                  A GENTLE INTRODUCTION TO
                  EARNED VALUE
                  MANAGEMENT SYSTEMS
                  “Good metrics let us see if we are doing the right
Glen B. Alleman   things and doing them well."
What Do Project Managers Need to Know to Be
Successful?

   Is the project on schedule?
   Is the project on budget?
   How much will this project cost on the end date?
   What is the end date for this project?
   Simple project analysis tools can answer these questions
    using time and cost tracking
   How much is it costing us to earn each unit of value
    –   $1.00 spent returns $X.00 of value?
    –   How much of the budget “should have been” spent at this point in
        the project?
    –   How much “value” has the work on the project “earned” so far?


                                                                           2/31
What Is Earned Value Analysis?

   It is a way to measure the amount of work actually
    performed on a project.
   It is a way to forecast a project’s cost and
    completion date using historical and statistical
    projections.
   It is a way to tell how well a project is
    “performing” compared to its original plan.
   Given this information it is a way to forecast how
    well the project will perform in the future.

                                                         3/31
Some Introductory Definitions
4/31
       In (olde) and (current )notation
          Budgeted Cost of Work Scheduled (BCWS)(PC)
           “The Planned Cost”
           –   This is the total budgeted cost. It answers the question “how much do we plan to
               spend?” A second question that is answered is “How much work should be been
               completed by this date?”
          Budgeted Cost of Work Performed (BCWP)(PV)
           “Earned Value”
           –   This is the cost originally budgeted to accomplish the work that has been
               completed. It answers the question “how much work has been actually
               completed?”
          Actual Cost of Work Performed (ACWP)(AC)
           “The Investment Cost”
           –   The actual cost to accomplish all the work that was performed by a specific
               date. It answers the question “how much did we actually spend to deliver the
               Earned Value?”
Basic Formulas Of Earned Value Management
            Simple EVMS Terms
BCWS        The planned of the work to be performed
BCWP        The “earned value” of the performed work
ACWP        The actual costs – in dollars – to complete the planned work
BAC         The budget to complete the project
            Cost and Schedule Variance
SV          Schedule Variance                            BCWP – BCWS
CV          Cost Variance                                BCWP – ACWP
SPI         Schedule Performance Index                   BCWP / BCWS
CPI         Cost Performance Index                       BCWP / ACWP
EAC         Estimate at Complete                         ACWP + (BAC – BCWP)
TCPI        To Complete Performance Index                (BAC – BCWP) / (EAC – ACWP)
ISAC        Independent Schedule at Complete             Schedule / SPI
VAC         Variance at Complete                         BAC – EAC
5 Print   this page and keep in your notebook. No one, not even the pros can remember these
                                 acronyms without a cheat sheet
6/31
       A Simple Edible Example
       It’s the holidays, it’s cookie baking time! Let’s use Earned Value to
       manage our Christmas Cookie project.
EVMS Of Our Holiday Cookie Baking
7/31
       Process
          Our Christmas Cookie           Analysis after one (1)
           “Plan”                          hour of baking we’ve
            40 cookies per batch          made …
            5 batches per hour (200          150 edible cookies
             cookies per hour)                  some were burnt,
            Schedule: 5 hours to               some hit the floor,
             make 1,000 cookies (a              the kids ate some of the
             big neighborhood)                   dough,
                                                fed some to the dog.
            Budgeted cost = $0.05
             per cookie                       Actual cost of ingredients
            Total Budget = $50.00
                                               after one hour (ACWP)
             for the 1,000 cookies             = $9.00
After One Hour of Making Cookies

        Simple EVMS
BCWS                                     $10.00     Planned cost
BCWP    150 cookies X $0.05 per Cookie    $7.50     Product cost
ACWP                                      $9.00     Materials cost
        Cost and Schedule Variance
SV      BCWP – BCWS ($7.50 - $10.00)     –$2.50     We’re behind schedule
CV      BCWP – ACWP ($7.50 - $9.00)      –$1.50     We’re over budget
SPI     BCWP / BCWS                        0.75     25% behind schedule
CPI     BCWP / ACWP                        0.833 17% over budget




                                             8/31
What’s Going To Happen At The End
 Of The Project?

       Forecasting our production
IEAC   BAC / CPI ($50.00 / 0.833)     $60.00      Our plan was $50.00, darn
VAC    BAC – IEAC ($50.00 – $60.00)   $10.00      We’ll be $10 over budget
ISAC   5 hours / SPI (5 / 0.75)         6.67      And we’re gonna be late




                                           9/31
Can We Catch Up In Time?
10




                                     Forecasting the future
     To Complete Performance Index    (Budget – BCWP) / (EAC – ACWP)
     TCPI                             (50.00 – 7.50) / (500.00 – 9.00)   1.036
                                      42.50 / 41.00
A Simple EVMS Chart
   (The linear form is never this way in practice, it is an S-Curve)


$50.00


$40.00
                                    BCWS                          SV
                                                                  in $   CV
$30.00


$20.00   SV in hours

                            ACWP
$10.00
                           BCWP

                Hour 1     Hour 2   Hour 3    Hour 4     Hour 5



                                                                              11/31
PUTTING THESE “SIMPLE”
CONCEPTS INTO PRACTICE
EVMS can be deployed in many ways. For us the straight
forward way is to “micro–schedule” the work activities.
                                                          12/31
A Micro–Schedule
   Micro–scheduling does NOT mean micro–managing.
   It means planning at a sufficient level of detail to
    identify useful tasks that can be measured in days (3 to
    5) or at most a week.
   Micro–schedules consists of:
     Objective completion criteria – so we know when we are
      done.
     “Budgets” and “Values” – usually representing person days
      and some “measurable” value to the customer in terms of
      dollars.
     Planned Completion Dates – so we know when to expect
      these tasks to be done.

                                      13/31
Some Fundamental Concepts of EVMS

   Never relate what was planned to be spent (BCWS) to
    the actual amount spent (ACWP).
     This tells us nothing of value
     It can warp our thinking into attempting to under–spend our
      allowed amount to report favorable numbers.
     Only report what was actually spent (ACWP) against what
      “value” was delivered for that planned investment (BCWP)
   Cost Performance (CV) reports what has been
    accomplished (BCWP) versus what was invested to
    accomplish that work (ACWP).

                                       14/31
15/31




A FRAMEWORK FOR
DEPLOYING EVMS
Let’s do it the simple way with some common sense†
First the Bad News
16
ANSI/EIA–748A–2002 And Success Criteria Of
Earned Value Management

   The EIA 748 specification calls out 32 performance
    criteria required for compliance.
   These criteria are too complex for our “agile”
    environment.
   There are 10 key criteria that can be deployed
    here.




                                                         17/31
ANSI/EIA–748A–2002 And Success
     Criteria Of Earned Value Management
18
10 Criteria For Successful EVMS
1. Define authorized work elements
2. Identify project organizational structure
5. Provide integrated planning, scheduling, budgeting, work
    authorization, and cost accumulation processes
6. Schedule the authorized work in a sequential manner that
    identifies the significant task dependencies
7. Identify physical products and organizations
8. Establish and maintain time–phased budget baseline
16. Record direct costs consistently in a formal manner
23. Periodically generate project metrics
25. Develop revised cost estimates–at–completion based on
    performance to date
28. Incorporate authorized changes in a timely manner

                                        19/31
10 Criteria For Successful EVMS
20
Define Authorized Work Elements
   Create a Work Breakdown Structure (WBS) for all
    activities at the micro–schedule level
   The scope of the entire project must be defined in order
    to measure performance.
     This is a problem for agile methods, since scope evolves as
      the project evolves
     Schedule major iterations on 2 to 3 week boundaries
     Generate “macro” estimates of future work and “micro”
      estimates of the current iteration's work
   Defined project objectives, deliverables, and key
    milestones are based primarily on experience
                                        21/31
Identify Project Organizational
Structure
   Identify the structure of the functional organizations
    performing the work
   Define all organizational elements responsible for
    delivering value
   Identify who is doing what and what value they are
    delivering
   Assign all tasks to specific named resources
   Identify the major milestones and those responsible
    for meeting the commitments represented by these
    milestones
                                   22/31
Provide Integrated Planning, Scheduling, Budgeting,
Work Authorization, And Cost Accumulation Processes

   Provide integration of the firm’s:
     Planning,

     Scheduling,

     Budgeting,

     Work  Authorization
     Cost accumulation

   Project management processes should be integrated
    with the WBS and the functional organization.


                                   23/31
Schedule The Authorized Work In A Sequential Manner
That Identifies The Significant Task Dependencies

   Describe the work sequence
   Identify significant dependencies required to meet
    the requirements
   Identify which tasks are impeading the process of
    other tasks
   Create a “master schedule” for larger projects to
    connect the subordinate projects



                                  24/31
Identify Physical Products And The
Organizations That Produce Them
   All project must be able to identify and measure
    physical performance
   Define metrics which convert to “planned values” into
    “earned values”
   Project must specify:
     Physical Products
     Deliverables
     Outputs
     Metrics
     Milestones
     Technical performance indicators



                                         25/31
Establish And Maintain A Time–phased
Performance Measurement Baseline
   Establish initial budgets on internal management
    estimates and external negotiated targets
   Budget for long–term efforts must be held at higher
    levels of the organization
   Time–phased budget is required to measure
    performance
     Staff

     Other   Direct Costs (ODC)


                                   26/31
Record Direct Cost Consistency In A
Formal System
   “Applied Direct Costs” is the preferred method of
    accounting for the accrual of “value”
   Isolate Level of Effort costs in a separate WBS
    element




                                  27/31
Periodically Generate Project Metrics

   The amount of planned versus budget earned for
    the work accomplished
   The amount of budget earned versus the actual
    direct costs for the same work
     This   is the “cost variance”
   This differentiates EVMS from other “actual versus
    budget” cost analysis
     Weekly   measures are now the “norm”
     Comparisons need to be detailed enough to provide
      intervention opportunities

                                      28/31
Develop Revised Cost Estimates–at–completion
(EAC) Based On Performance To Date

   Compare this information with the performance
    measure baseline to identify variances at
    completion




                                29/31
Incorporate Authorized Changes In A
Timely Manner
   All changes must be addressed as they effect
    budget and schedule
   Base changes on the estimated amount and
    assignment to functional organizations needs to be
    recorded as well
   All approved changes must be incorporated into the
    project baseline



                                 30/31
Ten Benefits of EVMS
   It is a single management control system to provide reliable and consistent
    data on project performance.
   It integrates work, schedule, and cost using a work breakdown structure.
   The associated database of completed projects is useful for comparative
    analysis.
   The cumulative cost performance index (CPI) provides an early warning
    signal.
   The schedule performance index provides an early warning signal.
   The CPI is a predictor for the final cost of the project.
   It uses an index–based method to forecast the final cost of the project.
   The “to-complete” performance index allows evaluation of the forecasted
    final cost.
   The periodic (e.g., weekly or monthly) CPI is a benchmark.
   The management by exception principle can reduce information overload.

                                                31/31

More Related Content

PPTX
Earned value management for Beginners
PDF
Earned Value Management
PDF
IMP & WBS - Getting Both Right is Paramount
PPTX
Earned Value Analysis - Basic Concepts
PPTX
project control using earned value analysis - Part 01
PPTX
PMBOK® 6ª edición NOVEDADES
PDF
Project Management Risks Review
PPTX
Earned value management
Earned value management for Beginners
Earned Value Management
IMP & WBS - Getting Both Right is Paramount
Earned Value Analysis - Basic Concepts
project control using earned value analysis - Part 01
PMBOK® 6ª edición NOVEDADES
Project Management Risks Review
Earned value management

What's hot (20)

PPTX
6- PMP Training - Cost Management
PPT
2.project lifecycle
PPTX
project management
PPTX
Earned Value Management, descubriendo el standard ANSI 748-B
PDF
EVM of Project Management...
PDF
Project quality management
PDF
Back to basics - Earned Value Management for beginners webinar
PDF
Project Scheduling & Controls
PPTX
Lec 03 project life cycle
PPTX
Project management
PPTX
projec kickoff presentation template
PDF
Project Controlling and Project Monitoring
PDF
The Future of Project Controls: Improve project performance using Big Data by...
PDF
Baseline Schedules 2
PPTX
Projrct Monitoring & Controling
PPT
Project Control- Overview Presentation Tafseer
PDF
Meeting Project Schedule Compliance Standards
PDF
Schedule Recovery Using Earned Value
PDF
Color coded Multi-Project Monitoring (CPM)
6- PMP Training - Cost Management
2.project lifecycle
project management
Earned Value Management, descubriendo el standard ANSI 748-B
EVM of Project Management...
Project quality management
Back to basics - Earned Value Management for beginners webinar
Project Scheduling & Controls
Lec 03 project life cycle
Project management
projec kickoff presentation template
Project Controlling and Project Monitoring
The Future of Project Controls: Improve project performance using Big Data by...
Baseline Schedules 2
Projrct Monitoring & Controling
Project Control- Overview Presentation Tafseer
Meeting Project Schedule Compliance Standards
Schedule Recovery Using Earned Value
Color coded Multi-Project Monitoring (CPM)
Ad

Viewers also liked (20)

PDF
Earning Value from Earned Value Management
PDF
A simple example of Earned Value Management (EVM) in action
PPTX
Earned Value Reporting
PDF
Control systems
PPT
Earned value
PDF
Earned Value fundamentals
PDF
Earned value in five easy pieces
PDF
Ev+agile=success
PDF
Big data meets evm (submitted)
PPS
Earned Value Management
PDF
Earned Value Management Meets Big Data
PDF
Measurement News Webinar
PDF
Earned value management with Examples | Control Cost | PMBOK | PMP
PDF
Successfully Integrating Agile and Earned Value
PDF
Agile in the government
PDF
Agile at scale resources
PDF
Applying the checklist manifesto for project management success
PDF
The simple problem of schedule performance indices
PDF
Flawless Execution
Earning Value from Earned Value Management
A simple example of Earned Value Management (EVM) in action
Earned Value Reporting
Control systems
Earned value
Earned Value fundamentals
Earned value in five easy pieces
Ev+agile=success
Big data meets evm (submitted)
Earned Value Management
Earned Value Management Meets Big Data
Measurement News Webinar
Earned value management with Examples | Control Cost | PMBOK | PMP
Successfully Integrating Agile and Earned Value
Agile in the government
Agile at scale resources
Applying the checklist manifesto for project management success
The simple problem of schedule performance indices
Flawless Execution
Ad

Similar to A gentle introduction to earned value management systems (neutral) (20)

PDF
EVMS Made Simple
PPTX
Earned Value Analysis in construction projects
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPT
EVA - Metrics.ppt
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PDF
Project monitoring and controlling with earned value management
PDF
Basics of EVM.pdf
PPT
Earned value
PDF
The simple problem of schedule performance indices
PPT
Project Earned Value Management and principles
PPT
R simpson elee
PDF
Evm class 02 1to15 by upad
PPT
Project Management Earned Value
PPTX
Earned Value Analysis
PDF
Basic Concepts of Earned Value Management.pdf
PPTX
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PPT
EARNED VALUE MANAGEMENT ANALYS 1.ppt
PPT
EarnedValue.ppt
PPTX
Project Cost Management
EVMS Made Simple
Earned Value Analysis in construction projects
Earned Value AnalysisTracking Project ProgressWh.docx
EVA - Metrics.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Project monitoring and controlling with earned value management
Basics of EVM.pdf
Earned value
The simple problem of schedule performance indices
Project Earned Value Management and principles
R simpson elee
Evm class 02 1to15 by upad
Project Management Earned Value
Earned Value Analysis
Basic Concepts of Earned Value Management.pdf
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EarnedValue.ppt
Project Cost Management

More from Glen Alleman (20)

PDF
Managing risk with deliverables planning
PDF
A Gentle Introduction to the IMP/IMS
PDF
Increasing the Probability of Project Success
PDF
Process Flow and Narrative for Agile+PPM
PDF
Practices of risk management
PDF
Principles of Risk Management
PDF
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
PDF
From Principles to Strategies for Systems Engineering
PDF
NAVAIR Integrated Master Schedule Guide guide
PDF
Building a Credible Performance Measurement Baseline
PDF
Integrated master plan methodology (v2)
PDF
IMP / IMS Step by Step
PDF
DHS - Using functions points to estimate agile development programs (v2)
PDF
Making the impossible possible
PDF
Heliotropic Abundance
PDF
Capabilities based planning
PDF
Process Flow and Narrative for Agile
PDF
Building the Performance Measurement Baseline
PPTX
Program Management Office Lean Software Development and Six Sigma
PDF
Policy and Procedure Rollout
Managing risk with deliverables planning
A Gentle Introduction to the IMP/IMS
Increasing the Probability of Project Success
Process Flow and Narrative for Agile+PPM
Practices of risk management
Principles of Risk Management
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
From Principles to Strategies for Systems Engineering
NAVAIR Integrated Master Schedule Guide guide
Building a Credible Performance Measurement Baseline
Integrated master plan methodology (v2)
IMP / IMS Step by Step
DHS - Using functions points to estimate agile development programs (v2)
Making the impossible possible
Heliotropic Abundance
Capabilities based planning
Process Flow and Narrative for Agile
Building the Performance Measurement Baseline
Program Management Office Lean Software Development and Six Sigma
Policy and Procedure Rollout

Recently uploaded (20)

PPTX
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PPTX
Big Data Technologies - Introduction.pptx
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
cuic standard and advanced reporting.pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PPT
Teaching material agriculture food technology
PDF
Encapsulation theory and applications.pdf
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
Approach and Philosophy of On baking technology
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
ACSFv1EN-58255 AWS Academy Cloud Security Foundations.pptx
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Big Data Technologies - Introduction.pptx
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
Network Security Unit 5.pdf for BCA BBA.
cuic standard and advanced reporting.pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Teaching material agriculture food technology
Encapsulation theory and applications.pdf
Reach Out and Touch Someone: Haptics and Empathic Computing
“AI and Expert System Decision Support & Business Intelligence Systems”
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
Understanding_Digital_Forensics_Presentation.pptx
Approach and Philosophy of On baking technology
How UI/UX Design Impacts User Retention in Mobile Apps.pdf

A gentle introduction to earned value management systems (neutral)

  • 1. 1/31 A GENTLE INTRODUCTION TO EARNED VALUE MANAGEMENT SYSTEMS “Good metrics let us see if we are doing the right Glen B. Alleman things and doing them well."
  • 2. What Do Project Managers Need to Know to Be Successful?  Is the project on schedule?  Is the project on budget?  How much will this project cost on the end date?  What is the end date for this project?  Simple project analysis tools can answer these questions using time and cost tracking  How much is it costing us to earn each unit of value – $1.00 spent returns $X.00 of value? – How much of the budget “should have been” spent at this point in the project? – How much “value” has the work on the project “earned” so far? 2/31
  • 3. What Is Earned Value Analysis?  It is a way to measure the amount of work actually performed on a project.  It is a way to forecast a project’s cost and completion date using historical and statistical projections.  It is a way to tell how well a project is “performing” compared to its original plan.  Given this information it is a way to forecast how well the project will perform in the future. 3/31
  • 4. Some Introductory Definitions 4/31 In (olde) and (current )notation  Budgeted Cost of Work Scheduled (BCWS)(PC) “The Planned Cost” – This is the total budgeted cost. It answers the question “how much do we plan to spend?” A second question that is answered is “How much work should be been completed by this date?”  Budgeted Cost of Work Performed (BCWP)(PV) “Earned Value” – This is the cost originally budgeted to accomplish the work that has been completed. It answers the question “how much work has been actually completed?”  Actual Cost of Work Performed (ACWP)(AC) “The Investment Cost” – The actual cost to accomplish all the work that was performed by a specific date. It answers the question “how much did we actually spend to deliver the Earned Value?”
  • 5. Basic Formulas Of Earned Value Management Simple EVMS Terms BCWS The planned of the work to be performed BCWP The “earned value” of the performed work ACWP The actual costs – in dollars – to complete the planned work BAC The budget to complete the project Cost and Schedule Variance SV Schedule Variance BCWP – BCWS CV Cost Variance BCWP – ACWP SPI Schedule Performance Index BCWP / BCWS CPI Cost Performance Index BCWP / ACWP EAC Estimate at Complete ACWP + (BAC – BCWP) TCPI To Complete Performance Index (BAC – BCWP) / (EAC – ACWP) ISAC Independent Schedule at Complete Schedule / SPI VAC Variance at Complete BAC – EAC 5 Print this page and keep in your notebook. No one, not even the pros can remember these acronyms without a cheat sheet
  • 6. 6/31 A Simple Edible Example It’s the holidays, it’s cookie baking time! Let’s use Earned Value to manage our Christmas Cookie project.
  • 7. EVMS Of Our Holiday Cookie Baking 7/31 Process  Our Christmas Cookie  Analysis after one (1) “Plan” hour of baking we’ve  40 cookies per batch made …  5 batches per hour (200  150 edible cookies cookies per hour)  some were burnt,  Schedule: 5 hours to  some hit the floor, make 1,000 cookies (a  the kids ate some of the big neighborhood) dough,  fed some to the dog.  Budgeted cost = $0.05 per cookie  Actual cost of ingredients  Total Budget = $50.00 after one hour (ACWP) for the 1,000 cookies = $9.00
  • 8. After One Hour of Making Cookies Simple EVMS BCWS $10.00 Planned cost BCWP 150 cookies X $0.05 per Cookie $7.50 Product cost ACWP $9.00 Materials cost Cost and Schedule Variance SV BCWP – BCWS ($7.50 - $10.00) –$2.50 We’re behind schedule CV BCWP – ACWP ($7.50 - $9.00) –$1.50 We’re over budget SPI BCWP / BCWS 0.75 25% behind schedule CPI BCWP / ACWP 0.833 17% over budget 8/31
  • 9. What’s Going To Happen At The End Of The Project? Forecasting our production IEAC BAC / CPI ($50.00 / 0.833) $60.00 Our plan was $50.00, darn VAC BAC – IEAC ($50.00 – $60.00) $10.00 We’ll be $10 over budget ISAC 5 hours / SPI (5 / 0.75) 6.67 And we’re gonna be late 9/31
  • 10. Can We Catch Up In Time? 10 Forecasting the future To Complete Performance Index  (Budget – BCWP) / (EAC – ACWP) TCPI  (50.00 – 7.50) / (500.00 – 9.00) 1.036  42.50 / 41.00
  • 11. A Simple EVMS Chart (The linear form is never this way in practice, it is an S-Curve) $50.00 $40.00 BCWS SV in $ CV $30.00 $20.00 SV in hours ACWP $10.00 BCWP Hour 1 Hour 2 Hour 3 Hour 4 Hour 5 11/31
  • 12. PUTTING THESE “SIMPLE” CONCEPTS INTO PRACTICE EVMS can be deployed in many ways. For us the straight forward way is to “micro–schedule” the work activities. 12/31
  • 13. A Micro–Schedule  Micro–scheduling does NOT mean micro–managing.  It means planning at a sufficient level of detail to identify useful tasks that can be measured in days (3 to 5) or at most a week.  Micro–schedules consists of:  Objective completion criteria – so we know when we are done.  “Budgets” and “Values” – usually representing person days and some “measurable” value to the customer in terms of dollars.  Planned Completion Dates – so we know when to expect these tasks to be done. 13/31
  • 14. Some Fundamental Concepts of EVMS  Never relate what was planned to be spent (BCWS) to the actual amount spent (ACWP).  This tells us nothing of value  It can warp our thinking into attempting to under–spend our allowed amount to report favorable numbers.  Only report what was actually spent (ACWP) against what “value” was delivered for that planned investment (BCWP)  Cost Performance (CV) reports what has been accomplished (BCWP) versus what was invested to accomplish that work (ACWP). 14/31
  • 15. 15/31 A FRAMEWORK FOR DEPLOYING EVMS Let’s do it the simple way with some common sense†
  • 16. First the Bad News 16
  • 17. ANSI/EIA–748A–2002 And Success Criteria Of Earned Value Management  The EIA 748 specification calls out 32 performance criteria required for compliance.  These criteria are too complex for our “agile” environment.  There are 10 key criteria that can be deployed here. 17/31
  • 18. ANSI/EIA–748A–2002 And Success Criteria Of Earned Value Management 18
  • 19. 10 Criteria For Successful EVMS 1. Define authorized work elements 2. Identify project organizational structure 5. Provide integrated planning, scheduling, budgeting, work authorization, and cost accumulation processes 6. Schedule the authorized work in a sequential manner that identifies the significant task dependencies 7. Identify physical products and organizations 8. Establish and maintain time–phased budget baseline 16. Record direct costs consistently in a formal manner 23. Periodically generate project metrics 25. Develop revised cost estimates–at–completion based on performance to date 28. Incorporate authorized changes in a timely manner 19/31
  • 20. 10 Criteria For Successful EVMS 20
  • 21. Define Authorized Work Elements  Create a Work Breakdown Structure (WBS) for all activities at the micro–schedule level  The scope of the entire project must be defined in order to measure performance.  This is a problem for agile methods, since scope evolves as the project evolves  Schedule major iterations on 2 to 3 week boundaries  Generate “macro” estimates of future work and “micro” estimates of the current iteration's work  Defined project objectives, deliverables, and key milestones are based primarily on experience 21/31
  • 22. Identify Project Organizational Structure  Identify the structure of the functional organizations performing the work  Define all organizational elements responsible for delivering value  Identify who is doing what and what value they are delivering  Assign all tasks to specific named resources  Identify the major milestones and those responsible for meeting the commitments represented by these milestones 22/31
  • 23. Provide Integrated Planning, Scheduling, Budgeting, Work Authorization, And Cost Accumulation Processes  Provide integration of the firm’s:  Planning,  Scheduling,  Budgeting,  Work Authorization  Cost accumulation  Project management processes should be integrated with the WBS and the functional organization. 23/31
  • 24. Schedule The Authorized Work In A Sequential Manner That Identifies The Significant Task Dependencies  Describe the work sequence  Identify significant dependencies required to meet the requirements  Identify which tasks are impeading the process of other tasks  Create a “master schedule” for larger projects to connect the subordinate projects 24/31
  • 25. Identify Physical Products And The Organizations That Produce Them  All project must be able to identify and measure physical performance  Define metrics which convert to “planned values” into “earned values”  Project must specify:  Physical Products  Deliverables  Outputs  Metrics  Milestones  Technical performance indicators 25/31
  • 26. Establish And Maintain A Time–phased Performance Measurement Baseline  Establish initial budgets on internal management estimates and external negotiated targets  Budget for long–term efforts must be held at higher levels of the organization  Time–phased budget is required to measure performance  Staff  Other Direct Costs (ODC) 26/31
  • 27. Record Direct Cost Consistency In A Formal System  “Applied Direct Costs” is the preferred method of accounting for the accrual of “value”  Isolate Level of Effort costs in a separate WBS element 27/31
  • 28. Periodically Generate Project Metrics  The amount of planned versus budget earned for the work accomplished  The amount of budget earned versus the actual direct costs for the same work  This is the “cost variance”  This differentiates EVMS from other “actual versus budget” cost analysis  Weekly measures are now the “norm”  Comparisons need to be detailed enough to provide intervention opportunities 28/31
  • 29. Develop Revised Cost Estimates–at–completion (EAC) Based On Performance To Date  Compare this information with the performance measure baseline to identify variances at completion 29/31
  • 30. Incorporate Authorized Changes In A Timely Manner  All changes must be addressed as they effect budget and schedule  Base changes on the estimated amount and assignment to functional organizations needs to be recorded as well  All approved changes must be incorporated into the project baseline 30/31
  • 31. Ten Benefits of EVMS  It is a single management control system to provide reliable and consistent data on project performance.  It integrates work, schedule, and cost using a work breakdown structure.  The associated database of completed projects is useful for comparative analysis.  The cumulative cost performance index (CPI) provides an early warning signal.  The schedule performance index provides an early warning signal.  The CPI is a predictor for the final cost of the project.  It uses an index–based method to forecast the final cost of the project.  The “to-complete” performance index allows evaluation of the forecasted final cost.  The periodic (e.g., weekly or monthly) CPI is a benchmark.  The management by exception principle can reduce information overload. 31/31