PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
1
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS
BASED ON DATA/INFORMATION GATHERED FROM VARIOUS
RELIABLE SOURCES. NONE OF THIS DATA/INFORMATION IS A
PROPERTY OF THE AUTHOR. NONE IS INTENDED TO MAKE A
PROFIT IN ANY WAY. THIS IS FOR PERSONAL USE ONLY.
PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
2
No great man ever complains of want of opportunity.
Ralph Waldo Emerson
PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
3
Table of Contents
Appendix H – Formula Sheet ................................................................................................................................. 4
Project Selection Methods ................................................................................................................................. 4
Depreciation ..................................................................................................................................................... 4
Planned Value .................................................................................................................................................. 4
Other Methods.................................................................................................................................................. 5
Schedule Management ..................................................................................................................................... 5
Cost Management .............................................................................................................................................. 5
Earned Value Management (EVM).............................................................................................................. 5
Communication ................................................................................................................................................... 8
Risk Management ................................................................................................................................................ 8
Procurements........................................................................................................................................................ 8
Estimates ................................................................................................................................................................ 9
PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
4
Project Selection Methods
Depreciation
Straight Line
Depreciation
The same amount of
depreciation is taken each
year.
Amt =
total
year count
Double Declining
Balance
Percentage is double the
straight line depreciation
Sum of Years Digits
(SYD)
𝑺𝒀𝑫 =
𝒏 (𝒏 + 𝟏)
𝟐
= 𝟓𝒚𝒆𝒂𝒓𝒔 =
𝟓(𝟓 + 𝟏)
𝟐
= 𝟏𝟓
𝑬𝒙𝒑𝒆𝒏𝒔𝒆 =
𝑹𝒆𝒎𝒂𝒊𝒏𝒊𝒏𝒈 𝒍𝒊𝒇𝒆
𝒔𝒖𝒎 𝒐𝒇 𝒚𝒆𝒂𝒓𝒔 𝒅𝒊𝒈𝒊𝒕
∗ 𝑫𝒆𝒑𝒓𝒆𝒄𝒊𝒂𝒃𝒍𝒆 𝑪𝒐𝒔𝒕
Planned Value
Future Value (FV) To determine the future
value of present money.
𝑭𝑽 = 𝑷𝑽 (𝟏 + 𝒊) 𝒏
PV = Present value
i = interest rate
n = number of periods
Present Value (PV) The current worth of a
future sum of money given
a specific rate of return.
𝑷𝑽 =
𝑭𝑽
(𝟏 + 𝒊) 𝒏
FV = Future value
i = interest rate
n = number of periods
Net Present Value
(NPV) / Net Present
Worth (NPW)
The difference between
the project’s current value
of cash inflow and the
current value of cash
outflow over many time
periods. The NPV must
always be positive. When
picking a project, one with
a higher NPV is preferred.
𝑵𝑷𝑽 = −𝑪 𝟎 + ∑
𝑪𝒕
(𝟏 + 𝒓) 𝒕
𝑻
𝒕=𝟏
Simplified –
𝑵𝑷𝑽 = −𝑪 𝟎 +
𝑪 𝟏
𝟏 + 𝒓
+
𝑪 𝟐
(𝟏 + 𝒓) 𝟐
+ ⋯ +
𝑪 𝑻
(𝟏 + 𝒓) 𝑻
-C0 = Initial investment
C = Future cash flow
PM NOTEBOOK APPENDIX H – FORMULA SHEET | SCHEDULE MANAGEMENT
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
5
r = Interest rate
T = Time period
Other Methods
Return on Investment
(ROI)
Measures the gain or loss
generated on an
investment relative to the
amount of money
invested. ROI is usually
expressed as a
percentage and is
typically used for personal
financial decisions, to
compare a company's
profitability or to compare
the efficiency of different
investments.
𝑹𝑶𝑰 =
𝑵𝒆𝒕 𝑷𝒓𝒐𝒇𝒊𝒕 (𝑹𝒆𝒕𝒖𝒓𝒏)
𝑰𝒏𝒗𝒆𝒔𝒕𝒎𝒆𝒏𝒕 (𝑪𝒐𝒔𝒕)
Schedule Management
Crashing Slope The cost per day of
crashing the project.
𝑪𝒓𝒂𝒔𝒉 𝑪𝒐𝒔𝒕 (𝑪𝑪) − 𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕 (𝑵𝑪)
𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵𝑫) − 𝑪𝒓𝒂𝒔𝒉 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪𝑫)
Cost Management
Earned Value Management (EVM)
BAC (Budget at
Completion)
Total project budget.
Planned % Complete How much percentage of
the work you should have
done according to
schedule.
Actual % Complete How much percentage of
the work you have
actually done.
PV (Planned Value) /
BCWS (Budgeted
Cost for Work
Scheduled).
The budgeted value of the
work completed.
PV = BAC ∗ Plan % Compl
PM NOTEBOOK APPENDIX H – FORMULA SHEET | COST MANAGEMENT
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
6
EV (Earned Value) /
BCWP (Budgeted
Cost for Work
Performed).
The actual value of the
work completed.
EV = BAC ∗ Actual % Compl
EV = CV + AC
EV = SV + PV
EV = CPI ∗ AC
EV = SPI ∗ PV
AC (Actual Cost) /
ACWP (Actual Cost
for Work Performed)
Total expenditure (money
spent) for the work.
SPI (Schedule
Performance Index)
Ratio reflects whether the
project work is ahead of (>
1.0) / on / behind (< 1.0)
schedule. Cumulative.
SPI = EV / PV
SV (Schedule
Variance)
How much time ahead of
(positive) / behind
(negative) schedule.
SV = EV – PV
CPI (Cost
Performance Index)
Ratio reflects whether the
project work is over (< 1.0)
of / on / under budget (>
1.0). Cumulative. It
measures how much
dollars you get for each
dollar spent.
Researchers have found
that the cumulative CPI
does not change by more
than 10% once a project is
approximately 20%
complete.
CPI = EV / AC
CV (Cost Variance) How much $ under
(positive) / over (negative)
budget.
CV = EV – AC
PM NOTEBOOK APPENDIX H – FORMULA SHEET | COST MANAGEMENT
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
7
EAC (Estimate at
Completion)
Estimates the planned cost
at project finish.
If no variances or you will continue at the
same rate of spending (when current
variances are seen as regular/typical of the
future) –
𝑬𝑨𝑪 = 𝑩𝑨𝑪 / 𝑪𝑷𝑰
Original rate calculation. I.e. when variances
are irregular/atypical (when there are
variances but the rest of the project will
continue at the normal behavior) –
𝑬𝑨𝑪 = 𝑨𝑪 + ( 𝑩𝑨𝑪 – 𝑬𝑽)
Or
𝑬𝑨𝑪 = 𝑩𝑨𝑪 − 𝑪𝑽
Considering SPI and CPI (when variances are
regular/typical) –
𝑬𝑨𝑪 = 𝑨𝑪 +
(𝑩𝑨𝑪 − 𝑬𝑽)
(𝑺𝑷𝑰 ∗ 𝑪𝑷𝑰)
New rate or the original rate was
fundamentally flawed –
EAC = AC + New Estimate
ETC (Estimate to
Complete)
Estimates the additional
cost needed for the
project finish.
ETC = EAC – AC
VAC (Variance at
Completion)
Estimates the difference
between EAC and original
planned value.
VAC = BAC – EAC
TCPI (To-Complete
Performance Index)
Ratio estimates efficiency
needed to finish the
project on budget.
Higher value means
stricter cost management.
Budget-based (when we need project to get
back to budget) –
𝑻𝑪𝑷𝑰 =
(𝑩𝑨𝑪 − 𝑬𝑽)
(𝑩𝑨𝑪 − 𝑨𝑪)
Estimation-based (to meet the new estimate)
–
PM NOTEBOOK APPENDIX H – FORMULA SHEET | COMMUNICATION
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
8
𝑻𝑪𝑷𝑰 =
(𝑩𝑨𝑪 − 𝑬𝑽)
(𝑬𝑨𝑪 − 𝑨𝑪)
Project Variance The final variance, which is
discovered only at the
project’s completion.
𝑽𝑨𝑹 = 𝑩𝑨𝑪 − 𝑨𝑪
Communication
Lines/Channels of
Communication
# Lines for n People =
n ∗ (n − 1)
2
Risk Management
Expected Monetary
Value (EMV)
EVM lets you examine
costs of all the paths you
might take through the
project and assign
monetary value to each
decision. Implies decision
tree analysis.
𝑬𝒙$𝑽 = ∑ 𝑽𝒊 𝑷𝒊
𝒏
𝒊=𝟏
Vi = The monetary value of event i.
Pi = Probability of occurrence of event i.
Procurements
Make-or-Buy
Analysis
The following formula can
be used to get how long
will it take for the lease
cost to be the same as the
purchase cost.
𝒎𝒐𝒏𝒕𝒉 𝒄𝒐𝒖𝒏𝒕
= 𝒂𝒃𝒔(
𝒃𝒖𝒊𝒍𝒅 𝒄𝒐𝒔𝒕𝒔 − 𝒃𝒖𝒚 𝒄𝒐𝒔𝒕𝒔
𝒃𝒖𝒊𝒍𝒅 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 − 𝒃𝒖𝒚 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔
)
Same formula can be represented in another
way –
𝒃𝒖𝒊𝒍𝒅 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 ∗ 𝒎𝒕𝒉 𝒄𝒏𝒕
= 𝒃𝒖𝒚 𝒄𝒐𝒔𝒕𝒔 + 𝒃𝒖𝒚 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔
∗ 𝒎𝒕𝒉 𝒄𝒏𝒕
Point of Total
Assumption (PTA)
PTA is the point on the cost
line of profit-cost curve
determined by contract
elements associated with
a fixed price incentive
contract, above which the
seller effectively bears all
the costs of a cost overrun.
𝑷𝑻𝑨 =
(𝑪𝒆𝒊𝒍𝒊𝒏𝒈 𝑷𝒓𝒊𝒄𝒆 − 𝑻𝒂𝒓𝒈𝒆𝒕 𝑷𝒓𝒊𝒄𝒆)
𝑩𝒖𝒚𝒆𝒓′ 𝒔 𝑺𝒉𝒂𝒓𝒆 𝑹𝒂𝒕𝒊𝒐
+ 𝑻𝒂𝒓𝒈𝒆𝒕 𝑪𝒐𝒔𝒕
PM NOTEBOOK APPENDIX H – FORMULA SHEET | ESTIMATES
DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION
GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY
OF THE AUTHOR.
9
Estimates
Simple/Triangular
Distribution
ESA =
(O + P + M)
3
Beta/PERT Estimate
Σ =
(O + P + 4M)
6
Beta Standard
Deviation / Sigma
σ =
(P − O)
6
Beta Variance
VARPERT = σ2
= (
(P − O)
6
)
2

More Related Content

PDF
PM Notebook - Appendix C - Data Representation Tools
PDF
PM Notebook - Appendix E - Estimating Techniques
PDF
PM Notebook - Appendix F - Forecasting Methods
PDF
PM Notebook - Chapter 12 - Procurement Management
PDF
PM Notebook
PDF
PM Notebook - Appendix B - Data Gathering Techniques
PDF
PM Notebook - Chapter 13 - Stakeholder Management
DOCX
Project selection and estimating technique spencer o’briencpmgt303
PM Notebook - Appendix C - Data Representation Tools
PM Notebook - Appendix E - Estimating Techniques
PM Notebook - Appendix F - Forecasting Methods
PM Notebook - Chapter 12 - Procurement Management
PM Notebook
PM Notebook - Appendix B - Data Gathering Techniques
PM Notebook - Chapter 13 - Stakeholder Management
Project selection and estimating technique spencer o’briencpmgt303

What's hot (20)

PPTX
Measurements Methods of forecasting errors
PPTX
Demand forecasting
PPTX
FORECASTING
PPT
Forecasting model 15 04-31
PPTX
ForecastIT 1. Introduction to Forecasting
PPT
Forecasting Techniques
PPT
Quantitative methods of demand forecasting
PPT
M&l case
PDF
What Are Common Forecasting Techniques
PPTX
Operations management forecasting
PPT
Forecasting
PPTX
FORECASTING MODELS
PPTX
PM685 - Kwon
PPT
Using Financial Forecasts to Advise Business - Method of Forecasting - Revised
PPTX
Introduction to Statistics
PPSX
Quantitative and qualitative forecasting techniques om
PPTX
Mba ii pmom_unit-1.3 forecasting a
PPSX
Forecasting
PPTX
forecasting
PPTX
Forecasting Models & Their Applications
Measurements Methods of forecasting errors
Demand forecasting
FORECASTING
Forecasting model 15 04-31
ForecastIT 1. Introduction to Forecasting
Forecasting Techniques
Quantitative methods of demand forecasting
M&l case
What Are Common Forecasting Techniques
Operations management forecasting
Forecasting
FORECASTING MODELS
PM685 - Kwon
Using Financial Forecasts to Advise Business - Method of Forecasting - Revised
Introduction to Statistics
Quantitative and qualitative forecasting techniques om
Mba ii pmom_unit-1.3 forecasting a
Forecasting
forecasting
Forecasting Models & Their Applications
Ad

Similar to PM Notebook - Appendix H - Formula Sheet (20)

PPTX
Project Cost Management
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPTX
Earned value for pmp and pmi acp exam
PDF
Project monitoring and controlling with earned value management
PPTX
Projects Control Using Earned Value Techniques - Part One
PPTX
project control using earned value analysis - Part 01
PPTX
PMP Training - 07 project cost management
PPTX
A simple approach to understanding Earned Value Management
PPTX
07 projectcostmanagement
PPTX
Earned Value Analysis
PPTX
6- PMP Training - Cost Management
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPTX
Earned value management (EVM)
PPTX
PMP COST FORMULAE
PPT
Module 06 Adv PM Budget Mgmt.ppt
PPT
Module 06 Adv Project Manager Budget Mgmt.ppt
PDF
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PPT
cost-managementtttttttttttttttttttttttttttttt.ppt
PPTX
Project monitoring & Earned Value Analysis
Project Cost Management
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Earned value for pmp and pmi acp exam
Project monitoring and controlling with earned value management
Projects Control Using Earned Value Techniques - Part One
project control using earned value analysis - Part 01
PMP Training - 07 project cost management
A simple approach to understanding Earned Value Management
07 projectcostmanagement
Earned Value Analysis
6- PMP Training - Cost Management
Earned Value AnalysisTracking Project ProgressWh.docx
Earned value management (EVM)
PMP COST FORMULAE
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
PM - EVM - Dr Najam Abbas - OHT 1.pdf
cost-managementtttttttttttttttttttttttttttttt.ppt
Project monitoring & Earned Value Analysis
Ad

More from Mohammad Elsheimy (18)

PDF
Mohammad Elsheimy - Solution Developer (CV)
PDF
PM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PDF
PM Notebook - Appendix D - Decision-Making Techniques
PDF
PM Notebook - Chapter 14 - Professional and Social Responsibility
PDF
PM Notebook - Chapter 11: Risk Management
PDF
PM Notebook - Chapter 10: Communication Management
PDF
PM Notebook - Chapter 9: Resources Management
PDF
PM Notebook - Chapter 8: Quality Management
PDF
PM Notebook - Chapter 7 - Cost Management
PDF
PM Notebook - Chapter 6 - Schedule Management
PDF
PM Notebook - Chapter 5 - Scope Management
PDF
PM Notebook - Chapter 4: Integration Management
PDF
PM Notebook - Chapter 3: The Process Framework
PDF
PM Notebook - Chapter 2: Organizations
PDF
PM Notebook - Chapter 1: Introduction
PPTX
What's New in Silverlight 5
PPTX
Microsoft Silverlight - An Introduction
PDF
Marshaling with C# Pocket Reference
Mohammad Elsheimy - Solution Developer (CV)
PM Notebook - Appendix G - Interpersonal/Team/Soft Skills
PM Notebook - Appendix D - Decision-Making Techniques
PM Notebook - Chapter 14 - Professional and Social Responsibility
PM Notebook - Chapter 11: Risk Management
PM Notebook - Chapter 10: Communication Management
PM Notebook - Chapter 9: Resources Management
PM Notebook - Chapter 8: Quality Management
PM Notebook - Chapter 7 - Cost Management
PM Notebook - Chapter 6 - Schedule Management
PM Notebook - Chapter 5 - Scope Management
PM Notebook - Chapter 4: Integration Management
PM Notebook - Chapter 3: The Process Framework
PM Notebook - Chapter 2: Organizations
PM Notebook - Chapter 1: Introduction
What's New in Silverlight 5
Microsoft Silverlight - An Introduction
Marshaling with C# Pocket Reference

Recently uploaded (20)

PDF
The Plan: Save the Palestinian Nation Now
PPTX
Strategic Plan 2023-2024 Presentation.pptx
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PPTX
Consulting on marketing-The needs wants and demands are a very important comp...
PDF
CISSP Domain 5: Identity and Access Management (IAM)
PPTX
Five S Training Program - Principles of 5S
PDF
The Cyber SwarmShield by Stéphane Nappo
PDF
Features of Effective decision making in Management
PDF
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
PPTX
Course Overview of the Course Titled.pptx
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PDF
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PPTX
MY GOLDEN RULES la regla de oro jhonatan requena
PDF
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PPTX
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
PPTX
Chapter Three for international political
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PDF
Human resources management is a best management
The Plan: Save the Palestinian Nation Now
Strategic Plan 2023-2024 Presentation.pptx
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
Consulting on marketing-The needs wants and demands are a very important comp...
CISSP Domain 5: Identity and Access Management (IAM)
Five S Training Program - Principles of 5S
The Cyber SwarmShield by Stéphane Nappo
Features of Effective decision making in Management
Air India AI-171 Crash in Ahmedabad A Tragic Wake-Up Call.
Course Overview of the Course Titled.pptx
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
MANAGEMENT LESSONS FROM ANCIENT KNOWLEDGE SYSTEM-ARTHASHASTRA AND THIRUKKURAL...
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
MY GOLDEN RULES la regla de oro jhonatan requena
Equity at the Helm_ Guiding Schools Through Inclusive Leadership by Dr.pdf
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
Chapter Three for international political
_ISO_Presentation_ISO 9001 and 45001.pptx
Human resources management is a best management

PM Notebook - Appendix H - Formula Sheet

  • 1. PM Notebook Summarizing Project Management Concepts for the PMP Exam Mohammad Elsheimy Road to PMP
  • 2. PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 1 DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA/INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA/INFORMATION IS A PROPERTY OF THE AUTHOR. NONE IS INTENDED TO MAKE A PROFIT IN ANY WAY. THIS IS FOR PERSONAL USE ONLY.
  • 3. PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 2 No great man ever complains of want of opportunity. Ralph Waldo Emerson
  • 4. PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 3 Table of Contents Appendix H – Formula Sheet ................................................................................................................................. 4 Project Selection Methods ................................................................................................................................. 4 Depreciation ..................................................................................................................................................... 4 Planned Value .................................................................................................................................................. 4 Other Methods.................................................................................................................................................. 5 Schedule Management ..................................................................................................................................... 5 Cost Management .............................................................................................................................................. 5 Earned Value Management (EVM).............................................................................................................. 5 Communication ................................................................................................................................................... 8 Risk Management ................................................................................................................................................ 8 Procurements........................................................................................................................................................ 8 Estimates ................................................................................................................................................................ 9
  • 5. PM NOTEBOOK APPENDIX H – FORMULA SHEET | PROJECT SELECTION METHODS DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 4 Project Selection Methods Depreciation Straight Line Depreciation The same amount of depreciation is taken each year. Amt = total year count Double Declining Balance Percentage is double the straight line depreciation Sum of Years Digits (SYD) 𝑺𝒀𝑫 = 𝒏 (𝒏 + 𝟏) 𝟐 = 𝟓𝒚𝒆𝒂𝒓𝒔 = 𝟓(𝟓 + 𝟏) 𝟐 = 𝟏𝟓 𝑬𝒙𝒑𝒆𝒏𝒔𝒆 = 𝑹𝒆𝒎𝒂𝒊𝒏𝒊𝒏𝒈 𝒍𝒊𝒇𝒆 𝒔𝒖𝒎 𝒐𝒇 𝒚𝒆𝒂𝒓𝒔 𝒅𝒊𝒈𝒊𝒕 ∗ 𝑫𝒆𝒑𝒓𝒆𝒄𝒊𝒂𝒃𝒍𝒆 𝑪𝒐𝒔𝒕 Planned Value Future Value (FV) To determine the future value of present money. 𝑭𝑽 = 𝑷𝑽 (𝟏 + 𝒊) 𝒏 PV = Present value i = interest rate n = number of periods Present Value (PV) The current worth of a future sum of money given a specific rate of return. 𝑷𝑽 = 𝑭𝑽 (𝟏 + 𝒊) 𝒏 FV = Future value i = interest rate n = number of periods Net Present Value (NPV) / Net Present Worth (NPW) The difference between the project’s current value of cash inflow and the current value of cash outflow over many time periods. The NPV must always be positive. When picking a project, one with a higher NPV is preferred. 𝑵𝑷𝑽 = −𝑪 𝟎 + ∑ 𝑪𝒕 (𝟏 + 𝒓) 𝒕 𝑻 𝒕=𝟏 Simplified – 𝑵𝑷𝑽 = −𝑪 𝟎 + 𝑪 𝟏 𝟏 + 𝒓 + 𝑪 𝟐 (𝟏 + 𝒓) 𝟐 + ⋯ + 𝑪 𝑻 (𝟏 + 𝒓) 𝑻 -C0 = Initial investment C = Future cash flow
  • 6. PM NOTEBOOK APPENDIX H – FORMULA SHEET | SCHEDULE MANAGEMENT DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 5 r = Interest rate T = Time period Other Methods Return on Investment (ROI) Measures the gain or loss generated on an investment relative to the amount of money invested. ROI is usually expressed as a percentage and is typically used for personal financial decisions, to compare a company's profitability or to compare the efficiency of different investments. 𝑹𝑶𝑰 = 𝑵𝒆𝒕 𝑷𝒓𝒐𝒇𝒊𝒕 (𝑹𝒆𝒕𝒖𝒓𝒏) 𝑰𝒏𝒗𝒆𝒔𝒕𝒎𝒆𝒏𝒕 (𝑪𝒐𝒔𝒕) Schedule Management Crashing Slope The cost per day of crashing the project. 𝑪𝒓𝒂𝒔𝒉 𝑪𝒐𝒔𝒕 (𝑪𝑪) − 𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕 (𝑵𝑪) 𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵𝑫) − 𝑪𝒓𝒂𝒔𝒉 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪𝑫) Cost Management Earned Value Management (EVM) BAC (Budget at Completion) Total project budget. Planned % Complete How much percentage of the work you should have done according to schedule. Actual % Complete How much percentage of the work you have actually done. PV (Planned Value) / BCWS (Budgeted Cost for Work Scheduled). The budgeted value of the work completed. PV = BAC ∗ Plan % Compl
  • 7. PM NOTEBOOK APPENDIX H – FORMULA SHEET | COST MANAGEMENT DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 6 EV (Earned Value) / BCWP (Budgeted Cost for Work Performed). The actual value of the work completed. EV = BAC ∗ Actual % Compl EV = CV + AC EV = SV + PV EV = CPI ∗ AC EV = SPI ∗ PV AC (Actual Cost) / ACWP (Actual Cost for Work Performed) Total expenditure (money spent) for the work. SPI (Schedule Performance Index) Ratio reflects whether the project work is ahead of (> 1.0) / on / behind (< 1.0) schedule. Cumulative. SPI = EV / PV SV (Schedule Variance) How much time ahead of (positive) / behind (negative) schedule. SV = EV – PV CPI (Cost Performance Index) Ratio reflects whether the project work is over (< 1.0) of / on / under budget (> 1.0). Cumulative. It measures how much dollars you get for each dollar spent. Researchers have found that the cumulative CPI does not change by more than 10% once a project is approximately 20% complete. CPI = EV / AC CV (Cost Variance) How much $ under (positive) / over (negative) budget. CV = EV – AC
  • 8. PM NOTEBOOK APPENDIX H – FORMULA SHEET | COST MANAGEMENT DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 7 EAC (Estimate at Completion) Estimates the planned cost at project finish. If no variances or you will continue at the same rate of spending (when current variances are seen as regular/typical of the future) – 𝑬𝑨𝑪 = 𝑩𝑨𝑪 / 𝑪𝑷𝑰 Original rate calculation. I.e. when variances are irregular/atypical (when there are variances but the rest of the project will continue at the normal behavior) – 𝑬𝑨𝑪 = 𝑨𝑪 + ( 𝑩𝑨𝑪 – 𝑬𝑽) Or 𝑬𝑨𝑪 = 𝑩𝑨𝑪 − 𝑪𝑽 Considering SPI and CPI (when variances are regular/typical) – 𝑬𝑨𝑪 = 𝑨𝑪 + (𝑩𝑨𝑪 − 𝑬𝑽) (𝑺𝑷𝑰 ∗ 𝑪𝑷𝑰) New rate or the original rate was fundamentally flawed – EAC = AC + New Estimate ETC (Estimate to Complete) Estimates the additional cost needed for the project finish. ETC = EAC – AC VAC (Variance at Completion) Estimates the difference between EAC and original planned value. VAC = BAC – EAC TCPI (To-Complete Performance Index) Ratio estimates efficiency needed to finish the project on budget. Higher value means stricter cost management. Budget-based (when we need project to get back to budget) – 𝑻𝑪𝑷𝑰 = (𝑩𝑨𝑪 − 𝑬𝑽) (𝑩𝑨𝑪 − 𝑨𝑪) Estimation-based (to meet the new estimate) –
  • 9. PM NOTEBOOK APPENDIX H – FORMULA SHEET | COMMUNICATION DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 8 𝑻𝑪𝑷𝑰 = (𝑩𝑨𝑪 − 𝑬𝑽) (𝑬𝑨𝑪 − 𝑨𝑪) Project Variance The final variance, which is discovered only at the project’s completion. 𝑽𝑨𝑹 = 𝑩𝑨𝑪 − 𝑨𝑪 Communication Lines/Channels of Communication # Lines for n People = n ∗ (n − 1) 2 Risk Management Expected Monetary Value (EMV) EVM lets you examine costs of all the paths you might take through the project and assign monetary value to each decision. Implies decision tree analysis. 𝑬𝒙$𝑽 = ∑ 𝑽𝒊 𝑷𝒊 𝒏 𝒊=𝟏 Vi = The monetary value of event i. Pi = Probability of occurrence of event i. Procurements Make-or-Buy Analysis The following formula can be used to get how long will it take for the lease cost to be the same as the purchase cost. 𝒎𝒐𝒏𝒕𝒉 𝒄𝒐𝒖𝒏𝒕 = 𝒂𝒃𝒔( 𝒃𝒖𝒊𝒍𝒅 𝒄𝒐𝒔𝒕𝒔 − 𝒃𝒖𝒚 𝒄𝒐𝒔𝒕𝒔 𝒃𝒖𝒊𝒍𝒅 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 − 𝒃𝒖𝒚 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 ) Same formula can be represented in another way – 𝒃𝒖𝒊𝒍𝒅 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 ∗ 𝒎𝒕𝒉 𝒄𝒏𝒕 = 𝒃𝒖𝒚 𝒄𝒐𝒔𝒕𝒔 + 𝒃𝒖𝒚 𝒎𝒕𝒉𝒍𝒚 𝒇𝒆𝒆𝒔 ∗ 𝒎𝒕𝒉 𝒄𝒏𝒕 Point of Total Assumption (PTA) PTA is the point on the cost line of profit-cost curve determined by contract elements associated with a fixed price incentive contract, above which the seller effectively bears all the costs of a cost overrun. 𝑷𝑻𝑨 = (𝑪𝒆𝒊𝒍𝒊𝒏𝒈 𝑷𝒓𝒊𝒄𝒆 − 𝑻𝒂𝒓𝒈𝒆𝒕 𝑷𝒓𝒊𝒄𝒆) 𝑩𝒖𝒚𝒆𝒓′ 𝒔 𝑺𝒉𝒂𝒓𝒆 𝑹𝒂𝒕𝒊𝒐 + 𝑻𝒂𝒓𝒈𝒆𝒕 𝑪𝒐𝒔𝒕
  • 10. PM NOTEBOOK APPENDIX H – FORMULA SHEET | ESTIMATES DISCLAIMER: THE MATERIAL INCLUDED IN THIS DOCUMENT IS BASED ON DATA / INFORMATION GATHERED FROM VARIOUS RELIABLE SOURCES. NONE OF THIS DATA / INFORMATION IS A PROPERTY OF THE AUTHOR. 9 Estimates Simple/Triangular Distribution ESA = (O + P + M) 3 Beta/PERT Estimate Σ = (O + P + 4M) 6 Beta Standard Deviation / Sigma σ = (P − O) 6 Beta Variance VARPERT = σ2 = ( (P − O) 6 ) 2