SlideShare a Scribd company logo
S
C
H
E
D
U
L
E
B
U
D
G
E
T
Earned Value Management
Forecasting
EARNED VALUE
ANALYSIS
in Project Management
Monitoring and measuring the project's cost, schedule, and work performed against the project
management plan at any given point in time, forecasting the project's completion date and final
cost, and analyzing variances in the schedule and budget as the project proceeds.
KEY PARAMETERS
PERFORMANCE MEASUREMENT METRICS
Performance Variances
Performance Indexes
PERFORMANCE FORECASTING METRICS
BUDGET AT COMPLETION
EARNED VALUE
COST
VARIANCE
COST
PERFORMANCE
INDEX
ESTIMATE
COMPLETION
ESTIMATE
COMPLETE
VARIANCE AT
COMPLETION
TO-COMPLETE
PERFORMANCE
INDEX
SCHEDULE
PERFORMANCE
INDEX
SCHEDULE
VARIANCE
BAC
No formula
Total budget for the project
ACTUAL COST PLANNED VALUE
AC
No formula
Actual cost of completing the
work component by a given point
in time.
CV
CV = EV – AC
Variance measuring actual
performance to date (or during
the period) against what's been
spent.
SV
SV = EV – PV
Variance measuring how much
behind or ahead of schedule at
given point in time.
CPI
CPI = EV / AC
Measure of whether project is
within budget or not at given
point in time.
EAC
EAC = BAC / CPI
Projection of expected total cost
of work component, schedule
activity, or project at completion,
based on available data at given
point in time.
ETC
ETC = EAC – AC
Projection of expected costs of
remaining work, based on
available data at given point in
time.
VAC
VAC = BAC – EAC
Projection of expected
variance between budget at
completion and estimate at
completion, based on
available data at given point
in time.
TCPI
2 formula:
• TCPI = (BAC – EV)/(BAC – AC); based on BAC (original BAC only
money available)
• TCPI = (BAC – EV)/(EAC – AC); based on EAC (new revised EAC
approved)
Projection of anticipated cost efficiency required to complete work with money
available.
Results: TCPI greater than 1.0 more difficult to achieve, TCPI less than 1.0 easier to
achieve.
SPI
SPI = EV / PV
Measure of whether schedule is
ahead of or behind what planned
for given point in time.
PV
PV = BAC x Planned
% complete
Approved budget assigned to
schedule activity or WBS
component to be completed by a
given point in time.
• Formula start with EV
• Results: below 1.0 = behind shedule/over
budget; exactly 1.0 = on schedule/budget;
above 1.0 = ahead of schedule/under budget
• Division
• Subtraction
EV
EV = BAC x Actual % complete
Value of work completed by a given point in time
compared to authorized budgeted amount assigned
to work component.
Source: A Guide to the Project
Management Body of Knowledge
(PMBOK® Guide)—Fifth Edition
Creative Commons Attribution 4.0
International Licence
TIPSOGRAPHIC.COM
Are you ready to learn
more or get more
details? Get your free PM
infographics today at
Tips That Make Life Easier
TIPSOGRAPHIC.COM
TIPSÖGRAPHIC

More Related Content

PDF
PMP Exam Prep_sample slides
PDF
07 project cost management
PDF
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PPT
PMP Certification Presentation
PDF
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PDF
Chap 5.5 validate scope
PDF
Project Management Framework - PMBOK 5
PPTX
pmi project management principles.pptx
PMP Exam Prep_sample slides
07 project cost management
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMP Certification Presentation
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
Chap 5.5 validate scope
Project Management Framework - PMBOK 5
pmi project management principles.pptx

What's hot (20)

PDF
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
PDF
Project Management Professional (PMP)
PDF
Pmp quality chapter 8
PDF
The new PMP, what it is and how to get prepared for it
PPTX
Project Scope Management - PMBOK6
PPTX
Pmp chapter(5) Scope Management
PDF
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
PPT
PMP Certification Chapter one Summary of PMBOK
PDF
Integrating project life cycle with process groups
PDF
Pmp time chapter 6
PDF
Chap 4.3 Direct and Manage Project work
PDF
PMP Exam Preparation - 200 Questions
PDF
Conduct procurements
PPTX
Pmo Concept
PDF
How to Choose a Project Delivery Method
PPT
Project Management PPT
PDF
PMP chap 1 - PMP Introduction (PMBOK 6)
PPTX
Instructor Slides - PMP/CAPM PMBOK 6th Edition
PDF
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PDF
PMP_Project Procurement Management
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Professional (PMP)
Pmp quality chapter 8
The new PMP, what it is and how to get prepared for it
Project Scope Management - PMBOK6
Pmp chapter(5) Scope Management
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
PMP Certification Chapter one Summary of PMBOK
Integrating project life cycle with process groups
Pmp time chapter 6
Chap 4.3 Direct and Manage Project work
PMP Exam Preparation - 200 Questions
Conduct procurements
Pmo Concept
How to Choose a Project Delivery Method
Project Management PPT
PMP chap 1 - PMP Introduction (PMBOK 6)
Instructor Slides - PMP/CAPM PMBOK 6th Edition
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP_Project Procurement Management
Ad

Viewers also liked (14)

PDF
Project Management Process Groups 101
PDF
How to Build Your Risk Management Plan – an Effective Checklist
PDF
Earned Value Management Essentials
PDF
Django10 cheat-sheet-grayscale
PDF
Executive Overview of Managing Agile Programs with Earned Value
PDF
EVMS Made Simple
PPTX
Jerald kerby
PDF
Earned value management in action - A Webinar by Vivek Prakash, pmwares
PPTX
Earned Value Management
PDF
Earned Value fundamentals
PPTX
Earned value management
Project Management Process Groups 101
How to Build Your Risk Management Plan – an Effective Checklist
Earned Value Management Essentials
Django10 cheat-sheet-grayscale
Executive Overview of Managing Agile Programs with Earned Value
EVMS Made Simple
Jerald kerby
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned Value Management
Earned Value fundamentals
Earned value management
Ad

Similar to Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://bit.ly/2m7tH2i (20)

PPTX
Project monitoring & Earned Value Analysis
PPTX
Earned Value Analysis in construction projects
PDF
Project monitoring and controlling with earned value management
PDF
PM - EVM - Dr Najam Abbas - OHT 1.pdf
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
PMP COST FORMULAE
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPT
EVA - Metrics.ppt
PPTX
Project cost control
PDF
Earned Value Management
PPTX
Project Cost Management - PMP preparation course
PDF
Program Management 2.0: Work Breakdown Structure
PPTX
Project monitoring lecture 1
PPTX
Project Cost Management
PPTX
Nasa+evm+reference+card nov+2015
PDF
Performing against the wall - SPI after completion
PDF
Earned value analysis - presentation
PDF
Evm.calculations.Summary sheet
PPTX
Track Project Performance - Earned Value Management
PPTX
Earned value analysis (1)
Project monitoring & Earned Value Analysis
Earned Value Analysis in construction projects
Project monitoring and controlling with earned value management
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Earned Value AnalysisTracking Project ProgressWh.docx
PMP COST FORMULAE
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
EVA - Metrics.ppt
Project cost control
Earned Value Management
Project Cost Management - PMP preparation course
Program Management 2.0: Work Breakdown Structure
Project monitoring lecture 1
Project Cost Management
Nasa+evm+reference+card nov+2015
Performing against the wall - SPI after completion
Earned value analysis - presentation
Evm.calculations.Summary sheet
Track Project Performance - Earned Value Management
Earned value analysis (1)

More from Tipsographic . com (18)

PPTX
The Funny #3
PPTX
The Funny #4
PPTX
The Funny #8
PPTX
The Funny #9
PPTX
The Funny #10
PPTX
The Funny #11
PPTX
The Funny #12
PPTX
The Funny #13
PPTX
The Funny #14
PPTX
The Funny #17
PPTX
The Funny #19
PPTX
The Funny #20
PDF
Business Professional Attire Checklist, Printable
PDF
PMP Certification: Plan Stakeholder Engagement (PMP 2018) → http://bit.ly/2mp...
PDF
PMP Certification: Project Procurement Management Whats, Whens, and Whys (PMP...
PDF
PMP 2018: Project Schedule Management
PDF
PDF
How to be a Google Power User
The Funny #3
The Funny #4
The Funny #8
The Funny #9
The Funny #10
The Funny #11
The Funny #12
The Funny #13
The Funny #14
The Funny #17
The Funny #19
The Funny #20
Business Professional Attire Checklist, Printable
PMP Certification: Plan Stakeholder Engagement (PMP 2018) → http://bit.ly/2mp...
PMP Certification: Project Procurement Management Whats, Whens, and Whys (PMP...
PMP 2018: Project Schedule Management
How to be a Google Power User

Recently uploaded (20)

PDF
WRN_Investor_Presentation_August 2025.pdf
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
Types of control:Qualitative vs Quantitative
DOCX
Business Management - unit 1 and 2
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
Training And Development of Employee .pdf
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PDF
How to Get Funding for Your Trucking Business
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PPT
Data mining for business intelligence ch04 sharda
WRN_Investor_Presentation_August 2025.pdf
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Laughter Yoga Basic Learning Workshop Manual
Lecture (1)-Introduction.pptx business communication
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Types of control:Qualitative vs Quantitative
Business Management - unit 1 and 2
Principles of Marketing, Industrial, Consumers,
Roadmap Map-digital Banking feature MB,IB,AB
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Training And Development of Employee .pdf
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
DOC-20250806-WA0002._20250806_112011_0000.pdf
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
How to Get Funding for Your Trucking Business
unit 1 COST ACCOUNTING AND COST SHEET
ICG2025_ICG 6th steering committee 30-8-24.pptx
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Data mining for business intelligence ch04 sharda

Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://bit.ly/2m7tH2i

  • 1. S C H E D U L E B U D G E T Earned Value Management Forecasting EARNED VALUE ANALYSIS in Project Management Monitoring and measuring the project's cost, schedule, and work performed against the project management plan at any given point in time, forecasting the project's completion date and final cost, and analyzing variances in the schedule and budget as the project proceeds. KEY PARAMETERS PERFORMANCE MEASUREMENT METRICS Performance Variances Performance Indexes PERFORMANCE FORECASTING METRICS BUDGET AT COMPLETION EARNED VALUE COST VARIANCE COST PERFORMANCE INDEX ESTIMATE COMPLETION ESTIMATE COMPLETE VARIANCE AT COMPLETION TO-COMPLETE PERFORMANCE INDEX SCHEDULE PERFORMANCE INDEX SCHEDULE VARIANCE BAC No formula Total budget for the project ACTUAL COST PLANNED VALUE AC No formula Actual cost of completing the work component by a given point in time. CV CV = EV – AC Variance measuring actual performance to date (or during the period) against what's been spent. SV SV = EV – PV Variance measuring how much behind or ahead of schedule at given point in time. CPI CPI = EV / AC Measure of whether project is within budget or not at given point in time. EAC EAC = BAC / CPI Projection of expected total cost of work component, schedule activity, or project at completion, based on available data at given point in time. ETC ETC = EAC – AC Projection of expected costs of remaining work, based on available data at given point in time. VAC VAC = BAC – EAC Projection of expected variance between budget at completion and estimate at completion, based on available data at given point in time. TCPI 2 formula: • TCPI = (BAC – EV)/(BAC – AC); based on BAC (original BAC only money available) • TCPI = (BAC – EV)/(EAC – AC); based on EAC (new revised EAC approved) Projection of anticipated cost efficiency required to complete work with money available. Results: TCPI greater than 1.0 more difficult to achieve, TCPI less than 1.0 easier to achieve. SPI SPI = EV / PV Measure of whether schedule is ahead of or behind what planned for given point in time. PV PV = BAC x Planned % complete Approved budget assigned to schedule activity or WBS component to be completed by a given point in time. • Formula start with EV • Results: below 1.0 = behind shedule/over budget; exactly 1.0 = on schedule/budget; above 1.0 = ahead of schedule/under budget • Division • Subtraction EV EV = BAC x Actual % complete Value of work completed by a given point in time compared to authorized budgeted amount assigned to work component. Source: A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Fifth Edition Creative Commons Attribution 4.0 International Licence TIPSOGRAPHIC.COM Are you ready to learn more or get more details? Get your free PM infographics today at Tips That Make Life Easier TIPSOGRAPHIC.COM TIPSÖGRAPHIC