Copyright © 2009, Niwot Ridge, Consulting LLC 1/74
2/74
3/74
4/74
5/74
6/74
So much for our strategy of
winning through technical
dominance
7/74
Product Tree
SOW
IPTs
IMP
IMS
BOEs
CWBS
8/74
Each element of the PMB is supportive of the others
The integrated whole is the basis of a credible PMB
Attribute Beneficial Outcome from this Attribute
Maturity Flows through
Program Events
§ Performance measurement is in units of increasing
maturity of the Technical Performance Measures
§ Each event is a mini authorization to proceed
Single outcome for each
work package (AC)
§ Measure Physical Percent Complete at the WP level
§ Use 0/100 for tasks for the vast majority of work
Technical Performance
Measures are explicitly
visible in the IMS
§ Connect Cost, Schedule, and Technical Performance
§ EV does not provide a means of adjust for “off TPM,” but
make your own adjustments to the risk numbers for now
Risk retirement explicitly
visible in the IMS
§ Risk retirement is embedded in the IMS
§ Risk mitigation means waiting until the risk happens
IMS flows vertically 1st
and horizontally 2nd
§ All work supports the assessment of maturity
§ Isolate tasks dependencies within a Work Package
No Event linkage except
for long lead items
§ 0/100 requires not partial completion
Decoupled dependences
improves risk
responsiveness
§ 1st round IMS defines a free flowing process
§ Maintaining this decoupling is key to a “dynamic” IMS
that can respond to the natural changes in the program
9/74
10/74
Risk Management
Requirements
Contractor Work
Breakdown Structure
(CWBS)
CWBS Dictionary / SOW
Integrated Master Plan
(IMP)
Integrated Master Schedule
(IMS)
Earned Value Management
System
Self Assessment / Award Fee
Determinations / CPAR’s
Technical Performance
Measures (TPM)
Process Metrics
ü Specifications
ü Work Statements
ü Tailored to and outlines entire program and products
ü Provides a single numbering system for the program
ü States all deliverables and their components
ü Follows IPT and CWBS structure
ü Descriptions of work traceable to the IMS elements
ü Event–driven Plan provides
roadmap of processes for program
ü Event–driven Schedule expands IMP
into Work Packages
ü Provides details and timing
ü Builds in risk mitigation activities
ü Connects measures of progress with
measures of increasing maturity
ü Connects System
Performance with
Continuous
Technical
Improvements
ü Connects Cost
Performance
with the IMS
Performance
ü Determined by program execution
11/74
Program
Events
Statement of
Work
CWBS
Significant
Accomplishments
Accomplishment
Criteria
CDRLs and
Deliverables
Tasks Contained
in Work Packages
Measures the progress to plan using Physical & Complete at the Accomplishment Criteria
(AC) and CWBS level
Defines
Aligned Aligned
Aligned
Aligned
Aligned
Completed SA’s are
entry criteria for
Program Events
Completed Work
Packages are exit
criteria for Tasks
Describes increasing
product maturity as 0/100 or
EVMS SD guidance
Documents the product
maturity that is aligned with
SOW and CWBS
Work necessary to
mature products
grouped by CWBS
Work structure
aligned to
SOW
12/74
13/74
14/74
DoD Guide DAG SEMP CWBS
IMP
IMS ISE
Technical Reviews
Event Timing of Technical Reviews X X X X X
Success criteria Technical Reviews X X X X X
Include entry and exit criteria for Technical Reviews
in IMP/IMS X X
Assess Technical Maturity in Technical Reviews X X X X
Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X
Integrate CWBS with: Requirements specification,
Statement of Work, and IMP/IMS/EVMS X X X
Link risk management and mitigation plans with
technical reviews, TPM, EVMS, and IMS X
Integrated Reviews
Include Technical Baseline Review (TBR) in IMS; X
Integrated Baseline Review: plans for event based
technical reviews, including entry and exit criteria
Correlation of TPM’s, IMP. IMS, and EVMS
X
15/74
16/74
17/74
18/74
19/74
20/74
Only put these on your bookshelf after you’ve read them
21/74
IMS
IMP
Describes the
strategy for
successful
program
delivery
Supplemental Schedules in CAM Notebook
Tasks Contained in Work Packages
Accomplishment
Criteria
Significant
Accomplishments
Program
Events
Integrated Master Plan (IMP)
§ Identifies program events, significant accomplishments, and
accomplishment criteria. System level, controlled document.
Integrated Master Schedule (IMS)
§ Logic network schedule of program planned activities
keyed to the imp’s accomplishment criteria
Supplemental Schedule
§ Created (as needed) to provide lower
levels of detail data within CAM notebook
§ Establishes the structure, parameters and basis for the
integrated master schedule (IMS) development
§ Basis of performance measurement system; common
element integrating cost, schedule, & performance
§ Constructed to provide integrated planning down to the
work package task level, provides horizontal & vertical
§ Supports control account schedules and
the management of day–to–day
operations
traceability, summarization of info and critical path
identification and analysis
schedules and are summarized in the IMS
and part of the program’s PMB
22/74
Form IMP
Development
Team
Gather Inputs
Establish
Criteria For
Events
Define And Or
Derive
Deliverable
Products
Define Events
For Program
And Products
Define IPT
Structure To
Implement
Product
Structure
Expand WBS
To IPT
Structure
Produce The
Product IMP
Matrix With
CWBS
Data
Dictionary
IMS Inputs
OBS Update CWBS Update
Define Program
Demonstration
Capabilities
Define
Accomplishments
For Each
Capability
Set Order Of
Program Events
Select Topics For
IMP Narratives
Define Tasks And
Work Products
For Each
Accomplishment
IMS Inputs
Summary Of IMP
With E/A/C
Initial Approval Of
IMP
Demonstrate How
Subject Are
Managed
Release To Baseline
Control For Use By IMS
… is an event–based plan depicting the overall structure of the
program and the key processes and activities. It defines
accomplishments and criteria for each event.
With the IMP, the increasing maturity of the program is stated
explicitly in the Significant Accomplishments (SA) and their
Accomplishment Criteria (AC).
It’s these key processes and activities that are the basis of the
credibility assessment.
Events are NOT milestones, they are mini–Authorizations to
Proceed. These mini-ATPs are the basis of maturity assessments
of the products and services of the program.
Work performed beyond the upcoming Program Event is
actually done “as risk.” 23/74
24/74
25/74
26/74
27/74
28/74
29/74
30/74
Through PDR, the majority of the work is building the deliverables from the CDRLs.
Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level.
31/74
32/74
33/74
34/74
35/74
§ Without an IMP there
is no strategy
§ Without an IMP the
us no place for the
work to reside
§ Without an IMP there
is no way to answer to
the question: “Why
are we doing this?”
§ Without an IMP there
is no way to measure
the increasing
maturity of the
deliverables
36/74
37/74
All work flows
vertically from
bottom up.
From Work Package
content to the Exit
Criteria of the WP
(AC), to the
Significant
Accomplishments
(SA) to the Program
Events (PE).
This flow is a
description of the
work that produces
increasing maturity.
38/74
The activities of a
Work Package
“exit” through the
Accomplishment
Criteria (AC).
Interconnections
between Work
Packages at the
task level should
be avoided.
Only 100%
complete work
should start the
next Work
Package.
PE
SA
ACs
Tasks
Completing AC starts
task in next AC
Completed Task
lands on AC
PE
SAs
ACs
Tasks
39/74
40/74
Cost Performance Baseline
Schedule Performance Baseline
Technical Performance Baseline
Perform
Functional
Analysis
Determine
Scope and
Approach
Develop
Technical
Logic
Develop
Technical
Baseline
Develop WBS
Define
Activities
Estimate
Time
Durations
Sequence
Activities
Finalize
Schedule
Identify
Apportioned
Milestones
Determine
Resource
Requirements
Prepare Cost
Estimate
Resource
Load
Schedule
Finalize
Apportioned
Milestones
Determine
Funding
Constraints
Approve
PMB
41/74
42/74
Program Events
Define the availability
of a Capability at a point in
time.
Accomplishments
Represent requirements
that enable Capabilities.
Criteria
Represent Work Packages that
fulfill Requirements.
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
package
§ The increasing maturing of a product or service is described through Events or Milestones,
Accomplishments, Criteria, and their Work Packages.
§ Each Event or Milestone represents the availability of one or more capabilities.
§ The presence of these capabilities is measured by the Accomplishments and their Criteria.
§ Accomplishments are the pre–conditions for the maturity assessment of the product or service at
each Event or Milestone.
§ This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the
activities which produce deliverables. This hierarchy also describes increasing program maturity
resulting from the activities contained in the Work Packages.
§ Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or
Milestones is measured in units of “physical percent complete” by connecting Earned Value with
Technical Performance Measures.
The Structure of a
Deliverables Based Plan
Work
Package
Monthly Status Report:
§ Validate schedule status
(start/complete/slip)
§ Validate work package
% complete
§ Take earned value from % Cmplt
§ Identify/process cost ETCs
Weekly Status Report:
§ Roll up of lower level schedule
status
§ Roll up of lower level % complete
or
§ Milestone start/complete
§ Milestone slip (early/late,
start/complete)
§ Physical % Complete of tasks
Weekly Status Report:
§ Milestone start/complete
§ Milestone slip (early/late,
start/complete)
§ % complete of tasks
Near term Rolling Wave
Control account span
IMS Activities
(at Work Package level
WP’s < 45 work days)
20 to 40
Workday tasks
Or even
weekly tasks
IMS Tasks
(one and two levels
below WP level)
IMP
WBS
Levels
1, 2, and 3
WBS
Levels
4 and 5
WBS’s
Below
Work
Package
Planning Package
43/74
44/74
45/74
Cost, Schedule, Technical Performance†
WBS
Task 100
Task 101
Task 102
Task 103
Task 104
Task 105
Task 106
†This is a Key concept. This is the part of the process
that integrates the cost and schedule risk impacts to
provide the basis of a credible schedule.
Without Technical Performance measures, Cost and
Schedule cannot show physical percent complete.
Probability
Density
Function
§ Research the Project
§ Find Analogies
§ Ask Endless Questions
§ Analyze the Results
§ What can go wrong?
§ How likely is it to go wrong?
§ What is the cause?
§ What is the consequence?
Monte Carlo Simulation
Tool is Mandatory
1.0
.8
.6
.4
.2
0 Days, Facilities, Parts, People
Cumulative Distribution Function
Days, Facilities,
Parts and People
46/74
DID–81650 calls out the
details of the IMS and it’s
statistical analysis
A ship on the beach is a lighthouse
to the sea – Dutch Proverb
47/74
48/74
49/74
50/74
51/74
§ In the example above, the Work Package Managers collectively come to an agreement on how the sequence of
how the work will be performed within each AC.
§ The result is a collective ownership of the outcome. This ownership comes from the collective development of
the project plan.
§ This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product
development firms. 52/74
53/74
54/74
55/74
56/74
57/74
58/74
59/74
60/74
61/74
AC: 005
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
AC:023
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
§ The 100% completed work in AC:005 is needed to start the work in AC:023
§ In the IMP/IMS paradigm, there is no Task-to-Task connection across
Accomplishment Criteria (AC) boundaries, only within an AC
§ The AC-to-AC linking states “…all work in the predecessor AC must be complete
before starting the successor work, assuring the minimum of rework due to
partially defined requirements or partially completed products”
62/74
PE: B
PE: A
SA: 001
SA: 002
SA: 003
SA: 004
PE: A
Task
Task
Task
AC: 006
§ The best arrangement has the completion of Event A start the first task in Event B.
§ All work performed beyond the date of Event A is done at risk.
§ At PDR (Event A), approval to proceed Event B (CDR) is given
§ Only long lead items should cross Program Event boundaries
§ All other work terminates on the Program Event where a formal review of the
planned maturity is conducted – SRR, SFR, PDR, CDR, …
§ This topology assures a complete assessment of “progress to plan,” is available at
each Program Event
63/74
SA: 008
PE: B
64/74
A Credible Performance Measurement Baseline
Assures Program Management has the needed performance information to deliver
on‒time, on‒budget, and on‒specification
Technical Performance Measures
Cost Schedule
Conventional Earned Value
+
=
§ The Master Schedule
used to derive Basis of
Estimate (BOE) not the
other way around.
§ Probabilistic cost
estimating uses past
performance and cost risk
modeling.
§ Labor, Materiel, and other
direct costs accounted for
in Work Packages.
§ Risk adjustments for all
elements of cost.
Cost Baseline
§ Earned Value is diluted by
missing technical
performance.
§ Earned Value is diluted by
postponed features.
§ Earned Value is diluted by
non compliant quality.
§ All these dilutions require
adjustments to the
Estimate at Complete
(EAC) and the To
Complete Performance
Index (TCPI).
Technical Performance
§ Requirements are
decomposed into physical
deliverables.
§ Deliverables are produced
through Work Packages.
§ Work Packages are
assigned to accountable
manager.
§ Work Packages are
sequenced to form the
highest value stream with
the lowest technical and
programmatic risk.
Schedule Baseline
65/74
66/74
67/74
68/74
This approach is called Product Development Kaizen and is used by Lean Six Sigma firms to
ferret out the system capabilities before any technical or operational requirements are defined.
Use this to reverse engineer or validate the WBS and connect WHAT with WHY before
proceeding to build the CWBS or confirm the WBS.
69/74
Update Contractor
System Spec
Update Program
Development
Allocate
Functional
Reqmts
Update Functional
System Design
Develop HWCI
Specifications
Develop SIL
Specifications
Build Astp1
F-18 IRR
SIL Baseline 1.0
Update SIL Test
Cases
Develop Prelim
SIL CSCI
Critical
Components
AstP 1,2
SSpS 1,2,3
1
2
3
4
6
7
5
8
10
9
11
13
14
15
Update AS Test
I&T on CVN
I&T on LHA
12
Contract Award + 15 days
Systems Requirements Review (SRR)
System Functional Review (SFR)
HW Preliminary Design Review (PDR)
System PDR
EDM 1.0
Baseline
EDM 2.0
Baseline
Mfg Docs
Available
TBD
TRR 1.0
EDM 7-8 TRR
70/74
§ Each collection point provides
an assessment of incremental
mission value.
§ Defining these points before
the project starts is the basis of
measuring progress to plan.
§ Because then you know what
done looks like before it
arrives.
Deliverables
WBS
Tasks and Schedule
Business Need
Process Invoices for
Top Tier Suppliers
1st Level
Electronic Invoice
Submittal
1st Level
Routing to Payables
Department
2nd Level
Payables Account
Verification
2nd Level
Payment Scheduling
2nd Level
Material receipt
verification
2nd Level
“On hand” balance
Updates
Work
Package
(WP)
1 2
3
4
6
5 A
B
Deliverables defined in WP
Terminal Node in the WBS
defines the products or
services that produce the
products of the project
Terminal node of the
WBS defined by a Work
Package.
Tasks within the Work
Package produce the
Deliverables
100% Completion of the
deliverables is the measure of
performance for the Work Package
Management of the
Work Package Tasks is
the responsibility of
the WP Manager.
A decomposition of the work
needed to fulfill the business
requirements
71/74
72/74
Maturity Action
Product Product State
Adjective Verb
Noun Verb
Complete
Design
Model/Sim
Preliminary
Risk: CEV-037 - Loss of Critical Functions During Descent
Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete)
Risk
Score
24
22
20
18
16
14
12
10
8
6
4
2
0
Conduct Force and Moment Wind
Develop analytical model to de
Conduct focus splinter review
Conduct Block 1 w ind tunnel te
Correlate the analytical model
Conduct w ind tunnel testing of
Conduct w ind tunnel testing of
Flight Application of Spacecra
CEV block 5 w ind tunnel testin
In-Flight development tests of
Damaged TPS flight test
31.Mar.05
5.Oct.05
3.Apr.06
3.Jul.06
15.Sep.06
1.Jun.07
1.Apr.08
1.Aug.08
1.Apr.09
1.Jan.10
16.Dec.10
1.Jul.11
Risk Response
and Risk ID in
IMS
Milestone Date
traceable between
RM Tool and IMS
73/74
Glen B. Alleman
Niwot Ridge Consulting
4347 Pebble Beach Drive
Niwot, Colorado 80503
303.241.9633
glen.alleman@niwotridge.com
Performance Based Planning®
Integrated Master Plan
Integrated Master Schedule
Earned Value
Risk Management
Proposal Support Services

More Related Content

PDF
Increasing the Probability of Project Success with Five Principles and Practices
DOC
The Role of the Architect in ERP and PDM System Deployment
PDF
Heliotropic Abundance
PDF
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
PDF
Resource Paper of Enterprise-Wide Deployment of EDM
PDF
What Makes a Good Concept of Operations?
PDF
Five immutable principles
PDF
IMP / IMS Step by Step
Increasing the Probability of Project Success with Five Principles and Practices
The Role of the Architect in ERP and PDM System Deployment
Heliotropic Abundance
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
Resource Paper of Enterprise-Wide Deployment of EDM
What Makes a Good Concept of Operations?
Five immutable principles
IMP / IMS Step by Step

What's hot (20)

PDF
NAVAIR Integrated Master Schedule Guide guide
PDF
Integrated Master Plan and Integrated Master Schedule
PDF
Integrated master plan methodology (v2)
PDF
A Guide for Capital Project Mamnagers
PDF
Agile Project Management Procedures
PPTX
Establishing the Performance Measurement Baseline
PPTX
Getting To Done - A Master Class Workshop
PDF
Process Flow and Narrative for Agile
PDF
Cure for cost and schedule growth
PDF
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
PDF
The simple problem of schedule performance indices
PPTX
Integrating risk with earned value
PDF
Integrating cost, schedule, and technical performance
PDF
Strategic portfolio management
PDF
Lifecycle
PDF
Brownfields agile draft v11
PDF
Improving Project Performance in the DOE
PDF
IMP IMS overview
PDF
Practices of risk management
DOC
Design Patterns in Electronic Data Management
NAVAIR Integrated Master Schedule Guide guide
Integrated Master Plan and Integrated Master Schedule
Integrated master plan methodology (v2)
A Guide for Capital Project Mamnagers
Agile Project Management Procedures
Establishing the Performance Measurement Baseline
Getting To Done - A Master Class Workshop
Process Flow and Narrative for Agile
Cure for cost and schedule growth
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
The simple problem of schedule performance indices
Integrating risk with earned value
Integrating cost, schedule, and technical performance
Strategic portfolio management
Lifecycle
Brownfields agile draft v11
Improving Project Performance in the DOE
IMP IMS overview
Practices of risk management
Design Patterns in Electronic Data Management
Ad

Similar to Building the Performance Measurement Baseline (20)

DOCX
Assessing Project Performance Beyond CPI/SPI
PDF
Integrating cost schedule and technical performance
PDF
How to build a credible performance measurement baseline (v5)
PDF
Building a Credible Performance Measurement Baseline
PDF
Building a Credible Performance Measurement Baseline
PDF
Integrating Agile and Earned Value Management
PDF
Earned Value Management and Agile
PDF
Earning Value from Earned Value Management
PDF
Building A Credible Measurement Baseline
DOCX
EVMS for Commercial projects
PDF
The Intersection of Earned Value Management and Agile Software Development
PDF
Integrated Agile Software Development with Earned Value Management
DOC
EVMS with Technical Performance Measures
PDF
Implementing Technical Performance Measures
PPTX
Using Technical Performance Progress
PDF
Notional cam interview questions (update)
PDF
Five Immutable Principles of Program Success and Their Supporting Processes a...
PPTX
Five Immutable Principles of Project of Digital Transformation Success
PDF
Agile in an ANSI-748-C environment
PDF
Increasing the probability of project success using Earned Value Management
Assessing Project Performance Beyond CPI/SPI
Integrating cost schedule and technical performance
How to build a credible performance measurement baseline (v5)
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Integrating Agile and Earned Value Management
Earned Value Management and Agile
Earning Value from Earned Value Management
Building A Credible Measurement Baseline
EVMS for Commercial projects
The Intersection of Earned Value Management and Agile Software Development
Integrated Agile Software Development with Earned Value Management
EVMS with Technical Performance Measures
Implementing Technical Performance Measures
Using Technical Performance Progress
Notional cam interview questions (update)
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Project of Digital Transformation Success
Agile in an ANSI-748-C environment
Increasing the probability of project success using Earned Value Management
Ad

More from Glen Alleman (20)

PDF
Managing risk with deliverables planning
PDF
A Gentle Introduction to the IMP/IMS
PDF
Increasing the Probability of Project Success
PDF
Process Flow and Narrative for Agile+PPM
PDF
Principles of Risk Management
PDF
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
PDF
From Principles to Strategies for Systems Engineering
PDF
DHS - Using functions points to estimate agile development programs (v2)
PDF
Making the impossible possible
PDF
Capabilities based planning
PPTX
Program Management Office Lean Software Development and Six Sigma
PDF
Policy and Procedure Rollout
PDF
Integrated Master Plan Development
PDF
Project Management Theory
PDF
Seven Habits of a Highly Effective agile project manager
PDF
Paradigm of agile project management (update)
PDF
The 5 Immutable principles of project management
PDF
Deliverables based planning handbook
PDF
Writing Proposal Text
PDF
Assessing Enterprise Project Risk
Managing risk with deliverables planning
A Gentle Introduction to the IMP/IMS
Increasing the Probability of Project Success
Process Flow and Narrative for Agile+PPM
Principles of Risk Management
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
From Principles to Strategies for Systems Engineering
DHS - Using functions points to estimate agile development programs (v2)
Making the impossible possible
Capabilities based planning
Program Management Office Lean Software Development and Six Sigma
Policy and Procedure Rollout
Integrated Master Plan Development
Project Management Theory
Seven Habits of a Highly Effective agile project manager
Paradigm of agile project management (update)
The 5 Immutable principles of project management
Deliverables based planning handbook
Writing Proposal Text
Assessing Enterprise Project Risk

Recently uploaded (20)

PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PDF
GDG Cloud Iasi [PUBLIC] Florian Blaga - Unveiling the Evolution of Cybersecur...
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PDF
Electronic commerce courselecture one. Pdf
PDF
Chapter 3 Spatial Domain Image Processing.pdf
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
CIFDAQ's Market Insight: SEC Turns Pro Crypto
PDF
Machine learning based COVID-19 study performance prediction
PDF
Modernizing your data center with Dell and AMD
PPTX
breach-and-attack-simulation-cybersecurity-india-chennai-defenderrabbit-2025....
PDF
cuic standard and advanced reporting.pdf
DOCX
The AUB Centre for AI in Media Proposal.docx
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PPTX
Big Data Technologies - Introduction.pptx
PDF
GamePlan Trading System Review: Professional Trader's Honest Take
PDF
NewMind AI Monthly Chronicles - July 2025
PPTX
MYSQL Presentation for SQL database connectivity
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
Reach Out and Touch Someone: Haptics and Empathic Computing
GDG Cloud Iasi [PUBLIC] Florian Blaga - Unveiling the Evolution of Cybersecur...
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
Electronic commerce courselecture one. Pdf
Chapter 3 Spatial Domain Image Processing.pdf
Unlocking AI with Model Context Protocol (MCP)
CIFDAQ's Market Insight: SEC Turns Pro Crypto
Machine learning based COVID-19 study performance prediction
Modernizing your data center with Dell and AMD
breach-and-attack-simulation-cybersecurity-india-chennai-defenderrabbit-2025....
cuic standard and advanced reporting.pdf
The AUB Centre for AI in Media Proposal.docx
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Big Data Technologies - Introduction.pptx
GamePlan Trading System Review: Professional Trader's Honest Take
NewMind AI Monthly Chronicles - July 2025
MYSQL Presentation for SQL database connectivity
“AI and Expert System Decision Support & Business Intelligence Systems”

Building the Performance Measurement Baseline

  • 1. Lewis + Fowler Aerospace Capabilities Briefing (Full).pptx V5 Copyright © 2009, Niwot Ridge, Consulting LLC 1/74
  • 7. So much for our strategy of winning through technical dominance 7/74
  • 8. Product Tree SOW IPTs IMP IMS BOEs CWBS 8/74 Each element of the PMB is supportive of the others The integrated whole is the basis of a credible PMB
  • 9. Attribute Beneficial Outcome from this Attribute Maturity Flows through Program Events § Performance measurement is in units of increasing maturity of the Technical Performance Measures § Each event is a mini authorization to proceed Single outcome for each work package (AC) § Measure Physical Percent Complete at the WP level § Use 0/100 for tasks for the vast majority of work Technical Performance Measures are explicitly visible in the IMS § Connect Cost, Schedule, and Technical Performance § EV does not provide a means of adjust for “off TPM,” but make your own adjustments to the risk numbers for now Risk retirement explicitly visible in the IMS § Risk retirement is embedded in the IMS § Risk mitigation means waiting until the risk happens IMS flows vertically 1st and horizontally 2nd § All work supports the assessment of maturity § Isolate tasks dependencies within a Work Package No Event linkage except for long lead items § 0/100 requires not partial completion Decoupled dependences improves risk responsiveness § 1st round IMS defines a free flowing process § Maintaining this decoupling is key to a “dynamic” IMS that can respond to the natural changes in the program 9/74
  • 10. 10/74
  • 11. Risk Management Requirements Contractor Work Breakdown Structure (CWBS) CWBS Dictionary / SOW Integrated Master Plan (IMP) Integrated Master Schedule (IMS) Earned Value Management System Self Assessment / Award Fee Determinations / CPAR’s Technical Performance Measures (TPM) Process Metrics ü Specifications ü Work Statements ü Tailored to and outlines entire program and products ü Provides a single numbering system for the program ü States all deliverables and their components ü Follows IPT and CWBS structure ü Descriptions of work traceable to the IMS elements ü Event–driven Plan provides roadmap of processes for program ü Event–driven Schedule expands IMP into Work Packages ü Provides details and timing ü Builds in risk mitigation activities ü Connects measures of progress with measures of increasing maturity ü Connects System Performance with Continuous Technical Improvements ü Connects Cost Performance with the IMS Performance ü Determined by program execution 11/74
  • 12. Program Events Statement of Work CWBS Significant Accomplishments Accomplishment Criteria CDRLs and Deliverables Tasks Contained in Work Packages Measures the progress to plan using Physical & Complete at the Accomplishment Criteria (AC) and CWBS level Defines Aligned Aligned Aligned Aligned Aligned Completed SA’s are entry criteria for Program Events Completed Work Packages are exit criteria for Tasks Describes increasing product maturity as 0/100 or EVMS SD guidance Documents the product maturity that is aligned with SOW and CWBS Work necessary to mature products grouped by CWBS Work structure aligned to SOW 12/74
  • 13. 13/74
  • 14. 14/74
  • 15. DoD Guide DAG SEMP CWBS IMP IMS ISE Technical Reviews Event Timing of Technical Reviews X X X X X Success criteria Technical Reviews X X X X X Include entry and exit criteria for Technical Reviews in IMP/IMS X X Assess Technical Maturity in Technical Reviews X X X X Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X Integrate CWBS with: Requirements specification, Statement of Work, and IMP/IMS/EVMS X X X Link risk management and mitigation plans with technical reviews, TPM, EVMS, and IMS X Integrated Reviews Include Technical Baseline Review (TBR) in IMS; X Integrated Baseline Review: plans for event based technical reviews, including entry and exit criteria Correlation of TPM’s, IMP. IMS, and EVMS X 15/74
  • 16. 16/74
  • 17. 17/74
  • 18. 18/74
  • 19. 19/74
  • 20. 20/74 Only put these on your bookshelf after you’ve read them
  • 21. 21/74 IMS IMP Describes the strategy for successful program delivery Supplemental Schedules in CAM Notebook Tasks Contained in Work Packages Accomplishment Criteria Significant Accomplishments Program Events Integrated Master Plan (IMP) § Identifies program events, significant accomplishments, and accomplishment criteria. System level, controlled document. Integrated Master Schedule (IMS) § Logic network schedule of program planned activities keyed to the imp’s accomplishment criteria Supplemental Schedule § Created (as needed) to provide lower levels of detail data within CAM notebook § Establishes the structure, parameters and basis for the integrated master schedule (IMS) development § Basis of performance measurement system; common element integrating cost, schedule, & performance § Constructed to provide integrated planning down to the work package task level, provides horizontal & vertical § Supports control account schedules and the management of day–to–day operations traceability, summarization of info and critical path identification and analysis schedules and are summarized in the IMS and part of the program’s PMB
  • 22. 22/74 Form IMP Development Team Gather Inputs Establish Criteria For Events Define And Or Derive Deliverable Products Define Events For Program And Products Define IPT Structure To Implement Product Structure Expand WBS To IPT Structure Produce The Product IMP Matrix With CWBS Data Dictionary IMS Inputs OBS Update CWBS Update Define Program Demonstration Capabilities Define Accomplishments For Each Capability Set Order Of Program Events Select Topics For IMP Narratives Define Tasks And Work Products For Each Accomplishment IMS Inputs Summary Of IMP With E/A/C Initial Approval Of IMP Demonstrate How Subject Are Managed Release To Baseline Control For Use By IMS
  • 23. … is an event–based plan depicting the overall structure of the program and the key processes and activities. It defines accomplishments and criteria for each event. With the IMP, the increasing maturity of the program is stated explicitly in the Significant Accomplishments (SA) and their Accomplishment Criteria (AC). It’s these key processes and activities that are the basis of the credibility assessment. Events are NOT milestones, they are mini–Authorizations to Proceed. These mini-ATPs are the basis of maturity assessments of the products and services of the program. Work performed beyond the upcoming Program Event is actually done “as risk.” 23/74
  • 24. 24/74
  • 25. 25/74
  • 26. 26/74
  • 27. 27/74
  • 28. 28/74
  • 29. 29/74
  • 30. 30/74
  • 31. Through PDR, the majority of the work is building the deliverables from the CDRLs. Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level. 31/74
  • 32. 32/74
  • 33. 33/74
  • 34. 34/74
  • 35. 35/74
  • 36. § Without an IMP there is no strategy § Without an IMP the us no place for the work to reside § Without an IMP there is no way to answer to the question: “Why are we doing this?” § Without an IMP there is no way to measure the increasing maturity of the deliverables 36/74
  • 37. 37/74 All work flows vertically from bottom up. From Work Package content to the Exit Criteria of the WP (AC), to the Significant Accomplishments (SA) to the Program Events (PE). This flow is a description of the work that produces increasing maturity.
  • 38. 38/74 The activities of a Work Package “exit” through the Accomplishment Criteria (AC). Interconnections between Work Packages at the task level should be avoided. Only 100% complete work should start the next Work Package. PE SA ACs Tasks Completing AC starts task in next AC Completed Task lands on AC
  • 40. 40/74
  • 41. Cost Performance Baseline Schedule Performance Baseline Technical Performance Baseline Perform Functional Analysis Determine Scope and Approach Develop Technical Logic Develop Technical Baseline Develop WBS Define Activities Estimate Time Durations Sequence Activities Finalize Schedule Identify Apportioned Milestones Determine Resource Requirements Prepare Cost Estimate Resource Load Schedule Finalize Apportioned Milestones Determine Funding Constraints Approve PMB 41/74
  • 42. 42/74 Program Events Define the availability of a Capability at a point in time. Accomplishments Represent requirements that enable Capabilities. Criteria Represent Work Packages that fulfill Requirements. Work Package Work Package Work Package Work Package Work Package Work Package Work Package Work package § The increasing maturing of a product or service is described through Events or Milestones, Accomplishments, Criteria, and their Work Packages. § Each Event or Milestone represents the availability of one or more capabilities. § The presence of these capabilities is measured by the Accomplishments and their Criteria. § Accomplishments are the pre–conditions for the maturity assessment of the product or service at each Event or Milestone. § This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the activities which produce deliverables. This hierarchy also describes increasing program maturity resulting from the activities contained in the Work Packages. § Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or Milestones is measured in units of “physical percent complete” by connecting Earned Value with Technical Performance Measures. The Structure of a Deliverables Based Plan Work Package
  • 43. Monthly Status Report: § Validate schedule status (start/complete/slip) § Validate work package % complete § Take earned value from % Cmplt § Identify/process cost ETCs Weekly Status Report: § Roll up of lower level schedule status § Roll up of lower level % complete or § Milestone start/complete § Milestone slip (early/late, start/complete) § Physical % Complete of tasks Weekly Status Report: § Milestone start/complete § Milestone slip (early/late, start/complete) § % complete of tasks Near term Rolling Wave Control account span IMS Activities (at Work Package level WP’s < 45 work days) 20 to 40 Workday tasks Or even weekly tasks IMS Tasks (one and two levels below WP level) IMP WBS Levels 1, 2, and 3 WBS Levels 4 and 5 WBS’s Below Work Package Planning Package 43/74
  • 44. 44/74
  • 45. 45/74
  • 46. Cost, Schedule, Technical Performance† WBS Task 100 Task 101 Task 102 Task 103 Task 104 Task 105 Task 106 †This is a Key concept. This is the part of the process that integrates the cost and schedule risk impacts to provide the basis of a credible schedule. Without Technical Performance measures, Cost and Schedule cannot show physical percent complete. Probability Density Function § Research the Project § Find Analogies § Ask Endless Questions § Analyze the Results § What can go wrong? § How likely is it to go wrong? § What is the cause? § What is the consequence? Monte Carlo Simulation Tool is Mandatory 1.0 .8 .6 .4 .2 0 Days, Facilities, Parts, People Cumulative Distribution Function Days, Facilities, Parts and People 46/74 DID–81650 calls out the details of the IMS and it’s statistical analysis
  • 47. A ship on the beach is a lighthouse to the sea – Dutch Proverb 47/74
  • 48. 48/74
  • 49. 49/74
  • 50. 50/74
  • 51. 51/74
  • 52. § In the example above, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed within each AC. § The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan. § This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product development firms. 52/74
  • 53. 53/74
  • 54. 54/74
  • 55. 55/74
  • 56. 56/74
  • 57. 57/74
  • 58. 58/74
  • 59. 59/74
  • 60. 60/74
  • 61. 61/74
  • 62. AC: 005 Work Pkg Work Pkg Work Pkg Work Pkg AC AC:023 Work Pkg Work Pkg Work Pkg Work Pkg AC § The 100% completed work in AC:005 is needed to start the work in AC:023 § In the IMP/IMS paradigm, there is no Task-to-Task connection across Accomplishment Criteria (AC) boundaries, only within an AC § The AC-to-AC linking states “…all work in the predecessor AC must be complete before starting the successor work, assuring the minimum of rework due to partially defined requirements or partially completed products” 62/74
  • 63. PE: B PE: A SA: 001 SA: 002 SA: 003 SA: 004 PE: A Task Task Task AC: 006 § The best arrangement has the completion of Event A start the first task in Event B. § All work performed beyond the date of Event A is done at risk. § At PDR (Event A), approval to proceed Event B (CDR) is given § Only long lead items should cross Program Event boundaries § All other work terminates on the Program Event where a formal review of the planned maturity is conducted – SRR, SFR, PDR, CDR, … § This topology assures a complete assessment of “progress to plan,” is available at each Program Event 63/74 SA: 008 PE: B
  • 64. 64/74
  • 65. A Credible Performance Measurement Baseline Assures Program Management has the needed performance information to deliver on‒time, on‒budget, and on‒specification Technical Performance Measures Cost Schedule Conventional Earned Value + = § The Master Schedule used to derive Basis of Estimate (BOE) not the other way around. § Probabilistic cost estimating uses past performance and cost risk modeling. § Labor, Materiel, and other direct costs accounted for in Work Packages. § Risk adjustments for all elements of cost. Cost Baseline § Earned Value is diluted by missing technical performance. § Earned Value is diluted by postponed features. § Earned Value is diluted by non compliant quality. § All these dilutions require adjustments to the Estimate at Complete (EAC) and the To Complete Performance Index (TCPI). Technical Performance § Requirements are decomposed into physical deliverables. § Deliverables are produced through Work Packages. § Work Packages are assigned to accountable manager. § Work Packages are sequenced to form the highest value stream with the lowest technical and programmatic risk. Schedule Baseline 65/74
  • 66. 66/74
  • 67. 67/74
  • 68. 68/74
  • 69. This approach is called Product Development Kaizen and is used by Lean Six Sigma firms to ferret out the system capabilities before any technical or operational requirements are defined. Use this to reverse engineer or validate the WBS and connect WHAT with WHY before proceeding to build the CWBS or confirm the WBS. 69/74
  • 70. Update Contractor System Spec Update Program Development Allocate Functional Reqmts Update Functional System Design Develop HWCI Specifications Develop SIL Specifications Build Astp1 F-18 IRR SIL Baseline 1.0 Update SIL Test Cases Develop Prelim SIL CSCI Critical Components AstP 1,2 SSpS 1,2,3 1 2 3 4 6 7 5 8 10 9 11 13 14 15 Update AS Test I&T on CVN I&T on LHA 12 Contract Award + 15 days Systems Requirements Review (SRR) System Functional Review (SFR) HW Preliminary Design Review (PDR) System PDR EDM 1.0 Baseline EDM 2.0 Baseline Mfg Docs Available TBD TRR 1.0 EDM 7-8 TRR 70/74 § Each collection point provides an assessment of incremental mission value. § Defining these points before the project starts is the basis of measuring progress to plan. § Because then you know what done looks like before it arrives.
  • 71. Deliverables WBS Tasks and Schedule Business Need Process Invoices for Top Tier Suppliers 1st Level Electronic Invoice Submittal 1st Level Routing to Payables Department 2nd Level Payables Account Verification 2nd Level Payment Scheduling 2nd Level Material receipt verification 2nd Level “On hand” balance Updates Work Package (WP) 1 2 3 4 6 5 A B Deliverables defined in WP Terminal Node in the WBS defines the products or services that produce the products of the project Terminal node of the WBS defined by a Work Package. Tasks within the Work Package produce the Deliverables 100% Completion of the deliverables is the measure of performance for the Work Package Management of the Work Package Tasks is the responsibility of the WP Manager. A decomposition of the work needed to fulfill the business requirements 71/74
  • 72. 72/74 Maturity Action Product Product State Adjective Verb Noun Verb Complete Design Model/Sim Preliminary
  • 73. Risk: CEV-037 - Loss of Critical Functions During Descent Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete) Risk Score 24 22 20 18 16 14 12 10 8 6 4 2 0 Conduct Force and Moment Wind Develop analytical model to de Conduct focus splinter review Conduct Block 1 w ind tunnel te Correlate the analytical model Conduct w ind tunnel testing of Conduct w ind tunnel testing of Flight Application of Spacecra CEV block 5 w ind tunnel testin In-Flight development tests of Damaged TPS flight test 31.Mar.05 5.Oct.05 3.Apr.06 3.Jul.06 15.Sep.06 1.Jun.07 1.Apr.08 1.Aug.08 1.Apr.09 1.Jan.10 16.Dec.10 1.Jul.11 Risk Response and Risk ID in IMS Milestone Date traceable between RM Tool and IMS 73/74
  • 74. Glen B. Alleman Niwot Ridge Consulting 4347 Pebble Beach Drive Niwot, Colorado 80503 303.241.9633 glen.alleman@niwotridge.com Performance Based Planning® Integrated Master Plan Integrated Master Schedule Earned Value Risk Management Proposal Support Services