SlideShare a Scribd company logo
1
What Is It ?
Why Do I Need It ?
How Do I Do It?
Earned Value Analysis
2
Today’s Situation
Need for accurate and consistent status
information
Numerous complex (and interrelated) projects
 Projects with many WBS activities
 Virtual offices
 Diverse and integrated manufacturing processes
3
There’s Room For Improvement
70% of projects are:
•Over budget
•Behind schedule
52% of all projects finish at
189% of their initial budget
And some, after huge investments
of time and money, are simply never
completed
Source:The Standish Group
4
How to answer the question:
“Have we done what we said we’d do?”
% complete estimating
% of Budget spent
% of work done
% of time elapsed
 subjective,
incomplete
 draws false
conclusions
5
Enter Earned Value Analysis
“Earned Value Analysis” is:
• an industry standard way to:
• measure a project’s progress,
• forecast its completion date and final cost, and
• provide schedule and budget variances along the
way.
By integrating three measurements, it provides
consistent, numerical indicators with which you can
evaluate and compare projects.
6
What’s More Important?
Knowing where you are
on schedule?
Knowing where you are
on budget?
Knowing where you are
on work accomplished?
7
EVA Integrates All Three
It compares the PLANNED amount of work
with what has actually been COMPLETED, to
determine if COST , SCHEDULE, and WORK
ACCOMPLISHED are progressing as planned.
Work is “Earned” or credited as it is
completed.
8
Earned Value is needed because...
Different measures of progress for
different types of tasks
Need to “roll up” progress of many
tasks into an overall project status
Need for a uniform unit of measure
(dollars or work-hours).
9
Earned Value is needed because...
Provides an “Early Warning” signal for prompt
corrective action.
 Bad news does not age well.
 Still time to recover
 Timely request for additional funds
10
And One More Reason
Why You Need EVA
?
11
Because It May Be Required!
These Set the Stage:
GPRA; 1993
FASA, Title V; 1994
Clinger-Cohen Act; 1996
And Then Along Came OMB! (Circular A-11, Part 7)
"Agencies must use a performance based acquisition
management system, based on ANSI/EIA Standard
748, to measure achievement of the cost, schedule,
and performance goals."
12
OK, So What Is This Stuff?
13
So, Is This Stuff New ?
It’s been around since the sixties.
“Cost/Schedule Control Systems Criteria”
(C/SCSC)
14
Examples of Informal Earned Value Analysis
It’s done informally without realizing it.
•30% time used,
•30% $$ spent
•So, if 30% of the work is done, I must be OK ??
•Shop floor estimates
•Cost comparisons
Budget vs. Actual
15
How’s This Project Doing?
0
20000
40000
60000
80000
100000
120000
Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03
Projected
Actual
16
Let’s Take A Look Under The Hood
17
But First! - We Must Get Organized
EVA works best when work is ‘compartmentalized’.
Compartmentalization is best achieved with a well-
planned Work Breakdown Structure.
So, how do I create a WBS for a really complex
project?
18
Proper WBS Design
One WBS per program
• Deliverable-oriented
• Work not in the WBS is out-of-scope
• Each descending level represents more detail
Full (and accurate) definition is key
• Defined deliverable(s)
• Timeframe for delivery of product
• Total cost (direct and indirect) to deliver product
Let’s Look at an example:
19
A Sample Work Breakdown Structure
Serve Pizzas to Customers
Provide the Place Cook the Food Serve Customers (Others)
Cook the Sauce
Make the Dough Build the Pizza
20
WBS Units are “Work Packages”
Lowest level WBS elements
Have an accompanying narrative
Have three measurable components
• Scope of work to be accomplished
• Total (direct and indirect) cost
• Timeframe for completion
21
Control Account Plans
A CAP is essentially a Work Package with some added
features:
Assignment of responsibility
• Organization
• Individual
Division (if necessary) into lower-level Work Packages.
Metrics for measuring EV performance
• Milestones
• % complete
• Other
The sum of the CAPs constitutes the Performance
Measurement Baseline
22
Some New Terms
PV – Planned Value
AC - Actual Cost
EV – Earned Value
23
Earned Value Definitions
PV: “Planned Value”
Planned cost of the total amount of work scheduled
to be performed by the milestone date.
24
PV – Planned Value or Budgeted Cost of
Work Scheduled
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWS
25
Earned Value Definitions (cont.)
AC: “Actual Cost of Work Performed”
Cost incurred to accomplish the work that has been
done to date.
26
ACWP - Actual Cost of Work Performed
49000
56000
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWP
ACWP
27
Earned Value Definitions (cont.)
EV: Earned value or Budgeted Cost of Work
Performed
The planned (not actual) cost to complete the work
that has been done.
28
EV- Earned Value or Budgeted Cost of Work
Performed
49000
55000
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWP
BCWS
29
55000
49000
56000
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWS
BCWP
ACWP
The Whole Story
30
Some Derived Metrics
SV: Schedule Variance (EV-PV)
 A comparison of amount of work performed during a
given period of time to what was scheduled to be
performed.
 A negative variance means the project is behind
schedule
CV: Cost Variance (EV-AC)
 A comparison of the budgeted cost of work
performed with actual cost.
 A negative variance means the project is over
budget.
31
Schedule Variance & Cost Variance
Schedule Variance = EV-PV
$49,000
- 55,000
SV = - $ 6,000
Cost Variance = EV-AC
$49,000
56,000
CV = - $7,000
32
SPI: Schedule Performance Index
SPI=EV/PV
 If SPI<1 means project is behind schedule
CPI: Cost Performance Index
CPI= EV/AC
If CPI<1 means project is over budget
CSI: Cost Schedule Index (CSI=CPI x SPI)
The further CSI is from 1.0, the less likely project
recovery becomes.
Some More Derived Metrics
33
Performance Metrics
SPI: EV/PV
49,000/55,000 = 0.891
CPI: EV/AC
49,000/56000 = 0.875
CSI: SPI x CPI
.891 x .875 = 0.780
34
Making Projections
Once a project is 10% complete, the
overrun at completion will not be less
than the current overrun.
Once a project is 20% complete,
the CPI does not vary from its current
value by more
than 10%.
The CPI and SPI are statistically accurate indicators of
final cost results.
Source: Defense Acquisition University
35
102000
90882
103865
0
20000
40000
60000
80000
100000
120000 Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Oct-03
Nov-03
Dec-03
BCWS
BCWP
ACWP
Making Projections
Today
36
102000
116,571
0
20000
40000
60000
80000
100000
120000
140000
Jan-03
M
ar-03
M
ay-03
Jul-03
Sep-03
Nov-03
Jan-04
M
ar-04
BCWS
BCWP
ACWP
Estimate to Complete
Today
37
A New Criteria
Activities “earn value” as they are completed.
The value earned is the WBS budgeted cost of the
activity completed to date.
38
Value of Earned Value
Schedule Status Reporting
Cost Status Reporting
Forecasting
39
But How Do I Do All This Stuff ?
With an Earned Value Management System
40
Requirements of Earned Value
Proper WBS Design
Baseline Budget Control Accounts
Baseline Schedule
Work measurement by Control Account
 work-hours, dollars, units, etc.
Good Project Management Practices
41
Shortcomings of Earned Value
Quantifying/measuring work progress
can be difficult.
Time required for data measurement,
input, and manipulation can be
considerable.
42
Summary
EVA & EVMS will help reduce guesswork in:
 Measuring performance
 forecasting
Need to get beyond misleading measures of
progress.
Reasons to use EVA and EVMS:
 Good project management practice
 OMB requirement
Incorporate into contracts
43
Earned Value Resources
http://www.pmi.org/
http://www.acq.osd.mil/pm/
ANSI/EIA 748 is available from:
Global Engineering Documents
800-854-7179
44
Earned Value Analysis
Questions/Discussion

More Related Content

PPT
EARNED VALUE MANAGEMENT ANALYS 1.ppt
PPT
EarnedValue.ppt
PPT
EVA - Metrics.ppt
PPT
PM Session 7
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PPTX
Project monitoring & Earned Value Analysis
PDF
Program Management 2.0: Work Breakdown Structure
PDF
Project monitoring and controlling with earned value management
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EarnedValue.ppt
EVA - Metrics.ppt
PM Session 7
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
Project monitoring & Earned Value Analysis
Program Management 2.0: Work Breakdown Structure
Project monitoring and controlling with earned value management

Similar to PF_EarnedValuePresentation.ppt (20)

PDF
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
PDF
Back to basics - Earned Value Management for beginners webinar
PPTX
Earned Value Analysis in construction projects
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PDF
Earned value analysis
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPTX
projectcostcontrol-130625012804-phpapp02 (1)
PPTX
Project cost & control
PPTX
Earned Value Management for project managers
PPTX
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PPT
IT Park - Earned Value ppt.ppt
PPTX
Earn Value Analysis in Economic Analysis.pptx
PPTX
Project monitoring lecture 1
PDF
An introduction to project accounting
PPTX
Project monitoring and monitoring tools
PDF
Basic Concepts of Earned Value Management.pdf
PPT
Ch 9 project monitoring &amp; control updated
PDF
Pmp cost chapter 7
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Back to basics - Earned Value Management for beginners webinar
Earned Value Analysis in construction projects
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Earned value analysis
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
projectcostcontrol-130625012804-phpapp02 (1)
Project cost & control
Earned Value Management for project managers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
IT Park - Earned Value ppt.ppt
Earn Value Analysis in Economic Analysis.pptx
Project monitoring lecture 1
An introduction to project accounting
Project monitoring and monitoring tools
Basic Concepts of Earned Value Management.pdf
Ch 9 project monitoring &amp; control updated
Pmp cost chapter 7

Recently uploaded (20)

PDF
how_to_earn_50k_monthly_investment_guide.pdf
PDF
ABriefOverviewComparisonUCP600_ISP8_URDG_758.pdf
PDF
Predicting Customer Bankruptcy Using Machine Learning Algorithm research pape...
PPTX
Globalization-of-Religion. Contemporary World
PPTX
4.5.1 Financial Governance_Appropriation & Finance.pptx
PDF
Understanding University Research Expenditures (1)_compressed.pdf
PPTX
Introduction to Managemeng Chapter 1..pptx
PPTX
Unilever_Financial_Analysis_Presentation.pptx
PDF
Dr Tran Quoc Bao the first Vietnamese speaker at GITEX DigiHealth Conference ...
PPTX
Introduction to Customs (June 2025) v1.pptx
PDF
way to join Real illuminati agent 0782561496,0756664682
PPTX
Basic Concepts of Economics.pvhjkl;vbjkl;ptx
PPT
E commerce busin and some important issues
PPTX
Session 3. Time Value of Money.pptx_finance
PDF
ECONOMICS AND ENTREPRENEURS LESSONSS AND
PPTX
Session 11-13. Working Capital Management and Cash Budget.pptx
PDF
Circular Flow of Income by Dr. S. Malini
PDF
Bladex Earnings Call Presentation 2Q2025
PDF
illuminati Uganda brotherhood agent in Kampala call 0756664682,0782561496
PDF
ssrn-3708.kefbkjbeakjfiuheioufh ioehoih134.pdf
how_to_earn_50k_monthly_investment_guide.pdf
ABriefOverviewComparisonUCP600_ISP8_URDG_758.pdf
Predicting Customer Bankruptcy Using Machine Learning Algorithm research pape...
Globalization-of-Religion. Contemporary World
4.5.1 Financial Governance_Appropriation & Finance.pptx
Understanding University Research Expenditures (1)_compressed.pdf
Introduction to Managemeng Chapter 1..pptx
Unilever_Financial_Analysis_Presentation.pptx
Dr Tran Quoc Bao the first Vietnamese speaker at GITEX DigiHealth Conference ...
Introduction to Customs (June 2025) v1.pptx
way to join Real illuminati agent 0782561496,0756664682
Basic Concepts of Economics.pvhjkl;vbjkl;ptx
E commerce busin and some important issues
Session 3. Time Value of Money.pptx_finance
ECONOMICS AND ENTREPRENEURS LESSONSS AND
Session 11-13. Working Capital Management and Cash Budget.pptx
Circular Flow of Income by Dr. S. Malini
Bladex Earnings Call Presentation 2Q2025
illuminati Uganda brotherhood agent in Kampala call 0756664682,0782561496
ssrn-3708.kefbkjbeakjfiuheioufh ioehoih134.pdf

PF_EarnedValuePresentation.ppt

  • 1. 1 What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis
  • 2. 2 Today’s Situation Need for accurate and consistent status information Numerous complex (and interrelated) projects  Projects with many WBS activities  Virtual offices  Diverse and integrated manufacturing processes
  • 3. 3 There’s Room For Improvement 70% of projects are: •Over budget •Behind schedule 52% of all projects finish at 189% of their initial budget And some, after huge investments of time and money, are simply never completed Source:The Standish Group
  • 4. 4 How to answer the question: “Have we done what we said we’d do?” % complete estimating % of Budget spent % of work done % of time elapsed  subjective, incomplete  draws false conclusions
  • 5. 5 Enter Earned Value Analysis “Earned Value Analysis” is: • an industry standard way to: • measure a project’s progress, • forecast its completion date and final cost, and • provide schedule and budget variances along the way. By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects.
  • 6. 6 What’s More Important? Knowing where you are on schedule? Knowing where you are on budget? Knowing where you are on work accomplished?
  • 7. 7 EVA Integrates All Three It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned. Work is “Earned” or credited as it is completed.
  • 8. 8 Earned Value is needed because... Different measures of progress for different types of tasks Need to “roll up” progress of many tasks into an overall project status Need for a uniform unit of measure (dollars or work-hours).
  • 9. 9 Earned Value is needed because... Provides an “Early Warning” signal for prompt corrective action.  Bad news does not age well.  Still time to recover  Timely request for additional funds
  • 10. 10 And One More Reason Why You Need EVA ?
  • 11. 11 Because It May Be Required! These Set the Stage: GPRA; 1993 FASA, Title V; 1994 Clinger-Cohen Act; 1996 And Then Along Came OMB! (Circular A-11, Part 7) "Agencies must use a performance based acquisition management system, based on ANSI/EIA Standard 748, to measure achievement of the cost, schedule, and performance goals."
  • 12. 12 OK, So What Is This Stuff?
  • 13. 13 So, Is This Stuff New ? It’s been around since the sixties. “Cost/Schedule Control Systems Criteria” (C/SCSC)
  • 14. 14 Examples of Informal Earned Value Analysis It’s done informally without realizing it. •30% time used, •30% $$ spent •So, if 30% of the work is done, I must be OK ?? •Shop floor estimates •Cost comparisons Budget vs. Actual
  • 15. 15 How’s This Project Doing? 0 20000 40000 60000 80000 100000 120000 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 Projected Actual
  • 16. 16 Let’s Take A Look Under The Hood
  • 17. 17 But First! - We Must Get Organized EVA works best when work is ‘compartmentalized’. Compartmentalization is best achieved with a well- planned Work Breakdown Structure. So, how do I create a WBS for a really complex project?
  • 18. 18 Proper WBS Design One WBS per program • Deliverable-oriented • Work not in the WBS is out-of-scope • Each descending level represents more detail Full (and accurate) definition is key • Defined deliverable(s) • Timeframe for delivery of product • Total cost (direct and indirect) to deliver product Let’s Look at an example:
  • 19. 19 A Sample Work Breakdown Structure Serve Pizzas to Customers Provide the Place Cook the Food Serve Customers (Others) Cook the Sauce Make the Dough Build the Pizza
  • 20. 20 WBS Units are “Work Packages” Lowest level WBS elements Have an accompanying narrative Have three measurable components • Scope of work to be accomplished • Total (direct and indirect) cost • Timeframe for completion
  • 21. 21 Control Account Plans A CAP is essentially a Work Package with some added features: Assignment of responsibility • Organization • Individual Division (if necessary) into lower-level Work Packages. Metrics for measuring EV performance • Milestones • % complete • Other The sum of the CAPs constitutes the Performance Measurement Baseline
  • 22. 22 Some New Terms PV – Planned Value AC - Actual Cost EV – Earned Value
  • 23. 23 Earned Value Definitions PV: “Planned Value” Planned cost of the total amount of work scheduled to be performed by the milestone date.
  • 24. 24 PV – Planned Value or Budgeted Cost of Work Scheduled 0 20000 40000 60000 80000 100000 120000 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 BCWS
  • 25. 25 Earned Value Definitions (cont.) AC: “Actual Cost of Work Performed” Cost incurred to accomplish the work that has been done to date.
  • 26. 26 ACWP - Actual Cost of Work Performed 49000 56000 0 20000 40000 60000 80000 100000 120000 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 BCWP ACWP
  • 27. 27 Earned Value Definitions (cont.) EV: Earned value or Budgeted Cost of Work Performed The planned (not actual) cost to complete the work that has been done.
  • 28. 28 EV- Earned Value or Budgeted Cost of Work Performed 49000 55000 0 20000 40000 60000 80000 100000 120000 Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03 BCWP BCWS
  • 30. 30 Some Derived Metrics SV: Schedule Variance (EV-PV)  A comparison of amount of work performed during a given period of time to what was scheduled to be performed.  A negative variance means the project is behind schedule CV: Cost Variance (EV-AC)  A comparison of the budgeted cost of work performed with actual cost.  A negative variance means the project is over budget.
  • 31. 31 Schedule Variance & Cost Variance Schedule Variance = EV-PV $49,000 - 55,000 SV = - $ 6,000 Cost Variance = EV-AC $49,000 56,000 CV = - $7,000
  • 32. 32 SPI: Schedule Performance Index SPI=EV/PV  If SPI<1 means project is behind schedule CPI: Cost Performance Index CPI= EV/AC If CPI<1 means project is over budget CSI: Cost Schedule Index (CSI=CPI x SPI) The further CSI is from 1.0, the less likely project recovery becomes. Some More Derived Metrics
  • 33. 33 Performance Metrics SPI: EV/PV 49,000/55,000 = 0.891 CPI: EV/AC 49,000/56000 = 0.875 CSI: SPI x CPI .891 x .875 = 0.780
  • 34. 34 Making Projections Once a project is 10% complete, the overrun at completion will not be less than the current overrun. Once a project is 20% complete, the CPI does not vary from its current value by more than 10%. The CPI and SPI are statistically accurate indicators of final cost results. Source: Defense Acquisition University
  • 37. 37 A New Criteria Activities “earn value” as they are completed. The value earned is the WBS budgeted cost of the activity completed to date.
  • 38. 38 Value of Earned Value Schedule Status Reporting Cost Status Reporting Forecasting
  • 39. 39 But How Do I Do All This Stuff ? With an Earned Value Management System
  • 40. 40 Requirements of Earned Value Proper WBS Design Baseline Budget Control Accounts Baseline Schedule Work measurement by Control Account  work-hours, dollars, units, etc. Good Project Management Practices
  • 41. 41 Shortcomings of Earned Value Quantifying/measuring work progress can be difficult. Time required for data measurement, input, and manipulation can be considerable.
  • 42. 42 Summary EVA & EVMS will help reduce guesswork in:  Measuring performance  forecasting Need to get beyond misleading measures of progress. Reasons to use EVA and EVMS:  Good project management practice  OMB requirement Incorporate into contracts