This document outlines the schedule for the DA-NAFC and LDC Building project from September 2013 to May 2015. It includes 265 tasks across various divisions such as civil works, concrete works, masonry works, and mechanical, electrical and plumbing works. Key milestones include the completion of formworks, reinforcement, and concrete pouring in January 2015. Testing and commissioning is scheduled to finish in May 2015. The document shows task durations, start and finish dates, and identifies critical tasks on the critical path with zero total slack. Variation orders were also incorporated to update the schedule.