SlideShare a Scribd company logo
o The Integrated Program Management Report (IPMR),
Data Item Description DI-MGMT-81861 (latest version)
at http://www.acq.osd.mil/evm/resources/PG-
DIDs.shtml, is a consolidation of the Contract
Performance Report (CPR) and the Integrated Master
Schedule (IMS). See NASA IPMR Data Requirements
Description (DRD) Guide for preparation of the IPMR
DRD.
o Sample Standard Analysis Package
PERFORMANCE MANAGEMENT REFERENCE CARD
ScheduleSlip
Management Reserve (MR)
Cost Variance
Schedule Variance
“Actuals”
ACWPCum
“Earned”
BCWPCum
“Plan”
BCWSCum
$
EAC
Time
Now
Completion
Date
PMB
Total Allocated Budget (TAB)
BAC
Time
EFFICIENCIES
Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0
CPI: For every $1.00 of actual cost, we earned $X worth of work planned
Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0
SPI: For every $1.00 of work planned (scheduled), $X worth of work was accomplished or earned.
CALCULATED ESTIMATE AT COMPLETION = Actuals to Date + [(Remaining Work) / (Performance Factor)]
Examples:
EACCPI = ACWPCUM + [ (BAC – BCWPCUM) / CPICUM ] – typically a best case
EACComposite = ACWPCUM + [ (BAC – BCWPCUM) / (CPICUM * SPICUM) ] – typically a worst case
TO COMPLETE PERFORMANCE INDEX (TCPI) § #
TCPITarget = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (Target – ACWPCUM)
TCPI: For every $1.00 of cost, estimate to earn $X worth of work planned to finish on EAC
§To Determine the TCPI for BAC or EAC ; Replace TARGET with BAC or EAC
# To Determine the Contract Level TCPI for EAC, You May Replace BAC with TAB
OVERALL STATUS*
% Schedule = (BCWSCUM / BAC) * 100
% Complete = (BCWPCUM / BAC) * 100
% Spent = (ACWPCUM / BAC) * 100
VARIANCES Positive is Favorable, Negative is Unfavorable
Cost Variance CV = BCWP – ACWP
(-)=over (+)=under budget CV % = (CV / BCWP) * 100
Schedule Variance SV = BCWP – BCWS
(-)=behind (+)=over schedule SV % = (SV / BCWS) * 100
Variance at Completion VAC = BAC – EAC
VAC % = (VAC / BAC) * 100
o NASA/SP-2012-599 EVM Implementation Handbook
o NASA/SP-2010-3406 Integrated Baseline Review (IBR)
Handbook
o NASA/SP-2010-3403 NASA Schedule Management
Handbook.
o Reporting for Non-EVM Contracts - see Appendix E
of the NASA/SP-2012-599 Earned Value Management
(EVM) Implementation Handbook for sample DRDs
o Instructions for Requesting Access to Empower
o To request the NASA Schedule Test and Assessment
Tool (STAT) application software, go to the NASA
Software Catalog at
https://software.nasa.gov/software/MFS-32602-1
EVM REPORTS (http://evm.nasa.gov/reports.html)
EVM IMPLEMENTATION HANDBOOKS (http://evm.nasa.gov/handbooks.html )
EVM REGULATIONS/REQUIREMENTS
Refer to the NASA Earned Value Management website http://evm.nasa.gov/
o OMB Circular A-11, Appendix J
o NASA NPD 7120.4D – NASA Engineering and Program/Project Management
o NPR 7120.5 – NASA Space Flight Program and Project Management Requirements - defines when EVM is
required and requires projects with EVM requirements to use an EVM system that complies with the 32 Guidelines
found in the EIA-748 Earned Value Management System (EVMS) Standard
o NPR 7120.7 – NASA Information Technology and Institutional Infrastructure Program and Project Management
Requirements
o NPR 7120.8 – NASA Research and Technology Program and Project Management Requirements
o NASA Procurement Class Deviation (PCD) 15-05, Class Deviation to NFS 1834.2, 1834.203-70, 1852.234-1,and
1852.234-2 – EARNED VALUE MANAGEMENT SYSTEM, November 10, 2015
o NASA Procurement Information Circular (PIC) 10-17, Class Deviation to NFS 1816.405-274: Award Fee Evaluation
Factors are not Directly Tied to EVM Metrics , November 15, 2010
o NASA PIC 15-06, Guidance on the Integrated Program Management Report (IPMR) for EVM, April 28, 2015
o NASA EVM Contract Requirements Checklist
o NASA/Defense Contract Management Agency Memorandum of Understanding
o NASA/SP-2010-3404 NASA Work Breakdown (WBS)
Structure Handbook
o NASA/SP2015-3708 EVM Reference Guide for Project
Control Account Managers
Work Packages Planning Packages
Control
Accounts
Summary Level
Planning Packages
Overrun
Negotiated
Contract Cost
Over Target
Baseline
Contract
Budget Base
Total Allocated Budget
Contract Price or
In-house Project Price
Performance Measurement
Baseline
Management
Reserve
Profit / Fees
(no In-house equivalent)
Authorized
Unpriced Work
Undistributed
Budget
NASA Contractor & In-house Project Hierarchy
*Note: For total contract, budget at
completion should include management
reserve and undistributed budget
ETC
Baseline Execution Index (BEI) & Hit/Miss Task % (Favorable is > 1.0, Unfavorable is < 1.0)
BEI = Total Baseline Tasks Completed / (Total Tasks with Baseline Finish On or Prior to Current Report Period)
Hit /Miss Task % = 100 * (Tasks Completed ON or PRIOR to Baseline Finish / Tasks Baselined to Finish within
Current Report Period).
1 of 2
Revised November 2015
EVM APPLICATION AND THRESHOLDSACRONYMS
ACWP Actual Cost of Work Performed – Cost actually incurred in accomplishing work performed aka Actual Cost (AC)
AUW Authorized Unpriced Work – Work formally authorized, but not yet negotiated/definitized
BAC Budget At Completion – Total budget for total project/contract thru any given level
BCWP Budgeted Cost for Work Performed – Value of completed work in terms of the work’s assigned budget aka Earned
Value (EV)
BCWS Budgeted Cost for Work Scheduled – Time-phased Budget Plan for work currently scheduled aka Planned Value (PV)
BEI Baseline Execution Index – Similar to the SPI, the metric used to indicate the efficiency with which actual work has been
accomplished when measured against the baseline. It compares the cumulative number of baselined tasks actually
completed each month to the cumulative number of baselined tasks scheduled to be completed each month. To assess
whether the tasks actually completed as planned during a current month, calculate the Hit/Miss Task %.
CA Control Account – Lowest WBS element assigned to a single focal point to plan & control scope / schedule / budget
CBB Contract Budget Base – Sum of the negotiated project/contract cost plus the estimated cost of authorized unpriced work.
It includes the PMB and MR. Customer approval is generally required to change it.
CPI Cost Performance Index – A measure of cost efficiency. Worth of work for every dollar spent. It compares BCWP to the
actual cost to perform that work (CPI = BCWP / ACWP).
CPM Critical Path Method – A sequential path of tasks in a network schedule that represents the longest overall duration
from “time now” through project completion. Any slippage of the tasks in the critical path will increase the project duration.
DRD Data Requirements Description – The document that describes the specific data required for supplier/contract
management and reporting.
EAC Estimate At Completion – Estimate of total cost for project/contract thru any given level generated by Supplier (Ktr),
PMO, DCMA, etc. = EACKtr / PMO / DCMA. The Supplier’s EAC is also known as Latest Revised Estimate (LRE).
ETC Estimate To Complete – Expected/anticipated costs needed to complete the remainder of work on project/contract.
IBR Integrated Baseline Review – A risk-based review conducted by Program/Project Management to ensure mutual
understanding between the customer and supplier of the risks inherent in the supplier’s performance measurement
baseline (PMB) and to ensure the PMB can be accomplished within the authorized schedule and budget.
IPMR Integrated Program Management Report – Consists of seven formats containing data for measuring cost and schedule
performance on Government acquisition contracts (Formats 1-5 formerly the Contract Performance Report (CPR)):
Format 1 defines cost and schedule performance data by product-oriented WBS elements.
Format 2 defines cost and schedule performance data by supplier's organization structure.
Format 3 defines changes to the Performance Measurement Baseline (PMB).
Format 4 Defines staffing forecasts.
Format 5 is a narrative report used to provide the required analysis of data contained in Formats 1-4 and 6.
Format 6 defines and contains the Integrated Master Schedule (IMS).
Format 7 defines the time-phased historical and forecast cost submission.
LOE Level of Effort – Effort of a general or supportive nature that does not produce definite end products. Examples include
supervision, program administration and contract administration.
NCC Negotiated Contract Cost – Contract Price Minus profit or fee(s). For In-house projects, the agreed to value.
OTB Over Target Baseline – Sum of CBB + additional budget approved for remaining work.
PAC Price At Completion – EAC Plus Adjusted Profit or Fee(s).
PMB Performance Measurement Baseline – The time-phased budget plan for authorized work.
PP Planning Package – Far-term effort not yet defined into WPs.
SLPP Summary Level Planning Package – Far-term contract activities not yet defined into CAs.
SPI Schedule Performance Index – A measure of schedule efficiency. It compares the BCWP to the work scheduled
(SPI = BCWP/BCWS). An index of 1.0 means the work is being performed right to the schedule. SPI > 1.0 means
that the work is ahead of schedule. SPI < 1.0 means that the work is behind schedule.
TAB Total Allocated Budget – Sum of all budgets for work on in-house project or contract = NCC, CBB, or OTB.
UB Undistributed Budget – Budget associated with specific work scope or authorized changes that have not been
assigned to a CA or lower level WBS element.
UFE Unallocated Future Expenses – Estimated cost that cannot be allocated to WBS elements due to risk and future needs.
VAC Variance at Completion – Comparison of the BAC to the EAC through any given level (expected overrun or underrun of
total costs)
WP Work Package – Near-term, detail-planned activities within control account; unit of work at level work is performed.
WBS Work Breakdown Structure – A hierarchical product-oriented division of program tasks depicting the breakdown of work
scope for work authorization, tracking, and reporting purposes.
Development/
Production
Contract
(Total
Estimated
Value)
EIA-748
EVMS
(PCD 15-
05)
NASA
EVMS
Solicitation
& Contract
Clause
(PCD15-05)
IPMR
DRD
(PIC 15-06)
WBS
DRD
Project
Cost
Report
DRD
(Non-
EVM)
Supplier
Flow
Down
(EVM)
Cost or
Incentive Type
≥ $100M
Validation
Required
Required:
NFS
1852.234-1
& NFS
1852.234-2
Required:
Formats 1, 3, 5
and 6 (IMS);
Recommended:
Formats 2, 4
and 7
Required Not
Required
Prime
contractor
responsible
for EVMS
requiremen
ts on sub-
contractors
using same
rules as
applied to
prime
contract.
Cost or
Incentive Type
$20M but
< $100M
Compliance
with
guidelines;
validation
not required
Required:
NFS
1852.234-1
& NFS
1852.234-2
with
Alternate
Required:
Formats 1, 3, 5,
and 6 (IMS);
Optional:
Formats 2, 4,
and 7
Required Not
Required
Cost or
Incentive Type
< $20M; Major
Acquisition
Non-
development
contracts
Not
required
(optional at
discretion of
PM)
Not required
unless PM
elects to
require
EVM; then
apply NFS
1852.234-1
& NFS
1852.234-2
with
Alternate
Required:
Format 6 (IMS)
Recommended:
Format 5
(Formats 1, 3
and 7 not
required unless
PM elects to
require EVM)
Required Required
If EVMS
and IPMR
not
required
Firm Fixed
Price > $20M
Not
required
Not required Required:
Format 6 (IMS);
Recommended:
Format 5
Required Not
required
Jerald Kerby, Agency EVM Program Executive & MSFC EVM Focal Point
jerald.g.kerby@nasa.gov
(256) 544-3243
EVM system compliance and use is required on all acquisitions for development designated as major in accordance with
OMB Circular A-11 and the Capital Programming Guide, and for development or production projects/contracts and
subcontracts, including those for flight and ground systems, institutional requirements (facility, information technology,
investment, etc.) valued at or greater than $20 million. The primary consideration for EVM applicability is the nature of the
work, associated risks, and the value of the effort. EVM is not recommended on Firm Fixed Price contracts or contracts
that are exclusively LOE.
Refer to the NASA Earned Value Management website at http://evm.nasa.gov/
2 of 2

More Related Content

PDF
Earning Value from Earned Value Management
PDF
Earned value in five easy pieces
PPTX
Earned Value Management (EVM) Limitations
PDF
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
PPT
Earned value
PPTX
Delivering nothing efficiently
PDF
Tiffany
PPT
EVM in MS Project
Earning Value from Earned Value Management
Earned value in five easy pieces
Earned Value Management (EVM) Limitations
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned value
Delivering nothing efficiently
Tiffany
EVM in MS Project

What's hot (18)

PDF
How to prepare recovery or revised schedule rev.2
PDF
A gentle introduction to earned value management systems (neutral)
PDF
Schedule Recovery Using Earned Value
PDF
160155061 project-monitoring-control
PPTX
project control using earned value analysis - Part 01
PPT
Earned value analysis training
PDF
Earned Value Management
PPTX
Sorge.les
PPT
L06 cost management
PPT
EVMS Gold Card
PDF
Earned value analysis for a construction project
DOC
Tim Howard
PDF
The Benefits of using Earned Value Management
PPTX
A simple approach to understanding Earned Value Management
PPTX
Evaluating Earned Value Management
PDF
Earned value analysis - presentation
PPT
005 benchmarking-kpi's
How to prepare recovery or revised schedule rev.2
A gentle introduction to earned value management systems (neutral)
Schedule Recovery Using Earned Value
160155061 project-monitoring-control
project control using earned value analysis - Part 01
Earned value analysis training
Earned Value Management
Sorge.les
L06 cost management
EVMS Gold Card
Earned value analysis for a construction project
Tim Howard
The Benefits of using Earned Value Management
A simple approach to understanding Earned Value Management
Evaluating Earned Value Management
Earned value analysis - presentation
005 benchmarking-kpi's
Ad

Similar to Nasa+evm+reference+card nov+2015 (20)

PDF
dfgd
PDF
Project monitoring and controlling with earned value management
PPTX
PMP COST FORMULAE
PDF
PMP Key Exam Concepts - Formulas
PDF
Basic Concepts of Earned Value Management.pdf
PPT
EVA - Metrics.ppt
PPTX
Project monitoring & Earned Value Analysis
PPTX
Earned value management (EVM)
PDF
Topic 10 - Project Performance Management.pdf
PPTX
Projects Control Using Earned Value Techniques - Part One
DOC
Earned Value Management Project Analysis
PPTX
Earned Value Management for project managers
PPTX
Earned Value Analysis
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPT
Evm power point 25 august 2015 prams co (2)
PPT
Evm power point 25 august 2015 prams co (2)
PPTX
Project Cost Management
PPTX
Earned value management for Beginners
PDF
CCP_SEC4_Progress and Cost Control
dfgd
Project monitoring and controlling with earned value management
PMP COST FORMULAE
PMP Key Exam Concepts - Formulas
Basic Concepts of Earned Value Management.pdf
EVA - Metrics.ppt
Project monitoring & Earned Value Analysis
Earned value management (EVM)
Topic 10 - Project Performance Management.pdf
Projects Control Using Earned Value Techniques - Part One
Earned Value Management Project Analysis
Earned Value Management for project managers
Earned Value Analysis
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
Project Cost Management
Earned value management for Beginners
CCP_SEC4_Progress and Cost Control
Ad

More from Dr Ezzat Mansour (20)

PDF
delay protocol
PDF
PERFORMANCE MONITORING USING EVM INDICATOR
PDF
The Earned Value Matutity Management Model
PDF
EARNED VALUE MANAGEMENT
PPT
PDF
Using CMMI to Improve Earned Value Management
PDF
Ray stratton aace presentation
PDF
Evm implementation handbook_sti13-059
PDF
The analysis and valuation of disruption
PDF
Agile and earned value management
PPT
Earned value
PDF
Methods of delay analysis
PDF
Application of value engineering in construction
PDF
Module 3 lecture 1 planning and scheduling(1)
PDF
معدلات إنتاجية المعدات
PDF
Pmp formulas v5
PDF
Pmp formula pocket guide
PDF
اعداد المشروع
PDF
Measurement of the_international_roughness_index_iri_using_an_autonomous_robo...
delay protocol
PERFORMANCE MONITORING USING EVM INDICATOR
The Earned Value Matutity Management Model
EARNED VALUE MANAGEMENT
Using CMMI to Improve Earned Value Management
Ray stratton aace presentation
Evm implementation handbook_sti13-059
The analysis and valuation of disruption
Agile and earned value management
Earned value
Methods of delay analysis
Application of value engineering in construction
Module 3 lecture 1 planning and scheduling(1)
معدلات إنتاجية المعدات
Pmp formulas v5
Pmp formula pocket guide
اعداد المشروع
Measurement of the_international_roughness_index_iri_using_an_autonomous_robo...

Recently uploaded (20)

PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PDF
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
PPTX
Concluding Session_Wrapup-India Jun 5 2024-Oct 5 2025 ZS.pptx
PPTX
Chapter One an overview of political economy
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PDF
Phillips model training for evaluation pdf
PPTX
Five S Training Program - Principles of 5S
PPTX
Human Resource Management | Introduction,Meaning and Definition
PDF
CISSP Domain 6: Security Assessment and Testing
PPT
Claims and Adjustment Business_Communication.pptx.ppt
PDF
The-Power-of-Communication (1).pdf......
PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PPTX
Course Overview of the Course Titled.pptx
PPTX
Effective_communication._(strategy).pptx
PPTX
BASIC H2S TRAINING for oil and gas industries
PPTX
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
PPTX
Human resources management -job perception concept
PDF
Case study -Uber strategic plan and management
PPTX
Consulting on marketing-The needs wants and demands are a very important comp...
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
Concluding Session_Wrapup-India Jun 5 2024-Oct 5 2025 ZS.pptx
Chapter One an overview of political economy
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
Phillips model training for evaluation pdf
Five S Training Program - Principles of 5S
Human Resource Management | Introduction,Meaning and Definition
CISSP Domain 6: Security Assessment and Testing
Claims and Adjustment Business_Communication.pptx.ppt
The-Power-of-Communication (1).pdf......
Improved_Leadership_in_Total_Quality_Lesson.pptx
Course Overview of the Course Titled.pptx
Effective_communication._(strategy).pptx
BASIC H2S TRAINING for oil and gas industries
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
Human resources management -job perception concept
Case study -Uber strategic plan and management
Consulting on marketing-The needs wants and demands are a very important comp...

Nasa+evm+reference+card nov+2015

  • 1. o The Integrated Program Management Report (IPMR), Data Item Description DI-MGMT-81861 (latest version) at http://www.acq.osd.mil/evm/resources/PG- DIDs.shtml, is a consolidation of the Contract Performance Report (CPR) and the Integrated Master Schedule (IMS). See NASA IPMR Data Requirements Description (DRD) Guide for preparation of the IPMR DRD. o Sample Standard Analysis Package PERFORMANCE MANAGEMENT REFERENCE CARD ScheduleSlip Management Reserve (MR) Cost Variance Schedule Variance “Actuals” ACWPCum “Earned” BCWPCum “Plan” BCWSCum $ EAC Time Now Completion Date PMB Total Allocated Budget (TAB) BAC Time EFFICIENCIES Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0 CPI: For every $1.00 of actual cost, we earned $X worth of work planned Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0 SPI: For every $1.00 of work planned (scheduled), $X worth of work was accomplished or earned. CALCULATED ESTIMATE AT COMPLETION = Actuals to Date + [(Remaining Work) / (Performance Factor)] Examples: EACCPI = ACWPCUM + [ (BAC – BCWPCUM) / CPICUM ] – typically a best case EACComposite = ACWPCUM + [ (BAC – BCWPCUM) / (CPICUM * SPICUM) ] – typically a worst case TO COMPLETE PERFORMANCE INDEX (TCPI) § # TCPITarget = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (Target – ACWPCUM) TCPI: For every $1.00 of cost, estimate to earn $X worth of work planned to finish on EAC §To Determine the TCPI for BAC or EAC ; Replace TARGET with BAC or EAC # To Determine the Contract Level TCPI for EAC, You May Replace BAC with TAB OVERALL STATUS* % Schedule = (BCWSCUM / BAC) * 100 % Complete = (BCWPCUM / BAC) * 100 % Spent = (ACWPCUM / BAC) * 100 VARIANCES Positive is Favorable, Negative is Unfavorable Cost Variance CV = BCWP – ACWP (-)=over (+)=under budget CV % = (CV / BCWP) * 100 Schedule Variance SV = BCWP – BCWS (-)=behind (+)=over schedule SV % = (SV / BCWS) * 100 Variance at Completion VAC = BAC – EAC VAC % = (VAC / BAC) * 100 o NASA/SP-2012-599 EVM Implementation Handbook o NASA/SP-2010-3406 Integrated Baseline Review (IBR) Handbook o NASA/SP-2010-3403 NASA Schedule Management Handbook. o Reporting for Non-EVM Contracts - see Appendix E of the NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook for sample DRDs o Instructions for Requesting Access to Empower o To request the NASA Schedule Test and Assessment Tool (STAT) application software, go to the NASA Software Catalog at https://software.nasa.gov/software/MFS-32602-1 EVM REPORTS (http://evm.nasa.gov/reports.html) EVM IMPLEMENTATION HANDBOOKS (http://evm.nasa.gov/handbooks.html ) EVM REGULATIONS/REQUIREMENTS Refer to the NASA Earned Value Management website http://evm.nasa.gov/ o OMB Circular A-11, Appendix J o NASA NPD 7120.4D – NASA Engineering and Program/Project Management o NPR 7120.5 – NASA Space Flight Program and Project Management Requirements - defines when EVM is required and requires projects with EVM requirements to use an EVM system that complies with the 32 Guidelines found in the EIA-748 Earned Value Management System (EVMS) Standard o NPR 7120.7 – NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements o NPR 7120.8 – NASA Research and Technology Program and Project Management Requirements o NASA Procurement Class Deviation (PCD) 15-05, Class Deviation to NFS 1834.2, 1834.203-70, 1852.234-1,and 1852.234-2 – EARNED VALUE MANAGEMENT SYSTEM, November 10, 2015 o NASA Procurement Information Circular (PIC) 10-17, Class Deviation to NFS 1816.405-274: Award Fee Evaluation Factors are not Directly Tied to EVM Metrics , November 15, 2010 o NASA PIC 15-06, Guidance on the Integrated Program Management Report (IPMR) for EVM, April 28, 2015 o NASA EVM Contract Requirements Checklist o NASA/Defense Contract Management Agency Memorandum of Understanding o NASA/SP-2010-3404 NASA Work Breakdown (WBS) Structure Handbook o NASA/SP2015-3708 EVM Reference Guide for Project Control Account Managers Work Packages Planning Packages Control Accounts Summary Level Planning Packages Overrun Negotiated Contract Cost Over Target Baseline Contract Budget Base Total Allocated Budget Contract Price or In-house Project Price Performance Measurement Baseline Management Reserve Profit / Fees (no In-house equivalent) Authorized Unpriced Work Undistributed Budget NASA Contractor & In-house Project Hierarchy *Note: For total contract, budget at completion should include management reserve and undistributed budget ETC Baseline Execution Index (BEI) & Hit/Miss Task % (Favorable is > 1.0, Unfavorable is < 1.0) BEI = Total Baseline Tasks Completed / (Total Tasks with Baseline Finish On or Prior to Current Report Period) Hit /Miss Task % = 100 * (Tasks Completed ON or PRIOR to Baseline Finish / Tasks Baselined to Finish within Current Report Period). 1 of 2 Revised November 2015
  • 2. EVM APPLICATION AND THRESHOLDSACRONYMS ACWP Actual Cost of Work Performed – Cost actually incurred in accomplishing work performed aka Actual Cost (AC) AUW Authorized Unpriced Work – Work formally authorized, but not yet negotiated/definitized BAC Budget At Completion – Total budget for total project/contract thru any given level BCWP Budgeted Cost for Work Performed – Value of completed work in terms of the work’s assigned budget aka Earned Value (EV) BCWS Budgeted Cost for Work Scheduled – Time-phased Budget Plan for work currently scheduled aka Planned Value (PV) BEI Baseline Execution Index – Similar to the SPI, the metric used to indicate the efficiency with which actual work has been accomplished when measured against the baseline. It compares the cumulative number of baselined tasks actually completed each month to the cumulative number of baselined tasks scheduled to be completed each month. To assess whether the tasks actually completed as planned during a current month, calculate the Hit/Miss Task %. CA Control Account – Lowest WBS element assigned to a single focal point to plan & control scope / schedule / budget CBB Contract Budget Base – Sum of the negotiated project/contract cost plus the estimated cost of authorized unpriced work. It includes the PMB and MR. Customer approval is generally required to change it. CPI Cost Performance Index – A measure of cost efficiency. Worth of work for every dollar spent. It compares BCWP to the actual cost to perform that work (CPI = BCWP / ACWP). CPM Critical Path Method – A sequential path of tasks in a network schedule that represents the longest overall duration from “time now” through project completion. Any slippage of the tasks in the critical path will increase the project duration. DRD Data Requirements Description – The document that describes the specific data required for supplier/contract management and reporting. EAC Estimate At Completion – Estimate of total cost for project/contract thru any given level generated by Supplier (Ktr), PMO, DCMA, etc. = EACKtr / PMO / DCMA. The Supplier’s EAC is also known as Latest Revised Estimate (LRE). ETC Estimate To Complete – Expected/anticipated costs needed to complete the remainder of work on project/contract. IBR Integrated Baseline Review – A risk-based review conducted by Program/Project Management to ensure mutual understanding between the customer and supplier of the risks inherent in the supplier’s performance measurement baseline (PMB) and to ensure the PMB can be accomplished within the authorized schedule and budget. IPMR Integrated Program Management Report – Consists of seven formats containing data for measuring cost and schedule performance on Government acquisition contracts (Formats 1-5 formerly the Contract Performance Report (CPR)): Format 1 defines cost and schedule performance data by product-oriented WBS elements. Format 2 defines cost and schedule performance data by supplier's organization structure. Format 3 defines changes to the Performance Measurement Baseline (PMB). Format 4 Defines staffing forecasts. Format 5 is a narrative report used to provide the required analysis of data contained in Formats 1-4 and 6. Format 6 defines and contains the Integrated Master Schedule (IMS). Format 7 defines the time-phased historical and forecast cost submission. LOE Level of Effort – Effort of a general or supportive nature that does not produce definite end products. Examples include supervision, program administration and contract administration. NCC Negotiated Contract Cost – Contract Price Minus profit or fee(s). For In-house projects, the agreed to value. OTB Over Target Baseline – Sum of CBB + additional budget approved for remaining work. PAC Price At Completion – EAC Plus Adjusted Profit or Fee(s). PMB Performance Measurement Baseline – The time-phased budget plan for authorized work. PP Planning Package – Far-term effort not yet defined into WPs. SLPP Summary Level Planning Package – Far-term contract activities not yet defined into CAs. SPI Schedule Performance Index – A measure of schedule efficiency. It compares the BCWP to the work scheduled (SPI = BCWP/BCWS). An index of 1.0 means the work is being performed right to the schedule. SPI > 1.0 means that the work is ahead of schedule. SPI < 1.0 means that the work is behind schedule. TAB Total Allocated Budget – Sum of all budgets for work on in-house project or contract = NCC, CBB, or OTB. UB Undistributed Budget – Budget associated with specific work scope or authorized changes that have not been assigned to a CA or lower level WBS element. UFE Unallocated Future Expenses – Estimated cost that cannot be allocated to WBS elements due to risk and future needs. VAC Variance at Completion – Comparison of the BAC to the EAC through any given level (expected overrun or underrun of total costs) WP Work Package – Near-term, detail-planned activities within control account; unit of work at level work is performed. WBS Work Breakdown Structure – A hierarchical product-oriented division of program tasks depicting the breakdown of work scope for work authorization, tracking, and reporting purposes. Development/ Production Contract (Total Estimated Value) EIA-748 EVMS (PCD 15- 05) NASA EVMS Solicitation & Contract Clause (PCD15-05) IPMR DRD (PIC 15-06) WBS DRD Project Cost Report DRD (Non- EVM) Supplier Flow Down (EVM) Cost or Incentive Type ≥ $100M Validation Required Required: NFS 1852.234-1 & NFS 1852.234-2 Required: Formats 1, 3, 5 and 6 (IMS); Recommended: Formats 2, 4 and 7 Required Not Required Prime contractor responsible for EVMS requiremen ts on sub- contractors using same rules as applied to prime contract. Cost or Incentive Type $20M but < $100M Compliance with guidelines; validation not required Required: NFS 1852.234-1 & NFS 1852.234-2 with Alternate Required: Formats 1, 3, 5, and 6 (IMS); Optional: Formats 2, 4, and 7 Required Not Required Cost or Incentive Type < $20M; Major Acquisition Non- development contracts Not required (optional at discretion of PM) Not required unless PM elects to require EVM; then apply NFS 1852.234-1 & NFS 1852.234-2 with Alternate Required: Format 6 (IMS) Recommended: Format 5 (Formats 1, 3 and 7 not required unless PM elects to require EVM) Required Required If EVMS and IPMR not required Firm Fixed Price > $20M Not required Not required Required: Format 6 (IMS); Recommended: Format 5 Required Not required Jerald Kerby, Agency EVM Program Executive & MSFC EVM Focal Point jerald.g.kerby@nasa.gov (256) 544-3243 EVM system compliance and use is required on all acquisitions for development designated as major in accordance with OMB Circular A-11 and the Capital Programming Guide, and for development or production projects/contracts and subcontracts, including those for flight and ground systems, institutional requirements (facility, information technology, investment, etc.) valued at or greater than $20 million. The primary consideration for EVM applicability is the nature of the work, associated risks, and the value of the effort. EVM is not recommended on Firm Fixed Price contracts or contracts that are exclusively LOE. Refer to the NASA Earned Value Management website at http://evm.nasa.gov/ 2 of 2