Planning and Scheduling for a Multi-Storied Building using MS-Project
Sachin Pashupatihal1, Prof. Vidyasagar V. Moogi2
1M.TECH (CCT) Student, Civil Engineering Dept. Jain College of Engineering, Belagavi, Karnataka, India
2Assistant Professor, Civil Engineering Dept. Jain College of Engineering, Belagavi, Karnataka, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - The object of the present work is to study the
scheduling methods and construction system of work for
multistorey buildings and to achieve the application of
Microsoft project software in planning and scheduling of a
multistorey RCC building construction and cost of
conformance for the project. To complete the above objectives
a hypothetical RCC residential G+7 building is considered. The
complete planning and schedulingofthis buildingisstudiedby
traditional technique used by Architects, Engineers and
contractors and is compared by modern software technique.
For this approach Microsoft project software is used for
planning and scheduling the RCC building. Observation shows
that Microsoft project software serves as an effective tool for
generating Gantt chart for the schedule of a construction
project and offers the minimum duration of construction time
by schedule crunching and project crashing methods in
software. Present work presents good information about the
application of Microsoft project software for the planningand
scheduling of building construction.
Key Words: Project, Time, Cost, Scheduling, Resource
Allocation, construction, Critical Path Method (CPM)
1. INTRODUCTION
The Building professional as an integral component of a
nation’s structure and plays an important role in financial
growth through multiple effects on other sectors of
economy. Companiesarealwayslookingfordevelopmentsin
utilities features, communication tools, effective
management methods, and harnessing human resources.
There are many issues being faced by the civil engineering
and most of them are time and cost related, due to
inadequate project planning and incorrect management
during completing. Many project planners say that the cost
of the project goes above the planned cost by 30% and it is
due to improper planning and scheduling. Largescaleworks
become more difficult so the opportunity of exchanging
information on papers with establishments at regular
intervals becomes nearly difficult. The casual project
management system cannot reach the demands of today’s
projects, as huge amount of data and evidence of a project
are always changeable. Project managers in the civil
engineering say that the amount of time spent on
communication is 70-80% and project certification is 70%
paper prone. A warning mechanism must be fulfilled which
can alarm the association aboutitsprojectsachievement and
failures in the meantime. Projects with better planning,
sufficient flow of resources and adequate machines cannot
achieve good results on its own. There has to be some
alerting mechanism, which can alarm the association about
its success and failures, on and off.
In India, due to an increasingly local and international
competition, construction companies are always motivated
for maximum productivity and a economical operational
benefit. Companies are always looking for developments in
equipment features, communication tools, efficient
management methods, and training human resources. They
are also narrowing their focus to study in certain projects
instead of taking up all forms of it. This specialization
requires a very streamlined method for monitoring
techniques and extremely good planning for the best
services. The profits of operative planning, scheduling and
control of building projects are: reduced construction time,
decreases cost overruns.
1.1 Project
The projects are the temporary striving which has
undertaken to create the unique products, results and
services.
Each and every Project will have an unmistakable start
date and moreover an end date. The projects are termed
finished just when the reason proposed has been
accomplished or when it has been chosen that the reason
can't be accomplished. For instance, if theventureistocreate
software design and it is wound upbybuildingupthesame,it
has said to be reason accomplished. The primary vital
element that decidesa projectis"Temporary".Theimportant
point to be noted for that the word temporary need not
means short. A task can keep going for6 months, or1year,or
even up till 10 years, yet the length of there has a positive
start and an end date for the task, it would be called as a
Project.
Also, project are "Unique" in nature, i.e. no two tasks can
have hundred percent closeness between them. In order to
explain a task is a project, the unique feature of the task
should be prominent, the minimumbringonefeatureatleast.
The individuality may not be obtainable in all parts of the
project. There can be recurrences in theprojectactivitiesand
deliverables, but the objective attempted for differs. For
occurrence, the exchange reasonable being directed each
year in any of the month has another project being doneeach
year, as it expects to undertake an alternate target a
apparently endless amount of time. The developingactivities
don't require exhausting planning since that will be gone to,
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1802
all the live long day. Be that as it may, as projects are one of
the unique kind we need to plan it in point of importance to
decrease the variabilities.
The key components of any task would be as per the
following:
 Project has described start and end date.
 End results are particular and responsible.
 Projects are logically expounded.
 The result of the project might be unique.
1.2 Microsoft Project
Microsoft Project is a project management software
product, established and sold by Microsoft. It is planned to
assist a project manager in increasing a plan, assigning
resources to tasks, tracking progress, managing the
inexpensive, and analysing workloads. MS project can be
used as a standalone tool for tracking project progress or it
can be used for tracking complexprojectdistributedin many
geographical areas and achieved by a number of project
managers. Microsoft project is planned to assist aaproject
manager in;
1. Developing a plan,
2. Assigning resources to tasks,
3. Tracking progress,
4. Managing budget and
5. Analysing workloads
1.3 Objective of Study
The main objective of this study is
1) To develop effective schedule by defining the various
activities and arranging these activities in an appropriate
sequential order.
2) To identify the resources required for all activities,
allocating and managing the same with efficiency.
3) Estimate duration required to complete the individual
activity with the available resources
4) To estimate the resources of the project according to the
quantities calculated.
5) Using Parametricandanalogousestimationcalculationsof
duration and resources.
6) Developing Critical Path Method to calculate total
duration of the project and its critical task.
7) Optimization of scheduling using fasttracking,crashingof
the duration and Bottom Up Estimation.
8) To identify the cost of quality of the Budget as per the
scope. Namely
 Cost of conformance
 Cost of non-conformance.
2. LITERATURE REVIEW
Shruti Singh, Shweta Istape, Amruta Surve, SahilPandey,
Avinash Singh, Sangram More (2018) In this study the
Planning and Scheduling has been done and the site where
located near Karjat, Mumbai, India. According to the
estimation they got 20 months to complete this building as
per their planning. For this building they have done CPM and
PERT analysis for Planning. After MSP work the project time
was completed in18monthsbyproperallocation.Hencethey
concluded that the MSP methodofplanningandschedulingis
more scientific.
Monish Kumar K, MaheshwarSMaregoudru,SparshaB.P
(2017) In this study they taken a Apartment for a project
work. The methodology has been done in two phases in first
phase collection of data andalsostructuraldrawings,soiltest
report, are collected and in second phase actual scheduling
process starts by using MS Project. After obtaining results
they concluded that Using MSP as a construction project
managementtool,projectplanningisdoneaccurately,Budget
cost of the project is easily obtained.
Pooja Tripathi, Vinay Kumar Singh, Pravin Singh Tomar,
J. P. Gupta (2018) By using Microsoft they made a study on
RCC building Project, and the objective of the project scopeis
to study the scheduling techniqueandconstructionsequence
for a multi-storey building. To achieve the above objectivesa
hypothetical RCC residential G+4 building is considered. The
traditional software which is used by the contractor is
compared with Microsoft Project. After obtaining the result
the MSP software works on Gantt chart concept. This gives
the easy considerate of the development of the work. It says
that the MS Project is more economical than traditional one.
3. METHODOLOGY
The Microsoft Project is used in this project. A proper start
and end time must be a project have. Within the obtainable
funds and resources the project must be completed and
within the assigned time the task must be managed by
achieving this a project can be complete in a defined period.
The procedure of the work in this process can be carried out
in the following way. The flow diagram of the process is
obtainable below.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1803
Fig -1: Flow Chart of Methodolgy
In the Microsoft Project the planning of the construction,the
programming and the optimization of the resources are
done. The methodology used for this project were the
activity was defined first, to prepare a programming report
the several activities were used with the different logical
relations and durations. Then, collecting a availability of
resources and assigning were this can be obtained by the
critical path, the levelling and analysis will be carried out
and the results will be concluded. In the below MSP the
activity were completely described in the following steps.
1. Planning
 Data Collections
 Quantity Surveying
2. Scheduling
3. Resource Optimization
 Resource Allocation
 Resource Levelling
4. Cost Benefit Analysis
Cost Benefit Analysis: It relates the cost of the quality with
the benefit derived from meeting the quality. The primary
advantage of achieving quality necessities are:
 Stakeholder’s satisfaction
 Costs are lower
 Productivity is higher
 Less rework
4. INVESTIGATION AND ANALYSIS
4.1 Estimation of the Project
The estimated data of the projectwherecollectedfromoffice
where the project were studied. The given format is in the
form of excel and the calculated quantities of earthwork
Excavated, steel reinforcement required, concrete quantity
etc were given. This were calculated and was summarized in
a excel sheet.
4.2 Planning, Scheduling and Budgeting In MSP
After Collecting the Building Estimation, the resource are
calculated and for each activity will be allocated with
duration in the sequence of the activity will be done further
in MSP the work Breakdown structure will be created by
using Intending and Out ending the activities. The activities
will be linked later with one another by giving the
predecessors.
The Resources like Manpower, Material and Machinery are
used for the allocating the resource for the specified activity
for the budgeting purpose. The rate per unity should be
given by the resources where allocatedsothatthenumberof
resource required to allocate forthespecifiedactivitysothat
the software automatically computes the total price for that
activity later the total budget of the project, and total cost of
all activity will be given.
Fig -2: Planning of Project in MSP
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1804
4.3 Resource Calculation
The labour productivity sheet where given by the company,
the required quantity of work were calculated depending on
which the labour requiredtocompletethe required quantity.
Depending on the duration of the activity the same was
implemented to planning, the number of labours required
per day can be changed. If again any changes required in the
number of labours.
4.4 Identifying the Critical path
Everyatask is essential, but only some of them are critical.
The critical path is a chain of linked tasksthatdirectlyaffects
the project finish date. If any task on the critical path is late,
the complete project is late.
The critical path is a series of tasks that controls the planned
start or finish date of the project. The tasksathatmakeupthe
critical path are typically interrelated by task needs. There
are likely to be many such networks of task throughoutyour
project plan. When the last task in the critical path is
finished, the project is also complete.
Fig -3: Critical Path of the Project
4.5 Cost Benefit Analysis
According to the cost of conformance the supervisor are
assigning to the each activity andQualityControl andQuality
Assurance is assigned for steel and concrete works this has
been done to reduce the over run of the cost after
completion of the project. Before spending 1% to2%oftotal
estimated cost we will be able to control the project over
run.
Fig -4: Supervisor and QA/QC resource sheet
Fig -5: Resource allocation for supervisor and QA/QC
5. RESULTS AND DISCUSSION
In this project using Microsoft Project the Projectduration is
optimized. By creating the WBS (Work Break down
Structure) and allocating the resources the total duration of
the project is calculated by planning and scheduling the
project. And also the cost benefit analysis has been done the
total cost of the project has been increased by 1% to 3% for
allocating supervisors and Quality Assurance and Quality
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1805
Control for the activities, the cost conformance can be
achieved.
5.1 Time Optimization
Efficiently scheduling the project for 768 days using CPM.
Fig -6: Critical path Method in MSP
5.2 Resource Calculation
According to the quantity of the project surveyed the
resource are calculated according to the productivity sheet
where given by the company the required quantity of work
were calculated depending on which the labour required to
complete required quantity.
Chart -1: Total duration for workers
5.3 Fast Tracking
The duration of the project was found to be 768 days after
fast tracking. The start to start predecessor were used for
the fast tracking process.
Fig -7: Fast tracking
5.4 Cost of conformance
Chart -2: Total duration for supervisor and QA/QC
Chart -3: Total cost for supervisor and QA/QC
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1806
Total cost of Conformance = Supervisor + QA/QC
= 216637.5 + 155400
= 372037 Rupees
6. CONCLUSIONS
Following conclusion can be made from the result obtained
from the project.
 Features like Critical Path MethodinMicrosoftProjectfor
Planning and Scheduling is proved to be very effective
then doing manual Planning and Scheduling
 Optimization of the Duration was carried out by Fast
tracking, Crashing and bottom of estimation to decrease
the duration of the project to 768 Days.
 After carrying out the duration Optimization it helped to
define the resource and its quantities.
 Microsoft Project helps to understand the under
allocation and over allocation of the Project and allows it
to level the resources timely.
 As we have estimated the activity duration using
parametric and analogousEstimation wecouldachieveto
get the accurate duration of the task.
 With the seven Basic Quality tools Project was executed
with zero defects.
 Adding on Extra resource in terms of supervisors and
Quality AssuranceQuality Control on to the tasks to
ensure the Quality in controlled and Monitored
throughout the duration of the Project therefore Cost of
Conformance = 3,72,037Rs
 According to the survey of KPMG, it says that after the
completion of the project, the overall cost of the project
10% to 30% of the cost will over run. The above cost of
conformance Graph it proves that spending
approximately 1% to 3% of total estimated cost we will
be able to control the project over run.
REFERENCES
[1] Shruti Singh, Shweta Istape, Amruta Surve, Sahil Pandey,
Avinash Singh,SangramMore.2018."COMPARATIVESTUDY
OF PLANNING AND SCHEDULING OF A CONSTRUCTION
PROJECT USING MICROSOFT PROJECT." IJRET:International
Journal of Research in Engineering and Technology, Volume
7, Issue 6, PP.32-40.
[2] Monish Kumar K, MaheshwarSMaregoudru,Sparsha B.P.
2017. "Construction Project Scheduling of MK Apartment
Using." International Research Journal of Engineering and
Technology (IRJET), Volume 4, Issue 7, PP.2275-2279.
[3] Pooja Tripathi, Vinay KumarSingh,Pravin Singh Tomar,J.
P. Gupta. 2018. "PLANNING AND SCHEDULING OF
MULTISTOREY RCC BUILDING USING MICROSOFT
PROJECT." International Journal of Engineering Science
Invention Research & Development Volume 4, Issue 11,
PP.356-364.
BIOGRAPHIES
Sachin Pashupatihal
M.TECH(CCT)Student, Civil
Engineering Dept. Jain College of
Engineering, Belagavi.
Karnataka, India
Prof. Vidyasagar V. Moogi
Assistant Professor, Civil
Engineering Dept. Jain College of
Engineering. Belagavi.
Karnataka

More Related Content

PDF
76 s201905
PDF
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
PDF
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
PDF
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
PDF
Construction Project Scheduling of MK Apartment using MS Project 2013
PDF
How software size influence productivity and project duration
PDF
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
PDF
Project Planning and Scheduling
76 s201905
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
Construction Project Scheduling of MK Apartment using MS Project 2013
How software size influence productivity and project duration
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Project Planning and Scheduling

What's hot (18)

PDF
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
PDF
I012335763
PDF
Project management tools and techniques- tutorsindia.com
PDF
Efficient Planning Scheduling and Delay Analysis of Residential Project
PDF
IRJET- Identification of Constraints and there Impact on Construction Pro...
PDF
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
PDF
Planning and Optimization of Resource Constrained Project Scheduling by using...
PDF
76 s201903
PDF
Planning
PDF
AN INTEGRATED MANAGEMENT AND MEASUREMENT OF CUSTOMER FEASIBLILTY IN CONSTRUCT...
PDF
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
DOCX
Assignment 2 : People in Projects
PDF
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
PDF
Earned Value Management for Design and Construction Project
PDF
Project Management overview talk 2021
PDF
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
PDF
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
DOCX
Project Management Leadership, And Skills : Planning And Control | Assignment...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
I012335763
Project management tools and techniques- tutorsindia.com
Efficient Planning Scheduling and Delay Analysis of Residential Project
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
Planning and Optimization of Resource Constrained Project Scheduling by using...
76 s201903
Planning
AN INTEGRATED MANAGEMENT AND MEASUREMENT OF CUSTOMER FEASIBLILTY IN CONSTRUCT...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Assignment 2 : People in Projects
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
Earned Value Management for Design and Construction Project
Project Management overview talk 2021
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
Project Management Leadership, And Skills : Planning And Control | Assignment...
Ad

Similar to IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project (20)

PDF
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
PDF
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
PDF
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
PDF
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
PDF
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
PDF
Resource scheduling in Construction Project Using Microsoft Project
PPTX
Construction project scheduling and quality control
PDF
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
PDF
Scheduling by using microsoft project 2013
PDF
H1303024956
DOCX
Latest Microsoft Project 2013 for civil work planning.docx
PDF
IRJET- Application of ABC Analysis for Material Management and Planning a...
PDF
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
DOCX
Microsoft Project 2013 training manual for civil engineering.docx
PDF
Ijciet 10 01_075
PPTX
Resource scheduling in Construction Projects Using MSP
PDF
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
PDF
Scheduling and Financial Analysis of a High Rise Building
PDF
A012610106
PPTX
Planning & Scheduling 222030008.pptx
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
Resource scheduling in Construction Project Using Microsoft Project
Construction project scheduling and quality control
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Scheduling by using microsoft project 2013
H1303024956
Latest Microsoft Project 2013 for civil work planning.docx
IRJET- Application of ABC Analysis for Material Management and Planning a...
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
Microsoft Project 2013 training manual for civil engineering.docx
Ijciet 10 01_075
Resource scheduling in Construction Projects Using MSP
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
Scheduling and Financial Analysis of a High Rise Building
A012610106
Planning & Scheduling 222030008.pptx
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
PPT on Performance Review to get promotions
PPTX
Sustainable Sites - Green Building Construction
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPT
Mechanical Engineering MATERIALS Selection
PPTX
additive manufacturing of ss316l using mig welding
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Geodesy 1.pptx...............................................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
OOP with Java - Java Introduction (Basics)
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPT on Performance Review to get promotions
Sustainable Sites - Green Building Construction
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Model Code of Practice - Construction Work - 21102022 .pdf
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Mechanical Engineering MATERIALS Selection
additive manufacturing of ss316l using mig welding
Internet of Things (IOT) - A guide to understanding
Geodesy 1.pptx...............................................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Lecture Notes Electrical Wiring System Components
Foundation to blockchain - A guide to Blockchain Tech
bas. eng. economics group 4 presentation 1.pptx
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
OOP with Java - Java Introduction (Basics)

IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1801 Planning and Scheduling for a Multi-Storied Building using MS-Project Sachin Pashupatihal1, Prof. Vidyasagar V. Moogi2 1M.TECH (CCT) Student, Civil Engineering Dept. Jain College of Engineering, Belagavi, Karnataka, India 2Assistant Professor, Civil Engineering Dept. Jain College of Engineering, Belagavi, Karnataka, India ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - The object of the present work is to study the scheduling methods and construction system of work for multistorey buildings and to achieve the application of Microsoft project software in planning and scheduling of a multistorey RCC building construction and cost of conformance for the project. To complete the above objectives a hypothetical RCC residential G+7 building is considered. The complete planning and schedulingofthis buildingisstudiedby traditional technique used by Architects, Engineers and contractors and is compared by modern software technique. For this approach Microsoft project software is used for planning and scheduling the RCC building. Observation shows that Microsoft project software serves as an effective tool for generating Gantt chart for the schedule of a construction project and offers the minimum duration of construction time by schedule crunching and project crashing methods in software. Present work presents good information about the application of Microsoft project software for the planningand scheduling of building construction. Key Words: Project, Time, Cost, Scheduling, Resource Allocation, construction, Critical Path Method (CPM) 1. INTRODUCTION The Building professional as an integral component of a nation’s structure and plays an important role in financial growth through multiple effects on other sectors of economy. Companiesarealwayslookingfordevelopmentsin utilities features, communication tools, effective management methods, and harnessing human resources. There are many issues being faced by the civil engineering and most of them are time and cost related, due to inadequate project planning and incorrect management during completing. Many project planners say that the cost of the project goes above the planned cost by 30% and it is due to improper planning and scheduling. Largescaleworks become more difficult so the opportunity of exchanging information on papers with establishments at regular intervals becomes nearly difficult. The casual project management system cannot reach the demands of today’s projects, as huge amount of data and evidence of a project are always changeable. Project managers in the civil engineering say that the amount of time spent on communication is 70-80% and project certification is 70% paper prone. A warning mechanism must be fulfilled which can alarm the association aboutitsprojectsachievement and failures in the meantime. Projects with better planning, sufficient flow of resources and adequate machines cannot achieve good results on its own. There has to be some alerting mechanism, which can alarm the association about its success and failures, on and off. In India, due to an increasingly local and international competition, construction companies are always motivated for maximum productivity and a economical operational benefit. Companies are always looking for developments in equipment features, communication tools, efficient management methods, and training human resources. They are also narrowing their focus to study in certain projects instead of taking up all forms of it. This specialization requires a very streamlined method for monitoring techniques and extremely good planning for the best services. The profits of operative planning, scheduling and control of building projects are: reduced construction time, decreases cost overruns. 1.1 Project The projects are the temporary striving which has undertaken to create the unique products, results and services. Each and every Project will have an unmistakable start date and moreover an end date. The projects are termed finished just when the reason proposed has been accomplished or when it has been chosen that the reason can't be accomplished. For instance, if theventureistocreate software design and it is wound upbybuildingupthesame,it has said to be reason accomplished. The primary vital element that decidesa projectis"Temporary".Theimportant point to be noted for that the word temporary need not means short. A task can keep going for6 months, or1year,or even up till 10 years, yet the length of there has a positive start and an end date for the task, it would be called as a Project. Also, project are "Unique" in nature, i.e. no two tasks can have hundred percent closeness between them. In order to explain a task is a project, the unique feature of the task should be prominent, the minimumbringonefeatureatleast. The individuality may not be obtainable in all parts of the project. There can be recurrences in theprojectactivitiesand deliverables, but the objective attempted for differs. For occurrence, the exchange reasonable being directed each year in any of the month has another project being doneeach year, as it expects to undertake an alternate target a apparently endless amount of time. The developingactivities don't require exhausting planning since that will be gone to,
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1802 all the live long day. Be that as it may, as projects are one of the unique kind we need to plan it in point of importance to decrease the variabilities. The key components of any task would be as per the following:  Project has described start and end date.  End results are particular and responsible.  Projects are logically expounded.  The result of the project might be unique. 1.2 Microsoft Project Microsoft Project is a project management software product, established and sold by Microsoft. It is planned to assist a project manager in increasing a plan, assigning resources to tasks, tracking progress, managing the inexpensive, and analysing workloads. MS project can be used as a standalone tool for tracking project progress or it can be used for tracking complexprojectdistributedin many geographical areas and achieved by a number of project managers. Microsoft project is planned to assist aaproject manager in; 1. Developing a plan, 2. Assigning resources to tasks, 3. Tracking progress, 4. Managing budget and 5. Analysing workloads 1.3 Objective of Study The main objective of this study is 1) To develop effective schedule by defining the various activities and arranging these activities in an appropriate sequential order. 2) To identify the resources required for all activities, allocating and managing the same with efficiency. 3) Estimate duration required to complete the individual activity with the available resources 4) To estimate the resources of the project according to the quantities calculated. 5) Using Parametricandanalogousestimationcalculationsof duration and resources. 6) Developing Critical Path Method to calculate total duration of the project and its critical task. 7) Optimization of scheduling using fasttracking,crashingof the duration and Bottom Up Estimation. 8) To identify the cost of quality of the Budget as per the scope. Namely  Cost of conformance  Cost of non-conformance. 2. LITERATURE REVIEW Shruti Singh, Shweta Istape, Amruta Surve, SahilPandey, Avinash Singh, Sangram More (2018) In this study the Planning and Scheduling has been done and the site where located near Karjat, Mumbai, India. According to the estimation they got 20 months to complete this building as per their planning. For this building they have done CPM and PERT analysis for Planning. After MSP work the project time was completed in18monthsbyproperallocation.Hencethey concluded that the MSP methodofplanningandschedulingis more scientific. Monish Kumar K, MaheshwarSMaregoudru,SparshaB.P (2017) In this study they taken a Apartment for a project work. The methodology has been done in two phases in first phase collection of data andalsostructuraldrawings,soiltest report, are collected and in second phase actual scheduling process starts by using MS Project. After obtaining results they concluded that Using MSP as a construction project managementtool,projectplanningisdoneaccurately,Budget cost of the project is easily obtained. Pooja Tripathi, Vinay Kumar Singh, Pravin Singh Tomar, J. P. Gupta (2018) By using Microsoft they made a study on RCC building Project, and the objective of the project scopeis to study the scheduling techniqueandconstructionsequence for a multi-storey building. To achieve the above objectivesa hypothetical RCC residential G+4 building is considered. The traditional software which is used by the contractor is compared with Microsoft Project. After obtaining the result the MSP software works on Gantt chart concept. This gives the easy considerate of the development of the work. It says that the MS Project is more economical than traditional one. 3. METHODOLOGY The Microsoft Project is used in this project. A proper start and end time must be a project have. Within the obtainable funds and resources the project must be completed and within the assigned time the task must be managed by achieving this a project can be complete in a defined period. The procedure of the work in this process can be carried out in the following way. The flow diagram of the process is obtainable below.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1803 Fig -1: Flow Chart of Methodolgy In the Microsoft Project the planning of the construction,the programming and the optimization of the resources are done. The methodology used for this project were the activity was defined first, to prepare a programming report the several activities were used with the different logical relations and durations. Then, collecting a availability of resources and assigning were this can be obtained by the critical path, the levelling and analysis will be carried out and the results will be concluded. In the below MSP the activity were completely described in the following steps. 1. Planning  Data Collections  Quantity Surveying 2. Scheduling 3. Resource Optimization  Resource Allocation  Resource Levelling 4. Cost Benefit Analysis Cost Benefit Analysis: It relates the cost of the quality with the benefit derived from meeting the quality. The primary advantage of achieving quality necessities are:  Stakeholder’s satisfaction  Costs are lower  Productivity is higher  Less rework 4. INVESTIGATION AND ANALYSIS 4.1 Estimation of the Project The estimated data of the projectwherecollectedfromoffice where the project were studied. The given format is in the form of excel and the calculated quantities of earthwork Excavated, steel reinforcement required, concrete quantity etc were given. This were calculated and was summarized in a excel sheet. 4.2 Planning, Scheduling and Budgeting In MSP After Collecting the Building Estimation, the resource are calculated and for each activity will be allocated with duration in the sequence of the activity will be done further in MSP the work Breakdown structure will be created by using Intending and Out ending the activities. The activities will be linked later with one another by giving the predecessors. The Resources like Manpower, Material and Machinery are used for the allocating the resource for the specified activity for the budgeting purpose. The rate per unity should be given by the resources where allocatedsothatthenumberof resource required to allocate forthespecifiedactivitysothat the software automatically computes the total price for that activity later the total budget of the project, and total cost of all activity will be given. Fig -2: Planning of Project in MSP
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1804 4.3 Resource Calculation The labour productivity sheet where given by the company, the required quantity of work were calculated depending on which the labour requiredtocompletethe required quantity. Depending on the duration of the activity the same was implemented to planning, the number of labours required per day can be changed. If again any changes required in the number of labours. 4.4 Identifying the Critical path Everyatask is essential, but only some of them are critical. The critical path is a chain of linked tasksthatdirectlyaffects the project finish date. If any task on the critical path is late, the complete project is late. The critical path is a series of tasks that controls the planned start or finish date of the project. The tasksathatmakeupthe critical path are typically interrelated by task needs. There are likely to be many such networks of task throughoutyour project plan. When the last task in the critical path is finished, the project is also complete. Fig -3: Critical Path of the Project 4.5 Cost Benefit Analysis According to the cost of conformance the supervisor are assigning to the each activity andQualityControl andQuality Assurance is assigned for steel and concrete works this has been done to reduce the over run of the cost after completion of the project. Before spending 1% to2%oftotal estimated cost we will be able to control the project over run. Fig -4: Supervisor and QA/QC resource sheet Fig -5: Resource allocation for supervisor and QA/QC 5. RESULTS AND DISCUSSION In this project using Microsoft Project the Projectduration is optimized. By creating the WBS (Work Break down Structure) and allocating the resources the total duration of the project is calculated by planning and scheduling the project. And also the cost benefit analysis has been done the total cost of the project has been increased by 1% to 3% for allocating supervisors and Quality Assurance and Quality
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1805 Control for the activities, the cost conformance can be achieved. 5.1 Time Optimization Efficiently scheduling the project for 768 days using CPM. Fig -6: Critical path Method in MSP 5.2 Resource Calculation According to the quantity of the project surveyed the resource are calculated according to the productivity sheet where given by the company the required quantity of work were calculated depending on which the labour required to complete required quantity. Chart -1: Total duration for workers 5.3 Fast Tracking The duration of the project was found to be 768 days after fast tracking. The start to start predecessor were used for the fast tracking process. Fig -7: Fast tracking 5.4 Cost of conformance Chart -2: Total duration for supervisor and QA/QC Chart -3: Total cost for supervisor and QA/QC
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1806 Total cost of Conformance = Supervisor + QA/QC = 216637.5 + 155400 = 372037 Rupees 6. CONCLUSIONS Following conclusion can be made from the result obtained from the project.  Features like Critical Path MethodinMicrosoftProjectfor Planning and Scheduling is proved to be very effective then doing manual Planning and Scheduling  Optimization of the Duration was carried out by Fast tracking, Crashing and bottom of estimation to decrease the duration of the project to 768 Days.  After carrying out the duration Optimization it helped to define the resource and its quantities.  Microsoft Project helps to understand the under allocation and over allocation of the Project and allows it to level the resources timely.  As we have estimated the activity duration using parametric and analogousEstimation wecouldachieveto get the accurate duration of the task.  With the seven Basic Quality tools Project was executed with zero defects.  Adding on Extra resource in terms of supervisors and Quality AssuranceQuality Control on to the tasks to ensure the Quality in controlled and Monitored throughout the duration of the Project therefore Cost of Conformance = 3,72,037Rs  According to the survey of KPMG, it says that after the completion of the project, the overall cost of the project 10% to 30% of the cost will over run. The above cost of conformance Graph it proves that spending approximately 1% to 3% of total estimated cost we will be able to control the project over run. REFERENCES [1] Shruti Singh, Shweta Istape, Amruta Surve, Sahil Pandey, Avinash Singh,SangramMore.2018."COMPARATIVESTUDY OF PLANNING AND SCHEDULING OF A CONSTRUCTION PROJECT USING MICROSOFT PROJECT." IJRET:International Journal of Research in Engineering and Technology, Volume 7, Issue 6, PP.32-40. [2] Monish Kumar K, MaheshwarSMaregoudru,Sparsha B.P. 2017. "Construction Project Scheduling of MK Apartment Using." International Research Journal of Engineering and Technology (IRJET), Volume 4, Issue 7, PP.2275-2279. [3] Pooja Tripathi, Vinay KumarSingh,Pravin Singh Tomar,J. P. Gupta. 2018. "PLANNING AND SCHEDULING OF MULTISTOREY RCC BUILDING USING MICROSOFT PROJECT." International Journal of Engineering Science Invention Research & Development Volume 4, Issue 11, PP.356-364. BIOGRAPHIES Sachin Pashupatihal M.TECH(CCT)Student, Civil Engineering Dept. Jain College of Engineering, Belagavi. Karnataka, India Prof. Vidyasagar V. Moogi Assistant Professor, Civil Engineering Dept. Jain College of Engineering. Belagavi. Karnataka