PRESENTED BY:
Rincy Joseph
Surbhi Gupta
Sugandha Vidge
Parana Vijay
Dulguun Turbat

(69)
(71)
(80)
(110)
Necessity of Materials Planning Material Planning is
necessary
• To avoid over ordering on under-ordering of materials.
• To reduce unwanted expenses due to last minute
ordering.
• To reduce capital locked up in excess.
• Independent Demand:
Demand for final products.
• Dependent Demand:

Demand fort items that are sub assemblies or
component parts to be used in production of finished
goods.
• It is a production planning process that starts from the
demand for finished products and plans the production
step by step of subassemblies and parts.
• Materials Requirements Planning (MRP) is a set of
techniques that takes the Master Production Schedule and
other information from inventory records and product
structure records as inputs to determine the requirements
and schedule of timing for each item.
• This inventory management system is appropriate for items that
have a dependent demand .
• MRP is applicable for industries that offer a variety of finished

products where the customer is allowed to choose among many
different options.
• MRP is most appropriate when the manufacturing environment
is complex and uncertain.
Control inventory levels

Assign operating priorities

Plan capacity to load the
production system
• Master Production Schedule (MPS)
• Bills of materials (BOM)
• Inventory status file
• Lead time
• Primary reports
1. Work orders
2. Purchase orders
3. Action notices or rescheduling notices
• Secondary reports
1. Exception reports

2. Planning reports
3. Performance Control reports
• Inventory transaction
• A listing of all of the raw materials, parts, subassemblies, and
assemblies needed to produce one unit of a product .
• BOM Shows way a finished product or parent item is put together
from individual components.
• Parent item shown at highest level or level zero , Parts that go into
parent item are called level 1 components and so on.
• Production planners explode BOM to determine the number, due
dates, and order dates of subcomponents.
• Based on actual customer orders and predicted demand.
• Indicates when each ordered item will be produced in coming
weeks, and in how much quantity.

• It is a plan specifying timing and quantity of production for
each end item.
• MPS inputs come from sales and marketing .
• MPS covers about 1-3 months into the future.
• Detailed information regarding the quantity of each item,
available in hand, on order to be released, for use in various
time periods.

• MRP system using inventory master file is used to determine the
quantity of material available for use in a given period.
• If sufficient items not available , the system includes the item on
the planned order release report .
• Also known as Inventory Master File
• Primary reports
1. Work orders / Planned orders - schedule indicating the
amount and timing of future orders.

2. Order Release - Authorization for the execution of planned
orders.
3. Action Notices or Rescheduling Notices - which orders are
to be released, revised and canceled during the current time
period.
• Secondary Reports
1. Performance control Reports – evaluate system operations . They
aid in measuring deviations from plans, and also provide information
to assess cost performance.
2. Planning Reports – are useful to forecast future inventory
requirements.
3. Exception Reports – these help to find the major discrepancies
such as late and overdue orders, excessive scrap rates, reporting
errors, etc.
• Exploding and Offsetting
• Gross and Net Requirements
• Releasing Orders
• Low level Coding and Netting
• Lead time – it is the time needed to perform the process . It
includes order preparation, queuing, processing moving receiving
and inspecting time as well as any expected delays.

• Exploding the requirements – it is the process of multiplying the
requirements by usage quantity of each item and recording the
appropriate requirements throughout the product tree.
• Offsetting – it is a process of placing the exploded requirements
in their proper periods based on lead time.
• Gross Requirement - Total expected demand of the product.
• Net Requirements - Actual amount needed in each time period.
Net Requirements = Gross Requirement – available inventory
• Planned on hand - Expected inventory on hand at the beginning of
each time period.
• Planned-order receipts - Quantity expected to received at the
beginning of the period
• Planned-order releases - Planned amount to order in each time
period
• Releasing an order – means authorization is given to buy the
necessary material or to manufacturing of required component.
• Scheduled Receipts – are orders placed on manufacturing or

on a vendor and represent a commitment to make or buy.
• Now, considering Scheduled Receipts,
Net Requirement = Gross Requirement – Scheduled Receipts –
available inventory
• Netting – is a process in which any stock on hand is subtracted from
the gross requirement determined through explosion, giving the
quantity of each item needed to manufacture the required finished
products.

• Low Level Code – is the lowest level on which a part resides in all
bills of material.
Low level codes are determined by starting at lowest level of bill of

material and working up, recording the level against the part. If part
exists on higher level, its existence on the lower level is already
recorded.
• Time buckets - The column in an inventory record that
represents a unit of time. It may be in days or weeks.

• Action bucket - The current time period.
• Action notices - Output from the MRP system identifying the
need for an action, to avoid future problem.
• Planning Horizon – is the total number of periods in a record.
• Keep inventory levels to a cost-effective minimum.
• Keeps track of inventory that is used.
• Tracks the amount of material that is required .

• Set safety stock levels for emergencies.
• Determine the best lot sizes to fulfill orders.
• Set up production times among the separate manufacturing
stages.
• Plan for future needs of raw
• Inaccurate information can result in mis-planning , overstock,
under-stock, or lack of appropriate resources.
• The inaccurate master schedule will provide wrong lengths of

time for production . Hence affecting planning.
• MRP systems can be costly and time-consuming to set up.
MRP I and MRP II
Manufacturing resource planning (MRPII) is defined as a method
for the effective planning of all resources of a manufacturing
company. Ideally, it addresses operational planning in units and

financial planning .
This is not exclusively a software function, but a combination of
people skills, dedication to data base accuracy, and computer
resources. It is a total company management concept for using
human resources which is used more productively.
MRP I and MRP II
• Business Planning
• Purchasing

• Distribution Requirement

Scheduling

• Forecasting

• Service Requirement Planning

• Inventory Control

• Capacity Requirement Planning

• Order Entry And

• Accounting

Management
• Shop Floor Control
• Faster Production Scheduling
• More efficient use of resources
Reduced inventories
Less idle time

Fewer bottlenecks
• Better priority planning
Quicker production starts
Schedule flexibility
• Improved customer service
Meet delivery dates

Improved quality
Lower price possibility
• Improved employee moral
• Better management information
• Error Due To Poor Information
• Use of averages
MRP I and MRP II

More Related Content

PPT
Material Resource Planning
PPT
Material Requirement Planning (MRP)
PPTX
Material requirement planning, MRP.
PPTX
Materials requirement planning
PPTX
PPT
Material requirement planning presentation
PPT
material requirement planning
PPT
Material requirement planning presentation
Material Resource Planning
Material Requirement Planning (MRP)
Material requirement planning, MRP.
Materials requirement planning
Material requirement planning presentation
material requirement planning
Material requirement planning presentation

What's hot (20)

PPTX
manufacturing resource planning
PPT
PPTX
AGGREGATE PRODUCTION PLANNING
PPTX
types of production system
PPTX
Objective of MRP and MRP II in computer study
PPSX
Aggregate planning
PPT
work measurement_operation management
PDF
What is master production schedule
PPTX
Facility layout
PPT
Master production schedule
PPTX
production planning and control
PPTX
Material requirement planning - Production and Operation Management
PPTX
Production planning & control & Forecasting
PPTX
Just in time manufacturing ppt
PPT
Production Planning and Control
PPTX
Capacity Requirement Planning, Rough Cut Capacity Planning
PPT
Capacity planning
PPT
Method study
PPT
production scheduling
manufacturing resource planning
AGGREGATE PRODUCTION PLANNING
types of production system
Objective of MRP and MRP II in computer study
Aggregate planning
work measurement_operation management
What is master production schedule
Facility layout
Master production schedule
production planning and control
Material requirement planning - Production and Operation Management
Production planning & control & Forecasting
Just in time manufacturing ppt
Production Planning and Control
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity planning
Method study
production scheduling
Ad

Viewers also liked (12)

PPT
Logistics Strategy
DOC
Facility location
PPTX
PPT
MRP II - Manufacturing Resource Planning ( Planejamento de Recursos de Produção)
PDF
58262864 09-administracao-financeira-do-estoque
PPTX
QUALITY & COST
PPTX
Aula de mrp
PDF
MRP1 vs MRP2
PPT
Aula mrp
PPTX
Logistics ppt
DOC
Plant layout
PPT
Ergonomics
Logistics Strategy
Facility location
MRP II - Manufacturing Resource Planning ( Planejamento de Recursos de Produção)
58262864 09-administracao-financeira-do-estoque
QUALITY & COST
Aula de mrp
MRP1 vs MRP2
Aula mrp
Logistics ppt
Plant layout
Ergonomics
Ad

Similar to MRP I and MRP II (20)

PPTX
Presentation2 mrp
PPT
Mrp1 prsntation-slides-1226827392037035-8
PPTX
Meterial Resource Planning 1
PPTX
Meterial Resource Planning 1
PPTX
Material requirement planning (mrp)
PDF
Module11. Material requirement plan..pdf
PDF
Mrp systems & scheduling
DOCX
Mrp 1
PPTX
Materials requirements planning
PPT
4. materials requirement planning
PPTX
PDF
MRP & ERP.pdf
PPTX
Production and operations management (POM)
PPTX
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
PPT
Operations Management Material Requirements Planning (MRP)
PPTX
MATERIAL REQUIREMENTS PLANNING (MRP)
DOC
147775601 erp-1
PPTX
Material Requirement Planning
PPT
Lect 6.ppt
DOCX
Material Requirements planning system 01Page to 04 Page
Presentation2 mrp
Mrp1 prsntation-slides-1226827392037035-8
Meterial Resource Planning 1
Meterial Resource Planning 1
Material requirement planning (mrp)
Module11. Material requirement plan..pdf
Mrp systems & scheduling
Mrp 1
Materials requirements planning
4. materials requirement planning
MRP & ERP.pdf
Production and operations management (POM)
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Operations Management Material Requirements Planning (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
147775601 erp-1
Material Requirement Planning
Lect 6.ppt
Material Requirements planning system 01Page to 04 Page

Recently uploaded (20)

DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
Deliverable file - Regulatory guideline analysis.pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
Training And Development of Employee .pdf
PDF
Laughter Yoga Basic Learning Workshop Manual
PDF
Business model innovation report 2022.pdf
PPTX
Lecture (1)-Introduction.pptx business communication
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
Types of control:Qualitative vs Quantitative
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPTX
Business Ethics - An introduction and its overview.pptx
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Deliverable file - Regulatory guideline analysis.pdf
HR Introduction Slide (1).pptx on hr intro
Training And Development of Employee .pdf
Laughter Yoga Basic Learning Workshop Manual
Business model innovation report 2022.pdf
Lecture (1)-Introduction.pptx business communication
Power and position in leadershipDOC-20250808-WA0011..pdf
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
Types of control:Qualitative vs Quantitative
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
340036916-American-Literature-Literary-Period-Overview.ppt
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Euro SEO Services 1st 3 General Updates.docx
Roadmap Map-digital Banking feature MB,IB,AB
Business Ethics - An introduction and its overview.pptx

MRP I and MRP II

  • 1. PRESENTED BY: Rincy Joseph Surbhi Gupta Sugandha Vidge Parana Vijay Dulguun Turbat (69) (71) (80) (110)
  • 2. Necessity of Materials Planning Material Planning is necessary • To avoid over ordering on under-ordering of materials. • To reduce unwanted expenses due to last minute ordering. • To reduce capital locked up in excess.
  • 3. • Independent Demand: Demand for final products. • Dependent Demand: Demand fort items that are sub assemblies or component parts to be used in production of finished goods.
  • 4. • It is a production planning process that starts from the demand for finished products and plans the production step by step of subassemblies and parts. • Materials Requirements Planning (MRP) is a set of techniques that takes the Master Production Schedule and other information from inventory records and product structure records as inputs to determine the requirements and schedule of timing for each item.
  • 5. • This inventory management system is appropriate for items that have a dependent demand . • MRP is applicable for industries that offer a variety of finished products where the customer is allowed to choose among many different options. • MRP is most appropriate when the manufacturing environment is complex and uncertain.
  • 6. Control inventory levels Assign operating priorities Plan capacity to load the production system
  • 7. • Master Production Schedule (MPS) • Bills of materials (BOM) • Inventory status file • Lead time
  • 8. • Primary reports 1. Work orders 2. Purchase orders 3. Action notices or rescheduling notices • Secondary reports 1. Exception reports 2. Planning reports 3. Performance Control reports • Inventory transaction
  • 9. • A listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product . • BOM Shows way a finished product or parent item is put together from individual components. • Parent item shown at highest level or level zero , Parts that go into parent item are called level 1 components and so on. • Production planners explode BOM to determine the number, due dates, and order dates of subcomponents.
  • 10. • Based on actual customer orders and predicted demand. • Indicates when each ordered item will be produced in coming weeks, and in how much quantity. • It is a plan specifying timing and quantity of production for each end item. • MPS inputs come from sales and marketing . • MPS covers about 1-3 months into the future.
  • 11. • Detailed information regarding the quantity of each item, available in hand, on order to be released, for use in various time periods. • MRP system using inventory master file is used to determine the quantity of material available for use in a given period. • If sufficient items not available , the system includes the item on the planned order release report . • Also known as Inventory Master File
  • 12. • Primary reports 1. Work orders / Planned orders - schedule indicating the amount and timing of future orders. 2. Order Release - Authorization for the execution of planned orders. 3. Action Notices or Rescheduling Notices - which orders are to be released, revised and canceled during the current time period.
  • 13. • Secondary Reports 1. Performance control Reports – evaluate system operations . They aid in measuring deviations from plans, and also provide information to assess cost performance. 2. Planning Reports – are useful to forecast future inventory requirements. 3. Exception Reports – these help to find the major discrepancies such as late and overdue orders, excessive scrap rates, reporting errors, etc.
  • 14. • Exploding and Offsetting • Gross and Net Requirements • Releasing Orders • Low level Coding and Netting
  • 15. • Lead time – it is the time needed to perform the process . It includes order preparation, queuing, processing moving receiving and inspecting time as well as any expected delays. • Exploding the requirements – it is the process of multiplying the requirements by usage quantity of each item and recording the appropriate requirements throughout the product tree. • Offsetting – it is a process of placing the exploded requirements in their proper periods based on lead time.
  • 16. • Gross Requirement - Total expected demand of the product. • Net Requirements - Actual amount needed in each time period. Net Requirements = Gross Requirement – available inventory • Planned on hand - Expected inventory on hand at the beginning of each time period. • Planned-order receipts - Quantity expected to received at the beginning of the period • Planned-order releases - Planned amount to order in each time period
  • 17. • Releasing an order – means authorization is given to buy the necessary material or to manufacturing of required component. • Scheduled Receipts – are orders placed on manufacturing or on a vendor and represent a commitment to make or buy. • Now, considering Scheduled Receipts, Net Requirement = Gross Requirement – Scheduled Receipts – available inventory
  • 18. • Netting – is a process in which any stock on hand is subtracted from the gross requirement determined through explosion, giving the quantity of each item needed to manufacture the required finished products. • Low Level Code – is the lowest level on which a part resides in all bills of material. Low level codes are determined by starting at lowest level of bill of material and working up, recording the level against the part. If part exists on higher level, its existence on the lower level is already recorded.
  • 19. • Time buckets - The column in an inventory record that represents a unit of time. It may be in days or weeks. • Action bucket - The current time period. • Action notices - Output from the MRP system identifying the need for an action, to avoid future problem. • Planning Horizon – is the total number of periods in a record.
  • 20. • Keep inventory levels to a cost-effective minimum. • Keeps track of inventory that is used. • Tracks the amount of material that is required . • Set safety stock levels for emergencies. • Determine the best lot sizes to fulfill orders. • Set up production times among the separate manufacturing stages. • Plan for future needs of raw
  • 21. • Inaccurate information can result in mis-planning , overstock, under-stock, or lack of appropriate resources. • The inaccurate master schedule will provide wrong lengths of time for production . Hence affecting planning. • MRP systems can be costly and time-consuming to set up.
  • 23. Manufacturing resource planning (MRPII) is defined as a method for the effective planning of all resources of a manufacturing company. Ideally, it addresses operational planning in units and financial planning . This is not exclusively a software function, but a combination of people skills, dedication to data base accuracy, and computer resources. It is a total company management concept for using human resources which is used more productively.
  • 25. • Business Planning • Purchasing • Distribution Requirement Scheduling • Forecasting • Service Requirement Planning • Inventory Control • Capacity Requirement Planning • Order Entry And • Accounting Management • Shop Floor Control • Faster Production Scheduling
  • 26. • More efficient use of resources Reduced inventories Less idle time Fewer bottlenecks • Better priority planning Quicker production starts Schedule flexibility
  • 27. • Improved customer service Meet delivery dates Improved quality Lower price possibility • Improved employee moral • Better management information
  • 28. • Error Due To Poor Information • Use of averages