Practical project risk assessment
APM Aberdeen
Robert Gordon University, Aberdeen
10th March 2015
Simon White
Consultant, Trigo White Ltd
+44 (0)7831 791 032
simon@trigowhite.com
Trigo White LtdRisk Management www.trigowhite.com
Risk management services
• Risk Management Plan development
• Risk workshop facilitation
• Qualitative risk assessment and analysis
• Risk register review
• Risk process design / review / implementation / audit
• Quantitative risk assessment and analysis
• Industry best practice
• Over 20 years’ consulting to a wide variety of industries
• Add value with risk management
Trigo White LtdRisk Management www.trigowhite.com
The risk workshop
• Valuable discussion: assumptions, inter-discipline issues, allows honesty
• Structured approach, best practice
• Engage project team, management and stakeholders
• Skilled facilitation, ensuring contribution from all team members, keeping focus
• Identify, discuss and qualify risks
– Cause, risk, effect
– Probability (H / M / L …)
– Impact on schedule, cost and safety, production, operations (H / M / L …)
• Capture mitigation options and fallback options
• Effect of mitigation
• Agree action owners and deadlines
• Make decisions – is it worth mitigating?
Probability Impact Score
Major scope change M VH 25
SIMOPS issues H L 17
DECC requires recycle L H 15
Delay to lift vessel arrival L M 9
… …
Trigo White LtdRisk Management www.trigowhite.com
The risk workshop
• Risks can be ranked and summarised
• Give focus on mitigation
• Establish agreement
• Demonstrate robustness
• What are our top risks? VH
Major
scope
change
H
DECC
requires
recycle
M
Delay to
lift vessel
arrival
L
SIMOPS
issues
L M H VH
Probability
Impact
Trigo White LtdRisk Management www.trigowhite.com
The risk register
• A useful live project document
• Prioritise, categorise risks
• Ranking, reporting of key risks
• Focus risk mitigation
• Track mitigation actions – progress and effectiveness
• Keep risk visible throughout planning and execution
• Risk analysis adds more value …
Trigo White LtdRisk Management www.trigowhite.com
Inputs for a risk analysis
• Base schedule (WBS)
– Around 50-300 activities
– “Forward-driven” logic
– Can use existing schedule, or create in a workshop
• Base cost estimate (CBS)
– Around 20-50 high-level cost elements
– Allowances / contingency identified
• Any risks already identified
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk assessment
• Quantify significant risks
– Probability (%)
– Schedule impact in days: P10, P50 and P90 (if it occurs)
– Cost impact in £: P10, P50 and P90 (if it occurs)
• Associate the risks with the schedule activities (WBS)
– E.g. “Delay to lift vessel arrival” will impact installation activities
• Associate the risks with the cost elements (CBS)
– E.g. “Delay to lift vessel arrival” will impact topsides cost
(optional)
Trigo White LtdRisk Management www.trigowhite.com
3 4 5 6 7 8 9 10 11 12
Probabilitydensity
Activity cost (MM USD)
P10 P50 P90
Quantitative risk assessment
• Further quantitative assessments
– Schedule variance (-10% / +30% for engineering activities)
– Cost variance (-5% / +10% for jacket fabrication cost)
– Variance accounts for:
• Estimating uncertainty
• Risks not specifically modelled
– Correlation (topsides fabrication costs are uncertain because of common
causes)
– Series / parallel impacts (poor weather and lift vessel delay are in parallel)
Trigo White LtdRisk Management www.trigowhite.com
Probabilitydensity
Total project cost (MM USD)
P10 P50 P90
23
Base = 16.4
Quantitative risk analysis
• The risk model shows the effect of the assumptions on the overall project
Base
estimate
(MMUSD)
Bulks 2.3
Fabrication 5.7
Transportation 1.9
Heavy lift vessel 1.6
Hook-up and
commissioning
4.3
Project services 0.6
Total 16.4
The P90 is a
"reasonably likely"
worst case.
Contingency at P90 = 6.6
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can be shown (on average) against the individual
costs
0
10
20
Bulks
Fabrication
Transportation
Heavyliftvessel
Hook-upand
commissioning
Projectservices
Total
P90 contingency:
Total base cost:
6.6
16.4
23.0Total P90 cost:
MMUSD
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can also be shown against different types of risk
0
10
20 Basecost
Technicalrisk
Non-technicalrisk
Total
P90 contingency:
Total base cost:
6.6
16.4
23.0Total P90 cost:
MMUSD
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk analysis
• The model shows the effect of the risk on schedule as well as cost
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk analysis
• The contribution of risks to the overall project cost or schedule can be
calculated
-1 -0.5 0 0.5 1 1.5
Variance of labour costs
Impact of SIMOPS issues
Impact of delay to lift vessel arrival
Variance of offshore labour rate
Variance of transportation rate
Impact of flotel unavailability
Impact of poor weather
MM USD
Contribution to P10 / P90
cost contingency
Contribution to P50
cost contingency
Trigo White LtdRisk Management www.trigowhite.com
Quantitative risk analysis
• The total contingency can be shown (on average) phased over time
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Jan-11
Jul-11
Jan-12
Jul-12
Jan-13
Jul-13
Jan-14
Jul-14
Jan-15
Jul-15
Jan-16
Jul-16
Jan-17
Jul-17
Jan-18
Jul-18
Jan-19
Monthlycost(MMUSD)
Base phasing
P10 phasing
P50 phasing
P90 phasing
Trigo White LtdRisk Management www.trigowhite.com
All this can be …
• Practical
• Defendable
• Valuable
Trigo White LtdRisk Management www.trigowhite.com
An example
• Offshore natural gas development
• Schedule: many assumptions, critical path, burn rates, weather
• Cost: management and partners require confidence, justification of
contingency, basis for decisions
• Production: delays hurt NPV
• Operability: shutdowns hurt NPV
• Busy multi-discipline team
• Busy project manager
• Need a meaningful risk report
Trigo White LtdRisk Management www.trigowhite.com
Full risk report
Trigo White LtdRisk Management www.trigowhite.com
Full risk report
• Documents risk identification and assessment process
• Shows who contributed to the process
• Includes risk register and all other assumptions
• Shows the model logic
• Gives full results
– Overall contingency on cost and schedule, with justification
– Breakdown of contingency by WBS, CBS and by risk
– Effect of mitigation
• Forms a permanent record of the team’s view of the risk to the project, at a
given point in time
• Refresh / update at each stage gate
Trigo White LtdRisk Management www.trigowhite.com
Benefits of risk analysis
• A valuable process
– Challenge project teams and base estimates
– Express uncertainty in the team’s base assumptions
– Capture risks, assumptions, issues, and their consequences
– Encourage open discussion amongst integrated team
• Demonstrate awareness of risk
– Agree and communicate the team’s view of the risk
– Justify contingency and mitigation efforts
– Allow challenges, discussion and negotiation
– Set realistic stakeholder expectations
• The risk model represents the perceived risk, and its logical
consequences
Trigo White LtdRisk Management www.trigowhite.com
About Simon White
• Over 20 years’ experience in risk management and risk analysis
– Wide variety of industries and major projects
– Three years as UK Risk Analyst for ConocoPhillips
– Previously Senior Risk Management Consultant and trainer for Pertmaster, Primavera and
Oracle
– Risk analyst for current major oil / gas projects such as Cygnus, Clair Ridge and Jasmine,
and a major government infrastructure programme
• Recognised as one of the leading practitioners of integrated project schedule and cost
risk management and analysis
– Methods allow project risk models to be interrogated and understood by project teams and
senior management
– Designed and built commercial risk software: Predict!, Arrisca, and a contributing architect to
Primavera Risk Analysis (Pertmaster)
– Develops tools for more practical and valuable project and business risk management.
Trigo White LtdRisk Management www.trigowhite.com
Questions?
Simon White
Consultant
Trigo White Ltd – Risk Management
+44 (0)7831 791 032
simon@trigowhite.com

More Related Content

PDF
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
PPTX
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
PPT
London 2012 Olympics, Managing and controlling contingency
PPT
Building business continuity through risk management, presented by Kimberley ...
PPT
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
PDF
Calculating contingency for management reserve
PDF
The importance of properly describing risks, presented by Peter Simon, 10th O...
PDF
Basic risk management presentation 17th june 2015
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
London 2012 Olympics, Managing and controlling contingency
Building business continuity through risk management, presented by Kimberley ...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Calculating contingency for management reserve
The importance of properly describing risks, presented by Peter Simon, 10th O...
Basic risk management presentation 17th june 2015

What's hot (20)

PPTX
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
PDF
Fujitsu’s management of contingency
PPT
NAPLIA Risk Management Presentation 2014
PDF
Enterprise risk management presentation to APM SWWE branch
PPTX
Project value risk management achieving the wow factor on your projects
PPT
Project risk analysis
PPT
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
PDF
project risk analysis
PPT
Project risk management workshops
PPTX
Project Risk Management (10)
PDF
Contingency and management reserve
PPT
Positioning project, programme and portfolio risk
PPTX
Project risk analysis
PDF
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
PPT
Quantitative Project Risk Analysis
PPTX
Analyzing And Managing Project Risk
PPTX
Derek Wright: risk v uncertainty case study
PPT
risk.ppt
PPTX
Alper Bender - Project Risk Management
PPTX
Kuala Lumpur - PMI Global Congress 2009 - Risk Management
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Fujitsu’s management of contingency
NAPLIA Risk Management Presentation 2014
Enterprise risk management presentation to APM SWWE branch
Project value risk management achieving the wow factor on your projects
Project risk analysis
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
project risk analysis
Project risk management workshops
Project Risk Management (10)
Contingency and management reserve
Positioning project, programme and portfolio risk
Project risk analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Quantitative Project Risk Analysis
Analyzing And Managing Project Risk
Derek Wright: risk v uncertainty case study
risk.ppt
Alper Bender - Project Risk Management
Kuala Lumpur - PMI Global Congress 2009 - Risk Management
Ad

Viewers also liked (20)

PDF
Promoting preventive mitigation of buildings against hurricanes
PDF
Project risk assessment presentation feb 2013
PPT
Risk Assessment Process NIST 800-30
PDF
Risk assessment principles and guidelines
PPTX
Risk assessment presentation
PPTX
Powerpoint Risk Assessment
PDF
Improved Schedule Risk Analysis through Metric Assessment
PPTX
Formal Risk Assessment Workshop
PPTX
School based mental health workshop: assessing and treating violent youth
PDF
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
PPT
PM Symposium 2009 Apply Risk Techniques on RAI Prj
PPTX
2010; Risk Management Workshop Rev.1.1
PDF
Fpso – general overview of conversion & topside process description -abstract
PPTX
Unit 11 - Final Project - Threat & Risk Assessment - Babeli
PPT
Wind provisions
PDF
Rational Design of FPSO Hulls
PDF
Maximising value to stakeholders through risk management
PDF
Lessons learned in implementing a QRA capability - Egan Naidoo
PDF
Concrete Restoration
PDF
Preventive Maintenance: Tips to Reduce Facility Costs and Breakdowns
Promoting preventive mitigation of buildings against hurricanes
Project risk assessment presentation feb 2013
Risk Assessment Process NIST 800-30
Risk assessment principles and guidelines
Risk assessment presentation
Powerpoint Risk Assessment
Improved Schedule Risk Analysis through Metric Assessment
Formal Risk Assessment Workshop
School based mental health workshop: assessing and treating violent youth
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
PM Symposium 2009 Apply Risk Techniques on RAI Prj
2010; Risk Management Workshop Rev.1.1
Fpso – general overview of conversion & topside process description -abstract
Unit 11 - Final Project - Threat & Risk Assessment - Babeli
Wind provisions
Rational Design of FPSO Hulls
Maximising value to stakeholders through risk management
Lessons learned in implementing a QRA capability - Egan Naidoo
Concrete Restoration
Preventive Maintenance: Tips to Reduce Facility Costs and Breakdowns
Ad

Similar to Practical project risk assessment, Simon White (20)

PPT
12. Project Risk Management
PPTX
SAD13 - Risk Analysis
PDF
Project Risk Management
PDF
Simon White - Where is the Risk?
PPT
Risk management - A short course
PDF
APM Thames Valley Network and The Charted Institute of Building: AI in the Pr...
DOCX
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
PPTX
اهم برزنتيشن لجنك2222
PPTX
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
PPTX
06 Crisis & Risk management
PPTX
OM Revised Final PPT presentation-2.pptx
PPT
Risk managementslides
PDF
RISK TEMPLATE FORMATE GOOD-ALIU OLAB.pdf
PDF
Managing the risk of change by "Simon White - Risk Management Consultant for ...
PDF
Risk Calculator PowerPoint Presentation Slides
PPT
Project Risk Management-Pankaj K Sinha
PPTX
Session 18 4th edition PMP
PPTX
Risk management
PDF
riskmanagement-170228074706trrrrrrrr.pdf
PDF
Project Risk Management
12. Project Risk Management
SAD13 - Risk Analysis
Project Risk Management
Simon White - Where is the Risk?
Risk management - A short course
APM Thames Valley Network and The Charted Institute of Building: AI in the Pr...
Risk and Procurement ManagementDr Paul BaguleyClass Slides.docx
اهم برزنتيشن لجنك2222
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
06 Crisis & Risk management
OM Revised Final PPT presentation-2.pptx
Risk managementslides
RISK TEMPLATE FORMATE GOOD-ALIU OLAB.pdf
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Risk Calculator PowerPoint Presentation Slides
Project Risk Management-Pankaj K Sinha
Session 18 4th edition PMP
Risk management
riskmanagement-170228074706trrrrrrrr.pdf
Project Risk Management

More from Association for Project Management (20)

PDF
How using AI in construction planning boosts efficiency and production
PDF
APM North East Network: Micro P3 Express – A framework for all small projects
PDF
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PDF
Transforming Tomorrow Managing Change in the Public Sector.pdf
PPTX
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
PPTX
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
PPTX
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
PPTX
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
PPTX
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
PPTX
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
PPTX
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
PPTX
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
PPTX
0945 APM presentation from Gabrielle Walker.pptx
PDF
How you can use behavioural insights on your projects and pitfalls to be awar...
PPTX
Sadie B Okiji - Head of projects, NHS Sussex
PPTX
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
PPTX
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
PPTX
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
PPTX
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
How using AI in construction planning boosts efficiency and production
APM North East Network: Micro P3 Express – A framework for all small projects
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Transforming Tomorrow Managing Change in the Public Sector.pdf
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
0945 APM presentation from Gabrielle Walker.pptx
How you can use behavioural insights on your projects and pitfalls to be awar...
Sadie B Okiji - Head of projects, NHS Sussex
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...

Recently uploaded (20)

PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
How to Get Approval for Business Funding
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
IFRS Notes in your pocket for study all the time
PDF
Technical Architecture - Chainsys dataZap
PDF
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
PDF
Comments on Crystal Cloud and Energy Star.pdf
PDF
Cours de Système d'information about ERP.pdf
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PDF
Booking.com The Global AI Sentiment Report 2025
PDF
Tata consultancy services case study shri Sharda college, basrur
PDF
Blood Collected straight from the donor into a blood bag and mixed with an an...
PDF
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
PDF
1911 Gold Corporate Presentation Aug 2025.pdf
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PPTX
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
PDF
How to Get Business Funding for Small Business Fast
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
How to Get Approval for Business Funding
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
IFRS Notes in your pocket for study all the time
Technical Architecture - Chainsys dataZap
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
Comments on Crystal Cloud and Energy Star.pdf
Cours de Système d'information about ERP.pdf
Module 2 - Modern Supervison Challenges - Student Resource.pdf
Booking.com The Global AI Sentiment Report 2025
Tata consultancy services case study shri Sharda college, basrur
Blood Collected straight from the donor into a blood bag and mixed with an an...
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Outsourced Audit & Assurance in USA Why Globus Finanza is Your Trusted Choice
1911 Gold Corporate Presentation Aug 2025.pdf
Lecture 3344;;,,(,(((((((((((((((((((((((
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
How to Get Business Funding for Small Business Fast

Practical project risk assessment, Simon White

  • 1. Trigo White LtdRisk Management www.trigowhite.com Practical project risk assessment APM Aberdeen Robert Gordon University, Aberdeen 10th March 2015 Simon White Consultant, Trigo White Ltd +44 (0)7831 791 032 simon@trigowhite.com
  • 2. Trigo White LtdRisk Management www.trigowhite.com Risk management services • Risk Management Plan development • Risk workshop facilitation • Qualitative risk assessment and analysis • Risk register review • Risk process design / review / implementation / audit • Quantitative risk assessment and analysis • Industry best practice • Over 20 years’ consulting to a wide variety of industries • Add value with risk management
  • 3. Trigo White LtdRisk Management www.trigowhite.com The risk workshop • Valuable discussion: assumptions, inter-discipline issues, allows honesty • Structured approach, best practice • Engage project team, management and stakeholders • Skilled facilitation, ensuring contribution from all team members, keeping focus • Identify, discuss and qualify risks – Cause, risk, effect – Probability (H / M / L …) – Impact on schedule, cost and safety, production, operations (H / M / L …) • Capture mitigation options and fallback options • Effect of mitigation • Agree action owners and deadlines • Make decisions – is it worth mitigating? Probability Impact Score Major scope change M VH 25 SIMOPS issues H L 17 DECC requires recycle L H 15 Delay to lift vessel arrival L M 9 … …
  • 4. Trigo White LtdRisk Management www.trigowhite.com The risk workshop • Risks can be ranked and summarised • Give focus on mitigation • Establish agreement • Demonstrate robustness • What are our top risks? VH Major scope change H DECC requires recycle M Delay to lift vessel arrival L SIMOPS issues L M H VH Probability Impact
  • 5. Trigo White LtdRisk Management www.trigowhite.com The risk register • A useful live project document • Prioritise, categorise risks • Ranking, reporting of key risks • Focus risk mitigation • Track mitigation actions – progress and effectiveness • Keep risk visible throughout planning and execution • Risk analysis adds more value …
  • 6. Trigo White LtdRisk Management www.trigowhite.com Inputs for a risk analysis • Base schedule (WBS) – Around 50-300 activities – “Forward-driven” logic – Can use existing schedule, or create in a workshop • Base cost estimate (CBS) – Around 20-50 high-level cost elements – Allowances / contingency identified • Any risks already identified
  • 7. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk assessment • Quantify significant risks – Probability (%) – Schedule impact in days: P10, P50 and P90 (if it occurs) – Cost impact in £: P10, P50 and P90 (if it occurs) • Associate the risks with the schedule activities (WBS) – E.g. “Delay to lift vessel arrival” will impact installation activities • Associate the risks with the cost elements (CBS) – E.g. “Delay to lift vessel arrival” will impact topsides cost (optional)
  • 8. Trigo White LtdRisk Management www.trigowhite.com 3 4 5 6 7 8 9 10 11 12 Probabilitydensity Activity cost (MM USD) P10 P50 P90 Quantitative risk assessment • Further quantitative assessments – Schedule variance (-10% / +30% for engineering activities) – Cost variance (-5% / +10% for jacket fabrication cost) – Variance accounts for: • Estimating uncertainty • Risks not specifically modelled – Correlation (topsides fabrication costs are uncertain because of common causes) – Series / parallel impacts (poor weather and lift vessel delay are in parallel)
  • 9. Trigo White LtdRisk Management www.trigowhite.com Probabilitydensity Total project cost (MM USD) P10 P50 P90 23 Base = 16.4 Quantitative risk analysis • The risk model shows the effect of the assumptions on the overall project Base estimate (MMUSD) Bulks 2.3 Fabrication 5.7 Transportation 1.9 Heavy lift vessel 1.6 Hook-up and commissioning 4.3 Project services 0.6 Total 16.4 The P90 is a "reasonably likely" worst case. Contingency at P90 = 6.6
  • 10. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk analysis • The total contingency can be shown (on average) against the individual costs 0 10 20 Bulks Fabrication Transportation Heavyliftvessel Hook-upand commissioning Projectservices Total P90 contingency: Total base cost: 6.6 16.4 23.0Total P90 cost: MMUSD
  • 11. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk analysis • The total contingency can also be shown against different types of risk 0 10 20 Basecost Technicalrisk Non-technicalrisk Total P90 contingency: Total base cost: 6.6 16.4 23.0Total P90 cost: MMUSD
  • 12. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk analysis • The model shows the effect of the risk on schedule as well as cost
  • 13. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk analysis • The contribution of risks to the overall project cost or schedule can be calculated -1 -0.5 0 0.5 1 1.5 Variance of labour costs Impact of SIMOPS issues Impact of delay to lift vessel arrival Variance of offshore labour rate Variance of transportation rate Impact of flotel unavailability Impact of poor weather MM USD Contribution to P10 / P90 cost contingency Contribution to P50 cost contingency
  • 14. Trigo White LtdRisk Management www.trigowhite.com Quantitative risk analysis • The total contingency can be shown (on average) phased over time 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 Jan-11 Jul-11 Jan-12 Jul-12 Jan-13 Jul-13 Jan-14 Jul-14 Jan-15 Jul-15 Jan-16 Jul-16 Jan-17 Jul-17 Jan-18 Jul-18 Jan-19 Monthlycost(MMUSD) Base phasing P10 phasing P50 phasing P90 phasing
  • 15. Trigo White LtdRisk Management www.trigowhite.com All this can be … • Practical • Defendable • Valuable
  • 16. Trigo White LtdRisk Management www.trigowhite.com An example • Offshore natural gas development • Schedule: many assumptions, critical path, burn rates, weather • Cost: management and partners require confidence, justification of contingency, basis for decisions • Production: delays hurt NPV • Operability: shutdowns hurt NPV • Busy multi-discipline team • Busy project manager • Need a meaningful risk report
  • 17. Trigo White LtdRisk Management www.trigowhite.com Full risk report
  • 18. Trigo White LtdRisk Management www.trigowhite.com Full risk report • Documents risk identification and assessment process • Shows who contributed to the process • Includes risk register and all other assumptions • Shows the model logic • Gives full results – Overall contingency on cost and schedule, with justification – Breakdown of contingency by WBS, CBS and by risk – Effect of mitigation • Forms a permanent record of the team’s view of the risk to the project, at a given point in time • Refresh / update at each stage gate
  • 19. Trigo White LtdRisk Management www.trigowhite.com Benefits of risk analysis • A valuable process – Challenge project teams and base estimates – Express uncertainty in the team’s base assumptions – Capture risks, assumptions, issues, and their consequences – Encourage open discussion amongst integrated team • Demonstrate awareness of risk – Agree and communicate the team’s view of the risk – Justify contingency and mitigation efforts – Allow challenges, discussion and negotiation – Set realistic stakeholder expectations • The risk model represents the perceived risk, and its logical consequences
  • 20. Trigo White LtdRisk Management www.trigowhite.com About Simon White • Over 20 years’ experience in risk management and risk analysis – Wide variety of industries and major projects – Three years as UK Risk Analyst for ConocoPhillips – Previously Senior Risk Management Consultant and trainer for Pertmaster, Primavera and Oracle – Risk analyst for current major oil / gas projects such as Cygnus, Clair Ridge and Jasmine, and a major government infrastructure programme • Recognised as one of the leading practitioners of integrated project schedule and cost risk management and analysis – Methods allow project risk models to be interrogated and understood by project teams and senior management – Designed and built commercial risk software: Predict!, Arrisca, and a contributing architect to Primavera Risk Analysis (Pertmaster) – Develops tools for more practical and valuable project and business risk management.
  • 21. Trigo White LtdRisk Management www.trigowhite.com Questions? Simon White Consultant Trigo White Ltd – Risk Management +44 (0)7831 791 032 simon@trigowhite.com