PILE LOAD TEST
Load Test on Piles – Methods of Pile Load Test
Prepared By: Dharmendra Singh
 Load tests on piles are conducted on completion of 28 days after casting
of piles.
 Two types of tests namely initial and routine tests, for each type of
loading viz. vertical, horizontal (lateral) pull out, are performed on piles.
 Initial Load Tests on Piles
• This test is performed to confirm the design load calculations and to
provide guidelines for setting up the limits of acceptance for routine
tests. It also gives an idea of the suitability of the piling system. Initial
Test on piles are to be carried out at one or more locations depending
on the number of piles required.
•
Load applied for the initial (cyclic) load test is 2.5 times the safe
carrying capacity of the pile. Loading for Initial Tests is conducted as
per Appendix ‘A’ Clause 6.3 of IS-2911 Part IV.
 Routine Load Tests on Piles
• Selection of piles for the Routine Test is done based on number of piles required
subject to maximum of ½% of total number of piles required. The number of
tests may be increased to 2% depending on the nature / type of structure. The
test load applied is 1½ times the safe carrying capacity of the pile.
• he Maintained load method as described in Clause 6.2 of IS-2911 (Part IV) – 1985
shall be followed for loading for the Routine Tests.
• This test will be performed for the following purposes:
• a) To ensure the safe load capacity of piles
• b) Detection of any unusual performance contrary to the findings of the Initial
Test.
• The tests shall be performed at the cut-off level only. A detailed report for the test
result is prepared.
 Vertical Load Tests on Piles
• This test will be carried out as stipulated in IS-2911 (Part IV)
1995.
 Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable.
The reinforcement shall be cut and head levelled with Plaster of Paris. A bearing plate with a
hole shall be placed on the head for the jack to rest.
 Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor
piles (if required) shall be placed at a center to center distance of 3 times the pile diameter
subject to a minimum distance of 2 M.
 Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm
sensitivity shall be used. They shall be positioned at equal distance around the piles on datum
bars resting on immovable supports at a distance of 3D (min. of 1.5 m) where D is the diameter
of pile or circumscribing circle for non-circular piles.
 Application of load- It shall be applied as specified depending on the type of test (routine /
initial). Each load shall be maintained till the rate of displacement of the pile top is either 0.1
mm in the first 30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The
next increment in the load shall be applied on achieving the aforesaid criterion.
The test load shall be maintained for 24 hours.
 Initial Tests– The safe load on a single pile shall be the least of the following:
(i) 2/3rd of the final load at which the total displacement attains a value of 12 mm unless
otherwise required in a given case on the basis of nature and type of structure in which
case, the safe load should be corresponding to the stated total displacement permissible.
(ii) 50% of the final load at which the total displacement equals 10% of the pile diameter in
case of uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles.
Routine Tests – Acceptance
The maximum settlement at test load should not exceed 12 mm.
 Lateral Load Tests on Piles
 The jack should be placed horizontally, between two piles. The load on the jack shall be the
same on both the piles. The load will be applied in increments of 20% of the estimated safe
load and at the cut off level. The load will be increased after the rate of displacement is
nearer to 0.1 mm per 30 minutes.
 If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall measure
the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm apart
vertically, shall be set up and the lateral displacement of the cut-off level calculated by similar
triangles.
 The safe load on the pile shall be the least of the following:
a) 50% of the final load at which the total displacement increases to 12 mm.
b) Final load at which the total displacement corresponds to 5 mm.
*Thank You*

More Related Content

PPTX
Pile load test
PPTX
Plate load test
PPTX
Health care reforms
PDF
Plaxis 3d tutorial manual
PPTX
Environment impact assessment
PDF
Supervision of piling works, ACES, 2011, Singapore
PPTX
use of blast furnace slag in road construction.ppt
PPT
High performance concrete ppt
Pile load test
Plate load test
Health care reforms
Plaxis 3d tutorial manual
Environment impact assessment
Supervision of piling works, ACES, 2011, Singapore
use of blast furnace slag in road construction.ppt
High performance concrete ppt

What's hot (20)

PDF
Bearing capacity of shallow foundations by abhishek sharma
PPT
Construction of diaphragm wall
PPTX
Types of joints in rigid pavement
PPTX
Pile foundation
PPT
Standard Penetration Test
PPTX
Sheet pile presentation
PPTX
Bridge foundation
PPTX
Expansive soil
PPTX
Cbr test
PPT
Stone columns - an overview(Ground improvement)
PDF
Plate load test
PPTX
Rcc design by working stress method
PPT
Flexible and-rigid-pavements
PPT
Pile foundation ppt 2 (usefulsearch.org) (useful search)
PDF
Pile Foundations
PPTX
Consolidation settlement
PPT
Sinking of well foundation
PPTX
Standard Penetration Test
PPT
TYPES OF PILE FOUNDATION & APPLICATIONS
PPTX
Earth pressure
Bearing capacity of shallow foundations by abhishek sharma
Construction of diaphragm wall
Types of joints in rigid pavement
Pile foundation
Standard Penetration Test
Sheet pile presentation
Bridge foundation
Expansive soil
Cbr test
Stone columns - an overview(Ground improvement)
Plate load test
Rcc design by working stress method
Flexible and-rigid-pavements
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile Foundations
Consolidation settlement
Sinking of well foundation
Standard Penetration Test
TYPES OF PILE FOUNDATION & APPLICATIONS
Earth pressure
Ad

Similar to Pile load test ppt (20)

PPT
METHOD AND ASSESSMENT FOR LOAD TEST.ppt
PPTX
ASTM E 09(COMPRESSION TEST)
PPTX
Unit II: Design of Static Equipment Foundations
PPTX
PILE LOAD TEST-abhishek.pptx
PDF
Astm d2938 unconfined compressive strength
PDF
publication_1580218342.pdf
PDF
178749411 astm-d-1633-00-standard-methods-for-compressive-strength-of-molded-...
PDF
A triaxial test is a laboratory procedure
DOCX
4-pile foundation.docx pile foundation.docx
PPTX
Plate load test and its interpretations
PDF
D1004.pdf
PPTX
California bearingratio test
PPTX
Compression_Flexural_and_Tensile_tests.pptx
DOCX
Tri axial test
PPTX
DETERMINATION OF UNCONFINED COMPRESSIVE STRENGTH OF SOIL
PPTX
PILE FOUNDATION.pptx
METHOD AND ASSESSMENT FOR LOAD TEST.ppt
ASTM E 09(COMPRESSION TEST)
Unit II: Design of Static Equipment Foundations
PILE LOAD TEST-abhishek.pptx
Astm d2938 unconfined compressive strength
publication_1580218342.pdf
178749411 astm-d-1633-00-standard-methods-for-compressive-strength-of-molded-...
A triaxial test is a laboratory procedure
4-pile foundation.docx pile foundation.docx
Plate load test and its interpretations
D1004.pdf
California bearingratio test
Compression_Flexural_and_Tensile_tests.pptx
Tri axial test
DETERMINATION OF UNCONFINED COMPRESSIVE STRENGTH OF SOIL
PILE FOUNDATION.pptx
Ad

Recently uploaded (20)

PDF
PPT on Performance Review to get promotions
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPTX
Geodesy 1.pptx...............................................
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Sustainable Sites - Green Building Construction
PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
web development for engineering and engineering
PPTX
CH1 Production IntroductoryConcepts.pptx
PPT on Performance Review to get promotions
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Geodesy 1.pptx...............................................
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Sustainable Sites - Green Building Construction
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
UNIT 4 Total Quality Management .pptx
web development for engineering and engineering
CH1 Production IntroductoryConcepts.pptx

Pile load test ppt

  • 1. PILE LOAD TEST Load Test on Piles – Methods of Pile Load Test Prepared By: Dharmendra Singh
  • 2.  Load tests on piles are conducted on completion of 28 days after casting of piles.  Two types of tests namely initial and routine tests, for each type of loading viz. vertical, horizontal (lateral) pull out, are performed on piles.
  • 3.  Initial Load Tests on Piles • This test is performed to confirm the design load calculations and to provide guidelines for setting up the limits of acceptance for routine tests. It also gives an idea of the suitability of the piling system. Initial Test on piles are to be carried out at one or more locations depending on the number of piles required. • Load applied for the initial (cyclic) load test is 2.5 times the safe carrying capacity of the pile. Loading for Initial Tests is conducted as per Appendix ‘A’ Clause 6.3 of IS-2911 Part IV.
  • 4.  Routine Load Tests on Piles • Selection of piles for the Routine Test is done based on number of piles required subject to maximum of ½% of total number of piles required. The number of tests may be increased to 2% depending on the nature / type of structure. The test load applied is 1½ times the safe carrying capacity of the pile. • he Maintained load method as described in Clause 6.2 of IS-2911 (Part IV) – 1985 shall be followed for loading for the Routine Tests. • This test will be performed for the following purposes: • a) To ensure the safe load capacity of piles • b) Detection of any unusual performance contrary to the findings of the Initial Test. • The tests shall be performed at the cut-off level only. A detailed report for the test result is prepared.
  • 5.  Vertical Load Tests on Piles • This test will be carried out as stipulated in IS-2911 (Part IV) 1995.
  • 6.  Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable. The reinforcement shall be cut and head levelled with Plaster of Paris. A bearing plate with a hole shall be placed on the head for the jack to rest.  Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor piles (if required) shall be placed at a center to center distance of 3 times the pile diameter subject to a minimum distance of 2 M.  Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm sensitivity shall be used. They shall be positioned at equal distance around the piles on datum bars resting on immovable supports at a distance of 3D (min. of 1.5 m) where D is the diameter of pile or circumscribing circle for non-circular piles.  Application of load- It shall be applied as specified depending on the type of test (routine / initial). Each load shall be maintained till the rate of displacement of the pile top is either 0.1 mm in the first 30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The next increment in the load shall be applied on achieving the aforesaid criterion.
  • 7. The test load shall be maintained for 24 hours.  Initial Tests– The safe load on a single pile shall be the least of the following: (i) 2/3rd of the final load at which the total displacement attains a value of 12 mm unless otherwise required in a given case on the basis of nature and type of structure in which case, the safe load should be corresponding to the stated total displacement permissible. (ii) 50% of the final load at which the total displacement equals 10% of the pile diameter in case of uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles. Routine Tests – Acceptance The maximum settlement at test load should not exceed 12 mm.
  • 8.  Lateral Load Tests on Piles
  • 9.  The jack should be placed horizontally, between two piles. The load on the jack shall be the same on both the piles. The load will be applied in increments of 20% of the estimated safe load and at the cut off level. The load will be increased after the rate of displacement is nearer to 0.1 mm per 30 minutes.  If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall measure the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm apart vertically, shall be set up and the lateral displacement of the cut-off level calculated by similar triangles.  The safe load on the pile shall be the least of the following: a) 50% of the final load at which the total displacement increases to 12 mm. b) Final load at which the total displacement corresponds to 5 mm.