The document provides scheduling information for the concrete works of several tower projects (N1-N4). It shows planned start/finish dates, actual start/finish dates, and delays for each floor slab for each tower. The progress status for all works is reported as 100% completed. Some key details include:
- Tower N4 had delays ranging from -138 to -7 days compared to planned schedules.
- Tower N3 saw delays between -104 to -50 days.
- Delays for Tower N2 ranged from -106 to -13 days.
- Tower N1 experienced delays from -79 to -12 days.