-Jan-13 07-Jan-13 02-Feb-13 05-Feb-13 24 A77750 Suspended Ceiling Tiles (Wet Area) 4 08-Jan-13 12-Jan-13 06-Feb-13 10-Feb-13 24 A77740 Floor Tiles Work (Wet Area) 5 13-Jan-13 17-Jan-13 18-Feb-13 23-Feb-13 30 SecondSecond Stage Finishes 7 19-Jan-13 27-Jan-13 24-Feb-13 07-Mar-13 34 A77340 Installation of Windows&Doors 3 19-Jan-13 21-Jan-13 24-Feb-13 26-Feb-13 30 A77410 Doors Ironmongery 3 19-Jan-13 21-Jan-13 05-Mar-13 07-Mar-13 38 A77380 Installation of Balustrades& Handrails 2 22-Jan-13 23-Jan-13 06-Mar-13 07-Mar-13 36 A77350 Installation of Mirrors 3 22-Jan-13 26-Jan-13 05-Mar-13 07-Mar-13 35 A77360 Installation of Kitchen Cabinets 3 22-Jan-13 26-Jan-1