BIM processes for the medium sized "Managing Architect" Practice!
Building Information Modelling Summit 2013 | 27 August 2013
Agenda
•  Fulton Trotter & BIM
•  Working with Tier 2 Contractors
•  What will the future hold?
Nathan Hildebrandt
Nathan Hildebrandt
•  Associate
•  Project Architect
•  Manage architectural team
•  11 years experience using
BIM software ‘ArchiCAD’
•  OpenBIM advocate
•  Graphisoft Development Panel
•  ArchiCAD Beta Tester
•  Member of BuildingSMART
•  BrisBIM Committee Member
Challenges with BIM
•  Significant shift in information creation
•  Implementation needs to be staged
•  Staff need to know how a building is built
•  BIM is still in its infancy
•  Standards are not in place
•  Leading to confusion from clients
Challenges with BIM
•  New Processes need to be developed
•  Costly if you head up dry gullies
Why Fulton Trotter embrace BIM
MacKillop Catholic College Library | Warnervale NSW | 2004
•  Why embark on BIM unless you benefit from it
•  FTA Clients don’t require BIM
•  FTA are embracing BIM as a process
•  Efficiencies – quicker production
•  Quality – less variations
•  More time for design
•  Future delivery process for all construction projects
Fulton Trotter’s BIM Journey
2003-2010
1993-2002
>1993
2011
2007–HinklerProject
2011<
Incorrect use of BIM Software
taken from Graphisoft ArchiCAD 8.1 Project Framework 2004
Case Studies
•  Hinkler Hall of Aviation – 3d Structural Steel Drawings
•  Wongaburra – Services Modelling
•  Tamborine Mountain College – Mobile Technology
•  Faith Lutheran College – Pilot full coordinated tender model
Hinkler Hall of Aviation
•  Completed in 2007
•  Complex Structural Steel Building
•  Simple Architectural Cladding Shell
Hinkler Hall of Aviation
3D Shop Drawings
•  3D Structural Steel Shop drawings produced in Tekla.
•  Quick and easy review process
•  Model reviewed outside of ArchiCAD
•  1800 shop drawings produced but not necessary to review in
as much detail.
Hinkler Hall of Aviation
3D Steel Shop Drawing Feedback
Hinkler Hall of Aviation
•  Real benefits in the process.
•  Benefits even greater today with Clash Detection Software.
Wongaburra
•  Upgrade of Existing Aged Care Facilities
•  Conversion of Undercroft Space into Administration Facilities
•  Service Consultants delivering typical 2D documentation
Wongaburra
•  2530 Floor to underside of slab
•  Habitable Space required to be obtained
•  Modelling the only answer
Wongaburra
Wongaburra
•  Modeling on its own wouldn’t have achieved the outcome.
•  Communication key to success of installation
Tamborine Mountain College
•  Secondary School Library and Teaching Spaces
•  500sqm
•  Consultants providing 2D information / documentation
Tamborine Mountain College
Communicating with a Virtual Model
•  Already used as a tool for
•  Design Reviews
•  Consultants
•  Client Sign Off on Design
•  Architect review on Site
•  Pilot project with Contractor.
•  Issued for trialling on Site.
Tamborine Mountain College
Tamborine Mountain College
•  Challenge getting Contractor
to use technology on site.
•  Provides a accompanying
piece of information to
drawings and specification.
•  Development of software will
transform the Construction
Industry.
Faith Lutheran College
•  Secondary Library
•  500sqm
Faith Lutheran College
•  Pilot Project for fully coordinated Consultant Team Model
•  Creation of workflows for multi-platform team
Workflow
Faith Lutheran College
Faith Lutheran College
•  Cost $10k timecost to test and develop workflows. Now in
place a good investment.
•  Delivered the project with -0.3% in Latent, Authority,
Documentation Variations. Client Variations 1.4%
•  Contractor didn’t embrace technology or 3D shop drawings
•  Had Contractor engaged in process would they benefit?
The Future – where are we heading
•  Everything is modelled
•  All notation automated, derived straight from the model
•  Specification & Schedules generated directly from the model
•  Model checking software will perform majority of QA tasks
•  Developing process of communication with our QS
•  Developing processes with our builders so they benefit
Working with Tier 2 Contractors
•  Uptake of BIM in Tier 2 is very limited
•  Working with regular Contractors to show benefits of
adapting to technology
•  Challenge is without standard deliverables from Clients
process development now could be a significant dry gully
•  Sub Contractors are smaller and investment to great?
How will the industry adapt
•  Question roles of Professional Consultants in the future!
•  Where will everyone fit it?
•  How do you adapt your business and remain relevant?
Road to Standard Deliverables
•  BuildingSMART are working along with a number of other
NFP organisations to create Guidelines.
•  Boost the uptake, clearer ideas of deliverables.
•  Clients can ask for an reasonable outcome and Project Team
will know what is needed to achieve it.
Thank You
Nathan Hildebrandt nathanh@fultontrotter.com.au +61 7 3291 1511
Tamborine Mountain College – Library

More Related Content

PDF
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
PDF
5th Qatar BIM User Day, Live modeling techniques on a single project
PPTX
BIM Bringing A Real Change in Construction
PPTX
BIM Implementation in a Lean Operating System
PPTX
BIM - Building Information Modelling
PDF
Optimize bim for reducing errors
PDF
5th Qatar BIM User Day, BIM Introduction
PDF
NW BIM 2018 1 TWF
3rd Qatar BIM User Day - The BIM Manager within the Project Organisation
5th Qatar BIM User Day, Live modeling techniques on a single project
BIM Bringing A Real Change in Construction
BIM Implementation in a Lean Operating System
BIM - Building Information Modelling
Optimize bim for reducing errors
5th Qatar BIM User Day, BIM Introduction
NW BIM 2018 1 TWF

What's hot (20)

PDF
NW BIM 2018 2 MGF
PDF
Bim and project controls
PPTX
Quality BIM Services : BIM Junction
PDF
Bim implementation
PDF
Plannerly and Dalux for construction system engineering
PPTX
BIM - Gaining Competitive Advantage
PDF
NW BIM 2018 6 Costain Smith
PDF
AU 2015: Enterprise, Beam Me Up: Inphi's Enterprise PLM Solution (PPT)
PDF
iBIM value to Data Center from design to operate
PDF
Leveraging BIM throughout the construction process
PDF
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
PDF
BIM SHOW LIVE 14 - Lego to Minecraft: from 3D CAD to BIM
PPTX
Bim4T: Building Information Modelling for Tender in the construction industry.
PPTX
Why Manufacturers Need BIM - #BIM4M2help
PDF
A New Development Platform Connecting BIM to Anything - Mr. Xiaodong LIANG Ch...
PPTX
Connecting SolidWorks EPDM and ENOVIA V6
PDF
081204 Virtual Design & Construction
PPTX
BIM For Free_28May2013_CaseyRutland_BIM for beginners
NW BIM 2018 2 MGF
Bim and project controls
Quality BIM Services : BIM Junction
Bim implementation
Plannerly and Dalux for construction system engineering
BIM - Gaining Competitive Advantage
NW BIM 2018 6 Costain Smith
AU 2015: Enterprise, Beam Me Up: Inphi's Enterprise PLM Solution (PPT)
iBIM value to Data Center from design to operate
Leveraging BIM throughout the construction process
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
BIM SHOW LIVE 14 - Lego to Minecraft: from 3D CAD to BIM
Bim4T: Building Information Modelling for Tender in the construction industry.
Why Manufacturers Need BIM - #BIM4M2help
A New Development Platform Connecting BIM to Anything - Mr. Xiaodong LIANG Ch...
Connecting SolidWorks EPDM and ENOVIA V6
081204 Virtual Design & Construction
BIM For Free_28May2013_CaseyRutland_BIM for beginners
Ad

Viewers also liked (7)

PDF
BIM for FM - What FM should know about BIM
PDF
BIM and Professional Indemnity Insurance
PDF
ArchiMAG_BIM_evolution_by_Victor_Silva
PDF
BIM from Designers Perspective - Rob Jackson
PDF
KED BIM Capabilities
PPT
BIM from an FM perspective
PPTX
BIM, Big Data and Mashup in Architectural Computing – Experimenting with Digi...
BIM for FM - What FM should know about BIM
BIM and Professional Indemnity Insurance
ArchiMAG_BIM_evolution_by_Victor_Silva
BIM from Designers Perspective - Rob Jackson
KED BIM Capabilities
BIM from an FM perspective
BIM, Big Data and Mashup in Architectural Computing – Experimenting with Digi...
Ad

Similar to Nathan Hildebrandt (20)

PPT
Corporate member event September 2015, BIM and Soft Landings
PPTX
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
PDF
CAD and BIM Outsourcing Services
PDF
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
PDF
Spar2010murphy
PPTX
Trusted BIM: Accurate As-Builts for Project Coordination
PDF
GTB-brochure.pdf
PDF
atb-brochure.pdf
PPTX
Innovation in practice presentation 10 06-15
PPTX
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
PDF
Delivering operational efficiency in the new dawn of complex BIM data through...
PPTX
MelBIM 190619
PDF
Barriers to bim implementation in gcc
PPTX
How Brick & Bolt Uses Technology to Avoid Project Delays.pptx
PPTX
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
PPTX
Building Information Modeling Workflows with AutoCAD Civil 3D
PPTX
What is bim, building information modeling
PPTX
It's a question of Design: Carl Gaunt #SPRAConference2017
PDF
BIM process adoption for integrated design and constuction
PPTX
BIM comp
Corporate member event September 2015, BIM and Soft Landings
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
CAD and BIM Outsourcing Services
Building Information Modelling (BIM) Lessons at University of Hull's Student ...
Spar2010murphy
Trusted BIM: Accurate As-Builts for Project Coordination
GTB-brochure.pdf
atb-brochure.pdf
Innovation in practice presentation 10 06-15
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
Delivering operational efficiency in the new dawn of complex BIM data through...
MelBIM 190619
Barriers to bim implementation in gcc
How Brick & Bolt Uses Technology to Avoid Project Delays.pptx
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
Building Information Modeling Workflows with AutoCAD Civil 3D
What is bim, building information modeling
It's a question of Design: Carl Gaunt #SPRAConference2017
BIM process adoption for integrated design and constuction
BIM comp

More from Informa Australia (13)

PDF
Conference Agenda
PDF
Xiangyu Wang
PDF
Phil Davies and Tim Surgenor
PDF
Richard Archer
PDF
Aleks Baltovski
PDF
Paul Nunn v2
PDF
David Mitchell
PDF
David Mitchell 5D bim today’s workflow for cost certainty
PDF
Andrew Gutteridge
PDF
Ricci Piper
PDF
Rafik Abdelkaddous
PDF
Chris Kane
PDF
Conference Agenda
Xiangyu Wang
Phil Davies and Tim Surgenor
Richard Archer
Aleks Baltovski
Paul Nunn v2
David Mitchell
David Mitchell 5D bim today’s workflow for cost certainty
Andrew Gutteridge
Ricci Piper
Rafik Abdelkaddous
Chris Kane

Recently uploaded (20)

PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Approach and Philosophy of On baking technology
PPTX
A Presentation on Touch Screen Technology
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PDF
Enhancing emotion recognition model for a student engagement use case through...
PDF
A novel scalable deep ensemble learning framework for big data classification...
PDF
A comparative study of natural language inference in Swahili using monolingua...
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PDF
Hybrid model detection and classification of lung cancer
PPTX
OMC Textile Division Presentation 2021.pptx
PDF
Getting Started with Data Integration: FME Form 101
PDF
WOOl fibre morphology and structure.pdf for textiles
PDF
A comparative analysis of optical character recognition models for extracting...
PPTX
Chapter 5: Probability Theory and Statistics
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Approach and Philosophy of On baking technology
A Presentation on Touch Screen Technology
gpt5_lecture_notes_comprehensive_20250812015547.pdf
MIND Revenue Release Quarter 2 2025 Press Release
Enhancing emotion recognition model for a student engagement use case through...
A novel scalable deep ensemble learning framework for big data classification...
A comparative study of natural language inference in Swahili using monolingua...
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
Hybrid model detection and classification of lung cancer
OMC Textile Division Presentation 2021.pptx
Getting Started with Data Integration: FME Form 101
WOOl fibre morphology and structure.pdf for textiles
A comparative analysis of optical character recognition models for extracting...
Chapter 5: Probability Theory and Statistics
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
Univ-Connecticut-ChatGPT-Presentaion.pdf
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf

Nathan Hildebrandt

  • 1. BIM processes for the medium sized "Managing Architect" Practice! Building Information Modelling Summit 2013 | 27 August 2013
  • 2. Agenda •  Fulton Trotter & BIM •  Working with Tier 2 Contractors •  What will the future hold?
  • 4. Nathan Hildebrandt •  Associate •  Project Architect •  Manage architectural team •  11 years experience using BIM software ‘ArchiCAD’ •  OpenBIM advocate •  Graphisoft Development Panel •  ArchiCAD Beta Tester •  Member of BuildingSMART •  BrisBIM Committee Member
  • 5. Challenges with BIM •  Significant shift in information creation •  Implementation needs to be staged •  Staff need to know how a building is built •  BIM is still in its infancy •  Standards are not in place •  Leading to confusion from clients
  • 6. Challenges with BIM •  New Processes need to be developed •  Costly if you head up dry gullies
  • 7. Why Fulton Trotter embrace BIM MacKillop Catholic College Library | Warnervale NSW | 2004 •  Why embark on BIM unless you benefit from it •  FTA Clients don’t require BIM •  FTA are embracing BIM as a process •  Efficiencies – quicker production •  Quality – less variations •  More time for design •  Future delivery process for all construction projects
  • 8. Fulton Trotter’s BIM Journey 2003-2010 1993-2002 >1993 2011 2007–HinklerProject 2011<
  • 9. Incorrect use of BIM Software taken from Graphisoft ArchiCAD 8.1 Project Framework 2004
  • 10. Case Studies •  Hinkler Hall of Aviation – 3d Structural Steel Drawings •  Wongaburra – Services Modelling •  Tamborine Mountain College – Mobile Technology •  Faith Lutheran College – Pilot full coordinated tender model
  • 11. Hinkler Hall of Aviation •  Completed in 2007 •  Complex Structural Steel Building •  Simple Architectural Cladding Shell
  • 12. Hinkler Hall of Aviation 3D Shop Drawings •  3D Structural Steel Shop drawings produced in Tekla. •  Quick and easy review process •  Model reviewed outside of ArchiCAD •  1800 shop drawings produced but not necessary to review in as much detail.
  • 13. Hinkler Hall of Aviation 3D Steel Shop Drawing Feedback
  • 14. Hinkler Hall of Aviation •  Real benefits in the process. •  Benefits even greater today with Clash Detection Software.
  • 15. Wongaburra •  Upgrade of Existing Aged Care Facilities •  Conversion of Undercroft Space into Administration Facilities •  Service Consultants delivering typical 2D documentation
  • 16. Wongaburra •  2530 Floor to underside of slab •  Habitable Space required to be obtained •  Modelling the only answer
  • 18. Wongaburra •  Modeling on its own wouldn’t have achieved the outcome. •  Communication key to success of installation
  • 19. Tamborine Mountain College •  Secondary School Library and Teaching Spaces •  500sqm •  Consultants providing 2D information / documentation
  • 20. Tamborine Mountain College Communicating with a Virtual Model •  Already used as a tool for •  Design Reviews •  Consultants •  Client Sign Off on Design •  Architect review on Site •  Pilot project with Contractor. •  Issued for trialling on Site.
  • 22. Tamborine Mountain College •  Challenge getting Contractor to use technology on site. •  Provides a accompanying piece of information to drawings and specification. •  Development of software will transform the Construction Industry.
  • 23. Faith Lutheran College •  Secondary Library •  500sqm
  • 24. Faith Lutheran College •  Pilot Project for fully coordinated Consultant Team Model •  Creation of workflows for multi-platform team Workflow
  • 26. Faith Lutheran College •  Cost $10k timecost to test and develop workflows. Now in place a good investment. •  Delivered the project with -0.3% in Latent, Authority, Documentation Variations. Client Variations 1.4% •  Contractor didn’t embrace technology or 3D shop drawings •  Had Contractor engaged in process would they benefit?
  • 27. The Future – where are we heading •  Everything is modelled •  All notation automated, derived straight from the model •  Specification & Schedules generated directly from the model •  Model checking software will perform majority of QA tasks •  Developing process of communication with our QS •  Developing processes with our builders so they benefit
  • 28. Working with Tier 2 Contractors •  Uptake of BIM in Tier 2 is very limited •  Working with regular Contractors to show benefits of adapting to technology •  Challenge is without standard deliverables from Clients process development now could be a significant dry gully •  Sub Contractors are smaller and investment to great?
  • 29. How will the industry adapt •  Question roles of Professional Consultants in the future! •  Where will everyone fit it? •  How do you adapt your business and remain relevant?
  • 30. Road to Standard Deliverables •  BuildingSMART are working along with a number of other NFP organisations to create Guidelines. •  Boost the uptake, clearer ideas of deliverables. •  Clients can ask for an reasonable outcome and Project Team will know what is needed to achieve it.
  • 31. Thank You Nathan Hildebrandt nathanh@fultontrotter.com.au +61 7 3291 1511 Tamborine Mountain College – Library