SlideShare a Scribd company logo
Copyright © 2015 ScottMadden, Inc. All rights reserved. Report _2015
Overcoming the Challenges of Large Capital
Programs/Projects
Applying Lessons Learned from Extended Power Uprates
June 2015
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Introduction
■ Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance
■ However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception
■ Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations
to ensure compliance with a number of concerns, including:
• Plant retrofits and conversions
• Ash pond closures
• Fukushima modifications
• Security upgrade requirements
• Extended power uprates (EPUs)
■ Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management
challenges
■ Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project
1
Lessons learned from extended power uprates can be applied to any large capital program/project.
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Overview of Power Uprates
■ Power uprates allow utilities to generate more electricity from their existing nuclear plants
■ Since the 1970s, the NRC has approved 154 uprates, which have collectively added generating capacity equivalent to about seven new
reactors
■ Three types of uprates are available to a nuclear plant operator: measurement uncertainty recapture, stretch, and extended
■ As shown in the table above, implementing EPUs presents the biggest project challenges, given the need to significantly modify major
pieces of plant equipment
2
Power Uprate Type
Increase to Licensed
Power Levels
Plant and System Impacts
Measurement uncertainty recapture < 2%
Implementing improved techniques for calculating reactor
power, e.g., utilizing state-of-the-art devices to more precisely
measure feedwater flow
Stretch 2 to 7%
Changing instrumentation settings without major plant
modifications
Extended 7 to 20%
Significantly modifying to major pieces of non-nuclear
equipment, e.g., high-pressure turbines, condensate pumps
and motors, main generators, and transformers
Source: www.nrc.gov, Backgrounder on Power Uprates for Nuclear Plants
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
EPU Project Challenges
EPU projects pose significant scope, implementation, and workforce management challenges
■ Scope
• Scope is fluid as the EPU project is implemented
• Outages are typically much bigger in scope than a refueling outage, requiring the significant change-outs or upgrades of major
equipment
• Changes to the plant configuration (structures, equipment, and systems) must be precisely documented
■ Implementation
• In many cases, the work is done while other units are still in operation
• A high degree of project control rigor is required to accurately track cost and schedule against evolving scope
• Physical security, ALARA limits, lock-out/tag-out requirements, etc., make the work environment very complex
■ Workforce management
• A large number of skilled teams (craft workers and supervisors) that may have never worked together are involved
• Some trades and/or skills are likely to be in short supply
• Many workers are new to a nuclear plant work environment and lack knowledge of nuclear safety and quality standards
3
Sources:
1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011
2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects”, Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Lessons Learned from Recent EPU Efforts
■ Planning for contingences is critical. In some cases:
• Actual costs more than doubled over initially planned costs
• Outage durations were as much as 25% longer than planned
• Additional outages were required to complete the work
■ Costs and schedules should include contingencies for productivity issues, replacing vs. repairing components, and licensing delays
• Preliminary cost estimates, based on conceptual scope, may not capture all of the work necessary to complete the project
• Some components that are initially expected to be repaired or recertified will require replacement, i.e., during configuration control
verification, perform a detailed drawing walk-down of pumps, motors, valve controls, etc., to minimize scope surprises
• Major construction activities at an operating nuclear plant, many of which occur in remote and radiologic-controlled portions of the
plant, can cause significant implementation difficulties and delays
– Space for installation can be extremely tight and may require removal or working around hundreds of interferences
– Productivity can be slowed due to the specialized and time-consuming procedures to ensure worker safety in radiologic-
controlled and electrically sensitive areas of the plant
• Increasingly conservative regulatory requirements outside of a company’s control can cause significant licensing delays
■ Obtaining and retaining experienced workers is a challenge
■ Active management of vendors is required to ensure productivity is maintained, issues are raised, and progress is on schedule
4
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
EPU Project Keys to Success
5
■ Encourage workforce collaboration and the ability of employees to voice concerns early and often to
avoid costly errors, re-work, and safety hazards, i.e., maintain a focus on quality and safety
■ Develop a self-critical culture focused on improvement and efficiency
■ Recognize that the EPU team can not anticipate all the changes that will occur during the project
■ Utilize project management technology where possible to improve efficiency and communication
■ Hold regular project team meetings and invite senior leadership periodically to reinforce the priority of
the project
Work Environment
Planning
■ Be honest and realistic about the complexity and uniqueness of the EPU project; investing early in
planning and current state analysis can save a lot of rework
■ Recognize that the planning process continues all the way to project completion and that the EPU team
should always be looking to improve costs, schedule, and general efficiency
■ Make benchmarking trips and incorporate lessons learned and insights, e.g., NEDO-33159, from recent
EPU and stretch uprates projects into planning
■ Bring in field engineers and/or craft supervisors early in the process for review and comment on actual
configuration vs. drawings and equipment installation implications
■ Hold combined design reviews with members from different disciplines; utilize the experience and
expertise from each discipline to come up with a collectively better solution
■ Develop integrated work packages to improve efficiency and overall performance
Sources:
1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011
2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects,” Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
EPU Project Keys to Success (Cont’d)
6
Vendor/ Contractor
Alignment
■ Align vendors and contractors with project objectives and the uniqueness of the project
■ Ensure vendors and contractors are aware of and held to the tenets of nuclear safety and align their
nuclear safety culture with that of your company
■ Work collaboratively with contractors and combine cost, schedule, and human performance monitoring
tools and processes
■ Ensure contracts have clear terms and conditions and are very specific in scope and timing
■ Plan for vendor handoffs of work products and resolve disputes promptly to reduce idle vendor time
Implementation
■ Manage like a large-scale engineering, procurement, and construction project and not like a
modifications project or refueling outage, e.g., funding is stage-gated
■ Collect accurate data and monitor relevant performance metrics throughout the EPU project
■ Conduct periodic independent project audits using industry experts with previous EPU experience
■ Involve employees who will operate the plant during implementation
■ Ensure operating staff are adequately trained on how the plant will operate after the power uprate, e.g.,
operations, maintenance, engineering, radiation protection personnel, etc.
■ Update all affected documentation, e.g., operating and maintenance procedures, to reflect the new
operating conditions
■ Focus on procedure development, training, and simulator modeling to help verify actual plant response
vs. expected plant response in power uprated conditions
Sources:
1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011
2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects,” Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
How ScottMadden Can Help
7
ScottMadden
Capital
Program/Project
Assistance
Perform a top-to-bottom
assessment of the capital
program to position it for
success from the start
Capital Program
Assessment
Capital
Program/Project
Management
Capital
Program/Project Tools
and Performance
Reporting
Assist in establishing and
implementing the organization
and governance to successfully
deliver the program/project
Assist in establishing and
implementing the tools and
performance reporting to
successfully control and monitor
the program/project
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Capital Program Assessment Overview
ScottMadden’s Capital Program Assessment examines how the capital program is implemented—from top to bottom—with a look
at the PMO and a review of the performance reporting and tools in place.
8
Program Management Office
Step 1: Capital Program Analysis Step 2: Process Evaluation
Copyright © 2013 by ScottMadden. All rights reserved.
5
Constructability activities within alliance projects are being introduced later in the cradle to grave construction process
than is typical for large project management
Findings
Constructability – Cost Savings Driver
Current lack of a constructability process across all the elements of the construction cradle to grave process is a
significant driver in NEA cost estimates being high
Best In Class Projects Typical NEA Project
ScottMadden’s approach analyzes these critical areas to provide a detailed assessment
of your capital program with actionable recommendations.
Step 6: Recommendations and Action Plan
EPU Project
Step 4: Execution AssessmentStep 3: Organization Analysis
Step 5:
Performance Reporting and Tools Evaluation
ScottMadden
Capital
Program/Project
Assistance
Capital Program
Assessment
Capital
Program/Project
Management
Capital
Program/Project Tools
and Performance
Reporting
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Capital Program/Project Management Overview
9
Focus On
◼ Organization and governance
◼ Functional relationship
management
◼ Partnership with other entities
Tools
◼ Performance Dashboard
◼ Issue List (high impact and level)
◼ Monthly Progress Report
◼ Risk Analysis and Mitigation Plan (high impact and
level)
◼ Inter-project coordination
◼ Inter-project resource
coordination
◼ Cross functionalities
◼ Best practice usage
◼ Documentation
management
◼ Project milestones
◼ Costs
◼ Times
◼ Business/technical goals
◼ Projects List
◼ Project Procedures
◼ Project Dashboard
◼ Milestones Tracking
◼ Issue List (Aggregated)
◼ Risk Analysis and Mitigation Plan (Aggregated)
◼ Weekly and Monthly Progress Reports
◼ Project Plan
◼ Project Documentation Management
◼ Milestones Tracking
◼ Risk Analysis and Mitigation Plan
◼ Change Request Management
◼ Issue List Management
◼ Project Baseline and Progress Report
◼ Weekly Progress Meeting Minutes
◼ Weekly Progress Report
◼ Monthly Progress Report
Program
Manager
Project Office
Project Managers
ScottMadden
Capital
Program/Project
Assistance
Capital Program
Assessment
Capital
Program/Project
Management
Capital
Program/Project Tools
and Performance
Reporting
Copyright © 2015 by ScottMadden, Inc. All rights reserved.
Capital Program/Project Management Tools and
Performance Reporting Overview
10
F.G.P. PROJECTS DRIVING BOARD
Status
Tendency
(previous)
Tendency
(actual)
TIME COST (Euro) Open issues
Order Project Description
Project
Manager
Type Impact 30-Apr-01 31-M ay-01
Baseline
Start
Baseline
End
Forecast
End
Budget
Actual Forecast & Critical Points
CMFR0027 PRGT00PB Powerbrain Sorrenti F M 1-Nov-00 31-Aug-01 31-Aug-01 26,550 26,085 26,550
CMEV0007 PRGT1572 Impl. Verrone Plant Serafino F M 15-Jan-01 28-Sep-01 28-Sep-01 82,633 0 82,633
CMSP0015 PRGT2982 HRMS new. Devel. Pukly F H 1-Jan-01 31-Dec-01 31-Dec-01 108,785 0 108,785
CMSP0015 PRGT3044 Web professional Pukly F M 15-Apr-01 31-Dec-01 31-Dec-01 71,975 0 71,975
CMSP0039 PRGT0017 Estesa Di Carlo O L 7-May-01 30-Jun-01 30-Jun-01 23,750 0 23,750
CMSP0015 PRGT3047 I.I.S. HR FGP Pukly F L 1-Jan-01 31-Jul-01 31-Jul-01 77,468 0 77,468
CMSP0028 PRGT0014 Engine Sperim. Appl. Brezigar O M 12-Apr-01 31-Dec-01 31-Dec-01 158,479 0 158,479
Total 549,640 26,085 549,640
Legend
Type Compulsory (O) Impact High (H) Status Critical Tendency Flat
Firm(F) Medium(M) Medium Raising
Opportunity (O) Low (L) On track Falling
CODE NAME TYPE
ORDER XXX XXX Date 05/17/2001
PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity
Description: References Architecture
Client: Operating System: Windows NT
Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT
IT Client Manager: Data Base: TBD
User Legal Entity/Functions: IT Application Manager:
IT Architect:
Impact on other Projects/Applications Notes Operating Costs Forecast
Operational: TBD
Maintenance: TBD
Milestones Issues
Start 28-Feb-01 Initial Budget 40,949
End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10
End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489
Expected gap 0.00% Expected gap -6.01% Closed Issues 20
Total Issues 30
% Open Issues/Total Issues 33.33%
Overall Project Status Best Practice Adherence
Impact:
Supplier:
Costs (Euro)
Project Characteristics
50% 100% 150% 200%
total cost forecast
50% 100% 150% 200%
total duration forecast
actualtoday
CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4
CODE NAME TYPE
ORDER XXX XXX Date 05/17/2001
PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity
Description: References Architecture
Client: Operating System: Windows NT
Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT
IT Client Manager: Data Base: TBD
User Legal Entity/Functions: IT Application Manager:
IT Architect:
Impact on other Projects/Applications Notes Operating Costs Forecast
Operational: TBD
Maintenance: TBD
Milestones Issues
Start 28-Feb-01 Initial Budget 40,949
End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10
End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489
Expected gap 0.00% Expected gap -6.01% Closed Issues 20
Total Issues 30
% Open Issues/Total Issues 33.33%
Overall Project Status Best Practice Adherence
Impact:
Supplier:
Costs (Euro)
Project Characteristics
50% 100% 150% 200%
total cost forecast
50% 100% 150% 200%
total duration forecast
actualtoday
CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4
CODE NAME TYPE
ORDER XXX XXX Date 05/17/2001
PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity
Description: References Architecture
Client: Operating System: Windows NT
Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT
IT Client Manager: Data Base: TBD
User Legal Entity/Functions: IT Application Manager:
IT Architect:
Impact on other Projects/Applications Notes Operating Costs Forecast
Operational: TBD
Maintenance: TBD
Milestones Issues
Start 28-Feb-01 Initial Budget 40,949
End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10
End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489
Expected gap 0.00% Expected gap -6.01% Closed Issues 20
Total Issues 30
% Open Issues/Total Issues 33.33%
Overall Project Status Best Practice Adherence
Impact:
Supplier:
Costs (Euro)
Project Characteristics
50% 100% 150% 200%
total cost forecast
50% 100% 150% 200%
total duration forecast
actualtoday
CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4
PROJECT PRGTnnnn Implementation MONTHLY STATUS REPORT
REF. 1 / 24
MONTH MARZO 2001
PHASE PROTOTIPAZIONE
PROJECT STATUS
E’ stato definito il System Integrator. E' stato definito il Piano di progetto.
E' stata impostata la proposta di Struttura Organizzativa di Progetto. E' stata impostata la baseline per i costi di Progetto
Sono state attivate le Procedure di Gestione Scope Change Request, di Gestione Issue List e di Gestione della Documentazione.
E' stato Definito il tool di gestione della documentazione di Progetto. E' stata impostata l'Analisi del Rischio.
OPEN ISSUES ACTIONS RESPONSILE DUE DATE
1 - L'Ambiente di Prototipazione non è disponibile. Predisporre ambiente prototipazione IT Project Manager 06/04/01
NEXT STEPS
Ufficializzazione Struttura Organizzativa di progetto. Definizione dei componenti dei team da parte dei Responsabili/Referenti.
Verifica profilo di spesa e budget Architettura Tecnologica. Impostazione attività di Quality Assurance.
APPROVED CHANGE REQUESTS
Nr. Description Approval Allocated
Date Contingency
15000
19108
21356
25130
28733
33000
38114
34303
36545
40949
15020
19208
21531
25355
29058
33375
34678
36920 38489
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
Gen01
Feb01
Mar01
Apr01
Mag01
Giu01
Lug01
Ago01
Set01
Ott01
Nov01
Dic01
Gen02
Feb02
Mar02
Apr02
Mag02
Giu02
Lug02
Ago02
Set02
Ott02
Nov02
Dic02
Gen03
Feb03
Mar03
Baseline (Core) Baseline (Contingency)
Actual Forecast
Jan-01
Feb-01
Mar-01
Apr-01
May-01
Jun-01
Jul-01
Aug-01
Sep-01
Oct-01
Nov-01
Dec-01
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Jun-02
Jul-02
Aug-02
Sep-02
Oct-02
Nov-02
Dec-02
Jan-03
Feb-03
Mar-03
Apr-03
Capability Release Design 1
Capability Release Design 2
System Test Set Up and Realisation 1
System Test Set Up and Realisation 2
Test & Training
Start Up
Support
ORDER COMM NameComm BASELINE VS ACTUAL VS FORECAST F.G.P.
PROJECT PRGTnnnn Implementation
COST (Euro)
Cost Type Cost Element Baseline Actual Forecast Notes
Development & Implementation 18,550 2,434 18,550
External Resources 0 0 0
Operational/Applicational Mngt 3,783 3,783 3,783
Total System Development 22,333 6,217 22,333
HW/SW Design & Consultancy 1,572 1,572 1,572
HW/SW Acquisition 6,500 6,500 6,500 I costi relativi all'architettura tecnologica saranno dettagliati al termine
SW Licences 3,145 3,145 3,145 della fase di definizione dei requisiti
Total HW/SW Mgnt 11,217 11,217 11,217
Total External Costs 33,550 17,434 33,550
Total Internal Resources 4,564 1,674 4,564
Partial Project Total 38,114 19,108 38,114
Contingency 2,835 100 375 Sono state attivate 3 Scope Change Request
Overall Project Total 40,949 19,208 38,489
HW/SW
Management
System
Development
Back to index
Performance Dashboard
Cost Tracking
Project Scorecard
Risk Map
Progress Report
Schedule
Costs Detail
Data Migration and Go-Live
Resources
Change Management
Project Governance
Low
High
Low High
Value
Manageability
Data Migration and Go-Live
Project Documentation
Resources
Change Management
Project Governance
Project Management
Technological Architecture
Application
Legacy Systems
Interfaces
Project Management
Technological Architecture
Application
Legacy Systems
Interfaces
Project Documentation
ScottMadden
Capital
Program/Project
Assistance
Capital Program
Assessment
Capital
Program/Project
Management
Capital
Program/Project Tools
and Performance
Reporting

More Related Content

PDF
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
PPTX
Decommissioning your offshore assets
PPTX
Wind farm re-powering, life extension and decommissioning
PDF
Rel maint-final
DOC
Resume - DiPasquale -Principal Project Engineer - Electrical
PDF
Data Recovery Approaches
PPSX
Risk Solutions for the Manager
PDF
Asset Integrity Management approach to achieve excellence in Process Safety
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Decommissioning your offshore assets
Wind farm re-powering, life extension and decommissioning
Rel maint-final
Resume - DiPasquale -Principal Project Engineer - Electrical
Data Recovery Approaches
Risk Solutions for the Manager
Asset Integrity Management approach to achieve excellence in Process Safety

What's hot (19)

PPTX
Skills development for the new Oil & Gas industry
DOC
NS Resume S
PPTX
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
PPTX
Pittsburgh case study midfield energy system
PDF
How Bell Energy can help you be a Sustainable and Profitable Organization
PDF
Esound Quick Brochure
PDF
Esound Brochure
DOC
PS JOB RESPONSIBILITIES - Linkedin
DOCX
Mark_Peterson_Jr_resume
PDF
Industrial RCx Smith_Hawksley.doc
PDF
Integrity Management Plan for Pipeline-G03178 Idzuari Azli
PPSX
Introduction to The Augustus Group and RBI
PPTX
Monetizing Risks - A Prioritization & Optimization Solution
DOCX
Angel David Rodriguez - Resume
PDF
Challenges and Opportunities in Implementing an Asset Management Program
PDF
10 - CIP-002-5.1 Medley - Carr
DOCX
jmeyercons10112016
PPTX
Smart Integrated Infrastructure and Controlling Water Loss
PPT
Lawrence.jim
Skills development for the new Oil & Gas industry
NS Resume S
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
Pittsburgh case study midfield energy system
How Bell Energy can help you be a Sustainable and Profitable Organization
Esound Quick Brochure
Esound Brochure
PS JOB RESPONSIBILITIES - Linkedin
Mark_Peterson_Jr_resume
Industrial RCx Smith_Hawksley.doc
Integrity Management Plan for Pipeline-G03178 Idzuari Azli
Introduction to The Augustus Group and RBI
Monetizing Risks - A Prioritization & Optimization Solution
Angel David Rodriguez - Resume
Challenges and Opportunities in Implementing an Asset Management Program
10 - CIP-002-5.1 Medley - Carr
jmeyercons10112016
Smart Integrated Infrastructure and Controlling Water Loss
Lawrence.jim
Ad

Similar to Overcoming the Challenges of Large Capital Programs/Projects (20)

PPTX
Overcoming the Challenges of Large Capital Programs/Projects
PDF
Resume - Jason Lewis
PDF
Importance of O&M
PDF
Petrotech Presenttaion- Punj Lloyd
PDF
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
PDF
Energy Management and the Evolution of Intelligent Motor Control and Drives @...
PDF
commissioning-federal-facilities.pdf
PDF
Building a comissioning guideline
DOC
Zaheer-CV- 2015
PDF
Anupama Kutty Resume
DOCX
Daniel Baze
DOC
Reliability Engineer
PDF
8A_5_RE_India19_079_presentation_Doug_Waters.pdf
DOCX
John Hopwood Resume
PPTX
Module-1_Power System & Load Forecasting
DOC
William Kelvin ParkerZ to A
DOC
CV-cassidy
DOC
Deepak Resume
PDF
road_map (1)
Overcoming the Challenges of Large Capital Programs/Projects
Resume - Jason Lewis
Importance of O&M
Petrotech Presenttaion- Punj Lloyd
Offshore Wind Energy: Improving Project Development and Supply Chain Processe...
Energy Management and the Evolution of Intelligent Motor Control and Drives @...
commissioning-federal-facilities.pdf
Building a comissioning guideline
Zaheer-CV- 2015
Anupama Kutty Resume
Daniel Baze
Reliability Engineer
8A_5_RE_India19_079_presentation_Doug_Waters.pdf
John Hopwood Resume
Module-1_Power System & Load Forecasting
William Kelvin ParkerZ to A
CV-cassidy
Deepak Resume
road_map (1)
Ad

More from ScottMadden, Inc. (20)

PDF
Creating IT Value-A Better Way to Make IT Investment Decisions
PDF
Benchmarking for Natural Gas LDCs
PDF
Benchmarking for Natural Gas LDCs
PPTX
ScottMadden Fossil Benchmarking Analysis
PDF
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
PDF
ScottMadden Fossil Benchmarking Analysis
PDF
ScottMadden Finance Shared Services Benchmark Highlights 2020
PDF
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
PDF
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
PDF
Energy Industry Update Webcast: Don't Stop Believin'
PDF
Combined Cycles
PDF
Technology for HR Shared Services
PDF
Building a Business Case for Shared Services
PDF
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
PDF
Next Generation Shared Services Centers
PDF
California’s Combined Cycle Costs in the Age of the Duck Curve
PDF
Capital Program Assessment Overview
PDF
Value of Strategic Direction
PDF
Generation Trends: What are the Impacts on Transmission?
PDF
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
Creating IT Value-A Better Way to Make IT Investment Decisions
Benchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCs
ScottMadden Fossil Benchmarking Analysis
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden Fossil Benchmarking Analysis
ScottMadden Finance Shared Services Benchmark Highlights 2020
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
Energy Industry Update Webcast: Don't Stop Believin'
Combined Cycles
Technology for HR Shared Services
Building a Business Case for Shared Services
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Next Generation Shared Services Centers
California’s Combined Cycle Costs in the Age of the Duck Curve
Capital Program Assessment Overview
Value of Strategic Direction
Generation Trends: What are the Impacts on Transmission?
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...

Recently uploaded (20)

PPTX
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
PPTX
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
Indian roads congress 037 - 2012 Flexible pavement
PPTX
History, Philosophy and sociology of education (1).pptx
PPTX
Digestion and Absorption of Carbohydrates, Proteina and Fats
PDF
Empowerment Technology for Senior High School Guide
PDF
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
A systematic review of self-coping strategies used by university students to ...
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PDF
What if we spent less time fighting change, and more time building what’s rig...
PPTX
Introduction to Building Materials
PDF
advance database management system book.pdf
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
IGGE1 Understanding the Self1234567891011
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
Chinmaya Tiranga quiz Grand Finale.pdf
Indian roads congress 037 - 2012 Flexible pavement
History, Philosophy and sociology of education (1).pptx
Digestion and Absorption of Carbohydrates, Proteina and Fats
Empowerment Technology for Senior High School Guide
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
Supply Chain Operations Speaking Notes -ICLT Program
Weekly quiz Compilation Jan -July 25.pdf
A systematic review of self-coping strategies used by university students to ...
Final Presentation General Medicine 03-08-2024.pptx
Practical Manual AGRO-233 Principles and Practices of Natural Farming
What if we spent less time fighting change, and more time building what’s rig...
Introduction to Building Materials
advance database management system book.pdf
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
A powerpoint presentation on the Revised K-10 Science Shaping Paper
IGGE1 Understanding the Self1234567891011
Chinmaya Tiranga Azadi Quiz (Class 7-8 )

Overcoming the Challenges of Large Capital Programs/Projects

  • 1. Copyright © 2015 ScottMadden, Inc. All rights reserved. Report _2015 Overcoming the Challenges of Large Capital Programs/Projects Applying Lessons Learned from Extended Power Uprates June 2015
  • 2. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Introduction ■ Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance ■ However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception ■ Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations to ensure compliance with a number of concerns, including: • Plant retrofits and conversions • Ash pond closures • Fukushima modifications • Security upgrade requirements • Extended power uprates (EPUs) ■ Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management challenges ■ Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project 1 Lessons learned from extended power uprates can be applied to any large capital program/project.
  • 3. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Overview of Power Uprates ■ Power uprates allow utilities to generate more electricity from their existing nuclear plants ■ Since the 1970s, the NRC has approved 154 uprates, which have collectively added generating capacity equivalent to about seven new reactors ■ Three types of uprates are available to a nuclear plant operator: measurement uncertainty recapture, stretch, and extended ■ As shown in the table above, implementing EPUs presents the biggest project challenges, given the need to significantly modify major pieces of plant equipment 2 Power Uprate Type Increase to Licensed Power Levels Plant and System Impacts Measurement uncertainty recapture < 2% Implementing improved techniques for calculating reactor power, e.g., utilizing state-of-the-art devices to more precisely measure feedwater flow Stretch 2 to 7% Changing instrumentation settings without major plant modifications Extended 7 to 20% Significantly modifying to major pieces of non-nuclear equipment, e.g., high-pressure turbines, condensate pumps and motors, main generators, and transformers Source: www.nrc.gov, Backgrounder on Power Uprates for Nuclear Plants
  • 4. Copyright © 2015 by ScottMadden, Inc. All rights reserved. EPU Project Challenges EPU projects pose significant scope, implementation, and workforce management challenges ■ Scope • Scope is fluid as the EPU project is implemented • Outages are typically much bigger in scope than a refueling outage, requiring the significant change-outs or upgrades of major equipment • Changes to the plant configuration (structures, equipment, and systems) must be precisely documented ■ Implementation • In many cases, the work is done while other units are still in operation • A high degree of project control rigor is required to accurately track cost and schedule against evolving scope • Physical security, ALARA limits, lock-out/tag-out requirements, etc., make the work environment very complex ■ Workforce management • A large number of skilled teams (craft workers and supervisors) that may have never worked together are involved • Some trades and/or skills are likely to be in short supply • Many workers are new to a nuclear plant work environment and lack knowledge of nuclear safety and quality standards 3 Sources: 1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011 2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects”, Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
  • 5. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Lessons Learned from Recent EPU Efforts ■ Planning for contingences is critical. In some cases: • Actual costs more than doubled over initially planned costs • Outage durations were as much as 25% longer than planned • Additional outages were required to complete the work ■ Costs and schedules should include contingencies for productivity issues, replacing vs. repairing components, and licensing delays • Preliminary cost estimates, based on conceptual scope, may not capture all of the work necessary to complete the project • Some components that are initially expected to be repaired or recertified will require replacement, i.e., during configuration control verification, perform a detailed drawing walk-down of pumps, motors, valve controls, etc., to minimize scope surprises • Major construction activities at an operating nuclear plant, many of which occur in remote and radiologic-controlled portions of the plant, can cause significant implementation difficulties and delays – Space for installation can be extremely tight and may require removal or working around hundreds of interferences – Productivity can be slowed due to the specialized and time-consuming procedures to ensure worker safety in radiologic- controlled and electrically sensitive areas of the plant • Increasingly conservative regulatory requirements outside of a company’s control can cause significant licensing delays ■ Obtaining and retaining experienced workers is a challenge ■ Active management of vendors is required to ensure productivity is maintained, issues are raised, and progress is on schedule 4
  • 6. Copyright © 2015 by ScottMadden, Inc. All rights reserved. EPU Project Keys to Success 5 ■ Encourage workforce collaboration and the ability of employees to voice concerns early and often to avoid costly errors, re-work, and safety hazards, i.e., maintain a focus on quality and safety ■ Develop a self-critical culture focused on improvement and efficiency ■ Recognize that the EPU team can not anticipate all the changes that will occur during the project ■ Utilize project management technology where possible to improve efficiency and communication ■ Hold regular project team meetings and invite senior leadership periodically to reinforce the priority of the project Work Environment Planning ■ Be honest and realistic about the complexity and uniqueness of the EPU project; investing early in planning and current state analysis can save a lot of rework ■ Recognize that the planning process continues all the way to project completion and that the EPU team should always be looking to improve costs, schedule, and general efficiency ■ Make benchmarking trips and incorporate lessons learned and insights, e.g., NEDO-33159, from recent EPU and stretch uprates projects into planning ■ Bring in field engineers and/or craft supervisors early in the process for review and comment on actual configuration vs. drawings and equipment installation implications ■ Hold combined design reviews with members from different disciplines; utilize the experience and expertise from each discipline to come up with a collectively better solution ■ Develop integrated work packages to improve efficiency and overall performance Sources: 1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011 2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects,” Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
  • 7. Copyright © 2015 by ScottMadden, Inc. All rights reserved. EPU Project Keys to Success (Cont’d) 6 Vendor/ Contractor Alignment ■ Align vendors and contractors with project objectives and the uniqueness of the project ■ Ensure vendors and contractors are aware of and held to the tenets of nuclear safety and align their nuclear safety culture with that of your company ■ Work collaboratively with contractors and combine cost, schedule, and human performance monitoring tools and processes ■ Ensure contracts have clear terms and conditions and are very specific in scope and timing ■ Plan for vendor handoffs of work products and resolve disputes promptly to reduce idle vendor time Implementation ■ Manage like a large-scale engineering, procurement, and construction project and not like a modifications project or refueling outage, e.g., funding is stage-gated ■ Collect accurate data and monitor relevant performance metrics throughout the EPU project ■ Conduct periodic independent project audits using industry experts with previous EPU experience ■ Involve employees who will operate the plant during implementation ■ Ensure operating staff are adequately trained on how the plant will operate after the power uprate, e.g., operations, maintenance, engineering, radiation protection personnel, etc. ■ Update all affected documentation, e.g., operating and maintenance procedures, to reflect the new operating conditions ■ Focus on procedure development, training, and simulator modeling to help verify actual plant response vs. expected plant response in power uprated conditions Sources: 1. IAEA Nuclear Energy Series No. NP-T-3.9, Power Uprate in Nuclear Power Plants: Guidelines and Experience, 2011 2. Von Lazar, Laszlo, “Lessons Learned from Successful Nuclear Uprate Projects,” Nuclear Power International Magazine, Volume 6, No. 4, July/August 2013
  • 8. Copyright © 2015 by ScottMadden, Inc. All rights reserved. How ScottMadden Can Help 7 ScottMadden Capital Program/Project Assistance Perform a top-to-bottom assessment of the capital program to position it for success from the start Capital Program Assessment Capital Program/Project Management Capital Program/Project Tools and Performance Reporting Assist in establishing and implementing the organization and governance to successfully deliver the program/project Assist in establishing and implementing the tools and performance reporting to successfully control and monitor the program/project
  • 9. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Capital Program Assessment Overview ScottMadden’s Capital Program Assessment examines how the capital program is implemented—from top to bottom—with a look at the PMO and a review of the performance reporting and tools in place. 8 Program Management Office Step 1: Capital Program Analysis Step 2: Process Evaluation Copyright © 2013 by ScottMadden. All rights reserved. 5 Constructability activities within alliance projects are being introduced later in the cradle to grave construction process than is typical for large project management Findings Constructability – Cost Savings Driver Current lack of a constructability process across all the elements of the construction cradle to grave process is a significant driver in NEA cost estimates being high Best In Class Projects Typical NEA Project ScottMadden’s approach analyzes these critical areas to provide a detailed assessment of your capital program with actionable recommendations. Step 6: Recommendations and Action Plan EPU Project Step 4: Execution AssessmentStep 3: Organization Analysis Step 5: Performance Reporting and Tools Evaluation ScottMadden Capital Program/Project Assistance Capital Program Assessment Capital Program/Project Management Capital Program/Project Tools and Performance Reporting
  • 10. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Capital Program/Project Management Overview 9 Focus On ◼ Organization and governance ◼ Functional relationship management ◼ Partnership with other entities Tools ◼ Performance Dashboard ◼ Issue List (high impact and level) ◼ Monthly Progress Report ◼ Risk Analysis and Mitigation Plan (high impact and level) ◼ Inter-project coordination ◼ Inter-project resource coordination ◼ Cross functionalities ◼ Best practice usage ◼ Documentation management ◼ Project milestones ◼ Costs ◼ Times ◼ Business/technical goals ◼ Projects List ◼ Project Procedures ◼ Project Dashboard ◼ Milestones Tracking ◼ Issue List (Aggregated) ◼ Risk Analysis and Mitigation Plan (Aggregated) ◼ Weekly and Monthly Progress Reports ◼ Project Plan ◼ Project Documentation Management ◼ Milestones Tracking ◼ Risk Analysis and Mitigation Plan ◼ Change Request Management ◼ Issue List Management ◼ Project Baseline and Progress Report ◼ Weekly Progress Meeting Minutes ◼ Weekly Progress Report ◼ Monthly Progress Report Program Manager Project Office Project Managers ScottMadden Capital Program/Project Assistance Capital Program Assessment Capital Program/Project Management Capital Program/Project Tools and Performance Reporting
  • 11. Copyright © 2015 by ScottMadden, Inc. All rights reserved. Capital Program/Project Management Tools and Performance Reporting Overview 10 F.G.P. PROJECTS DRIVING BOARD Status Tendency (previous) Tendency (actual) TIME COST (Euro) Open issues Order Project Description Project Manager Type Impact 30-Apr-01 31-M ay-01 Baseline Start Baseline End Forecast End Budget Actual Forecast & Critical Points CMFR0027 PRGT00PB Powerbrain Sorrenti F M 1-Nov-00 31-Aug-01 31-Aug-01 26,550 26,085 26,550 CMEV0007 PRGT1572 Impl. Verrone Plant Serafino F M 15-Jan-01 28-Sep-01 28-Sep-01 82,633 0 82,633 CMSP0015 PRGT2982 HRMS new. Devel. Pukly F H 1-Jan-01 31-Dec-01 31-Dec-01 108,785 0 108,785 CMSP0015 PRGT3044 Web professional Pukly F M 15-Apr-01 31-Dec-01 31-Dec-01 71,975 0 71,975 CMSP0039 PRGT0017 Estesa Di Carlo O L 7-May-01 30-Jun-01 30-Jun-01 23,750 0 23,750 CMSP0015 PRGT3047 I.I.S. HR FGP Pukly F L 1-Jan-01 31-Jul-01 31-Jul-01 77,468 0 77,468 CMSP0028 PRGT0014 Engine Sperim. Appl. Brezigar O M 12-Apr-01 31-Dec-01 31-Dec-01 158,479 0 158,479 Total 549,640 26,085 549,640 Legend Type Compulsory (O) Impact High (H) Status Critical Tendency Flat Firm(F) Medium(M) Medium Raising Opportunity (O) Low (L) On track Falling CODE NAME TYPE ORDER XXX XXX Date 05/17/2001 PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity Description: References Architecture Client: Operating System: Windows NT Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT IT Client Manager: Data Base: TBD User Legal Entity/Functions: IT Application Manager: IT Architect: Impact on other Projects/Applications Notes Operating Costs Forecast Operational: TBD Maintenance: TBD Milestones Issues Start 28-Feb-01 Initial Budget 40,949 End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10 End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489 Expected gap 0.00% Expected gap -6.01% Closed Issues 20 Total Issues 30 % Open Issues/Total Issues 33.33% Overall Project Status Best Practice Adherence Impact: Supplier: Costs (Euro) Project Characteristics 50% 100% 150% 200% total cost forecast 50% 100% 150% 200% total duration forecast actualtoday CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4 CODE NAME TYPE ORDER XXX XXX Date 05/17/2001 PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity Description: References Architecture Client: Operating System: Windows NT Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT IT Client Manager: Data Base: TBD User Legal Entity/Functions: IT Application Manager: IT Architect: Impact on other Projects/Applications Notes Operating Costs Forecast Operational: TBD Maintenance: TBD Milestones Issues Start 28-Feb-01 Initial Budget 40,949 End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10 End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489 Expected gap 0.00% Expected gap -6.01% Closed Issues 20 Total Issues 30 % Open Issues/Total Issues 33.33% Overall Project Status Best Practice Adherence Impact: Supplier: Costs (Euro) Project Characteristics 50% 100% 150% 200% total cost forecast 50% 100% 150% 200% total duration forecast actualtoday CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4 CODE NAME TYPE ORDER XXX XXX Date 05/17/2001 PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity Description: References Architecture Client: Operating System: Windows NT Client Legal Entity/Functions: IT Project Manager: HW Platform: Server Compaq NT IT Client Manager: Data Base: TBD User Legal Entity/Functions: IT Application Manager: IT Architect: Impact on other Projects/Applications Notes Operating Costs Forecast Operational: TBD Maintenance: TBD Milestones Issues Start 28-Feb-01 Initial Budget 40,949 End (Baseline) 31-Mar-03 Actual 19,208 Open Issues 10 End (Estimate to date) 31-Mar-03 Total Cost Forecast 38,489 Expected gap 0.00% Expected gap -6.01% Closed Issues 20 Total Issues 30 % Open Issues/Total Issues 33.33% Overall Project Status Best Practice Adherence Impact: Supplier: Costs (Euro) Project Characteristics 50% 100% 150% 200% total cost forecast 50% 100% 150% 200% total duration forecast actualtoday CRITICAL MEDIUM GOOD HIGH MEDIUM LOW 0 1 2 3 4 PROJECT PRGTnnnn Implementation MONTHLY STATUS REPORT REF. 1 / 24 MONTH MARZO 2001 PHASE PROTOTIPAZIONE PROJECT STATUS E’ stato definito il System Integrator. E' stato definito il Piano di progetto. E' stata impostata la proposta di Struttura Organizzativa di Progetto. E' stata impostata la baseline per i costi di Progetto Sono state attivate le Procedure di Gestione Scope Change Request, di Gestione Issue List e di Gestione della Documentazione. E' stato Definito il tool di gestione della documentazione di Progetto. E' stata impostata l'Analisi del Rischio. OPEN ISSUES ACTIONS RESPONSILE DUE DATE 1 - L'Ambiente di Prototipazione non è disponibile. Predisporre ambiente prototipazione IT Project Manager 06/04/01 NEXT STEPS Ufficializzazione Struttura Organizzativa di progetto. Definizione dei componenti dei team da parte dei Responsabili/Referenti. Verifica profilo di spesa e budget Architettura Tecnologica. Impostazione attività di Quality Assurance. APPROVED CHANGE REQUESTS Nr. Description Approval Allocated Date Contingency 15000 19108 21356 25130 28733 33000 38114 34303 36545 40949 15020 19208 21531 25355 29058 33375 34678 36920 38489 0 5000 10000 15000 20000 25000 30000 35000 40000 45000 Gen01 Feb01 Mar01 Apr01 Mag01 Giu01 Lug01 Ago01 Set01 Ott01 Nov01 Dic01 Gen02 Feb02 Mar02 Apr02 Mag02 Giu02 Lug02 Ago02 Set02 Ott02 Nov02 Dic02 Gen03 Feb03 Mar03 Baseline (Core) Baseline (Contingency) Actual Forecast Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01 Jan-02 Feb-02 Mar-02 Apr-02 May-02 Jun-02 Jul-02 Aug-02 Sep-02 Oct-02 Nov-02 Dec-02 Jan-03 Feb-03 Mar-03 Apr-03 Capability Release Design 1 Capability Release Design 2 System Test Set Up and Realisation 1 System Test Set Up and Realisation 2 Test & Training Start Up Support ORDER COMM NameComm BASELINE VS ACTUAL VS FORECAST F.G.P. PROJECT PRGTnnnn Implementation COST (Euro) Cost Type Cost Element Baseline Actual Forecast Notes Development & Implementation 18,550 2,434 18,550 External Resources 0 0 0 Operational/Applicational Mngt 3,783 3,783 3,783 Total System Development 22,333 6,217 22,333 HW/SW Design & Consultancy 1,572 1,572 1,572 HW/SW Acquisition 6,500 6,500 6,500 I costi relativi all'architettura tecnologica saranno dettagliati al termine SW Licences 3,145 3,145 3,145 della fase di definizione dei requisiti Total HW/SW Mgnt 11,217 11,217 11,217 Total External Costs 33,550 17,434 33,550 Total Internal Resources 4,564 1,674 4,564 Partial Project Total 38,114 19,108 38,114 Contingency 2,835 100 375 Sono state attivate 3 Scope Change Request Overall Project Total 40,949 19,208 38,489 HW/SW Management System Development Back to index Performance Dashboard Cost Tracking Project Scorecard Risk Map Progress Report Schedule Costs Detail Data Migration and Go-Live Resources Change Management Project Governance Low High Low High Value Manageability Data Migration and Go-Live Project Documentation Resources Change Management Project Governance Project Management Technological Architecture Application Legacy Systems Interfaces Project Management Technological Architecture Application Legacy Systems Interfaces Project Documentation ScottMadden Capital Program/Project Assistance Capital Program Assessment Capital Program/Project Management Capital Program/Project Tools and Performance Reporting