SlideShare a Scribd company logo
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
PMP:
Key Exam Concepts Series - Formulas
Crystal Clear understanding of key PMP concepts are
essential to pass the PMP exam. These slide will help you to:
• Visually learn key concepts
• Get deep understand with real world examples
• Sample Questions
Three point
estimation
Earned value
management
Forecasting
PV, FV, NPV,
EMV etc
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Definitions
Three point estimation:
• Accuracy improved by considering estimation uncertainty and
risk using three estimates to define an approximate range for an
activity’s cost.
Earned value management:
• It combines SCOPE, SCHEDULE, & RESOURCE measurements to
assess project performance and progress.
• It integrates the scope ,cost & schedule baselines, to form the
performance baseline
Forecasting:
• Forecasting is the process of predicting future project
performance based the current performance to date.
Miscellaneous formulas:
• Present value, Net Present value, Future value, EMV
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Three point estimation
Three point
estimation
Project schedule is the most important task which
depends on the activity estimation done by team.
Correctness of schedule heavily depends on the
accuracy of the duration of all project activities.
There are three basic techniques most widely used to
estimate activity duration and build the schedule.
Analogous Estimating
Parametric Estimating
Three Point Estimates
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Three point estimation
Weighted
average
• = (O + M + P) / 3Triangular Distribution
• = (O + 4M + P) / 6Beta Distribution or PERT
Accuracy improves by considering estimation uncertainty and risk
using three estimates to define an approximate range for an
activity’s cost.
Optimistic (O): Based on analysis of the best-case
scenario.
Most likely (M) : Based on realistic effort assessment
for required work & any predicted expenses (or ML)
Pessimistic (P). Based on analysis of the worst-case
scenario.
Three point
estimation
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Earned Value Management
It combines SCOPE, SCHEDULE, & RESOURCE
measurements to assess project performance and
progress.
It integrates the scope ,cost & schedule baselines, to
form the performance baseline
• It is authorized budget planned for work to be accomplished. Also known
as Budgeted Cost of Work Scheduled (BCWS). Total of PV (PMB or BAC).
Planned Value
(PV)
• It is actual amount of money spent to date. Also known as Actual Cost of
Work Performed (ACWP)
Actual cost
(AC)
• It is amount of money earned from completed work in a given time.
Earned Value is also known as Budgeted Cost of Work Performed
(BCWP).
Earned value
(EV)
Earned value
management
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Earned Value Management -> Earn Value (EV)
Earned value Calculation based on the Percentage completion
Schedule
Planned Value
(PV)
Percentage
Complete
Actual Cost
(AC)
Earn Value
(EV)
Task1 10,000 50% 6,000 ?
• Only 50% of work completed
• EV = 50% of PV
• EV = 50% of 10,000 = 5,000
Earn
Value
(EV)
Earned value
management
Schedule
Planned Value
(PV)
Percentage
Complete
Actual Cost
(AC)
Earn Value
(EV)
Task1 10,000 100% 9,000 ??
Task2 8,000 75% 6,000 ??
• EV = (100% of 10,000) + (75% of 8,000)
• EV = 10,000 + 6,000 = 16,000
Earn
Value
(EV)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• SV is a measure of schedule performance on a project.
• EVM & SV are best used with CPM scheduling & risk manag.
Schedule
variance (CV)
• It measure of cost performance on a project
• It indicates relationship of performance to costs spent
Cost variance
(CV)
• SPI is a measure of progress achieved compared to progress
planned on a project
Schedule
performance
index (SPI)
• CPI is a measure of the value of work completed compared
to the actual cost or progress made on the project.
Cost
performance
index (CPI)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• SPI = EV/PV
Schedule
performance
index
• CPI = EV/AC
Cost performance
index
Day1 Day2 Day3 Day4 Day5 Day6 Day7
Planned Budget (PV) 1,000 3,000 5,000 7,000 9,000 11,000 12,000
Actual Cost (AC) 1,100 3,300 6,600 9,900
Earned Value (EV) 1,000 2,000 3,000 4,000
PV: 7,000
BAC: 12,000
AC: 9,900
EV: 4,000
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Cost Variance
Schedule Variance
• SV = EV –PV
Schedule
variance
• CV= EV − ACCost variance
Note: All values are
cumulative
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
Planned
Value (PV)
Earned Value
(EV)
Actual Cost
(AC)
SV =
EV –PV
CV=
EV − AC
SPI =
EV/PV
CPI =
EV/AC
1000 800 1200 -200 -400 0.8 0.67
1500 1200 1800 -300 -600 0.8 0.67
• SV = EV –PVSchedule variance
• SPI = EV/PVSchedule performance index
• CV= EV − ACCost variance
• CPI = EV/ACCost performance index
Indexes
CPI
SPI
> 1
Under budget
Ahead of schedule
< 1
Over Budget
Behind schedule
= 1
On Budget
(planned cost)
On Schedule
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
Indexes
CPI
SPI
> 1
You are earning
more than the
spending. In other
words, you are
under budget.
More work has
been completed
than the planned
work. In other
words, you are
ahead of schedule.
< 1
You are earning
less than the
spending. In other
words, you’re over
budget
Less work is
completed than
the planned work.
In other words,
you are behind
schedule.
= 1
Earning &
spending are
equal. Or
proceeding exactly
as per planned
budget spending
On Schedule
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• Slowdown
with spending
to try to reach
optimal level
• Try to move
to optimal
otherwise re-
baseline.
• Continue as it
is
• Spend more
to catch up
Under Budget
but behind
schedule
Optimal –
Under Budget
& ahead of
Schedule
Over Budget
but ahead of
schedule
Worst case:
Over Budget
& behind
schedule
CPI >1
[Ahead of
Schedule]
CPI < 1
CPI >1
[Behind
Schedule]
CPI < 1
SPI < 1 [Under Budget] SPI >1
SPI < 1 [Over Budget] SPI >1
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting
Forecasting is used to come up with a future performance or
result of the project.
It gives project sponsors/management an early visibility on
of what may go wrong and help take preventive decision.
Forecasting
Estimate at
Completion (EAC)
Estimate to
Complete (ETC)
To Complete
Performance Index
(TCPI)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
Estimate at
Completion
As the project progresses, forecast for estimate at completion
(EAC) may develop based on project performance.
If BAC is no longer viable, forecasted EAC should be considered.
EAC involves making projections of conditions & events in the
project’s future based on current performance & other
knowledge.
Forecasts are generated, updated, and reissued based on work
performance data.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
Budgeted Rate:
• Absorb the Variance (originally planed budgeted
rate)
Current Progress:
• Take the ongoing project trend (CPI & SPI or only
CPI)
Erroneous scenario:
• Re-estimate the remaining portion
Estimate at
Completion
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
• EAC = AC + (BAC –EV)
Based on Budgeted
rate
• EAC = AC + (BAC –EV)/CPI = BAC / CPIBased on CPI.
• EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI
• EAC = AC + Bottom up estimateErroneous scenario:
EV=2K
AC=3.3K
BAC=12K
ETC=BAC-CV
EAC=AC+ETC
Estimate at
Completion
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate to Complete
ETC tell you, how much money you need to complete
the task at hand.
ETC = BAC - EV
VAC (Variance at completion) shows whether project is
forecasted to finish under or over budget
VAC = BAC – EAC
VAC % = VAC / BAC
Estimate to
Complete
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
TCPI is the measure of the CP that is required to be
achieved in order to meet a specified management goal
Ratio of cost to finish outstanding work to remaining
budget.
TCPI
calculation
Same Budget Use BAC
Revised Budget
Use Forecasted
EAC
If BAC is no longer viable, forecasted EAC should be approved, use in
the TCPI calculation.
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
PV: 6,000
BAC: 12,000
AC: 9,000
EV: 4,500
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Day1 Day2 Day3 Day4 Day5 Day6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= BAC-AC
= 3,000
Work Remaining
= BAC-EV
= 7,500
Case1: Same Budget
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
PV: 6,000
BAC: 12,000
AC: 9,000
EV: 4,500
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Day1 Day2 Day3 Day4 Day5 Day6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= EAC-AC
= 9,000
Work Remaining
= BAC-EV
= 7,500
EAC: 18,000
18,000
Case 2: Revised Budget
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
TCPI (based on the BAC):
(BAC –EV)
-----------------------------------------------------------------------------------------------------------
(BAC –AC)
TCPI (based on the EAC):
(BAC –EV)
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
(EAC –AC)
Work Remaining
----------------------
Fund Remaining
To-complete performance
index (TCPI) =
Case1 : TCPI
• (12,000-4,500)/(12,000-9,000)
• 7,500/3,000
• 2.5
Case2: TCPI
• (12,000-4,500)/(18,000-9,000)
• 7,500/9,000
• .83
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
• Project is in a comfortable position.If TCPI < 1
• Project have to perform with better cost performance than
the past cost performance.If TCPI > 1
• Project can continue with the same cost performance.if TCPI = 1
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Variance Analysis
An important aspect of project cost control includes determining the cause and
degree of variance relative to the cost baseline and deciding whether corrective or
preventive action is required.
Variance analysis is used in EVM for determining cause, impact, and corrective
actions
Cost (CV = EV –AC) Schedule (SV = EV –PV) VAC = BAC –EAC
Compare cost performance over time, schedule activities or work packages
overrunning and under running the budget, and estimated funds needed to
complete work in progress.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formulas
Miscellaneous
Formulas
Net present value (NPV):
• The total present value (PV) of a time series of
cash flows.
• It is a standard method for using the time value
of money to appraise long-term projects
Profit = Revenue – Costs
Profit Margin = Profit / Revenue
Evaluating efficiency of investment. Bigger
ROI is better.
ROI = (Gain – cost) / Gain
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formulas
Miscellaneous
Formulas
Internal Rate of Return:
• Interest rate received for an investment
consisting of payments and income that
occur at regular periods
Payback Period:
• The time it takes to recover your
investment in the project before you
start accumulating profit.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s
Money
Value as of Today (PV) Future value (FV)
Money – value depends on time
• Receiving AED 100 today has different meaning than
receiving it after 1 year.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s -> Future Value
• Present Value (PV) =
1,000
• Years : 2 years
• Interest: 5% (0.05)
• Future Value (FV) = ??
The future value ( FV )
• It refers to a method of calculating how much present value (PV)
of an asset or cash will be worth at a specific time in the future
FV = PV (1 + R)^N
• FV: Future value
• PV: Present value
• N: time of years
• R: Interest rate
PV=100, R=5%, N=1
• = 100 (1 + 0.05)^1 )
• = 100 * (1.05^1)
• = 100 * 1.05
• = 105
Above example
• = 1,000 (1 + 0.05)^2 )
• = 1,000 * (1.05^2)
• = 1,000 * 1.1025
• = 1,102.5
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s -> Present Value
Present Value:
• The value of an expected income(as of date of valuation)
• PV <= FV because money has interest-earning potential
• To calculate PV discount FV by interest rate
•Present Value (PV) = ?? •Years : 2 years
•Interest: 4% (0.05)
•Future Value (FV) = 1,000
PV = FV/ (1 + R)^N
• PV: Present value
• FV: Future value
• N: time of years
• R: Interest rate
Above example, what is PV??
• PV = 1,000 / (1 + 0.04)^2 )
• PV = 1,000 / (1.04^2)
• PV = 1,000 / 1.0816
• PV = 924
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Additional Free Resources
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!

More Related Content

PDF
PMP Chap 3 - Project Management Processes
PDF
Chap 4.3 Direct and Manage Project work
PDF
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PDF
PMP Chap 8 - Project Quality Management
PDF
Pmp chap13 - project stakeholder management details
PDF
PMP chap 1 - PMP Introduction (PMBOK 6)
PDF
PDF
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 3 - Project Management Processes
Chap 4.3 Direct and Manage Project work
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP Chap 8 - Project Quality Management
Pmp chap13 - project stakeholder management details
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP Chap 5 - Project Scope Management - Part 2

What's hot (20)

PDF
PMP Chap4-Project Integration Management Details: Part-2
PPTX
project management (10).pptx
PDF
Project quality management
PDF
PMP PMBOK 6th
PPTX
Smart project management - Best Practices to Manage Project effectively
PPTX
8.1 Plan Quality Management
PDF
Chap 5.4 Create WBS
PDF
Project Management Concepts
PPTX
9.0 Project Resource Management Overview
PDF
PMP Chap 12 - Project Procurement Management Details - Part2
PDF
PPTX
Project quality management
PDF
PMP 47 process definitions
PDF
PMP Chap 7 - Project Cost Management - Part 2
PDF
Pmp study-notes
PDF
Chap 8.1 Plan quality management
PPTX
Project integration management
PDF
Pmp chap 11 - project risk management - Part 2
PDF
Fundamentals of project management
PPTX
Project Quality Management - PMBOK6
PMP Chap4-Project Integration Management Details: Part-2
project management (10).pptx
Project quality management
PMP PMBOK 6th
Smart project management - Best Practices to Manage Project effectively
8.1 Plan Quality Management
Chap 5.4 Create WBS
Project Management Concepts
9.0 Project Resource Management Overview
PMP Chap 12 - Project Procurement Management Details - Part2
Project quality management
PMP 47 process definitions
PMP Chap 7 - Project Cost Management - Part 2
Pmp study-notes
Chap 8.1 Plan quality management
Project integration management
Pmp chap 11 - project risk management - Part 2
Fundamentals of project management
Project Quality Management - PMBOK6
Ad

Viewers also liked (19)

PDF
PMPProcessGroupTasks
PDF
PMBOK-5th ed: PMP- Flashcards Part1/5
PDF
Knowledge Area and 47 Processes Chart
PPT
Learning pmp formulas the easy way
PDF
PMP Chap9 - Project Human Resource management
PDF
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PDF
PMP Key Exam Concepts WPD, WPI & WPR
PPT
PMP Flash Card
PDF
PMP Key-exam-concepts-QA-QC-VS-VS
PDF
PMP Chap 4 - Project Integration Management - Part1
PDF
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PDF
PMP Chap 12 - Project Procurement Management Details - Part 1
PDF
PMBOK 5th Edition Mind map
PPTX
PMP Exam Changes
PDF
PMP Application form
PDF
Dr. APJ Abdul Kalam's Inspiring Quotes
PDF
PMP Chap 2- Org. Influence and Project Life Cycle
PDF
PMP 1600 Questions by TechFAQ360
PDF
PMP Chap 6 - Project Time management - Part1
PMPProcessGroupTasks
PMBOK-5th ed: PMP- Flashcards Part1/5
Knowledge Area and 47 Processes Chart
Learning pmp formulas the easy way
PMP Chap9 - Project Human Resource management
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
PMP Key Exam Concepts WPD, WPI & WPR
PMP Flash Card
PMP Key-exam-concepts-QA-QC-VS-VS
PMP Chap 4 - Project Integration Management - Part1
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMP Chap 12 - Project Procurement Management Details - Part 1
PMBOK 5th Edition Mind map
PMP Exam Changes
PMP Application form
Dr. APJ Abdul Kalam's Inspiring Quotes
PMP Chap 2- Org. Influence and Project Life Cycle
PMP 1600 Questions by TechFAQ360
PMP Chap 6 - Project Time management - Part1
Ad

Similar to PMP Key Exam Concepts - Formulas (20)

PPTX
Earned Value Management for project managers
PPTX
PMP COST FORMULAE
PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PPTX
Earned value management (EVM)
PPTX
Project monitoring & Earned Value Analysis
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PDF
Project monitoring and controlling with earned value management
PPTX
Earned Value Analysis
PPTX
Track Project Performance - Earned Value Management
PDF
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PPTX
Project Cost Management - PMP preparation course
PPTX
PMP Training - 07 project cost management
PPTX
Earned value management for Beginners
PDF
Earned value analysis - presentation
PDF
Cost Controlling And Forecasting of Project.pdf
PPTX
07 projectcostmanagement
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
Earned Value Management for project managers
PMP COST FORMULAE
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned value management (EVM)
Project monitoring & Earned Value Analysis
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Project monitoring and controlling with earned value management
Earned Value Analysis
Track Project Performance - Earned Value Management
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Project Cost Management - PMP preparation course
PMP Training - 07 project cost management
Earned value management for Beginners
Earned value analysis - presentation
Cost Controlling And Forecasting of Project.pdf
07 projectcostmanagement
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt

More from Anand Bobade (20)

PDF
Chap 12.3 Control Procurement
PDF
Chap 12.2 Conduct Procurement
PDF
Chap 12.1 Plan Procurement Management
PDF
Chap 12.0 Procurement Management overview
PDF
Chap 11.7 Monitor Risks
PDF
Chap 11.2 Identify Risks
PDF
Chap 10.3 Monitor Communication
PDF
Chap 10.2 Manage Communication
PDF
Chap 10.1 Plan Communication Management
PDF
Chap 9.6 Control Resources
PDF
Chap 9.5 Manage Team
PDF
Chap 9.4 Develop Team
PDF
Chap 9.3 Acquire Resources
PDF
Chap 9.2 Estimate Activity Resource
PDF
Chap 9.1 Pan Resource Management
PDF
Chap 9.0 Project Resource Management overview
PDF
Chap 7.4 Control Cost
PDF
Chap 7.2 Estimate Cost
PDF
Chap 7.3 Determine budget
PDF
Chap 7.1 Plan Cost Management
Chap 12.3 Control Procurement
Chap 12.2 Conduct Procurement
Chap 12.1 Plan Procurement Management
Chap 12.0 Procurement Management overview
Chap 11.7 Monitor Risks
Chap 11.2 Identify Risks
Chap 10.3 Monitor Communication
Chap 10.2 Manage Communication
Chap 10.1 Plan Communication Management
Chap 9.6 Control Resources
Chap 9.5 Manage Team
Chap 9.4 Develop Team
Chap 9.3 Acquire Resources
Chap 9.2 Estimate Activity Resource
Chap 9.1 Pan Resource Management
Chap 9.0 Project Resource Management overview
Chap 7.4 Control Cost
Chap 7.2 Estimate Cost
Chap 7.3 Determine budget
Chap 7.1 Plan Cost Management

Recently uploaded (20)

PPTX
Strategic Plan 2023-2024 Presentation.pptx
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PDF
Human resources management is a best management
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
PPTX
Effective_communication._(strategy).pptx
PDF
1_Corporate Goverance presentation topic
PDF
Case study -Uber strategic plan and management
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PDF
The-Power-of-Communication (1).pdf......
PPTX
Psychological_Contract_Presentation.pptx
PPTX
Human Resources management _HR structure
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PPTX
Consulting on marketing-The needs wants and demands are a very important comp...
PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PPTX
Chapter One an overview of political economy
PPTX
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
PPTX
Supervisory Styles and When to Use Them!
PPTX
Press Release Importance & Structure.pptx
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPT
Claims and Adjustment Business_Communication.pptx.ppt
Strategic Plan 2023-2024 Presentation.pptx
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
Human resources management is a best management
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
Effective_communication._(strategy).pptx
1_Corporate Goverance presentation topic
Case study -Uber strategic plan and management
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
The-Power-of-Communication (1).pdf......
Psychological_Contract_Presentation.pptx
Human Resources management _HR structure
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
Consulting on marketing-The needs wants and demands are a very important comp...
Improved_Leadership_in_Total_Quality_Lesson.pptx
Chapter One an overview of political economy
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
Supervisory Styles and When to Use Them!
Press Release Importance & Structure.pptx
Human Resource Management | Introduction,Meaning and Definition
Claims and Adjustment Business_Communication.pptx.ppt

PMP Key Exam Concepts - Formulas

  • 1. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) PMP: Key Exam Concepts Series - Formulas Crystal Clear understanding of key PMP concepts are essential to pass the PMP exam. These slide will help you to: • Visually learn key concepts • Get deep understand with real world examples • Sample Questions Three point estimation Earned value management Forecasting PV, FV, NPV, EMV etc
  • 2. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Definitions Three point estimation: • Accuracy improved by considering estimation uncertainty and risk using three estimates to define an approximate range for an activity’s cost. Earned value management: • It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project performance and progress. • It integrates the scope ,cost & schedule baselines, to form the performance baseline Forecasting: • Forecasting is the process of predicting future project performance based the current performance to date. Miscellaneous formulas: • Present value, Net Present value, Future value, EMV
  • 3. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Three point estimation Three point estimation Project schedule is the most important task which depends on the activity estimation done by team. Correctness of schedule heavily depends on the accuracy of the duration of all project activities. There are three basic techniques most widely used to estimate activity duration and build the schedule. Analogous Estimating Parametric Estimating Three Point Estimates
  • 4. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Three point estimation Weighted average • = (O + M + P) / 3Triangular Distribution • = (O + 4M + P) / 6Beta Distribution or PERT Accuracy improves by considering estimation uncertainty and risk using three estimates to define an approximate range for an activity’s cost. Optimistic (O): Based on analysis of the best-case scenario. Most likely (M) : Based on realistic effort assessment for required work & any predicted expenses (or ML) Pessimistic (P). Based on analysis of the worst-case scenario. Three point estimation
  • 5. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Earned Value Management It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project performance and progress. It integrates the scope ,cost & schedule baselines, to form the performance baseline • It is authorized budget planned for work to be accomplished. Also known as Budgeted Cost of Work Scheduled (BCWS). Total of PV (PMB or BAC). Planned Value (PV) • It is actual amount of money spent to date. Also known as Actual Cost of Work Performed (ACWP) Actual cost (AC) • It is amount of money earned from completed work in a given time. Earned Value is also known as Budgeted Cost of Work Performed (BCWP). Earned value (EV) Earned value management
  • 6. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Earned Value Management -> Earn Value (EV) Earned value Calculation based on the Percentage completion Schedule Planned Value (PV) Percentage Complete Actual Cost (AC) Earn Value (EV) Task1 10,000 50% 6,000 ? • Only 50% of work completed • EV = 50% of PV • EV = 50% of 10,000 = 5,000 Earn Value (EV) Earned value management Schedule Planned Value (PV) Percentage Complete Actual Cost (AC) Earn Value (EV) Task1 10,000 100% 9,000 ?? Task2 8,000 75% 6,000 ?? • EV = (100% of 10,000) + (75% of 8,000) • EV = 10,000 + 6,000 = 16,000 Earn Value (EV)
  • 7. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • SV is a measure of schedule performance on a project. • EVM & SV are best used with CPM scheduling & risk manag. Schedule variance (CV) • It measure of cost performance on a project • It indicates relationship of performance to costs spent Cost variance (CV) • SPI is a measure of progress achieved compared to progress planned on a project Schedule performance index (SPI) • CPI is a measure of the value of work completed compared to the actual cost or progress made on the project. Cost performance index (CPI)
  • 8. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • SPI = EV/PV Schedule performance index • CPI = EV/AC Cost performance index Day1 Day2 Day3 Day4 Day5 Day6 Day7 Planned Budget (PV) 1,000 3,000 5,000 7,000 9,000 11,000 12,000 Actual Cost (AC) 1,100 3,300 6,600 9,900 Earned Value (EV) 1,000 2,000 3,000 4,000 PV: 7,000 BAC: 12,000 AC: 9,900 EV: 4,000 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Cost Variance Schedule Variance • SV = EV –PV Schedule variance • CV= EV − ACCost variance Note: All values are cumulative
  • 9. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index Planned Value (PV) Earned Value (EV) Actual Cost (AC) SV = EV –PV CV= EV − AC SPI = EV/PV CPI = EV/AC 1000 800 1200 -200 -400 0.8 0.67 1500 1200 1800 -300 -600 0.8 0.67 • SV = EV –PVSchedule variance • SPI = EV/PVSchedule performance index • CV= EV − ACCost variance • CPI = EV/ACCost performance index Indexes CPI SPI > 1 Under budget Ahead of schedule < 1 Over Budget Behind schedule = 1 On Budget (planned cost) On Schedule
  • 10. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index Indexes CPI SPI > 1 You are earning more than the spending. In other words, you are under budget. More work has been completed than the planned work. In other words, you are ahead of schedule. < 1 You are earning less than the spending. In other words, you’re over budget Less work is completed than the planned work. In other words, you are behind schedule. = 1 Earning & spending are equal. Or proceeding exactly as per planned budget spending On Schedule
  • 11. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • Slowdown with spending to try to reach optimal level • Try to move to optimal otherwise re- baseline. • Continue as it is • Spend more to catch up Under Budget but behind schedule Optimal – Under Budget & ahead of Schedule Over Budget but ahead of schedule Worst case: Over Budget & behind schedule CPI >1 [Ahead of Schedule] CPI < 1 CPI >1 [Behind Schedule] CPI < 1 SPI < 1 [Under Budget] SPI >1 SPI < 1 [Over Budget] SPI >1
  • 12. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting Forecasting is used to come up with a future performance or result of the project. It gives project sponsors/management an early visibility on of what may go wrong and help take preventive decision. Forecasting Estimate at Completion (EAC) Estimate to Complete (ETC) To Complete Performance Index (TCPI)
  • 13. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): Estimate at Completion As the project progresses, forecast for estimate at completion (EAC) may develop based on project performance. If BAC is no longer viable, forecasted EAC should be considered. EAC involves making projections of conditions & events in the project’s future based on current performance & other knowledge. Forecasts are generated, updated, and reissued based on work performance data.
  • 14. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): Budgeted Rate: • Absorb the Variance (originally planed budgeted rate) Current Progress: • Take the ongoing project trend (CPI & SPI or only CPI) Erroneous scenario: • Re-estimate the remaining portion Estimate at Completion
  • 15. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): • EAC = AC + (BAC –EV) Based on Budgeted rate • EAC = AC + (BAC –EV)/CPI = BAC / CPIBased on CPI. • EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI • EAC = AC + Bottom up estimateErroneous scenario: EV=2K AC=3.3K BAC=12K ETC=BAC-CV EAC=AC+ETC Estimate at Completion
  • 16. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate to Complete ETC tell you, how much money you need to complete the task at hand. ETC = BAC - EV VAC (Variance at completion) shows whether project is forecasted to finish under or over budget VAC = BAC – EAC VAC % = VAC / BAC Estimate to Complete
  • 17. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI TCPI is the measure of the CP that is required to be achieved in order to meet a specified management goal Ratio of cost to finish outstanding work to remaining budget. TCPI calculation Same Budget Use BAC Revised Budget Use Forecasted EAC If BAC is no longer viable, forecasted EAC should be approved, use in the TCPI calculation. TCPI
  • 18. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI PV: 6,000 BAC: 12,000 AC: 9,000 EV: 4,500 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Day1 Day2 Day3 Day4 Day5 Day6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = BAC-AC = 3,000 Work Remaining = BAC-EV = 7,500 Case1: Same Budget
  • 19. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI PV: 6,000 BAC: 12,000 AC: 9,000 EV: 4,500 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Day1 Day2 Day3 Day4 Day5 Day6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = EAC-AC = 9,000 Work Remaining = BAC-EV = 7,500 EAC: 18,000 18,000 Case 2: Revised Budget
  • 20. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI TCPI (based on the BAC): (BAC –EV) ----------------------------------------------------------------------------------------------------------- (BAC –AC) TCPI (based on the EAC): (BAC –EV) ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- (EAC –AC) Work Remaining ---------------------- Fund Remaining To-complete performance index (TCPI) = Case1 : TCPI • (12,000-4,500)/(12,000-9,000) • 7,500/3,000 • 2.5 Case2: TCPI • (12,000-4,500)/(18,000-9,000) • 7,500/9,000 • .83 TCPI
  • 21. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI • Project is in a comfortable position.If TCPI < 1 • Project have to perform with better cost performance than the past cost performance.If TCPI > 1 • Project can continue with the same cost performance.if TCPI = 1 TCPI
  • 22. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Variance Analysis An important aspect of project cost control includes determining the cause and degree of variance relative to the cost baseline and deciding whether corrective or preventive action is required. Variance analysis is used in EVM for determining cause, impact, and corrective actions Cost (CV = EV –AC) Schedule (SV = EV –PV) VAC = BAC –EAC Compare cost performance over time, schedule activities or work packages overrunning and under running the budget, and estimated funds needed to complete work in progress.
  • 23. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formulas Miscellaneous Formulas Net present value (NPV): • The total present value (PV) of a time series of cash flows. • It is a standard method for using the time value of money to appraise long-term projects Profit = Revenue – Costs Profit Margin = Profit / Revenue Evaluating efficiency of investment. Bigger ROI is better. ROI = (Gain – cost) / Gain
  • 24. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formulas Miscellaneous Formulas Internal Rate of Return: • Interest rate received for an investment consisting of payments and income that occur at regular periods Payback Period: • The time it takes to recover your investment in the project before you start accumulating profit.
  • 25. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s Money Value as of Today (PV) Future value (FV) Money – value depends on time • Receiving AED 100 today has different meaning than receiving it after 1 year.
  • 26. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s -> Future Value • Present Value (PV) = 1,000 • Years : 2 years • Interest: 5% (0.05) • Future Value (FV) = ?? The future value ( FV ) • It refers to a method of calculating how much present value (PV) of an asset or cash will be worth at a specific time in the future FV = PV (1 + R)^N • FV: Future value • PV: Present value • N: time of years • R: Interest rate PV=100, R=5%, N=1 • = 100 (1 + 0.05)^1 ) • = 100 * (1.05^1) • = 100 * 1.05 • = 105 Above example • = 1,000 (1 + 0.05)^2 ) • = 1,000 * (1.05^2) • = 1,000 * 1.1025 • = 1,102.5
  • 27. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s -> Present Value Present Value: • The value of an expected income(as of date of valuation) • PV <= FV because money has interest-earning potential • To calculate PV discount FV by interest rate •Present Value (PV) = ?? •Years : 2 years •Interest: 4% (0.05) •Future Value (FV) = 1,000 PV = FV/ (1 + R)^N • PV: Present value • FV: Future value • N: time of years • R: Interest rate Above example, what is PV?? • PV = 1,000 / (1 + 0.04)^2 ) • PV = 1,000 / (1.04^2) • PV = 1,000 / 1.0816 • PV = 924
  • 28. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Additional Free Resources Visit Slide Share website & you will find other Knowledge area presentation… Please share!!