Estimation of a wall
Prepare a detailed estimate of a wall of building from the
given plan and section and general specifications
ABRAR UNIVERSITY
ABRAR UNIVERSITY
ABRAR UNIVERSITY
ABRAR UNIVERSITY
Exercise
Prepare a detailed estimate of a wall of building from the
given plan and section and general specifications:-
ABRAR UNIVERSITY
Lecture 4  Professional training course .pdf
ABRAR UNIVERSITY
Lecture 4  Professional training course .pdf
ABRAR UNIVERSITY
Methods of taking out quantities:
The quantities like earthwork, foundation concrete, brickwork in plinth and
superstructure etc., can be workout by any of the following two methods:
1. Long wall-short wall method.
2. Centre line method
3. Partly Centre line and long and wall method.
ABRAR UNIVERSITY
1. Long Wall and Short Wall Method
- For the calculating quantity of various construction item, long wall and short wall method is used.
- For measuring the long wall and short wall the external out-to-out length of walls running in the longitudinal
direction generally is considered as “long wall” .
- While the in-to-in internal length of walls running in the transverse direction is called as “short wall” or “cross
wall”.
- For calculating quantity multiply the length into the breadth and height of the wall.
- Length of Long Wall = Center to Center Length of wall + Half Breadth on One Side + Half Breadth on the Other
Side.
- Length of Short Wall = Centre to Centre Length – Half Breadth on One Side - Half Breadth on One other Side
Explanation:
Centre to center of long wall: 5m + 0.3/2 + 0.3/2 = 5.3m
Centre to center of short wall: 4m + 0.3/2 + 0.3/2 = 4.3m
Long wall = center to Centre length – 2 x half breadth
= 5.3m + 2 x 0.3/2 = 5.6
Long wall = 5m + 2x0.3 = 5.6m
Short wall = 4m
Long wall= centre to centre of long wall + 2x half thickness of
wall
Long wall = 5.3m + 2 x 0.15m =5.6m
Short wall= centre to centre of short wall – 2 x half thickness
of wall
• Short wall = 4.3m – 2 x 0.15 = 4m
G.L
• - Centre to Centre length of long wall = 5+ (1/2×0.30) + (1/2 x 0.30) = 5.30 m
- Centre to Centre length of short wall = 4+ (1/2 x 0.30) + (1/2×0.30) = 4.30 m
- Long wall = 5.3 + 2 x 0.45 = 6.2m
- Short wall = 4.3m – 2 x 0.45 = 3.4m
Calculate the following quantities:
Earthwork in Foundation, Concrete in foundation, Brickwork in plinth and
superstructure
Lecture 4  Professional training course .pdf
Lecture 4  Professional training course .pdf
Lecture 4  Professional training course .pdf
Lecture 4  Professional training course .pdf
Lecture 4  Professional training course .pdf
Lecture 4  Professional training course .pdf
THANK YOU
ABRAR UNIVERSITY

More Related Content

PDF
Long wall and short wall method 1
PDF
Long wall and short wall method 1
PPTX
PDF
Long wall and short wall method 3
PDF
Long wall and short wall method 2
PDF
Lecture 3 Building Quantity Calculation.pdf
PPTX
Quantity surveying & valuation prob.pptx
PDF
Long wall and short wall method 4
Long wall and short wall method 1
Long wall and short wall method 1
Long wall and short wall method 3
Long wall and short wall method 2
Lecture 3 Building Quantity Calculation.pdf
Quantity surveying & valuation prob.pptx
Long wall and short wall method 4

Similar to Lecture 4 Professional training course .pdf (20)

PPTX
Methods of estimation - Estimation, Costing and Valuation Engineering
PDF
LONG WALL AND SHORT WALL METHOD-6
PDF
Long wall and short wall method 5
PPTX
Methods of Taking out Quantities Estimating Costing and Valuation
PDF
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
PPTX
Cost estimation of a Building
PPTX
2 Presentation on Estimation and its Methods.pptx
PDF
E.C.V detail estimate By centre line and Long wall short wall method
PDF
EC Unit 002 new (1).pdf
PDF
Quantity notes pdf
PDF
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
PPTX
Quiz Lecture 1,2,4 CONSTRUCTION MEASUREMENTS
PDF
1. UNIT -I ESTIMATION OF BUILDINGS.pdf
PPTX
ESTIOMATION BY LONG WALL AND SHORT WALL METHGOD
PPTX
Cost estimation
PPTX
Report costing
PPTX
Estimation Costing and Valuation Unit 1
PPT
Pgche centreline presentation
PPTX
estimation of a g+5 structure
PPTX
estimation,its types and methods
Methods of estimation - Estimation, Costing and Valuation Engineering
LONG WALL AND SHORT WALL METHOD-6
Long wall and short wall method 5
Methods of Taking out Quantities Estimating Costing and Valuation
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Cost estimation of a Building
2 Presentation on Estimation and its Methods.pptx
E.C.V detail estimate By centre line and Long wall short wall method
EC Unit 002 new (1).pdf
Quantity notes pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
Quiz Lecture 1,2,4 CONSTRUCTION MEASUREMENTS
1. UNIT -I ESTIMATION OF BUILDINGS.pdf
ESTIOMATION BY LONG WALL AND SHORT WALL METHGOD
Cost estimation
Report costing
Estimation Costing and Valuation Unit 1
Pgche centreline presentation
estimation of a g+5 structure
estimation,its types and methods
Ad

More from Ahmed Mohamed Hassan (Baasaay) (9)

PDF
Lecture 1 Engineering Economics Lecture 1.pdf
PDF
Lecture 2 Hospital Architecture course.pdf
PDF
Lecture 1 hospital architecture course.pdf
PDF
Lecture 5 cost estimation training course .pdf
PDF
Estimation and Costing course lecture 1.pdf
PDF
Lecture 2 project procurement and contract management .pdf
PDF
Lecture 1 Introduction to Procurement and contract Management Management - Co...
PPTX
Lecture 1 Introduction to statics Engineering Mechanics hibbeler 14th edition
PDF
Aci mix design very good
Lecture 1 Engineering Economics Lecture 1.pdf
Lecture 2 Hospital Architecture course.pdf
Lecture 1 hospital architecture course.pdf
Lecture 5 cost estimation training course .pdf
Estimation and Costing course lecture 1.pdf
Lecture 2 project procurement and contract management .pdf
Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to statics Engineering Mechanics hibbeler 14th edition
Aci mix design very good
Ad

Recently uploaded (20)

PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
composite construction of structures.pdf
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Well-logging-methods_new................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
DOCX
573137875-Attendance-Management-System-original
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
Geodesy 1.pptx...............................................
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
web development for engineering and engineering
PPTX
Welding lecture in detail for understanding
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Internet of Things (IOT) - A guide to understanding
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
composite construction of structures.pdf
CYBER-CRIMES AND SECURITY A guide to understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Well-logging-methods_new................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
573137875-Attendance-Management-System-original
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Geodesy 1.pptx...............................................
CH1 Production IntroductoryConcepts.pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
web development for engineering and engineering
Welding lecture in detail for understanding

Lecture 4 Professional training course .pdf

  • 1. Instructor: Er. Ahmed Baasaay LECTURE 4 ABRAR UNIVERSITY
  • 2. Estimation of a wall Prepare a detailed estimate of a wall of building from the given plan and section and general specifications
  • 7. Exercise Prepare a detailed estimate of a wall of building from the given plan and section and general specifications:-
  • 13. Methods of taking out quantities: The quantities like earthwork, foundation concrete, brickwork in plinth and superstructure etc., can be workout by any of the following two methods: 1. Long wall-short wall method. 2. Centre line method 3. Partly Centre line and long and wall method. ABRAR UNIVERSITY
  • 14. 1. Long Wall and Short Wall Method - For the calculating quantity of various construction item, long wall and short wall method is used. - For measuring the long wall and short wall the external out-to-out length of walls running in the longitudinal direction generally is considered as “long wall” . - While the in-to-in internal length of walls running in the transverse direction is called as “short wall” or “cross wall”. - For calculating quantity multiply the length into the breadth and height of the wall. - Length of Long Wall = Center to Center Length of wall + Half Breadth on One Side + Half Breadth on the Other Side. - Length of Short Wall = Centre to Centre Length – Half Breadth on One Side - Half Breadth on One other Side
  • 15. Explanation: Centre to center of long wall: 5m + 0.3/2 + 0.3/2 = 5.3m Centre to center of short wall: 4m + 0.3/2 + 0.3/2 = 4.3m Long wall = center to Centre length – 2 x half breadth = 5.3m + 2 x 0.3/2 = 5.6 Long wall = 5m + 2x0.3 = 5.6m Short wall = 4m Long wall= centre to centre of long wall + 2x half thickness of wall Long wall = 5.3m + 2 x 0.15m =5.6m Short wall= centre to centre of short wall – 2 x half thickness of wall • Short wall = 4.3m – 2 x 0.15 = 4m
  • 16. G.L • - Centre to Centre length of long wall = 5+ (1/2×0.30) + (1/2 x 0.30) = 5.30 m - Centre to Centre length of short wall = 4+ (1/2 x 0.30) + (1/2×0.30) = 4.30 m - Long wall = 5.3 + 2 x 0.45 = 6.2m - Short wall = 4.3m – 2 x 0.45 = 3.4m Calculate the following quantities: Earthwork in Foundation, Concrete in foundation, Brickwork in plinth and superstructure