CSSE 372 Software Project
Management:
Earned Value Analysis
(EVA) Exercises
Shawn Bohner
Office: Moench Room F212
Phone: (812) 877-8685
Email: bohner@rose-hulman.edu
EVM excercise EVM excercise concepts & fundamentals
Learning Outcomes: Plan (verb)
Create a plan for an intermediate size software
project and manage to the plan. Maintain a
software project schedule.
n Do some Earned Value
Analysis
n Examine Estimated to
Complete Values
n Determine good and bad
Trends in the progress
You have the WBS and have identified
the activities. Where do you start with
Earned Value Analysis?
n Think for 15.11 seconds…
n Turn to a neighbor and
discuss it for a minute
n Then can we tawlk?
Earned Value Exercise (PV, AC, EV)
Task – Develop and install ten printer drivers.
• Budget - $100,000 ($10K per printer driver)
• Time – 10 weeks (1 printer driver per week)
At week 5:
• 4 printer drivers developed and installed
• $47,500 spent to date
PV = $???
AC = $???
EV = $???
Q1, 2, 3
Derived EVA Metrics: CV and SV
Schedule Variance
n Comparison of work
performed during a period
of time to what was
scheduled to be performed
n Negative SV means the
project is behind schedule
Cost Variance
n Comparison of the
budgeted cost of work
performed with actual
cost
n Negative CV means the
project is over budget
Q4
CV = EV–AC SV = EV–PV
Cost Variance (CV)
CV = EV - AC
= $???
Good News: If CV value is positive, the project is
currently under budget (spending less than
planned for the work)
Bad News: If CV value is negative, the project is
currently over budget (spending more than
planned for the work)
Earned Value Exercise (CV)
Cost Performance Index (CPI)
CPI = EV / AC
= ???
Good News: If CPI value is >1 or =1, the project
cost trend is currently under or at planned budget
Bad News: If CPI value <1, the project cost trend
is currently over budget
Earned Value Exercise (CPI)
Q5
Cost Variance % (CV%)
CV% = CV / EV
= ???%
Good News: If CV% value is positive, the project
is currently under budget by the CV%
Bad News: If CV% value is negative, the project is
currently over budget by the CV%
Earned Value Exercise (CV%)
Awkward!!!
Schedule Variance (SV)
SV = EV - PV
= ???
Good News: If SV value is positive, the project is
currently ahead of schedule
Bad News: If SV value is negative, the project is
currently behind schedule
Earned Value Exercise (SV)
Earned Value Exercise (SPI)
Schedule Performance Index (SPI)
SPI = EV / PV
= ???
Good News: If SPI value is >1 or =1, the project
schedule trend is currently ahead or on planned
schedule
Bad News: If SPI value <1, the project schedule
trend is currently behind schedule
Q6
Earned Value Exercise (SV%)
Schedule Variance % (SV%)
SV% = SV / PV
= ???%
Good News: If SV value is positive, the project is
currently ahead of schedule
Bad News: If SV value is negative, the project is
currently behind schedule
Q7
Earned Value Exercise
PV = $50,000
AC = $47,500
EV = $40,000
CV = -$7,500
CPI = 0.84
CV% = -19%
SV = -$10,000
SPI = 0.80
SV% = -20%
Task – Develop and install ten printer drivers.
• Budget - $100,000 ($10K per printer driver)
• Time – 10 weeks (1 printer driver per week)
At week 5:
• 4 printer drivers developed and installed
• $47,500 spent to date
But, when will we complete?
Estimate at Completion
(EAC)
Actual costs to date plus a new estimate for all
remaining work (original plan no longer valid)
EAC = AC + ETC
(ETC  Estimate to Complete)
Q8
Well, it’s a little involved…
Estimate at Completion
(EAC)
Actual costs to date plus remaining budget (current
variances viewed as atypical of future variances)
Actual costs to date plus remaining budget modified
by a performance factor (CPI) (current variances are
viewed as typical of future variances)
EAC = AC + [(BAC - EV) / CPI]
~EAC = BAC / CPI
Q8
Project: Alpha
C C
C
C
C C
S S
S
S
S S C
S
S
C
Under budget
Ahead of schedule
Over budget
Behind schedule
1.0
0.8
0.6
0.4
1.2
1.4
1.6
Project Week
8
7
6
5
4 9
3
2
1
Earned Value – Performance Indices
Good Progress
Project Week
8
7
6
5
4 9
3
2
1
1.0
0.8
0.6
0.4
1.2
1.4
1.6
C C
C
C
C
C
S S
S
S
S
S
Under budget
Ahead of schedule
Over budget
Behind schedule
Project: Beta
Earned Value – Performance Indices
Divergent Progress
Project: Charlie
C C
C
C C
C
S S
S
S
S
S C
S
Under budget
Ahead of schedule
Over budget
Behind schedule
1.0
0.8
0.6
0.4
1.2
1.4
1.6
Project Week
8
7
6
5
4 9
3
2
1
Earned Value – Performance Indices
Losing Ground
Q9
Recall: PV, EV and AC Curves
Cost and Schedule Variance
Another View of
Cost and Schedule Variance
Schedule
Variance
Cost Variance
PV
AC
EV
Time
Progress
EVM excercise EVM excercise concepts & fundamentals
Homework and Reading Reminders
n Read ahead with Chapter 9 of text for Monday
n Complete Homework 5 – Software Schedule
¨ Due by 11:55pm, Tuesday, October 9th, 2012
n Final Project – SW Proj. Mgt. Plan (SPMP)
¨ Completed by team…
¨ Due by 11:55pm, Friday, November 2nd, 2012.
¨ No late days –review swap with another team
Complete Homework 6 – Earned Value Analysis
¨ Due by 11:55pm, Tuesday, October 16th, 2012
n Have a great Fall break!

More Related Content

DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
PMP COST FORMULAE
PPTX
Earned Value Analysis in construction projects
PPTX
Project monitoring & Earned Value Analysis
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPTX
Project monitoring lecture 1
Earned Value AnalysisTracking Project ProgressWh.docx
PMP COST FORMULAE
Earned Value Analysis in construction projects
Project monitoring & Earned Value Analysis
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
Project monitoring lecture 1

Similar to EVM excercise EVM excercise concepts & fundamentals (20)

PPTX
Earned Value Management - Project Controls - Schedule Only.pptx
PPT
Earned value analysis training
PPTX
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
PDF
Earned value management
PPT
EVA - Metrics.ppt
PDF
Pmp cost chapter 7
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PDF
Back to basics - Earned Value Management for beginners webinar
PDF
PMP Key Exam Concepts - Formulas
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PDF
Basics of EVM.pdf
PDF
EVM of Project Management...
PPT
Earned Value Analysis
PDF
Project monitoring and controlling with earned value management
PPTX
Understanding_EVA_V2.pptx
PDF
Primavera Calender and Earned Value.pdf..
PPT
EARNED VALUE MANAGEMENT ANALYS 1.ppt
Earned Value Management - Project Controls - Schedule Only.pptx
Earned value analysis training
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
Earned value management
EVA - Metrics.ppt
Pmp cost chapter 7
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Back to basics - Earned Value Management for beginners webinar
PMP Key Exam Concepts - Formulas
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Basics of EVM.pdf
EVM of Project Management...
Earned Value Analysis
Project monitoring and controlling with earned value management
Understanding_EVA_V2.pptx
Primavera Calender and Earned Value.pdf..
EARNED VALUE MANAGEMENT ANALYS 1.ppt
Ad

Recently uploaded (20)

PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
Geodesy 1.pptx...............................................
PPT
Project quality management in manufacturing
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPT
introduction to datamining and warehousing
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPT
Mechanical Engineering MATERIALS Selection
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
PPT on Performance Review to get promotions
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Well-logging-methods_new................
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
Safety Seminar civil to be ensured for safe working.
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Geodesy 1.pptx...............................................
Project quality management in manufacturing
Fundamentals of safety and accident prevention -final (1).pptx
Internet of Things (IOT) - A guide to understanding
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Foundation to blockchain - A guide to Blockchain Tech
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
introduction to datamining and warehousing
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Embodied AI: Ushering in the Next Era of Intelligent Systems
Mechanical Engineering MATERIALS Selection
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT on Performance Review to get promotions
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Well-logging-methods_new................
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
Safety Seminar civil to be ensured for safe working.
Ad

EVM excercise EVM excercise concepts & fundamentals

  • 1. CSSE 372 Software Project Management: Earned Value Analysis (EVA) Exercises Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: bohner@rose-hulman.edu
  • 3. Learning Outcomes: Plan (verb) Create a plan for an intermediate size software project and manage to the plan. Maintain a software project schedule. n Do some Earned Value Analysis n Examine Estimated to Complete Values n Determine good and bad Trends in the progress
  • 4. You have the WBS and have identified the activities. Where do you start with Earned Value Analysis? n Think for 15.11 seconds… n Turn to a neighbor and discuss it for a minute n Then can we tawlk?
  • 5. Earned Value Exercise (PV, AC, EV) Task – Develop and install ten printer drivers. • Budget - $100,000 ($10K per printer driver) • Time – 10 weeks (1 printer driver per week) At week 5: • 4 printer drivers developed and installed • $47,500 spent to date PV = $??? AC = $??? EV = $??? Q1, 2, 3
  • 6. Derived EVA Metrics: CV and SV Schedule Variance n Comparison of work performed during a period of time to what was scheduled to be performed n Negative SV means the project is behind schedule Cost Variance n Comparison of the budgeted cost of work performed with actual cost n Negative CV means the project is over budget Q4 CV = EV–AC SV = EV–PV
  • 7. Cost Variance (CV) CV = EV - AC = $??? Good News: If CV value is positive, the project is currently under budget (spending less than planned for the work) Bad News: If CV value is negative, the project is currently over budget (spending more than planned for the work) Earned Value Exercise (CV)
  • 8. Cost Performance Index (CPI) CPI = EV / AC = ??? Good News: If CPI value is >1 or =1, the project cost trend is currently under or at planned budget Bad News: If CPI value <1, the project cost trend is currently over budget Earned Value Exercise (CPI) Q5
  • 9. Cost Variance % (CV%) CV% = CV / EV = ???% Good News: If CV% value is positive, the project is currently under budget by the CV% Bad News: If CV% value is negative, the project is currently over budget by the CV% Earned Value Exercise (CV%)
  • 11. Schedule Variance (SV) SV = EV - PV = ??? Good News: If SV value is positive, the project is currently ahead of schedule Bad News: If SV value is negative, the project is currently behind schedule Earned Value Exercise (SV)
  • 12. Earned Value Exercise (SPI) Schedule Performance Index (SPI) SPI = EV / PV = ??? Good News: If SPI value is >1 or =1, the project schedule trend is currently ahead or on planned schedule Bad News: If SPI value <1, the project schedule trend is currently behind schedule Q6
  • 13. Earned Value Exercise (SV%) Schedule Variance % (SV%) SV% = SV / PV = ???% Good News: If SV value is positive, the project is currently ahead of schedule Bad News: If SV value is negative, the project is currently behind schedule Q7
  • 14. Earned Value Exercise PV = $50,000 AC = $47,500 EV = $40,000 CV = -$7,500 CPI = 0.84 CV% = -19% SV = -$10,000 SPI = 0.80 SV% = -20% Task – Develop and install ten printer drivers. • Budget - $100,000 ($10K per printer driver) • Time – 10 weeks (1 printer driver per week) At week 5: • 4 printer drivers developed and installed • $47,500 spent to date
  • 15. But, when will we complete? Estimate at Completion (EAC) Actual costs to date plus a new estimate for all remaining work (original plan no longer valid) EAC = AC + ETC (ETC  Estimate to Complete) Q8
  • 16. Well, it’s a little involved… Estimate at Completion (EAC) Actual costs to date plus remaining budget (current variances viewed as atypical of future variances) Actual costs to date plus remaining budget modified by a performance factor (CPI) (current variances are viewed as typical of future variances) EAC = AC + [(BAC - EV) / CPI] ~EAC = BAC / CPI Q8
  • 17. Project: Alpha C C C C C C S S S S S S C S S C Under budget Ahead of schedule Over budget Behind schedule 1.0 0.8 0.6 0.4 1.2 1.4 1.6 Project Week 8 7 6 5 4 9 3 2 1 Earned Value – Performance Indices Good Progress
  • 18. Project Week 8 7 6 5 4 9 3 2 1 1.0 0.8 0.6 0.4 1.2 1.4 1.6 C C C C C C S S S S S S Under budget Ahead of schedule Over budget Behind schedule Project: Beta Earned Value – Performance Indices Divergent Progress
  • 19. Project: Charlie C C C C C C S S S S S S C S Under budget Ahead of schedule Over budget Behind schedule 1.0 0.8 0.6 0.4 1.2 1.4 1.6 Project Week 8 7 6 5 4 9 3 2 1 Earned Value – Performance Indices Losing Ground Q9
  • 20. Recall: PV, EV and AC Curves
  • 21. Cost and Schedule Variance
  • 22. Another View of Cost and Schedule Variance Schedule Variance Cost Variance PV AC EV Time Progress
  • 24. Homework and Reading Reminders n Read ahead with Chapter 9 of text for Monday n Complete Homework 5 – Software Schedule ¨ Due by 11:55pm, Tuesday, October 9th, 2012 n Final Project – SW Proj. Mgt. Plan (SPMP) ¨ Completed by team… ¨ Due by 11:55pm, Friday, November 2nd, 2012. ¨ No late days –review swap with another team Complete Homework 6 – Earned Value Analysis ¨ Due by 11:55pm, Tuesday, October 16th, 2012 n Have a great Fall break!