Monitoring Subcontracts
The views expressed in this presentation are DCAA's views and not
necessarily the views of other DoD organizations
Subcontracts

What should a contractor know about subcontracting:

 Subcontract Selection;
 Subcontracting Requirements, and
 Your responsibilities as a prime contractor.
See FAR 9-104.4
2
Subcontract Information

 The prime contractor (or higher-tier subcontractor) is
responsible for managing its subcontracts.
 Approval to subcontract out part of a Government
contract is not automatic.
 Higher-tier subcontractors must also manage their
subcontracts, even if they are not the prime contractor
on a Government contract.
3
Consent to Subcontract

FAR 44.204 (a) -- The contracting officer shall insert the clause at
52.244-2, Subcontracts in solicitations and contracts when
contemplating—
A cost-reimbursement contract
A letter contract that exceeds the simplified acquisition threshold
A fixed-price contract that exceeds the simplified acquisition
threshold under which unpriced contract actions (including
unpriced modifications or unpriced delivery orders) are
anticipated;
A time-and-materials contract that exceeds the simplified 

acquisition threshold

A labor-hour contract that exceeds the simplified acquisition
threshold.
4
Consent to Subcontract

FAR 52.244-2, Subcontracts
The Government reserves the right to review the
Contractor’s purchasing system as set forth in FAR

Subpart 44.3
If the Contractor does not have an approved
purchasing system, consent to subcontract is required
for certain subcontracts (cost reimbursement, time
and materials, etc.)
If the contractor has an approved purchasing system,
the contracting officer may still require consent for
certain subcontracts
5
Consent to Subcontract

FAR 52.244-2, Subcontracts
Requires the Contractor to notify the Contracting Officer
reasonably in advance of placing any subcontract or
modification thereof for which consent is required
including the following information:
A description of the supplies or services to be
subcontracted.
Identification of the type of subcontract to be used.
Identification of the proposed subcontractor.
the proposed subcontract price.
6
Consent to Subcontract

FAR 52.244-2
(f) Unless the consent or approval specifically provides 

otherwise, neither consent by the Contracting Officer to 

any subcontract nor approval of the Contractor’s
purchasing system shall constitute a determination -
(1) Of the acceptability of any subcontract terms or
conditions;
(2) Of the allowability of any cost under this contract; or
(3) To relieve the Contractor of any responsibility for
performing this contract.
7
Responsibilities

The prime contractor is responsible for managing
its subcontracts, per FAR 42.202(e)(2).
The prime contractor is primarily responsible for
subcontract award, technical and financial
performance, monitoring, and payment to the
subcontractor for the work accomplished under
subcontract terms.
8
Subcontractor Selection

If possible, the selection of a subcontractor
(including suppliers) should be on a competitive
basis.
FAR 52.244-5
Notify the Government upon award of the
subcontract and report subcontract costs as part
of the prime contractor's annual incurred cost
proposal.
9
Monitoring Subcontracts

The contractor’s internal control system over
subcontracts and intercompany orders should
provide for appropriate flow-down clauses into the
subcontract/intercompany that require:
 Government or contractor access to the subcontractor’s
books and records;
 Billings only include allowable costs; and
 The subcontractor/intercompany entity to submit annual
incurred cost proposal
10
Monitoring Subcontracts

• FAR 52.244-2 gives the Government the right to 

review a contractor’s purchasing system as set 

forth in FAR 44.3
•	 FAR 44.3 considers the following:
•	 Pricing policies and techniques
•	 Methods of evaluating subcontractor responsibility

•	 Planning, award, and postaward management of
major subcontract programs
11
Subcontracting Continued

 Know contract requirements regarding
subcontracting clauses.
 Do not assume that you can subcontract.
 If you are a subcontractor know what is required
of the prime.
12
Consent to Subcontract

 As a Government Contractor subcontracting out part of
the award may require consent from the contracting
officer.
 Designation of specific subcontractors during contract
negotiations does not in itself satisfy the requirements for
advance notification or consent pursuant to the clauses
at FAR 52.244-2
13
Consent to Subcontract

If you are considering subcontracting out part of
your Government contract notify the Contracting
Officer in advance, and know the responsibilities
of your contract.
14
Subcontract Information

Annual Incurred Cost Submission

FAR 52.216-7 (d)(2)(iii) Requires Contractor to complete
Schedule J as part of final indirect cost rate proposal
Schedule J Contains:
Listing of subcontracts awarded to companies for which the
contractor is the prime or upper-tier contractor
Prime and subcontract numbers
Subcontract value and award type
Amount claimed during the fiscal year
Subcontractor name, address, and point of contract information
15
Common Prime or Higher Tier 

Subcontract Deficiencies

 Failure to verify the subcontractor has an
adequate accounting system.
 Failure to appropriately monitor subcontract
effort.
 Failure to request a denial of access and notify
the ACO when the subcontractor refuses
access.
 Failure to notify the ACO, and obtain approval, to
subcontract.
16
Common Prime or Higher Tier 

Subcontract Deficiencies

 Failure to include the appropriate contract
clauses in the agreement with the subcontractor.
 Failure to ensure subcontract billings are
accurate and compliant with subcontract terms
 Failure to obtain an adequate incurred cost
submission from subcontractor.
17
Frequently Asked Questions

Can I assume that I can subcontract part of a 

Government contract?

NO. Review the prime contract and notify the ACO on
your intent to subcontract.
Am I responsible for the subcontractor’s pricing and
performance on a contract?
YES. The prime contractor (or higher tier
subcontractor) is responsible managing and
monitoring all aspects of the subcontract effort.
18

More Related Content

PDF
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
PDF
2017 Annual IFRS Update
PPTX
ptac -_you_won_a_contract...now_what
PPT
Lec 6.public procurement rules-2004
PPTX
Presentation on as 7 and 9
PPTX
Provision for warranties
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
PPT
Kenton Trace Technologies, LLC., VOB108 Briefing
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
2017 Annual IFRS Update
ptac -_you_won_a_contract...now_what
Lec 6.public procurement rules-2004
Presentation on as 7 and 9
Provision for warranties
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Kenton Trace Technologies, LLC., VOB108 Briefing

Viewers also liked (17)

PDF
Gadget Sketch
PDF
HMCTT A5 Leaflet FINAL v1.0
PDF
Barnbuds
PDF
Talous ja Yhteiskunta 4/2005
PDF
Working Prosses of PMCL Store Out-Surcing Project by KB
DOCX
EZILARASI . R
PPTX
EVALUACIÓN
PPTX
EVALUACIÓN
PDF
cal poly transcript
PPTX
Tap huan
PPTX
DCAA - Monitoring Subcontracts
PPTX
Сурган хүмүүжүүлэх ухаан-2
PPTX
Saúde do Idoso - Transtornos psiquicos
PPTX
Олон улсын валют, санхүү
PPTX
Транзисторт мултьвибратор хичээл
PPSX
Dog Photographer of the Year 2016 Winners
Gadget Sketch
HMCTT A5 Leaflet FINAL v1.0
Barnbuds
Talous ja Yhteiskunta 4/2005
Working Prosses of PMCL Store Out-Surcing Project by KB
EZILARASI . R
EVALUACIÓN
EVALUACIÓN
cal poly transcript
Tap huan
DCAA - Monitoring Subcontracts
Сурган хүмүүжүүлэх ухаан-2
Saúde do Idoso - Transtornos psiquicos
Олон улсын валют, санхүү
Транзисторт мултьвибратор хичээл
Dog Photographer of the Year 2016 Winners
Ad

Similar to Monitoring_Subcontracts (20)

PPT
Subcontract Clauses.PPTX
PDF
Advance 1020 1045
PDF
PDF
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
PDF
Extension of Time (EoT) in Construction Project presentation
PPTX
Presentation_Advisory & Intragroup service.pptx
PPTX
Procurement and Subcontractors
PDF
Engineering Contract for project managers..pdf
PPT
Contract financing
PPTX
Adb procurement guidelines icb-b3
DOCX
Document samples
PDF
Ak contract management
PPTX
A Case Study based on FIDIC and PAM Form 2006
PDF
UKA conference 2021 - 19 August 2021
PDF
Project procuremenet contract in ethiopia
PPTX
Liquidated damages contracts
PPTX
The Scoop on the Incurred Cost Submission
DOCX
Clause 14.docx
PPTX
Claims and insolvencies (1)
DOCX
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Subcontract Clauses.PPTX
Advance 1020 1045
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
Extension of Time (EoT) in Construction Project presentation
Presentation_Advisory & Intragroup service.pptx
Procurement and Subcontractors
Engineering Contract for project managers..pdf
Contract financing
Adb procurement guidelines icb-b3
Document samples
Ak contract management
A Case Study based on FIDIC and PAM Form 2006
UKA conference 2021 - 19 August 2021
Project procuremenet contract in ethiopia
Liquidated damages contracts
The Scoop on the Incurred Cost Submission
Clause 14.docx
Claims and insolvencies (1)
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Ad

More from Todd McAdams, CPA, CGMA, MAcc (9)

PDF
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
PDF
PDF
PDF
PDF
Provisional_Billing_Rates
PDF
Incurred_Cost_Submissions
PDF
Accounting_System_Requirements
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
Provisional_Billing_Rates
Incurred_Cost_Submissions
Accounting_System_Requirements

Monitoring_Subcontracts

  • 1. Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
  • 2. Subcontracts What should a contractor know about subcontracting:  Subcontract Selection;  Subcontracting Requirements, and  Your responsibilities as a prime contractor. See FAR 9-104.4 2
  • 3. Subcontract Information  The prime contractor (or higher-tier subcontractor) is responsible for managing its subcontracts.  Approval to subcontract out part of a Government contract is not automatic.  Higher-tier subcontractors must also manage their subcontracts, even if they are not the prime contractor on a Government contract. 3
  • 4. Consent to Subcontract FAR 44.204 (a) -- The contracting officer shall insert the clause at 52.244-2, Subcontracts in solicitations and contracts when contemplating— A cost-reimbursement contract A letter contract that exceeds the simplified acquisition threshold A fixed-price contract that exceeds the simplified acquisition threshold under which unpriced contract actions (including unpriced modifications or unpriced delivery orders) are anticipated; A time-and-materials contract that exceeds the simplified acquisition threshold A labor-hour contract that exceeds the simplified acquisition threshold. 4
  • 5. Consent to Subcontract FAR 52.244-2, Subcontracts The Government reserves the right to review the Contractor’s purchasing system as set forth in FAR Subpart 44.3 If the Contractor does not have an approved purchasing system, consent to subcontract is required for certain subcontracts (cost reimbursement, time and materials, etc.) If the contractor has an approved purchasing system, the contracting officer may still require consent for certain subcontracts 5
  • 6. Consent to Subcontract FAR 52.244-2, Subcontracts Requires the Contractor to notify the Contracting Officer reasonably in advance of placing any subcontract or modification thereof for which consent is required including the following information: A description of the supplies or services to be subcontracted. Identification of the type of subcontract to be used. Identification of the proposed subcontractor. the proposed subcontract price. 6
  • 7. Consent to Subcontract FAR 52.244-2 (f) Unless the consent or approval specifically provides otherwise, neither consent by the Contracting Officer to any subcontract nor approval of the Contractor’s purchasing system shall constitute a determination - (1) Of the acceptability of any subcontract terms or conditions; (2) Of the allowability of any cost under this contract; or (3) To relieve the Contractor of any responsibility for performing this contract. 7
  • 8. Responsibilities The prime contractor is responsible for managing its subcontracts, per FAR 42.202(e)(2). The prime contractor is primarily responsible for subcontract award, technical and financial performance, monitoring, and payment to the subcontractor for the work accomplished under subcontract terms. 8
  • 9. Subcontractor Selection If possible, the selection of a subcontractor (including suppliers) should be on a competitive basis. FAR 52.244-5 Notify the Government upon award of the subcontract and report subcontract costs as part of the prime contractor's annual incurred cost proposal. 9
  • 10. Monitoring Subcontracts The contractor’s internal control system over subcontracts and intercompany orders should provide for appropriate flow-down clauses into the subcontract/intercompany that require:  Government or contractor access to the subcontractor’s books and records;  Billings only include allowable costs; and  The subcontractor/intercompany entity to submit annual incurred cost proposal 10
  • 11. Monitoring Subcontracts • FAR 52.244-2 gives the Government the right to review a contractor’s purchasing system as set forth in FAR 44.3 • FAR 44.3 considers the following: • Pricing policies and techniques • Methods of evaluating subcontractor responsibility • Planning, award, and postaward management of major subcontract programs 11
  • 12. Subcontracting Continued  Know contract requirements regarding subcontracting clauses.  Do not assume that you can subcontract.  If you are a subcontractor know what is required of the prime. 12
  • 13. Consent to Subcontract  As a Government Contractor subcontracting out part of the award may require consent from the contracting officer.  Designation of specific subcontractors during contract negotiations does not in itself satisfy the requirements for advance notification or consent pursuant to the clauses at FAR 52.244-2 13
  • 14. Consent to Subcontract If you are considering subcontracting out part of your Government contract notify the Contracting Officer in advance, and know the responsibilities of your contract. 14
  • 15. Subcontract Information Annual Incurred Cost Submission FAR 52.216-7 (d)(2)(iii) Requires Contractor to complete Schedule J as part of final indirect cost rate proposal Schedule J Contains: Listing of subcontracts awarded to companies for which the contractor is the prime or upper-tier contractor Prime and subcontract numbers Subcontract value and award type Amount claimed during the fiscal year Subcontractor name, address, and point of contract information 15
  • 16. Common Prime or Higher Tier Subcontract Deficiencies  Failure to verify the subcontractor has an adequate accounting system.  Failure to appropriately monitor subcontract effort.  Failure to request a denial of access and notify the ACO when the subcontractor refuses access.  Failure to notify the ACO, and obtain approval, to subcontract. 16
  • 17. Common Prime or Higher Tier Subcontract Deficiencies  Failure to include the appropriate contract clauses in the agreement with the subcontractor.  Failure to ensure subcontract billings are accurate and compliant with subcontract terms  Failure to obtain an adequate incurred cost submission from subcontractor. 17
  • 18. Frequently Asked Questions Can I assume that I can subcontract part of a Government contract? NO. Review the prime contract and notify the ACO on your intent to subcontract. Am I responsible for the subcontractor’s pricing and performance on a contract? YES. The prime contractor (or higher tier subcontractor) is responsible managing and monitoring all aspects of the subcontract effort. 18