211-C01
SPI Week NO:
Status Date (G): 26-May-12 (H): 05 Rajab 1433 0.75 8
PM: Mohd Ali Planner: Allan Leyte
Contract Title: Rabigh II Royal Commision Early Infrastracture Works SCHEDULE ACTUAL VARIANCE
Contractor: XXX 1.50% 1.12% -0.38%
CONTRACTOR STATUS REPORT
SCOPE OF WORK :
The scope of works are:Utility Corridor:
Site works preparation and earthworks, Access roads to lift stations,
Potable, Fire and sanitary Sewer System including Lift Stations,
Security Fence, Electromechanical, electrical power distribution
system and Telecommunication works. Porta Cabin Building:
Installation of Portacabin buildings including related Civil,
Mechanical, Electrical works. Sewer, Potable and Fire water system,
electrical Power and Area lighting sytem and Chain link Fence for
the labor camp.
SCHEDULE DATA :
Item
No.
Contractual Milestone Baseline
Days
Change
Remarks
Contract Duration Current Contract Weeks : 8 of 156 156 0
Award Date 9-Apr-12 9-Apr-12 A 0
Notice To Proceed 9-Apr-12 9-Apr-12 A 0
1 Complete Mobilization and Construction Start 11-Jun-12 11-Jun-12 F 0 Waiting for the availability of
laydown Area
2 Complete Existing Conditions Survey and Submission of Reports and Site Setting out 9-Jul-12 9-Jul-12 F 0
3 Complete Security Fence 26-Aug-12 26-Aug-12 F 0
4 Complete Porta cabin buildings including fence around them 6-Jan-14 6-Jan-14 F 0
5 Complete infrastracture works for Porta Cabin buildings 7-Jul-14 7-Jul-14 F 0
6 Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, within utility
corridor, including sanitary lift stations and marl road
8-Dec-14 8-Dec-14 F 0
7 Complete All Remaining Work including Testing & Commissioning, Clean-up, Closeout
Documentation and ready for Initial Acceptance
9-Mar-15 9-Mar-15 F 0
8 Complete Demobilization 6-Apr-15 6-Apr-15 F 0
Contractor's
Forecast
156
Penalty Milestones
ENVIRONMENT, SAFETY and HEALTH :
Tool box Topic Next Week:
Previous This Period Total
Health & Safety
Lost Workday Cases (LWDC) 0 0 0
First Aid (FA) 0 0 0
Near Miss Incidents 0 0 0
Contract Man-hours 1,915 620 2,535
Environmental Issues
Major Environmental Incident 0 0 0
Minor Environmental Incident 0 0 0
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
Progress ( % )
Based on Earned Cost
To date This Period Previous
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
10.00% 27.27% 17.27%
Manpower Schedule Actual Variance
TOTAL MANPOWER
Saudi National Percentage (SC-46)
 Data Date
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
7-Apr-12
5-May-12
2-Jun-12
30-Jun-12
28-Jul-12
25-Aug-12
22-Sep-12
20-Oct-12
17-Nov-12
15-Dec-12
12-Jan-13
9-Feb-13
9-Mar-13
6-Apr-13
4-May-13
1-Jun-13
29-Jun-13
27-Jul-13
24-Aug-13
21-Sep-13
19-Oct-13
16-Nov-13
14-Dec-13
11-Jan-14
8-Feb-14
8-Mar-14
5-Apr-14
3-May-14
31-May-14
28-Jun-14
26-Jul-14
23-Aug-14
20-Sep-14
18-Oct-14
15-Nov-14
13-Dec-14
10-Jan-15
7-Feb-15
7-Mar-15
4-Apr-15
Week Beginning
Early Curve
Critical Path
Actual
Forecast
Data Date
Percent Complete Progress
STATUSAT :26-May-12
Schedule Actual Variance
1.50% 1.12% (0.38%)
211-C01
PM: Mohd Ali Planner: Allan Leyte Status Date (G): 26-May-12
Contract Title: Early Infrastracture Works Status date (H): 05 Rajab 1433
Contractor: XXX
CONTRACTOR STATUS REPORT
CONTRACTOR'S SUBMITTALS :
Technical Submittals Code 1 Code 2 Code 3 Code 4 Technical Queries Total Submitted to date Answered to date Critical TQ Pending
3 3 2 0
Total Required Submitted To Date Under Review Remaining
TBD 29 21
Materials
Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S
Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S
Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S
Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S
PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S
PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S
Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S
Legend:A:Actual F:Forecast S:Schedule
PROCUREMENT STATISTICS:
Submittal Date Approval Date P.O. Date Delivery Date Req'd Date
Major Construction Activities: UPCOMING ACTIVITIES for NEXT PERIOD:
PROGRESS HIGHLIGHTS for THIS PERIOD
WAITING FOR THE AVAILABILITY OF LAYDOWN AREA
CRITICAL ANALYSIS MITIGATION
PROGRESS HIGHLIGHTS
Prev. Month This Month To date
143,561 0 0 0 0 0 0 143,561
INVOICE ANALYSIS (SR x 1,000) :
Current
Contract Value
Paid
Previous Years
Paid Year to
Date
Paid
Year To Date
Invoice Status Cost to go
143,561 0 143,561 0 143,561 0 143,561 0.0%
% Change
BUDGET STATUS (SR x 1,000) :
Award
Value
Approved
Changes
Current
Contract Value
Approved
RFC's
Pending
Contract Value
Pending
Trends
Forecast
Contract Value
Status Date (G): (H): 05 Rajab 1433
PM: Mohd Ali Planner: Allan Leyte
Contract Title: Rabigh II Royal Commision Early Infrastracture Works
Contractor: XXX
MEETING MINUTES INPUT 211-C01
26-May-2012
Week 8
0 10 20 30 40 50 60 70 80 90
CONTRACTOR'S SUBMITTALS :
Technical Queries Total Submittedtodate Answered to date Critical TQ Pending Materials
0 Chain Linkfence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVCPipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcementbars 05-May-12 A 05-May-12 A 06-Jul-12 S
PROCUREMENT STATISTICS:
SubmittalDate ApprovalDate P.O.Date Delivery Date Req'dDate
CONTRACTOR'S SUBMITTALS :
Technical Submittals Code 1 Code 2 Code 3 Code 4
3 3 2
Total Required Submitted To Date Under Review Remaining
TBD 29 21
Progress ( % )
Manpower
Previous This Period Total
Health & Safety
Lost Workday Cases (LWDC) 0 0 0
First Aid (FA) 0 0 0
Near Miss Incidents 0 0 0
Contract Man-hours 1,915 620 2,535
Environmental Issues
Major Environmental Incident 0 0 0
Minor Environmental Incident 0 0 0
Technical Queries Total Submitted to date Answered to date Critical TQ Pending Materials
0 Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S
Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S
Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S
Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S
PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S
PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S
Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S
Legend:A:Actual F:Forecast S:Schedule
PROCUREMENT STATISTICS:
Submittal Date Approval Date P.O. Date Delivery Date Req'd Date
Upcoming
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
2nd Week
Progress ( % )
Based on Earned Cost
To date This Period Previous
1st Week
1.83% 2.21%
0.00% 0.00%
(1.83%) (2.21%)
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
Manpower Schedule Actual Variance
TOTAL MANPOWER
BI-WEEKLY PROGRESS REPORT
XXX
CONTRACT No. : 211-C01
Early Infrastracture Works
Report Date :
Week : 8 of 156
A. Upcoming
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
B. Upcoming
Schedule to date 2,158,974 950,614 1,208,360
Earned to date 1,609,901 715,511 894,389
Variance (549,074) (235,103) (313,971)
C. Upcoming
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
10.00% 27.27% 17.27% 0%
D. Baseline
Weeks 
Ahead/Behind
Contract Duration Current Contract Weeks : 8 of 156 156 156 0
9-Apr-12 9-Apr-12 A 0
1 11-Jun-12 11-Jun-12 F 0
2 9-Jul-12 9-Jul-12 F 0
3 26-Aug-12 26-Aug-12 F 0
4 6-Jan-14 6-Jan-14 F 0
5 7-Jul-14 7-Jul-14 F 0
6 8-Dec-14 8-Dec-14 F 0
7 9-Mar-15 9-Mar-15 F 0
8 6-Apr-15 6-Apr-15 F 0
E. Progress Highlights for period up to May 25, 2012
01
02
03
F. Risks / Challenges / Issues as of May 25, 2012
01
02
G. Upcoming Activities from the Period of 26 May '12 to 8 June '12
01
H. Material Procurement Schedule as of
Submittal Date Approval Date P.O. Date Required Date
01-May-12 01-May-12
03-May-12
05-May-12 05-May-12
06-May-12
09-May-12
09-May-12
09-May-12
09-May-12
22-May-12
13-May-12
23-May-12Grounding rods
Air release valve
Gate valve
Fire Hydrant
PVC conduits
PVC fittings
Steel Reinforcement bars
Concrete Mix Design
Butterfly valve
Materials Delivery Date
Chain Link fence
uPVC Pipes
Complete All Remaining Work including Testing & Commissioning, Clean-up,
Complete Demobilization
Complete Existing Conditions Survey and Submission of Reports and Site Setting out
Complete Security Fence
Complete Porta cabin buildings including fence around them
Complete infrastracture works for Porta Cabin buildings
Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom,
Contractor's
Forecast
Notice To Proceed
Complete Mobilization and Construction Start
Major Contract Evets/Milestones
Saudi National Percentage (SC-46)
1 3
18 13
TOTAL MANPOWER 30 34
12 21
17 10
0 0
10 18
0 0
2 3
Manpower Schedule Actual Variance
1st Week 2nd Week
2,634,281 3,171,044
0 0
(2,634,281) (3,171,044)
Progress ( SR ) Earned Cost To date This Period Previous
1st Week 2nd Week
1.83% 2.21%
0.00% 0.00%
(1.83%) (2.21%)
2nd Week
Progress ( % )
Based on Earned Cost
To date This Period Previous
1st Week
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%
Actual to Date
Schedule to Date
0 10 20 30 40 50 60 70 80 90

More Related Content

PDF
01. P269 - Project Implementation Programme - Rev 00
PDF
Contract 2 - Project Progress Status. Oct-13
PDF
Window Analysis @ 30-June-2012
PDF
10. Overall Implementation Programme
PPT
Power Point BLCC End of year Review
PDF
Monthly Progress Report No.13 - September 2011
01. P269 - Project Implementation Programme - Rev 00
Contract 2 - Project Progress Status. Oct-13
Window Analysis @ 30-June-2012
10. Overall Implementation Programme
Power Point BLCC End of year Review
Monthly Progress Report No.13 - September 2011

What's hot (6)

PDF
Steven Vukusic Resume
PPTX
Land Development Update: Oct. 8, 2015
DOC
Abdul basit resume
PPTX
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015
PDF
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
PPTX
Foundations for New Champlain Bridge Corridor Project
Steven Vukusic Resume
Land Development Update: Oct. 8, 2015
Abdul basit resume
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
Foundations for New Champlain Bridge Corridor Project
Ad

Similar to Wreport (20)

PDF
KVMRT Dashboard V2 July 16.pdf
PPT
Power Point BLCC End of year Review
PPTX
21 Capex 22-23 Template BPCL Jan 2024.pptx
PPTX
Civil Works of Air Separation Unit, Purification Unit and Sulfur Recovery Uni...
PPTX
Civil Works of Air Separation Unit, Purification Unit and Sulfur Recovery Uni...
PDF
Weekly report no 19
DOCX
2022-01-13-ALALAMEEN 08-WR08.docx
PPTX
Presentation for DHA on project progress(08-09-22).pptx
PPTX
Weekly Update for BPI Dau as of August 04, 2024 [Autosaved].pptx
PPTX
C&I July-2022.pptx
PPTX
Cluster Project for Cairn Vedanta gr.pptx
PPTX
REVISED PRESENTATION According to a 2022 report by the International Forum fo...
PPTX
KOM_LRDP Linch Redelopment project for ONGC.pptx
DOCX
Report for po no 7400005491.docx
PDF
Regional-Sports-Compex-Siteworks-and-Strategies-web.pdf
PPTX
Plant under construction at new greenfield
PDF
243-249 MANN STREET GOSFORD 1 s
PPTX
TAMAN ARA DAMAI (QMC) PHASE 2 WEEKLY PROGRESS 13122024.pptx
PPTX
Final Combined presenstation of URP RAJUK_PART_31.03.2021.pptx
PPTX
Weekly Update for BPI Dau as of August 10, 2024 [Autosaved].pptx
KVMRT Dashboard V2 July 16.pdf
Power Point BLCC End of year Review
21 Capex 22-23 Template BPCL Jan 2024.pptx
Civil Works of Air Separation Unit, Purification Unit and Sulfur Recovery Uni...
Civil Works of Air Separation Unit, Purification Unit and Sulfur Recovery Uni...
Weekly report no 19
2022-01-13-ALALAMEEN 08-WR08.docx
Presentation for DHA on project progress(08-09-22).pptx
Weekly Update for BPI Dau as of August 04, 2024 [Autosaved].pptx
C&I July-2022.pptx
Cluster Project for Cairn Vedanta gr.pptx
REVISED PRESENTATION According to a 2022 report by the International Forum fo...
KOM_LRDP Linch Redelopment project for ONGC.pptx
Report for po no 7400005491.docx
Regional-Sports-Compex-Siteworks-and-Strategies-web.pdf
Plant under construction at new greenfield
243-249 MANN STREET GOSFORD 1 s
TAMAN ARA DAMAI (QMC) PHASE 2 WEEKLY PROGRESS 13122024.pptx
Final Combined presenstation of URP RAJUK_PART_31.03.2021.pptx
Weekly Update for BPI Dau as of August 10, 2024 [Autosaved].pptx
Ad

More from Allan Leyte (18)

PDF
Construction Methodology Scheduling1
PDF
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
PDF
Sample MSProject with 16 DivisionFormat Variation(EOT)
PDF
BHP01-0 Bouly baseline on MSproject Format
PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PDF
WEIGHTING TABLE
PDF
PRODUCTION RATE APPX. NEW
PDF
Sample of Structural Steel Scheduling
PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PDF
p3 s-curves
PDF
Visio-Planning FlowChart-3
PDF
Bissa Upgrade weekly report 09May2016
PDF
Booster Pump cause of delay analysis
PDF
Sample Bidcom Presentation - Structural Works 12-28-11
PDF
Scheduling SLEX (FS)-InitialCPM
PDF
Offshore Programme using QP-P3 protocol
PDF
progress photos
PDF
Town Center presentation
Construction Methodology Scheduling1
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Sample MSProject with 16 DivisionFormat Variation(EOT)
BHP01-0 Bouly baseline on MSproject Format
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
WEIGHTING TABLE
PRODUCTION RATE APPX. NEW
Sample of Structural Steel Scheduling
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
p3 s-curves
Visio-Planning FlowChart-3
Bissa Upgrade weekly report 09May2016
Booster Pump cause of delay analysis
Sample Bidcom Presentation - Structural Works 12-28-11
Scheduling SLEX (FS)-InitialCPM
Offshore Programme using QP-P3 protocol
progress photos
Town Center presentation

Wreport

  • 1. 211-C01 SPI Week NO: Status Date (G): 26-May-12 (H): 05 Rajab 1433 0.75 8 PM: Mohd Ali Planner: Allan Leyte Contract Title: Rabigh II Royal Commision Early Infrastracture Works SCHEDULE ACTUAL VARIANCE Contractor: XXX 1.50% 1.12% -0.38% CONTRACTOR STATUS REPORT SCOPE OF WORK : The scope of works are:Utility Corridor: Site works preparation and earthworks, Access roads to lift stations, Potable, Fire and sanitary Sewer System including Lift Stations, Security Fence, Electromechanical, electrical power distribution system and Telecommunication works. Porta Cabin Building: Installation of Portacabin buildings including related Civil, Mechanical, Electrical works. Sewer, Potable and Fire water system, electrical Power and Area lighting sytem and Chain link Fence for the labor camp. SCHEDULE DATA : Item No. Contractual Milestone Baseline Days Change Remarks Contract Duration Current Contract Weeks : 8 of 156 156 0 Award Date 9-Apr-12 9-Apr-12 A 0 Notice To Proceed 9-Apr-12 9-Apr-12 A 0 1 Complete Mobilization and Construction Start 11-Jun-12 11-Jun-12 F 0 Waiting for the availability of laydown Area 2 Complete Existing Conditions Survey and Submission of Reports and Site Setting out 9-Jul-12 9-Jul-12 F 0 3 Complete Security Fence 26-Aug-12 26-Aug-12 F 0 4 Complete Porta cabin buildings including fence around them 6-Jan-14 6-Jan-14 F 0 5 Complete infrastracture works for Porta Cabin buildings 7-Jul-14 7-Jul-14 F 0 6 Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, within utility corridor, including sanitary lift stations and marl road 8-Dec-14 8-Dec-14 F 0 7 Complete All Remaining Work including Testing & Commissioning, Clean-up, Closeout Documentation and ready for Initial Acceptance 9-Mar-15 9-Mar-15 F 0 8 Complete Demobilization 6-Apr-15 6-Apr-15 F 0 Contractor's Forecast 156 Penalty Milestones ENVIRONMENT, SAFETY and HEALTH : Tool box Topic Next Week: Previous This Period Total Health & Safety Lost Workday Cases (LWDC) 0 0 0 First Aid (FA) 0 0 0 Near Miss Incidents 0 0 0 Contract Man-hours 1,915 620 2,535 Environmental Issues Major Environmental Incident 0 0 0 Minor Environmental Incident 0 0 0 Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) Progress ( % ) Based on Earned Cost To date This Period Previous A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) 10.00% 27.27% 17.27% Manpower Schedule Actual Variance TOTAL MANPOWER Saudi National Percentage (SC-46)  Data Date 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 7-Apr-12 5-May-12 2-Jun-12 30-Jun-12 28-Jul-12 25-Aug-12 22-Sep-12 20-Oct-12 17-Nov-12 15-Dec-12 12-Jan-13 9-Feb-13 9-Mar-13 6-Apr-13 4-May-13 1-Jun-13 29-Jun-13 27-Jul-13 24-Aug-13 21-Sep-13 19-Oct-13 16-Nov-13 14-Dec-13 11-Jan-14 8-Feb-14 8-Mar-14 5-Apr-14 3-May-14 31-May-14 28-Jun-14 26-Jul-14 23-Aug-14 20-Sep-14 18-Oct-14 15-Nov-14 13-Dec-14 10-Jan-15 7-Feb-15 7-Mar-15 4-Apr-15 Week Beginning Early Curve Critical Path Actual Forecast Data Date Percent Complete Progress STATUSAT :26-May-12 Schedule Actual Variance 1.50% 1.12% (0.38%)
  • 2. 211-C01 PM: Mohd Ali Planner: Allan Leyte Status Date (G): 26-May-12 Contract Title: Early Infrastracture Works Status date (H): 05 Rajab 1433 Contractor: XXX CONTRACTOR STATUS REPORT CONTRACTOR'S SUBMITTALS : Technical Submittals Code 1 Code 2 Code 3 Code 4 Technical Queries Total Submitted to date Answered to date Critical TQ Pending 3 3 2 0 Total Required Submitted To Date Under Review Remaining TBD 29 21 Materials Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S Legend:A:Actual F:Forecast S:Schedule PROCUREMENT STATISTICS: Submittal Date Approval Date P.O. Date Delivery Date Req'd Date Major Construction Activities: UPCOMING ACTIVITIES for NEXT PERIOD: PROGRESS HIGHLIGHTS for THIS PERIOD WAITING FOR THE AVAILABILITY OF LAYDOWN AREA CRITICAL ANALYSIS MITIGATION PROGRESS HIGHLIGHTS Prev. Month This Month To date 143,561 0 0 0 0 0 0 143,561 INVOICE ANALYSIS (SR x 1,000) : Current Contract Value Paid Previous Years Paid Year to Date Paid Year To Date Invoice Status Cost to go 143,561 0 143,561 0 143,561 0 143,561 0.0% % Change BUDGET STATUS (SR x 1,000) : Award Value Approved Changes Current Contract Value Approved RFC's Pending Contract Value Pending Trends Forecast Contract Value
  • 3. Status Date (G): (H): 05 Rajab 1433 PM: Mohd Ali Planner: Allan Leyte Contract Title: Rabigh II Royal Commision Early Infrastracture Works Contractor: XXX MEETING MINUTES INPUT 211-C01 26-May-2012 Week 8 0 10 20 30 40 50 60 70 80 90 CONTRACTOR'S SUBMITTALS : Technical Queries Total Submittedtodate Answered to date Critical TQ Pending Materials 0 Chain Linkfence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVCPipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcementbars 05-May-12 A 05-May-12 A 06-Jul-12 S PROCUREMENT STATISTICS: SubmittalDate ApprovalDate P.O.Date Delivery Date Req'dDate CONTRACTOR'S SUBMITTALS : Technical Submittals Code 1 Code 2 Code 3 Code 4 3 3 2 Total Required Submitted To Date Under Review Remaining TBD 29 21 Progress ( % ) Manpower Previous This Period Total Health & Safety Lost Workday Cases (LWDC) 0 0 0 First Aid (FA) 0 0 0 Near Miss Incidents 0 0 0 Contract Man-hours 1,915 620 2,535 Environmental Issues Major Environmental Incident 0 0 0 Minor Environmental Incident 0 0 0 Technical Queries Total Submitted to date Answered to date Critical TQ Pending Materials 0 Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S Legend:A:Actual F:Forecast S:Schedule PROCUREMENT STATISTICS: Submittal Date Approval Date P.O. Date Delivery Date Req'd Date Upcoming Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) 2nd Week Progress ( % ) Based on Earned Cost To date This Period Previous 1st Week 1.83% 2.21% 0.00% 0.00% (1.83%) (2.21%) A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) Manpower Schedule Actual Variance TOTAL MANPOWER
  • 4. BI-WEEKLY PROGRESS REPORT XXX CONTRACT No. : 211-C01 Early Infrastracture Works Report Date : Week : 8 of 156 A. Upcoming Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) B. Upcoming Schedule to date 2,158,974 950,614 1,208,360 Earned to date 1,609,901 715,511 894,389 Variance (549,074) (235,103) (313,971) C. Upcoming A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) 10.00% 27.27% 17.27% 0% D. Baseline Weeks  Ahead/Behind Contract Duration Current Contract Weeks : 8 of 156 156 156 0 9-Apr-12 9-Apr-12 A 0 1 11-Jun-12 11-Jun-12 F 0 2 9-Jul-12 9-Jul-12 F 0 3 26-Aug-12 26-Aug-12 F 0 4 6-Jan-14 6-Jan-14 F 0 5 7-Jul-14 7-Jul-14 F 0 6 8-Dec-14 8-Dec-14 F 0 7 9-Mar-15 9-Mar-15 F 0 8 6-Apr-15 6-Apr-15 F 0 E. Progress Highlights for period up to May 25, 2012 01 02 03 F. Risks / Challenges / Issues as of May 25, 2012 01 02 G. Upcoming Activities from the Period of 26 May '12 to 8 June '12 01 H. Material Procurement Schedule as of Submittal Date Approval Date P.O. Date Required Date 01-May-12 01-May-12 03-May-12 05-May-12 05-May-12 06-May-12 09-May-12 09-May-12 09-May-12 09-May-12 22-May-12 13-May-12 23-May-12Grounding rods Air release valve Gate valve Fire Hydrant PVC conduits PVC fittings Steel Reinforcement bars Concrete Mix Design Butterfly valve Materials Delivery Date Chain Link fence uPVC Pipes Complete All Remaining Work including Testing & Commissioning, Clean-up, Complete Demobilization Complete Existing Conditions Survey and Submission of Reports and Site Setting out Complete Security Fence Complete Porta cabin buildings including fence around them Complete infrastracture works for Porta Cabin buildings Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, Contractor's Forecast Notice To Proceed Complete Mobilization and Construction Start Major Contract Evets/Milestones Saudi National Percentage (SC-46) 1 3 18 13 TOTAL MANPOWER 30 34 12 21 17 10 0 0 10 18 0 0 2 3 Manpower Schedule Actual Variance 1st Week 2nd Week 2,634,281 3,171,044 0 0 (2,634,281) (3,171,044) Progress ( SR ) Earned Cost To date This Period Previous 1st Week 2nd Week 1.83% 2.21% 0.00% 0.00% (1.83%) (2.21%) 2nd Week Progress ( % ) Based on Earned Cost To date This Period Previous 1st Week 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100% Actual to Date Schedule to Date 0 10 20 30 40 50 60 70 80 90