CLIENT: ZabeelCLIENT: ZabeelCLIENT: ZabeelCLIENT: Zabeel
Investement L.I.CInvestement L.I.CInvestement L.I.CInvestement L.I.C
Planning Departement
Package No. : D0469
Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08
% Early Monthly 0.00% 0.48% 4.34% 10.99% 12.04% 15.57% 22.85% 18.84% 12.63% 2.24% 0.00%
% Accu. Early Monthly 0.00% 0.48% 4.83% 15.82% 27.87% 43.43% 66.29% 85.13% 97.76% 100.00% 100.00%
% Late Monthly 0.00% 0.00% 0.25% 2.92% 6.16% 12.95% 14.22% 13.92% 19.78% 20.05% 9.76%
% Accu. Late Monthly 0.00% 0.00% 0.25% 3.17% 9.34% 22.29% 36.50% 50.42% 70.20% 90.24% 100.00%
% Actual Monthly 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33% 0.00% 0.00% 0.00% 0.00%
% Actual Accum. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33%
Actual
Anantara Palm Jumeirah and Tiara Residences
Overall Progress S-Curve For Ceiling Works
Progress Status For Period Ending On < 26-January08 >
Month : January. 08Month : January. 08Month : January. 08Month : January. 08
Early Planned
Late Planned
4.83%
85.13%
100.00%
0.25%
9.34%
50.42%
70.20%
100.00%
66.29%
43.43%
97.76%
15.82%
27.87%
36.50%
22.29%
90.24%
3.17%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08
Months
%Progress
% Early Monthly
% Late Monthly
% Actual Monthly
% Accu. Early Monthly
% Accu. Late Monthly
% Actual Accum.
Data Date: 26Jan08
0.33%

More Related Content

PDF
Overall Progress S-Curve For Facades
PDF
Overall Progres S-Curve For Concrete Works
PDF
Presentation to CFO West 2015
PDF
Benefits_of_HomeUnion
PDF
PayrollStrcutures1
PDF
FFL Bonus Program
PPTX
Presupuestos de defensa y s.c.
PDF
Stampa tr severinofeb_2104
Overall Progress S-Curve For Facades
Overall Progres S-Curve For Concrete Works
Presentation to CFO West 2015
Benefits_of_HomeUnion
PayrollStrcutures1
FFL Bonus Program
Presupuestos de defensa y s.c.
Stampa tr severinofeb_2104

What's hot (20)

PDF
Program tracker dashboard v2 (example)
PPTX
Data driven financial charts corporate-fix
PPSX
Comparing investments the cherry picker
PPTX
Comparing investments the cherry picker
PPTX
Comparing investments the cherry picker
PDF
Daily Derivative Report
PPTX
Visibility & transparency on mission critical success factors
PPTX
Final analyst q1 2013
PPTX
Successfully Managing Your Property and Share Portfolio
PDF
Acquisition workshop 2
PDF
Domino
PPTX
Mythbusters for 360 short
PDF
2015 Who Went Where Survey Presentation - Jamie Grigsby
PDF
LBS - Economic and Financial Forecasts - June 2017
PDF
Ewatts sbm300
PDF
Φθινοπωρινές ασκήσεις μαθηματικών
PPT
Agel Business Prestation
PDF
AAP PERFORMANCE ANALYSIS EIP EIR EAIP EAIF EVESTMENT UPDATES 19960101 - 2017...
PDF
Cap table
PDF
BBUS 428 Homework Oct. 2nd
Program tracker dashboard v2 (example)
Data driven financial charts corporate-fix
Comparing investments the cherry picker
Comparing investments the cherry picker
Comparing investments the cherry picker
Daily Derivative Report
Visibility & transparency on mission critical success factors
Final analyst q1 2013
Successfully Managing Your Property and Share Portfolio
Acquisition workshop 2
Domino
Mythbusters for 360 short
2015 Who Went Where Survey Presentation - Jamie Grigsby
LBS - Economic and Financial Forecasts - June 2017
Ewatts sbm300
Φθινοπωρινές ασκήσεις μαθηματικών
Agel Business Prestation
AAP PERFORMANCE ANALYSIS EIP EIR EAIP EAIF EVESTMENT UPDATES 19960101 - 2017...
Cap table
BBUS 428 Homework Oct. 2nd
Ad

Viewers also liked (7)

PDF
Land degradation
PPT
Construction process
PPSX
Project network scheduling and S-curve
PDF
S curve innovation #BBTwisnu
PPSX
How to Create S Curve by MS Project 2013
PPSX
Project management
Land degradation
Construction process
Project network scheduling and S-curve
S curve innovation #BBTwisnu
How to Create S Curve by MS Project 2013
Project management
Ad

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

PDF
Kandil Mohammed Ibrahim_Sameh_Dissertation
PDF
Summary Progress Of Facade Works
PDF
Summary Progress Of Concrete Works
PDF
Progress Of Ceiling Per Floors
PDF
Overall Progress S-Curve For Elevators
PDF
Window Analysis @ 30-June-2012
PDF
01. P269 - Project Implementation Programme - Rev 00
PDF
10. Overall Implementation Programme
PDF
Building-Structure Planning Model
DOC
Rihan Height Project Execution Plan-Rev00
PDF
Monthly Progress Report No.13 - September 2011
PDF
Resources Calculations for Bldg. A
PDF
Contract 2 - Project Progress Status. Oct-13
Kandil Mohammed Ibrahim_Sameh_Dissertation
Summary Progress Of Facade Works
Summary Progress Of Concrete Works
Progress Of Ceiling Per Floors
Overall Progress S-Curve For Elevators
Window Analysis @ 30-June-2012
01. P269 - Project Implementation Programme - Rev 00
10. Overall Implementation Programme
Building-Structure Planning Model
Rihan Height Project Execution Plan-Rev00
Monthly Progress Report No.13 - September 2011
Resources Calculations for Bldg. A
Contract 2 - Project Progress Status. Oct-13

Overall Progress S-Curve For Ceiling

  • 1. CLIENT: ZabeelCLIENT: ZabeelCLIENT: ZabeelCLIENT: Zabeel Investement L.I.CInvestement L.I.CInvestement L.I.CInvestement L.I.C Planning Departement Package No. : D0469 Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 % Early Monthly 0.00% 0.48% 4.34% 10.99% 12.04% 15.57% 22.85% 18.84% 12.63% 2.24% 0.00% % Accu. Early Monthly 0.00% 0.48% 4.83% 15.82% 27.87% 43.43% 66.29% 85.13% 97.76% 100.00% 100.00% % Late Monthly 0.00% 0.00% 0.25% 2.92% 6.16% 12.95% 14.22% 13.92% 19.78% 20.05% 9.76% % Accu. Late Monthly 0.00% 0.00% 0.25% 3.17% 9.34% 22.29% 36.50% 50.42% 70.20% 90.24% 100.00% % Actual Monthly 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33% 0.00% 0.00% 0.00% 0.00% % Actual Accum. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33% Actual Anantara Palm Jumeirah and Tiara Residences Overall Progress S-Curve For Ceiling Works Progress Status For Period Ending On < 26-January08 > Month : January. 08Month : January. 08Month : January. 08Month : January. 08 Early Planned Late Planned 4.83% 85.13% 100.00% 0.25% 9.34% 50.42% 70.20% 100.00% 66.29% 43.43% 97.76% 15.82% 27.87% 36.50% 22.29% 90.24% 3.17% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Months %Progress % Early Monthly % Late Monthly % Actual Monthly % Accu. Early Monthly % Accu. Late Monthly % Actual Accum. Data Date: 26Jan08 0.33%