Mega Projects not Mega Problems
With
Intro
The rise of the Gigaproject
Customer success –Parsons
Aconex demo
Q&A
Agenda
Janet Poses
Bob Prieto
Hans Hoppe
David Shearon
Bob Prieto
Chairman & CEO - Strategic Program Management
Author – The GIGA Factor Program
Veteran executive of Fluor and Parsons Brinckerhoff
rpstrategic@Comcast.net
Strategic Program Management LLC
2/3 FAIL
WHY?
Recovering to the
Baseline
Corrections may act to increase
inefficiency of execution as
resources are “jerked” from one
task to another
PMTHEORY MUST CHANGE
 Management endeavors to introduce regularity in a world that
will never allow that to happen.
 Fayol’s plan, organize, direct, coordinate, and control are now
expanded to include confirming, monitoring, engaging,
influencing, and evolving.
 Project management must create context, capacities, and
capabilities.
“It’s not about perfecting an imperfect
model, it is about creating a new one.”
EXTENDED FOCUS OF LARGE COMPLEX PROJECTS
Classical Focus Extended Focus
Project readiness Owner readiness
Output focus Emergent outcomes (Multi-finality)
Tasks and transformative
flows
Flows including emergent
influencing and induced flows
Stakeholder management Stakeholder engagement (partners
in success)
Organize, direct, coordinate,
and control
Confirm, monitor, engage,
influence, evolve
IMPLICATIONS OF SCALE & COMPLEXITY
In a Nutshell
• Expanded/Strengthened
Foundations
• Transformational Process
(Traditional)View Not Enough
• Focus on Flows
• Semi-Permeable Boundary
 Simple Risk Relationships
 Complex Risk Relationships
STRENGTHENED FOUNDATIONS
 Owner’s readiness
Probability of the Improbable
Normal Cauchy
5 sigma
event
1 in 3.5 million 1 in 16
30 sigma
event
1 in 2.0 x 10 197 1 in 94
MEGAPROJECTS DO NOT FOLLOW
CLASSICALTRANSFORMATION
MEGAPROJECTS REQUIRE CHANGED LEADERSHIP
BEHAVIORS
Traditional Leadership Behaviors New Leadership Behaviors
Individual leadership vs. Group Cross Project Leadership
Control and order vs. Motivation and movement
Scientific management vs. Transformative leadership
Outputs focus vs. Shared outcomes focus
Assignment and directive vs. Agreement and acceptance of goals
Hierarchical and siloed vs. Project-wide flat communication and information
structures
Acceptance of normative vs. Questioning (assumption, process, outputs)
Adversarial or transactional approach vs. Collaboration and information sharing with
stakeholders
Management of tasks vs. Management of flows
Centralized decision making vs. Engaged and decentralized decision making
MEGAPROJECT CHALLENGES
Baselines are not accurate
Preliminary work not complete; risks not understood or
provided for
Time not valued
$$$ not understood
MEGAPROJECT CHALLENGES CONTINUED
Basis of design too narrow
Weak change management processes
Project management theory does not serve
Megaprojects
Inadequate owner experience/capabilities
Frameworks for life cycle analysis are inadequate
MEGAPROJECT ADVICE (1) –
STRENGTHEN FOUNDATIONS
Strategic Business Outcomes are #1 reason projects fail
Owner’s organizations are not ready
Baseline schedules and estimate are optimistic
Scope baselines must be “fit for purpose” and fixed
Low frequency, high impact risks are prematurely screened
out
MEGAPROJECT ADVICE (1) –
STRENGTHEN FOUNDATIONS (CONTINUED)
Track assumptions –
they migrate
Expand risk focus
Recognize risk profiles
change over time
MEGAPROJECT ADVICE (2)
USE NEW GOVERNANCE STRUCTURES
Top level RACI at outset of
program
Continuing focus on
program and organizational
alignment
Megaproject Dashboards
Will NeedToTrack
Outcomes Oriented
Parameters
MEGAPROJECT ADVICE (2)
USE NEW GOVERNANCE STRUCTURES (CONTINUED)
Formal readiness assessments
Performance based contracting, compensation and
management
Recognition of organizational change management role
Programs consist of “beginnings, middles and ends”
MEGAPROJECT ADVICE (3)
FOCUS ON FLOWS
Manage the arrows not just the tasks
Manage the “white space”
Ensure packaging and phasing enhances project schedule
Create supply chain opportunities through packaging
Drive program logistics plan
Project management must strengthen its focus on flow
management
MEGAPROJECT ADVICE (4)
RECOGNIZE MEGAPROJECT IS NOT BOUNDED
We Need to Improve Performance Assessment
Weaknesses
1.We do not “see” leading indicators well
(They get lost in the volumes of data)
2.We do not see the complexity of challenges embedded
in the project plan
Opportunity – Big Analytics
(We already have Big Data, now we need to be able to use it)
NEW PARADIGM FOR PROJECT CONTROL
•Attention to flows arising from outside the project
•Increased use of big analytics not only on project
performance data but also on a myriad of external data
sources.
•Project controls must be outward and forward
looking
CONCLUSION - MEGATHOUGHTS
1. Expand and Strengthen Foundations
2. Transformational ProcessView Not
Enough
3. Focus on Flows
4. Plan for Semi-Permeable Boundary
5. Stakeholder engagement is essential
Hans Hoppe
Principal Program Controls Manager
Parsons
“Parsons is committed to the
highest standards of integrity in
everything we do and to
transparency in all of our
processes...”
13,000+ employees - 70 years of experience
Project Roles:
– Program Management Consultant (PMC)
– Designer
– Program Management / Construction
Management (PMCM)
– Construction Manager (CM)
– APD
– Design-Build (DB)
– Public Private Partnership (PPP)
Industries:
– Infrastructure: Aviation, Rail,
Transportation, Bridge & Tunnel
– Industrial: Water/Wastewater,
Environmental, Telecom, O&G/Energy
– U.S. Federal: Environmental, Infrastructure,
Security, Defense
“Integrity. Ethics. Innovation. Parsons named as a
World’s Most Ethical Company for Eighth Year in a
Row.”
3 points of potential failure to watch for
1. Project start without the necessary scope, roles and systems in place
2. Lack of a collaborative mindset across the shared leadership team
3. Contracts terms and language which do not support the overall goal of
project success
Keys to mega project success
1. Take the time to set up and kick off the project correctly
2. Identify key challenges/risks
3. Implement proven structure and strategies
4. Use appropriate tools and systems that can accommodate your project
processes and needs
5. Use modern technology to manage volume and provide intelligence to data
Benefits of anticipating key challenges / risks
• Eliminate potential Error & Omissions (E&O) claims
• Design Consultant on a highly technical / complex rail project
• Many owner driven changes during design
• Virtually eliminated the chance of E&O claims
• Implementing requirements traceability tool with robust
change management processes
• Expedite change management processes
• Mega aviation program with many Contractors
• Forecasted the need for comprehensive
document/information management
• Able to invalidate Contractor’s claim within 48 hours
Cross organizational leadership
• Challenges of shared responsibility and risk
• Importance of leading by example to set the culture
• New tools needed to manage this type of structure
• project tools not company tools
Evolution from cross organizational collaboration
to cross organizational leadership
Cross organizational leadership example
• Project: Large aviation terminal expansion
• Challenges: Stakeholder management rather than engagement
• Cross organizational leadership team
• Mix of client and PM consulting firms to form an Enterprise Program Management (EPM) Team
• Set up for success
• Contracting style and language
• Accountability
• Project administration
• Process management
Establishing Enterprise Governance
Many Disparate Projects versus a Single Integrated Program
Common processes and cadence
• Across organizations
• Across disciplines
• Across contracts
What to look for in project-wide systems and tools
• Security (neutrality)
• Visibility / Transparency
• Configurability
• Insights (forward looking)
• Proven
Client
Contractor
PM
Subcontractor
Results on Interstate 405
• Improved submittal process reduces errors, rework and claims, helping
reduce contingency by US$1.375M
• 33% reduction on technical documents review cycles. With 35 reviewers, this
is an estimated savings of $5.5M over the project life.
• Automated utility tracking to reallocate three full time engineering resources.
“Aconex enabled project team members to manage
each of their specific processes using easily
configurable workflows.”
Mega Projects not Mega Problems
David Shearon
Solutions Consultant
Aconex
33
Time Lapse Video of Denver International Airport
Field
Inspections
Connecting teams project-wide
OperateConstructDesignBidPlan
Document
Control
RFIs &
Change Orders
Bidding &
Tenders
Workflows &
Approvals
BIM
Collaboration
Submittals Handover to
Operations
Cost
Management
Dashboards
& Reporting
In projects executed
on the platform
$1+
trillion
Documents managed
with complete auditability
1.2+
billion
User organizations
Interfacing efficiently
60+
thousand
Foresight and visibility to prevent surprises
Portfolio
Project
Process
Tasks
Every project member on a connected
platform with a single view
Enterprise-wide Collaboration
Line-of-sight into issues
Early Warnings & Predictive Insights
Unified project controls for a single
view of project performance
Integrated Project Controls
Connected Cost: Integrated, Configurable, Enterprise-wide
A modern collaborative project controls solution integrating cost, schedule, contracts & project information
Packages: Improved efficiency, productivity and quality
• Allow documentation and correspondence to be broken
down into discrete controlled sections, or ‘packages.’
• Better manage the many project processes through
design, construction and completion of the project.
Design Management
Configuration Management
Work Packaging
Demo: Mega Projects not Mega Problems
• Overview
• Insights
• Project controls
• BIM
• Packages
• Configurable workflows
We presented a live Aconex demo. Please view your demo at aconex.com/Demo.
Recap: Mega Projects not Mega Problems
• Implement tools and processes
that support collaborative
leadership.
• Use flexible systems that support
your project team and structure.
• Ensure project-wide insights so
you get advanced warning into
any project impacts.
Mega Projects not Mega Problems
Our thanks to Parsons and Strategic Program Management LLC
and to you for attending
Learn more at
aconex.com/Demo

More Related Content

PPTX
Mega project not mega problems session 2
PPTX
Digital transformation webinar amer slideshare
PDF
Avoid the risk and streamline your project controls
PPTX
Unlocking Engineering and Construction performance webinar apac slideshare
PPTX
Keep your project moving with aconex contract administration webinar slides
PPTX
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
PPTX
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
PDF
Optimize bim for reducing errors
Mega project not mega problems session 2
Digital transformation webinar amer slideshare
Avoid the risk and streamline your project controls
Unlocking Engineering and Construction performance webinar apac slideshare
Keep your project moving with aconex contract administration webinar slides
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
Optimize bim for reducing errors

What's hot (20)

PDF
Building castles on sand - Project Management in distributed project environment
DOC
Knox, Terrance_Resume_Comm_Sept-2015_Final
PPTX
A Beginner's Guide to IT Project Management
PPT
Chap01 introduction to project management
DOCX
Mike_Kuenkel_Complete Resume_20150422
PPT
PPT
Klastorin parte1 1
PDF
Principles of program governance
PDF
Basic Software Engineering
PPT
Infrastructure Project Manager
PDF
James dimas it infrastructure approach
PDF
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
PDF
Project Controls Expo, 18th Nov 2014 - "The 6 Key Elements for Improving Proj...
PDF
Resource scheduling & capacity planning for project online webinar 25 oct18
PPTX
10 reasons why projects fail or common mistakes to avoid
PDF
Theory of Project Management
DOC
An Introduction to Project management(project management tutorials)
PPTX
10 me667 chap5 coordination and control
PDF
The fact that your poject is agile is not (necessarily) a cost driver arlen...
Building castles on sand - Project Management in distributed project environment
Knox, Terrance_Resume_Comm_Sept-2015_Final
A Beginner's Guide to IT Project Management
Chap01 introduction to project management
Mike_Kuenkel_Complete Resume_20150422
Klastorin parte1 1
Principles of program governance
Basic Software Engineering
Infrastructure Project Manager
James dimas it infrastructure approach
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Project Controls Expo, 18th Nov 2014 - "The 6 Key Elements for Improving Proj...
Resource scheduling & capacity planning for project online webinar 25 oct18
10 reasons why projects fail or common mistakes to avoid
Theory of Project Management
An Introduction to Project management(project management tutorials)
10 me667 chap5 coordination and control
The fact that your poject is agile is not (necessarily) a cost driver arlen...
Ad

Similar to Mega project not mega problems session 1 (20)

PPTX
Project Management Framework
PPT
PM-1 Overview.ppt
PPTX
PM 01 - Introduction to Project Management
PPTX
Strategies for successful_engineering_management
PDF
Challenging Aspects of Modern Project Management
PDF
ICT 4109.pdf
PPT
Software Engineering (Software size estimation).ppt
PPT
Introduction To Project Management
PPT
Spm lecture-2
DOCX
Pmbok
PDF
Towards a hybrid approach between agile and traditional methods
PPTX
Unit 1.pptx
PDF
Entra lecture6 PM1.pdf
PPT
1 ch1
PPTX
INTRO.pptx
PDF
Project Portfolio Management
PDF
1. introduction
PDF
Advancing Engineering with AI through the Next Generation of Strategic Projec...
PPTX
Project management unit 5(1)
Project Management Framework
PM-1 Overview.ppt
PM 01 - Introduction to Project Management
Strategies for successful_engineering_management
Challenging Aspects of Modern Project Management
ICT 4109.pdf
Software Engineering (Software size estimation).ppt
Introduction To Project Management
Spm lecture-2
Pmbok
Towards a hybrid approach between agile and traditional methods
Unit 1.pptx
Entra lecture6 PM1.pdf
1 ch1
INTRO.pptx
Project Portfolio Management
1. introduction
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Project management unit 5(1)
Ad

More from Aconex (20)

PPTX
Webinar contract management aconex 6 septembre 2018
PDF
Webinar contract management aconex 5 juillet 2018
PPTX
5 methods session 2 webinar slideshare systems co
PPTX
Collaborative project controls across your entire portfolio
PDF
Atelier aconex bim_world_2018
PDF
Aconex business breakfast Praesentation
PPTX
Modernizando controles de proyecto
PPTX
Security best ways to protect your intellectual capital
PDF
Aconex connected cost webinar - drive project performance
PPTX
Digital Transformation 2018
PPTX
The rise of the “gigaproject”
PDF
How to successfully target and secure OBOR projects
PPTX
Global Trends in Delivery Projects
PPTX
Le BIM en support des études d’exécution
PPTX
Tendencias actuales en la entrega de proyectos PPP/UTEs-Consorcios
PPTX
Modernize project controls to ensure project success aecom
PPTX
Une plateforme collaborative qui met le BIM au cœur de votre gestion de proje...
PDF
Atelier BIM Aconex Présentation Nodal (French)
PPTX
"Show me the ROI" – concrete results from process improvement
PPTX
Webinar BIM Gagnez en productivité sur vos projets BIM (French)
Webinar contract management aconex 6 septembre 2018
Webinar contract management aconex 5 juillet 2018
5 methods session 2 webinar slideshare systems co
Collaborative project controls across your entire portfolio
Atelier aconex bim_world_2018
Aconex business breakfast Praesentation
Modernizando controles de proyecto
Security best ways to protect your intellectual capital
Aconex connected cost webinar - drive project performance
Digital Transformation 2018
The rise of the “gigaproject”
How to successfully target and secure OBOR projects
Global Trends in Delivery Projects
Le BIM en support des études d’exécution
Tendencias actuales en la entrega de proyectos PPP/UTEs-Consorcios
Modernize project controls to ensure project success aecom
Une plateforme collaborative qui met le BIM au cœur de votre gestion de proje...
Atelier BIM Aconex Présentation Nodal (French)
"Show me the ROI" – concrete results from process improvement
Webinar BIM Gagnez en productivité sur vos projets BIM (French)

Recently uploaded (20)

PDF
Empathic Computing: Creating Shared Understanding
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PPT
Teaching material agriculture food technology
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Electronic commerce courselecture one. Pdf
PDF
Modernizing your data center with Dell and AMD
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PPTX
Cloud computing and distributed systems.
PDF
KodekX | Application Modernization Development
Empathic Computing: Creating Shared Understanding
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Per capita expenditure prediction using model stacking based on satellite ima...
Understanding_Digital_Forensics_Presentation.pptx
Teaching material agriculture food technology
The Rise and Fall of 3GPP – Time for a Sabbatical?
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Electronic commerce courselecture one. Pdf
Modernizing your data center with Dell and AMD
Building Integrated photovoltaic BIPV_UPV.pdf
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Digital-Transformation-Roadmap-for-Companies.pptx
The AUB Centre for AI in Media Proposal.docx
Dropbox Q2 2025 Financial Results & Investor Presentation
Diabetes mellitus diagnosis method based random forest with bat algorithm
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Cloud computing and distributed systems.
KodekX | Application Modernization Development

Mega project not mega problems session 1

  • 1. Mega Projects not Mega Problems With
  • 2. Intro The rise of the Gigaproject Customer success –Parsons Aconex demo Q&A Agenda Janet Poses Bob Prieto Hans Hoppe David Shearon
  • 3. Bob Prieto Chairman & CEO - Strategic Program Management Author – The GIGA Factor Program Veteran executive of Fluor and Parsons Brinckerhoff rpstrategic@Comcast.net Strategic Program Management LLC
  • 5. WHY? Recovering to the Baseline Corrections may act to increase inefficiency of execution as resources are “jerked” from one task to another
  • 6. PMTHEORY MUST CHANGE  Management endeavors to introduce regularity in a world that will never allow that to happen.  Fayol’s plan, organize, direct, coordinate, and control are now expanded to include confirming, monitoring, engaging, influencing, and evolving.  Project management must create context, capacities, and capabilities. “It’s not about perfecting an imperfect model, it is about creating a new one.”
  • 7. EXTENDED FOCUS OF LARGE COMPLEX PROJECTS Classical Focus Extended Focus Project readiness Owner readiness Output focus Emergent outcomes (Multi-finality) Tasks and transformative flows Flows including emergent influencing and induced flows Stakeholder management Stakeholder engagement (partners in success) Organize, direct, coordinate, and control Confirm, monitor, engage, influence, evolve
  • 8. IMPLICATIONS OF SCALE & COMPLEXITY In a Nutshell • Expanded/Strengthened Foundations • Transformational Process (Traditional)View Not Enough • Focus on Flows • Semi-Permeable Boundary  Simple Risk Relationships  Complex Risk Relationships
  • 9. STRENGTHENED FOUNDATIONS  Owner’s readiness Probability of the Improbable Normal Cauchy 5 sigma event 1 in 3.5 million 1 in 16 30 sigma event 1 in 2.0 x 10 197 1 in 94
  • 10. MEGAPROJECTS DO NOT FOLLOW CLASSICALTRANSFORMATION
  • 11. MEGAPROJECTS REQUIRE CHANGED LEADERSHIP BEHAVIORS Traditional Leadership Behaviors New Leadership Behaviors Individual leadership vs. Group Cross Project Leadership Control and order vs. Motivation and movement Scientific management vs. Transformative leadership Outputs focus vs. Shared outcomes focus Assignment and directive vs. Agreement and acceptance of goals Hierarchical and siloed vs. Project-wide flat communication and information structures Acceptance of normative vs. Questioning (assumption, process, outputs) Adversarial or transactional approach vs. Collaboration and information sharing with stakeholders Management of tasks vs. Management of flows Centralized decision making vs. Engaged and decentralized decision making
  • 12. MEGAPROJECT CHALLENGES Baselines are not accurate Preliminary work not complete; risks not understood or provided for Time not valued $$$ not understood
  • 13. MEGAPROJECT CHALLENGES CONTINUED Basis of design too narrow Weak change management processes Project management theory does not serve Megaprojects Inadequate owner experience/capabilities Frameworks for life cycle analysis are inadequate
  • 14. MEGAPROJECT ADVICE (1) – STRENGTHEN FOUNDATIONS Strategic Business Outcomes are #1 reason projects fail Owner’s organizations are not ready Baseline schedules and estimate are optimistic Scope baselines must be “fit for purpose” and fixed Low frequency, high impact risks are prematurely screened out
  • 15. MEGAPROJECT ADVICE (1) – STRENGTHEN FOUNDATIONS (CONTINUED) Track assumptions – they migrate Expand risk focus Recognize risk profiles change over time
  • 16. MEGAPROJECT ADVICE (2) USE NEW GOVERNANCE STRUCTURES Top level RACI at outset of program Continuing focus on program and organizational alignment Megaproject Dashboards Will NeedToTrack Outcomes Oriented Parameters
  • 17. MEGAPROJECT ADVICE (2) USE NEW GOVERNANCE STRUCTURES (CONTINUED) Formal readiness assessments Performance based contracting, compensation and management Recognition of organizational change management role Programs consist of “beginnings, middles and ends”
  • 18. MEGAPROJECT ADVICE (3) FOCUS ON FLOWS Manage the arrows not just the tasks Manage the “white space” Ensure packaging and phasing enhances project schedule Create supply chain opportunities through packaging Drive program logistics plan Project management must strengthen its focus on flow management
  • 19. MEGAPROJECT ADVICE (4) RECOGNIZE MEGAPROJECT IS NOT BOUNDED We Need to Improve Performance Assessment Weaknesses 1.We do not “see” leading indicators well (They get lost in the volumes of data) 2.We do not see the complexity of challenges embedded in the project plan Opportunity – Big Analytics (We already have Big Data, now we need to be able to use it)
  • 20. NEW PARADIGM FOR PROJECT CONTROL •Attention to flows arising from outside the project •Increased use of big analytics not only on project performance data but also on a myriad of external data sources. •Project controls must be outward and forward looking
  • 21. CONCLUSION - MEGATHOUGHTS 1. Expand and Strengthen Foundations 2. Transformational ProcessView Not Enough 3. Focus on Flows 4. Plan for Semi-Permeable Boundary 5. Stakeholder engagement is essential
  • 22. Hans Hoppe Principal Program Controls Manager Parsons “Parsons is committed to the highest standards of integrity in everything we do and to transparency in all of our processes...”
  • 23. 13,000+ employees - 70 years of experience Project Roles: – Program Management Consultant (PMC) – Designer – Program Management / Construction Management (PMCM) – Construction Manager (CM) – APD – Design-Build (DB) – Public Private Partnership (PPP) Industries: – Infrastructure: Aviation, Rail, Transportation, Bridge & Tunnel – Industrial: Water/Wastewater, Environmental, Telecom, O&G/Energy – U.S. Federal: Environmental, Infrastructure, Security, Defense “Integrity. Ethics. Innovation. Parsons named as a World’s Most Ethical Company for Eighth Year in a Row.”
  • 24. 3 points of potential failure to watch for 1. Project start without the necessary scope, roles and systems in place 2. Lack of a collaborative mindset across the shared leadership team 3. Contracts terms and language which do not support the overall goal of project success
  • 25. Keys to mega project success 1. Take the time to set up and kick off the project correctly 2. Identify key challenges/risks 3. Implement proven structure and strategies 4. Use appropriate tools and systems that can accommodate your project processes and needs 5. Use modern technology to manage volume and provide intelligence to data
  • 26. Benefits of anticipating key challenges / risks • Eliminate potential Error & Omissions (E&O) claims • Design Consultant on a highly technical / complex rail project • Many owner driven changes during design • Virtually eliminated the chance of E&O claims • Implementing requirements traceability tool with robust change management processes • Expedite change management processes • Mega aviation program with many Contractors • Forecasted the need for comprehensive document/information management • Able to invalidate Contractor’s claim within 48 hours
  • 27. Cross organizational leadership • Challenges of shared responsibility and risk • Importance of leading by example to set the culture • New tools needed to manage this type of structure • project tools not company tools Evolution from cross organizational collaboration to cross organizational leadership
  • 28. Cross organizational leadership example • Project: Large aviation terminal expansion • Challenges: Stakeholder management rather than engagement • Cross organizational leadership team • Mix of client and PM consulting firms to form an Enterprise Program Management (EPM) Team • Set up for success • Contracting style and language • Accountability • Project administration • Process management
  • 29. Establishing Enterprise Governance Many Disparate Projects versus a Single Integrated Program Common processes and cadence • Across organizations • Across disciplines • Across contracts
  • 30. What to look for in project-wide systems and tools • Security (neutrality) • Visibility / Transparency • Configurability • Insights (forward looking) • Proven Client Contractor PM Subcontractor
  • 31. Results on Interstate 405 • Improved submittal process reduces errors, rework and claims, helping reduce contingency by US$1.375M • 33% reduction on technical documents review cycles. With 35 reviewers, this is an estimated savings of $5.5M over the project life. • Automated utility tracking to reallocate three full time engineering resources. “Aconex enabled project team members to manage each of their specific processes using easily configurable workflows.”
  • 32. Mega Projects not Mega Problems David Shearon Solutions Consultant Aconex
  • 33. 33 Time Lapse Video of Denver International Airport
  • 34. Field Inspections Connecting teams project-wide OperateConstructDesignBidPlan Document Control RFIs & Change Orders Bidding & Tenders Workflows & Approvals BIM Collaboration Submittals Handover to Operations Cost Management Dashboards & Reporting In projects executed on the platform $1+ trillion Documents managed with complete auditability 1.2+ billion User organizations Interfacing efficiently 60+ thousand
  • 35. Foresight and visibility to prevent surprises Portfolio Project Process Tasks
  • 36. Every project member on a connected platform with a single view Enterprise-wide Collaboration Line-of-sight into issues Early Warnings & Predictive Insights Unified project controls for a single view of project performance Integrated Project Controls Connected Cost: Integrated, Configurable, Enterprise-wide A modern collaborative project controls solution integrating cost, schedule, contracts & project information
  • 37. Packages: Improved efficiency, productivity and quality • Allow documentation and correspondence to be broken down into discrete controlled sections, or ‘packages.’ • Better manage the many project processes through design, construction and completion of the project. Design Management Configuration Management Work Packaging
  • 38. Demo: Mega Projects not Mega Problems • Overview • Insights • Project controls • BIM • Packages • Configurable workflows We presented a live Aconex demo. Please view your demo at aconex.com/Demo.
  • 39. Recap: Mega Projects not Mega Problems • Implement tools and processes that support collaborative leadership. • Use flexible systems that support your project team and structure. • Ensure project-wide insights so you get advanced warning into any project impacts.
  • 40. Mega Projects not Mega Problems Our thanks to Parsons and Strategic Program Management LLC and to you for attending Learn more at aconex.com/Demo

Editor's Notes

  • #25: Stakeholders Owners not ready – scope and funding not adequately defined Organizations not sufficiently aligned Interfaces Between organizations Between disciplines Between office and field Between organization levels
  • #39: Overview, then Insights Project Controls BIM Packages Workflows AWS 5 Star demo site has Packages enabled and functioning. Andrew Barron and or Stewart Stead re: Packages. Stewart Stead was very involved in the Beta program. The whole demo is 15. Probably need about 5 minutes minimum. Can use packages to manage design review process or quality sign off. Data sheet and deep dive on Packages from Gordon Sets of docs – grouped together, like a lot of work, QA a lot of correspondence and documentation and be able to manage as a group. Can group without using meta data. If rail project, can keep an older version for a previous project. Team binder has this functionality Beta: Fletcher LendLease Simic Bechtel Tim Crisp left John Holland