SlideShare a Scribd company logo
CSE Senior Design I
CSE Senior Design I
Earned Value Management
Earned Value Management
Partially adapted from Mike O’Dell. Some slides in this presentation were
originally developed by Mr. Tom Rethard.
Instructor: Manfred Huber
Instructor: Manfred Huber
4
2
Earned Value - What is it?
Earned Value - What is it?
Simply, it is a project monitoring and
measurement system that:
1. establishes a clear relationship between
planned
planned accomplishments and actual
actual
accomplishments
2.
2. reinforces
reinforces and rewards good planning
good planning practices
4
3
Earned Value - What is it?
Earned Value - What is it?
Basic concepts of Earned Value
Management (EVM)
 Each task in a project earns value as planned
planned
work
work is completed
For example (perhaps), if you were paid on this basis,
you would earn
earn $$ at key milestones based on the
value of what you have completed (earned value)
 Earned value can be compared to actual cost
and budgeted cost to determine variance and
predict future performance
4
4
Earned Value - What is it?
Earned Value - What is it?
 The budgeted cost
budgeted cost (e.g., dollars, person-hours,
person-days, etc.) in terms of your baseline
baseline
plan/budget
plan/budget of the work performed up to a specified
point in time
 Also known as Budgeted Cost of Work Performed
(BCWP
BCWP)
 Each task in the Work Breakdown Structure (WBS)
is assigned a BCWP based on its individual cost.
 Project BCWP is total of BCWP for all tasks required to
complete the project
4
5
Earned Value Components
Earned Value Components
 Planned Value (a.k.a. BCWS
BCWS)
 How much work (person-hours) you planned to have
accomplished at a given point in time (this is from the
WBS in your plan)
 Actual Cost (a.k.a. ACWP
ACWP)
 How much work (person-hours) you have actually spent
at a given point in time
 Earned Value (a.k.a. BCWP
BCWP)
 The value (person-hours) in terms of your base budget of
what you have accomplished at a given point in time (or,
% complete X Planned Value)
4
6
Earned Value: Example
Earned Value: Example
On Day X:
 PLANNED VALUE
PLANNED VALUE (Budgeted cost of the work scheduled, BCWS) =
18 + 10 + 16 + 6 = 50
 EARNED VALUE
EARNED VALUE (Budgeted cost of the work performed, BCWP) =
18 + 8 + 14 + 0 = 40
 ACTUAL COST
ACTUAL COST (of the work performed , ACWP) =
55 (from your project tracking - not evident in above chart)
18
8
14
Today
4
7
Earned Value: Example
Earned Value: Example
Cost
(Person-Hours)
Time (Date)
Planned Value
Planned Value: what your
plan called for sending on
the tasks planned to be
completed by this date.
Today
Earned Value
Earned Value: value
(cost) of what you have
accomplished to date, per
the base plan.
Actual Cost
Actual Cost: what you
have actually spent to
this point in time.
Budgeted (Planned) Spending
Budgeted (Planned) Spending
Actual Spending
Actual Spending
Earned Value
Earned Value
4
8
Earned Value: Example
Earned Value: Example
Cost
(Person-Hours)
Time (Date)
Today
Budgeted (Planned) Spending
Budgeted (Planned) Spending
Actual Spending
Actual Spending
Earned Value
Earned Value
Behind
Behind
Schedule
Schedule
Over
Over
Budget
Budget
4
9
Variance
Variance
Any schedule or cost deviation
schedule or cost deviation from a
specific plan.
Used within an organization to verify the
budget and schedule for a project
Frequently used as a key component of
plan reviews and performance
plan reviews and performance
measurement
measurement
4
10
Variance
Variance
Must compare scheduling and budget
variance at the same time
 Schedule variance
Schedule variance: deviations from work
planned – not a measure of changes in cost
 Cost variance
Cost variance: deviations from the
budget – not a measure of work scheduled vs.
work completed
Example: applying more $$/people to a task may
maintain the schedule, but it adds to cost… schedule
on track… over budget on expenses (cost)
4
11
Performance Indices
Performance Indices
Cost Performance Index
 CPI
CPI = BCWP/ACWP
Schedule Performance Index
 SPI
SPI = BCWP/BCWS
Analysis
 CPI > 1.0  exceptional performance
 CPI < 1.0  poor performance
 Similar for SPI
4
14
Earned Value & Variance: Example
Earned Value & Variance: Example
On Day X:
 PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50
 EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40
 ACTUAL COST (ACWP) = 55 (from your project tracking)
Therefore:
 Schedule Variance
Schedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind schedule)
 Schedule Performance Index
Schedule Performance Index = 40 / 50 = 0.8, or 80% of plan (a B-, at best)
 Cost Variance
Cost Variance = BCWP - ACWP = 40 - 55 = -15
 Cost Performance Index
Cost Performance Index = 40/55 = .73, or you’re getting an 73¢ return on every $1.00
(or, person-hour) spent on this project
18
8
14
4
15
Primary Measurement Methods
Primary Measurement Methods
Measurable
Measurable efforts
 Discrete increments of work
Discrete increments of work with definable
schedule and tangible results (i.e., real tasks with
a deliverable)
Level of effort
Level of effort
 Work that is not
not discernable in discrete
discrete,
measurable tasks (e.g., project management,
training)
4
16
Determining % Complete – When?
Determining % Complete – When?
 Allocate based on time spent – but what if you
spend more time than allocated?
 Allocate 50% at start of task, 50% at end
 But only for small, discrete tasks
small, discrete tasks
 Allocate 100% at start of task
 Allocate 100% at end of task
 Best solution if you keep tasks very small
keep tasks very small
 Allocate value at Critical Milestones
 Good solution when using with contract work
 Others?
Our approach
4
17
Another Example Project
Another Example Project
 Plans to spend $100K in each of first 4 weeks
(baseline budget, per documented plan
per documented plan)
 Actuals, at end of week 4 show: $325K spent
 BCWS = $400K ($100K x 4)
 ACWP = $325K
 What conclusions can you draw?
 Under budget?
 Is project on schedule?
4
18
Another Example Project
Another Example Project
Suppose BCWP is $300K
 How is this determined?
What conclusions now?
 SV = BCWP – BCWS
 SV = $300k - $400K = -$100K
Behind schedule
Behind schedule, but what does the $100K in variance
really mean?
 CV = BCWP – ACWP = $300K - $325K
Over budget
Over budget by $25K
4
19
Earned Value Management
Earned Value Management
 How can you use this information?
 Careful analysis of variance and trends
 Resetting schedule or budget, when appropriate
 Variance Analysis Questions
 What is the problem causing the variance?
 What is the impact on time, cost and performance?
 What is the impact on other efforts, if any?
 What corrective action is planned or under way?
 What are the expected results of the corrective action?
4
20
Earned Value Management
Earned Value Management
 Extraordinary variance or alarming trends may be
cause for reset or cancellation of
reset or cancellation of a project, but
where do you draw the line?
 How much variance to allow depends on a
number of factors:
 Life-cycle phase
 Length of life-cycle phase
 Length of project
 Type of estimate
 Accuracy of estimate
4
21
Variance Projection
Variance Projection
4
22
Performance Index Trends
Performance Index Trends
4
23
Ideal Performance Index
Ideal Performance Index
4
24
Closing Thoughts: Management
Closing Thoughts: Management
Reserve
Reserve
The padding always added to a project for
unexpected costs that are within project
scope
 Not an allowance for changes to scope
 Not part of the cost estimate
Added by upper management, not the project
manager.
4
25
Closing Thoughts: Government
Closing Thoughts: Government
Requirements
Requirements
 U.S. government contract cost tracking often must
include:
 BCWS
 BCWP
 ACWP
 Estimated cost at completion
 Budgeted cost at completion
 Cost and schedule variances with explanations
 Traceability
4
26
Summary
Summary
Cost, in the form of Earned Value or BCWP,
can be used to analyze progress
analyze progress of a project
Using Earned Value data to make critical
project decisions must be based on careful
careful
analysis
analysis of data, variances and trends

More Related Content

PPT
Earned value
PPT
Earned Value Analysis
PPT
EVA - Metrics.ppt
PPT
EARNED VALUE MANAGEMENT ANALYS 1.ppt
PDF
Basics of EVM.pdf
PDF
Project monitoring and controlling with earned value management
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPTX
Earned Value Analysis in construction projects
Earned value
Earned Value Analysis
EVA - Metrics.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
Basics of EVM.pdf
Project monitoring and controlling with earned value management
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Earned Value Analysis in construction projects

Similar to Project Earned Value Management and principles (20)

PPT
EarnedValue.ppt
PDF
Basic Concepts of Earned Value Management.pdf
PPTX
Project monitoring lecture 1
PDF
Odoo experience 2015 earned value management
PPT
Project Management Earned Value
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
Project Cost Management
PPTX
Earned Value Management chapter 8 pm2.pptx
PPT
Earned value Project Management (evpm)
PDF
CCP_SEC4_Progress and Cost Control
DOCX
What Is Earned Value Analysis
PPT
Evm power point 25 august 2015 prams co (2)
PPT
Evm power point 25 august 2015 prams co (2)
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPT
PF_EarnedValuePresentation.ppt
PPT
Project Planning and Excution chapter 4.ppt
PDF
Topic 10 - Project Performance Management.pdf
PPTX
Project monitoring & Earned Value Analysis
EarnedValue.ppt
Basic Concepts of Earned Value Management.pdf
Project monitoring lecture 1
Odoo experience 2015 earned value management
Project Management Earned Value
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Earned Value AnalysisTracking Project ProgressWh.docx
Project Cost Management
Earned Value Management chapter 8 pm2.pptx
Earned value Project Management (evpm)
CCP_SEC4_Progress and Cost Control
What Is Earned Value Analysis
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PF_EarnedValuePresentation.ppt
Project Planning and Excution chapter 4.ppt
Topic 10 - Project Performance Management.pdf
Project monitoring & Earned Value Analysis
Ad

Recently uploaded (20)

PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
PPT on Performance Review to get promotions
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
DOCX
573137875-Attendance-Management-System-original
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPTX
web development for engineering and engineering
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Digital Logic Computer Design lecture notes
PPTX
Geodesy 1.pptx...............................................
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
composite construction of structures.pdf
PPTX
Construction Project Organization Group 2.pptx
bas. eng. economics group 4 presentation 1.pptx
PPT on Performance Review to get promotions
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
573137875-Attendance-Management-System-original
OOP with Java - Java Introduction (Basics)
UNIT 4 Total Quality Management .pptx
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
web development for engineering and engineering
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Foundation to blockchain - A guide to Blockchain Tech
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Digital Logic Computer Design lecture notes
Geodesy 1.pptx...............................................
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
composite construction of structures.pdf
Construction Project Organization Group 2.pptx
Ad

Project Earned Value Management and principles

  • 1. CSE Senior Design I CSE Senior Design I Earned Value Management Earned Value Management Partially adapted from Mike O’Dell. Some slides in this presentation were originally developed by Mr. Tom Rethard. Instructor: Manfred Huber Instructor: Manfred Huber
  • 2. 4 2 Earned Value - What is it? Earned Value - What is it? Simply, it is a project monitoring and measurement system that: 1. establishes a clear relationship between planned planned accomplishments and actual actual accomplishments 2. 2. reinforces reinforces and rewards good planning good planning practices
  • 3. 4 3 Earned Value - What is it? Earned Value - What is it? Basic concepts of Earned Value Management (EVM)  Each task in a project earns value as planned planned work work is completed For example (perhaps), if you were paid on this basis, you would earn earn $$ at key milestones based on the value of what you have completed (earned value)  Earned value can be compared to actual cost and budgeted cost to determine variance and predict future performance
  • 4. 4 4 Earned Value - What is it? Earned Value - What is it?  The budgeted cost budgeted cost (e.g., dollars, person-hours, person-days, etc.) in terms of your baseline baseline plan/budget plan/budget of the work performed up to a specified point in time  Also known as Budgeted Cost of Work Performed (BCWP BCWP)  Each task in the Work Breakdown Structure (WBS) is assigned a BCWP based on its individual cost.  Project BCWP is total of BCWP for all tasks required to complete the project
  • 5. 4 5 Earned Value Components Earned Value Components  Planned Value (a.k.a. BCWS BCWS)  How much work (person-hours) you planned to have accomplished at a given point in time (this is from the WBS in your plan)  Actual Cost (a.k.a. ACWP ACWP)  How much work (person-hours) you have actually spent at a given point in time  Earned Value (a.k.a. BCWP BCWP)  The value (person-hours) in terms of your base budget of what you have accomplished at a given point in time (or, % complete X Planned Value)
  • 6. 4 6 Earned Value: Example Earned Value: Example On Day X:  PLANNED VALUE PLANNED VALUE (Budgeted cost of the work scheduled, BCWS) = 18 + 10 + 16 + 6 = 50  EARNED VALUE EARNED VALUE (Budgeted cost of the work performed, BCWP) = 18 + 8 + 14 + 0 = 40  ACTUAL COST ACTUAL COST (of the work performed , ACWP) = 55 (from your project tracking - not evident in above chart) 18 8 14 Today
  • 7. 4 7 Earned Value: Example Earned Value: Example Cost (Person-Hours) Time (Date) Planned Value Planned Value: what your plan called for sending on the tasks planned to be completed by this date. Today Earned Value Earned Value: value (cost) of what you have accomplished to date, per the base plan. Actual Cost Actual Cost: what you have actually spent to this point in time. Budgeted (Planned) Spending Budgeted (Planned) Spending Actual Spending Actual Spending Earned Value Earned Value
  • 8. 4 8 Earned Value: Example Earned Value: Example Cost (Person-Hours) Time (Date) Today Budgeted (Planned) Spending Budgeted (Planned) Spending Actual Spending Actual Spending Earned Value Earned Value Behind Behind Schedule Schedule Over Over Budget Budget
  • 9. 4 9 Variance Variance Any schedule or cost deviation schedule or cost deviation from a specific plan. Used within an organization to verify the budget and schedule for a project Frequently used as a key component of plan reviews and performance plan reviews and performance measurement measurement
  • 10. 4 10 Variance Variance Must compare scheduling and budget variance at the same time  Schedule variance Schedule variance: deviations from work planned – not a measure of changes in cost  Cost variance Cost variance: deviations from the budget – not a measure of work scheduled vs. work completed Example: applying more $$/people to a task may maintain the schedule, but it adds to cost… schedule on track… over budget on expenses (cost)
  • 11. 4 11 Performance Indices Performance Indices Cost Performance Index  CPI CPI = BCWP/ACWP Schedule Performance Index  SPI SPI = BCWP/BCWS Analysis  CPI > 1.0  exceptional performance  CPI < 1.0  poor performance  Similar for SPI
  • 12. 4 14 Earned Value & Variance: Example Earned Value & Variance: Example On Day X:  PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50  EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40  ACTUAL COST (ACWP) = 55 (from your project tracking) Therefore:  Schedule Variance Schedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind schedule)  Schedule Performance Index Schedule Performance Index = 40 / 50 = 0.8, or 80% of plan (a B-, at best)  Cost Variance Cost Variance = BCWP - ACWP = 40 - 55 = -15  Cost Performance Index Cost Performance Index = 40/55 = .73, or you’re getting an 73¢ return on every $1.00 (or, person-hour) spent on this project 18 8 14
  • 13. 4 15 Primary Measurement Methods Primary Measurement Methods Measurable Measurable efforts  Discrete increments of work Discrete increments of work with definable schedule and tangible results (i.e., real tasks with a deliverable) Level of effort Level of effort  Work that is not not discernable in discrete discrete, measurable tasks (e.g., project management, training)
  • 14. 4 16 Determining % Complete – When? Determining % Complete – When?  Allocate based on time spent – but what if you spend more time than allocated?  Allocate 50% at start of task, 50% at end  But only for small, discrete tasks small, discrete tasks  Allocate 100% at start of task  Allocate 100% at end of task  Best solution if you keep tasks very small keep tasks very small  Allocate value at Critical Milestones  Good solution when using with contract work  Others? Our approach
  • 15. 4 17 Another Example Project Another Example Project  Plans to spend $100K in each of first 4 weeks (baseline budget, per documented plan per documented plan)  Actuals, at end of week 4 show: $325K spent  BCWS = $400K ($100K x 4)  ACWP = $325K  What conclusions can you draw?  Under budget?  Is project on schedule?
  • 16. 4 18 Another Example Project Another Example Project Suppose BCWP is $300K  How is this determined? What conclusions now?  SV = BCWP – BCWS  SV = $300k - $400K = -$100K Behind schedule Behind schedule, but what does the $100K in variance really mean?  CV = BCWP – ACWP = $300K - $325K Over budget Over budget by $25K
  • 17. 4 19 Earned Value Management Earned Value Management  How can you use this information?  Careful analysis of variance and trends  Resetting schedule or budget, when appropriate  Variance Analysis Questions  What is the problem causing the variance?  What is the impact on time, cost and performance?  What is the impact on other efforts, if any?  What corrective action is planned or under way?  What are the expected results of the corrective action?
  • 18. 4 20 Earned Value Management Earned Value Management  Extraordinary variance or alarming trends may be cause for reset or cancellation of reset or cancellation of a project, but where do you draw the line?  How much variance to allow depends on a number of factors:  Life-cycle phase  Length of life-cycle phase  Length of project  Type of estimate  Accuracy of estimate
  • 22. 4 24 Closing Thoughts: Management Closing Thoughts: Management Reserve Reserve The padding always added to a project for unexpected costs that are within project scope  Not an allowance for changes to scope  Not part of the cost estimate Added by upper management, not the project manager.
  • 23. 4 25 Closing Thoughts: Government Closing Thoughts: Government Requirements Requirements  U.S. government contract cost tracking often must include:  BCWS  BCWP  ACWP  Estimated cost at completion  Budgeted cost at completion  Cost and schedule variances with explanations  Traceability
  • 24. 4 26 Summary Summary Cost, in the form of Earned Value or BCWP, can be used to analyze progress analyze progress of a project Using Earned Value data to make critical project decisions must be based on careful careful analysis analysis of data, variances and trends