ID Task Name Duration Start Finish
1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14
2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14
3 Array Area and General Works 110 days Sat 4/5/14 Wed 7/23/14
4 Civil Works 93 days Sat 4/5/14 Sun 7/6/14
5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14
6 Marking and Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14
7 Foundation and Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14
8 Foundation and Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14
9 Construction of Internal Roads 5 days Tue 4/22/14 Sat 4/26/14
10 Foundation Marking for Structures 5 days Mon 4/21/14 Fri 4/25/14
11 Excavation for Structure Foundation 20 days Tue 4/22/14 Sun 5/11/14
12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu 5/22/14
13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14
14 Cable trench 7 days Fri 5/23/14 Thu 5/29/14
15 Construction of Water Collection Tank 10 days Fri 5/23/14 Sun 6/1/14
16 Construction of Drainage system 30 days Tue 5/27/14 Wed 6/25/14
17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14
18 Lightening Arrester Foundation 5 days Sun 6/22/14 Thu 6/26/14
19 External Lighting Foundation 15 days Sun 6/22/14 Sun 7/6/14
20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14
21 Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14
22 Electrical Works 97 days Thu 4/17/14 Wed 7/23/14
23 Structure 57 days Thu 4/17/14 Fri 6/13/14
24 Purchase Order for Structure 0 days Thu 4/17/14 Thu 4/17/14
25 Payment for Structure 0 days Thu 4/24/14 Thu 4/24/14
26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14
27 Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14
28 PV Module 52 days Fri 4/25/14 Sun 6/15/14
29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14
30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14
31 Receiving of PV Module 30 days Fri 5/2/14 Sun 6/1/14
32 Installation of PV Module 15 days Sun 6/1/14 Sun 6/15/14
33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14
34 Purchase Order for SMB 0 days Mon 4/21/14 Mon 4/21/14
35 Payment for SMB 7 days Mon 4/21/14 Mon 4/28/14
36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14
37 Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14
38 Inverter 69 days Sat 4/19/14 Thu 6/26/14
39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat 4/19/14
40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14
41 Receiving of Inverter 60 days Sat 4/26/14 Wed 6/25/14
42 Installation of Inverter 2 days Wed 6/25/14 Thu 6/26/14
43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14
44 Purchase Order for DC Cable 0 days Tue 4/29/14 Tue 4/29/14
45 Payment for DC Cable 7 days Tue 4/29/14 Tue 5/6/14
46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14
47 Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14
48 Termination of DC Cable 5 days Fri 6/27/14 Tue 7/1/14
49 OFC 60 days Thu 5/1/14 Sun 6/29/14
50 Purchase Order for OFC 0 days Thu 5/1/14 Thu 5/1/14
51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14
52 Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14
53 Laying of OFC 5 days Sun 6/22/14 Fri 6/27/14
54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14
55 CCTV SYSTEM 40 days Sat 5/31/14 Wed 7/9/14
56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat 5/31/14
57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14
58 Receiving of CCTV 30 days Sat 6/7/14 Mon 7/7/14
59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14
60 Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14
61 Purchase order for Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14
62 Payment for Lightening Arrestor 7 days Sat 5/31/14 Sat 6/7/14
63 Receiving of Lightening Arrestor 30 days Sat 6/7/14 Mon 7/7/14
64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu 7/10/14
65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14
66 Purchase Order for SCADA System 0 days Tue 5/13/14 Tue 5/13/14
67 Payment for SCADA System 7 days Tue 5/13/14 Tue 5/20/14
68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14
/1 4/2
4/5 4/19
4/15 5/14
4/18 4/22
4/18 4/22
4/22 4/26
4/21 4/25
4/22 5/11
4/23 5/22
5/3 5/7
5/23 5/29
5/23 6/1
5/27 6/25
5/23 5/25
6/22 6/26
6/22 7/6
6/22 6/26
6/12 6/16
4/17
4/24
4/25 5/19
5/30 6/13
4/25
4/25 5/2
5/2 6/1
6/1 6/15
4/21
4/21 4/28
4/28 5/28
5/28 5/31
4/19
4/19 4/26
4/26 6/25
6/25 6/26
4/29
4/29 5/6
5/6 6/20
6/20 6/27
6/27 7/1
5/1
5/1 5/8
5/8 6/22
6/22 6/27
6/27 6/29
5/31
5/31 6/7
6/7 7/7
7/7 7/9
5/31
5/31 6/7
6/7 7/7
7/7 7/10
5/13
5/13 5/20
5/20 7/19
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 1
Project: Template PIS
Date: Wed 3/19/14
ID Task Name Duration Start Finish
69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14
70 External Lighting 57 days Wed 5/21/14 Wed 7/16/14
71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14
72 Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14
73 Receiving of Lighting System 40 days Wed 5/28/14 Mon 7/7/14
74 Installation and Termination of Lighting System 10 days Mon 7/7/14 Wed 7/16/14
75 Array Earthing 57 days Sun 5/18/14 Sun 7/13/14
76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14
77 Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14
78 Receiving of Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14
79 Array Earthing Installation and Connection 10 days Fri 7/4/14 Sun 7/13/14
80 Main Control Room & Substation 86 days Thu 4/24/14 Fri 7/18/14
81 Civil Work in MCR & Substation 60 days Sat 4/26/14 Tue 6/24/14
82 Marking 2 days Sat 4/26/14 Sun 4/27/14
83 Excavation 3 days Mon 4/28/14 Wed 4/30/14
84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14
85 Brick work 15 days Wed 5/21/14 Wed 6/4/14
86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14
87 Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14
88 Windows & Doors Fixing 7 days Thu 6/12/14 Wed 6/18/14
89 Painting work 7 days Thu 6/12/14 Wed 6/18/14
90 Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14
91 Power and Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14
92 Switch Yard Earthing Mat Construction 7 days Fri 5/16/14 Thu 5/22/14
93 Switch Yard Equipment Foundation 15 days Fri 5/23/14 Fri 6/6/14
94 Foundation for Transmission Towers 30 days Fri 5/23/14 Sat 6/21/14
95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14
96 Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14
97 Purchase Order for Transformer 0 days Thu 4/24/14 Thu 4/24/14
98 Payment for Transformer 7 days Thu 4/24/14 Thu 5/1/14
99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14
100 Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14
101 33 kV bay station 73 days Tue 4/29/14 Thu 7/10/14
102 Purchase Order for VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14
103 Payment for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14
104 Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14
105 Installation of Equipments 7 days Fri 6/27/14 Thu 7/3/14
106 Termination of Conductors 7 days Fri 7/4/14 Thu 7/10/14
107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14
108 Purchase Order for HT Panels 0 days Fri 5/9/14 Fri 5/9/14
109 Payment for HT Panels 7 days Fri 5/9/14 Fri 5/16/14
110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14
111 Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14
112 LT Panels 61 days Fri 5/9/14 Tue 7/8/14
113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14
114 Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14
115 Receiving of LT Panels 50 days Fri 5/16/14 Sat 7/5/14
116 Installation of LT Panels 4 days Sat 7/5/14 Tue 7/8/14
117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14
118 Purchase Order for LT Cable 0 days Sat 5/3/14 Sat 5/3/14
119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14
120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14
121 Laying of LT Cable 5 days Sun 6/29/14 Thu 7/3/14
122 Terination of LT Cable 5 days Wed 7/9/14 Sun 7/13/14
123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14
124 Purchase Order for HT Cable 0 days Mon 5/5/14 Mon 5/5/14
125 Payment for HT Cable 7 days Mon 5/5/14 Mon 5/12/14
126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14
127 Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14
128 Termination of HT Cable 5 days Wed 7/9/14 Sun 7/13/14
129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14
130 Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14
131 Payment for Control Cable 7 days Sat 5/10/14 Sat 5/17/14
132 Receiving of Control Cables 45 days Sat 5/17/14 Tue 7/1/14
133 Laying of Control Cable 4 days Tue 7/1/14 Fri 7/4/14
134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14
135 Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14
136 Purchase Order for LA 0 days Wed 5/21/14 Wed 5/21/14
7/19 7/23
5/21
5/21 5/28
5/28 7/7
7/7 7/16
5/18
5/18 5/25
5/25 7/4
7/4 7/13
4/26 4/27
4/28 4/30
5/1 5/20
5/21 6/4
6/5 6/11
6/12 6/18
6/12 6/18
6/12 6/18
6/15 6/24
5/6 5/20
5/16 5/22
5/23 6/6
5/23 6/21
4/24
4/24 5/1
5/1 6/30
6/30 7/4
4/29 5/1
5/1 5/8
5/8 6/27
6/27 7/3
7/4 7/10
5/9
5/9 5/16
5/16 7/5
7/5 7/8
5/9
5/9 5/16
5/16 7/5
7/5 7/8
5/3
5/3 5/10
5/10 6/29
6/29 7/3
7/9 7/13
5/5
5/5 5/12
5/12 7/1
7/1 7/5
7/9 7/13
5/10
5/10 5/17
5/17 7/1
7/1 7/4
7/9 7/11
5/21
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 2
Project: Template PIS
Date: Wed 3/19/14
ID Task Name Duration Start Finish
137 Payment for LA 7 days Wed 5/21/14 Wed 5/28/14
138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14
139 Installation of LA 5 days Tue 6/17/14 Sat 6/21/14
140 Battery System 57 days Fri 5/9/14 Fri 7/4/14
141 Purchase Order for Battery Bank 0 days Fri 5/9/14 Fri 5/9/14
142 Payment for Battery Bank 7 days Fri 5/9/14 Fri 5/16/14
143 Receiving of Battery Bank 45 days Fri 5/16/14 Mon 6/30/14
144 Installation of Battery Bank 5 days Mon 6/30/14 Fri 7/4/14
145 Switch Yard Earthing 30 days Sat 4/26/14 Sun 5/25/14
146 Purchase Order for Earthing Equipments 0 days Sat 4/26/14 Sat 4/26/14
147 Payment for Earthing Equipments 7 days Sat 4/26/14 Sat 5/3/14
148 Receiving of Earthing Equipments 20 days Sat 5/3/14 Fri 5/23/14
149 Installation and Connection 3 days Fri 5/23/14 Sun 5/25/14
150 Internal Lightning System 42 days Mon 5/26/14 Sun 7/6/14
151 Purchase Order for Poles and Lights 0 days Mon 5/26/14 Mon 5/26/14
152 Payment for Lighting System 7 days Mon 5/26/14 Mon 6/2/14
153 Receiving of Lighting System 30 days Mon 6/2/14 Wed 7/2/14
154 Installation and Termination of Lighting System 5 days Wed 7/2/14 Sun 7/6/14
155 Misc. Items(SDB,Feeders,ACDB,Industrial Socket) 67 days Tue 4/29/14 Fri 7/4/14
156 Purchase Order for Misc.Items 0 days Tue 4/29/14 Tue 4/29/14
157 Payment for Misc.Items 7 days Tue 4/29/14 Tue 5/6/14
158 Receiving of Misc.Items 50 days Tue 5/6/14 Wed 6/25/14
159 Installation and Termination of Misc.Items 10 days Wed 6/25/14 Fri 7/4/14
160 Weather monitoring system 42 days Sat 6/7/14 Fri 7/18/14
161 Purchase Order for WMS 0 days Sat 6/7/14 Sat 6/7/14
162 Payment for WMS 7 days Sat 6/7/14 Sat 6/14/14
163 Receiving of WMS 30 days Sat 6/14/14 Mon 7/14/14
164 Installation of WMS 5 days Mon 7/14/14 Fri 7/18/14
165 Transmission Line 57 days Fri 5/16/14 Fri 7/11/14
166 Purchase Order for Transmission Line Structures & Equipments0 days Fri 5/16/14 Fri 5/16/14
167 Payment for Transmission Line Structures & Equipments7 days Fri 5/16/14 Fri 5/23/14
168 Receiving of Structures and Equipments 30 days Fri 5/23/14 Sun 6/22/14
169 Installation and Stringing of Equipments 20 days Sun 6/22/14 Fri 7/11/14
170 Fire alarm system works 5 days Wed 7/9/14 Sun 7/13/14
171 Testing and commissioning 10 days Sat 7/19/14 Mon 7/28/14
172 Proposed Commercial Operation Date 1 day Tue 7/29/14 Tue 7/29/14
5/21 5/28
5/28 6/17
6/17 6/21
5/9
5/9 5/16
5/16 6/30
6/30 7/4
4/26
4/26 5/3
5/3 5/23
5/23 5/25
5/26
5/26 6/2
6/2 7/2
7/2 7/6
4/29
4/29 5/6
5/6 6/25
6/25 7/4
6/7
6/7 6/14
6/14 7/14
7/14 7/18
5/16
5/16 5/23
5/23 6/22
6/22 7/11
7/9 7/13
7/19 7/2
7/29 7
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 3
Project: Template PIS
Date: Wed 3/19/14

More Related Content

PDF
Drawings & Documents Required for Solar Projects
PDF
Phases of Construction - Solar Project
PPTX
Guide to Solar Project Implementation
PPTX
1 MW solar Power plant project Scheduling and Tracking
PPT
Solar Project Management
PDF
Engineering Drawings required for Solar Projects
PPTX
10 MW Solar PV power Plant - CPM & PERT, Design
DOCX
10 mw solar power plant
Drawings & Documents Required for Solar Projects
Phases of Construction - Solar Project
Guide to Solar Project Implementation
1 MW solar Power plant project Scheduling and Tracking
Solar Project Management
Engineering Drawings required for Solar Projects
10 MW Solar PV power Plant - CPM & PERT, Design
10 mw solar power plant

What's hot (20)

PDF
Solar Photovoltaic Power Plant: Best Practices
PDF
Developing Solar Projects
PDF
Gensol Rooftop EPC - Steps & Quality Management
PPTX
Project Proposal on 10 MW Solar PV Power Plant
PDF
Gensol - EPC Services
PDF
Technical Risks in Solar PV Projects 18.03.18
PDF
Epc project interdepency and Work Flow- promo
PPTX
Solar Power Plant Procurements
PDF
Project master schedule daughter station cng mini plant
PPT
Solar Power Project Development
PDF
Gensol detailed engineering services
PDF
List of Clearances for Solar Project
PDF
Roofsol Energy - O&M Presentation
PDF
PV solar Design and Installtion
PPTX
Study of Large Scale Grid interactive Solar PV power plant
PDF
Design Checklist_Electrical
PPT
Solar Power Plant System Sizing
PDF
Economics of Solar Park
PDF
WORKFLOW
PDF
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Solar Photovoltaic Power Plant: Best Practices
Developing Solar Projects
Gensol Rooftop EPC - Steps & Quality Management
Project Proposal on 10 MW Solar PV Power Plant
Gensol - EPC Services
Technical Risks in Solar PV Projects 18.03.18
Epc project interdepency and Work Flow- promo
Solar Power Plant Procurements
Project master schedule daughter station cng mini plant
Solar Power Project Development
Gensol detailed engineering services
List of Clearances for Solar Project
Roofsol Energy - O&M Presentation
PV solar Design and Installtion
Study of Large Scale Grid interactive Solar PV power plant
Design Checklist_Electrical
Solar Power Plant System Sizing
Economics of Solar Park
WORKFLOW
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Ad

Similar to MS Projects - 10 MW Implementation Schedule (20)

PDF
POW STTF 1 2023 (PT. SAM)NEW.pdf
PDF
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
PDF
Proposed Implementation Schedule for Chint.pdf
PDF
Pilkinton tenant improvement schedule
PDF
Hu, Maria (Yue) Assign 2 B
PDF
MS project Sample gantt chart
PDF
Engineering Design Center Project Schedule
PDF
Project plan in phases if a waterfall project
PDF
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
PDF
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
PDF
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
PDF
PDF
Jadwal Pelaksanaan PPI.pdf
PDF
Northwestern AU+Automation Timeline REV6 6-15-12
PDF
Northwestern AU+Automation Timeline REV6 6-15-12
PDF
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
PDF
PDF
MOL Schedule about health and environment
PDF
How To manuver microsoft project easily.
POW STTF 1 2023 (PT. SAM)NEW.pdf
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
Proposed Implementation Schedule for Chint.pdf
Pilkinton tenant improvement schedule
Hu, Maria (Yue) Assign 2 B
MS project Sample gantt chart
Engineering Design Center Project Schedule
Project plan in phases if a waterfall project
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Jadwal Pelaksanaan PPI.pdf
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
MOL Schedule about health and environment
How To manuver microsoft project easily.
Ad

More from Gensol Engineering Limited (20)

PDF
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
PDF
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
PDF
Gensol Engineering Limited - Investor Deck_26.09.2019
PDF
Electric Vehicles - Tax Benefits & Incentives_20.09.19
PDF
Phases of Construction & Erection for Wind Power Project_03 09 2019
PDF
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
PDF
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
PDF
List of Solar PV Tenders Floated in India - 11.03.2019
PDF
List of successful bidders 11.03.2019
PDF
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
PDF
Module Price Trend Analysis
PDF
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
PDF
Comparison of Solar-Wind Hybrid Policies-07.02.2019
PDF
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
PDF
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
PDF
Emerging Opportunities - Wind Solar Hybrid System
PDF
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
PDF
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
PDF
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
PDF
Gensol's Lender Engineer Credentials - 20.03.18
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Gensol Engineering Limited - Investor Deck_26.09.2019
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Phases of Construction & Erection for Wind Power Project_03 09 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
List of Solar PV Tenders Floated in India - 11.03.2019
List of successful bidders 11.03.2019
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Module Price Trend Analysis
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Emerging Opportunities - Wind Solar Hybrid System
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Gensol's Lender Engineer Credentials - 20.03.18

Recently uploaded (20)

PDF
Encapsulation theory and applications.pdf
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PDF
Network Security Unit 5.pdf for BCA BBA.
PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PPTX
sap open course for s4hana steps from ECC to s4
PDF
Electronic commerce courselecture one. Pdf
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPT
Teaching material agriculture food technology
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Spectral efficient network and resource selection model in 5G networks
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PDF
Review of recent advances in non-invasive hemoglobin estimation
PDF
Unlocking AI with Model Context Protocol (MCP)
PPTX
Programs and apps: productivity, graphics, security and other tools
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Assigned Numbers - 2025 - Bluetooth® Document
Encapsulation theory and applications.pdf
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
Network Security Unit 5.pdf for BCA BBA.
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
20250228 LYD VKU AI Blended-Learning.pptx
Reach Out and Touch Someone: Haptics and Empathic Computing
“AI and Expert System Decision Support & Business Intelligence Systems”
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
sap open course for s4hana steps from ECC to s4
Electronic commerce courselecture one. Pdf
Diabetes mellitus diagnosis method based random forest with bat algorithm
Teaching material agriculture food technology
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Spectral efficient network and resource selection model in 5G networks
The Rise and Fall of 3GPP – Time for a Sabbatical?
Review of recent advances in non-invasive hemoglobin estimation
Unlocking AI with Model Context Protocol (MCP)
Programs and apps: productivity, graphics, security and other tools
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Assigned Numbers - 2025 - Bluetooth® Document

MS Projects - 10 MW Implementation Schedule

  • 1. ID Task Name Duration Start Finish 1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14 2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14 3 Array Area and General Works 110 days Sat 4/5/14 Wed 7/23/14 4 Civil Works 93 days Sat 4/5/14 Sun 7/6/14 5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14 6 Marking and Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14 7 Foundation and Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14 8 Foundation and Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14 9 Construction of Internal Roads 5 days Tue 4/22/14 Sat 4/26/14 10 Foundation Marking for Structures 5 days Mon 4/21/14 Fri 4/25/14 11 Excavation for Structure Foundation 20 days Tue 4/22/14 Sun 5/11/14 12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu 5/22/14 13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14 14 Cable trench 7 days Fri 5/23/14 Thu 5/29/14 15 Construction of Water Collection Tank 10 days Fri 5/23/14 Sun 6/1/14 16 Construction of Drainage system 30 days Tue 5/27/14 Wed 6/25/14 17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14 18 Lightening Arrester Foundation 5 days Sun 6/22/14 Thu 6/26/14 19 External Lighting Foundation 15 days Sun 6/22/14 Sun 7/6/14 20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14 21 Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14 22 Electrical Works 97 days Thu 4/17/14 Wed 7/23/14 23 Structure 57 days Thu 4/17/14 Fri 6/13/14 24 Purchase Order for Structure 0 days Thu 4/17/14 Thu 4/17/14 25 Payment for Structure 0 days Thu 4/24/14 Thu 4/24/14 26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14 27 Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14 28 PV Module 52 days Fri 4/25/14 Sun 6/15/14 29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14 30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14 31 Receiving of PV Module 30 days Fri 5/2/14 Sun 6/1/14 32 Installation of PV Module 15 days Sun 6/1/14 Sun 6/15/14 33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14 34 Purchase Order for SMB 0 days Mon 4/21/14 Mon 4/21/14 35 Payment for SMB 7 days Mon 4/21/14 Mon 4/28/14 36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14 37 Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14 38 Inverter 69 days Sat 4/19/14 Thu 6/26/14 39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat 4/19/14 40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14 41 Receiving of Inverter 60 days Sat 4/26/14 Wed 6/25/14 42 Installation of Inverter 2 days Wed 6/25/14 Thu 6/26/14 43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14 44 Purchase Order for DC Cable 0 days Tue 4/29/14 Tue 4/29/14 45 Payment for DC Cable 7 days Tue 4/29/14 Tue 5/6/14 46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14 47 Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14 48 Termination of DC Cable 5 days Fri 6/27/14 Tue 7/1/14 49 OFC 60 days Thu 5/1/14 Sun 6/29/14 50 Purchase Order for OFC 0 days Thu 5/1/14 Thu 5/1/14 51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14 52 Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14 53 Laying of OFC 5 days Sun 6/22/14 Fri 6/27/14 54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14 55 CCTV SYSTEM 40 days Sat 5/31/14 Wed 7/9/14 56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat 5/31/14 57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14 58 Receiving of CCTV 30 days Sat 6/7/14 Mon 7/7/14 59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14 60 Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14 61 Purchase order for Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14 62 Payment for Lightening Arrestor 7 days Sat 5/31/14 Sat 6/7/14 63 Receiving of Lightening Arrestor 30 days Sat 6/7/14 Mon 7/7/14 64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu 7/10/14 65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14 66 Purchase Order for SCADA System 0 days Tue 5/13/14 Tue 5/13/14 67 Payment for SCADA System 7 days Tue 5/13/14 Tue 5/20/14 68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14 /1 4/2 4/5 4/19 4/15 5/14 4/18 4/22 4/18 4/22 4/22 4/26 4/21 4/25 4/22 5/11 4/23 5/22 5/3 5/7 5/23 5/29 5/23 6/1 5/27 6/25 5/23 5/25 6/22 6/26 6/22 7/6 6/22 6/26 6/12 6/16 4/17 4/24 4/25 5/19 5/30 6/13 4/25 4/25 5/2 5/2 6/1 6/1 6/15 4/21 4/21 4/28 4/28 5/28 5/28 5/31 4/19 4/19 4/26 4/26 6/25 6/25 6/26 4/29 4/29 5/6 5/6 6/20 6/20 6/27 6/27 7/1 5/1 5/1 5/8 5/8 6/22 6/22 6/27 6/27 6/29 5/31 5/31 6/7 6/7 7/7 7/7 7/9 5/31 5/31 6/7 6/7 7/7 7/7 7/10 5/13 5/13 5/20 5/20 7/19 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 1 Project: Template PIS Date: Wed 3/19/14
  • 2. ID Task Name Duration Start Finish 69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14 70 External Lighting 57 days Wed 5/21/14 Wed 7/16/14 71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14 72 Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14 73 Receiving of Lighting System 40 days Wed 5/28/14 Mon 7/7/14 74 Installation and Termination of Lighting System 10 days Mon 7/7/14 Wed 7/16/14 75 Array Earthing 57 days Sun 5/18/14 Sun 7/13/14 76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14 77 Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14 78 Receiving of Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14 79 Array Earthing Installation and Connection 10 days Fri 7/4/14 Sun 7/13/14 80 Main Control Room & Substation 86 days Thu 4/24/14 Fri 7/18/14 81 Civil Work in MCR & Substation 60 days Sat 4/26/14 Tue 6/24/14 82 Marking 2 days Sat 4/26/14 Sun 4/27/14 83 Excavation 3 days Mon 4/28/14 Wed 4/30/14 84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14 85 Brick work 15 days Wed 5/21/14 Wed 6/4/14 86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14 87 Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14 88 Windows & Doors Fixing 7 days Thu 6/12/14 Wed 6/18/14 89 Painting work 7 days Thu 6/12/14 Wed 6/18/14 90 Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14 91 Power and Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14 92 Switch Yard Earthing Mat Construction 7 days Fri 5/16/14 Thu 5/22/14 93 Switch Yard Equipment Foundation 15 days Fri 5/23/14 Fri 6/6/14 94 Foundation for Transmission Towers 30 days Fri 5/23/14 Sat 6/21/14 95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14 96 Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14 97 Purchase Order for Transformer 0 days Thu 4/24/14 Thu 4/24/14 98 Payment for Transformer 7 days Thu 4/24/14 Thu 5/1/14 99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14 100 Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14 101 33 kV bay station 73 days Tue 4/29/14 Thu 7/10/14 102 Purchase Order for VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14 103 Payment for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14 104 Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14 105 Installation of Equipments 7 days Fri 6/27/14 Thu 7/3/14 106 Termination of Conductors 7 days Fri 7/4/14 Thu 7/10/14 107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14 108 Purchase Order for HT Panels 0 days Fri 5/9/14 Fri 5/9/14 109 Payment for HT Panels 7 days Fri 5/9/14 Fri 5/16/14 110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14 111 Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14 112 LT Panels 61 days Fri 5/9/14 Tue 7/8/14 113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14 114 Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14 115 Receiving of LT Panels 50 days Fri 5/16/14 Sat 7/5/14 116 Installation of LT Panels 4 days Sat 7/5/14 Tue 7/8/14 117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14 118 Purchase Order for LT Cable 0 days Sat 5/3/14 Sat 5/3/14 119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14 120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14 121 Laying of LT Cable 5 days Sun 6/29/14 Thu 7/3/14 122 Terination of LT Cable 5 days Wed 7/9/14 Sun 7/13/14 123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14 124 Purchase Order for HT Cable 0 days Mon 5/5/14 Mon 5/5/14 125 Payment for HT Cable 7 days Mon 5/5/14 Mon 5/12/14 126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14 127 Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14 128 Termination of HT Cable 5 days Wed 7/9/14 Sun 7/13/14 129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14 130 Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14 131 Payment for Control Cable 7 days Sat 5/10/14 Sat 5/17/14 132 Receiving of Control Cables 45 days Sat 5/17/14 Tue 7/1/14 133 Laying of Control Cable 4 days Tue 7/1/14 Fri 7/4/14 134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14 135 Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14 136 Purchase Order for LA 0 days Wed 5/21/14 Wed 5/21/14 7/19 7/23 5/21 5/21 5/28 5/28 7/7 7/7 7/16 5/18 5/18 5/25 5/25 7/4 7/4 7/13 4/26 4/27 4/28 4/30 5/1 5/20 5/21 6/4 6/5 6/11 6/12 6/18 6/12 6/18 6/12 6/18 6/15 6/24 5/6 5/20 5/16 5/22 5/23 6/6 5/23 6/21 4/24 4/24 5/1 5/1 6/30 6/30 7/4 4/29 5/1 5/1 5/8 5/8 6/27 6/27 7/3 7/4 7/10 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/3 5/3 5/10 5/10 6/29 6/29 7/3 7/9 7/13 5/5 5/5 5/12 5/12 7/1 7/1 7/5 7/9 7/13 5/10 5/10 5/17 5/17 7/1 7/1 7/4 7/9 7/11 5/21 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 2 Project: Template PIS Date: Wed 3/19/14
  • 3. ID Task Name Duration Start Finish 137 Payment for LA 7 days Wed 5/21/14 Wed 5/28/14 138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14 139 Installation of LA 5 days Tue 6/17/14 Sat 6/21/14 140 Battery System 57 days Fri 5/9/14 Fri 7/4/14 141 Purchase Order for Battery Bank 0 days Fri 5/9/14 Fri 5/9/14 142 Payment for Battery Bank 7 days Fri 5/9/14 Fri 5/16/14 143 Receiving of Battery Bank 45 days Fri 5/16/14 Mon 6/30/14 144 Installation of Battery Bank 5 days Mon 6/30/14 Fri 7/4/14 145 Switch Yard Earthing 30 days Sat 4/26/14 Sun 5/25/14 146 Purchase Order for Earthing Equipments 0 days Sat 4/26/14 Sat 4/26/14 147 Payment for Earthing Equipments 7 days Sat 4/26/14 Sat 5/3/14 148 Receiving of Earthing Equipments 20 days Sat 5/3/14 Fri 5/23/14 149 Installation and Connection 3 days Fri 5/23/14 Sun 5/25/14 150 Internal Lightning System 42 days Mon 5/26/14 Sun 7/6/14 151 Purchase Order for Poles and Lights 0 days Mon 5/26/14 Mon 5/26/14 152 Payment for Lighting System 7 days Mon 5/26/14 Mon 6/2/14 153 Receiving of Lighting System 30 days Mon 6/2/14 Wed 7/2/14 154 Installation and Termination of Lighting System 5 days Wed 7/2/14 Sun 7/6/14 155 Misc. Items(SDB,Feeders,ACDB,Industrial Socket) 67 days Tue 4/29/14 Fri 7/4/14 156 Purchase Order for Misc.Items 0 days Tue 4/29/14 Tue 4/29/14 157 Payment for Misc.Items 7 days Tue 4/29/14 Tue 5/6/14 158 Receiving of Misc.Items 50 days Tue 5/6/14 Wed 6/25/14 159 Installation and Termination of Misc.Items 10 days Wed 6/25/14 Fri 7/4/14 160 Weather monitoring system 42 days Sat 6/7/14 Fri 7/18/14 161 Purchase Order for WMS 0 days Sat 6/7/14 Sat 6/7/14 162 Payment for WMS 7 days Sat 6/7/14 Sat 6/14/14 163 Receiving of WMS 30 days Sat 6/14/14 Mon 7/14/14 164 Installation of WMS 5 days Mon 7/14/14 Fri 7/18/14 165 Transmission Line 57 days Fri 5/16/14 Fri 7/11/14 166 Purchase Order for Transmission Line Structures & Equipments0 days Fri 5/16/14 Fri 5/16/14 167 Payment for Transmission Line Structures & Equipments7 days Fri 5/16/14 Fri 5/23/14 168 Receiving of Structures and Equipments 30 days Fri 5/23/14 Sun 6/22/14 169 Installation and Stringing of Equipments 20 days Sun 6/22/14 Fri 7/11/14 170 Fire alarm system works 5 days Wed 7/9/14 Sun 7/13/14 171 Testing and commissioning 10 days Sat 7/19/14 Mon 7/28/14 172 Proposed Commercial Operation Date 1 day Tue 7/29/14 Tue 7/29/14 5/21 5/28 5/28 6/17 6/17 6/21 5/9 5/9 5/16 5/16 6/30 6/30 7/4 4/26 4/26 5/3 5/3 5/23 5/23 5/25 5/26 5/26 6/2 6/2 7/2 7/2 7/6 4/29 4/29 5/6 5/6 6/25 6/25 7/4 6/7 6/7 6/14 6/14 7/14 7/14 7/18 5/16 5/16 5/23 5/23 6/22 6/22 7/11 7/9 7/13 7/19 7/2 7/29 7 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 3 Project: Template PIS Date: Wed 3/19/14