SlideShare a Scribd company logo
Instructor: Er. Ahmed Baasaay
LECTURE 5
Lecture 5 cost estimation training course .pdf
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
1.
Earthwork in excavation for
the foundation
L = (0.1m+4m+0.2m+3m + 0.1) +
2×0.45 = 8.3 m
For Long Wall: 3 8.3 0.9 1.1 24.65 cum
Short Wall of Drawing room and
Kitchen
3 3.3 0.9 1.1 9.80 cum
L = 4.2 – 2 x 0.45 = 3.3 m
Short Wall: for bedroom, bathroom
and WC
4 2.3 0.9 1.1 9.11 cum
L = 3.2 – 2 x 0.45 = 2.3 m
Wall in front of W. C 1 0.4 0.9 1.1 0.40 cum
L = (1.1 + 0.2) – 2 x 0.45 = 0.4 m
43.96 m3
2.
Plain cement Concrete (
1:4:8) for foundation
For Long Wall: 3 8.3 0.9 0.2 4.48 cum
For Short Wall: 3 3.3 0.9 0.2 1.78 cum
For Short Wall: 4 2.3 0.9 0.2 1.66 cum
wall in front of W.C 1 0.4 0.9 0.2 0.07 cum
7.99 m3
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
3.
Brick masonry up to
plinth in c.m.1:6
For long walls 1st footing 3 7.9 0.5 0.3 3.56
2nd footing 3 7.8 0.4 0.3 2.81
Plinth wall 3 7.7 0.3 0.85 5.89
For short walls 1st footing 3 3.7 0.5 0.3 1.67
2nd footing 3 3.8 0.4 0.3 1.37
Plinth wall 3 3.9 0.3 0.85 2.98
For short walls 1st footing 4 2.7 0.5 0.3 4
2nd footing 4 2.8 0.4 0.3 4
Plinth wall 4 2.9 0.3 0.85 4
Wall in front of W.C.: 1st footing 1 0.8 0.5 0.3 0.12
2nd footing 1 0.9 0.4 0.3 0.11
Plinth wall
1 1.0 0.3 0.85 0.26
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
1st Step 1 1.1 0.9 0.20 0.20
2nd Step 1 1.1 0.6 0.15 0.10
3rd Step 1 1.1 0.3 0.15 0.05
Total 25.04 m3
4. Damp proof coarse 5cm Thick
Long walls 3 7.7 0.3 - 6.93sqm
short walls-1 3 3.9 0.3 - 11.4 sqm
Short wall-2 4 2.9 0.3 - 3.48 sqm
Wall in front of W.C.: 1 1.0 0.3 - 0.30m Total= 22.11 m2
5. Earth filling in plinth
Bedroom 1 4 3 0.48 5.76
Drawing room 1 4 4 0.48 7.68
kitchen 1 4 3 0.48 5.76
Bathroom 1 3 1.7 0.48 2.45
Wc 1 1.3 1.1 0.48 0.69
Front of wc 1 1.5 1.1 0.48 0.79
Total 23.13 cum
Item
No.
Item Description (Work Details) No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
slab level in c.m. 1:6
6.
Brick masonry above plinth up to
For Long Wall: 3 7.6 0.2 3.0 13.68
For Short Wall: 1 3 4.0 0.2 3.0 7.2
For Short Wall 2 4 3.0 0.2 3.0 7.2
Wall in front of W.C. 1 1.1 0.2 3.0 0.66
Parapet wall Long wall 2 7.6 0.2 0.7 2.12
Short wall 2 7.2 0.2 0.7 2.02
32.88 m3
Deduction For Doors & Windows
D1 3 1.1 0.2 2.1 2
D2 2 0.9 0.2 2.1 0.76
G1 1 1.2 0.2 2.1 0.50
W1 4 1.8 0.2 1.4 2.02
W2 1 1.2 0.2 1.4 0.34
W3 1 1.5 0.2 1.4 0.42
V 2 0.6 0.2 0.6 0.14
Item
No.
Item Description (Work Details) No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
Deduction for lintels above
door and windows with 15cm
bearing at each end.
Lintel above D1 3 1.4 0.2 0.15 0.126
Lintel above D2 2 1.2 0.2 0.15 0.072
Lintel above G1 1 1.5 0.2 0.15 0.045
Lintel above W1 4 2.1 0.2 0.15 0.25
Lintel above W2 1 1.5 0.2 0.15 0.045
Lintel above W3 1 1.8 0.2 0.15 0.054
Lintel above V 2 0.9 0.2 0.15 0.054
Deduction= (-)0.646 m3
Net quantity of brickwork = 32.88-5.57-0.646= 22.54m^3 26.66 m^3
Item
No.
Item Description (Work Details) No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
7.
R.C.C works in slab, sunshade
and lintel
R.C.C slab 1 7.6 7.6 0.10 5.776
R.C.C Lintel above D1 4 1.2 0.2 0.15 0.144
R.C.C Lintel above D2 2 1.2 0.2 0.15 0.072
R.C.C Lintel above G1 1 1.5 0.2 0.15 0.045
R.C.C Lintel above W1 4 2.1 0.2 0.15 0.25
R.C.C Lintel above W2 1 1.5 0.2 0.15 0.045
R.C.C Lintel above W3 1 1.8 0.2 0.15 0.054
R.C.C Lintel above V 2 0.9 0.2 0.15 0.054
Sunshade on W1 4 2.1 0.6 0.1 0.504
Sunshade on W2 1 1.5 0.6 0.1 0.09
Sunshade on W3 1 1.8 0.6 0.1 0.108
Total 7 cum
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
8.
Smooth plaster inside the
rooms and ceilings in
c.m.1:3
Drg. Room 4 4.0 - 3.0 48.0
Bed Room 2 4.0 - 3.0 24.0
2 3.0 3.0 18.0
Kitchen 2 4.0 3.0 24.0
2 3.0 3.0 18.0
Bath 2 3.0 3.0 18.0
2 1.7 3.0 10.2
W.C. 2 1.3 3.0 7.8
2 1.1 3.0 6.6
2 1.5 3.0 9.0
2 1.1 3.0 6.6
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
ceiling plaster
Drg. Room 1 4.0 4.0 16.0
Bed Room 1 4.0 3.0 12.0
Kitchen 1 3.0 4.0 12.0
Bath 1 4.0 1.7 5.1
w.c. 1 1.3 1.1 1.43
in front of W.C 1 1.5 1.1 1.65
Total Quantity= 238.38 m2
D1 4/2 1.1 2.1 5.78
D2 4/2 0.9 2.1 3.78
G1 2/2 1.2 2.1 2.52
W1 4/2 1.8 1.4 5.04
W2 1/2 1.2 1.4 0.84
1/2 1.5 1.4 1.05
Total Deduction= (-)19.01 m2
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
The area of a ventilator is
less than 0.5m2 therefore no
deduction is made
For Door, half the number
of faces is deducted.
Net Quantity= 219.37 m2
plastering outside the rooms
and ceilings in c.m.1:3
Long Wall 2 7.6 - 3.8 57.76
Short wall 2 7.6 - 3.8 57.76
Inside of parapet walls 4 7.2 - 0.7 20.16
Sill of parapet wall long wall 2 7.6 - 0.2 3.04
Short wall 2 7.2 - 0.2 2.88
Total 141.6 m^2
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
9. Painting 2 coats and white
washing 1 coat Same as plastering 219.37 m2
10. 10cm thick P.C.C flooring
Bedroom 4 3 0.1 1.2 cum
Drawing room 4 4 0.1 1.6 cum
kitchen 4 3 0.1 1.2 cum
Bathroom 3 1.7 0.1 5.1 cum
Wc 1.3 1.1 0.1 1.43 cum
Front of wc 1.5 1.1 0.1 0.165 cum
Total 10.695 cum
Item
No.
Item Description (Work
Details)
No
Length
(L)
Breadth
(B)
Height
(H)
Quantity Remarks
9. 2cm thick marble flooring
Drg. Room 1 4.0 4.0 16.0
Bed Room 1 4.0 3.0 12.0
Kitchen 1 3.0 4.0 12.0
Bath 1 4.0 1.7 5.1
w.c. 1 1.3 1.1 1.43
in front of W.C 1 1.5 1.1 1.65
Steps Tread 3 1.1 0.3 0.99
Risers 4 1.1 - 0.15 0.66
9. wall finishing WC Long wall 2 1.3 - 2.5 6.5
Shor wall 2 1.1 - 2.5 5.5
Bathroom Long wall 2 3 - 2.5 15
Shor wall 2 1.7 - 2.5 5.5
Exercise
Estimate the quantities of the following given plan &
section
Doors & Windows
D1 (1.2 x 2.1)
D2 (0.9 x 2.1)
D3 (0.8 x 2.1)
W (1.2 x 1.5)
V (0.6 x 0.45)
THANK YOU

More Related Content

PDF
Final Estimation of Lecture hall (1).pdf
PPT
Construction Management Project
PPT
Project of construction management
PDF
1. UNIT -I ESTIMATION OF BUILDINGS.pdf
PPTX
Cost estimation of a Building
PDF
E.C.V detail estimate By centre line and Long wall short wall method
PDF
Boys home shed estimation
PDF
Boys home shed estimation
Final Estimation of Lecture hall (1).pdf
Construction Management Project
Project of construction management
1. UNIT -I ESTIMATION OF BUILDINGS.pdf
Cost estimation of a Building
E.C.V detail estimate By centre line and Long wall short wall method
Boys home shed estimation
Boys home shed estimation

Similar to Lecture 5 cost estimation training course .pdf (20)

PPTX
Quantity surveying & valuation prob.pptx
PDF
EC Unit 002 new (1).pdf
PDF
Girls home estimation
PDF
Girls home estimation
PPTX
Quantity surveying project
PDF
LONG WALL AND SHORT WALL METHOD-6
PDF
Quantity notes pdf
PPTX
Report costing
PPTX
Mode of measurement, rules for deduction of plastering & brickwork
PDF
72747160 estimation
PDF
Salma Mahgoub Portfolio.pdf Dec 2016
PPTX
Quantity Surveying Presentation by Abhijatrik-28C
PPTX
PDF
Lecture 3 Building Quantity Calculation.pdf
PPTX
Estimation
PDF
Small House Plans & Calculations.pdf
PDF
Long wall and short wall method 5
PDF
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
PDF
BSR - 2021 - Kiliinochchi - District
PDF
House Odendahl (SITE PLAN)-A1
Quantity surveying & valuation prob.pptx
EC Unit 002 new (1).pdf
Girls home estimation
Girls home estimation
Quantity surveying project
LONG WALL AND SHORT WALL METHOD-6
Quantity notes pdf
Report costing
Mode of measurement, rules for deduction of plastering & brickwork
72747160 estimation
Salma Mahgoub Portfolio.pdf Dec 2016
Quantity Surveying Presentation by Abhijatrik-28C
Lecture 3 Building Quantity Calculation.pdf
Estimation
Small House Plans & Calculations.pdf
Long wall and short wall method 5
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
BSR - 2021 - Kiliinochchi - District
House Odendahl (SITE PLAN)-A1
Ad

More from Ahmed Mohamed Hassan (Baasaay) (9)

PDF
Lecture 1 Engineering Economics Lecture 1.pdf
PDF
Lecture 2 Hospital Architecture course.pdf
PDF
Lecture 1 hospital architecture course.pdf
PDF
Lecture 4 Professional training course .pdf
PDF
Estimation and Costing course lecture 1.pdf
PDF
Lecture 2 project procurement and contract management .pdf
PDF
Lecture 1 Introduction to Procurement and contract Management Management - Co...
PPTX
Lecture 1 Introduction to statics Engineering Mechanics hibbeler 14th edition
PDF
Aci mix design very good
Lecture 1 Engineering Economics Lecture 1.pdf
Lecture 2 Hospital Architecture course.pdf
Lecture 1 hospital architecture course.pdf
Lecture 4 Professional training course .pdf
Estimation and Costing course lecture 1.pdf
Lecture 2 project procurement and contract management .pdf
Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to statics Engineering Mechanics hibbeler 14th edition
Aci mix design very good
Ad

Recently uploaded (20)

PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Sustainable Sites - Green Building Construction
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PPTX
additive manufacturing of ss316l using mig welding
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
Construction Project Organization Group 2.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
Well-logging-methods_new................
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPT
Project quality management in manufacturing
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPT
Mechanical Engineering MATERIALS Selection
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Sustainable Sites - Green Building Construction
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Model Code of Practice - Construction Work - 21102022 .pdf
additive manufacturing of ss316l using mig welding
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Construction Project Organization Group 2.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Well-logging-methods_new................
UNIT 4 Total Quality Management .pptx
Operating System & Kernel Study Guide-1 - converted.pdf
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Project quality management in manufacturing
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
bas. eng. economics group 4 presentation 1.pptx
Mechanical Engineering MATERIALS Selection

Lecture 5 cost estimation training course .pdf

  • 1. Instructor: Er. Ahmed Baasaay LECTURE 5
  • 3. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 1. Earthwork in excavation for the foundation L = (0.1m+4m+0.2m+3m + 0.1) + 2×0.45 = 8.3 m For Long Wall: 3 8.3 0.9 1.1 24.65 cum Short Wall of Drawing room and Kitchen 3 3.3 0.9 1.1 9.80 cum L = 4.2 – 2 x 0.45 = 3.3 m Short Wall: for bedroom, bathroom and WC 4 2.3 0.9 1.1 9.11 cum L = 3.2 – 2 x 0.45 = 2.3 m Wall in front of W. C 1 0.4 0.9 1.1 0.40 cum L = (1.1 + 0.2) – 2 x 0.45 = 0.4 m 43.96 m3 2. Plain cement Concrete ( 1:4:8) for foundation For Long Wall: 3 8.3 0.9 0.2 4.48 cum For Short Wall: 3 3.3 0.9 0.2 1.78 cum For Short Wall: 4 2.3 0.9 0.2 1.66 cum wall in front of W.C 1 0.4 0.9 0.2 0.07 cum 7.99 m3
  • 4. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 3. Brick masonry up to plinth in c.m.1:6 For long walls 1st footing 3 7.9 0.5 0.3 3.56 2nd footing 3 7.8 0.4 0.3 2.81 Plinth wall 3 7.7 0.3 0.85 5.89 For short walls 1st footing 3 3.7 0.5 0.3 1.67 2nd footing 3 3.8 0.4 0.3 1.37 Plinth wall 3 3.9 0.3 0.85 2.98 For short walls 1st footing 4 2.7 0.5 0.3 4 2nd footing 4 2.8 0.4 0.3 4 Plinth wall 4 2.9 0.3 0.85 4 Wall in front of W.C.: 1st footing 1 0.8 0.5 0.3 0.12 2nd footing 1 0.9 0.4 0.3 0.11 Plinth wall 1 1.0 0.3 0.85 0.26
  • 5. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 1st Step 1 1.1 0.9 0.20 0.20 2nd Step 1 1.1 0.6 0.15 0.10 3rd Step 1 1.1 0.3 0.15 0.05 Total 25.04 m3 4. Damp proof coarse 5cm Thick Long walls 3 7.7 0.3 - 6.93sqm short walls-1 3 3.9 0.3 - 11.4 sqm Short wall-2 4 2.9 0.3 - 3.48 sqm Wall in front of W.C.: 1 1.0 0.3 - 0.30m Total= 22.11 m2 5. Earth filling in plinth Bedroom 1 4 3 0.48 5.76 Drawing room 1 4 4 0.48 7.68 kitchen 1 4 3 0.48 5.76 Bathroom 1 3 1.7 0.48 2.45 Wc 1 1.3 1.1 0.48 0.69 Front of wc 1 1.5 1.1 0.48 0.79 Total 23.13 cum
  • 6. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks slab level in c.m. 1:6 6. Brick masonry above plinth up to For Long Wall: 3 7.6 0.2 3.0 13.68 For Short Wall: 1 3 4.0 0.2 3.0 7.2 For Short Wall 2 4 3.0 0.2 3.0 7.2 Wall in front of W.C. 1 1.1 0.2 3.0 0.66 Parapet wall Long wall 2 7.6 0.2 0.7 2.12 Short wall 2 7.2 0.2 0.7 2.02 32.88 m3 Deduction For Doors & Windows D1 3 1.1 0.2 2.1 2 D2 2 0.9 0.2 2.1 0.76 G1 1 1.2 0.2 2.1 0.50 W1 4 1.8 0.2 1.4 2.02 W2 1 1.2 0.2 1.4 0.34 W3 1 1.5 0.2 1.4 0.42 V 2 0.6 0.2 0.6 0.14
  • 7. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks Deduction for lintels above door and windows with 15cm bearing at each end. Lintel above D1 3 1.4 0.2 0.15 0.126 Lintel above D2 2 1.2 0.2 0.15 0.072 Lintel above G1 1 1.5 0.2 0.15 0.045 Lintel above W1 4 2.1 0.2 0.15 0.25 Lintel above W2 1 1.5 0.2 0.15 0.045 Lintel above W3 1 1.8 0.2 0.15 0.054 Lintel above V 2 0.9 0.2 0.15 0.054 Deduction= (-)0.646 m3 Net quantity of brickwork = 32.88-5.57-0.646= 22.54m^3 26.66 m^3
  • 8. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 7. R.C.C works in slab, sunshade and lintel R.C.C slab 1 7.6 7.6 0.10 5.776 R.C.C Lintel above D1 4 1.2 0.2 0.15 0.144 R.C.C Lintel above D2 2 1.2 0.2 0.15 0.072 R.C.C Lintel above G1 1 1.5 0.2 0.15 0.045 R.C.C Lintel above W1 4 2.1 0.2 0.15 0.25 R.C.C Lintel above W2 1 1.5 0.2 0.15 0.045 R.C.C Lintel above W3 1 1.8 0.2 0.15 0.054 R.C.C Lintel above V 2 0.9 0.2 0.15 0.054 Sunshade on W1 4 2.1 0.6 0.1 0.504 Sunshade on W2 1 1.5 0.6 0.1 0.09 Sunshade on W3 1 1.8 0.6 0.1 0.108 Total 7 cum
  • 9. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 8. Smooth plaster inside the rooms and ceilings in c.m.1:3 Drg. Room 4 4.0 - 3.0 48.0 Bed Room 2 4.0 - 3.0 24.0 2 3.0 3.0 18.0 Kitchen 2 4.0 3.0 24.0 2 3.0 3.0 18.0 Bath 2 3.0 3.0 18.0 2 1.7 3.0 10.2 W.C. 2 1.3 3.0 7.8 2 1.1 3.0 6.6 2 1.5 3.0 9.0 2 1.1 3.0 6.6
  • 10. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks ceiling plaster Drg. Room 1 4.0 4.0 16.0 Bed Room 1 4.0 3.0 12.0 Kitchen 1 3.0 4.0 12.0 Bath 1 4.0 1.7 5.1 w.c. 1 1.3 1.1 1.43 in front of W.C 1 1.5 1.1 1.65 Total Quantity= 238.38 m2 D1 4/2 1.1 2.1 5.78 D2 4/2 0.9 2.1 3.78 G1 2/2 1.2 2.1 2.52 W1 4/2 1.8 1.4 5.04 W2 1/2 1.2 1.4 0.84 1/2 1.5 1.4 1.05 Total Deduction= (-)19.01 m2
  • 11. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks The area of a ventilator is less than 0.5m2 therefore no deduction is made For Door, half the number of faces is deducted. Net Quantity= 219.37 m2 plastering outside the rooms and ceilings in c.m.1:3 Long Wall 2 7.6 - 3.8 57.76 Short wall 2 7.6 - 3.8 57.76 Inside of parapet walls 4 7.2 - 0.7 20.16 Sill of parapet wall long wall 2 7.6 - 0.2 3.04 Short wall 2 7.2 - 0.2 2.88 Total 141.6 m^2
  • 12. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 9. Painting 2 coats and white washing 1 coat Same as plastering 219.37 m2 10. 10cm thick P.C.C flooring Bedroom 4 3 0.1 1.2 cum Drawing room 4 4 0.1 1.6 cum kitchen 4 3 0.1 1.2 cum Bathroom 3 1.7 0.1 5.1 cum Wc 1.3 1.1 0.1 1.43 cum Front of wc 1.5 1.1 0.1 0.165 cum Total 10.695 cum
  • 13. Item No. Item Description (Work Details) No Length (L) Breadth (B) Height (H) Quantity Remarks 9. 2cm thick marble flooring Drg. Room 1 4.0 4.0 16.0 Bed Room 1 4.0 3.0 12.0 Kitchen 1 3.0 4.0 12.0 Bath 1 4.0 1.7 5.1 w.c. 1 1.3 1.1 1.43 in front of W.C 1 1.5 1.1 1.65 Steps Tread 3 1.1 0.3 0.99 Risers 4 1.1 - 0.15 0.66 9. wall finishing WC Long wall 2 1.3 - 2.5 6.5 Shor wall 2 1.1 - 2.5 5.5 Bathroom Long wall 2 3 - 2.5 15 Shor wall 2 1.7 - 2.5 5.5
  • 14. Exercise Estimate the quantities of the following given plan & section
  • 15. Doors & Windows D1 (1.2 x 2.1) D2 (0.9 x 2.1) D3 (0.8 x 2.1) W (1.2 x 1.5) V (0.6 x 0.45)