SlideShare a Scribd company logo
1
BASICS OF
EARNED VALUE
MANAGEMENT
2
Why use Earned Value
Management Systems?
“The Bottom Line”
• EVM can focus program management attention on
critical issues and risks during the “project” life
cycle
• How are you doing, and how do you know how you
are doing?
– Early problem identification
• Completion Estimates
– How far along are you? (64%, 50%, >40%)
– What is your productivity/efficiency?
– Work remaining
3
Five Basic Elements
BCWS Budgeted Cost of Work Scheduled
BCWP Budgeted Cost of Work Performed
ACWP Actual Cost of Work Performed
4
5 Basic Performance Data
Questions & Answers
QUESTION ANSWER ACRONYM
How much work should Budgeted Cost for BCWS
be done? Work Scheduled
How much work is done? Budgeted Cost for BCWP
Work Performed
How much did the is done Actual Cost of ACWP
work cost? Work Performed
5
What do we measure progress against?
and Why?
• Performance measurement baseline
– Budget that is spread over . . .
– Time, to accomplish the scope of
– Work, against which progress can be measured
• Earned Value is key concept
– how much progress did I make against my original
plan?
– expressed in dollars or hours
– Why? – early warning
$
time
baseline
earned value
6
Why do we need
Early Warning?
Small course corrections are
easier when made early…
… If you wait until you reach
the Iceberg, its too late!!!
7
Work Budgeted and Earned
• The value of the budgeted work is called:
Budgeted Cost of Work Scheduled
(BCWS)
• The value of work earned is called:
Budgeted Cost of Work Performed
(BCWP)
– BCWP is also called Earned Value (EV)
Budgeted Cost of Work Scheduled
(BCWS)
Total Budget = $5,000
to be spent over 5 months
I plan to lay 1 section
of track each month at an
estimated cost of $1,000.
BCWS each month = $1,000
Total BCWS = $5,000
Month 1
BCWS = $1,000
Month 4
BCWS = $1,000
Month 3
BCWS = $1,000
Month 5
BCWS = $1,000
Month 2
BCWS = $1,000
sum of all BCWS = performance baseline
9
Budgeted Cost of Work Performed
(BCWP)
aka. Earned Value
We’re at the end of
February, Track 1 is
complete and track 2 is ½
done.
BCWS = $1,000
Track 1
Track 2
BCWS = $1,000
50% done
Value of work
performed = $1,500
10
Schedule Variance
BC WS
BC WP
of the work I scheduled to have done,
how much did I budget for it to cost?
of the work I actually performed,
how much did I budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
BUDGET
BASED
example: SV = BCWP - BCWS = $1,500 - $2,000
SV= -$500 (negative = behind schedule)
11
Schedule Variance
$
BCWS
“the baseline”
BCWP
“earned value”
TIME
5,000
sv
12
Actual Cost of Work Performed
(ACWP)
Track 1 Cost = $1,500!
Track 2 Cost = $750 cost to
date
Total Cost to Date = $2,250
13
Cost Variance
BC WP
AC WP
of the work I actually performed,
how much did I budget for it to cost?
of the work I actually performed,
how much did it actually cost?
COST VARIANCE is the difference between budgeted cost
and actual cost
formula: CV $ = BCWP - ACWP
PERFORMANCE
BASED
example: CV = BCWP - ACWP = $1,500 - $2,250
CV= -$750 (negative = cost overrun)
14
Cost Variance
$
TIME
BCWP
“earned value”
ACWP
“actual cost”
5,000
cv
15
Variance Summary
• The difference between the BCWP and the
ACWP is called a cost variance
• The difference between the BCWP and
BCWS is called schedule variance and is
provided in terms of dollars
16
Trend Analysis
Cost Performance Index (CPI) measure of cost efficiency
CPI = Value of Work Completed (BCWP)
Cost of Work Completed (ACWP)
Schedule Performance Index (SPI) measure of schedule efficiency
SPI = Value of Work Completed (BCWP)
Value of Work Planned (BCWS)
Closer to “1” the better
Less than 1 = overrun (CPI); behind schedule (SPI)
Greater than 1 = underrun (CPI); ahead of schedule (SPI)
17
• DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET?
COST PERFORMANCE INDEX:
CPI = cost efficiency for work performed to date
(The value of work accomplished for each dollar spent)
SCHEDULE PERFORMANCE INDEX:
SPI = schedule efficiency with which work has been accomplished
(The rate at which work is being accomplished)
Performance Efficiencies
WORK
= ACCOMPLISHED
ACTUALS
WORK
= ACCOMPLISHED
WORK
SCHEDULED
WORK
BCWP ACCOMPLISHED $1500
= BCWS = WORK = $2000 = .75
SCHEDULED
WORK
BCWP ACCOMPLISHED $1500
= ACWP = ACTUAL = $2250 = .67
COST
18
EXERCISES
• Attendees – Go to your Exercise
Packet
19
Solution
Cost Variance = -10
Schedule Variance = + 20
CPI = .97
SPI = 1.07
• How would you describe this project?
Over budget, ahead of schedule

More Related Content

PPT
Earned Value Analysis
PPT
Earned value
PPT
Project Earned Value Management and principles
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
DOCX
What Is Earned Value Analysis
PDF
Project monitoring and controlling with earned value management
PPTX
Earned Value Analysis in construction projects
PDF
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Analysis
Earned value
Project Earned Value Management and principles
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
What Is Earned Value Analysis
Project monitoring and controlling with earned value management
Earned Value Analysis in construction projects
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation

Similar to Basics of EVM.pdf (20)

PDF
The simple problem of schedule performance indices
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPT
EVA - Metrics.ppt
PPTX
Earnvalue analysis in Software engineering
PPT
Project Management Earned Value
PPT
EARNED VALUE MANAGEMENT ANALYS 1.ppt
PDF
A gentle introduction to earned value management systems (neutral)
PDF
A gentle introduction to earned value management systems (neutral)
PDF
EVM of Project Management...
PPT
IT Park - Earned Value ppt.ppt
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
PPTX
Project monitoring lecture 1
PPT
Earned value Project Management (evpm)
PPT
EarnedValue.ppt
PPTX
Earn Value Analysis in Economic Analysis.pptx
PPTX
Earned value management (EVM)
The simple problem of schedule performance indices
Earned Value AnalysisTracking Project ProgressWh.docx
EVA - Metrics.ppt
Earnvalue analysis in Software engineering
Project Management Earned Value
EARNED VALUE MANAGEMENT ANALYS 1.ppt
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
EVM of Project Management...
IT Park - Earned Value ppt.ppt
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
Project monitoring lecture 1
Earned value Project Management (evpm)
EarnedValue.ppt
Earn Value Analysis in Economic Analysis.pptx
Earned value management (EVM)
Ad

Recently uploaded (20)

PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Welding lecture in detail for understanding
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
additive manufacturing of ss316l using mig welding
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Sustainable Sites - Green Building Construction
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
web development for engineering and engineering
PPT
Mechanical Engineering MATERIALS Selection
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
Lecture Notes Electrical Wiring System Components
Automation-in-Manufacturing-Chapter-Introduction.pdf
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Welding lecture in detail for understanding
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
additive manufacturing of ss316l using mig welding
Model Code of Practice - Construction Work - 21102022 .pdf
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
bas. eng. economics group 4 presentation 1.pptx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Embodied AI: Ushering in the Next Era of Intelligent Systems
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Sustainable Sites - Green Building Construction
UNIT-1 - COAL BASED THERMAL POWER PLANTS
web development for engineering and engineering
Mechanical Engineering MATERIALS Selection
CH1 Production IntroductoryConcepts.pptx
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Lecture Notes Electrical Wiring System Components
Ad

Basics of EVM.pdf

  • 2. 2 Why use Earned Value Management Systems? “The Bottom Line” • EVM can focus program management attention on critical issues and risks during the “project” life cycle • How are you doing, and how do you know how you are doing? – Early problem identification • Completion Estimates – How far along are you? (64%, 50%, >40%) – What is your productivity/efficiency? – Work remaining
  • 3. 3 Five Basic Elements BCWS Budgeted Cost of Work Scheduled BCWP Budgeted Cost of Work Performed ACWP Actual Cost of Work Performed
  • 4. 4 5 Basic Performance Data Questions & Answers QUESTION ANSWER ACRONYM How much work should Budgeted Cost for BCWS be done? Work Scheduled How much work is done? Budgeted Cost for BCWP Work Performed How much did the is done Actual Cost of ACWP work cost? Work Performed
  • 5. 5 What do we measure progress against? and Why? • Performance measurement baseline – Budget that is spread over . . . – Time, to accomplish the scope of – Work, against which progress can be measured • Earned Value is key concept – how much progress did I make against my original plan? – expressed in dollars or hours – Why? – early warning $ time baseline earned value
  • 6. 6 Why do we need Early Warning? Small course corrections are easier when made early… … If you wait until you reach the Iceberg, its too late!!!
  • 7. 7 Work Budgeted and Earned • The value of the budgeted work is called: Budgeted Cost of Work Scheduled (BCWS) • The value of work earned is called: Budgeted Cost of Work Performed (BCWP) – BCWP is also called Earned Value (EV)
  • 8. Budgeted Cost of Work Scheduled (BCWS) Total Budget = $5,000 to be spent over 5 months I plan to lay 1 section of track each month at an estimated cost of $1,000. BCWS each month = $1,000 Total BCWS = $5,000 Month 1 BCWS = $1,000 Month 4 BCWS = $1,000 Month 3 BCWS = $1,000 Month 5 BCWS = $1,000 Month 2 BCWS = $1,000 sum of all BCWS = performance baseline
  • 9. 9 Budgeted Cost of Work Performed (BCWP) aka. Earned Value We’re at the end of February, Track 1 is complete and track 2 is ½ done. BCWS = $1,000 Track 1 Track 2 BCWS = $1,000 50% done Value of work performed = $1,500
  • 10. 10 Schedule Variance BC WS BC WP of the work I scheduled to have done, how much did I budget for it to cost? of the work I actually performed, how much did I budget for it to cost? SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars) formula: SV $ = BCWP - BCWS BUDGET BASED example: SV = BCWP - BCWS = $1,500 - $2,000 SV= -$500 (negative = behind schedule)
  • 12. 12 Actual Cost of Work Performed (ACWP) Track 1 Cost = $1,500! Track 2 Cost = $750 cost to date Total Cost to Date = $2,250
  • 13. 13 Cost Variance BC WP AC WP of the work I actually performed, how much did I budget for it to cost? of the work I actually performed, how much did it actually cost? COST VARIANCE is the difference between budgeted cost and actual cost formula: CV $ = BCWP - ACWP PERFORMANCE BASED example: CV = BCWP - ACWP = $1,500 - $2,250 CV= -$750 (negative = cost overrun)
  • 15. 15 Variance Summary • The difference between the BCWP and the ACWP is called a cost variance • The difference between the BCWP and BCWS is called schedule variance and is provided in terms of dollars
  • 16. 16 Trend Analysis Cost Performance Index (CPI) measure of cost efficiency CPI = Value of Work Completed (BCWP) Cost of Work Completed (ACWP) Schedule Performance Index (SPI) measure of schedule efficiency SPI = Value of Work Completed (BCWP) Value of Work Planned (BCWS) Closer to “1” the better Less than 1 = overrun (CPI); behind schedule (SPI) Greater than 1 = underrun (CPI); ahead of schedule (SPI)
  • 17. 17 • DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET? COST PERFORMANCE INDEX: CPI = cost efficiency for work performed to date (The value of work accomplished for each dollar spent) SCHEDULE PERFORMANCE INDEX: SPI = schedule efficiency with which work has been accomplished (The rate at which work is being accomplished) Performance Efficiencies WORK = ACCOMPLISHED ACTUALS WORK = ACCOMPLISHED WORK SCHEDULED WORK BCWP ACCOMPLISHED $1500 = BCWS = WORK = $2000 = .75 SCHEDULED WORK BCWP ACCOMPLISHED $1500 = ACWP = ACTUAL = $2250 = .67 COST
  • 18. 18 EXERCISES • Attendees – Go to your Exercise Packet
  • 19. 19 Solution Cost Variance = -10 Schedule Variance = + 20 CPI = .97 SPI = 1.07 • How would you describe this project? Over budget, ahead of schedule