• CP-FLS-6
STRUCTURAL WORKS (CONCRETING)
FAIRVIEW TERRACES (PITTSBURGH)
STRUCTURAL
WORKS DIVIDED
INTO THREE (3)
AREAS
1: RETAIL AREA 1
2: RETAIL AREA 2
3: PARKING
3
1
2
Bidders History
LIST OF APPROVED BIDDERS
1. ALLAN
2. CHRIS
3. JOHN
4. DINKAR
5. ROB
LIST OF BIDDERS WHO DECLINED
1. ROLANDO
2. JOSE
Bid Abstract RETAIL AREA 1
 Rob, Dinkar & Chris are considered for negotiation.
 ALLAN   CHRIS   JOHN   DINKAR   ROB 
A RETAIL AREA 1
I. PRELIMINARIES 18.61 11.47 10.00 5.45 4.10 12.54
II SITE WORK
Gravel Bedding (100mm) 10.72 2.39 1.53 2.84 1.41 1.21
III CONCRETE REINFORCEMEN 25.36 21.73 25.36 24.05 20.65 25.75
IV
CAST IN PLACE CONCRETE 
(MDC SUPPLPIED)
11.70 9.59 17.01 13.23 8.87 7.66
V CONCRETE FORMS 94.14 52.84 35.23 26.93 31.71 36.99
VI CONCRETE ACCESSORIES 3.63 7.83 2.55 7.33 3.22 5.39
VII CONCRETE FINISHES 0.86 1.25 1.21 2.71 1.43 1.14
VIII SUNDRIES 0.50
Total Amount 165.020     107.100     93.390       82.540       71.390       90.68
Variance from Lowest Bidd 93.630       35.710       22.000       11.150       ‐            
% Variance 131.15% 50.02% 30.82% 15.62% 0.00%
(74.340) (16.420) (2.710) 8.140 19.290
81.98% 18.11% 2.99% -8.98% -21.27%
BUDGETITEM WORK DESCRIPTION
BIDDER'S PROPOSAL
VARIANCE
Bid Abstract RETAIL AREA 2
 Rob, Dinkar & John are considered for negotiation.
  ALLAN     CHRIS     JOHN     DINKAR     ROB  
B RETAIL AREA 2
I. PRELIMINARIES 18.61 8.66 8.50 5.30 4.11 10.34
II SITE WORK
Gravel Bedding (100mm) 8.09 1.81 1.19 2.14 1.09 0.91
III CONCRETE REINFORCEMEN 19.13 16.40 19.13 18.14 15.58 19.43
IV
CAST IN PLACE CONCRETE 
(MDC SUPPLPIED)
8.82 7.23 12.83 9.98 6.69 5.78
V CONCRETE FORMS  71.23 39.86 26.58 20.32 23.92 27.9
VI CONCRETE ACCESSORIES 2.86 5.91 1.92 5.64 2.45 4.07
VII CONCRETE FINISHES 0.64 0.94 0.91 2.04 1.08 0.86
VIII SUNDRIES 0.50
Total Amount 129.380     80.810       71.560       63.560       54.920       69.29
Variance from Lowest Bidd 74.460       25.890       16.640       8.640         ‐            
% Variance 135.58% 47.14% 30.30% 15.73% 0.00%
(60.090) (11.520) (2.270) 5.730 14.370
86.72% 16.63% 3.28% -8.27% -20.74%
BUDGETITEM WORK DESCRIPTION
BIDDER'S PROPOSAL
VARIANCE
Bid Abstract PARKING
 Rob Dinkar & John are considered for negotiation.
  ALLAN     CHRIS     JOHN     DINKAR     ROB  
C PARKING
I. PRELIMINARIES 18.61 8.08 5.36 9.00 4.11 10.00
II SITE WORK
Gravel Bedding (100mm) 8.99 1.94 2.52 1.37 1.26 1.07
III CONCRETE REINFORCEMEN 13.51 11.58 12.98 13.51 11.00 13.72
IV
CAST IN PLACE CONCRETE 
(MDC SUPPLPIED)
6.59 5.40 7.49 9.59 5.00 4.32
V CONCRETE FORMS  57.93 27.44 13.16 18.29 16.46 19.2
VI CONCRETE ACCESSORIES 1.69 3.75 2.96 1.07 1.70 2.13
VII CONCRETE FINISHES 7.41 15.78 24.00 10.45 12.64 9.97
VIII PRECAST CONCRETE 1.53 1.44 2.70 3.05 0.35 1.3
IX SUNDRIES 1.00
Total Amount 116.260     75.410       71.170       67.330       52.522       61.71
Variance from Lowest Bidd 63.738       22.888       18.648       14.808       ‐            
% Variance 121.35% 43.58% 35.51% 28.19% 0.00%
(54.550) (13.700) (9.460) (5.620) 9.188
88.40% 22.20% 15.33% 9.11% -14.89%
BUDGETITEM WORK DESCRIPTION
BIDDER'S PROPOSAL
VARIANCE
1.0  RETAIL AREA 1
I. PRELIMINARIES 18.61 11.47 10.00 5.45 4.10 9.00 12.54
II SITE WORK
Gravel Bedding (100mm) 10.72 2.39 1.53 2.84 1.41 0.99 1.21
III CONCRETE REINFORCEMENT 25.36 21.73 25.36 24.05 20.65 18.11 25.75
IV CAST IN PLACE CONCRETE (MD 11.70 9.59 17.01 13.23 8.87 7.44 7.66
V
CONCRETE FORMS & 
ACCESSORIES
94.14 52.84 35.23 26.93 31.71 36.40 36.99
VI CONCRETE ACCESSORIES 3.63 7.83 2.55 7.33 3.22 2.18 5.39
VII CONCRETE FINISHES 0.86 1.25 1.21 2.71 1.43 0.97 1.14
VIII SUNDRIES 0.50
Total Amount 165.02 107.10 93.39 82.54 71.39 75.09 90.68
-74.340 -16.420 -2.710 8.140 19.290 15.590
-82% -18% -3% 9% 21% 17%
ITEM WORK DESCRIPTION BUDGETCHRIS
ABC 
EVALUATION
ALLAN DINKARJOHN ROB
VARIANCE
Evaluation: RETAIL AREA 1
ALLAN CHRIS JOHN DINKAR ROB
2.0  RETAIL AREA 2
I. PRELIMINARIES 18.61 8.66 8.50 5.30 4.11 9.00 10.34
II SITE WORK
Gravel Bedding (100mm) 8.09 1.81 1.19 2.14 1.09 0.74 0.91
III CONCRETE REINFORCEMENT 19.13 16.40 19.13 18.14 15.58 13.66 19.43
IV CAST IN PLACE CONCRETE (MD 8.82 7.23 12.83 9.98 6.69 5.61 5.78
V
CONCRETE FORMS & 
ACCESSORIES
71.23 39.86 26.58 20.32 23.92 27.46 27.90
VI CONCRETE ACCESSORIES 2.86 5.91 1.92 5.64 2.45 1.65 4.07
VII CONCRETE FINISHES 0.64 0.94 0.91 2.04 1.08 0.73 0.86
VIII SUNDRIES 0.50
Total Amount 129.38 80.81 71.56 63.56 54.92 58.85 69.29
-60.090 -11.520 -2.270 5.730 14.370 10.440
-87% -17% -3% 8% 21% 15%
ITEM WORK DESCRIPTION BUDGET
ABC 
EVALUATION
VARIANCE
Evaluation: RETAIL AREA 2
ALLAN CHRIS JOHN DINKAR ROB
3.0  PARKING
I. PRELIMINARIES 18.61 ` 5.36 9.00 4.11 9.00 10.00
II SITE WORK
Gravel Bedding (100mm) 8.99 1.94 2.52 1.37 1.26 0.87 1.07
III CONCRETE REINFORCEMENT 13.51 11.58 12.98 13.51 11.00 9.65 13.72
IV CAST IN PLACE CONCRETE (MD 6.59 5.41 7.49 9.59 5.00 3.91 4.32
V
CONCRETE FORMS & 
ACCESSORIES
57.93 27.44 13.16 18.29 16.46 18.90 19.20
VI CONCRETE ACCESSORIES 1.69 3.75 2.96 1.07 1.70 0.87 2.13
VII CONCRETE FINISHES 7.41 15.78 24.00 10.45 12.64 7.32 9.97
VIII PRECAST CONCRETE 1.53 1.44 2.70 3.05 0.35 0.58 1.30
IX SUNDRIES 1.00
Total Amount 116.26 67.34 71.17 67.33 52.52 51.10 61.71
-54.550 -5.630 -9.460 -5.620 9.188 10.610
-88% -9% -15% -9% 15% 17%
ITEM WORK DESCRIPTION BUDGET
ABC 
EVALUATION
VARIANCE
Evaluation: PARKING
SUMMARY
ITEM AREA BUDGET ALLAN CHRIS JOHN DINKAR ROB ABC EVALUATION
I. RETAIL AREA 1 90.68 165.29    107.12    93.38      82.55      71.40      75.09                
II. RETAIL AREA 2 69.29 129.39    80.81      71.56      63.57      54.92      58.86                
159.970  294.680  187.930  164.940  146.120  126.320  133.950            
III. PARKING 61.71 116.26    75.41      67.34      71.18      52.53      51.10                
61.710    116.260  75.410    67.340    71.180    52.530    51.100              
221.680  410.940  263.340  232.280  217.300  178.850  185.050            GRAND TOTAL AMOUNT
Total Amount RETAIL
Total Amount PARKING
Negotiation Points:
 Negotiate for ABC rates
 Recommendation:
 ROB, DINKAR & JOHN considered for negotiation.
Benchmark
Description Unit
 KSP BLDG K 
DLM 
MDC 
Evaluation
Remarks
CONCRETING WORKS
Supply & Installation of 
Formworks
Shear Wall sq.m 580.00                 580.00      ADV Unit Rate
RC Stair sq.m 580.00                 580.00      ADV Unit Rate
Suspended Slab sq.m 580.00                 580.00      ADV Unit Rate
CAST IN PLACE CONCRETE
Slab on Grade cu.m 350.00                 350.00      ADV Unit Rate
Shear Wall cu.m 350.00                 350.00      ADV Unit Rate
RC Stair cu.m 350.00                 350.00      ADV Unit Rate
Suspended Slab cu.m 350.00                 350.00      ADV Unit Rate
Beam & Girder cu.m 350.00                 350.00      ADV Unit Rate
Retaining Wall cu.m 350.00                 350.00      ADV Unit Rate
END OF PRESENTATION
THANK YOU!

More Related Content

PPT
Wwii holocaust-overview-8952
PDF
Lightning Talk Tips
PPTX
الترددات
PDF
Profile Công ty Quảng cáo và Truyền thông Titan tại Đà Nẵng- Miền trung
DOCX
Ludwig y guapacha
PDF
Inflicted childhood neurotrauma (shaken baby syndrome) ophthalmic findings
Wwii holocaust-overview-8952
Lightning Talk Tips
الترددات
Profile Công ty Quảng cáo và Truyền thông Titan tại Đà Nẵng- Miền trung
Ludwig y guapacha
Inflicted childhood neurotrauma (shaken baby syndrome) ophthalmic findings

Viewers also liked (9)

KEY
Lessons Learnt from WooThemes
DOCX
The occurrence script final .
PDF
Ip Office Brochure
PPTX
Question Six - What have you learned about technologies from the process of c...
PDF
Educación inclusiva, diversidad y discursividad.aldo ocampo gonzález
XLS
Calificaciones Aranza Michelle
PDF
โครงงานคอมพิวเตอร์444
PDF
Tulevaisuuden teknologiat 26.11.2011
Lessons Learnt from WooThemes
The occurrence script final .
Ip Office Brochure
Question Six - What have you learned about technologies from the process of c...
Educación inclusiva, diversidad y discursividad.aldo ocampo gonzález
Calificaciones Aranza Michelle
โครงงานคอมพิวเตอร์444
Tulevaisuuden teknologiat 26.11.2011
Ad

Similar to Sample Bidcom Presentation - Structural Works 12-28-11 (17)

PPTX
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
PPTX
2nd Presentation NAME 338
PPTX
NAME 338 , Presentation 1
PPTX
a0a39d70-becd-4258-bc6c-a06224bf22b0.pptx
DOC
Cost of breeder farm
PPTX
Municipal Presentation Sarad Dahal.pptx
PDF
RMC 34 KUMILY - POOPPARA ROAD
PPTX
PCM_Construction of Maliana II Irrigation_Rev.2 terbaru.pptx
PDF
QS.pdf
PDF
232365141 1-qs-techinical-data
PDF
PP1 Project 3 Feasibility study
PDF
Design of security room
PPTX
project-presentation of the engineering sector pptx
PPTX
PRESENTATION.pptxA EXPERIMENTAL STUDY ON PARTIAL REPLACEMENT OF FINE AGGREGA...
PDF
070002179.PDF
PPTX
PCM_Construction of Maliana II Irrigation_Rev.1.pptx
PPTX
second review.pptx
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
2nd Presentation NAME 338
NAME 338 , Presentation 1
a0a39d70-becd-4258-bc6c-a06224bf22b0.pptx
Cost of breeder farm
Municipal Presentation Sarad Dahal.pptx
RMC 34 KUMILY - POOPPARA ROAD
PCM_Construction of Maliana II Irrigation_Rev.2 terbaru.pptx
QS.pdf
232365141 1-qs-techinical-data
PP1 Project 3 Feasibility study
Design of security room
project-presentation of the engineering sector pptx
PRESENTATION.pptxA EXPERIMENTAL STUDY ON PARTIAL REPLACEMENT OF FINE AGGREGA...
070002179.PDF
PCM_Construction of Maliana II Irrigation_Rev.1.pptx
second review.pptx
Ad

More from Allan Leyte (18)

PDF
Construction Methodology Scheduling1
PDF
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
PDF
Sample MSProject with 16 DivisionFormat Variation(EOT)
PDF
BHP01-0 Bouly baseline on MSproject Format
PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PDF
WEIGHTING TABLE
PDF
PRODUCTION RATE APPX. NEW
PDF
Sample of Structural Steel Scheduling
PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PDF
p3 s-curves
PDF
Wreport
PDF
Visio-Planning FlowChart-3
PDF
Bissa Upgrade weekly report 09May2016
PDF
Booster Pump cause of delay analysis
PDF
Scheduling SLEX (FS)-InitialCPM
PDF
Offshore Programme using QP-P3 protocol
PDF
progress photos
PDF
Town Center presentation
Construction Methodology Scheduling1
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Sample MSProject with 16 DivisionFormat Variation(EOT)
BHP01-0 Bouly baseline on MSproject Format
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
WEIGHTING TABLE
PRODUCTION RATE APPX. NEW
Sample of Structural Steel Scheduling
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
p3 s-curves
Wreport
Visio-Planning FlowChart-3
Bissa Upgrade weekly report 09May2016
Booster Pump cause of delay analysis
Scheduling SLEX (FS)-InitialCPM
Offshore Programme using QP-P3 protocol
progress photos
Town Center presentation

Sample Bidcom Presentation - Structural Works 12-28-11

  • 1. • CP-FLS-6 STRUCTURAL WORKS (CONCRETING) FAIRVIEW TERRACES (PITTSBURGH)
  • 2. STRUCTURAL WORKS DIVIDED INTO THREE (3) AREAS 1: RETAIL AREA 1 2: RETAIL AREA 2 3: PARKING 3 1 2
  • 3. Bidders History LIST OF APPROVED BIDDERS 1. ALLAN 2. CHRIS 3. JOHN 4. DINKAR 5. ROB LIST OF BIDDERS WHO DECLINED 1. ROLANDO 2. JOSE
  • 4. Bid Abstract RETAIL AREA 1  Rob, Dinkar & Chris are considered for negotiation.  ALLAN   CHRIS   JOHN   DINKAR   ROB  A RETAIL AREA 1 I. PRELIMINARIES 18.61 11.47 10.00 5.45 4.10 12.54 II SITE WORK Gravel Bedding (100mm) 10.72 2.39 1.53 2.84 1.41 1.21 III CONCRETE REINFORCEMEN 25.36 21.73 25.36 24.05 20.65 25.75 IV CAST IN PLACE CONCRETE  (MDC SUPPLPIED) 11.70 9.59 17.01 13.23 8.87 7.66 V CONCRETE FORMS 94.14 52.84 35.23 26.93 31.71 36.99 VI CONCRETE ACCESSORIES 3.63 7.83 2.55 7.33 3.22 5.39 VII CONCRETE FINISHES 0.86 1.25 1.21 2.71 1.43 1.14 VIII SUNDRIES 0.50 Total Amount 165.020     107.100     93.390       82.540       71.390       90.68 Variance from Lowest Bidd 93.630       35.710       22.000       11.150       ‐             % Variance 131.15% 50.02% 30.82% 15.62% 0.00% (74.340) (16.420) (2.710) 8.140 19.290 81.98% 18.11% 2.99% -8.98% -21.27% BUDGETITEM WORK DESCRIPTION BIDDER'S PROPOSAL VARIANCE
  • 5. Bid Abstract RETAIL AREA 2  Rob, Dinkar & John are considered for negotiation.   ALLAN     CHRIS     JOHN     DINKAR     ROB   B RETAIL AREA 2 I. PRELIMINARIES 18.61 8.66 8.50 5.30 4.11 10.34 II SITE WORK Gravel Bedding (100mm) 8.09 1.81 1.19 2.14 1.09 0.91 III CONCRETE REINFORCEMEN 19.13 16.40 19.13 18.14 15.58 19.43 IV CAST IN PLACE CONCRETE  (MDC SUPPLPIED) 8.82 7.23 12.83 9.98 6.69 5.78 V CONCRETE FORMS  71.23 39.86 26.58 20.32 23.92 27.9 VI CONCRETE ACCESSORIES 2.86 5.91 1.92 5.64 2.45 4.07 VII CONCRETE FINISHES 0.64 0.94 0.91 2.04 1.08 0.86 VIII SUNDRIES 0.50 Total Amount 129.380     80.810       71.560       63.560       54.920       69.29 Variance from Lowest Bidd 74.460       25.890       16.640       8.640         ‐             % Variance 135.58% 47.14% 30.30% 15.73% 0.00% (60.090) (11.520) (2.270) 5.730 14.370 86.72% 16.63% 3.28% -8.27% -20.74% BUDGETITEM WORK DESCRIPTION BIDDER'S PROPOSAL VARIANCE
  • 6. Bid Abstract PARKING  Rob Dinkar & John are considered for negotiation.   ALLAN     CHRIS     JOHN     DINKAR     ROB   C PARKING I. PRELIMINARIES 18.61 8.08 5.36 9.00 4.11 10.00 II SITE WORK Gravel Bedding (100mm) 8.99 1.94 2.52 1.37 1.26 1.07 III CONCRETE REINFORCEMEN 13.51 11.58 12.98 13.51 11.00 13.72 IV CAST IN PLACE CONCRETE  (MDC SUPPLPIED) 6.59 5.40 7.49 9.59 5.00 4.32 V CONCRETE FORMS  57.93 27.44 13.16 18.29 16.46 19.2 VI CONCRETE ACCESSORIES 1.69 3.75 2.96 1.07 1.70 2.13 VII CONCRETE FINISHES 7.41 15.78 24.00 10.45 12.64 9.97 VIII PRECAST CONCRETE 1.53 1.44 2.70 3.05 0.35 1.3 IX SUNDRIES 1.00 Total Amount 116.260     75.410       71.170       67.330       52.522       61.71 Variance from Lowest Bidd 63.738       22.888       18.648       14.808       ‐             % Variance 121.35% 43.58% 35.51% 28.19% 0.00% (54.550) (13.700) (9.460) (5.620) 9.188 88.40% 22.20% 15.33% 9.11% -14.89% BUDGETITEM WORK DESCRIPTION BIDDER'S PROPOSAL VARIANCE
  • 7. 1.0  RETAIL AREA 1 I. PRELIMINARIES 18.61 11.47 10.00 5.45 4.10 9.00 12.54 II SITE WORK Gravel Bedding (100mm) 10.72 2.39 1.53 2.84 1.41 0.99 1.21 III CONCRETE REINFORCEMENT 25.36 21.73 25.36 24.05 20.65 18.11 25.75 IV CAST IN PLACE CONCRETE (MD 11.70 9.59 17.01 13.23 8.87 7.44 7.66 V CONCRETE FORMS &  ACCESSORIES 94.14 52.84 35.23 26.93 31.71 36.40 36.99 VI CONCRETE ACCESSORIES 3.63 7.83 2.55 7.33 3.22 2.18 5.39 VII CONCRETE FINISHES 0.86 1.25 1.21 2.71 1.43 0.97 1.14 VIII SUNDRIES 0.50 Total Amount 165.02 107.10 93.39 82.54 71.39 75.09 90.68 -74.340 -16.420 -2.710 8.140 19.290 15.590 -82% -18% -3% 9% 21% 17% ITEM WORK DESCRIPTION BUDGETCHRIS ABC  EVALUATION ALLAN DINKARJOHN ROB VARIANCE Evaluation: RETAIL AREA 1
  • 8. ALLAN CHRIS JOHN DINKAR ROB 2.0  RETAIL AREA 2 I. PRELIMINARIES 18.61 8.66 8.50 5.30 4.11 9.00 10.34 II SITE WORK Gravel Bedding (100mm) 8.09 1.81 1.19 2.14 1.09 0.74 0.91 III CONCRETE REINFORCEMENT 19.13 16.40 19.13 18.14 15.58 13.66 19.43 IV CAST IN PLACE CONCRETE (MD 8.82 7.23 12.83 9.98 6.69 5.61 5.78 V CONCRETE FORMS &  ACCESSORIES 71.23 39.86 26.58 20.32 23.92 27.46 27.90 VI CONCRETE ACCESSORIES 2.86 5.91 1.92 5.64 2.45 1.65 4.07 VII CONCRETE FINISHES 0.64 0.94 0.91 2.04 1.08 0.73 0.86 VIII SUNDRIES 0.50 Total Amount 129.38 80.81 71.56 63.56 54.92 58.85 69.29 -60.090 -11.520 -2.270 5.730 14.370 10.440 -87% -17% -3% 8% 21% 15% ITEM WORK DESCRIPTION BUDGET ABC  EVALUATION VARIANCE Evaluation: RETAIL AREA 2
  • 9. ALLAN CHRIS JOHN DINKAR ROB 3.0  PARKING I. PRELIMINARIES 18.61 ` 5.36 9.00 4.11 9.00 10.00 II SITE WORK Gravel Bedding (100mm) 8.99 1.94 2.52 1.37 1.26 0.87 1.07 III CONCRETE REINFORCEMENT 13.51 11.58 12.98 13.51 11.00 9.65 13.72 IV CAST IN PLACE CONCRETE (MD 6.59 5.41 7.49 9.59 5.00 3.91 4.32 V CONCRETE FORMS &  ACCESSORIES 57.93 27.44 13.16 18.29 16.46 18.90 19.20 VI CONCRETE ACCESSORIES 1.69 3.75 2.96 1.07 1.70 0.87 2.13 VII CONCRETE FINISHES 7.41 15.78 24.00 10.45 12.64 7.32 9.97 VIII PRECAST CONCRETE 1.53 1.44 2.70 3.05 0.35 0.58 1.30 IX SUNDRIES 1.00 Total Amount 116.26 67.34 71.17 67.33 52.52 51.10 61.71 -54.550 -5.630 -9.460 -5.620 9.188 10.610 -88% -9% -15% -9% 15% 17% ITEM WORK DESCRIPTION BUDGET ABC  EVALUATION VARIANCE Evaluation: PARKING
  • 10. SUMMARY ITEM AREA BUDGET ALLAN CHRIS JOHN DINKAR ROB ABC EVALUATION I. RETAIL AREA 1 90.68 165.29    107.12    93.38      82.55      71.40      75.09                 II. RETAIL AREA 2 69.29 129.39    80.81      71.56      63.57      54.92      58.86                 159.970  294.680  187.930  164.940  146.120  126.320  133.950             III. PARKING 61.71 116.26    75.41      67.34      71.18      52.53      51.10                 61.710    116.260  75.410    67.340    71.180    52.530    51.100               221.680  410.940  263.340  232.280  217.300  178.850  185.050            GRAND TOTAL AMOUNT Total Amount RETAIL Total Amount PARKING
  • 11. Negotiation Points:  Negotiate for ABC rates  Recommendation:  ROB, DINKAR & JOHN considered for negotiation.
  • 12. Benchmark Description Unit  KSP BLDG K  DLM  MDC  Evaluation Remarks CONCRETING WORKS Supply & Installation of  Formworks Shear Wall sq.m 580.00                 580.00      ADV Unit Rate RC Stair sq.m 580.00                 580.00      ADV Unit Rate Suspended Slab sq.m 580.00                 580.00      ADV Unit Rate CAST IN PLACE CONCRETE Slab on Grade cu.m 350.00                 350.00      ADV Unit Rate Shear Wall cu.m 350.00                 350.00      ADV Unit Rate RC Stair cu.m 350.00                 350.00      ADV Unit Rate Suspended Slab cu.m 350.00                 350.00      ADV Unit Rate Beam & Girder cu.m 350.00                 350.00      ADV Unit Rate Retaining Wall cu.m 350.00                 350.00      ADV Unit Rate