SlideShare a Scribd company logo
Management, Cost, and Schedule Reviewfor the Deimos Impact & Observation Spacecraft (DIOS)
Mission
Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney, David Habashy, Brian Hardie,
Brandon Hing, Zujia Huang, Sung Kim, and Jonathan Saenger
Georgia Institute of Technology, Atlanta, GA, 30332
This document discusses the Management, Cost, and Schedule Review for the Deimos
Impact & Observation Spacecraft of the DIOS mission and provides the charts and tables
to that show the mission is able to meet its key requirements. The project cost covers both
the staffing the personnel, as well at the cost of the cubesats components. The project
schedule is included and is divided into phases A-F.
Nomenclature
CBE Currently Best Estimate
CDR Critical Design Review
CERR Critical Events Readiness Review
DR Decommissioning Review
DRR Disposal Readiness Review
FAD Formulation Agreement Document
MCR Mission Concept Review
MDR Mission Definition Review
MEV Maximum Expected Value
MRR Mission Readiness Review
ORR Operational Readiness Review
PDR Preliminary Design Review
SIR System Integration Review
SRR System Requirements Review
ΔVi Velocity change for initial burn, m/s
ΔVc Velocity change for impactor burn, m/s
ΔVo Velocity change for observer burn, m/s
ΔVT Total velocity change, m/s
I. Introduction
The objective of the Deimos Impact & Observation Spacecraft (DIOS) Mission is to determine the origin and
composition of Mars’ moon Deimos. Current hypotheses from NASA’s decadal survey speculate that Deimos is
either an asteroid captured from the asteroid belt or accreted from a collision between Mars and another large body.
According to NASA’s Vision and Voyages for Planetary Science in the Decade 2013-2022, Deimos plays an
important role in the future exploration of Mars, especially if it is related to volatile-rich asteroids. If it is, Deimos
may be a surviving representative of a family of bodies from the outer asteroid belt that reached the inner solar
system and delivered volatiles and organics to the accreting terrestrial planets.1 During the course of this mission,
DIOS will analyze the surface and sub-surface composition of Deimos to definitively determine the moon’s origin.
In order to consider the mission to be considered a complete success, the following mission requirements must
be met:
1. The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for the
CubeSat Spectrometer to detect
2. The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including
oxygen, carbon dioxide, carbon monoxide, water, and ammonia
3. The CubeSat shall analyze the plume with a spectrometer and determine the 1.3µm absorption levels, as
well as the absorption levels of volatiles
This document discusses the trajectory design that will allow DIOS to achieve a flyby of Deimos while providing
the optimum velocities to achieve the mission requirements.
II. Key Requirements
The two major design goals of the spacecraft are to generate a plume of Deimos subsurface material, and to
relay the composition of the material to Earth. The driving requirements serve to fulfill these two goals either
directly or secondarily.
1. Shall be ready for launch by July 20th 2020
2. Shall arrive at Deimos between February 16th 2021 and February 17th 2021
3. Shall not exceed 5.6 million dollars in total cost
4. Shall have an acceptable amount of risk.
III. Project Management
Figure 1. Work Breakdown Structure
The work breakdown structure (WBS) is created by grouping the spacecraft subsystems and development
phases.The WBS is not organized chronologically. Project management facilitates the development of the
spacecraft subsystems which are then put togetherby the integration supervisor.The testing supervisormakes sure
the completed spacecraft meets the launch requirements. The launch preparation supervisormakes sure the
completed, tested spacecraft is ready and present for launch. The post-launch supervisoranalyzes the data once the
mission is complete. The purple box represents a post-doctoralassociate. The red boxes represent 4 graduate
students.The yellow boxes represent 8 undergraduate students.The green boxes represent the general tasks that the
higher-up boxes are responsible for. Below the green boxes would be detailed descriptions of what the green boxes
entail. An example would be “Gather propulsion requirements from the trajectory group. Analyze available
propulsion systemoptions.Perform trade studies for propulsion systems based upon deltaV, mass, size, power, etc.”
The cost in terms of work breakdown structure elements is detailed in Table 1. The majority of costs for the
mission stems from project management, specifically facilities and administrative fees, and project system
engineering. Facilities and administrative fees consists ofwage and benefits for all personnelas well as tuition and
health care for graduate students.Project systems engineering contains the majority of the cubesat components
necessary for the mission.
Table 1. Cost by WBS Elements
IV. Project Cost
Personnel
The Research and Development (R&D) team of DIOS mission consists of1 principal investigator(PI), 1 post
doctoral associate,4 graduate students and 8 part-time undergraduate students,giving a total team size of 13. The
principal investigatoracts as the project leader and primary contact.The post doctoral associate acts as an executive
manager that coordinates work between graduate and undergraduate students and assist themwith professional
experience. The four graduate students are in charge of project systems engineering, spacecraft flight systems
engineering, science payload engineering, and mission systems engineering respectively, with the undergraduate
students sharing theirworkload under guidance.
The PI requires a base salary of $113,381 in FY 2017 when the project starts.The salary increases on a predicted 3%
rate per year, until FY 2020 when the development phase ends.The post doctoralassociate requires a base salary of
estimated $45,000 in FY 2017 and a 1.5% raise in every succeeding year.. The four graduate students require a base
salary of estimated $26,000 each in FY 2017, giving a total of $104,000, plus a 1.5% raise every year. The
undergraduate students,working part-time and for course credits, are not paid.
The PI and post doctoralassociate also require fringe benefits at a rate of 28.8% in FY 2017, a combined amount of
$45.614. Therefore, total salaries and fringe benefits in FY 2017 is $307,995. Total salaries and fringe benefits over
4 years is $1,288,535.
Equipment
The equipment required for the DIOS mission are primarily on-board equipment and components,and mostly
appears as non-recurring cost.Only equipment with cost close to or exceeding $5,000 are considered significant for
discussion. There are 8 major on-board components of significant cost, covering C&DH, ADCS, power, propulsion,
communication and scientific payload. Table 2 lists those components and their costs.The costs oftwo propulsion
systems,Vacco MiPS and Rocketdyne MPS-130, have not been disclosed by manufacturers, and are estimated
values based on similar products.All other costs are given by manufacturers or providers.
Table 2. Equipment Cost Profile
Equipment Quantity Cost
1. IRIS 1 $150,000.00
2. BCT XACT 2 $290,246.00
3. VACCO End-Mounted MiPS 1 $50,000.00
4. Argus 1000 IR Spectrometer 1 $49,500.00
5. Clyde Space 2U Deployable Array 4 $40,000.00
6. CS High Power Bundle C:
EPS + 80 Whr Battery 2 $38,600.00
7. Rocketdyne MPS-130 1 $35,000.00
8. Nanomind A3200 1 $10,000.00
9. Cube Computer 1 $4,970.00
10. Total Equipment 14 $668,316.00
Travel
Only full-time investigators,including PI, post doctoral associate and graduate students(6personnels total)are
accounted for in travel and conference. The expected location of the conference (Aerospace Conference) is Big Sky,
Montana,and the expected location of design review is at JPL in Pasadena,California. Both trips are expected to
last one week. Hotels nearby the locations of interest provided quotes for the trip. Delta Airlines was used to
estimate transportation costs foreach member. The total amount for travel costs per year is $23,450 for the entire
mission.
Trainee/Participant Costs
There were no trainees or participants associated with the mission. All necessary testing deals with component
testing.The mission does not require any human to physically accompany the cubesat.Therefore no costs associated
with trainees or participants (stipend, tuition, etc.) were accounted for.
Other Direct Costs
Other direct costs mainly include publication/documentation cost, miscellaneous terms associated to graduate
students and Deep Space Network operation cost.The publication and documentation cost is estimated at $5,000
and is a non-recurring cost term. For graduate students,health insurance and tuition are major costs.The health
insurance is rated at 4.7% in FY 2017, a total of $4,888 for 4 students.The tuition is rated at $1,489 per person per
month. The combined total is $76,360 in FY17. The health insurance increases by 1.5% per year until project ends
in FY 2020. The Deep Space Network cost was calculated using an equation provided by NASA.
The equation above calculates the aperture fees for DSN. The aperture fee coverage is detailed in Table 3. The DSN
cost came out to be $2,114.00 per year. This cost is less than $5,000, but was included due to its crucial role in the
mission.
Table 3. Aperture Fee Coverage for DSN
Summary
The total cost for each year is listed below in Table 4. The non-recurring equipment cost are counted as cost for first
year(FY 2017). Counting contingency for all costs,the total cost over four years is $2,654,874, less than half of the
$5.3M limit. The full cost profile can be found in the appendix.
Table 4. Overall mission cost over four years.
Year 2017 2018 2019 2020 Total
Total Cost $1,083,234 $395,855 $428,973 $438,931 $2,346,995
Total Cost with Contingency $1,161,583 $489,028 $500,607 $512,533 $2,663,753
V. Project Schedule
Figure 2. Project Life Cycle (Note: Red Triangles - Required Review)2
Pre-Phase A
Figure 3. Pre-Phase A Gantt Chart
Pre-Phase A will consist of concept studies relating to the mission. This may include refining the mission concept,
preliminary mission architecture design, and assessing technology and engineering development. Using these, staff
and infrastructure requirements will be determined for the project. With the work done in Pre-Phase A, a
Formulation Agreement Document (FAD) will be developed as a tool for communicating and negotiating the
project’s funding and schedule requirements for mission development. Before entering Phase A of the project, a
Mission Concept Review (MCR) will be conducted to ensure life-cycle review objectives and expected maturity
states have been met. 4
Pre-Phase A will last approximately 2 months.
Phase A
Figure 4. Phase A Gantt Chart
Phase A is the first phase of project formulation. Within this step, concept and technology development activities
will be performed to develop a mission architecture that meets programrequirements and constraints for the p roject.
This will ensure the mission definition and plans are mature enough to begin Phase B.
The activities in this phase include:
· Developing/defining project requirements to the systemlevel
· Developing systemarchitecture
· Developing cost and schedule estimates for the project
· Identifying and mitigating development risks
· Updating staffing/infrastructure requirements
In this phase, two reviews will be conducted. In the middle of this phase, a System Requirements Review (SRR)
will be performed to evaluate whether the performance requirements of the system satisfy the program’s
requirements of the project. At the end of Phase A, a Mission Definition Review (MDR) will be conducted to
determine if the maturity of the mission definition is sufficient to begin Phase B. 4
Phase A will last 5 months.
Phase B
Figure 5. Phase B Gantt Chart
Phase B is the final phase of project formulation and deals with the preliminary design and technology completion
activities. In this phase, technology development will be completed, heritage hardware and software assessments
will be performed, engineering prototyping will be conducted, and risk-mitigation activities will be identified.
Furthermore, mission objectives, requirements, cost estimates, and schedule estimates will be updated.
At the end of this phase, a Preliminary Design Review (PDR) will be conducted. The PDR will consist of
evaluating the planning, cost, and schedule developed during Formulation and assessing the preliminary design’s
compliance with the mission requirements.4
Phase B will last approximately 8 months.
Phases C-D
Phases C and D are the steps in which project implementation is conducted. In Phase C, final systemdesigns will be
completed and documented, and fabrication of test and flight architecture will begin. Phase D consists of system
assembly, integration, and testing various systempieces, while performing verification and validation on products as
they are integrated. During this phase, hardware and software documentation will be finalized, issues from testing
will be resolved, and the systemwill be prepared for launch and shipment.
Figure 6. Phase C Gantt Chart
In Phase C, two reviews will be conducted, the Critical Design Review (CDR) and the System Integration Review
(SIR). The objective of the CDR is to evaluate the integrity of the project design and the ability of the system to
meet mission requirements with appropriate margin and risk. The CDR is performed in the middle of Phase C. The
SIR will evaluate the readiness of the project to begin assembly, integration, and testing.4 The SIR is performed at
the end of Phase C.
Figure 7. Phase D Gantt Chart
In Phase D, the Operational Readiness Review (ORR) and Mission Readiness Review (MRR) will be conducted.
The ORR is used to evaluate the readiness of the project to assemble, integrate, and test flight systems. The ORR is
performed in the middle of Phase D. The MRR is used to assess the pre-flight operational readiness of the project.
This will insure there are no problems with the flight systems and all personnel and infrastructure are ready to
support launch. The MRR is performed at the end of Phase D.4
Phase C will last around 15 months and Phase D will last around 11 months.
Phase E-F
Figure 8. Phase E Gantt Chart
Phase E is the launch, operations, and sustainment of the mission. The parameters for this phase are determined by
the flight schedule. In this phase, a Critical Events Readiness Review (CERR), and Decommissioning Review (DR)
are performed. The CERR will evaluate the readiness of the project to execute a critical event during flight
operations. The DR (towards the end of the mission) will evaluate the readiness of the project to conduct closeout
activities.4
Figure 9. Phase F Gantt Chart
Phase F deals with the decommissioning of the mission. This phase begins with a Disposal Readiness Review
(DRR), in which the readiness of the project for disposal will be evaluated.4 In this stage, final archival of data and
spacecraft closeout will be performed.
Phase E will last under 9 months and Phase F will last 1 month.
Critical Path
Figure 10. Critical Path
The critical path of the project shows that the minimum duration of the project will be 50 months. Each of the
activity times are broken down in the Phase summaries above. This path does not include schedule margin, which is
discussed below.
Schedule Margin
The planned activities of this mission will last 52 months, providing 8 months of schedule margin. This will provide
sufficient margin for activities that may take more time than expected such as assembly, integration, and testing.
The schedule margin rate is 0.133.
VI. Project-level Risk Assessment and Mitigations
1. Propulsion isn’t ready in time
2. Production schedule surpasses time allotted until launch
3. Components don’t meet testing standards
4. Costs are higher than expected
5. Loss of satellite upon launch
Figure 11. Project-level risk assessment matrix.
There are five major project-level risks to be considered in risk analysis,the likelihood and consequences ofwhich
are summarized in figure 11.
An overdue in propulsion systemdelivery is mission-critical, particularly for the Rocketdyne MPS-130 propulsion
module. The high delta-V capability is essential for the success ofDIOS mission; however, the MPS-130 has been
in test phase for a long time without anticipated date of availability. The Vacco cold gas propulsion module, on the
other hand,has samples already available and is generally higher in TRL than the MPS-130. The cold gas
propulsion is also less mission critical and can be replaced by othersimilar products should the delivery fail to
achieve,
An overdue in spacecraft production also leads to direct failure of mission, since the launch vehicle and launch date
is not undercontrol of the DIOS mission team. The likelihood of an project overdue is to the best reduced by setting
the end date of Phase D(systemassembly, integration and testing) at least six months prior to launch, giving a
generous margin for any delay.
A loss of satellite upon launch will lead to direct failure of mission, but the possibility is low given the very high
reliability of launch vehicle(Atlas V), with only one partial failure per 66 flights. The sub-model Atlas V-541 used
for Mars 2020 mission has three successfullaunches to date with no failure. Should a launch vehicle accident occur
and the spacecraft is lost, cost would be reimbursed partially by insurance.
Unsatisfactory quality of spacecraft components threatens the reliability of spacecraft and thus the possibility of
mission success.However, many of the components are off-the-shelf and have been tested by other successful
missions. The component in development, such as the MPS-130, will be manufactured by top-tier companies, and
thus the chances of component failing standards are low. Other structuralparts, including frame, wire and
thermal/radiation protection are held to relatively low standards,given the somewhat short(less than one year)
lifespan of the spacecraft.In addition, redundant testing will be performed to guarantee readiness of all compon ents;
extra testing and possible fixing of parts are accounted for in schedule design.
A cost overdue is likely, given the unpredictability of project progress.For instance, increase of cost will occur if
components are replaced, duplicates are used for testing,or if salary level increases over the year at a rate higher
than anticipated. However, reasonable cost overdue are covered in contingency and will not be impeding the
mission. Should cost rise above the maximum anticipated level, it is most likely still within the $5.3M limit and thus
additional funding can be acquired.
VII. Descopes
If we need to save on costs or time, there are several different options for descoping.The first would be to reduce
the amount of testing for each part. This would reduce the amount of time for building the components for the
satellite, which reduces the overall build time. It also would decrease the costs associated to test the components.
However, this would increase the risk failure of the components.
Anotherdescope option would be to reduce the amount of employees. This would decrease the total cost by
reducing the amounts paid due to salaries. The downside to this option is that it would increase the production time,
since there would be fewer people to work on the components.This could also increase the risk of individual
components.
A third option would be to reduce the amount of trips to conferences and design review trip. This would reduce the
cost that do not apply directly to the manufacturing of the satellite. However, this would reduce the amount of
critique and feedback received. Also, mission exposure would be far lower.
VIII. Conclusion.
The Management, Cost, and Schedule Review for the Deimos Impact & Observation Spacecraft of the
DIOS mission and provides the charts and tables to that show the mission is able to meet its key
requirements. The project cost covers both the staffing the personnel, as well at the cost of the cubesats
components.The total estimated project cost with contingency falls well below the monetary limit given
to each team. The project schedule is included and is divided into phases A-F.
IX. References
1K.M. Brumbaugh, The Metrics of Spacecraft Design Reusability and Cost Analysis as Applied to Cubesats,2012.
2
Chapter2. NASA Life Cycles for Space Flight Programs and Projects. (2012, August 14). Retrieved from NASA
Procedural Requirements:
http://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7120_005E_&page_name=Chapter2
3
NASA's Mission Operations and Communications Services, NASA Deep Space. (2014).
https://deepspace.jpl.nasa.gov/files/dsn/6_nasa_mocs_2014_10_01_14.pdf (accessed November 5, 2016).
4(2014). NASA Space Flight Program and Project Management Handbook. NASA, Hampton. Retrieved from
https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20150000400.pdf
5
Preparing a Budget,Georgia Tech Office of Sponsored Programs. http://www.osp.gatech.edu/budget (accessed
November 5, 2016).
X. Appendix
Category Quantity
Funds
Requested
Year
2
Year
3
Year
4 Contingency
A. Senior Personnel - - - - - -
1. Principal Investigator (PI) 1 $113,381.00
$116,782
.43
$120,285
.90
$123,894
.48 20.00%
2. Co-PI 0 $0.00 $0.00 $0.00 $0.00
3. Co-PI 0 $0.00 $0.00 $0.00 $0.00
4. Co-PI 0 $0.00 $0.00 $0.00 $0.00
5. Others 0 $0.00 $0.00 $0.00 $0.00
6. Total Senior Personnel 1 $113,381.00
$116,782
.43
$120,285
.90
$123,894
.48
B. Other Personnel - - - - -
1. Post Doctoral Associates 1 $45,000.00
$46,350.
00
$47,740.
50
$49,172.
72 20.00%
2. Other Professionals 0 $0.00 $0.00 $0.00 $0.00
3. Graduate Students 4 $104,000.00
$107,120
.00
$110,333
.60
$113,643
.61 20.00%
4. Undergraduate Students 8 $0.00 $0.00 $0.00 $0.00
5. Secretarial - Clerical 0 $0.00 $0.00 $0.00 $0.00
6. Others 0 $0.00 $0.00 $0.00 $0.00
7. Total Other Personnel 13 $104,000.00
$107,120
.00
$158,074
.10
$162,816
.32
TOTAL SALARIES AND WAGES - $262,381.00
$270,252
.43
$278,360
.00
$286,710
.80
C. Fringe Benefits - $45,613.73
$46,982.
14
$48,391.
60
$49,843.
35
TOTAL SALARIES AND WAGES
FRINGE BENEFITS - $307,994.73
$317,234
.57
$326,751
.60
$336,554
.16
D. Equipment - - - - -
1. IRIS 1 $150,000.00 $0.00 $0.00 $0.00 10.00%
2. BCT XACT 2 $290,246.00 $0.00 $0.00 $0.00 5.00%
3. VACCO End-Mounted MiPS 1 $50,000.00 $0.00 $0.00 $0.00 15.00%
4. Argus 1000 IR Spectrometer 1 $49,500.00 $0.00 $0.00 $0.00 5.00%
5. Clyde Space 2U Deployable
Array 4 $40,000.00 $0.00 $0.00 $0.00 5.00%
6. CS High Power Bundle C: 2 $38,600.00 $0.00 $0.00 $0.00 5.00%
EPS + 80 Whr Battery
7. Rocketdyne MPS-130 1 $35,000.00 $0.00 $0.00 $0.00 15.00%
8. Nanomind A3200 1 $10,000.00 $0.00 $0.00 $0.00 5.00%
9. Cube Computer 1 $4,970.00 $0.00 $0.00 $0.00 5.00%
10. Total Equipment 14 $668,316.00 $0.00 $0.00 $0.00 -
E. Travel - - - - - -
1. Conference Trip Entrance 6 $8,400.00
$8,400.0
0
$8,400.0
0
$8,400.0
0 10.00%
2. Design Review Trip 6 $0.00 $0.00 $0.00 $0.00 0.00%
3. Hotels 6 $3,150.00
$3,150.0
0
$3,150.0
0
$3,150.0
0 10.00%
4. Transportation 6 $11,900.00
$11,900.
00
$11,900.
00
$11,900.
00 10.00%
5. Total Travel Costs $23,450.00
$23,450.
00
$23,450.
00
$23,450.
00 -
F. Trainee/Participant Costs - - - - - -
1. Stipends 0 $0.00 $0.00 $0.00 $0.00 0.00%
2. Tuition & Fees 0 $0.00 $0.00 $0.00 $0.00 0.00%
3. Trainee Travel 0 $0.00 $0.00 $0.00 $0.00 0.00%
4. Other 0 $0.00 $0.00 $0.00 $0.00 0.00%
5. Total Participants 0 $0.00 $0.00 $0.00 $0.00 0.00%
G. Other Direct Costs - - - - - -
1. Materials and Supplies - $0.00 $0.00 $0.00 $0.00 0.00%
2. Publication/Documentation 1 $5,000.00 $0.00 $0.00 $0.00 5.00%
3. Consultant Services 0 $0.00 $0.00 $0.00 $0.00 0.00%
4. Computer Services 0 $0.00 $0.00 $0.00 $0.00 0.00%
5. Subcontracts 0 $0.00 $0.00 $0.00 $0.00 0.00%
6. Others (Grad Healthcare,
Tuition) 4 $76,360.00
$76,506.
64
$76,657.
68
$76,813.
25 5.00%
7. Deep Space Network Costs 1 $2,114.00
$2,114.0
0
$2,114.0
0
$2,114.0
0 5.00%
8. Total Direct Costs - $83,474.00
$78,620.
64
$78,771.
68
$78,927.
25 -
TOTAL YEARLY COST - $1,083,234.73
$395,855
.21
$428,973
.28
$438,931
.41 -
TOTAL ESTIMATED PROJECT
COST
$2,346,994.6
3 - - - - -
TOTAL YEARLY COST WITH
CONTINGENCY - $1,161,583.70
$489,02
8.16
$500,60
7.19
$512,53
3.60 -
TOTAL COST WITH
CONTINGENCY
$2,663,752.6
5 - - - - -
Management, Cost, and Schedule Paper for Project A.D.I.O.S.

More Related Content

PPTX
Lecture 06 project_cost_management
PDF
Cleopatra Enterprise Added Value
PDF
Legionellen Lund Universität
PDF
Network stafford alumni
PDF
A Dramatic Broadband Rescue_Broadband Communities Property of the Month Artic...
PDF
RegistrationCard130415055205raviv0208
DOCX
Mission Concept Paper for Project A.D.I.O.S.
PPTX
PMP Training Project Cost Management Part 1
Lecture 06 project_cost_management
Cleopatra Enterprise Added Value
Legionellen Lund Universität
Network stafford alumni
A Dramatic Broadband Rescue_Broadband Communities Property of the Month Artic...
RegistrationCard130415055205raviv0208
Mission Concept Paper for Project A.D.I.O.S.
PMP Training Project Cost Management Part 1

Viewers also liked (16)

PPT
Social media and relationship development for sales
PDF
ملاحظات مهمة عن تعجيل المشاريع
PPTX
Final Presentation for Project A.D.I.O.S.
PPTX
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
PPTX
Project Cost Management
PPTX
Qs Approach To Project Cost
PPTX
Total Cost Management - Synergy between Cost Estimating and Project Controls
DOCX
hai zindigi auro ke kaam ana per speech
PPTX
PMBoK, discussion #5: Project Cost Management
DOC
[3] rpp sd kelas 6 tokoh dan penemu
PPTX
project cost management
PDF
Cost Estimation in Project Management - Case of Solar Assisted Water Pump
PPT
ادارة تكلفة المشروع
DOCX
Martin Farrow - Resume.2
PDF
Project Management C8 -cost_estimation_and_budgeting
DOC
MEMO-13-839_EN
Social media and relationship development for sales
ملاحظات مهمة عن تعجيل المشاريع
Final Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Project Cost Management
Qs Approach To Project Cost
Total Cost Management - Synergy between Cost Estimating and Project Controls
hai zindigi auro ke kaam ana per speech
PMBoK, discussion #5: Project Cost Management
[3] rpp sd kelas 6 tokoh dan penemu
project cost management
Cost Estimation in Project Management - Case of Solar Assisted Water Pump
ادارة تكلفة المشروع
Martin Farrow - Resume.2
Project Management C8 -cost_estimation_and_budgeting
MEMO-13-839_EN
Ad

Similar to Management, Cost, and Schedule Paper for Project A.D.I.O.S. (20)

PDF
Leo final report
PPT
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
PPT
Impediments to Interagency Cooperation on Space and Earth Science Missions
PPTX
Investments in the Future: NASA's Technology Programs
PDF
DANDE - Operations and Implications
PPTX
Shinn
DOCX
My CV 09-07-15
PDF
ROSES-CADET
PDF
IEEE-Communications-Mag-CSDCYorkU
DOCX
Cure for Cost and Schedule Growth
PDF
PDF
Cure for cost and schedule growth (submitted)
PDF
Cure for cost and schedule growth
PDF
Risk management paper
DOCX
ResearchTopicDevelopment_21Aug2014
DOCX
Case Analysis Guidelines by Dr. Dave Worrells and Mr. Scott.docx
PDF
2016,Problem B
PDF
North America Aerospace Project
PPTX
NASA Headquarters Associate Administrators' Panel: Exploration Systems Missio...
PDF
Resume 2015
Leo final report
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
Impediments to Interagency Cooperation on Space and Earth Science Missions
Investments in the Future: NASA's Technology Programs
DANDE - Operations and Implications
Shinn
My CV 09-07-15
ROSES-CADET
IEEE-Communications-Mag-CSDCYorkU
Cure for Cost and Schedule Growth
Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth
Risk management paper
ResearchTopicDevelopment_21Aug2014
Case Analysis Guidelines by Dr. Dave Worrells and Mr. Scott.docx
2016,Problem B
North America Aerospace Project
NASA Headquarters Associate Administrators' Panel: Exploration Systems Missio...
Resume 2015
Ad

More from Sung (Stephen) Kim (12)

PPTX
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
PDF
Critical Design Review Paper for Project A.R.E.S.
PDF
Initial Proposal for Project A.R.E.S.
PPTX
Flight Readiness Review Presentation for Project A.R.E.S.
PPTX
Critical Design Review Presentation for Project A.R.E.S.
PDF
Flight Readiness Review for Project A.R.E.S.
DOCX
Final Paper Avalanche Risk Assessment
PPTX
Avalanche Risk Assessment Final Presentation
PPTX
NASA Tech Integration Georgia Tech Grand Challenge
PPTX
Mission Concept Presentation for Project A.D.I.O.S.
PPTX
Payloads Presentation for Project A.D.I.O.S.
DOCX
Final Paper for Project A.D.I.O.S.
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Critical Design Review Paper for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.
Final Paper Avalanche Risk Assessment
Avalanche Risk Assessment Final Presentation
NASA Tech Integration Georgia Tech Grand Challenge
Mission Concept Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.
Final Paper for Project A.D.I.O.S.

Recently uploaded (20)

PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Sustainable Sites - Green Building Construction
PPTX
additive manufacturing of ss316l using mig welding
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
Welding lecture in detail for understanding
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Construction Project Organization Group 2.pptx
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
Digital Logic Computer Design lecture notes
PPT
Mechanical Engineering MATERIALS Selection
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
Lecture Notes Electrical Wiring System Components
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Sustainable Sites - Green Building Construction
additive manufacturing of ss316l using mig welding
bas. eng. economics group 4 presentation 1.pptx
Welding lecture in detail for understanding
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Operating System & Kernel Study Guide-1 - converted.pdf
Construction Project Organization Group 2.pptx
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Digital Logic Computer Design lecture notes
Mechanical Engineering MATERIALS Selection
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Internet of Things (IOT) - A guide to understanding
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
CYBER-CRIMES AND SECURITY A guide to understanding
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Lecture Notes Electrical Wiring System Components

Management, Cost, and Schedule Paper for Project A.D.I.O.S.

  • 1. Management, Cost, and Schedule Reviewfor the Deimos Impact & Observation Spacecraft (DIOS) Mission Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney, David Habashy, Brian Hardie, Brandon Hing, Zujia Huang, Sung Kim, and Jonathan Saenger Georgia Institute of Technology, Atlanta, GA, 30332 This document discusses the Management, Cost, and Schedule Review for the Deimos Impact & Observation Spacecraft of the DIOS mission and provides the charts and tables to that show the mission is able to meet its key requirements. The project cost covers both the staffing the personnel, as well at the cost of the cubesats components. The project schedule is included and is divided into phases A-F. Nomenclature CBE Currently Best Estimate CDR Critical Design Review CERR Critical Events Readiness Review DR Decommissioning Review DRR Disposal Readiness Review FAD Formulation Agreement Document MCR Mission Concept Review MDR Mission Definition Review MEV Maximum Expected Value MRR Mission Readiness Review ORR Operational Readiness Review PDR Preliminary Design Review SIR System Integration Review SRR System Requirements Review ΔVi Velocity change for initial burn, m/s ΔVc Velocity change for impactor burn, m/s ΔVo Velocity change for observer burn, m/s ΔVT Total velocity change, m/s I. Introduction The objective of the Deimos Impact & Observation Spacecraft (DIOS) Mission is to determine the origin and composition of Mars’ moon Deimos. Current hypotheses from NASA’s decadal survey speculate that Deimos is either an asteroid captured from the asteroid belt or accreted from a collision between Mars and another large body. According to NASA’s Vision and Voyages for Planetary Science in the Decade 2013-2022, Deimos plays an important role in the future exploration of Mars, especially if it is related to volatile-rich asteroids. If it is, Deimos may be a surviving representative of a family of bodies from the outer asteroid belt that reached the inner solar system and delivered volatiles and organics to the accreting terrestrial planets.1 During the course of this mission, DIOS will analyze the surface and sub-surface composition of Deimos to definitively determine the moon’s origin. In order to consider the mission to be considered a complete success, the following mission requirements must be met:
  • 2. 1. The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for the CubeSat Spectrometer to detect 2. The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including oxygen, carbon dioxide, carbon monoxide, water, and ammonia 3. The CubeSat shall analyze the plume with a spectrometer and determine the 1.3µm absorption levels, as well as the absorption levels of volatiles This document discusses the trajectory design that will allow DIOS to achieve a flyby of Deimos while providing the optimum velocities to achieve the mission requirements. II. Key Requirements The two major design goals of the spacecraft are to generate a plume of Deimos subsurface material, and to relay the composition of the material to Earth. The driving requirements serve to fulfill these two goals either directly or secondarily. 1. Shall be ready for launch by July 20th 2020 2. Shall arrive at Deimos between February 16th 2021 and February 17th 2021 3. Shall not exceed 5.6 million dollars in total cost 4. Shall have an acceptable amount of risk. III. Project Management Figure 1. Work Breakdown Structure The work breakdown structure (WBS) is created by grouping the spacecraft subsystems and development phases.The WBS is not organized chronologically. Project management facilitates the development of the
  • 3. spacecraft subsystems which are then put togetherby the integration supervisor.The testing supervisormakes sure the completed spacecraft meets the launch requirements. The launch preparation supervisormakes sure the completed, tested spacecraft is ready and present for launch. The post-launch supervisoranalyzes the data once the mission is complete. The purple box represents a post-doctoralassociate. The red boxes represent 4 graduate students.The yellow boxes represent 8 undergraduate students.The green boxes represent the general tasks that the higher-up boxes are responsible for. Below the green boxes would be detailed descriptions of what the green boxes entail. An example would be “Gather propulsion requirements from the trajectory group. Analyze available propulsion systemoptions.Perform trade studies for propulsion systems based upon deltaV, mass, size, power, etc.” The cost in terms of work breakdown structure elements is detailed in Table 1. The majority of costs for the mission stems from project management, specifically facilities and administrative fees, and project system engineering. Facilities and administrative fees consists ofwage and benefits for all personnelas well as tuition and health care for graduate students.Project systems engineering contains the majority of the cubesat components necessary for the mission. Table 1. Cost by WBS Elements IV. Project Cost Personnel The Research and Development (R&D) team of DIOS mission consists of1 principal investigator(PI), 1 post doctoral associate,4 graduate students and 8 part-time undergraduate students,giving a total team size of 13. The principal investigatoracts as the project leader and primary contact.The post doctoral associate acts as an executive manager that coordinates work between graduate and undergraduate students and assist themwith professional experience. The four graduate students are in charge of project systems engineering, spacecraft flight systems
  • 4. engineering, science payload engineering, and mission systems engineering respectively, with the undergraduate students sharing theirworkload under guidance. The PI requires a base salary of $113,381 in FY 2017 when the project starts.The salary increases on a predicted 3% rate per year, until FY 2020 when the development phase ends.The post doctoralassociate requires a base salary of estimated $45,000 in FY 2017 and a 1.5% raise in every succeeding year.. The four graduate students require a base salary of estimated $26,000 each in FY 2017, giving a total of $104,000, plus a 1.5% raise every year. The undergraduate students,working part-time and for course credits, are not paid. The PI and post doctoralassociate also require fringe benefits at a rate of 28.8% in FY 2017, a combined amount of $45.614. Therefore, total salaries and fringe benefits in FY 2017 is $307,995. Total salaries and fringe benefits over 4 years is $1,288,535. Equipment The equipment required for the DIOS mission are primarily on-board equipment and components,and mostly appears as non-recurring cost.Only equipment with cost close to or exceeding $5,000 are considered significant for discussion. There are 8 major on-board components of significant cost, covering C&DH, ADCS, power, propulsion, communication and scientific payload. Table 2 lists those components and their costs.The costs oftwo propulsion systems,Vacco MiPS and Rocketdyne MPS-130, have not been disclosed by manufacturers, and are estimated values based on similar products.All other costs are given by manufacturers or providers. Table 2. Equipment Cost Profile Equipment Quantity Cost 1. IRIS 1 $150,000.00 2. BCT XACT 2 $290,246.00 3. VACCO End-Mounted MiPS 1 $50,000.00 4. Argus 1000 IR Spectrometer 1 $49,500.00 5. Clyde Space 2U Deployable Array 4 $40,000.00 6. CS High Power Bundle C: EPS + 80 Whr Battery 2 $38,600.00 7. Rocketdyne MPS-130 1 $35,000.00 8. Nanomind A3200 1 $10,000.00 9. Cube Computer 1 $4,970.00 10. Total Equipment 14 $668,316.00 Travel Only full-time investigators,including PI, post doctoral associate and graduate students(6personnels total)are accounted for in travel and conference. The expected location of the conference (Aerospace Conference) is Big Sky, Montana,and the expected location of design review is at JPL in Pasadena,California. Both trips are expected to last one week. Hotels nearby the locations of interest provided quotes for the trip. Delta Airlines was used to
  • 5. estimate transportation costs foreach member. The total amount for travel costs per year is $23,450 for the entire mission. Trainee/Participant Costs There were no trainees or participants associated with the mission. All necessary testing deals with component testing.The mission does not require any human to physically accompany the cubesat.Therefore no costs associated with trainees or participants (stipend, tuition, etc.) were accounted for. Other Direct Costs Other direct costs mainly include publication/documentation cost, miscellaneous terms associated to graduate students and Deep Space Network operation cost.The publication and documentation cost is estimated at $5,000 and is a non-recurring cost term. For graduate students,health insurance and tuition are major costs.The health insurance is rated at 4.7% in FY 2017, a total of $4,888 for 4 students.The tuition is rated at $1,489 per person per month. The combined total is $76,360 in FY17. The health insurance increases by 1.5% per year until project ends in FY 2020. The Deep Space Network cost was calculated using an equation provided by NASA. The equation above calculates the aperture fees for DSN. The aperture fee coverage is detailed in Table 3. The DSN cost came out to be $2,114.00 per year. This cost is less than $5,000, but was included due to its crucial role in the mission. Table 3. Aperture Fee Coverage for DSN
  • 6. Summary The total cost for each year is listed below in Table 4. The non-recurring equipment cost are counted as cost for first year(FY 2017). Counting contingency for all costs,the total cost over four years is $2,654,874, less than half of the $5.3M limit. The full cost profile can be found in the appendix. Table 4. Overall mission cost over four years. Year 2017 2018 2019 2020 Total Total Cost $1,083,234 $395,855 $428,973 $438,931 $2,346,995 Total Cost with Contingency $1,161,583 $489,028 $500,607 $512,533 $2,663,753 V. Project Schedule Figure 2. Project Life Cycle (Note: Red Triangles - Required Review)2
  • 7. Pre-Phase A Figure 3. Pre-Phase A Gantt Chart Pre-Phase A will consist of concept studies relating to the mission. This may include refining the mission concept, preliminary mission architecture design, and assessing technology and engineering development. Using these, staff and infrastructure requirements will be determined for the project. With the work done in Pre-Phase A, a Formulation Agreement Document (FAD) will be developed as a tool for communicating and negotiating the project’s funding and schedule requirements for mission development. Before entering Phase A of the project, a Mission Concept Review (MCR) will be conducted to ensure life-cycle review objectives and expected maturity states have been met. 4 Pre-Phase A will last approximately 2 months. Phase A
  • 8. Figure 4. Phase A Gantt Chart Phase A is the first phase of project formulation. Within this step, concept and technology development activities will be performed to develop a mission architecture that meets programrequirements and constraints for the p roject. This will ensure the mission definition and plans are mature enough to begin Phase B. The activities in this phase include: · Developing/defining project requirements to the systemlevel · Developing systemarchitecture · Developing cost and schedule estimates for the project · Identifying and mitigating development risks · Updating staffing/infrastructure requirements In this phase, two reviews will be conducted. In the middle of this phase, a System Requirements Review (SRR) will be performed to evaluate whether the performance requirements of the system satisfy the program’s requirements of the project. At the end of Phase A, a Mission Definition Review (MDR) will be conducted to determine if the maturity of the mission definition is sufficient to begin Phase B. 4 Phase A will last 5 months. Phase B
  • 9. Figure 5. Phase B Gantt Chart Phase B is the final phase of project formulation and deals with the preliminary design and technology completion activities. In this phase, technology development will be completed, heritage hardware and software assessments will be performed, engineering prototyping will be conducted, and risk-mitigation activities will be identified. Furthermore, mission objectives, requirements, cost estimates, and schedule estimates will be updated. At the end of this phase, a Preliminary Design Review (PDR) will be conducted. The PDR will consist of evaluating the planning, cost, and schedule developed during Formulation and assessing the preliminary design’s compliance with the mission requirements.4 Phase B will last approximately 8 months. Phases C-D Phases C and D are the steps in which project implementation is conducted. In Phase C, final systemdesigns will be completed and documented, and fabrication of test and flight architecture will begin. Phase D consists of system assembly, integration, and testing various systempieces, while performing verification and validation on products as they are integrated. During this phase, hardware and software documentation will be finalized, issues from testing will be resolved, and the systemwill be prepared for launch and shipment.
  • 10. Figure 6. Phase C Gantt Chart In Phase C, two reviews will be conducted, the Critical Design Review (CDR) and the System Integration Review (SIR). The objective of the CDR is to evaluate the integrity of the project design and the ability of the system to meet mission requirements with appropriate margin and risk. The CDR is performed in the middle of Phase C. The SIR will evaluate the readiness of the project to begin assembly, integration, and testing.4 The SIR is performed at the end of Phase C. Figure 7. Phase D Gantt Chart
  • 11. In Phase D, the Operational Readiness Review (ORR) and Mission Readiness Review (MRR) will be conducted. The ORR is used to evaluate the readiness of the project to assemble, integrate, and test flight systems. The ORR is performed in the middle of Phase D. The MRR is used to assess the pre-flight operational readiness of the project. This will insure there are no problems with the flight systems and all personnel and infrastructure are ready to support launch. The MRR is performed at the end of Phase D.4 Phase C will last around 15 months and Phase D will last around 11 months. Phase E-F Figure 8. Phase E Gantt Chart Phase E is the launch, operations, and sustainment of the mission. The parameters for this phase are determined by the flight schedule. In this phase, a Critical Events Readiness Review (CERR), and Decommissioning Review (DR) are performed. The CERR will evaluate the readiness of the project to execute a critical event during flight operations. The DR (towards the end of the mission) will evaluate the readiness of the project to conduct closeout activities.4
  • 12. Figure 9. Phase F Gantt Chart Phase F deals with the decommissioning of the mission. This phase begins with a Disposal Readiness Review (DRR), in which the readiness of the project for disposal will be evaluated.4 In this stage, final archival of data and spacecraft closeout will be performed. Phase E will last under 9 months and Phase F will last 1 month.
  • 13. Critical Path Figure 10. Critical Path The critical path of the project shows that the minimum duration of the project will be 50 months. Each of the activity times are broken down in the Phase summaries above. This path does not include schedule margin, which is discussed below. Schedule Margin The planned activities of this mission will last 52 months, providing 8 months of schedule margin. This will provide sufficient margin for activities that may take more time than expected such as assembly, integration, and testing. The schedule margin rate is 0.133. VI. Project-level Risk Assessment and Mitigations
  • 14. 1. Propulsion isn’t ready in time 2. Production schedule surpasses time allotted until launch 3. Components don’t meet testing standards 4. Costs are higher than expected 5. Loss of satellite upon launch Figure 11. Project-level risk assessment matrix. There are five major project-level risks to be considered in risk analysis,the likelihood and consequences ofwhich are summarized in figure 11. An overdue in propulsion systemdelivery is mission-critical, particularly for the Rocketdyne MPS-130 propulsion module. The high delta-V capability is essential for the success ofDIOS mission; however, the MPS-130 has been in test phase for a long time without anticipated date of availability. The Vacco cold gas propulsion module, on the other hand,has samples already available and is generally higher in TRL than the MPS-130. The cold gas propulsion is also less mission critical and can be replaced by othersimilar products should the delivery fail to achieve, An overdue in spacecraft production also leads to direct failure of mission, since the launch vehicle and launch date is not undercontrol of the DIOS mission team. The likelihood of an project overdue is to the best reduced by setting the end date of Phase D(systemassembly, integration and testing) at least six months prior to launch, giving a generous margin for any delay. A loss of satellite upon launch will lead to direct failure of mission, but the possibility is low given the very high reliability of launch vehicle(Atlas V), with only one partial failure per 66 flights. The sub-model Atlas V-541 used for Mars 2020 mission has three successfullaunches to date with no failure. Should a launch vehicle accident occur and the spacecraft is lost, cost would be reimbursed partially by insurance. Unsatisfactory quality of spacecraft components threatens the reliability of spacecraft and thus the possibility of mission success.However, many of the components are off-the-shelf and have been tested by other successful missions. The component in development, such as the MPS-130, will be manufactured by top-tier companies, and thus the chances of component failing standards are low. Other structuralparts, including frame, wire and thermal/radiation protection are held to relatively low standards,given the somewhat short(less than one year) lifespan of the spacecraft.In addition, redundant testing will be performed to guarantee readiness of all compon ents; extra testing and possible fixing of parts are accounted for in schedule design.
  • 15. A cost overdue is likely, given the unpredictability of project progress.For instance, increase of cost will occur if components are replaced, duplicates are used for testing,or if salary level increases over the year at a rate higher than anticipated. However, reasonable cost overdue are covered in contingency and will not be impeding the mission. Should cost rise above the maximum anticipated level, it is most likely still within the $5.3M limit and thus additional funding can be acquired. VII. Descopes If we need to save on costs or time, there are several different options for descoping.The first would be to reduce the amount of testing for each part. This would reduce the amount of time for building the components for the satellite, which reduces the overall build time. It also would decrease the costs associated to test the components. However, this would increase the risk failure of the components. Anotherdescope option would be to reduce the amount of employees. This would decrease the total cost by reducing the amounts paid due to salaries. The downside to this option is that it would increase the production time, since there would be fewer people to work on the components.This could also increase the risk of individual components. A third option would be to reduce the amount of trips to conferences and design review trip. This would reduce the cost that do not apply directly to the manufacturing of the satellite. However, this would reduce the amount of critique and feedback received. Also, mission exposure would be far lower. VIII. Conclusion. The Management, Cost, and Schedule Review for the Deimos Impact & Observation Spacecraft of the DIOS mission and provides the charts and tables to that show the mission is able to meet its key requirements. The project cost covers both the staffing the personnel, as well at the cost of the cubesats components.The total estimated project cost with contingency falls well below the monetary limit given to each team. The project schedule is included and is divided into phases A-F. IX. References 1K.M. Brumbaugh, The Metrics of Spacecraft Design Reusability and Cost Analysis as Applied to Cubesats,2012. 2 Chapter2. NASA Life Cycles for Space Flight Programs and Projects. (2012, August 14). Retrieved from NASA Procedural Requirements: http://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7120_005E_&page_name=Chapter2 3 NASA's Mission Operations and Communications Services, NASA Deep Space. (2014). https://deepspace.jpl.nasa.gov/files/dsn/6_nasa_mocs_2014_10_01_14.pdf (accessed November 5, 2016). 4(2014). NASA Space Flight Program and Project Management Handbook. NASA, Hampton. Retrieved from https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20150000400.pdf 5 Preparing a Budget,Georgia Tech Office of Sponsored Programs. http://www.osp.gatech.edu/budget (accessed November 5, 2016).
  • 16. X. Appendix Category Quantity Funds Requested Year 2 Year 3 Year 4 Contingency A. Senior Personnel - - - - - - 1. Principal Investigator (PI) 1 $113,381.00 $116,782 .43 $120,285 .90 $123,894 .48 20.00% 2. Co-PI 0 $0.00 $0.00 $0.00 $0.00 3. Co-PI 0 $0.00 $0.00 $0.00 $0.00 4. Co-PI 0 $0.00 $0.00 $0.00 $0.00 5. Others 0 $0.00 $0.00 $0.00 $0.00 6. Total Senior Personnel 1 $113,381.00 $116,782 .43 $120,285 .90 $123,894 .48 B. Other Personnel - - - - - 1. Post Doctoral Associates 1 $45,000.00 $46,350. 00 $47,740. 50 $49,172. 72 20.00% 2. Other Professionals 0 $0.00 $0.00 $0.00 $0.00 3. Graduate Students 4 $104,000.00 $107,120 .00 $110,333 .60 $113,643 .61 20.00% 4. Undergraduate Students 8 $0.00 $0.00 $0.00 $0.00 5. Secretarial - Clerical 0 $0.00 $0.00 $0.00 $0.00 6. Others 0 $0.00 $0.00 $0.00 $0.00 7. Total Other Personnel 13 $104,000.00 $107,120 .00 $158,074 .10 $162,816 .32 TOTAL SALARIES AND WAGES - $262,381.00 $270,252 .43 $278,360 .00 $286,710 .80 C. Fringe Benefits - $45,613.73 $46,982. 14 $48,391. 60 $49,843. 35 TOTAL SALARIES AND WAGES FRINGE BENEFITS - $307,994.73 $317,234 .57 $326,751 .60 $336,554 .16 D. Equipment - - - - - 1. IRIS 1 $150,000.00 $0.00 $0.00 $0.00 10.00% 2. BCT XACT 2 $290,246.00 $0.00 $0.00 $0.00 5.00% 3. VACCO End-Mounted MiPS 1 $50,000.00 $0.00 $0.00 $0.00 15.00% 4. Argus 1000 IR Spectrometer 1 $49,500.00 $0.00 $0.00 $0.00 5.00% 5. Clyde Space 2U Deployable Array 4 $40,000.00 $0.00 $0.00 $0.00 5.00% 6. CS High Power Bundle C: 2 $38,600.00 $0.00 $0.00 $0.00 5.00%
  • 17. EPS + 80 Whr Battery 7. Rocketdyne MPS-130 1 $35,000.00 $0.00 $0.00 $0.00 15.00% 8. Nanomind A3200 1 $10,000.00 $0.00 $0.00 $0.00 5.00% 9. Cube Computer 1 $4,970.00 $0.00 $0.00 $0.00 5.00% 10. Total Equipment 14 $668,316.00 $0.00 $0.00 $0.00 - E. Travel - - - - - - 1. Conference Trip Entrance 6 $8,400.00 $8,400.0 0 $8,400.0 0 $8,400.0 0 10.00% 2. Design Review Trip 6 $0.00 $0.00 $0.00 $0.00 0.00% 3. Hotels 6 $3,150.00 $3,150.0 0 $3,150.0 0 $3,150.0 0 10.00% 4. Transportation 6 $11,900.00 $11,900. 00 $11,900. 00 $11,900. 00 10.00% 5. Total Travel Costs $23,450.00 $23,450. 00 $23,450. 00 $23,450. 00 - F. Trainee/Participant Costs - - - - - - 1. Stipends 0 $0.00 $0.00 $0.00 $0.00 0.00% 2. Tuition & Fees 0 $0.00 $0.00 $0.00 $0.00 0.00% 3. Trainee Travel 0 $0.00 $0.00 $0.00 $0.00 0.00% 4. Other 0 $0.00 $0.00 $0.00 $0.00 0.00% 5. Total Participants 0 $0.00 $0.00 $0.00 $0.00 0.00% G. Other Direct Costs - - - - - - 1. Materials and Supplies - $0.00 $0.00 $0.00 $0.00 0.00% 2. Publication/Documentation 1 $5,000.00 $0.00 $0.00 $0.00 5.00% 3. Consultant Services 0 $0.00 $0.00 $0.00 $0.00 0.00% 4. Computer Services 0 $0.00 $0.00 $0.00 $0.00 0.00% 5. Subcontracts 0 $0.00 $0.00 $0.00 $0.00 0.00% 6. Others (Grad Healthcare, Tuition) 4 $76,360.00 $76,506. 64 $76,657. 68 $76,813. 25 5.00% 7. Deep Space Network Costs 1 $2,114.00 $2,114.0 0 $2,114.0 0 $2,114.0 0 5.00% 8. Total Direct Costs - $83,474.00 $78,620. 64 $78,771. 68 $78,927. 25 - TOTAL YEARLY COST - $1,083,234.73 $395,855 .21 $428,973 .28 $438,931 .41 - TOTAL ESTIMATED PROJECT COST $2,346,994.6 3 - - - - - TOTAL YEARLY COST WITH CONTINGENCY - $1,161,583.70 $489,02 8.16 $500,60 7.19 $512,53 3.60 - TOTAL COST WITH CONTINGENCY $2,663,752.6 5 - - - - -