This document contains a progress report for the construction of various structures in the Anantara Palm Jumeirah and Tiara Residences development for Zabeel Investement. It shows that while most structures like the residential and hotel towers are 1-2% behind schedule, concrete work, the parking structure, clubhouse and swimming pool are further behind schedule, with variances ranging from 2-20% behind planned progress. The document provides the planned progress, actual progress and variance for each structure as of January 26, 2008.