SlideShare a Scribd company logo
Jason Douglas
Earned Value Basics and Application
Jason Douglas– PM, Senior PM and Portfolio Lead
The Road Ahead
• Earn Value Defined
• Reasons why Earned Value is not used
• What causes Earned Value not to be Accurate
• Earned Value Pre-requisites
• Simple Scenario
• Formula Basics
• Question 1
• Question 1 Answers
• Other Earned Factors to Consider
• Summary and Next Steps
Earned ValueDefined
Earned value management (EVM) is used to assess and grade a PM and
their project based on the schedule and cost performance of a project.
A PM needs to demonstrate control and one key areas is EVM:
• Ahead of / on / behind schedule
• Under / on / over budget
• Earned value management (EVM) is based on the concept that
• i) work completed will deliver value and
• ii) the value delivered equals the budget put into the work.
Reasons Why Earned Value is NOT used
• Too hard and expensive too
• Not enough budget or time
• Programme Management has not allocated enough time for
development or standardisation
• Plans are not mature enough
• Internal or External charge out rates will be exposed to customer or
other resources
• No documented requirements
• Incomplete requirements
• Just because requirements are
baselined does no make them
complete
• SMART* approach needs to be
used
• WBS* not used or not accepted;
(Plan the Plan)
• WBS incomplete;
• Plan not integrated (WBS-Schedule-
Budget)
• Schedule and/or budget incorrect
• Change management not used or
ineffective;
• Cost collection system inadequate;
• Incorrect progress recorded
• When is a task 0,20,80,100% complete
• management influence and/or
control.
• Contingencies added in to the project
Earned Value Pre-Requisites
• The project must have an agreed
‘Baseline Budget’
• Implications Include
• Project Outlook (budget from
Account) aligned to
• Cost Model
• Schedule (Effort, Duration and
Deliverables).
• AS IS model to be agreed/baselined
• If there is no contingency then
project slippages or additional
meetings need Change Requests
(CR) for money and time.
• Decision is needed on CR triggers
• Raw Financial Reports need to be
timely and align with reported
progress
• Requirements, deliverables,
governance approach and processes
need to be agreed up front.
• Good will
Simple Scenario
• Build a Fence with 10 Panels, each panel takes a day.
• It is day 4, 4 panels should have been built
• Each panel has a value of £100
Formulas Basics
Planned Value (PV) At end of day 4, 4 panels
should be complete
4 panels x £100 =£400
The budgeted value of the
work completed so far at a
specific date
Earned Value (EV) By end of day 4 only 3
panels have been built
hence the EV is £300
The actual value of the
work completed so far at a
specific date
Actual Cost (AC) By end of day 4 actual cost
is £400
The total expenditure for
the work so far at a
specific date
Budget At Completion
(BAC)
10 Panels at £100 each =
£1000
The total budget for the
project
Formula Basics Continued
Schedule Variance (SV) At end of day 4,
SV= £300-£400
-£100
Minus is behind schedule
Plus is in front
Is the projects work ahead
or behind schedule
SV=EV-PV
Schedule Performance
Index (SPI)
By end of day 4
SPI= £300/£400
0.75
Minus now becomes below
one
Plus becomes higher than
one
Represents schedule
variance as a ratio
SPI=EV/PV
Formula Basics Continued
Cost Variance (CV) At end of day 4,
CV= £300-£400
-£100
Minus is behind budget
Plus is in front
Is the projects costs ahead
or behind budget
CV=EV-AC
Cost Performance Index
(CPI)
By end of day 4
CPI= £300/£400
0.75
Minus is achieved less than
is planned
Plus achieved more than is
planned
Represents schedule
variance as a ratio
CPI=EV/AC
SPI and CPI Interpretation
• CPI above 1 – for every £ spent, obtaining more value that is expected
• SPI - how close the actual work is to the schedule – above 1 ahead of
schedule
• Interesting when combining 2 ratios together
CPI 0.75 / SPI 0.90 Spending too much money and behind time. Investigate
CPI 0.90 / SPI 1.5 Spending too much money getting ahead of schedule
CPI 1.5 / SPI 0.90 Adding lots of value but slower than planned
CPI 1.5 / SPI 1.5 Adding lots of value / faster than planned. CR required
and replan.
Question 1
• Bid Budget of £15,000 which includes uplifts. £10,000 is the Labour Cost. The Project Lasts 5
weeks and the money should be spent evenly
• By end of week 2 The following deliverables are completed, Project Start Up, Set up in corporate
system for reporting, request for labour and requests for getting labour reports done. The project
has been created a project sharepoint, Cost Model, CR Templates, DAIR Log Created, Projects
Meetings Set Up, Requirements are Baselined, Capacity Sheet Submitted, Bid Charter Baselined,
Pricing sheet submitted, Network Diagram created. The Cost registered in labour systems is
£4500. However 3 weeks work is Completed.
• What is the BAC, EV, PV, AC
• What is SV, SPI
• What is the CV, CPI
• Interpret the data what does it mean
PTO to see answers
Answers
• What is the BAC, EV, PV, AC
• BAC = £10,000
• EV = £6,000 (3 Weeks effort)
• PV = £4,000 (2 weeks effort)
• AC =£4,500 what has been spent
• What is SV, SPI
• SV = EV-PV £6,000 - £4,000 SV = £2000
• SPI = EV/PV £6,000/£4000 SPI = 1.5
• What is the CV, CPI
• CV = EV-AC £6,000-£4,500 = £1,500
• CPI = EV/AC =1.33
• Interpret the data what does it mean
• Ahead of schedule and ahead of budget at end of week 2.
EV Considerations
• Physical Measurement — directly transform the physical measurement of the amount of
work completed into EV
• example: building 10 Panels each has a value of £100 expected to be completed in 10 days in
proportion, earned value of 3 panel built is £300
• Percentage Complete — directly transform the percentage of the amount of work
completed into EV
• example: building 10 panel each has a value of £100 expected to be completed in 10 days in
proportion, earned value of 30% complete is £300
• Weighted Milestone — a EV is assigned to the 100% completion of each milestone of the
work packages with prior agreement with stakeholders
• Fixed Formula — a specific percentage of the overall PV is assigned to the start of a work
package and the remaining assigned upon completion; these must be agreed upon in the
project management plan
• 0/100 rule: 0% EV at the activity begins; 100% EV upon completion
• 20/80 rule: 20% EV at the activity begins; 80% EV upon completion.
• 50/50 rule: 50% EV at the activity begins; 50% EV upon completion
Summary and Next Steps
• Basic 101 of what is earned value
• Why we use it
• Covered of simple example and had a practise question
• Next Lesson on Earned value
• Applying Earned Value to projects and programmes
• More complex formula such as budget at completion
Thank you
Any questions to Jason Douglas
Jasondouglas1105@outlook.com
Mobile 07496002461
16

More Related Content

PDF
Earned Value fundamentals
PDF
Back to basics - Earned Value Management for beginners webinar
PDF
The Benefits of using Earned Value Management
PPSX
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
PPS
Earned Value Management
PDF
EVM of Project Management...
PPT
Earned value analysis training
PPTX
Earned value management (EVM)
Earned Value fundamentals
Back to basics - Earned Value Management for beginners webinar
The Benefits of using Earned Value Management
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
Earned Value Management
EVM of Project Management...
Earned value analysis training
Earned value management (EVM)

What's hot (19)

PPT
Earned value
PDF
Earned value management
PDF
A simple example of Earned Value Management (EVM) in action
PPTX
Earned Value Analysis
PPTX
Earned Value Management
PPT
Earned Value Analysis
PPTX
Earned value management
PDF
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
PDF
Project Control Process
PPTX
Earned value analysis
PPT
Earned Value
PDF
Earned value management in action - A Webinar by Vivek Prakash, pmwares
PPTX
Earned value for pmp and pmi acp exam
PPSX
PMP Exam Preparation Course: 06 Project Cost Management
PPT
Earned value Project Management (evpm)
PPTX
Earned Value Analysis
PPTX
Earned value analysis (1)
Earned value
Earned value management
A simple example of Earned Value Management (EVM) in action
Earned Value Analysis
Earned Value Management
Earned Value Analysis
Earned value management
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
Project Control Process
Earned value analysis
Earned Value
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value for pmp and pmi acp exam
PMP Exam Preparation Course: 06 Project Cost Management
Earned value Project Management (evpm)
Earned Value Analysis
Earned value analysis (1)
Ad

Viewers also liked (10)

PDF
Art is not the Enemy_Writing Sample from Exhibition Catalogue
DOCX
CVofAndrewMichaelBlairworkhistory
PDF
MOHAMMED. ABED CV
PDF
Verity About us e-brochure
PPTX
Realty Connection - Fidelity - Broker Presentation
PDF
Curriculum Vitae of MD. ENAMUL HAQUE
PDF
Thesis Final Version
PPT
A Presentation On Summer Internship Project Done At
DOC
Project Report on e banking
PDF
Verity About us e-brochure
Art is not the Enemy_Writing Sample from Exhibition Catalogue
CVofAndrewMichaelBlairworkhistory
MOHAMMED. ABED CV
Verity About us e-brochure
Realty Connection - Fidelity - Broker Presentation
Curriculum Vitae of MD. ENAMUL HAQUE
Thesis Final Version
A Presentation On Summer Internship Project Done At
Project Report on e banking
Verity About us e-brochure
Ad

Similar to Jason douglas earned value 1 0 (20)

PDF
Project monitoring and controlling with earned value management
PPTX
project control using earned value analysis - Part 01
PPTX
Projects Control Using Earned Value Techniques - Part One
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPT
Project Management Earned Value
PPTX
Earned Value Management chapter 8 pm2.pptx
PPTX
Project monitoring & Earned Value Analysis
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PPTX
Earned Value Management - Project Controls - Schedule Only.pptx
PPT
EVA - Metrics.ppt
PPT
project monitoring_and_control in project mgt
PPTX
Project monitoring lecture 1
PDF
Earned Value Management
PPTX
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
PDF
Earned value analysis
PDF
Project managment 6 (a)
PPTX
Earned Value Management for project managers
PDF
Basic Concepts of Earned Value Management.pdf
Project monitoring and controlling with earned value management
project control using earned value analysis - Part 01
Projects Control Using Earned Value Techniques - Part One
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Earned Value AnalysisTracking Project ProgressWh.docx
Project Management Earned Value
Earned Value Management chapter 8 pm2.pptx
Project monitoring & Earned Value Analysis
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
Earned Value Management - Project Controls - Schedule Only.pptx
EVA - Metrics.ppt
project monitoring_and_control in project mgt
Project monitoring lecture 1
Earned Value Management
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
Earned value analysis
Project managment 6 (a)
Earned Value Management for project managers
Basic Concepts of Earned Value Management.pdf

Recently uploaded (20)

PDF
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PPTX
Astra-Investor- business Presentation (1).pptx
PDF
Blood Collected straight from the donor into a blood bag and mixed with an an...
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PDF
Introduction to Generative Engine Optimization (GEO)
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PPTX
CTG - Business Update 2Q2025 & 6M2025.pptx
PDF
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PPTX
operations management : demand supply ch
PPTX
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
Astra-Investor- business Presentation (1).pptx
Blood Collected straight from the donor into a blood bag and mixed with an an...
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Introduction to Generative Engine Optimization (GEO)
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
Module 2 - Modern Supervison Challenges - Student Resource.pdf
CTG - Business Update 2Q2025 & 6M2025.pptx
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
Slide gioi thieu VietinBank Quy 2 - 2025
operations management : demand supply ch
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
2025 Product Deck V1.0.pptxCATALOGTCLCIA

Jason douglas earned value 1 0

  • 1. Jason Douglas Earned Value Basics and Application Jason Douglas– PM, Senior PM and Portfolio Lead
  • 2. The Road Ahead • Earn Value Defined • Reasons why Earned Value is not used • What causes Earned Value not to be Accurate • Earned Value Pre-requisites • Simple Scenario • Formula Basics • Question 1 • Question 1 Answers • Other Earned Factors to Consider • Summary and Next Steps
  • 3. Earned ValueDefined Earned value management (EVM) is used to assess and grade a PM and their project based on the schedule and cost performance of a project. A PM needs to demonstrate control and one key areas is EVM: • Ahead of / on / behind schedule • Under / on / over budget • Earned value management (EVM) is based on the concept that • i) work completed will deliver value and • ii) the value delivered equals the budget put into the work.
  • 4. Reasons Why Earned Value is NOT used • Too hard and expensive too • Not enough budget or time • Programme Management has not allocated enough time for development or standardisation • Plans are not mature enough • Internal or External charge out rates will be exposed to customer or other resources
  • 5. • No documented requirements • Incomplete requirements • Just because requirements are baselined does no make them complete • SMART* approach needs to be used • WBS* not used or not accepted; (Plan the Plan) • WBS incomplete; • Plan not integrated (WBS-Schedule- Budget) • Schedule and/or budget incorrect • Change management not used or ineffective; • Cost collection system inadequate; • Incorrect progress recorded • When is a task 0,20,80,100% complete • management influence and/or control. • Contingencies added in to the project
  • 6. Earned Value Pre-Requisites • The project must have an agreed ‘Baseline Budget’ • Implications Include • Project Outlook (budget from Account) aligned to • Cost Model • Schedule (Effort, Duration and Deliverables). • AS IS model to be agreed/baselined • If there is no contingency then project slippages or additional meetings need Change Requests (CR) for money and time. • Decision is needed on CR triggers • Raw Financial Reports need to be timely and align with reported progress • Requirements, deliverables, governance approach and processes need to be agreed up front. • Good will
  • 7. Simple Scenario • Build a Fence with 10 Panels, each panel takes a day. • It is day 4, 4 panels should have been built • Each panel has a value of £100
  • 8. Formulas Basics Planned Value (PV) At end of day 4, 4 panels should be complete 4 panels x £100 =£400 The budgeted value of the work completed so far at a specific date Earned Value (EV) By end of day 4 only 3 panels have been built hence the EV is £300 The actual value of the work completed so far at a specific date Actual Cost (AC) By end of day 4 actual cost is £400 The total expenditure for the work so far at a specific date Budget At Completion (BAC) 10 Panels at £100 each = £1000 The total budget for the project
  • 9. Formula Basics Continued Schedule Variance (SV) At end of day 4, SV= £300-£400 -£100 Minus is behind schedule Plus is in front Is the projects work ahead or behind schedule SV=EV-PV Schedule Performance Index (SPI) By end of day 4 SPI= £300/£400 0.75 Minus now becomes below one Plus becomes higher than one Represents schedule variance as a ratio SPI=EV/PV
  • 10. Formula Basics Continued Cost Variance (CV) At end of day 4, CV= £300-£400 -£100 Minus is behind budget Plus is in front Is the projects costs ahead or behind budget CV=EV-AC Cost Performance Index (CPI) By end of day 4 CPI= £300/£400 0.75 Minus is achieved less than is planned Plus achieved more than is planned Represents schedule variance as a ratio CPI=EV/AC
  • 11. SPI and CPI Interpretation • CPI above 1 – for every £ spent, obtaining more value that is expected • SPI - how close the actual work is to the schedule – above 1 ahead of schedule • Interesting when combining 2 ratios together CPI 0.75 / SPI 0.90 Spending too much money and behind time. Investigate CPI 0.90 / SPI 1.5 Spending too much money getting ahead of schedule CPI 1.5 / SPI 0.90 Adding lots of value but slower than planned CPI 1.5 / SPI 1.5 Adding lots of value / faster than planned. CR required and replan.
  • 12. Question 1 • Bid Budget of £15,000 which includes uplifts. £10,000 is the Labour Cost. The Project Lasts 5 weeks and the money should be spent evenly • By end of week 2 The following deliverables are completed, Project Start Up, Set up in corporate system for reporting, request for labour and requests for getting labour reports done. The project has been created a project sharepoint, Cost Model, CR Templates, DAIR Log Created, Projects Meetings Set Up, Requirements are Baselined, Capacity Sheet Submitted, Bid Charter Baselined, Pricing sheet submitted, Network Diagram created. The Cost registered in labour systems is £4500. However 3 weeks work is Completed. • What is the BAC, EV, PV, AC • What is SV, SPI • What is the CV, CPI • Interpret the data what does it mean PTO to see answers
  • 13. Answers • What is the BAC, EV, PV, AC • BAC = £10,000 • EV = £6,000 (3 Weeks effort) • PV = £4,000 (2 weeks effort) • AC =£4,500 what has been spent • What is SV, SPI • SV = EV-PV £6,000 - £4,000 SV = £2000 • SPI = EV/PV £6,000/£4000 SPI = 1.5 • What is the CV, CPI • CV = EV-AC £6,000-£4,500 = £1,500 • CPI = EV/AC =1.33 • Interpret the data what does it mean • Ahead of schedule and ahead of budget at end of week 2.
  • 14. EV Considerations • Physical Measurement — directly transform the physical measurement of the amount of work completed into EV • example: building 10 Panels each has a value of £100 expected to be completed in 10 days in proportion, earned value of 3 panel built is £300 • Percentage Complete — directly transform the percentage of the amount of work completed into EV • example: building 10 panel each has a value of £100 expected to be completed in 10 days in proportion, earned value of 30% complete is £300 • Weighted Milestone — a EV is assigned to the 100% completion of each milestone of the work packages with prior agreement with stakeholders • Fixed Formula — a specific percentage of the overall PV is assigned to the start of a work package and the remaining assigned upon completion; these must be agreed upon in the project management plan • 0/100 rule: 0% EV at the activity begins; 100% EV upon completion • 20/80 rule: 20% EV at the activity begins; 80% EV upon completion. • 50/50 rule: 50% EV at the activity begins; 50% EV upon completion
  • 15. Summary and Next Steps • Basic 101 of what is earned value • Why we use it • Covered of simple example and had a practise question • Next Lesson on Earned value • Applying Earned Value to projects and programmes • More complex formula such as budget at completion
  • 16. Thank you Any questions to Jason Douglas Jasondouglas1105@outlook.com Mobile 07496002461 16

Editor's Notes

  • #6: Specific Measurable Attainable Realistic Timely – SMART (Framework for writing requirements) Workbreak down structure. – once the project has asked the questions, what do you want (requirements), and the project team has responded with what we need to do (Scope), the How WBS is how we do it, break down the scope into segments called decomposition.
  • #7: AS IS – is the current mode of operation or model. In Contrast there there to the To Be – end point. CR – Change Requests, these are used to change requirements, scope, time or quality from an agreed point.
  • #10: Planned Value (PV) The budgeted value of the work completed so far at a specific date Earned Value (EV) The actual value of the work completed so far at a specific date  Actual Cost (AC) The total expenditure for the work so far at a specific date
  • #13: BAC – budget at completion Earned Value Planned Value Actual Value Schedule Variance Scheduled Variance Index Cost Variance Cost Performance Index