 This article is to explain Project Management
Concept as a quick reference through step by step
guidance using MS Project 2013
 The targeted audience is a beginner to the project
management and experienced with MS Project in
early version, such 2007 or 2010
Guide line
4Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
1. Start Project
2. Plan the Tasks
3. Assign resources
4. Project Baseline set up
5. Update progress
6. Forecast Information
7. Step by Step to S-Curve
8. Step by Step Export Data to Excel (Visual Report)
9. Close Project
Table of Contents
5Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 Prior to start the project planning, Project manager
should be identified, who can set up a project plan
in MS project 2013
Step-1: Start Project
1. Create a new
Project File
To create a new blank project in Project,
click the file tab. Click new
6Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
2. Set project
start date
Go to Project tab. Click Project information
Step-1: Start Project
7Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-1: Start Project
3. Define Project
Calendar
Go to Project tab. Click Change Working
time
8Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-1: Start Project
4. Save the
Project file
Go to Tab file, select save as with Project
Name or Job Order running number
9Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 In the planning stage, we need to achieved project’s
goals. To do this, we have to identify the project’s
milestone, deliverables and tasks.
 This plan can be use work breakdown structure
(WBS).
Step-2: Plan the Tasks
10Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-2: Plan the Tasks
1. Enter Task Click View tab. In the Task View groups,
click Gantt Chart. In the Task Name fields,
enter tasks.
11Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-2: Plan the Tasks
2. Decide how
you want to
Schedule Task
In Project 2013, we can schedule tasks
manually or automatically. Select schedule
method after enter a new tasks by clicking
in the Task Mode column:-
Note: New Tasks manually set by default in
Option Tab
12Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-2: Plan the Tasks
3. Outline Tasks Create task hierarchy including tasks and
milestones under summary task, which can
be represent phase or other work divisions.
Click the Task tab. In the Schedule group
select Indent or Outdent button
• Tip: if you created a summary task with
duration, start or finish date, then the
tasks that fall under the summary task
will not be rolled up to this summary
tasks.
13Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
4. Enter Durations Click the Duration field for a task and enter
a Duration. Two way to entering a
duration:-
 Mutually Schedule task
 A number or text like
“Tomorrow” or “Next after roll
shell” etc.
 Auto Schedule task
 Number only, 3d=3 Days,
0d=milestone, 6? is an estimate
duration.
Note: Both can selected in the Task Mode
Step-2: Plan the Tasks
14Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-2: Plan the Tasks
5. Link Tasks to
show
relationships
Click the Task tab, in the View Group click
Gantt Chart. Select the tasks that you want
to link then click the Link Tasks button in
the Schedule group, or move a mouse to
bar chart press and drack down to tasks
that you want to link.
To change the default Finish-to-Start (FS),
double click the link line and change.
15Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 Assignments are the associations between specific
tasks and the resources needed to completed them.
We can assign more than one resources to a tasks.
 We can assign work resources (People), material
(pipe/shell etc.) and cost (THB) to tasks.
Step-3: Assign Resources
16Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-3: Assign Resources
1. Add Resources
to Project
Click the Task Tab, in the Views dropdown
list select Resources Sheet. In the
Resources Name filed, type the name of
resources that we’ll use in this project.
17Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
2. Assign
Resources to
Tasks
In the Resources Tab, Click Assign
Resources the click resources name then
click assign
Step-3: Assign Resources
18Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-3: Assign Resources
3. Enter the Work
Hours spending
on Tasks
After assign a resources to the Tasks, work
hours automatically show in a Work. If PM
prefer control a Working hours, it can be
change in in Work Field. Entering Work
reflects real world scheduling.
Go to Gantt Chart, right click on column
then click Insert Columns type "WORK” to
select the Work Columns
19Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-3: Assign Resources
4. Know the Work
Tasks Type
After Assign a resources to Tasks, MS
Project determine how to schedule the
tasks based on the tasks type.(Manually
tasks don’t use task type) durations may
change as we assign resources to tasks.
How tasks types work
Work, duration and unit are determined by
formula:-
Work =Duration x Units
20Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-3: Assign Resources
In a… If we revised
Work
If we revised
Duration
If we revised
units
Fixed units tasks Duration changes Work changes Duration changes
Fixed work tasks Duration changes Units change Duration changes
Fixed duration tasks Units change Work changes Work changes
 To set a default task type for the entire project, click the
options. Go to Schedule group, in the default task type box
shown fixed units as a default, we can change to Fixed
Duration or Fixed Work
 To change the task type for an individual, go to tasks tab in
properties group click information or to tasks name double
click it will appear.
21Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-3: Assign Resources
5. Identify factors
effecting task
schedules
We can use MS Project 2013 to help for
understanding how changes one task can
effect the rest of the project.
Click the task tab then in the Schedule
group click Inspect Task. A pane opens on
the left showing the factors that affect the
scheduling of selected task.
Or double click in tasks name.
22Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 Create a baseline or interim plan is to compare
between plan and actual.
 Saving baseline plan enables to identify and solve
discrepancy and plan more accurately for similar
future projects.
Step-4: Set the Project Baseline
23Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-4: Set the Project Base Line
1. Save the
baseline plan
After the plan is solidly in place for the
finish date, budget and scope, we can
submit a plan for approval.
Once it has been approved, save the
baseline plan.
Click the Project tab, in Schedule group
click Set Baseline
24Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-4: Set the Project Base Line
2.View baseline
data in Gantt
Chart views
In Gantt chart view, move a mouse to gantt
area, right click and select Bar Style.
Name Appearance Show for
Task
Row From To
Base Plan
(Custom)
Select bar
shave and
color
Select Normal 2 or 3 Baseline Start Baseline finish
25Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-4: Set the Project Base Line
3. View Baseline
in a Table
Go to View tab, in Data group click to Table
and select Variance or insert columns with
custom field.
26Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 Updating the progress is the only way to ensure it
stays on tracks as work is performed. The focus at
this point is on managing changes, updating the
schedule, tracking progress and communicating
project information.
 MS Project 2013 tracks 3 sets of date: Current,
Baseline and Actual. When we set the baseline,
current = baseline. when a task is 100% complete,
current=actual.
Step-5: Update Progress
27Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-5: Update Progress
1. Manage
Change
Managing changes involves modifying
duration, date, dependencies, resource
assignment or tasks based on requested
changes or new information.
Keep the current fields up to date and
compare to baseline.
28Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-5: Update Progress
2. Track actual
date and duration
It’s the best to decide on a single method
for tracking progress. We can enter
percentage complete, actual start and
finish dates, actual remaining durations or
actual and remaining work.
Click the Task tab, select the task that we
want to enter actual progress. In the
Schedule group select the amount of
progress done on the tasks.
Default: 0%, 25%, 50%, 75%, 100%
Note: we can put a number direct to
%Complete field
29Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-5: Update Progress
3. Track Actual
Hours and Cost
If we want to enter actual and remaining
work hours or costs, use tracking table.
Click View tab, in Data group point Table
and select Tracking.
Enter progress data in the Act. Work or Act.
Cost field for the task. Program is
determine if we put the actual start and
actual finish or % Complete.
30Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 MS Project 2013 provide many ways of built in
report, but for us we have to create a customize
report by using S-Curve Reports.
Step-6: View Report Information
31Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-6: View Report Information
1. Select a View MS Project 2013 has old and new views to
help you to see project information and
report it to others. Click the View Tab, in
either the Task Views group or Resources
Views group, select the view you want to
use. There’re many view but most usful
ones include:-
• Team planner View
• Timeline View
• Gantt Chart View
• Calendar View
32Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-6: View Report Information
2. Customize a
View
Select the view you want to customize and
then on the Format tab click the type of
view element you want to change, such as
the bar style on the Gantt Chart or
gridlines and time scales of any views.
Tips & Tricks, if you want to filter, sort or
group tasks prior to printing, click the View
tab and then in the Data group, click sort,
Filter or Group options.
33Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-6: View Report Information
3. Print a View or
Report
Set up the current view that we want it to
look when printed. Click the File Tab and
then click Print. A preview part of the view
to see the actual size of the view as it will
be printed.
34Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-6: View Report Information
4. Generate a
Report
In Report tab has many report to view
information of project but we’re intent to
create the S-Curve by using MS Project as a
tools, we’ll focus on how to do it.
Click the Report tab, go to View reports
group, select Customer
35Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 In the field list (right hand) Select Category to Time.
36Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 Then Select Field go to Work, click Actual Work and
Cumulative Actual Work only.
37Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 The Click on Baseline, click Baseline Cumulative
Work, just only one.
38Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 In chart area Right click to change chart type.
 Select Chart type to Combo.
39Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 In the Change Chart Type dialog in Series Name
choose All Cumulative (Actual & Baseline) Chart type
to Line Type.
 Actual Work chart type to Clustered Column and
Click Secondary Axis
40Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 In Field List, in Tasks Tab look at Select Category, click
Edit customize time from Days to Weeks and change
format as you like.
41Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 In design Tab, choose format color as you like.
 In Chart Layout select Layout No 5 to show Data
42Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-7: Step by Step to S-Curve
 Final as just Fonts size and others
43Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-8: Export Data to Excel
1. Visual Report Go to Report tab, select on Visual reports
Export.
Select template dialog show, go to Task
Usage tab, move a mouse on Cash Flow
Report template, then click Edit Template.
In Visual Report-Field Picker is pop up, in
Available Field, select Base line Cumulative
Work and Cumulative Actual Work add to
selected Fields.
44Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-8: Export Data to Excel
2. Analyze Data in
Pivot Table
In PivotTable Fields, select only Actual
Work, Baseline Cumulative work and
Cumulative Actual Work.
45Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-8: Export Data to Excel
3. Custom Charts
in Excel
In Pivot Tab Fields, select only Baseline
Cumulative Work, Cumulative Actual Work
and Actual Work.
In Chart Area Right Click mouse select
Combo chart, then All cumulative change
type to Line only Actual Work to Clustter
Column.
46Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-8: Export Data to Excel
47Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
 Just because your project is almost finished doesn’t
mean that your work is done.
 We still need to solve any final project detail and
customer acceptance for final deliverables.
 Conduct a “Lessons Learned” session, recording
information about areas for improvement and best
practices.
 Make any final update to project plan.
 Finally archive the project plan according to our
organization’s guideline.
Step-9: Close the Project
48Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-9: Close the Project
1. Create a Final
Report
Click the Report tab, click Visual Reports to
see project data as a Pivot Table report in
Excel 2013 or Pivot Diagram view in Visio
professional 2013
We can also view basic reports that don’t
require Excel or Visio. Click Report Tab
many report category available to view
depend on how we want to views.
49Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Step-9: Close the Project
2. Save a Project
as a Template
After completing a project, we have to
leverage what we’ve learned in the project
by making it as a template for future
projects.
Click the File tab and Save As and then in
the Save As Type box click Template.
50Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037
Thanks you
End

More Related Content

PDF
Earned Value Management
PPSX
Project network scheduling and S-curve
PPTX
Tendering process, Bid Evaluation & Award Process
PPTX
Construction contract
PPTX
Ms project 2016 overview
PPTX
MANAGEMENT INFORMATION SYSTEM ppt
PPTX
All Types of sensor in power point presentation
PPTX
Estimation and Costing - Contracts
Earned Value Management
Project network scheduling and S-curve
Tendering process, Bid Evaluation & Award Process
Construction contract
Ms project 2016 overview
MANAGEMENT INFORMATION SYSTEM ppt
All Types of sensor in power point presentation
Estimation and Costing - Contracts

What's hot (20)

PPSX
How to Create S-Curve by MS Project 2010
PPSX
How to create S-Curve by MS Project 2013
PPTX
Introduction To Primavera (P6)
PPT
Primavera Training P6
PDF
Project planning and scheduling
PPTX
PRIMAVERA P6 manual.pptx
PDF
Scheduling by using microsoft project 2013
PDF
Sample wbs for_upstream_epcic_project
PPT
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PDF
Primavera P6 manual
PDF
Ms project lectures
PPTX
Project proposal writing civil engg
PDF
Ms Project Workshop
PDF
PM using P6
PPTX
Primavera presentation
PPTX
00 Introduction of project scheduling
PPSX
MS Project 2010 Training
PPTX
Labour Productivity for construction projects
PDF
Project Scheduling & Controls
PPTX
Work breakdown structures
How to Create S-Curve by MS Project 2010
How to create S-Curve by MS Project 2013
Introduction To Primavera (P6)
Primavera Training P6
Project planning and scheduling
PRIMAVERA P6 manual.pptx
Scheduling by using microsoft project 2013
Sample wbs for_upstream_epcic_project
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Primavera P6 manual
Ms project lectures
Project proposal writing civil engg
Ms Project Workshop
PM using P6
Primavera presentation
00 Introduction of project scheduling
MS Project 2010 Training
Labour Productivity for construction projects
Project Scheduling & Controls
Work breakdown structures
Ad

Viewers also liked (6)

PPT
Chap013 4er1
PDF
Project Control Process
PPT
Project control
PDF
Project Controlling and Project Monitoring
PPT
Project planning and control
PPT
The Project Management Process - Week 9 Performance Management
Chap013 4er1
Project Control Process
Project control
Project Controlling and Project Monitoring
Project planning and control
The Project Management Process - Week 9 Performance Management
Ad

Similar to How to Create S Curve by MS Project 2013 (20)

DOCX
Project Management Quick Reference Guide for Microsoft Project 2007
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
PDF
MS Project Guide.pdf
DOCX
Project Management Quick Reference Guide
DOCX
Project Management Quick Reference Guide For Microsoft Project 2007
PDF
sMs project tutorial_iit
PDF
Ms project tutorial
PDF
Ms project 2000 tutorial
PDF
MSIS & IT 425L Group Assignment One assignment help.pdf
PDF
Omni plan 2-manual
DOCX
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
PDF
Team Contract
DOCX
Project NameCommunication PlanOverviewEffective and .docx
PPTX
Introduction to Microsoft Project 2010
DOC
Devry proj 586 week 3 project guidelines microsoft project new
PDF
Project management by MS Project 2010
DOCX
CSCI 714 Software Project Planning and EstimationLec.docx
PPTX
Microsoft Project Foundations Course.pptx
PPTX
Ms project presentation
Project Management Quick Reference Guide for Microsoft Project 2007
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
MS Project Guide.pdf
Project Management Quick Reference Guide
Project Management Quick Reference Guide For Microsoft Project 2007
sMs project tutorial_iit
Ms project tutorial
Ms project 2000 tutorial
MSIS & IT 425L Group Assignment One assignment help.pdf
Omni plan 2-manual
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
Team Contract
Project NameCommunication PlanOverviewEffective and .docx
Introduction to Microsoft Project 2010
Devry proj 586 week 3 project guidelines microsoft project new
Project management by MS Project 2010
CSCI 714 Software Project Planning and EstimationLec.docx
Microsoft Project Foundations Course.pptx
Ms project presentation

Recently uploaded (20)

PPTX
AcademyNaturalLanguageProcessing-EN-ILT-M02-Introduction.pptx
DOCX
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
PPTX
The Effect of Human Resource Management Practice on Organizational Performanc...
PPTX
worship songs, in any order, compilation
PPTX
Effective_Handling_Information_Presentation.pptx
PPTX
Role and Responsibilities of Bangladesh Coast Guard Base, Mongla Challenges
PDF
Parts of Speech Prepositions Presentation in Colorful Cute Style_20250724_230...
PPTX
INTERNATIONAL LABOUR ORAGNISATION PPT ON SOCIAL SCIENCE
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
Relationship Management Presentation In Banking.pptx
PPTX
An Unlikely Response 08 10 2025.pptx
PPTX
Learning-Plan-5-Policies-and-Practices.pptx
DOCX
"Project Management: Ultimate Guide to Tools, Techniques, and Strategies (2025)"
PPTX
2025-08-10 Joseph 02 (shared slides).pptx
PPTX
fundraisepro pitch deck elegant and modern
PPTX
The spiral of silence is a theory in communication and political science that...
PPTX
Tablets And Capsule Preformulation Of Paracetamol
PPTX
Tour Presentation Educational Activity.pptx
PPTX
Hydrogel Based delivery Cancer Treatment
PPTX
nose tajweed for the arabic alphabets for the responsive
AcademyNaturalLanguageProcessing-EN-ILT-M02-Introduction.pptx
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
The Effect of Human Resource Management Practice on Organizational Performanc...
worship songs, in any order, compilation
Effective_Handling_Information_Presentation.pptx
Role and Responsibilities of Bangladesh Coast Guard Base, Mongla Challenges
Parts of Speech Prepositions Presentation in Colorful Cute Style_20250724_230...
INTERNATIONAL LABOUR ORAGNISATION PPT ON SOCIAL SCIENCE
_ISO_Presentation_ISO 9001 and 45001.pptx
Relationship Management Presentation In Banking.pptx
An Unlikely Response 08 10 2025.pptx
Learning-Plan-5-Policies-and-Practices.pptx
"Project Management: Ultimate Guide to Tools, Techniques, and Strategies (2025)"
2025-08-10 Joseph 02 (shared slides).pptx
fundraisepro pitch deck elegant and modern
The spiral of silence is a theory in communication and political science that...
Tablets And Capsule Preformulation Of Paracetamol
Tour Presentation Educational Activity.pptx
Hydrogel Based delivery Cancer Treatment
nose tajweed for the arabic alphabets for the responsive

How to Create S Curve by MS Project 2013

  • 1. 1Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 OS-MSP-001 Rev.: 01 / 17-03-2016
  • 2. 2Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Sample of Visual in excel
  • 3. 3Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  This article is to explain Project Management Concept as a quick reference through step by step guidance using MS Project 2013  The targeted audience is a beginner to the project management and experienced with MS Project in early version, such 2007 or 2010 Guide line
  • 4. 4Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 1. Start Project 2. Plan the Tasks 3. Assign resources 4. Project Baseline set up 5. Update progress 6. Forecast Information 7. Step by Step to S-Curve 8. Step by Step Export Data to Excel (Visual Report) 9. Close Project Table of Contents
  • 5. 5Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  Prior to start the project planning, Project manager should be identified, who can set up a project plan in MS project 2013 Step-1: Start Project 1. Create a new Project File To create a new blank project in Project, click the file tab. Click new
  • 6. 6Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 2. Set project start date Go to Project tab. Click Project information Step-1: Start Project
  • 7. 7Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-1: Start Project 3. Define Project Calendar Go to Project tab. Click Change Working time
  • 8. 8Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-1: Start Project 4. Save the Project file Go to Tab file, select save as with Project Name or Job Order running number
  • 9. 9Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  In the planning stage, we need to achieved project’s goals. To do this, we have to identify the project’s milestone, deliverables and tasks.  This plan can be use work breakdown structure (WBS). Step-2: Plan the Tasks
  • 10. 10Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-2: Plan the Tasks 1. Enter Task Click View tab. In the Task View groups, click Gantt Chart. In the Task Name fields, enter tasks.
  • 11. 11Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-2: Plan the Tasks 2. Decide how you want to Schedule Task In Project 2013, we can schedule tasks manually or automatically. Select schedule method after enter a new tasks by clicking in the Task Mode column:- Note: New Tasks manually set by default in Option Tab
  • 12. 12Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-2: Plan the Tasks 3. Outline Tasks Create task hierarchy including tasks and milestones under summary task, which can be represent phase or other work divisions. Click the Task tab. In the Schedule group select Indent or Outdent button • Tip: if you created a summary task with duration, start or finish date, then the tasks that fall under the summary task will not be rolled up to this summary tasks.
  • 13. 13Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 4. Enter Durations Click the Duration field for a task and enter a Duration. Two way to entering a duration:-  Mutually Schedule task  A number or text like “Tomorrow” or “Next after roll shell” etc.  Auto Schedule task  Number only, 3d=3 Days, 0d=milestone, 6? is an estimate duration. Note: Both can selected in the Task Mode Step-2: Plan the Tasks
  • 14. 14Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-2: Plan the Tasks 5. Link Tasks to show relationships Click the Task tab, in the View Group click Gantt Chart. Select the tasks that you want to link then click the Link Tasks button in the Schedule group, or move a mouse to bar chart press and drack down to tasks that you want to link. To change the default Finish-to-Start (FS), double click the link line and change.
  • 15. 15Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  Assignments are the associations between specific tasks and the resources needed to completed them. We can assign more than one resources to a tasks.  We can assign work resources (People), material (pipe/shell etc.) and cost (THB) to tasks. Step-3: Assign Resources
  • 16. 16Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-3: Assign Resources 1. Add Resources to Project Click the Task Tab, in the Views dropdown list select Resources Sheet. In the Resources Name filed, type the name of resources that we’ll use in this project.
  • 17. 17Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 2. Assign Resources to Tasks In the Resources Tab, Click Assign Resources the click resources name then click assign Step-3: Assign Resources
  • 18. 18Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-3: Assign Resources 3. Enter the Work Hours spending on Tasks After assign a resources to the Tasks, work hours automatically show in a Work. If PM prefer control a Working hours, it can be change in in Work Field. Entering Work reflects real world scheduling. Go to Gantt Chart, right click on column then click Insert Columns type "WORK” to select the Work Columns
  • 19. 19Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-3: Assign Resources 4. Know the Work Tasks Type After Assign a resources to Tasks, MS Project determine how to schedule the tasks based on the tasks type.(Manually tasks don’t use task type) durations may change as we assign resources to tasks. How tasks types work Work, duration and unit are determined by formula:- Work =Duration x Units
  • 20. 20Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-3: Assign Resources In a… If we revised Work If we revised Duration If we revised units Fixed units tasks Duration changes Work changes Duration changes Fixed work tasks Duration changes Units change Duration changes Fixed duration tasks Units change Work changes Work changes  To set a default task type for the entire project, click the options. Go to Schedule group, in the default task type box shown fixed units as a default, we can change to Fixed Duration or Fixed Work  To change the task type for an individual, go to tasks tab in properties group click information or to tasks name double click it will appear.
  • 21. 21Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-3: Assign Resources 5. Identify factors effecting task schedules We can use MS Project 2013 to help for understanding how changes one task can effect the rest of the project. Click the task tab then in the Schedule group click Inspect Task. A pane opens on the left showing the factors that affect the scheduling of selected task. Or double click in tasks name.
  • 22. 22Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  Create a baseline or interim plan is to compare between plan and actual.  Saving baseline plan enables to identify and solve discrepancy and plan more accurately for similar future projects. Step-4: Set the Project Baseline
  • 23. 23Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-4: Set the Project Base Line 1. Save the baseline plan After the plan is solidly in place for the finish date, budget and scope, we can submit a plan for approval. Once it has been approved, save the baseline plan. Click the Project tab, in Schedule group click Set Baseline
  • 24. 24Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-4: Set the Project Base Line 2.View baseline data in Gantt Chart views In Gantt chart view, move a mouse to gantt area, right click and select Bar Style. Name Appearance Show for Task Row From To Base Plan (Custom) Select bar shave and color Select Normal 2 or 3 Baseline Start Baseline finish
  • 25. 25Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-4: Set the Project Base Line 3. View Baseline in a Table Go to View tab, in Data group click to Table and select Variance or insert columns with custom field.
  • 26. 26Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  Updating the progress is the only way to ensure it stays on tracks as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress and communicating project information.  MS Project 2013 tracks 3 sets of date: Current, Baseline and Actual. When we set the baseline, current = baseline. when a task is 100% complete, current=actual. Step-5: Update Progress
  • 27. 27Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-5: Update Progress 1. Manage Change Managing changes involves modifying duration, date, dependencies, resource assignment or tasks based on requested changes or new information. Keep the current fields up to date and compare to baseline.
  • 28. 28Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-5: Update Progress 2. Track actual date and duration It’s the best to decide on a single method for tracking progress. We can enter percentage complete, actual start and finish dates, actual remaining durations or actual and remaining work. Click the Task tab, select the task that we want to enter actual progress. In the Schedule group select the amount of progress done on the tasks. Default: 0%, 25%, 50%, 75%, 100% Note: we can put a number direct to %Complete field
  • 29. 29Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-5: Update Progress 3. Track Actual Hours and Cost If we want to enter actual and remaining work hours or costs, use tracking table. Click View tab, in Data group point Table and select Tracking. Enter progress data in the Act. Work or Act. Cost field for the task. Program is determine if we put the actual start and actual finish or % Complete.
  • 30. 30Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  MS Project 2013 provide many ways of built in report, but for us we have to create a customize report by using S-Curve Reports. Step-6: View Report Information
  • 31. 31Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-6: View Report Information 1. Select a View MS Project 2013 has old and new views to help you to see project information and report it to others. Click the View Tab, in either the Task Views group or Resources Views group, select the view you want to use. There’re many view but most usful ones include:- • Team planner View • Timeline View • Gantt Chart View • Calendar View
  • 32. 32Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-6: View Report Information 2. Customize a View Select the view you want to customize and then on the Format tab click the type of view element you want to change, such as the bar style on the Gantt Chart or gridlines and time scales of any views. Tips & Tricks, if you want to filter, sort or group tasks prior to printing, click the View tab and then in the Data group, click sort, Filter or Group options.
  • 33. 33Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-6: View Report Information 3. Print a View or Report Set up the current view that we want it to look when printed. Click the File Tab and then click Print. A preview part of the view to see the actual size of the view as it will be printed.
  • 34. 34Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-6: View Report Information 4. Generate a Report In Report tab has many report to view information of project but we’re intent to create the S-Curve by using MS Project as a tools, we’ll focus on how to do it. Click the Report tab, go to View reports group, select Customer
  • 35. 35Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  In the field list (right hand) Select Category to Time.
  • 36. 36Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  Then Select Field go to Work, click Actual Work and Cumulative Actual Work only.
  • 37. 37Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  The Click on Baseline, click Baseline Cumulative Work, just only one.
  • 38. 38Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  In chart area Right click to change chart type.  Select Chart type to Combo.
  • 39. 39Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  In the Change Chart Type dialog in Series Name choose All Cumulative (Actual & Baseline) Chart type to Line Type.  Actual Work chart type to Clustered Column and Click Secondary Axis
  • 40. 40Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  In Field List, in Tasks Tab look at Select Category, click Edit customize time from Days to Weeks and change format as you like.
  • 41. 41Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  In design Tab, choose format color as you like.  In Chart Layout select Layout No 5 to show Data
  • 42. 42Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-7: Step by Step to S-Curve  Final as just Fonts size and others
  • 43. 43Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-8: Export Data to Excel 1. Visual Report Go to Report tab, select on Visual reports Export. Select template dialog show, go to Task Usage tab, move a mouse on Cash Flow Report template, then click Edit Template. In Visual Report-Field Picker is pop up, in Available Field, select Base line Cumulative Work and Cumulative Actual Work add to selected Fields.
  • 44. 44Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-8: Export Data to Excel 2. Analyze Data in Pivot Table In PivotTable Fields, select only Actual Work, Baseline Cumulative work and Cumulative Actual Work.
  • 45. 45Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-8: Export Data to Excel 3. Custom Charts in Excel In Pivot Tab Fields, select only Baseline Cumulative Work, Cumulative Actual Work and Actual Work. In Chart Area Right Click mouse select Combo chart, then All cumulative change type to Line only Actual Work to Clustter Column.
  • 46. 46Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-8: Export Data to Excel
  • 47. 47Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037  Just because your project is almost finished doesn’t mean that your work is done.  We still need to solve any final project detail and customer acceptance for final deliverables.  Conduct a “Lessons Learned” session, recording information about areas for improvement and best practices.  Make any final update to project plan.  Finally archive the project plan according to our organization’s guideline. Step-9: Close the Project
  • 48. 48Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-9: Close the Project 1. Create a Final Report Click the Report tab, click Visual Reports to see project data as a Pivot Table report in Excel 2013 or Pivot Diagram view in Visio professional 2013 We can also view basic reports that don’t require Excel or Visio. Click Report Tab many report category available to view depend on how we want to views.
  • 49. 49Author: Ong-Art Sanpinit Charter Engineer วฟก. 1037 Step-9: Close the Project 2. Save a Project as a Template After completing a project, we have to leverage what we’ve learned in the project by making it as a template for future projects. Click the File tab and Save As and then in the Save As Type box click Template.