SlideShare a Scribd company logo
2
Most read
5
Most read
8
Most read
Modus Operandi Of Concrete Test
By Design & Contracts Dept.
Page 1 of 12
1. Introduction
A concrete test is performed to learn more about the properties of a specific sample of
concrete and to determine compressive strength of concrete. Because concrete is an
important structural element, testing is mandatory in many reasons. Test Result are also
kept in file in case a problem develops in the future. Concrete Compression Strength
report is required for various purposes including the following
 To identify and compliance of actual strength compared with Design Strength.
 To make Decision by the Designer if unusual cases.
 Safe guard to construction companies and legal documents to show to Government
authorities (If required)
2. Existing Policy on Concrete Compressive Strength Tests & Re-Bar Tensile
Strength test of at different Phase of Construction (Memo dt 13/11/2010):
SL
NO
Construction
Phase
Test Number of
Sample Set
Testing Laboratory
1 Pile Concrete
Cube
As per
requirement
1.*BRTC(1-set)
2.**ACL(at every 40 piles
intervals)
2 Pile Cap Concrete
Cube
01+01 BRTC & ACL
3 Footing Concrete
Cube
01+01 BRTC & ACL
4 Ground Floor
Column
Concrete
Cube
01+01 BRTC & ACL
Reinforcement 01 BRTC
5 All others Floor
Column
Concrete
Cube
01 ACL(Three successive floor
intervals)
6 Basement Roof Concrete
Cube
01+01 BRTC & ACL
7 Ground Floor
Roof
Concrete
Cube
01+01 BRTC & ACL
8 All other Roof
Slabs
Concrete
Cube
01 for each 1.ACL(For all roof slab)
2.BRTC(Three successive
roof slabs intervals)
Page 2 of 12
3. Modus Operandi
1) PIC will collect and necessary preparation of cube/cylinder Mold as described in the
‘’Cube making Procedure” in Anuxiure-1.
2) Sample collection, preservation and send to relevant lab in due time by PIC. In this
regard PIC ,Concerned AH will fill up the enclosed checklist annexed as “Annexure-
2” and forward to GM-PO
3) PIC will send samples to ACL, BUET, RMC lab in due time as per Memo dt
13/11/2010.
4) PIC will inform DCD for testing during submission of the samples in case of ACL
testing.
5) DCD concerned will ensure testing of samples in time and prepare the report in case
of testing in ACL lab.
6) DCD will preserve all the original report in H/O file and forward the copy to AMD for
his perusal in case of failure reports. One set of photocopy will forward to projects.
7) Further DCD will study all the reports and consult with our consultant for specific
and required cases (if any).
8) PIC will ensure timely testing in RMC lab/BUET lab test and original set will forward
to DCD.
9) DCD will also monitor and compliance project base testing and preserve all original
documents.
10) Concerned officials from respective Departments :-
a) Concerned official of DCD Technical team
i. Engr. Md Mominur Rouf (AGM-DC)
ii. Engr. Laila Noor (SrM-SD)
iii. Engr. Mohsinul Azad (SrEXC-SD)
iv. Engr. Abir Hossain (EXC-SD)
v. Engr. Farhat Aziz Sheen (EXC-SD)
b) Laboratory-in-Charge
i. Accountant (Central Store)
c) Laboratory Assistant
i. Site Assistant (Central Store)
d) Maintenance Works
i. Electrical maintenance support will be provided by EWD Maintenance wing prior
receiving the requisition from DCD. Necessary cost up to Tk.1500/- will be
borne by Project pretty cash where the Lab is attached & relevant approval
may be taken from concerned RH.
Page 3 of 12
ii. Mechanical & others maintenance support will be provided by MRD prior
receiving the requisition from DCD. Necessary cost up to TK.2500/- will be
borne by Project pretty cash where the Lab is attached & relevant approval
may be taken from concerned RH..
iii. Calibration & other up gradation (if any) will be performed by external agencies
prior Management approval through DCD.
iv. Hydraulic oil for machineries and other routine maintenance items will be
supplied by IM section prior requisition from DCD.
v. Routine maintenance will be done by Lab In Charge. DCD will monitor.
11) Responsibilities in Details:
a) Responsibilities of Lab In-Charge:
i. To manage overall activities of the Lab.
ii. To maintain all records, Files, Registry book of the Lab.
iii. To receive Specimen from projects and ensure specification(quality of sample)
requirements.
iv. To co-ordinate with the Technical Team.
v. Report Disbursement.
vi. To supervise Lab Assistant activities.
vii. To ensure due maintenance of the equipments.
b) Responsibilities of Technical Team [DCD]:
i. To perform the test with the help of Lab Assistant.
ii. To prepare the Test Report.
iii. To prepare Testing Schedule.
iv. To ensure timely performing tests.
v. Technical vetting of reports (if required) through Consultants.
vi. To preserve the original Reports in respective File of DCD.
c) Responsibilities of Lab Assistant:
i. To operate the Machine.
ii. To preserve cylinders.
iii. To perform Curing.
iv. Tested Cylinders disposal.
v. To provide necessary supports to the Lab-in-Charge and the Technical Team.
vi. To ensure Security of the Lab.
Page 4 of 12
12) Responsibilities of Area Head(AH) & Project in Charge(PIC)
i. To ensure proper sampling, preservation and timely send the sample to
concerned Lab as in this manual. [as per Internal memo on 13/11/10)
ii. To fill up the checklist as Annexure-1 and sent to GMPO with a copy to AGMDC.
14) Cube Making Apparatus:
i. Cube moulds of (15 X 15 X 15) cm size [minimum 3 no for each set]
ii. Trowel
iii. Sampling Scoop
iv. (25X25X400)mm square steel tamping rod with lower end flat / STEEL BAR 16MM
DIA AND 60CM LONG
v. 15cm long MS flat bar
vi. Wooden/rubber Hammer
vii. Wrench
viii. Steel BRASH
ix. Scraper
x. STEEL SCALE
xi. STEEL PAN
xii. MIXTURE MACHINE
xiii. Mould releasing oil ETC.
Page 5 of 12
CUBE MOULD TROWEL
SCOOP TAMPING ROD
RUBBER HAMMER WRENCH
Page 6 of 12
STEEL BRUSH SCRAPER
STEEL SCALE STEEL PAN
MIXTURE MACHINE MOULD RELEASING OIL
Page 7 of 12
15) Cube Making Procedure:
i. Separate the mould assembly and clean all interior faces, base with scraper to
remove rust/cement coating.
ii. Assemble cube moulds checking every dimension with steel scale /15cm long MS
flat bar.
iii. Oil the interior surface of the mould with mould releasing oil to prevent adhesion
of concrete. Don’t use excess oil.
iv. Sample should be true representative of concrete being used.
v. For site mixing, mixing time should be at least one minute or 20 revolutions of the
mixer from adding all aggregates to obtain a homogeneous mix.
vi. For ready mix concrete, before collecting concrete it should be mixed properly in
the mixer truck.
vii. Sample collecting pan should be near, clean and free from any loose material.
Collecting pan may be slightly moist with water but staking of water should be
avoided.
viii. At least one set (3cubes) sample should be taken from the same batch / mix.
ix. Fill the concrete in the molds in layers approximately 5 cm thick (total 3 layers).
x. Cube moulds of (15 X 15 X 15) cm size [minimum 3 no for each set].
xi. Each layer should be compacted BY 35 STROKES with tamping ROD [STEEL BAR
16MM DIA AND 60CM LONG, BULLET POINTED AT LOWER END] OR 25STROKES
WITH TAMPING BAR [25MM SQUARE AND 400MM LENGTH, lower end flat]
xii. Concrete should poured in the mould and tempered properly so as not to have
any voids.
xiii. The top surface of the specimen should be made even and smooth. This is done
by putting cement paste and spreading smoothly on whole area of specimen and
smoothen it with trowel.
xiv. Vibrate the mould using rubber / wooden hammer to remove air content/ voids
from concrete.
xv. Store the cube moulds in a place which is free from vibration and cover the
surface of the concrete with a piece of damp sacking for initial 16 to 24 hours.
xvi. After 24 hours of casting cubes, remove cubes from moulds. For ready mix
concrete sometimes it may take more than 24 hours to harden the concrete in
that case wait until concrete gains sufficient hardness.
xvii. After removing from mould mark casting date and name of structure for which
concrete being used on the cubes with a permanent marker. Submerge cubes
under clean water for curing.
Page 8 of 12
xviii. After 28 days take out cubes from curing tank.
xix. Send to laboratory / testing Authority for test.
xx. During transportation care should be taken to avoid any damage (broken edge) of
cubes.
16) Common Reasons behind the Failure of Concrete Test RESULTS:
i. High Water Cement Ratio.
ii. Use Inferior quality as well as improper gradation of stone chips / brick chips.
iii. Insufficient FM & poor gradation of Sand.
iv. Quality of Cement.
v. Inappropriate mixing procedure & timing.
vi. Faulty sampling.
vii. Inadequate and inaccurate time of curing.
viii. Adulteration of coarse and fine aggregate such as mud, clay, coal, wood or other
organic materials etc.
ix. Unskilled operation, handling and transportation.
x. Calibration of Machineries.
xi. Carelessness during testing like sample placement and loading.
xii. FEW PRACTICAL Problems observed in different Projects:
 Cubes are not found uniform size and shape.
 Too many pores in cube surfaces.
 Sending cube to lab without SSD condition(Saturated surface dry
Condition)
 Broken edges
 Surface undulation(not leveled and smooth) etc.
Page 9 of 12
Cubes not having uniform shape
Page 10 of 12
Having pores at cube surface
Cubes not in “SSD” condition
Page 11 of 12
Undulation surface
Broken Edges
Page 12 of 12
ANNEXURE-1
Asset Development & Holdings Ltd.
91 Gulshan,Dhaka
Cube Sent for Testing to BUET & ACL Checking Form
Project: Address:
Sl Structural
Item to be
Checked
Sample list for BRTC &
ACL
Date Checked
& signed
by PIC
Checked by AH Remarks
Sign Date
1 Pile BRTC(1 set)
ACL(at every 40 piles
intervals)
2 Pile Cap BRTC(1 set)
ACL(1 set)
3 Footing BRTC(1 set)
ACL(1 set)
4 Ground
Floor
Column
BRTC(1 set)
ACL(1 set)
5 All others
Floor
Column
ACL(Three
successive
floor
intervals)
1st
Floor
4th
Floor
8th
Floor
6 Basement
Roof
BRTC(1 set)
ACL(1 set)
7 Ground
Floor Roof
BRTC(1 set)
ACL(1 set)
8 All other
Roof Slabs
BRTC(Three
successive
roof slabs
intervals)
1st
Floor
4th
Floor
8th
Floor
ACL(For all
roof slab)
1st
Floor
2nd
Floor
3rd
Floor
4th
Floor
5th
Floor
6th
Floor
7th
Floor
8th
Floor

More Related Content

PDF
California Bearing Ratio(CBR) Test.pdf
PDF
Chapter 7 DESIGN OF FOOTING
PDF
CBR Test
PDF
Chapter 12
PDF
Rankine’s Theory of Bearing Capacity, Rankine’s ANALYSIS FOR BEARING CAPACITY
DOC
Unit2 fluid static
PDF
Civil engineering lab tests pdf
PPTX
Standard penetration test(spt)
California Bearing Ratio(CBR) Test.pdf
Chapter 7 DESIGN OF FOOTING
CBR Test
Chapter 12
Rankine’s Theory of Bearing Capacity, Rankine’s ANALYSIS FOR BEARING CAPACITY
Unit2 fluid static
Civil engineering lab tests pdf
Standard penetration test(spt)

What's hot (20)

PPTX
Cube test REPORT - DCC2042
DOCX
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
PDF
sampling and testing of aggregates
PDF
Cement Test.pdf
PDF
Softening point of bitumious
PDF
Structural engineer s pocket book
PDF
Cbr test
DOCX
Chapter 6 earth pressure
PPTX
Site Investigation and Example of Soil Sampling
PPT
Laboratory soil compaction test
PDF
Aggregate impact value test experiment
DOCX
Specific Gravity of Cement
PDF
Class 6 Shear Strength - Direct Shear Test ( Geotechnical Engineering )
PDF
Iii design-of-steel-structures-unit-2
PDF
Bs8110 design notes
DOCX
Individual lab report for bd rodded
PDF
Understanding sieve analysis of sand
PPTX
SHALLOW FOUNDATION
PPTX
Interface treatment
PPTX
Soil investigation
Cube test REPORT - DCC2042
DCC3113 DETERMINATION OF AGGREGATE IMPACT VALUE.
sampling and testing of aggregates
Cement Test.pdf
Softening point of bitumious
Structural engineer s pocket book
Cbr test
Chapter 6 earth pressure
Site Investigation and Example of Soil Sampling
Laboratory soil compaction test
Aggregate impact value test experiment
Specific Gravity of Cement
Class 6 Shear Strength - Direct Shear Test ( Geotechnical Engineering )
Iii design-of-steel-structures-unit-2
Bs8110 design notes
Individual lab report for bd rodded
Understanding sieve analysis of sand
SHALLOW FOUNDATION
Interface treatment
Soil investigation
Ad

Similar to Manual Of Concrete Compression Test (20)

PPT
Construction basic SIP
DOC
Column & beam
DOC
Concreting of super structure
PDF
Case hole logging for beginner - cement log .pdf
DOCX
@ETCONp Construction Exam 8 .DOCX
DOC
HCB Manual gtz 2008.doc
PDF
Trial mixing concrete .pdf
PDF
Delhi metro presention
PPTX
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PDF
Casting process and moulding process file for trainning report complet trainn...
PDF
Concrete Mix Design Report
PDF
07 a60105 estimatingandcosting
PDF
VG Check list for OHE mast grouting rev 00
PDF
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
PPT
DOCX
CPCCBC5018A Apply Structural Principles To The Construction Of Medium Rise.docx
PDF
Formwork & Falsework Practice_2009(July)_to AK.pdf
PPTX
Permeable concrete pavement
PDF
Re development works at east kidwai nagar, New Delhi
PDF
API 510 Practice Exam #5 CLOSE BOOK Questions.pdf
Construction basic SIP
Column & beam
Concreting of super structure
Case hole logging for beginner - cement log .pdf
@ETCONp Construction Exam 8 .DOCX
HCB Manual gtz 2008.doc
Trial mixing concrete .pdf
Delhi metro presention
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
Casting process and moulding process file for trainning report complet trainn...
Concrete Mix Design Report
07 a60105 estimatingandcosting
VG Check list for OHE mast grouting rev 00
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
CPCCBC5018A Apply Structural Principles To The Construction Of Medium Rise.docx
Formwork & Falsework Practice_2009(July)_to AK.pdf
Permeable concrete pavement
Re development works at east kidwai nagar, New Delhi
API 510 Practice Exam #5 CLOSE BOOK Questions.pdf
Ad

Recently uploaded (20)

PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Digital Logic Computer Design lecture notes
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
additive manufacturing of ss316l using mig welding
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
web development for engineering and engineering
PPT
introduction to datamining and warehousing
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
Lecture Notes Electrical Wiring System Components
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Digital Logic Computer Design lecture notes
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
additive manufacturing of ss316l using mig welding
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
web development for engineering and engineering
introduction to datamining and warehousing
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
CYBER-CRIMES AND SECURITY A guide to understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Safety Seminar civil to be ensured for safe working.
Lecture Notes Electrical Wiring System Components
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Embodied AI: Ushering in the Next Era of Intelligent Systems
Operating System & Kernel Study Guide-1 - converted.pdf

Manual Of Concrete Compression Test

  • 1. Modus Operandi Of Concrete Test By Design & Contracts Dept.
  • 2. Page 1 of 12 1. Introduction A concrete test is performed to learn more about the properties of a specific sample of concrete and to determine compressive strength of concrete. Because concrete is an important structural element, testing is mandatory in many reasons. Test Result are also kept in file in case a problem develops in the future. Concrete Compression Strength report is required for various purposes including the following  To identify and compliance of actual strength compared with Design Strength.  To make Decision by the Designer if unusual cases.  Safe guard to construction companies and legal documents to show to Government authorities (If required) 2. Existing Policy on Concrete Compressive Strength Tests & Re-Bar Tensile Strength test of at different Phase of Construction (Memo dt 13/11/2010): SL NO Construction Phase Test Number of Sample Set Testing Laboratory 1 Pile Concrete Cube As per requirement 1.*BRTC(1-set) 2.**ACL(at every 40 piles intervals) 2 Pile Cap Concrete Cube 01+01 BRTC & ACL 3 Footing Concrete Cube 01+01 BRTC & ACL 4 Ground Floor Column Concrete Cube 01+01 BRTC & ACL Reinforcement 01 BRTC 5 All others Floor Column Concrete Cube 01 ACL(Three successive floor intervals) 6 Basement Roof Concrete Cube 01+01 BRTC & ACL 7 Ground Floor Roof Concrete Cube 01+01 BRTC & ACL 8 All other Roof Slabs Concrete Cube 01 for each 1.ACL(For all roof slab) 2.BRTC(Three successive roof slabs intervals)
  • 3. Page 2 of 12 3. Modus Operandi 1) PIC will collect and necessary preparation of cube/cylinder Mold as described in the ‘’Cube making Procedure” in Anuxiure-1. 2) Sample collection, preservation and send to relevant lab in due time by PIC. In this regard PIC ,Concerned AH will fill up the enclosed checklist annexed as “Annexure- 2” and forward to GM-PO 3) PIC will send samples to ACL, BUET, RMC lab in due time as per Memo dt 13/11/2010. 4) PIC will inform DCD for testing during submission of the samples in case of ACL testing. 5) DCD concerned will ensure testing of samples in time and prepare the report in case of testing in ACL lab. 6) DCD will preserve all the original report in H/O file and forward the copy to AMD for his perusal in case of failure reports. One set of photocopy will forward to projects. 7) Further DCD will study all the reports and consult with our consultant for specific and required cases (if any). 8) PIC will ensure timely testing in RMC lab/BUET lab test and original set will forward to DCD. 9) DCD will also monitor and compliance project base testing and preserve all original documents. 10) Concerned officials from respective Departments :- a) Concerned official of DCD Technical team i. Engr. Md Mominur Rouf (AGM-DC) ii. Engr. Laila Noor (SrM-SD) iii. Engr. Mohsinul Azad (SrEXC-SD) iv. Engr. Abir Hossain (EXC-SD) v. Engr. Farhat Aziz Sheen (EXC-SD) b) Laboratory-in-Charge i. Accountant (Central Store) c) Laboratory Assistant i. Site Assistant (Central Store) d) Maintenance Works i. Electrical maintenance support will be provided by EWD Maintenance wing prior receiving the requisition from DCD. Necessary cost up to Tk.1500/- will be borne by Project pretty cash where the Lab is attached & relevant approval may be taken from concerned RH.
  • 4. Page 3 of 12 ii. Mechanical & others maintenance support will be provided by MRD prior receiving the requisition from DCD. Necessary cost up to TK.2500/- will be borne by Project pretty cash where the Lab is attached & relevant approval may be taken from concerned RH.. iii. Calibration & other up gradation (if any) will be performed by external agencies prior Management approval through DCD. iv. Hydraulic oil for machineries and other routine maintenance items will be supplied by IM section prior requisition from DCD. v. Routine maintenance will be done by Lab In Charge. DCD will monitor. 11) Responsibilities in Details: a) Responsibilities of Lab In-Charge: i. To manage overall activities of the Lab. ii. To maintain all records, Files, Registry book of the Lab. iii. To receive Specimen from projects and ensure specification(quality of sample) requirements. iv. To co-ordinate with the Technical Team. v. Report Disbursement. vi. To supervise Lab Assistant activities. vii. To ensure due maintenance of the equipments. b) Responsibilities of Technical Team [DCD]: i. To perform the test with the help of Lab Assistant. ii. To prepare the Test Report. iii. To prepare Testing Schedule. iv. To ensure timely performing tests. v. Technical vetting of reports (if required) through Consultants. vi. To preserve the original Reports in respective File of DCD. c) Responsibilities of Lab Assistant: i. To operate the Machine. ii. To preserve cylinders. iii. To perform Curing. iv. Tested Cylinders disposal. v. To provide necessary supports to the Lab-in-Charge and the Technical Team. vi. To ensure Security of the Lab.
  • 5. Page 4 of 12 12) Responsibilities of Area Head(AH) & Project in Charge(PIC) i. To ensure proper sampling, preservation and timely send the sample to concerned Lab as in this manual. [as per Internal memo on 13/11/10) ii. To fill up the checklist as Annexure-1 and sent to GMPO with a copy to AGMDC. 14) Cube Making Apparatus: i. Cube moulds of (15 X 15 X 15) cm size [minimum 3 no for each set] ii. Trowel iii. Sampling Scoop iv. (25X25X400)mm square steel tamping rod with lower end flat / STEEL BAR 16MM DIA AND 60CM LONG v. 15cm long MS flat bar vi. Wooden/rubber Hammer vii. Wrench viii. Steel BRASH ix. Scraper x. STEEL SCALE xi. STEEL PAN xii. MIXTURE MACHINE xiii. Mould releasing oil ETC.
  • 6. Page 5 of 12 CUBE MOULD TROWEL SCOOP TAMPING ROD RUBBER HAMMER WRENCH
  • 7. Page 6 of 12 STEEL BRUSH SCRAPER STEEL SCALE STEEL PAN MIXTURE MACHINE MOULD RELEASING OIL
  • 8. Page 7 of 12 15) Cube Making Procedure: i. Separate the mould assembly and clean all interior faces, base with scraper to remove rust/cement coating. ii. Assemble cube moulds checking every dimension with steel scale /15cm long MS flat bar. iii. Oil the interior surface of the mould with mould releasing oil to prevent adhesion of concrete. Don’t use excess oil. iv. Sample should be true representative of concrete being used. v. For site mixing, mixing time should be at least one minute or 20 revolutions of the mixer from adding all aggregates to obtain a homogeneous mix. vi. For ready mix concrete, before collecting concrete it should be mixed properly in the mixer truck. vii. Sample collecting pan should be near, clean and free from any loose material. Collecting pan may be slightly moist with water but staking of water should be avoided. viii. At least one set (3cubes) sample should be taken from the same batch / mix. ix. Fill the concrete in the molds in layers approximately 5 cm thick (total 3 layers). x. Cube moulds of (15 X 15 X 15) cm size [minimum 3 no for each set]. xi. Each layer should be compacted BY 35 STROKES with tamping ROD [STEEL BAR 16MM DIA AND 60CM LONG, BULLET POINTED AT LOWER END] OR 25STROKES WITH TAMPING BAR [25MM SQUARE AND 400MM LENGTH, lower end flat] xii. Concrete should poured in the mould and tempered properly so as not to have any voids. xiii. The top surface of the specimen should be made even and smooth. This is done by putting cement paste and spreading smoothly on whole area of specimen and smoothen it with trowel. xiv. Vibrate the mould using rubber / wooden hammer to remove air content/ voids from concrete. xv. Store the cube moulds in a place which is free from vibration and cover the surface of the concrete with a piece of damp sacking for initial 16 to 24 hours. xvi. After 24 hours of casting cubes, remove cubes from moulds. For ready mix concrete sometimes it may take more than 24 hours to harden the concrete in that case wait until concrete gains sufficient hardness. xvii. After removing from mould mark casting date and name of structure for which concrete being used on the cubes with a permanent marker. Submerge cubes under clean water for curing.
  • 9. Page 8 of 12 xviii. After 28 days take out cubes from curing tank. xix. Send to laboratory / testing Authority for test. xx. During transportation care should be taken to avoid any damage (broken edge) of cubes. 16) Common Reasons behind the Failure of Concrete Test RESULTS: i. High Water Cement Ratio. ii. Use Inferior quality as well as improper gradation of stone chips / brick chips. iii. Insufficient FM & poor gradation of Sand. iv. Quality of Cement. v. Inappropriate mixing procedure & timing. vi. Faulty sampling. vii. Inadequate and inaccurate time of curing. viii. Adulteration of coarse and fine aggregate such as mud, clay, coal, wood or other organic materials etc. ix. Unskilled operation, handling and transportation. x. Calibration of Machineries. xi. Carelessness during testing like sample placement and loading. xii. FEW PRACTICAL Problems observed in different Projects:  Cubes are not found uniform size and shape.  Too many pores in cube surfaces.  Sending cube to lab without SSD condition(Saturated surface dry Condition)  Broken edges  Surface undulation(not leveled and smooth) etc.
  • 10. Page 9 of 12 Cubes not having uniform shape
  • 11. Page 10 of 12 Having pores at cube surface Cubes not in “SSD” condition
  • 12. Page 11 of 12 Undulation surface Broken Edges
  • 13. Page 12 of 12 ANNEXURE-1 Asset Development & Holdings Ltd. 91 Gulshan,Dhaka Cube Sent for Testing to BUET & ACL Checking Form Project: Address: Sl Structural Item to be Checked Sample list for BRTC & ACL Date Checked & signed by PIC Checked by AH Remarks Sign Date 1 Pile BRTC(1 set) ACL(at every 40 piles intervals) 2 Pile Cap BRTC(1 set) ACL(1 set) 3 Footing BRTC(1 set) ACL(1 set) 4 Ground Floor Column BRTC(1 set) ACL(1 set) 5 All others Floor Column ACL(Three successive floor intervals) 1st Floor 4th Floor 8th Floor 6 Basement Roof BRTC(1 set) ACL(1 set) 7 Ground Floor Roof BRTC(1 set) ACL(1 set) 8 All other Roof Slabs BRTC(Three successive roof slabs intervals) 1st Floor 4th Floor 8th Floor ACL(For all roof slab) 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor 7th Floor 8th Floor