Earned Value ManagementEVM in 1+10 + 1 slidesTiago Franco (gama.franco@gmail.com)
AgendaOnce upon a time…The ProjectMental NoteHow Much Did I Spent?Am I On Time?Am I On Budget?The Full PictureThe Variances & Indicators (juicy)Quiz
Once upon a time…
The ProjectImage from: http://www.fiosinc.com/
Mental NotePV - Planned ValueHow much should I spend and execute?AC - Actual CostHow much did I spent?EV - Earned ValueHow much did I execute?
How Much Did I Spent?Image from: http://www.wikipedia.org
Am I On Time?Image from: http://www.wikipedia.org
Am I On Budget? Image from: http://www.wikipedia.org
The FullPictureImage from: http://www.wikipedia.org
The Variances & Indicators (Juicy)CV = Cost Variance = EV – ACIf CV < 0 then executing at an higher costIf CV > 0 then executing at an lower costSV = Schedule Variance = EV – PVIf SV < 0 then going slower than plannedIf SV > 0 then going faster than planned
The Variances & Indicators (Juicy)CPI – Cost Performance Index = EV/ACIf CPI < 1 then executing at an higher costIf CPI > 1 then executing at an lower costSPI - Schedule Performance Indicator = EV/PVIf SPI < 1 then going slower than plannedIf SPI > 1 then going faster than planned
QuizIs a CPI > 1 and/or an SPI > 1 a good thing?

More Related Content

PPTX
Earned value management (EVM)
PPTX
A simple approach to understanding Earned Value Management
PPT
Project Cost Management
PPT
Earned value
PDF
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
PPT
Project Control- Overview Presentation Tafseer
PDF
EVM of Project Management...
PPT
Project cost management-slides
Earned value management (EVM)
A simple approach to understanding Earned Value Management
Project Cost Management
Earned value
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
Project Control- Overview Presentation Tafseer
EVM of Project Management...
Project cost management-slides

What's hot (20)

PPS
Earned Value Management
PDF
ACONEX-workflow System
PPTX
7.4 Earned Value Analysis
PDF
Earned value analysis - presentation
PDF
Chap 9.1 Pan Resource Management
PDF
Project Risk Management
PDF
Chap 6.4 Estimate Activity Duration
PDF
Earned Value Management
PPTX
Earned value management for Beginners
PPTX
project management (10).pptx
PDF
07 project cost management
PPTX
Work breakdown structure
PPTX
Earned value management
PDF
Tahap Pra Konstruksi SPAL - Pekerjaan Persiapan
PDF
Introduction to Earned Value Management
 
PDF
How to create a work breakdown structure (wbs)
PPT
Wbs & Project Scheduling
PPTX
Planning_and_scheduling.pptx
PDF
Project Scheduling & Controls
PPT
Project Time Management
Earned Value Management
ACONEX-workflow System
7.4 Earned Value Analysis
Earned value analysis - presentation
Chap 9.1 Pan Resource Management
Project Risk Management
Chap 6.4 Estimate Activity Duration
Earned Value Management
Earned value management for Beginners
project management (10).pptx
07 project cost management
Work breakdown structure
Earned value management
Tahap Pra Konstruksi SPAL - Pekerjaan Persiapan
Introduction to Earned Value Management
 
How to create a work breakdown structure (wbs)
Wbs & Project Scheduling
Planning_and_scheduling.pptx
Project Scheduling & Controls
Project Time Management
Ad

Viewers also liked (19)

PDF
A simple example of Earned Value Management (EVM) in action
PDF
Earned Value Management Essentials
PDF
EVMS Made Simple
PDF
Executive Overview of Managing Agile Programs with Earned Value
PDF
Django10 cheat-sheet-grayscale
PPTX
Jerald kerby
PDF
Earned value management in action - A Webinar by Vivek Prakash, pmwares
PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PDF
Earned Value fundamentals
PPTX
project control using earned value analysis - Part 01
PDF
Back to basics - Earned Value Management for beginners webinar
PDF
Earned value management with Examples | Control Cost | PMBOK | PMP
PDF
A gentle introduction to earned value management systems (neutral)
PDF
Earning Value from Earned Value Management
PPT
Cost Control
PDF
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
A simple example of Earned Value Management (EVM) in action
Earned Value Management Essentials
EVMS Made Simple
Executive Overview of Managing Agile Programs with Earned Value
Django10 cheat-sheet-grayscale
Jerald kerby
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value fundamentals
project control using earned value analysis - Part 01
Back to basics - Earned Value Management for beginners webinar
Earned value management with Examples | Control Cost | PMBOK | PMP
A gentle introduction to earned value management systems (neutral)
Earning Value from Earned Value Management
Cost Control
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
Ad

Similar to Earned Value Management (6)

PDF
Pm 8 cost_management
PDF
Pm 8 cost_management
PDF
Project Management 3.2 cost
PDF
Pmp formulas pmbok6
PDF
Pmp formulas pmbok5
PDF
EVM excercise EVM excercise concepts & fundamentals
Pm 8 cost_management
Pm 8 cost_management
Project Management 3.2 cost
Pmp formulas pmbok6
Pmp formulas pmbok5
EVM excercise EVM excercise concepts & fundamentals

Recently uploaded (20)

PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
Solaris Resources Presentation - Corporate August 2025.pdf
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PPTX
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
PDF
Tata consultancy services case study shri Sharda college, basrur
PDF
Technical Architecture - Chainsys dataZap
PDF
How to Get Approval for Business Funding
PDF
Comments on Crystal Cloud and Energy Star.pdf
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
1911 Gold Corporate Presentation Aug 2025.pdf
PPTX
Astra-Investor- business Presentation (1).pptx
PDF
How to Get Business Funding for Small Business Fast
PDF
How to Get Funding for Your Trucking Business
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
PDF
Booking.com The Global AI Sentiment Report 2025
Slide gioi thieu VietinBank Quy 2 - 2025
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
Solaris Resources Presentation - Corporate August 2025.pdf
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Lecture 3344;;,,(,(((((((((((((((((((((((
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
Tata consultancy services case study shri Sharda college, basrur
Technical Architecture - Chainsys dataZap
How to Get Approval for Business Funding
Comments on Crystal Cloud and Energy Star.pdf
Principles of Marketing, Industrial, Consumers,
1911 Gold Corporate Presentation Aug 2025.pdf
Astra-Investor- business Presentation (1).pptx
How to Get Business Funding for Small Business Fast
How to Get Funding for Your Trucking Business
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
NEW - FEES STRUCTURES (01-july-2024).pdf
Booking.com The Global AI Sentiment Report 2025

Earned Value Management

  • 1. Earned Value ManagementEVM in 1+10 + 1 slidesTiago Franco (gama.franco@gmail.com)
  • 2. AgendaOnce upon a time…The ProjectMental NoteHow Much Did I Spent?Am I On Time?Am I On Budget?The Full PictureThe Variances & Indicators (juicy)Quiz
  • 3. Once upon a time…
  • 4. The ProjectImage from: http://www.fiosinc.com/
  • 5. Mental NotePV - Planned ValueHow much should I spend and execute?AC - Actual CostHow much did I spent?EV - Earned ValueHow much did I execute?
  • 6. How Much Did I Spent?Image from: http://www.wikipedia.org
  • 7. Am I On Time?Image from: http://www.wikipedia.org
  • 8. Am I On Budget? Image from: http://www.wikipedia.org
  • 9. The FullPictureImage from: http://www.wikipedia.org
  • 10. The Variances & Indicators (Juicy)CV = Cost Variance = EV – ACIf CV < 0 then executing at an higher costIf CV > 0 then executing at an lower costSV = Schedule Variance = EV – PVIf SV < 0 then going slower than plannedIf SV > 0 then going faster than planned
  • 11. The Variances & Indicators (Juicy)CPI – Cost Performance Index = EV/ACIf CPI < 1 then executing at an higher costIf CPI > 1 then executing at an lower costSPI - Schedule Performance Indicator = EV/PVIf SPI < 1 then going slower than plannedIf SPI > 1 then going faster than planned
  • 12. QuizIs a CPI > 1 and/or an SPI > 1 a good thing?