IMPALA
North-West, Rustenburg
PROJECT TYPE: OPENCAST MINING
CLIENT:
Impala Platinum Mine
VALUE:
R340 Million
CONSULTANTS:
None
PROJECT DURATION:
Contract renewable annually
DATE OF PROJECT:
1 April 1998
PROJECT DESCRIPTION:
Opencast Mining of both Merensky and UG2
Reef to a depth of 35m. Contract is renewed on
annual basis.
Approximate volumes mined for the project :-
• Blasted over burden 37,438,859m³
• Topsoil 5,841,186m³
• Ore 2,347,362m³
• Topsoil Rehab 5,695,638m³
• Filling Void 12,724,866m³

More Related Content

PDF
Project-sheet Blinkwater TSF
PDF
Kombat Copper Corporate Presentation
PPT
Working with Dragline
PPT
Mining machinary nit rourkela
PPTX
Shovel excavator
PPT
Concept of oc mine planning & design(final)
PDF
Openpit Design Fundas
PDF
Openpit fundamentals
Project-sheet Blinkwater TSF
Kombat Copper Corporate Presentation
Working with Dragline
Mining machinary nit rourkela
Shovel excavator
Concept of oc mine planning & design(final)
Openpit Design Fundas
Openpit fundamentals

More from Gert Buitendach (9)

PDF
GJB CMP 2014 Group Foto
PDF
Kuseleka Opencast
PDF
Reef crushing - Lonmin
PDF
Sasol mafutha
PDF
Vlakfontein Coal Mine
PDF
Project-sheet Lonmin deepening
PDF
Project-sheet beeshoek
PDF
Concor Opencast previous experience
PDF
Ocm divisional company profile
GJB CMP 2014 Group Foto
Kuseleka Opencast
Reef crushing - Lonmin
Sasol mafutha
Vlakfontein Coal Mine
Project-sheet Lonmin deepening
Project-sheet beeshoek
Concor Opencast previous experience
Ocm divisional company profile
Ad

Recently uploaded (20)

DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PPTX
Project Management_ SMART Projects Class.pptx
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPTX
Astra-Investor- business Presentation (1).pptx
PDF
Solaris Resources Presentation - Corporate August 2025.pdf
PPTX
Negotiation and Persuasion Skills: A Shrewd Person's Perspective
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PDF
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
PPTX
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
PPTX
basic introduction to research chapter 1.pptx
PDF
Introduction to Generative Engine Optimization (GEO)
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Slide gioi thieu VietinBank Quy 2 - 2025
Project Management_ SMART Projects Class.pptx
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Astra-Investor- business Presentation (1).pptx
Solaris Resources Presentation - Corporate August 2025.pdf
Negotiation and Persuasion Skills: A Shrewd Person's Perspective
Hand book of Entrepreneurship 4 Chapters.docx
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
Slide gioi thieu VietinBank Quy 2 - 2025
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
basic introduction to research chapter 1.pptx
Introduction to Generative Engine Optimization (GEO)
Principles of Marketing, Industrial, Consumers,
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
Charisse Litchman: A Maverick Making Neurological Care More Accessible
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
Ad

Impala Opencast Mining

  • 1. www.construction.murrob.com IMPALA North-West, Rustenburg PROJECT TYPE: OPENCAST MINING CLIENT: Impala Platinum Mine VALUE: R340 Million CONSULTANTS: None PROJECT DURATION: Contract renewable annually DATE OF PROJECT: 1 April 1998 PROJECT DESCRIPTION: Opencast Mining of both Merensky and UG2 Reef to a depth of 35m. Contract is renewed on annual basis. Approximate volumes mined for the project :- • Blasted over burden 37,438,859m³ • Topsoil 5,841,186m³ • Ore 2,347,362m³ • Topsoil Rehab 5,695,638m³ • Filling Void 12,724,866m³