Management, Cost, and
Schedule
Team 3
DIOS - Deimos Impact & Observation Spacecraft
Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney,
David Habashy, Brian Hardie, Brandon Hing, Zujia Huang, Sung Kim, Jonathan Saenger
2
Mission Concept
Mission Goal: Direct an impactor into Deimos at high velocities to launch a plume of
surface and subsurface debris into space. The plume will be analyzed by an infrared
spectrometer to determine the composition Deimos. This will determine whether
Deimos is a C or D type asteroid, or Mars ejecta. In addition, prebiotic volatile
concentrations will be analyzed to determine asteroid contributions to early life.
Mission Objectives:
- The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for
the CubeSat Spectrometer to detect
- The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including
oxygen, carbon dioxide, carbon monoxide, water, and ammonia
- The CubeSat shall analyze the plume with a spectrometer and determine the 1.3 µm absorption
levels, as well as the absorption levels of volatiles
3
Key Requirements
The two major design goals of the spacecraft are to generate a plume of Deimos subsurface
material, and to relay the composition of the material to Earth. The driving requirements serve to fulfill
these two goals either directly or secondarily.
1. Shall be ready for launch by July 20th 2020
2. Shall arrive at Deimos between February 19th 2021 and February 20th 2021
3. Shall not exceed 5.6 million dollars in total cost
4. Shall have an acceptable amount of risk.
4
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
DIOS Work Breakdown Structure Cost Element
6
Total Cost Profile
7
Cost Estimation Methodology
8
Cost Estimation Methodology for DSN
9
Project
Life Cycle
10
System Schedule, Critical Path, Schedule Margin
Pre-Phase A: 1/1/17 - 3/1/17 (2 months)
Phase A: 3/2/17 - 7/31/17 (5 months)
Phase B: 8/1/17 - 4/1/18 (8 months)
Phase C: 4/1/18 - 7/20/19 (15 months)
Phase D: 7/21/19 - 7/13/20 (12 months)
Phase E: 7/14/20 - 3/31/21 (9 months)
Phase F: 4/1/21 - 5/2/21 (1 month)
Total: 52 months
Margin: 8 months
11
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Management, Cost, and Schedule Presentation for Project A.D.I.O.S.
Project Implementation Flowchart
15
Flight Schedule
Significant events during flight
Days Elapsed since Separation Seconds
Separation
Date
ΔVi ΔVc + ΔVo Impact Flyby
Observe
Time
21-Jul 2020 4 208.22667 210.80 210.85 248.72
22-Jul 2020 4 207.22667 209.81 209.86 260.54
23-Jul 2020 4 206.22667 208.82 208.86 257.12
24-Jul 2020 4 205.22667 207.83 207.87 255.70
16
Project Risk Areas and Mitigations
17
Risk Assessment
Likelihood
Consequence
1. Propulsion isn’t ready in time of launch
○ If so, we will have to find a new propulsion
system.
2. Production schedule surpasses time allotted until
launch
○ We have margins built into our production
schedule to account for more.
3. Components don’t meet testing standards
○ The schedule margin accounts for fixing
4. Costs are higher than expected
○ Total mission cost with contingency is still the
total allocated budget
1
2
6
4 3
5
Descopes
Reduce the amount of quality testing
Reduces build time but increases risks
Reduce the amount of employees
Reduces salary costs but increases build time
Reduce the amount of trips to conferences and design
review trips
Reduces costs but reduces centainity of design.
18

More Related Content

PPTX
SDG 15.3.1-LDN indicators_unccd_reporting, Hakki Emrah Erdogan
PDF
e-SOTER Regional pilot platform as EU contribution to a Global Soil observing...
 
PPTX
Preliminary progress on global soil erosion assessment
PPT
Christopher Yang Poster_NHedit
PPTX
IGARSS 2011_Temimi.pptx
PPT
041026 Icap Transp Quant
PDF
Ma, Jin: Inverse modelling of global carbonyl sulfide budget using TM5-4DVAR ...
PPTX
Final Project
SDG 15.3.1-LDN indicators_unccd_reporting, Hakki Emrah Erdogan
e-SOTER Regional pilot platform as EU contribution to a Global Soil observing...
 
Preliminary progress on global soil erosion assessment
Christopher Yang Poster_NHedit
IGARSS 2011_Temimi.pptx
041026 Icap Transp Quant
Ma, Jin: Inverse modelling of global carbonyl sulfide budget using TM5-4DVAR ...
Final Project

Viewers also liked (20)

PPTX
Final Presentation for Project A.D.I.O.S.
PPSX
PMP Exam Preparation Course: 06 Project Cost Management
PPTX
Lecture 06 project_cost_management
PDF
Cleopatra Enterprise Added Value
DOC
PDF
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
DOC
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
PDF
Copywriter's Workshop Certificate
PDF
As parábolas de jesus com joachim jeremias
PPTX
PMP Training Project Cost Management Part 1
PPTX
PDF
03 2016 inail rischio chimico laboratori
PPTX
Jimmy delgado saia reingenieria
PDF
ملاحظات مهمة عن تعجيل المشاريع
PDF
Серводвигатели серии SQ Sicme motori
DOCX
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
PPTX
Project Cost Management
PPTX
Total Cost Management - Synergy between Cost Estimating and Project Controls
PPTX
Qs Approach To Project Cost
PPTX
PMBoK, discussion #5: Project Cost Management
Final Presentation for Project A.D.I.O.S.
PMP Exam Preparation Course: 06 Project Cost Management
Lecture 06 project_cost_management
Cleopatra Enterprise Added Value
Spatio temporal modeling of snow flake crystals using packardªs cellular auto...
Kozma Szilárd asztrológus: A Lilith inverzió és a keresztény asztrológia V.
Copywriter's Workshop Certificate
As parábolas de jesus com joachim jeremias
PMP Training Project Cost Management Part 1
03 2016 inail rischio chimico laboratori
Jimmy delgado saia reingenieria
ملاحظات مهمة عن تعجيل المشاريع
Серводвигатели серии SQ Sicme motori
Management, Cost, and Schedule Paper for Project A.D.I.O.S.
Project Cost Management
Total Cost Management - Synergy between Cost Estimating and Project Controls
Qs Approach To Project Cost
PMBoK, discussion #5: Project Cost Management
Ad

Similar to Management, Cost, and Schedule Presentation for Project A.D.I.O.S. (20)

DOCX
Final Paper for Project A.D.I.O.S.
PDF
Risk management paper
PPTX
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
PDF
geo7_crafting_geoinformation
PDF
Inter fellous freilich
PDF
Inter fellous freilich
PDF
Risk management case study
PPT
Market Briefing. Japan part 2. 28th January
PPT
Ianson
PDF
KGrothe Capstone Project Final Presentation
PDF
Meterological Technology International, Nov 2010
PPTX
Algae blooms tracker
PPT
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
DOCX
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
PDF
Mercator Ocean newsletter 24
PDF
NEO Surveyor Project Overview CL24_2189.pdf
PPTX
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
PDF
NorthDakotaSYSTEMS
PDF
Mercator Ocean newsletter 31
DOCX
Final Mission Proposal
Final Paper for Project A.D.I.O.S.
Risk management paper
C0.5: CEOS and Oceans - Chu Ishida, Alex Held
geo7_crafting_geoinformation
Inter fellous freilich
Inter fellous freilich
Risk management case study
Market Briefing. Japan part 2. 28th January
Ianson
KGrothe Capstone Project Final Presentation
Meterological Technology International, Nov 2010
Algae blooms tracker
WE2.L10 - NASA's Evolving Approaches to Maximizing Applications Return from o...
PHY 103 Final Project Guidelines and RubricOverviewThe final .docx
Mercator Ocean newsletter 24
NEO Surveyor Project Overview CL24_2189.pdf
Aben, Ilse: Using satellite observations to detect and quantify concentrated ...
NorthDakotaSYSTEMS
Mercator Ocean newsletter 31
Final Mission Proposal
Ad

More from Sung (Stephen) Kim (12)

PPTX
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
PDF
Critical Design Review Paper for Project A.R.E.S.
PDF
Initial Proposal for Project A.R.E.S.
PPTX
Flight Readiness Review Presentation for Project A.R.E.S.
PPTX
Critical Design Review Presentation for Project A.R.E.S.
PDF
Flight Readiness Review for Project A.R.E.S.
DOCX
Final Paper Avalanche Risk Assessment
PPTX
Avalanche Risk Assessment Final Presentation
PPTX
NASA Tech Integration Georgia Tech Grand Challenge
PPTX
Mission Concept Presentation for Project A.D.I.O.S.
PPTX
Payloads Presentation for Project A.D.I.O.S.
DOCX
Mission Concept Paper for Project A.D.I.O.S.
Project A.R.E.S. Outreach Program Presentation: Frederick Douglass High School
Critical Design Review Paper for Project A.R.E.S.
Initial Proposal for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
Critical Design Review Presentation for Project A.R.E.S.
Flight Readiness Review for Project A.R.E.S.
Final Paper Avalanche Risk Assessment
Avalanche Risk Assessment Final Presentation
NASA Tech Integration Georgia Tech Grand Challenge
Mission Concept Presentation for Project A.D.I.O.S.
Payloads Presentation for Project A.D.I.O.S.
Mission Concept Paper for Project A.D.I.O.S.

Recently uploaded (20)

PPT
Project quality management in manufacturing
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
web development for engineering and engineering
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
composite construction of structures.pdf
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Sustainable Sites - Green Building Construction
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
OOP with Java - Java Introduction (Basics)
DOCX
573137875-Attendance-Management-System-original
PPTX
Internet of Things (IOT) - A guide to understanding
Project quality management in manufacturing
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Arduino robotics embedded978-1-4302-3184-4.pdf
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
CH1 Production IntroductoryConcepts.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
web development for engineering and engineering
UNIT-1 - COAL BASED THERMAL POWER PLANTS
composite construction of structures.pdf
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Sustainable Sites - Green Building Construction
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Lesson 3_Tessellation.pptx finite Mathematics
Strings in CPP - Strings in C++ are sequences of characters used to store and...
Embodied AI: Ushering in the Next Era of Intelligent Systems
OOP with Java - Java Introduction (Basics)
573137875-Attendance-Management-System-original
Internet of Things (IOT) - A guide to understanding

Management, Cost, and Schedule Presentation for Project A.D.I.O.S.

  • 1. Management, Cost, and Schedule Team 3 DIOS - Deimos Impact & Observation Spacecraft Jeff Anderson, Thomas Blachman, Andrew Fallon, John Franklin, Samuel Gaultney, David Habashy, Brian Hardie, Brandon Hing, Zujia Huang, Sung Kim, Jonathan Saenger
  • 2. 2
  • 3. Mission Concept Mission Goal: Direct an impactor into Deimos at high velocities to launch a plume of surface and subsurface debris into space. The plume will be analyzed by an infrared spectrometer to determine the composition Deimos. This will determine whether Deimos is a C or D type asteroid, or Mars ejecta. In addition, prebiotic volatile concentrations will be analyzed to determine asteroid contributions to early life. Mission Objectives: - The impactor shall collide with Deimos’ surface and generate a plume sufficient enough in size for the CubeSat Spectrometer to detect - The impactor shall penetrate Deimos’ surface deep enough to expose volatile compounds including oxygen, carbon dioxide, carbon monoxide, water, and ammonia - The CubeSat shall analyze the plume with a spectrometer and determine the 1.3 µm absorption levels, as well as the absorption levels of volatiles 3
  • 4. Key Requirements The two major design goals of the spacecraft are to generate a plume of Deimos subsurface material, and to relay the composition of the material to Earth. The driving requirements serve to fulfill these two goals either directly or secondarily. 1. Shall be ready for launch by July 20th 2020 2. Shall arrive at Deimos between February 19th 2021 and February 20th 2021 3. Shall not exceed 5.6 million dollars in total cost 4. Shall have an acceptable amount of risk. 4
  • 6. DIOS Work Breakdown Structure Cost Element 6
  • 11. System Schedule, Critical Path, Schedule Margin Pre-Phase A: 1/1/17 - 3/1/17 (2 months) Phase A: 3/2/17 - 7/31/17 (5 months) Phase B: 8/1/17 - 4/1/18 (8 months) Phase C: 4/1/18 - 7/20/19 (15 months) Phase D: 7/21/19 - 7/13/20 (12 months) Phase E: 7/14/20 - 3/31/21 (9 months) Phase F: 4/1/21 - 5/2/21 (1 month) Total: 52 months Margin: 8 months 11
  • 16. Flight Schedule Significant events during flight Days Elapsed since Separation Seconds Separation Date ΔVi ΔVc + ΔVo Impact Flyby Observe Time 21-Jul 2020 4 208.22667 210.80 210.85 248.72 22-Jul 2020 4 207.22667 209.81 209.86 260.54 23-Jul 2020 4 206.22667 208.82 208.86 257.12 24-Jul 2020 4 205.22667 207.83 207.87 255.70 16
  • 17. Project Risk Areas and Mitigations 17 Risk Assessment Likelihood Consequence 1. Propulsion isn’t ready in time of launch ○ If so, we will have to find a new propulsion system. 2. Production schedule surpasses time allotted until launch ○ We have margins built into our production schedule to account for more. 3. Components don’t meet testing standards ○ The schedule margin accounts for fixing 4. Costs are higher than expected ○ Total mission cost with contingency is still the total allocated budget 1 2 6 4 3 5
  • 18. Descopes Reduce the amount of quality testing Reduces build time but increases risks Reduce the amount of employees Reduces salary costs but increases build time Reduce the amount of trips to conferences and design review trips Reduces costs but reduces centainity of design. 18

Editor's Notes