Dr Ian Cammack
i.j.Cammack@soton.ac.uk
MSc Project Management
MANG6310: Breakdown Structures
Definition
• “A deliverable-orientated hierarchical decomposition of the work to be
executed by the project team to accomplish the project objectives and create
the required deliverables. It organizes and defines the total scope of the
project. Each descending level represents an increasingly detailed definition
of the project work …”
PMI 2006 p. 3
Example of WBS
Purpose
• Definition of project’s scope / assists communication
• Balances control needs with an appropriate and effective level of detailed
project data
• Framework for specifying performance objectives / estimating & change
control
• Framework for status & progress reports. It supports quest for accountability
• Communication between project manager and stakeholder
Key principles
• All the work done by both internal & external participants
• All deliverables - internal, external & interim
• 100% rule:
– the sum of the work at a ‘child’ level must equal 100% of the work
represented by the ‘parent’
– Do not include work outside the scope of approved work
Work breakdown structures
• Level 1 is always a single element
• Level 2 high level deliverables / products. Defined by nouns & numbered #.#
(e.g. 1.1)
• Level 3 decomposes level 2 into sub-products or into work processes. Defined
by nouns for products and nouns + verbs for processes. #.#.# (e.g. 1.1.1)
• Level 4 decomposes processes into activities #.#.#.# (e.g. 1.1.1.1)
Presentation 1, 2 or 3
Presentation 4
Presentation 5
Presentation 6: WBS Dictionary
Whichever you choose to use make sure it is clear
- font at least 10 pt (A4 page)
- Can be printed out clearly in monochrome (black, grey & white)
Project
Deliverables
Product
Elements
Process
Activities
Product
Breakdown
Structure
(PBS)
Work
Breakdown
Structure
(WBS)
WBS Layers
Definitions
• Deliverable (Product):an actual entity required by the project; should
be specified within the Statement of Requirements
• Process: a series of actions that produce a change or development
• Activities / Tasks: a specific deed, piece of work required to be done
Quality criteria for breakdown structures
• Deliverable orientated grouping
• Defines scope of the work
• Communicates scope to all stakeholders
• 100% of work inc. internal, external and interim deliverables
• Level of decomposition (depth) is driven by risk
• Each element can be assigned to accountable individual / unit
• 100% rule for ‘parent’ : ‘child’ groups
• Nouns for deliverables (upper levels)
• Nouns & Verb descriptors for processes / tasks (lower levels)
• Uses a coding scheme to indicate hierarchical structure
• Create by the people doing the work
• Constructed with technical input from subject experts
• Constructed in an iterative fashion
• Updated in accordance with project change control
How Deep Do We Go ?
• 3 or 4 levels should be sufficient BUT it depends on
– Level of risk
– Level of control - what you define you have to control
– Need for estimating accuracy
– Value of the work
– Hours required.
• “Ideal work packages are 80 hours [effort] and less than 2-4 weeks duration”
(Kerzner 1998 p.548)
Contractors WBS
Bid packages
•Contractors develop WBS aligned
to owners WBS
•Integrate many subcontractors
WBS into master plan
•Owner tracks against contractors
WBS
Risks from a poorly constructed WBS
• Incomplete project definition
• Unclear work assignments, goals / deliverables
• Scope creep
• Budget / schedule overrun (as they were not based on all the work)
• Missing work items
How to ….
• Has the project been defined in a charter, mandate, statement of
requirements etc.?
• Is the WBS being developed by the people doing the work?
• What are the projects component parts?
• Have all deliverables / products been identified (internal / external &
interim)?
• What needs to be done?
• Has the project been thought through? Are products decomposed to
processes?
• Has work associated with managing risk been identified?
Additional information
• Problem diagnostic checklist from the PMI practice standard for WBS (double
click on gold box)
• Example of a WBS from the PMI practice standard (double click on blue box)
Post Script: Work Package Description
• Date
• Person authorised : individual with whom the agreement has been
made
• Work Package Description:
• Product Description: attach the relevant product description(s)
• Techniques / process / procedures to be used
• Interfaces with other products to be satisfied
• Interfaces with other people
• Joint agreement on effort, cost, start & end dates
• Constraints
• Reporting arrangements / Problem handling escalation
OGC 2005 p.391-392

More Related Content

PDF
What is a Work Breakdown Structure?
PPT
Work Breakdown Structure
PPTX
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
PDF
Integrated Master Plan Development
PPT
WBS presentation
PDF
Work Breakdown Structure
PPTX
Project Mangement
PDF
Work Breakdown Structure PMI.pdf
What is a Work Breakdown Structure?
Work Breakdown Structure
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
Integrated Master Plan Development
WBS presentation
Work Breakdown Structure
Project Mangement
Work Breakdown Structure PMI.pdf

What's hot (20)

PPTX
Primavara
PPTX
Earned Value Analysis
PPT
Project cost management-slides
PPTX
Smart project management - Best Practices to Manage Project effectively
PPTX
Work Breakdown Structures (WBS)
PPTX
ppt for primevera
PPTX
Project Time Management
PPTX
Work breakdown structure
PPTX
PROJECT SCHEDULE
PPT
Primavera Training P6
PPTX
03 Construction Project Planning and Scheduling
PPTX
Project management
PDF
Primavera P6 manual
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PPTX
Work breakdown structure in project management ppt by kiran j
PPTX
Construction Delay Analysis, Simplified
PPTX
Earned value analysis (1)
PDF
Primavera - Tutorial
PPTX
Project Management Steps
Primavara
Earned Value Analysis
Project cost management-slides
Smart project management - Best Practices to Manage Project effectively
Work Breakdown Structures (WBS)
ppt for primevera
Project Time Management
Work breakdown structure
PROJECT SCHEDULE
Primavera Training P6
03 Construction Project Planning and Scheduling
Project management
Primavera P6 manual
Extension of time (E.O.T) By Ahmed Ibarhim
Work breakdown structure in project management ppt by kiran j
Construction Delay Analysis, Simplified
Earned value analysis (1)
Primavera - Tutorial
Project Management Steps
Ad

Viewers also liked (7)

DOCX
Project termination
PPTX
Work breakdown Structure
PPTX
work breakdown structure
PPTX
Work breakdown structure
PDF
Work Breakdown Structure
PPTX
Project control. Management
PPTX
Work breakdown structure ppt
Project termination
Work breakdown Structure
work breakdown structure
Work breakdown structure
Work Breakdown Structure
Project control. Management
Work breakdown structure ppt
Ad

Similar to Work breakdown structures (20)

PPT
Unit 3 WorkBreakdownStructure.ppt related to project management
PPTX
5. Work Breakdown Structure-- slides for help 1.pptx
PDF
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
PDF
Workbreakdownstructureppt 130410021152-phpapp02
PPT
PM Session 4
PPTX
PROJECT MANAGEMENT Work Breakdown Structure
PPT
Chapter 2 Work Break down Structure1.ppt
PPT
Chapter 2 Work Break down Structure (1).ppt
PPTX
Babu 143
DOCX
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
PPT
Chap004
PPT
Chap004
DOCX
PositioningPositioning of Product or ServiceParis based weig.docx
PPTX
Work breakdown structurep
PPTX
Prince.wbs.sow
PPTX
Work breakdown structure (WBS) PRESENTATION.pptx
DOCX
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
PPT
Work breakdownstructure
DOCX
1 Work Breakdown Structures (WBS) 2 WBS .docx
Unit 3 WorkBreakdownStructure.ppt related to project management
5. Work Breakdown Structure-- slides for help 1.pptx
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
Workbreakdownstructureppt 130410021152-phpapp02
PM Session 4
PROJECT MANAGEMENT Work Breakdown Structure
Chapter 2 Work Break down Structure1.ppt
Chapter 2 Work Break down Structure (1).ppt
Babu 143
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
Chap004
Chap004
PositioningPositioning of Product or ServiceParis based weig.docx
Work breakdown structurep
Prince.wbs.sow
Work breakdown structure (WBS) PRESENTATION.pptx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
Work breakdownstructure
1 Work Breakdown Structures (WBS) 2 WBS .docx

More from Ian Cammack (19)

PPTX
Human Factors in Project Management Session 6 leadership issue 1
PPTX
Human Factors in Project Management Session 5 team working issue 1
PPTX
Human Factors in Project Management Session 4 motivation issue 1
PPTX
Human factors in project Management Session 3 communications issue 1
PPTX
Human Factors in Project Management: Stakeholder Management
PPTX
Human Factors in Project Management Session 1 projects are about people issue 1
PPT
Bj research session 10 presenting your findings
PPT
Bj research session 9 analysing quantitative
PDF
Bj research session 8 gathering quantitative data
PPT
Business research Methods session 7 qualitative techniques
PPT
Business Research Methods session 6 research design
PPT
Business Research Methods session 3
PPT
Business Research Methods session 2
PPT
Research Methods for Business Students
PPTX
Introduction to Project Management
PPTX
Product based planning
PPTX
Project Selection
PPTX
Project requirements management
PPTX
Goal directed project management
Human Factors in Project Management Session 6 leadership issue 1
Human Factors in Project Management Session 5 team working issue 1
Human Factors in Project Management Session 4 motivation issue 1
Human factors in project Management Session 3 communications issue 1
Human Factors in Project Management: Stakeholder Management
Human Factors in Project Management Session 1 projects are about people issue 1
Bj research session 10 presenting your findings
Bj research session 9 analysing quantitative
Bj research session 8 gathering quantitative data
Business research Methods session 7 qualitative techniques
Business Research Methods session 6 research design
Business Research Methods session 3
Business Research Methods session 2
Research Methods for Business Students
Introduction to Project Management
Product based planning
Project Selection
Project requirements management
Goal directed project management

Recently uploaded (20)

PDF
Basic Mud Logging Guide for educational purpose
PDF
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
TR - Agricultural Crops Production NC III.pdf
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
Complications of Minimal Access Surgery at WLH
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
Business Ethics Teaching Materials for college
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPTX
Cell Structure & Organelles in detailed.
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Pre independence Education in Inndia.pdf
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
Final Presentation General Medicine 03-08-2024.pptx
Basic Mud Logging Guide for educational purpose
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
TR - Agricultural Crops Production NC III.pdf
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
Complications of Minimal Access Surgery at WLH
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
Renaissance Architecture: A Journey from Faith to Humanism
Business Ethics Teaching Materials for college
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Cell Structure & Organelles in detailed.
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Pre independence Education in Inndia.pdf
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
VCE English Exam - Section C Student Revision Booklet
Final Presentation General Medicine 03-08-2024.pptx

Work breakdown structures

  • 1. Dr Ian Cammack i.j.Cammack@soton.ac.uk MSc Project Management MANG6310: Breakdown Structures
  • 2. Definition • “A deliverable-orientated hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work …” PMI 2006 p. 3
  • 4. Purpose • Definition of project’s scope / assists communication • Balances control needs with an appropriate and effective level of detailed project data • Framework for specifying performance objectives / estimating & change control • Framework for status & progress reports. It supports quest for accountability • Communication between project manager and stakeholder
  • 5. Key principles • All the work done by both internal & external participants • All deliverables - internal, external & interim • 100% rule: – the sum of the work at a ‘child’ level must equal 100% of the work represented by the ‘parent’ – Do not include work outside the scope of approved work
  • 7. • Level 1 is always a single element • Level 2 high level deliverables / products. Defined by nouns & numbered #.# (e.g. 1.1) • Level 3 decomposes level 2 into sub-products or into work processes. Defined by nouns for products and nouns + verbs for processes. #.#.# (e.g. 1.1.1) • Level 4 decomposes processes into activities #.#.#.# (e.g. 1.1.1.1)
  • 11. Presentation 6: WBS Dictionary Whichever you choose to use make sure it is clear - font at least 10 pt (A4 page) - Can be printed out clearly in monochrome (black, grey & white)
  • 13. Definitions • Deliverable (Product):an actual entity required by the project; should be specified within the Statement of Requirements • Process: a series of actions that produce a change or development • Activities / Tasks: a specific deed, piece of work required to be done
  • 14. Quality criteria for breakdown structures • Deliverable orientated grouping • Defines scope of the work • Communicates scope to all stakeholders • 100% of work inc. internal, external and interim deliverables • Level of decomposition (depth) is driven by risk • Each element can be assigned to accountable individual / unit • 100% rule for ‘parent’ : ‘child’ groups • Nouns for deliverables (upper levels) • Nouns & Verb descriptors for processes / tasks (lower levels) • Uses a coding scheme to indicate hierarchical structure • Create by the people doing the work • Constructed with technical input from subject experts • Constructed in an iterative fashion • Updated in accordance with project change control
  • 15. How Deep Do We Go ? • 3 or 4 levels should be sufficient BUT it depends on – Level of risk – Level of control - what you define you have to control – Need for estimating accuracy – Value of the work – Hours required. • “Ideal work packages are 80 hours [effort] and less than 2-4 weeks duration” (Kerzner 1998 p.548)
  • 16. Contractors WBS Bid packages •Contractors develop WBS aligned to owners WBS •Integrate many subcontractors WBS into master plan •Owner tracks against contractors WBS
  • 17. Risks from a poorly constructed WBS • Incomplete project definition • Unclear work assignments, goals / deliverables • Scope creep • Budget / schedule overrun (as they were not based on all the work) • Missing work items
  • 18. How to …. • Has the project been defined in a charter, mandate, statement of requirements etc.? • Is the WBS being developed by the people doing the work? • What are the projects component parts? • Have all deliverables / products been identified (internal / external & interim)? • What needs to be done? • Has the project been thought through? Are products decomposed to processes? • Has work associated with managing risk been identified?
  • 19. Additional information • Problem diagnostic checklist from the PMI practice standard for WBS (double click on gold box) • Example of a WBS from the PMI practice standard (double click on blue box)
  • 20. Post Script: Work Package Description • Date • Person authorised : individual with whom the agreement has been made • Work Package Description: • Product Description: attach the relevant product description(s) • Techniques / process / procedures to be used • Interfaces with other products to be satisfied • Interfaces with other people • Joint agreement on effort, cost, start & end dates • Constraints • Reporting arrangements / Problem handling escalation OGC 2005 p.391-392