SlideShare a Scribd company logo
Earned Value Management in Cost
Management
Mgt & Constr Plg
Col Kunal Krishna
Introduction to Earned
Value Method (EVM)
• Integrated Performance Measurement: EVM combines schedule
and cost metrics for comprehensive project performance analysis.
• Risk Mitigation Strategy: Utilizing EVM allows early identification of
potential project cost overruns and delays.
• Industry-Specific Applications: In Indian construction, EVM
enhances accountability amidst diverse regulatory challenges and
resource constraints.
Earned Value
Management (EVM)
Overview
• Technique for measuring project performance and
progress objectively.
• Integrates project scope, schedule, and cost parameters
to provide accurate forecasts and insights into project
performance issues.
• The significance of EVM lies in its ability to help project
managers predict future performance and identify
potential risks early.
The Three Core Metrics of EVM
Planned Value (PV)
Planned Value (PV) represents the budgeted cost of work scheduled to be completed
by a certain date. It is a measure of the work that should have been accomplished at
a point in time.
Earned Value (EV)
Earned Value (EV) is the budgeted amount for the work actually completed at a
specific point in time. It indicates the earned progress of the project.
Actual Cost (AC)
Actual Cost (AC) is the total cost incurred for the actual work completed by a specific
point in time. It provides a real expenditure figure for comparison with PV and EV.
EVM Terminology
Budget at Completion
(BAC)
Estimate at
Completion (EAC)
Estimate to Complete
(ETC)
- Budget at Completion (BAC) is
the total budget allocated for
the project.
- Crucial for calculating planned
value and forecasting
remaining work.
- Estimate at Completion (EAC)
provides a forecast of the
project's final cost, calculated
by EAC = AC + ETC.
- Helps in predicting the end
cost under current
performance trends.
- Estimate to Complete (ETC) is
the forecasted cost needed to
complete the remaining
project work.
- Derived using ETC = EAC - AC,
contributing to accurate
forecasting and financial
planning.
Steps to
Implement EVM
Performance Monitoring: Continuous
monitoring tracks project health, enabling
timely interventions to mitigate risks.
Baseline Plan Development: Establishing a
baseline plan is crucial for measuring
project performance against expectations.
Scope Definition: Clearly defining project
scope ensures focused deliverables and
prevents scope creep.
Planned Value
• Also known as Budgeted Cost of Work Scheduled (BCWS)
• BAC (Budget at Completion): The total budget allocated for the
project.
• Planned Percentage of Completion: The percentage of work that
should be completed by the given date according to the project
schedule.
Earned Value
• Also known as also known as Budgeted Cost of Work Performed
(BCWP)
• BAC (Budget at Completion): The total budget allocated for the
project.
• Planned Percentage of Completion: The percentage of work that
should be completed by the given date according to the project
schedule.
Key Formulas in EVM
Cost Variance (CV) and Schedule Variance (SV)
• Cost Variance (CV) is calculated as CV = EV - AC, and it measures cost
performance by comparing earned value with actual cost.
• Schedule Variance (SV) is SV = EV - PV, and it indicates schedule performance by
comparing earned value with planned value.
• Cost Performance Index (CPI) is CPI = EV / AC, and it measures cost efficiency.
• Schedule Performance Index (SPI) is SPI = EV / PV, and it measures schedule efficiency.
These indices help assess project health effectively.
Cost Performance Index (CPI) and Schedule Performance
Index (SPI)
What is CPI?
• Definition
• Cost Performance Index (CPI) measures the cost efficiency of a
project.
• It compares the value of work completed to the actual cost
incurred.
• Formula: CPI = EV / AC
• EV (Earned Value): Value of work actually completed.
• AC (Actual Cost): Actual cost incurred for the completed work.
Interpreting CPI
• CPI > 1:
• Project is under budget.
• More than one dollar’s worth of work for every dollar spent.
• CPI = 1:
• Project is on budget.
• Exactly one dollar’s worth of work for every dollar spent.
• CPI < 1:
• Project is over budget.
• Less than one dollar’s worth of work for every dollar spent.
Example Calculation
• Example:
• EV (Earned Value): $50,000
• AC (Actual Cost): $60,000
• CPI Calculation:
• CPI = 50,000 / 60,000 = 0.83
• Interpretation:
• CPI = 0.83
• Project is over budget.
Importance of CPI
• Cost Efficiency Assessment
• Evaluates how well the project is using its budget.
• Forecasting
• Predicts total project cost at completion.
• Decision Making
• Identifies need for corrective actions if CPI is low.
• Confirms good cost performance if CPI is high.
Using CPI
for Project
Control
Stakeholder
Comn
Provide clear, quantifiable measures of cost
performance.
Performance
Reviews
Regularly monitor CPI to track project
performance.
Corrective
Actions
Implement changes to improve cost
efficiency.
What is SPI?
Definition
• Schedule Performance Index (SPI) measures the schedule efficiency of a project.
• It compares the value of work actually completed to the planned value of that
work.
Formula: SPI = EV / PV
• EV (Earned Value): The value of work actually completed.
• PV (Planned Value): The value of work planned to be completed by a specific
point in time.
Interpreting SPI
• Project is ahead of schedule.
• More work has been completed than planned.
SPI > 1:
• Project is on schedule.
• The amount of work completed matches the planned schedule.
SPI = 1:
• Project is behind schedule.
• Less work has been completed than planned.
SPI < 1:
Sample Calculation
• EV (Earned Value): $50,000
• PV (Planned Value): $60,000
Example:
• SPI = 50,000 / 60,000 = 0.83
SPI Calculation:
• SPI = 0.83
• Project is behind schedule.
Interpretation:
Importance of SPI
• SPI helps in evaluating how efficiently the project is
adhering to its planned schedule.
Schedule
Efficiency
Assessment:
• SPI can be used to predict future schedule performance
and potential completion dates.
Forecasting:
• A low SPI indicates that corrective actions might be
needed to get the project back on track.
• Conversely, a high SPI shows good schedule performance.
Decision Making:
Using SPI for Project Control
• Corrective Actions
• If the SPI indicates poor schedule performance, project managers can
investigate the root causes and implement corrective actions to improve
efficiency.
• Performance Reviews
• Regularly calculating SPI helps in monitoring project performance and
making timely decisions to ensure schedule adherence.
• Stakeholder Communication
• SPI provides a clear and quantifiable measure of schedule performance,
which is useful for reporting to stakeholders.
Benefits of EVM
• Improved project visibility and control
• Early warning of performance issues
• Better decision making
• Enhanced communication among stakeholders.
• Provides a single integrated view of cost and
schedule performance, simplifying complex project
tracking.
Challenges in Implementing EVM
Initial Setup and
Training
Data Accuracy and
Consistency
Resistance to
Change
Setting up EVM requires
a clear definition of
project scope and WBS,
which can be time-
consuming. Training the
team to understand EVM
concepts and tools is also
critical.
Accurate and consistent
data entry is essential for
reliable EVM outputs.
Inconsistent data can
lead to incorrect
performance evaluations
and misguided decision-
making.
Implementing EVM
might face resistance
from team members
used to traditional
management methods.
Communicating the
benefits and integrating
EVM gradually can help
mitigate resistance.
Metric Formula Interpretation
Planned Value (PV) Σ (Planned % Complete) * BAC Shows expected progress
Earned Value (EV) Σ (Actual % Complete) * BAC Shows actual progress
Actual Cost (AC) Σ Actual Costs to date Shows real expenditure
Cost Variance (CV) EV - AC Positive indicates under budget
Schedule Variance (SV) EV - PV Positive indicates ahead of
schedule
Cost Performance Index (CPI) EV / AC >1 indicates cost efficiency
Schedule Performance Index (SPI) EV / PV >1 indicates schedule efficiency
EVM Metrics in Tabular Form
Jai Hind

More Related Content

PPTX
Earned value management (EVM)
PDF
PMP Key Exam Concepts - Formulas
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PDF
Back to basics - Earned Value Management for beginners webinar
PPTX
Track Project Performance - Earned Value Management
PDF
Project monitoring and controlling with earned value management
Earned value management (EVM)
PMP Key Exam Concepts - Formulas
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Back to basics - Earned Value Management for beginners webinar
Track Project Performance - Earned Value Management
Project monitoring and controlling with earned value management

Similar to Earned Value Management for project managers (20)

PPTX
Project monitoring & Earned Value Analysis
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPTX
PMP COST FORMULAE
PDF
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PPTX
Earned Value Analysis
PPTX
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
PDF
Earned value management
PDF
Earned value analysis
PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PPTX
PMP Training - 07 project cost management
PPTX
Earned value analysis
PPTX
Project Cost Management
PDF
Earned Value Management
PDF
Earned Value Management using Odoo
PPTX
Project monitoring lecture 1
PDF
Topic 10 - Project Performance Management.pdf
PPTX
Earned value management for Beginners
PPTX
Project cost & control
PPTX
projectcostcontrol-130625012804-phpapp02 (1)
Project monitoring & Earned Value Analysis
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PMP COST FORMULAE
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Earned Value Analysis
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
Earned value management
Earned value analysis
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PMP Training - 07 project cost management
Earned value analysis
Project Cost Management
Earned Value Management
Earned Value Management using Odoo
Project monitoring lecture 1
Topic 10 - Project Performance Management.pdf
Earned value management for Beginners
Project cost & control
projectcostcontrol-130625012804-phpapp02 (1)
Ad

Recently uploaded (20)

PDF
TED Talk on how to make TED Talk slides.pdf
PPTX
Human Resources management _HR structure
PDF
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
PPTX
Chapter-3.pptx project life cycle presentation
PDF
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
PPTX
power of team work; how to develop team work
PPTX
Chapter Three for international political
PPTX
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PPTX
BASIC H2S TRAINING for oil and gas industries
PPTX
Self-Awareness and Values Development presentation
PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PPT
Project Management - Scope Management.ppt
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
FSC Building Trust in LGs august 8 2025.pptx
PDF
The Cyber SwarmShield by Stéphane Nappo
PPTX
Organisational behaviour_ managerial applications of perception
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PPTX
MY GOLDEN RULES la regla de oro jhonatan requena
TED Talk on how to make TED Talk slides.pdf
Human Resources management _HR structure
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
Chapter-3.pptx project life cycle presentation
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
power of team work; how to develop team work
Chapter Three for international political
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
BASIC H2S TRAINING for oil and gas industries
Self-Awareness and Values Development presentation
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
Project Management - Scope Management.ppt
Human Resource Management | Introduction,Meaning and Definition
FSC Building Trust in LGs august 8 2025.pptx
The Cyber SwarmShield by Stéphane Nappo
Organisational behaviour_ managerial applications of perception
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
MY GOLDEN RULES la regla de oro jhonatan requena
Ad

Earned Value Management for project managers

  • 1. Earned Value Management in Cost Management Mgt & Constr Plg Col Kunal Krishna
  • 2. Introduction to Earned Value Method (EVM) • Integrated Performance Measurement: EVM combines schedule and cost metrics for comprehensive project performance analysis. • Risk Mitigation Strategy: Utilizing EVM allows early identification of potential project cost overruns and delays. • Industry-Specific Applications: In Indian construction, EVM enhances accountability amidst diverse regulatory challenges and resource constraints.
  • 3. Earned Value Management (EVM) Overview • Technique for measuring project performance and progress objectively. • Integrates project scope, schedule, and cost parameters to provide accurate forecasts and insights into project performance issues. • The significance of EVM lies in its ability to help project managers predict future performance and identify potential risks early.
  • 4. The Three Core Metrics of EVM Planned Value (PV) Planned Value (PV) represents the budgeted cost of work scheduled to be completed by a certain date. It is a measure of the work that should have been accomplished at a point in time. Earned Value (EV) Earned Value (EV) is the budgeted amount for the work actually completed at a specific point in time. It indicates the earned progress of the project. Actual Cost (AC) Actual Cost (AC) is the total cost incurred for the actual work completed by a specific point in time. It provides a real expenditure figure for comparison with PV and EV.
  • 5. EVM Terminology Budget at Completion (BAC) Estimate at Completion (EAC) Estimate to Complete (ETC) - Budget at Completion (BAC) is the total budget allocated for the project. - Crucial for calculating planned value and forecasting remaining work. - Estimate at Completion (EAC) provides a forecast of the project's final cost, calculated by EAC = AC + ETC. - Helps in predicting the end cost under current performance trends. - Estimate to Complete (ETC) is the forecasted cost needed to complete the remaining project work. - Derived using ETC = EAC - AC, contributing to accurate forecasting and financial planning.
  • 6. Steps to Implement EVM Performance Monitoring: Continuous monitoring tracks project health, enabling timely interventions to mitigate risks. Baseline Plan Development: Establishing a baseline plan is crucial for measuring project performance against expectations. Scope Definition: Clearly defining project scope ensures focused deliverables and prevents scope creep.
  • 7. Planned Value • Also known as Budgeted Cost of Work Scheduled (BCWS) • BAC (Budget at Completion): The total budget allocated for the project. • Planned Percentage of Completion: The percentage of work that should be completed by the given date according to the project schedule.
  • 8. Earned Value • Also known as also known as Budgeted Cost of Work Performed (BCWP) • BAC (Budget at Completion): The total budget allocated for the project. • Planned Percentage of Completion: The percentage of work that should be completed by the given date according to the project schedule.
  • 9. Key Formulas in EVM Cost Variance (CV) and Schedule Variance (SV) • Cost Variance (CV) is calculated as CV = EV - AC, and it measures cost performance by comparing earned value with actual cost. • Schedule Variance (SV) is SV = EV - PV, and it indicates schedule performance by comparing earned value with planned value. • Cost Performance Index (CPI) is CPI = EV / AC, and it measures cost efficiency. • Schedule Performance Index (SPI) is SPI = EV / PV, and it measures schedule efficiency. These indices help assess project health effectively. Cost Performance Index (CPI) and Schedule Performance Index (SPI)
  • 10. What is CPI? • Definition • Cost Performance Index (CPI) measures the cost efficiency of a project. • It compares the value of work completed to the actual cost incurred. • Formula: CPI = EV / AC • EV (Earned Value): Value of work actually completed. • AC (Actual Cost): Actual cost incurred for the completed work.
  • 11. Interpreting CPI • CPI > 1: • Project is under budget. • More than one dollar’s worth of work for every dollar spent. • CPI = 1: • Project is on budget. • Exactly one dollar’s worth of work for every dollar spent. • CPI < 1: • Project is over budget. • Less than one dollar’s worth of work for every dollar spent.
  • 12. Example Calculation • Example: • EV (Earned Value): $50,000 • AC (Actual Cost): $60,000 • CPI Calculation: • CPI = 50,000 / 60,000 = 0.83 • Interpretation: • CPI = 0.83 • Project is over budget.
  • 13. Importance of CPI • Cost Efficiency Assessment • Evaluates how well the project is using its budget. • Forecasting • Predicts total project cost at completion. • Decision Making • Identifies need for corrective actions if CPI is low. • Confirms good cost performance if CPI is high.
  • 14. Using CPI for Project Control Stakeholder Comn Provide clear, quantifiable measures of cost performance. Performance Reviews Regularly monitor CPI to track project performance. Corrective Actions Implement changes to improve cost efficiency.
  • 15. What is SPI? Definition • Schedule Performance Index (SPI) measures the schedule efficiency of a project. • It compares the value of work actually completed to the planned value of that work. Formula: SPI = EV / PV • EV (Earned Value): The value of work actually completed. • PV (Planned Value): The value of work planned to be completed by a specific point in time.
  • 16. Interpreting SPI • Project is ahead of schedule. • More work has been completed than planned. SPI > 1: • Project is on schedule. • The amount of work completed matches the planned schedule. SPI = 1: • Project is behind schedule. • Less work has been completed than planned. SPI < 1:
  • 17. Sample Calculation • EV (Earned Value): $50,000 • PV (Planned Value): $60,000 Example: • SPI = 50,000 / 60,000 = 0.83 SPI Calculation: • SPI = 0.83 • Project is behind schedule. Interpretation:
  • 18. Importance of SPI • SPI helps in evaluating how efficiently the project is adhering to its planned schedule. Schedule Efficiency Assessment: • SPI can be used to predict future schedule performance and potential completion dates. Forecasting: • A low SPI indicates that corrective actions might be needed to get the project back on track. • Conversely, a high SPI shows good schedule performance. Decision Making:
  • 19. Using SPI for Project Control • Corrective Actions • If the SPI indicates poor schedule performance, project managers can investigate the root causes and implement corrective actions to improve efficiency. • Performance Reviews • Regularly calculating SPI helps in monitoring project performance and making timely decisions to ensure schedule adherence. • Stakeholder Communication • SPI provides a clear and quantifiable measure of schedule performance, which is useful for reporting to stakeholders.
  • 20. Benefits of EVM • Improved project visibility and control • Early warning of performance issues • Better decision making • Enhanced communication among stakeholders. • Provides a single integrated view of cost and schedule performance, simplifying complex project tracking.
  • 21. Challenges in Implementing EVM Initial Setup and Training Data Accuracy and Consistency Resistance to Change Setting up EVM requires a clear definition of project scope and WBS, which can be time- consuming. Training the team to understand EVM concepts and tools is also critical. Accurate and consistent data entry is essential for reliable EVM outputs. Inconsistent data can lead to incorrect performance evaluations and misguided decision- making. Implementing EVM might face resistance from team members used to traditional management methods. Communicating the benefits and integrating EVM gradually can help mitigate resistance.
  • 22. Metric Formula Interpretation Planned Value (PV) Σ (Planned % Complete) * BAC Shows expected progress Earned Value (EV) Σ (Actual % Complete) * BAC Shows actual progress Actual Cost (AC) Σ Actual Costs to date Shows real expenditure Cost Variance (CV) EV - AC Positive indicates under budget Schedule Variance (SV) EV - PV Positive indicates ahead of schedule Cost Performance Index (CPI) EV / AC >1 indicates cost efficiency Schedule Performance Index (SPI) EV / PV >1 indicates schedule efficiency EVM Metrics in Tabular Form