S.M.E.D (Single minute Exchange of day)
                            Metal structure calculation



CALCULATION OF THE STRUCTURE

Two hypothesis.
      1. We suppose the load will be leant just on one beams.
      2. We suppose the load distributed equally on each .


      First :

      The heaviest mould weighs 3200kg , We suppose a distributed load
      3200Kg/540mm =6Kg/mm



                     6Kg/mm




R1                                             R2


We use a square hollow beam:

R1 + R 2 = 6 • 540
6 • 540 • 270 = 540 R1
R1 = 1620 Kg
R 2 = 1620 Kg

Maximum moment


          4200kg




1176000
S.M.E.D (Single minute Exchange of day)
                                Metal structure calculation




Q = −6 x + 1620
Mf = −3 x 2 + 1620 x

x = 270mm
Mf max = −3 • 2702 + 1670 • 270
Mf max = 218700 Kg • mm

Square hollow beam




Steel A-42

                                                    218000 Kg • m  L 
σ adm = 260 Kg           2                    260 =              • 
                    mm                                 L
                                                              4
                                                                  2
          M f max                                       
σ adm =             •x                                  12 
              Ix                              L = 18mm


          .


Square de 40.2               L=40mm (length) y e=2mm (thickness)




                                                  M f max                               M f max (Kg • mm )
W = 3.40cm3 = 3400mm 3                  σ adm =                   260 Kg        2   =
                                                      W                    mm              3400mm 3


Mf max = 884000 Kg • mm            Mf   max    > 218000     (Kg   • mm     )            Cumple
S.M.E.D (Single minute Exchange of day)
                                 Metal structure calculation


 Second hypothesis :




                     2Kg/mm




R1                                           R2

            R1 + R 2 = 2 • 540
            2 • 540 • 270 = 540 R1
            R1 = 1080 Kg
            R 2 = 1080 Kg



 Maximum moment

                     2Kg/mm




 R1


 Q = −2 x + 540
     Mf = − x 2 + 540 x


     x = 270 mm
     Mf max = (− 1) • 270 2 + 540 • 270
     Mf max = 72900 Kg • mm
S.M.E.D (Single minute Exchange of day)
                                Metal structure calculation




                                                    72900 Kg • m  L 
σ adm = 260 Kg           2                   260 =              • 
                    mm                                 L
                                                              4
                                                                 2
          M f max                                       
σ adm =             •x                                  12 
            Ix                                L = 12mm


          12mm de lado, the standard which fits best according to the regulation NBE
EA-95


          L= 40mm;           e = 2mm




                                                  M f max                                M f max (Kg • mm )
W = 3.40cm3 = 3400mm 3                 σ adm =                     260 Kg        2   =
                                                    W                       mm              3400mm3


Mf max = 884000 Kg • mm                Mf   max    > 72900   (Kg   • mm     )   Cumple




CALCULATION OF THE LIFT




Calculation of the total load lean on the lift

Ct = Cd + Ces

Cd = depots loaded; Ces = weight metallic structure.
S.M.E.D (Single minute Exchange of day)
                           Metal structure calculation


ρac= 7850 Kg / m 3 (Steel density).
ρpp = 1kg / m 3       (Polypropylene density)

Measurement of the depots:
   •   ∅235mm x 835
   •   ∅235mm x 605

Cálculation of the depot´s load


   M                                                   π • 0.2352
ρ=                M = ρ • V : M = 7851• 0.850 •                     = 284Kg   Deposito1
   V                                                       4
   M                                  π • 0.2352
ρ=                M = 7851• 0.605 •                = 206Kg                    Deposito2
   V                                      4


Calculation of the metallic structure load

M = ρ • V Ves = L • as = 3.555 • 0.060 2 = 0.012798 mm 3 Volumen de la estructura metálica
M = 7850 • 0.012798 = 100 Kg
Ct = Cd + Ces Ct = 490 + 100 = 590
Suponiendo que los deposito esta n llenos

                                              590 kg
                        Seccion A-A




                      E:1/5
S.M.E.D (Single minute Exchange of day)
                                Metal structure calculation


section A-A




                     Q=590Kg




                     Mf=590*50Kgmm




                                                               :
     •     Sheer stress.
     •     Bending moment.


Sheer stress
                      a     a
                 590 •  •a•
     Q • Me
τ≥          ;         2     2 ≤ 26• 0.5        a = 12mm      (sec ción maciza)
      b•I               a 4
                     a•
                        12
Momento flector

     Mf           590 • 50 • 3 a
σ≥       y : 26 =             • ;    a = 30mm       Con un coeficiente de seguridad N=3
      I               a4       2
                      12
Estándar profile according to the regulations is 40.2




         Mf          590 • 50 • 3
σ≥          y : 26 ≥              • 20    do not meet the minimum security conditions
          I            66000
S.M.E.D (Single minute Exchange of day)
                           Metal structure calculation


profile 60.2
     Mf          590 • 50 • 3
σ≥      y : 26 ≥              • 30
      I            248000                  meet all the specifications



     (*)Meeting all the specifications according to the regulations NBE-EA95.




Calculation metal sheet nº7

                                     550 Kg.




                         59mm




     Sección B-B


Section B-B

                        550 Kg
   550*59

                                 b


                    a
Sheer stress

                    b        b
               550 • • 20 •
   Q • Me
τ≥        ;         2        2 ≤ 26• 0.5          b = 5mm
    b•I             20 • b 4
                 b•
                      12
S.M.E.D (Single minute Exchange of day)
                               Metal structure calculation




     Bending moment


           Mf          550 • 59 • 3 b
     σ≥       y : 26 ≥             •     b = 10.5mm
            I            20 • b 4    2
                           12
     The metal sheet has 11mm of thickness


     Calculation metal sheet nº8



                            550 Kg
      30

                                     a

Sección C-C
                   60

     section C-C



                            550 Kg
        550*54
                                     b


                        a

     Bending moment


           Mf          550 • 54 • 3 b
     σ≥       y : 26 ≥             •     b = 8mm      N=3
            I            40 • b 4    2
                           12

     The thickness is of 8mm.

     Screw calculation for piece 9
S.M.E.D (Single minute Exchange of day)
                            Metal structure calculation




      N            225(*) • 3                     De diámetro
σ=          26 ≥              D = 2 mm
      A             D •π •8



Sheer screw calculation


      Q             225(*) • 3
τ =         13 ≥                 D = 8mm Cogemos el mayor, necesitamos un tornillo de
      A             π •D2
                        4
métrica 8

More Related Content

DOC
Metal Structure Calculations
DOC
Assignment [4] machining with solutions
PDF
Advanced Composites Final Paper
PDF
Eg stress in beam
DOC
Assignments metal cutting - 1
PDF
1 perhitungan-balok
PDF
The mineral reserves & reserves estimation using triangular methods
DOCX
theory of metal cutting assignment problems
Metal Structure Calculations
Assignment [4] machining with solutions
Advanced Composites Final Paper
Eg stress in beam
Assignments metal cutting - 1
1 perhitungan-balok
The mineral reserves & reserves estimation using triangular methods
theory of metal cutting assignment problems

What's hot (16)

PPTX
Production function economic
PPTX
Section 3
PDF
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PDF
AAE550_Final_LuQi
PDF
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
PDF
N30UH Grade Neodymium Magnets Data
PDF
X10703 (me8593)
DOCX
Structural building by engineer abdikani farah ahmed(enggalaydh)
PDF
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
PDF
Bending stress numericals unit 1 part 2
PDF
Slab panel desing sheet (1) (2)
PDF
Capítulo 11 mancais de contato rolante
PDF
Term project "Design of Slab Formwork"
PPTX
22564 emd 1.9 numericals
PPTX
22564 emd 1.11 numericals
PPTX
22564 emd 1.10 numericals
Production function economic
Section 3
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
AAE550_Final_LuQi
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
N30UH Grade Neodymium Magnets Data
X10703 (me8593)
Structural building by engineer abdikani farah ahmed(enggalaydh)
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
Bending stress numericals unit 1 part 2
Slab panel desing sheet (1) (2)
Capítulo 11 mancais de contato rolante
Term project "Design of Slab Formwork"
22564 emd 1.9 numericals
22564 emd 1.11 numericals
22564 emd 1.10 numericals
Ad

Viewers also liked (20)

PDF
Marketing Online B2B
PPTX
Rasmus Lassen, Byggechef i Københavns Ejendomme
PDF
عيب انتي بنت
PDF
Can Free Speech Survive The Social Media Mob?
PPTX
Bootstrap & Mobile-Web
PDF
Siri Guru Granth Sahib Ji
PPTX
Talent Gallery - Global Headhunting
PPTX
Når fremtiden forstyrrer
PDF
Infographic: Why Slamby?
PDF
How to create successful Employee Referral Program?
PDF
Sam Gedragsverandering
PPS
602 - Ants at work
PDF
Позиционирование подрядчика
PPSX
Saory,An.(by Averio)
PPS
Sirat Rasaul Allah
PDF
Ad mob 2010 mart istatistikleri-
PPT
YouTube felhasználói szemmel kontra ügynökségi gyakorlatban
PDF
How to attract and retain Gen Z?
PDF
Prezentace mobilního marketingu od PHOMEDIA s.r.o.
PPTX
Caracteristici avansate ale punctului de vânzare
Marketing Online B2B
Rasmus Lassen, Byggechef i Københavns Ejendomme
عيب انتي بنت
Can Free Speech Survive The Social Media Mob?
Bootstrap & Mobile-Web
Siri Guru Granth Sahib Ji
Talent Gallery - Global Headhunting
Når fremtiden forstyrrer
Infographic: Why Slamby?
How to create successful Employee Referral Program?
Sam Gedragsverandering
602 - Ants at work
Позиционирование подрядчика
Saory,An.(by Averio)
Sirat Rasaul Allah
Ad mob 2010 mart istatistikleri-
YouTube felhasználói szemmel kontra ügynökségi gyakorlatban
How to attract and retain Gen Z?
Prezentace mobilního marketingu od PHOMEDIA s.r.o.
Caracteristici avansate ale punctului de vânzare
Ad

Similar to Metal Structure Calculations (20)

PDF
TALAT Lecture 2301: Design of Members Example 9.4: Beam-column with cross weld
PDF
TALAT Lecture 2711: Design of a Helicopter Deck
PDF
M E C H A N I C S O F S O L I D S J N T U M O D E L P A P E R{Www
PPT
Engineering science lesson 6 2
XLS
Bridge rf cal sheet 0 1
PPTX
concreto trabajo sobre losas y vigas diseño
PDF
Measurements and Dimensional Analysis.pdf
PDF
Designofmachinemembers I Jntu Model Paper{Www.Studentyogi.Com}
PDF
D E S I G N O F M A C H I N E M E M B E R S I J N T U M O D E L P A P E R...
DOC
10346 07 08 examination paper
PDF
Research in Composites for Aero Engine Applications
DOC
1st basement b25
PDF
Exercises of bending_518
PDF
TALAT Lecture 2301: Design of Members Example 7.1: Concentrated force
PDF
Solutions completo elementos de maquinas de shigley 8th edition
PPT
Engineering science lesson 7
DOC
Formul me-3074683 Erdi Karaçal Mechanical Engineer University of Gaziantep
PDF
Capítulo 1 - Mecânica dos Fluidos
PDF
Fox solution
TALAT Lecture 2301: Design of Members Example 9.4: Beam-column with cross weld
TALAT Lecture 2711: Design of a Helicopter Deck
M E C H A N I C S O F S O L I D S J N T U M O D E L P A P E R{Www
Engineering science lesson 6 2
Bridge rf cal sheet 0 1
concreto trabajo sobre losas y vigas diseño
Measurements and Dimensional Analysis.pdf
Designofmachinemembers I Jntu Model Paper{Www.Studentyogi.Com}
D E S I G N O F M A C H I N E M E M B E R S I J N T U M O D E L P A P E R...
10346 07 08 examination paper
Research in Composites for Aero Engine Applications
1st basement b25
Exercises of bending_518
TALAT Lecture 2301: Design of Members Example 7.1: Concentrated force
Solutions completo elementos de maquinas de shigley 8th edition
Engineering science lesson 7
Formul me-3074683 Erdi Karaçal Mechanical Engineer University of Gaziantep
Capítulo 1 - Mecânica dos Fluidos
Fox solution

More from Bieito.o (7)

PDF
Pen Assembly Motion 1 Model (1
PPTX
Pen Assembly
PPTX
PresentacióN S.M.E.D
PDF
Pneumatic Colouring Elevator System
PDF
Lean Moulds
PDF
Pneum elevation deposit system
PDF
Drilling
Pen Assembly Motion 1 Model (1
Pen Assembly
PresentacióN S.M.E.D
Pneumatic Colouring Elevator System
Lean Moulds
Pneum elevation deposit system
Drilling

Metal Structure Calculations

  • 1. S.M.E.D (Single minute Exchange of day) Metal structure calculation CALCULATION OF THE STRUCTURE Two hypothesis. 1. We suppose the load will be leant just on one beams. 2. We suppose the load distributed equally on each . First : The heaviest mould weighs 3200kg , We suppose a distributed load 3200Kg/540mm =6Kg/mm 6Kg/mm R1 R2 We use a square hollow beam: R1 + R 2 = 6 • 540 6 • 540 • 270 = 540 R1 R1 = 1620 Kg R 2 = 1620 Kg Maximum moment 4200kg 1176000
  • 2. S.M.E.D (Single minute Exchange of day) Metal structure calculation Q = −6 x + 1620 Mf = −3 x 2 + 1620 x x = 270mm Mf max = −3 • 2702 + 1670 • 270 Mf max = 218700 Kg • mm Square hollow beam Steel A-42 218000 Kg • m  L  σ adm = 260 Kg 2 260 = •  mm L 4 2 M f max   σ adm = •x  12  Ix L = 18mm . Square de 40.2 L=40mm (length) y e=2mm (thickness) M f max M f max (Kg • mm ) W = 3.40cm3 = 3400mm 3 σ adm = 260 Kg 2 = W mm 3400mm 3 Mf max = 884000 Kg • mm Mf max > 218000 (Kg • mm ) Cumple
  • 3. S.M.E.D (Single minute Exchange of day) Metal structure calculation Second hypothesis : 2Kg/mm R1 R2 R1 + R 2 = 2 • 540 2 • 540 • 270 = 540 R1 R1 = 1080 Kg R 2 = 1080 Kg Maximum moment 2Kg/mm R1 Q = −2 x + 540 Mf = − x 2 + 540 x x = 270 mm Mf max = (− 1) • 270 2 + 540 • 270 Mf max = 72900 Kg • mm
  • 4. S.M.E.D (Single minute Exchange of day) Metal structure calculation 72900 Kg • m  L  σ adm = 260 Kg 2 260 = •  mm L 4 2 M f max   σ adm = •x  12  Ix L = 12mm 12mm de lado, the standard which fits best according to the regulation NBE EA-95 L= 40mm; e = 2mm M f max M f max (Kg • mm ) W = 3.40cm3 = 3400mm 3 σ adm = 260 Kg 2 = W mm 3400mm3 Mf max = 884000 Kg • mm Mf max > 72900 (Kg • mm ) Cumple CALCULATION OF THE LIFT Calculation of the total load lean on the lift Ct = Cd + Ces Cd = depots loaded; Ces = weight metallic structure.
  • 5. S.M.E.D (Single minute Exchange of day) Metal structure calculation ρac= 7850 Kg / m 3 (Steel density). ρpp = 1kg / m 3 (Polypropylene density) Measurement of the depots: • ∅235mm x 835 • ∅235mm x 605 Cálculation of the depot´s load M π • 0.2352 ρ= M = ρ • V : M = 7851• 0.850 • = 284Kg Deposito1 V 4 M π • 0.2352 ρ= M = 7851• 0.605 • = 206Kg Deposito2 V 4 Calculation of the metallic structure load M = ρ • V Ves = L • as = 3.555 • 0.060 2 = 0.012798 mm 3 Volumen de la estructura metálica M = 7850 • 0.012798 = 100 Kg Ct = Cd + Ces Ct = 490 + 100 = 590 Suponiendo que los deposito esta n llenos 590 kg Seccion A-A E:1/5
  • 6. S.M.E.D (Single minute Exchange of day) Metal structure calculation section A-A Q=590Kg Mf=590*50Kgmm : • Sheer stress. • Bending moment. Sheer stress a a 590 • •a• Q • Me τ≥ ; 2 2 ≤ 26• 0.5 a = 12mm (sec ción maciza) b•I a 4 a• 12 Momento flector Mf 590 • 50 • 3 a σ≥ y : 26 = • ; a = 30mm Con un coeficiente de seguridad N=3 I a4 2 12 Estándar profile according to the regulations is 40.2 Mf 590 • 50 • 3 σ≥ y : 26 ≥ • 20 do not meet the minimum security conditions I 66000
  • 7. S.M.E.D (Single minute Exchange of day) Metal structure calculation profile 60.2 Mf 590 • 50 • 3 σ≥ y : 26 ≥ • 30 I 248000 meet all the specifications (*)Meeting all the specifications according to the regulations NBE-EA95. Calculation metal sheet nº7 550 Kg. 59mm Sección B-B Section B-B 550 Kg 550*59 b a Sheer stress b b 550 • • 20 • Q • Me τ≥ ; 2 2 ≤ 26• 0.5 b = 5mm b•I 20 • b 4 b• 12
  • 8. S.M.E.D (Single minute Exchange of day) Metal structure calculation Bending moment Mf 550 • 59 • 3 b σ≥ y : 26 ≥ • b = 10.5mm I 20 • b 4 2 12 The metal sheet has 11mm of thickness Calculation metal sheet nº8 550 Kg 30 a Sección C-C 60 section C-C 550 Kg 550*54 b a Bending moment Mf 550 • 54 • 3 b σ≥ y : 26 ≥ • b = 8mm N=3 I 40 • b 4 2 12 The thickness is of 8mm. Screw calculation for piece 9
  • 9. S.M.E.D (Single minute Exchange of day) Metal structure calculation N 225(*) • 3 De diámetro σ= 26 ≥ D = 2 mm A D •π •8 Sheer screw calculation Q 225(*) • 3 τ = 13 ≥ D = 8mm Cogemos el mayor, necesitamos un tornillo de A π •D2 4 métrica 8