64 th  Avenue / Mufford Crescent Rail Overpass F ebruary 9, 2009
Today’s Situation Safety is an issue every time a train travels through the Langley municipalities Long delays at rail crossings result in increased costs and environmental impacts For every minute a train blocks a crossing there is a five minute multiplier effect on traffic resulting in gridlock during peak hours
CTA Warrants ALREADY exceeded for Grade Separation
 
2006 Community Survey 69% are prepared to pay $60 per year/ $5 per month  to construct options that will avoid congestion at Rail Crossings.
The Need Port Metro Vancouver –essential for Canada, BC, Metro Vancouver, Langleys Growth in Road & Rail Traffic Continuing & increasing GRIDLOCK without overpasses Port Expansion in progress 3rd Berth completion in 2009 Phase 2 to add 3 more berths (total 6 berths)
Projected Train Growth
First Choice Use Alternative Rail Route(s) for Heavy Rail Traffic to/from port This has been explored vigorously and exhaustively and we are advised this is not a realistic option.
Facing Reality Seek an overpass solution which : Improves Safety Functions Effectively Is sustainable Environmentally: CEAA, ALC Socially Economically Is ‘doable’ Is ‘fundable’
TOL Master Transportation Plan Willowbrook Street Plan 6.3B
Finding an Optimum Solution Wide support for an overpass Rail O/P is a distinct benefit in all scenarios (including passenger train)  Mobility is enhanced by roads in a grid network Effective, efficient, provides alternatives Proposed overpass adds a strategic network link Primarily for Langley traffic As an alternative for other traffic  during  a rail event.
Map 64/ Mufford Network Link
Open House (OH) 390 attendees Provided the project valuable input and suggestions to improve or enhance the design Identified information gaps that exist and we will address tonight
Regional Network Recent upgrades to Pacific Highway and Highway#10 west of Cloverdale and imminent construction of South Fraser Perimeter Road will help avoid congestion in Langley.
 
Langley Network Until recently traffic from northwest to southeast and return relies on Langley By-Pass. Network enhanced by addition of 2 links – both rail overpasses 204 St (City network N-S), and  64/Mufford (E-W) Result: balanced use of network with traffic distribution that avoids pinch points and entanglement.
64/Mufford Overpass Open Houses revealed several specific concerns regarding community issues and further impacts. What we heard.  Traffic at capacity at Glover/72/Crush especially during a rail event with queues onto 216. Resolve to consider improvements at this intersection. Residents along 64 are concerned with increased traffic.  Resolve to direct traffic to Glover by installing directional signage at 216/64 to Highway 1.
 
Other alignment options Community is seeking answers to other alignments; First principles: Improve safety (separate vehicles from trains); Network connectivity (improve mobility, decrease congestion, improve emergency response times); Network redundancy (alternative route in event of accident or emergency)
 
Option ‘J’ PROS Separates trains / vehicles Smaller initial impact to ALR lands CONS   Fails to improve network connectivity
Option ‘J’ CONS (cont’d) Focuses traffic into a congested area. Requires widening of By-Pass Requires longer structure  S/bound connection from Glover difficult and costly High environmental impact in difficult soils Increases ALR impact in med./long term Not supported by other partners.
Public Consultation Since 2004 Langley Township has consulted with the public on design concepts and alignments Oct. 25, 2004, Presentation of design concepts to Mayor and Council April 30, 2005, Willowbrook Mall, Public display.  May 3, 2005, Christian Life Assembly, Joint Township & City Council Meeting. Public display.  March 16, 2006, Community Survey reveals traffic remains top concern and 69% are prepared to pay $60 per year / $5 per month  to construct options that will avoid congestion at Rail Crossings.  February 5, 2007 Council Report 07-15 “Master Transportation Plan” March 22, 2007, Civic Facility, Public Open House Master Transportation Plan
Other Issues Project does not include closing of farm accesses that cross railway Port expansion increases rail traffic – Transport Canada initiated study to determine strategy to resolve transportation/community impacts. Project funding is $51M of which Langley Township share is $9.3M There are no plans to double track CP Rail or widen Hwy #10 (Glover Road) in this area. The Province and ALC have no plans to exclude land from the ALR in this area.
END OF PRESENTATION

More Related Content

PDF
AAB #11 241 Somerville, MA:latest route around our rights
PPT
64 Mufford Project Status - Dec 15, 2008
PDF
Dumbarton transportation corridor study update
PPT
South Fraser transit plan
PPTX
BCRT Overview
PPT
Mayor Kurt Alberts Presentation
PPTX
RBRC Presentation oct 18_11_langley chamber final
PPTX
The State of Rail in Illinois
AAB #11 241 Somerville, MA:latest route around our rights
64 Mufford Project Status - Dec 15, 2008
Dumbarton transportation corridor study update
South Fraser transit plan
BCRT Overview
Mayor Kurt Alberts Presentation
RBRC Presentation oct 18_11_langley chamber final
The State of Rail in Illinois

What's hot (20)

PPTX
Transit-Oriented Communities for South of Fraser
PDF
Georgia Traffic Mega Projects December 2019
PPT
Port Orange Mobility Plan Fpza Presentation 2009
PPTX
Connecting to the future: how transport will shape the City of Fremantle
PPTX
PPTX
Swanston Street Presentation
PPT
Auckland public transport issues presentation - 30 july 04 - birkenhead colle...
PDF
APWA mid atlantic awards
PDF
SMART Plan DTPW Corridor Estimates
PPT
Township of Langley Community Rail Study Council Presentation April 21
PPTX
Phil Lawes
PPT
Neighborhood Greenways
PPT
Building a Better Metro: Possibilities for BRT
PDF
HSH Dearborn County Indiana June 2019 fullbinder_v4-printversion-60p
PDF
SE Corridor Opening_2014
PDF
RV 2015: Sustainable Corridors: Broad and Specific Looks by Robert Hastings
PDF
State Bridge Profile Colorado 2014
PDF
State Bridge Profile California 2014
PPTX
Highway civil
PDF
State Bridge Profile New York 2014
Transit-Oriented Communities for South of Fraser
Georgia Traffic Mega Projects December 2019
Port Orange Mobility Plan Fpza Presentation 2009
Connecting to the future: how transport will shape the City of Fremantle
Swanston Street Presentation
Auckland public transport issues presentation - 30 july 04 - birkenhead colle...
APWA mid atlantic awards
SMART Plan DTPW Corridor Estimates
Township of Langley Community Rail Study Council Presentation April 21
Phil Lawes
Neighborhood Greenways
Building a Better Metro: Possibilities for BRT
HSH Dearborn County Indiana June 2019 fullbinder_v4-printversion-60p
SE Corridor Opening_2014
RV 2015: Sustainable Corridors: Broad and Specific Looks by Robert Hastings
State Bridge Profile Colorado 2014
State Bridge Profile California 2014
Highway civil
State Bridge Profile New York 2014
Ad

Viewers also liked (8)

PPS
Ahi Va El Dinero. .
PPT
Servicio Comunitario Robinsoniano
PPT
contaminacion
PPT
Instalando Rails en Windows
PDF
Bmma240108 Social Networks Hr 4
PPT
United States
PPT
Los Alimentos
Ahi Va El Dinero. .
Servicio Comunitario Robinsoniano
contaminacion
Instalando Rails en Windows
Bmma240108 Social Networks Hr 4
United States
Los Alimentos
Ad

Similar to Overpass Solution (20)

PDF
Waterfront Transit Reset Phase 2 Display Panels
PPT
TOWNSHIP OF LANGLEY/PROVINCIAL, REGIONAL AND LOCAL TRANSPORTATION PLANS AND S...
PDF
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
PPTX
February Transit Update Presentation
PPTX
I-66 Multimodal Improvements Inside the Beltway
PDF
Toronto Relief Line Public Meeting Presentation
PPTX
2016-06-06 Scarborough Subway Extension SAG
PPTX
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
PDF
2024-06_SheppardConsultationRnd2_Final_.pdf
PDF
CapstonePoster 36x48 Supernova
PPTX
I495 route 9 sac meeting 1 9 8-11
PPTX
JKRAJEWSKI_ODOT2014_Light Rail Presentation
PPTX
Coordinated Transit Planning in Toronto
PPTX
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
PPT
02 cta yellow line station evanston cc 04.16.12
PPTX
VTA North County Open House Presentation April 2014
PPTX
Fairfax County and Franconia-Springfield Parkways - Alternatives Analysis and...
PDF
2003 Menlo Park Grade Separation Report
PDF
Highland Creek Village Transportation Master Plan
PPTX
BC Ministry of Transportation Transit Presentation
Waterfront Transit Reset Phase 2 Display Panels
TOWNSHIP OF LANGLEY/PROVINCIAL, REGIONAL AND LOCAL TRANSPORTATION PLANS AND S...
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
February Transit Update Presentation
I-66 Multimodal Improvements Inside the Beltway
Toronto Relief Line Public Meeting Presentation
2016-06-06 Scarborough Subway Extension SAG
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
2024-06_SheppardConsultationRnd2_Final_.pdf
CapstonePoster 36x48 Supernova
I495 route 9 sac meeting 1 9 8-11
JKRAJEWSKI_ODOT2014_Light Rail Presentation
Coordinated Transit Planning in Toronto
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
02 cta yellow line station evanston cc 04.16.12
VTA North County Open House Presentation April 2014
Fairfax County and Franconia-Springfield Parkways - Alternatives Analysis and...
2003 Menlo Park Grade Separation Report
Highland Creek Village Transportation Master Plan
BC Ministry of Transportation Transit Presentation

More from jgabateman (20)

PDF
Langley School District Enrollment
PPT
196 Street Rail Overpass Plan
PPTX
Aldergrove Aquifer Issues
PPTX
Murrayville Heritage Conservation Area
PPT
District Energy in the Township of Langley
PPT
Employment Lands Study
PPT
Langley Child & Youth Committee
PPT
Rcmp Quarterly Report
PPT
Public Hearing Development Applications 2009 12 14
PPT
Special Development Applications 2009 12 14
PPT
Regular Development Applications 2009 12 14
PDF
Aplin Martin Presentation Dec 7
PDF
Aplin Martin Presentation Dec 7
PPSX
Trust Status Oct 26
PPT
Special Development Applications 2009 10 26
PPTX
Safer Homes
PPT
Regular Development Applications 2009 10 26
PDF
E Comm 9 1 1
PPT
Invasive Species in the Township of Langley
PPTX
Experience The Fraser
Langley School District Enrollment
196 Street Rail Overpass Plan
Aldergrove Aquifer Issues
Murrayville Heritage Conservation Area
District Energy in the Township of Langley
Employment Lands Study
Langley Child & Youth Committee
Rcmp Quarterly Report
Public Hearing Development Applications 2009 12 14
Special Development Applications 2009 12 14
Regular Development Applications 2009 12 14
Aplin Martin Presentation Dec 7
Aplin Martin Presentation Dec 7
Trust Status Oct 26
Special Development Applications 2009 10 26
Safer Homes
Regular Development Applications 2009 10 26
E Comm 9 1 1
Invasive Species in the Township of Langley
Experience The Fraser

Recently uploaded (20)

PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
Business model innovation report 2022.pdf
PDF
How to Get Funding for Your Trucking Business
PPT
Data mining for business intelligence ch04 sharda
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
Types of control:Qualitative vs Quantitative
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PPT
Chapter four Project-Preparation material
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
A Brief Introduction About Julia Allison
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Roadmap Map-digital Banking feature MB,IB,AB
WRN_Investor_Presentation_August 2025.pdf
Business model innovation report 2022.pdf
How to Get Funding for Your Trucking Business
Data mining for business intelligence ch04 sharda
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
340036916-American-Literature-Literary-Period-Overview.ppt
Types of control:Qualitative vs Quantitative
unit 1 COST ACCOUNTING AND COST SHEET
Chapter four Project-Preparation material
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Probability Distribution, binomial distribution, poisson distribution
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Power and position in leadershipDOC-20250808-WA0011..pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx
HR Introduction Slide (1).pptx on hr intro
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
A Brief Introduction About Julia Allison
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx

Overpass Solution

  • 1. 64 th Avenue / Mufford Crescent Rail Overpass F ebruary 9, 2009
  • 2. Today’s Situation Safety is an issue every time a train travels through the Langley municipalities Long delays at rail crossings result in increased costs and environmental impacts For every minute a train blocks a crossing there is a five minute multiplier effect on traffic resulting in gridlock during peak hours
  • 3. CTA Warrants ALREADY exceeded for Grade Separation
  • 4.  
  • 5. 2006 Community Survey 69% are prepared to pay $60 per year/ $5 per month to construct options that will avoid congestion at Rail Crossings.
  • 6. The Need Port Metro Vancouver –essential for Canada, BC, Metro Vancouver, Langleys Growth in Road & Rail Traffic Continuing & increasing GRIDLOCK without overpasses Port Expansion in progress 3rd Berth completion in 2009 Phase 2 to add 3 more berths (total 6 berths)
  • 8. First Choice Use Alternative Rail Route(s) for Heavy Rail Traffic to/from port This has been explored vigorously and exhaustively and we are advised this is not a realistic option.
  • 9. Facing Reality Seek an overpass solution which : Improves Safety Functions Effectively Is sustainable Environmentally: CEAA, ALC Socially Economically Is ‘doable’ Is ‘fundable’
  • 10. TOL Master Transportation Plan Willowbrook Street Plan 6.3B
  • 11. Finding an Optimum Solution Wide support for an overpass Rail O/P is a distinct benefit in all scenarios (including passenger train) Mobility is enhanced by roads in a grid network Effective, efficient, provides alternatives Proposed overpass adds a strategic network link Primarily for Langley traffic As an alternative for other traffic during a rail event.
  • 12. Map 64/ Mufford Network Link
  • 13. Open House (OH) 390 attendees Provided the project valuable input and suggestions to improve or enhance the design Identified information gaps that exist and we will address tonight
  • 14. Regional Network Recent upgrades to Pacific Highway and Highway#10 west of Cloverdale and imminent construction of South Fraser Perimeter Road will help avoid congestion in Langley.
  • 15.  
  • 16. Langley Network Until recently traffic from northwest to southeast and return relies on Langley By-Pass. Network enhanced by addition of 2 links – both rail overpasses 204 St (City network N-S), and 64/Mufford (E-W) Result: balanced use of network with traffic distribution that avoids pinch points and entanglement.
  • 17. 64/Mufford Overpass Open Houses revealed several specific concerns regarding community issues and further impacts. What we heard. Traffic at capacity at Glover/72/Crush especially during a rail event with queues onto 216. Resolve to consider improvements at this intersection. Residents along 64 are concerned with increased traffic. Resolve to direct traffic to Glover by installing directional signage at 216/64 to Highway 1.
  • 18.  
  • 19. Other alignment options Community is seeking answers to other alignments; First principles: Improve safety (separate vehicles from trains); Network connectivity (improve mobility, decrease congestion, improve emergency response times); Network redundancy (alternative route in event of accident or emergency)
  • 20.  
  • 21. Option ‘J’ PROS Separates trains / vehicles Smaller initial impact to ALR lands CONS Fails to improve network connectivity
  • 22. Option ‘J’ CONS (cont’d) Focuses traffic into a congested area. Requires widening of By-Pass Requires longer structure S/bound connection from Glover difficult and costly High environmental impact in difficult soils Increases ALR impact in med./long term Not supported by other partners.
  • 23. Public Consultation Since 2004 Langley Township has consulted with the public on design concepts and alignments Oct. 25, 2004, Presentation of design concepts to Mayor and Council April 30, 2005, Willowbrook Mall, Public display. May 3, 2005, Christian Life Assembly, Joint Township & City Council Meeting. Public display. March 16, 2006, Community Survey reveals traffic remains top concern and 69% are prepared to pay $60 per year / $5 per month to construct options that will avoid congestion at Rail Crossings. February 5, 2007 Council Report 07-15 “Master Transportation Plan” March 22, 2007, Civic Facility, Public Open House Master Transportation Plan
  • 24. Other Issues Project does not include closing of farm accesses that cross railway Port expansion increases rail traffic – Transport Canada initiated study to determine strategy to resolve transportation/community impacts. Project funding is $51M of which Langley Township share is $9.3M There are no plans to double track CP Rail or widen Hwy #10 (Glover Road) in this area. The Province and ALC have no plans to exclude land from the ALR in this area.