1 Write short note on:
(a)Project deliverables: Deliverable is a term used in project management to describe a tangible or
intangible object produced as a result of the project that is intended to be delivered to a customer
(either internal or external). A deliverable could be a report, a document, a server upgrade or any other
buildingblockof anoverall
(b) Project Rating Index (PRI): The PDRI is intended to evaluate the completeness of scope definition,
specifically on industrial construction projects, at any point prior to the time a project is considered for
authorization to perform detailed design and construction. This paper will highlight the importance of
scope definition and its direct impact on project success, specifically focusing on how recent industry
trendsare changingthe traditional projectenvironment.
(d) Scope change control: A scope change is any modification to the agreed-upon project scope a
defined by the approved WBS. Scope changes often require adjustments to cost, time, quality, or other
project activities. These are fed back through the planning process, technical and planning documents
are updated as needed and stakeholders notified as appropriate.A scope change is related to cost ,time
and qualityof project.Tomake projectplanning
(d)Partnering: Partnering is described as establishing a long term win-win relationship based on mutual
trust and teamwork, and on sharing of both risks and rewards. Partnering arrangement can be between
laborand management,
2 BudgetEstimation of ABC Company Ltd.
ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather accessories. Over
the years, the company, which started out as a local firm,has made its mark as an international
corporation. However,the company is still working as a traditional set up.
The high quality and durability of products have increased the demand of the products in the market.
As the production of the organisation is being increased to meet the demand, the traditional set up is
creating hurdlesin the production process.
Organisation conflicts have arisen among the team members because of the unorganised hierarchical
structure of the company, which is affecting the output of the organisation. Now that the
management has decided to expand the business and opened up branches abroad, the company is
facing two more problems. The first problem is in budgeting as the company is unfamiliar with
international market conditions, strategy, and business policy while the second problem is conflicts at
the time of team formation due to lack of experience of and exposure to multinational work culture,
which has further affectedthe output of the company.
The company can estimate the budget through two methods, the bottom - up approach and the top -
down approach. The bottom -up approach is generally followed by the MNCs as it is more accurate
and reliable.
Mr.Parag has been appointed as the country head of the company and he has also been assigned the
responsibilityofincorporatingthe advanced projectset up in the organisation.
Questions:
Whichproject estimationapproach shouldbe usedby the company and why?
Bottom-up estimating(alsocalleddetail or resource-drivenestimating)
The estimator breaks a project into distinct line items, and then breaks those line items into smaller,
distinct line items, and so on, until he or she arrives at the component (or resource) level – the level of
detail atwhichthe price of the componentsisrelativelyconsistentacrossprojects.
Top-downestimating(also calledparametric estimating)
This approach typically relies on cost histories from past projects, and knowledge of the specific
parameters of those projects. Using the previous example, reviewing previous bridge projects to
determine that there are correlations between the cost of the bridge and key factors like size and the
primarymaterial usedgivesthe estimatorvaluable data.
In other words, all things being equal, if the new bridge is 10% larger than the previous bridge, its top-
down cost estimate might be 10% higher. While this approach can be fast, it is less likely to uncover
potential cost-eatingdangerslike challengingsiteconditionsorfluctuationsinraw material costs.
The practical reality is that both approaches are likely to be used by most companies and on most
projects. Top-down may be the only approach possible for a conceptual estimate for an early-stage
project. And even later-stage estimates might involve a mix of items, some estimated top-down and
othersbottom-up.
2. Whattype of project organisationstructure should be usedby the company and why?
Answer:
 Flat Organizational Structure: Many small companies use a flat organizational structure, where
very few levels of management separate executives from analysts, secretaries and lower-level
employees. Flat organizations work best when a company hasless than 20 employees, especially
if the companyemploysone ortwo employeesperdepartment.
 Functional Organizational Structure: A functional organizational structure is centered on job
functions, such as marketing, research and development and finance. Small companies should
use a functional
3 What is the importance of operational feasibility? Explain the factors that affect operational
feasibility.
Answer: Operational feasibility is as important as technical feasibility (or any other kind of feasibility for
that matter), and yet it can be the first thing to get brushed under the carpet. The conversation changes
and that ‘intelligent system’ everyone was discussing is transformed back into a mere ‘thing’: a
deliverable to drop into the organisation. We’ll find out later if we can make it happen; if we can weave
it intodepartmentsandheartsassuccessfullyaswe canplugit intosoftware platforms.
Working Lean means minimising waste. And operational feasibility should surely be fed into product
developmentcycleslike anyothercritical
4 Write short noteson
(a) Monte Carlo analysis: A problem solving technique used to approximate the probability of certain
outcomes by running multiple trial runs, called simulations, using random variables. Monte Carlo
simulationis
(b) Work break down structure: A work breakdown structure (WBS), in project management and
systems engineering, is a deliverable-oriented decomposition of a project into smaller components. A
work breakdown structure element may be a product, data, service, or any combination thereof. A WBS
alsoprovidesthe necessary
(c)Resource loading: Resource loading mainly involves your manpower or employees. In resource
loading, each employee is assigned a task or a percentage of a project (X percent of the whole). Usually,
it's 25 percent of the whole. Then the employee is assigned other tasks until he or she reaches 100
percentbooked.Thiswouldthenmean
(d) Definitive estimate (amethodto estimate cost of a project):
"A definitive estimate is prepared from well defined data, specifications, drawings, etc. This category
covers all estimate ranges from a minimum to maximum definitive type. These estimates are used for
bidproposals,
5 What do you understand by cost of quality? Elaborate on various types of costs of quality associated
with a project.
Answer: The term “quality costs” has different meanings to different people. Some equate “quality
costs” with the costs of poor quality due to finding and correcting defective work. Others equate the
term with the costs to attain good quality. Others use the term to mean the costs of running the quality
department.Inmysite,the term"
6 Explain some of ISO standards that should be considered by the project manager during project
execution.Listthe advantages of projectmanagement software.
Answer: Management system standards: ISO management system standards provide a model to follow
when setting up and operating a management system. Like all our standards, they are the result of
international, expert consensus and therefore offer the benefit of global management experience and
good practice. These standards can be applied to any organisation, large or small, whatever the product
or service andregardlessof the sectorof activity.
Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601

More Related Content

DOCX
Pm0011 project planning and scheduling
DOCX
Pm0011 project planning and scheduling
DOCX
Pm0011 project planning and scheduling
DOCX
Pm0011 project planning and scheduling
DOCX
Project management 3rd sem - smu mba solved assignments
DOC
CMMI Implementation Guide
DOCX
Presentation by dhruba jyoti chaudhuri
DOCX
Presentation by vignesh swamidurai
Pm0011 project planning and scheduling
Pm0011 project planning and scheduling
Pm0011 project planning and scheduling
Pm0011 project planning and scheduling
Project management 3rd sem - smu mba solved assignments
CMMI Implementation Guide
Presentation by dhruba jyoti chaudhuri
Presentation by vignesh swamidurai

What's hot (19)

PDF
A review paper
DOCX
Essay questions
PDF
House of Quality in Total Quality Management
DOCX
Smu mba sem 3 pm spring 2015 assignments
DOC
Evolve methodology
DOCX
Smu mba sem 3 pm summer 2015 assignments
PPT
Sukhchan Alliance Llc Cmmi
PDF
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
PDF
Process architecture vs modeling
PDF
How to Increase the Value of the PMMMs as a Business-oriented Framework
DOCX
Running head critical path method1 critical path method7critic
PDF
Governance of mega and giga programs
PDF
Understanding transition performance during offshore IT outsourcing
PPTX
Contract review
PDF
TQM-diagram house of quality
PDF
Qfd dfss
DOCX
Project managment (pm) solved assignments summer 2015
PDF
Microsoft Abbreviations Dictionary
A review paper
Essay questions
House of Quality in Total Quality Management
Smu mba sem 3 pm spring 2015 assignments
Evolve methodology
Smu mba sem 3 pm summer 2015 assignments
Sukhchan Alliance Llc Cmmi
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
Process architecture vs modeling
How to Increase the Value of the PMMMs as a Business-oriented Framework
Running head critical path method1 critical path method7critic
Governance of mega and giga programs
Understanding transition performance during offshore IT outsourcing
Contract review
TQM-diagram house of quality
Qfd dfss
Project managment (pm) solved assignments summer 2015
Microsoft Abbreviations Dictionary
Ad

Similar to Pm0011 project planning and scheduling (20)

DOCX
Pm0011 project planning and scheduling
DOCX
Pm0011 project planning and scheduling
DOCX
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
PDF
Asset Finance Systems: Project Initiation "101"
PDF
Asset Finance Systems: Project Initiation "101"
DOCX
Pm0011 project planning and scheduling
PDF
How to Reach Peak Performance With the Product Management Organizational Heal...
DOCX
MBA 6951, Managing Complex Projects 1 Course Learning.docx
DOCX
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
DOCX
Pm0010 – interduction to project management
PPT
Week9 Define And Document Business Problems
DOCX
Pm0015 quantitative methods in project management
DOCX
Pm0011 project planning and scheduling
DOCX
The Retail Store Where convenience, quali.docx
DOCX
Business Case Templatewww.ProjectManagementDocs.comBusines.docx
DOCX
Business Case Templatewww.ProjectManagementDocs.comBusines.docx
DOC
Chandrashekhar resume
PDF
Project Planning, Execution And Closure Essay
DOCX
Pm0011 – project planning and scheduling
PPTX
Why do the Projects fail
Pm0011 project planning and scheduling
Pm0011 project planning and scheduling
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
Pm0011 project planning and scheduling
How to Reach Peak Performance With the Product Management Organizational Heal...
MBA 6951, Managing Complex Projects 1 Course Learning.docx
Assignment 1AgileProjectCharterTemplateExample.pdfC Examp.docx
Pm0010 – interduction to project management
Week9 Define And Document Business Problems
Pm0015 quantitative methods in project management
Pm0011 project planning and scheduling
The Retail Store Where convenience, quali.docx
Business Case Templatewww.ProjectManagementDocs.comBusines.docx
Business Case Templatewww.ProjectManagementDocs.comBusines.docx
Chandrashekhar resume
Project Planning, Execution And Closure Essay
Pm0011 – project planning and scheduling
Why do the Projects fail
Ad

Pm0011 project planning and scheduling

  • 1. Dear students get fully solved assignments Send your semester & Specialization name to our mail id : “ help.mbaassignments@gmail.com ” or Call us at : 08263069601 Assignment DRIVE FALL 2014 PROGRAM MBADS (SEM 3/SEM 5) MBAFLEX/ MBA (SEM3) PGDPMN(SEM 1) SUBJECT CODE & NAME PM0011 – PROJECT PLANNING ANDSCHEDULING BK ID B1937 CREDIT & MARKS 4 CREDITS & 60 MARKS 1 Write short note on: (a)Project deliverables: Deliverable is a term used in project management to describe a tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a server upgrade or any other buildingblockof anoverall (b) Project Rating Index (PRI): The PDRI is intended to evaluate the completeness of scope definition, specifically on industrial construction projects, at any point prior to the time a project is considered for authorization to perform detailed design and construction. This paper will highlight the importance of scope definition and its direct impact on project success, specifically focusing on how recent industry trendsare changingthe traditional projectenvironment. (d) Scope change control: A scope change is any modification to the agreed-upon project scope a defined by the approved WBS. Scope changes often require adjustments to cost, time, quality, or other project activities. These are fed back through the planning process, technical and planning documents are updated as needed and stakeholders notified as appropriate.A scope change is related to cost ,time and qualityof project.Tomake projectplanning
  • 2. (d)Partnering: Partnering is described as establishing a long term win-win relationship based on mutual trust and teamwork, and on sharing of both risks and rewards. Partnering arrangement can be between laborand management, 2 BudgetEstimation of ABC Company Ltd. ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather accessories. Over the years, the company, which started out as a local firm,has made its mark as an international corporation. However,the company is still working as a traditional set up. The high quality and durability of products have increased the demand of the products in the market. As the production of the organisation is being increased to meet the demand, the traditional set up is creating hurdlesin the production process. Organisation conflicts have arisen among the team members because of the unorganised hierarchical structure of the company, which is affecting the output of the organisation. Now that the management has decided to expand the business and opened up branches abroad, the company is facing two more problems. The first problem is in budgeting as the company is unfamiliar with international market conditions, strategy, and business policy while the second problem is conflicts at the time of team formation due to lack of experience of and exposure to multinational work culture, which has further affectedthe output of the company. The company can estimate the budget through two methods, the bottom - up approach and the top - down approach. The bottom -up approach is generally followed by the MNCs as it is more accurate and reliable. Mr.Parag has been appointed as the country head of the company and he has also been assigned the responsibilityofincorporatingthe advanced projectset up in the organisation. Questions: Whichproject estimationapproach shouldbe usedby the company and why? Bottom-up estimating(alsocalleddetail or resource-drivenestimating) The estimator breaks a project into distinct line items, and then breaks those line items into smaller, distinct line items, and so on, until he or she arrives at the component (or resource) level – the level of detail atwhichthe price of the componentsisrelativelyconsistentacrossprojects. Top-downestimating(also calledparametric estimating) This approach typically relies on cost histories from past projects, and knowledge of the specific parameters of those projects. Using the previous example, reviewing previous bridge projects to determine that there are correlations between the cost of the bridge and key factors like size and the primarymaterial usedgivesthe estimatorvaluable data.
  • 3. In other words, all things being equal, if the new bridge is 10% larger than the previous bridge, its top- down cost estimate might be 10% higher. While this approach can be fast, it is less likely to uncover potential cost-eatingdangerslike challengingsiteconditionsorfluctuationsinraw material costs. The practical reality is that both approaches are likely to be used by most companies and on most projects. Top-down may be the only approach possible for a conceptual estimate for an early-stage project. And even later-stage estimates might involve a mix of items, some estimated top-down and othersbottom-up. 2. Whattype of project organisationstructure should be usedby the company and why? Answer:  Flat Organizational Structure: Many small companies use a flat organizational structure, where very few levels of management separate executives from analysts, secretaries and lower-level employees. Flat organizations work best when a company hasless than 20 employees, especially if the companyemploysone ortwo employeesperdepartment.  Functional Organizational Structure: A functional organizational structure is centered on job functions, such as marketing, research and development and finance. Small companies should use a functional 3 What is the importance of operational feasibility? Explain the factors that affect operational feasibility. Answer: Operational feasibility is as important as technical feasibility (or any other kind of feasibility for that matter), and yet it can be the first thing to get brushed under the carpet. The conversation changes and that ‘intelligent system’ everyone was discussing is transformed back into a mere ‘thing’: a deliverable to drop into the organisation. We’ll find out later if we can make it happen; if we can weave it intodepartmentsandheartsassuccessfullyaswe canplugit intosoftware platforms. Working Lean means minimising waste. And operational feasibility should surely be fed into product developmentcycleslike anyothercritical 4 Write short noteson (a) Monte Carlo analysis: A problem solving technique used to approximate the probability of certain outcomes by running multiple trial runs, called simulations, using random variables. Monte Carlo simulationis (b) Work break down structure: A work breakdown structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components. A work breakdown structure element may be a product, data, service, or any combination thereof. A WBS alsoprovidesthe necessary
  • 4. (c)Resource loading: Resource loading mainly involves your manpower or employees. In resource loading, each employee is assigned a task or a percentage of a project (X percent of the whole). Usually, it's 25 percent of the whole. Then the employee is assigned other tasks until he or she reaches 100 percentbooked.Thiswouldthenmean (d) Definitive estimate (amethodto estimate cost of a project): "A definitive estimate is prepared from well defined data, specifications, drawings, etc. This category covers all estimate ranges from a minimum to maximum definitive type. These estimates are used for bidproposals, 5 What do you understand by cost of quality? Elaborate on various types of costs of quality associated with a project. Answer: The term “quality costs” has different meanings to different people. Some equate “quality costs” with the costs of poor quality due to finding and correcting defective work. Others equate the term with the costs to attain good quality. Others use the term to mean the costs of running the quality department.Inmysite,the term" 6 Explain some of ISO standards that should be considered by the project manager during project execution.Listthe advantages of projectmanagement software. Answer: Management system standards: ISO management system standards provide a model to follow when setting up and operating a management system. Like all our standards, they are the result of international, expert consensus and therefore offer the benefit of global management experience and good practice. These standards can be applied to any organisation, large or small, whatever the product or service andregardlessof the sectorof activity. Dear students get fully solved assignments Send your semester & Specialization name to our mail id : “ help.mbaassignments@gmail.com ” or
  • 5. Call us at : 08263069601