Construction Methodology Scheduling1
COLUMN FOOTING TO GROUND FLOOR
(SUSPENDED SLAB)
DONE
AREA 4
AREA 6AREA 5
AREA 2AREA 1 AREA 3
T3
T1
T2
CONCRETING WORKS
3rd FLOOR (PODIUM FLOOR)
CONCRETING WORKS
Start: August 20, 2015
End : August 31, 2015
AREA 4
Start: August 22, 2015
End : September 02, 2015
AREA 5
AREA 1
T3
T1
T2
AREA 3B
AREA 2
AREA 3A
DONE
4th FLOOR SLAB
CONCRETING WORKS
Start: August 04, 2015
End : September 07, 2015
Start: June 01, 2015
End : September 07, 2015
Start: August 31, 2015
End : September 12, 2015
AREA 4
Start: September 02, 2015
End : September 15, 2015
AREA 5
AREA 3A
AREA 2 AREA 1
AREA 3B
Start: July 25, 2015
End : September 02, 2015
T3
T1
T2
Start: June 09,2015
End : August 31, 2015
DONE
ON GOING
NOT YET DONE
2 1
TOTAL Volume : 367.36 m³
CONSTRUCTION ZONING & SEQUENCE
4. CONSTRUCTION METHODOLOGY
TOWER 1 (ROOF DECK SLAB)
V = 172.66 m³
D = 8 days
Start : 11-07-15
Finish: 11-15-15
V = 194.70 m³
D = 8 days
Start : 11-07-15
Finish: 11-15-15
ZONE 1
ZONE 2
4th
5th
6th
7th
8th
9th
10th
11th
12th
14th
15th
16th
Roof Deck
Machine Room FFL
Machine Room Deck
FOUNDATION WORKS START OCTOBER 1,2014
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
PODIUM LEVEL
4th
5th
PODIUM LEVEL
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
50% Supported
On going masonry works
100% Supported
CONCRETED FLOOR
August 06, 2015
4th
5th
6th
7th
8th
9th
On going Architectural Finishes
50% Supported
On going Masonry Works
Complete Structural Works at Podium Level
PODIUM LEVEL
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
CONCRETED FLOOR
September 19, 2015
100% Supported
Installation of Window frames
& application of Waterproofing
Interior Partitioning Works &
Installation of Window Glass
Start of Architectural Finishes
Painting at Exterior Walls
4th
5th
6th
7th
8th
9th
10th
11th
12th
14th
PODIUM LEVEL
On-going Architectural Finishes
Topping Off- Oct 20, 2015
On Going ID Fit out @ Residential Units
On going Architectural Finishes
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
50 % Supported
CONCRETED FLOOR
October 22, 2015
100 % Supported
Installation of Window frames
& application of Waterproofing
Interior Partitioning Works &
Installation of Window Glass
Painting at Exterior Walls
On going Construction of amenities
4th
5th
6th
7th
8th
9th
10th
11th
12th
14th
15th
16th
Roof Deck
Machine Room FFL
TOC Machine Room Deck
100 % Supported
PODIUM LEVEL
Topping Off- November 17, 2015
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
On going ID Fit out
Done ID Fit out on Residential areas
Done Architectural Finishes
50 % Supported
Installation of Window frames
& application of Waterproofing
Interior Partitioning Works &
Installation of Window Glass
Painting at Exterior Walls
On-going Architectural Finishes
Done ID Fit out
On going Works at amenities
On going Architectural
Works
4th
5th
6th
7th
8th
9th
10th
11th
12th
14th
15th
16th
Roof Deck
Machine Room FFL
TOC Machine Room Deck
On going Works at Amenities
PODIUM LEVEL
January 27, 2016
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)
Done ID Fit out
Done ID Fit out on Residential areas
Done Architectural Works
On-going
Architectural
Finishes
Painting at Exterior Walls
Start of Initial Punch Listing
of units and common areas
Building Fully Watertight
4th
5th
6th
7th
8th
9th
10th
11th
12th
14th
15th
16th
Roof Deck
Machine Room FFL
TOC Machine Room Deck
PODIUM LEVEL
October 20, 2016
Done Project Full Handover
4. CONSTRUCTION METHODOLOGY
(General Construction Sequence)

More Related Content

PDF
Dan wraggett professional portfolio school works
PDF
Dan Wraggett_Professional Portfolio_School Works
PPTX
Long span structures in Concrete and Steel
PPT
Presentazione negrini&varetto
PDF
Sample MSProject with 16 DivisionFormat Variation(EOT)
PDF
Pmr Planned Reports 2011 Construction Sector
PDF
Preparing Daily Construction Reports
PPT
Radiant Floor Applications
Dan wraggett professional portfolio school works
Dan Wraggett_Professional Portfolio_School Works
Long span structures in Concrete and Steel
Presentazione negrini&varetto
Sample MSProject with 16 DivisionFormat Variation(EOT)
Pmr Planned Reports 2011 Construction Sector
Preparing Daily Construction Reports
Radiant Floor Applications

Viewers also liked (15)

PPTX
SlabTek Foundation Outperforms Other Slab Options
PPTX
Elegance 72 unitised aluminium curtain wall system by Sapa Building System
PPTX
LOAD BEARING WALL
PPTX
Staticus presentation 2013
PDF
E n e r g o Cement Plant - Projects
PDF
Comparison of lateral analysis of reinforced concrete and steel silo
PDF
Vibrating machinery steel skid on piles
PDF
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
PDF
The Ins & Outs of Concrete Silo Inspection
PDF
Seismic response of reinforced concrete silos
PDF
Steel silo failure case study
PPT
Facade pattern
PDF
Sap tutorial for dynamics
PPT
Formwork
PDF
Post Tensioning System Utracon Structural system Pvt Ltd
SlabTek Foundation Outperforms Other Slab Options
Elegance 72 unitised aluminium curtain wall system by Sapa Building System
LOAD BEARING WALL
Staticus presentation 2013
E n e r g o Cement Plant - Projects
Comparison of lateral analysis of reinforced concrete and steel silo
Vibrating machinery steel skid on piles
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
The Ins & Outs of Concrete Silo Inspection
Seismic response of reinforced concrete silos
Steel silo failure case study
Facade pattern
Sap tutorial for dynamics
Formwork
Post Tensioning System Utracon Structural system Pvt Ltd
Ad

Similar to Construction Methodology Scheduling1 (20)

PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PDF
ScheduleRev- 6
PDF
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
PPT
rustomji urbania- technical presentation (r2) (1).ppt
PDF
Sample Project Monitoring-EVM Analysis
PDF
Project Monitoring with EVM Analysis
PDF
Adoradegoa Brochure for real estate and purchase
PDF
Adoradegoa-Oct24-Final-261124 Update for October
PDF
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
PPTX
Document design for presentation in class
PDF
Balinese residences at adora de goa
PPT
CONSTRUCTION USING FORMS
PPT
superstructure ppt.ppt
PDF
Method Statement Kota Kasablanka 3
PPTX
Creek Road Case Study - D.Higgins
PPTX
PLSH PPT
PPTX
Look Ahead Oct 11 to 24 - Keyplan.pptx
PDF
Working drawings
PDF
Pm final gann chart
PPTX
Sunshine_ W2 Dec'23_09.12.23.pptx
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
ScheduleRev- 6
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
rustomji urbania- technical presentation (r2) (1).ppt
Sample Project Monitoring-EVM Analysis
Project Monitoring with EVM Analysis
Adoradegoa Brochure for real estate and purchase
Adoradegoa-Oct24-Final-261124 Update for October
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Document design for presentation in class
Balinese residences at adora de goa
CONSTRUCTION USING FORMS
superstructure ppt.ppt
Method Statement Kota Kasablanka 3
Creek Road Case Study - D.Higgins
PLSH PPT
Look Ahead Oct 11 to 24 - Keyplan.pptx
Working drawings
Pm final gann chart
Sunshine_ W2 Dec'23_09.12.23.pptx
Ad

More from Allan Leyte (15)

PDF
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
PDF
BHP01-0 Bouly baseline on MSproject Format
PDF
WEIGHTING TABLE
PDF
PRODUCTION RATE APPX. NEW
PDF
Sample of Structural Steel Scheduling
PDF
p3 s-curves
PDF
Wreport
PDF
Visio-Planning FlowChart-3
PDF
Bissa Upgrade weekly report 09May2016
PDF
Booster Pump cause of delay analysis
PDF
Sample Bidcom Presentation - Structural Works 12-28-11
PDF
Scheduling SLEX (FS)-InitialCPM
PDF
Offshore Programme using QP-P3 protocol
PDF
progress photos
PDF
Town Center presentation
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
BHP01-0 Bouly baseline on MSproject Format
WEIGHTING TABLE
PRODUCTION RATE APPX. NEW
Sample of Structural Steel Scheduling
p3 s-curves
Wreport
Visio-Planning FlowChart-3
Bissa Upgrade weekly report 09May2016
Booster Pump cause of delay analysis
Sample Bidcom Presentation - Structural Works 12-28-11
Scheduling SLEX (FS)-InitialCPM
Offshore Programme using QP-P3 protocol
progress photos
Town Center presentation

Construction Methodology Scheduling1

  • 2. COLUMN FOOTING TO GROUND FLOOR (SUSPENDED SLAB) DONE AREA 4 AREA 6AREA 5 AREA 2AREA 1 AREA 3 T3 T1 T2 CONCRETING WORKS
  • 3. 3rd FLOOR (PODIUM FLOOR) CONCRETING WORKS Start: August 20, 2015 End : August 31, 2015 AREA 4 Start: August 22, 2015 End : September 02, 2015 AREA 5 AREA 1 T3 T1 T2 AREA 3B AREA 2 AREA 3A DONE
  • 4. 4th FLOOR SLAB CONCRETING WORKS Start: August 04, 2015 End : September 07, 2015 Start: June 01, 2015 End : September 07, 2015 Start: August 31, 2015 End : September 12, 2015 AREA 4 Start: September 02, 2015 End : September 15, 2015 AREA 5 AREA 3A AREA 2 AREA 1 AREA 3B Start: July 25, 2015 End : September 02, 2015 T3 T1 T2 Start: June 09,2015 End : August 31, 2015 DONE ON GOING NOT YET DONE
  • 5. 2 1 TOTAL Volume : 367.36 m³ CONSTRUCTION ZONING & SEQUENCE 4. CONSTRUCTION METHODOLOGY TOWER 1 (ROOF DECK SLAB) V = 172.66 m³ D = 8 days Start : 11-07-15 Finish: 11-15-15 V = 194.70 m³ D = 8 days Start : 11-07-15 Finish: 11-15-15 ZONE 1 ZONE 2
  • 6. 4th 5th 6th 7th 8th 9th 10th 11th 12th 14th 15th 16th Roof Deck Machine Room FFL Machine Room Deck FOUNDATION WORKS START OCTOBER 1,2014 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) PODIUM LEVEL
  • 7. 4th 5th PODIUM LEVEL 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) 50% Supported On going masonry works 100% Supported CONCRETED FLOOR August 06, 2015
  • 8. 4th 5th 6th 7th 8th 9th On going Architectural Finishes 50% Supported On going Masonry Works Complete Structural Works at Podium Level PODIUM LEVEL 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) CONCRETED FLOOR September 19, 2015 100% Supported Installation of Window frames & application of Waterproofing Interior Partitioning Works & Installation of Window Glass Start of Architectural Finishes Painting at Exterior Walls
  • 9. 4th 5th 6th 7th 8th 9th 10th 11th 12th 14th PODIUM LEVEL On-going Architectural Finishes Topping Off- Oct 20, 2015 On Going ID Fit out @ Residential Units On going Architectural Finishes 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) 50 % Supported CONCRETED FLOOR October 22, 2015 100 % Supported Installation of Window frames & application of Waterproofing Interior Partitioning Works & Installation of Window Glass Painting at Exterior Walls On going Construction of amenities
  • 10. 4th 5th 6th 7th 8th 9th 10th 11th 12th 14th 15th 16th Roof Deck Machine Room FFL TOC Machine Room Deck 100 % Supported PODIUM LEVEL Topping Off- November 17, 2015 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) On going ID Fit out Done ID Fit out on Residential areas Done Architectural Finishes 50 % Supported Installation of Window frames & application of Waterproofing Interior Partitioning Works & Installation of Window Glass Painting at Exterior Walls On-going Architectural Finishes Done ID Fit out On going Works at amenities On going Architectural Works
  • 11. 4th 5th 6th 7th 8th 9th 10th 11th 12th 14th 15th 16th Roof Deck Machine Room FFL TOC Machine Room Deck On going Works at Amenities PODIUM LEVEL January 27, 2016 4. CONSTRUCTION METHODOLOGY (General Construction Sequence) Done ID Fit out Done ID Fit out on Residential areas Done Architectural Works On-going Architectural Finishes Painting at Exterior Walls Start of Initial Punch Listing of units and common areas Building Fully Watertight
  • 12. 4th 5th 6th 7th 8th 9th 10th 11th 12th 14th 15th 16th Roof Deck Machine Room FFL TOC Machine Room Deck PODIUM LEVEL October 20, 2016 Done Project Full Handover 4. CONSTRUCTION METHODOLOGY (General Construction Sequence)