Recommendation for commissioning testing
of medium voltage cables
The recommendation
© 2011 SebaKMT – MADE in GERMANY 2
Recommendation for commissioning
testing of medium voltage cables.
Includes:
 Sheath testing
 Withstand testing
 PD testing
 The treatment recommendation was created by the same work group,
which was responsible for the development of the VDE Cable Data Base
 Members of this working group are specialists of
- 18 Power Utilities
- 4 Universities
- 4 Service providers for testing and diagnosis
- 1 Accessory manufacturer
- 1 Cable consulting company
- 4 Manufacturers of PD measuring systems
Note: VDE cable database is a web-based database where PD measurements are stored
and where also the PD affected accessories has been inspected. This get a better
knowledge about the type of faults and its remaining life time. (www.VDE-Kabeldatenbank.de)
Initiators
© 2012 SebaKMT – MADE in GERMANY 3
 The experience of 20 years commissioning testing with 0.1 Hz VLF test
voltage indicate, that by a voltage test, only the very serious workmanship
failures are detected.
 There is a large variety of workmanship failures, which pass the com-
missioning tests, and fail only after several months or years of operation.
Target
 Fulfillment of the statutory requirements of the Operation Safety Act, the
BGV A3 and the VDE 0105 in respect to the commissioning test of newly
installed resp. modified electrical systems.
 Quality control of newly installed cables/ accessories by PD testing
 Gaining information for the condition assessment of cable systems
Motivation
© 2012 SebaKMT – MADE in GERMANY 4
Sheath Material PE PVC
Identification 2Y Y
Cable types (examples) NA2XS(F)2Y NA2XSY
Test voltage type DC DC
Test voltage level < 5 kV < 3 kV
Test duration < 5 min < 5 min
Typical leakage current < 100 µA/km < 800 µA/km @ 3 kV
Table 1: Test voltage levels and requirements
Contents
Cable sheath testing
© 2012 SebaKMT – MADE in GERMANY 5
N A 2X S 2Y 1 x 150 rm /25 12/20 kV
Norm cable acc. to DIN VDE
Conductor Material (A = Al / C = CU)
Shield (S = Cu / K = Pb)
Dielectric (2X = XLPE / Y = PVC)
Sheath (2Y = PE / Y = PVC)
Description of German abbreviations of cables
Contents
Cable sheath testing
© 2012 SebaKMT – MADE in GERMANY 6
Table 2: Overview of the voltage levels and durations to be used for plastic
and paper mass impregnated MV cables after repair or reallocation.
Insulation DC AC 45 Hz < f < 65 Hz AC f = 0,1 Hz
Test Level
UT = x Uo
Test
duration
min
Test
Level
UT = x Uo
Test
duration
min
Test Level
UT = x Uo
Test
duration
min
PVC Uo/U=6/10 kV
34 to 48 kV
Uo/U=12/20 kV
67 to 96 kV
Uo/U=18/30 kV
76 to 108 kV
15 to 30 2 30
XLPE, PE 2 60 3 60
PILC and mixed
cables with PVC
Uo/U=6/10 kV
34 to 48 kV
Uo/U=12/20 kV
67 to 96 kV
Uo/U=18/30 kV
76 to 108 kV
15 to 30 2 30 3 30
Mixed cables of
XLPE/PE with
PVC and PILC
2 60 3 60
Contents
Cable withstand testing (aged/ in-service cables)
© 2012 SebaKMT – MADE in GERMANY 7
Experiences of 20 years commissioning tests with 0.1 Hz VLF test voltages
indicated that this reveals only the very serious workmanship failures. There
is a large variety of workmanship issues which pass the VLF commissioning
tests, and fail only after several months/ years of operation under load.
Field statistics on newly installed cables indicates that test failures appear
within 15 to 30 minutes of operation. Test durations of 60 minutes produced
no additional information or results. Therefore, a test duration of 30 minutes
is considered as sufficient.
A significant amount of the faults that are probably not detected during the
withstand tests can be detected and localized by an additional partial
discharge measurement.
Testing of cable insulation after new installation of pure XLPE Cables
Contents
Cable withstand testing (new cables)
© 2012 SebaKMT – MADE in GERMANY 8
PD Measurements for commissioning tests
PD measurements allows to check the cable installation quality as well
as the condition of the complete system installation. Potential fault
spots can be detected in an early stage, and an evaluation of the
system and a budgeting of the required investments can be made.
A fundamental rule is:
Partial discharges occurring at U0 indicates a high risk of operating.
PD measurement test systems with the following type of voltages are
commercially available:
 0.1 Hz VLF (VLF – Very Low Frequency)
 20 – 300 Hz AC (AC – Alternating Current)
100 – 500 Hz damped AC ( DAC – Damped AC)
Contents
Cable withstand testing (new cables)
© 2012 SebaKMT – MADE in GERMANY 9
PD Measurement for quality assurance on newly installed systems
Newly installed cable accessories are, with a correct installation, PD free up
to at least 1.7 U0.
Field experiences showed that some types of accessories require several
load changes resp. temperature cycles, before they are PD free. This has
to be considered during the evaluation, or the PD test has to be repeated
after some load cycles.
The voltage has to be increased in steps up to the maximum test voltage
level. Possible PD signal have to recorded.
The test voltage has to be present for a sufficient duration to enable a
reliable detection of fault spots and to confirm the dielectric strength.
Contents
Cable withstand testing (new cables)
© 2012 SebaKMT – MADE in GERMANY 10
PD Measurement for quality assurance on newly installed systems
For different voltage types, the following test procedure is recommended:
0,1 Hz VLF - Stepwise increase of the test voltage up to 2 U0
- 10 minutes stress duration @ 2 U0 to test the
dielectric strength and operational readiness
20 – 300 Hz - Stepwise increase of the test voltage up to 2 U0
- 5 minutes stress duration @ 2 U0 to test the
dielectric strength and operational readiness
100 – 500 Hz DAC - Stepwise increase of the test voltage up to 1.7 U0
- VWD (multiple test 50 cycles) @ 1.7 U0 to test the
dielectric strength and operational readiness
Contents
Cable withstand testing (new cables)
© 2012 SebaKMT – MADE in GERMANY 11
Test result Evaluation Recommendation
No detectable
PD
Test passed Requirement BNL < 100 pC (BNL = background noise level)
For cables with high attenuation (during calibration with 1000 pC, no end
reflection detectable) the PD measurement must be performed from
both ends.
Ui < Uo Test not passed Replacement of the affected accessories, new measurement on the new
installed accessory (confirmation of the PD fault spot only based on
visible installation errors, there are not PD tracks visible)
Entry into www.VDE-Kabeldatenbank.de)
For operational reasons, a temporary net operation after passed test
acc. to table 2 is permittable.
Ui between 1
and 1.7 Uo
Commissioning
of the cable
system possible,
but repeated
tests after 4 to 8
weeks
Result of the repeated measurement:
- If Ui  1.7 Uo the test is passed
- If Ui < 1.7 Uo the test is not passed
-Replacement of the affected accessories (visual inspection to identify
the installation errors and PD fault spots (Voids, de-lamination,
tracking/PD erosion) Entry into www.VDE-Kabeldatenbank.de)
In exceptional situations, at Ui between 1.2 and 1.7 Uo, the system can
be released for continuous operation. In this case annual repeated
measurements to control the stability of Ui have to be performed.
Contents
Cable withstand testing (new cables)
Table 3: Evaluation and recommendation of measurement results
© 2012 SebaKMT – MADE in GERMANY 12
Case Procedure Requirements
New cables
(completely new installation)
- Sheath testing
- 0.1 Hz VLF test
alternatively
- PD measurement
Table 1
Table 2, Part 2.2
Table 3
Aged cables
(Fault elimination, partial
replacement, re-jointing, loop
insertion
- Sheath testing
- 0.1 Hz VLF test
alternatively
- PD measurement
Table 1
Table 2, Part 2.2
Table 3
The PD measurement has to be considered as a qualitative valuable part of the
commissioning test
Contents
Final recommended procedures
Table 4: Recommendation for testing of MV cables
© 2012 SebaKMT – MADE in GERMANY 13
Contact
Name: Hein Putter
Telefon: 0049-1759361560
E-Mail: putter.h@sebakmt.com
Thank you for your attention!
© 2012 SebaKMT – MADE in GERMANY 14
For more info please visit our website:
www.sebakmt.com
© 2012 SebaKMT – MADE in GERMANY 15

More Related Content

PDF
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
PDF
Deis talk-nov-2014-revised
PDF
Results of 10 years after installation tests with partial discharge detection...
PDF
P D Measurements On H V Joints
PDF
Insulation testing of power cable
PDF
KEMET EMC Filter Applications
PDF
Assuring Reliability of Critical Power Cable Systems
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Deis talk-nov-2014-revised
Results of 10 years after installation tests with partial discharge detection...
P D Measurements On H V Joints
Insulation testing of power cable
KEMET EMC Filter Applications
Assuring Reliability of Critical Power Cable Systems

What's hot (20)

PDF
Construction and Test Results for Automotive Conductive Polymer Capacitors
PDF
EE-55 Power Cables Testing & Fault Location
PDF
Advances in Ceramic Capacitors
PDF
Webinar 85 85-box_dc_link
PDF
Split core ct, rogowski coil (2016)
PDF
Transformer Oil Testing services
DOCX
Kaizenreport
PDF
K-SIM Usage and Techniques for Simulating KEMET Capacitors
PDF
Runlite 38mm Filament LED LM-80 test report.PDF
PDF
Michael Wood - Loader electric shocks, a case study
PDF
Multifunction Calibrator By Zeal Manufacturing And Calibration Services Priva...
PDF
Power transformer maintenance
PDF
A2.34+transformer+maintenance+tutorial
PDF
Ceramic Safety Capacitors - Avoiding the Confusion
PDF
The Cable Sniffer - A New & Proven Technique For Locating LV Cable Faults
PPTX
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
PPTX
Understanding isoiec 14763 3 cabling standards
PDF
KEMET AEC Reliability 2016 Workshop Slides
PPTX
New ALS70/80 Series & Press-Fit
PDF
Box DC Link in industrial and automotive applications
Construction and Test Results for Automotive Conductive Polymer Capacitors
EE-55 Power Cables Testing & Fault Location
Advances in Ceramic Capacitors
Webinar 85 85-box_dc_link
Split core ct, rogowski coil (2016)
Transformer Oil Testing services
Kaizenreport
K-SIM Usage and Techniques for Simulating KEMET Capacitors
Runlite 38mm Filament LED LM-80 test report.PDF
Michael Wood - Loader electric shocks, a case study
Multifunction Calibrator By Zeal Manufacturing And Calibration Services Priva...
Power transformer maintenance
A2.34+transformer+maintenance+tutorial
Ceramic Safety Capacitors - Avoiding the Confusion
The Cable Sniffer - A New & Proven Technique For Locating LV Cable Faults
Traditional Ratio, Burden, Admittance and Demag Testing – Part I
Understanding isoiec 14763 3 cabling standards
KEMET AEC Reliability 2016 Workshop Slides
New ALS70/80 Series & Press-Fit
Box DC Link in industrial and automotive applications
Ad

Viewers also liked (15)

PDF
C&I Cables Tests
PDF
Basic Partial Discharge
PDF
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
PPTX
New Approaches for Maintenance Grounding in Medium Voltage Switchgear
PPT
Seminar on Partial Discharge detection methods
PPTX
Partial Discharge Detection Products by EA Technology
PDF
IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...
PDF
Hv Cable Testing
PDF
cable testing and intallation
PPTX
Joints and terminations
PPTX
Switchgear presentation
PPTX
Switchgear presentation
PPTX
Precise kilometer calculation by underground cable fault detector
PPTX
Switchgear presentation
PPTX
Underground cables
C&I Cables Tests
Basic Partial Discharge
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
New Approaches for Maintenance Grounding in Medium Voltage Switchgear
Seminar on Partial Discharge detection methods
Partial Discharge Detection Products by EA Technology
IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...
Hv Cable Testing
cable testing and intallation
Joints and terminations
Switchgear presentation
Switchgear presentation
Precise kilometer calculation by underground cable fault detector
Switchgear presentation
Underground cables
Ad

Similar to Heinputter 2 (20)

PPT
Pruebas de cables con VLF (Very Low Frequency)
PDF
B10d en
PDF
Cable test set_easytest_20_kv
PDF
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
DOC
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
PDF
IEEE-Alberta_Partial-Discharge.pdf
PPTX
IEEE-Alberta_Partial-Discharge new high voltages .pptx
PDF
Relay testing procedure
PDF
ABB Instrumentation. Automation products, ProcessMaster
PDF
Seaward Catalog High Voltage Test Tools
PDF
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
PPT
OWTS M28.ppt
PDF
ipec mtekpro joint venture technology for testing and measuring instruments
PDF
Seaward KD1E High Voltage HV Indicators & Detectors, Phasing Units, Ammeters ...
PPTX
570523777-Digital-Testing-of-High-Voltage-Circuit-Breaker-2.pptx
PDF
ABB Training Manual.pdf
PDF
DereMurray - APEC 2014 - Noise Susceptibility of delta-Vbe Temperature Sensors
DOCX
Electrical testing
PDF
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
PDF
Comparison of Different Voltage Waveforms for Cable PD Testing.pdf
Pruebas de cables con VLF (Very Low Frequency)
B10d en
Cable test set_easytest_20_kv
Brosur Fluke Insulation Resistance Testing. Hubungi PT. Siwali Swantika 021-4...
Gabriel Ojeah - HV CONFERENCE PAPER- PERTH 2015
IEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge new high voltages .pptx
Relay testing procedure
ABB Instrumentation. Automation products, ProcessMaster
Seaward Catalog High Voltage Test Tools
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
OWTS M28.ppt
ipec mtekpro joint venture technology for testing and measuring instruments
Seaward KD1E High Voltage HV Indicators & Detectors, Phasing Units, Ammeters ...
570523777-Digital-Testing-of-High-Voltage-Circuit-Breaker-2.pptx
ABB Training Manual.pdf
DereMurray - APEC 2014 - Noise Susceptibility of delta-Vbe Temperature Sensors
Electrical testing
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
Comparison of Different Voltage Waveforms for Cable PD Testing.pdf

Heinputter 2

  • 1. Recommendation for commissioning testing of medium voltage cables
  • 2. The recommendation © 2011 SebaKMT – MADE in GERMANY 2 Recommendation for commissioning testing of medium voltage cables. Includes:  Sheath testing  Withstand testing  PD testing
  • 3.  The treatment recommendation was created by the same work group, which was responsible for the development of the VDE Cable Data Base  Members of this working group are specialists of - 18 Power Utilities - 4 Universities - 4 Service providers for testing and diagnosis - 1 Accessory manufacturer - 1 Cable consulting company - 4 Manufacturers of PD measuring systems Note: VDE cable database is a web-based database where PD measurements are stored and where also the PD affected accessories has been inspected. This get a better knowledge about the type of faults and its remaining life time. (www.VDE-Kabeldatenbank.de) Initiators © 2012 SebaKMT – MADE in GERMANY 3
  • 4.  The experience of 20 years commissioning testing with 0.1 Hz VLF test voltage indicate, that by a voltage test, only the very serious workmanship failures are detected.  There is a large variety of workmanship failures, which pass the com- missioning tests, and fail only after several months or years of operation. Target  Fulfillment of the statutory requirements of the Operation Safety Act, the BGV A3 and the VDE 0105 in respect to the commissioning test of newly installed resp. modified electrical systems.  Quality control of newly installed cables/ accessories by PD testing  Gaining information for the condition assessment of cable systems Motivation © 2012 SebaKMT – MADE in GERMANY 4
  • 5. Sheath Material PE PVC Identification 2Y Y Cable types (examples) NA2XS(F)2Y NA2XSY Test voltage type DC DC Test voltage level < 5 kV < 3 kV Test duration < 5 min < 5 min Typical leakage current < 100 µA/km < 800 µA/km @ 3 kV Table 1: Test voltage levels and requirements Contents Cable sheath testing © 2012 SebaKMT – MADE in GERMANY 5
  • 6. N A 2X S 2Y 1 x 150 rm /25 12/20 kV Norm cable acc. to DIN VDE Conductor Material (A = Al / C = CU) Shield (S = Cu / K = Pb) Dielectric (2X = XLPE / Y = PVC) Sheath (2Y = PE / Y = PVC) Description of German abbreviations of cables Contents Cable sheath testing © 2012 SebaKMT – MADE in GERMANY 6
  • 7. Table 2: Overview of the voltage levels and durations to be used for plastic and paper mass impregnated MV cables after repair or reallocation. Insulation DC AC 45 Hz < f < 65 Hz AC f = 0,1 Hz Test Level UT = x Uo Test duration min Test Level UT = x Uo Test duration min Test Level UT = x Uo Test duration min PVC Uo/U=6/10 kV 34 to 48 kV Uo/U=12/20 kV 67 to 96 kV Uo/U=18/30 kV 76 to 108 kV 15 to 30 2 30 XLPE, PE 2 60 3 60 PILC and mixed cables with PVC Uo/U=6/10 kV 34 to 48 kV Uo/U=12/20 kV 67 to 96 kV Uo/U=18/30 kV 76 to 108 kV 15 to 30 2 30 3 30 Mixed cables of XLPE/PE with PVC and PILC 2 60 3 60 Contents Cable withstand testing (aged/ in-service cables) © 2012 SebaKMT – MADE in GERMANY 7
  • 8. Experiences of 20 years commissioning tests with 0.1 Hz VLF test voltages indicated that this reveals only the very serious workmanship failures. There is a large variety of workmanship issues which pass the VLF commissioning tests, and fail only after several months/ years of operation under load. Field statistics on newly installed cables indicates that test failures appear within 15 to 30 minutes of operation. Test durations of 60 minutes produced no additional information or results. Therefore, a test duration of 30 minutes is considered as sufficient. A significant amount of the faults that are probably not detected during the withstand tests can be detected and localized by an additional partial discharge measurement. Testing of cable insulation after new installation of pure XLPE Cables Contents Cable withstand testing (new cables) © 2012 SebaKMT – MADE in GERMANY 8
  • 9. PD Measurements for commissioning tests PD measurements allows to check the cable installation quality as well as the condition of the complete system installation. Potential fault spots can be detected in an early stage, and an evaluation of the system and a budgeting of the required investments can be made. A fundamental rule is: Partial discharges occurring at U0 indicates a high risk of operating. PD measurement test systems with the following type of voltages are commercially available:  0.1 Hz VLF (VLF – Very Low Frequency)  20 – 300 Hz AC (AC – Alternating Current) 100 – 500 Hz damped AC ( DAC – Damped AC) Contents Cable withstand testing (new cables) © 2012 SebaKMT – MADE in GERMANY 9
  • 10. PD Measurement for quality assurance on newly installed systems Newly installed cable accessories are, with a correct installation, PD free up to at least 1.7 U0. Field experiences showed that some types of accessories require several load changes resp. temperature cycles, before they are PD free. This has to be considered during the evaluation, or the PD test has to be repeated after some load cycles. The voltage has to be increased in steps up to the maximum test voltage level. Possible PD signal have to recorded. The test voltage has to be present for a sufficient duration to enable a reliable detection of fault spots and to confirm the dielectric strength. Contents Cable withstand testing (new cables) © 2012 SebaKMT – MADE in GERMANY 10
  • 11. PD Measurement for quality assurance on newly installed systems For different voltage types, the following test procedure is recommended: 0,1 Hz VLF - Stepwise increase of the test voltage up to 2 U0 - 10 minutes stress duration @ 2 U0 to test the dielectric strength and operational readiness 20 – 300 Hz - Stepwise increase of the test voltage up to 2 U0 - 5 minutes stress duration @ 2 U0 to test the dielectric strength and operational readiness 100 – 500 Hz DAC - Stepwise increase of the test voltage up to 1.7 U0 - VWD (multiple test 50 cycles) @ 1.7 U0 to test the dielectric strength and operational readiness Contents Cable withstand testing (new cables) © 2012 SebaKMT – MADE in GERMANY 11
  • 12. Test result Evaluation Recommendation No detectable PD Test passed Requirement BNL < 100 pC (BNL = background noise level) For cables with high attenuation (during calibration with 1000 pC, no end reflection detectable) the PD measurement must be performed from both ends. Ui < Uo Test not passed Replacement of the affected accessories, new measurement on the new installed accessory (confirmation of the PD fault spot only based on visible installation errors, there are not PD tracks visible) Entry into www.VDE-Kabeldatenbank.de) For operational reasons, a temporary net operation after passed test acc. to table 2 is permittable. Ui between 1 and 1.7 Uo Commissioning of the cable system possible, but repeated tests after 4 to 8 weeks Result of the repeated measurement: - If Ui  1.7 Uo the test is passed - If Ui < 1.7 Uo the test is not passed -Replacement of the affected accessories (visual inspection to identify the installation errors and PD fault spots (Voids, de-lamination, tracking/PD erosion) Entry into www.VDE-Kabeldatenbank.de) In exceptional situations, at Ui between 1.2 and 1.7 Uo, the system can be released for continuous operation. In this case annual repeated measurements to control the stability of Ui have to be performed. Contents Cable withstand testing (new cables) Table 3: Evaluation and recommendation of measurement results © 2012 SebaKMT – MADE in GERMANY 12
  • 13. Case Procedure Requirements New cables (completely new installation) - Sheath testing - 0.1 Hz VLF test alternatively - PD measurement Table 1 Table 2, Part 2.2 Table 3 Aged cables (Fault elimination, partial replacement, re-jointing, loop insertion - Sheath testing - 0.1 Hz VLF test alternatively - PD measurement Table 1 Table 2, Part 2.2 Table 3 The PD measurement has to be considered as a qualitative valuable part of the commissioning test Contents Final recommended procedures Table 4: Recommendation for testing of MV cables © 2012 SebaKMT – MADE in GERMANY 13
  • 14. Contact Name: Hein Putter Telefon: 0049-1759361560 E-Mail: putter.h@sebakmt.com Thank you for your attention! © 2012 SebaKMT – MADE in GERMANY 14
  • 15. For more info please visit our website: www.sebakmt.com © 2012 SebaKMT – MADE in GERMANY 15