Partial Backfill
  Alternative
       January 21, 2010
Cooperator’s Meeting Presentation
Partial Backfill Alternative

Considerations
•  Be responsive to an Issue
•  Minimize water that collects in the pit
•  Return waste rock to the pit
•  Minimize resources that are used in
   backfilling
•  Minimize air impacts
Partial Backfill Alternative
   Environmental Considerations

•  Compliance with all applicable regulations
   including ADEQ BADCT and air regulations
•  Maintain a Hydraulic Sink
•  Geochemical considerations with the addition of
   a mix of finer grained materials
•  Stormwater controls during backfill
•  Effect on concurrent reclamation and on
   reclamation planning
Pit Lake Development
Hydrogeologic Study Results
                              Pit Lake
                                             Pit Lake Depth
           Period            Elevation
                                                  (feet)
                             (ft amsl)

        Mine Closure          (None)               0

     Closure + 20 years        3,591              541

     Closure + 50 years        3,751              701

     Closure + 100 years       3,869              819


•  Backfill elevation – 3825 ft amsl (est.)
•  Elevation was estimated to maintain sink (modeling to confirm
   elevation estimation with operational adjustments as necessary)
Other Considerations

•  Heap Leach remains undisturbed
•  Haulage fleet used will be consistent in size
   to current fleet
•  Loading equipment (shovel used will
   be consistent with current loading
   equipment)
•  Waste rock density is 11.95 ft3/ton
•  Swell factor for the rock is 1.3
Other Considerations

•  Amount of material necessary for backfill is
   90 million tons (46 million cubic yards)
•  Allowance of 5% added for construction of
   ramps for downhill haulage
•  Total material rehandled 94 million tons
•  36-months required to complete backfill
•  Hauls will incorporate 3 switchbacks at
   -10% grade at a maximum 13 mph
Backfill and
Excavation Area
•  Excavation on 50 foot
   benches
•  Start elevation approx
   5429 ft amsl
•  Final elevation 5200
   ft amsl
•  Dumped into pit from
   3825 ft elevation
Productivity by Bench
         Bench	
                Tonnage	
  	
  	
  	
   Cumula+ve	
                    Haulage	
  
       Eleva+on	
  	
  	
  	
   (x	
  1,000)	
   Tonnage	
  	
  	
  	
  	
  	
  	
   Produc+on	
  	
  	
  
       (.	
  amsl)	
                                     (x	
  1,000)	
              (tons/hour)	
  
          5420                        8,938                    8,938                     379
          5400                     18,435                    27,373                      387
          5350                     18,689                   46,062                       395
          5300                     16,277                   62,338                       403
          5250                     12,977                   75,315                       411
          5200                        8,720                 84,036                       419


This information was used to determine the appropriate
haulage fleet for this activity matched to one shovel.
Required Haulage Hours and Units

                          Rehandle	
                              CAT	
  793C	
  Truck	
  Fleet	
  
        Post-­‐Mining	
  
                             Tons	
  	
  	
  	
  	
  	
  	
  
           Year	
                                               Opera+ng	
  
                          (x	
  1,000)	
                                                  Units	
  
                                                                 Hours	
  
                   1                       28,774                 74,740                  16
                   2                       28,853                 72,439                  16
                   3                       26,409                 64,021                  15
               Total                       84,036                211,201                  16



  Modeling indicates that 16 trucks will be required in the
  first 19 months of the project and 15 for the remainder.

More Related Content

PPT
Transport & digging capacity calculation
PPT
Basic E&Mcalculations for a coal mining project
PPTX
Analysing shovel dumper productivity for coal mine
PPTX
Use of Integrated loader dumper over Shovel dumper combination
PDF
TGS NSA- Freeport 3D
 
PPT
Serecon_Obstruction_Mapper_Examples
PDF
Hydrodynamic Analysis of a Horizontal Axis Marine Current Turbine with a Boun...
PDF
MPCPosterGrinding2
Transport & digging capacity calculation
Basic E&Mcalculations for a coal mining project
Analysing shovel dumper productivity for coal mine
Use of Integrated loader dumper over Shovel dumper combination
TGS NSA- Freeport 3D
 
Serecon_Obstruction_Mapper_Examples
Hydrodynamic Analysis of a Horizontal Axis Marine Current Turbine with a Boun...
MPCPosterGrinding2

What's hot (14)

PDF
Alex Persico Power Point
PDF
Odc tank project bdq to za
PDF
Kaybob 2014 v2
 
DOCX
My contributions to indusries for 39 years
ZIP
Attachments 23 12_2010
PPT
OptiSurface Landforming Technology
PDF
Zonnedaken op bedrijfsgebouwen klimaatplein event
PPT
Blasting inprovement techniques
PPTX
Master Student Presentation in Construction Technology Course
PPTX
2D seismic analysis of Chalk play in the northern Dutch offshore
PPTX
Productivity analysis of Burried/underground cable laying Activity
PPTX
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
PDF
ditching
PDF
Seal-One Cantarell-418
Alex Persico Power Point
Odc tank project bdq to za
Kaybob 2014 v2
 
My contributions to indusries for 39 years
Attachments 23 12_2010
OptiSurface Landforming Technology
Zonnedaken op bedrijfsgebouwen klimaatplein event
Blasting inprovement techniques
Master Student Presentation in Construction Technology Course
2D seismic analysis of Chalk play in the northern Dutch offshore
Productivity analysis of Burried/underground cable laying Activity
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
ditching
Seal-One Cantarell-418
Ad

Viewers also liked (11)

PPT
PDF
Development Length Hook Splice Of Reinforcements
PDF
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
PDF
Design of reinforced concrete as per aci 318
PPTX
F3 Subsoil drainage and installation
PPTX
Reinfocing details of column
PDF
Sp 34-1987 handbook on reinforcement and detailing
PPT
Reinforcement detailing
PPTX
Bar bending schedule(by akhil)
PPTX
Civil Engineering (Beams,Columns)
Development Length Hook Splice Of Reinforcements
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
Design of reinforced concrete as per aci 318
F3 Subsoil drainage and installation
Reinfocing details of column
Sp 34-1987 handbook on reinforcement and detailing
Reinforcement detailing
Bar bending schedule(by akhil)
Civil Engineering (Beams,Columns)
Ad

Similar to Partial Pit Backfill Alternative (6)

PPTX
City Council August 7, 2012 Hickory update & Water Supply Update
PDF
Hard Creek Nickel Investor Presentation
PDF
Petrobras´ Business Plan - At a Glance | CEO José Sergio Gabrielli de Azevedo...
PPTX
Png 492 pec final-presentation[1][1]
PPTX
Png 492 pec final-presentation
PDF
2009 11 11 Byrd A Different Approach To Decom Liability
City Council August 7, 2012 Hickory update & Water Supply Update
Hard Creek Nickel Investor Presentation
Petrobras´ Business Plan - At a Glance | CEO José Sergio Gabrielli de Azevedo...
Png 492 pec final-presentation[1][1]
Png 492 pec final-presentation
2009 11 11 Byrd A Different Approach To Decom Liability

More from Hudbay Minerals Inc. (20)

PDF
Well Protection Program - Groundwater Modeling Presentation
PDF
Rosemont Copper Cooperating Agencies - 2009
PDF
Rosemont Copper - Mining Law of 1872
PDF
Rosemont Copper - Tailings: Reused Mine Rock
PDF
Rosemont Copper Dry Stack Presentation 2009
PDF
Dry Stack Tailings Overview
PDF
Rosemont Reclamation Plan July 2007
PDF
Reclamation Requirements
PDF
Reclamation Examples - Before and After
PDF
Regional Groundwater Flow Models
PDF
Baseline Traffic Study
PDF
Baseline Noise Study
PDF
Heap Leach Facilities
PDF
Geotechnical Study
PDF
Mine Rock Geochemistry and Pit Lake Model
PDF
Rosemont Project Orientation
PDF
Water Supply Plan & Hydrogeology "Westside Presentation"
PDF
Rosemont Project Hydrogeology & Water Supply
PDF
Facilities Engineering Presentation
PDF
Aquifer Protection Permitting: Rosemont Mine
Well Protection Program - Groundwater Modeling Presentation
Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper - Mining Law of 1872
Rosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper Dry Stack Presentation 2009
Dry Stack Tailings Overview
Rosemont Reclamation Plan July 2007
Reclamation Requirements
Reclamation Examples - Before and After
Regional Groundwater Flow Models
Baseline Traffic Study
Baseline Noise Study
Heap Leach Facilities
Geotechnical Study
Mine Rock Geochemistry and Pit Lake Model
Rosemont Project Orientation
Water Supply Plan & Hydrogeology "Westside Presentation"
Rosemont Project Hydrogeology & Water Supply
Facilities Engineering Presentation
Aquifer Protection Permitting: Rosemont Mine

Recently uploaded (20)

PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
advance database management system book.pdf
PPTX
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
PPTX
UNIT III MENTAL HEALTH NURSING ASSESSMENT
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
Hazard Identification & Risk Assessment .pdf
PPTX
Lesson notes of climatology university.
PDF
RMMM.pdf make it easy to upload and study
LDMMIA Reiki Yoga Finals Review Spring Summer
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
Computing-Curriculum for Schools in Ghana
Final Presentation General Medicine 03-08-2024.pptx
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
advance database management system book.pdf
UV-Visible spectroscopy..pptx UV-Visible Spectroscopy – Electronic Transition...
UNIT III MENTAL HEALTH NURSING ASSESSMENT
Weekly quiz Compilation Jan -July 25.pdf
What if we spent less time fighting change, and more time building what’s rig...
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
Hazard Identification & Risk Assessment .pdf
Lesson notes of climatology university.
RMMM.pdf make it easy to upload and study

Partial Pit Backfill Alternative

  • 1. Partial Backfill Alternative January 21, 2010 Cooperator’s Meeting Presentation
  • 2. Partial Backfill Alternative Considerations •  Be responsive to an Issue •  Minimize water that collects in the pit •  Return waste rock to the pit •  Minimize resources that are used in backfilling •  Minimize air impacts
  • 3. Partial Backfill Alternative Environmental Considerations •  Compliance with all applicable regulations including ADEQ BADCT and air regulations •  Maintain a Hydraulic Sink •  Geochemical considerations with the addition of a mix of finer grained materials •  Stormwater controls during backfill •  Effect on concurrent reclamation and on reclamation planning
  • 5. Hydrogeologic Study Results Pit Lake Pit Lake Depth Period Elevation (feet) (ft amsl) Mine Closure (None) 0 Closure + 20 years 3,591 541 Closure + 50 years 3,751 701 Closure + 100 years 3,869 819 •  Backfill elevation – 3825 ft amsl (est.) •  Elevation was estimated to maintain sink (modeling to confirm elevation estimation with operational adjustments as necessary)
  • 6. Other Considerations •  Heap Leach remains undisturbed •  Haulage fleet used will be consistent in size to current fleet •  Loading equipment (shovel used will be consistent with current loading equipment) •  Waste rock density is 11.95 ft3/ton •  Swell factor for the rock is 1.3
  • 7. Other Considerations •  Amount of material necessary for backfill is 90 million tons (46 million cubic yards) •  Allowance of 5% added for construction of ramps for downhill haulage •  Total material rehandled 94 million tons •  36-months required to complete backfill •  Hauls will incorporate 3 switchbacks at -10% grade at a maximum 13 mph
  • 8. Backfill and Excavation Area •  Excavation on 50 foot benches •  Start elevation approx 5429 ft amsl •  Final elevation 5200 ft amsl •  Dumped into pit from 3825 ft elevation
  • 9. Productivity by Bench Bench   Tonnage         Cumula+ve   Haulage   Eleva+on         (x  1,000)   Tonnage               Produc+on       (.  amsl)   (x  1,000)   (tons/hour)   5420 8,938 8,938 379 5400 18,435 27,373 387 5350 18,689 46,062 395 5300 16,277 62,338 403 5250 12,977 75,315 411 5200 8,720 84,036 419 This information was used to determine the appropriate haulage fleet for this activity matched to one shovel.
  • 10. Required Haulage Hours and Units Rehandle   CAT  793C  Truck  Fleet   Post-­‐Mining   Tons               Year   Opera+ng   (x  1,000)   Units   Hours   1 28,774 74,740 16 2 28,853 72,439 16 3 26,409 64,021 15 Total 84,036 211,201 16 Modeling indicates that 16 trucks will be required in the first 19 months of the project and 15 for the remainder.