Netting Example in D01 client 110 October 10 th  2006 Prepared by Ludmila Monin
Introduction BOM and Route Netting is a custom transaction developed as part of SAP 4.7 implementation at Electro-Motive Diesel (EMD). Netting is an automation of multiple procedural steps performed consistently to achieve the goal – generate a custom Bill of Materials and production routings in order to build and cost a unique locomotive designed for a specific sales order. ZNET is the netting transaction. It supports user interface, performs netting functions, maintains custom materials, BOMs and routings.
Business Process Create an inquiry, followed by a sales order. Use Variant Configurator to select required assemblies. Generate an Order BOM based on the selected options. Maintain basic BOMs and routings. This includes PLI and EDL assemblies and routings. Execute ZNET transaction to net planned BOMs – one station at a time. Verify netted planned BOMs. Execute ZNET transaction to generate final netted BOMs. Execute ZNET transaction to generate production routings based on final netted BOMs.
Sales order S068880 for locomotive model 92140
Order BOM configured and generated for: order S068880 line item 10 in delivering plant 1001 (usage 3).
ZNET transaction initial entry screen.
Typical locomotive netting screen. Majority of stations on this order have already been final netted and routed. Station 24 has been netted in memory: i.e. no new materials saved, no BOMs saved.
BOM netting process log, every netting step is logged.
Netting detailed trace helps in determining any issues in case of error result.
Material Master maintenance log for Station 24.
Illustrates the ability to create and re-create Planned BOMs.
When Production BOMs (Final) are created – the Planned BOMs (if any) are deleted.
Routing netting process log, every netting step is logged. There are two indicators in the left portion of the screen: (N) Netting and (C) Creating. In this example, routing was netted in memory only.
Illustrates error handling while attempting to create netting routing.
PLI and EDL list from the Order BOM for Station 1.
PLI and EDL detail BOMs for Station 1.
Netted BOM detail for Station 1.
ZCA51 transaction executed for Station 1 production routing.

More Related Content

PDF
Advanced Java Programming
PDF
Visteon_FMF
PDF
Adding a BOLT pass
PDF
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PDF
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
PDF
Vlsi course syllabus verilog language
PDF
Ato cycle
PDF
Oracle Database InMemory
Advanced Java Programming
Visteon_FMF
Adding a BOLT pass
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
Vlsi course syllabus verilog language
Ato cycle
Oracle Database InMemory

Similar to Netting Demo 10-2006 (20)

PDF
Cim lab manual (10 mel77) by mohammed imran
PDF
Roland: 3-axis Set-Up Positional & Flip Milling
PPTX
Hexagonal Architecture: The Standard for Qt Embedded Applications
PPTX
File0 ala conchesumareeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee01.pptx
PPT
CS4961-L9.ppt
PDF
RISC-V 30908 patra
PDF
DOC
Klausing, Patrick Resume Consultant2
PDF
Tutorial_Caf_2020_etool.pdf
PDF
RhinoCAM_RotaryPrimer_SoftMaterials
PPTX
IBM MQ Whats new - up to 9.3.4.pptx
PPT
Lo #5 manufacturing technology (jan 2016)
PPTX
PLC BASED AUTOMATED SYSTEM IN PROCESS INDUSTRY (Final Presentation)
PDF
Ims05 ims 100 k benchmark
PDF
Mes pfs pmc en
PPT
Ae08 system vb_script
PPT
Optimization_model_of the propsed kiiraEV assembly lineprstn
PDF
RM Seminar_CNC_final.pdf.........................
PDF
5035-Pipeline-Optimization-Techniques.pdf
PPT
PLC Training Intro
Cim lab manual (10 mel77) by mohammed imran
Roland: 3-axis Set-Up Positional & Flip Milling
Hexagonal Architecture: The Standard for Qt Embedded Applications
File0 ala conchesumareeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee01.pptx
CS4961-L9.ppt
RISC-V 30908 patra
Klausing, Patrick Resume Consultant2
Tutorial_Caf_2020_etool.pdf
RhinoCAM_RotaryPrimer_SoftMaterials
IBM MQ Whats new - up to 9.3.4.pptx
Lo #5 manufacturing technology (jan 2016)
PLC BASED AUTOMATED SYSTEM IN PROCESS INDUSTRY (Final Presentation)
Ims05 ims 100 k benchmark
Mes pfs pmc en
Ae08 system vb_script
Optimization_model_of the propsed kiiraEV assembly lineprstn
RM Seminar_CNC_final.pdf.........................
5035-Pipeline-Optimization-Techniques.pdf
PLC Training Intro
Ad

Recently uploaded (20)

PPTX
FINAL PPT.pptx cfyufuyfuyuy8ioyoiuvy ituyc utdfm v
PPTX
CYBER SECURITY PPT.pptx CYBER SECURITY APPLICATION AND USAGE
PPTX
Overview Planner of Soft Skills in a single ppt
PPTX
Nervous_System_Drugs_PPT.pptxXXXXXXXXXXXXXXXXX
PPTX
A slide for students with the advantagea
PDF
シュアーイノベーション採用ピッチ資料|Company Introduction & Recruiting Deck
PPTX
Surgical thesis protocol formation ppt.pptx
PPTX
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
PDF
313302 DBMS UNIT 1 PPT for diploma Computer Eng Unit 2
PPTX
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
PPTX
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
PDF
Entrepreneurship PowerPoint for students
PDF
Biography of Mohammad Anamul Haque Nayan
PPTX
Job-opportunities lecture about it skills
PPTX
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
PPTX
Prokaryotes v Eukaryotes PowerPoint.pptx
PDF
Blue-Modern-Elegant-Presentation (1).pdf
PDF
MCQ Practice CBT OL Official Language 1.pptx.pdf
PDF
servsafecomprehensive-ppt-full-140617222538-phpapp01.pdf
PPTX
DPT-MAY24.pptx for review and ucploading
FINAL PPT.pptx cfyufuyfuyuy8ioyoiuvy ituyc utdfm v
CYBER SECURITY PPT.pptx CYBER SECURITY APPLICATION AND USAGE
Overview Planner of Soft Skills in a single ppt
Nervous_System_Drugs_PPT.pptxXXXXXXXXXXXXXXXXX
A slide for students with the advantagea
シュアーイノベーション採用ピッチ資料|Company Introduction & Recruiting Deck
Surgical thesis protocol formation ppt.pptx
OnePlus 13R – ⚡ All-Rounder King Performance: Snapdragon 8 Gen 3 – same as iQ...
313302 DBMS UNIT 1 PPT for diploma Computer Eng Unit 2
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
cse couse aefrfrqewrbqwrgbqgvq2w3vqbvq23rbgw3rnw345
Entrepreneurship PowerPoint for students
Biography of Mohammad Anamul Haque Nayan
Job-opportunities lecture about it skills
ESD MODULE-5hdbdhbdbdbdbbdbdbbdndbdbdbdbbdbd
Prokaryotes v Eukaryotes PowerPoint.pptx
Blue-Modern-Elegant-Presentation (1).pdf
MCQ Practice CBT OL Official Language 1.pptx.pdf
servsafecomprehensive-ppt-full-140617222538-phpapp01.pdf
DPT-MAY24.pptx for review and ucploading
Ad

Netting Demo 10-2006

  • 1. Netting Example in D01 client 110 October 10 th 2006 Prepared by Ludmila Monin
  • 2. Introduction BOM and Route Netting is a custom transaction developed as part of SAP 4.7 implementation at Electro-Motive Diesel (EMD). Netting is an automation of multiple procedural steps performed consistently to achieve the goal – generate a custom Bill of Materials and production routings in order to build and cost a unique locomotive designed for a specific sales order. ZNET is the netting transaction. It supports user interface, performs netting functions, maintains custom materials, BOMs and routings.
  • 3. Business Process Create an inquiry, followed by a sales order. Use Variant Configurator to select required assemblies. Generate an Order BOM based on the selected options. Maintain basic BOMs and routings. This includes PLI and EDL assemblies and routings. Execute ZNET transaction to net planned BOMs – one station at a time. Verify netted planned BOMs. Execute ZNET transaction to generate final netted BOMs. Execute ZNET transaction to generate production routings based on final netted BOMs.
  • 4. Sales order S068880 for locomotive model 92140
  • 5. Order BOM configured and generated for: order S068880 line item 10 in delivering plant 1001 (usage 3).
  • 6. ZNET transaction initial entry screen.
  • 7. Typical locomotive netting screen. Majority of stations on this order have already been final netted and routed. Station 24 has been netted in memory: i.e. no new materials saved, no BOMs saved.
  • 8. BOM netting process log, every netting step is logged.
  • 9. Netting detailed trace helps in determining any issues in case of error result.
  • 10. Material Master maintenance log for Station 24.
  • 11. Illustrates the ability to create and re-create Planned BOMs.
  • 12. When Production BOMs (Final) are created – the Planned BOMs (if any) are deleted.
  • 13. Routing netting process log, every netting step is logged. There are two indicators in the left portion of the screen: (N) Netting and (C) Creating. In this example, routing was netted in memory only.
  • 14. Illustrates error handling while attempting to create netting routing.
  • 15. PLI and EDL list from the Order BOM for Station 1.
  • 16. PLI and EDL detail BOMs for Station 1.
  • 17. Netted BOM detail for Station 1.
  • 18. ZCA51 transaction executed for Station 1 production routing.