Application of Time Divisions Scheduling Techniques for Duration and
Quantity based Project Control is a Vivacious Decision Process
Balaprasad Vitthal Gajul1, Gaurav Desai2
1Postgraduate student, Department of Civil Engineering, School Engineering and Technology, Sandip University
Nashik, Maharashtra, India
2Assistant Professor, Department of Civil Engineering, School Engineering and Technology, Sandip University
Nashik, Maharashtra, India.
-------------------------------------------------------------------------***------------------------------------------------------------------------
Abstract— the scheduling plays crucial part for planning, executing, controlling, monitoring and closing the construction
projects within stipulated time and in budget. The construction projects are complex in nature because there are various
activities which are interconnected to each other and have to be completed in stipulated time limit and given budget. The
Gantt chart and CPM have some drawbacks make these tools insufficient for project tracking, monitoring and reviewing of
projects on account of both these tools are based on only duration of project activities. But, it is observed that in actual
construction projects activities are connected to each other not only related to duration but also with the quantity of work.
Hence the project unable to perform as per planned schedule requirements.
This study offers a modified new scheduling technique to overcome the limitations of Gantt and Critical path
method using Unit Time & Work Divisions Technique tool that offers a daily tracking, monitoring and reviewing of project
schedule. To overcome periodical review of schedule by adopting the duration as well as work quantity of each activity
into separate divisions. This new scheduling technique is expected to help project managers to achieve a better level of
control over projects with better conceptualization, optimization and determination reinforce to meet project success.
Key words: Monitoring and reviewing, Interrelationship of activities, Critical Path Divisions scheduling Technique
(CPD), Work quantity and Project control.
1. INTRODUCTION
The successful completion of project in construction industry mainly depends on completion of project in scheduled
time and in budget. The Project Tracking, Monitoring and Control based on Duration and quantity divisions scheduling
Techniques is a vivacious decision process. The construction project consist number of activities which are interconnected
to each other hence management tracking monitoring reviewing and controlling of such projects till completion of project
entirely is very distraught and complexity job,. The project managers/ site Engineer are generally handle project with
Gantt Charts and Critical Path Method (CPM). The project manager/ site Engineer use Gantt charts and critical path
method to determine the inter relationship of activities. While schedule of the project mainly the project duration,
activities float times, data about the degree flexibleness related to the schedule of project and the critical or non-
criticalness of the activities are very important.
Project managers/ site Engineer generally adopt two methods that are Gantt Chart Method and Critical Path Method
(CPM). The short coming of these two methods that these methods are based on only duration of project tracking. These
two methods neither tracked duration as well as quantity of work. There are some lacunas in Critical Path Method (CPM)
and Gantt Chart Method this study gives the new method of scheduling technique considering Critical Path Division (CPD)
techniques that gives a daily tracking monitoring and reviewing of project scheduling by showing the duration as well as
quantity of each activity into different divisions. The technique is supportive to project manager/ site Engineer to control
the project not only from start to end with excellent control but also give support to take decision each day duration as
well as quantity wise to complete the project within stipulated time period successfully.
2. METHODOLOGY
There are some lacunas in Critical Path Method (CPM) and Gantt Chart Method this study gives the new method of
scheduling technique considering Critical Path Division (CPD) techniques that gives a daily tracking monitoring and
reviewing of project scheduling by showing the duration as well as quantity of each activity into different divisions.
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6290
Figure No: 1 Flow Chart of Methodology
The following way traditional activity duration is divided in number of days as shown below
Table 1. Show the activity in network analysis as per critical path division technique
1 E 2
4days
A. Traditional representation of activities in network
E1 E2 E3 E4
1st day 2nd day 3rd day 4th day
4 days representation
B. Representation of activities by critical path division
technique
Result discussion and conclusion
Validation of modified techniques
Develop a new alternative scheduling model by modifying the above of commonly
used techniques by handling the relationship between activities by divisonal the
time in seperate time divisions work out quantities of each activity and determine
the work quantity for each time division for individual activity
Find out the areas in the above techniques which makes themless effcienet for
project control and hence project success
Identify the commonly used management techniques for planning, scheduling and
project control CPM and Gantt Chart
Study of various management techniques
by literature survey by discussion with field professionals
Problem Statement
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6291
The work quantity of activities are divided in day work and duration also suppose the exaction is going to
executed in 4 days then each day the work should be done 25% as per base plan schedule. Presentation can be shown as
following.
Table 2. Representation of Work by duration as well as Quantity of an activity
Excavation activity split in 4 days i.e 100/4 = 25%
E1 E2 E3 E4
1st day 2nd day 3rd day 4th day
25% 25% 25% 25%
4 days representation
Representation of activities by time and work division technique
This technique able to do day to day activity dividing rather than activity-by-activity which provided in critical path
method (CPM). This technique helps to monitor base line to work done schedule on time division technique. (Daily
monitoring the progress not only on duration basis but also work quantity basis).
Table 3. Representation of Day by Day Update in Scheduling
3. OBJECTIVES OF RESEARCH
The construction industry have number of activities and they are interconnected to each other hence to complete
the project in stipulated time and budget. This study develop an effective method of scheduling model for construction
E1 E2 E3 E4 E1 E2 E3 E4
25% 25% 25% 25% 10% 35% 35% 20%
P1 P2 P3 P4 P1 P2 P3 E4
25% 25% 25% 25% 20% 20% 30% 30%
A. As per planned schedule A. As per Build schedule
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6292
projects. It beats the hindrances of management techniques, which are commonly used during project control, Tracking,
review and monitoring.
Detailed objectives:
 The scheduling techniques used in construction industry commonly by professionals and its study.
 The discussion with experts, and extensive review on advantages disadvantages and effectiveness of different
scheduling techniques like Gantt chart and (CPM) critical path method. Literature review and survey on different
scheduling and management technique. The questioner data survey.
 The detail study procedures of implementation and improvement in CPM and Gantt chart.
Develop an alternative and improved new scheduling technique model mechanism that is based on divisional activity
durations and work quantity.
4. NEED OF THE STUDY
The construction industry project manager/ site Engineer using Gantt chart and critical path method for scheduling
construction projects even though there are some lacunas in these techniques. The traditional representation of critical
path method and Gantt chart lacks the ability to clearly represent and record details as-built information like slow or fast
progress of project and complete, representation of work interruptions caused by the various parties involved. Critical
path method is based on two unrealistic assumptions: that the project deadline is not restricted and that resources are
unlimited. Therefore, the most cost-effective corrective actions needed in order to recover delays and overruns in project
is required in these techniques.
Both these techniques are when acts as baseline for measuring progress, it is difficult to use it to initiate appropriate
corrective actions for recovering delays and overruns. The following list shows the most critical views of CPM and Gantt
Charts.
 In critical path method activates considers only Finish to Start relationship while many construction activities
consists Start to Start and Finish to Finish relationships. Gantt Charts shows the relationship of all activities all but
not able to decide critical and non-critical activities. Both critical path method and Gantt chart are not provide the
perfect critical days of individual activities,
 Gantt chart and critical path method considers only time relationship of activities but the construction industry
project activities are interrelated to each other related not only duration but also quantity of work.
 Critical path method and Gantt chart techniques are in sufficient to daily decision making and revision of project plan
and schedule.
 These critical path method and Gantt chart could be difficult to update. After several updates have been done, it
becomes hard to read. Schedules updates are usually out of date when they are finished.
The construction industry project have many complex projects the scheduling technique CPM network may be
complicated. That makes it very difficult to communicate and understand.
When the construction project comes in execution stage the monitoring and tracking was important to track the project
as per base line schedule of project.
As per general practice the project tracking and monitoring activity done by critical path method and Gantt chart
periodically as per planned start and finish time only.
The construction industry in many countries in world done survey for delays. The study conducted in India by the
Infrastructure and Project Monitoring Division of the Ministry of Statistics and Program Implementation in 2004 they
reported that out of 646 central sector projects costing about $50 trillion, approximately 40% are behind schedule, with
delays ranging from 1 to 252 months (Lyer and Jha, 2006). Which denotes that construction industry projects not perform
as per initial planning and schedules.
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6293
5. DATA COLLECTION QUESTIONER SURVEY
Questioner survey denoted that there is requirement of day to day monitoring in simple excel format for consultants,
project manage and site Engineer.
Figure 2 shows questioner survey graphical presentation
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6294
Data collection
Name of project: Residential Building.
Address: Sr.No.886/B, P.No.6 Rane nagar Mumbai
Agra road, Nashik-422009
Name of owner: Shri. Dattatray Kondaji Thete
Through Developer and GPA Holder Shree Gurudatta
Construction Through Proprietor
shri. Yadunath Baburao Vibhute
Area of Construction: 805.25sq.M
Type of Building: G+4RCC Structure
Total Duration of Project (Planned): 180 days.
Start Date: 12/03/2018.
End Date (Planned): 03/05/2019.
Name of contractor: Shri. Anil N Yeola and Stru. Engg.
Anil N Yeola of Nashik.
Total no. of Activities: 73
Figure 3 show the completed residential project
6. DATA ANALYSIS
1. Analysis of Data collected from Questionnaire Survey
The questionnaire survey show that the most consultant/ site Engineer/ contractor generally use excel sheet for their
daily work but it is insufficient to show daily tracking of project duration wise and quantity wise hence this study initiated.
2. Analysis of Data Collected from the case study
Figure 4. Gantt chart for day to day monitoring time division method
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6295
In above Gantt chart the activity split in the days duration hence it shows that the activity is not itself
critical but some of days of activity are critical.
- The red capsule indicate the critical days of that activity.
- The blue capsule indicate the non-critical days of that activity.
7. Result and discussion:
The traditional representation of Gantt chart represented by using MS-Project shows the critical activities of
project which are shown by red colour bars for total activities which is Critical activities.
Figure No 4 shows the same Gantt chart but based on the unit division scheduling mechanism which describes
each segments ( activity dived in days) of every activity of entire project. As it is also represented by using MS-project it
provides exact critical days of activities involved in project. Excavation Activity has only three days are critical shown by
red colour where as traditional Gantt chart shows the whole activity is critical for the same schedule. This shows the
effectiveness of Unit division Scheduling Technique over traditional Gantt chart technique for scheduling.
8. Conclusion
In mainly construction industry the two scheduling methods adopted that are Critical path method and Gantt chart
(Bar Chart), Critical Path Method (CPM) generally in commonly used for scheduling the construction projects by project
Engineer/ project managers. This two Critical path method and Gantt Chart (Bar Chart) methods have some drawbacks
to provide successful decision making reinforce for projects Critical path method (CPM ) shows Critical activities and
critical path but not able to show the data of interrelationship of activities that are in project. . Gantt chart not able to
show data of critical activities.
The completion of project in schedule time and given budget the project the project manager/ site Engineer deal to
actual monitoring of project and to overcome lacunas in Critical Path Method (CPM) and Gantt Chart Method this study
gives the new method of scheduling technique considering Critical Path Division(CPD) techniques with its mathematical
formulation that gives a daily tracking monitoring and reviewing of project scheduling by showing the duration as well as
quantity of each activity into different divisions.
In this method the production and time base relationship between the each activates. This two component based
method gives vivacious decision process having following advantage.
 At very Nano- level critical path division method.
 Nice approach to understanding the project scheduling
 In progress of work very less time required to re schedule.
 We can avoid the very complex project relationship in activities scheduling.
 Nice construction project monitoring tracking reviewing by using not only duration but also quantity
(production) based scheduling for completion of project in time and budget.
 It gives us very accurate analysis of schedule during the execution and after execution of project.
REFERENCES
1. Shailla (2014), “Comparative Study of Management Operation System Techniques (MOST) and CPM in Construction
Scheduling.” International Journal of Engineering Trends and Technology (IJETT), 18-8, pp371-379.
2. David Arditi, Onur B. Tokdemir2 and KangsukSuh (2002), “Challenges in Line-of-Balance Scheduling.” Journal of
Construction Engineering and Management, ASCE, 128, pp545-556.
3. Ron Winter, F. BurakEvrenosoglu (2011), “MS Project for Construction Schedulers.” The AACE International 55th
Annual Meeting, California, USA.
4. Fang-Ying Shen, Andrew S. Chang (2014), “Effectiveness of Coordination Metods in Construction Projects.” Journal of
Management in Engineering, ASCE.
5. Gunnar Lucko (2009), “Productivity Scheduling Method: Linear Schedule Analysis with Singularity Functions.”
Journal of Construction Engineering and Management, ASCE, 135, pp246-253.
6. YakubuOlawale and Ming Sun (2013), “PCIM: Project Control and Inhibiting-Factors Management Model.” Journal of
Management in Engineering, ASCE, 29, pp60-70.
7. Lihui Zhang, Jianxun Qi (2012), “Controlling Path and Controlling Segment Analysis in Repetitive Scheduling
Method.” Journal of Construction Engineering and Management, ASCE, 138, pp1341-1345.
INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056
VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6296
8. TarekHegazy, and Wail Menesi, (2008), “Delay Analysis under Multiple Baseline Updates.” Journal of Construction
Engineering and Management, ASCE, 136, pp1078-1085
9. Galloway P. D. (2006). "Survey of the construction industry relative to the use of CPM scheduling for construction
projects." Journal of Construction Engineering and Management, ASCE, 132(7), pp697–711
10. D. K. H. Chua, L. J. Shen and S. H. Bok (2003), “Constraint-Based Planning with Integrated Production Scheduler over
Internet.” Journal of Construction Engineering and Management, ASCE, 129, pp293-301.
11. Rene´ A. Yamı´n and David J. Harmelink (2001), “Comparison of Linear Scheduling Model (LSM) and Critical Path
Method (CPM).” Journal of Construction Engineering and Management, ASCE, 127, pp374-381.
12. Patricia D. Galloway. (2006). “Survey of the Construction Industry Relative to the Use of CPM Scheduling for
Construction Projects.” Journal of Construction Engineering and Management, ASCE, 132, pp697-711.
13. Su-Ling Fan and H. P. Tserng (2006), “Object-Oriented Scheduling for Repetitive Projects with Soft Logics.” Journal of
Construction Engineering and Management, ASCE, 132, pp35-48.
14. Ming Lu1 and Heng Li (2003), “Resource-Activity Critical-Path Method for Construction Planning.” Journal of
Construction Engineering and Management, ASCE, 129, 412-420.
15. William Ibbs, Long D. Nguyen (2007), “Schedule Analysis under the effect of resource Allocation.” Journal of
Construction Engineering and Management, ASCE, 133, 133-138.
16. PasitLorterapong, MongkolUssavadilokrit (2013), “ Construction Scheduling Using the Constraint Satisfaction
Problem Method.” Journal of Construction Engineering and Management, ASCE, 139, pp414-422.
17. Daniel Castro-Lacoture, Gursel A Suer, Julian Gonzalez-joaqui and J. K. Yates (2009), “Construction Project Scheduling
with Time, Cost and Material Restrictions using Fuzzy Mathematical Models and Critical Path Method.” Journal of
Construction Engineering and Management, ASCE, 135, pp1096-1104
18. Kenneth O. Hartley (1993), “How to make Project Schedules Really Work for You.” Journal of Management in
Engineering, ASCE, 9, pp167-173.

More Related Content

PDF
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
PDF
IRJET- Scheduling and Labour Management for Residential Building Project usin...
PDF
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
PPTX
Resource scheduling in Construction Projects Using MSP
PDF
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
PDF
Resource scheduling in Construction Project Using Microsoft Project
PDF
Line of Balance
PDF
Methodologies of Project Progress Measurement
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
Resource scheduling in Construction Projects Using MSP
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
Resource scheduling in Construction Project Using Microsoft Project
Line of Balance
Methodologies of Project Progress Measurement

What's hot (17)

PDF
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
DOCX
edSe275 ms project-assignment
PDF
Meeting Project Schedule Compliance Standards
PDF
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
PDF
PERT, GANTT CHART and BENCHMARKING
PPSX
Project Management 4 Schedule Management
PDF
Application of Earned Value Method and Delay Analysis on Construction Project...
PDF
construction project planing
PDF
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
PDF
Review on Planning and Scheduling of Construction Project by Management Tool ...
PDF
CCP_SEC3_Planning and Scheduling
PPTX
PERT Ghant chart and bench marking with application to nursing
PDF
IIRJET-Cost Control Techniques for Construction Project
DOCX
Use of network scheduling technique
PDF
Construction Management - New Trends
DOCX
Construction Planning and Scheduling of Residential Building by MS Project by...
PDF
IRJET- Value Management
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
edSe275 ms project-assignment
Meeting Project Schedule Compliance Standards
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
PERT, GANTT CHART and BENCHMARKING
Project Management 4 Schedule Management
Application of Earned Value Method and Delay Analysis on Construction Project...
construction project planing
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
Review on Planning and Scheduling of Construction Project by Management Tool ...
CCP_SEC3_Planning and Scheduling
PERT Ghant chart and bench marking with application to nursing
IIRJET-Cost Control Techniques for Construction Project
Use of network scheduling technique
Construction Management - New Trends
Construction Planning and Scheduling of Residential Building by MS Project by...
IRJET- Value Management
Ad

Similar to IRJET- Application of Time Divisions Scheduling Techniques for Duration and Quantity based Project Control is a Vivacious Decision Process (20)

PDF
Ijciet 10 01_075
PDF
Literature Review in Project Scheduling Techniques
PPTX
PM-5 chapter project management (1).pptx
PPTX
PM-chapter 00005 project management.pptx
PDF
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
PDF
Scheduling coordination and control of projects
PPTX
lecture 14.construction project management
PDF
Critical path method with detailed description
PDF
IRJET- Critical Chain Project Management in Construction Projects
PPTX
PERT and CPM
PPTX
Nce603 mod unit1
PDF
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPTX
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
PDF
Repetitive project scheduling theory and methods 1st Edition Zhang
PPTX
Critical Path Method
PDF
CPM and PERT
PDF
PERT AND CPM PROJECT MANAGEMENT
PDF
Efficient Planning Scheduling and Delay Analysis of Residential Project
PPTX
PROJECT SCHEDULE
Ijciet 10 01_075
Literature Review in Project Scheduling Techniques
PM-5 chapter project management (1).pptx
PM-chapter 00005 project management.pptx
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
Scheduling coordination and control of projects
lecture 14.construction project management
Critical path method with detailed description
IRJET- Critical Chain Project Management in Construction Projects
PERT and CPM
Nce603 mod unit1
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
PROJECT-SCHEDULING-pptx.pptx
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
Repetitive project scheduling theory and methods 1st Edition Zhang
Critical Path Method
CPM and PERT
PERT AND CPM PROJECT MANAGEMENT
Efficient Planning Scheduling and Delay Analysis of Residential Project
PROJECT SCHEDULE
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...

Recently uploaded (20)

PDF
composite construction of structures.pdf
PPT
Mechanical Engineering MATERIALS Selection
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Construction Project Organization Group 2.pptx
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
web development for engineering and engineering
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
R24 SURVEYING LAB MANUAL for civil enggi
DOCX
573137875-Attendance-Management-System-original
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Geodesy 1.pptx...............................................
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
composite construction of structures.pdf
Mechanical Engineering MATERIALS Selection
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Construction Project Organization Group 2.pptx
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
web development for engineering and engineering
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
UNIT-1 - COAL BASED THERMAL POWER PLANTS
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
R24 SURVEYING LAB MANUAL for civil enggi
573137875-Attendance-Management-System-original
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Geodesy 1.pptx...............................................
UNIT 4 Total Quality Management .pptx
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Lecture Notes Electrical Wiring System Components
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx

IRJET- Application of Time Divisions Scheduling Techniques for Duration and Quantity based Project Control is a Vivacious Decision Process

  • 1. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6289 Application of Time Divisions Scheduling Techniques for Duration and Quantity based Project Control is a Vivacious Decision Process Balaprasad Vitthal Gajul1, Gaurav Desai2 1Postgraduate student, Department of Civil Engineering, School Engineering and Technology, Sandip University Nashik, Maharashtra, India 2Assistant Professor, Department of Civil Engineering, School Engineering and Technology, Sandip University Nashik, Maharashtra, India. -------------------------------------------------------------------------***------------------------------------------------------------------------ Abstract— the scheduling plays crucial part for planning, executing, controlling, monitoring and closing the construction projects within stipulated time and in budget. The construction projects are complex in nature because there are various activities which are interconnected to each other and have to be completed in stipulated time limit and given budget. The Gantt chart and CPM have some drawbacks make these tools insufficient for project tracking, monitoring and reviewing of projects on account of both these tools are based on only duration of project activities. But, it is observed that in actual construction projects activities are connected to each other not only related to duration but also with the quantity of work. Hence the project unable to perform as per planned schedule requirements. This study offers a modified new scheduling technique to overcome the limitations of Gantt and Critical path method using Unit Time & Work Divisions Technique tool that offers a daily tracking, monitoring and reviewing of project schedule. To overcome periodical review of schedule by adopting the duration as well as work quantity of each activity into separate divisions. This new scheduling technique is expected to help project managers to achieve a better level of control over projects with better conceptualization, optimization and determination reinforce to meet project success. Key words: Monitoring and reviewing, Interrelationship of activities, Critical Path Divisions scheduling Technique (CPD), Work quantity and Project control. 1. INTRODUCTION The successful completion of project in construction industry mainly depends on completion of project in scheduled time and in budget. The Project Tracking, Monitoring and Control based on Duration and quantity divisions scheduling Techniques is a vivacious decision process. The construction project consist number of activities which are interconnected to each other hence management tracking monitoring reviewing and controlling of such projects till completion of project entirely is very distraught and complexity job,. The project managers/ site Engineer are generally handle project with Gantt Charts and Critical Path Method (CPM). The project manager/ site Engineer use Gantt charts and critical path method to determine the inter relationship of activities. While schedule of the project mainly the project duration, activities float times, data about the degree flexibleness related to the schedule of project and the critical or non- criticalness of the activities are very important. Project managers/ site Engineer generally adopt two methods that are Gantt Chart Method and Critical Path Method (CPM). The short coming of these two methods that these methods are based on only duration of project tracking. These two methods neither tracked duration as well as quantity of work. There are some lacunas in Critical Path Method (CPM) and Gantt Chart Method this study gives the new method of scheduling technique considering Critical Path Division (CPD) techniques that gives a daily tracking monitoring and reviewing of project scheduling by showing the duration as well as quantity of each activity into different divisions. The technique is supportive to project manager/ site Engineer to control the project not only from start to end with excellent control but also give support to take decision each day duration as well as quantity wise to complete the project within stipulated time period successfully. 2. METHODOLOGY There are some lacunas in Critical Path Method (CPM) and Gantt Chart Method this study gives the new method of scheduling technique considering Critical Path Division (CPD) techniques that gives a daily tracking monitoring and reviewing of project scheduling by showing the duration as well as quantity of each activity into different divisions.
  • 2. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6290 Figure No: 1 Flow Chart of Methodology The following way traditional activity duration is divided in number of days as shown below Table 1. Show the activity in network analysis as per critical path division technique 1 E 2 4days A. Traditional representation of activities in network E1 E2 E3 E4 1st day 2nd day 3rd day 4th day 4 days representation B. Representation of activities by critical path division technique Result discussion and conclusion Validation of modified techniques Develop a new alternative scheduling model by modifying the above of commonly used techniques by handling the relationship between activities by divisonal the time in seperate time divisions work out quantities of each activity and determine the work quantity for each time division for individual activity Find out the areas in the above techniques which makes themless effcienet for project control and hence project success Identify the commonly used management techniques for planning, scheduling and project control CPM and Gantt Chart Study of various management techniques by literature survey by discussion with field professionals Problem Statement
  • 3. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6291 The work quantity of activities are divided in day work and duration also suppose the exaction is going to executed in 4 days then each day the work should be done 25% as per base plan schedule. Presentation can be shown as following. Table 2. Representation of Work by duration as well as Quantity of an activity Excavation activity split in 4 days i.e 100/4 = 25% E1 E2 E3 E4 1st day 2nd day 3rd day 4th day 25% 25% 25% 25% 4 days representation Representation of activities by time and work division technique This technique able to do day to day activity dividing rather than activity-by-activity which provided in critical path method (CPM). This technique helps to monitor base line to work done schedule on time division technique. (Daily monitoring the progress not only on duration basis but also work quantity basis). Table 3. Representation of Day by Day Update in Scheduling 3. OBJECTIVES OF RESEARCH The construction industry have number of activities and they are interconnected to each other hence to complete the project in stipulated time and budget. This study develop an effective method of scheduling model for construction E1 E2 E3 E4 E1 E2 E3 E4 25% 25% 25% 25% 10% 35% 35% 20% P1 P2 P3 P4 P1 P2 P3 E4 25% 25% 25% 25% 20% 20% 30% 30% A. As per planned schedule A. As per Build schedule
  • 4. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6292 projects. It beats the hindrances of management techniques, which are commonly used during project control, Tracking, review and monitoring. Detailed objectives:  The scheduling techniques used in construction industry commonly by professionals and its study.  The discussion with experts, and extensive review on advantages disadvantages and effectiveness of different scheduling techniques like Gantt chart and (CPM) critical path method. Literature review and survey on different scheduling and management technique. The questioner data survey.  The detail study procedures of implementation and improvement in CPM and Gantt chart. Develop an alternative and improved new scheduling technique model mechanism that is based on divisional activity durations and work quantity. 4. NEED OF THE STUDY The construction industry project manager/ site Engineer using Gantt chart and critical path method for scheduling construction projects even though there are some lacunas in these techniques. The traditional representation of critical path method and Gantt chart lacks the ability to clearly represent and record details as-built information like slow or fast progress of project and complete, representation of work interruptions caused by the various parties involved. Critical path method is based on two unrealistic assumptions: that the project deadline is not restricted and that resources are unlimited. Therefore, the most cost-effective corrective actions needed in order to recover delays and overruns in project is required in these techniques. Both these techniques are when acts as baseline for measuring progress, it is difficult to use it to initiate appropriate corrective actions for recovering delays and overruns. The following list shows the most critical views of CPM and Gantt Charts.  In critical path method activates considers only Finish to Start relationship while many construction activities consists Start to Start and Finish to Finish relationships. Gantt Charts shows the relationship of all activities all but not able to decide critical and non-critical activities. Both critical path method and Gantt chart are not provide the perfect critical days of individual activities,  Gantt chart and critical path method considers only time relationship of activities but the construction industry project activities are interrelated to each other related not only duration but also quantity of work.  Critical path method and Gantt chart techniques are in sufficient to daily decision making and revision of project plan and schedule.  These critical path method and Gantt chart could be difficult to update. After several updates have been done, it becomes hard to read. Schedules updates are usually out of date when they are finished. The construction industry project have many complex projects the scheduling technique CPM network may be complicated. That makes it very difficult to communicate and understand. When the construction project comes in execution stage the monitoring and tracking was important to track the project as per base line schedule of project. As per general practice the project tracking and monitoring activity done by critical path method and Gantt chart periodically as per planned start and finish time only. The construction industry in many countries in world done survey for delays. The study conducted in India by the Infrastructure and Project Monitoring Division of the Ministry of Statistics and Program Implementation in 2004 they reported that out of 646 central sector projects costing about $50 trillion, approximately 40% are behind schedule, with delays ranging from 1 to 252 months (Lyer and Jha, 2006). Which denotes that construction industry projects not perform as per initial planning and schedules.
  • 5. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6293 5. DATA COLLECTION QUESTIONER SURVEY Questioner survey denoted that there is requirement of day to day monitoring in simple excel format for consultants, project manage and site Engineer. Figure 2 shows questioner survey graphical presentation
  • 6. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6294 Data collection Name of project: Residential Building. Address: Sr.No.886/B, P.No.6 Rane nagar Mumbai Agra road, Nashik-422009 Name of owner: Shri. Dattatray Kondaji Thete Through Developer and GPA Holder Shree Gurudatta Construction Through Proprietor shri. Yadunath Baburao Vibhute Area of Construction: 805.25sq.M Type of Building: G+4RCC Structure Total Duration of Project (Planned): 180 days. Start Date: 12/03/2018. End Date (Planned): 03/05/2019. Name of contractor: Shri. Anil N Yeola and Stru. Engg. Anil N Yeola of Nashik. Total no. of Activities: 73 Figure 3 show the completed residential project 6. DATA ANALYSIS 1. Analysis of Data collected from Questionnaire Survey The questionnaire survey show that the most consultant/ site Engineer/ contractor generally use excel sheet for their daily work but it is insufficient to show daily tracking of project duration wise and quantity wise hence this study initiated. 2. Analysis of Data Collected from the case study Figure 4. Gantt chart for day to day monitoring time division method
  • 7. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6295 In above Gantt chart the activity split in the days duration hence it shows that the activity is not itself critical but some of days of activity are critical. - The red capsule indicate the critical days of that activity. - The blue capsule indicate the non-critical days of that activity. 7. Result and discussion: The traditional representation of Gantt chart represented by using MS-Project shows the critical activities of project which are shown by red colour bars for total activities which is Critical activities. Figure No 4 shows the same Gantt chart but based on the unit division scheduling mechanism which describes each segments ( activity dived in days) of every activity of entire project. As it is also represented by using MS-project it provides exact critical days of activities involved in project. Excavation Activity has only three days are critical shown by red colour where as traditional Gantt chart shows the whole activity is critical for the same schedule. This shows the effectiveness of Unit division Scheduling Technique over traditional Gantt chart technique for scheduling. 8. Conclusion In mainly construction industry the two scheduling methods adopted that are Critical path method and Gantt chart (Bar Chart), Critical Path Method (CPM) generally in commonly used for scheduling the construction projects by project Engineer/ project managers. This two Critical path method and Gantt Chart (Bar Chart) methods have some drawbacks to provide successful decision making reinforce for projects Critical path method (CPM ) shows Critical activities and critical path but not able to show the data of interrelationship of activities that are in project. . Gantt chart not able to show data of critical activities. The completion of project in schedule time and given budget the project the project manager/ site Engineer deal to actual monitoring of project and to overcome lacunas in Critical Path Method (CPM) and Gantt Chart Method this study gives the new method of scheduling technique considering Critical Path Division(CPD) techniques with its mathematical formulation that gives a daily tracking monitoring and reviewing of project scheduling by showing the duration as well as quantity of each activity into different divisions. In this method the production and time base relationship between the each activates. This two component based method gives vivacious decision process having following advantage.  At very Nano- level critical path division method.  Nice approach to understanding the project scheduling  In progress of work very less time required to re schedule.  We can avoid the very complex project relationship in activities scheduling.  Nice construction project monitoring tracking reviewing by using not only duration but also quantity (production) based scheduling for completion of project in time and budget.  It gives us very accurate analysis of schedule during the execution and after execution of project. REFERENCES 1. Shailla (2014), “Comparative Study of Management Operation System Techniques (MOST) and CPM in Construction Scheduling.” International Journal of Engineering Trends and Technology (IJETT), 18-8, pp371-379. 2. David Arditi, Onur B. Tokdemir2 and KangsukSuh (2002), “Challenges in Line-of-Balance Scheduling.” Journal of Construction Engineering and Management, ASCE, 128, pp545-556. 3. Ron Winter, F. BurakEvrenosoglu (2011), “MS Project for Construction Schedulers.” The AACE International 55th Annual Meeting, California, USA. 4. Fang-Ying Shen, Andrew S. Chang (2014), “Effectiveness of Coordination Metods in Construction Projects.” Journal of Management in Engineering, ASCE. 5. Gunnar Lucko (2009), “Productivity Scheduling Method: Linear Schedule Analysis with Singularity Functions.” Journal of Construction Engineering and Management, ASCE, 135, pp246-253. 6. YakubuOlawale and Ming Sun (2013), “PCIM: Project Control and Inhibiting-Factors Management Model.” Journal of Management in Engineering, ASCE, 29, pp60-70. 7. Lihui Zhang, Jianxun Qi (2012), “Controlling Path and Controlling Segment Analysis in Repetitive Scheduling Method.” Journal of Construction Engineering and Management, ASCE, 138, pp1341-1345.
  • 8. INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: 2395-0056 VOLUME: 06 ISSUE: 05 | MAY 2019 WWW.IRJET.NET P-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 6296 8. TarekHegazy, and Wail Menesi, (2008), “Delay Analysis under Multiple Baseline Updates.” Journal of Construction Engineering and Management, ASCE, 136, pp1078-1085 9. Galloway P. D. (2006). "Survey of the construction industry relative to the use of CPM scheduling for construction projects." Journal of Construction Engineering and Management, ASCE, 132(7), pp697–711 10. D. K. H. Chua, L. J. Shen and S. H. Bok (2003), “Constraint-Based Planning with Integrated Production Scheduler over Internet.” Journal of Construction Engineering and Management, ASCE, 129, pp293-301. 11. Rene´ A. Yamı´n and David J. Harmelink (2001), “Comparison of Linear Scheduling Model (LSM) and Critical Path Method (CPM).” Journal of Construction Engineering and Management, ASCE, 127, pp374-381. 12. Patricia D. Galloway. (2006). “Survey of the Construction Industry Relative to the Use of CPM Scheduling for Construction Projects.” Journal of Construction Engineering and Management, ASCE, 132, pp697-711. 13. Su-Ling Fan and H. P. Tserng (2006), “Object-Oriented Scheduling for Repetitive Projects with Soft Logics.” Journal of Construction Engineering and Management, ASCE, 132, pp35-48. 14. Ming Lu1 and Heng Li (2003), “Resource-Activity Critical-Path Method for Construction Planning.” Journal of Construction Engineering and Management, ASCE, 129, 412-420. 15. William Ibbs, Long D. Nguyen (2007), “Schedule Analysis under the effect of resource Allocation.” Journal of Construction Engineering and Management, ASCE, 133, 133-138. 16. PasitLorterapong, MongkolUssavadilokrit (2013), “ Construction Scheduling Using the Constraint Satisfaction Problem Method.” Journal of Construction Engineering and Management, ASCE, 139, pp414-422. 17. Daniel Castro-Lacoture, Gursel A Suer, Julian Gonzalez-joaqui and J. K. Yates (2009), “Construction Project Scheduling with Time, Cost and Material Restrictions using Fuzzy Mathematical Models and Critical Path Method.” Journal of Construction Engineering and Management, ASCE, 135, pp1096-1104 18. Kenneth O. Hartley (1993), “How to make Project Schedules Really Work for You.” Journal of Management in Engineering, ASCE, 9, pp167-173.