The contractor is 8 weeks into a 156-week contract to complete early infrastructure works. Progress is slightly behind schedule due to delays in obtaining the laydown area. Upcoming activities include site surveys and security fencing installation. Material submittals are in process with some approvals still pending. Safety performance has been good with no lost-time incidents reported in the period.