SlideShare a Scribd company logo
Understanding
Earned Value Analysis
PMI.org
How is project health measured?
Project Manager evaluates project’s triple constraint of
scope, time and cost
Key Questions
• Is the project performing to budget?
• Is the project on schedule to deliver the agreed scope?
Typically Summarize Project Health using Green, Yellow,
Red Status
(Traffic Light Reporting)
Problems with the Traffic Light status approach
Subjective to interpretation and influence
• No objective measurement to guide Project Health
• A project can report green and suddenly turn red before a few days
before the launch
• A project can report red and be rationalized to green or yellow
without any objective data
• No prior indicators to problems
Apply Earned Value Analysis
Earned Value Analysis (EVA)
• Earned Value Analysis is an objective method to measure project
performance in terms of scope, time and cost
• Use EVA metrics are used to measure project health and
project performance
Earned Value Characteristics
Point in Time Evaluation
• How much work did you PLAN to complete? (Planned Value)
• How much work did you ACTUALLY complete? (Earned Value)
• How much did you spend to complete the work? (Actual Cost)
EVA Example
A $10,000 software project is scheduled for 4 weeks.
At the end of the third week, the project is 50% complete
and the actual costs to date is $9,000
Planned Value (PV) = $7,500
Earned Value (EV) = $5,000
Actual Cost (AC) = $9,000
What is the project health?
Schedule Variance = EV – PV = $5,000 – $7,500 = - $2,500
Schedule Performance Index (SPI) = EV/PV = $5,000 / $7,500 = .66
Cost Variance = EV – AC = $5,000 - $9,000 = - $4,000
Cost Performance Index (CPI) = EV/AC = $5,000 / $9,000 = .55
Objective metrics indicate the project is behind schedule and over budget.
On-target projects have an SPI and CPI of 1 or greater
Forecasting Costs
If the project continues at the current performance,
what is the true cost of the project?
Estimate At Complete
= Budget At Complete (BAC) / CPI
= $10,000 / .55 = $18,181
At the end of the project, the total project costs will be $18,181
Establish Ranges to Guide Traffic Light Status
Traffic Light status is useful in conveying
overall project with one color
Establish objective SPI and CPI ranges to
determine the true project color.
Green [1.0 - .95]
Yellow [.94 - .85]
Red [.84, 0]
[1.0 - .95]
[.94 - .85]
[.84, 0]
Earned Value Summary
• Earned Value is an objective method of determining project performance
instead of subjective approaches
• Apply Earned Value enforces the project discipline of tracking project actual
performance against baseline costs and dates
• Estimate at Complete calculation can forecast true project costs
based on project performance
PMI.org
14 FEBRUARY 2023 11

More Related Content

PPTX
Understanding Earned Value Analysis (EVA)
PDF
Earned value analysis
PPTX
Project monitoring lecture 1
PPTX
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PPTX
Earned Value Management for project managers
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PPTX
Project monitoring & Earned Value Analysis
PPTX
Earned Value Analysis in construction projects
Understanding Earned Value Analysis (EVA)
Earned value analysis
Project monitoring lecture 1
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
Earned Value Management for project managers
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Project monitoring & Earned Value Analysis
Earned Value Analysis in construction projects

Similar to Understanding_EVA_V2.pptx (20)

DOCX
Earned value understanding
PPT
The Project Management Process - Week 9 Performance Management
PDF
Project monitoring and controlling with earned value management
PDF
Back to basics - Earned Value Management for beginners webinar
PPT
Lecture 5- Monitoring and Controlling Projects.ppt
PDF
Application of Earned Value Method and Delay Analysis on Construction Project...
PPTX
Earned Value Analysis
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
project control using earned value analysis - Part 01
PPTX
Projects Control Using Earned Value Techniques - Part One
PPT
EVA - Metrics.ppt
PDF
Your Projects May Be Robbing You Blind
PDF
(Presentation) Cis utilization of earned value management for monitoring prod...
PPTX
Earned value management (EVM)
PDF
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
DOCX
Available online at www.sciencedirect.comInternational Jou.docx
PPTX
Jason douglas earned value 1 0
PPTX
Project Cost Management
PPTX
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
Earned value understanding
The Project Management Process - Week 9 Performance Management
Project monitoring and controlling with earned value management
Back to basics - Earned Value Management for beginners webinar
Lecture 5- Monitoring and Controlling Projects.ppt
Application of Earned Value Method and Delay Analysis on Construction Project...
Earned Value Analysis
Earned Value AnalysisTracking Project ProgressWh.docx
project control using earned value analysis - Part 01
Projects Control Using Earned Value Techniques - Part One
EVA - Metrics.ppt
Your Projects May Be Robbing You Blind
(Presentation) Cis utilization of earned value management for monitoring prod...
Earned value management (EVM)
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Available online at www.sciencedirect.comInternational Jou.docx
Jason douglas earned value 1 0
Project Cost Management
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
Ad

Recently uploaded (20)

PPT
Design_with_Watersergyerge45hrbgre4top (1).ppt
PDF
The New Creative Director: How AI Tools for Social Media Content Creation Are...
PPTX
t_and_OpenAI_Combined_two_pressentations
PDF
Slides PDF: The World Game (s) Eco Economic Epochs.pdf
PPT
FIRE PREVENTION AND CONTROL PLAN- LUS.FM.MQ.OM.UTM.PLN.00014.ppt
PPTX
artificial intelligence overview of it and more
PPTX
Funds Management Learning Material for Beg
PDF
Smart Home Technology for Health Monitoring (www.kiu.ac.ug)
PDF
📍 LABUAN4D EXCLUSIVE SERVER STAR GAMING ASIA NO.1 TERPOPULER DI INDONESIA ! 🌟
PPTX
E -tech empowerment technologies PowerPoint
PDF
SlidesGDGoCxRAIS about Google Dialogflow and NotebookLM.pdf
PDF
simpleintnettestmetiaerl for the simple testint
PPTX
SAP Ariba Sourcing PPT for learning material
PPTX
IPCNA VIRTUAL CLASSES INTERMEDIATE 6 PROJECT.pptx
PDF
The Evolution of Traditional to New Media .pdf
PPT
isotopes_sddsadsaadasdasdasdasdsa1213.ppt
PPTX
Slides PPTX: World Game (s): Eco Economic Epochs.pptx
PDF
FINAL CALL-6th International Conference on Networks & IOT (NeTIOT 2025)
PPTX
newyork.pptxirantrafgshenepalchinachinane
PDF
SASE Traffic Flow - ZTNA Connector-1.pdf
Design_with_Watersergyerge45hrbgre4top (1).ppt
The New Creative Director: How AI Tools for Social Media Content Creation Are...
t_and_OpenAI_Combined_two_pressentations
Slides PDF: The World Game (s) Eco Economic Epochs.pdf
FIRE PREVENTION AND CONTROL PLAN- LUS.FM.MQ.OM.UTM.PLN.00014.ppt
artificial intelligence overview of it and more
Funds Management Learning Material for Beg
Smart Home Technology for Health Monitoring (www.kiu.ac.ug)
📍 LABUAN4D EXCLUSIVE SERVER STAR GAMING ASIA NO.1 TERPOPULER DI INDONESIA ! 🌟
E -tech empowerment technologies PowerPoint
SlidesGDGoCxRAIS about Google Dialogflow and NotebookLM.pdf
simpleintnettestmetiaerl for the simple testint
SAP Ariba Sourcing PPT for learning material
IPCNA VIRTUAL CLASSES INTERMEDIATE 6 PROJECT.pptx
The Evolution of Traditional to New Media .pdf
isotopes_sddsadsaadasdasdasdasdsa1213.ppt
Slides PPTX: World Game (s): Eco Economic Epochs.pptx
FINAL CALL-6th International Conference on Networks & IOT (NeTIOT 2025)
newyork.pptxirantrafgshenepalchinachinane
SASE Traffic Flow - ZTNA Connector-1.pdf
Ad

Understanding_EVA_V2.pptx

  • 2. How is project health measured? Project Manager evaluates project’s triple constraint of scope, time and cost Key Questions • Is the project performing to budget? • Is the project on schedule to deliver the agreed scope? Typically Summarize Project Health using Green, Yellow, Red Status (Traffic Light Reporting)
  • 3. Problems with the Traffic Light status approach Subjective to interpretation and influence • No objective measurement to guide Project Health • A project can report green and suddenly turn red before a few days before the launch • A project can report red and be rationalized to green or yellow without any objective data • No prior indicators to problems
  • 4. Apply Earned Value Analysis Earned Value Analysis (EVA) • Earned Value Analysis is an objective method to measure project performance in terms of scope, time and cost • Use EVA metrics are used to measure project health and project performance
  • 5. Earned Value Characteristics Point in Time Evaluation • How much work did you PLAN to complete? (Planned Value) • How much work did you ACTUALLY complete? (Earned Value) • How much did you spend to complete the work? (Actual Cost)
  • 6. EVA Example A $10,000 software project is scheduled for 4 weeks. At the end of the third week, the project is 50% complete and the actual costs to date is $9,000 Planned Value (PV) = $7,500 Earned Value (EV) = $5,000 Actual Cost (AC) = $9,000
  • 7. What is the project health? Schedule Variance = EV – PV = $5,000 – $7,500 = - $2,500 Schedule Performance Index (SPI) = EV/PV = $5,000 / $7,500 = .66 Cost Variance = EV – AC = $5,000 - $9,000 = - $4,000 Cost Performance Index (CPI) = EV/AC = $5,000 / $9,000 = .55 Objective metrics indicate the project is behind schedule and over budget. On-target projects have an SPI and CPI of 1 or greater
  • 8. Forecasting Costs If the project continues at the current performance, what is the true cost of the project? Estimate At Complete = Budget At Complete (BAC) / CPI = $10,000 / .55 = $18,181 At the end of the project, the total project costs will be $18,181
  • 9. Establish Ranges to Guide Traffic Light Status Traffic Light status is useful in conveying overall project with one color Establish objective SPI and CPI ranges to determine the true project color. Green [1.0 - .95] Yellow [.94 - .85] Red [.84, 0] [1.0 - .95] [.94 - .85] [.84, 0]
  • 10. Earned Value Summary • Earned Value is an objective method of determining project performance instead of subjective approaches • Apply Earned Value enforces the project discipline of tracking project actual performance against baseline costs and dates • Estimate at Complete calculation can forecast true project costs based on project performance