2
Overview
•
•
•
•
•
•

3

Introduction
Application
LO/TO Program
Lockouts Types
Training
Contractors
Introduction
• Lockout/Tagout is a horizontal standard which
means all industries must comply.
– Estimated to prevent
• Approximately 120 fatalities
per year
• 28,000 serious injuries
• 32,000 minor injuries

4
Introduction
• LO/TO accidents are severe
– Average lost work days for
failure to LO/TO is 24 days
per injury
– 7% of all fatalities are related
to failure to LO/TO

5
Introduction
• Purpose of the Control of Hazardous
Energy Program:
– If a risk exists to any person on unexpected
start up, all protective measures are taken to
isolate all sources of hazardous energy.

6
Application
Application of Lockout/Tagout is required:
– when servicing and/or maintaining machines
or equipment,
– if it is necessary to remove a guard or bypass
safety device or interlock,
– if employee has the potential to be exposed to
material being processed or machine cycle.

7
Application
The Lockout/Tagout standard does not apply to:
– Cord and Plug Electrical Equipment
• plug under exclusive control of employee
performing servicing or maintenance
– Hot Tap operations..transmission and distribution
systems..water,gas, stream or petroleum products
• continuity of service essential
• shutdown of system is impractical
• documented procedures are followed
8
LO/TO Program
• Responsibility of the program is assigned to a
responsible person.
– lock acquisition
– safe work procedures
– training coordination
– contractor coordination
– assist supervisors in implementation and
enforcement of disciplinary actions for noncompliance
9
LO/TO Program
• Conduct periodic inspections
• Document changes in control
program as result of inspections
• Assist in development of specific
procedures
• Maintain program availability for
employees and interested persons
10
LO/TO Program
• Any employee who may be involved
in the operation, installation, service
or maintenance of any machine or
equipment that has potential for
release of hazardous energy is
authorized to Lockout/Tagout if he or
she is trained.
11
LO/TO Program
Authorized Employee
• Person who locks
out or tags out
machine
• Appendix of the
LO/TO Program
contains a list of
Authorized
Employees
12
LO/TO Program
Authorized

13
LO/TO Program
• Affected employees are those employees
whose job requires them to operate
machine or process on which
maintenance or service is being
performed.
– Need to be notified on shutdown and start up.

14
Lockouts
• Individual Lockout:
– Shut down, control off, lockout
– Stored energy dissipated, isolated
– Operate controls for operation, verify OFF
– Work may proceed
– If shift changes, individual LO/TO repeated by
next shift

15
Lockouts
• Individual restoration to service:
– Replace all guards and safety devices
– Notify all personnel/affected employees
– Vents and bleeders closed, blinds removed,
blocks and tags removed
– Each employee removes his or her lock

16
Lockouts
• Group Lockout:
– Same as individual lockout except
• Operations personnel will place keys in lock box…
and fill out “Isolation List for Group Lockout”
• Operations turns equipment over to Maintenance
Department
• Maintenance will place their personal lock and
complete work
• update “Isolation List”
17
Lockouts
• Group restoration to service:
– Maintenance - replaces all guards and safety
devices
– Maintenance - notifies all Personnel/Affected
Employees
– Vents and bleeders closed, blinds removed,
blocks and tags removed
– Maintenance and Operations - each
employee removes his or her lock
18
Lockouts
• Long Term Safety Lockout:
– Extended period of time… discontinued ...not
longer part of operation
– Long term locks available for use by the
responsible person

19
Training
Additional Training for Authorized Persons
– When implementation is required.
– Recognition of hazardous energies.
– Returning equipment to service.
– If questions on application specific actions to
be taken.

20
Training
Additional training
required if . . .
– new equipment is
introduced
– changes in LO/TO
equipment
– periodic audit
identifies need

21
MCC

22
Contractors
• Exchange of LO/TO procedures
• Agreement of procedures before
work begins
• Discipline of contractor and/or
contractor employee(s) for failure
to LO/TO
23
DANGER!

24
Questions?

25

More Related Content

PPT
Aa loto53013
PPS
Aa loto53013b
PDF
Guide lockout-tagout information and products
PDF
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
PPT
Lockout tagout
PPT
Lock Out / Tag Out
PDF
Lockout/Tagout Training (Contractor Version)
PPT
Osha Lockout Tagout
Aa loto53013
Aa loto53013b
Guide lockout-tagout information and products
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
Lockout tagout
Lock Out / Tag Out
Lockout/Tagout Training (Contractor Version)
Osha Lockout Tagout

What's hot (12)

PDF
Lockout/Tagout Training (OEM Version)
PPT
Lockout/Tagout
PPT
Control of Hazardous Energy
PPT
Lockout tagout
PDF
OSHA Lockout / Tagout Rule
PDF
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
PPT
Lockout/Tagout
PDF
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
PPT
Pchatelot300908
 
PPS
Lockout tagout standard
PDF
Operations integritydesignconstructioncommissioning
PPTX
Lockout tagout standard
Lockout/Tagout Training (OEM Version)
Lockout/Tagout
Control of Hazardous Energy
Lockout tagout
OSHA Lockout / Tagout Rule
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Lockout/Tagout
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
Pchatelot300908
 
Lockout tagout standard
Operations integritydesignconstructioncommissioning
Lockout tagout standard
Ad

Viewers also liked (8)

PPTX
INTERVIEWS OF WOMEN WHO HAVE MADE A DIFFERENCE IN OUR SOCIETY
PPTX
Electrical Hazards and Safety Measures
PDF
Top 20 Safety Quotes To Improve Your Safety Culture
PDF
Top 10 safety slogans near miss
PPTX
Safety Quotes
PPTX
Industrial safety.ppt
PPT
Industrial hazards and safety measures
PPT
Industrial safety
INTERVIEWS OF WOMEN WHO HAVE MADE A DIFFERENCE IN OUR SOCIETY
Electrical Hazards and Safety Measures
Top 20 Safety Quotes To Improve Your Safety Culture
Top 10 safety slogans near miss
Safety Quotes
Industrial safety.ppt
Industrial hazards and safety measures
Industrial safety
Ad

Similar to Lockout tagout2 (20)

PPT
Lock Out-Tag Out.ppt
PDF
Overcoming The Challenges of Implementing a Lockout Program
PDF
LOTO Training.pdf
PDF
LOCK OUT _ TAG OUT .pdf Lock Out Tag out is a safe procedure used in industry.
PPT
LOTO_2b2-on-hazardous-energy-trainin.ppt
PDF
Written Programs.pdf
PPTX
LOTO & ENERGY ISOLATION.pptx
PDF
Panduit Lockout Tagout For Workplace Electrical Safety - 'Why do I Need Locko...
PDF
Engineering LOTO of how to apply LOTO at work place
PPTX
SnackCraft LOTO Authorized Training.pptx
PPTX
LOTO Safety Training Presentation. pptx
PPTX
Loto presentation
PPT
Lockout Tag power point for safety +.ppt
PPTX
it is log tag out sytem to be used while maintence of CHP/ HEMM
PDF
Understanding Lockout Tagout_ A Comprehensive Guide to Saving Lives at the Wo...
PPT
Lockout-Tagout 2023.ppt
PDF
Lockout _ Tagout Electrical Safety.pdf lotos systems
PPT
KHF-HSE-TI-001-LOTO Training for LOTO training
PDF
LOTO 2
PPTX
Mainteance Program
Lock Out-Tag Out.ppt
Overcoming The Challenges of Implementing a Lockout Program
LOTO Training.pdf
LOCK OUT _ TAG OUT .pdf Lock Out Tag out is a safe procedure used in industry.
LOTO_2b2-on-hazardous-energy-trainin.ppt
Written Programs.pdf
LOTO & ENERGY ISOLATION.pptx
Panduit Lockout Tagout For Workplace Electrical Safety - 'Why do I Need Locko...
Engineering LOTO of how to apply LOTO at work place
SnackCraft LOTO Authorized Training.pptx
LOTO Safety Training Presentation. pptx
Loto presentation
Lockout Tag power point for safety +.ppt
it is log tag out sytem to be used while maintence of CHP/ HEMM
Understanding Lockout Tagout_ A Comprehensive Guide to Saving Lives at the Wo...
Lockout-Tagout 2023.ppt
Lockout _ Tagout Electrical Safety.pdf lotos systems
KHF-HSE-TI-001-LOTO Training for LOTO training
LOTO 2
Mainteance Program

Recently uploaded (20)

PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
IGGE1 Understanding the Self1234567891011
PDF
International_Financial_Reporting_Standa.pdf
PDF
Trump Administration's workforce development strategy
PPTX
20th Century Theater, Methods, History.pptx
PPTX
Introduction to pro and eukaryotes and differences.pptx
PPTX
Computer Architecture Input Output Memory.pptx
PDF
Empowerment Technology for Senior High School Guide
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
DOCX
Cambridge-Practice-Tests-for-IELTS-12.docx
PDF
My India Quiz Book_20210205121199924.pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Complications of Minimal Access-Surgery.pdf
PPTX
TNA_Presentation-1-Final(SAVE)) (1).pptx
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
Weekly quiz Compilation Jan -July 25.pdf
Practical Manual AGRO-233 Principles and Practices of Natural Farming
202450812 BayCHI UCSC-SV 20250812 v17.pptx
IGGE1 Understanding the Self1234567891011
International_Financial_Reporting_Standa.pdf
Trump Administration's workforce development strategy
20th Century Theater, Methods, History.pptx
Introduction to pro and eukaryotes and differences.pptx
Computer Architecture Input Output Memory.pptx
Empowerment Technology for Senior High School Guide
Chinmaya Tiranga quiz Grand Finale.pdf
Cambridge-Practice-Tests-for-IELTS-12.docx
My India Quiz Book_20210205121199924.pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Complications of Minimal Access-Surgery.pdf
TNA_Presentation-1-Final(SAVE)) (1).pptx
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf

Lockout tagout2

  • 2. Worker Training of Electrical Hazards Including Arc Flash SH-16614-07 This material was produced under grant number SH-16614-07 from the Occupational Safety and Health Administration, U.S. Department of Labor. It does not necessarily reflect the views or policies of the U.S. Department of Labor, nor does mention of trade names, commercial products, or organizations imply endorsement by the U.S. Government. 2
  • 4. Introduction • Lockout/Tagout is a horizontal standard which means all industries must comply. – Estimated to prevent • Approximately 120 fatalities per year • 28,000 serious injuries • 32,000 minor injuries 4
  • 5. Introduction • LO/TO accidents are severe – Average lost work days for failure to LO/TO is 24 days per injury – 7% of all fatalities are related to failure to LO/TO 5
  • 6. Introduction • Purpose of the Control of Hazardous Energy Program: – If a risk exists to any person on unexpected start up, all protective measures are taken to isolate all sources of hazardous energy. 6
  • 7. Application Application of Lockout/Tagout is required: – when servicing and/or maintaining machines or equipment, – if it is necessary to remove a guard or bypass safety device or interlock, – if employee has the potential to be exposed to material being processed or machine cycle. 7
  • 8. Application The Lockout/Tagout standard does not apply to: – Cord and Plug Electrical Equipment • plug under exclusive control of employee performing servicing or maintenance – Hot Tap operations..transmission and distribution systems..water,gas, stream or petroleum products • continuity of service essential • shutdown of system is impractical • documented procedures are followed 8
  • 9. LO/TO Program • Responsibility of the program is assigned to a responsible person. – lock acquisition – safe work procedures – training coordination – contractor coordination – assist supervisors in implementation and enforcement of disciplinary actions for noncompliance 9
  • 10. LO/TO Program • Conduct periodic inspections • Document changes in control program as result of inspections • Assist in development of specific procedures • Maintain program availability for employees and interested persons 10
  • 11. LO/TO Program • Any employee who may be involved in the operation, installation, service or maintenance of any machine or equipment that has potential for release of hazardous energy is authorized to Lockout/Tagout if he or she is trained. 11
  • 12. LO/TO Program Authorized Employee • Person who locks out or tags out machine • Appendix of the LO/TO Program contains a list of Authorized Employees 12
  • 14. LO/TO Program • Affected employees are those employees whose job requires them to operate machine or process on which maintenance or service is being performed. – Need to be notified on shutdown and start up. 14
  • 15. Lockouts • Individual Lockout: – Shut down, control off, lockout – Stored energy dissipated, isolated – Operate controls for operation, verify OFF – Work may proceed – If shift changes, individual LO/TO repeated by next shift 15
  • 16. Lockouts • Individual restoration to service: – Replace all guards and safety devices – Notify all personnel/affected employees – Vents and bleeders closed, blinds removed, blocks and tags removed – Each employee removes his or her lock 16
  • 17. Lockouts • Group Lockout: – Same as individual lockout except • Operations personnel will place keys in lock box… and fill out “Isolation List for Group Lockout” • Operations turns equipment over to Maintenance Department • Maintenance will place their personal lock and complete work • update “Isolation List” 17
  • 18. Lockouts • Group restoration to service: – Maintenance - replaces all guards and safety devices – Maintenance - notifies all Personnel/Affected Employees – Vents and bleeders closed, blinds removed, blocks and tags removed – Maintenance and Operations - each employee removes his or her lock 18
  • 19. Lockouts • Long Term Safety Lockout: – Extended period of time… discontinued ...not longer part of operation – Long term locks available for use by the responsible person 19
  • 20. Training Additional Training for Authorized Persons – When implementation is required. – Recognition of hazardous energies. – Returning equipment to service. – If questions on application specific actions to be taken. 20
  • 21. Training Additional training required if . . . – new equipment is introduced – changes in LO/TO equipment – periodic audit identifies need 21
  • 23. Contractors • Exchange of LO/TO procedures • Agreement of procedures before work begins • Discipline of contractor and/or contractor employee(s) for failure to LO/TO 23

Editor's Notes

  • #5: Estimated to: Cost about 135 million each per year Affect approximately 631,000 employers Affect approximately 39 million employees
  • #6: This is for FY 1988, quote for LO/TO preamble to the LO/TO Standard effective Oct. 31, 1989 National Average lost work days per injury are 14 days 2% of all non-fatal injuries are related to failure to LO/TO
  • #7: The program establishes minimum requirements for energy isolating sources. If employees or contractor employees perform any installation, service, or maintenance where the unexpected activation, start up, or release of stored energy could represent risk to any employees or equipment, all protective measures are to be taken to isolate all sources of hazardous energy.
  • #16: Isolated by breaking joint, placing blind Operating controls for operation, return control to off